Appendix 1: Regulatory & Regeneration Delivery Plan 2022/23 - Interim Progress
Our communities
Our residents health and wellbeing remains a priority
Action Status Progress Due Date Note Owner
Conduct property inspections of host
properties identified through the Super
Sponsor Scheme (Homes for Ukraine)
31-Mar-2023
45 inspections undertaken. 41 properties passed the physical checks and 4
failed. 29 hosts withdrew from the scheme and 22 hosts did not respond.
Two remaining milestones are on track and are due at year-end.
John Stevenson
Commence implementation of the Shaping
Places for Wellbeing pilot in Clydebank 31-Mar-2023 A steering group has been established and priorities and actions have been
identified to be taken forward in 2023/24. Pamela Clifford
Our Environment
Our resources are used in an environmentally sustainable way
Action Status Progress Due Date Note Owner
Co-ordinate, monitor and report the progress
of the Council’s Climate Change Action Plan
for 2022/23
31-Mar-2023
The Climate Change Action Plan continues to be monitored regularly and
progress reported quarterly to the Recovering & Renewal Board via the
Climate Change Action Group (CCAG). The most recent progress report
was submitted to the Recovering & Renewal Board in December 2022.
In summary, 11 actions are progressing as planned and 7 are
complete. Four PI's are currently not on track for achieving their targets.
These will continue to be monitored and reported at year-end.
Adam Armour -
Florence
Risk Description Current Assessment Target Assessment Date Reviewed Note Owner
Inability to reduce
carbon footprint in
line with targets
The risk that the Council will be unable to
achieve net zero emissions by 2045, both
in relation to mitigating carbon emissions
and adapting to the impacts of climate
change. Net zero refers to achieving an
overall balance between emissions
produced and emissions taken out of the
atmosphere. This target has been
developed in a way that mirrors the
emission reduction trajectory set by the
05-Oct-2022
The Council’s carbon footprint for 2021/22
is 24,022 tonnes of CO2e against a target of
22,803.  This means we have increased our
carbon emissions by 1.2% rather than
reduced them by 3.5% over the previous
financial year. Challenges related to the
following:
New Carbon Reduction Targets - Stricter
carbon reduction targets set by the Climate
Adam Armour -
Florence
Appendix 1

Page 2

Risk Description Current Assessment Target Assessment Date Reviewed Note Owner
Scottish Government in light of the
Climate Emergency.
Change Strategy mean that annual
reductions will be more challenging to
achieve net zero by 2045.  However, it
should be expected that there will be
fluctuations on our carbon reduction journey
towards 2045.
COVID 19 Pandemic - The pandemic had an
unprecedented impact on our Council
operations and residents.  More staff work
remotely and as a result we have had to
add carbon emissions from homeworking to
the Council’s overall carbon footprint.
Emissions relating to energy, waste and
travel have also increased because, like the
whole world, West Dunbartonshire is
‘bouncing back’ from the pandemic.
Waste Streams – Waste and recycling make
up almost 52% of the Council’s carbon
footprint.  Waste levels, particularly from
residents, have been increasing since
2012/13, with the highest recorded
emissions occurring in 2021/22.  Since
waste is the largest proportion of Council
emissions, improvements to emissions from
other sources do not have as much of an
impact on our carbon footprint.
Heating – Heating makes up about 20% of
the Council’s carbon footprint.  Whilst
carbon emissions for heating have
decreased slightly, the benefits of our
energy efficiency interventions have been
impacted by ventilation requirements in
schools as a result of the pandemic.
Heating will work harder and go on for
longer as a result of windows and doors
having to be open across all of our schools.

Page 3

Our neighbourhoods are sustainable and attractive
Action Status Progress Due Date Note Owner
Provide further legal and planning support to
the delivery of the new affordable housing
programme
31-Mar-2023 Ongoing support has been provided for the More Homes programme. Alan Douglas
Promote the next phase of Queens Quay
Housing 31-Mar-2023
Regular meetings are taking place with the owner and development agent
of the site to discuss the next housing phase for Queens Quay. The Council
are investigating ways of supporting the provision and implementation of
further housing on Queens Quay.
Pamela Clifford;
Gillian
McNamara
Our Economy
Our area has the infrastructure for sustainable and inclusive growth where businesses can flourish
Action Status Progress Due Date Note Owner
Deliver key regeneration sites across West
Dunbartonshire 31-Mar-2023
• Exxon site - Council (in August 2022) and Glasgow City Region (in
November 2022) agreed to defer the Final Business Case that unlocks
capital funding for the infrastructure at the Exxon site until June 2023.
• Carless site - Officers are working with the Malin Group to progress
the Scottish Marine Technology Park at Carless. Malin Group are
creating flood storage to enable development and working towards
submitting a planning application in early 2023.
• Lomondgate site - Strathleven Regen Community Interest Company
are negotiating the sale of the final sites for development at
Lomondgate and considering options for a successor company.
Gillian
McNamara
Explore commercial opportunities in our town
centres and wider regeneration sites 31-Mar-2023
• A funding application was submitted to the Scottish Government's
Green Growth Accelerator fund in early December to expand the
infrastructure and capacity of the District Heating Network.
• Progressing the first phase of the Artizan redevelopment. Early
intervention works were approved by IRED in September 2022 with
demolition of the vacant building to the rear commencing in May
2023. A feasibility study for redevelopment is also underway.
Gillian
McNamara;
Magda Swider
Support Town Centre Recovery 31-Mar-2023
Multi-year projects include:
• first phase of Alexandria Masterplan, including Smollett Fountain
roadworks, which is now complete;
• first phase of the Clydebank Town Centre Framework, including a
Levelling Up Fund funding application for the proposed transportation
hub and planning for the development of the Playdrome site; and
Gillian
McNamara;
Magda Swider

Page 4

• agreed first stage improvement plan for the Artizan Centre, with
works soon underway.
Develop a new Economic Development
Strategy and action plan 31-Mar-2023
The Economic Development Strategy 2022/27 was approved at IRED
Committee on 2 November 2022. The supporting action plan is currently
being developed for implementation from 1 April 2023.
Gillian
McNamara;
Gillian Scholes
Ensure regeneration sites are progressed to
enable high quality development to be
achieved on the ground
31-Mar-2023
Support continues for the key regeneration to ensure that the best
development is achieved by extensive pre application discussions, the
Place and Design Panel, Elected Member Briefings and through the
planning application process and discharge of conditions.
• The Queens Quay – Clydebank Health and Care Centre has opened
and 146 flatted dwellings complete and occupied.
• Clydebank town centre – detailed pre-application discussions held
with developer of Playdrome site, with planning application submission
expected soon.
• Carless – pre-application discussions continue re submission of Malin
Group PPP application. Remediation works ongoing.
• Exxon – remediation work ongoing. Bid submitted for Vacant and
Derelict Land Improvement Programme funding for green
infrastructure elements of development.
• Dumbarton town centre – working closely with consultants on
proposals for Artizan Centre. Glencairn House planning application has
been submitted.
• Alexandria town centre – Prior approval for demolition works has been
issued and Lidl application has been submitted.
Pamela Clifford
Monitor the development of the key
regeneration sites to ensure they comply with
the approved consent
31-Mar-2023
Monitoring key regeneration sites to ensure they comply with approved
consent is ongoing in terms of Exxon, Carless/ Scottish Marine Technology
Park, Queens Quay sites and other key development sites.
Pamela Clifford
Risk Description Current Assessment Target Assessment Date Reviewed Note Owner
Affordability of the
Exxon City Deal
Project
There is a risk that the affordability of
delivering the City Deal Exxon project is
beyond the resources being made
available from Glasgow City Region City
Deal.
15-Dec-2022
Risk remains unchanged. The project board
is looking at savings options during the
design development to mitigate rising costs.
Gillian
McNamara
Failure to deliver
Queens Quay
Masterplan
Following completion of Council
investment there is a risk the housing plot
sales do not materialise in the next 3-7
years, with implications for the return on
investment and the business case for the
District Heating Network.
15-Dec-2022
Risk remains unchanged. Focus continues
on landowners securing new housing
developments for the site.
Pamela Clifford;
Gillian
McNamara

Page 5

Risk Description Current Assessment Target Assessment Date Reviewed Note Owner
Inability to meet
demands of Council
to progress
regeneration projects
within desired
timescales
The number and complexity of
regeneration projects is putting
considerable strain on the resources
available which can be exacerbated by
delays out with the control of the service
and when pinch points on different
projects occur at roughly the same time.
15-Dec-2022
Risk remains unchanged. Individual projects
continue to progress, reducing the likelihood
of undesirable outcomes
Pamela Clifford;
Alan Douglas;
Gillian
McNamara
Our Council
Our workforce is resilient and skilled where digital technology supports service delivery for our residents
Action Status Progress Due Date Note Owner
Develop and implement wellbeing, employee
engagement, equality and training plans to
enable capabilities, improved resilience and
promotion of a diverse workforce.
31-Mar-2023
Progress based on interim monitoring. The following are of note:
• Employee absence rates remain significantly lower than Council
average.
• Be-the-best conversations conducted regularly with  information
linking to improved employee engagement, recognition, personal and
professional development
Management
Team
Develop and implement employee life cycle
plans in line with the People First Strategy to
attract and retain the workforce.
31-Mar-2023
Progress based on interim monitoring. The following are of note:
• Senior Democratic services Officer recruited early to allow for
handover and e.g.  Early attendance at Council meeting.
• Officers in acting up positions have been successful in achieving
promotion within the service.
• Full participation and leadership of Project Boards ensure that our
employees’ skills are shared and they in turn benefit from the skills
and experience of others.
• Internal growth opportunities reflected in Planning and Building
Standards and Trading Standards whereby Apprentices and Trainees
have progressed to management positions.
Management
Team
Implement service review process including
role design, use of new technology and new
ways of working to add resilience, address
gaps, and establish opportunities for
efficiencies
31-Mar-2023
Progress based on interim monitoring. The following are of note:
• Fit For Future Review being implemented in Planning & Building
Standards.
• Involvement in Local and National development of Digital and Spatial
Planning.
Management
Team
Develop and implement training plans and
development opportunities to improve
capabilities and resilience within the
workforce.
31-Mar-2023
Progress based on interim monitoring. The following are of note:
• The service demonstrates well-developed leadership skills linked to
succession planning and Service Delivery Needs. Collaborative and
improved working practices.
• Participation in the 4D Quantum Programme.
Management
Team

Page 6

Action Status Progress Due Date Note Owner
Our Council is adaptable and focused on delivering best value for our residents
Action Status Progress Due Date Note Owner
Provide legal services to West Dunbartonshire
Energy LLP in relation to heat supply
agreements and network supply contracts
31-Mar-2023
Support continues to be provided to the Energy LLP.  Standard form Heat
agreements provided for domestic properties and discussions ongoing on
Commercial agreements.
Alan Douglas
Provide legal advice, guidance and support on
the emerging National Care Service 31-Mar-2023
Legal advice has been provided on the Scottish Parliament
consultation.  Advice provided on an ongoing basis to the Council and
Short Life Working Group.
Alan Douglas
Complete business case and seek Council
capital funding for IDOX Electronic Document
Management System for Planning & Business
Standards
31-Mar-2023 Meeting with ICT in January 2023 to review business case, identify project
group and seek comments before proceeding to prepare growth bid. Pamela Clifford
Implement Fit for Future improvement plan
for Building Standards 31-Mar-2023
The focus on improving customer service has been successful.  Good
progress has been made with ICT actions, with implementation of
automatic downloads and the implementation of Enterprise to follow in
2023. Work will continue on the outstanding actions of the Improvement
Plan.  In late 2022 the Scottish Government granted the verification role
to Building Standards for another 6 years.
Pamela Clifford
Designate and train service data ambassadors
for the Corporate Data Information
Management system (MAGIC) and evaluate
its use
31-Mar-2023
Training provided to Legal, Asset Management, Greenspace, Roads, Waste
Services, Communications and Consultancy Services. Training of other
services will continue.
Pamela Clifford
Complete the Rediscovering the Antonine Wall
Project and start preparation for Phase 2: Re-
imaging the Antoine Wall
31-Mar-2023
Progress continues on delivering the remaining elements of the project
and all are on target for completion by 31 March 2023. The partners are
committed to the development of the Reimagining project, with internal
WDC and all partner workshops scheduled for January 2023 to shape the
new Antonine Wall Management Plan and project ideas.
Pamela Clifford
Implement the provisions of National Planning
Framework 4 for West Dunbartonshire’s
planning policies and priorities, adopt LDP 2
and commence work on LDP3
31-Mar-2023
The Scottish Parliament have agreed NPF4 and the Scottish Ministers will
adopt and publish NPF4 on 13th February 2023  meaning that it will be a
significant material consideration in the determination of planning
applications. No final decision has been taken on adopting LDP2.
Preliminary background work has commenced on LDP3 but the relevant
Regulations and Guidance have still to be published by the Scottish
Government.
Pamela Clifford

Page 7

Action Status Progress Due Date Note Owner
Complete the co-ordination of the
refurbishment of civic areas of Clydebank
Town Hall
31-Mar-2023 The wood panelling in the Chamber and Members' Corridor has been
completed.  Awaiting estimated costs and timescales for remaining works.
George
Hawthorn
Risk Description Current Assessment Target Assessment Date Reviewed Note Owner
Failure  to monitor
and enforce
regulatory areas with
public risk
The Council fails to comply with statutory
regulatory duties in respect of
environmental health, trading standards
and licensing laws.
14-Dec-2022
While approval was granted at the Council
budget meeting on 9/3/2022 for the
recruitment of an additional two EHO posts,
both posts were recommended and
accepted as a political savings option at
Council on 21 December 2022. Any impact
will be monitored.
Annemarie
Clelland;
Michael
McDougall;
John Stevenson
Income for services
continues to be
dramatically reduced
as a result of the
COVID-19 pandemic
Relates to registration, licensing, planning
and building control which have been
impacted as a result of the COVID-19
pandemic.
14-Dec-2022
Income reduction as a result of the
economic impact of COVID remains an
issue.
Alan Douglas
Failure to adequately
respond to an
emergency situation
such as a multiple
fatality workplace
accident, outbreak of
food borne
communicable
disease, a major
public health incident
or pandemic
There is a national shortage of qualified
staff in Environmental Health, across
Scotland. This impacts on West
Dunbartonshire Council. Vacancy levels at
WDC might impact on our ability to
respond to emergencies. 
14-Dec-2022
While interim management arrangements
are still in place for the Environmental
Health (EH) Manager's post, the two EH
Officer posts agreed at the Council budget
meeting on 9/3/2022 are not to be taken
forward based on the Council decision on
savings options on 21 December 2022. Any
impact will be monitored.
John Stevenson
Inability to recruit
successfully to enable
performance to be
maintained
There is a current issue with recruitment
of qualified staff in various parts of the
service.
14-Dec-2022
The two EH Officer posts agreed at the
Council budget meeting on 9/3/2022 are
not  to be taken forward based on the
Council decision on savings options on 21
December 2022. Any impact will be
monitored.
Pamela Clifford;
John Stevenson
Our residents are engaged and empowered

Page 8

Action Status Progress Due Date Note Owner
Plan and conduct the Scottish Local
Government Elections in May 2022 31-May-2022 Elections were conducted successfully with 22 members elected to serve
on the new Council.
George
Hawthorn
Implement the action plan to set up the new
Council following the Local Government
Elections
31-Mar-2023
The action plan has been completed. All new members have received
induction training and equipment, the new committee timetable is in place
and standing orders have been reviewed.
George
Hawthorn
Plan and organise the nomination process for
Community Councils and where necessary
hold elections to identify successful
candidates
31-Dec-2022 All nomination processes have been completed; no elections were
required.
George
Hawthorn
Risk Status
Alert
Warning
OK
Action Status
In progress and on track
Completed