WEST DUNBARTONSHIRE COUNCIL
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 5
Budget Forecast
Spend
£000 £000 % £000 £000 %
Project Life Financials 30 0 0% 30 0 0%
Current Year Financials 30 0 0% 30 0 0%
Project Description
Project Manager Karen Shannon
Chief Officer Laurence Slavin
Project Lifecycle 31-Mar-23 31-Mar-23
Project Life Financials 50 43 86% 51 1 1%
Current Year Financials 7 0 0% 8 1 10%
Project Description
Project Manager Karen Shannon
Chief Officer Laurence Slavin
Project Lifecycle 31-Mar-23 31-Mar-23
Project Life Financials 40 5 12% 40 (0) 0%
Current Year Financials 35 0 0% 35 0 0%
Project Description
Project Manager Karen Shannon
Chief Officer Laurence Slavin
Project Lifecycle 30-Sep-23 30-Sep-23
Main Issues / Reason for Variance
The various claim forms and departmental reports have been reviewed and updated and the relevant online request forms were submitted to the
Digital Sub-Group to be converted to Online Achieve Forms.  The various claim forms and departmental reports have now been converted to
Online Achieve Forms and are in the process of being tested. Once complete, the supplier will take matters forward with their design team. An
anticipated timeline for completion of the project, taking into account the various stages i.e. development, testing, going live etc. will be drawn up
in conjunction with the supplier at that time.  Budget spend anticipated in 2022/23.
Mitigating Action
None required at this time.
Mitigating Action
None required at this time.
Anticipated Outcome
Upgraded version with PCI compliant telephone payment system.
Electronic Insurance System
Acquisition of a claims/incident management system supported by an electronic document management
system.
31 August 2022
Budget Details
Project Life Financials
Spend to Date Variance
Payment Card Industry Data Security Standard (PCIDSS)
Module would ensure that WDC were compliant with the current requirements of PCIDSS for card payments
without the need for numerous costly workarounds
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Budget was rephased to 2022-23 as version upgrade of the Council's cash receipting system is required beforehand and is currently underway.
Anticipated Outcome
Upgraded Electronic Insurance System.
Enhancements to Cash Receipting System
Main Issues / Reason for Variance
Budget was rephased to 2022-2023 as this is a number of mini projects and the first part is the version upgrade which is actively progressing.
After this upgrade we can move onto other enhancements which are anticipated to finish in September 2023.
Mitigating Action
None required at this time.
Anticipated Outcome
Enhancements to the cash receipting system including PCI compliant telephone payment system.
To enhance the cash receipting system in the way payments are made and allocated to back office by
increasing the level of security that is required for online payments made by customers
Planned End Date Forecast End Date
Planned End Date Forecast End Date
Appendix 6

Page 2

WEST DUNBARTONSHIRE COUNCIL
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 5
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 August 2022
Budget Details
Project Life Financials
Spend to Date Variance
Project Life Financials 60 5 8% 60 0 0%
Current Year Financials 25 0 0% 25 0 0%
Project Description
Project Manager Adrian Gray
Chief Officer Laurence Slavin
Project Lifecycle 31-Mar-22 31-Oct-22
Project Life Financials 5 0 0% 5 0 0%
Current Year Financials 5 0 0% 5 0 0%
Project Description
Project Manager Jackie Nicol Thomson
Chief Officer Laurence Slavin
Project Lifecycle 31-Mar-23 31-Mar-23
Project Life Financials 1,000 0 0% 1,000 0 0%
Current Year Financials 1,000 0 0% 1,000 0 0%
Project Description
Project Manager Gillian McNeilly
Chief Officer Laurence Slavin
Project Lifecycle 31-Mar-23 31-Mar-23
Main Issues / Reason for Variance
Delays in completion of required data cleansing prior to the upgrade have caused the start of the upgrade to be deemed too close to the financial
year end to risk disruption to preparation of the draft final accounts. The upgrade will be delayed until October 2022.
Cost of Living
To support Council and community organisations with capital costs for cost of living initiatives.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Working Group currently developing proposals for initiative.
Mitigating Action
None required
Anticipated Outcome
Initialive will assist with cost of living crisis
IFRS 16 Database
This is a system which will ensure that WDC has the correct level of information and adheres to correct
reporting of IFRS16 - Leasing. 
Planned End Date Forecast End Date
Main Issues / Reason for Variance
The purchase of software to allow new accounting treatment of leases to be appropriately reported is on track. Full spend anticipated FY
2022/2023.
Mitigating Action
None required
Anticipated Outcome
Purchase of software for accounting for leases.
Mitigating Action
None possible at this time.
Anticipated Outcome
Development of Agresso system later than originally anticipated but within original budget.
Agresso development
The purpose of this project is to carry out an upgrade of the Agresso Finance System which was last
upgraded in 2015. The requirement to upgrade is to maintain a level of support available from Unit 4 who
have advised that support for older versions of the system is being reduced.
Planned End Date Forecast End Date

Page 3

WEST DUNBARTONSHIRE COUNCIL
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 5
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 August 2022
Budget Details
Project Life Financials
Spend to Date Variance
Project Life Financials 53 13 25% 53 0 0%
Current Year Financials 33 0 0% 33 0 0%
Project Description
Project Manager Alan Douglas
Chief Officer Peter Hessett
Project Lifecycle 31-Mar-24 31-Mar-24
Project Life Financials 30 0 0% 30 0 0%
Current Year Financials 10 0 0% 10 0 0%
Project Description
Project Manager Pamela Clifford
Chief Officer Peter Hessett
Project Lifecycle 31-Mar-23 31-Mar-23
Project Life Financials 15 4 24% 15 0 0%
Current Year Financials 11 0 0% 11 0 0%
Project Description
Project Manager Stephen Daly
Chief Officer Amanda Graham
Project Lifecycle 31-Mar-23 31-Mar-23
Anticipated Outcome
Review of service requirements & telephony functionality will inform works to improve citizen experience.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Improvements to Contact Centre telephony were completed as scheduled during 2021/2022.  Further works have been scoped and agreed for
improvement to Housing telephony, benefiting both residents and the Council.  A review of the out of hours service is currently being undertaken
including work to upgrade telephony.  Any works will also incur professional fees for necessary scripting works.  We are also exploring call
recording technology across all the Contact Centre telephony.  It is anticipated these projects will be completed during the financial year
2022/2023.
Mitigating Action
None required.
Telephone System Upgrade
To improve Housing Repairs telephone platform for incoming calls, providing improved Management
Information.
Anticipated Outcome
Preservation of Historic Site.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Council's capital contribution towards the multi-partner (five local authorities and Historic Environment Scotland) Rediscovering the Antonine
Wall project will be paid by the end of the financial year.
Mitigating Action
None Required.
Re -imagine Antonine Wall 
Council's capital contribution towards the multi-partner (five local authorities and Historic Environment
Scotland) Rediscovering the Antonine Wall project which is also funded by the Heritage Lottery Fund.
Trainee solicitor in place. Budget will be fully spent.
Mitigating Action
None required at this time.
Anticipated Outcome
Solicitor support for Capital Projects, with full budget spend anticipated.
Solicitor Project Support for Capital Projects
Solicitor costs to directly support capital projects
Planned End Date Forecast End Date
Main Issues / Reason for Variance

Page 4

WEST DUNBARTONSHIRE COUNCIL
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 5
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 August 2022
Budget Details
Project Life Financials
Spend to Date Variance
Project Life Financials 421 232 55% 421 (0) 0%
Current Year Financials 91 3 3% 91 (0) 0%
Project Description
Project Manager David Main
Chief Officer Amanda Graham
Project Lifecycle 31-Mar-24 31-Mar-24
Project Life Financials 3,987 1,185 30% 4,000 13 0%
Current Year Financials 1,662 (2) 0% 1,662 0 0%
Project Description
Project Manager Sarah Christie/Michelle Lynn
Chief Officer Amanda Graham
Project Lifecycle 31-Mar-23 31-Mar-23
Project Life Financials 1,700 43 3% 1,590 (110) -6%
Current Year Financials 1,590 43 3% 1,590 0 0%
Project Description
Project Manager Michelle Lynn/ Sarah Christie
Chief Officer Amanda Graham
Project Lifecycle 31-Mar-24 31-Mar-24
Heritage Capital Fund
Heritage Capital Fund.
Main Issues / Reason for Variance
Work is underway to progress furniture replacement at Dumbarton, Duntocher and Parkhall libraries during 2022/2023.  Budget of £0.1m has
been rephased to  next financial year for Dalmuir library as work is currently scheduled for 2023/2024.
Mitigating Action
None required.
Anticipated Outcome
Project carried forward to align with Asset Management programme.
Main Issues / Reason for Variance
Project in design phase and planning application submitted August 2022.
Mitigating Action
None available at this time.
Anticipated Outcome
Re-development of Glencairn House in Dumbarton High Street to a purpose built library and museum, within budget albeit later than originally
anticipated.
Anticipated Outcome
Project to be delivered on budget and within revised timescale.
Glencairn House
Re-development of Glencairn House in Dumbarton High St to a purpose built library and museum.
Planned End Date Forecast End Date
Planned End Date Forecast End Date
None available at this time.
Transformation of Infrastructure Libraries and Museums
To improve performance and efficiency of Council's Libraries and Cultural Services.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
The original projected spend has been affected by internal and external delays due to the Covid 19 recovery, a reduction in the scope of the
Clydebank Town Hall project, a change in the delivery date for the Clydebank Museum at Clydebank Library during the contract award stage,
while the new Dalmuir Library and Gallery had to be rescheduled for approval in August 2021. Officers are now making progress to get projects
back on track, projects will still be delivered in full, and a review of optimism bias will be undertaken in the projections for 2022/23.
Mitigating Action

Page 5

WEST DUNBARTONSHIRE COUNCIL
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 5
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 August 2022
Budget Details
Project Life Financials
Spend to Date Variance
Project Life Financials 40 0 0% 40 0 0%
Current Year Financials 40 0 0% 40 0 0%
Project Description
Project Manager John Anderson
Chief Officer Amanda Graham
Project Lifecycle 31-Mar-22 31-Mar-23
Project Life Financials 1,422 422 30% 1,422 0 0%
Current Year Financials 1,422 422 30% 950 (472) -33%
Project Description
Project Manager Patricia Kerr
Chief Officer Victoria Rogers
Project Lifecycle 31-Mar-23 31-Mar-23
Project Life Financials 60 50 83% 60 0 0%
Current Year Financials 17 7 40% 17 0 0%
Project Description
Project Manager Patricia Kerr
Chief Officer Victoria Rogers
Project Lifecycle 31-Oct-22 31-Oct-22
Mitigating Action
None available at this time.
Anticipated Outcome
Technical aspect of the project is complete and WDC assisting with user testing. Delayed but on budget.
Internet of Things Asset Tracking
Asset Tracking.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Technical aspect of the project is complete and WDC are assisting with user testing. Delayed but on budget.
Anticipated Outcome
Most of capital allocated to HSCP will be used to review/replace the current case management systems and will be rephased in line with the
project plan. Supply chain delays may continue to impact delivery and spend.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Some replacement Chrome book orders have been received by schools. Uplift and disposal of old devices being scheduled. Planning for MOB
replacements to be issued to users but dependency on In Tune module of 365. Gathering inventory information for next batch of replacements.
Mitigating Action
Continue to escalate and meet framework suppliers to confirm delivery lead times.
Investigate other procurement routes as well as adjust the project scope to replace where stock allows.
ICT Modernisation
This budget is to facilitate ICT infrastructure and modernise working practices.
Mitigating Action
None required
Anticipated Outcome
New floor fitted in Alexandria Community Sports Hall.
Alexandria Community Centre Sports Hall re-flooring
Alexandria Community Centre Sports Hall re-flooring
Planned End Date Forecast End Date
Main Issues / Reason for Variance
The Alexandria Community Centre Sports Hall continues to be utilised as COVID-19 vaccine centre during 2022/23 and the work will be
postponed until the last quarter of the financial year.

Page 6

WEST DUNBARTONSHIRE COUNCIL
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 5
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 August 2022
Budget Details
Project Life Financials
Spend to Date Variance
Project Life Financials 1,297 241 19% 1,297 0 0%
Current Year Financials 1,297 241 19% 1,000 (297) -23%
Project Description
Project Manager Brian Miller/ Patricia Kerr
Chief Officer Victoria Rogers
Project Lifecycle 31-Mar-23 31-Mar-23
Project Life Financials 450 189 42% 450 0 0%
Current Year Financials 173 11 7% 150 (23) -13%
Project Description
Project Manager Dorota Piotrowicz/ Patricia Kerr
Chief Officer Victoria Rogers
Project Lifecycle 30-Sep-23 30-Sep-23
Majority of budget spent but delayed.
ICT Security & DR
The project is for the enhancement of security systems, server replacement and the update of corporate
applications to ensure compliance with 15/16 PSN requirements, to enhance the disaster recovery
capabilities of WDC.
Main Issues / Reason for Variance
Project spend relates to internal and external resources to implement new systems, processes and user training skills. Mailbox migration aspect
of the project delayed until cloud backup is implemented (procurement of backup in progress and target implementation is October 2022
following tendering committee approval). Implementation of device management functionality in 365 is on target to go live in September 2022.
Information governance work stream baseline review is complete and implementation of action plan is at planning stage. Recruitment of
resources to train end users and carry out mail migrations has started.
Mitigating Action
Continue to monitor the various work streams to accelerate aspects of the project where possible if suppliers can provide resource. Continue to
assess where a) internal skills have developed, b) external resource is needed for introducing new functionality in the future to inform future
bidding cycles and c) temporary recruitment/secondment is required.
Anticipated Outcome
Anticipated Outcome
Anticipate the majority of budget being spent this financial year but some works are planned for the last quarter of the year for Public Sector
Network (PSN) annual compliance submission.
365 Implementation
Project services to delivery Microsoft 365 Implementation including 3rd party supplier, training, technical
consultancy etc.
Planned End Date Forecast End Date
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Storage Area Network (SAN) delivered and installation planning underway. Switch replacement in schools completed during the summer break. 
Switch replacement for Church Street at planning stage as required down time. Server replacement at scoping stage.
Mitigating Action
Monitor supply chain issues. Continue tendering processes and implementation stages for each project.