Page 1

WEST DUNBARTONSHIRE COUNCIL
REVENUE BUDGETARY CONTROL 2022/2023
ANALYSIS FOR VARIANCES OVER £50,000
PERIOD END DATE
Total Budget Annual Spend RAG Status
£000 £000 £000 %
Finance 1,398 1,429 32 2% 
Service Description
Main Issues / Reason for Variance
Mitigating Action
Anticipated Outcome
Revenues & Benefits 2,103 2,147 44 2% 
Service Description
Main Issues / Reason for Variance
Mitigating Action
Anticipated Outcome
Environmental Health 699 750 51 7% 
Service Description
Main Issues / Reason for Variance
Mitigating Action
Anticipated Outcome
Planning 377 629 252 67% 
Service Description
Main Issues / Reason for Variance
Mitigating Action
Anticipated Outcome
Information Services 4,502 4,440 (62) -1% 
Service Description
Main Issues / Reason for Variance
Mitigating Action
Anticipated Outcome
This Service provides Building & Planning services
The main reason for the adverse variance is that income is lower than budgeted due to
cancelled or delayed building projects. The expected income shortfall has increased since P4
by a further £94k after a further review. This variance has been reported in previous months
but was being offset in part by savings on staff costs caused by vacancies, the staffing
vacancy savings have been removed in P5.
No action required
Overspend is anticipated
This service area provides general ICT support to the Council and also supports
transformational change and modernisation of working practices through technology
Supplies and Services is favourable due to computer licence costs projected to cost less than
budgeted.
None required at this point.
Underspend is projected.
The 3 Groups within this service (Food and Business Group, Environmental Pollution Group
and Community Health Protection Group) are responsible for all aspects of Environmental
Health work.
The main reason for the adverse variance is a reduction in expected income for pest control in
particular.
No action can be taken at this time
Overspend is anticipated
The service provided by this area deal with benefits, council tax and debt recovery.
No action is possible at this time.
Overspend is anticipated
Additional Covid-19 self-isolation grants are being paid by this service with the cost being
offset by additional funding. Vacancies being covered by overtime therefore targeted turnover
savings not being fully achieved.
The service provided by this area deals with Accountancy, Capital, Treasury, Reconciliations,
Cash Office and Municipal Bank
Main reason for adverse variance is full turnover savings are not being achieved, however this
is being offset by an increase in anticipated income.
The position continues to be monitored by management to identify any savings which may
help reduce this position
An adverse variance is likely
31 August 2022
Budget Details
Variance Analysis
Variance
Appendix 3

Page 2

Total Budget Annual Spend RAG Status
£000 £000 £000 %
Budget Details
Variance Analysis
Variance
Catering Services 4,454 4,383 (71) -2% 
Service Description
Main Issues / Reason for Variance
Mitigating Action A review of the vacancies and overtime position going forward is underway
Anticipated Outcome
Building Cleaning 1,703 1,661 (42) -2% 
Service Description
Main Issues / Reason for Variance
Mitigating Action
Anticipated Outcome
Catering Services across WDC
Overall variance is favourable due to vacancies. Increased spend negates some of the
favourable variance due to a one off charge for the early termination charges for contract for
vending machines and a higher level of overtime than predicted due to the vacancies.
Overspend is anticpated
This service provides cleaning services across all council buildings
The reason for the favourable variance is the number of ongoing vacancies
None required at present
Underspend likely