WEST DUNBARTONSHIRE COUNCIL
Report by Chief Officer – Supply, Distribution & Property
Corporate Services Committee : 2 November 2022
Subject: Supply, Distribution & Property Delivery Plan 2022/23
Corporate Procurement Unit
1 Purpose
1.1 The purpose of this report is to provide members with the Corporate
Procurement Unit priorities within the Supply Distribution & Property (SD&P)
Delivery Plan 2022/23.
2 Recommendations
2.1 It is recommended that Committee notes the contents of the Plan.
3 Background
3.1 In line with the Strategic Planning & Performance Framework, each Chief
Officer develops an annual Delivery Plan which sets out actions to help deliver
the Strategic Plan and address the performance challenges and service
priorities identified in the planning process. The Plan also provides an
overview of services and resources, including employees and budgets, sets
out the performance indicators (PIs) for monitoring progress and considers the
relevant risks.
3.2 Following the local government election in May 2022, a new five-year
Strategic Plan was developed in consultation with stakeholders and submitted
to Council for approval in October. This sets out the Council’s priorities,
objectives and key PIs, providing clear direction for the development of the
first set of annual delivery plans, of which the Supply Distribution & Property
Delivery Plan is one of eight. 
3.3 The implementation of the Corporate Procurement Unit priorities within the
SD&P Delivery Plan will be monitored by the management team with interim
progress reported to Corporate Services Committee in February 2023 and
year-end progress in May 2023.
4 Main Issues
4.1 An extract from the SD&P 2022/23 Delivery Plan is included at Appendix 1.
This sets out the achievements and challenges for Corporate Procurement
Unit over the past year, as well as the priorities for 2022/23.
4.2 They include: Continue to incorporate social benefits in the contract activity;
Implement the Fit for Future Action Plan for Procurement – P2P Phase 1;
ITEM 12

Page 2

deliver procurement savings and benefits; and refresh contract and supply
management Policy.   
5 People Implications
5.1 There are no direct people implications arising from this report.
6 Financial & Procurement Implications
6.1 There are no direct financial or procurement implications arising from this
report.
7 Risk Analysis
7.1 Failure to deliver on the actions assigned to SD&P including Corporate
Procurement Unit, may have a direct impact on the delivery of the Council’s
Strategic Plan. It is essential that remedial action is taken to ensure strategic
delivery plans achieve the commitments detailed and approved.
8 Equalities Impact Assessment
8.1 Screening and impact assessments will be carried out on specific activities as
required.
9 Consultation
9.1 The delivery plans were developed through consultation with officers from the
strategic service areas.
10 Strategic Assessment
10.1 The delivery plans set out actions to support the successful delivery of the
strategic priorities and objectives of the Council.
Chief Officer: Angela Wilson
Service Area: Supply Distribution & Property
Date:  30 September 2022
_____________________________________________________________
Person to Contact:  Karen Connelly
karen.Connelly@west-dunbarton.gov.uk
Appendices: Appendix 1: Corporate Procurement Unit Extract from the
Supply, Distribution & Property Delivery Plan 2022/23
Background Papers: Strategic Plan 2022/27 - Council, 26 October 2022

Page 3

Strategic Planning & Performance Framework 2022/27
Wards Affected: All