WEST DUNBARTONSHIRE COUNCIL Appendix 5 GENERAL SERVICES CAPITAL PROGRAMME ANALYSIS OF PROJECTS AT RED ALERT STATUS PERIOD END DATE PERIOD 3 Budget Forecast Spend £000 £000 % £000 £000 % Project Life Financials 9 0 0% 9 0 0% Current Year Financials 3 0 0% 0 (3) -100% Project Description Project Manager David Thomson Chief Officer David Thomson Project Lifecycle 31-Mar-23 31-Mar-23 Project Life Financials 0 3 0% 0 0 0% Current Year Financials 0 3 0% 3 3 0% Project Description Project Manager David Thomson Chief Officer David Thomson Project Lifecycle 31-Mar-23 31-Mar-23 Project Life Financials 33 0 0% 33 0 0% Current Year Financials 33 0 0% 0 (33) -100% Project Description Project Manager Alan Douglas Chief Officer Peter Hessett Project Lifecycle 31-Mar-24 31-Mar-24 None available at this time. Anticipated Outcome Requisition of ICT Equipment. Valuation Joint Board - ICT Refresh FY 22/23 Replacement of laptops, monitors and other ICT equipment. Planned End Date Forecast End Date Requisition ICT Equipment. Planned End Date Forecast End Date Main Issues / Reason for Variance This budget remains unspent and is likely to be carried forward into FY 23/24. Mitigating Action 30 June 2022 Budget Details Project Life Financials Spend to Date Variance Valuation Joint Board - Requisition of ICT Equipment Main Issues / Reason for Variance Replacement of laptops, monitors and other ICT equipment. No further spend anticipated. Mitigating Action None available at this time. Anticipated Outcome Replacement of laptops and ICT equipment Main Issues / Reason for Variance Budget has been rephased from 2021/22. The project could not proceed as originally planned as Officers are required to access the office and hardware the system will run on and COVID-19 restrictions have prevented this. The project will have to go back out to tender following the upgrade to Microsoft 365. The project will not be completed in this financial year. Mitigating Action Legal to discuss impact of Microsoft 365 with ICT. Anticipated Outcome Project to be completed in 2023/24. Legal Case Management System Legal Case Management System Planned End Date Forecast End Date
Page 2
WEST DUNBARTONSHIRE COUNCIL GENERAL SERVICES CAPITAL PROGRAMME ANALYSIS OF PROJECTS AT RED ALERT STATUS PERIOD END DATE PERIOD 3 Budget Forecast Spend 30 June 2022 Budget Details Project Life Financials Spend to Date Variance Project Life Financials 379 42 11% 379 (0) 0% Current Year Financials 0 0 0% 46 46 0% Project Description Project Manager Arun Menon Chief Officer Victoria Rogers Project Lifecycle 31-Mar-30 31-Mar-30 Development of Workforce Management System Project to develop the Workforce Management System. Anticipated Outcome Development of Workforce Management System. Planned End Date Forecast End Date Main Issues / Reason for Variance Annual staff cost recharge of £0.046m is expected this financial year. Mitigating Action None required.