WEST DUNBARTONSHIRE COUNCIL
Appendix 5
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT RED ALERT STATUS
PERIOD END DATE
PERIOD 3
Budget Forecast
Spend
£000 £000 % £000 £000 %
Project Life Financials 9 0 0% 9 0 0%
Current Year Financials 3 0 0% 0 (3) -100%
Project Description
Project Manager David Thomson
Chief Officer David Thomson
Project Lifecycle 31-Mar-23 31-Mar-23
Project Life Financials 0 3 0% 0 0 0%
Current Year Financials 0 3 0% 3 3 0%
Project Description
Project Manager David Thomson
Chief Officer David Thomson
Project Lifecycle 31-Mar-23 31-Mar-23
Project Life Financials 33 0 0% 33 0 0%
Current Year Financials 33 0 0% 0 (33) -100%
Project Description
Project Manager Alan Douglas
Chief Officer Peter Hessett
Project Lifecycle 31-Mar-24 31-Mar-24
None available at this time.
Anticipated Outcome
Requisition of ICT Equipment.
Valuation Joint Board - ICT Refresh FY 22/23
Replacement of laptops, monitors and other ICT equipment.
Planned End Date Forecast End Date
Requisition ICT Equipment.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
This budget remains unspent and is likely to be carried forward into FY 23/24.
Mitigating Action
30 June 2022
Budget Details
Project Life Financials
Spend to Date Variance
Valuation Joint Board - Requisition of ICT Equipment
Main Issues / Reason for Variance
Replacement of laptops, monitors and other ICT equipment. No further spend anticipated.
Mitigating Action
None available at this time.
Anticipated Outcome
Replacement of laptops and ICT equipment
Main Issues / Reason for Variance
Budget has been rephased from 2021/22.  The project could not proceed as originally planned as Officers are required to access the
office and hardware the system will run on and COVID-19 restrictions have prevented this.  The project will have to go back out to
tender following the upgrade to Microsoft 365.  The project will not be completed in this financial year. 
Mitigating Action
Legal to discuss impact of Microsoft 365 with ICT.
Anticipated Outcome
Project to be completed in 2023/24.
Legal Case Management System
Legal Case Management System
Planned End Date Forecast End Date

Page 2

WEST DUNBARTONSHIRE COUNCIL
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT RED ALERT STATUS
PERIOD END DATE
PERIOD 3
Budget Forecast
Spend
30 June 2022
Budget Details
Project Life Financials
Spend to Date Variance
Project Life Financials 379 42 11% 379 (0) 0%
Current Year Financials 0 0 0% 46 46 0%
Project Description
Project Manager Arun Menon
Chief Officer Victoria Rogers
Project Lifecycle 31-Mar-30 31-Mar-30
Development of Workforce Management System
Project to develop the Workforce Management System.
Anticipated Outcome
Development of Workforce Management System.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Annual staff cost recharge of £0.046m is expected this financial year.
Mitigating Action
None required.