WEST DUNBARTONSHIRE COUNCIL
Report by Chief Officer – Citizen, Culture & Facilities
Corporate Services Committee: 17 August 2022
Subject: Citizen, Culture & Facilities Delivery Plan 2021/22 Year End
progress 
1 Purpose
1.1 This report provides members with the year-end progress of the 2021/22
Delivery Plan. 
2 Recommendations
2.1 It is recommended that Committee:
• Notes progress made on the delivery of the 2021/22 plan.
3 Background
3.1 In line with the Strategic Planning & Performance Framework each Chief
Officer develops an annual Delivery Plan which sets out actions to help deliver
the Strategic Plan and address the performance challenges and service
priorities identified in the planning process. The Plan also provides an
overview of services and resources, including employees and budgets, sets
out the performance indicators (PIs) for monitoring progress and considers the
relevant risks.
3.2 Progress is reported to this Committee twice yearly, at mid-year and year-end.
The progress at year end includes the Delivery Plan for Culture which was 
reported separately to the Culture Committee at mid year.  
4. Main Issues
4.1 The 2021/22 Delivery Plan was presented to Corporate Services Committee
on 19 May 2021 and mid-year progress reported on 24 November 2021.
4.2 The Delivery Plan for 2021/22 was supported by an action plan of activities to
be delivered over the year. Appendix 1 details the progress on delivery of this
action plan.
4.3 18 of the 25 actions have been completed in year as planned. Covid-19
continued to impact on services and delivery during 2021/22 and the
remaining seven actions have not been completed as planned as a result of
the pandemic and will be carried forward and completed in 2022/23:
• Deliver the SLIC funded Pass It On schools project – 75% complete;
• Develop and launch an innovative heritage strategy, reflecting the
investment in the cultural offering for the area – 75% complete;
ITEM 13

Page 2

• Develop  the strategic vision and work plan for Titan crane to ensure it
becomes a key heritage attraction for the area – 66% complete;
• Successfully deliver the £421k capital investment across the branch
network and finalise the branding improvements at all branches- 60%
complete;
• Deliver the employee training and engagement programme funded by
SLIC – 25% complete;
• Progress investment projects in Alexandria library, Clydebank museum
and Dalmuir gallery – 66% complete and
• Review the management structure of Libraries – 50% complete.
4.4 Year end values are available for 12 of the 18 PIs set out in the plan. Eight
met or exceeded targets (green), two narrowly missed targets (amber) and
two were further adrift of targets (red). The latter relate to the following, which
were impacted by the pandemic:
• Percentage of citizens who agree the Council listen to community
views when designing and delivering services.
• Percentage of Local Government Benchmarking Framework
performance indicators prioritised by the council that have improved
locally.
4.5 Four performance indicators showed improvement in both the short and long
term trend, three showed improvement in the short trend and three showed
improvement in the long trend.
4.6 Each service area also developed a suite of quality standards, which set out
the level of service that users and stakeholders can expect to receive, and
remind both the organisation and employees of the challenges and obligations
they face in delivering best value services. Of the nine PIs measuring quality
standards, seven exceeded targets (green) and two were further adrift of the
targets (red). Full details are set out in Appendix 2.
5 People Implications
5.1 There are no direct people implications arising from this report.
6 Financial & Procurement Implications
6.1 There are no direct financial or procurement implications arising from this
report.
7 Risk Analysis
7.1 Failure to deliver on the actions assigned to Citizen, Culture & Facilities may
have a direct impact on the delivery of the Council’s Strategic Plan. It is
essential that remedial action is taken to ensure strategic delivery plans
achieve the commitments detailed and approved.
8 Equalities Impact Assessment

Page 3

8.1 Screening and impact assessments will be carried out on specific activities as
required.
9 Consultation
9.1 The delivery plans were developed through consultation with officers from the
strategic service areas.
10 Strategic Assessment
10.1 The Delivery Plans set out actions to support the successful delivery of the
strategic priorities of the Council.
Chief Officer: Amanda Graham
Service Area: Citizen, Culture & Facilities
Date:  17 August 2022
________________________________________________________________
Person to Contact:  Karen Connelly, P&S Business Partner
karen.Connelly@west-dunbarton.gov.uk
Appendices: Appendix 1: CCF Delivery Plan 2021/22 - Year-end
Progress;
Appendix 2: CCF Quality Standards 2021/22 - Year-end
Progress
Background Papers: 2021/22 CCF Delivery Plan Report – Corporate Services
Committee, 19 May 2021
2021/22 CCF Delivery Plan Mid-year Report – Corporate
Services Committee, 24 November 2021
2021/22 Culture Delivery Plan Mid-year Report – Culture
Committee, 
Wards Affected: All