WEST DUNBARTONSHIRE COUNCIL
Report by the Chief Officer – Resources
Corporate Services Committee – 27 May 2026
___________________________________________________________________ 
Subject: Corporate Services Capital Budgetary Control Report to 31 January 2026  
(Period 10) 
1. Purpose 
1.1 This report provides an update on the Corporate Services capital programme
to 31 January 2026. 
2. Recommendations 
2.1 Committee is asked to: 
i) Note the current position of the 2025/26 capital budget for Corporate
Services 
ii) Note the revised completion dates in respect of 2 projects detailed in
Appendix 2 (Para 4.4). 
iii) Note the reprofiling of 4 projects in Appendix 3 of (£0.669m) over the
project life. 
3. Background 
3.1 On 5 March 2025 the Council approved the updated General Services Capital
Plan for 2025/2026 to 2033/34.  The three years from 2025/26 to 2027/28
were approved in detail with the remaining years being indicative. The budget
agreed under the auspice of Corporate Services Committee was £4.078m for
2025/26 and £29.301m for the project life budget. 
4. Main Issues 
4.1 Exhibit 1 sets out the revised capital budget at period 7 as reported to
Corporate Services Committee on 4 February 2026. 
Exhibit 1: Revised Capital Budget as at 31 October 2025. 
2025/26
(£m)
Project
Life (£m)
Corporate Services Capital Budget Agreed 5
March 2025 4.078 29.301
Reprofiling reported to committee on 13 August
and 4 February 0.015 (0.094)
Approved P&T Capital Bid – Data Strategy 0.027 0.027
Revised Capital Budget as at Period 7 4.120 29.234
ITEM 16

Page 2

4.2 Progress against the 2025/26 capital plan is detailed in: 
Appendix 1 – Project Life Summary by Chief Officer 
Appendix 2 – Projects Off Track 
Appendix 3 – Changes to Capital Plan for Noting 
Appendix 4 – All Projects 
4.3  The overall program summary report at Appendix 1 shows that planned
expenditure against the budget is currently on track. Note Appendix 1 is
constructed assuming all changes in this report are approved. 
4.4  Appendix 2 highlights 2 projects currently showing as off-track, all of which
are due to revised completion dates.  
• Project RES 4 (Community Success Capital Fund) is off-track due to no
active or pending requests for funding. 
• Project RES 5 (Community Sports Success) is off track due to no active
or pending requests for funding. 
4.5  Appendix 3 highlights 4 projects where the expenditure requires to be
reprofiled but there is no need for additional budget. 
4.6  Exhibit 2 sets out the revised capital budget at period 10 after amending it to
reflect the Council decisions taken in relation to the agenda item, General
Services Capital Report Budgetary Control Report (Period 10) on the 25 of
March. 
Exhibit 2: Revised Capital Budget 
2025/26
(£m)
Project
Life (£m)
Corporate Services Capital Budget as at 31
October 2025 4.120 29.234
Approved Review of Capital Programme (Para
4.9) (0.033) (0.421)
Projects completed and removed (Para 4.10) 0 (3.173)
Projects complete at 31 January 2026 (Para
4.11) (0.010) (0.512)
Proposed revised Capital Budget as at
Period 10 4.077 25.128
Reprofiling over project life (Appendix 3) (0.669) 0
Proposed revised Capital Budget as at
Period 10 after Council Approval 3.408 25.128 
4.8  Appendix 4 shows all projects with approved in year and project life budgets
as well as anticipated expenditure. It highlights the 2025/26 budget is
£4.077m. Spend as at period 10 is £1.975m (57.94%) of the current forecast
spend of £3.408m.

Page 3

4.9  Following the Review of West Dunbartonshire Council’s Capital Programme
paper approved by Council on 17 December 2025 with one amendment per
the motion, the changes below have been applied to the capital plan: 
• Projects removed
o Legal Case Management System (RR 1) - £0.033m 
• Projects with reduced budget allocation
o Finance Ledger System (RES 11) - £0.200m
o Development of Workforce Management System (P&T 4) - £0.188m 
4.10  Following the above adjustments, historic project life budgets completed and
removed have been applied which reduces project life by £3.173m. 
4.11  Additionally Cost of Living (RES 3) has been completed at 31 January 2026. 
5. Option Appraisal 
5.1 No option appraisal was required for this report. 
6. People Implications 
6.1 There are no people implications. 
7. Financial and Procurement Implications 
7.1 The report notes the projected in-year financial position for capital budgets. 
8. Risk Analysis 
8.1 The main risks are as follows: 
(a) The reported variances should be viewed in the knowledge that there
are a number of variable factors which could arise between now and 31
March which could affect the year end results for capital budgets. 
(b) As a consequence of current market conditions, inflation is at an all-time
high and interest rates continue to be volatile. To forecast for the full
year costs budget assumptions have been required. These assumptions
continue to change regularly and therefore it is likely the projected year
end budgetary position will change from that reported. 
9. Equalities Impact Assessment (EIA) 
9.1 No equalities impact assessment was required in relation to this report. 
10. Environmental Sustainability 
10.1 No assessment of environmental sustainability was required in relation to this
report.

Page 4

11. Consultation 
11.1 All services involved in delivering the capital budgets have been consulted in
the compilation of this report. 
12. Strategic Assessment 
12.1 Proper budgetary control and sound financial practice are cornerstones
of good governance and support Council and officers to pursue the
strategic priorities of the Council’s current Strategic Plan. This report
forms part of the financial governance of the Council. 
Laurence Slavin
Chief Officer – Resources
Date: 15 April 2026
________________ 
Person to Contact:  Lynsey Dickson, Finance Business Partner  
Council Offices, Church Street, Dumbarton   
E-mail: lynsey.dickson@west-dunbarton.gov.uk 
Appendices:  Appendix 1 - Project Life Summary  
Appendix 2 - Projects Off Track 
Appendix 3 - Changes to Capital Plan for Noting
Appendix 4 - All Approved Projects 
Background Papers:   General Services Capital Plan Update - Council 5 March 
2025 
Capital Budgetary Control Report (P3) – Council 27 
August 2025 
Capital Budgetary Control Report (P5) – Council 29 
October 2025    
Capital Budgetary Control Report (P7) – Council 17 
December 2025    
Review of West Dunbartonshire Councils Capital    
Programme – Council 17 December 2025    
Capital Budgetary Control Report (P10) – Council 24    
March 2026 
Wards Affected           All Wards