WEST DUNBARTONSHIRE COUNCIL 
Report by Chief Officer - Resources 
Committee: Corporate Services Committee 27 May 2026 
Subject: Resources Delivery Plan 2025/26 - Year-end Progress & 
Resources Delivery Plan 2026/27 
1 Purpose 
1.1 This report sets out the year-end progress of the 2025/26 Delivery Plan and
presents the new Delivery Plan for 2026/27. 
2 Recommendations 
2.1 It is recommended that Committee notes the progress achieved at year-end
and the new Plan for 2026/27. 
3 Background 
3.1 In line with the Strategic Planning & Performance Framework, each Chief
Officer develops an annual Delivery Plan which sets out actions to help deliver
the Strategic Plan and address the performance challenges and service
priorities identified in the planning process. The Plan also provides an
overview of services and resources, including employees and budgets, sets
out the performance indicators (PIs) for monitoring progress and considers the
relevant risks. 
4 Main Issues 
2025/26 Year-end Progress 
4.1 The 2025/26 Delivery Plan was presented to Corporate Services Committee
on 21 May 2025 and mid-year progress reported on 12 November 2025. 
4.2 Full details of year-end progress are set out in Appendix 1. 
4.3 The progress of the Plan’s 18 actions is summarised below: 
Progress No. (%) 
Completed 16 (89%) 
Overdue 2 (11%) 
ITEM 11

Page 2

4.4 The overdue action relates to the following and will be carried forward and
completed in 2026/27:
• Complete the redevelopment of Glencairn House - 95% complete.
• Implement service review process including role design, use of new
technology and new ways of working to add resilience, address gaps, and
establish opportunities for efficiencies - 91% complete. 
4.5 Year-end data is available for nine of the Plan’s 20 PIs. The performance of
those PIs is summarised below: 
Performance Against Target No. (%) 
Target met or exceeded 9 of 9
(100%)
Performance Over Time
(As one of the nine PIs is new for 2025/26, this section relates to eight
PIs)
No. (%) 
Improved over short term (or maintained high level of
performance)
6 of 8 (75%) 
Improved over longer term (or maintained high level of
performance)
6 of 8 (75%) 
4.6 The full set of PIs will be reported through the Council’s annual performance
reporting process once all data becomes available. 
2026/27 Delivery Plan 
4.7 The 2026/27 Delivery Plan is set out at Appendix 2. 
4.8 Key priorities include:
• delivering sustainable, quality services within the context of significant
financial challenges
• implementing a new financial management system 
• reviewing ways to decrease corporate debt in relation to sundry, non-
domestic rates, Council Tax, and rent
• reviewing ways to improve rent collection rates in conjunction with
Housing and W4U
• automating Council processes and information provision
• progressing the disposal of key strategic sites
• maximising rental income from the Council’s non-operational property
portfolio
• reviewing non-domestic rates of the Council’s operational property
portfolio
• completing the Artizan redevelopment
• completing the Faifley Community Campus development
• progressing the buildings upgrades programme
• progressing the depot refurbishment programme
• supporting Council services to deliver the asset related savings agreed by
Council

Page 3

• progressing the implementation of the Global Internal Audit Standards and
CIPFA’s Code of Practice for the Governance of Internal Audit in UK Local
Government within the internal audit team’s methodologies and processes
• progressing a shared service internal audit service 
4.9 Implementation of the Plan will be monitored by the management team with
mid-year and year-end progress reported to Corporate Services Committee
and Infrastructure, Regeneration and Economic Development Committee
(asset management elements only) around November 2026 and May 2027
respectively. 
5 People Implications 
5.1 There are no direct people implications arising from this report. 
6 Financial & Procurement Implications 
6.1  There are no direct financial or procurement implications arising from this
report. 
7 Risk Analysis 
7.1 Failure to deliver on the actions assigned to Resources may have a direct
impact on the delivery of the Council’s Strategic Plan. It is essential that
remedial action is taken to ensure strategic delivery plans achieve the
commitments detailed. 
8 Equalities Impact Assessment 
8.1 Screening and impact assessments will be carried out on specific activities as
required. 
9 Consultation 
9.1  The delivery plans were developed through consultation with officers from the
strategic service areas. 
10 Strategic Assessment 
10.1  The delivery plans set out actions to support the successful delivery of the
strategic priorities and objectives of the Council. 
Chief Officer: Laurence Slavin
Service Area:  Resources
Date:   30 April 2026
_____________________________________________________________

Page 4

Person to Contact:  Lynn Henderson    
lynn.henderson@west-dunbarton.gov.uk 
Appendices:  Appendix 1: Resources Delivery Plan 2025/26 - Year-end
Progress  
Appendix 2: Resources Delivery Plan 2026/27 
Background Papers: Resources Delivery Plan 2025/26 - Corporate Services
Committee, 21 May 2025 
Resources Delivery Plan 2025/26 Mid-year Progress -
Corporate Services Committee, 12 November 2025 
Strategic Planning & Performance Framework 2022/27   
Wards Affected: All