WEST DUNBARTONSHIRE COUNCIL 
Report by Chief Officer - Regulatory & Regeneration 
Committee: Corporate Services Committee 27 May 2026 
Subject: Regulatory & Regeneration Delivery Plan 2025/26 - Year-end Progress
& Regulatory & Regeneration Delivery Plan 2026/27 
1 Purpose 
1.1 This report sets out the year-end progress of the 2025/26 Delivery Plan and
presents the new Delivery Plan for 2026/27. 
2 Recommendations 
2.1 It is recommended that Committee notes the progress achieved at year-end
and the new Plan for 2026/27. 
3 Background 
3.1 In line with the Strategic Planning & Performance Framework, each Chief
Officer develops an annual Delivery Plan which sets out actions to help deliver
the Strategic Plan and address the performance challenges and service
priorities identified in the planning process. The Plan also provides an
overview of services and resources, including employees and budgets, sets
out the performance indicators (PIs) for monitoring progress and considers the
relevant risks. 
4 Main Issues 
2025/26 Year-end Progress 
4.1 The 2025/26 Delivery Plan was presented to Corporate Services Committee
on 21 May 2025 and mid-year progress reported on 12 November 2025. 
4.2 Full details of year-end progress are set out in Appendix 1. 
4.3 The progress of the Plan’s 34 actions is summarised below: 
Progress No. (%) 
Completed 28 (82%) 
Overdue 5 (15%) 
Cancelled  1 (3%)   
4.4 Overdue actions relate to the following and will be carried forward and
completed in 2026/27: 
ITEM 10

Page 2

• Develop the Local Heat and Energy Efficiency Strategy Delivery Plan -
50% complete
• Produce a planning focused delivery programme to support key
regeneration sites and enable high quality development to be achieved on
the ground - 25% complete
• Explore commercial opportunities in our town centres and wider
regeneration sites - 75% complete
• Prepare a robust evidence report for the next Local Development Plan
(LDP3) for submission for Gatecheck to Scottish Government Planning
and Environmental Appeals Division - 50% complete
• Review processes and procedures within Legal Services’ Commercial &
Place and Citizen & Regulatory teams - 75% complete 
4.5 Year-end data is available for 16 of the Plan’s 26 PIs. The performance of
those PIs is summarised below: 
Performance Against Target No. (%) 
Target met or exceeded 9 of 16 (56%) 
Target narrowly missed 1 of 16 (6%) 
Target significantly missed 6 of 16 (38%)
Performance Over Time
(As 4 of the 16 PIs are new for 2025/26, this section relates to 12 PIs)
No. (%) 
Improved over short term (or maintained a high level
of performance)
5 of 12 (42%) 
Improved over longer term (or maintained a high
level of performance)
4 of 12 (33%) 
4.6 Targets that were significantly missed relate to the following PIs:
• Percentage of planned underage sales visits carried out by Trading
Standards to premises registered on the Scottish Government tobacco
and nicotine vapour product retailers register - 60% against a target of
95%
• Planning Applications (Major Developments - Without Processing
Agreement): Average number of weeks to decision - 21.7 weeks against a
target of 16 weeks
• Planning Applications (Locals - Householder): Average number of weeks
to decision - 13.7 weeks against a target of 8 weeks
• Planning Applications (Other Locals): Average number of weeks to
decision - 9.6 weeks against a target of 8 weeks
• Planning Applications (Other Locals): Percentage decided within statutory
8-week timescale - 55.9% against a target of 80%
• Percentage of building warrant applications responded to within 20
working days - 62.98% against a target of 95% 
4.7 The full set of PIs will be reported through the Council’s annual performance
reporting process once all data becomes available.

Page 3

2026/27 Delivery Plan 
4.8 The 2026/27 Delivery Plan is set out at Appendix 2. 
4.9 Key priorities include:
• delivering sustainable, quality services within the context of significant
financial challenges
• delivering key regeneration sites across West Dunbartonshire
• promoting the next phase of Queens Quay Housing
• exploring commercial opportunities in our town centres and wider
regeneration sites 
• supporting town centre revitalisation
• finalising the Visitor Levy Scheme
• developing a new Economic Development Strategy
• developing a Climate Change Strategy and action plan
• completing the Local Heat and Energy Efficiency Delivery Plan
• implementing the Scottish Parliamentary Elections for the Dumbarton and
Clydebank and Milngavie Constituencies in May 2026
• planning for the Local Government elections in May 2027
• reviewing the Scheme for Establishment of Community Councils
• conducting Community Council elections
• developing Community Planning
• contributing to the Community Learning and Development Plan
• providing legal services to the Council and West Dunbartonshire Energy
LLP in relation to heat supply agreements and network supply contracts
• Implementing the extension of the statutory duty (Tobacco and Vapes Bill)
in line with our enforcement policy
• advising businesses re the introduction of Vaping Products Duty and
compliance of vaping products
• delivering collaborative projects with Trading Standards partners
• progressing the Local Development Plan 3
• reviewing the planning pre-application process
• completing the installation of the new document management system for
Planning and Building Standards 
• providing training to Environmental Health Officers to respond to the Food
(Promotion & Placement) (Scotland) Regulations 2025
• supporting the implementation and development of a new Enterprise
Resource Planning System in relation to procurement 
4.10 Implementation of the Plan will be monitored by the management team with
mid-year and year-end progress reported to Corporate Services Committee
and Infrastructure, Regeneration and Economic Development Committee
(economic development elements only) around November 2026 and May
2027 respectively. 
5 People Implications 
5.1 There are no direct people implications arising from this report.

Page 4

6 Financial & Procurement Implications 
6.1  There are no direct financial or procurement implications arising from this
report. 
7 Risk Analysis 
7.1 Failure to deliver on the actions assigned to Regulatory & Regeneration may
have a direct impact on the delivery of the Council’s Strategic Plan. It is
essential that remedial action is taken to ensure strategic delivery plans
achieve the commitments detailed. 
8 Equalities Impact Assessment 
8.1 Screening and impact assessments will be carried out on specific activities as
required. 
9 Consultation 
9.1  The delivery plans were developed through consultation with officers from the
strategic service areas. 
10 Strategic Assessment 
10.1  The delivery plans set out actions to support the successful delivery of the
strategic priorities and objectives of the Council. 
Chief Officer: Alan Douglas
Service Area:  Regulatory & Regeneration
Date:   29 April 2026
_____________________________________________________________ 
Person to Contact:  Lynn Henderson    
lynn.henderson@west-dunbarton.gov.uk 
Appendices:  Appendix 1: Regulatory & Regeneration Delivery Plan
2025/26 - Year-end Progress  
Appendix 2: Regulatory & Regeneration Delivery Plan
2026/27

Page 5

Background Papers: Regulatory & Regeneration Delivery Plan 2025/26 -
Corporate Services Committee, 21 May 2025 
Regulatory & Regeneration Delivery Plan 2025/26 Mid-
year Progress - Corporate Services Committee, 12
November 2025 
Strategic Planning & Performance Framework 2022/27   
Wards Affected: All