Democracy Spraffa

Item 05 - Minutes of Previous Meeting

West Dunbartonshire Council · 27 May 2026
Back to Corporate Services Committee — 27 May 2026 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

CORPORATE SERVICES COMMITTEE 
At a Hybrid Meeting of the Corporate Services Committee held in the Civic Space,
16 Church Street, Dumbarton on Wednesday, 27 February 2026 at 2.00 p.m. 
Present: Councillors Kevin Crawford, Ian Dickson, Fiona Hennebry, David
McBride, Michelle McGinty, Lawrence O’Neill, Chris Pollock,
Martin Rooney and William Rooney. 
Attending: Peter Hessett Chief Executive; Alan Douglas, Chief Officer –
Regulatory and Regeneration; Amanda Graham, Chief Officer –
Citizen, Culture and Facilities; Victoria Rogers, Chief Officer –
People and Technology; Laurence Slavin, Chief Officer –
Resources; Michelle Lynn, Asset Manager; Carol Alderson,
Finance Manager; Ryan Chalmers, Section Head – Resources;
Arun Menon, Business Support Manager; James Gallacher,
Service Manager – ICT; Louise Hastings, Strategic People and
Change Manager; Janine Corr, Business Partner – Resources;
Chris Anderson, Principal Solicitor (Legal Officer); and Scott
Kelly, Committee Officer. 
Apologies: Apologies for absence were intimated on behalf of Councillors
Gordon Scanlan and Clare Steel. 
Councillor William Rooney in the Chair 
STATEMENT BY CHAIR – AUDIO STREAMING 
Councillor William Rooney, Chair, advised that the meeting was being audio
streamed and broadcast live to the internet and would be available for playback. 
DECLARATIONS OF INTEREST 
It was noted that there were no declarations of interest in any of the items of
business on the agenda. 
RECORDING OF VOTES 
The Committee agreed that all votes taken during the meeting would be carried out
by roll call vote to ensure an accurate record. 
ITEM 5

Page 2

MINUTES OF PREVIOUS MEETING 
The Minutes of Meeting of the Corporate Services Committee held on 12 November
2025 were submitted and approved as a correct record. 
MINUTES OF JOINT CONSULTATIVE FORUM 
The Minutes of Meeting of the Joint Consultative Forum held on 18 September 2025
were submitted and all decisions contained therein were approved. 
OPEN FORUM 
The Committee noted that no open forum questions had been submitted by
members of the public. 
PEOPLE AND TECHNOLOGY SPEND 2026-27 
A report was submitted by the Chief Officer – People and Technology providing a
detailed breakdown of the planned People and Technology spend for both capital
and revenue, covering new and existing contracts valued above £10,000 and
seeking approval to procure and contract for the requisite goods and services. 
After discussion and having heard the Service Manager – ICT in further explanation
and in answer to Members’ questions, the Committee agreed:- 
(1) to note the revenue and capital spend detail included in the report; 
(2) to note the projects to deliver this spend would be included in the 2026-27
People and Technology Delivery Plan currently in development and to be
reported to a future meeting of the Committee; 
(3) to approve the procurement of and award by the Chief Officer – Regulatory
and Regeneration in consultation with the Chief Officer – People and
Technology of all contracts valued at £213,477 (VAT inclusive) and above
subject to the cost being within the approved budget and the tender being in
line with normal tender parameters; 
(4) to note, that where the contract award is less than £213,477 (VAT inclusive),
authority is delegated to the Chief Officer – Regulatory and Regeneration in
consultation with the Chief Officer – People and Technology to instruct the
award of contracts for the planned revenue and capital spend, detailed in the
report, to suppliers providing the most economically advantageous offer to the
Council;

Page 3

(5) to approve the revenue spend included in the report, including approval to
explore and secure multi-year contracts, contracts using framework
agreements and/or contracts using dynamic purchasing systems beyond the
term of approved budgets where efficiencies and savings can be achieved;
and 
(6) to approve the projects specified in Section 3 of the report, shown in Appendix
1 to these Minutes. 
Note: Councillor McGinty entered the meeting during consideration of this item. 
THE PROVISION OF MANAGED WORK FOR HOUSING BENEFIT AND COUNCIL
TAX REDUCTION 
A report was submitted by the Chief Officer – Resources seeking approval to procure
the provision of managed work associated with the processing of Housing Benefit
and Council Tax Reduction claims. 
Having heard the Chief Officer – Resources in further explanation and in answer to
Members’ questions, the Committee agreed to approve the procurement of the
managed work associated with the processing of Housing Benefit and Council Tax
Reduction for a two year period with the option on the Council’s part to extend for a
further two 12-month periods, subject to continued funding from the Department for
Work and Pensions as detailed in paragraph 4.2 of the report. 
WRITE-OFF OF NATIONAL NON-DOMESTIC RATES 2025/26 
A report was submitted by the Chief Officer – Resources seeking approval of
the write-off of debts in respect of National Non-Domestic Rates (NNDR), which had
been deemed as irrecoverable during the financial year 2025/2026. 
After discussion and having heard the Chief Officer – Resources in answer to a
Member’s question, the Committee agreed the write-off of NNDR accounts totalling
£150,933.73. 
CORPORATE SERVICES REVENUE BUDGETARY CONTROL REPORT
TO 31 OCTOBER 2025 (PERIOD 7) 
A report was submitted by the Chief Officer – Resources on the revenue financial
performance to 31 October 2025 of those services under the auspices of the
Corporate Services Committee. 
After discussion and having heard the Chief Officer – Resources and the Chief
Officer – Citizen, Culture and Facilities, in further explanation and in answer to
Members’ questions, the Committee agreed to note the contents of the report which
showed the revenue account was currently projected to underspend against budget
by £0.138m (0.34%of the total budget) at the year-end.

Page 4

CORPORATE SERVICES CAPITAL BUDGETARY CONTROL REPORT
TO 31 OCTOBER 2025 (PERIOD 7) 
A report was submitted by the Chief Officer – Resources providing an update on the
Corporate Services capital programme to 31 October 2025. 
The Committee agreed:- 
(1) to note the current position of the 2025/26 capital budget for Corporate
Services; and 
(2) to note that the project life total was currently on track. 
The meeting closed at 2.21 p.m.

Page 5

Appendix 1
Table 1 – Existing Agreed ICT 1-Year Capital Plan
Capital allocation 2026/27
ICT Security & Resilience £387,000
ICT Modernisation £459,000
Total £841,000 
Table 2 – Proposed Projects ICT Capital Spend 2026-27
Description Capital (Est)
ICT Security & DR, Resilience £387,000
1. Replace Ageing Infrastructure Hardware £94,000
2. Security Compliance remediation £70,000
3. Security Resourcing - multi-year consultancy services £23,000
4. Internal ICT resource recharges £90,000
5. Security Patching Improvements £20,000
6. Cisco Enterprise Agreement £90,000
ICT Modernisation £459,000
1. Chromebooks Device replacement: (laptops, PCs,
chromebooks and mobile phones for both Corporate and
Education)
£336,000
2. Resources to Support a range of corporate projects. £123,000
Total £846,000 
Estimated Annual Revenue Spend over £10,000 (based on 2025-26)
Microsoft Enterprise Agreement Licences Phoenix 31.12.2028 £631,200
Wide Area Network SWAN 2.0 01.02.2033 £186,700
Social Work Case Management & Scheduler OLM 31.03.2026 £134,700
Cloud Telephony System BT 01.12.2030 £120,000
Integrated Housing Management System Aareon UK 07.02.2027 £115,100
Education MIS SEEMIS 02.05.2026 £105,500
Remote Access BT 31.12.2026 £97,000
M365 Education licenses Phoenix 01.07.2026 £83,500
Revenue & Benefits Northgate 31.03.2026 £79,600
Automation Software UI Path 01.02.2027 £74,400
Leisure Management MRM Gladstone 01.11.2026 £68,400
365 Cloud Backup Barracuda 31.10.2026 £67,800
Electronic Document Management Civica 31.03.2026 £57,800
Various/ Amalgamated Housing Benefits and Allocations Civica 31.03.2026 £57,800

Page 6

Online Forms Granicus 30.11.2026 £49,000
Vulnerability Management Qualys Computacenter 24.12.2026 £39,500
Firewall Support BT 12.05.2029 £37,000
Planning & Building Uniform System IDOX 31.03.2026 £35,900
Job Costing CIS Core Accuris 30.01.2026 £32,600
Employability Case Management Advice Pro ACM 30.03.2026 £32,400
Security Filtering Management Infosec 04.06.2026 £31,900
Roads – Lighting, Collision, Flood Mgmt. WDM Various dates £31,400
Library Management Spydus Civica 1.12.2029 £29,100
Energy Management Navigator Inspired 01.04.2026 £27,500
Local Government Digital Transformation Scottish Gov. 31.03.2026 £27,400
Virtual Server Environment Support Phoenix/VMware 22.12.2025 £27,300
Corporate Arrears System Merchant 31.05.2026 £26,900
Flare Environmental Services Civica 31.03.2026 £26,900
GGP GIS software ESRI 31.03.2026 £26,700
Workforce Management Frontier 07.10.2026 £26,000
Freshservice ICT Service Desk Softcat 28.02.2026 £25,900
Backup Management Insight 31.12.2028 £25,800
Asset Management CIPFA 30.04.2026 £24,300
Performance Management system Ideagan 30.04.2026 £21,600
Server Maintenance Park Place 02.09.2026 £20,500
Election Management Avantguard IDOX 28.02.2026 £20,100
Vehicle Management Fleetmaster Trapeze UK 31.03.2026 £19,700
Education Gateway Glasgow C.C 06.06.2026 £17,600
Council Website Support Brace Digital 31.10.2026 £15,600
ORACLE ULA Oracle 05.04.2026 £14,800
ORBIS Northgate/NEC 31.03.2026 £14,800
Device Security Management Antivirus IT Bus Ltd. 26.06.2026 £13,900
Agresso support Hennessy IT 31.05.2027 £13,500
NBS Building RIBA 31.12.2028 £12,400
Housing Homeless database AVD 31.03.2026 £12,300
Health & Safety system Figtree 14.07.2026 £12,200
Council Meetings System Astech 30.04.2026 £11,900
Phishing simulation and training platform Metacompliance 11.06.2026 £11,800
Resource Booking System Omnijo 31.03.2026 £10,700