Democracy Spraffa

Document Pack (Bookmarked) - CSC 27 05 26

West Dunbartonshire Council · 27 May 2026
Back to Corporate Services Committee — 27 May 2026 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

Agenda 
Corporate Services Committee 
Date:  Wednesday, 27 May 2026 
Time:  10:00 
Format:  Hybrid Meeting 
Contact:       committee.admin@west-dunbarton.gov.uk 
Dear Member 
Please attend a meeting of the Corporate Services Committee as detailed above.   
Members will have the option to attend the meeting remotely or in person at the Civic
Space, 16 Church Street, Dumbarton. 
The business is shown on the attached agenda. 
Yours faithfully 
PETER HESSETT 
Chief Executive 
Page 1

Page 2

Distribution:- 
Councillor Kevin Crawford
Councillor Ian Dickson
Councillor David McBride 
Councillor Michelle McGinty
Councillor John Millar
Councillor Lawrence O’Neill (Vice Chair)
Councillor Lauren Oxley
Councillor Chris Pollock
Councillor Martin Rooney
Councillor William Rooney (Chair)
Councillor Gordon Scanlan
Councillor Hazel Sorrell 
Chief Executive
Chief Officers 
Date of issue:  14 May 2026 
Audio Streaming 
Audio recordings of the meeting (including the attendance or contribution of any party
participating or making a contribution) will be published on the Council’s website and
the Council’s host’s webcast/audio stream platform. 
You should be aware that the Council is a Data Controller under the General Data
Protection Regulation.  Data collected during this audio stream will be retained in
accordance with the Council’s Privacy Notice and Retention Schedules including, but
not limited to, for the purpose of keeping historical records and making those records
available via the Council’s internet site. 
Page 2

Page 3

CORPORATE SERVICES COMMITTEE 
WEDNESDAY, 27 MAY 2026 
AGENDA 
1 STATEMENT BY CHAIR – AUDIO STREAMING 
The Chair will be heard in connection with the above. 
2 APOLOGIES 
3 DECLARATIONS OF INTEREST 
Members are invited to declare if they have an interest in any of the items of 
business on this agenda and the reasons for such declarations. 
4 RECORDING OF VOTES 
The Committee is asked to agree that all votes taken during the meeting be
caried out by roll call vote to ensure an accurate record. 
5 MINUTES OF PREVIOUS MEETING      7 - 12 
Submit, for approval as a correct record, the Minutes of Meeting of the
Corporate Services Committee held on 4 February 2026. 
6 MINUTES OF JOINT CONSULTATIVE FORUM     13 - 14 
Submit for information and where necessary ratification, the Minutes of
Meeting of the Joint Consultative Forum held on 12 March 2026. 
7 OPEN FORUM 
The Committee is asked to note that no open forum questions have been
submitted by members of the public. 
8/ 
Page 3

Page 4

8 CITIZEN, CULTURE AND FACILITIES 2025/26 – YEAR-END 15 - 51
PROGRESS AND CITIZEN, CULTURE AND FACILITIES
DELIVERY PLAN 2026/27     
Submit report by the Chief Officer – Citizen, Culture and Facilities setting out
the year-end progress of the 2025/26 Delivery Plan and presenting the new
Delivery Plan for 2026/27. 
9 PEOPLE AND TECHNOLOGY DELIVERY PLAN 2025/26 –  53 - 93
YEAR-END PROGRESS AND PEOPLE AND TECHNOLOGY
DELIVERY PLAN 2026/27 
Submit report by the Chief Officer – People and Technology setting out the
year-end progress of the 2025/26 Delivery Plan and presenting the new
Delivery Plan for 2026/27.   
10 REGULATORY AND REGENERATION DELIVERY PLAN   95 - 156
2025/26 – YEAR-END PROGRESS AND REGULATORY AND
REGENERATION DELIVERY PLAN 2026/27 
Submit report by the Chief Officer – Regulatory and Regeneration setting out
the year-end progress of the 2025/26 Delivery Plan and presenting the new
Delivery Plan for 2026/27.   
11 RESOURCES DELIVERY PLAN 2025/26 – YEAR-END   157 - 198
PROGRESS AND RESOURCES DELIVERY PLAN 2026/27 
Submit report by the Chief Officer – Resources setting out the year-end
progress of the 2025/26 Delivery Plan and presenting the new Delivery Plan
for 2026/27. 
12 WEST DUNBARTONSHIRE LEISURE TRUST BUSINESS  199 - 222
PLAN 2026/27 
Submit report by the Chief Officer – Citizen, Culture and Facilities providing
an update on the West Dunbartonshire Leisure Trust Business Plan 2026-27. 
13 COUNCIL WORKFORCE PLAN 2022-2027: UPDATE AND  223 - 279
ANNUAL ACTION PLANS 2025/26 
Submit report by the Chief Officer – People and Technology providing an
update on the Council’s workforce planning activity for 2025/26. 
14/
Page 4

Page 5

14 PROVISION OF A CASH RECEIPTING SYSTEM   281 - 287 
Submit report by the Chief Officer – Resources seeking approval to
commence the tendering process for the Provision of a Cash Receipting
System for the period 1 April 2027 to 31 March 2029, with an option to extend
for a further two additional 12 month periods to 31 March 2031 for West
Dunbartonshire Council. 
15 CORPORATE SERVICES REVENUE BUDGETARY   
CONTROL REPORT TO 31 JANUARY 2026 (PERIOD 10)
289 - 306 
Submit report by the Chief Officer – Resources on the revenue financial
performance to 31 January 2026 of those services under the auspices of the
Corporate Services Committee. 
16 CORPORATE SERVICES CAPITAL BUDGETARY   
CONTROL REPORT TO 31 JANUARY 2026 (PERIOD 10)
307 - 314 
Submit report by the Chief Officer – Resources providing an update on the
Corporate Services capital programme to 31 January 2026. 
Page 5

Page 6

Page 6

Page 7

CORPORATE SERVICES COMMITTEE 
At a Hybrid Meeting of the Corporate Services Committee held in the Civic Space,
16 Church Street, Dumbarton on Wednesday, 27 February 2026 at 2.00 p.m. 
Present: Councillors Kevin Crawford, Ian Dickson, Fiona Hennebry, David
McBride, Michelle McGinty, Lawrence O’Neill, Chris Pollock,
Martin Rooney and William Rooney. 
Attending: Peter Hessett Chief Executive; Alan Douglas, Chief Officer –
Regulatory and Regeneration; Amanda Graham, Chief Officer –
Citizen, Culture and Facilities; Victoria Rogers, Chief Officer –
People and Technology; Laurence Slavin, Chief Officer –
Resources; Michelle Lynn, Asset Manager; Carol Alderson,
Finance Manager; Ryan Chalmers, Section Head – Resources;
Arun Menon, Business Support Manager; James Gallacher,
Service Manager – ICT; Louise Hastings, Strategic People and
Change Manager; Janine Corr, Business Partner – Resources;
Chris Anderson, Principal Solicitor (Legal Officer); and Scott
Kelly, Committee Officer. 
Apologies: Apologies for absence were intimated on behalf of Councillors
Gordon Scanlan and Clare Steel. 
Councillor William Rooney in the Chair 
STATEMENT BY CHAIR – AUDIO STREAMING 
Councillor William Rooney, Chair, advised that the meeting was being audio
streamed and broadcast live to the internet and would be available for playback. 
DECLARATIONS OF INTEREST 
It was noted that there were no declarations of interest in any of the items of
business on the agenda. 
RECORDING OF VOTES 
The Committee agreed that all votes taken during the meeting would be carried out
by roll call vote to ensure an accurate record. 
ITEM 5
Page 7

Page 8

MINUTES OF PREVIOUS MEETING 
The Minutes of Meeting of the Corporate Services Committee held on 12 November
2025 were submitted and approved as a correct record. 
MINUTES OF JOINT CONSULTATIVE FORUM 
The Minutes of Meeting of the Joint Consultative Forum held on 18 September 2025
were submitted and all decisions contained therein were approved. 
OPEN FORUM 
The Committee noted that no open forum questions had been submitted by
members of the public. 
PEOPLE AND TECHNOLOGY SPEND 2026-27 
A report was submitted by the Chief Officer – People and Technology providing a
detailed breakdown of the planned People and Technology spend for both capital
and revenue, covering new and existing contracts valued above £10,000 and
seeking approval to procure and contract for the requisite goods and services. 
After discussion and having heard the Service Manager – ICT in further explanation
and in answer to Members’ questions, the Committee agreed:- 
(1) to note the revenue and capital spend detail included in the report; 
(2) to note the projects to deliver this spend would be included in the 2026-27
People and Technology Delivery Plan currently in development and to be
reported to a future meeting of the Committee; 
(3) to approve the procurement of and award by the Chief Officer – Regulatory
and Regeneration in consultation with the Chief Officer – People and
Technology of all contracts valued at £213,477 (VAT inclusive) and above
subject to the cost being within the approved budget and the tender being in
line with normal tender parameters; 
(4) to note, that where the contract award is less than £213,477 (VAT inclusive),
authority is delegated to the Chief Officer – Regulatory and Regeneration in
consultation with the Chief Officer – People and Technology to instruct the
award of contracts for the planned revenue and capital spend, detailed in the
report, to suppliers providing the most economically advantageous offer to the
Council; 
Page 8

Page 9

(5) to approve the revenue spend included in the report, including approval to
explore and secure multi-year contracts, contracts using framework
agreements and/or contracts using dynamic purchasing systems beyond the
term of approved budgets where efficiencies and savings can be achieved;
and 
(6) to approve the projects specified in Section 3 of the report, shown in Appendix
1 to these Minutes. 
Note: Councillor McGinty entered the meeting during consideration of this item. 
THE PROVISION OF MANAGED WORK FOR HOUSING BENEFIT AND COUNCIL
TAX REDUCTION 
A report was submitted by the Chief Officer – Resources seeking approval to procure
the provision of managed work associated with the processing of Housing Benefit
and Council Tax Reduction claims. 
Having heard the Chief Officer – Resources in further explanation and in answer to
Members’ questions, the Committee agreed to approve the procurement of the
managed work associated with the processing of Housing Benefit and Council Tax
Reduction for a two year period with the option on the Council’s part to extend for a
further two 12-month periods, subject to continued funding from the Department for
Work and Pensions as detailed in paragraph 4.2 of the report. 
WRITE-OFF OF NATIONAL NON-DOMESTIC RATES 2025/26 
A report was submitted by the Chief Officer – Resources seeking approval of
the write-off of debts in respect of National Non-Domestic Rates (NNDR), which had
been deemed as irrecoverable during the financial year 2025/2026. 
After discussion and having heard the Chief Officer – Resources in answer to a
Member’s question, the Committee agreed the write-off of NNDR accounts totalling
£150,933.73. 
CORPORATE SERVICES REVENUE BUDGETARY CONTROL REPORT
TO 31 OCTOBER 2025 (PERIOD 7) 
A report was submitted by the Chief Officer – Resources on the revenue financial
performance to 31 October 2025 of those services under the auspices of the
Corporate Services Committee. 
After discussion and having heard the Chief Officer – Resources and the Chief
Officer – Citizen, Culture and Facilities, in further explanation and in answer to
Members’ questions, the Committee agreed to note the contents of the report which
showed the revenue account was currently projected to underspend against budget
by £0.138m (0.34%of the total budget) at the year-end.
Page 9

Page 10

CORPORATE SERVICES CAPITAL BUDGETARY CONTROL REPORT
TO 31 OCTOBER 2025 (PERIOD 7) 
A report was submitted by the Chief Officer – Resources providing an update on the
Corporate Services capital programme to 31 October 2025. 
The Committee agreed:- 
(1) to note the current position of the 2025/26 capital budget for Corporate
Services; and 
(2) to note that the project life total was currently on track. 
The meeting closed at 2.21 p.m. 
Page 10

Page 11

Appendix 1
Table 1 – Existing Agreed ICT 1-Year Capital Plan
Capital allocation 2026/27
ICT Security & Resilience £387,000
ICT Modernisation £459,000
Total £841,000 
Table 2 – Proposed Projects ICT Capital Spend 2026-27
Description Capital (Est)
ICT Security & DR, Resilience £387,000
1. Replace Ageing Infrastructure Hardware £94,000
2. Security Compliance remediation £70,000
3. Security Resourcing - multi-year consultancy services £23,000
4. Internal ICT resource recharges £90,000
5. Security Patching Improvements £20,000
6. Cisco Enterprise Agreement £90,000
ICT Modernisation £459,000
1. Chromebooks Device replacement: (laptops, PCs,
chromebooks and mobile phones for both Corporate and
Education)
£336,000
2. Resources to Support a range of corporate projects. £123,000
Total £846,000 
Estimated Annual Revenue Spend over £10,000 (based on 2025-26)
Microsoft Enterprise Agreement Licences Phoenix 31.12.2028 £631,200
Wide Area Network SWAN 2.0 01.02.2033 £186,700
Social Work Case Management & Scheduler OLM 31.03.2026 £134,700
Cloud Telephony System BT 01.12.2030 £120,000
Integrated Housing Management System Aareon UK 07.02.2027 £115,100
Education MIS SEEMIS 02.05.2026 £105,500
Remote Access BT 31.12.2026 £97,000
M365 Education licenses Phoenix 01.07.2026 £83,500
Revenue & Benefits Northgate 31.03.2026 £79,600
Automation Software UI Path 01.02.2027 £74,400
Leisure Management MRM Gladstone 01.11.2026 £68,400
365 Cloud Backup Barracuda 31.10.2026 £67,800
Electronic Document Management Civica 31.03.2026 £57,800
Various/ Amalgamated Housing Benefits and Allocations Civica 31.03.2026 £57,800
Page 11

Page 12

Online Forms Granicus 30.11.2026 £49,000
Vulnerability Management Qualys Computacenter 24.12.2026 £39,500
Firewall Support BT 12.05.2029 £37,000
Planning & Building Uniform System IDOX 31.03.2026 £35,900
Job Costing CIS Core Accuris 30.01.2026 £32,600
Employability Case Management Advice Pro ACM 30.03.2026 £32,400
Security Filtering Management Infosec 04.06.2026 £31,900
Roads – Lighting, Collision, Flood Mgmt. WDM Various dates £31,400
Library Management Spydus Civica 1.12.2029 £29,100
Energy Management Navigator Inspired 01.04.2026 £27,500
Local Government Digital Transformation Scottish Gov. 31.03.2026 £27,400
Virtual Server Environment Support Phoenix/VMware 22.12.2025 £27,300
Corporate Arrears System Merchant 31.05.2026 £26,900
Flare Environmental Services Civica 31.03.2026 £26,900
GGP GIS software ESRI 31.03.2026 £26,700
Workforce Management Frontier 07.10.2026 £26,000
Freshservice ICT Service Desk Softcat 28.02.2026 £25,900
Backup Management Insight 31.12.2028 £25,800
Asset Management CIPFA 30.04.2026 £24,300
Performance Management system Ideagan 30.04.2026 £21,600
Server Maintenance Park Place 02.09.2026 £20,500
Election Management Avantguard IDOX 28.02.2026 £20,100
Vehicle Management Fleetmaster Trapeze UK 31.03.2026 £19,700
Education Gateway Glasgow C.C 06.06.2026 £17,600
Council Website Support Brace Digital 31.10.2026 £15,600
ORACLE ULA Oracle 05.04.2026 £14,800
ORBIS Northgate/NEC 31.03.2026 £14,800
Device Security Management Antivirus IT Bus Ltd. 26.06.2026 £13,900
Agresso support Hennessy IT 31.05.2027 £13,500
NBS Building RIBA 31.12.2028 £12,400
Housing Homeless database AVD 31.03.2026 £12,300
Health & Safety system Figtree 14.07.2026 £12,200
Council Meetings System Astech 30.04.2026 £11,900
Phishing simulation and training platform Metacompliance 11.06.2026 £11,800
Resource Booking System Omnijo 31.03.2026 £10,700 
Page 12

Page 13

JOINT CONSULTATIVE FORUM 
At a Meeting of the Joint Consultative Forum held in the Civic Space, 16 Church
Street, Dumbarton on Thursday, 12 March 2026 at 2.00 p.m. 
Present: Councillors Lawrence O’Neill, Martin Rooney and Gordon
Scanlan; Michael McCallion (EIS); William Whitehill (GMB); Joe
Keegan (SSTA); Audrey McKie (Unison); and Conor Farmer
(Unite). 
Attending: Victoria Rogers, Chief Officer – People and Technology; Alan
Douglas, Chief Officer – Regulatory and Regulatory; Gillian
Hamilton, Chief Education Officer; Amanda Graham, Chief
Officer – Citizen, Culture and Facilities; James Gallacher, ICT
Manager; Andrew Cameron, ICT Infrastructure Section Head;
Louise Hastings, Strategic People and Change Manager; and
Carly Chisholm, Committee Officer.   
Apologies: Apologies for absence were intimated on behalf of Councillors
David McBride, Michell McGinty, Chris Pollock and Hazel
Sorrell; David Scott (GMB); Peter Hessett – Chief Executive;
Gail Macfarlane, Chief Officer – Roads and Neighbourhood; and
Laurence Slavin, Chief Officer – Resources.   
Michael McCallion in the Chair 
DECLARATIONS OF INTEREST 
It was noted that there were no declarations of interest in the item of business on the
agenda. 
MINUTE OF PREVIOUS MEETING 
The Minute of Meeting of the Joint Consultative Forum held on 11 December 2025
was submitted and approved as a correct record. 
ITEM 6
Page 13

Page 14

PRESENTATION: PHISHING & UPDATE ON CYBER POSTURE 
Officers provided a presentation in relation to Phishing and Cyber Posture.  After
discussion, and having heard officers in answer to Members’ questions, the Forum
agreed to note the presentation.  The Members thanked the ICT team for their
extensive work contribution and commended them on responsiveness and
professionalism. 
TRADES UNION ISSUES 
The Forum noted that the Trades Union had not provided, in advance of the meeting,
any issues that they wished to raise. 
The meeting closed at 3:22 p.m. 
Page 14

Page 15

WEST DUNBARTONSHIRE COUNCIL 
Report by Chief Officer – Citizen, Culture and Facilities 
Corporate Services Committee 27 May 2026 
Subject: Citizen, Culture and Facilities 2025/26 - Year-end Progress and
Citizen, Culture and Facilities Delivery Plan 2026/27 
1 Purpose 
1.1 This report sets out the year-end progress of the 2025/26 Delivery Plan and
presents the new Delivery Plan for 2026/27. 
2 Recommendations 
2.1 It is recommended that Committee notes the progress achieved at year-end
and the new Plan for 2026/27. 
3 Background 
3.1 In line with the Strategic Planning & Performance Framework, each Chief
Officer develops an annual Delivery Plan which sets out actions to help deliver
the Strategic Plan and address the performance challenges and service
priorities identified in the planning process. The Plan also provides an
overview of services and resources, including employees and budgets, sets
out the performance indicators (PIs) for monitoring progress and considers the
relevant risks. 
4 Main Issues 
2025/26 Year-end Progress 
4.1 The 2025/26 Delivery Plan was presented to Corporate Services Committee
on 21 May 2025 and mid-year progress reported on 12 November 2025. 
4.2 Full details of year-end progress are set out in Appendix 1. 
ITEM 8
Page 15

Page 16

4.3 The progress of the Plan’s 27 actions is summarised below: 
Progress No. (%) 
Completed 24 (89%) 
Overdue 3 (11%) 
4.4 Overdue actions relate to the following and will be carried forward and
completed in 2026/27: 
• Progress funding application to support heritage activity programme for
Glencairn House -75%
• Launch public access to local history and archive collections – 75%
• Relocate Dumbarton Library to Glencairn House with new staffing model in
place – 80% 
4.5 Year-end data is available for 14 of the Plan’s 18 PIs. The performance of
those PIs is summarised below: 
Performance Against Target No. (%) 
Target met or exceeded 9 (64%) 
Target marginally missed 3 (21%) 
Target significantly missed 2 (15%) 
Performance Over Time No. (%) 
Improved over short term (or maintained high
level of performance)
6 (43%) 
Improved over longer term (or maintained high
level of performance)
5 (36%) 
4.6 Where target was significantly missed, this relates to the following PI’s: 
• % of residents satisfied with Council services overall: 49% against a target
of 70%.
• % of residents who feel the Council communicates with them well: 38%
against a target of 60% 
4.7 The full set of PIs will be reported through the Council’s annual performance
reporting process once all data becomes available. 
2026/27 Delivery Plan 
4.8 The 2026/27 Delivery Plan is set out at Appendix 2. 
4.9 Key priorities include: 
• Embed new contact centre telephony platform.  
Page 16

Page 17

• Continue to support relocation of Dumbarton library to Glencairn House,
and relocation of Library Services to Strathleven Place. Embed new
Libraires strategy, prepare for assessment under National Libraries
Service Framework and provide recommendations following Library
Services consultation. 
• Progress review of accessibility of the website and intranet and upgrade
content management system.
• Embed Facilities Management service redesign, consider the options to
develop an FM training academy and apprentice programme and
participate in the Council wide Good Food Nation Plan
• Develop strategic communication plan to support budget savings initiatives
and to support service changes.
• Plan heritage activity programme for Glencairn House, progress planning
for future decant of WDC collections to Strathleven Place. Progress a plan
to establish Culture Collective, secure re-accreditation for Clydebank
Museum and launch public access to the local history archive collections. 
• Support budget consultation, progress plans to strengthen approach to
strategic engagement and prepare plan for development of Strategic Plan
2027-32.         
4.10 Implementation of the Plan will be monitored by the management team with
mid-year and year-end progress reported to Corporate Services Committee
around November 2026 and May 2027 respectively. 
5 People Implications 
5.1 There are no direct people implications arising from this report. 
6 Financial & Procurement Implications 
6.1  There are no direct financial or procurement implications arising from this
report. 
7 Risk Analysis 
7.1 Failure to deliver on the actions assigned to Citizen, Culture and Facilities
may have a direct impact on the delivery of the Council’s Strategic Plan. It is
essential that remedial action is taken to ensure strategic delivery plans
achieve the commitments detailed. 
8 Equalities Impact Assessment 
8.1 Screening and impact assessments will be carried out on specific activities as
required. 
9 Consultation 
9.1  The delivery plans were developed through consultation with officers from the
strategic service areas. 
Page 17

Page 18

10 Strategic Assessment 
10.1  The delivery plans set out actions to support the successful delivery of the
strategic priorities and objectives of the Council. 
Chief Officer: Amanda Graham
Service Area:  Citizen, Culture and Facilities,
Date:   22 April 2026
_____________________________________________________________ 
Person to Contact:  Performance & Strategy Business Partner    
karen.Connelly@west-dunbarton.gov.uk 
Appendices:  Appendix 1: Citizen, Culture and Facilities Delivery Plan
2025/26 – Year-end Progress
Appendix 2: Citizen, Culture and Facilities Delivery Plan
2026/27 
Background Papers: Citizen, Culture and Facilities Delivery Plan 2025/26 -
Corporate Services Committee, 21 May 2025 
Citizen, Culture and Facilities Delivery Plan 2025/26 Mid-
year Progress - Corporate Services Committee, 12
November 2025 
Strategic Planning & Performance Framework 2022/27   
Wards Affected: All
Page 18

Page 19

Appendix 1 - CCF Delivery Plan Year-end Progress 25/26 
1. Our Communities 
Objective 2. Our residents health and wellbeing remains a priority 
Performance Indicator
2024/25 2025/26
Owner
Value Status Value Target Short Trend Long Trend Note
Number of attendances per 1,000 population for
indoor sports and leisure facilities 6,632  7,226 6,159  
Target exceeded with improvement
on previous year. Leisure Centre
usage continues to grow, in particular
through health & fitness activities
including gym and group fitness
classes
John Anderson
% of pupil medical dietary requests met 100%  100% 100%  
Target met. Requests for a medically
prescribed diet are considered
alongside information gathered from
Parent/Carers; Head Teachers;
General Practitioners; Dietitians;
Health Visitors; Speech and
Language Therapists and the school's
Catering Manager to ensure an
alternative menu can be provided. 
Sharon Jump
% of pupils who take up free school meals (P1-7) 76%  75% 75%  
Target met. Following Scottish
Government initiative, we are now
providing free school meals to pupils
currently in P6 & P7 if the
parent/carer receives the Scottish
Child Payment for the child. Working
Sharon Jump
ITEM 8 - APPENDIX 1
Page 19

Page 20

Performance Indicator
2024/25 2025/26
Owner
Value Status Value Target Short Trend Long Trend Note
with external agencies we have been
able to identify the pupils who are
entitled to free school meals and
ensure we have the appropriate
school meal provision in place. 
Action Status Progress Due Date Note Owner
Participate in the Council wide Good Food Plan   31-Mar-2026
Action complete. Initial meeting held with
representatives from Roads & Neighbourhood,
HSCP, Education, Resources November 2025 agreed
further meetings will be held in 2026 once outcome
national plan and implementation date of Local
Authority good food nation plans have to be
produced by has been confirmed.
Sharon Jump
Ensure appropriate free school meal provision
is in place   31-Mar-2026
Action complete. We are engaging with colleagues in
Education and across Revenue and Benefits service
to ensure the relevant data is being shared
timeously and all pupils who qualify for free school
meals are identified.
Sharon Jump 
Objective 3. Our residents are supported to increase life and learning skills 
Performance Indicator
2024/25 2025/26
Owner
Value Status Value Target Short Trend Long Trend Note
Total number of library issues (Physical and e-
Issues) 249,379  240,359 220,000  
Performance exceeded target.  When
compared with 24-25 there has been
a 6% increase in physical issues and
a decrease of 11% for e-issues. 
Increased promotion of digital book
borrowing is required for 26-27.
Stephen Daly
Page 20

Page 21

Performance Indicator
2024/25 2025/26
Owner
Value Status Value Target Short Trend Long Trend Note
Total number of visits to museums and heritage
centres (virtual & in person) 147,271  117,141 106,500  
Performance exceeded target. We are
continuing to see an increase in
visitor numbers and digital public
access is increasing. 
Lauren Crooks
Total number of library visits (physical and virtual) 474,519  670,214 384,996  
A significant increase of 41% when
compared with year 24-25.  This
increase is driven by virtual visits to
the library online catalogue since
moving to the new Library
Management System.  This may
demonstrate the increased user
experience in using and accessing the
catalogue along with more accurate
recording of virtual visit statistics. We
will review and increase the target
for 26/27. 
Stephen Daly
% Residents satisfied with Libraries 75%  80% 75%  
Target exceeded. We received 175
responses to this question with 141
satisfied with the service. 
Stephen Daly
% Satisfaction with museums & galleries 81%  78% 80%  
Performance marginally missed
target and down by 3% from
previous year. Of the 125 responses
to this question, 98 were satisfied
with the service. Comments include
lack of knowledge of where the
museums and galleries are and what
is on. 
Satisfaction data is now sourced from
the Council’s Citizens’ Panel. This
change has resulted in a smaller
respondent base, meaning that
variations in satisfaction levels are
more pronounced. As a result,
findings should be viewed as
indicative rather than fully
representative.
Progress of Glencairn, Clydebank
Heritage hub and conversion of
Dumbarton library should support
improved satisfaction.
Lauren Crooks
Page 21

Page 22

Action Status Progress Due Date Note Owner
Progress funding application to support heritage
activity programme for Glencairn House   31-Mar-2026
The action will be carried forward into 2025/26. 
Implementation has been delayed while options are
considered to ensure the activity programme is
delivered effectively once the venue is open.
Productive discussions with the Strathleven
Foundation have taken place, and elements of the
original proposal will now be incorporated into a
wider, funded Greenspace project.
Lauren Crooks
Prepare for opening of new Clydebank Museum
and Launch Heritage Programme   31-Mar-2026
Action Complete. Clydebank Museum and Local
History & Archives is now successfully open to the
public and the Museum Galleries Scotland (MGS)
funded Heritage Project Worker is now in post. The
activity programme is now underway; engagement
has been strong to date.
Lauren Crooks
Progress next phase of planning for future
decant of WDC collections to Strathleven   31-Mar-2026
Action progressing as planned. List of requirements
complete and available for next stage. We continue
to work with colleagues in Corporate Asset
Management as the Capital project plan progresses.
The mapping exercise for collections will take place
alongside this progression.   
Lauren Crooks
Launch public access to local history and
archive collections   31-Mar-2026
Action will carry over into 2026/27. The Ancestry
project is complete, with strong usage levels and
royalty payments now being received. The Content
Management System (CMS) element will carry over
into 2026/27 due to delays caused by a CMS
back‑end upgrade and server integration issues.
These have now been resolved, catalogue uploads
to Modes are complete, and the contractor is
finalising checks ahead of confirming a go‑live date.  
Lauren Crooks
Develop the co-located Faifley Community
Library and embed into branch network   31-Mar-2026
Action complete as planned. Visitor numbers remain
good following the move with an average of 500
visitors per month from November to January.
Children and parents are visiting the library after
school. We will continue to monitor the provision
and how this develops as the campus completes the
final phase of development. 
Stephen Daly
Relocate Dumbarton Library to Glencairn House
with new staffing model in place.   31-Mar-2026
Action overdue and will be carried forward into
2026/27. We continue to work closely with our
assets colleagues regarding the timeline for the
move to take place. Due to unexpected issues the
Stephen Daly
Page 22

Page 23

Action Status Progress Due Date Note Owner
new building has yet to be handed over to the
Service. Following handover, we plan a closure of 3
weeks to allow the move to take place. The mobile
library will offer library book borrowing services
outside Dumbarton Library to ensure a library
service continues for citizens throughout the move
period. Staffing operational plans for Glencairn have
been shared with managers.  
Create a strategy document for West
Dunbartonshire Libraries   31-Mar-2026
Action complete. Following public consultation 98%
of respondents see libraries as vital to their
community's future. The consultation feedback
highlighted 5 priorities for the service to deliver; 1.
Discovering new books, 2. Enjoying a Calm,
welcoming space, 3. Having lots of resources in one
place, 4.Getting helpful advice from staff, 5. Joining
in a range of activities and classes.  These priorities
have informed the 4 drafted Strategic
Aims.  Strategic Aim 1: Reading and Learning,
Strategic Aim 2: Fostering Community Wellbeing,
Strategic Aim 3: Empowering Connections, Strategic
Aim 4: Sustainable Development and Innovation. 
Stephen Daly
Develop and deliver the Libraries Empower
Connections Digital Offering   31-Mar-2026
Action complete. Tablet devices have been procured
along with an interactive screen within Clydebank
Library. Activities began with drop-in sessions for
citizens to seek advice on accessing online Council
services. The project then pivoted when a need was
identified and highlighted via the Performance and
Strategy Team regarding the need for digital
assistance for deaf people in accessing Council
services. A successful scoping meeting was held
with the group with the project funding BSL
Interpreters. The group were not previously aware
of library services and the digital services/classes on
offer or how to access Council services online. The
entire group joined the library at the session to be
able to access services. A programme has been
developed for the group to support the use of
devices to access library and other online services
which will run in November. The British Deaf
Association highlighted this as the first digital
programme specifically for deaf people in Scotland
tackling digital exclusion.  
Stephen Daly
Page 23

Page 24

Action Status Progress Due Date Note Owner
Contribute to Planning, Decant and Relocation
of Library Services from Poplar Road.   31-Mar-2026
Action complete. Libraries has progressed planning
for the relocation as far as possible at this time and
will continue to contribute to plans for relocation of
services from Poplar Road to Strathleven Place in
2026-27 in line with Assets Project Timeline. This
action will follow the move of Dumbarton Library to
Glencairn Library and Museum which is due for
handover to service May 2026.  
Stephen Daly 
4. Our Council 
Objective 10. Our workforce is resilient and skilled where digital technology supports service delivery for our residents 
Action Status Progress Due Date Note Owner
Develop and implement wellbeing, employee
engagement, equality and learning and
development plans to enable capabilities,
improve resilience and promotion of a diverse
workforce  
31-Mar-2026
Action complete. Work is underway to explore
automation options for a workforce scheduling tool
for Libraries, which may also be extended to the
Contact Centre depending on outcome. Facilities
management Service redesign is complete with
ongoing staff engagement in place.
All Managers
Implement service review process including
role design, use of new technology and new
ways of working to add resilience, address
gaps, and establish opportunities for
efficiencies  
31-Mar-2026
Action complete. Arts and Heritage service and
Facilities Management has implemented team and
structural changes to deliver the required saving for
2026/27, with structures reviewed against SOM. The
new FM service model strengthens resilience,
supporting staff absence management,
development, and career progression for frontline
staff.
In Libraries, work is underway to review and
develop management role profiles where these do
not currently exist, and frontline role profiles have
been updated to meet Programme For Government
All Managers
Page 24

Page 25

Action Status Progress Due Date Note Owner
(PFG) requirements. Within Contact Centres,
one-to-one reviews have identified service
improvements, which have been successfully
implemented across Reception and Contact Centre. 
Develop and implement learning and
development opportunities to improve
capabilities and resilience within the workforce.  
31-Mar-2026
Action complete. Performance is being proactively
managed with Facilities Management. The actions
being implemented by the management team will
continue. Council telephone performance reviewed
and reported to PMRG Sept 25. The service will
continue to monitor and report as required. Forum
of CCF senior managers to share best practice is in
place with regular diarised meetings. 
All Managers 
Objective 11. Our Council is adaptable and focused on delivering best value for our residents 
Performance Indicator
2024/25 2025/26
Owner
Value Status Value Target Short Trend Long Trend Note
Percentage of complaints received by the Council
that are resolved/ closed at Stage 1 83.75%   90%   Data will be available late May. Stephen Daly
Percentage of complaints received by the Council
that are resolved at Stage 2 4.5%   10%   Data will be available late May. Stephen Daly
% of telephone calls answered within 5 minutes by
Repairs Contact Centre as a proportion of all calls
answered.
86%  90% 90%  
Target met showing improvement
from previous year. Of over 39,300
calls received, 32,810 were answered
within 5 minutes. The data for
quarter 4 is up to 17 March when the
new telephony system was
introduced. Training on the reporting
from the system is underway.   
Stephen Daly
% of telephone calls answered within 3 minutes by
Contact Centre as a proportion of all calls
answered.
78%  79% 90%  
Target marginally missed with
improvement from last year. More
than 27,630 calls received. Of these
20,452 calls were answered within 3
Stephen Daly
Page 25

Page 26

Performance Indicator
2024/25 2025/26
Owner
Value Status Value Target Short Trend Long Trend Note
minutes. A further 4426 were
answered after 3 minutes. 
Reduced resourcing and increased
call volume relating to various
Council service issues contributed
alongside increased call handle time
due to increased complexity in calls
received. 
Residents satisfaction with Council services overall 71%  49% 70%  
Target significantly missed with a
downward trend from previous year.
Of the 304 responses, comments
include: dissatisfaction with the
service provided by a number of
services across the Council, the poor
condition of the local environment,
and high cost of Council Tax with
reduced services. Satisfaction data is
now sourced from the Council’s
Citizens’ Panel. This change has
resulted in a smaller respondent
base, meaning that variations in
satisfaction levels are more
pronounced. As a result, findings
should be viewed as indicative rather
than fully representative.
Lauren Crooks 
Action Status Progress Due Date Note Owner
Support upgrade to Contact Centre Telephony
Platform   31-Mar-2026
Action complete. New telephony system is now in
place, and a new corporate user group is being
established to support operational implementation
and use.
Stephen Daly
Facilities Management Service Redesign   31-Mar-2026
Action complete. Service redesign was implemented
successfully on 30th March 2026. This new model
will support efficiencies and was introduced
following extensive engagement followed by
matching and interview process for staff. 
Sharon Jump
Consider the options to develop an FM training
academy and apprentice programme   31-Mar-2026 Action complete. Discussions have taken place with
W4U and Education to identify options for Sharon Jump
Page 26

Page 27

Action Status Progress Due Date Note Owner
development of apprenticeship opportunities. Dates
are to be confirmed for participation at Careers
evenings and further engagement with Secondary
Head Teachers and W4U will be scheduled for
academic year August 2026. 
Risk Description Current
Assessment Target Assessment Date Reviewed Note Owner
Risk of Failure to meet
citizen expectation and
service standards
Risk of citizen dissatisfaction due to us
not doing what we say we will when we
say we will. 
01-Apr-2026
Demand to the Contact Centre
continues to be more complex and
outcomes to satisfy the Citizens are
much harder to achieve. This is also
visible on Social Media. Evidence to
support this is the service changes an
challenges within Waste Services, with
this and conditions of roads, speed of
response to Housing enquiries and
ongoing concerns to Housing Repair
updates being the most significant
number of calls to the Council. Citizens
are dissatisfied as indicated in the final
telephone survey. 
No change to risk matrix.
Stephen Daly
Failure to effectively
manage and learn from
complaints
There is a risk of damage to the
Council's reputation. If complaints are
not handled effectively, there can be an
adverse effect on the public perception
of the Council which can lead to a lack of
trust in the services provided.   
01-Apr-2026
Work continues to engage with
services and improve response times
and learning outcomes. 
The likelihood remains the same in
terms of no new evidence being visible
in how Services have improved their
processes by learning from complaints. 
No change to risk matrix
Stephen Daly 
Objective 12. Our residents are engaged and empowered
Page 27

Page 28

Performance Indicator
2024/25 2025/26
Owner
Value Status Value Target Short Trend Long Trend Note
Percentage of residents who are satisfied with the
Council website 84.2%  76% 85%  
Performance marginally missed
target and down by 8.2% from
previous year. Of the 259 responses,
comments include; some difficulty
navigating and finding required
information and slow or no response
to online enquiries. These enquiries
are managed by each service area
rather than the Web team.
Satisfaction data is now sourced from
the Council’s Citizens’ Panel. This
change has resulted in a smaller
respondent base, meaning that
variations in satisfaction levels are
more pronounced. As a result,
findings should be viewed as
indicative rather than fully
representative.  
Stephen Daly
% of stage 2 complaints responded to within 20
working days. 41%   100%   Data will be available late May. Stephen Daly
% of residents who feel the Council communicates
with them well.  53%  38% 60%  
Target significantly missed.
Performance has continued to reduce
although has been trending in red
status for some time. Of the 242
responses to this question,
comments include a view most
communication is online, a lack of
feedback on consultations, and view
generally only receive direct
communication for payments/ bills.
Satisfaction data is now sourced from
the Council’s Citizens’ Panel. This
change has resulted in a smaller
respondent base, meaning that
variations in satisfaction levels are
more pronounced. As a result,
findings should be viewed as
indicative rather than fully
representative.
Lauren Crooks
Page 28

Page 29

Performance Indicator
2024/25 2025/26
Owner
Value Status Value Target Short Trend Long Trend Note
No. of transactions undertaken online 64,048  60,857 59,000  
Target exceeded. Targets were
increased for 2025/26 based on
increased online transactions
including garden waste fees, and
West Dunbartonshire Leisure Trust
(WDLT) now using its own payment
system.
Stephen Daly
% of stage 1 complaints responded to within 5
working days. 95%   100%   Data will be available late May. Stephen Daly 
Action Status Progress Due Date Note Owner
Implement Arts and Heritage revised team and
service provision   31-Mar-2026
Action complete. A review of the team structure
including role profiles and tasks has been
undertaken and the amendments to service
provision have been agreed. 
Lauren Crooks
Review website coding to ensure it complies
with regulations   31-Mar-2026
Action complete. The external site is in a strong
position and was randomly selected 
by the Government Digital Services for an
accessibility audit: Both the sites accessibility
compliance and our accessibility statement were
determined as compliant.
Stephen Daly
Progress plan to enhance intranet accessibility   31-Mar-2026
Action complete. The intranet is a continuous issue
due to the number of editors able to edit and add
pages which can cause an issue with content. We
have reduced some of the easy to fix content and
coding issues in 2025/26.
Stephen Daly
Review website accessibility to ensure it
complies with regulations   31-Mar-2026
Action complete and will continue on an ongoing
basis to ensure compliance as new accessibility
regulations are introduced. Performance has
exceeded the original plan, with the external site
currently achieving 98% compliance.
Stephen Daly
Implement Contact Centre revised team and
service provision   31-Mar-2026
Action complete and savings delivered.  Ongoing
monitoring of Contact Centre performance will
continue and appropriate actions or proposals
considered as required.  
Stephen Daly
Page 29

Page 30

Action Status Progress Due Date Note Owner
Develop a communication plan to support
budget savings initiatives for 25/26   31-Mar-2026
Action complete. The communication plan was
extensive to ensure the key messages and changes
to frontline services was effective.  
Lauren Crooks
Carry out Strategic Needs Assessment to
support Strategic Plan 2027-2032.   31-Mar-2026
This action has been successfully completed.  Initial
analysis undertaken to give an overview of the
current and future needs of the local community to
identify priority areas of focus to reduce inequalities.
Further analysis will be undertaken in 2026/27  The
strategic needs assessment will form the basis of
future work to be undertaken in development of the
Council Strategic plan 2027-2032.
Lauren Crooks
Identify underrepresented groups and
implement actions to encourage better strategic
engagement and participation  
31-Mar-2026
This action has been successfully completed. We
have engaged with underrepresented groups around
the budget consultation ensuring a range of groups
had the opportunity to have their views reflected.
BSL users took part in digital classes to support BSL
users getting online to access key Council services
as well as building general digital confidence.
Through our engagement with young people during
the budget conversation, they have indicated they
would be interested in forming a dedicated young
persons Citizens Panel and we hosted the first in
March of this year where young people fed back on
a range of topics relating to living in West
Dunbartonshire as well as their commitment to
advance the young persons citizens Panel for future
years.   
Lauren Crooks
Carry out strategic engagement to support
budget consultation 2026/27   31-Mar-2026
This action has been successfully completed. To
support the Council budget consultation for
2026/27, a priority based survey was conducted
with the general population of West Dunbartonshire
and eight focus groups were carried out with a
range of community organisations, young people
and equality groups. The findings were presented to
Council on 29th October to assist Chief Officers and
Elected members understand the community
priorities. 
Lauren Crooks
Develop Equalities Outcomes and
Mainstreaming Plan 2025-29   31-Mar-2026
This action has been successfully completed. The
new Equalities Plan 25-29 has been developed and
now published as per our duties. The ensuing action
plan will be progressed over the 4 years of the plan
and reported to committee twice a year.
Lauren Crooks
Page 30

Page 31

Risk Description Current
Assessment Target Assessment Date Reviewed Note Owner
Risk of Ineffective
Communications /
Reputation Risk
Ineffective use of corporate
communication channels may result in
messages that are inconsistent with
authorised responsibilities or established
performance measures. Employees
without intranet access or email access
may not receive communications. Not
effectively managing corporate
responses to adverse events may lead to
an erosion of the Council's reputation.  
01-Apr-2026
A number of processes and strategies
are in place to ensure external and
external communication is effective
and protects the Council's reputation. 
No change to risk matrix 
Lauren Crooks  
Action Status   
Overdue 
Not on track 
In Progress and on track 
Completed 
PI Status 
Target significantly missed 
Target narrowly missed 
Target met or exceeded 
Long Term Trends 
Improving 
No change 
Getting worse 
Short Term Trends 
Improving 
No change 
Getting worse 
Page 31

Page 32

2026/27
CITIZEN, CULTURE AND
FACILITIES 
ITEM 8 - APPENDIX 2
Page 32

Page 33

APPENDIX 2   
Contents 
1. Introduction .................................................................................................................................................................................................... 3
2. Performance Review ...................................................................................................................................................................................... 3
3. Strategic Assessment .................................................................................................................................................................................... 6
4. Resources .................................................................................................................................................................................................... 13
Appendix 1: Action Plan .......................................................................................................................................................................................... 16 
Page 33

Page 34

1. Introduction 
Citizen, Culture and Facilities comprises a wide range of services covering Citizen Services, Strategic Communications, Facilities Management
& Town Hall, Libraries and Cultural Services and Performance and Strategy and monitoring of West Dumbartonshire Leisure Trust. It is one of
seven strategic areas responsible for delivering the Council’s Strategic Plan. Key actions to help achieve this are set out in this Delivery Plan,
together with actions to address any performance challenges and service priorities identified in the planning process. 
The progress of this Plan will be monitored and managed by the management team and reported to Corporate Services Committee twice yearly,
at mid-year and year-end. 
2. Performance Review 
The CCF management team completed a detailed review of 2025/26 performance, focusing on the following: 
• 2025/26 Delivery Plan year-end progress
• Local Government Benchmarking Framework (LGBF) comparative data
• Citizens’ Panel feedback;
• Complaints; and 
• Continuous Improvement 
This review highlighted our key achievements and challenges in 2025/26. These are summarised below. 
Key Achievements in 2025/26 
Listed below are some of the major achievements in each service area. All services achieve many other key outcomes for the Council and its
residents throughout the year which are not recorded here but are as important. 
Citizen, Libraries and Digital Services 
• External Funding was used by libraries to deliver digital sessions to local Deaf Community members. The British Deaf Association noted this
work as the first of its kind in Scotland. 
Page 34

Page 35

APPENDIX 2   
• Libraries obtained funding from Scottish Library and Information Council to establish its first Near Me Hub offering digital access to NHS
appointments from a private space in Clydebank Library 
• Government Digital Service (GDS) has concluded its second accessibility audit of WDC external website and confirms it meets the required
legal standards.
• Citizens Services processed significant number of Welfare Fund applications totaling 11,717. Of these 8815 were Crisis Grant and 2902 were
Community Care Grant 
• Contact Centre and Out of Hours service continued to work to identify ways to manage instances of unanticipated increases in call volumes
due to a number of unplanned events 
Facilities Management 
• New service model launched to enhance delivery, ensure resilience and support efficiencies.  
• Continued to secure income and bookings at Clydebank Town Hall hosting a variety of successful events including civic, awards, dance and
theatre shows and celebrations, in particular weddings. 
Strategic Communications, Culture & Performance 
• Provided comprehensive communications support for the budget process and implementation phase of service delivery changes as a result
of savings.
• Successful launch of the ancestry programme, including new income stream and strong public interest. 
• Successful opening and launch of Clydebank Museum and Heritage Hub.
• Developed and implemented budget consultation model with early engagement to inform the 2026/27 budget conversations and priorities.
• Provided a high level of equalities support during the budget process, ensuring Equality Impact Assessments (EIA) were completed
adequately for over 120 initiatives across the Council.   
Key Challenges in 2025/26 
Cross Service
• Resilience / Capacity Challenges. There is increasing demand and growing reliance on Citizen and Digital Services and Communications
to support the delivery of Council-wide efficiency savings. With reduced staffing levels and required changes to service delivery, overall
capacity is significantly impacted. This work frequently extends beyond planned timescales, delaying scheduled service specific initiatives as
Page 35

Page 36

APPENDIX 2   
a result. Going forward, strict prioritisation and new approaches to service delivery, including service redesign where appropriate, will be
essential.
• Absence due to sickness. There is a significant level of sickness absence within CCF and this affects levels of service, particularly as the
teams now lack the capacity or resilience to cover due to efficiencies which have reduced the workforce. This leads to reduced level of
service, increased management time spent supporting absence, increased pressure and impacts on staff morale. 
• Delays in the capital programme. Delays in the delivery of Glencairn House Library and Museum and the subsequent effect on the
development and delivery of the publicly accessible collections store and archive at Strathleven Place have impacted on service delivery and
service satisfaction in both Libraries and Arts and Heritage. This requires reprioritisation within the service in conjunction with our colleagues
from the Corporate Assets team as the programme timelines are pushed out. 
Citizen, Libraries and Digital Services 
• The unplanned demand for calls continues to impact resource and service satisfaction.  
• Changes to ways of working within services increase the complexity and volume of calls to the Contact Centres and place additional demand
on the service with longer call handle time, and more time to resolve issues. This has impacted on the Council reputation indicators and
increased social media attention.
• There continues to be an increase in the volume and complexity of complaints which increases the time and capacity taken to resolve. 
• Increased reliance on the web and intranet including the growth in the size and content means increased hosting and bandwidth costs, added
pressure to maintain quality, accessibility, security and a continuing need to ensure information remains current particularly with services
responsible for keeping the web team informed of any changes. 
Facilities Management.
• High levels of absence continue to have an impact on available resource resulting in reduced workforce numbers and increased costs and
demands on existing teams.
• The rate of turnover coupled with the time taken to recruit and train employees continued to be a challenge. 
Strategic Communications, Culture & Performance 
• The Communications and Arts & Heritage teams continued to operate without a full complement of staff for most of the year resulting in
increased demand on staff and alternative service models being introduced.
• Council-wide changes to ways of working have resulted in the need for more complex communications support which requires additional
capacity and requires extended input, and this has put additional pressure on the Communications team. 
Page 36

Page 37

APPENDIX 2   
3. Strategic Assessment 
The CCF management team completed a strategic assessment to determine the major influences on service delivery and priorities in 2026/27.
The key factors are summarised below. 
Key Factors 
Financial Challenges   
The entire public sector is continuing to face significant financial challenges due to a range of factors including inflationary cost increases, pay
awards not being fully funded by the Scottish Government and insufficient overall funding to support the delivery of front line and back-office
services. The Council is currently faced with an estimated cumulative funding gap in 2027/28 of £10.905m rising to £44.028m by 2030/31. We
will continue to monitor the overall financial position of the Council and updates on estimated future budget gaps will be reported to Elected
Members throughout 2026/27. 
These challenges require further action to balance our budget and protect services for residents. Within Citizen Culture and Facilities, this means
available funding will be reduced over time and we will need to reconfigure how we work, what we do, where we work, and potentially reduce the
number of people employed. In this context, we will aim to continue to provide a sustainable, quality service to internal and external clients,
employees and citizens. 
Budget Sensitivity Analysis
In reviewing the service budget projections, consideration has been given to sensitivity of these budgets, in particular for higher risk/ higher value
budgets which may have a significant impact on budgetary control and future budget projections. The analysis has considered sensitivity around
demand, costs and charges, and income levels. In CCF income budgets are more susceptible to fluctuations given the uncertainties surrounding
demand. Within this service, budgets identified as being more susceptible to fluctuations are the Town Hall in respect of rising utility costs and
Facilities Management as a result of pressure on food costs in Catering. The Town Hall is also susceptible to fluctuations depending on levels of
income that are achieved.
Leisure Trust Management Fee
Page 37

Page 38

APPENDIX 2 
The savings options agreed to deliver the 2026/27 budget have resulted in a reduction in the management fee paid to West Dunbartonshire
Leisure Trust (WDLT) for delivery of a range of leisure and sport services, including management of sport and leisure facilities, community
facilities, sports development, Active Schools, outdoor recreation facilities and events. The fee paid by the Council to WDLT for 2026/27 will be
reduced by 5%.
Citizen, Libraries and Digital Services 
Telephony Enhancements 
ICT have provided an upgraded corporate telephone system, this includes an upgrade to the contact centre telephony platform which will provide
more flexibility and functionality including call recording. In 2026/27 we will embed the system operationally, investigate and test the various
levels of functionality to maximise efficiency, provide resilience and help customers better. 
Reduce Contact Centre Resource
The savings options agreed to deliver the 2026/27 budget have resulted in a resource reduction in the Contact Centre. Currently Citizen
Services operates the Customer Contact Centre, Housing Repairs Contact Centre, the Scottish Welfare Fund, manages complains and provides
a reception at 16 Church Street. The Council recognises that for many people, their digital skills, literacy or deprivation can prevent them from
accessing the internet and for this reason it is important to maintain alternative means of contacting the Council. It is also recognised that for a
number of people the option to call rather than access services online is a preference rather than a necessity. Work will continue to promote
alternative methods of contacting or reporting issues to the Council including via email and the website. Over 2026/27 we will implement Contact
Centre revised team and service provision. 
Embed Libraries Strategy 
The Libraries Strategy document outlining a renewed vision and future operating model which aligns with local and national initiatives and
ambitions has been approved by management. In 2026/27 we will publish the strategy and continue to progress embedding it operationally with
all Libraries staff. 
Glencairn House – New Library Launch 
The redevelopment of Glencairn House into a combined museum/library facility via WDC’s successful Levelling Up Fund bid is nearing
completion and is being managed by Corporate Asset Management. The design includes relocation of Dumbarton Library to Glencairn House.
While relocation plans and a staffing model have been developed, unforeseen delays to completion and handover have impacted timescales.
Page 38

Page 39

APPENDIX 2   
Following handover in 2026 we will progress the relocation and launch the service to suit the new library and Children’s Library in addition we will
develop a programme of activities that establishes Glencairn House and the Children’s Library as a central hub for community engagement with
library services. We will explore how to optimise the use of the new immersive technology installed in the Children’s Library, funded by the
Strathleven Foundation, and assess its potential to support our efforts in engaging new audiences. 
Relocate Library Services  
Libraries’ main office functions will relocate from Poplar Road to Strathleven Place. Libraries will contribute to the project team leading on
services relocating. This includes the mobile library, home delivery service, Learning Services and Library support functions. This initiative is tied
to the completion of Glencairn House. In 2026/27 we will continue to support the progress of the relocation with our colleagues in Asset
Management.   
Library Services Consultation
West Dunbartonshire Libraries are at the heart of our communities supporting reading, literacy, lifelong learning, cultural engagement, and
community wellbeing as well as ensuring inclusive digital access and welcoming spaces for all. Demand for Council services, and the associated
delivery costs, are increasing year on year with there being insufficient funding to absorb these increases. Consequently, the Council needs to
consider how best to meet the needs of communities within the reduced resources available.
To ensure library services continue to meet the evolving needs of local communities, we carried out a consultation in November 2025 to gain
feedback into how libraries are used, any barriers to access, and which services and resources are most valued. We received over 250
responses. Over 2026/27 we will report the consultation findings and our recommendations to shape delivery, ensuring that library provision
remains inclusive, sustainable, and aligned with community priorities. 
National Library Service Framework 
The How Good is Our Public Library Service framework is designed for public library services to evaluate the quality and effectiveness of their
service provision, to consider the value and impact of their services, identify areas for improvement, and demonstrate their contribution to wider
policy goals. It is divided into three Quality Indicators. In 2026-27 libraries will prepare for assessment of Quality Indicator 1 – Supporting
Reading. The service will grade their provision using the six-point scale graded from unsatisfactory to excellent. This will then go forward for peer
review. The national framework has recently been updated and it’s essential for the service to undertake this work to maintain access to external
funding streams.   
Website and Intranet Accessibility  
Page 39

Page 40

APPENDIX 2   
Web Content Accessibility Guidelines (WCAG 2.2 AA) is the new minimum accessibility standard for all UK Government public sector websites
and mobile apps. The UK government is monitored to confirm compliance. Over 2026/27 we will put actions in place to make sure the content on
the website is still complaint with the new standards and build a plan to address issues with the intranet, where accessibility can be enhanced. In
addition to comply with the upgraded Guidelines we will review the coding of the website to ensure it still complies and address any issues. 
Upgrade Content Management System
We will upgrade the Content Management System from V13 to V17 to ensure the platform remains secure, stable and fully supported and
maintain compliance with modern standards. 
Facilities Management Services 
Facilities Management Improvement Plan - Service Redesign 
A review of the FM management structure was undertaken in 2022/23 to respond to Scottish Government policy changes and resultant service
expansion, provide additional support for frontline employees and ultimately deliver a more efficient and sustainable service. A revised
management structure was introduced in 2023/24, alongside new policies, procedures and a staff training programme and during 2024/25 a
proposal for a new operating model developed.  In 2025/26, further training was delivered, the frontline service was redesigned, and a new
operating model across catering, cleaning and janitorial services implemented, including new roles, role profiles and enhanced training. During
2026/27, the focus will be on embedding the new ways of working through continued training, mentoring and staff engagement. 
Training and Capacity  
Appropriate training is a key requirement for the Facilities Management (FM) service. Establishing a centrally located training academy would
strengthen the delivery of consistent training and support across FM teams. A standardised approach would reduce training time, inconsistency,
and errors, while supporting skills development, refresher training, and awareness of new industry developments. Enhanced training improves
staff capability, service efficiency, and overall performance, while also providing clear progression opportunities for employees. This approach
supports the development of a cross-skilled workforce, ensures sufficient staff capacity, and builds greater service resilience. Progress during
2025/26 was limited due to the capacity required for the service redesign. In 2026/27, we will continue to work with colleagues in Education and
Working4U to develop an apprenticeship programme and explore options for establishing a training academy at Clydebank Town Hall. 
Good Food Nation Plan
The Good Food Nation (Scotland) Act 2022 provides a framework to progress toward Scotland being a Good Food Nation where people benefit
from the food they produce, buy, cook and serve and eat each day. A national consultation on proposals for the plan is complete. In 2025/26 FM
Page 40

Page 41

APPENDIX 2   
worked alongside other service areas within the authority to review the outputs and understand the obligations as a result of the national work 
and inform the next steps in developing the required Council wide GFN plan. The commencement of section 10 of the Good Food Nation
(Scotland) Act 2022 begins the 12-month clock for relevant authorities (local authorities and territorial health boards) to produce “local” Good
Food Nation Plans with relevant authority Good Food Nation Plans due to be published on 1 April 2028. This plan will be Council wide and will
include a number of service areas. An internal working group has been established and will reconvene when the guidance from Scottish
Government is available. During 2026/27 we will work with other service areas to support the development of the Council wide action plan. 
Strategic Communications, Culture & Performance 
Strategic Communications Team 
Communication Plan to Support Budget Savings Initiatives
Following the budget meeting in March 2026, a number of savings options to balance the budget were agreed. There are a number of these
which will result in changes to the operation of frontline services and will require formal communications planning to ensure objectives are met,
target audiences are reached, and key messages are provided effectively. In 2026/27 bespoke communications plans will be developed to
support this activity in each service area. 
Communications Plans to Support Service changes – Operational support 
There is a growing number and diversity of service changes across the Council and the majority of these require strategic communications
support to help ensure residents clearly understand what is changing, why the change is happening, and how it will affect their experience. By
preparing communications plans in advance, the team ensures the Council is communicating in a way that is accessible, timely, and sensitive to
the diverse needs of the people who rely on our services. Each plan will identify which users may be most impacted, tailor information so it is
easy to understand, and choose the right channels. In 2026/27 we will work with Services across the council on the implementation of service
delivery changes to deliver proactive, transparent, and consistent communications plans to minimise disruption, support users through the
transition, and maintain trust by ensuring they feel informed. 
Arts & Heritage Team 
Glencairn House  
Work will continue to progress detailed exhibition design and content for the redevelopment of Glencairn House into a combined museum/library
facility. Following design workshops and feedback, content was developed to support an ambitious heritage activity programme for Glencairn
Page 41

Page 42

APPENDIX 2   
House. Glencairn House will open to the public as a new state of the art library and museum. The completion was delayed from 2025 with
handover anticipated spring 2026 and will mean the phased opening is expected June 2026. In 2026/27 we will continue to support this progress
and will further progress the plans to support a programme of heritage engagement for Glencairn House.
Strathleven Place
In tandem with the Glencairn House redevelopment, planning will commence on the current Dumbarton Library building on Strathleven Place to
be converted into a publicly accessible archive and collections store for the Council’s most important heritage objects and documents.
In 2025/26 A&H progressed plans to review the storage areas and collections to prepare for the future decant to Strathleven House. In 2026/27
A&H in conjunction with our Assets colleagues will prepare and progress a plan for the mapping of storage and capacity and the safe relocation
of all museums, fine art, local history & archival collections and the relocation of the Arts & Heritage team from Poplar Road to Strathleven Place.   
Launch public access to A&H collections
Arts and Heritage have introduced two digitisation projects into the service in 2024-25 both of which significantly increase public engagement
with the services’ museum, fine art, local history & archival collections. The Ancestry Project sees the digitisation of name rich archive resources
for use in genealogy has been successfully completed. MODES replaces the previous ADLIB system and will provide public access to local
collections, benefitting research and engagement with our resources, also allowing for the management and maintenance of collections records
by the service. We have encountered technical issues which has delayed the launch of the public access to the collections. Our colleagues in
ICT are working with the third party providers to agree a solution. In 2026/27 following the technical issues being resolved we will progress the
launch of 10 databases plus access to Newspapers.com which will give online public access to local historical newspaper articles for the first
time.   
Culture Collective Bid  
Creative Scotland are providing funding to establish a Culture Collective that brings together a wide range of local artists and community
partners. The aim is to co-design and deliver a programme of cultural and artistic activity that strengthens local identity, supports creative
practice, and responds to community needs. The proposed funding of around £200,000–£250,000 would enable us to commission artists,
support community-led projects, and build the local infrastructure and resources needed to ensure meaningful long-term cultural development. In
2026/27 we will open dialogue with Creative Scotland and explore available funding to establish a Culture Collective for West Dunbartonshire
over the coming years. 
Accreditation – Clydebank Museum 
Page 42

Page 43

APPENDIX 2   
We will progress work to secure re-accreditation for Clydebank Museum through the Museum Galleries Scotland Museum Accreditation
Scheme. Achieving this accreditation demonstrates that we meet nationally recognised museum standards, and supports our ability to access
future funding streams, including those restricted to accredited museums. As part of the process, we must evidence compliance with key
standards such as strong governance, robust collections management, high-quality public engagement, and effective care and preservation of
collections. This renewal will ensure the museum remains well-positioned for ongoing development and future investment. 
Performance & Strategy Team 
Strategic Engagement 
In line with the Council’s Strategic Plan, to ensure our residents are engaged and empowered we will continue to review and strengthen our
approach towards strategic engagement with a particular focus on increasing participation from seldom heard voices, improving how we
feedback results to the community and partners, and exploring best practice with engagement tools. We will support the Council with budget
consultations and continue to gather resident’s views through the Citizens Panel. In 2026/27 we will deliver on the ambitions of the Strategic
Planning and Performance Framework and support the Council budget consultation 2027/28. 
Strategic Planning - 2027-2032
In line with the Council’s approach to strategic planning, work will begin in 2026/27 to identify key priorities for the next five years based on
findings from the Strategic Needs Assessment (SNA). The Strategic Needs Assessment is a high-level document and a precursor to the
engagement with key stakeholders to develop the new Strategic Plan which will set the vision and direction for Council services over the five-
year period of 2027-2032. In 2026/27, we will deliver on the ambitions of the Strategic Planning and Performance Framework and we will
progress the development of the Strategic Plan 2027-32.   
Reduce Performance & Strategy Team Resource
The savings options agreed to deliver the 2026/27 budget have resulted in a resource reduction in the Performance and Strategy team. 
The P&S team is responsible for the Council’s core performance management, strategic planning, public performance reporting, benchmarking,
consultation, equality duties and data analysis. The team enables the Council to meet key statutory obligations, including best value and Equality
Act requirements, and supports Audit Scotland reporting and funding compliance. With major work on the Strategic Plan 2027-32 required
beginning in 2026, reduced staffing will mean prioritising statutory duties, resulting in limited support for operational performance, continuous
improvement and delivery planning across services. In 2026/27 we will progress plans to implement the revised team and service provision. 
Continuous Improvement
Page 43

Page 44

APPENDIX 2   
Continuous improvement is central to all that we do. The actions set out in this section, as well as those at an operational level not included in
this Delivery Plan, demonstrate our commitment to continuous improvement and take account of the wider Best Value focus on vision and
leadership; governance and accountability; effective use of resources; partnerships and collaborative working; working with communities;
sustainability and fairness and equality. 
Action Plan 
The challenges identified in Section 2 and the key factors identified in Section 3 have informed CCF priorities for 2026/27. Appendix 1 sets out
the action plan to address them. It also includes:
• performance indicators and targets that will enable progress to be monitored and reported to stakeholders
• strategic workforce actions to address workforce issues identified in the planning process; and 
• strategic and/or service risks. 
In relation to the latter, strategic risks represent the potential for the Council to take advantage of opportunities or fail to meet stated strategic
objectives and those that require strategic leadership. Service risks relate to service delivery and represent the potential for impact on individual
services, or the experience of those who work within the services, i.e. employees, partners, contractors and volunteers or service users and
clients in receipt of the services provided. In identifying the relevant risks for 2026/27 and actions to mitigate them, the aim is to improve or
maintain the current position (i.e. the current risk score) set out in the appendix. 
4. Resources 
Finance 
Citizen, Culture and Facilities has a revenue budget of £16.630m and no capital budget in 2026/27. A breakdown by service area is set out
below. We will make the best use of the resources available to deliver on key priority areas and secure external/match funding where this is
possible. 
Service Area Gross Expenditure
2026/27 (£m)
Gross Income
2026/27 (£m)
Net Expenditure
2026/27 (£m)
Capital Budget
2026/27 (£m)
Page 44

Page 45

APPENDIX 2   
Performance & Strategy 0.266   -    0.266  0
Communications and Marketing 0.323  -0.022  0.301  0
Citizen Service 1.770  -0.221  1.549  0
Libraries 2.043  -0.011  2.032  0
Arts and Heritage 0.303  -0.060  0.243  0
Clydebank Town Hall 0.513  -0.170  0.343  0
Facilities Management 0.677          - 0.677  0
Building Cleaning  2.552  -0.262  2.290  0
Building Cleaning - PPP 1.104  -1.105  0 0
Facilities Assistants 2.903  -0.066  2.837  0
Events 0.113  -0.093  0.020  0
Catering Services 6.953  -0.958  5.994  0
School Crossing Patrollers 0.074   -    0.075  0
Total 19.601 -2.970 16.630 0 
Employees 
Employee Numbers
The headcount and full-time equivalent staff in each service area (as of 31st March 2026) are as follows: 
Service Area Headcount FTE
Communications & Sales 5 5
Customer Services 39 32.4
Facilities Management (Including Town Hall) 564 358
Libraries 58 37.4
Arts & Heritage 4 3.5
Performance & Strategy  4 3.6
Page 45

Page 46

APPENDIX 2   
Absence in 2025/26 
The quarterly absence statistics for Citizen, Culture and Facilities are shown below together with the Council average for the same periods for
comparison. The figures have been higher than the Council average for 2025/26: 
Absence in 2025/26 Quarter 1 Quarter 2 Quarter 3 Quarter 4 Annual FTE days lost per
FTE employee
Citizen, Culture and Facilities  8.78% 6.53% 9.47% 9.94% 20.34
COUNCIL WIDE TOTAL 6.17% 5.39% 7.2% 7.65% 14.38  
TOTAL 674 439.9
Page 46

Page 47

APPENDIX 2   
Appendix 1: Action Plan   
1. Our Communities   
Objective 2. Our residents health and wellbeing remains a priority 
Performance Indicator Target 26-27 Owner
% of pupil medical dietary requests met  100% Sharon Jump
% of pupils who take up free school meals (P1-7) 75% Sharon Jump
Number of attendances per 1,000 population for indoor sports and leisure facilities 6200 John Anderson 
Action Due Date Owner
Participate in the Council wide Good Food Nation Plan 31-Mar-2027 Sharon Jump 
Objective 3. Our residents are supported to increase life and learning skills 
Performance Indicator Target 26-27 Owner
Total number of visits to funded and part funded museums and heritage centres (in person & virtual)  106,500 Lauren Crooks
% of adults satisfied with museums and galleries 80% Lauren Crooks
Total number of library visits (physical and virtual)  552,000 Stephen Daly
Total number of library issues (physical and e-issues) 220,000 Stephen Daly
% of adults satisfied with libraries 75% Stephen Daly
Page 47

Page 48

APPENDIX 2   
Action Due Date Owner
Plan and agree heritage activity programme for Glencairn House 31-Mar-2027 Lauren Crooks
Progress next phase of planning for future decant of WDC collections to Strathleven  31-Mar-2027 Lauren Crooks
Launch public access to local history and archive collections  31-Mar-2027 Lauren Crooks
Open dialogue with Creative Scotland to establish a Culture Collective for West Dunbartonshire 31-Mar-2027 Lauren Crooks
Progress and gain re-accreditation for Clydebank Museum  31-Mar-2027 Lauren Crooks
Embed new Libraries strategy. 31-Mar-2027 Stephen Daly
Contribute to the planning, decant and relocation of Library Services to Strathleven Pl  31-Mar-2027 Stephen Daly
Launch Glencairn House programme of Library activities. 31-Mar-2027 Stephen Daly
Provide recommendations following Library Services consultation 31-Mar-2027 Stephen Daly
Prepare for assessment under National Libraries Service Framework 31-Mar-2027 Stephen Daly 
4. Our Council 
Objective 10. Our workforce is resilient and skilled where digital technology supports service delivery for our residents 
Action Due Date Owner
Workforce Planning; Develop and implement wellbeing, employee engagement, equality and learning and
development plans to enable capabilities, improve resilience and promotion of a diverse workforce 31-Mar-2027 All Managers 
Workforce Planning; Develop and implement employee life cycle plans in line with the People First Strategy
to attract and retain the workforce.
31-Mar-2027 All Managers
Workforce Planning; Implement service review process including role design, use of new technology and
new ways of working to add resilience, address gaps, and establish opportunities for efficiencies
31-Mar-2027 All Managers
Page 48

Page 49

APPENDIX 2 
Action Due Date Owner
Workforce Planning; Develop and implement learning and development opportunities to improve capabilities
and resilience within the workforce.
31-Mar-2027 All Managers 
Objective 11. Our Council is adaptable and focused on delivering best value for our residents 
Performance Indicator Target 26-27 Owner
% of complaints received by the Council that are resolved at Stage 1 90% Stephen Daly
% of complaints received by the Council that are resolved at Stage 2 10% Stephen Daly
% of telephone calls answered within 3 minutes by Contact Centre as a proportion of all calls answered. 90% Stephen Daly
% of telephone calls answered within 5 minutes by Repairs Contact Centre as a proportion of all calls
answered.
90% Stephen Daly
Residents satisfaction with Council services overall 70% Lauren Crooks 
Action Due Date Owner
Embed new Contact Centre telephony platform. 31-Mar-2027 Stephen Daly
Implement Contact Centre revised team and service provision 31-Mar-2027 Stephen Daly
Following Facilities Management service redesign, embed new ways of working   31-Mar-2027 Sharon Jump
Consider the options to develop an FM training academy and apprentice programme  31-Mar-2027 Sharon Jump
Implement Performance & Strategy revised team and service provision 31-Mar-2027 Lauren Crooks
Adjust West Dunbartonshire Leisure Trust management fee 31-Mar-2027 Amanda Graham 
Page 49

Page 50

APPENDIX 2   
Risk Description Current Assessment Target Assessment Owner
Risk of failure to meet
citizen expectation and
service standards
Risk of citizen dissatisfaction due to us not doing what
we say we will when we say we will.  Stephen Daly
Failure to effectively
manage and learn from
complaints
There is a risk of damage to the Council's reputation.
If complaints are not handled effectively, there can be
an adverse effect on the public perception of the
Council which can lead to a lack of trust in the
services provided.   
Stephen Daly 
Objective 12. Our residents are engaged and empowered 
Performance Indicator Target 26-27 Owner
% of residents who are satisfied with the Council website 80% Stephen Daly
% of stage 1 complaints responded to within 5 working days. 100% Stephen Daly
% of stage 2 complaints responded to within 20 working days. 100% Stephen Daly
No. of transactions undertaken online 59,000 Stephen Daly
% of residents who feel the Council communicates well with them 60% Lauren Crooks 
Action Due Date Owner
Upgrade Content Management System 31-Mar-2027 Stephen Daly
Review website accessibility to ensure it complies with regulations 31-Mar-2027 Stephen Daly
Page 50

Page 51

APPENDIX 2   
Action Due Date Owner
Progress plan to enhance intranet accessibility 31-Mar-2027 Stephen Daly
Develop a communication plan to support budget savings initiatives for 26/27 31-Mar-2027 Lauren Crooks
Prepare a communications plan to support service changes 31-Mar-2027 Lauren Crooks
Support the West Dunbartonshire budget consultation for 27/28 31-Mar-2027 Lauren Crooks
Deliver on the ambitions of the Strategic Planning and Performance Framework 31-Mar-2027 Lauren Crooks
Progress the development of the Strategic Plan 2027-32  31-Mar-2027 Lauren Crooks 
Risk Description  Current Assessment Target Assessment Owner
Risk of Ineffective
Communications /
Reputation Risk
Ineffective use of corporate communication channels
may result in messages that are inconsistent with
authorised responsibilities or established performance
measures. Employees without intranet access or
email access may not receive communications. Not
effectively managing corporate responses to adverse
events may lead to an erosion of the Council's
reputation.  
Lauren Crooks 
Page 51

Page 52

Page 52

Page 53

WEST DUNBARTONSHIRE COUNCIL 
Report by Chief Officer – People and Technology 
Corporate Services Committee: 27 May 2026 
Subject:  People and Technology Delivery Plan 2025/26 - Year-end Progress
and Delivery Plan 2026/27 
1 Purpose 
1.1 This report sets out the year-end progress of the 2025/26 Delivery Plan and
presents the new Delivery Plan for 2026/27. 
2 Recommendations 
2.1 It is recommended that Committee note the progress achieved at year-end
and the new Plan for 2026/27. 
3 Background 
3.1 In line with the Strategic Planning & Performance Framework, each Chief
Officer develops an annual Delivery Plan which sets out actions to help deliver
the Strategic Plan and address the performance challenges and service
priorities identified in the planning process. The Plan also provides an
overview of services and resources, including employees and budgets, sets
out the performance indicators (PIs) for monitoring progress and considers the
relevant risks. 
4 Main Issues 
2025/26 Year-end Progress 
4.1 The 2025/26 Delivery Plan was presented to Corporate Services Committee
on 21 May 2025 and mid-year progress reported on 12 November 2025. 
4.2 Full details of year-end progress are set out in Appendix 1. 
ITEM 9
Page 53

Page 54

4.3 The progress of the Plan’s 23 actions is summarised below: 
Progress No. (%) 
Completed 22 (96%) 
Overdue 1 (4%) 
4.4 Overdue actions relate to the following and will be carried forward and
progressed in 2026/27:
• Continue to develop the Council and HSCP response to power resilience
arrangements - 75% complete 
4.5 Year-end data is available for 9 of the Plan’s 9 PIs. The performance of those
PIs is summarised below: 
Performance Against Target No. (%) 
Target met or exceeded 5 (55.5%) 
Target significantly missed 4 (44.5%)   
Performance Over Time No. (%) 
Improved over short term (or maintained high
level of performance)
7 (87.5%) 
Improved over longer term (or maintained high
level of performance)
7 (87.5%) 
4.6 Where target was significantly missed, this relates to the following PI’s: 
• % employee attendance improvement rate (teachers and local
government); -1.3% against a target of 1%. 
• % of our workforce who have declared a disability; 1.6% against a target of
2.2%.
• % of our workforce who have stated they are LGBT; 1.4% against a target
of 2.5%.
• % of Council employees who feel valued in the workplace; 40% against a
target of 75%. 
4.7 The full set of PIs will be reported through the Council’s annual performance
reporting process. 
2026/27 Delivery Plan 
4.8 The 2026/27 Delivery Plan is set out at Appendix 2. 
4.9 Key priorities include: 
Business Support (including Corporate Administration Support; Transactional      
HR and Pay) 
Page 54

Page 55

• Implement statutory pay and pension changes
• Undertake annual payroll audit
• Further explore automation to expedite payments
• Review leadership support 
ICT
• Further secure the Council’s technology infrastructure
• Implement next phase of Microsoft 265 SharePoint and One Drive
• Develop further cyber logging strategies to support Managed Detection
and Response (MDR) technology
• Complete review of devices due to be replaced
• Review and explore next generation technologies including Artificial
Intelligence (AI) agents 
People & Change
• Implement the Fit for Future review of Sickness Absence process and
procedure
• Continue to embed key Health and Safety practices. – Prioritise cross
skilling in and developing team knowledge of Health Surveillance.   
• Refine spending plans to support workforce development in light of the
reduction in Corporate Training Budget
• Prioritise digital improvements to Strategic HR service delivery.
• Progress the plan to mainstream digital transformation across the Council 
Resilience
• Maintain and manage the review process for Council and HSCP Core
Plans
• Manage and oversee the Business Continuity Process for the Council and
HSCP
• Continue to develop the Council and HSCP response and power resilience
arrangements 
4.10 Implementation of the Plan will be monitored by the management team with
mid-year and year-end progress reported to Corporate Services Committee
around November 2026 and May 2027 respectively. 
5 People Implications 
5.1 There are no direct people implications arising from this report. 
6 Financial & Procurement Implications 
6.1  There are no direct financial or procurement implications arising from this
report. 
7 Risk Analysis 
Page 55

Page 56

7.1 Failure to deliver on the actions assigned to People and Technology may
have a direct impact on the delivery of the Council’s Strategic Plan. It is
essential that remedial action is taken to ensure strategic delivery plans
achieve the commitments detailed. 
8 Equalities Impact Assessment 
8.1 Screening and impact assessments will be carried out on specific activities as
required. 
9 Consultation 
9.1  The delivery plans were developed through consultation with officers from the
strategic service areas. 
10 Strategic Assessment 
10.1  The delivery plans set out actions to support the successful delivery of the
strategic priorities and objectives of the Council. 
Chief Officer: Victoria Rogers
Service Area:  People and Technology
Date:   23 April 2026
_____________________________________________________________ 
Person to Contact:  Karen Connelly    
Performance & Strategy Business Partner
karen.Connelly@west-dunbarton.gov.uk 
Appendices:  Appendix 1: People and Technology Delivery Plan
2025/26 - Year-end Progress 
Appendix 2: People and Technology Delivery Plan
2026/27
Background Papers: People and Technology Delivery Plan 2025/26 -
Corporate Services Committee, 21 May 2025 
People and Technology Delivery Plan 2025/26 Mid-year
Progress - Corporate Services Committee, 12 November
2025 
Strategic Planning & Performance Framework 2022/27   
Wards Affected: All
Page 56

Page 57

Unmarked 
Appendix 1 - P&T Delivery Plan Year-end Progress 25/26 
4. Our Council 
Objective 10. Our workforce is resilient and skilled where digital technology supports service delivery for our residents 
Performance Indicator
2024/25 2025/26
Owner Value Status Value Target Short
Trend
Long
Trend Note
Percentage of ICT helpdesk incidents
fixed with half day of being logged. 78.03%  80.73% 70%  
Target exceeded with
continued improvement.
Overall, 13622 ICT helpdesk
incidents were resolved
within a half day of being
reported. The target for
26/27 will increase to 75%.
James
Gallacher
% of our workforce who have declared
a disability 1.4%  1.6% 2.2%  
Target missed although we
have seen a slight increase
in those who have disclosed
this information. Action
continues to encourage
Louise
Hastings
ITEM 9 - APPENDIX 1
Page 57

Page 58

Unmarked
Performance Indicator
2024/25 2025/26
Owner Value Status Value Target Short
Trend
Long
Trend Note
employees to provide
equalities data.
% of our workforce who have stated
they are LGBT 1.3%  1.4% 2.5%  
Target missed. Performance
has marginally increased.
The data for LGB and Trans
are collated separately and
therefore have been
reported separately. These
figures are a % of the total
workforce. 
Louise
Hastings
% of our workforce who are from a
Black minority ethnic group 0.7%  1% 1%  
Target met showing an
increase in those who have
disclosed Black minority
ethnic group.
Louise
Hastings
Disability pay gap -0.2%  -0.15% 10%  
Target met. Total workforce
who have declared a
disability average hourly rate
is £20.35. Total workforce
who have declared no
disability average hourly rate
is £20.32 
Louise
Hastings
The percentage of the highest paid 5%
employees who are women 62.2%  64% 50%  
Performance exceeds
target. A slight increase from
previous year in the number
of women within the top 5%
highest paid.
Louise
Hastings
Page 58

Page 59

Unmarked
Performance Indicator
2024/25 2025/26
Owner Value Status Value Target Short
Trend
Long
Trend Note
Gender pay gap 0.04%  -0.66% 3%  
Target exceeded. Female
average hourly rate is
£21.22 and Male average
hourly rate is £21.08.
Louise
Hastings
% employee attendance improvement
rate (teachers & local govt.) -4.3%  -1.3% 1%  
Target missed. It is
encouraging to note that the
improvement rate was
positive in Q1 and Q2 of
2025/26 however significant
increases in sickness
absence, particularly in Q4
of the year have meant that
the target has not been met.
Supporting employee
wellbeing remains a key
focus of the Council with the
current Fit for Future
programme focussed on
identifying process
improvements which will
further aide policy
compliance.  Employee
supports continue to be
communicated to the
workforce with additional
improvements to the
workforce console identified
to aide managers in the
Louise
Hastings
Page 59

Page 60

Unmarked
Performance Indicator
2024/25 2025/26
Owner Value Status Value Target Short
Trend
Long
Trend Note
effective management of
sickness absence. 
Percentage of Council employees who
feel valued in the workplace 45%  40% 75%  
The target has been missed
this year and is reflective of
challenges being reported in
the wider public
sector.  Whilst the decline is
disappointing, given the
ongoing financial challenges
that the Council faces and
the associated pressures on
services, it not
unexpected.  In their
"Analysis of the Public
Sector Workforce -
September 2025" report, the
Chartered Institute of
Personnel and Development
(CIPD) found that despite
strong motivations to serve
the public, employees report
that workload pressures and
resource constraints can
impact employee morale.  
Louise
Hastings 
Page 60

Page 61

Unmarked
Action Status Progress Due Date Note Owner
Maintain and manage the review
process for Council & HSCP Core
Plans  
31-Mar-2026
Action Complete. Multi agency
exercises for West Dunbartonshire
Councils 3 Control of Major Accident
Hazards (COMAH) sites successfully
completed. Report & Recommendations
for all 3 COMAH Sites shared as
required, with Health & Safety
Executive (HSE), Scottish
Environmental Protection Agency
(SEPA) and other relevant partners. 
All Internal & External Emergency Plans
and Multi-Agency Incident Response
Guides (MAIRGs) have been updated.
Contingency Planning Liaison Group
(CPLG) has now been established for
all 3 COMAH Sites. 
Scott
McFarlane
Manage and oversee the Business
Continuity Process for the Council
and HSCP  
31-Mar-2026
Action Complete. Plan reviewed and
updated with new sections added to the
BCP template in relation to Power
Resilience. The Business Impact
Analysis (BIA) has been updated to
align with the 4 main risks of disruption.
This information will then be transferred
to the SRG Essential Services
document to assist the SRG during an
incident. All BCP workshops have been
completed, these include an overview
of the Civil Contingencies Act, talk
Scott
McFarlane
Page 61

Page 62

Unmarked
Action Status Progress Due Date Note Owner
through the BC Plan and a few
scenarios.
Continue to develop the Council and
HSCP response and power
resilience arrangements  
31-Mar-2026
Action is ongoing. Provision of resilient
communications has progressed with
the 2nd Antenna installation completed
along with further testing. Some
additional work by Raynet, the third-
party provider is required to complete
the system. 
A second SRG Power Resilience
workshop has taken place to discuss
and progress all related work and
actions. There are a number of actions
that require to be progressed before
undertaking an exercise.     
Power resilience is a complex and
evolving area of work. No local authority
can be fully prepared for a national
power outage; however, mitigation and
preparedness activity continues to be
strengthened.
A national power outage presents a
range of uncertainties requiring
proportionate planning and assurance.
Work is ongoing to ensure that the
Council & HSCP are best prepared.  
Scott
McFarlane
Further secure the next phase of the
Council’s technology infrastructure   31-Mar-2026 Action complete. The final on premise
data will be migrated in April 2026. 
James
Gallacher
Page 62

Page 63

Unmarked
Action Status Progress Due Date Note Owner
Deliver next phase of fit for purpose
bandwidth capacity to all Council
locations  
31-Mar-2026
Action complete. This project has been
completed as anticipated with 80
council sites migrated to new SWAN2
network. These upgrades have
increased bandwidth capacity across
the council network and improved
network performance.
James
Gallacher
Develop and Implement next stage
of Microsoft 365 roadmap   31-Mar-2026
Action complete. This transformational
project has progressed well with over
70% of services now migrated to
SharePoint and One Drive. The final
Service roll out will be completed before
the end of 2026.  
James
Gallacher
Complete review of ICT devices due
to be replaced   31-Mar-2026
Action complete. All key workstreams
completed on time and services
provided with modern, robust and fit for
purpose laptops and PC's. 
James
Gallacher
Review and explore next generation
technologies   31-Mar-2026
Action complete. We have enabled use
of artificial intelligence, note taking and
automation tools across the council,
allowing employees to increase
productivity and reduce manual tasks.
James
Gallacher
Progress the plan to mainstream
digital transformation across the
council  
31-Mar-2026
Action complete. Highlights including
digital themes to support in upskilling
digital skills in the workforce. A digital
themed Senior Manager Network
(SMN) event and engagement of
workforce including elected members,
operational employee and senior
Louise Hastings
Page 63

Page 64

Unmarked
Action Status Progress Due Date Note Owner
leadership in the development of a Data
Strategy.
Workforce Planning: Develop and
implement wellbeing, employee
engagement, equality and learning
and development plans to enable
capabilities, improve resilience and
promotion of a diverse workforce  
31-Mar-2026
Action complete. To support P&C
restructure transition, we developed
and delivered wellbeing sessions and
did a review of purpose and scheduling
of P&C team meetings. These changes
will help to ensure that team
development and wellbeing is
supported within the reduced capacity
of the new team structure.
Louise Hastings
Workforce Planning: Develop and
implement employee life cycle plans
in line with the People First Strategy
to attract and retain the workforce.  
31-Mar-2026
Action complete. New role profiles
developed and tested.  Implementation
will commence in 2026/27 with
approach being considered in light of
reduced resource available.
Louise Hastings
Workforce Planning: Implement
service review process including
role design, use of new technology
and new ways of working to add
resilience, address gaps, and
establish opportunities for
efficiencies  
31-Mar-2026 Action complete. ICT restructure
completed in line with SOM compliance. Louise Hastings
Workforce Planning: Develop and
implement learning and
development opportunities to
improve capabilities and resilience
within the workforce.  
31-Mar-2026
Action complete. Strategic Human
Resources, HR Connect and Payroll
are in process of migrating to M365 and
Sharepoint, team meetings have taken
place to develop teams awareness of
Louise Hastings
Page 64

Page 65

Unmarked
Action Status Progress Due Date Note Owner
functionality and support resources
shared to develop skills. 
Risk Description Current
Assessment
Target
Assessment
Date
Reviewed Note Owner
Workforce
Management
System not fit for
purpose
There is a risk that the
WMS system is not fit-
for-purpose thereby
requiring manual
workarounds restricting
the level of automation
impacting on
efficiencies  
01-Apr-
2026
The system remains to contain
issues that requires the users to
engage in workaround making it
not as robust as one would
expect.  This is unlikely to
change. 
No change to risk matrix 
Arun Menon
Challenges in
protecting the Health
and Safety of
Employees and
Others
Failure to meet the
Council’s duty to protect
the health, safety and
welfare of its employees
and other people who
might be affected by its
business 
07-Apr-
2026
The Corporate H&S team
continue to review and
streamline key service areas,
including safety standards,
training, and health surveillance
in partnership with OH and
managers. They oversee
workplace inspections, audits,
risk assessments, fire safety
management, and specialist
monitoring across the Council.
Regular reporting to PMRG has
strengthened management
engagement and led to a
significant reduction in overdue
actions, supporting a more
Louise Hastings
Page 65

Page 66

Unmarked
Risk Description Current
Assessment
Target
Assessment
Date
Reviewed Note Owner
proactive approach to health
and safety. 
No change to risk matrix.
Complexities in
ensuring an
appropriately
resourced and
resilient workforce
Failure to ensure that
there is an appropriately
resourced and resilient
workforce in place to
meet future
organisational needs, in
effectively executing the
Council’s 2022-27
Strategic Plan. 
08-Apr-
2026
Workforce Planning Strategy in
place for 2022-2027. 
People First Strategy is in place
covering 2022-2027 and this is a
consolidation of a number of
areas: well-being, employee
engagement, workforce
planning, learning and
development and digital. 
WDC are recognised as leading
in terms of adapting flexible
working practices. Wellbeing
resources remain in place and
absence is closely monitored,
with stress and minor ailments
being the most common causes.
Employee communication
continues through multiple
channels, though engagement
levels have declined amid
financial pressures and
organisational restructuring.
Digital transformation is
Louise Hastings
Page 66

Page 67

Unmarked
Risk Description Current
Assessment
Target
Assessment
Date
Reviewed Note Owner
progressing through M365
SharePoint and the Fit for the
Future programme to improve
efficiency and wellbeing
processes, supported by digital
learning resources. Reductions
in people support functions have
increased pressures on service
delivery.  
No change to Risk Matrix
Keeping abreast of
developments in the
innovative use of
Information
Technologies
Failure to keep pace
with changing
technology environment  
07-Apr-
2026
The Council is delivering a
range of digital and service
improvement initiatives,
including the replacement of its
telephony system with a cloud-
based contact centre and
continued investment in cloud
services such as Microsoft
SharePoint and OneDrive.
Microsoft Copilot Chat has been
introduced to support employee
productivity, with further AI
solutions and automation under
development. ICT has
strengthened digital
infrastructure through the
completion of the SWAN
network upgrade and enhanced
James
Gallacher
Page 67

Page 68

Unmarked
Risk Description Current
Assessment
Target
Assessment
Date
Reviewed Note Owner
internet and data centre
capacity. New support services,
including an ICT live chat
function, have been well
received, while technology pilots
such as AI notetaking and new
finance and planning systems
continue to support service
transformation. 
No change to risk matrix.
Threat of Cyber-
attack
Data, systems and/or
infrastructure are
impacted as result of
security attacks which
are increasing in
number at a time when
this threat is already
placing demands on
resources to deliver
increased levels of
security controls. 
07-Apr-
2026
Cyber security continues to
present a high and inherent risk
for the Council due to sustained
and increasing levels of targeted
attacks across the UK public
sector, including recent incidents
affecting Scottish local
authorities. The threat
landscape is evolving, driven by
geopolitical tensions, particularly
state-sponsored activity, and the
growing sophistication of attack
methods such as ransomware,
advanced persistent threats,
phishing, and social
engineering. The increased
adoption of emerging
technologies, including artificial
James
Gallacher
Page 68

Page 69

Unmarked
Risk Description Current
Assessment
Target
Assessment
Date
Reviewed Note Owner
intelligence, alongside reliance
on third-party suppliers, further
expands the Council’s risk
exposure.
To mitigate these risks, the
Council is maintaining a strong
focus on proactive cyber
resilience measures. This
includes the implementation of
enhanced cyber incident
detection and response
capability, continuous
improvement of vulnerability and
patch management,
strengthened backup and
disaster recovery arrangements,
and ongoing staff awareness
through training and simulated
phishing exercises. Regular
engagement with ICT security
partners and adherence to
national guidance and standards
ensures continual assessment
and improvement of the
Council’s cyber security posture.
Progress continues in line with
the Public Sector Action Plan
and Public Sector Network
compliance requirements, with
Page 69

Page 70

Unmarked
Risk Description Current
Assessment
Target
Assessment
Date
Reviewed Note Owner
sustained vigilance aligned to
National Cyber Security Centre
and Scottish Government
guidance. 
No Change to Risk matrix 
Objective 11. Our Council is adaptable and focused on delivering best value for our residents 
Action Status Progress Due Date Note Owner
Implement CAS team reduction and
adjust service provision   31-Mar-2026
Action complete. This has now been
delivered, and budget has been
adjusted for start of the FY 2025/26.
Arun Menon
Undertake annual Payroll Audit   31-Mar-2026 Action completed as planned. Arun Menon
Implement statutory Payroll
changes   31-Mar-2026 Action complete. New financial year
statutory payroll updates implemented. Arun Menon
Progress outsourcing of Print Room   31-Mar-2026
Action complete. The migration is
progressing well with templates being
shared with supplier.  It is likely the print
work will commence after Council Tax
Annual Billing in April 26. 
Arun Menon
Implement ICT revised team
structure and adjust service
provision  
31-Mar-2026
Action complete.
Secondment/Development opportunity
in the Applications Team complete with
James
Gallacher
Page 70

Page 71

Unmarked
Action Status Progress Due Date Note Owner
secondment commencing October
2025. 
Review and implementation of the roles
needed within Device Team completed
September 2025.
Review of overlapping roles and
responsibilities across Server and
Applications Teams progressing.
Changes relating to SOM approved at
PMRG on 22nd September. 
Implementation planning in progress.
Implement the Fit for Future
programme of reviews.   31-Mar-2026
Action complete. The FfF review
focused on the corporate 'supporting
employee wellbeing' process.  Review
of the Return to Work (RTW) process is
complete, and improvements will be
implemented from 01/04/26. 
Louise Hastings
Continue to embed key Health and
Safety practices.   31-Mar-2026
Action complete. The Corporate H&S
team have completed KPI's for quarters
1 and 2 in line with our corporate plan
for 25 -26 and are moving on to the
Plan for 26-27.
Louise Hastings
Improve employee life cycle and
optimise employee development
opportunities  
31-Mar-2026
Action complete. Learning opportunities
across skills passports and digital
learning have been reviewed, updates
made where required, promotion of
national materials has been completed
where appropriate to ensure alignment
Louise Hastings
Page 71

Page 72

Unmarked
Action Status Progress Due Date Note Owner
and is being incorporated into next
years planned activity.  Role of Digi
Champs has been utilised through
M365 project and a more targeted
approach for the group's support is
being planned for next year.
Implement People & Change Team
Restructure including reduction of
Organisational Development Team  
31-Mar-2026
Action complete. Impact of review
complete and service delivery plan for
26/27 planned accordingly to reflect
reduced resource levels.
Louise Hastings
Undertake a strategic review of job
profiles across the Council   31-Mar-2026
Action complete. Template has been
developed and tested.  Soft launch
completed through live service
redesigns, implementation plan will be
carried out in 2026/27 to take account
of resource restrictions. 
Louise Hastings   
Action Status 
Cancelled 
Overdue 
Not on track 
In Progress and on track 
Completed 
Page 72

Page 73

Unmarked 
PI Status 
Target significantly missed 
Target narrowly missed 
Target met or exceeded  
Long Term Trends 
Improving 
No change 
Getting worse 
Short Term Trends 
Improving 
No change 
Getting worse 
Page 73

Page 74

2026-27
DELIVERY PLAN 
People and Technology 
ITEM 9 - APPENDIX 2
Page 74

Page 75

Contents
1. Introduction ............................................................................................................................................................................2
2. Performance Review .............................................................................................................................................................2
3. Strategic Assessment ............................................................................................................................................................6
4. Resources ........................................................................................................................................................................... 14 
Appendix 1: Action Plan ................................................................................................................................................................. 17 
Page 75

Page 76

1. Introduction 
People and Technology comprise a wide range of services covering Strategic HR, Organisational Development, Change and
Digital, ICT, Transactional Services (HR advice, pensions and pay), Health, Safety and Risk and Organisational Resilience. It is
one of seven strategic areas responsible for delivering the Council’s Strategic Plan. Key actions to help achieve that are set out
in this Delivery Plan, together with actions to address any performance issues and service priorities identified in the planning
process. 
The progress of this Plan will be monitored and managed by the management team and reported to Corporate Services
Committee bi-annually, at mid-year and year-end. 
2. Performance Review 
The management team completed a detailed review of 2025/26 performance, focusing on the following: 
• 2025/26 Delivery Plan year-end progress;
• Local Government Benchmarking Framework (LGBF) comparative data;
• National Digital Office programmes;
• Cabinet Office and Scottish Government Security compliance and guidance; and
• Continuous Improvement. 
This review highlighted our key achievements and challenges in 2025/26. These are summarised below. 
Key Achievements 2025/26 
Transactional Support
• Completed annual payroll audit and associated corrections.
• Processed Local Government Employees; Teachers and Chief Executive pay awards inclusive of significant and complex
arrears element. 
• Processed backdated salaries for a number of large-scale restructures and evaluations with complex arrears. 
• Implemented new Disclosure Scotland Act requirements Council wide.
Page 76

Page 77

• Continued improvements and development of all HR and Payroll online forms and automation efficiencies from associated
systems.
• Supporting the implementation of Resource Booker for Facilities Management Service.
• Implementation of HR21 upgrade to V5 with associated online training.
• Continued development of online forms across new process areas, enhancing data consistency and streamlining the data
collection and processing workflows.
• Continued cross-training teams across multiple functions, enhancing team resilience against a backdrop of reduced
resources and increased workload. 
ICT
• Completed the Scottish Wide Area Network (SWAN2) project by installing fit for future bandwidth at 80 Council sites including
upgrading the main data centre and internet lines.
• Upgraded main core network switches at Aurora data centre alongside installation of new firewalls to enhance security and
improve data throughput across the Council network.
• Implemented new telephony platform. The project has been highly successful, with all Council landline numbers migrating to
the new BT cloud solution. As part of the project, a new Council Contact Centre is now operational, providing enhanced
functionality that will improve communication with citizens.
• Completed Multi-Function Device (MFD) project by deploying new machines across Council offices.
• Introduced cross-organisation network access for NHS employees in Council buildings.
• Migrated Corporate and Education services to Microsoft 365 technology.
• Introduced Artificial Intelligence (AI) tools CoPilot and MS Teams Transcription across the Council.
• Implemented a new Cyber Incident and Response System to enhance protection of Council infrastructure.
• Introduced a new live chat support feature to connect users to ICT support analysts in real-time.
• Upskilled ICT employees with industry-standard training in infrastructure, 365, applications, device, and cyber security fields. 
• Restructured ICT service to ensure SOM compliance and service delivery improvements.
• Provided work placements in ICT for young citizens of West Dunbartonshire via W4U Thrive and Education Career Ready
programmes. 
People and Change
• Funding secured and work commenced on development of Council Data Strategy; the strategy will provide a foundation and
roadmap for data to be used as a strategic asset and unlock insights that have been blocked due to siloed, legacy systems. 
Page 77

Page 78

• New approach to Fit for Future launched with a focus on corporate processes.
• Content of Learning and Development programme reviewed and average rating from participants was 4.7 out of 5. 
• Health and Safety enhanced H&S committee reports with improved data and visuals, completed occupational noise risk
assessments, and delivered service audits against WDC Safety Management Standards.
• Promotion of Paid Work placements within Council services has resulted in entry level talent pool in a number of key
services. 
Business Resilience
• Supported a range of minor events and major incidents across the local area, working in support of multi-agency partners.
• Organised & facilitated Control of Major Accident Hazards (COMAH) exercises for WDC three COMAH Sites.
• Refreshed business continuity arrangements, working closely with services in focus group scenarios.
• Completed installation of a second antenna, phase 2 of the Raynet communications coverage, the first of its kind in Scotland,
and providing resilient communications in the event of an emergency/incident resulting in power outage. 
Key Challenges in 2025/26 
Resilience/ Capacity Challenges
• Across People and Technology, there are a range of challenges linked to a continuing and increased demand for support,
and a reliance on technology which is anticipated to be an ongoing pressure in future years. The workforce levels are now
outstripped by service demands. Over the last few years, we have encouraged services to become more self-reliant by
introducing self-serve and developing automation of key processes to promote efficiency in time-consuming tasks, however,
buy-in from wider service areas has been slow. Similarly, the take up of service champions to assist with key priorities, such
as digital transformation, has been a challenge with significant improvement required to support change. In 2026/27 we will
continue to promote automation and self-reliance. 
Transactional Services Challenges
• Operational demands with restructuring and evolution of the Council establishment requires increased input and associated
transactional processing from small Council wide supporting teams.
• HMRC statutory requirements for Salary Sacrifice Payrolling creating more work.
• Employment Rights Act will significantly change the operational requirements and associated employment rights with HR and
Payroll system updates required. 
Page 78

Page 79

• Introduction of iConnect reporting for Teachers’ pension scheme to Scottish Public Pension Agency.
• Demands on operational centres of expertise are increasing, with statutory requirements taking priority. However, ongoing
Council transactional demands persist, creating pressure and conflicts that require service expectations to be re-evaluated.
• CAS is experiencing a significant loss of talent, creating critical capacity gaps. Internal movement and limited internal
applicant pools mean that most new recruits are external, resulting in longer onboarding and training periods. This impacts
service continuity and increases the risk of delays in operational delivery during peak periods. Recruitment is underway, but
the dependency on external hires prolongs the time required to restore full capability. 
People and Change Challenges
• Ongoing financial pressures are driving increased restructures, placing further strain on Strategic HR; while mitigations and
digital improvements are in place, significant changes arising from the Employment Rights Bill add complexity and will
significantly limit wider service development, as already seen with the People First strategy.
• The change in focus of Fit for Future to corporate processes, will identify efficiencies in the process for managers however it
is anticipated that the improvements relating to data and insights will assist in policy compliance, in turn this may increase
demand on the Strategic HR further.  To mitigate against this, part of the review includes reviewing the supports in place that
enable managers to self-serve.
• While there is increasing demand for digital solutions, limited corporate capacity and operational pressures mean there is a
risk that employees do not develop the skills needed to use these tools effectively; services embedding digital skills
development into workforce planning is key to ensuring value is realised.
• Health & Safety will work to maintain visibility and require support and commitment from senior management whilst looking to
ensure compliance with statutory and legislative requirements and cross skilling the team members to improve service
resilience. 
• The People and Change team continues to face significant pressure from the pace and volume of organisational change,
including supporting employee wellbeing, skills development and engagement alongside major Council-wide initiatives such
as Microsoft 365 rollout, restructures, all within a context of limited resources and increasing workload. These factors are
impacting employee wellbeing, engagement and industrial relations, intensifying the role of the team, and creating a retention
risk for Strategic HR as team members can progress to external roles that may offer fewer pressures and greater resources. 
Page 79

Page 80

ICT Challenges 
▪ Cyber security risk: Managing an increasingly complex threat landscape, including modern cyber-attacks alongside
traditional risks such as physical access breaches, social engineering and impersonation. This requires a layered
approach spanning technology, processes and workforce awareness.
▪ Resource constraints and service delivery: Reduced ICT resources require adjustments to the service delivery model
with improved technology allowing capacity to be directed. There is still a reliance on capital-funded roles to support
service-led projects. From 31 March 2026, ICT resources will reduce further, leaving a single 3rd Line Network Analyst to
respond to critical incidents such as network outages. During these incidents there are options to allocate network support
resources from other ICT teams.
▪ Hybrid working pressures: Ensuring laptops are regularly returned onsite and connected to the internal network to
maintain security and device health. Sustained growth in demand for ICT support and technology to enable hybrid
working, alongside delivery of appointment-based support, service desk telephones, live chat and walk-up Tech Bar.
▪ Data resilience and cost pressures: Defining and maintaining robust backup strategies while managing data growth and
storage costs during a period of heightened cyber threat and ongoing budget constraints.
▪ Revenue cost growth: Increasing revenue pressures as suppliers continue to move from capital-based licensing models
to recurring revenue-funded arrangements.
▪ Skills and training: Significant challenges in maintaining appropriate technical and cyber skills following a 60% reduction
in the central ICT training budget. This has increased reliance on external government cyber funding and free training
resources to sustain industry-standard capability across the ICT workforce. 
Resilience
• The power resilience exercise has been delayed as some tasks have taken longer than anticipated to complete due to
competing priorities. 
3. Strategic Assessment 
The People and Technology management team completed a strategic assessment to determine the major influences on service
delivery and priorities in 2026/27. These are summarised below. 
Key Factors 
Page 80

Page 81

Financial Challenges 
The entire public sector is continuing to face significant financial challenges due to a range of factors including inflationary cost
increases, pay awards not being fully funded by the Scottish Government and insufficient overall funding to support the delivery
of front line and back-office services. The Council is currently faced with an estimated cumulative funding gap in 2027/28 of
£10.905m rising to £44.028m by 2030/31. We will continue to monitor the overall financial position of the Council and updates on
estimated future budget gaps will be reported to Elected Members throughout 2026/27. 
These challenges require further action to balance our budget and protect services for residents. Within People & Technology,
this means available funding will be reduced over time and we will need to reconfigure how we work, what we do, where we
work, and potentially reduce the number of people employed. In this context, we will aim to continue to provide a sustainable,
quality service to internal clients, employees and our citizens. 
Budget Sensitivity Analysis 
In reviewing the service budget projections, consideration has been given to sensitivity of these budgets, in particular for higher
risk/ higher value budgets which may have a significant impact on budgetary control and future budget projections. The analysis
has considered sensitivity around demand, costs and charges, and income levels. 
Within People and Technology budgets identified as being more susceptible to fluctuations include; ICT Computer Software, due
to technological updates, enhancements, security updates, integration, user base growth, regulatory compliance and inflation. 
Transactional Support 
Automation of Processes and Information Provision
Many employees across the Council are employed in manual processes and information provision, such as processing invoices
and updating transactional spreadsheets. Many such processes can be automated, providing benefits such as faster service
delivery, improved quality and greater flexibility, as well as enabling employees to refocus on more complex and meaningful
tasks rather than those that are repetitive and mundane. Progress on this action will be reported within Resources Delivery plan. 
Payroll
Page 81

Page 82

It is critical to ensure that employees are paid contractual and non-contractual payments accurately, in accordance with Terms
and Conditions of service, and in a timely manner. In 2026/27 we will continue to ensure compliance with all statutory
requirements and timelines. Annual actions include payroll audit and implementation of statutory payroll changes. 
Review Leadership Support following transfer to CAS
The savings options agreed to deliver the 2026/27 budget have resulted in a review of the Leadership Support Team. The
Leadership Support Team provides administrative and personal assistant support to the Chief Executive and Chief Officers of the
Council. There are synergies between the work of the Leadership Support Supervisor and that of Corporate Administrative
Support Team Leaders. Additionally, the introduction of AI-enabled transcribing of meetings and other digital solutions is likely to
reduce demand in Leadership Support Team, enabling the streamlining of work. The team has now transferred to the Corporate
Administrative Support, in advance of the saving option to reduce the number of Supervisor/Team Leader posts required. 
ICT 
The Council faces rapid technological change alongside ongoing budgetary and resource constraints. Demand for ICT services
continues to grow, driven by: 
▪ Rising citizen expectations for digital access and efficient services
▪ Financial pressures requiring cost-effective solutions
▪ Strategic transformation objectives across all service areas 
Infrastructure and Technology 
The Council has invested heavily in Microsoft 365 cloud services and has made significant progress on associated projects
throughout 2025/26. Phase 1 service areas have been migrated to SharePoint and OneDrive, and the main deliverable in
2026/27 is to complete migration for the remaining Council services and partner organisations Valuation Joint Board (VJB) and
Health and Social Care Partnership (HSCP). 
During 2026/27, our improvement programme will continue with the replacement of infrastructure switches at Council sites. This
project will enhance network performance throughout each upgraded site. In addition, wireless technology will be upgraded
further to deliver Wi‑Fi 6 capability across Council locations. Cloud technology will continue to gather pace throughout the year
as the Council strengthens resilience and implements improved backup and disaster recovery arrangements. 
Page 82

Page 83

Cyber Security
As reliance on digital technology continues to grow, so does the importance of protecting the systems and data that support vital
Council services. Local government is increasingly a target for cyber threats, and the organisation is committed to staying ahead
of these risks. The Council has made significant investments in cyber security, both in technology and in training for employees
to safeguard sensitive information and ensure the continuity of services that citizens rely on every day. This includes protecting
personal data and the digital infrastructure that underpins all Council technology. 
To improve security and lower cyber-attack risks, the Council has implemented a Managed Detection and Response (MDR)
system. This upgrade boosts cyber protection, enables new logging strategies through 2026/27, and supports ongoing
infrastructure security. 
AI Adoption and Future Strategy
The Council is accelerating the integration of Artificial Intelligence (AI), automation, and advanced machine learning to enhance
efficiency and resilience. AI tools such as Copilot are becoming standard across service areas with adoption increasing,
providing virtual assistance as resources tighten and workloads grow. 
Key Developments:
• Enhanced Copilot 365 versions will be deployed in 2026/27, enabling employees to streamline processes and boost
productivity.
• Next generation AI Agents will be explored by People and Technology teams. These intelligent systems can
autonomously perceive, reason, make decisions and act to complete tasks often without direct employee intervention,
unlocking further automation opportunities. 
Strategic Impact of AI use:
• Improved operational efficiency and resilience.
• Reduced manual workload for employees.
• Foundation for future innovation through autonomous AI-driven processes. 
ICT Device Review Project
ICT will undertake the annual device review project for PCs, laptops, and mobile phones that are reaching end of life and or 5-
year refresh point as per the ICT Strategy 2023-28. In 2026/27 we will complete review of devices due to be replaced and plan
for significant Chromebook device replacement throughout Education for 2027/28.
Page 83

Page 84

ICT Resources 
The savings measures agreed to deliver the 2026/27 budget have resulted in further reductions in ICT resources, leading to
continued loss of experience, skills, and knowledge within the team. ICT provides centralised services across the Council and its
partners, including the HSPC, West Dunbartonshire Leisure Trust, and the VJB. These services include the delivery and support
of network infrastructure, enabling hybrid access to critical business systems such as finance, social care, and housing. 
Additionally, ICT supports all schools and early years establishments to ensure technology for learning and teaching is
maintained, assisting teachers and young people in achieving educational outcomes. The reduction in resources will inevitably
lead to changes in service delivery and longer response times to outages. In 2026/27, ICT will continue to review team structures
and adjust service provision to align with reduced capacity, while prioritising critical services and maintaining compliance with
security and operational standards. Progress will be reported within ICT Workforce Plan. 
People and Change 
Fit for Future Reviews (FfF) and People First Strategy
A new approach to Fit for Future was adopted in 2025/26 with a particular focus on corporate processes, the first of which was
sickness absence. This is in line with the next stage of the employment life cycle outlined in the People First Strategy i.e.
retention and development and will be the focus of strategy work in 2026/27.  Using the same range of service design tools, the
corporate focus will mean that efficiencies can be achieved across the Council with data being utilised to measure where the
efficiencies arise and the associated saving. In relation to sickness absence, it is anticipated that duplication of effort will be
identified and removed, online forms will be improved and changes to further aid managers to effectively self service will be
identified.  Furthermore, opportunities to utilise AI will also be explored as will ways to improve the data insights gathered on
sickness absence. Over time, as more processes are reviewed a clear path will be visible as to where the changes have had an
impact. This approach also means that the benefit will be realised Council wide and aid services in identifying where similar
improvements and changes could be adapted for their own processes, essentially providing a blueprint for change.   
Enhancing Digital Service Delivery 
Following the completion of the People and Change restructure in 2025/26, Strategic HR is prioritising digital service
improvements to offset reduced team capacity, including greater self‑service for managers, expanded use of automation and AI,
improved intranet content, and increased channel shift towards a chatbot as the first point of contact. These changes are
Page 84

Page 85

intended to free capacity to focus on high‑demand areas such as restructures linked to savings, complex employee relations
cases, and upcoming Employment Rights Bill changes, whilst activity post restructure in the OD team will concentrate on core
service delivery. 
Health & Safety
The team will continue to target the ongoing delivery of our annual H&S plan as, through this, we have identified the necessary
priorities for the team to ensure ongoing Council compliance with statutory requirements and best H&S practice.  Poor H&S
practice creates significant risk for the Council both in terms of financial and reputational damage. Work will continue through this
programme of delivery to ensure that the team are cross skilled in key areas of work to support team resilience, particularly in
relation to Health Surveillance. 
Transformation and Continuous Improvement 
Digital Transformation
Key areas for the coming year will be the continued roll out of Microsoft 365, whereby ICT and the Change and Digital teams will
work jointly to support services with sound structures and best practice as they migrate to M365 collaboration services (MS
Teams, SharePoint and OneDrive).  In addition, work to build the data skills and knowledge in the Council will continue with the
Change and Digital team promoting learning opportunities available through Scottish Government’s Digital Skills Academy and
other providers as appropriate. This work will be strengthened by the development of a Data Strategy which will provide the
foundations needed to ensure that data is used as a strategic asset in the Council and leveraged to inform decision making,
ensuring that the insights gained from data within the Council are meaningful and evidence based. Work will continue through
the workforce planning process to ensure that services are continuing to consider development needs in relation to data and
digital solutions.
The level of resource available to progress this work Council wide will likely have an impact on the pace of change and whilst
some digital solutions can be implemented quickly, there is a risk that the realisation of benefits could be hampered if services
don’t drive forward changes in behaviour. Support will remain available through the continued roll out of M365/Sharepoint and by
ensuring that the work of the Change and Digital team is visible, will demonstrate how service design can be used to drive
forward change and provide a blueprint through the Fit for Future programme. This will be complemented by the work being
undertaken nationally by Society of Local Authority Chief Executives and Senior Managers SOLACE/Improvement Service with
regards to the ‘Digital 2 Be State’ for local government in Scotland.
Page 85

Page 86

The work will be further strengthened through the development and implementation of the Data Strategy which will provide the
foundations to ensure that services are able to maximise the insights gained from data and remove barriers created by legacy
systems. We will also continue to support development of the Workforce Management System (WMS) to aid wider process and
digital transformation and continue to develop automations within transactional processes through collaborative practice, service
design and maximising digital practice. Technology is developing quickly and the Council needs to ensure that they keep pace in
order to capitalise on the benefits this brings to service improvement, costs and delivery. This must be looked at collaboratively
with users and employees to ensure understanding, best practice and skills required. In 2026/27 we will continue to progress our
plan to mainstream digital transformation across the Council. 
Corporate Training Budget
The savings options agreed to deliver the 2026/27 budget have resulted in a reduction to the Council's corporate training budget.
It funds workforce development activities such as i-learn modules, leadership programmes (Modern Leaders, Inspiring Leaders),
and digital tools. In addition, it supports specific needs including retraining displaced employees and service-driven requests
identified through workforce planning. The reduction of £15,000 reduces the level of support available. 
Business Resilience 
Service Core Plans
The Civil Contingencies Officer has continued to support West Dunbartonshire’s resilience planning, and response arrangements
to ensure adequate officers are trained at all levels throughout the Council and HSCP to support the Council’s response to any
incident within West Dunbartonshire. Various plans have been developed and are reviewed annually; these assist with the
Councils readiness to respond to emergencies and other unplanned events. In 2026/27 we will continue to maintain and manage
the review process for Council & HSCP Core Plans, this will include an exercise to test the draft incident response plan for
relocation of residents following evacuation in care homes. 
Business Continuity 
This includes managing the Council and HSCPs Business Continuity Plans (BCPs), this process is typically reviewed on an
annual basis or following an incident or an event to ensure they remain fit for purpose. All BCPs essentially feed into the
Strategic Business Continuity plan to provide reassurances to Chief Executive and Chief Officers that essential services have
been considered, and adequate risk measures are put in place to minimise disruption. In 2026/27 an updated Business Impact
Analysis (BIA) will be added, this will produce a definitive list of all Council & HSCP Essential Services, in order of priority.
Page 86

Page 87

Incident Stand Down guidance will also be included in this iteration. CCS will continue to Manage and oversee the Business
Continuity Process for the Council and HSCP. 
Power Resilience
Power Resilience differs from Business Continuity Planning due to the complexities surrounding this risk. The aim of this work is
to provide a robust and tested framework for the Council’s Power Resilience arrangements to a National Electricity Transmission
System (NETS) failure incident. The purpose of this work is to provide confidence to the Chief Executive and Chief Officers that
service managers have considered this risk, applied mitigation measures and raised awareness across their service, especially
with employees. In 2026/27 we will introduce a new system to prioritise all Council & HSCP Essential Services, along with a new
template to capture them. New Assurance Checklists will detail how each Service will aim to deliver each Essential Service, and
at the same time prioritising those most at risk / vulnerable within our community. In 2026/27 we will continue to develop the
Council and HSCP response and power resilience arrangements, including processing the testing of the Council/ Raynet project,
which includes the installation of two antenna in the local area. A suite of documents to manage and support this response, is
also required.
Continuous Improvement
Continuous improvement is central to all that we do. The actions set out in this section as well as those at an operational level
not included in this Delivery Plan, demonstrate our commitment to continuous improvement and take account of the wider Best
Value focus on vision and leadership; governance and accountability; effective use of resources; partnerships and collaborative
working; working with communities; sustainability; and fairness and equality. 
Action Plan 
The challenges identified in Section 2 and the key factors identified in Section 3 have informed P&T priorities for 2025/26.
Appendix 1 sets out the action plan to address them. It also includes:
• performance indicators and targets that will enable progress to be monitored and reported to stakeholders
• strategic workforce actions to address workforce issues identified in the planning process; and 
• strategic and/or service risks. 
In relation to the latter, strategic risks represent the potential for the Council to take advantage of opportunities or fail to meet
stated strategic objectives and those that require strategic leadership. Service risks relate to service delivery and represent the
potential for impact on individual services, or the experience of those who work within the services, i.e. employees, partners,
Page 87

Page 88

contractors and volunteers or service users and clients in receipt of the services provided. In identifying the relevant risks for
2026/27 and actions to mitigate them, the aim is to improve or maintain the current position (i.e. the current risk score) set out in
the appendix. 
4. Resources 
Finance 
People and Technology have a net revenue budget of £11.289m and a capital budget of £0.954m in 2026/27. A breakdown by
section is set out below. A significant amount of budget allocated to ICT covers centralised systems. We will make the best use
of the resources available to deliver on key priority areas and secure external/match funding where this is possible. 
Service Area Gross Expenditure
2026/27 (£m)
Gross Income
2026/27 (£m)
Net Expenditure
2026/27 (£m)
Capital Budget
2026/27 (£m)
Transactional  1.083  -0.051 1.032  0
Strategic People & Change  2.062  -0.056  2.006  0.108
ICT  5.986  -0.521  5.465  0.850
Central Admin Support  2.865  -0.078  2.786  0
Total 11.995  -0.706  11.289  0.954 
Employees 
Employee Numbers 
The headcount and full-time equivalent employees in each section (as of 31st March 2026) are as follows:
Service Area Headcount FTE
Business Support (Corporate Admin Support, HR & Payroll
Service Centre)
113 (HR: 23; CAS: 90) 100 (HR: 20.8; CAS: 79.2)
Page 88

Page 89

Absence in 2025/26 
The quarterly absence statistics for People and Technology are shown below together with the Council average for the same
periods for comparison. The figures for People and Technology have been lower than the Council average throughout 2025/26. 
Absence in 2025/26 Quarter 1 Quarter 2 Quarter 3 Quarter 4 Annual FTE days lost per FTE employee
P&T Service  1.75% 0.26% 1.15% 1.33% 2.95
COUNCIL WIDE TOTAL 6.17% 5.39% 7.2% 7.65% 14.38 
People & Change (Strategic HR, H&S, Risk, Change, OD
& Digital)
29 27.2
ICT 55 51.2
TOTAL 197 178.4
Page 89

Page 90

Appendix 1: Action Plan 
4. Our Council 
Objective 10. Our workforce is resilient and skilled where digital technology supports service delivery for our residents 
Performance Indicator 2026/27 
Target Owner
Percentage of ICT helpdesk incidents fixed with half day of being logged. 75% James Gallacher
% of our workforce who have declared a disability 2.2% Louise Hastings
% of our workforce who have stated they are LGBT 2.5% Louise Hastings
% of our workforce who are from a black minority ethnic group 1% Louise Hastings
Disability pay gap 10% Louise Hastings
The percentage of the highest paid 5% employees who are women 50% Louise Hastings
Gender pay gap 3% Louise Hastings
Percentage of Council employees who agree or strongly agree that in general, they feel valued in their role at
WDC
75% Louise Hastings
% employee attendance improvement rate (teachers & local govt.) 1% Louise Hastings 
Page 90

Page 91

Action Due Date Owner
Further secure the next phase of the Council’s technology infrastructure  31 Mar 2027 James Gallacher
Implement next phase of Microsoft 365 SharePoint & One Drive  31 Mar 2027 James Gallacher
Develop further cyber logging strategies to support MDR technology 31 Mar 2027 James Gallacher
Review and explore next generation technologies including AI agents 31 Mar 2027 James Gallacher
Complete review of devices due to be replaced 31 Mar 2027 James Gallacher
Maintain and manage the review process for Council & HSCP Core Plans 31 Mar 2027 Scott McFarlane
Manage and oversee the Business Continuity Process for the Council and HSCP 31 Mar 2027 Scott McFarlane
Continue to develop the Council and HSCP response and power resilience arrangements 31 Mar 2027 Scott McFarlane
Review Leadership Support function, identify improvements and implement changes 31 Mar 2027 Arun Menon
Work jointly with Strategic People & Change to implement changes arising from ERA 2025 31 Mar 2027 Arun Menon
Progress the plan to mainstream digital transformation across the Council 31 Mar 2027 Louise Hastings
Prioritise digital improvements to Strategic HR service delivery 31 Mar 2027 Louise Hastings
Workforce Planning: Develop and implement wellbeing, employee engagement, equality and learning and
development plans to enable capabilities, improve resilience and promotion of a diverse workforce 31 Mar 2027 All Managers
Workforce Planning: Develop and implement employee life cycle plans in line with the People First Strategy
to attract and retain the workforce 31 Mar 2027 All Managers
Workforce Planning: Implement service review process including role design, use of new technology and new
ways of working to add resilience, address gaps, and establish opportunities for efficiencies  31 Mar 2027 All Managers
Page 91

Page 92

Action Due Date Owner
Workforce Planning: Develop and implement learning and development opportunities to improve capabilities
and resilience within the workforce. 31 Mar 2027 All Managers 
Risk Description Current
Assessment Target Assessment Owner
Workforce
Management System
not fit for purpose
There is a risk that the WMS system is not fit-for-purpose
thereby requiring manual workarounds restricting the
level of automation impacting on efficiencies  
Arun Menon
Challenges in
protecting the Health
and Safety of
Employees and
Others
Failure to meet the Council’s duty to protect the health,
safety and welfare of its employees and other people
who might be affected by its business    
Louise Hastings
Complexities in
ensuring an
appropriately
resourced and
resilient workforce
Failure to ensure that there is an appropriately resourced
and resilient workforce in place to meet future
organisational needs, in effectively executing the
Council’s 2022-27 Strategic Plan.    
Louise Hastings
Threat of Cyber-attack
Data, systems and/or infrastructure are impacted as
result of security attacks which are increasing in number
at a time when this threat is already placing demands on
resources to deliver increased levels of security controls.    
James Gallacher
Page 92

Page 93

Risk Description Current
Assessment Target Assessment Owner
Keeping abreast of
developments in the
innovative use of
Information
Technologies
Failure to keep pace with changing technology
environment     James Gallacher 
Objective 11. Our Council is adaptable and focused on delivering best value for our residents 
Action Due Date Owner
Implement statutory payroll changes 31 Mar 2027 Arun Menon
Undertake annual payroll audit 31 Mar 2027 Arun Menon
Review leadership support and explore transfer to CAS 31 Mar 2027 Arun Menon
Implement the Fit for Future review of Sickness Absence process and procedure 31 Mar 2027 Louise Hastings
Continue to embed key Health and Safety practices. – Prioritise cross skilling in and developing team
knowledge of Health Surveillance.   
31 Mar 2027 Louise Hastings
Implement reduction in Corporate Training Budget 31 Mar 2027 Louise Hastings 
Page 93

Page 94

Page 94

Page 95

WEST DUNBARTONSHIRE COUNCIL 
Report by Chief Officer - Regulatory & Regeneration 
Committee: Corporate Services Committee 27 May 2026 
Subject: Regulatory & Regeneration Delivery Plan 2025/26 - Year-end Progress
& Regulatory & Regeneration Delivery Plan 2026/27 
1 Purpose 
1.1 This report sets out the year-end progress of the 2025/26 Delivery Plan and
presents the new Delivery Plan for 2026/27. 
2 Recommendations 
2.1 It is recommended that Committee notes the progress achieved at year-end
and the new Plan for 2026/27. 
3 Background 
3.1 In line with the Strategic Planning & Performance Framework, each Chief
Officer develops an annual Delivery Plan which sets out actions to help deliver
the Strategic Plan and address the performance challenges and service
priorities identified in the planning process. The Plan also provides an
overview of services and resources, including employees and budgets, sets
out the performance indicators (PIs) for monitoring progress and considers the
relevant risks. 
4 Main Issues 
2025/26 Year-end Progress 
4.1 The 2025/26 Delivery Plan was presented to Corporate Services Committee
on 21 May 2025 and mid-year progress reported on 12 November 2025. 
4.2 Full details of year-end progress are set out in Appendix 1. 
4.3 The progress of the Plan’s 34 actions is summarised below: 
Progress No. (%) 
Completed 28 (82%) 
Overdue 5 (15%) 
Cancelled  1 (3%)   
4.4 Overdue actions relate to the following and will be carried forward and
completed in 2026/27: 
ITEM 10
Page 95

Page 96

• Develop the Local Heat and Energy Efficiency Strategy Delivery Plan -
50% complete
• Produce a planning focused delivery programme to support key
regeneration sites and enable high quality development to be achieved on
the ground - 25% complete
• Explore commercial opportunities in our town centres and wider
regeneration sites - 75% complete
• Prepare a robust evidence report for the next Local Development Plan
(LDP3) for submission for Gatecheck to Scottish Government Planning
and Environmental Appeals Division - 50% complete
• Review processes and procedures within Legal Services’ Commercial &
Place and Citizen & Regulatory teams - 75% complete 
4.5 Year-end data is available for 16 of the Plan’s 26 PIs. The performance of
those PIs is summarised below: 
Performance Against Target No. (%) 
Target met or exceeded 9 of 16 (56%) 
Target narrowly missed 1 of 16 (6%) 
Target significantly missed 6 of 16 (38%)
Performance Over Time
(As 4 of the 16 PIs are new for 2025/26, this section relates to 12 PIs)
No. (%) 
Improved over short term (or maintained a high level
of performance)
5 of 12 (42%) 
Improved over longer term (or maintained a high
level of performance)
4 of 12 (33%) 
4.6 Targets that were significantly missed relate to the following PIs:
• Percentage of planned underage sales visits carried out by Trading
Standards to premises registered on the Scottish Government tobacco
and nicotine vapour product retailers register - 60% against a target of
95%
• Planning Applications (Major Developments - Without Processing
Agreement): Average number of weeks to decision - 21.7 weeks against a
target of 16 weeks
• Planning Applications (Locals - Householder): Average number of weeks
to decision - 13.7 weeks against a target of 8 weeks
• Planning Applications (Other Locals): Average number of weeks to
decision - 9.6 weeks against a target of 8 weeks
• Planning Applications (Other Locals): Percentage decided within statutory
8-week timescale - 55.9% against a target of 80%
• Percentage of building warrant applications responded to within 20
working days - 62.98% against a target of 95% 
4.7 The full set of PIs will be reported through the Council’s annual performance
reporting process once all data becomes available. 
Page 96

Page 97

2026/27 Delivery Plan 
4.8 The 2026/27 Delivery Plan is set out at Appendix 2. 
4.9 Key priorities include:
• delivering sustainable, quality services within the context of significant
financial challenges
• delivering key regeneration sites across West Dunbartonshire
• promoting the next phase of Queens Quay Housing
• exploring commercial opportunities in our town centres and wider
regeneration sites 
• supporting town centre revitalisation
• finalising the Visitor Levy Scheme
• developing a new Economic Development Strategy
• developing a Climate Change Strategy and action plan
• completing the Local Heat and Energy Efficiency Delivery Plan
• implementing the Scottish Parliamentary Elections for the Dumbarton and
Clydebank and Milngavie Constituencies in May 2026
• planning for the Local Government elections in May 2027
• reviewing the Scheme for Establishment of Community Councils
• conducting Community Council elections
• developing Community Planning
• contributing to the Community Learning and Development Plan
• providing legal services to the Council and West Dunbartonshire Energy
LLP in relation to heat supply agreements and network supply contracts
• Implementing the extension of the statutory duty (Tobacco and Vapes Bill)
in line with our enforcement policy
• advising businesses re the introduction of Vaping Products Duty and
compliance of vaping products
• delivering collaborative projects with Trading Standards partners
• progressing the Local Development Plan 3
• reviewing the planning pre-application process
• completing the installation of the new document management system for
Planning and Building Standards 
• providing training to Environmental Health Officers to respond to the Food
(Promotion & Placement) (Scotland) Regulations 2025
• supporting the implementation and development of a new Enterprise
Resource Planning System in relation to procurement 
4.10 Implementation of the Plan will be monitored by the management team with
mid-year and year-end progress reported to Corporate Services Committee
and Infrastructure, Regeneration and Economic Development Committee
(economic development elements only) around November 2026 and May
2027 respectively. 
5 People Implications 
5.1 There are no direct people implications arising from this report. 
Page 97

Page 98

6 Financial & Procurement Implications 
6.1  There are no direct financial or procurement implications arising from this
report. 
7 Risk Analysis 
7.1 Failure to deliver on the actions assigned to Regulatory & Regeneration may
have a direct impact on the delivery of the Council’s Strategic Plan. It is
essential that remedial action is taken to ensure strategic delivery plans
achieve the commitments detailed. 
8 Equalities Impact Assessment 
8.1 Screening and impact assessments will be carried out on specific activities as
required. 
9 Consultation 
9.1  The delivery plans were developed through consultation with officers from the
strategic service areas. 
10 Strategic Assessment 
10.1  The delivery plans set out actions to support the successful delivery of the
strategic priorities and objectives of the Council. 
Chief Officer: Alan Douglas
Service Area:  Regulatory & Regeneration
Date:   29 April 2026
_____________________________________________________________ 
Person to Contact:  Lynn Henderson    
lynn.henderson@west-dunbarton.gov.uk 
Appendices:  Appendix 1: Regulatory & Regeneration Delivery Plan
2025/26 - Year-end Progress  
Appendix 2: Regulatory & Regeneration Delivery Plan
2026/27 
Page 98

Page 99

Background Papers: Regulatory & Regeneration Delivery Plan 2025/26 -
Corporate Services Committee, 21 May 2025 
Regulatory & Regeneration Delivery Plan 2025/26 Mid-
year Progress - Corporate Services Committee, 12
November 2025 
Strategic Planning & Performance Framework 2022/27   
Wards Affected: All
Page 99

Page 100

Official
Appendix 1: Regulatory & Regeneration Delivery Plan 2025/26 – Year-end Progress 
1. Our communities 
Our residents’ health and wellbeing remains a priority 
Performance Indicator
2024/25 2025/26
Owner Value Status Value Target Short
Trend
Long
Trend Note
Percentage of air quality monitoring
stations complying with the national
objective for nitrogen dioxide at the
nearest building façades of
residential properties, schools,
hospitals and care homes (40ug/m3
NO2)
100%  100% 100%   Target met with all 33 monitoring stations
complying with the national objective. Mark Walsh
Percentage of highest priority pest
control service requests responded
to within 2 working days
98%  96% 95%  
Target exceeded, with 1,156 of 1,190
requests responded to within 2 working
days. However, there has been a small
decline in the short- and long-term trends. 
Eilidh Paton
Percentage of planned underage
sales visits carried out by Trading
Standards to premises registered on
the Scottish Government tobacco
and nicotine vapour product retailers
register
New for
2025/26  60% 95% N/A N/A
Target missed due to a number of factors.
A period of long-term sickness absence
reduced team capacity and increased the
workload for the remaining two officers.
Limited team resilience made forward
planning more challenging. In addition,
higher-priority work, including illicit
tobacco investigations, toy safety issues,
a large fireworks seizure, and a number of
reports made to the procurator fiscal,
Annemarie
Clelland
ITEM 10 - APPENDIX 1
Page 100

Page 101

Official
Performance Indicator
2024/25 2025/26
Owner Value Status Value Target Short
Trend
Long
Trend Note
required resources to be redirected,
resulting in fewer advisory visits being
completed. We will look to prioritise these
visits in 2026/27 and aim to complete
them towards the beginning of the year.
Financial impact of disruptive
activities carried out by Trading
Standards on illegal trading
New for
2025/26  
Data
only PI   2025/26 data available late May 2026. Annemarie
Clelland
Percentage of businesses brought
into compliance by Trading
Standards
New for
2025/26   75%   2025/26 data available late May 2026. Annemarie
Clelland
Food Law: Percentage of food
businesses in the highest risk
category (1 to 6 monthly inspections
by Food & Business Group) that
were inspected on time
100%  95% 100%  
While the target was narrowly missed due
to significantly reduced resources as a
result of long-term absence and a vacancy
over the period, performance remains
high.
Eilidh Paton
Food Law: Percentage of food
businesses in the high-risk category
(12 monthly inspections by Food &
Business Group) that were
inspected on time
87%  89% 80%   Target exceeded and both the short and
long trends are improving. Eilidh Paton
Food Law: Percentage of food
businesses in the medium to low-
risk category (>12 Monthly
inspections by Food and Business
Group) that were inspected on time
New for
2025/26  87% 60% N/A N/A
Target exceeded. As this is a new
indicator for 2025/26, neither short nor
long trend data is available this year.
Eilidh Paton 
Page 101

Page 102

Official
Action Status Progress Due Date Note Owner
Implement the requirements of
the Digital Markets, Competition
and Consumers Act 2024  
31-Mar-
2026
Completed as planned. All officers have attended
training offered by the Chartered Trading Standards
Institute and we continue to attend working groups with
colleagues to ensure our application of the legislation is
consistent across the profession. 
Annemarie
Clelland
Support and advise businesses
in relation to the new Tobacco &
Vapes Bill 2024  
31-Mar-
2026
Completed as planned. Trading Standards Officers have
contacted all traders registered with the Scottish
Government to sell nicotine vapour products to advise of
the upcoming display ban and we have introduced
authorisations to ensure officers are legally permitted to
enforce the new requirements. However, the display ban
did not come into force as expected and there is
currently no date set for this. Once the ban has been
introduced, we will monitor complaints to identify non-
compliance and take action where required but this will
be challenging due to competing priorities and resource
constraints.
Annemarie
Clelland 
2. Our Environment 
Our local environment is protected, enhanced and valued 
Performance Indicator
2024/25 2025/26
Owner Value Status Value Target Short
Trend
Long
Trend Note
Air Quality: PM10
Concentration 9.4  9 18  
The year-end value is well within the
national target of 18ug (micrograms) and
both the short and long trends have
improved.
Mark Walsh 
Page 102

Page 103

Official 
Our resources are used in an environmentally sustainable way 
Performance Indicator
2024/25 2025/26
Owner Value Status Value Target Short
Trend
Long
Trend Note
Tonnage of carbon dioxide
emissions from Council
operations and assets
18,235   18,188  
2025/26 data is available in November
when all utilities bills and waste figures are
validated in advance of preparing our
annual mandatory climate change report
for submission to the Scottish Government
in November 2026. 
2024/25 data, reported in November 2025,
shows significant progress. The value of
18,235 tonnes represents 33.8% reduction
on the previous year, 44.7% reduction on
the 2012/13 baseline and 5.7% ahead of
projected target. These are positive steps.
However, the main reduction is from the
Council's scope 3 waste emissions, which
is a result of shifting a significant amount
of waste from landfill to incineration
through the Net Zero Cooperation
Agreement with Glasgow City Council.
Both scope 1 and 2 emissions increased
slightly for 2024/25 period. To reach a
61% reduction by 2030/31 we need to
reduce a further 16.3% in just over five
years and investment in required to
reduce gas, electricity and diesel
consumption. 
Amanda
Kean
Page 103

Page 104

Official 
Action Status Progress Due Date Note Owner
Co-ordinate, monitor and report
the progress of the Council’s
Climate Change Action Plan for
2025/26  
31-Mar-
2026
Completed as planned. The Climate Change Action
Group meets regularly to progress and monitor this work
stream. To encourage wider engagement, service
specific meetings have been arranged and are now
underway.
Amanda
Kean
Develop the Local Heat and
Energy Efficiency Strategy
Delivery Plan  
31-Mar-
2026
Overdue. Recruitment for the Local Heat and Energy
Efficiency post has taken longer than anticipated. Due to
other commitments, there is not the capacity within the
climate team to finalise the Local Heat and Energy
Efficiency Delivery Plan. Once the post is filled, the
Delivery Plan will be finalised. This action will be carried
forward in 2026/27 and completed.
Amanda
Kean 
Risk Description Current
Assessment
Target
Assessment
Date
Reviewed Note Owner
Inability to
reduce carbon
footprint in line
with targets
The risk that the Council will be
unable to achieve net zero
emissions by 2045, both in
relation to mitigating carbon
emissions and adapting to the
impacts of climate change. Net
zero refers to achieving an
overall balance between
emissions produced and
emissions taken out of the
atmosphere. This target has
been developed in a way that
mirrors the emission reduction
trajectory set by the Scottish  
01-Apr-
2026
The risk assessment remains
unchanged from mid-year. 
The Council's most recent
emissions, reported in November
2025 for 2024/25, showed
significant progress. (Details are
set out under the PI ‘Tonnage of
carbon dioxide emissions from
Council operations and assets’
above.) 
The long-term Climate Change
Coordinator vacancy has been
filled internally; this currently
Alan
Douglas;
Amanda
Kean; Gail
Macfarlane
Page 104

Page 105

Official
Risk Description Current
Assessment
Target
Assessment
Date
Reviewed Note Owner
Government in light of the
Climate Emergency. 
leaves another vacancy within the
energy team that will be filled as
soon as possible. Participation
from service areas has increased
at Climate Change Action Plan
meetings and emission
reductions actions and projects
are forthcoming. The Council also
has the opportunity to utilise
ClimateView and track trajectory
to Net Zero, allowing actions and
projects to be prioritised and a
more collective, strategic
approach to be implemented. 
The Strategic Risk will be
reviewed at the next Climate
Change Action Plan meeting for
relevance and an amended risk /
set of risks will be reported to
future meetings. 
Our neighbourhoods are sustainable and attractive 
Action Status Progress Due Date Note Owner
Promote the next phases of
Queens Quay Housing  
31-Mar-
2026
Completed as planned. Officers continue to progress this site
and support delivery. A planning application for residential
development on part of the site has been submitted and
further residential applications are expected Q2 2026/2027.
Michael
Mulgrew;
Magda
Swider 
Page 105

Page 106

Official 
3. Our Economy 
Our area has the infrastructure for sustainable and inclusive growth where businesses can flourish 
Performance Indicator
2024/25 2025/26
Owner Value Status Value Target Short
Trend
Long
Trend Note
Number of businesses given
advice and assistance to
start up through Business
Gateway
190  188 180  
Target exceeded. During 2025/26, 188
businesses were provided with advice to
start-up through Business Gateway,
exceeding the target of 180.
Gillian
Scholes
Percentage of procurement
spent on local
small/medium-sized
enterprises and SMEs who
have a presence in West
Dunbartonshire
33.42%   36%   2025/26 value available July 2026. Iain Skene
Number of business
gateway start-ups per
10,000 population
21.32   19.78  
2025/26 data for this Local Government
Benchmarking Framework (LGBF) indicator
will be available at a later date following
publication by the Improvement Service. 
Based on the LGBF comparative data for
the previous year (2024/25) published by
the Improvement Service in February 2026,
performance was better than the Scottish
average of 12.3, and better than the family
group average of 12.2, with a ranking of 2
of 32 local authorities, down 1 place from
the previous year.
Gillian
Scholes
Page 106

Page 107

Official
Performance Indicator
2024/25 2025/26
Owner Value Status Value Target Short
Trend
Long
Trend Note
Proportion of properties
receiving superfast
broadband
99.8%   99%  
2025/26 data for this LGBF indicator will be
available at a later date following
publication by the Improvement Service. 
Based on the LGBF comparative data for
the previous year (2024/25) published by
the Improvement Service in February 2026,
performance was better than the Scottish
average of 97.1%, and better than the
family group average of 99.1%, with a
ranking of 1 of 32 local authorities,
consistent with the previous year.
Gillian
Scholes
Immediately available
employment land as a % of
total land allocated for
employment purposes
40.7   40  
2025/26 data for this LGBF indicator will be
available at a later date following
publication by the Improvement Service. 
Based on the LGBF comparative data for
the previous year (2024/25) published by
the Improvement Service in February 2026,
performance was better than the Scottish
average of 21.3%, and better than the
family group average of 28.6%, with a
ranking of 8 of 32 local authorities, down 1
place from the previous year.
Michael
Mulgrew 
Page 107

Page 108

Official
Action Status Progress Due Date Note Owner
Produce a planning focused
delivery programme to support
key regeneration sites and
enable high quality development
to be achieved on the ground  
31-Mar-
2026
Overdue. While we scoped out the content of the
programme with Economic Development and began
drafting a document setting out how key regeneration
sites will be supported, this has now stalled due to
workload constraints. This will be taken forward in
2026/27 and completed by end of the period.
Michael
Mulgrew
Deliver key regeneration sites
across West Dunbartonshire  
31-Mar-
2026
Completed as planned. 
• Work to support the regeneration of the Exxon and
Scottish Marine Technology Park (SMTP) is progressing
well. SMTP was approved as an Investment Zone project
in November 2025 and Malin Group are currently
preparing an Outline Business Case. Investment Zone
funding will contribute £20m towards development of the
SMTP over the next 10 years. 
• An application for Regeneration Capital Grant funding
progressed to Stage 2 and results are expected in
Spring. 
• Construction works on the Exxon site are progressing
well, with a significant milestone achieved in January
2026 when the western underbridge was completed by
Network Rail. Work is also underway on marketing the
Exxon site and further updates will be provided to the
project board.
Magda
Swider
Explore commercial opportunities
in our town centres and wider
regeneration sites  
31-Mar-
2026
Overdue. Progress has been achieved in a number of
areas over the year including discussions with
prospective developers with regards to the Queens Quay
development and appointment of consultants to develop
a Tourism Strategy for the West Dunbartonshire. 
Magda
Swider
Page 108

Page 109

Official
Action Status Progress Due Date Note Owner
However, one milestone relating to the Council's
consideration of the Planning Permission in Principle
(PPIP) application for the Masterplan Dumbarton Artizan
redevelopment has been delayed due to prolonged
engagement with the Scottish Environmental Protection
Agency (SEPA) which is a statutory consultee. SEPA
objected to the application on the grounds that it does
not comply with Policy 22 of the National Planning
Framework 4 and provided comments on our Flood Risk
Assessment. The Flood Risk Assessment was
subsequently amended to address their feedback and
re-submitted to Planning and we are currently awaiting
SEPA’s response. SEPA’s objection will not be lifted,
however, once their response is received, the PPIP will
be considered by the Council. It is expected to be Spring
or early Summer 2026.
Deliver business support
interventions through the UK
Shared Prosperity Fund 2025/26  
31-Mar-
2026
Completed as planned. Business grants available
through the UK Shared Prosperity Fund have been
promoted through social media, council website and
directly to eligible businesses. The UK Government has
extended the deadline for grant spend until the end of
September 2026. We will continue to appraise and
process applications to maximise funding through this
period.
Gillian
Scholes
Support town centre revitalisation   31-Mar-
2026
Completed as planned. In Alexandria, we have been
working with the Business Improvement District to
develop designs for Mitchell Way/main Street
improvements. We have also appointed a contractor for
the Alexander Street improvements, another of the
Alexandria Masterplan projects. In Clydebank, a big
Magda
Swider
Page 109

Page 110

Official
Action Status Progress Due Date Note Owner
milestone was achieved when the Pride in Place Plan
was submitted to the UK Government. Once approved it
will unlock up to £20m funding over the next 10 years. In
Dumbarton, delivery of the UK Government funded
regeneration works in the town centre is progressing
well, with Phase 1 of Artizan redevelopment now on site. 
Develop a monitoring and
compliance framework for major
and strategic regeneration sites
to ensure compliance with
approved consents  
31-Mar-
2026
Completed as planned. The monitoring and compliance
framework is developed and will be implemented as part
of the review of the statutory Planning Enforcement
Charter in 2026/27.
Michael
Mulgrew 
Risk Description Current
Assessment
Target
Assessment
Date
Reviewed Note Owner
Failure to
deliver Queens
Quay
Masterplan
Following completion of Council
investment there is a risk the
housing plot sales do not
materialise in the next 3-7
years, with implications for the
return on investment and the
business case for the District
Heating Network. 
11-Mar-
2026
Risk remains unchanged.
Delivery of site remains
embedded in service
workstreams.
Michael
Mulgrew;
Magda
Swider
Inability to meet
demands of
Council to
progress
regeneration
projects within
The number and complexity of
regeneration projects is putting
considerable strain on the
resources available which can
be exacerbated by delays out
with the control of the service
and when pinch points on  
11-Mar-
2026
Risk remains unchanged.
Individual projects continue to
progress and are regularly
reviewed, reducing the likelihood
of undesirable outcomes.
Embedded in workstreams to
ensure sufficient resource to
Manager of
Legal and
Democratic
Services;
Michael
Mulgrew;
Page 110

Page 111

Official
Risk Description Current
Assessment
Target
Assessment
Date
Reviewed Note Owner
desired
timescales
different projects occur at
roughly the same time. 
support delivery of projects within
required timescales.
Magda
Swider 
4. Our Council 
Our workforce is resilient and skilled where digital technology supports service delivery for our residents 
Action Status Progress Due Date Note Owner
Develop and implement
employee life cycle plans in line
with the People First Strategy to
attract and retain the workforce  
31-Mar-
2026
Completed as planned. We have implemented revised
structures in several teams following management
reviews, including Legal Services, Planning, Building
Standards and Environmental Health. These will be
complete once a number of vacancies are filled.
• Legal Services - Completed in part with the posts of
Licensing Assistant and Solicitor (Citizen & Regulator
Team) filled and two other vacant posts advertised.
• Planning - Competed and fully staffed in current
structure.
• Building Standards - A training post is going through
Job Evaluation and a technical support officer is
attending an HNC Architectural Technology course.
• Environmental Health - one of two Environmental
Health Officer posts have been filled with one
remaining vacancy.
Alan
Douglas
Implement service review
process including role design,
use of new technology and new
ways of working to add  
31-Mar-
2026
Completed as planned. Work is ongoing to review the
management structure in line with the Council’s Strategic
Operating Model principles to identify and address areas
of non-compliance, with new role profiles prepared.
Alan
Douglas
Page 111

Page 112

Official
Action Status Progress Due Date Note Owner
resilience, address gaps, and
establish opportunities for
efficiencies
We continue to review the impact of saving options and
management adjustments identified as part of budget
process for 2025/26 and implement any required
changes. 
• Democratic Services - This has been completed, with
minimum impact on service delivery.
• Planning, Building Standards & Environmental Health
- Within Environmental Health, four saving options
were identified: Savings for review of Environmental
Health and Antonine Wall have been achieved with
minimal impact on overall service delivery. Part of the
Antonine Wall saving was to be achieved by an
increase in fee income. Income looks to be on track
but will not be known until year end. Planning savings
will not be achieved as option was a backstop where
a Lead Planner post was not able to be filled but the
service was successful in recruitment. Combining
Dog and Pest Control posts is ongoing through job
evaluation and saving is expected to be achieved in
line with target. Full operational impact will not be
known until year end.
• Legal Services & Trading Standards - While the
Records Management Officer retired in late July, the
impact will not be known until year-end. Work is
ongoing to deliver Trading Standards saving option.
• Building Standards has developed a revised structure
that supports career pathways. Further details are set
out in the action below.
• Further changes introduced to comply with SOM
Principles with Energy and Compliance, Legal and
Page 112

Page 113

Official
Action Status Progress Due Date Note Owner
Democratic and Registration Services all having
changes to Senior Management- with Registration
Services moving to Citizen, Culture and Facilities
from 1st April 2026.
Develop and implement learning
and development plans and
development opportunities to
improve capabilities and
resilience within the workforce  
31-Mar-
2026
Completed as planned. Relating specifically to Building
Standards, we have identified learning opportunities that
support the development of skills and knowledge
required for hard to fill posts in the team. This has been
achieved through a revised structure that supports
career pathways. The new structure, agreed by the
Strategic Resources & Recovery Group, is now being
implemented in conjunction with Human Resources and
Job Evaluation. Building Standards has also secured a
funded place on an HNC Architectural Technology
course for an officer from the technical support team.
Alan
Douglas 
Our Council is adaptable and focused on delivering best value for our residents 
Performance Indicator
2024/25 2025/26
Owner Value Status Value Target Short
Trend
Long
Trend Note
Planning Applications
(Major Developments -
Without Processing
Agreement): Average
number of weeks to
decision
20.3  21.7 16  
Target missed. One major application was
decided in this period that took longer to
process than normal and required to be re-
reported to committee due to a request for
further information and consultation. In
addition, whilst not part of this performance
indicator, the service also processed two
national planning applications.
Michael
Mulgrew
Page 113

Page 114

Official
Performance Indicator
2024/25 2025/26
Owner Value Status Value Target Short
Trend
Long
Trend Note
Planning Applications
(Locals - Householder):
Average number of weeks
to decision
8.2  13.7 8  
Target missed. This was due to a small
number of applications exceeding the target
time. The performance equates to 89.3% of
applications decided in the 8-week timescale
with the monthly data showing that the
service met the 8-week target in 9 out of 12
months. It is expected that performance will
continue to improve in 2026/27.
Michael
Mulgrew
Planning Applications
(Other Locals): Average
number of weeks to
decision
14.1  9.6 8  
Target missed although the short and long
trends are improving. Whilst the target has
been missed, this was an improvement on
the previous year 2024/25 and is expected to
further improve in 2026/27.
Michael
Mulgrew
Planning Applications
(Major Developments – With
Processing Agreements): 
Percentage decided within
agreed target 
New for
2025/26 N/A N/A 90% N/A N/A There were no applications of this type in
2025/26.
Michael
Mulgrew
Planning Applications
(Locals – Householder):
Percentage decided within
statutory 8-week timescale
New for
2025/26  89.3% 80% N/A N/A
Target exceeded. 67 of 75 applications of
this type were decided within the statutory 8-
week timescale.
Michael
Mulgrew
Planning Applications
(Other Locals): Percentage
decided within statutory 8-
week timescale
New for
2025/26  55.9% 80% N/A N/A
Target missed. 33 of 59 applications of this
type met the 8-week timescale. This was due
to a number of older applications clearing the
system that pre-date the new project
Michael
Mulgrew
Page 114

Page 115

Official
Performance Indicator
2024/25 2025/26
Owner Value Status Value Target Short
Trend
Long
Trend Note
management approach that was introduced
in late summer 2025. Since December 2025,
this target has been met consistently, and
this trend is expected to continue into
2026/27.
Percentage of building
warrant applications
responded to within 20
working days
95.6%  62.98% 95%  
Target missed. 206 of 327 building warrant
applications were responded to within 20
working days. Performance was impacted by
a combination of vacant posts and a
significant period of back-office outage and
longer-term absences in late summer 2025.
Performance was further impacted by vacant
posts and longer-term absences January -
March 2026. Recruitment and
implementation of a new back-office
document management system is expected
to improve performance in 2026/27.
Judi
Jamieson
Percentage of
Environmental Health
service requests from
citizens first responded to
within 2 working days
90%  90% 90%  
Target met. Performance is consistent with
the previous year and although there has
been a slight reduction over the long term, it
remains high.
Eilidh Paton
Cash savings achieved from
procurement activity £3,857,546  £1,845,0
89 £400,000  
Target exceeded. Savings included a
recurring saving on Janitorial Supplies
(£171k x 4 years), a saving on Microsoft
Licences, both corporate and education
(£596k), one off savings on various building
Iain Skene
Page 115

Page 116

Official
Performance Indicator
2024/25 2025/26
Owner Value Status Value Target Short
Trend
Long
Trend Note
materials eAuctions / further competitions
(£254k), and various works contracts
tendered under budget (£127k). 
Action Status Progress Due Date Note Owner
Prepare a succession plan to
recruit and replace the Manager
of Democratic and Registration
Services post  
31-Jan-
2026
Completed as planned. Handover meeting took place on
23 January with new manager in post from 2 March
2026.
Manager of
Legal and
Democratic
Services;
Continue to develop the 20-
minute mapping tool for use at
both local and regional levels  
31-Mar-
2026
Completed as planned. We continue to use the tool and
explore ways it can be developed as part of the
Geographic Information System and Local Development
Plan workstreams.
Michael
Mulgrew
Prepare a robust evidence
report for the next Local
Development Plan (LDP3) for
submission for Gatecheck to
Scottish Government Planning
and Environmental Appeals
Division  
31-Mar-
2026
Overdue. Work on the evidence report is advancing but
is taking significantly longer than anticipated due to the
breadth and complexity of the work. It has not been
possible to progress this to submission as planned.
Officers continue to work to complete the evidence report
and it will be complete in 2026/27. A revised
Development Plan Scheme will be reported to
September Planning committee to reflect changes to
programming.
Michael
Mulgrew
Continue to promote and
support communities in the
preparation of Local Place Plans  
31-Mar-
2026
Completed as planned. Officers continued to engage
communities in the preparation of Local Place Plans.
Funding was available to support communities until the
end of March 2026 and had limited uptake.
Michael
Mulgrew
Page 116

Page 117

Official
Action Status Progress Due Date Note Owner
Develop a plan to ensure
compliance with the new
Building Standards Regulations
is implemented  
31-Mar-
2026
Cancelled. This action has been cancelled as the
required regulations and guidance have not been
implemented by the Scottish Government relating to the
new compliance regime.
Michael
Mulgrew
Progress the introduction of a
new document management
system for Planning and
Building Standards  
31-Mar-
2026
Completed as planned. The system has been procured
and implementation is in progress. Full system will be
operational in 2026/27 as scheduled.
Michael
Mulgrew
Provide procurement advice,
guidance and support on non-
complex procurement for low
contractual risk projects  
31-Mar-
2026
Completed as planned with support provided to service
areas as and when required. Iain Skene
Continue to implement the key
deliverables from the
Procurement Improvement Plan
focusing on reporting
improvements within WeBuy
purchase to pay system  
31-Mar-
2026
Completed as planned. We have completed a number of
reporting improvements in the WeBuy purchase to pay
system.
Iain Skene
Provide legal services to the
Council and West
Dunbartonshire Energy LLP in
relation to heat supply
agreements and network supply
contracts  
31-Mar-
2026
Completed as planned. Legal services continue to
provide advice to the Council and West Dunbartonshire
Energy LLP in relation to connecting a new client to the
network.
Manager of
Legal and
Democratic
Services;
Continue to provide high quality
and timely legal support across
all Council services  
31-Mar-
2026
Completed as planned. Legal Services continue to
provide support to all Council services as well as the
Health & Social Care Partnership and the Leisure Trust
in relation to a number of matters that contribute towards
Manager of
Legal and
Democratic
Services;
Page 117

Page 118

Official
Action Status Progress Due Date Note Owner
the Council's strategic priorities and protect the Council's
interests in a range of matters. For example:
• Issued Notice of confirmation of the proposed
Gruggies Burn Flood Alleviation Scheme.
• Legal support on decriminalisation of car parking.
• Legal support on the development of Scottish Marine
Technology Park.
Review processes and
procedures within Legal
Services’ Commercial & Place
and Citizen & Regulatory teams  
31-Mar-
2026
Overdue. Awaiting the appointment of a new Section
Head in Citizen & Regulatory.
Manager of
Legal and
Democratic
Services;
Review workstreams and
procedures within
Environmental Health  
31-Mar-
2026
Completed as planned. High level workstream reviews,
such as dog and pest control, have taken place and
actions arising are being taken forward under general
service improvement actions.
Michael
Mulgrew
Review the planning
preapplication process  
31-Mar-
2026
Completed as planned. Draft process changes and
guidance have been prepared and are under review
internally with the service. This is linked to a budget
option for 2026/27 and a report regarding cost changes
will be taken to a future planning committee.
Michael
Mulgrew
Work with other Steering Group
partners to support Historic
Environment Scotland to finalise
a new Antonine Wall
Management Plan  
31-Mar-
2026
Completed as planned. We continue to engage with all
Steering Group partners on the Antonine Wall project.
Michael
Mulgrew 
Page 118

Page 119

Official
Risk Description Current
Assessment
Target
Assessment
Date
Reviewed Note Owner
Failure to monitor
and enforce
regulatory areas with
public risk
The Council fails to comply
with statutory regulatory
duties in respect of
environmental health,
trading standards and
licensing laws   
05-Mar-
2026
The year-end risk assessment
has increased since mid-year,
particularly to reflect
circumstances within Trading
Standards. 
Within Trading Standards, low
staffing numbers and competing
priorities continued to put
pressure on the service. This will
be exacerbated when a full-time
Trading Standards Officer post is
deleted from the structure as
previously agreed as part of the
2025/26 budget savings. During
2025/26, the service received
considerable pressure in relation
to fireworks where resources
were not able to fulfil demand.
This has also led to an increase
in the year-end risk assessment.
Where possible, our high-risk
routine inspections continue as
well as our reactive work into
criminal complaints and
intelligence received but other
areas of proactive work such as
market surveillance and animal
Annemarie
Clelland;
Eilidh
Paton;
Manager of
Legal and
Democratic
Services
Page 119

Page 120

Official
Risk Description Current
Assessment
Target
Assessment
Date
Reviewed Note Owner
health and welfare work is difficult
to achieve. 
Within Environmental Health, low
staffing numbers and competing
priorities continue to put pressure
on the service as did a long-term
absence throughout the majority
of 2025/26. All statutory work is
being prioritised but continuing
reduced resources, including one
vacancy, will likely impact
2026/27. 
Licensing Standards Officers
continue to engage in a pro-
active programme of inspections.
Reactive work is driven by
complaints and applications
received. They also engage with
Scottish Society of Local
Authority Lawyers and
Administrators, Licensing Forum
and other bodies to assist with
horizon scanning to identify
emerging issues.
Page 120

Page 121

Official
Risk Description Current
Assessment
Target
Assessment
Date
Reviewed Note Owner
Failure to adequately
respond to an
emergency situation
such as a multiple
fatality workplace
accident, outbreak of
food borne
communicable
disease, a major
public health incident
or pandemic
There is a national
shortage of qualified staff
in Environmental Health,
across Scotland. This
impacts on West
Dunbartonshire Council.
Vacancy levels at WDC
might impact on our ability
to respond to emergencies. 
01-Apr-
2026
The risk score remains
unchanged since mid-end. Due to
a reduction in staff resources as a
result of budget savings and
difficulty recruiting qualified
Environment Health Officers,
management and team
responsibilities have significantly
increased as a result of service
restructure. We will continue
monitor the impact.
Eilidh Paton
Inability to recruit
successfully to
enable performance
to be maintained
There is a current issue
with recruitment of
qualified staff in various
parts of the service.   
11-Mar-
2026
Risk remains unchanged. Whilst
Planning is fully staffed currently,
the recruitment landscape across
the service as a whole remains
challenging with vacancies
difficult to fill.
Michael
Mulgrew;
Eilidh Paton
Failure to secure best
value of procurement
spend and ensure
compliance with
financial regulations
Improved procurement
management process,
contract strategies,
planning, monitoring and
reporting in collaboration
with services will continue
to mitigate against non-
compliant procurement
spend  
03-Mar-
2026
There are a number of actions
and strategies in place to deliver
best value in procurement.
However, the transfer of low
complexity procurement to
service areas when utilising a
framework agreement may be
increasing the risk. The risk
assessment therefore remains
high but unchanged. Further
training and guidance for services
has been rolled out.
Iain Skene
Page 121

Page 122

Official
Risk Description Current
Assessment
Target
Assessment
Date
Reviewed Note Owner
Failure to continue to
achieve increased
savings from
procurement activity
As second or third
generation revenue
contracts seldom deliver
the same cost savings as
first generation, the
contract strategies need to
focus on governance,
operating models, total
cost of ownership, service
quality and innovation  
03-Mar-
2026
Reduction in staff due to previous
Council measures to address the
budget gap and global supply
chain issues that impact directly
on price means that risks to
savings will increase. There are
also a number of market factors
which are difficult to mitigate -
increases to employers’ national
insurance, high inflation and the
potential impact of climate
change. As a result of these
factors, the risk remains
unchanged.
Iain Skene 
Our residents are engaged and empowered 
Performance Indicator
2024/25 2025/26
Owner Value Status Value Target Short
Trend
Long
Trend Note
Percentage of Council and
Committee minutes
produced within 3 clear
working days of the meeting
100%   98%   2025/26 data available late May
2026.
Carol-Ann
Burns
Percentage of committee
agendas published within
standing order timescales
100%   99%   2025/26 data available late May
2026.
Carol-Ann
Burns 
Page 122

Page 123

Official
Action Status Progress Due Date Note Owner
Implement the various
requirements of the Scottish
Elections (Representation and
Reform) Act  
31-Mar-
2026
Completed as planned. The project plan and nomination
pack have been updated to include the new legislative
requirements.
Manager of
Legal and
Democratic
Services; 
Plan for the Scottish
Parliamentary Elections for the
Dumbarton and Clydebank and
Milngavie Constituencies  
31-Mar-
2026
Completed as planned. All preparation work for the
election has been completed.
Manager of
Legal and
Democratic
Services; 
Conduct an interim review of the
Polling Scheme in West
Dunbartonshire  
31-Oct-
2025
Completed as planned. Council has approved changes
to polling scheme and Electoral Registration Officer has
been notified to amend registers accordingly.
Manager of
Legal and
Democratic
Services; 
Continue the development of
Community Planning  
31-Mar-
2026
Completed as planned. The development of Community
Planning has progressed well during 2025/26. A review
of Delivery Improvement Groups was completed and a
recommendations paper was submitted to the
Management Board in November setting out
recommendations on partnership reporting. A pilot in
Alexandria looking at access to services was established
and the initial engagement stage was completed in
2025/26. Next steps will be identified, and this work will
continue in 2026/27.
Colin Smith
Continue to contribute to the
Community Learning and
Development Plan 2024/27  
31-Mar-
2026
Completed as planned. The Communities Team
continues to deliver community development support to
groups across West Dunbartonshire to maximise their
impact. This can be through support to secure external
funding, promotion or by developing skills and improving
governance arrangements. The team is represented on
the Community Development Alliance and plays a key
Colin Smith
Page 123

Page 124

Official
Action Status Progress Due Date Note Owner
role in supporting communities through the development
of Locality Plans. Of particular note, we supported the
completion of two community-led Local Place Plans in
Old Kilpatrick and Central Alexandria, both of which have
been approved and adopted at Planning Committee.
Conclude the Cash First Project
including evaluation  
31-Mar-
2026
Completed as planned. The Cash First Project is a
Scottish Government initiative to end the need for food
banks in Scotland through providing funds or vouchers to
people in financial crisis. Delivered jointly by the
Communities Team and Working 4U, it has been very
successful, with the available funding reaching those
most in need through a network of trusted partner
referrals. The Communities Team has developed and
carried out the evaluation engagement to support the
Cash-First programme. This will be submitted to the
Scottish Government as the end of the project draws to a
successful close.
Colin Smith 
Risk Description Current
Assessment
Target
Assessment
Date
Reviewed Note Owner
Engaging
positively with
Residents,
Communities &
Partnerships
The risk that the Council fails to
adequately engage, establish
and maintain positive
relationships with local residents
and communities in addition to
partnership bodies.   
11-Mar-2026
A partnership approach to
Community engagement is being
undertaken led by the Community
Planning Partnership and
associated partnerships -
Community Learning and
Development and Community
Development Alliance in particular.
The Communities Team and other
partners deliver community
Colin Smith
Page 124

Page 125

Official
Risk Description Current
Assessment
Target
Assessment
Date
Reviewed Note Owner
development work which seeks to
raise awareness of community
planning and Community
Empowerment in communities.
Locality plans, community-led place
planning and work to support the
Clydebank Neighbourhood Board’s
community engagement means this
risk is unchanged. 
Action Status 
Cancelled 
Overdue 
Completed 
PI Status 
Target significantly missed 
Target narrowly missed 
Target met or exceeded 
Risk Status 
Alert 
Warning 
OK 
Long Term Trends 
Improving 
No change 
Getting worse 
Short Term Trends 
Improving 
No change 
Getting worse 
Page 125

Page 126

2026/27
REGULATORY &
REGENERATION
Appendix 2: Regulatory & Regeneration Delivery Plan 2026/27           
ITEM 10 - APPENDIX 2
Page 126

Page 127

Contents 
1. Introduction ............................................................................................................................................................................... 2
2. Performance Review ................................................................................................................................................................. 2
3. Strategic Assessment ............................................................................................................................................................... 8
4. Resources ............................................................................................................................................................................... 19
Appendix 1: Action Plan ..................................................................................................................................................................... 21 
Page 127

Page 128

1. Introduction 
Regulatory & Regeneration comprises a wide range of services covering legal, trading standards, licensing, records management, planning,
building standards, environmental health, democratic and registration services, economic development, community planning and procurement. It
is one of seven strategic areas responsible for delivering the Council’s Strategic Plan. Key actions to help achieve that are set out in this Delivery
Plan, together with actions to address any performance issues and service priorities identified in the planning process. 
The progress of this Plan will be monitored and managed by the management team and reported to Corporate Services Committee and
Infrastructure, Regeneration & Economic Development Committee (economic development elements only) twice yearly, at mid-year and year-
end. 
2. Performance Review 
The management team completed a detailed review of 2025/26 performance, focusing on the following:
• 2025/26 Delivery Plan year-end progress;
• Local Government Benchmarking Framework comparative performance;
• National Planning Improvement Framework;
• Citizens’ Panel feedback; and
• Complaints. 
This review highlighted our key achievements and challenges in 2025/26. These are summarised below. 
Key Achievements in 2025/26 
Listed below are some of the major achievements in each service area that were particularly challenging or unusual.  All services achieve many
other fantastic outcomes for the Council and its residents throughout the year which are not recorded here but are often as important. 
Democratic & Registration Services
• Planned and delivered a successful local by-election in Ward 6 - Clydebank Waterfront.
• Closed the registration office in Clydebank with minimum impact on the public and staffing, resulting in a saving to the Council.
• Delivered updated hybrid system for committee and council meetings at low cost.
• Reviewed the scheme of polling districts and polling places ensuring it is fit for purpose for future elections.
Page 128

Page 129

Legal Services & Trading Standards
• Seized 32,480 cigarettes and 5.9kg of hand-rolling tobacco from retailers supplied or operated by serious and organised crime groups. This
represents an average resale value of £31,000 in loss of sales revenue, with referrals made to His Majesty’s Revenue and Customs (HMRC)
for financial sanctions to be imposed. Trading Standards led on this illicit tobacco enforcement project along with Police Scotland and HMRC
and will continue to lead on this work locally with funding confirmed from HMRC until 2029.
• Agreed Heads of Terms for the Disposal of two major housing sites at Queens Quay which, subject to planning, will deliver up to 460 units
and multi-million pound capital receipts over the next three years.
• Acted for the Council in residential conveyancing matters to secure the purchase of residential properties to supplement the Council’s
housing stock through our Buy Back scheme. 
Planning, Building Standards & Environmental Health
• Secured a funded place via the Scottish Building Standards Hub for a Technical Support Officer to upskill to a Trainee Building Standards
Surveyor.
• Procured the new document management system for Planning and Building Standards. Implementation has begun and will be complete in
2026.
• Received endorsement from the National Planning Improvement Champion for the Planning Service’s first National Planning Improvement
Plan and provided an update on progress that was also endorsed. 
• Appointed a Lead Planning Officer within the Development Management Team, a Surveyor within Building Standards and an Environmental
Health Officer within Environmental Health, filling previously long-term vacancies. 
• Supported the housing emergency by granting planning permission for a number of high quality new social housing developments, including
at Queen Mary Avenue, Ottawa Crescent, Golfhill Drive and the former Clydebank Health Centre. The service also supported development
of larger market sites, including at the former Thomsons Yard, Dumbarton. Following considerable work to overcome site constraints and
consultee concerns, a currently vacant prominent waterfront site in Dumbarton will be redeveloped with high quality new housing and
facilitate the continued development of the Riverside Pathway through the site. 
• Continued support for delivery of key regeneration sites including, Exxon, Carless (Scottish Marine Technology Park) and Queens Quay
through close working with other the applicants, other Council services and external partners. 
• Secured funding from the Planning Hub to assist with Local Development Plan work. 
Economic Development and Regeneration
• Completed formal visitor levy consultation and obtained Council approval to implement a 5% visitor levy from 1 July 2027.
• With support from the Council, the Malin Group and Strathclyde University, succeeded in securing £20m funding for the Scottish Marine
Technology Park from the City Region’s Advanced Manufacturing and Precision Engineering Investment Zone. 
Page 129

Page 130

• Contributed to numerous strands of the UK Shared Prosperity Fund delivery, including providing support to 190 new business start-ups and
delivering a range of business growth interventions and successfully delivering a series of community soup events to increase local
democracy.  
• Started construction works on site for Phase 1 of the UK Government funded redevelopment of the Artizan shopping centre in Dumbarton.
• Supported the Clydebank Neighbourhood Board in developing a Regeneration Plan (including a 4-year Investment Plan) which outlines the
main priorities for Clydebank to be delivered over the next 10 years with (up to) £20m of Pride in Place funding.
• Worked with Alexandria BID and wider Alexandria community to develop proposals for the Main Street improvements, progressing delivery of
projects originating from the Alexandria Masterplan.  
• Worked with the Loch Lomond and Trossachs National Park to develop Balloch Pierhead Action Plan. 
• Submitted applications to the Scottish Government's Regeneration Capital Grant Fund with the application for Scottish Marine Technology
Park  being successful securing millions of pounds for remediation of site.
• Reported significant progress in reducing carbon emissions from Council operations and assets based on the latest 2024/25 figure of 18,235
tonnes. This represents a 33.8% reduction on the previous year, a 44.7% reduction on 2012/13 baseline and 5.7% ahead of projected target.
• Delivered 5 Community Soup Events in Old Kilpatrick, Dalmuir and Dumbarton, with two additional themed Soups working with West
Dunbartonshire secondary schools and groups engaged in biodiversity activities.  Some were organised by the Communities Team with
community input while others were led by communities with support from the Team. Over £6,000 in small grants were awarded to local
community groups supporting community activity.
• Delivered 250 appointments and co-ordinated 670.30 hours of volunteer activity (2025 calendar year) through the Community Transport’s
Health Appointments Transport Service (HATS).  £30,000 in Strathclyde Partnership for Transport (SPT) funding was brought into West
Dunbartonshire.
• Supported Old Kilpatrick Community Council and Alexandria Community Council to complete Local Place Plans for their areas, which have
subsequently been adopted at the Council’s Planning Committee.       
Procurement
• Delivered strategic contracts including: 
o Services – Property Maintenance & Cleaning, Addiction Services, Counselling in Schools, Exxon Site Supervisor and Quantity Surveyor,
Parking Management Back Office Support, Bureau Management Services, Cashless Register System for Schools, Legionella Water
Management, Co-mingled Recyclate (DMR), Measured term contact for Plumbing, Cleaning Services for Void and Homeless Properties
o Works – 4x Sports Pitches, Queen Mary Avenue Design and Build, External Building Fabric Upgrades, Demolition of Skypoint Centre,
Refurbishment of 3 Play Areas, Development of New Allotment Site - Overburn
Page 130

Page 131

o Goods – Substantial Fleet Replacement Programme and Tyres, Mini-Buses for Educational Support Needs Transport, Multiple Building
Materials Contracts, Device Replacement and Microsoft Licences, New Finance Enterprise Resource Planning (ERP) Software,
Washroom Solutions and Sanitary Products
• Examples of Innovative Approaches for strategic contracts included:
o Adult Care at Home Services – Worked collaboratively with HSCP and Commissioning Team to create our first framework, providing
increased security for providers, longer term price certainty for the Council and improved procurement compliance.
o eAuctions for Building Materials – New approach to secure savings across paint and electrical materials which included market
engagement to ensure suppliers understood bidding process
o Washroom Solutions – Engaged with client departments to determine core list of products and new processes to establish savings
o Fleet – Worked with department to agree varied routes to market for many different categories of vehicles to ensure best value
o Additional Needs Education Transport – Suggested to department to examine bus purchase to replace expensive taxi routes, then
supported resulting procurement leading to savings option approved by Council.
• Alongside Working4U team, collaborated with partners and suppliers to continue to improve sustainability and deliver local, social and
community benefits resulting in (as at end of Q3)
o £80,616 donated to local community projects (circa £42k in cash and £38k in materials)
o 23 work experience posts (23 work experience weeks for 23 different individuals) 
o 753 hours contributed to local charities, community groups, schools, and West Dunbartonshire Council departments.
o 6 full time employment posts being filled. 
Key Challenges in 2025/26 
Cross Service
• The national skills shortage of qualified and experienced officers in Planning, Environmental Health, Trading Standards and Building
Standards continued during this period, resulting in reduced staff complements across many services and increased demands on existing
and inexperienced staff. This is a challenge experienced by most local authorities and has resulted in alternative service delivery models,
including the use of agency staff and initiatives being led at a national level such as Future Planners Project and Building Standards hub. A
new Regulatory apprenticeship is being developed and may provide opportunities in the future. 
Democratic & Registration Services
• The service experienced a relatively high turnover of staff in both democratic services and the election team which was challenging.
However, successful recruitment resulted in all key positions being filled with highly qualified, experienced staff. 
Page 131

Page 132

Legal Services & Trading Standards
• Increased requirement for specialist construction contracts associated with infrastructure and regeneration priorities impacted on the
Commercial & Place Section’s workload, changing the skills dynamic required to meet client requirements.
• Recruitment of solicitors has been challenging with a lack of applicants for both permanent and temporary positions in both the Commercial &
Place and Citizen & Regulatory Sections. This has been exacerbated by the loss of key staff and together these factors have had an adverse
impact on service delivery.
• The Trading Standards service faced significant challenges in relation to fireworks over the period from October to December 2025, with the
demand for the service far exceeding our capacity, leaving the team overwhelmed. As a result, we were unable to respond appropriately to
every case, leading to a failure in enforcement responsibilities. 
• The Trading Standards service workforce, both nationally and in West Dunbartonshire Council, is ageing with low numbers of people entering
the profession. This presents a challenge in ensuring a resilient service. With three Trading Standards Officers in West Dunbartonshire, a
long-term sickness absence highlighted the severe strain on the team and the implications of future reductions in the staffing budget. 
Planning, Building Standards & Environmental Health
• Whilst vacancies have reduced, recruiting within Building Standards and Environmental Health remains challenging. These have been harder
to fill roles which is creating knock on effects in terms of workload and performance.
• The current case management system for Planning and Building standards resulted in increased pressures on the service with workarounds
and manual processes required with the back-office system being unavailable for a significant period in late summer. This added pressure to
officer workload and our consultees, which had a negative impact on performance statistics. There have also been knock on impacts on
other workstreams of the Technical Support Team due to the time spent on the current case management system, for example on Street
Naming and Numbering and the Corporate Address Gazetteer. 
• Staff absence, combined with system outages and vacant posts, significantly impacted Building Standards in late summer. This resulted in
significantly decreased performance statistics whilst the team recovered, and a new officer started. In early 2026 the team started to see the
impact of ongoing changes to the scope of role within Building Standards to meet verification requirements. This includes a new Professional
Competency Framework, enhanced compliance, new time recording, additional work to demonstrate strengthened operational and
performance frameworks and future 3rd party audit.
• The Environmental Health workforce, both nationally and in West Dunbartonshire Council, is ageing with low numbers of people entering the
profession, made significantly worse with the removal of the BSc Environmental Health from the University of the West of Scotland. This
presents a challenge in ensuring a resilient service. Two long term sickness absences and the removal of the Dog Warden and Private
Landlord Registration Officer highlighted the severe strain on the team. To accommodate these pressures, an Environmental Health Officer
was seconded from the Food & Business Regulation team to Environmental and Community Health Protection team. 
Page 132

Page 133

• The Development Planning and Place team have had to revise the timescales for the production of the next Local Development Plan.
Workload and timescales remain very challenging, and the adoption of the next Local Development Plan is forecast to be delayed beyond
the March 2028 deadline set by Scottish Government. 
Economic Development and Regeneration
• Delivering private sector homes at Queens Quay continued to be a challenge in 2025/26 but we meet with our commercial partner regularly
and there were some positive discussions with potential developers.
• Businesses continued to face many economic challenges in 2025/26, including energy costs and employee recruitment and retention. The
on-going advice available through Business Gateway will continue to help them to recover and grow in the year ahead.
• Significant proposed reductions in the UK Shared Prosperity Fund revenue budget for 2026/27 is likely to have an impact on the grant
funding available to support local businesses with growth projects and job creation.
• Securing external funding to progress regeneration of our strategic sites and town centre assets is challenging. Regeneration team continue
to explore funding streams and provide support to private owners to help them progress their projects.
• Significant proportion of privately owned buildings in our town centres which suffer from lack of maintenance and investment continues to be
a challenge which hinders town centre revitalisation.
• Uncertainty regarding the regeneration funding in the Scottish Government’s budget and longer-term spending plans.
• Lack of funding to secure adequate long-term management and maintenance programme for new and existing regeneration projects, and
public areas in general.
• Resourcing the operation and further development of the District Heating Centre remains very challenging due to inability to attract a lead
officer within the Climate Change team.
• Despite carbon emissions for 2024/25 showing a significant reduction, it will be challenging to achieve future targets as outlined in our
Climate Change Strategy. Emissions were reduced in 2024/25 due to new waste arrangements with Glasgow City Council while emissions
from some other sources increased. To ensure Net Zero targets are met by 2045, consideration should be given to additional resources to
ensure continued progress.
• The Climate Change Team had vacancies throughout the year which impacted on the completion of some tasks, particularly the Local Heat
and Energy Efficiency Delivery Plan.
• The cost-of-living crisis and the increase in various renewable energy technologies within the Council’s new supply housing have seen a
significant uplift in the number of residents requiring Energy Efficiency support. This has proved challenging to facilitate within our existing
resources. 
Page 133

Page 134

Procurement
• Previous year efficiency options led to a reduction in procurement team resource. This led to processes being introduced which place more
responsibility for procurement on client services. This continues to be a challenge, especially as efficiency options within client services are
considered and implemented. 
3. Strategic Assessment 
The Regulatory & Regeneration management team completed a detailed strategic assessment to determine the major influences on service
delivery and priorities in 2026/27 and beyond. This covered a review of local and national political priorities, new legislation and technology,
Council policies, and our continued recovery from the pandemic, cost of living crisis and the financial challenges facing the Council. The key
issues are outlined below. 
Key Factors 
Financial Challenges 
The entire public sector is continuing to face significant financial challenges due to a range of factors including inflationary cost increases, pay
awards not being fully funded by the Scottish Government and insufficient overall funding to support the delivery of front line and back-office
services. The Council is currently faced with an estimated cumulative funding gap in 2027/28 of £10.905m rising to £44.028m by 2030/31. We
will continue to monitor the overall financial position of the Council and updates on estimated future budget gaps will be reported to Elected
Members throughout 2026/27. 
These challenges require further action to balance our budget and protect services for residents. Within Regulatory & Regeneration, this means
that available funding will be reduced over time and we will need to reconfigure how we work, what we do, where we work, and potentially
reduce the number of people employed. In this context, we will aim to continue to provide a sustainable, quality service to internal clients and the
public. 
Budget Sensitivity Analysis 
In reviewing the service budget projections, consideration has been given to the sensitivity of these budgets, in particular for higher risk/ higher
value budgets which may have a significant impact on budgetary control and future budget projections. The analysis has considered sensitivity
around demand, costs and charges, and income levels.
Page 134

Page 135

In Regulatory & Regeneration there were no budgets identified as being more susceptible to fluctuations. However, on a more Council-wide
basis, the Council’s cost of borrowing is susceptible to fluctuations in the bank interest rate due to the level of the Council’s short-term borrowing. 
Key Strategic Regeneration Sites 
Delivery of a number of key regeneration projects, which span multiple years, will continue to be progressed in 2026/27. The main focus will be
the Bowling Strategic Opportunity on the former Exxon site and the Scottish Marine Technology Park on the former Carless oil terminal site, led
by the Malin group. 
For the Exxon site, the focus will be on delivering the infrastructure and developing the marketing strategy to realise the economic benefits of the
site. Funding opportunities to deliver the proposed Dunglass Castle Community Parkland will also be explored. For the Carless site, the Council
will continue to support the Malin group in the delivery of the first phase of the proposed Scottish Marine Technology Park. 
Actions: Deliver key strategic regeneration sites across West Dunbartonshire 
Queens Quay 
Infrastructure works for this 80-acre residential waterfront development were completed in 2020/21. In the year ahead, the focus on securing
housing developments across the site in partnership with site owner Clydeside Regeneration Ltd. will continue. This is a challenge, particularly in
relation to flatted private homes which the market is finding commercially challenging. Discussions will continue with Clydeside Regeneration Ltd
and the two prospective purchasers of the first sale sites have development commence in this financial year. 
Action: Promote the next phases of Queens Quay Housing 
Key Commercial Opportunities 
Identifying commercial opportunities in conjunction with the private sector will continue to be a priority in 2026/27. Discussions with developers
who may wish to enter a partnership with the Council to achieve joint benefits from a commercial, housing and low carbon perspective will be
progressed. The Regeneration Capital Fund of £12.40m has been allocated across a number of projects. The Fund’s key operating principles
and allocations to specific projects agreed by Committee will be progressed. Opportunities include: 
Page 135

Page 136

• Exxon: As infrastructure works progress, the Council will consider how to promote and deliver the best uses for the site and, working with the
City Region and Scottish Enterprise, will encourage developer interest in the site to meet the growth targets set out in the City Deal business
case. 
• NHS Golden Jubilee: We will seek to deliver the extension of the District Heating network to the hospital and explore opportunities presented
by the expansion of the hospital for development and regeneration of Queen Quay and Clydebank, generally.
• Scottish Marine Technology Park: We will continue to work with the Malin Group in their ambition to deliver the Scottish Marine Technology
Park at the former Carless site near Old Kilpatrick and assist them in attracting business and funding to the site. A joint project board
continues to provide support and direction as the Malin Group progress the development through the planning and infrastructure
implementation stages.
• Clydebank: We will support the Neighbourhood Board in undertaking a feasibility study to explore redevelopment and investment
opportunities for the southern part of the shopping centre,
• Artizan: We will explore opportunities and undertake a feasibility study to explore investment opportunities in future phases of the Artizan
redevelopment. 
Action: Explore commercial opportunities in our town centres and wider regeneration sites 
Visitor Levy Scheme 
West Dunbartonshire Council approved the decision to introduce a 5% visitor levy scheme at Council committee in November 2025. The start
date for the levy will be 1 July 2027. The income raised must be used to develop, support, and sustain facilities and services which are 
substantially used by visitors and is estimated to be approximately £1.7 million per annum.   
Action: Finalise the Visitor Levy Scheme for introduction in July 2027 
Economic Development Strategy 2027-2032 
A new Economic Development Strategy will be developed which will provide an updated economic vision and strategic priorities for West
Dunbartonshire for a five-year period from 2027 to 2032. This new strategy will build on the foundations established in the previous 2022-2027
Economic Development Strategy.   
Action: Develop a new Economic Development Strategy 2027- 2032
Page 136

Page 137

Town Centre Revitalisation 
Assisting town centres to adjust to the current shopping trends and embrace new challenges will be our focus in 2026/27, with support for high
street businesses a key priority. We will continue to develop projects to make our town centres attractive places and take advantage of the
external funding, including the UK Government’s funding streams and Place-Based Investment Programme funds provided by the Scottish
Government. We will also work with and support community groups or businesses which plan to invest in and establish themselves in our town
centres, and whose plans align with our town centre regeneration agenda. 
• Clydebank has been awarded £20 million funding from the UK Government as part of the Pride in Place Programme (former Plan for 
Neighbourhood).  This funding will support delivery of the projects which reflect the priorities of the local community. Many projects align with
the Clydebank Development Framework which provides a vision for how the town will be transformed, from reducing retail dominance to a
vibrant mixed use and inhabited town centre that meets the needs of the whole community. A Clydebank Neighbourhood Board (former Town
Board), chaired by Liz Connolly, oversees the Fund and the Pride in Place Plan which has been submitted to the UK Government for review.
The first tranche of capital funding is expected in April 2026. Meanwhile, capacity funding has already been awarded to support engagement
and initial project development costs. 
• In Dumbarton, the focus for the next year will be on completing the Levelling Up Fund programme of works, including the refurbishment and
reuse of Glencairn House as a library and museum, and the revitalisation of the Artizan Centre.  We are also exploring other ways to improve
the High Street over the coming years and will continue supporting Planning with the Heritage and Place Programme application which could
fund works to some of the most prominent town centre historic properties. Over the next year we expect to be working with the landowner
Turnberry Homes in preparations for delivery of the waterfront pathway on their land, planned to start in 2027.We will also continue working
in partnership with Historic Environment Scotland and the Maritime Museum to make Dumbarton town centre and waterfront a more
attractive place for visitors. 
• In Alexandria, the next phase of the 2021 Masterplan will be delivered, with an emphasis on Alexander Street improvements which align with
Green Heritage Corridors and Cycling and Walking Network masterplan priority projects. We will also continue to work with Alexandria BID
and the local community to develop detailed designs for Mitchell Way and Main Street improvements, with works expected to start on site in
early 2027. 
Action: Support town centre revitalisation
Page 137

Page 138

Climate Change Strategy 2026-2031 and Action Plan 2026/27 
The Council has a Climate Change Strategy for 2021 to 2026 which was developed in response to the climate emergency and to provide a route
map towards meeting Scotland’s national net zero carbon target by 2045. A revised Strategy will be developed in the year ahead, building on the
accomplishments and progress set out in the current strategy and reinforcing the ambition to deliver a just transition to net zero emissions. It will
focus on reducing the Council’s carbon emissions and adapting to the impacts of climate change over a five-year period from 2026 to 2031. An
annual action plan will be developed to support delivery, with actions devolved to relevant service areas to take forward. Progress against the
2026/27 action plan will be monitored and reported to senior management and Council on a regular basis. 
Action: Develop the Climate Change Strategy 2026-2031 and associated Action Plan for 2026/27 
Local Heat and Energy Efficiency Delivery Plan 
The Local Heat and Energy Efficiency Strategy 2024-2029 sets out the long-term plan for heat decarbonisation and improved energy efficiency
of buildings throughout the Council area. It sets out the changes to each sector of buildings stock that are needed, identifying strategic heat
decarbonisation zones and prioritising delivery areas. Development of the existing Queens Quay District Heat Network will continue and other
opportunities for area-based heat decarbonisation and energy efficiency will be progressed. A Delivery Plan will be completed in 2026/27 to
support the implementation of the Strategy. 
Action: Complete the Local Heat and Energy Efficiency Delivery Plan for implementation 
Scottish Parliamentary Elections 
The Scottish Parliamentary elections are scheduled to take place in May 2026. Initial planning was carried out in 2025/26, and this will continue
into 2026/27 in the run up to the election in May. This will be another major challenge for the relatively inexperienced election team as every
election is different, and this one will be made more challenging by the introduction of new legislation and the appointment of a new election
manager. 
Action: Implement the Scottish Parliamentary Elections for the Dumbarton and Clydebank and Milngavie Constituencies in May 2026 
Page 138

Page 139

Scheme for the Establishment of Community Councils in West Dunbartonshire 
The Scheme for the establishment of Community Councils in West Dunbartonshire requires to be reviewed in 2026 (every four years). The
review will comprise a three-stage consultation process commencing with a review of the existing community council boundaries in February
2026 and ending with a revised scheme in October 2026.  The review will be led by the Manager of Democratic and Registration Services and
supported by the Communities Team who will assist with the consultation process and engage with all community councils and the Community
Council Forum. 
Action: Review the Scheme for Establishment of Community Councils 
Community Council Elections 
Following the review of the Scheme for Establishment of Community Councils, the Council is required to hold community council elections which
reflect any changes to the boundaries and scheme.  Council will determine the timetable for these elections once the new scheme has been
agreed. 
Action: Conduct Community Council Elections 
Local Government Elections 
The Scottish Local Government Elections are scheduled to be held in May 2027, but preparation and planning will commence as early as
October 2026.  This planning will not only include arrangements for the poll and count of votes but will also include arrangements for the election
and induction of any new elected members and formation of the new Council. 
Action: Prepare for the implementation of the Local Government Elections in May 2027 and make arrangements for the induction of newly
elected members and formation of the new Council 
Community Planning West Dunbartonshire 
The Community Empowerment (Scotland) Act 2015 sets out clear requirements for public bodies in promoting a greater level of local decision-
making and empowerment of citizens. Empowered communities can deliver a range of benefits that include improved physical and mental
health, increased confidence and social networks, reduced sense of isolation and can reduce demand on public sector resources.
Page 139

Page 140

Our approach to community empowerment focuses on Community Planning and the development of locality plans, specific projects that promote
local participation and empowerment and regular engagement with local people, particularly in our most disadvantaged communities. Progress
will be monitored by Community Planning West Dunbartonshire and reported through the Empowered Delivery Improvement Group. 
Action: Continue the development of Community Planning 
Community Learning and Development 
The Community Learning and Development (Scotland) Regulations 2013 place a statutory requirement on local authorities to publish a plan
every three years. The plan should outline how the Council will co-ordinate and secure ‘adequate and efficient’ Community Learning and
Development provision with other sector partners. We continue to deliver against our current Community Learning & Development Plan 2024/27
to provide community-based learning opportunities throughout West Dunbartonshire. 
For 2026/27, we will contribute to the delivery of the Community Learning and Development Plan through community planning and community
development work and further development of and participation in the Empowered Delivery Improvement Group /Community Development
Alliance.   
Action: Contribute to the Community Learning and Development Plan 2024-2027 
District Heating Network 
The District Heating Network provides low carbon heating and cooling solutions to the Queens Quay regeneration site. It aims to significantly
reduce fuel poverty and deprivation within some of the poorer neighbourhoods of West Dunbartonshire and, crucially, contribute to key climate
change targets. As the District Heating Network matures, it is anticipated that new customer and expansion opportunities will arise. 
Legal services will continue to support the expansion programme through the provision of legal advice and leadership in the negotiation of
contracts with prospective customers. 
Action: Provide legal services to the Council and West Dunbartonshire Energy LLP in relation to heat supply agreements and network supply
contracts 
Page 140

Page 141

Tobacco and Vapes Bill 
Royal Assent of the Tobacco and Vapes Bill is expected on 1st October 2026. This will amend existing legislation, regulating the tobacco and
nicotine vapour product market more stringently. It is expected that from 1st January 2027, no person born on or after 1st January 2009 can
legally purchase tobacco or tobacco products. There will be changes made to the definition of a ‘vaping product’ to expand the products this
encompasses and nicotine pouches will be included in the legislative framework for the first time. 
Trading Standards Officers will undertake training and ensure they are aware of the requirements of the legislation to competently advise on the
amendments and take enforcement action where required. 
Action: Implement the extension of the statutory duty (Tobacco and Vapes Bill) placed upon the Council in line with our enforcement policy 
Trading Standards Collaborative Projects 
In recognition of our current resource challenges and the changing nature of our work, modifications will be made to how we manage our
workload and the demands on the service. Partnership working will be prioritised, including: 
• Leading an amnesty on unsafe electrical chargers with the Scottish Fire and Rescue Services. Funding provided by Electrical Safety First will
be available to swap unsafe or non-compliant chargers with vouchers to purchase compliant items from local retailers. We will work with local
food banks to ensure we take the service to those most at risk.
• Working with Police Scotland and the Community Alarm and Telecare Team to distribute ‘no cold calling’ stickers to areas most targeted by
cold callers. Stickers have been purchased using funding from Police Scotland (who met 90% of the costs) and will be distributed using their
youth volunteers and colleagues in the Telecare Team. This is of particular benefit as we remove support for the establishment and
maintenance of existing ‘no cold calling’ zones. 
Action: Deliver collaborative projects with our Trading Standards partners 
Vaping Products Duty 
A new excise duty has been placed on vaping products by the UK Government. A flat rate of £2.20 per 10ml of vaping liquid sold will come into
force on the 1st October 2026, increasing the price of some liquids by more than 220%. 
Page 141

Page 142

West Dunbartonshire Council has 210 registered premises for the sale of tobacco and vapes, with at least six premises confirmed to be linked to
serious and organised crime groups who are profiting from the sale of illicit tobacco. It is expected that the significant price increase in vaping
products will drive a market in illicit and traditionally counterfeit stocks being available and result in detrimental health effects for users. 
Advice will be offered to businesses ahead of the introduction of the new duty and based on intelligence received, officers will conduct test
purchases and visit premises to ensure sales of vaping products are compliant. 
Action: Provide advice to businesses re the introduction of Vaping Products Duty and ensure compliance of vaping products 
Local Development Plan 3 
The Local Development Plan is a statutory, long-term plan for the West Dunbartonshire Council Area, (excepting that portion of the Council that
is within the Loch Lomond and Trossachs National Park), that sets out how places will change in the future, including where development should
and shouldn’t happen. The next Local Development Plan for the area, called LDP3, is due to be adopted in 2028 and work has now commenced
on its preparation. 
The current Development Plan Scheme, which sets out how LDP3 will be developed was agreed by the 2023 December Planning Committee.
An annual update was presented to the September 2025 Planning Committee which included a revised timescale. Workforce pressures have
resulted in the program being pushed back 7 months with the submission of the evidence report to the Scottish Government’s Planning and
Environmental Appeals Division (DPEA) expected around June 2026.     
Action: Prepare a robust evidence report for the next Local Development Plan (LDP3) for submission for Gatecheck to Scottish Government
Planning and Environmental Appeals Division 
Planning Preapplication Process 
The Development Planning and Place and Development Management Teams will review the current preapplication process to ensure that the
process is fit for purpose and delivers on both placemaking and performance outcomes. The review will consider the customer guidance and set
out clearly the service standards associated with all aspects of the preapplication process to ensure that customers have clearly defined
outcomes and can identify the best route for their needs. 
Action: Review the planning preapplication process
Page 142

Page 143

New Document Management System for Planning and Building Standards 
Integration between the current case management and document management systems for Planning and Building Standards has been identified
as a key service constraint that is causing delays for both customers and staff and a number of unsustainable workarounds are required. A
business case and funding for a fully integrated IDOX based Document Management System with our existing IDOX Uniform Enterprise case
management system has been approved to proceed. The service is progressing with implementation of the new system and it is expected to be
fully in place by summer 2026. 
Action: Complete the installation of the new document management system for Planning and Building Standards 
Food (Promotion and Placement) (Scotland) Regulations 2025 
The introduction of the Food (Promotion and Placement) (Scotland) Regulations 2025 in October 2026 is designed to restrict the promotion of
food and drink high in fat, sugar or salt.  
Local authorities will be responsible for enforcing the policy using powers in the Food Safety Act 1990 and the Food (Scotland) Act 2015. There
have been no additional resources provided by the Scottish Government for this, creating an extra burden on the team. This means we that we
cannot proactively enforce this legislation, which is a similar position taken by other local authorities. However, we will ensure Environmental
Health Officers are trained to respond to the regulations where required. 
Action: Provide Environmental Health Officers with the appropriate training to respond to the Food (Promotion and Placement) (Scotland)
Regulations 2025 where required 
Enterprise Resource Planning System 
The Council is implementing a new enterprise resource planning system (ERP). The system will initially focus on Finance but there are optional
modules covering other areas of the business such as Human Resources, Procurement and Warehousing. 
Page 143

Page 144

As part of the roll out, there will need to be connectivity setup to allow the new system to communicate with the Council’s existing purchase to
pay system, responsibility for which sits with the procurement team. There is also the option to switch to the ERP’s own purchase to pay system,
utilise its contract management module and / or its contract database module. The procurement team will therefore form part of the wider project
team and support the implementation of the new system and its potential development in relation to procurement. 
Action: Support the implementation and development of a new Enterprise Resource Planning System in relation to procurement 
Continuous Improvement 
Continuous improvement is central to all that we do. The actions set out in this section, as well as those at an operational level not included in
this Delivery Plan, demonstrate our commitment to continuous improvement and take account of the wider Best Value focus on vision and
leadership; governance and accountability; effective use of resources; partnerships and collaborative working; working with communities;
sustainability; and fairness and equality. 
Action Plan 
The challenges identified in Section 2 and the key factors identified in Section 3 have informed Regulatory & Regeneration priorities for 2026/27.
Appendix 1 sets out the action plan to address them. It also includes:
• performance indicators that will enable progress to be monitored and reported to stakeholders;
• strategic workforce actions to address workforce issues identified in the planning process; and
• strategic and/or service risks. 
In relation to the latter, strategic risks represent the potential for the Council to take advantage of opportunities or fail to meet stated strategic
objectives and that require strategic leadership. Service risks relate to service delivery and represent the potential for impact on individual
services, or the experience of those who work within the services, i.e. employees, partners, contractors and volunteers, or service users and
clients in receipt of the services provided. In identifying the relevant risks for 2026/27 and actions to mitigate them, we aim to improve or
maintain the current position (i.e. the current risk score) set out in the appendix. 
Page 144

Page 145

4. Resources 
Finance 
Regulatory & Regeneration has a net revenue budget of £5.829m and a capital budget of £11.471m in 2026/27. A breakdown by service area is
set out below. We will make the best use of the resources available to deliver on key priority areas and secure external/match funding where this
is possible.      
Service Area Gross Expenditure
2026/27 (£m)
Gross Income
2026/27 (£m)
Net Expenditure
2026/27 (£m)
Capital Budget
2026/27 (£m) (Figures subject to ongoing verification)
Democratic & Registration 1.832 0.115 1.717 0.000
Environmental Health 1.056 0.374 0.682 0.000
Licensing 0.272 0.465 -0.193 0.000
Legal Services & Trading Standards 1.016 0.088 0.928 0.000
Procurement 0.789 0.080 0.709 0.000
Building & Planning 1.461 0.743 0.718 0.000
Economic Development 1.887 0.619 1.268 11.471
Total 8.313 2.484 5.829 11.471
Page 145

Page 146

Employees 
Employee Numbers
The headcount and full time equivalent (FTE) staff in each service area (as of 31st March 2026) are as follows: 
Absence 
The 2025/26 quarterly absence figures for Regulatory & Regeneration are shown below together with the Council average for the same periods
for comparison. Absence was lower than the Council average throughout 2025/26: 
Absence in 2025/26 Quarter 1 Quarter 2 Quarter 3 Quarter 4 Annual FTE* days lost
per FTE employee
Regulatory & Regeneration 3.08% 2.94% 1.71% 2.2% 6.35
Council Wide Total 6.17% 5.39% 7.2% 7.65% 14.38  
Regulatory and Regeneration Headcount FTE
Democratic and Registration Services 28 19.8
Economic Development 19 17.8
Legal Services 21 19.3
Planning, Building Standards and Environmental Health 35 33.6
Regulatory Management 2 2
Procurement 11 10.8
TOTAL 116 103.3
Page 146

Page 147

Appendix 1: Action Plan 
Please Note: PI targets for 2026/27 are indicative until 2025/26 year-end values are available. 
1. Our communities 
Our residents’ health and wellbeing remains a priority 
Performance Indicator
2026/27
Owner
Target
Percentage of air quality monitoring stations complying with the national objective for nitrogen dioxide at the
nearest building façades of residential properties, schools, hospitals and care homes (40ug/m3 NO2) 100% Mark Walsh
Percentage of highest priority pest control service requests responded to within 2 working days 95% Eilidh Paton
Percentage of planned underage sales visits carried out by Trading Standards to premises registered on the
Scottish Government tobacco and nicotine vapour product retailers register 95% Annemarie
Clelland
Financial impact of disruptive activities carried out by Trading Standards on illegal trading  N/A Annemarie
Clelland
Percentage of businesses brought into compliance by Trading Standards 75% Annemarie
Clelland
Percentage of Environmental Health service requests from citizens first responded to within 2 working days 90% Eilidh Paton
Food Law: Percentage of food businesses in the highest risk category (1 to 6 monthly inspections by Food &
Business Group) that were inspected on time 100% Eilidh Paton
Food Law: Percentage of food businesses in the high-risk category (12 monthly inspections by Food &
Business Group) that were inspected on time 80% Eilidh Paton
Page 147

Page 148

Performance Indicator
2026/27
Owner
Target
Food Law: Percentage of food businesses in the medium to low-risk category (>12 Monthly inspections by
Food and Business Group) that were inspected on time 60% Eilidh Paton 
Action Due Date Owner
Implement the extension of the statutory duty (Tobacco and Vapes Bill) placed upon the Council in line with
our enforcement policy 31-Mar-2027 Annemarie
Clelland
Deliver collaborative projects with our Trading Standards partners 31-Mar-2027 Annemarie
Clelland
Provide advice to businesses re the introduction of Vaping Products Duty and ensure compliance of vaping
products 31-Mar-2027 Annemarie
Clelland
Provide Environmental Health Officers with the appropriate training to respond to the Food (Promotion and
Placement) (Scotland) Regulations 2025 where required 31-Mar-2027 Eilidh Paton 
Risk Description Current
Assessment
Target
Assessment Owner
Failure to monitor and
enforce regulatory areas
with public risk
The Council fails to comply with statutory regulatory duties in
respect of environmental health, trading standards and
licensing laws 
Annemarie
Clelland;
Manager of
Legal and
Democratic
Services; Eilidh
Paton
Page 148

Page 149

Risk Description Current
Assessment
Target
Assessment Owner
Failure to adequately
respond and investigate
intelligence relating to
fireworks being sold from
residential and non-
registered business
premises
The Trading Standards Service was challenged by the number
of complaints and intelligence in relation to the storage and
sale of fireworks in 2025/26. With concerns over a growing
societal issue around the misuse of fireworks there is no
reason to believe that 2026/27 will see a reduction.    
Annemarie
Clelland
Failure to adequately
respond to an
emergency situation
such as a multiple fatality
workplace accident,
outbreak of food borne
communicable disease,
a major public health
incident or pandemic
There is a national shortage of qualified staff in Environmental
Health, across Scotland. This impacts on West Dunbartonshire
Council. Vacancy levels at WDC might impact on our ability to
respond to emergencies.   
Eilidh Paton 
Our residents are supported to increase life and learning skills 
Action Due Date Owner
Continue to contribute to the Community Learning and Development Plan 2024-2027 31-Mar-2027 Colin Smith 
2. Our Environment 
Our local environment is protected, enhanced and valued
Page 149

Page 150

Performance Indicator
2026/27
Owner
Target
Air Quality: PM10 Concentration 18 Mark Walsh 
Our resources are used in an environmentally sustainable way
Performance Indicator
2026/27
Owner
Target
Tonnage of carbon dioxide emissions from Council operations and assets 17,035 Amanda Kean 
Action Due Date Owner
Develop the Climate Change Strategy 2026-2031 and associated Action Plan for 2026/27 31-Mar-2027 Amanda Kean
Complete the Local Heat and Energy Efficiency Delivery Plan for implementation 31-Mar-2027 Amanda Kean 
Risk Description Current
Assessment
Target
Assessment Owner
Inability to reduce carbon
footprint in line with
targets
The risk that the Council will be unable to achieve net zero
emissions by 2045, both in relation to mitigating carbon
emissions and adapting to the impacts of climate change. Net
zero refers to achieving an overall balance between emissions
produced and emissions taken out of the atmosphere. This
target has been developed in a way that mirrors the emission
reduction trajectory set by the Scottish Government in light of
the Climate Emergency. 
Alan Douglas;
Amanda Kean;
Gail Macfarlane 
Page 150

Page 151

Our neighbourhoods are sustainable and attractive 
Action Due Date Owner
Finalise the Visitor Levy Scheme for introduction in July 2027 31-Mar-2027 Gillian Scholes 
3. Our Economy 
Our area has the infrastructure for sustainable and inclusive growth where businesses can flourish 
Performance Indicator
2026/27
Owner
Target
Number of businesses given advice and assistance to start up through Business Gateway 180 Gillian Scholes
Percentage of procurement spent on local small/medium-sized enterprises and SMEs who have a presence in
West Dunbartonshire 36% Iain Skene
Number of business gateway start-ups per 10,000 population 19.78 Gillian Scholes
Proportion of properties receiving superfast broadband 99% Gillian Scholes
Immediately available employment land as a % of total land allocated for employment purposes 40 Michael Mulgrew 
Action Due Date Owner
Deliver key strategic regeneration sites across West Dunbartonshire 31-Mar-2027 Magda Swider
Promote the next phases of Queens Quay Housing 31-Mar-2027 Michael Mulgrew;
Magda Swider
Page 151

Page 152

Action Due Date Owner
Explore commercial opportunities in our town centres and wider regeneration sites 31-Mar-2027 Magda Swider
Support town centre revitalisation 31-Mar-2027 Magda Swider
Develop a new Economic Development Strategy 2027-2032 31-Mar-2027 Gillian Scholes 
Risk Description Current
Assessment
Target
Assessment Owner
Failure to deliver Queens
Quay Masterplan
Following completion of Council investment there is a risk the
housing plot sales do not materialise in the next 3-7 years,
with implications for the return on investment and the business
case for the District Heating Network.   
Michael
Mulgrew;
Magda Swider
Inability to meet
demands of Council to
progress regeneration
projects within desired
timescales
The number and complexity of regeneration projects is putting
considerable strain on the resources available which can be
exacerbated by delays out with the control of the service and
when pinch points on different projects occur at roughly the
same time.   
Manager of
Legal and
Democratic
Services;
Michael
Mulgrew;
Magda Swider 
4. Our Council 
Our workforce is resilient and skilled where digital technology supports service delivery for our residents 
Page 152

Page 153

Action Due Date Owner
Develop and implement wellbeing, employee engagement, equality and learning and development plans to
enable capabilities, improve resilience and promotion of a diverse workforce 31-Mar-2027 Alan Douglas
Develop and implement employee life cycle plans in line with the People First Strategy to attract and retain the
workforce 31-Mar-2027 Alan Douglas
Implement service review process including role design, use of new technology and new ways of working to
add resilience, address gaps, and establish opportunities for efficiencies 31-Mar-2027 Alan Douglas
Develop and implement learning and development plans and development opportunities to improve
capabilities and resilience within the workforce. 31-Mar-2027 Alan Douglas 
Our Council is adaptable and focused on delivering best value for our residents 
Performance Indicator
2026/27
Owner
Target
Planning Applications (Major Developments - Without Processing Agreement): Average number of weeks to
decision 16 Michael Mulgrew
Planning Applications (Locals - Householder): Average number of weeks to decision 8 Michael Mulgrew
Planning Applications (Other Locals): Average number of weeks to decision 8 Michael Mulgrew
Planning Applications (Major Developments – With Processing Agreements):  Percentage decided within
agreed target 90% Michael Mulgrew
Planning Applications (Locals – Householder): Percentage decided within statutory 8-week timescale 80% Michael Mulgrew
Planning Applications (Other Locals): Percentage decided within statutory 8-week timescale 80% Michael Mulgrew
Page 153

Page 154

Performance Indicator
2026/27
Owner
Target
Percentage of building warrant applications responded to within 20 working days 95% Judi Jamieson
Cash savings achieved from procurement activity £400,000.00 Iain Skene 
Action Due Date Owner
Provide legal services to the Council and West Dunbartonshire Energy LLP in relation to heat supply
agreements and network supply contracts 31-Mar-2027
Manager of Legal
and Democratic
Services
Prepare a robust evidence report for the next Local Development Plan (LDP3) for submission for Gatecheck to
Scottish Government Planning and Environmental Appeals Division 31-Mar-2027 Michael Mulgrew
Complete the installation of the new document management system for Planning and Building Standards 31-Mar-2027 Michael Mulgrew
Support the implementation and development of a new Enterprise Resource Planning System in relation to
procurement 31-Mar-2027 Iain Skene
Review the planning preapplication process 31-Mar-2027 Michael Mulgrew 
Risk Description Current
Assessment
Target
Assessment Owner
Inability to recruit
successfully to enable
performance to be
maintained
There is a current issue with recruitment of qualified staff in
various parts of the service. 
Michael
Mulgrew; Eilidh
Paton
Page 154

Page 155

Risk Description Current
Assessment
Target
Assessment Owner
Failure to secure best
value of procurement
spend and ensure
compliance with financial
regulations
Improved procurement management process, contract
strategies, planning, monitoring and reporting in collaboration
with services will continue to mitigate against non-compliant
procurement spend  
Iain Skene
Failure to continue to
achieve increased
savings from
procurement activity
As second or third generation revenue contracts seldom
deliver the same cost savings as first generation, the contract
strategies need to focus on governance, operating models,
total cost of ownership, service quality and innovation  
Iain Skene 
Our residents are engaged and empowered 
Performance Indicator
2026/27
Owner
Target
Percentage of Council and Committee minutes produced within 3 clear working days of the meeting 98% Carol-Ann Burns
Percentage of committee agendas published within standing order timescales 99% Carol-Ann Burns 
Action Due Date Owner
Continue the development of Community Planning 31-Mar-2027 Colin Smith
Review the Scheme for Establishment of Community Councils 31-Mar-2027
Manager of Legal
and Democratic
Services; Colin
Smith
Page 155

Page 156

Action Due Date Owner
Conduct Community Council Elections 31-Mar-2027
Manager of Legal
and Democratic
Services
Implement the Scottish Parliamentary Elections for the Dumbarton and Clydebank and Milngavie
Constituencies in May 2026 31-Mar-2027
Manager of Legal
and Democratic
Services
Prepare for the implementation of the Local Government Elections in May 2027 and arrange the induction of
newly elected members and formation of the new Council 31-Mar-2027
Manager of Legal
and Democratic
Services 
Risk Description Current
Assessment
Target
Assessment Owner
Engaging positively with
Residents, Communities
& Partnerships
The risk that the Council fails to adequately engage, establish
and maintain positive relationships with local residents and
communities in addition to partnership bodies. 
Colin Smith 
Page 156

Page 157

WEST DUNBARTONSHIRE COUNCIL 
Report by Chief Officer - Resources 
Committee: Corporate Services Committee 27 May 2026 
Subject: Resources Delivery Plan 2025/26 - Year-end Progress & 
Resources Delivery Plan 2026/27 
1 Purpose 
1.1 This report sets out the year-end progress of the 2025/26 Delivery Plan and
presents the new Delivery Plan for 2026/27. 
2 Recommendations 
2.1 It is recommended that Committee notes the progress achieved at year-end
and the new Plan for 2026/27. 
3 Background 
3.1 In line with the Strategic Planning & Performance Framework, each Chief
Officer develops an annual Delivery Plan which sets out actions to help deliver
the Strategic Plan and address the performance challenges and service
priorities identified in the planning process. The Plan also provides an
overview of services and resources, including employees and budgets, sets
out the performance indicators (PIs) for monitoring progress and considers the
relevant risks. 
4 Main Issues 
2025/26 Year-end Progress 
4.1 The 2025/26 Delivery Plan was presented to Corporate Services Committee
on 21 May 2025 and mid-year progress reported on 12 November 2025. 
4.2 Full details of year-end progress are set out in Appendix 1. 
4.3 The progress of the Plan’s 18 actions is summarised below: 
Progress No. (%) 
Completed 16 (89%) 
Overdue 2 (11%) 
ITEM 11
Page 157

Page 158

4.4 The overdue action relates to the following and will be carried forward and
completed in 2026/27:
• Complete the redevelopment of Glencairn House - 95% complete.
• Implement service review process including role design, use of new
technology and new ways of working to add resilience, address gaps, and
establish opportunities for efficiencies - 91% complete. 
4.5 Year-end data is available for nine of the Plan’s 20 PIs. The performance of
those PIs is summarised below: 
Performance Against Target No. (%) 
Target met or exceeded 9 of 9
(100%)
Performance Over Time
(As one of the nine PIs is new for 2025/26, this section relates to eight
PIs)
No. (%) 
Improved over short term (or maintained high level of
performance)
6 of 8 (75%) 
Improved over longer term (or maintained high level of
performance)
6 of 8 (75%) 
4.6 The full set of PIs will be reported through the Council’s annual performance
reporting process once all data becomes available. 
2026/27 Delivery Plan 
4.7 The 2026/27 Delivery Plan is set out at Appendix 2. 
4.8 Key priorities include:
• delivering sustainable, quality services within the context of significant
financial challenges
• implementing a new financial management system 
• reviewing ways to decrease corporate debt in relation to sundry, non-
domestic rates, Council Tax, and rent
• reviewing ways to improve rent collection rates in conjunction with
Housing and W4U
• automating Council processes and information provision
• progressing the disposal of key strategic sites
• maximising rental income from the Council’s non-operational property
portfolio
• reviewing non-domestic rates of the Council’s operational property
portfolio
• completing the Artizan redevelopment
• completing the Faifley Community Campus development
• progressing the buildings upgrades programme
• progressing the depot refurbishment programme
• supporting Council services to deliver the asset related savings agreed by
Council
Page 158

Page 159

• progressing the implementation of the Global Internal Audit Standards and
CIPFA’s Code of Practice for the Governance of Internal Audit in UK Local
Government within the internal audit team’s methodologies and processes
• progressing a shared service internal audit service 
4.9 Implementation of the Plan will be monitored by the management team with
mid-year and year-end progress reported to Corporate Services Committee
and Infrastructure, Regeneration and Economic Development Committee
(asset management elements only) around November 2026 and May 2027
respectively. 
5 People Implications 
5.1 There are no direct people implications arising from this report. 
6 Financial & Procurement Implications 
6.1  There are no direct financial or procurement implications arising from this
report. 
7 Risk Analysis 
7.1 Failure to deliver on the actions assigned to Resources may have a direct
impact on the delivery of the Council’s Strategic Plan. It is essential that
remedial action is taken to ensure strategic delivery plans achieve the
commitments detailed. 
8 Equalities Impact Assessment 
8.1 Screening and impact assessments will be carried out on specific activities as
required. 
9 Consultation 
9.1  The delivery plans were developed through consultation with officers from the
strategic service areas. 
10 Strategic Assessment 
10.1  The delivery plans set out actions to support the successful delivery of the
strategic priorities and objectives of the Council. 
Chief Officer: Laurence Slavin
Service Area:  Resources
Date:   30 April 2026
_____________________________________________________________
Page 159

Page 160

Person to Contact:  Lynn Henderson    
lynn.henderson@west-dunbarton.gov.uk 
Appendices:  Appendix 1: Resources Delivery Plan 2025/26 - Year-end
Progress  
Appendix 2: Resources Delivery Plan 2026/27 
Background Papers: Resources Delivery Plan 2025/26 - Corporate Services
Committee, 21 May 2025 
Resources Delivery Plan 2025/26 Mid-year Progress -
Corporate Services Committee, 12 November 2025 
Strategic Planning & Performance Framework 2022/27   
Wards Affected: All 
Page 160

Page 161

Official
Appendix 1: Resources Delivery Plan 2025/26 – Year-end Progress 
1. Our Communities 
Our residents are supported to increase life and learning skills 
Action Status Progress Due Date Note Owner
Complete the redevelopment of
Glencairn House  
31-Mar-
2026
Overdue. The redevelopment of Glencairn House, a
heritage-led regeneration initiative to transform a
historically significant building in Dumbarton town centre
into a vibrant cultural and community hub, is almost
complete. Practical completion was achieved in April
after the building was handed over to the Corporate
Assets team however snagging issues have emerged
which has delayed the timescales for opening the
building. This will be carried forward into 2026/27.
Michelle
Lynn
Progress the Faifley Community
Campus development  
31-Mar-
2026
Completed as planned. This £34.5 million investment
creates a modern, sustainable, purpose-built campus
that brings together education, community, and leisure
facilities under one roof. It provides state-of-the-art
classrooms, flexible learning spaces, and enhanced
digital infrastructure to support improved educational
outcomes. Phase 2 works relating to the demolition of
the old school buildings, the construction of outdoor
sports facilities, and external landscaping, are due to be
completed in 2026.
Michelle
Lynn 
ITEM 11 - APPENDIX 1
Page 161

Page 162

Official 
2. Our Environment 
Our neighbourhoods are sustainable and attractive 
Performance Indicator
2024/25 2025/26
Owner Value Status Value Target Short
Trend
Long
Trend Note
Percentage of Consultancy
Services project
deliverables for General
Services projects delivered
as planned
New for
2025/26  100% 80% N/A N/A Target exceeded. Michelle
Lynn 
Action Status Progress Due Date Note Owner
Progress the building upgrades
programme  
31-Mar-
2026
Completed as planned. All works were completed on
schedule and within budget. They included
improvements across a range of assets, from education
and community facilities to operational depots,
embedding sustainability principles such as energy-
efficient systems, low-carbon materials, and improved
accessibility.
Our strong performance is further demonstrated through
the latest Local Government Benchmarking Framework
data for 2024/25, where West Dunbartonshire exceeded
both the Scottish and family group averages for
suitability and condition of operational buildings. We
achieved a national ranking of 6th for suitability and 13th
for condition out of 32 councils, reflecting the positive
impact of sustained investment and effective asset
management.
Michelle
Lynn 
Page 162

Page 163

Official 
3. Our Economy 
Our area has the infrastructure for sustainable and inclusive growth where businesses can flourish 
Performance Indicator
2024/25 2025/26
Owner Value Status Value Target Short
Trend
Long
Trend Note
Number of invoices paid
within 30 calendar days of
receipt as a percentage of
all invoices paid
91.6%   91%   2025/26 data available May. Ryan
Chalmers 
Our partnerships support economic development to deliver increased prosperity for our area 
Performance Indicator
2024/25 2025/26
Owner Value Status Value Target Short
Trend
Long
Trend Note
Time for processing
applications for new
Housing Benefits claims
from application receipt date
to the day the claim is
decided
23  16.7 25  
Target met with excellent
performance from the team in
2025/26 despite the challenges of
increased workloads within the
service.
Ryan
Chalmers
Time for processing
applications for notifications
of changes of
circumstances for Housing
Benefits from the application
receipt date to the day the
claim is decided
4.2  5 5  
Target met despite the increased
workloads in the service including
an increase in full case reviews
that are carried out to ensure
accuracy and reduce fraud.
Ryan
Chalmers 
Page 163

Page 164

Official 
4. Our Council 
Our workforce is resilient and skilled where digital technology supports service delivery for our residents 
Action Status Progress Due Date Note Owner
Develop and implement
wellbeing, employee
engagement, equality and
learning and development plans
to enable capabilities, improve
resilience and promotion of a
diverse workforce  
31-Mar-
2026
Completed as planned. We continue to develop
succession planning and build resilience in key areas
across our services. This is done in a number of ways,
including revised management structures, identifying
potential within current teams to address skills gaps,
mapping resilience for critical roles and tasks, including
cover arrangements for short-term absence, and
highlighting gaps where alternative approaches (e.g.
cross-service collaboration, short-term development
opportunities) may be required. 
Laurence
Slavin
Develop and implement
employee life cycle plans in line
with the People First Strategy to
attract and retain the workforce  
31-Mar-
2026
Completed as planned. Responding to recruitment
challenges is difficult in the current climate with
significant financial pressures and a competitive job
market. However, through succession planning, we have
sought to develop career pathways and development
opportunities where possible.
Laurence
Slavin
Implement service review
process including role design,
use of new technology and new
ways of working to add
resilience, address gaps, and
establish opportunities for
efficiencies  
31-Mar-
2026
Overdue. The Internal Audit service was reviewed and a
new service delivery model identified and implemented.
Within Finance, implementation continues in line with the
timetable with all actions due in 2025/26 completed:
temporary posts in place, succession planning
completed, Finance Business Partners realigned.
Implementation will continue into 2026/27 as planned. 
Laurence
Slavin
Page 164

Page 165

Official
Action Status Progress Due Date Note Owner
A restructure of Corporate Asset Management is also
well underway, looking at a range of matters including
staff development, career progression, and a trainee
post. However, due to resourcing issues, we have been
unable to complete this by year-end. It will be carried
forward and completed in 2026/27.
Develop and implement learning
and development plans and
development opportunities to
improve capabilities and
resilience within the workforce  
31-Mar-
2026
Completed as planned. Cross-skilling for resilience and
career progression has been implemented in Finance
Services and Corporate Asset Management. In Business
Support, given the financial pressures and a limited
training budget, focus has been on maximising internal
opportunities such as job shadowing, project-based
development, and knowledge sharing across teams.
Regular discussions with staff continue to identify and
support career conversations, ensuring staff feel valued
and engaged despite constrained resources.
Laurence
Slavin 
Our Council is adaptable and focused on delivering best value for our residents 
Performance Indicator
2024/25 2025/26
Owner Value Status Value Target Short
Trend
Long
Trend Note
Percentage of council
buildings in which all public
areas are suitable for and
accessible to disabled
people
97%  97% 97%  
Target met with performance
consistently high over both the
short and long terms.
Michelle
Lynn
Page 165

Page 166

Official
Performance Indicator
2024/25 2025/26
Owner Value Status Value Target Short
Trend
Long
Trend Note
Value of outstanding sundry
debt as a percentage of
total that is more than 90
days old from date of
invoice
65.4%   70%   2025/26 data available May. Ryan
Chalmers
Rent collected as a % of
total rent due 99.58%  99.96% 99.4%  
Target met with improved
performance from 2024/25 which
is an excellent achievement
considering the impacts on rent
collection.  The continued financial
challenges facing tenants due to
the current cost of living,
increased rent and council tax and
while the reduction in Department
for Work & Pensions deductions
from benefits towards arrears
provides additional benefits to
tenants, this impacts the rent
collection if these are not paid by
tenant. From April 2024/25,
Department for Work & Pensions
introduced the Fairer Repayment
Rate which saw previous
deductions towards rent arrears
decrease from 25% to 15%,
therefore all deductions to the
Council dropped by 10% which
was a significant decrease in
Ryan
Chalmers
Page 166

Page 167

Official
Performance Indicator
2024/25 2025/26
Owner Value Status Value Target Short
Trend
Long
Trend Note
income for rent.  However, due to
the early intervention by the
Corporate Debt team on these
cases, this reduced the impact of
this loss enabling us to meet
target.
Percentage of capital
receipts achieved as
forecast
100%  90% 90%   Target achieved in 2025/26 as per
programme.
Michelle
Lynn
Cost of collecting council tax
per dwelling £0.68   £2.00   2025/26 data available May. Ryan
Chalmers
Percentage of income due
from council tax received by
the end of the year
93.8%   93.9%   2025/26 data available May. Ryan
Chalmers
Proportion of operational
buildings that are suitable
for their current use
95%  95% 93%  
Target exceeded. Based on the
LGBF comparative data for
2024/25 published by the
Improvement Service in February
2026, performance was better
than the Scottish average of
85.7% and better than the family
group average of 86.1%, with a
ranking of 6 of 32 local authorities,
up 4 places from the previous
year.
Michelle
Lynn
Page 167

Page 168

Official
Performance Indicator
2024/25 2025/26
Owner Value Status Value Target Short
Trend
Long
Trend Note
Proportion of internal floor
area of operational buildings
in satisfactory condition
93%  93% 91%  
Target exceeded. Based on the
LGBF comparative data for
2024/25 published by the
Improvement Service in February
2026, performance was better
than the Scottish average of
91.0%, and better than the family
group average of 90.1%, with a
ranking of 13 of 32 local
authorities, consistent with the
previous year.
Michelle
Lynn
Current tenants' arrears as
a percentage of total rent
due
8.18%   9%   2025/26 data available May. Ryan
Chalmers
Gross rent arrears (all
tenants) as at 31 March
each year as a percentage
of rent due for the reporting
year
8.81%  8.46% 9.3%  
Target met with improved
performance from 2024/25 which
is an excellent achievement
considering the impacts on rent
collection.  The continued financial
challenges facing the tenants due
to the current cost of living,
increased rent and council tax and
while the reduction in Department
for Work & Pensions deductions
from benefits towards arrears
provides additional benefits to
tenants, this impacts the rent
Ryan
Chalmers
Page 168

Page 169

Official
Performance Indicator
2024/25 2025/26
Owner Value Status Value Target Short
Trend
Long
Trend Note
collection if these are not paid by
tenant. From April 2024/25,
Department for Work & Pensions
introduced the Fairer Repayment
Rate which saw previous
deductions towards rent arrears
decrease from 25% to 15%,
therefore all deductions to the
Council dropped by 10% which
was a significant decrease in
income for rent.  However, due to
the early intervention by the
Corporate Debt team on these
cases, this reduced the impact of
this loss enabling us to meet
target.
Income generated as a % of
total revenue budget 11%   11%  
2025/26 value will be available
after 30 June 2026 following the
completion of the draft financial
statements.
Carol
Alderson 
Action Status Progress Due Date Note Owner
Progress the procurement of a
new Financial Management
System  
31-Mar-
2026
Completed as planned. The project is progressing well
with the system scoping and set-up on track. Work is
also underway around agreeing the most appropriate
data migration strategy. Phase 1 will continue into
Arun Menon
Page 169

Page 170

Official
Action Status Progress Due Date Note Owner
2026/27, with activities related to system configuration
and set-up.
Review ways of decreasing
corporate debt through
continued improvements to debt
collection processes in relation
to sundry, NDR, Council Tax
and rent  
31-Mar-
2026
Completed as planned. Changes have been made to
some processes to streamline and improve collections
with Debt Partners and the Department for Work and
Pensions. A new action plan has been developed for
2026/27 to manage the impact of the financial pressures
faced by residents.
Ryan
Chalmers
Review ways to improve rent
collection rates in conjunction
with Housing and W4U  
31-Mar-
2026
Completed as planned. The Government’s Fairer
Repayment Policy has impacted rent collection with a
reduction in the income from the Department for Work &
Pensions of 8% compared to 2024/25. This increases
contact with tenants as a result of rent arrear deductions
decreasing to the Council with an increased income to
the tenant, therefore arrangements need to be set up
and/or reviewed as a result. An action plan has been
developed for 2026/27 to improve rent collection and
support tenants.
Ryan
Chalmers
Maximise automation
opportunities across the Council  
31-Mar-
2026
Completed as planned. Workstream progressing well
with several automations completed in relation to a
range of activities including commercial waste invoices,
sickness absence notifications and school meals and
clothing grants. New ideas are regularly sought and
programmed into the pipeline.
Arun Menon
Progress the disposal of key
strategic sites  
31-Mar-
2026
Completed as planned. We implemented the Council’s
Disposal Strategy, ensuring surplus and underutilised
assets were identified, marketed, and sold in line with
strategic objectives, delivering the agreed capital
receipts.
Michelle
Lynn
Page 170

Page 171

Official
Action Status Progress Due Date Note Owner
Progress the depot
refurbishment programme  
31-Mar-
2026
Completed as planned. The successful refurbishment of
Council depots ensures these operational hubs remain fit
for purpose and compliant with health, safety, and
environmental standards and that they embed
sustainability principles to reduce environmental impact
and support the Council’s net-zero targets, including
energy efficient systems, improved insulation and low-
carbon materials.
Michelle
Lynn
Develop and implement plans
and support services to achieve
the asset related savings
agreed by Council  
31-Mar-
2026
Completed as planned. We consulted with services to
support them to achieve the asset related savings due in
2025/26.
Michelle
Lynn
Review new Global Internal
Audit Standards and new CIPFA
Code of Practice and identify
and implement any actions to
ensure compliance  
31-Mar-
2026
Completed as planned. A detailed gap analysis was
carried out between current practice and required
practice. This identified that operational aspects are
broadly compliant with the new standards. Additional
actions in relation to training and raising further
awareness throughout the Council will be taken forward
by the new manager in 2026/27.
Andi
Priestman
Review eligibility for Council Tax
exemptions and identify
potential income due to the
Council  
31-Mar-
2026
Completed as planned. A report has been compiled with
the findings generating some good outcomes for the
Council in terms of income due.
Andi
Priestman 
Page 171

Page 172

Official
Risk Description Current
Assessment
Target
Assessment
Date
Reviewed Note Owner
Debt is not
recovered
efficiently or
effectively, with
inherent risk of
financial loss
The processes deployed in
collection of monies owed to the
Council are inefficient and
ineffective resulting in money
not collected on time or having
to be written off.   
11-Mar-
2026
The risk score remains
unchanged from mid-year. We
effectively implement the
Corporate Debt Policy and
ensure income maximisation
through improvements to the
automation of collecting debt.
Ryan
Chalmers
Increase in the
level of rent
arrears due to
the level of
Welfare Reform
changes and
general state of
economy
The Council sees an increase in
its level of rent arrears due to
lower disposable income and
national changes to the national
benefits regime and the ongoing
economic position   
11-Mar-
2026
The risk score is unchanged from
mid-year and remains high due to
the current cost of living that is
linked to increasing energy costs,
food costs and inflation. Financial
support and advice is provided to
those impacted by the cost of
living with arrangements being
reviewed as appropriate.
Ryan
Chalmers
Maintaining
Council Assets
that are fit for
purpose
The risk that the Council's
assets and facilities are not fully
fit for purpose with consequent
adverse impact on our ability to
deliver efficient and effective
services. Assets included in this
assessment are the Council’s
property portfolio.  
01-Apr-
2026
The risk score remains low due to
the ongoing programme of capital
works. The Property Action Plan
2023-28, approved at
Infrastructure, Regeneration and
Economic Development
Committee in February 2023, will
monitor all requirements to
maintain the risk score.
Michelle
Lynn 
Page 172

Page 173

Official 
Our residents are engaged and empowered 
Performance Indicator
2024/25 2025/26
Owner Value Status Value Target Short
Trend
Long
Trend Note
Percentage of council
resources directed by
communities
0.94%   1%  
2025/26 data will be available late
August 2026 when it is submitted
to CoSLA (Convention of Scottish
Local Authorities).
Carol
Alderson;
Colin Smith 
Action Status Progress Due Date Note Owner
Engage with relevant
community groups over the
potential to lease Dalmuir Golf
Course  
31-Mar-
2026
Completed as planned. Lease transaction to the existing
users was completed 1 July 2025.
Michelle
Lynn 
Strong financial governance and sustainable budget management (Service Objective) 
Performance Indicator
2024/25 2025/26
Owner Value Status Value Target Short
Trend
Long
Trend Note
Amount of free reserves as
a percentage of the
prudential reserve target -
HRA
74%   100%  
2025/26 value will be available
after 30 June 2026 following the
completion of the draft financial
statements.
Carol
Alderson
Amount of free reserves as
a percentage of the
prudential reserve target -
General services
61%   100%  
2025/26 value will be available
after 30 June 2026 following the
completion of the draft financial
statements.
Carol
Alderson
Page 173

Page 174

Official
Performance Indicator
2024/25 2025/26
Owner Value Status Value Target Short
Trend
Long
Trend Note
Percentage variance to
budget projected (General
Services budget)
1.01%   0%  
2025/26 value will be available
after 30 June 2026 following the
completion of the draft financial
statements.
Carol
Alderson
Percentage of Audit Plan
completed 60%   85%   2025/26 data available September
2026.
Andi
Priestman 
Action Status Progress Due Date Note Owner
Develop and refine capital and
revenue reporting processes  
31-Mar-
2026
Completed as planned. Revised revenue Budgetary
Control Report presented to Council to improve
transparency and a separate quarterly treasury update
will be reported alongside the capital budgetary control
reports from Period 3 in financial year 2026/27.
Carol
Alderson 
Risk Description Current
Assessment
Target
Assessment
Date
Reviewed Note Owner
Failure to
provide a
reasonable level
of assurance on
the Council's
governance, risk
management
and internal
control
procedures 
Internal Audit is unable to
provide a reasonable level
assurance on the Council's
governance, risk management
and internal control
arrangements.   
01-Apr-
2026
Risk remains unchanged from
mid-year. 
The Internal Audit Annual Report
and Assurance Report for
2025/26 will be presented to June
Audit Committee outlining the
current status of the plan. It is
intended that as much fieldwork
as possible will be completed by
end of June to inform the year
Andi
Priestman
Page 174

Page 175

Official
Risk Description Current
Assessment
Target
Assessment
Date
Reviewed Note Owner
end audit opinion but this
depends on capacity to complete
the plan as there have been
further vacancies arising in the
team. There is also the annual
governance statement work
where Chief Officers provide a
self-assessment of compliance
with the local code of good
governance which provides
further assurance.
Failure to meet
statutory
deadlines for
external returns
(including
HMRC) and
financial
statements
Finance Services failing to meet
statutory deadlines resulting in
lost revenue or penalty costs 
12-Mar-
2026
The current assessment remains
unchanged. While the risk
remains high due to staff
turnover, difficulty recruiting staff
with relevant experience, and
issues with business continuity,
there are a range of controls in
place to mitigate it.
Carol
Alderson
Financial
projections are
significantly
incorrect
Financial projections for both
capital and revenue are
significantly incorrect resulting in
insufficient reserves being held.   
20-Feb-
2026
Information on projections is
updated on an ongoing basis.
However, with the volatility of the
economy, and general inflationary
issues, the figures are changing
regularly. The Council's Chief
Financial Officer engages
regularly with the Directors of
Finance across all 32 Scottish
Councils to sense check material
Laurence
Slavin
Page 175

Page 176

Official
Risk Description Current
Assessment
Target
Assessment
Date
Reviewed Note Owner
assumptions in financial
forecasts. Furthermore, there is
regular engagement with the
Council's appointed Treasury
advisors in relation to projected
future changes to bank interest
rates.
Significant
financial funding
reductions /
limitations from
Scottish
Government
It is expected the Council will
continue to be faced with
significant real term funding
reductions from the national
settlement. This is based on
local government settlements in
recent years (with the exception
of 2025/2026). This coincides
with a period where costs and
demographic pressures are
continuing to rise in relation to
social care, significant
inflationary increases and pay
award pressures linked to
inflation.  
20-Feb-
2026
It is expected the Council will
continue to be faced with
significant real term funding
reductions from the national
settlement. This is based on the
Spending Review published by
the Scottish Government in
January 2026 which sets out
multi-year spending plans over
the three-year period 2026/27-
2028/29 across the various
portfolios. It illustrates that Local
Government funding, in cash
terms, is expected to decrease by
0.07% over the three-year period
which will require councils to
absorb the financial pressures
brought about by all inflationary
increases.
Laurence
Slavin 
Page 176

Page 177

Official
Action Status 
Overdue 
Completed 
PI Status 
Target met or exceeded 
Risk Status 
Alert 
Warning 
OK 
Long Term Trends 
Improving 
No change 
Getting worse 
Short Term Trends 
Improving 
No change 
Getting worse 
Page 177

Page 178

2026/27
RESOURCES
Appendix 2: Resources Delivery Plan 2026/27
ITEM 11 - APPENDIX 2
Page 178

Page 179

Contents` 
1. Introduction .................................................................................................................................................................................................... 2
2. Performance Review ...................................................................................................................................................................................... 2
3. Strategic Assessment .................................................................................................................................................................................... 5
4. Resources .................................................................................................................................................................................................... 12
Appendix 1: Action Plan .......................................................................................................................................................................................... 14 
Page 179

Page 180

1. Introduction 
Resources comprises Finance, Business Support, Internal Audit & Fraud and Asset Management. It provides accountancy, treasury
management, business support, internal audit and fraud and asset management services to the Council and external clients including the West
Dunbartonshire Leisure Trust, the Valuation Joint Board, Clydebank Property Company, charities and trusts, and West Dunbartonshire Energy
Ltd. Company. In addition, it provides direct services to residents of West Dunbartonshire. 
It is one of seven strategic areas responsible for delivering the Council’s Strategic Plan. Key actions to help achieve that are set out in this
Delivery Plan, together with actions to address any performance issues and service priorities identified in the planning process. Progress will be
monitored and managed by the management team and reported to Corporate Services Committee and Infrastructure, Regeneration & Economic
Development Committee (asset management elements only) twice yearly, at mid-year and year-end. 
2. Performance Review 
The Resources management team completed a detailed review of 2025/26 performance, focusing on: 
• 2025/26 Delivery Plan year-end progress
• Local Government Benchmarking Framework (LGBF) comparative performance
• Citizens’ Panel feedback
• Complaints. 
This review highlighted our key achievements and challenges in 2025/26. These are summarised below. 
Key Achievements in 2025/26 
Finance
• Implemented new processes across finance to streamline the year end timetable and presented the 2024/25 Annual Accounts to Council by
the 18 June 2025, two months earlier than previous year ensuring draft Accounts were submitted by the statutory deadline.
• Delivered service and financial returns to public sector bodies.
• Supported transformation projects within the Council and completed procurement exercise for a new financial ledger system.
• Continued to refine Revenue and Capital reporting.
Page 180

Page 181

• Developed a revised team structure, scheduled for implementation in 2026/27, to ensure operational resilience following anticipated
retirement of senior team members within the same period.
• Upgraded the cash receipting system to enhance security and Payment Card Industry compliance.
• Introduced automation to streamline the reconciliation and banking processes.
• Identified an opportunity to terminate £33.1m of long-term fixed rate loans in return for a discounted repayment amount. The total discount for
early repayment was £4.3m which was used to rebuild the Council and HRA reserves. 
Business Support 
• Processed £0.5m in Clothing Grants to parents and carers of 3,764 school pupils. 
• Processed £2.8m in Discretionary Housing Payments to assist 4,112 vulnerable tenants with housing costs.
• Processed £22.3m in Housing Benefit payments to assist residents with housing costs.
• Processed £10.1m in Council Tax Reduction payments to assist residents with council tax charges.
• Improved the rent arrears process, working in partnership with Housing and Department for Work and Pensions Universal Credit Service.
• Increased efficiency by developing and improving automation solutions to process Employee New Start, Sickness Absence, Teachers
Pension Notification, Free School Meals, Clothing Grants and Discretionary Housing payments.
• Continued to develop automations across the council services to aid challenging budget savings targets. 
Internal Audit & Fraud
• Three new reports were received through the National Fraud Initiative exercise comparing CTRS data to HMRC data. Matches identified are
being investigated and at 31 March 2026, 59 overpayments totalling £176,174 have been identified and are now being recovered.
• Finalised the 2024/25 annual audit plan and progressed the 2025/26 audit plan.
• Delivered actual recoveries and re-billings of £300,870 (1 April 2025 to 31 March 2026) through the Corporate Fraud Team. 
Asset Management 
• Progressed the delivery of the Glencairn House project which is an ambitious heritage-led regeneration initiative to transform a historically
significant building into a vibrant cultural and community hub, preserving its architectural character while introducing modern facilities.
Practical completion has been achieved, however post completion a snagging issue has been identified and this is currently being rectified.
• Delivered the Faifley Campus project which is a £34.5million investment to create a modern, purpose-built campus that brings together
education, community, and leisure facilities under one roof and provides state-of-the-art classrooms, flexible learning spaces, and enhanced
digital infrastructure to support improved educational outcomes. 
Page 181

Page 182

• Played a pivotal role in advancing the development phase of the Exxon City Deal Project, a major regeneration initiative designed to unlock
economic growth and improve connectivity across West Dunbartonshire. This phase focused on complex preparatory work, including
extensive stakeholder engagement with landowners, statutory bodies, and community representatives to ensure alignment with planning and
infrastructure requirements. 
• Played a critical role in the successful refurbishment of Council depots and the school estate, ensuring these operational hubs remain fit for
purpose and compliant with health, safety, and environmental standards and embed sustainability principles, incorporating energy efficient
systems, improved insulation, and low-carbon materials to reduce environmental impact and support the Council’s net-zero targets.
• Completed the Posties Park project which was a flagship development to transform Posties Park into a state-of-the-art sports hub, delivering
on the Council’s commitment to high-quality facilities that promote community engagement, health, and leisure. Originally moved to Asset
Management in January 2025, the project overcame earlier delays and was successfully managed to ensure steady progress and adherence
to the revised schedule. By completing and renaming the development as Lachie Stewart Memorial Park in October 2025, the Council has
delivered a sustainable, inclusive facility that enhances local wellbeing and supports active lifestyles. 
Key Challenges in 2025/26 
Finance
• Reconciling and managing a significant number of funding streams, mainly due to Scottish Government priorities within limited resource
constraints.
• Providing personal development for staff by allocating new roles to officers resulting in a significant learning curve whilst continuing to provide
a quality service to customers.
• Maintaining the level of service delivery with conflicting pressures and resource constraints.
• Collaborating with External Audit to work to restore the audit timetable to its planned schedule while the finance team balance competing
demands and sustaining continuity of service delivery and continue to ensure timely delivery of all required outputs such as the 2026/27
budget, budgetary control reporting and other local authority returns.
• Continuing to manage cost pressures within the services and deliver a balanced budget. 
Business Support
• Collection of rent arrears was impacted by reductions in direct deductions from 25% to 15% due to the DWP’s Fairer Repayment Rate. This
reduction of 10% from April 2025 across all deductions which impacted collection rates.
• Collection of council tax was also impacted by Fairer Repayment Rate, increased cost of living pressures along with the 11.5% Council Tax
increase in 2025/26. 
Page 182

Page 183

• Managing levels of service delivery with the levels of resource reductions across business support and other services that had a direct impact
on the collection work of the Corporate Debt Section with residents requiring additional financial and personal support. 
Internal Audit & Fraud
• Providing a sustainable internal audit service longer term continued to be a challenge. On 23 November 2023, the now discontinued West
Dunbartonshire Council /Inverclyde Council Shared Services Committee agreed to note the continuation of shared Internal Audit and Fraud
management arrangements between the two councils in the short to medium term and that wider discussions would continue with
neighbouring councils on possible options to create a more sustainable delivery model for Internal Audit and Fraud Services over the longer
term. At the December 2024 Council meeting, elected members supported a small expansion to the number of posts covered under the
existing shared arrangement with Inverclyde Council. Recruitment to these posts was not successful, however discussions with a third
council, East Dunbartonshire, were progressed in late 2025 for a shared management arrangement across the three Councils which will be
implemented from 2026/27. 
Asset Management 
• Staff turnover, coupled with the time required to recruit, and train employees, continued to present significant challenges and is expected to
remain a pressure point into 2026/27. Retaining skilled staff and accelerating onboarding processes will be critical to maintaining service
continuity and delivering planned projects.
• The national skills shortage of qualified and experienced officers in Asset Management has led to a reduced workforce and increased
demands on existing teams. This has required the introduction of alternative service delivery models, including greater use of external
consultants and shared service arrangements, which will need careful management to ensure quality and cost control.
• Increasing supply chain issues driven by rising energy, transport, and raw material costs, continue to impact the availability of labour and
materials and ultimately project costs and delays. 
3. Strategic Assessment 
The Resources management team completed a strategic assessment to determine the major influences on service delivery and priorities in
2026/27. The key factors are summarised below. 
Page 183

Page 184

Key Factors 
Financial Challenges 
The entire public sector is continuing to face significant financial challenges due to a range of factors including inflationary cost increases, pay
awards not being fully funded by the Scottish Government and insufficient overall funding to support the delivery of front line and back-office
services. The Council is currently faced with an estimated cumulative funding gap in 2027/28 of £10.905m rising to £44.028m by 2030/31. We
will continue to monitor the overall financial position of the Council and updates on estimated future budget gaps will be reported to Elected
Members throughout 2026/27. 
These challenges require further action to balance our budget and protect services for residents. Within Resources, this means available funding
will be reduced over time and we will need to reconfigure how we work, what we do, where we work, and potentially reduce the number of
people employed. In this context, we will aim to continue to provide a sustainable, quality service to internal and external clients and the public. 
Budget Sensitivity Analysis 
In reviewing the service budget projections, consideration has been given to the sensitivity of these budgets, in particular for higher risk/ higher
value budgets which may have a significant impact on budgetary control and future budget projections. The analysis has considered sensitivity
around demand, costs and charges, and income levels. 
Within Resources, budgets which have been identified as being more susceptible to fluctuations include:
• Building materials which are subject to global supply chain pressures and price volatility
• Labour costs which are impacted by national skills shortages and recruitment challenges
• Transport fuel costs which are influenced by energy markets trends and inflation
• Capital plan delivery which is exposed to delays and cost escalation due to procurement and contractor availability 
From an Asset Management perspective, additional sensitivity arises from:
• Property maintenance and lifecycle costs, which can increase significantly due to inflation in construction and compliance requirements.
• Land acquisition and disposal values, which fluctuate with market conditions and economic uncertainty.
• Sustainability and compliance investments, where costs for energy efficient upgrades and carbon reduction measures may rise due to
regulatory changes and technology pricing.
Page 184

Page 185

On a more Council-wide basis, the Council’s cost of borrowing is susceptible to fluctuations in the bank interest rate due to the level of the
Council’s short to medium term borrowing. 
New Financial Management System 
The main financial management system (FMS) used by Finance to manage the General Ledger, Accounts Payable and Accounts Receivable
functions is Agresso. During 2023/24 the current service provider announced they would cease support for the system in December 2025. As a
business-critical system, it would not be practical for Finance to use the system unsupported longer term for reasons of compliance and cyber-
security protection. 
Consequently, a steering group and project team were set up to oversee the introduction of a new cloud-based FMS, with the procurement of the
new system completed in 2025/26. In 2026/27, we will commence the implementation phase with a proposed go-live date at the end of March
2027. 
Manage Corporate Debt 
Wider economic factors, particularly the cost-of-living crisis, have impacted the collection of rent, Council Tax and sundry debt. The Council is
finding it more difficult to collect all the money it is owed resulting in increased levels of debt across a range of debt types. In 2026/27, we will:
• continue to review ways of decreasing corporate debt through continued improvements to debt collection processes in relation to sundry,
non-domestic rates, Council Tax and rent
• continue to review ways to improve rent collection rates in conjunction with Housing and W4U. 
Automate Processes and Information Provision 
Staff across the Council are employed in manual processes and information provision, such as processing invoices and updating transactional
spreadsheets. Many such processes could be automated, providing benefits such as faster service delivery, improved quality and greater
flexibility, as well as enabling staff to refocus on more complex tasks rather than repetitive tasks. In 2026/27, we will continue to pursue
automation opportunities across the Council to improve efficiency. 
Page 185

Page 186

Income from Capital Receipts 
Continuing to secure income for the Council is a key priority and the Corporate Asset Management Framework supports this through the delivery
of capital receipts from the disposal of key strategic sites. The Framework will highlight non-performing property assets, inform the process for
considering future disposals, and generate additional income through the disposal of redundant assets. In 2026/27, we will monitor progress
against the Framework and the disposal of key strategic sites and provide an annual update on progress. We are in the process of phasing out
the reliance placed on capital receipts as part of the annual budget setting process. 
Income from Non-Operational Portfolio
In addition to generating capital receipts through disposals, the Council’s non-operational property portfolio continues to provide an important
source of recurring income. Asset Management actively manages these assets (such as leased commercial properties, industrial units, and land
holdings) to maximise rental income and ensure strong occupancy levels. This involves regular lease reviews, rent negotiations, and proactive
marketing of vacant units, alongside maintaining compliance with statutory obligations and delivering value for money. By optimising the
performance of the non-operational portfolio, the Council secures a sustainable revenue stream that supports service delivery and reduces
reliance on one-off capital receipts. Looking ahead to 2026/27, Asset Management will continue to monitor market conditions, explore
opportunities for portfolio rationalisation, and identify potential for income growth through strategic investment and improved asset utilisation.
Review Non-Domestic Rates of Operational Portfolio
Asset Management has continued to review and monitor Non-Domestic Rates (NDR) liabilities across the Council’s operational property portfolio
to ensure accuracy and value for money. This work involves validating rateable values, challenging discrepancies, and identifying opportunities
for reliefs or exemptions where applicable. The review process also supports budget forecasting and financial planning, as NDR represents a
significant cost for operational assets such as schools, offices, and depots. By maintaining up-to-date property data and engaging with the
Assessor’s Office, Asset Management ensures compliance while actively seeking to minimise unnecessary expenditure. Looking ahead, the
team will continue to explore efficiency measures, including rationalisation of underutilised space and leveraging changes in property use to
reduce rate liabilities, contributing to the Council’s wider financial sustainability objectives.
Artizan Redevelopment 
The Levelling Up Fund is a UK government initiative for regenerating town centres and high streets, upgrading local transport, and investing in
cultural and heritage assets. Following a successful bid to the Fund, work is underway to progress the redevelopment of Artizan in Dumbarton
Page 186

Page 187

town centre. Planning permission has been approved and a contractor appointed. In 2026/27, we will complete the redevelopment in line with
the agreed plan and report progress to the Levelling Up Project Board. 
Faifley Community Campus Development
In September 2023, the Council approved plans to create a new education and community campus on the site of the current St Joseph’s Primary
School. This significant capital investment project brings together a range of education and community facilities within the Faifley Schools
Community Campus. Following planning approval and the start of construction in February 2024, Phase1 was completed in 2025/26. This has
delivered modern, purpose-built school buildings for St Joseph’s and Edinbarnet Primary Schools, integrated early learning and childcare
facilities, and shared community spaces designed to support local engagement and wellbeing. The campus includes state-of-the-art classrooms,
digital learning infrastructure, sports facilities, and landscaped outdoor areas, all built to high sustainability standards with energy-efficient
systems and low-carbon materials. Governance and oversight have continued through the dedicated Learning Estate Project Board, with regular
updates provided to the Education Committee and Council via budgetary reports. The completion of Phase 1 represents a major milestone in
creating a vibrant, inclusive hub for education and community life in Faifley. Work is now progressing on the second and final phase of the
project, due for completion in 2026/27. This will focus on demolishing the old buildings and creating new car parking and external landscaped
spaces, including an all-weather sports pitch and multi-use games area.
Building Upgrades
The 2026/27 programme for delivering corporate asset building upgrades will focus on renovation, remodelling, and refreshing key corporate
buildings in line with the objectives of the Corporate Asset Management Plan. This includes improving building functionality, compliance with
statutory standards, and enhancing energy efficiency to support the Council’s net-zero ambitions. Works will target priority assets identified
through condition surveys and lifecycle assessments, ensuring investment is directed where it delivers the greatest operational and financial
benefit. Upgrades will incorporate modernised office layouts to support hybrid working, improved accessibility, and sustainability measures such
as LED lighting, insulation improvements, and low-carbon heating systems. In 2026/27, we will progress the building upgrades programme in
accordance with the agreed plan and timeframe, while maintaining robust governance, cost control, and stakeholder engagement to minimise
disruption and deliver long-term value.
Depot Refurbishment
The Council’s depot estate has been identified as no longer fit for purpose, impacting operational efficiency and compliance. Following a
comprehensive review and feasibility assessment, it was agreed that refurbishment of the existing estate offered the most cost-effective solution
compared to a full new-build programme. In 2026/27, the Depots Project Board will continue to lead the delivery of the refurbishment
Page 187

Page 188

programme, building on the progress achieved in 2025/26. This phase will focus on modernising facilities to meet health and safety standards,
improving welfare areas for staff, upgrading fleet maintenance workshops, and incorporating sustainability measures such as energy-efficient
lighting, improved insulation, and low-carbon heating systems. The programme will also address site security, digital connectivity, and layout
optimisation to support operational needs and future service delivery models. Robust governance and stakeholder engagement will remain
central to ensure works are delivered on time, within budget, and with minimal disruption to frontline services.
Asset Related Council Savings
In line with the Council’s agreed savings options for 2026/27, a number of initiatives involve changes to the Council’s asset base that will require
dedicated support from the Asset Management team. These initiatives include rationalisation of underutilised properties, space optimisation
within corporate buildings, and potential disposal or repurposing of non-essential assets to reduce operating costs and generate income.
Throughout the year, Asset Management will work in close partnership with relevant services to develop detailed implementation plans, ensuring
that changes are delivered in a way that supports service continuity and compliance with statutory obligations. The team will also provide
technical advice, property data analysis, and project management expertise to enable informed decision-making and timely delivery of agreed
savings. By embedding sustainability and efficiency principles into these initiatives, Asset Management will help the Council achieve its financial
targets while maintaining a fit-for-purpose estate that supports operational needs.
Global Internal Audit Standards & CIPFA Code of Practice for the Governance of Internal Audit in UK Local Government 
Global Internal Audit Standards guide the worldwide professional practice of internal auditing and serve as a basis for evaluating and elevating
the quality of the internal audit function. New standards for 2025 provide an updated framework to support internal auditors in effectively
assessing risks, ensuring transparency, and aligning audit practices with global best practices. In addition, CIPFA has introduced a new Code of
Practice to support authorities in establishing and maintaining their internal audit arrangements in line with the statutory regulations. The Code
supports the practice of internal audit under the Global Internal Audit Standards in the UK public sector. 
We conducted a gap analysis of our internal audit practice against the new Global Internal Audit Standards and CIPFA’s new Code of Practice in
2025/26 and identified and implemented actions to ensure compliance. In 2026/27, we will continue to embed the new standards and Code of
Practice within the internal audit’s team’s methodologies and processes. 
Page 188

Page 189

Shared service internal audit 
Discussions with Inverclyde Council and East Dunbartonshire Council over the future shared management delivery model for Internal Audit and
Fraud were progressed in late 2025 and this will be implemented from 2026/27. 
Continuous Improvement 
Continuous improvement is central to all that we do. The actions set out in this section, as well as those at an operational level not included in
this Delivery Plan, demonstrate our commitment to continuous improvement and take account of the wider Best Value focus on vision and
leadership; governance and accountability; effective use of resources; partnerships and collaborative working; working with communities;
sustainability; and fairness and equality. 
Action Plan 
The challenges identified in Section 2 and the key factors identified in Section 3 have informed Resources priorities for 2026/27. Appendix 1 sets
out the action plan to address them. It also includes: 
• performance indicators and targets that will enable progress to be monitored and reported to stakeholders
• strategic workforce actions to address workforce issues identified in the planning process
• strategic and/or service risks. 
In relation to the latter, strategic risks represent the potential for the Council to take advantage of opportunities or fail to meet stated strategic
objectives and those that require strategic leadership. Service risks relate to service delivery and represent the potential for impact on individual
services, or the experience of those who work within the services, i.e. employees, partners, contractors and volunteers, or service users and
clients in receipt of the services provided. In identifying the relevant risks for 2026/27 and actions to mitigate them, the aim is to improve or
maintain the current position (i.e. the current risk score) set out in the appendix. 
Page 189

Page 190

4. Resources 
Finance 
Resources has a net revenue budget of £6.209m and a capital budget of £13.049m in 2026/27. A breakdown by service area is set out below.
We will make the best use of the resources available to deliver on key priority areas and secure external/match funding where this is possible. 
Service Area Gross Expenditure
2026/27 (£m)
Gross Income
2026/27(£m)
Net Expenditure
2026/27 (£m)
Capital Budget
2026/27(£m) (Figures subject to ongoing verification)
Audit 0.387 0.057 0.330 0.000
Finance 1.862 0.135 1.727 0.554
Rent Rebates & Allowances 32.426 30.225 2.201 0.000
Revenue & Benefits 3.159 0.443 2.716 0.000
Finance Service Centre 0.545 0.069 0.476 0.000
Cost of Collection of Rates 0.091 0.120 -0.029 0.000
Cost of Collection of Council Tax 0.074 1.162 -1.088 0.000
Office Accommodation 1.538 0.396 1.142 0.000
Central Repairs & Maintenance 1.453 0.000 1.453 0.000
Corporate Asset Maintenance 2.729 2.729 0.000 12.495
Corporate Assets 2.712 5.431 -2.719 0.000
Total 46.976 40.767 6.209 13.049 
Page 190

Page 191

Employees 
Employee Numbers 
The headcount and full-time equivalent staff in each service area (as of 31 March 2026) are as follows: 
*Figures do not reflect matrix management arrangements and resources shared with other services. 
Absence 
The 2025/26 quarterly absence figures for Resources are shown below, together with the Council average for the same periods for comparison.
The figures for Resources were lower than the Council average throughout 2025/26. 
2025/26 Absence  Quarter 1 Quarter 2 Quarter 3 Quarter 4 Annual FTE days lost
per FTE employee
Resources 4.45% 4.25% 5.68% 3.33% 11.38
Council Wide Total 6.17% 5.39% 7.2% 7.65% 14.38  
Service Area Headcount FTE
Audit & Fraud 4 3.1
Finance 35 31.6
Asset Management* 20 19.2
Business Support 75 67.5
Total 134 121.4
Page 191

Page 192

Appendix 1: Action Plan 
Please Note: PI targets for 2026/27 are indicative until 2025/26 year-end data is available. 
1. Our Communities 
Our residents are supported to increase life and learning skills 
Action Due Date Owner
Complete the Faifley Community Campus 31-Mar-2027 Michelle Lynn 
2. Our Environment 
Our neighbourhoods are sustainable and attractive 
Action Due Date Owner
Progress the building upgrades programme 31-Mar-2027 Michelle Lynn 
Page 192

Page 193

3. Our Economy 
Our area has the infrastructure for sustainable and inclusive growth where businesses can flourish 
Performance Indicator
2026/27
Owner
Target
Number of invoices paid within 30 calendar days of receipt as a percentage of all invoices paid 91% Ryan Chalmers 
Action Due Date Owner
Complete the Artizan redevelopment 31-Mar-2027 Michelle Lynn 
Our partnerships support economic development to deliver increased prosperity for our area 
Performance Indicator
2026/27
Owner
Target
Time for processing applications for new Housing Benefits claims from application receipt date to the day the
claim is decided 25 Ryan Chalmers
Time for processing applications for notifications of changes of circumstances for Housing Benefits from the
application receipt date to the day the claim is decided 5 Ryan Chalmers 
Page 193

Page 194

4. Our Council 
Our workforce is resilient and skilled where digital technology supports service delivery for our residents 
Action Due Date Owner
Develop and implement wellbeing, employee engagement, equality and learning and development plans to
enable capabilities, improve resilience and promotion of a diverse workforce 31-Mar-2027 Laurence Slavin
Develop and implement employee life cycle plans in line with the People First Strategy to attract and retain the
workforce 31-Mar-2027 Laurence Slavin
Implement service review process including role design, use of new technology and new ways of working to
add resilience, address gaps, and establish opportunities for efficiencies 31-Mar-2027 Laurence Slavin
Develop and implement learning and development plans and development opportunities to improve
capabilities and resilience within the workforce. 31-Mar-2027 Laurence Slavin 
Our Council is adaptable and focused on delivering best value for our residents 
Performance Indicator
2026/27
Owner
Target
Percentage of council buildings in which all public areas are suitable for and accessible to disabled people 97% Michelle Lynn
Value of outstanding sundry debt as a percentage of total that is more than 90 days old from date of invoice 70% Ryan Chalmers
Rent collected as a % of total rent due 99.4% Ryan Chalmers
Percentage of capital receipts achieved as forecast 90% Michelle Lynn
Page 194

Page 195

Performance Indicator
2026/27
Owner
Target
Percentage of income from non-operational portfolio achieved as forecast 85% Michelle Lynn
Cost of collecting council tax per dwelling £2.00 Ryan Chalmers
Percentage of income due from council tax received by the end of the year 93.9% Ryan Chalmers
Proportion of operational buildings that are suitable for their current use 93% Michelle Lynn
Proportion of internal floor area of operational buildings in satisfactory condition 91% Michelle Lynn
Current tenants' arrears as a percentage of total rent due 9% Ryan Chalmers
Gross rent arrears (all tenants) as at 31 March each year as a percentage of rent due for the reporting year 9.3% Ryan Chalmers
Income generated as a % of total revenue budget 11% Carol Alderson 
Action Due Date Owner
Commence the implementation of the new Financial Management System 31-Mar-2027 Carol Alderson;
Arun Menon
Review ways of decreasing corporate debt through continued improvements to debt collection processes in
relation to sundry, non-domestic rates, Council Tax and rent 31-Mar-2027 Ryan Chalmers
Review ways to improve rent collection rates in conjunction with Housing and W4U 31-Mar-2027 Ryan Chalmers
Maximise automation opportunities across the Council 31-Mar-2027 Arun Menon
Progress the disposal of key strategic sites 31-Mar-2027 Michelle Lynn
Maximise income from non-operational portfolio 31-Mar-2027 Michelle Lynn
Page 195

Page 196

Action Due Date Owner
Review non-domestic rates of operational portfolio 31-Mar-2027 Michelle Lynn
Progress the depot refurbishment programme 31-Mar-2027 Michelle Lynn
Develop and implement plans and support services to achieve the asset related savings agreed by Council 31-Mar-2027 Michelle Lynn
Progress the implementation of the Global Internal Audit Standards and CIPFA’s Code of Practice within the
internal audit team’s methodologies and processes 31-Mar-2027
New Shared
Internal Audit
Manager
Progress a shared service internal audit service 30-Jun-2026 Laurence Slavin 
Risk Description Current
Assessment
Target
Assessment Owner
Debt is not recovered
efficiently or effectively,
with inherent risk of
financial loss
The processes deployed in collection of monies owed to the
Council are inefficient and ineffective resulting in money not
collected on time or having to be written off. 
Ryan Chalmers
Increase in the level of
rent arrears due to the
level of Welfare Reform
changes and general
state of economy
The Council sees an increase in its level of rent arrears due to
lower disposable income and national changes to the national
benefits regime and the ongoing economic position 
Ryan Chalmers
Maintaining Council
Assets that are fit for
purpose
The risk that the Council's assets and facilities are not fully fit
for purpose with consequent adverse impact on our ability to
deliver efficient and effective services. Assets included in this
assessment are the Council’s property portfolio.  
Michelle Lynn 
Page 196

Page 197

Our residents are engaged and empowered 
Performance Indicator
2026/27
Owner
Target
Percentage of council resources directed by communities 1% Carol Alderson;
Colin Smith 
Strong financial governance and sustainable budget management (Service Objective) 
Performance Indicator
2026/27
Owner
Target
Amount of free reserves as a percentage of the prudential reserve target - HRA 100% Carol Alderson
Amount of free reserves as a percentage of the prudential reserve target - General services 100% Carol Alderson
Percentage variance to budget projected (General Services budget) 0% Carol Alderson
Percentage of Audit Plan completed 85% New Shared
Internal Audit
Manager 
Page 197

Page 198

Risk Description Current
Assessment
Target
Assessment Owner
Failure to provide a
reasonable level of
assurance on the
Council's governance,
risk management and
internal control
procedures 
Internal Audit is unable to provide a reasonable level
assurance on the Council's governance, risk management and
internal control arrangements. 
New Shared
Internal Audit
Manager 
Failure to meet statutory
deadlines for external
returns (including
HMRC) and financial
statements
Finance Services failing to meet statutory deadlines resulting
in lost revenue or penalty costs  Carol Alderson
Financial projections are
significantly incorrect
Financial projections for both capital and revenue are
significantly incorrect resulting in insufficient reserves being
held. 
Laurence Slavin
Significant financial
funding reductions /
limitations from Scottish
Government
It is expected the Council will continue to be faced with
significant real term funding reductions from the national
settlement. This is based on local government settlements in
recent years (with the exception of 2025/2026). This coincides
with a period where costs and demographic pressures are
continuing to rise in relation to social care, significant
inflationary increases and pay award pressures linked to
inflation.  
Laurence Slavin 
Page 198

Page 199

Official
WEST DUNBARTONSHIRE COUNCIL 
Report by Chief Officer – Citizen, Culture & Facilities 
Corporate Services Committee: 27 May 2026
___________________________________________________________________ 
Subject: West Dunbartonshire Leisure Trust Business Plan 2026/27    
1. Purpose 
1.1 The purpose of this report is to update members on the West Dunbartonshire 
Leisure Trust Business Plan for 2026/27. 
2. Recommendations 
2.1 It is recommended the Committee: 
• approves the report and the 2026/27 West Dunbartonshire Leisure Trust
Business Plan;
• formally agree the WDLT management fee as set out in this report, the
sum having already been included in the Council’s 2026/27 revenue
budget. 
3. Background 
3.1 West Dunbartonshire Leisure Trust (the Trust) is a company limited by
guarantee with charitable status. In addition to being regulated by the
Companies Act (2006), the company is also subject to the charities regulator
in Scotland, OSCR (Office of the Scottish Charity Regulator). 
3.2 West Dunbartonshire Leisure Trust was incorporated as a company in
December 2011 and started trading on 5th April 2012. 
3.3  There are nine members of the company who serve as trustees comprising of
three (3) West Dunbartonshire Councillors (Partner Trustees), an Employee
Representative Trustee and five (5) Independent Trustees. The board of
Trustees (who are also directors of West Dunbartonshire Leisure Trust for the
purposes of company law) has control of the company subject to providing
and operating the services in accordance with the Legal Agreement reached
with West Dunbartonshire Council and provides strategic direction to the
General Manager and his management team. 
3.4  West Dunbartonshire Leisure Trust is responsible for the strategic and
operational management of West Dunbartonshire Council’s Sport and Leisure
Facilities, Community Facilities, Sports Development, Active Schools, Outdoor
Recreation Facilities and for event delivery on behalf of the Council. 
3.5     In order to ensure the Council meets its obligations to provide adequate
provision of facilities for the residents of the area for recreational, sporting,          
ITEM 12  
Page 199

Page 200

Official
cultural and social activities in terms of Section 14 of the Local Government
and Planning (Scotland) Act 1982, there is a Services Agreement in place
between the Council and the Leisure Trust. The Trust is paid a management
fee for delivery of the services through an annual funding commitment. 
3.6  The Services Agreement states that the Leisure Trust should bring a draft
Business Plan forward that illustrates the resources which WDLT intends to
use to deliver its services. It should also include information on the expected
expenditure required to provide those services, and the amount of funding
required from the Council in the form of the management fee. This report and
the accompanying Business Plan (Appendix 1) fulfil this requirement. 
3.7  This report is presented to Committee on behalf of WDLT by the Chief Officer
for Citizen, Culture, and Facilities (CCF) who is the senior officer responsible
for monitoring WDLT activity on behalf of the Council. 
3.8  The final 2025/26 management fee was £4,645,492. 
4. Main Issues 
4.1 At the Council budget setting meeting on 4 March, 2026, it was agreed the
management fee provided by the Council to the Leisure Trust for the financial
year 2026/27 would be £5,048,830 incorporating estimated costs for the 26/27
pay award, increases to Strathclyde Pension employer’s contribution rate and
adjusting for a 5% saving.   
4.2 A number of budget savings have been implemented within the accounts 
to achieve the current anticipated budget expenditure; including from the
removal of a vacant post, along with additional income assumptions based on
service charge increases, projected growth in health and fitness memberships
and continued expansion of the Learn to Swim programme.. 
4.4  
Projected Trust costs 2026/27 £
Expenditure Costs 10,343,958
Total Projected Costs 10,343,958  
Projected Trust income 
Draft Management Fee 5,048,830
Income (Customer Receipts) 5,055,222
Income (Grant Funding & Misc)    239,906
Total Projected Income 10,343,958 
4.5 The Leisure Trust proposes to deliver the following in the coming year as per
the Business Plan at Appendix 1: 
4.6 Sport & Leisure
Page 200

Page 201

Official
The strategic and operational management of the Council’s three wet and dry
leisure centres, Vale of Leven Swimming Pool; the Meadow Centre and
Clydebank Leisure Centre.  
4.7 Community Services
The strategic and operational management of the Council’s Community
Facilities (currently 5); Theatre; outdoor Grass Pitches (13); Synthetic Pitches
(3); an outdoor Bowling Green and the new Lachie Stewart Memorial Athletics
Track in Levengrove Park, Dumbarton. In the coming year this will be further
augmented with two new floodlight 4G synthetic pitches at Argyll Park,
Alexandria and Mountblow, Clydebank, 
4.8 Sports Development 
Through the Sports Development team, continuing to widen opportunities for
all residents to participate in sport. This is achieved via the provision of
community and school sports programmes, club and coach development
initiatives and the delivery of various mass participation sports events across
the area. With the opening of the new Athletic Track at Posties Park the Trust
will work with athletic clubs to generate usage and programme opportunities
for residents to participate in athletics. 
4.9 Active Schools 
Through Active Schools, providing more and higher quality opportunities for
children and young people to take part in sport and physical activity before,
during lunchtime and after school. 
Following the introduction of a new delivery model, performance is growing
and Key Performance Indicators have been developed to monitor this going
forward and reported on a quarterly basis to the Trust’s Board of Directors
and the Council’s Partnership Officer. 
4.10 Major Outdoor Events
The Trust will continue to deliver the Scottish Pipe Band Championships and
West Dunbartonshire Firework Display on behalf of the Council. In addition to
delivering outdoor events for the Council, the Trust also manages and delivers
the Run Loch Lomond 10k & 5k Road Races.  
4.11  Key Performance Indicators 
To enable the Council to monitor Trust service delivery during the year a
number of Key Performance Indicators are set and reported on. The agreed
suite for 2026/27 is included in the Business Plan. 
5. People Implications 
5.1 There are no direct people implications for the Council arising from this report 
6. Financial and Procurement Implications 
Page 201

Page 202

Official
6.1  As outlined in this report and the Business Plan, the Trust’s proposed service
delivery would be supported by a management fee from the Council to the
Leisure Trust of £5,048,830 in 2026/27. 
6.2 There are no procurement implications from this report 
7. Risk Analysis 
7.1 There is a risk that income may not materialise or that costs are greater than
estimated. The Council’s Partnership Officer meets with the Trust
Management monthly to discuss and monitor progress, highlight issues and
consider remedial actions. The Trust has reserves available, currently sitting
at the reserve target, to mitigate against any unforeseen cost pressures. 
8. Equalities Impact Assessment (EIA) 
8.1 An EIA was undertaken on the 2026/27 Business Plan. This identified the 
Plan would have a positive impact and benefits to the local area. The 
Business Plan has a stated commitment to equality and inclusion. 
Participation is lower for some groups, women, disabled people and BAME 
People, so explicit note of the centrality of equalities can help inform planning 
and practice. WDLT will continue to prioritise this in the coming year and 
beyond. 
9. Consultation 
9.1  Consultation on this report has taken place with WDLT management, 
Finance, Legal and Assets.  
10. Strategic Assessment 
10.1 This report supports the following Strategic Plan objectives: 
• Our Communities ‘Resilient and Thriving’ 
Amanda Graham
Chief Officer – Citizen, Culture & Facilities
29 April 2026 
________________________________________________________________ 
Person to Contact: Amanda Graham, Chief Officer - Citizen, Culture &
Facilities
Email: amanda.graham@west-dunbarton.gov.uk 
Appendices: Appendix 1: WDLT Business Plan 2026/27 
Appendix 2: EIA for the WDLT Business Plan 2026/27 
Background Papers: None 
Page 202

Page 203

Official 
Wards Affected:  All 
Page 203

Page 204

Official 
BUSINESS
PLAN                         
2026-2027 
“Inspiring Active                                        
&
Healthier
Communities
ITEM 12 - APPENDIX 1
Page 204

Page 205

Official 
Contents Page(s)
Message from the General Manager 3
Introduction 4
Trust Activity 4 
Staffing 5
Financial Budget 2026/27 6
Five Year Strategic Plan & Annual Delivery Plan 7
Key Performance Indicators 8 – 11
Accessibility Statement 12 
Page 205

Page 206

Official
Message from the General Manager 
I am pleased to present West Dunbartonshire Leisure Trust’s 2026/27 Business Plan.
Guided by our mission of Inspiring Active and Healthier Communities, this plan
outlines how we will continue to support local people to live healthier, happier, and more
active lives. 
Our work in the year ahead is shaped by our three strategic objectives: Health &
Wellbeing Opportunities for All, A Thriving Not-For-Profit Charity, and Financial
Sustainability. These objectives ensure we stay focused on delivering inclusive services,
strengthening our organisational resilience, and operating responsibly as a charitable
trust dedicated to community benefit. 
A key priority for 2026/27 will be our partnership work in assisting develop and
implementing a Physical Activity for Health Strategy for West Dunbartonshire. Through
close collaboration with West Dunbartonshire Council, health and social care partners,
and community organisations, we aim to create accessible pathways into physical activity
for people of all ages and abilities. This shared approach will help reduce participation
barriers, tackle local health inequalities, and extend the positive impact of physical activity
across our communities; while reinforcing the social value we deliver as an organisation. 
This business plan outlines clear targets, and the resources we will dedicate to achieving
them. But plans alone don’t deliver results, people do. I am confident that with our
collective focus and commitment, we will not only meet the ambitions set out here but
exceed them. 
I look forward to delivering another successful chapter in West Dunbartonshire Leisure
Trust’s development and building on our progress together in the year ahead. 
John Anderson
General Manager 
Page 206

Page 207

Official
Introduction 
WDLT is a company limited by guarantee with charitable status and was incorporated in
December 2011 and started trading in April 2012. WDLT is responsible for the strategic
and operational management of the council’s Sport and Leisure Facilities; Community
Facilities; Outdoor Pitches & Bowling Greens (transferred to WDLT 3 April 2017); Sports
Development; Active Schools; and the delivery of the Council’s major Outdoor Events. 
This Business Plan outlines the activity planned in the coming year and the financial
budget required to deliver these services in 2026/27. This includes the level of
Management Fee from WDC. 
Trust Activity 
WDLT proposes to deliver the following on behalf of the Council in 2026/27: 
Sport & Leisure
The strategic and operational management of the council’s three wet and dry leisure
centres, Vale of Leven Swimming Pool; the Meadow Centre; and Clydebank Leisure
Centre. 
Community Services
The strategic and operational management of the council’s Community Facilities (currently
5); Theatre; outdoor Grass Pitches (13); Synthetic Pitches (3); an outdoor Bowling Green;
and the new Lachie Stewart Memorial Athletics Track in Levengrove Park, Dumbarton. 
We will work with the Council to ensure the successful commissioning and operation of
two new floodlight 4G synthetic pitches at Argyll Park, Alexandria and Mountblow,
Clydebank (replacing two existing grass pitches at the same sites). 
Sports Development
Our Sports Development team is focused on widening opportunities for all residents to
participate in sport. This is achieved via the provision of community and school sports
programmes, club and coach development initiatives and the delivery of various mass
participation sports events across the area. 
Active Schools
Our Active Schools team aim to provide more and higher quality opportunities for children
and young people to take part in sport and physical activity before, during lunchtime and
after school. 
Major Outdoor Events
We will continue to deliver an annual programme of outdoor events for the Council. This
Events Calendar includes the Scottish Pipe Band Championships, and a Firework Display. 
In addition to delivering outdoor events for the Council, we also manage and deliver the
Run Loch Lomond 10k & 5k Road Races. 
Page 207

Page 208

Official 
Staffing 
To deliver the vast array of services/programmes (136.59 FTE) employees (excluding
casual workers/coaches/instructors) are required to be utilised by WDLT. The tables
below provide a breakdown of the FTE for each service area: 
Business Support (12.06 FTE)  Leisure Services (80.99 FTE)
Designation FTE Designation FTE
General Manager 1 Operations & Finance Officer 1
Business & Customer Services Coordinator 1 Leisure Facility Officer 1
Development Officer 0.86 Fitness Officer 2
Lead Live Active Advisor 1 Technical Officer 2
Systems & Administration Officer 1 Duty Officer 8.19
Live Active Advisor 2 Leisure Attendant 51.34
Training Officer 0.8 Fitness Attendant 8.39
Data & Digital Media Officer 1 Receptionist 12.17
Admin Support Assistants 3.4 General Operative 8.55   
Sport & Physical Activity (25.33 FTE)  Community Services (26.58 FTE)
Designation FTE Designation FTE
AS, Sport & Physical Activity Manager 1  Community Facilities Officer 1
Active Schools Coordinator 6  Duty Officer 2
Sport & Physical Activity Coordinator Aquatics 1  Facility Assistant 20.86
Sport & Physical Activity Coordinator 3 General Operative 2.72
Assistant Swimming Dev Officer 4  
Lead Coach 3.5  
Assistant Coach 6.41   
Page 208

Page 209

Official
Financial Budget 2026/27 
To deliver the programme outlined above, with the resources listed, WDLT forecasts the
following financial requirements which were approved at the Council’s Budget Meeting
on 4 March 2026. 
Management Fee 
The following key adjustments have been applied to the calculation of the 2026/2027
Management Fee: 
Key Adjustments 
Base Subsidy (Management Fee 2025/26) £4,645,492 
Employee Costs Uplift £234,000 
Increased Employer Pension Contribution (from 6.5% to 17.5%) £464,750 
WDC Saving (5%)                                                                                      (£253,412) 
Loan Interest Charges for New 4G Pitches (£42,000) 
Management Fee 2026/27 £5,048,830 
This would represent an increase in the management fee from the Council of £403,338 
(based on an alteration to the 2025/26 Management Fee due to no works caried out on
the new synthetic pitches in 2025/26) approximately 8.7% from 2025/26. 
Income 
2025/26
Budget (£)
2026/27
Budget (£)
Change in
Budget (£)
Management Fee 4,597,492 5,048,830 451,338
Customer Receipts 4,455,902 5,055,222 599,320
Grant Funding 239,906 239,906 -
Income Total 9,293,300 10,343,958 1,050,658 
Expenditure 
2025/26
Budget (£)
2026/27
Budget (£)
Change in
Budget (£)
Expenditure Totals 9,293,300 10,343,958 1,050,658 
Budget savings have been applied across the accounts wherever possible to support the
anticipated expenditure for the year. This includes the removal of the Assistant Sports
Development Officer post, along with additional income assumptions based on service
charge increases, projected growth in health and fitness memberships, and continued
expansion of the Learn to Swim programme. 
Page 209

Page 210

Official
Five Year Strategic & Annual Delivery Plan 
This Strategic Plan sets out our Strategic Objectives & Priorities for the next five years
(2023 – 2028). It has been developed to provide a focus and strategic approach to ensure
WDLT continues to maintain and develop services aiming to meet our Company Objects
and compliment National Strategies and West Dunbartonshire’s Strategic Plan. 
The following Infographic demonstrates how our Strategic Plan Objectives align with our
Company Values and Missions Statement. We are an organisation that aspires to the
highest standards in everything we do, and we adopt six core values, which will underpin
how we deliver on our three strategic objectives and priorities to achieve our mission. 
The following table highlights our Strategic Priorities against our Objectives: 
Objectives: Health & Wellbeing
Opportunities for All
A Thriving Not For
Profit Charity
Financial
Sustainability 
Priorities:
Facilities
Programmes
Partnerships
People
Profile
Technology
Income
Financial Resources
Sound Governance 
Our full Strategic Plan can be accessed here 
WDLT have also developed a Delivery Plan for 2025/26 identifying the key actions we will
undertake to assist achieve the Strategic Priorities within our Strategic Plan. 
Page 210

Page 211

Official
Key Performance Indicators 
Following a review of the previous Key Performance Indicators (KPIs) with the Council’s
WDLT Partnership Officer, the following KPIs for 2026/27 have been agreed: 
Strategic Objective – Health & Wellbeing Opportunities for All 
Priority – Facilities 
Performance Indicator 2023/24
Actual
2024/25
Actual
2025/26
Actual
2026/27
Target
CC1 Wet Activities 351,471 404,835 428,123 450,000
CC2 Dry Activities 496,061 582,223 651,518 700,000
Overall Usage 1,273,815 1,383,194 1,437,068 1,500,000
Total No. H&F Members 6,696 7,801 8,564 9,150 
Priority – Programmes 
Performance Indicator 2023/24
Actual
2024/25
Actual
2025/26
Actual
2026/27
Target
Physical Inactive Individuals
Referred to the Live Active
Scheme
New
Indicator
New
Indicator 1,019 1,050*
No. of Learn to Swim Visits 115,208 122,751 148,958 156,000
No. of Community Sport
Programme Visits 27,661 31,863 32,757 33,000
No. of Holiday Activity Visits 4,718 4,754 4,904 4,950 
Page 211

Page 212

Official
Priority – Partnerships   
Performance Indicator 2023/24
Actual
2024/25
Actual
2025/26
Actual
2026/27
Target
% of Live Active Referrals
Active after 3 Months
New
Indicator
New
Indicator 679 630*
% of Live Active Referrals
Active after 6 Months
New
Indicator
New
Indicator 564 475*
% of Live Active Referrals
Active after 12 Months
New
Indicator
New
Indicator 455 400*
Targeted Active Schools
Participants - SIMD 1 & 2 1,236 1,247 2,798 2,900
Targeted Active Schools
Participants – ASN  1,950 2,928 3,227 3,500
% of Primary School Roll
participating in Active
Schools Sessions
34% 40% 45% 46%
% of Secondary School Roll
participating in Active
Schools Sessions 
15% 17% 24% 25%
% of Total School Roll
participating in Active
Schools Sessions 
24.5% 34.5% 34.5% 36%
Free access to Holiday
Activities 14,552 20,713 17,694 18,500 
* Targets set by Graeter Glasgow Health Board 
Page 212

Page 213

Official
Strategic Objective – A Thriving Not For Profit Charity 
Priority – People 
Performance Indicator 2023/24
Actual
2024/25
Actual
2025/26
Actual
2026/27
Target
Number of Workshops /
Training Sessions / Courses
delivered
584 610 701 700
No. of delivers for Active
Schools Sessions  283 246 254 260 
Technology 
Performance Indicator 2023/24
Actual
2024/25
Actual
2025/26
Actual
2026/27
Target 
MobilePro Users 36,951 49,315 51,273 52,000
% of on-line customer
transactions 18.5% 42.14% 43% 45% 
Priority – Profile 
Performance Indicator 2023/24
Actual
2024/25
Actual
2025/26
Actual
2026/27
Target 
MobilePro Club Hits 1,048,117 1,382,273 1,104,023 1,125,000
Social media posts that
promotes opportunities;
celebrates success and
demonstrates impact the
Trust delivers
864 1,732 1,263 1,300 
Page 213

Page 214

Official
Strategic Objective – Financial Sustainability 
Priority – Income 
Performance Indicator 2023/24
Actual
2024/25
Actual
2025/26
Actual
2026/27
Target 
Income £4,103,964 £4,744,787 £5,024,208** £5,055,222
Income Generated from
Gym Use/Memberships £1,526,982 £1,864,173 £2,107,250 £2,300,000
Income generated from
Swimming Activities £813,478 £902,465 £1,072,212 £1,200,000 
Priority – Financial Resources 
Performance Indicator 2023/24
Actual
2024/25
Actual
2025/26
Actual
2026/27
Target 
% Income (Mgt Fee) 51.8% 45.6% 47.8%** 50% 
% Income (Receipts) 48.2% 54.4% 52.2%** 50% 
Expenditure £9,132,129 £9,145,825 £9,222,923** £10,343,958 
Cost per Visit (Mgt Fee) £3.47 £2.88 £3.28** £3.37 
Priority – Sound Governance 
Performance Indicator 2023/24
Actual
2024/25
Actual
2025/26
Actual
2026/27
Target
Completion of all agreed
recommendations
following Internal Audits
95% 95% 100%  100%
Achievement of Unqualified
Accounts 
Unqualified
Accounts 
Unqualified
Accounts 
Unqualified
Accounts 
Unqualified
Accounts 
** Based on projected outturns
Page 214

Page 215

Official
This document is also available in other languages, large print and
audio format on request.
Arabic 
Hindi
 01389 737527
 West Dunbartonshire Council, 16 Church Street, Dumbarton, G82
3PU
 communications@west-dunbarton.gov.uk 
Page 215

Page 216

Official 
West Dunbartonshire Leisure Trust
Alexandria Community Centre
Main Street
Alexandria
G83 0NU
Tel: 01389 757806
Fax: 01389 751557
Email: leisureservicesadmin@west-dunbarton.gov.uk
Website: www.wdleisure.net 
West Dunbartonshire Leisure is a recognised Scottish Charity: SC 042999;
VAT Registered: GB 129 7502; and Company Registered: SC 413707
delivering services on behalf of West Dunbartonshire Council
Page 216

Page 217

Assessment No 1499
Strategic Team CCF
Lead Officer John Anderson
Who else has been
involved in developing
this EIA
Jane Wight, Business & Customer Services Coordinator 
Title WDLT Business Plan 2026/27
Description: (Provide a
brief overview of the
aims and objectives of
this policy)
To clearly set out the financial and staffing resources required
to deliver the key actions and performance indicators
throughout 2026/2027 
Who have you
engaged and consulted
with as part of your
Strategic Leadership Group. Potentially Convenors and
Committee.
Who will be affected by
this proposal?
WDC and WDLT staff, WDLT Service users and potential
service users. 
Does the proposals involve the procurement of any goods or services? No
If yes, please confirm that you have contacted our procurement services to
discuss your requirements and viewed the guidance
No 
Relevance screening: If the proposal/policy is relevant to any of the six areas then an
Equality Impact Assessment must be carried out.
You must indicate if there is any relevance to the six areas 
Duty to eliminate discrimination (E), advance equal opportunities (A) or
foster good relations (F)
Yes
Relevance to Human Rights (HR) Human Rights Act/European Convention
on Human Rights
Yes
Relevance to Health Impacts (H) Yes
Relevance to United Nations Convention on the Rights of the Child
(UNCRC)
Yes
Relevance to Social Economic Impacts (SE) or Fairer Scotland Duty (FSD) Yes
Relevance to Scottish Consumer Duty (SCD) No 
ITEM 12 - APPENDIX 2
Page 217

Page 218

Consider any needs and policy drivers e.g. Council or national strategies and
plans /and any barriers which equality groups may have in relation to this
policy. 
List evidence you are using to support this assessment. 
Consider the impact of your policy on people and how they will be able to
access goods, services and information with no barriers and state the potential
impact. 
Specific group to
consider
What Key Drivers and
Evidence has been used to
inform this assessment. (i.e.
national statistics - Scot Govt; or
local statistics - workforce data,
Citizens Panel)
For each group, state the
potential Impact –
Positive/Negative/Neutral
Age                                                                                                  The leisure centres host a range
of suitable classes for all ages
from pre school football and
beginner swimming lessons to
60+ tai chi and aqua aerobics
classes. The centres are also
well located in each of the main
towns within West
Dunbartonshire and opened from
early morning to late in the
evening.
Positive, as well as ensuring
access for all ages for exercise
for mental and physical
wellbeing, the centres offer vital
local access 7 days per week.
The impact, specifically for older
and young people, is of huge
benefit.
Disability                                                                                           WDLT have adopted a proactive
approach in relation to
accessibility of services for
disabled people, and BSL users.
Walkthrough videos have been
produced for each of the 3 main
leisure centres with audio and
subtitles to assist customers. 
Staff training is in place to
support the accessibility of
disabled people.
Explicit recognition of the
centrality of equality helps
support accessible and inclusive
service design and provision.
Gender Reassign                                                                                      Some people who have re
assigned or are re assigning
their gender can face stigma
accessing services.
Explicit recognition of the
centrality of equality helps
support accessible and inclusive
service design and provision
Marriage & Civil
Partnership                                                                        
Tends to cross cut with sex and
sexual orientation, in terms of
services provision and
employment.
No evidence available of likely
differential impact around
marriage and civil partnership.
Pregnancy &
Maternity                                                                               
Cross cuts with sex. Explicit recognition of the
centrally of equality helps support
accessible and inclusive service
design and provision.   
Page 218

Page 219

Race                                                                                                 During lockdown evidence
suggests that BME groups have
suffered worse health outcomes,
including health outcomes. As
noted we have made health and
well being for all as a priority.
Our inclusive support should
support participation across
under-represented ethnic groups.
Religion and
Belief                                                                                 
This can cross cut with sex
especially in the area of demand
for women only services,
therefore access to for example
swimming for women only may
often meet needs around sex
and religion and belief.
Providing services in an inclusive
manner will always be of benefit.
Sex                                                                                                  In Scotland more men participate
in sport than women. More men
are members of sports clubs
than women, and women often
participate in different sports
from men. Lower participation by
women in sport begins at around
13 to 15 years old Evidence
suggest that during lockdown,
women have taken on the main
burden of home schooling,
opportunities for women to
participate in physical activity are
therefore more important than
ever.
Providing services in an inclusive
manner, will always be of benefit.
Sexual
Orientation                                                                                  
Data on sports participation in
Scotland indicates that lesbian,
gay and bisexual participants are
not significantly different from
heterosexuals in activity levels.
However, adults who identified
as having an ‘other’ sexual
orientation were significantly less
likely to meet activity
recommendations than the
national average. It is important
to treat these findings with
caution however, due to
anticipated under reporting of
LGB people who are not ‘out’
within surveys.
Providing services in an inclusive
manner will always be of benefit. 
This section must be completed if there are potential Human Rights impacts,
this includes but is not limited to Human Rights Act 1998 considerations 
Human Rights                                                                                         Considering participation from a
Human Rights perspective can
help ensure an inclusive
Positive; supporting everyone's
can participate supports the
exercise of peoples human    
Page 219

Page 220

approach. 
The approach  of the WDLT
supports supports Children and
Young peoples 'Provision' and
'participation' two domains of the
UNCRC
rights, including UNCRC rights.         
This section must be completed if there are potential Human Rights impacts,
this includes but is not limited to Human Rights Act 1998 considerations 
Health                                                                                               Mental and physical health are
intertwined. Some groups have
suffered increased disadvantage
during the Covid 19 lockdowns.
Explicit recognition of Equality
and Human rights as core
considerations that cross cut in
service design and delivery can
improve inclusion.     
This section must be completed if any there are any potential socio-economic
impacts including but not limited to those covered by the Fairer Scotland Duty 
Social &
Economic
Impact                                                                            
WDLT is a significant Employer in
the WD area.
WDLT is a significant provider of
services. The greatest focus on
socio-economic status in sport and
physical activity relates to health.
Health research links poorer
health and wellbeing, including
lower levels of physical activity, to
lower economic status.
There is explicit recognition of
the need to have due regard to
socioeconomic impacts of
strategic decisions This
supports the proper execution of
this duty by the Council in its
relationship with WDLT             
This section must be completed if any potential impact on children and young
people up to the age of 18 
United Nations
Convention on
the Rights of the
Child                                                
The three domains of the
UNCRC, participation, protection,
provision, and also promotion of
rights are all relevant.
Positive 
This section must be completed in reference to the Scottish Consumer Duty 
Scottish
Consumer Duty                                                                              
N/A N/A 
Consider cumulative impact of the proposal 
Cumulative and
intersectional
impacts                                                               
Where people and communities
are members of several
disadvantaged groups this can
multiply barriers and
disadvantage Members of the
WDLT have participated in
Equality Impact Assessment
Service restart and redesign
provided an excellent
opportunities to embed Equalities
and Human rights approaches for
the benefit of staff and service
users. New online training
resources have been created by   
Page 220

Page 221

training and processes. WDC and these are shared with
WDLT staff. 
Page 221

Page 222

State how the impact of the proposal/policy be monitored and reported on an ongoing
basis including how actions will be delivered to mitigate any negative impacts or
secure positive impacts. 
Summary of overall impact(s) of the proposal.
EIA 1499: The business plan has a stated commitment to equality and inclusion;
participation is lower for some groups, women, disabled people and BME people so
explicit note of the centrality of equalities can help inform planning and practice. A
range of positive impacts for equality groups are noted. The approach  of the WDLT
supports supports Children and Young peoples participation and provision of services
for them. 
Name of the senior manager who has approved this assessment
John Anderson 
Page 222

Page 223

Official
WEST DUNBARTONSHIRE COUNCIL 
Report by Chief Officer – People & Technology 
Corporate Services Committee:  27 May 2026
___________________________________________________________________ 
Subject: Council Workforce Plan 2022-2027:  Update and Annual Action
Plans 2025/26 
1. Purpose 
1.1 The purpose of this report is to provide an update on the Council’s workforce
planning activity for 2025/26.   
2. Recommendations 
2.1 The Committee is asked to:
• Note progress during 2025/26 in delivering against the Council Workforce
Plan within the People First Strategy; 
• Note the workforce profile as of 31st March 2026 and key changes; and
• Note progress within the Workforce Plans for each service. 
3. Background 
3.1 The Workforce Planning Strategy and Framework 2022 - 2027 reflects the 5-
year People First Strategy and incorporates the Council’s Strategic Planning
Framework. 
3.2 The Council Workforce Plan is subject to monitoring and evaluation to ensure
that it remains effective in delivering required outcomes and is responsive to
any changes in circumstances, which subsequently arise. This report contains
2 sections and associated appendices: 
• The progress and achievements made over the last year (Appendix 1);
• The current workforce profile and monitoring, examining any changes
(Appendix 2). 
3.3 Service’s annual action plans are scoped under the four Workforce Planning
Priorities from the Corporate Workforce Plan for each Chief Officer Area and
are submitted to the relevant Committee as part of the Delivery Planning
process. Separate delivery reports are tabled at this committee. 
3.4 Whilst separate planning processes exist in relation to West Dunbartonshire
Health & Social Care Partnership (HSCP), appropriate alignment is in place
with links to the Health Care Staffing and Workforce Planning Oversight
Group to ensure that Council employees working within HSCP are included
and benefit from all Council Wide initiatives and relevant workforce planning
requirements. 
ITEM 13
Page 223

Page 224

Official
4. Main Issues 
4.1 The attached (Appendix 1) updates on the annual action plans at Chief Officer
Service level for 2025/26 under the 4 Priorities:
Priority 1. Our People (Workforce Profile): Ensure resilience and
engagement of the workforce;
Priority 2. Recruitment & Retention: Current and predicted future
workforce gaps are addressed and core skill sets retained;
Priority 3. Structure & Roles: Service structures and delivery model/s
are stable, fit for purpose and future requirements;
Priority 4. Skills & Capabilities: Current and future skills gaps and
capabilities are addressed.
These 4 priorities are formed from the Corporate Workforce plan which
reflects the People First Strategic Plan (Appendix 3). 
4.2 Key Achievements 
4.2.1 Key achievements over 2025/26 for workforce planning within the context of
the People First Strategy have been summarised and reflect the People &
Technology Service Plan as reported to this committee. Details of key
achievements are in Section 2 - Performance & Review of the Service
Delivery Plan. 
4.3 Workforce Planning Strategy & Framework 
4.3.1 Workforce Planning continues to be challenging in a climate of budget savings
and limited resources. The demand for support has been high around the
Council’s savings options and the subsequent volume and pace of service re-
designs, an on-going need for support related to SWITCH and Organisational
Change processes for employees and managers.  This has been during a
time when Strategic HR has undertaken its own re-structure and transitioned
into new ways of working. 
4.3.2   All reviews consider the Council’s Standard operating Model (SOM) and
digital requirements with services, including Strategic HR and wider corporate
services taking part in the roll out of Office 365, SharePoint and OneDrive this
year. 
4.3.3 Previous years have seen intense volume and activity around the Voluntary
Severance/Voluntary Early Retirement (VS/VER) which presented challenges
to resource.  Considering the limited number of speculative VS/VER requests
that could be approved, a targeted approach is now being taken.  Requests
are limited to those impacted by service redesigns.  This change in approach
supported timely decision making, resourcing and will continue into 2026/27. 
4.3.4  There has been significant development in the workforce planning console,
including new data tiles and an updated interface to improve usability.  It is
Page 224

Page 225

Official
encouraging to note that usage of the console continues to increase with
training available from Strategic HR.   
4.3.5 Substantial progress has also been made in the development of generic role
profiles which will ultimately play a key part in aiding succession planning,
critical role analysis, job evaluation, skills matrix development (including digital
skills) and organisational cross skilling in line with our leadership frameworks
and recruitment to roles. 
4.4 Overview of National Picture 
4.4.1 As part of wider workforce planning, the Council continues to input into
national and local strategies. Every 2-3 years there is a commitment that a
National Workforce Planning Survey will be undertaken, led by the Society of
Personnel and Development Scotland (SPDS) and the Improvement Service
(IS).  The National Workforce Planning Survey for all 32 Local Authorities will
be repeated in the coming year, and in preparation planning has already
commenced. The findings and recommendations from the previous survey
were communicated to all Chief Officers and raised at COSLA (Convention of
Scottish Local Authorities) for wider action. 
4.4.2 The Improvement Service are currently developing a template for a National 
(Scottish) Local Authority workforce dashboard.  If approved through 
SOLACE, this will reflect the workforce data of local authorities at a national 
level, expanding upon the Local Government Benchmarking indicators for the 
workforce and the key findings of the National Workforce Planning Survey. 
This year’s survey will also inform the development of the dashboard. 
4.4.3  Additionally, a pilot has been agreed through national groups to highlight
Local Authorities as an employer of choice through promotional activities and
materials.  Given the success of this activity in England, it is anticipated that
raising the profile of Scottish Local Authorities in this manner will aid
recruitment and retention. This will support our People First Year 1 actions for
recruitment. 
4.4.4 The Glasgow City Region Skills Working Group partnered with the University
of West of Scotland to introduce a course for Environmental Health Officers
following the success of the ‘fast track’ course for Trainee Planners last year.
The goal is that this new provision will support local authorities in the Glasgow
City Region area to address recruitment shortages and availability of
qualifications in this profession. 
Page 225

Page 226

Official
4.5  Priority 1. Our People (Workforce Profile): Ensure resilience and
engagement of the workforce. 
Equalities 
4.5.1 Understanding the makeup of the workforce continues to be a priority.  A data
verification exercise was carried out in 2025/26 and posted on Trickle,
Workforce Update.  This did not result in any increased information being
received.  Alternative ways of collecting information are currently being
considered. 
4.5.2 Focus has been given to maintaining the Equally Safe at Work (ESAW)
programme Development Tier. This year has continued to focus on the
development of a sexual harassment policy information in line with the new
legislative changes on employers to prevent sexual harassment as outlined in
the policy section below. The 2 e-learning modules ‘Together for gender
equality’ and ‘Gender Based Violence’ have continued to be available and
promoted. 
Wellbeing 
4.5.3 The Wellbeing priority in 2025/26 was the renewal of contracts for the
employee benefits platform (Vivup) and the financial wellbeing platform (My
Money Matters).  The preparatory work has been completed, and the new
contracts will commence in 2026/27. Continued promotion of My Money
Matters has resulted in a 41% increase in employees with shared cost
additional voluntary contributions (AVC’s) to their pensions in the past year.
This delivers a saving to the Council and the employee through the
mechanism of a tax efficient salary sacrifice agreement.  The value of monthly
employer savings linked to AVCs has also increased by around 59% in the
past year.  In addition, the employee benefits platform, Vivup has seen usage
rise by approximately 75%, and employer savings from salary sacrifice for
home goods and electronics have increased by 28%. 
Employee Engagement 
4.5.4 Through the ‘People First’ Strategy, the Council has committed to develop
and improving employee engagement by building on existing good practice.
The Council’s main tool for employee engagement remains the digital platform
Trickle, available via the website or app which supports inclusivity as it is
accessible to the whole workforce. This enables the workforce, including front
line employees, to raise issues and access information via the app on their
phone.  Recognising the benefits of this employee engagement tool, work has
continued to focus on improving the level of engagement with Trickle across
existing and new users. The number of users is currently 1984, which is a
small decrease from1999 as reported in 2024/25.  The Strategic HR team are
working with services locally to drive the increase in users by directly linking to
Page 226

Page 227

Official
workforce planning actions where needed and encouraging Trickle
Champions to be appointed in services.  While Trickle has been in place since
2020 and offers clear benefits as a communication and engagement tool, a
full review is planned for 2026, in advance of contract renewal. This review
will assess the impact of Trickle on employee engagement, ensure continued
value for money, and consider alternative options where necessary. 
4.5.5 The Council continues to promote several initiatives to support employee
engagement including Trickle, 1-2-1 (Be the Best) conversations to support
workforce development, recognising success and value through employee
recognition awards and understanding the workforce voice through Trickle
Moodsense.  This is in addition to monthly workforce updates to inform the
workforce of key updates across ICT, HR and Health and Safety. 
4.5.6 Due to the volume of service re-design processes, employee engagement has
been concentrated around consultation processes and ensuring employees
receive the required information and supports to enable informed decisions to
be made. Services have concentrated on this at a local level through
meetings and various written information around the consultation packs with
some services making use of internet spaces to cascade and share
information for large and front-line service areas.  Examples of this are the
dedicated intranet pages set up by Facilities Management and Care at Home. 
4.5.7 Demonstrating that the Council values employees and celebrates success is a
key component of employee engagement. A range of initiatives are in place to
support this, including the relaunch of the Council’s employee Recognition
Awards.  Aligned to the Council’s core ACHIEVE values and launched in
November 2024, the first ACHIEVE Awards Ceremony was held on 1 May
2025.  A total of 36 nominations were received across all award categories,
with winners recognised for their contributions will be celebrated at the next
Awards Ceremony.  To ensure the awards remain meaningful, high-quality
and sustainable, it is proposed that the ACHIEVE Awards are held on a
biennial basis. This will allow sufficient time to promote the awards, embed
recognition within services, and align the programme more effectively with
wider workforce engagement and organisational priorities. 
Policy 
4.5.8 The Employment Rights Bill has brought multiple legislative changes in the
last quarter of 25/26 into the first quarter of 26/27 including:
• Changes to statutory sick pay entitlements; 
• Trade Union recognition, in particular notice requirements for ballot and
strike action;
• Day 1 rights to paternity, parental and bereavement leave for parents;
• Collective redundancy award limits and; 
• Sexual harassment and whistleblowing. 
Page 227

Page 228

Official 
4.5.9 Efforts and resources have been concentrated around understanding impacts,
assessment of risks and reviewing the employment-based policies and
guidance to reflect these changes. This has also involved communications to
Trade Unions, Managers and employees to ensure compliance and
awareness. 
4.5.10 Further legislative changes are scheduled throughout 2026 and efforts
continue to be focused on the review, impact assessment and implementation
of these changes to ensure preparedness.  Forthcoming changes include:
• Unfair dismissal rights after 6 months;
• Prohibition of exploitative practices regarding ‘fire & re-hire'; 
• Duty to prevent sexual harassment by a 3rd party; 
• Removal of zero hours contracts and right for workers to be given
average hours contracts after 12 weeks;
• Enhanced protection for pregnant employees and those on
maternity leave in relation to redundancy;
• Unpaid bereavement leave 
4.5.11 Whilst work was paused on the Resolution Framework due to other priorities
and resources this will be reviewed in the future with consideration given to
digital and AI supports in the development of this framework. 
4.6 Priority 2. Recruitment & Retention: Current and predicted future workforce
gaps are addressed and core skill sets retained 
4.6.1 Progress remains steady on this workstream with agreement for national
recruitment resources to be developed and piloted within 2 local authorities as
outlined at 4.4.3.to highlight the image of Scottish local authorities as an
employer of choice. 
4.6.2 As per section 4.3.5 Reflecting our Standard Operating Model (SOM)
structures and the People First strategy workstreams, a role profile template
has been developed supporting the requirements around job evaluation,
workforce and succession planning, skills development, job quality and
equalities. 
4.6.3 A comprehensive review of the Onboarding approach was undertaken and
this culminated in the development of a centralised Onboarding hub which
was published on the intranet in May 2025.  This hub offers useful guidance
and information for new employees and managers/team leaders who provide
onboarding support, all conveniently located in one place. 
4.6.4 Additional supports were also developed including a toolkit with an     
onboarding checklist for managers, an onboarding checklist for employees
and an onboarding checklist for those with senior officer responsibilities. 
Page 228

Page 229

Official
4.6.5 On a local basis the HR Adviser team have been supporting various ‘mock
interview’ experiences for High School pupils to prepare them for the world of
future work and positive destinations but also promoted the Council as an
employer  
Job Evaluation 
4.6.6 This year has seen a significant number of job evaluations being progressed
following the implementation of the new Job Evaluation Policy and Procedure
and streamlining of processes including the on-line forms. Efforts have
concentrated around ensuring evaluations are undertaken within timelines
where possible including forward scheduling and the list of roles awaiting
evaluation significantly reduced. Job evaluation has been a key activity this
year in relation to progressing the service review processes and work around
the Strategic Operating Model. The volume of roles for re-evaluation
continues to exceed previous years. 
4.6.7 Work continues to ensure all data relating to job evaluation is robust and fit for
purpose which includes the archiving of historic role profiles and job
evaluation information. Also, in relation to the Strategic Operating Model
(SOM) providing structured governance moving forward to any proposed
changes in line with the Workforce Plan as outlined in section 4.7.3. 
Career Pathways & Succession Planning 
4.6.8 Recruitment and retention remain challenging for certain roles within the
Council which follows national trends. Service areas have looked to address
these issues with re-structures incorporating succession planning and looking
to develop clear career pathways. 
4.6.9 Recruitment actions to attract diverse talent remains a priority with links to
Working 4U to provide better connections to current and potential talent pools.
This year efforts have concentrated around the promotion of Paid Work
Placements across the Council with Services being encouraged to offer time-
limited, paid work placements for individuals from priority groups who often
face compounded barriers to employment. These include Vulnerable Young
People, Long-Term Unemployed, Economically Inactive, Families
Experiencing Poverty, Individuals with Disabilities, People with Long-Term
Health Conditions, Neurodiverse Individuals, Care Experienced Individuals,
Minority Ethnic Communities, Community Justice Participants and Residents
in Areas of Multiple Deprivation as identified by the Strategic Employability
Group. 
4.6.10 The paid work placements are fully funded by the ‘No One Left Behind’ fund
with the potential to draw from the UK Shared Prosperity Fund offering
meaningful experience, enhanced confidence, and improved job readiness by
supporting service users into a paid work placement, for a period of up to 6
months. To date there are currently 5 placements in progress across
Page 229

Page 230

Official
Education, ICT, Planning & Building Standards and the Contact Centre
supporting communities into employment, the diversification of our workforce
and talent pipelines for entry level posts. 
4.7 Priority 3. Structure & Roles: Service structures and delivery model/s are
stable, fit for purpose and future requirements 
Budget Savings 
4.7.1 Priority has remained on supporting services across the Council to make the
relevant savings through service reviews and re-structures ensuring services
continue to be robust and fit for current and future demand. A number of key
services reviews have been reflected with the service workforce plan updates
in Appendix 1.  The focus for workforce planning remains to stabilise the
workforce and work priorities. With future budget gaps predicted, longer-term
workforce planning remains difficult in addition to reviewing how services can
be automated/digitalised or delivered more efficiently. 
4.7.2 Services with budget savings agreed for 2026/27 are again entering formal
consultation periods with cognisance of the new and proposed legislative
changes. Effective employee engagement remains core to this process and
the workforce console and data continue to be imperative to inform and fully
understand the implications of proposals for service delivery, the workforce
and ensure accurate notification of the potential impacts. 
SOM (Standard Operating Model) 
4.7.3 Work continues to ensure that the spans of control and ratios of employees to
managers is correct and fit for purpose, to ensure service delivery moving
forward. This includes the SOM principles and a tier-by-tier approach with
Chief Officers and Service Managers down to grade 10 being reviewed and
actions planned/commenced to ensure compliance within re-structures and a
consistent structure in place to deliver the services required in the future.
Work has also commenced on Grade 9 and governance arrangements are
ensuring role profiles are updated to reflect current responsibilities and duties. 
Fit for Future (FfF) Service reviews 
4.7.4 A FfF review of the approach to supporting employee wellbeing (with a focus
on sickness absence) commenced in 2025/26.  The Supporting Employee
Wellbeing policy states that every employee should have a Return to Work
(RTW) meeting after every absence but figures between October 2023 and
September 2025 outlined, only 92% of RTW meetings were recorded and only
52% of RTW online forms completed.  The review explored the RTW process
which should be followed when an employee returns to work following a
sickness absence (where no manager’s prompt has been reached). 
Page 230

Page 231

Official
4.7.5 The data (from October 2023 and September 2025) was analysed, the
processes were mapped and those who complete RTW tasks were asked
about their experiences of the process to help identify areas for improvement. 
As a result, the intranet pages were updated to make the guidance more
straightforward for managers to follow and improvements to the online form
introduced. Work will continue in the new financial year by focussing on the
approach when manager’s prompt has been reached and the subsequent
steps which should be taken. It is expected that these improvements will
support managers and employees to undertake these processes more
effectively, essentially bring efficiencies and contribute to supporting
attendance. 
Information & Data 
4.7.6 The workforce planning console is the key interface of workforce information
for managers using real time data.  Further developments have taken place
this year providing the following: 
• Maternity Leave indicators
• First Aid Allowances indicators and reporting
• Timesheet analysis now included Teacher specific payments
• Moving of HR21 reports onto the Console
• Demonstration Console created for Training and illustration purposes
• New front-end layout, style and colour scheme
• Minor improvements to SSSC registration and pre-registration report
• Various behind the scenes improvements for performance 
4.7.7  As this remains a key tool for daily workforce planning and longer-term trend 
analysis, future improvements are planned around post specific reporting,  
moving further HR21 reports to the console, integrating the Leisure Trust to
the console and further improvements to the user interface. Table 1 below 
outlines the console usage over the period. 
Page 231

Page 232

Official
Table 1   
4.7.8  The number of hits on the console has increased from last year by 426 with
the top reasons for remaining similar as illustrated below in Diagram 1 and 2:
Diagram 1 (Below): Console Hits 2024/25: 
Console Usage 2024-25 Console Usage 2025-26 
Month
Average No of users
per day ** Including
weekends 
Month 
Average No of Users
per day **not
including weekends)
APR-24 8.2 Apr -  25 31.27
May-24 9.2 May -  25 32.23
Jun-24 10.6 Jun - 25 29.81
Jul-24 11.8 Jul - 25 28.83
Aug-24 18.2 Aug -25 34.62
Sep-24 23.3 Sept - 25 30.05
Oct-24 23.1 Oct -25 35.43
Nov-24 23.8 Nov -25 34.95
Dec-24 18.2 Dec - 25 27.87
Jan-25 23.7 Jan - 26 35.55
Feb-25 28 Feb-26 35.20
Mar-25 31 Mar- 26 28.73
Page 232

Page 233

Official 
Diagram 2 (Above): Console Hits 2025/26 
4.7.9 Data and analytics continues to play a key role in considering future resource
requirements and supported the People & Change function, leading to a
review of the workload and support the team provides. 
4.7.10 Surveys, self-evaluation, service design and quality improvement exercises
and workshops continue to provide beneficial insight into areas for
enhancement and have informed associated action plans. 
4.8 Priority 4. Skills & Capabilities: Current and future skills gaps and
capabilities are addressed. 
Learning & Development 
4.8.1 Following the People & Change restructure, Learning and Development 
activity has been incorporated within the People & Change Partners remit. 
This change supports a more joined up and consistent approach to   
workforce development, organisational change and capacity building across  
the Council.   
4.8.2 The comprehensive in-house delivery programme continues to be well 
supported by managers and employees.  Feedback from delegates   
continues to be very positive across all programmes with an average rating 
of 4.7/5.  Feedback from delegates reinforces that employees both enjoy the  
development and can apply the learning in their own workplace context. 
4.8.3 Usage of iLearn continues to be key in the development process, although
there is a decrease in numbers this year this may also be due to the
declining headcount and recruitment intake as course are usually renewed
every 1-2 years. The number of users still engaging is substantial and
learning remains accessible on any device 24/7 iLearn providing flexibility to
Page 233

Page 234

Official
ensure that there is learning provision for all employees, regardless of their 
working hours or style.  Usage over the last 3 years can be seen in Diagram
3 below: 
Diagram 3 
Digital Transformation & Skills 
4.8.4 A Digital Senior Manager’s Network was delivered in June 2025.  External
speakers were present to update on:
• Alignment of local and national priorities
• M365 – the art of the possible
• Demistifying RPA and AI
• Turning Data into Action
4.8.5 Service Design training was offered.  This training (developed in-house by a
qualified service designer) provided an overview of service design including
research methods, the development of an idea through to solution and
continuous improvement thereafter.
4.8.6 Two resources (Digital Duel and Digital Dilemma) were developed with an
aim of making digital fun.  Digital Duel introduced a character and allocated
them points in 6 different digital related categories.  Thereafter you tried to
win all the cards by picking the category which you thought would beat your
opponent (i.e. the computer).  Digital Dilemma made further use of these
characters but posed a digital related question and asked who the best
character would be to help.
4.8.7 The Digital Office for Scottish Local Government and the Scottish Digital
Academy developed a series of 15 videos on data literacy focussing on what
data is and why it matters.  The series was advertised on a weekly basis.
4.8.8 The Digital Office for Scottish Local Government, the Scottish Government
and the Data Literacy Academy worked in partnership to create Data Literacy
training and two employees from the Change & Digital team participated in
Page 234

Page 235

Official
the pilot delivery of this training.  One employee successfully completed the
Data for Business training and the other completed the Data for Business Pro
training.
4.8.9 The M365 Skills Hub was advertised.  This is an online learning resource for
Microsoft users which is available to local authorities and other public sector
organisations.  Through the hub, self-paced guided learning is available, you
can view recordings of training sessions and there are opportunities to join
live training sessions in the future.  Free training opportunities from Microsoft
were advertised including the 5-week TechHer programme which offers free
introductory training on cloud computing, artificial intelligence, power
platform, Copilot and online security.  Virtual Training Hours were promoted. 
This training gives employees an opportunity to develop their digital skills by
attending instructor led webinars. Topics which were offered during the most
recent programme included Microsoft 365 Copilot, Copilot Chat, Copilot
Agents, Power BI, boosting productivity with Copilot in Outlook, PowerPoint,
Word and Excel.
4.9 The current workforce profile 
4.9.1 The workforce profile as at 31/3/26 is attached in Appendix 2, with
comparisons made against the previous year and commentary on trends. 
The main observations are detailed below. 
4.9.2 There has been a 3.93% decrease in Headcount and working hours which is
nearly double the decrease of the previous year. When compared to the same
period last year, there has been a headcount reduction of 210 across the
council, a 100 more than last year. This reduction change is spread across
the services and is mainly accounted for by the implementation of savings
options and recruitment restrictions. 
4.9.3 This year has seen a decrease in fixed term contracts indicative of  service
reviews coming to a conclusion and a further decrease of 10 apprenticeships
mainly from Roads & Neighbourhood Services. The casual/supply pool
headcount has also decreased particularly supply teachers. This is due to
auditing of the pool for those who have not undertaken work within a specific
time frame, moving teachers into different contracts and also them moving to
employment elsewhere. It is also indicative of the reducing pool of qualified
teachers available to the Council.   
4.9.4 Reviewing the comparison data the overall workforce has steadily 
declined across the services in measures that are indicative of their size with 
the bulk of the reductions in Community Health & Care, most likely due to the 
Home Care Review. 
4.9.5 The percentage split of the overall sex profile continues to remain a static with
an overall split of 26.6% male and 73.4.% females as does the age
distribution.  It can be noted that there is a slight difference in the age group
categories, although the 60–64-year-old category percentage remains stable,
Page 235

Page 236

Official
loss of headcount from other age groups has resulted in this being the second
highest age category this year. The percentage of those working past 65
years of age has remained stable. 
4.9.6 In line with the reduction in headcount there is also a less new starts this year
as Services make considerations around budgets, structures and recruitment.
Turnover has increased this year also to 15.7%, 3.5% from the previous year
in line with that of 2022/23 (15% in 2022/23, 13.2% in 2023/24 to 12.2% in
2024/25).  The highest percentage turnover remains in Citizen, Culture and
Facilities closely followed by Education and Community Health & Care in
terms of headcount.   
4.9.7 There has also been a slight increase in the number of Voluntary Severance
and Voluntary Early Retirement (VS/VER) by 5 from 2024/25 due to service
reviews and budget savings being implemented. Although the VS/VER
process is now targeted and individuals who are part of the service review
processes where their roles are ‘at risk’ it is expected that this figure will
remain similar as we enter into 2026/27 budget savings processes. 
4.9.8 The number of employees taking retirement between the ages of 55-59 has
decreased this year along with the number of flexible retirement applications
approved. It is noted that the changes to the Pension fund in terms of strain
on the fund figures for flexible retirement and Services ability to mitigate these
in the current financial climate will have impacted on the number of approved
applications.  Flexible Retirement continues to be a popular option for
employees who wish to work in a reduced capacity and access their pension
whilst enabling the Council to retain their skills and experience, however the
trend of a reduction in those released may continue due to the costs
associated. 
4.9.9 This year has seen a slight increase in sickness absence compared to the
previous year (14.53 full time equivalent workdays lost per employee) from
14.3. in 2024/25.  Although the same reasons of minor illness, personal stress
and acute medical conditions remain the highest with front line employees
having the highest levels of sickness. Employee wellbeing and engagement
supports will continue to be developed and deployed. 
4.10 Workforce Planning Actions for 2026/27 
4.10.1 The Corporate Workforce Plan for 2026/27 has been reviewed and updated in
line with progress and priorities and key actions are summarised in the P&T
Delivery Plan 2026/27 at Section 3, Strategic Assessment. 
4.10.2 A summary of key areas for progression and continued development are
outlined and build on many of the actions in previous years. It is recognised
that these actions are all interdependent and contribute to the wider People
First Strategy but are also reliant of resourcing which requires to be prioritised
to meet the needs of service delivery and savings. 
Page 236

Page 237

Official
4.10.3 A mid-year update will be provided as part of the service delivery plan
reporting schedule, and a more detailed outline of progression will be reported
at the end of 2026/27 for workforce planning. 
4.10.4 The People First and Workforce Planning Strategies will require review
following 2027 and planning and consideration around future strategic
developments is likely to commence this year in line with the Council’s
Strategic Planning Process. 
4.10.5 The priority areas of work will continue under the same banners as 2024/25
and outlined in section 4.1 and will be managed through the People and
Technology Service Delivery Plan.   
5 People Implications 
5.1 Integration of workforce planning within wider organisational planning
processes ensures that workforce issues are effectively identified and
addressed. This supports the Council’s commitment to its’ employees in
relation to all aspects of their employment, ensuring that employees’ needs
are met, and that efficient and modern services are effectively delivered both
now and in the future. 
6. Financial and Procurement Implications 
6.1 There are no additional financial or procurement implications associated with
this report. There are funding streams associated with the initiatives
mentioned in this report, but these are already secured. 
7. Risk Analysis 
7.1 A robust approach to workforce planning ensures that the Council identifies
current and future needs and identifies potential risks to the council at an early
stage. This proactive approach allows strategies and policies to be developed
that ensure the continued delivery of best value services. A risk has been
identified in relation to being sufficiently resourced to be able to undertake key
workforce planning actions in the coming year and/or to be able to respond to
workforce planning actions arising. 
8. Equalities Impact Assessment (EIA) 
8.1 A full EIA is not required in relation to the Council Workforce Plan as
individual assessments will be undertaken in relation to each area of work
referred to as it is progressed. 
Page 237

Page 238

Official
9. Consultation 
9.1 The Strategic Leadership Group have been involved in the development of
the plan through preparation of the Delivery Plans and this report and
associated appendices have been provided to the relevant trade unions on
12th May 2026. 
10. Strategic Assessment 
10.1 The contents of this report and the workforce planning process supports the
Council’s Priority 4, ‘Our Council’, Objective 10 ‘Our workforce is resilient and
skilled where digital technology supports service delivery for our residents’ to
make the best use of both financial and human resources resulting in a
positive impact upon service provision. 
Victoria Rogers 
Chief Officer - People & Technology 
Date: 12th May 2026 
Person to Contact: Lisa MacGregor, People and Change Partner
16 Church Street, Dumbarton
Tel: 07949800801
Email: Lisa.MacGregor@west-dunbarton.gov.uk 
Appendices: Appendix 1 – Council Workforce Plan Progress update
2024/25 
Appendix 2 – Workforce Profile and Monitoring 31st
March 2026 
Background Papers: Council Workforce Plan 2017-2022:  Update & Annual
Action Plan 2022/23
Chief Officer Area Workforce Plans (as part of Service
Delivery Plans) 2022-2027
The Workforce Planning Strategy and Framework 2022 –
2027 
Wards Affected:  None 
Page 238

Page 239

Appendix 1 - Workforce Planning 25-26 Strategic Actions Overview actions. 
3lst March 2026 
1. Our People (Workforce Profile) 
Strategy
Develop and implement wellbeing, employee engagement, equality, and training plans to enable capabilities, improved resilience and promotion of a diverse workforce. 
SERVICE KEY ACTIONS TO CONTINUE INTO 2026/27
Citizens, Culture and Facilities – Amanda Graham, Chief
Officer 
• Review employee engagement following Facilities
Management model implementation - consultation for
service redesign is complete. Facilities management has
implemented ongoing engagement as part of redesign and
will have a further staff survey following implementation of
the new service model in 2026/26
• Investigating technology options with Council data analyst
to deliver improved absence and leave planning in contact
center alongside market research 
• Libraries looking at automation to provide work force
scheduling tool and subject to outputs this may transfer to
Contact Centre 
Education Services – Gillian Hamilton, Chief Officer • Moving to implementation of Children's Support Service
review
• Children’s Support Service Review
currently paused 
Housing Services, Peter Barry, Chief Officer • The Building Services improvement plan continues to be
implemented with significant progress made with ongoing
focus on automation, communication, and culture. 
ITEM 13 - APPENDIX 1
Page 239

Page 240

• Regular 1-to-1s with frontline staff are embedded,
alongside monthly toolbox talks, monthly newsletters, and
biannual Be the Best conversations. There has been a
noticeable positive shift in culture, with continued emphasis
on maintaining effective back-to-basics conversations. 
People & Technology, Victoria Rogers, Chief Officer • People & Change restructure and transition completed
• Developed and delivered wellbeing session for People &
Change team to support team in busy transition period
following restructure
• Monthly Team Meeting format updated to reflect current
needs of team with weekly team calls adjusted to reflect
requirements to help to ensure team development and
wellbeing is supported within the reduced capacity of the
new team structure. 
Resources, Laurence Slavin, Chief Officer • Assessed succession planning across service areas to
ensure preparedness for known and potential
exits/absences from the Council and supports for
individuals and wider team. Actions completed including
creation of temporary roles to aid succession planning in
Finance and realigning Finance Business Partner roles to
support transition to new structure
• Planning commenced in Asset Management in preparation
for planned retirements
• Consider future structured approach to workforce planning
rather than piecemeal reductions including Finance
restructure, changes within Audit team, succession planning
in Assets and mapping of critical roles in Business Support.
• Reviewed age profile for succession planning across Asset
services in anticipation of flexible working/retirement 
Page 240

Page 241

applications over next 1-2 years to ensure resilience 
Roads & Neighbourhood, Gail MacFarlane, Chief Officer • Continued monitoring of workforce demographics to ensure
resilience and promotion of service for breakdown of
gender stereotypical roles through Modern Apprenticeship  
and Recruitment Programmes
• Working 4U have continued to promote of roles with a
gender Bais across all genders. This includes sessions
within schools to attract or encourage school students to
have a broader understanding of the opportunities available
to them
• Roads Structure Review commenced identifying single point
dependencies
• Grounds and Waste services will promote use of trickle with
front line staff at the next “toolbox talks”. 
• Commenced reviewing of succession
planning requirements (Critical
Roles). Action progressing with
Roads Structure Review commenced
and Grounds and Waste Review to
commence.
• Service working with HR to develop
a workforce update highlighting the
benefits of Trickle to front line staff 
CASE STUDY: 
P&T – People & Change Re-structure
As part of workforce planning activity to support compliance with the Strategic Operating Model (SOM), several targeted changes were implemented across People & Change
specialist teams. These changes focused on maintaining statutory and core service delivery while reducing management layers and accepting a measured reduction in
capacity for discretionary and improvement activity.  Within Organisational Development, the removal of a senior lead post improved SOM compliance and strengthened
alignment with Strategic HR through revised line management arrangements. Core learning and development provision continued unchanged, supported by an existing
strategy to 2027. The primary impact was a reduction in capacity to design new interventions or respond to bespoke requests. 
In Health & Safety, the move to a single lead model reflected successful succession planning and increased generalist capability across the team, including fire safety
competencies. Statutory duties continued to be met, although some audit and inspection cycles were extended from two to three years from 2025/26, reflecting reduced
capacity and the loss of specialist experience. 
Strategic HR experienced a reduction in senior management capacity through the deletion of a People & Change Partner post, increasing spans of control to achieve SOM
Page 241

Page 242

compliance. While core reactive and operational support continues to be prioritised, preventative, wellbeing, and improvement activity has reduced.  The approach taken
across the teams mitigated against the loss of 2 experienced members of the team in a short space of team, with the retirement of the previous Strategic People and Change
Manager being brought forward, this meant that the pool of People and Change Partners were able to apply for a promoted post with the vacancy created through the
appointment being taken as the saving and avoiding a compulsory redundancy situation.   
Through the use of the Organisational Change Policy and Procedure and successful succession planning, the team have been able to transition to the new structure effectively
whilst mitigating impact on core service delivery. 
2. Recruitment & Retention 
Strategy
Develop and implement employee life cycle plans in line with the People First Strategy to attract and retain the workforce. 
SERVICE KEY ACTIONS TO CONTINUE INTO 2026/27
Citizens, Culture and Facilities – Amanda Graham, Chief
Officer 
• Recruitment has centred around facilities management and
the re-structure with several new promoted posts being
available for internal employees giving increases of grade
and hours as well as development opportunities 
• Remaining vacancies to be filled
externally following exhaustion on
internal employee talent pools.
Education Services – Gillian Hamilton, Chief Officer • Completion of annual staffing exercise is complete to
support the recruitment and retention of teachers in line
with service and workforce needs, school roll projections,
national policy and organisational change procedures
• Exit strategies for temporary funding streams that impact
on employee roles has commenced along with
Organisational Change procedure – further work will
proceed in 2026/27 
• Allocation of probationer teachers
still to take place along with bulk
recruitment exercise for teachers.
Housing Services, Peter Barry, Chief Officer • Reviewed methods to improve recruitment & retention for
hard to recruit roles within each service area
• Increased scope for advertising roles for plumbing and
• Work is also underway to explore
costings and information for a
Housing Options Toolkit for all
Page 242

Page 243

Joiners. This had a positive impact after apprenticeship
additional year is allocated to retain staff and improve
qualification levels. 
• Implemented quarterly check-ups with area coordinator to
ensure retention of workforce and ensure best experience
for the apprenticeship, this has resulted in positive
experiences and encouraged take up of driving licences for
improved future employment.
• Reviewed Career Pathways in Housing and access to
qualifications/learning to allow employees to progress by
encouraging staff to undertake HNC construction
management course.
• Work is also underway to explore costings and information
for a Housing Options Toolkit for all frontline Housing
Operations staff. 
frontline Housing Operations staff. 
People & Technology, Victoria Rogers, Chief Officer • New role profile templates developed and tested to support
job evaluation, recruitment & retention, succession planning
& career pathways and employee development. 
• Implementation will commence in
26/27 with approach considering
reduced resource available.
Regulatory & Regeneration, Alan Douglas, Chief Officer • Completed implementation of management review in legal
services by filling vacant posts including section head posts
• Completed implementation of restructure in Building,
Planning and Environmental Health Services by filling
remaining vacant posts where possible.
• Developed a building standards training post and a
technical support officer is attending an HNC Architectural
Technology course to ensure resilience 
• Further work to be completed
regarding new posts that will
require to be filled.
Resources, Laurence Slavin, Chief Officer • Actions planned for this year in relation to responding to
recruitment requirements in terms of national shortages, 
Page 243

Page 244

attraction to the role and gender barriers, career pathways,
and development opportunities
• Developed pathways, where feasible, for career progression
and foster continuous learning and development to ensure
the council is retaining and developing talent 
CASE STUDY:
Housing Services – Building Services & Modern Apprenticeships 
Building Services has, in recent years faced problems in relation to recruiting skilled trade employees into the service and the retention of
apprentices after their training time was served.  A benchmark comparison of other Local Authorities was undertaken and indicated that our
salary rates were average compared to the external market.  It was acknowledged however that our terms and conditions and security of
employment are better than the private sector and that we cannot compete with short term (higher renumerated) contracts. 
In order to retain our apprentices and create a talent pool to ensure we are appropriately resourced in the future the Service offered apprentices
1 year fixed term contracts at the end of apprenticeships with a view to make permanent if possible. The Service also promoted an advanced
craft qualification which the Council fully funded.  As a Council employee there is always an opportunity to undergo additional training which we
part fund too.  In addition to advertising on My Job Scotland alone, the service have also shared vacancies and opportunities on the Council
Facebook page to widen the search when recruiting whilst promoting our Terms and conditions of employment. 
Although recruitment remains a challenge, with these additional steps we can ensure that any recruitment opportunities are explored fully.  The
number of apprentices leaving within a year of the time being served is now low and we look to provide any learning opportunities where
possible to retain them.  Depending on the external market at the time of the recruitment there may not be a good response but re-
advertisement often yields more interest. 
Next steps would be to continue to build on the initiatives in place and through the monthly Workforce Update continue to promote ongoing
training opportunities as well as tapping into any partner training which is applicable for continuing development. 
Page 244

Page 245

Priority 3: Roles & Structures
Strategy:
Implement service review process including role design, use of new technology and new ways of working to add resilience, address gaps, and establish opportunities for
efficiencies. 
SERVICE KEY ACTIONS TO CONTINUE INTO 2026/27
Citizens, Culture and Facilities – Amanda Graham, Chief
Officer 
• Considered roles in relation to optimum operating model
along-side budget savings with work underway to consider
the delivery of savings for 26/27. 
• Arts and Heritage review has commenced and has identified
a requirement to changes to roles and/or structure of the
team with SOM compliance considered
• Libraries Review has commenced and preparation is
underway to consider work required to review and develop
role profiles for Library staff where there is a requirement to
review profiles (Management team).  Role profiles for front
line staff amended to account for Protection of Vulnerable
Groups (PVG) requirements
• Consider peer supports in contact centre for Learning &
Development and efficiencies. One to one process has
identified opportunities, and we have delivered the same via
reception and contact centre
• New model has been developed and will ensure we provide
appropriate resilience for service delivery staff development
and support career progression for front line staff.   
• Arts and Heritage review to continue 
Education Services – Gillian Hamilton, Chief Officer • Reviewed roles within staffing team to ensure they are fit for
purpose and future focussed with a particular attention to
project delivery roles
• Reviewed Early Years Assistant role to ensure that it is fit for
purpose. 
• Consultation with trade unions is
due to commence.
Page 245

Page 246

• 2025/26 Savings options implemented across the service
with consideration of service delivery and impacts on teams            
New Faifley Campus opened with required changes to         
teams in Auchnacraig & Lennox made to ensure that   
transition was appropriately supported
• Implement Children's Support Service review commenced
with new role in place
• Reviewed of how the Professional Learning Team deliver the
service to ensure new requirements met with limited
resource following changes to General Teaching Council
Standards (GTCS) levels. Engagement maintained with GTCS,
West Partnership, and neighbouring Local Authorities to
support implementation of the updated MyGTCS platform.
Full engagement with GTCS training materials to support
successful rollout. Guidance and training actively promoted
to provisionally registered teachers, supporters, and head
teachers. 
• All Probationer Teachers completed training on MyGTCS
platform functionality and responsibilities.
• Expansion of Additional Support Needs support with the
new Riverside establishment opening in August 2025
• Implemented use of new technology and new ways of
working to add resilience, address gaps, and establish
opportunities for efficiencies including online payment
processes implemented to support automated payment of
childcare hours and Out of School Care and fully remote
access to the Psychological Service database delivered in
collaboration with ICT.
• Shared Google Classroom promoted and used effectively to
streamline access to student data and resources for Student
Coordinators and School Regents with Google File structure
established based on How Good is Our Local Education 
• New job profiles undergoing job
evaluation implementation is
aligned to support service review
which is currently delayed 
Page 246

Page 247

Authority and the National Improvement Framework, ready
for population.
• Continued use and updating of local protocols and systems
for managing student placements including active
engagement with stakeholders, new guidance, and training
opportunities to ensure high quality, GDPR compliant
placement processes. Includes ongoing engagement with
national networks to ensure alignment with national
protocols and partnership working with universities to
ensure accurate and timely placement information.
• Initial scoping with PEPs to align self-evaluation to new
guidance and list of Performance Indicators for Education,
Learning and Attainment produced to audit duplication and
repetition. Supporting templates and datasets produced for
Early Years Data Leads and New Primary Data Leads
established 
•  Excel training for new Primary Data Leads delivered in
January 2026.
• Completion of local authority self-evaluation How Good is
our Local Authority evaluation in quality indicator 1.2
Improving outcomes and How Good is our Local Authority
evaluation in quality indicator 1.1 Leadership, Direction and
Continuous Improvement. Engagement with QUAD local
authority officers to evaluate strengths and areas for
improvement. 
• Dates and topics agreed for Early
Years Data Leads to support
expansion of system wide data
work. 
• Engagement with Education Officer
(Senior Phasing) regarding
Secondary Data Leads Programme
via Curriculum Support Networks- 
proposal completed and agreed in
principle. 
Housing Services, Peter Barry, Chief Officer • Modernised service delivery through workforce flexibility
and capacity including pilots for multi-skilling and flexible
working to improve efficiency, Value for Money, and
customer satisfaction
• Flexible retirement and flexible working have been
• Work is ongoing with Strategic HR
partner to review Housing Assets
structure for SOM compliance
Page 247

Page 248

considered and implemented where possible
• A continual drive towards Value for money exercises and
ideas run through all monthly meetings to achieve relet
standards and repairs policy standards adequately without
exceeding obligations, managing throughput and customer
expectation.
• Reviewed Fixed Term contracts within Building and filled
permanently for resilience.
• Work is ongoing with Strategic HR partner to review HA
structure for SOM compliance 
People & Technology, Victoria Rogers, Chief Officer • Implement ICT revised team structure and adjusted service
provision. Structure is SOM Compliant with adjustments at
management level. 
Regulatory & Regeneration, Alan Douglas, Chief Officer • Reviewed structure in line with SOM principles to identify
and address areas of non-compliance where necessary.
Changes identified to management level roles
• Reviewed impact of saving options and management
adjustments identified as part of budget process for 25/26
and implement any required changes.
• Planning, Building Services and Environmental Health
identified within options. Savings for Review of
Environmental Health and Antonine Wall achieved with
minimal impact on overall service delivery. 
• Implementing flexible structure in Building Standards team
that allows appointments to be made based on service need
whilst providing potential career pathway in key areas of
work. 
• Actions to implement changes
required have begun 
• Planning savings in progress - Lead
Planner post was not able to be
filled but service has now been
successful in recruitment.
Combining Dog and Pest Control
ongoing and savings expected to be
achieved in line with target. 
• Building Services Structure agreed.
Structure will be in place 26/27
Page 248

Page 249

Resources, Laurence Slavin, Chief Officer • Review Internal Audit Service - Activity planned for 25/26
completed.  Service reviewed and new delivery model
identified and implemented.
• Continued to embed the new structure within Finance in line
with timetable; temporary posts in place, succession
planning completed, Finance Business Partner roles
realigned.  
• Service re-structure in Asset management commenced
• Implementation will continue into
26/27 as planned until completion. 
• Service re-structure in Asset
management in relation to working
hours, trainee post, career
progression, Som Compliance and
staff development and resilience
delayed due to resources but will
continue in 2026/27 
Roads & Neighbourhood, Gail MacFarlane, Chief Officer • Review structure and roles in Roads & Neighbourhood to
reflect service delivery requirements in line with budget
savings for 2025/26 and SOM Compliance
• 
• Cross service review underway to
review service capacity and
resources.
CASE STUDY: 
Citizen, Culture & Facilities - Facilities Management – Re-structure 
Facilities Management (FM) is one of the Council’s largest services, employing around 600 staff delivering cleaning, janitorial and catering
services across operational and educational buildings. 
Prior to the redesign, the service faced long-standing challenges including high absence levels, recruitment and retention difficulties,
fragmented contracts and limited career pathways.
In response, a comprehensive service redesign was undertaken, informed by a service review, staff survey, working groups, extensive
consultation wih employees and ongoing engagement with Trade Union colleagues. 
Over 400 one-to-one meetings were held with staff, supported by regular communications and access to wellbeing and HR support.
Implemented on 30 March 2026, the new model provides a more resilient, flexible and efficient service, with fairer contracts, clearer progression
Page 249

Page 250

routes and reduced reliance on overtime and agency cover.
Next steps include embedding the new structure, ongoing staff engagement and monitoring workforce outcomes to ensure benefits are
sustained. 
4. Skills & Capabilities 
Strategy
Develop and implement training plans and development opportunities to improve capabilities and resilience within the workforce.
SERVICE KEY ACTIONS TO CONTINUE INTO 2026/27
Citizens, Culture and Facilities – Amanda Graham, Chief
Officer 
• Addressed performance issues within services to ensure
quality services in Facilities management and contact
centre. Performance is being proactively managed with
Facilities Management. Telephone performance reviewed
and reported to PMRG Sept 2Report produced and outcome
and actions completed. Visited all SMT for discussion on
customer service and complaint management. Awareness
and adherence sessions
• Developed forum for managers for ‘lessons learned’ across
service for peer support and consistency of application
meeting every 6 weeks to review instances and share best
practice.
• Develop and implement learning and development
opportunities to improve capabilities and resilience within
the workforce. 
Education Services – Gillian Hamilton, Chief Officer • Employees worked with corporate support teams to explore
further opportunities to use robotic process automation in
school offices and reduce volume of manual admin tasks. A
list of possible automation projects has been submitted.
• Ensure employees are appropriately skilled to implement
the digitisation of school transportation processes. 
• List of possible automation projects
has been submitted for
consideration
• This action is shared with Internal
Transport. Education team are
upskilling in terms of GIS and
Page 250

Page 251

• Implement Continuing Lifelong Professional Learning
guidance for Early Years employee group that are SSSC
registered to ensure compliance with new registration
requirements
• Identified and develop opportunities to maximise impact of
Share point across the service and adapt ways of working as
required
• Update on changes to professional learning requirements
shared with Heads and Managers at the Leaders Meeting
and Scottish Social Services Council (SSSC) advice support
guide issued to all staff teams.
• Pathways Model shared with all establishment leaders
alongside Professional Review and Development (PRD)
paperwork and guidance reinforcing expectations around
PRD engagement. 
• Leadership Pathways Model promoted through bulletin,
social media, staff focus groups, and Google platforms.
• Leadership Pathways Model updated to align with Support
Staff and Support Staff in Specialist Settings, clarifying core
and enhanced expectations.
• ELCO workforce survey completed to gather views on
further training and support needs.
• Evidence gathering underway through data review and the
first focus group (WDC DHTs) to identify leaders and
establishments not yet involved in coaching development.
• Whole service professional learning offer established in
collaboration with all Education services.
• Comprehensive central professional learning overview
developed and shared for Terms 1–2, updated in January for
Terms 3–4, providing streamlined access for all ELCC,
Primary, and Secondary staff.
• Overview promoted via Professional Learning Coordinators
webforms, and IT are upskilling in
filling in the forms online instead of
paper-based systems.
Page 251

Page 252

Term 1 Forum and HT Induction.
• Multi agency Calendar of Professional Learning shared
across platforms as part of the WDC Professional Learning
Overview and through networks and forums.
• Central booking system for professional learning spaces
embedded.
• Temporary Staff Learning Passport implemented to support
staff in evidencing training, impact, and development
needs.
• Six Improving Our Classrooms (IOC) participants
undertaking this year’s programme; all have completed five
core sessions and begun data interrogation to inform
Casetudy improvement Questions.
• Learning visits scheduled for January/February to support
triangulation of evidence.
•  Four IOC mentors recruited from last year's cohort, with
one returning mentor added.
• Education team upskilling in GIS and webforms.
•  IT team upskilling to complete forms online instead of
using paper based systems. 
Housing Services, Peter Barry, Chief Officer • Refresh management skills and effectiveness to meet
service demands and financial pressure - focus at
management meeting has been to apply financial
constrictions and make saving where possible.
• Management skills and effectiveness refreshed through the
introduction of Power BI service reports across Housing
Operations, now in place for Team Leaders and above. 
• New reports covering areas such as, abatements, decants,
voids, and lettings are actively used. Balanced scorecards
are scheduled between Team Leaders and Management to 
Page 252

Page 253

help reduce spend while maintaining value for money and
service quality. 
• Ongoing monitoring continues to ensure management
capability remains effective in addressing service demands
and financial pressures. 
People & Technology, Victoria Rogers, Chief Officer • Digital Skills of team developed in order to support roll out
of M365 and Sharepoint- as appropriate Resources shared,
further learning will now be part of business as usual skills
development for team.
• Strategic Human Resources, HR Connect and Payroll are in
process of migrating to M365 and Sharepoint, team
meetings taken place to develop teams awareness of
functionality and support resources shared to develop skills. 
Regulatory & Regeneration, Alan Douglas, Chief Officer • Identified learning opportunities that support the
development of skills and knowledge required for hard to
fill posts in Building Standards team - revised structure to
support career pathway agreed by Strategic Resources &
Recovery Group
• The service secured a funded place on an HNC Architectural
Technology course that has been attended by an officer
from the technical support team. 
• Implementing in conjunction with
HR and Job Evaluation.
Resources, Laurence Slavin, Chief Officer • Developed pathways, where feasible, for career progression
and foster continuous learning and development to ensure
the council is retaining and developing talent - In Business
Support given the financial pressures, SOM and limited
training budget, focus has been on maximising internal
opportunities such as job shadowing, project-based
development, and knowledge sharing across teams. 
Page 253

Page 254

• Regular 1 to 1 discussions will continue to identify
aspirations and support career conversations, ensuring staff
feel valued and engaged despite constrained resources.
• Focus on cross skilling of roles/skills for resilience and
career progression in Asset Management & Finance Services.  
Roads & Neighbourhood, Gail MacFarlane, Chief Officer • Upskilling drivers across the service to undertake the range
of driving duties to promote cross service working and
improve resilience - Drivers put through LGV training and
C1+E trailer training. 
• Fit for future actions progressed including training for
mechanics and new ilearn developed within Fleet Services to
promote development opportunities. Cross service
consideration being given to hard to recruit roles.
• Mechanics trained in maintenance of Electric vehicles and to
continue to monitor development of technology to stay up
to date 
CASE STUDY: 
Education Services – Leadership Pathways Model 
Leadership development across the service lacked consistency, transparency and systematic monitoring, making it difficult to ensure equitable
access to high-quality professional learning. There was no single mechanism to track participation, identify gaps across sectors or ensure staff
were being supported consistently regardless of role or establishment. Workforce analysis highlighted further risks, including an ageing
leadership profile, anticipated retirements, recruitment challenges and uneven engagement in existing opportunities. These issues collectively
demonstrated the need for a manageable, equitable and transparent model to strengthen leadership capacity and support sustainable
workforce planning. 
Page 254

Page 255

To address these challenges, we developed and implemented the WDC Leadership Pathways Model—a structured, progressive and
service-wide approach to leadership development. The model includes a universal strand offering all staff access to high-quality leadership
learning, and a targeted workforce-planning strand that tracks participation to ensure transparency and equity. It was co-designed with staff
across all sectors to identify role-specific leadership skills and align professional learning with GTCS and SSSC Standards, corporate
leadership frameworks, PRD processes and the wider WDC professional learning offer. Designed as a live, adaptive framework, the model is
regularly updated to remain responsive to emerging needs. 
The model has delivered clear benefits, creating a consistent, transparent and standards-aligned approach to leadership development. Staff
now access a streamlined “one stop shop” offering coherent, role-specific learning and clear pathways for progression. Engagement has
strengthened significantly: uptake of the national Into Headship Award has nearly doubled, with many participants progressing into acting or
permanent Head Teacher roles. Of the 60 staff engaged in the model in session 24/25, 42% moved into the promoted post they were preparing
for. Staff report improved communication about opportunities, greater equity of access and easier navigation of professional learning. The
model has also enhanced workforce planning by enabling targeted, needs-led professional learning informed by robust monitoring data. 
Next steps will continue the focus on deepening integration of the Leadership Pathways Model within the WDC Be the Best Framework to
ensure all staff, including non-teaching colleagues, access leadership development. We will continue embedding leadership development within
PRD processes, using evaluation data to refine professional learning offers and expand high-quality, role-specific opportunities. Ongoing
monitoring will strengthen the workforce-planning strand by maintaining a clear profile of staff preparing for promotion. We will also widen
communication channels and support leaders and Professional Learning Coordinators to champion the model, ensuring early-career staff
experience leadership development as a core expectation of practice and sustaining a future-focused leadership workforce. 
Page 255

Page 256

Official
Appendix 2 – Workforce Profile and Monitoring Report – 31st March 2026 
This appendix provides information on the workforce demographic, allowing for monitoring of trends and consideration of workforce
impacts and includes headcount, contract status, grade, sex and gender profiles, length of service, new starts, turnover and leavers
and analysis of employees released through early retirement and voluntary severance. Also included is information relating to
redeployment through the SWITCH process and sickness absence. 
1. Headcount 
Table 1.1 below relates to the year-end workforce profile as of 31st March 2026 and examines changes in that profile over time. 
Table 1.1 
When compared to the same period last year the council wide total headcount has decreased by 220 overall. This is due to
reductions of 166 permanent contracts, 10 apprenticeships and 44 fixed term contracts. The casual headcount has decreased by
100 compared to the previous year, mainly due to a reduction of 128 casual teachers. This will be due to auditing the casual pool
and placements in other contracts. 
ITEM 13 - APPENDIX 2 
Page 256

Page 257

Official
Table 1.2 below shows this year’s figures compared to the last 4 years and illustrates a reduction in apprenticeship roles since
2025, after seeing an increase between 2023 – 2024. It also captures the steady decline in the workforce; -7.89% in the fixed term
headcount and -3.34% in the permanent headcount. 
Table 1.2 Headcount Variance 
Overall Headcount
Variance Apprentices Fixed Term Permanent Total
31/03/2022 - 31/03/2026 No. % of Total Yrly Var No. % of Total Yrly Var No. % of Total Yrly Var No. Yrly Var
31/03/2022 54 0.91% -7.00% 527 8.91% -1.00% 5335 90.18% 1% 5916 -1.00%
31/03/2023 62 1.06% 14.81% 485 8.26% -7.97% 5326 90.69% -0.17% 5873 -0.73%
31/03/2024 69 1.17% 11.29% 509 8.92% 4.95% 5123 91.44% -3.81% 5701 -2.93%
31/03/2025 59 1.05% -14.49% 558 9.98% 9.63% 4974 88.96% -2.91% 5591 -1.93%
31/03/2026 49 0.91% -16.95% 514 9.57% -7.89% 4808 89.52% -3.34% 5371 -3.93% 
Page 257

Page 258

Official
Table 1.3 below provides more information on the variance across all services with the comparison data illustrating the steady
reduction of the workforce. 
Table 1.3 Variance across services (in headcount) 
2026 compared to 2025 Apprentice Fixed-Term Permanent Total
Citizen Culture & Facilities 0 0 16 -37 605 20 621 -17
Education 4 -1 126 7 895 -30 1025 -24
Housing 34 -2 27 -2 478 -24 539 -28
People & Technology 1 0 15 -4 181 -10 197 -14
Regulatory & Regeneration 0 0 3 -1 107 2 110 1
Resources 0 0 4 -2 164 0 168 -2
Roads & Neighbourhood 10 -7 54 6 340 -26 404 -27
Chief Exec Office 49 -10 245 -33 2770 -68 3064 -111
Child Health Care & Criminal Justice 0 0 25 2 226 -3 251 -1
Community Health & Care 0 0 82 -15 784 -75 866 -90
Finance & Resources 0 0 1 0 5 0 6 0
Mental Health Addiction & Learning Disabilities 0 0 5 3 110 -18 115 -15
Strategy, Planning & Health Improvement 0 0 1 0 28 -5 29 -5
Health & Social Care Partnership 0 0 114 -10 1153 -101 1267 -111
Strategic Management 0 0 0 0 12 0 12 0
Local Government Employees Total 49 -10 359 -43 3935 -169 4343 -222
Education (Teachers) 0 0 155 -1 873 3 1028 2
Council Wide Total 49 -10 514 -44 4808 -166 5371 -220 
During the reporting period 2025/26 Community Health and Care had the most significant reduction in headcount, this is influenced
by Care at Home service re-design. 
Page 258

Page 259

Official 
Table 1.4 shows the casual variance headcount compared to last year and shows a decrease of 128 casual workers registered for
work with the Council. Invigilators were previously reported in this category but have been separated as they are not covered by
any bargaining group (Local Government or Teachers) and their pay is reclaimed from SQA. 
Table 1.4 Casual Variance 
Casual   Invigilators  
Citizen Culture & Facilities 51 22 0 0
Education 45 4 81 2
Housing 2 0 0 0
People & Technology 0 0 0 0
Regulatory & Regeneration 5 0 0 0
Resources 0 0 0 0
Roads & Neighbourhood 3 -25 0 0
Chief Exec Office 106 1 81 2
Child Health Care & Criminal Justice 24 -2 0 0
Community Health & Care 85 29 0 0
Finance & Resources 0 0 0 0
Mental Health Addiction & Learning Disabilities 0 0 0 0
Strategy, Planning & Health Improvement 0 0 0 0
Health & Social Care Partnership 109 27 0 0
Strategic Management 0 0 0 0
Local Government Employees Total 215 28 81 2
Education (Teachers) 310 -128 0 0
Council Wide Total 525 -100 81 2 
Page 259

Page 260

Official
2. Full time Equivalent 
Table 2.1 
Apprentice Fixed-Term Permanent Total
Citizen Culture & Facilities 0.00 11.03 447.41 458.44
Education 4.00 84.91 724.55 813.46
Housing 34.00 24.98 454.52 513.50
People & Technology 1.00 13.69 167.64 182.32
Regulatory & Regeneration 0.00 2.60 100.60 103.20
Resources 0.00 4.00 149.72 153.72
Roads & Neighbourhood 10.00 49.49 328.56 388.05
Chief Exec Office 49.00 190.69 2373.00 2612.69
Child Health Care & Criminal Justice 0.00 22.70 202.43 225.13
Community Health & Care 0.00 57.32 587.97 645.30
Finance & Resources 0.00 1.00 4.80 5.80
Mental Health Addiction & Learning Disabilities 0.00 4.48 96.04 100.52
Strategy, Planning & Health Improvement 0.00 1.00 25.04 26.04
Health & Social Care Partnership 0.00 86.50 916.28 1002.79
Strategic Management 0.00 0.00 11.80 11.80
Local Government Employees Total 49.00 277.20 3301.08 3627.28
Education (Teachers) 0.00 144.60 786.20 930.80
Council Wide Total 49.00 421.80 4087.28 4558.08 
Page 260

Page 261

Official 
Table 2.2 Overall FTE Variance 
Overall FTE Variance   
31/03/2022 -
31/03/2026
Apprentices Fixed Term Permanent Total
No. % of Total Yrly Var No.
% of
Total Yrly Var No.
% of
Total Yrly Var No.  Yrly Var
31/03/2022 54 1.09% -35.00% 439 8.88% -6.000% 4453 90.03% 0.00% 4947 -1.00%
31/03/2023 61 1.24% 12.96% 414 8.43% -5.69% 4433 90.33% -0.45% 4908 -0.79%
31/03/2024 68 1.00% 11.48% 423 8.80% 2.17% 4269 89.68% -3.70% 4760 -3.02%
31/03/2025 59 1.26% -13.24% 448 9.61% 5.91% 4153 89.14% -2.72% 4659 -2.12%
31/03/2026 49 1.08% -16.95% 421 9.24% -6.03% 4087 89.67% -1.59% 4558 -2.17% 
Trends indicate a reduction across apprentices, fixed term and permanent contracts in 2025/26. 
Page 261

Page 262

Official 
3. Fixed Term Contracts 
There are 514 employees working on a fixed term basis and 121 of these hold fixed term contracts which have a duration
exceeding 2 years (relevant for various employment rights). This is a decrease from the previous year. The table below illustrates
the location of these employees and compares to last year. 
Table 3.1 
2025 2026
Citizen Culture & Facilities 2 4
Education 31 22
Housing 24 11
People & Technology 4 6
Regulatory & Regeneration 4 1
Resources 2 1
Roads & Neighbourhood 39 41
Chief Exec Office 106 86
Child Health Care & Criminal Justice 7 11
Community Health & Care 4 14
Finance & Resources 0 0
Mental Health Addiction & Learning Disabilities 0 1
Strategy, Planning & Health Improvement 0 0
Health & Social Care Partnership 11 26
Strategic Management 0 0
Local Government Employees Total 117 112
Education (Teachers) 26 9
Council Wide Total 143 121 
Page 262

Page 263

Official
4. Full time / Part time Split 
Table 4.1 
Full-Time Part-Time
Citizen Culture & Facilities 177 444
Education 367 658
Housing 459 80
People & Technology 156 41
Regulatory & Regeneration 87 23
Resources 117 51
Roads & Neighbourhood 356 48
Chief Exec Office 1719 1345
Child Health Care & Criminal Justice 189 62
Community Health & Care 159 707
Finance & Resources 5 1
Mental Health Addiction & Learning Disabilities 59 56
Strategy, Planning & Health Improvement 21 8
Health & Social Care Partnership 433 834
Strategic Management 11 1
Local Government Employees Total 2163 2180
Education (Teachers) 713 315
Council Wide Total 2876 2495 
The number of full time contracts has reduced this year by 37 and the number of part time contracts has also decreased by 183,
reflective of the drop in headcount. 
Page 263

Page 264

Official 
5. Grade Profile 
Table 5.1 
As shown above the most prominent grade amongst Local Government Employees remains Grade 4, followed by Grade 5. For
teachers the most prominent grade remains a Main Grade Teacher. 
Page 264

Page 265

Official
6. Sex Profile 
Table 6.1 
Female Male 
Headcount % Headcount %
Citizen Culture & Facilities 508 81.8% 113 18.2%
Education 959 93.6% 66 6.4%
Housing 154 28.6% 385 71.4%
People & Technology 131 66.5% 66 33.5%
Regulatory & Regeneration 68 61.8% 42 38.2%
Resources 106 63.1% 62 36.9%
Roads & Neighbourhood 77 19.1% 327 80.9%
Chief Exec Office 2003 65.4% 1061 34.6%
Child Health Care & Criminal Justice 203 80.9% 48 19.1%
Community Health & Care 786 90.8% 80 9.2%
Finance & Resources 6 100.0% 0 0.0%
Mental Health Addiction & Learning Disabilities 76 66.1% 39 33.9%
Strategy, Planning & Health Improvement 24 82.8% 5 17.2%
Health & Social Care Partnership 1095 86.4% 172 13.6%
Strategic Management 8 66.7% 4 33.3%
Local Government Employees Total 3106 71.5% 1237 28.5%
Education (Teachers) 834 81.1% 194 18.9%
Council Wide Total 3940 73.4% 1431 26.6% 
The sex profile remains consistent with 73.4% of the workforce female and 26.6% male. There are no significant changes across
the workforce with female predominance in Education and HSCP and male predominance in Roads and Neighbourhood and
Housing & Employability. 
Page 265

Page 266

Official
7. Age Profile 
Table 7.1 
16-19 20-24 25-29 30-34 35-39 40-44 45-49 50-54 55-59 60-64 65+
Citizen Culture & Facilities 1.1% 2.7% 4.2% 8.2% 12.4% 13.4% 11.0% 9.0% 13.8% 17.1% 7.1%
Education 0.5% 3.5% 5.7% 7.4% 5.7% 11.1% 13.6% 12.4% 19.6% 14.1% 6.4%
Housing 0.9% 3.4% 5.5% 9.1% 10.5% 12.7% 12.5% 12.1% 15.4% 13.3% 4.6%
People & Technology 0.9% 3.4% 5.5% 9.1% 10.5% 12.7% 12.5% 12.1% 15.4% 13.3% 4.6%
Regulatory & Regeneration 0.0% 1.2% 8.0% 8.8% 12.7% 15.9% 11.2% 14.7% 13.9% 9.2% 4.4%
Resources 0.1% 2.4% 3.7% 8.4% 11.4% 8.7% 9.4% 12.0% 19.2% 18.2% 6.5%
Roads & Neighbourhood 0.0% 0.0% 0.0% 16.7% 0.0% 0.0% 16.7% 33.3% 16.7% 16.7% 0.0%
Chief Exec Office 0.9% 3.4% 5.5% 9.1% 10.5% 12.7% 12.5% 12.1% 15.4% 13.3% 4.6%
Child Health Care & Criminal Justice 0.0% 1.2% 8.0% 8.8% 12.7% 15.9% 11.2% 14.7% 13.9% 9.2% 4.4%
Community Health & Care 0.1% 2.4% 3.7% 8.4% 11.4% 8.7% 9.4% 12.0% 19.2% 18.2% 6.5%
Finance & Resources 0.0% 0.0% 0.0% 16.7% 0.0% 0.0% 16.7% 33.3% 16.7% 16.7% 0.0%
Mental Health Addiction & Learning
Disabilities 0.0% 0.9% 4.3% 9.6% 9.6% 13.9% 8.7% 21.7% 16.5% 12.2% 2.6%
Strategy, Planning & Health Improvement 0.0% 0.0% 0.0% 3.4% 10.3% 13.8% 27.6% 13.8% 10.3% 13.8% 6.9%
Health & Social Care Partnership 0.1% 2.0% 4.5% 8.5% 11.4% 10.7% 10.1% 13.6% 17.7% 15.8% 5.7%
Strategic Management 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 8.3% 50.0% 16.7% 25.0% 0.0%
Local Government Employees Total 0.7% 3.0% 5.2% 8.9% 10.7% 12.0% 11.8% 12.6% 16.1% 14.0% 4.9%
Education (Teachers) 0.0% 2.4% 9.3% 16.5% 16.3% 16.1% 15.5% 9.9% 9.6% 2.5% 1.7%
Council Wide Total 0.5% 2.9% 6.0% 10.4% 11.8% 12.8% 12.5% 12.1% 14.8% 11.8% 4.3%  
The distribution curve for the age demographic across the council remains consistent with previous years. The highest proportion of
people are in the 55-59 age group, with age groups 60-64, 50-54 and then 40-44, being the next age groups with the highest
proportion. This has changed slightly as there the number of 60-64 year old’s percentage has increased into the top 3 highest
percentages although the percentage has remained the same other age groups have more lost headcount.   The percentage of
employees working past 65 across the council has remained consistent since the previous period at 4.3% compared to 4.6% last
year. 
Page 266

Page 267

Official
8. Length of Service 
Table 8.1 
Less than 1 year 1 to 9 years 10 or more years 
Headcount Percentage Headcount Percentage Headcount Percentage
Citizen Culture & Facilities 61 9.8% 292 47.0% 268 43.2%
Education 73 7.1% 522 50.9% 430 42.0%
Housing 14 2.6% 222 41.2% 303 56.2%
People & Technology 9 4.6% 94 47.7% 94 47.7%
Regulatory & Regeneration 10 9.1% 44 40.0% 56 50.9%
Resources 6 3.6% 41 24.4% 121 72.0%
Roads & Neighbourhood 24 5.9% 176 43.6% 204 50.5%
Chief Exec Office 197 6.4% 1391 45.4% 1476 48.2%
Child Health Care & Criminal Justice 27 10.8% 99 39.4% 125 49.8%
Community Health & Care 43 5.0% 457 52.8% 366 42.3%
Finance & Resources 0 0.0% 1 16.7% 5 83.3%
Mental Health Addiction & Learning Disabilities 7 6.1% 41 35.7% 67 58.3%
Strategy, Planning & Health Improvement 0 0.0% 10 34.5% 19 65.5%
Health & Social Care Partnership 77 6.1% 608 48.0% 582 45.9%
Strategic Management 1 8.3% 6 50.0% 5 41.7%
Local Government Employees Total 275 6.3% 2005 46.2% 2063 47.5%
Education (Teachers) 66 6.4% 411 40.0% 551 53.6%
Council Wide Total 341 6.3% 2416 45.0% 2614 48.7% 
The distribution of Length of service has remained consistent, with the highest percentage remaining within 10 years or more. 
*Above data pertains to West Dunbartonshire Council service only (excluding continuous service with any other public authority to
which the redundancy Payments Modification Order (Local Government) 1983 (as amended applies). 
Page 267

Page 268

Official 
9. New Starts 
Table 9.1 
Apprentice Fixed-Term Permanent Total
Citizen Culture & Facilities 0 5 56 61
Education 2 50 21 73
Housing 4 2 8 14
People & Technology 0 5 4 9
Regulatory & Regeneration 0 2 8 10
Resources 0 1 5 6
Roads & Neighbourhood 0 3 21 24
Chief Exec Office 6 68 123 197
Child Health Care & Criminal Justice 0 7 20 27
Community Health & Care 0 9 34 43
Finance & Resources 0 0 0 0
Mental Health Addiction & Learning Disabilities 0 3 4 7
Strategy, Planning & Health Improvement 0 0 0 0
Health & Social Care Partnership 0 19 58 77
Strategic Management 0 0 1 1
Local Government Employees Total 6.0 87.0 182.0 275
Education (Teachers) 0 51 15 66
Council Wide Total 6 138 197 341 
341 new employees joined the council in 2025/26 which is a decrease of 58 from last year. The table above shows this information
by service and contract type. 
Page 268

Page 269

Official
10. Turnover 
Table 10.1 
Staff at 1
April 2025
Staff at 1
April 2026 Average
Leavers in
Last 12
Months
Turnover %
Citizen Culture & Facilities 638 621 630 217 34.5%
Education 1049 1025 1037 178 17.2%
Housing 567 539 553 46 8.3%
People & Technology 211 197 204 18 8.8%
Regulatory & Regeneration 109 110 110 11 10.0%
Resources 170 168 169 15 8.9%
Roads & Neighbourhood 431 404 418 56 13.4%
Chief Exec Office 3175 3064 3120 541 17.3%
Child Health Care & Criminal Justice 252 251 252 33 13.1%
Community Health & Care 956 866 911 149 16.4%
Finance & Resources 6 6 6 1 16.7%
Mental Health Addiction & Learning Disabilities 130 115 123 17 13.9%
Strategy, Planning & Health Improvement 34 29 32 5 15.9%
Health & Social Care Partnership 1378 1267 1323 205 15.5%
Strategic Management 12 12 12 1 8.3%
Local Government Employees Total 4565 4343 4454 747 16.8%
Education (Teachers) 1026 1028 1027 114 11.1%
Council Wide Total 5591 5371 5481 861 15.7% 
The information above presents an increase in turnover of 3.5% since the previous period. The leaver’s information in section 11
outlines that the vast majority of leavers remain as resignations and age retirals. 
Page 269

Page 270

Official 
11. Leavers 
The numbers of leavers has increased in 2026 by 233 in comparison to 2025’s 688 leavers. 2026 has seen an increase in
comparison to other previous years of 855 employees leaving in 2023, 795 in 2022, 490 in 2021, and 457 in 2020. 
This section will also detail employees who have accepted Early Retirement – Efficiencies / Redundancy, Flexible Retirement and
Retirement between 55 – 59 years of age during the reporting period. It also notes the employees who have been added to the
SWITCH Register. 
Table 11.1 Leavers 
Death in Service
Dismissal - End of Cont
Dismissal - Ill Heath
Dismissal - Summary
Dismissal - W
ith Notice
Employee Not Started
Incorrect Entry
MPO
to Main
Redundancy
Resignation
Retiral - Age
Retiral - Efficiency
Retiral - Ill Health
Retiral on Option (60+)
Severance - Efficiency
Teacher - End Fixed
Term
Teacher - Ill Health
Teacher - Other
Teacher - Retirement
Age
Teacher - Retirement
Oth
Teacher - Vol Resign
Oth
TUPE
Transfer
Unused Casual
Total
Citizen Culture &
Facilities * * 6 0 * * 0 71 6 88 19 0 6 * 6 0 0 0 0 0 0 0 6 217
Education * 13 * 0 * * * 9 0 97 27 0 * * * * 0 0 * 0 0 0 9 178
Housing 0 * * * 0 0 0 0 * 22 10 0 * * 0 0 0 0 0 0 0 * * 46
People & Technology * * 0 0 0 0 0 * 0 7 * * 0 * 0 0 0 0 0 0 0 0 0 18
Regulatory &
Regeneration 0 * 0 0 0 * 0 0 * 6 * * 0 0 0 0 0 0 0 0 0 0 0 11
Resources 0 0 0 0 0 0 0 0 * 7 * * 0 * * 0 0 0 0 0 0 0 0 15
Roads & Neighbourhood * 6 * 0 0 0 0 * 5 12 17 * 0 * 7 0 0 0 0 0 0 0 0 56
Chief Exec Office 5 26 11 * 5 * * 82 16 239 80 9 13 11 16 * 0 0 * 0 0 * 18 541
Child Health Care &
Criminal Justice 0 0 * 0 0 * 0 0 0 22 6 0 * * 0 0 0 0 0 0 0 0 * 33
Community Health &
Care 0 0 14 * * * 0 * 7 63 32 0 9 8 0 0 0 0 0 0 0 0 9 149
Finance & Resources 0 0 0 0 0 0 0 0 0 * 0 0 0 0 0 0 0 0 0 0 0 0 0 *
Page 270

Page 271

Official
Mental Health Addiction
& Learning Disabilities 0 0 0 * * 0 0 0 * 6 * * 0 * * 0 0 0 0 0 0 0 * 17
Strategy, Planning &
Health Improvement 0 0 0 0 0 0 0 0 0 * * 0 0 * 0 0 0 0 0 0 0 0 0 5
Health & Social Care
Partnership 0 0 15 * * * 0 * 9 94 41 * 10 12 * 0 0 0 0 0 0 0 11 205
Strategic Management 0 0 0 0 0 0 0 0 0 0 0 0 0 1 0 0 0 0 0 0 0 0 0 *
Local Government
Employees Total 5 26 26 * 9 6 * 83 25 333 121 11 23 24 17 * 0 0 * 0 0 * 29 747
Education (Teachers) 0 0 0 0 0 0 0 0 0 * * 0 0 * * 53 0 * 22 7 25 0 0 114
Council Wide Total 5 26 26 * 9 6 * 83 25 334 123 11 23 26 18 55 0 * 23 7 25 * 29 861 
* Figures of under 5 have been removed and replaced with a * due to the possible identification of individuals. 
Table 11.2 Retirements 55-59 
55-59 01/04 - 30/09 01/10 - 31/03 Annual Council Wide Total
31/03/2022 0 5 5
31/03/2023 6 4 10
31/03/2024 10 3 13
31/03/2025 8 8 16
31/03/2026 3 6 9 
The Local Government Pension Scheme allows scheme members to retire from age 55 without employer consent. The terms of
this provision allow members to access their pension benefits with an actuarial reduction applied (to compensate the fund for the
member taking their benefits early) with no consequential costs for the council. There has been a decrease in the number of
employees retiring and accessing their pension benefits compared to the previous 3 years. 
Page 271

Page 272

Official
Table 11.3 Flexible Retirement 
Flexible 01/04 - 30/09 01/10 - 31/03 Annual Council Wide Total
31/03/2022 10 28 38
31/03/2023 19 26 45
31/03/2024 23 39 62
31/03/2025 26 12 38
31/03/2026 26 5 31 
Flexible retirement is available to members of the Local Government Pension Scheme, excluding teachers. The approval of those
employees granted flexible retirement is monitored by the Chief Officer, People and Technology, and the Chief Officer, Resources. 
Every effort is being made to support flexible retirement requests where possible, and services regularly revisit applications with a
view to release. 
Table 11.3 above shows the number of flexible retirements released in the period for this year and four previous reporting periods
for comparison purposes. There has been a decrease this year for flexible retirement with this year’s figure showing the lowest
figure since pre-2022. While flexible retirement requests that result in a strain on the fund will not normally be granted,
consideration will be given to cases where these costs can be mitigated or where exceptional circumstances exist. 
It is anticipated that Flexible Retirement will continue to be a popular option for employees who wish to work in a reduced capacity
and access their pension whilst enabling the Council to retain their skills and experience, however the trend of a reduction in those
released may continue due to the costs associated. 
12.  SWITCH (Redeployment) 
Redeployment is monitored and delivered centrally by Strategic HR. Employees are added to the SWITCH register for a number of
different reasons:- 
• Through organisational change employees may be displaced, at risk of redundancy or placed in lower graded posts;
• Due to ill-health, they may become unable to continue in their substantive post;
• Through Job Evaluation where a post is evaluated lower than the current grade;
• Or where an employee is coming to the end of a fixed term contract and has more than 2 years’ service.   
To support employees to return to their previous rate of pay all employees who have been matched but remain on pay protection
are also retained on the register. 
Page 272

Page 273

Official
Table 12.1 below details the number of employees who were on the redeployment register at the start of the reporting period
(01/04/2025), the number who joined the register in the 6 months up to 30/09/2025 and 31/03/2026 and the number who remain on
the register at the end of the reporting period (31/03/2026).   
Table 12.1 SWITCH 
Reason
Number of
employees
on the
Register at
the start of
the period
(01/04/2025)
Number of
employees
added during
the period
Number of
employees
removed
during the
period
Number of
Employees
on the
register at
the end of the
period
(30/09/2025)
Number of
employees
added during
the period
Number of
employees
removed
during the
period
Number of
Employees
on the
register at
the end of
the period
(31/03/2026)
Ill Health (Capability) 3 2 1 4 3 2 5
Ill health (Disability) 0 1 0 1 0 1 0
Organisational Change 5 23 8 20 19 18 21
Other Process (FTA
end, Job Evaluation,
Performance) 2 0 1 1 0 0 1
TOTALS 10 26 10 26 22 21 27         
Pay Protection 2 1 1 2 0 1 1 
There has been a significant increase in the number of employees being added to the Redeployment (SWITCH) Register between
1st April 2025 and 31st March 2026 and from 2024/5. Discussions continues to be  held  in relation to the benefits of SWITCH and
within consultations for service re-designs. The Council holds a duty of care towards individuals and they will be automatically listed
on SWITCH going forward where their roles are at risk. 
Page 273

Page 274

Official 
13. Apprentices 
Table 13.1 
Level 2 Level 3 Total
Citizen Culture & Facilities 0 0 0
Education 0 4 4
Housing 0 34 34
People & Technology 0 1 1
Regulatory & Regeneration 0 0 0
Resources 0 0 0
Roads & Neighbourhood 0 10 10
Chief Exec Office 0 49 49
Child Health Care & Criminal Justice 0 0 0
Community Health & Care 0 0 0
Finance & Resources 0 0 0
Mental Health Addiction & Learning Disabilities 0 0 0
Strategy, Planning & Health Improvement 0 0 0
Health & Social Care Partnership 0 0 0
Strategic Management 0 0 0
Local Government Employees Total 0 49 49
Education (Teachers) 0 0 0
Council Wide Total 0 49 49 
The number of apprenticeships supported by the council in Level 2 and Level 3 has decreased by 10. A reduction has been seen
across Education, Housing and Roads & Neighbourhood. There are currently no level 2 apprentices across any service areas. 
Page 274

Page 275

Official
14. Sickness Absence 
From 1st April 2025 to 31st March 2026, there was a decrease in Council wide sickness absence to 65224.13 FTE days lost
compared to 66814.70 in 2024/25 with 14.53 FTE workdays lost per employee being reported, an increase from 14.3 in 2024/25.
The highest absence still remains in the front-line employee service areas. Implementation of employee engagement and wellbeing
practices continue and hope to bring improvements for future periods. 
Table 14.1 Annual Absence for Council 
The table above illustrates the reasons for absence distribution across the year and Minor Illness is the highest category of
absence followed by personal stress and acute medical conditions which were the same 3 highest categories in 2024/25. Full
details and analysis of sickness absence is covered in the wellbeing report submitted to committee. 
Page 275

Page 276

Official
Table 14.2 Reasons for Absence 
Absence Reason Working Days Lost Percentage of Lost Days
Minor Illness 23,334.4 21%
Back Pain 4,840.7 4%
Musculo-skeletal Injuries 13,180.3 12%
Stress Personal 20,295.8 19%
Recur Medical Condition 4,930.7 5%
Injury/Accident (Non Work) 2,639.1 2%
Injury/Accident (Work) 2,366.6 2%
Mental Health 9,508.3 9%
Acute Medical Conditions 17,628.0 16%
Pregnancy Related 2,106.4 2%
Drink/Drug Related 229.6 0%
Stress - Work Related 6,816.9 6%
Long Covid 790.0 1%
TOTAL 108,666.8 100% 
The table above illustrates the reasons for absence and the number and percentage of the total days lost during 2025/26. Minor
Illness continues to be the reason for absence with the highest number of days followed Acute Medical Conditions and Personal
Stress. This reflects the same pattern as 2024/25. 
Page 276

Page 277

Official
Voluntary Severance/Voluntary Early Retirement 
VS/VER was one offering available to employees to reduce the workforce as agreed in the budget setting process for 2025/26. 
Table 15.1 - Notes of Interest 
Service  No of Note of Interest Received 
Citizen Culture Facilities  39
Education Learning & Attain  6
Housing 5
HSCP  8
People & Technology  2
Regulatory & Regeneration  1
Resources  3
Roads & Neighbourhood  5
TOTAL  69 
In total, there were 69 notes of interest submitted during the period 2025/26. This is a significant decrease from the previous year
where 452 notes of interest were submitted. Table 15.1 provides a breakdown by Service. Not all notes of interest progressed to
offer stage for several reasons, including eligibility criteria not met, interest withdrawn, or an oversubscription in a particular area. 
Table 15.2 Voluntary Early Retirement and Voluntary Severance (VS/VER - Efficiency/Redundancy) by Year 
VS/VER 01/04 - 30/09 01/10 - 31/03 Annual Council Wide Total
31/03/2022 0 0 0
31/03/2023 0 9 9
31/03/2024 46 2 48
31/03/2025 13 16 29
31/03/2026 16 18 34 
There had been a slight increase in employees being released through VER/VS since March 2025 in line with budget savings
required for 2025/26. 
Page 277

Page 278

Official
Table 15.3 - Released via VS/VER: 1 April 2025 – 31 March 2026 by Service 
Service 
No of
Employees 
No of
FTE 
Citizen Culture Facilities  11 7.4
Education Learning &
Attainment  2 1.9
Housing  1 1
HSCP 10 5.2
People & Technology  2 2
Regulatory & Regeneration  1 1
Resources  0 0
Roads & Neighbourhood  7 3.7 
Total  34 22.2 
During the period, a total of 34 employees were granted early retirement on grounds of efficiency of the service, redundancy or
released on voluntary severance as shown in table 15.3 above and 15.4 below. 
Table 15. 4 – Voluntary Early Retirement/Severance (1st April 2025 – 31st March 2026) 
In line with data protection requirements, the table above shows the data consolidated as a council wide figure which includes
employees in the Health & Social Care Partnership. 
* Net savings take account of annual costs. 
* One-off costs include provisional capitalisation (strain on the fund) costs. 
Council wide No. of EE’s *One-Off Costs  Annual Costs
(Recurring)
Net Annual
Savings 
(Recurring)  
TOTALS* 34 £811,316.61 £6,558.26 £705,466.78
Page 278

Page 279

Official
In respect of the 35 employees released, 18 were granted early retirement on efficiency or redundancy grounds and 17 were
granted voluntary severance.  The number of employees being released through voluntary early retirement/severance has
increased from the previous year as detailed in table 15.4 above. 
The reductions achieved have contributed approximately £705,000 towards on-going savings with initial one-off costs of
approximately £811,000. Applications are still in the process of being considered in-line with service re-designs where appropriate. 
Page 279

Page 280

Page 280

Page 281

Official
WEST DUNBARTONSHIRE COUNCIL 
Report by Chief Officer - Resources 
Corporate Services Committee: 27 May 2026
Subject: Provision of a Cash Receipting System
1. Purpose
1.1 The purpose of this report is to seek approval of Committee to commence
the tendering process for the Provision of a Cash Receipting System for the
period 1 April 2027 to 31 March 2029, with an option to extend for a further
two additional 12 month periods  to 31 March 2031 for West Dunbartonshire
Council (“the Council”).
2. Recommendations
2.1 It is recommended that the Committee approves the process to begin
invitations to tender for the Provision of a Cash Receipting System for a two
year period from 1 April 2027 until 31 March 2029, with an option to extend
for a further two additional 12 months until 31 March 2031 
2.2 To delegate authority to the Chief Officer: Regulatory and Regeneration to
conclude, on behalf of the Council, the award of the contract for the
Provision of a Cash Receipting System subject to the Chief Officer
Resources being satisfied as to the terms offered.
3. Background
3.1 The cash receipting system provides citizens of West Dunbartonshire
Council with the facility to make payments either face to face, online or by
telephone. In addition to this the service provides the facility to manage all of
the Council’s income and to accurately record payments received to the
Council’s back office systems e.g. Council Tax, Rents, etc. This system is a
key control system for The Council.
3.2 Following a tendering exercise in 2023 Capita Business Services Ltd
continued to be the Council Provider of a Cash Receipting System for a
period of 2 years from 1 September 2023 to 31 August 2025 with an option
to extend for a further two 12 months until 31 August 2027.
3.3 The current contract was varied after a review of the terms offered by the
Council’s current provider for the extension period and it was agreed that an
extension to 31 March 2027 be accepted by the Chief Officer-Resources
under delegated authority.
ITEM 14
Page 281

Page 282

Official
4. Main Issues
4.1 The Provision of a Cash Receipting System is critical to the continued
financial stability of the Council and is required to collect income from and
make payments to various stakeholders.
4.2 It is essential that the procurement process is carried out well in advance of
the expiry date of the current contract to ensure a seamless process of
continuation of the service in the event that a new contractor is identified.
4.3 A tender exercise ensures that we secure the best price for the Council.
5. People Implications
5.1 There are no people implications.
6. Financial and Procurement Implications
6.1 The Council currently incurs costs of around £55,000 per year in respect of
the Provision of a Cash Receipting System for services provided by our
existing provider.
6.2 The selection of the most suitable provider of the Provision of a Cash
receipting System may result in increased efficiencies in relation to day-to-day
activities.
6.3 All procurement activity carried out by the Council in excess of £50K is
subject to a contract strategy. The contract strategy for the provision of a
Cash Receipting System services will be produced by the Corporate
Procurement Unit in close consultation with Finance Officers. The contract
strategy shall include but may not be limited to; contract scope, service
forward plan, the market, procurement model and routes – including existing
delivery vehicles, roles and responsibilities, risks, issues and opportunities
and ongoing contract management.
7. Risk Analysis
7.1 If the contract is not tendered the existing providers will be able to provide
the service. However, the prices may be subject to fluctuation and may no
longer be competitive. Having a contract in place enables the prices to be set
for a fixed period and a formal terms and conditions to be put in place, to
ensure that the Council receives best value.
7.2 There is the risk that if the Provision of a Cash Receipting System
Contract is not awarded the Council will be unable to fulfil its financial
obligations to various stakeholders.
Page 282

Page 283

Official
8. Equalities Impact Assessment (EIA)
8.1 No issues were identified in a screening for potential equality impact of
this report.
9. Consultation
9.1 The report has been subject to consultation with appropriate Strategic Leads. 
10. Strategic Assessment
10.1  Sound financial practice and budgetary control are imperative to assist with
the governance of the Council and supports officers of the Council in
achieving the five strategic priorities. The General Services revenue budget
contributes to all categories by providing funding in specific areas to help the
Council achieve and develop these priorities.
10.2  The provision of a Cash Receipting System will contribute to delivery of the
Council strategic priorities through efficient and effective frontline services
that improve the everyday lives of residents. Further opportunities to
maximise the positive social, economical and environmental impact for West
Dunbartonshire through the contract will also be explored, e.g. through the
use of Community Benefit Clauses
Laurence Slavin
Chief Officer-Resources
Date: 22 April 2026 
Person to Contact: Karen Shannon, Section Head (Financial, Administration
& Control)
Church Street, Dumbarton Telephone 07584 475469
Email: Karen.Shannon@west-dunbarton.gov.uk 
Appendices: Equality Impact Assessment 
Background Papers: None
Wards Affected: All Council Wards 
Page 283

Page 284

Assessment No 1494
Strategic Team RES
Lead Officer Karen Shannon
Who else has been
involved in developing
this EIA
Karen Shannon-Section Head/Business Partner
Carol Alderson-Finance Manager
Ric Rea-Performance & Strategy officer 
Title Provision of a Cash Receipting System
Description: (Provide a
brief overview of the
aims and objectives of
this policy)
The cash receipting system provides citizens of West
Dunbartonshire Council with the facility to make payments
either face to face, online or by telephone. In addition to this
the service provides the facility to manage all the Council’s
income and to accurately record payments received to the
Council’s back-office systems e.g. Council Tax, Rents, etc.
This system is a key control system for The Council.
Who have you
engaged and consulted
with as part of your
Finance, Procurement, Legal
Who will be affected by
this proposal?
All individuals, organisations that make payments to the
Council or receive payments from the Council. All internal
users of the system. This is a continuation of an existing
service, but the provider is unknown at this time. 
Does the proposals involve the procurement of any goods or services? Yes
If yes, please confirm that you have contacted our procurement services to
discuss your requirements and viewed the guidance
Yes 
Relevance screening: If the proposal/policy is relevant to any of the six areas then an
Equality Impact Assessment must be carried out.
You must indicate if there is any relevance to the six areas 
Duty to eliminate discrimination (E), advance equal opportunities (A) or
foster good relations (F)
Yes
Relevance to Human Rights (HR) Human Rights Act/European Convention
on Human Rights
No
Relevance to Health Impacts (H) No
Relevance to United Nations Convention on the Rights of the Child
(UNCRC)
No
Relevance to Social Economic Impacts (SE) or Fairer Scotland Duty (FSD) Yes
Relevance to Scottish Consumer Duty (SCD) No 
ITEM 14 - APPENDIX 1
Page 284

Page 285

Consider any needs and policy drivers e.g. Council or national strategies and
plans /and any barriers which equality groups may have in relation to this
policy. 
List evidence you are using to support this assessment. 
Consider the impact of your policy on people and how they will be able to
access goods, services and information with no barriers and state the potential
impact. 
Specific group to
consider
What Key Drivers and
Evidence has been used to
inform this assessment. (i.e.
national statistics - Scot Govt; or
local statistics - workforce data,
Citizens Panel)
For each group, state the
potential Impact –
Positive/Negative/Neutral
Age                                                                                                  No evidence of any differential
impact
Neutral
Disability                                                                                           Systems used by the public need
to be accessible to disabled
people, this will remain at the
same level
Neutral
Gender Reassign                                                                                      No evidence of any differential
impact
Neutral
Marriage & Civil
Partnership                                                                        
No evidence of any differential
impact
Neutral
Pregnancy &
Maternity                                                                               
No evidence of any differential
impact
Neutral
Race                                                                                                 No evidence of any differential
impact
Neutral
Religion and
Belief                                                                                 
No evidence of any differential
impact
Neutral
Sex                                                                                                  No evidence of any differential
impact
Neutral
Sexual
Orientation                                                                                  
No evidence of any differential
impact
Neutral 
This section must be completed if there are potential Human Rights impacts,
this includes but is not limited to Human Rights Act 1998 considerations 
Human Rights                                                                                         No evidence of any differential
impact
Neutral             
Page 285

Page 286

This section must be completed if any there are any potential socio-economic
impacts including but not limited to those covered by the Fairer Scotland Duty 
Social &
Economic
Impact                                                                            
Need to have due regard to the
Fairer Scotland Duty.
Possibilities for communities
benefits are examined during
procurement processes, these will
be required of the successful
contractor based on the value of
the contract works but are
determined later in the process
based on the capabilities of the
individual contractor.
Likely to be neutral in terms of
significant impacts.           
This section must be completed if any potential impact on children and young
people up to the age of 18 
United Nations
Convention on
the Rights of the
Child                                                
No evidence of any differential
impact
Neutral 
This section must be completed in reference to the Scottish Consumer Duty 
Scottish
Consumer Duty                                                                              
We have examined the
proposals for any possible harm
to consumers. Re-provisioning
will ensure continuation of
services to people and
businesses. 
Neutral 
Consider cumulative impact of the proposal 
Cumulative and
intersectional
impacts                                                               
No evidence of any cumulative
differential impact
Neutral 
Page 286

Page 287

State how the impact of the proposal/policy be monitored and reported on an ongoing
basis including how actions will be delivered to mitigate any negative impacts or
secure positive impacts. 
Summary of overall impact(s) of the proposal.
EIA 1494: Possibilities for communities benefits are examined during procurement
processes, these will be required of the successful contractor. Given the size and type
of contract, it is likely to be neutral in terms of socio-economic significant impacts. 
Name of the senior manager who has approved this assessment
Laurence Slavin 
Page 287

Page 288

Page 288

Page 289

WEST DUNBARTONSHIRE COUNCIL 
Report by Chief Officer - Resources
Corporate Services Committee: 27 May 2026 
Subject: Corporate Services Revenue – Budgetary Control Report to 31st 
January 2026 (Period 10) 
1. Purpose 
1.1 This report provides an update on the revenue financial performance to 31
January 2026 of those services under the auspices of the Corporate
Services Committee (CSC). 
2. Recommendations 
2.1 Members are asked to: 
i) Note the contents of this report which show the revenue account is
currently projected to underspend against budget by £0.607m (1.51%
of the total budget) at the year-end. 
3. Background 
3.1 The revised 2025/26 revenue budget presented to Committee in January
was £40.229m.  Since then, changes worth £0.002m have been agreed to
the budget which revises the 2025/26 budget as follows: 
£m
Revised budget as at Period 7 40.229
Minor budget movements between committees. 0.002
Revised budget as at Period 10 40.231 
4. Main Issues 
Service Delivery Position (£0.607m Favourable) 
4.1 The summary report at Appendix 1 highlights a projected favourable variance
(underspend) against Corporate Services of £0.607m (1.51% of the total
budget).  Appendix 2 provides more detailed service reports by Chief Officer.
The main reason for the movement in the outturn from Period 7 is detailed in
the table below with explanations for the underspend provided in Appendix 3.    
4.2 Information on any projected annual variances in excess of £0.050m are
highlighted and noted within Appendix 3, with additional information on action
being taken to minimise or mitigate overspends where possible. 
ITEM 15
Page 289

Page 290

£m £m
Variance at Period 7  (0.138)
Movement in Variance  
Resources:
• Audit- favourable variance due to vacancies
• Finance- favourable movement in employee
costs due to vacancies and a reduction in
computer software charges
• Cost of Collection Rate & Council Tax –
increase income from Statutory Additions
• Office Accommodation- increase in income
from charges to users  
(0.073)
(0.062) 
(0.189) 
(0.056) 
(0.380)
Regulatory and Regeneration: 
• Planning – reduction in employee costs due to
vacancies and an increase in income received
• Other service movement less than £50k 
(0.065) 
(0.005)  (0.070)
People & Technology: 
• Other service movements less than £50k      (0.050)  (0.050)
Citizens, Culture and Facilities: 
• Other service movements less than £50k    0.031  0.031
Period 10 underlying favourable variance     (0.607) 
Earmarked Reserve Position 
4.3 Services are anticipating the use of £0.737m (Period 7: £0.891m) of
earmarked reserves. This is a reduction in planned spend of £0.154m in
2025/26, resulting in an increased carry forward to be used mainly to support
local foodbanks as approved at Council 5 March 2026. Information on the
earmarked reserve spend is shown in Appendix 4. 
Monitoring of Efficiencies 
4.4 A list of agreed efficiencies and management adjustments totalling £1.527m is
shown within Appendix 5.  Current indications show that £1.377m is on target
to be achieved. 
5. Option Appraisal 
5.1 No option appraisal was required for this report. 
6. People Implications 
6.1 There are no people implications. 
7. Financial and Procurement Implications 
7.1 Other than the financial position noted above, there are no financial or
procurement implications from this budgetary control report. 
Page 290

Page 291

8. Risk Analysis 
8.1 The main risks are as follows: 
The present variances should be viewed in the knowledge that there are a
number of variable factors which could arise between now and 31 March
which could affect the year end. 
9. Equalities Impact Assessment (EIA) 
9.1 No equalities impact assessment was required in relation to this report. 
10. Environmental Sustainability 
10.1 No assessment of environmental sustainability was required in relation to this
report. 
11. Consultation 
11.1 All services involved in delivering the revenue budgets have been consulted in
the compilation of this report. 
12. Strategic Assessment 
12.1 Proper budgetary control and sound financial practice are cornerstones of
good governance and support Council and officers to pursue the strategic
priorities of the Council’s current Strategic Plan. This report forms part of the
financial governance of the Council. 
__________________
Laurence Slavin
Chief Officer – Resources
Date: 27 May 2026
__________________________________________________________________
Person to Contact: Carol Alderson. Finance Manager 
Council Offices, Church Street, Dumbarton  
E-mail: carol.alderson@west-dunbarton.gov.uk 
Appendices: Appendix 1 - Revenue Budgetary Control 2025/26 
– Corporate Summary; 
Appendix 2 -  Revenue Budgetary Control 2025/26
– Service Summaries;
Appendix 3 - Analysis of Revenue Variances over 
£50,000; 
Appendix 4 -  Earmarked Balances
Appendix 5 -  Monitoring of Efficiencies 
Page 291

Page 292

Background Papers: 
• Ledger output – Period 10
• General Services Revenue Estimates 2025/26   
Wards Affected           All Wards 
Page 292

Page 293

REVENUE BUDGETARY CONTROL 2025/26
CORPORATE SERVICES SUMMARY
PERIOD END DATE 31 January 2026
Total Budget
2025/26
Spend to Date
2025/26
Forecast
Spend 2025/26
Net Variance
attributable to
earmarked
reserves spend
Underlying
Variance
excluding
earmarked
reserves
spend
Annual
RAG
Status
£000 £000 £000 £000 % £000 £000
Audit 291 174 219 (72) -25% 0 (72) 
Finance 1,538 1,278 1,540 3 0% 32 (29) 
Rent Rebates & Allowances 2,201 2,672 2,201 0 0% 0 0 
Revenues & Benefits 2,424 2,399 2,899 475 20% 427 48 
Finance Service Centre 437 345 450 13 3% 0 13 
Cost of Collection of Rates (29) 0 (64) (36) 124% 0 (36) 
Cost of Collection of Council Tax (1,072) (239) (1,228) (156) -15% 0 (156) 
Central Admin Support 2,602 2,115 2,510 (91) -4% 0 (91) 
Procurement 605 588 612 7 1% 0 7 
Democratic and Registration Service 1,609 1,309 1,577 (32) -2% 0 (32) 
Environmental Health 575 385 507 (67) -12% 0 (67) 
Licensing (221) (214) (231) (10) -4% 0 (10) 
Legal Services/Trading Standards 885 705 862 (23) -3% 0 (23) 
Planning 557 439 504 (53) -10% 52 (105) 
Transactional Services 902 780 926 25 3% 0 25 
Strategic People and Change 1,863 1,536 1,878 15 1% 6 9 
Information Services 5,093 5,115 5,055 (38) -1% 0 (38) 
Legal Fees & Settlement 0 9 9 9 0% 9 (0) 
Communications & Marketing 277 253 299 21 8% 16 5 
Citizen Services 1,386 1,082 1,349 (37) -3% 0 (37) 
Performance & Strategy 241 191 229 (12) -5% 0 (12) 
Clydebank Town Hall 339 246 292 (46) -14% 0 (46) 
Office Accomodation 1,195 1,630 1,244 49 4% 0 49 
Libraries 1,833 1,489 1,794 (39) -2% 0 (39) 
Arts and Heritage 306 158 212 (94) -31% 0 (94) 
Catering Services 5,095 4,906 5,469 374 7% 0 374 
Building Cleaning 2,128 1,798 2,105 (23) -1% 0 (23) 
Building Cleaning PPP (95) (299) (120) (25) 27% 0 (25) 
Facilities Assistants 2,739 2,086 2,545 (194) -7% 0 (194) 
Facilities Management 305 473 417 112 37% 150 (38) 
Leisure Management 4,094 4,055 4,170 76 2% 45 31 
Events 28 25 25 (3) -9% 0 (3) 
School Crossing Patrollers 99 87 103 3 3% 0 3 
40,231 37,574 40,361 130 0.32% 737 (607) Total Net Expenditure
Service / Subjective Summary Variance 2025/26
ITEM 15 - APPENDIX 1
Page 293

Page 294

WEST DUNBARTONSHIRE COUNCIL
REVENUE BUDGETARY CONTROL 2025/26
CORPORATE SERVICES COMMITTEE DETAIL
PERIOD END DATE 31 January 2026
Total Budget
2025/26 
YTD Spend
2025/26 
Forecast
Spend
2025/26
Net Variance
attributable to
earmarked
reserves spend
Underlying
Variance
excluding
earmarked
reserves spend
RAG Status
£000 £000 £000 £000 % £000 £000
Employee 32,197 26,092 31,284 (915) (3%) 6 (921) 
Property 2,280 1,914 2,349 69 3% 0 69 
Transport and Plant 3,514 3,548 3,480 (34) (1%) 0 (34) 
Supplies, Services and Admin 3,428 3,316 4,329 903 26% 520 382 
Payments to Other Bodies 37,762 25,791 37,827 64 0% 45 19 
Other 0 0 0 0 0% 150 (150) 
Gross Expenditure 79,181 60,662 79,269 87 0% 721 (633) 
Income (38,950) (23,088) (38,908) 42 0% 16 26 
Net Expenditure 40,231 37,574 40,361 130 0% 737 (607) 
£000 £000 £000 £000 % £000 £000
Employee 341 213 268 (73) (21%) 0 (73) 
Property 0 0 0 0 0% 0 0 
Transport and Plant 3 3 3 0 3% 0 0 
Supplies, Services and Admin 0 0 0 0 0% 0 0 
Payments to Other Bodies 0 0 0 0 0% 0 0 
Other 0 0 0 0 0% 0 0 
Gross Expenditure 344 216 271 (73) (21%) 0 (73) 
Income (53) (42) (52) 1 2% 0 1 
Net Expenditure 291 174 219 (72) (25%) 0 (72) 
£000 £000 £000 £000 % £000 £000
Employee 1,589 1,332 1,597 9 1% 0 9 
Property 0 0 0 0 0% 0 0 
Transport and Plant 50 (0) 11 (39) (78%) 0 (39) 
Supplies, Services and Admin 2 34 34 32 1476% 32 0 
Payments to Other Bodies 0 0 0 0 0% 0 0 
Other 0 0 0 0 0% 0 0 
Gross Expenditure 1,641 1,367 1,643 2 0% 32 (30) 
Income (103) (89) (103) 1 1% 0 1 
Net Expenditure 1,538 1,278 1,540 3 0% 32 (29) 
£000 £000 £000 £000 % £000 £000
Employee 0 0 0 0 0% 0 0 
Property 0 0 0 0 0% 0 0 
Transport and Plant 0 0 0 0 0% 0 0 
Supplies, Services and Admin 0 0 0 0 0% 0 0 
Payments to Other Bodies 32,426 20,635 32,426 0 0% 0 0 
Other 0 0 0 0 0% 0 0 
Gross Expenditure 32,426 20,635 32,426 0 0% 0 0 
Income (30,225) (17,962) (30,225) 0 0% 0 0 
Net Expenditure 2,201 2,672 2,201 0 0% 0 0 
£000 £000 £000 £000 % £000 £000
Employee 1,981 1,703 2,038 57 3% 0 57 
Property 2 1 2 0 0% 0 0 
Transport and Plant 30 13 41 11 36% 0 11 
Supplies, Services and Admin 855 1,112 1,326 472 55% 427 44 
Payments to Other Bodies 0 0 0 0 0% 0 0 
Other 0 0 0 0 0% 0 0 
Gross Expenditure 2,867 2,830 3,407 539 19% 427 112 
Income (443) (430) (508) (64) (15%) 0 (64) 
Net Expenditure 2,424 2,399 2,899 475 20% 427 48 
Service Summary Variance 2025/26
All Services
Audit
Finance
Rent Rebates & Allowances
Revenues & Benefits
ITEM 15 - APPENDIX 2
Page 294

Page 295

WEST DUNBARTONSHIRE COUNCIL APPENDIX 2
REVENUE BUDGETARY CONTROL 2025/26
CORPORATE SERVICES COMMITTEE DETAIL
PERIOD END DATE 31 January 2026
Total Budget
2025/26 
YTD Spend
2025/26 
Forecast
Spend
2025/26
Net Variance
attributable to
earmarked
reserves spend
Underlying
Variance
excluding
earmarked
reserves spend
RAG Status Service Summary Variance 2025/26
£000 £000 £000 £000 % £000 £000
Employee 407 336 404 (3) (1%) 0 (3) 
Property 0 0 0 0 0% 0 0 
Transport and Plant 49 32 65 16 33% 0 16 
Supplies, Services and Admin 42 42 45 3 7% 0 3 
Payments to Other Bodies 0 0 0 0 0% 0 0 
Other 0 0 0 0 0% 0 0 
Gross Expenditure 498 410 514 16 3% 0 16 
Income (61) (64) (64) (3) (5%) 0 (3) 
Net Expenditure 437 345 450 13 3% 0 13 
£000 £000 £000 £000 % £000 £000
Employee 0 0 0 0 0% 0 0 
Property 0 0 0 0 0% 0 0 
Transport and Plant 3 0 3 0 0% 0 0 
Supplies, Services and Admin 89 0 113 24 27% 0 24 
Payments to Other Bodies 0 0 0 0 0% 0 0 
Other 0 0 0 0 0% 0 0 
Gross Expenditure 91 0 116 24 26% 0 24 
Income (120) 0 (180) (60) (50%) 0 (60) 
Net Expenditure (29) 0 (64) (36) 124% 0 (36) 
£000 £000 £000 £000 % £000 £000
Employee 0 0 0 0 0% 0 0 
Property 0 0 0 0 0% 0 0 
Transport and Plant 44 73 81 37 84% 0 37 
Supplies, Services and Admin 30 22 30 0 0% 0 0 
Payments to Other Bodies 0 0 0 0 0% 0 0 
Other 0 0 0 0 0% 0 0 
Gross Expenditure 74 95 111 37 50% 0 37 
Income (1,146) (334) (1,339) (193) (17%) 0 (193) 
Net Expenditure (1,072) (239) (1,228) (156) 15% 0 (156) 
£000 £000 £000 £000 % £000 £000
Employee 607 514 614 7 1% 0 7 
Property 0 0 0 0 0% 0 0 
Transport and Plant 0 0 0 (0) (50%) 0 (0) 
Supplies, Services and Admin 2 2 2 (0) (4%) 0 (0) 
Payments to Other Bodies 76 76 76 0 0% 0 0 
Other 0 0 0 0 0% 0 0 
Gross Expenditure 685 592 692 7 1% 0 7 
Income (80) (4) (80) 0 0% 0 0 
Net Expenditure 605 588 612 7 1% 0 7 
£000 £000 £000 £000 % £000 £000
Employee 1,693 1,384 1,653 (39) (2%) 0 (39) 
Property 0 0 0 0 0% 0 0 
Transport and Plant 7 2 3 (4) (16%) 0 (4) 
Supplies, Services and Admin 25 25 36 11 0% 0 11 
Payments to Other Bodies 0 0 0 0 0% 0 0 
Other 0 0 0 0 0% 0 0 
Gross Expenditure 1,724 1,411 1,692 (32) (2%) 0 (32) 
Income (115) (102) (115) (0) (0%) 0 (0) 
Net Expenditure 1,609 1,309 1,577 (32) (2%) 0 (32) 
Cost of Collection of Rates
Finance Service Centre
Democratic and Registration Service
Cost of Collection of Council Tax
Procurement
Page 295

Page 296

WEST DUNBARTONSHIRE COUNCIL APPENDIX 2
REVENUE BUDGETARY CONTROL 2025/26
CORPORATE SERVICES COMMITTEE DETAIL
PERIOD END DATE 31 January 2026
Total Budget
2025/26 
YTD Spend
2025/26 
Forecast
Spend
2025/26
Net Variance
attributable to
earmarked
reserves spend
Underlying
Variance
excluding
earmarked
reserves spend
RAG Status Service Summary Variance 2025/26
£000 £000 £000 £000 % £000 £000
Employee 2,612 2,146 2,554 (59) (2%) 0 (59) 
Property 0 0 0 0 0% 0 0 
Transport and Plant 11 5 11 0 0% 0 0 
Supplies, Services and Admin 0 0 0 0 0% 0 0 
Payments to Other Bodies 0 0 0 0 0% 0 0 
Other 0 0 0 0 0% 0 0 
Gross Expenditure 2,623 2,152 2,565 (59) (2%) 0 (59) 
Income (22) (37) (54) (33) (151%) 0 (33) 
Net Expenditure 2,602 2,115 2,510 (91) (4%) 0 (91) 
£000 £000 £000 £000 % £000 £000
Employee 833 628 766 (67) (8%) 0 (67) 
Property 6 3 6 0 0% 0 0 
Transport and Plant 10 5 10 (1) (6%) 0 (1) 
Supplies, Services and Admin 22 25 30 8 37% 0 8 
Payments to Other Bodies 77 58 77 (0) (0%) 0 (0) 
Other 0 0 0 0 0% 0 0 
Gross Expenditure 949 718 889 (59) (6%) 0 (59) 
Income (374) (334) (382) (8) (2%) 0 (8) 
Net Expenditure 575 385 507 (67) (12%) 0 (67) 
£000 £000 £000 £000 % £000 £000
Employee 236 195 235 (1) (0%) 0 (1) 
Property 0 0 0 0 0% 0 0 
Transport and Plant 1 0 1 0 0% 0 0 
Supplies, Services and Admin 8 9 10 2 25% 0 2 
Payments to Other Bodies 0 0 0 0 0% 0 0 
Other 0 0 0 0 0% 0 0 
Gross Expenditure 244 204 245 1 1% 0 1 
Income (465) (418) (477) (11) (2%) 0 (11) 
Net Expenditure (221) (214) (231) (10) 4% 0 (10) 
£000 £000 £000 £000 % £000 £000
Employee 950 705 856 (94) (10%) 0 (94) 
Property 0 0 0 0 0% 0 0 
Transport and Plant 3 2 3 (0) (9%) 0 (0) 
Supplies, Services and Admin 18 41 54 35 192% 0 35 
Payments to Other Bodies 1 0 1 0 0% 0 0 
Other 0 0 0 0 0% 0 0 
Gross Expenditure 973 748 914 (59) (6%) 0 (59) 
Income (88) (43) (52) 37 41% 0 37 
Net Expenditure 885 705 862 (23) (3%) 0 (23) 
£000 £000 £000 £000 % £000 £000
Employee 1,102 878 1,054 (48) (4%) 0 (48) 
Property 0 0 0 0 0% 0 0 
Transport and Plant 2 0 1 (1) (60%) 0 (1) 
Supplies, Services and Admin 24 81 86 62 257% 52 10 
Payments to Other Bodies 173 91 149 (23) (13%) 0 (23) 
Other 0 0 0 0 0% 0 0 
Gross Expenditure 1,300 1,051 1,290 (10) (1%) 52 (62) 
Income (743) (612) (786) (43) (6%) 0 (43) 
Net Expenditure 557 439 504 (53) (10%) 52 (105) 
Legal Services/Trading Standards
Licensing
Planning
Central Admin Support
Environmental Health
Page 296

Page 297

WEST DUNBARTONSHIRE COUNCIL APPENDIX 2
REVENUE BUDGETARY CONTROL 2025/26
CORPORATE SERVICES COMMITTEE DETAIL
PERIOD END DATE 31 January 2026
Total Budget
2025/26 
YTD Spend
2025/26 
Forecast
Spend
2025/26
Net Variance
attributable to
earmarked
reserves spend
Underlying
Variance
excluding
earmarked
reserves spend
RAG Status Service Summary Variance 2025/26
£000 £000 £000 £000 % £000 £000
Employee 915 792 971 56 6% 0 56 
Property 0 0 0 0 0% 0 0 
Transport and Plant 4 2 4 0 0% 0 0 
Supplies, Services and Admin 0 0 0 0 0% 0 0 
Payments to Other Bodies 0 0 0 0 0% 0 0 
Other 0 0 0 0 0% 0 0 
Gross Expenditure 919 793 975 56 6% 0 56 
Income (17) (13) (49) (32) (184%) 0 (32) 
Net Expenditure 902 780 926 25 3% 0 25 
£000 £000 £000 £000 % £000 £000
Employee 1,628 1,366 1,618 (10) (1%) 6 (17) 
Property 1 1 1 0 0% 0 0 
Transport and Plant 8 32 20 12 156% 0 12 
Supplies, Services and Admin 280 169 270 (10) (4%) 0 (10) 
Payments to Other Bodies 0 0 0 0 0% 0 0 
Other 0 0 0 0 0% 0 0 
Gross Expenditure 1,918 1,567 1,910 (8) (0%) 6 (14) 
Income (55) (31) (32) 24 43% 0 24 
Net Expenditure 1,863 1,536 1,878 15 1% 6 9 
£000 £000 £000 £000 % £000 £000
Employee 2,459 2,017 2,411 (49) (2%) 0 (49) 
Property 2 2 2 0 4% 0 0 
Transport and Plant 3,160 3,294 3,110 (50) (2%) 0 (50) 
Supplies, Services and Admin 3 0 0 (3) (100%) 0 (3) 
Payments to Other Bodies 0 0 0 0 0% 0 0 
Other 0 0 0 0 0% 0 0 
Gross Expenditure 5,624 5,313 5,522 (101) (2%) 0 (101) 
Income (530) (198) (467) 63 12% 0 63 
Net Expenditure 5,093 5,115 5,055 (38) (1%) 0 (38) 
£000 £000 £000 £000 % £000 £000
Employee 0 0 0 0 0% 0 0 
Property 0 0 0 0 0% 0 0 
Transport and Plant 0 0 0 0 0% 0 0 
Supplies, Services and Admin 0 9 9 9 0% 9 0 
Payments to Other Bodies 0 0 0 0 0% 0 0 
Other 0 0 0 0 0% 0 0 
Gross Expenditure 0 9 9 9 0% 9 0 
Income 0 0 0 0 0% 0 0 
Net Expenditure 0 9 9 9 0% 9 0 
£000 £000 £000 £000 % £000 £000
Employee 290 243 289 (1) (1%) 0 (1) 
Property 0 0 0 0 0% 0 0 
Transport and Plant 0 0 0 (0) (100%) 0 (0) 
Supplies, Services and Admin 9 10 10 2 18% 0 2 
Payments to Other Bodies 0 0 0 0 0% 0 0 
Other 0 0 0 0 0% 0 0 
Gross Expenditure 299 253 299 (0) (0%) 0 (0) 
Income (22) 0 0 22 100% 16 6 
Net Expenditure 277 253 299 21 8% 16 5 
Transactional Services
Strategic People and Change
Information Services
Legal Fees & Settlement
Communications & Marketing
Page 297

Page 298

WEST DUNBARTONSHIRE COUNCIL APPENDIX 2
REVENUE BUDGETARY CONTROL 2025/26
CORPORATE SERVICES COMMITTEE DETAIL
PERIOD END DATE 31 January 2026
Total Budget
2025/26 
YTD Spend
2025/26 
Forecast
Spend
2025/26
Net Variance
attributable to
earmarked
reserves spend
Underlying
Variance
excluding
earmarked
reserves spend
RAG Status Service Summary Variance 2025/26
£000  £000  £000 £000 % £000 £000
Employee 1,532 1,244 1,479 (53) (3%) 0 (53) 
Property 0 0 0 0 0% 0 0 
Transport and Plant 0 0 0 (0) (100%) 0 (0) 
Supplies, Services and Admin 63 51 84 21 33% 0 21 
Payments to Other Bodies 0 0 0 0 71% 0 0 
Other 0 0 0 0 0% 0 0 
Gross Expenditure 1,595 1,296 1,563 (32) (2%) 0 (32) 
Income (209) (214) (214) (5) (2%) 0 (5) 
Net Expenditure 1,386 1,082 1,349 (37) (3%) 0 (37) 
£000  £000  £000 £000 % £000 £000
Employee 227 189 225 (2) (1%) 0 (2) 
Property 0 0 0 0 0% 0 0 
Transport and Plant 0 0 0 0 0% 0 0 
Supplies, Services and Admin 0 0 0 0 0% 0 0 
Payments to Other Bodies 14 4 7 (8) (54%) 0 (8) 
Other 0 0 0 0 0% 0 0 
Gross Expenditure 241 194 232 (9) (4%) 0 (9) 
Income 0 (3) (3) (3) 0% 0 (3) 
Net Expenditure 241 191 229 (12) (5%) 0 (12) 
£000 £000 £000 £000 % £000 £000
Employee 158 138 160 2 1% 0 2 
Property 293 223 245 (48) (17%) 0 (48) 
Transport and Plant 0 0 0 0 0% 0 0 
Supplies, Services and Admin 40 20 27 (13) (33%) 0 (13) 
Payments to Other Bodies 0 1 1 1 0% 0 1 
Other 0 0 0 0 0% 0 0 
Gross Expenditure 492 382 432 (59) (12%) 0 (59) 
Income (153) (135) (140) 13 8% 0 13 
Net Expenditure 339 246 292 (46) (14%) 0 (46) 
£000 £000 £000 £000 % £000 £000
Employee 127 101 128 1 1% 0 1 
Property 1,239 1,136 1,344 105 8% 0 105 
Transport and Plant 0 0 0 0 0% 0 0 
Supplies, Services and Admin 42 45 41 (1) (4%) 0 (1) 
Payments to Other Bodies 20 0 20 0 0% 0 0 
Other 0 0 0 0 0% 0 0 
Gross Expenditure 1,428 1,282 1,532 104 7% 0 104 
Income (233) 348 (288) (55) (24%) 0 (55) 
Net Expenditure 1,195 1,630 1,244 49 4% 0 49 
£000 £000 £000 £000 % £000 £000
Employee 1,391 1,136 1,344 (47) (3%) 0 (47) 
Property 276 210 262 (15) (5%) 0 (15) 
Transport and Plant 15 12 16 1 4% 0 1 
Supplies, Services and Admin 161 147 188 27 17% 0 27 
Payments to Other Bodies 0 6 6 6 0% 0 6 
Other 0 0 0 0 0% 0 0 
Gross Expenditure 1,844 1,510 1,815 (29) (2%) 0 (29) 
Income (11) (21) (21) (10) (91%) 0 (10) 
Net Expenditure 1,833 1,489 1,794 (39) (2%) 0 (39) 
Office Accomodation
Libraries
Clydebank Town Hall
Citizen Services
Performance & Strategy
Page 298

Page 299

WEST DUNBARTONSHIRE COUNCIL APPENDIX 2
REVENUE BUDGETARY CONTROL 2025/26
CORPORATE SERVICES COMMITTEE DETAIL
PERIOD END DATE 31 January 2026
Total Budget
2025/26 
YTD Spend
2025/26 
Forecast
Spend
2025/26
Net Variance
attributable to
earmarked
reserves spend
Underlying
Variance
excluding
earmarked
reserves spend
RAG Status Service Summary Variance 2025/26
£000 £000 £000 £000 % £000 £000
Employee 327 202 232 (95) (29%) 0 (95) 
Property 3 6 10 7 261% 0 7 
Transport and Plant 0 0 0 (0) (94%) 0 (0) 
Supplies, Services and Admin 23 7 23 0 1% 0 0 
Payments to Other Bodies 13 4 10 (4) (28%) 0 (4) 
Other 0 0 0 0 0% 0 0 
Gross Expenditure 366 220 274 (92) (25%) 0 (92) 
Income (60) (62) (62) (2) (3%) 0 (2) 
Net Expenditure 306 158 212 (94) (31%) 0 (94) 
£000 £000 £000 £000 % £000 £000
Employee 4,280 3,561 4,255 (25) (1%) 0 (25) 
Property 113 89 115 3 2% 0 3 
Transport and Plant 110 68 92 (18) (17%) 0 (18) 
Supplies, Services and Admin 1,873 1,347 1,919 46 2% 0 46 
Payments to Other Bodies 29 52 52 24 84% 0 24 
Other 0 0 0 0 0% 0 0 
Gross Expenditure 6,404 5,117 6,433 29 0% 0 29 
Income (1,309) (211) (964) 345 26% 0 345 
Net Expenditure 5,095 4,906 5,469 374 7% 0 374 
£000 £000 £000 £000 % £000 £000
Employee 2,193 1,708 2,085 (108) (5%) 0 (108) 
Property 239 153 234 (5) (2%) 0 (5) 
Transport and Plant 2 0 1 (1) (45%) 0 (1) 
Supplies, Services and Admin 17 34 36 20 119% 0 20 
Payments to Other Bodies 0 0 0 0 0% 0 0 
Other 0 0 0 0 0% 0 0 
Gross Expenditure 2,450 1,895 2,356 (94) (4%) 0 (94) 
Income (322) (97) (251) 71 22% 0 71 
Net Expenditure 2,128 1,798 2,105 (23) (1%) 0 (23) 
£000 £000 £000 £000 % £000 £000
Employee 941 766 916 (25) (3%) 0 (25) 
Property 60 39 60 0 0% 0 0 
Transport and Plant 0 0 0 0 0% 0 0 
Supplies, Services and Admin 9 1 9 0 1% 0 0 
Payments to Other Bodies 0 0 0 0 0% 0 0 
Other 0 0 0 0 0% 0 0 
Gross Expenditure 1,010 806 985 (25) (2%) 0 (25) 
Income (1,105) (1,105) (1,105) 0 0% 0 0 
Net Expenditure (95) (299) (120) (25) 27% 0 (25) 
Arts and Heritage
Catering Services
Building Cleaning PPP
Building Cleaning
Page 299

Page 300

WEST DUNBARTONSHIRE COUNCIL APPENDIX 2
REVENUE BUDGETARY CONTROL 2025/26
CORPORATE SERVICES COMMITTEE DETAIL
PERIOD END DATE 31 January 2026
Total Budget
2025/26 
YTD Spend
2025/26 
Forecast
Spend
2025/26
Net Variance
attributable to
earmarked
reserves spend
Underlying
Variance
excluding
earmarked
reserves spend
RAG Status Service Summary Variance 2025/26
£000 £000 £000 £000 % £000 £000
Employee 2,743 2,076 2,517 (226) (8%) 0 (226) 
Property 44 52 67 23 52% 0 23 
Transport and Plant 0 0 0 (0) (79%) 0 (0) 
Supplies, Services and Admin 12 2 7 (5) (38%) 0 (5) 
Payments to Other Bodies 0 0 0 0 0% 0 0 
Other 0 0 0 0 0% 0 0 
Gross Expenditure 2,799 2,130 2,591 (208) (7%) 0 (208) 
Income (60) (44) (46) 15 24% 0 15 
Net Expenditure 2,739 2,086 2,545 (194) (7%) 0 (194) 
£000 £000 £000 £000 % £000 £000
Employee 541 430 516 (25) (5%) 0 (25) 
Property 0 0 0 0 0% 0 0 
Transport and Plant 2 3 3 1 73% 0 1 
Supplies, Services and Admin (259) 33 (109) 150 (58%) 0 150 
Payments to Other Bodies 22 22 22 0 1% 0 0 
Other 0 0 0 0 0% 150 (150) 
Gross Expenditure 305 488 432 127 42% 150 (23) 
Income 0 (15) (15) (15) 0% 0 (15) 
Net Expenditure 305 473 417 112 37% 150 (38) 
£000 £000 £000 £000 % £000 £000
Employee 0 0 0 0 0% 0 0 
Property 0 0 0 0 0% 0 0 
Transport and Plant 0 0 0 0 0% 0 0 
Supplies, Services and Admin 0 0 0 0 0% 0 0 
Payments to Other Bodies 4,833 4,772 4,909 76 2% 45 31 
Other 0 0 0 0 0% 0 0 
Gross Expenditure 4,833 4,772 4,909 76 2% 45 31 
Income (739) (717) (739) (0) (0%) 0 (0) 
Net Expenditure 4,094 4,055 4,170 76 2% 45 31 
£000 £000 £000 £000 % £000 £000
Employee 0 0 0 0 0% 0 0 
Property 0 0 0 0 0% 0 0 
Transport and Plant 0 3 3 3 0% 0 3 
Supplies, Services and Admin 35 49 49 13 38% 0 13 
Payments to Other Bodies 78 70 70 (8) (11%) 0 (8) 
Other 0 0 0 0 0% 0 0 
Gross Expenditure 114 121 121 8 7% 0 8 
Income (86) (96) (96) (10) (12%) 0 (10) 
Net Expenditure 28 25 25 (3) (9%) 0 (3) 
£000 £000 £000 £000 % £000 £000
Employee 95 87 101 6 6% 0 6 
Property 0 0 0 0 0% 0 0 
Transport and Plant 0 0 0 0 0% 0 0 
Supplies, Services and Admin 4 0 2 (3) (63%) 0 (3) 
Payments to Other Bodies 0 0 0 0 0% 0 0 
Other 0 0 0 0 0% 0 0 
Gross Expenditure 99 87 103 3 3% 0 3 
Income 0 0 0 0 0% 0 0 
Net Expenditure 99 87 103 3 3% 0 3 
School Crossing Patrollers
Facilities Assistants
Facilities Management
Leisure Management
Events
Page 300

Page 301

WEST DUNBARTONSHIRE COUNCIL
REVENUE BUDGETARY CONTROL 2025/26
ANALYSIS FOR VARIANCES OVER £50,000
PERIOD END DATE
Total Budget Forecast Spend Use of EMR RAG Status
£000 £000 £000 £000 %
Audit 291 219 0 (72) -25% 
Service Description
Main Issues / Reason for Variance
Mitigating Action
Anticipated Outcome
Cost of Collection of Council Tax (1,072) (1,228) 0 (156) 15% 
Service Description
Main Issues / Reason for Variance
Mitigating Action
Anticipated Outcome
Central Admin Support 2,602 2,510 0 (91) -4% 
Service Description
Main Issues / Reason for Variance
Mitigating Action
Anticipated Outcome
Environmental Health 575 507 0 (67) -12% 
Service Description
Main Issues / Reason for Variance
Mitigating Action
Anticipated Outcome
31 January 2026
Budget Details
Variance Analysis
Variance after the use
of EMR
Internal audit of council services.
Favourable variance arising from underspend in staffing costs due to vacant posts.
No action required.
A favourable variance is anticipated.
This service collects Council tax from local residents. The services also provides support and advice to
those residents regarding council tax.
A higher than anticipated favourable income outturn is anticipated from Statutory Additions.
None required.
Favourable variance is anticipated.
The 3 Groups within this service (Food and Business Group, Environmental Pollution Group and
Community Health Protection Group) are responsible for all aspects of Environmental Health work.
The reason for the favourable variance is the number of ongoing vacancies.
None Required
Favourable variance is anticipated.
This services deals with administration functions within the Authority.
Employee turnover is ahead of budget together with an uplift in recharges
None required.
Favourable variance is anticipated.
ITEM 15 - APPENDIX 3
Page 301

Page 302

WEST DUNBARTONSHIRE COUNCIL APPENDIX 3
REVENUE BUDGETARY CONTROL 2025/26
ANALYSIS FOR VARIANCES OVER £50,000
PERIOD END DATE
Total Budget Forecast Spend Use of EMR RAG Status
£000 £000 £000 £000 %
31 January 2026
Budget Details
Variance Analysis
Variance after the use
of EMR
Planning 557 504 52 (105) -19% 
Service Description
Main Issues / Reason for Variance
Mitigating Action
Anticipated Outcome
Arts and Heritage 306 212 0 (94) -31% 
Service Description
Main Issues / Reason for Variance
Mitigating Action
Anticipated Outcome
Catering Services 5,095 5,469 0 374 7% 
Service Description
Main Issues / Reason for Variance
Mitigating Action
Anticipated Outcome
Facilities Assistants 2,739 2,545 0 (194) -7% 
Service Description
Main Issues / Reason for Variance
Mitigating Action
Anticipated Outcome
The favourable variance is attributable to employee vacancies and income from planning pre-applications.
None required.
Favourable variance is anticipated.
There is a favourable variance against employee costs as a result of vacancies.
none necessary
Favourable variance
None.
None.
Although there is a small favourable variance against employee costs as a result of vacancies this has
been offset by adverse variances against food purchases and kitchen equipment repairs and, particularly,
against income. The income budget was overstated and includes £350k which was also shown within
General Revenue Grant income. This was highlighted as a 2026/27 budget pressure in the June 2025
Finance Update to Council.
This Service provides Building & Planning services.
Favourable variance
This service provides Facility Assistants throughout WDC buildings.
There is a favourable variance against employee costs as a result of vacancies.
Catering Services across WDC
Adverse variance
This service provides the provision & protection of Arts & Heritage
Page 302

Page 303

WEST DUNBARTONSHIRE COUNCIL
MONITORING OF EARMARKED BALANCES 2025/26 BY CHIEF OFFICER
DEPARTMENT   25/26 Estimate  25/26        
Spend to Date 
25/26 Probable
Outturn 
To be carried
forward into 26/27 
Description 
£  £  £  £         
1 Revs & Bens: Social Welfare Fund 374,103                 -                     374,103             -                              To pay the balance of Scottish Welfare Fund grants expenditure funded by the Scottish Government.  Carried forward to 2025/26.         
2 Revs & Bens: DWP funding 53,000                   -                     53,000               -                              To support activities related to Housing Benefit and Council Tax Reduction, including system enhancements scheduled for completion in
FY25/26.
3 Financial Service Centre: Automation Team (VKY)  26,284                   -                     -                     26,284                        Expenditure linked to the VKY Automation contract approved in 2020/21 as part of the Robotic Process Automation (RPA) rollout. 
4 Intromissions 200,000                 -                     200,000                      Build up of reserve to pay for future liability for historic child abuse cases (as agreed at Council October 2024)         
5 Regulatory - New document management system 90,000                   -                     45,000               45,000                        The Planning and Building Standards require a new document management system to replace the current system. The current timeline is to
procure over two years due to the different stages in the process and the time needed to undertake them. 
6 Regulatory - Underspend in 'design panel' budget for IDOX
upgrade
7,000                      7,000                 7,000                 -                              This balances relates to the initial stages of designing the new Planning and Building Standards document management system and will be
spent this financial year.         
7 Developer Contributions 379,000                 -                     379,000                      These are financial or in-kind contributions received from developers and are associated with specific agreements. They need to be retained
and used for the purposes specified in the individual agreements.         
8 Energy Efficiency 330,000                 -                     330,000                      The funds relate to a Scottish Government Grant received some years ago for energy efficiency projects. A programme of energy 
improvement projects will be developed with the potential to recycle savings back to the fund.         
9 Business Support 220,000                 -                     220,000                      Business Loans Scotland Income to be used for future business support activity over the next 2-3 years.
10 OD & Change Training Budget 8,773                      -                     -                     8,773                          Funding allocated to meet defined training needs       
11 Previous provision for equal pay/holiday pay 194,663                 -                     9,499                 185,164                      Balance for outstanding equal pay/holiday pay claims and associated legal expenses.
RESOURCES
REGULATORY & REGENERATION
PEOPLE & TECHNOLOGY
ITEM 15 - APPENDIX 4
Page 303

Page 304

WEST DUNBARTONSHIRE COUNCIL APPENDIX 4
MONITORING OF EARMARKED BALANCES 2025/26 BY CHIEF OFFICER
DEPARTMENT   25/26 Estimate  25/26        
Spend to Date 
25/26 Probable
Outturn 
To be carried
forward into 26/27 
Description 
£  £  £  £
12 Cost of Living 4: Fund the successful spending on Sport & Leisure
for children during holiday times for the next 4 years. £45,000 per
year.
107,040                 45,000               45,000               62,040                        Additional payments to WDLT for holiday activities (eg gym and swimming classes) provided over Easter ,summer and autumn
13 Cost of Living 7: Introduce a programme of creative engagement
and learning focused on supporting people through recovery and
improving wellbeing. £5,000 per year for 4 years.
10,000                   -                     10,000                        The £5k for each of the four years was partially spent in 23/24 and 24/25 and will be fully spent in 25/26 once Glencairn and the new
museum space in Clydebank are opened.
14 Transfer to Foodbank support fund 151,680                 31,680               31,680               120,000                    
15 Smoothing Fund -                          -                     172,199             -                             The smoothing fund is being used to offset service overspends where savings/efficiencies have not been achieved in year.  £150k is being
used to cover the delay in implementing a new management operating model in facilities. In addition, £16k will also be met from the
smoothing fund in relation to the shortfall in the generation of site income from television/film productions within Comms & Marketing and
a further £6k due to the delays in the recruitment of the council's Digital Officer. It is anticipated that these costs will be offset by savings in
26/27.                                                                                                                               
TOTAL USE OF EARMARKED RESERVES                2,151,543                 83,680               737,481                   1,586,261
COST OF LIVING
STRATEGIC RESERVES
Page 304

Page 305

WEST DUNBARTONSHIRE COUNCIL
MONITORING OF EFFICIENCIES AND MANAGEMENT ADJUSTMENTS 2025/26
Efficiency Detail Ref Chief Officer
Budgeted
Amount      
£000 
Projection of
Total Saved      
£000 
Projection of
Total Not Saved       
£000 Comment
1 Charging for Pre application advice RR09 A Douglas 5                        5                         -                         Saving anticipated to be achieved
2 Remove £12,500 of Nightzone West funding provided to Police Scotland RR01 A Douglas 1                        1                         -                         Saving anticipated to be achieved
3
Review compliance with Strategic Opening Model to identify areas where teams
or posts can be merged CCF26 A Douglas 50                      50                      -                         Saving anticipated to be achieved
4 Revised Legal Charges for Transactions RR06 A Douglas 25                      25                      -                         Saving anticipated to be achieved
5 Registrars RR09 A Douglas 18                      18                      -                         Saving anticipated to be achieved
6 Building Standards A Douglas 10                      10                      -                         Saving anticipated to be achieved
7 Reduce Community Budgeting fund CCF10 A Douglas 27                      27                      -                         Saving anticipated to be achieved
8 Remove Members’ Secretary RR04 A Douglas 22                      22                      -                         Saving anticipated to be achieved
9 Reduce Trading Standards team RR17 A Douglas 14                      14                      -                         Saving anticipated to be achieved
10 Reduce Records Management team RR18 A Douglas 14                      14                      -                         Saving anticipated to be achieved
11 Close Clydebank Registration Office RR19 A Douglas 8                        8                         -                         Saving anticipated to be achieved
12 Combine dog warden & pest control posts RR10 A Douglas 38                      38                      -                         Saving anticipated to be achieved
13 Lead planner replaced by basic grade officer RR11 A Douglas 7                        7                         -                         Saving anticipated to be achieved
14 Antonine wall RR12 A Douglas 27                      27                      -                         Saving anticipated to be achieved
15 Review environmental health RR13 A Douglas 35                      35                      -                         Saving anticipated to be achieved
16 Development planning & placemaking RR20 A Douglas 55                      55                      -                         Saving anticipated to be achieved
17 Review core library staffing (outwith branch libraries)  and remove one post CCF19 A Graham 18                      18                      -                         Saving anticipated to be achieved
18
Review the Communities team reducing the delivery of community based
services CCF26 A Graham 15                      15                      -                         Saving anticipated to be achieved
19 Increase events income CCF05 A Graham 8                        8                         -                         Saving anticipated to be achieved
20 Review film locations and formalise fee arrangements CCF06 A Graham 8                        8                         -                         Saving anticipated to be achieved
21 Reduce Highland Games Spend CCF01 A Graham 15                      15                      -                         Saving anticipated to be achieved
22 Reduce Contact Centre by 2 FTE CCF09 A Graham 30                      30                      -                         Saving anticipated to be achieved
23 Reduce Community Engagement Budget CCF11 A Graham 22                      22                      -                         Saving anticipated to be achieved
24 Reduction in Arts and Heritage - 1.5 FTE reduction. CCF18 A Graham 30                      30                      -                         Saving anticipated to be achieved
25 Review Facilities Mgt Operating Model CCF04 A Graham 300                    150                    150                       
Consultations with workforce on new
operating model have taken longer than
anticipated. Shortfall covered by smoothing
fund.
26 Remove two franking machines and further reduce use of first class mail RES11 L Slavin 8                        8                         -                         Saving anticipated to be achieved
27 Review External Funding - Delete Community Wellbeing Fund RES01 L Slavin 20                      20                      -                         Saving anticipated to be achieved
28 Reduce Corporate Debt team RES06 L Slavin 44                      44                      -                         Saving anticipated to be achieved
29 Reduce Housing Benefit  and Council Tax team RES14 L Slavin 16                      16                      -                         Saving anticipated to be achieved
30 Review of Capital Programme  RES06 L Slavin 66                      66                      -                         Saving anticipated to be achieved
ITEM 15 - APPENDIX 5  
Page 305

Page 306

WEST DUNBARTONSHIRE COUNCIL APPENDIX 5
MONITORING OF EFFICIENCIES AND MANAGEMENT ADJUSTMENTS 2025/26
Efficiency Detail Ref Chief Officer
Budgeted
Amount      
£000 
Projection of
Total Saved      
£000 
Projection of
Total Not Saved       
£000 Comment
31 Restrict choice in office equipment to pre-agreed catalogue items/amounts. PT05 V Rogers 5                        5                         -                         Saving anticipated to be achieved
32
Reduce the Council’s training budget, retaining budget to cover essential
corporate requirements PT07 V Rogers 5                        5                         -                         Saving anticipated to be achieved
33
Reduce manual processing by automating the generation of debtor and creditor
invoices RES11 V Rogers 25                      25                      -                         Saving anticipated to be achieved
34 Remove counselling and physio PT10 V Rogers 9                        9                         -                         Saving anticipated to be achieved
35 Remove telephone survey CCF13 V Rogers 9                        9                         -                         Saving anticipated to be achieved
36 Performance and Strategy Budget Efficiencies CCF15 V Rogers 9                        9                         -                         Saving anticipated to be achieved
37 Reduce design budget CCF16 V Rogers 12                      12                      -                         Saving anticipated to be achieved
38 Reduce Corporate Administration Support 3 FTE Reduction. PT12 V Rogers 91                      91                      -                         Saving anticipated to be achieved
39 People & Change Team Restructure PT14 V Rogers 62                      62                      -                         Saving anticipated to be achieved
40 Organisational Development Reduction PT15 V Rogers 60                      60                      -                         Saving anticipated to be achieved
41 Outsource  Print Room function PT18 V Rogers 25                      25                      -                         Saving anticipated to be achieved
42 Reduce ICT team: 4 FTE PT20 V Rogers 84                      84                      -                         Saving anticipated to be achieved
43
Review the Communities team reducing the delivery of community based
services CCF26 A Graham 87                      87                      -                         Saving anticipated to be achieved
44 Reduction in 2 FTE paralegal support to contracts and property section RR08 A Douglas 90                      90                      -                         Saving anticipated to be achieved
TOTAL AGREED SAVINGS OPTIONS & MANAGEMENT ADJUSTMENTS 1,527                1,377                 150                       
Page 306

Page 307

WEST DUNBARTONSHIRE COUNCIL
Report by the Chief Officer – Resources
Corporate Services Committee – 27 May 2026
___________________________________________________________________ 
Subject: Corporate Services Capital Budgetary Control Report to 31 January 2026  
(Period 10) 
1. Purpose 
1.1 This report provides an update on the Corporate Services capital programme
to 31 January 2026. 
2. Recommendations 
2.1 Committee is asked to: 
i) Note the current position of the 2025/26 capital budget for Corporate
Services 
ii) Note the revised completion dates in respect of 2 projects detailed in
Appendix 2 (Para 4.4). 
iii) Note the reprofiling of 4 projects in Appendix 3 of (£0.669m) over the
project life. 
3. Background 
3.1 On 5 March 2025 the Council approved the updated General Services Capital
Plan for 2025/2026 to 2033/34.  The three years from 2025/26 to 2027/28
were approved in detail with the remaining years being indicative. The budget
agreed under the auspice of Corporate Services Committee was £4.078m for
2025/26 and £29.301m for the project life budget. 
4. Main Issues 
4.1 Exhibit 1 sets out the revised capital budget at period 7 as reported to
Corporate Services Committee on 4 February 2026. 
Exhibit 1: Revised Capital Budget as at 31 October 2025. 
2025/26
(£m)
Project
Life (£m)
Corporate Services Capital Budget Agreed 5
March 2025 4.078 29.301
Reprofiling reported to committee on 13 August
and 4 February 0.015 (0.094)
Approved P&T Capital Bid – Data Strategy 0.027 0.027
Revised Capital Budget as at Period 7 4.120 29.234
ITEM 16
Page 307

Page 308

4.2 Progress against the 2025/26 capital plan is detailed in: 
Appendix 1 – Project Life Summary by Chief Officer 
Appendix 2 – Projects Off Track 
Appendix 3 – Changes to Capital Plan for Noting 
Appendix 4 – All Projects 
4.3  The overall program summary report at Appendix 1 shows that planned
expenditure against the budget is currently on track. Note Appendix 1 is
constructed assuming all changes in this report are approved. 
4.4  Appendix 2 highlights 2 projects currently showing as off-track, all of which
are due to revised completion dates.  
• Project RES 4 (Community Success Capital Fund) is off-track due to no
active or pending requests for funding. 
• Project RES 5 (Community Sports Success) is off track due to no active
or pending requests for funding. 
4.5  Appendix 3 highlights 4 projects where the expenditure requires to be
reprofiled but there is no need for additional budget. 
4.6  Exhibit 2 sets out the revised capital budget at period 10 after amending it to
reflect the Council decisions taken in relation to the agenda item, General
Services Capital Report Budgetary Control Report (Period 10) on the 25 of
March. 
Exhibit 2: Revised Capital Budget 
2025/26
(£m)
Project
Life (£m)
Corporate Services Capital Budget as at 31
October 2025 4.120 29.234
Approved Review of Capital Programme (Para
4.9) (0.033) (0.421)
Projects completed and removed (Para 4.10) 0 (3.173)
Projects complete at 31 January 2026 (Para
4.11) (0.010) (0.512)
Proposed revised Capital Budget as at
Period 10 4.077 25.128
Reprofiling over project life (Appendix 3) (0.669) 0
Proposed revised Capital Budget as at
Period 10 after Council Approval 3.408 25.128 
4.8  Appendix 4 shows all projects with approved in year and project life budgets
as well as anticipated expenditure. It highlights the 2025/26 budget is
£4.077m. Spend as at period 10 is £1.975m (57.94%) of the current forecast
spend of £3.408m.
Page 308

Page 309

4.9  Following the Review of West Dunbartonshire Council’s Capital Programme
paper approved by Council on 17 December 2025 with one amendment per
the motion, the changes below have been applied to the capital plan: 
• Projects removed
o Legal Case Management System (RR 1) - £0.033m 
• Projects with reduced budget allocation
o Finance Ledger System (RES 11) - £0.200m
o Development of Workforce Management System (P&T 4) - £0.188m 
4.10  Following the above adjustments, historic project life budgets completed and
removed have been applied which reduces project life by £3.173m. 
4.11  Additionally Cost of Living (RES 3) has been completed at 31 January 2026. 
5. Option Appraisal 
5.1 No option appraisal was required for this report. 
6. People Implications 
6.1 There are no people implications. 
7. Financial and Procurement Implications 
7.1 The report notes the projected in-year financial position for capital budgets. 
8. Risk Analysis 
8.1 The main risks are as follows: 
(a) The reported variances should be viewed in the knowledge that there
are a number of variable factors which could arise between now and 31
March which could affect the year end results for capital budgets. 
(b) As a consequence of current market conditions, inflation is at an all-time
high and interest rates continue to be volatile. To forecast for the full
year costs budget assumptions have been required. These assumptions
continue to change regularly and therefore it is likely the projected year
end budgetary position will change from that reported. 
9. Equalities Impact Assessment (EIA) 
9.1 No equalities impact assessment was required in relation to this report. 
10. Environmental Sustainability 
10.1 No assessment of environmental sustainability was required in relation to this
report.
Page 309

Page 310

11. Consultation 
11.1 All services involved in delivering the capital budgets have been consulted in
the compilation of this report. 
12. Strategic Assessment 
12.1 Proper budgetary control and sound financial practice are cornerstones
of good governance and support Council and officers to pursue the
strategic priorities of the Council’s current Strategic Plan. This report
forms part of the financial governance of the Council. 
Laurence Slavin
Chief Officer – Resources
Date: 15 April 2026
________________ 
Person to Contact:  Lynsey Dickson, Finance Business Partner  
Council Offices, Church Street, Dumbarton   
E-mail: lynsey.dickson@west-dunbarton.gov.uk 
Appendices:  Appendix 1 - Project Life Summary  
Appendix 2 - Projects Off Track 
Appendix 3 - Changes to Capital Plan for Noting
Appendix 4 - All Approved Projects 
Background Papers:   General Services Capital Plan Update - Council 5 March 
2025 
Capital Budgetary Control Report (P3) – Council 27 
August 2025 
Capital Budgetary Control Report (P5) – Council 29 
October 2025    
Capital Budgetary Control Report (P7) – Council 17 
December 2025    
Review of West Dunbartonshire Councils Capital    
Programme – Council 17 December 2025    
Capital Budgetary Control Report (P10) – Council 24    
March 2026 
Wards Affected           All Wards 
Page 310

Page 311

Official#
Summary at Period 10
Project Life
Budget
Project Life
Forecast
Spend
Project Life
Variance On Track Off Track
£'000 £'000 £'000
Resources 15,596             15,596            0 4                                     2
People and Technology 9,532               9,532              0 5                                     0
Total 25,128             25,128            0 9 2
ITEM 16 - APPENDIX 1
Page 311

Page 312

Official#
Projects that are Off Track at Period 10
Service Project
Approved Project Life
Cost
Revised Project
Life Cost
Project Life
Variance
Initial Completion
Date
Revised
Completion Date
£'000 £'000 £'000
Resources RES 4 - Community Success Capital Fund                                     150                         150                  -   31/03/2026 31/03/2027
Resources RES 5  - Community Sports Success                                     250                         250                  -   31/03/2026 31/03/2027
Project Name: Project - RES 4 - Community Success Capital Fund Project Manager: Michelle Lynn
Initial Completion End Date: 31/03/2026 Revised End Date: 31/03/2027
How was this project initially funded: Please Detail any additional funding:
Prudential Borrowing n/a
Why is the project classified as off track and what has caused the issues identified?
What action will be taken to rectify the position?
New Completion Date: 31/03/2027 Prudential Borrowing
What are the implications on the actions proposed?
Revenue Implications:-
Virement Implications:- n/a
Project Name: Project - RES 5 - Community Sports Success Project Manager: Michelle Lynn
Initial Completion End Date: 31/03/2026 Revised End Date: 31/03/2027
How was this project initially funded: Please Detail any additional funding:
Prudential Borrowing n/a
Why is the project classified as off track and what has caused the issues identified?
What action will be taken to rectify the position?
New Completion Date: 31/03/2027 Prudential Borrowing
What are the implications on the actions proposed?
Revenue Implications:-
Virement Implications:- n/a
The allocation set aside for community groups to apply for remains uncommitted at this stage, as we currently have no active or pending requests for funding. Given the absence of demand in the current financial year,
the budget is proposed to be reprofiled into 26/27.  Reprofiling will ensure that the funding remains available and aligned with future community needs, allowing groups sufficient time to develop proposals and submit
applications. This approach supports effective financial management by preventing underspend in the current year while safeguarding the resource for its intended purpose.  The budget will continue to be monitored,
and officers will engage with community organisations ahead of and into the 26/27 financial year.
Source of Funding:
n/a
The allocation set aside for community groups to apply for remains uncommitted at this stage, as we currently have no active or pending requests for funding. Given the absence of demand in the current financial year,
the budget is proposed to be reprofiled into 26/27.  Reprofiling will ensure that the funding remains available and aligned with future community needs, allowing groups sufficient time to develop proposals and submit
applications. This approach supports effective financial management by preventing underspend in the current year while safeguarding the resource for its intended purpose.  The budget will continue to be monitored,
and officers will engage with community organisations ahead of and into the 26/27 financial year.
Source of Funding:
n/a
ITEM 16 - APPENDIX 2
Page 312

Page 313

Official#
Changes to Capital Plan and Implications at P10
Project - RES 4 Initial End Date  Revised End Date Reprofiling Current Year  2026/27  2027/28  2028/29  2029/30  2030/31  2031/32  2032/33  2033/34  Total Capital Plan
£'000 £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000
Community Success Capital Fund 150 0 0 0 0 0 0 0 0                         150
Community Success Capital Fund Revised 31/03/2026 31/03/2027 129 21 129 0 0 0 0 0 0 0                         150
Explanation
Project - RES 5 Initial End Date  Revised End Date Reprofiling Current Year  2026/27  2027/28  2028/29  2029/30  2030/31  2031/32  2032/33  2033/34  Total Capital Plan
£'000 £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000
Community Sports Success 240 0 0 0 0 0 0 0 0                         240
Community Sports Success Revised 31/03/2026 31/03/2027 231 9 231 0 0 0 0 0 0 0                         240
Explanation
Project - RES 11 Initial End Date  Revised End Date Reprofiling Current Year  2026/27  2027/28  2028/29  2029/30  2030/31  2031/32  2032/33  2033/34  Total Capital Plan
£'000 £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000
Finance Ledger System 31/03/2027 31/03/2027 430 335                         765
Finance Ledger System Revised 218 212 553                         765
Explanation
Project - P&T 4 Initial End Date  Revised End Date Reprofiling Current Year  2026/27  2027/28  2028/29  2029/30  2030/31  2031/32  2032/33  2033/34  Total Capital Plan
£'000 £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000
Development of Workforce Management System 31/03/2027 31/03/2027 93 17 0 0 0 0 0 0 0                         110
Development of Workforce Management System Revised 91 2 108 0 0 0 0 0 0 0                         110
Explanation
£91k required to be carried forward to 26/27 due to statutory and ICT priorities delaying implemenations.
The allocation set aside for community groups to apply for remains uncommitted at this stage, as we currently have no active or pending requests for funding. Given the absence of demand in the current financial year, the budget is proposed to be reprofiled into 26/27.  Reprofiling will ensure that the funding remains
available and aligned with future community needs, allowing groups sufficient time to develop proposals and submit applications. This approach supports effective financial management by preventing underspend in the current year while safeguarding the resource for its intended purpose.  The budget will continue to
be monitored, and officers will engage with community organisations ahead of and into the 26/27 financial year.
The allocation set aside for community groups to apply for remains uncommitted at this stage, as we currently have no active or pending requests for funding. Given the absence of demand in the current financial year, the budget is proposed to be reprofiled into 26/27.  Reprofiling will ensure that the funding remains
available and aligned with future community needs, allowing groups sufficient time to develop proposals and submit applications. This approach supports effective financial management by preventing underspend in the current year while safeguarding the resource for its intended purpose.  The budget will continue to
be monitored, and officers will engage with community organisations ahead of and into the 26/27 financial year.
Expenditure profile has changed due to current phase of implementation project being mainly information gathering. Expect costs to pickup as project moves into training and test phases which will occur during 26/27 financial year.
Page 313
ITEM 16 - APPENDIX 3

Page 314

Official#
All Projects Approved at P10
Service Project Completion Date Revised End Date
Project Life
Budget
Spend to
31/03/2025
Spend Projected
in Current Year Projected
Future Spend
Total Projected Spend Project Variance Approved Budget
2025/26 Actual to date 2025/26 Projected Spend In Year Variance
£000 £'000  £'000  £'000  £'000 £'000 £'000 £'000 £'000
RES 1 Valuation Joint Board - Requisition of ICT Equipment 31 March 2028 31 March 2028 30 17 4 9 30 0 4 0 4 0
RES 2 Agresso Development 31 March 2026 31 March 2026 92 86 6 0 92 0 6 1 6 0
RES 4 Community Success Capital Fund 31 March 2026 31 March 2027 150 0 21 129 150 0 150 21 21 (129)
RES 5 Community Sports Success 31 March 2026 31 March 2027 250 10 9 231 250 0 240 9 9 (231)
RES 9 Direct Project Support 31 March 2026 31 March 2026 14,274 0 1,586 12,688 14,274 0 1,586 669 1,586 0
RES 11 Finance Ledger System 31 March 2027 31 March 2027 800 34 212 553 800 0 430 196 212 (218)
Total Resources 15,596 147 1,838 13,610 15,596 0 2,416 896 1,838 (578)
P&T 1 ICT Modernisation 31 March 2026 31 March 2026 4,579 0 578 4,001 4,579 0 578 527 578 0
P&T 2 ICT Security & DR 31 March 2026 31 March 2026 3,833 0 737 3,096 3,833 0 737 415 737 0
P&T 3 365 Implementation 31 March 2026 31 March 2026 983 757 226 0 983 0 226 135 226 0
P&T 4 Development of Workforce Management System 31 March 2027 31 March 2027 110 0 2 108 110 0 93 1 2 (91)
P&T 5 Data Strategy 31 March 2026 31 March 2026 27 0 27 0 27 0 27 0 27 0
Total P&T 9,532 757 1,570 7,205 9,532 0 1,661 1,078 1,570 (91)
Overall Total 25,128 904 3,408 20,815 25,128 0 4,077 1,975 3,408 (669)
Full Project Life In Year