WEST DUNBARTONSHIRE COUNCIL
Report by the Chief Officer – Resources
Corporate Services Committee – 4 February 2026
___________________________________________________________________
Subject: Corporate Services Capital Budgetary Control Report to 31 October 2025
(Period 7)
1. Purpose
1.1 This report provides an update on the Corporate Services capital programme
to 31 October 2025.
2. Recommendations
2.1 Committee is asked to:
i) Note the current position of the 2025/26 capital budget for Corporate
Services
ii) Note that the project life total is currently on track.
3. Background
3.1 On 5 March 2025 the Council approved the updated General Services Capital
Plan for 2025/2026 to 2033/34.  The three years from 2025/26 to 2027/28
were approved in detail with the remaining years being indicative. The budget
agreed under the auspice of Corporate Services Committee was £4.078m for
2025/26 and £29.301m for the project life budget.
4. Main Issues
4.1 Exhibit 1 sets out the revised capital budget at period 5 as reported to
Corporate Services Committee on 12 November 2025.
Exhibit 1: Revised Capital Budget as at 31 August 2025.
2025/26
(£m)
Project
Life (£m)
Corporate Services Capital Budget Agreed 5
March 2025 4.078 29.301
Reprofiling reported to committee on 13 August 0.133 (0.094)
Approved P&T Capital Bid – Data Strategy 0.027 0.027
Revised Capital Budget as at Period 5 4.238 29.234
4.2 Progress against the 2025/26 capital plan is detailed in:
Appendix 1 – Project Life Summary by Chief Officer
ITEM 12

Page 2

Appendix 2 – Projects Off Track – not required for period 7 as there are no off
track projects to report.
Appendix 3 – Changes to Capital Plan for Noting
Appendix 4 – All Projects
4.3 The overall program summary report at Appendix 1 shows that planned
expenditure against the budget is currently on track. Note Appendix 1 is
constructed assuming all changes in this report are approved.
4.4 Appendix 3 highlights 1 project where the expenditure requires to be reprofiled
but there is no need for additional budget.
4.5 Exhibit 2 sets out the revised capital budget at period 7 after approval of the
General Services Capital Report Budgetary Control Report (Period 7) by
Council on the 17th of December of the recommendation contained within this
report.
4.6 Decisions taken on 17 December 2025 at Council on the Financial Update
(savings taken) and the Review of West Dunbartonshire Councils Capital
Programme will be applied to the P10 Capital BCR due to the timing
differences of the reports.
Exhibit 2: Revised Capital Budget
2025/26
(£m)
Project
Life (£m)
Corporate Services Capital Budget as at 31
August 2025 4.238 29.234
No changes to capital budgets 0 0
Proposed revised Capital Budget as at
Period 7 4.238 29.234
Reprofiling over project life (Appendix 3) (0.118) 0
Proposed revised Capital Budget as at
Period 7 after Council Approval 4.120 29.234
4.7 Appendix 4 shows all projects with approved in year and project life budgets
as well as anticipated expenditure. It highlights the 2025/26 budget is
£4.238m. Spend as at period 7 is £1.129m (27.41%) of the current forecast
spend of £4.120m.
5. Option Appraisal
5.1 No option appraisal was required for this report.
6. People Implications
6.1 There are no people implications.
7. Financial and Procurement Implications

Page 3

7.1 The report notes the projected in-year financial position for capital budgets.
8. Risk Analysis
8.1 The main risks are as follows:
(a) The reported variances should be viewed in the knowledge that there are
a number of variable factors which could arise between now and 31
March which could affect the year end results for capital budgets.
(b) As a consequence of current market conditions, inflation is at an all-time
high and interest rates continue to be volatile. To forecast for the full year
costs budget assumptions have been required. These assumptions
continue to change regularly and therefore it is likely the projected year
end budgetary position will change from that reported.
9. Equalities Impact Assessment (EIA)
9.1 No equalities impact assessment was required in relation to this report.
10. Environmental Sustainability
10.1 No assessment of environmental sustainability was required in relation to this
report.
11. Consultation
11.1 All services involved in delivering the capital budgets have been consulted in
the compilation of this report.
12. Strategic Assessment
12.1 Proper budgetary control and sound financial practice are cornerstones
of good governance and support Council and officers to pursue the
strategic priorities of the Council’s current Strategic Plan. This report
forms part of the financial governance of the Council.
Laurence Slavin
Chief Officer – Resources
Date: 05 January 2026
________________
Person to Contact: Lynsey Dickson, Finance Business Partner
Council Offices, Church Street, Dumbarton
E-mail: lynsey.dickson@west-dunbarton.gov.uk
Appendices: Appendix 1 - Project Life Summary
Appendix 3 - Changes to Capital Plan for Noting
Appendix 4 - All Approved Projects

Page 4

Background Papers:  General Services Capital Plan Update - Council 5 March
2025
Capital Budgetary Control Report (P3) – Council 27
August 2025
Capital Budgetary Control Report (P5) – Council 29
October 2025
Capital Budgetary Control Report (P7) – Council 17
December 2025
Wards Affected          All Wards