WEST DUNBARTONSHIRE COUNCIL
Report by the Chief Officer – Resources
Corporate Services Committee – 12 November 2025
___________________________________________________________________
Subject: Corporate Services Capital Budgetary Control Report to 31 August 2025
(Period 5)
1. Purpose
1.1 This report provides an update on the Corporate Services capital programme
to 31 August 2025.
2. Recommendations
2.1 Committee is asked to:
i) Note the current position of the 2025/26 capital budget for Corporate
Services
ii) Note that the project life total is currently on track.
iii) Note the additional capital budget of £0.027m for data strategy (Para
4.6).
3. Background
3.1 On 5 March 2025 the Council approved the updated General Services Capital
Plan for 2025/2026 to 2033/34.  The three years from 2025/26 to 2027/28
were approved in detail with the remaining years being indicative. The budget
agreed under the auspice of Corporate Services Committee was £4.078m for
2025/26 and £29.301m for the project life budget.
4. Main Issues
4.1 Exhibit 1 sets out the revised capital budget at period 3 as reported to
Corporate Services Committee on 13 August 2025.
Exhibit 1: Revised Capital Budget as at 30 June 2025.
2025/26
(£m)
Project
Life (£m)
Corporate Services Capital Budget Agreed 5
March 2025 4.078 29.301
Reprofiling reported to committee on 13 August 0.133 (0.094)
Revised Capital Budget as at Period 3 4.211 29.207
4.2 Progress against the 2025/26 capital plan is detailed in:
ITEM 17

Page 2

Appendix 1 – Project Life Summary by Chief Officer
Appendix 2 – Projects Off Track – not required for period 5 as there are no off
track projects to report.
Appendix 3 – Changes to Capital Plan for Noting – not required for period 5
Appendix 4 – All Projects
4.3 The overall program summary report at Appendix 1 shows that planned
expenditure against the budget is currently on track. Note Appendix 1 is
constructed assuming all changes in this report are approved.
4.4 Exhibit 2 sets out the revised capital budget at period 5 assuming approval by
Council on the 29th of October of the recommendation contained within this
report.
Exhibit 2: Revised Capital Budget
2025/26
(£m)
Project
Life (£m)
Corporate Services Capital Budget as at 30
June 2025 4.211 29.207
Approved P&T 5 Capital Bid – Data Strategy
(Para 4.6) 0.027 0.027
Proposed revised Capital Budget as at
Period 5 subject to Council Approval 4.238 29.234
4.5 Appendix 4 shows all projects with approved in year and project life budgets
as well as anticipated expenditure. It highlights the 2025/26 budget is
£4.238m with current forecast spend of £4.238m. The spend as at period 5 is
£0.364m (8.58%) of the current forecast spend of £4.238m.
4.6 Members are asked to note an additional capital budget of £0.027m to fund
data strategy.
This bid has been reviewed by the Strategic Asset Management Group who
recommend that £0.027m is added to the Capital plan to allow the People and
Technology team to provide a robust data strategy which would be the
cornerstone of creating a sustainable, modern data ecosystem capable of
meeting the Council’s evolving needs while improving outcomes for its
residents. A data strategy provides a unified framework for aligning data
governance, technology, and processes with organisational goals. This
approach positions the Council to effectively transform its data into a strategic
asset that can be better utilised and controlled to achieve financial efficiencies
and benefits while addressing challenges and setting the foundation of a clear
path for long-term data-driven success.
The new data platform and modern ways of working will drive operational
efficiencies and bring time-saving benefits forecast from the outset. The
Council can also better understand the changing landscape of public sector
demand on services and keep pace with legislative demands on statutory
services, and privacy and security requirements.

Page 3

This project has been included in appendix 4 (P&T 5).
5. Option Appraisal
5.1 No option appraisal was required for this report.
6. People Implications
6.1 There are no people implications.
7. Financial and Procurement Implications
7.1 The report notes the projected in-year financial position for capital budgets.
8. Risk Analysis
8.1 The main risks are as follows:
(a) The reported variances should be viewed in the knowledge that there are
a number of variable factors which could arise between now and 31
March which could affect the year end results for capital budgets.
(b) As a consequence of current market conditions, inflation is at an all-time
high and interest rates continue to be volatile. To forecast for the full year
costs budget assumptions have been required. These assumptions
continue to change regularly and therefore it is likely the projected year
end budgetary position will change from that reported.
9. Equalities Impact Assessment (EIA)
9.1 No equalities impact assessment was required in relation to this report.
10. Environmental Sustainability
10.1 No assessment of environmental sustainability was required in relation to this
report.
11. Consultation
11.1 All services involved in delivering the capital budgets have been consulted in
the compilation of this report.
12. Strategic Assessment
12.1 Proper budgetary control and sound financial practice are cornerstones
of good governance and support Council and officers to pursue the
strategic priorities of the Council’s current Strategic Plan. This report
forms part of the financial governance of the Council.

Page 4

Laurence Slavin
Chief Officer – Resources
Date: 01 October 2025
________________
Person to Contact: Lynsey Dickson
Council Offices, Church Street, Dumbarton
E-mail: lynsey.dickson@west-dunbarton.gov.uk
Appendices:
Appendix 1 - Project Life Summary
Appendix 2 - Off Track Projects – not required at P5
Appendix 3 - Changes to Capital Plan for Noting – not required at P5
Appendix 4 - All Approved Projects
Background Papers: 
General Services Capital Plan Update - Council 5 March 2025
Capital Budgetary Control Report (P3) – Council 27 August 2025
Wards Affected         
All Wards