Appendix 1: Resources Delivery Plan 2025/26 - Mid-year Progress
1. Our Communities
Our residents are supported to increase life and learning skills
Action Status Progress Due Date Note Owner
Complete the redevelopment of
Glencairn House
31-Mar-
2026
Progressing as planned. While there have been delays
due to unforeseen circumstances on site, they will not
impact the 31 December deadline for the completion and
handover of the Children's Library and main building.
Michelle
Lynn
Progress the Faifley Community
Campus development
31-Mar-
2026
Progressing as planned. Phase 1 of the project handed
over and completed on programme.
Michelle
Lynn
2. Our Environment
Our neighbourhoods are sustainable and attractive
Q1 2025/26 Q2 2025/26
Performance Indicator Status Value Target Status Value Target Short
Trend
Long
Trend Note Owner
Percentage of Consultancy
Services project
deliverables for General
Services projects delivered
as planned
40% 20% 50% 40% Target exceeded in both Q1 and Q2 and on
track to meet or exceed annual target.
Michelle
Lynn

Page 2

2
Action Status Progress Due Date Note Owner
Progress the building upgrades
programme
31-Mar-
2026
Progressing as planned. The building upgrades
programme is on track, with works completed in the first
half of the year.
Michelle
Lynn
3. Our Economy
Our area has the infrastructure for sustainable and inclusive growth where businesses can flourish
Q1 2025/26 Q2 2025/26
Performance Indicator Status Value Target Status Value Target Short
Trend
Long
Trend Note Owner
Number of invoices paid
within 30 calendar days
of receipt as a
percentage of all invoices
paid
94.3% 91% 91% 91% Targets met in both quarters. Ryan
Chalmers
Our partnerships support economic development to deliver increased prosperity for our area
Q1 2025/26 Q2 2025/26
Performance Indicator Status Value Target Status Value Target Short
Trend
Long
Trend Note Owner
Time for processing
applications for new
Housing Benefits claims
from application receipt
date to the day the claim
is decided
25 25 22.5 25
Targets met in in both quarters despite the
increased contact due to migration to
universal credits for customers.
Ryan
Chalmers

Page 3

3
Q1 2025/26 Q2 2025/26
Performance Indicator Status Value Target Status Value Target Short
Trend
Long
Trend Note Owner
Time for processing
applications for
notifications of changes
of circumstances for
Housing Benefits from
the application receipt
date to the day the claim
is decided
4.9 5 5 5
Targets met in both quarters despite the
increased contact due to migration to
universal credits for customers.
Ryan
Chalmers
4. Our Council
Our workforce is resilient and skilled where digital technology supports service delivery for our residents
Action Status Progress Due Date Note Owner
Develop and implement wellbeing,
employee engagement, equality
and learning and development
plans to enable capabilities,
improve resilience and promotion
of a diverse workforce
31-Mar-
2026
Progressing as planned. We continue to develop
succession planning and build resilience in key areas
across our services. This is done in a number of ways,
including revised management structures, identifying
potential within current teams to address skills gaps,
mapping resilience for critical roles and tasks, including
cover arrangements for short-term absence, and
highlighting gaps where alternative approaches (e.g.
cross-service collaboration, short-term development
opportunities) may be required.
Laurence
Slavin

Page 4

4
Action Status Progress Due Date Note Owner
Develop and implement employee
life cycle plans in line with the
People First Strategy to attract and
retain the workforce
31-Mar-
2026
Progressing as planned. Responding to recruitment
challenges is difficult in the current climate with significant
financial pressures and a competitive job market.
However, through succession planning, we have sought
to develop career pathways and development
opportunities where possible.
Laurence
Slavin
Implement service review process
including role design, use of new
technology and new ways of
working to add resilience, address
gaps, and establish opportunities
for efficiencies
31-Mar-
2026
Progressing as planned. Implementation of the new
Finance structure is progressing and this will continue into
the next year as planned. A restructure of Corporate
Asset Management is also underway, looking at a range
of matters including staff development, career
progression, and a trainee post.
Laurence
Slavin
Develop and implement learning
and development plans and
development opportunities to
improve capabilities and resilience
within the workforce
31-Mar-
2026
Progressing as planned. Cross-skilling for resilience and
career progression has been implemented in Finance
Services and Corporate Asset Management. In Business
Support, given the financial pressures and a limited
training budget, focus will be on maximising internal
opportunities such as job shadowing, project-based
development, and knowledge sharing across teams.
Regular discussions with staff continue to identify and
support career conversations, ensuring staff feel valued
and engaged despite constrained resources.
Laurence
Slavin

Page 5

5
Our Council is adaptable and focused on delivering best value for our residents
Q1 2025/26 Q2 2025/26
Performance Indicator Status Value Target Status Value Target Short
Trend
Long
Trend Note Owner
Percentage of income due
from council tax received
by the end of the year %
29.58% 28% 54.5% 53%
Targets met in both quarters despite the
financial challenges faced by our
residents and changes to the Department
for Work and Pensions Fairer Repayment
Rate, which impact the Council Tax
recoveries taken towards debts.
Ryan
Chalmers
Current tenants' arrears as
a percentage of total rent
due %
9.3% 9% 8.55% 9%
While the target was narrowly missed in
Q1, the target was met in Q2 despite the
financial challenges faced by our tenants
and changes to the Department for Work
and Pensions Fairer Repayment Rate.  
Ryan
Chalmers
Gross rent arrears (all
tenants) as at 31 March
each year as a percentage
of rent due for the
reporting year
9.8% 9.3% 9.13% 9.3%
While the target was narrowly missed in
Q1, the target was met in Q2 despite the
financial challenges being faced by our
tenants and changes to the Department
for Work and Pensions Fairer Repayment
Rate.  
Ryan
Chalmers
Action Status Progress Due Date Note Owner
Progress the procurement of a
new Financial Management
System
31-Mar-
2026
Progressing as planned. Following the production of a
comprehensive specification for the system, we worked
with Corporate Procurement to identify the procurement
route and potential suppliers, arranged demonstrations,
and evaluated systems. We are now at the contract stage
with the preferred supplier.
Arun
Menon

Page 6

6
Action Status Progress Due Date Note Owner
Review ways of decreasing
corporate debt through continued
improvements to debt collection
processes in relation to sundry,
NDR, Council Tax and rent
31-Mar-
2026
Progressing as planned. We reviewed the process
between Housing and Corporate Debt in relation to rent
collection. Housing and the Corporate Debt Team
Leaders met regularly to review, discuss, and resolve any
issues and meetings are planned for the rest of the year.
The remaining milestones are on track to be completed
by their due dates in the second half of the year.
Ryan
Chalmers
Review ways to improve rent
collection rates in conjunction with
Housing and W4U
31-Mar-
2026
Progressing as planned. We reviewed the debt recovery
process following changes to the Government’s Fairer
Repayment Policy which reduced the maximum amount
that can be taken from benefits to pay for rent arrears,
from 25% to 15%.
Recoveries have reduced in line with the Fairer
Repayment Policy however the current reduction is
around 6% and we have a process in place to monitor
this for rest of the year.
We have also reviewed the process between Housing
and Corporate Debt in relation to rent collection as
outlined in the previous action.
The remaining milestones are on track to be completed
by their due dates in the second half of the year.
Ryan
Chalmers
Maximise automation opportunities
across the Council
31-Mar-
2026
Progressing as planned. We have completed several
automations in relation to a range of activities including
commercial waste invoices, sickness absence
notifications and school meals and clothing grants.
Arun
Menon

Page 7

7
Action Status Progress Due Date Note Owner
Further opportunities identified through workshops with all
Chief Officer areas are progressing.
Progress the disposal of key
strategic sites
31-Mar-
2026
Progressing as planned. We are on track to deliver
agreed capital receipts on key sites.
Michelle
Lynn
Progress the depot refurbishment
programme
31-Mar-
2026
Progressing as planned. Work has commenced onsite
and the programme of works is underway and on track.
Michelle
Lynn
Develop and implement plans and
support services to achieve the
asset related savings agreed by
Council
31-Mar-
2026
Progressing as planned. We have consulted with services
to support them to achieve the asset related savings due
in the first half of the year.
Michelle
Lynn
Review new Global Internal Audit
Standards and new CIPFA Code
of Practice and identify and
implement any actions to ensure
compliance
31-Mar-
2026
Milestones for this action are due to commence in the
second half of the year.
Andi
Priestman
Review eligibility for Council Tax
exemptions and identify potential
income due to the Council
31-Mar-
2026
Completed as planned. A report has been compiled with
the findings generating some good outcomes for the
Council in terms of income due.
Andi
Priestman
Risk Description Current
Assessment
Target
Assessment
Date
Reviewed Note Owner
Debt is not
recovered
efficiently or
effectively, with
inherent risk of
financial loss
The processes deployed in
collection of monies owed to the
Council are inefficient and
ineffective resulting in money
not collected on time or having
to be written off.
02-Oct-
2025
Risk remains unchanged from
year-end. We effectively
implement the amended
Corporate Debt Policy and ensure
income maximisation with
improvements to the automation
of collecting debt.
Ryan
Chalmers

Page 8

8
Risk Description Current
Assessment
Target
Assessment
Date
Reviewed Note Owner
Increase in the
level of rent
arrears due to
the level of
Welfare Reform
changes and
general state of
economy
The Council sees an increase in
its level of rent arrears due to
lower disposable income and
national changes to the national
benefits regime and the ongoing
economic position
02-Oct-
2025
Risk remains unchanged from
year-end. The risk remains high
due to the current cost of living
that is linked to increasing energy
costs, food costs and inflation.
Financial support and advice are
provided to those impacted by the
cost of living with arrangements
being reviewed as appropriate.
Ryan
Chalmers
Maintaining
Council Assets
that are fit for
purpose
The risk that the Council's
assets and facilities are not fully
fit for purpose with consequent
adverse impact on our ability to
deliver efficient and effective
services. Assets included in this
assessment are the Council’s
property portfolio.
08-Oct-
2025
The risk score remains low due to
the ongoing programme of capital
works. The Property Action Plan
2023-28, approved at
Infrastructure, Regeneration and
Economic Development
Committee in February 2023, will
monitor all requirements to
maintain the risk score.
Michelle
Lynn
Our residents are engaged and empowered
Action Status Progress Due Date Note Owner
Engage with relevant community
groups over the potential to lease
Dalmuir Golf Course
31-Mar-
2026
Completed as planned. Lease transaction to the existing
users was completed 1 July 2025.
Michelle
Lynn

Page 9

9
Strong financial governance and sustainable budget management (Service Objective)
Action Status Progress Due Date Note Owner
Develop and refine capital and
revenue reporting processes
31-Mar-
2026
Progressing as planned. We have developed the revenue
Budgetary Control Report to improve transparency within
the revenue report that is presented to Council and
committees. This new format will be presented to Council
at the end of October and relevant committees going
forward.
Carol
Alderson
Risk Description Current
Assessment
Target
Assessment
Date
Reviewed Note Owner
Failure to provide
a reasonable
level of
assurance on the
Council's
governance, risk
management and
internal control
procedures
Internal Audit is unable to provide
a reasonable level assurance on
the Council's governance, risk
management and internal control
arrangements.
07-Oct-
2025
The Internal Audit Annual Report and
Assurance Report for 2025/26 will be
presented to the June 2026 Audit
Committee.
Andi
Priestman
Failure to meet
statutory
deadlines for
external returns
(including HMRC)
and financial
statements
Finance Services failing to meet
statutory deadlines resulting in lost
revenue or penalty costs
02-Oct-
2025
The current assessment remains
unchanged from year-end. While the
risk remains high due to staff turnover,
difficulty recruiting staff with relevant
experience, and issues with business
continuity, there are a range of controls
in place to mitigate it.
Carol
Alderson

Page 10

10
Risk Description Current
Assessment
Target
Assessment
Date
Reviewed Note Owner
Financial
projections are
significantly
incorrect
Financial projections for both
capital and revenue are
significantly incorrect resulting in
insufficient reserves being held.
09-Oct-
2025
Information on projections is updated
on an ongoing basis. However, with
the volatility of the economy, and
general inflationary issues, the figures
are changing regularly. The Council's
Chief Financial Officer engages
regularly with the Directors of Finance
across all 32 Scottish Councils to
sense check material assumptions in
financial forecasts. Furthermore, there
is regular engagement with the
Council's appointed Treasury advisors
in relation to projected future changes
to bank interest rates.
Laurence
Slavin
Significant
financial funding
reductions /
limitations from
Scottish
Government
It is expected the Council will
continue to be faced with significant
real term funding reductions from
the national settlement. This is
based on local government
settlements in recent years (with
the exception of 2025/2026). This
coincides with a period where costs
and demographic pressures are
continuing to rise in relation to
social care, significant inflationary
increases and pay award pressures
linked to inflation. Whilst there are
ongoing discussions between the
Scottish Government and Local
09-Oct-
2025
Assumptions on future funding levels
and other material budget assumptions
are updated regularly and reported to
Council periodically throughout the
year. It is expected that future
settlement funding will be insufficient to
pay for current levels of service
delivery. Furthermore, it is expected
future local government settlements
will be a real terms reduction in local
government funding, including those
services delegated to the HSCP Board.
Laurence
Slavin

Page 11

11
Risk Description Current
Assessment
Target
Assessment
Date
Reviewed Note Owner
Government on reducing the ring
fencing of funding the reality is that
material elements of funding
remain ring fenced which
significantly restricts how the
Council can most effectively use
the funds made available to it.
Action Status
In Progress and on track
Completed
PI Status
Target narrowly missed
Target met or exceeded
Risk Status
Alert
Warning
OK
Long Term Trends
Improving
No change
Declining
Short Term Trends
Improving
No change
Declining

Page 12

No embedded text on this page.