Appendix 1: Regulatory & Regeneration Delivery Plan 2025/26 - Mid-year Progress
1. Our communities
Our residents’ health and wellbeing remain a priority
H1 2025/26
Performance Indicator Status Value Target Short
Trend
Long
Trend Note Owner
Percentage of planned
underage sales visits carried
out by Trading Standards to
premises registered on the
Scottish Government tobacco
and nicotine vapour product
retailers register
40% 95% N/A as new PI for
2025/26
Target missed. Low staffing numbers and higher priority
work have had an impact on our ability to meet this target.
We have very little intelligence on the sale of tobacco to
children. As we cannot commit our finite staffing resources
to underage sales of tobacco without evidence that it is a
problem, we have focused our limited resources to the
underage sale of nicotine vapour products.
Annemarie
Clelland
Action Status Progress Due Date Note Owner
Implement the requirements of the
Digital Markets, Competition and
Consumers Act 2024
31-Mar-
2026
Completed as planned. All officers have attended training
offered by the Chartered Trading Standards Institute and
we continue to attend working groups with colleagues to
ensure our application of the legislation is consistent
across the profession.
Annemarie
Clelland
Support and advise businesses in
relation to the new Tobacco &
Vapes Bill 2024
31-Mar-
2026
Trading Standards Officers have contacted all traders
registered with the Scottish Government to sell nicotine
vapour products to advise of the upcoming display ban.
We intended visiting premises with a low compliance
history to provide further guidance but this has been
challenging due to higher priority work. We will continue
to monitor complaints to identify non-compliance and will
act where required.
Annemarie
Clelland

Page 2

2
2. Our Environment
Our resources are used in an environmentally sustainable way
Action Status Progress Due Date Note Owner
Co-ordinate, monitor and report
the progress of the Council’s
Climate Change Action Plan for
2025/26
31-Mar-
2026
Progressing as planned. The Climate Change Action
Group meets regularly to progress and monitor this work
stream. To encourage wider engagement, service
specific meetings have been arranged and are now
underway.
Elaine
Troup
Develop the Local Heat and
Energy Efficiency Strategy
Delivery Plan
31-Mar-
2026
Progressing as planned. A draft of the Local Heat and
Energy Efficiency Delivery Plan is complete and under
review by colleagues before being taken forward for
board approval.
Elaine
Troup
Risk Description Current
Assessment
Target
Assessment
Date
Reviewed Note Owner
Inability to
reduce
carbon
footprint in
line with
targets
The risk that the Council will be
unable to achieve net zero emissions
by 2045, both in relation to mitigating
carbon emissions and adapting to the
impacts of climate change. Net zero
refers to achieving an overall balance
between emissions produced and
emissions taken out of the
atmosphere. This target has been
developed in a way that mirrors the
emission reduction trajectory set by
the Scottish Government in light of
the Climate Emergency.
08-Oct-2025
The risk of non-delivery of carbon
emissions targets remains significant to
reflect the increasing gap between
actual and target Co2 emissions. There
has been a long-term vacancy within
the Climate Change and Energy Team
that continues to impact the progress of
the Climate Change Action Plan. The
Climate Change and Energy Team
continue to work across the Council to
promote active participation from all
service areas and to support a
reduction of emissions.
Elaine
Troup

Page 3

3
Our neighbourhoods are sustainable and attractive
Action Status Progress Due Date Note Owner
Promote the next phases of
Queens Quay Housing
31-Mar-
2026
Progressing as planned. The Council continues to
discuss the development of the site with the landowner.
Part of the site is expected to be sold for housing within
this reporting year. The Planning Service has also
engaged with Scottish Government officials around the
development of the site as part of the Housing
Emergency workstreams.
Michael
Mulgrew;
Elaine
Troup
3. Our Economy
Our area has the infrastructure for sustainable and inclusive growth where businesses can flourish
Q1 2025/26 Q2 2025/26
Performance Indicator Status Value Target Status Value Target Short
Trend
Long
Trend Note Owner
Number of businesses
given advice and assistance
to start up through Business
Gateway
53 45 53 45
Targets met in both Q1 and Q2. On
track to meet year-end target of 180,
with 106 business start-ups supported
from 1 April until end of September
2025.
Gillian
Scholes
Action Status Progress Due Date Note Owner
Produce a planning focused
delivery programme to support key
regeneration sites and enable high
quality development to be
achieved on the ground
31-Mar-
2026
Progressing as planned. We have scoped out the
content of the programme with Economic Development
and we are drafting a document setting out how key
regeneration sites will be supported.
Michael
Mulgrew

Page 4

4
Action Status Progress Due Date Note Owner
Deliver key regeneration sites
across West Dunbartonshire
31-Mar-
2026
Progressing as planned.
Work to support the regeneration of the Exxon and
Scottish Marine Technology Park is progressing well.
The Council hosted a successful Scottish Marine
Technology Park workshop on 21 August 2025 with
representatives from the Scottish and UK governments,
Glasgow City Region, and Scottish Enterprise. Follow-on
work includes the development of an action plan that will
be circulated to all participants. The Council also
submitted two funding applications for the Regeneration
Capital Grant Fund (a Scottish Government fund which
supports locally developed regeneration projects) with
the Scottish Marine Technology Park progressing to the
second stage.
Work is also underway on the marketing of the Exxon
site and further updates will be provided to the project
board.
Elaine
Troup
Explore commercial opportunities
in our town centres and wider
regeneration sites
31-Mar-
2026
Progressing as planned.
The Artizan application for Planning Permission in
Principle is progressing and is expected to be
considered by the Council by the end of 2025 subject to
a response from a statutory consultee SEPA (Scottish
Environmental Protection Agency) being provided in
time.
Discussions on how to progress the Queens Quay
development in Clydebank are continuing with the
landowners, Scottish Government, and potential housing
developers.
Magda
Swider

Page 5

5
Action Status Progress Due Date Note Owner
Work on the development of a regeneration-led Tourism
& Heritage Strategy is progressing albeit slowly due to
resource issues.
Deliver business support
interventions through the UK
Shared Prosperity Fund 2025/26
31-Mar-
2026
Progressing as planned. Business grants available
through the UK Shared Prosperity Fund have been
promoted through social media, the council website and
directly to eligible businesses. The team are continuing
to appraise and process applications.
Gillian
Scholes
Support town centre revitalisation 31-Mar-
2026
Starting works on site at the Artizan in Dumbarton has
been delayed to allow more time to complete additional
site investigations. It is anticipated that the works will
start in Autumn/Winter 2025, with the date yet to be
confirmed.
Projects in Alexandria are progressing well. A contractor
for the Alexander Street works will be appointed in
November. The Mitchell Way/Main Street project is
progressing through RIBA (Royal Institute of British
Architects) Stage 2, the concept design stage, with
consultations with local stakeholders and community
ongoing. The designs will be finalised in November.
Clydebank is part of the UK Government’s Plan for
Neighbourhoods investment programme, providing up to
£20 million for eligible areas over a 10-year period. The
Neighbourhood Board in Clydebank is developing the
Regeneration Plan which will be submitted to the UK
Government by 28 November as part of the funding
process.
Magda
Swider

Page 6

6
Action Status Progress Due Date Note Owner
Develop a monitoring and
compliance framework for major
and strategic regeneration sites to
ensure compliance with approved
consents
31-Mar-
2026
This action is due to commence in December as
planned.
Michael
Mulgrew
Risk Description Current
Assessment
Target
Assessment
Date
Reviewed Note Owner
Failure to
deliver Queens
Quay
Masterplan
Following completion of Council
investment there is a risk the
housing plot sales do not
materialise in the next 3-7
years, with implications for the
return on investment and the
business case for the District
Heating Network.
01-Oct-
2025
Risk remains unchanged. Focus
continues on landowner agreeing
a housing proposal with a
potential developer. Delivery
embedded into workstreams to
promote development at site.
Michael
Mulgrew;
Elaine
Troup
Inability to meet
demands of
Council to
progress
regeneration
projects within
desired
timescales
The number and complexity of
regeneration projects is putting
considerable strain on the
resources available which can
be exacerbated by delays out
with the control of the service
and when pinch points on
different projects occur at
roughly the same time.
01-Oct-
2025
Risk remains unchanged.
Individual projects continue to
progress and are regularly
reviewed, reducing the likelihood
of undesirable outcomes.
Embedded into workstreams to
ensure sufficient resource to
support delivery of projects within
required timescales.
Michael
McDougall;
Michael
Mulgrew;
Elaine
Troup

Page 7

7
4. Our Council
Our workforce is resilient and skilled where digital technology supports service delivery for our residents
Action Status Progress Due Date Note Owner
Develop and implement employee
life cycle plans in line with the
People First Strategy to attract and
retain the workforce
31-Mar-
2026
Progressing as planned. We have implemented revised
structures in several teams following management
reviews, including Legal Services, Planning, Building
Standards and Environmental Health. These will be
complete once a number of vacancies are filled.
 Legal Services - Completed in part with the posts of
Licensing Assistant and Solicitor (Citizen & Regulator
Team) filled and two other vacant posts advertised.
 Planning – Competed and fully staffed in current
structure.
 Building Standards – A training post is going through
Job Evaluation and a technical support officer is
attending an HNC Architectural Technology course.
 Environmental Health - one of two Environmental
Health Officer posts have been filled with one
remaining vacancy.
Alan
Douglas
Implement service review process
including role design, use of new
technology and new ways of
working to add resilience, address
gaps, and establish opportunities
for efficiencies
31-Mar-
2026
Progressing as planned.
 Work is ongoing to review the management structure
in line with the Council’s Strategic Operating Model
principles to identify and address areas of non-
compliance, with new role profiles prepared.
 We continue to review the impact of saving options
and management adjustments identified as part of
Alan
Douglas

Page 8

8
Action Status Progress Due Date Note Owner
budget process for 2025/26 and implement any
required changes.
o Democratic Services - This has been completed
for Democratic Services, with minimum impact on
service delivery.
o Planning, Building Standards & Environmental
Health - Within Environmental Health, four saving
options were identified: Savings for review of
Environmental Health and Antonine Wall have
been achieved with minimal impact on overall
service delivery. Part of the Antonine Wall saving
was to be achieved by an increase in fee income.
Income looks to be on track but will not be known
until year end. Planning savings will not be
achieved as option was a backstop where a Lead
Planner post was not able to be filled but the
service was successful in recruitment. Combining
Dog and Pest Control posts is ongoing through
job evaluation and saving is expected to be
achieved in line with target. Full operational
impact will not be known until year end.
o Legal Services & Trading Standards - While the
Records Management Officer retired in late July,
the impact will not be known until year-end. Work
is ongoing to deliver Trading Standards saving
option.
 Building Standards has developed a revised structure
that supports career pathways. Further details are set
out in the action below.

Page 9

9
Action Status Progress Due Date Note Owner
Develop and implement learning
and development plans and
development opportunities to
improve capabilities and resilience
within the workforce
31-Mar-
2026
Completed as planned. Relating specifically to Building
Standards, we have identified learning opportunities that
support the development of skills and knowledge
required for hard to fill posts in the team. This has been
achieved through a revised structure that supports
career pathways. The new structure, agreed by the
Strategic Resources & Recovery Group, is now being
implemented in conjunction with Human Resources and
Job Evaluation. Building Standards has also secured a
funded place on an HNC Architectural Technology
course for an officer from the technical support team.
Alan
Douglas
Our Council is adaptable and focused on delivering best value for our residents
H1 2025/26
Performance Indicator Status Value Target Short
Trend
Long
Trend Note Owner
Planning Applications
(Major Developments -
Without Processing
Agreement): Average
number of weeks to
decision
N/A N/A 16 N/A as new period
for 2025/26
Michael
Mulgrew
Planning Applications
(Major Developments –
With Processing
Agreements):  Percentage
decided within agreed
target
N/A N/A 80% N/A as new PI for
2025/26
No such applications were processed in this period.
Michael
Mulgrew

Page 10

10
H1 2025/26
Performance Indicator Status Value Target Short
Trend
Long
Trend Note Owner
Planning Applications
(Locals - Householder):
Average number of weeks
to decision
7.84 8 N/A as new period
for 2025/26 Target met. Michael
Mulgrew
Planning Applications
(Locals – Householder):
Percentage decided within
statutory 8-week timescale
88.6% 80% N/A as new PI for
2025/26 Target met. Michael
Mulgrew
Planning Applications
(Other Locals): Average
number of weeks to
decision
12.9 8 N/A as new period
for 2025/26
Michael
Mulgrew
Planning Applications
(Other Locals): Percentage
decided within statutory 8-
week timescale
43.8% 80% N/A as new PI for
2025/26
Planning has been impacted by both planned, and
unplanned, back-office downtime that has impacted
local performance. The service has also been working
to clear a backlog of older applications as we continue
to implement a project management approach. Michael
Mulgrew
Cash savings achieved
from procurement activity £112,432 £200,000
Although the target was missed at mid-year, we expect
to achieve the annual target of £400,000 as a higher
proportion of contracts are due in the second half of the
year.
Iain Skene

Page 11

11
Q1 2025/26 Q2 2025/26
Performance Indicator Status Value Target Status Value Target Short
Trend
Long
Trend Note Owner
Percentage of building
warrant applications
responded to within 20
working days
69.31% 95% N/A Not yet
available 95% N/A
Building Standards is currently impacted
by a severe resourcing issue.
Performance is expected to recover by
Q3 due to vacant posts being filled in
September. Data for Q2 is not available
until November 2025.
Judi
Ferguson
Action Status Progress Due Date Note Owner
Prepare a succession plan to
recruit and replace the Manager of
Democratic and Registration
Services post
31-Jan-
2026
Progressing as planned. Job profile has been reviewed
and submitted to job evaluation team.
George
Hawthorn
Continue to develop the 20-minute
mapping tool for use at both local
and regional levels
31-Mar-
2026
Progressing as planned. We continue to use the tool and
explore ways it can be developed as part of the
Geographic Information System and Local Development
Plan workstreams.
Michael
Mulgrew
Prepare a robust evidence report
for the next Local Development
Plan (LDP3) for submission for
Gatecheck to Scottish Government
Planning and Environmental
Appeals Division
31-Mar-
2026
Progressing as planned. We have reviewed the Local
Development Plan work plan and revised timelines and
the Planning Committee approved the new Development
Plan Scheme in September. The Scheme has now been
published on the Council's website.
Michael
Mulgrew
Continue to promote and support
communities in the preparation of
Local Place Plans
31-Mar-
2026
Progressing as planned. Officers continue to engage and
support communities in preparing Local Place Plans.
Michael
Mulgrew

Page 12

12
Action Status Progress Due Date Note Owner
Develop a plan to ensure
compliance with the new Building
Standards Regulations is
implemented
31-Mar-
2026
Local authorities are awaiting new guidance on Building
Standards from the Scottish Government. This action will
be taken forward once received.
Michael
Mulgrew
Progress the introduction of a new
document management system for
Planning and Building Standards
31-Mar-
2026
Progressing as planned. The system has been procured
and work is underway to establish a project board and
develop an implementation plan for 2025/26 and
2026/27.
Michael
Mulgrew
Provide procurement advice,
guidance, and support on non-
complex procurement for low
contractual risk projects
31-Mar-
2026
Progressing as planned with support provided to service
areas as and when required. Iain Skene
Continue to implement the key
deliverables from the Procurement
Improvement Plan focusing on
reporting improvements within
WeBuy purchase to pay system
31-Mar-
2026
Progressing as planned. We have completed a number
of reporting improvements in the WeBuy purchase to pay
system.
Iain Skene
Provide legal services to the
Council and West Dunbartonshire
Energy LLP in relation to heat
supply agreements and network
supply contracts
31-Mar-
2026
Progressing as planned. Legal services continue to
provide advice to the Council and West Dunbartonshire
Energy LLP in relation to connecting a new client to the
network.
Michael
McDougall
Continue to provide high quality
and timely legal support across all
Council services
31-Mar-
2026
Progressing as planned. Legal Services continue to
provide support to all Council services as well as the
Health & Social Care Partnership and the Leisure Trust
in relation to a number of matters that contribute towards
the Council's strategic priorities and protect the Council's
interests in a range of matters. For example:
Michael
McDougall

Page 13

13
Action Status Progress Due Date Note Owner
 Issued Notice of confirmation of the proposed
Gruggies Burn Flood Alleviation Scheme.
 Legal support on decriminalisation of car parking.
 Legal support on the development of Scottish Marine
Technology Park.
Review processes and procedures
within Legal Services’ Commercial
& Place and Citizen & Regulatory
teams
31-Mar-
2026
Progressing as planned. However, due to vacancy, the
Section Head of commercial & Place is continuing to
assist with court work which will limit time to progress
this in the second half of the year.
Michael
McDougall
Review workstreams and
procedures within Environmental
Health
31-Mar-
2026
Progressing as planned. We continue to review
workstreams and procedures across Environmental
Heath to improve efficiencies as well as staff and
customer satisfaction.
Michael
Mulgrew
Review the planning preapplication
process
31-Mar-
2026
Progressing as planned. Benchmarking has been carried
out with other local authorities to inform our review with
further analysis due be conducted in the coming months.
It is anticipated that the revised process will be
implemented in 2026/27.
Michael
Mulgrew
Work with other Steering Group
partners to support Historic
Environment Scotland to finalise a
new Antonine Wall Management
Plan
31-Mar-
2026
Progressing as planned. We continue to work with our
Steering Group partners on the Antonine Wall
Management Plan.
Michael
Mulgrew

Page 14

14
Risk Description Current
Assessment
Target
Assessment
Date
Reviewed Note Owner
Failure to monitor
and enforce
regulatory areas
with public risk
The Council fails to
comply with statutory
regulatory duties in
respect of
environmental health,
trading standards and
licensing laws
01-Oct-2025
The risk assessment remains unchanged and
low due to mitigating actions.
Licensing Standards Officers continue to
engage in a pro-active programme of
inspections. Reactive work is driven by
complaints and applications received. They
also engage with Scottish Society of Local
Authority Lawyers and Administrators,
Licensing Forum, and other bodies to assist
with horizon scanning to identify emerging
issues.
Within Trading Standards, low staffing
numbers and a long-term absence, as well as
competing priorities, continue to put pressure
on the service. This will be exacerbated when
a full-time Trading Standards Officer post is
deleted from the structure. Where possible,
our high-risk routine inspections continue as
well as our reactive work into complaints and
intelligence received but other areas of
proactive work prove difficult to complete.
Within Environmental Health low staffing
numbers and competing priorities continue to
put pressure on the service. All statutory work
is being prioritised but continuing reduced
resources, including one vacancy and a long-
term absence, will likely impact this year.
Annemarie
Clelland;
Michael
McDougall;
Eilidh Paton

Page 15

15
Risk Description Current
Assessment
Target
Assessment
Date
Reviewed Note Owner
Failure to
adequately
respond to an
emergency
situation such as a
multiple fatality
workplace
accident, outbreak
of food borne
communicable
disease, a major
public health
incident or
pandemic
There is a national
shortage of qualified
staff in Environmental
Health, across
Scotland. This impacts
on West
Dunbartonshire
Council. Vacancy
levels at WDC might
impact on our ability to
respond to
emergencies.
01-Oct-2025
The risk score is unchanged since year-end.
Due to a reduction in staff resources as a
result of budget savings and difficulty
recruiting qualified Environment Health
Officers, management and team
responsibilities have significantly increased as
a result of service restructure. We will
continue monitor the impact.
Eilidh Paton
Inability to recruit
successfully to
enable
performance to be
maintained
There is a current
issue with recruitment
of qualified staff in
various parts of the
service.
01-Oct-2025
Whilst there has been some successful
recruitment within planning and environmental
health there remains an overall risk due to the
number of vacancies within Building
Standards and Environmental Health.
Michael
Mulgrew;
Eilidh Paton
Failure to secure
best value of
procurement
spend and ensure
compliance with
financial
regulations
Improved procurement
management process,
contract strategies,
planning, monitoring,
and reporting in
collaboration with
services will continue
to mitigate against
non-compliant
procurement spend
01-Oct-2025
There are a number of actions and strategies
in place to deliver best value in procurement.
However, the transfer of low complexity
procurement to service areas when utilising a
framework agreement may be increasing the
risk. The risk assessment therefore remains
high but unchanged. Further training and
guidance for services has been rolled out.
Iain Skene

Page 16

16
Risk Description Current
Assessment
Target
Assessment
Date
Reviewed Note Owner
Failure to continue
to achieve
increased savings
from procurement
activity
As second or third
generation revenue
contracts seldom
deliver the same cost
savings as first
generation, the
contract strategies
need to focus on
governance, operating
models, total cost of
ownership, service
quality and innovation
01-Oct-2025
Reduction in staff due to previous Council
measures to address the budget gap and
global supply chain issues that impact directly
on price means that risks to savings will
increase. There are also a number of market
factors which are difficult to mitigate -
increases to employers’ national insurance,
high inflation, and the potential impact of
climate change. As a result of these factors,
the risk remains unchanged.
Iain Skene
Our residents are engaged and empowered
Q1 2025/26 Q2 2025/26
Performance Indicator Status Value Target Status Value Target Short
Trend
Long
Trend Note Owner
Percentage of Council and
Committee minutes
produced within 3 clear
working days of the meeting
100% 98% 100% 98%
Q1 and Q2 targets both met with all
Council and committee minutes
produced within the timescale
Carol-Ann
Burns
Percentage of committee
agendas published within
standing order timescales
100% 99% 100% 99%
Q1 and Q2 targets both met with all
committee agendas published within
standing order timescales.
Carol-Ann
Burns

Page 17

17
Action Status Progress Due
Date Note Owner
Implement the various requirements
of the Scottish Elections
(Representation and Reform) Act
31-Mar-
2026
Progressing as planned. The project plan has been
updated to include new/additional actions arising from the
new legislation.
George
Hawthorn
Plan for the Scottish Parliamentary
Elections for the Dumbarton and
Clydebank and Milngavie
Constituencies
31-Mar-
2026
Progressing as planned. Project plan has been drafted to
include changes to legislation.
George
Hawthorn
Conduct an interim review of the
Polling Scheme in West
Dunbartonshire
31-Oct-
2025
Progressing as planned. Public consultation on Returning
Officer's Representations is underway.
George
Hawthorn
Continue the development of
Community Planning
31-Mar-
2026
Progressing as planned. Work on the development of
Community Planning has progressed well during 2025/26.
A review of Delivery Improvement Groups is now complete
and a recommendations paper will be submitted to the
Management Board in November. This includes
recommendations on partnership reporting.
Elaine
Troup
Continue to contribute to the
Community Learning and
Development Plan 2024/27
31-Mar-
2026
Progressing as planned. The Communities Team continues
to deliver community development support to groups
across West Dunbartonshire to maximise their impact. This
can be through support to secure external funding,
promotion or by developing skills and improving
governance arrangements. The team is represented on the
Community Development Alliance and plays a key role in
supporting communities through the development of
Locality Plans.
Colin Smith;
Elaine
Troup

Page 18

18
Action Status Progress Due
Date Note Owner
The Communities Team successfully delivered a
programme of engagement for the Clydebank
Neighbourhood Board in support of their Regeneration Plan
due to be submitted to the UK Government by 28th
November as part of their Plan for Neighbourhoods
investment programme.
Conclude the Cash First Project
including evaluation
31-Mar-
2026
Progressing as planned. This test of change project has
been delivered jointly by the Communities Team and
Working 4U. It has been a very successful project with the
available funding reaching those most in need through a
network of trusted partner referrals. The demand for the
project resulted in additional funding from the Scottish
Government during 2024/25. All funds have now been
exhausted and both teams will continue to liaise with the
Scottish Government and their partners to conclude the
evaluation process.
Elaine
Troup
Risk Description Current
Assessment
Target
Assessment
Date
Reviewed Note Owner
Engaging
positively
with
Residents,
Communities
&
Partnerships
The risk that the Council
fails to adequately engage,
establish and maintain
positive relationships with
local residents and
communities in addition to
partnership bodies.
08-Oct-2025
This risk has been reviewed and reduced to
reflect the increase in community engagement
being undertaken by the Community Planning
Partnership, supported by the Communities
Team and other partners. While the
Communities Team continue to deliver
community development work, this has had
more of a focus on community planning related
work through the delivery of a pilot project (on-
going), early engagement with communities
Colin Smith;
Elaine
Troup

Page 19

19
Risk Description Current
Assessment
Target
Assessment
Date
Reviewed Note Owner
regarding locality plans, and also the work to
support the Clydebank Neighbourhood Board.
With this approach continuing, the risk of not
engaging with communities can be reduced.
Action Status
Not on track
In Progress and on track
Completed
PI Status
Target significantly missed
Target met or exceeded