WEST DUNBARTONSHIRE COUNCIL 
Report by Chief Officer - Resources 
Corporate Services Committee: 21 May 2025 
Subject:  Cost of Living – Capital Fund 
1. PURPOSE 
1.1 To report to members on the closure of the Cost-of-Living Capital Fund
(the fund) and report on the groups it has supported since it was
established in June 2022.    
2. RECOMMENDATIONS 
2.1 Members are asked to: 
a) note the level of support provided via the Cost-of-Living Capital
Fund 
b) agree the remaining £10,379 be removed from the capital plan with
this to be formally agreed by full Council. 
3. BACKGROUND 
3.1 At a meeting of West Dunbartonshire Council on 22 June 2022, an
emergency item of business was considered and approved by
members in relation to the cost-of-living crisis. This made £1,000,000 of
capital funds available to support Council and community organisations
with capital costs for cost-of-living initiatives. 
3.2 In order to progress the initiatives set out in the motion and other
developing action in relation to tackling the impact of the cost of living
crisis, it was decided the previously established cross-party Cost of
Living Working Group (the Working Group) would be the most
appropriate forum to discuss and monitor progress, emerging issues
and proposed activity. 
3.3 The June 2022 motion also asked that a process be developed to
review applications for capital funding to be submitted through the
Working Group for consideration and then passed to an appropriate
committee or Council for approval.  On 26 October 2022 full Council
approved the guidance and application form to support the Fund and
the process to manage the Fund, including delegating powers to the
Chief Officer – Resources to approve or reject applications to the Fund.
The agreed application approval process can be summarised as
follows: 
ITEM 16

Page 2

1. Applicant applies via Council website
2. Finance Officer reviews application to ensure it meets the criteria
of the Fund and application is complete
3. Chief Officer – Resources circulates a summary of application to
the Working Group with his recommendation for
acceptance/rejection for their consideration
4. Working Group provide feedback and ask any questions
regarding the application.
5. Final decision on whether to approve funding delegated to the
Chief Officer - Resources. 
4. MAIN ISSUES 
4.1 Over the period November 2022 – March 2025 a total of 55 applications
were received and three allocations were made to reflect Council
decisions. This is summarised in Exhibit 1 with more detail provided in the
subsequent paragraphs. 
Exhibit 1 – Summarised Use of Cost-of-Living Capital Fund
Status Number £
Approved in Full 26 484,915
Partially Approved 10 204,153
Returned Unspent  (30,068)
Total Paid Out (Para 4.2)  659,000
Council Decisions (Para 4.3) 5 330,621
Rejected 19 0
Total 60 989,621
Remaining Fund  10,379 
4.2 Successful Applicants (£659,000) 
Exhibit 2 sets out the 36 groups either fully or partially supported, the
amount they were awarded and a summary of the purpose of the award. 
Exhibit 2 – Successful Applicants 
Group Purpose  Award
(£)
1 West Dunbartonshire
Community Foodshare
Van 19,413
2 Clydebank Men's Shed Replacement saws and ancillary
equipment
4,100
3 Clyde Shopmobility Computer equipment, mobility
scooters and mobility aids
6,870
4 Carers of West
Dunbartonshire
Laptop, projector and accessories 3,309
5 Dalmuir Church Drop in
Pantry
Industrial cooker, dishwashers and
laptop
7,643
6 Faifley Community Council Van 20,000

Page 3

7 Daniel's Wish Sensory equipment 9,143
8 Lomond and Clyde Care &
Repair
Van 22,000
9 Awestruck Academy Upgrade nursery, kitchen, IT suite
and leisure equipment
29,589
10 Mini Messy Monsters Sensory equipment 3,800
11 Our Warriors Sensory equipment 5,000
12 Tullochan Commercial range cooker and
ventilation for Common Good Café
9,663
13 Y Sort It Renew windows in gym hall, stage
and activity area
15,120
14 Dumbarton Area Council on
Alcohol
Double glazing, central heating,
rewiring and flooring
39,644
15 BenView Resource Centre A new boiler (subsequently
returned as unspent)
30,000
16 West Dunbartonshire
Community Foodshare
Fund a new boiler 5,610
17 Old Kilpatrick Food Parcels Kitchen development and new
toilets.  In addition, OKFP applied
for £11,000 of funding for
architect's fees and supervised
project management. Working
Group agreed the Council will
provide these services on a pro-
bono basis to avoid OKFP
incurring these costs.
44,000
18 Dalmuir Barclay Church
Pantry
Purchase a van (£68 returned as
unspent)
20,000
19 Lomond Clyde Care & Repair Purchase a van 22,903
20 Clydebank Asbestos Group Repair meeting hub 37,560
21 Golden Friendships Air conditioning unit 20,000
22 Clydebank Men’s Shed Install a dust processor system 16,500
23 Lomond Parish Church Establish a community pantry 29,400
24 Alternatives Improve the kitchen and to provide
a community space in Dalmuir
Community Café
5,599
25 Haldane Youth Services To refurbish current rooms and
provide a warm space for the
community to come for training and
internet access
27,051
26 Kinship Care To fund unit refurbishment,
computer / gaming equipment,
furnishings and kitchen equipment
27,500
27 Flourishing Faifley Purchase a van 20,846
28 Carers of West
Dunbartonshire
To refurbish premises 29,774
29 Dalmuir Barclay Church
Pantry Kitchen refurbishment 16,330
30
The Recycle Room
Refurbish the building and provide
a van 37,400

Page 4

31
OKFP
Refurbish windows, fire doors,
toilets and heating 17,900
32
Inler Park Trust
To rebuild gym and upgrade 
building & heating  38,000
33
BenView Resource Centre
To enhance warm hub
environment 8,170
34 Blue Triangle To purchase equipment for a social
space
4,998
35 Alternatives To fund window replacement 1,435
36 Loch Lomond Rugby Club Install Kitchen, flooring,
appliances, furnishings, install
double glazing and roller shutters
32,798 
Returned Unspent Amount  (30,068) 
Total   659,000 
4.3 Council Decisions (£332,000) 
When agreeing the 2024/25 and 2025/26 Council budgets, Council
agreed, in relation to the Fund to add three new initiatives. 
2024/25 - £150,000 General Capital Community Success Fund: The
Council agreed to establish this capital fund using the Cost-of-Living
Capital monies and have it available to support community groups for
capital expenditure. This investment has helped ensure groups are in a
practical position to move forward with lease arrangements and
ensuring future asset transfers are viable and sustainable in the long
term.  As at April 2025 this fund has supported three groups to the cost
of £148,621 leaving a balance of £1,379 which can be removed from
the capital plan.  This is summarised below. 
1. Antonine Sports, Glenhead Community Centre – £107,381 
Enabling works to support group in preparing to take on asset.  This
covered minor repairs, compliance upgrades and essential upgrades 
needed to bring the asset up to a useable standard.  Also a condition
surveys was carried out as these are the critical first step in helping
community groups make informed decisions about whether an asset
transfer is viable.  Most groups do not have the resources or
technical expertise to commission surveys, and without this
information, they may take on significant unknown risks.  By funding
these surveys up front, we have derisked the process and given
groups the confidence and evidence they need to develop strong
business plans and secure funding and support 
2. Old Kilpatrick Food Parcels - £7,510 
Costs associated with intruder alarm repair and a condition survey. 
3. West Dunbartonshire Activity Centre - £33,730
Enabling works to support group in preparing to take on assets.  This
covered a condition survey, minor repairs, compliance upgrades and
essential upgrades

Page 5

needed to bring the asset up to a useable standard.   
2024/25 - £32,000 Building improvements Old Kilpatrick Food
Parcels - Napier Hall: The £32,000 is to fund building works including
to supply and fit utilities, gas, electricity and plumbing. This funding has
been provided to the group and the works are ongoing. 
2025/26 - £150,000 to Flourishing Faifley: contribution towards a new
4G Football Pitch at Faifley Knowes. 
4.4 Applications Rejected 
The reasons for the 19 applications where no funding was awarded can
be summarised as: 
1. No clear link to cost-of-living crisis (8)
2. Application not capital in nature (5)
3. Application withdrawn by applicant (2)
4. Applicant referred on to Energy Fund (2)
5. Application from a private citizen (1)
6. Application met criteria but already well supported by fund (1) 
4.5 Summary and Recommendation 
With the exception of a small balance of £10,379, the £1 million set aside
for the Cost-of-Living Capital Fund has been fully expended or committed.
It has helped support 36 community groups and provided further support
to five groups through the funds set aside by Council decisions made
when agreeing the 2024/25 and 2025/26 budgets.  It is recommended that
Corporate Services note the level of support provided via the Cost-of-
Living Capital Fund and agree that the remaining £10,379 be removed
from the capital plan.  This would be formally agreed by Council when the
next Council capital budgetary control report is presented. 
5. PEOPLE IMPLICATIONS 
5.1 None directly from this report. 
6. FINANCIAL AND PROCUREMENT IMPLICATIONS 
6.1 Report summarises the use of £1m of capital funds. 
7. RISK ANALYSIS 
7.1 None directly from this report 
8. EQUALITIES IMPACT ASSESSMENT (EIA) 
8.1 None directly from this report

Page 6

9. CONSULTATION 
9.1 The views of all the Cost-of-Living Working Group have been requested
on this report and feedback incorporated herein. 
10. STRATEGIC ASSESSMENT 
10.1 The recommendation in this report supports the delivery of the Council
Strategic Plan and in particular the achievement of the following priorities:
o Our Communities – Resilient and Thriving;
o Our Council – Inclusive and Adaptable 
Laurence Slavin
Chief Officer - Resources
Date:   15 April 2025 
Person to Contact: Laurence Slavin, Chief Officer - Resources 
E-mail: laurence.slavin@west-dunbarton.gov.uk 
Background Papers
Council Motion – 22 June 2022
Council Report - Cost of Living – Capital Fund – 26 October 2022
Council Budget Report – 06 March 2024
Council Budget Report – 05 March 2025