WEST DUNBARTONSHIRE COUNCIL
Report by the Chief Officer – Resources
Corporate Services Committee – 21 May 2025
___________________________________________________________________ 
Subject: Corporate Services Capital Budgetary Control Report to 31 January 2025  
(Period 10). 
1. Purpose 
1.1 This report provides an update on the Corporate Services capital programme
to 31 January 2025. 
2. Recommendations 
2.1 Committee is asked to: 
i) Note the current position of the 2024/25 capital budget for Corporate
Services 
ii) Note that the project life total is currently on track. 
3. Background 
3.1 On 6 March 2024 the Council approved the updated General Services Capital
Plan for 2024/2025 to 2032/33.  The three years from 2024/25 to 2026/27
were approved in detail with the remaining years being indicative. The budget
agreed under the auspice of Corporate Services Committee was £3.264m for
2024/25 and £28.560m for the project life budget. 
4. Main Issues 
4.1 Exhibit 1 sets out the revised capital budget at period 7 as reported to
Committee 5 February 2025. 
Exhibit 1: Revised Capital Budget as at 31 January 2025. 
2024/25
(£m)
Project
Life (£m)
Corporate Services Capital Budget Agreed 6
March 2024. 3.624 28.560
Updates reported to Committee on 14 August
and 6 November 2024. 0.432 0.390
ITEM 15

Page 2

Reprofiling reported to Committee on 6
November 2024. 0.123 0.000
Replacement of Council’s financial ledger
system. 0.100 1.000
New Approved Budget at Period 7  4.279  29.950 
4.2 Progress against the 2024/25 capital plan is detailed in: 
Appendix 1 – Project Life Summary by Chief Officer 
Appendix 2 – Projects Off Track – not required for period 10 as there are no
off-track projects to report 
Appendix 3 – Changes to Project Profiles at P10 
Appendix 4 – All Projects 
4.3  The overall program summary report at Appendix 1 shows that planned
expenditure against the budget agreed 6 March 2024 is on track. 
4.4  Appendix 4 shows all projects with approval in year and project life budgets as
well as anticipated expenditure. It highlights that the 2024/25 budget is
£4.279m with current forecast spend of £4. 164m.The spend as at period 10 is
£1.532m (36.79%) of the current forecast spend of £4.164m. 
4.5 Exhibit 2 sets out the revised capital budget at period 10 following approval at
Council on 5 March 2025 as part of the new capital programme. 
Exhibit 2: Revised Capital Budget 
2024/25
(£m)
Project
Life (£m)
Revised Capital Budget as at 31 January
2025  4.279  29.950
Updates agreed as part of Capital Plan 5 March
2025.  0 0.004
Reprofiling of Projects reported to Council 5
March 2025 (see appendix 3) (0.080) 0
Underspend – RES 2 Cash Receipting Systems
Enhancements (0.025) (0.025)
Underspend – RES 4 Agresso Development (0.010) (0.010)
Revised Capital Budget Period 10. 4.164 29.919 
5. Option Appraisal 
5.1 No option appraisal was required for this report.

Page 3

6. People Implications 
6.1 There are no people implications. 
7. Financial and Procurement Implications 
7.1 The report notes the projected in-year financial position for capital budgets. 
8. Risk Analysis 
8.1 The main risks are as follows: 
(a) The reported variances should be viewed in the knowledge that there
are a number of variable factors which could arise between now and 31
March which could affect the year end results for capital budgets. 
(b) As a consequence of current market conditions, inflation is at an all-time
high and interest rates continue to be volatile. To forecast for the full
year costs budget assumptions have been required. These assumptions
continue to change regularly and therefore it is likely the projected year
end budgetary position will change from that reported. 
9. Equalities Impact Assessment (EIA) 
9.1 No equalities impact assessment was required in relation to this report. 
10. Environmental Sustainability 
10.1 No assessment of environmental sustainability was required in relation to this
report. 
11. Consultation 
11.1 All services involved in delivering the capital budgets have been consulted in
the compilation of this report. 
12. Strategic Assessment 
12.1 Proper budgetary control and sound financial practice are cornerstones
of good governance and support Council and officers to pursue the
strategic priorities of the Council’s current Strategic Plan. This report
forms part of the financial governance of the Council. 
Laurence Slavin
Chief Officer – Resources
Date: 06 May 2025
________________ 
Person to Contact: Adrian Gray 
Council Offices, Church Street, Dumbarton

Page 4

E-mail: adrian.gray@west-dunbarton.gov.uk 
Appendices: Appendix 1 -  Project Life Summary 
Appendix 2 -  Projects Off Track – not required at P10 
Appendix 3 - Reprofiled Projects 
Appendix 4 -  Details of all Projects. 
Background Papers:  General Services Capital Plan Update - Council 6 March 
2024.      
Capital Monitoring Report – Council 26 March 2025. 
Wards Affected           All Wards