Appendix 1 - CCF Delivery Plan Year-end Progress 24/25
1. Our Communities
Objective 1. Our neighbourhoods are safe, resilient and inclusive
2023/24 2024/25
Performance Indicator
Value Status Value Target Short Trend Long Trend Note
Owner
Number of adults and young people participating in
engagement activity through Community
Development activity (Community Dev' only)
New PI for
24/25 683 600
Target exceeded. The level of
engagement activity fluctuates across
the year with a dip in engagement
figures in Quarter 3 only. The
remaining quarters saw the level of
engagement exceed the target set.
This included a high level of
engagement through the planned
Community Soup events that were
successfully delivered as part of the
UK Shared Prosperity Fund
Elaine Troup

Page 2

2
Action Status Progress Due Date Note Owner
Support community planning partners to
develop and deliver two CP events to support
increased participation
31-Mar-2025
Action overdue. The 2024/25 proposed approach for
the Community Planning Partnership has delivered
one successful community event and has the second
event in development for delivery in May 2025. This
action will continue into 2025/26 for completion.
Elaine Troup
Risk Description Current
Assessment Target Assessment Date Reviewed Note Owner
Engaging positively with
Residents, Communities &
Partnerships
The risk that the Council fails to
adequately engage, establish and
maintain positive relationships with local
residents and communities in addition to
partnership bodies.
10-Apr-2025
The on-going financial challenges
facing local authorities has had an
impact on budgets available to support
the active engagement with local
residents, communities and
partnerships.
This has resulted in an increase to the
risk matrix. Likelihood increased from
1 to 2.
Elaine Troup
Objective 2. Our residents health and wellbeing remains a priority
2023/24 2024/25
Performance Indicator
Value Status Value Target Short Trend Long Trend Note
Owner
% of pupil medical dietary requests met 100% 100% 100% Target met. Sharon Jump
% of pupils who take up free school meals ( P1-7 ) 75% 76% 75% Target met. Sharon Jump
Action Status Progress Due Date Note Owner
Increase the number of locations offering
access to free period products 31-Mar-2025
Completed as planned. Additional locations in
community owned premises have been identified,
promotion will continue within communities to
Elaine Troup

Page 3

3
Action Status Progress Due Date Note Owner
ensure availability of products in areas of most
need. Going forward Facilities Management will
ensure stocks are maintained in community
locations.
Review the outputs from Good Food Nation
Consultation process. 31-Mar-2025
Action overdue. The Good Food Nation requirements
will apply across a number of services in the
Council. Further detail awaited from Scottish
Government following completion of review of full
consultation responses. This action will carry over to
25/26.
Sharon Jump
Objective 3. Our residents are supported to increase life and learning skills
2023/24 2024/25
Performance Indicator
Value Status Value Target Short Trend Long Trend Note
Owner
Total number of library issues (Physical and e-
Issues) 241,783 249,379 210,000 Target exceeded and will be
increased to 220,000 for 25/26. Emma Eremin
Total number of visits to museums and heritage
centres (virtual & in person) 108,117 110,979 79,884 Target exceeded Target will be
increased to 106,500 for 25/26. Lauren Crooks
Total number of library visits (physical and virtual) 431,449 474,519 360,000 Target exceeded and will be
increased to 385,000 for 25/26. Emma Eremin
% Residents satisfied with Libraries 91% 75% 90%
Target significantly missed.
Announcements to changes in library
services continues to have an impact
on satisfaction. Increased activities
and awareness of programmes
running in recently collocated
branches should support improved
satisfaction
Emma Eremin
% Satisfaction with museums & galleries 89% 81% 88%
Target marginally missed. Progress of
Glencairn, Clydebank Heritage hub
and conversion of Dumbarton library
should support improved satisfaction.
Lauren Crooks

Page 4

4
Action Status Progress Due Date Note Owner
Progress funding application to support heritage
activity programme for Glencairn House
(including supporting the progress of the
opening)
31-Mar-2025
Action completed as planned. The original
completion date of Glencairn House was March 2024
and is now scheduled for summer 2025. In 2025/26
we will continue to support this progress and will
further progress the external funding to support a
programme of heritage engagement for Glencairn
House.
Lauren Crooks
Progress storage review and planning for future
decant of WDC collections to Strathleven 31-Mar-2025
Action overdue. Given the move to Strathleven will
now not be taking place until 2026 the team will be
revising plans to account for this in line with the
assets phasing programme. This action will carry
over to 2025/26. 
Lauren Crooks
Support progress of plan for opening of
Clydebank Heritage Hub 31-Mar-2025
Action completed as planned.  Return of Local
History & Archive collections back to Clydebank has
been completed. The enabling works are currently
underway and progressing well. The next stage will
be the museum fit out on site over 2025/26. The
funding application submitted by Arts and Heritage
to Museums Galleries Scotland for a museums
development grant to support programme activity in
the arts and heritage activity on site on the opening
of the new space has been successful.
Lauren Crooks
Support progress of new collections
management software. (MODES) 31-Mar-2025
Action completed as planned. Following completion
of the back-end build of the MODES system for WDC
collections, providing access to the new system for
the Arts & Heritage team. Work is now underway on
the front-end build for the MODES platform currently
being designed by Orangeleaf which will provide
public access early in 2025/26.
Lauren Crooks
Continue to delivery youth learning and
community-based learning and participation
opportunities.
31-Mar-2025
Action completed as planned. Year 1 Actions have
been identified and developed with partners through
The Youth Alliance and Community Development
Alliance (Empowered DIG).  Ownership and
reporting on actions will be shared across the
partnerships with future reporting to Community
Planning Management Board.
Elaine Troup
Implement and embed a new delivery model for
co-located libraries 31-Mar-2025
Action completed as planned. Dalmuir, Parkhall and
Balloch libraries are co-located.  Visitor and Stock
statistics being reviewed to inform 2025/26 spend
and staffing.
Emma Eremin

Page 5

5
Action Status Progress Due Date Note Owner
Create a strategy document for West
Dunbartonshire Libraries 31-Mar-2025
Action overdue and will be carried over to 2025/26,
to allow satisfactory time to undertake a full public
consultation which is required to inform strategy.
National frameworks and strategies have been
identified. Public consultation is in development to
inform the strategy and will be delivered in 2025/26.
Emma Eremin
Migrate the Libraries Management System
(LMS) to a new software supplier 31-Mar-2025
Action completed as planned. The Library
Management System is in use with procedures
developed on an ongoing basis according to
business need.
Emma Eremin
4. Our Council
Objective 10. Our workforce is resilient and skilled where digital technology supports service delivery for our residents
Action Status Progress Due Date Note Owner
Develop and implement wellbeing, employee
engagement, equality and learning and
development plans to enable capabilities,
improve resilience and promotion of a diverse
workforce
31-Mar-2025
Action completed as planned. We continue to embed
full team meetings across the contact centre.
Facilities management has undertaken a staff survey
and a more consistent approach to engagement is
being introduced including increased presence of
team leaders across the service. 
All Managers
Develop and implement employee life cycle
plans in line with the People First Strategy to
attract and retain the workforce.
31-Mar-2025
Action completed as planned. Working groups in
place to consider progress of next phase of Facilities
Management service review with a view to
improving recruitment and retention.
All Managers
Implement service review process including role
design, use of new technology and new ways of
working to add resilience, address gaps, and
establish opportunities for efficiencies
31-Mar-2025
Action completed as planned. Staff engagement has
been undertaken on the colocation of libraries.
Employee impact has been minimised by retaining
level of staffing in each affected branch and working
collaboratively on any issues. A Library Strategy is
All Managers

Page 6

6
Action Status Progress Due Date Note Owner
in progress. Health Literacy training has been
identified as required and will be delivered by NHS
Public Health in 2025.  Digital skills also require
some upskilling to widen digital access offer in all
libraries. Work has started within Facilities
Management on developing a suitable operating
model for Faifley Campus.
Develop and implement learning and
development opportunities to improve
capabilities and resilience within the workforce.
31-Mar-2025
Action completed as planned. Upskilling and new
processes are being progressed to support the
introduction of a new customer hub system for
customer services. In Facilities Management,
following additional training, HR practices and
policies are embedded across the service and
training sessions including stock control have been
completed.
All Managers
Objective 11. Our Council is adaptable and focused on delivering best value for our residents
2023/24 2024/25
Performance Indicator
Value Status Value Target Short Trend Long Trend Note
Owner
Percentage of complaints received by the Council
that are resolved/ closed at Stage 1 81.5% 83.75% 90%
Target marginally missed with
marginal improvement on previous
year. Overall, 1633 complaints were
received and of these 1435 were
closed or resolved at Stage 1. The
number of complaints received
significantly increased in 2024/25
due to issues with Waste collections
over festive period. Alongside this
increased workload, the complexity of
complaints also means more
complaints being escalated from
Stage 1.
Lorraine Phimister
Percentage of complaints received by the Council
that are resolved at Stage 2 3.58% 4.5% 10%
Target achieved. Overall, 1633
complaints were received of these 51
were closed at Stage 2.
Lorraine Phimister

Page 7

7
2023/24 2024/25
Performance Indicator
Value Status Value Target Short Trend Long Trend Note
Owner
% of telephone calls answered within 5 minutes by
Repairs Contact Centre as a proportion of all calls
answered.
80.6% 86% 90%
Target marginally missed with
improvement on previous year. Over
41,300 calls handled with 35,740
answered within 5 mins. And another
4,333 calls answered after 5mins.
Sustained number of calls for updates
to existing repairs and increased call
handle time. We continue to work
with Building Services to improve
performance.
Lorraine Phimister
% of telephone calls answered within 3 minutes by
Contact Centre as a proportion of all calls
answered.
91% 78% 90%
Target missed with downward trend
from previous year. Over 28,100
handled with 21,945 answered within
3 mins. And a further 4,938 calls
answered after 3 mins. Reduced
resourcing following savings options
and increased calls from Waste
Services issues over festive period
alongside the Garden Waste Permit
contributed to reduced performance.
Lorraine Phimister
Residents satisfaction with Council services overall 78% 71% 85%
Target significantly missed with
downward trend. Recent changes
across a number of Council services
due to budget reductions continue to
impact on the satisfaction rate.
Lauren Crooks
Action Status Progress Due Date Note Owner
Implement complaints management process
enhancements – next phase 31-Mar-2025 Action completed as planned. System now live and
will be monitored until fully embedded.   Lorraine Phimister
Explore telephony self-serve options 31-Mar-2025
Action completed as planned. We explored the
telephony enhancements needed with our ICT
colleagues. Over 2025/26 an upgrade to the contact
centre telephony platform will be progressed by our
ICT colleagues. This will provide the required
enhancements.
Stephen Daly
Roll out child friendly complaint procedure. 31-Mar-2025
Action completed as planned. The process for Child
Friendly complaints has been much more
streamlined than anticipated. Guidance to be
Lorraine Phimister

Page 8

8
Action Status Progress Due Date Note Owner
finalised by SPSO, this will not be a new procedure
but will sit alongside existing complaints handling
processes.  Meetings have been held with Education
and Social Work and update will be provided to
PMRG via quarterly complaints report in March
2025. 
Progress Community Facilities Plan 31-Mar-2025
Action overdue although expected to be completed
early in 2025/26. Whilst one centre remains in
Council ownership at this time. Discussions are
underway to conclude a lease agreement.
Amanda Graham
Progress commercialisation and income
generation opportunities 31-Mar-2025
Action overdue. Whilst some advertising revenue
has been secured, part of the saving related to
generating additional income from leasing buildings,
including Bruce Street Baths and Clydebank Leisure
Centre to external parties. This has not materialised
and a cost pressure of £154k has been built into the
budget going forward as a result this saving needs
to be reversed.
Amanda Graham
Review and redesign of the Communities team
service delivery 31-Mar-2025
Action overdue. Following a review of the service a
decision was taken to ensure the continuation of
Youth Learning and CLD / community planning
under separate functions. Work is on-going to
support staff as they move to different service areas
to continue their work however progress has
experienced delays due to resourcing challenges.
This action will carry over into 2025/26.
Elaine Troup
Review operating model of Facilities
Management service – Next Phase 31-Mar-2025
Action completed as planned. Staff survey
undertaken, with just below 30% response rate,
feedback being reviewed to develop improvement
actions as required. Back to work sessions
undertaken across all teams and well attended. The
next phase will progress in 2025/26.  
Sharon Jump
Review menu and food purchase to minimise
waste and reduce costs 31-Mar-2025
Action completed as planned. New three weekly
menu in place. Review of products and pricing
complete. High schools are all purchasing the same
products and costing and pricing is aligned and in
line with procurement process. Both support a
reduction of wastage and costs. We will continue to
monitor this going forward.  
Sharon Jump

Page 9

9
Action Status Progress Due Date Note Owner
Review library materials and staffing 31-Mar-2025
Action completed as planned. Spending and
materials reviewed to inform 2025-26 operational
stock strategy plans. 
Emma Eremin
Risk Description Current
Assessment Target Assessment Date Reviewed Note Owner
Risk of Failure to meet
citizen expectation and
service standards
Risk of citizen dissatisfaction due to us
not doing what we say we will when we
say we will.
11-Feb-2025
This assessment has moved from
green to amber based on an increase
in likelihood. This is evidenced through
demand to the Contact Centre
becoming more complex and outcomes
to satisfy the Citizens being much
harder to achieve. This is also visible
on Social Media. Evidence to support
this is the challenging situations on
Waste Services for Missed Bins, Festive
Collections, Conditions of Roads, speed
of response to Housing enquiries,
ongoing concerns to Housing Repair
updates being the most significant
number of calls to the Council. We are
seeing that more citizens are
dissatisfied as indicated in the final
telephone survey.
Change to Risk matrix. Likelihood has
increased from 2 to 3.
Stephen Daly
Failure to effectively
manage and learn from
complaints
There is a risk of damage to the
Council's reputation. If complaints are
not handled effectively, there can be an
adverse effect on the public perception
of the Council which can lead to a lack of
trust in the services provided.
11-Feb-2025
Work continues to engage with
services and improve response times
and learning outcomes. Action plan
agreed with internal audit to address
challenges with the compliance of
complaint management was completed
summer 2024.
The likelihood remains the same in
terms of no new evidence being visible
in how Services have improved their
processes by learning from complaints.
No change to risk matrix
Stephen Daly

Page 10

10
Objective 12. Our residents are engaged and empowered
2023/24 2024/25
Performance Indicator
Value Status Value Target Short Trend Long Trend Note
Owner
Percentage of residents who are satisfied with the
Council website 90% 85% 85% Target met. Jonathan Muir
% of stage 2 complaints responded to within 20
working days. 57.89% 41% 100%
Target significantly missed. Overall,
85 complaints were handled at Stage
2. Of these 21 were responded to
within 20 working days. A further 19
were closed with extensions being
applied. Delays in responses are due
to the complexity of matters raised
and also delays in responses being
received from services.
Lorraine Phimister
% of residents who feel WDC keeps people
informed of important information 63% 53% 75%
Target significantly missed with
performance continuing on a
downward trend. This feedback
reflects on how well individual
services communicate and interact
with residents when they make
contact
Lauren Crooks
No. of transactions undertaken online 59,368 64,048 56,500 Target exceeded and will increase to
59,000 for 25/26. Jonathan Muir
% of stage 1 complaints responded to within 5
working days. 66.8% 95% 100%
Target marginally missed, with
consistent improvement over the
year. Overall, 1486 complaints were
closed at Stage 1. Of these 1146
stage 1 complaints were responded
to within 5 working days. A further
179 stage 1 complaints were closed
with extensions being applied. 
Delays were due to increased
workload and delays in responses
from services
Lorraine Phimister

Page 11

11
Action Status Progress Due Date Note Owner
Progress upgrade online content management
system – next phase 31-Mar-2025
Action completed as planned. Both sites have now
been upgraded to the latest Long Term Supported
version on the Content Management System. We
also deployed a security hotfix that was released on
both sites.
Jonathan Muir
Progress security reviews of websites 31-Mar-2025
Action completed as planned. An additional hotfix
was release at the start of 2025, this has been
installed on both the internet and intranet website.
All security issues raised at the start of the year
have been applied, we have a few low-level security
issues to look into next financial year.
Jonathan Muir
Review accessibility of the website and intranet. 31-Mar-2025
Action completed as planned. The external site has
maintained a very high standard/score and we have
started working through the intranet. The intranet is
always going to be an issue, as the webteam are not
the main editors for it and the site is large and
growing.
Jonathan Muir
Develop Strategic Communications Strategy 31-Mar-2025
Action completed as planned. Final draft has been
approved by Chief Officer, and draft proposals are
progressing for elected member briefing.
Lauren Crooks
Develop a communication plan to support
budget savings initiatives 31-Mar-2025
Action completed as planned. The communication
plan was extensive to ensure the key messages and
changes to frontline services was effective. 
Lauren Crooks
Deliver the UK Shared Prosperity Funded
projects 31-Mar-2025
Action completed as planned. The UK Shared
Prosperity funded projects are complete This
included awareness raising and capacity building to
support communities to host their own Community
Soup events as a way of engaging people in local
decision making. The projects also included the
improvement of four community gardens completed
by community groups.
Elaine Troup
Develop an approach for the future provision of
community budgeting 31-Mar-2025
Action completed as planned. Phase 7 of Community
Budgeting has been successfully developed and
delivered with the aim of addressing food insecurity
across West Dunbartonshire. The project launched
on 2 December 2024 and all funds awarded to
successful groups during March 2025.
Elaine Troup
Continue to Develop an approach to food
insecurity 31-Mar-2025
Action completed as planned. This test of change
project has been successfully developed and
delivered during 2025/26 with the demand for the
Elaine Troup

Page 12

12
Action Status Progress Due Date Note Owner
fund increasing over time.  The project team has
continually reviewed, evaluated and amended the
approach to ensure people are able to access the
fund and receive the support required. The next
steps of the project have been agreed and will
conclude during 2025/26.
Progress plans to strengthen approach to
strategic engagement 31-Mar-2025
Action completed as planned. To further strengthen
our approach to strategic engagement, the 2025/26
Budget Conversation engaged with community
organisations representing a wide range of the
community. We have also reviewed participation
across a range of engagement events to identify
under-represented groups and taken steps to
increase participation from these groups. Work will
continue as part of our wider equality plans to
ensure engagement is as representative as possible
and all communities feel valued.
Nicola Docherty
Reflect legislative changes from Scottish Gov in
WDC equalities framework, process and
procedures
31-Mar-2025
Action completed as planned. The Equality &
Diversity Working Group (EDWG) has been updated
on revisions to the Public Sector Equality Duty. We
have developed the new Equality Outcome &
Mainstreaming Plan for 2025-29. We continue to
review our processes to ensure that equalities are at
the forefront of our practices.
Nicola Docherty
Develop WDC British Sign Language plan 2024-
30 31-Mar-2025
Action completed as planned. We have developed, in
conjunction with BSL users, the statutory BSL plan
2024-30 identifying key outcome areas for West
Dunbartonshire. this has been published in English
and BSL. As part of this we have developed an
action plan, that will be updated on a yearly basis.
We continue to engage with BSL users to ensure
they have the opportunity to participate in decision
making within the Council.
Nicola Docherty

Page 13

13
Risk Description Current
Assessment Target Assessment Date Reviewed Note Owner
Failure to secure
community and partner buy
-in for the emerging
Community Empowerment
Strategy and Action Plan.
In order to deliver on the ambitions of
the Community Empowerment Strategy
and associated action plan, it is vital that
a partnership approach is promoted to
ensure best use of resources, skills and
expertise.
31-Mar-2025
The community empowerment agenda
is being progressed by the Council and
partners across the Community
Planning Partnership with reporting on
community development through the
Empowered Delivery Improvement
Group.  Community development work
will continue to support individual and
community empowerment and
resilience focused on locality planning,
community councils and community
asset transfers.
No change to risk matrix
Elaine Troup
Failure to deliver on the
capacity building of the
Community Empowerment
(Scotland) Act
There is an ever greater need to support
and develop communities. Community
capacity building and community
development work continues within
existing resources.
10-Apr-2025
Delivering the Council's community
empowerment agenda remains a
priority however organisational
changes will see different services
deliver on different work streams. The
on-going financial challenges facing
local authorities has had an impact on
budgets available to support
community empowerment.
This has resulted in an increase to the
risk matrix. Likelihood increased from
2 to 3. 
Elaine Troup
Risk of Ineffective
Communications /
Reputation Risk
Ineffective use of corporate
communication channels may result in
messages that are inconsistent with
authorised responsibilities or established
performance measures. Employees
without intranet access or email access
may not receive communications. Not
effectively managing corporate
responses to adverse events may lead to
an erosion of the Council's reputation.
01-Apr-2025
There is no change to risk matrix. A
number of processes and strategies
are in place to ensure internal and
external communication is effective
and protects the Council's reputation.
Lauren Crooks

Page 14

14
Action Status
Cancelled
Overdue
Not on track
In Progress and on track
Completed
PI Status
Target significantly missed
Target narrowly missed
Target met or exceeded
Risk Status
Alert
Warning
OK
Long Term Trends
Improving
No change
Declining
Short Term Trends
Improving
No change
Declining