WEST DUNBARTONSHIRE COUNCIL
Report by Chief Officer – Citizen, Culture and Facilities
Corporate Services Committee 21 May 2025
Subject:Citizen, Culture and Facilities 2024/25 - Year-end Progress and
Citizen, Culture and Facilities Delivery Plan 2025/26
1 Purpose
1.1 This report sets out the year-end progress of the 2024/25 Delivery Plan and
presents the new Delivery Plan for 2025/26.
2 Recommendations
2.1 It is recommended that Committee notes the progress achieved at year-end
and the new Plan for 2025/26.
3 Background
3.1 In line with the Strategic Planning & Performance Framework, each Chief
Officer develops an annual Delivery Plan which sets out actions to help deliver
the Strategic Plan and address the performance challenges and service
priorities identified in the planning process. The Plan also provides an
overview of services and resources, including employees and budgets, sets
out the performance indicators (PIs) for monitoring progress and considers the
relevant risks.
3.2 In the last few months of 2024/25, several services and teams across the
Council were realigned to other Chief Officer areas. For consistency and
transparency, the year-end progress reports reflect the content of the 2024/25
delivery plans reported to the relevant committees at the beginning of that
year, with none of the organisational changes that took place in-year included.
Those changes are, however, reflected in the new delivery plans for 2025/26.
4 Main Issues
2024/25 Year-end Progress
4.1 The 2024/25 Delivery Plan was presented to Corporate Services Committee
on 22 May 2024 and mid-year progress reported on 6 November 2024.
4.2 Full details of year-end progress are set out in Appendix 1.
ITEM 7

Page 2

4.3 The progress of the Plan’s 35 actions is summarised below:
Progress No. (%)
Complet
ed 28 (80%)
Overdue 7 (20%)
4.4 Overdue actions relate to the following and with the exception of
commercialisation will be carried forward and completed in 2025/26:
 Review the outputs from Good Food Nation consultation process – 80%
 Progress storage review and planning for future decant of WDC collections
to Strathleven – 66%
 Create a strategy document for West Dunbartonshire Libraries – 75%
 Progress Community Facilities Plan – 75%
 Progress commercialisation and income generation opportunities – 33%
The following will be monitored in the Regulatory & Regeneration 2025/26
plan;
 Support community planning partners to develop and deliver two
Community Planning (CP) events to support increased participation – 75%
 Review and redesign of the Communities team service delivery – 80%
4.5 Year-end data is available for all the Plan’s 18 PIs. The performance of those
PIs is summarised below:
Performance Against Target No. (%)
Target met or exceeded 9 (50%)
Target marginally missed 5 (28%)
Target significantly missed 4 (22%)
Performance Over Time No. (%)
Improved over short term (or maintained high
level of performance)
9 (50%)
Improved over longer term (or maintained high
level of performance)
7 (39%)
4.6 Where target was significantly missed, this relates to the following PI’s:
 % residents satisfied with Libraries: 75% against a target of 90%.
 % residents satisfied with Council services overall: 71% against a target of
85%.
 % of stage 2 complaints responded to within 20 working days: 41% against
a target of 100%.
 % of residents who feel WDC keeps people informed of important
information: 53% against a target of 75%.
4.7 The full set of PIs will be reported through the Council’s annual performance
reporting process once all data becomes available.

Page 3

2025/26 Delivery Plan
4.8 The 2025/26 Delivery Plan is set out at Appendix 2.
4.9 Key priorities include:
 Support upgrade of telephony platform. 
 Finalise libraires strategy document, support new Faifley community
library, support relocation of Dumbarton library to Glencairn House, and
relocation of Library Services to Strathleven Place. Launch Empower
Connections digital offering.
 Progress review of accessibility of the website and intranet.
 Complete Facilities Management service redesign, enhance training,
increase capacity, progress free school meal programme and support
outputs from Good Food Nation consultation process.
 Develop strategic communication plan to support budget savings initiatives
 Progress funding application to support heritage activity programme for
Glencairn House, undertake planning for future decant of WDC collections
to Strathleven Place, support progress of plan for opening of Clydebank
Heritage Hub and launch public access to the local history archive
collections.
 Progress plans to strengthen approach to strategic engagement, prepare
Strategic Needs Assessment (SNA) and deliver Equalities Outcomes and
Mainstreaming Plan 2025-29.          
4.10 Implementation of the Plan will be monitored by the management team with
mid-year and year-end progress reported to Corporate Services Committee
around November 2025 and May 2026 respectively.
5 People Implications
5.1 There are no direct people implications arising from this report.
6 Financial & Procurement Implications
6.1 There are no direct financial or procurement implications arising from this
report.
7 Risk Analysis
7.1 Failure to deliver on the actions assigned to Citizen, Culture and Facilities
may have a direct impact on the delivery of the Council’s Strategic Plan. It is
essential that remedial action is taken to ensure strategic delivery plans
achieve the commitments detailed.
8 Equalities Impact Assessment
8.1 Screening and impact assessments will be carried out on specific activities as
required.
9 Consultation

Page 4

9.1 The delivery plans were developed through consultation with officers from the
strategic service areas.
10 Strategic Assessment
10.1 The delivery plans set out actions to support the successful delivery of the
strategic priorities and objectives of the Council.
Chief Officer: Amanda Graham
Service Area: Citizen, Culture and Facilities,
Date: 17 April 2025
_____________________________________________________________
Person to Contact: Performance & Strategy Business Partner
karen.Connelly@west-dunbarton.gov.uk
Appendices: Appendix 1: Citizen, Culture and Facilities Delivery Plan
2024/25 – Year-end Progress
Appendix 2: Citizen, Culture and Facilities Delivery Plan
2025/26
Background Papers: Citizen, Culture and Facilities Delivery Plan 2024/25 -
Corporate Services Committee, 22 May 2024
Citizen, Culture and Facilities Delivery Plan 2024/25 Mid-
year Progress - Corporate Services Committee, 6
November 2024
Strategic Planning & Performance Framework 2022/27
Wards Affected: All