Page 1

Management Board Meeting
Development and Improvement Groups (DIGs): Highlights and
Issues Report
FOR INFORMATION ONLY X
FOR DECISION
Name of DIG Flourishing Delivery and Improvement Group
(DIG).
Date of report 22/04/2024
Name and email of lead contact Peter Barry
1 Highlights of activity and progress since last meeting
Regeneration 
Dumbarton
Levelling Up Programme
• Glencairn House - Clark Contracts appointed as the Principal Contractor.
Works starting on site w/c 15 April.
• Connecting Dumbarton - works nearly completed, artwork in the
underpass remains to be installed.
• Masterplan for redevelopment of the Artizan was approved by
Infrastructure, Regeneration and Economic Development Committee on
1 November 23. Planning application for Phase 1 works expected in May
24.
• Design Team progressing the detailed designs for the
Artizan Redevelopment Masterplan, application for
Planning Permission in Principle is expected in May 24.
• Demolition of units to rear has been delayed due to a requirement to divert
Scottish Water pipes, works expected to commence on site in May 24.
Alexandria
• Restoration of Smollett Fountain mostly completed, Heron was installed
w/c 15 April.
• Discussions on a potential Business Improvement District ongoing, the
traders were successful in securing £20k of seedcorn funding from the
ITEM 9

Page 2

Scottish Government towards BID development. Officers are supporting the
process as and when required.
• Shared Prosperity Funded shopfront improvement grants applications
being received however progress is slower than anticipated. The
businesses struggle with providing the required evidence, however the
guidance has been amended to make the process easier.
• Alexander Street improvements project has commenced and Page & Park
were appointed as a lead consultant. The project originated from the
Masterplan and is part of the Green Heritage Corridors projects. It will be
funded from the Place Based investment Programme fund.
Clydebank
Queens Quay District Heating Network
• Legal and commercial discussions regarding the West College Scotland
and Golden Jubilee connections ongoing
• Technical exchange of information is well advanced with the Golden
Jubilee and Commercial Discussions around tariff, resilience and liability
issues are to be advanced.
• Works to connect a further 46 Clydebank Housing Association flats on
Dumbarton Road underway, with some publicity planned for the first “Heat
On” anticipated before the end of the month.
Town Centre
• Planning application for the Clydebank Canal-side Activities Centre
progressing. The delivery of the project, however, has been put on hold.
Y Sort It withdrew their interest in the centre as due to funding cuts they
are unable to take on premises and have decided to prioritise their core
activities. We will explore opportunities for securing an alternative
tenant, and look if the future centre could be advertised as a
commercial let opportunity.
• £20M UK Government funding from Long-Term Plan for Towns
announced for Clydebank Town. A new Town Board chaired by an
independent Chairperson (Liz Connolly) will have its first meeting on 10
May. A report seeking approval for the governance arrangements was
approved by Infrastructure, Regeneration and Economic Development
Committee on 7 February 24.
Exxon
• Council officers continue to seek additional funding from City
Region to contribute towards the costs of the project.
• Stage 2 application for Scottish Government Vacant and Derelict
Land Fund for greenspace and footpaths was submitted 2023,
however due to financial difficulties no funding was awarded for
the coming financial year for any projects.
• It is hoped that the remaining land acquisitions and/or licences to
occupy will be concluded shortly to allow enabling works to begin
(actual start date dependent on revised Balfour Beatty
Programme).

Page 3

• The remediation has taken longer due to further contamination
found at the riverside; this has delayed the completion of the
remediation by approximately a month.
• A new promotional brochure for the site has been produced.
Scottish Marine Technology Park
• Council continuing to work with the Malin Group to support the
relocation of their business to Carless and to help with the
identification of additional funding for land remediation
• Planning application now submitted
• Work complete on the flood mitigation project, and Malin Group have
appointed a designer for the Quayside, both of which are being funded by
Clyde Mission and the Council, the latter being subject to a further
development agreement
• With support from the Council, Malin and Strathclyde University
submitted a bid to the City Region Investment Zone for Maritime Supply
Chain Innovation Centre. (further details below).
Place Based Investment Programme (PBIP) Grants
• Infrastructure, Regeneration and Economic Development Committee
on 1 November 23 approved allocation of £471k of PBIP funds
towards Community Grants
• Small and Large grants have been widely advertised and we receive a total
of 13 eligible applications from all across the West Dunbartonshire.
£61,758k were awarded to those applicants following a public voting
process.
• Large grants – 26 applications were received for a total of £1.8m and were
reviewed by the Council Officers w/c 19 February. The following groups
were awarded funding:
Project Cost
1st Glen Lusset Scout Group £ 54,550.00
Dumbarton Tennis Club £ 40,000.00
Clydebank Community Sport Hub £ 96,900.00
RSPB £ 74,437.45
Milton Village Community Group £ 90,000.00
St Augustine’s Episcopal Church £ 18,280.00
Duntocher Village Hall £ 25,000.00
TOTAL
£
399,167.45

Page 4

• All grants have already been distributed to the grantees. We will review the
progress after 3 months (for small grants) and 6 months (for large grants)
Regeneration Capital Grant Fund
• Regeneration Team have issued a call for Expressions of interest (EOI) for
Regeneration Capital Grant Fund 25/26 in anticipation of the Scottish
government announcing the fund later in the Spring. We have received 5
EOIs from the following groups:
• Old Kilpatrick Food Parcels
• Flourishing Faifley Community Hub (Knowes pavilion)
• Glenhead Centre (Antonine Community Centre Duntocher)
• Kilbowie Community heritage Centre - St Andrew’s Church
(Clydebank)
• RSBP Scotland visitor hub (Gartocharn)
• In addition, we are aware of Westbridgend Community Centre
(Dumbarton) looking to submit an application again this year (they did not
get through to Stage 2 last year). 
• Submitted EOIs will be assessed by a panel of Council Officers and a
number of eligible applications will be chosen to be supported for Stage 1
submission. Regeneration Officers will offer assistance to the prospective
applicants. 
Business Support 
• During 2023/24, 200 businesses were assisted to start-up through the
Business Gateway service which exceeded the annual target of 180
and 30 established businesses were assisted with development of a
growth action plan (target 30).
• The business grants available through the UK Shared Prosperity Fund
are continuing to receive applications. The grants include a Recovery &
Growth grant, Early Stage Growth grant, Working Towards Net Zero
grant & Enhancing West Dunbartonshire’s Tourism Events &
Attractions grant.
• A Food & Drink Challenge Fund developed in partnership with the
Working4Business group to provide a competitive grant to food and
drink manufacturers and producers that could evidence growth projects
has provided £5,000 funding to 3 local businesses (Cherry-On-Top,
Tartan Rocket & Island Slice Ltd).
• Working in partnership with Glasgow City Region and Strathclyde
University to provide businesses with green business advice through
the development of carbon baseline assessments. This support is
funded through UK Shared Prosperity Fund. A process is in now in
place to refer local businesses with 4 businesses being referred to
date.
• Business Support team in partnership with Procurement colleagues
have booked a stand at the Supplier Development Programme’s Meet
the Buyer 2024 event on 5th June at Hampden Park to promote tender
opportunities.

Page 5

City Region/Scottish Government/UK Levelling Up 
• Glasgow City Region will be one of two Investment Zones in Scotland
and as a result will benefit from a package of funding and tax relief
measures estimated to be worth £160M over 10 years. The details of
the offer will be co-produced by City Region and Member Authorities,
Scottish Government and UK Govt (DHLUC). Phase two closed at the
end of March and involved an open call for detailed project applications
from businesses and organisations in the following ‘Priority Clusters’ - 
Advanced Manufacturing, Health & Life Sciences, and Digital &
Enabling Technology.
• Malin and Strathclyde University with support from the Council have
submitted a Phase 2 bid to support the development of a Maritime
Supply Chain Innovation Centre at Carless site. 
Employability/Learning/Income Maximisation – 
• Working4U is responsible for delivering services that help people to
address the barriers that prevent them from considering work as an
option; improve their skill sets and secure employment. This rests on
input from employability (Work), community learning and development
(Learn) and debt/benefit support (Money) services. 
• Collectively these services are addressing poverty and disadvantage
by supporting people to increase income through work and benefit
entitlement, reduce their cost of living and address barriers to work
and learning opportunities.
• In 2023/2024 Working4U provided work, learning and money support
for 8,597 people. Of those:
o 362 people were supported through apprenticeships and in
work progression;
o 1,064 to enter education or training;
o 867 people were supported to gain a qualification;
o 439 people secured employment.
• Community learning and development services contributed to this
success by providing access to community-based learning that focussed
on the most marginalised people/families in our community. This
included support for:
o Adult/Youth Literacies;
o Community-based vocational courses;
o Digital Learning;
o ESOL; and
o Family Learning.
• The Working4U debt and benefit support services assisted residents to:
o Manage £1.27m of debt;
o Secure £8.3m of benefit entitlements.
• More information about Working4U and partner services is provided in
Annex A

Page 6

• West Dunbartonshire Council is the lead agency for the management
and delivering services. Grants have been distributed to private and
Third sector organisations to support the No One Left Behind and UK
Shared Prosperity aims.
• In the forthcoming period we will continue to work with partners through
the Local Employability Strategic group, Adult Learning Partnership and
Information and Advice partnership to co-ordinate activities that will
support people to maximise income, reduce costs and overcome
barriers to opportunity. 
2 Outline of any issues/risks and how these are being managed 
Regeneration 
Inflation and rising costs are a challenge in project delivery. We are looking at
adjusting scope to make projects affordable, or seeking additional funding where
possible. 
Tight timescales associated with external funding pose a challenge to project
delivery. We are seeking support from external consultants where appropriate,
and work collaboratively with other teams to identify solutions. We also continue
to engage with the funders. 
Towns Fund for Clydebank is a new approach to delivery with limited control and
engagement from the Council, we are liaising with the Chair as well as our
DLUHC contacts to understand how the guidance should be implemented and
what will work in Clydebank context. 
Business Support 
A delay in finalising the Extend Plus grant agreement with Strathclyde University
led to a delay in referring businesses for carbon baseline assessments. A
business referral process is now in place which will allow the team to promote to
local businesses. 
Employability 
The risks for the employability service centres on the ability to secure reliable
external training providers capable of delivering services in the local area. We are
managing this by providing each grant recipient with a key contact and providing
them with the opportunity to identify delivery challenges at an early stage. In
addition, late notification of grant awards, which are now a common feature of
eternal funding, are causing delays and uncertainty among service providers.

Page 7

3 Outline of the main outputs expected before next meeting 
Regeneration 
• Alexandria, Alexander Street – public engagement completed, Stage
3 design underway.
• Clydebank, Activity Centre – planning permission anticipated. An
alternative delivery plan agreed.
• Clydebank, Long-Term Plan for Towns – first Board meeting held,
community engagement and development of Investment Plan
underway.
• Dumbarton, Artizan – demolition contract underway
• Dumbarton, Artizan – Stage 3 design completed, planning application
for Phase 1 works and for Planning Permission in Principle (PPIP for
the Masterplan) submitted.
• 25/26 RCGF Stage 1 applications submitted by selected community
groups and external organisations (subject to Scottish Government
timescales)
• Exxon enabling works commenced on site 
Business Support 
• Increase the number of business referrals to Strathclyde University to
receive carbon baseline assessments.
• Promote and deliver the business grant support programmes within the
UK Shared Prosperity Fund.
• Continue to provide Business Gateway service to start-ups and
established local businesses.
• Attend Meet the Buyer event to promote tender opportunities
• Receive feedback from Glasgow City Region regarding Phase 2
Investment Zone bid for Maritime Supply Chain Innovation Centre 
Employability 
• Working4U has continued to manage grant support services and deliver
Work, Learn, Money activities and over the course of 2023/24  we have
assisted 8,597 people: Of these we have
o Assisted 362 people through apprenticeships and in-work
progression;
o Supported 1,064 into education and training;
o 867 have gained a qualification;
o 439 have secured employment.
• In addition we have:
o Assisted people to secure £8.3m of additional benefits; and
o Manage £1.27m of debt.
• As such, we have achieved the targets for these activities
and are currently planning our priorities for the forthcoming
year.

Page 8

4 What are your requirements of partners in the Community Planning
Management Board to achieve the outcomes of the DIG?  
Placemaking 
Good placemaking will continue to underpin the regeneration, development and
improvement work in the town centres as we aim to align funding and resources,
with Council, DIG partners and external funding, to achieve our ambitions. 
Business Support 
The on-going commitment and support from the community partners will help to
maximise the impacts of the business support activity being developed and
implemented through the Flourishing DIG. This will assist with reinforcing our efforts
to develop a strong local economy that will provide access to opportunity for all in
West Dunbartonshire. 
Employability 
We will continue to deliver the NOLB, Parental Employability support programmes
and UK Shared prosperity activity. We will continue to work in partnership through
the Adult Learning Partnership and local employability partnership. 
We ask the partners to continue with their contribution to the local employability
group by attending or sending representation where appropriate to the strategic
group; the creative design group (service providers) and the frontline community of
interest. These groups are making a positive contribution to identifying and
addressing challenges in West Dunbartonshire. 
In addition, we will be updating our Community Learning and Development Plan and
Annual Child Poverty Report. We ask that partners give consideration into their
contribution to these processes and associated services. 
5 Please outline any good news story you wish to share                                               