Community Planning West
Dunbartonshire Executive Group –
Meeting Note and Actions 
Date:  Monday 20 January 2025
___________________________________________________________________ 
Time:  11:00
___________________________________________________________________ 
Item
1. Welcome, introductions and apologies. 
In Attendance:
Peter Hessett (Chair) (PH), Selina Ross (SR), Gail MacFarlane (GM),
Fiona Taylor (FT), Jonathan Harris (JH), Patricia Robertson (PR),
Amanda Graham (AG), Elaine Troup (ET), Megyn Tyrell (MT), Elaine
Boyle (EB). 
PH welcomed Tricia Robertson to the meeting. PR will replace JH as
Partnership Superintendent following a short handover period. Both will
attend the next CPWD meeting. 
Apologies: Lesley James (LJ).
2. Note and action log of previous meeting 
 PB/ET to discuss DIG reporting as part of handover to GM –
Complete.
 ET to request info from Scottish Community Planning Network on
reporting structures for consideration – Complete, up-date provided. 
 ET to contact all DIG leads to arrange time to meet – Complete,
meeting held in January and further meetings will be arranged.
 ET to draft and circulate a report on the Pilot Approach prior to CPWD
pre-agenda - Complete.
 ET to share Strategic Needs Assessment with CPEG members -
Complete. 
 All to discuss second CP event – Complete and discussed as part
of the agenda. 
 Further discussion to be arranged with AG, LJ, ET on domestic abuse
and violence against women and role of CP – Complete, and further
discussion on-going with DIG leads.
ITEM 5 - 
APPENDIX 1

Page 2

 Future CPEG meeting dates to be agreed - Complete.
3.1 DIG updates on Action Plans 
 Flourishing DIG – Handover to GM now complete and meeting
planned for mid-February where they aim will be to refresh the action
plan and identify key priorities.  
 Empowered – SR provided an up-date on progress incorporating the
Community Development Alliance within the Empowered DIG which
has resulted in improved membership and focus.  Members are
working on a refreshed plan with a focus on added value.   
 Independent – met last week and is on course with the action plan.
Membership and attendance remains a challenge for this DIG.   
Review of DIGs - ET provided a summary of the meeting last week with
all DIG leads. The purpose was to review DIG reporting. All members
appreciated the opportunity to come together for the review and to benefit
from increased awareness of what other DIGs deliver. Significant positive
discussion about the partnership working across West Dunbartonshire
however some concern around attendance/membership of at DIG
meetings. 
The meeting resulted in the following agreed next steps:
 Undertake a mapping exercise of all partnership working across
WD to inform future reporting and DIG structure. 
 Liaise with other local authorities (NAC) on their approach to
reporting 
 Follow-up meeting with all DIG leads to develop a proposal to
streamline future reporting. 
 Future report to CPWD on recommended approach. 
Action ET – to progress a review of DIGs. 
3.2 Exception reporting: Nothing raised. 
4. Proposed Approach for CPWD in 24/25. 
Proposal for a second community planning event -  
SR has agreed that CVS will lead on the second community planning
event due to take place in March 25. The event will be a workshop
session focussing on the development of a local climate hub. The event
will present an opportunity for the wider partnership to contribute to the
discussions and ensure robust engagement with the local community on
climate change. 
Action: SR will progress and provide a verbal up-date to the next CPWD
Management Board. 
Pilot project and establishment of a partnership working group.
Following approval of CPWD Management Board in November there has
been discussions with several partners and an initial meeting will take
place towards the end of January to define the scope of the project and a
timeframe for delivery.

Page 3

Action: ET to provide a verbal up-date to the next CPWD Management
Board. 
5. CPWD Management Board Meeting feedback 
Positive feedback from the group the last CPWD board meeting. In
general it was felt that participation at the meetings was increasing. 
The following Agenda items were confirmed:
a). Introduction from Brian Dornan, Head of Strategy, Scottish
Government and Place Director for CPWD.
b).Whole Family Wellbeing Update (Presentation by Claire Cusick) 
c). Trauma Informed Practice Strategy for approval (Margaret-Jane
Cardno, HSCP)
d). Review of DIG reporting – Verbal up-date from ET
e)  Pilot Project Up-date – Verbal up-date from ET
f) Community Planning Event – Verbal up-date from SR  
6. AOCB and Date of Next Meeting 
PH provided an up-date on the introductory meeting held with CPWD’s
new Place Director, Brian Dornan.  BD is also Head of Strategy for the
First Minister. BD has agreed to provide a brief introduction at the next
CPWD Management Board meeting. 
Meeting dates:
 CPWD Board – Thursday, 20 February (MS Teams)
 CPEG – Monday 21 April (MS Teams)
 CPWD Board – Thursday 22 May (in-person event, venue needed) 
No. Action Progress
3.  Action ET – to progress a review of DIGs.  In progress
4. Action: SR will progress and provide a verbal
up-date on the planned second event to the
next CPWD Management Board. 
Action: ET to provide a verbal up-date to the
next CPWD Management Board on the review
of the DIG structure. 
In progress 