Democracy Spraffa

Item 5 - Internal Audit Plan 2023-24 - Progress to 18 July 2023

West Dunbartonshire Council · 9 August 2023
Back to Audit Committee — 9 August 2023 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

WEST DUNBARTONSHIRE COUNCIL
Report by Chief Officer – Resources
Audit Committee: 9 August 2023
Subject: Internal Audit Plan 2023/24 – Progress to 18 July 2023
1. Purpose
1.1 The purpose of this report is to advise Members of progress at 18 July 2023
against the Internal Audit Plan for 2023/24.
1.2 The report also advises Members of:
• Recently issued Internal Audit reports and action plans; and
• Status of implementation progress relating to action plans from previously
issued Internal Audit reports.
2. Recommendations
2.1 It is recommended that Members note the contents of this report.
3. Background
3.1 The annual audit plan for 2023/24 was approved by the Audit Committee on 8
May 2023.  This report provides information on the progress in implementing
the plan.
3.2  When audit reports are issued by Internal Audit, an action plan is agreed with
management in relation to issues highlighted by the audit report.  Progress on
implementing the actions is monitored by Internal Audit on a monthly basis and
regularly reported to the Audit Committee.
4. Main Issues
4.1. The annual audit plan sets out the audit coverage for the year utilising available
staff resources to enable the Shared Service Manager – Audit & Fraud to provide
the annual internal audit opinion regarding the adequacy and effectiveness of
internal control within the Council.
4.2 In accordance with the risk-based audit methodology, for each audit, one of four
audit opinions is expressed:
Strong In our opinion there is a sound system of internal
controls designed to ensure that the organisation is
able to achieve its objectives.  
Satisfactory In our opinion isolated areas of control weakness
were identified which, whilst not systemic, put
some organisation objectives at risk.  
ITEM 5

Page 2

Requires Improvement In our opinion systemic and/or material control
weaknesses were identified such that some
organisation objectives are put at significant risk.
Unsatisfactory In our opinion the control environment was
considered inadequate to ensure that the
organisation is able to achieve its objectives.
4.3 Detailed findings and recommendations reported to management are graded using
the following criteria:   
Red In our opinion the control environment is insufficient to address the
risk and this could impact the Council as a whole. 
Corrective action must be taken and should start immediately. 
Overseen to completion by Corporate Management Team.
Amber In our opinion there are areas of control weakness which we consider
to be individually significant but which are unlikely to affect the
Council as a whole.
Corrective action must be taken (some exceptions may be agreed
with Internal Audit) within reasonable timeframe.
Overseen to completion by Chief Officer/Head of Service.
Green In our opinion the risk area is well controlled or our audit highlighted
areas for minor control improvement and/or areas of minor control
weakness. 
Process improvements/efficiencies may be actioned at management
discretion in consultation with Internal Audit.
Managed by service owner. 
Not reported in Audit Committee papers.
4.4 There were no audit reviews finalised since the last Audit Committee meeting in
June 2023.  The team are finalising reviews from the 2022/23 audit plan and
planning is now underway for the 2023/24 audit plan.
4.5 The status of the 2023/24 audit plan is attached at Appendix 1.
4.6 In relation to audit work for the Integration Joint Board, the 2022/23 audit plan is
almost complete and the agreed audit plan for 2023/24 will now be progressed with
regular reporting to the Integration Joint Board Audit & Performance Committee.
4.7 In relation to the Valuation Joint Board, the 2022/23 audit is complete.  Planning for
the 2023/24 audit plan has not started.
4.8 In relation to the Leisure Trust, the 2022/23 audit is complete.  Planning for the
2023/24 audit plan has not started.
4.9 Internal and External Audit Action Plans
In relation to audit action plans, these are monitored by Internal Audit on a monthly
basis.  There were 8 actions due for completion by the end of June, 4 of which have
been reported as completed by management and action dates in relation to 4
actions have been missed with revised dates now set.  The status report at 30 June
2023 is provided at Appendix 2.

Page 3

Ongoing Corporate Fraud Team Work
4.10 The Corporate Fraud team’s day to day work continues to focus on referrals relating
to council tax reduction/single person discounts, joint working with DWP in relation
to housing benefit and council tax reduction, referrals relating to housing tenancies
and investigating relevant national fraud initiative matches.
4.11 The Internal Audit Team and the Corporate Fraud Team continue to work together
as appropriate in order to ensure a joined-up approach to fraud investigation and
detection for example in relation to whistleblowing enquiries.
National Fraud Initiative
4.12 The National Fraud Initiative is a series of biennial exercises run by the Cabinet
Office and Audit Scotland to identify or prevent fraud and error by matching
electronic data held by public bodies. Participating bodies are required to
investigate data discrepancies within a timescale and report back on any savings.
4.13 The matches for the 2022 exercise have now been received and investigations are
underway.  To date 440 matches have been investigated with 1 fraud being
detected totalling £1,678 relating to a Housing Benefit/Student Loan match which is
being recovered.
Benchmarking
4.14 In accordance with the Council’s Strategic Improvement Framework, services
should undertake benchmarking activity with the equivalent function in other
Councils.  Therefore, the Council’s Internal Audit service has entered into a
benchmarking group which involves seven other Councils, these being:
• Argyll and Bute;
• Clackmannanshire;
• East Dunbartonshire;
• Falkirk;
• West Lothian;
• Inverclyde; and
• Stirling.
4.15 Meetings will continue to take place during 2023 to review performance against
agreed performance indicators and identify other areas for sharing of best
practice.    
5. People Implications
5.1 There are no people implications.
6. Financial and Procurement Implications
6.1 The Corporate Fraud Team activity can result in actual recoveries, charges and
re-billings.  Financial results to 30 June 2023 total £13,541.
6.2 There are no procurement implications arising from this report.

Page 4

7. Risk Analysis
7.1 There is a risk that failure to deliver the Internal Audit Plan would result in an
inability to provide a reasonable level of assurance over the Council’s system of
internal financial control to those charged with governance.  The main basis for
providing assurance is coverage of the planned risk-based audits.  Every
endeavour is made to ensure that no material slippage occurs in risk-based
audits by concentrating resources on these audits.
8. Equalities Impact Assessment (EIA)
8.1 There are no direct equalities impacts arising from the report however where an
agreed action results in a change in process this will be considered for equalities
impact by the relevant service.
9. Consultation
9.1 This report has been subject to consultation with appropriate Chief Officers.
10. Strategic Assessment
10.1 This report relates to strong corporate governance.
....................................
Laurence Slavin
Chief Officer - Resources
Date: 18 July 2023
Person to Contact: Andi Priestman, Shared Service Manager – Audit & Fraud
E-mail: andi.priestman@west-dunbarton.gov.uk
Appendices: 2023/24 Annual Audit Plan – Progress to 18 July 2023
(Appendix 1)
Status of Internal Audit Action Plans at 18 July 2023 (Appendix
2)
Background Papers: Audit Committee – 8 May 2023: Internal Audit Annual Plan
2023/24
Audit Committee – 21 March 2018: Counter Fraud and
Corruption Strategy
Internal Audit Reports - Copies available on request
Wards Affected: All wards