1. Purpose
1.1 The purpose of this report is to provide Members with an update on
treasury management to 31 August 2022.
2. Recommendations
2.1 Members are requested to:
(a) Note the treasury management stewardship information within the
appended report;
(b) Note the 2022/23 revised estimates of treasury and prudential
indicators as advised within the appended report (Tables A, B, C, D, E,
F, H, L and N); and
(c) Note that the appended report has been remitted to the Audit
Committee from Council to ensure further scrutiny takes place.
3. Background
3.1 In accordance with the Treasury Policy governing the Council’s treasury
management activities during 2022/23, the Chief Officer - Resources is
required to provide a mid year Report to Members regarding the Treasury
function.
3.2 The mid year report covers the period 1 April 2022 to 31 August 2022 and
details the current position (where appropriate) and revises the 2022/23
estimates where required.
3.3 The Audit Committee is responsible for ensuring effective scrutiny of the
treasury management strategy and policies and the report will be reported
to a future meeting of that Committee for further scrutiny.
4. Main Issues
Treasury Management Stewardship Report
4.1  A copy of the report is attached as Appendix 1.
ITEM 6

Page 2

4.2 The report provides details of key changes to the Council’s capital activity
(the prudential indicators), the economic outlook, the actual and proposed
treasury management activity (borrowing and investment) and the risk
approach to treasury management (the treasury management indicators).
4.3 The revised estimate for gross capital expenditure during 2022/23
(Table A) has increased by £21.458m from the original estimate due
to revision to the ongoing forecast outturn figures for both the General
Services capital plan and the HRA capital plan which are regularly
reported to Members (mainly additional slippage carried forward from
2021/22 following the year-end; additional spend linked to an increase
in grant income now anticipated; and slippage in spend projected for
2022/23).  
4.4 The external debt figures included within Table C includes both short
term and long term debt due to a strategy of using short term
borrowing to fund long term capital investment enabling the Council to
take advantage of lower interest rates.  
5. Option Appraisal
5.1 No option appraisal was required for this report.
6. People Implications
6.1 There are no personnel issues.
7. Financial and Procurement Implications
7.1 There are no direct financial or procurement implications arising from
this report.
8. Risk Analysis
8.1 Although the appended report provides a mid year position in relation
to treasury management there are three main risks associated with
the formulation of prudential indicators and the treasury management
strategy as detailed in Appendix 1.  These risks are noted below;
however the Council has robust monitoring processes in place and
provides regular reports to Council and ensures further scrutiny by
elected Members at the Audit Committee:
(a) Capital receipts which affect the capital financing and borrowing
requirement may not materialise and if this occurs then additional
borrowing will be required in order to fund the financing requirement;
(b) The risk of Counterparties default (i.e. loss of principal sum invested)
must also be taken into account; however the Council has robust

Page 3

controls included within its treasury management and investment
strategies that will assist in mitigating this risk; and
(c) Capital inflation may increase capital expenditure levels, which in
turn may affect the capital financing and borrowing requirement
leading to an increase in borrowing, assuming no additional capital
receipts are available.
9. Equalities Impact Assessment
9.1 No equalities impact assessment was required in relation to this
report.
10. Environmental Sustainability
10.1 No assessment of environmental sustainability was required in relation
to this report.
11. Consultation
11.1 The views of Legal Services have been requested on this report and
have advised there are neither any issues nor concerns.
12. Strategic Assessment
12.1 Proper budgetary control and sound financial practice are
cornerstones of good governance and support Council and officers to
pursue the 5 strategic priorities of the Council’s Strategic Plan.
12.2 Treasury management contributes to the Financial Strategy via the
interdependency that exists between pro-active treasury management
and the formulation of long term financial plans.
_______________________
Laurence Slavin
Chief Officer – Resources
Date: 19 October 2022
Person to Contact:  Jackie Nicol-Thomson, Finance Business Partner
Council Offices, Church Street, Dumbarton
Email: Jackie. NicolTomson@west-dunbarton.gov.uk
Appendix: Appendix 1: Mid Year Monitoring Report 2022/23
Treasury Management and Prudential Indicators 
1 April 2022 to 30 September 2022

Page 4

Background Papers: 1. Loans register and portfolio;
2. Debt rescheduling schedules; and
3. Prudential Indicators 2021/22 to 2031/32 and Treasury
Management Strategy 2022/23 to 2031/32 (Council 23
March 2022)