WEST DUNBARTONSHIRE COUNCIL
Report by Chief Officer – People & Technology
Audit Committee: 18th February 2026
___________________________________________________________________
Subject: Strategic Risks 2022-2027
1. Purpose
1.1 To provide an update on the strategic risks for 2022-27.
2. Recommendations
2.1 It is recommended that the Committee:
 Note the strategic risks as detailed at Appendix 1, and
 Endorse the removal of risk SR005.
3. Background
3.1 The Council’s 2022 – 2027 strategic risks were agreed by the Corporate
Services and Audit Committees in November 2022. The appended risks have
been reviewed with re-assessment undertaken before being reported to this
committee. This report is submitted as agreed to Audit Committee on a bi-
annual basis.
4. Main Issues
Strategic Risk
4.1 In line with the Council’s Risk Management Framework, a re-assessment of
the strategic risks has taken place as detailed within Appendix 1. Each risk is
managed through internal controls, linked actions and associated milestones
with the objective being to reduce or stabilise the level of risk through
completion of linked actions over a period and/or ensure mitigation factors are
adequate should the risks actually materialise.
4.2 Table 1 represents a risk dashboard that includes information on the original,
current and target rating for each strategic risk, as well as an assessment of
the current risk status. Each strategic risk is identified and supported by more
detailed information available on a “drill-down” basis in Appendix 1.
Six strategic risks associated actions and milestones are met and are
progressing as expected whilst getting closer to reaching their assigned
targets. SR001, SR007, SR008, and SR011 are currently off target, which is
explained in further detail below.
ITEM 7

Page 2

4.3 Following feedback from the Audit Committee meeting in September 2025, a
strategic review has been undertaken of SR005 ‘Engaging Positively with
Residents, Communities and Partnerships’. The review concluded that this
area no longer meets the criteria for a strategic risk and compared to other
strategic risks the milestones are less definitive and more challenging to
measure. This may lead to reporting being more subjective and unreliable. It
is recommended that SR005 be removed from the Strategic Risk Register.
The Chief Officer for Regulatory and Regeneration will assess whether the
residual elements of this risk should alternatively be monitored and managed
at a service level.

Page 3

Table 1 Key Strategic Risk Information
Strategic Risk Original
Risk
October
2022
Current
Risk
February
2026
Target
Risk
March
2027
Risk Status
Rationale
SR 001  Significant
financial funding
reductions/limitations
from Scottish Government
SR 002  Challenges in
implementing broad-
ranging school
improvement to raise
attainment and
achievement
SR 003  Maintaining
Council Assets that are fit
for purpose
SR 004  Keeping abreast
of developments in the
innovative use of
Information Technologies
SR 005  Engaging
positively with Residents,
Communities &
Partnerships
SR 006  Challenges in
protecting the Health and
Safety of Employees and
Others
SR 007  Complexities in
ensuring an appropriately
resourced and resilient
workforce

Page 4

Risk Methodology and Reporting
4.3 Each strategic risk is populated in Pentana in terms of the following template:
 Risk title and code;
 Description;
 Ownership;
 Potential effect;
 Measures of impact;
 Risk factors;
 Internal controls;
 Risk opportunity; and
 Linked actions.
4.4 Each risk has been scored using a “4 x 4” matrix for likelihood and impact in
relation to:
 Current risk (with review dates set at pre-determined intervals); and
 Target risk (i.e. 31 March 2027 - the duration of the Strategic Plan).
The risk descriptors used in the “4 x 4” matrix are as follows:
SR 008 Threat of Cyber
Attack
SR 009  Challenges in
delivering effective
services in relation to
Roads & Neighbourhoods
SR 010  Failure to
maintain Housing Stock
SR 011  Inability to
reduce carbon footprint in
line with targets

Page 5

Likelihood 
Score Descriptor
1 Unlikely
2 Likely
3 Very likely
4 Certain
Impact
Score Descriptor
1 Minor
2 Moderate
3 Significant
4 Critical
4.5 For ownership, each strategic risk is “Managed By” a Chief Officer and
“Assigned To” a Senior Officer. Strategic risks are also reported on a bi-
annual basis to the Performance & Monitoring Review Group.
Service Risk
4.6 Following the methodology in 4.3 to 4.4 above, each service has owned
operational risk registers in Pentana (the Council’s performance system)
which were reviewed as part of the 2025/26 service planning process.
4.7 Significant financial funding reductions/limitations from Scottish Government
It is expected the Council will continue to be faced with significant real term
funding reductions from the national settlement. This is based on the
Spending Review published by the Scottish Government in January 2026
which sets out multi-year spending plans over the three-year period 2026/27-
2028/29 across the various portfolios.  It illustrates that Local Government
funding, in cash terms, is expected to decrease by 0.07% over the three-year
period which will require councils to absorb the financial pressures brought
about by all inflationary increases.
4.8 Threat of Cyber Attack
This risk will always be high as the threat and likelihood of a Cyber Attack
remains. The UK public sector is still experiencing elevated levels of targeted
Cyber-attacks including recent attacks on Scottish councils. As this risk
continues to be high the emphasis remains on proactive measures to protect
the confidentiality, integrity and availability of our data, critical infrastructure,
and overall business operations.  
Key risks and continual threats include:

Page 6

 Geopolitical threat increasing due to current world tensions. Russia is
recognised by national security operations as the world’s largest cyber threat
actor.
 Demand for emerging technologies such as Artificial Intelligence solutions
present new challenges for the council to implement and secure.
 Risk to Backup technology and corruption of council data.
 Ransomware attacks – surge in recent years, potential for significant financial
loss and operational disruption.
 Advanced Persistent Threats (APT’s) – sophisticated stealthy attacks
conducted by well-resourced groups, targets include critical infrastructure,
government bodies and large corporations.
 User awareness – Phishing attempts on the rise with more sophisticated
techniques being deployed including voice and text phishing. Targeted threats
tailored to specific areas of the Council are being observed. Social
Engineering and ‘old school’ cyber-attacks now present a higher risk.
 Third Party Risks – The Council often relies on third party vendors and
suppliers, increasing the risk of cyber-attacks through the supply chain.
Mitigations:
 Implementation of a new Cyber Incident Logging and Response system
(MDR) offering enhanced protection.
 Continual improvement of our vulnerability/patch management systems and
processes.
 Continual promotion of Cyber awareness through simulated phishing
campaigns supported by our online security training and awareness platform.
 Social Engineering guidance issued to all employees with new ‘Be Cyber
Smart’ campaign.
 Engagement with ICT Security Partners to highlight and advise on specific
areas of risk.
 Continual assessment and improvement of our Cyber Security posture.
 Robust Business Continuity and Disaster Recovery plans with a new ICT
backup policy in place.
Progress continues to take place to improve our security posture in line with
the national Public Sector Action plan (PSAP) and Public Sector Network
(PSN) compliance. Vigilance of the National Cyber Security Centre (NCSC)
Cyber Security and Scottish Government (SC3) guidance continues to remain
in place.
4.9 Complexities in ensuring an appropriately resourced and resilient workforce
The risk rating remains scored at a 6. The difficult funding position means an
impact on an appropriately resourced and resilient workforce is expected, this
is now starting to become clear in the employee engagement measures in
place with fewer employees feeling valued than last year as reported at JCF
in September 2025. It is unlikely that this change will be reversed whilst
services continue to review structures and service delivery models in
response to the Council's financial challenges.

Page 7

The Workforce Planning Strategy is in place for 2022-2027. Additionally, the
People First Strategy covers the same period and consolidates several areas:
well-being, employee engagement, workforce planning, learning and
development and digital. A robust package of wellbeing resources continues
to be available, the council is recognised as a leading employer in terms of
adapting flexible working practices, attendance levels are closely monitored,
with personal stress and minor ailment absences currently prevalent.
Digital improvements continue to be prioritised with the ongoing roll out of M
365 Share point and the Fit for Future programme now focussing on corporate
processes with a view to identifying and reducing waste and duplication.
Reductions across the people support functions mean that there are ongoing
challenges in supporting services and this is being mitigated where possible
by using digital tools to free capacity and focussing on essential service
delivery activity, but it should be noted that service levels have been impacted
with certain activities ceasing such as regular HR attendance at management
meetings.
4.10 Inability to reduce carbon footprint in line with targets
The Council's emissions for 2024/25 were reported in November 2025
showing significant progress; 28.3% reduction on the previous year, 44.7%
reduction on 2012/13 baseline and 17.9% ahead of projected target. These
are positive steps however the main reduction is from the Council's scope 3
waste emissions, which is a result of shifting a significant amount of waste
from landfill to incineration through the Net Zero Cooperation Agreement with
Glasgow City Council.
Both scope 1 and 2 emissions increased slightly for 2024/25 period. To reach
a 61% reduction by 30/31 we need to reduce a further 16.3% in just over five
years and investment in required to reduce gas, electricity and diesel
consumption.
The long-term Climate Change Coordinator vacancy has been filled internally;
this currently leaves another vacancy within the energy team that will be filled
as soon as possible. Participation from service areas has increased at
Climate Change Action Plan meetings and emission reductions actions and
projects are forthcoming. The Council also has the opportunity to utilise
ClimateView and track trajectory to Net Zero, allowing actions and projects to
be prioritised and a more collective, strategic approach to be implemented.
The Council may be able to reduce the risk assessment of non-delivery of
carbon emissions targets, but further consideration is needed

Page 8

5. People Implications
5.1 There are no people implications associated with this report, other than in
relation to the mitigation of risk.
6. Financial and Procurement Implications
6.1 There are no financial and/or procurement implications directly associated
with this report however there are in relation to any expenditure linked to
mitigation.
7. Risk Analysis
7.1 Failure to ensure robust risk management is likely to result in the Council
being criticised by External Auditors for not having an integrated approach to
embedding risk management within the authority with the result that a “no
scrutiny required” status would not be achieved.
7.2 Progressing with a robust risk management approach will demonstrate that
the Council is taking ownership of risk management and ensuring effective
measures are in place. The ability to demonstrate risk ownership should
benefit the Council in terms of:
 Understanding risk and its potential impact on the Council’s priorities and
objectives;
 Reducing insurance premiums going forward by recognising that a mature
approach to risk management will contribute to a reduction in the number
and value of claims across a range of insurance classifications;
 Contributing towards incident prevention based upon post-incident
investigation;
 Meeting statutory/regulatory requirements; and
Ensuring better partnership working with external and internal partners.
8. Equalities Impact Assessment (EIA)
8.1 EIA 548 notes the positive impacts of an approach to risk that integrates
considerations on equalities, human rights health and social and economic
impacts that is aligned with the content of the new Strategic Plan.
9. Consultation
9.1 The strategic risks have been discussed with the Chief Officers and senior
management. The reports to committee are available to the Trades Union and
consultation undertaken as required.
9.2 The strategic risks have been cross checked with WD HSCP. This ensures
that issues affecting HSCP are reflected within the wider council strategic risk
report.

Page 9

10. Strategic Assessment
10.1 At its meeting on 26 October 2022, the Council agreed that its four main
strategic priorities for 2022 - 2027 are as follows:
 Our Communities - Resilient and Thriving
 Our Environment - A Greener Future
 Our Economy - Strong and Flourishing
 Our Council - Inclusive & Adaptable
10.2 The strategic risks have been identified to complement and underpin all
strategic priorities.
Name:   Victoria Rogers
Designation:   Chief Officer People & Technology
Date:   30th January 2026
Person to Contact: Harry McGhie, Risk & Health and Safety Officer
Harry.McGhie@west-dunbarton.gov.uk
Appendices: Appendix 1: Detailed Strategic Risk List
Background Papers: West Dunbartonshire Council Strategic Plan 2022-2027
Risk Management Framework
EIA screening