Page 1

West Dunbartonshire Council 
Report by the Chief Officer - Resources 
Audit Committee - 24 September 2025 
Subject: 2024/25 Treasury Management Annual Report 
1. Purpose 
1.1 The purpose of this report is to advise the Committee of the operation of the
treasury function and its activities in 2024/25 and request that the Committee
remits the report to the full Council for their approval. 
2.  Recommendations 
2.1 Committee to note the contents of the 2024/25 Annual Treasury Management
Report. 
2.2 Committee to remit the 2024/25 Annual Treasury Management Report. 
to full Council for approval. 
3. Background 
3.1 In accordance with the Treasury Policy governing the Council’s treasury
management activities the Chief Officer - Resources is required to provide an
Annual Report to Members regarding the Treasury function. 
3.2 One of the key clauses is that a responsible body is required to ensure effective
scrutiny of the treasury management strategy and polices.  Within West
Dunbartonshire Council the body identified to fulfil this role is the Audit Committee. 
4. Main Issues 
2024/25 Treasury Management Annual Report 
4.1 A copy of the 2024/25 Treasury Management Annual Report is attached (Appendix
1) with it based upon the Council’s unaudited 2024/25 Financial Statements. 
4.2 The report details the loans borrowed and repaid during the course of the year,
associated interest rates and debt rescheduling undertaken.  
4.3 External borrowing (excluding Public Private Partnership (PPP) borrowing and
leases) has increased during the year from £718.597m at the beginning of the
year to £789.860m at the end of the year. This was mainly due to capital
expenditure and the repayment of temporary loans. Over the year as new
debt has been borrowed and maturing debt replaced, the average interest
Item 7
Page 55
Pre-Agenda Drafts

Page 2

rate on loans held has decreased from 4.48% at 31 March 2024 to 4.35% at
31 March 2025. 
4.4 Consideration was given to available interest rates, and mainly short-term
borrowing has been utilised to finance the current capital programme to take
advantage of slightly lower interest rates.   
4.5 Investments have decreased as at the 31 March 2025 from £28.997m at the
beginning of the year to £13.820m at the year-end. The average interest rate
on these investments held as at 31 March 2025 decreased from 4.62% to
4.51%. 
4.6 As at 31 March 2025 fixed rate borrowing under 12 months was 39.29%. This is
below the maximum allowable limit for short term debt and is as a result of action
taken to reprofile the debt from short term to long loans. We will continue to take
action with a longer term target to bring short term borrowing toward a figure less
than 30% of the overall debt portfolio however this needs to be done prudently
whilst monitoring projected future interest rates. All other year end indicators
advised within Appendix 1 of this report are within the limits previously agreed by
Council. 
5. Option Appraisal 
5.1 No option appraisal was required for this report. 
6. People Implications 
6.1 There are no personnel issues. 
7. Financial and Procurement Implications 
7.1 There are no financial or procurement implications. 
8. Risk Analysis 
8.1 There are three main risks associated with the formulation of prudential
indicators. These are noted below. However the Council has robust
monitoring processes in place and provides regular reports to Council and
ensures further scrutiny by elected Members at the Audit Committee: 
(a) The risk of Counterparties default (i.e. loss of principal sum invested)
however, the Council has robust controls included within its treasury
management and investment strategies that will assist in mitigating this risk. 
(b) Capital inflation may increase capital expenditure levels, which in turn may
affect the capital financing and borrowing requirement leading to an increase
in borrowing, assuming no additional capital receipts or other funding are
available.   
Page 56
Pre-Agenda Drafts

Page 3

(c) Capital receipts which affect the capital financing and borrowing requirement
may not materialise which would require additional borrowing to fund the
financing requirement. 
9. Equalities Impact Assessment 
9.1 No equalities impact assessment was required in relation to this report. 
10. Environmental Sustainability 
10.1 No assessment of environmental sustainability was required in relation to this
report 
11.  Consultation 
11.1 The views of Legal Services have been requested on this report and have
advised there are neither any issues nor concerns. 
12. Strategic Assessment 
12.1 Proper budgetary control and sound financial practice are cornerstones of
good governance and support Council and officers to pursue the 5 strategic
priorities of the Council’s Strategic Plan. 
12.2 Treasury management contributes to the Financial Strategy via the
interdependency that exists between pro-active treasury management and the
formulation of long term financial plans. 
Laurence Slavin
Chief Officer - Resources
Date: 27 August 2025 
Person to Contact:  Lynsey Dickson, 
Finance Business Partner    
Council Offices, Church Street
Email: Lynsey.Dickson@west-dunbarton.gov.uk 
Appendix: Appendix 1 - Annual Report 2024/25 -Treasury Management
and Actual Prudential Indicators 
Background Papers: Loans register and portfolio;    
Debt rescheduling schedules;
Prudential Indicators 2024/25 to 2033/34 and Treasury
Management Strategy 2024/25 to 2033/34
(Council 26 March 2025); 
Page 57
Pre-Agenda Drafts

Page 4

Mid-Year Monitoring Report 2024/25 - Treasury
Management and Prudential Indicators (Council 18
December 2024); and
Treasury Management Annual Report 2023/24 (Council
18 December 2024)
Local Government Finance Circular 5/2022 - statutory
repayment of debt – short term financial flexibility:
guidance 
Wards Affected:  No wards directly affected.
Page 58
Pre-Agenda Drafts