Page 1

Planning and Regulatory Services Committee 
Tuesday, 20 December 2022 
NOTICE IS HEREBY GIVEN that a Meeting of the Planning and Regulatory
Services Committee is to be held at Council Chambers, Council Office, High
Street, Elgin, IV30 1BX on Tuesday, 20 December 2022 at 09:30. 
BUSINESS 
1 Sederunt 
2 Declaration of Group Decisions and Members Interests * 
3 Resolution
Consider, and if so decide, adopt the following resolution:
"That under Section 50A (4) and (5) of the Local Government
(Scotland) Act 1973, as amended, the public and media
representatives be excluded from the meeting for Item 14 and 15 of
business on the grounds that it involves the likely disclosure of exempt
information of the class described in the relevant Paragraphs of Part 1
of Schedule 7A of the Act.”   
4 Minute of Meeting dated 25 October 2022 7 - 50
5 Written Questions ** 
Guidance Note 51 - 52
6 Planning Application 22/01104/APP
Report by Appointed Officer  
Proposed new recycling building at Grays Recycling Ltd Nether Dallachy
Spey Bay Fochabers for Grays Recycling Services Ltd  
53 - 86
Page 1

Page 2

7 Planning Application 22/01544/APP
Report by Appointed Officer  
Change of use from agricultural use to temporary outdoor nursery to be
used March to October 2023 during the refurbishment and extension of
the nursery at Aberlour Primary School at New Cemetery Aberlour
Cemetery High Street Aberlour for Moray Council  
87 -
134
8 Planning Application 2200410APP_Redacted 135 -
176
9 Planning Application 2200563APP_Redacted 177 -
266
10 Planning Application 2201269APP_Redacted 267 -
316
11 Development Plan Scheme 2023 - Moray Local
Development Plan 2027
Report by Depute Chief Executive (Economy, Environment and
Finance)  
317 -
344
12 Planning Policy Guidance - Moray Local Development
Plan 2020
Report by Depute Chief Executive (Economy, Environment and
Finance)  
345 -
352
13 Question Time ***
Consider any oral question on matters delegated to the Committee in
terms of the Council's Scheme of Administration. 
Item(s) which the Committee may wish to consider with
the Press and Public excluded   
14 Review of Tree Preservation Orders [Para 13]
• Information, which if disclosed to the public, would reveal that the
Authority proposes, for the purposes of consultation, make an
order or direction under any enactment which might allow an
individual or organisation to defeat the purpose of the notice or
order; 
15 Tree Preservation Order [Para 13]
• Information relating to instructions to counsel any opinion of
counsel and any advice received, information obtained or action to
be taken in connection with any legal proceedings; 
Page 2

Page 3

Summary of Planning and Regulatory Services
Committee functions:
Town and Country Planning; Building Standards; Environmental
Health; Trading Standards; Weights & Measures, Tree Preservation
Orders, and Contaminated Land issues.     
Watching the Meeting
Any person wishing to attend the meeting should contact
customer services on 01343 563217 prior to the meeting as the
number of attendees is restricted due to the recent Covid
pandemic  
You can however watch the webcast of the meeting by going to :
http://www.moray.gov.uk/moray_standard/page_43661.html 
Page 3

Page 4

GUIDANCE NOTES 
* Declaration of Group Decisions and Members Interests - The Chair of the
meeting shall seek declarations from any individual or political group at the
beginning of a meeting whether any prior decision has been reached on how
the individual or members of the group will vote on any item(s) of business on
the Agenda, and if so on which item(s).  A prior decision shall be one that the
individual or the group deems to be mandatory on the individual or the group
members such that the individual or the group members will be subject to
sanctions should they not vote in accordance with the prior decision.  Any such
prior decisions will be recorded in the Minute of the meeting. 
** Written Questions - Any Member can put one written question about any
relevant and competent business within the specified remits not already on the
agenda, to the Chair provided it is received by the Proper Officer or Committee
Services by 12 noon two working days prior to the day of the meeting.  A copy
of any written answer provided by the Chair will be tabled at the start of the
relevant section of the meeting.  The Member who has put the question may,
after the answer has been given, ask one supplementary question directly
related to the subject matter, but no discussion will be allowed. 
No supplementary question can be put or answered more than 10 minutes after
the Council has started on the relevant item of business, except with the
consent of the Chair. If a Member does not have the opportunity to put a
supplementary question because no time remains, then he or she can submit it
in writing to the Proper Officer who will arrange for a written answer to be
provided within 7 working days. 
*** Question Time - At each ordinary meeting of the Committee ten minutes will be
allowed for Members questions when any Member of the Committee can put a
question to the Chair on any business within the remit of that Section of the
Committee.  The Member who has put the question may, after the answer has
been given, ask one supplementary question directly related to the subject
matter, but no discussion will be allowed. 
No supplementary question can be put or answered more than ten minutes
after the Committee has started on the relevant item of business, except with
the consent of the Chair.  If a Member does not have the opportunity to put a
supplementary question because no time remains, then he/she can submit it in
writing to the proper officer who will arrange for a written answer to be provided
within seven working days. 
Page 4

Page 5

THE MORAY COUNCIL 
Planning and Regulatory Services Committee 
SEDERUNT 
Councillor David Gordon  (Chair)
Councillor Marc Macrae  (Depute Chair)  
Councillor Neil Cameron  (Member)
Councillor John Cowe  (Member)
Councillor John Divers  (Member)
Councillor Amber Dunbar  (Member)
Councillor Donald Gatt  (Member)
Councillor Sandy Keith  (Member)
Councillor Scott Lawrence  (Member)
Councillor Graham Leadbitter  (Member)
Councillor Paul McBain  (Member)
Councillor Derek Ross  (Member)
Councillor Draeyk Van Der Horn  (Member)
Councillor Sonya Warren  (Member)  
Clerk Name: Lissa Rowan
Clerk Telephone: 07765 741754
Clerk Email: committee.services@moray.gov.uk 
Page 5

Page 6

Page 6

Page 7

MORAY COUNCIL 
MINUTE OF THE MEETING OF THE PLANNING AND REGULATORY SERVICES
COMMITTEE 
25 OCTOBER 2022 
COUNCIL CHAMBERS, ELGIN 
PRESENT 
Councillors Gordon (Chair), Macrae, Cameron, Cowe, Divers, Dunbar, Gatt, Keith,
Lawrence, Leadbitter, McBain, Ross, Van Der Horn and Warren. 
IN ATTENDANCE 
Head of Economic Growth and Development, Development Management and
Building Standards Manager, Mr N MacPherson, Principal Planning Officer, Mr R
Smith, Principal Planning Officer, Strategic Planning and Development Manager, Ms
Webster, Principal Planning Officer (Strategic Planning and Development), Mrs D
Anderson, Senior Engineer (Transportation),  Ms L MacDonald, Senior Planning
Officer, Ms R MacDougall, Senior Planning Officer, Legal Services Manager and Mrs
L Rowan, Committee Services Officer as Clerk to the Committee. 
1. DECLARATION OF GROUP DECISIONS AND MEMBER’S INTERESTS 
In terms of Standing Order 20 and the Councillors’ Code of Conduct, there were no
declarations from Group Leaders or Spokespersons in regard to any prior decisions
taken on how Members will vote on any item on the agenda. 
Councillor Ross advised the Committee that, in respect of Item 8 “Town Centre
Improvement Plan” his wife is the Chair of the Speyside Community Council and had
submitted representations on behalf of the organisation however, following advice
from the Legal Adviser, was content that this did not preclude him from taking part in
the debate.  Councillor Gatt also confirmed, in respect of Item 8 “Town Centre
Improvement Plan” he had made a representation during the public consultation and
sought advice from the Legal Adviser as to whether this would preclude him from the
debate.  In response, the Legal Adviser advised that, as this was not a quasi-judicial
meeting or in relation to any planning application, then this would not stop Councillor
Gatt participating in the debate.  The Chair also stated that he had made a
representation during the consultation for Item 8 “Town Centre Improvement Plan”
however this was prior to becoming a Councillor and stated that he would take part
in the debate of this item.  Councillor Van Der Horn confirmed, in respect of Item 6
“Planning Application 22/01094/AMC” that he lives in Findhorn and is aware of the
site however, having consulted with the Legal Adviser, was content that he could
fairly consider the application.   
Subject to these clarifications, there were no declarations of Member’s interests in
respect of any item on the agenda. 
2. MINUTE OF MEETING DATED 16 AUGUST 2022
Item 4
Page 7

Page 8

The minute of the meeting of the Planning and Regulatory Services Committee
dated 16 August 2022 was submitted and approved. 
3. WRITTEN QUESTIONS 
The Committee noted that no written questions had been submitted. 
4. PLANNING APPLICATION 22/00499/APP 
Ward 2 – Keith and Cullen 
Proposed quarry extension at Cairdshill Quarry Keith Moray AB55 5PA for
Tarmac Caledonian Ltd 
A report was submitted by the Appointed Officer recommending that, for reasons
detailed in the report, planning permission be granted for a proposed quarry
extension at Cairdshill Quarry Keith Moray AB55 5PA for Tarmac Caledonian Ltd. 
It was noted that the application had been referred to Committee in terms of the
Scheme of Delegation as the application is a major development ad defined under
the Hierarchy Regulations 2009 because the site area exceeds 2 ha. 
Following consideration, the Committee agreed to grant planning permission in
respect of Planning Application 22/00499/APP subject to the conditions detailed
within the report. 
1. The permission hereby granted shall be for a limited period only and shall
cease to have effect on 41 years the initiation of development (the 'cessation
date') by which time and prior to that cessation date, the application site shall
be cleared of all development approved or involved in implementing the terms
of the permission hereby granted (including all mobile plant and machinery, any
ancillary works, infrastructure, fixtures and fittings, etc.), and the site shall be
re-instated in accordance with a restoration and aftercare scheme which shall
previously have been submitted to and approved in writing by the Council, as
Planning Authority (see Condition 3 below). Written confirmation of the date of
initiation of development shall be submitted to the Council, as planning
authority prior to commencement of development (see notes regarding
submission of Notification of Initiation of Development attached to this decision
notice). 
Reason: To ensure an acceptable form of development enabling the
development to progress in accordance with the applicant's submitted
particulars to allow for full extraction of available resources and site restoration
thereafter, and to retain control over the use of the site and enable further
consideration to be given to the operations, effects and impact of the use upon
the amenity, character and appearance of the site and surrounding area
together with securing removal of all site infrastructure used in the extraction
process prior to embarking upon the restoration of the site. 
2. Except where otherwise provided for, or agreed and/or amended by the terms
of this permission, the applicant/operator shall operate the development in
Page 8

Page 9

accordance with the provisions of the application, the Environmental Review
supporting document by Dalgleish Associates Limited, dated March 2022, titled
"Proposed Extension to Cairdshill Quarry, Keith" and the plans hereby
approved. For the avoidance of doubt this shall include compliance with the
mitigation measures listed in table 13.1 on pages 188 to 190 inclusive of the
Environmental Review (unless otherwise specified/controlled by conditions
within this decision notice) and adherence to the Waste Management Plan
(Appendix 3). 
Reason: To ensure an acceptable form of development in accordance with the
submitted particulars and in order to safeguard the amenities, character and
appearance of the locality within which the proposal is located. 
3. Notwithstanding the indicative final site restoration plan shown on drawing
C161-00055-13 (which is not approved) at least one (1) year prior to completion
of mineral workings ceasing on the site, a Site Specific Restoration and
Aftercare Plan shall be submitted to and approved in writing by the Council, as
planning authority in consultation with SEPA. The plan shall be in accordance
with the information detailed within Sections 3 and 4 (Development Proposals
and Restoration and Aftercare) of the Environmental Review supporting
document by Dalgleish Associates Limited, dated March 2022, and include (but
not be limited to) the following information:
a) the arrangement for the removal of all buildings and structures (both
mobile and fixed plant, etc.) from the site; 
b) details of the finalised landform to be provided on site, including all
water/pond areas and all areas of site mounding or regrading of
excavated material to be retained or provided as part of the landform
together with elevations, cross and long sections and existing and finished
levels details (relative to a fixed datum); 
c) the provisions for re-instatement for after-uses to include agricultural
grassland, species rich grassland, woodland/tree and shrub/scrub
planting, ephemeral wetland, marginal planting and bare ground and
habitat creation as proposed within the Environmental Review supporting
document including sections and finished ground levels to show the
finished profile of the re-instated ground; 
d) landscaping and planting/seeding information associated with the
proposed formation of all identified habitats (to include species, girth,
height, siting etc.); 
e) details of stock proof fencing; and 
f) the arrangements for the monitoring and aftercare scheme which shall
specify all the steps to be taken and the time periods within which the
steps will be taken (to be a minimum of 5 years); any seeding, trees or
shrubs that die or become seriously damaged or diseased within 5 years
of planting shall be removed and replaced by others of a similar size and
species within the next planting season). 
Thereafter, the restoration of the site and aftercare shall be carried out in
accordance with the approved details. 
Reason: To retain control over this development and ensure that the site is
appropriately restored in the interests of the protection of the environment, as
these details are currently lacking from the application. 
4. No works in connection with the development hereby approved shall
Page 9

Page 10

commence unless an archaeological written scheme of investigation (WSI) has
been submitted to and approved in writing by the planning authority and a
programme of archaeological works has been carried out in accordance with
the approved WSI. The programme of works shall comprise a 5% trial trenching
evaluation of the proposed development area, and be carried out by a suitably
qualified archaeological contractor. The WSI shall include details of how the
recording and recovery of archaeological resources found within the application
site shall be undertaken, and how any updates, if required, to the written
scheme of investigation will be provided throughout the implementation of the
programme of archaeological works. Should the archaeological works reveal
the need for post excavation analysis the development hereby approved shall
not be brought into use unless a post-excavation research design (PERD) for
the analysis, publication and dissemination of results and archive deposition
has been submitted to and approved in writing by the planning authority. The
PERD shall be carried out in complete accordance with the approved details. 
Reason: To safeguard and record the archaeological potential of the area. 
5. In respect of existing private water supply infrastructure identified as being
affected by the development, prior to the commencement of the development
hereby approved, details of the measures to be taken to protect the quality and
quantity of existing water supplies (or to provide replacement supplies) shall be
submitted to and agreed in writing by the Council, as Planning Authority.
Thereafter, the measures will be implemented in accordance with the agreed
details. 
Reason: To ensure that the development does not impact on the sufficiency
and wholesomeness of water supply to existing neighbouring properties. 
6. No development or works shall commence within the extension area until the
area has been enclosed by a stock proof fence which shall be maintained
thereafter for the lifetime of the consent and until the restoration scheme is
complete.   
Reason: In the interests of the safety of the public and of livestock and in order
to control the working of the site within the approved boundaries. 
7. Unless otherwise agreed with the Council, as Planning Authority the annual
rate of extraction shall not exceed 75,000 tonnes and the operator shall
maintain records of output/production from the excavated area, to be made
available to the Council, as Planning Authority at any time and on request. 
Reason: In order to retain control over the working of the site and its impact on
the area. 
8. All quarry operations shall be carried out and permitted between 0700 - 1800,
Monday to Friday, and 0700 - 1230, Saturdays and at no other times without
the written consent of the Council, as planning authority in consultation with the
Environmental Health Manager, notwithstanding the separate time periods in
condition 16 which specifically relate to blasting times. 
Reason: In order that the times of quarry operations are controlled to minimise
disturbance to local residents. 
Page 10

Page 11

9. During the normal daytime working hours defined in the above condition, the
free-field Equivalent Continuous Noise Level (LAeq,1hr) for the period,
excluding bund formation, soil and overburden handling activity and quartzite
drilling operations, shall not exceed the greater of 45dB(A) or the background
sound level + 10 dB for daytime operations, as determined at any existing noise
sensitive property. For the avoidance of doubt the average background sound
level (L A 90) at dwellings is stated in Tables 1.1 to 1.4 of noise impact
assessment supporting document by Vibrock Limited, dated 29 March 2022,
reference R22.11375/1/RK and titled "Noise Impact Assessment. Cairdshill
Quarry Extension, Morayshire. Dalgleish Associates Limited." 
Reason: In order that noise from the development is controlled so as not to
cause noise nuisance to local residents. 
10. During the normal daytime working hours defined in condition 8, the free-field
Equivalent Continuous Noise Level (LAeq,1hr) from quartzite drilling
operations, shall not exceed 55dB(A), as recorded at any existing noise
sensitive property and be limited to a period not exceeding 10 days in any
calendar year. 
Reason: In order that noise from the development is controlled so as not to
cause noise nuisance to local residents. 
11. Noise from soil and overburden handling shall not exceed the free-field
Equivalent Continuous Noise level ( LAeq,1hr ) of 70 dB(A) at any existing
noise sensitive property and be limited to a period not exceeding 8 weeks in a
year at any one property. 
Reason: In order that noise from the bund formation phase of development is
controlled and that the duration of this activity is limited in duration, so as not to
cause noise nuisance to local residents. 
12. Broad spectrum white noise vehicle reversing alarms shall be installed on all
vehicular quarry plant. 
Reason: In order that noise from the development is controlled so as not to
cause noise nuisance to local residents. 
13. At the reasonable request of the Planning Authority, following a complaint
relating to noise from quarry operations at the development, the developer shall
measure at its own expense noise emissions as they relate to the permitted
consent limits, having regard to measurement locations and methodologies as
detailed in Planning Advise Note 'PAN50, Annex A: The Control of Noise at
Surface Mineral Workings'. The results of such monitoring shall thereafter be
forwarded to the Planning Authority. In the event of a breach of noise limits a
scheme of mitigation shall be brought into action and its implementation agreed
with the Planning Authority. 
Reason: In order that noise from the development is controlled so as not to
cause noise nuisance to local residents. 
14. Prior to the development hereby approved commencing, a written scheme to
control blasting operations shall be submitted and agreed with the Planning
Page 11

Page 12

Authority. The results of monitoring associated with the agreed scheme shall be
made available in writing to the Planning Authority on request. 
Reason: In order that blasting operations are considered and managed, in
order to protect local residents. 
15. Ground vibration as a result of blasting operations at the development shall not
exceed a peak particle velocity of 6 mms-1 (95% confidence level) at residential
properties, with no individual blast exceeding a peak particle velocity of 12mms-
1. The measurement shall be the maximum of 3 mutually perpendicular
directions taken at the ground surface at any vibration sensitive building. 
Reason: In order that vibration associated with blasting from the development
is controlled so as not to cause nuisance to local residents. 
16. No blasting shall be carried out on the site except between the following times
(1000 and 1200 hours) and (1400 and 1600 hours) Monday to Fridays and
(1000 and 1200 hours) on Saturday. There shall be no blasting or drilling
operations on Sundays, Bank Holidays or National Holidays. 
Reason: In order that the times of blasting operations are controlled to
minimise disturbance to local residents. 
17. The above condition 16 shall not apply in cases of emergency when it is
considered necessary to carry out blasting operations in the interests of safety.
The Planning Authority shall be notified in writing immediately of the nature and
circumstances of any such event. 
Reason: In order that that the Planning Authority is informed of any emergency
situation where the above condition cannot be met. 
18. A Site Dust Management Plan for the site shall be maintained throughout the
lifetime of the development in accordance with Section 9.9 of the Environmental
Review supporting document by Dalgleish Associates Limited, dated March
2022, and titled "Proposed Extension to Cairdshill Quarry, Keith." 
Reason: In order to ensure that dust emissions are considered and managed,
in order to prevent dust nuisance to local residents. 
19. Prior to the development hereby approved commencing details of the
operational site lighting shall be submitted to and agreed in writing by the
Planning Authority, in consultation with the Environmental Health Manager.
Thereafter, the agreed lighting details shall be maintained throughout the
lifetime of the development. 
Reason: In order to ensure that light emissions are controlled so as not to give
rise to a nuisance to local residents. 
20. Prior to the commencement of any works associated with the establishment or
undertaking of new quarrying operations or within 3 months of the issue of
planning consent (whichever is soonest) the applicant must submit the following
information for approval by the Planning Authority in consultation with the
Roads Authority:
Page 12

Page 13

a. Details (Plans scale 1:500 min and Management Strategy) for the
provision of physical and other mitigation measures to prevent the
discharge of water and loose material from the site onto the public road. 
Reason: To ensure the safety and free flow of traffic on the public road and
access to the site by minimising the road safety impact from extraneous
material and surface water in the vicinity of the new access. 
21. Prior to the commencement of any works associated with the establishment or
undertaking of new quarrying operations visibility splays of 2.4 metres by 70
metres (minimum) in both directions, shall be provided at both accesses to the
development onto the U43h, clear of any obstruction above 0.6 metres in
height, measured from the level of the carriageway. 
Thereafter the visibility splays shall be maintained for the lifetime of the use of
the accesses. 
Reason: To enable drivers of vehicles entering or exiting the site to have a
clear view so that they can undertake the manoeuvre safely and with the
minimum interference to the safety and free flow of traffic on the public road. 
22. Prior to the commencement of any works associated with the establishment or
undertaking of new quarrying operations or within 3 months of the issue of
planning consent (whichever is soonest) the applicant must submit the following
information for approval by the Planning Authority in consultation with the
Roads Authority: 
Plans (1:500 min) showing the location and design of road improvement works
to widen the U43h to a minimum of 7.3m over a continuous length of 100m
from the site access eastwards towards the A96 with bend widening and
geometry changes and associated improvements to road verges,  drainage and
boundary treatments and cutting back of vegetation within the road envelope as
necessary to accommodate two-way unopposed HGV traffic movements and
resurfacing of the full width of the carriageway over 20 metres centred on each
of the site entrances and exits. 
Thereafter, prior to the commencement of any works associated with the
establishment or undertaking of new quarrying operations the works shall be
completed in accordance with the approved details. 
Reason: To ensure an acceptable development in road safety terms through
the provision of details currently lacking and/or incorrectly shown on the
submitted particulars to date. 
23. No development shall take place until documentary evidence has been
submitted to and approved in writing by the Council, as Planning Authority
demonstrating that the Restoration Guarantee Fund from the Minerals Products
Association (MPA) is available and can be implemented, should it prove
expedient to do so.  The operator shall provide annual confirmation of
continuing membership of the MPA.  In the event that, for any reason, the
operator ceases to be a member of the MPA it shall within 31 days produce to
the Council a performance bond, for a sum to be agreed between the parties,
both acting reasonably, and granted by a UK bank or other approved financial
provider. 
Page 13

Page 14

Reason: To ensure adequate restoration of the site. 
24. The Water Management Plan and embedded mitigation measures as detailed
within the submitted Hydrological and Hydrogeological Assessment (Section
6.7 refers) and Drainage Strategy (Appendix 5) of the Environmental Review
supporting document prepared by Dalgleish Associates Limited, dated March
2022, shall be fully implemented by the applicant/operator, unless otherwise
agreed in writing with the Council, as Planning Authority.   
Reason: To ensure adequate protection of the water environment and to
prevent potential pollution impacts. 
25. No works in connection with the development hereby approved shall
commence until detailed calculations, scaled drawings, cross sections and
specifications for the attenuation and flow control device for the development
have been submitted to and approved in writing by the Council, as Planning
Authority. These shall be in accordance with the details outlined in the
submitted Drainage Strategy (Appendix 5) and Hydrological and
Hydrogeological Assessment of the Environmental Review supporting
document prepared by Dalgleish Associates Limited, dated March 2022.
Thereafter the development shall be carried out in accordance with these
approved details.  
Reason: To ensure that surface water drainage is provided and complies with
the principles of SUDs in order to protect the water environment. 
26. The rights permitted under Paragraphs 1a and 1b of Class 55 of the Town and
Country Planning (General Permitted Development) (Scotland) Order 1992, are
hereby withdrawn.  The installation of any buildings not specified in the
planning application will require the prior approval of the Council, as planning
authority in accordance with Class 56. 
Reason: In the interests of residential amenity and to ensure that the Planning
Authority retains control over the future use of the site. 
27. Notwithstanding the indicative final site restoration plan shown on drawing
C161-00055-13 (which is not approved) prior to the phased restoration works
during Phase 1 (regrading and planting of northern overburden mound and
eastern quarry edge) a Restoration and Aftercare Plan shall be submitted to
and approved in writing by the Council, as planning authority. The plan shall be
in accordance with the information detailed within Sections 3 and 4
(Development Proposals and Restoration and Aftercare) of the Environmental
Review supporting document by Dalgleish Associates Limited, dated March
2022, and include (but not be limited to) the following information:
a) details of the finalised landform to be provided on site during phase 1,
including all areas of site mounding or regrading of excavated material to
be retained or provided as part of the landform together with elevations,
cross and long sections and existing and finished levels details (relative to
a fixed datum); 
b) landscaping and planting/seeding information associated with the
proposed formation of all identified habitats (to include species, girth,
height, siting etc.); and
Page 14

Page 15

c) the arrangements for the monitoring and aftercare scheme which shall
specify all the steps to be taken and the time periods within which the
steps will be taken (to be a minimum of 5 years); any seeding, trees or
shrubs that die or become seriously damaged or diseased within 5 years
of planting shall be removed and replaced by others of a similar size and
species within the next planting season). 
Thereafter, the restoration of the site and aftercare during phase 1 shall be
carried out in accordance with the approved details. 
Reason: To retain control over this development and ensure that the site is
appropriately restored in the interests of the protection of the environment, as
these details are currently lacking from the application. 
28. The development to which this permission relates must be begun not later than
the expiration of 3 years beginning with the date on which the permission is
granted. 
Reason: The time limit condition is imposed in order to comply with the
requirements of section 58 of the Town and Country Planning (Scotland) Act
1997 as amended. 
5. PLANNING APPLICATION 21/01963/APP 
Ward 3 – Buckie 
Proposed residential development (Phase 1) associated landscaping and
infrastructure and demolition of existing dwellinghouse at R7 Land at Muirton,
Muirton Way, Buckie, Moray for Morlich Homes Ltd 
A report was submitted by the Appointed Officer recommending that, for reasons
detailed in the report, planning permission be granted for a proposed residential
development (Phase 1) associated landscaping and infrastructure and demolition of
existing dwellinghouse at R7 Land at Muirton, Muirton Way, Buckie, Moray for
Morlich Homes Ltd 
It was noted that the application had been referred to Committee in terms of the
Scheme of Delegation as the proposal exceeds 50 house units and falls within the
category of a major development as defined in the Town and Country Planning
(Hierarchy of Developments) (Scotland) Regulations 2009. 
During his introduction, Mr MacPherson, Principal Planning Officer advised the
Committee that, in relation to Condition 7, 2 reasons for the condition had been
included in error and that the Committee should disregard the first one as this was
covered in the second reason.  This was noted. 
During discussion surrounding access to the cemetery, concern was raised in
relation to how buses will enter and exit the cemetery and the impact this may have
on Alba Road. 
In response, Mrs Anderson, Senior Engineer (Transportation) advised that access to
the cemetery is a matter for the Lands and Parks Service however she was aware of
proposed changes to ensure that it is suitable for pedestrians and that occasional
Page 15

Page 16

use of Alba Place may be required if there are buses transporting people to the
cemetery.  Mrs Anderson further assured the Committee that buses are no larger
than refuse collection vehicles, which Alba Road was able to accommodate however
would continue to monitor the use of Alba Road to ensure that there is no adverse
impact. 
In relation to EV Charging Points detailed in Condition 22, Councillor Van Der Horn
queried whether this condtion could be amended as follows “No development shall
be occupied until the plan includes EV charging infrastructure”. 
In response, Mr MacPherson, Principal Planning Officer suggested the following
wording “a detailed plan of all EV charging for houses flats and communal parking be
provided and no houses and flats occupied until this is in place”.  However, following
the meeting, and after reviewing the Site Plan (Drawing 19-39/PL/02 Rev B), it was
noted by Officers that EV local points are already detailed and that further details are
also provided on the house type plans for many plots where the point of connection
is on the building.  Taking this into consideration, it was considered that there was no
requirement to amend Condition 22 and the following rewording of Condition 22 was
agreed in conjunction with the Chair and Councillor Van Der Horn. 
“The provision of EV charging infrastructure shall be implemented in accordance with
drawing number 19-39/PL/02 Rev B “Phase 1 Site Plan - Including housing mix and
schedule” and approved house plans showing EV charging infrastructure. No house
or flat shall be occupied until the EV charging infrastructure associated with the
parking for the unit has been provided and made available for connection of an EV
charging unit. 
Thereafter the development shall be completed in accordance with the approved
details.” 
During further discussion surrounding the provision cycle storage, it was asked that a
condition be added to ensure safe, secure, weatherproof cycle storage for all units
that have no secure garden or garage in the development. 
In response, Mrs Anderson, Senior Engineer (Transportation) advised that Condition
17b related to cycle storage and Mr MacPherson, Principal Planning Officer agreed
to amend this to ensure cycle storage for all units with no secure garden or garage. 
With regard to the access to the development at the junction at Barhill Road, concern
was raised that this is a challenging junction and it was queried whether any
additional safety measures would be put in place. 
In response, Mrs Anderson, Senior Engineer (Transportation) advised that this
junction would be further considered by the Transportation Service. 
Thereafter, the Committee agreed: 
(i) that the Transportation Service will give further consideration to access
requirements to the nearby cemetery and to the junction at Barhill Road; 
(ii) to grant planning permission in respect of Planning Application 21/01963/APP
subject to: 
Page 16

Page 17

• the completion of a (Section 75) legal agreement regarding developer
obligations relating to primary and secondary school provision and transport
requirements; 
• the following conditions and reasons with the following amendments: 
o the removal of the first reason for Condition 7; 
o condition 17b) to read “No details are provided for the bike storage for
units with no secure garden and garage. The bike store shown between
parking bays to the front of plots 61/62 does not appear to be set back
from the parking spaces and needs to be set back or relocated close by.
Details (Plans (1:200 min) and specifications are required for the
provision of secure weatherproof cycle parking for units with no secure
garden and garage in accordance with the Moray Local Development
Plan 2020 Parking Standards)”; 
o condition 22 to read “The provision of EV charging infrastructure shall
be implemented in accordance with drawing number 19-39/PL/02 Rev B
“Phase 1 Site Plan - Including housing mix and schedule” and approved
house plans showing EV charging infrastructure. No house or flat shall
be occupied until the EV charging infrastructure associated with the
parking for the unit has been provided and made available for
connection of an EV charging unit. 
Thereafter the development shall be completed in accordance with the
approved details”. 
1. The development to which this permission relates must be begun not later than
the expiration of 3 years beginning with the date on which the permission is
granted. 
Reason: The time limit condition is imposed in order to comply with the
requirements of section 58 of the Town and Country Planning (Scotland) Act
1997 as amended. 
2. Prior to the commencement of any works, a full site Construction Environmental
Management Plan, including a dedicated pollution prevention section, shall be
submitted to and approved in writing by the Council, as Planning Authority, and
thereafter all work shall be carried out in accordance with the approved plan. 
Reason: In order to minimise the impacts of necessary construction works on
the environment. 
3. A construction phase surface water management plan shall be submitted a
minimum of two months prior to the commencement of the development and
shall be agreed in writing prior to work commencing with the Planning Authority
in consultation with Moray Flood Risk Management. The plan shall include
measures to prevent increased flood risk to neighbouring properties and
measures to ensure heavily silted surface water does not enter any
watercourse. 
Thereafter the development shall be carried out in accordance with the agreed
details.
Page 17

Page 18

Reason:  To prevent surface water flooding during the course of the
development and minimise risk to adjacent watercourses. 
4. The 19 units identified as affordable housing on the approved site plan shall
only be used for affordable housing purposes in accordance with the
agreement(s) reached between the applicant/developer and Moray Council
and/or any registered social landlord (e.g. housing association or similar) to
enable the long term delivery of affordable housing on this site; and no
development shall commence until details of the agreement(s) to confirm the
arrangements for the delivery of the proposed affordable accommodation
hereby approved shall be submitted to and approved in writing by the Council,
as Planning Authority. 
Thereafter, the development shall be implemented in accordance with the
approved details. 
Reason: To ensure an acceptable form of development in terms of the required
provision and delivery of the affordable housing accommodation proposed for
this site wherein the benefits of such provision are passed on to serve the
community in future years. 
5. The accessible housing identified on the approved Site Plan, shall be provided
in accordance with the Accessible housing statement submitted in support of
this application and each accessible house shall thereafter be retained a such
throughout the lifetime of the development.   
Reason: To ensure accessible housing is provided and retained within the
development hereby approved.   
6. Unless otherwise agreed in writing with the planning authority, the equipped
play area shall be provided in accordance with the approved plans prior to the
commencement of the 30th residential unit on site. Thereafter the equipped
play area shall be maintained in accordance with the approved Landscape
Management Plan for the lifetime of the development. 
Reason: To ensure the timeous provision of the play area and surrounding
open space. 
7. No development shall commence until an amended Landscape Scheme has
been submitted to and approved by the Council, as Planning Authority. This
shall be based upon the Landscaping/Biodiversity drawing number 19-39/PL/06
Rev B, and show and clarify the following:
a) The position and number of species to be planted in the approved rain
gardens and roadside swales, 
b) The location of all public areas to be finished in grass, which
notwithstanding the details shown on the approved site plan, shall include
the kick about area within the play park,
c) The arrangements for the time-scale(s) for all new planting, seeding and
turfing to be undertaken on the site, and including the woodland planting
to the southwest of the site and the tree avenue along the old cemetery
load shown on the approved site plan and
d)  Details for the landscaping and timing of the area identified for future
neighbourhood development on the site plan. 
Page 18

Page 19

Reason: In order to remove any ambiguity regarding the terms of the
landscape scheme, to also ensure structural planting blocks are provided to
help integrate this phase of the development and to ensure that the approved
landscaping works are timeously carried out and properly maintained in a
manner which will not adversely affect the development or amenity and
character of the area. 
8. The development hereby approved shall be carried out in accordance with the
mitigation measures as identified within the Preliminary Ecological Appraisal
submitted in support of this application.   
Reason: To ensure the proposals minimise the impact on the surrounding
wildlife and maximises opportunities for habitat creation.   
9. The development hereby approved shall be carried out in accordance with the
mitigation, compensation and biodiversity enhancement measures as identified
within the bat survey submitted in support of this application.   
Reason: To ensure the proposals minimise the impact on bats and maximises
opportunities for habitat creation.   
10. Prior to development commencing a surface water maintenance plan shall be
submitted to and approved in writing by the local Planning Authority. All surface
water drainage provision within the development shall be implemented in
accordance with the details contained in the Drainage Impact Assessment,
submitted in support of this proposal.  Each residential unit hereby approved
shall not be brought into use until it is connected to the approved drainage
arrangements.  Thereafter the drainage arrangements and surface water
maintenance plan shall be will be retained and maintained throughout the
lifetime of the development.       
Reason: To ensure surface water from the development is disposed of and
maintained in a sustainable manner. 
11. All bird and bat boxes and hedgehog highways as shown on the approved
Landscaping/Biodiversity shall be provided prior to the completion of the house
on which they are located or within 3 months of the completion of the
development (whichever is the sooner).   
Reason: In order to ensure these habitat enhancement measures are provided
as soon as practical, in the interests of supporting biodiversity on site.   
12. Unless otherwise agreed in writing with the Planning Authority all boundary
enclosures shall be provided in accordance with the details specified on the
approved site plan.  The boundary enclosures associated with each house/unit
hereby approved shall be provided prior to completion of each house/unit and
thereafter retained throughout the lifetime of the development.   
Reason: To ensure the timeous provision, retention and specification of the
approved boundary enclosures in the interests of the character and appearance
of the development.   
Page 19

Page 20

13. No works in connection with the development hereby approved shall
commence unless an archaeological written scheme of investigation (WSI) has
been submitted to and approved in writing by the planning authority and a
programme of archaeological works has been carried out in accordance with
the approved WSI. The WSI shall include details of how the recording and
recovery of archaeological resources found within the application site shall be
undertaken, and how any updates, if required, to the written scheme of
investigation will be provided throughout the implementation of the programme
of archaeological works. This should comprise a level 1 archaeological standing
building survey of the farmstead & farmhouse, prior to demolition, as well as an
archaeological trial trenching evaluation of 5-7% of the total proposed
development site, these works to be undertaken by a suitably qualified
archaeological contractor. 
Should the archaeological works reveal the need for post excavation analysis
the development hereby approved shall not be occupied unless a post-
excavation research design (PERD) for the analysis, publication and
dissemination of results and archive deposition has been submitted to and
approved in writing by the planning authority. The PERD shall be carried out in
complete accordance with the approved details. 
Reason: To safeguard and record the archaeological potential of the area. 
14. No development shall commence until details confirming the installation of fibre
broadband connection for each residential unit (to be provided prior to
occupation of each residential unit) have been submitted to and approved in
writing by the Council, as Planning Authority. Thereafter, the development shall
be implemented in accordance with these approved details, unless otherwise
agreed in writing by the Council, as Planning Authority. 
Reason: To ensure the residential units hereby approved are served by
appropriate high speed internet connections, in accordance with policy PP3 –
Infrastructure and Services of the Moray Local Development Plan 2020. 
15. Prior to commencement of development timescales for the provision of the
public art as shown on the approved site plan and detailed on page 16 of the
placemaking statement dated December 2021, submitted in support of this
application, shall be provided and agreed in writing with the local planning
authority and subsequently implemented in accordance with the agreed
timescales. The public art shall thereafter be retained throughout the lifetime of
the development.   
Reason: To ensure the public art is timeously provided. 
16. Notwithstanding the details submitted shown within the adopted road layout
plan which does not include a road connection to the New Cemetery are not
acceptable. No development shall commence until the following have been
submitted for approval in writing by the Planning Authority in consultation with
the Roads Authority and Lands and Parks: 
• details (Plans scale 1:500 min) for a road connection (including
footways/cyclepaths) to be provided between Alba Road and the New
Cemetery Car Park; 
• a development phasing plan (roads and plots) to demonstrate that no
works shall commence on any part of the development to the north of the
Page 20

Page 21

existing cemetery connection until the approved road connection
(including footways and cyclepaths) between Alba Road and the New
Cemetery Car Park have been completed and opened to the public. 
Thereafter, unless otherwise agreed in writing by the Planning Authority the
development, shall be completed in accordance with the approved details and
access to the New Cemetery Car Park. 
Reason:  To ensure access is provided in the interests of an acceptable
development, road safety and the provision of details currently lacking from the
submission and to ensure pedestrian and vehicle access is maintained to the
“New Cemetery” at all times throughout the construction of the development.   
17. Notwithstanding the site layout details below submitted (which are not
acceptable) no development shall commence until details are submitted and
approved in writing by the Planning Authority in consultation with the Roads
Authority to address the following: 
a)  Plots 55 and 56 (which require 3 parking spaces) show a public footway
between the 3 proposed parking spaces which is unacceptable. (Either
the footway fronting plots 55-57) shall be relocated adjacent to the
carriageway or an additional parking space must be provided within the
plot to the rear of the buildings);
b)  No details are provided for the bike storage for units with no secure
garden and garage. The bike store shown between parking bays to the
front of plots 61/62 does not appear to be set back from the parking
spaces and needs to be set back or relocated close by. Details (Plans
(1:200 min) and specifications are required for the provision of secure
weatherproof cycle parking for units with no secure garden and garage in
accordance with the Moray Local Development Plan 2020 Parking
Standards);
c)  The details for the proposed footway/verge in front of Plot 21 are
unacceptable/lacking detail. (Revised details (Plans 1:500 min) required
showing the footway located adjacent to the carriageway);
d)  Plots 13 and 14 show (Drawing PL-39/PL/02 Rev B) show a shared wide
dropped kerb opening which is unacceptable. (Revised details (Plans
1:500 min) required showing the footway relocated adjacent to the
carriageway and single width driveway crossings of the footway);
e)  A 3m cyclepath between the Plot 28/29 boundaries. No details of fencing
are provided. Minimum clearances are required between the cyclepath
and any fence or boundary features in accordance with Cycling by
Design. (Revised details showing the proposed cyclepath boundary
details (walls/fences etc), their height and positions set back in
accordance with the requirements of Cycling by Design are required); 
f)  Plot 27 and 29 ‘Duffus’ 4 bed houses require a minimum of 3 parking
spaces. The current proposals indicate 1 garage space and 1 driveway
space. The driveway for plot 27 is less than 6 metres in front of the garage
opening. Plot 27 therefore has a shortfall of 2 parking spaces and plot 29
has a shortfall of 1 parking space. (Revised details (Plans scale 1:200
min) are required to show provision for 3 parking spaces for each plot; 
g)  The proposed junction with Alba Road severs the existing 3m cyclepath
with no provision to reconnect the existing cyclepath or provide 3m wide
crossings of Roads 1 and 2 which are required to maintain connectivity.
(Details (Plans 1:500min) are required for a continuous 3m wide cyclepath
on the north side of Road 1 and Alba Road with a 3m wide crossing of
Page 21

Page 22

Road 2. The existing cyclepath on Alba Road to the south must be
extended along the south side of Road 1 and 3m wide crossings provide
of Road 1 to form a continuous cyclepath connection from the south). 
Thereafter unless otherwise agreed in writing by the Planning Authority, the
development shall be completed in accordance with the approved details. No
house or flat shall be occupied until parking has been provided and made
available for use by that house or flat. Parking arrangements shall be retained
and maintained in perpetuity as parking spaces for use in conjunction with that
house or flat hereby approved. 
Reason: To ensure the availability of the level of parking necessary for
residents/visitors/others, in the interests of an acceptable development, road
safety and the provision of details currently lacking from the submission. 
18. No works shall commence on site until a Construction Traffic Management Plan
has been submitted to and approved in writing by the Council, as Planning
Authority in consultation with the Roads Authority. The Construction Traffic
Management Plan shall include the following information: 
• duration of works; 
• construction programme/phasing; 
• construction compound location(s) 
• hours of operation for delivery of materials and plant; 
• full details of any temporary construction access (note: no construction
traffic shall be permitted via Golf View Drive unless approved in writing by
the Planning Authority in consultation with the Roads Authority) ; 
• measures to be put in place to prevent material being deposited on the
public road and measures to be put in place to monitor and clean the
public road; 
• measures to be put in place to safeguard the movements of pedestrians; 
• traffic management measures to be put in place during works including
any specific instructions to drivers; and 
• site parking provision, loading and unloading and turning areas for
construction traffic. 
Thereafter, the development shall be implemented in accordance with the
approved details. 
Reason:  To ensure an acceptable form of development in terms of the
arrangements to manage traffic during construction works at the site. 
19. No development shall commence until evidence has been submitted to confirm
that a Road Safety Audit (Stage 1/2) for the internal road layout new junction
onto Alba Place and modifications and extension to Golf View Drive have been
completed in agreement with the Roads Authority and revised details for any
revised layouts have been submitted for approval in writing by the Planning
Authority in consultation with the Roads Authority. 
Thereafter, unless otherwise agreed in writing by the Planning Authority, the
development shall be completed in accordance with the approved details. 
Reason: In the interests of road safety and the provision of details currently
lacking from the submission. 
Page 22

Page 23

20. No development shall commence until details have been submitted to confirm
the maintenance/ factoring arrangements for all landscaped areas within or
adjacent to the public road (including footways and cycle paths, verges, and
service strips but excluding residential plot boundaries). Thereafter the
landscaping shall be maintained in accordance with the approved
arrangements and it must be ensured that landscaping will not interfere with the
function of the public road or cause a hazard to road users. 
Reason:  In the interests of road safety and the provision of details currently
lacking from the submission. 
21. No more than 5 residential units shall take access from the northern accesses
via Golf View Drive until the proposed road and footways between Golf View
Drive and Alba Road have been completed in accordance with the approved
details and opened to the public. 
Reason: To ensure that acceptable access and connectivity is provided to the
development. 
22. The provision of EV charging infrastructure shall be implemented in accordance
with drawing number 19-39/PL/02 Rev B “Phase 1 Site Plan - Including housing
mix and schedule” and approved house plans showing EV charging
infrastructure. No house or flat shall be occupied until the EV charging
infrastructure associated with the parking for the unit has been provided and
made available for connection of an EV charging unit. 
Thereafter the development shall be completed in accordance with the
approved details. 
Reason:  In the interests of an acceptable form of development and the
provision of infrastructure to support the use of low carbon transport. 
23. Driveways over service verges shall be constructed to accommodate vehicles
and shall be surfaced with bituminous macadam unless otherwise agreed with
the Council, as Planning Authority in consultation with the Roads Authority. 
Reason: To ensure acceptable infrastructure is provided at the property
accesses. 
24. No boundary fences, hedges, walls or any other obstruction whatsoever over 1
metre in height and fronting onto the public road shall be within 2.4 metres of
the edge of the carriageway and nothing fronting onto a cyclepath shall be
within 0.25 metres of the edge of the cyclepath, measured from the level of the
public carriageway, unless otherwise agreed in writing by the Council, as
Planning Authority in consultation with the Roads Authority. 
Reason: To enable drivers of vehicles leaving driveways to have a clear view
over a length of road sufficient to allow safe exit and to prevent obstructions to
cyclepath users, in the interests of road safety for the proposed development
and other road users. 
25. Householder permitted development rights (as defined in the Town and Country
Planning (General Permitted Development) (Scotland) Order 1922, (as
amended) (or any Order revoking and re-enacting that Order(s) with or without
Page 23

Page 24

modification shall be removed from any service strips along plot frontages and
no amendments to planting within these areas shall be permitted. 
Reason: To ensure an acceptable form of development and effective roads
drainage infrastructure is provided and safeguarded. 
26.   The consent hereby permitted relates to phase one only (65 dwellings units,
associated landscaping and infrastructure) and no other development. 
Reason: To clarify the extent of the development permitted. 
6. PLANNING APPLICATION 22/00715/APP 
Ward 2 – Keith and Cullen 
Installation  of  an  energy  storage  facility  including  battery enclosures 
power  conversion  units  transformer  substations  grid  connection 
infrastructure  vehicular access and associated works at Land At Drum Farm
Keith Moray for Renewable Energy Systems Limited 
A report was submitted by the Appointed Officer recommending that, for reasons
detailed in the report, planning permission be granted for the installation of an energy
storage facility including battery enclosures, power conversion units, transformer
substations, grid connection infrastructure, vehicular access and associated works at
Land at Drum Farm, Keith, Moray for Renewable Energy Systems Limited. 
It was noted that the application had been referred to Committee in terms of the
Scheme of Delegation as the application is major as the proposal relates to
electricity generation with a capacity of more than 20Mw. 
During discussion relating to planting surrounding the development, it was noted that
the site was geometric in shape and it was queried whether screening of the site
could be broken up with hedging and mature trees so that it blends into the
landscape more effectively. 
In response, Mrs MacDonald, Senior Planning Officer advised that a specific
standard of trees could be requested and that Condition 18 would be amended to
reflect this. 
Thereafter, the Committee agreed to grant planning permission in respect of
Planning Application 22/00715/APP subject to the following conditions and reasons
with an amendment to Condition 18 to read: 
“Notwithstanding the details shown on approved plan P22-0056.001 Rev B all trees
to be planted shall be at least heavy standard.  In all other regards all landscaping
works shall be carried out in accordance with the details shown on approved plan
P22-0056.001 Rev B in the first planting season following the first operation of the
development hereby approved. 
Any trees or plants which (within a period of 5 years from the planting) die, are
removed or become seriously damaged or diseased shall be replaced in the
following planting season with others of similar size, number and species unless
otherwise approved by the Council, as Planning Authority”.
Page 24

Page 25

1. The development to which this permission relates must be began not later than
the expiration of 5 years beginning with the date on which this permission is
granted. 
Reason: The time limit condition is imposed in order to comply with the
requirements of section 58 of the Town and Country Planning (Scotland) Act
1997 as amended. 
2. No development shall commence until final details of all the proposed battery
system and storage including the battery enclosure, transformers, grid
compliance equipment, substation building and spares storage container have
been submitted to and agreed in writing by the Planning Authority.  For the
avoidance of doubt the final installations shall not exceed the dimensions
shown on approved plans 04872-RES-SUB-DR-PT-003 re v1, 04872-RES-
SUB-DR-PT-002 rev 1, 04872-RES-SUB-DR-PT-001 rev 1, 04872-RES-PCS-
DR-PT-001 rev 1 and 04872-RES-SUB-DR-PT-004 rev 1 the installation shall
be finished in white, grey or green.  Thereafter only the approved details shall
be implemented. 
Reason:  To ensure that the development harmonises with its surroundings.   
3. No development shall commence until a pre-construction survey for badgers
and otters, in line with the recommendations contained in section 4.4 of the
submitted report entitled 'Preliminary Ecological Appraisal' by RES dated March
2022, has been undertaken and a report of survey has been submitted to, and
approved in writing by, the Council, as Planning Authority. The survey shall
include mitigation measures where any impact, or potential impact, on
protected species or their habitats has been identified and a species protection
plan. Development and work shall progress in accordance with any mitigation
measures contained within the approved report of survey and the timescales
contained therein. 
Reason: To ensure that the site and its environs are surveyed and the
development does not have an adverse impact on protected species or habitat. 
4. No development shall commence until details including the number, location
and specification of artificial bat and bird roosts to be placed throughout site
have been submitted to and agreed in writing with the Planning Authority. 
Thereafter the approved items shall be provided prior to the first use of the site
hereby approved.   
Reason: To secure biodiversity enhancements of the site.   
5. Notwithstanding the submitted details no development shall commence until full
details of the proposed acoustic fence have been submitted to and agreed in
writing by the Planning Authority in consultation with the Environmental Health
Authority.  For the avoidance of doubt a 3m high acoustic barrier shall be
installed in accordance with Section 5 of the noise impact assessment
supporting document by RES, dated 21 April 2022 Ref: 04872-3761753, and
titled "Assessment of Acoustic Impact for the Proposed Drum Farm Energy
Storage Project.", and as detailed on the approved plans 04872-RES-LAY-DR-
PT-001 3 and 04872-RES-SEC-DR-PT-002 1. 
Page 25

Page 26

Thereafter the approved fence shall be installed prior to the first use of the site
hereby approved and maintained in perpetuity. 
Reason: To protect local residents from noise nuisance due to the use of the
development. 
6. No development shall commence until evidence has been submitted to and
accepted in writing by the Planning Authority to demonstrate that Scottish
Water (protectdwsources@scottishwater.co.uk) have been notified that works
are to take place. 
Reason: To ensure the safeguarding of the drinking water catchment area. 
7. No development shall commence until evidence of a satisfactory Wear and
Tear agreement has been submitted to and agreed in writing by the Planning
Authority in consultation with the Roads Authority.  The scope of the Wear and
Tear Agreement shall be agreed with the Planning Authority in consultation with
the Roads Authority and shall include a condition survey of the network
undertaken jointly by the developer and a representative from the Council. The
survey shall include the full extent of the agreed construction traffic route(s)
(within Moray) between the site and the ‘A’ class road network. In addition, the
Wear and Tear agreement shall also include condition surveys of all roads
identified as ‘unsuitable’ which must be agreed with the Planning Authority in
consultation with the Roads Authority. 
Reason: To mitigate the potential risks from damage to the public road
occurring during the construction phase of the development. 
8. No development shall commence until evidence of a financial guarantee or
bond or suitable equivalent has been put in place to ensure the repair of the
public road serving the site in the event that the developer fails to meet their
obligations (as agreed as part of a Wear and Tear agreement) to maintain the
road in a safe condition during the construction phase of the development and
to restore the road to its pre-development condition within 1 year of the
development becoming operational and has been submitted to and agreed in
writing with the Council, as Planning Authority in consultation with the Roads
Authority.  For the avoidance of doubt the agreement shall cover the section of
the U35H Drum-Ardrone Road from the A96 to the site entrance.   
Reason: To mitigate the potential risks from damage to the public road
occurring during the construction phase of the development. 
9. No development shall commence until a Construction Traffic Management Plan
(CTMP) has been submitted to an agreed in writing by the Planning Authority in
consultation with the Roads Authority.  Thereafter the development shall be
carried out in accordance with the agreed CTMP at all times.  For the
avoidance of doubt the CTMP shall include as a minimum the following
information:
• duration of works;
• construction programme;
• parking provision, loading and unloading areas for construction traffic;
• full details of temporary arrangements to safeguard pedestrian
movements during the construction period;
Page 26

Page 27

• proposals to safeguard vulnerable pedestrians at and around Keith
Primary School during the construction period;
• full details of any temporary access;
• measures to be put in place to prevent material being deposited on the
public road;
• traffic management measures to be put in place during works including
any specific instructions to drivers; and
• a programme of monitoring for all routes identified within the CTMP during
construction will be required. 
Reason: To ensure an acceptable form of development in terms of the
arrangements to manage traffic during construction works at the site. 
10. No development (except that associated with the visibility splays) shall
commence until: 
i.  a visibility splay 2.4 metres by 120 metres, with all boundaries set back to
a position behind the required visibility splay, has been provided in both
directions at the access onto the public road; and 
ii.  Thereafter the visibility splay shall be maintained at all times free from any
obstruction exceeding 0.6 metres above the level of the carriageway. 
Reason: To enable drivers of vehicles leaving the site to have a clear view over
a length of road sufficient to allow safe exit, in the interests of road safety for
the proposed development and other road users through the provision of details
currently lacking. 
11. No development (other than that associated with the passing places) shall
commence until two passing places to the Moray Council standards and
specification have been constructed on the U35H Drum - Ardrone Road at the
locations shown on drawing no. 04872-RES-ACC-DR-PT-001 submitted on
22.06.2022. 
Reason: To enable drivers of vehicles to have adequate forward visibility to
see approaching traffic and for two vehicles to safely pass each other ensuring
the safety and free flow of traffic on the public road. 
12. Prior to the first use of the development hereby approved the site entrance and
access track shall be constructed in accordance with approved drawing no.
04872-RES-ACC-DR-PT-002.  
Reason: To ensure acceptable infrastructure at the development access.  
13. No water shall be permitted to drain or loose material be carried onto the public
footway/carriageway. 
Reason: To ensure the safety and free flow of traffic on the public road and
access to the site by minimising the road safety impact from extraneous
material and surface water in the vicinity of the new access. 
14. Construction works (including vehicle movements) associated with the
development audible at any point on the boundary of any noise sensitive
dwelling shall be permitted between 0800 - 1900 hours, Monday to Friday and
0800 - 1300 hours on Saturdays only, and at no other times out with these
permitted hours (including National Holidays) shall construction works be
Page 27

Page 28

undertaken except where previously agreed in advance in writing with the
Council, as Planning Authority and where so demonstrated that operational
constraints require limited periods of construction works to be undertaken out
with the permitted/stated hours of working. 
Reason: To protect local residents from noise nuisance in ensuring the
construction phase is restricted within permitted hours to protect local residents
from noise nuisance due to the use of the development. 
15. The rating level of noise associated with the development shall not exceed the
background sound level by more than 5 dB at the nearest noise sensitive
dwelling which is lawfully existing or has planning permission at the date of this
permission. For the avoidance of doubt the modal background sound level for
the daytime period and night-time period respectively has been determined as
an L A 90 of 40 dB and 31 dB, as stated in Section 4 of the noise impact
assessment supporting document by RES, dated 21 April 2022 Ref: 04872-
3761753, and titled "Assessment of Acoustic Impact for the Proposed Drum
Farm Energy Storage Project." The rating level and background sound level
associated with this condition are defined within BS 4142: 2014 + A1:2019
Methods for rating and assessing industrial and commercial sound.     
Reason: To protect local residents from noise nuisance due to the use of the
development. 
16. The operational site lighting shall be provided in accordance with approved
drawings 04872-RES-LAY-DR-PT-001 Rev3 and 04872-RES-SEC-DR-PT-001,
Rev1, and no other external lighting shall be installed. 
Reason: To protect local residents from light nuisance due to the use of the
development. 
17. The development shall at all times be carried out in accordance with the
approved Construction Environmental Management Plan entitled ‘Drum Farm
Battery Storage Project’ by RES, dated 8 March 2022, Ref: 04872-3704703. 
Reason: To ensure environmental impacts are suitably managed and
maintained during the construction phase. 
18. Notwithstanding the details shown on approved plan P22-0056.001 Rev B all
trees to be planted shall be at least heavy standard.  In all other regards all
landscaping works shall be carried out in accordance with the details shown on
approved plan P22-0056.001 Rev B in the first planting season following the
first operation of the development hereby approved. 
Any trees or plants which (within a period of 5 years from the planting) die, are
removed or become seriously damaged or diseased shall be replaced in the
following planting season with others of similar size, number and species
unless otherwise approved by the Council, as Planning Authority”. 
Reason: To ensure that the approved landscaping works are timeously carried
out and properly maintained in a manner which will not adversely affect the
development or amenity and character of the area.       
19. All foul and surface water drainage proposals shall be in accordance with the
Page 28

Page 29

submitted report Flood risk Statement and Drainage Impact Assessment, dated
05 May 2022 and approved drawing 04872-RES-LAY-DR-PT-001 rev 3. 
Reason: To ensure that surface water drainage is provided timeously and
complies with the principles of SuDS; in order to protect the water environment. 
7. PLANNING APPLICATION 22/01208/APP 
Ward 1 – Speyside and Glenlivet 
Section 42 to amend condition 3 of 17/01003/APP in relation to time period
Meikle Hill Dallas Moray for The Dallas Trust 
A report was submitted by the Appointed Officer recommending that, for reasons
detailed in the report, planning permission be granted for a Section 42 to amend
condition 3 of 17/01003/APP in relation to time period at Meikle Hill, Dallas, Moray
for The Dallas Trust. 
It was noted that the application had been referred to Committee in terms of the
Scheme of Delegation as the proposal is a major planning application. 
Following consideration, the Committee agreed to grant planning permission in
respect of Planning Application 22/01208/APP subject to the following conditions and
reasons: 
1. The development as hereby granted shall begin no later than 5 years from the
date of this permission; and for the purposes of this permission, the
development as hereby granted shall be that as described and approved under
formal decision notice 14/01087/EIA dated 25 June 2015 i.e. for six (6) wind
turbines only, to be undertaken in accordance with the turbine model design
and site infrastructure layout arrangements as shown on amended drawings
60289428-ENG -003 Rev C and -002 Rev C as received from the applicant on
1 April 2015 which forms part of the development as approved under
application 14/01087/EIA and the request to vary Condition 20 has been
removed. 
Reason: In accordance with Section 58 (4) of the Town and Country Planning
(Scotland) Act 1997 taking into account the nature and requirements for
implementation of the development and to ensure an acceptable form of
development whereby all turbines as proposed are located within an Area of
Search and in the Upland Moorland and Forestry Landscape Character
Type/Area with greatest potential for windfarm development and in the Upland
Moorland and Forestry/Upland Plateau with Forest (10) Landscape Character
Type wherein there is limited scope to accommodate this large turbine
typology, and in the interests of the appearance and amenity of the surrounding
locality including account of landscape and visual effects of the development,
and in accordance with the applicant's agent's submitted particulars (email 18
August 2017 refers). 
2. Except where otherwise provided for, or required by the terms of this
permission, the permission hereby granted relates strictly to the dimensions
and specifications of the turbine design (including make, model, design, power
rating and sound power level of the turbine to be used) and site layout
Page 29

Page 30

infrastructure arrangements as provided for in the application and, with the
exception of any micro-siting of turbines and other infrastructure, to all other
mitigation measures as identified in the Environmental Statement and
subsequent Addendum I and II of the Environmental Statement (as included
within application 14/01087/EIA), and any amendment thereof shall be subject
to the express prior written approval of the Council, as planning authority. 
Reason: To ensure the development is carried out in accordance with the
submitted application particulars and that the merits and implications of any
proposed micro-siting or other variation to the development as approved can be
assessed in terms of impact on landscape and visual, cultural and natural
heritage and/or other environmental interests, etc. 
3. The permission as hereby granted is for a period of 40 years from the date
when electricity is first exported from any wind turbine within the development
to the electricity grid network (First Export Date) and written confirmation of this
First Export Date shall be provided to the Council, as planning authority within
one month thereof.  Within 12 months of the expiry of this period the wind
turbines and ancillary equipment shall be dismantled to ground level and
removed from the site and the land shall be restored in accordance with the
details agreed under condition 5 below. 
Reason: To define the duration of the permission and enable a review and;
where required, a re-assessment of the environmental and other impacts of the
development. 
4. The applicant/developer/wind turbine operator shall, after the First Export Date,
record information continuously regarding the monthly supply of electricity to
the national grid from each turbine within the development hereby granted and
retain the information for a period of at least 24 months. The information shall
be made available to the Council, as planning authority within one month of any
request being made. 
In the event that any wind turbine(s) installed and commissioned fail(s) to
supply electricity on a commercial basis to the grid for a continuous period of 6
months, or is no longer required, the turbine(s) in question shall be deemed to
have ceased to be required. Under such circumstances, the wind turbine(s)
along with any ancillary equipment, fixtures and fittings no longer required in
connection with the retained turbines shall, within 3 months of the end of the
said continuous six month period or when ceasing to be no longer required, be
dismantled and removed from the site and the surrounding land shall be re-
instated in accordance with a re-instatement scheme including specification of
all works and timescale for re-instatement which shall previously have been
submitted to and approved by the Council, as planning authority. 
Reason: To ensure that any redundant or non-functioning wind turbine(s) is/are
removed from the site in the interests of public safety, amenity and
environmental protection and to ensure acceptable arrangements for the re-
instatement of the ground are provided. 
5. No development shall commence until: 
a) a draft Restoration and Decommissioning Plan for the site has been
submitted to and approved in writing by the Council, as planning authority
Page 30

Page 31

in consultation with SEPA, SNH and/or other agencies as appropriate;
and 
b)  thereafter, and not later than 12 months prior to the expiry of this
permission or decommissioning of the development, whichever is the
sooner, a detailed Restoration and Decommissioning Plan, based upon
(the principles of the approved draft Plan shall be submitted to and
approved by the Council, as planning authority in consultation with SEPA,
SNH and/or other agencies as appropriate. The Plan shall include
provision for all turbines and ancillary infrastructure and equipment
(including all buildings and structures, hardstandings and tracks, etc.) to
be decommissioned, de-energised, and dismantled to ground level and
removed from the site together with the arrangements to retain any
access tracks and other infrastructure on the site, the treatment of
disturbed ground surfaces, the management and timing of all proposed
works, environmental management provisions including traffic and noise
management plans to address issues likely to arise during the
decommissioning period and provisions for the restoration and aftercare
of the site; and 
Thereafter, the development shall be decommissioned and the site restored in
accordance with the approved plan details. 
Reason: To ensure the re-instatement of the site in an acceptable and timeous
manner with all wind turbines and associated development removed from the
site in the interests of safety, environmental protection, amenity and
appearance of the site upon the surrounding area. 
6. Prior to the development commencing, details shall be submitted to and
approved in writing by the Council, as planning authority regarding evidence of
a bond or other similar financial provision to be put in place to cover all
decommissioning and site restoration costs on the expiry of the permission
(Condition 5) or where all 6 turbines cease to be required (Condition 4) or
where works other than the erection of turbines have been undertaken but no
turbines are erected on the site (for example, in the event that no Scheme is
agreed/implemented (Condition 25), whichever is the sooner. The required
bond or equivalent shall: 
a)  be based on the Restoration and Decommissioning Plan (as required by
Condition 5); 
b)  include documentary evidence to demonstrate that the amount of the
bond or financial provision is sufficient to meet the full estimated costs of
decommissioning, including dismantling, removal, disposal, site
restoration, remediation and all other incidental works and professional
costs; and 
c) include details to ensure that the proposed financial arrangements will be
maintained and be subject to periodic review throughout the lifetime of the
development. The review period shall be not less than 5 yearly intervals
from commencement of the development, or such other period as may be
agreed in writing with the Council, as planning authority and the findings
of the review shall be submitted to and approved by the Council, as
planning authority. 
Thereafter, the development shall not commence until written evidence has
been provided to the Council, as planning authority to confirm that the approved
bond or financial provision arrangement has been put in place. 
Page 31

Page 32

Reason: To ensure that sufficient funds are available to address the expected
full costs of decommissioning and re-instatement and restoration of the site. 
7. No development shall commence until details have been submitted to and
approved by the Council, as planning authority in consultation with SNH, SEPA
and other agencies where appropriate regarding; 
a)  confirmation of the make, model, design, power rating and sound power
levels of the turbines to be used; 
b)  the external colour and/or finish of the turbines including towers, nacelles
and blades which shall be non-reflective, semi-matt pale grey; 
c) together with details including further landscape and visual impact
information to demonstrate that they will not adversely affect the
landscape and visual character, integrity and amenity of the site or the
surrounding area, the location, design specifications and external material
finishes and colour of any external wind turbine transformer kiosk, unless
otherwise located within the tower of the wind turbine; 
d)  for the substation compound, the design external appearance and
material finishes and colour of all proposed buildings and structures to be
erected, stationed or installed within the compound area together with the
finalised site layout arrangements, including the external appearance,
dimensions and surfacing materials for the compound area, any walls,
paths or other proposed/required ancillary infrastructure to be provided,
any required/proposed external switch gear infrastructure to be located
within the compound, the arrangements for access and parking and
disposal of foul and surface water from the compound area, and all
required/proposed landscaping to be provided around the compound or
elsewhere within the site to screen and/or mitigate the landscape and
visual impact of the compound and its infrastructure therein; 
e)  excluding the requirement for compensatory planting (see Condition 28)
and for all other required/proposed landscaping requirements throughout
the site, a landscape scheme (see Condition 9); 
f)  the location(s) and design specifications for all required/proposed
upgraded existing and new watercourse crossings, to include information
to demonstrate that they are designed to convey a 1 in 200 year plus
climate change design flow without causing constriction of flows or
increasing the risk of flooding elsewhere (SEPA consultation response on
application 14/01087/EIA, 16 July 2014, par 1.1, 1.10, 1.11 refers); 
g)  for the formation of access tracks and watercourse crossings, information
including the extent and scale of the required/proposed works to
demonstrate that no land raising occurs within the functional flood plain of
any watercourse without the provision of associated compensatory
storage and an assessment of the changes to floodplain conveyance
(SEPA consultation responses on application 14/01087/EIA and
17/01003/APP, 16 July 2014 and 14 July 2017, pars 1.1, 1.5 - 1.11 and
pars 1.1 - 1.9 refer); 
h)  details of the arrangements including timescale(s) for inspection to
manage and mitigate surface water run-off during all stages of the
development including proposals/regimes for inspection and maintenance
of drains to prevent blockages (SEPA consultation response on
application 14/01087/EIA, 16 July 2014, par 1.12 refers); 
i)  based on investigation, further information to establish the viability of
utilising and upgrading of sections of existing tracks on the site (including
the track along the edge of forestry to the eastern edge of the application
Page 32

Page 33

site) together with justification for not using/upgrading existing tracks and
creating new access tracks (SEPA consultation response on application
14/01087/EIA, 16 July 2014, par 2.3 refers); 
j)  details to demonstrate that all track bases are made permeable to shallow
ground water flows where constructed through wet heath (M15) and any
other groundwater dependent terrestrial ecosystems (GWDTEs) including
the instances of the M6 community that are crossed (Environmental
Statement, Volume 2, Chapter 10 and SEPA consultation response on
application 14/01087/EIA, 16 July 2014, par 2.4 refers); 
k)  details for the location(s) and design specifications for the proposed
installation of ultra-violet and pre-filtration treatment arrangements to any
private water supply to be provided/used for human consumption within
the development site during the construction and operational stages of the
development; 
l)  confirmation of all required/proposed mitigation measures (where not
already embedded within the submitted design and layout of the
development) for all stages of the development, to be contained within a
Schedule of Mitigation or similar together with details regarding the
process to control/action changes from any agreed Schedule of Mitigation. 
The Schedule shall include, but be not limited to, all required/proposed
measures to mitigate the impact of the development upon water resources,
hydrology, hydrogeology and geology and nature conservation (including
ecology and ornithology, protected species and habitats) interests. These
details may be incorporated within any site specific Construction Environmental
Management Plan (CEMP) (see Condition 8 below); and 
Thereafter the development shall be implemented in accordance with the
approved details. 
Reason: Details of the matters specified are lacking from the submission and
to ensure an acceptable form of development in landscape, visual and/or other
environmental considerations, including addressing the risk of flooding and
surface water run-off, to minimise impacts on wetland habitats and maintain
(chemical) quality of water supplied to downslope wetlands, to minimise
impacts upon nature conservation interests, and to provide for a wholesome
private water supply where proposed as part of the development. 
8. No development shall commence until details have been submitted to and
approved by the Council, as planning authority in consultation with SEPA and
SNH and other agencies as appropriate regarding a site-specific Construction
Environmental Management Plan (CEMP). The CEMP shall incorporate details
for the environmental management, pollution prevention (not just during
construction) and the following: 
a)  surface water management plan; 
b)  pollution prevention plan; 
c)  site waste management plan; 
d)  watercourse engineering; 
e)  peat management - to include details of all peat stripping, excavation,
arrangements for storage and re-use of peat in accordance with best
practice; 
f)  (construction) noise management plan (see Condition 28); 
g)  species protection plans - to include those for breeding birds and bats,
and GWTDEs including arrangements for pre-commencement surveys to
Page 33

Page 34

confirm presence/absence of species on site, timing of works(s) to avoid
disturbance, development of buffer areas to prevent encroachment onto
and into areas of protected species and valued habitats, etc.; 
h)  habitat management plan - to include the arrangements to manage,
monitor and mitigate the loss of habitats and compensate for losses within
and beyond the site, and proposals and practices to enhance bio-diversity
to off-set habitat and species damage or loss, including restoration of
areas of blanket bog and wet heath and improving areas for golden
plover; 
i)  invasive non-native species protocol - to address all bio-security and other
measures to be adopted to control the spread of giant hogweed and
skunk cabbage in and around the Dallas/Kellas area. 
In addition, the CEMP shall also include reference to the terms of appointment
of an appropriately qualified Ecological Clerk of Works (to be appointed by the
applicant/developer/wind turbine operator and approved by the Council, as
planning authority after consultation with SNH), to include a remit with roles and
responsibilities which shall include, but not necessarily be limited to, the
monitoring of all works carried out on site and ensuring compliance with all
environmental and nature conservation mitigation works and working practices,
advising and training on adequate environmental and nature conservation
interests within and adjoining the site, directing the placement of development
infrastructure within the site and powers to halt development on site where
environmental considerations warrant such action. 
Thereafter, the development shall be carried out in accordance with the
approved Plan. 
Reason: In order to minimise the impacts of construction and operation of the
development upon the environment and secure detailed information on the
delivery of mitigation works and measures as identified which are currently
lacking from the submitted particulars. 
9. Excluding the requirements for compensatory planting (Condition 28), the
Landscape scheme shall show: 
a)  the location of any existing trees, shrubs and hedgerows on the site and
identify those to be retained and those to be removed; 
b)  details of measures to be taken to protect any existing landscape features
to be retained during the course of developing the site; 
c)  details of the numbers, species, position, planting distances and sizes of
all new planting to be undertaken; 
d)  details of all earth mounding/moulding works to be undertaken, to include
the proposed formation of bunding or similar screening around the sub-
station compound or along the access tracks or elsewhere within the site
together with details regarding the location, extent and design
specification for their construction and formation of all earth works and
cross-sections details to relate the works to both existing and finished
ground levels; and 
e)  details regarding the time-scale(s) for undertaking all landscaping and
earth works. 
Thereafter, all planting or seeding and earthwork operations shall be
implemented in accordance with the approved details and any trees or plants
which (within a period of 5 years from planting) die, are removed or become
Page 34

Page 35

diseased or damaged shall be replaced in the following planting season with
others of similar size, number and species unless otherwise agreed in writing
with the Council, as planning authority. 
Reason: Details of the matters specified are lacking from the submission and
to ensure an acceptable form of development including addressing the
landscape and visual and environmental impact of the substation and access
tracks upon the appearance and amenity of the development upon the
surrounding area and to ensure that all approved landscape works are
timeously carried out and properly maintained. 
10. The blades of all turbines shall rotate in the same direction and no names,
symbols, signs or logos or similar means of advertisement, other than those
required for health and safety reasons, shall be displayed on any part of the
turbines, masts, buildings, structures or other infrastructure associated with the
development without the prior written consent of the Council, as planning
authority. 
Reason: To minimise the visual impact arising from the appearance of the
development. 
11. In relation to each of the two borrow pit locations as identified on amended
drawing 60289428-ENG-002 Rev C: 
a) materials excavated from each pit location shall be used solely for
purposes in conjunction with this Meikle Hill wind farm development and
for no other use or purpose without the prior written consent of the
Council, as planning authority; and 
b)  no development shall commence until details for each borrow pit have
been submitted to and approved by the Council, as planning authority
regarding: 
i.  finalised location and dimensions, including area and depth of
excavation, together with cross and long sections across the pit area
to show the extent and depth of excavation relative to existing and
finished (excavated depth) ground levels; 
ii.  location(s), extent and height of any temporary storage of material
both before and after processing on the site; 
iii.  location(s) and description of plant and machinery to be used to
process excavated material on the site; 
iv.  location and details of arrangement for fencing or similar means of
enclosure to be erected to define and limit the area of borrow pit
working (and within which all borrow pit activity including storage and
movement of materials and machinery shall be located at all times); 
v.  location and details of arrangements for surface water management
include de-watering ponds etc; 
vi.  proposed timescales for all excavation activity; 
vii.  the arrangements for site restoration and after-care of each borrow
pit, to include: 
a)  details including sections of proposed/required re-grading and
levelling works to re-integrate the area with its surroundings; 
b)  details of sub-material and topsoil arrangements to be provided
to enable re-instatement of the area to form a natural habitat; 
c)  details of all plantings to be undertaken (see Condition 9); and 
d)  timescale for site re-instatement works. 
Page 35

Page 36

Thereafter, all borrow pit activity shall be undertaken in accordance with the
approved details. 
Reason: Details of the matters specified are lacking from the submission and
to ensure an acceptable form of development including consideration of the
landscape and visual impact upon the surrounding area during both excavation
and re-instatement of each borrow pit area. 
12. No development shall commence until details have been submitted to and
approved in writing by the Council, as planning authority in consultation with the
Moray Access Manager regarding a Public Access Plan for the
development/site (to include both existing arrangements and all
required/proposed access arrangements during all stages of the development,
including the construction stage). In particular, the plan shall show: 
a)  all existing paths, tracks and rights of way and any areas currently outwith
or excluded from statutory access rights (under Part 1 of the Land Reform
(Scotland) Act 2003); and 
b)  any areas proposed for exclusion from statutory access rights, for reasons
of privacy, disturbance or curtilage, in relation to proposed buildings or
structures; and 
c)  all paths and tracks proposed for construction, for use by walkers, riders,
cyclists, and all ability users; and 
d) any diversions or paths - temporary or permanent - proposed for the
purposes of the development; and 
e)  details to include location, design specifications and time-scales for
provision for the following: 
i)  details of specific access controls, for example gates to be inserted
at main access points, etc; 
ii)  details of the arrangements to provide for public access for horse
riders, cyclists, pedestrians and the less able; and 
iii)  proposals to accommodate and enhance through access and
connectivity to/from the local paths network, to include the provision
and incorporation of a new path linking from the vehicle track near
turbine 1 through to the existing Right of Way located along the
southern boundary of the site; and 
iv)  details of all signage /mapboards or similar to be provided at key
access points to highlight all outdoor access opportunities. 
Thereafter, the development shall be implemented in accordance with the
approved details. 
Reason: To mitigate the effects of the development and maintain and improve
public access and connectivity both within, and to and from the site. 
13. No development works (including site clearance) shall commence until details
have been submitted to and approved by the Council, as planning authority in
consultation with Aberdeenshire Council Archaeology Services regarding a
written scheme of investigation (with timescales) to secure and undertake the
implementation of a programme of archaeological works. Thereafter, the
development and all recording and recovery of archaeological resources within
the development site shall be implemented in accordance with the approved
scheme. 
Reason: To safeguard and record the archaeological potential of the area. 
Page 36

Page 37

14. All construction activities associated with the development, including vehicle
movements at the site shall be permitted only between 07:00 and 19:00 hours,
Mondays - Fridays, and 07:00 and 16:00 hours on Saturdays, with no working
on Sundays or public holidays. Any required works outwith the stated times
likely to be audible at the curtilage of any noise sensitive property shall not be
permitted except with the prior written consent of the Council, as planning
authority in consultation with the Environmental Health Manager or in the case
of an emergency. 
Reason: In order to minimise the impact of construction works on the amenity
of the surrounding area including local residents. 
15. Blasting times associated with the development including the formation of
borrow pits shall be restricted as follows i.e. 
a)  no blasting shall be carried out on the site except between 10:00 and 
12:00 hours, and 14:00 and 16:00 hours, Mondays to Fridays, and 10:00
and 12:00 hours on Saturdays; and 
b)  no blasting or drilling operations on Sundays or other public holidays. 
The above blasting time arrangements shall not apply in cases of
emergency where it is considered necessary to carry out blasting
operations in the interests of safety. The Council, as planning authority
shall be notified in writing immediately of the nature and circumstances of
any such event. 
Reason: To protect nearby residents from undue noise and disturbance
impacts and loss of amenity. 
16. Ground vibration as a result of blasting operations at the site, for example
where required to form the borrow pits shall, at all times, not exceed a peak
particle velocity of 10mms-1 in 95% of all blasts and no individual blast shall
exceed a peak particle velocity of 12mms-1 as measured at vibration sensitive
buildings. The measurement shall be the maximum of 3 mutually perpendicular
directions taken at the ground surface at any vibration sensitive building. 
Reason: To protect nearby residents from undue noise and disturbance
impacts and loss of amenity. 
17. At the reasonable request of the Council, as planning authority in conjunction
with the Environmental Health Manager, following receipt of any complaint
relating to vibration experienced from development operations including
blasting operations to form borrow pits, the applicant/developer/wind turbine
operator shall take steps to measure and monitor, at its own expense, ground
vibration to ensure compliance with Condition 16. Within two (2) weeks of being
so notified of vibration being experienced (or as longer as the Council, as
planning authority may allow) the applicant/developer/wind turbine operator
shall submit to the Council, as planning authority in consultation with the
Environmental Health Manager the results of such monitoring together with
details (including timescale for implementation) of measures to monitor and
address vibration impacts to ensure compliance with the requirements of
Condition 16. Thereafter, the development shall be implemented in accordance
with the approved details. 
Page 37

Page 38

Reason: To protect nearby residents from undue noise and disturbance
impacts and loss of amenity. 
18. At the reasonable request of the Council, as planning authority in conjunction
with the Environmental Health Manager, following receipt of any complaint
relating to shadow flicker associated with the development hereby approved,
the applicant/developer/wind turbine operator shall investigate and instigate
appropriate measures to mitigate the effects of shadow flicker. Within two (2)
weeks of being so notified of shadow flicker being experienced (or as longer as
the Council, as planning authority may allow) the applicant/developer/ wind
turbine operator shall submit to the Council, as planning authority in
consultation with the Environmental Health Manager the results of such
investigations together with details of measures to address the effects of
shadow flicker, including the timescale within which the measures will be
implemented. Thereafter, the development shall be implemented in accordance
with the approved details. 
Reason: In order to redress and mitigate any identified impacts of shadow
flicker and safeguard the amenity of local residents. 
19. At the reasonable request of the Council, as planning authority following receipt
of any complaint where interference to domestic television reception is caused
as a result of the development hereby approved, the applicant /developer/wind
turbine operator shall take steps to make good the reception, either by
eliminating the cause of the interference or by providing an alternative means
by which television signals may be received. Within two (2) weeks of being
notified by the Council, as planning authority of the existence of such
interference (or within a longer period as the planning authority may allow) the
applicant/developer/wind turbine operator shall submit to the Council, as
planning authority for its approval, proposals to make good the reception,
including the timescale within which the proposals will be undertaken.
Thereafter, the development shall be carried out in accordance with the
approved details.   
Reason: In accordance with the applicant's submitted particulars and in order
to ensure that an alternative means of obtaining television reception can be
achieved and/or mitigated in the event of interference caused to domestic
television reception. 
20. At the reasonable request of the Council, as planning authority following receipt
of any complaint where interference to fixed link frequency band signals is
caused as a result of the development hereby approved, the
applicant/developer/wind turbine operator shall take steps to make good the
fixed link frequency band signals, either by eliminating the cause of the
interference or by providing an alternative means by which fixed link frequency
band signals may be received. Within two (2) weeks of being notified by the
Council, as planning authority of the existence of such interference (or within
such longer period as the planning authority may allow) the
applicant/developer/wind turbine operator shall submit to the Council, as
planning authority for its approval proposals to make good the fixed link
frequency band signals, including the timescale within which the proposal shall
be undertaken. Thereafter, the proposals shall be carried out in accordance
with the approved details. 
Page 38

Page 39

Reason: In order to ensure that an alternative means of maintaining fixed link
telecommunications infrastructure can be achieved and fixed promptly in the
event of interference caused to existing fixed links. 
21. Prior to the commencement of deliveries to the site including movement of any
abnormal load, details shall be submitted to and be approved in writing by the
Council, as planning authority in consultation with Transport Scotland, as trunk
roads authority and/or its operating company regarding a Route Access Report
or equivalent, including swept path analysis or similar where appropriate, to
identify the proposed route for any abnormal load movements on the trunk road
and demonstrate that exceptional loads can be transported through the trunk
road network safely. The details shall include all required or proposed
accommodation measures including timescales for all required/proposed
removal of street furniture, junction widening, and traffic management, etc. and
show that the transportation of turbine components will not have any
detrimental effect on structures within the route path. Thereafter, the
development shall be implemented in accordance with the approved details. 
Reason: To minimise interference and maintain the safety and free flow of
traffic on the trunk road as a result of the traffic moving to and from the
development. 
22. During the delivery period of the wind turbine construction materials, any
additional signing or temporary traffic control measures deemed necessary due
to the size or length of any loads being delivered or removed shall be
undertaken by a recognised (QA) traffic management consultant, in accordance
with the name of the consultant which shall previously have been provided to
the Council, as planning authority in consultation with Transport Scotland, as
trunk roads authority and/or its operating company before any construction
commences. 
Reason: To minimise interference and maintain the safety and free flow of
traffic on the trunk road and to ensure that the transportation of turbine
components will not have a detrimental effect on the road and on structures
along the delivery route. 
23. Prior to the commencement of development details of the following shall be
submitted to and approved by the Council, as planning authority in consultation
with Transportation Manager (and Transport Scotland where appropriate): 
a)  detailed proposals for undertaking both trial runs and also delivery of
abnormal indivisible loads, to include (but not be limited to) identification
of all temporary and permanent modifications and measures required to
protect the public road and structures together with the arrangements for
traffic, vehicle holding areas and non-vehicular management during
deliveries, time restrictions for deliveries i.e. outwith school crossing patrol
times, etc; 
b)  a Traffic Management Plan, in accordance with the scope and content of
the required Plan which shall have previously been submitted to and
approved by the Council, as planning authority in consultation with the
Transportation Manager. The Traffic Management Plan shall cover the
duration of the development, methods of dealing with large delivery
vehicles, methods of marshalling and manoeuvring at junctions on the
public road network, any temporary traffic waiting restriction requirements
Page 39

Page 40

and all modifications to the road network and traffic management
arrangements; 
c)  detailed plans (to include location and design construction specifications)
to confirm the full extent of the proposed road widening of the B9010 to
5.5m; 
d)  details (1:200 scale drawing) of the proposed access junction onto the 
B9010 Pluscarden Road. The width of the vehicular access shall be a
minimum of 7.3m and have a maximum gradient of 1:20 measured for the
first 25m from the edge of the public carriageway (B9010). The first 25m
of the access shall be to The Moray Council specification and surfaced
with hot rolled asphalt. The access radii shall accommodate the abnormal
load vehicle movements as determined in the Traffic Management Plan,
and shall be kerbed using 254 x 127mm splayed/half battered precast
concrete kerbs to The Moray Council specification. Any existing ditch,
watercourse or drain under the site access shall be piped using a 300mm
minimum diameter of pipe. The pipe shall be laid to a self-cleansing
gradient; 
e)  a detailed drawing (scale 1:500 or 1:1000 which shall also include details
to demonstrate control of the land) showing the provision of a visibility
splay of 4.5m x 215m, and a schedule of maintenance for the area within
the visibility splay; and 
f)  in order to monitor, assess and address the impact of construction and
delivery traffic on the road network between the site access and the A96,
an assessment of the network and a programme of monitoring during
construction. The assessment shall include provision for a 'before and
after' condition survey to be carried out jointly with Council's
Transportation Section, traffic counters on the B9010 east and west of the
site access in advance of any construction traffic, either permanently or on
a scheduled basis (to be agreed with the Council, as roads authority)
throughout the construction period and for a period after works are
completed. 
Thereafter, all modifications to the road network and traffic management
arrangements shall be implemented in accordance with the approved details
and all required works to the public road network shall be completed prior to the
delivery of any materials to the development site. 
Reason: To ensure an acceptable development including the provision of
additional information currently lacking from the submission and to ensure
acceptable infrastructure is provided along the proposed delivery/ construction
route to the site access in the interests of road safety. 
24. Prior to the commencement of construction and of deliveries to the site,
including abnormal loads and abnormal indivisible loads, the following shall be
provided (in accordance with the approved details and to The Moray Council
standards and specifications): 
a)  abnormal load trial run(s) shall be undertaken after mitigation works have
been undertaken (as approved under Condition 23 above) to confirm the
works are acceptable and to identify any other restrictions not previously
addressed including confirmation of the required/proposed vertical
clearances at bridge crossings, and the frequency and location of all
required abnormal load passing places/oncoming vehicle holding areas.
Representatives from Moray Council Transportation (Traffic), the Trunk
Roads Authority and Police Scotland must be invited to the trial run(s); 
Page 40

Page 41

b) for all abnormal indivisible loads, all required/proposed works approved
under Conditions 23 and 24a above shall be provided in accordance with
the approved details and to The Moray Council standards and
specifications. Any works undertaken shall be permanent for the duration
of the operation of the development unless otherwise agreed in writing
with the Council, as planning authority in consultation with the
Transportation Manager; 
c)  all road widening/alterations/verge hardening as identified in Conditions
23 and 24a above, the site access onto the B9010 and any dropped kerbs
required to allow overrunning of hardened verge;
d)  the 50m section of new 40mm thick Hot Rolled Asphalt which shall be
provided on the B9010 Pluscarden Road (25m either side of the centreline
of the access, over the entire width of the road) unless otherwise agreed
in writing by the Council, as planning authority in consultation with the
Transportation Manager; and 
e)  the visibility splay of 4.5m x 215m (Condition 23 refers) and thereafter, the
visibility splay shall be maintained at all times free from any obstruction
exceeding 1.0m above the level of the carriageway in accordance with the
agreed schedule of maintenance. 
Reason: To ensure an acceptable development including the provision of
additional information currently lacking from the submission and to ensure
acceptable infrastructure is provided along the proposed delivery/ construction
route to the site access in the interests of road safety. 
25. No wind turbine shall be erected unless and until an Air Traffic Control Radar
Mitigation Scheme, to address the impact of the wind turbine upon air safety,
has been submitted to and approved in writing by the Council, as planning
authority in consultation with the Ministry of Defence (Defence Infrastructure
Organisation) where: 
a)  the Air Traffic Control Radar Mitigation Scheme is a scheme which shall
be designed to mitigate the impact of the development upon the operation
of the Primary Surveillance Radar at RAF Lossiemouth ("the Radar") and
the air traffic control operations of the Ministry of Defence (MOD) which is
reliant upon the Radar. The Air Traffic Control Radar Mitigation Scheme
shall set out the appropriate measures to be implemented to mitigate the
impact of the development on the Radar and shall be in place for the
operational life of the development provided the Radar remains in
operation; and 
b)  no turbines shall become operational unless and until all those measures
required by the approved Air Traffic Control Radar Mitigation Scheme
have been implemented prior to operation of the turbines and the Council,
as planning authority in consultation with the Ministry of Defence (Defence
Infrastructure Organisation) has confirmed this in writing. 
.
Thereafter, the development shall be operated fully in accordance with the
approved Air Traffic Control Radar Mitigation Scheme. 
Reason: In the interests of military aviation safety. 
26. MOD-accredited 25 candela omni-directional aviation lighting OR infra-red
warning lighting shall be installed with an optimised flash pattern of 60 flashes
per minute of 200ms to 500ms duration at the highest practicable point on all
the turbines in accordance with confirmation of the proposed lighting
Page 41

Page 42

arrangements to be installed which shall have been previously submitted to and
approved in writing by the Council, as planning authority in consultation with the
Ministry of Defence, Defence Infrastructure Organisation Safeguarding Officer
prior to any light installation. Thereafter, the turbines shall be erected with this
confirmed lighting installed and the lighting shall remain operational at all times
throughout the duration of the permission hereby granted. 
Reason: In the interests of military aviation safety. 
27. No development shall commence until details have been submitted to the
Council, as planning authority to confirm the submission of the following
information to the Ministry of Defence, Defence Infrastructure Organisation and
Civil Aviation Authority (Defence Geographic Centre (AIS Information Centre)): 
a)  the date construction starts and ends; 
b)  the exact position of the wind turbine towers in latitude and longitude; 
c)  a description of all structures over 300 feet high; 
d)  the maximum extension height of all construction equipment; the height
above ground level of the tallest structure; and 
e)  details of the approved lighting scheme to be installed (Condition 26
refers). 
Reason: To ensure the erected turbines present no risk to air safety. 
28. No development shall commence until details have been submitted to the
Council, as planning authority in consultation with Forestry Commission
Scotland regarding details of a woodland planting scheme (the Replanting
Scheme) within Moray to compensate, in this case, the removal of 8ha of
existing woodland from the site in order to accommodate the development. 
The Replanting Scheme details shall: 
a)  include the specifications for 
i.  on-site replanting; 
ii.  off-site compensatory planting; 
iii.  tree maintenance and protection to established planting (including 
Deer Management); and 
b)  comply with the requirements set out in the UK Forestry Standard
(Forestry Commissions, 2011. ISBN 978-0-85538-830-0) and the
guidelines to which it refers and include: 
i.  details of the location of the area to be planted; 
ii.  details of land owners and occupiers of the land to be planted; 
iii.  the nature, design and specification of the proposed woodland to be
planted; 
iv.  details of all necessary consents for the Replanting Scheme and
timescales within which each shall be obtained; 
v.  the phasing and associated timescales for implementing the 
Replanting Scheme; and 
vi. proposals for the maintenance and establishment of the Replanting
Scheme, including annual checks; protection from predation;
replacement planting; fencing; ground preparation; and drainage,
etc. 
Thereafter, the development shall be implemented in accordance with the
approved Replanting Scheme details, including the phasing and timescales as
set out therein. 
Page 42

Page 43

Reason: Details of the matters specified are lacking from the submission and
to ensure an acceptable form of development where replacement or
compensatory planting is provided where the development results in a loss of
woodland. 
29. No development shall commence until details shall be submitted to and
approved by the Council, as planning authority in consultation with the
Environmental Health Manager regarding a Noise Management Plan, to identify
all sources of noise emissions associated with the construction phase of the
development together with details of all measures to manage and mitigate the
effects of construction noise occurring at and within the site. Thereafter, the
development shall be implemented in accordance with the approved
management plan. 
Reason: Details of the matters specified are lacking from the submitted
particulars and have yet to be determined (Environmental Statement, Volume
2, Chapter 7 refers) and in order to manage and minimise the impact of noise
associated with construction activity upon the amenity of local residents. 
30. The rating level of noise emissions from the combined effects of the 6 wind
turbines comprising the Meikle Hill wind farm as hereby approved (including the
application of any tonal penalty) when determined in accordance with the
attached Guidance Notes (see Additional Information as included in this formal
decision notice) shall not exceed the values for the relevant integer wind speed
set out in, or derived from, the tables attached to these conditions at any
dwelling which is lawfully existing or has planning permission at the date of this
permission and: 
a)  The wind farm operator shall continuously log power production, wind
speed and wind direction, all in accordance with Guidance Note 1(d). This
data shall be retained for a period of not less than 24 months. The wind
farm operator shall provide this information in the format set out in
Guidance Note 1(e) to the Council, as planning authority on its request,
within 14 days of receipt in writing of such a request. 
b)  Within 21 days from receipt of a written request from the Council, as
planning authority following a complaint to it from an occupant of a
dwelling alleging noise disturbance at that dwelling, the wind farm
operator shall, at its expense, employ a consultant approved by the
Council, as planning authority to assess the level of noise emissions from
the wind farm at the complainant's property in accordance with the
procedures described in the attached Guidance Notes. The written
request from the Council, as planning authority shall set out at least the
date, time and location that the complaint relates to and any identified
atmospheric conditions, including wind direction, and include a statement
as to whether, in the opinion of the Council, as planning authority, the
noise giving rise to the complaint contains or is likely to contain a tonal
component. 
c)  The assessment of the rating level of noise emissions shall be undertaken
in accordance with an assessment protocol that shall previously have
been submitted to and approved in writing by the Council, as planning
authority. The protocol shall include the proposed measurement location
identified in accordance with the Guidance Notes where measurements
for compliance checking purposes shall be undertaken, whether noise
giving rise to the complaint contains or is likely to contain a tonal
component, and also the range of meteorological and operational
Page 43

Page 44

conditions (which shall include the range of wind speeds, wind directions,
power generation and times of day) to determine the assessment of rating
level of noise emissions. The proposed range of conditions shall be those
which prevailed during times when the complainant alleges there was
disturbance due to noise, having regard to the written request of the
Council, as planning authority under paragraph (b), and such others as
the independent consultant considers likely to result in a breach of the
noise limits. 
d)  Where a dwelling to which a complaint is related is not listed in the tables
attached to these conditions, the wind farm operator shall submit to the
Council, as planning authority for written approval proposed noise limits
selected from those listed in the Tables to be adopted at the complainant's
dwelling for compliance checking purposes. The proposed noise limits are
to be those limits selected from the Tables specified for a listed location
which the independent consultant considers as being likely to experience
the most similar background noise environment to that experienced at the
complainant's dwelling. The rating level of noise emissions resulting from
the combined effects of the wind turbines when determined in accordance
with the attached Guidance Notes shall not exceed the noise limits
approved in writing by the Council, as planning authority for the
complainant's dwelling. For the sake of clarification the Meikle Hill Wind
Farm Environmental Statement, Volume 2, Main Report, Chapter 7, has
advised that any occupants of Aultahuish and Scottackleys have a direct
financial involvement in the wind farm development. Therefore, in
accordance with ETSU-R-97, higher noise limits are applicable under
these conditions for these properties only. 
e)  The wind farm operator shall provide to the Council, as planning authority
the independent consultant's assessment of the rating level of noise
emissions undertaken in accordance with the Guidance Notes within 2
months of the date of the written request of the Council, as planning
authority for compliance measurements to be made under paragraph (b),
unless the time limit is extended in writing by the Council, as planning
authority. The assessment shall include all data collected for the purposes
of undertaking the compliance measurements, such data to be provided in
the format set out in Guidance Note 1(e) of the Guidance Notes. The
instrumentation used to undertake the measurements shall be calibrated
in accordance with Guidance Note 1(a) and certificates of calibration shall
be submitted to the Council, as planning authority with the independent
consultant's assessment of the rating level of noise emissions. 
f)  Where a further assessment of the rating level of noise emissions from
the wind farm is required pursuant to Guidance Note 4(c), the wind farm
operator shall submit a copy of the further assessment within 21 days of
submission of the independent consultant's assessment pursuant to
paragraph (c) above unless the time limit has been extended in writing by
the Council, as planning authority. 
Table 1: Between 07:00 and 23:00 - Noise limits expressed in dB LA90,10
minute as a function of the standardised wind speed (m/s) at 10 metre height
as determined within the site averaged over 10 minute periods. 
Location: Standardised wind speed at 10 metre height (m/s) within the site
averaged over 10-minute periods. 
Page 44

Page 45

3 4 5 6 7 8 9 10 11 12
Tombreck
Farm
35  35  35  35  37.6  40.9  44.2  47.4  50.1  52.3 
Scottackleys 45  45  45  45  45  45  45  45  45.4  48.9 
Aultahuish 45  45  45  45  45  45  45.4  48.7  51.7  54.2 
Torchastle 35  35  35  35  37.2  40.9  44.5  47.8  50.7  52.9 
Ballachraggan 35  35  35  35  36.2  38.7  41.3  44.0  46.5  48.9 
Table 2: Between 23:00 and 07:00 - Noise limits expressed in dB LA90,10
minute as a function of the standardised wind speed (m/s) at 10 metre height
as determined within the site averaged over 10 minute periods. 
Location: Standardised wind speed at 10 metre height (m/s) within the site
averaged over 10-minute periods. 
3 4 5 6 7 8 9 10 11 12
Tombreck Farm  40  40  40  40  40  40  40.6  43.6  46  47.4 
Scottackleys  45  45  45  45  45  45  45  45  45.8  48.8 
Aultahuish  45  45  45  45  45  45  45  46.9  49.8  54.2 
Torchastle  40  40  40  40  40  40  40.6  43.6  46  47.4 
Ballachraggan  40  40  40  40  40  40  40.2  43.1  45.9  48.4 
Table 3: Coordinate locations of the properties listed in Tables 1 and 2. 
Property Easting Northing
Tombreck Farm  314030 852721
Scottackleys 312914 850420
Aultahuish 314038 849458
Torchastle 313163 852532
Ballachraggan   313336 849197 
Note to Table 3: The geographical coordinate references are provided for the
purpose of identifying the general location of dwellings to which a given set of
noise limits applies. 
Reason: To ensure an acceptable form of development and in order to protect
the amenity of any nearby residents from any undue noise and disturbance. 
31. Prior to the first commencement of the operation of the development hereby
approved details shall be submitted to and approved by the Council, as
planning authority in consultation with the Environmental Health Manager,
regarding a scheme for the assessment and regulation of amplitude modulation
effects. 
Reason: To ensure an acceptable form of development and in order to protect
the amenity of any nearby residents from any undue noise and disturbance. 
8. PLANNING APPLICATION 22/01094/AMC 
Councillor Cameron left the meeting at this juncture. 
Page 45

Page 46

Ward 8 – Forres 
Approval of matters specified in conditions 1, 4-6 imposed on 19/00320/PPP
(Erect a dwellinghouse and associated landscaping) on Plot 5 North Whins
Findhorn Moray for Arboreal Architecture 
A report was submitted by the Appointed Officer recommending that, for reasons
detailed in the report, planning permission be granted for an approval of matters
specified in conditions 1, 4-6 imposed on 19/00320/PPP (Erect a dwellinghouse and
associated landscaping) on Plot 5, North Whins, Findhorn, Moray for Arboreal
Architecture. 
It was noted that the application had been referred to Committee as it was agreed at
the meeting on 10 December 2019 that all further applications related to reference
19/00320/PPP be reported to this Committee. 
Following consideration, the Committee agreed to grant planning permission in
respect of Planning Application 22/01094/AMC subject to the following conditions
and reasons: 
1. That the development to which the permission relates must be begun not later
than whichever is the later of the following dates:-
(i)  the expiration of 3 years from the date of the grant of planning permission
in principle; or
(ii)  the expiration of 2 years from the final approval of the matters specified in
conditions or in the case of approval on different dates the final approval
of the last such matter to be approved. 
Reason: The time limit condition is imposed in order to comply with the
requirements of Section 59 of the Town and Country Planning (Scotland) Act
1997 as amended by the Planning etc. (Scotland) Act 2006.  
2. The development hereby granted forms part of, and is related to, the
development granted planning permission under formal decision notice
19/00320/PPP dated 4 November 2019 wherein the terms and conditions as
attached to that permission are hereby reiterated and remain in force in so far
as they relate to the development hereby approved, in particular Conditions 10-
20 inclusive, including any details already approved there under to discharge
the requirements of the identified conditions. 
Reason: To ensure an acceptable form of development and that it progresses
in accordance with the already approved and required details. 
3. Development shall not proceed except in accordance with the Drainage
Statement by whitby wood (ref: P450000-FN-C-0001) for 601 North Whins,
Findhorn received on 10 August 2022.   
Reason: In order to minimise the impacts of the development works upon the
environment. 
4. All landscaping works shall be carried out in accordance with approved plan
156-2.20 REV – H. Unless otherwise agreed in writing with the planning
authority details all planting, seeding or turfing shall be carried out in the first
planting season following the first occupation of any of the units hereby
Page 46

Page 47

approved.  Any trees or plants which (within a period of 5 years from the
planting) die, are removed or become seriously damaged or diseased shall be
replaced in the following planting season with others of similar size, number
and species unless otherwise approved by the Council, as Planning Authority. 
Reason: To ensure that the approved landscaping works are timeously carried
out and properly maintained in a manner which will not adversely affect the
development or amenity and character of the area and because no such
information was included with the application.   
5. Parking provision shall be two car parking spaces for the dwelling house. The
car parking spaces shall be provided within the space as per the drawing No.
156-1.00, prior to the first occupation and thereafter the parking spaces shall be
retained throughout the lifetime of the development, unless otherwise agreed in
writing with the Council as Planning Authority. 
Reason: To ensure the permanent availability of the level of parking necessary
for residents/visitors/others in the interests of an acceptable development and
road safety. 
6. For the avoidance of doubt, the annexe hereby approved shall be used solely
for purposes incidental to the enjoyment of the dwelling hereby, currently
known as ‘Plot 5, North Whins’. At all times it shall be used for purposes
incidental and ancillary to the use of that existing property and not used, let or
otherwise disposed of as a separate unit of accommodation nor used for any
other purpose. 
Reason: In order to enable the Planning Authority to retain effective control
over future development within the application site so that it is carefully
managed and does not result in over-development or an adverse impact on the
amenity of the area. 
9. MORAY LOCAL DEVELOPMENT PLAN 2027 – BUSINESS NEEDS AND
WOODLAND STRATEGY PROCUREMENT REQUIREMENT 
A report by the Depute Chief Executive (Economy, Environment and Finance) asked
the Committee to approve the appointment of external consultants to carry out a
Business Needs Survey and a Woodland Strategy, both of which will be used to
inform the Evidence Report stage of the new Local Development Plan (LDP) and the
Regional Spatial Strategy (RSS). 
During discussion surrounding the Woodland Strategy, it was queried whether
previous decisions relating to woodland use had been considered, particularly in
relation to biomass and predicted fuel sources. 
In response, the Strategic Planning and Development Manager advised that these
were issues were being considered and that briefs in relation to the Business Needs
Study and the Woodland Strategy are being prepared within his Team and that he
would share these with members of the Committee following the meeting.  This was
noted. 
Following consideration, the Committee agreed: 
Page 47

Page 48

(i) the appointment of external consultants to undertake a Business Needs
Survey and a Woodland Strategy for Moray; 
(ii) to note that the Strategic Planning and Development Manager would share
the briefs in relation to the Business Nees Study and the Woodland
Strategy following the meeting. 
10. TOWN CENTRE IMPROVEMENT PLANS 
Under reference to paragraph 10 of the Minute of the meeting of this Committee
dated 18 January 2022, a report by the Depute Chief Executive (Economy,
Environment and Finance) asked the Committee to note the representations
received to the draft Town Centre Improvement Plans (TCIP) and agree the
Council’s response to these, approve the final TCIP for Aberlour, Buckie, Dufftown,
Forres, Keith and Lossiemouth and Delivery Plan, and agree the allocation of funds
for TCIP proposals as set out in section 5.4 of the report. 
During her introduction, Ms Webster, Senior Planning Officer (Strategic Planning and
Development) advised that recommendation iii) in the report should include
reference to section 5.2 and 5.4 of the report.  This was noted. 
During discussion surrounding the Economic Recovery Fund, in particular, £10k
being allocated for the refurbishment of public toilets in Aberlour, it was queried
whether Community Groups in Aberlour could be consulted on the most appropriate
way to use this money to benefit the community. 
In response, the Head of Economic Growth and Development suggested that the
decision on how the £10k spend for Aberlour Public Toilets and public realm works
be applied be delegated to himself following public consultation as part of the new
local development plan and in consultation with Ward Members.  This was agreed. 
Thereafter, the Committee joined the Chair in commending Officers in bringing
forward the Town Centre Improvement Plans and thereafter agreed: 
(i) to note the representations received to the public consultation on the draft TCIP
for Aberlour, Buckie, Dufftown, Forres, Keith and Lossiemouth and the Council’s
response to these set out in Appendix 1; 
(ii) to approve the final TCIP and Delivery Plan for Aberlour, Buckie, Dufftown,
Forres, Keith and Lossiemouth set out in Appendix 2 and that these will be a
material consideration in the development management process; 
(iii) the TCIP projects set out in section 5.2 and 5.4 of this report are to be funded
through the Place-based Investment Fund (PBIF) for the financial year 2022/23
and Economic Recovery Fund (ERF) for the financial year 2023/24; 
(iv) to delegate to the Head of Economic Growth and Development the £10k spend
for Aberlour Public Toilets and public realm works, which will be subject to public
consultation as part of the new local development plan and consultation with
Ward Members to determine how the £10k funding will be applied. 
11. BROWNFIELD SITES – SHORTLIST
Page 48

Page 49

Councillor Cameron re-joined the meeting at this juncture. 
Under reference to paragraph 17 of the Minute of the meeting of this Committee
dated 1 March 2022, a report by the Depute Chief Executive (Economy, Environment
and Finance) informed the Committee of the assessment of brownfield sites, the
prioritisation of sites and next steps to assess feasibility and develop options. 
During discussion surrounding the redevelopment of brownfield sites in town centres,
it was queried whether consideration could be given to the provision of
accommodation for 2-3 groups and nursery children due to a shortage of provision in
this area. 
In response, the Strategic Planning and Development Manager agreed to this
request. 
Thereafter, the Committee agreed: 
(i) that the sites identified at 4.3 are taken forward in the short term for further
investigation and feasibility work; 
(ii) to delegate authority to the Head of Economic Growth and Development to
incorporate substitute sites to be taken forward for feasibility work should funding
not be secured for other priority sites or any of the sites prove at an early stage to
be unfeasible; and 
(iii) that consideration be given to the provision of accommodation for 2-3 groups and
nursery children when considering redevelopment of brownfield sites. 
12. SUSPENSION OF STANDING ORDERS 
The Chair sought the agreement of the Committee to suspend Standing Order 75 to
allow the meeting to continue beyond 12.45 pm.  This was agreed. 
13. QUESTION TIME 
Councillor Warren welcomed the reinstatement of site visits however queried how
these had been reinstated as she was of the view that a decision had to be made by
Full Council. 
In response, the Head of Economic Growth and Development explained that the
original report had asked for agreement to temporarily suspend site visits due to the
restrictions in place as a result of the Covid-19 pandemic and, as these restrictions
are now lifted, it was considered that site visits could automatically resume without
the need for a further report to Council. 
The Legal Adviser apologised to the Committee stating that she had been of the
understanding that a report to Council lifting the suspension was required which is
why she had given this advice consistently.  This had subsequently proved not to be
the case. 
Page 49

Page 50

Councillor Leadbitter sought an update on the Pop-Up Shop Scheme as he was
aware of businesses that are keen to use it. 
In response, the Head of Economic Growth and Development advised that Officers
are trying to progress the scheme however there are some difficulties in relation to
obtaining lease agreements.  He further advised that the suitability of some premises
in the High Street in Elgin are currently being considered. 
Councillor Ross made reference to the recent Public Inquiry in relation to the Clash
Gour and Rothes III developments where the decision made by the Council to object
to the development was overturned by the Reporter with consent being granted for
both developments and queried how much it had cost the Council to make
representations at the Public Inquiry. 
In response, the Legal Adviser advised that the external cost to the Council currently
sits at around £150,000 which did not include staff time. 
Councillor Ross raised concern that the Council may be reluctant to make
representations on developments due to the risk of cost to the Council should the
decision be challenged. 
In response, the Legal Adviser advised that the Council could not compromise its
policies when responding to consultations or considering planning applications and
that further discussions would need to take place in this regard. 
The Head of Economic Growth and Development further stated that the Council
would not avoid making a representation to escape cost and would always try to
defend its position.  With regard to the cost to the Council in relation to the Public
Inquiry process, this has been raised with the Chief Planner, the DPEA and Energy
Consents Unit with a view to making the process easier and less costly.  He further
added that National Planning Framework 4 would shape policies in Moray in the
future in terms windfarm development and how local communities could benefit from
these developments. 
Councillor Leadbitter asked if the Chairs of the Planning and Regulatory Services
and Economic Development and Infrastructure Services Committees could raise
these concerns with COSLA. 
In response, both Chairs agreed to this request. 
Councillor Van Der Horn raised concern in relation to developments that impact
cycle and walkways, particularly in relation to the impact to the B9011 in Kinloss
where the new development cuts through the existing cycle and footpath and the
remedial works to the cycle and walkways were sub-standard. 
In response, the Development Management and Building Standards Manager
advised that she was aware of some enquires in relation to breaches of planning
control on that site and would look into this further. 
Page 50

Page 51

GUIDANCE NOTE PRODUCED FOR PLANNING & REGULATORY SERVICES COMMITTEE
MEETING OF 20 DECEMBER 2022 
REPORT ON APPLICATION 
“Note for guidance of the Committee where the decision of the Planning and Regulatory Services Committee is
contrary to the recommendations of the Director of Environmental Services in respect to a Planning Application.” 
Any Councillor putting forward a motion to refuse an application, contrary to recommendation, shall clearly state the
reasons for refusal.  These reasons should be based on policies contained in the approved Local Development Plan or
some other material consideration.  Time should be allowed to ensure that these reasons are carefully noted for
minuting purposes. 
Where Councillors put forward a motion to approve an application, contrary to recommendation, an indication
should be given of any specific matters which should be subject of conditions along with reasons which should be
based on policies in the approved Local Development Plan or some other appropriate consideration. 
Note for guidance where the decision of the Planning and Regulatory Services Committee is to depart from the
Local or Structure Plan. 
Where a Councillor is convinced that there is reason to depart from Local Development Plan policy; then the
Councillor’s reasons for making the motion should be clearly stated for minuting purposes.  Any matters which should
be subject to conditions drafted subsequently by the Director of Environmental Services should be indicated. If the
Committee remains of a mind to approve such an application then the whole matter will be subject to statutory
procedures as apply. In such cases, Councillors should be aware that the application may require to be advertised as
a departure and any objections reported to the next available meeting of the Planning and Regulatory Services
Committee.  It also may be necessary to convene a hearing to consider the views of objectors. 
There are three potential consequences if Committee takes a decision where the proper procedures have not been
followed in whole or in part.  Firstly, the person aggrieved by a decision may apply to the Supreme Courts in Scotland
for an Order either compelling the Council to act according to law, quashing the decision altogether or declaring a
decision to be unlawful coupled with an order to prevent the decision being implemented.  A referral to the Supreme
Courts in these circumstances is known as applying for Judicial Review.   
Secondly, in addition to the application for Judicial Review when questions of alleged failure, negligence or
misconduct by individuals or local authorities in the management of public funds arise and are raised either by or
with the External Auditor of the Council and where an individual can be blamed the sanctions available are:- 
Censure of a Councillor or an Officer
Suspension of a Councillor for up to one year
Disqualification of a Councillor for up to five years 
In the case of the Council being to blame, recommendations may be made to the Scottish Ministers about rectification
of the authorities accounts. Ministers can make an order giving effect to these recommendations. 
Thirdly, whilst the Ombudsman accepts that Planning authorities have the freedom to determine planning applications
as they wish procedural impropriety may be interpreted as maladministration.  This can also lead to recommendations
by the Ombudsman that compensation be paid. 
Consistent implementation of departure procedures maintains public confidence in the planning system and is
consistent with the time and effort invested in preparing the Local Development Plan. 
Page 51

Page 52

Page 52

Page 53

WARD 04_17 
22/01104/APP
14th September
2022
Proposed new recycling building at Grays Recycling Ltd
Nether Dallachy Spey Bay Fochabers
for Grays Recycling Services Ltd 
Comments:  
 This application is not a major application but the floor area proposed exceeds
2000m2 and under the approved delegation scheme is required to be determined
by the Planning & Regulatory Services Committee.
 The application was advertised for neighbour notification purposes. 
 No representations have been received. 
Procedure: 
None. 
Recommendation    Grant Planning Permission - subject to the following: 
Conditions/Reasons 
1. The development to which this permission relates must be began not later than
the expiration of 3 years beginning with the date on which this permission is
granted. 
Reason: The time limit condition is imposed in order to comply with the
requirements of section 58 of the Town and Country Planning (Scotland) Act 1997
as amended. 
2. No development shall commence until a Construction Traffic Management Plan
(CTMP) has been submitted to and agreed in writing by the Planning Authority in
consultation with the Roads Authority. Thereafter the development shall be carried
out in accordance with the agreed CTMP at all times. For the avoidance of doubt
the CTMP shall include as a minimum the following information: 
   Details of the routes for construction traffic from the A Class Road network to
the site; 
   duration of works; 
   construction programme;  parking provision, loading and unloading areas for
construction traffic; 
   full details of temporary arrangements to safeguard pedestrian movements
during the construction period; 
Item 6
Page 53

Page 54

   full details of any temporary access; 
   measures to be put in place to prevent material being deposited on the
public road; 
   traffic management measures to be put in place during works including any
specific instructions to drivers; and
   a programme of monitoring for all routes identified within the CTMP during
construction will be required. 
Reason: To ensure an acceptable form of development in terms of the
arrangements to manage traffic during construction works at the site. 
3. All drainage proposals shall be in accordance with the submitted report entitled
Surface Drainage Design Report, by Campbell of Doune Ltd dated July 2022 and
approved drawings 2749-031 and 301 and shall be provided in full prior to the first
use of the building hereby approved.   
Reason: To ensure that surface water drainage is provided timeously and
complies with the principles of SuDS; in order to protect the water environment. 
4. All planting shall be carried out in accordance with approved plan 2749 -032 rev B
and shall be carried out in the first planting season following the completion of the
building hereby approved.  Thereafter the landscaping and planting shall be
maintained as detailed on the approved plan.   
Reason: To ensure that the landscaping and associated biodiversity
enhancement are timeously provided. 
Reason(s) for Decision
The Council’s reason(s) for making this decision are:- 
The proposal accords with the provisions of the development plan and there are no
material considerations that indicate otherwise.   
List of Informatives: 
THE TRANSPORTATION MANAGER, DIRECT SERVICES has commented that:- 
Planning consent does not carry with it the right to carry out works within the
public road boundary. 
The roads from the A98 to the site (U8E Enzie - Cunninghaugh Road and U9E
Auchenhalrig Road) and the road from the site to East of Portgordon (C16E Byres
- Tannachy Road) would not be suitable for the movement of construction traffic. 
Public utility apparatus may be affected by this proposal. Contact the appropriate
utility service in respect of any necessary utility service alterations which have to
be carried out at the expense of the developer. 
Page 54

Page 55

No building materials/scaffolding/builder’s skip shall obstruct the public road
(including footpaths) without permission from the Roads Authority. 
SCOTTISH WATER have commented as follows: 
The applicant should be aware that we are unable to reserve capacity at our water
and/or waste water treatment works for their proposed development. Once a
formal connection application is submitted to Scottish Water after full planning
permission has been granted, we will review the availability of capacity at that time
and advise the applicant accordingly. 
All proposed developments require to submit a Pre-Development Enquiry (PDE)
Form to be submitted directly to Scottish Water via our Customer Portal prior to
any formal Technical Application being submitted. This will allow us to fully
appraise the proposals. 
Where it is confirmed through the PDE process that mitigation works are
necessary to support a development, the cost of these works is to be met by the
developer, which Scottish Water can contribute towards through Reasonable Cost
Contribution regulations. 
Since the introduction of the Water Services (Scotland) Act 2005 in April 2008 the
water industry in Scotland has opened to market competition for non-domestic
customers. All Non-domestic Household customers now require a Licensed
Provider to act on their behalf for new water and waste water connections. Further
details can be obtained at www.scotlandontap.gov.uk 
Certain discharges from non-domestic premises may constitute a trade effluent in
terms of the Sewerage (Scotland) Act 1968. Trade effluent arises from activities
including; manufacturing, production and engineering; vehicle, plant and
equipment washing, waste and leachate management. It covers both large and
small premises, including activities such as car washing and launderettes.
Activities not covered include hotels, caravan sites or restaurants. 
If you are in any doubt as to whether the discharge from your premises is likely to
be trade effluent, please contact us on 0800 778 0778 or email
TEQ@scottishwater.co.uk using the subject “Is this Trade Effluent?". Discharges
that are deemed to be trade effluent need to apply separately for permission to
discharge to the sewerage system. The forms and application guidance notes can
be found here. 
SW Public General. 
Trade effluent must never be discharged into surface water drainage systems as
these are solely for draining rainfall run off. 
Page 55

Page 56

LIST OF PLANS AND DRAWINGS SHOWING THE DEVELOPMENT
Reference No. Version No. Title/Description
301  Surface Drainage arrangement
2749-LP  Location plan
2749-030  Elevations and floor plans
2479-031  Site plan and sections 
2479-032 Landscaping plan 
Page 56

Page 57

Plans, drawings and other material submitted to the local authority
are protected by the Copyright, Designs and Patents Act 1988
(section 47). You may only use material which is downloaded and/
or printed for consultation purposes, to compare current
applications with previous schemes and to check whether
developments have been completed in accordance with approved
plans.
Further copies must not be made without the prior permission of
the copyright owner.
Maps shown in the Planning Committee Report can only be used
for the purposes of the Planning Committee. Any other use risks
infringing Crown Copyright and may lead to prosecution or civil
proceedings. Maps produced within this Planning Committee
Report can only be reproduced with the express permission of the
Moray Council and other Copyright holders. This permission must
be granted in advance.
PLANNING APPLICATION
COMMITTEE SITE PLAN
Site Address:
Grays Recycling Ltd
Nether Dallachy
Planning Application Ref Number: 
22/01104/APP 
Location Plan
Applicant Name: 
Grays Recycling Services Ltd 
Page 57

Page 58

Site Location
Page 58

Page 59

Site
plan
16/01664/APP
Page 59

Page 60

Landscaping
16/
Page 60

Page 61

Elevations
Page 61

Page 62

Photo location plan
Page 62

Page 63

Page 63

Page 64

Page 64

Page 65

PLANNING APPLICATION: 22/01104/APP 
In the event that a recommendation on this planning application is overturned the
Committee is reminded of the advice contained on the front page of the agenda for
Reports on Applications 
1. THE PROPOSAL 
    This application seeks planning permission for a building to house
recycling operations at an existing recycling site.
   The proposed building measures 30m x 72m and will be 10.94m to the
ridge.
   The building will have concrete walls with blue metal sheeting on the roof
and upper parts of the walls.  The blue will match the colour of existing
buildings on site.
   The output of the site will remain 20,800 tonnes per year and there will be
no increase as a result of this development.
   The operational hours of the site are 0730 – 1730 Monday – Friday and
0730 -1200 on a Saturday.  These will not be altered.  
   A landscaping plan has been provided.
   A drainage statement and supporting statement have been provided
support of the application. 
2. THE SITE 
   The site is an existing recycling business on the edge of the former
Dallachy Airfield.
   The site is surrounded by open countryside.
   The site extends to 2ha and includes all of the existing recycling complex.
   There is a collection of buildings on site along with skips and other
external storage.
   There is an existing access from the public road which runs to the east of
the site. 
3. HISTORY 
09/00856/FUL - Erect a steel portal framed building to form office workshop
and secure shredding accommodation at The Old Airfield, Nether Dallachy –
Granted 24.11.2009. 
06/02545/FUL - Erection of prefabricated office at Disused Airfield, Nether
Dallachy – Granted 26.01.2007. 
Page 65

Page 66

4. POLICY - SEE APPENDIX 
5. ADVERTISEMENTS 
5.1 Advertised for neighbour notification expired 30 September 2022. 
6. CONSULTATIONS 
Transportation: No objection subject to a condition relating to the provision of
Construction Traffic Management Plan (CTMP). 
Environmental Health: No objection 
Moray Flood Risk Management: No objection 
Contaminated Land: No objection 
Archaeology: No objection 
Scottish Water: No objection 
SEPA:  No objection on flood risk grounds. Based on available information
there is some uncertainty over the accuracy of the flood maps in this location as
there are no records of flooding in the vicinity of the site or within the Dry Burn
catchment.  However, the proposal relates to an existing site so there will be no
increase in the vulnerability of use, and the development will allow materials
currently stored outside to be enclosed which would reduce the level of material
that could be mobilised in the event of a flood so SEPA would have no
concerns in relation to flood risk.   
Environmental Protection (waste) – No objection.  Welcome the proposal as
it will enable containment of material and allow for loading and unloading of
vehicles to be done without being impacted by weather conditions. Additional
sorting / separation facilities is also an environmental benefit as it will allow
more recyclable material to be extracted from waste stockpiles and improving
the quantity and quality of recyclable material. 
7. OBJECTIONS-REPRESENTATIONS 
None. 
8. OBSERVATIONS 
8.1 Following consideration of the revised draft National Planning Framework 4
which was laid before parliament on 8th November 2022, the draft (yet to be
formally adopted) is to be given no weight in the consideration of planning
applications. Section 25 of the 1997 Act as amended requires applications to
be determined in accordance with the development plan i.e. the adopted Moray
Page 66

Page 67

Local Development Plan 2020 (MLDP) unless material considerations indicate
otherwise. The main planning issues are considered below: 
8.2 Principal of Development (DP1 & DP5) 
Policy DP5 supports the extension of rural business where there is a locational
need for the site and the proposal is in accordance with all other relevant
policies.  The proposal forms part of a well-established business and the use
will allow the continuation and consolidation of that business.  There is a strong
locational need for this development in this location alongside the existing
business which includes several buildings and significant external storage.  The
proposal will allow a new sorting and picking facility to be installed which will
increase efficiency and allow more recyclable material to be extracted from
waste.  Once this building is operational there will be no further need for
external storage and vehicles will be unloaded within the building which will
reduce the impact of weather.  This picking and sorting machinery is similar to
that in the existing building but it is more efficient.  The proposal will allow the
existing business to make the practices more efficient and external storage to
cease.  This will enhance the overall appearance of the site and reduce the risk
of loose material escaping outwith the site particularly during in bad weather. 
The proposed building is suitably sited alongside an existing building within an
established business complex.  There are no immediate neighbours or other
receptors who would be adversely impacted by the development.  The use is
appropriate to its setting and will not result in an overbearing loss of amenity. 
The proposal complies with policies DP1 (i) (e) and DP5.   
8.3 Design & Materials (DP1) 
The building has a basic rectangular footprint with a pitched roof.  The walls will
be a combination of concrete and metal sheeting and there will be metal
sheeting on the roof.  The metal sheeting will be blue to match existing
buildings on site.  The building has a simple and functional appearance that
reflects the intended use and is in keeping with the character of existing
buildings on site.  The building is larger than the existing building on site but will
be read in the context of the wider recycling complex.  The site is on the edge
of a disused airfield and any development is prominent in this setting. 
However, the site has a strong industrial character that is well established and
this building is in keeping with that.  The proposal is of a scale and character
that is appropriate to the surrounding area and the development complies with
policy DP1 (i) (a). 
8.4 Landscaping & Biodiversity (EP2 & EP5)
Policy EP2 requires proposals for more than 1000m2 to create new or enhance
habitats of ecological and amenity value.  This proposal is supported by a
landscaping plan which shows an area of new planting at the entrance to the
site alongside the public road.  This includes an area of wildflower meadow
along the roadside and planting of native species in the north east corner. The
area of landscaping proposed is relatively small in relation to the overall site but
the proposal is considered to be commensurate with the scale of development
proposed in this application.  The proposed landscaping will create new
foraging and habitat opportunities for birds and other species.  In addition to
creating a new habitat the proposed area of landscaping will enhance the
entrance to the side and will be of amenity value to the overall site.   The
Page 67

Page 68

proposal will create a biodiversity and amenity enhancement and therefore
comply with policies EP2 and EP5. 
8.5 Flood Risk (EP12)
The site is identified on SEPA Flood Risk Maps as being at risk of both fluvial
and pluvial flooding.  SEPA have highlighted that there might be some doubt
over the accuracy of the mapping in this location as they have no records of
flooding in the vicinity or within the Dry Burn catchment.  Nonetheless the site is
identified on the maps and the proposal is assessed on that basis.  SEPA
advise that they have no objection on flood risk grounds.  This assessment is
based on the fact that there is a strong locational need to site this building
alongside the existing operation and there is no change in the vulnerability of
use of the site.  Furthermore, it is noted that some of the material that will be
stored in the proposed building is currently stored outside and this building
would therefore reduce the level of material that might become mobile in the
event of a flood.  It is therefore concluded that the development will not be at
significant risk of flooding nor will it increase the risk of flooding elsewhere.  The
proposal therefore accords with policy EP12.   
8.6 Drainage (EP12) 
It is noted above that the site is identified as being at risk of both fluvial and
pluvial flooding.  A detailed Drainage Impact Assessment has been provided in
support of the application which sets out the justification for the proposed
soakaway.  Moray Flood Risk Management have reviewed and are content with
this information, and have no objection to the proposals.  A condition is
recommended requiring the drainage proposals to be implemented in full in
accordance with the proposed details.  The proposals will ensure that surface
water is effectively managed in a sustainable manner in accordance in with
policy EP12.   
8.7 Access and Parking (DP1)
No changes are proposed to the existing access from the public road or to the
current parking arrangements.  Given that the proposal does not represent a
significant expansion in the operation the Transportation Manager is content
that no alterations or improvements are required.  A condition is recommended
requiring the submission of a Construction Traffic Management Plan.  This
must include details of the route of construction deliveries, arrangements for
unloading as well as the movement of construction vehicles on site.  The
recommended condition will ensure that construction traffic is effectively
managed.  The proposals comply with policy DP1.   
Conclusion
The application will allow the consolidation of an existing business.  The
building is suitably sited and is designed in a manner that is appropriate to the
surrounding area.  The proposal accords with policy and all technical matters
have been adequately addressed.  The proposal is recommended for approval. 
Page 68

Page 69

REASON(S) FOR DECISION
The Council’s reason(s) for making this decision are: - 
The proposal accords with the provisions of the development plan and there
are no material considerations that indicate otherwise. 
Author/Contact
Officer:
Lisa Macdonald           
Senior Planning Officer
Ext: 01343 563479 
Beverly Smith
Development Management & Building Standards Manager
Page 69

Page 70

Page 70

Page 71

APPENDIX 
POLICY 
Adopted Moray Local Development Plan 2015 
Proposed Moray Local Development Plan 2020 
PP1 PLACEMAKING 
a) Development must be designed to create successful, healthy places that support
good physical and mental health, help reduce health inequalities, improve people's
wellbeing, safeguard the environment and support economic development.   
b) A Placemaking Statement is required for residential developments of 10 units and
above to be submitted with the planning application to articulate how the
development proposal addresses the requirements of policy PP1 Placemaking and
other relevant LDP policies and guidance.  The Placemaking Statement must include
sufficient information for the council to carry out a Quality Audit.  Where considered
appropriate by the council, taking account of the nature and scale of the proposed
development and of the site circumstances, this shall include a landscaping plan, a
topographical survey, slope analysis, site sections, 3D visualisations, a Street
Engineering Review and a Biodiversity Plan.  The Placemaking Statement must
demonstrate how the development promotes opportunities for healthy living and
working. The landscape plan must set out details of species type, size, timescales for
planting and maintenance. 
c) To create successful, healthy places residential developments of 10 units and above
must comply with Scottish Government policy Creating Places and Designing Streets
and must incorporate the following fundamental principles: 
(i) Character and Identity
• Create places that are distinctive to prevent homogenous 'anywhere'
development;
• Provide a number of character areas reflecting site characteristics that
have their own distinctive identity and are clearly distinguishable;
• Provide distinctiveness between and in each character area through a
combination of measures including variation in urban form, street
structure/network, architecture and masonry, accent features (such as
porches), surrounds and detailing, materials (buildings and surfaces),
colour, boundary treatments, hard/soft landscaping and a variety of
approaches to tree species and planting that emphasises the hierarchy of
open spaces and streets within a cohesive design strategy for the whole
development;
• Distinctiveness must be reinforced along main thoroughfares, open
spaces and places where people may congregate such as
shopping/service centres;
• Retain, incorporate and/or respond to relevant elements of the landscape
such as topography and planted features, natural and historic
environment, and propose street naming (in residential developments of
20 units and above, where proposed names are to be submitted with the
planning application) to retain and enhance local associations;
Page 71

Page 72

(ii) Healthier, Safer Environments
• Designed to prevent crime, fear of crime and anti-social behaviour with
good levels of natural surveillance and security using treatments such as
low boundary walls, dual frontages (principal rooms) and well-lit routes to
encourage social interaction.  Unbroken high boundary treatments such
as wooden fencing and blank gables onto routes, open spaces and
communal areas will not be acceptable.
• Designed to encourage physical exercise for people of all abilities.
• Create a distinctive urban form with landmarks, key buildings, vistas,
gateways and public art to provide good orientation and navigation
through the development.
• Provide a mix of compatible uses, where indicated within settlement
statements, integrated into the fabric of buildings within the street.
• Prioritise pedestrians and cyclists by providing a permeable movement
framework that incorporates desire lines (including connecting to and
upgrading existing desire lines) and is fully integrated with the surrounding
network to create walkable neighbourhoods and encourage physical
activity.
• Integrate multi- functional active travel routes, green and open space into
layout and design, to create well connected places that encourage
physical activity, provide attractive spaces for people to interact and to
connect with nature.
• Create safe streets that influence driver behaviour to reduce vehicle
speeds that are appropriate to the local context such as through shorter
streets, reduced visibility and varying the building line.
• Provide seating opportunities within streets, paths and open spaces for all
generations and mobility's to interact, participate in activity, and rest and
reflect.
• Provide for people with mobility problems or a disability to access
buildings, places and open spaces.
• Create development with public fronts and private backs. 
• Maximise environmental benefits through the orientation of buildings,
streets and open space to maximise the health benefits associated with
solar gain and wind shelter. 
(iii) Housing Mix
• Provide a wide range of well integrated tenures, including a range of
house types and plot sizes for different household sizes, incomes and
generations and meet the affordable and accessible requirements of
policy DP2 Housing.
• All tenures of housing should have equal access to amenities, greenspace
and active travel routes. 
(iv) Open Spaces/Landscaping
• Provide accessible, multi-functional open space within a clearly defined
hierarchy integrated into the development and connected via an active
travel network of  green/blue corridors that are fully incorporated into the
development and to the surrounding area, and meet the requirements of
policy EP5 Open Space and the Open Space Strategy Supplementary
Guidance and Policy EP12 Managing the Water Environment and
Page 72

Page 73

Drainage Impact Assessment for New Developments Supplementary
Guidance.
• Landscaped areas must provide seasonal variation, (mix of planting and
colour) including native planting for pollination and food production.
• Landscaping areas that because of their size, shape or location would not
form any useable space or that will not positively contribute to the
character of an area will not contribute to the open space requirements of
Policy EP4 Open Space.
• Semi-mature tree planting and shrubs must be provided along all routes
with the variety of approaches reflecting and accentuating the street
hierarchy.
• Public and private space must be clearly defined.
• Play areas (where identified) must be inclusive, providing equipment so
the facility is for every child/young person regardless of ability and
provided upon completion of 50% of the character area.
• Proposals must provide advance landscaping identified in site
designations and meet the quality requirements of policy EP5 Open
Space.
• Structural landscaping must incorporate countryside style paths (such as
bound or compacted gravel) with waymarkers.
•  Maintenance arrangements for all paths, trees, hedging, shrubs, play/
sports areas, roundabouts and other open/ green spaces and blue/green
corridors must be provided. 
v) Biodiversity
• Create a variety of high quality multi- functional green/blue spaces and
networks that connect people and nature, that include trees, hedges and
planting to enhance biodiversity and support habitats/wildlife and comply
with policy EP2 Biodiversity and Geodiversity and EP5 Open Space.
• A plan detailing how different elements of the development will contribute
to supporting biodiversity must be included in the design statement
submitted with the planning application.
• Integrate green and blue infrastructure such as swales, permeable paving,
SUDS ponds, green roofs and walls and grass/wildflower verges into
streets, parking areas and plots to sustainably address drainage and
flooding issues and enhance biodiversity from the outset of the
development.
• Developments must safeguard and where physically possible extend or
enhance wildlife corridors and green/blue networks and prevent
fragmentation of existing habitats. 
(vi) Parking
• Car parking must not dominate the streetscape to the front or rear of
properties.  On all streets a minimum of 50% of car parking must be
provided to the side or rear and behind the building line with a maximum
of 50% car parking within the front curtilage or on street, subject to the
visual impact being mitigated by hedging, low stone boundary walls or
other acceptable treatments that enhance the streetscape.
• Provide semi-mature trees and planting within communal private and
public/visitor parking areas and on-street parking at a maximum interval of
4 car parking spaces.
Page 73

Page 74

• Secure and covered cycle parking and storage, car sharing spaces and
electric car charging points must be provided in accordance with policy
DP1 Development Principles.
• Parking areas must use a variation in materials to reduce the visual
impact on the streetscene. 
(vii) Street Layout and Detail
• Provide a clear hierarchy of streets reinforced through street width,
building density and street and building design, materials, hard/soft
landscaping and a variety of approaches to tree planting and shrubs.
• Streets and connecting routes should encourage walking and cycling over
use of the private car by providing well connected, safe and appealing
routes.
• Design junctions to prioritise pedestrians, accommodate active travel and
public transport and service/emergency vehicles to reflect the context and
urban form and ensure that the street pattern is not standardised.  
• Dead-end streets/cul-de-sacs will only be selectively permitted such as on
rural edges or where topography, site size, shape or relationship to
adjacent developments prevent an alternative more permeable layout.
These must be short, serving no more than 10 units and provide walking
and cycling through routes to maximise connectivity to the surrounding
area.
• Where a roundabout forms a gateway into, or a landmark within, a town
and/or a development, it must be designed to create a gateway feature or
to contribute positively to the character of the area.
• Design principles for street layouts must be informed by a Street
Engineering Review (SER) and align with Roads Construction Consent
(RCC) to provide certainty that the development will be delivered as per
the planning consent. 
(d) Future masterplans will be prepared through collaborative working and in partnership
between the developer and the council for Lochyhill (Forres), Barhill Road (Buckie),
Elgin Town Centre/Cooper Park, Elgin North East, Clarkly Hill, Burghead and West
Mosstodloch.  Masterplans that are not prepared collaboratively and in partnership
with the council will not be supported.  Masterplans that are approved will be
Supplementary Guidance to the Plan.¬¬¬ 
(e) Proposals for sites must reflect the key design principles and safeguard or enhance
the green networks set out in the Proposals Maps and Settlement Statements. 
Alternative design solutions may be proposed where justification is provided to the
planning authority's satisfaction to merit this. 
PP2  SUSTAINABLE ECONOMIC GROWTH
Development proposals which support the Moray Economic Strategy to deliver
sustainable economic growth will be supported where the quality of the natural and built
environment is safeguarded, there is a clear locational need and all potential impacts can
be satisfactorily mitigated. 
PP3  INFRASTRUCTURE & SERVICES
Development must be planned and co-ordinated with infrastructure to ensure that places
function properly and proposals are adequately served by infrastructure and services.   
Page 74

Page 75

a) In relation to infrastructure and services developments will be required to provide the
following as may be considered appropriate by the planning authority, unless these
requirements are considered not to be necessary: 
i)  Education, Health, Transport, Sports and Recreation and Access facilities in
accord with Supplementary Guidance on Developer Obligations and Open
Space. 
ii)  Green infrastructure and network requirements specified in policy EP5 Open
Space, Town and Village Maps and, contained within Supplementary Guidance
on the Open Space Strategy, Masterplans and Development Briefs. 
iii)  Mitigation/modification to the existing transport network (including road and rail)
to address the impact of the proposed development in terms of safety and
efficiency.  This may include but not be limited to passing places, road
widening, junction enhancement, bus stop infrastructure, and drainage
infrastructure.  A number of potential road and transport improvements are
identified and shown on the Town and Village Maps as Transport Proposals
(TSP's) including the interventions in the Elgin Transport Strategy. These
requirements are not exhaustive and do not pre-empt any measures which may
result from the Transport Assessment process. 
iv)  Electric car charging points must be provided at all commercial and community
parking facilities.  Access to charging points must also be provided for
residential properties, where in-curtilage facilities cannot be provided to any
individual residential property then access to communal charging facilities
should be made available.  Access to other nearby charging facilities will be
taken into consideration when identifying the need for communal electric
charging points. 
v)  Active Travel and Core Path requirements specified in the Council's Active
Travel Strategy and Core Path Plan. 
vi)  Safe transport and access routes linking to existing networks and mitigating the
impacts of development off-site. 
vii)  Information Communication Technology (ICT) and fibre optic broadband
connections for all premises unless justification is provided to substantiate it is
technically unfeasible. 
viii)  Foul and surface water drainage, including Sustainable Urban Drainage
Systems (SUDS), including construction phase SUDS. 
ix)  Measures that implement the waste management hierarchy as defined in the
Zero Waste Plan for Scotland including the provision of local waste storage and
recycling facilities designed into the development in accord with policy PP1
Placemaking.  For major applications a site waste management plan may be
required to ensure that waste minimisation is achieved during the construction
phase. 
Page 75

Page 76

x)  Infrastructure required to improve or increase capacity at Water Treatment
Works and Waste Water Treatment Works will be supported subject to
compliance with policy DP1. 
xi) A utilities plan setting out how existing and new utility (including gas, water,
electricity pipelines and pylons) provision has been incorporated into the layout
and design of the proposal.  This requirement may be exempted in relation to
developments where the council considers it might not be appropriate, such as
domestic or very small scale built developments and some changes of use. 
b)  Development proposals will not be supported where they:
i)  Create new accesses onto trunk roads and other main/key routes (A941 & A98)
unless significant economic benefits are demonstrated or such access is
required to facilitate development that supports the provisions of the
development plan. 
ii)  Adversely impact on active travel routes, core paths, rights of way, long
distance and other access routes and cannot be adequately mitigated by an
equivalent or better alternative provision in a location convenient for users. 
iii)  Adversely impact on blue/green infrastructure, including green networks
important for wildlife unless an equivalent or better alternative provision will be
provided. 
iv)  Are incompatible with key waste sites at Dallachy, Gollanfield, Moycroft and
Waterford and would prejudice their operation. 
v)  Adversely impact on community and recreational sites, buildings or
infrastructure including CF designations and cannot be adequately mitigated. 
vi)  Adversely impact on flood alleviation and mitigation infrastructure. 
vii)  Compromise the economic viability of bus or rail facilities.   
c)  Harbours 
Development within and diversification of harbours to support their sustainable
operation will be supported subject to compliance with other policies and settlement
statements. 
d)  Developer Obligations 
Developer obligations will be sought to mitigate any measurable adverse impact of a
development proposal on local infrastructure, including education, healthcare,
transport (including rail), sports and recreational facilities and access routes. 
Obligations will be sought to reduce, eliminate or compensate for this impact.
Developer obligations may also be sought to mitigate any adverse impacts of a
development, alone or cumulatively with other developments in the area, on the
natural environment. 
Where necessary obligations that can be secured satisfactorily by means of a
planning condition attached to planning permission will be done this way.  Where this
cannot be achieved, the required obligation will be secured through a planning
agreement in accordance with Circular 3/2012 on Planning Obligations.  
Page 76

Page 77

Developer obligations will be sought in accordance with the Council's Supplementary
Guidance on Developer Obligations.  This sets out the anticipated infrastructure
requirements, including methodology and rates.   
Where a developer considers that the application of developer obligations renders a
development commercially unviable a viability assessment and 'open-book
accounting' must be provided by the developer which Moray Council, via the District
Valuer, will verify, at the developer's expense.  Should this be deemed accurate then
the Council will enter into negotiation with the developer to determine a viable level
of developer obligations.   
The Council's Developer Obligations Supplementary Guidance provides further detail
to support this policy. 
DP1 DEVELOPMENT PRINCIPLES 
This policy applies to all development, including extensions and conversions and will be
applied reasonably taking into account the nature and scale of a proposal and individual
circumstances. 
The Council will require applicants to provide impact assessments in order to determine
the impact of a proposal. Applicants may be asked to determine the impacts upon the
environment, transport network, town centres, noise, air quality, landscape, trees, flood
risk, protected habitats and species, contaminated land, built heritage and archaeology
and provide mitigation to address these impacts. 
Development proposals will be supported if they conform to the relevant Local
Development Plan policies, proposals and additional guidance, meet the following criteria
and address their individual and cumulative impacts: 
(i) Design
a) The scale, density and character must be appropriate to the surrounding area
and create a sense of place (see Policy PP1) and support the principles of a
walkable neighbourhood. 
b) The development must be integrated into the surrounding landscape which will
include safeguarding existing trees and undertaking replacement planting to
include native trees for any existing trees that are felled, and safeguarding any
notable topographical features (e.g. distinctive knolls), stone walls and existing
water features by avoiding channel modifications and culverting. A tree survey
and tree protection plan must be provided with planning applications for all
proposals where mature trees are present on site or that may impact on trees
outwith the site. The strategy for new tree provision should follow the principles
of the "Right Tree in the Right Place". 
c) Make provision for new open space and connect to existing open space under
the requirements of Policy EP5 and provide details of the future maintenance of
these spaces. A detailed landscape plan must be submitted with planning
applications and include information about green/blue infrastructure, tree
species, planting, ground/soil conditions, and natural and man-made features
(e.g. grass areas, wildflower verges, fencing, walls, paths, etc.).
Page 77

Page 78

d) Demonstrate how the development will conserve and enhance the natural and
built environment and cultural heritage resources, retain original land contours
and integrate into the landscape. 
e) Proposals must not adversely impact upon neighbouring properties in terms of
privacy, daylight or overbearing loss of amenity. 
f)  Proposals do not result in backland development or plots that are subdivided by
more than 50% of the original plot.  Sub-divided plots must be a minimum of
400m2, excluding access and the built-up area of the application site will not
exceed one-third of the total area of the plot and the resultant plot density and
layout reflects the character of the surrounding area. 
g)  Pitched roofs will be preferred to flat roofs and box dormers are not acceptable. 
h)  Existing stone walls on buildings and boundaries must be retained. 
Alterations and extensions must be compatible with the character of the
existing building in terms of design, form, choice of materials and positioning
and meet all other relevant criteria of this policy. 
i)  Proposals must orientate and design buildings to maximise opportunities for
solar gain. 
j)  All developments must be designed so as to ensure that all new buildings avoid
a specified and rising proportion of the projected greenhouse gas emissions
from their use (calculated on the basis of the approved design and plans for the
specific development) through the installation and operation of low and zero-
carbon generating technologies. 
(ii) Transportation
a) Proposals must provide safe entry and exit from the development, including the
appropriate number and type of junctions, maximise connections and routes for
pedestrians and cyclists, including links to active travel and core path routes,
reduce travel demands and ensure appropriate visibility for all road users at
junctions and bends. Road, cycling, footpath and public transport connections
and infrastructure must be provided at a level appropriate to the development
and connect people to education, employment, recreation, health, community
and retail facilities. 
b) Car parking must not dominate the street scene and must be provided to the
side or rear ¬and behind the building line. Maximum (50%) parking to the front
of buildings and on street may be permitted provided that the visual impact of
the parked cars is mitigated by hedging or low stone boundary walls. Roadways
with a single carriageway must provide sufficient off road parking to avoid
access routes being blocked to larger service vehicles and prevent parking on
pavements. 
c) Provide safe access to and from the road network, address any impacts on
road safety and the local road, rail and public transport network. Any impacts
identified through Transport Assessments/ Statements must be identified and
mitigated. This may include but would not be limited to, passing places, road
Page 78

Page 79

widening, junction improvements, bus stop infrastructure and drainage
infrastructure. A number of potential mitigation measures have been identified
in association with the development of sites and the most significant are shown
on the Proposals Map as TSP's. 
d) Provide covered and secure facilities for cycle parking at all flats/apartments,
retail, community, education, health and employment centres. 
e) Garages and parking provision must be designed to comply with Moray Council
parking specifications see Appendix 2. 
f)  The road layout must be designed to allow for the efficient mechanical
sweeping of all roadways and channels, paviors, turning areas and junctions.
The road layout must also be designed to enable safe working practices,
minimising reversing of service vehicles, with hammerheads minimised in
preference to turning areas such as road stubs or hatchets, and to provide
adequate space for the collection of waste and movement of waste collection
vehicles. 
g) The road and house layout in urban development should allow for communal
refuse collection points where the design does not allow for individual storage
within the curtilage and / or collections at kerbside. Communal collection points
may either be for the temporary storage of containers taken by the individual
householder or for the permanent storage of larger containers. The
requirements for a communal storage area are stated within the Council's
Kerbside Collection Policy, which will be a material consideration. 
h) Road signs should be minimised designed and placed at the back of footpaths
to reduce street clutter, avoid obstructing pedestrian movements and
safeguarding sightlines; 
i)  Within communal parking areas there will be a requirement for electric car
charging points. Parking spaces for car sharing must be provided where a need
is identified by the Transportation Manager. 
(iii) Water environment, pollution, contamination
a) Acceptable water and drainage provision must be made, including the use of
sustainable urban drainage systems (SUDS) for dealing with surface water
including temporary/ construction phase SUDS (see Policy EP12). 
b) New development should not be located in areas at flood risk or increase
vulnerability to flooding (see Policy EP12). Exceptions to this would only be
considered in specific circumstances, e.g. extension to an existing building or
change of use to an equal or less vulnerable use. Where this exception is
applied the proposed development must include resilience measures such as
raised floor levels and electrical sockets. 
c) Proposals must avoid major hazard sites and address any potential risk of
pollution including ground water contamination in accordance with recognised
pollution prevention and control measures. 
Page 79

Page 80

d) Proposals must protect and wherever practicable enhance water features
through for example naturalisation of watercourses by introducing a more
natural planform and removing redundant or unnecessary structures. 
e) Proposals must address and sufficiently mitigate any contaminated land issues. 
f)  Make acceptable arrangements for waste collection and management and
encourage recycling. 
g) Avoid sterilising significant workable reserves of minerals, prime agricultural
land or productive forestry. 
h)  Proposals must avoid areas at risk of coastal erosion and coastal change. 
DP5 BUSINESS & INDUSTRY
a) Development of employment land is supported to deliver the aims of the Moray
Economic Strategy.  A hierarchical approach will be taken when assessing proposals
for business and industrial uses. New and existing employment designations are set
out in Settlement Statements and their description identifies where these fall within
the policy hierarchy. 
Proposals must comply with Policy DP1, site development requirements within town
and village statements, and all other relevant policies within the Plan. Office
development that will attract significant numbers of people must comply with Policy
DP7 Retail/Town Centres. 
Efficient energy and waste innovations should be considered and integrated within
developments wherever possible. 
b) Business Parks 
Business parks will be kept predominantly for 'high-end' businesses such as those
related to life sciences and high technology uses.  These are defined as Class 4
(business) of the Town and Country Planning (Use Classes) (Scotland) Order 1997.
This applies to new proposals as well as redevelopment within established Business
Parks. 
Proposals for the development of new business parks must adhere to the key design
principles set out in town statements or Development Frameworks adopted by the
Council.   
c) Industrial Estates 
Industrial Estates will be primarily reserved for uses defined by Classes 4 (business),
5 (general) and 6 (storage and distribution) of the Town and Country Planning (Use
Classes) (Scotland) Order 1997. This applies to new proposals as well as
redevelopment within established Industrial Estates.  Industrial Estates could be
suitable sites for waste management facilities.   
d) Existing Business Areas 
Long established business uses will be protected from non-conforming uses (e.g.
housing).  The introduction or expansion of non-business uses (e.g. retail) will not be
permitted, except where the total redevelopment of the site is proposed.   
Page 80

Page 81

e) Other Uses 
Class 2 (business and financial), 3 (food and drink), 11 (assembly and leisure) and
activities which do not fall within a specific use class (sui generis), including waste
management facilities will be considered in relation to their suitability to the business
or industrial area concerned, their compatibility with neighbouring uses and the
supply of serviced employment land.  Retail uses will not be permitted unless they
are considered ancillary to the principal use (e.g. manufacture, wholesale).  For this
purpose, 'ancillary' is taken as being linked directly to the existing use of the unit and
comprising no more than 10% of the total floor area up to a total of 1,000 sq metres
(gross) or where a sequential approach in accordance with town centre first
principles has identified no other suitable sites and the proposal is in accordance
with all other relevant policies and site requirements are met. 
f) Areas of Mixed Use 
Proposals for a mix of uses where site specific opportunities are identified within
Industrial Estate designations in the Settlement Statement, will be considered
favourably where evidence is provided to the authority's satisfaction that the
proposed mix will enable the servicing of employment land and will not compromise
the supply of effective employment land.  A Development Framework that shows the
layout of the whole site, range of uses, landscaping, open space and site specific
design requirements must be provided. The minimum levels of industrial use
specified within designations must be achieved on the rest of the site. 
g) Rural Businesses and Farm Diversification 
Proposals for new business development and extensions to existing businesses in
rural locations including tourism and distillery operations will be supported where
there is a locational need for the site and the proposal is in accordance with all other
relevant policies. 
A high standard of design appropriate to the rural environment will be required and
proposals involving the rehabilitation of existing properties (e.g. farm steadings) to
provide business premises will be encouraged. 
Outright retail activities will be considered against policy DP7, and impacts on
established shopping areas, but ancillary retailing (e.g. farm shop) will generally be
acceptable. 
Farm diversification proposals and business proposals that will support the economic
viability of the farm business are supported where they meet the requirements of all
other relevant Local Development Plan policies. 
h) Inward Investment Sites 
The proposals map identifies a proposed inward investment site at Dallachy which is
safeguarded for a single user business proposal seeking a large (up to 40ha), rural
site. Additional inward investment sites may be identified during the lifetime of the
Plan. 
Proposals must comply with Policy DP1 and other relevant policies. 
EP2 BIODIVERSITY
All development proposals must, where possible, retain, protect and enhance features of
biological interest and provide for their appropriate management.  Development must
Page 81

Page 82

safeguard and where physically possible extend or enhance wildlife corridors and
green/blue networks and prevent fragmentation of existing habitats. 
Development should integrate measures to enhance biodiversity as part of multi-functional
spaces/ routes. 
Proposals for 4 or more housing units or 1000 m2 or more of commercial floorspace must
create new or, where appropriate, enhance natural habitats of ecological and amenity
value. 
Developers must demonstrate, through a Placemaking Statement where required by
Policy PP1 which incorporates a Biodiversity Plan, that they have included biodiversity
features in the design of the development. Habitat creation can be achieved by providing
links into existing green and blue networks, wildlife friendly features such as wildflower
verges and meadows, bird and bat boxes, amphibian friendly kerbing, wildlife crossing
points such as hedgehog highways and planting to encourage pollination, wildlife friendly
climbing plants, use of hedges rather than fences, incorporating biodiversity measures into
SUDS and retaining some standing or lying dead wood, allotments, orchards and
woodlands. 
Where development would result in loss of natural habitats of ecological amenity value,
compensatory habitat creation will be required where deemed appropriate. 
EP12 MANAGEMENT AND ENHANCEMENT OF THE WATER ENVIRONMENT
a) Flooding
New development will not be supported if it would be at significant risk of flooding
from any source or would materially increase the possibility of flooding elsewhere.
For development at or near coastal locations, this includes consideration of future
flooding that may be caused by sea level rise and/or coastal change eroding existing
natural defences in the medium and long term. 
Proposals for development in areas considered to be at risk from flooding will only be
permitted where a flood risk assessment to comply with the recommendations of
Scottish Planning Policy and to the satisfaction of Scottish Environment Protection
Agency and the Council is provided by the applicant. 
There are different levels of flood risk assessment dependent on the nature of the
flood risk. The level of assessment should be discussed with the Council prior to
submitting a planning application. 
Level 1 -  a flood statement with basic information with regard to flood risk.
Level 2 -  full flood risk assessment providing details of flood risk from all sources,
results of hydrological and hydraulic studies and any appropriate
proposed mitigation. 
Assessments must demonstrate that the development is not at risk of flooding and
would not increase the probability of flooding elsewhere.  Level 2 flood risk
assessments must be signed off by a competent professional.  The Flood Risk
Assessment and Drainage Impact Assessment for New Development Supplementary
Guidance provides further detail on the information required. 
Page 82

Page 83

Due to continuing changes in climatic patterns, the precautionary principle will apply
when reviewing any application for an area at risk from inundation by floodwater.
Proposed development in coastal areas must consider the impact of tidal events and
wave action when assessing potential flood risk. 
The following limitations on development will also be applied to take account of the
degree of flooding as defined in Scottish Planning Policy;
a) In areas of little to no risk (less than 0.1%), there will be no general constraint to
development.
b) Areas of low to medium risk (0.1% to 0.5%) will be considered suitable for most
development. A flood risk assessment may be required at the upper end of the
probability range i.e. (close to 0.5%) and for essential civil infrastructure and the
most vulnerable uses. Water resistant materials and construction may be
required. Areas within this risk category will generally not be suitable for civil
infrastructure. Where civil infrastructure must be located in these areas or is
being substantially extended, it should be designed to be capable of remaining
operational and accessible during flooding events.
c) Areas of medium to high risk (0.5% or above) may be suitable for:
• Residential, institutional, commercial and industrial development within
built up areas provided that flood protection measures to the appropriate
standard already exist and are maintained, are under construction, or are
a planned measure in a current flood management plan.
• Essential infrastructure within built up areas, designed and constructed to
remain operational during floods and not impede water flow.
• Some recreational, sport, amenity and nature conservation uses, provided
appropriate evacuation procedures are in place, and
• Employment related accommodation e.g. caretakers or operational staff. 
Areas within these risk categories will generally not be suitable for the following
uses and where an alternative/lower risk location is not available¬¬;
• Civil infrastructure and most vulnerable uses.
• Additional development in undeveloped and sparsely developed areas,
unless a location is essential for operational reasons e.g. for navigation
and water based recreation, agriculture, transport or utilities infrastructure
(which should be designed to be operational during floods and not impede
water flows).
• New caravan and camping sites 
Where development is permitted, measures to protect against or manage flood risk
will be required and any loss of flood storage capacity mitigated to achieve a neutral
or better outcome. Water resistant materials and construction must be used where
appropriate. Land raising and elevated buildings on structures such as stilts are
unlikely to be acceptable. 
b) Surface Water Drainage: Sustainable Urban Drainage Systems (SUDS)
Surface water from development must be dealt with in a sustainable manner that has
a neutral effect on flooding or which reduces the risk of flooding. The method of
dealing with surface water must also avoid pollution and promote habitat
enhancement and amenity. All sites must be drained by a sustainable drainage
system (SUDS) designed in line with current CIRIA guidance. Drainage systems
must contribute to enhancing existing "blue" and "green" networks while contributing
to place-making, biodiversity, recreational, flood risk and climate change objectives.
Page 83

Page 84

When considering the appropriate SUDS design for the development the most
sustainable methods, such as rainwater harvesting, green roofs, bio retention
systems, soakaways, and permeable pavements must be considered first.  If it is
necessary to include surface water attenuation as part of the drainage system, only
above ground attenuation solutions will be considered, unless this is not possible
due to site constraints.   
If below ground attenuation is proposed the developer must provide a robust
justification for this proposal.  Over development of a site or a justification on
economic grounds will not be acceptable.  When investigating appropriate SUDS
solutions developers must integrate the SUDS with allocated green space, green
networks and active travel routes to maximise amenity and biodiversity benefits. 
Specific arrangements must be made to avoid the issue of permanent SUDS
features becoming silted-up with run-off. Care must be taken to avoid the spreading
and/or introduction of invasive non-native species during the construction of all
SUDS features.  On completion of SUDS construction the developer must submit a
comprehensive Operation and Maintenance Manual.  The ongoing maintenance of
SUDS for all new development will be undertaken through a factoring agreement, the
details of which must be supplied to the Planning Authority.   
All developments of less than 3 houses or a non-householder extension under 100
square metres must provide a Drainage Statement.  A Drainage Assessment will be
required for all developments other than those identified above. 
c) Water Environment
Proposals, including associated construction works, must be designed to avoid
adverse impacts upon the water environment including Ground Water Dependent
Terrestrial Ecosystems and should seek opportunities for restoration and/or
enhancement, if appropriate. The Council will only approve proposals impacting on
water features where the applicant provides a report to the satisfaction of the Council
that demonstrates that any impact (including cumulative) on water quality, water
quantity, physical form (morphology), river hydrology, sediment transport and
erosion, coastal processes (where relevant) nature conservation (including protected
species), fisheries, recreational, landscape, amenity and economic and social impact
can be adequately mitigated. 
The report must consider existing and potential impacts up and downstream of the
development particularly in respect of potential flooding. The Council operates a
presumption against the culverting of watercourses and any unnecessary
engineering works in the water environment. 
A buffer strip of at least 6 metres between any new development and all water
features is required and should be proportional to the bank width and functional river
corridor (see table on page 96). This must achieve the minimum width within the
specified range as a standard, however, the actual required width within the range
should be calculated on a case by case basis by an appropriately qualified individual.
These must be designed to link with blue and green networks, including appropriate
native riparian vegetation and can contribute to open space requirements. 
Page 84

Page 85

Developers may be required to make improvements to the water environment as part
of the development. Where a Water Framework Directive (WFD)¬ water body
specific objective is within the development boundary, or in proximity, developers will
need to address this within the planning submission through assessment of potential
measures to address the objective and implementation, unless adequate justification
is provided. Where there is no WFD objective the applicant should still investigate
the potential for watercourse restoration along straightened sections or removal of
redundant structures and implement these measures where viable. 
Width to watercourse Width of buffer strip (either side)
(top of bank) 
Less than 1m 6m
1-5m 6-12m
5-15m 12-20m
15m+ 20m+ 
The Flood Risk Assessment and Drainage Impact Assessment for New Development
Supplementary Guidance provides further detail on the information required to
support proposals. 
EP13 FOUL DRAINAGE 
All development within or close to settlements (as defined in the Local Development Plan)
of more than 2,000 population must connect to the public sewerage system unless
connection  is not permitted due to lack of capacity. In such circumstances, temporary
provision of private sewerage systems may be allowed provided Scottish Water has
confirmed investment to address this constraint has been allocated within its investment
Programme and the following requirements have been met; 
• Systems must not have an adverse effect on the water environment
• Systems must be designed and built to a standard which will allow adoption by
Scottish Water
• Systems must be designed such that they can be easily connected to a public sewer
in the future. Typically this will mean providing a drainage line up to a likely point of
connection. 
All development within or close to settlements (as above) of less than 2,000 population will
require to connect to public sewerage except where a compelling case is made otherwise.
Factors to be considered in such a case will include size of the proposed development,
whether the development would jeopardise delivery of public sewerage infrastructure and
existing drainage problems within the area. 
Where a compelling case is made, a private system may be acceptable provided it does
not pose or add a risk of detrimental effects, including cumulative, to the natural and built
environment, surrounding uses or amenity of the general area. 
Where a private system is deemed to be acceptable, within settlements as above or small
scale development in the countryside, a discharge to land, either full soakaway or raised
mound soakaway, compatible with Technical Handbooks (which sets out guidance on how
proposals may meet the Building  Regulations) must be explored prior to considering a
discharge to surface waters. 
Page 85

Page 86

EP14 POLLUTION, CONTAMINATION & HAZARDS
a)  Pollution
Development proposals which may cause significant air, water, soil, light or noise
pollution or exacerbate existing issues must be accompanied by a detailed
assessment report on the levels, character and transmission of the potential pollution
with measures to mitigate impacts. Where significant or unacceptable impacts
cannot be mitigated, proposals will be refused.   
b) Contamination
Development proposals on potentially contaminated land will be approved where
they comply with other relevant policies and; 
i) The applicant can demonstrate through site investigations and risk assessment,
that the site is in a condition suitable for the proposed development and is not
causing significant pollution of the environment; and
ii) Where necessary, effective remediation measures are agreed to ensure the
site is made suitable for the new use and to ensure appropriate disposal and/ or
treatment of any hazardous material. 
c) Hazardous sites
Development proposals must avoid and not impact upon hazardous sites or result in
public safety concerns due to proximity or use in the vicinity of hazardous sites. 
EP8 HISTORIC ENVIRONMENT
a) Scheduled Monuments and Unscheduled Archaeological Sites of Potential
National Importance.
Where a proposed development potentially has a direct impact on a Scheduled
Monument, Scheduled Monument Consent (SMC) is required, in addition to any
other necessary consents.  Historic Environment Scotland manage these consents. 
Development proposals will be refused where they adversely affect the integrity of
the setting of Scheduled Monuments and unscheduled archaeological sites of
potential national importance unless the developer proves that any significant
adverse effects are clearly outweighed by exceptional circumstances, including
social or economic benefits of national importance. 
b) Local Designations
Development proposals which adversely affect sites of local archaeological
importance or the integrity of their settings will be refused unless; 
• Local public benefits clearly outweigh the archaeological value of the site, and
• Consideration has been given to alternative sites for the development and
preservation in situ is not possible.
• Where possible any adverse effects can be satisfactorily mitigated at the
developer's expense. 
The Council will consult Historic Environment Scotland and the Regional
Archaeologist on development proposals which may affect Scheduled Monuments,
nationally important archaeological sites and locally important archaeological sites.
Page 86

Page 87

WARD 01_17 
22/01544/APP
27th October 2022
Change of use from agricultural use to temporary
outdoor nursery to be used March to October 2023
during the refurbishment and extension of the nursery at
Aberlour Primary School at New Cemetery Aberlour
Cemetery High Street Aberlour
for Moray Council 
Comments: 
• Advertised as a departure from Moray Local Development Plan 2020.
• A site visit will have been carried out.
• The application is being made by the Planning Authority and relates to Council
land.
• This application seeks consent for a temporary outdoor nursery to be sited on
Council owned land in the village of Aberlour. It is required whilst the existing
nursery at Aberlour Primary School is refurbished which is due to commence in
2023. 
• The application is being considered by Committee as it raises matters of wider
community interest. 
Procedure: 
 None required. 
Recommendation 
Grant Planning Permission - subject to the following: 
Conditions/Reasons 
1. The development to which this permission relates must be begun not later than
the expiration of 3 years beginning with the date on which the permission is
granted. 
Reason: The time limit condition is imposed in order to comply with the
requirements of section 58 of the Town and Country Planning (Scotland) Act 1997
as amended. 
2. No development shall commence on site until a Construction Traffic Management
Plan has been submitted to and approved in writing by the Council, as Planning
Authority in consultation with the Roads Authority. The Construction Traffic
Item 7
Page 87

Page 88

Management Plan shall include the following information:
a)   Construction programme;
b)   Details for the removal of any excavated materials from site including the
estimated volume and destination(s) for disposal.
c)   Full details of any temporary construction access or the construction traffic
route between the site and the A95;
d)   Traffic management measures to be put in place during works including any
specific instructions to drivers; and
e)   Details of any temporary construction compounds or parking provision.
f)   The Plan shall also cover the construction phase when the structures are
removed and the ground reinstated.
Thereafter, the development shall be implemented in accordance with the
approved details. 
Reason: To ensure an acceptable form of development in terms of the
arrangements to manage traffic during construction works at the site. 
3. The development hereby approved shall not be brought into operation until the
1.8m high close boarded fence has been erected in accordance with the approved
plans. The fence shall be retained thereafter in accordance with the approved
plans throughout the lifetime of the development. 
Reason: To ensure that there is no adverse impact upon the privacy and amenity
of neighbouring properties/uses. 
4. The development hereby approved shall not be brought into operation until the
emergency pedestrian access gate on the east side of the site has been provided
in accordance with the approved plans. The gate shall be retained thereafter in
accordance with the approved plans throughout the lifetime of the development.
For the avoidance of doubt, the fence shall be kept unlocked at all times when the
nursery is in operation. 
Reason: To ensure that there is adequate access/egress provision for
pedestrians in any flood events. 
5. The development hereby approved shall be operated in accordance with the
approved Operational Plan and Statement on Mitigation unless otherwise agreed
in writing with the Council as Planning Authority. 
Reason: To ensure that there is no adverse impact upon the privacy and amenity
of neighbouring properties/uses. 
6. The development hereby approved shall be constructed and finished in
accordance with the approved plans and drawings unless otherwise agreed in
writing with the Council as Planning Authority. 
Reason: To ensure the development is appropriate to the surrounding area and
integrated into the landscape.
Page 88

Page 89

7. The development hereby approved shall be used for a temporary period only
between 1 March 2023 and 31 October 2023 unless otherwise agreed in writing
with the Council as Planning Authority. All structures, fencing,
hardstanding/parking area and all other development as shown on the approved
plans shall thereafter be removed within 3 months of the expiry of this consent
(i.e. by 31 January 2024) or within 3 months of the cessation of the operations
whichever is the sooner and the land restored to grassland. 
Reason: As the development has been assessed in relation to a temporary use of
the site in terms of amenity, visual and flooding land use planning considerations. 
Reason(s) for Decision
The Council’s reason(s) for making this decision are:- 
The proposal accords with the relevant provisions of the Moray Development Plan 2020
and there are no material considerations that indicate otherwise.   
List of Informatives: 
THE DEVELOPMENT MANAGEMENT & BUILDING STANDARDS MANAGER has
commented that:- 
Please contact the Building Standards Duty Officer in order to ascertain whether a
Building Warrant will be required for these proposals between 2pm and 4pm or
telephone on 03001234561.  No appointment is necessary.  Alternatively e-mail
buildingstandards@moray.gov.uk 
The developer should note that Scottish Water have advised that they have live
infrastructure (combined sewers, and water mains) in proximity of development
area so developer must identify any potential conflicts with them – more detail in
their consultation response.   
The SCOTTISH ENVIRONMENT PROTECTION AGENCY has commented that:- 
In the event that any application is lodged seeking to extend the period of use of
the nursery hereby approved, such an application must incorporate a detailed
Flood Risk Assessment. 
As the permission sought is temporary and reversible in nature, it would not
warrant a recognised increase in land use vulnerability on a permanent basis and
any future development proposed for the site must be treated as a potential
increase in flood risk. The principle of development as a ‘Most Vulnerable’ land
use has not therefore been established at the site. 
Page 89

Page 90

LIST OF PLANS AND DRAWINGS SHOWING THE DEVELOPMENT
Reference No. Version No. Title/Description
61680_SK-102  Site sections elevations
61680 TON SK 001  Site location plan
61680-SK-100 B Site and layout plan 
Page 90

Page 91

Plans, drawings and other material submitted to the local authority
are protected by the Copyright, Designs and Patents Act 1988
(section 47). You may only use material which is downloaded and/
or printed for consultation purposes, to compare current
applications with previous schemes and to check whether
developments have been completed in accordance with approved
plans.
Further copies must not be made without the prior permission of
the copyright owner.
Maps shown in the Planning Committee Report can only be used
for the purposes of the Planning Committee. Any other use risks
infringing Crown Copyright and may lead to prosecution or civil
proceedings. Maps produced within this Planning Committee
Report can only be reproduced with the express permission of the
Moray Council and other Copyright holders. This permission must
be granted in advance.
PLANNING APPLICATION
COMMITTEE SITE PLAN
Site Address:
New Cemetery Aberlour Cemetery
High Street Aberlour
Planning Application Ref Number: 
22/01544/APP 
Location Plan
Applicant Name: 
Moray Council
Page 91

Page 92

Site Location
Page 92

Page 93

Site and layout plan
16/01664/APP
Page 93

Page 94

Site sectional elevations
16/01664/APP
Page 94

Page 95

16/
Page 95

Page 96

Photo 1 looking to High Street
Page 96

Page 97

Photo 2 looking to Kismet
Page 97

Page 98

Photo 3 looking over site from bridge
Page 98

Page 99

Photo 4 looking to High Street & from by Speyside Way
Page 99

Page 100

Photo 5 looking to site from cemetery car park
Page 100

Page 101

Photo 6 looking to site from access road
Page 101

Page 102

Photo 7 from houses
Page 102

Page 103

PLANNING APPLICATION: 22/01544/APP 
In the event that a recommendation on this planning application is overturned the
Committee is reminded of the advice contained on the front page of the agenda for
Reports on Applications 
1. THE PROPOSAL 
This application seeks full planning permission for the change of use of a small
field to form a temporary outdoor nursery during the refurbishment and
extension of the existing nursery at Aberlour Primary School.  The temporary
nursery will be required from March to October 2023 with use of the facilities
only taking place during term times. 
The key features of the proposals are as follows:
   Parking area with permeable finish to be formed adjacent to road leading
to Alice Littler car parking area with access to site for children taken
through access point in fencing to be erected.
   4 parking spaces plus cycle and powered two wheeler provision to be
made.
   A 1.8 metre high close boarded larch fence is proposed around the site,
along the entire site frontage to the road (set back behind the parking
area) and then set some 10 metres northwards into the site from the
cemetery to the south and around 8 metres at points from the housing to
the east to create a “buffer zone”. 
   Siting of temporary structures including two yurts (roof height 3.34
metres), wigwam/tepee, polytunnel, container, two small pitched roof
wooden sheds and tarpaulin covered areas supported on struts/poles. 
Two hide/shelters are proposed along with rain gardens, fire pit and paths.
   The closest of these structures to the housing to the east will be around
30 metres from the mutual site boundary with the facilities to be located in
the western part of the site.
   Silenced mini generator or blown air heater will be used for heating - these
will be enclosed in timber housing.
   All ground excavated to create the areas for the facilities will be stored on
site in bunding of maximum height 1.2 metres and reused in site
reinstatement.  Minimal excavation of around 150 mm is anticipated. 
   It is not proposed to connect to public water or drainage services, but
rather to have an off-grid facility with no new buried servicing. Siting of
three portaloos is proposed, bottled water for hand washing serviced by
the nearby station tea room with facilities for handwashing provided in the
messy play sinks in the tarpaulin covered area and in the polytunnel
similar to other outdoor nurseries. This polytunnel will have a hard surface
floor. 
   Washing of equipment and utensils is to be dealt with by the existing
catering assistant at Aberlour Primary school, with back up provision
being an agreement to access facilities within the former railway station
building. 
Page 103

Page 104

   Following discussion with SEPA an emergency pedestrian access gate is
proposed in the south east corner of the site leading into the adjacent
cemetery area with access then onto the High Street.
   Opening hours anticipated to be term time only from 8:50 am to 2:50pm. 
As noted above these new facilities are required in order to accommodate the
children attending the existing Council operated nursery at the primary school
whilst the nursery is being refurbished to meet current standards and to ensure
continued nursery provision within Aberlour. It is understood this involves
around 20 children. The applicants considered a range of alternative sites in the
area with the application site chosen for reasons of availability/ownership,
proximity to school so avoiding additional transport issues for parents, central
location in village and access to nearby facilities for staff breaks and hot
running water. 
Supporting information has been provided including: 
   Operational statement outlining the measures to be taken to minimise
disturbance during funeral services including engaging with churches,
funeral parlours etc. regarding services and making plans to either take
the children inside the yurt at such times for quiet activities or in good
weather to take them to a suitable outdoor venue such as the adjacent
Alice Littler park. A buffer zone is also proposed around the site with fence
erected to separate the activities from the cemetery. 
   Statement of mitigation measures including timber fence set into site to
create buffer zone from sensitive users in terms of privacy and noise
reduction, use of permeable surfaces on areas which are exposed to
rainfall, with storm water run-off to be collected in water butts and reused. 
Additional traffic will be generated as this is a temporary relocation of an
existing facility with most users/workers able to continue their existing
pattern of travel due to the proximity to the existing nursery. 
2. THE SITE 
   Small field within the settlement of Aberlour, directly adjacent to Aberlour
cemetery. 
   Currently grassland of around 0.37 hectares with a 35 metre site frontage. 
   Fronts road leading to Alice Littler Park with Speyside Way running
westward along the south western part of the site frontage.
   The site sits within the ENV9 designation ‘Cemeteries and proposed
extensions’ within the Aberlour Settlement Statement.
   To north west of the site is the car park serving the Alice Littler Park and
recycling centre with the park beyond this leading to the River Spey.
   A detached residential property at Kismet lies to the north in its own
gardens with block wall and vegetation along this boundary.
   Residential properties lie to the rear (east) of the site at 132 A High Street
with stone boundary wall along this boundary. Further south east along
this rear boundary lies the rear gardens of 134 -136 High Street with the
former hall (now dental practice) further south east again along this
boundary.
   Aberlour Cemetery lies to the south with a stone wall along this boundary. 
Page 104

Page 105

3. HISTORY 
There is no history on the site itself. 
Relevant planning history is: 
20/01374/APP - Alter and extend accommodation provide temporary classroom
accommodation and upgrade the nursery garden at Aberlour Primary School
Nursery - consent granted for this and accompanying Listed Building
application. This site lies on Mary Avenue to the south. 
4. POLICY - SEE APPENDIX 
5. ADVERTISEMENTS 
5.1 The proposal has been advertised in the local press as a potential departure
from the Development Plan and for neighbour notification purposes. 
6. CONSULTATIONS 
Transportation Manager: No objections subject to condition requiring a
Construction Traffic Management Plan being agreed. The Transportation
Manager is satisfied with the access arrangements to the location, subject to
conditions recommended. 
Environmental Health: On receipt of further information on toilet and hand
washing facilities have now confirmed they are satisfied with the proposed
arrangements. 
Flood Risk Management: No objections. 
Estates: No objections. 
Access Manager: No objections. 
Archaeology Service: No objections. 
Contaminated Land: No objections. 
SEPA: Initially advised that information submitted was insufficient to determine
the flooding impacts given the location of the site within an area at risk of
flooding from the River Spey. Further information was required on alternative
sites considered, emergency flood access/egress for pedestrians and
consideration of siting of infrastructure to avoid flood risk. On receipt and
consideration of this further information SEPA has now advised that given the
temporary nature of the proposal, it would be acceptable and would not
constitute a ‘most vulnerable’ use. If it were to become more permanent, then a
detailed Flood Risk Assessment would be required. 
Page 105

Page 106

Scottish Water: No objections. Note that they have live infrastructure
(combined sewers, and water mains) in proximity to the development area so
developer must identify any potential conflicts with these services. 
7. OBJECTIONS-REPRESENTATIONS 
NOTE: Following the determination of this application, name and address
details will be/have been removed (i.e. redacted) in accordance with the
General Data Protection Regulations (paragraph 3 of Minute, Planning &
Regulatory Services Committee 16 September 2014). 
A representation has been received from the local Community Council who
have noted that whilst they support the creation of outdoor learning nurseries
they object to the proposed development which they consider to be on an
unsuitable site for the following reasons, even for a 6 month period. 
Issue: Access to and from the site is unsuitable. Footpath past the old
Packhorse Bridge onto the Speyside Way is not suitable for buggies, no
footpath along Elchies Road, no footpath from the Church, tea rooms and Mash
Tun. Generation of additional traffic in a busy location where roads serve the
park and recycling centre. Roads are narrow in places with no separation of
pedestrians and vehicles, and no safe walking route for people with young
children.
Comment (PO): The relevant consultee (Transportation Manager) has no
objections to the proposals. In relation to the points raised by the objector the
Transportation Manager has highlighted that the site is accessed from the
existing network which is in constant use by pedestrians, cyclists and vehicles
accessing, amongst other things, the Alice Littler Park, recycling facilities,
Speyside Way, Old Station and Mash Tun. The park area and square are
notably busy with school children during breaks and after school. The activity
and layout of the access route to the carpark encourage a change in driver
behaviour which promotes reduced driving speeds and urges a more
cautionary driving style. 
Vehicle drivers already expect to see non-vehicular activity sharing access in
the area and an increased presence of non-vehicular activity would further
diminish any sense of vehicular dominance and reinforce positive behaviours.
Children travelling to the nursery would be expected to be accompanied by an
adult at all times which reduces the risks compared with an unaccompanied
minor. Whilst it is accepted that there is likely to be an increase in traffic volume
associated with the nursery, the use is identified as temporary and the nursery
could take proactive steps to promote walking and cycling to the site which
would be supported. 
Issue: Site is too close to fast flowing River Spey with the Alice Littler Park and
Speyside Way being flooded in 2009, 2014 and 2017 between March and
October.  
Comment (PO): The site lies partially within an area identified by SEPA’s flood
maps as being at risk of flooding. Relevant technical consultees were therefore
consulted. The Flood Risk Management Team has no objections to the
Page 106

Page 107

proposals. Following submission of further information as noted in the
consultation section of this report SEPA has advised given the temporary
nature of the site, the proposed pedestrian gate leading east away from the
site, SEPA raises no objection to the application. The wider locality, susceptible
to flooding is already used for recreation/play. 
Issue: Concerns regarding large numbers of people passing the site – queries
whether CCTV will be installed.
Comment (PO): The site will be enclosed by a 1.8 metre high fence which will
safeguard the privacy of the users of the facility. The installation of CCTV is a
matter for the applicants to consider and not a land use planning consideration.
There is no policy requirement for surveillance.   
Issue: Environmental health concerns relating to lack of running water for
children to wash their hands, no changing or washing facilities for children who
use nappies/incontinence pads with toilets at Tea Room not suitable for this as
well as leaving the nursery understaffed if staff need to take children there.
Comment (PO):  The Environmental Health Section has been consulted and
sought further information on washing arrangements as set out in the
consultations section. The section have confirmed that they are satisfied about
the use of bottled water, and other arrangements for hygiene. 
The proposed temporary development will be operating “off grid” which is not
unusual with outdoor nurseries. It is understood that the Care Inspectorate
have been involved with the development of this facility and are supportive of
the outdoor decant plan which has been planned in accordance with Care
Inspectorate and Scottish Government guidance on outdoor play. In any event
the development will be regulated by the Care Inspectorate and this will cover
staffing and welfare issues which are not the remit of the Planning Authority. 
Issue: Concern regarding conflict with adjacent cemetery use. Note the
intention to consult with the Church regarding funeral times – highlight the
Church does not carry out all funeral/burials in the cemetery and other bodies
will need to be consulted. Also highlight that people visit graves other than at
funerals and this needs to be considered noting it is difficult to keep a large
group of children quiet.
Comment (PO): This point has discussed with the Open Space Manager who
has provided advice on how best to liaise with relevant funeral providers. This
has been included in an operational plan submitted by the applicants.  The
Open Space Manager has further commented that points of contact should be
established with the Registration Service who manage funeral bookings and the
Open Space Cemetery Team Leader who manages and oversees funerals at
the cemetery.  Users of the site would however be mindful not just of funerals
but also of bereaved families/visitors who routinely visit this well-attended
cemetery. 
This plan explains how the applicants will liaise with relevant bodies and ensure
that the children are either taken off site for outdoor play or have a quiet time in
the yurts at times of funeral services. Cognisance will also be taken of how to
ensure there is no significant conflicts with bereaved persons visiting the
cemetery with the buffer zone of around 10 metres to be provided from the
cemetery boundary with the facilities set behind a screen fence to reduce
Page 107

Page 108

impacts. Furthermore the proposed nursery use will have limited opening hours
and will not involve weekends whereby potential conflicts may be minimised. 
It is also noted that there is a recreational park and the Speyside Way already
close by the cemetery whereby there is a degree of recreational use and
associated disturbance in the area at present. Cemeteries within settlements
are typically subject to background noise/activity even when interments are
under way.   
Issue: Related to the above point of taking children off site at times of funerals,
concern is raised regarding ratio of staff to pupils for taking such young children
off the site in a location so close to the fastest flowing river in Scotland. 
Comment (PO): The level of staffing of a nursery is not a land use planning
consideration. It will however be considered by the relevant authority (Care
Inspectorate) who will ensure that children’s’ safety and welfare is fully taken
into account. The site is proposed to be enclosed such that children would not
be able to walk toward the river. A public park and play areas are already within
proximity of the River Spey, where no segregation exists. 
8. OBSERVATIONS 
8.1 Following consideration of the revised draft National Planning Framework 4
which was laid before parliament on 8 November 2022, the draft (yet to be
formally adopted) is to be given no weight in the consideration of planning
applications. Section 25 of the 1997 Act as amended requires applications to
be determined in accordance with the development plan i.e. the adopted Moray
Local Development Plan 2020 (MLDP) unless material considerations indicate
otherwise. The main planning issues are considered below. 
8.2 Background 
As noted previously this application is for a temporary outdoor nursery to be
sited on Council owned land in the village of Aberlour, required whilst the
existing nursery at Aberlour Primary School is refurbished. These works are
due to commence in 2023. 
8.3 Principle (Policy EP5) 
The application site is part of an area designated in the Local Development
Plan as “ENV 9 - Cemeteries and proposed extensions at Aberlour Cemetery”
The supporting text explains that open space that contributes to the
environmental amenity of Aberlour will be safeguarded from development that
is not related to their current use as set out in the table which explains the uses.
The Moray Council Open Space Strategy Supplementary Guidance provides
more detail on the description of such spaces and describes the application site
as amenity ground of poor quality as it lacks any clear function and is not
readily accessible. However it notes that it is reserved for a cemetery extension
with stringent requirements in place by SEPA which may compromise this
aspiration. Development potential is noted as being for cemetery extension or a
short term temporary use. 
8.3.1 In such ENV designations Policy EP5: Open Space applies. This explains that
development which would result in a change of use of a site identified as an
Page 108

Page 109

ENV designation in a settlement statement to anything other than open space
will be refused, the only exceptions being where the proposal is for essential
community infrastructure required to deliver the key objectives of the Council
and its community planning partners (excluding housing) or for a site specific
opportunity identified within the settlement statement. 
8.3.2 If such an exception applies then the development requires to:
• Be sited and designed to minimise adverse impacts on the principal
function of the space and the key qualities and features identified in the
Moray Open Space Strategy Supplementary Guidance. 
• Demonstrate that there is a clear excess of the type of ENV and the loss
of the open space will not negatively impact upon the quality, accessibility
and quantity of open space provision and does not fragment green
networks (with reference to the Moray Open Space Strategy
Supplementary Guidance, green network mapping and for ENV4 Sports
Area in consultation with SportScotland) or replacement open space
provision of equivalent function, quality and accessibility is made. 
8.3.3 The temporary use of unused or underused land as green infrastructure is
encouraged, this will not prevent any future development potential which has
been identified from being realised. 
8.3.4 The justification for Policy EP5 explains that open space is important for many
reasons including supporting healthy and active lifestyles as well as providing
spaces to relax and unwind supporting mental health. The Open Space
Strategy Supplementary Guidance explains that the designation of sites as
ENV seeks to protect open space from inappropriate development 
8.3.5 In this particular case the site is not used as open space, and as noted in the
Open Space Strategy Supplementary Guidance lacks any clear function, with
potential for short term temporary use. The application site is reserved for a
cemetery extension which is the main purpose of its designation rather than as
public open space. Indeed there is ample and attractive public open space in
close proximity at the popular Alice Littler Park.  The proposed development is
for a temporary use which is in line with the description of the site in the Open
Space Strategy Supplementary Guidance. 
8.3.6 Aside from these factors, in terms of the policy background of Policy EP5 Open
Space which presumes against the change of use of land covered by ENV
designations, the proposed development is considered to fall into the exception
category because it is for a temporary nursery required to educate children
whilst the existing nursery is being refurbished.  This is considered to be
essential community infrastructure required to deliver the key objectives of the
Council and its community planning partners given that a priority of the
Corporate Plan is to provide a sustainable education service aiming for
excellence.   
8.3.7 Policy EP5 also requires such exceptions to be sited to and designed to
minimise any adverse impacts on the principle function of the space and to
demonstrate that there is a clear excess of this type of ENV and that it does not
impact upon the quality of open space provision 
Page 109

Page 110

8.3.8 The detail of the design and siting will be considered later in this report but in
more general terms, as noted in the Open Space Strategy Supplementary
Guidance, the application site lacks any clear function. In essence it is
designated as ENV in order to reserve it for the cemetery expansion with ample
open space provision in the immediate area.  The temporary use proposed
does not prejudice its future use for the cemetery extension, nor does it impact
upon the quality of open space provision in Aberlour. 
8.3.9 In these overall circumstances the proposed development is considered in
principle to comply with Policy EP5. 
8.4 Siting, Amenity and Design (PP1, EP3 and DP1) 
Policy PP1 Placemaking seeks to ensure that new development is designed to
create successful healthy places that improve people’s wellbeing, safeguard
the environment and support economic development, promote character and
identity and biodiversity.  Policy DP1: Development Principles sets out the need
for the scale, density and character of new development to be appropriate to
the surrounding area, integrated into the surrounding landscape with no
adverse impacts upon neighbouring properties in terms of privacy, daylight or
overbearing loss of amenity 
8.4.1 In this regard in general terms the development is well located within the
designated settlement of Aberlour, close to key community amenities such as
the Speyside Way, Alice Littler Park, recycling centre and cafes. It is located
within ready walking distance of the original nursery location with proximity to
the Alice Littler park and Speyside Way meaning that the users of the nursery
will be able to benefit from the potential outdoor education opportunities nearby,
with no conflicts of use arising. 
8.4.2 The application site is effectively a gap site whereby development here has the
potential to fit into the wider streetscape. Existing townscape features such as
stone boundary walls will remain unchanged and given the short term nature of
the proposed development there will be no particular landscape or townscape
impacts arising. 
8.4.3 This proposed temporary development involves a collection of structures which
are visually tied together by the use of timber on sheds, tarpaulin supports etc.
and is considered to be appropriate for the children’s educational use proposed
here, helping to create a visually interesting environment. The proposed
development will be screened by a screen fence which will afford privacy and
security to the users, with its timber design being appropriate here.  This will
also help protect the privacy and amenity of adjacent residential properties
together with the proposed buffer zone. 
8.4.4 In terms of amenity issues and neighbours, the proposed site is also directly
adjacent to a cemetery which is still used for burials and is well attended in
terms of visits by the bereaved to gravesides. This is therefore a sensitive land
use in terms of the holding of funeral services and also in terms of visitors to
the cemetery, when a peaceful setting is important. As outlined earlier in the
representations section the applicants have provided an operational plan to
explain how any potential conflicts may be handled.  This explains how the
applicants will liaise with relevant bodies and ensure that the children are either
Page 110

Page 111

taken off site for outdoor play or have a quiet time in the yurts at times of
funeral services. Cognisance will also be taken of how to ensure there is no
significant conflicts with bereaved persons visiting the cemetery. The buffer
zone of around 10 metres to be provided at the boundary with the cemetery,
with the facilities set behind the proposed screen fence, should help to reduce
impacts. Furthermore the proposed nursery use will have limited opening hours
and will not involve weekends whereby potential conflicts may be minimised
over the 6 month period of the development. For clarity the operational plan is
sought in this instance to ensure the site generally operates as described and
to ensure mitigation for neighbouring amenity is secured, but the detailed
operational requirements and on-site safety considerations are overseen by the
Care Inspectorate and under other legislation. 
8.4.5 In these overall circumstances the development is considered to comply with
policy with no significant adverse impacts on the surrounding environment and
neighbouring uses. 
8.4.6 Finally in terms of design and siting issues, the site is also located within the
Spey Valley Special Landscape Area where Policy EP3 on Special Landscape
Areas and Landscape Character applies. This policy seeks to ensure that
development does not prejudice the special qualities, adopts the highest
standards of design and within designated settlements conforms to relevant
policies and reflects the traditional settlement character in terms of siting and
design. The proposed development for a temporary outdoor nursery for 6
months is not considered to conflict with this policy. 
8.5 Environmental Impacts (DP1 and EP2)
Policy DP1: Development Principles also sets out that development should
conserve and enhance the natural environment as does Policy EP2 Biodiversity
which aims to deliver biodiversity enhancements 
8.5.1 There is no loss of any particular habitats arising from this development which
involves rough grazing land. During the operation of the proposals there is
some opportunity to deliver some habitat enhancements through the proposed
rain gardens and other educational activities which may be delivered here. The
proposal is therefore considered to comply with policy. 
8.6 Access and Servicing (DP1, PP3, EP12 and EP13)
Policy PP3 Infrastructure and Services sets out how new development should
be coordinated with infrastructure to ensure that places function properly and
are adequately serviced. Policy DP1 Development Principles also sets out the
need for appropriate servicing and access. 
8.6.1 Proposed access, vehicular and pedestrian, will be off the existing network
servicing the Alice Littler park and adjacent facilities with some parking
(including cycle provision) provided on site.  As noted in representations section
earlier this existing network is in constant use by pedestrians, cyclists and
vehicles accessing amongst other things, the Alice Little Park, recycling
facilities, Speyside Way, Old Station and Mash Tun. The park area and square
are notably busy with school children during breaks and after school. The
activity and layout of the access route to the carpark encourage a change in
driver behaviour which promotes reduced driving speeds and urges a more
Page 111

Page 112

cautionary driving style. Vehicle drivers already expect to see non-vehicular
activity sharing access in the area and an increased presence of non-vehicular
activity would further diminish any sense of vehicular dominance and reinforce
positive behaviours. Children travelling to nursery would be expected to be
accompanied by an adult at all times which reduces the risks compared with an
unaccompanied minor. Whilst it is accepted that there is likely to be an increase
in traffic volume associated with the nursery, the use is identified as temporary
and the nursery could take proactive steps to promote walking and cycling to
the site which would be supported. 
8.6.2 In these circumstances the technical consultee (Transportation Team) has no
objections subject to appropriate planning conditions being attached with
regard to agreement on a Construction Traffic Management Plan to ensure no
conflicts with other users as the construction stage.   
8.6.3 Policy DP1 also requires that acceptable water and drainage provision is made
including the use of sustainable urban drainage systems (SuDS) for the
disposal of surface water. This is expanded upon in Policy EP12 Management
and Enhancement of the Water Environment and Policy EP13 Foul Drainage.
In this case water and drainage is off grid and the technical consultee (Flood
Risk Management Team) has no objection to the proposed development nor
has Scottish Water who have highlighted that the applicant will require to
contact them regarding any assets they may have in the vicinity. 
8.6.4 In these circumstances the development is capable of being satisfactorily
serviced and is considered to comply with policy. 
8.7 Flooding (EP12)
Policy EP12 Management and Enhancement of the Water Environment sets
out that development will not be supported if at significant risk of flooding from
any source or would materially increase the likelihood of flooding elsewhere. In
this case part of the application site lies within an area identified as being at risk
of flooding from the River Spey on SEPA’s flood maps with SEPA holding
records of flooding in the area from the Spey including the existing car park and
Speyside Way at the front of the site. Nurseries are classified as a most
vulnerable use in terms of SEPA’s Land Use Vulnerability Guidance. 
Accordingly SEPA required further information on alternative sites considered,
emergency flood access/egress for pedestrians and consideration of siting of
infrastructure to avoid flood risk in order to fully consider flood risk here. SEPA
also advised that provided that this is justifiably the only suitable site and that
there is a provision of safe access and egress away from the flood plain and
development within the area thought to be at risk of flooding has been
minimised as much as possible, they may be able to remove their objection
(subject to conditions) on flood risk grounds. As this is a temporary
development, the risk of exposure to flooding is lower than it would be over a
longer period of time and the level of flood risk assessment requested is only
appropriate for a temporary development. SEPA do not consider the long-term
risk of flooding to the site to have been adequately assessed and any
application for permanent development must be supported by a more detailed
flood risk assessment and clearly avoid areas at risk of flooding. 
Page 112

Page 113

8.7.1 However, given the temporary nature of the use, and with the presence of
pedestrian routes away from the source of flooding via a gate to the east side of
the site, they do not consider that the temporary use is unacceptable. Moray
Council’s own Flood Risk Management Team also raise no objection to the
proposed temporary use. Specifically in relation to policy EP12, given the
temporary, reversible nature of the use proposed and the fact it would not
contribute to flooding itself it is not considered to conflict with policy. 
8.8 Cultural issues (EP8)
Policy EP8 Historic Environments seeks to ensure that there is no adverse
effect on sites of local archaeological importance or the integrity of their
settings. The application site is part of a wider area identified on the Historic
Environment Record as the standing structure of Charlestown of Aberlour
founded in 1812 by Charles Grant, Laird of Elchies, although an earlier
settlement existed in this location. The Archaeology Service was therefore
consulted and has no objection to the proposals. 
8.8.1 To the west beyond the newer part of the cemetery is the category B listed
Aberlour Burial ground, remains of the former parish church of St Drostan and
the Macpherson Grant mausoleum. These historic assets are not impacted
upon by the proposed development. 
8.8.2 The development is therefore considered to comply with policy. 
Conclusion
The proposed development for a temporary outdoor nursery required to
facilitate the refurbishment of the existing nursery at Aberlour Primary School is
considered to comply with Local Development Plan policies subject to
appropriate planning conditions being attached relating to time periods,
reinstatement, construction traffic management, operational matters and
emergency egress/access in order to ensure that any impacts on the
surrounding area are minimised and that satisfactory provision is made in the
event of flood events. 
Approval is therefore recommended on this basis. 
REASON(S) FOR DECISION
The Council’s reason(s) for making this decision are: - 
The proposal accords with the relevant provisions of the Moray Development
Plan 2020 and there are no material considerations that indicate otherwise.   
Author/Contact
Officer:
Katherine Donnachie      
Planning Officer
Ext:  01343 563101 
Beverly Smith
Development Management & Building Standards Manager
Page 113

Page 114

Page 114

Page 115

APPENDIX 
POLICY 
Adopted Moray Local Development Plan 2020 
ENV9 Cemeteries and proposed extensions 
Aberlour Cemetery and Aberlour Cemetery Extension (AB/OS/015) 
PP1 PLACEMAKING 
a) Development must be designed to create successful, healthy places that support
good physical and mental health, help reduce health inequalities, improve people's
wellbeing, safeguard the environment and support economic development.   
b) A Placemaking Statement is required for residential developments of 10 units and
above to be submitted with the planning application to articulate how the
development proposal addresses the requirements of policy PP1 Placemaking and
other relevant LDP policies and guidance.  The Placemaking Statement must include
sufficient information for the council to carry out a Quality Audit.  Where considered
appropriate by the council, taking account of the nature and scale of the proposed
development and of the site circumstances, this shall include a landscaping plan, a
topographical survey, slope analysis, site sections, 3D visualisations, a Street
Engineering Review and a Biodiversity Plan.  The Placemaking Statement must
demonstrate how the development promotes opportunities for healthy living and
working. The landscape plan must set out details of species type, size, timescales for
planting and maintenance. 
c) To create successful, healthy places residential developments of 10 units and above
must comply with Scottish Government policy Creating Places and Designing Streets
and must incorporate the following fundamental principles: 
(i) Character and Identity
• Create places that are distinctive to prevent homogenous 'anywhere'
development;
• Provide a number of character areas reflecting site characteristics that
have their own distinctive identity and are clearly distinguishable;
• Provide distinctiveness between and in each character area through a
combination of measures including variation in urban form, street
structure/network, architecture and masonry, accent features (such as
porches), surrounds and detailing, materials (buildings and surfaces),
colour, boundary treatments, hard/soft landscaping and a variety of
approaches to tree species and planting that emphasises the hierarchy of
open spaces and streets within a cohesive design strategy for the whole
development;
• Distinctiveness must be reinforced along main thoroughfares, open
spaces and places where people may congregate such as
shopping/service centres;
• Retain, incorporate and/or respond to relevant elements of the landscape
such as topography and planted features, natural and historic
environment, and propose street naming (in residential developments of
Page 115

Page 116

20 units and above, where proposed names are to be submitted with the
planning application) to retain and enhance local associations; 
(ii) Healthier, Safer Environments
• Designed to prevent crime, fear of crime and anti-social behaviour with
good levels of natural surveillance and security using treatments such as
low boundary walls, dual frontages (principal rooms) and well-lit routes to
encourage social interaction.  Unbroken high boundary treatments such
as wooden fencing and blank gables onto routes, open spaces and
communal areas will not be acceptable.
• Designed to encourage physical exercise for people of all abilities.
• Create a distinctive urban form with landmarks, key buildings, vistas,
gateways and public art to provide good orientation and navigation
through the development.
• Provide a mix of compatible uses, where indicated within settlement
statements, integrated into the fabric of buildings within the street.
• Prioritise pedestrians and cyclists by providing a permeable movement
framework that incorporates desire lines (including connecting to and
upgrading existing desire lines) and is fully integrated with the surrounding
network to create walkable neighbourhoods and encourage physical
activity.
• Integrate multi- functional active travel routes, green and open space into
layout and design, to create well connected places that encourage
physical activity, provide attractive spaces for people to interact and to
connect with nature.
• Create safe streets that influence driver behaviour to reduce vehicle
speeds that are appropriate to the local context such as through shorter
streets, reduced visibility and varying the building line.
• Provide seating opportunities within streets, paths and open spaces for all
generations and mobility's to interact, participate in activity, and rest and
reflect.
• Provide for people with mobility problems or a disability to access
buildings, places and open spaces.
• Create development with public fronts and private backs. 
• Maximise environmental benefits through the orientation of buildings,
streets and open space to maximise the health benefits associated with
solar gain and wind shelter. 
(iii) Housing Mix
• Provide a wide range of well integrated tenures, including a range of
house types and plot sizes for different household sizes, incomes and
generations and meet the affordable and accessible requirements of
policy DP2 Housing.
• All tenures of housing should have equal access to amenities, greenspace
and active travel routes. 
(iv) Open Spaces/Landscaping
• Provide accessible, multi-functional open space within a clearly defined
hierarchy integrated into the development and connected via an active
travel network of  green/blue corridors that are fully incorporated into the
development and to the surrounding area, and meet the requirements of
policy EP5 Open Space and the Open Space Strategy Supplementary
Page 116

Page 117

Guidance and Policy EP12 Managing the Water Environment and
Drainage Impact Assessment for New Developments Supplementary
Guidance.
• Landscaped areas must provide seasonal variation, (mix of planting and
colour) including native planting for pollination and food production.
• Landscaping areas that because of their size, shape or location would not
form any useable space or that will not positively contribute to the
character of an area will not contribute to the open space requirements of
Policy EP4 Open Space.
• Semi-mature tree planting and shrubs must be provided along all routes
with the variety of approaches reflecting and accentuating the street
hierarchy.
• Public and private space must be clearly defined.
• Play areas (where identified) must be inclusive, providing equipment so
the facility is for every child/young person regardless of ability and
provided upon completion of 50% of the character area.
• Proposals must provide advance landscaping identified in site
designations and meet the quality requirements of policy EP5 Open
Space.
• Structural landscaping must incorporate countryside style paths (such as
bound or compacted gravel) with waymarkers.
•  Maintenance arrangements for all paths, trees, hedging, shrubs, play/
sports areas, roundabouts and other open/ green spaces and blue/green
corridors must be provided. 
v) Biodiversity
• Create a variety of high quality multi- functional green/blue spaces and
networks that connect people and nature, that include trees, hedges and
planting to enhance biodiversity and support habitats/wildlife and comply
with policy EP2 Biodiversity and Geodiversity and EP5 Open Space.
• A plan detailing how different elements of the development will contribute
to supporting biodiversity must be included in the design statement
submitted with the planning application.
• Integrate green and blue infrastructure such as swales, permeable paving,
SUDS ponds, green roofs and walls and grass/wildflower verges into
streets, parking areas and plots to sustainably address drainage and
flooding issues and enhance biodiversity from the outset of the
development.
• Developments must safeguard and where physically possible extend or
enhance wildlife corridors and green/blue networks and prevent
fragmentation of existing habitats. 
(vi) Parking
• Car parking must not dominate the streetscape to the front or rear of
properties.  On all streets a minimum of 50% of car parking must be
provided to the side or rear and behind the building line with a maximum
of 50% car parking within the front curtilage or on street, subject to the
visual impact being mitigated by hedging, low stone boundary walls or
other acceptable treatments that enhance the streetscape.
• Provide semi-mature trees and planting within communal private and
public/visitor parking areas and on-street parking at a maximum interval of
4 car parking spaces.
Page 117

Page 118

• Secure and covered cycle parking and storage, car sharing spaces and
electric car charging points must be provided in accordance with policy
DP1 Development Principles.
• Parking areas must use a variation in materials to reduce the visual
impact on the streetscene. 
(vii) Street Layout and Detail
• Provide a clear hierarchy of streets reinforced through street width,
building density and street and building design, materials, hard/soft
landscaping and a variety of approaches to tree planting and shrubs.
• Streets and connecting routes should encourage walking and cycling over
use of the private car by providing well connected, safe and appealing
routes.
• Design junctions to prioritise pedestrians, accommodate active travel and
public transport and service/emergency vehicles to reflect the context and
urban form and ensure that the street pattern is not standardised.  
• Dead-end streets/cul-de-sacs will only be selectively permitted such as on
rural edges or where topography, site size, shape or relationship to
adjacent developments prevent an alternative more permeable layout.
These must be short, serving no more than 10 units and provide walking
and cycling through routes to maximise connectivity to the surrounding
area.
• Where a roundabout forms a gateway into, or a landmark within, a town
and/or a development, it must be designed to create a gateway feature or
to contribute positively to the character of the area.
• Design principles for street layouts must be informed by a Street
Engineering Review (SER) and align with Roads Construction Consent
(RCC) to provide certainty that the development will be delivered as per
the planning consent. 
(d) Future masterplans will be prepared through collaborative working and in partnership
between the developer and the council for Lochyhill (Forres), Barhill Road (Buckie),
Elgin Town Centre/Cooper Park, Elgin North East, Clarkly Hill, Burghead and West
Mosstodloch.  Masterplans that are not prepared collaboratively and in partnership
with the council will not be supported.  Masterplans that are approved will be
Supplementary Guidance to the Plan.¬¬¬ 
(e) Proposals for sites must reflect the key design principles and safeguard or enhance
the green networks set out in the Proposals Maps and Settlement Statements. 
Alternative design solutions may be proposed where justification is provided to the
planning authority's satisfaction to merit this. 
PP3  INFRASTRUCTURE & SERVICES
Development must be planned and co-ordinated with infrastructure to ensure that places
function properly and proposals are adequately served by infrastructure and services.   
a) In relation to infrastructure and services developments will be required to provide the
following as may be considered appropriate by the planning authority, unless these
requirements are considered not to be necessary: 
Page 118

Page 119

i)  Education, Health, Transport, Sports and Recreation and Access facilities in
accord with Supplementary Guidance on Developer Obligations and Open
Space. 
ii)  Green infrastructure and network requirements specified in policy EP5 Open
Space, Town and Village Maps and, contained within Supplementary Guidance
on the Open Space Strategy, Masterplans and Development Briefs. 
iii)  Mitigation/modification to the existing transport network (including road and rail)
to address the impact of the proposed development in terms of safety and
efficiency.  This may include but not be limited to passing places, road
widening, junction enhancement, bus stop infrastructure, and drainage
infrastructure.  A number of potential road and transport improvements are
identified and shown on the Town and Village Maps as Transport Proposals
(TSP's) including the interventions in the Elgin Transport Strategy. These
requirements are not exhaustive and do not pre-empt any measures which may
result from the Transport Assessment process. 
iv)  Electric car charging points must be provided at all commercial and community
parking facilities.  Access to charging points must also be provided for
residential properties, where in-curtilage facilities cannot be provided to any
individual residential property then access to communal charging facilities
should be made available.  Access to other nearby charging facilities will be
taken into consideration when identifying the need for communal electric
charging points. 
v)  Active Travel and Core Path requirements specified in the Council's Active
Travel Strategy and Core Path Plan. 
vi)  Safe transport and access routes linking to existing networks and mitigating the
impacts of development off-site. 
vii)  Information Communication Technology (ICT) and fibre optic broadband
connections for all premises unless justification is provided to substantiate it is
technically unfeasible. 
viii)  Foul and surface water drainage, including Sustainable Urban Drainage
Systems (SUDS), including construction phase SUDS. 
ix)  Measures that implement the waste management hierarchy as defined in the
Zero Waste Plan for Scotland including the provision of local waste storage and
recycling facilities designed into the development in accord with policy PP1
Placemaking.  For major applications a site waste management plan may be
required to ensure that waste minimisation is achieved during the construction
phase. 
x)  Infrastructure required to improve or increase capacity at Water Treatment
Works and Waste Water Treatment Works will be supported subject to
compliance with policy DP1. 
xi) A utilities plan setting out how existing and new utility (including gas, water,
electricity pipelines and pylons) provision has been incorporated into the layout
Page 119

Page 120

and design of the proposal.  This requirement may be exempted in relation to
developments where the council considers it might not be appropriate, such as
domestic or very small scale built developments and some changes of use. 
b)  Development proposals will not be supported where they:
i)  Create new accesses onto trunk roads and other main/key routes (A941 & A98)
unless significant economic benefits are demonstrated or such access is
required to facilitate development that supports the provisions of the
development plan. 
ii)  Adversely impact on active travel routes, core paths, rights of way, long
distance and other access routes and cannot be adequately mitigated by an
equivalent or better alternative provision in a location convenient for users. 
iii)  Adversely impact on blue/green infrastructure, including green networks
important for wildlife unless an equivalent or better alternative provision will be
provided. 
iv)  Are incompatible with key waste sites at Dallachy, Gollanfield, Moycroft and
Waterford and would prejudice their operation. 
v)  Adversely impact on community and recreational sites, buildings or
infrastructure including CF designations and cannot be adequately mitigated. 
vi)  Adversely impact on flood alleviation and mitigation infrastructure. 
vii)  Compromise the economic viability of bus or rail facilities.   
c)  Harbours 
Development within and diversification of harbours to support their sustainable
operation will be supported subject to compliance with other policies and settlement
statements. 
d)  Developer Obligations 
Developer obligations will be sought to mitigate any measurable adverse impact of a
development proposal on local infrastructure, including education, healthcare,
transport (including rail), sports and recreational facilities and access routes. 
Obligations will be sought to reduce, eliminate or compensate for this impact.
Developer obligations may also be sought to mitigate any adverse impacts of a
development, alone or cumulatively with other developments in the area, on the
natural environment. 
Where necessary obligations that can be secured satisfactorily by means of a
planning condition attached to planning permission will be done this way.  Where this
cannot be achieved, the required obligation will be secured through a planning
agreement in accordance with Circular 3/2012 on Planning Obligations.   
Developer obligations will be sought in accordance with the Council's Supplementary
Guidance on Developer Obligations.  This sets out the anticipated infrastructure
requirements, including methodology and rates.   
Page 120

Page 121

Where a developer considers that the application of developer obligations renders a
development commercially unviable a viability assessment and 'open-book
accounting' must be provided by the developer which Moray Council, via the District
Valuer, will verify, at the developer's expense.  Should this be deemed accurate then
the Council will enter into negotiation with the developer to determine a viable level
of developer obligations.   
The Council's Developer Obligations Supplementary Guidance provides further detail
to support this policy. 
DP1 DEVELOPMENT PRINCIPLES 
This policy applies to all development, including extensions and conversions and will be
applied reasonably taking into account the nature and scale of a proposal and individual
circumstances. 
The Council will require applicants to provide impact assessments in order to determine
the impact of a proposal. Applicants may be asked to determine the impacts upon the
environment, transport network, town centres, noise, air quality, landscape, trees, flood
risk, protected habitats and species, contaminated land, built heritage and archaeology
and provide mitigation to address these impacts. 
Development proposals will be supported if they conform to the relevant Local
Development Plan policies, proposals and additional guidance, meet the following criteria
and address their individual and cumulative impacts: 
(i) Design
a) The scale, density and character must be appropriate to the surrounding area
and create a sense of place (see Policy PP1) and support the principles of a
walkable neighbourhood. 
b) The development must be integrated into the surrounding landscape which will
include safeguarding existing trees and undertaking replacement planting to
include native trees for any existing trees that are felled, and safeguarding any
notable topographical features (e.g. distinctive knolls), stone walls and existing
water features by avoiding channel modifications and culverting. A tree survey
and tree protection plan must be provided with planning applications for all
proposals where mature trees are present on site or that may impact on trees
outwith the site. The strategy for new tree provision should follow the principles
of the "Right Tree in the Right Place". 
c) Make provision for new open space and connect to existing open space under
the requirements of Policy EP5 and provide details of the future maintenance of
these spaces. A detailed landscape plan must be submitted with planning
applications and include information about green/blue infrastructure, tree
species, planting, ground/soil conditions, and natural and man-made features
(e.g. grass areas, wildflower verges, fencing, walls, paths, etc.). 
d) Demonstrate how the development will conserve and enhance the natural and
built environment and cultural heritage resources, retain original land contours
and integrate into the landscape. 
Page 121

Page 122

e) Proposals must not adversely impact upon neighbouring properties in terms of
privacy, daylight or overbearing loss of amenity. 
f)  Proposals do not result in backland development or plots that are subdivided by
more than 50% of the original plot.  Sub-divided plots must be a minimum of
400m2, excluding access and the built-up area of the application site will not
exceed one-third of the total area of the plot and the resultant plot density and
layout reflects the character of the surrounding area. 
g)  Pitched roofs will be preferred to flat roofs and box dormers are not acceptable. 
h)  Existing stone walls on buildings and boundaries must be retained. 
Alterations and extensions must be compatible with the character of the
existing building in terms of design, form, choice of materials and positioning
and meet all other relevant criteria of this policy. 
i)  Proposals must orientate and design buildings to maximise opportunities for
solar gain. 
j)  All developments must be designed so as to ensure that all new buildings avoid
a specified and rising proportion of the projected greenhouse gas emissions
from their use (calculated on the basis of the approved design and plans for the
specific development) through the installation and operation of low and zero-
carbon generating technologies. 
(ii) Transportation
a) Proposals must provide safe entry and exit from the development, including the
appropriate number and type of junctions, maximise connections and routes for
pedestrians and cyclists, including links to active travel and core path routes,
reduce travel demands and ensure appropriate visibility for all road users at
junctions and bends. Road, cycling, footpath and public transport connections
and infrastructure must be provided at a level appropriate to the development
and connect people to education, employment, recreation, health, community
and retail facilities. 
b) Car parking must not dominate the street scene and must be provided to the
side or rear ¬and behind the building line. Maximum (50%) parking to the front
of buildings and on street may be permitted provided that the visual impact of
the parked cars is mitigated by hedging or low stone boundary walls. Roadways
with a single carriageway must provide sufficient off road parking to avoid
access routes being blocked to larger service vehicles and prevent parking on
pavements. 
c) Provide safe access to and from the road network, address any impacts on
road safety and the local road, rail and public transport network. Any impacts
identified through Transport Assessments/ Statements must be identified and
mitigated. This may include but would not be limited to, passing places, road
widening, junction improvements, bus stop infrastructure and drainage
infrastructure. A number of potential mitigation measures have been identified
in association with the development of sites and the most significant are shown
on the Proposals Map as TSP's. 
Page 122

Page 123

d) Provide covered and secure facilities for cycle parking at all flats/apartments,
retail, community, education, health and employment centres. 
e) Garages and parking provision must be designed to comply with Moray Council
parking specifications see Appendix 2. 
f)  The road layout must be designed to allow for the efficient mechanical
sweeping of all roadways and channels, paviors, turning areas and junctions.
The road layout must also be designed to enable safe working practices,
minimising reversing of service vehicles, with hammerheads minimised in
preference to turning areas such as road stubs or hatchets, and to provide
adequate space for the collection of waste and movement of waste collection
vehicles. 
g) The road and house layout in urban development should allow for communal
refuse collection points where the design does not allow for individual storage
within the curtilage and / or collections at kerbside. Communal collection points
may either be for the temporary storage of containers taken by the individual
householder or for the permanent storage of larger containers. The
requirements for a communal storage area are stated within the Council's
Kerbside Collection Policy, which will be a material consideration. 
h) Road signs should be minimised designed and placed at the back of footpaths
to reduce street clutter, avoid obstructing pedestrian movements and
safeguarding sightlines; 
i)  Within communal parking areas there will be a requirement for electric car
charging points. Parking spaces for car sharing must be provided where a need
is identified by the Transportation Manager. 
(iii) Water environment, pollution, contamination
a) Acceptable water and drainage provision must be made, including the use of
sustainable urban drainage systems (SUDS) for dealing with surface water
including temporary/ construction phase SUDS (see Policy EP12). 
b) New development should not be located in areas at flood risk or increase
vulnerability to flooding (see Policy EP12). Exceptions to this would only be
considered in specific circumstances, e.g. extension to an existing building or
change of use to an equal or less vulnerable use. Where this exception is
applied the proposed development must include resilience measures such as
raised floor levels and electrical sockets. 
c) Proposals must avoid major hazard sites and address any potential risk of
pollution including ground water contamination in accordance with recognised
pollution prevention and control measures. 
d) Proposals must protect and wherever practicable enhance water features
through for example naturalisation of watercourses by introducing a more
natural planform and removing redundant or unnecessary structures. 
e) Proposals must address and sufficiently mitigate any contaminated land issues. 
Page 123

Page 124

f)  Make acceptable arrangements for waste collection and management and
encourage recycling. 
g) Avoid sterilising significant workable reserves of minerals, prime agricultural
land or productive forestry. 
h)  Proposals must avoid areas at risk of coastal erosion and coastal change. 
EP2 BIODIVERSITY
All development proposals must, where possible, retain, protect and enhance features of
biological interest and provide for their appropriate management.  Development must
safeguard and where physically possible extend or enhance wildlife corridors and
green/blue networks and prevent fragmentation of existing habitats. 
Development should integrate measures to enhance biodiversity as part of multi-functional
spaces/ routes. 
Proposals for 4 or more housing units or 1000 m2 or more of commercial floorspace must
create new or, where appropriate, enhance natural habitats of ecological and amenity
value. 
Developers must demonstrate, through a Placemaking Statement where required by
Policy PP1 which incorporates a Biodiversity Plan, that they have included biodiversity
features in the design of the development. Habitat creation can be achieved by providing
links into existing green and blue networks, wildlife friendly features such as wildflower
verges and meadows, bird and bat boxes, amphibian friendly kerbing, wildlife crossing
points such as hedgehog highways and planting to encourage pollination, wildlife friendly
climbing plants, use of hedges rather than fences, incorporating biodiversity measures into
SUDS and retaining some standing or lying dead wood, allotments, orchards and
woodlands. 
Where development would result in loss of natural habitats of ecological amenity value,
compensatory habitat creation will be required where deemed appropriate. 
EP3 SPECIAL LANDSCAPE AREAS AND LANDSCAPE CHARACTER
i)  Special Landscape Areas (SLA's) 
Development proposals within SLA's will only be permitted where they do not
prejudice the special qualities of the designated area set out in the Moray Local
Landscape Designation Review, adopt the highest standards of design in
accordance with Policy DP1 and other relevant policies, minimises adverse impacts
on the landscape and visual qualities the area is important for, and are for one of the
following uses; 
a) In rural areas (outwith defined settlement and rural grouping boundaries);
i) Where the proposal involves an appropriate extension or change of use to
existing buildings, or
ii) For uses directly related to distilling, agriculture, forestry and fishing which
have a clear locational need and demonstrate that there is no alternative
location, or
iii) For nationally significant infrastructure developments identified in the
National Planning Framework, 
Page 124

Page 125

b) In urban areas (within defined settlement, rural grouping boundaries and LONG
designations);
i) Where proposals conform with the requirements of the settlement
statements, Policies PP1, DP1 and DP3 as appropriate and all other
policy requirements, and
ii) Proposals reflect the traditional settlement character in terms of siting and
design. 
c) The Coastal (Culbin to Burghead, Burghead to Lossiemouth, Lossiemouth to
Portgordon, Portgordon to Cullen Coast), Cluny Hill, Spynie, Quarrywood and
Pluscarden SLA's are classed as " sensitive" in terms of Policy DP4 and no
new housing in the open countryside will be permitted within these SLA's. 
Proposals for new housing within other SLA's not specified in the preceding
para will be considered against the criteria set out above and the criteria of
Policy DP4. 
d) Where a proposal is covered by both a SLA and CAT or ENV
policy/designation, the CAT policy or ENV policy/designation will take
precedence. 
b ii) Landscape Character 
New developments must be designed to reflect the landscape characteristics
identified in the Landscape Character Assessment of the area in which they are
proposed. 
Proposals for new roads and hill tracks associated with rural development must
ensure that their alignment and use minimises visual impact, avoids sensitive natural
heritage and historic environment features, including areas protected for nature
conservation, carbon rich soils and protected species, avoids adverse impacts upon
the local hydrology and takes account of recreational use of the track and links to the
wider network. 
EP5 OPEN SPACE
a)  Existing Open Space (ENV's and Amenity Land)
Development which would result in a change of use of a site identified under the
ENV designation in settlement statements or amenity land designations in rural
groupings to anything other than open space use will be refused. Proposals that
would result in a change of use of an ENV4 Sports Area to any other use (including
other ENV categories) will be refused. The only exceptions are where the proposal is
for essential community infrastructure required to deliver the key objectives of the
Council and its Community Planning Partners, excluding housing, or for a site
specific opportunity identified within the settlement statement. Where one of these
exceptions applies, proposals must: 
• Be sited and designed to minimise adverse impacts on the principal function of
the space and the key qualities and features identified in the Moray Open
Space Strategy Supplementary Guidance. 
• Demonstrate that there is a clear excess of the type of ENV and the loss of the
open space will not negatively impact upon the quality, accessibility and
quantity of open space provision and does not fragment green networks (with
Page 125

Page 126

reference to the Moray Open Space Strategy Supplementary Guidance, green
network mapping and for ENV4 Sports Area in consultation with SportScotland)
or replacement open space provision of equivalent function, quality and
accessibility is made. 
The temporary use of unused or underused land as green infrastructure is
encouraged, this will not prevent any future development potential which has been
identified from being realised. Proposals that would result in a change of use of an
ENV4 Sports Area to any other use (including other ENV categories) will be refused. 
Proposals for allotments or community growing on existing open space will be
supported where they do not adversely affect the primary function of the space or the
key qualities and features identified in the Moray Open Space Strategy
Supplementary Guidance and a locational requirement has been identified in the
Council's Food Growing Strategy. Consideration will include related aspects such as
access, layout, design and car parking requirements. 
Any new/proposed extension to existing cemetery sites requiring an intrusive ground
investigation must be undertaken in accordance with SEPA's guidance on assessing
the impacts of cemeteries on groundwater before any development occurs at the
site. 
Areas identified in Settlement Statements as ENV are categorised based on their
primary function as set out below. These are defined in the Open Space Strategy
Supplementary Guidance. 
ENV 1 Public Parks and Gardens
ENV 2  Amenity Greenspace
ENV 3  Playspace for children and teenagers
ENV 4  Sports Areas
ENV 5  Green Corridors 
ENV 6  Natural/Semi-Natural Greenspace
ENV 7  Civic Space 
ENV 8  Allotments
ENV 9  Cemeteries and proposed extensions
ENV 10 Private Gardens and Grounds 
ENV 11 Other Functional Greenspace 
b) Green Infrastructure and Open Space in New Development
New development must incorporate accessible multifunctional open space of
appropriate quantity and quality to meet the needs of development and must provide
green infrastructure to connect to wider green/blue networks. In Elgin, Buckie and
Forres green infrastructure must be provided as required in the green network
mapping. Blue drainage infrastructure will require to be incorporated within green
open space. The blue-green context of the site will require to be considered from the
very outset of the design phase to reduce fragmentation and maximize  the multi-
benefits arising from this infrastructure. 
Open space provision in new developments must meet the accessibility, quality and
quantity standards set out below and meet the requirements of policy PP1
Placemaking, EP2 Biodiversity, other relevant policies and any site specific
requirements within the Settlement Statements.  Developers must demonstrate
Page 126

Page 127

through a Placemaking Statement that they have considered these standards in the
design of the open space, this must include submission of a wider analysis plan that
details existing open space outwith the site, key community facilities in the area and
wider path networks. 
i) Accessibility Standard 
Everyone will live within a five minute walk of a publicly usable space of at least
0.2ha. 
ii) Quality Standard 
All new development proposals will be assessed and must achieve a very good
quality score of no less than 75%. Quality will be assessed by planning officers
at the planning application stage against the five criteria below using the bullet
point prompts.  Each criterion will be scored on a scale of 0 (poor) to 5 (very
good) with an overall score for the whole development expressed as a
percentage. 
Accessible and well connected
• Allows movement in and between places, consideration to be given to
reflecting desire lines, permeable boundaries, and multiple access points 
• Accessible entrances in the right places. 
• Accessible for all generations and mobility's, including consideration of
gradient and path surfaces. 
• Provide appropriately surfaced, inclusive, high quality paths. 
• Connects with paths, active travel routes and other transport modes
including bus routes.
• Offers connecting path network with legible waymarking and signage. 
Attractive and Appealing Places
• Attractive with positive image created through character and quality
elements. 
• Attractive setting for urban areas.
• Quality materials, equipment and furniture.
• Attractive plants and landscape elements that support character, including
providing seasonal and sensory variation and food production. 
• Welcoming boundaries and entrance areas. 
• Adequate bin provision.
• Long term maintenance measures in place.¬ 
Biodiverse supporting ecological networks (see Policy EP2 Biodiversity)
• Contribute positively to biodiversity through the creation of new natural
habitats for ecological and amenity value.  
• Large enough to sustain wildlife populations, including green/blue
networks and landscaping.   
• Offers a diversity of habitats. 
• Landscaping and open space form part of wider landscape structure and
setting.
• Connects with wider blue/green networks Provide connections to existing
green/bue networks and avoids fragmentation of existing habitats. 
• Ensure a balance between areas managed positively for biodiversity and
areas managed primarily for other activities e.g. play, sport.
Page 127

Page 128

• Resource efficient, including ensuring open space has a clear function
and is not "left over". 
Promotes activity, health and well being
• Provides multifunctional open space for a range of outdoor physical
activities reflecting user needs and location. 
• Provides diverse play, sport, and recreational facilities for a range of ages
and user groups.
• Providing places for social interaction, including supporting furniture to
provide seating and resting opportunities.  
• Appropriate high quality facilities meeting needs and reflecting the site
location and site. 
• Carefully sited facilities for a range of ages with consideration to be given
to existing facilities, overlooking, and ease of access for users. 
• Open space is flexible to accommodate changing needs. 
Safe, Welcoming and contributing to Character and Identity
• Safe and welcoming.
• Good levels of natural surveillance.
• Discourage anti-social behaviour.
• Appropriate lighting levels. 
• Sense of local identity and place. 
• Good routes to wider community facilities e.g connecting to schools,
shops, or transport nodes.
• Distinctive and memorable places that support local culture and
identity.¬¬
• Catering for a range of functions and activities providing a multi-functional
space meeting needs.
• Community involvement in management. 
b iii) Quantity Standard
Unless otherwise stated in site designations, the following quantity standards
will apply.
• Residential sites less than 10 units - landscaping to be determined under
the terms of Policy DP1 Development Principles to integrate the new
development.
• Residential sites 10-50 units and new industrial sites- minimum 15% open
space
• Residential sites 51-200 units- minimum 20% open space
• Residential sites 201 units and above and Business Parks- minimum 30%
open space which must include allotments, formal parks and playspaces
within residential sites. 
In meeting the quantity requirements, only spaces which have a clear multi benefit
function will be counted. Structure and boundary landscaping areas must make
provision for public access and link into adjacent green corridors. The quantity
standard must be met within the designation boundaries. For windfall sites the
quantity standard must be new open space provision within the application
boundaries. 
Open Spaces approved in new developments will be classed as ENV spaces upon
granting of consent.
Page 128

Page 129

Proposals must also comply with the Council's Open Space Strategy Supplementary
Guidance. 
EP12 MANAGEMENT AND ENHANCEMENT OF THE WATER ENVIRONMENT
a) Flooding
New development will not be supported if it would be at significant risk of flooding
from any source or would materially increase the possibility of flooding elsewhere.
For development at or near coastal locations, this includes consideration of future
flooding that may be caused by sea level rise and/or coastal change eroding existing
natural defences in the medium and long term. 
Proposals for development in areas considered to be at risk from flooding will only be
permitted where a flood risk assessment to comply with the recommendations of
Scottish Planning Policy and to the satisfaction of Scottish Environment Protection
Agency and the Council is provided by the applicant. 
There are different levels of flood risk assessment dependent on the nature of the
flood risk. The level of assessment should be discussed with the Council prior to
submitting a planning application. 
Level 1 -  a flood statement with basic information with regard to flood risk.
Level 2 -  full flood risk assessment providing details of flood risk from all sources,
results of hydrological and hydraulic studies and any appropriate
proposed mitigation. 
Assessments must demonstrate that the development is not at risk of flooding and
would not increase the probability of flooding elsewhere.  Level 2 flood risk
assessments must be signed off by a competent professional.  The Flood Risk
Assessment and Drainage Impact Assessment for New Development Supplementary
Guidance provides further detail on the information required. 
Due to continuing changes in climatic patterns, the precautionary principle will apply
when reviewing any application for an area at risk from inundation by floodwater.
Proposed development in coastal areas must consider the impact of tidal events and
wave action when assessing potential flood risk. 
The following limitations on development will also be applied to take account of the
degree of flooding as defined in Scottish Planning Policy;
a) In areas of little to no risk (less than 0.1%), there will be no general constraint to
development.
b) Areas of low to medium risk (0.1% to 0.5%) will be considered suitable for most
development. A flood risk assessment may be required at the upper end of the
probability range i.e. (close to 0.5%) and for essential civil infrastructure and the
most vulnerable uses. Water resistant materials and construction may be
required. Areas within this risk category will generally not be suitable for civil
infrastructure. Where civil infrastructure must be located in these areas or is
being substantially extended, it should be designed to be capable of remaining
operational and accessible during flooding events.
c) Areas of medium to high risk (0.5% or above) may be suitable for:
• Residential, institutional, commercial and industrial development within
built up areas provided that flood protection measures to the appropriate
Page 129

Page 130

standard already exist and are maintained, are under construction, or are
a planned measure in a current flood management plan.
• Essential infrastructure within built up areas, designed and constructed to
remain operational during floods and not impede water flow.
• Some recreational, sport, amenity and nature conservation uses, provided
appropriate evacuation procedures are in place, and
• Employment related accommodation e.g. caretakers or operational staff. 
Areas within these risk categories will generally not be suitable for the following
uses and where an alternative/lower risk location is not available¬¬;
• Civil infrastructure and most vulnerable uses.
• Additional development in undeveloped and sparsely developed areas,
unless a location is essential for operational reasons e.g. for navigation
and water based recreation, agriculture, transport or utilities infrastructure
(which should be designed to be operational during floods and not impede
water flows).
• New caravan and camping sites 
Where development is permitted, measures to protect against or manage flood risk
will be required and any loss of flood storage capacity mitigated to achieve a neutral
or better outcome. Water resistant materials and construction must be used where
appropriate. Land raising and elevated buildings on structures such as stilts are
unlikely to be acceptable. 
b) Surface Water Drainage: Sustainable Urban Drainage Systems (SUDS)
Surface water from development must be dealt with in a sustainable manner that has
a neutral effect on flooding or which reduces the risk of flooding. The method of
dealing with surface water must also avoid pollution and promote habitat
enhancement and amenity. All sites must be drained by a sustainable drainage
system (SUDS) designed in line with current CIRIA guidance. Drainage systems
must contribute to enhancing existing "blue" and "green" networks while contributing
to place-making, biodiversity, recreational, flood risk and climate change objectives. 
When considering the appropriate SUDS design for the development the most
sustainable methods, such as rainwater harvesting, green roofs, bio retention
systems, soakaways, and permeable pavements must be considered first.  If it is
necessary to include surface water attenuation as part of the drainage system, only
above ground attenuation solutions will be considered, unless this is not possible
due to site constraints.   
If below ground attenuation is proposed the developer must provide a robust
justification for this proposal.  Over development of a site or a justification on
economic grounds will not be acceptable.  When investigating appropriate SUDS
solutions developers must integrate the SUDS with allocated green space, green
networks and active travel routes to maximise amenity and biodiversity benefits. 
Specific arrangements must be made to avoid the issue of permanent SUDS
features becoming silted-up with run-off. Care must be taken to avoid the spreading
and/or introduction of invasive non-native species during the construction of all
SUDS features.  On completion of SUDS construction the developer must submit a
comprehensive Operation and Maintenance Manual.  The ongoing maintenance of
Page 130

Page 131

SUDS for all new development will be undertaken through a factoring agreement, the
details of which must be supplied to the Planning Authority.   
All developments of less than 3 houses or a non-householder extension under 100
square metres must provide a Drainage Statement.  A Drainage Assessment will be
required for all developments other than those identified above. 
c) Water Environment
Proposals, including associated construction works, must be designed to avoid
adverse impacts upon the water environment including Ground Water Dependent
Terrestrial Ecosystems and should seek opportunities for restoration and/or
enhancement, if appropriate. The Council will only approve proposals impacting on
water features where the applicant provides a report to the satisfaction of the Council
that demonstrates that any impact (including cumulative) on water quality, water
quantity, physical form (morphology), river hydrology, sediment transport and
erosion, coastal processes (where relevant) nature conservation (including protected
species), fisheries, recreational, landscape, amenity and economic and social impact
can be adequately mitigated. 
The report must consider existing and potential impacts up and downstream of the
development particularly in respect of potential flooding. The Council operates a
presumption against the culverting of watercourses and any unnecessary
engineering works in the water environment. 
A buffer strip of at least 6 metres between any new development and all water
features is required and should be proportional to the bank width and functional river
corridor (see table on page 96). This must achieve the minimum width within the
specified range as a standard, however, the actual required width within the range
should be calculated on a case by case basis by an appropriately qualified individual.
These must be designed to link with blue and green networks, including appropriate
native riparian vegetation and can contribute to open space requirements. 
Developers may be required to make improvements to the water environment as part
of the development. Where a Water Framework Directive (WFD)¬ water body
specific objective is within the development boundary, or in proximity, developers will
need to address this within the planning submission through assessment of potential
measures to address the objective and implementation, unless adequate justification
is provided. Where there is no WFD objective the applicant should still investigate
the potential for watercourse restoration along straightened sections or removal of
redundant structures and implement these measures where viable. 
Width to watercourse Width of buffer strip (either side)
(top of bank) 
Less than 1m  6m
1-5m  6-12m
5-15m  12-20m
15m+  20m+ 
The Flood Risk Assessment and Drainage Impact Assessment for New Development
Supplementary Guidance provides further detail on the information required to
support proposals. 
Page 131

Page 132

EP13 FOUL DRAINAGE 
All development within or close to settlements (as defined in the Local Development Plan)
of more than 2,000 population must connect to the public sewerage system unless
connection  is not permitted due to lack of capacity. In such circumstances, temporary
provision of private sewerage systems may be allowed provided Scottish Water has
confirmed investment to address this constraint has been allocated within its investment
Programme and the following requirements have been met; 
• Systems must not have an adverse effect on the water environment
• Systems must be designed and built to a standard which will allow adoption by
Scottish Water
• Systems must be designed such that they can be easily connected to a public sewer
in the future. Typically this will mean providing a drainage line up to a likely point of
connection. 
All development within or close to settlements (as above) of less than 2,000 population will
require to connect to public sewerage except where a compelling case is made otherwise.
Factors to be considered in such a case will include size of the proposed development,
whether the development would jeopardise delivery of public sewerage infrastructure and
existing drainage problems within the area. 
Where a compelling case is made, a private system may be acceptable provided it does
not pose or add a risk of detrimental effects, including cumulative, to the natural and built
environment, surrounding uses or amenity of the general area. 
Where a private system is deemed to be acceptable, within settlements as above or small
scale development in the countryside, a discharge to land, either full soakaway or raised
mound soakaway, compatible with Technical Handbooks (which sets out guidance on how
proposals may meet the Building  Regulations) must be explored prior to considering a
discharge to surface waters. 
EP8 HISTORIC ENVIRONMENT
a) Scheduled Monuments and Unscheduled Archaeological Sites of Potential
National Importance.
Where a proposed development potentially has a direct impact on a Scheduled
Monument, Scheduled Monument Consent (SMC) is required, in addition to any
other necessary consents.  Historic Environment Scotland manage these consents. 
Development proposals will be refused where they adversely affect the integrity of
the setting of Scheduled Monuments and unscheduled archaeological sites of
potential national importance unless the developer proves that any significant
adverse effects are clearly outweighed by exceptional circumstances, including
social or economic benefits of national importance. 
b) Local Designations
Development proposals which adversely affect sites of local archaeological
importance or the integrity of their settings will be refused unless; 
• Local public benefits clearly outweigh the archaeological value of the site, and
• Consideration has been given to alternative sites for the development and
preservation in situ is not possible.
Page 132

Page 133

• Where possible any adverse effects can be satisfactorily mitigated at the
developer's expense. 
The Council will consult Historic Environment Scotland and the Regional
Archaeologist on development proposals which may affect Scheduled Monuments,
nationally important archaeological sites and locally important archaeological sites. 
Page 133

Page 134

Page 134

Page 135

WARD 04_17 
22/00410/APP
30th March 2022
Erect showroom warehouse and workshop building on
Site 17 Elgin Business Park Elgin Moray 
for Yorsipp Pension Trustees 
Comments: 
 A SITE VISIT has been carried out. 
 The application is reported to Committee because it is for a building with a floor
area in excess of 2,000 sqm.
 Advertised for neighbour notification purposes – notification not possible because
no premises are situated on land to which notification can be sent. 
 One representation has been received. 
Procedure: 
 None 
Recommendation   Grant planning permission - subject to the following:- 
Conditions/Reasons 
1. The development to which this permission relates must be begun not later than
the expiration of 3 years beginning with the date on which the permission is
granted. 
Reason: The time limit condition is imposed in order to comply with the
requirements of section 58 of the Town and Country Planning (Scotland) Act 1997
as amended. 
2. The retail showroom element associated with the development hereby permitted
shall be restricted to the floor area shown on the approved ground floor plan
drawing number 1085/PL/05, and remain ancillary to the use of the building as a
warehouse. All retailing shall be in accordance with the detail specified in the
Supporting Statement submitted with and approved as part of this application. 
Reason: To ensure retailing remains associated with the principal use of the
building for storage and distribution, to allow the planning authority to give
consideration for alternative retail uses for the site, in the interests of the vitality of
viability of nearby town and retail centres. 
Item 8
Page 135

Page 136

3. All landscaping shall be undertaken in accordance with the approved landscaping
scheme (drawing number 1185/PL/03 Rev E) hereby approved, and within the
Woodland Screen planting, all planting should be planted with a maximum 2.4
metre spacing for trees with shrubs and smaller planting being spaced at least 0.6
metres apart. 
Reason: To ensure the planting is undertaken in accordance with the landscaping
scheme, and that the woodland screen planting is of a sufficient density to offer
screening from the trunk road to the north. 
4. All planting, seeding or turfing, as well as biodiversity measures forming part of the
approved landscaping scheme shall be undertaken in the first planting season
following first occupation/use or completion of the development hereby approved,
whichever is the soonest. Any trees or plants which (within a period of 5 years
from the planting) die, are removed or become seriously damaged or diseased
shall be replaced in the following planting season with others of similar size,
number and species unless this Council (as Planning Authority) agrees otherwise
in writing. 
Reason: To order to ensure that the approved landscaping works and biodiversity
measures are timeously carried out and properly maintained in a manner which
will not adversely affect the development or amenity and character of the area. 
5. All drainage shall be carried out in accordance with approved Drainage Impact
Assessment and associated drawings. 
Reason: To ensure suitable provision of surface water drainage, in the interests
of the environment and the prevention of flooding. 
6. No development shall commence until details (Site Utilities Plan scale 1:500 min)
have been submitted to and approved in writing by the Planning Authority. 
Reason: In the interest of an acceptable form of development and the submission
of details to address details shown incorrectly or missing from the submission. 
7. Notwithstanding the details submitted (plan/sections and engineering assessment)
for the proposed retaining wall(s) within the development (which are insufficient to
confirm (or otherwise) the extent of any structures within the development which
may be retaining the public road), no development shall commence until details
(plans (scale 1:500 min, including cross sections at 2m intervals) and engineering
calculations) have been submitted which demonstrate the extents to which any
structures within the development would be retaining the public road. 
Thereafter no development shall commence until evidence has been submitted to
the Planning Authority which demonstrates that the statutory processes for the
approval of the design of any retaining structures have been completed
satisfactorily.   
Reason: In the interests of an acceptable form of development in the interests of
road safety and the provision of details currently lacking from the submission.
Page 136

Page 137

8. Notwithstanding the details submitted for the customer parking layout (which are
not accepted). No development shall commence until details (Plans scale 1:500
min) have been submitted to and approved in writing by the Planning Authority
which confirm a separation strip of 1 metre (minimum) between the parking aisle
(within the customer parking) and the back of the public cyclepath. Thereafter the
development shall be completed in accordance with the approved details. 
Reason: In the interest of an acceptable form of development and the submission
of details to confirm that there is sufficient clearance between the internal
vehicular layout and the public cyclepath to mitigate the risk of potential road
safety issues for pedestrians and cyclists from vehicles manoeuvring within the
development. 
9. No works shall commence on site until a Construction Traffic Management Plan
has been submitted to and approved in writing by the Council, as Planning
Authority in consultation with the Roads Authority. The Construction Traffic
Management Plan shall include the following information:
   duration of works;
   construction programme;
   full details of any temporary construction access;
   measures to be put in place to prevent material being deposited on the
public road;
   measures to be put in place to safeguard the movements of pedestrians;
   traffic management measures to be put in place during works including any
specific instructions to drivers; and
   details for construction staff parking provision and loading and unloading
areas for construction traffic. 
Thereafter, the development shall be implemented in accordance with the
approved details. 
Reason: To ensure an acceptable form of development in terms of the
arrangements to manage traffic during construction works at the site. 
10. Prior to the access to the development becoming operational a visibility splay 4.5
metres by 70 metres in both directions shall be provided. Thereafter unless
otherwise approved in writing by the Planning Authority the visibility splay shall be
maintained clear of any obstruction above 0.26 metres in height, measured from
the level of the carriageway. 
Reason: To ensure an acceptable standard of development is provided
throughout the development site at all times in the interests of road safety. 
11. Prior to completion of the development or the development becoming operational
(whichever is soonest) parking shall be provided in accordance with the approved
plans. Thereafter the parking shall be available at all times, unless otherwise
agreed in writing by the Planning Authority. 
Page 137

Page 138

Reason: To ensure the permanent availability of the level of parking necessary for
the development in the interest of an acceptable development and road safety. 
12. Notwithstanding the details submitted for EV charging (which are insufficient and
do not show the charging unit locations or specifications) no development shall
commence until the following details for the provision of 6no. 22Kw Electric
Vehicle (EV) charging spaces have been submitted for approval by the Planning
Authority in consultation with the Roads Authority:
   Details showing the type and specifications (22Kw minimum) of the proposed
EV charging units(s). 
Thereafter the EV charging facilities shall be provided in accordance with the
approved details prior to the development becoming operational or opened to the
public and maintained for use thereafter unless otherwise agreed in writing by the
Planning Authority. 
Reason: In the interests of an acceptable form of development and the provision
of infrastructure to support the use of low carbon transport, through the provision
of details currently lacking from the submission. 
Reason(s) for Decision
The Council’s reason(s) for making this decision are:- 
Whilst not fully in accordance with the Elgin I7 Barmuckity Business Park designation
requirements of the Moray Local Development Plan 2020, where by the layout does not
present an active frontage to the A96, the proposed layout is considered to be an
acceptable departure from this designation (and subsequently policies DP5 – Business
and Industry and DP1 Development Principles) on the basis the arrangement enables
development of the site whilst ensuring the pylon running through the site is
safeguarded. 
The proposed open space provision falls below the 15% required for new industrial
sites (13% in this case) as required under policy EP5 – Open Space. However given
the safeguarding area required to the pylon corridor, the proposed hedge planting
outwith the site, provision of staff garden and subject to revised planting details being
provided for the woodland strip which would improve the quality of the open space
provision, the proposal is therefore an acceptable departure from policy EP5. 
The proposal complies with all other relevant policies of the development plan and
there are no material considerations that indicate otherwise. 
List of Informatives: 
THE DEVELOPMENT MANAGEMENT & BUILDING STANDARDS MANAGER has
commented that:- 
A Building Warrant will be required for the proposals. Should you require further
Page 138

Page 139

assistance please contact the Building Standards Duty Officer between 2pm and
4pm or telephone on 03001234561.  No appointment is necessary.  Alternatively
e-mail buildingstandards@moray.gov.uk 
THE TRANSPORTATION MANAGER has commented that:- 
Roads Construction Consent is required for any new structure which retains the
public road. The following extracts from the Moray (Aberdeenshire) Standards for
Roads Construction Consent are highlighted for the applicants benefit.   
2.4.Design Requirements 
Construction Consent will be granted only where proposals for the layout and
construction of roads, structures, road drainage and lighting meet the Local Roads
Authority’s standards. Guidance as to how these standards should be achieved is
contained in this document: Geometric and Layout Details in Part 2; Construction
Details in Part 3. Since economy of maintenance will be a major
consideration in the assessment of applications for Construction Consent,
the use of structures to support roads (e.g. retaining walls and bridges)
should be avoided wherever possible. Structures will require the appropriate
authorisation including approval in principle of the structure and the method of
analysis. 
3.7.Structures Agreements 
Where Construction Consent provides for a road to be supported by a structure,
the Local Roads Authority will normally enter into an agreement with the
developer, in terms of Section 79(1) (c) of the Roads (Scotland) Act 1984,
whereby the bridge will heritably vest in the Local Roads Authority. Other essential
structures will also require an agreement to enable these structures and solums to
vest in the Local Roads Authority. However, where a bridge or other structure and
solum have not been so acquired, the Local Roads Authority will be responsible
only for maintaining the road surface. Retaining walls should only be used in
exceptional circumstances at the discretion of the Roads Development
Engineer. Walls constructed to support the road (at the time of road construction)
will normally be adopted. Walls constructed to retain adjacent ground and/or
forming part of a building will not be adopted. 
Transportation recommended that the proposals be revised to remove any
structures which would retain the public road however wish to note that this could
not be accommodated within the current site layout without a loss of parking
provision. 
It is the view of the Roads Authority that this development and the proposal for a
retaining wall supporting the public road would not constitute an exceptional
circumstance to support the approval of any wall retaining the public road. Whilst
development may be supported in planning terms it is considered unlikely that
Roads Construction Consent would be approved and therefore the proposals may
be at risk of not being implementable. 
Parking for the proposed development has been assessed based on the specific
end user due to the nature of the operation. Should the end user change the
Page 139

Page 140

parking requirements shall be reviewed to determine the appropriate level of
provision. 
Before commencing development, the applicant is obliged to apply for
Construction Consent in accordance with Section 21 of the Roads (Scotland) Act
1984 for new roads. The applicant will be required to provide technical
information, including drawings and drainage calculations, and provide a Road
Bond to cover the full value of the works in accordance with the Security for
Private Road Works (Scotland) 1985 Regulations. Advice on this matter can be
obtained from the Moray Council web site or by emailing
transport.develop@moray.gov.uk 
Construction Consent shall include a CCTV survey of all existing roads drainage
to be adopted and core samples to determine the construction depths and
materials of the existing road. Any requirement for a Road Safety Audit will be
determined through the Roads Construction Consent process or subsequent to
the road construction prior to any road adoption. 
Requirement for any traffic calming, road construction materials and specifications
and any SUDs related to the drainage of the public road must be submitted and
approved through the formal Roads Construction Consent process. 
Planning consent does not carry with it the right to carry out works within the
public road boundary and the applicant is obliged to contact the Transportation
Manager for road opening permit in accordance with the Roads (Scotland) Act
1984. This includes any temporary access joining with the public road. 
If required, street furniture which needs to be repositioned will be at the expense
of the developer.  In addition any existing roadside ditch may require a pipe or
culvert. Advice on these matters can be obtained by e-mailing
transport.develop@moray.gov.uk. 
No building materials/scaffolding/builder's skip shall obstruct the public road
(including footpaths) without permission from the Roads Authority. 
The applicant shall be responsible for ensuring that surface/ground water does not
run from the public road into their site. 
The applicant shall ensure that their operations do not adversely affect any Public
Utilities, which should be contacted prior to commencement of operations. 
The applicants shall free and relieve the Roads Authority from any claims arising
out of his operations on the road or extension to the road. 
The Transportation Manager must always be contacted before any works
commence. This includes any temporary access, which should be agreed with the
Roads Authority prior to work commencing on it. 
Page 140

Page 141

LIST OF PLANS AND DRAWINGS SHOWING THE DEVELOPMENT
Reference No. Version No. Title/Description
1085/PL/01  Location plan
1085/PL/03   E Landscape plan
1085/PL/05  Proposed ground floor plan
1085/PL/06  Mezzanine floor plan
1085/PL/07  Elevations
1085/PL/08  Section A-A
1085/PL/09   C Site cross sections X-X
1085/PL/02   C Site plan 
List of Documents to be Approved 
 Drainage Impact Assessment & Silverwells Revised Drainage Design Layout
 Supporting Statement
Page 141

Page 142

Page 142

Page 143

Plans, drawings and other material submitted to the local authority
are protected by the Copyright, Designs and Patents Act 1988
(section 47). You may only use material which is downloaded and/
or printed for consultation purposes, to compare current
applications with previous schemes and to check whether
developments have been completed in accordance with approved
plans.
Further copies must not be made without the prior permission of
the copyright owner.
Maps shown in the Planning Committee Report can only be used
for the purposes of the Planning Committee. Any other use risks
infringing Crown Copyright and may lead to prosecution or civil
proceedings. Maps produced within this Planning Committee
Report can only be reproduced with the express permission of the
Moray Council and other Copyright holders. This permission must
be granted in advance.
PLANNING APPLICATION
COMMITTEE SITE PLAN
Site Address:
Site 17 Elgin Business Park
Elgin
Planning Application Ref Number: 
22/00410/APP 
Location Plan
Applicant Name: 
Yorsipp Pension Trustees 
Page 143

Page 144

Site Location
Page 144

Page 145

Site plan
16/01664/APP
Page 145

Page 146

Landscape plan
16/
Page 146

Page 147

Elevations
16/
Page 147

Page 148

16/
Page 148

Page 149

Photo 1
Page 149

Page 150

Photo 2
Page 150

Page 151

Photo 3
Page 151

Page 152

Photo 4
Page 152

Page 153

PLANNING APPLICATION: 22/00410/APP 
In the event that a recommendation on this planning application is overturned the
Committee is reminded of the advice contained on the front page of the agenda for
Reports on Applications 
1. THE PROPOSAL 
   Erection of showroom, warehouse, workshop and distribution centre (all in
one building) with associated yard, storage areas, car parking, access and
landscaping.
   The building would have a floor area of 3264 sqm with a covered canopy
area of 1152 sqm. Within the building, the showroom would occupy 1536
sqm, workshop 432 sqm and warehouse 1296 sqm. A 1750 sqm
mezzanine floor would be used for storage. 
   The walls of the building would be finished with roughcast for the lower 2.4
metres, with grey cladding above and to the roof. The overhanging section
of canopy would be enclosed with interspersed full height wood effect
composite cladding.
   Access would be via a new access to Kirkhill Avenue to the west of the
site, which would lead to a customer parking area. Staff parking would be
to the south of the site whilst a delivery and hardstanding yard area would
be in the north of the site (adjacent to the A96).
   Landscaping is proposed within the customer car park, as well as along
the northern, eastern and western boundaries of the site.
   Foul drainage would discharge to public sewers whilst water supply will be
from the public network. Surface water drainage would be via a SuDS
system. 
2. THE SITE 
   A 1.66 ha plot of undeveloped land within the recently established Elgin
Business Park at Barmuckity, to the east of Elgin.
   The site is bounded by the A96 Elgin to Aberdeen trunk road to the north,
St Andrew’s Road to the east, Kirkhill Avenue to the south and south west,
and an adjacent undeveloped plot to the west.
   The business park has a number of sites under development or recently
completed, and includes a mix of commercial uses as well as a petrol
filling station, drive through coffee shop and a hotel.
   An electricity pylon bisects the site on an east-west axis.
   The site is located within the I7 Barmuckity Business Park designation in
the Elgin Settlement Statement of the Moray Local Development Plan
2020.
   The position of the building upon the plot is partially influenced by the
need in designation I7 to avoid the functional flood plain in this locality. 
Page 153

Page 154

3. HISTORY 
09/00287/SCN – Screening opinion for erection of business park at Barmuckity,
Elgin adopted by Moray Council on 20 April 2009 confirming the development
will not require Environmental Impact Assessment. 
09/00883/FUL – Planning permission for formation of road layout and access
for business park at Barmuckity, Elgin granted planning permission on 14 July
2011 by Planning and Regulatory Services Committee following their meeting
of 14 June 2011. 
4. POLICY - SEE APPENDIX 
5. ADVERTISEMENTS 
5.1 Advertised for neighbour notification purposes. 
6. CONSULTATIONS 
Environmental Health – No objections. 
Contaminated Land – No objections. 
Transportation Manager - No objections, conditions recommended requiring
detail of extent of proposed retaining wall. 
Scottish Water – No objections, sufficient capacity at Badentinan Water
Treatment Works for water supply, and Moray West Water Treatment Works for
foul drainage. 
Strategic Planning and Development – Sufficient supporting information
provided with the application to justify location (in respect of retail), with the
proposal complying with policy DP5 and DP7. Proposal is an acceptable
departure from Elgin I7, policy DP1 and policy EP5 – Open Space with regard
to site layout due to constraints from the pylon that passes through the site. 
Developer Obligations – No obligations sought. 
Moray Flood Risk Management – No objections following revision to drainage
arrangement. 
Transport Scotland – No objections. 
SSEN Transmissions – Proposed arrangement offers sufficient
distance/separation between operations proposed as part of this development
and the safe operation of the 132Kv overhead transmission that passes through
the site.
Page 154

Page 155

Aberdeenshire Council Archaeology Service – No objections. 
7. OBJECTIONS-REPRESENTATIONS 
NOTE: Following the determination of this application, name and address
details will be/have been removed (i.e. redacted) in accordance with the
General Data Protection Regulations (paragraph 3 of Minute, Planning &
Regulatory Services Committee 16 September 2014). 
Issue: Object on the basis Use Class 1 (Shops) would not be ancillary to Use
Class 6 (Storage and Distribution), but the driver of the need for such storage
and distribution, and this is contrary to Barmuckity Business Park Strategic
Framework 2016 and Moray Local Development Plan 2020 policy DP7 –
Retail/Town Centres.
Comments (PO): The Barmuckity Business Park Strategic Framework has
been superseded by the designation text for site I7 – Barmuckity Business Park
in the Moray Local Development Plan 2020. 
The applicant is an industrial equipment supplies company with branches
across the north of Scotland, including an existing site at Pinefield Industrial
Estate in Elgin. The use of the building is for use class 6 (storage or
distribution) with associated retail. Supporting information provided with the
application states that 95% of their trade is to manufacturing, trade and public
sector, with the remaining 5% of trade to individuals. 90% of orders are placed
by phone/online and delivered. Detailed consideration is given to the suitability
of the proposed use under observations below, which considers the proposal
acceptable under the terms of policy DP7 and the Barmuckity Business Park
designation I7 in which it sits. 
8. OBSERVATIONS 
8.1 Following consideration of the revised draft National Planning Framework 4
which was laid before parliament on 8th November 2022, the draft (yet to be
formally adopted) is to be given no weight in the consideration of planning
applications. Section 25 of the 1997 Act as amended requires applications to
be determined in accordance with the development plan i.e. the adopted Moray
Local Development Plan 2020 (MLDP) unless material considerations indicate
otherwise. The main planning issues are considered below: 
8.2 Principle of Development, Retail Implications (DP5, DP7 and I7)
The site falls within the I7 Barmuckity Business Park designation of the Elgin
Settlement Statement of the MLDP. Policy DP5 requires all development to
comply with relevant sites designations, and on industrial estate designations
notes that such areas are primarily reserved for uses within use classes 4
(business), 5 (general industrial) and 6 (storage or distribution). The site
development requirements of I7 set out criteria for development on the
designation, notably requiring all development to comply with the Barmuckity
Page 155

Page 156

Business Park Strategic Framework as detailed in the MLDP. With regard to
suitable uses, the designation notes the primary function of Barmuckity
Business Park is for uses within use classes 4, 5 and 6. 
8.2.1 The Strategic Framework sets out the expected land use and landscape layout
for the development of the business park, and divides it into 6 areas. The site
subject to this application falls into “Area 2” which specifies a variety of land
uses including those for visiting members of the public, recognising the
prominence of the area due to its frontage to the A96. 
8.2.2 The proposed use of the building is use class 6 (with ancillary retailing under
use class 1) falls within uses deemed acceptable for the location within this
area of the business park designation and Strategic Framework. Consideration
will be given to the various design and siting criteria in the following Design,
Layout and Siting section below. 
8.2.3 Policy DP7 – Retail/Town Centres (part d) makes reference to the requirements
of policy DP5 – Business and Industry with respect to ancillary retailing. Policy
DP5 presumes against retail development on business or industrial areas
unless it is ancillary to the principal use (e.g. wholesale). In such instances
ancillary is defined as being directly linked to the principal use of the unit and
comprising no more than 10% of the floor area up to a total of 1000 sqm.
Anything in excess of this must be assessed via a sequential approach taken in
accordance with town centre first principles. This should identify no other
suitable sites and the proposal should be in accordance with all other relevant
polices and site requirements. 
8.2.4 The proposed retail/showroom element exceeds 10% of the floor area of the
building and is in excess of 1000 sqm, therefore a sequential approach must be
taken. In relation to this matter, the applicant has submitted a supporting
statement with reference to the requirements of policies DP5 and DP7. 
8.2.5 This supporting statement notes that the applicant is an industrial supplies
company with outlets across the north of Scotland, including one in Elgin at
Pinefield Industrial Estate. The applicant would relocate that outlet to this
proposal. 95% of trade from their Elgin branch is to manufacturing, trade and
public sector, with the remaining 5% to individual members of the public. 90%
of all orders are placed by phone/online and delivered. The delivery catchment
takes in a large proportion of North East Scotland between Forres to Peterhead
and southwards to Speyside. The nature of the retail element is such that
goods are on display in a “supermarket” type trade shop where customers can
view stock prior to purchase, and items retailed tend to be higher end
equipment/professional equipment rather than lower end/DIY models, as well
as large bulky industrial supplies. A large volume and variety of stock is held on
site to enable fast delivery to customers, hence why a relatively large
warehouse and trade area is proposed. 
8.2.6 The supporting statement notes that alternative sites to enable expansion of the
Elgin branch were investigated elsewhere in Elgin (including Ashgrove Road
and Chanonry as well as neighbouring land to enable expansion of their
existing site at Pinefield), however attempts at securing these were either
unsuccessful or the land was considered unsuitable for the applicant’s needs.
Page 156

Page 157

The existing site in Pinefield is at full capacity and there is need to provide
sufficient space to expand and allow those customers that do collect purchases
(often in larger commercial vehicles) to park and manoeuvre safely. 
8.2.7 Taking account of the policy requirements of policies DP7 and DP5, the
supporting information accompanying the application is considered to
demonstrate that the proposed unit would be an acceptable development in the
industrial estate designation. The nature of retail involved is related to the main
function of the warehouse premises and is not typical of a town centre. It is also
worth noting that the applicant’s current business operates out of a designated
industrial estate (which would subsequently free up their current premises for
development/other uses, the applicant stating it will make several 140 – 190
sqm units for let to small and medium sized enterprises). 
8.2.8 In light of the foregoing evaluation the proposal is considered to be suitable in
principle, complying with policies DP5 and DP7. 
8.3 Design, Layout and Siting (DP1, I7)
At a high level, policy DP1 – Development Principles requires all development
to be designed and sited at a suitable level and integrated into the surrounding
landscape. With regard to the I7 designation in which the site sits, there are a
number of design and siting criteria within the designation text and Barmuckity
Business Park Strategic Framework to ensure a consistent layout and
landscape framework for all development within the I7 designation. 
8.3.1 The I7 designation and the Framework both set out that the area subject to this
application must have a strong frontage to the A96, with parking provision
contained to the rear of buildings and ensure landscaping is provided to frame
views of the site from the main road. It also notes that sufficient safeguarding
must be provided for overhead power lines that run through the area. 
8.3.2 Scottish and Southern Electricity Networks Transmission were consulted on
this application, and have been involved in discussions with the applicant in
formulating the proposal. There is a recognised requirement for sufficient
safeguarding to be put in place to ensure the safe operation of a transmission
line that runs through the site. Due to the necessary safeguarding area for this,
the area left for development of a building on the corner of the site adjacent to
the roundabout on the A96 leaves little space for a building to be erected. As a
result, the building is positioned to the south of the power line within, and the
yard and storage area for the proposal is located in the north of the site. 
8.3.3 In order to mitigate the impact of the yard being in a relatively prominent
position, the applicant has proposed woodland planting along the edge of the
A96 to allow screening of the site from the road. Whilst this is contrary to the
requirements of the Framework, the position of the power line makes this
arrangement the only feasible arrangement of the plot, where tree screening
must avoid powerlines. On the basis sufficient landscaping/woodland is
proposed for screening (with minimum density specified in recommended
landscaping condition), the proposal can be considered to be an acceptable
departure from the designation requirements (and subsequently policy DP5). 
Page 157

Page 158

8.3.4 With regard to the design of the building itself, the building is typical of an
industrial/commercial building found in an industrial estate. The design
statement notes that in order to ensure it integrates within the landscape, cut
and fill will be used to ensure the building and yard will sit at a relatively lower
level within the site. Along with landscaping and use of a variety of materials on
the north eastern elevation including timber effect cladding on the north eastern
elevation, the building will have a relatively positive frontage when viewed from
the A96. Within the site and in addition to that used on the boundary of the site,
landscaping has been used to break up and define areas of parking for
customers as required in the Framework. Staff parking is contained within the
site with the parking to the north of the building under the pylon area and the
parking to the south sitting at a lower level than the adjacent public road. Whilst
no landscaping has been proposed due to the constraints of the pylon and the
adjacent retaining wall, this is considered to be an acceptable departure from
this requirement of the Framework. 
8.3.5 Overall the proposed design, siting and layout of the building along with
landscaping is considered suitable for this prominent site within the relatively
new business park. Whilst not fully in accordance with the I7 designation
requirements, the proposed layout is considered to be an acceptable departure
from this designation (and subsequently policy DP5) on the basis the
arrangement enables development of the site whilst ensuring the pylon running
through the site is safeguarded. The proposal complies with the I7 designation
and requirements of policy DP1 in all other respects. 
8.4 Open Space (EP5) and Biodiversity (EP2)
Open space including a staff garden/seating area has been provided within the
site, though this is at a rate of 13% of the site area rather than 15% as required
under policy EP5. In this case given the safeguarding area required to the pylon
corridor, provision of staff garden and proposed and adjacent structural
landscaping which would improve the quality of the open space provision, the
slightly lower figure of 13% is considered an acceptable departure from policy
EP5. 
8.4.1 Policy EP2 requires development proposals to, where possible, retain, protect
and enhance all biological interest and provide for their appropriate
management. This also states that proposals for 1000 sqm or more of
commercial floorspace must create new or where appropriate enhance natural
habitats of ecological value. In this case the applicant has proposed bird boxes,
and insect and bee bricks to be used to enhance biodiversity in the
landscaped/woodland areas. These biodiversity measures satisfy the
requirements of policy EP2. 
8.5 Drainage and Sewerage (EP12, EP13)
Policy EP12 Management and Enhancement of the Water Environment sets
out detailed criteria to ensure proposals meet siting, design and servicing
requirements including provision of SuDS. This includes requirements for
surface water from new development to be dealt with in a sustainable manner
that has a neutral effect on the risk of flooding or which reduces the risk of
flooding. It is noted that the building is to be located at a higher position than
the active flood plain to the north west. 
Page 158

Page 159

8.5.1 A Drainage Impact Assessment has been submitted with the application which
details the proposed surface drainage arrangements for the proposed
development. Plans show permeable surfacing, swales and filter trenches
would be used to treat surface water. 
8.5.2 Moray Flood Risk Management have assessed this information, are content
with its findings and have raised no objections to the proposal. The proposal is
considered to comply with the aforementioned policies in respect of surface
water drainage. 
8.5.3 A connection to the foul drainage network is proposed for foul drainage.
Scottish Water have not objected to this, noting sufficient capacity in the local
network and the Moray West Water Treatment Works. The proposal therefore
complies with policy EP13 Foul Drainage. 
8.6 Access and Parking (PP3)
A new access would be formed from the public road to the south west of the
site (Kirkhill Avenue). Suitable access arrangements can therefore be provided
for vehicles, as well as pedestrians and cyclists, noting there is access to the
bus stop to the north west of the site of the A96. Cycle parking has been
proposed on site along with suitable parking for vehicles (including EV charging
provision). The Transportation Manager has raised no objections to this
proposal, subject to conditions in respect of parking and access provision, as
well as a requirement for further structural detail of the retaining wall to the
south of the site. Subject to these conditions, the proposal is considered to
comply with the requirements of policy PP3. 
8.7 Developer Obligations (PP3)
Given the floor area exceeds 1000 sqm, the development is potentially subject
to developer obligations under policy PP3 and the associated Developer
Obligations Supplementary Guidance. In this case the proposal is not liable to
pay any obligations. 
8.8 Environmental Impact Assessment – Screening Opinion
Upon valid submission this application was screened by Moray Council (as
competent authority) under regulation 11 of The Town and Country Planning
(Environmental Impact Assessment) (Scotland) Regulations 2017 to determine
whether or not Environmental Impact Assessment (EIA) was required. 
8.8.1 On 4 April 2022 Moray Council adopted a screening opinion stating EIA was
not required for this proposal. 
Recommendation 
Approve. 
REASON(S) FOR DECISION
The Council’s reason(s) for making this decision are: - 
Whilst not fully in accordance with the Elgin I7 Barmuckity Business Park
designation requirements of the Moray Local Development Plan 2020, where
by the layout does not present an active frontage to the A96, the proposed
layout is considered to be an acceptable departure from this designation (and
Page 159

Page 160

subsequently policies DP5 – Business and Industry and DP1 Development
Principles) on the basis the arrangement enables development of the site whilst
ensuring the pylon running through the site is safeguarded. 
The proposed open space provision falls below the 15% required for new
industrial sites (13% in this case) as required under policy EP5 – Open Space.
However given the safeguarding area required to the pylon corridor, the
proposed hedge planting outwith the site, provision of staff garden and subject
to revised planting details being provided for the woodland strip which would
improve the quality of the open space provision, the proposal is therefore an
acceptable departure from policy EP5. 
The proposal complies with all other relevant policies of the development plan
and there are no material considerations that indicate otherwise.   
Author/Contact
Officer:
Andrew Miller            
Senior Planning Officer
Ext: 01343 563274 
Beverly Smith
Development Management & Building Standards Manager 
Page 160

Page 161

APPENDIX 
POLICY 
Moray Local Development Plan 2020 
I7   Barmuckity Business Park Industrial Estate 
• Proposals must comply with the Barmuckity Business Park Strategic Framework
shown on page 153.
• Barmuckity's primary function is for Class 4 Business, Class 5 General Industrial and
Class 6 Storage or Distribution. A minimum of 14.69 ha* is reserved for these uses. 
• A greater mix of uses is supported across 7.41 ha* of the site; these areas are
adjacent to the A96 and are shown within the Barmuckity Business Park Strategic
Framework as areas 2, 3 and 6. Within these areas Use Class 4 Business, Class 5
General Industrial, Class 6 Storage or Distribution, Class 7 Hotel and Hostels, and
Class 11 Assembly and Leisure are supported subject to other policies including
policy DP7. Retailing may be acceptable where retailing is ancillary to the main use. 
• An access strategy is required to be agreed with Transport Scotland for Phase 2
(west) of the development.
• Positive frontages onto the A96 must be provided and the quality of design must
reflect the key gateway to Elgin. 
• Vehicular connection over the railway line to be retained/provided to Moss of
Barmuckity to the south.
• A vehicular connection to the south to be safeguarded to enable future provision of
access to Elgin South development.
• Strategic and boundary landscaping must be provided in compliance with the
approved Landscape Design for Elgin Business Park - Phase 1 submitted to the
Council on 30th May 2018. Phase 2 landscaping to be in compliance with the
Strategic Framework.
• Individual proposals on plots within the wider site must provide a landscape and
maintenance plan. Landscaping must complement the strategic and boundary
landscaping in the relevant area. Landscaping must be used to define plots.   
• Level 2 Flood Risk Assessment (FRA) required. No development within the
functional floodplain. No development within 6m of the watercourses. 
• Areas at risk from flooding must be made a landscape feature to provide biodiversity
and a high amenity setting for development. 
• Drainage Impact Assessment (DIA) required. 
• Phase 1 Habitat Survey required. 
• A Water Framework Directive waterbody specific objective will require to be
addressed.
• Footpath and cycle connections within and to outwith the site required.  
(*This is a net area which excludes landscaping, areas at risk of flooding etc.) 
PP3  INFRASTRUCTURE & SERVICES
Development must be planned and co-ordinated with infrastructure to ensure that places
function properly and proposals are adequately served by infrastructure and services.   
Page 161

Page 162

a) In relation to infrastructure and services developments will be required to provide the
following as may be considered appropriate by the planning authority, unless these
requirements are considered not to be necessary: 
i)  Education, Health, Transport, Sports and Recreation and Access facilities in
accord with Supplementary Guidance on Developer Obligations and Open
Space. 
ii)  Green infrastructure and network requirements specified in policy EP5 Open
Space, Town and Village Maps and, contained within Supplementary Guidance
on the Open Space Strategy, Masterplans and Development Briefs. 
iii)  Mitigation/modification to the existing transport network (including road and rail)
to address the impact of the proposed development in terms of safety and
efficiency.  This may include but not be limited to passing places, road
widening, junction enhancement, bus stop infrastructure, and drainage
infrastructure.  A number of potential road and transport improvements are
identified and shown on the Town and Village Maps as Transport Proposals
(TSP's) including the interventions in the Elgin Transport Strategy. These
requirements are not exhaustive and do not pre-empt any measures which may
result from the Transport Assessment process. 
iv)  Electric car charging points must be provided at all commercial and community
parking facilities.  Access to charging points must also be provided for
residential properties, where in-curtilage facilities cannot be provided to any
individual residential property then access to communal charging facilities
should be made available.  Access to other nearby charging facilities will be
taken into consideration when identifying the need for communal electric
charging points. 
v)  Active Travel and Core Path requirements specified in the Council's Active
Travel Strategy and Core Path Plan. 
vi)  Safe transport and access routes linking to existing networks and mitigating the
impacts of development off-site. 
vii)  Information Communication Technology (ICT) and fibre optic broadband
connections for all premises unless justification is provided to substantiate it is
technically unfeasible. 
viii)  Foul and surface water drainage, including Sustainable Urban Drainage
Systems (SUDS), including construction phase SUDS. 
ix)  Measures that implement the waste management hierarchy as defined in the
Zero Waste Plan for Scotland including the provision of local waste storage and
recycling facilities designed into the development in accord with policy PP1
Placemaking.  For major applications a site waste management plan may be
required to ensure that waste minimisation is achieved during the construction
phase. 
Page 162

Page 163

x)  Infrastructure required to improve or increase capacity at Water Treatment
Works and Waste Water Treatment Works will be supported subject to
compliance with policy DP1. 
xi) A utilities plan setting out how existing and new utility (including gas, water,
electricity pipelines and pylons) provision has been incorporated into the layout
and design of the proposal.  This requirement may be exempted in relation to
developments where the council considers it might not be appropriate, such as
domestic or very small scale built developments and some changes of use. 
b)  Development proposals will not be supported where they:
i)  Create new accesses onto trunk roads and other main/key routes (A941 & A98)
unless significant economic benefits are demonstrated or such access is
required to facilitate development that supports the provisions of the
development plan. 
ii)  Adversely impact on active travel routes, core paths, rights of way, long
distance and other access routes and cannot be adequately mitigated by an
equivalent or better alternative provision in a location convenient for users. 
iii)  Adversely impact on blue/green infrastructure, including green networks
important for wildlife unless an equivalent or better alternative provision will be
provided. 
iv)  Are incompatible with key waste sites at Dallachy, Gollanfield, Moycroft and
Waterford and would prejudice their operation. 
v)  Adversely impact on community and recreational sites, buildings or
infrastructure including CF designations and cannot be adequately mitigated. 
vi)  Adversely impact on flood alleviation and mitigation infrastructure. 
vii)  Compromise the economic viability of bus or rail facilities.   
c)  Harbours 
Development within and diversification of harbours to support their sustainable
operation will be supported subject to compliance with other policies and settlement
statements. 
d)  Developer Obligations 
Developer obligations will be sought to mitigate any measurable adverse impact of a
development proposal on local infrastructure, including education, healthcare,
transport (including rail), sports and recreational facilities and access routes. 
Obligations will be sought to reduce, eliminate or compensate for this impact.
Developer obligations may also be sought to mitigate any adverse impacts of a
development, alone or cumulatively with other developments in the area, on the
natural environment. 
Where necessary obligations that can be secured satisfactorily by means of a
planning condition attached to planning permission will be done this way.  Where this
cannot be achieved, the required obligation will be secured through a planning
agreement in accordance with Circular 3/2012 on Planning Obligations.  
Page 163

Page 164

Developer obligations will be sought in accordance with the Council's Supplementary
Guidance on Developer Obligations.  This sets out the anticipated infrastructure
requirements, including methodology and rates.   
Where a developer considers that the application of developer obligations renders a
development commercially unviable a viability assessment and 'open-book
accounting' must be provided by the developer which Moray Council, via the District
Valuer, will verify, at the developer's expense.  Should this be deemed accurate then
the Council will enter into negotiation with the developer to determine a viable level
of developer obligations.   
The Council's Developer Obligations Supplementary Guidance provides further detail
to support this policy. 
DP1 DEVELOPMENT PRINCIPLES 
This policy applies to all development, including extensions and conversions and will be
applied reasonably taking into account the nature and scale of a proposal and individual
circumstances. 
The Council will require applicants to provide impact assessments in order to determine
the impact of a proposal. Applicants may be asked to determine the impacts upon the
environment, transport network, town centres, noise, air quality, landscape, trees, flood
risk, protected habitats and species, contaminated land, built heritage and archaeology
and provide mitigation to address these impacts. 
Development proposals will be supported if they conform to the relevant Local
Development Plan policies, proposals and additional guidance, meet the following criteria
and address their individual and cumulative impacts: 
(i) Design
a) The scale, density and character must be appropriate to the surrounding area
and create a sense of place (see Policy PP1) and support the principles of a
walkable neighbourhood. 
b) The development must be integrated into the surrounding landscape which will
include safeguarding existing trees and undertaking replacement planting to
include native trees for any existing trees that are felled, and safeguarding any
notable topographical features (e.g. distinctive knolls), stone walls and existing
water features by avoiding channel modifications and culverting. A tree survey
and tree protection plan must be provided with planning applications for all
proposals where mature trees are present on site or that may impact on trees
outwith the site. The strategy for new tree provision should follow the principles
of the "Right Tree in the Right Place". 
c) Make provision for new open space and connect to existing open space under
the requirements of Policy EP5 and provide details of the future maintenance of
these spaces. A detailed landscape plan must be submitted with planning
applications and include information about green/blue infrastructure, tree
species, planting, ground/soil conditions, and natural and man-made features
(e.g. grass areas, wildflower verges, fencing, walls, paths, etc.).
Page 164

Page 165

d) Demonstrate how the development will conserve and enhance the natural and
built environment and cultural heritage resources, retain original land contours
and integrate into the landscape. 
e) Proposals must not adversely impact upon neighbouring properties in terms of
privacy, daylight or overbearing loss of amenity. 
f)  Proposals do not result in backland development or plots that are subdivided by
more than 50% of the original plot.  Sub-divided plots must be a minimum of
400m2, excluding access and the built-up area of the application site will not
exceed one-third of the total area of the plot and the resultant plot density and
layout reflects the character of the surrounding area. 
g)  Pitched roofs will be preferred to flat roofs and box dormers are not acceptable. 
h)  Existing stone walls on buildings and boundaries must be retained. 
Alterations and extensions must be compatible with the character of the
existing building in terms of design, form, choice of materials and positioning
and meet all other relevant criteria of this policy. 
i)  Proposals must orientate and design buildings to maximise opportunities for
solar gain. 
j)  All developments must be designed so as to ensure that all new buildings avoid
a specified and rising proportion of the projected greenhouse gas emissions
from their use (calculated on the basis of the approved design and plans for the
specific development) through the installation and operation of low and zero-
carbon generating technologies. 
(ii) Transportation
a) Proposals must provide safe entry and exit from the development, including the
appropriate number and type of junctions, maximise connections and routes for
pedestrians and cyclists, including links to active travel and core path routes,
reduce travel demands and ensure appropriate visibility for all road users at
junctions and bends. Road, cycling, footpath and public transport connections
and infrastructure must be provided at a level appropriate to the development
and connect people to education, employment, recreation, health, community
and retail facilities. 
b) Car parking must not dominate the street scene and must be provided to the
side or rear ¬and behind the building line. Maximum (50%) parking to the front
of buildings and on street may be permitted provided that the visual impact of
the parked cars is mitigated by hedging or low stone boundary walls. Roadways
with a single carriageway must provide sufficient off road parking to avoid
access routes being blocked to larger service vehicles and prevent parking on
pavements. 
c) Provide safe access to and from the road network, address any impacts on
road safety and the local road, rail and public transport network. Any impacts
identified through Transport Assessments/ Statements must be identified and
mitigated. This may include but would not be limited to, passing places, road
Page 165

Page 166

widening, junction improvements, bus stop infrastructure and drainage
infrastructure. A number of potential mitigation measures have been identified
in association with the development of sites and the most significant are shown
on the Proposals Map as TSP's. 
d) Provide covered and secure facilities for cycle parking at all flats/apartments,
retail, community, education, health and employment centres. 
e) Garages and parking provision must be designed to comply with Moray Council
parking specifications see Appendix 2. 
f)  The road layout must be designed to allow for the efficient mechanical
sweeping of all roadways and channels, paviors, turning areas and junctions.
The road layout must also be designed to enable safe working practices,
minimising reversing of service vehicles, with hammerheads minimised in
preference to turning areas such as road stubs or hatchets, and to provide
adequate space for the collection of waste and movement of waste collection
vehicles. 
g) The road and house layout in urban development should allow for communal
refuse collection points where the design does not allow for individual storage
within the curtilage and / or collections at kerbside. Communal collection points
may either be for the temporary storage of containers taken by the individual
householder or for the permanent storage of larger containers. The
requirements for a communal storage area are stated within the Council's
Kerbside Collection Policy, which will be a material consideration. 
h) Road signs should be minimised designed and placed at the back of footpaths
to reduce street clutter, avoid obstructing pedestrian movements and
safeguarding sightlines; 
i)  Within communal parking areas there will be a requirement for electric car
charging points. Parking spaces for car sharing must be provided where a need
is identified by the Transportation Manager. 
(iii) Water environment, pollution, contamination
a) Acceptable water and drainage provision must be made, including the use of
sustainable urban drainage systems (SUDS) for dealing with surface water
including temporary/ construction phase SUDS (see Policy EP12). 
b) New development should not be located in areas at flood risk or increase
vulnerability to flooding (see Policy EP12). Exceptions to this would only be
considered in specific circumstances, e.g. extension to an existing building or
change of use to an equal or less vulnerable use. Where this exception is
applied the proposed development must include resilience measures such as
raised floor levels and electrical sockets. 
c) Proposals must avoid major hazard sites and address any potential risk of
pollution including ground water contamination in accordance with recognised
pollution prevention and control measures. 
Page 166

Page 167

d) Proposals must protect and wherever practicable enhance water features
through for example naturalisation of watercourses by introducing a more
natural planform and removing redundant or unnecessary structures. 
e) Proposals must address and sufficiently mitigate any contaminated land issues. 
f)  Make acceptable arrangements for waste collection and management and
encourage recycling. 
g) Avoid sterilising significant workable reserves of minerals, prime agricultural
land or productive forestry. 
h)  Proposals must avoid areas at risk of coastal erosion and coastal change. 
DP5 BUSINESS & INDUSTRY
a) Development of employment land is supported to deliver the aims of the Moray
Economic Strategy.  A hierarchical approach will be taken when assessing proposals
for business and industrial uses. New and existing employment designations are set
out in Settlement Statements and their description identifies where these fall within
the policy hierarchy. 
Proposals must comply with Policy DP1, site development requirements within town
and village statements, and all other relevant policies within the Plan. Office
development that will attract significant numbers of people must comply with Policy
DP7 Retail/Town Centres. 
Efficient energy and waste innovations should be considered and integrated within
developments wherever possible. 
b) Business Parks 
Business parks will be kept predominantly for 'high-end' businesses such as those
related to life sciences and high technology uses.  These are defined as Class 4
(business) of the Town and Country Planning (Use Classes) (Scotland) Order 1997.
This applies to new proposals as well as redevelopment within established Business
Parks. 
Proposals for the development of new business parks must adhere to the key design
principles set out in town statements or Development Frameworks adopted by the
Council.   
c) Industrial Estates 
Industrial Estates will be primarily reserved for uses defined by Classes 4 (business),
5 (general) and 6 (storage and distribution) of the Town and Country Planning (Use
Classes) (Scotland) Order 1997. This applies to new proposals as well as
redevelopment within established Industrial Estates.  Industrial Estates could be
suitable sites for waste management facilities.   
d) Existing Business Areas 
Long established business uses will be protected from non-conforming uses (e.g.
housing).  The introduction or expansion of non-business uses (e.g. retail) will not be
permitted, except where the total redevelopment of the site is proposed.   
Page 167

Page 168

e) Other Uses 
Class 2 (business and financial), 3 (food and drink), 11 (assembly and leisure) and
activities which do not fall within a specific use class (sui generis), including waste
management facilities will be considered in relation to their suitability to the business
or industrial area concerned, their compatibility with neighbouring uses and the
supply of serviced employment land.  Retail uses will not be permitted unless they
are considered ancillary to the principal use (e.g. manufacture, wholesale).  For this
purpose, 'ancillary' is taken as being linked directly to the existing use of the unit and
comprising no more than 10% of the total floor area up to a total of 1,000 sq metres
(gross) or where a sequential approach in accordance with town centre first
principles has identified no other suitable sites and the proposal is in accordance
with all other relevant policies and site requirements are met. 
f) Areas of Mixed Use 
Proposals for a mix of uses where site specific opportunities are identified within
Industrial Estate designations in the Settlement Statement, will be considered
favourably where evidence is provided to the authority's satisfaction that the
proposed mix will enable the servicing of employment land and will not compromise
the supply of effective employment land.  A Development Framework that shows the
layout of the whole site, range of uses, landscaping, open space and site specific
design requirements must be provided. The minimum levels of industrial use
specified within designations must be achieved on the rest of the site. 
g) Rural Businesses and Farm Diversification 
Proposals for new business development and extensions to existing businesses in
rural locations including tourism and distillery operations will be supported where
there is a locational need for the site and the proposal is in accordance with all other
relevant policies. 
A high standard of design appropriate to the rural environment will be required and
proposals involving the rehabilitation of existing properties (e.g. farm steadings) to
provide business premises will be encouraged. 
Outright retail activities will be considered against policy DP7, and impacts on
established shopping areas, but ancillary retailing (e.g. farm shop) will generally be
acceptable. 
Farm diversification proposals and business proposals that will support the economic
viability of the farm business are supported where they meet the requirements of all
other relevant Local Development Plan policies. 
h) Inward Investment Sites 
The proposals map identifies a proposed inward investment site at Dallachy which is
safeguarded for a single user business proposal seeking a large (up to 40ha), rural
site. Additional inward investment sites may be identified during the lifetime of the
Plan. 
Proposals must comply with Policy DP1 and other relevant policies. 
EP2 BIODIVERSITY
All development proposals must, where possible, retain, protect and enhance features of
biological interest and provide for their appropriate management.  Development must
Page 168

Page 169

safeguard and where physically possible extend or enhance wildlife corridors and
green/blue networks and prevent fragmentation of existing habitats. 
Development should integrate measures to enhance biodiversity as part of multi-functional
spaces/ routes. 
Proposals for 4 or more housing units or 1000 m2 or more of commercial floorspace must
create new or, where appropriate, enhance natural habitats of ecological and amenity
value. 
Developers must demonstrate, through a Placemaking Statement where required by
Policy PP1 which incorporates a Biodiversity Plan, that they have included biodiversity
features in the design of the development. Habitat creation can be achieved by providing
links into existing green and blue networks, wildlife friendly features such as wildflower
verges and meadows, bird and bat boxes, amphibian friendly kerbing, wildlife crossing
points such as hedgehog highways and planting to encourage pollination, wildlife friendly
climbing plants, use of hedges rather than fences, incorporating biodiversity measures into
SUDS and retaining some standing or lying dead wood, allotments, orchards and
woodlands. 
Where development would result in loss of natural habitats of ecological amenity value,
compensatory habitat creation will be required where deemed appropriate. 
EP5 OPEN SPACE
a)  Existing Open Space (ENV's and Amenity Land)
Development which would result in a change of use of a site identified under the
ENV designation in settlement statements or amenity land designations in rural
groupings to anything other than open space use will be refused. Proposals that
would result in a change of use of an ENV4 Sports Area to any other use (including
other ENV categories) will be refused. The only exceptions are where the proposal is
for essential community infrastructure required to deliver the key objectives of the
Council and its Community Planning Partners, excluding housing, or for a site
specific opportunity identified within the settlement statement. Where one of these
exceptions applies, proposals must: 
• Be sited and designed to minimise adverse impacts on the principal function of
the space and the key qualities and features identified in the Moray Open
Space Strategy Supplementary Guidance. 
• Demonstrate that there is a clear excess of the type of ENV and the loss of the
open space will not negatively impact upon the quality, accessibility and
quantity of open space provision and does not fragment green networks (with
reference to the Moray Open Space Strategy Supplementary Guidance, green
network mapping and for ENV4 Sports Area in consultation with SportScotland)
or replacement open space provision of equivalent function, quality and
accessibility is made. 
The temporary use of unused or underused land as green infrastructure is
encouraged, this will not prevent any future development potential which has been
identified from being realised. Proposals that would result in a change of use of an
ENV4 Sports Area to any other use (including other ENV categories) will be refused. 
Page 169

Page 170

Proposals for allotments or community growing on existing open space will be
supported where they do not adversely affect the primary function of the space or the
key qualities and features identified in the Moray Open Space Strategy
Supplementary Guidance and a locational requirement has been identified in the
Council's Food Growing Strategy. Consideration will include related aspects such as
access, layout, design and car parking requirements. 
Any new/proposed extension to existing cemetery sites requiring an intrusive ground
investigation must be undertaken in accordance with SEPA's guidance on assessing
the impacts of cemeteries on groundwater before any development occurs at the
site. 
Areas identified in Settlement Statements as ENV are categorised based on their
primary function as set out below. These are defined in the Open Space Strategy
Supplementary Guidance. 
ENV 1 Public Parks and Gardens
ENV 2  Amenity Greenspace
ENV 3  Playspace for children and teenagers
ENV 4  Sports Areas
ENV 5  Green Corridors 
ENV 6  Natural/Semi-Natural Greenspace
ENV 7  Civic Space 
ENV 8  Allotments
ENV 9  Cemeteries and proposed extensions
ENV 10 Private Gardens and Grounds 
ENV 11 Other Functional Greenspace 
b) Green Infrastructure and Open Space in New Development
New development must incorporate accessible multifunctional open space of
appropriate quantity and quality to meet the needs of development and must provide
green infrastructure to connect to wider green/blue networks. In Elgin, Buckie and
Forres green infrastructure must be provided as required in the green network
mapping. Blue drainage infrastructure will require to be incorporated within green
open space. The blue-green context of the site will require to be considered from the
very outset of the design phase to reduce fragmentation and maximize  the multi-
benefits arising from this infrastructure. 
Open space provision in new developments must meet the accessibility, quality and
quantity standards set out below and meet the requirements of policy PP1
Placemaking, EP2 Biodiversity, other relevant policies and any site specific
requirements within the Settlement Statements.  Developers must demonstrate
through a Placemaking Statement that they have considered these standards in the
design of the open space, this must include submission of a wider analysis plan that
details existing open space outwith the site, key community facilities in the area and
wider path networks. 
i) Accessibility Standard 
Everyone will live within a five minute walk of a publicly usable space of at least
0.2ha. 
Page 170

Page 171

ii) Quality Standard 
All new development proposals will be assessed and must achieve a very good
quality score of no less than 75%. Quality will be assessed by planning officers
at the planning application stage against the five criteria below using the bullet
point prompts.  Each criterion will be scored on a scale of 0 (poor) to 5 (very
good) with an overall score for the whole development expressed as a
percentage. 
Accessible and well connected
• Allows movement in and between places, consideration to be given to
reflecting desire lines, permeable boundaries, and multiple access points 
• Accessible entrances in the right places. 
• Accessible for all generations and mobility's, including consideration of
gradient and path surfaces. 
• Provide appropriately surfaced, inclusive, high quality paths. 
• Connects with paths, active travel routes and other transport modes
including bus routes.
• Offers connecting path network with legible waymarking and signage. 
Attractive and Appealing Places
• Attractive with positive image created through character and quality
elements. 
• Attractive setting for urban areas.
• Quality materials, equipment and furniture.
• Attractive plants and landscape elements that support character, including
providing seasonal and sensory variation and food production. 
• Welcoming boundaries and entrance areas. 
• Adequate bin provision.
• Long term maintenance measures in place.¬ 
Biodiverse supporting ecological networks (see Policy EP2 Biodiversity)
• Contribute positively to biodiversity through the creation of new natural
habitats for ecological and amenity value.  
• Large enough to sustain wildlife populations, including green/blue
networks and landscaping.   
• Offers a diversity of habitats. 
• Landscaping and open space form part of wider landscape structure and
setting.
• Connects with wider blue/green networks Provide connections to existing
green/bue networks and avoids fragmentation of existing habitats. 
• Ensure a balance between areas managed positively for biodiversity and
areas managed primarily for other activities e.g. play, sport.
• Resource efficient, including ensuring open space has a clear function
and is not "left over". 
Promotes activity, health and well being
• Provides multifunctional open space for a range of outdoor physical
activities reflecting user needs and location. 
• Provides diverse play, sport, and recreational facilities for a range of ages
and user groups.
• Providing places for social interaction, including supporting furniture to
provide seating and resting opportunities.  
Page 171

Page 172

• Appropriate high quality facilities meeting needs and reflecting the site
location and site. 
• Carefully sited facilities for a range of ages with consideration to be given
to existing facilities, overlooking, and ease of access for users. 
• Open space is flexible to accommodate changing needs. 
Safe, Welcoming and contributing to Character and Identity
• Safe and welcoming.
• Good levels of natural surveillance.
• Discourage anti-social behaviour.
• Appropriate lighting levels. 
• Sense of local identity and place. 
• Good routes to wider community facilities e.g connecting to schools,
shops, or transport nodes.
• Distinctive and memorable places that support local culture and
identity.¬¬
• Catering for a range of functions and activities providing a multi-functional
space meeting needs.
• Community involvement in management. 
b iii) Quantity Standard
Unless otherwise stated in site designations, the following quantity standards
will apply.
• Residential sites less than 10 units - landscaping to be determined under
the terms of Policy DP1 Development Principles to integrate the new
development.
• Residential sites 10-50 units and new industrial sites- minimum 15% open
space
• Residential sites 51-200 units- minimum 20% open space
• Residential sites 201 units and above and Business Parks- minimum 30%
open space which must include allotments, formal parks and playspaces
within residential sites. 
In meeting the quantity requirements, only spaces which have a clear multi
benefit function will be counted. Structure and boundary landscaping areas
must make provision for public access and link into adjacent green corridors.
The quantity standard must be met within the designation boundaries. For
windfall sites the quantity standard must be new open space provision within
the application boundaries. 
Open Spaces approved in new developments will be classed as ENV spaces
upon granting of consent. 
Proposals must also comply with the Council's Open Space Strategy
Supplementary Guidance. 
EP12 MANAGEMENT AND ENHANCEMENT OF THE WATER ENVIRONMENT
a) Flooding
New development will not be supported if it would be at significant risk of flooding
from any source or would materially increase the possibility of flooding elsewhere.
For development at or near coastal locations, this includes consideration of future
Page 172

Page 173

flooding that may be caused by sea level rise and/or coastal change eroding existing
natural defences in the medium and long term. 
Proposals for development in areas considered to be at risk from flooding will only be
permitted where a flood risk assessment to comply with the recommendations of
Scottish Planning Policy and to the satisfaction of Scottish Environment Protection
Agency and the Council is provided by the applicant. 
There are different levels of flood risk assessment dependent on the nature of the
flood risk. The level of assessment should be discussed with the Council prior to
submitting a planning application. 
Level 1 -  a flood statement with basic information with regard to flood risk.
Level 2 -  full flood risk assessment providing details of flood risk from all sources,
results of hydrological and hydraulic studies and any appropriate
proposed mitigation. 
Assessments must demonstrate that the development is not at risk of flooding and
would not increase the probability of flooding elsewhere.  Level 2 flood risk
assessments must be signed off by a competent professional.  The Flood Risk
Assessment and Drainage Impact Assessment for New Development Supplementary
Guidance provides further detail on the information required. 
Due to continuing changes in climatic patterns, the precautionary principle will apply
when reviewing any application for an area at risk from inundation by floodwater.
Proposed development in coastal areas must consider the impact of tidal events and
wave action when assessing potential flood risk. 
The following limitations on development will also be applied to take account of the
degree of flooding as defined in Scottish Planning Policy;
a) In areas of little to no risk (less than 0.1%), there will be no general constraint to
development.
b) Areas of low to medium risk (0.1% to 0.5%) will be considered suitable for most
development. A flood risk assessment may be required at the upper end of the
probability range i.e. (close to 0.5%) and for essential civil infrastructure and the
most vulnerable uses. Water resistant materials and construction may be
required. Areas within this risk category will generally not be suitable for civil
infrastructure. Where civil infrastructure must be located in these areas or is
being substantially extended, it should be designed to be capable of remaining
operational and accessible during flooding events.
c) Areas of medium to high risk (0.5% or above) may be suitable for:
• Residential, institutional, commercial and industrial development within
built up areas provided that flood protection measures to the appropriate
standard already exist and are maintained, are under construction, or are
a planned measure in a current flood management plan.
• Essential infrastructure within built up areas, designed and constructed to
remain operational during floods and not impede water flow.
• Some recreational, sport, amenity and nature conservation uses, provided
appropriate evacuation procedures are in place, and
• Employment related accommodation e.g. caretakers or operational staff. 
Page 173

Page 174

Areas within these risk categories will generally not be suitable for the following
uses and where an alternative/lower risk location is not available¬¬;
• Civil infrastructure and most vulnerable uses.
• Additional development in undeveloped and sparsely developed areas,
unless a location is essential for operational reasons e.g. for navigation
and water based recreation, agriculture, transport or utilities infrastructure
(which should be designed to be operational during floods and not impede
water flows).
• New caravan and camping sites 
Where development is permitted, measures to protect against or manage flood
risk will be required and any loss of flood storage capacity mitigated to achieve
a neutral or better outcome. Water resistant materials and construction must be
used where appropriate. Land raising and elevated buildings on structures such
as stilts are unlikely to be acceptable. 
b) Surface Water Drainage: Sustainable Urban Drainage Systems (SUDS)
Surface water from development must be dealt with in a sustainable manner that has
a neutral effect on flooding or which reduces the risk of flooding. The method of
dealing with surface water must also avoid pollution and promote habitat
enhancement and amenity. All sites must be drained by a sustainable drainage
system (SUDS) designed in line with current CIRIA guidance. Drainage systems
must contribute to enhancing existing "blue" and "green" networks while contributing
to place-making, biodiversity, recreational, flood risk and climate change objectives. 
When considering the appropriate SUDS design for the development the most
sustainable methods, such as rainwater harvesting, green roofs, bio retention
systems, soakaways, and permeable pavements must be considered first.  If it is
necessary to include surface water attenuation as part of the drainage system, only
above ground attenuation solutions will be considered, unless this is not possible
due to site constraints.   
If below ground attenuation is proposed the developer must provide a robust
justification for this proposal.  Over development of a site or a justification on
economic grounds will not be acceptable.  When investigating appropriate SUDS
solutions developers must integrate the SUDS with allocated green space, green
networks and active travel routes to maximise amenity and biodiversity benefits. 
Specific arrangements must be made to avoid the issue of permanent SUDS
features becoming silted-up with run-off. Care must be taken to avoid the spreading
and/or introduction of invasive non-native species during the construction of all
SUDS features.  On completion of SUDS construction the developer must submit a
comprehensive Operation and Maintenance Manual.  The ongoing maintenance of
SUDS for all new development will be undertaken through a factoring agreement, the
details of which must be supplied to the Planning Authority.   
All developments of less than 3 houses or a non-householder extension under 100
square metres must provide a Drainage Statement.  A Drainage Assessment will be
required for all developments other than those identified above. 
Page 174

Page 175

c) Water Environment
Proposals, including associated construction works, must be designed to avoid
adverse impacts upon the water environment including Ground Water Dependent
Terrestrial Ecosystems and should seek opportunities for restoration and/or
enhancement, if appropriate. The Council will only approve proposals impacting on
water features where the applicant provides a report to the satisfaction of the Council
that demonstrates that any impact (including cumulative) on water quality, water
quantity, physical form (morphology), river hydrology, sediment transport and
erosion, coastal processes (where relevant) nature conservation (including protected
species), fisheries, recreational, landscape, amenity and economic and social impact
can be adequately mitigated. 
The report must consider existing and potential impacts up and downstream of the
development particularly in respect of potential flooding. The Council operates a
presumption against the culverting of watercourses and any unnecessary
engineering works in the water environment. 
A buffer strip of at least 6 metres between any new development and all water
features is required and should be proportional to the bank width and functional river
corridor (see table on page 96). This must achieve the minimum width within the
specified range as a standard, however, the actual required width within the range
should be calculated on a case by case basis by an appropriately qualified individual.
These must be designed to link with blue and green networks, including appropriate
native riparian vegetation and can contribute to open space requirements. 
Developers may be required to make improvements to the water environment as part
of the development. Where a Water Framework Directive (WFD)¬ water body
specific objective is within the development boundary, or in proximity, developers will
need to address this within the planning submission through assessment of potential
measures to address the objective and implementation, unless adequate justification
is provided. Where there is no WFD objective the applicant should still investigate
the potential for watercourse restoration along straightened sections or removal of
redundant structures and implement these measures where viable. 
Width to watercourse Width of buffer strip (either side)
(top of bank) 
Less than 1m  6m
1-5m 6-12m
5-15m 12-20m
15m+ 20m+ 
The Flood Risk Assessment and Drainage Impact Assessment for New Development
Supplementary Guidance provides further detail on the information required to
support proposals. 
EP13 FOUL DRAINAGE 
All development within or close to settlements (as defined in the Local Development Plan)
of more than 2,000 population must connect to the public sewerage system unless
connection  is not permitted due to lack of capacity. In such circumstances, temporary
provision of private sewerage systems may be allowed provided Scottish Water has
Page 175

Page 176

confirmed investment to address this constraint has been allocated within its investment
Programme and the following requirements have been met; 
• Systems must not have an adverse effect on the water environment
• Systems must be designed and built to a standard which will allow adoption by
Scottish Water
• Systems must be designed such that they can be easily connected to a public sewer
in the future. Typically this will mean providing a drainage line up to a likely point of
connection. 
All development within or close to settlements (as above) of less than 2,000 population will
require to connect to public sewerage except where a compelling case is made otherwise.
Factors to be considered in such a case will include size of the proposed development,
whether the development would jeopardise delivery of public sewerage infrastructure and
existing drainage problems within the area. 
Where a compelling case is made, a private system may be acceptable provided it does
not pose or add a risk of detrimental effects, including cumulative, to the natural and built
environment, surrounding uses or amenity of the general area. 
Where a private system is deemed to be acceptable, within settlements as above or small
scale development in the countryside, a discharge to land, either full soakaway or raised
mound soakaway, compatible with Technical Handbooks (which sets out guidance on how
proposals may meet the Building  Regulations) must be explored prior to considering a
discharge to surface waters. 
Page 176

Page 177

WARD 02_17 
22/00563/APP
12 April 2022
Erection of 3 Wind Turbines (at max height 149.9 metre
to blade tip), control building and substation and
formation of access tracks (including turning heads),
hardstanding, temporary construction compound and
associated works and infrastructure at Lurg Hill
Deskford Moray for Vento Ludens Ltd 
Comments: 
 The appointed officer considers the matter raises matters of wider community
interest and/or planning significance by virtue of the scale or height of the
turbines, which exceed 40 metre (to blade tip). 
 Advertised as a departure from the development plan, under Schedule 3 of the
Development Management Regulations 2013 and for neighbour notification
purposes. 
 2 letters of objection have been received. 
Procedure: 
 None. 
Recommendation Grant Planning Permission - Subject to the following: 
Conditions/Reasons 
1. The development to which this permission relates must be begun not later than
the expiration of 5 years beginning with the date on which the permission is
granted. 
Reason: The time limit condition is imposed in order to comply with the
requirements of section 58 of the Town and Country Planning (Scotland) Act 1997
as amended. 
2. The permission as hereby granted is for a period of 35 years from the date when
electricity is first exported from any wind turbine within the development to the
electricity grid network (First Export Date), and written confirmation of this First
Export Date shall be provided to the Council, as planning authority within one
month thereof. 
Reason: To define the duration of the permission. 
Item 9
Page 177

Page 178

3. In the event that any wind turbine(s) installed and commissioned fail(s) to supply
electricity on a commercial basis to the grid for a continuous period of 12 months,
or is no longer required, the turbine(s) in question shall be deemed to have
ceased to be required. Under such circumstances, the wind turbine(s) along with
any ancillary equipment, fixtures and fittings no longer required in connection with
the remaining turbine(s) shall be dismantled and removed from the site within 6
months of the end of the said continuous 6 month period, or when ceasing to be
no longer required. 
Thereafter, the surrounding land shall be re-instated in accordance with a re-
instatement scheme to include specification of all works and timescale for re-
instatement of the land, which shall previously have been submitted to and
approved by the Council, as planning authority. 
Reason: To ensure that any redundant or non-functioning wind turbine(s) is/are
removed from the site in the interests of public safety, amenity and environmental
protection and to ensure acceptable arrangements for the re-instatement of the
ground are provided. 
4. No development (excluding preliminary ground investigation which shall be
permitted) shall commence until:
a) draft Decommissioning and Site Restoration Plan for the site has been
submitted to and approved in writing by the Council, as planning authority in
consultation with SEPA, NatureScot and/or other agencies as appropriate;
and 
b)   thereafter, and not later than 12 months prior to the expiry of this permission
or decommissioning of the development, whichever is the sooner, a detailed
Decommissioning and Site Restoration Plan, based upon the principles
outlined in the approved draft Plan, shall be submitted to and approved by
the Council, as planning authority in consultation with SEPA, SNH and/or
other agencies as appropriate. 
The required/proposed plans shall include provision for all turbines and ancillary
infrastructure and equipment (including all buildings and structures, hardstandings
and tracks, etc.) to be decommissioned, de-energised and dismantled to at least
ground level and thereafter, removed from the site together with the arrangements
to retain any access tracks and other infrastructure on the site, the treatment of
disturbed ground surfaces, the management and timing of all proposed works, the
provisions for environmental management including traffic and other plans to
address issues and impacts likely to arise during the decommissioning period and
the provisions for the restoration and aftercare of the site. 
Thereafter, the development shall be decommissioned and the site restored and
re-instated in accordance with the approved Plan details. 
Reason: To ensure the arrangements for both decommissioning of the
development and re-instatement of the site are undertaken in an appropriate
environmentally acceptable and timeous manner, with all wind turbines and
associated infrastructure permanently removed from the site in the interests of
Page 178

Page 179

safety, environmental protection, amenity and appearance of the site and the
surrounding area. 
5. Prior to the development commencing, details shall be submitted to and approved
in writing by the Council, as planning authority regarding evidence of a bond or
other similar financial provision to be put in place to cover all decommissioning
and site restoration costs on the expiry of the permission or where the turbines
cease to be required, whichever is the sooner.  The required bond or equivalent
shall: 
a)   be based on the Decommissioning and Site Restoration Plan (as required by
Condition 4);
b)    include documentary evidence to demonstrate that the amount of the bond
or financial provision is sufficient to meet the full estimated costs of
decommissioning and site restoration, including dismantling, removal,
disposal, site restoration, remediation and all other incidental works and
professional costs; and 
c) include details to ensure and demonstrate that the proposed financial
arrangements will be maintained and be subject to periodic review
throughout the lifetime of the development.  The findings of each successive
review shall be submitted to and approved by the Council, as planning
authority, and include evidence to demonstrate that financial arrangements
continue to remain in place and remain sufficient for both the
decommissioning of the development and restoration of the site.  The review
period shall be not less than 5 yearly intervals from commencement of the
development, or such other period as may be agreed in writing with the
Council, as planning authority. 
Thereafter, the development shall not commence until written evidence has been
provided to the Council, as planning authority to confirm that the approved bond or
financial provision arrangement has been put in place. 
Reason: To ensure that sufficient funds are available to address the anticipated
arrangements and estimate of costs of decommissioning and re-instatement and
restoration of the site. 
6. No development shall commence (excluding preliminary ground investigation
which shall be permitted) until the following information has been submitted to and
approved by the Council, as planning authority in consultation with SEPA,
NatureScot and other agencies where appropriate:  
a) details of the make, model, design, power rating and sound power levels of
all turbines to be used (and at all times the total number of turbines to be
erected shall not exceed 3 and the blade tip height shall not exceed 149.9
metres above ground level); 
b) the external colour and/of finish of the turbines including towers, nacelles
and blades, which shall be non-reflective, semi-matt pale grey/off-white; 
c) unless otherwise located within the tower of each wind turbine, the location,
design specifications, external material finishes and colour of any external
wind turbine transformer housing; 
d) for the sub-station compound, the design external appearance and material
finishes and colour of all proposed buildings and structures to be erected,
Page 179

Page 180

stationed or installed within the compound area (including any sub-station
control building) together with the finalised site layout arrangements
including the location, dimensions, external appearance and surfacing
materials for the compound area, all fencing or other means of enclosure to
be erected and all other proposed/required ancillary infrastructure to be
provided including any required/proposed external switch gear infrastructure
to be located within the compound, the arrangements for access and parking
and disposal of foul and surface water from the compound area, external
lighting arrangements (where proposed), etc.; 
e) for the temporary construction compound, the location, extent and site layout
arrangements including the placement and purpose/use of all
buildings/structures within the compound, areas for storage of materials,
parking, disposal of foul and surface water, means of enclosure, and external
lighting arrangements, etc. together with timescales for both establishment
and removal of the temporary construction compound and details for
restoration and re-instatement of the site following removal of the temporary
compound;
f) detailed access track designs for all on-site access tracks and passing
places, to include their location and routing, design construction
specifications and surfacing materials, and the arrangements for drainage
disposal for each track section; 
g) the location(s) and design specification(s) for all required/proposed up-
graded existing and new watercourse crossings and engineering works
within the water environment.  With the exception of any proposed
watercourse crossings and directly related tracks, the details shall
demonstrate that all new infrastructure works occur out with a 50 metre
buffer area from water features on the site unless justification is provided, all
watercourse crossings shall be adequately sized to enable them to
accommodate 1 in 200 year peak flows (with allowance for climate change of
35% increase in flows) at each point without causing constriction of flows or
increasing the risk of flooding elsewhere, and where watercourse crossings
cannot be avoided, the use of bottomless or arched culverts (or bridging
solutions) which do not affect the bed or banks of the watercourse, and all
designs of crossings shall follow good practice guidelines;
h) a drainage assessment or strategy addressing all drainage from the site to
include the location(s), design specification(s) and timescale(s) for provision
of the arrangements for the disposal of foul and surface water from the site,
the former shall include the disposal of effluent from the site and the latter
shall incorporate SUDs, and provide for details to address both construction
and operational stages of the development and demonstrate how run-off will
be managed to minimise the risk of flooding, erosion, sediment run-off and
pollution of any watercourse; 
i) details of arrangements to monitor private water supplies during all stages of
the development, and in the event of any adverse effects on water quality or
quantity being identified, the arrangements and procedures to undertake
restorative and remedial works to maintain any supply.  This shall include
measures to monitor the supply known as 'Mid Skeith' to detect any changes
to water quality and allow for further mitigation measures to be put in place if
necessary.  This shall include notification to Scottish Water at
potectdwsources@scottishwater.co.uk, 3 months in advance of any works
Page 180

Page 181

commencing on site to make its operational teams aware (see consultation
response date 30 November 2022); and 
j) details of all required/proposed mitigation measures (where not already
embedded within the submitted design and layout of the development) for all
stages of the development, to be contained within a Schedule of Mitigation or
similar together with details regarding the process to control/action changes
from any agreed Schedule of Mitigation.  The Schedule shall include (but not
be limited to) all required/proposed measures to mitigate the impact of the
development upon the water environment (hydrology, hydrogeology and
geology) and nature conservation (ecology and ornithology including
protected species and sensitive habitat) interests. 
Thereafter, the development shall be implemented in accordance with the
approved details 
Reason: Details of the matters specified are lacking from the submission and to
ensure an acceptable form of development in landscape, visual and/or other
environmental considerations, including addressing the risk of damage from
flooding and surface water effects including pollution, erosion and sediment
impacts on the environment, to minimise impacts on ecological habitats, in the
interests of good land management and protection and enhancement of habitats,
and to maintain the wholesome provision of any private water supply where
affected by the development. 
7. No development shall commence until a detailed Site-specific Construction
Environmental Management Plan has been submitted to and approved in writing
by the Council, as Planning Authority in consultation with SEPA, NatureScot and
other agencies as appropriate.  The Plan shall be closely based on supporting
document by Atmos Consulting, dated March 2022, document reference 57120,
titled “Lurg Hill Wind Farm - Outline Construction Environmental Management
Plan”, address all stages of the development (construction, operation and
decommissioning), and identify all works and elements potentially capable of
giving rise to pollution or causing environmental harm, and all required/proposed
measures to mitigate the identified impacts.  The Plan shall include but not be
limited to the following:  
a) construction method statement covering the provision of all turbines and site
infrastructure;
b) pollution prevention and control measures – to include arrangements for
storage and management of oil, fuel and concrete on the site;
c) construction surface water management plan - to include a map of all
watercourses and ditches on site and all proposed infrastructure, mitigation
proposals and justification of appropriateness, a map of all proposed
mitigation locations (i.e. silt fences, straw bales, cross drains, settlement
lagoons, etc.) and details of procedures for dealing with emergencies and
spills;
d) drainage management plan - to address the management of foul and surface
water drainage, in both water quality and quantity terms and the
arrangements to dispose of foul effluent, and manage surface water to
prevent flooding, and pollution of water courses (see Condition 6 h);
e) peat protection/management plan to show how the finalised micro-sited
Page 181

Page 182

layout has been designed to minimise impact on and avoid areas of deep
peat.  Specifically, the plan must show peat probing results and in the vicinity
of Turbine 1 and include results of a detailed survey on a 10 metre by 10
metre grid basis around the centre of the proposed turbine base and track
leading to it.
f) emergency procedures to include the locations and use of spill kits, etc. and
provisions for staff training;
g) adverse weather (wet weather) working – to include an action plan (after
H&S considerations) about arrangements for working and assessment of
potential damage including sediment mitigation, use of equipment (for
example, pumps), etc.;
h) ground and surface water management and treatment - to include details for
monitoring (to be established prior to the commencement of works on site
and thereafter for all subsequent stages of the development), and a
response plan to detail actions to be taken should impacts on the water
environment occur;
i) water abstraction – to include details of any abstraction/dewatering,
proposed quantities, uses and discharges including use of any temporary
sub-surface water controls such as de-watering during construction (and
where de-watering is used, the Plan shall demonstrate that any such
discharges are limited to discharges that are of uncontaminated groundwater
abstracted directly through boreholes/well pointing and discharged without
contact with any other drainage run-off);
j) details of construction compound(s) to include the arrangements for
refuelling, tools and materials storage, car parking and concrete batching
plant, settlement lagoons (to prevent cement and concrete washing out into
ground or surface water) and the details of the final outfall to surface or
groundwater and the arrangements to treat such effluent prior to discharge,
for example by installation of a treatment plant or use of alternative
arrangements (for example, that wash out water is tankered off-site, etc.);
these details shall be agreed with the Planning Authority in advance in terms
of siting and form of construction;
k) dust management plan; 
l) measures to prevent loose or deleterious material being deposited on the
local road network including provision for on-site wheel cleaning, etc; 
m) noise management plan - to identify all sources of noise emissions
associated with the construction phase of the development together with
details of all measures to manage and mitigate the effects of construction
noise occurring at and within the site; 
n) details of all required/proposed pre-commencement of development
ecological surveys to be undertaken to determine the presence or otherwise
of any designated habitat or protected species, to include a schedule
identifying which habitats and species will be subject to survey, the scope
and time-scale(s) for undertaking each survey, and thereafter the results of
the surveys together with all further measures required/ proposed to mitigate
the impact of the development upon those species and habitats as identified
within the Environmental Appraisal (Chapter 6 Ecology and Chapter 7
Ornithology, mitigation sections for construction and operational phases
refers); and 
Page 182

Page 183

o) invasive non-native species protocol – to address all bio-security and other
measures to be adopted to remove or prevent the spread of any non-native
plant species on the site. 
In addition, the CEMP shall include reference to the terms of appointment of an
appropriately qualified Ecological Clerk of Works (ECoW), to be appointed by the
applicant/developer/wind turbine operator and approved by the Council, as
planning authority in consultation with NatureScot.  The terms should identify the
period(s) of appointment and the remit of the ECoW in terms of roles and
responsibilities which should include (but not be limited to) undertaking pre-
construction survey work and monitoring compliance with the hydrological and
ecological/ornithological commitments and mitigation arrangements to be
undertaken, as identified in the Environmental Appraisal and other supporting
documents including the Outline CEMP, overseeing the placement of
development infrastructure within the site and addressing all environmental
considerations, and the arrangements for reporting upon works undertaken on site
and incidences of non-compliance of works to the Council, as planning authority
and the applicant/developer/wind farm operator’s construction representatives. 
Thereafter, the development shall be carried out in accordance with the approved
Plan. 
Reason: In order to ensure that all development works are undertaken and
managed in an environmental acceptable manner and to minimise the impacts
arising from construction and operation of the development upon the environment,
to secure detailed information on the delivery of mitigation works and measures as
identified which are current lacking from the submitted particulars and to secure
effective monitoring and compliance of all. 
8. Prior to the commencement of any part of the development:
a) Detailed proposals for undertaking trial runs and also delivery of abnormal
indivisible loads, must be submitted for approval by the Planning Authority in
consultation with Roads Authority.  Details must include but not be limited to
detailed proposals (1:200 drawing) of the temporary measures to be
provided and the proposed access onto the C4L, temporary and permanent
modifications and measures required to protect the public road and
structures, traffic, vehicle holding areas and non vehicular management
during deliveries, time restrictions for deliveries i.e. outwith school crossing
patrol times.
b) A Construction Traffic Management Plan (CTMP) must be submitted for
approval by the Planning Authority in consultation with the Roads Authority. 
The traffic management plan must cover the duration of the development,
methods of dealing with the large delivery vehicles.  The plan shall also
include, the methods of marshalling and manoeuvring at junctions on the
public road network and any temporary traffic waiting restriction
requirements and all modifications to the road network and traffic
management arrangements.  Routes for deliveries to and from the site and
confirmations of routes not to be used by construction vehicles and workers
to access the site and measures to be put in place to prevent material being
deposited on the public road.
Page 183

Page 184

c) Details (1:200 scale drawing) of the proposed access junction onto the C4L
(Bogmuchals - Berryhillock Road) must be submitted and approved by the
Planning Authority in consultation with the Roads Authority.  The width of the
vehicular access shall be a minimum of 7.3 metres and have a maximum
gradient of 1:20 measured for the first 25 from the edge of the public
carriageway.  The first 25 metres of the access shall be to The Moray
Council specification and surfaced with hot rolled asphalt.  Any existing ditch,
watercourse or drain under the site access shall be piped using a 300
millimetres minimum diameter of pipe.  The pipe shall be laid to a self-
cleansing gradient.  Technical approval required for access to demonstrate
proposals will prevent water and loose materials from being discharged onto
the public road. 
d) A detailed drawing (scale 1:500 or 1:1000 which shall also include details to
demonstrate control of the land) showing a visibility splay 4.5 metres by 160
metres and a schedule of maintenance for the area within the visibility splay
shall be submitted to and approved by the Council, as Planning Authority in
consultation with the Roads Authority. 
e) Detailed drawing(s) (scale 1:500) showing the location and design of 3
passing places at locations to be agreed with the Roads Authority. One
approximately 50 – 100 metres to the west of the proposed access onto the
C4L to replace the existing passing place at the access onto the C4L.  The
second (to achieve a maximum passing place spaced of not more than 150
metres) to be located approximately 50 – 100 metres to the east of the
proposed access onto the C4L.  The third passing place to be located
approximately 130-150 metres east of the existing passing place at Greenhill
(to achieve a maximum spacing of not more than 150 metres between
passing places). 
f) Details of the vehicle gross weights and maximum axle loads are required. 
Thereafter, the works shall be implemented in accordance with the approved
details. 
Reason: To ensure an acceptable development in road safety terms through the
provision of details currently lacking. 
9. Prior to the commencement of construction and deliveries: 
a)  Evidence that a S96 ‘Wear and Tear’ agreement between the developer and
the Roads Authority has been completed and signed by both parties, must
be submitted to the Planning Authority.  The scope of the agreement shall
assess, monitor and address the impact of construction and delivery traffic
on the road network for the duration of the construction of the development
and must include all roads within the Moray Council area between the site
access and the first ‘A’ class road along the agreed construction access
route(s). 
b)  Abnormal load trial run(s) must be undertaken after all mitigation works have
been completed to confirm the works are acceptable and to identify any
other restrictions not previously addressed and the frequency and location of
abnormal load passing places/oncoming vehicle holding areas required. 
Representatives from Moray Council Transportation (Traffic), and Police
Scotland must be invited to the trial run.
Page 184

Page 185

c)  Prior to any abnormal indivisible load being delivered to the site, all
suspensive works approved through condition (8 a,b,c,d,e,f) required prior to
commencement of construction, must be provided in accordance with the
approved plans.  Any works undertaken are to be permanent for the duration
of the operation of the development unless otherwise agreed in writing with
the Roads Authority. 
d)  The visibility splay of 4.5 metres by 160 metres shall be provided and
thereafter the visibility splay shall be maintained at all times free from any
obstruction exceeding 1.0 metres above the level of the carriageway in
accordance with the agreed schedule of maintenance. 
Thereafter, the works shall be implemented in accordance with the approved
details. 
Reason: The provision of details currently lacking and in order to ensure that
acceptable infrastructure is provided on the route to/from the development in the
interests of road safety. 
10. The proposed route for any abnormal loads on the trunk road network must be
approved by Transport Scotland, as the Trunk Roads Authority, prior to the
movement of any abnormal load.  Any accommodation measures required,
including the removal of street furniture, junction widening, traffic management,
must similarly be approved.  Full details of proposed works shall be developed in
consultation with the Trunk Road Operating Company and Transport Scotland
Area Manager at the earliest opportunity through a Minute of Agreement
(https://www.transport.gov.scot/our-approach/industry-guidance/work-on-the-
scottish-trunk-road-network) and issued for their approval prior to the
commencement of construction operations. 
Reason: To maintain safety for both the trunk road traffic and the traffic moving to
and from the development ; and to ensure that the transportation of abnormal
loads will not have any detrimental effect on the trunk road network. 
11. Any additional signing or temporary traffic control measures deemed necessary
due to the size or length of loads being delivered must be undertaken by a
recognised Quality Assured traffic management consultant, to be approved by the
Planning Authority, in consultation with Transport Scotland as the Trunk Roads
Authority, before delivery commences. 
Reason: To ensure that abnormal loads will not have any detrimental effect on
the trunk road network. 
12. The developer shall submit proposals for an abnormal loads delivery trial-run to be
undertaken with the involvement of Police Scotland and prior to the
commencement of abnormal loads deliveries.  Trial-run proposals shall be
submitted to and approved in writing by the Planning Authority, in consultation
with Transport Scotland as the Trunk Roads Authority. 
Reason: To ensure that the transportation of abnormal loads will not have any
detrimental effect on the trunk road network.
Page 185

Page 186

13. No development shall commence until a Construction Traffic Management Plan
(CTMP) has been prepared and approved in writing by the Planning Authority, in
consultation with Transport Scotland as the Trunk Roads Authority. 
Reason: To minimise interference with the safety and free flow of the traffic on the
trunk road , to ensure the safety of pedestrians and cyclists using the trunk road
and adjacent facilities, and to be consistent with current guidance and best
practice. 
14. All vehicles transporting construction material to and from the proposed
development should be sheeted. 
Reason: To ensure that material from the site is not deposited on the trunk road
to the detriment of road safety. 
15. Prior to the commencement of construction, vehicle wheel cleansing facilities shall
be installed and brought into operation, the design and siting of which shall be
subject to the prior approval of the planning authority, in consultation with
Transport Scotland as the Trunk Roads Authority. 
Reason: To ensure that material from the site is not deposited on the trunk road
to the detriment of road safety. 
16. Prior to any decommissioning of the development, a Decommissioning Plan shall
be prepared and approved in writing by the Planning Authority, in consultation with
Transport Scotland as the Trunk Roads Authority. 
Reason: To minimise interference with the safety and free flow of the traffic on the
trunk road. 
17. No development shall commence unless and until an Air Traffic Control Radar
Mitigation Scheme to address the impact of the wind turbine upon air safety has
been submitted to and approved in writing by the Local Planning Authority in
consultation with the Ministry of Defence (MOD). 
The Air Traffic Control Radar Mitigation Scheme is a scheme designed to mitigate
the impact of the development upon the operation of the Primary Surveillance
Radar at RAF Lossiemouth (and the air traffic control operations of the MOD
which is reliant upon the Radar. 
The Air Traffic Control Radar Mitigation Scheme shall set out the appropriate
measures to be implemented to mitigate the impact of the development on the
Radar and shall be in place for the operational life of the development provided
the Radar remains in operation. 
No turbines shall become operational unless and until all those measures required
by the approved Air Traffic Control Radar Mitigation Scheme to be implemented
prior to the operation of the turbines have been implemented and the Local
Planning Authority has confirmed this in writing.  The development shall thereafter
Page 186

Page 187

be operated fully in accordance with the approved Air Traffic Control Radar
Mitigation Scheme. 
Reason: To maintain aviation safety. 
18. Prior to commencing construction of any wind turbine generators, or deploying
any construction equipment or temporal structure(s) 50 metres or more in height
(above ground level) the undertaker must submit an aviation lighting scheme for
the approval of the Moray Council in conjunction with the Ministry of Defence
defining how the development will be lit throughout its life to maintain civil and
military aviation safety requirements as determined necessary for aviation safety
by the Ministry of Defence. 
This should set out:
a)   details of any construction equipment and temporal structures with a total
height of 50 metres or greater (above ground level) that will be deployed
during the construction of wind turbine generators and details of any aviation
warning lighting that they will be fitted with; and 
b)   the locations and heights of all wind turbine generators and any anemometry
mast featured in the development identifying those that will be fitted with
aviation warning lighting identifying the position of the lights on the wind
turbine generators; the type(s) of lights that will be fitted and the performance
specification(s) of the lighting type(s) to be used. 
Thereafter, the undertaker must exhibit such lights as detailed in the approved
aviation lighting scheme. The lighting installed will remain operational for the
lifetime of the development. 
Reason: To maintain aviation safety. 
19. The undertaker must notify the Ministry of Defence, at least 14 days prior to the
commencement of the works, in writing of the following information: 
a) the date of the commencement of the erection of wind turbine generators; 
b) the maximum height of any construction equipment to be used in the
erection of the wind turbines; 
c) the date any wind turbine generators are brought into use; and
d) the latitude and longitude and maximum heights of each wind turbine
generator, and any anemometer mast(s). 
The Ministry of Defence must be notified of any changes to the information
supplied in accordance with these requirements and of the completion of the
construction of the development. 
Reason: To maintain aviation safety. 
20. Prior to the commencement of the development or any tree felling on the site, a
Compensatory Planting Plan (CP) detailing the provision of 9.3ha of tree planting
shall be submitted to and approved in writing by the Council, as Planning Authority
in consultation with Scottish Forestry.  The CP must provide full details of the
proposed planting, including its maintenance over the entire life-span of the
Page 187

Page 188

development and include the following information:
a) details of the person(s) that survey, describe, assess, specify and deliver
both the felling proposals and on-site and off-site CP proposals must have
the relevant qualifications, technical abilities and have the necessary
experience e.g. a chartered forester;
b) the location of the on-site and off-site CP covering an area of 9.3ha should
be fully detailed, described and supported with good quality maps.  If peat
depth is a relevant consideration, a full assessment should be undertaken
using recognised survey techniques and details of this provided in the
application;
c) details of any statutory consents required to carry out the proposed CP;
d) a full silvicultural proposal for compensatory planting, supported with maps
should be provided.  This should include: ground preparation, drainage,
planting technique, stocking density, species, maintenance and a protection
plan for the life of the development;
e) details of the timing of the CP.  All CP should be completed within five years
after the woodland is removed or within two years of the development being
completed.  A maintenance plan with appropriate timescales should be
provided for the life of the development.  Subsequent establishment should
be completed within the period for which enforcement action can be taken;
f) details for monitoring of CP conditions or arrangements: An independent,
qualified and technically competent professional(s) (e.g. chartered forester)
with the required experience should inspect the CP scheme at regular
intervals (year 1, 5 and 10) to ensure that the trees are planted correctly,
maintained to the required standard and ultimately established into
woodland.  The woodland must be maintained thereafter.  This professional
individual should report to the planning authority, to allow the CP condition to
be managed and ultimately discharged; and
g) restocking timescales should be completed within two years after the
woodland is removed or within two years of the associated section of the
development being completed.  This should only be extended if the Hylobius
Decision Support System clearly shows that a delay would be a benefit,
restocking should not be extended beyond 5 years in any instance. 
Reason: To mitigate the effects of the development on woodland and ensure
provision of satisfactory compensatory planting. 
21. The permission hereby granted shall not be exercised in addition to, or in
conjunction with the permission approved under formal decision notice
22/00339/APP, dated 5 July 2022 (Section 42 application to modify Condition 1 of
planning permission 17/01198/EIA /  PPA-300-2052, granting permission for "a
period of 30 years from the date when electricity if first exported from any wind
turbine within the development to the electricity network (First Export Date)" to
granting a permission for a period of 35 years). 
Reason: In order to avoid any ambiguity regarding the terms of this consent and
to ensure that mitigation measures as set out within the EA (omitting turbines 4
and 5) are met. 
Page 188

Page 189

22. The rating level of noise immissions from the combined effects of the wind
turbines (including the application of any tonal penalty and amplitude modulation
(AM) penalty) when determined in accordance with the attached Guidance Notes
(to this condition), shall not exceed the values for the relevant integer wind speed
set out in, or derived from, the tables attached to these conditions at any dwelling
which is lawfully existing or has planning permission at the date of this permission
and:
a) the wind farm operator shall continuously log power production, wind speed
and wind direction, all in accordance with Guidance Note 1(d).  This data
shall be retained for a period of not less than 24 months.  The wind farm
operator shall provide this information in the format set out in Guidance Note
1(e) to the Local Planning Authority on its request, within 14 days of receipt
in writing of such a request;
b) within 21 days from receipt of a written request from the Local Planning
Authority following a complaint to it from an occupant of a dwelling alleging
noise disturbance at that dwelling, the wind farm operator shall, at its
expense, employ a consultant approved by the Local Planning Authority to
assess the level of noise immissions from the wind farm at the complainant’s
property in accordance with the procedures described in the attached
Guidance Notes.  The written request from the Local Planning Authority shall
set out at least the date, time and location that the complaint relates to and
any identified atmospheric conditions, including wind direction, and include a
statement as to whether, in the opinion of the Local Planning Authority, the
noise giving rise to the complaint contains or is likely to contain a tonal
component or is likely to contain an amplitude modulation (AM) component;
c) the assessment of the rating level of noise immissions shall be undertaken in
accordance with an assessment protocol that shall previously have been
submitted to and approved in writing by the Local Planning Authority.  The
protocol shall include the proposed measurement location identified in
accordance with the Guidance Notes where measurements for compliance
checking purposes shall be undertaken, whether noise giving rise to the
complaint contains or is likely to contain a tonal component and/or amplitude
modulation (AM) component, and also the range of meteorological and
operational conditions (which shall include the range of wind speeds, wind
directions, power generation and times of day) to determine the assessment
of rating level of noise immissions.  The proposed range of conditions shall
be those which prevailed during times when the complainant alleges there
was disturbance due to noise, having regard to the written request of the
Local Planning Authority under paragraph (b), and such others as the
independent consultant considers likely to result in a breach of the noise
limits;
d) where a dwelling to which a complaint is related is not listed in the tables
attached to these conditions, the wind farm operator shall submit to the Local
Planning authority for written approval proposed noise limits selected from
those listed in the Tables to be adopted at the complainant’s dwelling for
compliance checking purposes.  The proposed noise limits are to be those
limits selected from the Tables specified for a listed location which the
independent consultant considers as being likely to experience the most
similar background noise environment to that experienced at the
complainant’s dwelling.  The rating level of noise immissions resulting from
Page 189

Page 190

the combined effects of the wind turbines when determined in accordance
with the attached Guidance Notes shall not exceed the noise limits approved
in writing by the Local Planning Authority for the complainant’s dwelling;
e) the wind farm operator shall provide to the Local Planning Authority the
independent consultant’s assessment of the rating level of noise immissions
undertaken in accordance with the Guidance Notes within 2 months of the
date of the written request of the Local Planning Authority for compliance
measurements to be made under paragraph (b), unless the time limit is
extended in writing by the Local Planning Authority.  Unless otherwise
agreed in writing by the Planning Authority, the assessment shall be
accompanied by all data collected for the purposes of undertaking the
compliance measurements, such data to be provided in the format set out in
Guidance Note 1(e) of the Guidance Notes with the exception of audio data
which shall be supplied in the format in which it is recorded.  The
instrumentation used to undertake the measurements shall be calibrated in
accordance with Guidance Note 1(a) and certificates of calibration shall be
submitted to the Local Planning Authority with the independent consultant’s
assessment of the rating level of noise immissions; and
f) where a further assessment of the rating level of noise immissions from the
wind farm is required pursuant to Guidance Note 4(c), the wind farm operator
shall submit a copy of the further assessment within 21 days of submission
of the independent consultant’s assessment pursuant to paragraph (c) above
unless the time limit has been extended in writing by the Local Planning
Authority. 
Table 1: Between 07:00 and 23:00 – Noise limits expressed in dB LA90,10 minute as a
function of the standardised wind speed (m/s) at 10 metre height as determined
within the site averaged over 10 minute periods. 
LOCATION Standardised wind speed at 10 metre height (m/s) within
the site averaged over 10-minute periods
4 5 6 7 8 9 10 11 12
Myreton 35.0 35.0 35.3 37.9 40.9 44.1 47.7 51.6 55.8
Clochmacreich 35.0 35.7 38.7 41.5 44.1 46.3 47.8 48.6 48.4
Kintywaird 35.0 35.0 36.2 39.1 41.9 44.6 47.0 48.9 50.0
Brambleburn Cottage 35.0 35.0 35.0 37.0 39.9 42.8 45.4 47.5 48.8
Over Windyhills 35.0 35.7 38.7 41.5 44.1 46.3 47.8 48.6 48.4
Netherton of Windyhills 35.0 35.7 38.7 41.5 44.1 46.3 47.8 48.6 48.4
Backies 35.0 35.7 38.7 41.5 44.1 46.3 47.8 48.6 48.4
Upper Skeith 35.0 35.7 38.7 41.5 44.1 46.3 47.8 48.6 48.4
Mid Skeith 35.0 35.7 38.7 41.5 44.1 46.3 47.8 48.6 48.4
Little Skeith 35.0 35.0 36.2 39.1 41.9 44.6 47.0 48.9 50.0
Langley 35.0 35.0 35.0 37.0 39.9 42.8 45.4 47.5 48.8
Croylet 35.0 35.0 35.0 37.0 39.9 42.8 45.4 47.5 48.8 
Page 190

Page 191

Table 2: Between 23:00 and 07:00 – Noise limits expressed in dB LA90,10 minute as a
function of the standardised wind speed (m/s) at 10 metre height as determined
within the site averaged over 10 minute periods. 
LOCATION Standardised wind speed at 10 metre height (m/s) within
the site averaged over 10-minute periods 
4 5 6 7 8 9 10 11 12
Myreton 40.0 40.0 40.0 40.0 40.0 40.0 42.2 47.2 52.9
Clochmacreich 40.0 40.0 40.0 40.0 40.0 43.0 45.2 46.2 45.7
Kintywaird 40.0 40.0 40.0 40.0 41.0 44.1 46.2 46.7 45.1
Brambleburn Cottage 40.0 40.0 40.0 40.0 40.0 40.0 42.8 46.6 49.8
Over Windyhills 40.0 40.0 40.0 40.0 40.0 43.0 45.2 46.2 45.7
Netherton of Windyhills 40.0 40.0 40.0 40.0 40.0 43.0 45.2 46.2 45.7
Backies 40.0 40.0 40.0 40.0 40.0 43.0 45.2 46.2 45.7
Upper Skeith 40.0 40.0 40.0 40.0 40.0 43.0 45.2 46.2 45.7
Mid Skeith 40.0 40.0 40.0 40.0 40.0 43.0 45.2 46.2 45.7
Little Skeith 40.0 40.0 40.0 40.0 41.0 44.1 46.2 46.7 45.1
Langley 40.0 40.0 40.0 40.0 40.0 40.0 42.8 46.6 49.8
Croylet 40.0 40.0 40.0 40.0 40.0 40.0 42.8 46.6 49.8 
Table 3: Coordinate locations of the dwellings listed in Tables 1 and 2. 
Myreton 349628 856425
Clochmacreich 349452 858035
Kintywaird 351482 859347
Brambleburn Cottage 350969 856448
Over Windyhills 349264 856733
Netherton of Windyhills 349308 857282
Backies 349762 858923
Upper Skeith 349992 859109
Mid Skeith 350327 859293
Little Skeith 350937 859394
Langley 351560 856770
Croylet 350359 856276 
Note to Table 3: The geographical coordinate references are provided for the
purpose of identifying the general location of dwellings to which a given set of
noise limits applies. 
Reason: To ensure an acceptable form of development and in order to protect the
amenity of any nearby residents from any undue noise and disturbance. 
23. The wind farm operator shall employ an independent consultant, approved by the
Planning Authority, to measure, at the operator’s own expense, the level of noise
immisions from the wind turbines within the first year of the operation of the
turbines.  The measurement procedures, which may include filtering data
according to wind direction, shall be approved by the Planning Authority prior to
commencement of monitoring and shall be implemented as approved.  The results
Page 191

Page 192

of the measurement exercise shall be forwarded to the Planning Authority as soon
as practicable after the completion of the monitoring exercise. 
Reason: To ensure an acceptable form of development and in order to protect the
amenity of any nearby residents from any undue noise and disturbance. 
24. Construction works (including vehicle movements) associated with the
development audible at any point on the boundary of any noise sensitive dwelling
shall be permitted between 0700 - 1900 hours, Monday to Friday and 0700 - 1300
hours on Saturdays only, and at no other times out with these permitted hours
(including National Holidays).  The above construction hours shall apply, unless
otherwise agreed in writing with the Planning Authority, and where so
demonstrated exceptional operational constraints require limited periods of
construction works to be undertaken out with the permitted construction hours. 
Reason: To ensure an acceptable form of development and in order to protect the
amenity of any nearby residents from any undue noise and disturbance. 
25. There shall be no blasting at the development. 
Reason: To ensure an acceptable form of development and in order to protect the
amenity of any nearby residents from any noise disturbance or vibration. 
26. A shadow flicker impact control unit shall be installed prior to operation to turbine
1 at the development, in accordance with the details submitted in the supporting
email by Atmos consulting, dated 9th August 2022 and titled “RE:22/00563/APP
Lurg Hill - Shadow flicker assessment - Env Appraisal- Section 13”. 
Reason: To ensure an acceptable form of development and in order to protect the
amenity of any nearby residents from any undue shadow flicker. 
27. At the reasonable request of the Planning Authority following a complaint the wind
farm operator shall investigate and instigate appropriate mitigation measures to
minimise the effects of shadow flicker. 
Reason: To ensure an acceptable form of development and in order to protect the
amenity of any nearby residents from any undue shadow flicker. 
28. The blades of all turbines shall rotate in the same direction and no name, symbol,
sign or logo or similar means of advertisement, other than those required for
health and safety reasons, shall be displayed on any part of the turbines, masts,
buildings/ structures and plant, or other infrastructure associated with the
development without the prior written consent of the Council, as planning
authority. 
Reason: To minimise the visual impact arising from the appearance of the
development. 
29.   a)  All wind turbines, buildings, masts, areas of hardstanding and tracks shall be
constructed in the locations shown in Figure 3.2 Site Layout. The location of
Page 192

Page 193

the wind turbines, compounds, areas of hardstanding and tracks may be
varied (micro-sited) within the site subject to the following, unless otherwise
approved in advance in writing by the Planning Authority:
i.   no wind turbine, building, mast, tracks, hardstanding or other ancillary
infrastructure shall be moved more than 50 metres from the position
shown on Figure 3.2 Site Layout; 
ii.   all micro-siting permissible under this condition must be approved in
advance in writing by the Environmental Clerk of Works (ECoW).
b)   No later than two months after the Date of Final Commissioning, an updated
site plan shall be submitted to the Planning Authority showing the final
position of all wind turbines, anemometry masts, areas of hardstanding,
tracks and associated infrastructure forming part of the development. The
plan must also specify areas where micro-siting has taken place and, for
each instance, be accompanied by the Environmental Clerk of Works or
Planning Authority’s approval, as applicable. 
Reason: To ensure that micro-siting decisions take account of environmental
impacts and local ground conditions. 
REASON(S) FOR DECISION
The Council’s reason(s) for making this decision are:- 
This proposal represents an acceptable renewable energy development proposal for
Moray.  The scheme accords with local and national planning policy regarding the
expansion of renewable energy, including its contribution to renewable energy targets. 
The proposed development would introduce changes to the height and blade
dimensions of the turbines and a reduction in turbine numbers from five to three when
compared with the consented development at this site.  While significant adverse
effects on landscape character and views would be associated with this proposal, these
effects require to be considered within the context of the existing consent of a wind farm
on this site, which carries significant weight as a material consideration. 
The omission of the two northern-most turbines would provide mitigation of visual
effects in close views from residential properties and from the Cullen House Inventory
listed designed landscape (should existing forestry be felled on Clune Hill).  The
changes made to the size of the turbines (a difference of just under 20m) would not be
readily appreciable in the majority of views from the wider area.  With this mitigation
and when compared to the consented scheme, for landscape and visual effects, the
proposal is considered to be an acceptable departure from Policies DP1 and DP9,
subject to Turbines 4 and 5 of 17/01198/EIA and 22/00339/APP not being constructed
alongside the proposal. 
From detailed assessment and subject to conditions to avoid or mitigate any significant
impacts, the proposal satisfies all other policy requirements as set out within the Moray
Local Development Plan 2020, relating to the natural and built environment, residential
amenity, cultural heritage, woodland removal, the water environment, transport, noise,
aviation, telecommunications, socio-economic, recreational and tourism interests. 
Page 193

Page 194

List of Informatives: 
THE TRANSPORTATION MANAGER, DIRECT SERVICES has commented that:- 
Prior to the commencement of deliveries or any construction work, a Section 96
Agreement under the Roads (Scotland) Act 1984 will be required to be approved
between the developer and the roads Authority.  This is to ensure that the costs to
repair any damage to the public roads as a result of the construction work traffic
are met by the applicant. 
The scope of the S96 Wear and Tear Agreement must include a condition survey
of the network including the full extent of the agreed construction traffic route(s)
(within Moray) between the site and the ‘A’ class road network.  In addition the
wear and tear agreement shall also include condition surveys of all roads
identified as ‘unsuitable’ which must be agreed with the Roads Authority.  On the
basis of the current indicative access routes the following initial routes are
identified as ‘unsuitable’ for use by construction traffic. 
C7L Craibstone - Fordyce Road
U57al Oathillock Road
U57l Main Road/Kirkton Road
C62L Clune – Ardiecow 
A programme of monitoring for all routes identified within the CTMP during
construction shall be included. 
Proposals for the management of abnormal indivisible loads to be approved, must
also include measures to ensure the safety of non-vehicular road users. 
It is not acceptable to over run central refuge / splitter islands, they are not
constructed to take vehicle loadings.  Proposals submitted must show how this will
be managed during deliveries.  It is also not appropriate to remove signing for the
duration of the abnormal loads therefore confirmation of how signs will be
managed during the delivery phase needs to be agreed. 
Transport Scotland must be consulted with respect to all deliveries proposed via
the Trunk Road.  The neighbouring Local Authorities, through which the delivery
route may pass, Highland/Aberdeenshire/Aberdeen City, must also be consulted. 
Planning consent does not carry with it the right to construct a new road or any
part of a road.  In accordance with Section 21 of the Roads (Scotland) Act 1984
Construction Consent for new roads (includes passing places, modified junctions
and footpaths) that will form part of the public road will be required.  Advice on this
matter can be obtained by emailing Transport.Develop@moray.gov.uk and
reference to the following pages on the Council web site 
Checklist: http://www.moray.gov.uk/downloads/file68812.pdf
RCC: http://www.moray.gov.uk/moray_standard/page_65638.html
Specification http://www.moray.gov.uk/downloads/file68813.pdf 
Page 194

Page 195

The applicant is obliged to apply for a road opening permit in accordance with
Section 85 of the Roads (Scotland) Act 1984.  Advice on this matter can be
obtained by emailing roadspermits@moray.gov.uk  and reference to the following
page on the Council web site: Road Opening:
http://www.moray.gov.uk/moray_standard/page_79860.html 
Public utility apparatus may be affected by this proposal.  Contact the appropriate
utility service in respect of any necessary utility service alterations which have to
be carried out at the expense of the developer. 
If required, street furniture will need to be repositioned at the expense of the
developer.  In addition any existing roadside ditch may require a pipe or culvert. 
Advice on these matters can be obtained by emailing road.maint@moray.gov.uk 
The applicants shall be responsible for any necessary diversion of any utilities or
drainage present at the locations where works are to be undertaken. 
The applicants shall meet all costs of improvements to the road infrastructure,
which are required as a result of the development. 
The applicants shall meet all costs of removal and re-erection of road signage,
which are required as a result of the delivery of the abnormal loads. 
The applicants shall meet all costs of diverting any footpath or cycleway during the
construction period, including signage. 
The applicants shall free and relieve the Roads Authority from any claims arising
out of his operations on the road or extension to the road. 
No retaining structures or embankments shall be constructed along the edge of
the road, whether retaining the public road or ground adjoining the public road
without prior consultation and agreement of the Roads Authority. 
TRANSPORT SCOTLAND, has commented that: 
The applicant should be informed that the granting of planning consent does not
carry with it the right to carry out works within the trunk round boundary and that
permission must be granted by Transport Scotland Roads Directorate.  Where any
works are required on the trunk road, contact details are provided on Transport
Scotland’s response to the planning authority which is available on the Council’s
planning portal. 
Trunk road modification works shall, in all respects, comply with the Design
Manual for Roads and Bridges and the Specification for Highway Works published
by HMSO.  The developer shall issue a certificate to that effect, signed by the
design organisation. 
Trunk road modifications shall, in all respects, be designed and constructed to
arrangements that comply with the Disability Discrimination Act: Good Practice
Page 195

Page 196

Guide for Roads published by Transport Scotland.  The developer shall provide
written confirmation of this, signed by the design organisation. 
The DEVELOPMENT MANAGEMENT AND BUILDING STANDARDS MAANGER, has
commented that: 
The control building will require a building warrant. 
During the decommissioning phase of the development proposal or when the wind
turbines are deemed to have ceased to be required (conditions 2 and 3 of this
consent refer) the wind turbines and any ancillary equipment, fixtures and fittings
should be recycled and/or re-used when they reach end-of-use as far as is
practicable.  Details of methods and technologies to be used to recycle and/or re-
use these materials should be submitted as part of any prospective submission to
purify conditions 3 and 4 of this planning consent. 
SCOTTISH WATER, has commented that: 
See attached consultation response dated 30 November 2022. 
The DEFENCE INFRASTRCTURE ORGANISATION, has commented that: 
See attached consultation response dated 9 May 2022. 
The ENVIRONMENTAL HEALTH MANAGER, has commented that: 
Should the control building that forms part of this development be connected to a
private water supply, and if the water is used for human consumption (which
includes washing and other sanitary purposes), the supply is likely to come within
the scope of The Water Intended for Human Consumption (Private Supplies)
(Scotland) Regulations 2017.  These regulations require that someone who is
adding a new part to a private supply system (such as a new water source or
connection), must tell the Council as enforcing authority before they do so.  It is an
offence to use a new or modified supply covered by these regulations unless the
supply has been risk assessed and approved by the enforcing authority.  You are
recommended to contact the Council’s Environmental Health section (tel 0300
1234561, email environmentalhealth@moray.gov.uk) at least eight weeks before
the supply is intended to be used to arrange for a risk assessment to be
undertaken. 
Guidance Notes for Noise Condition 22. 
These notes are to be read with and form part of the noise condition.  They further
explain the condition and specify the methods to be employed in the assessment
of complaints about noise immissions from the wind farm.  The rating level at each
integer wind speed is the arithmetic sum of the wind farm noise level as
determined from the best-fit curve described in Guidance Note 2 of these
Guidance Notes, any tonal penalty applied in accordance with Guidance Note 3,
and any Amplitude Modulation (AM) penalty applied in Guidance Note 6.
Reference to ETSU-R-97 refers to the publication entitled “The Assessment and
Page 196

Page 197

Rating of Noise from Wind Farms” (1997) published by the Energy Technology
Support Unit (ETSU) for the Department of Trade and Industry (DTI). 
Guidance Note 1 
a) Values of the LA90, 10 minute noise statistic should be measured at the
complainant’s property, using a sound level meter of EN 60651/BS EN
60804 Type 1, or BS EN 61672 Class 1 quality (or the equivalent UK
adopted standard in force at the time of the measurements) set to measure
using the fast time weighted response as specified in BS EN 60651/BS EN
60804 or BS EN 61672-1 (or the equivalent UK adopted standard in force at
the time of the measurements).  This should be calibrated in accordance with
the procedure specified in BS 4142: 1997 (or the equivalent UK adopted
standard in force at the time of the measurements).  Measurements shall be
undertaken in such a manner to enable amplitude modulation and/or tonal
penalties to be applied in accordance with these Guidance Notes. 
b) The microphone should be mounted at 1.2 – 1.5 metres above ground level,
fitted with a two-layer windshield or suitable equivalent approved in writing by
the Local Planning Authority, and placed outside the complainant’s dwelling.
Measurements should be made in “free field” conditions.  To achieve this,
the microphone should be placed at least 3.5 metres away from the building
facade or any reflecting surface except the ground at the approved
measurement location.  In the event that the consent of the complainant for
access to his or her property to undertake compliance measurements is
withheld, the wind farm operator shall submit for the written approval of the
Local Planning Authority details of the proposed alternative representative
measurement location prior to the commencement of measurements and the
measurements shall be undertaken at the approved alternative
representative measurement location. 
c) The LA90 10 minute measurements should be synchronised with
measurements of the 10-minute arithmetic mean wind and operational data
logged in accordance with Guidance Note 1(d), including the power
generation data from the turbine control systems of the wind farm. 
d) To enable compliance with the conditions to be evaluated, the wind farm
operator shall continuously log arithmetic mean wind speed in metres per
second and wind direction in degrees from north at hub height for each
turbine, and at any on site meteorological mast, if available, together with the
arithmetic mean power generated by each turbine, all in successive 10-
minute periods.  Unless an alternative procedure is previously agreed in
writing with the Planning Authority, this hub height wind speed, averaged
across all operating wind turbines, shall be used as the basis for the
analysis.  All 10 minute arithmetic average mean wind speed data measured
at hub height shall be ‘standardised’ to a reference height of 10 metres as
described in ETSU-R-97 at page 120 using a reference roughness length of
0.05 metres.  It is this standardised 10 metre height wind speed data, which
is correlated with the noise measurements determined as valid in
accordance with Guidance Note 2, such correlation to be undertaken in the
Page 197

Page 198

manner described in Guidance Note 2. All 10-minute periods shall
commence on the hour and in 10- minute increments thereafter. 
e) Data provided to the Local Planning Authority in accordance with the noise
condition shall be provided in comma separated values in electronic format. 
f) A data logging rain gauge shall be installed in the course of the assessment
of the levels of noise immissions.  The gauge shall record over successive
10-minute periods synchronised with the periods of data recorded in
accordance with Note 1(d). 
Guidance Note 2 
a) The noise measurements shall be made so as to provide not less than 20
valid data points as defined in Guidance Note 2. 
b) Valid data points are those measured in the conditions specified in the
agreed written protocol under paragraph (c) of the noise condition, but
excluding any periods of rainfall measured in the vicinity of the sound level
meter.  Rainfall shall be assessed by use of a rain gauge that shall log the
occurrence of rainfall in each 10 minute period concurrent with the
measurement periods set out in Guidance Note 1. 
c) For those data points considered valid in accordance with Guidance Note
2(b), values of the LA90, 10 minute noise measurements and corresponding
values of the 10 minute standardised 10 metre height wind speed, as derived
from the site measured wind speed source(s) agreed in writing with the
Planning Authority in accordance with Guidance Note 1(d), shall be plotted
on an XY chart with noise level on the Y-axis and the standardised mean
wind speed on the X-axis. A least squares, “best fit” curve of an order
deemed appropriate by the independent consultant (but which may not be
higher than a fourth order) should be fitted to the data points and define the
wind farm noise level at each integer speed. 
Guidance Note 3 
a) Where, in accordance with the approved assessment protocol under
paragraph (c) of the noise condition, noise immissions at the location or
locations where compliance measurements are being undertaken contain or
are likely to contain a tonal component, a tonal penalty is to be calculated
and applied using the following rating procedure. 
b) For each 10 minute interval for which LA90, 10 minute data have been
determined as valid in accordance with Guidance Note 2 a tonal assessment
shall be performed on noise immissions during 2 minutes of each 10 minute
period.  The 2 minute periods should be spaced at 10 minute intervals
provided that uninterrupted uncorrupted data are available (“the standard
procedure”).  Where uncorrupted data are not available, the first available
uninterrupted clean 2 minute period out of the affected overall 10 minute
period shall be selected.  Any such deviations from the standard procedure,
Page 198

Page 199

as described in Section 2.1 on pages 104-109 of ETSU-R-97, shall be
reported. 
c) For each of the 2 minute samples the tone level above or below audibility
shall be calculated by comparison with the audibility criterion given in Section
2.1 on pages 104 to 109 of ETSU-R-97. 
d) The average tone level above audibility shall be calculated for each wind
speed bin, each bin being 1 metre per second wide and centred on integer
wind speeds.  Samples for which the tones were below the audibility criterion
or no tone was identified, a value of zero audibility shall be substituted. 
e) The tonal penalty for each wind speed bin is derived from the margin above
audibility of the tone according to the figure below. 
Guidance Note 4 
a) If a tonal penalty is to be applied in accordance with Guidance Note 3 the
rating level of the turbine noise at each wind speed is the arithmetic sum of
the measured noise level as determined from the best fit curve described in
Guidance Note 2 and the penalty for tonal noise as derived in accordance
with Guidance Note 3 at each integer wind speed within the range specified
by the Local Planning Authority in its written protocol under paragraph (c) of
the noise condition. 
b) If no tonal penalty is to be applied then the rating level of the turbine noise at
each wind speed is equal to the measured noise level as determined from
the best fit curve described in Guidance Note 2. 
c) In the event that the rating level is above the limit(s) set out in the Tables
attached to the noise conditions or the noise limits for a complainant’s
dwelling approved in accordance with paragraph (d) of the noise condition,
the independent consultant shall undertake a further assessment of the
rating level to correct for background noise so that the rating level relates to
wind turbine noise immission only. 
Page 199

Page 200

d) The wind farm operator shall ensure that all the wind turbines in the
development are turned off for such period as the independent consultant
requires to undertake the further assessment.  The further assessment shall
be undertaken in accordance with the following steps: 
e) Repeating the steps in Guidance Note 2, with the wind farm switched off,
and determining the background noise (L3) at each integer wind speed
within the range requested by the Local Planning Authority in its written
request under paragraph (b) and the approved protocol under paragraph (c)
of the noise condition. 
f) The wind farm noise (L1) at this speed shall then be calculated as follows
where L2 is the measured level with turbines running but without the addition
of any tonal penalty: 
g) The rating level shall be re-calculated by adding arithmetically the tonal
penalty (if any is applied in accordance with Note 3) to the derived wind farm
noise L1 at that integer wind speed. 
h) If the rating level after adjustment for background noise contribution and
adjustment for amplitude modulation and/or tonal penalties (if required in
accordance with Guidance Note 3 and 5) at any integer wind speed lies at or
below the values set out in the Tables attached to the conditions or at or
below the noise limits approved by the Local Planning Authority for a
complainant’s dwelling in accordance with paragraph (d) of the noise
condition then no further action is necessary.  If the rating level at any integer
wind speed exceeds the values set out in the Tables attached to the
conditions or the noise limits approved by the Local Planning Authority for a
complainant’s dwelling in accordance with paragraph (d) of the noise
condition then the development fails to comply with the conditions. 
Guidance Note 5 
a) Where, in accordance with the assessment protocol agreed under the noise
condition, noise immissions at the location or locations where compliance
measurements are being undertaken contain or are likely to contain an
amplitude modulation component, an amplitude modulation penalty is to be
calculated and applied using the following rating procedure. 
b) The analysis of amplitude modulation shall be undertaken using the Institute
of Acoustics (IOA) metric described in “A Method for Rating Amplitude
Modulation in Wind Turbine Noise” dated 9th August 2016 or any update of
that method.  The value of AM obtained with the IOA metric for each ten-
minute period shall be converted to a penalty in decibels in accordance with
the graph below.  At each integer wind speed, a penalty for AM would be
based on the arithmetic average of the calculated penalties for all valid
periods assessed at this wind speed.
Page 200

Page 201

Guidance Note 6 
At each integer wind speed, the tonal penalty determined in accordance with
Guidance Note 3 and the amplitude modulation penalties determined in
accordance with Guidance Note 5 would be added arithmetically, except where
the AM penalty and the tonal penalty relate to the same characteristic (eg
amplitude modulated tones), only the larger of the AM or tonal penalty should be
applied. 
LIST OF PLANS AND DRAWINGS SHOWING THE DEVELOPMENT
Reference No. Version No. Title/Description 
Environmental Appraisal  
Forestry Statement  
Outline Construction Environmental Management Plan  
Extended Phase 1 Survey  
Ornithological Survey (sensitive)
FIGURE 3-5  Control building
FIGURE 3-7  Crane hardstanding
FIGURE 3-6  Foundations
FIGURE 6-3  Infrastructure buffers
FIGURE 3-1  Location plan
FIGURE 3-2  Site layout plan
FIGURE 3-4  Turbine elevations 
Page 201

Page 202

Page 202

Page 203

Plans, drawings and other material submitted to the local authority
are protected by the Copyright, Designs and Patents Act 1988
(section 47). You may only use material which is downloaded and/
or printed for consultation purposes, to compare current
applications with previous schemes and to check whether
developments have been completed in accordance with approved
plans.
Further copies must not be made without the prior permission of
the copyright owner.
Maps shown in the Planning Committee Report can only be used
for the purposes of the Planning Committee. Any other use risks
infringing Crown Copyright and may lead to prosecution or civil
proceedings. Maps produced within this Planning Committee
Report can only be reproduced with the express permission of the
Moray Council and other Copyright holders. This permission must
be granted in advance.
PLANNING APPLICATION
COMMITTEE SITE PLAN
Site Address:
Lurg Hill
Deskford
Planning Application Ref Number: 
22/00563/APP
Location Plan
Applicant Name: 
Vento Ludens Ltd
Page 203

Page 204

Site Location
Page 204

Page 205

Site layout
Page 205

Page 206

Turbine elevations
Page 206

Page 207

Control building
Page 207

Page 208

16/01664/APP
Page 208

Page 209

Photo 1
16/
Page 209

Page 210

Photo 2
16/
Page 210

Page 211

Photo 3
16/
Page 211

Page 212

Page 212

Page 213

PLANNING APPLICATION: 22/00563/APP 
In the event that a recommendation on this planning application is overturned the
Committee is reminded of the advice contained on the front page of the agenda for
Reports on Applications 
1. THE PROPOSAL 
   This application seeks planning permission for the erection of 3 wind
turbines (at maximum height 149.9m to blade tip), control
building/substation and formation of access tracks at Lurg Hill, Deskford.
This is an alternative scheme to the approved 5 wind turbine ‘Consented
Development’ (17/01198/EIA, Planning Appeal reference: PPA-300-2052
and 22/00339/APP).
   The development components would include the following:
1. 3 wind turbine generators of up to 149.9 tip height, with a 81.9m high
hub, 136m rotor diameter and a maximum rated output of 15MW (3 x
5MW);
2. Turbine concrete foundations (x3) up to 23m diameter, up to 3m
deep (dependent on ground conditions); 
3. Hardstanding areas (x3), approx. 50m x 25m with compacted
granular fill over a geo-grid, to be located adjacent to each turbine
for crane and temporary storage for turbine components (to be left in
place for the lifetime of the development to facilitate future
maintenance, replacement of major components and
decommissioning).
4. Compound approx. 30m x 20m of hardcore surface/concrete
platforms enclosed by security fencing, containing control building
(approx. 10m x 15m x 5.5m) to house switchgear and other control
systems plus staff welfare facilities and external
transformer/generator compound area. Foul drainage would be
collected in a septic tank with soakaway, and water supply for
welfare facilities would to be provided by water harvesting and
ultraviolet filter system (or other drinking water arrangements to be
agreed if not suitable). 
5. Upgraded vehicular site access point onto the public road and
construction of passing places; 
6. On-site access tracks (new and upgrading of existing onsite tracks),
approx. upgraded track length: 2,670m, approx. new track length:
360m; 
7. On-site electrical connections, cable trenches 1m deep, 1.2m wide
installed in areas along access tracks; 
8. Watercourse crossings - 6 no. existing culverts to be upgraded; and
9. A temporary construction compound and laydown area 50m x 50m.
   As noted from the supporting Planning Statement and Environmental
Appraisal: 
   Detailed design will be completed following pre-construction works
and a 50m micro siting allowance is proposed for all infrastructure
Page 213

Page 214

components to allow for any necessary adjustments (to allow
flexibility in siting for localised ground conditions). 
   The locations of the turbines and proposed infrastructure (as per the
consented development) have been designed to avoid onsite
environmental constraints including gradient, watercourses and peat
and remain an appropriate distance away from residential properties
to minimise potential impact from noise and visual impact on
residential amenity. 
   The proposed development is anticipated to be operational for 35
years, following which it would be decommissioned and restoration
undertaken as agreed, or a new planning application submitted to
extend the life of the Wind Farm. 
   The application is accompanied by supporting documents including an
Environmental Appraisal and associated technical appendices (Extended
Phase 1 Habitat Survey and Bat Habitat Assessment, Ornithological
Survey Report, Residential Visual Amenity Assessment, Shadow Flicker
Assessment, Noise Impact Assessment, Forestry Statement, Abnormal
Loads Assessment, Cultural Heritage Gazeteer), Design and Access
Statement, Planning Statement, Outline Construction Environmental
Management Plan (CEMP) and a Pre-Application Consultation Report. 
   The proposed development design and footprint remains the same as the
consented development, other than the changes outlined below:
   Reduction in turbines from 5 to 3 turbines (removing the northern-
most turbines nos. 4 and 5);
   Increase in tip height from 130m to 149.9m, and rotor blade diameter
from 90m to 136m;
   Reduction in new track length from approximately 760m to 360m;
and
   Increase in turbine foundation diameter from 20m to 23m. 
2. THE SITE 
   The proposed development site is located approximately 8.7km south of
Cullen and 10km northeast of Keith.
   The turbines would straddle the northern flank of Lurg Hill, located
approximately midway between Cullen and Keith. 
   The B9018 Keith to Cullen road runs north/south approx. 1km to the west
of the site. The site partially borders Aberdeenshire Council area to the
northeast. 
   The total site area covers approximately 137 hectares and comprises
plantation woodland (parts of which have been felled), heathland and
tracks, with approx. 2.5ha land take for turbines, and associated
infrastructure. 
   The site would be accessed from the north via an existing access track (to
be upgraded) which joins onto the nearby C4L (Bogmuchals - Berryhillock
Road); the access junction onto the C4L is to be upgraded and widened. 
   The site is not subject to any international, national, regional or local
landscape, built environment or nature conservation designations, and
there are no known designated archaeological assets within the site. 
Page 214

Page 215

   The site is not at risk of flooding from rivers. Small parts of the site are
subject to low/medium/high risk of surface water flooding, the extent of
which is localised. 
   The site lies within the Moray Onshore Wind Energy non-statutory
guidance (2020) 'Area of Search' for medium turbines (50m to 80m) but
outwith the search area for larger wind turbines. 
   The 'landmark hills' of Bin of Cullen and Knock Hill lie 6km and 4km to the
north-west and south-east respectively. 
3. HISTORY 
For the site: 
22/01324/APP – Section 42 application to modify Condition 1 of planning
permission 19/00908/APP to extend the expiration period of the consented
meteorological mast at Lurg Hill to 30 September 2025 – approved 27 October
2022. 
22/00339/APP – Section 42 application to vary condition 1 of planning
permission 17/01198/EIA to extend the operational lifetime of the consented
five turbine wind farm at Lurg Hill (Planning Appeal Reference:PPA-300-2052)
from 30 years to 35 years - approved 5 July 2022. 
21/01269/PAN – Proposal of Application Notice for proposal to construct 5 wind
turbines with tip height of up to 149.9m plus associated infrastructure on Lurg
Hill, Deskford. Responses dated 3 September and 14 October 2021 confirmed
consultation arrangements and publicity event to be acceptable, and provided
feedback from the Planning and Regulatory Services Committee to be taken
into account in the development of the application. This highlighted the need for
the Applicant to mitigate against the impact the extra height of the turbines will
have on the landscape by positioning them appropriately; and that connectivity
issues be borne in mind for members of the public with poor internet connection
during the virtual public consultation. 
21/00843/PEMAJ – Pre application major development enquiry to erect 5 wind
turbines with a tip height of up to 149.9m, associated infrastructure, crane
hardstandings, onsite access track, working areas and substation at Lurg Hill,
Deskford. Response issued 5 August 2021 provided pre application advice
including policy comments, consultee input and requirements in terms of
supporting information to accompany any application. 
20/01600/SCN - Screening Opinion adopted 19 January 2021 for proposed
development of up to 5 wind turbines with a tip height of up to 149.9m,
associated infrastructure, crane hardstandings, onsite access track, working
areas and substation at Lurg Hill, Deskford; assessment confirmed the proposal
to be a Schedule 2 development but not likely to result in significant
environmental effects when compared to the existing consented development,
and therefore not requiring to be subject to EIA procedures. 
17/01198/EIA – Erection of 5 wind turbines (at max height 130m to blade tip)
control building and substation and formation of access tracks (including turning
Page 215

Page 216

heads) hardstanding temporary construction compound and associated works
and infrastructure at Lurg Hill, Deskford - approved/allowed at appeal by the
Planning and Environmental Appeals Division (DPEA) on 25 February 2019
(Planning Appeal Reference:PPA-300-2052). 
15/01340/SCO - Scoping Opinion issued for 6 turbines with tip height up to
130m at Lurg Hill, Deskford - response confirmed that EIA was required and
environmental issues and potential impacts to be taken into account were
identified. 
For the area: 
21/01887/SCO - Scoping Opinion request for the redesign of Consented
Aultmore Wind Farm 16 turbines up to 200m to blade tip. Scoping response to
Energy Consent Unit issued 20 January 2022. This site lies 3.4km to the west
of the application site. 
21/00484/APP – Vary condition 1 attached to planning permission
16/01657/APP to increase the operational life period of Aultmore Wind Farm
(13 wind turbines (12 x 110m high, and 1 x 90m high) from 27 to 30 years at
Aultmore Forest, Drybridge - approved 20 August 2021. This proposal lies
3.4km to the west of the application site and has yet to be constructed. 
16/01657/APP- Vary conditions 1, 18 and 24 of planning permission
07/02375/EIA relating to the Aultmore Wind Farm approved 28/02/17. This
consent was granted for a 5 year period and was extended by 21/00484/APP
above. This proposal lies 3.4km to the west of the application site. 
13/02057/S36 - Erection of 16 wind turbines (125m to blade tip) at Hill of Towie
Windfarm, known as Hill of Towie II. Located immediately south of the existing
Hill of Towie wind farm, this proposal was subject of a Public Inquiry in
September 2015 (following objection by the Moray Council to the Scottish
Government Energy Consents and Deployment Unit (lodged in 2014)), and
subsequently approved in June 2017. This wind farm has yet to be constructed
and will lie 20km to the south-west of the current proposal. 
12/01165/APP - Erection of 1 no. turbine (80m to tip) at Edingight, Grange,
Keith - approval/allowed on appeal by DPEA January 2013. This lies 2.1km to
the south-east of the application site and is operational. 
11/01384/APP - Erection of 1 no. wind turbine (56m rotor diameter) with a
maximum height of up to 78m and ancillary infrastructure at Followsters,
Newmill - approved February 2012. Permission to vary the turbine model
(revised nacelle design) was subsequently approved under 13/00479/APP in
May 2013. This lies 9.2km south-west of the application site and is operational. 
10/02092/EIA - Formation of wind farm comprising 6 wind turbines (125m in
height, total capacity up to 21MW) and associated infrastructure including
access tracks, control building housing switchgear equipment and buried
cables at Edintore, Keith - approved/allowed at appeal by DPEA in 2012. These
are located approx. 15km to the southwest of the site and are operational. 
Page 216

Page 217

09/00763/FUL - Erection of 2 x 2.3 megawatt wind turbines (92.4m to tip) and
associated works at Netherton of Windyhills, Grange Crossroads - approved
October 2010. These are located 1.4km south-west of the current application
site and are operational. 
09/00247/FUL - Install two 800kw wind turbines (79m to tip) at Myreton,
Crossroads - approved/allowed following review by Local Review Body July
2010. These are located 1.5km to the south-west of the application site and are
operational. 
07/01102/FUL - Install a 50kw wind turbine with a hub height of 50m and blade
diameter of 48m (79.6m to tip) at Myreton, Crossroads - approved February
2008. This lies 1.4km to the southwest of the application site and is operational. 
07/02375/EIA - Construction, operation and decommission of a wind farm
comprising 13 wind turbines (12 x 110m high, and 1 x 90m high) and other
ancillary development at Aultmore Forest, Drybridge - approved 27.02.2014
and subsequently extended on 28.02.2017 under application 16/01657/APP to
vary conditions 1, 18 and 24 of planning permission 07/02375/EIA (extension to
time limit and operational period, and noise levels). This proposal lies 3.4km to
the west of the application site and has yet to be constructed. 
04/02472/FUL - Construct 1 no. wind turbine (70m to tip height) at Balnamoon,
Crossroads, Keith - approved/allowed on appeal by Scottish Ministers October
2005. This lies 3.5km to the south-west and is operational. 
02/02099/EIA - Erection of 21 wind turbines (100m to tip) and 2 wind masts at
Hills of Towie, Knockan and McHattie's Cairn, Drummuir - approved/allowed on
appeal in 2005. These lie 18km to the southwest and have been erected and
are operational. 
Aberdeenshire turbines: 
APP/2009/3565 - Erection of 2 no. wind turbines (99.5m to tip) at Land at
Muirake, Cornhill, Banff - approved 2010. These are located 5km to the east
and are erected and operational. 
APP/2012/2786 - Erection of 1 no wind turbine (79m to tip) at Land at Braeside,
Fordyce, Banff - approved August 2012. This lies 3.5km to the north-east and
has yet to be constructed. 
APP/2003/1692 - Erection of 7 Wind Turbines at Boyndie Airfield, Banff -
approved July 2004. These lie 12km to the north-east and is operational. 
4. POLICY - SEE APPENDIX 
5. ADVERTISEMENTS 
5.1 Advertised as a departure from the development plan. 
Advertised under Schedule 3 of the Development Management Regulations
2013. 
Page 217

Page 218

Advertised for neighbour notification purposes. 
6. CONSULTATIONS 
Strategic Planning and Development (SPD) – No objection. Comments
outlining relevant provisions of the Moray Local Development Plan 2020,
Scottish Planning Policy (SPP) (Spatial Framework) and Moray Onshore Wind
Energy (MOWE) Non-Statutory Guidance 2020 and Moray Wind Energy
Landscape Capacity Study 2017.  
Notes that the principle of development has been established through the
existing consent and the proposal seeks to increase the heights of the consent
turbines by 19.9m to 149.9m (blade tip). The proposal is likely to incur
significant adverse landscape character and visual effects, however these
effects need to be considered in the context of the consented scheme and the
omission of two turbines of the consented scheme would provide some limited
mitigation of visual effects in close views from residential properties and Cullen
House. With this mitigation and when compared to the consented scheme, for
landscape and visual effects, the proposal is considered to be an acceptable
departure from Policies DP1 and DP9, subject to Turbines 4 and 5 of
17/01198/EIA not being constructed alongside the proposal. 
The development proposes enhancement measures which will lead to
biodiversity gain through the restoration of woodland and habitat reinstatement.
The proposal will result in the permanent removal of 9.3ha of woodland that
requires off-site compensatory planting and a management plan must be
submitted for approval by Scottish Forestry and the Planning Authority prior to
commencement of development. 
Note that the proposed development will generate up to a maximum of 15MW
of renewable electricity, helping meet the Scottish Government’s renewable
energy generation targets in the post-2020 period and help work towards the
net zero GHG emission target by 2045. 
The proposal complies with all other relevant policy requirements, as set out in
PP3 Infrastructure and Services, DP1 Development Principles, DP9 Renewable
Energy, EP2 Biodiversity, EP3 Special Landscape Areas and Landscape
Character and EP7 Forestry, Woodlands and Trees, subject to conditions
where appropriate. 
Environmental Health - No objection, subject to conditions requiring levels of
noise immissions from the combined effects of the wind turbines (including
application of any tonal penalty and amplitude modulation) not to exceed
identified levels; the wind farm operator to log power production data, wind
speed and wind direction for not less than 24 months, to be provided to the
Council upon request; measures to address any complaints received including
assessment of noise immissions; a 12 month monitoring scheme of noise
immissions; submission of details the final make/model, design power rating
and sound power levels of the turbine; construction activities including vehicle
movements permitted only between 07:00 to 19:00 hrs, Monday - Friday and
07:00 to 13:00 hrs, Saturdays, and no other times (including National Holiday)
Page 218

Page 219

unless otherwise agreed and where so demonstrated exceptional
circumstances require limited periods of construction works; no blasting in the
formation and use of borrow pits; the installation of a shadow flicker impact
control unit to turbine 1; and measures to address any complaints received
regarding shadow flicker. 
Environmental Health, Contaminated Land - No objection. 
Environmental Health, Private Water Supplies - No objection, subject to
condition requiring submission/approval of details of arrangements to monitor
private water supplies during all stages of the development, and in the event of
any adverse effects on water quality or quantity being identified, the
arrangements and procedures to undertake restorative and remedial works to
maintain any supply. This shall include measures to monitor the supply known
as 'Mid Skeith' to detect any changes to water quality and allow for further
mitigation measures to be put in place if necessary. 
Informative advice regarding notification to the Council of any water supply to
the control building for human consumption which involves a new source or
connection to a private water supply. 
Scottish Water – No objection. The proposed development activity and site
boundary falls within a drinking water catchment where a Scottish Water
abstraction is located. Scottish Water abstractions are designated as Drinking
Water Protected Areas (DWPA) under Article 7 of the Water Framework
Directive. The Muiresk Intake (River Deveron) supplies Turriff Water Treatment
Works (WTW) and it is essential that water quality and water quantity in the
area are protected. The development activity is a sufficient distance from the
intake that it is likely to be low risk, however care should be taken and water
quality protection measures must be implemented. Informative advice seeking
notification to Scottish Water prior to works commencing. 
Environmental Protection/Moray Access Manager - No objection. 
Transportation Manager - No objection, subject to conditions as
recommended requiring detailed proposals of abnormal load trial run(s) to be
undertaken prior to construction and deliveries to determine additional
accommodation works, restrictions, frequency; a Construction Traffic
Management Plan; details of upgrading works of the C4L (Bogmuchals -
Berryhillock Road)/site access junction including access width, radii, kerbing,
visibility splay and drainage; detailed drawings/construction of 3 passing places
on the C4L road; road widening/alterations/verge hardening to be permanent
for duration of development; evidence of a signed S96 'Wear and Tear'
agreement including a 'before and after' condition video surveys required for
delivery and construction traffic routes; etc. 
Moray Flood Risk Management - No objection, subject to conditions
regarding submission/approval of a detailed drainage design and SUDs
measures; a construction surface water management to include a map of all
watercourses, mitigation proposals and justification of appropriateness, map of
mitigation locations and emergency and spill procedures; drainage
management plans to address surface water and foul drainage; and details of
Page 219

Page 220

stream crossings and all water course engineering designed to accommodate
the 1 in 200 year flows (including a 30% allowance for climate change). 
SEPA – Notes that the application comprises no changes to the footprint or
location of infrastructure of the consented development (Planning application
17/01198/EIA, Planning Appeal PPA-300- 2052) apart from an increase in tip
height and the removal of the two northern most turbines. For the previous
application SEPA requested conditions be attached to any consent and these
were attached to the consented development. 
As there are no changes to the proposal in relation to its own interests, SEPA
requests that the same, or similarly worded conditions be attached to any
consent for the present application for the three turbines. It also requests that
condition wording is updated to ensure that detailed peat probing results in the
vicinity of turbine 1 is supplied with the CEMP to show that deep peat will be
avoided.   
(Officer Note: For sake of completeness, these conditions require the
submission/approval of a plan showing how the finalised micro-sited layout has
been designed to minimise impacts on and avoid areas of deep peat; a site-
specific Construction and Environmental Management Plan (CEMP) to address
all waste management, pollution prevention and environmental management
issues; details for all water crossings, to be designed to accommodate 1 in 200
year peak flows (with allowance for climate change) to reduce flood risk; and no
borrow pits to be permitted.) 
NatureScot – NatureScot has reviewed the application documents and
confidential ornithological report. Notes that it has provided advice in the past
for this site and there are no impacts on designated sites or issues that would
raise concerns of national interest. In support of their planning application the
applicant has submitted an environmental appraisal (EA). This includes
chapters on ecology and ornithology which include mitigation that is appropriate
to minimise the risk to ecological interests during the construction and operation
of the wind farm. 
RSPB Scotland – No response at time of report. 
Scottish Forestry – Scottish Forestry (SF) has previously (17/01198/EIA )
been in pre-consultation discussion with the developer in regard to this
application and the revised forestry statement incorporates proposed
amendments to the previous application, primarily a reduction in the area of
woodland loss requiring off-site compensatory planting.
Scottish Forestry notes that whilst considerable effort has been taken to reduce
the need to permanently remove woodland, it is unavoidable that 9.3ha of
compensatory planting will be required to ensure that there is no net loss of
woodland as a result of this development. Commitment from the applicant to
provide this planting is set out within the Forestry Statement summary
submitted with the application. 
Based on the above, SF raises no objection subject to a condition requiring
delivery of compensatory planting (CP) through an approved management plan
agreed with SF and the planning authority prior to the commencement of the
Page 220

Page 221

proposed development and the felling of trees. The CP must provide all the
details of the proposed planting, including its maintenance over the entire life-
span of the development.  
Historic Environment Scotland – Historic Environment Scotland (HES) has
assessed the application for its historic environment interests and has no
comments to make on the proposals. Our decision not to provide comments
should not be taken as our support for the proposals. This application should be
determined in accordance with national and local policy on development
affecting the historic environment, together with related policy guidance. 
Transport Scotland - No objection, subject to conditions requiring
submission/approval of the routing of any abnormal loads on the trunk road
network, accommodation measures and traffic management; additional signing
or temporary traffic control measures; proposals for an abnormal loads delivery
trail-run with involvement of Police Scotland; a Construction Traffic
Management Plan (CTMP); all vehicles transporting construction material to
and from the proposed development to be sheeted; installation of vehicle wheel
cleansing facilities; and decommissioning plan. 
Aberdeenshire Council - No objection. Notes that conditions as detailed under
PPA-300-2052 (or variants of such) will apply to the current application, and
recommends no further conditions. Also provides a justification statement for
information purposes setting out the principle matters for consideration from
Aberdeenshire Council’s perspective, which relate to landscape and visual
impact and resultant noise experienced by sensitive receptors: 
Noise 
Aberdeenshire Council’s Environmental Health service advises no objection. It
advises:
Regarding operational noise and receptors in Aberdeenshire, as the
development is within Moray Council area it’s Moray Councils responsibility to
scrutinise the NIA in detail and set appropriate noise limits for all properties,
whether in Moray or Aberdeenshire. It is noted that the nearest properties lie
within Moray. Provided that reasonable noise limits are set, Environmental
Health has no concerns. 
An attached consultation response from the Environment Health Service
highlights Amplitude Modulation effects which (based on experience in
Aberdeenshire) feature in the majority of noise complaints and as such
recommends that this should be considered and applied as a condition if the
Planning Authority are minded to grant consent.   
Assessment of Landscape and Visual impact
In assessing the Landscape and Visual impact of the proposed 3 x 149.9m high
(to tip) turbines, they must be considered in the context of the consented
scheme comprising 5 x 130m high turbines. It is acknowledged that 3 principal
viewpoints have been identified within Aberdeenshire area (Durn Hill (11),
Findlater (12) and Cornhill (8). Having now looked that the comparison
viewpoints, along with the ZTV’s and wirelines of the proposed development
and the consented development, it is acknowledged that there is some
additional visual dominance in that the turbines will be more visible from some
Page 221

Page 222

of the highlighted visual receptors as a result of both the height increment and
blade diameter increment. However, it is considered that the increment in
height of the 3 southern turbines within the group is somewhat off-set by the
removal of the 2 northerly consented turbines from the development. 
The increment in scale of the proposed development is more noticeable at
locations in close proximity to the proposed site. These locations are outwith
the Aberdeenshire Council boundary. 
Taking account of the above, the magnitude of change between the consented
and proposed developments is considered to be low. On this basis,
Aberdeenshire Council raise no objections to the development.  
Aberdeenshire Council Archaeology Service - No objection. Requests that
comment to be passed to applicant to note that Durn Hill Hillfort (8km to the
northwest of the application site) is now designated as a scheduled monument
(SM 13748). 
MOD Safeguarding – No safeguarding objection, subject to conditions
requiring the submission/approval of an Air Traffic Control Radar Mitigation
Scheme to mitigate the impact of the development upon the operation of the
Primary Surveillance Radar at RAF Lossiemouth, an aviation lighting scheme
covering construction and operational phases to maintain civil and military
aviation safety requirements, and a scheme for aviation charting and safety
management confirming date of commencement of works, maximum height of
construction equipment, date wind turbines are brought into use and final
coordinates and maximum heights of wind turbines and any anemometer
mast(s).  
National Air Traffic Systems - No safeguarding objection. 
Civil Aviation Authority - No response received at time of report. 
Aberdeen International Airport Ltd – No objection.   
Atkins Global - No objection. 
Joint Radio Company (JRC) Windfarms – No objection. 
Ofcom - No response received at time of report. 
Scottish and Southern Energy - No response at time of report. 
Cullen and Deskford Community Council - No objection. 
Strathisla Community Council - No response at time of report. 
7. OBJECTIONS-REPRESENTATIONS 
NOTE: Following the determination of this application, name and address
details will be/have been removed (i.e. redacted) in accordance with the
Page 222

Page 223

General Data Protection Regulations (paragraph 3 of Minute, Planning &
Regulatory Services Committee 16 September 2014). 
Issue: Shadow flicker concerns affecting nearby residential property due to the
close proximity of the nearest turbines, forests may partially screen property
from the wind farm for the foreseeable future, but at some point this will be
felled, exposing neighbours to turbines that are too close to residential
properties.
Comment (PO): From the Environmental Appraisal and updated shadow flicker
modelling, three inhabited residential properties to the north are likely to
experience potential shadow flicker effects from the northern-most turbine 1,
exceeding UK Government guidelines of 30 hours of shadow flicker per year or
30 minutes per day. In order to mitigate these impacts the applicant proposes
to install a shadow flicker impact control unit/module to turbine 1 (which would
stop and start the turbine during the affected periods) similar to mitigation
proposed for the consented development. The Environmental Health Section
has reviewed and is content with this information, and has raised no objection
subject to imposition of a condition requiring installation of a shadow flicker
control module to turbine 1, and measures to address any complaints received
regarding shadow flicker. 
Issue Grateful that the developers listened to the community and omitted
turbines no. 4 and no. 5 from the new development proposal, however was not
given any reassurances that the two excluded turbines would not be
constructed at a later date. 
Comment (PO): The proposed development and associated impacts have
been assessed based on evaluation of the submitted plans and information for
3 wind turbines only. As the current proposal and consented development
occupy the same area, to ensure a satisfactory form of development (and avoid
any ambiguity regarding the terms of this consent) a condition shall be imposed
preventing the implementation of this permission in addition to, or in conjunction
with the consented development. The applicant has confirmed that it does have
an intention to erect turbines 4 and 5 of the consented development. 
Issue: Adverse visual impact on the area due to the size of the proposed wind
turbines, 
Comment (PO): The proposal is considered, on balance, to represent an
appropriate form of renewable development for this location with acceptable
visual impacts, as outlined within the observations section below. The proposed
Development would introduce changes to the proportions of the turbines and a
reduction in turbine numbers when compared with the Consented
Development. While adverse effects on landscape character and views would
be associated with the proposal, these effects require to be considered in the
context of the existing consent of a wind farm on this site. 
Issue: Impacts on wildlife during construction and operation of the wind farm.
Comment (PO): The EA has assessed the likely effects of the development on
ecological and ornithology interests, and predicts no significant adverse
impacts subject to mitigation measures identified within the EA being fully
Page 223

Page 224

implemented. NatureScot has raised no concerns in relation to the proposal,
and from review of the chapters on ecology and ornithology in the EA considers
that the proposed mitigation is appropriate to minimise the risk to ecological
interests during the construction and operation of the wind farm. 
Issue: The planning documentation contains a mistake, contributor’s property
is not the stated distance from the nearest turbine which is closer.
Comment (PO): The applicant has clarified that page 12 of the Residential
Visual Amenity Assessment (RVAA) contains an error. The distance to the
contributor’s property (Little Skeith) of 1.86km should read 1.1km, as per Table
1 of the RVAA. The distance is evident from the maps within the RVAA and has
informed the assessment conclusions. 
8. OBSERVATIONS 
8.1 Background 
For this application, the Pre-Application Consultation Report outlines the extent
of the applicant's engagement with the local community in accordance with the
Proposal of Application Notice (PAN) (21/01269/PAN). This included holding an
online virtual public exhibition (attended by 11 people), a second physical in-
person public exhibition (attended by 6 people), consultation with Cullen and
Deskford Community Council, Strathisla Community Council, Deskford and
District Community Association, Fordyce and Sandend Community Council,
implementation of a dedicated project website and circulation of two separate
letters to 102 local residents within a 2km radius from the proposed
development. Nine feedback forms were completed/submitted across both
public events.   
8.1.1 The report sets out that an interim design (for 5 turbines) was presented to local
residents at the virtual public exhibition held in October 2021, with the design
being based on the proposed layout for the consented development.
Comments raised through consultation then informed the progression of the
final project design and amendments were made to the proposals by removing
turbines 4 and 5, and the assessment, where necessary. Topics of concern to
local residents included ecology and ornithology, transport, visual impacts,
noise, access and the impact on local communities. These concerns were
previously addressed within the application for the consented development and
where relevant were taken forward in the final assessment and design of the
current proposed development. Furthermore design changes made following
the first public exhibition in October 2021 directly addressed comments
received from the public, in particular in relation to feedback regarding turbine
5. As noted from the report the removal of turbines 4 and 5 has lessened the
effects of the proposed development further, particularly in respect to noise and
visual effects, without compromising the overall positive contribution to
achieving climate change targets. 
8.1.2 An EIA Screening request has been submitted alongside the application. From
review of this request and having screened the application against the EIA
Regulations the proposal is not considered to be EIA development. 
Page 224

Page 225

8.1.3 Following consideration of the revised draft National Planning Framework 4
which was laid before parliament on 8th November 2022, the draft (yet to be
formally adopted) is to be given no weight in the consideration of planning
applications. Section 25 of the 1997 Act as amended requires applications to
be determined in accordance with the Development Plan i.e. the adopted
Moray Local Development Plan 2020 (MLDP) unless material considerations
indicate otherwise.   
8.1.4 The main issues are considered below. 
8.2 Relationship of proposal to national renewable energy policy/guidance 
International and UK policy frameworks are supportive of renewable energy
proposals which help to facilitate a transition to a low carbon economy. National
Planning Framework (NPF3) for Scotland sets out the spatial strategy for
Scotland's development. NPF3 makes specific reference to onshore wind
energy having an important role in delivering the commitment to a low carbon
energy generation. The revised draft National Planning Framework 4 (not
adopted) sets out that measures to address the global climate emergency and
nature crises, and that reduction of carbon emissions will be accelerated. This
includes support for all forms of renewable energy development, onshore and
offshore. 
8.2.1 The Climate Change (Scotland) Act 2009 (the Climate Change Act) has
committed Scotland to becoming carbon-neutral by 2045. This target is legally
binding rather than an ambition and requires to be reflected in the way in which
renewable energy projects are addressed by public bodies when exercising
their functions. Beyond NPF3 there are a number of considerations relevant to
the planning consideration process, which have been taken into account in
arriving at the recommendation below. These include amongst others, The
Scottish Government’s Programme for Scotland 2020-21, The Environment
Strategy for Scotland, February 2020, Climate Change (Emissions Reductions
Targets) (Scotland) Act 2019, Scottish Government Climate Change Plan
(2018), Scottish Government Onshore Wind Policy Statement 2017 and
Scottish Energy Strategy (2017). These highlight the need to reduce carbon
emissions (for which wind energy will play key a part) but do qualify this with
the need to protect landscapes, built and natural heritage, residents and other
interests. 
8.2.2 The commitment to the creation of a low carbon place is reiterated in Scottish
Planning Policy. The applicant’s Planning Statement sets out that national
policy is significant and supportive of this proposed wind farm which will provide
clean renewable energy, contributing to electricity supply, and support
measures to tackle climate change. 
8.2.3 Scottish Planning Policy (SPP) requires that “planning should direct the right
development to the right place”, which is an important issue in this proposal.
The policy principles set out for “Delivering Heat and Electricity” in SPP include;
   Support the transformational change to a low carbon economy, consistent
with national objectives and targets; 
   Support the development of a diverse range of electricity generation from
renewable energy technologies - including the expansion of renewable
energy generation capacity and the development of heat networks; 
Page 225

Page 226

   Guide developments to appropriate locations and advise on the issues
that will be taken into account when specific proposals are being
assessed. 
8.3 Spatial Framework
Scottish Planning Policy (SPP) requires planning authorities to set out, in the
development plan, a spatial framework identifying those areas that are likely to
be most appropriate for onshore wind farms as a guide for developers and
communities, following a set methodology (Para 161). This has been done
through the Spatial Framework within the Moray Local Development Plan
(MLDP) 2020, which has been a broad-brush approach required to comply with
SPP and covers a significant land area of Moray. All the proposed turbines are
located within an area with potential for wind farm development of turbines over
35 metres to tip height, with no upper height limit identified. 
8.3.1 The limitations of the very strategic Spatial Framework are recognised and SPP
(Para 162) further requires that local development planning authorities should
identify where there is strategic capacity for wind farms and areas with the
greatest potential for wind development. The Moray Onshore Wind Energy
(MOWE) Non-Statutory Guidance 2020 identifies such areas and none of the
proposed turbines are located within an Area of Greatest Potential for Very
Large Turbines, Extensions and Repowering. Notwithstanding this, the principle
of development has been established by the existing consent and therefore the
proposal is considered to support the principles of SPP highlighted above. 
8.4 Moray Onshore Wind Energy (MOWE) Non-Statutory Guidance 2020 and
Moray Wind Energy Landscape Capacity Study 2017 
The MOWE Non-Statutory Guidance and the Landscape Capacity Study are
material considerations for development management purposes. Incorporating
the outcomes from the Landscape Capacity Study, the Guidance identifies five
typologies of wind turbine, including “Very Large 130m-150m” (to blade tip),
and highlights that there is very limited scope to accommodate further large
scale wind turbine developments in Moray in landscape and visual terms. 
8.4.1 The proposed development is located within the Broad Forested Hills Within
Upland Farmland (8a) Landscape Character Type (LCT) as defined in the
Guidance and Landscape Capacity Study. LCT8a is assessed as having high
sensitivity to the very large typology (>130m) with no scope to accommodate
turbines of this scale in this landscape. In this case, the principle of
development has however been established at this location through the existing
consent and the proposal seeks to increase the heights of the consent turbines
by 19.9m. 
8.5 Moray Local Development Plan 2020 
8.6 Principle of Renewable Energy Proposal (DP9 and PP2) 
Policy DP9 Renewable Energy states that all renewable energy proposals will
be considered favourably where they meet the following criteria:
i.   They are compliant with policies to safeguard and enhance the built and
natural environment; 
ii.   They do not result in the permanent loss or permanent damage of prime
agricultural land;  
Page 226

Page 227

iii.   They avoid of address any unacceptable significant adverse impacts
including: 
 Landscape and visual impacts. 
 Noise impacts. 
 Air quality impacts. 
 Electromagnetic disturbance. 
 Impact on water environment. 
 Impact on carbon rich soils and peat land hydrology. 
 Impact on woodland and forestry interests. 
 Traffic impact mitigation during both construction and operation. 
 Ecological Impact. 
 Impact on tourism and recreational interests. 
8.6.1 In addition, the policy sets out proposals will be considered against the extent
to which it contributes to renewable energy generation targets, effects on
greenhouse gas emissions and economic benefits, such as employment. 
8.6.2 For onshore wind turbines the policy states that detailed consideration will be
determined through site specific consideration of matters such as landscape
and visual impact, cumulative impact, along with other impacts such as noise,
shadow flicker, visual dominance etc., on which further guidance is set out in
the MOWE Non-Statutory Guidance and as informed by the Landscape
Capacity Study. The submitted Environmental Appraisal Report (EA-R)
provides an assessment of these potential impacts which are detailed within the
observations section below. 
8.6.3 The Planning Statement (PS) sets out that the proposed development will
generate up to a maximum of 15MW of renewable electricity, helping meet the
Scottish Government’s renewable energy generation targets in the post-2020
period and assist towards meeting the net zero emission target by 2045. This is
anticipated to generate an average annual electricity output in the region of
52,500 MWh, the equivalent of electricity for approximately 14,000 households
and offsetting 22,601 tonnes of carbon dioxide per year, for its proposed 35-
year life. It will therefore make a notable contribution to progress towards
achieving the targets set out in the Renewables Route Map and the Onshore
Wind Policy Statement. It will also contribute to employment opportunities and
likely result in beneficial impacts in terms of job creation and opportunities for
local businesses. 
8.6.4 PP2 Sustainable Economic Growth states that development proposals which
support the Moray Economic Strategy to deliver sustainable economic growth
will be supported where the natural and built environment is safeguarded. As
noted from the Planning Statement the proposed development would contribute
to continued growth of the construction and engineering industry within the
region through the provision of employment opportunities. 
8.7 Landscape and Visual Appraisal 
(DP1, DP9 and MOWE Supplementary Guidance)
As already outlined, policy DP9 Renewable Energy supports wind energy
proposals in locations where the landscape is capable of accommodating the
development without unacceptable significant adverse impacts on landscape
Page 227

Page 228

character or visual amenity. Similarly policy DP1 Development Principles seeks
to ensure that the scale and design of any development is appropriate to the
landscape in which it is set. The proposal has been advertised as a departure
from this policy, given that the height of the turbines exceed the height advised
as appropriate to the capacity of the landscape in which they would sit. 
8.7.1 As already outlined Landscape and Visual Impact Assessment for onshore
energy proposals in Moray is assessed against Moray Onshore Wind Energy
2017 Policy Guidance (MOWE) and The Moray Wind Energy Landscape
Capacity Study 2017 (MWELCS) which is a technical appendix to the MOWE.
This is non statutory Supplementary Guidance forming part of the MLDP 2020
and the Landscape Capacity Study is a material consideration, referenced in
policy DP9. 
8.7.2 The Council’s appointed Landscape Adviser has undertaken a detailed review
of the submitted Environmental Appraisal with regard to landscape, visual and
cumulative effects from the proposed development. The following assessment
is based upon this appraisal and has informed the officer’s consideration of
these aspects of the application:   
8.7.3 The Landscape and Visual Appraisal (LVA) set out in the EA
The Landscape and Visual Appraisal provided by the applicant principally
focusses on the difference between the consented and the proposed
developments. In adopting this approach, the consented development is
assumed to form the landscape and visual baseline. The LVA concludes that
the additional effects associated with the proposal (which comprises fewer but
larger turbines) would not be significant. 
8.7.4 The following appraisal summarises the effects of the proposed development
on the existing baseline prior to reaching a judgement on the differences
between the consented and proposed schemes in the conclusions to this
report. 
8.7.5 Effects on landscape character
From review of the LVA, the proposal would result in significant adverse
(localised) effects on the Broad Forested Hills within Upland Farmland
Landscape Character Type (LCT) 8a (in which the site is located). Similar
adverse effects would also arise on the smaller scale valley of the Burn of
Deskford which lies within the Rolling Coastal Farmland LCT 4a to the north of
the site. No other LCTs within Moray would be significantly affected. 
8.7.6 For the Broad Forested Hills within Upland Farmland LCT 8a, the Zone and
Theoretical Visibility Map (ZTV) shows that the proposed development would
have widespread theoretical visibility. When considered against the existing
baseline, the proposed development would have a similarly localised adverse
effect on the character of this LCT as the consented development. There is a
slight difference in the area of the LCT physically affected by the proposed
development as a result of the two removed turbines, and the increased scale
of the proposed development turbines also results in very slight increases in
theoretical visibility extent across the LCT. However, the underlying landscape
characteristics of indistinct upland landform with simple forestry and moorland
Page 228

Page 229

landcover found within this LCT provide a clear upland context for development
of this scale. 
8.7.7 Taking these factors into account, the magnitude of change against the existing
baseline situation is considered to be medium-high within a localised area of
this LCT (within around 2km of the proposed development turbines). This
magnitude of change would reduce to low for parts of the LCT or other parts of
the LCT beyond this localised area surrounding the site. When considering the
implications of the design change from the consented development, the LVA
predicts that the increased scale of the proposed development combined with
the reduction of turbine numbers would not result in notable change to the LCT. 
8.7.8 For the Rolling Coastal Farmland LCT 4a, the ZTV shows that this LCT has
widespread theoretical visibility across the Deskford valley with breaks resulting
from the landforms of Clune Hill and Cotton Hill, the forestry of which further
restricts visibility in northern parts of this LCT, including in the area around
Cullen. When considered against the existing baseline, the proposed
development would have an adverse effect on the smaller scale of the Deskford
valley characteristics of this LCT, as an indirect consequence of the proposed
development appearing on the forested ridgeline that forms the backdrop to the
valley landscape below it. The magnitude of change against the existing
baseline situation is considered to be medium within a localised area of this
LCT (within the area of this LCT to the south of Deskford). Magnitude of change
would drop to low, north of this localised area and to negligible when north of
Clune Hill. 
8.7.9 When considering the implications of the design change from the consented
development, the LVA concludes that the increased scale of the proposed
development combined with the reduction of turbine numbers would not result
in any discernible change to the LCT. 
8.7.10  Effects on representative viewpoints
The Zone of Theoretical Visibility map in Figure 5.6 of the EA shows consistent
theoretical visibility extending within 5km of the wind farm becoming more
broken in extent beyond this distance. Visibility is shielded to some degree to
the north-west beyond 6km by the higher ground of Bin of Cullen and to the
west beyond 8km through Millstone Hill. 
8.7.11 14 representative viewpoints have been selected for the LVA with these being
agreed with the Council. These viewpoints lie within 10km of the revised
proposal, the focussed study area agreed for the LVA. The visualisations
produced by the applicant show the consented and proposed schemes from
each of these viewpoints to aid comparison. From review of this information, it
is considered that significant adverse effects would principally occur from views
close to the wind farm within the Deskford valley (including from the B9018)
(Viewpoints 1 and 2) and from Knock Hill (Viewpoint 3), with reduced effects for
views further from the proposal.  
8.7.12 For these closer views the LVA predicts that the increased scale of the
proposed development would be discernible in comparison with the scale of the
consented development, however the proposal is more compact and with
removal of two consented development turbines it would have a reduced
Page 229

Page 230

horizontal extent. When balancing these differences brought about by the
proposed development, the LVA considers that the change experienced in
these views would only slightly increase compared to that experienced for the
consented development, and that the magnitude of change of the proposed
development against the implications of the design change is considered to be
negligible or low. 
8.7.13 Effects on residential properties
The Residential Visual Amenity Assessment (RVAA) considers the visual
impact of the proposed development on private views and private visual
amenity from 30 residential properties within a 2km radius of the site. This has
been prepared in accordance with the Landscape Institute’s Technical
Guidance Note 2/19 ‘Residential Visual Amenity Assessment’ (RVAA), the
purpose of the RVAA being to identify those properties where the effect of the
proposed development leads to the ‘Residential Visual Amenity Threshold’
being reached or, in other words, where the effect could be described as
overwhelming or overbearing. 
8.7.14 The submitted Residential Visual Amenity Assessment (RVAA) concludes that
visual amenity from 14 properties would be significantly affected but that none
of these would reach the Residential Visual Amenity Threshold such that the
development would become overwhelming or overbearing, due to factors such
as intervening distance and screening between the properties and proposed
wind turbines, and a combination of property setting, visual containment from
vegetation and buildings and orientation (views from main windows/property
frontages). This is a similar judgement to that reached for the consented
development, the findings of which have been verified following site visits.   
8.7.15 As noted from the RVAA, removal of the two northern-most turbines, and
particularly Turbine 5, would provide mitigation for a number of residential
properties. For these properties the RVAA predicts that there would be minor
beneficial effects due to the reduced horizontal extent of the development and
removal of the northern-most turbines. The increased size of the remaining
three turbines is likely to be more discernible where there are close and largely
unscreened views, in particular from properties 6 and 11, Clochmariech and
Langlanburn, which lie 1.1km and 1.4km to the east of the proposed
development. For these, the RVAA concludes that the proposed development
would not cause unacceptable overbearing effects however due to the relatively
narrow field of view of the proposed turbines affecting a small proportion of the
overall views from both properties and the development having a more compact
appearance with a reduced horizontal extent. In addition, in terms of
orientation, Clochmariech, located below the site has principle views to the
north with only limited oblique views of the development. Langlangurn,
occupying an elevated position facing east towards Lurg Hill on the west side of
the B9018 would have a view of the turbines, however this would not be to an
extent that there would be a significant detrimental overbearing impact. 
8.7.16 Cumulative landscape and visual effects
The LVA considers cumulative scenarios and combined effects of the proposal
with other operational and consented wind farms within 10km and 20km study
areas surrounding the site. Cumulative effects are predicted to range between
Minor and Negligible, the extent of which would be dependent upon the location
Page 230

Page 231

of the receptor. In relation to cumulative effects, the LVA notes that there will be
instances where differences in the turbine scale of the proposed development
would increase the contrast with the scale of other nearby existing turbines,
particularly Myreton and Netherton of Windyhills to the south, however these
will be limited and localised in extent. 
8.7.17 For the consented scenario, the majority of consented turbines are distant and
as such have little visual interaction with the proposed development that would
allow comparison of scale to be apparent. The proposed development and
consented Aultmore wind farm (of 13 turbines, 90/110m high to blade tip) to the
west occupy different parts of the wider skyline. The proposed development,
whilst within the same wider visual context as Aultmore would not often be
experienced directly in front of or adjacent to it and differences in scale with this
consented scheme would not therefore be as apparent as with closer existing
turbines. 
8.7.18 As noted from the planning history for the area, a revised Aultmore wind farm
proposal is currently at scoping stage and should this come forward as an
application is likely to comprise substantially larger turbines up to 200m to
blade tip. Significant combined cumulative effects over and above those
predicted for the Lurg Hill proposal with the consented Aultmore wind farm
could occur on landscape character and on views from the B9018, the Bin of
Cullen and The Knock and from surrounding settlement where the two
developments would be seen together and sequentially. Notwithstanding this,
as the proposal is not at application stage it carries less weight than the
consented Aultmore wind farm development and has not been appraised in the
LVA.   
8.7.19 Conclusions on LVA
The proposed development would introduce changes to the proportions of the
turbines and a reduction in turbine numbers when compared with the
consented development at this site. While significant adverse effects on
landscape character and views would be associated with this proposal, these
effects require to be considered within the context of the existing consent of a
wind farm on this site. 
8.7.20 The omission of the two northern-most turbines would provide mitigation of
visual effects in close views from residential properties and from the Cullen
House Inventory listed designed landscape (should existing forestry be felled
on Clune Hill). The changes made to the size of the turbines (a difference of
just under 20m) would not be readily appreciable in the majority of views from
the wider area. With this mitigation and when compared to the consented
scheme, for landscape and visual effects, the proposal is considered to be an
acceptable departure from Policies DP1 and DP9, subject to Turbines 4 and 5
of 17/01198/EIA and 22/00339/APP not being constructed alongside the
proposal. 
8.8 Residential Amenity (noise and shadow flicker) (DP1, DP9 and EP14)
Policy DP1 Development Principles seek to ensure that new developments do
not create pollution which may adversely affect the environment or local
amenity. Policy DP9 Renewable Energy requires proposals to address
unacceptable significant adverse effects on communities and local amenity
Page 231

Page 232

including impacts on noise and shadow flicker and the potential for associated
mitigation. Policy EP14 Pollution, Contamination and Hazards sets out that
development proposals which may cause significant air, water, soil, light or
noise pollution should be accompanied by a detailed assessment report on the
levels, character and transmission of the potential pollution, with measures to
mitigate impact. 
8.8.1 Chapter 10 of the EA addresses these effects. A revised noise assessment and
updated shadow flicker modelling undertaken in accordance with relevant
guidance have been submitted with the application. 
8.8.2 Noise: The noise assessment has been undertaken based on the proposed
wind turbine locations and a candidate wind turbine model accounting for the
proposed increase in tip height. This predicts that noise levels from the
operation of the proposed development at the closest properties would neither
exceed relevant limits nor those set by the consented development. The
assessment also shows that cumulative noise levels, due to the operation of
the proposed Development and the closest cumulative developments within
5km, would not exceed the noise limits for the closest properties. For noise
associated with the construction phase (including decommissioning phase), the
noise assessment for the consented development concluded that the
separation distance between the construction areas and access routes and the
closest receptors was sufficient to ensure that construction-related noise effects
would not cause undue disturbance. As the proposed development comprises
no changes to the location of the turbines or infrastructure, the conclusions of
the construction noise assessment remain unchanged. The anticipated noise
effects of the proposed development therefore remain unchanged from the
consented development. 
8.8.3 The Council’s Environmental Health Section has reviewed and is content with
the findings of this assessment, and has raised no objection subject to
conditions enabling the monitoring and enforcement of noise limits at various
properties, submission/approval of full details of the final make/model of the
turbine, controls on construction times, no permitted blasting or borrow pits and
controls on Amplitude Modulation noise. 
8.8.4 Shadow Flicker:  The updated shadow flicker modelling undertaken for the
proposal assess effects from the three turbines on surrounding properties.
Seven residential properties are located within 10 rotor diameters of the
proposed turbines, three of which have been identified as experiencing greater
than 30 hours of shadow flicker per year from turbine 1. UK Government
guidelines note that a limit of up of 30 hours per year or 30 minutes on the
worst affected day is considered acceptable. The applicant proposes to install a
shadow flicker impact control unit/module to turbine 1 to mitigate potential
unacceptable impacts from shadow flicker to residential properties, similar to
mitigation proposed for the consented Development. 
8.8.5 The Environmental Health Section has reviewed and is content with this
information, and has raised no objection subject to imposition of a condition
requiring installation of a shadow flicker control module to turbine 1, and
measures to address any complaints received regarding shadow flicker. 
Page 232

Page 233

8.8.6 From the above and subject to the recommended conditions, the proposal is
not considered to result in unacceptable significant adverse effects on noise or
shadow flicker, including effects on the amenity of any nearby sensitive
receptors and would accord with the amenity requirements of policies DP1,
DP9 and EP14. 
8.9 Natural Heritage (Ecology and Ornithology) and Biodiversity (EP1, EP2
and DP9) 
Policy EP1: Natural Heritage Designations sets out that development likely to
have a significant effect on European Site Designations, National Designations
or Local Designations will not be permitted subject to criteria set out within the
policy. Where development is likely to affect protected species, a species
survey and where necessary a Species Protection Plan should be prepared to
accompany any planning application. Policy EP2: Biodiversity sets out that all
development proposals must, where possible, retain, protect and enhance
features of biological interest and provide for their appropriate management.
Policy DP9 Renewable Energy requires proposals to avoid or address
significant adverse impacts on ecology. 
8.9.1 There are no statutory or non-statutory nature conservation designations within
the application site. Designated sites within the wider area include Reidside
Moss Special Area of Conservation (SAC) and SSSI, designated for its active
raised bog priority feature which lies approx. 9.25km to the east southeast;
Sheilwood Pastures SSSI located approx. 5.59 km to the southeast designated
for its biological features; and the Moray Firth Special Protection Area (SPA)
which supports identified non-breeding and migratory bird species of European
importance 7.4km to the north.   
8.9.2 Chapter 6 and 7 of the EA evaluates the effects of the proposed development
on ecological and ornithology interests on the site, and has been supported by
an ecological desk study and two Technical Appendices: 6-1 Extended Phase 1
Habitat Survey and Bat Habitat Assessment, and 7-1 Ornithological Surveys. 
These predict no significant effects or adverse impacts, including cumulative
effects subject to mitigation measures identified within the EA being
implemented. 
8.9.3 The extended Phase 1 Habitat survey found the site to support habitats typical
of those within conifer plantation sites within the surrounding area and Scotland
in general. The identified habitats comprised predominantly coniferous
plantation, improved grassland, amenity grassland and semi-natural coniferous
woodland. 
8.9.4 The Habitat survey included a daylight bat feature assessment to identify
potential or confirmed roost sites, along with six months of vantage point
surveys, and a raptor survey. During the survey visible signs of badger and
pine martin, and bat flights were noted, but no setts, dens or bat roosts were
recorded (similar to the findings for the consented development). 
8.9.5 The recorded level of ornithological activity for the proposed development was
observed to be very similar to that for the consented development, with no
evidence of breeding within the site. Species were typical of that found within a
Page 233

Page 234

commercial forestry plantation and none were recorded in such numbers at
heights and location to be considered at collision risk. 
8.9.6 The EA also sets out that the proposal would have no adverse effects on the
Moray Firth Special Area of Protection (SPA) due to the separation distance
with the proposed development site and fact that no qualifying species of the
SPA were observed on site. 
8.9.7 The applicant proposes a range of mitigation measures and adherence to good
practice measures during construction and operation to minimise ecological
impacts from the proposal during construction and operation. These include the
provision of; a Construction Environmental Management Plan (CEMP), with the
full scope to be agreed with Moray Council in consultation NatureScot and
SEPA, prior to development commencing; Construction Method Statement;
appointment of an Ecological Clerk of Works to oversee works, monitor
ecological constraints and audit appointed contractor’s environmental
performance, delivery of toolbox talks and supervision of construction work;
adoption of 'best practice' to reduce/prevent pollution of watercourses and
incidents; pre-construction species and bird surveys, with results informing
whether the CEMP will include further mitigation with regard to protected
species and consultation with NatureScot; re-instatement of habitats to areas
subject to disturbance, such as the temporary construction compound area;
and establishment of a Habitat Management Plan (HMP). 
8.9.8 NatureScot has been consulted and has advised that there are no impacts on
designated sites or issues that would raise concerns of national interest. It is
also content with the ecology and ornithology chapters within the EA, which set
out appropriate mitigation to minimise the risk to ecological interests during the
construction and operation of the wind farm. 
8.9.9 From the above considerations and subject to conditions where recommended,
the proposal is not considered to result in unacceptable significant adverse
effects on nature conservation (ecological and ornithological) interests), and
would accord with development plan policies EP1, EP2 and DP9. 
8.10 Impact on Woodland 
(EP7 Forestry Woodlands and Trees and Scottish Government Control of
Woodland Removal Policy, and DP9)
Policy EP7 Forestry Woodlands and Trees states that proposals that must
retain healthy trees and incorporate them within the proposal unless it is
technically unfeasible to retain them. Policy DP9 Renewable Energy requires
proposals to avoid or adequately resolve impacts on forest and woodlands. 
8.10.1 The proposed development site lies within a managed coniferous woodland
plantation and will result in felling associated with the construction and
operation of the wind farm; some woodland felling has already occurred in
accordance with the existing consent for the site and an updated Forestry
Statement, including felling and replanting plans, has been provided with the
application. This incorporates amendments to the forestry plans as a result of
the changes of the layout for a reduced number of turbines, and proposes a
reduction of woodland loss requiring off-site compensatory planting of 9.3 ha
(previously 12.86 for the consented scheme). 
Page 234

Page 235

8.10.2 Scottish Forestry (SF) has assessed and is content with this information, and
raises no objection to the proposal subject to a condition requiring delivery of
compensatory planting through an approved management plan agreed with SF
and the Council prior to commencement of development or felling. Subject to
this condition being imposed the proposal complies with Policy EP7 and DP9. 
8.11 Hydrology, Hydrogeology and Geology 
(PP3, DP1, EP12, EP13, EP14, EP16 and DP9)
Policies PP3 Instructure and Services and DP1 Development Principles (iii)
Water Environment, Pollution, Contamination require development to be
planned and coordinated with infrastructure to ensure places function properly,
and proposals are adequately served by infrastructure and services in terms of
foul and surface water drainage and water supply. Policy EP12 Management
and Enhancement of the Water Environment requires surface water from
development to be dealt with in a sustainable manner (SuDS) that has a neutral
effect on the risk of flooding or which reduces the risk of flooding. Policy EP13
Foul Drainage requires developments to connect to the public sewage system
whenever possible. Policy EP14 Pollution Contamination Hazards outlines
requirements for managing pollution and contamination within development
proposals. Policy E16 Geodiversity and soil resources states that developments
should minimise disturbance to peat and other carbon rich soils and undertake
an assessment of any potential effects. A peat depth survey must be
undertaken which demonstrates areas of deep peat have been avoided. Policy
DP9 Renewable Energy requires proposals to avoid adverse or address
unacceptable significant adverse impacts on the water environment and carbon
rich soils and peat land hydrology. 
8.11.1 Chapter 8 of the EA addresses the potential effects of the proposed
development on the hydrology, hydrogeology and geology. Given the minor
changes to the layout and reduction in infrastructure, this assessment of effects
has involved a review of the Hydrology, Hydrogeology and Geology information
submitted with the Planning Application 17/01198/EIA, any new
guidance/information, and also takes account of additional mitigations required
by planning conditions of the consented development. The EA concludes that
potential effects on the water environment from the proposed development
remain unchanged from those of the consented development and that impacts
will be negligible or minor, due to environmental measures embedded in the
design, and mitigation measures to be adopted during construction and
construction best practice (outlined below). 
8.11.2 The proposed development occupies an elevated commercial forested area
and is not at risk from fluvial flooding. There is some risk of localised pluvial
(surface water flooding) along the main watercourses including the Hoggie Burn
and in small scattered areas. Apart from watercourse crossings these do not
intersect with proposed infrastructure. 
8.11.3 Generally, any potential effects from the proposed development are expected
to occur during the construction phase, at areas where infrastructure is
proposed, with more limited effects during the operational and
decommissioning phases. These include impacts on surface water run-off
characteristics and water quality, soil erosion, accidental spillages/concrete
Page 235

Page 236

pollution/sedimentation entering ground water and surface water environments,
effects on private water supplies and abstractions, increased flood risk, and
damage to peat or GWDTE's. Where possible, these have been mitigated by
environmental measures incorporated within the design of the scheme itself,
and where initial impacts are not alleviated, through additional proposed
mitigation measures. These measures are summarised as follows:
   The consented Development layout went through a series of changes to
minimise disturbance of peat; removal of turbine 4 will mean that no
disturbance of peat and therefore all peat is now avoided;   
   Use of existing tracks as much as possible, with new track layout
designed to minimise length. Further minimisation has been achieved by
reducing tack and removing turbines 4 and 5; 
   Provision of 50 m buffer zones around all watercourses except where
there are watercourse crossings; 
   Implementation of a Drainage Management Plan to include for turbine,
track, hard standing and cable laying works and operation; 
   New ditch design, track cross drainage, silt traps, dams etc. to be in
accordance with guidelines as in the consented development; 
   All watercourse crossings will accommodate 1:200 year flows with climate
change allowance and in accordance with good practice; 
   Private Water Supply monitoring arrangements; 
   Appointment of an Environmental Clerk of Works (EnvCoW) during
construction; 
   Development/implementation of a Construction Environmental
Management Plan (CEMP) and specific Construction Method Statements
(CMS) to focus on good practice mitigation measures and identify
measures to prevent or minimise effects on the environment including
pollution prevention and environmental monitoring arrangements. 
8.11.4 The Private Water Supply Assessment undertaken for the consented
development has been reviewed as part of the current proposal. This has
identified over 30 potential private water supplies (PWS) within 2km of the
proposed development, however only one, located at Mid Skeith, is within the
proposed development site. This is not on a public register but its zone of
contribution may be within an area potentially impacted by construction and
operation of access tracks. To address any potential adverse impacts from
construction the EA proposes mitigation measures and a monitoring
programme of this source to detect any changes to water quality and allow
further mitigation to be put in place if necessary (along the same lines as the
previous consented development). 
8.11.5 Several potential Ground Water Dependent Terrestrial Ecosystem communities
(GWDTE) (M23 rush pasture, M6 flush and M15 wet heath) were identified on
and adjacent to the site in small clearings in the plantation and on forest rides.
Following a hydrogeological risk assessment these were classified however as
habitats with low groundwater dependency and largely surface water fed, and
not true GWDTEs. 
8.11.6 A peat depth survey was carried out as part of the original work for the
consented development in 2017. This revealed several small areas of localised
Page 236

Page 237

peat within the site boundary, but none that are likely to be disturbed by
construction or operation of infrastructure.   
8.11.7 In terms of flood risk the EA concludes that the proposed development would
not result in increased flood risk both on and off the site, due to its location
outwith any fluvial flood risk area, site characteristics and proposed on site
drainage arrangements. 
8.11.8 From consultation, SEPA has not objected to the development in terms of its
key interests (which include ground water abstractions, peat management,
engineering activities in the water environment, pollution prevention and
environmental management, borrow pits and GWDTE). As that there are no
changes to the footprint or location of the infrastructure of the consented
development SEPA has requested that the same, or similarly worded
conditions be attached to any consent for the current application, with the
exception of updated condition wording to ensure that detailed peat probing
results in the vicinity of turbine 1 is supplied with the CEMP to show that deep
peat will be avoided. These shall be re-imposed as recommended.   
8.11.9 Scottish Water has raised no objection to the proposal and has advised that
although the proposed activity and site boundary falls within a drinking water
catchment where a Scottish Water abstraction is located, the activity is a
sufficient distance from the intake and that it is likely to be low risk. It confirms
that water quality protection measures should be implemented to ensure that
water quality and water quantity in the area are protected, and in the event of
an incident occurring that could affect Scottish Water it be notified immediately.
It also highlights that the fact that this area is located within a drinking water
catchment should be noted in documentation, contractors working on site
should be made aware of this during site inductions and that Scottish Water is
notified 3 months prior to works commencing to make its operational teams
aware there will be activity taking place in the catchment. 
8.11.10 The Council’s Contaminated Land, following consultation, has raised no
objection to the proposal. 
8.11.11 The Flood Risk Management Section has raised no objection in terms of
flooding and drainage impacts, subject to conditions requiring
submission/approval of a detailed drainage design and SUDs measures; a
construction surface water management to include a map of all watercourses,
mitigation proposals and justification of appropriateness, map of mitigation
locations and emergency and spill procedures; drainage management plans to
address surface water and foul drainage; and details of stream crossings and
all water course engineering designed to accommodate the 1 in 200 year flows
(including a 35% allowance for climate change). 
8.11.12 The Private Water Section has raised no objection, subject to a condition
requiring submission/approval of details of arrangements to monitor private
water supplies during all stages of the development, and in the event of any
adverse effects on water quality or quantity being identified, the arrangements
and procedures to undertake restorative and remedial works to maintain any
supply. This shall include measures to monitor the supply known as 'Mid Skeith'
Page 237

Page 238

to detect any changes to water quality and allow for further mitigation measures
to be put in place if necessary. 
8.11.13 Drawing from the above and subject to the recommended conditions, the
proposal is not considered to result in unacceptable significant adverse effects
on hydrology, hydrogeology and geological (drainage, flooding, pollution
prevention, contamination and peat) interests and would accord with
development plan policies PP3, DP1, EP12, EP13, EP14, EP16 and DP9. 
8.12 Cultural Heritage (EP8, EP10 and EP11) 
Policy EP8 Historic Environment seeks to protect historic and archaeological
assets. Policies EP10 Listed Buildings and EP11 Battlefields, Gardens and
Designed Landscapes states that development proposals will be refused where
they would have a detrimental effect on the character, integrity or setting of
listed buildings and Garden and Designed Landscapes. Policy DP9 Renewable
Energy requires proposals to avoid or adequately resolve impacts on the
historic environment and cultural heritage. 
8.12.1 Chapter 9 of the EA assesses the potential for direct physical effects upon
archaeological remains as well as the potential for operational and cumulative
setting effects upon designated heritage assets. The methodology for the
assessment follows best practice guidelines/guidance, including HES’s
Managing Change in the Historic Environment: Setting (Historic Environment
Scotland (HES 2020) based on three study areas (1km, 5km and 10km), and
includes a Zone of Theoretical Visibility Map, viewpoint visualisations and
analysis of effects on a number of identified assets. The assessment predicts
no significant adverse impacts on the historic environment and confirms that no
mitigation is required. 
8.12.2 One non-designated asset, a modern metal water tank, has been identified
within the site which could potentially be affected by the construction of the
proposed development due to micro siting. This is considered to be of
negligible importance however as it is a common feature with local interest
only. The potential for further, as yet unknown heritage assets for the
consented development was considered low, due to the proposed development
site having been heavily disturbed by ploughing and afforestation. This
assessment is unchanged and as such recommends no mitigation. 
8.12.3 In terms of the wider area, potential effects on the settings of designated
heritage assets within the 5km and 10km study areas have been considered.
This includes eight Scheduled Monuments, 21 Listed Buildings, the Cullen
House Inventory listed designed landscape, and Berryhillock Conservation
Area within the 5km study area lying within the ZTV. Detailed assessments of
these assets were carried out for the consented development where it was
found that there would be no significant indirect effects on their setting. The
anticipated effects on these interests remain unchanged from those predicted
for the consented development. 
8.12.4 The EA includes a further assessment of potential effects on the Regionally
Significant forts on Durn Hill (Asset 78, approx. 8.3km to the northeast of the
development), the Bin of Cullen (Asset 123, approx. 6.4km the north northwest)
and St John’s Church and Tower of Deskford (Asset 21 and 66) (Category A
Page 238

Page 239

listed and a scheduled monument) which lie approx. 3.3km to the north. This
shows that although the proposal will be visible in some views from these
assets, their key archaeological, historic or architectural interests would not be
impacted upon negatively due to intervening screening and woodland cover,
topography, and for the fort sites, distance from the turbines and expansive
panoramic views available from the sites and their landscape setting. 
8.12.5 Following consultation, Historic Environment Scotland (HES) has raised no
concerns regarding the proposed development. 
8.12.6 The Council's Archaeological Advisor following consultation has raised no
objection to the proposal. 
8.12.7 From the above observations the proposal would not have unacceptable
significant adverse effects on cultural heritage interests and complies with
development plan policies EP8, EP10, EP11 and DP9. 
8.13 Traffic and Transport (PP3, DP1 and DP9)
Policy PP3 Infrastructure and Services seeks to ensure development is planned
and co-ordinated with infrastructure to enable places to function properly and
are adequately serviced. Part (a) (iii) requires, where appropriate, proposed
developments to mitigate/modify the existing transport network to address the
impact of the proposed development in terms of safety and efficiency. Policy
DP1 Development Principles (ii) sets out transportation requirements including
provision of safe entry and exit from development, safe access to and from the
road network and mitigation of road safety impacts. Policy DP9 Renewable
Energy requires proposals to avoid or address unacceptable traffic impacts
during construction and operation. 
8.13.1 Chapter 9 of the EA considers potential traffic and transport impacts associated
with the construction and operation of the proposed development on the
surrounding public road network and on sensitive receptors. Assessment
methodology has entailed scoping of routes and traffic, traffic counter data
gathering, and the carrying out of an Abnormal Loads Assessment and analysis
of the likely effects, along with mitigation measures to minimise any effects. The
assessment predicts no significant or adverse effects on the road network, and
recommends mitigation measures to reduce the potential for effects as far as
practicable. 
8.13.2 As previously identified, the development site will be accessed from the north
via an existing access track which is to be modified for the proposed
development. Other offsite road modifications (passing places etc.) to be
agreed in consultation with relevant Roads Authorities are likely to required. 
8.13.3 Most traffic effects would occur during the construction phase programme
which is anticipated to last approximately 6 months, with substantially reduced
levels during subsequent commissioning and operational/maintenance phases.
Traffic effects during decommissioning are also predicted to be significantly
less than that generated for construction. 
8.13.4 For the construction phase, road stone for the access tracks and
hardstandings, and concrete required for construction would be sourced from
Page 239

Page 240

the Blackhillock Quarry, located approx. 29km to the south via the A96, A95,
A9022 and C5L roads. General construction traffic (staff LGVs and cars) is
anticipated to come from Keith, via the A95, A9022 and C5L roads. Based upon
the submitted Abnormal Indivisible Load (AIL) Access Study, the delivery route
for the turbine components would be from the Port of Inverness - A9-A96-A97-
Aberchirder bypass access road, A9022 and C5L roads. 
8.13.5 According to the EA, deliveries of road stone will take place during the first 3
months, the highest number being in month 3 with an average of 56 two-way
HGV trips daily. For concrete deliveries, the highest numbers would be made
during months 3, 4 and 5 (average 12 two-way daily movements), whilst for
delivery of turbines, this would occur during months 4 and 5 (average 30
convoys per month). The EA predicts the increase in HGV traffic on the C5L
and A9022 roads (58% and 41% respectively) which is expected given the low
baseline levels of HGVs along these rural roads. It also notes that the increase
in total traffic levels will be within accepted limits (set out within guidance for
assessment of environmental effects of traffic (Institute for Environmental
Management and Assessment (1993) ‘IEMA Guidelines’), and as all impacts
are on a temporary basis, and considerably lower during the other four months
of the construction stage, the impact on the C5L and B9022 is considered to be
minor. 
8.13.6 With no significant traffic effects predicted to occur, the EA concludes that no
mitigation is required but, as an enhanced measure, a Construction Traffic
Management Plan (CTMP) will be prepared. 
8.13.7 Following consultation, Transport Scotland has raised no objection to the
development subject to conditions to address impacts on the trunk road
network; these include requiring submission/approval of the routing of any
abnormal loads on the trunk road network, accommodation measures and
traffic management; additional signing or temporary traffic control measures;
proposals for an abnormal loads delivery trail-run with involvement of Police
Scotland; a Construction Traffic Management Plan (CTMP); all vehicles
transporting construction material to and from the proposed development to be
sheeted; installation of vehicle wheel cleansing facilities; and decommissioning
plan. 
8.13.8 Similarly, the Council's Transportation Manager has raised no objection to the
development subject to conditions to address impacts on the local road network
requiring detailed proposals of abnormal load trial run(s) to be undertaken prior
to construction and deliveries to determine additional accommodation works,
restrictions and frequency; a Construction Traffic Management Plan; details of
upgrading works of the C4L Bogmuchals - Berryhillock Road/site access
junction including access width, radii, kerbing, visibility splay and drainage;
detailed drawings/construction of 3 passing places on the C4L road; road
widening/alterations/verge hardening to be permanent for duration of
development; evidence of a signed S96 'Wear and Tear' agreement including a
'before and after' condition video surveys required for delivery and construction
traffic routes; etc. 
8.13.9 Drawing from the above and subject to conditions requested by consultees, the
proposal is not considered to have unacceptable significant adverse effects on
Page 240

Page 241

traffic and transport matters, and would accord with policies PP3, DP1 and
DP9. 
8.14 Aviation Issues (EP15 and DP9) 
Policy EP15 MoD Safeguarding states that development proposals must not
adversely impact upon MoD operations and requires consultation with the
Defence Infrastructure Organisation on any proposals within safeguarding
consultation zones. Policy DP9 seeks to ensure that renewable energy
proposals avoid any impacts resulting from aviation and defence constraints
including flight paths and aircraft radar. 
8.14.1 Chapter 13 of the EA considers effects of the proposed development on civilian
and military aircraft activity, including air safeguarding and radar interests. The
assessment predicts that effects to Ministry of Defence (MOD) radar systems at
RAF Lossiemouth are likely to occur which will require mitigation. No other
impacts on civilian aviation interests are anticipated. 
8.14.2 In terms of civil aviation interests, National Air Traffic Systems and Aberdeen
Airport have not objected to the proposal as having unacceptable or significant
adverse effects on aircraft activity. 
8.14.3 For military aviation, the EIA for the consented development identified potential
effects on the MoD radar at RAF Lossiemouth, and a technical solution to these
was agreed with the MoD subsequent to the submission of the planning
application and confirmed in the Appeal Decision for the consented
development (PPA-300-2052). The solution to potential radar interference at
RAF Lossiemouth by the proposed development remains the same, as agreed
with MoD. As per the conditions of the consented development an Air Traffic
Control Radar Mitigation Scheme will set out the appropriate measures to be
implemented to mitigate the impact on the radar. 
8.14.4 The MoD, following consultation, has raised no objection to the current
proposal subject to conditions requiring submission/approval of the Air Traffic
Control Radar Mitigation Scheme, an aviation lighting scheme covering
construction and a scheme for aviation charting and safety management
confirming date of commencement of works, maximum height of construction
equipment, date wind turbines are brought into use and final coordinates and
maximum heights of wind turbines and any anemometer mast(s). 
8.14.5 From the above and subject to the conditions, the proposal is not considered to
result in unacceptable significant adverse effects on military and civilian
aviation and would accord with policies DP9 and EP15. 
8.15 Telecommunications and Electromagnetic Interference (DP9) 
Policy DP9 seeks to ensure that renewable energy proposals avoid any
unacceptable significant adverse impacts including electromagnetic
interference. 
8.15.1 Chapter 13 of the EA considers the potential impacts of the development upon
fixed communication links in the vicinity of the site. This predicts no likely
effects upon telecommunications during construction or operation, as
concluded previously for the consented development. It also commits to
Page 241

Page 242

providing mitigation should interference with fixed link frequency band signals
be identified as a result of the proposed development, and if required, to make
good the fixed link frequency band signals, either by eliminating the cause of
the interference or by providing an alternative means by which fixed link
frequency band signals may be received. 
8.15.2 The turbines are located outwith the zone of influence for known
communication links and therefore no impacts are predicted or require
mitigation. 
8.15.3 Following consultation fixed link network operators have not objected to the
development. 
8.15.4 As a precaution, and as adopted for the consented development, in the event of
any complaint(s) being received regarding interference to television signals or
other telecommunication fixed link systems, a condition shall be imposed
requiring the applicant/wind turbine operator to investigate and rectify any
adverse effects. 
8.15.5 Subject to the condition, the proposal is not considered to result in
unacceptable significant adverse effects upon telecommunications
infrastructure and assets and electromagnetic interference, and would accord
with policy DP9. 
8.16 Socio-economic, Recreation and Tourism Interests (DP9 and PP3)
Policy DP9 seeks to ensure that renewable energy proposals avoid any
unacceptable significant adverse impacts on tourism or recreational interests.
Policy PP3 Infrastructure and Services part (b) states that development
proposals will not be supported where they adversely impact on access routes
and cannot be adequately mitigated by an equivalent or better alternative
provision in a location convenient for users. 
8.16.1 Chapter 12 of the EA assesses the potential impacts of the proposed
development upon socio-economic, tourism and recreation interests. This
predicts that similar effects would occur to those from the consented
development, and these are considered to be negligible to slight beneficial and
will typically be localised in nature. 
8.16.2 Socio-economic Interests 
The EA identifies a positive benefit arising in terms of expenditure and local
employment. The proposed development is estimated to make a contribution to
the local economy and generate a UK turnover of £10 million during the
construction stage, with around £7.7 million in Scottish turnover anticipated,
and circa 80 jobs during construction and through its operational life. The EA
considers the construction effects to be positive, but short-term and localised,
and that potential effects are be unchanged from the conclusion of the
consented development 2017 Environmental Statement, and assessed to be
negligible. 
8.16.3 The EA confirms that in accordance with the Scottish Government's Good
Practice Principles for Community Benefits document (published May 2019),
the applicant will provide community funding in line with SG recommended
Page 242

Page 243

levels (£5,000 per installed megawatt of generating capacity equating to
£75,000 per). The setting up of a Community Benefit Fund is not a matter that
should influence the planning decision and would be arranged separate to the
planning process. 
8.16.4 Recreational and Tourism Interests 
As the site is not currently used for formal outdoor access purposes the
proposal would have a minimal effect on public access during the construction
period with any impact being temporary during the construction phase. By
improving access to the site and the surrounding area with access tracks being
formed and upgraded, potential effects are therefore considered to be
unchanged from the conclusion of the consented development 2017
Environmental Statement and are assessed to be slight beneficial. 
8.16.5 The proximity of the proposed development to Knock Hill (3.62km to the
southeast) would give rise to some adverse effects upon its setting and views
from its summit. As the hill is popular with walkers this effect could potentially
detract from the recreational value of the path, although it is acknowledged that
perceptions towards turbines differ between individuals. It is considered that the
change in this view however would only slightly increase in comparison to that
experienced for the consented development, and would be acceptable. 
8.16.6 Following consultation, the Moray Access Manager has not objected to the
proposal. 
8.16.7 From the above, the proposal is considered to accord with policies DP9 and
PP3 in terms of socio-economic, Recreation and Tourism Interests. 
8.17 Arrangements for decommissioning and site restoration (DP9) 
Policy DP9 seeks to ensure that renewable energy proposals address
appropriate provision for decommissioning and site restoration. 
8.17.1 Permission is sought for a 35 year period and if permitted recommended
conditions will require appropriate mitigation of the site. The EA outlines
information in relation to decommissioning and site reinstatement, which would
entail preparation of a restoration scheme prior to decommissioning (or
submission of a new application to extend the lifetime of the wind farm). A
condition is recommended which seeks a bond or other form of financial
guarantee to ensure sufficient funds are available to cover all costs of site
decommissioning and re-instatement, the latter to be reviewed at regular
intervals during the lifetime of the development to ensure it remains sufficient to
meet the costs of decommissioning. 
8.17.2 Based on the above and subject to the condition the proposal is considered to
comply with the decommissioning and restoration requirements of Policy DP9. 
8.18 Developer Obligations (PP3) 
No planning obligations contributions are due as such development would not
have any impact on community facilities, schools etc. Separate to this it was
decided by the Planning and Regulatory Services Committee on 18 October
2012 to remove the pursuit or contribution of funds to "Community Benefit
Funds" from the development management system.
Page 243

Page 244

Conclusion
This proposal represents an acceptable renewable energy development
proposal for Moray. The scheme accords with aspects of local and national
planning policy regarding the expansion of renewable energy, including its
contribution to renewable energy targets. 
The proposed development would introduce changes to the height and blade
dimensions of the turbines and a reduction in turbine numbers from five to three
when compared with the consented development at this site. While significant
adverse effects on landscape character and views would be associated with
this proposal, these effects require to be considered within the context of the
existing consent of a wind farm on this site, which carries significant weight as a
material consideration. 
The omission of the two northern-most turbines would provide mitigation of
visual effects in close views from residential properties and from the Cullen
House Inventory listed designed landscape (should existing forestry be felled
on Clune Hill). The changes made to the size of the turbines (a difference of
just under 20m) would not be readily appreciable in the majority of views from
the wider area. With this mitigation and when compared to the consented
scheme, for landscape and visual effects, the proposal is considered to be an
acceptable departure from Policies DP1 and DP9, subject to Turbines 4 and 5
of 17/01198/EIA and 22/00339/APP not being constructed alongside the
proposal. 
Following detailed assessment and subject to conditions to avoid or mitigate
any significant impacts, the proposal would be satisfy all other policy
requirements set out in the Moray Local Development Plan 2020, relating to the
natural and built environment, residential amenity, cultural heritage, woodland
removal, the water environment, transport, noise, aviation, telecommunications,
socio-economic, recreational and tourism interests. 
Subject to the conditions recommended, approval should be granted. 
REASON(S) FOR DECISION
The Council’s reason(s) for making this decision are:- 
This proposal represents an acceptable renewable energy development
proposal for Moray. The scheme accords with local and national planning policy
regarding the expansion of renewable energy, including its contribution to
renewable energy targets. 
The proposed development would introduce changes to the proportions of the
turbines and a reduction in turbine numbers when compared with the
consented development at this site. While significant adverse effects on
landscape character and views would be associated with this proposal, these
effects require to be considered within the context of the existing consent of a
wind farm on this site, which carries significant weight as a material
consideration. 
Page 244

Page 245

The omission of the two northern-most turbines would provide mitigation of
visual effects in close views from residential properties and from the Cullen
House Inventory listed designed landscape (should existing forestry be felled
on Clune Hill). The changes made to the size of the turbines (a difference of
just under 20m) would not be readily appreciable in the majority of views from
the wider area. With this mitigation and when compared to the consented
scheme, for landscape and visual effects, the proposal is considered to be an
acceptable departure from Policies DP1 and DP9, subject to Turbines 4 and 5
of 17/01198/EIA and 22/00339/APP not being constructed alongside the
proposal. 
From detailed assessment and subject to conditions to avoid or mitigate any
significant impacts, the proposal satisfies all other policy requirements as set
out within the Moray Local Development Plan 2020, relating to the natural and
built environment, residential amenity, cultural heritage, woodland removal, the
water environment, transport, noise, aviation, telecommunications, socio-
economic, recreational and tourism interests. 
Author/Contact
Officer:
Richard Smith            
Principal Planning Officer
Ext: 01343 563256 
Beverly Smith
Development Management & Building Standards Manager
Page 245

Page 246

Page 246

Page 247

APPENDIX 
POLICY 
Moray Local Development Plan 2020 
PP2  SUSTAINABLE ECONOMIC GROWTH
Development proposals which support the Moray Economic Strategy to deliver
sustainable economic growth will be supported where the quality of the natural and built
environment is safeguarded, there is a clear locational need and all potential impacts can
be satisfactorily mitigated. 
PP3  INFRASTRUCTURE & SERVICES
Development must be planned and co-ordinated with infrastructure to ensure that places
function properly and proposals are adequately served by infrastructure and services.   
a) In relation to infrastructure and services developments will be required to provide the
following as may be considered appropriate by the planning authority, unless these
requirements are considered not to be necessary: 
i)  Education, Health, Transport, Sports and Recreation and Access facilities in
accord with Supplementary Guidance on Developer Obligations and Open
Space. 
ii)  Green infrastructure and network requirements specified in policy EP5 Open
Space, Town and Village Maps and, contained within Supplementary Guidance
on the Open Space Strategy, Masterplans and Development Briefs. 
iii)  Mitigation/modification to the existing transport network (including road and rail)
to address the impact of the proposed development in terms of safety and
efficiency.  This may include but not be limited to passing places, road
widening, junction enhancement, bus stop infrastructure, and drainage
infrastructure.  A number of potential road and transport improvements are
identified and shown on the Town and Village Maps as Transport Proposals
(TSP's) including the interventions in the Elgin Transport Strategy. These
requirements are not exhaustive and do not pre-empt any measures which may
result from the Transport Assessment process. 
iv)  Electric car charging points must be provided at all commercial and community
parking facilities.  Access to charging points must also be provided for
residential properties, where in-curtilage facilities cannot be provided to any
individual residential property then access to communal charging facilities
should be made available.  Access to other nearby charging facilities will be
taken into consideration when identifying the need for communal electric
charging points. 
v)  Active Travel and Core Path requirements specified in the Council's Active
Travel Strategy and Core Path Plan. 
vi)  Safe transport and access routes linking to existing networks and mitigating the
impacts of development off-site. 
Page 247

Page 248

vii)  Information Communication Technology (ICT) and fibre optic broadband
connections for all premises unless justification is provided to substantiate it is
technically unfeasible. 
viii)  Foul and surface water drainage, including Sustainable Urban Drainage
Systems (SUDS), including construction phase SUDS. 
ix)  Measures that implement the waste management hierarchy as defined in the
Zero Waste Plan for Scotland including the provision of local waste storage and
recycling facilities designed into the development in accord with policy PP1
Placemaking.  For major applications a site waste management plan may be
required to ensure that waste minimisation is achieved during the construction
phase. 
x)  Infrastructure required to improve or increase capacity at Water Treatment
Works and Waste Water Treatment Works will be supported subject to
compliance with policy DP1. 
xi) A utilities plan setting out how existing and new utility (including gas, water,
electricity pipelines and pylons) provision has been incorporated into the layout
and design of the proposal.  This requirement may be exempted in relation to
developments where the council considers it might not be appropriate, such as
domestic or very small scale built developments and some changes of use. 
b)  Development proposals will not be supported where they:
i)  Create new accesses onto trunk roads and other main/key routes (A941 & A98)
unless significant economic benefits are demonstrated or such access is
required to facilitate development that supports the provisions of the
development plan. 
ii)  Adversely impact on active travel routes, core paths, rights of way, long
distance and other access routes and cannot be adequately mitigated by an
equivalent or better alternative provision in a location convenient for users. 
iii)  Adversely impact on blue/green infrastructure, including green networks
important for wildlife unless an equivalent or better alternative provision will be
provided. 
iv)  Are incompatible with key waste sites at Dallachy, Gollanfield, Moycroft and
Waterford and would prejudice their operation. 
v)  Adversely impact on community and recreational sites, buildings or
infrastructure including CF designations and cannot be adequately mitigated. 
vi)  Adversely impact on flood alleviation and mitigation infrastructure. 
vii)  Compromise the economic viability of bus or rail facilities.   
c)  Harbours 
Development within and diversification of harbours to support their sustainable
operation will be supported subject to compliance with other policies and settlement
statements.
Page 248

Page 249

d)  Developer Obligations 
Developer obligations will be sought to mitigate any measurable adverse impact of a
development proposal on local infrastructure, including education, healthcare,
transport (including rail), sports and recreational facilities and access routes. 
Obligations will be sought to reduce, eliminate or compensate for this impact.
Developer obligations may also be sought to mitigate any adverse impacts of a
development, alone or cumulatively with other developments in the area, on the
natural environment. 
Where necessary obligations that can be secured satisfactorily by means of a
planning condition attached to planning permission will be done this way.  Where this
cannot be achieved, the required obligation will be secured through a planning
agreement in accordance with Circular 3/2012 on Planning Obligations.   
Developer obligations will be sought in accordance with the Council's Supplementary
Guidance on Developer Obligations.  This sets out the anticipated infrastructure
requirements, including methodology and rates.   
Where a developer considers that the application of developer obligations renders a
development commercially unviable a viability assessment and 'open-book
accounting' must be provided by the developer which Moray Council, via the District
Valuer, will verify, at the developer's expense.  Should this be deemed accurate then
the Council will enter into negotiation with the developer to determine a viable level
of developer obligations.   
The Council's Developer Obligations Supplementary Guidance provides further detail
to support this policy. 
DP1 DEVELOPMENT PRINCIPLES 
This policy applies to all development, including extensions and conversions and will be
applied reasonably taking into account the nature and scale of a proposal and individual
circumstances. 
The Council will require applicants to provide impact assessments in order to determine
the impact of a proposal. Applicants may be asked to determine the impacts upon the
environment, transport network, town centres, noise, air quality, landscape, trees, flood
risk, protected habitats and species, contaminated land, built heritage and archaeology
and provide mitigation to address these impacts. 
Development proposals will be supported if they conform to the relevant Local
Development Plan policies, proposals and additional guidance, meet the following criteria
and address their individual and cumulative impacts: 
(i) Design
a) The scale, density and character must be appropriate to the surrounding area
and create a sense of place (see Policy PP1) and support the principles of a
walkable neighbourhood. 
b) The development must be integrated into the surrounding landscape which will
include safeguarding existing trees and undertaking replacement planting to
Page 249

Page 250

include native trees for any existing trees that are felled, and safeguarding any
notable topographical features (e.g. distinctive knolls), stone walls and existing
water features by avoiding channel modifications and culverting. A tree survey
and tree protection plan must be provided with planning applications for all
proposals where mature trees are present on site or that may impact on trees
outwith the site. The strategy for new tree provision should follow the principles
of the "Right Tree in the Right Place". 
c) Make provision for new open space and connect to existing open space under
the requirements of Policy EP5 and provide details of the future maintenance of
these spaces. A detailed landscape plan must be submitted with planning
applications and include information about green/blue infrastructure, tree
species, planting, ground/soil conditions, and natural and man-made features
(e.g. grass areas, wildflower verges, fencing, walls, paths, etc.). 
d) Demonstrate how the development will conserve and enhance the natural and
built environment and cultural heritage resources, retain original land contours
and integrate into the landscape. 
e) Proposals must not adversely impact upon neighbouring properties in terms of
privacy, daylight or overbearing loss of amenity. 
f)  Proposals do not result in backland development or plots that are subdivided by
more than 50% of the original plot.  Sub-divided plots must be a minimum of
400m2, excluding access and the built-up area of the application site will not
exceed one-third of the total area of the plot and the resultant plot density and
layout reflects the character of the surrounding area. 
g)  Pitched roofs will be preferred to flat roofs and box dormers are not acceptable. 
h)  Existing stone walls on buildings and boundaries must be retained. 
Alterations and extensions must be compatible with the character of the
existing building in terms of design, form, choice of materials and positioning
and meet all other relevant criteria of this policy. 
i)  Proposals must orientate and design buildings to maximise opportunities for
solar gain. 
j)  All developments must be designed so as to ensure that all new buildings avoid
a specified and rising proportion of the projected greenhouse gas emissions
from their use (calculated on the basis of the approved design and plans for the
specific development) through the installation and operation of low and zero-
carbon generating technologies. 
(ii) Transportation
a) Proposals must provide safe entry and exit from the development, including the
appropriate number and type of junctions, maximise connections and routes for
pedestrians and cyclists, including links to active travel and core path routes,
reduce travel demands and ensure appropriate visibility for all road users at
junctions and bends. Road, cycling, footpath and public transport connections
and infrastructure must be provided at a level appropriate to the development
Page 250

Page 251

and connect people to education, employment, recreation, health, community
and retail facilities. 
b) Car parking must not dominate the street scene and must be provided to the
side or rear ¬and behind the building line. Maximum (50%) parking to the front
of buildings and on street may be permitted provided that the visual impact of
the parked cars is mitigated by hedging or low stone boundary walls. Roadways
with a single carriageway must provide sufficient off road parking to avoid
access routes being blocked to larger service vehicles and prevent parking on
pavements. 
c) Provide safe access to and from the road network, address any impacts on
road safety and the local road, rail and public transport network. Any impacts
identified through Transport Assessments/ Statements must be identified and
mitigated. This may include but would not be limited to, passing places, road
widening, junction improvements, bus stop infrastructure and drainage
infrastructure. A number of potential mitigation measures have been identified
in association with the development of sites and the most significant are shown
on the Proposals Map as TSP's. 
d) Provide covered and secure facilities for cycle parking at all flats/apartments,
retail, community, education, health and employment centres. 
e) Garages and parking provision must be designed to comply with Moray Council
parking specifications see Appendix 2. 
f)  The road layout must be designed to allow for the efficient mechanical
sweeping of all roadways and channels, paviors, turning areas and junctions.
The road layout must also be designed to enable safe working practices,
minimising reversing of service vehicles, with hammerheads minimised in
preference to turning areas such as road stubs or hatchets, and to provide
adequate space for the collection of waste and movement of waste collection
vehicles. 
g) The road and house layout in urban development should allow for communal
refuse collection points where the design does not allow for individual storage
within the curtilage and / or collections at kerbside. Communal collection points
may either be for the temporary storage of containers taken by the individual
householder or for the permanent storage of larger containers. The
requirements for a communal storage area are stated within the Council's
Kerbside Collection Policy, which will be a material consideration. 
h) Road signs should be minimised designed and placed at the back of footpaths
to reduce street clutter, avoid obstructing pedestrian movements and
safeguarding sightlines; 
i)  Within communal parking areas there will be a requirement for electric car
charging points. Parking spaces for car sharing must be provided where a need
is identified by the Transportation Manager. 
Page 251

Page 252

(iii) Water environment, pollution, contamination
a) Acceptable water and drainage provision must be made, including the use of
sustainable urban drainage systems (SUDS) for dealing with surface water
including temporary/ construction phase SUDS (see Policy EP12). 
b) New development should not be located in areas at flood risk or increase
vulnerability to flooding (see Policy EP12). Exceptions to this would only be
considered in specific circumstances, e.g. extension to an existing building or
change of use to an equal or less vulnerable use. Where this exception is
applied the proposed development must include resilience measures such as
raised floor levels and electrical sockets. 
c) Proposals must avoid major hazard sites and address any potential risk of
pollution including ground water contamination in accordance with recognised
pollution prevention and control measures. 
d) Proposals must protect and wherever practicable enhance water features
through for example naturalisation of watercourses by introducing a more
natural planform and removing redundant or unnecessary structures. 
e) Proposals must address and sufficiently mitigate any contaminated land issues. 
f)  Make acceptable arrangements for waste collection and management and
encourage recycling. 
g) Avoid sterilising significant workable reserves of minerals, prime agricultural
land or productive forestry. 
h)  Proposals must avoid areas at risk of coastal erosion and coastal change. 
DP9 RENEWABLE ENERGY 
a) All Renewable Energy Proposals 
All renewable energy proposals will be considered favourably where they meet the
following criteria: 
i) They are compliant with policies to safeguard and enhance the built and natural
environment; 
ii) They do not result in the permanent loss or permanent damage of prime
agricultural land; 
iii) They avoid or address any unacceptable significant adverse impacts including: 
• Landscape and visual impacts.
• Noise impacts.
• Air quality impacts.
• Electromagnetic disturbance.
• Impact on water environment.
• Impact on carbon rich soils and peat land hydrology.
• Impact on woodland and forestry interests.
• Traffic impact -mitigation during both construction and operation.
Page 252

Page 253

• Ecological Impact.
• Impact on tourism and recreational interests. 
In addition to the above criteria, detailed assessment of impact will include
consideration of the extent to which the proposal contributes to renewable energy
generation targets, its effect on greenhouse gas emissions and net economic impact,
including socio-economic benefits such as employment. 
b) Onshore wind turbines 
In addition to the assessment of the impacts outlined in part a) above, the following
considerations will apply: 
i) The Spatial Framework 
Areas of Significant Protection (Map 2): where the Council will apply significant
protection and proposals may be appropriate in circumstances where any
significant effects on the qualities of these areas can be substantially overcome
by siting, design and other mitigation. 
Areas with Potential (Map 1): where proposals are likely to be acceptable
subject to Detailed Consideration. 
ii) Detailed Consideration 
The proposal will be determined through site specific consideration of the
following on which further guidance will be set out in supplementary guidance
and as informed by the landscape capacity study: 
Landscape and visual impact:
• the landscape is capable of accommodating the development without
unacceptable significant adverse impact on landscape character or visual
amenity.
• the proposal is appropriate to the scale and character of its setting,
respects the main features of the site and the wider environment and
addresses the potential for mitigation. 
Cumulative impact
• unacceptable significant adverse impact from two or more wind energy
developments and the potential for mitigation is addressed. 
Impact on local communities
• the proposal addresses unacceptable significant adverse impact on
communities and local amenity including the impacts of noise, shadow
flicker, visual dominance and the potential for associated mitigation. 
Other
• the proposal addresses unacceptable significant adverse impacts arising
from the location within an area subject to potential aviation and defence
constraints including flight paths and aircraft radar.
• the proposal avoids or adequately resolves other impacts including on the
natural and historic environment, cultural heritage, biodiversity, forest and
woodlands and tourism and recreational interests - core paths, visitor
centres, tourist trails and key scenic routes.
Page 253

Page 254

• the proposal addresses any physical site constraints and appropriate
provision for decommissioning and restoration. 
iii) Extensions and Repowering of Existing Wind Farms 
The proposal will be determined through assessment of the details of the
proposal against Part a) and Parts b) (i) and (ii) above.  Detailed assessment of
impact will include consideration of the extent to which:
• the proposal, for extensions, impacts on the existing wind farm(s) setting
and the ability to sit in the landscape on its own should the existing wind
farm be decommissioned before the extension.
• the proposal, for repowering, makes use of existing infrastructure and
resources, where possible, and limits the need for additional footprint. 
c) Biomass 
Proposals for the development of commercial biomass will be supported if the
following criteria are met. 
• Applicants must confirm which form of biomass will fuel the plant and if a
mixture of biomass is proposed then what percentage split will be attributed to
each fuel source.
• Proposals must demonstrate that they have taken account of the amount of
supply fuel over the life of the project.
• When considering wood biomass proposals, the scale and location of new
development is appropriate to the volume of local woodfuel available. Sources
of fuel must be identified and must be sustainable.
• The location must have suitable safe access arrangements and be capable of
accommodating the potential transport impacts within the surrounding roads
network.
• A design statement must be submitted, which should include photomontages
from viewpoints agreed by the Council.
• There must be a locational justification for proposals outwith general
employment land designations. The proposed energy use, local heat users and
connectivity of both heat users and electricity networks must be detailed.
Proposals which involve potential or future heat users will not be supported
unless these users can be brought online in conjunction with the operation of
the plant.
• Details of the predicted energy input and output from the plant demonstrating
the plant efficiency and utilisation of heat must be provided.
• Where necessary, appropriate structural landscaping must be provided to
assist the development to integrate sensitively. 
The criteria set out in relation to all renewable energy proposals (part a) must also be
met. 
The Council will consult with Scottish Forestry to help predict potential woodfuel
supply projections in the area. 
d) Heat 
Where a heat network exists or is planned, proposals should include infrastructure to
allow connection to that network. 
Page 254

Page 255

Where no heat network is present or planned: 
• Proposals should consider the feasibility for the creation of or connection to a
heat network.
• Proposals should safeguard piperuns within the development, to its curtilage,
for future connection to a heat network.
• Proposals should consider the provision of energy centres, or the reservation of
land for an energy centre to facilitate future connection to a heat network. 
Proposals for new development will be compared with the Scotland Heat Map to
identify if it could make use of an existing heat supply or provide excess heat to heat
users.  This will be the case until the Council has concluded work on identifying
where heat networks, heat storage and energy centres exist or would be appropriate
in the plan area, at which point reference to that work should be made. 
Developments which have a high heat demand are encouraged to co-locate with
sources of heat supply. 
Where heat networks are not viable, proposals should include the use of
microgeneration technologies and heat recovery associated with individual
properties, unless demonstrating this is unnecessary or unviable. 
The criteria set out in relation to all renewable energy proposals (part a) must also be
met. 
EP1 NATURAL HERITAGE DESIGNATIONS
a) European Site designations
Development likely to have a significant effect on a European Site and which is not
directly connected with or necessary to the conservation management of that site
must be subject to an appropriate assessment of the implications for its conservation
objectives. Proposals will only be approved where the appropriate assessment has
ascertained that there will be no adverse effect on the integrity of the site. 
In exceptional circumstances, proposals that could affect the integrity of a European
Site may be approved where: 
i) There are no alternative solutions, and
ii) There are imperative reasons of over-riding public interest including those of a
social or economic nature, and
iii) Compensatory measures are provided to ensure that the overall coherence of
the Natura network is protected. 
For European Sites hosting a priority habitat or species (as defined in Article 1 of the
The Conservation (Natural Habitat & c.) Regulations 1994), prior consultation with
the European Commission via Scottish Ministers is required unless the imperative
reasons of overriding public interest relate to human health, public safety or
beneficial consequences of primary importance to the environment. 
b) National designations
Development proposals which will affect a National Park, National Scenic Area
(NSA), Site of Special Scientific Interest (SSSI) or National Nature Reserve will only
be permitted where:
Page 255

Page 256

i) The objectives of designation and the overall integrity of the area will not be
compromised; or
ii) Any significant adverse effects on the qualities for which the site has been
designated are clearly outweighed by social, environmental or economic
benefits of national importance. 
c) Local Designations
Development proposals likely to have a significant adverse effect on Local Nature
Reserves, wildlife sites or other valuable local habitats will be refused unless it can
be demonstrated that;
i) Public benefits clearly outweigh the nature conservation value of the site, and
ii) There is a specific locational requirement for the development, and
iii) Any potential impacts can be satisfactorily mitigated to conserve and enhance
the site's residual conservation interest. 
d) European Protected Species
European Protected Species are identified in the Habitats Regulations 1994 (as
amended in Scotland). Where a European Protected Species may be present or
affected by development or activity arising from development, a species survey and
where necessary a Species Protection Plan should be prepared to accompany the
planning application, to demonstrate how the Regulations will be complied with. The
survey should be carried out by a suitably experienced and licensed ecological
surveyor. 
Proposals that would have an adverse effect on European Protected Species will not
be approved unless; 
• The need for development is one that is possible for SNH to grant a license for
under the Regulations (e.g. to preserve public health or public safety).
• There is no satisfactory alternative to the development.
• The development will not be detrimental to the maintenance of the favourable
conservation status of the species. 
e) Other protected species
Wild birds and a variety of other animals are protected under domestic legislation,
such as the Wildlife and Countryside Act 1981 (as amended in Scotland by the
Nature Conservation (Scotland) Act 2004 and the Wildlife and Natural Environment
(Scotland) Act 2011), Protection of Badgers Act 1992 and Marine (Scotland) Act
2010. Where a protected species may be present or affected by development or
activity arising from development, a species survey and where necessary a Species
Protection Plan should be prepared to accompany the planning application to
demonstrate how legislation will be complied with. The survey should be carried out
by a suitably experienced ecological surveyor, who may also need to be licensed
depending on the species being surveyed for. 
Proposals which would have an adverse effect on badgers or their setts must be
accompanied by a Badger Protection Plan demonstrating how impacts will be
avoided, mitigated, minimised or compensated for. 
Page 256

Page 257

EP2 BIODIVERSITY 
All development proposals must, where possible, retain, protect and enhance features of
biological interest and provide for their appropriate management.  Development must
safeguard and where physically possible extend or enhance wildlife corridors and
green/blue networks and prevent fragmentation of existing habitats. 
Development should integrate measures to enhance biodiversity as part of multi-functional
spaces/ routes. 
Proposals for 4 or more housing units or 1000 m2 or more of commercial floorspace must
create new or, where appropriate, enhance natural habitats of ecological and amenity
value. 
Developers must demonstrate, through a Placemaking Statement where required by
Policy PP1 which incorporates a Biodiversity Plan, that they have included biodiversity
features in the design of the development. Habitat creation can be achieved by providing
links into existing green and blue networks, wildlife friendly features such as wildflower
verges and meadows, bird and bat boxes, amphibian friendly kerbing, wildlife crossing
points such as hedgehog highways and planting to encourage pollination, wildlife friendly
climbing plants, use of hedges rather than fences, incorporating biodiversity measures into
SUDS and retaining some standing or lying dead wood, allotments, orchards and
woodlands. 
Where development would result in loss of natural habitats of ecological amenity value,
compensatory habitat creation will be required where deemed appropriate. 
EP3 SPECIAL LANDSCAPE AREAS AND LANDSCAPE CHARACTER
i)  Special Landscape Areas (SLA's) 
Development proposals within SLA's will only be permitted where they do not
prejudice the special qualities of the designated area set out in the Moray Local
Landscape Designation Review, adopt the highest standards of design in
accordance with Policy DP1 and other relevant policies, minimises adverse impacts
on the landscape and visual qualities the area is important for, and are for one of the
following uses; 
a) In rural areas (outwith defined settlement and rural grouping boundaries);
i) Where the proposal involves an appropriate extension or change of use to
existing buildings, or
ii) For uses directly related to distilling, agriculture, forestry and fishing which
have a clear locational need and demonstrate that there is no alternative
location, or
iii) For nationally significant infrastructure developments identified in the
National Planning Framework, 
b) In urban areas (within defined settlement, rural grouping boundaries and LONG
designations);
i) Where proposals conform with the requirements of the settlement
statements, Policies PP1, DP1 and DP3 as appropriate and all other
policy requirements, and
ii) Proposals reflect the traditional settlement character in terms of siting and
design.
Page 257

Page 258

c) The Coastal (Culbin to Burghead, Burghead to Lossiemouth, Lossiemouth to
Portgordon, Portgordon to Cullen Coast), Cluny Hill, Spynie, Quarrywood and
Pluscarden SLA's are classed as "sensitive" in terms of Policy DP4 and no new
housing in the open countryside will be permitted within these SLA's. 
Proposals for new housing within other SLA's not specified in the preceding
para will be considered against the criteria set out above and the criteria of
Policy DP4. 
d) Where a proposal is covered by both a SLA and CAT or ENV
policy/designation, the CAT policy or ENV policy/designation will take
precedence. 
b ii) Landscape Character 
New developments must be designed to reflect the landscape characteristics
identified in the Landscape Character Assessment of the area in which they are
proposed. 
Proposals for new roads and hill tracks associated with rural development must
ensure that their alignment and use minimises visual impact, avoids sensitive natural
heritage and historic environment features, including areas protected for nature
conservation, carbon rich soils and protected species, avoids adverse impacts upon
the local hydrology and takes account of recreational use of the track and links to the
wider network. 
EP7 FORESTRY, WOODLANDS AND TREES
a) Moray Forestry and Woodland Strategy
Proposals which support the economic, social and environmental objectives and
projects identified in the Moray Forestry and Woodlands Strategy will be supported
where they meet the requirements of other relevant Local Development Plan
policies.  The council will consult Scottish Forestry on proposals which are
considered to adversely affect forests and woodland.  Development proposals must
give consideration to the relationship with existing woodland and trees including
shading, leaf/needle cast, branch cast, wind blow, water table impacts and
commercial forestry operations. 
b) Tree Retention and Survey 
Proposals must retain healthy trees and incorporate them within the proposal unless
it is technically unfeasible to retain these.  Where trees exist on or bordering a
development site, a tree survey, tree protection plan and mitigation plan must be
provided with the planning application if the trees or trees bordering the site (or their
roots) have the potential to be affected by development and construction activity. 
Proposals must identify a safeguarding distance to ensure construction works,
including access and drainage arrangements, will not damage or interfere with the
root systems in the short or longer term.  A landscaped buffer may be required where
the council considers that this is required to maintain an appropriate long term
relationship between proposed development and existing trees and woodland. 
Where it is technically unfeasible to retain trees, compensatory planting on a one for
one basis must be provided in accordance with (e) below. 
Page 258

Page 259

c) Control of Woodland Removal 
In support of the Scottish Government's Control of Woodland Removal Policy,
Woodland removal within native woodlands identified as a feature of sites protected
under Policy EP1 or woodland identified as Ancient Woodland will not be supported. 
In all other woodlands development which involves permanent woodland removal will
only be permitted where it would achieve significant and clearly defined additional
public benefits (excluding housing) and where removal will not result in unacceptable
adverse effects on the amenity, landscape, biodiversity, economic or recreational
value of the woodland or prejudice the management of the woodland. 
Where it is proposed to remove woodland, compensatory planting at least equal to
the area to be felled must be provided in accordance with e) below. 
d) Tree Preservation Orders and Conservation Areas 
The council will serve Tree Preservation Orders (TPO's) on potentially vulnerable
trees which are of significant amenity value to the community as whole, trees that
contribute to the distinctiveness of a place or trees of significant biodiversity value. 
Within Conservation Areas, the council will only agree to the felling of dead, dying, or
dangerous trees. Trees felled within Conservation Areas or subject to TPO must be
replaced, unless otherwise agreed by the council. 
e) Compensatory Planting 
Where trees or woodland are removed in association with development, developers
must provide compensatory planting to be agreed with the planning authority either
on site, or an alternative site in Moray which is in the applicant's control or through a
commuted payment to the planning authority to deliver compensatory planting and
recreational greenspace. 
GUIDANCE TREES AND DEVELOPMENT
Trees are an important part of Moray's towns and villages and surrounding countryside,
adding colour and interest to the townscape and a sense of nature in our built
environment. They contribute to the diversity of the countryside, in terms of landscape,
wildlife habitat and shelterbelts. Trees also have a key role to play in terms of climate
change by helping to absorb carbon dioxide which is one of the main greenhouse gases
that cause global warming. 
The cumulative loss of woodlands to development can result in significant loss of
woodland cover. In compliance with the Scottish Government Control of Woodland
Removal policy, woodland removal should only be allowed where it would achieve
significant and clearly defined additional public benefits. In appropriate cases a proposal
for compensatory planting may form part of this balance. Where woodland is to be
removed then the Council will require compensatory planting to be provided on site, on
another site in Moray within the applicant's control or through a commuted payment to the
Council towards woodland and greenspace creation and enhancement. Developers
proposing compensatory planting are asked to follow the guidance for site assessment
and woodland design as laid out in Scottish Forestry's "Woodland Creation, Application
Guidance" and its subsequent updates, when preparing their proposal. 
The Council requires a Tree Survey and Tree Protection Plan to be submitted by the
applicant with any planning application for detailed permission on designated or windfall
Page 259

Page 260

sites which have trees on them. The survey should include a schedule of trees and/or
groups of trees and a plan showing their location, along with the following details; 
• Reference number for each tree or group of trees.
• Scientific and common names.
• Height and canopy spread in metres (including consideration of full height and
spread).
• Root protection area.
• Crown clearance in metres.
• Trunk diameters in metres (measures at 1.5m above adjacent ground level for single
stem trees or immediately above the root flare for multi stemmed trees).
• Age and life expectancy.
• Condition (physiological and structural).
• Management works required.
• Category rating for all trees within the site (U, A, B or C *). This arboricultural
assessment will be used to identify which trees are suitable for retention within the
proposed development. 
*BS5837 provides a cascading quality assessment process for categorisation of trees
which tree surveys must follow. An appropriately scaled tree survey plan needs to
accompany the schedule. The plan should be annotated with the details of the tree
survey, showing the location, both within and adjacent to the site, of existing trees, shrubs
and hedgerows. Each numbered tree or groups of trees should show the root protection
area and its category U, A, B, C. 
Based on the guidance in BS5837, only category U trees are discounted from the Tree
Survey and Tree Protection Plan process. Trees in category A and B must be retained,
with category C trees retained as far as practicable and appropriate. Trees proposed for
removal should be replaced with appropriate planting in a landscape plan which should
accompany the application. Trees to be retained will likely be set out in planning
conditions, if not already covered by a Tree Preservation Order. 
If a tree with habitat value is removed, then measures for habitat reinstatement must be
included in the landscape plan. It is noted that in line with part b) of policy EP7 where
woodland is removed compensatory planting must be provided regardless of tree
categorisation." 
A Tree Protection Plan (TPP) must also be submitted with planning applications,
comprising a plan and schedule showing; 
• Proposed design/ layout of final development, including accesses and services.
• Trees to be retained- with those requiring remedial work indicated.
• Trees to be removed.
• Location (and specification) of protective fencing around those trees to be retained
based on the Root Protection Area. 
The TPP should show how the tree survey information has informed the design/ layout
explaining the reasoning for any removal of trees. 
Landscape Scheme
Where appropriate a landscape scheme must be submitted with planning applications,
clearly setting out details of what species of trees, shrubs and grass are proposed, where,
Page 260

Page 261

what standard and when planting will take place. Landscape schemes must aim to deliver
multiple benefits in terms of biodiversity, amenity, drainage and recreation as set out in
policy. 
The scheme should also set out the maintenance plan. Applicants/ developers will be
required to replace any trees, shrubs or hedges on the site which die, or are dying,
severely damaged or diseased which will be specified in planning conditions. 
Tree species native to Scotland are recommended for planting in new development -
Alder, Aspen, Birch, Bird Cherry, Blackthorn, Crab Apple, Elm, Gean, Hawthorn, Hazel,
Holly, Juniper, Sessile Oak, Rowan, Scots Pine, Whitebeam, Willow. 
EP8 HISTORIC ENVIRONMENT
a) Scheduled Monuments and Unscheduled Archaeological Sites of Potential
National Importance.
Where a proposed development potentially has a direct impact on a Scheduled
Monument, Scheduled Monument Consent (SMC) is required, in addition to any
other necessary consents.  Historic Environment Scotland manage these consents. 
Development proposals will be refused where they adversely affect the integrity of
the setting of Scheduled Monuments and unscheduled archaeological sites of
potential national importance unless the developer proves that any significant
adverse effects are clearly outweighed by exceptional circumstances, including
social or economic benefits of national importance. 
b) Local Designations
Development proposals which adversely affect sites of local archaeological
importance or the integrity of their settings will be refused unless; 
• Local public benefits clearly outweigh the archaeological value of the site, and
• Consideration has been given to alternative sites for the development and
preservation in situ is not possible.
• Where possible any adverse effects can be satisfactorily mitigated at the
developer's expense. 
The Council will consult Historic Environment Scotland and the Regional
Archaeologist on development proposals which may affect Scheduled Monuments,
nationally important archaeological sites and locally important archaeological sites. 
EP11 BATTLEFIELDS, GARDENS AND DESIGNED LANDSCAPES 
Development proposals which adversely affect nationally designated Battlefields or
Gardens and Designed Landscapes or their setting will be refused unless; 
a) The overall character and reasons for the designation will not be compromised, or
b) Any significant adverse effects can be satisfactorily mitigated and are clearly
outweighed by social, environmental, economic or strategic benefits. 
The Council will consult Historic Environment Scotland and the Regional Archaeologist on
any proposals which may affect Inventory Sites. 
Page 261

Page 262

EP12 MANAGEMENT AND ENHANCEMENT OF THE WATER ENVIRONMENT
a) Flooding 
New development will not be supported if it would be at significant risk of flooding
from any source or would materially increase the possibility of flooding elsewhere.
For development at or near coastal locations, this includes consideration of future
flooding that may be caused by sea level rise and/or coastal change eroding existing
natural defences in the medium and long term. 
Proposals for development in areas considered to be at risk from flooding will only be
permitted where a flood risk assessment to comply with the recommendations of
Scottish Planning Policy and to the satisfaction of Scottish Environment Protection
Agency and the Council is provided by the applicant. 
There are different levels of flood risk assessment dependent on the nature of the
flood risk. The level of assessment should be discussed with the Council prior to
submitting a planning application. 
Level 1 -  a flood statement with basic information with regard to flood risk.
Level 2 -  full flood risk assessment providing details of flood risk from all sources,
results of hydrological and hydraulic studies and any appropriate
proposed mitigation. 
Assessments must demonstrate that the development is not at risk of flooding and
would not increase the probability of flooding elsewhere.  Level 2 flood risk
assessments must be signed off by a competent professional.  The Flood Risk
Assessment and Drainage Impact Assessment for New Development Supplementary
Guidance provides further detail on the information required. 
Due to continuing changes in climatic patterns, the precautionary principle will apply
when reviewing any application for an area at risk from inundation by floodwater.
Proposed development in coastal areas must consider the impact of tidal events and
wave action when assessing potential flood risk.   
The following limitations on development will also be applied to take account of the
degree of flooding as defined in Scottish Planning Policy;
a) In areas of little to no risk (less than 0.1%), there will be no general constraint to
development.
b) Areas of low to medium risk (0.1% to 0.5%) will be considered suitable for most
development. A flood risk assessment may be required at the upper end of the
probability range i.e. (close to 0.5%) and for essential civil infrastructure and the
most vulnerable uses. Water resistant materials and construction may be
required. Areas within this risk category will generally not be suitable for civil
infrastructure. Where civil infrastructure must be located in these areas or is
being substantially extended, it should be designed to be capable of remaining
operational and accessible during flooding events.
c) Areas of medium to high risk (0.5% or above) may be suitable for:
• Residential, institutional, commercial and industrial development within
built up areas provided that flood protection measures to the appropriate
standard already exist and are maintained, are under construction, or are
a planned measure in a current flood management plan.
• Essential infrastructure within built up areas, designed and constructed to
remain operational during floods and not impede water flow.
Page 262

Page 263

• Some recreational, sport, amenity and nature conservation uses, provided
appropriate evacuation procedures are in place, and
• Employment related accommodation e.g. caretakers or operational staff. 
Areas within these risk categories will generally not be suitable for the following
uses and where an alternative/lower risk location is not available¬¬;
• Civil infrastructure and most vulnerable uses. 
• Additional development in undeveloped and sparsely developed areas,
unless a location is essential for operational reasons e.g. for navigation
and water based recreation, agriculture, transport or utilities infrastructure
(which should be designed to be operational during floods and not impede
water flows).
• New caravan and camping sites 
Where development is permitted, measures to protect against or manage flood
risk will be required and any loss of flood storage capacity mitigated to achieve
a neutral or better outcome. Water resistant materials and construction must be
used where appropriate. Land raising and elevated buildings on structures such
as stilts are unlikely to be acceptable. 
b) Surface Water Drainage: Sustainable Urban Drainage Systems (SUDS) 
Surface water from development must be dealt with in a sustainable manner that has
a neutral effect on flooding or which reduces the risk of flooding. The method of
dealing with surface water must also avoid pollution and promote habitat
enhancement and amenity. All sites must be drained by a sustainable drainage
system (SUDS) designed in line with current CIRIA guidance. Drainage systems
must contribute to enhancing existing "blue" and "green" networks while contributing
to place-making, biodiversity, recreational, flood risk and climate change objectives. 
When considering the appropriate SUDS design for the development the most
sustainable methods, such as rainwater harvesting, green roofs, bio retention
systems, soakaways, and permeable pavements must be considered first.  If it is
necessary to include surface water attenuation as part of the drainage system, only
above ground attenuation solutions will be considered, unless this is not possible
due to site constraints.   
If below ground attenuation is proposed the developer must provide a robust
justification for this proposal.  Over development of a site or a justification on
economic grounds will not be acceptable.  When investigating appropriate SUDS
solutions developers must integrate the SUDS with allocated green space, green
networks and active travel routes to maximise amenity and biodiversity benefits. 
Specific arrangements must be made to avoid the issue of permanent SUDS
features becoming silted-up with run-off. Care must be taken to avoid the spreading
and/or introduction of invasive non-native species during the construction of all
SUDS features.  On completion of SUDS construction the developer must submit a
comprehensive Operation and Maintenance Manual.  The ongoing maintenance of
SUDS for all new development will be undertaken through a factoring agreement, the
details of which must be supplied to the Planning Authority.   
Page 263

Page 264

All developments of less than 3 houses or a non-householder extension under 100
square metres must provide a Drainage Statement.  A Drainage Assessment will be
required for all developments other than those identified above. 
c) Water Environment 
Proposals, including associated construction works, must be designed to avoid
adverse impacts upon the water environment including Ground Water Dependent
Terrestrial Ecosystems and should seek opportunities for restoration and/or
enhancement, if appropriate. The Council will only approve proposals impacting on
water features where the applicant provides a report to the satisfaction of the Council
that demonstrates that any impact (including cumulative) on water quality, water
quantity, physical form (morphology), river hydrology, sediment transport and
erosion, coastal processes (where relevant) nature conservation (including protected
species), fisheries, recreational, landscape, amenity and economic and social impact
can be adequately mitigated. 
The report must consider existing and potential impacts up and downstream of the
development particularly in respect of potential flooding. The Council operates a
presumption against the culverting of watercourses and any unnecessary
engineering works in the water environment. 
A buffer strip of at least 6 metres between any new development and all water
features is required and should be proportional to the bank width and functional river
corridor (see table on page 96). This must achieve the minimum width within the
specified range as a standard, however, the actual required width within the range
should be calculated on a case by case basis by an appropriately qualified individual.
These must be designed to link with blue and green networks, including appropriate
native riparian vegetation and can contribute to open space requirements. 
Developers may be required to make improvements to the water environment as part
of the development. Where a Water Framework Directive (WFD)¬ water body
specific objective is within the development boundary, or in proximity, developers will
need to address this within the planning submission through assessment of potential
measures to address the objective and implementation, unless adequate justification
is provided. Where there is no WFD objective the applicant should still investigate
the potential for watercourse restoration along straightened sections or removal of
redundant structures and implement these measures where viable. 
Width to watercourse Width of buffer strip (either side)
(top of bank) 
Less than 1m 6m
1-5m        6-12m
5-15m 12-20m
15m+ 20m+ 
The Flood Risk Assessment and Drainage Impact Assessment for New Development
Supplementary Guidance provides further detail on the information required to
support proposals. 
Page 264

Page 265

EP13 FOUL DRAINAGE 
All development within or close to settlements (as defined in the Local Development Plan)
of more than 2,000 population must connect to the public sewerage system unless
connection is not permitted due to lack of capacity. In such circumstances, temporary
provision of private sewerage systems may be allowed provided Scottish Water has
confirmed investment to address this constraint has been allocated within its investment
Programme and the following requirements have been met; 
• Systems must not have an adverse effect on the water environment.
• Systems must be designed and built to a standard which will allow adoption by
Scottish Water.
• Systems must be designed such that they can be easily connected to a public sewer
in the future. Typically this will mean providing a drainage line up to a likely point of
connection. 
All development within or close to settlements (as above) of less than 2,000 population will
require to connect to public sewerage except where a compelling case is made otherwise.
Factors to be considered in such a case will include size of the proposed development,
whether the development would jeopardise delivery of public sewerage infrastructure and
existing drainage problems within the area. 
Where a compelling case is made, a private system may be acceptable provided it does
not pose or add a risk of detrimental effects, including cumulative, to the natural and built
environment, surrounding uses or amenity of the general area. 
Where a private system is deemed to be acceptable, within settlements as above or small
scale development in the countryside, a discharge to land, either full soakaway or raised
mound soakaway, compatible with Technical Handbooks (which sets out guidance on how
proposals may meet the Building  Regulations) must be explored prior to considering a
discharge to surface waters. 
EP14 POLLUTION, CONTAMINATION & HAZARDS
a)  Pollution 
Development proposals which may cause significant air, water, soil, light or noise
pollution or exacerbate existing issues must be accompanied by a detailed
assessment report on the levels, character and transmission of the potential pollution
with measures to mitigate impacts. Where significant or unacceptable impacts
cannot be mitigated, proposals will be refused.   
b) Contamination 
Development proposals on potentially contaminated land will be approved where
they comply with other relevant policies and; 
i) The applicant can demonstrate through site investigations and risk assessment,
that the site is in a condition suitable for the proposed development and is not
causing significant pollution of the environment; and
ii) Where necessary, effective remediation measures are agreed to ensure the
site is made suitable for the new use and to ensure appropriate disposal and/ or
treatment of any hazardous material. 
Page 265

Page 266

c) Hazardous sites 
Development proposals must avoid and not impact upon hazardous sites or result in
public safety concerns due to proximity or use in the vicinity of hazardous sites. 
EP15 MOD SAFEGUARDING
Development proposals must not adversely impact upon Ministry of Defence safeguarding
operations. Details of consultation zones for Kinloss Barracks and RAF Lossiemouth and
development types which will be subject to consultation with the Defence Infrastructure
Organisation are available from Moray Council. The outer boundaries of the zones are
shown on the Proposals Map. 
EP16 GEODIVERSITY AND SOIL RESOURCES
Where peat and other carbon rich soils are present disturbance to them may lead to the
release of carbon dioxide contributing to the greenhouse gas emissions. Applications
should minimise this release and must be accompanied by an assessment of the likely
effects associated with any development work and aim to mitigate any adverse impacts
arising. 
Where areas of important geological interest are present, such as geological Sites of
Special Scientific Interest (SSSI) or Geological Conservation Review (GCR) sites are
present, excavations or built development can damage, destroy and/or prevent access to
the irreplaceable geological features. Development should avoid sensitive geological
areas or otherwise demonstrate how the geological interests will be safeguarded. 
For major developments, minerals and large scale (over 20MW) renewable energy
proposals, development will only be permitted where it has been demonstrated that
unnecessary disturbance of soils, geological interests, peat and any associated vegetation
is avoided. Evidence of the adoption of best practice in the movement, storage,
management and reinstatement of soils must be submitted along with any relevant
planning application, including, if necessary, measures to prevent the spread of invasive
non-native species. 
Major developments, minerals and large scale renewable energy proposals on areas of
peat and/or land habitat will only be permitted for these uses where: 
a) The economic, social and/or environmental benefits of the proposal outweigh any
potential detrimental effect on the environment (in particular with regard to the
release of carbon dioxide into the atmosphere); and
b) It has been clearly demonstrated that there is no viable alternative. 
Where development on peat is deemed acceptable, a peat depth survey must be
submitted which demonstrates that the areas of deepest peat have been avoided. Where
required, a peat management plan must also be submitted which demonstrates that
unnecessary disturbance, movement, degradation or erosion of peat is avoided and
proposes suitable mitigation measures and appropriate reuse.
Commercial peat extraction will not be permitted. 
Page 266

Page 267

WARD 04_17 
22/01269/APP
12 September 2022
Erect storage warehouses and ancillary development
(amenity block sprinkler tank and pump house) land
engineering (cut and fill),realignment of Core Burn and
associated engineering and infrastructure works
including access and sub-station on Land To The South
Of Crisp Maltings Portgordon Buckie Moray
for William Grant & Sons Distillers Ltd 
Comments:  
 A site visit will have been carried out.
 The application is for a site with an area of 2 or more hectares. 
 Advertised for neighbour notification purposes – notification not possible because
no premises are situated on land to which notification can be sent. 
 6 representations have been received. 
Procedure: 
 None. 
Recommendation 
Grant Planning Permission – Subject to the following: 
Conditions/Reasons 
1. The development to which this permission relates must be begun not later than
the expiration of 3 years beginning with the date on which the permission is
granted. 
Reason: The time limit condition is imposed in order to comply with the
requirements of section 58 of the Town and Country Planning (Scotland) Act 1997
as amended. 
2. No development shall commence until a Construction Traffic Management Plan
(CTMP) has been submitted to an agreed in writing by the Planning Authority in
consultation with the Roads Authority. Thereafter the development shall be carried
out in accordance with the agreed CTMP at all times. For the avoidance of doubt
the CTMP shall include as a minimum the following information:
a)   duration of works;
b)   construction programme;
Item 10
Page 267

Page 268

c)   number of vehicle movements (i.e. materials, plant, staff, components);
d)   schedule for delivery of materials and plant;
e)   parking provision, loading and unloading areas for construction traffic;
f)   full details of temporary arrangements to safeguard pedestrian movements
during the construction period;
g)   full details of any temporary access;
h)   measures to be put in place to prevent material being deposited on the
public road;
i)   traffic management measures to be put in place during works including any
specific instructions to drivers.
j)   full details of construction traffic routes from/to the site, including any
proposals for temporary haul routes and routes to be used for the disposal of
any materials from the site;
k)   a programme of monitoring for all routes identified within the CTMP during
construction will be required 
Reason: To ensure an acceptable form of development in terms of the
arrangements to manage traffic during construction works at the site. 
3. No development shall commence until evidence of a satisfactory Wear and Tear
Agreement has been submitted to and agreed in writing by the Planning Authority
in consultation with the Roads Authority. The scope of the Wear and Tear
Agreement shall be agreed with the Planning Authority in consultation with the
Roads Authority and shall include a condition survey of the network undertaken
jointly by the developer and a representative from the Council. The survey shall
include the full extent of the agreed construction traffic route(s) (within Moray)
between the site and the ‘A’ class road network. In addition, the wear and tear
agreement shall also include condition surveys of all roads identified as
‘unsuitable’ which must be agreed with the Planning Authority in consultation with
the Roads Authority as a part of condition ‘2’ above. 
Reason: To mitigate the potential risks from damage to the public road occurring
during the construction phase of the development. 
4. No development shall commence until evidence of a financial guarantee or bond
or suitable equivalent and a Wear and Tear Agreement have been put in place to
ensure the repair of the public road serving the site in the event that the road is
not maintained in a safe condition during the construction phase of the
development and to restore the road to its pre-development condition within 1
year of the development becoming operational has been submitted to and agreed
in writing with the Council, as Planning Authority. For the avoidance of doubt the
agreement shall cover the section of the A990 Enzie - Portgordon - Buckie Road
from the A98 to the site entrance as a minimum and all roads identified for off-site
disposal of material/soil as in condition ‘1’ above. 
Reason: To mitigate the potential risks from damage to the public road occurring
during the construction phase of the development. 
Page 268

Page 269

5.  No development shall commence until:
a)   a visibility splay 4.5 metres by 215 metres, with all boundaries set back to a
position behind the required visibility splay, has been provided in both
directions at the access onto the public road; and
b)   Thereafter the visibility splay shall be maintained at all times free from any
obstruction exceeding 0.6 metres above the level of the carriageway.
c)   Additionally a forward visibility splay of 215m is required to maintain at the
site entrance for the vehicles waiting on the main road to turn right into the
site access. These vehicles must be able to see oncoming traffic and be
seen by following traffic. 
Reason: To enable drivers of vehicles leaving/entering the site to have a clear
view over a length of road sufficient to allow safe exit/entry, in the interests of road
safety for the proposed development and other road users. 
6. No water shall be permitted to drain or loose material be carried onto the public
footway/carriageway. 
Reason: To ensure the safety and free flow of traffic on the public road and
access to the site by minimising the road safety impact from extraneous material
and surface water in the vicinity of the new access. 
7. Two car parking spaces shall be provided within the site prior to the warehouse
being completed or becoming operational and shall be maintained and available
for use thereafter for the lifetime of the development unless otherwise agreed in
writing with the Council as Planning Authority. 
Reason: To ensure the permanent availability of the level of parking necessary for
employees/visitors/others in the interests of an acceptable development and road
safety. 
8. No development shall commence until the following details for the provision of an
Electric Vehicle (EV) charging space have been submitted for approval by the
Planning Authority in consultation with the Roads Authority:
   A detailed drawing (scale 1:200) showing the type and specifications of the
proposed EV charging units(s) to serve a minimum of 1 space with a
minimum power output of 22Kw (Rapid Charger). EV charging unit is to be
connected to an appropriate electricity supply and should include details
(written proposals and plans) to confirm the provision of the necessary
cabling, ducting, and consumer units capable of supporting the future
charging unit. 
Thereafter the EV charging facilities shall be provided in accordance with the
approved details prior to the development becoming operational or opened and
maintained for use thereafter unless otherwise agreed in writing by the Planning
Authority in consultation with the Roads Authority. 
Reason: In the interests of an acceptable form of development and the provision
of infrastructure to support the use of low carbon transport, through the provision
of details currently lacking from the submission.
Page 269

Page 270

9. Construction works (including vehicle movements) associated with the
development audible at any point on the boundary of any noise sensitive dwelling
shall be permitted between 0800 - 1900 hours, Monday to Friday and 0800 - 1300
hours on Saturdays only, and at no other times out with these permitted hours
(including National Holidays). The above construction hours shall apply, unless
otherwise agreed in writing with the Planning Authority, and where so
demonstrated exceptional operational constraints require limited periods of
construction works to be undertaken out with the permitted construction hours. 
Reason: To protect local residents from noise nuisance in ensuring the
construction phase is restricted within permitted hours. 
10. Prior to development commencing, a Construction Environmental Management
Plan (CEMP) shall be submitted to and agreed in writing by the Planning Authority
in consultation with the Environmental Health Manager. The plan shall include
measures to minimise construction related noise (including vibration), dust and
artificial lighting. Thereafter the development will be carried out in accordance with
the agreed plan. 
Reason: In order that environmental emissions are considered and managed at
the construction phase, in order to protect local residents. 
11. The rating level of noise associated with the development shall not exceed the
background sound level by more than 5 dB at the nearest noise sensitive dwelling
which is lawfully existing or has planning permission at the date of this permission.
For the avoidance of doubt, the rating level and background sound level
associated with this condition are defined within BS 4142: 2014 + A1:2019
Methods for rating and assessing industrial and commercial sound. 
Reason: To protect local residents from noise nuisance due to the use of the
development. 
12. Unless otherwise agreed in writing with the Council as Planning Authority in
consultation with the Environmental Health Manager, external operations or
vehicle movements relating to the operation of the warehouses shall only take
place between 08.00 and 19.00 hours, Monday to Friday and 8am and 1pm, on
Saturdays, and no external operations or vehicle movements shall take place on
bank/public holidays. 
Reason: In order to minimise noise pollution in the interests of the amenity of
neighbouring residents. 
13. Prior to the development commencing details of the operational site lighting shall
be submitted to and agreed in writing by the Planning Authority, in consultation
with the Environmental Health Manager. Thereafter, the agreed lighting details
shall be maintained throughout the lifetime of the development. 
Reason: To protect residents from light nuisance due to the use of the
development.
Page 270

Page 271

14. Prior to the commencement of development, an updated flood risk assessment on
the detailed design of the channel realignment and bank reinforcement should be
provided to the satisfaction of the Planning Authority in consultation with SEPA
which demonstrates there is no increase in flood risk from the proposals. The
submitted Portgordon Flood Risk Assessment REV03 envireau water September
2022 and the drawings in Appendix B Outline Core Burn Re-alignment Channel
Design Drawings CBEC eco engineering should be used as the basis for the
detailed channel design.   
Thereafter the development shall be carried out in accordance with the agreed
detailed design of the channel realignment and bank reinforcement.   
Reason: To ensure the channel realignment and bank reinforcement is designed
to an acceptable standard in the interests of minimising flood risk to the site.     
15. Prior to development commencing details of the proposed foul sewerage system
shall be submitted to and agreed in writing with the planning authority in
consultation with the flood risk management team.  Thereafter the agreed foul
drainage system shall be installed in accordance with the agreed details, prior to
the first use of the site.   
Reason: To ensure the installation of an acceptable private foul drainage system.   
16. A construction phase surface water management plan shall be submitted a
minimum of two months prior to the commencement of the development and shall
be agreed in writing prior to work commencing with the Planning Authority in
consultation with Moray Flood Risk Management. The plan shall include measures
to prevent increased flood risk and to ensure heavily silted surface water does not
enter any watercourse. 
Thereafter the development shall be carried out in accordance with the agreed
details. 
Reason: To prevent surface water flooding during the course of the development
and minimise risk to adjacent watercourses. 
17. The surface water drainage arrangements for the development shall be provided
and maintained in accordance with the approved Drainage Impact Assessment
G:\C&S\EC22743\reports\R001 Drainage Impact Assessment Rev B.docx, dated
29/11/22, prepared by Blyth and Blyth, unless otherwise agreed by the Council, as
Planning Authority. These shall be installed and operational prior to the first use of
the buildings hereby approved. 
Reason: To ensure that surface water drainage is provided timeously and
complies with the principles of SuDS in order to protect the water environment. 
18. Notwithstanding the provisions of the Town and Country Planning (Use Classes)
(Scotland) Order 1997 (or any order revoking and re-enacting that order) the
approval hereby granted only relates to the use of the two proposed buildings as
Page 271

Page 272

Whisky Cask Storage and for no other use or purpose without the prior approval
of the Council, as Planning Authority. 
Reason: In order to retain Local Authority control over the use of the site and to
ensure that consideration can be given to the effects and impact of uses other
than that approved herewith. 
19. Notwithstanding the provisions of the Town and Country Planning (General
Permitted Development) (Scotland) Order 1992 (or any order revoking and re-
enacting that order) no development specified in Article 3, Schedule 1, Part 3,
Class 13 shall be carried out without the approval of the Council, as Planning
Authority. 
Reason: In order to retain control over the use of the site and to ensure that
consideration can be given to the effects and impact of uses other than that
approved herewith. 
20. No works in connection with the development hereby approved shall commence
unless an archaeological written scheme of investigation (WSI) has been
submitted to and approved in writing by the planning authority and a programme
of archaeological works has been carried out in accordance with the approved
WSI. The WSI shall include details of how the recording and recovery of
archaeological resources found within the application site shall be undertaken,
and how any updates, if required, to the written scheme of investigation will be
provided throughout the implementation of the programme of archaeological
works. 
Should the archaeological works reveal the need for post excavation analysis the
development hereby approved shall not be brought into use unless a post-
excavation research design (PERD) for the analysis, publication and
dissemination of results and archive deposition has been submitted to and
approved in writing by the planning authority. The PERD shall be carried out in
complete accordance with the approved details. 
Reason: To safeguard and record the archaeological potential of the area. 
21. Prior to development commencing a detailed phasing landscape plan (including
timescales), landscape maintenance and woodland management plan shall be
submitted to and agreed in writing with the planning authority.  Thereafter the
approved landscaping/woodland shall be implemented and maintained in
accordance with the agreed details. 
Reason: To ensure the landscaping is delivered, retained and maintained
throughout the lifetime of the development.   
22. Landscaping as detailed on the approved landscaping plan, shall be provided in
the planting season following the completion or first use of the development
(whichever is the soonest).   
Page 272

Page 273

Reason: To ensure an acceptable scheme of landscaping is provided and
maintained to aid the visual integration of the development and enhance habitat
and biodiversity value of the site.   
23.  Prior to development commencing details including design, number, position and
schedule for installation of bat and bird boxes to be provided adjacent to the SUDs
ponds, shall be submitted to and agreed in writing with the Planning Authority. 
Thereafter the bat and bird boxes shall be erected in accordance with the agreed
details and retained throughout the lifetime of the development.   
Reason: To ensure the timeous provision of bat and bird boxes, in the interests of
enhancing habitat provision across the site.   
Reason(s) for Decision
The Council’s reason(s) for making this decision are:- 
The erection of buildings for whisky storage in this location is considered acceptable
and would not have an adverse impact on the surrounding area. The proposal complies
with the provisions of the development plan and there are no material considerations
that indicate otherwise. 
List of Informatives: 
THE DEVELOPMENT MANAGEMENT & BUILDING STANDARDS MANAGER has
commented that:- 
A Building Warrant will be required for the proposals. Should you require further
assistance please contact the Building Standards Duty Officer between 2pm and
4pm or telephone on 03001234561. No appointment is necessary. Alternatively e-
mail buildingstandards@moray.gov.uk 
THE TRANSPORTATION MANAGER has commented that:- 
The applicant is obliged to apply for a road opening permit in accordance with
Section 56 of the Roads (Scotland) Act 1984. Advice on this matter can be
obtained by emailing roadspermits@moray.gov.uk and reference to the following
page on the Council web site Road Opening:
http://www.moray.gov.uk/moray_standard/page_79860.html 
Public utility apparatus may be affected by this proposal. Contact the appropriate
utility service in respect of any necessary utility service alterations which have to
be carried out at the expense of the developer. 
No building materials/scaffolding/builder’s skip shall obstruct the public road
(including footpaths) without permission from the Roads Authority. 
The applicant shall free and relieve the Roads Authority from any claims arising
out of their operations on the road or extension to the road.
Page 273

Page 274

The applicant shall be responsible for ensuring that surface/ground water does not
run from the public road into their property. 
The applicants shall be responsible for any necessary diversion of any utilities or
drainage present at the locations where works are to be undertaken. 
The applicants shall meet all costs of improvements to the road infrastructure,
which are required as a result of the development. 
No retaining structures or embankments shall be constructed along the edge of
the road, whether retaining the public road or ground adjoining the public road
without prior consultation and agreement of the Roads Authority. 
THE SCOTTISH ENVIRONMENT PROTECTION AGENCY has commented that:- 
SEPA regulates several matters covered by this planning application including the
proposed re-alignment of the Core Burn. We will address all matters relating to
regulation when the appropriate regulatory application is made. It is an applicant’s
responsibility to ensure their proposals will meet all relevant regulatory
requirements and they are working within regulatory guidelines. We prefer all the
technical information required for any SEPA consents to be submitted at the same
time as the planning or similar application. We consider it to be at the applicant's
commercial risk if planning permission is granted for a development/process which
cannot gain authorisation from us, or if any significant changes required during the
regulatory stage necessitate a further planning application or similar application
and/or neighbour notification or advertising. 
Additional information
   Details of regulatory requirements and good practice advice for the applicant
can be found on the Regulations section of our website.
   Proposals which impact on the water environment may be regulated under
The Water Environment (Controlled Activities) (Scotland) Regulations 2011.
Refer applicants to CAR_a_practical_guide and our water permitting team at
waterpermitting@sepa.org.uk 
   Proposals such as industrial processes which have air emissions, or
intensive agriculture may require a permit under the Pollution Prevention and
Control (Scotland) Regulations 2012 (PPC 2012). Refer applicants to the
Pollution Prevention section of our website and our waste and industry team
at wasteandindustry@sepa.org.uk
   Proposals which involve the treatment, storage or disposal of waste may
require a waste management licence under The Waste Management
Licensing (Scotland) Regulations 2011. Refer applicants to the waste section
of our website and our waste permitting team at
wastepermitting@sepa.org.uk 
We welcome that you have recognised the Control of Major Accident Hazards
Regulations 2015 (COMAH Regulations) will apply to your proposals and wish to
provide the regulatory advice detailed below. If you have any queries on the
COMAH process, please email wasteandindustry@sepa.org.uk  
Page 274

Page 275

• SEPA is aware of the existing Grissan lower tier COMAH establishment
located nearby at the Portgordon Maltings, Buckie, Moray, AB56 5BU and
the associated Hazardous Substance Consent application 22/01401/HAZ
which is under determination. We recommend you ascertain whether the
proposed development lies within a consultation distance set by HSE around
a major hazard site and if it does, understand whether or how this could
affect your layout. Perhaps this consultation has already been undertaken
but we felt it best to bring this point to your attention. 
• As the Regulations will apply, the Applicant must notify the COMAH
Competent Authority (HSE and SEPA) within a reasonable period of time
(normally taken to be between 3 and 6 months) prior to construction of the
proposed development. At that time, the anticipated COMAH status of the
site as a lower or upper tier establishment should be confirmed by providing
a comparison of the proposed quantity of flammable substances to be stored
against the qualifying thresholds described in Schedule 1 of the Regulations. 
• Details of how to make a COMAH notification are available on the HSE
website. 
• Following notification, SEPA will expect the Applicant to submit an
assessment of the environmental risks, demonstrating that ‘All Measures
Necessary’ have been undertaken in relation to the potential for ‘Major
Accidents to the Environment’. The latest version of the guidance for
undertaking such an assessment can be found on SEPA’s website. The
assessment submitted will need to include details of the procedural, design,
and modelling arrangements proposed to address environmental risk and
mitigate the potential impacts of a major accident to the environment. If the
site is identified as upper tier under the COMAH Regulations then the
environmental risk assessment will need to be submitted as part of a Safety
Report for the establishment. 
• It is noted & welcomed that the proposed drainage system includes
provisions for firewater containment. SEPA intend to contact the drainage
consultants Blyth and Blyth directly to clarify certain points surrounding these
proposals. 
• The applicant should contact the local authority to discuss the need for a
Hazardous Substances Consent. SEPA & HSE would expect to be consulted
on any such application which is made. 
SCOTTISH GAS NETWORKS have commented that:- 
Please note that the pipeline in the vicinity of the proposed development is a
Major Accident Hazard Pipeline in terms of the Pipelines Safety Regulations
1996. Please note the HSE guidance document L82:A Guide to the Pipelines
Safety Regulations 1996, (http://www.hse.gov.uk/pubns/books/l82.htm), in
particular the guidance on safety regulations 15 and 16 and the emergency plan
under Regulation 25. 
Page 275

Page 276

In addition, please note your requirements under HSE Document: PADHI: HSE’s
Land Use Planning Methodology (www.hse.gov.uk/landuseplanning/padhi.pdf)
for any major accident hazard pipeline. 
This pipeline is also legally protected by a Deed of Servitude which restricts
building and other works within the servitude area (as described in the deed). 
LIST OF PLANS AND DRAWINGS SHOWING THE DEVELOPMENT
Reference No. Version
No.
Title/Description
D01  East elevation long section 1
D02  East elevation long section 2
L01  H Landscape mitigation plan - LVIA Figure 4 updated 
EC22743:PL:014  Cell 12 warehouse - elevations and floor plan
EC22743:PL:015  16 Cell warehouse - elevations and floor plan
EC22743:PL:006  8 Cell warehouse - elevations and floor plan
EC22743:PL:010  Typical civils construction details sheet 1
EC22743:PL:011  Amenity building - elevations and floor plan
EC22743:PL:012  Sprinkler tanks and pumphouse elevations and floor plans
EC22743:PL:013  Substation - elevations and floor plan 
L02  C Planting plan
EC22743:PL:001   C Location plan
EC22743:PL:003   E Proposed site layout
EC22743:PL:004   D General arrangement
EC22743:PL:005   B Proposed site sections
EC22743:PL:009   C Proposed drainage layout 
Information to accompany decision:  
Drainage Impact Assessment G:\C&S\EC22743\reports\R001 Drainage Impact
Assessment Rev B.docx, dated 29/11/22, prepared by Blyth and Blyth.  
Page 276

Page 277

Plans, drawings and other material submitted to the local authority
are protected by the Copyright, Designs and Patents Act 1988
(section 47). You may only use material which is downloaded and/
or printed for consultation purposes, to compare current
applications with previous schemes and to check whether
developments have been completed in accordance with approved
plans.
Further copies must not be made without the prior permission of
the copyright owner.
Maps shown in the Planning Committee Report can only be used
for the purposes of the Planning Committee. Any other use risks
infringing Crown Copyright and may lead to prosecution or civil
proceedings. Maps produced within this Planning Committee
Report can only be reproduced with the express permission of the
Moray Council and other Copyright holders. This permission must
be granted in advance.
PLANNING APPLICATION
COMMITTEE SITE PLAN
Site Address:
Land To The South Of Crisp Maltings
Portgordon
Planning Application Ref Number: 
22/01269/APP 
Location Plan
Applicant Name: 
William Grant & Sons Distillers Ltd
Page 277

Page 278

Site Location
Page 278

Page 279

General arrangement
16/
Page 279

Page 280

Landscape plan
16/01664/APP
Page 280

Page 281

Page 281

Page 282

Page 282

Page 283

Page 283

Page 284

Page 284

Page 285

Page 285

Page 286

Site from South East
Page 286

Page 287

PLANNING APPLICATION: 22/01269/APP 
In the event that a recommendation on this planning application is overturned the
Committee is reminded of the advice contained on the front page of the agenda for
Reports on Applications 
1. THE PROPOSAL 
   Planning permission is sought for the erection of 4 whisky storage
warehouses, associated access, drainage, landscaping and diversion of
the Core Burn.   
   The site extends to 16 hectares, with the total footprint of the warehouses
being 50,000sqm.  
   Each warehouse is split into cells, with each individual cell measuring 37m
by 28m and 13.2m in height.  Each cell has a shallow pitched roof, with
the walls being finished in a mixture of dark green cladding on the upper
portion, with harled base walls and the roof also finished in dark green
cladding.  Each cell also has a roller/pedestrian door and pump house on
the gable elevation.  The differing size buildings will contain 8, 12 and 16
cells.
   Further elements of the proposal consist of a flat roof modular amenities
building (office, kitchen, drying room & toilets) measuring 10m by 9m, by
2.6 high finished in dark green.  Two sprinkler storage tanks with a 5.5m
diameter and 6.5m in height and associated flat roof pump house
measuring 8m by 7m by 3.3m high. A flat roof substation measuring 10m
by 4.5m by 3m high.  
   Access is proposed via the existing road which serves the neighbouring
maltings and anaerobic digestion plants.  
   The proposal also involves the realignment of the Core Burn which
presently flows along a ditch to the south of the site.  The applicants
propose to divert this further south within the site and incorporate this
within the wetland/pond also proposed to the south of the site. 
   4 hectares of the site is set aside for landscaping with a 20m wide band of
coniferous trees proposed to the north of the site, a further band of
coniferous trees varying in width up to 35m wide to the east of the site.  A
band of broadleaf planting is proposed to the west of the site, varying in
width from 10m to 20m wide and supplements the existing woodland
bounding the site on this side.  To the south of the site lies the wetland
area, which varies in width from 42m to 100m and incorporates a block of
broadleaf planting varying in width from 8m to 63m wide. Between the
coniferous and broadleaf woodland planting proposed, this will equate to
approx. 25,000 trees planted.   
Page 287

Page 288

2.  THE SITE 
• The site lies to the south of the Crisp Maltings at Portgordon and presently
comprises agricultural land, with the Core Burn flowing within a ditch
towards the south of the site.  
• The site is bounded by the existing woodland and anaerobic digestion
plant to the west, further open farmland with neighbouring houses beyond
to the south and the A990 public road to the east. 
• There are no environmental or landscape designations covering the site
and the site is defined within the Local Development Plan as open
countryside and is not covered by any specific designations within the
plan.  Approximately 4 hectares of the south eastern corner of the site is
identified as being prime agricultural land (3.1 classification).  
• A section of the western portion of the site is affected by both surface
water flood risk and flood risk associated with the Core Burn.  
• The site also contains a high pressure gas pipeline, which runs along a
corridor to the north of the site. 
3.  HISTORY 
22/00632/SCN – Environmental impact assessment screening opinion issued
confirming that this proposal does not constitute EIA development.   
22/00631/PAN – Proposal of Application Notice for erection of warehouses (up
to 50,000sqm) land engineering (cut and fill) realignment of Core Burn and
associated engineering and infrastructure works on land to South of Crisp
Maltings, Buckie. Response dated 6 May 2022 confirmed consultation
arrangements and publicity event to be acceptable. 
4.  POLICY - SEE APPENDIX 
5.  ADVERTISEMENTS 
5.1  Advertised for neighbour notification purposes. 
6.  CONSULTATIONS 
Contaminated Land – No objections. 
Scottish Water – No objections.   
Transportation Manager – No objection subject to conditions and informatives
being attached to the consent. The conditions relate to formation of visibility
splays, wear and tear agreement, a construction traffic management plan and
provision of EV charging. 
Page 288

Page 289

Archaeology – No objections, subject to condition relating to archaeological
investigation and recording of any finds.  Archaeological investigation is
ongoing on the site at present.    
SEPA – No objections subject to a condition relating to the design of the Core
Burn realignment. Informative attached regarding other SEPA regulatory
aspects. 
Moray Flood Risk Management – No objections subject to condition relating
to adherence with the submitted Drainage Impact Assessment. 
Environmental Health – No objections subject to conditions relating to
constructions activity, operating hours, site lighting, construction environmental
management plan and operational noise limits.    
Health and Safety Executive – No objections. 
Scottish Gas Networks – No objection subject to informatives.   
Strategic Planning & Delivery – Comments provided in relation to locational
justification of the site, landscaping and visual impact.   
7.  OBJECTIONS-REPRESENTATIONS 
NOTE: Following the determination of this application, name and address
details will be/have been removed (i.e. redacted) in accordance with the
General Data Protection Regulations (paragraph 3 of Minute, Planning &
Regulatory Services Committee 16 September 2014). 
6 representations have been received. 
All objections/representations have been read and where material, given the
appropriate consideration prior to the decision reached. 
Headings of objection reasons selected by objectors from objection/
representation from the online objection page: 
   Affecting natural environment
   Contrary to Local Plan
   Drainage
   Height of proposed development
   Inappropriate materials/finishes
   Lack of landscaping
Page 289

Page 290

   Noise
   Over-development of site
   Poor design
   Procedures not followed correctly
   Traffic
   Road access
   Road safety
   Over-development of site
   Precedent
   Community Council/Association Consult
   View affected  
The grounds for representation are summarised as follows: 
Issue: Environmental Impact Assessment.
   Moray Planning have not asked for an EIA [environmental impact
assessment] for the development especially as this site bounds the
Coastal Special Landscape Area [SLA] which is part of the important
Moray Coastal strip both important visually and environmentally as a
sensitive unique coastal environment - Portgordon is home to a significant
wildlife population, not only the Grey Seal colony for which human activity
is the major threat.
   The scale of the storage/warehousing development will have a significant
and complex adverse environmental impact. No formal Environmental
Impact Analysis has been prepared and it is of concern that Moray
Council has decided that this is not required on the basis of the scale of
development. The wider Moray Firth has a number of national
designations including Special Protection Area, Special Landscape Area,
SSSI & RAMSAR and therefore the wider environmental impact and
impact on local biodiversity has not been seriously considered.
Comment (PO): The Special Landscape Area designation lies to the north of
Portgordon and covers the coastal fringe, it does not bound the site. 
The decision reached on the EIA screening opinion followed pre application
consultation with NatureScot and SEPA amongst others who did not raise any
concerns regarding the potential environmental impact of the proposal.  The
site is remote from the Moray Firth and taking into account the nature of the
proposals, will not result in any direct impact on the environmental interests of
the firth. The Core Burn has already been significantly altered via human
intervention. 
An ecology appraisal has been submitted in support of the application which
identifies that the proposal will not have any adverse impact on designated
environmental sites or protected species and the wetland area should result in
significant habitat enhancement for surrounding wildlife.   
Issue: Visual Impact.
   Adopted Moray Planning Local Plan policy documents distinctly refer to
the protected landscape in relation to uninterrupted views to the Cullen
Bin from all aspects along the coast.
Page 290

Page 291

   Locally the visual impact of these huge warehouses is proposed with
insignificant mitigation to reduce their presence in the open nature of the
local landscape.
   Promoting a location close to the existing Maltings & biomass facility
means that a 'tipping point' is reached that completely changes the
landscape, setting and character of this approach on the A990 to
Portgordon from the south.
   The scale, massing, density and volume of the four warehouse buildings
of around 50,000sqm (equivalent to 7 full size football pitches) with 13m
ridge heights is not in keeping with the local largely rural character, will
adversely affect the local landscape and have a significant detrimental
visual and environmental impact. The first visual impression on
approaching Portgordon on the A990 the south will be of an industrial
park. The design of the buildings is poor, very functional and does not
integrate into the landscape.
   This proposed scheme is the size of an Amazon Fulfilment centre on the
doorstep of a community of less than 900 residents. There is potential for
a serious negative impact on community amenity, the quality of life and
environment locally along with the erosion of key assets in this
neighbourhood. The visual impact of these huge warehouses is proposed
with insignificant mitigation to reduce their presence in the open nature of
the local landscape.
Comment (PO): The visual impact and design of the proposals are considered
in the observations section of this report, whereby it is concluded that whilst the
proposals will be visible within the local landscape, this does not merit the
refusal of the application.   
As with most maturation warehousing found throughout Moray, the design of
the buildings are functional, however, such buildings are an existing common
feature throughout the Moray landscape and as such are not considered to
incongruous with the established working character of the rural landscape.
Whisky maturation warehousing is not uncommon in the wider locality with
whisky warehousing present to the east at Inchgower Distillery. 
Taking into account the separation between the site and the Bin of Cullen, the
proposals are not considered to have any adverse impact on the setting of this
local landmark.   
Issue: Prime Agricultural land.
   Loss of prime quality farmland, and the impact this has on current tenants,
which goes against adopted Planning and environmental policy.
Comment (PO): This issue is discussed in the observation section of this
report whereby it is concluded that the loss of the Prime Agricultural Land does
not merit the refusal of the application.   
Issue: Road Safety.
   Increase in heavy traffic movements of commercial vehicles into the long
term, the A98 is already a high incident corridor, with frequent local
catastrophic accidents - the lack of infrastructure investment for this
development would impact on local safety with the A990 feeder road to
Portgordon and day to day amenities.
Page 291

Page 292

   Road infrastructure is not adequate into and out of proposed site. As you
know the A98/96 can be closed on a regular basis due to the amount of
accidents that occur, this would mean even more large vehicles coming
through the village at speed.
   The Transport Statement underplays the negative safety impact of
increase in heavy traffic movements of commercial vehicles on the
B9016/A98/A990 junction, which is already a difficult junction.
Comment (PO): The applicants have confirmed that HGV traffic from the
operation of the development will not be routed through Portgordon.   
The Councils Transportation Manager have assessed the road infrastructure
serving the site and subject to conditions as recommended, have no objection
to the approval of the application.  Of note, once operational and the
warehouses are stocked, the number of vehicles movements will be limited. 
Issue: Outfall to Moray Firth causing pollution.
Comment (PO): There is no outfall to the Moray Firth proposed as part of this
development.   
Issue: Future Development.
   Fear of future development on this site of over 200 hectares with an
unknown agenda by the greater WM Grants ownership and associated
business operations within their related holding companies.
Comment (PO): This application must be assessed on its own merits.  Any
application for future development will need to be assessed in accordance with
the Local Development Plan policies in place at that time and taking into
account any other relevant material considerations.   
Issue: Lack of investment in a sustainable local employment infrastructure. We
need future planning for a symbiotic relationship with communities of
Fochabers, Portgordon and Buckie - to local benefit.
Comment (PO): The principles of community wealth building have been
incorporated into the draft national Planning Framework 4, however, this is yet
to be adopted by Scottish Ministers and as such this proposal must be
considered in accordance with current Moray Development Plan policy, where
community wealth building is not incorporated into policy.  The proposals have
been assessed in terms of development obligations however, no contributions
were identified.   
Issue: Loss of environmental and wildlife diversity, even though this is currently
farmland - the micro diversity is lost forever, with concreting over large areas.
Comment (PO): The habitat enhancements proposed as a result of this
development are considered to result in a considerable net gain over the
habitat value offered by the existing farmland.   
Issue: Drainage and flood risk.
   Loss of natural groundwater percolation and the fears of uncontrolled
flooding due to stormwater run-off, Portgordon has previously suffered
from storm floods off the open farmland.
   The impact on groundwater levels/percolation and the impact of run off
from the buildings & hard standings in heavy rain brings immediate
concerns about flooding due to stormwater run-off. Portgordon has
Page 292

Page 293

already suffered from significant storm floods including from the open
farmland in 1999 & 2013.
Comment (PO): The Drainage Impact Assessment and Flood Risk
Assessment submitted in support of this application identify that the proposal
will not result any greater flood risk as a result of the proposals.  Both SEPA
and Moray Flood Risk Management have been consulted on the proposals and
have no objection to the approval of the application subject to the conditions as
recommended. 
Issue: Design.
   These buildings are of the lowest denominator of build/investment cost,
barely a 20th Century envelope let alone one suitable for the 21st C and
beyond - modern day expectation is for development to 'build back better',
green roofing, solar PV roofing, buried structures, highly insulated shells,
rainwater/grey water harvesting, sustainable local materials, low
embodied carbon build methods - and appropriate visual style to this area
of small historic residential coastal settlements.
Comment (PO): The development must be assessed on the basis on which it
is submitted and there is no development plan policy basis to insist that a
different approach to the design of a functional warehouse.   
Issue: Principle of Development.
The site selection analysis in the Planning Statement is superficial. Only two
other locations are considered and an alternative option of a distributed location
strategy with a number of smaller more resilient facilities has not been
examined. On the basis that Scotch Whisky is very important in the national &
Moray economy, Moray Council should be proactive in identifying potential
locations, other than mainstream industrial sites, as part of the Local
Development Plan for this kind of facility.
Comment (PO): There is no development plan policy requirement to detail
other sites considered as part of planning application.  The proposal must be
assessed on the basis on which it is submitted.  Whilst the Moray Local
Development Plan does not designate specific sites for maturation
warehousing, it is supportive of growing the whisky industry and has policies for
the consideration of rural businesses/development. The Moray Economic
Strategy does support traditional industries in Moray and the location of
warehousing is often industry led, due to their wish to operational need. 
8.  OBSERVATIONS 
8.1  Following consideration of the revised draft National Planning Framework 4
which was laid before parliament on 8th November 2022, the draft (yet to be
formally adopted) is to be given no weight in the consideration of planning
applications. Section 25 of the 1997 Act as amended requires applications to
be determined in accordance with the development plan i.e. the adopted Moray
Local Development Plan 2020 (MLDP) unless material considerations indicate
otherwise. The main planning issues are considered below: 
8.2  Principle, Siting/Character and Design (PP2, DP1, DP5) 
Policy PP2 Sustainable Economic Growth supports proposals which deliver
sustainable economic growth where the natural and built environment is
Page 293

Page 294

safeguarded, there is clear locational need and any potential impacts can be
satisfactorily mitigated. 
8.2.1 Policy DP1 Development Principles, sets out detailed criteria to ensure
development proposals satisfy siting, design and servicing requirements. This
also requires submission of supporting information to inform assessment where
required. 
8.2.2 Policy DP5 Business and Industry states proposals for new business
development and extensions to existing businesses in rural locations including
tourism and distillery operations will be supported where there is a locational
need and is of a high standard of design appropriate to the rural environment. 
8.2.3 The applicants have submitted a planning statement in support of the proposals
which details the rationale behind the selection of the proposed site.  In brief
this highlights that there is currently a shortage of whisky storage within Moray
and that without storage facilities, production and expansion of the industry in
the area will not be possible.  This proposal represents a significant investment
in whisky storage in the area, which will enable the expansion of a Key Growth
Sector as identified within the Moray Economic Strategy.  Whilst other sites
were considered, the proposed site was identified as being the most suitable in
that it is within Speyside, which is desirable in terms of product provenance, it is
close to distilling operations i.e. within 20 miles of Dufftown and saves transport
and storage of the whisky elsewhere within Scotland. The roads serving the site
are of a sufficient standard to accommodate the associated HGV traffic.  The
site is relatively flat and avoids the need for significant regrading associated
with the proposals.  The development will be viewed in conjunction with the
existing adjacent maltings and anaerobic digestion (AD) plant and is therefore
being sited in what is already a working landscape.  There are no landscape or
environmental designations associated with the site.  The applicants have a
commercial relationship with Grissan Renewable Energy, who built and operate
the adjacent AD plant, where the newest phase of the development being
progressed involves the production of biomethane, whereby in time both the
diesel trucks serving the AD plant and those serving the proposed maturation
warehouse will be replaced by biomethane trucks. This will result in a huge
carbon saving when compared to existing diesel truck movements and is an
excellent example of a circular economy, whereby the waste products from the
distilling industry are used to provide biomethane and the waste from the AD
process is used as fertiliser to help grow crops which are used in the whisky
industry and the circular cycle continues.   
8.2.4 In addition to the above the applicants have also outlined that it would not be
suitable to locate the maturation warehousing on a site designated for industrial
purposes within the development plan, as it would not be possible to find a
designated site large enough to accommodate the applicants needs and even if
a large enough site was found given the health and safety requirements
associated with maturation warehousing it would be likely that there would be a
conflict of uses between the maturation warehousing and other industrial uses. 
Also the siting of maturation warehousing on designated industrial land would
have a sterilising effect on what would otherwise be flexible industrial land
capable of meeting the needs of other industrial businesses in the area.   
Page 294

Page 295

8.2.5 With all of the above in mind there is considered to be ample justification to
meet the locational requirements of policies PP2 and DP5.   
8.2.6 In terms of siting, design and potential impact on the character of the area,
given the scale of the proposal it will inevitably be highly visible within the local
landscape.  The applicants have submitted a landscape and visual appraisal in
support of the general development which includes visualisations to aid the
understanding of the likely visual impact of the proposals.   
8.2.7 From a review of this landscape and visual assessment and having visited the
site, as noted previously in terms of locational justification, the site is located in
a part of the landscape which is already characterised by its working nature. 
Other maturation warehouses are present in relatively close proximity to the
site (3km east at Inchgower distillery), the adjacent Crisp Maltings and
neighbouring AD plant already have a strong influence on the landscape along
with the industrial development in and around Buckie, which is visible across
the coastal fringe.  When looking at Moray as a whole there are numerous
maturation warehouses located throughout the landscape and therefore whilst
the proposal will be visible it will not be incongruous with the landscape.   
8.2.8 When looking more closely at the characteristics of the site in detail, the site is
relatively flat and will require minimal earthworks to accommodate the proposal
again limiting the visual potential visual impact of the proposal.  The
visualisations and long section provided in support of the application illustrate
how the site sits within a low point within the landscape and when taking into
account undulations and existing woodland in the wider landscape the visual
impact of the proposals will be localised. The visual impact of the scheme will
be mitigated further by the dark green colouration of the buildings and the
woodland planting proposed around the site.  Whilst it is accepted that this
woodland will take time to become effective, it will help soften the impact of the
proposal in the medium term.   
8.2.9 In terms of impact of the nearest residential properties, there is considered to
be sufficient separation between the proposal and these properties to ensure
the development does not result in an overbearing impact and whilst the views
from these properties may be affected, in planning terms, the right to a view is
not a material planning consideration and therefore cannot be taken into
account in determining this proposal.   
8.2.10 Overall whilst the proposal will inevitably result in visual impact, taking all of the
above factors into account, the site is considered to be well located to
accommodate such a large development and balances the need to provide
maturation storage facilities within Moray to enable the growth of the whisky
industry with the need to protect the established character of the countryside in
which the proposal is sited.   
8.3 Drainage and Flooding (DP1, PP3, EP12 & EP13) 
Policies DP1 Development Principles, PP3 Infrastructure and Services and
EP12 Management and Enhancement of the Water Environment set out
detailed criteria to ensure proposals meet siting, design and servicing
requirements including provision of SuDS. This includes requirements for
surface water from new development to be dealt with in a sustainable manner
Page 295

Page 296

that has a neutral effect on the risk of flooding or which reduces the risk of
flooding. 
8.3.1 A Drainage Impact Assessment and Flood Risk Assessment has been
submitted with the application which details the proposed surface drainage
arrangements for the proposed development.  Two large SUDs basins are
proposed to the south west of the site and have been incorporated into a larger
landscaped area.  The SUDs basins will be edged with a wetland fringe
planting scheme which will then be bounded by meadow or woodland planting.   
In this case the applicant propose to realign the Core Burn as part of the
proposals.  The natural path of the Core Burn has been altered for many years,
where historically the Burn has been ditched and its natural course lost.  With
this in mind the realignment and integration of the burn as part of the proposed
wetland area is encouraged and will result in a net enhancement of the natural
habitat value across this site.   
8.3.2 Following consultation with Scottish Water it has been identified that there are
no foul sewers in the vicinity of the site and therefore the applicants have
outlined within the drainage statement that a biodisc treatment plant will be
incorporated into the site along with appropriate discharge to a soakaway.  A
condition has been recommended to agree the full details of this system prior to
development commencing.   
8.3.3 Both SEPA and Moray Flood Risk Management have been consulted on the
proposals and have no objection to the approval of the application subject to
the conditions as recommended.  With this in mind the proposals are
considered compliant with policies DP1, PP3, EP12 and EP13.   
8.4 Biodiversity and Prime Agricultural Land (EP2 and DP1) 
Policy EP2 requires development proposals to, where possible, retain, protect
and enhance all biological interest and provide for their appropriate
management. This also states that proposals for 1000sqm or more of
commercial floorspace must create new or where appropriate enhance natural
habitats of ecological value. 
8.4.1 Given the current use of the site for agricultural purposes it presently has
limited habitat and biodiversity value and this is reflected within the findings of
the ecology survey submitted in support of the application.  As outlined within
the previous drainage section, the applicants propose to create a wetland area,
integrating the Core Burn and incorporating a pond.  Approximately 4 hectares
of the 16 hectare site have been given over to landscaping with around 25,000
trees being proposed as part of the landscape scheme.  The landscape
scheme also incorporates, wetland planting and two separate types of
meadowland mix planting to enhance variety and habitat value across the site. 
The creation of the pond to the south of the site also opens up an excellent
opportunity to incorporate bat and bird boxes on the warehouse buildings,
providing an ideal foraging habitat and the applicants have incorporated this
into the scheme.   
8.4.2 Taking the above into account the proposals are compliant with policy EP2. 
Page 296

Page 297

8.4.3 In terms of impact on Prime Agricultural Land, policy DP1 outlines that the
proposals must avoid sterilising significant workable reserves of Prime
Agricultural Land.  In this case the proposals involve the loss of approx. 4
hectares of 3.1 classification Prime Agricultural Land, within the south east
corner of the site.  No definition of “significant” is provided within the
development plan, however, it is questionable as to whether the loss of 4
hectares of Prime Agricultural Land is significant when it lies within a wider area
of prime agricultural land extending to over 830 hectares.  In addition, to insist
that no development takes place within this corner of the site, would result in a
corner of a field bounded by the public road to the east and split in two by the
Core Burn with the remainder of the field being developed and as such this
remaining corner would not be considered to constitute significant workable
reserves of Prime Agricultural Land.  Whilst the loss of any Prime Agricultural
Land is undesirable, in this instance the losses associated with the proposals
are not considered to outweigh the benefits of this proposal.   
8.5 Access and Parking (DP1 and PP3) 
Policy DP1 requires that proposals must provide a safe entry and exit from the
development and conform with the Council’s current policy on Parking
Standards. Policy PP3 requires development to be planned and co-ordinated
with infrastructure to ensure that places function properly and proposals are
adequately served by infrastructure and services. 
8.5.1 A Transport Statement has been submitted in support of the proposals and the
Transportation Section has been consulted and has raised no objection to the
grant of permission subject to conditions relating to the formation of visibility
splays, a wear and tear agreement, a Construction Traffic Management Plan
and provision of EV charging.   
8.5.2 In terms of access and parking, subject to the conditions as recommended, the
proposal complies with policy DP1 and PP3. 
8.6 Pollution (Noise & light) (EP14) 
The Environmental Health Manager has assessed this information and has
raised no objection to the grant of permission subject to conditions controlling
operating hours, lighting, noise levels, construction work hours and submission
of a Construction Environmental Management Plan to control/manage
environmental emissions (noise, vibration, dust and artificial lighting) during the
construction phase. 
8.6.1 Subject to the compliance with above conditions the proposal would accord
with policy EP14. 
8.7 Developer Obligations (PP3)
The development has been the subject of a developer obligations assessment
in accordance with policy PP3, however, in this instance no developer
obligations have been identified.   
8.8 Archaeology (EP8)
A Written Scheme of Investigation has been submitted in support of this
application and the Regional Archaeologist has no objection to the approval of
the application subject to archaeological investigation of the site prior to
Page 297

Page 298

development commencing.  The applicants have elected to proceed with this on
site investigation prior to this application being determined and this is why the
northern portion of the site has the top soil removed at present.   
Conclusion
Whilst it is recognised, that the proposed development will be highly visible
within the local landscape, the development represents a significant investment
in whisky storage in the area, which will enable the expansion of a Key Growth
Sector as identified within the Moray Economic Strategy.  The location of this
storage within Moray has the potential to reduce the transportation miles of
whisky casks significantly, when compared to the potential storage of casks in
central Scotland and this coupled with the siting of the proposal adjacent to the
approved biomethane fuelling station will enable the applicants to convert to the
use of biomethane HGV’s, overall resulting in very significant carbon savings. 
The incorporation of 4 hectares of landscaped areas, including the wetland
area and woodlands, resulting in the planting of 25,000 trees, will result in a net
habitat value gain when compared to the present use of the site for farmland. 
Taking these factors into account the benefits of the proposal are consider to
outweigh any visual impact and as such the application is recommended for
approval.     
REASON(S) FOR DECISION 
The Council’s reason(s) for making this decision are: - 
The erection of buildings for whisky storage in this location is considered
acceptable and would not have an adverse impact on the surrounding area.
The proposal complies with the provisions of the development plan and there
are no material considerations that indicate otherwise. 
Author/Contact
Officer:
Iain T Drummond          
Planning Officer
Ext: 01343 563607 
Beverly Smith
Development Management & Building Standards Manager
Page 298

Page 299

APPENDIX 
POLICY 
Moray Local Development Plan 2020
PP1 PLACEMAKING 
a) Development must be designed to create successful, healthy places that support
good physical and mental health, help reduce health inequalities, improve people's
wellbeing, safeguard the environment and support economic development.   
b) A Placemaking Statement is required for residential developments of 10 units and
above to be submitted with the planning application to articulate how the
development proposal addresses the requirements of policy PP1 Placemaking and
other relevant LDP policies and guidance.  The Placemaking Statement must include
sufficient information for the council to carry out a Quality Audit.  Where considered
appropriate by the council, taking account of the nature and scale of the proposed
development and of the site circumstances, this shall include a landscaping plan, a
topographical survey, slope analysis, site sections, 3D visualisations, a Street
Engineering Review and a Biodiversity Plan.  The Placemaking Statement must
demonstrate how the development promotes opportunities for healthy living and
working. The landscape plan must set out details of species type, size, timescales for
planting and maintenance. 
c) To create successful, healthy places residential developments of 10 units and above
must comply with Scottish Government policy Creating Places and Designing Streets
and must incorporate the following fundamental principles: 
(i) Character and Identity
• Create places that are distinctive to prevent homogenous 'anywhere'
development;
• Provide a number of character areas reflecting site characteristics that
have their own distinctive identity and are clearly distinguishable;
• Provide distinctiveness between and in each character area through a
combination of measures including variation in urban form, street
structure/network, architecture and masonry, accent features (such as
porches), surrounds and detailing, materials (buildings and surfaces),
colour, boundary treatments, hard/soft landscaping and a variety of
approaches to tree species and planting that emphasises the hierarchy of
open spaces and streets within a cohesive design strategy for the whole
development;
• Distinctiveness must be reinforced along main thoroughfares, open
spaces and places where people may congregate such as
shopping/service centres;
• Retain, incorporate and/or respond to relevant elements of the landscape
such as topography and planted features, natural and historic
environment, and propose street naming (in residential developments of
20 units and above, where proposed names are to be submitted with the
planning application) to retain and enhance local associations; 
Page 299

Page 300

(ii) Healthier, Safer Environments
• Designed to prevent crime, fear of crime and anti-social behaviour with
good levels of natural surveillance and security using treatments such as
low boundary walls, dual frontages (principal rooms) and well-lit routes to
encourage social interaction.  Unbroken high boundary treatments such
as wooden fencing and blank gables onto routes, open spaces and
communal areas will not be acceptable.
• Designed to encourage physical exercise for people of all abilities.
• Create a distinctive urban form with landmarks, key buildings, vistas,
gateways and public art to provide good orientation and navigation
through the development.
• Provide a mix of compatible uses, where indicated within settlement
statements, integrated into the fabric of buildings within the street.
• Prioritise pedestrians and cyclists by providing a permeable movement
framework that incorporates desire lines (including connecting to and
upgrading existing desire lines) and is fully integrated with the surrounding
network to create walkable neighbourhoods and encourage physical
activity.
• Integrate multi- functional active travel routes, green and open space into
layout and design, to create well connected places that encourage
physical activity, provide attractive spaces for people to interact and to
connect with nature.
• Create safe streets that influence driver behaviour to reduce vehicle
speeds that are appropriate to the local context such as through shorter
streets, reduced visibility and varying the building line.
• Provide seating opportunities within streets, paths and open spaces for all
generations and mobility's to interact, participate in activity, and rest and
reflect.
• Provide for people with mobility problems or a disability to access
buildings, places and open spaces.
• Create development with public fronts and private backs. 
• Maximise environmental benefits through the orientation of buildings,
streets and open space to maximise the health benefits associated with
solar gain and wind shelter. 
(iii) Housing Mix
• Provide a wide range of well integrated tenures, including a range of
house types and plot sizes for different household sizes, incomes and
generations and meet the affordable and accessible requirements of
policy DP2 Housing.
• All tenures of housing should have equal access to amenities, greenspace
and active travel routes. 
(iv) Open Spaces/Landscaping
• Provide accessible, multi-functional open space within a clearly defined
hierarchy integrated into the development and connected via an active
travel network of  green/blue corridors that are fully incorporated into the
development and to the surrounding area, and meet the requirements of
policy EP5 Open Space and the Open Space Strategy Supplementary
Guidance and Policy EP12 Managing the Water Environment and
Drainage Impact Assessment for New Developments Supplementary
Guidance.
Page 300

Page 301

• Landscaped areas must provide seasonal variation, (mix of planting and
colour) including native planting for pollination and food production.
• Landscaping areas that because of their size, shape or location would not
form any useable space or that will not positively contribute to the
character of an area will not contribute to the open space requirements of
Policy EP4 Open Space.
• Semi-mature tree planting and shrubs must be provided along all routes
with the variety of approaches reflecting and accentuating the street
hierarchy.
• Public and private space must be clearly defined.
• Play areas (where identified) must be inclusive, providing equipment so
the facility is for every child/young person regardless of ability and
provided upon completion of 50% of the character area.
• Proposals must provide advance landscaping identified in site
designations and meet the quality requirements of policy EP5 Open
Space.
• Structural landscaping must incorporate countryside style paths (such as
bound or compacted gravel) with waymarkers.
•  Maintenance arrangements for all paths, trees, hedging, shrubs, play/
sports areas, roundabouts and other open/ green spaces and blue/green
corridors must be provided. 
v) Biodiversity
• Create a variety of high quality multi- functional green/blue spaces and
networks that connect people and nature, that include trees, hedges and
planting to enhance biodiversity and support habitats/wildlife and comply
with policy EP2 Biodiversity and Geodiversity and EP5 Open Space.
• A plan detailing how different elements of the development will contribute
to supporting biodiversity must be included in the design statement
submitted with the planning application.
• Integrate green and blue infrastructure such as swales, permeable paving,
SUDS ponds, green roofs and walls and grass/wildflower verges into
streets, parking areas and plots to sustainably address drainage and
flooding issues and enhance biodiversity from the outset of the
development.
• Developments must safeguard and where physically possible extend or
enhance wildlife corridors and green/blue networks and prevent
fragmentation of existing habitats. 
(vi) Parking
• Car parking must not dominate the streetscape to the front or rear of
properties.  On all streets a minimum of 50% of car parking must be
provided to the side or rear and behind the building line with a maximum
of 50% car parking within the front curtilage or on street, subject to the
visual impact being mitigated by hedging, low stone boundary walls or
other acceptable treatments that enhance the streetscape.
• Provide semi-mature trees and planting within communal private and
public/visitor parking areas and on-street parking at a maximum interval of
4 car parking spaces.
• Secure and covered cycle parking and storage, car sharing spaces and
electric car charging points must be provided in accordance with policy
DP1 Development Principles.
Page 301

Page 302

• Parking areas must use a variation in materials to reduce the visual
impact on the streetscene. 
(vii) Street Layout and Detail
• Provide a clear hierarchy of streets reinforced through street width,
building density and street and building design, materials, hard/soft
landscaping and a variety of approaches to tree planting and shrubs.
• Streets and connecting routes should encourage walking and cycling over
use of the private car by providing well connected, safe and appealing
routes.
• Design junctions to prioritise pedestrians, accommodate active travel and
public transport and service/emergency vehicles to reflect the context and
urban form and ensure that the street pattern is not standardised.  
• Dead-end streets/cul-de-sacs will only be selectively permitted such as on
rural edges or where topography, site size, shape or relationship to
adjacent developments prevent an alternative more permeable layout.
These must be short, serving no more than 10 units and provide walking
and cycling through routes to maximise connectivity to the surrounding
area.
• Where a roundabout forms a gateway into, or a landmark within, a town
and/or a development, it must be designed to create a gateway feature or
to contribute positively to the character of the area.
• Design principles for street layouts must be informed by a Street
Engineering Review (SER) and align with Roads Construction Consent
(RCC) to provide certainty that the development will be delivered as per
the planning consent. 
(d) Future masterplans will be prepared through collaborative working and in partnership
between the developer and the council for Lochyhill (Forres), Barhill Road (Buckie),
Elgin Town Centre/Cooper Park, Elgin North East, Clarkly Hill, Burghead and West
Mosstodloch.  Masterplans that are not prepared collaboratively and in partnership
with the council will not be supported.  Masterplans that are approved will be
Supplementary Guidance to the Plan.¬¬¬ 
(e) Proposals for sites must reflect the key design principles and safeguard or enhance
the green networks set out in the Proposals Maps and Settlement Statements. 
Alternative design solutions may be proposed where justification is provided to the
planning authority's satisfaction to merit this. 
PP2  SUSTAINABLE ECONOMIC GROWTH
Development proposals which support the Moray Economic Strategy to deliver
sustainable economic growth will be supported where the quality of the natural and built
environment is safeguarded, there is a clear locational need and all potential impacts can
be satisfactorily mitigated. 
PP3  INFRASTRUCTURE & SERVICES
Development must be planned and co-ordinated with infrastructure to ensure that places
function properly and proposals are adequately served by infrastructure and services.   
a) In relation to infrastructure and services developments will be required to provide the
following as may be considered appropriate by the planning authority, unless these
requirements are considered not to be necessary:
Page 302

Page 303

i)  Education, Health, Transport, Sports and Recreation and Access facilities in
accord with Supplementary Guidance on Developer Obligations and Open
Space. 
ii)  Green infrastructure and network requirements specified in policy EP5 Open
Space, Town and Village Maps and, contained within Supplementary Guidance
on the Open Space Strategy, Masterplans and Development Briefs. 
iii)  Mitigation/modification to the existing transport network (including road and rail)
to address the impact of the proposed development in terms of safety and
efficiency.  This may include but not be limited to passing places, road
widening, junction enhancement, bus stop infrastructure, and drainage
infrastructure.  A number of potential road and transport improvements are
identified and shown on the Town and Village Maps as Transport Proposals
(TSP's) including the interventions in the Elgin Transport Strategy. These
requirements are not exhaustive and do not pre-empt any measures which may
result from the Transport Assessment process. 
iv)  Electric car charging points must be provided at all commercial and community
parking facilities.  Access to charging points must also be provided for
residential properties, where in-curtilage facilities cannot be provided to any
individual residential property then access to communal charging facilities
should be made available.  Access to other nearby charging facilities will be
taken into consideration when identifying the need for communal electric
charging points. 
v)  Active Travel and Core Path requirements specified in the Council's Active
Travel Strategy and Core Path Plan. 
vi)  Safe transport and access routes linking to existing networks and mitigating the
impacts of development off-site. 
vii)  Information Communication Technology (ICT) and fibre optic broadband
connections for all premises unless justification is provided to substantiate it is
technically unfeasible. 
viii)  Foul and surface water drainage, including Sustainable Urban Drainage
Systems (SUDS), including construction phase SUDS. 
ix)  Measures that implement the waste management hierarchy as defined in the
Zero Waste Plan for Scotland including the provision of local waste storage and
recycling facilities designed into the development in accord with policy PP1
Placemaking.  For major applications a site waste management plan may be
required to ensure that waste minimisation is achieved during the construction
phase. 
x)  Infrastructure required to improve or increase capacity at Water Treatment
Works and Waste Water Treatment Works will be supported subject to
compliance with policy DP1. 
Page 303

Page 304

xi) A utilities plan setting out how existing and new utility (including gas, water,
electricity pipelines and pylons) provision has been incorporated into the layout
and design of the proposal.  This requirement may be exempted in relation to
developments where the council considers it might not be appropriate, such as
domestic or very small scale built developments and some changes of use. 
b)  Development proposals will not be supported where they:
i)  Create new accesses onto trunk roads and other main/key routes (A941 & A98)
unless significant economic benefits are demonstrated or such access is
required to facilitate development that supports the provisions of the
development plan. 
ii)  Adversely impact on active travel routes, core paths, rights of way, long
distance and other access routes and cannot be adequately mitigated by an
equivalent or better alternative provision in a location convenient for users. 
iii)  Adversely impact on blue/green infrastructure, including green networks
important for wildlife unless an equivalent or better alternative provision will be
provided. 
iv)  Are incompatible with key waste sites at Dallachy, Gollanfield, Moycroft and
Waterford and would prejudice their operation. 
v)  Adversely impact on community and recreational sites, buildings or
infrastructure including CF designations and cannot be adequately mitigated. 
vi)  Adversely impact on flood alleviation and mitigation infrastructure. 
vii)  Compromise the economic viability of bus or rail facilities.   
c)  Harbours 
Development within and diversification of harbours to support their sustainable
operation will be supported subject to compliance with other policies and settlement
statements. 
d)  Developer Obligations 
Developer obligations will be sought to mitigate any measurable adverse impact of a
development proposal on local infrastructure, including education, healthcare,
transport (including rail), sports and recreational facilities and access routes. 
Obligations will be sought to reduce, eliminate or compensate for this impact.
Developer obligations may also be sought to mitigate any adverse impacts of a
development, alone or cumulatively with other developments in the area, on the
natural environment. 
Where necessary obligations that can be secured satisfactorily by means of a
planning condition attached to planning permission will be done this way.  Where this
cannot be achieved, the required obligation will be secured through a planning
agreement in accordance with Circular 3/2012 on Planning Obligations.   
Developer obligations will be sought in accordance with the Council's Supplementary
Guidance on Developer Obligations.  This sets out the anticipated infrastructure
requirements, including methodology and rates.  
Page 304

Page 305

Where a developer considers that the application of developer obligations renders a
development commercially unviable a viability assessment and 'open-book
accounting' must be provided by the developer which Moray Council, via the District
Valuer, will verify, at the developer's expense.  Should this be deemed accurate then
the Council will enter into negotiation with the developer to determine a viable level
of developer obligations.   
The Council's Developer Obligations Supplementary Guidance provides further detail
to support this policy. 
DP1 DEVELOPMENT PRINCIPLES 
This policy applies to all development, including extensions and conversions and will be
applied reasonably taking into account the nature and scale of a proposal and individual
circumstances. 
The Council will require applicants to provide impact assessments in order to determine
the impact of a proposal. Applicants may be asked to determine the impacts upon the
environment, transport network, town centres, noise, air quality, landscape, trees, flood
risk, protected habitats and species, contaminated land, built heritage and archaeology
and provide mitigation to address these impacts. 
Development proposals will be supported if they conform to the relevant Local
Development Plan policies, proposals and additional guidance, meet the following criteria
and address their individual and cumulative impacts: 
(i) Design
a) The scale, density and character must be appropriate to the surrounding area
and create a sense of place (see Policy PP1) and support the principles of a
walkable neighbourhood. 
b) The development must be integrated into the surrounding landscape which will
include safeguarding existing trees and undertaking replacement planting to
include native trees for any existing trees that are felled, and safeguarding any
notable topographical features (e.g. distinctive knolls), stone walls and existing
water features by avoiding channel modifications and culverting. A tree survey
and tree protection plan must be provided with planning applications for all
proposals where mature trees are present on site or that may impact on trees
outwith the site. The strategy for new tree provision should follow the principles
of the "Right Tree in the Right Place". 
c) Make provision for new open space and connect to existing open space under
the requirements of Policy EP5 and provide details of the future maintenance of
these spaces. A detailed landscape plan must be submitted with planning
applications and include information about green/blue infrastructure, tree
species, planting, ground/soil conditions, and natural and man-made features
(e.g. grass areas, wildflower verges, fencing, walls, paths, etc.). 
d) Demonstrate how the development will conserve and enhance the natural and
built environment and cultural heritage resources, retain original land contours
and integrate into the landscape.
Page 305

Page 306

e) Proposals must not adversely impact upon neighbouring properties in terms of
privacy, daylight or overbearing loss of amenity. 
f)  Proposals do not result in backland development or plots that are subdivided by
more than 50% of the original plot.  Sub-divided plots must be a minimum of
400m2, excluding access and the built-up area of the application site will not
exceed one-third of the total area of the plot and the resultant plot density and
layout reflects the character of the surrounding area. 
g)  Pitched roofs will be preferred to flat roofs and box dormers are not acceptable. 
h)  Existing stone walls on buildings and boundaries must be retained. 
Alterations and extensions must be compatible with the character of the
existing building in terms of design, form, choice of materials and positioning
and meet all other relevant criteria of this policy. 
i)  Proposals must orientate and design buildings to maximise opportunities for
solar gain. 
j)  All developments must be designed so as to ensure that all new buildings avoid
a specified and rising proportion of the projected greenhouse gas emissions
from their use (calculated on the basis of the approved design and plans for the
specific development) through the installation and operation of low and zero-
carbon generating technologies. 
(ii) Transportation
a) Proposals must provide safe entry and exit from the development, including the
appropriate number and type of junctions, maximise connections and routes for
pedestrians and cyclists, including links to active travel and core path routes,
reduce travel demands and ensure appropriate visibility for all road users at
junctions and bends. Road, cycling, footpath and public transport connections
and infrastructure must be provided at a level appropriate to the development
and connect people to education, employment, recreation, health, community
and retail facilities. 
b) Car parking must not dominate the street scene and must be provided to the
side or rear ¬and behind the building line. Maximum (50%) parking to the front
of buildings and on street may be permitted provided that the visual impact of
the parked cars is mitigated by hedging or low stone boundary walls. Roadways
with a single carriageway must provide sufficient off road parking to avoid
access routes being blocked to larger service vehicles and prevent parking on
pavements. 
c) Provide safe access to and from the road network, address any impacts on
road safety and the local road, rail and public transport network. Any impacts
identified through Transport Assessments/ Statements must be identified and
mitigated. This may include but would not be limited to, passing places, road
widening, junction improvements, bus stop infrastructure and drainage
infrastructure. A number of potential mitigation measures have been identified
in association with the development of sites and the most significant are shown
on the Proposals Map as TSP's.
Page 306

Page 307

d) Provide covered and secure facilities for cycle parking at all flats/apartments,
retail, community, education, health and employment centres. 
e) Garages and parking provision must be designed to comply with Moray Council
parking specifications see Appendix 2. 
f)  The road layout must be designed to allow for the efficient mechanical
sweeping of all roadways and channels, paviors, turning areas and junctions.
The road layout must also be designed to enable safe working practices,
minimising reversing of service vehicles, with hammerheads minimised in
preference to turning areas such as road stubs or hatchets, and to provide
adequate space for the collection of waste and movement of waste collection
vehicles. 
g) The road and house layout in urban development should allow for communal
refuse collection points where the design does not allow for individual storage
within the curtilage and / or collections at kerbside. Communal collection points
may either be for the temporary storage of containers taken by the individual
householder or for the permanent storage of larger containers. The
requirements for a communal storage area are stated within the Council's
Kerbside Collection Policy, which will be a material consideration. 
h) Road signs should be minimised designed and placed at the back of footpaths
to reduce street clutter, avoid obstructing pedestrian movements and
safeguarding sightlines; 
i)  Within communal parking areas there will be a requirement for electric car
charging points. Parking spaces for car sharing must be provided where a need
is identified by the Transportation Manager. 
(iii) Water environment, pollution, contamination
a) Acceptable water and drainage provision must be made, including the use of
sustainable urban drainage systems (SUDS) for dealing with surface water
including temporary/ construction phase SUDS (see Policy EP12). 
b) New development should not be located in areas at flood risk or increase
vulnerability to flooding (see Policy EP12). Exceptions to this would only be
considered in specific circumstances, e.g. extension to an existing building or
change of use to an equal or less vulnerable use. Where this exception is
applied the proposed development must include resilience measures such as
raised floor levels and electrical sockets. 
c) Proposals must avoid major hazard sites and address any potential risk of
pollution including ground water contamination in accordance with recognised
pollution prevention and control measures. 
d) Proposals must protect and wherever practicable enhance water features
through for example naturalisation of watercourses by introducing a more
natural planform and removing redundant or unnecessary structures. 
e) Proposals must address and sufficiently mitigate any contaminated land issues.
Page 307

Page 308

f)  Make acceptable arrangements for waste collection and management and
encourage recycling. 
g) Avoid sterilising significant workable reserves of minerals, prime agricultural
land or productive forestry. 
h)  Proposals must avoid areas at risk of coastal erosion and coastal change. 
DP5 BUSINESS & INDUSTRY
a) Development of employment land is supported to deliver the aims of the Moray
Economic Strategy.  A hierarchical approach will be taken when assessing proposals
for business and industrial uses. New and existing employment designations are set
out in Settlement Statements and their description identifies where these fall within
the policy hierarchy. 
Proposals must comply with Policy DP1, site development requirements within town
and village statements, and all other relevant policies within the Plan. Office
development that will attract significant numbers of people must comply with Policy
DP7 Retail/Town Centres. 
Efficient energy and waste innovations should be considered and integrated within
developments wherever possible. 
b) Business Parks 
Business parks will be kept predominantly for 'high-end' businesses such as those
related to life sciences and high technology uses.  These are defined as Class 4
(business) of the Town and Country Planning (Use Classes) (Scotland) Order 1997.
This applies to new proposals as well as redevelopment within established Business
Parks. 
Proposals for the development of new business parks must adhere to the key design
principles set out in town statements or Development Frameworks adopted by the
Council.   
c) Industrial Estates 
Industrial Estates will be primarily reserved for uses defined by Classes 4 (business),
5 (general) and 6 (storage and distribution) of the Town and Country Planning (Use
Classes) (Scotland) Order 1997. This applies to new proposals as well as
redevelopment within established Industrial Estates.  Industrial Estates could be
suitable sites for waste management facilities.   
d) Existing Business Areas 
Long established business uses will be protected from non-conforming uses (e.g.
housing).  The introduction or expansion of non-business uses (e.g. retail) will not be
permitted, except where the total redevelopment of the site is proposed.   
e) Other Uses 
Class 2 (business and financial), 3 (food and drink), 11 (assembly and leisure) and
activities which do not fall within a specific use class (sui generis), including waste
management facilities will be considered in relation to their suitability to the business
or industrial area concerned, their compatibility with neighbouring uses and the
Page 308

Page 309

supply of serviced employment land.  Retail uses will not be permitted unless they
are considered ancillary to the principal use (e.g. manufacture, wholesale).  For this
purpose, 'ancillary' is taken as being linked directly to the existing use of the unit and
comprising no more than 10% of the total floor area up to a total of 1,000 sq metres
(gross) or where a sequential approach in accordance with town centre first
principles has identified no other suitable sites and the proposal is in accordance
with all other relevant policies and site requirements are met. 
f) Areas of Mixed Use 
Proposals for a mix of uses where site specific opportunities are identified within
Industrial Estate designations in the Settlement Statement, will be considered
favourably where evidence is provided to the authority's satisfaction that the
proposed mix will enable the servicing of employment land and will not compromise
the supply of effective employment land.  A Development Framework that shows the
layout of the whole site, range of uses, landscaping, open space and site specific
design requirements must be provided. The minimum levels of industrial use
specified within designations must be achieved on the rest of the site. 
g) Rural Businesses and Farm Diversification 
Proposals for new business development and extensions to existing businesses in
rural locations including tourism and distillery operations will be supported where
there is a locational need for the site and the proposal is in accordance with all other
relevant policies. 
A high standard of design appropriate to the rural environment will be required and
proposals involving the rehabilitation of existing properties (e.g. farm steadings) to
provide business premises will be encouraged. 
Outright retail activities will be considered against policy DP7, and impacts on
established shopping areas, but ancillary retailing (e.g. farm shop) will generally be
acceptable. 
Farm diversification proposals and business proposals that will support the economic
viability of the farm business are supported where they meet the requirements of all
other relevant Local Development Plan policies. 
h) Inward Investment Sites 
The proposals map identifies a proposed inward investment site at Dallachy which is
safeguarded for a single user business proposal seeking a large (up to 40ha), rural
site. Additional inward investment sites may be identified during the lifetime of the
Plan. 
Proposals must comply with Policy DP1 and other relevant policies. 
EP2 BIODIVERSITY
All development proposals must, where possible, retain, protect and enhance features of
biological interest and provide for their appropriate management.  Development must
safeguard and where physically possible extend or enhance wildlife corridors and
green/blue networks and prevent fragmentation of existing habitats. 
Development should integrate measures to enhance biodiversity as part of multi-functional
spaces/ routes. 
Page 309

Page 310

Proposals for 4 or more housing units or 1000 m2 or more of commercial floorspace must
create new or, where appropriate, enhance natural habitats of ecological and amenity
value. 
Developers must demonstrate, through a Placemaking Statement where required by
Policy PP1 which incorporates a Biodiversity Plan, that they have included biodiversity
features in the design of the development. Habitat creation can be achieved by providing
links into existing green and blue networks, wildlife friendly features such as wildflower
verges and meadows, bird and bat boxes, amphibian friendly kerbing, wildlife crossing
points such as hedgehog highways and planting to encourage pollination, wildlife friendly
climbing plants, use of hedges rather than fences, incorporating biodiversity measures into
SUDS and retaining some standing or lying dead wood, allotments, orchards and
woodlands. 
Where development would result in loss of natural habitats of ecological amenity value,
compensatory habitat creation will be required where deemed appropriate. 
EP7 FORESTRY, WOODLANDS AND TREES
a) Moray Forestry and Woodland Strategy 
Proposals which support the economic, social and environmental objectives and
projects identified in the Moray Forestry and Woodlands Strategy will be supported
where they meet the requirements of other relevant Local Development Plan
policies.  The council will consult Scottish Forestry on proposals which are
considered to adversely affect forests and woodland.  Development proposals must
give consideration to the relationship with existing woodland and trees including
shading, leaf/needle cast, branch cast, wind blow, water table impacts and
commercial forestry operations. 
b) Tree Retention and Survey 
Proposals must retain healthy trees and incorporate them within the proposal unless
it is technically unfeasible to retain these.  Where trees exist on or bordering a
development site, a tree survey, tree protection plan and mitigation plan must be
provided with the planning application if the trees or trees bordering the site (or their
roots) have the potential to be affected by development and construction activity. 
Proposals must identify a safeguarding distance to ensure construction works,
including access and drainage arrangements, will not damage or interfere with the
root systems in the short or longer term.  A landscaped buffer may be required where
the council considers that this is required to maintain an appropriate long term
relationship between proposed development and existing trees and woodland. 
Where it is technically unfeasible to retain trees, compensatory planting on a one for
one basis must be provided in accordance with (e) below. 
c) Control of Woodland Removal 
In support of the Scottish Government's Control of Woodland Removal Policy,
Woodland removal within native woodlands identified as a feature of sites protected
under Policy EP1 or woodland identified as Ancient Woodland will not be supported. 
In all other woodlands development which involves permanent woodland removal will
only be permitted where it would achieve significant and clearly defined additional
public benefits (excluding housing) and where removal will not result in unacceptable
Page 310

Page 311

adverse effects on the amenity, landscape, biodiversity, economic or recreational
value of the woodland or prejudice the management of the woodland. 
Where it is proposed to remove woodland, compensatory planting at least equal to
the area to be felled must be provided in accordance with e) below. 
d) Tree Preservation Orders and Conservation Areas 
The council will serve Tree Preservation Orders (TPO's) on potentially vulnerable
trees which are of significant amenity value to the community as whole, trees that
contribute to the distinctiveness of a place or trees of significant biodiversity value. 
Within Conservation Areas, the council will only agree to the felling of dead, dying, or
dangerous trees. Trees felled within Conservation Areas or subject to TPO must be
replaced, unless otherwise agreed by the council. 
e) Compensatory Planting 
Where trees or woodland are removed in association with development, developers
must provide compensatory planting to be agreed with the planning authority either
on site, or an alternative site in Moray which is in the applicant's control or through a
commuted payment to the planning authority to deliver compensatory planting and
recreational greenspace. 
GUIDANCE TREES AND DEVELOPMENT
Trees are an important part of Moray's towns and villages and surrounding countryside,
adding colour and interest to the townscape and a sense of nature in our built
environment. They contribute to the diversity of the countryside, in terms of landscape,
wildlife habitat and shelterbelts. Trees also have a key role to play in terms of climate
change by helping to absorb carbon dioxide which is one of the main greenhouse gases
that cause global warming. 
The cumulative loss of woodlands to development can result in significant loss of
woodland cover. In compliance with the Scottish Government Control of Woodland
Removal policy, woodland removal should only be allowed where it would achieve
significant and clearly defined additional public benefits. In appropriate cases a proposal
for compensatory planting may form part of this balance. Where  woodland is to be
removed then the Council will require compensatory planting to be provided on site, on
another site in Moray within the applicant's control or through a commuted payment to the
Council towards woodland and greenspace creation and enhancement. Developers
proposing compensatory planting are asked to follow the guidance for site assessment
and woodland design as laid out in Scottish Forestry's "Woodland Creation, Application
Guidance" and its subsequent updates, when preparing their proposal. 
The Council requires a Tree Survey and Tree Protection Plan to be submitted by the
applicant with any planning application for detailed permission on designated or windfall
sites which have trees on them. The survey should include a schedule of trees and/or
groups of trees and a plan showing their location, along with the following details; 
• Reference number for each tree or group of trees.
• Scientific and common names.
• Height and canopy spread in metres (including consideration of full height and
spread).
• Root protection area.
Page 311

Page 312

• Crown clearance in metres.
• Trunk diameters in metres (measures at 1.5m above adjacent ground level for single
stem trees or immediately above the root flare for multi stemmed trees).
• Age and life expectancy.
• Condition (physiological and structural).
• Management works required.
• Category rating for all trees within the site (U, A, B or C *). This arboricultural
assessment will be used to identify which trees are suitable for retention within the
proposed development. 
*BS5837 provides a cascading quality assessment process for categorisation of trees
which tree surveys must follow. An appropriately scaled tree survey plan needs to
accompany the schedule. The plan should be annotated with the details of the tree
survey, showing the location, both within and adjacent to the site, of existing trees, shrubs
and hedgerows. Each numbered tree or groups of trees should show the root protection
area and its category U, A, B, C. 
Based on the guidance in BS5837, only category U trees are discounted from the Tree
Survey and Tree Protection Plan process. Trees in category A and B must be retained,
with category C trees retained as far as practicable and appropriate. Trees proposed for
removal should be replaced with appropriate planting in a landscape plan which should
accompany the application. Trees to be retained will likely be set out in planning
conditions, if not already covered by a Tree Preservation Order. 
If a tree with habitat value is removed, then measures for habitat reinstatement must be
included in the landscape plan. It is noted that in line with part b) of policy EP7 where
woodland is removed compensatory planting must be provided regardless of tree
categorisation." 
A Tree Protection Plan (TPP) must also be submitted with planning applications,
comprising a plan and schedule showing; 
• Proposed design/ layout of final development, including accesses and services.
• Trees to be retained- with those requiring remedial work indicated.
• Trees to be removed.
• Location (and specification) of protective fencing around those trees to be retained
based on the Root Protection Area. 
The TPP should show how the tree survey information has informed the design/ layout
explaining the reasoning for any removal of trees. 
Landscape Scheme
Where appropriate a landscape scheme must be submitted with planning applications,
clearly setting out details of what species of trees, shrubs and grass are proposed, where,
what standard and when planting will take place. Landscape schemes must aim to deliver
multiple benefits in terms of biodiversity, amenity, drainage and recreation as set out in
policy. 
The scheme should also set out the maintenance plan. Applicants/ developers will be
required to replace any trees, shrubs or hedges on the site which die, or are dying,
severely damaged or diseased which will be specified in planning conditions. 
Page 312

Page 313

Tree species native to Scotland are recommended for planting in new development -
Alder, Aspen, Birch, Bird Cherry, Blackthorn, Crab Apple, Elm, Gean, Hawthorn, Hazel,
Holly, Juniper, Sessile Oak, Rowan, Scots Pine, Whitebeam, Willow. 
EP12 MANAGEMENT AND ENHANCEMENT OF THE WATER ENVIRONMENT
a) Flooding
New development will not be supported if it would be at significant risk of flooding
from any source or would materially increase the possibility of flooding elsewhere.
For development at or near coastal locations, this includes consideration of future
flooding that may be caused by sea level rise and/or coastal change eroding existing
natural defences in the medium and long term. 
Proposals for development in areas considered to be at risk from flooding will only be
permitted where a flood risk assessment to comply with the recommendations of
Scottish Planning Policy and to the satisfaction of Scottish Environment Protection
Agency and the Council is provided by the applicant. 
There are different levels of flood risk assessment dependent on the nature of the
flood risk. The level of assessment should be discussed with the Council prior to
submitting a planning application. 
Level 1 -  a flood statement with basic information with regard to flood risk.
Level 2 -  full flood risk assessment providing details of flood risk from all sources,
results of hydrological and hydraulic studies and any appropriate
proposed mitigation. 
Assessments must demonstrate that the development is not at risk of flooding and
would not increase the probability of flooding elsewhere.  Level 2 flood risk
assessments must be signed off by a competent professional.  The Flood Risk
Assessment and Drainage Impact Assessment for New Development Supplementary
Guidance provides further detail on the information required. 
Due to continuing changes in climatic patterns, the precautionary principle will apply
when reviewing any application for an area at risk from inundation by floodwater.
Proposed development in coastal areas must consider the impact of tidal events and
wave action when assessing potential flood risk. 
The following limitations on development will also be applied to take account of the
degree of flooding as defined in Scottish Planning Policy;
a) In areas of little to no risk (less than 0.1%), there will be no general constraint to
development.
b) Areas of low to medium risk (0.1% to 0.5%) will be considered suitable for most
development. A flood risk assessment may be required at the upper end of the
probability range i.e. (close to 0.5%) and for essential civil infrastructure and the
most vulnerable uses. Water resistant materials and construction may be
required. Areas within this risk category will generally not be suitable for civil
infrastructure. Where civil infrastructure must be located in these areas or is
being substantially extended, it should be designed to be capable of remaining
operational and accessible during flooding events.
c) Areas of medium to high risk (0.5% or above) may be suitable for:
• Residential, institutional, commercial and industrial development within
built up areas provided that flood protection measures to the appropriate
Page 313

Page 314

standard already exist and are maintained, are under construction, or are
a planned measure in a current flood management plan.
• Essential infrastructure within built up areas, designed and constructed to
remain operational during floods and not impede water flow.
• Some recreational, sport, amenity and nature conservation uses, provided
appropriate evacuation procedures are in place, and
• Employment related accommodation e.g. caretakers or operational staff. 
Areas within these risk categories will generally not be suitable for the following
uses and where an alternative/lower risk location is not available¬¬;
• Civil infrastructure and most vulnerable uses.
• Additional development in undeveloped and sparsely developed areas,
unless a location is essential for operational reasons e.g. for navigation
and water based recreation, agriculture, transport or utilities infrastructure
(which should be designed to be operational during floods and not impede
water flows).
• New caravan and camping sites 
Where development is permitted, measures to protect against or manage flood
risk will be required and any loss of flood storage capacity mitigated to achieve
a neutral or better outcome. Water resistant materials and construction must be
used where appropriate. Land raising and elevated buildings on structures such
as stilts are unlikely to be acceptable. 
b) Surface Water Drainage: Sustainable Urban Drainage Systems (SUDS)
Surface water from development must be dealt with in a sustainable manner that has
a neutral effect on flooding or which reduces the risk of flooding. The method of
dealing with surface water must also avoid pollution and promote habitat
enhancement and amenity. All sites must be drained by a sustainable drainage
system (SUDS) designed in line with current CIRIA guidance. Drainage systems
must contribute to enhancing existing "blue" and "green" networks while contributing
to place-making, biodiversity, recreational, flood risk and climate change objectives. 
When considering the appropriate SUDS design for the development the most
sustainable methods, such as rainwater harvesting, green roofs, bio retention
systems, soakaways, and permeable pavements must be considered first.  If it is
necessary to include surface water attenuation as part of the drainage system, only
above ground attenuation solutions will be considered, unless this is not possible
due to site constraints.   
If below ground attenuation is proposed the developer must provide a robust
justification for this proposal.  Over development of a site or a justification on
economic grounds will not be acceptable.  When investigating appropriate SUDS
solutions developers must integrate the SUDS with allocated green space, green
networks and active travel routes to maximise amenity and biodiversity benefits. 
Specific arrangements must be made to avoid the issue of permanent SUDS
features becoming silted-up with run-off. Care must be taken to avoid the spreading
and/or introduction of invasive non-native species during the construction of all
SUDS features.  On completion of SUDS construction the developer must submit a
comprehensive Operation and Maintenance Manual.  The ongoing maintenance of
Page 314

Page 315

SUDS for all new development will be undertaken through a factoring agreement, the
details of which must be supplied to the Planning Authority.   
All developments of less than 3 houses or a non-householder extension under 100
square metres must provide a Drainage Statement.  A Drainage Assessment will be
required for all developments other than those identified above. 
c) Water Environment
Proposals, including associated construction works, must be designed to avoid
adverse impacts upon the water environment including Ground Water Dependent
Terrestrial Ecosystems and should seek opportunities for restoration and/or
enhancement, if appropriate. The Council will only approve proposals impacting on
water features where the applicant provides a report to the satisfaction of the Council
that demonstrates that any impact (including cumulative) on water quality, water
quantity, physical form (morphology), river hydrology, sediment transport and
erosion, coastal processes (where relevant) nature conservation (including protected
species), fisheries, recreational, landscape, amenity and economic and social impact
can be adequately mitigated. 
The report must consider existing and potential impacts up and downstream of the
development particularly in respect of potential flooding. The Council operates a
presumption against the culverting of watercourses and any unnecessary
engineering works in the water environment. 
A buffer strip of at least 6 metres between any new development and all water
features is required and should be proportional to the bank width and functional river
corridor (see table on page 96). This must achieve the minimum width within the
specified range as a standard, however, the actual required width within the range
should be calculated on a case by case basis by an appropriately qualified individual.
These must be designed to link with blue and green networks, including appropriate
native riparian vegetation and can contribute to open space requirements. 
Developers may be required to make improvements to the water environment as part
of the development. Where a Water Framework Directive (WFD)¬ water body
specific objective is within the development boundary, or in proximity, developers will
need to address this within the planning submission through assessment of potential
measures to address the objective and implementation, unless adequate justification
is provided. Where there is no WFD objective the applicant should still investigate
the potential for watercourse restoration along straightened sections or removal of
redundant structures and implement these measures where viable. 
Width to watercourse Width of buffer strip (either side)
(top of bank) 
Less than 1m  6m
1-5m 6-12m
5-15m 12-20m
15m+ 20m+ 
The Flood Risk Assessment and Drainage Impact Assessment for New Development
Supplementary Guidance provides further detail on the information required to
support proposals. 
Page 315

Page 316

EP13 FOUL DRAINAGE 
All development within or close to settlements (as defined in the Local Development Plan)
of more than 2,000 population must connect to the public sewerage system unless
connection  is not permitted due to lack of capacity. In such circumstances, temporary
provision of private sewerage systems may be allowed provided Scottish Water has
confirmed investment to address this constraint has been allocated within its investment
Programme and the following requirements have been met; 
• Systems must not have an adverse effect on the water environment
• Systems must be designed and built to a standard which will allow adoption by
Scottish Water
• Systems must be designed such that they can be easily connected to a public sewer
in the future. Typically this will mean providing a drainage line up to a likely point of
connection. 
All development within or close to settlements (as above) of less than 2,000 population will
require to connect to public sewerage except where a compelling case is made otherwise.
Factors to be considered in such a case will include size of the proposed development,
whether the development would jeopardise delivery of public sewerage infrastructure and
existing drainage problems within the area. 
Where a compelling case is made, a private system may be acceptable provided it does
not pose or add a risk of detrimental effects, including cumulative, to the natural and built
environment, surrounding uses or amenity of the general area. 
Where a private system is deemed to be acceptable, within settlements as above or small
scale development in the countryside, a discharge to land, either full soakaway or raised
mound soakaway, compatible with Technical Handbooks (which sets out guidance on how
proposals may meet the Building  Regulations) must be explored prior to considering a
discharge to surface waters.
Page 316

Page 317

REPORT TO: PLANNING AND REGULATORY SERVICES COMMITTEE ON 20
DECEMBER 2022 
SUBJECT: DEVELOPMENT PLAN SCHEME 2023- MORAY LOCAL
DEVELOPMENT PLAN 2027 
BY:  DEPUTE CHIEF EXECUTIVE (ECONOMY, ENVIRONMENT AND
FINANCE) 
1. REASON FOR REPORT 
1.1 This report asks the Committee to consider the current timetable for the
preparation of the new Local Development Plan (LDP) 2027 and to agree that
the Development Plan Scheme (DPS) and Participation Statement is submitted
to the Scottish Government. 
1.2 This report is submitted to Committee in terms of Section III E (2) of the
Council's Scheme of Administration relating to the Review and Preparation of
Strategic and Local Plans. 
2. RECOMMENDATION 
2.1 It is recommended that the Committee agree the DPS and Participation         
Statement for 2023, as set out in Appendices 1 and 2 and that the Scheme
is submitted to the Scottish Government. 
3. BACKGROUND 
3.1 Planning authorities have a statutory requirement to set out a timetable for the
review/production of their LDP in the form of a DPS and to submit this annually
to the Scottish Government. 
3.2 The Planning (Scotland) Act 2019 introduces changes to the LDP preparation
process. The most significant changes include; 
• The need to produce an Evidence Report rather than a Main Issues
Report. This is to ensure that sufficient evidence is in place to justify the
spatial strategy in the LDP and to justify any local policy positions.
• The introduction of a Gate check to consider areas of dispute in the
Evidence Report. This is intended to help streamline the later Examination
Item 11
Page 317

Page 318

process by agreeing key aspects such as housing land requirements at an
earlier stage.
• Regional minimum housing land requirements being set by the Scottish
Government.
• The LDP will be place based, with National Planning Framework 4 (NPF4)
setting national policies which will form part of the LDP and an expectation
that only limited “local” policies will be included in the LDP, where the
need is evidenced. NPF4 policies will have greater weight in decision
making until any new local policies are adopted.
• The need to produce a Regional Spatial Strategy (RSS) either individually
or collectively with adjacent authorities. The RSS and LDP will together
form the long-term spatial plan to manage change.
• The need to invite and consider Local Place Plans.
• A greater focus on engagement and delivery. 
3.3 Draft NPF4 and the draft LDP Regulations were reported to a meeting of this
Committee on 1 March 2022 (para 9 of minute refers). The revised draft version
of NPF4 was laid before Scottish Parliament on 8th November 2022 for
approval. As soon as practicable after the NPF has been adopted, the Scottish
Ministers are to publish it. When the NPF4 is published it triggers changes to
the meaning of the development plan and commences section 13 of the
Planning (Scotland) Act 2019. This will amend section 24 “Meaning of the
development plan” of the 1997 Act, which will bring NPF4 in to be part of the
development plan. That section is also the part that will set out that “in the
event of any incompatibility between a provision of the NPF and a provision of a
local development plan, whichever of them is the later in date is to prevail. 
3.4 Following approval of NPF4, the Scottish Government will consider and
approve the final version of the Development Plan Regulations which means
that the DPS has been prepared with a degree of uncertainty as to the final
content of the Regulations. 
3.5 The target date for adopting new LDP’s is 5 years from the date of adoption of
NPF4.  The key milestones for preparing LDP2027 are; 
• Development Plan Scheme and Participation Statement published
December 2022
• Call for Ideas, invitation to prepare Local Place Plans and setting up self-
build register January 2023
• Regional Spatial Strategy February 2023 to November 2023
• Evidence Report to Council March 2024
• Gatecheck procedure April 2024- December 2024
• Proposed Plan to Council December 2025
• Examination process May 2026- March 2027
• Adoption of new Plan September 2027 
3.6 The LDP process involves extensive community and stakeholder participation
throughout, moving from informal evidence gathering and support for LPP to
more formal consultation, awareness raising and neighbour notification at
Proposed Plan stage. 
Page 318

Page 319

3.7 The timescales for the Gatecheck and Examination processes are difficult to
predict as they are largely outwith the Council’s control and managed by an
independent person appointed by Scottish Ministers. However, the Council can
ensure that these are carried out as timeously as possible by ensuring the
Evidence Report and Examination casework are thoroughly researched,
evidenced and presented. 
4. PROPOSALS 
4.1  The DPS for 2023 is set out in Appendix 1 and is intended to be a project
management tool.   
4.2 The DPS identifies other workstreams required to inform the Evidence Report,
the lead service/section, where there is a cost involved beyond staffing and
when external consultancy will be required.   
4.3 The Participation Statement in Appendix 2 sets out who, when, where and how
engagement will take place, including how members will be involved. A range
of engagement tools will be used at different events to engage with as wide an
audience as possible across the Moray LDP area. 
4.4 There are a number of workstreams already underway with the proposed
formal review process beginning in January 2023. Work already underway
includes; 
• Housing Need and Demand Assessment- led by Housing service
• Woodland Strategy- procurement process underway
• Business Needs Survey- procurement process underway
• Brownfield sites review- reported to Planning and Regulatory Services
Committee October 2022
• Tree Preservation Order review- reported to this meeting 
• Town Centre Improvement Plans- reported to Planning and Regulatory
Services Committee October 2022
• Site survey work- ongoing
• Evidence report structure- ongoing
• Retail Study- complete
• Urban capacity studies- underway 
5. SUMMARY OF IMPLICATIONS 
(a) Corporate Plan and 10 Year Plan (Local Outcomes Improvement Plan
(LOIP)) 
The LDP is a vital aspect of supporting and facilitating the Council’s
priority for economic growth.  The Plan also aims to deliver other key
objectives including the delivery of affordable housing, provision of land
for employment purposes and conservation and enhancement of our high
quality natural and historic environment. 
Page 319

Page 320

The annual DPS monitors progress of the Plan and is submitted to the
Scottish Government to ensure Moray has an up to date LDP, which is a
key performance indicator in the Planning Performance Framework (PPF)
and a statutory requirement. 
(b) Policy and Legal 
Preparation of the LDP, RSS and DPS is a statutory responsibility in the
Council’s role as Planning Authority.  Preparation must follow statutory
procedures. 
(c) Financial implications 
A budget pressure was highlighted in the report to this Committee on 23rd
March 2021 (para 13 of minute refers) for critical transportation appraisals
of £200,000 in the 2022/23 financial year and £50,000 in the 2023/24
financial year. These transportation studies are essential to support the
LDP, meet the requirements of Transport Scotland and identify mitigation
measures, which form the basis for transportation related developer
obligations. Transport budgets will not be spent this year due to delays in
finalising and adopting NPF4 which has resulted in many planning
authorities delaying LDP reviews. 
Transport budgets will therefore commence in 2023/24 financial year and
continue into 2024/25 and 2025/26, likely to be split £100,000, £100,000
and £50,000. Once Transport Scotland guidance has been updated the
proportions over the financial years may change. 
Other costs required to inform and develop the LDP will be met from the
LDP annual revenue budget. 
It is unknown if the cost of the Gatecheck process is to be met by local
authorities. The cost of the Examination process will result in a budget
pressure in 2026/27.   
(d) Risk Implications 
A project risk register has been prepared. Key risks identified are set out
below which all raise risks of delays to the LDP process or risk of not
delivering the proposals within the Plan; 
• Insufficient evidence collated and included within the Evidence Report- risk
of delay, Reporter requests additional information and/ or re-write
Evidence Report
• Inclusion of evidence indicating a local policy pathway at odds with
national policy- risk of delay if local policy approach contrary to NPF4.
• Staff resources- risks associated with other competing workloads and risks
associated with losing experienced members of staff which would add
delay, not only within Strategic Planning and Development but other
services
• Uncertainty over procedures until the new LDP regulations are adopted
Page 320

Page 321

• Failing to meet the governments aspirations for wide engagement in the
process
• Risk of not resourcing services to deliver the plan and meet the aspirations
for planners to be enablers of change 
The proposed approach and timelines set out in the DPS endeavours to
mitigate these risks, where possible. 
(e) Staffing Implications 
Preparing the LDP is a statutory requirement and will therefore be a
priority for the Strategic Planning and Development section over the next
few years.  At key peaks in workload this can have an impact upon other
workload commitments. The new Plan will have a strong focus on climate
change and the climate change officers within Strategic Planning and
Development will be involved in the Evidence Report, Regional Spatial
Strategy, interpretation of NPF4 and development of the Proposed Plan. 
Preparation of the LDP and its subsequent delivery involves other
services, particularly Transportation, Housing, Education, Estates, Legal,
Consultancy and Development Management, which impacts upon
workloads and performance within these services.  
(f) Property 
None at this stage. 
(g) Equalities/Socio Economic Impact 
None. 
(h) Climate Change and Biodiversity Implications 
The new planning system will include national and local planning policies
aimed at reducing carbon emissions and addressing our nature crisis as
well as concepts such as 20 minute neighbourhoods which will be key
drivers in delivering change. The DPS subject of this report is a project
management tool, setting out key milestones for the preparation of the
next LDP and is not considered to have any direct carbon or biodiversity
impacts. 
As referenced in the staffing implications above, climate change officers
will be involved in the LDP process. 
A full Carbon and Biodiversity Assessment will be undertaken at Evidence
Report stage. 
(i) Consultations 
Consultation has taken place with the Depute Chief Executive Economy,
Environment and Finance, the Head of Economic Growth and
Development, the Head of Education Resources and Communities, the
Page 321

Page 322

Legal Services Manager, the acting Housing Strategy and Development
Manager, the Senior Engineer Transportation, the Equal Opportunities
Officer, the Principal Climate Change Officer, the Development
Management and Building Standards Manager and Deborah O’Shea 
(Principal Accountant) and their comments incorporated into the report. 
5. CONCLUSION 
5.1 Planning authorities are required to annually review their DPS which sets
out the timetable for the review/replacement of the LDP. 
5.2 The DPS 2023 sets out the timetable for the preparation of the next LDP
and the Participation Statement sets out details of how the Council will
engage throughout the process. 
Author of Report:  Gary Templeton
Strategic Planning and Development Manager
and Emma Gordon, Planning Officer 
Background Papers: 
Ref: 
Page 322

Page 323

PLANNING AND DEVELOPMENT SERVICES
DEVELOPMENT PLAN SCHEME
DECEMBER 2022
APPENDIX 1Item 11
Page 323

Page 324

Your place, Your plan, Your future
Page 324

Page 325

INTRODUCTION 
The Town and Country Planning (Scotland) Act
1997 (as amended by the Planning etc (Scotland)
Act 2006), the Town and Country Planning
(Development Planning) Regulations 2008, and
the Planning (Scotland) Act 2019 require
planning authorities to prepare a Development
Plan Scheme each year. 
The Development Plan Scheme sets out the
timelines for preparing the new Local
Development Plan 2027, updates on planning
guidance and masterplanning and includes a
Participation Statement which sets out who,
when and how we will consult with stakeholders. 
The Scheme is reviewed annually. The process for
preparing local development plans in Scotland is
changing and will be informed by the final
version of National Planning Framework 4 and
new Development Planning Regulations which
are anticipated to be adopted by the Scottish
Government by the end of 2022 and early 2023
respectively.  Key changes included within the
Planning (Scotland) Act 2019 include the
replacement of the Main Issues Report stage with
a new Evidence Report and Gatecheck procedure
aiming to streamline the Examination process
and ensure an evidence led approach is taken in
preparing the Proposed Plan. 
The timelines will be reviewed and updated as
work progresses on the various workstreams to
support the existing LDP and to prepare the new
LDP. Preparing the new Plan will involve extensive
stakeholder and community engagement and
the Planning (Scotland) Act 2019 requires
engagement with specific stakeholder groups
such as young people. The Participation
Statement is included as an Appendix to this
Scheme.
1
Development Plan Scheme 2022
map showing the extent of the Moray Council area
JUST WAITING FOR THIS MAP
Aberlour Dufftown
CraigellachieArchiestown
Rothes
Dallas
Rafford
Dyke Forres
Findhorn
Kinloss
Alves
Elgin
Lossiemouth
Duffus
Burghead
Cummingston Hopeman
Lhanbryde
Keith
Newmill
Rothiemay
Cullen
Portknockie
Findochty
Buckie
PortgordonKingston
Garmouth
Fochabers
Mosstodloch
Urquhart
©
Crown Copyright 2022 
The Moray Council 100023422
Moray Local Development Plan Area
Page 325

Page 326

Your place, Your plan, Your future
2
Moray Local Development Plan 2020
The MLDP2020 was adopted on 27th July 2020. A number of Masterplans, Supplementary Guidance
and additional planning guidance have been produced to support the Plan and these can be viewed
at http://www.moray.gov.uk/moray_standard/page_133431.html 
The following work will be progressed over the next 12 months to support the LDP2020 and inform
the new LDP2027. 
Additional Planning Policy Guidance Q4 2022
NPF4 policy guidance / interpretation Q1/2 2023
Mosstodloch Masterplan approved Q3 2023
Findrassie Masterplan approved Q3 2023
Landscape Sensitivity Study approved Q3 2023
Lochyhill Masterplan to be determined
Developer Obligations Supplementary Guidance updated Q4 2023
Woodland Strategy Q3 2023 
Moray Local Development Plan 2027
The diagram below summarises the key timelines in preparing the new LDP27 which will replace the
current LDP2020. 
As with many planning authorities in Scotland, the early stages of the plan process were delayed due
to uncertainties around the final content and timescale for implementation of the Planning (Scotland)
Act 2019 which received royal assent in summer 2019. 
In October 2020 the Scottish Government issued draft transitional arrangements which were further
revised and indicated that if the Proposed LDP is not published by June 2022 then the new procedures
would come into effect and the Plan preparation process would have to start again from the
beginning. 
Under the new requirements, the Scottish Government has confirmed that the target is to have new
LDP’s in place within 5 years of NPF4 being adopted. The timelines below reflect that target.
Page 326

Page 327

3
Development Plan Scheme 2022
Invitation to prepare Local Place
Plans and Call for Ideas
January/ February 2023 
Prepare Evidence Report 
January to December 2023 
Report Evidence Report to Council 
March 2024 
Gatecheck 
April 2024 to December 2024 
Prepare and Report 
Proposed Plan to Council 
January 2025 to August 2025 
Consult on Proposed Plan
September 2025 to Dec 2025 
Prepare Examination  papers and
report to Council
January 2026 to August 2026 
Examination 
September 2026 to April 2027 
Modifications 
May/ June 2027 
Adoption 
September 2027
Prepare Regional Spatial Strategy
March 2023 to December 2023 
Report Regional Spatial Strategy
to Council
March 2024 
Full details of the work packages
involved in preparing the new
LDP are set out in Appendix 1.
Key timelines in preparing the new LDP27
Page 327

Page 328

Your place, Your plan, Your future
4
Participation Statement 
The Council is committed to encouraging participation from as wide a range of stakeholders as
possible in all Local Development Plan related activities, such as masterplans, development briefs and
other guidance published throughout the lifetime of the Plan. This Participation Statement outlines
how communities and stakeholders will be engaged and have the opportunity to engage, shape and
inform the Local Development Plan and associated documents, in line with National Standards for
Community Engagement. 
The Council aims to ensure that; 
l All engagement events are inclusive, open and transparent, this will be reflected in the venues we
use, the documents we produce and our methods of engagement;
l Representations are fully considered and help to shape our approach and that feedback is provide
to all representations received;
l We take the extra step to engage with as wide an audience as possible, reflecting the diverse
nature of our community. 
At the outset of the Local Development Plan process we will engage with elected members and with
community councils/ associations, explaining the process, seeking views on land use matters, raising
awareness of Local Place Plans and how Community Councils can help to raise awareness of the Plan.  
Key agencies such as SEPA, Historic Environment Scotland, NatureScot, Scottish Forestry, Transport
Scotland, Highlands and Islands Enterprise, NHS Grampian and Scottish Water will be engaged
throughout the process. The Council has an infrastructure Delivery Group which includes
representation from Transport Scotland, NHS Grampian, Scottish Water and officers from the Council
Housing, Transportation and Planning service. The Council will continue to liaise with and consult with
Homes for Scotland as an umbrella group and with its individual members. 
The full Participation Statement is set out in Appendix 2.
Page 328

Page 329

5
Development Plan Scheme 2022
Development Plan
Scheme 
Participation
Statement 
Self-Build land
register 
Invitation to prepare
Local Place Plans 
Call for Ideas 
Early engagement to
inform Evidence
Report (see
Participation
Statement) 
20 minute approach
for Moray 
Demographics-
population,
migration,
households,
employment for ER 
Brownfield sites
assessment 
Prepare Housing
Land requirement 
Town and village
capacity studies 
Review Countryside
Around Town
boundaries                
Internal 
Internal 
Internal 
Internal 
Internal 
Internal 
Internal 
Internal 
Internal 
Internal 
Internal 
Internal
Dec 2022 
Dec 2022 
Publish February/
March 2023 
Publish January/
February 2023 
Publish January/
February 2023 
February 2023 to
September 2023 
Agreed approach
June 2023 
Review Complete
October 2023 
Report to P&RS
October 2022 
Complete HLR paper
July 2023 
Complete studies
end May 2023 
Complete review end
April 2023
No 
No 
No 
No 
Advertisement 
No 
No 
No 
No 
No 
No 
No
Progress
on track
Work package Internal/
External
Timelines Budget
requirement
Page 329

Page 330

Your place, Your plan, Your future
6
Review Special
Landscape Area
boundaries 
Review Town Centre
boundaries 
Housing Need and
Demand Assessment 
Review of action
taken to support and
promote construction
and adaptation of
housing to meet the
needs of older people
and disabled people 
Strategic Housing
Investment Plan* 
Summary of the
action taken by the
planning authority to
meet the
accommodation
needs of Gypsy/
Travellers and an
analysis of the extent
to which that action
has helped meet
those needs. 
Housing Land Audit
2023 & 2024 
Need for short term
let control areas 
Annual Monitoring
report 2023 and 2024  
Internal 
Internal 
Internal- led
by Housing 
Internal 
Internal 
Internal 
Internal 
Internal 
Internal 
Complete review end
April 2023 
Complete review end
April 2023 
Complete by June
2023 
Complete by June
2023 
Annual review 
Complete by end
October 2023 
Annual reviews.
Complete by end
June 
Review complete by
June 2023 
Annual reviews
No 
No 
Financed by
Housing Services 
No 
No 
No 
No 
No 
No
Progress
on track
Work package Internal/
External
Timelines Budget
requirement
Page 330

Page 331

7
Development Plan Scheme 2022
Employment Land
Audit 
Town Centre Health
Checks 2023 
Retail Study 
Tourism development
opportunities 
Minerals survey
Demonstrate capable
of meeting the 10
year landbank of
construction
aggregate in all
market areas, existing
permitted minerals
reserves and relevant
elements from
aggregates survey 
Tourism Strategy * 
Moray Economic
Strategy * 
Annual economic
activity report/
Council strategy 
Business Needs
survey 
Areas of inequality
and socio economic
performance
indicators 
Internal 
Internal 
External 
Internal 
Internal 
Internal 
Internal 
Internal 
External 
Internal 
Annual review
complete by end
June 
October 2023 
Reported to P&RS
Committee April
2022 
Complete December
2023 
Complete by end
September 2023 
Complete by end
September 2023 
Complete by end
October 2023 
Complete by end
October 2023 
Complete by end
September 2023 
Complete by end
September 2023 
No 
No 
No 
No 
No 
No 
No 
No 
£20k 
January to May
2023 
Progress
on track
Work package Internal/
External
Timelines Budget
requirement
Complete
Page 331

Page 332

Your place, Your plan, Your future
8
Town Centre
Improvement Plans 
Community benefits
(NPF4 policy) 
Open Space Strategy 
Carbon calculations
NPF4 policy
methodology 
Play Sufficiency
Assessment 
LBAP- priority
habitats and species
and site data 
Forestry/ Woodland &
potential wider land
uses and recreation 
Conservation Area
Appraisals phase 1 
National strategies
relating to climate
change and land use* 
Areas of poor air
quality
Internal 
Internal 
Internal 
Internal 
External 
External 
External 
External 
Internal 
Internal
Report to P&RS
Committee October
2022 
Community benefits
report going to Nov
Corporate Services
Cttee. NPF4 approach
to be progressed by
Q1/Q2 2023 
Audit complete end
February 2023.
Complete draft by
end September 2023 
Completed by end
Q1/Q2 2023 
Commission April
2023, complete
October 2023 
April 2023 to
December 2023 
January 2023 to
September 2023 
Complete April 2023 
Complete August
2023 
Complete August
2023
No 
No 
No 
No 
£30k 
£12,000 
£45k split between
Moray Council, HIE
and Scottish
Forestry 
£12,000 in 22/23,
potential for
further appraisal
work in 23/24 
No 
No
Progress
on track
Work package Internal/
External
Timelines Budget
requirement
Page 332

Page 333

9
Development Plan Scheme 2022
Sources and scale of
climate change
emissions and climate
risks to the region 
Heat mapping to
inform potential for
co-locating
developments with
high heat demand
with sources of heat
supply 
Rural Areas 
Carbon and
biodiversity
offsetting
methodologies 
Opportunities for
Aquaculture 
Realise full potential
for electricity and
heat from renewable,
low carbon and zero
emission sources 
Areas of constraint
for green energy 
National waste
management plan* 
Local waste data 
Strategic Flood Risk
Assessment 
Internal 
Internal 
Internal 
Internal and
External 
Internal 
Internal 
Internal with
minor
external
input 
Internal 
Internal 
Internal 
Complete August
2023 
Complete by end July
2023 
Complete September
2023 
Just Transition
funding secured 
Complete August
2023 
Complete by October
2023 
Complete June 2023 
Complete June 2023 
Complete June 2023 
September 2022 to
February 2023 
No 
No 
No 
Complete
September 2023 
No 
No 
Potential spend on
landscape
sensitivity study 
No 
No 
No 
Progress
on track
Work package Internal/
External
Timelines Budget
requirement
Page 333

Page 334

Your place, Your plan, Your future
10
River Basin
Management Plans* 
Buildings at risk
register* 
Wildland/ areas with
wild land quality* 
Data on peat and
carbon rich soils* 
Native Woodland
Survey of Scotland
and Ancient
Woodland Inventory 
Review Tree
Preservation Orders 
Review of areas
designated for their
local nature
conservation
interests 
Coastal evidence and
information- erosion,
coastal change 
Core Paths* 
Landscape Sensitivity
Study, details of wind
turbines and solar
farms and other RE
infrastructure 
Allotments and Food
growing areas 
Internal 
Internal 
Internal 
Internal 
Internal 
Internal 
Internal 
Internal 
Internal 
Internal 
Internal 
Complete by August
2023 
Complete by August
2023 
Complete by August
2023 
Complete by August
2023 
Complete by August
2023 
Report to P&RS
Committee
December 2022 
Complete by
September 2022 
Complete by August
2023 
Complete by
September 2023 
Report to P&RS
Committee 
Q3 2023/24 
Complete by October
2023
No 
No 
No 
No 
No 
No 
No 
No 
No 
£5k 
No 
Progress
on track
Work package Internal/
External
Timelines Budget
requirement
Page 334

Page 335

11
Development Plan Scheme 2022
Sport and Recreation
Strategy 
Details of
infrastructure
capacity and planned
investments,
including
communications,
drainage, water,
energy, healthcare,
education, digital and
grey, green and blue
infrastructure,
drinking water
facilities, sewerage,
gas, electricity
networks 
Learning Estate
Strategy* 
Reflect proposals
from Moray Transport
Strategy* Elgin
Transport Strategy* 
Transport Appraisal
and model 
Transport evidence
baseline-identify
gaps 
Evidence base on
public transport* 
Condition, use and
proposals for
harbours 
TBD 
Internal 
Internal-
Education 
Internal 
External 
Internal 
Internal 
Internal 
TBD 
Complete by
September 2023 
Assess implications
by September 2023 
Complete by
September 2023 
1st stage Complete
by September 2023,
2nd stage timeline to
be confirmed 
Complete by
September 2023 
Complete by
September 2023 
Complete by
September 2023 
TBD 
No 
No 
No 
£250,000 
No 
No 
No 
Progress
on track
Work package Internal/
External
Timelines Budget
requirement
Page 335

Page 336

Your place, Your plan, Your future
12
Travel to work
patterns 
Active travel
networks and data 
Active Travel
Strategy* 
Digital infrastructure
and not spots, gaps in
provision, investment
plans 
Data on low carbon
infrastructure 
Electric Vehicle
Infrastructure
Strategy* 
Engagement re
Evidence report,
Place based issues,
RSS 
How we have sought
views 
How we have invited
LPP and taken
account of registered
LPP 
Public health and
well-being indicators,
health issues such as
obesity, mental
health, heart disease 
Site appraisal
methodology 
Internal 
Internal 
Internal 
External 
Internal 
Internal 
Internal with
minor
external 
Internal 
Internal 
Internal 
Internal
Complete by
September 2023 
Complete by
September 2023 
Complete by
September 2023 
Complete by
September 2023 
Complete by
September 2023 
Complete by
September 2023 
Complete by October
2023 
Complete by January
2023 
Complete by January
2023 
Complete by
September 2023 
Complete September
2023
No 
No 
No 
No 
No 
No 
£5k potential
facilitation 
None 
None 
None 
None 
Progress
on track
Work package Internal/
External
Timelines Budget
requirement
Page 336

Page 337

13
Development Plan Scheme 2022
Evidence from impact
assessments
including carrying
out the Equality,
Fairer Assessment 
Areas of prime
agricultural land* 
High risk
development areas
(HSE)* 
Creative Scotland
plans and local
cultural plans* 
Number and range of
cultural venues and
facilities, including
live music 
LOIP, Community Plan
implications for LDP* 
Draft Evidence Report
chapters sent to
stakeholders. Set out
any areas of dispute
regarding evidence
and areas of
agreement
Report to full Council 
Gatecheck Procedure 
Internal 
Internal 
Internal 
Internal 
Internal 
Internal 
Internal 
Internal 
External-
DPEA 
At Evidence Report
and Proposed Plan
reporting stage 
Complete July 2023 
Complete July 2023 
Complete September
2023 
Complete September
2023 
Complete September
2023 
Send January 2024 
Report to full Council
March 2024 
April 2024 to
December 2024 
None 
None 
None 
None 
None 
None 
None 
None 
Cost of Gatecheck
to be clarified by
Scottish
Government 
Progress
on track
Work package Internal/
External
Timelines Budget
requirement
Page 337

Page 338

Your place, Your plan, Your future
14
Template for
settlement
statements- place
based approach 
Develop local policies
and guidance 
Prepare Delivery Plan 
Draft spatial strategy 
Report proposed plan
to full Council 
12 week consultation 
Prepare schedule 4’s
for Council and
Examination 
Report Schedule 4’s
to Council and
request Examination 
Reporter issues
further information
requests and
convenes hearings if
necessary 
Reporter issues
Examination report
and Plan modified 
Intention to adopt 
Adopt Plan 
Publish Delivery
Programme 
Internal 
Internal 
Internal 
Internal 
Internal 
Internal 
Internal 
Internal 
Internal 
External 
Internal 
Internal 
Internal 
March 2023 
March 2023 to
September 2023 
April to June 2025 
February 2023 to
November 2023 
August 2025 
September to end
November 2025 
December 2025 to
April 2026 
August 2026 
September 2026 to
April 2027 
May/ June2027 
July 2027 
September 2027 
September 2027 
None 
None 
None 
None 
None 
None 
None 
None 
None 
Council required to
pay for cost of
Examination 
None 
None 
None 
Progress
on track
Work package Internal/
External
Timelines Budget
requirement
Page 338

Page 339

15
Development Plan Scheme 2022
APPENDIX 2
Strategic
Environmental
Assessment Scoping
Report 
SEA Draft 
Environmental
Report 
Final Environmental
Report 
Publish post adoption
SEA Statement 
Habitats Regulation
Assessment 
Report RSS to
Committee 
Internal 
Internal 
Internal 
Internal 
Internal 
Internal 
March 2023 
January 2025 
June 2025 
November 2027 
June 2025 
March 2024 
None 
None 
None 
None 
Potential
facilitation of
workshops
Progress
on track
Work package Internal/
External
Timelines Budget
requirement
Item 11
Page 339

Page 340

Your place, Your plan, Your future
16
Participation Statement 
Engagement Outcomes  
l Early meaningful and inclusive engagement meeting National Standards for Engagement
l Youth Engagement linked to the Curriculum for Excellence
l Geographic and demographic spread of engagement
l Spatial outputs from engagement to inform “Place” based plan
l Partnership working to engage beyond Local Development Plan both locally and strategically on
Moray Growth Deal, Regional Spatial Strategy and Locality Plans
l Deliver engagement through a climate change lens
Page 340

Page 341

Evidence Gathering and Evidence Report Stage
Now to September 2023
Methods of
Engagement Online
Website
Social Media
‘Place’ Survey
Open Space online tool
Face to face
Drop in Exhibitions
Mobile events
Community Mapping
Learning Estate Review and PB events
Technology
Game/App development
Mentimetre - surveys, polls,
quizzes
Facilitated Sessions
Local Place Plans
Key Agencies and Internal Stakeholder
workshops 
Elected Members workshops
Development
Working Group
Jointly hosted events
with the Digital
Health Institute
Jointly hosted events
with the Digital
Health Institute
Environment
Working Group
Workshops
Open Space
Strategy
online tool
RSS
LDP
Dedicated
Web page
Support for Plans
(resources permitting)
Drop-in
Exhibitions
LPP’sPlace
Survey
Call for
Sites
Call for
Sites
Community
Mapping Events
Community
Mapping
JCC
event
Housing Needs and
Demand Assessment
Mobile Events in
towns and villages
Embedded in
Youth
Engagement
High School Competition
Explore development of App/Game
with UHI
Learning Estate review events
Youth Facilities participatory
budgeting (PB) events
Mentimetre - polls and surveys
Open Space online tool
Elderly
Children and
Young People
Local Place
Plans
General
Public
People with
Disabilities
Gypsy
Travellers
Parents 
and Carers
Elected
Members
Key Agencies and
Internal
Stakeholders
Community
Councils
LPP’s
Page 341

Page 342

Gatecheck
Apr 24 - Dec 24 Jan 25 - Aug 26 Sept 26 - Apr 27 September 27 Oct 27 Onwards
DeliveryAdoptionExaminationProposed Plan
What engagement we are going to undertake at each stage
Evidence
Gathering
Evidence
Report
Now Mar 24
Engage
Community Mapping
events 
Mobile drop ins 
Joint Community Councils
event 
Call for Sites 
Local Place Plans (LPP’s) 
Open Space Strategy
online tool 
Play Sufficiency
Assessment 
High School Competition 
Game/app 
Development and
Environment workshops 
Sign Off of Evidence
Report
Webpage updates
supported by social
media 
Infographic of key
findings of the Evidence
Report and conclusions
Neighbour Notification 
Drop In Exhibitions to
advise on process for
submitting objections 
Website and social
media campaign to
promote drop in events
Examination webpage
to keep updated on
progress 
Emails to objectors on
progress and process
Statutory Notices 
Website update 
Distribution of copies of
all documents to
libraries 
Consult all agencies
referred to within the
Delivery Programme
Monitoring report
consultation
Inform Consult Inform Inform and 
Consult Consult
Page 342

Page 343

Designed and produced by Environmental Services © The Moray Council 2021
Page 343

Page 344

Page 344

Page 345

REPORT TO: PLANNING AND REGULATORY SERVICES COMMITTEE ON 
20 DECEMBER 2022 
SUBJECT: PLANNING POLICY GUIDANCE – MORAY LOCAL
DEVELOPMENT PLAN 2020 
BY:  DEPUTE CHIEF EXECUTIVE (ECONOMY, ENVIRONMENT AND
FINANCE) 
1. REASON FOR REPORT 
1.1 This report asks the Committee to approve planning policy guidance (PPG) for
Policies PP1 Placemaking, DP1 Development Principles and EP5 Open
Space of the Moray Local Development Plan (MLDP) 2020 in respect of
inclusive and accessible play. 
1.2 This report is submitted to Committee in terms of Section III (E) (2) of the
Council's Scheme of Administration relating to the review and preparation of
Strategic and Local Plans. 
2. RECOMMENDATION 
2.1 It is recommended that the Committee agrees:- 
(i) to approve the planning policy guidance (PPG) for the Moray Local
Development Plan (MLDP) 2020, as set out in Appendix 1; 
(ii) that the PPG will be used as a material consideration in the
determination of planning applications; and 
(iii) to note that this PPG will be combined with the guidance approved
by this Committee in May 2022 into one document. 
3. BACKGROUND 
3.1 The MLDP 2020 was formally adopted on 27 July 2020. At a meeting on 3
June 2020, the Emergency Cabinet agreed that additional policy guidance
would be provided to clarify certain policy aspects of the MLDP 2020 (para 6
of the minute refers). 
Item 12
Page 345

Page 346

3.2 A number of updates covering matters such as placemaking, trees and listed
buildings have been approved by this Committee at its meetings on 15
September 2020 (para 16 of the minute refers), 10 November 2020 (para 10
of the minute refers), 23 March 2021 (para 13 of the minute refers) and 31
May 2022 (para 9 of the minute refers). 
3.3 It has become apparent through the operation of polices that further
clarification is required on what constitutes inclusive and accessible play
areas and equipment. 
4. STATUS 
4.1 The PPG is intended as an evolving technical guide/aid for developers and
officers to be updated as further clarification on policy requirements becomes
evident through the operation of the MLDP 2020 and as such, the guidance is
not publically consulted upon but once agreed, will be used as material
consideration in the determination of planning applications. 
5. INCLUSIVE AND ACCESSIBLE PLAY 
5.1 Policy PP1 requires play areas to be inclusive, providing equipment so that
the facility caters for every child/young person regardless of ability. Policies
DP1 and EP5 requires open space to be accessible for all generations and
mobility (including consideration of gradients and path surfaces) and provide
diverse play facilities for a range of ages. 
5.2 The guidance proposed in APPENDIX I provides clarity on the requirements
for the provision of inclusive and accessible play areas and establishes a
consistent approach to the assessment of such. As well as providing
clarification regarding terminology, the PPG sets out the minimum
requirements for inclusive and wheelchair exclusive play equipment based on
the park hierarchy, as set out on Policy EP5 and the Open Space Strategy
Supplementary Guidance. Clarification is also provided in respect of
accessibility to and from recreational spaces so as to avoid physical barriers
to participation. 
5.3 The PPG provides examples that will assist in the design of play areas and
establishes the requirements for a variety of equipment that meets the needs
of different ages and abilities. Applications will require to be supported by a
statement which demonstrates how the proposed play area meets
requirements in respect of play equipment, types and values. 
5.4 Consultation has been undertaken with ParentAble Moray who were
supportive of the principles of the PPG. Comments provided in relation to
accessible materials and sensory planting have been reflected in the PPG. 
Page 346

Page 347

6. SUMMARY OF IMPLICATIONS 
(a) Corporate Plan and 10 Year Plan (Local Outcomes Improvement
Plan (LOIP))
The MLDP 2020 is a vital aspect in supporting and facilitating the
Council’s priority for economic growth. The Plan also aims to deliver
other key aspects of Moray 2026, including the delivery of affordable
housing and conservation and enhancement of Moray’s high quality and
historic environment. The PPG seeks to support these key aims. 
(b) Policy and Legal
The MLDP is a statutory plan which brings together and helps deliver
key aspects of Moray 2026 and other national and local plans, strategies
and policies. This PPG helps to deliver high quality places that are
inclusive and accessible and is fundamental to achieving both national
and local aspirations. 
(c) Financial implications
None. 
(d) Risk Implications
The PPG provides a clear and consistent approach to the
implementation of MLDP 2020 policies. There is a risk that if the PPG is
not in place then this might inhibit the creation of inclusive and
accessible play areas, which is detrimental to health and wellbeing. 
(e) Staffing Implications
Work on the PPG has been undertaken as part of the workload of
Strategic Planning & Development. 
(f) Property
None. 
(g) Equalities/Socio Economic Impact
The guidance is intended to assist Moray Council in promoting equality
of opportunity on the grounds of disability. In order to ensure that the
PPG reflects this, Officers have consulted with local representatives of
parents with disabled children. An Equality Impact Assessment will be
undertaken as part of the design of new play areas or the upgrading of
existing play areas. 
(h) Climate Change and Biodiversity Impacts
There are no climate change or biodiversity implications arising from this
report. However, as part of embedding climate change principles within
the planning process, there is an expectation for developments to
minimise carbon emissions in their design and construction and be
adaptive to the expected impacts of climate change. 
(i) Consultations
Depute Chief Executive (Economy, Environment and Finance), the Head
of Economic Growth and Development, the Head of Financial Services,
the Legal Services Manager, the Development Management and
Page 347

Page 348

Building Standards Manager, the Open Spaces Manager, the Principle
Climate Change Strategy Officer, the Equal Opportunities Officer and
Lissa Rowan (Committee Services Officer) have been consulted and are
in agreement with the contents of the report. Any comments received
have been incorporated into the report. 
7. CONCLUSION 
7.1 The PPG is an evolving document that is intended to be updated as
further clarification on the interpretation of policies becomes evident
through the operation of the MLDP 2020. 
7.2 The proposed guidance provides clarification on the requirements for
the provision of inclusive and accessible play areas. 
Author of Report: Darren Westmacott, Planning Officer (Strategic Planning
& Development)
Background Papers: 
Ref: 
Page 348

Page 349

Inclusive and Accessible Play 
Play areas in new developments, and their subsequent replacement/upgrading,
must be inclusive and accessible, providing children and young people of different
abilities with equal access to high quality social and play provision. 
Inclusive and Wheelchair Exclusive Play Equipment
At least 50% of play equipment provided in play areas must be to inclusive
standards and integrated throughout the layout. Inclusive means equipment that
is designed to be used by children of all ages and abilities, including those with
disabilities. A variety of equipment must be provided that meets the needs of
different ages, groups and abilities. 
For larger parks, wheelchair exclusive equipment must also be provided. This is
equipment that is designed to be used by those in a wheelchair, either remaining
in the chair or being transferred onto an item of equipment, and can only be used
exclusively by those in a wheelchair (i.e. wheelchair swing). 
Based on the park hierarchy set out in the Open Space Strategy, the minimum
number of pieces of inclusive and wheelchair exclusive play equipment are:- 
Park Hierarchy                Total Pieces        Inclusive           Non            Wheelchair 
of Equipment                                Inclusive          Exclusive
Public Park                                   14                          7                      6                          1
Neighbourhood Park               10                          5                      4                          1
Pocket Park                                   6                           3                      3                          0
NOTE: A two swing set is considered to constitute a single piece of equipment. 
The equipment provided in Public and Neighbourhood Parks must display all of
the differing play values/types set out in the table below. Pocket Parks must
display a minimum of 6 differing play values/types. All parks must provide
opportunities for creative, imaginative and sensory play as well as space for social
interactions. 
Planning Policy Guidance
1
POLICY PP1, DP1 AND EP5
A statement must be provided evidencing how the design and implementation of
the play area meets the equipment and play values/types requirements. It should
be noted that wheelchair swings are excluded from assessment against 'Swinging'. 
Running, skipping and/or hopping             Rocking
Climbing                                                               Rotating or spinning
Swinging                                                              Gliding
Sliding                                                                   Jumping
Balancing                                                             Crawling
In addition to these play equipment requirements, sensory panels and/or
instruments must also be provided in all parks. This is equipment that stimulates
the senses and may be tactile, auditory or visual. Sensory planting is also
encouraged in landscaping proposals. 
Accessibility
Accessibility is defined as surfacing and paths which do not present physical barriers
to participation, including entrances and exits, movement around space and access
to equipment (play and non-play). Proposals for play areas must be located where
paths and recreational spaces are on gradients that are suitably flat. Surfacing, paths
and benches (inclusive and wheelchair-friendly) must be designed to be fully
accessible to people of all ages and abilities.  This means that materials used must
prevent any barriers to access, such as grass matting or wetpour. The use of play bark
chippings and raised play areas will not be acceptable. 
An Equalities Impact Assessment will be undertaken by the Planning Authority as
part of the assessment of play area proposals. The annotated photographs below
provide some advice when designing a play area.
Item 12
Page 349

Page 350

Moray Local Development Plan 2020 2
POLICY PP1, DP1 AND EP5
Good use of colour, utilising accessible materials and providing a variety of equipment.
Good mix of inclusive equipment but could be expanded to cater for all ages.Good mix of equipment for different ages and abilities but on a slope which
impacts on accessibility.
Page 350

Page 351

Planning Policy Guidance
3
POLICY PP1, DP1 AND EP5
Provision of wheelchair exclusive play equipment but not accessible due to lack of
path provision to use equipment.
Provision of inclusive equipment but not accessible due to lack of path provision
to the equipment.
Poor access into play area with no footpath and
inappropriate gradient meaning it is not accessible for
all.
Close proximity of disabled car parking spaces and
accessible path to play area.
Raised play areas and bark chippings are unacceptable
Page 351

Page 352

Page 352