Democracy Spraffa

Supplementary Agenda Document Pack - Planning and Regulatory Services Committee - 25/10/2022

Moray Council · 25 October 2022
Back to Planning and Regulatory Services Committee — 25 October 2022 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

Planning and Regulatory Services Committee 
Tuesday, 25 October 2022 
The undernoted report(s) has been added to the agenda for the meeting of Planning
and Regulatory Services Committee at 09:30, in terms of Section 50B (4)(b) of the
Local Government (Access to Information) Act 1985 by reason of special
circumstances on the Chair accepting the report as urgent business. 
NOTE REFERRED TO:- 
5b. Planning Application - 22/00715/APP
Report by Appointmed Officer  
Installation of an energy storage facility including battery enclosures
power conversion units transformer substations grid connection
infrastructure vehicular access and associated works at Land at Drum
Farm Keith Moray for Renewable Energy Systems Limited  
3 - 48
5c. Planning Application - 22/01208/APP
Report by Appointmed Officer  
Section 42 to amend condition 3 of 17/01003/APP in relation to time
period Meikle Hill Dallas Moray for The Dallas Trust  
49 -
110 
Page 1

Page 2

Page 2

Page 3

WARD 02_17
22/00715/APP
12th May 2022
Installation  of  an  energy  storage  facility  including 
battery enclosures  power  conversion  units 
transformer  substations  grid  connection  infrastructure
vehicular access and associated works at Land At Drum
Farm Keith Moray 
for Renewable Energy Systems Limited
Comments:
 The application is a Major application as the proposal relates to electricity
generation with a capacity of more than 20Mw.
 The application was advertised for neighbour notification purposes.
 No representations have been received.
Procedure:
None. 
Recommendation
Grant Planning Permission - subject to the following:
Conditions/Reasons
1. The development to which this permission relates must be began not later than
the expiration of 5 years beginning with the date on which this permission is
granted.
Reason: The time limit condition is imposed in order to comply with the
requirements of section 58 of the Town and Country Planning (Scotland) Act 1997
as amended.
2. No development shall commence until final details of all the proposed battery
system and storage including the battery enclosure, transformers, grid compliance
equipment, substation building and spares storage container have been submitted
to and agreed in writing by the Planning Authority.  For the avoidance of doubt the
final installations shall not exceed the dimensions shown on approved plans
04872-RES-SUB-DR-PT-003 re v1, 04872-RES-SUB-DR-PT-002 rev 1, 04872-
RES-SUB-DR-PT-001 rev 1, 04872-RES-PCS-DR-PT-001 rev 1 and 04872-RES-
SUB-DR-PT-004 rev 1 the installation shall be finished in white, grey or green.
Thereafter only the approved details shall be implemented.
Item 5b.
Page 3

Page 4

Reason:  To ensure that the development harmonises with its surroundings.   
3. No development shall commence until a pre-construction survey for badgers and
otters, in line with the recommendations contained in section 4.4 of the submitted
report entitled 'Preliminary Ecological Appraisal' by RES dated March 2022, has
been undertaken and a report of survey has been submitted to, and approved in
writing by, the Council, as Planning Authority. The survey shall include mitigation
measures where any impact, or potential impact, on protected species or their
habitats has been identified and a species protection plan. Development and work
shall progress in accordance with any mitigation measures contained within the
approved report of survey and the timescales contained therein. 
Reason: To ensure that the site and its environs are surveyed and the
development does not have an adverse impact on protected species or habitat. 
4. No development shall commence until details including the number, location and
specification of artificial bat and bird roosts to be placed throughout site have been
submitted to and agreed in writing with the Planning Authority.  Thereafter the
approved items shall be provided prior to the first use of the site hereby approved.   
Reason: To secure biodiversity enhancements of the site.   
5. Notwithstanding the submitted details no development shall commence until full
details of the proposed acoustic fence have been submitted to and agreed in
writing by the Planning Authority in consultation with the Environmental Health
Authority.  For the avoidance of doubt a 3m high acoustic barrier shall be installed
in accordance with Section 5 of the noise impact assessment supporting
document by RES, dated 21 April 2022 Ref: 04872-3761753, and titled
"Assessment of Acoustic Impact for the Proposed Drum Farm Energy Storage
Project.", and as detailed on the approved plans 04872-RES-LAY-DR-PT-001 3
and 04872-RES-SEC-DR-PT-002 1. 
Thereafter the approved fence shall be installed prior to the first use of the site
hereby approved and maintained in perpetuity. 
Reason: To protect local residents from noise nuisance due to the use of the
development. 
6. No development shall commence until evidence has been submitted to and
accepted in writing by the Planning Authority to demonstrate that Scottish Water
(protectdwsources@scottishwater.co.uk) have been notified that works are to take
place. 
Reason: To ensure the safeguarding of the drinking water catchment area. 
7. No development shall commence until evidence of a satisfactory Wear and Tear
agreement has been submitted to and agreed in writing by the Planning Authority
in consultation with the Roads Authority.  The scope of the Wear and Tear
Agreement shall be agreed with the Planning Authority in consultation with the
Roads Authority and shall include a condition survey of the network undertaken
Page 4

Page 5

jointly by the developer and a representative from the Council. The survey shall
include the full extent of the agreed construction traffic route(s) (within Moray)
between the site and the ‘A’ class road network. In addition, the Wear and Tear
agreement shall also include condition surveys of all roads identified as
‘unsuitable’ which must be agreed with the Planning Authority in consultation with
the Roads Authority. 
Reason: To mitigate the potential risks from damage to the public road occurring
during the construction phase of the development. 
8. No development shall commence until evidence of a financial guarantee or bond
or suitable equivalent has been put in place to ensure the repair of the public road
serving the site in the event that the developer fails to meet their obligations (as
agreed as part of a Wear and Tear agreement) to maintain the road in a safe
condition during the construction phase of the development and to restore the
road to its pre-development condition within 1 year of the development becoming
operational and has been submitted to and agreed in writing with the Council, as
Planning Authority in consultation with the Roads Authority.  For the avoidance of
doubt the agreement shall cover the section of the U35H Drum-Ardrone Road
from the A96 to the site entrance.   
Reason: To mitigate the potential risks from damage to the public road occurring
during the construction phase of the development. 
9. No development shall commence until a Construction Traffic Management Plan
(CTMP) has been submitted to an agreed in writing by the Planning Authority in
consultation with the Roads Authority.  Thereafter the development shall be
carried out in accordance with the agreed CTMP at all times.  For the avoidance of
doubt the CTMP shall include as a minimum the following information:
   duration of works;
    construction programme;
   parking provision, loading and unloading areas for construction traffic;
   full details of temporary arrangements to safeguard pedestrian movements
during the construction period;
   proposals to safeguard vulnerable pedestrians at and around Keith Primary
School during the construction period;
   full details of any temporary access;
    measures to be put in place to prevent material being deposited on the
public road;
   traffic management measures to be put in place during works including any
specific instructions to drivers; and
   a programme of monitoring for all routes identified within the CTMP during
construction will be required. 
Reason: To ensure an acceptable form of development in terms of the
arrangements to manage traffic during construction works at the site. 
10. No development (except that associated with the visibility splays) shall commence
until: 
Page 5

Page 6

i.  a visibility splay 2.4 metres by 120 metres, with all boundaries set back to a
position behind the required visibility splay, has been provided in both
directions at the access onto the public road; and 
ii.  Thereafter the visibility splay shall be maintained at all times free from any
obstruction exceeding 0.6 metres above the level of the carriageway. 
Reason: To enable drivers of vehicles leaving the site to have a clear view over a
length of road sufficient to allow safe exit, in the interests of road safety for the
proposed development and other road users through the provision of details
currently lacking. 
11. No development (other than that associated with the passing places) shall
commence until two passing places to the Moray Council standards and
specification have been constructed on the U35H Drum - Ardrone Road at the
locations shown on drawing no. 04872-RES-ACC-DR-PT-001 submitted on
22.06.2022. 
Reason: To enable drivers of vehicles to have adequate forward visibility to see
approaching traffic and for two vehicles to safely pass each other ensuring the
safety and free flow of traffic on the public road. 
12. Prior to the first use of the development hereby approved the site entrance and
access track shall be constructed in accordance with approved drawing no.
04872-RES-ACC-DR-PT-002.  
Reason: To ensure acceptable infrastructure at the development access.  
13. No water shall be permitted to drain or loose material be carried onto the public
footway/carriageway. 
Reason: To ensure the safety and free flow of traffic on the public road and
access to the site by minimising the road safety impact from extraneous material
and surface water in the vicinity of the new access. 
14. Construction works (including vehicle movements) associated with the
development audible at any point on the boundary of any noise sensitive dwelling
shall be permitted between 0800 - 1900 hours, Monday to Friday and 0800 - 1300
hours on Saturdays only, and at no other times out with these permitted hours
(including National Holidays) shall construction works be undertaken except
where previously agreed in advance in writing with the Council, as Planning
Authority and where so demonstrated that operational constraints require limited
periods of construction works to be undertaken out with the permitted/stated hours
of working. 
Reason: To protect local residents from noise nuisance in ensuring the
construction phase is restricted within permitted hours to protect local residents
from noise nuisance due to the use of the development. 
15. The rating level of noise associated with the development shall not exceed the
background sound level by more than 5 dB at the nearest noise sensitive dwelling
Page 6

Page 7

which is lawfully existing or has planning permission at the date of this permission.
For the avoidance of doubt the modal background sound level for the daytime
period and night-time period respectively has been determined as an L A 90 of 40
dB and 31 dB, as stated in Section 4 of the noise impact assessment supporting
document by RES, dated 21 April 2022 Ref: 04872-3761753, and titled
"Assessment of Acoustic Impact for the Proposed Drum Farm Energy Storage
Project." The rating level and background sound level associated with this
condition are defined within BS 4142: 2014 + A1:2019 Methods for rating and
assessing industrial and commercial sound.     
Reason: To protect local residents from noise nuisance due to the use of the
development. 
16. The operational site lighting shall be provided in accordance with approved
drawings 04872-RES-LAY-DR-PT-001 Rev3 and 04872-RES-SEC-DR-PT-001,
Rev1, and no other external lighting shall be installed. 
Reason: To protect local residents from light nuisance due to the use of the
development. 
17. The development shall at all times be carried out in accordance with the approved
Construction Environmental Management Plan entitled ‘Drum Farm Battery
Storage Project’ by RES, dated 8 March 2022, Ref: 04872-3704703. 
Reason: To ensure environmental impacts are suitably managed and maintained
during the construction phase. 
18. All landscaping works shall be carried out in accordance with the details shown on
approved plan P22-0056.001 Rev B in the first planting season following the first
operation of the development hereby approved. 
Any trees or plants which (within a period of 5 years from the planting) die, are
removed or become seriously damaged or diseased shall be replaced in the
following planting season with others of similar size, number and species unless
otherwise approved by the Council, as Planning Authority. 
Reason: To ensure that the approved landscaping works are timeously carried
out and properly maintained in a manner which will not adversely affect the
development or amenity and character of the area.       
19. All foul and surface water drainage proposals shall be in accordance with the
submitted report Flood risk Statement and Drainage Impact Assessment, dated 05
May 2022 and approved drawing 04872-RES-LAY-DR-PT-001 rev 3. 
Reason: To ensure that surface water drainage is provided timeously and
complies with the principles of SuDS; in order to protect the water environment. 
Page 7

Page 8

Reason(s) for Decision
The Council’s reason(s) for making this decision are:- 
The proposal accords with the provisions of the development plan and there are no
material considerations that indicate otherwise. 
List of Informatives: 
THE DEVELOPMENT MANAGEMENT & BUILDING STANDARDS MANAGER has
commented that:- 
A Building Warrant may be required for the development. 
SCOTTISH WATER have commented as follows: 
Water Capacity Assessment 
Scottish Water has carried out a Capacity review and we can confirm the
following: 
There is currently sufficient capacity in the HERRICKS WTW 1970 NJ458494
Water Treatment Works to service your development. However, please note that
further investigations may be required to be carried out once a formal application
has been submitted to us. 
Wastewater Capacity Assessment 
There is currently sufficient capacity for a foul only connection in the KEITH
WWTW 1964 NJ434518 Waste Water Treatment works to service your
development. However, please note that further investigations may be required to
be carried out once a formal application has been submitted to us. 
Please Note
The applicant should be aware that we are unable to reserve capacity at our water
and/or waste water treatment works for their proposed development. Once a
formal connection application is submitted to Scottish Water after full planning
permission has been granted, we will review the availability of capacity at that time
and advise the applicant accordingly. 
Drinking Water Protected Areas
A review of our records indicates that the proposed activity falls within a drinking
water catchment where a Scottish Water abstraction is located. Scottish Water
abstractions are designated as Drinking Water Protected Areas (DWPA) under
Article 7 of the Water Framework Directive. The River Deveron supplies Turriff
Water Treatment Works (WTW) and it is essential that water quality and water
quantity in the area are protected. In the event of an incident occurring that could
affect Scottish Water we should be notified immediately using the Customer
Helpline number 0800 0778 778. 
The activity is a sufficient distance from the intake that it is likely to be low risk,
however care should be taken, and water quality protection measures must be
Page 8

Page 9

implemented. 
It would also be useful to be kept informed of when work commences on the site
and further information on how to do so is detailed below. 
Scottish Water have produced a list of precautions for a range of activities. This
details protection measures to be taken within a DWPA, the wider drinking water
catchment and if there are assets in the area. Please note that site specific risks
and mitigation measures will require to be assessed and implemented. These
documents and other supporting information can be found on the activities within
our catchments page of our website at www.scottishwater.co.uk/slm 
We welcome receipt of this notification about the proposed activity within a
drinking water catchment where a Scottish Water abstraction is located. 
The fact that this area is located within a drinking water catchment should be
noted in documentation. Also anyone working on site should be made aware of
this during site inductions and we would also like to take the opportunity, to
request that in advance of any works commencing on site, Scottish Water is
notified at protectdwsources@scottishwater.co.uk  so we can make our
operational teams aware there will be activity taking place in the catchment. 
Surface Water
For reasons of sustainability and to protect our customers from potential future
sewer flooding, Scottish Water will not accept any surface water connections into
our combined sewer system. 
There may be limited exceptional circumstances where we would allow such a
connection for brownfield sites only, however this will require significant
justification from the customer taking account of various factors including legal,
physical, and technical challenges. 
In order to avoid costs and delays where a surface water discharge to our
combined sewer system is anticipated, the developer should contact Scottish
Water at the earliest opportunity with strong evidence to support the intended
drainage plan prior to making a connection request. We will assess this evidence
in a robust manner and provide a decision that reflects the best option from
environmental and customer perspectives. 
General notes:
Scottish Water asset plans can be obtained from our appointed asset plan
providers: 
Site Investigation Services (UK) Ltd
Tel: 0333 123 1223
Email: sw@sisplan.co.uk
www.sisplan.co.uk 
Scottish Water’s current minimum level of service for water pressure is 1.0 bar or
10m head at the customer’s boundary internal outlet. Any property which cannot
Page 9

Page 10

be adequately serviced from the available pressure may require private pumping
arrangements to be installed, subject to compliance with Water Byelaws. If the
developer wishes to enquire about Scottish Water’s procedure for checking the
water pressure in the area, then they should write to the Customer Connections
department at the above address. 
If the connection to the public sewer and/or water main requires to be laid through
land out-with public ownership, the developer must provide evidence of formal
approval from the affected landowner(s) by way of a deed of servitude. 
Scottish Water may only vest new water or waste water infrastructure which is to
be laid through land out with public ownership where a Deed of Servitude has
been obtained in our favour by the developer. 
The developer should also be aware that Scottish Water requires land title to the
area of land where a pumping station and/or SUDS proposed to vest in Scottish
Water is constructed. 
Please find information on how to submit application to Scottish Water at our
Customer Portal. 
Next Steps:
All Proposed Developments 
All proposed developments require to submit a Pre-Development Enquiry (PDE)
Form to be submitted directly to Scottish Water via our Customer Portal prior to
any formal Technical Application being submitted. This will allow us to fully
appraise the proposals. 
Where it is confirmed through the PDE process that mitigation works are
necessary to support a development, the cost of these works is to be met by the
developer, which Scottish Water can contribute towards through Reasonable Cost
Contribution regulations. 
Non Domestic/Commercial Property: 
Since the introduction of the Water Services (Scotland) Act 2005 in April 2008 the
water industry in Scotland has opened to market competition for non-domestic
customers. All Non-domestic Household customers now require a Licensed
Provider to act on their behalf for new water and waste water connections. Further
details can be obtained at www.scotlandontap.gov.uk 
Trade Effluent Discharge from Non Dom Property: 
Certain discharges from non-domestic premises may constitute a trade effluent in
terms of the Sewerage (Scotland) Act 1968. Trade effluent arises from activities
including; manufacturing, production and engineering; vehicle, plant and
equipment washing, waste and leachate management. It covers both large and
small premises, including activities such as car washing and launderettes.
Activities not covered include hotels, caravan sites or restaurants. 
Page 10

Page 11

If you are in any doubt as to whether the discharge from your premises is likely to
be trade effluent, please contact us on 0800 778 0778 or email
TEQ@scottishwater.co.uk using the subject “Is this Trade Effluent?". Discharges
that are deemed to be trade effluent need to apply separately for permission to
discharge to the sewerage system. The forms and application guidance notes can
be found here. 
Trade effluent must never be discharged into surface water drainage systems as
these are solely for draining rainfall run off. 
For food services establishments, Scottish Water recommends a suitably sized
grease trap is fitted within the food preparation areas, so the development
complies with Standard 3.7 a) of the Building Standards Technical Handbook and
for best management and housekeeping practices to be followed which prevent
food waste, fat oil and grease from being disposed into sinks and drains. 
The Waste (Scotland) Regulations which require all non-rural food businesses,
producing more than 50kg of food waste per week, to segregate that waste for
separate collection. The regulations also ban the use of food waste disposal units
that dispose of food waste to the public sewer. Further information can be found at
www.resourceefficientscotland.com 
THE SCOTTISH ENVIRONMENT PROTECTION AGENCY has commented that:- 
Details of regulatory requirements and good practice advice, for example in
relation to private drainage, can be found on the regulations section of our
website. If you are unable to find the advice you need for a specific regulatory
matter, please contact a member of the local compliance team at:
gs@sepa.org.uk 
SSE has commented that:- 
It is recommended that the Applicant refers to the relevant guidance and
requirements put in place by the Health and Safety Executive in relation to
clearance requirements for works adjacent to overhead electricity line. We refer
the Applicant to the HSE guidance note: GS6 (4th Edition) ‘Avoiding danger from
overhead powerlines.’ 
We would also request that the Applicant notifies SSEN Asset Management at the
following email address, Transmission.Asset.Management@sse.com, at least 30
days’ prior to commencing works on site to allow us to advise on the required
safety precautions for construction. 
LIST OF PLANS AND DRAWINGS SHOWING THE DEVELOPMENT
Reference No. Version No. Title/Description
04872-RES-ACC-DR-PT-002  Proposed site entrance
04872-RES-ACC-DR-PT-001  Proposed passing place
04872-RES-MAP-DR-XX-002 2 Location plan
Page 11

Page 12

04872-RES-SEC-DR-PT-002 1 Acoustic fencing
04872-RES-SUB-DR-PT-001 1 Substation buildings
04872-RES-SUB-DR-PT-003 1 Auxiliary transformer
04872-RES-BAT-DR-PT-001 1 Battery enclosure
P22-0056.001 B Detailed landscape proposal
04872-RES-SUB-DR-PT-002 1 Grid compliance equipment
04872-RES-LAY-DR-PT-001 3 Infrastructure layout plan
04872-RES-SEC-DR-PT-001 1 Lighting and CCTV column
04872-RES-PCS-DR-PT-001 1 PCS and Transformer
04872-RES-MAP-DR-XX-001 2 Site location plan
04872-RES-SUB-DR-PT-004 1 Spares storage container 
04872-RES-PRO-DR-PT-001     2 Proposed Site Elevations sheet 1 of 2
04872-RES-PRO-DR-PT-001     2 Proposed Site Elevations sheet 2 of 2 
Page 12

Page 13

Plans, drawings and other material submitted to the local authority
are protected by the Copyright, Designs and Patents Act 1988
(section 47). You may only use material which is downloaded and/
or printed for consultation purposes, to compare current
applications with previous schemes and to check whether
developments have been completed in accordance with approved
plans.
Further copies must not be made without the prior permission of
the copyright owner.
Maps shown in the Planning Committee Report can only be used
for the purposes of the Planning Committee. Any other use risks
infringing Crown Copyright and may lead to prosecution or civil
proceedings. Maps produced within this Planning Committee
Report can only be reproduced with the express permission of the
Moray Council and other Copyright holders. This permission must
be granted in advance.
PLANNING APPLICATION
COMMITTEE SITE PLAN
Site Address:
LAND AT DRUM FARM
KEITH
Planning Application Ref Number: 
22/00715/APP
Location Plan
Applicant Name: 
Renewable Energy Systems Limited 
Page 13

Page 14

Site Location Plan
Page 14

Page 15

Site Plan
Page 15

Page 16

Proposed site elevations
Page 16

Page 17

Proposed site elevations
Page 17

Page 18

Photo location plan
16/01664/APP
Page 18

Page 19

Photo 1
16/
Page 19

Page 20

Photo 2
Page 20

Page 21

Photo 3
Page 21

Page 22

Page 22

Page 23

PLANNING APPLICATION: 22/00715/APP 
In the event that a recommendation on this planning application is overturned the
Committee is reminded of the advice contained on the front page of the agenda for
Reports on Applications 
1. THE PROPOSAL 
   The application seeks planning permission for an energy storage facility
including battery enclosures, transformers, substations, grid connection
infrastructure and a spares/maintenance container along with access,
external lighting, secure fencing and landscaping.
   The compound will be enclosed by 3m high timber board fence which will
secure the site and act as acoustic barrier.
   Landscaping is proposed on the edge of the site outwith the compound
itself.  This includes the provision of earth bunds on the north west and
south west boundaries of the site on which planting will be provided.
   The application is supported by an Acoustic Assessment, Construction
Environmental Management Plan (CEMP), Flood Risk and Drainage
Impact Assessment, Historic Environment Assessment, Planning, Design
and Access Statement, Pre-application consultation (PAC) Report,
Preliminary Ecological Appraisal, Transport Statement, Landscape and
Visual Assessment. 
2. THE SITE 
   The site is located to the south east of the substation on Westerton Road,
Keith. 
   The site area is 2.06ha.
   The site is on the eastern edge of Keith and is bounded by fields to the
north, south and west. The land is largely flat and open. 
   Access is proposed from the U35H to the north of the site and west of
Drum Farm. 
   There are overhead lines close to the south eastern boundary of the site.
   The access track and the path which runs south west from the site
towards Keith are core paths (CP-KT07).
   The site is immediately adjacent to the Countryside Around Towns buffer
identified around Keith. A section of the existing track running for
approximately 150m from the public road encroaches on the CAT.   
3. HISTORY 
21/01786/SCN - Development of a battery energy storage system on Land at
Drum Farm Keith - Screening opinion issued 11 November 2021. 
Page 23

Page 24

21/01750/PAN - Installation of a battery energy storage system (BESS)
including siting of battery containers power conversion units and transformers a
substation hardstanding area fencing vehicular access grid connection and
ancillary works on Land At Drum Farm Keith – reported to Planning and
Regulatory Services Committee on 9 December 2021.  Members had no
comments to make.  Following the submission of the PAN an online public
event was held on 30 November 2021 and information was made available on
the developer’s website with details of how to make comments between 30
November 2021 and 7 January 2022.  Nobody attended the online event and
comments were made in response to the information displayed on the website. 
Both Strathisla and Keith Community Councils were directly invited to make
comment but neither did.   
4. POLICY - SEE APPENDIX 
5. ADVERTISEMENTS 
5.1 Advertised for neighbour notification 24 May 2022. 
6. CONSULTATIONS 
Keith Community Council:  No comment. 
Strathisla Community Council:  No comment. 
Strategic Planning & Development:  No objection.  There is a locational need
for this development and it can be integrated into the landscape.  The proposal
complies with Policies PP3, DP1, DP5, DP9, EP2, EP12 and EP14. 
Transportation:  No objection subject to the provision of a road bond and
conditions relation to the formation of the access, the provision of passing
places and the submission of a Construction Phase Management Plan (CPMT).   
Environmental Health:  No objection subject to conditions relating to
construction hours, noise and an acoustic barrier, the implementation of the
CEMP and external lighting. 
Archaeology:  No objection. 
Moray Flood Risk Management:  No objection. 
Contaminated Land:  No objection. 
Access Manager:  No objection. 
Developer Obligations:  None sought. 
SEPA:  No objection. 
Page 24

Page 25

Scottish Water:  No objection. 
SSE:  No objection. 
7. OBJECTIONS-REPRESENTATIONS 
No representations received.   
8. OBSERVATIONS 
8.1 Section 25 of the 1997 Act as amended requires applications to be determined
in accordance with the development plan i.e. the adopted Moray Local
Development Plan 2020 (MLDP) unless material considerations indicate
otherwise. The main planning issues are considered below: 
8.2 Duration of Consent 
The applicant has requested that the application be granted subject to a
condition that allows 5 years for development to commence.  Since 1 October
the planning authority is required to impose conditions regarding the time
period for commencement (previously it was a statutory obligation highlighted in
the accompanying notes) and has the power to vary the time period.  In this
case the applicant has advised that the upgrades are required to the
transmission network and the adjoining substation before the proposal can be
connected.  In order to retain their grid connection offer the applicant must
secure planning permission.    Given the circumstances outlined by the
developer a 5 year consent is considered to be acceptable in this instance.   
8.3 Compliance with Renewable Energy Policy (DP9) 
Policy DP9 is supportive of renewable energy development where they meet
the criteria set out in the policy.  The proposal will not adversely impact on built
or natural heritage features and therefore complies with DP9 (a) (i) in that it is
compliant with policies to safeguard and enhance the built and natural
environment.  The development will take place on farm land but it is not
identified as Prime Agricultural Land therefore part (ii) is also complied with.
Part (iii) requires that the development must avoid or address significant
adverse impact identified in the policy.  In so far as the issues identified in part
(iii) apply to this development the proposal is considered to comply.   The
development is sited on farm land on the outskirts of Keith.  The site abuts the
Countryside Around Town (CAT) around Keith as identified in the MLDP 2020.  
A small section of the track running for approximately 150m from the public
road towards the main part of the site is just within the CAT. Given that the only
works proposed here relate to the upgrading of the existing track this is
considered to be acceptable.  The Supporting Statement makes clear that there
is a strong locational need for the siting proposed.  The site is close to the
existing substation in the town which is essential for the development to limit
electrical losses during transmission and ensure the maximum efficiency of the
system.  It is also highlighted that the electrical substation has a viable import
and export capacity to service the development.   The locational justification is
acknowledged.  The siting in close proximity to the existing substation also
provides context for the development and reduces the overall visual and
Page 25

Page 26

landscape impact as the substation is already a dominant feature in the
landscape.   A Landscape and Visual Impact Assessment has been submitted
which concludes that the impact on landscape character would not be
significant as the surrounding landscape is already influenced by similar land
uses.  It also notes that the proposed planting will reduce the impact on
landscape features.  It is recognised that there will be some major visual
impacts particularly for users of the surrounding core path and some nearby
houses but the report highlights that these views will be read in the context of
the existing substation and overhead lines with the proposed planting further
reducing the impact. The final battery design is subject to further detailed
design and will not be finalised until closer to the commencement of
construction. It is noted from the submitted plans that the battery infrastructure
including the enclosures themselves and the transformer may be finished in
white, grey or green.  While a muted colour would be preferable to better
integrate into the surrounding landscape the agent advises that this may not be
possible as the technology often requires lighter colours for cooling and it is not
possible to paint or clad them.  A condition is therefore recommended requiring
final details of all the battery installations including colours to be submitted for
final approval. 
8.3.1 The landscape and visual impacts are overall found to be localised and limited
in nature.  The existing infrastructure and the proposed landscaping works will
reduce the overall impact and ensure that the level of change is acceptable in
this setting.     
8.3.2 It is noted below that the noise impact can be effectively mitigated and
measures are recommended to ensure that the development does not
adversely impact on protected species.   
8.3.3 The development will help towards meeting net-zero targets and contribute
towards greater energy security.  The proposal is appropriately located
alongside existing infrastructure and is considered to comply with policy DP9.   
8.4 Landscaping (EP5)
A detailed landscaping plan has been provided with the application.  This
includes the provision of two earth bunds along the north and western
boundaries of the site.  These will be a maximum of 1.5m high with trees
planted on them.   An area in the south eastern corner of the site is set aside
for low level shrubs and planting to avoid conflict with the existing overhead
lines.   Hedging and tree planting is also proposed to the north east and south
east. Wildflower planting will be provided throughout.  The planting will provide
both screening and setting for the development.  It will soften the overall impact
of the development and help to integrate it into the wider landscape.  It will also
provide biodiversity enhancement by providing increased foraging and shelter
options.  Conditions are recommended to ensure that the planting is timeously
provided and adequately maintained.  The landscaping is appropriate to the
character of this development and will help to create an attractive and
appealing place in accordance with policy EP5.    
8.5 Noise, Light & Pollution (EP14)
A Noise Impact Assessment has been produced in support of the application. 
This concludes that with appropriate mitigation including a 3m high acoustic
Page 26

Page 27

fence around the compound the impact will be low during the daytime.  There
will be a greater impact at night but this will not be adverse.  The Environmental
Health Manager is content with the findings of the report and has
recommended conditions in line with the conclusions it contains.  These seek to
control the construction working hours, the operational noise levels and the
provision of the recommended acoustic fence.  Details of a proposed fence are
included with the application but these are presented as indicative details only
and do not include all the information required to ensure that the fence is of a
suitable construction to mitigate noise as intended.  It is therefore
recommended that final details are sought by condition.  The recommended
conditions will ensure that noise associated with the development will not cause
significant pollution and therefore the proposal complies with policy EP14. 
8.5.1 The site plan shows the location of lighting columns.  The Environmental Health
Manager is content with the proposals provided that the no additional external
lighting is provided.  Subject to this recommended condition the development
will not cause significant light pollution and as such complies with policy EP14.   
8.5.2 A further condition is recommended requiring the submitted CEMP to be
implement at all times.  This will ensure that adequate pollution control
measures are in place during the construction phase.   
8.5.3 Subject to the proposed mitigation and recommended conditions the proposals
comply with policy EP14.   
8.6 Access (DP1) 
The site is accessed via an existing track that joins the public road to the north
of the site.  The existing track which is a Core Path will be upgraded (see
below) to facilitate the development.  The Transportation Manager has no
objection to the use of this access subject to conditions to ensure that the
junction with the public road is formed to an acceptable standard and to secure
adequate visibility splays at the access.  Vehicles will arrive via the Drum Farm
– Ardrone Road.  Two additional passing places are being sought on this road
in locations that have been agreed with the Transportation Manager.  A Wear
and Tear agreement will also be put in place along with a road bond to ensure
that any damage to the public road arising from the development is rectified
and there are sufficient funds in place to cover this.  It is also recommended
that a Construction Phase Traffic Management Plan (CPTMP) is sought by
condition.   The Transportation Manager has no objections to the proposals
subject to the conditions as recommended.  The recommended conditions will
ensure that the development provides safe entry and exit and adequately
mitigates impact on the adjoining public road and therefore the proposal
complies with policies DP1 (ii) (a) and (c).   
8.7 Impact on the Core Path (DP1) 
A core path (CP-KT07) runs to the north and to the west of the site.  The
section that runs north from the main part of the site towards the public road will
become the access to the site.  The track is currently an unmade grass track
although it appears to be well used.  The proposal is to improve the track to an
unbound granular finish and install filter drains along either side.  It will remain a
core path and continue to be accessible.  The Access Manager has no
Page 27

Page 28

objection.  The development will enhance the core path and ensure that access
is maintained.  The proposal therefore complies with policy DP1 (ii)(a).   
8.8 Drainage (EP12)
The development is supported by a drainage statement.  Surface water will be
dealt with by means of an attenuation basin along the south eastern boundary
of the site with a discharge to the burn to the south.  Moray Flood Risk
Management are content with the proposals but a condition is recommended to
ensure that the proposals are implemented in full and in a timeous manner.   
The proposals will ensure that surface water is dealt with in a sustainable
manner that has a neutral effect on flooding and as such the proposals accord
with policy EP12.   
8.9 Impact on Species and Biodiversity (EP1 & EP2) 
A preliminary ecological survey has been carried out.  The survey found
evidence of use by badgers but no setts were identified.  The survey also noted
evidence of otter activity and while the site offers limited opportunities for otter
shelter there is potential for the works to impact on otters.  The survey advises
that additional pre-start surveys for badger and otter should be carried out and
a condition is recommended to address this.  The recommended condition will
ensure that any required mitigation is put in place and there is no adverse
impact on protected species.  Subject to condition the proposal accords with
policy EP1. 
8.9.1 It is noted above that landscaping is to be provided around the site which will
contribute to biodiversity enhancement of the site.  The native hedgerows, tree
planting and wildflower mix will provide additional foraging and nesting
opportunities.  The planning statement makes reference to the installation of
bat and bird boxes but these features are not identified on the submitted plans. 
A condition is therefore recommended to ensure to that these features are
provided to maximise the biodiversity benefits of the development.  The
proposals will ensure that the development will enhance the biodiversity value
of the site and ensure that these features are a fully integrated part of the
development.  Subject to condition the proposal complies with policy EP2.   
8.10 Impact on SSE Infrastructure
There is SSE infrastructure in the vicinity of the development.  The landscaping
has been designed to account for this.  SSE have requested that they are
notified that work is to be undertaken and an informative note to that effect is
recommended.   
Conclusion
The development will contribute to meeting national carbon reduction targets and will also
increase energy security.  There is a site specific justification for development in this
location as it is close to a substation that has capacity to connect to the grid.  The site can
be suitably serviced and any suitable mitigation is proposed in relation to potential impacts
on noise or protected species.  The landscape and visual impact is considered to be
acceptable in this setting for other similar developments already dominate the landscape. 
The proposal is in accordance with policy and it is recommended for approval.   
Page 28

Page 29

REASON(S) FOR DECISION
The Council’s reason(s) for making this decision are: - 
The proposal accords with the provisions of the development plan and there are no
material considerations that indicate otherwise. 
Author/Contact
Officer:
Lisa MacDonald           
Senior Planning Officer
Ext: 01343 563479 
Beverly Smith
Development Management & Building Standards Manager
Page 29

Page 30

Page 30

Page 31

APPENDIX 
POLICY 
Adopted Moray Local Development Plan 2015 
Proposed Moray Local Development Plan 2020 
PP1 PLACEMAKING 
a) Development must be designed to create successful, healthy places that support
good physical and mental health, help reduce health inequalities, improve people's
wellbeing, safeguard the environment and support economic development.   
b) A Placemaking Statement is required for residential developments of 10 units and
above to be submitted with the planning application to articulate how the
development proposal addresses the requirements of policy PP1 Placemaking and
other relevant LDP policies and guidance.  The Placemaking Statement must include
sufficient information for the council to carry out a Quality Audit.  Where considered
appropriate by the council, taking account of the nature and scale of the proposed
development and of the site circumstances, this shall include a landscaping plan, a
topographical survey, slope analysis, site sections, 3D visualisations, a Street
Engineering Review and a Biodiversity Plan.  The Placemaking Statement must
demonstrate how the development promotes opportunities for healthy living and
working. The landscape plan must set out details of species type, size, timescales for
planting and maintenance. 
c) To create successful, healthy places residential developments of 10 units and above
must comply with Scottish Government policy Creating Places and Designing Streets
and must incorporate the following fundamental principles: 
(i) Character and Identity
• Create places that are distinctive to prevent homogenous 'anywhere'
development;
• Provide a number of character areas reflecting site characteristics that
have their own distinctive identity and are clearly distinguishable;
• Provide distinctiveness between and in each character area through a
combination of measures including variation in urban form, street
structure/network, architecture and masonry, accent features (such as
porches), surrounds and detailing, materials (buildings and surfaces),
colour, boundary treatments, hard/soft landscaping and a variety of
approaches to tree species and planting that emphasises the hierarchy of
open spaces and streets within a cohesive design strategy for the whole
development;
• Distinctiveness must be reinforced along main thoroughfares, open
spaces and places where people may congregate such as
shopping/service centres;
• Retain, incorporate and/or respond to relevant elements of the landscape
such as topography and planted features, natural and historic
environment, and propose street naming (in residential developments of
20 units and above, where proposed names are to be submitted with the
planning application) to retain and enhance local associations;
Page 31

Page 32

(ii) Healthier, Safer Environments
• Designed to prevent crime, fear of crime and anti-social behaviour with
good levels of natural surveillance and security using treatments such as
low boundary walls, dual frontages (principal rooms) and well-lit routes to
encourage social interaction.  Unbroken high boundary treatments such
as wooden fencing and blank gables onto routes, open spaces and
communal areas will not be acceptable. 
• Designed to encourage physical exercise for people of all abilities. 
• Create a distinctive urban form with landmarks, key buildings, vistas,
gateways and public art to provide good orientation and navigation
through the development. 
• Provide a mix of compatible uses, where indicated within settlement
statements, integrated into the fabric of buildings within the street. 
• Prioritise pedestrians and cyclists by providing a permeable movement
framework that incorporates desire lines (including connecting to and
upgrading existing desire lines) and is fully integrated with the surrounding
network to create walkable neighbourhoods and encourage physical
activity. 
• Integrate multi- functional active travel routes, green and open space into
layout and design, to create well connected places that encourage
physical activity, provide attractive spaces for people to interact and to
connect with nature. 
• Create safe streets that influence driver behaviour to reduce vehicle
speeds that are appropriate to the local context such as through shorter
streets, reduced visibility and varying the building line. 
• Provide seating opportunities within streets, paths and open spaces for all
generations and mobility's to interact, participate in activity, and rest and
reflect. 
• Provide for people with mobility problems or a disability to access
buildings, places and open spaces. 
• Create development with public fronts and private backs. 
• Maximise environmental benefits through the orientation of buildings,
streets and open space to maximise the health benefits associated with
solar gain and wind shelter. 
(iii) Housing Mix
• Provide a wide range of well integrated tenures, including a range of
house types and plot sizes for different household sizes, incomes and
generations and meet the affordable and accessible requirements of
policy DP2 Housing.
Page 32

Page 33

• All tenures of housing should have equal access to amenities, greenspace
and active travel routes. 
(iv) Open Spaces/Landscaping
• Provide accessible, multi-functional open space within a clearly defined
hierarchy integrated into the development and connected via an active
travel network of green/blue corridors that are fully incorporated into the
development and to the surrounding area, and meet the requirements of
policy EP5 Open Space and the Open Space Strategy Supplementary
Guidance and Policy EP12 Managing the Water Environment and
Drainage Impact Assessment for New Developments Supplementary
Guidance.
• Landscaped areas must provide seasonal variation, (mix of planting and
colour) including native planting for pollination and food production.
• Landscaping areas that because of their size, shape or location would not
form any useable space or that will not positively contribute to the
character of an area will not contribute to the open space requirements of
Policy EP4 Open Space.
• Semi-mature tree planting and shrubs must be provided along all routes
with the variety of approaches reflecting and accentuating the street
hierarchy.
• Public and private space must be clearly defined.
• Play areas (where identified) must be inclusive, providing equipment so
the facility is for every child/young person regardless of ability and
provided upon completion of 50% of the character area.
• Proposals must provide advance landscaping identified in site
designations and meet the quality requirements of policy EP5 Open
Space.
• Structural landscaping must incorporate countryside style paths (such as
bound or compacted gravel) with waymarkers.
•  Maintenance arrangements for all paths, trees, hedging, shrubs, play/
sports areas, roundabouts and other open/ green spaces and blue/green
corridors must be provided. 
v) Biodiversity
• Create a variety of high quality multi- functional green/blue spaces and
networks that connect people and nature, that include trees, hedges and
planting to enhance biodiversity and support habitats/wildlife and comply
with policy EP2 Biodiversity and Geodiversity and EP5 Open Space.
• A plan detailing how different elements of the development will contribute
to supporting biodiversity must be included in the design statement
submitted with the planning application.
• Integrate green and blue infrastructure such as swales, permeable paving,
SUDS ponds, green roofs and walls and grass/wildflower verges into
streets, parking areas and plots to sustainably address drainage and
flooding issues and enhance biodiversity from the outset of the
development.
• Developments must safeguard and where physically possible extend or
enhance wildlife corridors and green/blue networks and prevent
fragmentation of existing habitats. 
Page 33

Page 34

(vi) Parking
• Car parking must not dominate the streetscape to the front or rear of
properties.  On all streets a minimum of 50% of car parking must be
provided to the side or rear and behind the building line with a maximum
of 50% car parking within the front curtilage or on street, subject to the
visual impact being mitigated by hedging, low stone boundary walls or
other acceptable treatments that enhance the streetscape.
• Provide semi-mature trees and planting within communal private and
public/visitor parking areas and on-street parking at a maximum interval of
4 car parking spaces.
• Secure and covered cycle parking and storage, car sharing spaces and
electric car charging points must be provided in accordance with policy
DP1 Development Principles.
• Parking areas must use a variation in materials to reduce the visual
impact on the streetscene. 
(vii) Street Layout and Detail
• Provide a clear hierarchy of streets reinforced through street width,
building density and street and building design, materials, hard/soft
landscaping and a variety of approaches to tree planting and shrubs.
• Streets and connecting routes should encourage walking and cycling over
use of the private car by providing well connected, safe and appealing
routes.
• Design junctions to prioritise pedestrians, accommodate active travel and
public transport and service/emergency vehicles to reflect the context and
urban form and ensure that the street pattern is not standardised.  
• Dead-end streets/cul-de-sacs will only be selectively permitted such as on
rural edges or where topography, site size, shape or relationship to
adjacent developments prevent an alternative more permeable layout.
These must be short, serving no more than 10 units and provide walking
and cycling through routes to maximise connectivity to the surrounding
area.
• Where a roundabout forms a gateway into, or a landmark within, a town
and/or a development, it must be designed to create a gateway feature or
to contribute positively to the character of the area.
• Design principles for street layouts must be informed by a Street
Engineering Review (SER) and align with Roads Construction Consent
(RCC) to provide certainty that the development will be delivered as per
the planning consent. 
(d) Future masterplans will be prepared through collaborative working and in partnership
between the developer and the council for Lochyhill (Forres), Barhill Road (Buckie),
Elgin Town Centre/Cooper Park, Elgin North East, Clarkly Hill, Burghead and West
Mosstodloch.  Masterplans that are not prepared collaboratively and in partnership
with the council will not be supported.  Masterplans that are approved will be
Supplementary Guidance to the Plan.¬¬¬ 
(e) Proposals for sites must reflect the key design principles and safeguard or enhance
the green networks set out in the Proposals Maps and Settlement Statements. 
Alternative design solutions may be proposed where justification is provided to the
planning authority's satisfaction to merit this. 
Page 34

Page 35

PP2  SUSTAINABLE ECONOMIC GROWTH
Development proposals which support the Moray Economic Strategy to deliver
sustainable economic growth will be supported where the quality of the natural and built
environment is safeguarded, there is a clear locational need and all potential impacts can
be satisfactorily mitigated. 
PP3  INFRASTRUCTURE & SERVICES
Development must be planned and co-ordinated with infrastructure to ensure that places
function properly and proposals are adequately served by infrastructure and services.   
a) In relation to infrastructure and services developments will be required to provide the
following as may be considered appropriate by the planning authority, unless these
requirements are considered not to be necessary: 
i)  Education, Health, Transport, Sports and Recreation and Access facilities in
accord with Supplementary Guidance on Developer Obligations and Open
Space. 
ii)  Green infrastructure and network requirements specified in policy EP5 Open
Space, Town and Village Maps and, contained within Supplementary Guidance
on the Open Space Strategy, Masterplans and Development Briefs. 
iii)  Mitigation/modification to the existing transport network (including road and rail)
to address the impact of the proposed development in terms of safety and
efficiency.  This may include but not be limited to passing places, road
widening, junction enhancement, bus stop infrastructure, and drainage
infrastructure.  A number of potential road and transport improvements are
identified and shown on the Town and Village Maps as Transport Proposals
(TSP's) including the interventions in the Elgin Transport Strategy. These
requirements are not exhaustive and do not pre-empt any measures which may
result from the Transport Assessment process. 
iv)  Electric car charging points must be provided at all commercial and community
parking facilities.  Access to charging points must also be provided for
residential properties, where in-curtilage facilities cannot be provided to any
individual residential property then access to communal charging facilities
should be made available.  Access to other nearby charging facilities will be
taken into consideration when identifying the need for communal electric
charging points. 
v)  Active Travel and Core Path requirements specified in the Council's Active
Travel Strategy and Core Path Plan. 
vi)  Safe transport and access routes linking to existing networks and mitigating the
impacts of development off-site. 
vii)  Information Communication Technology (ICT) and fibre optic broadband
connections for all premises unless justification is provided to substantiate it is
technically unfeasible. 
Page 35

Page 36

viii)  Foul and surface water drainage, including Sustainable Urban Drainage
Systems (SUDS), including construction phase SUDS. 
ix)  Measures that implement the waste management hierarchy as defined in the
Zero Waste Plan for Scotland including the provision of local waste storage and
recycling facilities designed into the development in accord with policy PP1
Placemaking.  For major applications a site waste management plan may be
required to ensure that waste minimisation is achieved during the construction
phase. 
x)  Infrastructure required to improve or increase capacity at Water Treatment
Works and Waste Water Treatment Works will be supported subject to
compliance with policy DP1. 
xi) A utilities plan setting out how existing and new utility (including gas, water,
electricity pipelines and pylons) provision has been incorporated into the layout
and design of the proposal.  This requirement may be exempted in relation to
developments where the council considers it might not be appropriate, such as
domestic or very small scale built developments and some changes of use. 
b)  Development proposals will not be supported where they:
i)  Create new accesses onto trunk roads and other main/key routes (A941 & A98)
unless significant economic benefits are demonstrated or such access is
required to facilitate development that supports the provisions of the
development plan. 
ii)  Adversely impact on active travel routes, core paths, rights of way, long
distance and other access routes and cannot be adequately mitigated by an
equivalent or better alternative provision in a location convenient for users. 
iii)  Adversely impact on blue/green infrastructure, including green networks
important for wildlife unless an equivalent or better alternative provision will be
provided. 
iv)  Are incompatible with key waste sites at Dallachy, Gollanfield, Moycroft and
Waterford and would prejudice their operation. 
v)  Adversely impact on community and recreational sites, buildings or
infrastructure including CF designations and cannot be adequately mitigated. 
vi)  Adversely impact on flood alleviation and mitigation infrastructure. 
vii)  Compromise the economic viability of bus or rail facilities.   
c)  Harbours 
Development within and diversification of harbours to support their sustainable
operation will be supported subject to compliance with other policies and settlement
statements. 
d)  Developer Obligations 
Developer obligations will be sought to mitigate any measurable adverse impact of a
development proposal on local infrastructure, including education, healthcare,
Page 36

Page 37

transport (including rail), sports and recreational facilities and access routes. 
Obligations will be sought to reduce, eliminate or compensate for this impact.
Developer obligations may also be sought to mitigate any adverse impacts of a
development, alone or cumulatively with other developments in the area, on the
natural environment. 
Where necessary obligations that can be secured satisfactorily by means of a
planning condition attached to planning permission will be done this way.  Where this
cannot be achieved, the required obligation will be secured through a planning
agreement in accordance with Circular 3/2012 on Planning Obligations.   
Developer obligations will be sought in accordance with the Council's Supplementary
Guidance on Developer Obligations.  This sets out the anticipated infrastructure
requirements, including methodology and rates.   
Where a developer considers that the application of developer obligations renders a
development commercially unviable a viability assessment and 'open-book
accounting' must be provided by the developer which Moray Council, via the District
Valuer, will verify, at the developer's expense.  Should this be deemed accurate then
the Council will enter into negotiation with the developer to determine a viable level
of developer obligations.   
The Council's Developer Obligations Supplementary Guidance provides further detail
to support this policy. 
DP1 DEVELOPMENT PRINCIPLES 
This policy applies to all development, including extensions and conversions and will be
applied reasonably taking into account the nature and scale of a proposal and individual
circumstances. 
The Council will require applicants to provide impact assessments in order to determine
the impact of a proposal. Applicants may be asked to determine the impacts upon the
environment, transport network, town centres, noise, air quality, landscape, trees, flood
risk, protected habitats and species, contaminated land, built heritage and archaeology
and provide mitigation to address these impacts. 
Development proposals will be supported if they conform to the relevant Local
Development Plan policies, proposals and additional guidance, meet the following criteria
and address their individual and cumulative impacts: 
(i) Design
a) The scale, density and character must be appropriate to the surrounding area
and create a sense of place (see Policy PP1) and support the principles of a
walkable neighbourhood. 
b) The development must be integrated into the surrounding landscape which will
include safeguarding existing trees and undertaking replacement planting to
include native trees for any existing trees that are felled, and safeguarding any
notable topographical features (e.g. distinctive knolls), stone walls and existing
water features by avoiding channel modifications and culverting. A tree survey
and tree protection plan must be provided with planning applications for all
Page 37

Page 38

proposals where mature trees are present on site or that may impact on trees
outwith the site. The strategy for new tree provision should follow the principles
of the "Right Tree in the Right Place". 
c) Make provision for new open space and connect to existing open space under
the requirements of Policy EP5 and provide details of the future maintenance of
these spaces. A detailed landscape plan must be submitted with planning
applications and include information about green/blue infrastructure, tree
species, planting, ground/soil conditions, and natural and man-made features
(e.g. grass areas, wildflower verges, fencing, walls, paths, etc.). 
d) Demonstrate how the development will conserve and enhance the natural and
built environment and cultural heritage resources, retain original land contours
and integrate into the landscape. 
e) Proposals must not adversely impact upon neighbouring properties in terms of
privacy, daylight or overbearing loss of amenity. 
f)  Proposals do not result in backland development or plots that are subdivided by
more than 50% of the original plot.  Sub-divided plots must be a minimum of
400m2, excluding access and the built-up area of the application site will not
exceed one-third of the total area of the plot and the resultant plot density and
layout reflects the character of the surrounding area. 
g)  Pitched roofs will be preferred to flat roofs and box dormers are not acceptable. 
h)  Existing stone walls on buildings and boundaries must be retained. 
Alterations and extensions must be compatible with the character of the
existing building in terms of design, form, choice of materials and positioning
and meet all other relevant criteria of this policy. 
i)  Proposals must orientate and design buildings to maximise opportunities for
solar gain. 
j)  All developments must be designed so as to ensure that all new buildings avoid
a specified and rising proportion of the projected greenhouse gas emissions
from their use (calculated on the basis of the approved design and plans for the
specific development) through the installation and operation of low and zero-
carbon generating technologies. 
(ii) Transportation
a) Proposals must provide safe entry and exit from the development, including the
appropriate number and type of junctions, maximise connections and routes for
pedestrians and cyclists, including links to active travel and core path routes,
reduce travel demands and ensure appropriate visibility for all road users at
junctions and bends. Road, cycling, footpath and public transport connections
and infrastructure must be provided at a level appropriate to the development
and connect people to education, employment, recreation, health, community
and retail facilities. 
b) Car parking must not dominate the street scene and must be provided to the
side or rear ¬and behind the building line. Maximum (50%) parking to the front
Page 38

Page 39

of buildings and on street may be permitted provided that the visual impact of
the parked cars is mitigated by hedging or low stone boundary walls. Roadways
with a single carriageway must provide sufficient off road parking to avoid
access routes being blocked to larger service vehicles and prevent parking on
pavements. 
c) Provide safe access to and from the road network, address any impacts on
road safety and the local road, rail and public transport network. Any impacts
identified through Transport Assessments/ Statements must be identified and
mitigated. This may include but would not be limited to, passing places, road
widening, junction improvements, bus stop infrastructure and drainage
infrastructure. A number of potential mitigation measures have been identified
in association with the development of sites and the most significant are shown
on the Proposals Map as TSP's. 
d) Provide covered and secure facilities for cycle parking at all flats/apartments,
retail, community, education, health and employment centres. 
e) Garages and parking provision must be designed to comply with Moray Council
parking specifications see Appendix 2. 
f)  The road layout must be designed to allow for the efficient mechanical
sweeping of all roadways and channels, paviors, turning areas and junctions.
The road layout must also be designed to enable safe working practices,
minimising reversing of service vehicles, with hammerheads minimised in
preference to turning areas such as road stubs or hatchets, and to provide
adequate space for the collection of waste and movement of waste collection
vehicles. 
g) The road and house layout in urban development should allow for communal
refuse collection points where the design does not allow for individual storage
within the curtilage and / or collections at kerbside. Communal collection points
may either be for the temporary storage of containers taken by the individual
householder or for the permanent storage of larger containers. The
requirements for a communal storage area are stated within the Council's
Kerbside Collection Policy, which will be a material consideration. 
h) Road signs should be minimised designed and placed at the back of footpaths
to reduce street clutter, avoid obstructing pedestrian movements and
safeguarding sightlines; 
i)  Within communal parking areas there will be a requirement for electric car
charging points. Parking spaces for car sharing must be provided where a need
is identified by the Transportation Manager. 
(iii) Water environment, pollution, contamination
a) Acceptable water and drainage provision must be made, including the use of
sustainable urban drainage systems (SUDS) for dealing with surface water
including temporary/ construction phase SUDS (see Policy EP12). 
b) New development should not be located in areas at flood risk or increase
vulnerability to flooding (see Policy EP12). Exceptions to this would only be
Page 39

Page 40

considered in specific circumstances, e.g. extension to an existing building or
change of use to an equal or less vulnerable use. Where this exception is
applied the proposed development must include resilience measures such as
raised floor levels and electrical sockets. 
c) Proposals must avoid major hazard sites and address any potential risk of
pollution including ground water contamination in accordance with recognised
pollution prevention and control measures. 
d) Proposals must protect and wherever practicable enhance water features
through for example naturalisation of watercourses by introducing a more
natural planform and removing redundant or unnecessary structures. 
e) Proposals must address and sufficiently mitigate any contaminated land issues. 
f)  Make acceptable arrangements for waste collection and management and
encourage recycling. 
g) Avoid sterilising significant workable reserves of minerals, prime agricultural
land or productive forestry. 
h)  Proposals must avoid areas at risk of coastal erosion and coastal change. 
DP9 RENEWABLE ENERGY 
a) All Renewable Energy Proposals
All renewable energy proposals will be considered favourably where they meet the
following criteria: 
i) They are compliant with policies to safeguard and enhance the built and natural
environment; 
ii) They do not result in the permanent loss or permanent damage of prime
agricultural land; 
iii) They avoid or address any unacceptable significant adverse impacts including: 
• Landscape and visual impacts.
• Noise impacts.
• Air quality impacts.
• Electromagnetic disturbance.
• Impact on water environment.
• Impact on carbon rich soils and peat land hydrology.
• Impact on woodland and forestry interests.
• Traffic impact -mitigation during both construction and operation.
• Ecological Impact.
• Impact on tourism and recreational interests. 
In addition to the above criteria, detailed assessment of impact will include
consideration of the extent to which the proposal contributes to renewable energy
generation targets, its effect on greenhouse gas emissions and net economic impact,
including socio-economic benefits such as employment. 
Page 40

Page 41

b) Onshore wind turbines
In addition to the assessment of the impacts outlined in part a) above, the following
considerations will apply: 
i) The Spatial Framework 
Areas of Significant Protection (Map 2): where the Council will apply significant
protection and proposals may be appropriate in circumstances where any
significant effects on the qualities of these areas can be substantially overcome
by siting, design and other mitigation. 
Areas with Potential (Map 1): where proposals are likely to be acceptable
subject to Detailed Consideration. 
ii)     Detailed Consideration 
The proposal will be determined through site specific consideration of the
following on which further guidance will be set out in supplementary guidance
and as informed by the landscape capacity study: 
Landscape and visual impact:
• the landscape is capable of accommodating the development without
unacceptable significant adverse impact on landscape character or visual
amenity.
• the proposal is appropriate to the scale and character of its setting,
respects the main features of the site and the wider environment and
addresses the potential for mitigation. 
Cumulative impact
• unacceptable significant adverse impact from two or more wind energy
developments and the potential for mitigation is addressed. 
Impact on local communities
• the proposal addresses unacceptable significant adverse impact on
communities and local amenity including the impacts of noise, shadow
flicker, visual dominance and the potential for associated mitigation. 
Other
• the proposal addresses unacceptable significant adverse impacts arising
from the location within an area subject to potential aviation and defence
constraints including flight paths and aircraft radar.
• the proposal avoids or adequately resolves other impacts including on the
natural and historic environment, cultural heritage, biodiversity, forest and
woodlands and tourism and recreational interests - core paths, visitor
centres, tourist trails and key scenic routes.
• the proposal addresses any physical site constraints and appropriate
provision for decommissioning and restoration. 
iii) Extensions and Repowering of Existing Wind Farms 
The proposal will be determined through assessment of the details of the
proposal against Part a) and Parts b) (i) and (ii) above.  Detailed assessment of
impact will include consideration of the extent to which:
Page 41

Page 42

• the proposal, for extensions, impacts on the existing wind farm(s) setting
and the ability to sit in the landscape on its own should the existing wind
farm be decommissioned before the extension.
• the proposal, for repowering, makes use of existing infrastructure and
resources, where possible, and limits the need for additional footprint. 
c) Biomass
Proposals for the development of commercial biomass will be supported if the
following criteria are met. 
• Applicants must confirm which form of biomass will fuel the plant and if a
mixture of biomass is proposed then what percentage split will be attributed to
each fuel source.
• Proposals must demonstrate that they have taken account of the amount of
supply fuel over the life of the project.
• When considering wood biomass proposals, the scale and location of new
development is appropriate to the volume of local woodfuel available. Sources
of fuel must be identified and must be sustainable.
• The location must have suitable safe access arrangements and be capable of
accommodating the potential transport impacts within the surrounding roads
network.
• A design statement must be submitted, which should include photomontages
from viewpoints agreed by the Council.
• There must be a locational justification for proposals outwith general
employment land designations. The proposed energy use, local heat users and
connectivity of both heat users and electricity networks must be detailed.
Proposals which involve potential or future heat users will not be supported
unless these users can be brought online in conjunction with the operation of
the plant.
• Details of the predicted energy input and output from the plant demonstrating
the plant efficiency and utilisation of heat must be provided.
• Where necessary, appropriate structural landscaping must be provided to
assist the development to integrate sensitively. 
The criteria set out in relation to all renewable energy proposals (part a) must also be
met. 
The Council will consult with Scottish Forestry to help predict potential woodfuel
supply projections in the area. 
d) Heat
Where a heat network exists or is planned, proposals should include infrastructure to
allow connection to that network. 
Where no heat network is present or planned: 
• Proposals should consider the feasibility for the creation of or connection to a
heat network.
• Proposals should safeguard piperuns within the development, to its curtilage,
for future connection to a heat network.
• Proposals should consider the provision of energy centres, or the reservation of
land for an energy centre to facilitate future connection to a heat network.
Page 42

Page 43

Proposals for new development will be compared with the Scotland Heat Map to
identify if it could make use of an existing heat supply or provide excess heat to heat
users.  This will be the case until the Council has concluded work on identifying
where heat networks, heat storage and energy centres exist or would be appropriate
in the plan area, at which point reference to that work should be made. 
Developments which have a high heat demand are encouraged to co-locate with
sources of heat supply. 
Where heat networks are not viable, proposals should include the use of
microgeneration technologies and heat recovery associated with individual
properties, unless demonstrating this is unnecessary or unviable. 
The criteria set out in relation to all renewable energy proposals (part a) must also be
met. 
EP1 NATURAL HERITAGE DESIGNATIONS
a) European Site designations
Development likely to have a significant effect on a European Site and which is not
directly connected with or necessary to the conservation management of that site
must be subject to an appropriate assessment of the implications for its conservation
objectives. Proposals will only be approved where the appropriate assessment has
ascertained that there will be no adverse effect on the integrity of the site. 
In exceptional circumstances, proposals that could affect the integrity of a European
Site may be approved where: 
i) There are no alternative solutions, and
ii) There are imperative reasons of over-riding public interest including those of a
social or economic nature, and
iii) Compensatory measures are provided to ensure that the overall coherence of
the Natura network is protected. 
For European Sites hosting a priority habitat or species (as defined in Article 1 of the
The Conservation (Natural Habitat & c.) Regulations 1994), prior consultation with
the European Commission via Scottish Ministers is required unless the imperative
reasons of overriding public interest relate to human health, public safety or
beneficial consequences of primary importance to the environment. 
b) National designations 
Development proposals which will affect a National Park, National Scenic Area
(NSA), Site of Special Scientific Interest (SSSI) or National Nature Reserve will only
be permitted where:
i) The objectives of designation and the overall integrity of the area will not be
compromised; or
ii) Any significant adverse effects on the qualities for which the site has been
designated are clearly outweighed by social, environmental or economic
benefits of national importance. 
Page 43

Page 44

c) Local Designations 
Development proposals likely to have a significant adverse effect on Local Nature
Reserves, wildlife sites or other valuable local habitats will be refused unless it can
be demonstrated that;
i) Public benefits clearly outweigh the nature conservation value of the site, and
ii) There is a specific locational requirement for the development, and
iii) Any potential impacts can be satisfactorily mitigated to conserve and enhance
the site's residual conservation interest. 
d) European Protected Species 
European Protected Species are identified in the Habitats Regulations 1994 (as
amended in Scotland). Where a European Protected Species may be present or
affected by development or activity arising from development, a species survey and
where necessary a Species Protection Plan should be prepared to accompany the
planning application, to demonstrate how the Regulations will be complied with. The
survey should be carried out by a suitably experienced and licensed ecological
surveyor. 
Proposals that would have an adverse effect on European Protected Species will not
be approved unless; 
• The need for development is one that is possible for SNH to grant a license for
under the Regulations (e.g. to preserve public health or public safety).
• There is no satisfactory alternative to the development.
• The development will not be detrimental to the maintenance of the favourable
conservation status of the species. 
e) Other protected species 
Wild birds and a variety of other animals are protected under domestic legislation,
such as the Wildlife and Countryside Act 1981 (as amended in Scotland by the
Nature Conservation (Scotland) Act 2004 and the Wildlife and Natural Environment
(Scotland) Act 2011), Protection of Badgers Act 1992 and Marine (Scotland) Act
2010. Where a protected species may be present or affected by development or
activity arising from development, a species survey and where necessary a Species
Protection Plan should be prepared to accompany the planning application to
demonstrate how legislation will be complied with. The survey should be carried out
by a suitably experienced ecological surveyor, who may also need to be licensed
depending on the species being surveyed for. 
Proposals which would have an adverse effect on badgers or their setts must be
accompanied by a Badger Protection Plan demonstrating how impacts will be
avoided, mitigated, minimised or compensated for. 
EP2 BIODIVERSITY
All development proposals must, where possible, retain, protect and enhance features of
biological interest and provide for their appropriate management.  Development must
safeguard and where physically possible extend or enhance wildlife corridors and
green/blue networks and prevent fragmentation of existing habitats. 
Development should integrate measures to enhance biodiversity as part of multi-functional
spaces/ routes. 
Page 44

Page 45

Proposals for 4 or more housing units or 1000 m2 or more of commercial floorspace must
create new or, where appropriate, enhance natural habitats of ecological and amenity
value. 
Developers must demonstrate, through a Placemaking Statement where required by
Policy PP1 which incorporates a Biodiversity Plan, that they have included biodiversity
features in the design of the development. Habitat creation can be achieved by providing
links into existing green and blue networks, wildlife friendly features such as wildflower
verges and meadows, bird and bat boxes, amphibian friendly kerbing, wildlife crossing
points such as hedgehog highways and planting to encourage pollination, wildlife friendly
climbing plants, use of hedges rather than fences, incorporating biodiversity measures into
SUDS and retaining some standing or lying dead wood, allotments, orchards and
woodlands. 
Where development would result in loss of natural habitats of ecological amenity value,
compensatory habitat creation will be required where deemed appropriate. 
EP12 MANAGEMENT AND ENHANCEMENT OF THE WATER ENVIRONMENT
a) Flooding
New development will not be supported if it would be at significant risk of flooding
from any source or would materially increase the possibility of flooding elsewhere.
For development at or near coastal locations, this includes consideration of future
flooding that may be caused by sea level rise and/or coastal change eroding existing
natural defences in the medium and long term. 
Proposals for development in areas considered to be at risk from flooding will only be
permitted where a flood risk assessment to comply with the recommendations of
Scottish Planning Policy and to the satisfaction of Scottish Environment Protection
Agency and the Council is provided by the applicant. 
There are different levels of flood risk assessment dependent on the nature of the
flood risk. The level of assessment should be discussed with the Council prior to
submitting a planning application. 
Level 1 -  a flood statement with basic information with regard to flood risk.
Level 2 -  full flood risk assessment providing details of flood risk from all sources,    
results of hydrological and hydraulic studies and any appropriate
proposed mitigation. 
Assessments must demonstrate that the development is not at risk of flooding and
would not increase the probability of flooding elsewhere.  Level 2 flood risk
assessments must be signed off by a competent professional.  The Flood Risk
Assessment and Drainage Impact Assessment for New Development Supplementary
Guidance provides further detail on the information required. 
Due to continuing changes in climatic patterns, the precautionary principle will apply
when reviewing any application for an area at risk from inundation by floodwater.
Proposed development in coastal areas must consider the impact of tidal events and
wave action when assessing potential flood risk. 
The following limitations on development will also be applied to take account of the
degree of flooding as defined in Scottish Planning Policy;
Page 45

Page 46

a) In areas of little to no risk (less than 0.1%), there will be no general constraint to
development.
b) Areas of low to medium risk (0.1% to 0.5%) will be considered suitable for most
development. A flood risk assessment may be required at the upper end of the
probability range i.e. (close to 0.5%) and for essential civil infrastructure and the
most vulnerable uses. Water resistant materials and construction may be
required. Areas within this risk category will generally not be suitable for civil
infrastructure. Where civil infrastructure must be located in these areas or is
being substantially extended, it should be designed to be capable of remaining
operational and accessible during flooding events.
c) Areas of medium to high risk (0.5% or above) may be suitable for:
• Residential, institutional, commercial and industrial development within
built up areas provided that flood protection measures to the appropriate
standard already exist and are maintained, are under construction, or are
a planned measure in a current flood management plan.
• Essential infrastructure within built up areas, designed and constructed to
remain operational during floods and not impede water flow.
• Some recreational, sport, amenity and nature conservation uses, provided
appropriate evacuation procedures are in place, and
• Employment related accommodation e.g. caretakers or operational staff. 
Areas within these risk categories will generally not be suitable for the following
uses and where an alternative/lower risk location is not available¬¬;
• Civil infrastructure and most vulnerable uses.
• Additional development in undeveloped and sparsely developed areas,
unless a location is essential for operational reasons e.g. for navigation
and water based recreation, agriculture, transport or utilities infrastructure
(which should be designed to be operational during floods and not impede
water flows).
• New caravan and camping sites. 
Where development is permitted, measures to protect against or manage flood risk
will be required and any loss of flood storage capacity mitigated to achieve a neutral
or better outcome. Water resistant materials and construction must be used where
appropriate. Land raising and elevated buildings on structures such as stilts are
unlikely to be acceptable. 
b) Surface Water Drainage: Sustainable Urban Drainage Systems (SUDS)
Surface water from development must be dealt with in a sustainable manner that has
a neutral effect on flooding or which reduces the risk of flooding. The method of
dealing with surface water must also avoid pollution and promote habitat
enhancement and amenity. All sites must be drained by a sustainable drainage
system (SUDS) designed in line with current CIRIA guidance. Drainage systems
must contribute to enhancing existing "blue" and "green" networks while contributing
to place-making, biodiversity, recreational, flood risk and climate change objectives. 
When considering the appropriate SUDS design for the development the most
sustainable methods, such as rainwater harvesting, green roofs, bio retention
systems, soakaways, and permeable pavements must be considered first.  If it is
necessary to include surface water attenuation as part of the drainage system, only
above ground attenuation solutions will be considered, unless this is not possible
due to site constraints.  
Page 46

Page 47

If below ground attenuation is proposed the developer must provide a robust
justification for this proposal.  Over development of a site or a justification on
economic grounds will not be acceptable.  When investigating appropriate SUDS
solutions developers must integrate the SUDS with allocated green space, green
networks and active travel routes to maximise amenity and biodiversity benefits. 
Specific arrangements must be made to avoid the issue of permanent SUDS
features becoming silted-up with run-off. Care must be taken to avoid the spreading
and/or introduction of invasive non-native species during the construction of all
SUDS features.  On completion of SUDS construction the developer must submit a
comprehensive Operation and Maintenance Manual.  The ongoing maintenance of
SUDS for all new development will be undertaken through a factoring agreement, the
details of which must be supplied to the Planning Authority.   
All developments of less than 3 houses or a non-householder extension under 100
square metres must provide a Drainage Statement.  A Drainage Assessment will be
required for all developments other than those identified above. 
c) Water Environment
Proposals, including associated construction works, must be designed to avoid
adverse impacts upon the water environment including Ground Water Dependent
Terrestrial Ecosystems and should seek opportunities for restoration and/or
enhancement, if appropriate. The Council will only approve proposals impacting on
water features where the applicant provides a report to the satisfaction of the Council
that demonstrates that any impact (including cumulative) on water quality, water
quantity, physical form (morphology), river hydrology, sediment transport and
erosion, coastal processes (where relevant) nature conservation (including protected
species), fisheries, recreational, landscape, amenity and economic and social impact
can be adequately mitigated. 
The report must consider existing and potential impacts up and downstream of the
development particularly in respect of potential flooding. The Council operates a
presumption against the culverting of watercourses and any unnecessary
engineering works in the water environment. 
A buffer strip of at least 6 metres between any new development and all water
features is required and should be proportional to the bank width and functional river
corridor (see table on page 96). This must achieve the minimum width within the
specified range as a standard, however, the actual required width within the range
should be calculated on a case by case basis by an appropriately qualified individual.
These must be designed to link with blue and green networks, including appropriate
native riparian vegetation and can contribute to open space requirements. 
Developers may be required to make improvements to the water environment as part
of the development. Where a Water Framework Directive (WFD)¬ water body
specific objective is within the development boundary, or in proximity, developers will
need to address this within the planning submission through assessment of potential
measures to address the objective and implementation, unless adequate justification
is provided. Where there is no WFD objective the applicant should still investigate
the potential for watercourse restoration along straightened sections or removal of
redundant structures and implement these measures where viable.
Page 47

Page 48

Width to watercourse Width of buffer strip (either side)
(top of bank) 
Less than 1m  6m
1-5m  6-12m
5-15m  12-20m
15m+  20m+ 
The Flood Risk Assessment and Drainage Impact Assessment for New Development
Supplementary Guidance provides further detail on the information required to
support proposals. 
EP14 POLLUTION, CONTAMINATION & HAZARDS
a)  Pollution
Development proposals which may cause significant air, water, soil, light or noise
pollution or exacerbate existing issues must be accompanied by a detailed
assessment report on the levels, character and transmission of the potential pollution
with measures to mitigate impacts. Where significant or unacceptable impacts
cannot be mitigated, proposals will be refused.   
b) Contamination
Development proposals on potentially contaminated land will be approved where
they comply with other relevant policies and; 
i) The applicant can demonstrate through site investigations and risk assessment,
that the site is in a condition suitable for the proposed development and is not
causing significant pollution of the environment; and
ii) Where necessary, effective remediation measures are agreed to ensure the
site is made suitable for the new use and to ensure appropriate disposal and/ or
treatment of any hazardous material. 
c) Hazardous sites
Development proposals must avoid and not impact upon hazardous sites or result in
public safety concerns due to proximity or use in the vicinity of hazardous sites. 
Page 48

Page 49

WARD 01_17 
22/01208/APP
23rd August 2022
Section 42 to amend condition 3 of 17/01003/APP in
relation to time period Meikle Hill Dallas Moray 
for The Dallas Trust 
Comments: 
 The proposal is a major planning application.
 The application was advertised for neighbour notification purposes.
 No representations have been received. 
Procedure: 
 None. 
Recommendation 
Grant Planning Permission - subject to the following: 
Conditions/Reasons 
1. The development as hereby granted shall begin no later than 5 years from the
date of this permission; and for the purposes of this permission, the development
as hereby granted shall be that as described and approved under formal decision
notice 14/01087/EIA dated 25 June 2015 i.e. for six (6) wind turbines only, to be
undertaken in accordance with the turbine model design and site infrastructure
layout arrangements as shown on amended drawings 60289428-ENG -003 Rev C
and -002 Rev C as received from the applicant on 1 April 2015 which forms part of
the development as approved under application 14/01087/EIA and the request to
vary Condition 20 has been removed. 
Reason: In accordance with Section 58 (4) of the Town and Country Planning
(Scotland) Act 1997 taking into account the nature and requirements for
implementation of the development and to ensure an acceptable form of
development whereby all turbines as proposed are located within an Area of
Search and in the Upland Moorland and Forestry Landscape Character Type/Area
with greatest potential for windfarm development and in the Upland Moorland and
Forestry/Upland Plateau with Forest (10) Landscape Character Type wherein
there is limited scope to accommodate this large turbine typology, and in the
interests of the appearance and amenity of the surrounding locality including
account of landscape and visual effects of the development, and in accordance
with the applicant's agent's submitted particulars (email 18 August 2017 refers). 
Item 5c.
Page 49

Page 50

2. Except where otherwise provided for, or required by the terms of this permission,
the permission hereby granted relates strictly to the dimensions and specifications
of the turbine design (including make, model, design, power rating and sound
power level of the turbine to be used) and site layout infrastructure arrangements
as provided for in the application and, with the exception of any micro-siting of
turbines and other infrastructure, to all other mitigation measures as identified in
the Environmental Statement and subsequent Addendum I and II of the
Environmental Statement (as included within application 14/01087/EIA), and any
amendment thereof shall be subject to the express prior written approval of the
Council, as planning authority. 
Reason: To ensure the development is carried out in accordance with the
submitted application particulars and that the merits and implications of any
proposed micro-siting or other variation to the development as approved can be
assessed in terms of impact on landscape and visual, cultural and natural heritage
and/or other environmental interests, etc. 
3. The permission as hereby granted is for a period of 40 years from the date when
electricity is first exported from any wind turbine within the development to the
electricity grid network (First Export Date) and written confirmation of this First
Export Date shall be provided to the Council, as planning authority within one
month thereof.  Within 12 months of the expiry of this period the wind turbines and
ancillary equipment shall be dismantled to ground level and removed from the site
and the land shall be restored in accordance with the details agreed under
condition 5 below. 
Reason: To define the duration of the permission and enable a review and; where
required, a re-assessment of the environmental and other impacts of the
development. 
4. The applicant/developer/wind turbine operator shall, after the First Export Date,
record information continuously regarding the monthly supply of electricity to the
national grid from each turbine within the development hereby granted and retain
the information for a period of at least 24 months. The information shall be made
available to the Council, as planning authority within one month of any request
being made. 
In the event that any wind turbine(s) installed and commissioned fail(s) to supply
electricity on a commercial basis to the grid for a continuous period of 6 months,
or is no longer required, the turbine(s) in question shall be deemed to have
ceased to be required. Under such circumstances, the wind turbine(s) along with
any ancillary equipment, fixtures and fittings no longer required in connection with
the retained turbines shall, within 3 months of the end of the said continuous six
month period or when ceasing to be no longer required, be dismantled and
removed from the site and the surrounding land shall be re-instated in accordance
with a re-instatement scheme including specification of all works and timescale for
re-instatement which shall previously have been submitted to and approved by the
Council, as planning authority. 
Reason: To ensure that any redundant or non-functioning wind turbine(s) is/are
Page 50

Page 51

removed from the site in the interests of public safety, amenity and environmental
protection and to ensure acceptable arrangements for the re-instatement of the
ground are provided. 
5. No development shall commence until: 
a) a draft Restoration and Decommissioning Plan for the site has been
submitted to and approved in writing by the Council, as planning authority in
consultation with SEPA, SNH and/or other agencies as appropriate; and 
b)  thereafter, and not later than 12 months prior to the expiry of this permission
or decommissioning of the development, whichever is the sooner, a detailed
Restoration and Decommissioning Plan, based upon (the principles of the
approved draft Plan shall be submitted to and approved by the Council, as
planning authority in consultation with SEPA, SNH and/or other agencies as
appropriate. The Plan shall include provision for all turbines and ancillary
infrastructure and equipment (including all buildings and structures,
hardstandings and tracks, etc.) to be decommissioned, de-energised, and
dismantled to ground level and removed from the site together with the
arrangements to retain any access tracks and other infrastructure on the site,
the treatment of disturbed ground surfaces, the management and timing of
all proposed works, environmental management provisions including traffic
and noise management plans to address issues likely to arise during the
decommissioning period and provisions for the restoration and aftercare of
the site; and 
Thereafter, the development shall be decommissioned and the site restored in
accordance with the approved plan details. 
Reason: To ensure the re-instatement of the site in an acceptable and timeous
manner with all wind turbines and associated development removed from the site
in the interests of safety, environmental protection, amenity and appearance of the
site upon the surrounding area. 
6. Prior to the development commencing, details shall be submitted to and approved
in writing by the Council, as planning authority regarding evidence of a bond or
other similar financial provision to be put in place to cover all decommissioning
and site restoration costs on the expiry of the permission (Condition 5) or where all
6 turbines cease to be required (Condition 4) or where works other than the
erection of turbines have been undertaken but no turbines are erected on the site
(for example, in the event that no Scheme is agreed/implemented (Condition 25),
whichever is the sooner. The required bond or equivalent shall: 
a)  be based on the Restoration and Decommissioning Plan (as required by
Condition 5); 
b)  include documentary evidence to demonstrate that the amount of the bond
or financial provision is sufficient to meet the full estimated costs of
decommissioning, including dismantling, removal, disposal, site restoration,
remediation and all other incidental works and professional costs; and 
c) include details to ensure that the proposed financial arrangements will be
maintained and be subject to periodic review throughout the lifetime of the
development. The review period shall be not less than 5 yearly intervals from
commencement of the development, or such other period as may be agreed
Page 51

Page 52

in writing with the Council, as planning authority and the findings of the
review shall be submitted to and approved by the Council, as planning
authority. 
Thereafter, the development shall not commence until written evidence has been
provided to the Council, as planning authority to confirm that the approved bond or
financial provision arrangement has been put in place. 
Reason: To ensure that sufficient funds are available to address the expected full
costs of decommissioning and re-instatement and restoration of the site. 
7. No development shall commence until details have been submitted to and
approved by the Council, as planning authority in consultation with SNH, SEPA
and other agencies where appropriate regarding; 
a)  confirmation of the make, model, design, power rating and sound power
levels of the turbines to be used; 
b)  the external colour and/or finish of the turbines including towers, nacelles
and blades which shall be non-reflective, semi-matt pale grey; 
c) together with details including further landscape and visual impact
information to demonstrate that they will not adversely affect the landscape
and visual character, integrity and amenity of the site or the surrounding
area, the location, design specifications and external material finishes and
colour of any external wind turbine transformer kiosk, unless otherwise
located within the tower of the wind turbine; 
d)  for the substation compound, the design external appearance and material
finishes and colour of all proposed buildings and structures to be erected,
stationed or installed within the compound area together with the finalised
site layout arrangements, including the external appearance, dimensions and
surfacing materials for the compound area, any walls, paths or other
proposed/required ancillary infrastructure to be provided, any
required/proposed external switch gear infrastructure to be located within the
compound, the arrangements for access and parking and disposal of foul
and surface water from the compound area, and all required/proposed
landscaping to be provided around the compound or elsewhere within the
site to screen and/or mitigate the landscape and visual impact of the
compound and its infrastructure therein; 
e)  excluding the requirement for compensatory planting (see Condition 28) and
for all other required/proposed landscaping requirements throughout the site,
a landscape scheme (see Condition 9); 
f)  the location(s) and design specifications for all required/proposed upgraded
existing and new watercourse crossings, to include information to
demonstrate that they are designed to convey a 1 in 200 year plus climate
change design flow without causing constriction of flows or increasing the
risk of flooding elsewhere (SEPA consultation response on application
14/01087/EIA, 16 July 2014, par 1.1, 1.10, 1.11 refers); 
g)  for the formation of access tracks and watercourse crossings, information
including the extent and scale of the required/proposed works to
demonstrate that no land raising occurs within the functional flood plain of
any watercourse without the provision of associated compensatory storage
and an assessment of the changes to floodplain conveyance (SEPA
Page 52

Page 53

consultation responses on application 14/01087/EIA and 17/01003/APP, 16
July 2014 and 14 July 2017, pars 1.1, 1.5 - 1.11 and pars 1.1 - 1.9 refer); 
h)  details of the arrangements including timescale(s) for inspection to manage
and mitigate surface water run-off during all stages of the development
including proposals/regimes for inspection and maintenance of drains to
prevent blockages (SEPA consultation response on application
14/01087/EIA, 16 July 2014, par 1.12 refers); 
i)  based on investigation, further information to establish the viability of utilising
and upgrading of sections of existing tracks on the site (including the track
along the edge of forestry to the eastern edge of the application site)
together with justification for not using/upgrading existing tracks and creating
new access tracks (SEPA consultation response on application
14/01087/EIA, 16 July 2014, par 2.3 refers); 
j)  details to demonstrate that all track bases are made permeable to shallow
ground water flows where constructed through wet heath (M15) and any
other groundwater dependent terrestrial ecosystems (GWDTEs) including
the instances of the M6 community that are crossed (Environmental
Statement, Volume 2, Chapter 10 and SEPA consultation response on
application 14/01087/EIA, 16 July 2014, par 2.4 refers); 
k)  details for the location(s) and design specifications for the proposed
installation of ultra-violet and pre-filtration treatment arrangements to any
private water supply to be provided/used for human consumption within the
development site during the construction and operational stages of the
development; 
l)  confirmation of all required/proposed mitigation measures (where not already
embedded within the submitted design and layout of the development) for all
stages of the development, to be contained within a Schedule of Mitigation or
similar together with details regarding the process to control/action changes
from any agreed Schedule of Mitigation. 
The Schedule shall include, but be not limited to, all required/proposed measures
to mitigate the impact of the development upon water resources, hydrology,
hydrogeology and geology and nature conservation (including ecology and
ornithology, protected species and habitats) interests. These details may be
incorporated within any site specific Construction Environmental Management
Plan (CEMP) (see Condition 8 below); and 
Thereafter the development shall be implemented in accordance with the
approved details. 
Reason: Details of the matters specified are lacking from the submission and to
ensure an acceptable form of development in landscape, visual and/or other
environmental considerations, including addressing the risk of flooding and
surface water run-off, to minimise impacts on wetland habitats and maintain
(chemical) quality of water supplied to downslope wetlands, to minimise impacts
upon nature conservation interests, and to provide for a wholesome private water
supply where proposed as part of the development. 
8. No development shall commence until details have been submitted to and
approved by the Council, as planning authority in consultation with SEPA and
Page 53

Page 54

SNH and other agencies as appropriate regarding a site-specific Construction
Environmental Management Plan (CEMP). The CEMP shall incorporate details for
the environmental management, pollution prevention (not just during construction)
and the following: 
a)  surface water management plan; 
b)  pollution prevention plan; 
c)  site waste management plan; 
d)  watercourse engineering; 
e)  peat management - to include details of all peat stripping, excavation,
arrangements for storage and re-use of peat in accordance with best
practice; 
f)  (construction) noise management plan (see Condition 28); 
g)  species protection plans - to include those for breeding birds and bats, and
GWTDEs including arrangements for pre-commencement surveys to confirm
presence/absence of species on site, timing of works(s) to avoid disturbance,
development of buffer areas to prevent encroachment onto and into areas of
protected species and valued habitats, etc.; 
h)  habitat management plan - to include the arrangements to manage, monitor
and mitigate the loss of habitats and compensate for losses within and
beyond the site, and proposals and practices to enhance bio-diversity to off-
set habitat and species damage or loss, including restoration of areas of
blanket bog and wet heath and improving areas for golden plover; 
i)  invasive non-native species protocol - to address all bio-security and other
measures to be adopted to control the spread of giant hogweed and skunk
cabbage in and around the Dallas/Kellas area. 
In addition, the CEMP shall also include reference to the terms of appointment of
an appropriately qualified Ecological Clerk of Works (to be appointed by the
applicant/developer/wind turbine operator and approved by the Council, as
planning authority after consultation with SNH), to include a remit with roles and
responsibilities which shall include, but not necessarily be limited to, the
monitoring of all works carried out on site and ensuring compliance with all
environmental and nature conservation mitigation works and working practices,
advising and training on adequate environmental and nature conservation
interests within and adjoining the site, directing the placement of development
infrastructure within the site and powers to halt development on site where
environmental considerations warrant such action. 
Thereafter, the development shall be carried out in accordance with the approved
Plan. 
Reason: In order to minimise the impacts of construction and operation of the
development upon the environment and secure detailed information on the
delivery of mitigation works and measures as identified which are currently lacking
from the submitted particulars. 
9. Excluding the requirements for compensatory planting (Condition 28), the
Landscape scheme shall show: 
a)  the location of any existing trees, shrubs and hedgerows on the site and
identify those to be retained and those to be removed; 
Page 54

Page 55

b)  details of measures to be taken to protect any existing landscape features to
be retained during the course of developing the site; 
c)  details of the numbers, species, position, planting distances and sizes of all
new planting to be undertaken; 
d)  details of all earth mounding/moulding works to be undertaken, to include the
proposed formation of bunding or similar screening around the sub-station
compound or along the access tracks or elsewhere within the site together
with details regarding the location, extent and design specification for their
construction and formation of all earth works and cross-sections details to
relate the works to both existing and finished ground levels; and 
e)  details regarding the time-scale(s) for undertaking all landscaping and earth
works. 
Thereafter, all planting or seeding and earthwork operations shall be implemented
in accordance with the approved details and any trees or plants which (within a
period of 5 years from planting) die, are removed or become diseased or
damaged shall be replaced in the following planting season with others of similar
size, number and species unless otherwise agreed in writing with the Council, as
planning authority. 
Reason: Details of the matters specified are lacking from the submission and to
ensure an acceptable form of development including addressing the landscape
and visual and environmental impact of the substation and access tracks upon the
appearance and amenity of the development upon the surrounding area and to
ensure that all approved landscape works are timeously carried out and properly
maintained. 
10. The blades of all turbines shall rotate in the same direction and no names,
symbols, signs or logos or similar means of advertisement, other than those
required for health and safety reasons, shall be displayed on any part of the
turbines, masts, buildings, structures or other infrastructure associated with the
development without the prior written consent of the Council, as planning
authority. 
Reason: To minimise the visual impact arising from the appearance of the
development. 
11. In relation to each of the two borrow pit locations as identified on amended
drawing 60289428-ENG-002 Rev C: 
a) materials excavated from each pit location shall be used solely for purposes
in conjunction with this Meikle Hill wind farm development and for no other
use or purpose without the prior written consent of the Council, as planning
authority; and 
b)  no development shall commence until details for each borrow pit have been
submitted to and approved by the Council, as planning authority regarding: 
i.  finalised location and dimensions, including area and depth of
excavation, together with cross and long sections across the pit area to
show the extent and depth of excavation relative to existing and
finished (excavated depth) ground levels; 
ii.  location(s), extent and height of any temporary storage of material both
Page 55

Page 56

before and after processing on the site; 
iii.  location(s) and description of plant and machinery to be used to
process excavated material on the site; 
iv.  location and details of arrangement for fencing or similar means of
enclosure to be erected to define and limit the area of borrow pit
working (and within which all borrow pit activity including storage and
movement of materials and machinery shall be located at all times); 
v.  location and details of arrangements for surface water management
include de-watering ponds etc; 
vi.  proposed timescales for all excavation activity; 
vii.  the arrangements for site restoration and after-care of each borrow pit,
to include: 
a)  details including sections of proposed/required re-grading and
levelling works to re-integrate the area with its surroundings; 
b)  details of sub-material and topsoil arrangements to be provided to
enable re-instatement of the area to form a natural habitat; 
c)  details of all plantings to be undertaken (see Condition 9); and 
d)  timescale for site re-instatement works. 
Thereafter, all borrow pit activity shall be undertaken in accordance with the
approved details. 
Reason: Details of the matters specified are lacking from the submission and to
ensure an acceptable form of development including consideration of the
landscape and visual impact upon the surrounding area during both excavation
and re-instatement of each borrow pit area. 
12. No development shall commence until details have been submitted to and
approved in writing by the Council, as planning authority in consultation with the
Moray Access Manager regarding a Public Access Plan for the development/site
(to include both existing arrangements and all required/proposed access
arrangements during all stages of the development, including the construction
stage). In particular, the plan shall show: 
a)  all existing paths, tracks and rights of way and any areas currently outwith or
excluded from statutory access rights (under Part 1 of the Land Reform
(Scotland) Act 2003); and 
b)  any areas proposed for exclusion from statutory access rights, for reasons of
privacy, disturbance or curtilage, in relation to proposed buildings or
structures; and 
c)  all paths and tracks proposed for construction, for use by walkers, riders,
cyclists, and all ability users; and 
d) any diversions or paths - temporary or permanent - proposed for the
purposes of the development; and 
e)  details to include location, design specifications and time-scales for provision
for the following: 
i)   details of specific access controls, for example gates to be inserted at
main access points, etc; 
ii)   details of the arrangements to provide for public access for horse
riders, cyclists, pedestrians and the less able; and 
iii)  proposals to accommodate and enhance through access and
Page 56

Page 57

connectivity to/from the local paths network, to include the provision
and incorporation of a new path linking from the vehicle track near
turbine 1 through to the existing Right of Way located along the
southern boundary of the site; and 
iv)  details of all signage /mapboards or similar to be provided at key
access points to highlight all outdoor access opportunities. 
Thereafter, the development shall be implemented in accordance with the
approved details. 
Reason: To mitigate the effects of the development and maintain and improve
public access and connectivity both within, and to and from the site. 
13. No development works (including site clearance) shall commence until details
have been submitted to and approved by the Council, as planning authority in
consultation with Aberdeenshire Council Archaeology Services regarding a written
scheme of investigation (with timescales) to secure and undertake the
implementation of a programme of archaeological works. Thereafter, the
development and all recording and recovery of archaeological resources within
the development site shall be implemented in accordance with the approved
scheme. 
Reason: To safeguard and record the archaeological potential of the area. 
14. All construction activities associated with the development, including vehicle
movements at the site shall be permitted only between 07:00 and 19:00 hours,
Mondays - Fridays, and 07:00 and 16:00 hours on Saturdays, with no working on
Sundays or public holidays. Any required works outwith the stated times likely to
be audible at the curtilage of any noise sensitive property shall not be permitted
except with the prior written consent of the Council, as planning authority in
consultation with the Environmental Health Manager or in the case of an
emergency. 
Reason: In order to minimise the impact of construction works on the amenity of
the surrounding area including local residents. 
15. Blasting times associated with the development including the formation of borrow
pits shall be restricted as follows i.e. 
a)  no blasting shall be carried out on the site except between 10:00 and 
12:00 hours, and 14:00 and 16:00 hours, Mondays to Fridays, and 10:00 and
12:00 hours on Saturdays; and 
b)  no blasting or drilling operations on Sundays or other public holidays. 
The above blasting time arrangements shall not apply in cases of emergency
where it is considered necessary to carry out blasting operations in the
interests of safety. The Council, as planning authority shall be notified in
writing immediately of the nature and circumstances of any such event. 
Reason: To protect nearby residents from undue noise and disturbance impacts
and loss of amenity. 
Page 57

Page 58

16. Ground vibration as a result of blasting operations at the site, for example where
required to form the borrow pits shall, at all times, not exceed a peak particle
velocity of 10mms-1 in 95% of all blasts and no individual blast shall exceed a
peak particle velocity of 12mms-1 as measured at vibration sensitive buildings.
The measurement shall be the maximum of 3 mutually perpendicular directions
taken at the ground surface at any vibration sensitive building. 
Reason: To protect nearby residents from undue noise and disturbance impacts
and loss of amenity. 
17. At the reasonable request of the Council, as planning authority in conjunction with
the Environmental Health Manager, following receipt of any complaint relating to
vibration experienced from development operations including blasting operations
to form borrow pits, the applicant/developer/wind turbine operator shall take steps
to measure and monitor, at its own expense, ground vibration to ensure
compliance with Condition 16. Within two (2) weeks of being so notified of
vibration being experienced (or as longer as the Council, as planning authority
may allow) the applicant/developer/wind turbine operator shall submit to the
Council, as planning authority in consultation with the Environmental Health
Manager the results of such monitoring together with details (including timescale
for implementation) of measures to monitor and address vibration impacts to
ensure compliance with the requirements of Condition 16. Thereafter, the
development shall be implemented in accordance with the approved details. 
Reason: To protect nearby residents from undue noise and disturbance impacts
and loss of amenity. 
18. At the reasonable request of the Council, as planning authority in conjunction with
the Environmental Health Manager, following receipt of any complaint relating to
shadow flicker associated with the development hereby approved, the
applicant/developer/wind turbine operator shall investigate and instigate
appropriate measures to mitigate the effects of shadow flicker. Within two (2)
weeks of being so notified of shadow flicker being experienced (or as longer as
the Council, as planning authority may allow) the applicant/developer/ wind turbine
operator shall submit to the Council, as planning authority in consultation with the
Environmental Health Manager the results of such investigations together with
details of measures to address the effects of shadow flicker, including the
timescale within which the measures will be implemented. Thereafter, the
development shall be implemented in accordance with the approved details. 
Reason: In order to redress and mitigate any identified impacts of shadow flicker
and safeguard the amenity of local residents. 
19. At the reasonable request of the Council, as planning authority following receipt of
any complaint where interference to domestic television reception is caused as a
result of the development hereby approved, the applicant /developer/wind turbine
operator shall take steps to make good the reception, either by eliminating the
cause of the interference or by providing an alternative means by which television
signals may be received. Within two (2) weeks of being notified by the Council, as
planning authority of the existence of such interference (or within a longer period
Page 58

Page 59

as the planning authority may allow) the applicant/developer/wind turbine operator
shall submit to the Council, as planning authority for its approval, proposals to
make good the reception, including the timescale within which the proposals will
be undertaken. Thereafter, the development shall be carried out in accordance
with the approved details.   
Reason: In accordance with the applicant's submitted particulars and in order to
ensure that an alternative means of obtaining television reception can be achieved
and/or mitigated in the event of interference caused to domestic television
reception. 
20. At the reasonable request of the Council, as planning authority following receipt of
any complaint where interference to fixed link frequency band signals is caused as
a result of the development hereby approved, the applicant/developer/wind turbine
operator shall take steps to make good the fixed link frequency band signals,
either by eliminating the cause of the interference or by providing an alternative
means by which fixed link frequency band signals may be received. Within two (2)
weeks of being notified by the Council, as planning authority of the existence of
such interference (or within such longer period as the planning authority may
allow) the applicant/developer/wind turbine operator shall submit to the Council,
as planning authority for its approval proposals to make good the fixed link
frequency band signals, including the timescale within which the proposal shall be
undertaken. Thereafter, the proposals shall be carried out in accordance with the
approved details. 
Reason: In order to ensure that an alternative means of maintaining fixed link
telecommunications infrastructure can be achieved and fixed promptly in the event
of interference caused to existing fixed links. 
21. Prior to the commencement of deliveries to the site including movement of any
abnormal load, details shall be submitted to and be approved in writing by the
Council, as planning authority in consultation with Transport Scotland, as trunk
roads authority and/or its operating company regarding a Route Access Report or
equivalent, including swept path analysis or similar where appropriate, to identify
the proposed route for any abnormal load movements on the trunk road and
demonstrate that exceptional loads can be transported through the trunk road
network safely. The details shall include all required or proposed accommodation
measures including timescales for all required/proposed removal of street
furniture, junction widening, and traffic management, etc. and show that the
transportation of turbine components will not have any detrimental effect on
structures within the route path. Thereafter, the development shall be
implemented in accordance with the approved details. 
Reason: To minimise interference and maintain the safety and free flow of traffic
on the trunk road as a result of the traffic moving to and from the development. 
22. During the delivery period of the wind turbine construction materials, any
additional signing or temporary traffic control measures deemed necessary due to
the size or length of any loads being delivered or removed shall be undertaken by
a recognised (QA) traffic management consultant, in accordance with the name of
Page 59

Page 60

the consultant which shall previously have been provided to the Council, as
planning authority in consultation with Transport Scotland, as trunk roads authority
and/or its operating company before any construction commences. 
Reason: To minimise interference and maintain the safety and free flow of traffic
on the trunk road and to ensure that the transportation of turbine components will
not have a detrimental effect on the road and on structures along the delivery
route. 
23. Prior to the commencement of development details of the following shall be
submitted to and approved by the Council, as planning authority in consultation
with Transportation Manager (and Transport Scotland where appropriate): 
a)  detailed proposals for undertaking both trial runs and also delivery of
abnormal indivisible loads, to include (but not be limited to) identification of
all temporary and permanent modifications and measures required to protect
the public road and structures together with the arrangements for traffic,
vehicle holding areas and non-vehicular management during deliveries, time
restrictions for deliveries i.e. outwith school crossing patrol times, etc; 
b)  a Traffic Management Plan, in accordance with the scope and content of the
required Plan which shall have previously been submitted to and approved
by the Council, as planning authority in consultation with the Transportation
Manager. The Traffic Management Plan shall cover the duration of the
development, methods of dealing with large delivery vehicles, methods of
marshalling and manoeuvring at junctions on the public road network, any
temporary traffic waiting restriction requirements and all modifications to the
road network and traffic management arrangements; 
c)  detailed plans (to include location and design construction specifications) to
confirm the full extent of the proposed road widening of the B9010 to 5.5m; 
d)  details (1:200 scale drawing) of the proposed access junction onto the 
B9010 Pluscarden Road. The width of the vehicular access shall be a
minimum of 7.3m and have a maximum gradient of 1:20 measured for the
first 25m from the edge of the public carriageway (B9010). The first 25m of
the access shall be to The Moray Council specification and surfaced with hot
rolled asphalt. The access radii shall accommodate the abnormal load
vehicle movements as determined in the Traffic Management Plan, and shall
be kerbed using 254 x 127mm splayed/half battered precast concrete kerbs
to The Moray Council specification. Any existing ditch, watercourse or drain
under the site access shall be piped using a 300mm minimum diameter of
pipe. The pipe shall be laid to a self-cleansing gradient; 
e)  a detailed drawing (scale 1:500 or 1:1000 which shall also include details to
demonstrate control of the land) showing the provision of a visibility splay of
4.5m x 215m, and a schedule of maintenance for the area within the visibility
splay; and 
f)  in order to monitor, assess and address the impact of construction and
delivery traffic on the road network between the site access and the A96, an
assessment of the network and a programme of monitoring during
construction. The assessment shall include provision for a 'before and after'
condition survey to be carried out jointly with Council's Transportation
Section, traffic counters on the B9010 east and west of the site access in
advance of any construction traffic, either permanently or on a scheduled
Page 60

Page 61

basis (to be agreed with the Council, as roads authority) throughout the
construction period and for a period after works are completed. 
Thereafter, all modifications to the road network and traffic management
arrangements shall be implemented in accordance with the approved details and
all required works to the public road network shall be completed prior to the
delivery of any materials to the development site. 
Reason: To ensure an acceptable development including the provision of
additional information currently lacking from the submission and to ensure
acceptable infrastructure is provided along the proposed delivery/ construction
route to the site access in the interests of road safety. 
24. Prior to the commencement of construction and of deliveries to the site, including
abnormal loads and abnormal indivisible loads, the following shall be provided (in
accordance with the approved details and to The Moray Council standards and
specifications): 
a)  abnormal load trial run(s) shall be undertaken after mitigation works have
been undertaken (as approved under Condition 23 above) to confirm the
works are acceptable and to identify any other restrictions not previously
addressed including confirmation of the required/proposed vertical
clearances at bridge crossings, and the frequency and location of all required
abnormal load passing places/oncoming vehicle holding areas.
Representatives from Moray Council Transportation (Traffic), the Trunk
Roads Authority and Police Scotland must be invited to the trial run(s); 
b) for all abnormal indivisible loads, all required/proposed works approved
under Conditions 23 and 24a above shall be provided in accordance with 
the approved details and to The Moray Council standards and specifications.
Any works undertaken shall be permanent for the duration of the operation of
the development unless otherwise agreed in writing with the Council, as
planning authority in consultation with the Transportation Manager; 
c)  all road widening/alterations/verge hardening as identified in Conditions 23
and 24a above, the site access onto the B9010 and any dropped kerbs
required to allow overrunning of hardened verge;
d)  the 50m section of new 40mm thick Hot Rolled Asphalt which shall be
provided on the B9010 Pluscarden Road (25m either side of the centreline of
the access, over the entire width of the road) unless otherwise agreed in
writing by the Council, as planning authority in consultation with the
Transportation Manager; and 
e)  the visibility splay of 4.5m x 215m (Condition 23 refers) and thereafter, the
visibility splay shall be maintained at all times free from any obstruction
exceeding 1.0m above the level of the carriageway in accordance with the
agreed schedule of maintenance. 
Reason: To ensure an acceptable development including the provision of
additional information currently lacking from the submission and to ensure
acceptable infrastructure is provided along the proposed delivery/ construction
route to the site access in the interests of road safety. 
25. No wind turbine shall be erected unless and until an Air Traffic Control Radar
Page 61

Page 62

Mitigation Scheme, to address the impact of the wind turbine upon air safety, has
been submitted to and approved in writing by the Council, as planning authority in
consultation with the Ministry of Defence (Defence Infrastructure Organisation)
where: 
a)  the Air Traffic Control Radar Mitigation Scheme is a scheme which shall be
designed to mitigate the impact of the development upon the operation of the
Primary Surveillance Radar at RAF Lossiemouth ("the Radar") and the air
traffic control operations of the Ministry of Defence (MOD) which is reliant
upon the Radar. The Air Traffic Control Radar Mitigation Scheme shall set
out the appropriate measures to be implemented to mitigate the impact of
the development on the Radar and shall be in place for the operational life of
the development provided the Radar remains in operation; and 
b)  no turbines shall become operational unless and until all those measures
required by the approved Air Traffic Control Radar Mitigation Scheme have
been implemented prior to operation of the turbines and the Council, as
planning authority in consultation with the Ministry of Defence (Defence
Infrastructure Organisation) has confirmed this in writing. 
.
Thereafter, the development shall be operated fully in accordance with the
approved Air Traffic Control Radar Mitigation Scheme. 
Reason: In the interests of military aviation safety. 
26. MOD-accredited 25 candela omni-directional aviation lighting OR infra-red
warning lighting shall be installed with an optimised flash pattern of 60 flashes per
minute of 200ms to 500ms duration at the highest practicable point on all the
turbines in accordance with confirmation of the proposed lighting arrangements to
be installed which shall have been previously submitted to and approved in writing
by the Council, as planning authority in consultation with the Ministry of Defence,
Defence Infrastructure Organisation Safeguarding Officer prior to any light
installation. Thereafter, the turbines shall be erected with this confirmed lighting
installed and the lighting shall remain operational at all times throughout the
duration of the permission hereby granted. 
Reason: In the interests of military aviation safety. 
27. No development shall commence until details have been submitted to the Council,
as planning authority to confirm the submission of the following information to the
Ministry of Defence, Defence Infrastructure Organisation and Civil Aviation
Authority (Defence Geographic Centre (AIS Information Centre)): 
a)  the date construction starts and ends; 
b)  the exact position of the wind turbine towers in latitude and longitude; 
c)  a description of all structures over 300 feet high; 
d)  the maximum extension height of all construction equipment; the height
above ground level of the tallest structure; and 
e)  details of the approved lighting scheme to be installed (Condition 26 refers). 
Reason: To ensure the erected turbines present no risk to air safety. 
28. No development shall commence until details have been submitted to the Council,
Page 62

Page 63

as planning authority in consultation with Forestry Commission Scotland regarding
details of a woodland planting scheme (the Replanting Scheme) within Moray to
compensate, in this case, the removal of 8ha of existing woodland from the site in
order to accommodate the development. 
The Replanting Scheme details shall: 
a)  include the specifications for 
i.  on-site replanting; 
ii.  off-site compensatory planting; 
iii.  tree maintenance and protection to established planting (including 
Deer Management); and 
b)  comply with the requirements set out in the UK Forestry Standard (Forestry
Commissions, 2011. ISBN 978-0-85538-830-0) and the guidelines to which it
refers and include: 
i.  details of the location of the area to be planted; 
ii.  details of land owners and occupiers of the land to be planted; 
iii.  the nature, design and specification of the proposed woodland to be
planted; 
iv.  details of all necessary consents for the Replanting Scheme and
timescales within which each shall be obtained; 
v.  the phasing and associated timescales for implementing the 
Replanting Scheme; and 
vi. proposals for the maintenance and establishment of the Replanting
Scheme, including annual checks; protection from predation;
replacement planting; fencing; ground preparation; and drainage, etc. 
Thereafter, the development shall be implemented in accordance with the
approved Replanting Scheme details, including the phasing and timescales as set
out therein. 
Reason: Details of the matters specified are lacking from the submission and to
ensure an acceptable form of development where replacement or compensatory
planting is provided where the development results in a loss of woodland. 
29. No development shall commence until details shall be submitted to and approved
by the Council, as planning authority in consultation with the Environmental Health
Manager regarding a Noise Management Plan, to identify all sources of noise
emissions associated with the construction phase of the development together
with details of all measures to manage and mitigate the effects of construction
noise occurring at and within the site. Thereafter, the development shall be
implemented in accordance with the approved management plan. 
Reason: Details of the matters specified are lacking from the submitted particulars
and have yet to be determined (Environmental Statement, Volume 2, Chapter 7
refers) and in order to manage and minimise the impact of noise associated with
construction activity upon the amenity of local residents. 
30. The rating level of noise emissions from the combined effects of the 6 wind
turbines comprising the Meikle Hill wind farm as hereby approved (including the
application of any tonal penalty) when determined in accordance with the attached
Guidance Notes (see Additional Information as included in this formal decision
Page 63

Page 64

notice) shall not exceed the values for the relevant integer wind speed set out in,
or derived from, the tables attached to these conditions at any dwelling which is
lawfully existing or has planning permission at the date of this permission and: 
a)  The wind farm operator shall continuously log power production, wind speed
and wind direction, all in accordance with Guidance Note 1(d). This data
shall be retained for a period of not less than 24 months. The wind farm
operator shall provide this information in the format set out in Guidance Note
1(e) to the Council, as planning authority on its request, within 14 days of
receipt in writing of such a request. 
b)  Within 21 days from receipt of a written request from the Council, as
planning authority following a complaint to it from an occupant of a dwelling
alleging noise disturbance at that dwelling, the wind farm operator shall, at its
expense, employ a consultant approved by the Council, as planning authority
to assess the level of noise emissions from the wind farm at the
complainant's property in accordance with the procedures described in the
attached Guidance Notes. The written request from the Council, as planning
authority shall set out at least the date, time and location that the complaint
relates to and any identified atmospheric conditions, including wind direction,
and include a statement as to whether, in the opinion of the Council, as
planning authority, the noise giving rise to the complaint contains or is likely
to contain a tonal component. 
c)  The assessment of the rating level of noise emissions shall be undertaken in
accordance with an assessment protocol that shall previously have been
submitted to and approved in writing by the Council, as planning authority.
The protocol shall include the proposed measurement location identified in
accordance with the Guidance Notes where measurements for compliance
checking purposes shall be undertaken, whether noise giving rise to the
complaint contains or is likely to contain a tonal component, and also the
range of meteorological and operational conditions (which shall include the
range of wind speeds, wind directions, power generation and times of day) to
determine the assessment of rating level of noise emissions. The proposed
range of conditions shall be those which prevailed during times when the
complainant alleges there was disturbance due to noise, having regard to the
written request of the Council, as planning authority under paragraph (b),
and such others as the independent consultant considers likely to result in a
breach of the noise limits. 
d)  Where a dwelling to which a complaint is related is not listed in the tables
attached to these conditions, the wind farm operator shall submit to the
Council, as planning authority for written approval proposed noise limits
selected from those listed in the Tables to be adopted at the complainant's
dwelling for compliance checking purposes. The proposed noise limits are to
be those limits selected from the Tables specified for a listed location which
the independent consultant considers as being likely to experience the most
similar background noise environment to that experienced at the
complainant's dwelling. The rating level of noise emissions resulting from the
combined effects of the wind turbines when determined in accordance with
the attached Guidance Notes shall not exceed the noise limits approved in
writing by the Council, as planning authority for the complainant's dwelling.
For the sake of clarification the Meikle Hill Wind Farm Environmental
Statement, Volume 2, Main Report, Chapter 7, has advised that any
Page 64

Page 65

occupants of Aultahuish and Scottackleys have a direct financial involvement
in the wind farm development. Therefore, in accordance with ETSU-R-97,
higher noise limits are applicable under these conditions for these properties
only. 
e)  The wind farm operator shall provide to the Council, as planning authority the
independent consultant's assessment of the rating level of noise emissions
undertaken in accordance with the Guidance Notes within 2 months of the
date of the written request of the Council, as planning authority for
compliance measurements to be made under paragraph (b), unless the time
limit is extended in writing by the Council, as planning authority. The
assessment shall include all data collected for the purposes of undertaking
the compliance measurements, such data to be provided in the format set
out in Guidance Note 1(e) of the Guidance Notes. The instrumentation used
to undertake the measurements shall be calibrated in accordance with
Guidance Note 1(a) and certificates of calibration shall be submitted to the
Council, as planning authority with the independent consultant's assessment
of the rating level of noise emissions. 
f)  Where a further assessment of the rating level of noise emissions from the
wind farm is required pursuant to Guidance Note 4(c), the wind farm operator
shall submit a copy of the further assessment within 21 days of submission
of the independent consultant's assessment pursuant to paragraph (c) above
unless the time limit has been extended in writing by the Council, as planning
authority. 
Table 1: Between 07:00 and 23:00 - Noise limits expressed in dB LA90,10 minute
as a function of the standardised wind speed (m/s) at 10 metre height as
determined within the site averaged over 10 minute periods. 
Location: Standardised wind speed at 10 metre height (m/s) within the site
averaged over 10-minute periods. 
3 4 5 6 7 8 9 10 11 12
Tombreck Farm 35  35  35  35  37.6  40.9  44.2  47.4  50.1  52.3 
Scottackleys 45  45  45  45  45  45  45  45  45.4  48.9 
Aultahuish 45  45  45  45  45  45  45.4  48.7  51.7  54.2 
Torchastle 35  35  35  35  37.2  40.9  44.5  47.8  50.7  52.9 
Ballachraggan 35  35  35  35  36.2  38.7  41.3  44.0  46.5  48.9 
Table 2: Between 23:00 and 07:00 - Noise limits expressed in dB LA90,10 minute
as a function of the standardised wind speed (m/s) at 10 metre height as
determined within the site averaged over 10 minute periods. 
Location: Standardised wind speed at 10 metre height (m/s) within the site
averaged over 10-minute periods. 
3 4 5 6 7 8 9 10 11 12
Tombreck Farm  40  40  40  40  40  40  40.6  43.6  46  47.4 
Scottackleys  45  45  45  45  45  45  45  45  45.8  48.8 
Page 65

Page 66

Aultahuish  45  45  45  45  45  45  45  46.9  49.8  54.2 
Torchastle  40  40  40  40  40  40  40.6  43.6  46  47.4 
Ballachraggan  40  40  40  40  40  40  40.2  43.1  45.9  48.4 
Table 3: Coordinate locations of the properties listed in Tables 1 and 2. 
Property Easting Northing
Tombreck Farm  314030 852721
Scottackleys 312914 850420
Aultahuish 314038 849458
Torchastle 313163 852532
Ballachraggan   313336 849197 
Note to Table 3: The geographical coordinate references are provided for the
purpose of identifying the general location of dwellings to which a given set of
noise limits applies. 
Reason: To ensure an acceptable form of development and in order to protect the
amenity of any nearby residents from any undue noise and disturbance. 
31. Prior to the first commencement of the operation of the development hereby
approved details shall be submitted to and approved by the Council, as planning
authority in consultation with the Environmental Health Manager, regarding a
scheme for the assessment and regulation of amplitude modulation effects. 
Reason: To ensure an acceptable form of development and in order to protect the
amenity of any nearby residents from any undue noise and disturbance. 
Reason(s) for Decision
The Council’s reason(s) for making this decision are:- 
The proposal accords with the provisions of the development plan and there are no
material considerations that indicate otherwise. 
List of Informatives: 
The DEVELOPMENT MANAGEMENT & BUILDING STANDARDS MANAGER has
commented that:- 
A Building Warrant will be required for the proposals. Should you require further
assistance please do not hesitate to contact Building Standards, Environmental
Services Department, Council Office, High Street, ELGIN IV30 1BX or by
telephoning 01343 563243. 
Application 14/01087/EIA is described as the "Erection of wind farm comprising 10
wind turbines 126.5m high to tip and associated access track and ancillary
infrastructure erection of 1no permanent anemometer mast temporary formation of
Page 66

Page 67

construction compound and erection of 2no temporary anemometer masts at
Meikle Hill Dallas Moray". During consideration, application 14/01087/EIA was
amended with the number of turbines was reduced from 10 to 6 turbines and
Condition 1 of this decision notice confirms that as amended only 6 turbines were
approved. 
References to "Environmental Statement" and "Addendum" within this decision
notice refer to supporting documents submitted and considered as part of formal
decision notice 14/01087/EIA dated 24 June 2015 and remain relevant in the
context of this formal decision notice. 
THE SCOTTISH ENVIRONMENT PROTECTION AGENCY has commented that:- 
See consultation responses dated 14 July 2017 (for application 17/010003/APP)
and 16 July 2014, 9 April 2015 (for application 14/01087/EIA regarding detailed
and regulatory advice for the applicant including the expected content of the
Construction Environmental Management Plan advice and requirements for
authorisations under The Water Environment (Controlled Activities) (Scotland)
Regulations 2011 as amended (CAR) for water crossings. 
It is recommended that the CEMP is submitted at least 2 months prior to the
commencement of any works on site; this is to allow the necessary agencies
sufficient time to fully review the mitigation proposals and avoid any potential
delays to the project moving forward. 
THE TRANSPORTATION MANAGER, DIRECT SERVICES has commented that:- 
The following informatives, as appended to formal decision notice 14/01087/EIA
remain relevant in the context of the current proposal: 
Proposals for the management of abnormal indivisible loads to be approved must
also include measures to ensure the safety of non-vehicular road users. 
It is not acceptable to over-run central refuge/splitter islands; they are not
constructed to take vehicle loadings particularly when combined with heavy
turning between the A96 /B9010. Proposals submitted must show how this will be
managed during deliveries. It is also not appropriate to remove signing for the
duration of the abnormal loads therefore confirmation of how signs will be
managed during the delivery phase needs to be agreed. 
Prior to the commencement of deliveries or construction work a Section 96
Agreement under the Roads (Scotland) Act 1984 will be required to be approved
between the developer and the roads Authority. This is to ensure that the costs to
repair any damage to the public roads as a result of the construction work traffic
are met by the applicant. 
Transport Scotland must be consulted with respect to all deliveries proposed via
the A96 (Trunk Road). The neighbouring Local Authorities, through which the
delivery route may pass, Highland/Aberdeenshire/Aberdeen City, must also be
consulted. 
Page 67

Page 68

Planning consent does not carry with it the right to construct a new road or any
part of a road. In accordance with Section 21 of the Roads (Scotland) Act 1984
Construction Consent for new roads (includes passing places, modified junctions
and footpaths) that will form part of the public road will be required. 
Advice on this matter can be obtained by emailing
transport.develop@moray.gov.uk  and reference to the following pages on the
Council web site: 
Checklist: http://www.moray.gov.uk/downloads/file68812.pdf 
RCC: http://www.moray.gov.uk/moray_standard/page_65638.html  
Specification http://www.moray.gov.uk/downloads/file68813.pdf   
The applicant is obliged to apply for a road opening permit in accordance with
Section 85 of the Roads (Scotland) Act 1984. Advice on this matter can be
obtained by emailing roads.permits@moray.gov.uk  and reference to the following
page on the Council web site: Road Opening:
http://www.moray.gov.uk/moray_standard/page_79860.html 
Public utility apparatus may be affected by this proposal. Contact the appropriate
utility service in respect of any necessary utility service alterations which have to
be carried out at the expense of the developer. 
If required, street furniture will need to be repositioned at the expense of the
developer. In addition any existing roadside ditch may require a pipe or culvert.
Advice on these matters can be obtained by emailing road.maint@moray.gov.uk   
The applicants shall be responsible for any necessary diversion of any utilities or
drainage present at the locations where works are to be undertaken. 
The applicants shall meet all costs of improvements to the road infrastructure,
which are required as a result of the development. 
The applicants shall meet all costs of removal and re-erection of road signage,
which are required as a result of the delivery of the abnormal loads. 
The applicants shall meet all costs of diverting any footpath or cycleway during the
construction period, including signage. 
The applicant shall be responsible for ensuring that surface/ground water does not
run from the public road into his property. 
The applicants shall free and relieve the Roads Authority from any claims arising
out of his operations on the road or extension to the road. 
No retaining structures or embankments shall be constructed along the edge of
the road, whether retaining the public road or ground adjoining the public road
without prior consultation and agreement of the Roads Authority. 
Bridges and Structures - The developer must contact Neil Fotheringham, Senior
Engineer Moray Council Consultancy at Academy Street, Elgin - Tel (01343)
Page 68

Page 69

562542 to discuss the proposals. 
Traffic Management Plan - The developer must contact the Senior Engineer,
Traffic Section at Moray Council HQ, Elgin - Tel (01343) 563 3780 to discuss the
proposals. 
Roads Drainage - The developer must contact the Roads Authority Roads
Maintenance Manager (East) at Ashgrove Depot, Elgin - Tel (01343) 557300, Ext
7325 to discuss the proposals". 
SCOTTISH NATURAL HERITAGE has commented that:- 
See consultation response dated 25 July 2014 for application 14/01087/EIA
wherein the developer is recommended to adopt and implement in full all
mitigation measures set out in the ES including measures for protected species
(including birds and bats), with support given to the development of a species
protection plan and breeding bird protection plan, adoption of buffer area and
stand-off areas to minimise impact on bats, etc. and where the applicant is
encouraged to maintain records of bats during lifetime of the development,
specifically activity around turbines including instances of bat mortality/carcass
searches and to make this data available to the Bat Conservation Trust or local
bat group. SNH support and welcome the development of a habitat management
plan and peat management plan and compensatory tree planting, and a
monitoring protocol for invasive non-native species should be included (as part of
any CEMP) and cover not just construction but rather the lifetime of the wind farm. 
The FORESTRY COMMISSION SCOTLAND has commented that:-  
The Environmental Statement provides no specific detail about the mitigation for
the proposed deforestation. It recognises Scottish Government's Policy on the
Control of Woodland removal and agrees to conform to its principles but it does
not specify how or when it will meet the requirements. 
Forestry Commission Scotland (FCS) is supportive of the design considerations
within For the purposes of the compensatory planting condition, "Commencement
of Development" means the implementation of this consent by the carrying out of
(a) a material operation within the meaning of section 27(4) of the 1997 Planning
Act (other than any operations associated with ground or site investigation works);
or (b) any deforestation associated with the implementation of this consent. and
"Necessary Consents" means (a) any consent or permission required by an
enactment to enable the approved Replanting Scheme (or an approved Amended
Replanting Scheme as the case may be) to be implemented in accordance with
the phasing and associated timescales for implementation contained in the
approved Replanting Scheme (or an approved Amended Replanting Scheme as
the case may be); and (b) any right or permission to take entry to or access over
land required by the Company or parties acting on its behalf to implement the
approved Replanting Scheme (or an approved Amended Replanting Scheme as
the case may be). 
Page 69

Page 70

The CIVIL AVIATION AUTHORITY has commented that:- 
There is an international civil aviation requirement for all structures of 300 feet
(91.4 metres) or more to be charted on aeronautical charts. However, on behalf of
other non-regulatory aviation stakeholders, in the interest of aviation safety, the
CAA requests that any feature/structure 70 feet in height, or greater, above
ground level is notified to the Defence Geographic Centre ICGDGC-
ProdAISAFDb@mod.uk  including the location(s), height(s) and lighting status of
the feature/structure, the estimated and actual dates of construction and the
maximum height of any construction equipment to be used, at least 6 weeks prior
to the start of construction, to allow for the appropriate notification to the relevant
aviation communities. 
Any structure of 150 metres or more must be lit in accordance with the Air
Navigation Order and should be appropriately marked. If an aviation stakeholder
(including the MOD) made a request for lighting it is highly likely that the CAA
would support such a request, particularly if the request falls under Section 47 of
the Aviation Act. 
The effective height of a wind turbine is the maximum height to blade tip. 
SCOTTISH & SOUTHERN ELECTRIC has commented that: 
From records, there is a tower line spanning the access route to the proposed
wind farm therefore care must be taken when transporting the turbines to site with
regards to clearances. To checking clearances call Transmissions Operations
Manager Ian Gray on 01343 549807 or 07767 852808. All works in close
proximity to overhead lines they must be done in accordance with Health and
Safety Guidance Note GS6. 
There is also a high voltage underground cable within the site and care must be
taken when working that all works be carried out in accordance with the Health
and Safety Guidance Note HS (G) 47. 
THE ENVIRONMENTAL HEALTH MANAGER, DEVELOPMENT SERVICES, has
commented that:- 
Guidance Notes for noise condition 30 (above). 
These notes are to be read with and form part of the noise condition. They further
explain the condition and specify the methods to be employed in the assessment
of complaints about noise emissions from the wind farm. The rating level at each
integer wind speed is the arithmetic sum of the wind farm noise level as
determined from the best-fit curve described in Guidance Note 2 of these
Guidance Notes and any tonal penalty applied in accordance with Guidance Note
3. Reference to ETSU-R-97 refers to the publication entitled "The Assessment
and Rating of Noise from Wind Farms" (1997) published by the Energy
Technology Support Unit (ETSU) for the Department of Trade and Industry (DTI). 
Page 70

Page 71

Guidance Note 1 
(a) Values of the LA90,10 minute noise statistic should be measured at the
complainant's property, using a sound level meter of EN 60651/BS EN
60804 Type 1, or BS EN 61672 Class 1 quality (or the equivalent UK
adopted standard in force at the time of the measurements) set to measure
using the fast time weighted response as specified in BS EN 60651/BS EN
60804 or BS EN 61672-1 (or the equivalent UK adopted standard in force at
the time of the measurements). This should be calibrated in accordance with
the procedure specified in BS 4142: 1997 (or the equivalent UK adopted
standard in force at the time of the measurements). Measurements shall be
undertaken in such a manner to enable a tonal penalty to be applied in
accordance with Guidance Note 3. 
(b) The microphone should be mounted at 1.2 - 1.5 metres above ground level,
fitted with a two-layer windshield or suitable equivalent approved in writing by
the Council, as planning authority, and placed outside the complainant's
dwelling. Measurements should be made in "free field" conditions. To
achieve this, the microphone should be placed at least 3.5 metres away from
the building facade or any reflecting surface except the ground at the
approved measurement location. In the event that the consent of the
complainant for access to his or her property to undertake compliance
measurements is withheld, the wind farm operator shall submit for the written
approval of the Council, as planning authority details of the proposed
alternative representative measurement location prior to the commencement
of measurements and the measurements shall be undertaken at the
approved alternative representative measurement location. 
(c)   The LA90, 10 minute measurements should be synchronised with
measurements of the 10 minute arithmetic mean wind and operational data
logged in accordance with Guidance Note 1(d), including the power
generation data from the turbine control systems of the wind farm. 
(d) To enable compliance with the conditions to be evaluated, the wind farm
operator shall continuously log arithmetic mean wind speed in metres per
second and wind direction in degrees from north at hub height for each
turbine and arithmetic mean power generated by each turbine, all in
successive 10 minute periods. Unless an alternative procedure is previously
agreed in writing with the Council, as planning authority, this hub height wind
speed, averaged across all operating wind turbines, shall be used as the
basis for the analysis. All 10 minute arithmetic average mean wind speed
data measured at hub height shall be 'standardised' to a reference height of
10 metres as described in ETSU-R-97 at page 120 using a reference
roughness length of 0.05 metres. It is this standardised 10 metre height wind
speed data, which is correlated with the noise measurements determined as
valid in accordance with Guidance Note 2, such correlation to be undertaken
in the manner described in Guidance Note 2. All 10-minute periods shall
commence on the hour and in 10 minute increments thereafter. 
(e) Data provided to the Council, as planning authority in accordance with the
noise condition shall be provided in comma separated values in electronic
Page 71

Page 72

format. 
(f)  A data logging rain gauge shall be installed in the course of the assessment
of the levels of noise emissions. The gauge shall record over successive 10
minute periods synchronised with the periods of data recorded in accordance
with Note 1(d). 
Guidance Note 2 
(a) The noise measurements shall be made so as to provide not less than 20
valid data points as defined in Guidance Note 2. 
(b) Valid data points are those measured in the conditions specified in the
agreed written protocol under paragraph (c) of the noise condition, but
excluding any periods of rainfall measured in the vicinity of the sound level
meter. Rainfall shall be assessed by use of a rain gauge that shall log the
occurrence of rainfall in each 10-minute period concurrent with the
measurement periods set out in Guidance Note 1. In specifying such
conditions the Council, as planning authority shall have regard to those
conditions which prevailed during times when the complainant alleges there
was disturbance due to noise or which are considered likely to result in a
breach of the limits. 
(c)  For those data points considered valid in accordance with Guidance Note
2(b), values of the LA90, 10-minute noise measurements and corresponding
values of the 10-minute wind speed, as derived from the standardised ten
metre height wind speed averaged across all operating wind turbines using
the procedure specified in Guidance Note 1(d), shall be plotted on an XY
chart with noise level on the Y-axis and the standardised mean wind speed
on the X-axis. A least squares, "best fit" curve of an order deemed
appropriate by the independent consultant (but which may not be higher than
a fourth order) should be fitted to the data points and define the wind farm
noise level at each integer speed. 
Guidance Note 3 
(a) Where, in accordance with the approved assessment protocol under
paragraph (c) of the noise condition, noise emissions at the location or
locations where compliance measurements are being undertaken contain or
are likely to contain a tonal component, a tonal penalty is to be calculated
and applied using the following rating procedure. 
(b)  For each 10-minute interval for which LA90, 10-minute data have been
determined as valid in accordance with Guidance Note 2 a tonal assessment
shall be performed on noise emissions during 2 minutes of each 10-minute
period. The 2 minute periods should be spaced at 10- minute intervals
provided that uninterrupted uncorrupted data are available ("the standard
procedure"). Where uncorrupted data are not available, the first available
uninterrupted clean 2 minute period out of the affected overall 10 minute
period shall be selected. Any such deviations from the standard procedure,
as described in Section 2.1 on pages 104- 109 of ETSU-R-97, shall be
reported. 
Page 72

Page 73

(c)  For each of the 2 minute samples the tone level above or below audibility
shall be calculated by comparison with the audibility criterion given in Section
2.1 on pages 104 to 109 of ETSU-R-97. 
(d)  The tone level above audibility shall be plotted against wind speed for each
of the 2 minute samples. Samples for which the tones were below the
audibility criterion or no tone was identified, a value of zero audibility shall be
used. 
(e)  A least squares "best fit" linear regression line shall then be performed to
establish the average tone level above audibility for each integer wind speed
derived from the value of the "best fit" line at each integer wind speed. If
there is no apparent trend with wind speed then a simple arithmetic mean
shall be used. This process shall be repeated for each integer wind speed for
which there is an assessment of overall levels in Guidance Note 2. 
(f)  The tonal penalty is derived from the margin above audibility of the tone
according to the figure below. 
Guidance Note 4 
(a) If a tonal penalty is to be applied in accordance with Guidance Note 3 the
rating level of the turbine noise at each wind speed is the arithmetic sum of
the measured noise level as determined from the best fit curve described in
Guidance Note 2 and the penalty for tonal noise as derived in accordance
with Guidance Note 3 at each integer wind speed within the range specified
by the Council, as planning authority in its written protocol under paragraph
(c) of the noise condition. 
(b)  If no tonal penalty is to be applied then the rating level of the turbine noise at
each wind speed is equal to the measured noise level as determined from
the best fit curve described in Guidance Note 2. 
(c) In the event that the rating level is above the limit(s) set out in the Tables
attached to the noise conditions or the noise limits for a complainant's
dwelling approved in accordance with paragraph (d) of the noise condition,
the independent consultant shall undertake a further assessment of the
rating level to correct for background noise so that the rating level relates to
wind turbine noise emissions only. 
(d)  The wind farm operator shall ensure that all the wind turbines in the
development are turned off for such period as the independent consultant
requires to undertake the further assessment. The further assessment shall
be undertaken in accordance with the following steps: 
(e) Repeating the steps in Guidance Note 2, with the wind farm switched off,
and determining the background noise (L3) at each integer wind speed
Page 73

Page 74

within the range requested by the Council, as planning authority in its written
request under paragraph (b) and the approved protocol under paragraph (c)
of the noise condition. 
(f) The wind farm noise (L1) at this speed shall then be calculated as follows
where L2 is the measured level with turbines running but without the addition
of any tonal penalty: 
(g) The rating level shall be re-calculated by adding arithmetically the tonal
penalty (if any is applied in accordance with Note 3) to the derived wind farm
noise L1 at that integer wind speed. 
(h) If the rating level after adjustment for background noise contribution and
adjustment for tonal penalty (if required in accordance with note 3 above) at
any integer wind speed lies at or below the values set out in the Tables
attached to the conditions or at or below the noise limits approved by the
Council as planning authority for a complainant's dwelling in accordance with
paragraph (d) of the noise condition then no further action is necessary. If
the rating level at any integer wind speed exceeds the values set out in the
Tables attached to the conditions or the noise limits approved by the Council,
as planning authority for a complainant's dwelling in accordance with
paragraph (d) of the noise condition then the development fails to comply
with the conditions. 
LIST OF PLANS AND DRAWINGS SHOWING THE DEVELOPMENT
Reference No. Version No. Title/Description
60289428-ENG-001  Location plan 
Page 74

Page 75

Plans, drawings and other material submitted to the local authority
are protected by the Copyright, Designs and Patents Act 1988
(section 47). You may only use material which is downloaded and/
or printed for consultation purposes, to compare current
applications with previous schemes and to check whether
developments have been completed in accordance with approved
plans.
Further copies must not be made without the prior permission of
the copyright owner.
Maps shown in the Planning Committee Report can only be used
for the purposes of the Planning Committee. Any other use risks
infringing Crown Copyright and may lead to prosecution or civil
proceedings. Maps produced within this Planning Committee
Report can only be reproduced with the express permission of the
Moray Council and other Copyright holders. This permission must
be granted in advance.
PLANNING APPLICATION
COMMITTEE SITE PLAN
Site Address:
Meikle Hill
Dallas
Planning Application Ref Number: 
22/01208/APP 
Location Plan
Applicant Name: 
The Dallas Trust 
Page 75

Page 76

Site Location
Page 76

Page 77

Site Layout
Page 77

Page 78

Page 78

Page 79

PLANNING APPLICATION: 22/01208/APP 
In the event that a recommendation on this planning application is overturned the
Committee is reminded of the advice contained on the front page of the agenda for
Reports on Applications 
1.   THE PROPOSAL 
This is an application under section 42 of the Planning Act, which seeks to vary
the terms of condition 3 of 17/01003/APP to extend the operational lifetime of
the approved Meikle Hill windfarm from 27 years to 40 years. 
The application to be varied (17/01003/APP) was itself a variation to the original
planning permission (14/01087/EIA) for the Meikle Hill wind farm. The 2017
application increased the operation lifetime of the development from 25 to 27
years (condition 3) and varied condition 7 in relation to the provision of
information on land raising, condition 14 to allow operations outwith the
approved construction working hours in the event of an emergency, condition
24  to alter an incorrect word in relation to height of obstructions in the visibility
splay and condition 25 to allow development to commence but no turbine to be
erected the provision of a radar mitigation scheme.  This permission was
granted subject to a 5 year period for commencement rather than the statutory
3 year period. 
The original application (as amended) granted permission for: 
   6, three-bladed, variable speed, turbines and associated ancillary
infrastructure (reduced from 10 turbines during the course of the
application). 
     each turbine is 126.5m high (to blade tip) (80m hub height, 93m rotor
diameter) with a maximum rated capacity of 2.3MW i.e. 13.8MW for the
total development. 
     each turbine to be located on reinforced concrete foundations, approx.
21m in diameter and 3 - 4m in depth with a crane pad, approx. 40 x 22m
and separate assembly area approx. 40 x 15m located alongside. 
    1 (permanent) 80m high anemometer mast, of steel lattice construction set
on a reinforced concrete foundation, to be erected north-west of turbine 6. 
    1 (temporary) 80m high anemometer mast, a single pole supported by guy
wires, to be erected west of turbine 5. 
     a substation compound with control building, to be located adjacent to
access track and north of existing overhead power lines.
   a temporary construction compound to be located approx. midway
between the site access off the B9010 road and the turbines. 
   turbines to connect to national grid network via underground cabling to
proposed substation and thereafter, to the existing Dallas substation. 
     new up-graded junction to be formed at site entrance onto B9010 with
approx. 6.6km of access track to be provided (approx. 1.4km of up-graded
track and 5km of new access track). The approx. "J"-shaped track layout
Page 79

Page 80

connects all turbines and the permanent wind mast, off which two spurs
lead to turbines 2 and 4, and 5 respectively. 
   proposed drainage system to include SUDS including swales and cross
drains for access tracks and settlement lagoons adjacent to turbine pads
and watercourses.
     2 existing watercourse crossings to be up-graded and 5 new crossings to
be constructed (detailed design to be agreed). 
     2 borrow pits are also proposed. 
2.   THE SITE 
From the previous applications: 
   the site is approx. 510ha with all turbines located in the southern part of
the site on and between the side slopes of Meikle Hill (288 mAOD) to the
west and Mill Buie (342 mAOD) to the east. 
    the turbines are sited between approx. 245 and 270 mAOD (turbine 2 and
6 respectively). Turbine 1, the southernmost turbine, is located close to
the southern boundary of the site. Turbines 6 and 5 are the most northerly
and westerly located turbines respectively. 
   generally, the topography across the site is gently sloping with the
southern and most elevated part of the site comprising upland moorland
with some forestry plantation to the north-west on Meikle Hill and
Hillockhead (235 mAOD), the latter forming a backdrop to Dallas. 
   to the north and north-west, the land slopes down towards Dallas and
agricultural land extending along the River Lossie and B9010 road. 
   to the south and west is a mix of agricultural and wooded land. 
   to the south and east, the land cover is moorland and forestry with the
existing 40-turbine Rothes I and II wind farm development [the Rothes
development] located immediately to the south-east of the site. 
   Dallas and Kellas are approx. 2km distant from the site boundary. Elgin
and Forres are approx. 13.5km and 13km to the north-east and north-west
respectively.
   individual properties and farmsteads are located around the outer margins
of the site. 
    watercourses including Back Stripe and Cold Burn etc. drain towards the
River Lossie to the north.
   the site is bounded by the B9010 road to the north whilst the minor Dallas
- Kellas road forms part of the western boundary of the site. 
   the existing access onto the B9010 road and access track leading to
Blackhills will be upgraded and used for access to the site, including
construction traffic. To the south of Blackhills, the new section of access
track crosses over agricultural land and moorland to/from the turbines. 
   except for known archaeological interests recorded within the site, the
proposal is not located within any national or local landscape designation
nor within any international or national cultural heritage or nature
conservation designations. The Pluscarden Area of Great Landscape
Value (AGLV) and the Kellas Oakwood SSSI designations are located to
the north but outwith the site. 
Page 80

Page 81

   The site is not covered by any national or local environmental
designations.
   For renewable energy policy purposes (at the time of granting application
14/01087/EIA), all 6 turbines were located within an 'Area of Search' and
within the Upland Moorland and Forestry Landscape Character Area/Type
(LCT) as identified in the Moray Council, Supplementary Planning Policy
Guidance: Moray Onshore Wind Energy (MOWE) (March 2013) and
Moray Wind Energy Landscape Capacity Study (MLCS) 2012.
   The site remains within the Upland Moorland and Forestry/Upland Plateau
with Forest (10) LCT as defined in the Moray Wind Energy Landscape
Capacity Study (MLCS) 2017.  The Moray Onshore Wind Energy
Guidance (MOWE) 2020 also shows the site is located within an Area with
greatest potential” for large typology wind farm development and identifies
this LCT has having medium sensitivity to large typology (greater than
80m) wind turbines as approved on this site. 
3.   HISTORY 
13/00867/SCO - Erect 26 wind turbines of a maximum height of 126.5m to tip
(in relation to S36 submission) – determined 14 June 2013 
13/01915/PAN - Proposed wind farm at Meikle Hill, Dallas – reported to
Planning and Regulatory Services Committee – closed 7 November 2013 
14/01087/EIA - Erection of wind farm comprising 10 wind turbines, 126.5m high
to tip, and associated access track and ancillary infrastructure, erection of 1no
permanent anemometer mast, temporary formation of construction compound
and erection of 2no temporary anemometer masts at Meikle Hill Dallas -
approved 24 June 2015. 
Following amendments, with turbines 7 - 10 omitted, 6 turbines were granted
permission subject to (31no) conditions. 
17/01003/APP - Variation of conditions 3, 7, 14, 20, 24 and 25 of planning
permission 14/01087/EIA at Meikle Hill, Dallas – approved 11 December 2017. 
This application varied the following conditions:
   Condition 3, to allow a 27-year consent time limit;
   Condition 7(g), to require a topological plan in relation to land raising
within the floodplain for the formation of access track and water crossings;
   Condition 14, to allow construction activities to take place outwith the
specified hours in the event of an emergency;
   Condition 24(e), to address a grammatical error by changing the word
"about" to "allow" in relation to the requirement for a visibility splay; and
   Condition 25, to allow development to commence but not erect a turbine
until an Air Traffic Control Radar Mitigation Scheme has been agreed and
implemented. 
The application also sought a 5 year period within which to commence the
development.  
Page 81

Page 82

Relevant Nearby Wind Energy Proposals 
07/02800/S36 - Extension to wind farm at Rothes Wind Farm – approved by the
Energy Consents Unit 12 January 2010 - East of the application site. 
13/00615/EIA - Erection of eight wind turbines (Rotor diameter 80m) and
associated infrastructure at Kellas House, Kellas – approved 12 November
2014 – East of application site. 
01/02056/S36  - Construct and operate wind powered electricity generating
station (28 turbines and ancillary works) at Cairn Uish, Rothes Estate –
approved by the Energy Consents Unit  - East of application site – operational. 
19/00156/S36 - Erect 29 wind turbines consisting of 18 turbines of an overall
height from base to tip not exceeding 225m 8 turbines of an overall height from
base to tip not exceeding 200m and 3 turbines of an overall height from base to
not exceeding 149.9m associated infrastructure at Rothes III – to be
determined by Scottish Ministers following the previous Public Local Inquiry –
South East of application site. 
18/01591/S36 - Erect 48 wind turbines with blade tip height between 130 and
176 metres with installed capacity in excess of 50MW at Clash Gour Wind
Farm – to be determined by Scottish Ministers following the previous Public
Local Inquiry – South West of application site. 
20/01026/S36 - Proposed wind farm extension at Berry Burn Wind Farm,
Dunphail - approved by the Energy Consents Unit  8 December 2021 – South
West of application site. 
04/02473/S36 – Berry Burn wind farm - approved by the Energy Consents Unit
8 August 2009 –South West of application site – operational. 
13/00053/EIA - Erect 12no wind turbines (rotor diameter 71m) at Hill Of
Glaschyle, Dunphail – granted on appeal 31 March 2014 – West of the site –
operational. 
18/00523/S36 - Proposed wind farm comprising of 7 wind turbines 6 of a
maximum height base to tip not exceeding 149.9m and 1 of maximum height
not exceeding 134m external transformer housing site tracks crane pad
foundations underground electricity cable control building temporary
construction and compound 2 borrow pits associated works/infrastructure and
health and safety signage at Paul's Hill II Wind Farm - approved by the Energy
Consents Unit 18 December 2020 – South of the site. 
03/01426/S36 - S36 application to an extension to already consented windfarm
(increase in turbine capacity) at Paul’s Hill - approved by the Energy Consents
Unit – South of the site – operational. 
4.   POLICY - SEE APPENDIX 
Page 82

Page 83

5.   ADVERTISEMENTS 
5.1   Advertised for the purposes of Neighbour Notification. 
6.   CONSULTATIONS 
Heldon Community Council: No response. 
Strategic Planning & Development:  No objection.  The proposal is solely to
vary Condition 3 (duration of permission) of planning permission
17/01003/APP, a full assessment of the merits of the wind farm against MLDP
2020 policies has not been undertaken by SP&D as planning permission
remains extant and no physical changes to the development are proposed. 
Officer Note – For clarity, an assessment of the proposal against the relevant
policies of MLDP 2020 has been undertaken by the Development Management
Section and as referred to below in the Observations Section of this report). 
Transportation:  No objection. 
Environmental Health:  No objection. 
Moray Flood Risk Management:  No objection. 
Aberdeenshire Archaeology Service:  No objection. 
Climate Change Team: No objection. 
Contaminated Land:  No objection. 
Private Water Supplies: No objection. 
Developer Obligations: None sought. 
Moray Access Manager:  No response. 
SEPA:  No comment. 
Scottish Forestry:  No objection. 
Nature Scot:  No response. 
MOD: No objection. 
National Air Traffic Systems (NATS): No objection. 
RSPB:  No comment. 
Highland and Islands Airports: No objection. 
Aberdeen Airport: No objections. 
Page 83

Page 84

Atkins Global – Windfarms: No objection. 
JRC Windfarms: No objection. 
Civil Aviation Authority: No response. 
Ofcom: No response. 
SSE Transmission: No response. 
7.   OBJECTIONS-REPRESENTATIONS 
None. 
8.   OBSERVATIONS 
8.1  Section 42 of the Town and Country Planning (Scotland) Act 1997 as amended
allows applicants to apply to develop land without compliance with conditions
previous attached to a planning consent. In determining such an application,
the Council, as Planning Authority can only consider the conditions subject to
which planning permission should be granted and may: 
   grant permission unconditionally (i.e. remove the conditions attached to
the planning consent); 
   grant permission conditionally with differing conditions; or 
   refuse the application (i.e. keep the conditions attached to the planning
consent). 
8.2  Section 25 of the 1997 Act as amended requires applications to be determined
in accordance with the Development Plan i.e. the adopted Moray Local
Development Plan 2020 (MLDP) unless material considerations indicate
otherwise. 
8.3  The main issues are considered below: 
8.4   Background
The original planning application 14/01087/EIA was approved by the Planning
and Regulatory Services Committee and determined on the 24 June 2015.  The
application as approved was for 6 126.5 m high turbines with a total output of
13.8mw.  At the time of the original submission 10 turbines with an output of
23mw were proposed and as such the application was a Major application as
defined by the Development Hierarchy Regulations 2009.  Formal pre-
application procedures were therefore required.  Following the reduction in the
scheme the proposal fell below the ‘Major’ threshold (20mw) and should it be
submitted afresh it would be dealt with as a ‘local’ application.  Following the
grant of planning permission a Section 42 application (17/01003/APP) was
submitted which sought to vary several of the conditions attached to the 2014
consent.  The most significant of these were the variation to condition 3 to
extend the operational lifetime of the development from 25 to 27 years and the
change to condition 25 to allow development to commence but no turbines to
Page 84

Page 85

be erected before a radar mitigation plan had been produced.  The 2017
consent was granted with a commencement period of 5 years.   
8.4.1  The 2014 application was considered likely to have potential significant
environmental effects and was submitted with a voluntary Environmental
Statement (ES) prepared under the Environmental Impact Assessment (EIA). 
Two Addendums to the ES were prepared to reflect two amendments made to
reduce the number of turbines.  Neither the current application or the s.42
application (17/01003/APP) that preceded it include a fresh Environmental
Impact Assessment Report.  It was noted at the time of the 2017 application
that the Regulations do not specifically provide for a proposal to vary conditions
of an earlier development but the current proposal is neither a new
development per se nor does it alter the previously approved number, design
(including height) and location/site layout arrangements for 6 turbines at Meikle
Hill which were previously regarded as not having any unacceptable or
significant effects. Furthermore, the current proposal is considered unlikely to
result in any new, or introduce additional, environmental effects beyond those
previously assessed. The Moray Local Development Plan 2020 Special
Landscape Area designation covering the Pluscarden valley to the north is also
some distance from the current site. It is also noted that appropriate mitigation
of environmental impacts forms part of the conditions which are to be
reiterated. 
8.4.2  In considering a Section 42 application the planning authority can only consider
the conditions that are the subject of the application although this does not
preclude consideration of the overall effect of granting a new permission. If the
decision is that the Section 42 application should be granted a new permission
is created and all conditions of the previous consent must be reiterated in order
to have effect.  In this case it is recommended that condition 3 is varied as
requested by the applicant and all the other conditions are reiterated
unchanged.  This includes condition 1 which allows a 5 year commencement
period rather than the statutory 3 years.   
8.4.3  Both the original permission (14/01087/EIA) and the approved Section 42
application (17/01003/APP) were considered under previous local plans. It is
therefore necessary to consider the proposal against current local and national
policy. 
8.5  Relationship of proposal to national renewable energy policy/guidance
International and UK policy frameworks are generally supportive of renewable
energy proposals which help to facilitate a transition to a low carbon economy.
National Planning Framework (NPF3) for Scotland sets out the spatial strategy
for Scotland's development. NPF3 makes specific reference to onshore wind
energy having an important role in delivering the commitment to a low carbon
energy generation. The November 2020 Position Statement on the 4th National
Planning Framework indicates that measures to address climate change and
reduction of carbon emissions will be accelerated. 
8.5.1   The Climate Change (Scotland) Act 2009 places a duty on public bodies to act
sustainably and meet emissions targets including a requirement to achieve at
least an 80% reduction in greenhouse gas emissions by 2050 (over 1990
levels). Beyond the NPF3 there are a number of considerations relevant to the
Page 85

Page 86

Section 36 process, which are taken into account in arriving at the below
recommendation. They are The Scottish Government’s Programme for
Scotland 2020-21, The Environment Strategy for Scotland, February 2020,
Climate Change (Emissions Reductions Targets) (Scotland) Act 2019, Scottish
Government Climate Change Plan (2018), Scottish Government Onshore Wind
Policy Statement 2017 and Scottish Energy Strategy (2017). These generally
stress the need to reduce carbon emissions (for which wind energy will clearly
play a part) but do qualify this with the need to protect landscapes, built and
natural heritage, residents and other interests. 
8.5.2   The commitment to the creation of a low carbon place is reiterated in Scottish
Planning Policy. The applicants submissions regard national policy as being
significant and supportive of this proposal where this development, as a proven
technology providing a source of safe and locally produced renewable energy
for many years, will make a significant contribution towards renewable energy
production at the national and local level. Whilst it is noted that some targets
have been met for renewable energy production it is noted that the Scottish
Government’s guidance continues to support renewable energy development
and it is recognised that this reflects the thrust of national policy. 
8.5.3   Scottish Planning Policy (SPP) requires that “planning should direct the right
development to the right place”, which is an important issue in this proposal.
The policy principles set out for “Delivering Heat and Electricity” in SPP include; 
•   Support the transformational change to a low carbon economy, consistent
with national objectives and targets; 
•   Support the development of a diverse range of electricity generation from
renewable energy technologies - including the expansion of renewable
energy generation capacity and the development of heat networks; 
•   Guide developments to appropriate locations and advise on the issues
that will be taken into account when specific proposals are being
assessed. 
8.5.4  (SPP) requires planning authorities to set out in the development plan a spatial
framework identifying those areas that are likely to be most appropriate for
onshore wind farms as a guide for developers and communities, following a set
methodology (para 161). This has been done through the spatial framework
included within the Moray Local Development Plan 2020. This is a broad-brush
approach required to comply with Scottish Planning Policy and covers
approximately 40% of the Moray Local Development Plan Area. The proposed
site is located within an area with potential for wind farm development. SPP
(para 162) recognises the limitations of the strategic spatial framework and
further requires that local development planning authorities should identify
where there is strategic capacity for wind farms and areas with the greatest
potential for wind development. The Moray Onshore Wind Energy (MOWE)
Non-Statutory Guidance 2020 identifies such areas. The application site is
within an area of greatest potential for large typologies (80-130m). 
8.5.5   The detailed mapping of constraints and guidance on areas with greatest
potential is set out in the Moray Onshore Wind Energy Guidance 2017
(MOWE), with the proposal site located partially within an area identified as
having opportunities for extension and repowering. Of note, as identified in the
Page 86

Page 87

consultation from Strategic Planning & Development the 2017 MOWE and
Landscape Capacity Study are currently non statutory guidance and are under
review and is likely to become a sensitivity study in line with Nature Scot
guidance. They still do however represent the most detailed and up to date
guidance on wind energy landscape capacity in Moray and remain fit for
purpose. 
8.6  MOWE Non-Statutory Guidance 2020 and Moray Wind Energy Landscape
Capacity Study 2017
The MOWE Non-Statutory Guidance and the Landscape Capacity Study are
material considerations for development management purposes. Incorporating
the outcomes from the Landscape Capacity Study, the Guidance identifies five
typologies of wind turbine and highlights that there is very limited scope to
accommodate further large scale wind turbine developments in Moray in
landscape and visual terms. 
8.6.1  The proposed development is located within Upland Moorland and
Forestry/Upland Plateau with Forest (10) Landscape Character Type (LCT) as
defined in MLCS 2017 and MOWE 2020. LCT10 is assessed in the study as
having Medium sensitivity to the large typology (80-130m). This indicates that
some key landscape characteristics or aspects visual amenity are sensitive but
there is still some ability to accommodate development in some situations
without significant character change or visual impact.  The operational Rothes
and Rothes II wind farms are already present in the LCT along with this
proposal and the other consented schemes at Glashkyle (built) and Kellas
(consent still extant).  The operational wind farms at Paul’s Hill and Berry Burn
are on the adjoining open rolling uplands LCT. 
8.6.2   The Upland Moorland and Forestry LCT consists a gently undulating plateau-
like landform.  The land cover is predominantly moorland and forestry.  The
MLCS concludes that there may be some potential to accommodate further
turbine development within this LCT although it is noted that the outer edges
provide important backdrop and containment to the wider area.   It should be
noted that the current proposal relates to a consented application that pre-dates
the MLCS and therefore forms part of the baseline assessment.   
8.7  Compliance with Renewable Energy Policy (PP1, PP2, DP1, DP9, EP1,
EP7, EP8 and MOWE) 
It is noted about that national planning policy and guidance supports wind
energy developments. The development plan has changed since the
determination of the previous applications.  In considering the current proposal
to extend the operational lifetime of the development the Committee should
consider the extent to which the proposal continues to comply with the
development. Policy DP9 ‘Renewable Energy’ is the principle policy on which
the application must be determined but this includes a requirement to comply
with all other relevant policies of the development plan. The policy requires
renewable energy proposals to address unacceptable impacts in relation to
landscape and visual impacts, noise, air quality, electromagnetic disturbance,
the water environment, carbon rich soils and peat, woodland and forestry, traffic
both during construction and operation, impact on tourism and recreational
interests. For wind farms the policy specifically requires compliance with the
spatial framework, and site specific consideration informed by the Landscape
Page 87

Page 88

Character Study, impacts on communities including through issues such as
shadow flicker, aviation and defence issues, cumulative issues and
decommissioning and restoration. 
8.7.1   In terms of Landscape and Visual Impact the Landscape Character Study
which supports policy DP9 and MOWE is dated 2017. It takes account of the
approved wind farm at Meikle Hill in its baseline assessment and the
assessment of scope for future development assumes that this development
will be built and will be present in the landscape for some time to come. Any
development approved since the original consent at on this site (14/01087/EIA)
would have considered it as part of the assessment of cumulative impact so the
proposed extension of the operational lifetime will not result in any additional
cumulative impacts.  The approved wind farm is an established part of the
assessment of wind farm capacity in the area and as such the siting is
considered to comply with policy. 
8.7.2   The most notable change in this locality in terms of windfarm capacity has been
the approval of the extensions at Berry Burn (20/01026/S36) and Paul’s Hill
(18/00523/S36) but both these developments would have been considered in
the context of the existing approved development at Meikle Hill.   
8.7.3  There are no changes to the proposal in terms of the layout, height or number
of turbines proposed. The impacts of the development will therefore be the
same as those associated with the previous development.  Issues relating to
noise, shadow flicker, electromagnetic disturbance, impacts on the water
environment and peat, forestry, traffic impact, ecology, tourism and recreation,
archaeology and mod interests. No concerns in relation to these matters have
been raised by consultees. Where necessary mitigation or other suitable
controls is covered by condition. The granting of a s.42 application has the
effect of creating a new planning application therefore the conditions of the
previous consent will be reiterated to ensure that all mitigation measures
remain in place.   
8.7.4  It is noted that some of the original survey work in relation to protected species
and habitats is now out of date. However, condition 8 requires amongst other
items, pre-commencement surveys, species protection plans and a habitat
management plan. Nature Scot have been consulted and confirm that they are
content that the recommended condition will ensure that all necessary pre-
construction surveys and species mitigation will take place in advance of any
work commencing. 
8.7.5  It is considered that the previous conditions which are to be reiterated are
sufficient in relation to decommissioning and restoration. Condition 1 requires
the turbines to be removed within a year of the recommended 40 year
operational life span ending, condition 5 requires the submission of a
restoration and decommission plan and condition 6 requires the provision of a
bond to cover the cost of restoration. These arrangements are considered to be
sufficient to ensure adequate decommissioning and restoration.
Page 88

Page 89

8.8  Operational Lifetime of the Development 
The purpose of the current application is to increase the operational lifetime of
the development from 27 years (increased from 25 years under 17/01003/APP)
to 40 years. The applicant has stated that this extension is required to reflect
changes in technology and experience that have demonstrated that wind
turbines can operate safely and efficiently for longer periods. The applicant’s
submission in this case is considered to be reasonable. 
8.8.1  At the time of the original approval (14/01087/EIA) wind farms were typically
granted permission for a period of 25 years which reflected the standard
manufacturers warrantee. These periods have increased as technology and
experience has increased. Operational periods of 30 years or longer are now
common.  In the case of the current application the approved development
would not be altered in any way but would be present on site for an additional
13 years. This would have the benefit of increasing the renewable energy
output of the development and would reduce the net carbon impact of the
development over its lifetime. All the existing proposed mitigation measures
would remain in place and it is noted that no consultees have expressed any
concern about the proposed extension of the operational lifetime of the
development. The proposed extension to the operational life of the wind farm is
therefore considered reasonable in this case and would prolong the output of a
renewable energy source. 
8.9  Developer Obligations
In line with policy no developer contribution has been sought in this case. Any
required "Community benefit" is given separate consideration from the planning
merits of the proposal. 
Conclusion
The proposed variation of condition 3 would extend the operational lifetime of
the development from 27 to 40 years.  For the avoidance of doubt the
recommendation reiterates all other conditions of the previous consent
including condition 1 which allows 5 years for the commencement of
development.   The extension of operational lifetime reflects advances in
technology and will bring the development in line with more recent consents
and will allow the renewable energy benefits of the scheme to be maximised. It
is therefore recommended that planning permission is granted. 
REASON(S) FOR DECISION
The Council’s reason(s) for making this decision are: - 
The proposal accords with the provisions of the development plan and there
are no material considerations that indicate otherwise.   
Author/Contact
Officer:
Lisa Macdonald           
Senior Planning Officer
Ext: 01343 563479 
Beverly Smith
Development Management & Building Standards Manager
Page 89

Page 90

Page 90

Page 91

APPENDIX 
POLICY 
Proposed Moray Local Development Plan 2020 
PP1 PLACEMAKING 
a) Development must be designed to create successful, healthy places that support
good physical and mental health, help reduce health inequalities, improve people's
wellbeing, safeguard the environment and support economic development.   
b) A Placemaking Statement is required for residential developments of 10 units and
above to be submitted with the planning application to articulate how the
development proposal addresses the requirements of policy PP1 Placemaking and
other relevant LDP policies and guidance.  The Placemaking Statement must include
sufficient information for the council to carry out a Quality Audit.  Where considered
appropriate by the council, taking account of the nature and scale of the proposed
development and of the site circumstances, this shall include a landscaping plan, a
topographical survey, slope analysis, site sections, 3D visualisations, a Street
Engineering Review and a Biodiversity Plan.  The Placemaking Statement must
demonstrate how the development promotes opportunities for healthy living and
working. The landscape plan must set out details of species type, size, timescales for
planting and maintenance. 
c) To create successful, healthy places residential developments of 10 units and above
must comply with Scottish Government policy Creating Places and Designing Streets
and must incorporate the following fundamental principles: 
(i) Character and Identity
• Create places that are distinctive to prevent homogenous 'anywhere'
development;
• Provide a number of character areas reflecting site characteristics that
have their own distinctive identity and are clearly distinguishable;
• Provide distinctiveness between and in each character area through a
combination of measures including variation in urban form, street
structure/network, architecture and masonry, accent features (such as
porches), surrounds and detailing, materials (buildings and surfaces),
colour, boundary treatments, hard/soft landscaping and a variety of
approaches to tree species and planting that emphasises the hierarchy of
open spaces and streets within a cohesive design strategy for the whole
development;
• Distinctiveness must be reinforced along main thoroughfares, open
spaces and places where people may congregate such as
shopping/service centres;
• Retain, incorporate and/or respond to relevant elements of the landscape
such as topography and planted features, natural and historic
environment, and propose street naming (in residential developments of
20 units and above, where proposed names are to be submitted with the
planning application) to retain and enhance local associations; 
Page 91

Page 92

(ii) Healthier, Safer Environments
• Designed to prevent crime, fear of crime and anti-social behaviour with
good levels of natural surveillance and security using treatments such as
low boundary walls, dual frontages (principal rooms) and well-lit routes to
encourage social interaction.  Unbroken high boundary treatments such
as wooden fencing and blank gables onto routes, open spaces and
communal areas will not be acceptable. 
• Designed to encourage physical exercise for people of all abilities. 
• Create a distinctive urban form with landmarks, key buildings, vistas,
gateways and public art to provide good orientation and navigation
through the development. 
• Provide a mix of compatible uses, where indicated within settlement
statements, integrated into the fabric of buildings within the street. 
• Prioritise pedestrians and cyclists by providing a permeable movement
framework that incorporates desire lines (including connecting to and
upgrading existing desire lines) and is fully integrated with the surrounding
network to create walkable neighbourhoods and encourage physical
activity. 
• Integrate multi- functional active travel routes, green and open space into
layout and design, to create well connected places that encourage
physical activity, provide attractive spaces for people to interact and to
connect with nature. 
• Create safe streets that influence driver behaviour to reduce vehicle
speeds that are appropriate to the local context such as through shorter
streets, reduced visibility and varying the building line. 
• Provide seating opportunities within streets, paths and open spaces for all
generations and mobility's to interact, participate in activity, and rest and
reflect. 
• Provide for people with mobility problems or a disability to access
buildings, places and open spaces. 
• Create development with public fronts and private backs. 
• Maximise environmental benefits through the orientation of buildings,
streets and open space to maximise the health benefits associated with
solar gain and wind shelter. 
(iii) Housing Mix
• Provide a wide range of well integrated tenures, including a range of
house types and plot sizes for different household sizes, incomes and
generations and meet the affordable and accessible requirements of
policy DP2 Housing.
• All tenures of housing should have equal access to amenities, greenspace
and active travel routes.
Page 92

Page 93

(iv) Open Spaces/Landscaping
• Provide accessible, multi-functional open space within a clearly defined
hierarchy integrated into the development and connected via an active
travel network of green/blue corridors that are fully incorporated into the
development and to the surrounding area, and meet the requirements of
policy EP5 Open Space and the Open Space Strategy Supplementary
Guidance and Policy EP12 Managing the Water Environment and
Drainage Impact Assessment for New Developments Supplementary
Guidance.
• Landscaped areas must provide seasonal variation, (mix of planting and
colour) including native planting for pollination and food production.
• Landscaping areas that because of their size, shape or location would not
form any useable space or that will not positively contribute to the
character of an area will not contribute to the open space requirements of
Policy EP4 Open Space.
• Semi-mature tree planting and shrubs must be provided along all routes
with the variety of approaches reflecting and accentuating the street
hierarchy.
• Public and private space must be clearly defined.
• Play areas (where identified) must be inclusive, providing equipment so
the facility is for every child/young person regardless of ability and
provided upon completion of 50% of the character area.
• Proposals must provide advance landscaping identified in site
designations and meet the quality requirements of policy EP5 Open
Space.
• Structural landscaping must incorporate countryside style paths (such as
bound or compacted gravel) with waymarkers.
•  Maintenance arrangements for all paths, trees, hedging, shrubs, play/
sports areas, roundabouts and other open/ green spaces and blue/green
corridors must be provided. 
v) Biodiversity
• Create a variety of high quality multi- functional green/blue spaces and
networks that connect people and nature, that include trees, hedges and
planting to enhance biodiversity and support habitats/wildlife and comply
with policy EP2 Biodiversity and Geodiversity and EP5 Open Space.
• A plan detailing how different elements of the development will contribute
to supporting biodiversity must be included in the design statement
submitted with the planning application.
• Integrate green and blue infrastructure such as swales, permeable paving,
SUDS ponds, green roofs and walls and grass/wildflower verges into
streets, parking areas and plots to sustainably address drainage and
flooding issues and enhance biodiversity from the outset of the
development.
• Developments must safeguard and where physically possible extend or
enhance wildlife corridors and green/blue networks and prevent
fragmentation of existing habitats. 
(vi) Parking
• Car parking must not dominate the streetscape to the front or rear of
properties.  On all streets a minimum of 50% of car parking must be
Page 93

Page 94

provided to the side or rear and behind the building line with a maximum
of 50% car parking within the front curtilage or on street, subject to the
visual impact being mitigated by hedging, low stone boundary walls or
other acceptable treatments that enhance the streetscape.
• Provide semi-mature trees and planting within communal private and
public/visitor parking areas and on-street parking at a maximum interval of
4 car parking spaces.
• Secure and covered cycle parking and storage, car sharing spaces and
electric car charging points must be provided in accordance with policy
DP1 Development Principles.
• Parking areas must use a variation in materials to reduce the visual
impact on the streetscene. 
(vii) Street Layout and Detail
• Provide a clear hierarchy of streets reinforced through street width,
building density and street and building design, materials, hard/soft
landscaping and a variety of approaches to tree planting and shrubs.
• Streets and connecting routes should encourage walking and cycling over
use of the private car by providing well connected, safe and appealing
routes.
• Design junctions to prioritise pedestrians, accommodate active travel and
public transport and service/emergency vehicles to reflect the context and
urban form and ensure that the street pattern is not standardised.  
• Dead-end streets/cul-de-sacs will only be selectively permitted such as on
rural edges or where topography, site size, shape or relationship to
adjacent developments prevent an alternative more permeable layout.
These must be short, serving no more than 10 units and provide walking
and cycling through routes to maximise connectivity to the surrounding
area.
• Where a roundabout forms a gateway into, or a landmark within, a town
and/or a development, it must be designed to create a gateway feature or
to contribute positively to the character of the area.
• Design principles for street layouts must be informed by a Street
Engineering Review (SER) and align with Roads Construction Consent
(RCC) to provide certainty that the development will be delivered as per
the planning consent. 
(d) Future masterplans will be prepared through collaborative working and in partnership
between the developer and the council for Lochyhill (Forres), Barhill Road (Buckie),
Elgin Town Centre/Cooper Park, Elgin North East, Clarkly Hill, Burghead and West
Mosstodloch.  Masterplans that are not prepared collaboratively and in partnership
with the council will not be supported.  Masterplans that are approved will be
Supplementary Guidance to the Plan. 
(e) Proposals for sites must reflect the key design principles and safeguard or enhance
the green networks set out in the Proposals Maps and Settlement Statements. 
Alternative design solutions may be proposed where justification is provided to the
planning authority's satisfaction to merit this.
Page 94

Page 95

PP2  SUSTAINABLE ECONOMIC GROWTH
Development proposals which support the Moray Economic Strategy to deliver
sustainable economic growth will be supported where the quality of the natural and built
environment is safeguarded, there is a clear locational need and all potential impacts can
be satisfactorily mitigated. 
PP3  INFRASTRUCTURE & SERVICES
Development must be planned and co-ordinated with infrastructure to ensure that places
function properly and proposals are adequately served by infrastructure and services.   
a) In relation to infrastructure and services developments will be required to provide the
following as may be considered appropriate by the planning authority, unless these
requirements are considered not to be necessary: 
i)  Education, Health, Transport, Sports and Recreation and Access facilities in
accord with Supplementary Guidance on Developer Obligations and Open
Space. 
ii)  Green infrastructure and network requirements specified in policy EP5 Open
Space, Town and Village Maps and, contained within Supplementary Guidance
on the Open Space Strategy, Masterplans and Development Briefs. 
iii)  Mitigation/modification to the existing transport network (including road and rail)
to address the impact of the proposed development in terms of safety and
efficiency.  This may include but not be limited to passing places, road
widening, junction enhancement, bus stop infrastructure, and drainage
infrastructure.  A number of potential road and transport improvements are
identified and shown on the Town and Village Maps as Transport Proposals
(TSP's) including the interventions in the Elgin Transport Strategy. These
requirements are not exhaustive and do not pre-empt any measures which may
result from the Transport Assessment process. 
iv)  Electric car charging points must be provided at all commercial and community
parking facilities.  Access to charging points must also be provided for
residential properties, where in-curtilage facilities cannot be provided to any
individual residential property then access to communal charging facilities
should be made available.  Access to other nearby charging facilities will be
taken into consideration when identifying the need for communal electric
charging points. 
v)  Active Travel and Core Path requirements specified in the Council's Active
Travel Strategy and Core Path Plan. 
vi)  Safe transport and access routes linking to existing networks and mitigating the
impacts of development off-site. 
vii)  Information Communication Technology (ICT) and fibre optic broadband
connections for all premises unless justification is provided to substantiate it is
technically unfeasible. 
Page 95

Page 96

viii)  Foul and surface water drainage, including Sustainable Urban Drainage
Systems (SUDS), including construction phase SUDS. 
ix)  Measures that implement the waste management hierarchy as defined in the
Zero Waste Plan for Scotland including the provision of local waste storage and
recycling facilities designed into the development in accord with policy PP1
Placemaking.  For major applications a site waste management plan may be
required to ensure that waste minimisation is achieved during the construction
phase. 
x)  Infrastructure required to improve or increase capacity at Water Treatment
Works and Waste Water Treatment Works will be supported subject to
compliance with policy DP1. 
xi) A utilities plan setting out how existing and new utility (including gas, water,
electricity pipelines and pylons) provision has been incorporated into the layout
and design of the proposal.  This requirement may be exempted in relation to
developments where the council considers it might not be appropriate, such as
domestic or very small scale built developments and some changes of use. 
b)  Development proposals will not be supported where they:
i)  Create new accesses onto trunk roads and other main/key routes (A941 & A98)
unless significant economic benefits are demonstrated or such access is
required to facilitate development that supports the provisions of the
development plan. 
ii)  Adversely impact on active travel routes, core paths, rights of way, long
distance and other access routes and cannot be adequately mitigated by an
equivalent or better alternative provision in a location convenient for users. 
iii)  Adversely impact on blue/green infrastructure, including green networks
important for wildlife unless an equivalent or better alternative provision will be
provided. 
iv)  Are incompatible with key waste sites at Dallachy, Gollanfield, Moycroft and
Waterford and would prejudice their operation. 
v)  Adversely impact on community and recreational sites, buildings or
infrastructure including CF designations and cannot be adequately mitigated. 
vi)  Adversely impact on flood alleviation and mitigation infrastructure. 
vii)  Compromise the economic viability of bus or rail facilities.   
c)  Harbours 
Development within and diversification of harbours to support their sustainable
operation will be supported subject to compliance with other policies and settlement
statements. 
d)  Developer Obligations 
Developer obligations will be sought to mitigate any measurable adverse impact of a
development proposal on local infrastructure, including education, healthcare,
Page 96

Page 97

transport (including rail), sports and recreational facilities and access routes. 
Obligations will be sought to reduce, eliminate or compensate for this impact.
Developer obligations may also be sought to mitigate any adverse impacts of a
development, alone or cumulatively with other developments in the area, on the
natural environment. 
Where necessary obligations that can be secured satisfactorily by means of a
planning condition attached to planning permission will be done this way.  Where this
cannot be achieved, the required obligation will be secured through a planning
agreement in accordance with Circular 3/2012 on Planning Obligations.   
Developer obligations will be sought in accordance with the Council's Supplementary
Guidance on Developer Obligations.  This sets out the anticipated infrastructure
requirements, including methodology and rates.   
Where a developer considers that the application of developer obligations renders a
development commercially unviable a viability assessment and 'open-book
accounting' must be provided by the developer which Moray Council, via the District
Valuer, will verify, at the developer's expense.  Should this be deemed accurate then
the Council will enter into negotiation with the developer to determine a viable level
of developer obligations.   
The Council's Developer Obligations Supplementary Guidance provides further detail
to support this policy. 
DP1 DEVELOPMENT PRINCIPLES 
This policy applies to all development, including extensions and conversions and will be
applied reasonably taking into account the nature and scale of a proposal and individual
circumstances. 
The Council will require applicants to provide impact assessments in order to determine
the impact of a proposal. Applicants may be asked to determine the impacts upon the
environment, transport network, town centres, noise, air quality, landscape, trees, flood
risk, protected habitats and species, contaminated land, built heritage and archaeology
and provide mitigation to address these impacts. 
Development proposals will be supported if they conform to the relevant Local
Development Plan policies, proposals and additional guidance, meet the following criteria
and address their individual and cumulative impacts: 
(i) Design
a) The scale, density and character must be appropriate to the surrounding area
and create a sense of place (see Policy PP1) and support the principles of a
walkable neighbourhood. 
b) The development must be integrated into the surrounding landscape which will
include safeguarding existing trees and undertaking replacement planting to
include native trees for any existing trees that are felled, and safeguarding any
notable topographical features (e.g. distinctive knolls), stone walls and existing
water features by avoiding channel modifications and culverting. A tree survey
and tree protection plan must be provided with planning applications for all
Page 97

Page 98

proposals where mature trees are present on site or that may impact on trees
outwith the site. The strategy for new tree provision should follow the principles
of the "Right Tree in the Right Place". 
c) Make provision for new open space and connect to existing open space under
the requirements of Policy EP5 and provide details of the future maintenance of
these spaces. A detailed landscape plan must be submitted with planning
applications and include information about green/blue infrastructure, tree
species, planting, ground/soil conditions, and natural and man-made features
(e.g. grass areas, wildflower verges, fencing, walls, paths, etc.). 
d) Demonstrate how the development will conserve and enhance the natural and
built environment and cultural heritage resources, retain original land contours
and integrate into the landscape. 
e) Proposals must not adversely impact upon neighbouring properties in terms of
privacy, daylight or overbearing loss of amenity. 
f)  Proposals do not result in backland development or plots that are subdivided by
more than 50% of the original plot.  Sub-divided plots must be a minimum of
400m2, excluding access and the built-up area of the application site will not
exceed one-third of the total area of the plot and the resultant plot density and
layout reflects the character of the surrounding area. 
g)  Pitched roofs will be preferred to flat roofs and box dormers are not acceptable. 
h)  Existing stone walls on buildings and boundaries must be retained. 
Alterations and extensions must be compatible with the character of the
existing building in terms of design, form, choice of materials and positioning
and meet all other relevant criteria of this policy. 
i)  Proposals must orientate and design buildings to maximise opportunities for
solar gain. 
j)  All developments must be designed so as to ensure that all new buildings avoid
a specified and rising proportion of the projected greenhouse gas emissions
from their use (calculated on the basis of the approved design and plans for the
specific development) through the installation and operation of low and zero-
carbon generating technologies. 
(ii) Transportation
a) Proposals must provide safe entry and exit from the development, including the
appropriate number and type of junctions, maximise connections and routes for
pedestrians and cyclists, including links to active travel and core path routes,
reduce travel demands and ensure appropriate visibility for all road users at
junctions and bends. Road, cycling, footpath and public transport connections
and infrastructure must be provided at a level appropriate to the development
and connect people to education, employment, recreation, health, community
and retail facilities. 
b) Car parking must not dominate the street scene and must be provided to the
side or rear ¬and behind the building line. Maximum (50%) parking to the front
Page 98

Page 99

of buildings and on street may be permitted provided that the visual impact of
the parked cars is mitigated by hedging or low stone boundary walls. Roadways
with a single carriageway must provide sufficient off road parking to avoid
access routes being blocked to larger service vehicles and prevent parking on
pavements. 
c) Provide safe access to and from the road network, address any impacts on
road safety and the local road, rail and public transport network. Any impacts
identified through Transport Assessments/ Statements must be identified and
mitigated. This may include but would not be limited to, passing places, road
widening, junction improvements, bus stop infrastructure and drainage
infrastructure. A number of potential mitigation measures have been identified
in association with the development of sites and the most significant are shown
on the Proposals Map as TSP's. 
d) Provide covered and secure facilities for cycle parking at all flats/apartments,
retail, community, education, health and employment centres. 
e) Garages and parking provision must be designed to comply with Moray Council
parking specifications see Appendix 2. 
f)  The road layout must be designed to allow for the efficient mechanical
sweeping of all roadways and channels, paviors, turning areas and junctions.
The road layout must also be designed to enable safe working practices,
minimising reversing of service vehicles, with hammerheads minimised in
preference to turning areas such as road stubs or hatchets, and to provide
adequate space for the collection of waste and movement of waste collection
vehicles. 
g) The road and house layout in urban development should allow for communal
refuse collection points where the design does not allow for individual storage
within the curtilage and / or collections at kerbside. Communal collection points
may either be for the temporary storage of containers taken by the individual
householder or for the permanent storage of larger containers. The
requirements for a communal storage area are stated within the Council's
Kerbside Collection Policy, which will be a material consideration. 
h) Road signs should be minimised designed and placed at the back of footpaths
to reduce street clutter, avoid obstructing pedestrian movements and
safeguarding sightlines; 
i)  Within communal parking areas there will be a requirement for electric car
charging points. Parking spaces for car sharing must be provided where a need
is identified by the Transportation Manager. 
(iii) Water environment, pollution, contamination
a) Acceptable water and drainage provision must be made, including the use of
sustainable urban drainage systems (SUDS) for dealing with surface water
including temporary/ construction phase SUDS (see Policy EP12). 
b) New development should not be located in areas at flood risk or increase
vulnerability to flooding (see Policy EP12). Exceptions to this would only be
Page 99

Page 100

considered in specific circumstances, e.g. extension to an existing building or
change of use to an equal or less vulnerable use. Where this exception is
applied the proposed development must include resilience measures such as
raised floor levels and electrical sockets. 
c) Proposals must avoid major hazard sites and address any potential risk of
pollution including ground water contamination in accordance with recognised
pollution prevention and control measures. 
d) Proposals must protect and wherever practicable enhance water features
through for example naturalisation of watercourses by introducing a more
natural planform and removing redundant or unnecessary structures. 
e) Proposals must address and sufficiently mitigate any contaminated land issues. 
f)  Make acceptable arrangements for waste collection and management and
encourage recycling. 
g) Avoid sterilising significant workable reserves of minerals, prime agricultural
land or productive forestry. 
h)  Proposals must avoid areas at risk of coastal erosion and coastal change. 
DP9 RENEWABLE ENERGY 
a) All Renewable Energy Proposals
All renewable energy proposals will be considered favourably where they meet the
following criteria: 
i) They are compliant with policies to safeguard and enhance the built and natural
environment; 
ii) They do not result in the permanent loss or permanent damage of prime
agricultural land; 
iii) They avoid or address any unacceptable significant adverse impacts including: 
• Landscape and visual impacts.
• Noise impacts.
• Air quality impacts.
• Electromagnetic disturbance.
• Impact on water environment.
• Impact on carbon rich soils and peat land hydrology.
• Impact on woodland and forestry interests.
• Traffic impact -mitigation during both construction and operation.
• Ecological Impact.
• Impact on tourism and recreational interests. 
In addition to the above criteria, detailed assessment of impact will include
consideration of the extent to which the proposal contributes to renewable energy
generation targets, its effect on greenhouse gas emissions and net economic impact,
including socio-economic benefits such as employment.
Page 100

Page 101

b) Onshore wind turbines
In addition to the assessment of the impacts outlined in part a) above, the following
considerations will apply: 
i) The Spatial Framework 
Areas of Significant Protection (Map 2): where the Council will apply significant
protection and proposals may be appropriate in circumstances where any
significant effects on the qualities of these areas can be substantially overcome
by siting, design and other mitigation. 
Areas with Potential (Map 1): where proposals are likely to be acceptable
subject to Detailed Consideration. 
ii) Detailed Consideration
The proposal will be determined through site specific consideration of the
following on which further guidance will be set out in supplementary guidance
and as informed by the landscape capacity study: 
Landscape and visual impact:
• the landscape is capable of accommodating the development without
unacceptable significant adverse impact on landscape character or visual
amenity.
• the proposal is appropriate to the scale and character of its setting,
respects the main features of the site and the wider environment and
addresses the potential for mitigation. 
Cumulative impact
• unacceptable significant adverse impact from two or more wind energy
developments and the potential for mitigation is addressed. 
Impact on local communities
• the proposal addresses unacceptable significant adverse impact on
communities and local amenity including the impacts of noise, shadow
flicker, visual dominance and the potential for associated mitigation. 
Other
• the proposal addresses unacceptable significant adverse impacts arising
from the location within an area subject to potential aviation and defence
constraints including flight paths and aircraft radar.
• the proposal avoids or adequately resolves other impacts including on the
natural and historic environment, cultural heritage, biodiversity, forest and
woodlands and tourism and recreational interests - core paths, visitor
centres, tourist trails and key scenic routes.
• the proposal addresses any physical site constraints and appropriate
provision for decommissioning and restoration. 
iii) Extensions and Repowering of Existing Wind Farms 
The proposal will be determined through assessment of the details of the
proposal against Part a) and Parts b) (i) and (ii) above.  Detailed assessment of
impact will include consideration of the extent to which:
Page 101

Page 102

• the proposal, for extensions, impacts on the existing wind farm(s) setting
and the ability to sit in the landscape on its own should the existing wind
farm be decommissioned before the extension.
• the proposal, for repowering, makes use of existing infrastructure and
resources, where possible, and limits the need for additional footprint. 
c) Biomass
Proposals for the development of commercial biomass will be supported if the
following criteria are met. 
• Applicants must confirm which form of biomass will fuel the plant and if a
mixture of biomass is proposed then what percentage split will be attributed to
each fuel source.
• Proposals must demonstrate that they have taken account of the amount of
supply fuel over the life of the project.
• When considering wood biomass proposals, the scale and location of new
development is appropriate to the volume of local woodfuel available. Sources
of fuel must be identified and must be sustainable.
• The location must have suitable safe access arrangements and be capable of
accommodating the potential transport impacts within the surrounding roads
network.
• A design statement must be submitted, which should include photomontages
from viewpoints agreed by the Council.
• There must be a locational justification for proposals outwith general
employment land designations. The proposed energy use, local heat users and
connectivity of both heat users and electricity networks must be detailed.
Proposals which involve potential or future heat users will not be supported
unless these users can be brought online in conjunction with the operation of
the plant.
• Details of the predicted energy input and output from the plant demonstrating
the plant efficiency and utilisation of heat must be provided.
• Where necessary, appropriate structural landscaping must be provided to
assist the development to integrate sensitively. 
The criteria set out in relation to all renewable energy proposals (part a) must also be
met. 
The Council will consult with Scottish Forestry to help predict potential woodfuel
supply projections in the area. 
d) Heat
Where a heat network exists or is planned, proposals should include infrastructure to
allow connection to that network. 
Where no heat network is present or planned: 
• Proposals should consider the feasibility for the creation of or connection to a
heat network.
• Proposals should safeguard piperuns within the development, to its curtilage,
for future connection to a heat network.
• Proposals should consider the provision of energy centres, or the reservation of
land for an energy centre to facilitate future connection to a heat network.
Page 102

Page 103

Proposals for new development will be compared with the Scotland Heat Map to
identify if it could make use of an existing heat supply or provide excess heat to heat
users.  This will be the case until the Council has concluded work on identifying
where heat networks, heat storage and energy centres exist or would be appropriate
in the plan area, at which point reference to that work should be made. 
Developments which have a high heat demand are encouraged to co-locate with
sources of heat supply. 
Where heat networks are not viable, proposals should include the use of
microgeneration technologies and heat recovery associated with individual
properties, unless demonstrating this is unnecessary or unviable. 
The criteria set out in relation to all renewable energy proposals (part a) must also be
met. 
EP14 POLLUTION, CONTAMINATION & HAZARDS
a)  Pollution
Development proposals which may cause significant air, water, soil, light or noise
pollution or exacerbate existing issues must be accompanied by a detailed
assessment report on the levels, character and transmission of the potential pollution
with measures to mitigate impacts. Where significant or unacceptable impacts
cannot be mitigated, proposals will be refused.   
b) Contamination
Development proposals on potentially contaminated land will be approved where
they comply with other relevant policies and; 
i) The applicant can demonstrate through site investigations and risk assessment,
that the site is in a condition suitable for the proposed development and is not
causing significant pollution of the environment; and
ii) Where necessary, effective remediation measures are agreed to ensure the
site is made suitable for the new use and to ensure appropriate disposal and/ or
treatment of any hazardous material. 
c) Hazardous sites
Development proposals must avoid and not impact upon hazardous sites or result in
public safety concerns due to proximity or use in the vicinity of hazardous sites. 
EP1 NATURAL HERITAGE DESIGNATIONS
a) European Site designations 
Development likely to have a significant effect on a European Site and which is not
directly connected with or necessary to the conservation management of that site
must be subject to an appropriate assessment of the implications for its conservation
objectives. Proposals will only be approved where the appropriate assessment has
ascertained that there will be no adverse effect on the integrity of the site. 
In exceptional circumstances, proposals that could affect the integrity of a European
Site may be approved where: 
i) There are no alternative solutions, and
Page 103

Page 104

ii) There are imperative reasons of over-riding public interest including those of a
social or economic nature, and
iii) Compensatory measures are provided to ensure that the overall coherence of
the Natura network is protected. 
For European Sites hosting a priority habitat or species (as defined in Article 1 of the
The Conservation (Natural Habitat & c.) Regulations 1994), prior consultation with
the European Commission via Scottish Ministers is required unless the imperative
reasons of overriding public interest relate to human health, public safety or
beneficial consequences of primary importance to the environment. 
b) National designations 
Development proposals which will affect a National Park, National Scenic Area
(NSA), Site of Special Scientific Interest (SSSI) or National Nature Reserve will only
be permitted where:
i) The objectives of designation and the overall integrity of the area will not be
compromised; or
ii) Any significant adverse effects on the qualities for which the site has been
designated are clearly outweighed by social, environmental or economic
benefits of national importance. 
c) Local Designations 
Development proposals likely to have a significant adverse effect on Local Nature
Reserves, wildlife sites or other valuable local habitats will be refused unless it can
be demonstrated that;
i) Public benefits clearly outweigh the nature conservation value of the site, and
ii) There is a specific locational requirement for the development, and
iii) Any potential impacts can be satisfactorily mitigated to conserve and enhance
the site's residual conservation interest. 
d) European Protected Species 
European Protected Species are identified in the Habitats Regulations 1994 (as
amended in Scotland). Where a European Protected Species may be present or
affected by development or activity arising from development, a species survey and
where necessary a Species Protection Plan should be prepared to accompany the
planning application, to demonstrate how the Regulations will be complied with. The
survey should be carried out by a suitably experienced and licensed ecological
surveyor. 
Proposals that would have an adverse effect on European Protected Species will not
be approved unless; 
• The need for development is one that is possible for SNH to grant a license for
under the Regulations (e.g. to preserve public health or public safety).
• There is no satisfactory alternative to the development.
• The development will not be detrimental to the maintenance of the favourable
conservation status of the species. 
e) Other protected species 
Wild birds and a variety of other animals are protected under domestic legislation,
such as the Wildlife and Countryside Act 1981 (as amended in Scotland by the
Nature Conservation (Scotland) Act 2004 and the Wildlife and Natural Environment
Page 104

Page 105

(Scotland) Act 2011), Protection of Badgers Act 1992 and Marine (Scotland) Act
2010. Where a protected species may be present or affected by development or
activity arising from development, a species survey and where necessary a Species
Protection Plan should be prepared to accompany the planning application to
demonstrate how legislation will be complied with. The survey should be carried out
by a suitably experienced ecological surveyor, who may also need to be licensed
depending on the species being surveyed for. 
Proposals which would have an adverse effect on badgers or their setts must be
accompanied by a Badger Protection Plan demonstrating how impacts will be
avoided, mitigated, minimised or compensated for. 
EP2 BIODIVERSITY
All development proposals must, where possible, retain, protect and enhance features of
biological interest and provide for their appropriate management.  Development must
safeguard and where physically possible extend or enhance wildlife corridors and
green/blue networks and prevent fragmentation of existing habitats. 
Development should integrate measures to enhance biodiversity as part of multi-functional
spaces/ routes. 
Proposals for 4 or more housing units or 1000 m2 or more of commercial floorspace must
create new or, where appropriate, enhance natural habitats of ecological and amenity
value. 
Developers must demonstrate, through a Placemaking Statement where required by
Policy PP1 which incorporates a Biodiversity Plan, that they have included biodiversity
features in the design of the development. Habitat creation can be achieved by providing
links into existing green and blue networks, wildlife friendly features such as wildflower
verges and meadows, bird and bat boxes, amphibian friendly kerbing, wildlife crossing
points such as hedgehog highways and planting to encourage pollination, wildlife friendly
climbing plants, use of hedges rather than fences, incorporating biodiversity measures into
SUDS and retaining some standing or lying dead wood, allotments, orchards and
woodlands. 
Where development would result in loss of natural habitats of ecological amenity value,
compensatory habitat creation will be required where deemed appropriate. 
EP7 FORESTRY, WOODLANDS AND TREES
a) Moray Forestry and Woodland Strategy 
Proposals which support the economic, social and environmental objectives and
projects identified in the Moray Forestry and Woodlands Strategy will be supported
where they meet the requirements of other relevant Local Development Plan
policies.  The council will consult Scottish Forestry on proposals which are
considered to adversely affect forests and woodland.  Development proposals must
give consideration to the relationship with existing woodland and trees including
shading, leaf/needle cast, branch cast, wind blow, water table impacts and
commercial forestry operations. 
b) Tree Retention and Survey 
Proposals must retain healthy trees and incorporate them within the proposal unless
it is technically unfeasible to retain these.  Where trees exist on or bordering a
Page 105

Page 106

development site, a tree survey, tree protection plan and mitigation plan must be
provided with the planning application if the trees or trees bordering the site (or their
roots) have the potential to be affected by development and construction activity. 
Proposals must identify a safeguarding distance to ensure construction works,
including access and drainage arrangements, will not damage or interfere with the
root systems in the short or longer term.  A landscaped buffer may be required where
the council considers that this is required to maintain an appropriate long term
relationship between proposed development and existing trees and woodland. 
Where it is technically unfeasible to retain trees, compensatory planting on a one for
one basis must be provided in accordance with (e) below. 
c) Control of Woodland Removal 
In support of the Scottish Government's Control of Woodland Removal Policy,
Woodland removal within native woodlands identified as a feature of sites protected
under Policy EP1 or woodland identified as Ancient Woodland will not be supported. 
In all other woodlands development which involves permanent woodland removal will
only be permitted where it would achieve significant and clearly defined additional
public benefits (excluding housing) and where removal will not result in unacceptable
adverse effects on the amenity, landscape, biodiversity, economic or recreational
value of the woodland or prejudice the management of the woodland. 
Where it is proposed to remove woodland, compensatory planting at least equal to
the area to be felled must be provided in accordance with e) below. 
d) Tree Preservation Orders and Conservation Areas 
The council will serve Tree Preservation Orders (TPO's) on potentially vulnerable
trees which are of significant amenity value to the community as whole, trees that
contribute to the distinctiveness of a place or trees of significant biodiversity value. 
Within Conservation Areas, the council will only agree to the felling of dead, dying, or
dangerous trees. Trees felled within Conservation Areas or subject to TPO must be
replaced, unless otherwise agreed by the council. 
e) Compensatory Planting 
Where trees or woodland are removed in association with development, developers
must provide compensatory planting to be agreed with the planning authority either
on site, or an alternative site in Moray which is in the applicant's control or through a
commuted payment to the planning authority to deliver compensatory planting and
recreational greenspace. 
GUIDANCE TREES AND DEVELOPMENT
Trees are an important part of Moray's towns and villages and surrounding countryside,
adding colour and interest to the townscape and a sense of nature in our built
environment. They contribute to the diversity of the countryside, in terms of landscape,
wildlife habitat and shelterbelts. Trees also have a key role to play in terms of climate
change by helping to absorb carbon dioxide which is one of the main greenhouse gases
that cause global warming. 
The cumulative loss of woodlands to development can result in significant loss of
woodland cover. In compliance with the Scottish Government Control of Woodland
Page 106

Page 107

Removal policy, woodland removal should only be allowed where it would achieve
significant and clearly defined additional public benefits. In appropriate cases a proposal
for compensatory planting may form part of this balance. Where woodland is to be
removed then the Council will require compensatory planting to be provided on site, on
another site in Moray within the applicant's control or through a commuted payment to the
Council towards woodland and greenspace creation and enhancement. Developers
proposing compensatory planting are asked to follow the guidance for site assessment
and woodland design as laid out in Scottish Forestry's "Woodland Creation, Application
Guidance" and its subsequent updates, when preparing their proposal. 
The Council requires a Tree Survey and Tree Protection Plan to be submitted by the
applicant with any planning application for detailed permission on designated or windfall
sites which have trees on them. The survey should include a schedule of trees and/or
groups of trees and a plan showing their location, along with the following details; 
• Reference number for each tree or group of trees.
• Scientific and common names.
• Height and canopy spread in metres (including consideration of full height and
spread).
• Root protection area.
• Crown clearance in metres.
• Trunk diameters in metres (measures at 1.5m above adjacent ground level for single
stem trees or immediately above the root flare for multi stemmed trees).
• Age and life expectancy.
• Condition (physiological and structural).
• Management works required.
• Category rating for all trees within the site (U, A, B or C *). This arboricultural
assessment will be used to identify which trees are suitable for retention within the
proposed development. 
*BS5837 provides a cascading quality assessment process for categorisation of trees
which tree surveys must follow. An appropriately scaled tree survey plan needs to
accompany the schedule. The plan should be annotated with the details of the tree
survey, showing the location, both within and adjacent to the site, of existing trees, shrubs
and hedgerows. Each numbered tree or groups of trees should show the root protection
area and its category U, A, B, C. 
Based on the guidance in BS5837, only category U trees are discounted from the Tree
Survey and Tree Protection Plan process. Trees in category A and B must be retained,
with category C trees retained as far as practicable and appropriate. Trees proposed for
removal should be replaced with appropriate planting in a landscape plan which should
accompany the application. Trees to be retained will likely be set out in planning
conditions, if not already covered by a Tree Preservation Order. 
If a tree with habitat value is removed, then measures for habitat reinstatement must be
included in the landscape plan. It is noted that in line with part b) of policy EP7 where
woodland is removed compensatory planting must be provided regardless of tree
categorisation." 
A Tree Protection Plan (TPP) must also be submitted with planning applications,
comprising a plan and schedule showing; 
Page 107

Page 108

• Proposed design/ layout of final development, including accesses and services.
• Trees to be retained- with those requiring remedial work indicated.
• Trees to be removed.
• Location (and specification) of protective fencing around those trees to be retained
based on the Root Protection Area. 
The TPP should show how the tree survey information has informed the design/ layout
explaining the reasoning for any removal of trees. 
Landscape Scheme
Where appropriate a landscape scheme must be submitted with planning applications,
clearly setting out details of what species of trees, shrubs and grass are proposed, where,
what standard and when planting will take place. Landscape schemes must aim to deliver
multiple benefits in terms of biodiversity, amenity, drainage and recreation as set out in
policy. 
The scheme should also set out the maintenance plan. Applicants/ developers will be
required to replace any trees, shrubs or hedges on the site which die, or are dying,
severely damaged or diseased which will be specified in planning conditions. 
Tree species native to Scotland are recommended for planting in new development -
Alder, Aspen, Birch, Bird Cherry, Blackthorn, Crab Apple, Elm, Gean, Hawthorn, Hazel,
Holly, Juniper, Sessile Oak, Rowan, Scots Pine, Whitebeam, Willow. 
EP8 HISTORIC ENVIRONMENT
a) Scheduled Monuments and Unscheduled Archaeological Sites of Potential
National Importance. 
Where a proposed development potentially has a direct impact on a Scheduled
Monument, Scheduled Monument Consent (SMC) is required, in addition to any
other necessary consents.  Historic Environment Scotland manage these consents. 
Development proposals will be refused where they adversely affect the integrity of
the setting of Scheduled Monuments and unscheduled archaeological sites of
potential national importance unless the developer proves that any significant
adverse effects are clearly outweighed by exceptional circumstances, including
social or economic benefits of national importance. 
b) Local Designations 
Development proposals which adversely affect sites of local archaeological
importance or the integrity of their settings will be refused unless; 
• Local public benefits clearly outweigh the archaeological value of the site, and
• Consideration has been given to alternative sites for the development and
preservation in situ is not possible.
• Where possible any adverse effects can be satisfactorily mitigated at the
developer's expense. 
The Council will consult Historic Environment Scotland and the Regional
Archaeologist on development proposals which may affect Scheduled Monuments,
nationally important archaeological sites and locally important archaeological sites. 
Page 108

Page 109

EP15 MOD SAFEGUARDING
Development proposals must not adversely impact upon Ministry of Defence safeguarding
operations. Details of consultation zones for Kinloss Barracks and RAF Lossiemouth and
development types which will be subject to consultation with the Defence Infrastructure
Organisation are available from Moray Council. The outer boundaries of the zones are
shown on the Proposals Map. 
Page 109

Page 110

Page 110