Moray Local Review Body 
Thursday, 15 June 2023 
NOTICE IS HEREBY GIVEN that a Meeting of the Moray Local Review Body is to
be held at Council Chambers, Council Office, High Street, Elgin, IV30 1BX on
Thursday, 15 June 2023 at 09:30. 
BUSINESS 
1 Sederunt 
2 Declaration of Group Decisions and Members Interests * 
3 Minute of Meeting dated 15 June 2023 5 - 12
4 LR289 - Ward 4 - Fochabers Lhanbryde
Planning Application 22/01292/APP – Erect dwellinghouse on Plot 3,
Milnduff, Drybridge, Buckie  
13 -
108
5 LR288 - Ward 7 - Elgin City South
Planning Application 22/01451/APP – Retrospective permission for
boundary fence at 94 Springfield Road, Elgin  
109 -
152 
Summary of Local Review Body functions:
To conduct reviews in respect of refusal of planning permission or
unacceptable conditions as determined by the delegated officer, in
terms of the Scheme of Delegation to Officers under Section 43(A)(i) of
the Town & Country Planning (Scotland) Act 1997 and the Town &
Country Planning (Scheme of Delegation and Local Review
Procedure)(Scotland) Regulations 2013, or where the Delegated
Officer has not determined the application within 3 months of
registration.     
Page 1

Page 2

Page 2

Page 3

GUIDANCE NOTES 
* Declaration of Group Decisions and Members Interests - The Chair of the
meeting shall seek declarations from any individual or political group at the
beginning of a meeting whether any prior decision has been reached on how
the individual or members of the group will vote on any item(s) of business on
the Agenda, and if so on which item(s).  A prior decision shall be one that the
individual or the group deems to be mandatory on the individual or the group
members such that the individual or the group members will be subject to
sanctions should they not vote in accordance with the prior decision.  Any such
prior decisions will be recorded in the Minute of the meeting. 
** Written Questions - Any Member can put one written question about any
relevant and competent business within the specified remits not already on the
agenda, to the Chair provided it is received by the Proper Officer or Committee
Services by 12 noon two working days prior to the day of the meeting.  A copy
of any written answer provided by the Chair will be tabled at the start of the
relevant section of the meeting.  The Member who has put the question may,
after the answer has been given, ask one supplementary question directly
related to the subject matter, but no discussion will be allowed. 
No supplementary question can be put or answered more than 10 minutes after
the Council has started on the relevant item of business, except with the
consent of the Chair. If a Member does not have the opportunity to put a
supplementary question because no time remains, then he or she can submit it
in writing to the Proper Officer who will arrange for a written answer to be
provided within 7 working days. 
*** Question Time - At each ordinary meeting of the Committee ten minutes will be
allowed for Members questions when any Member of the Committee can put a
question to the Chair on any business within the remit of that Section of the
Committee.  The Member who has put the question may, after the answer has
been given, ask one supplementary question directly related to the subject
matter, but no discussion will be allowed. 
No supplementary question can be put or answered more than ten minutes
after the Committee has started on the relevant item of business, except with
the consent of the Chair.  If a Member does not have the opportunity to put a
supplementary question because no time remains, then he/she can submit it in
writing to the proper officer who will arrange for a written answer to be provided
within seven working days. 
Page 3

Page 4

THE MORAY COUNCIL 
Moray Local Review Body 
SEDERUNT 
Councillor Marc Macrae  (Chair)
Councillor Amber Dunbar  (Depute Chair)  
Councillor Neil Cameron  (Member)
Councillor Juli Harris  (Member)
Councillor Sandy Keith  (Member)
Councillor Paul McBain  (Member)
Councillor Derek Ross  (Member)
Councillor Draeyk Van Der Horn  (Member)
Councillor Sonya Warren  (Member)  
Clerk Name: Lissa Rowan
Clerk Telephone: 07765 741754
Clerk Email: committee.services@moray.gov.uk 
Page 4

Page 5

MORAY COUNCIL 
Minute of Meeting of the Moray Local Review Body 
Thursday, 20 April 2023 
Council Chambers, Council Office, High Street, Elgin, IV30 1BX 
PRESENT 
Councillor Neil Cameron, Councillor Amber Dunbar, Councillor Juli Harris, Councillor
Sandy Keith, Councillor Marc Macrae, Councillor Paul McBain, Councillor Derek
Ross, Councillor Draeyk Van Der Horn, Councillor Sonya Warren 
IN ATTENDANCE 
Mrs L MacDonald, Senior Planning Officer Mr A Miller, Senior Planning Officer and
Miss K Donnachie, Planning Officer as Planning Advisers, Mr S Hoath, Senior
Solicitor and Mrs J Smith, Solicitor as Legal Advisers and Mrs L Rowan, Committee
Services Officer as Clerk to the Committee. 
1         Chair 
Councillor Macrae, being Chair of the Moray Local Review Body, chaired the
meeting.   
2         Declaration of Group Decisions and Members Interests 
In terms of Standing Order 21 and the Councillor's Code of Conduct, there were no
declarations from Group Leaders or Spokespersons in regard to any prior decisions
taken on how Members will vote on any item on the agenda or any declarations of
Members interests in respect of any item on the agenda.  
For transparency, in relation to Item 6, Case LR285, Councillor Warren stated that
in the previous Council term, local Buckie Ward Members had been consulted on
the sale of this land and that the Applicant is also a member of the Findochty
Community Council however she stated that this would not influence her judgement
when determining this application.  
Councillor Warren further noted that Item 4, Case LR283 was not in Buckie and that
the Case should state that the proposal is in the Fochabers Lhanbryde Ward.   
3         Minute of Meeting dated 16 February 2023 
The Minute of the meeting dated 16 February 2023 was submitted and approved.   
4         Order of Business 
The Chair sought the agreement of the Moray Local Review Body to vary the order
business and take the cases in the following order, Item 4 Case LR283, Item 6
Item 3
Page 5

Page 6

LR285, Item 5 LR284, Item 7 LR286 and Item 8 LR 287, to allow Officers to be
present for the relevant items of business.  This was agreed.   
5         Case LR283 - Ward 4 – Fochabers Lhanbryde 
Planning Application 22/00164/PPP – Erect a dwellinghouse on site at
Broadly by Buckie  
A request was submitted by the Applicant, seeking a review of the decision of the
Appointed Officer, in terms of the Scheme of Delegation, to refuse planning
permission on the grounds that:  
The development would result in an intensification of use of the access junction
onto the public road, where there is presently restricted visibility and which would be
likely to give rise to conditions detrimental to the road safety of road users contrary
to Moray Local Development Plan (MLDP) policy DP1 (Development Principles)
section (ii) - 'Transportation', part 'a)' (safe entry and exit).  
A Summary of Information Report set out the reasons for refusal, together with the
documents considered or prepared by the Appointed Officer in respect of the
planning application, in addition to the Notice of Review, Grounds for Review and
supporting documents submitted by the Applicant.  
In response to a question from the Chair as to whether the Legal or Planning
Advisers had any preliminary matters to raise, both the Legal and Planning Advisers
advised that they had nothing to raise at this time.  
The Chair then asked the Moray Local Review Body (MLRB) if it had sufficient
information to determine the request for review.  In response, the MLRB
unanimously agreed that it had sufficient information to determine the case.  
Councillor Dunbar, having visited the site and considered the Case in detail, moved
that the MLRB uphold the appeal and grant planning permission in principle in
relation to Planning Application 22/00164/PPP with a condition to resolve any
issues in relation to land ownership and the visibility splay prior to start of any
development.  This was seconded by Councillor Warren.  
In response, the Legal Adviser pointed out that the reason for refusal was that the
proposal did not comply with policy DP1 (Development Principles) of the MLDP
2020 in terms of safe entry to and from the site and sought clarification as to
whether Councillor Dunbar was of the view that the proposal complied with Policy
DP1 or was an acceptable departure from Policy DP1.  
Councillor Dunbar stated that it was her understanding that if the issues of land
ownership and visibility splay were rectified, then the proposal would comply with
policy.  
Mrs MacDonald, Planning Adviser confirmed that the Appointed Officer was of the
view that these issues could not be adequately controlled by condition, however it
was up to the MLRB to decide whether these issues could be controlled by
condition.  Mrs MacDonald further stated that approval of this application was
subject to a legal agreement in terms of developer obligations and that the
Transportation Service had recommended that access to and from the development
should be from at least 15 metres down the private track rather than the public road
Page 6

Page 7

and that EV charging would also be required and sought the agreement of the
MLRB to add these condtions and also any standard conditions and informatives if
minded to approve the planning application..    
In response, Councillor Dunbar agreed to add these conditions to her motion for
approval.  
Councillor Harris sought clarification as to whether there would be any condition in
relation to the height of fencing or vegetation at the visibility splay.  
In response, Mrs MacDonald stated that the visibility splay condition would limit the
height of fencing or vegetation to no more than 0.6 metre.  
There being no-one otherwise minded, the MLRB unanimously agreed to uphold
the appeal and grant planning permission in principle in relation to Planning
Application 22/00164/PPP subject to:  
(i) the inclusion of conditions to address the issues of land ownership and
visibility splay with fencing/vegetation no more than a height of 0.6 metre; 
(ii) the completion of a legal agreement in terms of developer obligations; 
(iii) a condition to ensure that access to and from the development should be from
at least 15 metres down the private track rather than the public road; 
(iv) a condition to ensure the provision of EV charging; and 
(v) any other standard conditions and informatives.   
6         Case LR285 - Ward 3 - Buckie 
Planning Application 22/00327/APP – Change of use of amenity land to
garden ground at Rockside, 8 Jubilee Terrace, Findochty, Buckie  
Under reference to paragraph 4 of the Minute of the meeting of the Moray Local
Review Body (MLRB) dated 16 February 2023, a request was submitted by the
Applicant, seeking a review of the decision of the Appointed Officer, in terms of the
Scheme of Delegation, to refuse planning permission on the grounds that:  
The proposal would be contrary to policies EP9, EP3, EP6 and DP1 of the Moray
Local Development Plan (MLDP) 2020 for the following reasons: 
1 This proposed change of use would result in the loss of a portion of
distinctive grassland, which acts as an attractive transition between the built
up area of the village and the beach beyond and also acts as a useful
amenity area and as such its loss would have an adverse impact on the
amenity, character and appearance of the conservation area in which it lies
and the qualities of the wider Special Landscape Area. 
2 The proposed site straddles the settlement boundary, with the majority of
the site lying out with the settlement boundary, where policy EP6 precludes
any development immediately out with the settlement boundary and in this
instance, given the adverse impacts on the character and amenity of the
area which would result from the development, there is not considered to be
Page 7

Page 8

any material planning considerations which would merit departing from
policy. 
A Summary of Information Report set out the reasons for refusal, together with the
documents considered or prepared by the Appointed Officer in respect of the
planning application, in addition to the Notice of Review, Grounds for Review and
supporting documents submitted by the Applicant.  
In response to a question from the Chair as to whether the Legal or Planning
Advisers had any preliminary matters to raise, the Legal Adviser advised that he
had nothing to raise at this time.   
Mrs MacDonald, Planning Adviser advised that the Case included 2 copies of the
plan, one being the original plan and another called “Revision A” and that
Members should consider “Revision A”, as this was the plan that was refused. This
was noted.  
Councillor Warren stated that local Ward Members had been consulted on the sale
of land referred to in this proposal and sought guidance from the Legal Adviser as
to whether she should declare a full interest in this case and take no part in the
consideration of this item.  
In response, the Legal Adviser advised that it is up to each member to decide
whether they can fairly consider each application based on the information provided
within the case.  
In response, Councillor Warren stated that local Ward Members had been provided
with 3 options in relation to the sale of this land and that they had settled on one
option therefore declared a full interest in this item, left the meeting at this juncture
and took no further part in the consideration of this item.  
Councillor Cameron, having visited the site and considered the case in detail,
agreed with the original decision of the Appointed Officer stating that permitting the
development would erode public land and moved that the MLRB refuse the appeal
and uphold the original decision of the Appointed Officer to refuse Planning
Application 22/00327/APP as the proposal does not comply with policies EP9
(Conservation Areas), EP3 (Special Landscape Areas and Landscape Character),
EP6 (Settlement Boundaries) and DP1 (Development Principles) of the MLDP
2020.  This was seconded by Councillor Harris.  
There being no-one otherwise minded, the MLRB agreed to refuse the appeal and
uphold the original decision of the Appointed Officer to refuse Planning Application
22/00327/APP as the proposal does not comply with policies EP9 (Conservation
Areas), EP3 (Special Landscape Areas and Landscape Character), EP6
(Settlement Boundaries) and DP1 (Development Principles) of the MLDP 2020. 
Councillor Warren re-joined the meeting at this juncture.   
7         Case LR284 - Ward 4 - Fochabers Lhanbryde 
Planning Application 22/01066/APP – Alter and extend dwellinghouse at 35
Gordon Street, Portgordon, Buckie  
Page 8

Page 9

Under reference to paragraph 4 of the Minute of the meeting of the Moray Local
Review Body (MLRB) dated 16 February 2023, a request was submitted by the
Applicant, seeking a review of the decision of the Appointed Officer, in terms of the
Scheme of Delegation, to refuse planning permission on the grounds that:  
The proposed alterations and extension are contrary to Moray Local Development
Plan 2020 policy DP1(i)(a) for the following reasons: 
1 The proposed rear dormers are considered unacceptable as they are of an
irregular shape which is not keeping with the form and character of the
existing traditional property and surrounding area. 
2 The proposed first floor extension incorporates an irregular roof shape
giving the appearance of a two storey flat roof extension which creates
unnecessary bulk and is incongruous with the main parent property.  
A Summary of Information Report set out the reasons for refusal, together with the
documents considered or prepared by the Appointed Officer in respect of the
planning application, in addition to the Notice of Review, Grounds for Review and
supporting documents submitted by the Applicant.  
In response to a question from the Chair as to whether the Legal or Planning
Advisers had any preliminary matters to raise, the Planning Adviser advised that
she had nothing to raise at this time.  
The Chair then asked the Moray Local Review Body (MLRB) if it had sufficient
information to determine the request for review.  In response, the MLRB
unanimously agreed that it had sufficient information to determine the case.  
Councillor Van Der Horn, having considered the case in detail, moved that the
appeal be upheld and planning permission granted in respect of Planning
Application 22/01066/APP.  He acknowledged concerns in relation to the view of
the proposal from the west however stated that this could be mitigated with a
condition asking that more planting be provided.  In terms of the design of the
proposal, Councillor Van Der Horn was of the view that the modern design was
acceptable and added to architectural diversity.  He further noted the support of the
local Portgordon Community Trust.  With regard to some concerns of the proposal
being viewed as a block, Councillor Van Der Horn suggested that new drawings
could be submitted to mitigate against those concerns.  
Councillor Cameron agreed with Councillor Van Der Horn’s comments and
seconded his motion.  
Mr Hoath, Legal Adviser reminded the MLRB of the reasons for refusal set out in
the Summary of Information report and sought clarification from Councillor Van Der
Horn as to whether the policy complies with, or is an acceptable departure from,
policy DP1 (Development Principles) (i)(a).  He further noted Councillor Van Der
Horn's comments in relation to increased planting and new drawings and asked if
these were to be addressed by means of condition.  
In response, Councillor Van Der Horn stated that this proposal would be an
acceptable departure from policy as there are already examples of similar
extensions in the area with a condition to add additional planting to mitigate against
the impact from the view from the west.  Councillor Van Der Horn went on to retract
his previous comments in relation to additional drawings.  Councillor Cameron
Page 9

Page 10

confirmed that, after considering Councillor Van Der Horn's further comments, he
still wished to second his motion.  
Miss Donnachie, Planning Adviser advised that, should the MLRB be minded to
uphold the appeal and grant planning permission, a condition could be added in
relation to the increased landscaping requiring that a landscape plan be provided in
addition to standard conditions and informatives.  She further sought clarification
from Councillor Van Der Horn as to whether he considered the proposal to be a
departure from policy DP1(i)(a) or whether he was of the view the proposal
complied with policy.  
In response, Councillor Van Der Horn stated that in some way the proposal is a
departure as the proposal has an impact however complied as it would not
adversely affect the character of the street, and on the whole was of the view that
the proposal complied with policy DP1(i)(a).  
Councillor Ross, having visited the site and considered the case in detail agreed
with the original decision of the Appointed Officer to refuse the application as it is
contrary to policy DP1(i)(a) and moved as an amendment, that the MLRB agree to
refuse the appeal and uphold the original decision of the Appointed Officer to refuse
Planning Application 22/01066/APP as it is contrary to policy DP1 (Development
Principles) (i)(a) of the MLDP 2020.  This was seconded by Councillor Warren. 
On a division there voted: 
For the Motion (6):  Councillors Van Der Horn, Cameron, Dunbar, Harris,
Macrae and McBain 
For the Amendment
(3): Councillors Ross, Warren and Keith
Abstentions (0): Nil  
Accordingly, the Motion became the finding of the Meeting and the MLRB agreed to
uphold the appeal and grant planning permission in respect of Planning Application
22/01066/APP as the proposal complies with policy DP1 (Development Principles)
(i)(a) of the MLDP 2020 with the inclusion of a condition for the provision of
increased landscaping including a landscape plan, as well as standard conditions
and informatives.   
8         Case LR286 - Ward 5 - Heldon and Laich 
Planning Application 22/01594/APP – Proposed erection of garage/storage
shed and partial change of use from Farm Land to Garden Ground at The
Forecourt, Cummingston  
A request was submitted by the Applicant, seeking a review of the decision of the
Appointed Officer, in terms of the Scheme of Delegation, to refuse planning
permission on the grounds that:  
1 The proposals is contrary to Moray Local Development Plan Policies 2020
EP6 and the Cummingston Settlement Text as the proposal would introduce
a large building at the edge of the village on land that is immediately outwith
the existing settlement boundary resulting in additional linear roadside
development along the B9040 and increasing the potential for coalescence
Page 10

Page 11

with surrounding settlements. 
2 The proposals is contrary to Moray Local Development Plan Policies 2020
DP1 (i) (a) and EP3 as the development fails to reflect the traditional
settlement character in terms of siting and design as the siting of a building
of this size in this prominent location would not reflect the character of this
part of the village. 
In response to a question from the Chair as to whether the Legal or Planning
Advisers had any preliminary matters to raise, the Legal Adviser advised that he
had nothing to raise at this time.  
Mr Miller, Planning Adviser advised that Members on the site visit had noted that
some works had already commenced on the site and that, whilst some of these
works did not require planning permission, some of the works do need planning
permission including the change of use of agricultural land to garden ground, which
is subject to the planning application.  However he reminded the Moray Local
Review Body (MLRB) that the planning application should be considered based on
the information considered by the Appointed Officer at the time of determination and
no weight should be given to the partly retrospective nature of this review.  This was
noted.  
The Chair then asked the MLRB if it had sufficient information to determine the
request for review.  In response, the MLRB unanimously agreed that it had
sufficient information to determine the case.  
During discussion, the MLRB raised concern in relation to the size of the proposal
which is not in keeping with the character of the surrounding area and unanimously
agreed to uphold the original decision of the Appointed Officer to refuse planning
permission in respect of Planning Application 22/01594/APP as the proposal is
contrary to policy EP6 (Settlement Boundaries), DP1 (Development Principles) (i)
(a) and EP3 (Special Landscape Areas and Landscape Character) of the MLDP
2020.   
9         Case LR287 - Ward 4 - Fochabers Lhanbryde 
Planning Application 22/01423/APP – Change of use from amenity to garden
ground with erection of 1.8m timber fence at 10 Linksview Road, Mosstodloch  
A request was submitted by the Applicant, seeking a review of the decision of the
Appointed Officer, in terms of the Scheme of Delegation, to refuse planning
permission on the grounds that:  
The proposed development departs from the Moray Local Development Plan
(MLDP) 2020 Policy EP5 (Open Space) and Mosstodloch designation ENV6
Natural/Semi-Natural Greenspace which require ENV designations in settlement
statements to be retained as open space and where the proposal does not
constitute one of the policy exemptions to the retention of open space. The ENV
designation has been reinforced by the Mosstodloch Settlement Statement,
superseding the previous erosion of the designation from past consents. The
proposal is therefore unacceptable.  
A Summary of Information Report set out the reasons for refusal, together with the
documents considered or prepared by the Appointed Officer in respect of the
Page 11

Page 12

planning application, in addition to the Notice of Review, Grounds for Review and
supporting documents submitted by the Applicant.  
In response to a question from the Chair as to whether the Legal or Planning
Advisers had any preliminary matters to raise, both the Legal and Planning Advisers
advised that they had nothing to raise at this time.  
The Chair then asked the Moray Local Review Body (MLRB) if it had sufficient
information to determine the request for review.  In response, the MLRB
unanimously agreed that it had sufficient information to determine the case.  
Councillor Ross, having visited the site and considered the case in detail, moved
that the MLRB refuse the appeal and uphold the original decision of the Appointed
Officer to refuse planning permission in respect of Planning Application
22/01423/APP as the proposal is contrary to Policy EP5 (Open Space) of the MLDP
2020 and the Mosstodloch designation ENV6 (Natural/Semi-Natural Greenspace).  
There being no-one otherwise minded, the MLRB agreed to refuse the appeal and
uphold the original decision of the Appointed Officer to refuse planning permission
in respect of Planning Application 22/01423/APP as the proposal is contrary to
Policy EP5 (Open Space) of the MLDP 2020 and the Mosstodloch designation
ENV6 (Natural/Semi-Natural Greenspace).   
Page 12

Page 13

MORAY LOCAL REVIEW BODY 
16 MAY 2023 
SUMMARY OF INFORMATION FOR CASE No LR289 
Ward 4 – Fochabers Lhanbryde 
Planning Application 22/01292/APP – Erect dwellinghouse on Plot 3, Milnduff,
Drybridge, Buckie 
Planning permission was granted under the Statutory Scheme of Delegation by the
Appointed Officer on 16 January 2023 subject to the following conditions: 
1. The development to which this permission relates must be begun not later
than the expiration of 3 years beginning with the date on which the permission
is granted. 
Reason: The time limit condition is imposed in order to comply with the
requirements of section 58 of the Town and Country Planning (Scotland) Act
1997 as amended. 
2. No development works shall commence on the dwelling house until a detailed
drawing (scale 1:200) has been submitted to and approved in writing by the
Council, as Planning Authority in consultation with the Roads Authority
confirming the provision of, or location where a future Electric Vehicle (EV)
charging unit is to be connected to an appropriate electricity supply, including
details (written proposals and plans) to confirm the provision of the necessary
cabling, ducting, and consumer units capable of supporting the future
charging unit; and thereafter the EV charging infrastructure shall be provided
in accordance with the approved drawing and details prior to the first
occupation of the dwelling house. 
Reason: In the interests of an acceptable form of development and the
provision of infrastructure to support the use of low carbon transport, through
the provision of details currently lacking. 
3. No water shall be permitted to drain or loose material be carried onto the
public carriageway. 
Reason: To ensure the safety and free flow of traffic on the public road and
access to the site by minimising the road safety impact from extraneous
material and surface water in the vicinity of the new access.  
Item 4
Page 13

Page 14

2  
4. A visibility splay 2.4 metres by 120 metres to the north-west shall be provided
at the access onto the public road, and maintained thereafter at all times free 
from any obstruction greater than 0.6m in height measured from the level of
the carriageway. 
Reason: To enable drivers of vehicles leaving the site to have a clear view
over a length of road sufficient to allow safe exit, in the interests of road safety
for the proposed development and other road users. 
5. Three car parking spaces shall be provided within the site prior to the
occupation or completion of the dwelling house, whichever is the sooner. The
parking spaces shall thereafter be retained throughout the lifetime of the
development, unless otherwise agreed in writing with the Council as Planning
Authority. 
Reason: To ensure the permanent availability of the level of parking
necessary for residents/visitors/others in the interests of an acceptable
development and road safety. 
6. Prior to the occupation of the house hereby approved a scheme of effective
treatment to the private water supply shall be fully installed and properly
maintained for the lifetime of the development. The scheme must ensure that
the water to the house would fully comply with the regulatory limits stated in
The Water Intended for Human Consumption (Private Supplies) (Scotland)
regulations 2017 and should specifically include effective point of entry
ultraviolet treatment, prefiltration, pH correction measures and
iron/manganese treatment. 
Reason: To ensure that the development is served by an adequate and
wholesome water supply. 
7. The paddock area associated with the plot as identified in the approved site
plan, shall be only used as paddock land, and not for domestic garden
purposes. Note. For the avoidance of doubt, the paddock does not have the
benefit of permitted development rights under Article 2(4), Schedule, Part 1
Classes 3B (Building, engineering, installation or other operation within the
curtilage of a dwellinghouse for any purpose incidental to the enjoyment of the
dwellinghouse) of the Town and Country Planning (General Permitted
Development) (Scotland) Order 1992, as amended by the Town & Country
Planning (General Permitted Development) (Scotland) Amendment Order
2011 (or any Order revoking and re-enacting that Order(s) with or without
modifications). 
Reason: To safeguard the rural character of the site and its surroundings, by
mitigating against any domestic encroachment into adjoining farm/paddock
land. 
8. Unless otherwise agreed in writing with the Planning Authority, boundary
enclosures surrounding the site hereby approved shall only comprise post and
wire fencing or hedging made up of native species (birch, gean, hawthorn,
scots pine, beech, oak, holly). In addition 15% of the plot must be landscaped
with native tree species (whips and feathered trees at least 1.5 metres in 
Page 14

Page 15

3 
height, planted at a density of 1 per 4 sqm). All planting, seeding or turfing
shall be carried out in the first planting and seeding seasons following the
commencement of development. Any trees or plants which within a period of
five years from the completion of the development die, for whatever reason
are removed or damaged shall be replaced in the next planting season with
others of the same size and species. 
Reason: To ensure an acceptable scheme of landscaping to aid the
integration of the house into the surrounding landscape and ensure the
planting is timeously provided. 
9. Notwithstanding the details shown on the approved plans, the roof of the
dwellinghouse hereby approved shall be finished in natural slate. 
Reason: To ensure the highest standards of material finish are achieved for
new housing in the countryside and that new housing is finished in a manner
which reflects the traditional material finishes of houses in Moray. 
10. The residential caravan hereby permitted is solely for the use of the applicant
or developer for the duration of the construction works associated with the
development hereby approved. Within 3 years from the date of this decision
notice or within 2 months following the occupation or completion of the
dwellinghouse, whichever is the sooner, the caravan shall be removed
permanently from the site, along with all associated fixtures and fittings. 
Reason: To ensure the removal of the residential caravan from the site
following the completion of the adjacent house, in the interests of minimising
and removing the visual impact of the caravan. 
Documents considered or prepared by the Appointed Officer in respect of the above
planning application are attached as Appendix 1. 
The Notice of the Review, Grounds for Review and any supporting documents
submitted by the Applicant are attached as Appendix 2. 
No Further Representations were received in response to the Notice of Review. 
At the meeting of the Moray Local Review Body (MLRB) on 16 February 2023, the
MLRB noted that National Planning Framework 4 (NPF4) had been adopted by the
Council on Monday 13 February 2023 and that all planning applications determined
beyond this date would have to take NPF4 into consideration, as this is now part of
the MLDP 2020 and deferred consideration of the above Review to request further
information from the Appointed Officer and Interested Parties after considering the
planning application in light of NPF4 with any response received being forwarded to
the Applicant for comment. 
NPF4 has no impact on this LRB case.
Page 15

Page 16

Page 16

Page 17

Track
Minduff
P Const & PER Bdy
Ward Bdy
158.8m
152.7m151.3m
Location plan for Planning Application Reference Number :
22/01292/APP
This map is reproduced from Ordnance Survey material with the permission of Ordnance Survey on behalf of the Controller of Her Majesty's
Stationary Office Unauthorised reproduction infringes  Crown Copyright and may lead to prosecution or civil proceedings.
(c) Crown Copyright.  The Moray Council 100023422 2023 Page 17

Page 18

Page 18

Page 19

APPENDIX 1 
DOCUMENTS CONSIDERED
OR PREPARED BY THE
APPOINTED OFFICER
Page 19

Page 20

Page 20

Page 21

Page 1 of 8
The Moray Council Council Office High Street Elgin IV30 1BX  Tel: 0300 1234561  Email: development.control@moray.gov.uk
Applications cannot be validated until all the necessary documentation has been submitted and the required fee has been paid.
Thank you for completing this application form:
ONLINE REFERENCE 100475230-004
The online reference is the unique reference for your online form only. The  Planning Authority will allocate an Application Number when
your form is validated. Please quote this reference if you need to contact the planning Authority about this application.
Type of Application
What is this application for? Please select one of the following: *
 Application for planning permission (including changes of use and surface  mineral working).
 Application for planning permission in principle.
 Further application, (including renewal of planning permission, modification, variation or removal of a planning condition etc)
 Application for Approval of Matters specified in conditions.
Description of Proposal
Please describe the proposal including any change of use: *  (Max 500 characters)
Is this a temporary permission? *  Yes  No
If a change of use is to be included in the proposal has it already taken place?  Yes  No
(Answer ‘No’ if there is no change of use.) *
Has the work already been started and/or completed? *
 No  Yes – Started  Yes - Completed
Applicant or Agent Details
Are you an applicant or an agent? * (An agent is an architect, consultant or someone else acting
on behalf of the applicant in connection with this application)  Applicant  Agent
Erect dwelling house
Page 21

Page 22

Page 2 of 8
Agent Details
Please enter Agent details
Company/Organisation:
Ref. Number: You must enter a Building Name or Number, or both: *
First Name: * Building Name:
Last Name: * Building Number:
Address 1
Telephone Number: * (Street): *
Extension Number: Address 2:
Mobile Number: Town/City: *
Fax Number: Country: *
Postcode: *
Email Address: *
Is the applicant an individual or an organisation/corporate entity? *
 Individual  Organisation/Corporate entity
Applicant Details
Please enter Applicant details
Title: You must enter a Building Name or Number, or both: *
Other Title: Building Name:
First Name: * Building Number:
Address 1
Last Name: * (Street): *
Company/Organisation Address 2:
Telephone Number: * Town/City: *
Extension Number: Country: *
Mobile Number: Postcode: *
Fax Number:
Email Address: *
Mr
Christopher
Timothy
Bremner
Wright
Drybridge
Cameron Crescent
23
Minduff
07876758717
AB56 5LB
AB56 1AG
Scotland
Scotland
Buckie
Buckie
christopher.bremner@hotmail.com
Page 22

Page 23

Page 3 of 8
Site Address Details
Planning Authority:
Full postal address of the site (including postcode where available):
Address 1:
Address 2:
Address 3:
Address 4:
Address 5:
Town/City/Settlement:
Post Code:
Please identify/describe the location of the site or sites
Northing Easting
Pre-Application Discussion
Have you discussed your proposal with the planning authority? *  Yes  No
Pre-Application Discussion Details Cont.
In what format was the feedback given? *
 Meeting  Telephone  Letter  Email
Please provide a description of the feedback you were given and the name of the officer who provided this feedback. If a processing
agreement [note 1] is currently in place or if you are currently discussing a processing agreement with the planning authority, please
provide details of this. (This will help the authority to deal with this application more efficiently.) * (max 500 characters)
Title: Other title:
First Name: Last Name:
Correspondence Reference Date (dd/mm/yyyy):
Number:
Note 1. A Processing agreement involves setting out the key stages involved in determining a planning application, identifying what
information is required and from whom and setting timescales for the delivery of various stages of the process.
Revised design sent to achieve 6.75m ridge height.
Mr
Moray Council
Iain Drummond
12/08/2022
Plot 3 Minduff
860411 343427
Page 23

Page 24

Page 4 of 8
Site Area
Please state the site area:
Please state the measurement type used:  Hectares (ha)  Square Metres (sq.m)
Existing Use
Please describe the current or most recent use: *  (Max 500 characters)
Access and Parking
Are you proposing a new altered vehicle access to or from a public road? *  Yes  No
If Yes please describe and show on your drawings the position of any existing. Altered or new access points, highlighting the changes
you propose to make. You should also show existing footpaths and note if there will be any impact on these.
Are you proposing any change to public paths, public rights of way or affecting any public right of access? *  Yes  No
If Yes please show on your drawings the position of any affected areas highlighting the changes you propose to make, including
arrangements for continuing or alternative public access.
How many vehicle parking spaces (garaging and open parking) currently exist on the application
Site?
How many vehicle parking spaces (garaging and open parking) do you propose on the site (i.e. the
Total of existing and any new spaces or a reduced number of spaces)? *
Please show on your drawings the position of existing and proposed parking spaces and identify if these are for the use of particular
types of vehicles (e.g. parking for disabled people, coaches, HGV vehicles, cycles spaces).
Water Supply and Drainage Arrangements
Will your proposal require new or altered water supply or drainage arrangements? *  Yes  No
Do your proposals make provision for sustainable drainage of surface water?? *  Yes  No
(e.g. SUDS arrangements) *
Note:-
Please include details of SUDS arrangements on your plans
Selecting ‘No’ to the above question means that you could be in breach of Environmental legislation.
Are you proposing to connect to the public water supply network? *
 Yes
 No, using a private water supply
 No connection required
If No, using a private water supply, please show on plans the supply and all works needed to provide it (on or off site).
4381.00
House plot with previous approval
0
4
Page 24

Page 25

Page 5 of 8
Assessment of Flood Risk
Is the site within an area of known risk of flooding? *  Yes  No  Don’t Know
If the site is within an area of known risk of flooding you may need to submit a Flood Risk Assessment before your application can be
determined. You may wish to contact your Planning Authority or SEPA for advice on what information may be required.
Do you think your proposal may increase the flood risk elsewhere? *  Yes  No  Don’t Know
Trees
Are there any trees on or adjacent to the application site? *  Yes  No
If Yes, please mark on your drawings any trees, known protected trees and their canopy spread close to the proposal site and indicate if
any are to be cut back or felled.
Waste Storage and Collection
Do the plans incorporate areas to store and aid the collection of waste (including recycling)? *  Yes  No
If Yes or No, please provide further details: * (Max 500 characters)
Residential Units Including Conversion
Does your proposal include new or additional houses and/or flats? *  Yes  No
How many units do you propose in total? *
Please provide full details of the number and types of units on the plans. Additional information may be provided in a supporting
statement.
All Types of Non Housing Development – Proposed New Floorspace
Does your proposal alter or create non-residential floorspace? *  Yes  No
Schedule 3 Development
Does the proposal involve a form of development listed in Schedule 3 of the Town and Country  Yes  No  Don’t Know
Planning (Development Management Procedure (Scotland) Regulations 2013 *
If yes, your proposal will additionally have to be advertised in a newspaper circulating in the area of the development. Your planning
authority will do this on your behalf but will charge you a fee. Please check the planning authority’s website for advice on the additional
fee and add this to your planning fee.
If you are unsure whether your proposal involves a form of development listed in Schedule 3, please check the Help Text and Guidance
notes before contacting your planning authority.
Planning Service Employee/Elected Member Interest
Is the applicant, or the applicant’s spouse/partner, either a member of staff within the planning service or an  Yes  No
elected member of the planning authority? *
area to store bins. collection from the existing turning area at the end of the Minduff road.
1
Page 25

Page 26

Page 6 of 8
Certificates and Notices
CERTIFICATE AND NOTICE UNDER REGULATION 15 – TOWN AND COUNTRY PLANNING (DEVELOPMENT MANAGEMENT
PROCEDURE) (SCOTLAND) REGULATION 2013
One Certificate must be completed and submitted along with the application form. This is most usually Certificate A, Form 1,
Certificate B, Certificate C or Certificate E.
Are you/the applicant the sole owner of ALL the land? *  Yes  No
Is any of the land part of an agricultural holding? *  Yes  No
Certificate Required
The following Land Ownership Certificate is required to complete this section of the proposal:
Certificate A
Land Ownership Certificate
Certificate and Notice under Regulation 15 of the Town and Country Planning (Development Management Procedure) (Scotland)
Regulations 2013
Certificate A
I hereby certify that –
(1) - No person other than myself/the applicant was an owner (Any person who, in respect of any part of the land, is the owner or is the
lessee under a lease thereof of which not less than 7 years remain unexpired.) of any part of the land to which the application relates at
the beginning of the period of 21 days ending with the date of the accompanying application.
(2) - None of the land to which the application relates constitutes or forms part of an agricultural holding
Signed: Christopher Bremner
On behalf of: Mr Timothy Wright
Date: 01/09/2022
 Please tick here to certify this Certificate. *
Checklist – Application for Planning Permission
Town and Country Planning (Scotland) Act 1997
The Town and Country Planning (Development Management Procedure) (Scotland) Regulations 2013
Please take a few moments to complete the following checklist in order to ensure that you have provided all the necessary information
in support of your application. Failure to submit sufficient information with your application may result in your application being deemed
invalid. The planning authority will not start processing your application until it is valid.
a) If this is a further application where there is a variation of conditions attached to a previous consent, have you provided a statement to
that effect? *
 Yes  No  Not applicable to this application
b) If this is an application for planning permission or planning permission in principal where there is a crown interest in the land, have
you provided a statement to that effect? *
 Yes  No  Not applicable to this application
c) If this is an application for planning permission, planning permission in principle or a further application and the application is for
development belonging to the categories of national or major development (other than one under Section 42 of the planning Act), have
you provided a Pre-Application Consultation Report? *
 Yes  No  Not applicable to this application
Page 26

Page 27

Page 7 of 8
Town and Country Planning (Scotland) Act 1997
The Town and Country Planning (Development Management Procedure) (Scotland) Regulations 2013
d) If this is an application for planning permission and the application relates to development belonging to the categories of national or
major developments and you do not benefit from exemption under Regulation 13 of The Town and Country Planning (Development
Management Procedure) (Scotland) Regulations 2013, have you provided a Design and Access Statement? *
 Yes  No  Not applicable to this application
e) If this is an application for planning permission and relates to development belonging to the category of local developments (subject
to regulation 13. (2) and (3) of the Development Management Procedure (Scotland) Regulations 2013) have you provided a Design
Statement? *
 Yes  No  Not applicable to this application
f) If your application relates to installation of an antenna to be employed in an electronic communication network, have you provided an
ICNIRP Declaration? *
 Yes  No  Not applicable to this application
g) If this is an application for planning permission, planning permission in principle, an application for approval of matters specified in
conditions or an application for mineral development, have you provided any other plans or drawings as necessary:
 Site Layout Plan or Block plan.
 Elevations.
 Floor plans.
 Cross sections.
 Roof plan.
 Master Plan/Framework Plan.
 Landscape plan.
 Photographs and/or photomontages.
 Other.
If Other, please specify: *  (Max 500 characters)
Provide copies of the following documents if applicable:
A copy of an Environmental Statement. *  Yes  N/A
A Design Statement or Design and Access Statement. *  Yes  N/A
A Flood Risk Assessment. *  Yes  N/A
A Drainage Impact Assessment (including proposals for Sustainable Drainage Systems). *  Yes  N/A
Drainage/SUDS layout. *  Yes  N/A
A Transport Assessment or Travel Plan  Yes  N/A
Contaminated Land Assessment. *  Yes  N/A
Habitat Survey. *  Yes  N/A
A Processing Agreement. *  Yes  N/A
Other Statements (please specify). (Max 500 characters)
Page 27

Page 28

Page 8 of 8
Declare – For Application to Planning Authority
I, the applicant/agent certify that this is an application to the planning authority as described in this form. The accompanying
Plans/drawings and additional information are provided as a part of this application.
Declaration Name: Mr Christopher Bremner
Declaration Date: 01/09/2022
Page 28

Page 29

6750
1315
Plot 2
Plot 3
FFL = 172.460
FFL +173.550m
Original approved
house outline
(09/01922/APP)
MUTUAL TURNING AREA
A-A
1694
MUTUAL TURNING AREA
B-B
IN ROOF SOLAR PV SYSTEM
Plot 3
FFL = 172.460
CHRISTOPHER BREMNER
PLANS
07876758717
christopher.bremner@hotmail.com
Planning and Building Warrant applications...
New House - Conversion -
Garage - Extension...
Site Sections
18-08-22  1:150@A3
Drawing No. 20-121-PL02
Mr & Mrs Wright
Plot 3 Minduff,
Drybridge, Buckie
Page 29

Page 30

Page 30

Page 31

8400
9300
3000
OPEN FIELD
Plot 1
Plot 2
Plot 3
Passing Place
PADDOCK FOR PLOT 1 / SPACE
FOR SOAKAWAY ETC.
*ALL FENCES TO BE 900mm
HIGH TIMBER POST & WIRE. MUTUAL TURNING AREA
PADDOCK FOR PLOT 3
PADDOCK FOR PLOT 1 / SPACE
FOR SOAKAWAY ETC.
DRIVEWAY SURFACE
FORMED WITH
POROUS PAVIORS.
FFL = 172.460
ROAD TO BE  SUFFICIENT TO
SUPPORT A VEHICLE AXLE LOAD
OF 14 TONNES.
PADDOCK FOR PLOT 3
Plot 4 & 5 DrivewayPassing Place
Plot 1,2,3 Driveway
FFL +173.100m
FFL +173.550m
150mm pvc
EXISTING SURFACE WATER DITCH
Family Room
Lounge
Dining Room
Kitchen
Vest.Hall
Garage
St.
St.
Pantry
Bathroom Bedroom 6
Mud Room
Gravel drive way
Previously approved
house outline
(12/02050/APP)
Treatment plant
Surface water
Attenuation trench
Original approved
house outline
(09/01922/APP)
Foul Soakaway
AIR SOURCE
OUTSIDE UNIT
WATER BOREHOLE
57.629897, -2.949992
NEW TREE PLANTING.
R
B
B
B NEW TREE PLANTING.
B
B
A
A
S
S
N
Temporary static
caravan during
house build
All planting, seeding or turfing as may be
compromised in the approved details shall be
carried out in the first planting and seeding
seasons following the commencement of the
development.
Any trees, plants or hedging, which within a
period of five years from the completion of
the development die, for whatever reason are
removed or damaged shall be replaced in the
next planning season with others of the same
size and species
Notes
A range of 'Selected Standard'
LANSCAPE LEGEND
S - Silver Birch (Betula Pendula) Whip/Feather
O - Oak(Quercus Petraea) Whip/Feather
B - Beech (Fagus sylvatica) Whip/Feather
R - Rowan (Sorbus Aucuparia)  Whip/Feather Spacing - 2m x 2m
CHRISTOPHER BREMNER
PLANS
07876758717
christopher.bremner@hotmail.com
Planning and Building Warrant applications...
New House - Conversion -
Garage - Extension...
Site Plan
29-09-21  1:500@A3
Drawing No. 20-121-PL03
Mr & Mrs Wright
Plot 3 Minduff,
Drybridge, Buckie
Page 31

Page 32

Page 32

Page 33

Plot 1
Plot 2
Plot 3
FFL +173.100m
FFL +172.460m
FFL +173.550m
Plot 5
FFL +176.450m
2395sqm o.t.b.
3594sqm o.t.b.
3
2
0
0
2400
1
8
0
0
3
9
5
0
6
6
0
0
1
0
9
0
1
0
9
0
3
7
5
0
3
0
0
0
1
1
6
5
4000
3600
6
0
0
0
6
0
0
0
1
2
0
0
6
0
0
0
3
6
0
0
3300
Family Room
Utility
Lounge
Dining Room
Kitchen
Vest.Hall
Garage
St.
St.
Pantry
Bathroom
Bedroom
Play room
2
7
2
5
1
2
0
0
2
7
8
5
3
0
0
0
3
5
2
5
1
8
0
0
2
9
6
0
1
2
3
4
5
F
a
m
i
l
y
R
o
o
m
L
o
u
n
g
e
D
i
n
i
n
g
R
o
o
m
K
i
t
c
h
e
n
V
e
s
t
.
H
a
l
l
G
a
r
a
g
e
S
t
.
S
t
.
P
a
n
t
r
y
B
a
t
h
r
o
o
m
B
e
d
r
o
o
m
6
M
u
d
R
o
o
m
N
CHRISTOPHER BREMNER
PLANS
07876758717
christopher.bremner@hotmail.com
Planning and Building Warrant applications...
New House - Conversion -
Garage - Extension...
Location
29-09-21  1:1250@A3
Drawing No. 21-126-PL04
Mr & Mrs Wright
Plot 3 Minduff,
Drybridge, Buckie
Page 33

Page 34

Page 34

Page 35

North Elevation
35°
East Elevation
6750
6750
3750
2400
4950
10901090
6160
6000
1200
3000
5765
1050
3000
1090
2785
4000
2960
6000
3300
1800
1800
3600
3600
1800
Family Room
Lounge
Dining Room
Kitchen
Vest.
Hall
Garage
St. St.
Pantry
Bathroom
Bedroom 6
Ground Floor Plan
144m2
Mud Room
3615
760
4500
South Elevation
IN ROOF SOLAR PV SYSTEM
6750
West Elevation
AIRSOURCE UNIT
6750
1925
7675
2800
4000
3125
4200
3400
3500 4800
2625
11001100
3600
3600
2625
2625
2625
1200
1200
4100
1800
First Floor Plan
132m2
Bedroom 2
Bedroom 3
Bedroom 5
Bedroom 4
St.
cyl
Dressing
W
W
W
W
Ensuite Ensuite
Ensuite
St.
Master Bedroom
Study area
CHRISTOPHER BREMNER
PLANS
christopher.bremner@hotmail.com
Planning and Building Warrant applications...
New House - Conversion -
Garage - Extension...
Proposed Plan
07-11-22  1:50/100@A1
Drawing No. 20-121-PL01
Mr & Mrs Wright
Plot 3 Minduff,
Drybridge, Buckie
EXTERNAL FINISHES:-
1. Slate effect tiles
2. Tuscany beige Roughcast.
3. Natural stone feature gable.
4. White UPVC Windows & Doors.
5. White UPVC Soffit and Fascia.
Page 35

Page 36

Page 36

Page 37

gmcsurveys
Surveys, Setting-Out Civil Engineering Design 
Site Investigation & Drainage
Assessment
PLOT 3 MINDUFF
Gary Mackintosh Bsc
gmcsurveys@gmail.com
Gary Mackintosh
Email: gmcsurveys@gmail.com
Tel: 07557431702
Page 37

Page 38

gmcsurveys             Site Investigation & Drainage Assessment Minduff
PAGE 1
Contents
Client: ............................................................................................................................................................ 2
Site Address: ................................................................................................................................................. 2
Planning Reference: ................................................................................................................................... 2
Date: ............................................................................................................................................................... 2
Job Number: .................................................................................................................................................. 2
Company Information: .............................................................................................................................. 2
Assessment completed by:........................................................................................................................ 2
Introduction: ................................................................................................................................................ 3
Soil Conditions: ........................................................................................................................................... 3
Percolation/Soakaway Testing: .............................................................................................................. 4
Conclusion and Recommendations: ...................................................................................................... 4
Foul Water Discharge via Soakaway: ..................................................................................................... 5
Surface Water Dispersal via Soakaway: ................................................................................................ 5 
Page 38

Page 39

gmcsurveys             Site Investigation & Drainage Assessment Minduff
PAGE 2
Client: 
Mr and Mrs Wright
Site Address:
Proposed Dwelling
Minduff
Buckie
Planning Reference:
TBC
Date:
12th January 2022
Job Number:
GMC22-009
Company Information:
Assessment completed by: 
Gary Mackintosh Bsc
GMCSurveys
34 Castle Street
Forres
Moray
IV36 1PW
Email: gmcsurveys@gmail.com
Telephone: 07557431702
Page 39

Page 40

gmcsurveys             Site Investigation & Drainage Assessment Minduff
PAGE 3
Introduction:
The proposals are to erect a new private dwelling within Plot 3 of the previously
approved development located at Minduff, By Buckie together with all associated
infrastructure. 
The SEPA Flood maps have been consulted which confirm the property is not at risk
of fluvial or pluvial flooding during a 1:200year event. 
GMC Surveys have been asked to carry out a site investigation in order to provide a
drainage solution for the proposed development.
Soil Conditions:
Excavations were carried out by mechanical excavator on 26th November 2021 to
assess the existing ground conditions and carry out infiltration and percolation
testing for the management of foul and surface waters via soakaways.
The trial pits were excavated to depths of 1.8m and no groundwater was
encountered.
The excavations consisted of 0 – 300mm Topsoil, 300 – 1200mm brown/red, firm to
stiff, gravelly Clays overlying mixed gravels and rock easily broken with the teeth
of the excavator proved to the depth of the excavations.
There was no evidence of fill material or contamination within the trial pits and no
ground water was encountered. The natural soils have a minimum bearing
capacity of 75kn/m2. 
Page 40

Page 41

gmcsurveys             Site Investigation & Drainage Assessment Minduff
PAGE 4
Percolation/Soakaway Testing:
Percolation testing was carried out in full accordance with BS6297: 2007 + A1: 2008
and as described in Section 3.9 of the Scottish Building Standards Technical
Handbook (Domestic). The results can be found in the table below.            
1st 2nd 3rd Mean
Date of Test 26/11/21 26/11/21 26/11/21   
TH01 1440s 2040s 2340s       1940s         
Average Soil
Vp       12.93s/mm
Infiltration testing:
Infiltration testing was carried out in full accordance with BRE digest 365. The
results can be found in the table below. 
Infiltration
Test Pit Dimensions (w/l) Test Zone (mbgl)
Infiltration Rate
(m/s)
INF01 1.2m x 1.2m  1.0 - 1.8 2.43 x 10-5 
Conclusion and Recommendations:
Based on the onsite investigations it can be confirmed that the underlying soils are
suitable for the use of standard stonefilled soakaways as a drainage solution for
both foul and surface waters.
The Vp rate is below the maximum threshold of 15s/mm therefore a ‘Packaged
Sewage Treatment Plant’ would be required, the final details of which are to be
confirmed by the chosen supplier. 
Page 41

Page 42

gmcsurveys             Site Investigation & Drainage Assessment Minduff
PAGE 5
Foul Water Discharge via Soakaway:
As the Vp rate is below 15s/mm, in addition to the package sewage treatment plant,
SEPA require that 3.6m2 per person or 25m2 minimum be allowed for the foul water
soakaway, whichever is greater. 
3.6 x 8 (6 Bedroom) = 28.80m2 
It is therefore proposed to install a soakaway with a minimum base area of 25m2.
This area can be provided with soakaway plan dimensions 7.20m x 4.00m at a depth
of 0.45m below invert level. Alternative dimensions may be adopted to better suit
the site layout ensuring that the minimum base area of 28.80m2 is maintained.
Surface Water Dispersal via Soakaway:
Please see attached surface water calculations detailing the requirement and
suitability for soakaway dimensions of 8.0m x 3.5m at a depth of 1.50m below the
invert level based on the proposed contributing area of 315m2 (proposed roof area)
up to and including a 1:30year event with 35% allowance for climate change.
Soakaway Details can be found in Appendix A.
SEPA and Building Regulations require that infiltration systems (soakaways) are
located at least:
– 50m from any spring, well or borehole used as drinking water supply
– 10m horizontally from any water course and any inland and coastal waters,
permeable drain (including culvert), road or railway
– 5m from a building or boundary 
Page 42

Page 43

         
	




Page 44






                          
 
      ! "
 #
 $    % & $ '  (  )  *  + & $    , '

$
-  .
   % / 0 1 1 0   " 0 / 2
3 4 5 6 4 7
8 9 : : ; < 4 7
= > ; :
? @ 4 A : B ;
C D ; E :
F G H 9 : B I : J K L L @ 4 M : J
N O P Q R S T U V W X X Y Z W [ \ T ]
^
W _ X ` [ ] a ` Q ] _
^
P ` \ ` b ` c
d
S e f f g h h i
j f k h j k f f
j
d
S   
Rectangular pit design data:-
Pit length         =  8 m Pit width        =  3.5 m
Depth below invert =  1.5 m Percentage voids  = 30.0%
Imperm. area       =  315 m² Infilt. factor    = 0.000024 m/s
Return period      =  100 yrs Climate change    = 30%
Calculations :-
Surface area of soakaway to 50% storage depth (not inc. base):-
a
l m n
= 2 x (length + width) x depth/2 = 17.2 m²
Outflow factor : O = a
l m n
x Infiltration rate = 0.000414 m/s
Soakaway storage volume : S
> B ; o > E
= length x width x depth x %voids/100 = 12.6 m³
Duration Rainfall Inflow Depth Outflow Storage
mm/hr m³ (hmax) m m³ m³
5 mins 111.6 2.9 0.12 2.790.33
10 mins 87.1 4.6 0.25 4.310.51
15 mins 72.9 5.7 0.37 5.370.64
30 mins 51.7 8.1 0.75 7.390.88
1 hrs 34.9 11.0 1.49 9.501.13
2 hrs 22.5 14.2 2.98 11.201.33
4 hrs 14.3 18.0 5.96 12.021.43
6 hrs 10.9 20.5 8.94 11.601.38
10 hrs 7.7 24.2 14.90 9.311.11
24 hrs 4.2 31.9 35.77 0.000.00
Actual volume : S
> B ; o > E 
= 12.600 m³
Required volume : S
@ : p J 7 
= 12.020 m³
Soakaway volume storage OK.
Minimum required a
l m n  
: 16.46 m²
Actual a
l m n
: 17.25 m²
Minimum depth required: 1.43 m
Time to maximum 4 hrs
Emptying time to 50% volume = t
l m n
= S
@ : p J
x 0.5 / (a
l m n
x Infiltration rate) = 04:01 (hr:min))
Soakaway emptying time is OK.
Page 43

Page 45

         
	




Page 46






                          
 
      ! "
 #
 $    % & $ '  (  )  *  + & $    , '

$
-  .
   % / 0 1 1 0   " 0 / 2
3 4 5 6 4 7
8 9 : : ; < 4 7
= > ; :
? @ 4 A : B ;
C D ; E :
F G H 9 : B I : J K L L @ 4 M : J
N O P Q R S T U V W X X Y Z W [ \ T ]
^
W _ X ` [ ] a ` Q ] _
^
P ` \ ` b ` c
d
S e f f g h h i
j f k h j k f f
f
d
S   
Location hydrological data (FSR):-
Location      = BUCKIE (GRAMP) Grid reference   = NJ4265
M5-60 (mm)    =  13.5 r                = 0.25
Soil index    = 0.15 SAAR (mm/yr)     =  750
WRAP          = 1 Area = Scotland and N. Ireland
Soil classification for WRAP type  1
i)   Well drained permeable sandy or loam soils and shallower analogues over highly permeable
limestone, chalk, sandstone or related drifts;
ii)  Earthy peat soils drained by dykes and pumps;
iii) Less permeable loamy over clayey soils on plateaux adjacent to very permeable soils in
valleys.
N.B. The rainfall rates are calculated using the location specific
values above in accordance with the Wallingford procedure.
Page 44

Page 47

gmcsurveys             Site Investigation & Drainage Assessment Minduff
PAGE 6 
Appendix A
Test Hole Locations 
Page 45

Page 48

Plot 3
Plot 2
R
B
Plot 1
DATE:DESCRIPTION:REV: BY:
REVISION:PROJECT NO: DRAWING NO:
DRAWN:DATE: CHECKED:
TITLE:
SCALE AT A4:
CLIENT:
SITE:
STATUS:
gmcsurveys
Surveys, Setting Out, Civil Engineering Design
T: 07557 431 702
E: gmcsurveys@gmail.com
ISSUE
NTS JAN22 GM
Test Hole Location
Appendix A -GMC22-009
Mr and Mrs Wright
Plot 3 MinduffBy Buckie
INF01
BC01
TH01
Page 46

Page 49

gmcsurveys             Site Investigation & Drainage Assessment Minduff
PAGE 7 
Appendix B
Soakaway Details/Certificates 
Page 47

Page 50

100mm BED TO BE PIPE
BEDDING MATERIAL
150mm BED
TO BE PIPE
BEDDING
MATERIAL
450mm DIA INSPECTION
CHAMBER AND COVER
100mm BED TO
BE PIPE BEDDING
MATERIAL
100mm DIA SOLID PIPE 100mm DIA SOLID PIPE
100mm DIA SOLID PIPE
PIT FILLED WITH CLEAN
CRUSHED ROCK,
SURROUNDED WITH
TERRAM 1000 OR
EQUAL. BASE OF PIT
OPEN - NO TERRAM
150mm DIA UPVC INSPECTION
1500mm
800mm
MIN COVER
MD COVER AND FRAME RODDING EYE COVER
LONGITUDINAL SECTION THROUGH
RAINWATER SOAKAWAY (NTS)
300mm FROM EDGE OF SOAKAWAY TO PIPE
AROUND PERIMETER
RODDING EYE COVER
200mm Inspection Pipe and Cover
100mm DIA DISTRIBUTION HALF
PERFORATED PIPE
100mm DIA DISTRIBUTION HALF
PERFORATED PIPE
100mm DIA DISTRIBUTION HALF
PERFORATED PIPE
PLAN VIEW
SOAKAWAY ARRANGEMENTS (NTS)
1.55m
1.55m
7.20m
4.0m
DISTRIBUTION BOX
INSPECTION / SAMPLING
CHAMBER AND COVER
SECTION A - A THROUGH
FOUL WATER SOAKAWAY (NTS)
RODDING EYE COVERREPLACE SOIL
ANTI VERMIN MESH
TERRAM 1000 GEOTEXTILE SIDES AND
TOP ONLY WITH 1000mm LAPS
100mm DIA DISTRIBUTION HALF
PERFORATED PIPE
100mm DIA UPVC SOLID PIPE
150mm THICK 10mm CHIPS
CLEAN CRUSHED ROCK
100-50 GRADING
7.20m LONG X 4.0m WIDE X 0.45m DEEP SOAKAWAY
100mm DIA UPVC SOLID PIPE
100mm DIA UPVC SOLID PIPE
600
450mm
200mm DIA UPVC INSPECTION
PIPES PERFOTATED WITH COVERSMD COVER AND FRAME
500mm DISTRIBUTION CHAMBER
WITH PVC RISER TO GROUND
LEVEL
AA
Dimensions as per Report
FULLY PERFORATED 150mm pvc PIPE
DATE:DESCRIPTION:REV: BY:
REVISION:PROJECT NO: DRAWING NO:
DRAWN:DATE: CHECKED:
TITLE:
SCALE AT A4:
CLIENT:
SITE:
STATUS:
gmcsurveys
Surveys, Setting Out, Civil Engineering Design
T: 07557 431 702
E: gmcsurveys@gmail.com
ISSUE
NTS GM
Appendix B -
Soakaway Details
JAN22
GMC22-009
Mr and Mrs Wright
Plot 3 MinduffBy Buckie
Page 48

Page 51

gmcsurveys
Surveys,Setting Out Civil Engineering Design 
Certificate For Proposed Sub – Surface Soakaways
Foul Water 
Applicants Name: Mr and Mrs Wright
Address:                Plot 3, Minduff, By Buckie
Site Address:         Proposed New Dwelling at Above Address
Date of Tests:        26th November 2021
Weather Conditions: Dry/Overcast 
Percolation Test/Soakaway Sizing:            
1st 2nd 3rd Mean
Date of Test 26/11/21 26/11/21 26/11/21   
TH01 1440s 2040s 2340s       1940s         
Average Soil
Vp       12.93s/mm 
Location: TP1 
Average Soil Vp: 12.93s/mm 
PE: 8 
Base Area (min): 28.80m2 (as per SEPA requirements) 
I hereby certify that I have carried out the above tests in full accordance with
BS6297: 2007 + A1: 2008 and as described in Section 3.9 of the Scottish Building
Standards Technical Handbook (Domestic). 
Signed: G Mackintosh         Gary Mackintosh BSc.             Date: 12th January 2022 
Company: GMC Surveys, 34 Castle Street, Forres, Morayshire. IV36 1PW 
gmcsurveys
34 castle Street
Forres
Moray
IV36 1PW
T: 07557 431 702
E:gmcsurveys@gmail.com
Page 49

Page 52

gmcsurveys
Surveys,Setting Out Civil Engineering Design 
Certificate For Proposed Sub – Surface Soakaways
Surface Water 
Applicants Name: Mr and Mrs Wright
Address:                Plot 3, Minduff, By Buckie
Site Address:         Proposed New Dwelling at Above Address
Date of Tests:        26th November 2021
Weather Conditions: Dry/Overcast 
Trial Pit Test – Surface Water: 
Depth of Excavation: 1.8 
Water Table Present:  No 
Infiltration Test: 
Location: INF01 
Infiltration Test Zone: 1.0 – 1.8mbgl 
Infiltration Rate (m/s): 2.43 x 10-5 
Contributing Area: 315m2 
Soakaway Size: 8.0m x 3.5m x 1.5 below the invert of the pipe (30year)           
I hereby certify that I have carried out the above tests in accordance with the
procedures specified in BRE Digest 365:1991. 
Signed: G Mackintosh         Gary Mackintosh BSc.             Date: 12th January 2021 
Company: GMC Surveys, 34 Castle Street, Forres, Morayshire. IV36 1PW 
gmcsurveys
34 castle Street
Forres
Moray
IV36 1PW
T: 07557 431 702
E:gmcsurveys@gmail.com
Page 50

Page 53

Page 51

Page 54

Page 52

Page 55

Page 53

Page 56

Page 54

Page 57

MORAY COUNCIL
PLANNING CONSULTATION RESPONSE
From:   The Moray Council, Flood Risk Management
Planning Application Ref. No: 21/01560/APP 
I have the following comments to make on the application:-  
Please
x
(a) I OBJECT to the application for the reason(s) as stated below  
(b) I have NO OBJECTIONS to the application and have no condition(s) and/or
comment(s) to make on the proposal  
(c) I have NO OBJECTIONS to the application subject to condition(s) and/or
comment(s) about the proposal as set out below   
(d) Further information is required in order to consider the application as set out below   
Contact: Leigh Moreton Date  23/11/22
email address: leigh.moreton@moray.gov.uk Phone No 
Consultee: The Moray Council, Flood Risk Management 
Page 55

Page 58

Page 56

Page 59

From: Teresa Ruggeri <Teresa.Ruggeri@moray.gov.uk>
Sent: 13 Sep 2022 10:31:31
To: DMSMyEmail@moray.gov.uk
Cc:
Subject: FW: 22/01292/APP Erect dwellinghouse on Plot 3 Minduff, Drybridge, Buckie
Attachments:    
Hi,  
No developer obligations will be sought for this application as it relates to an extant consent, 09/01922/APP.  
Thanks
Rebecca  
Rebecca Morrison| Infrastructure Growth/Obligations Officer (Strategic Planning and
Development) | Economic Growth and Development
rebecca.morrison@moray.gov.uk | website | facebook | twitter | instagram | news
Page 57

Page 60

Page 58

Page 61

Consultee Comments for Planning Application 22/01292/APP
Application Summary
Application Number: 22/01292/APP
Address: Plot 3 Minduff Drybridge Buckie Moray
Proposal: Erect dwellinghouse on
Case Officer: Iain T Drummond
Consultee Details
Name: Mr CL Consultations
Address: Environmental Health, Council Offices, High Street Elgin, Moray IV30 1BX
Email: Not Available
On Behalf Of: Contaminated Land
Comments
Approved unconditionally
Page 59

Page 62

Page 60

Page 63

MORAY COUNCIL 
PLANNING CONSULTATION RESPONSE 
From:   Transportation Manager 
Planning Application Ref. No: 22/01292/APP
Erect dwellinghouse  on Plot 3 Minduff Drybridge Buckie Moray for Mr Timothy Wright 
I have the following comments to make on the application:-  
Please 
(a) I OBJECT to the application for the reason(s) as stated below  
(b) I have NO OBJECTIONS to the application and have no condition(s) and/or
comment(s) to make on the proposal 

(c) I have NO OBJECTIONS to the application subject to condition(s) and/or
comment(s) about the proposal as set out below   
x
(d) Further information is required in order to consider the application as set out
below 

This proposal is for the erection of a new dwelling which is to be served via an existing
access which is to be shared by two other new properties. The overall development
requires the provision of a turning area for refuse vehicles at the end of the public road.
The turning area has now been constructed (and is presently within the 1 year
maintenance period prior to formally being adopted as part of the public road network
(Roads Construction Consent (RCC 595) relates). The access to the site has also been
surfaced. The following conditions would therefore apply:
Conditions
1. No development works shall commence on the dwelling house until a detailed drawing
(scale 1:200) has been submitted to and approved in writing by the Council, as
Planning Authority in consultation with the Roads Authority confirming the provision of,
or location where a future Electric Vehicle (EV) charging unit is to be connected to an
appropriate electricity supply, including details (written proposals and plans) to confirm
the provision of the necessary cabling, ducting, and consumer units capable of
supporting the future charging unit; and thereafter the EV charging infrastructure shall
be provided in accordance with the approved drawing and details prior to the first
occupation of the dwelling house. 
Reason: In the interests of an acceptable form of development and the provision of
infrastructure to support the use of low carbon transport, through the provision of details
currently lacking. 
2. No water shall be permitted to drain or loose material be carried onto the public
carriageway. 
Reason: To ensure the safety and free flow of traffic on the public road and access to the
site by minimising the road safety impact from extraneous material and surface water in
the vicinity of the new access.
Page 61

Page 64

3. A visibility splay 2.4 metres by 120 metres to the north-west shall be provided at the
access onto the public road, and maintained thereafter at all times free from any
obstruction greater than 0.6m in height measured from the level of the carriageway. 
Reason: To enable drivers of vehicles leaving the site to have a clear view over a length of
road sufficient to allow safe exit, in the interests of road safety for the proposed
development and other road users. 
4. Three car parking spaces shall be provided within the site prior to the occupation or
completion of the dwelling house, whichever is the sooner.  The parking spaces shall
thereafter be retained throughout the lifetime of the development, unless otherwise
agreed in writing with the Council as Planning Authority.   
Reason: To ensure the permanent availability of the level of parking necessary for
residents/visitors/others in the interests of an acceptable development and road safety.
Further comment(s) to be passed to applicant
Planning consent does not carry with it the right to carry out works within the public road
boundary. 
The provision of Electric Vehicle (EV) chargers and/or associated infrastructure shall be
provided in accordance with Moray Council guidelines. Cabling between charging units
and parking spaces must not cross or obstruct the public road including footways.
Infrastructure provided to enable EV charging must be retained for this purpose for the
lifetime of the development unless otherwise agreed in writing by the Planning Authority.  
Guidance on Electric Vehicle (EV) Charging requirements can be found at:
http://www.moray.gov.uk/downloads/file134860.pdf 
Public utility apparatus may be affected by this proposal.  Contact the appropriate utility
service in respect of any necessary utility service alterations which have to be carried out
at the expense of the developer. 
No building materials/scaffolding/builder’s skip shall obstruct the public road (including
footpaths) without permission from the Roads Authority. 
The applicant shall free and relieve the Roads Authority from any claims arising out of
their operations on the road or extension to the road. 
Contact: AG Date 13 September 2022
email address: Transport.develop@moray.gov.uk  
Consultee: TRANSPORTATION 
Return response to  consultation.planning@moray.gov.uk 
Please note that information about the application including consultation responses and representations (whether in support or objection) received on the proposal will be published on the Council’s website at http://public.moray.gov.uk/eplanning/  (You can also use this site to track progress of the application and view details of any consultation responses and
representations (whether in support or objection) received on the proposal).  In order to comply with the Data Protection Act, personal information including signatures, personal telephone and email details will be removed prior to publication using “redaction” software to avoid (or mask) the display of such information.  Where appropriate other “sensitive”
information within documents will also be removed prior to publication online. 
Page 62

Page 65

Consultation Request Notification - Private Water
Supplies
Planning Authority Name Moray Council
Response Date 20th September 2022
Planning Authority
Reference
22/01292/APP
Nature of Proposal
(Description)
Erect dwellinghouse  on
Site Plot 3 Minduff
Drybridge
Buckie
Moray
Site Postcode N/A
Site Gazetteer UPRN 000133059924
Proposal Location Easting 343431
Proposal Location Northing 860397
Area of application site (M2) 4381
Additional Comments
Development Hierarchy
Level
LOCAL
Supporting Documentation
URL
https://publicaccess.moray.gov.uk/eplanning/ce
ntralDistribution.do?caseType=Application&ke
yVal=RHKJDOBGI6F00
Previous Application 12/02050/APP
21/01560/APP
Date of Consultation 6th September 2022
Is this a re-consultation of
an existing application?
Yes
Applicant Name Mr Timothy Wright
Applicant Organisation
Name
Applicant Address 23 Cameron Crescent
Buckie
Moray
AB56 1AG
Agent Name Christopher Bremner
Agent Organisation Name
Agent Address
Minduff
Drybridge
Buckie
Moray
AB56 5LB
Agent Phone Number Telephone : 07876758717  
Agent Email Address N/A
Case Officer Iain T Drummond
Page 63

Page 66

Case Officer Phone number 01343 563607
Case Officer email address iain.drummond@moray.gov.uk
PA Response To consultation.planning@moray.gov.uk
NOTE:
If you do not respond by the response date, it will be assumed that you
have no comment to make.
The statutory period allowed for a consultation response is 14 days. 
Due to scheduling pressures if a definitive response is not received
within 21 days this may well cause the two month determination period
to be exceeded.
Data Protection - Moray Council is the data controller for this process.  Information collected about
you on this form will be used to process your Planning Application, and the Council has a duty to
process your information fairly.  Information we hold must be accurate, up to date, is kept only for
as long as is necessary and is otherwise shared only where we are legally obliged to do so.  You
have a legal right to obtain details of the information that we hold about you.
For full terms please visit  http://www.moray.gov.uk/moray_standard/page_121513.html
For full Data Protection policy, information and rights please see
http://www.moray.gov.uk/moray_standard/page_119859.html
You can contact our Data Protection Officer at info@moray.gov.uk or 01343 562633 for more
information.
Please respond using the attached form:-
Page 64

Page 67

MORAY COUNCIL
PLANNING CONSULTATION RESPONSE
From: Environmental Health – Private Water Supplies
Planning Application Ref. No: 22/01292/APP
Erect dwellinghouse  on Plot 3 Minduff Drybridge Buckie Moray for Mr Timothy
Wright
I have the following comments to make on the application:-
Please
x
(a) I OBJECT to the application for the reason(s) as stated below 
(b) I have NO OBJECTIONS to the application and have no condition(s)
and/or comment(s) to make on the proposal

(c) I have NO OBJECTIONS to the application subject to condition(s) and/or
comment(s) about the proposal as set out below 
x
HOLDING COMMENTS
(d ) Further information in relation to the proposed private water supply
has been requested from the applicant and the application should
not be approved nor submitted to committee for determination until
the final consultation response clearing the supply has been
received from Environmental Health (Private Water Supplies)

Reason(s) for objection
To ensure that the development is served by an adequate and wholesome water supply.
Condition(s)
Prior to the occupation of the house hereby approved a scheme of effective treatment to
the private water supply shall be fully installed and properly maintained for the lifetime of
the development. The scheme must ensure that the water to the house would fully comply
with the regulatory limits stated in The Water Intended for Human Consumption (Private
Supplies) (Scotland) Regulations 2017 and should specifically include effective point of
entry ultraviolet treatment, prefiltration, pH correction measures and iron/manganese
treatment.
Further comment(s) to be passed to applicant
Contact: Adrian Muscutt Date…15/9/22………………………..
email address: Phone No  …………………………..
Consultee: Environmental Health – Private Water Supplies
Page 65

Page 68

Return response to consultation.planning@moray.gov.uk
Please note that information about the application including consultation responses and
representations (whether in support or objection) received on the proposal will be
published on the Council’s website at http://publicaccess.moray.gov.uk/eplanning/   (You
can also use this site to track progress of the application and view details of any
consultation responses and representations (whether in support or objection) received on
the proposal).  In order to comply with the Data Protection Act, personal information
including signatures, personal telephone and email details will be removed prior to
publication using “redaction” software to avoid (or mask) the display of such information. 
Where appropriate other “sensitive” information within documents will also be removed
prior to publication online.
Page 66

Page 69

Page 67

Page 70

Consultee Comments for Planning Application 22/01292/APP
Application Summary
Application Number: 22/01292/APP
Address: Plot 3 Minduff Drybridge Buckie Moray
Proposal: Erect dwellinghouse on
Case Officer: Iain T Drummond
Consultee Details
Name: Mr EH Consultations
Address: Environmental Health, Council Offices, High Street Elgin, Moray IV30 1BX
Email: Not Available
On Behalf Of: Environmental Health C12
Comments
Approved unconditionally
Page 68

Page 71

Page 69

Page 72

REPORT OF HANDLING 
Ref No: 22/01292/APP Officer: Iain T Drummond
Proposal
Description/
Address  
Erect dwellinghouse  on Plot 3 Minduff Drybridge Buckie Moray
Date: 09.01.2023 Typist Initials: SS 
RECOMMENDATION
Approve, without or with condition(s) listed below Y
Refuse, subject to reason(s) listed below N
Legal Agreement required e.g. S,75 N
Notification to Scottish Ministers/Historic Scotland N
Hearing requirements
Departure N
Pre-determination N 
CONSULTATIONS
Consultee Date
Returned Summary of Response 
Planning And Development Obligations 09/09/22 No contributions sought due to extant
consent on site.
Moray Flood Risk Management 12/09/22 No objections
Environmental Health Manager 12/09/22 No objections
Contaminated Land 14/09/22 No objections
Private Water Supplies 15/09/22 No objections subject to condition
Transportation Manager 13/09/22 No objections subject to conditions and
informatives. 
DEVELOPMENT PLAN POLICY
Policies Dep Any Comments 
(or refer to Observations below)
PP3 Infrastructure and Services N 
DP1 Development Principles N 
DP4 Rural Housing N 
EP2 Biodiversity N 
EP12 Management and Enhancement Water N 
EP13 Foul Drainage N 
EP14 Pollution Contamination Hazards N 
REPRESENTATIONS
Representations Received  NO
Total number of representations received
Page 70

Page 73

Page 2 of 4
Names/Addresses of parties submitting representations 
Summary and Assessment of main issues raised by representations
Issue:
Comments (PO): 
OBSERVATIONS – ASSESSMENT OF PROPOSAL 
Proposal & Site  
 This application seeks to amend the design of the houses approved on site via applications
09/01922/APP and 12/02050/APP, both of which have had a lawful start to the consents in the
form of the partial formation of access and therefore remain extant.   
 The proposed house consists of a one and a half storey, T-shaped house with integral double
garage.   
 The proposed amended house design overlaps and largely sits on the same footprint as the
previously consented houses on this site.   
 This application seeks detailed planning permission for the amendment of the design previously
approved on site from a larger one and a half storey house.   
 Use of a private water supply is proposed with foul drainage disposed of via a treatment plant
and soakaway and surface water disposed of via a separate soakaway.    
 The temporary siting of a static caravan is also proposed throughout the duration of the
construction of the dwellinghouse.   
Appraisal  
Section 25 of the 1997 Act as amended requires applications to be determined in accordance with
the development plan i.e. the adopted Moray Local Development Plan 2020 (MLDP) unless material
considerations indicate otherwise. The main planning issues are considered below: 
Principle of the development (PP1, DP1 and DP2)   
The principle of erecting a house on this site has already been established via the approval of
applications 09/01922/APP and 12/02050/APP and therefore what requires to be considered as part
of this application is the amendments to the design and siting of the house.   
Design and amenity (PP1, DP1, DP4 and EP2)  
In terms of the amended house design, with the exception of the roof finish, the proposal is compliant
with the design and material finish requirements of policy DP4.  Where the applicants have specified
the use of slate effect tiles, policy DP4 specifically stipulates the use of natural slate or corrugated
roofing on houses in the countryside and precludes the use of concrete tiles and as such a condition
has been attached to the consent to ensure the finish of the house is natural slate in line with policy
requirements.  Landscaping proposals are lacking from the scheme, however, a condition has been
attached to ensure tree planting covering 15% of the site as required by policy is achieved.     
No tree removal is proposed as part of this application and in terms of biodiversity, the provision of
planting across the site will ensure biodiversity levels within the plot are enhanced.   
The temporary siting of a static caravan throughout the duration of the construction of the house is
also considered to be acceptable, subject to the condition as applied that the caravan is removed
following the completion or occupation of the dwellinghouse.   
Overall the proposals are considered to be compliant with policies PP1, DP1, DP4 and EP2.   
Page 71

Page 74

Page 3 of 4
Drainage (EP12, EP13)  
Drainage information has been provided with the application and identifies the means of surface
water disposal from the site.  Moray Flood Risk Management have assessed this information and
have no objections to the approval of the application. Environmental Health have also confirmed that
the proposed private water supply is sufficient to serve the proposed house subject to condition as
recommended and as such the proposal is considered to comply with policy EP12 and EP13.    
Access (DP1)  
Transportation have no objection to the approval of the application subject to conditions as
recommended and as such the development complies with policy DP1 in this regard.    
Developer obligations and affordable housing (PP3 and DP2) 
Developer obligations have already been paid in relation to the extant consent on site and as such
the proposals are compliant with policies PP3 and DP2.   
Conclusion and Recommendation  
Based on all of the above, taking into account comments received from consultees, this application is
considered to comply with development plan policy and is therefore recommended for approval
subject to conditions.   
REASON(S) FOR DECISION 
The Council's reason(s) for making this decision are:- 
The proposal complies with the provisions of the Moray Local Development Plan 2020 and
there are no material considerations that indicate otherwise.   
OTHER MATERIAL CONSIDERATIONS TAKEN INTO ACCOUNT 
None. 
HISTORY
Reference No. Description 
Erect house at Plot 3 Minduff Drybridge Buckie Moray
12/02050/APP Decision Permitted Date Of Decision 24/05/13   
Erect dwellinghouse on Plot 3 Minduff Drybridge Buckie Moray 
21/01560/APP Decision Refuse Date Of Decision 02/02/22   
ADVERT
Advert Fee paid? Yes
Local Newspaper Reason for Advert Date of expiry 
Banffshire Advertiser and
Herald No Premises 03/10/22
PINS No Premises 03/10/22 
Page 72

Page 75

Page 4 of 4
DEVELOPER CONTRIBUTIONS (PGU)
Status NONE SOUGHT 
DOCUMENTS, ASSESSMENTS etc. *
* Includes Environmental Statement, Appropriate Assessment, Design Statement, Design and Access Statement, RIA,
TA, NIA, FRA etc
Supporting information submitted with application? YES 
Summary of main issues raised in each statement/assessment/report
Document Name:  Drainage assessment
Main Issues:  Outlines the drainage methodology for the site.  
.
S.75 AGREEMENT
Application subject to S.75 Agreement  NO
Summary of terms of agreement:   
Location where terms or summary of terms can be inspected:   
DIRECTION(S) MADE BY SCOTTISH MINISTERS (under DMR2008 Regs)
Section 30 Relating to EIA  NO
Section 31 Requiring planning authority to provide information
and restrict grant of planning permission  NO
Section 32 Requiring planning authority to consider the imposition
of planning conditions  NO
Summary of Direction(s)   
Page 73

Page 76

Page 74

Page 77

(Page 2 of 9) Template:PEAPPZ Ref: 22/01292/APP
IMPORTANT NOTE
YOU ARE OBLIGED TO COMPLY WITH THESE CONDITIONS AND NOTES
SCHEDULE OF CONDITIONS
By this Notice the Moray Council has GRANTED PLANNING PERMISSION for this
proposal subject to conditions as appropriate to ensure implementation of the
proposal under the Town & Country Planning (Scotland) Act 1997, as amended. It
is important that these conditions are adhered to and failure to comply may
result in enforcement action being taken.
CONDITION(S)
Permission is granted subject to the following conditions: -
1 The development to which this permission relates must be begun not later
than the expiration of 3 years beginning with the date on which the
permission is granted.
Reason: The time limit condition is imposed in order to comply with the
requirements of section 58 of the Town and Country Planning (Scotland) Act
1997 as amended.
2 No development works shall commence on the dwelling house until a
detailed drawing (scale 1:200) has been submitted to and approved in
writing by the Council, as Planning Authority in consultation with the Roads
Authority confirming the provision of, or location where a future Electric
Vehicle (EV) charging unit is to be connected to an appropriate electricity
supply, including details (written proposals and plans) to confirm the
provision of the necessary cabling, ducting, and consumer units capable of
supporting the future charging unit; and thereafter the EV charging
infrastructure shall be provided in accordance with the approved drawing
and details prior to the first occupation of the dwelling house.
Reason: In the interests of an acceptable form of development and the
provision of infrastructure to support the use of low carbon transport, through
the provision of details currently lacking.
3 No water shall be permitted to drain or loose material be carried onto the
public carriageway.
Reason: To ensure the safety and free flow of traffic on the public road and
access to the site by minimising the road safety impact from extraneous
material and surface water in the vicinity of the new access.
4 A visibility splay 2.4 metres by 120 metres to the north-west shall be
provided at the access onto the public road, and maintained thereafter at all
times free from any obstruction greater than 0.6m in height measured from
the level of the carriageway.
Page 75

Page 78

(Page 3 of 9) Template:PEAPPZ Ref: 22/01292/APP
Reason: To enable drivers of vehicles leaving the site to have a clear view
over a length of road sufficient to allow safe exit, in the interests of road
safety for the proposed development and other road users.
5 Three car parking spaces shall be provided within the site prior to the
occupation or completion of the dwelling house, whichever is the sooner.
The parking spaces shall thereafter be retained throughout the lifetime of the
development, unless otherwise agreed in writing with the Council as
Planning Authority.
Reason: To ensure the permanent availability of the level of parking
necessary for residents/visitors/others in the interests of an acceptable
development and road safety.
6 Prior to the occupation of the house hereby approved a scheme of effective
treatment to the private water supply shall be fully installed and properly
maintained for the lifetime of the development. The scheme must ensure that
the water to the house would fully comply with the regulatory limits stated in
The Water Intended for Human Consumption (Private Supplies) (Scotland)
Regulations 2017 and should specifically include effective point of entry
ultraviolet treatment, prefiltration, pH correction measures and
iron/manganese treatment.
Reason: To ensure that the development is served by an adequate and
wholesome water supply.
7 The paddock area associated with the plot as identified in the approved site
plan, shall be only used as paddock land, and not for domestic garden
purposes. Note. For the avoidance of doubt, the paddock does not have the
benefit of permitted development rights under Article 2(4), Schedule, Part 1
Classes 3B (Building, engineering, installation or other operation within the
curtilage of a dwellinghouse for any purpose incidental to the enjoyment of
the dwellinghouse) of the Town and Country Planning (General Permitted
Development) (Scotland) Order 1992, as amended by the Town & Country
Planning (General Permitted Development) (Scotland) Amendment Order
2011 (or any Order revoking and re-enacting that Order(s) with or without
modifications).
Reason: To safeguard the rural character of the site and its surroundings, by
mitigating against any domestic encroachment into adjoining farm/paddock
land.
8 Unless otherwise agreed in writing with the Planning Authority, boundary
enclosures surrounding the site hereby approved shall only comprise post
and wire fencing or hedging made up of native species (birch, gean,
hawthorn, scots pine, beech, oak, holly).  In addition 15% of the plot must be
landscaped with native tree species (whips and feathered trees at least 1.5
metres in height, planted at a density of 1 per 4 sqm).
All planting, seeding or turfing shall be carried out in the first planting and
seeding seasons following the commencement of development.  Any trees
or plants which within a period of five years from the completion of the
Page 76

Page 79

(Page 4 of 9) Template:PEAPPZ Ref: 22/01292/APP
development die, for whatever reason are removed or damaged shall be
replaced in the next planting season with others of the same size and
species.
Reason: To ensure an acceptable scheme of landscaping to aid the
integration of the house into the surrounding landscape and ensure the
planting is timeously provided.
9 Notwithstanding the details shown on the approved plans, the roof of the
dwellinghouse hereby approved shall be finished in natural slate.
Reason: To ensure the highest standards of material finish are achieved for
new housing in the countryside and that new housing is finished in a manner
which reflects the traditional material finishes of houses in Moray.
10. The residential caravan hereby permitted is solely for the use of the applicant
or developer for the duration of the construction works associated with the
development hereby approved. Within 3 years from the date of this decision
notice or within 2 months following the occupation or completion of the
dwellinghouse, whichever is the sooner, the caravan shall be removed
permanently from the site, along with all associated fixtures and fittings.
Reason: To ensure the removal of the residential caravan from the site
following the completion of the adjacent house, in the interests of minimising
and removing the visual impact of the caravan.
REASON(S) FOR DECISION
The Council’s reason(s) for making this decision are:-
The proposal complies with the provisions of the Moray Local Development Plan
2020 and there are no material considerations that indicate otherwise.
LIST OF PLANS AND DRAWINGS SHOWING THE DEVELOPMENT
The following plans and drawings form part of the decision:-
Reference Version Title
20-121-PL02 Site sections
20-121-PL03 Site plan
20-126-Pl04 Location plan
20-121-PL01 Elevations and floor plans
IMPORTANT NOTES ABOUT THIS DECISION
Page 77

Page 80

(Page 5 of 9) Template:PEAPPZ Ref: 22/01292/APP
COMMENCEMENT AND COMPLETION OF THE DEVELOPMENT
The following are statutory requirements of the Town & Country Planning (Scotland)
Act 1997, as amended.  Failure to meet their respective terms represents a breach
of planning control and may result in formal enforcement action.  Copies of the
notices referred to below are attached to this permission for your use.
NOTIFICATION OF INITIATION OF DEVELOPMENT
S.27A of the 1997 Act, as amended requires that any person who has been granted
planning permission (including planning permission in principle) and intends to start
development must, as soon as practicable after deciding the date they will start work
on the development, give notice to the planning authority of that date.  This ensures
that the planning authority is aware that the development is underway and can follow
up on any suspensive conditions attached to the permission. Therefore, prior to any
work commencing on site, the applicant/developer must complete and submit to the
Moray Council, as planning authority, the attached Notification of Initiation of
Development.
NOTIFICATION OF COMPLETION OF DEVELOPMENT
S.27B of the 1997 Act, as amended requires that any person who completes a
development for which planning permission (including planning permission in
principle) has been given must, as soon as practicable after doing so, give notice of
completion to the planning authority.  This will ensure that the planning authority is
aware that the development is complete and can follow up any planning conditions.
Therefore, on completion of the development or as soon as practicable after doing
so, the applicant/developer must complete and submit to the Moray Council, as
planning authority the attached Notification of Completion of Development.
NOTIFICATION OF COMPLETION OF PHASED DEVELOPMENT
Under S.27B(2) of the 1997 Act, as amended where permission is granted for
phased development, the permission is subject to a condition (see Schedule of
Conditions above) requiring the applicant/developer as soon as practicable after
each phase to give notice of that completion to the planning authority.  This will allow
the planning authority to be aware that particular phase(s) of the development is/are
complete.
When the last phase is completed the applicant/developer must also complete and
submit a Notification of Completion of Development.
ADDITIONAL NOTES FOR INFORMATION OF THE APPLICANT
The following notes are provided for your information including comments received
from consultees:-
THE TRANSPORTATION MANAGER, DIRECT SERVICES has commented that:-
Planning consent does not carry with it the right to carry out works within the
public road boundary.
The provision of Electric Vehicle (EV) chargers and/or associated infrastructure
Page 78

Page 81

(Page 6 of 9) Template:PEAPPZ Ref: 22/01292/APP
shall be provided in accordance with Moray Council guidelines. Cabling
between charging units and parking spaces must not cross or obstruct the
public road including footways. Infrastructure provided to enable EV charging
must be retained for this purpose for the lifetime of the development unless
otherwise agreed in writing by the Planning Authority. Guidance on Electric
Vehicle (EV) Charging requirements can be found at:
http://www.moray.gov.uk/downloads/file134860.pdf
Public utility apparatus may be affected by this proposal. Contact the
appropriate utility service in respect of any necessary utility service alterations
which have to be carried out at the expense of the developer.
No building materials/scaffolding/builder's skip shall obstruct the public road
(including footpaths) without permission from the Roads Authority.
The applicant shall free and relieve the Roads Authority from any claims arising
out of their operations on the road or extension to the road.
DETAILS OF ANY VARIATION MADE TO ORIGINAL PROPOSAL,
AS AGREED WITH APPLICANT (S.32A of 1997 ACT)
None
DETAILS WHERE DIFFERENT TIME-PERIOD(S) FOR DURATION OF PLANNING
PERMISSION IMPOSED (S.58/59 of 1997 ACT)
None
TERMS OF S.75 AGREEMENT RELATING TO THIS APPLICATION
The terms, or summary of terms of the Agreement can be inspected at:-
None
NOTICE OF APPEAL
TOWN AND COUNTRY PLANNING (SCOTLAND) ACT 1997
If the applicant is aggrieved by the decision to refuse permission for or approval
required by a condition in respect of the proposed development, or to grant
permission or approval subject to conditions, the applicant may require the planning
authority to review the case under section 43A of the Town and Country Planning
(Scotland) Act 1997 within three months from the date of this notice.  The notice of
review should be addressed to The Clerk, The Moray Council Local Review Body,
Legal and Committee Services, Council Offices, High Street, Elgin IV30 1BX.  This
form is also available and can be submitted online or downloaded from
www.eplanning.scotland.gov.uk
If permission to develop land is refused or granted subject to conditions and the
owner of the land claims that the land has become incapable of reasonably
beneficial use in its existing state and cannot be rendered capable of reasonably
Page 79

Page 82

(Page 7 of 9) Template:PEAPPZ Ref: 22/01292/APP
beneficial use by the carrying out of any development which has been or would be
permitted, the owner of the land may serve on the planning authority a purchase
notice requiring the purchase of the owner of the land’s interest in the land in
accordance with Part 5 of the Town and Country Planning (Scotland) Act 1997.
Page 80

Page 83

APPENDIX 2 
NOTICE OF REVIEW,
GROUNDS FOR REVIEW &
SUPPORTING DOCUMENTS
Page 81

Page 84

Page 82

Page 85

Page 1 of 5
The Moray Council Council Office High Street Elgin IV30 1BX  Tel: 0300 1234561  Email: development.control@moray.gov.uk
Applications cannot be validated until all the necessary documentation has been submitted and the required fee has been paid.
Thank you for completing this application form:
ONLINE REFERENCE 100475230-006
The online reference is the unique reference for your online form only. The  Planning Authority will allocate an Application Number when
your form is validated. Please quote this reference if you need to contact the planning Authority about this application.
Applicant or Agent Details
Are you an applicant or an agent? * (An agent is an architect, consultant or someone else acting
on behalf of the applicant in connection with this application)  Applicant  Agent
Agent Details
Please enter Agent details
Company/Organisation:
Ref. Number: You must enter a Building Name or Number, or both: *
First Name: * Building Name:
Last Name: * Building Number:
Address 1
Telephone Number: * (Street): *
Extension Number: Address 2:
Mobile Number: Town/City: *
Fax Number: Country: *
Postcode: *
Email Address: *
Is the applicant an individual or an organisation/corporate entity? *
  Individual    Organisation/Corporate entity
Christopher
Bremner
Drybridge
Minduff
07876758717
AB56 5LB
Scotland
Buckie
christopher.bremner@hotmail.com
Page 83

Page 86

Page 2 of 5
Applicant Details
Please enter Applicant details
Title: You must enter a Building Name or Number, or both: *
Other Title: Building Name:
First Name: * Building Number:
Address 1
Last Name: * (Street): *
Company/Organisation Address 2:
Telephone Number: * Town/City: *
Extension Number: Country: *
Mobile Number: Postcode: *
Fax Number:
Email Address: *
Site Address Details
Planning Authority:
Full postal address of the site (including postcode where available):
Address 1: 
Address 2:
Address 3:
Address 4:
Address 5:
Town/City/Settlement:
Post Code:
Please identify/describe the location of the site or sites
Northing Easting
Mr
T
Moray Council
Wright Cameron Crescent
23
AB56 1AG
Plot 3 Minduff
Scotland
860411
Buckie
343427
christopher.bremner@hotmail.com
Page 84

Page 87

Page 3 of 5
Description of Proposal
Please provide a description of your proposal to which your review relates. The description should be the same as given in the
application form, or as amended with the agreement of the planning authority: *
(Max 500 characters)
Type of Application
What type of application did you submit to the planning authority? *
  Application for planning permission (including householder application but excluding application to work minerals).
  Application for planning permission in principle.
  Further application.
  Application for approval of matters specified in conditions.
What does your review relate to? *
  Refusal Notice.
 Grant of permission with Conditions imposed.
  No decision reached within the prescribed period (two months after validation date or any agreed extension) – deemed refusal.
Statement of reasons for seeking review
You must state in full, why you are a seeking a review of the planning authority’s decision (or failure to make a decision). Your statement
must set out all matters you consider require  to be taken into account in determining your review. If necessary this can be provided as a
separate document in the ‘Supporting Documents’ section: *  (Max 500 characters)
Note: you are unlikely to have a further opportunity to add to your statement of appeal at a later date, so it is essential that you produce
all of the information you want the decision-maker to take into account.
You should not however raise any new matter which was not before the planning authority at the time it decided your application (or at
the time expiry of the period of determination), unless you can demonstrate that the new matter could not have been raised before that
time or that it not being raised before that time is a consequence of exceptional circumstances.
Have you raised any matters which were not before the appointed officer  at the time the  Yes   No
Determination on your application was made? *
If yes, you should explain in the box below, why you are raising the new matter, why it was not raised with the appointed officer before
your application was determined and why you consider it should be considered in your review: * (Max 500 characters)
Erect dwellinghouse on Plot 3 Minduff Drybridge Buckie Moray
Review of condition 9 to allow tile roof finish.
Page 85

Page 88

Page 4 of 5
Please provide a list of all supporting documents, materials and evidence which you wish to submit with your notice of review and intend
to rely on in support of your review. You can attach these documents electronically later in the process: * (Max 500 characters)
Application Details
Please provide the application reference no. given to you by your planning
authority for your previous application.
What date was the application submitted to the planning authority? *
What date was the decision issued by the planning authority? *
Review Procedure
The Local Review Body will decide on the procedure to be used to determine your review and may at any time during the review
process require that further information or representations be made to enable them to determine the review. Further information may be
required by one or a combination of procedures, such as: written submissions; the holding of one or more hearing sessions and/or
inspecting the land which is the subject of the review case.
Can this review continue to a conclusion, in your opinion, based on a review of the relevant information provided by yourself and other
parties only,  without any further procedures? For example, written submission, hearing session, site inspection. *
 Yes   No
In the event that the Local Review Body appointed to consider your application decides to inspect the site, in your opinion:
Can the site be clearly seen from a road or public land? *  Yes   No
Is it possible for the site to be accessed safely and without barriers to entry? *  Yes    No
Checklist – Application for Notice of Review
Please complete the following checklist to make sure  you have provided all the necessary information in support of your appeal. Failure
to submit all this  information may result in your appeal  being deemed invalid.
Have you provided the name and address of the applicant?.  *  Yes   No
Have you provided the date and reference number of the application which is the subject of this  Yes   No
review? *
If you are the agent, acting on behalf of the applicant, have you provided details of your name  Yes   No   N/A
and address and indicated whether any notice or correspondence required in connection with the
review should be sent to you or the applicant? *
Have you provided a statement setting out your reasons for requiring a review and by what  Yes   No
procedure (or combination of procedures) you wish the review to be conducted? *
Note: You must state, in full, why you are seeking a review on your application. Your statement must set out all matters you consider
require to be taken into account in determining your review. You may not have a further opportunity to add to your statement of review
at a later date. It is therefore essential that you submit with your notice of review, all necessary information and evidence that you rely
on and wish the Local Review Body to consider as part of your review.
Please attach a copy of all documents, material and evidence which you intend to rely on  Yes   No
(e.g. plans and Drawings) which are now the subject of this review *
Note: Where the review relates to a further application e.g. renewal of planning permission or modification, variation or removal of a
planning condition or where it relates to an application for approval of matters specified in conditions, it is advisable to provide the
application reference number, approved plans and decision notice (if any) from the earlier consent.
Approved documents - Site plan, site sections, location plan, floor plans & elevations. Report of Handing Planning decision
22/01292/APP
16/01/2023
02/09/2022
Page 86

Page 89

Page 5 of 5
Declare – Notice of Review
I/We the applicant/agent certify that this is an application for review on the grounds stated.
Declaration Name: Mr Christopher Bremner
Declaration Date: 12/04/2023
Page 87

Page 90

Page 88

Page 91

1                                                                      
Christopher Bremner
Minduff ▪ Drybridge ▪ Buckie ▪ Moray ▪ AB56 5LB ▪ email: Christopher.bremner@hotmail.com ▪ mobile: 07876758717 
Plot 3 Minduff, Drybridge, AB56 5LB 
22/01292/APP 
We wish to appeal condition 9 on as detailed below. 
9. Notwithstanding the details shown on the approved plans, the roof of the dwellinghouse
hereby approved shall be finished in natural slate. 
Reason: 
To ensure the highest standards of material finish are achieved for new housing in the
countryside and that new housing is finished in a manner which reflects the traditional material
finishes of houses in Moray. 
A slate roof would not be in keeping with the immediately adjacent plot 2 and plot 5 which can
be seen in the background. 
Plot 2 - 18/00446/APP -  Completed 30/03/2021
Plot 5 - 15/01553/APP – Completed 23/06/2022
Both of these properties were approved and recently completed with Rathmore roof tiles. 
The Rathmore is a flat concrete interlocking tile with a smooth finish, its thin leading edge and
hidden interlocking features provides a slate like appearance.
Plot 1 is also about to commence on site and has a live consent with a condition to use artificial
Slate. 09/01922/APP. 
Page 89

Page 92

2 
This OS plan shows all the properties on this stretch of road and ones visible from the site.
There aren't many with slate roofs. 
1. Plot 1 Minduff  – Approved Planning permission
2. Plot 2 Minduff  – Recently completed with Quinn Rathmore roof tiles
3. Plot 5 Minduff  - Recently completed with Quinn Rathmore roof tiles
4. Plot 4 Minduff  – Approved Planning permission
5. Hillpark   – Tiles
6. Mandara   – Red tiles
7. Kingswood   – Tiles
8. Backstripes   – Tiles
9. Slack of Bait   – Tiles
10. Bramble cottage – Tiles
11. Glenshee  – Tiles
12. Whitegate  – Tiles
13. Whitegate lodge – Tiles
14. Little Thorneybank – Tiles
15. Greenbank  – Massive shed with profile cladding that can be seen for miles.
16. Newton  – Old stone house with slate roof
17. Hillfolds  – Old stone house with slate roof
18. Parkhill  – Old stone house with slate roof 
We could understand having to comply with the slate roof policy if this was a new site on its own
with no historic consent, but this is not the case with this application. 
We therefore would like the condition to use Slates removed from this consent.
Page 90

Page 93

REPORT OF HANDLING 
Ref No: 22/01292/APP Officer: Iain T Drummond
Proposal
Description/
Address  
Erect dwellinghouse  on Plot 3 Minduff Drybridge Buckie Moray
Date: 09.01.2023 Typist Initials: SS 
RECOMMENDATION
Approve, without or with condition(s) listed below Y
Refuse, subject to reason(s) listed below N
Legal Agreement required e.g. S,75 N
Notification to Scottish Ministers/Historic Scotland N
Hearing requirements
Departure N
Pre-determination N 
CONSULTATIONS
Consultee Date
Returned Summary of Response 
Planning And Development Obligations 09/09/22 No contributions sought due to extant
consent on site.
Moray Flood Risk Management 12/09/22 No objections
Environmental Health Manager 12/09/22 No objections
Contaminated Land 14/09/22 No objections
Private Water Supplies 15/09/22 No objections subject to condition
Transportation Manager 13/09/22 No objections subject to conditions and
informatives. 
DEVELOPMENT PLAN POLICY
Policies Dep Any Comments 
(or refer to Observations below)
PP3 Infrastructure and Services N 
DP1 Development Principles N 
DP4 Rural Housing N 
EP2 Biodiversity N 
EP12 Management and Enhancement Water N 
EP13 Foul Drainage N 
EP14 Pollution Contamination Hazards N 
REPRESENTATIONS
Representations Received  NO
Total number of representations received
Page 91

Page 94

Page 2 of 4
Names/Addresses of parties submitting representations 
Summary and Assessment of main issues raised by representations
Issue:
Comments (PO): 
OBSERVATIONS – ASSESSMENT OF PROPOSAL 
Proposal & Site  
 This application seeks to amend the design of the houses approved on site via applications
09/01922/APP and 12/02050/APP, both of which have had a lawful start to the consents in the
form of the partial formation of access and therefore remain extant.   
 The proposed house consists of a one and a half storey, T-shaped house with integral double
garage.   
 The proposed amended house design overlaps and largely sits on the same footprint as the
previously consented houses on this site.   
 This application seeks detailed planning permission for the amendment of the design previously
approved on site from a larger one and a half storey house.   
 Use of a private water supply is proposed with foul drainage disposed of via a treatment plant
and soakaway and surface water disposed of via a separate soakaway.    
 The temporary siting of a static caravan is also proposed throughout the duration of the
construction of the dwellinghouse.   
Appraisal  
Section 25 of the 1997 Act as amended requires applications to be determined in accordance with
the development plan i.e. the adopted Moray Local Development Plan 2020 (MLDP) unless material
considerations indicate otherwise. The main planning issues are considered below: 
Principle of the development (PP1, DP1 and DP2)   
The principle of erecting a house on this site has already been established via the approval of
applications 09/01922/APP and 12/02050/APP and therefore what requires to be considered as part
of this application is the amendments to the design and siting of the house.   
Design and amenity (PP1, DP1, DP4 and EP2)  
In terms of the amended house design, with the exception of the roof finish, the proposal is compliant
with the design and material finish requirements of policy DP4.  Where the applicants have specified
the use of slate effect tiles, policy DP4 specifically stipulates the use of natural slate or corrugated
roofing on houses in the countryside and precludes the use of concrete tiles and as such a condition
has been attached to the consent to ensure the finish of the house is natural slate in line with policy
requirements.  Landscaping proposals are lacking from the scheme, however, a condition has been
attached to ensure tree planting covering 15% of the site as required by policy is achieved.     
No tree removal is proposed as part of this application and in terms of biodiversity, the provision of
planting across the site will ensure biodiversity levels within the plot are enhanced.   
The temporary siting of a static caravan throughout the duration of the construction of the house is
also considered to be acceptable, subject to the condition as applied that the caravan is removed
following the completion or occupation of the dwellinghouse.   
Overall the proposals are considered to be compliant with policies PP1, DP1, DP4 and EP2.   
Page 92

Page 95

Page 3 of 4
Drainage (EP12, EP13)  
Drainage information has been provided with the application and identifies the means of surface
water disposal from the site.  Moray Flood Risk Management have assessed this information and
have no objections to the approval of the application. Environmental Health have also confirmed that
the proposed private water supply is sufficient to serve the proposed house subject to condition as
recommended and as such the proposal is considered to comply with policy EP12 and EP13.    
Access (DP1)  
Transportation have no objection to the approval of the application subject to conditions as
recommended and as such the development complies with policy DP1 in this regard.    
Developer obligations and affordable housing (PP3 and DP2) 
Developer obligations have already been paid in relation to the extant consent on site and as such
the proposals are compliant with policies PP3 and DP2.   
Conclusion and Recommendation  
Based on all of the above, taking into account comments received from consultees, this application is
considered to comply with development plan policy and is therefore recommended for approval
subject to conditions.   
REASON(S) FOR DECISION 
The Council's reason(s) for making this decision are:- 
The proposal complies with the provisions of the Moray Local Development Plan 2020 and
there are no material considerations that indicate otherwise.   
OTHER MATERIAL CONSIDERATIONS TAKEN INTO ACCOUNT 
None. 
HISTORY
Reference No. Description 
Erect house at Plot 3 Minduff Drybridge Buckie Moray
12/02050/APP Decision Permitted Date Of Decision 24/05/13   
Erect dwellinghouse on Plot 3 Minduff Drybridge Buckie Moray 
21/01560/APP Decision Refuse Date Of Decision 02/02/22   
ADVERT
Advert Fee paid? Yes
Local Newspaper Reason for Advert Date of expiry 
Banffshire Advertiser and
Herald No Premises 03/10/22
PINS No Premises 03/10/22 
Page 93

Page 96

Page 4 of 4
DEVELOPER CONTRIBUTIONS (PGU)
Status NONE SOUGHT 
DOCUMENTS, ASSESSMENTS etc. *
* Includes Environmental Statement, Appropriate Assessment, Design Statement, Design and Access Statement, RIA,
TA, NIA, FRA etc
Supporting information submitted with application? YES 
Summary of main issues raised in each statement/assessment/report
Document Name:  Drainage assessment
Main Issues:  Outlines the drainage methodology for the site.  
.
S.75 AGREEMENT
Application subject to S.75 Agreement  NO
Summary of terms of agreement:   
Location where terms or summary of terms can be inspected:   
DIRECTION(S) MADE BY SCOTTISH MINISTERS (under DMR2008 Regs)
Section 30 Relating to EIA  NO
Section 31 Requiring planning authority to provide information
and restrict grant of planning permission  NO
Section 32 Requiring planning authority to consider the imposition
of planning conditions  NO
Summary of Direction(s)   
Page 94

Page 97

(Page 1 of 9)  Template:PEAPPZ  Ref: 22/01292/APP 
[Fochabers Lhanbryde]
Application for Planning Permission 
TO Mr Timothy Wright 
c/o Christopher Bremner 
Minduff 
Drybridge 
Buckie 
Moray 
AB56 5LB   
With reference to your application for planning permission under the above-
mentioned Act as amended, Moray Council in exercise of its powers hereby GRANT
planning permission for the following development:- 
Erect dwellinghouse on Plot 3 Minduff Drybridge Buckie Moray  
in accordance with the plan(s) docquetted as relative hereto and the particulars
given in the application, and where appropriate, subject to the condition(s) and
reason(s) as set out in the attached schedule. 
This permission does not carry with it any necessary consent or approval to the
proposed development under the building regulations or other statutory enactments
and the development should not be commenced until all consents have been
obtained. 
Date of Notice:  16 January 2023 
Head Economic Growth and Development Services
Economy, Environment and Finance
Moray Council
Council Office
High Street
ELGIN
Moray     
IV30 1BX 
MORAY COUNCIL
TOWN AND COUNTRY PLANNING (SCOTLAND) ACT 1997,
as amended 
PERMISSION FOR DEVELOPMENT 
Page 95

Page 98

(Page 2 of 9)  Template:PEAPPZ  Ref: 22/01292/APP 
IMPORTANT NOTE 
YOU ARE OBLIGED TO COMPLY WITH THESE CONDITIONS AND NOTES 
SCHEDULE OF CONDITIONS 
By this Notice the Moray Council has GRANTED PLANNING PERMISSION for this
proposal subject to conditions as appropriate to ensure implementation of the
proposal under the Town & Country Planning (Scotland) Act 1997, as amended.  It
is important that these conditions are adhered to and failure to comply may
result in enforcement action being taken. 
CONDITION(S)
Permission is granted subject to the following conditions: -   
1 The development to which this permission relates must be begun not later
than the expiration of 3 years beginning with the date on which the
permission is granted.   
Reason: The time limit condition is imposed in order to comply with the
requirements of section 58 of the Town and Country Planning (Scotland) Act
1997 as amended.   
2 No development works shall commence on the dwelling house until a
detailed drawing (scale 1:200) has been submitted to and approved in
writing by the Council, as Planning Authority in consultation with the Roads
Authority confirming the provision of, or location where a future Electric
Vehicle (EV) charging unit is to be connected to an appropriate electricity
supply, including details (written proposals and plans) to confirm the
provision of the necessary cabling, ducting, and consumer units capable of
supporting the future charging unit; and thereafter the EV charging
infrastructure shall be provided in accordance with the approved drawing
and details prior to the first occupation of the dwelling house. 
Reason: In the interests of an acceptable form of development and the
provision of infrastructure to support the use of low carbon transport, through
the provision of details currently lacking. 
3 No water shall be permitted to drain or loose material be carried onto the
public carriageway. 
Reason: To ensure the safety and free flow of traffic on the public road and
access to the site by minimising the road safety impact from extraneous
material and surface water in the vicinity of the new access. 
4 A visibility splay 2.4 metres by 120 metres to the north-west shall be
provided at the access onto the public road, and maintained thereafter at all
times free from any obstruction greater than 0.6m in height measured from
the level of the carriageway. 
Page 96

Page 99

(Page 3 of 9)  Template:PEAPPZ  Ref: 22/01292/APP 
Reason: To enable drivers of vehicles leaving the site to have a clear view
over a length of road sufficient to allow safe exit, in the interests of road
safety for the proposed development and other road users. 
5 Three car parking spaces shall be provided within the site prior to the
occupation or completion of the dwelling house, whichever is the sooner.
The parking spaces shall thereafter be retained throughout the lifetime of the
development, unless otherwise agreed in writing with the Council as
Planning Authority. 
Reason: To ensure the permanent availability of the level of parking
necessary for residents/visitors/others in the interests of an acceptable
development and road safety.   
6 Prior to the occupation of the house hereby approved a scheme of effective
treatment to the private water supply shall be fully installed and properly
maintained for the lifetime of the development. The scheme must ensure that
the water to the house would fully comply with the regulatory limits stated in
The Water Intended for Human Consumption (Private Supplies) (Scotland)
Regulations 2017 and should specifically include effective point of entry
ultraviolet treatment, prefiltration, pH correction measures and
iron/manganese treatment.   
Reason: To ensure that the development is served by an adequate and
wholesome water supply. 
7 The paddock area associated with the plot as identified in the approved site
plan, shall be only used as paddock land, and not for domestic garden
purposes. Note. For the avoidance of doubt, the paddock does not have the
benefit of permitted development rights under Article 2(4), Schedule, Part 1
Classes 3B (Building, engineering, installation or other operation within the
curtilage of a dwellinghouse for any purpose incidental to the enjoyment of
the dwellinghouse) of the Town and Country Planning (General Permitted
Development) (Scotland) Order 1992, as amended by the Town & Country
Planning (General Permitted Development) (Scotland) Amendment Order
2011 (or any Order revoking and re-enacting that Order(s) with or without
modifications).   
Reason: To safeguard the rural character of the site and its surroundings, by
mitigating against any domestic encroachment into adjoining farm/paddock
land.   
8 Unless otherwise agreed in writing with the Planning Authority, boundary
enclosures surrounding the site hereby approved shall only comprise post
and wire fencing or hedging made up of native species (birch, gean,
hawthorn, scots pine, beech, oak, holly).  In addition 15% of the plot must be
landscaped with native tree species (whips and feathered trees at least 1.5
metres in height, planted at a density of 1 per 4 sqm).     
All planting, seeding or turfing shall be carried out in the first planting and
seeding seasons following the commencement of development.  Any trees
or plants which within a period of five years from the completion of the
Page 97

Page 100

(Page 4 of 9)  Template:PEAPPZ  Ref: 22/01292/APP
development die, for whatever reason are removed or damaged shall be
replaced in the next planting season with others of the same size and
species.   
Reason: To ensure an acceptable scheme of landscaping to aid the
integration of the house into the surrounding landscape and ensure the
planting is timeously provided.   
9 Notwithstanding the details shown on the approved plans, the roof of the
dwellinghouse hereby approved shall be finished in natural slate.     
Reason: To ensure the highest standards of material finish are achieved for
new housing in the countryside and that new housing is finished in a manner
which reflects the traditional material finishes of houses in Moray.   
10.  The residential caravan hereby permitted is solely for the use of the applicant
or developer for the duration of the construction works associated with the
development hereby approved.   Within 3 years from the date of this decision
notice or within 2 months following the occupation or completion of the
dwellinghouse, whichever is the sooner, the caravan shall be removed
permanently from the site, along with all associated fixtures and fittings. 
Reason: To ensure the removal of the residential caravan from the site
following the completion of the adjacent house, in the interests of minimising
and removing the visual impact of the caravan.   
REASON(S) FOR DECISION
The Council’s reason(s) for making this decision are:-  
The proposal complies with the provisions of the Moray Local Development Plan
2020 and there are no material considerations that indicate otherwise.   
LIST OF PLANS AND DRAWINGS SHOWING THE DEVELOPMENT
The following plans and drawings form part of the decision:-
Reference Version Title
20-121-PL02  Site sections
20-121-PL03  Site plan
20-126-Pl04  Location plan
20-121-PL01  Elevations and floor plans 
IMPORTANT NOTES ABOUT THIS DECISION 
Page 98

Page 101

(Page 5 of 9)  Template:PEAPPZ  Ref: 22/01292/APP 
COMMENCEMENT AND COMPLETION OF THE DEVELOPMENT  
The following are statutory requirements of the Town & Country Planning (Scotland)
Act 1997, as amended.  Failure to meet their respective terms represents a breach
of planning control and may result in formal enforcement action.  Copies of the
notices referred to below are attached to this permission for your use. 
NOTIFICATION OF INITIATION OF DEVELOPMENT 
S.27A of the 1997 Act, as amended requires that any person who has been granted
planning permission (including planning permission in principle) and intends to start
development must, as soon as practicable after deciding the date they will start work
on the development, give notice to the planning authority of that date.  This ensures
that the planning authority is aware that the development is underway and can follow
up on any suspensive conditions attached to the permission.  Therefore, prior to any
work commencing on site, the applicant/developer must complete and submit to the
Moray Council, as planning authority, the attached Notification of Initiation of
Development.   
NOTIFICATION OF COMPLETION OF DEVELOPMENT 
S.27B of the 1997 Act, as amended requires that any person who completes a
development for which planning permission (including planning permission in
principle) has been given must, as soon as practicable after doing so, give notice of
completion to the planning authority.  This will ensure that the planning authority is
aware that the development is complete and can follow up any planning conditions. 
Therefore, on completion of the development or as soon as practicable after doing
so, the applicant/developer must complete and submit to the Moray Council, as
planning authority the attached Notification of Completion of Development. 
NOTIFICATION OF COMPLETION OF PHASED DEVELOPMENT 
Under S.27B(2) of the 1997 Act, as amended where permission is granted for
phased development, the permission is subject to a condition (see Schedule of
Conditions above) requiring the applicant/developer as soon as practicable after
each phase to give notice of that completion to the planning authority.  This will allow
the planning authority to be aware that particular phase(s) of the development is/are
complete.  
When the last phase is completed the applicant/developer must also complete and
submit a Notification of Completion of Development. 
ADDITIONAL NOTES FOR INFORMATION OF THE APPLICANT
The following notes are provided for your information including comments received
from consultees:- 
THE TRANSPORTATION MANAGER, DIRECT SERVICES has commented that:- 
Planning consent does not carry with it the right to carry out works within the
public road boundary. 
The provision of Electric Vehicle (EV) chargers and/or associated infrastructure
Page 99

Page 102

(Page 6 of 9)  Template:PEAPPZ  Ref: 22/01292/APP
shall be provided in accordance with Moray Council guidelines. Cabling
between charging units and parking spaces must not cross or obstruct the
public road including footways. Infrastructure provided to enable EV charging
must be retained for this purpose for the lifetime of the development unless
otherwise agreed in writing by the Planning Authority. Guidance on Electric
Vehicle (EV) Charging requirements can be found at:
http://www.moray.gov.uk/downloads/file134860.pdf 
Public utility apparatus may be affected by this proposal. Contact the
appropriate utility service in respect of any necessary utility service alterations
which have to be carried out at the expense of the developer. 
No building materials/scaffolding/builder's skip shall obstruct the public road
(including footpaths) without permission from the Roads Authority. 
The applicant shall free and relieve the Roads Authority from any claims arising
out of their operations on the road or extension to the road. 
DETAILS OF ANY VARIATION MADE TO ORIGINAL PROPOSAL,
AS AGREED WITH APPLICANT (S.32A of 1997 ACT) 
None 
DETAILS WHERE DIFFERENT TIME-PERIOD(S) FOR DURATION OF PLANNING
PERMISSION IMPOSED (S.58/59 of 1997 ACT) 
None 
TERMS OF S.75 AGREEMENT RELATING TO THIS APPLICATION
The terms, or summary of terms of the Agreement can be inspected at:- 
None 
NOTICE OF APPEAL
TOWN AND COUNTRY PLANNING (SCOTLAND) ACT 1997 
If the applicant is aggrieved by the decision to refuse permission for or approval
required by a condition in respect of the proposed development, or to grant
permission or approval subject to conditions, the applicant may require the planning
authority to review the case under section 43A of the Town and Country Planning
(Scotland) Act 1997 within three months from the date of this notice.  The notice of
review should be addressed to The Clerk, The Moray Council Local Review Body,
Legal and Committee Services, Council Offices, High Street, Elgin IV30 1BX.  This
form is also available and can be submitted online or downloaded from
www.eplanning.scotland.gov.uk   
If permission to develop land is refused or granted subject to conditions and the
owner of the land claims that the land has become incapable of reasonably
beneficial use in its existing state and cannot be rendered capable of reasonably
Page 100

Page 103

(Page 7 of 9)  Template:PEAPPZ  Ref: 22/01292/APP
beneficial use by the carrying out of any development which has been or would be
permitted, the owner of the land may serve on the planning authority a purchase
notice requiring the purchase of the owner of the land’s interest in the land in
accordance with Part 5 of the Town and Country Planning (Scotland) Act 1997. 
Page 101

Page 104

(Page 8 of 9)  Template:PEAPPZ  Ref: 22/01292/APP 
MORAY COUNCIL 
NOTIFICATION OF INITIATION OF DEVELOPMENT 
Section 27A Town and Country Planning (Scotland) Act 1997 
Application Number  22/01292/APP 
Date Decision Issued 
Location and Description of
Development 
Erect dwellinghouse  on Plot 3 Minduff Drybridge
Buckie Moray 
Please note that all suspensive conditions must be discharged prior to
commencement of development 
Date works are to
Commence 
Name, Address and contact details of developer 
The Full name and Address and contact details of the landowner, if a different
person 
Where an agent is appointed, their full name and contact details 
Signed 
Name (Print) 
Date 
Please complete and return this form to: 
Development Management & Building Standards Manager, Moray Council, PO
Box 6760, Elgin, Moray, IV30 1BX  
OR
E-mail:  development.control@moray.gov.uk 
Page 102

Page 105

(Page 9 of 9)  Template:PEAPPZ  Ref: 22/01292/APP 
MORAY COUNCIL 
NOTIFICATION OF COMPLETION OF DEVELOPMENT 
Section 27A Town and Country Planning (Scotland) Act 1997 
Application Number  22/01292/APP 
Date Decision Issued 
Location and Description of
Development 
Erect dwellinghouse  on Plot 3 Minduff Drybridge
Buckie Moray   
Date of completion of works 
Name, Address and contact details of developer 
The Full name and Address and contact details of the landowner, if a different
person 
Where an agent is appointed, their full name and contact details 
Signed 
Name (Print) 
Date 
Please complete and return this form to: 
Development Management & Building Standards Manager, Moray Council, PO
Box 6760, Elgin, Moray IV30 1BX  
E-mail:  development.control@moray.gov.uk 
Page 103

Page 106

Page 104

Page 107

Page 105

Page 108

Page 106

Page 109

Page 107

Page 110

Page 108

Page 111

MORAY LOCAL REVIEW BODY 
16 MAY 2023 
SUMMARY OF INFORMATION FOR CASE No LR288 
Ward 7 – Elgin City South 
Planning Application 22/01451/APP – Retrospective permission for boundary
fence at 94 Springfield Road, Elgin 
Planning permission was refused under the Statutory Scheme of Delegation by the
Appointed Officer on 12 January 2023 on the grounds that: 
1. The high level boundary fence is out of keeping with the established open
aspect character of the existing site and neighbouring housing and would
therefore fail to comply with Policy DP1 (i) (a). 
2. The high level fencing would partially enclose an area of open space to the
rear of the property which requires natural surveillance in order to reduce
crime and would therefore fail to comply with policy PP1 (ii). 
Documents considered or prepared by the Appointed Officer in respect of the above
planning application are attached as Appendix 1. 
The Notice of the Review, Grounds for Review and any supporting documents
submitted by the Applicant are attached as Appendix 2. 
No Further Representations were received in response to the Notice of Review. 
At the meeting of the Moray Local Review Body (MLRB) on 16 February 2023, the
MLRB noted that National Planning Framework 4 (NPF4) had been adopted by the
Council on Monday 13 February 2023 and that all planning applications determined
beyond this date would have to take NPF4 into consideration, as this is now part of
the MLDP 2020 and deferred consideration of the above Review to request further
information from the Appointed Officer and Interested Parties after considering the
planning application in light of NPF4 with any response received being forwarded to
the Applicant for comment. 
The Appointed Officer’s response is attached as Appendix 5.  There was no
response from the Applicant or any of the Interested Parties.
Item 5
Page 109

Page 112

Page 110

Page 113

6 to 12
El
30 to
38 to 44
22 to 28
Path (um)
SPRINGFIELD ROAD
KIRKTON PLACE
Mast
HELDON PLACE
1
3
45
21
71
46
50
19
8
67 13
28
65
48
11
35
27
6
20
86
52
94
74
26
10
16
15
34
22
102
84
23
29
106
17
2
24
55
4
7
5
51
62
49
54
92
43
25
98
PLACE
MANNOCH COURT
4
1
2
8
13
13
4
11
11
1
19
1
16
2
8
46
10 1365
1
21
2
2
Location plan for Planning Application Reference Number :
22/01451/APP
This map is reproduced from Ordnance Survey material with the permission of Ordnance Survey on behalf of the Controller of Her Majesty's
Stationary Office Unauthorised reproduction infringes  Crown Copyright and may lead to prosecution or civil proceedings.
(c) Crown Copyright.  The Moray Council 100023422 2023 Page 111

Page 114

Page 112

Page 115

APPENDIX 1 
DOCUMENTS CONSIDERED
OR PREPARED BY THE
APPOINTED OFFICER
Page 113

Page 116

Page 114

Page 117

Page 1 of 5
The Moray Council Council Office High Street Elgin IV30 1BX  Tel: 0300 1234561  Email: development.control@moray.gov.uk
Applications cannot be validated until all the necessary documentation has been submitted and the required fee has been paid.
Thank you for completing this application form:
ONLINE REFERENCE 100602338-001
The online reference is the unique reference for your online form only. The  Planning Authority will allocate an Application Number when
your form is validated. Please quote this reference if you need to contact the planning Authority about this application.
Description of Proposal
Please describe accurately the work proposed: * (Max 500 characters)
Has the work already been started and/ or completed? *
 No  Yes - Started  Yes – Completed
Applicant or Agent Details
Are you an applicant or an agent? * (An agent is an architect, consultant or someone else acting
on behalf of the applicant in connection with this application)  Applicant  Agent
Retrospective planning for boundary fence with amended drawings to the requirements of the transport managers comments in
previous application
Page 115

Page 118

Page 2 of 5
Applicant Details
Please enter Applicant details
Title: You must enter a Building Name or Number, or both: *
Other Title: Building Name:
First Name: * Building Number:
Address 1
Last Name: * (Street): *
Company/Organisation Address 2:
Telephone Number: * Town/City: *
Extension Number: Country: *
Mobile Number: Postcode: *
Fax Number:
Email Address: *
Site Address Details
Planning Authority:
Full postal address of the site (including postcode where available):
Address 1:
Address 2:
Address 3:
Address 4:
Address 5:
Town/City/Settlement:
Post Code:
Please identify/describe the location of the site or sites
Northing Easting
Mr
94 SPRINGFIELD ROAD
Michael
Moray Council
Barron Springfield road
94
ELGIN
IV30 6YU
Iv306yu
Scotland
861385
Elgin
321513
Page 116

Page 119

Page 3 of 5
Pre-Application Discussion
Have you discussed your proposal with the planning authority? *  Yes  No
Pre-Application Discussion Details Cont.
In what format was the feedback given? *
 Meeting  Telephone  Letter  Email
Please provide a description of the feedback you were given and the name of the officer who provided this feedback. If a processing
agreement [note 1] is currently in place or if you are currently discussing a processing agreement with the planning authority, please
provide details of this. (This will help the authority to deal with this application more efficiently.) * (max 500 characters)
Title: Other title:
First Name: Last Name:
Correspondence Reference Date (dd/mm/yyyy):
Number:
Note 1. A Processing agreement involves setting out the key stages involved in determining a planning application, identifying what
information is required and from whom and setting timescales for the delivery of various stages of the process.
Trees
Are there any trees on or adjacent to the application site? *  Yes  No
If yes, please mark on your drawings any trees, known protected trees and their canopy spread close to the proposal site and indicate if
any are to be cut back or felled.
Access and Parking
Are you proposing a new or altered vehicle access to or from a public road? *  Yes  No
If yes, please describe and show on your drawings the position of any existing, altered or new access points, highlighting the changes
you proposed to make. You should also show existing footpaths and note if there will be any impact on these.
Planning Service Employee/Elected Member Interest
Is the applicant, or the applicant’s spouse/partner, either a member of staff within the planning service or an  Yes  No
elected member of the planning authority? *
Certificates and Notices
CERTIFICATE AND NOTICE UNDER REGULATION 15 – TOWN AND COUNTRY PLANNING (DEVELOPMENT MANAGEMENT
PROCEDURE) (SCOTLAND) REGULATION 2013
One Certificate must be completed and submitted along with the application form. This is most usually Certificate A, Form 1,
Certificate B, Certificate C or Certificate E.
Are you/the applicant the sole owner of ALL the land? *  Yes  No
Is any of the land part of an agricultural holding? *  Yes  No
information on applying for permission with updated drawings of previous application
Mr
Andrew Miller
17/01/2022
Page 117

Page 120

Page 4 of 5
Certificate Required
The following Land Ownership Certificate is required to complete this section of the proposal:
Certificate A
Land Ownership Certificate
Certificate and Notice under Regulation 15 of the Town and Country Planning (Development Management Procedure) (Scotland)
Regulations 2013
Certificate A
I hereby certify that –
(1) - No person other than myself/the applicant was an owner (Any person who, in respect of any part of the land, is the owner or is the
lessee under a lease thereof of which not less than 7 years remain unexpired.) of any part of the land to which the application relates at
the beginning of the period of 21 days ending with the date of the accompanying application.
(2) - None of the land to which the application relates constitutes or forms part of an agricultural holding
Signed: Mr Michael Barron
On behalf of:
Date: 05/10/2022
 Please tick here to certify this Certificate. *
Checklist – Application for Householder Application
Please take a few moments to complete the following checklist in order to ensure that you have provided all the necessary information
in support of your application. Failure to submit sufficient information with your application may result in your application being deemed
invalid. The planning authority will not start processing your application until it is valid.
a) Have you provided a written description of the development to which it relates?.  *  Yes  No
b) Have you provided the postal address of the land to which the development relates, or if the land in question  Yes  No
has no postal address, a description of the location of the land?  *
c) Have you provided the name and address of the applicant and, where an agent is acting on behalf of the  Yes  No
applicant, the name and address of that agent.?  *
d) Have you provided a location plan sufficient to identify the land to which it relates showing the situation of the  Yes  No
land in relation to the locality and in particular in relation to neighbouring land? *. This should have a north point
and be drawn to an identified scale.
e) Have you provided a certificate of ownership? *  Yes  No
f) Have you provided the fee payable under the Fees Regulations? *  Yes  No
g) Have you provided any other plans as necessary? *  Yes  No
Continued on the next page
Page 118

Page 121

Page 5 of 5
A copy of the other plans and drawings or information necessary to describe the proposals
(two must be selected). *
You can attach these electronic documents later in the process.
 Existing and Proposed elevations.
 Existing and proposed floor plans.
 Cross sections.
 Site layout plan/Block plans (including access).
 Roof plan.
 Photographs and/or photomontages.
Additional Surveys – for example a tree survey or habitat survey may be needed. In some instances you  Yes  No
may need to submit a survey about the structural condition of the existing house or outbuilding.
A Supporting Statement – you may wish to provide additional background information or justification for your  Yes  No
Proposal. This can be helpful and you should provide this in a single statement. This can be combined with a
Design Statement if required. *
You must submit a fee with your application. Your application will not be able to be validated until the appropriate fee has been
Received by the planning authority.
Declare – For Householder Application
I, the applicant/agent certify that this is an application for planning permission as described in this form and the accompanying
Plans/drawings and additional information.
Declaration Name: Mr Michael Barron
Declaration Date: 05/10/2022
Page 119

Page 122

Page 120

Page 123

S
P
R
IN
G
F
IE
L
D
R
O
A
D
16
2
94
86
98
92
0
50
10
El Sub
Sta
M
A
N
N
O
C
H
C
O
U
R
T
H
E
L
D
O
N
P
L
A
C
E
S
P
R
IN
G
F
IE
L
D
R
O
A
D
10
102
1062
1621
13
2
8
1113
10
23
Play
Area
H
E
L
D
O
N
P
L
A
C
E
K
IR
K
T
O
N
P
L
A
C
E
PH
1
24
2
8
4
94
86
74
98
92
84
25
27
13
19
15
0
100
20
50
Drawing
No. 1
SITE
PLAN
1-500
Site
Area
- 300m
2
(outlined
in
Red)
LOCATION
PLAN
1-1250
Retrospective
Planning
Application,
Fence
Erected
to
side
of House,
94
Springfield
Road,
Elgin,
IV30
6YU.
Mr M. Barron
New
fence -
100mm
wide x 20mm
thick fencing boards with
20mm
gaps between boards. Colour - dark brown
Fence kept clear of visibility splays.
900mm
high
900mm
high
ELEVATION
FROM
SPRINGFIELD
ROAD
1-100
Site
area
outlined
in
red
new
fence
shown
in
green
2.4x5.0m
visibility
splays
noted
in
blue
fence
line
behind
visibility
splay
fence
height to
be
900m
m
at
visibility
splay
Rev
A
- Fence
line
at RHS
am
ended, Fence height at LHS
lowered. Jan
'22
Page 121

Page 124

Page 122

Page 125

S
P
R
IN
G
F
IE
L
D
R
O
A
D
16
2
94
86
98
92
0
50
10
El Sub
Sta
M
A
N
N
O
C
H
C
O
U
R
T
H
E
L
D
O
N
P
L
A
C
E
S
P
R
IN
G
F
IE
L
D
R
O
A
D
10
102
1062
1621
13
2
8
1113
10
23
Play
Area
H
E
L
D
O
N
P
L
A
C
E
K
IR
K
T
O
N
P
L
A
C
E
PH
1
24
2
8
4
94
86
74
98
92
84
25
27
13
19
15
0
100
20
50
Drawing
No. 1
SITE
PLAN
1-500
Site
Area
- 300m
2
(outlined
in
Red)
LOCATION
PLAN
1-1250
Retrospective
Planning
Application,
Fence
Erected
to
side
of House,
94
Springfield
Road,
Elgin,
IV30
6YU.
Mr M. Barron
New
fence -
100mm
wide x 20mm
thick fencing boards with
20mm
gaps between boards. Colour - dark brown
Fence kept clear of visibility splays.
900mm
high
900mm
high
ELEVATION
FROM
SPRINGFIELD
ROAD
1-100
Site
area
outlined
in
red
new
fence
shown
in
green
2.4x5.0m
visibility
splays
noted
in
blue
fence
line
behind
visibility
splay
fence
height to
be
900m
m
at
visibility
splay
Rev
A
- Fence
line
at RHS
am
ended, Fence height at LHS
lowered. Jan
'22
Page 123

Page 126

Page 124

Page 127

My partner and I moved into our property on June 4th 2017. We decided in march 2018 to replace
the existing 1.2 meter high boundary fence with a 1.8 meter high fence to the rear. This was due to
several concerning issues. School kids littering our garden, throwing items of food at our dog and
in some cases opening the gateand letting him
out,this resulted in us not being able to let him
into the garden during school hours when the school kids were out. The head teacher was
contacted by myself on a number of occasions and is happy to be contacted with regards to the
issues we discussed. Items from
our garden such as plants and garden ornamentsaswell as our
garden benchgoing missing which lead to us installing CCTV directed at the front and rear of the
property.
We also had many issues with people leaving the
local pub and entering our garden aswell as the garden of the property to the front of our house,
to relieve themselves.
By replacing the 1.2 meter boundary fence with a 1.8 meter high boundary fence this provided us
with the much needed privacy and also a safe and secure environment for our nephew, dog and
future children of our own.
At the time of doing so we were unaware of the need for planning permission as the fence height
of 1.8 meters is the same scale as properties across the road from
us and in the surrounding area
local to us and around Elgin as a whole.
Included inthis applicationis a revised drawing of the fence, we have addressed the points set out
by the transportation manager, who in their reportin our previous applicationacknowledgedthe
need for privacy due to the high number of pedestrian and vehicle movement in the area.
On receiving letters of notification of ourpreviousplanning application a number of our neighbors
came to us with concerns as to what was going on, being aware of the difficulties we occurred four
years ago. We also recently had a school kid enter our driveway, walk up to our door and get his
friend to film
him
for a tik-tok video heavily kicking our front door whilst we were at work. We
were alerted to this by our ring doorbell and was recorded on our front of house CCTV.
None of these details about the issues we were having werenoted in our initial planning
application as our architect submitted the application without knowing the details.
We are expecting our first child in januaryand we fear the removal of thefencewould leave us
with an unsafe garden to bring our child up inaswell as havingamajor affect on our nephews
routine asthiswould involve him
not being able to play in the gardenaswel as our previous
problems returning.
Page 125

Page 128

Page 126

Page 129

S
P
R
IN
G
F
IE
L
D
R
O
A
D
16
2
94
86
98
92
0
50
10
El Sub
Sta
M
A
N
N
O
C
H
C
O
U
R
T
H
E
L
D
O
N
P
L
A
C
E
S
P
R
IN
G
F
IE
L
D
R
O
A
D
10
102
1062
1621
13
2
8
1113
10
23
Play
Area
H
E
L
D
O
N
P
L
A
C
E
K
IR
K
T
O
N
P
L
A
C
E
PH
1
24
2
8
4
94
86
74
98
92
84
25
27
13
19
15
0
100
20
50
Drawing
No. 1
SITE
PLAN
1-500
Site
Area
- 300m
2
(outlined
in
Red)
LOCATION
PLAN
1-1250
Retrospective
Planning
Application,
Fence
Erected
to
side
of House,
94
Springfield
Road,
Elgin,
IV30
6YU.
Mr M. Barron
1820mm
high
New
fence -
100mm
wide x 20mm
thick fencing boards with
20mm
gaps between boards. Colour - dark brown
1200mm
high
ELEVATION
FROM
SPRINGFIELD
ROAD
1-100
Site
area
outlined
in
red
new
fence
shown
in
green
Page 127

Page 130

Page 128

Page 131

Consultation Request Notification 
Planning Authority Name Moray Council
Response Date  21st October 2022
Planning Authority
Reference
22/01451/APP
Nature of Proposal
(Description)
Retrospective planning for boundary fence at
Site 94 Springfield Road
Elgin
Moray
IV30 6YU 
Site Postcode N/A
Site Gazetteer UPRN 000133029398
Proposal Location Easting 321513
Proposal Location Northing 861385
Area of application site (M2) 
Additional Comment 
Development Hierarchy
Level
LOCAL
Supporting Documentation
URL
https://publicaccess.moray.gov.uk/eplanning/ce
ntralDistribution.do?caseType=Application&ke
yVal=RJBI0TBGIY000
Previous Application 21/01030/APP 
Date of Consultation 7th October 2022
Is this a re-consultation of
an existing application?
No
Applicant Name Mr Michael Barron
Applicant Organisation
Name 
Applicant Address 94 Springfield road
Elgin
Scotland
Iv306yu 
Agent Name 
Agent Organisation Name 
Agent Address 
Agent Phone Number 
Agent Email Address N/A
Case Officer Sheila Bernard
Case Officer Phone number 
Case Officer email address sheila.bernard@moray.gov.uk
PA Response To consultation.planning@moray.gov.uk 
NOTE:
If you do not respond by the response date, it will be assumed that you have no
comment to make. 
The statutory period allowed for a consultation response is 14 days.  Due to scheduling
Page 129

Page 132

pressures if a definitive response is not received within 21 days this may well cause the
two month determination period to be exceeded. 
Data Protection - Moray Council is the data controller for this process.  Information collected about
you on this form will be used to process your Planning Application, and the Council has a duty to
process your information fairly.  Information we hold must be accurate, up to date, is kept only for
as long as is necessary and is otherwise shared only where we are legally obliged to do so.  You
have a legal right to obtain details of the information that we hold about you.
For full terms please visit  http://www.moray.gov.uk/moray_standard/page_121513.html 
For full Data Protection policy, information and rights please see
http://www.moray.gov.uk/moray_standard/page_119859.html 
You can contact our Data Protection Officer at info@moray.gov.uk or 01343 562633 for more
information. 
Please respond using the attached form:- 
Page 130

Page 133

MORAY COUNCIL 
PLANNING CONSULTATION RESPONSE 
From:   Transportation Manager 
Planning Application Ref. No: 22/01451/APP
Retrospective planning for boundary fence at 94 Springfield Road Elgin Moray IV30 6YU for
Mr Michael Barron 
I have the following comments to make on the application:-  
Please 
(a) I OBJECT to the application for the reason(s) as stated below  
(b) I have NO OBJECTIONS to the application and have no condition(s) and/or
comment(s) to make on the proposal 

(c) I have NO OBJECTIONS to the application subject to condition(s) and/or
comment(s) about the proposal as set out below   
x
(d) Further information is required in order to consider the application as set out
below 

This proposal relates to a previous retrospective planning application for the erection of a
high boundary fence (21/01030/APP), and is effectively to now alter the erected
boundaries in order to accommodate suitable pedestrian and vehicular visibility splays. 
The submitted proposals show the lowering of the existing boundary fence adjacent to the
vehicular access and adjacent to the existing remote footpath along the south east corner
of the site; along with the setting back of the existing boundary fence located along the
south west corner of the site; and thereby effectively re-instating the (key) visibility splays
which were previously available prior to the high boundary being erected 
Transportation therefore has no objections to the proposed alterations.
Condition(s)
1. Within three months of the date of this decision notice the sections of the existing high
boundary fence shall be set back/ reduced in height in accordance with submitted
drawing number 1 Revision A. 
Reason: To ensure acceptable development in the interests of road safety. 
Further comment(s) to be passed to applicant
Planning consent does not carry with it the right to carry out works within the public road
boundary. 
No building materials/scaffolding/builder’s skip shall obstruct the public road (including
footpaths) without permission from the Roads Authority. 
Page 131

Page 134

Contact: AG Date 25 October 2022
email address: transport.develop@moray.gov.uk  
Consultee: TRANSPORTATION 
Return response to  consultation.planning@moray.gov.uk 
Please note that information about the application including consultation responses and representations (whether in support or objection) received on the proposal will be published on the Council’s website at
http://publicaccess.moray.gov.uk/eplanning/  (You can also use this site to track progress of the application and view details of any consultation responses and representations (whether in support or objection) received
on the proposal).  In order to comply with the Data Protection Act, personal information including signatures, personal telephone and email details will be removed prior to publication using “redaction” software to avoid
(or mask) the display of such information.  Where appropriate other “sensitive” information within documents will also be removed prior to publication online.
Page 132

Page 135

REPORT OF HANDLING 
Ref No: 22/01451/APP Officer: Fiona Olsen
Proposal
Description/
Address  
Retrospective permission for boundary fence at 94 Springfield Road Elgin Moray IV30
6YU
Date: 06.01.2023 Typist Initials: SS 
RECOMMENDATION
Approve, without or with condition(s) listed below 
Refuse, subject to reason(s) listed below Y
Legal Agreement required e.g. S,75 
Notification to Scottish Ministers/Historic Scotland 
Hearing requirements
Departure 
Pre-determination 
CONSULTATIONS
Consultee Date
Returned Summary of Response 
Transportation Manager 25/10/22 No Objections subject to a condition 
DEVELOPMENT PLAN POLICY
Policies Dep Any Comments 
(or refer to Observations below)
PP1 Placemaking Y See below
DP1 Development Principles Y See below 
REPRESENTATIONS
Representations Received  NO
Total number of representations received
Names/Addresses of parties submitting representations 
Summary and Assessment of main issues raised by representations
Issue:
Comments (PO): 
OBSERVATIONS – ASSESSMENT OF PROPOSAL 
Section 25 of the 1997 Act as amended requires applications to be determined in accordance with
the development plan i.e. the adopted Moray Local Development Plan 2020 (MLDP) unless material
considerations indicate otherwise. The main planning issues are considered below:   
Page 133

Page 136

Page 2 of 4
Proposal 
The application seeks retrospective planning permission for a boundary fence which encloses an
existing domestic garden.    
The existing fence measures approx. 1.82m to the rear and side boundaries. The fence slopes down
to a height of approx. 1.2m to the front boundary and is constructed in timber, stained in a dark
brown.    
The application proposes to reduce the height of the fence on part of the side boundary to 1.2m in
order to ensure an appropriate pedestrian visibility splay is achieved at the property access.    
Site  
The site is located at 92 Springfield Road, New Elgin, Elgin and is an existing semi-detached property
with gable end facing onto Springfield Road. The house fronts to a footpath to the west, with houses
either side of the path. To the rear, the house backs on to a path and area of open space. 
Site History 
A previous application was submitted for retrospective permission for the fence in 2021
(21/01030/APP refers) and was subsequently refused. These proposals are slightly altered from the
previous application in that the fence is proposed to be lowered at the eastern end of the side
boundary to approx. 1.2m in height in order to provide a pedestrian visibility splay. These alterations
to the fence height have not yet been undertaken. 
Policy Assessment 
Siting and Design (MLDP 2020 Policies DP1 & PP3) 
This application is assessed against policies DP1 and PP3 of the Moray Local Development plan
2020. Policy DP1 requires that the scale, density and character of all development be appropriate to
the surrounding area, be integrated into the surrounding landscape and not adversely impact upon
neighbouring properties in terms of privacy, daylight or overbearing loss of amenity.    
Policy PP1 requires that developments are designed to prevent crime, fear of crime and anti-social
behaviour with good levels of natural surveillance and security using treatments such as low
boundary walls. It also states that unbroken high boundary treatments such as wooden fencing and
blank gables onto routes, open spaces and communal areas will not be acceptable.   
The application seeks to retrospective permission for a 1.82m metre fence (to the rear and side
boundaries) and 1.2m fence (to the front boundary) at an existing dwellinghouse. Although it is
proposed to reduce the fence in height partially on the side boundary (to approx. 1.2m), the majority
of the side boundary and entirety of the rear boundary is proposed to be retained at approx 1.82m in
height.    
The existing site and surrounding area are characterised by terraced or semi-detached
dwellinghouses, set along an established building line in a uniform manner. These properties are
enclosed by low rise boundary treatments, particularly where they bound pathways, which results in
most housing having open aspect gardens (including to the side and rear boundaries).  The high level
boundary fence here (at approx. 1.82m) would fully enclose the side and rear garden in a manner not
in keeping with the established open aspect character present along Springfield Road and
surrounding streets. As a result, a high level boundary fence in this location would be out of keeping
with the established character of low level boundary fencing in this area and would therefore be
unacceptable in terms of policy DP1. 
An area of open space lies to the rear of the property, with a number of neighbouring properties
forming pedestrian access onto this area. These properties form a 'U' shape and are all defined by
low level boundary fencing. This open aspect ensures provision of natural surveillance to the area of
open space which reduces crime. Again the high level side boundary fence faces onto a footpath,
Page 134

Page 137

Page 3 of 4
running along the edge of Springfield Road.  Therefore the proposal for a high level boundary fence
in this location would not comply with policy PP1 which does not permit unbroken high level boundary
enclosures where they face onto routes, open spaces and communal areas.     
Road Safety (DP1) 
Policy DP1 requires all development to provide a safe and suitable access to the road network. The
submitted plans show the lowering of the existing boundary fence adjacent to the vehicular access
and adjacent to the existing remote footpath along the south east corner of the site; along with the
setting back of the existing boundary fence located along the south west corner of the site; and
thereby effectively re-instating the (key) visibility splays which were previously available prior to the
high boundary being erected. The Transportation Section have been consulted and are satisfied with
the amendments to the boundary fence proposed and would have no objections, subject to a
condition requiring the required sections of fence to be lowered and set back, in accordance with the
submitted drawings, within three months of any decision date. This however would not overcome the
aforementioned objections and the application will be refused. 
Conclusion  
The existing high level boundary fence is out of keeping with the established open aspect character
of the existing site and neighbouring housing and would therefore fail to comply with Policy DP1 (i)
(a). The high level fencing would also partially enclose an area of open space to the rear of the
property which requires natural surveillance in order to reduce crime and would therefore fail to
comply with policy PP1 (ii). 
OTHER MATERIAL CONSIDERATIONS TAKEN INTO ACCOUNT 
None. 
HISTORY
Reference No. Description 
Retrospective application for fence erected to side of house at 94 Springfield
Road Elgin Moray IV30 6YU 
21/01030/APP Decision Refuse Date Of Decision 08/10/21   
ADVERT
Advert Fee paid? N/A
Local Newspaper Reason for Advert Date of expiry 
DEVELOPER CONTRIBUTIONS (PGU)
Status N/A 
Page 135

Page 138

Page 4 of 4
DOCUMENTS, ASSESSMENTS etc. *
* Includes Environmental Statement, Appropriate Assessment, Design Statement, Design and Access Statement, RIA,
TA, NIA, FRA etc
Supporting information submitted with application?  NO
Summary of main issues raised in each statement/assessment/report
Document Name: 
Main Issues: 
S.75 AGREEMENT
Application subject to S.75 Agreement  NO
Summary of terms of agreement:   
Location where terms or summary of terms can be inspected:   
DIRECTION(S) MADE BY SCOTTISH MINISTERS (under DMR2008 Regs)
Section 30 Relating to EIA  NO
Section 31 Requiring planning authority to provide information
and restrict grant of planning permission  NO
Section 32 Requiring planning authority to consider the imposition
of planning conditions  NO
Summary of Direction(s)   
Page 136

Page 139

Page 137

Page 140

(Page 2 of 3) Ref:  22/01451/APP
IMPORTANT
YOUR ATTENTION IS DRAWN TO THE REASONS and NOTES BELOW
SCHEDULE OF REASON(S) FOR REFUSAL
By this Notice, Moray Council has REFUSED this proposal.  The Council’s reason(s)
for this decision are as follows: -
1. The high level boundary fence is out of keeping with the established open
aspect character of the existing site and neighbouring housing and would
therefore fail to comply with Policy DP1 (i) (a).
2. The high level fencing would partially enclose an area of open space to the rear
of the property which requires natural surveillance in order to reduce crime and
would therefore fail to comply with policy PP1 (ii).
LIST OF PLANS AND DRAWINGS SHOWING THE DEVELOPMENT
The following plans and drawings form part of the decision:-
Reference Version Title
Location Plan
Elevations
Page 138

Page 141

(Page 3 of 3) Ref:  22/01451/APP
NOTICE OF APPEAL
TOWN AND COUNTRY PLANNING (SCOTLAND) ACT 1997
If the applicant is aggrieved by the decision to refuse permission for or approval
required by a condition in respect of the proposed development, or to grant
permission or approval subject to conditions, the applicant may require the planning
authority to review the case under section 43A of the Town and Country Planning
(Scotland) Act 1997 within three months from the date of this notice.  The notice of
review should be addressed to The Clerk, Moray Council Local Review Body, Legal
and Committee Services, Council Offices, High Street, Elgin IV30 1BX.  This form is
also available and can be submitted online or downloaded from
www.eplanning.scotland.gov.uk
If permission to develop land is refused or granted subject to conditions and the
owner of the land claims that the land has become incapable of reasonably
beneficial use in its existing state and cannot be rendered capable of reasonably
beneficial use by the carrying out of any development which has been or would be
permitted, the owner of the land may serve on the planning authority a purchase
notice requiring the purchase of the owner of the land’s interest in the land in
accordance with Part 5 of the Town and Country Planning (Scotland) Act 1997.
Page 139

Page 142

Page 140

Page 143

APPENDIX 2 
NOTICE OF REVIEW,
GROUNDS FOR REVIEW &
SUPPORTING DOCUMENTS
Page 141

Page 144

Page 142

Page 145

Page 1 of 4
The Moray Council Council Office High Street Elgin IV30 1BX  Tel: 0300 1234561  Email: development.control@moray.gov.uk
Applications cannot be validated until all the necessary documentation has been submitted and the required fee has been paid.
Thank you for completing this application form:
ONLINE REFERENCE 100624748-001
The online reference is the unique reference for your online form only. The  Planning Authority will allocate an Application Number when
your form is validated. Please quote this reference if you need to contact the planning Authority about this application.
Applicant or Agent Details
Are you an applicant or an agent? * (An agent is an architect, consultant or someone else acting
on behalf of the applicant in connection with this application)  Applicant  Agent
Applicant Details
Please enter Applicant details
Title: You must enter a Building Name or Number, or both: *
Other Title: Building Name:
First Name: * Building Number:
Address 1
Last Name: * (Street): *
Company/Organisation Address 2:
Telephone Number: * Town/City: *
Extension Number: Country: *
Mobile Number: Postcode: *
Fax Number:
Email Address: *
Mr
Michael
Barron Springfield road
94
Iv306yu
Scotland
Elgin
Page 143

Page 146

Page 2 of 4
Site Address Details
Planning Authority:
Full postal address of the site (including postcode where available):
Address 1: 
Address 2:
Address 3:
Address 4:
Address 5:
Town/City/Settlement:
Post Code:
Please identify/describe the location of the site or sites
Northing Easting
Description of Proposal
Please provide a description of your proposal to which your review relates. The description should be the same as given in the
application form, or as amended with the agreement of the planning authority: *
(Max 500 characters)
Type of Application
What type of application did you submit to the planning authority? *
  Application for planning permission (including householder application but excluding application to work minerals).
  Application for planning permission in principle.
  Further application.
  Application for approval of matters specified in conditions.
94 SPRINGFIELD ROAD
retrospective planning for boundary fence 22/01451/APP
Moray Council
ELGIN
IV30 6YU
861385 321513
Page 144

Page 147

Page 3 of 4
What does your review relate to? *
  Refusal Notice.
 Grant of permission with Conditions imposed.
  No decision reached within the prescribed period (two months after validation date or any agreed extension) – deemed refusal.
Statement of reasons for seeking review
You must state in full, why you are a seeking a review of the planning authority’s decision (or failure to make a decision). Your statement
must set out all matters you consider require  to be taken into account in determining your review. If necessary this can be provided as a
separate document in the ‘Supporting Documents’ section: *  (Max 500 characters)
Note: you are unlikely to have a further opportunity to add to your statement of appeal at a later date, so it is essential that you produce
all of the information you want the decision-maker to take into account.
You should not however raise any new matter which was not before the planning authority at the time it decided your application (or at
the time expiry of the period of determination), unless you can demonstrate that the new matter could not have been raised before that
time or that it not being raised before that time is a consequence of exceptional circumstances.
Have you raised any matters which were not before the appointed officer  at the time the  Yes   No
Determination on your application was made? *
If yes, you should explain in the box below, why you are raising the new matter, why it was not raised with the appointed officer before
your application was determined and why you consider it should be considered in your review: * (Max 500 characters)
Please provide a list of all supporting documents, materials and evidence which you wish to submit with your notice of review and intend
to rely on in support of your review. You can attach these documents electronically later in the process: * (Max 500 characters)
Application Details
Please provide the application reference no. given to you by your planning
authority for your previous application.
What date was the application submitted to the planning authority? *
What date was the decision issued by the planning authority? *
reasons for seeking review are uploaded in supporting documents
reasons for seeking review transport managers advised drawing revised plans to fit transport managers drawings
22/01451/APP
12/01/2023
06/10/2022
Page 145

Page 148

Page 4 of 4
Review Procedure
The Local Review Body will decide on the procedure to be used to determine your review and may at any time during the review
process require that further information or representations be made to enable them to determine the review. Further information may be
required by one or a combination of procedures, such as: written submissions; the holding of one or more hearing sessions and/or
inspecting the land which is the subject of the review case.
Can this review continue to a conclusion, in your opinion, based on a review of the relevant information provided by yourself and other
parties only,  without any further procedures? For example, written submission, hearing session, site inspection. *
 Yes   No
In the event that the Local Review Body appointed to consider your application decides to inspect the site, in your opinion:
Can the site be clearly seen from a road or public land? *  Yes   No
Is it possible for the site to be accessed safely and without barriers to entry? *  Yes    No
Checklist – Application for Notice of Review
Please complete the following checklist to make sure  you have provided all the necessary information in support of your appeal. Failure
to submit all this  information may result in your appeal  being deemed invalid.
Have you provided the name and address of the applicant?.  *  Yes   No
Have you provided the date and reference number of the application which is the subject of this  Yes   No
review? *
If you are the agent, acting on behalf of the applicant, have you provided details of your name  Yes   No   N/A
and address and indicated whether any notice or correspondence required in connection with the
review should be sent to you or the applicant? *
Have you provided a statement setting out your reasons for requiring a review and by what  Yes   No
procedure (or combination of procedures) you wish the review to be conducted? *
Note: You must state, in full, why you are seeking a review on your application. Your statement must set out all matters you consider
require to be taken into account in determining your review. You may not have a further opportunity to add to your statement of review
at a later date. It is therefore essential that you submit with your notice of review, all necessary information and evidence that you rely
on and wish the Local Review Body to consider as part of your review.
Please attach a copy of all documents, material and evidence which you intend to rely on  Yes   No
(e.g. plans and Drawings) which are now the subject of this review *
Note: Where the review relates to a further application e.g. renewal of planning permission or modification, variation or removal of a
planning condition or where it relates to an application for approval of matters specified in conditions, it is advisable to provide the
application reference number, approved plans and decision notice (if any) from the earlier consent.
Declare – Notice of Review
I/We the applicant/agent certify that this is an application for review on the grounds stated.
Declaration Name: Mr Michael Barron
Declaration Date: 11/04/2023
Page 146

Page 149

We are seeking review of our recently refused planning application for a 6ft fence at the side of our
house because we believe we have been penalised because someone cannot see into our garden, a
garden which we have made lovely and family friendly for our 5-year-old pet dog and our now 11-
week-old baby. We feel that an appeal allows someone out with the Moray Council Planning
department to review this application and take a nonbiased point of view considering all aspects and
hopefully come up with a solution as to how we can maintain a safe, enclosed, private garden for our
family home. We feel an appeal would help support us in a fair trial as every time we submit
something to the Moray Council it seems to be a different excuse each time and a lack of care and
consideration for what we are trying to do. Most importantly, our reasons for appealing the refusal
are child and pet safety, cleanliness, theft prevention and privacy, none of which have been
considered by the Moray Council Planning Officers. 
The application has been refused twice and, on both occasions, has had a new reason for refusal,
none of which relate to the original letter regarding a 6ft fence at the side of the house. The first
refusal was because the fence did not fit the character of the area and was not deemed safe by the
transport manager as it is on the roadside. The second refusal was again because it did not fit the
character of the area, but the planning officer had also added in that it blocks vision of crime. It has
been frustrating not being able to have someone from the Council come round to the garden and try
and help us keep somewhat of our fence or explain things to us. Covid has continually been used as
an excuse but with all due respect, my wife works as a nurse, and we do not need reminded about
how covid has impacted on our lives. A simple discussion when site visits were taking place could
have been arranged at a two-meter distance in the garden. In reference to the transport manager’s
report – he is the only person at the Council who seemed to consider our privacy and so failed our
current fence but commented with new drawings what he would deem road and path safe therefore
grant permission. We were happy to change the fence to meet the new drawing and so submitted
that on the second application, but it was failed and given another new reason for refusal. Our fence
was erected in 2018 a few months after we moved into the property. We were served a notice to
apply for retrospective planning for the 6ft fence three years later in 2021. The policies – DP1 and
PP3 of the Moray Local Development Plan 2020 in which the planning officers refer to in their reports
are policies which were not in place when the fence was initially erected. With regards to the 2020
policies – why were we asked to apply for retrospective planning and pay a fee if the policies about
character of the area and crime reference were already in place. The planning officer who served the
notice either did not know about these policies suggesting they were not in place until after our
application was submitted or he believed we would get permission for the fence. 
In addition I would also like to add that taking our fence down to 4ft will not make a difference to
viewing crime. We also share a 6ft fence between the neighbouring house which has been in place
since 2017 by choice of both parties therefore there is no vision down to the neighbouring gardens
and this has never been an issue and the neighbours are grateful for the extra bit of privacy. Policy
DP1 2020 refers to the development not adversely impacting neighbouring properties in terms of
privacy, day light and overbearing loss of amenity as quoted by the latest planning officer in her
report. When our neighbours were served with letters about our fence, they did not understand
what the problem was. With regards to loss of amenities we are not sure what amenities our fence
prevents someone from having. Our architect was also of the same opinion. We are not responsible
for reporting crime that happens out with our property boundary. With reference to not fitting the
character of the area, there has been a house extension in the local area where the materials used
have been new and updated models, so it does not match with the surrounding houses in the
Page 147

Page 150

neighbourhood, yet it was passed by planning. There are several properties in the local area with 6ft
fencing on the roadside and blocking vision round paths, in particular Dornoch Links, Elgin – the path
coming from the street onto the fast Elgin – Birnie Road with no vision round the corner but this was
passed by planning.  We have gone from initially being informed that planning is required for a 6ft
fence at the side of the house to being told that the fence at the back blocks vision round the path to
then the front driveway restricting view to then the fence being out of character and now the fence
blocks vision of crime. Having a 4ft fence would allow a police officer to look further round the
corner onto the path but from a distance they would need to be on the same path to view what
crime they were witnessing, similar for regular pedestrians. 
The review should also consider why the Moray Council planning department only responded to our
many contacts in the beginning because we reported concerns to our Local MSP. The Council have
not been very forthcoming nor supportive in the matter. We were posted a letter and just expected
to take the fence down which we have not and sadly in the process have had no support from the
Council around how we can maintain some of our privacy in our own bought home. There have been
different views and reasons shared by the Council over an initial letter, a phone call and reports but
no direct face to face verbal communication. We have spoken to the local head teacher at the High
School with regards to children during school hours who have accessed our garden for no good
reason, littering, trying to feed our dog and on one occasion damage to the property by a school
child. We also spoke with Police Scotland about items missing from the garden when we initially
moved in and were told that there is minimal, they can do because it is open to opportunists with a
4ft fence. We previously wrote and discussed the issues with the lack of communication from The
Moray Council to Richard Lochhead and have again contacted him with regards to this matter. 
The removal of the 6ft fence down to a 4ft fence would cause child safety and road safety issues due
to problems we occurred with the 4ft fence we had when moving into the property where people
would purposely open our gate resulting in our dog being able to escape from the garden. There was
also the road safety factor of my autistic nephew who would regularly climb over the 4ft fence due to
lack of understanding of road safety.
Page 148

Page 151

S
P
R
IN
G
F
IE
L
D
R
O
A
D
16
2
94
86
98
92
0
50
10
El Sub
Sta
M
A
N
N
O
C
H
C
O
U
R
T
H
E
L
D
O
N
P
L
A
C
E
S
P
R
IN
G
F
IE
L
D
R
O
A
D
10
102
1062
1621
13
2
8
1113
10
23
Play
Area
H
E
L
D
O
N
P
L
A
C
E
K
IR
K
T
O
N
P
L
A
C
E
PH
1
24
2
8
4
94
86
74
98
92
84
25
27
13
19
15
0
100
20
50
Drawing
No. 1
SITE
PLAN
1-500
Site
Area
- 300m
2
(outlined
in
Red)
LOCATION
PLAN
1-1250
Retrospective
Planning
Application,
Fence
Erected
to
side
of House,
94
Springfield
Road,
Elgin,
IV30
6YU.
Mr M. Barron
New
fence -
100mm
wide x 20mm
thick fencing boards with
20mm
gaps between boards. Colour - dark brown
Fence kept clear of visibility splays.
900mm
high
900mm
high
ELEVATION
FROM
SPRINGFIELD
ROAD
1-100
Site
area
outlined
in
red
new
fence
shown
in
green
2.4x5.0m
visibility
splays
noted
in
blue
fence
line
behind
visibility
splay
fence
height to
be
900m
m
at
visibility
splay
Rev
A
- Fence
line
at RHS
am
ended, Fence height at LHS
lowered. Jan
'22
Page 149

Page 152

Page 150

Page 153

APPENDIX 3 
RESPONSE TO REQUEST FOR
FURTHER INFORMATION
Page 151

Page 154

1
Lissa Rowan
Subject: RE: 22/01451/APP - 94 Springfield Road Elgin
From: Fiona Olsen <Fiona.Olsen@moray.gov.uk> 
Sent: 13 April 2023 10:44
To: Lissa Rowan <Lissa.Rowan@moray.gov.uk>
Cc: Beverly Smith <Beverly.Smith@moray.gov.uk>
Subject: RE: 22/01451/APP - 94 Springfield Road Elgin 
Hi Lissa, 
Happy that no new information is presented. 
NPF4 Comments: 
National Planning Framework 4 (NPF4) was adopted by the Scottish Ministers on 13th February 2023, following
approval by the Scottish Parliament in January. The basic siting and design principles for householder developments
continue to apply within NPF4 Policy 16(g). 