Housing and Community Safety Committee 
Tuesday, 21 June 2022 
NOTICE IS HEREBY GIVEN that a Meeting of the Housing and Community Safety
Committee is to be held at Council Chambers, Council Office, High Street, Elgin,
IV30 1BX on Tuesday, 21 June 2022 at 14:00. 
BUSINESS 
1. Sederunt 
2. Declaration of Group Decisions and Members Interests * 
3. Resolution
Consider, and if so decide, adopt the following resolution:
"That under Section 50A (4) and (5) of the Local Government
(Scotland) Act 1973, as amended, the public and media
representatives be excluded from the meeting for Items 12 and 13 of
business on the grounds that it involves the likely disclosure of exempt
information of the class described in the relevant Paragraphs of Part 1
of Schedule 7A of the Act.”   
4. Minute of the Meeting of 22 March 2022 7 - 10
5. Written Questions ** 
6. Housing and Property Services - Unaudited Outturn as
at 31 March 2022
Report by Depute Chief Executive (Economy, Environment and
Finance)   
11 - 20
7. Local Housing Strategy 2019 - 2024 Mid Term Review
Report by Depute Chief Executive (Economy, Environment and
Finance)  
21 - 30
Page 1

Page 2

8. Housing Investment 2021-22
Report by Depute Chief Executive (Economy, Environment and
Finance)   
31 - 48
9. Allocations Policy Annual Performance Report 2021-22
Report by Depute Chief Executive (Economy, Environment and
Finance)  
49 - 58
10. Performance Report (Housing and Property Services) -
Period to March 2022
Report by Depute Chief Executive (Economy, Environment and
Finance)   
59 - 68
11. Question Time ***
Consider any oral question on matters delegated to the Committee in
terms of the Council's Scheme of Administration. 
Item(s) which the Committee may wish to consider with
the Press and Public excluded   
12. Decommissioning of Temporary Homeless
Accommodation
• Information relating to any particular occupier or former occupier of,
or applicant for, accommodation provided by or at the expense of
the Authority;
• Information relating to staffing matters; 
13. Building Services Trading Operation Budget 2021-22 -
Budget Monitoring
• Information on terms proposed or to be proposed by or to the
Authority; 
Summary of the Housing and Community Safety
Committee functions:
To deal with matters relating to Housing/HMOs, Housing Regeneration,
Homelessness, Social Inclusion, Equalities, Community Safety, Anti-
Social Behaviour (including road accidents) and Community Liaison.     
Page 2

Page 3

Any person wishing to attend the meeting should contact customer services
on 01343 563217 prior to the meeting as the number of attendees is restricted
due to the recent Covid pandemic 
You can however watch the webcast of the meeting by going to :
http://www.moray.gov.uk/moray_standard/page_43661.html 
Page 3

Page 4

GUIDANCE NOTES 
* Declaration of Group Decisions and Members Interests - The Chair of the
meeting shall seek declarations from any individual or political group at the
beginning of a meeting whether any prior decision has been reached on how
the individual or members of the group will vote on any item(s) of business on
the Agenda, and if so on which item(s).  A prior decision shall be one that the
individual or the group deems to be mandatory on the individual or the group
members such that the individual or the group members will be subject to
sanctions should they not vote in accordance with the prior decision.  Any such
prior decisions will be recorded in the Minute of the meeting. 
** Written Questions - Any Member can put one written question about any
relevant and competent business within the specified remits not already on the
agenda, to the Chair provided it is received by the Proper Officer or Committee
Services by 12 noon two working days prior to the day of the meeting.  A copy
of any written answer provided by the Chair will be tabled at the start of the
relevant section of the meeting.  The Member who has put the question may,
after the answer has been given, ask one supplementary question directly
related to the subject matter, but no discussion will be allowed. 
No supplementary question can be put or answered more than 10 minutes after
the Council has started on the relevant item of business, except with the
consent of the Chair. If a Member does not have the opportunity to put a
supplementary question because no time remains, then he or she can submit it
in writing to the Proper Officer who will arrange for a written answer to be
provided within 7 working days. 
*** Question Time - At each ordinary meeting of the Committee ten minutes will be
allowed for Members questions when any Member of the Committee can put a
question to the Chair on any business within the remit of that Section of the
Committee.  The Member who has put the question may, after the answer has
been given, ask one supplementary question directly related to the subject
matter, but no discussion will be allowed. 
No supplementary question can be put or answered more than ten minutes
after the Committee has started on the relevant item of business, except with
the consent of the Chair.  If a Member does not have the opportunity to put a
supplementary question because no time remains, then he/she can submit it in
writing to the proper officer who will arrange for a written answer to be provided
within seven working days. 
Page 4

Page 5

THE MORAY COUNCIL 
Housing and Community Safety Committee 
SEDERUNT 
Councillor Amber Dunbar  (Chair)
Councillor Donald Gatt  (Depute Chair)  
Councillor James  Allan  (Member)
Councillor Theresa Coull  (Member)
Councillor John Divers  (Member)
Councillor Jérémie Fernandes  (Member)
Councillor David Gordon  (Member)
Councillor Sandy Keith  (Member)
Councillor Scott Lawrence  (Member)
Councillor Paul McBain  (Member)
Councillor Shona Morrison  (Member)
Councillor Bridget Mustard  (Member)
Councillor Derek Ross  (Member)  
Ms Anna Bamforth  (Non-Voting Member)
Ms Jane Bartecki  (Non-Voting Member)
Mr Ronald Tolmie  (Non-Voting Member)
Clerk Name: Lindsey Robinson
Clerk Telephone: 07966 120593
Clerk Email: committee.services@moray.gov.uk 
Page 5

Page 6

Page 6

Page 7

MORAY COUNCIL 
Minute of Meeting of the Housing and Community Safety Committee 
Tuesday, 22 March 2022 
Various Locations via Video-Conference 
PRESENT 
Councillor George Alexander, Councillor James  Allan, Councillor Theresa Coull,
Councillor Lorna Creswell, Councillor John Divers, Councillor Donald Gatt, Councillor
Marc Macrae, Councillor Aaron McLean, Councillor Louise Nicol, Councillor Laura
Powell, Councillor Derek Ross 
APOLOGIES 
Ms Anna Bamforth, Ms Jane Bartecki, Councillor David Bremner, Councillor Ryan
Edwards, Councillor Maria McLean, Mr Ronald Tolmie 
IN ATTENDANCE 
Head of Housing and Property Services, Acting Housing Strategy and Development
Manager, Building Services Manager, Legal Services Manager and Mrs L Rowan,
Committee Services Officer as Clerk to the Committee. 
1         Chair 
Councillor Nicol, being chair of the Housing and Community Safety Committee,
chaired the meeting.   
2         Acknowledgements 
The Chair acknowledged that this was the last meeting of the Housing and
Community Safety Committee prior to the constitution of the new Council in May
2022 and thanked the Committee and Officers for their input over the last 5 years.   
3         Declaration of Group Decisions and Members Interests 
In terms of Standing Order 20 and the Councillors’ Code of Conduct, there were no
declarations from Group Leaders or Spokespersons in regard to any prior
decisions taken on how Members will vote on any item on the agenda.  
Councillor Divers declared an interested in Item 10 “Council New Build – Report on
Tender – South Glassgreen Fyvie Green, Elgin” as his son is an employee of the
Developer.  There were no further declarations of Member’s interests in respect of
any item on the agenda. 
4         Resolution 
Item 4.
Page 7

Page 8

The Meeting resolved that under Section 50A (4) and (5) of the Local Government
(Scotland) Act 1973, as amended, the public and media representatives be
excluded from the meeting for Item 13 of business on the grounds that it involves
the likely disclosure of exempt information of the class described in the relevant
Paragraphs of Part 1 of Schedule 7A of the Act. 
Paragraph Number of Minute  Paragraph Number of Schedule 7a and Reason
11, 12 and 13    9 
5         Minute of Meeting dated 8 February 2022 
The minute of the meeting of the Housing and Community Safety Committee dated
8 February 2022 was submitted and approved.   
6         Written Questions 
The Committee noted that no written questions had been submitted.   
7         Housing and Property Services Service Plan 2022-23 
Councillor A McLean joined the meeting during discussion of this item.  
Under reference to paragraph 14 of the Minute of the meeting of Moray Council
dated 19 January 2022, a report by the Depute Chief Executive (Economy,
Environment and Finance) invited the Committee to consider the Housing and
Property Services Service Plan for 2022-23.  
Following consideration, the Committee agreed to approve the Service Plan for
Housing and Property Services as set out in Appendix 1 of the report.   
8         Housing Investment 2021-22 
A report by the Depute Chief Executive (Economy, Environment and Finance)
informed the Committee of the budget position to 31 December 2021 for the
Housing Investment Programme for 2021/22.  
Following consideration, the Committee agreed:
1. the position as at 31 December 2021 with regards to the Housing Investment
Programme for 2021/22, as detailed in Section 3 and Appendices I to VI of the
report; and 
2. the revised Housing Investment Programme projected outturn to 31 March
2022, as detailed in Section 3 and Appendices I to VI of the report.    
9         Housing and Property Services Budget Monitoring - 31 December 2021 
Under reference to paragraph 5 of the Minute of the meeting of Moray Council
dated 22 February 2022, a report by the Depute Chief Executive (Economy,
Environment and Finance) presented the budget position for the Housing Revenue
Page 8

Page 9

Account (HRA) and General Services Other Housing Budget for the period up to
31 December 2021.  
Following consideration the Committee agreed: 
1. to note the budget monitoring report for the period to 31 December 2021; and 
2. the service developments of £47,799 as detailed within paragraph 8.4 of the
report.   
10         Question Time 
Councillor A McLean sought clarification as to where tenants should seek advice in
relation to energy efficiency and support with the rising cost of living and asked if
this information could be displayed on the Council’s social media platforms.  
In response, the Head of Housing and Property Services advised that this
information would be highlighted through the Housing Newsletter.  
Councillor A McLean further thanked Mrs Matheson, Benefits and Money Advice
Manager and her team for their continued work in providing an excellent service.   
11         Council New Build - Report on Tender - South Glassgreen Fyvie
Green, Elgin [Para 9] 
Councillor Divers, having declared an interest in this item, took no part in its
consideration or decision.  
Under reference to paragraph 14 of the Minute of the meeting of Moray Council
dated 23 February 2022, a report by the Depute Chief Executive (Economy,
Environment and Finance) presented an evaluation of the tender received from the
Council New Build Programme Phase 9 project at South Glassgreen/Fyvie Green,
Elgin.  
During discussion surrounding encouraging communities to grow their own food, it
was queried whether gardens in Council new build houses could be provided with
at least 1ft of top soil so that tenants can grow their own food.  
In response, the Acting Housing Strategy and Development Manager advised that
consideration would be given to amending the design guide to reflect that at least
1ft of topsoil is provided for tenants wishing to grow their own food.  
Thereafter, the Committee agreed:
1. to accept the tender received from Springfield Properties PLC for South
Glassgreen/Fyvie Green, Elgin; 
2. to note that progress on the delivery of the Council’s new build programme will
be reported to a future meeting of this Committee; and 
3. that consideration would be given to amending the design guide to reflect that
at least 1ft of topsoil is provided for tenants wishing to grow their own food.    
Page 9

Page 10

12         Council New Build Tender - Bilbohall, Elgin Phase 1 [Para 9] 
Councillor Divers re-joined the meeting at this juncture.  
Under reference to paragraph 8 of the Minute of the meeting of the Housing and
Community Safety Committee dated 7 December 2021, a report by the Depute
Chief Executive (Economy, Environment and Finance) presented an update of the
tender for the Council New Build Programme Phase 9 project at Blbohall, Elgin.  
Following consideration, the Committee agreed:
1. to grant the Head of Housing and Property delegated authority to accept the
most advantageous tender for construction; 
2. the financial implications of including passivhaus features within the housing
specification; and 
3. to note that progress on the delivery of the Council’s new build programme will
be reported to a future meeting of this Committee.    
13         Building Services Trading Operation Budget 2021-22 - Budget
Monitoring [Para 9] 
A report by the Depute Chief Executive (Economy, Environment and Finance)
presented the budget monitoring information for the period to 31 December 2021
for the Building Services Trading Operation.  
Following consideration, the Committee agreed to note:  
1. the financial information for the period to 31 December 2021, as detailed in
section 5 and Appendix I of the report; 
2. Building Services operating performance for the period to 31 December 2021,
as set out in section 6 of the report; and 
3. the revised projected outturn to 31 March 2022, as detailed in section 7 and
Appendix I of the report.     
Page 10

Page 11

REPORT TO:  HOUSING AND COMMUNITY SAFETY COMMITTEE ON 21 JUNE
2022 
SUBJECT: HOUSING AND PROPERTY SERVICES – UNAUDITED OUTTURN
AS AT 31 MARCH 2022 
BY:  DEPUTE CHIEF EXECUTIVE (ECONOMY, ENVIRONMENT AND
FINANCE) 
1. REASON FOR REPORT 
1.1 This report presents the unaudited outturn position for the Housing Revenue
Account (HRA) and General Services Other Housing Budget for the period up
to 31 March 2022. 
1.2 This report is submitted to Committee in terms of Section III G (1) of the
Council's Scheme of Administration relating to the management of budgets. 
2. RECOMMENDATION 
2.1 It is recommended that the Committee considers and notes the
unaudited outturn for 2021/22 for the period to 31 March 2022. 
3. BACKGROUND 
3.1 The Council agreed the HRA Budget for 2022/23 at a Moray Council meeting
on 22 February 2022 (paragraph 5 of the Minute refers). Housing and
Property budget monitoring reports are presented quarterly. 
3.2 The COVID-19 pandemic and subsequent lockdown period has impacted on
the budget spend as the service has sought to recover from the impact of
restrictions. 
4. HOUSING REVENUE ACCOUNT TO 31 MARCH 2022 
4.1 APPENDIX I details the provisional and unaudited HRA budget position to 31
March 2022. 
4.2 The main expenditure variances relate to:– 
Item 6.
Page 11

Page 12

4.2.1 Supervision and management – there are a range of variations within this
budget resulting in a net underspend of £43k. The main underspends were in
staffing (£85k), due to unfilled vacancies, central support services/shared
accommodation (£75k) and insurance (17k). These were partially offset by an
overspend in voids (£103k), due to the increased level of recovery activity,
pool car recharges (£23k) and other minor overspends (£8k). 
4.2.2 Sheltered Housing – there was an overspend of £5k arising from energy,
repairs & maintenance costs. 
4.2.3 Repairs and maintenance – there was an underspend of £277k net in the
repairs and maintenance budgets, which comprised of planned/cyclical
(£823k) and the DLO surplus return (£46k – estimated at this stage). The
planned/cyclical underspend was due to reduced output in insulation
programmes being undertaken due to pandemic impact and market conditions
(£562k), roof and fabric repairs (£238k), asbestos works (£118k) and
rainwater goods (£80k). An overspend in disabled adaptations of £349k arose
due to having been budgeted under capital spend, but moved to revenue
following a review of the nature of the expenditure, with many of the
adaptations being minor works.  The cumulative underspends were partially
offset by overspends in response repairs (£377k, with £171k relating to
damage caused by Storm Arwen) and voids (£215k). 
4.2.4 Financing Costs – there was an overspend of £418k due to the higher than
anticipated cost of borrowing following interest rate increases. 
4.2.5 Bad and doubtful debts – there was an underspend of £79k, arising from
lower write-offs and following a previous increase in bad debt provision. 
4.2.6 CFCR – There was an underspend of £47k based on the estimated balancing
figure to maintain level of HRA reserves. 
4.2.7 Downsizing Incentive Scheme – there was an underspend of £28k with
fewer transfers than expected completed during the year, with a number of
moves suspended due to COVID-19 and prioritisation of lets to homeless
households in line with Scottish Government guidance. 
4.2.8 Service Developments – there was an underspend of £58k arising from a
vacanct post and the later commissioning of the Housing Need and Demand
Assessment.  
4.2.9 The income at 31 March 2022 was £61k lower than expected.  This is due
mainly to revenue from new build housing in Keith being delayed due to
restriction of works and fewer reactive repairs invoiced to tenants at the year
end, partially offset by  higher income from interest on revenue balances due
to increased interest rates. 
4.2.10 The estimated HRA surplus at 31 March 2022 was £48k, increasing the HRA
balance to £2.449m. This compares with a projected outturn at Q3 of
£2.401m. 
Page 12

Page 13

5 OTHER HOUSING BUDGET 
5.1 APPENDIX II provides details of the provisional and unaudited budget position
to 31 March 2022. 
5.2 Planning and Development consists of Improvement Grants and Affordable
Housing budgets.  There was an overspend of £3k arising from a shortfall in
grant income against budgeted target (£68k). This was partially offset by and
underspend in discretionary grants and admin costs (£65k). Discretionary
grants are given to homeowners for disabled adaptations with this budget
managed by the Moray Integration Joint Board.   
5.3 Housing Management relates to the Gypsy/Traveller budget. This shows an
underspend of £11k due to reduced staffing expenditure (£9k) and reduced
expenditure on supplies and services (£2k). 
5.4 Homelessness/Allocations comprises of Homelessness and Housing Support
services. There were variations across a range of budgets within this heading
resulting in an overspend of £41k in this budget. This is comprised of an
overspend of £5k in Housing Support, mainly due to sheltered housing staff
costs and an overspend of £217k in temporary accommodation budgets, mainly
due to additional repairs and furniture costs (£76k), loss of income due to
arrears/voids (£71k), storage and low occupancy rates at a property which is
being considered for closure in 2022/23. These were partially offset by an
underspend of £181k in other Homelessness budgets, predominantly £190k
against the rapid rehousing transition plan due to delays in implementing
Housing First on account of recruitment challenges, which is ear-marked
Scottish Government funding which will therefore be carried forward. 
5.5 Miscellaneous General Services Housing comprises of House Loans and the
complex needs development at Urquhart Place, Lhanbryde.  There was an
underspend of £30k across these three budgets.  The main reason for this was
lower than anticipated repairs and maintenance costs relating to Urquhart Place
(£36k), supplemented by an underspend in mortgage repayments (1k); these
underspends were partially offset by an overspend in grounds maintenance
(£7k), which had been funded by a now exhausted maintenance bond with an
RSL. 
5.6 The Building Services Budget is reported in detail separately on this
Committee’s agenda. Whilst not finalised a modest £5k underspend is
anticipated at this point. 
5.7 The Property Services Budget includes the budgets for the Design and
Property Resources. There was an underspend of £428k at year end, arising
primarily from lower administrative and management costs (£153k), lower
central repairs and maintenance charges (£146k), increased rental
income/lower costs in industrial estates (£121k) and other miscellany (£21k).
This cumulative underspend of £441k in Property Resources was partially offset
by a £17k overspend in Design, predominantly due to software costs. 
5.8 Housing and Property Savings – Staffing savings (£19k) above target were
achieved by year end. These savings arose mainly to due to unfilled vacancies.
Page 13

Page 14

5.9 Housing and Property Allocations – there was an overspend (£28k) primarily
due to less income than budgeted for shared building service recharges.  This
budget will be reviewed in 2022/23. 
5.10 COVID-19 – there was a service underspend of £33k attributable to the Tenant
Hardship Fund balance being carried forward (£39k) as ear-marked reserves-
and an overspend of £6k due to building reconfiguration costs.   
5.11 As at 31 March 2022, the Other Housing Budget shows an unaudited net
underspend of £454k.   
6 SUMMARY OF IMPLICATIONS 
(a) Corporate Plan and 10 Year Plan (Local Outcomes Improvement
Plan (LOIP))
The provision of new affordable housing, the maintenance of the
Council’s housing stock and dealing with homelessness are priorities
identified within the Corporate Plan, the Council’s Local Housing
Strategy, the Strategic Housing Investment Plan (SHIP) and the Housing
and Property Service Plan. 
(b) Policy and Legal
There are no policy or legal implications arising from this report. 
(c) Financial Implications
The financial implications of this report are considered in Sections 4 and
5 of this report and detailed in APPENDICES I and II. 
(d) Risk Implications
Budget Managers are aware of their responsibilities for managing budget
allocations and approval for variance will be sought from the Committee
in line with Financial Regulations. 
(e) Staffing implications
None. 
(f) Property
None. 
(g) Equalities/Socio Economic Impact
There are no equalities/socio economic impacts arising from this report. 
(h) Climate Change and Biodiversity Impacts 
There are no climate change/biodiversity impacts arising from this report. 
(i) Consultations 
This report has been prepared in close consultation with Finance
staff. Consultation on this report has been carried out with Deborah
O’Shea (Interim Chief Financial Officer Moray Integration Joint
Board), the Legal Services Manager, Senior Managers within
Page 14

Page 15

Housing and Property Services and Lindsey Robinson (Committee
Services Officer) who all agree the content of the report where it
relates to their area of responsibility. 
7 CONCLUSION 
7.1 This report sets out the provisional and unaudited budget position for
the HRA and General Services Housing budgets to 31 March 2022 and
also comments on the variances on these budgets. 
Author of Report: Edward Thomas, Head of Housing and Property Services
Background Papers:   Held by author
Ref:    SPMAN-1285234812-1086
Page 15

Page 16

Page 16

Page 17

Housing Revenue Account    Appendix I    
Budget Monitoring to 31st March 2022   
Service Description Annual Budget
2021-22
Actual to 31
March 2022
Variance to
31 March
2022
Expenditure £,000 £,000 £,000
Supervision & Management 4,297 4,254 43
Sheltered Housing 22 27 (5)
Repairs and Maintenance 7,678 7,401 277
Financing Costs 3,880 4,298 (418)
Bad & Doubtful Debts 225 146 79
CFCR 4,910 4,863 47
Downsizing Incentive Scheme 72 44 28
Service Development 119 61 58
Total Gross Expenditure 21,203 21,094 109        
Income £,000 £,000 £,000
Non-dwelling rents 229 228 (1)
House rents 20,880 20,847 (33)
IORB 4 26 22
Other income 90 41 (49)
Total Income 21,203 21,142 (61)        
Surplus / (Deficit) for the year 0 48 48        
Accumulated Surplus Balance brought
forward   2,401          
Estimated Surplus Balance at 31 March
2022   2,449   
Item 6.
Page 17

Page 18

Page 18

Page 19

General Services Housing & Property  Appendix II    
Monitoring to 31st March 2022   
Annual Actual Variance
Service Description Budget to at   
2021-22 31 March
2022
31 March
2022    
£'000 £'000 £'000
Planning & Development 251 254 (3)          
Housing Management 18 7 11          
Homelessness / Allocations 2250 2291 (41)          
Miscellaneous General Services
Housing (20) (50) 30          
Building Services                          -  (5) 5          
Property Services 915 487 428          
General Services Housing & Property
Savings 19 0 19          
General Services Housing & Property
Allocations (161) (133) (28)        
Covid 19 - GS Housing & Property   87 54 33          
General Services Housing & Property
Total  3359 2905 454 
Item 6.
Page 19

Page 20

Page 20

Page 21

REPORT TO: HOUSING AND COMMUNITY SAFETY COMMITTEE ON 21 JUNE
2022 
SUBJECT: LOCAL HOUSING STRATEGY 2019-2024 MID TERM REVIEW 
BY:  DEPUTE CHIEF EXECUTIVE (ECONOMY, ENVIRONMENT AND
FINANCE) 
1. REASON FOR REPORT 
1.1 To inform the Committee of progress made in achieving the outcomes of the
Local Housing Strategy 2019-2024 and of progress made with the
development of the next Housing Need and Demand Assessment. 
1.2 This report is submitted to Committee in terms of Section III G (11) of the
Council's Scheme of Administration relating to the preparation and
implementation of strategic housing plans. 
2. RECOMMENDATION 
2.1 It is recommended that the Committee: 
(i) considers and notes progress made on the outcomes of the Local
Housing Strategy 2019-2024; 
(ii) considers and approves the Local Housing Strategy Action Plan
2022/23 - 2023/24; 
(iii) consider and note progress made on development of the next
Housing Need and Demand Assessment (HNDA); and 
(iv) agrees the service developments of £46k per annum detailed at
paragraph 5.3. 
3. BACKGROUND 
3.1 The Housing (Scotland) Act 2001 requires local authorities to produce a Local
Housing Strategy (LHS) supported by an assessment of housing need and
demand. 
3.2 The LHS was approved by Communities Committee on 2 April 2019 and is
available on the Council’s website at
http://www.moray.gov.uk/moray_standard/page_1917.html
Item 7.
Page 21

Page 22

3.3 Due to COVID-19, annual reporting has not been completed but progress
against targets has been reported regularly as part of the Service Plan.  This
is a mid-term review of the LHS based on the Action Plan for 2019/20, along
with an updated Action Plan for 2022-24 for consideration and approval
(APPENDIX I).  Due to COVID-19 and the need to reprioritise workloads,
some LHS Actions have been continued into the new Action Plan. 
3.4 The priorities the LHS set out to achieve are: 
Priority 1: To improve access to housing across all tenures and address
housing need
Priority 2: To prevent and alleviate homelessness
Priority 3: To assist people requiring specialist housing
Priority 4: To improve the condition and energy efficiency of housing, and
minimise fuel poverty 
3.5 On 16 February 2021, the Economic Growth, Housing and Environmental
Sustainability Committee were advised that, following consultation with the
Moray Tenants’ Forum and Scottish Housing Regulator, the review of the
Tenant Participation Strategy would be delayed until 2022/23 but would
commence at the earliest opportunity (paragraph 11 of the Minute refers). 
3.6 On 8 February 2022, the findings of the 2021 Tenant Survey along with a
Tenant Survey Improvement Plan were presented to Housing and Community
Safety Committee (paragraph 8 of the Minute refers).   
4. PROGRESS ON LHS ACTIONS 
LHS Priority 1:  To improve access to housing across all tenures and
address housing need 
New Build affordable housing
4.1 Since April 2019, 320 new affordable homes have been completed and 
occupied, with a further 126 expected during 2022/23, illustrated in the table
below: 
Compl
Year Landlord Buckie
HMA
Elgin
HMA
Forres
HMA
Keith
HMA
Speyside
HMA Total
2019/20 Moray Council 28     28
Hanover HA  46    46
2020/21 Moray Council  102    102
2021/22
Moray Council  46    46
Cairn HA  16    16
Hanover HA 31 41    72
Osprey Housing  10    10
2022/23
Moray Council    33  33
Cairn HA  28 28   56
Grampian HA   37   37
Total 59 289 65 33 0 446
13.2% 64.8% 14.6% 7.4% 0% 100% 
Page 22

Page 23

4.2 Progress on the Moray Affordable Housing Programme is reported to 
Committee twice a year, most recently in December 2021 (Paragraph 9 of 
minute refers).   
Moray Council’s Allocations Policy
4.3  The operation of the Council’s Allocations Policy is reported to Committee 
annually, with Housing List quotas reviewed and agreed each time.  The last 
report was considered by Economic Growth, Housing and Environmental 
Sustainability Committee on 8 June 2021.  There is an upward trend in the 
relet rate of Council housing following implementation of the Allocations Policy 
in May 2019, which is positive as the increased availability of permanent 
housing options assists the Council to deliver its Rapid Rehousing Transition 
Plan (RRTP) (see Para 4.2.1 below).   
4.4 During 2022/23, work will begin on a revised Allocations Policy, using current 
good practice and the findings of the Housing Need and Demand Assessment 
(see Section 5 below) with the aim of implementing a new Policy during 2024. 
Downsizing Incentive Scheme
4.5 The scheme’s activity has been impacted by COVID-19, through the cessation 
of house moves and also the reluctance of some households to consider 
moving, especially those in shielding groups.  Despite these obstacles the 
numbers of tenancies created under the Downsizing Scheme are: 
Year No of new tenancies
2019/20 22
2020/21 14
2021/22 19
Total 55 
Officers anticipate that the numbers of tenancies created through the
Downsizing Incentive Scheme will return to pre-COVID levels during 2022/23.    
LHS Priority 2:  To prevent and alleviate homelessness 
Rapid Rehousing Transition Plan review
4.6   The Rapid Rehousing Transition Plan (RRTP) is currently being reviewed and 
will be submitted to the Scottish Government by the end of June 2022. 
Officers intend to update Committee on the RRTP during summer/autumn 
2022. 
4.7 At 31 March 2022, 99 units of temporary accommodation were in occupation,
with zero B&B in use.  We are also on course to achieve a further 10 unit 
reduction during 2022. This is a significant achievement as the majority of 
other local authorities have seen a rise in the use of temporary 
accommodation. 
4.8 A report detailing the operation of the Council’s Allocations Policy, including 
allocations to homeless households, is elsewhere on this agenda.     
Development of Housing First
4.9       In common with many other support and health and social care providers, 
recruitment of appropriately skilled housing support workers has been
Page 23

Page 24

challenging and has been an obstacle to progress.  Two Housing Support 
worker posts have recently been recruited through secondment.  Officers 
anticipate that the first Housing First tenancies will start during summer 2022. 
LHS Priority 3:  To assist people requiring specialist housing 
4.10 During the LHS term to date i.e. since April 2019, the aim to provide 30-40% 
of new building affordable housing as specialist/amenity housing through the 
Strategic Housing Investment Plan has been achieved, as illustrated in the 
table below: 
Compl
Year
Land
lord
1 bed
gen
needs
2 Bed
Amenity
2 Bed
Gen
needs
2
Bed
WC
3 Bed
Amenity
3 Bed
Gen
needs
4+
Bed
Gen
needs
4
Bed
WC
Extra
care Total
2019/20
Moray
Council 8   2 1 6 11   28
Hanover
HA  14     1  31 46
2020/21 Moray
Council 32 32  2 2 18 15 1  102
2021/22
Moray
Council 12 8 6   18 2   46
Cairn HA 14     2    16
Hanover
HA 22 11  1 5 19 14   72
Osprey
Housing 4     6    10
2022/23
Moray
Council 16 14   1 2    33
Cairn HA 8 20 12   10 6   56
Grampian
HA 8 14 8 1 1  5   37
Total 124 113 26 6 10 81 54 1 31 446
27.8% 25.3% 5.8% 1.3% 2.2% 18.2% 12.1% 0.2% 7.0% 100% 
Housing for people with learning disabilities
4.11 Officers continue to work proactively in partnership with Health and Social 
Care Moray and NHS Grampian in the delivery of additional specialist housing 
with support for people with learning disabilities.  Provision has already been 
made at Highland Yard, Buckie and Spynie, Elgin.  Further provision is 
planned at Garmouth Road, Lhanbryde and Pinegrove, Elgin.  The planning 
consent at Bilbohall, Elgin granted in March 2021 includes a “care village” 
which will make provision for this group in Phase 2 of development. 
LHS Priority 4:  To improve the condition and energy efficiency of
housing, and minimise fuel poverty 
EESSH/EESSH2
4.12 Moray Council’s progress on compliance with the Energy Efficiency Standard 
in Social Housing (EESSH) is behind schedule and we must comply with 
EESSH2 by 2032.  A large scale stock condition survey was completed in 
March 2021.  This detailed information has provided Officers with the base to 
begin to develop an Investment Plan which will ensure EESSH2 is achieved. 
Energy Efficient Scotland Area Based Scheme (EES:ABS)
4.13 The Council has been administering the Scottish Government’s EES:ABS 
(formerly HEEPS:ABS) funding since the fund’s inception 9 years ago. The
Page 24

Page 25

Council receives an annual allocation of funding from the Scottish 
Government for provision of “grant in kind” via EES:ABS to private owners, 
with a focus on the alleviation of fuel poverty.   
4.14 During the term of the LHS, 228 properties have been improved under the 
scheme, in locations right across Moray. 
Year Tenure
Internal
Wall
Insulation
Cavity
Wall
Insulation
Loft
insulation
Under
floor
Insulation
Total
2019/20 Council owned 25 21 1 1 48
Private sector 70    70
2020/21 Council owned 10    10
Private sector 97  3  100
Total 202 21 4 1 228 
4.15 The Scheme is now managed by Changeworks as the Council’s contractor, 
and offers insulation improvements targeted to households who meet 
qualifying criteria.  The criteria are published on the Council’s website at 
http://www.moray.gov.uk/moray_standard/page_132310.html. The EES:ABS 
scheme is reported to Committee annually, most recently on 7 December 
2021 (paragraph 8 of Minute refers). 
4.16 Energy advice is available to all via Home Energy Scotland (administered by 
SCARF, Aberdeen), but the Council also supports the charity REAP (Rural 
Environmental Action Project) to provide locally based energy advice with the 
added value of home visits to those who need them. 
5 TENANT PARTICIPATION 
5.1   Section 9 of the published LHS refers to Tenant Participation.  The Scottish 
Social Housing Charter sets out the outcomes and standards that all social 
landlords are expected to achieve, which includes publication of a Tenant 
Participation (TP) Strategy and to take account of the views and priorities of 
tenants in shaping services. Moray Council’s Tenant Participation Strategy is 
available at www.moray.gov.uk/tenantparticipation   
5.2 Since the Charter’s introduction in 2012, there have been two significant
performance failures reported to the Scottish Housing Regulator about other
social landlords.  It is notable that both were relating to tenant participation
and both were upheld.   
5.3 The HRA budget set by Moray Council on 22 February 2022 (Paragraph 9 of
Minute refers) included provision for service developments totalling £456k,
which included recruitment of a dedicated Tenant Participation (TP) Officer
and ancillary equipment.  Officers are now seeking approval to recruit to this
new post.  The post-holder will be required to develop and implement a new
Tenant Participation Strategy and ensure compliance with statutory
obligations.  It is expected that this additional resource would have a positive
impact on the areas listed below:   
• The Moray Tenants Forum, the body that represent Moray Council 
Tenants, have been unable to meet as a group since the onset of the
Page 25

Page 26

pandemic.  Current tenant representatives have been unable to attend 
digital meetings, due to tenants’ lack of capacity and facilities.  As a 
result, throughout the pandemic, engagement has taken place on a 
one-to-one basis by telephone and/or by post.  Similarly, the Service 
Improvement Panel has been unable to carry out scrutiny of housing 
services.   
• The 2021 Tenant Survey showed that the main reason for     
dissatisfaction in relation to tenant participation was mainly due to a   
lack of awareness of the opportunities to get involved (45%).  The TP
Officer would be responsible for increasing awareness and    
participation, and for implementing the Improvement Plan.   
•        The TP Officer will be required to innovate to help remove barriers, and
encourage greater diversity amongst participating tenants.   For
example amongst traditionally hard to reach groups such as younger
people, ethnic minorities, people with disabilities or caring
responsibilities and those living in rural areas.   
• Promotion of digital engagement opportunities could fit well with the
Council’s environmental aims in terms of carbon reduction and
reduced costs travelling to meetings etc. 
• The additional resource provided by the TP Officer aligns well with
development of participatory budgeting and community capacity
building. 
• Moray Council was one of 8 social landlords chosen to take part in the
Next Steps Programme, which aims to support landlords to develop
their tenant participation strategies, scrutiny arrangements and
improve their performance against the outcomes and standards of the
Scottish Social Housing Charter.  Moray’s Action Plan was finalised in
2019 but the majority of the recommendations are yet to be
implemented.  The Action Plan identified the Council would benefit
from the appointment of a dedicated Participation Officer. 
• The development of the new Tenant Participation Strategy will be
reported via the Service Plan reporting mechanisms. 
6 HOUSING NEED AND DEMAND ASSESSMENT 2022/23 
6.1 Arneil Johnston have been appointed to complete the next Housing Need and
Demand Assessment (HNDA), following a mini-competition completed with the
support of the Procurement Team.  The work will include primary research
facilitated by Research Resource who recently completed our Tenants Survey. 
This work will progress throughout 2022/23 and the outputs will support the
development of the next Local Development Plan and the next Local Housing
Strategy (LHS).   
7 SUMMARY OF IMPLICATIONS 
(a) Corporate Plan and 10 Year Plan (Local Outcomes Improvement
Plan (LOIP))
Page 26

Page 27

All of the LHS Outcomes are closely aligned with the objectives of the
Corporate Plan and 10 Year Plan. 
(b) Policy and Legal
It is a requirement of the Housing (Scotland) Act 2001 that local
authorities have a Local Housing Strategy.  Detailed guidance has been
produced by the Scottish Government. 
(c) Financial implications
The financial implications are detailed in para 5.2 above and will be a
cost to the Housing Review Account in 2022/23 of £46,264 per annum. 
(d) Risk Implications
Since the Social Housing Charter’s introduction in 2012, there have been
two significant performance failures reported to the Scottish Housing
Regulator about other social landlords.  It is notable that both were
relating to tenant participation and both were upheld.  Therefore there is
a risk that Moray Council would be subject to similar scrutiny from the
Scottish Housing Regulator, mitigated by the recruitment of a TP Officer. 
(e) Staffing Implications
Approval of the service development detailed in paragraph 5.3 will result
in a 1.0 FTE increase in the Housing Management service.  The required
post will go to HR for consultation if approval is granted by the
Committee. 
(f) Property
There are no property requirements/implications arising directly from this
report. 
(g) Equalities/Socio Economic Impact
It is a statutory requirement that equality issues should be addressed in
the LHS.  Data and evidence about the particular housing and support
needs of equality groups was gathered as part of the Council’s Housing
Need and Demand Assessment.  The LHS sets out how the Council
intends to address these needs.  The LHS includes an Equality Impact
Assessment.  Equality groups were consulted as part of the preparation
of the LHS. 
(h) Climate Change and Biodiversity Impacts
The LHS Outcomes and Actions on fuel poverty and energy efficiency
are closely aligned to the Council’s Climate Change Strategy, and Local
Heat and Energy Efficiency Strategy (LHEES). 
(i) Consultations
Consultation on this report has taken place with the Depute Chief
Executive (Economy, Environment and Finance), Head of Housing and
Property, Head of Development Services, Head of Environmental
Services, the Strategic Planning and Development Manager, The Head
of Community Care, the Chief Officer Health and Social Care Moray, the
Chief Financial Officer, Legal Services Manager, Equal Opportunities
Officer, Lindsey Robinson (Committee Services Officer), and senior
managers within Housing and Property Services.
Page 27

Page 28

8 CONCLUSION 
8.1 This report provides the Committee with details of the achievements of 
the Local Housing Strategy 2019-2024 to date, a revised Action Plan for 
its remaining term.  The report provides details of actions already taken 
on development of a Housing Need and Demand Assessment which will 
support the next Local Housing Strategy and Local Development Plan. 
The report seeks approval to recruit a Tenant Participation Officer. 
Author of Report: Fiona Geddes, Acting Housing Strategy and Development
Manager
Background Papers: Held by author
Ref: SPMAN-1285234812-1096 
Page 28

Page 29

Moray Local Housing Strategy 2019-2024 Action Plan 2022/23/24 Appendix I
Responsibility Timescale Status
Moray Council/
RSLs Annual SHIP published annually
Moray Council 2022-24
Moray Council 2023-24
Moray Council/
RSLs Annual RRTP sets Homelessness List quota for 2022/23
at 45% +/-5%
Moray Council 2022/23
Moray Council/
RSLs
Annual
(ARC)
Moray Council 2023-24
Moray Council 2023-24
Moray Council 2019-24 Ongoing
Moray Council ongoing
Moray Council/
RSLs ongoing
Moray Council ongoing
Moray Council 2022-23
Deliver updated Housing Need and Demand Assessment (2022/23 based)
Complete RSL Nominations Agreement review
Revise the Council's Allocations Policy
Provide a high quality Housing Options Service
Implement the Rapid Rehousing Transition Plan incl Housing First
Action
Priority 1:  Improve access to housing in all tenures and alleviate housing need
Review RSL Nominations Agreements
Revise the Temporary Accommodation Charging Policy
Increase the supply of affordable rented housing
Regularly review allocations quotas
Implement Moray Council’s Downsizing Incentive Scheme
Priority 2:  Prevent and alleviate homelessness
Minimise the time taken to relet vacant social housing
Complete Moray Council Sheltered Housing review
Ensure provision of high quality Housing Support
Make the best use of
existing social
housing
Page 1 of 2
Item 7.
Page 29

Page 30

Moray Local Housing Strategy 2019-2024 Action Plan 2022/23/24 Appendix 1
Responsibility Timescale StatusAction
Moray Council 2019-24
See Housing Supply Target.  30-40% of funding is
allocated to development of amenity housing,
although this varies from site to site.
SHIP 2019-24 Progress led by Health and Social Care Moray
Increase tenure choice for older
people
Support implementation of the LDP 2020
Accessible Housing Policy (DP2 (f)) Moray Council 2019-24
People with learning
disabilities
Health and Social
Care Moray 2019-24 Contribute to aims of the LD Accommodation
Review, led by Health and Social Care Moray
Gypsy/ Travellers Moray Council Ongoing
Moray Council Ongoing
Moray Council Ongoing
Moray Council Ongoing Support available, including interest-free loans.
Moray Council 2019-24
Moray Council Ongoing
Increase supply of appropriate housing with care for people with learning
disabilities
Priority 3:  Assist people requiring specialist housing
Stock condition -
Private sector
Increase the supply of ambulant disabled housing for affordable rent
People with physical
disabilities
Implement the Protocol and Guidelines for the Response to Unauthorised
Camping in Moray
Priority 4:  Improve the condition and energy efficiency of housing, and minimise fuel poverty
Develop a Corporate approach to the use of available enforcement powers,
including Compulsory Purchase Orders (CPOs), and designation of Housing
Renewal Areas.
Implement the Private Landlord Registration Scheme Repairing Standard
Implement the Scheme of Assistance
Target support under the Scheme of Assistance to owners of BTS stock or those
who cannot afford the cost of essential repairs
Increase supply of extra care housing
Minimise empty homes in the private sector
Page 2 of 2Page 30

Page 31

REPORT TO:   HOUSING AND COMMUNITY SAFETY COMMITTEE ON 21 JUNE
2022  
SUBJECT: HOUSING INVESTMENT 2021/22   
BY:  DEPUTE CHIEF EXECUTIVE (ECONOMY, ENVIRONMENT AND
FINANCE) 
1. REASON FOR REPORT 
1.1 This report informs the Committee of the actual unaudited outturn to 31 March
2022 for the Housing Investment Programme for 2021/22. 
1.2 This report is submitted to Committee in terms of Section III G (3) of the
Council's Scheme of Administration relating to the maintenance of the
Council’s housing stock. 
2. RECOMMENDATION 
2.1 It is recommended that the Committee consider and notes the Housing 
Investment Programme unaudited outturn to 31 March 2022, as detailed 
in Section 3 and Appendices I to VI. 
3. BACKGROUND 
Investment Programme
3.1    APPENDIX I shows income and expenditure for 2021/22.  The Appendix
includes expenditure of £4,976k on the Council house new build programme
as ‘Other Capital Expenditure’.  This, however, is now the subject of a
separate monitoring report and the figure is provided for information only.
The figures show that an overall year-end expenditure of £14,218k was
achieved, which represents a spend of 76% against the £18,655k annual
budget, and a shortfall of £4,437k.  The shortfall in investment is attributable
to Coronavirus restrictions during 2021/22, which presented a number of
issues that included supply chain and internal staff resourcing delays
progressing a number of work activities.  
3.2    The level of expenditure within the individual budget headings that make up
the programme are shown in paragraphs 3.2 to 3.5 below.  The expenditure
figure represents all payments which have progressed through the finance
system to 31 March 2022, which is £754k higher than the most recent
projection.   
3.3    APPENDIX II shows expenditure on Response and Void Repairs.  Spend was
£4,943k to 31 March 2022 and represents a £573k overspend of the agreed
Item 8.
Page 31

Page 32

programme.  An overspend of £359k occurred in repairs following a back log
of non-emergency repairs after Covid restrictions eased, as well as
unanticipated emergency and make good repair costs following Storm Arwen
and Malik in late 2021.  Void repairs costs also outturned £214k over budget,
as a result of an upturn in void repair numbers following  the easing of Covid
restrictions, which saw a substantial increase in properties requiring repairs in
advance of relet. 
3.4    APPENDIX III shows expenditure on Estate Works.  Spend of £486k was
achieved to 31 March 2022 and represents 87% of the agreed programme
level.   
3.5    APPENDIX IV shows expenditure on Cyclic Maintenance.  Spend of £547k
was achieved to 31 March 2022 and represents 81% of the agreed
programme level.  The shortfall in investment is attributable to underspends in
the cyclical serving and external painter work programmes that occurred due
to internal staff resource and no access issues during the pandemic. 
3.6    APPENDIX V shows expenditure on Planned Maintenance and Other
Investments.  Spend of £8,242k was achieved to 31 March 2022 and
represents 63% of the agreed programme level. A significant underspend of
£4,810k occurred as a result of  Coronavirus restriction during 2021/2022,
which presented a number of issues that included availability of contractors,
supply chain issues and internal staff resourcing issues. 
3.7 The Energy Efficiency Standard for Social Housing (EESSH)   
programme expenditure figures are very low in relation to budget.  The 
main reason for this is delay in concluding a major contract for Warm 
Homes Round 4 grant funding with OVO Energy Limited (OVO), with 
COVID lockdown periods resulting in heating installation work being 
suspended for several months.  The recent takeover of Scottish and 
Southern Energy Limited (SSE) by OVO has delayed progress on 245 
new heating systems. Surveys are ongoing and 31 installations have 
taken place up to 31 March 2022 we are targeting completion of the 
programme for November 2022. This is however dependent of the   
availability of Air Source Heat Pumps and boilers which are also being 
affected industry shortages. 
3.8      The Low Carbon Infrastructure Transformation Programme LCITP project 
received approval of grant funding of £1.3m to Moray Council at the end of 
July 2021. The COVID-19 pandemic has impacted upon this  project and 
caused delays, procurement has now taken place and contractor appointed. 
Surveys are underway, however the industry is experiencing long lead in 
periods for Air Source Heat Pumps which will impact on the completion date 
for the project now anticipated to be March 2023.   
General Programme Updates
3.9      A major stock condition survey was carried out in early 2021.  This has 
provided essential information on prioritised investment programmes for the 
next 30 years and gives advice on requirements to meet standards for 
EESSH and SHQS compliance. 
Page 32

Page 33

3.10 A programme to upgrade smoke alarms in all Council properties in
accordance with new legislation in the aftermath of the Grenfell tragedy is
underway.  The appointed contractor completed 4,658 house upgrades to 31
March 2022.   Building Services DLO is also carrying out upgrades to
properties as part of void and planned maintenance works, with a further 859
properties upgraded to 31 March 2022.  This means that 5517 (88%) of
properties were completed to the new standard at 31 March 2022.  The target
for compliance was February 2022 and has subsequently been relaxed by
Scottish Government and at 31 March 2022,706 properties still require to be
completed (253 properties require building warrants to be in place before
works can commence, with no access the main reason for delays in the
remainder). 
3.11 As a result of the no access issues experienced, we are now considering
moving to forced entry to gain access to undertake this work, which will only
take place after all reasonable access attempts are exhausted, and will be
carried out in accordance with our agreed forced entry procedure.   
Income and Expenditure for Private Sector Housing
3.12 APPENDIX VI shows the position with regard to grant expenditure for Private
Sector Housing Grant to 31 March 2022.  The budget in Category B is the
responsibility of the Moray Integration Joint Board and the information is only
for noting at this Committee.  The legally committed figure of £477k
represents 95.40% of the allocated budget.  Spend to 31 March 2022 was
£318k which represents 63.60% of the allocated budget.  The underspend of
this budget was due to COVID-19 restrictions. 
3.13 The legally committed figure in Category C of £100k represents 95.20% of the
allocated budget.  Spend to 31 March 2022 was £49k which represents
46.60% of the allocated budget.  The underspend of this budget was due to
COVID-19 restrictions. 
4 SUMMARY OF IMPLICATIONS 
(a) Corporate Plan and 10 Year Plan (Local Outcomes Improvement
Plan (LOIP))
The provision of new affordable housing, the maintenance of the Council
is housing stock and dealing with homelessness are priorities identified
within the Corporate Plan, the Council’s Local Housing Strategy, the
Strategic Housing Investment Plan (SHIP) and the Housing and Property
Service Plan. 
(b) Policy and Legal
Maintenance and improvement works are carried out in order to meet
statutory legal requirements and in accordance with current relevant
policies. 
(c) Financial implications
The financial implications associated within this report are dealt with in
paragraphs 3.1 to 3.11 above, with details of the Council house new
build programme now being the subject of a separate monitoring report. 
Page 33

Page 34

(d) Risk implications
Failure to expend agreed budgets may affect the Council’s ability to
maintain stock at the SHQS, replace life expired elements and attain the
EESSH.  Budget Managers are aware of responsibilities for managing
budget allocations and approval for variance will be sought from
Committee in line with the Financial Regulations. 
(e) Staffing implications
There are no staffing implications associated with this report. 
(f) Property
The improvement and maintenance of the housing stock will ensure that
it remains sustainable in the longer term both physically and
environmentally. 
(g) Equalities/Socio Economic Impact
There are no equalities issues associated with this report, as it is to
inform the Committee on budget monitoring. 
(h)   Climate Change and Biodiversity Impacts
The continued investment in the Council Owned Housing Stock identified
in this report will assist the Council to achieve its climate change targets
by utilising a range of energy saving measures that incorporate zero or
low carbon into design, construction materials and systems that support
the Council in achieving The Energy Efficiency Standard for Social
Housing (EESSH). 
(i) Consultations
Consultations have taken place with the Head of Housing and Property
Services, Building Services Manager, Legal Services Manager, Principal
Accountant (Deborah O’Shea), Lindsey Robinson (Committee Services
Officer), and Home Improvement Services Manager, who all agree with
the sections of the report relating to their areas of responsibility.   
5     CONCLUSION 
5.1      The report shows that the Councils progress in respect of Housing 
investment for both the Council’s housing stock and the private sector 
has been adversely impacted because of delays during the Coronavirus 
pandemic.  Financial information highlighted shows that housing 
investment has slightly recovered following the easing of Coronavirus 
restrictions, however, delays to a number of a key planned investment 
programmes has led to a 24% (£4,437k) shortfall in overall investment . 
Recovery of programmes is essential to enable the Council to address
the identified priorities to improve the quality of housing stock in Moray. 
More specifically, the ongoing investment in the Council’s housing 
stock enables it to be maintained at the Scottish Housing Quality 
Standard, allows for replacement of life expired elements and makes 
progress towards the attainment of both the Moray Standard and the 
Energy Efficiency Standard for Social Housing. 
Author of Report: Paul Kendrick, Asset Manager 
Page 34

Page 35

Background Papers:   Held on file/sharepoint
Ref:    SPMAN-1285234812-1102
Page 35

Page 36

Page 36

Page 37

APPENDIX I
(all amounts in £'000)
HOUSING INVESTMENT PROGRAMME
Annual Budget
2021/22
Expenditure plus
commitments to
date
%
expendituere plus
committed to date
Expenditure to date
%
Budget spent to
date
Budget balance
Expenditure
Response, Gas & Void Repairs 4,370 4,943 113% 4,943 113% -573
Estate Works 557 529 95% 486 87% 71
Cyclic Maintenance 676 547 81% 547 81% 129
Planned Maintenance (Revenue) 2,062 1,086 53% 1,086 53% 976
Planned Maintenance (Capital) 10,620 6,793 64% 6,793 64% 3,827
Other Investment 370 363 98% 363 98% 7
Sub Total 18,655 14,261 76% 14,218 76% 4,437
Other Capital Expenditure
New Build - Capital Costs 16,305 4,976
Total 34,960 19,194
Funded by
HRA Revenue 7,675 7,425 97%
Government Grant 10,489 1,166 11%
Use of Council Tax Discount 550 662 120%
Prudential Borrowing 10,336 5,081 49%
Other Grants 1,000 0 0%
Capital Receipts 0 0 0%
C.F.C.R 4,910 4,860 99%
Total 34,960 19,194 55%
INVESTMENT PROGRAMME INCOME AND EXPENDITURE 2021/22
31 March 2022
Item 8.
Page 37

Page 38

Page 38

Page 39

APPENDIX II
(all amounts in £'000)
RESPONSE AND VOIDS REPAIRS
Annual Budget
2021/22
Expenditure plus
commitments to date
%
expendituere plus
committed to date
Expenditure to date
%
Budget spent to
date
Budget balance
West Area Office 1,386 1,797 130% 1,797 130% -411
East Area Office 1,074 1,012 94% 1,012 94% 62
Void House Repairs & Dec Vouchers 1,385 1,599 115% 1,599 115% -214
Gas Heating Repairs 525 535 102% 535 102% -10
4,370 4,943 113% 4,943 113% -573
31 March 2022
INVESTMENT PROGRAMME EXPENDITURE 2021/22
Item 8.
Page 39

Page 40

Page 40

Page 41

APPENDIX III
(all amounts in £'000)
ESTATE WORKS
Annual Budget
2021/22
Expenditure plus
commitments to
date
%
expendituere plus
committed to date
Expenditure to date
%
Budget spent to
date
Budget balance
Garage Upgrades 25 1 4% 1 4% 24
Asbestos 260 179 69% 142 55% 118
Landscape Maintenance 42 48 114% 43 102% -1
Estates/Forum Upgrades 230 242 105% 242 105% -12
Miscellaneous 0 59 0% 58 0% -58
557 529 95% 486 87% 71
31 March 2022
INVESTMENT PROGRAMME EXPENDITURE 2021/22
Item 8.
Page 41

Page 42

Page 42

Page 43

APPENDIX IV
(all amounts in £'000)
CYCLIC MAINTENANCE
Outturn
Annual Budget
2021/22
Expenditure plus
commitments to
date
%
expendituere plus
committed to date
Expenditure to date
%
Budget spent to
date
Budget balance
Gas Servicing 335 286 85% 286 85% 49
Solid Fuel Servicing 21 14 67% 14 67% 7
Air Source Heat Pump Servicing 25 35 140% 35 140% -10
Smoke Detector Servicing 35 5 14% 5 14% 30
PPR & External Painterwork 210 178 85% 178 85% 32
General Servicing 50 29 58% 29 58% 21
Inspections/House Surveys 0 0 0% 0 0% 0
676 547 81% 547 81% 129
INVESTMENT PROGRAMME EXPENDITURE 2021/22
31 March 2022
Item 8.
Page 43

Page 44

Page 44

Page 45

APPENDIX V
(all amounts in £'000)
PLANNED MAINTENANCE & OTHER INVESTMENTS
Outurn
Annual Budget
2021/22
Expenditure plus
commitments to date
%
expendituere plus
committed to date
Expenditure to date
%
Budget spent to
date
Budget balance
Kitchens and Bathrooms 1,470 781 53% 781 53% 689
Central Heating 2,000 1,399 70% 1,399 70% 601
Doors and Windows 950 508 53% 508 53% 442
Smoke Alarms/Co Upgrades 2,300 1,969 86% 1,969 86% 331
EESSH 3,900 2,136 55% 2,136 55% 1,764
Sub Total (Capital) 10,620 6,793 64% 6,793 64% 3,827
Rainwatergoods 250 170 68% 170 68% 80
Roof and Fabric Repairs 400 162 41% 162 41% 238
Plumbing Upgrades 50 9 18% 9 18% 41
Electrical Upgrades 350 375 107% 375 107% -25
Safety & Security 20 1 5% 1 5% 19
Common Stairs 40 25 63% 25 63% 15
Insulation 800 238 30% 238 30% 562
Energy Performance Certs (EPC) 0 31 0% 31 0% -31
Sheltered Housing 30 0 0% 0 0% 30
Decoration Vouchers 72 37 51% 37 51% 35
Shower Installations 50 38 76% 38 76% 12
Sub Total (Revenue) 2,062 1,086 53% 1,086 53% 976
Disabled Adaptations 360 349 97% 349 97% 11
Enabling Projects 10 14 140% 14 140% -4
Sub Total (Other Investment) 370 363 98% 363 98% 7
Total 13,052 8,242 63% 8,242 63% 4,810
INVESTMENT PROGRAMME EXPENDITURE 2021/22
31 March 2022
Item 8.
Page 45

Page 46

Page 46

Page 47

APPENDIX VI
(all amounts in £'000)
Budget Allocation
2021/22
Spend to date
Balance
Legally Committed
Completed Cases
CATEGORY
Independent Living
Category A (Revenue) 8 0 8 8 0
Category B 500 318 182 477 30
Category C 105 56 49 100 15
Overall Total 613 374 239 585 45
CATEGORY DESCRIPTIONS
Category A External agency running costs
Category B Grant Assistance to aid Independent Living - Adaptations
Category C Grant Assistance to aid Independent Living - House Condition Works
31 March 2022
SCHEME OF ASSISTANCE - 2021/22
PRIVATE SECTOR HOUSING GRANT
Item 8.
Page 47

Page 48

Page 48

Page 49

REPORT TO: HOUSING AND COMMUNITY SAFETY COMMITTEE ON 21 JUNE
2022 
SUBJECT: ALLOCATIONS POLICY ANNUAL PERFORMANCE REPORT
2021/22 
BY:  DEPUTE CHIEF EXECUTIVE (ECONOMY, ENVIRONMENT AND
FINANCE) 
1. REASON FOR REPORT 
1.1 To inform the Committee of the performance of the Council’s Allocations
Policy during 2021/22. 
1.2 This report is submitted to Committee in terms of Section III G (11) of the
Council's Scheme of Administration relating to the preparation and
implementation of strategic housing plans. 
2. RECOMMENDATION 
2.1 It is recommended that the Committee: 
(i) considers and notes the performance identified within the report; 
(ii) agrees the allocations quotas for 2022/23 detailed at Paragraph 5.4
of this report; and 
(iii) agrees the service developments of £41k per annum detailed at
paragraph 7.4. 
3. BACKGROUND 
3.1 The Council has considered performance monitoring information on the
operation of its Housing Allocation Policy annually since 2005.  The most
recent report was presented to Economic Growth, Housing and Environmental
Sustainability Committee on 8 June 2021 (Paragraph 16 of the Minute refers). 
3.2 The Communities Committee approved the Moray Local Housing Strategy
(LHS) 2019-2024 on 2 April 2019 (Paragraph 8 of the Minute refers).  The
LHS sets out the Council’s approach to addressing housing need and
homelessness, property condition and fuel poverty.  The operation of the
Allocations Policy is a key factor in the delivery of LHS outcomes. 
Item 9.
Page 49

Page 50

3.3 The Communities Committee approved a revised Allocations Policy on 5
February 2019 (Paragraph 9 of the Minute refers) for implementation from 1
May 2019.  A further review of the Allocations Policy is included in the Local
Housing Strategy Action Plan 2022-24 presented elsewhere on this agenda. 
4. ANALYSIS OF HOUSING LIST ALLOCATION AND DEMAND TRENDS 
4.1 Statistical information on the operation of the policy is presented in
APPENDIX I.  The statistics for 2020/21 and 2021/22 should be viewed in the
context of the national response to the COVID-19 pandemic and associated
restrictions in activity. 
4.2 Table 1 provides details of the housing list for the last 5 years. This shows
that the Transfer List and Waiting List have increased but there has been a
reduction in the Homeless List over the last 5 years.  However, these
reductions may have been affected by the COVID-19 pandemic.  Also, it is
possible that persons in shielding categories may have been deterred from
making an application during the pandemic.  With the exception of 2020/21,
the Transfer List has been increasing consistently since 2013/14 and this has
been attributed to the new build housing programme with its emphasis on
accessible housing and larger family-sized accommodation.  Housing List
trends were considered in depth as part of the development of Housing Needs
and Demand Assessment (HNDA) 2017 and the Local Housing Strategy
(LHS) 2019-2024, and were reflected in the revised Allocations Policy
implemented on 1 May 2019. 
4.3 Table 2 details the size and type of housing required by applicants on the
housing list.  Over the past 5 years, there have been significant increases in
demand for larger 4+ bed family sized housing and also amenity/accessible
housing.  The latter is consistent with the projected demographic changes in
Moray and the ageing population.  Demand for sheltered housing has reduced
despite demographic changes. 
4.4 Table 3 provides summarised information on the 1st area preferences of
current housing list applicants.  It shows that area preferences are broadly in
proportion to the number of dwellings (all tenures) in each Housing Market
Area. 
4.5 Applicants who apply for housing are able to state where they want to live.
This allows them the choice of any, or all, of the 62 lettings areas across
Moray.  These choices can be driven by urgency and availability, rather than a
desire to live in a particular area, settlement or town.  To support strategic
planning for affordable housing, applicants are asked separately to state their
1st, 2nd and 3rd areas of preference (i.e. where they would ideally choose to
live).  This second, strategic question is the source used to inform the
Council’s approach to delivery of new affordable housing across geographical
areas, and is reflected in the Strategic Housing Investment Plan (SHIP). 
4.6 Table 4 provides details of the number of re-lets from Council stock in
2021/22.  When this is compared to the housing list as at 31 March 2022, it
shows that there were 8 applicants on the list per re-let (8:1) during 2021/22. 
However this pressure varies greatly across house types and sizes: 
Page 50

Page 51

• 1 bed general needs (27:1);
• 2 bed general needs (4:1); and 
• 4 bed (69:1). 
4.7 The table also shows that there is no evidence of significant migration
between Housing Market Areas (HMA). 
4.8 Table 5 shows that there is an increasing trend in re-let rates, as intended,
with the introduction of the revised Allocations Policy in May 2019.  Increasing
the numbers of vacancies from existing stock will assist the Council to
successfully deliver the Rapid Rehousing Transition Plan.  Although the
number of relets reduced in 2020/21, this can be attributed to the COVID-19
restrictions on house-moves in all tenures for part of 2020. 
5. ALLOCATIONS QUOTAS FOR THE HOUSING LIST 
5.1 The housing list consists of three separate lists (waiting, transfer and
homelessness).  The Homeless List includes those who have been assessed
as statutorily homeless, the Waiting List consists of applicants who are waiting
for a council house, and includes current RSL tenants; and the Transfer List of
those who are current Council tenants and who need or want to move.  The
proportion of allocations to be made to each list is determined annually by
Committee. 
5.2 Table 6 shows the proportion of allocations made to applicants from the 3
housing lists, over the last 5 years.   
5.3 The Rapid Rehousing Transition Plan aims to minimise the use of temporary
accommodation and provide permanent housing options to homeless
households as quickly as possible.  The Homeless List quota proposed below
is intended to strike an appropriate balance between the need to implement
the Rapid Rehousing Transition Plan, and the need to minimise any
unintended consequences of increased quota i.e. that the Homeless List
would be seen by applicants as the quickest route into permanent housing,
and would significantly increase as a result.   
5.4 Historically the Council has taken a pragmatic view and agreed quotas
intended to strike an acceptable balance between all lists.  The quotas
proposed for 2022/23 remain unchanged from the 2020/21 targets and are: 
List Target Tolerance
Homeless List 50% +/-5%
Waiting List 32% +/-5%
Transfer List 18% +/-5% 
6. NEW BUILD LETTINGS PLAN 
6.1 The new build lettings plan was introduced in 2015.  A revised Lettings Plan
was approved by Housing and Community Safety Committee on 8 February
2022 (Para 7 of the draft Minute refers).  The Plan sets out how the Council
will deviate from the Allocations Policy in identifying the first tenant in new
Page 51

Page 52

build properties, with the aim of establishing successful, sustainable new
communities, and this includes deviation from Housing List quotas. 
6.2 Table 7 shows there were 57 Council new lets during 2021/22.  There were
new build handovers at the end of 2020/21 which were not let until the start of
2021/22. 
6.3 Table 8 shows the proportions of allocations from each List, and that 47% of
new lets were allocated to Transfer List applicants. 
7. HOUSING INFORMATION SYSTEMS ASSISTANT 
7.1 The housing management system, supplied by Northgate, comprises various
modules specific to our business areas.  The system is central to the day to
day operations of the Housing and Property service.  Northgate invest in the
system on an on-going basis, to take account of statutory duties, legislative
changes and the need for reporting and measuring performance. 
Consequently, two product releases are made each year which include new
modules and enhancements.  Northgate will continue to provide produce
support whilst we continue to install product releases and keep the system up
to date. 
7.2 The Housing Online module was introduced in June 2021.  Housing Online
allows Housing List applicants to complete and maintain their application
online.  This module has the potential to be further developed to provide a
wider range of online services to applicants and tenants. 
7.3 The review of the Council’s Allocations Policy referred to in Paragraph 3.3
above will require changes to be made to the Northgate system.  This will
involve scenario testing as the new policy interventions evolve as well as
system changes required to implement any new policy.  Since May 2019, the
Housing Information Systems Officer has been the only staff member with the
skills and experience to complete these client role tasks, and this has already
been identified as a business continuity risk. 
7.4 The HRA budget set in February 2022 included provision for service
developments, which included recruitment of a 1.0 FTE Housing Information
Systems Assistant.  Officers seek approval to progress recruitment to this
post.  This would mitigate the business continuity risk and would provide the
resource required to develop and implement ICT related service
enhancements for housing list applicants and tenants, potentially increasing
efficiency, as well as delivery of training to system users and facilitating
knowledge transfer.  
Page 52

Page 53

8. SUMMARY OF IMPLICATIONS 
(a) Corporate Plan and 10 Year Plan (Local Outcomes Improvement
Plan (LOIP))
Moray 2027 and the Service Plan identify the need to address the
shortage of affordable housing and tackle homelessness.  The
Allocations Policy seeks to make the best use of the Council’s housing
stock and promote healthier citizens and more people living well in their
communities. 
(b) Policy and Legal
The primary legislation governing allocations of Council housing is
contained within the Housing (Scotland) Act 1987 as amended by the
Housing (Scotland) Act 2001, the Homelessness etc. (Scotland) Act
2003 and the Housing (Scotland) Act 2014. This legislation provides the
Council with the discretion to develop allocation and local letting policies
in line with local priorities. 
The Scottish Social Housing Charter sets out standards against which
the Scottish Housing Regulator will assess local authorities as part of its
inspection regime. 
(c) Financial implications
The financial implications of this report were included in the HRA Budget
monitoring report considered by Housing and Community Safety
Committee on 22 March 20222 (para 9 of the Minute refers).  This cost
of this post will be up to £13,622 from the 2022/23 budget and £40,865
per annum from 2023/24 onward. 
(d) Risk Implications
Recruitment to the post detailed in Para 7.4 would mitigate a previously
identified business continuity risk. 
(e) Staffing Implications
There are no staffing implications arising from this report. 
(f) Property
There are no property implications arising from this report. 
(g) Equalities/Socio Economic Impact
There are no impacts in relation to equal opportunities or the socio-
economic duty as the purpose of the report is to inform Committee on
performance. 
(h) Climate Change and Biodiversity Impacts
There are no climate change implications arising from this report. 
(i) Consultations
Consultation on this report has taken place with the Corporate Director
(Economic Development, Planning and Infrastructure), the Head of
Housing and Property, Housing Needs Manager, Housing Services
Manager, Acting Chief Financial Officer, Equal Opportunities Officer,
Page 53

Page 54

Legal Services Manager, and Lindsey Robinson (Committee Services
Officer).   
9. CONCLUSION 
9.1 This report presents the annual review of the operation of the Council’s
Housing Allocations Policy.  It presents proposed allocations quotas for
2022/23, unchanged from 2021/22.  The quotas proposed are intended to
complement implementation of the Rapid Rehousing Transition Plan. 
9.2 The report also seeks approval to recruit a 1.0 FTE Housing Information
Systems Assistant to mitigate the existing business continuity risk and
facilitate ICT related service improvements. 
Author of Report: Fiona Geddes, Acting Housing Strategy and Development
Manager
Background Papers: with author
Ref: SPMAN-1285234812-1098 
Page 54

Page 55

Moray Council Allocations Policy Performance Report 2021/22 APPENDIX I
Table 1:  No of applicants on the Housing List at year end
List 2017/18 2018/19 2019/20 2020/21 2021/22
Change
since
2017/18
(No)
Change
since
2017/18
(%)
Homeless List 112 121 92 101 97 -15 -13.4%
Housing Waiting List 2,434 2,474 2,989 2,425 2,754 320 13.1%
Transfer List 521 552 628 533 621 100 19.2%
Total 3,067 3,147 3,709 3,059 3,472 405 13.2% 
Table 2:  Size and type of property sought by applicants at year end
Property size and type 2017/18 2018/19 2019/20 2020/21 2021/22
Change
since
2017/18
(No)
Change
since
2017/18
(%)
1 bed general needs 1,210 1,210 1,427 1,180 1,347 137 11.3%
1 bed amenity/ wheelchair accessible 325 325 526 418 487 162 49.8%
2 bed general needs 701 701 713 590 682 -19 -2.7%
2 bed amenity/ wheelchair accessible 108 108 152 123 138 30 27.8%
3 bed general needs 437 437 518 442 466 29 6.6%
3 bed amenity/ wheelchair accessible 27 27 34 31 37 10 37.0%
4 bed general needs 146 146 201 168 195 49 33.6%
4 bed amenity/ wheelchair accessible 13 13 7 7 11 -2 -15.4%
5+ bed all types 42 42 58 48 68 26 61.9%
sheltered 58 58 73 52 41 -17 -29.3%
Total 3,067 3,067 3,709 3,059 3,472 405   
Item 9.
Page 55

Page 56

Moray Council Allocations Policy Performance Report 2021/22 APPENDIX I
Table 3:  Where applicants wish to live – 1st Area Preference as at 31 March 2019
List Buckie
HMA
Elgin
HMA
Forres
HMA
Keith
HMA
Speyside
HMA
CNP
HMA Total
Homeless List 10 64 20 3     97
Transfer List 117 339 83 51 24 7 621
Housing Waiting List 391 1,552 453 184 147 27 2,754
Total 518 1,955 556 238 171 34 3,472
14.9% 56.3% 16.0% 6.9% 4.9% 1.0% 100.0%
% dwellings (Source: HNDA Appendix 2) 16.8% 47.6% 18.0% 8.3% 8.0% 1.2% 100.0% 
Table 4:  Re-lets by property size and type 2020/21 (secure tenancies only)
Property size and type Buckie
HMA
Elgin
HMA
Forres
HMA
Keith
HMA
Speyside
HMA
CNP
HMA Total
ratio/ relative
pressure (lets
vs demand)
Bedsit     3       3 n/a
1 bed general needs 4 29 10 1 5   49 27.5
1 bed amenity/ wheelchair accessible 21 53 8 8 13   103 4.7
2 bed general needs 40 79 10 13 14   156 4.4
2 bed amenity/ wheelchair accessible 12 12 2 5 3   34 4.1
3 bed general needs 15 27 2 9 2 1 56 8.3
3 bed amenity/ wheelchair accessible 4 6 3 1     14 2.6
4 bed all types 1 2         3 68.7
5+ bed all types             0 n/a
sheltered 6 16 5       27 1.5
Total 103 224 43 37 37 1 445 7.8
23.1% 50.3% 9.7% 8.3% 8.3% 0.2% 100.0% 
% dwellings (Source: HNDA Appendix 2) 16.8% 47.6% 18.0% 8.3% 8.0% 1.2% 100.0% 
Page 56

Page 57

Moray Council Allocations Policy Performance Report 2021/22 APPENDIX I 
Table 5:  Rate of relets to Council stock (turnover) (new lets excluded)
Council stock 2017/18 2018/19 2019/20 2020/21 2021/22
Change
since
2017/18
(No)
Change
since
2017/18
(%)
Council stock 6,053 6,122 6,149 6,251 6,297 244 4.0%
No of relets 371 377 470 340 445 74 19.9%
Rate of relets 6.1% 6.2% 7.6% 5.4% 7.1%   
Table 6:  Allocations by Housing list (secure tenancies)(relets and new lets)
List 2017/18 2018/19 2019/20 2020/21 2021/22
Homeless List 214 51.2% 187 42.0% 256 51.4% 212 49.2% 264 52.6%
Housing Waiting List 117 28.0% 149 33.5% 143 28.7% 92 21.3% 150 29.9%
Transfer List 87 20.8% 109 24.5% 99 19.9% 127 29.5% 88 17.5%
Total 418 100.0% 445 100.0% 498 100.0% 431 100.0% 502 100.0% 
Page 57

Page 58

Moray Council Allocations Policy Performance Report 2021/22 APPENDIX I 
Table 7:  Moray Council new build completions 2020/21 (new lets)
House type  Buckie
HMA
Elgin
HMA
Forres
HMA
Keith
HMA
Speyside
HMA
CNP
HMA Total
1 bed general needs   19         19 33.3%
2 bed general needs   6         6 10.5%
2 bed amenity/wheelchair accessible   11         11 19.3%
3 bed general needs   18         18 31.6%
3 bed amenity/wheelchair accessible   1         1 1.8%
4+ bed all types   2         2 3.5%
Total  0 57 0 0 0 0 57 100.0% 
Table 8:  Moray Council new lets 
List 2018/19 2019/20 2020/21 2021/22
Homeless List 18 26.5% 5 17.9% 11 12.1% 10 17.5%
Housing Waiting List 28 41.2% 6 21.4% 37 40.7% 27 47.4%
Transfer List 22 32.4% 17 60.7% 43 47.3% 20 35.1%
Total 68 100.0% 28 100.0% 91 100.0% 57 100.0% 
Page 58

Page 59

REPORT TO: HOUSING AND COMMUNITY SAFETY COMMITTEE ON 21 JUNE
2022                                                                                                       
SUBJECT: PERFORMANCE REPORT (HOUSING AND PROPERTY
SERVICES) – PERIOD TO MARCH 2022 
BY:  DEPUTE CHIEF EXECUTIVE (ECONOMY, ENVIRONMENT AND
FINANCE) 
1. REASON FOR REPORT 
1.1 To inform the Committee of the performance of the service for the period to 31
March 2022. 
1.2 This report is submitted to Council in terms of Section III (A) (4) of the
Council's Scheme of Administration to monitor performance of the services
within the Committee’s remit in accordance with the Council’s performance
management framework. 
2. RECOMMENDATION 
2.1 It is recommended that Committee: 
(i) Scrutinise and note performance in the areas of Service Planning,
Service Performance and other related data to the end of
September 2021; 
(ii) notes the actions being taken to improve performance where 
required; and 
(iii) delegates authority to the Head of Housing and Property Services
to submit the Annual Assurance Statement on behalf of
committee, following a briefing for members as detailed in
paragraph 6.9.   
3. BACKGROUND 
3.1 On 7 August 2019, the Moray Council, approved a revised Performance
Management Framework for services (para 5 of the minute refers).   
4. SERVICE PLANNING 
4.1 Each service plan sets out the planned strategic and service level priorities
and outcomes it intends to deliver in the coming year aligning closely with
Item 10.
Page 59

Page 60

financial planning, corporate and community planning partnership strategic
priorities. This report provides an interim update on progress on the service
plan, key outcomes and performance indicators. Committee is invited to
review progress to secure assurance that is satisfactory and to provide
scrutiny and further direction where performance requires attention. 
4.2 The narrative included is by exception, links to Service Plan Actions and
Performance Indicators can be accessed within the Backing Papers of this
report. 
Strategic Outcomes – Successes
4.3 To better understand tenant satisfaction, findings from the 2021 tenant survey
were presented to this Committee in February 2022 (item 8 of the Minute
refers).  Tenant satisfaction with housing services is reported across seven
indicators each applying a target of 90% satisfaction; two indictors achieved
target with the remaining five reporting satisfaction levels of above 80%.  A
revised improvement plan will be submitted to this Committee for
consideration in August 2022. (ACTION HPS20-22.S4.3.1 INDICATORS
H1.3, 1.6) 
SERVICE PLAN PRIORITIES RAG
STRATEGIC
LEVEL
Assess and respond to the housing
needs of older people in partnership
with IJB
80%
Prepare a Climate Change Strategy
and Action Plan 100%
Investigate and better understand
the reasons for poor satisfaction
rates as identified in the Best Value
Audit (BV)
100%  
SERVICE
LEVEL
Provide an adequate supply of
affordable housing in Moray 95%
Transform the approach of
addressing homelessness in Moray 80%
Reduce fuel poverty in Moray 40%
Improve the energy efficiency of the
Council's housing stock 60%
Improve management of void
Council houses 45%
Improve performance of response
repairs to Council houses 60%
Review Housing Maintenance
Partnership Agreement 30%
The condition of Council houses is
good and meets required standards 100%
Compliance with new fire and smoke
alarm legislation in all Council
houses
86%
Make the best use of the Council's
property assets 70%  
RECOVERY
&
RENEWAL
Infrastructure Development 86%  
OVERALL PLAN PROGRESS 77%   
13
5
12
3 0
SERVICE PLAN PI'S
Above
Target
Within
Target
Below
Target
Data Only
Data not
available
33
Page 60

Page 61

Strategic Outcomes – Challenges and Actions to Support
4.4 Responding to the housing needs of older people is well progressed, albeit
out with the original due date.  The Housing Need and Demand Assessment
is developed In partnership with the Integration Joint Board and budgetary
provision has been carried forward and scheduled within the 2022/23 Service
Plan. (ACTION HPS20-22.S4.1.1) 
Service Level Outcomes - Successes
4.5  With the effects of COVID-19 on the programme lessening, the Scottish
Government funding allocation of £9.633m has been committed.  An
additional £0.742m funding was secured as a result of authorities being
unable to spend allocations extending the programme being delivered.
(ACTION HPS20-22.S5.01.1.3) 
Service Level Outcomes – Challenges and Actions to Support
4.6 The impact of the pandemic on the service has delayed and disrupted the
delivery of many Service Plan priorities, however progress continues to be
made out with original due dates as detailed. 
4.7 In the year to March 2022, 46 new council houses were delivered, with a
further 33 delayed into 2022/23, the HRA Business Plan will determine the
forward programme. (ACTION HPS20-22.S5.01.1.4) 
4.8 Recruitment of three Housing Support Workers to support delivery of the
Housing First Project has been unsuccessful.  The vacancies have been
reconfigured and in the interim the Housing First Project will launch with
existing officers supporting initial tenancies scheduled to be in place mid-May.
(ACTION HPS20-22.S5.02.1.3) 
4.9 As at 31 March 2022, £778k (36%) of the Scottish Government Home Energy
Efficiency Programme Area Based Scheme (HEEPS:ABS) 2020/21 funding
allocation has been spent.  The 2021/22 funding allocation of £1.9m is to be
drawn down by June 2022.  The contract for delivery of the Scheme has been
awarded and householder engagement procedures are being established.
(ACTION HPS20-22.S5.03.1.1) 
4.10 Improving the energy efficiency of the Council’s housing stock has
progressed, with full compliance with Energy Efficiency Standard for Social
Housing (EESSH) anticipated by March 2023.  At the end of March 2022,
60% of properties are now meeting standard with significant programmes of
work approved for the year ahead.  Recently published Local Government
Benchmarking Framework (LGBF) results for 2020/21 report Moray ranked
26th of 32 local authorities in the percentage of council dwellings that are
energy efficient, therefore a similar ranking can be anticipated for 2021/22.  
(ACTION HPS20-22.S5.04.1.1-2) 
4.11 The management of void properties has improved with an average re let
timescale of 62 days, down from 72 days last year but still significantly above
target of 32 days.  The percentage of rent lost due to voids, at 1.25% is
double the target value (0.63%).  The high number of voids since the easing
of lockdown restrictions have placed pressure on teams with ongoing issues
such as labour resource, utility provider delays and high levels of repairs. 
With void numbers reducing, it is anticipated that performance will improve
Page 61

Page 62

during 2022/23.  The Void Improvement Group meets regularly to improve
process and procedure in a bid to accelerate improvements. (ACTIONS
HPS20-22.S5.05.1.1-2 INDICATORS H2.10e, 5.4, 5.6) 
4.12 Limited progress has been made on reviewing repairs targets, the Housing
Management Team have agreed proposals and a revised project plan aims to
consult with tenants and representatives by summer 2022.  A report on the
findings will be submitted to this Committee in late 2022 with implementation
planned from April 2023. (ACTION HPS20-22.S5.06.1.1 INDICATORS H2.9b,
2.10b, 2.10d) 
4.13 The review of the Housing Maintenance Partnership will be undertaken in the
second half of 2022/23 which ties in with the revised 3 year Housing
Investment Plan to demonstrate that best value is being achieved from the
partnership.  A project board will oversee the review, as well as monitor the
progress against the Housing Investment Plan to ensure delivery as planned.
(ACTION HPS20-22.S5.07.1.1) 
4.14 Compliance with new fire and smoke legislation, subject to slippage, is
anticipated to be completed by September 2022 with consideration being
given to no access measures in order to meet the statutory requirement.  As
at March 2022, 862 (14%) properties remain outstanding, principally due to no
access issues, which is similar to the experiences across other local
authorities.  The Scottish Housing Regulator has confirmed that there will be
no challenge for non-compliance. (ACTION HPS20-22.S5.09.1.1) 
4.15 The Property Asset Management Appraisal (PAMA) is progressing with an
update due to be submitted to Committee in August 2022.  The Depot and
Store will be considered in a wider review of non-office assets with an update
also due for submission to Committee within a similar timeframe.  Changes to
working practices during COVID are being further considered to maximise the
efficiencies within the office estate over the next 12 months, significantly
broadening the scope of the original work stream. (ACTION HPS20-
22.S5.10.1.1) 
4.16 As stated in para 4.3 above, five measures of tenant satisfaction fell just short
of target in 2021/22.  These will be addressed within the revised Improvement
Plan. (INDICATORS H1.1, 2.3, 2.4, 2.14, 4.9) 
4.17 The percentage of council housing stock meeting the Scottish Housing Quality
Standard decreased to 47.3% in 2021/22.  The requirement for stock to be
EESSH compliant, introduced in January 2021 and amended fire safety
regulations from February 2022, both contributory factors to not achieving
target.  It is anticipated that the completion of fire safety upgrades and focus
on heating installations planned for the coming year will improve performance
results in this area. (INDICATOR H2.1)  
Page 62

Page 63

Renewal and Recovery Successes
4.18 Infrastructure development has progressed with high-level business cases
prepared for sites at Forres and Rothes, approved by the Asset Management
Working Group in November 2021.  Purchase prices have been received for
Forres and options of land purchase and infrastructure delivery discussed for
Rothes. (ACTION HPS20-22.S6.01.1.2-3) 
Recovery and Renewal - challenges and actions to support
4.19 In the provision of employment land and industrial units, designs and costings
for joint working with the Highlands and Islands Enterprise have been delayed
due to resourcing.  Funding has been allocated in the Council’s capital plan
for 2022/23.  (ACTIONS HPS20-22.S6.01.1.1, 1.4-5) 
5. SERVICE PERFORMANCE 
5.1  In line with the Performance Management Framework, operational
performance is reviewed quarterly by departmental management.  Areas
performing well and/or areas subject to a decreasing trend or where
benchmarking results show performance significantly below comparators will
be reported to this committee for member scrutiny. 
5.2 Initial publication of 2020-21 Local Government Benchmarking Framework
Indicators in February 2022 will be refreshed in early June.  The full suite can
be viewed using the My Local Council tool.  Published indicators for this
service have been incorporated within the relevant section of this report
depending on whether results are used to evidence progress against
strategic, service level or operational priorities. 
5.3  The narrative included in this report is by exception, links to Service
Performance Indicators can be accessed within the Background Papers at the
end of this report.   
4
2
3
31
2
SERVICE PERFORMANCE
PI'S
Above
Target
Within
Target
Below
Target
Data Only
Data not
available
42
Page 63

Page 64

Operational Indicators - Successes
5.4 The percentage of new tenancies being sustained for more than one year
continues to exceed 90% inferring that appropriate support is in place. 
(INDICATORS H4.1a, 1c, 1f) 
5.5 The completion of medical adaptations shows a return to pre-pandemic
performance levels, average times to complete applications and undertake
the work required have improved and there has been a significant reduction in
the number of households waiting for adaptions to their home. (INDICATORS
H4.4, 4.4a-d) 
Operational Indicators - Challenges and Actions to Support
5.6 In 2021/22, 54.7% of housing applications were admitted to the list within 10
days against an expectation that all applications meet the target timescale. 
Performance in quarters 2 and 3 showed a significant drop which coincides
with easing of COVID-19 regulations and the additional pressures that placed
on resources as a result. (INDICATOR H4.15) 
5.7 In 2021/22, gross rent arrears were 3.8% of rent due, a year on year increase
and above target (2.8%) performance.  LGBF indicator results for 2020/21
allow comparison across all local authorities.  Despite not meeting the local
target, Moray continues as the top performing authority in relation to gross
rent arrears with the national average for that period 8.19%.  Increasing
current tenants’ arrears of 4.5% against a target of 3.5%, perhaps suggests
the cost of living crisis, increasing inflation, fuel and energy costs may be
contributory factors that will pose further challenge in 2022/23. (INDICATORS
H5.3, 5.5) 
6. OTHER PERFORMANCE RELATED DATA 
Complaints & MP/MSP Enquiries
6.1 In line with the Performance Management Framework, complaints are
reviewed quarterly by departmental management in terms of time taken to
respond, outcome and learning points. Detailed tables can be accessed within
the Background Papers section of this report. 
6.2 In the half year to March 2022, 80 complaints were closed by Housing and
Property Services, of which 69 (86%) were frontline stage, 7 (9%) were
investigative stage and 4 (5%) were escalated.     
6.3 Of those closed at frontline stage, 42 (61%) were either upheld or part upheld.
77% of frontline complaints were completed within the target of 5 working
days; on average taking 4.4 days to complete. 
6.4 Of those closed at investigative and escalated, 8 (73%) were either upheld or
part upheld.  73% of investigative and escalated complaints were completed
with the target of 20 working days; on average taking 24 days to complete. 
6.5 The majority of upheld or part-upheld complaints relate to repairs, capital,
planned maintenance, with corrective actions put in place for each.   
6.6 In the second half of 2021/22, 104 enquiries were dealt with, the majority
relating to housing needs. 
Page 64

Page 65

Other Performance (not included within Service Plan) 
Annual Assurance Statement
6.7 The Scottish Social Housing Charter came into force on 1 April 2012. The aim
of the Charter is to improve the quality and value of the services provided by
social landlords. The Charter sets out the minimum standards and outcomes
that tenants can expect from their landlord, including the quality of and value
for money of services, the standard of homes and the opportunities to
participate in their landlord’s decision-making processes. Using a range of
performance indicators, the Scottish Housing Regulator (SHR) monitors, and
assesses landlords’ performance against the Charter. 
6.8 Each year social landlords must submit an Annual Return on the Charter
(ARC) to the SHR and an Assurance Statement by 31 October. The Annual
Assurance Statement assures the SHR and our tenants and other service
users that we comply with our regulatory and statutory obligations. 
6.9 National ARC data for comparison will be published on 31 August 2022,
allowing insufficient time for the analysis required to inform the Assurance
Statement to be included in the agenda for the 6 September 2022 meeting of
this committee. It is therefore intended that a briefing for committee members
will be arranged in October 2022 in order to present the performance data and
draft Assurance Statement prior to the deadline for submission on 31 October
2022. In order that it can be approved on behalf of committee prior to the
subsequent meeting on 15 November 2022, delegated authority is sought for
the Head of Housing and Property to approve the draft following consultation
with members at the briefing and for the Chair & Vice-chair to sign the
statement on behalf of committee. 
Social Landlords Annual Performance Report
6.10 The SHR also requires social landlords to produce an annual report on their
performance against the Charter and make it available to tenants and other
customers by no later than 31 October. 
6.11 The SHR expects the report to be developed in partnership with tenants and
other customers, rather than exclusively by the Council. The format, content
and design of the Council’s report has been developed in discussion with the
Moray Tenants’ Forum. The report mirrors the key themes of the Charter. 
6.12 Similar to the Assurance Statement, the Annual Performance report is
dependent on access to the national ARC data, accordingly it is intended that
the report will be prepared by officers in consultation with
tenants/stakeholders and will be presented to members at the briefing in
October 2022, prior to publication in advance of the deadline.   
Consultation and Engagement
6.13 During August to November 2021, the Council carried out a 3-yearly, large
scale, Tenants Survey. This is a requirement of the Scottish Housing
Regulator and the results will be reported in the ARC 2021/22. The survey
involved telephone interviews with a random sample of around 30% of
Council tenants. The final results were presented to members of this
committee in a briefing on 19 January 2022 and reported to the committee
meeting on 8 February 2022. The findings will inform the future investment
priorities and service delivery plans for tenants over the next 3 years and a
Page 65

Page 66

Tenant Survey Improvement Plan will be reported to the committee meeting
on 15 November 2022. 
7. SUMMARY OF IMPLICATIONS 
(a) Corporate Plan and 10 Year Plan (Local Outcomes Improvement
Plan (LOIP))
Performance measurement is used to ensure the efficient and
sustainable delivery of services to meet the Council’s priorities in both
the Corporate Plan and the LOIP. 
(b) Policy and Legal
The Council has a statutory requirement to publish a range of
information that will demonstrate that it is securing best value and assist
in comparing performance both over time and between authorities where
appropriate. 
(c) Financial implications
None. 
(d) Risk Implications
None. 
(e) Staffing Implications
None. 
(f) Property
None. 
(g) Equalities/Socio Economic Impact
An Equality Impact Assessment is not required as this report is to inform
the Committee on performance. 
(h)   Climate Change and Biodiversity Impacts
None. 
(i) Consultations
The Head of Housing and Property Services, Depute Chief Executive
(Economy, Environment and Finance) and Service Managers have been
consulted with any comments received incorporated into this report. 
8. CONCLUSION 
8.1 As at March 2022, overall progress against planned actions was 77%
complete.  The service has been significantly challenged in delivering
improvement work around energy efficiency of the Council’s housing
stock and management of void council houses due to COVID-19
restrictions, as these have eased the pace of improvement activity has
increased with further improvement anticipated during 2022/23.   
Author of Report: Christopher Dewhurst, Research & Information Officer
Background Papers: Service Plan Actions 
Service Plan Performance Indicators 