Democracy Spraffa

Supplementary Agenda Document Pack - Economic Development and Infrastructure Services Committee - 02/05/2023

Moray Council · 2 May 2023
Back to Economic Development and Infrastructure Services Committee — 2 May 2023 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

Economic Development and Infrastructure Services
Committee 
Tuesday, 02 May 2023 
SUPPLEMENTARY AGENDA 
The undernoted reports have been added to the Agenda for the meeting of the
Economic Development and Infrastructure Services Committee to be held at
Council Chambers, Council Office, High Street, Elgin, IV30 1BX on Tuesday, 02
May 2023 at 09:30. 
BUSINESS 
6a) Economy, Environment and Finance Service Plans 2023-
24
Report by Depute Chief Executive (Economy, Environment and
Finance)  
3 - 56
6b) Economic Recovery Plan Delivery 2022-23
Report by Depute Chief Executive (Economy, Environment and
Finance)  
57 - 70
6c) Climate Change Plan and Route Map to Net Zero
Report by Depute Chief Executive (Economy, Environment and
Finance)  
71 -
134 
Page 1

Page 2

Page 2

Page 3

REPORT TO: ECONOMIC DEVELOPMENT AND INFRASTRUCTURE
SERVICES COMMITTEE ON 2 MAY 2023 
SUBJECT: ECONOMY, ENVIRONMENT AND FINANCE (EEF) SERVICE
PLANS 2023-24 
BY:  DEPUTE CHIEF EXECUTIVE (ECONOMY, ENVIRONMENT AND
FINANCE) 
1. REASON FOR REPORT 
1.1 To invite the Committee to consider the Economy, Environment and Finance
Service Plans for 2023-24, noting that the Service Plan for Financial Services
will be considered at Corporate Committee on 13 June 2023, the Economic
Growth and Development Services Plan will also be considered at the
Planning and Regulatory Services Committee on 30 May 2023 and the
Housing and Property Services Plan at the Housing and Community Safety
Committee on 9 May 2023, each in terms of their respective remits. 
1.2 This report is submitted to Committee in terms of Section III (B) (50) of the
Council's Administrative Scheme relating to ensuring that the organisation,
administrative and management processes of the Council are designed to
make the most effective contribution to achieving the Council’s objectives and
to keep these procedures under review. 
2. RECOMMENDATION 
2.1 In terms of the remit of this Committee, and subject to later scrutiny and
approval as set out in paragraph 1.1 above where required, it is
recommended that Committee consider and approve the Service Plans
for Economic Growth and Development, Housing and Property Services
and Environmental and Commercial Services (Appendices 1-3). 
3. BACKGROUND 
3.1 Service planning is a key aspect of the Council’s Performance Management
Framework and is undertaken annually to set out the strategic direction for
services over the coming months.   
3.2 The service planning process focuses on forward planning for medium-term
activities supporting delivery of the Local Outcomes Improvement Plan (Loip)
Item 6a)
Page 3

Page 4

and Corporate Plan.  The Council planning process also includes team plans
that focus on short term tactical and operational activities supporting delivery
of the service plan and strategies and Employee Review and Development
Plans (ERDP) provide individual planning for employees’ activities and
development. 
3.3 As well as identifying service developments and improvements, the Service
Plan Framework requires an assessment of the output and outcome
requirements for services based on the Council’s priorities, statutory and
regulatory requirements and other relevant factors and matching of resources
to these priorities. Priority outcomes are those included in the Council’s
Corporate Plan that directly relate to the service or are influenced by the
service and should be clearly identified. 
3.4 Setting clear measurable outcomes and defining key indicators by which
progress will be assessed is a recognised area for development within the
Council and these Service Plans are part of the improvement journey to
implement the Performance Management Framework. For some actions it can
be difficult to identify a measurable outcome (e.g. a change in legislation that
must be implemented, or updating a policy framework). It can also be
challenging where there is currently no clear baseline or benchmarking from
which informed targets and reasonable steps towards these can be
developed. Therefore, as far as possible efforts have been made to set
measurable outcomes for service plan actions but in some cases outputs or
milestones have been used so that it is still possible to measure whether the
action has been progressed as intended. In other areas, further work will be
required to refine outcomes in future. So for example, in some actions,
strategic and delivery planning is not yet concluded and so performance
indicators are not yet agreed. Where possible in such cases milestones are
provided. 
3.5 A summary of progress is given below based on the annual reviews carried
out for each of the service areas. 
3.6  Reference is also made to the report to the Council on 2 February 2023 on
the progress of work to revise the Corporate Plan following the local
government elections in May 2022 and to take account of the issues from the
Covid pandemic that will influence future service requirements and the
Scottish Government programme for government.  The Council agreed that
Service Plans be prepared as normal and that they be further reviewed as
required as part of the normal 6 monthly performance reporting framework to
take account of any revisions and change in direction in the new Corporate
Plan (para 15 of the minute refers).  These plans focus on the period from
April 2023 to April 2024. 
3.8 Economic Growth and Development 
3.8.1 Progress on planned work (success) 
• Production and approval of apprenticeship strategy for the Community
Planning Partnership.
• Production and approval of Community Safety Strategy.
Page 4

Page 5

• Achieved “green” status for building standards performance framework.
• Achieved “green” status for Planning Performance framework.
• Developed programme of work to respond to new NPF4 requirements.
• Obtained Just Transition funding to progress Carbon related feasibility
studies.
• Implemented UK shared Prosperity Fund.
• Finalised European Social Fund projects.
• Climate Change Strategy in delivery and progressing actions within
available resources.
• Progressed Moray Growth Deal with 2 projects now in delivery and 6
projects working towards Full Business Case. 
3.8.2 Progress on planned work (areas for development/not delivered) 
• Establish succession planning by providing training route for
Environmental Health Officers. Work continues on this area. 
3.8.3 Planned focus in new plan (reflecting above and challenges to come) 
• Progressing the Climate Change Strategy and Action Plan
• Delivering Moray Growth Deal
• Progressing community wealth building
• Delivering Town Centre Improvement Works
• Progress with the new Local Development Plan 
3.9 Housing and Property Services 
3.9.1 Progress on planned work (success)   
• Continued work to deliver a reduction in relet time of over 10% and
corresponding void rent loss by reviewing voids processes.
• Successful review of the initial 2019-24 Rapid Rehousing Transition Plan
submitted to the Scottish Government.
• Acquisition of properties through open market and Ministry of Defence.
• Support for the national response to the crisis in Ukraine, ensuring
housing needs continued to be met after initial host arrangements ended.
• Enhanced capacity for Tenant Participation.
• Developed proposals for rent restructure.
• Progressed work on Office Review as part of Smarter Working project.
• Developed an annual review of valuation for the Council’s property asset
portfolio. 
3.9.2 Progress on planned work (areas for development/not delivered) 
• Unable to proceed with elements of industrial estate development in
Forres and Speyside due to site suitability, however this has been re-
profiled within our capital programme for future years to enable further
market analysis and identification.
• Tenant Participation actions were delayed due to recruitment challenges,
however our Customer Engagement Officer is now in post and enhanced
work is underway.
Page 5

Page 6

• Progress with depot review made however project timescale extended
due to capacity issues.
• Service improvements for Repairs systems and Housing Management
have taken longer than anticipated due to absences and management
capacity.   
3.9.3 Planned focus in new plan (reflecting above and challenges to come) 
• A change in technical guidance for Electrical Certification has
necessitated development of a remedial programme that we are currently
investigating.
• Due to budgetary challenges, an in-year review of temporary
accommodation charging was required to avoid a deficit position.
• The service experienced a number of absences of staff in key positions
within the service which impeded progress in a number of key areas. 
Succession planning is being developed to mitigate any future recurrence. 
3.10 Environmental and Commercial Services 
3.10.1 Progress on planned work (success)   
• Lossiemouth East Beach Footbridge opened as planned on 31 May 2022
• Active Travel Strategy approved and in delivery. The pilot participatory
budgeting projects are underway in Buckie and Keith.
• Buckie Harbour infrastructure, legal agreements with Ocean Winds were
finalised in December 2022
• Electric Vehicle Infrastructure Strategy and Expansion Plan drafted and
approved by committee 
3.10.2 Progress on planned work (areas for development/not delivered) 
• Energy from Waste plant, commissioning delayed because of construction
issues. Contingency arrangements have been put in place by the
contractor which saw Moray’s waste continuing to go to Dallachy land fill
site. The plant is due to be commissioned for full operations in August
2023.
• Buckie Harbour Masterplan has been delayed with supplier issues, and
will be delivered early 23/24.
• The roll out of Free School Meals to Primary 6/7 has been delayed by
Scottish Government. 
3.10.3 Planned focus in new plan (reflecting above and challenges to come) 
• Delivery of the Deposit Return Scheme as set out by Scottish Government
in relation to increasing recycling rates of single use drinks containers.
This will also lead into the Extended Producer Responsibilities around
food packaging, the impacts of which for the council are currently being
assessed as information is clarified.
• Further activity to deliver the Climate Change Action Plan 
Service Plans for 2023/24
Page 6

Page 7

3.11  Given the pressures across all services and the need to prioritise resources to
the council’s priorities, services are focussing on essential service delivery
and developments and taking account of the planned review of the Corporate
Plan when undertaking service planning. The three Service Plans are
attached to this report as follows: 
Appendix 1: Economic Growth and Development
Appendix 2: Housing & Property
Appendix 3:  Environmental and Commercial 
4. SUMMARY OF IMPLICATIONS 
a) Corporate Plan and 10 Year Plan (Local Outcomes Improvement
Plan (LOIP)
The Service Plans were informed by the LOIP and the Council’s
Corporate Plan.   
(b) Policy and Legal
Statutory requirements and Council policies are considered by managers
when preparing service plans for the year ahead. 
(c) Financial implications
No additional financial resources beyond those previously reported to
service committees are required to support the Service Plans. 
(d) Risk Implications
Up to date risk registers are maintained and considered as part of the
service planning process. 
(e)  Staffing Implications
Service Plans are integral to good management practice including
workforce planning and assisting with communication about work plans
for staff, identifying priorities and matching staff time to the Council’s
priorities.   
(f) Property
There are no property implications arising from this report. 
(g) Equalities
Managers consider equalities issues for staff and service users when
assessing current service delivery arrangements and future
requirements. 
(h) Climate Change and Biodiversity Impacts
There are no climate change and biodiversity impacts from this report. 
(i) Consultations
Heads of Service have worked with their management teams to
prepare the Services Plans attached as Appendices 1-3 and have
contributed to the updates in this report. 
5. CONCLUSION
Page 7

Page 8

5.1 Service Plans have been prepared identifying the improvements
targeted for the period up to April 2024.  In preparing the plans
managers have taken account of risk, performance data (including
inspections and Best Value), the LOIP, the Corporate Plan and other
relevant factors such as audit and inspection outcomes.  Consideration
has also been given to the longer term impacts of the Covid-19
pandemic and action that is required to respond to them, these
considerations now being embedded in core work. The Service Plans
identify the priority rating ascribed for each action and key performance
measures to enable progress in delivery of core service requirements
and improvements will be tracked. 
Author of Report: Rhona Gunn
Background Papers:  Report to Council on 19 January: Corporate Plan
Preparation  
Report to EDI on 22 March 2022: - Service Plans 2022/23 
Report to Council on 2 February 2023: Corporate Plan 
Ref: SPMAN-1108985784-860 
Page 8

Page 9

APPENDIX 1
SERVICE PLAN Economic Growth and Development
Master: SPMAN-851087866-707 
1. Service Definition:  Economic Growth and Development Service delivers key regulatory services associated with Planning, Building Standards, Environmental Health and Trading Standards and
leads on Economic Development activity and Climate Change : -
Environmental Health and Trading Standards deliver regulatory services for food safety, health and safety, animal health, private water supply, public health, private water supplies,
housing, landlord registration, consumer advice, trading standards, alcohol and tobacco sales.
Development Management and Building Standards manage planning and building standards applications and enforcement activity, both services aim to be self-financing attracting
significant income through the statutory fees associated with applications.
Economic Growth and Regeneration has responsibility for business gateway, external funding including management of European funds, town centre activities, Business improvement
districts, skills and employability. 
Strategic Planning and Delivery is responsible for the Local Development Plan, supporting delivery of Moray Economic Strategy, Moray Growth Deal and associated projects and
programmes and Climate Change. 
2. Service Resources: 96 FTE
Annual Budget 2022/23: Net Revenue £3.4 million 
3. What have we identified for improvement in {Financial Year}? What evidence did we use to identify this improvement? 
Please add benchmark information wherever available and relevant to the improvement.
Sustainable service with sufficient numbers of qualified staff to deliver council priorities
and statutory functions.
Workforce planning data and demographic profile of service, recruitment outcomes and significant shortage
of applicants in some professions, workloads, new works streams and duties, expectations on service levels
and delivery, risk to public health and economy, risk to reputation, budget pressures.
Community Wealth Building Strategy  Government policy and case studies, procurement impacts, supply chain development, economic
assessments.
Climate Change and Biodiversity Route Map for 2030
Assessment of actions completed to date, assessment of available technologies and costs and practicalities
of implementing transition
Town Centre Improvement Plan delivery Town centre improvement plans 
Item 6a)
Page 9

Page 10

APPENDIX 1
SERVICE PLAN Economic Growth and Development
Master: SPMAN-851087866-707 
4. Strategic Outcome
or Priority 
Action  Planned Outcome  Outcome measures  Completion
target 
Lead
Priority Rating
(1 high 3 low and
4 for ongoing, 5
for on hold?)
(L) Developing a diverse,
inclusive & sustainable
economy. (CP) Our Future:
Create a vibrant economy
Delivery of Moray
Growth Deal 
Development and delivery
of Housing Mix Delivery
Project 
Cultural Quarter Project
• Retain and attract
young
people/families
(16-29yrs) to live
and work in the
area
• address
occupational
segregation and
gender inequality in
employment
including the
significant gender
pay gap, and
under-employment
issues for women
• create new high-
quality jobs in
existing sector and
diversify the
region’s economy
into new high value
areas
• create
opportunities
across Moray
which will help
secure the future
prosperity of its
many communities
{Note: the deal
benefits per above
indicators cannot be
measured with any
accuracy until more
projects are well into
delivery hence use of
milestones}   
Full Business Case
Approved
Full Business Case
Approved 
Milestones: 
Quarter 2 23/24 
Quarter 4 23/24
Jim Grant 1
Page 10

Page 11

APPENDIX 1
SERVICE PLAN Economic Growth and Development
Master: SPMAN-851087866-707
(L) Building a better future
for our children & young
people. (CP) Our People:
Opportunity for people to
be the best they can be
Climate Change and
Biodiversity Route Map 
Achievement of targets,
indicators and outcomes
identified in Climate Change
Action Plan: 
Achievement of targets,
indicators and outcomes
identified in Climate Change
Action Plan 
Carbon Neutral Council 
by 2030 
Annual carbon emission
report for Moray Council: 
CLIM1: CO2 emissions
area wide per capita 
CLIM2: CO2 emissions
area wide: emissions within
scope of Local Authority per
capita 
Percentage of completed
actions within the route
map and annual carbon
reporting
Milestones: 2030
overarching target 
Q1 23/24 
annual (Q4 23/24) 
annual (Q4 23/24) 
annual (Q1 23/24)
Gary Templeton 
Page 11

Page 12

APPENDIX 1
SERVICE PLAN Economic Growth and Development
Master: SPMAN-851087866-707 
5. Service Level
Outcomes or Priorities  Action  Planned Outcome  Outcome Measures
Completion
Target  Lead  Priority rating
Environmental Health and
Trading Standards
provision of service
Identify route for training
local Environmental
Health Officers and
associated budget needs 
Ensuring sufficient qualified
staff for the future of the
service 
Report to Committee 
Recruitment of 2 trainee
EHOs 
Milestones: 
June 23 
30/09/23 
KS 1
Economic Growth and
Regeneration
Maximise external
funding for Council
priorities including Town
Centre Improvement
works and employability
embedding a community
wealth building approach
to economic
development.
Business, Skills and
infrastructure investments to
enable economic activity
and retain wealth locally.
Percentage of
unemployed people
assisted into work from
council operated / funded
employability
programmes(LGBF – year
in arrears) 
Additional (external)
Funding awarded to
deliver economic
development focussed
projects (SLAED) 
Percentage of Anchor
procurement spend with
local businesses – local
PI.  
Percentage of contracts
commenced during the
year which have a
community benefit – local
PI. 
Number of business
gateway start-ups per
10,000 population(LGBF –
measured year in arrears) 
Investment in  Economic
Development and Tourism
per 1,000
population(LGBF –
measured year in arrears) 
Proportion of people
earning less than the living
wage(LGBF – measured
year in arrears) 
Measured
annually and
when
LGBMF/SLAED
data available:
31/03/24
KC 1
Page 12

Page 13

APPENDIX 1
SERVICE PLAN Economic Growth and Development
Master: SPMAN-851087866-707
Strategic Planning and
Delivery
Town Centre
Improvement Delivery
Plan and LDP 2027
Developing a diverse,
inclusive and sustainable
economy: By the year 2030
Moray will have a
sustainable and inclusive
economy which generates
improved opportunities for
everyone, including more
skilled and higher paid jobs 
% of LDP delivery plan for
2023/24 complete 
Town Vacancy
Rates(LGBF – year in
arrears) 
Immediately available
employment land as a
percentage of total land
allocated for employment
purposes in the local
development plan(LGBF –
year in arrears) 
External funding achieved
for delivery of strategic
plans associated with
Town Centres and LDP 
Measured
annually and
when LGBMF
data available:
31/03/24
GT 1
Workforce development The service identifies and
secures future needs for
succession planning,
including necessary
apprenticeship/training
opportunities required to
meet future needs,
providing career
pathways including
continuing professional
development and job
specific learning. 
The service improves the
ERDP experience and
holds accurate
records,  including
continuous professional
development (CPD) -
from mandatory training
through to service and
job specific learning
Moray Council can provide
effective services with
sufficient staffing resource
and expertise. 
A more resilient service
capable of growing and
nurturing local talent into
professional service roles. 
Staff and are safe and
competent in their roles as a
result of taking part in
regular and appropriate
continuous professional
development opportunities,
including digital and
customer skills 
Number of staff
progressing in career
graded roles or training
posts. 
% of Professional staff in
Env Health, Planning,
Trading Standards and
Building Standards over
the age of 55. 
Evidence that all staff
have undertaken
mandatory training. 
Number of ERDPs
completed
100% of ERDPs carried
out within timescale 
100% office based staff
completing Customer
Excellence e-learning
module. 
31/03/2024 
March 2024 (and
reviewed
annually) 
March 2024 (and
reviewed
annually) 
March 2024 (and
reviewed
annually) 
JG 1 
Page 13

Page 14

Page 14

Page 15

APPENDIX 2
SERVICE PLAN HOUSING AND PROPERTY SERVICES
Master: SPMAN-851087866-214 
1. Service
Definition: 
Management and maintenance of Council housing stock, local strategic housing function, statutory duties
in relation to homelessness and fuel poverty, development and delivery of the Moray Affordable Housing
Supply Programme (AHSP), maintenance of the Council’s corporate buildings, management of the
Council’s corporate property portfolio and the industrial estate, Building Service DLO, Property Design,
Asset Management and Estates function.
2. Service
Resources:
350.5 FTE employees
Annual Budget 2023/24: £45.2m comprised of Housing Revenue Account (HRA) £22.8m, Building
Services £11.1m, General Services Housing & Property £11.3m 
3. What have we identified for improvement in
{Financial Year}?
What evidence did we use to identify this improvement? 
Please add benchmark information wherever available and
relevant to the improvement.
Smarter Working Project rollout Property Asset Management Appraisal – office review element
Depot & Stores Review Property Asset Management Appraisal – depot and stores review
element
Local Housing Strategy 2024-29
Housing Need & Demand Assessment due to be completed in June
2023 and will inform future strategy. 
Rent Restructure and Rent Setting Policy review
Identified as part of the HRA Business Plan review 2021/22 and initial
review. Evidence that current structure is impeding the programme to
improve stock to EESSH standards. Evidence that current structure
includes inequity and complexity across 386 rent levels. Potential to
develop a fairer, more transparent and sustainable rent structure
which reflects the value tenants place on the quality and specification
of their home.
Item 6a)
Page 15

Page 16

APPENDIX 2
SERVICE PLAN HOUSING AND PROPERTY SERVICES
Master: SPMAN-851087866-214
Systemic Review of Quality and Customer Service for
Housing Repairs 
Informed by volume of tenant and elected member representations
and complaints. Comprehensive review of data including complaints to
inform a systemic action plan for improvement in terms of quality,
value for money and customer satisfaction.  
Revise the Housing Contribution Statement with Health
& Social Care Moray
The Housing Contribution Statement is a statutory requirement
forming part of the IJB Strategic Commissioning Plan.
Improve attainment of EESSH (Energy Efficiency
Standard for Social Housing) and SHQS (Scottish
Housing Quality Standard)
Scottish Housing Regulator and benchmarking data 
Page 16

Page 17

APPENDIX 2
SERVICE PLAN HOUSING AND PROPERTY SERVICES
Master: SPMAN-851087866-214 
4. Strategic
Outcome or
Priority 
Action  Planned
Outcome 
Outcome
measures 
Completion
target 
Lead
Priority
Rating
(1 high 3 low
and 4 for
ongoing, 5
for on hold?)
(L) Improving
Wellbeing of our
population (CP) Our
People: Provide
opportunities for
people to be the best
they can be 
Revise the
Housing
Contribution
Statement with
Health & Social
Care Moray
Assess and
respond to the
housing needs of
older people, in
partnership with
IJB
Over a 3 year
programme an
average of 30% of
affordable homes
at accessible
standard are
delivered 
Achieve strategic
alignment of
allocations,
operations and
development
between the
Council and IJB
31 March 2024 
31 December
2023
Housing
Strategy &
Development
Manager
2
Page 17

Page 18

APPENDIX 2
SERVICE PLAN HOUSING AND PROPERTY SERVICES
Master: SPMAN-851087866-214 
5. Service Level
Outcomes or
Priorities 
Action  Planned
Outcome 
Outcome
Measures
Completion
Target  Lead  Priority
rating
Programme staged
implementation of
the Property Asset
Management
Appraisal (PAMA)
Smarter Working
Project rollout
Improving how
the Council
manages and
maintains its
property assets 
Develop the
organisational
culture, skills and
environment to
embrace and
embed flexible
and hybrid
working
Complete early
adopters pilot in
HQ building 
100% of staff
whose role is
suitable for
hybrid working,
provided with
equipment
to work in a hybrid
style 
Equip 12 small and
5 large fully
operational hybrid
meeting rooms 
Implement smarter
working across HQ
campus.
Milestones:
30 June 2023 
30 June 2023 
30 June 2023 
31 December
2023
Senior
Project
Officer
(Smarter
Working)
2
Programme staged
implementation of
the Property Asset
Management
Appraisal (PAMA)
Depot & Stores
review
Improving how
the Council
manages and
maintains its
property assets 
Initial report to
committee setting
out immediate
objectives and
approach 
Milestones:
30 June 2023 
Property
Asset
Manager
2
Page 18

Page 19

APPENDIX 2
SERVICE PLAN HOUSING AND PROPERTY SERVICES
Master: SPMAN-851087866-214
Develop & report
on OBC 
Report full business
case to Committee 
First Phase
Reduction of
number of depots
by 3 
31 December
2023 
31 March 2024 
31 March 2024
Systemic Review of
Housing Repairs 
Undertake
systemic review
of quality and
customer service
for housing
repairs 
Develop and
implement
improvement
plan.
Increased
customer
satisfaction 
Reduction in
complaints 
Value for money
assurance
Completion of
Process Review &
Improvement Plan 
Implementation of
improvement plan 
Level of complaints
decreased by 10% 
Repairs requiring
follow-up reduced
by 10% 
Milestones: 
30 September
2023 
31 March 2024 
31 March 2024 
31 March 2024
Building
Services
Manager
1
Rent Setting Policy
Review
Undertake review
of rental structure
to ensure it aligns
with business
plan priorities. 
Assurance that
the rent structure
is fair and
sustainable
across the range
of property sizes,
types and
condition and
Review of rental
structure 
Tenant
Engagement on
proposals 
Milestones:
31 March 2023 
30 September
2023 
31 March 2024
Housing
Strategy &
Development
Manager
2
Page 19

Page 20

APPENDIX 2
SERVICE PLAN HOUSING AND PROPERTY SERVICES
Master: SPMAN-851087866-214
Engage with
tenants regarding
review.
enables delivery
of strategic and
regulatory
priorities.
Approval of multi-
year rent
strategy/revised
rental structure. 
Increase
satisfaction with
property condition
for new tenants by
5% 
31 March 2024 
Workforce Training
and Development -
to meet demands
and deliver
priorities
The service
improves the
ERDP
experience and
holds accurate
records, including
continuous
professional
development
(CPD) - from
mandatory
training through
to service and job
specific learning.
Staff are safe and
competent in their
roles as a result
of taking part in
regular and
appropriate
continuous
professional
development
opportunities,
including digital
and customer
skills
Evidence that all
staff have
undertaken
mandatory training. 
Number of ERDPs
completed
100% of ERDPs
carried out within
timescale 
100% office based
staff completing
Customer
Excellence e-
learning module. 
March 2024
(and
reviewed
annually) 
March 2024
(measured
quarterly) 
March 2024
(and
reviewed
annually) 
Head of
Service
2
(L) Developing a
diverse, inclusive &
sustainable
economy. (CP) Our
Continue to
reduce the
carbon impact
arising from
Housing &
Phased
improvement of
energy efficiency
within corporate
Carbon Neutral by
2030 
Reduction in
emissions arising
2030 
31 March
2024 
Property
Asset
Manager
2
Page 20

Page 21

APPENDIX 2
SERVICE PLAN HOUSING AND PROPERTY SERVICES
Master: SPMAN-851087866-214
Future: Create a
vibrant economy
Property
Services
buildings and
housing stock.
from energy
consumption  
against 21/22
baseline of 10,022
tonnes of CO2
(subject to
adjustment for
covid) 
% of houses which
meet EESSH
increased from
baseline of 63.4%
to 80% 
31 March
2024
(L) Improving
Wellbeing of our
population (CP) Our
People: Provide
opportunities for
people to be the
best they can be
Develop the
Local Housing
Strategy 2024-29
Ensure future
housing needs
identified in
Housing Need &
Demand
Assessment are
met, particularly
for priority
groups. 
Conclude and
publish the revised
HNDA 
Identify priorities
arising from the
HNDA and policy
implications 
Delivery of revised
Local Housing
Strategy
Milestones: 
30
September
2023 
31 December
2023 
31 March
2024 
Housing
Strategy &
Development
Manager
2
Page 21

Page 22

Page 22

Page 23

APPENDIX 3  
SERVICE PLAN Environmental and Commercial Services
Master: SPMAN-851087866-214 
1. Service
Definition: 
Environmental and Commercial Services is a diverse service with twenty one discrete functions
delivered by four services: -
Roads Maintenance deliver management and maintenance of public roads, winter maintenance, street
lighting, fleet services.
Environmental Protection manage and maintain all parks, open spaces, core paths, countryside ranger
service, amenity areas and burial grounds  waste/recycling collection, waste disposal, street cleaning,
school meal service, building cleaning and janitorial service for council buildings
Transportation has responsibility for the management of all traffic and road safety functions, street
works co-ordination, active and sustainable travel, transport planning and strategies, off street car
parks, public transport unit PTU, and includes maintenance and operation of 6 harbours including a
dredger.
Consultancy provides civil engineering construction related services including bridge management, road
design, contract management and flood risk.
2. Service
Resources:
Roads Maintenance 137FTE/ Environmental Protection 408.57FTE/Transportation 76.83FTE
Consultancy 13FTE = Total 635.5 FTE 
Annual Budget 2023/24   Capital £16,859,000 Revenue £27,535,693 
3. What have we identified for improvement in
2023-2024
What evidence did we use to identify this improvement? 
Please add benchmark information wherever available and
relevant to the improvement.
Public Car Parks and Council Fleet - Increase
provision and use of electric vehicles and plant with
supporting infrastructure   
Flood Risk Management - Surface Water
Management Plans 
• Moray Council - Climate Change Action Plan 
• Severe weather events due to impact of climate change and the
resilience required to respond to such incidents
(continued) 
Item 6a)
Page 23

Page 24

APPENDIX 3  
SERVICE PLAN Environmental and Commercial Services
Master: SPMAN-851087866-214
3. What have we identified for improvement in
2023-2024
What evidence did we use to identify this improvement? 
Please add benchmark information wherever available and
relevant to the improvement.
(Cont)
We will work to protect and enhance our
environment, creating a more
resilient and sustainable future by: 
• Reducing CO2 emissions by progressing the
transition to the new joint energy waste
facility.   
• Delivering a resilient and sustainable Waste 
Management Service to support  our Climate
Change Strategy 
• Promoting Green and Active travel 
• Improving inspection rates of network bridges 
• Workforce Development to meet demands
and deliver priorities. 
• Achievement of targets, indicators and outcomes identified in
Climate Change Action Plan via reduction in CO2 emissions -
achieving carbon neutrality in terms of the council footprint by
2030
• Government & Zero Waste Scotland targets, “send no more than
5% of remaining waste to            
landfill” and related legislative change 
• Moray Council  - Active Travel Strategy 
• Cycling Action Plan for Scotland commitment that 10% of
everyday journeys will be by bike. 
• Transport Scotland commitment to delivery of 53km of path
network with European Regional Development Fund) ERDF
funding 
• Association for Public Sector Excellence (APSE) Benchmarking
/Public Service Improvement Framework(PSIF) / Key
Performance Indicators 
• Achievement of targets, indicators and outcomes regarding
ERDPs and Customer Satisfaction data.
• (PSIF) assessment of planned service areas
Page 24

Page 25

APPENDIX 3  
SERVICE PLAN Environmental and Commercial Services
Master: SPMAN-851087866-214
3. What have we identified for improvement in
2023-2024
What evidence did we use to identify this improvement? 
Please add benchmark information wherever available and
relevant to the improvement. 
Note: Bold font in Action Column signifies Action has been carried forward from previous year 
4. Strategic
Outcome or
Priority 
Action  Planned
Outcome 
Outcome
measures 
Completion
target 
Lead
Priority
Rating
(1 high 3
low and 4
for ongoing,
5 for on
hold?)
(L) Developing a
diverse, inclusive &
sustainable economy.
(CP) Our Future:
Create a vibrant
economy
.
(4a) i) Increase
provision and
use of electric
vehicles and
plan with
supporting
infrastructure 
Increase
provision and
use of electric
vehicles and
plant with
supporting
infrastructure: 
i)Reduction of
CO2 emissions
in future /
Prioritised list of
locations for
Electric vehicle
charging
investment 
i)Install 80
charging
infrastructure
points at
strategic
locations
throughout
Moray 
Milestones:
1.Completion
of Strategy
2.Approval
3. Installation 
Completion
by 31 March
2024 
Roads
Maintenance
Manager 
2
Page 25

Page 26

APPENDIX 3  
SERVICE PLAN Environmental and Commercial Services
Master: SPMAN-851087866-214 
4. Strategic
Outcome or
Priority 
Action  Planned
Outcome 
Outcome
measures 
Completion
target 
Lead
Priority
Rating
(1 high 3
low and 4
for ongoing,
5 for on
hold?) 
ii)We will make
progress to
decarbonise the
Council Fleet 
ii)Increased
Electric Vehicle
provision to meet
Climate change
targets 2030 
ii)Increase Moray
Council electric
fleet by 
15%   
31 March
2024 
Roads
Maintenance
Manager
2
(L) Developing a
diverse, inclusive &
sustainable economy.
(CP) Our Future:
Create a vibrant
economy
(4b)   We will
implement a
strategy for
public use of
On-Street and
Off- Street (Car
Parks) Charging
Infrastructure. 
Increase
provision and
use of electric
vehicles and
plant with
supporting
infrastructure: 
Reduction of
CO2 emissions
in future /
Prioritised list of
locations for
Electric vehicle 
Increase the total
number of
locations with
direct access to
suitable charging
infrastructure by
10% * 
Milestone:
Strategy
Approved
September
2022 
Transportation
Manager 
2
Page 26

Page 27

APPENDIX 3  
SERVICE PLAN Environmental and Commercial Services
Master: SPMAN-851087866-214 
4. Strategic
Outcome or
Priority 
Action  Planned
Outcome 
Outcome
measures 
Completion
target 
Lead
Priority
Rating
(1 high 3
low and 4
for ongoing,
5 for on
hold?)
charging
investment 
*Note: Ongoing
work to increase
the total number
of locations with
direct access to
suitable charging
infrastructure by
10% by 2025 is
dependent on
funding and the
way electric
vehicle EV
charging
infrastructure is
provided. 
Currently under
review by
Scottish Futures
Trust / Transport
Scotland 
Milestone:
Procured
approach
September 
2023 
10% increase
by 2025* 
Page 27

Page 28

APPENDIX 3  
SERVICE PLAN Environmental and Commercial Services
Master: SPMAN-851087866-214 
4. Strategic
Outcome or
Priority 
Action  Planned
Outcome 
Outcome
measures 
Completion
target 
Lead
Priority
Rating
(1 high 3
low and 4
for ongoing,
5 for on
hold?)
(L) Developing a
diverse, inclusive &
sustainable economy.
(CP) Our Future:
Create a vibrant
economy
(4c) We will
develop Surface
Water
Management
Plans SWMP
Implementing
surface water
infrastructure
improvements in
vulnerable flood
risk areas: 
Reducing the risk
of surface water
flooding to
properties in
vulnerable areas  
Implementing
surface water
infrastructure
improvements in
vulnerable flood
risk areas: 
(levels of risk
and areas to be
identified in
surface water
management
plans) 
New schemes
prioritised in
Local Flood Risk
Management
Plans for 2022 –
2028 will reduce
risk to
Milestones:
Scottish
Water
modelling
review along
with review of
information
provided by
communities
in Forres and
Findhorn by
end 2023/24. 
Draft SWMP
for Forres
and Findhorn
by end
2024/25. 
Schemes
from existing
SWMPs at
Elgin, Buckie,
Keith and
Rothes to be
Consultancy
Manager 
2
Page 28

Page 29

APPENDIX 3  
SERVICE PLAN Environmental and Commercial Services
Master: SPMAN-851087866-214 
4. Strategic
Outcome or
Priority 
Action  Planned
Outcome 
Outcome
measures 
Completion
target 
Lead
Priority
Rating
(1 high 3
low and 4
for ongoing,
5 for on
hold?)
approximately
100 properties in
Moray.) 
developed
after 2026
and 2028
subject to
Scottish
Government
Capital
Funding 
5. Service Level
Outcomes or
Priorities 
Action  Planned
Outcome 
Outcome
Measures
Completion
Target  Lead  Priority
rating
Improving the
Transportation
network
(5a) We will
produce a new
Road Safety Plan
in partnership
with Community
Planning
Partnership
members
5a Safe
transportation
network and
communities.  
Reduction in road
casualties 
( following
implementation of
plan) 
Milestones:
Approval of
Plan-
December 2023 
Note:
Anticipated
Reduction in 
road casualties
in Moray will be
Transportation
Manager 
2
Page 29

Page 30

APPENDIX 3  
SERVICE PLAN Environmental and Commercial Services
Master: SPMAN-851087866-214
5. Service Level
Outcomes or
Priorities 
Action  Planned
Outcome 
Outcome
Measures
Completion
Target  Lead  Priority
rating
confirmed
following
adoption of
Road Safety
Plan
Improving our
operations
(5b) We will
improve the
rate of Principal
Inspections
undertaken
on the Council’s
network
bridges by
reassigning
this work as a top
priority
Principal
Inspections
rate complies
with
legislation (each
network bridge
to be
inspected every
six
years) and
Moray
improves the
inspection rate
to a similar
standard to other
Local
Authorities
63 Principal
Inspections
will be undertaken
each year.   
Benchmarked
improvement in
bridge condition. 
(Data is currently
gathered and reported
to SCOTS Society of
Chief Officers of
Transportation
Scotland and will be
added to performance
reports when
available)
December 2025 Consultancy
Manager
4
Improved Service
Delivery
(5c)Migrate our
current IT asset
management
system to a web
based browser
system with
increased end to
The public
interface will
enable members
of the public /
elected
members to
track progress
Improved
customer
communication
and satisfaction
levels by 5%
End March 2024 Road
Maintenance
Manager
2
Page 30

Page 31

APPENDIX 3  
SERVICE PLAN Environmental and Commercial Services
Master: SPMAN-851087866-214
5. Service Level
Outcomes or
Priorities 
Action  Planned
Outcome 
Outcome
Measures
Completion
Target  Lead  Priority
rating
end mobile
functionality 
(included in IT
delivery plan)
on roads
maintenance
defects on line
with real time
updates of
enquiries.
Harbour
Development /
Climate Change
(5d) We will
enable
infrastructure to
support the Moray
West Wind farm
project 
Additional 3
crew Transfer
vessels
operating from
Buckie Harbour 
Tracking of
detailed planning
stage of the
redevelopment of
the harbour front
including a new
harbour office for
use as the Moray
West wind farm’s
Operational &
Maintenance
base. 
Harbour will also
be redesigned
allowing for the
new pontoons to
cope with the
vessels involved
in the
development work
of the wind farm
and future activity
OW facility to be
built by April
2024 
Milestones
1. Demolition of
harbour
office –15
May 2023 
2. Start work of
new O/M
base – 15 
May 2023
3. Entry to pier
3 – 5 June
2023
4. Pontoon
completion
and
operational
date – 16
October
2023 
Head of Env
and
Commercial
Services
1
Page 31

Page 32

APPENDIX 3  
SERVICE PLAN Environmental and Commercial Services
Master: SPMAN-851087866-214
5. Service Level
Outcomes or
Priorities 
Action  Planned
Outcome 
Outcome
Measures
Completion
Target  Lead  Priority
rating 
Deliver a Buckie
Harbour Master
Plan 
Increased
activity from
supported
supply chain
jobs 
50 new direct jobs
in operation 
5. Construction
of  new
harbour
office
deadline of
completion –
end March
2024 
Milestone:
Delivery of
Buckie Harbour
Master Plan
July 2023 
July 2024
Page 32

Page 33

APPENDIX 3  
SERVICE PLAN Environmental and Commercial Services
Master: SPMAN-851087866-214
5. Service Level
Outcomes or
Priorities 
Action  Planned
Outcome 
Outcome
Measures
Completion
Target  Lead  Priority
rating
Environment/
Climate Change
(5e) We will
progress
the Joint Energy
from
Waste project
with
Aberdeenshire
ASC and
Aberdeen City
Councils ACC
to have a long
term and
sustainable
approach to
waste
management
Increased
efficiency of
Waste
management in
Moray removing
the
reliance on
landfill
operations, in
accordance with
Moray
Council Climate
Change
Strategy and
Action
Plan and Waste
Scotland
Regulations
2012
Diversion of
approximately
23,000
tonnes of residual
waste
from landfill to
energy
recovery per
annum. 
Meet Scottish
Government
target of 5% to
landfill by 2025
Milestones:
27.02.23 –
Waste deliveries
from Aberdeen
City Council 
27.03.23 –
Waste deliveries
from
Aberdeenshire
Council 
24.04.23 –
Waste deliveries
from Moray
Council 
Planned
Facilities
Services
Commencement
Date (Fully
operational per
contract) -
12.08.23 
Head of
Environmental
and
Commercial
Services 
1
Page 33

Page 34

APPENDIX 3  
SERVICE PLAN Environmental and Commercial Services
Master: SPMAN-851087866-214
5. Service Level
Outcomes or
Priorities 
Action  Planned
Outcome 
Outcome
Measures
Completion
Target  Lead  Priority
rating
Environment/
Climate Change
(5f) We will
implement the
deposit return
scheme as
established by
Scottish
Government 
Ensure all
secondary
schools are
complying with
the deposit
return scheme. 
At least50% of
eligible items sold
at school
canteens put
through for
collection
Within 3 months
of
implementation
date  - currently
March 2024 
Environmental
Protection
Manager
4
Environment/
Climate Change
(5g) We will
promote and
develop active
and green travel: 
i)In schools 
i)Increased
awareness and
participation in
active and green
travel in schools   
Objective - 95% of
primary schools
delivering Level 2
Bikeability by
2027. (Current
baseline figures -
75% of primary
schools delivering
2022, with a 67%
completion rate) 
Milestones:
Bikeability
programme to
be delivered
over the next 5
years -  
All measures
complete
December 2025 
Transportation
Manager  2 
Page 34

Page 35

APPENDIX 3  
SERVICE PLAN Environmental and Commercial Services
Master: SPMAN-851087866-214
5. Service Level
Outcomes or
Priorities 
Action  Planned
Outcome 
Outcome
Measures
Completion
Target  Lead  Priority
rating 
ii) We will
undertake a pilot
participatory
budget PB project
to plan and deliver
the elements of
the strategy. 
ii)Communities
are engaged in
the delivery
infrastructure to
support the
Active Travel
Strategy 
Objective - 60% of
all journeys to
school to be
walked, wheeled
or cycled by 2027.
(Current baseline
figures from
HUSS 2021 -
52.3%) 
£50k allocated
and schemes
delivered 
December 2027 
Measured
annually 
31 March 2024 
2
Our Future
Environment
(5h) We will
improve the
condition of
Moray’s core
paths by
implementing the
prioritised core
iii)Improve the
accessibility and
overall condition
of our core paths
network 
Plan approved 
Delivery indicators
set 
Milestones:
June 23 
June 23
Environmental
Protection
Manager
4
Page 35

Page 36

APPENDIX 3  
SERVICE PLAN Environmental and Commercial Services
Master: SPMAN-851087866-214
5. Service Level
Outcomes or
Priorities 
Action  Planned
Outcome 
Outcome
Measures
Completion
Target  Lead  Priority
rating
path action plan
(2023 -2026) 
Improving our
operations
(5i) We will
continue to work
towards
increasing our
overall recycling
performance by
regular
engagement with
residents and
commercial
customers
through waste
specific PR
campaigns. 
Recycling
targets to
increase
performance -
Regular reviews
of quarterly
SEPA site
returns and
Waste Data
Flow
submissions will
be used to
identify priority
areas. 
60 % overall
recycling
performance
achieved.   
Government
Waste targets
achieved 
Confirmed
annual recycling
rates for Local
Authorities
published by
SEPA around
September each
year for the
previous year,
for inclusion in
Q4 reports.
Environmental
Protection
Manager
4
Page 36

Page 37

APPENDIX 3  
SERVICE PLAN Environmental and Commercial Services
Master: SPMAN-851087866-214
5. Service Level
Outcomes or
Priorities 
Action  Planned
Outcome 
Outcome
Measures
Completion
Target  Lead  Priority
rating
Improving our
operations
(5j)  Catering -
We will improve
the school
service and
deliver healthier
and more
sustainable
school meals. 
We will improve
our uptake of
Universal Free
school meals
and comply with
the Food and
Drink in Schools
(Scotland)
Regulations 
Improved uptake
of Primary school
meals:
78% target
achieved 
(Current baseline
2022/23 -75%)
March 2024  Environmental
Protection
Manager
4
Delivering capital
projects
(5k) We will
upgrade at least
two play areas
per year and
engage with our
communities
through
participatory
budgeting
influence
expenditure and
Enhanced local
play
environment
At least two
upgraded play
areas per year.
Completion: 31
March 2025 
Milestone: 31
March 2024 
Environmental
Protection
Manager
4
Page 37

Page 38

APPENDIX 3  
SERVICE PLAN Environmental and Commercial Services
Master: SPMAN-851087866-214
5. Service Level
Outcomes or
Priorities 
Action  Planned
Outcome 
Outcome
Measures
Completion
Target  Lead  Priority
rating
design of
upgrades. 
Workforce
Development - to
meet demands
and deliver
priorities 
(5li)The service
improves the
ERDP experience
and holds
accurate
records,  including
continuous
professional
development
(CPD) - from
mandatory training
through to service
and job specific
learning 
Staff and are
safe and
competent in
their roles as a
result of taking
part in regular
and appropriate
continuous
professional
development
opportunities,
including digital
and customer
skills 
Evidence that all
staff have
undertaken
mandatory
training. 
Number of ERDPs
completed
100% of ERDPs
carried out within
timescale 
100% office based
staff completing
Customer
Excellence e-
learning module. 
March 2024
(and reviewed
annually) 
March 2024
(and reviewed
annually) 
March 2024
(and reviewed
annually) 
Head of
Service 
2
Page 38

Page 39

APPENDIX 3  
SERVICE PLAN Environmental and Commercial Services
Master: SPMAN-851087866-214
5. Service Level
Outcomes or
Priorities 
Action  Planned
Outcome 
Outcome
Measures
Completion
Target  Lead  Priority
rating
(5lii) Continuous
Improvement -
We will
undertake a staff
led self-
assessment of
our service
activities and
customer results
using the PSIF
model ( Public
Service
Improvement
Framework)
Results from this
self-assessment
will allow for long
term
improvements to
the section to be
identified via a
targeted Action
Plan 
Progress areas of
PSIF assessment
within the service
as per
programme. 
Milestone1 – One
new Service
Assessment
Complete to Plan 
Milestone 2-
Action Plan for
2023/ 24 complete 
Dec 2023 
March 2024 
Page 39

Page 40

Page 40

Page 41

APPENDIX 3  
SERVICE PLAN Environmental and Commercial Services
Master: SPMAN-851087866-214 
1. Service
Definition: 
Environmental and Commercial Services is a diverse service with twenty one discrete functions
delivered by four services: -
Roads Maintenance deliver management and maintenance of public roads, winter maintenance, street
lighting, fleet services.
Environmental Protection manage and maintain all parks, open spaces, core paths, countryside ranger
service, amenity areas and burial grounds  waste/recycling collection, waste disposal, street cleaning,
school meal service, building cleaning and janitorial service for council buildings
Transportation has responsibility for the management of all traffic and road safety functions, street
works co-ordination, active and sustainable travel, transport planning and strategies, off street car
parks, public transport unit PTU, and includes maintenance and operation of 6 harbours including a
dredger.
Consultancy provides civil engineering construction related services including bridge management, road
design, contract management and flood risk.
2. Service
Resources:
Roads Maintenance 137FTE/ Environmental Protection 408.57FTE/Transportation 76.83FTE
Consultancy 13FTE = Total 635.5 FTE 
Annual Budget 2023/24   Capital £16,859,000 Revenue £27,535,693 
3. What have we identified for improvement in
2023-2024
What evidence did we use to identify this improvement? 
Please add benchmark information wherever available and
relevant to the improvement.
Public Car Parks and Council Fleet - Increase
provision and use of electric vehicles and plant with
supporting infrastructure   
Flood Risk Management - Surface Water
Management Plans 
• Moray Council - Climate Change Action Plan 
• Severe weather events due to impact of climate change and the
resilience required to respond to such incidents
(continued) 
Item 6a)
Page 41

Page 42

APPENDIX 3  
SERVICE PLAN Environmental and Commercial Services
Master: SPMAN-851087866-214
3. What have we identified for improvement in
2023-2024
What evidence did we use to identify this improvement? 
Please add benchmark information wherever available and
relevant to the improvement.
(Cont)
We will work to protect and enhance our
environment, creating a more
resilient and sustainable future by: 
• Reducing CO2 emissions by progressing the
transition to the new joint energy waste
facility.   
• Delivering a resilient and sustainable Waste 
Management Service to support  our Climate
Change Strategy 
• Promoting Green and Active travel 
• Improving inspection rates of network bridges 
• Workforce Development to meet demands
and deliver priorities. 
• Achievement of targets, indicators and outcomes identified in
Climate Change Action Plan via reduction in CO2 emissions -
achieving carbon neutrality in terms of the council footprint by
2030
• Government & Zero Waste Scotland targets, “send no more than
5% of remaining waste to            
landfill” and related legislative change 
• Moray Council  - Active Travel Strategy 
• Cycling Action Plan for Scotland commitment that 10% of
everyday journeys will be by bike. 
• Transport Scotland commitment to delivery of 53km of path
network with European Regional Development Fund) ERDF
funding 
• Association for Public Sector Excellence (APSE) Benchmarking
/Public Service Improvement Framework(PSIF) / Key
Performance Indicators 
• Achievement of targets, indicators and outcomes regarding
ERDPs and Customer Satisfaction data.
• (PSIF) assessment of planned service areas
Note: Bold font in Action Column signifies Action has been carried forward from previous year
Page 42

Page 43

APPENDIX 3  
SERVICE PLAN Environmental and Commercial Services
Master: SPMAN-851087866-214 
4. Strategic
Outcome or
Priority 
Action  Planned
Outcome 
Outcome
measures 
Completion
target 
Lead
Priority
Rating
(1 high 3
low and 4
for ongoing,
5 for on
hold?)
(L) Developing a
diverse, inclusive &
sustainable economy.
(CP) Our Future:
Create a vibrant
economy
.
(4a) i) Increase
provision and
use of electric
vehicles and
plan with
supporting
infrastructure 
ii)We will make
progress to
decarbonise the
Council Fleet 
Increase
provision and
use of electric
vehicles and
plant with
supporting
infrastructure: 
i)Reduction of
CO2 emissions
in future /
Prioritised list of
locations for
Electric vehicle
charging
investment 
ii)Increased
Electric Vehicle
provision to meet
Climate change
targets 2030 
i)Install 80
charging
infrastructure
points at
strategic
locations
throughout
Moray 
ii)Increase Moray
Council electric
fleet by 
15%   
Milestones:
1.Completion
of Strategy
2.Approval
3. Installation 
Completion
by 31 March
2024 
31 March
2024 
Roads
Maintenance
Manager 
Roads
Maintenance
Manager 
2
2
Page 43

Page 44

APPENDIX 3  
SERVICE PLAN Environmental and Commercial Services
Master: SPMAN-851087866-214 
4. Strategic
Outcome or
Priority 
Action  Planned
Outcome 
Outcome
measures 
Completion
target 
Lead
Priority
Rating
(1 high 3
low and 4
for ongoing,
5 for on
hold?)
(L) Developing a
diverse, inclusive &
sustainable economy.
(CP) Our Future:
Create a vibrant
economy
(4b)   We will
implement a
strategy for
public use of
On-Street and
Off- Street (Car
Parks) Charging
Infrastructure. 
Increase
provision and
use of electric
vehicles and
plant with
supporting
infrastructure: 
Reduction of
CO2 emissions
in future /
Prioritised list of
locations for
Electric vehicle
charging
investment 
Increase the total
number of
locations with
direct access to
suitable charging
infrastructure by
10% * 
*Note: Ongoing
work to increase
the total number
of locations with
direct access to
suitable charging
infrastructure by 
Milestone:
Strategy
Approved
September
2022 
Milestone:
Procured
approach
September 
2023 
10% increase
by 2025* 
Transportation
Manager 
2
Page 44

Page 45

APPENDIX 3  
SERVICE PLAN Environmental and Commercial Services
Master: SPMAN-851087866-214 
4. Strategic
Outcome or
Priority 
Action  Planned
Outcome 
Outcome
measures 
Completion
target 
Lead
Priority
Rating
(1 high 3
low and 4
for ongoing,
5 for on
hold?)
10% by 2025 is
dependent on
funding and the
way electric
vehicle EV
charging
infrastructure is
provided. 
Currently under
review by
Scottish Futures
Trust / Transport
Scotland 
(L) Developing a
diverse, inclusive &
sustainable economy.
(CP) Our Future:
Create a vibrant
economy
(4c) We will
develop Surface
Water
Management
Plans SWMP
Implementing
surface water
infrastructure
improvements in
vulnerable flood
risk areas: 
Reducing the risk
of surface water
flooding to
Implementing
surface water
infrastructure
improvements in
vulnerable flood
risk areas: 
(levels of risk
and areas to be
identified in
surface water
Milestones:
Scottish
Water
modelling
review along
with review of
information
provided by
communities
in Forres and
Consultancy
Manager 
2
Page 45

Page 46

APPENDIX 3  
SERVICE PLAN Environmental and Commercial Services
Master: SPMAN-851087866-214 
4. Strategic
Outcome or
Priority 
Action  Planned
Outcome 
Outcome
measures 
Completion
target 
Lead
Priority
Rating
(1 high 3
low and 4
for ongoing,
5 for on
hold?)
properties in
vulnerable areas  
management
plans) 
New schemes
prioritised in
Local Flood Risk
Management
Plans for 2022 –
2028 will reduce
risk to
approximately
100 properties in
Moray.) 
Findhorn by
end 2023/24. 
Draft SWMP
for Forres
and Findhorn
by end
2024/25. 
Schemes
from existing
SWMPs at
Elgin, Buckie,
Keith and
Rothes to be
developed
after 2026
and 2028
subject to
Scottish
Government
Capital
Funding 
Page 46

Page 47

APPENDIX 3  
SERVICE PLAN Environmental and Commercial Services
Master: SPMAN-851087866-214
5. Service Level
Outcomes or
Priorities 
Action  Planned
Outcome 
Outcome
Measures
Completion
Target  Lead  Priority
rating
Improving the
Transportation
network
(5a) We will
produce a new
Road Safety Plan
in partnership
with Community
Planning
Partnership
members
5a Safe
transportation
network and
communities.  
Reduction in road
casualties 
( following
implementation of
plan) 
Milestones:
Approval of
Plan-
December 2023 
Note:
Anticipated
Reduction in 
road casualties
in Moray will be
confirmed
following
adoption of
Road Safety
Plan
Transportation
Manager 
2
Improving our
operations
(5b) We will
improve the
rate of Principal
Inspections
undertaken
on the Council’s
network
bridges by
reassigning
this work as a top
priority
Principal
Inspections
rate complies
with
legislation (each
network bridge
to be
inspected every
six
years) and
Moray
63 Principal
Inspections
will be undertaken
each year.   
Benchmarked
improvement in
bridge condition. 
(Data is currently
gathered and reported
to SCOTS Society of
Chief Officers of
Transportation
December 2025 Consultancy
Manager
4
Page 47

Page 48

APPENDIX 3  
SERVICE PLAN Environmental and Commercial Services
Master: SPMAN-851087866-214
5. Service Level
Outcomes or
Priorities 
Action  Planned
Outcome 
Outcome
Measures
Completion
Target  Lead  Priority
rating
improves the
inspection rate
to a similar
standard to other
Local
Authorities
Scotland and will be
added to performance
reports when
available)
Improved Service
Delivery
(5c)Migrate our
current IT asset
management
system to a web
based browser
system with
increased end to
end mobile
functionality 
(included in IT
delivery plan)
The public
interface will
enable members
of the public /
elected
members to
track progress
on roads
maintenance
defects on line
with real time
updates of
enquiries.
Improved
customer
communication
and satisfaction
levels by 5%
End March 2024 Road
Maintenance
Manager
2
Harbour
Development /
Climate Change
(5d) We will
enable
infrastructure to
support the Moray
West Wind farm
project 
Additional 3
crew Transfer
vessels
operating from
Buckie Harbour 
Tracking of
detailed planning
stage of the
redevelopment of
the harbour front
including a new
harbour office for
use as the Moray
West wind farm’s
Operational &
OW facility to be
built by April
2024 
Milestones
1. Demolition of
harbour
office –15
May 2023 
Head of Env
and
Commercial
Services
1
Page 48

Page 49

APPENDIX 3  
SERVICE PLAN Environmental and Commercial Services
Master: SPMAN-851087866-214
5. Service Level
Outcomes or
Priorities 
Action  Planned
Outcome 
Outcome
Measures
Completion
Target  Lead  Priority
rating 
Deliver a Buckie
Harbour Master
Plan 
Increased
activity from
supported
supply chain
jobs 
Maintenance
base. 
Harbour will also
be redesigned
allowing for the
new pontoons to
cope with the
vessels involved
in the
development work
of the wind farm
and future activity 
50 new direct jobs
in operation 
2. Start work of
new O/M
base – 15 
May 2023
3. Entry to pier
3 – 5 June
2023
4. Pontoon
completion
and
operational
date – 16
October
2023 
5. Construction
of  new
harbour
office
deadline of
completion –
end March
2024 
Milestone:
Delivery of
Buckie Harbour
Master Plan
July 2023 
Page 49

Page 50

APPENDIX 3  
SERVICE PLAN Environmental and Commercial Services
Master: SPMAN-851087866-214
5. Service Level
Outcomes or
Priorities 
Action  Planned
Outcome 
Outcome
Measures
Completion
Target  Lead  Priority
rating  
July 2024
Environment/
Climate Change
(5e) We will
progress
the Joint Energy
from
Waste project
with
Aberdeenshire
ASC and
Aberdeen City
Councils ACC
to have a long
term and
sustainable
approach to
waste
management
Increased
efficiency of
Waste
management in
Moray removing
the
reliance on
landfill
operations, in
accordance with
Moray
Council Climate
Change
Strategy and
Action
Plan and Waste
Scotland
Regulations
2012
Diversion of
approximately
23,000
tonnes of residual
waste
from landfill to
energy
recovery per
annum. 
Meet Scottish
Government
target of 5% to
landfill by 2025
Milestones:
27.02.23 –
Waste deliveries
from Aberdeen
City Council 
27.03.23 –
Waste deliveries
from
Aberdeenshire
Council 
24.04.23 –
Waste deliveries
from Moray
Council 
Planned
Facilities
Services
Commencement
Date (Fully
operational per
Head of
Environmental
and
Commercial
Services 
1
Page 50

Page 51

APPENDIX 3  
SERVICE PLAN Environmental and Commercial Services
Master: SPMAN-851087866-214
5. Service Level
Outcomes or
Priorities 
Action  Planned
Outcome 
Outcome
Measures
Completion
Target  Lead  Priority
rating
contract) -
12.08.23 
Environment/
Climate Change
(5f) We will
implement the
deposit return
scheme as
established by
Scottish
Government 
Ensure all
secondary
schools are
complying with
the deposit
return scheme. 
At least50% of
eligible items sold
at school
canteens put
through for
collection
Within 3 months
of
implementation
date  - currently
March 2024 
Environmental
Protection
Manager
4
Environment/
Climate Change
(5g) We will
promote and
develop active
and green travel: 
i)In schools 
i)Increased
awareness and
participation in
active and green
travel in schools   
Objective - 95% of
primary schools
delivering Level 2
Bikeability by
2027. (Current
baseline figures -
75% of primary
schools delivering 
Milestones:
Bikeability
programme to
be delivered
over the next 5
years -  
All measures
complete
December 2025 
Transportation
Manager  2 
Page 51

Page 52

APPENDIX 3  
SERVICE PLAN Environmental and Commercial Services
Master: SPMAN-851087866-214
5. Service Level
Outcomes or
Priorities 
Action  Planned
Outcome 
Outcome
Measures
Completion
Target  Lead  Priority
rating 
ii) We will
undertake a pilot
participatory
budget PB project
to plan and deliver
the elements of
the strategy. 
ii)Communities
are engaged in
the delivery
infrastructure to
support the
Active Travel
Strategy 
2022, with a 67%
completion rate) 
Objective - 60% of
all journeys to
school to be
walked, wheeled
or cycled by 2027.
(Current baseline
figures from
HUSS 2021 -
52.3%) 
£50k allocated
and schemes
delivered 
December 2027 
Measured
annually 
31 March 2024  2 
Our Future
Environment
(5h) We will
improve the
condition of
Moray’s core
paths by
iii)Improve the
accessibility and
overall condition
of our core paths
network 
Plan approved 
Milestones:
June 23 
Environmental
Protection
Manager
4
Page 52

Page 53

APPENDIX 3  
SERVICE PLAN Environmental and Commercial Services
Master: SPMAN-851087866-214
5. Service Level
Outcomes or
Priorities 
Action  Planned
Outcome 
Outcome
Measures
Completion
Target  Lead  Priority
rating
implementing the
prioritised core
path action plan
(2023 -2026)
Delivery indicators
set 
June 23
Improving our
operations
(5i) We will
continue to work
towards
increasing our
overall recycling
performance by
regular
engagement with
residents and
commercial
customers
through waste
specific PR
campaigns. 
Recycling
targets to
increase
performance -
Regular reviews
of quarterly
SEPA site
returns and
Waste Data
Flow
submissions will
be used to
identify priority
areas. 
60 % overall
recycling
performance
achieved.   
Government
Waste targets
achieved 
Confirmed
annual recycling
rates for Local
Authorities
published by
SEPA around
September each
year for the
previous year,
for inclusion in
Q4 reports.
Environmental
Protection
Manager
4
Page 53

Page 54

APPENDIX 3  
SERVICE PLAN Environmental and Commercial Services
Master: SPMAN-851087866-214
5. Service Level
Outcomes or
Priorities 
Action  Planned
Outcome 
Outcome
Measures
Completion
Target  Lead  Priority
rating
Improving our
operations
(5j)  Catering -
We will improve
the school
service and
deliver healthier
and more
sustainable
school meals. 
We will improve
our uptake of
Universal Free
school meals
and comply with
the Food and
Drink in Schools
(Scotland)
Regulations 
Improved uptake
of Primary school
meals:
78% target
achieved 
(Current baseline
2022/23 -75%)
March 2024  Environmental
Protection
Manager
4
Delivering capital
projects
(5k) We will
upgrade at least
two play areas
per year and
engage with our
communities
through
participatory
budgeting
influence
expenditure and
Enhanced local
play
environment
At least two
upgraded play
areas per year.
Completion: 31
March 2025 
Milestone: 31
March 2024 
Environmental
Protection
Manager
4
Page 54

Page 55

APPENDIX 3  
SERVICE PLAN Environmental and Commercial Services
Master: SPMAN-851087866-214
5. Service Level
Outcomes or
Priorities 
Action  Planned
Outcome 
Outcome
Measures
Completion
Target  Lead  Priority
rating
design of
upgrades. 
Workforce
Development - to
meet demands
and deliver
priorities 
(5li)The service
improves the
ERDP experience
and holds
accurate
records,  including
continuous
professional
development
(CPD) - from
mandatory training
through to service
and job specific
learning 
Staff and are
safe and
competent in
their roles as a
result of taking
part in regular
and appropriate
continuous
professional
development
opportunities,
including digital
and customer
skills 
Evidence that all
staff have
undertaken
mandatory
training. 
Number of ERDPs
completed
100% of ERDPs
carried out within
timescale 
100% office based
staff completing
Customer
Excellence e-
learning module. 
March 2024
(and reviewed
annually) 
March 2024
(and reviewed
annually) 
March 2024
(and reviewed
annually) 
Head of
Service 
2
Page 55

Page 56

APPENDIX 3  
SERVICE PLAN Environmental and Commercial Services
Master: SPMAN-851087866-214
5. Service Level
Outcomes or
Priorities 
Action  Planned
Outcome 
Outcome
Measures
Completion
Target  Lead  Priority
rating
(5lii) Continuous
Improvement -
We will
undertake a staff
led self-
assessment of
our service
activities and
customer results
using the PSIF
model ( Public
Service
Improvement
Framework)
Results from this
self-assessment
will allow for long
term
improvements to
the section to be
identified via a
targeted Action
Plan 
Progress areas of
PSIF assessment
within the service
as per
programme. 
Milestone1 – One
new Service
Assessment
Complete to Plan 
Milestone 2-
Action Plan for
2023/ 24 complete 
Dec 2023 
March 2024 
Page 56

Page 57

REPORT TO: ECONOMIC DEVELOPMENT AND INFRASTRUCTURE
SERVICES COMMITTEE ON 2 MAY 2023 
SUBJECT: ECONOMIC RECOVERY PLAN DELIVERY 2022/23 
BY:  DEPUTE CHIEF EXECUTIVE (ECONOMY, ENVIRONMENT AND
FINANCE) 
1. REASON FOR REPORT 
1.1 To provide Committee with an overview of economic development activity
delivered during the 2022/23 financial year, as set out within the Economic
Recovery Plan. 
1.2 This report is submitted to Committee in terms of Section III (F) (2) of the
Council's Scheme of Administration relating to the exercise of functions that
promote economic development. 
2. RECOMMENDATION 
2.1  It is recommended that Committee:- 
(i) acknowledge the positive impact of the Economic Recovery Plan in 
minimising the negative effects of the pandemic upon the local 
economy; and 
(ii) agree that this be accepted as the final report covering the delivery 
of the Economic Recovery Plan. 
3. BACKGROUND 
3.1 Moray Economic Partnership (MEP) provides leadership and strategic
direction for the economic component of the Community Planning
Partnership. The economic partnership members are Moray
Council, Highlands and Islands Enterprise (HIE), UHI Moray, Skills
Development Scotland (SDS), Moray Chamber of Commerce (MCC), Visit
Moray Speyside (VMS), Federation of Small Business (FSB) and tsiMORAY.
The partners each act as economic development agencies with key individual
influences on the local economy. This influence is enhanced through acting in
cooperation in the implementation of the Moray Economic Strategy.
Item 6b)
Page 57

Page 58

3.2 To minimise the local economic shock from COVID-19, MEP established an
Economic Recovery Plan for the region. The plan set out a range of business
support initiatives to stimulate the economy and sustain businesses
vulnerable to the effects of the pandemic. The Economic Recovery Plan was
developed around the principles of: 
• Smart growth: placing business resilience at the heart of the recovery
• Clean growth: supporting the transition towards net zero
• Inclusive growth: addressing local inequalities
• Fair work: providing security and equality of opportunity for all
employees 
• Targeting disadvantage: providing targeted support to vulnerable
groups
• Smart procurement: maximising local impact through public spend 
3.3 This high level economic development action plan was approved by the
Economic Growth, Housing and Environmental Sustainability Committee, at
its meeting on 6 October 2020 (paragraph 9 of the minute refers). The
Economic Recovery Plan outlined a range of actions aimed at facilitating the
recovery of the economy, to be delivered across the MEP membership. The
following sections of the report provide an overview of the actions delivered to
date, with a specific focus on the previous financial year. 
4. BUSINESS GRANTS AND START UP SUPPORT 
(Activities led by) Business Gateway and HIE 
4.1 The DigitalBoost programme, funded by Scottish Government and delivered
via Business Gateway, has continued to provide specialist digital support to
businesses throughout Scotland. There have been 3x 18 hour digital projects
completed with Moray businesses since the programme commenced, plus 6x
1 hour digital surgeries. Up to the end of January 2023, there were 133 Moray
attendees across the wide range of DigitalBoost webinars. However, the
DigitalBoost Development Grant, available during 2021/22, was not available
this financial year. 
4.2 Across the entire Highlands and Islands region, £1m was available through
the Young Company Capital Investment Scheme to support emerging
businesses. However, this was a short life scheme, and therefore not
delivered during 2022/23. A total of 6 businesses in Moray received support
via this fund to a total aid value of £91,771. 
4.3 HIE has delivered a further Young Business Capital Scheme during 2022/23.
In Moray, there were a further 2 additional business supported via this HIE
discretionary fund to a total aid value of £107,875. 
4.4 A regional budget of £0.5m was made available for ecommerce funding
support through HIE. The vast majority of this fund was spent during 2021/22
with a small amount of underspend available for 2022/23. However, none of
this underspend was awarded to Moray organisations. There were 9 Moray
businesses that benefited from this funding scheme.
Page 58

Page 59

5. SMALL BUSINESS SUPPORT 
Business Gateway and HIE 
5.1 Business growth and resilience has suffered as a result of the pandemic,
resulting in fewer business start-ups. This is evidenced in the Scottish Local
Authority Economic Development (SLAED) Indicator Framework Report,
provided separately, which confirms that the number of Business Start-ups
per 10,000 people in Moray has stagnated over the past two years, after
having declined at beginning of the pandemic. To attempt to address this a
number of actions were included within the Economic Recovery Plan to
support small businesses. 
5.2 The procurement consultancy initiative introduced as part of the Economic
Recovery Plan continued to support Moray based businesses. The two year
programme ran until 31st December 2022 and provided assistance with
Public Contract Scotland (PCS) registration and tender preparation including
1-2-1 support with writing and submitting a tender bid. 6.5 days of
procurement support were delivered to local businesses via this programme
across its full duration. However, there was no additional uptake on the
procurement consultancy during the 2022/23 financial year. 
5.3 Additionally, a consultancy programme to mitigate the impacts of Brexit was
also delivered via Business Gateway (BG). The Brexit consultancy initiative
was also introduced as part of the Economic Recovery Plan and ran for the
same period until 31st December 2022, providing support with exporting to
mitigate the impacts of Brexit. 33.5 days of this specialist support was
delivered to local businesses throughout this time. 
5.4 As also reported in the SLAED Indicator Framework Report, the number of
unique customer accounts with BG has rebounded. This demonstrates that
while business start-up numbers may remain below pre-pandemic levels,
there is growing interest in entrepreneurial activity. 
5.5 Through its business-as-usual remit, HIE’s Moray Team has supported 12
new investments to 3rd party organisations at varying intervention levels to the
value of £1.12M, contributing towards total project costs of £6.37m. These
projects have:
• Supported 100 jobs
• Increasing turnover by a cumulative £34.7m
• Grown international sales by £16m 
5.6 In addition to new approvals, HIE in Moray has been spending across 85
investments in total which takes in carry over commitment from previous
years’ approvals to a total spend of £2.32m. 
5.7 HIE have also continued to support the two project posts recruited to support
the delivery of the Destination Marketing Organisation (DMO) Recovery
project. HIE hosted a 2-day DMO Network Event for DMO’s across the
Highlands and Islands in October 2022. The HIE Moray Team has also
supported the delivery of a Strategy Workshop for Visit Moray Speyside with a
Page 59

Page 60

focus on development of a new 5 Year Strategy to ensure the sustainability of
the organisation post the DMO Recovery project. 
5.8 The Economic Growth and Regeneration Team administered a Discretionary
Business Support Fund with a budget of £400,000, which was allocated from
the COVID-19 Economic Recovery Fund. This was set up to provide financial
assistance to businesses from Hospitality and Leisure including Retailers that
offer Hospitality, Supply Chains, Events and Close Contact sectors that were
affected by the December 2021/January 2022 COVID-19 measures. To be
eligible for the one-off grant of £6,000, the businesses had to show that they
had been unable to get financial support from any of the administrative public
bodies since December 2021. 113 businesses applied for the fund and 33
were assessed as eligible and a total of £198,000 in grants was approved. An
underspend of £202,000 was re-allocated between the Flexible Food Fund
(£162,000) and a Sport and Culture Hardship Fund (£40,000). 
6. TOWN CENTRES 
Moray Council 
6.1 As part of the Economic Recovery Action Plan, Moray Council allocated
£50,000 to set-up and develop a Pop-up Shop Scheme and £100,000 to offer
50% capital start-up grants to a maximum value of £10,000, following
participation in the scheme. Expression of interest forms were submitted by
38 new or existing businesses and 84 enquiries were received from those
interested in learning more about the scheme. Three pop-up shops launched
in Moray and six businesses took part in the scheme, helping to bring vacant
properties back into use and increase footfall in town centres. In May 2022
one of the properties in Buckie secured a tenant and withdrew from the
scheme. The Business Gateway premises on Elgin High Street was then
repurposed for use as a pop-up shop in October 2022 and three businesses
occupied the shop until the scheme ended in January 2023. There was no
uptake in the capital start-up grant linked to the Pop-up Shop Scheme. A local
social enterprise had been commissioned to assist with promotional activities
but this did not proceed due to delays with the scheme. Therefore, part of the
budget that had been allocated to this element of the project was unspent,
resulting in a final project spend of £12,043. 
6.2 A programme of Town Centre Improvement Plans are continuing to be
developed following community consultation. The Council commitment of
£200,000 has been carried over into 2023/24 as a revenue budget was
required for the design work to be able to deliver on the capital works. There
was insufficient internal staff resource to deliver the projects, though this has
now been secured through another fund for the next financial year. 
6.3 Development Management and Building Standards have continued to enable
town centre development through the provision of additional support, including
free pre enquiry advice. There is a dedicated point of contact for Elgin town
centre with Elgin BID, for coordinating and arranging meetings across
services in Environmental Health, Building Standards and Planning to assist
with free pre-application advice prior to formal submission. There is a duty
Page 60

Page 61

officer available for Planning and Building Standards, where free advice is
available for residential enquiries. Development Management also offer
guidance to small businesses through the desk duty service in terms of
guiding them though the consenting process. Additionally, Development
Management have given pre-application advice and support to Moray Growth
Deal projects. A Senior Planning Officer has served as the designated contact
over the past 12 months. 
6.4 The overall £1,676,000 Town Centre Capital Fund was allocated to 68
projects. The original expenditure deadline of March 2021 for works to be
completed or at least contracts signed was extended to 31 March 2023, due
to the current economic climate and the impacts of COVID-19. To date
£1,096,148.52 of the fund has been spent and £579,851.48 has been
committed; 42 projects have been completed, 6 started and 20 have
committed funds with the intention that the works will be completed and the
grants spent in full before the end of 2023/2024 ensuring the original
outcomes of the fund will be met. 
6.5 £410,000 of the COVID-19 Economic Recovery Fund was allocated to the
Town Centre Capital Business Improvement and Town Centre Capital
Business Start-up funds. The aim of these being to provide investment that
would drive local economic activities and repurpose town centres to become
more diverse, successful and sustainable. Town Centre Capital Business
Improvements Grants were made available for inside and outside work to
create a COVID safe environment and improve the attractiveness of the
business to encourage people to shop local and the create greater footfall.
The fund provided grants at an intervention of 75% up to a maximum of
£15,000 to reflect that most businesses have little reserves left as a result of
the pandemic. In total 38 businesses were awarded grants totalling £346,000.
The purpose of the Town Centre Capital Business Start-up Grants was to
offer capital start-up grants to applicants to allow start-up businesses access
to capital funding which would not otherwise be available. The grants were
offered at an intervention rate of 50% up to a maximum of £10,000 for new
businesses wishing to set up a permanent base in any town centre in Moray.
6 start-up businesses were awarded £51,830. 
6.6 The Local Development Plan delivery programme was allocated a budget of
£70,000, which supported the development of Town Centre Improvement
Plans. In the current year, this has also allowed the commissioning of a
Business and Property Needs Study and Woodland and Forest Strategy. Both
of which will be reported to the Planning and Regulatory Services Committee
later in 2023. 
7. HOUSING AND INFRASTRUCTURE 
HIE, UHI Moray, and Moray Council 
7.1 Delivery of the Strategic Housing Investment Plan over the next 2 years will
provide 199 affordable homes with at a cost of approximately £20m per year
via investment from Scottish Government, Housing Revenue Account (HRA)
and Registered Social Landlords (RSL).
Page 61

Page 62

7.2 High level business cases for the purchase and development of employment
land in Speyside/East Moray and Forres were approved by the Asset
Management Working Group in November 2021. However, general
development costs have since increased substantially due to cost inflation. In
Speyside, detailed designs and costings of the preferred site revealed access
difficulties and high development costs, rendering the proposals unviable.
Officers are working with consultants and local landowners to try and identify
a potentially suitable alternative site. While in Forres, the landowner had
confirmed willingness to sell land on the Enterprise Park. Work to progress
with its purchase and development (of serviced sites plus small business
units) was well advanced when the landowner advised the land was instead
required for alternative development proposals. Officers had also progressed
work on the purchase of privately owned land adjacent to the Enterprise Park
to bring forward development of serviced sites plus small business units, on a
Joint Venture basis. However, site investigations showed the majority of the
site to be unsuitable and very expensive to develop. The Joint Venture partner
has withdrawn and the project is now considered unviable. Officers are now
investigating alternative sites in the Forres area and the capital allocation has
been deferred accordingly. 
7.3 Development Management have determined a number of planning
applications for housing developments timeously which in turn has supported
the delivery of housing and infrastructure developments. 
8. PROCUREMENT 
Moray Council 
8.1 To support the adoption of a Community Wealth Building (CWB) approach
within procurement, at its meeting on 28 October 2020, Council approved the
allocation of funding for the employment of a CWB Officer (Paragraph 16 of
the minute refers). The CWB Officer has developed a Moray wide CWB
Strategy, which is being reported to the June meeting of the committee. 
8.2 However, at its meeting on 8 March 2023, Council approved the decision to
make a budgetary saving by removing the temporary CWB Officer Post and
redeploying the post holder into a vacant Business Gateway Officer post. This
means that there will no longer be dedicated post to lead on the delivery of a
CWB approach (paragraph 14 of the draft minute refers). The actions
identified within the strategy will now be delivered via existing resource across
the Council. 
8.3 As also approved by Council on 28 October 2020, and described in Section 4
above, consultancy provision has been made available for small business to
support procurement and supplier development through assisting companies
in preparing bids (paragraph 14 of the minute refers). There was however
minimal interest in this as documented. 
Page 62

Page 63

9. SOCIAL ENTERPRISE / COMMUNITY SUPPORT 
HIE, UHI Moray, and Moray Council 
9.1 Costs for the Rural Tourism Infrastructure Fund (RTIF) funded Coast to
Country project had to be adjusted to offset the rise in construction costs as a
result of inflationary pressures. This resulted in final project costs of £802,751
with an increased RTIF award of £375,000 match funded by increased
contributions of £60,000 from HIE and £367,751 from the Council. The Coast
to Country project is an integral part of a Moray wide strategic staycation
programme. It is being delivered in partnership between the Council, Visit
Moray Speyside Tourism Business Improvement District, HIE, and various
Community Trusts and Associations. The Coast to Country project will
enhance tourist infrastructure and facilities across the region, providing an
improved visitor experience and mitigating negative impacts upon local
communities. All elements of the project are due for completion in Spring
2023. 
9.2 As an extension of the national ‘Scotland Loves Local’ campaign led by
Scotland’s Town Partnership, local authorities were invited to participate in the
‘Scotland Loves Local Gift Card’ scheme to support local businesses
emerging from the impact of COVID-19, protect local jobs, and encourage
consumers to think local first. During the first year 119 Moray businesses
registered, including a wide range of retail, food and drink, accommodation
services and health & beauty businesses. This resulted in 54 gift cards being
sold, generating £1,730 for the Moray economy. To support this project,
£70,000 from the Economic Recovery Fund was allocated to create a
temporary dedicated Development Project Officer post for a period of 12
months, provide promotional budget and administration cost to continue the
scheme.  Over 200 businesses are now registered for the scheme and 1780
cards worth £87,119 have now been sold and retained within the local
economy. 
9.3 HIE has invested £250,304 in social enterprise organisations during this
period, levering in external investment of £394,400. This included capital
support towards the creation of the Portgordon Community Hub in the former
Richmond Arms, which has been acquired by the community with support
from HIE’s Community Assets Team and Scottish Land Fund. These
investments are projected to generate an increased turnover in the social
economy of £264,411 and support 8 jobs in the third sector. 
9.4 Investment has continued this year from the HIE Moray Team to support
development officer posts in Dufftown, Portgordon, Lossiemouth, Cullen,
Forres, Tomintoul and Glenlivet and Leanchoil Trust with a focus on
developing community assets, as well as project posts in tsiMORAY
supporting the Moray Social Enterprise Network, Development Officer
Network, Health & Wellbeing Forum as well as capacity building, governance
and funding support. 
9.5 The Moray Council Economic Growth & Regeneration team provided support
to a number of social enterprises and community groups with applications to
the Scotland Towns Partnership Scotland Loves Local II fund. Of the seven
Page 63

Page 64

applications made, three were successful; Elgin City Centre Illuminations
project (£15,000), Keith & Strathisla Regeneration Partnership (£10,000) and
Destination Dufftown (£17,500). Work continues with each of the projects,
with all anticipated for completion before June 2023. 
10. MORAY GROWTH DEAL 
HIE, UHI Moray, Digital Health Initiative, and Moray Council 
10.1 During 2022/23 Growth Deal activity has focused on establishing the
Programme Management Office, the Digital Health project progressing work
associated with their delivery phase and the remaining projects working to
prepare their Full Business Cases. Significant progress has been made and
the following has been achieved during each of the financial quarters of
2022/23. 
10.2 Quarter 1:
• Full Business Case for Bus Revolution approved by the Moray Growth
Deal Board, with the project expected to enter delivery in Q1 23/24
• Ministerial launch of the Digital Health project
• Majority of programme and project roles filled 
10.3 Quarter 2:
• Programmatic controls relating to risk, assurance and reporting
enhanced
• Internal audit of the Growth Deal activity undertaken in the second half
of 2022. 
10.4 Quarter 3:
• Business Enterprise Hub Memorandum of Understanding signed with
Moray Council and Robertson Construction which enables RIBA design
stages to be progressed.
• Detailed engagement activity commenced by the Cultural Quarter
project to collate evidence that will help shape the vision for Elgin Town
Hall and Grant Lodge.
• Tender for Dallas Dhu Housing Mix Delivery site design work launched.
• Offer received from Boeing for how they will support the Moray
Aerospace, Advanced Technology Innovation Centre (MAATIC) facility 
10.5 Quarter 4:
• The Deal’s first annual report produced
• Implementation activity progressed in preparation for the launch of Bus
Revolution services in Q1 23/24, including marketing activity, final
testing of the app, revised livery applied to vehicles and drivers
recruited
• Workshop held to identify synergies and any potential cross-linkages
between the closely aligned MAATIC, BE Hub and MICM projects
relating to research, innovation and work with businesses 
Page 64

Page 65

11. EMPLOYABILITY AND SKILLS 
DWP, Developing the Young Workforce (DYW), HIE, Moray Chamber of
Commerce, UHI Moray, Moray Council, Skills Development Scotland
(SDS), tsiMORAY 
11.1 The DYW Moray school co-ordinators continue to work with the secondary
schools to establish strong links with businesses, helping to enhance
curriculum. This academic session has also seen the return of career fairs
within schools facilitated by the co-ordinators as well as face to face mock
interviews, CV checks and career talks helping to inspire and better prepare
young people for the world of work. 56 businesses have signed up this year to
support the Young Person’s Guarantee including offering apprenticeships,
work placements and school and college engagements. 
11.2 A significant programme of employability support and training provision has
been provided by the Moray Pathways Local Employability Partnership in
2022/23. Moray Council is the anchor organisation and commissions all
employability services on behalf of the Moray Pathways Local Employability
Partnership (LEP). Since the implementation of the No-One Left Behind
(NOLB) employability strategy in 2019, the Scottish Government have
devolved all employability funding to be managed by the LEP, to ensure that
local labour market needs are met. The LEP consists of the following
organisations; Barnardo’s Scotland, Community Learning and Development
(Moray Council), Department for Work and Pensions, DYW Moray, Economic
Growth and Regeneration (Moray Council), Education (Moray Council),
Strategic Planning and Development (Moray Council) Enable Scotland, HIE,
Moray Integrated Joint Board (NHS Grampian), Skills Development Scotland,
tsiMORAY and UHI Moray. 
11.3 The Moray Pathways Hub @ the Inkwell continues to provide essential
services for people of all ages. Having opened in June 2021, the Hub
celebrated its first anniversary in this financial year. Over 500 people have
engaged with partners who provide employability support and training
provision within the Hub, with a total of 124 people progressing into
employment as a result of this. There is a short film which celebrates the first
year of the Moray Pathways Hub. 
11.4 The Moray Employer Recruitment Incentive (MERI) scheme was launched in
April 2021. During 2022/23, a further 109 people have been matched into a 12
month paid job placement with a range of Third Sector, Public and Private
employers. The scheme was offered to young people, adults, and parents
who were also within the 7 high priority target groups. 
11.5 The programme of enhanced keyworker support within the NOLB model has
resulted in the Moray Council Employability Team now offering an all age
employability support service. Keyworkers provide vital end to end support
and co-ordinate the provision provided by the wider partnership. There are
keyworkers who work with young people, adults over age of 25 and parents in
poverty. 
Page 65

Page 66

11.6 An investment of £800,000 via the European Social Fund (ESF) and matched
funded by the LEP (NOLB Scottish Government Grant) has commissioned
provision across all of the following employability categories:
• Engagement and Needs Assessment
• Barrier Removal
• Vocational Activity
• Employer Engagement and Job Matching 
11.7 The following providers were commissioned to support individuals of all ages:
FACT, UHI Moray Training department, Lossiemouth Entertainment
Academy, Enable Works, Barnardos Works, Apex Scotland, Social Enterprise
Academy and the Elgin Youth Development Group employability programme. 
Over 250 participants have participated and continue to be actively engaged
with these services. The 1:1 keyworkers are co-ordinating and reviewing their
Pathway Plan as they progress. The sector based providers have worked in
collaboration with employers from within key Moray growth sectors. 
11.8 During 2022/23 a total of 676 people have engaged with end to end
keyworker support and support from our partners within the LEP:
• 371 Young People, which includes care experienced young people,
those living in a jobless household, young people with mental health
issues and people with disabilities
• 254 Adults over 25, including those who are considered long term
unemployed, people from ethnic minority backgrounds, people living in
poverty, and people with mental health issues and disabilities
• 93 Parents in Poverty 
11.9 As a result of the programmes delivered via the LEP the following outcomes
have been achieved:
• 39% progressing into training programmes 
• 29 % progressing into employment 
• 17% progressing into further education 
• 15% actively engaging with employability support from 1:1 Keyworkers
to overcome barriers to progression 
12. SUMMARY OF IMPLICATIONS 
(a) Corporate Plan and 10 Year Plan (Local Outcomes Improvement
Plan (LOIP))
Effective monitoring and review of economic activity supports the
corporate plan priority of promoting economic development and growth,
as well as the LOIP priority of a growing and sustainable economy.   
(b) Policy and Legal
There are no policy and legal issues arising directly from this report. 
(c) Financial implications
The financial implications relating to all Council spend associated with
delivery of Economic Recovery Plan activities are outlined within
Appendix A.   
Page 66

Page 67

Savings of £48,000 from the Community Wealth Building post have
already been approved and taken.  Underspends on 3 revenue projects
are not required going forward and the aggregate underspend of
£192,094 will be returned to reserves.  A further £121,000 return to
reserves arises from a project with additional core budget allocation.
Further underspends of around £250,000 from two projects have been
reallocated to the Flexible Food Fund and Sport and Culture Hardship
Fund. 
Slippage of £2,695,000 on 3 capital projects is reflected in the indicative
10 year capital plan approved by Council on 1 March. 
In total expenditure of £5,168,000 was planned - £3,503,000 capital and
£1,665,000 revenue.  Total revenue expenditure to date is £872,000. 
Actual and committed capital expenditure totals £803,000. 
(d) Risk Implications
There are no risk implications arising directly from this report. 
(e) Staffing Implications
There are no staffing implications arising from this report, which have not
already been detailed within. 
(f) Property
There are no property implications arising from this report, which have
not already been detailed within. 
(g) Equalities/Socio Economic Impact
The Economic Recovery Plan aims to promote fair and equitable growth
in the economy. 
(h) Climate Change and Biodiversity Impacts
There are no climate change or biodiversity issues arising directly from
this report. However, it is likely that a number of the interventions
delivered in support of the Economic Recovery Plan would have a
positive impact in reducing carbon emissions through transport and
logistics via the development of local supply chains. 
(i) Consultations
Depute Chief Executive (Economy, Environment and Finance), the Head
of Economic Growth and Development, the Legal Services Manager, the
Payments Manager, Chief Financial Officer, the Strategic Planning and
Development Manager, the Economic Growth and Regeneration
Manager, the Principal Climate Change Officer, the Equal Opportunities
Officer and Lissa Rowan (Committee Services Officer) have been
consulted and their comments have been incorporated into the report. 
Page 67

Page 68

13. CONCLUSION 
13.1 The Economic Recovery Plan was effectively targeted towards
addressing and alleviating the negative economic consequences of the
pandemic. As detailed in the sections above, the actions delivered via
the Economic Recovery Plan have provided support and assistance to a
variety of communities and industries. This has been critical in keeping
local unemployment and business failure under control, minimising the
impact of the pandemic upon the local economy. 
13.2 However, the challenges facing the economy have now evolved, with the
cost of doing business and the energy crisis now the most pressing
threats to our business community. Many of the interventions as set out
in the Economic Recovery Plan have now reached a conclusion. It is
therefore proposed that this be accepted as the final report covering the
delivery of the Economic Recovery Plan. 
13.3 Ongoing reporting of the Moray Economic Strategy, Community Wealth
Building Strategy, Apprenticeship Strategy, and Local Employability
Delivery Plan will instead provide vehicles for monitoring the health of
the economy and assessing the impact of public led economic
development interventions. Reporting of the outstanding activities
associated with the Economic Recovery Plan will be included within the
annual monitoring of these strategies. The KPIs for the Economic
Recovery Plan have also been incorporated into these strategic policies
to ensure consistency in how these actions continue to be reported. 
Author of Report: Chris Muir, Senior Officer Economic Strategy and
Development 
Background Papers: Economic Recovery Plan 
Ref:
http://spman.moray.gov.uk/MANComRepDraftSite/DevSer
vLib/2023%2005%2002%20EDI%20Committee/REPORT%20-
%20ECONOMIC%20RECOVERY%20PLAN%20DELIVERY%20202223.doc
Page 68

Page 69

Appendix A
Category Activity
Revenue /
Capital Match Funding
Original
Budget up to
23-24 Spend to date Commitment Remaining Budget Comments
£ £ £ £
Small Business
Support
Procurement and Brexit  Consultancy Revenue £35k HIE 70,000 14,915 55,085 The remaining budget of £55,085 consists of both HIE and Council contributions. Therefore
this is to be carried forward and used for support additional procurement initiatives, linked to
the delivery of the Community Wealth Building Strategy
Town Centre Improvement Plans Capital 200,000 0 200,000 This budget has been carried over into 2023/24 as a revenue budget was required for the
design work to be able to deliver on the capital works
Pop Up Shop Scheme Revenue 50,000 12,043 37,957 The remaining budget is an underspend which can be returned to reserves.
Town Centre Start Up Revenue 100,000 0 100,000 The remaining budget is an underspend which can be returned to reserves.
Discretionary Business Support Revenue 400,000 198,000 202,000 £400k was allocated from the Covid-19 Economic Recovery Fund for the Discretionary
Business Support Fund. £198k in grants were approved, with the remaining budget of £202k re-
allocated between the Flexible Food Fund (£162k) and a Sport and Culture Hardship Fund
(£40k)
Business Improvement Grant Revenue 410,000 336,899 73,101 £410k of the Covid-19 Economic Recovery Fund was allocated to the Town Centre Capital
business improvements and start-up funds. There are a small number of claims still to be
submitted from the remaining budget of £73,101, with the remainder to be re-allocated to the
Flexible Food Fund
Local Development Plan Revenue 245,000 123,480 121,520 Planned expendirure for 2023/24 id being met from core budget with a budget pressur of
£100,000 having been approved when the budget was set.  The balance of £121,520 can be
returned to reserves 
Employment land and industrial units in
Forres
Capital 1,500,000 5,000 1,495,000 This budget was reprofiled for 2027/28 as part of the capital plan approved by Council on 8
March 2023 (paragraph 12 of the draft minute refers)
Employment land and industrial units in
Speyside / East of Moray
Capital 1,000,000 0 1,000,000 This budget was reprofiled for 2026/27 as part of the capital plan approved by Council on 8
March 2023 (paragraph 12 of the draft minute refers)
Community Wealth Building Officer Revenue £70k – HIE 140,000 58,092 81,908 At its meeting on 8 March 2023, Council approved the decision to make a budgetary saving by
removing the temporary Community Wealth Building Officer post and redeploying the post
holder into a vacant Business Gateway Officer post. This resulted in a temporary saving of
£48k, with the remainder of the match funding from HIE being retained to fund the ongoing
work relating to CWB via the redeployed officer
Procurement Officer Revenue 184,000 112,000 72,000 Council approved budget for a permanent Procurement Officer post at its meeting on 28
October 2020 (paragraph 16 of the minute refers). The officer has been appointed from 1
February 2021. The remaining budget is required to support the ongoing costs of retaining this
permanent post.
Social
Enterprise/    
Community
Support
Rural Tourism Infrastructure Fund Capital £375k – Visit Scotland
£60k – HIE
802,751 361,179 441,572 0 Increase in final project costs to £802,751. Met by an increased RTIF award of £375,000,
match funded by increased contributions of £60,000 from HIE and £367,751 from the Council
Employability
and Skills
Kickstart Revenue 66,000 11,863 54,137 The remaining budget is an underspend which can be returned to reserves.
Procurement
Town Centres
Housing and
Infrastructure
Item 6b)
Page 69

Page 70

Page 70

Page 71

REPORT TO: ECONOMIC DEVELOPMENT AND INFRASTRUCTURE
SERVICES COMMITTEE ON 2 MAY 2023 
SUBJECT: CLIMATE CHANGE PLAN AND ROUTE MAP TO NET ZERO 
BY:  DEPUTE CHIEF EXECUTIVE (ECONOMY, ENVIRONMENT AND
FINANCE) 
1. REASON FOR REPORT 
1.1 To ask the Committee to approve the update to the Route Map to Net Zero
(RMNZ), approve in principle an updated climate change action plan subject
to consideration as part of the financial planning process, approve a climate
change engagement strategy, and note progress with the actions approved
within the Climate Change Strategy (CCS) for 2020-2030. 
1.2 This report is submitted to Council in terms of Section III (F) (33) of the
Council’s Scheme of Administration relating to providing, developing and
monitoring the Council’s Economic Development and Infrastructure Services. 
2. RECOMMENDATION 
2.1 It is recommended that Committee: 
(i) approve the updated RMNZ as set out in Appendix 1, the updated
Climate Change Actions in Appendix 2, and the Climate Change
Engagement Strategy in Appendix 3; 
(ii) notes that while the latest data available indicates that 2030 remains
in the range of possible dates when net zero will be met, to ensure
this is achieved the Council must commit to an aspirational
approach to reducing carbon emissions in key areas but that the
ability to implement such an approach is currently questionable
without significant external funding; and 
(iii) notes the ongoing budget pressure arising from statutory climate
change measures (as set out in section 1.2 of Appendix 1) for which
external funding is essential. 
Item 6c)
Page 71

Page 72

3. BACKGROUND 
3.1 Climate change is arguably the biggest challenge that we and future
generations will face. On the 27 June 2019 the Council made a Declaration
which recognised that climate change is an ecological emergency, and that
the Council needs to take necessary actions to protect our area, country and
planet (para 6 of the Minute refers).   
3.2 In response to the commitments made in the declaration, on the 10 March
2021 (para 13 of the Minute refers) the Council adopted the CCS for 2020-
2030.  The strategy set a goal of the Council being carbon neutral for direct
emissions by 2030 and that the Council, its officers and members will work
with others across Moray to deliver that goal.   
3.3 When the CCS was approved it was agreed that there was a need to develop
a detailed route map to set out a pathway how the Council could reach net
zero emissions by 2030 and forecast how emissions will be reduced through
the Council’s actions. This was adopted by Council on 6 April 2022 (para 18 of
the Minute refers) with the RMNZ to be updated annually with up to date data
on current emissions and future projections. 
4. ROUTE MAP TO NET ZERO 
4.1 The RMNZ in Appendix 1 sets out the current pathway to net-zero for the
Council by 2030 by explaining actions to target the councils major emissions
sources; buildings (electricity and heat), fleet, waste, and operating emissions.
The changes from the previous RMNZ are set out in Section 4 in Appendix 1
and in sections 4.3-4.5 below. 
4.2 In 2021/22, the Council’s recorded carbon emissions were 24,490 tonnes of
carbon dioxide equivalent (tCO2e) – an increase of 2,014 tCO2e (9%)
compared to reporting year 2020/21. This increase in the Council’s recorded
carbon emissions during 2021/22 is principally the result of services returning
to ‘business as usual’ following the operational changes necessitated by the
Covid-19 pandemic and this increase was predicted within the Council’s
RMNZ. It should be noted that the 2021/22 figures represent a reduction of
almost 1,000 tCO2e from the pre-pandemic submission of 2019/20. 
4.3 As is shown in Figure 13 of Appendix 1, the areas with the greatest potential
for securing further reductions are reducing thermal demand in buildings
through energy efficiency improvements and the replacement of gas boilers
with air source heat pumps or other low or zero carbon alternatives. At
present, it is difficult to be certain there will be enough progress in the
decarbonisation of the council building stock to ensure the net zero targets are
met without unnecessary offset. The current state of some of the buildings are
unknown, and so the works required to bring them to net zero is uncertain.   
4.4 As set out in the Energy Consumption Action Options and Decarbonisation of
Corporate Buildings report to this Committee on 7 February 2023 (paragraph
18 of the draft Minute refers) the need where possible to progress a ‘fabric
first’ approach to building design to reduce energy use may delay the
replacement of heating systems in order to ensure older buildings have an
Page 72

Page 73

adequate level of insulation required for low carbon heating systems. The
difficulties in fleet decarbonisation were also set out in the Update on Zero
Emission Fleet Replacement Strategy report to this Committee on 7 February
2023 (paragraph 10 of the draft Minute refers). The impacts of these concerns
and the altered timelines are reflected in the carbon reduction projections in
this update to the routemap. 
4.5 The current exercise to capture a programme of work to make the public
building stock carbon neutral will allow accurate figures to be calculated for
financial costs and emissions reductions to assist decisions the council makes
on how to progress. To progress this programme it is essential that the
smarter working (formerly office review) and the depots and stores reviews
are completed during 2023-24 to allow subsequent actions to progress at a
pace that will allow the council to reach net zero by 2030.   
4.6 If the Council progresses decarbonisation of its buildings and fleet as a
priority, and all decisions on future change are made by 2025, then a more
accurate assumption can be made of residual emissions and the need for
carbon sequestration through inset/offset. This will give a milestone for the
council to recommit to the 2030 net zero target knowing the costs and carbon
offset. 
4.7  As shown in Figure 15, the annual emissions forecast of the council’s current
pathway is shown within a range of estimates to highlight the uncertainties
around current estimates of carbon reductions. In addition to the current
pathway, the estimated range in emissions between an aspirational and
restricted approach are shown.
• Current pathway - a realistic timescale built around the expected work
programme of the council but, until otherwise informed, presumes a more
restricted approach to aspects which are not yet agreed such as building
heat decarbonisation. 
• Aspirational approach – the quickest possible timescale to get works
done to meet the council’s net zero target. It is assumed that finances will
be available to invest in projects which will reduce future costs. Timings
take into account any technical issues which may prevent work
completion over a shorter timescale
• Restricted approach – a slower timescale than the current pathway
where, for whatever reason, additional resources are not prioritised for
climate change. This would have the consequence of missing the 2030
deadline and missing opportunities to reduce carbon early. This may
result in requiring substantially more investment over a shorter period of
time to achieve the statutory deadlines. 
4.8  It is accepted that there are practical reasons why all of the Council public
buildings and fleet will not be converted to net zero by 2030. The Council will
have to develop an offsetting strategy to plan how to sequester residual
emissions to balance out these areas if it is to meet the 2030 target.  Part of
these emissions can be offset by managing current land and woodland to
maximise carbon sequestration. Funding secured from the Just Transition
Fund is being used to baseline the carbon emissions of Council landholdings,
to identify land types that can be improved, and to give advice on how to
develop an offsetting project for the Council and for the wider Moray area. 
Page 73

Page 74

4.9 By taking an aspirational approach to carbon reduction it is still feasible for
Moray Council to achieve net zero by 2030  if key decisions on building
decarbonisation and rationalisation of the estate are taken, and progress is
made to consistently improve fleet vehicles, reduce waste, and improve
insulation, heating, and hot water systems over the next seven years.
However, the expected level of capital spend means that securing external
funding for measures such as decarbonising council buildings will be essential
if the target of 2030 is to be met. Although increasingly all external funding
has net zero as a condition of grant regardless of the main purpose, the level
of work required to decarbonise public buildings will require specific additional
funding just for that purpose. 
5. ACTION PLAN 
5.1 The updated Climate Change Action Plan is included in Appendix 2.
Progress on these actions are reported to the Climate Change Board on a
quarterly basis and updated to this committee on an annual basis.
Amendments to the actions have been agreed at the Climate Change Board.
Details of amendments and completed actions are highlighted at the start of
the appendix. 
6. ENGAGEMENT STRATEGY 
6.1 The Climate Change Engagement Strategy is included in Appendix 3. As
instructed in the original Strategy and Action Plan, climate change officers
have prepared an engagement strategy to accompany the Climate Change
Plan and Route Map to Net Zero. The engagement strategy supports the
council’s journey to net zero by outlining a framework for engagement and
associated actions from the Route Map. It does not include any additional
actions or place additional expectations upon officers, but will act as a guide
to all departments in how to communicate and engage on climate and
biodiversity related issues consistently and effectively. It will also keep a
record of which actions within the wider Strategy and Route Map have
engagement elements. 
6.2 Recent reduction in staff capacity means there is less capacity for climate
change engagement activity within the wider Moray community. However,
engagement-related actions from the Route Map are led by officers across the
council and its partners, many of which are fulfilling statutory functions (e.g.
Local Development Plan). The adoption of this strategy should therefore
support climate change action to become embedded across the council and
climate change implications to be considered in all engagement activity and
communications with staff, communities and businesses. 
7. NEXT STEPS 
7.1 The council’s emissions will continue to be reported annually through the
Public Bodies Climate Change Duties statutory report each November, with
the latest data brought to Committee. 
Page 74

Page 75

7.2 This RMNZ will be periodically reviewed and refined as more projects are
scoped out and more clarity is obtained in terms of carbon emissions from
decarbonisation trends, future technologies or offsetting mechanisms and
accounting. 
7.3 An annual progress report on the route map will continue to be brought to this
Committee each year and will provide regular updates against actions and
emissions progress. 
7.4 As stated earlier, the additional work to reduce emissions contained in the
RMNZ will require substantial funding over the next ten years and the ability to
commit to this will need to be considered through the council’s financial
planning process.  While much of the initial planning for these changes should
be able to progress using existing budgets, significant additional resources to
progress these actions will be required to move towards implementation and
given the current financial position, the ability to identify these additional
resources in questionable in the absence of significant external funding . 
7.5 Apart from access to capital resources, there are actions that could be taken
to lower these risk factors and these are identified in page 23 of Appendix 1.
Adopting some of these suggestions would allow more capacity within
services and ensure a more aspirational pathway could be progressed.
Suggestions of actions to create additional capacity within the council are as
follows: 
Building heat Dedicated staff resource to manage building decarbonisation. To
initially focus on planning of appropriate interventions on a
building by building basis and then lead on implementation.
Transport Dedicated project management resource within fleet to progress
decarbonisation project and keep pace with the rapidly expanding
LEV marketplace.
Waste Create dedicated waste education resource within council or
support equivalent third sector project
Operating
Emissions
Include appropriate reporting in service plans to ensure climate
change is a sectional priority and service change is progressed.
This could be rolled out as part of the engagement around
updating the CCS.
Expand our roll out of Carbon Literacy Training and require key
individuals to participate.  
Nature &
Biodiversity
An offsetting/biodiversity strategy (such as works to change land
management regimes, purchase of additional land, and tree
planting to sequester emissions) will be set out in a subsequent
report, and presented to Council through the appropriate
channels. The work to implement these actions will need
budgetary approval to progress the work in an offsetting strategy.
The creation of dedicated project management resource within
Open Spaces to progress practical biodiversity and
decarbonisation work.
External
Influence
Increase resources for climate change community engagement. 
Page 75

Page 76

7.6 Given the £20m budget gap and ongoing reviews of the Corporate Plan and
Medium to Long Term Financial Plan, officers cannot currently recommend
that these additional resources are earmarked to enable progress along a
more aspirational pathway.  This will however have implications in terms of
progress towards meeting the 2030 target, and the state of preparedness to
recommit to this in 2025. 
8. SUMMARY OF IMPLICATIONS 
(a) Corporate Plan and 10 Year Plan (Local Outcomes Improvement
Plan (LOIP))
The CCS supports the priorities set out in the Corporate Plan and 10
Year Plan. The Council has declared a climate change emergency, a
nature emergency, and the measures set out in the CCS seek to create
a resilient, biodiverse, fair and more sustainable future for everyone
within Moray. 
The strategy is aligned to deliver the priorities:
• Ensuring a just transition for all in the shift to a low carbon economy;
• Addressing inequalities of fuel poverty;
• Empowering individuals and communities through education and
information provision to make informed choices with respect to
climate change;
• Protecting and enhancing the world we live in to protect it for the
future; and 
• Being innovative in identifying solutions for cost reduction and
income generation opportunities. 
(b) Policy and Legal
Climate Change (Scotland) Act 2009 places a duty on public bodies to
act in a way they consider most sustainable and in the way best
calculated to contribute to the delivery of Scotland’s climate change
targets; in the way best calculated to help deliver any programme for
climate change adaptation laid before the Scottish Parliament; in a way it
considers most sustainable. The 2030 target adopted by the Council
reflects an accelerated route to net zero beyond that currently set by
legislation
Climate change is increasingly being embedded in all government
policies ranging from Infrastructure delivery, energy policies and NPF4
and these will influence the majority of council policies moving forward. 
(c) Financial implications
To achieve a position of net zero carbon emissions by 2030 will require
significant capital investment as well as additional revenue investment to
bolster staffing resources. This will be subject to consideration as part of
the financial planning process and reflecting relative corporate priorities
within a very constrained financial envelope. 
£500,000 from Council reserves has been set aside for one-off funding in
the capital plan for 2023/24 to support initial steps. However, progressing
actions from the Electric Vehicles, Buildings, and Hydrogen Strategies,
and offsetting plans that are not covered by current approved plans will
Page 76

Page 77

require additional budgetary approval through the normal process if they
are to progress. 
(d) Risk Implications
Climate change is arguably the biggest challenge that we face in our
lifetime and for future generations. It poses significant risks to our health,
our economy, our environment, and endangers the wellbeing of future
generations.  There is a risk that the Council’s aim of being net zero by
2030 will not be realised if the actions within the CCS including
decarbonisation of Council fleet and buildings are not progressed as a
priority. 
(e) Staffing Implications
There are no direct staffing implications leading from this report. 
(f) Property
The outcome of the buildings decarbonisation strategy will impact on
council housing, corporate buildings and the Learning Estate. These
implications will be set out in more detail as the key actions relating to
Property are progressed. 
(g) Equalities/Socio Economic Impact
Climate Change will impact on every service area delivered by the
council. It has the potential to impact on equalities for example in respect
of support for active travel and fuel poverty which will have a positive
socio-economic impact. 
Climate change will lead to more extreme adverse weather events in
Moray which will have a disproportionate impact on those already in
poverty or with the inability to adapt to this change. 
(h) Climate Change and Biodiversity Impacts
The RMNZ will help focus attention on the actions required to ensure the
council is on track for the 2030 net zero target.  Reducing emissions will
help the global climate emergency and allow the council to lead by
example.  Tree planting and nature restoration to assist in carbon
sequestration could be used to help promote biodiversity and amenity. 
(i) Consultations
Consultations have been undertaken with the Chief Executive, the
Depute Chief Executive (Economy, Environment and Finance), the Head
of Economic Growth and Development, the Head of Governance,
Strategy and Performance, the Head of Housing and Property, the Head
of Environmental and Commercial Services, the Head of Education
Resources and Communities, the Legal Services Manager, the Energy
Officer, the Equal Opportunities Officer, the Chief Financial Officer and
Lissa Rowan (Committee Services Officer). Where comments have been
received, these have been included within the report. 
Page 77

Page 78

9. CONCLUSION 
9.1 This report provides an update on progress to the council target of
being carbon neutral by 2030. While the current pathway the council is
on means that 2030 remains in the range of possible dates when net
zero will be met, doing so will require adoption of a more aspirational
pathway for which funding has not as yet been identified. 
9.2 Decisions around buildings and depot infrastructure must be made to
allow for a more accurate estimate on the offset needed for the 2030
target. 
Author of Report: Rod Lovie, Principal Climate Change Strategy Officer
Background Papers: 
Ref:     
Page 78

Page 79

1 | P a g e
Item 6c)
Page 79

Page 80

i 
Contents 
Foreword ........................................................................................................................................................................................................................................ iii
Section 1: Why we are taking climate change action ................................................................................................................................................................. 1
1.1 Introduction............................................................................................................................................................................................................................. 1
1.2 Statutory obligations ............................................................................................................................................................................................................... 2
1.3 Co-benefits of taking climate change action .......................................................................................................................................................................... 3
Section 2: Our approach to climate change action .................................................................................................................................................................... 5
2.1 Accounting for net zero .......................................................................................................................................................................................................... 5
2.2 Approach to our targets .......................................................................................................................................................................................................... 5
2.3 Baselining our emissions ....................................................................................................................................................................................................... 6
Section 3: What impact are we having on climate change? ...................................................................................................................................................... 7
3.1 Building heat and electricity ................................................................................................................................................................................................... 7
3.2 Transport ................................................................................................................................................................................................................................ 8
3.3 Waste ................................................................................................................................................................................................................................... 10
3.4 Operating emissions ............................................................................................................................................................................................................ 11
3.5 Procurement and investment ............................................................................................................................................................................................... 13
3.6 Nature and carbon sequestration ......................................................................................................................................................................................... 14
3.7 External influence ................................................................................................................................................................................................................. 15
Section 4: What progress are we making? ................................................................................................................................................................................ 17
4.1 Current pathway of recorded emissions .............................................................................................................................................................................. 17
4.2 Progress ............................................................................................................................................................................................................................... 17
4.3 Concerns .............................................................................................................................................................................................................................. 19
4.4 Benefits and threats associated with current pathway ......................................................................................................................................................... 19
4.5 Carbon sequestration ........................................................................................................................................................................................................... 20
Section 5: Where are we going? ................................................................................................................................................................................................. 21
Page 80

Page 81

ii 
5.1 Pathway to net zero ............................................................................................................................................................................................................. 21
5.2 Limitations and risks ............................................................................................................................................................................................................. 22
5.3 2025 decision point .............................................................................................................................................................................................................. 24
5.4 Adaptation and resilience ..................................................................................................................................................................................................... 24
Section 6: Conclusion ................................................................................................................................................................................................................. 26
Glossary ........................................................................................................................................................................................................................................ 27 
Page 81

Page 82

iii 
Foreword
Our climate is changing at a rate never before experienced.
Human activity has been the major source of all global warming in recent
history and we must strive to deliver on our collective responsibility to be the
main drivers of action.
At the launch of the AR6 Synthesis Report of the Intergovernmental Panel
on Climate Change (IPCC) on 20 March 2023, UN Secretary-General
António Guterres said: 
It is therefore clear that the decisions we take today will prove pivotal for the
generations to come.
There is a very limited opportunity remaining for us to take the necessary
actions to ensure that future impacts are mitigated and that our communities
are properly adapted. These form part of our statutory priorities.
Our Climate Change Plan and Routemap to Net Zero complements our
Climate Change Strategy by providing the strategic approach necessary to
achieve these priorities.
By setting an ambitious net zero target of 2030 for direct Council emissions,
we have set our sights on taking all of the opportunities available for early
adaptation and mitigation measures. In doing so, we will also be delivering
on the priorities of our Corporate Plan by unlocking a wealth of co-benefits
for the people of Moray.
As set out in our Climate Change Plan and Routemap to Net Zero, this
will not be easy. But nor is it beyond our grasp at this time. 
Cllr Marc Macrae
CHAIR, ECONOMIC DEVELOPMENT &
INFRASTRUCTURE SERVICES COMMITTEE
Cllr Draeyk van der Hørn
CLIMATE CHANGE CHAMPION 
“Humanity is on thin ice – and that ice is melting fast.
In short, our world needs climate action on all fronts --
everything, everywhere, all at once.
Specifically, leaders of developed countries must commit to
reaching net zero as close as possible to 2040, the limit they
should all aim to respect.
This can be done.
Every country must be part of the solution. Demanding others
move first only ensures humanity comes last.” 
Page 82

Page 83

1 
1. Why we are taking climate change action
1.1  Introduction
All local authorities signed Scotland’s Climate Change Declaration in 2007
and 28 have since declared or otherwise recognised the climate emergency. 
Moray Council declared a climate emergency in June 2019 and agreed a
Climate Change Strategy in 2020. The strategy has a commitment to net
zero direct emissions from council activities by 2030. This Climate Change
Plan and Routemap to Net Zero complements the strategy by providing an
annual update on progress, actions and the way forward.
In addition, the council declared a nature emergency in February 2023,
recognising the value of nature and its role in realising climate targets,
maintaining a strong economy, and for protecting the health and wellbeing
of future generations. The importance of using nature-based solutions to
climate change are well recognised, with positive outcomes for both
mitigation and adaptation1.
The climate is changing faster than ever previously experienced. Globally
scientists agree that greenhouse gas emissions from human activities are
the main reason for global temperature increases over the past 150 years2
(Figure 1).
Increased carbon dioxide in the atmosphere also has a profound impact on
the health and wellbeing of the population. There is approximately 1 excess
death per 4,500 tCO2e emitted3 and the impacts of climate change will be
felt disproportionately by people on low incomes who have contributed least
to the increase in greenhouse gas emissions4. 
The impact of global temperature increases has already been significant.
Weather patterns are changing and sea levels are rising. These changes are 
1 Seddon et al. (2020) ‘Global recognition of the importance of nature-based solutions to the
impacts of climate change’.
2 IPCC (2021) Climate Change 2021: The Physical Science Basis.
leading to severe events such as heatwaves, floods, droughts and wildfires,
and increasingly so in the Moray region (Figure 2).
Coastal flooding is of particular concern and impact in Moray due to rising
sea levels and storm surges leading to property damage, infrastructure
disruption and loss of habitable land. The first ‘climate refugees’ in the British
Isles are from a coastal community in Wales5.
Climate change also poses the greatest threat to the natural environment
and the ecosystem services that it provides (Figure 3). This threat will in turn
negatively impact the Moray food and drink sector, tourism sector, and
overall health and wellbeing. 
3 Bressler (2021) ‘The mortality cost of carbon’. 
4 UK Government (2019) The Impacts of Climate Change.
5 BBC News (2022) The UK ‘climate refugees’ who won’t leave.
Figure 1. Global atmospheric carbon dioxide (CO2) concentration from 803,720 BCE to
present day. Data from National Oceanic and Atmospheric Administration (2023).
Page 83

Page 84

2 
Figure 2. Frequency of extreme events occurring in Moray. Data from various Scottish
public agencies. 
1.2  Statutory obligations
Moray Council has a statutory responsibility to undertake climate change
action. 
Scotland aims to reduce greenhouse gas emissions by 75 per cent by 2030
and to reach net zero by 2045. The Climate Change (Scotland) Act 2009
places a duty on all public bodies to act to deliver on the national climate
change targets.
Under this legislation, Moray Council has three main duties:
• Mitigation: To contribute to reducing greenhouse gas emissions
• Adaptation: To help Moray adapt to the changing climate
• Sustainability: To act in a sustainable manner.
The council must report on compliance with these duties annually in
accordance with the Climate Change (Duties of Public Bodies: Reporting
Requirements) (Scotland) Order 2015 and subsequent amendments.
This council is required to provide the following information in annual climate
change reports:
• its target date for achieving zero direct emissions;
• its targets for reducing indirect emissions; 
• how its targets will align spending plans and use of resources to
contribute to reducing emissions; 
• how it will publish progress to achieving emissions reduction targets;
and
• what contribution it has made to helping deliver Scotland’s Climate
Change Adaptation Programme.
National Planning Framework 4 (NPF4) gives significant consideration to
carbon, climate change and biodiversity by incorporating the national climate
change targets into the local planning system to promote sustainable
development.
The Heat Networks (Scotland) Act 2021 aims to regulate and support the
development of heat networks. Heat networks distribute heat from a central
0
10
20
30
40
50
1960 1965 1970 1975 1980 1985 1990 1995 2000 2005 2010 2015 2020
Number of events
Climatological events Meteorological events
Figure 3. Ecosystem services gained from nature (NatureScot 2022)
Page 84

Page 85

3 
source to multiple buildings, reducing the need for individual heating systems
and promoting energy efficiency. The council is required to undertake
assessments of the potential for heat networks in Moray and develop plans
to promote their use.
The Local Heat and Energy Efficiency Strategies (Scotland) Order 2022
requires the council to develop plans to improve energy efficiency and
reduce carbon emissions in buildings across Moray, to support the transition
to net zero. 
The Nature Conservation (Scotland) Act 2004 aims to protect and conserve
biodiversity and natural habitats. It places a duty on the council to consider
biodiversity in its decision-making processes and to promote the
conservation of local habitats and species.
The Transport (Scotland) Act 2019 aims to promote sustainable transport
and reduce greenhouse gas emissions from the transport sector. It has
provided the council with greater powers to implement Low Emission Zones
and improve active travel infrastructure.
1.3 Co-benefits of taking climate change action
Local authorities and community planning partners play a vital leadership
role in driving the ambition and local collaboration necessary to integrate net
zero and the green recovery into planning and investment decisions5. In
addition, taking action on climate change presents opportunities to promote
co-benefits which support multiple demands from local communities and
businesses. The co-benefits of climate action can include the creation of
green jobs, improved public health from active travel and cleaner air, and
enhanced biodiversity due to the expansion of green space. 
Such co-benefits could also support the delivery of themes within the Moray
Council Corporate Plan 2024. Table 1 highlights a selection of potential co-
benefits achievable which align with Corporate Plan priorities. 
5 Improvement Service (2023) Community Planning Improvement Board: Climate change
and sustainability key messages.
Table 1. Selection of potential co-benefits achievable through delivery of Climate Change
actions.
Our people
✔ Improved health and wellbeing
✔ Reduced health and social care costs
✔ Protect the most vulnerable from climate impacts
Our place
✔ Strong, well-connected communities
✔ Community-led improvements
✔ Public involvement in planning
✔ Improved greenspaces and access to the natural environment
Our future
✔ Increased demand and opportunities for green jobs and skills
✔ Retaining young people in Moray
✔ Strong local economy and community wealth
✔ Improved standard of living
✔ Resilience to climate change impacts
✔ Reduced energy and maintenance bills
✔ Reduced costs from severe event damage
✔ Opportunities for council revenue generation 
Early investment in climate change adaptation delivers strong value for
money, with most measures delivering £2 to £10 of net wider economic
benefits locally for every £1 spent6. In addition, around £9 in property
damages and wider impacts can be avoided. 
6 UK National Audit Office (2022) ‘Climate change adaptation: the government’s role and
progress’.
Page 85

Page 86

4 
Page 86

Page 87

5 
2. Our approach to climate change action
2.1  Accounting for net zero
Net zero means cutting greenhouse gas emissions to as close to zero as
possible, with any remaining emissions re-absorbed from the atmosphere –
for example, by oceans and forests7. 
Emissions originate from sources directly within the council’s control (Scope
1), or where it is the direct user of a good or service (Scope 2), e.g. fleet
vehicle emissions and grid electricity use. The Moray Council target for net
zero is to reduce direct operating emissions of the council to net zero by
2030.
Other emissions originate from sources where the council has an interest but
no direct control (Scope 3), e.g. procurement of food for school catering.
Calculating the latter involves a greater level of uncertainty: both in the
emissions themselves, and the level of responsibility for them.
The council has a duty to report on all Scope 1 and 2 emissions, all Scope 3
emissions from “relevant and significant areas of the organisation’s indirect
emissions” greater than 1% of total organisational emissions. 
2.2 Approach to our targets
The council has previously has agreed that its targets should be ambitious
and achievable. They should provide a realistic but agile pathway towards
the aim of net zero carbon emissions by 2030. 
The targets should be measurable and recording mechanisms should be
transparent and improved over time. Where there is uncertainty,
assumptions backed by expertise will be made and stated clearly to avoid
understating the council’s climate impact.
The council’s targets will include direct emissions, and estimate how these
and indirect emissions may change in the future. They will:
• Be clear on what is included in the scope of the council’s emissions;
• Cover all Scope 1 and 2 emissions and appropriate areas of Scope
3 emissions (e.g. municipal waste); 
7 United Nations (2023) What is net zero?
• Have interim reduction targets at set periods that align to the Scottish
Government interim targets; and
• Reduce residual emissions to as low a level as possible and set out
how natural carbon sequestration methods will be used to achieve
net zero emissions. 
The council will use a carbon management hierarchy approach to prioritise
its targets and necessary actions (Figure 5). This approach prioritises the
avoidance of carbon emissions to deliver lasting change. Where avoidance
of emissions is not possible then they should be reduced through service
efficiencies or redesign. Removal of emissions is required where further
reductions cannot be achieved. 
Offsetting ‘unavoidable’ emissions through offsetting schemes should be
considered as a last resort in target setting. Offsetting large amounts of
carbon is discouraged as large scale offsets are not sustainable and
guidance makes clear that public bodies are required to reduce emissions
as much as possible before considering offsets.
Figure 4. Emissions scope classification for Moray Council activities.
Page 87

Page 88

6 
For example, actions might look like: 
• AVOID: Redesign services to enable smarter working. 
• REDUCE: Reduce energy through smart timing solutions.
• REPLACE: Decarbonisation of the council’s fleet.
• OFFSET: Plant an area of woodland to offset unavoidable emissions. 
2.3 Baselining our emissions
Calculating baseline emissions helps to determine the level of intervention
needed to achieve net zero carbon emissions, and to allow progress to be
monitored.
The council’s carbon emissions from 2017/18 are used as a baseline for
emissions (Table 2). This year was chosen as it was the earliest year that
had a comprehensive return of emissions to the Scottish Government.
It should be noted that as these data are from prior to the pandemic,
operational emissions were minimal as most staff worked from an office base
and home working emissions were not being recorded. The first time the
council recorded homeworking emissions was during the pandemic. 
Table 2. Moray Council 2017/18 baseline carbon emissions.
Emission source by area and source Carbon emissions
(tCO2e)
Building
heat
Natural gas 4,077.9
Gas oil 1,034.1
Biomass 34.7
Purchased heat and steam 15.4
Building electricity
Primary schools and nurseries 1,122.0
Secondary schools 1,177.3
Unmetered electricity 1,685.5
Offices 523.8
Community facilities 358.5
Residential homes and day
centres 145.7
Sports facilities 249.6
Industrial 346.2
Other 611.0
Transport
Diesel 3,591.5
Petrol 27.5
Gas oil 776.6
Electric vehicles 0.0
Hybrid vehicles 0.0
Marine fuel oil 68.2
W
aste
Landfill gas 0.0
Municipal refuse to landfill 9,130.3
Commercial, industrial and
clinical waste to landfill 2,048.7
Recycling and composting 387.2
Operational
emissions
Outdoor spaces 72.1
Homeworking emissions 0.0
Water supply and treatment 125.8
Corporate travel 394.8
Figure 5. Moray Council carbon management hierarchy.
Page 88

Page 89

7 
3. What impact are we having on climate change?
The way the council conducts its work and manages its assets all has an
impact on the climate. In this section, the extent of this impact is explored.
If progress is to be made on the council’s targets, it must consider what it is
doing and how it is doing it. Within that, the council should also reflect on the
lessons it can learn from examples of good practice and how these can be
applied to future action. 
The actions in this section form part of the council’s climate change action
plan. There is an opportunity to develop these actions further as part of the
Climate Change Strategy update in 2024.
3.1   Building heat and electricity 
3.1.1 Overview
The council’s property portfolio comprises a range of buildings including
offices, schools, libraries, sports facilities and depots. These buildings vary
in age, size, energy efficiency and condition.
Most of the council’s buildings are heated by natural gas or gas oil. However,
there are a few sites where biomass has been installed.
Building electricity is provided by the national grid, although some buildings
have been fitted with solar PV panels. Electricity use also includes street
lighting and safety floodlighting.
There are a series of national phased targets for all publicly-owned buildings
to meet zero emission heating requirements, with a backstop of 2038. 
To enable this, support is being provided by the Scottish Government via
the:
• Scottish Public Sector Energy Efficiency Loan Scheme (Salix)
• Scottish Public Sector Non-Domestic Energy Efficiency (NDEE)
Frameworks and Project Support Unit (PSU)
• Scottish Central Government Energy Efficiency Grant Scheme
3.1.2 Current emissions
Emissions from the council’s buildings are split into two categories: building
heat and building electricity.
Building electricity emissions currently represent 12% of our overall
emissions. As shown in Figure 6, building electricity emissions have
decreased by 55% from our baseline. This is due to a greener national grid
and reduced electricity consumption through efficiency programmes such as
those in Case Study 1. 
Building heat emissions currently represent 24% of the council’s overall
emissions.
Whilst use of gas oil and purchased heat and steam has decreased over the
baseline period, Figure 6 illustrates an increased reliance in the most recent
reporting period on natural gas and gas oil for building heat. This is largely
due to a return to ‘business as usual’ working practices following the marked
decrease in these emissions during the Covid-19 pandemic working
restrictions.
0
1,000
2,000
3,000
4,000
5,000
6,000
7,000
2017/18 2018/19 2019/20 2020/21 2021/22
Carbon emissions (tCO
2e) Natural gas
Building electricity
Gas oil
Biomass
Purchased heat and
steam
Figure 6. Building electricity and heat emissions from baseline date to present.
Page 89

Page 90

8 
Case study 1:  Elgin High School solar panels 
The council installed a 47kWp solar PV panel system at Elgin High School
in October 2017. Since its commissioning, the system has generated over
177,491kWh of electricity and brought in over £5,000 in Feed-In-Tariff
payments.
The solar PV system produces around 3,500kWh every year, which has
significantly reduced the school’s carbon footprint and energy bills.
The UK energy price crisis has led to a major increase in energy prices,
which has resulted in a shorter payback period for solar PV installations.
As energy prices increase, the value of electricity generated by solar PV
systems also increases. This means that the payback period for the initial
investment in a solar PV system is reduced, as the system can generate
more revenue in a shorter timeframe.
The council can access several funding opportunities to implement solar
PV systems including via the Scottish Public Sector Energy Efficiency
Loan Scheme (Salix). 
3.1.3 Action areas
Outcomes Actions include:
Reduced heat
and electricity
consumption 
▪ Increasing building user awareness of ways to reduce
energy use and save utility costs
▪ Reviewing building opening times
▪ Reducing the heat set point of buildings
▪ Progress a ‘fabric first’ approach to building design
▪ Identifying opportunities for heating and power
refurbishment in the learning estate
▪ Promoting Smarter Working
More energy
produced by
renewables and
low carbon
sources
▪ Feasibility studies to consider renewable energy potential
across the Council’s property portfolio
▪ Installing renewable energy technologies on council-
owned buildings and land
▪ Replacement of carbon-based heating systems
Reduced
building carbon
output and
increased
energy
efficiency
▪ Aim to achieve zero carbon standards for all new
buildings, including housing and schools
▪ Achieve Energy Efficiency Standard for Social Housing
(EESSH) for all council housing 
3.2   Transport 
3.2.1 Overview
The council’s fleet is used by employees to conduct council business and
deliver services for the people of Moray. It comprises over 500 cars, vans,
buses, trucks, specialist vehicles and vessels.
The majority of the fleet runs on diesel or gas oil fuel. Marine fuel oil is
currently used in council vessels. Petrol is used for open spaces machinery.
There are a series of national targets in relation to public sector transport
fleets:
Page 90

Page 91

9 
• All fossil fuel cars to be replaced by zero emission alternatives by
2025
• No purchases of fossil fuel powered light commercial vehicles (under
3.5 tonnes) after 2025, with remaining vehicles phased out by 2030
• Phase out heavy duty vehicles by 2040
The Zero Emission Fleet Replacement Strategy details the council’s plans to
decarbonise the remainder of the fleet in line with the Scottish Government’s
net zero targets.
3.2.2 Current emissions
Emissions from the fleet are mostly from the use of diesel (Figure 7). 
In the most recent reporting period, there has been a rise in emissions from
diesel use (Figure 8). This is largely due to a return to ‘business as usual’
working practices following the marked decrease in these emissions during
the Covid-19 pandemic working restrictions. 
Figure 7. Breakdown of Moray Council transport emissions 2021-22.
Figure 8. Transport emissions from baseline date to present. 
3.2.3 Action areas
Outcomes Actions include:
Decarbonised
council fleet
▪ Displacing fossil fuel powered vehicles and plant with
ULEV alternatives
Increased
awareness of
actions and
opportunities to
reduce
emissions
▪ Developing and promoting staff travel plans
▪ Delivering and promoting active travel to school
campaigns
▪ Developing a calendar of sustainable events
▪ Conducting new staff travel survey in April 2023
Facilitating
emissions
reduction
▪ Developing strategy and guidance for provision of public
EV charging facilities in Moray
▪ Organising bicycle maintenance sessions and led rides for
staff
▪ Parking management around schools and supporting
modal shift from vehicles to active travel 
0
500
1,000
1,500
2,000
2,500
3,000
3,500
4,000
2017/18 2018/19 2019/20 2020/21 2021/22
Carbon emissions (tCO
2e)
Diesel
Gas oil
Marine fuel oil
Petrol
Page 91

Page 92

10 
3.3   Waste 
3.3.1 Overview
Waste is collected across Moray from households and commercial
organisations. The council currently operates a landfill site at Nether
Dallachy which handles household, commercial, industrial and clinical waste. 
Disposing of waste within landfill is the worst option for the environment and
leads to significant carbon emissions. It should be the last resort for waste
disposal (Figure 9).   
In 2023, the council will be diverting waste from landfill to a new energy from
waste facility (Case Study 2).
There are several national targets in relation to waste management:
• Minimum recycling from all sources to be 70% by 2025
• Maximum of 5% of all waste sent to landfill by 2025
• 33% reduction in food waste by 2025
Case study 2: Recovering energy from waste 
From mid-2023, the council’s non-recyclable waste will be processed at
the NESS energy from waste facility. 
Aberdeen City Council, Aberdeenshire Council and Moray Council are
working together to create the facility to process non-recyclable waste.
The facility is being built at the former gas holder site at East Tullos
Industrial Estate in Aberdeen. It will take the remaining, non-recyclable
waste from the three councils and combust it cleanly and completely. 
The process will produce electricity which will then be sold to the National
Grid and steam which will be used in a local district heat network to provide
low cost heating to homes in the nearby Torry area.
Modern energy from waste plants are commonly used throughout northern
Europe and are considered utility plants alongside other power stations. In
Scotland there are currently two operational plants.
Despite the council’s best efforts to reduce residual waste through
minimisation campaigns, recycling, composting and use of other
treatments, a substantial quantity of residual waste that is generated will
still need to be collected and cannot be landfilled anymore. 
Diverting this residual waste from landfill to this facility will reduce the
council’s waste emissions by around 95%. 
Figure 9. Scotland’s waste management hierarchy (Scottish Government 2015)
Page 92

Page 93

11 
3.3.2 Current emissions
The council’s landfill accounts for 97% of all waste emissions. The remaining
waste emissions result from the processes involved in recycling and
composting waste. 
The production of landfill gas at Nether Dallachy results in a negligible level
of annual emissions. 
3.3.3 Action areas
Outcomes Actions include:
Reduced
emissions from
non-recyclable
waste
▪ Diverting non-recyclable waste to NESS energy from
waste facility in Aberdeen
Reduction in
residual waste
▪ Working with Zero Waste Scotland and third sector
partners to progress projects to reduce waste through re-
use and recycling
▪ Carrying out education on recycling and waste reduction
to improve sustainability awareness and recycling in
schools and across council buildings
▪ Reducing the charge for garden waste (brown bin) permits
▪ Supporting creation and promotion of a Community
Identified Benefits Portal, facilitating collaborative
relationships between local construction firms/developers
and circular economy initiatives
▪ Improving recycling and food composting facilities in
schools 
3.4   Operating Emissions 
3.4.1 Overview
Operating emissions result from the day-to-day work of the council. These
include an annually estimated carbon emissions impact for employees
working from home, electricity use in outdoor spaces, the use and treatment
of water and corporate travel.
3.4.2 Current emissions
The council’s operating emissions have marginally increased over the past
year (Figure 11).
Homeworking emissions, first recorded in 2020/21, have risen due to an
increase in the overall size of the workforce during the reporting period. The
methodology for calculating this is set externally but work to improve the
reporting of this emission source has been undertaken by the council’s
climate change officers and will take effect from reporting year 2022/23
onwards.
Emissions from electricity use in outdoor spaces have followed a decreasing
trend in recent years owing to ongoing decarbonisation programmes such
as those in Case Study 3. In the past year, these emissions have increased
due to higher use of EV charging points.
0
1,000
2,000
3,000
4,000
5,000
6,000
7,000
8,000
9,000
10,000
2017/18 2018/19 2019/20 2020/21 2021/22
Carbon emissions (tCO
2e) Municipal refuse to
landfill
Commercial, industrial
and clinical waste to
landfill
Recycling and
composting
Landfill gas
Figure 10. Waste emissions from baseline date to present.
Page 93

Page 94

12 
Case study 3:  LED street lighting programme
The council’s street lighting spend-
to-save programme saw the
replacement of approximately
17,600 lamps across Moray with
LED alternatives. 
The typical lifespan of an LED street
light is estimated to around 25 years. 
By comparison, traditional lamps last
4-5 years, resulting in more costly
maintenance regime requirements. 
The programme has resulted in energy use reductions of almost 70%, as
well as a reduction in light pollution across the Moray region. 
3.4.3 Action areas
Outcomes Actions include:
Reduced
emissions from
operational
actions
▪ Supporting homeworkers to reduce their emissions
through relevant advice and practical assistance
▪ Introducing a ZEV salary sacrifice scheme for employees
▪ Promoting Smarter Working
▪ Increasing use of the cloud to reduce server network and
electricity consumption
▪ Continue to make school meals more sustainable with a
reduced carbon impact
▪ Developing and promoting more vegetarian and vegan
food options
Increased
awareness of
actions and
opportunities to
reduce
emissions
▪ Developing and delivering Carbon Literacy training for
employees and elected members
▪ Updating climate change awareness training as part of the
employee induction process
▪ Increasing opportunities for ‘Learning for Sustainability’
within the school curriculum
▪ Applying zero and low carbon objectives as a factor in all
investment decisions in relation to budgets and the Capital
Plan
▪ Ensuring the Climate Change Strategy and Action Plan
are living documents and remain fresh and valid until 2030
▪ Assessing climate change and biodiversity impacts as part
of all reports to committee
▪ Supporting the development of knowledge and skills to
promote innovation and effective carbon management
across departments
▪ Supporting opportunities for teachers and pupils to access
and share knowledge/resources to progress climate
change work 
0
200
400
600
800
1,000
1,200
2017/18 2018/19 2019/20 2020/21 2021/22
Carbon emissions (tCO
2e)
Homeworking
emissions
Water supply and
treatment
Outdoor spaces
Corporate travel
Figure 11. Operating emissions from baseline date to present. 
Page 94

Page 95

13 
3.5   Procurement and Investment
3.5.1 Overview
Around a third of the country’s emissions are dependent on sectors that are
directly shaped or influenced by local authority practices, policy or
partnerships8. It is to this end that procurement performs such a key role in
reducing national climate impact.
Case study 4:  Food for Moray supplier engagement event
The Food for Moray event invited
any business interested in
supplying fresh meat, fruit and veg
and bakery products to schools to
learn more about the process and
gain advice from the teams
involved.
Suppliers spoke with relevant officers to find out about the criteria for
supplying schools, how they can operate more sustainably and evidence
this in their bids. The event was attended by officers from catering, climate
change, procurement and community wealth building, as well as advisers
from Business Gateway. Existing suppliers were on hand to share their
experience of supplying the council.
Suppliers liked that they could come to talk with relevant officers and
obtain information before deciding whether to proceed with the tender
process. It was an excellent opportunity for officers to handle any concerns
or misconceptions about the process at an early stage.
Feedback from attendees was very positive. Three local butchers went on
to join the tender process, and one purchased an electric van.
8 UK Climate Change Committee (2020) ‘Local authorities and the sixth carbon budget’.
Procurement of goods and services with the council amounts to some £140
million annually. The council therefore has a significant influence locally and
regionally on climate change through procurement.
The Procurement Reform (Scotland) Act 2014 introduced a sustainable
procurement duty for local authorities. This requires that before the council
buys anything, it must think about:
• how it can improve the social, environmental and economic wellbeing
of Moray, with a particular focus on reducing inequality
• how its procurement processes can facilitate the involvement of
SMEs, third sector bodies and supported business
• how public procurement can be used to promote innovation
Climate change and procurement officers have worked to develop a simple
process for suppliers to evidence their carbon reduction actions when
bidding for smaller contracts.
The council has also developed Sustainable Procurement Guidance and an
associated training module and embedded this within the tender process to
reflect the priorities and actions of the Climate Change Strategy. 
3.5.2 Action areas
Outcomes Actions include:
Support
suppliers to
reduce their
climate impact
▪ Developing a simple process for suppliers to evidence
their carbon reduction actions when bidding for smaller
contracts
▪ Developing an action plan for raising awareness to local
business of new opportunities created through the
Scottish Government’s Just Transition approach, following
approval of the Community Wealth Building Strategy
Maximise
opportunities for
climate action
through
procurement
▪ Continuing to develop the non-cash benefits available
through procurement
▪ Implementing updates into the procurement process
▪ Developing sustainable procurement guidance and
updating modules as appropriate
▪ Supporting and informing departmental lead officers
through the sustainable procurement process
Page 95

Page 96

14 
3.6   Nature and carbon sequestration 
3.6.1 Overview
The council has a duty to further the conservation of biodiversity when
carrying out our responsibilities. 
There are two broad national targets:
• Scotland will be nature positive by 2030 - halting and reversing nature
loss by 2030, measured from a baseline of 2020
• Biodiversity will be restored and regenerated by 2045
This ambition is further supported by NPF4. NPF4 places the climate and
nature crises at the centre of planning policy, in addition to rebalancing
planning policy to ensure that positive effects for biodiversity are secured.
The council’s Climate Change Strategy recognises the interrelationship
between climate and nature, and that the council must take action to protect,
restore and enhance biodiversity. A nature emergency was declared by the
council in February 2023. 
Many of the council’s activities have the potential to drive biodiversity loss or
nature recovery. These include discharging responsibility as a planning
authority through planning policy, as a landowner by how the council
manages its estate, and as an education authority through how well the
council connects young people with nature. Enhancing biodiversity also has
the opportunity to sequester carbon through well managed soil and
vegetation, thereby reducing net emissions (Figure 12). 
During 2023, the council’s Woodland and Forestry Strategy is being updated.
This alongside separate research into carbon sequestration potential of
council owned land will provide evidence to aid development of a planting
project which would work with community volunteers to plant trees and
wildflowers. 
Case study 5: Wards wildlife site - biodiversity enhancements 
Direct grants totalling £225,000 for restoring nature from the Scottish
Government have enabled a number of biodiversity enhancing projects
over the past two years. A priority for this funding is the Wards wildlife site
in Elgin as it is both a valuable space for people to enjoy nature, and for
wildlife to thrive. 
The wetland needs active management to keep it in a healthy condition,
so a plan is now in place to guide this work. The overgrown pond has been
partially cleared, restoring a large area of open water for birds,
amphibians, insects to thrive in. Several new wader scrapes have been
created, adding to the diversity of habitats.   
Water levels are now being monitored as there are suggestions the site
may be drying out. Careful management of the extensive ditch network
will ensure that the unique and valuable urban wetland continues to
provide unique homes for plants, animals and insects, as well as storing
carbon in the peaty ground and helping address climate change. 
Engagement with local schools and community groups is encouraging
people to become involved in looking after and enjoying the Wards. 
Page 96

Page 97

15 
3.6.3 Action areas
Outcomes Actions include:
Maximise
opportunities to
sequester
carbon within
existing council
assets
▪ Commissioning research for baseline carbon
sequestration potential of council land holdings, and
opportunities to expand and manage these assets
▪ Developing a Carbon Offsetting Plan which ensures that
management of council assets is planned to maximise
carbon sequestration
[biodiversity
outcomes – if
agreed by
Committee]
[A report on biodiversity is being presented to ED&I
committee in May 2023. Any agreed biodiversity actions will
be added here.] 
Figure 12. Nature based solutions to climate change (based on content from Improvement
Service 2021). 
3.7   External influence 
3.7.1 Overview
Many of the council’s statutory duties are related to helping reduce
greenhouse gas emissions in the wider Moray area. This includes actions
such as supporting energy efficiency improvements in homes, active travel
and green training as part of a Just Transition away from fossil fuels.
While this will not reduce the council’s direct carbon footprint, the Climate
Change Strategy also seeks to reduce carbon emissions across Moray.
Engaging with the community is essential to understand local concerns and
bring about necessary change. A collaborative approach can lead to more
effective policies, behavioural changes, enhanced community resilience and
a reduction in climate change impacts (Case Study 6).
The council has commenced work on its Local Heat and Energy Efficiency
Strategy (LHEES). This strategy is crucial for communities as it aims to
provide affordable and sustainable heating solutions, reduce energy
consumption and alleviate fuel poverty. LHEES can help to create jobs in the
green sector, improve health and wellbeing, and contribute to achieving net
zero – thus ultimately benefitting the community and wider environment.
NPF4 will help to guide the location of new housing, transport links and
infrastructure, ensuring that communities have access to the services they
need whilst enhancing the environment and meeting net zero targets. 
NPF4 introduces the concept of Local Place Plans (LPPs) which are
community-led plans that provide a framework for shaping the future of local
places. LPPs are an essential tool for engaging with communities and
fostering local democracy, ensuring that Moray’s towns and villages are
designed with the people who live there in mind.
The council’s Hydrogen Strategy seeks to create a local supply chain for
hydrogen production and use, providing job opportunities and economic
benefits for the region. Using green hydrogen as a fuel for transport, heating
and industrial processes will be essential to cutting Moray’s area emissions.
Adapting to the
impacts of
climate change
Reducing carbon
emissions and
storing carbon
safely
Preventing the
loss of
biodiversity and
protecting our
natural capital
Improving
health and
wellbeing and
reducing health
inequalities
Building
stronger and
more resilient
communities
Nurturing our
young people
Supporting a
Green Recovery
and Just
Transition
Page 97

Page 98

16 
Case study 6: Scotland’s Climate Week 2022 
A week of engagement across Moray, led by the council’s climate change
officers in collaboration with tsiMORAY aimed to highlight positive climate
action and bring people into the conversation. 
Fortunate timing made the use of one of the council’s new electric vehicles
available, enabling a team of officers and partners to travel across Moray.
The event engaged over 600 young people in two-way dialogue, and also
involved libraries, social enterprises, businesses, and the public in sharing
local, innovative, solutions to climate change. 
A follow up video highlighted the week’s activities and some of the areas
where the council and other organisations across Moray are taking action
on climate change. Dedicated climate change information for staff was
launched on Interchange during the week, along with a news item with links
to national events and quizzes. 
Schools and libraries welcomed being involved and suggested ways to
expand engagement in these areas. While the ability to hold such a wide
reaching event was a unique opportunity and is unlikely to be repeated
without additional resources, it was extremely valuable in terms of the
positive impact on young people, raising the profile of climate action in
Moray and demonstrating collaboration between different organisations
and council departments. 
3.7.2 Action areas
Outcomes Actions include:
Develop skills
and the
economy
▪ Increasing provision of relevant skills and knowledge for a
greener economy to support delivery of the Moray
Apprenticeship Strategy
▪ Supporting the planning and delivery of awareness raising
events for businesses to transition to a green economy
▪ Joining support networks to assist the progress of climate
change action
Enabling the
community to
understand and
take action on
climate change
▪ Consulting community groups and residents about climate
change action and delivering the Moray Climate Change
Engagement Strategy
▪ Supporting the work of the Moray Climate Assembly
▪ Engaging with communities to facilitate renewable energy
projects
▪ Promoting Moray-specific climate emergency training for
community groups and organisations 
▪ Promoting the Active Travel Strategy
▪ Delivering the LHEES programme
▪ Continuing the Energy Efficiency Scotland: Area Based
Scheme (EES: ABS)
▪ Delivering the Moray Hydrogen Strategy
Strategic
planning which
reflects the
climate and
nature
emergency
▪ Implementing NPF4 policies relating to the climate and
nature crises.
▪ Developing a Regional Spatial Strategy
▪ Reviewing the Forest and Woodland Strategy, Food
Growing Strategy and Open Space Strategy
▪ Developing 20-minute neighbourhood concepts for
Moray’s main towns and embedding within the next Local
Development Plan
▪ Promoting and supporting brownfield over greenfield
development
▪ Developing carbon guidance to support Moray Growth
Deal projects
▪ Developing carbon and offsetting guidance for
development applicants in line with NPF4
▪ Monitoring and reporting of area-wide carbon emissions
and actions                                                                                                                            
Page 98

Page 99

17 
4. What progress are we making? 
4.1  Current pathway of recorded emissions
The current pathway of recorded emissions is a projection towards 2030
using the baseline and other known emissions data. It shows how recorded
emissions may change over this time period when considering the council’s
pre-planned actions. Only activities which are highly likely are accounted for
within this projection. Carbon sequestration is considered and accounted for
within net zero projections separately in sections 4.5 and 5.1.
This pathway highlights the increase in emissions as a result of the council’s
services returning towards a ‘business as usual’ approach following the
pandemic. Notwithstanding that, the overall trend remains that emissions
continue to reduce from the baseline value to a level where a carbon
sequestration scheme may be used to offset any remaining emissions
(Figure 13). In this figure, annual emissions are divided into five categories
(Table 2).
Table 2. Explanation of emissions categories used in carbon emission reporting.
Category Description
Operating emissions Emissions generated by the council through its day-to-day
work. These consist of emissions that the council can
control and influence. These are recorded in the annual
greenhouse gas emissions reporting.
Waste Emissions from dealing with municipal and industrial-level
waste. These are recorded in the annual greenhouse gas
emissions reporting.
Building electricity Emissions from electricity use in council buildings. These
are recorded in the annual greenhouse gas emissions
reporting.
Transport Emissions from the operation of the council’s fleet vehicles
and vessels. These are recorded in the annual
greenhouse gas emissions reporting.
Building heat Emissions from heating of council buildings. These are
recorded in the annual greenhouse gas emissions
reporting.
The current pathway aims to find a compromise between speed,
technological limitations and funding. Whilst there are likely to be budgetary
restrictions, this pathway avoids late adoption of technology and measures.
This is to reduce carbon emissions and also because demand could impact
on the cost of supply as the 2045 deadline approaches and public and private
sectors are potentially legislated to take action.
A balanced approach to the implementation of measures is more likely to
benefit from reducing costs of measures as the scaling up of production
reduces costs. This could also allow planned solutions to align with national
infrastructure investment. For example, vehicles could continue to transition
to zero carbon using batteries, or hydrogen could become more dominant if
electricity distribution networks are unable to cope with the electrification of
both heat and transport. 
The calculations for the current pathway account for:
• Internal factors: Known internal changes that will impact on
emissions, e.g. confirmed waste management change.
• External factors: Known external changes that will impact on
emissions, e.g. ongoing decarbonisation of the national grid.
• Population change: Annual changes in population, based on the
2018 Scottish Sub-National Populations Projections for Moray, which
may impact future emissions. 
4.2 Progress
Progress has been made by climate change officers in improving the
council’s homeworking emission estimates. From reporting year 2022/23
onwards, this emission source is forecast to reduce considerably as more
information is available around homeworking employees.
A delay was experienced in implementing the planned shift from landfill to
energy from waste. This will now occur partially in 2023 and fully from 2024,
leading to a 95% reduction in waste emissions going forward.
Building electricity emissions continue to decrease primarily owing to
ongoing decarbonisation of the national grid. Council electricity use reduction
projects also contribute to this and currently have a target of 2% reduction
annually.
Page 99

Page 100

18 
0
5,000
10,000
15,000
20,000
25,000
30,000
2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030
Carbon emissions (tCO
2e)
Building heat Transport Building electricity Waste Operating emissions
Figure 13. Current pathway of recorded carbon emissions from baseline date to 2030. Figures from 2022 onwards are forecast estimates and denoted by a lighter colour.
Page 100

Page 101

19 
Difficulties in the global vehicle market has led to a slowdown in the
availability of electric vehicles for the council’s planned fleet replacement
programme. This will lead to an increase in diesel emissions into the late
2020s.
Building heat emissions remain relatively stagnant with the exception of
planned decarbonisation by 2030 of off-gas grid properties using gas oil. The
upcoming ‘Heat in Buildings Strategy’ will present a course of
decarbonisation action for the remaining building heat emissions. The
actions agreed within this strategy can then be used to inform future updates
to the Climate Change Plan and Routemap to Net Zero. 
4.3 Concerns
Given the current rate of progress, it is difficult to be confident there will be
sufficient progress in the decarbonisation of the building heat and electricity
categories to ensure that the net zero target is met without excessive carbon
sequestration offset. The current condition of some of the buildings is
unknown. Therefore, the works required to bring them to net zero is also
uncertain.
Net zero must be budgeted for and taken into consideration in the pace of
decision making around the renovation and rationalisation of the council
building stock. This will enable the production of accurate estimates of
financial costs and emissions reductions which will assist future planning.
The council’s smarter working, depot and store reviews must be completed
promptly to give direction on which buildings to improve and which to
rationalise. A completion timescale of 2023/24 is necessary to enable actions
to progress at a pace which assists in reaching the 2030 net zero target.
More efficient use of workspaces and technology could lead to a reduction
in single use accommodation and an increase in the number of co-located
partnership facilities.
The difficulties and expense of converting buildings to reach net zero means
that if delays are experienced then emissions relating to buildings may not
reduce sufficiently by 2030. Therefore, greater emphasis on other parts of
council operations reaching net zero quicker (following the aspirational
approach), and increased carbon sequestration, may have to be explored if
the pace of change continues to be insufficient and the target remains set at
2030.
If all information gathering and decisions on future change are made by 2025
then a more accurate assumption can be made for residual emissions and
the need for carbon sequestration through carbon sequestration insetting
and offsetting. This will provide a decision point milestone for the council to
reassess the commitment to the 2030 net zero target knowing the full costs
and carbon sequestration requirements. 
4.4 Benefits and threats associated with current pathway
In summary, the benefits of threats of the current pathway are:
Benefits Threats
Reflects the path the council is currently
pursuing. Does not commit the council
to altering the timing or type of planned
expenditure. 
Statutory deadlines are met.
Carbon sequestration will be required to
reach net zero by 2030 as
decarbonisation of estate and fleet will
not be complete. 
Uncertainty around timescale for
building improvement relating to carbon
emissions. 
Many of the current commitments to
reduce carbon emissions are currently
unfunded by the council. The council
requires to use its full breadth of powers
to raise/attract funding, apply for
government and other external funding,
and lobby for further powers or financial
assistance as may be required.
Page 101

Page 102

20 
4.5  Carbon sequestration
To continue delivering services, some residual emissions will be
unavoidable. Carbon sequestration will be required to offset these
emissions. Wherever possible this should take place on council owned land
and include wider community benefits, in line with national guidance9. 
Carbon is sequestered by vegetation and soil. The quantity of carbon that
can be sequestered varies according to land cover type. 
An analysis of the carbon sequestration potential of council land assets was
conducted in early 2023. The analysis provided:
• An approximate, current baseline level of carbon sequestration 
• An action plan to change existing land assets to sequester further
carbon
The current approximate baseline carbon sequestration value of all Moray
Council owned and operated land (an area of approximately 318 ha) is
estimated as 2,121 tCO2e per year.
Changing how the council manages its land to increase how much carbon is
held in vegetation and soils is central to mitigating climate change impacts10.
To this end, the types of land assets most suitable for change have been
identified. This provides an approximate additional carbon sequestration
value (above the baseline) of 2,277 tCO2e per year (Figure 14).
There is potential for even more carbon sequestration from council owned
land which is currently leased out. If some of this was developed into
woodland there is an estimated additional carbon sequestration value of
1,200 tCO2e per year. In addition to this there would be an opportunity to
include innovative projects such as green walls. Whilst such schemes can
deliver a wide range of co-benefits, the carbon sequestration potential is not
as significant as fully nature-based solutions.
A decision on the council’s approach to carbon sequestration will be the
subject of a report to committee in late 2023. This is necessary for the 
9 Scottish Government (2023) Guidance on nature-based carbon reduction projects.
10 NatureScot (2023) Managing nature for carbon capture.
required resource to be made available to progress beyond the current
baseline level of sequestration.
Figure 14. Carbon sequestration potential from council land assets.
0 1,000 2,000 3,000 4,000 5,000 6,000
Carbon sequestration from council land assets (tCO2e)
Current level
Potential
Potential additional (land
currently leased out)
Page 102

Page 103

21 
5. Where are we going?
5.1 Pathway to net zero
A net zero routemap provides options for the strategic decarbonisation of an
organisation over a set timescale. This document has been developed by
considering three possible approaches towards net zero emissions, involving
different combinations of decarbonisation interventions. This will enable the
council to engage strategically with the Scottish Government and other
partners on its net zero journey as all the options will involve partnership
working on actions and funding priorities.
The pathways being considered are:
• Current pathway - a realistic timescale built around the expected
work programme of the council but, until otherwise informed,
presumes a more restricted approach to aspects which are not yet
agreed. This includes projects which have not yet sourced external
funding, but set at a realistic, if challenging, timescale
• Aspirational approach – the quickest possible timescale to get
works done to meet the council’s net zero target. It is assumed that
finances will be available to invest in projects which will reduce future
costs. Timings take into account any technical issues which may
prevent work completion over a shorter timescale
• Restricted approach – a slower timescale than the current pathway
where, for whatever reason, additional resources are not prioritised
for climate change. This would have the consequence of potentially
missing the 2030 deadline and requiring substantially more
resources invested in carbon offsetting every year post 2045 to meet
national targets as a minimum
There is a lot of information currently unknown and so there are no firm
projections for these aspects. Assumptions have had to be made around the
aspirational and restricted approaches to heating decarbonisation, and to the
extent of improvements to council green space with possible nature and
carbon sequestration improvements. The assumptions behind the different
approaches are set out in Table 3.
Current pathway 
▪ It is not currently known if all statutory deadlines will be met. Achieving these
deadlines will be challenging.
▪ Projections for the future means that net zero carbon emissions by 2030 is
possible although more accurate data is needed.
▪ Requires quick roll out of building and fleet decarbonisation as soon as firm
plans made.
▪ Requires substantial additional investment which has not been budgeted for
in a short period of time.
▪ Medium to high level of carbon sequestration and associated costs.
▪ Potential revenue generating opportunities through the development of
commercial carbon offsetting schemes.
Aspirational approach
▪ Achieves net zero carbon emissions by 2030 target and all current statutory
deadlines.
▪ Maximise potential for carbon offsetting and aspirational approach for
heating decarbonisation.
▪ Additional staffing resource across services would be required.
▪ Potential revenue generating opportunities through the development of
commercial carbon offsetting schemes.
Restricted approach
▪ Some statutory deadlines will not be met.
▪ Net zero by 2030 target will only be met with substantial levels of offset at
significant cost to the Council.
▪ Uncertainty if delaying improvements will cost more or save money.
▪ Missed opportunity to generate revenue from emerging commercial carbon
offsetting market. 
Table 3. Assumptions behind routemap pathways.
Page 103

Page 104

22 
The current pathway represents the decisions which have been taken and,
where no firm plans are in place, presumes that decarbonisation will take
place at a rate to meet statutory deadlines. As shown in Figure 15, this
means the pathway is potentially closer to a restricted approach in 2030 but
could shift if more aspirational approaches to decarbonisation can be funded
and adopted.
Going forward there is still a large range in the possible level of carbon
emissions in 2030. We know that we will be somewhere between these and
our exact pathway will be dependent on the actions the council takes in all
areas of operations. While the 2030 target is possible, it will only be achieved
if the decarbonisation of heat in buildings happens at pace. At present there
is not firm costed plans or adequate levels of funding available to ensure this
will happen.
5.2 Limitations and risks
There are technological, practical, and financial limitations which will impact
on the route to net zero and have to be taken into account whether or not an
aspirational or restricted approach is preferred. 
These limitations include:
Area Limiting Factors
Buildings Financial costs of energy efficient buildings are likely to be 10% more
than standard buildings, although this should decline as technology is
mainstreamed.
There are practical limitations to the speed of decarbonising council
building stock:
▪ Reviews of the building stock and suitability of heating solutions
have to be carried out before budgets decided.
▪ Fabric first approach means improved insulation measures are
needed before new heating solutions.
▪ The heating solutions for some properties (e.g. hydrogen) have
not reached market yet. 
Transport Production restrictions and costs will influence when it is practical for
different types of vehicles to transition to low carbon alternatives.
Electric vans are more expensive and the transition of heavy plant is
only likely to be technologically practical toward the end of the
programme and may use different technologies such as hydrogen fuel
cells.
Improvements to infrastructure and training schemes for technicians
and mechanics are needed to make a move to low carbon alternatives
a success.
Waste The council has contractual conditions associated with the energy
recovery project.
Operating
Emissions
Smarter Working changes to working methods and services provision
will take time to be agreed.
Departmental thinking required to ensure climate change is a priority
and service change is agreed timeously.
Nature &
Biodiversity
Principles around the council offsetting have to be developed, e.g. It
should be local, and it should have co-benefits such as amenity or job
creation.
External
Influence
Opportunities to change these are limited because the council only has
influence, not control, over many of these. Therefore encouraging
behavioural change will be required.
Apart from access to capital resources, there are actions that can be taken
to lower these risk factors:
Figure 15. Possible range in net carbon emissions from present to 2030.
0
5,000
10,000
15,000
20,000
25,000
2022 2023 2024 2025 2026 2027 2028 2029 2030
Net carbon emissions (tCO
2e)
Estimated range in emissions between
aspirational and restricted approaches
Current pathway
Page 104

Page 105

23 
Area Risk Suggested possible action Outcome Co-benefits
Building heat Lack of capital resources and
uncertainty of the suitability of
different heating solutions prior to
fabric first improvements.
Currently planning is being
undertaken by staff with
significant existing workloads.
Dedicated staff resource to
manage building
decarbonisation. To initially
focus on planning of appropriate
interventions on a building by
building basis and then lead on
implementation. 
More certainty on timing and
which heating solutions are
suitable to meet the 2038 net
zero public buildings deadline.
Local businesses/employment know what work
is coming up and rationale for staff training or
business planning, heating costs reduced for
council.
Transport Delays in converting fleet to LEV
options because of uncertainty
around future technologies,
infrastructure, workshop facilities,
grid connections (electric),
availability - storage facilities
(hydrogen), staffing, technical
training & available budget.
Dedicated project management
resource within fleet to progress
decarbonisation project and
keep pace with the rapidly
expanding LEV marketplace.
More certainty over emerging
technology options and
timetable for fleet
decarbonisation. Reduced
carbon emissions in line with the
councils route map to net zero
Encourage wider local market to decarbonise,
demonstrate leadership, driving hydrogen
economy and EV provision so supporting other
public and private sector fleet providers, health
improvements through lower particulate
emissions and anthropogenic heat.
Waste Lack of progress on reuse and
recycling to lower residual waste
volumes. Lack of waste education
resources.
Create dedicated waste
education resource within
council or support equivalent
third sector project
Community buy-in for recycling
and reuse initiatives. Lower
residual waste emissions.
Increased third sector involvement, financial
savings for community through re-use,
reduction in waste costs.
Operating
Emissions
Lack of priority given to climate
change at a sectional level means
opportunities to reduce emissions
are missed.
Include appropriate reporting in
service plans to ensure climate
change is a sectional priority
and service change is
progressed.
Expand our roll out of Carbon
Literacy Training and require
key individuals to participate.
Carbon budgets and PIs
implemented within sections.
Grey fleet governance
improvement.
Training of elected members,
senior managers and officers
with significant carbon
responsibility.
Financial savings through reduction in
resource use, waste, travel, energy, potential
culture change and staff sense of involvement
through ability to influence change
Engagement and training would have the
potential to increase the pace of getting to net
zero.
Nature &
Biodiversity
Council open space is not used to
promote biodiversity and nature
enhancement.
Create dedicated project
management resource within
Open Spaces to progress
practical biodiversity and
decarbonisation work.
Nature and biodiversity
improvements on council open
space. Enable access to nature
funding sources for greenspace
improvements.
Health improvements through better green
space, nature and biodiversity, opportunities
for community involvement in biodiversity
projects.
External
Influence
Lack of resource allocation
means no opportunity to engage
meaningfully with community.
Increase resources for climate
change community engagement.
Support community and
businesses and allow projects to
progress across Moray.
Community involvement, a focal point for
community and businesses to lead on climate
action.
Page 105

Page 106

24 
While property, fleet and waste services are planning to decarbonise their
activities, the co-benefits of investing in climate change action and reducing
carbon emissions will be to assist local business and the third sector as well
as showing leadership and a way forward through the crisis.
By May 2024 our Climate Change Strategy will be updated. This process will
be an opportunity to include carbon reduction targets in individual service
plans. This would give a focus on reducing carbon emissions through service
delivery and not just through areas like fleet and property. Rolling out the
Carbon Literacy Training will embed this knowledge throughout the council
and enable staff in all sections to look over the plans of their sections to
highlight carbon savings and how service delivery could adapt to a changing
climate. 
5.3 2025 decision point
If all relevant information is gathered and decisions on decarbonisation are
made by 2025 then more accurate calculations can be made for the level of
residual emissions in 2030 and the need for carbon sequestration through
inset/offset. However, a commitment to resource an aspirational approach
will need to be taken soon in order to guarantee the 2030 target will be met.
At present there is not adequate levels of funding allocated to allow such an
aspirational approach to happen.
The decision point milestone will enable the council to reassess the
commitment to the 2030 net zero target knowing the full costs and carbon
offsetting requirements. This will enable a more informed decision to be
made regarding whether the target of being net zero by 2030 is achievable
with resources and redesign or if it is advisable to push back the target and
invest in other aspects to ensure an appropriate response to the climate and
nature emergencies. 
5.4 Adaptation and resilience 
We have a statutory duty within the Public Bodies Climate Change Duties
annual report to record how we are contributing to Scotland’s Adaptation
Programme. There is also a statutory duty to carry out actions to adapt to
the impacts of climate change. 
Case study 7:  Flood and coastal defences 
In the last decade, over £170 million has been invested to alleviate the
impacts of flooding in Moray. These flood alleviation schemes have
protected homes and infrastructure from flood events to an estimated
value of £86 million and counting.
An innovative pathway approach is now being used to develop new flood
and coastal erosion plans. This will enable the council to plan for, and
react to, different scenarios as they are triggered. Collaborative working
across services will ensure the coastal plans links with wider adaptation
plans and how services can be delivered while taking into account of
possible climate change impacts. 
The local impacts of climate change will include:
• damage to infrastructure such as buildings, roads and power
supplies
• damage to ecosystems, water supplies and agricultural production
• disrupted food supply chains and increased costs
• disproportionate health and economic effects on vulnerable groups
Global carbon emission trajectories at present fall far short of restricting
average temperature rises to a safe 1.5°C. If global targets continue to be
missed then the quality of life we know in Moray today will no longer be
Page 106

Page 107

25 
recognisable to our children by 2100, due to the extreme circumstances they
will be living in. 
Pressure on council services will increase as a result of climate change.
Action taken now to reduce our emissions and to prepare for climate change
impacts will minimise damage, reduce overall costs and protect the most
vulnerable people in our communities. 
Page 107

Page 108

26 
6. Conclusion
It is feasible for Moray Council to achieve net zero by 2030, but only if key
decisions on building decarbonisation and rationalisation of the estate are
taken, and progress is made to consistently improve fleet vehicles, reduce
waste, and improve insulation, heating, and hot water systems over the next
seven years. This means the 2030 target will only be achieved if a more
aspirational approach to decarbonisation is adopted. Present levels of
funding and resources means a more restricted pathway is currently being
adopted. 
The expected level of capital spend means that securing external funding for
measures such as decarbonising council buildings will be essential if the
target of 2030 is to be met. Although increasingly all external funding has net
zero as a condition of grant regardless of the main purpose, the level of work
required to decarbonise public buildings will require specific additional
funding just for that purpose.
If all relevant information is gathered and long term decisions on
decarbonisation are made by 2025 then more accurate calculations can be
made to determine the residual emissions in 2030 and the need for carbon
sequestration through inset/offset. In addition it may be possible to better
quantify and accelerate change in carbon reductions through embedding
climate actions into service delivery plans.
This will provide the information for a decision point milestone to allow
reassessment of the commitment to the 2030 net zero target knowing the full
costs and carbon offset. A more informed decision can be made whether the
target of being net zero by 2030 is achievable or if it is advisable to review
the target and invest in other aspects of climate change to ensure an
appropriate response to the climate and nature emergencies.
A proactive pathway as demonstrated by the aspirational approach could
avoid a situation whereby we pay a premium for low-carbon solutions in the
future because demand exceeds availability, and for commercial carbon
offsetting schemes. However, caution should also be taken as buying carbon
solutions too soon may involve a premium for new technology. Hence there
is a need for an agile approach which can flex across planned approaches
as the context demands, informed by expertise. 
While the 2030 target is possible, it will only be achieved if there is a shift in
focus onto a more aspirational route. At present there is not adequate levels
of funding available to ensure the reduction in carbon emissions will happen
at the required pace. Without deploying our existing resources, creating
additional staff resources in key areas, a defined capital plan contribution,
and more external funding secured, the restricted pathway is looking more
and more likely to continue and so bring the prospect of pushing back the
date when we will reach net zero. 
As the energy price increases over the last six months has shown,
assumptions on potential cost savings through energy interventions are
difficult to predict. However, it is known that investing is energy saving early
will save costs, and investment in energy schemes has the potential to
provide income for the Council which could contribute to the decarbonisation
programme. 
Page 108

Page 109

27 
Glossary
Term Definition
Active travel Journeys made by modes of transport that are fully or partially people-powered, irrespective of the purpose of the journey. It includes walking, people using
wheelchairs, cycling (including e-bikes) to name a few.
Adaptation Adjustments in natural or human systems in response to actual or expected climatic stimuli or their effects, which moderates harm or exploits beneficial opportunities.
Anthropogenic Resulting from or produced by human activities.
AR6 Synthesis Report A comprehensive summary of the latest scientific knowledge on climate change, including its impacts, risks, and potential solutions, compiled by the IPCC.
Baseline Historical period specified for the purpose of comparing greenhouse gas emissions.
Biodiversity The variability among living organisms from all sources, including, inter alia, terrestrial, marine and other aquatic ecosystems and the ecological complexes of which
they are part; this includes diversity within species, between species and of ecosystems (UN 1992).
Carbon In this context, an umbrella term used to describe all of the greenhouse gases.
Carbon dioxide (CO2) A naturally occurring gas, CO2 is also a by-product of burning fossil fuels (such as oil, gas and coal), of burning biomass, of land-use changes and of industrial
processes (e.g., cement production). It is the principal anthropogenic greenhouse gas that affects the Earth’s radiative balance.
Carbon Literacy
Training
Certificated training which equips individuals with the knowledge, skills and motivation to reduce their carbon footprint and take practical action to mitigate climate
change, based on a thorough understanding of the science and impact of carbon emissions.
Carbon sequestration The process of removing carbon from the atmosphere and storing it in long-term carbon sinks.
Circular economy A circular economy is one in which resources are kept in use for as long as possible.
Climate action Efforts taken to mitigate and adapt to the impacts of climate change.
Climate change The state of the climate that can be identified (e.g., by using statistical tests) by changes in the mean and/or the variability of its properties and that persists for an
extended period, typically decades or longer.
Climate emergency A situation in which urgent action is required to reduce or halt climate change and avoid potentially irreversible environmental damage resulting from it.
Climate refugee A person who has been forced to flee their home because climate change has made it impossible to stay.
Climatological event Events reflecting changes in weather patterns over a long term (e.g. droughts, heatwaves), or events influenced by these changes (e.g. wildfires).
Co-benefits The positive effects that a policy or measure aimed at one objective might have on other objectives, thereby increasing the total benefits for society or the environment.
Co-benefits are often subject to uncertainty and depend on local circumstances and implementation practices, among other factors.
Direct emissions Emissions directly under the organisation’s control.
Drought A prolonged period of abnormally dry weather that results in a water shortage, causing significant impacts on crops, ecosystems and human activities.
Page 109

Page 110

28 
Ecosystem services
Ecological processes or functions having monetary or non-monetary value to individuals or society at large. These are frequently classified as (1) supporting services
such as productivity or biodiversity maintenance, (2) provisioning services such as food or fibre, (3) regulating services such as climate regulation or carbon
sequestration, and (4) cultural services such as tourism or spiritual and aesthetic appreciation.
Excess deaths The number of deaths that occur which exceed the expected number of deaths based on historical data or trends.
Flood The overflowing of the normal confines of a stream or other body of water, or the accumulation of water over areas that are not normally submerged. Floods include
river (fluvial) floods, flash floods, urban floods, pluvial floods, sewer floods and coastal floods.
Fuel poverty A situation where households struggle to afford adequate heating and energy services, leading to poor living conditions and negative health and wellbeing outcomes.
This is often considered to be where fuel costs exceed 10% of net income after housing costs.
Green jobs Employment opportunities which contribute to environmental sustainability.
Green recovery The transition to a more sustainable and resilient economy following a crisis, such as the Covid-19 pandemic, that prioritises investment in low carbon technologies,
sustainable infrastructure and job creation in environmentally friendly sectors.
Greenhouse gas
emissions Any gas that contributes to the greenhouse effect by absorbing infrared radiation in the atmosphere.
Heatwave A heatwave is an extended period of hot weather relative to the expected conditions of the area at that time of year. In Moray, a heatwave event is defined as at least
three consecutive days with daily maximum air temperatures meeting or exceeding 25°C.
Indirect emissions Emissions outside the organisation’s control but over which it has an influence.
Insetting The process of offsetting carbon emissions by sequestering carbon within the organisation's own landholdings.
IPCC Intergovernmental Panel on Climate Change. A scientific body established by the United Nations to provide policymakers with regular assessments of the state of
climate science and the potential impacts of climate change, as well as strategies for mitigation and adaptation.
Just Transition The process of transitioning to a sustainable economy that is socially equitable, inclusive, and which provides fair opportunities for workers and communities affected
by the shift.
Meteorological event Short-term weather events occurring over a period of hours or days (e.g. convective storms).
Mitigation A human intervention to reduce emissions or enhance the sinks of greenhouse gases.
Nature emergency The rapidly worsening state of the natural world, including the loss of biodiversity, ecosystem degradation, and the threat of ecological collapse, caused by human
activities such as habitat destruction, pollution and climate change.
Net zero Net zero emissions are achieved when anthropogenic emissions of greenhouse gases to the atmosphere are balanced by anthropogenic removals over a specified
period.
Offsetting The practice of compensating for carbon emissions by funding projects that reduce greenhouse gas emissions outside of the organisation's own landholdings.
Sustainability A dynamic process that guarantees the persistence of natural and human systems in an equitable manner.
tCO2e Tonnes of carbon dioxide equivalent. A metric used to compare the emissions from various greenhouse gases on the basis of their global-warming potential, by
converting amounts of other gases to the equivalent amount of carbon dioxide with the same global warming potential.
Wildfire Any uncontrolled vegetation fire which requires a decision, or action, regarding suppression. 
Page 110

Page 111

APPENDIX 2
1 | P a g e
M: Mitigation action       A: Adaptation Action       B: Biodiversity Action
Climate Change Strategy Actions
Details of Climate Change Strategy Actions with an initial explanation of completions, updates and actions added, followed by a full list of the updated
actions. Progress on these actions are reported to the Climate Change Board on a quarterly basis and updated to ED&I committee on an annual basis.
Actions Completed
Action Explanation for Completion
Continue to purchase vehicles with anti-idling
technology 
Trucks come as standard with anti-idling tech, we monitor other vehicles via on board vehicle
telematics. Action closed to enable focus on other action areas.
Improve sustainability and recycling in schools
including reduction / elimination of single use plastic
packaging, a greater selection of recyclable materials
across school catering services
Banning of single use plastic means much of this has been superseded. Marked as completed and
another action added for council buildings/waste education in general.
Embed net zero aspirations in Levelling Up Fund bid Completed. Projects aim to reduce carbon through reuse of vacant and derelict sites, using
renewable energy solutions and innovative design, promoting active travel and promoting
biodiversity greening of the Centre.
By default operate PCs and related equipment in the
most energy efficient mode, e.g. auto switch off
A technical policy has been implemented to automatically power off PCs in schools at a certain
time. Continue to utilise the various national hardware frameworks to ensure that the devices we
procure, adhere to these. There is little more that can be achieved and this action can be closed.
Actions Updated
Action Explanation for Update
Replace vehicles with low energy alternatives as soon
as is practically feasible
Align Moray Council targets for fleet decarbonisation with the Scottish Government targets to
phase out light commercial vehicles by 2030 and heavy duty vehicles by 2040.
Progress a “fabric first” approach to allow buildings to
reduce carbon emissions to net zero
Challenges of costs including capital investment which does not generate any financial savings
and potential increased running costs in relation to decarbonisation. All capital interventions
required, which do not have a spend to save payback within 15 years, must be provided with a full
Item 6c)
Page 111

Page 112

APPENDIX 2
2 | P a g e
M: Mitigation action       A: Adaptation Action       B: Biodiversity Action
life cycle cost appraisal taking account of net zero objectives.
Reporting of area-wide emissions and actions. Lack of capacity for wider community engagement means area wide report will be developed
alongside the Regional Spatial Strategy
Support the development of carbon knowledge and
skills to promote innovation and effective carbon
management across departments
After an initial pilot, a lack of capacity to continue to support individual climate change champions
means the focus will be on support for sections to reduce their individual emissions.
Community actions (7.10 – 7.14) Lack of capacity for wider community engagement means these actions will be progressed by the
Moray Climate Hub with support from Council officers. 
Actions Added
Action Explanation for Addition
Adaptation benchmarking - Identify current
adaptation work happening across the council,
including gaps and opportunities
Overview of Councils Climate Change adaptation plans now part of the annual statutory return.
Continue to deliver the Moray Hydrogen Strategy, and
explore accessing other available funds if resources
allow.
To include hydrogen update that was missing from original CCS actions.
Moray Growth Deal Carbon Guidance Additional guidance required
NPF4 Carbon guidance for applicants and offsetting
requirements
Required due to new National Planning Framework 4
Improve sustainability and recycling in schools and
across council buildings. Promote recycling and waste
reduction through waste education.
To replace action on single use plastics. 
Page 112

Page 113

APPENDIX 2
3 | P a g e
M: Mitigation action       A: Adaptation Action       B: Biodiversity Action 
1  Building heat and electricity 
Action M A B Time Period/Phase SMART Measure Resources Delivery Lead
1.1 Progress a “fabric first” approach to allow buildings
to reduce carbon emissions to net zero
Y Y  Design – plan and budget for
decarbonisation. Backstop date of
2038 to decarbonise heating
systems in public buildings
Building SAP Ratings; % of
carbon neutral council
buildings
Staff time and
significant external
capital resources
required
Property
Services
1.2 Increased renewable energy generation from
Council buildings and land. Subject to project
appraisal and technical feasibility.
Y Y  Scoping & research.  Delivery
during 2023/24
Capacity (kW) of energy
generation installed
All projects would
be subject to
business case
approval with a
defined ROI.
Energy
1.3 Complete Learning Estate Asset Management plan
to identify opportunities for 'Heating and Power'
refurbishment and implemented over next 10
years.
Y   Scoping & Research. Complete
2024/25. Backstop date of 2038 to
decarbonise heating systems in
public buildings
Building SAP Ratings; % of
carbon neutral council
buildings
Staff time and
significant external
capital resources
required
Programme
Manager,
Learning Estate
1.4 Aim to achieve zero carbon standards in all new
buildings, including housing and schools
Y   Design and Development , no
timescale set
% of new buildings that are
net zero carbon standard
Additional expense
over non net-zero
building
Property
Services
1.5 Achieve Energy Efficiency Standard for Social
Housing (EESSH) for all Council houses
Y   Delivery – ongoing. EPC Band C or
higher by 2025.
EPC Band B or higher by 2032
% of Council houses achieving
EPC Band B (Energy Efficiency
rating), or are as energy
efficient as practically
possible.
% of Council houses that are
carbon neutral.
External resources
required to achieve
ambition
Property
Services
1.6 Increase building user awareness of ways of
reducing energy use and saving utility costs.
Y   Delivery - ongoing No of energy events Staff time Energy 
Page 113

Page 114

APPENDIX 2
4 | P a g e
M: Mitigation action       A: Adaptation Action       B: Biodiversity Action 
2  Transport 
Action M A B Time Period/Phase SMART Measure Resources Delivery Lead
2.1 Replace vehicles with low energy alternatives as
soon as is practically feasible
Y Y  Targets for fleet decarbonisation
aligned with the Scottish
Government targets to phase out
light commercial vehicles by 2030
and heavy duty vehicles by 2040
Fossil fuel consumption
reduced by 55% by 2030.
Vehicle
replacement
programme. Staff
time and capital
resources required
Transport
2.2 Develop and promote Travel Plans for Moray
Council, Major Employers and Schools
Y   Delivery - ongoing Staff Surveys on Travel
Behaviour. Number of
schools and businesses with
Travel Plans implemented.
Staff time Transport
2.3 Active Travel to School campaign and promotion,
including parking management around schools,
and supporting modal shift from vehicles to active
travel wherever feasible
Y   Delivery - ongoing No of pupils using active
travel
Staff time Transport
2.4 Develop Strategy and Guidance for provision of
Public Electric Vehicle Charging facilities in Moray
Y   Delivery - ongoing Number and type of public EV
chargers 
Implement as
funding becomes
available.
Transport 
3  Waste 
Action M A B Time Period/Phase SMART Measure Resources Delivery Lead
3.1 Reduction of waste landfilled through diversion to
energy recovery
Y   Design. Complete in 2023/24 95% diversion from
landfill by 2024
Staff time Waste
3.2 Reduce waste through reuse and recycling Y   Delivery – Ongoing. Application for increase recycling rates Staff time Waste
Page 114

Page 115

APPENDIX 2
5 | P a g e
M: Mitigation action       A: Adaptation Action       B: Biodiversity Action
a re-use hub
3.3 Improve sustainability and recycling in schools and
across council buildings. Promote recycling and
waste reduction through waste education.
Y   Delivery. Ongoing  Staff time Waste
3.4 Supporting creation and promotion of Community
Identified Benefits portal. Facilitating collaborative
relationships between local construction firms /
developers and circular economy initiatives.
Y Y Y Delivery - ongoing Record of circular economy
focussed community benefits
Staff time New CWB post
structure TBC 
4  Operating Emissions 
Action M A B Time Period/Phase SMART Measure Resources Delivery Lead
Smarter Working
4.1 Support homeworkers to reduce their emissions
through promotion or signposting to advice and
explore potential for practical assistance
Y   Delivery - ongoing  Staff time Climate Change
/ Energy
4.2 Determine which buildings are surplus to
requirements. Development of shared co-
location facilities for all community areas (e.g.
business, volunteers, leisure)
Y   Scoping & Research. Complete in
2023/24
Progress by 2023/24  Heavily dependent
upon other factors,
e.g. multiple
reviews, external
partners, etc.
Property
Services
4.3 Promote on-line working / Smarter Working Y   Delivery. Ongoing Reduction in office space.
Reduction in officer travel.
Increase in flexible working
arrangement 
Property
Services
4.4 Increase use of virtual environment to reduce
server network and consequent electricity
consumption
Y   Delivery. Ongoing  Incorporate into
ICT Digital Strategy
- draft by 2023
ICT
Page 115

Page 116

APPENDIX 2
6 | P a g e
M: Mitigation action       A: Adaptation Action       B: Biodiversity Action
Governance & Training
4.5 Apply zero and low carbon objectives as a factor
in all investment decisions in relation to budgets
and the Capital Plan
Y Y Y Design & development Incorporate carbon
objectives into the AMWG,
budgets and capital plan
Staff time Climate Change
supported by
other sections
as appropriate
4.6 Ensure the Climate Change Strategy and
associated Action Plan are living documents and
remain fresh and valid until 2030.
Y Y Y Delivery. Ongoing CCS reviewed every 3 years.
Route Map reviewed
Annually, with updates every
six months
Staff time Climate Change
4.7 Climate Change and Biodiversity assessed as part
of all committee papers
Y Y Y Delivery. Ongoing  Staff time All sections
4.8 Adaptation benchmarking - Identify current
adaptation work happening across the council,
including gaps and opportunities 
y  Delivery. Initial benchmarking
complete by November 2023 
Staff time Climate Change
supported by
other sections
as appropriate
4.9 Carbon Literacy – In depth training on climate
change implications and opportunities to be
delivered in house
Y Y  Delivery. Ongoing No of staff completed
training, follow up surveys
on impact
Staff time Climate Change 
4.10 Update online Climate Change awareness
training 
Y   Design and development.
Complete in 2023/24
No of staff through training  Staff time Climate Change
4.11 Support the development of carbon knowledge
and skills to promote innovation and effective
carbon management across departments
Y   Design & development in 2023/24
to allow carbon budgeting
included in Section PIs 
Staff time Climate Change
supported by
other sections
as appropriate
Education
4.12 Support opportunities for teachers and pupils to
access and share  knowledge and resources  to
progress climate change work
Y  Y Delivery. Ongoing  Staff time Climate Change
4.13 Increase opportunities for Learning for
Sustainability within the curriculum for children
and young people.
Y  Y Delivery. Ongoing No of training/CPD sessions
delivered to staff. No of early
years settings/ schools with
Learning for Sustainability
Staff time Education
Page 116

Page 117

APPENDIX 2
7 | P a g e
M: Mitigation action       A: Adaptation Action       B: Biodiversity Action
(LfS) in their curriculum
Improvements in outdoor
learning environment
4.14 Continue to make school meals more sustainable
with a reduced carbon impact. Develop and
promote more vegetarian options, e.g. ‘meat
free’ days and vegan options
improved recycling & food composting facilities
in schools
Y   Delivery. Ongoing Percentage of food and
produce sourced locally.
Percentage of meal options
offered that are vegetarian
or vegan
Menu planning and
local suppliers
Catering /
Climate Change 
5   Procurement and Investment 
Action M A B Time Period/Phase SMART Measure Resources Delivery Lead
5.1 Continue to develop the non-cash benefits
available through procurement
Y Y  Delivery. Ongoing Monitor and report on
through the sustainable
procurement section of the
Annual Procurement Strategy
Procurement team
and lead officer
Procurement
and new CWB
post structure
TBC. Climate
Change to
assist.
5.2 Implement updates into procurement process Y   Scoping & Research. Ongoing Update to SPD Staff time Procurement
5.3 Develop simple process for suppliers to evidence
their carbon reduction attempts when bidding for
smaller contracts
Y   Scoping & Research. Ongoing Measure use of tool Staff time to
develop process, to
trial and
implement.
Climate Change
to assist in
developing and
progressing
5.4 Develop an action plan for raising awareness of
local business of new opportunities created
through just transition, following approval of CWB
strategy.
Y   Scoping & Research. Ongoing No of suppliers assisted. Staff time to
develop
communications
plan and participate
in Supplier
Development
Forum
Procurement /
new CWB post
structure TBC. /
Climate change
Page 117

Page 118

APPENDIX 2
8 | P a g e
M: Mitigation action       A: Adaptation Action       B: Biodiversity Action
5.5 To further develop Sustainable Procurement
guidance and support and inform departmental
lead officers through the process.  Modules can be
reviewed for further updates as appropriate.
Y   Scoping & Research. Ongoing Increase in the number of
sustainable measures noted
and incorporated in tender
submissions
Staff time Procurement
with Climate
Change to assist 
6   Nature and biodiversity 
Action M A B Time Period/Phase SMART Measure Resources Delivery Lead
6.1 Commission research for baseline carbon inset of
council land holdings, along with opportunities to
expand and manage
Y Y Y Commission research during
2022/23
Research delivered Staff time – JT Fund Climate Change
6.2 Development of Carbon Offsetting Plan and
ensuring management of council land holdings is
planned to maximise carbon sequestration
Y Y Y Develop plan in 2022/23 and
review management in 2023/24
Plan delivered and work
started
TBD Climate change,
Estates, Open
Spaces 
The report on biodiversity going to ED&I in May is
the opportunity to determine actions and add any
to the Climate Change strategy. Agreed actions will
be included here       
7   External Influence 
Action M A B Time Period/Phase SMART Measure Resources Delivery Lead
Strategic Delivery 
Page 118

Page 119

APPENDIX 2
9 | P a g e
M: Mitigation action       A: Adaptation Action       B: Biodiversity Action
7.1 Develop LHEES Strategy Y   Creation of strategy by December
2023 
Staff time, technical
support
Climate Change
7.2
Continue the Energy Efficiency Scotland: Area
Based Scheme EES:ABS
Y   Ongoing SHCS - % of private sector
dwellings with SAP B or C
Dependant on
continued Scottish
Government
funding.
Housing Services
7.3
Promotion of the Active Travel Strategy Y   Delivery. Ongoing Mode of transport survey
information. Quantity of new
active travel infrastructure
provided Number of website
'hits'
Staff time Transport
7.4
Continue to deliver the Moray Hydrogen Strategy,
and explore accessing other available funds if
resources allow.
Y Y  Ongoing  Staff time Climate Change
Officers with
support from
Fleet, Energy
and Property as
appropriate
7.5
Reporting of area-wide emissions and actions.  Y Y Y Link with the Regional Spatial
Strategy 
Staff time Strategic
Planning &
Development
7.6
Engagement Strategy - Consult, raise awareness,
communicate and engage with staff, residents,
businesses and organisations across Moray about
climate change. Promote relevant campaigns. 
Y Y Y Delivery. Ongoing Greater engagement from
staff and residents
Staff time Climate change,
alongside
energy team,
transport, waste
team etc. as
appropriate and
external CPP
partners
7.7 Join support networks to assist the progress of
climate change work 
Y Y Y Delivery. Ongoing Involvement with support
networks
Staff time Climate change
Skills and Economic Development
7.8
Increase the provision of relevant skills and
knowledge for a greener economy to support
deliver of the Moray Apprenticeship Strategy.
Y  Y Delivery. Ongoing  Staff time New CWB post
structure TBC,
Economic
Page 119

Page 120

APPENDIX 2
10 | P a g e
M: Mitigation action       A: Adaptation Action       B: Biodiversity Action
Working in partnership with UHI Moray, Moray
Chamber, FSB.
Development,
Business
Gateway
7.9
Support planning and delivery of awareness raising
event to promote new opportunities for existing
businesses in the green economy transition.
Y Y  Delivery. Ongoing   New CWB post
structure TBC,
Economic
Development,
Business
Gateway
Community Action
7.10 Assist effective governance for CC priorities for
Moray.
Y Y Y  Monitoring and reporting
system in place. Improved
communication between
local orgs and Moray Council
regarding climate change
policy and action
Staff time Climate Change
in partnership
with the CPP,
public, private
and community
organisations. 
A key role for
the Moray
Climate Hub
7.11 Consult community groups and residents about
climate change
Y Y Y 
7.12 Support the work of the Moray Climate Assembly. Y Y Y 
7.13 Engage with local communities to facilitate
renewable energy
Y Y  
7.14 Promote Moray-specific climate emergency
training for local groups and organisations
Y Y Y 
Strategic Planning & Development
7.15
Implement NPF 4 policies relating to the climate
and nature crisis.
Y Y Y Delivery. Ongoing  Staff time Strategic
Planning &
Development
7.16
Develop Regional Spatial Strategy, concentrating
growth in existing centres, identifying
opportunities for carbon reduction and renewable
energy projects, woodland expansion, peatland
restoration
Y Y Y Delivery - ongoing  Staff time Strategic
Planning &
Development
7.17
Review Forest and woodland strategy Y Y Y Delivery - ongoing  Staff time Strategic
Planning &
Development
Page 120

Page 121

APPENDIX 2
11 | P a g e
M: Mitigation action       A: Adaptation Action       B: Biodiversity Action
7.18
Develop 20 minute neighbourhood concepts for
Moray’s main towns, and embed within next Local
Development Plan
Y Y  Delivery - ongoing  Staff time Strategic
Planning &
Development
7.19
Promote and support brownfield development
over greenfield development.
Y  Y Delivery - ongoing Setting targets for brownfield
development in housing land
requirements
Enacting this will
require budget
support
Strategic
Planning &
Development
7.20
Deliver Moray Growth Deal Housing Mix Delivery
project.
Y Y Y Design & Development. Complete
2025/26 
Staff time Strategic
Planning &
Development
7.21
Review and support Food Growing Strategy and
Open Space Strategy
Y Y Y Delivery - ongoing maximise food growing
opportunities and to
maximise opportunities for
tree planting and active
travel measures
Staff time Strategic
Planning &
Development
7.22 Moray Growth Deal Carbon Guidance    Complete 2025/26  Staff time Strategic
Planning &
Development
7.24 NPF4 Carbon guidance for applicants and
offsetting requirements   
Ongoing  Staff time Strategic
Planning &
Development 
Page 121

Page 122

12 | P a g e
Overview of Actions
Key
Phase 1 - Scoping & Research
Phase 2 - Design & Developing Business Case
Phase 3 - Delivery 
No. Action
2021/22
2022/23
2023/24
2024/25
2025/26
2026/27
2027/28
2028/29
2029/30
2030/31
1.1 Progress a “fabric first” approach to allow buildings to
reduce carbon emissions to net zero                    
1.2 Increased renewable energy generation from council
assets.                    
1.3 Complete Learning Estate AMP.                    
1.4 Implement zero carbon standards in new buildings.                    
1.5 Achieve EESSH for all council houses.                    
1.6 Increased building user awareness on energy usage.                    
2.1 Replace vehicles with low energy alternatives as soon
as is practically feasible.                    
2.2 Develop and promote Travel Plans for council, etc.                    
2.3 Promote and enhance active travel at schools.                    
2.4 Develop strategy and guidance for public EV charging
facilities.                    
3.1 Reduction of waste landfilled through diversion to
energy recovery.                    
3.2 Reduce waste through reuse and recycling.                    
3.3 Improve sustainability and recycling in schools and
across council buildings.          
3.4 Support creation and promotion of Community
Identified Benefits porta.                    
4.1 Support homeworkers to reduce their emissions.                    
4.2 Ratify buildings and develop shared facilities.                    
4.3 Promote and increase opportunities for smarter
working.                    
4.4 Increase use of virtual environment for information.                    
4.5 Apply zero and low carbon objectives in all investment
decisions.                    
4.6 Ensure CCS and CCAP remain fresh and valid until
2030.                    
4.7 CC and Biodiversity assessment as part of all
committee papers.                    
4.8 Adaptation benchmarking          
4.9 Deliver carbon literacy training.                    
4.10 Update CC awareness training as part of staff
induction process.                    
4.11 Support the development of carbon knowledge and
management across departments                    
4.12 Support networking opportunities for teachers and
pupils on CC.                    
4.13 Increase opportunities for Learning for Sustainability
in schools.                    
4.14 Continue to reduce carbon impact of school meals.                    
5.1 Continue to develop the non-cash benefits through
procurement.                    
5.2 Implement updates into procurement process.                    
Page 122

Page 123

13 | P a g e
5.3 Develop simple process for suppliers to evidence
carbon reduction.                    
5.4 Develop action plan for raising awareness of local
businesses.                    
5.5 Develop sustainable procurement guidance and
inform lead officers.                    
6.1 Commission research for baseline carbon inset                     
6.2 Development of Indicative Carbon Offsetting Plan.                    
7.1 Develop LHEES strategy.                    
7.2 Continue the EES ABS programme.                    
7.3 Promotion of the Active Travel Strategy.                    
7.4 Moray hydrogen Strategy          
7.5 Reporting of area-wide emissions.                    
7.6 Internal CC Engagement.                    
7.7 Join support networks to assist the progress of climate
change work                     
7.8 Feed into the development of Moray apprenticeship
strategy.                    
7.9 Support awareness raising for businesses.                    
7.10 Assist effective governance for CC priorities for Moray.                    
7.11 Consult community groups and residents about
climate change                    
7.12 Support the work of the Moray Climate Assembly.                    
7.13 Engage with local communities to facilitate renewable
energy                    
7.14 promote Moray-specific climate emergency training                     
7.15 Implement NPF 4 policies relating to the climate crisis.                    
7.16 Develop Regional Spatial Strategy                    
7.17 Review Forest and woodland strategy                    
7.18 Develop 20 minute neighbourhood concepts for
Moray’s main towns                    
7.19 Promote and support brownfield development over
greenfield development.                    
7.20 Deliver Moray Growth Deal Housing Mix Delivery
project.                    
7.21 Review and support Food Growing Strategy and Open
Space Strategy                    
7.22 Moray Growth Deal Carbon Guidance          
7.23 NPF4 Carbon guidance for applicants and offsetting
requirements           
Page 123

Page 124

Page 124

Page 125

APPENDIX 3 
Moray Council Climate Change Engagement 
Outline Strategy for Engagement 
Context or Introduction
Moray Council approved its Climate Change Strategy and Action Plan in March 2021, setting out the
council’s aim to have net zero greenhouse gas emissions by 2030. The national approach to tackling
the global climate crisis places a legal duty on local authorities to reduce their emissions, adapt to
climate change impacts and to act sustainably. It also recognises the crucial leadership role that local
authorities will have in supporting the national goal for Scotland to be net-zero by 2045. Under the
UN Framework Convention on Climate Change and the Paris Agreement, people in the UK have a
legal right to information and education on climate change and how it will affect them and to
participation in decision making processes.
The Scottish Government’s climate change engagement strategy, Net Zero Nation1, highlights that
although public concern for climate change has greatly increased in the last decade, behaviour
changes have not followed this upward curve.  The evidence suggests that targeting individuals,
specific behaviour related nudges, raising awareness and providing information are not effective at
changing behaviour on their own.  Furthermore, experiences of distress around the climate and
ecological crisis are now widespread, which can counterintuitively lead to a sense of powerlessness
and inaction. 
As a result, the new national strategy emphasises the need for a holistic, systemic approach that
positively communicates the fundamental shifts taking place, and which are required by society. For
behaviour change to be successful, engagement and messaging should: be combined with enabling
infrastructure; connect people with the wider action taking place in the transition to net zero,
therefore normalising net zero living; celebrate our collective (rather than personal) responsibility
and the many benefits arising from action on climate change. 
Moray Council must use this approach to embed action on climate change throughout the
organisation and workforce, and at the same time engage with our wider community and use local
voices to shape climate based service improvements in ways that work for the people of Moray. To
support the Moray-wide contribution towards the national net zero goal, the council should seek to
promote positive stories that connect people with what is happening both locally and beyond. 
This engagement plan will support the journey to net zero by outlining a framework for engagement
and associated actions. It will therefore act as a guide for the council to use best practice in
communicating and engaging with internal and external stakeholders on climate and biodiversity
related issues, and also keep a record of engagement actions within the wider Strategy and Route
Map. 
Aims and what we want to achieve
We aim to support action on climate change and biodiversity loss through effective engagement and
communication with council staff, elected members and the Moray community. 
1 Net Zero Nation https://www.gov.scot/publications/net-zero-nation-public-engagement-strategy-climate-
change/
Item 6c)
Page 125

Page 126

APPENDIX 3 
Our strategic objectives align with the Net Zero Nation approach which is based around the three
pillars; Understand, Participate and Act1. 
Principles for engagement
The evolving relationship between the public and climate change will be monitored. It will be
important to be responsive to policy changes and to make the most of moments when issues are
high on the agenda. Equally important is a sensitivity to the capacity of people to act, therefore it
will be essential to co-ordinate messages and engagement around interventions for which the
enabling infrastructure is in place.
The Net Zero Nation strategy identifies seven guiding principles to underpin effective climate change
engagement; 
• Positive – uplifting, motivating, relatable, co-benefits
• Putting people first – communities play a key role
• Participative – conversation and discussion
• Just – understanding and engaging with those most affected 
• Inclusive – equal and accessible engagement 
• Evidence based – using sound science, improving engagement through active reflection 
• Open and transparent – ensuring our actions are seen and understood
These principles will be followed alongside the national standards for community engagement2; 
2 https://www.voicescotland.org.uk/national-standards
•We will communicatethe wider transformational changes that are happening in
order to meet net zero, and how these relateto our work, communities and
personal lives
•This will look like a low carbon culture embedded across the council and
underpinning decisions and actions taken by staff
Understand
•We willinvolve council staff and the wider community in shaping the changes
required by the climate crisis
•This will look like communities and all council staff engagedin shaping the
council’s response to the climate emergency and biodiversity crisis and related
activities;
Participate
•We will normaliselow carbon living and inspirepositive changes to take place
•This will look like council staff and the wider community feeling supported and
empoweredto make the collective changes required to meet net zero targets
Act
Page 126

Page 127

APPENDIX 3 
Delivery
The Climate Change Strategy outlines the discrete responsibilities for its delivery, however all
individuals of every level within Moray Council are encouraged be engaged themselves and to
demonstrate leadership within their own sphere of influence towards the net zero goal.
Where specific actions from the Climate Change Strategy and Route Map are assigned to
departments, they will take the lead on engagement in these areas. Services who may engage on
climate change issues through their work areas include, but are not limited to, Energy, Housing and
Property, Strategic Planning and Development,  Economic Development, Transport, Environmental
Protection, Procurement, Education, ICT, Catering and PR.
Climate change officers will work with other departments to co-ordinate and monitor engagement
actions, supporting delivery of engagement that is consistent with this plan and aligned with the
Scottish Government’s approach and the latest evidence. 
Strategy Review
This engagement strategy will be reviewed and updated every three years. Lessons learned and
feedback received will inform future updates.
Engagement actions will be monitored for progress and updated as appropriate. Progress reports
will be included within the overall Climate Change Strategy reporting framework. 
Engaging within the Council
Stakeholders
All council staff and elected members will contribute to the council meeting its emission reduction
target, acting sustainably and adapting to the impacts of climate change. 
Page 127

Page 128

APPENDIX 3 
Key stakeholders and partners include those in decision making capacities (management as well as
elected members) and those working in sections with greater carbon implications or in public facing
roles (including teachers).  
In order to bring about the transformation required to meet the 2030 target and prepare for the
impacts of climate change, significant improvement is required to fully engage staff with the Climate
Change Strategy. A key priority will be to build and deliver narratives that resonate with a diverse
range of values that staff and members may hold. 
Methods of engagement
Rationale Potential methods
Build capacity and skills Networks, e-learning, in person training
(Carbon Literacy)
Feedback and information gathering Pop up coffee chats (free cake!), networks,
suggestion ‘box’ 
Disseminate info/ influence behaviour change Interchange, Connect, Team Brief, story maps,
themed campaign/ promotion
Monitor engagement, track attitude and
behaviour change
Surveys 
Engage wider staff group (including offline and
not otherwise engaged)
Focus groups
Pop up coffee chats (free cake!) 
Monitoring and Review 
Engagement of the council workforce is essential for the council to meet the challenges of climate
change and meet our ambitious net zero goal. Initial figures indicate a significant gap in engagement
on the issue of climate change, with a 2021 survey circulated to all staff stimulating a 2.5% return
rate which is lower than average Pulse survey response rates and is therefore not representative and
is likely also skewed by sampling bias (for example having stronger views or an interest in climate
change issues). However, the survey also highlighted that, of those who responded, only 49% were
either moderately or very aware of the Climate Change Strategy itself, indicating there is likely a very
low level of awareness across the full staff population of the council’s response to this crisis (and
perhaps their role in this). 
Measuring the level and quality of engagement will highlight areas where more work is needed and
will support evaluation of progress in delivering the overall strategy. Ongoing engagement will be
regularly monitored, and feedback actively sought, with the aim of improving the methods and
reach of future engagement activity. 
Specific events will be followed by evaluation and reflection on what worked well and how to learn
from what was less successful. Evaluation will seek to identify barriers to engagement and change,
and inform future approaches that address these issues. 
Examples of measurement criteria:
• Qualitative analysis of comments and feedback
• Analytics e.g.  survey response rates, story map engagement
• Evidence of engagement from staff across all council departments
• Evidence of how engagement has shaped changes in working practice
• Number of learners having completed training
Page 128

Page 129

APPENDIX 3 
Engaging with the wider community
Stakeholders
Climate change affects the whole Moray community and so all local residents are stakeholders and
will be encouraged to engage with the transition to net zero and to create resilient and sustainable
communities.  
Individuals, communities and organisations across Moray are already working hard to support and
inspire climate action and the council will work with them to wherever we can. The council will
demonstrate leadership through our actions, and support community groups and businesses seeking
to reduce their carbon footprint adapt to changes in climate and look after our natural environment
and biodiversity. We will collaborate closely with our partners in public and third sector
organisations who are working to deliver these objectives. 
In particular, reducing Moray’s area wide emissions will require a broad cultural shift and adoption
of new norms. It will be important to build and deliver narratives that resonate with a diverse range
of values and concerns. It will also be essential that we listen to the voices of those who are most
vulnerable to the impacts of climate change, including children.  
Methods of engagement
Rationale Potential Methods
Disseminate info/ influence behaviour change Social media (Moray Council accounts), press
releases, story maps, videos
Feedback and information gathering  Workshops, focus groups, consultation events,
surveys, online tools/ apps
Involve community in decision making Participatory budgeting
Monitor engagement, track attitude and
behaviour change
Surveys
Provide advice and information Climate change web pages on council site
Build capacity and skills Promote training and e-learning resources
Engage youth Arts and creativity, games and tech 
Monitoring and Review 
Acting on climate change is largely viewed as the responsibility of the public sector and so the
council must demonstrate strong leadership in this area to the Moray community. As resources
allow, measuring levels of engagement will highlight areas that require a more targeted approach
and will support evaluation of progress in delivering the Climate Change Strategy.
Ongoing engagement will be regularly monitored and feedback actively sought from partners and
participants to inform how to improve the methods and reach of engagement activity in future. 
Specific events will be followed by evaluation and reflection on what worked well and how to learn
from what was less successful. Evaluation will seek to identify barriers to engagement and change,
and inform future approaches that address these issues.
Examples of measurement criteria:
• Qualitative analysis of comments and feedback
• Analytics from social media and surveys
Page 129

Page 130

APPENDIX 3 
• Evidence of engagement with hard to reach groups
• Evidence of how engagement has influenced council services and that feedback has been
provided to participants
• Evidence of productive partnership working with stakeholders/community groups 
Page 130

Page 131

APPENDIX 3 
Engagement Actions
Most of the actions within the Climate Change Strategy and Route Map to Net Zero will involve
elements of engagement or communication.   
Engagement actions on climate change are central to the Climate Change Strategy and are included
throughout the action plan in the route map to net zero. The Climate Change Strategy aims to
consult, raise awareness, communicate and engage with residents, businesses and organisations
across Moray about climate change. Please refer to these documents for further information and the
full list of actions. Below is an overview of those actions identified as being most relevant to this
engagement strategy. 
Wider community 
Strategic local development |Climate change route map actions 7.15 to 7.24
Strategic Planning and Development will be leading on the Local Development Plan 2027 (LDP)
consultation, with early stakeholder and community engagement to inform the LDP evidence report
ongoing until late 2023.  A wide variety of engagement tools will be used, including apps and other
online tools, workshops and drop ins. The outcomes for this stage are: 
• Early meaningful and inclusive engagement meeting National Standards for Engagement
• Youth Engagement linked to the Curriculum for Excellence
• Geographic and demographic spread of engagement
• Spatial outputs from engagement to inform “Place” based plan
• Partnership working to engage beyond Local Development Plan both locally and strategically
on Moray Growth Deal, Regional Spatial Strategy and Locality Plans
• Deliver engagement through a climate change lens
Following completion of the Evidence Report, several stages of informing and consulting will take
place until adoption of the new LDP in 2027. This will involve website and social media updates, drop
in exhibitions, direct correspondence and making copies of the final plan available to the public. 
Other engagement alongside the LDP process will include a review of the Forest and Woodland
Strategy, consulting with key stakeholders and industry representatives. Public consultation will
involve all stakeholders including local landowners, community councils and active community
organisations to ensure the needs of the local community are met, especially in terms of leisure and
recreation. 
Opportunities to bring stakeholders together to progress biodiversity actions as part of the LDP and
development management will be explored. Engagement around biodiversity and our natural
environment will be a priority for development planning. 
The LDP aims to support the concept of “20 minute neighbourhoods”.  Public engagement will
support the design of places that enable residents to meet their day-to-day needs within a 20
minute walk of their home; through access to safe walking and cycling routes, or by public transport.
The Moray Growth Deal will present opportunities to showcase innovation and leadership in net
zero design, construction and operation of projects to the wider community and businesses in
Moray. 
Page 131

Page 132

APPENDIX 3 
Skills and knowledge in the community |Climate change route map actions 5.4, 7.8 and 7.9 to 7.14
Increasing the provision of skills and knowledge required to progress a greener economy will involve
cross-council collaboration between Strategic Planning and Development, Procurement and
Economic Development. This will involve awareness raising to promote opportunities for existing
businesses in the green economy transition.
Climate change officers will support partners to develop and deliver climate emergency training that
is specific to the area. Further support to communities will involve supporting the work of the Moray
Climate Assembly, the development of a Moray climate action hub and good communication
between the Council and local organisations regarding climate change policy and action. 
Connecting people to resources |Climate change route map actions 3.4, 6.2, 7.6 7.9, 7.12, 7.13 7.14
Communities will be supported to access information and advice for renewable energy projects.
Climate Change and Economic Development Officers will work with Moray climate action hub to
engage with community groups. Similar support for communities will be developed for tree planting/
offsetting.  
Raising awareness of the opportunities for just transition and the circular economy will highlight the
multiple benefits businesses can realise through taking action on climate change. This work will
involve officers from across the Council. 
Climate change officers will also work with other council departments and partner organisations to
promote campaigns that connect people, community groups and businesses to information, support
or enabling infrastructure as they emerge.
Sustainable Travel |Climate change route map actions 2.2, 2.3 and 7.3 
Transport will deliver the Council’s Active Travel Strategy 2022-2027, which includes several actions
that correspond with the Climate Change Strategy. Employers will be encouraged to develop active
travel plans to reduce the use of car travel to work. Similarly, schools will be supported to develop
active travels plans alongside a wider campaign to encourage active travel to school. 
Staff Engagement 
Learning |Climate change route map actions, 4.12 and 4.13
Climate change officers will co-ordinate and deliver certified carbon literacy training to staff to
increase knowledge and empower individuals to embed climate action throughout their work. This
training will be offered to all staff but will also be delivered to target groups such as elected
members, senior management and key service areas. A short e-module will provide a snapshot of
climate emergency training and will be included as part of staff inductions. 
Education will continue to lead the delivery of Learning for Sustainability within the curriculum,
supporting CPD for teachers and increased opportunities for pupils. Climate change officers will
support teachers and pupils to access relevant resources and information.
Knowledge exchange |Climate change route map actions 4.6 and 7.6
Climate change action plans will be kept up to date through regular engagement with staff.  
Page 132

Page 133

APPENDIX 3 
Behaviour change |Climate change route map actions 1.6, 2.2, 4.1
Energy officers will encourage a reduction of energy use in Council buildings through engagement
with staff, delivery of workshops in schools on an ongoing basis. Climate change officers will support
this and also lead on promoting resources to support homeworking staff to reduce emissions at
home. 
Transport will develop and promote Moray Council’s travel plan, encouraging staff to increase active
travel, public transport, and car share options. 
Page 133

Page 134

APPENDIX 3 
Links 
Net Zero Nation https://www.gov.scot/publications/net-zero-nation-public-engagement-strategy-
climate-change/ 
Moray Council climate change web page, including the Strategy and Route Map
http://www.moray.gov.uk/moray_standard/page_136444.html 
Moray Council Interchange staff climate pages
http://interchange.moray.gov.uk/int_standard/Page_143298.html  
Page 134