Audit and Scrutiny Committee
Tuesday, 24 June 2025
NOTICE IS HEREBY GIVEN that a Meeting of the Audit and Scrutiny Committee
is to be held at Council Chambers, Council Office, High Street, Elgin, IV30 1BX
on Tuesday, 24 June 2025 at 14:00.
BUSINESS
1. Sederunt
2. Declaration of Group Decisions and Members Interests *
3. Resolution
Consider, and if so decide, adopt the following resolution:
"That under Section 50A (4) and (5) of the Local Government
(Scotland) Act 1973, as amended, the public and media
representatives be excluded from the meeting for Item 13 of business
on the grounds that it involves the likely disclosure of exempt
information of the class described in the relevant Paragraphs of Part 1
of Schedule 7A of the Act.”
4. Minute of meeting of 7 May 2025 7 - 12
5. Written Questions **
6. Internal Audit Annual Report 2024-25
Report by Audit and Risk Manager
13 - 28
7. Internal Audit Section Update Report
Report by Audit and Risk Manager
29 - 64
8. Internal Audit Review - Building Services - Reactive
Repairs
Report by Audit and Risk Manager
65 - 84
Page 1

Page 2

9. Internal Audit Review - Keith Grammar School
Report by Audit and Risk Manager
85 -
100
10. Internal Audit Review - Information Communications
Technology Hardware Assets
Report by Audit and Risk Manager
101 -
120
11. Audit and Scrutiny Committee - Self-Assessment and
Evaluation Exercises
Report by Audit and Risk Manager
121 -
142
12. Annual Governance Statement
Report by Chief Executive
143 -
162
Item(s) which the Committee may wish to consider with
the Press and Public excluded
13. Internal Audit Follow Up Review - Cyber Security and E-
Mail Security [Para 14]
• 14. Information relating to action taken, or to be taken, in
connection with the prevention, investigation or prosecution of
crime.
Summary of Audit and Scrutiny Committee functions:
Audit Functions - Consider reports from the Council's internal auditor
& Audit Scotland concerning Council Functions.
Scrutiny Functions - Scrutinising the policies of the Council and their
effectiveness in meeting the action plans of the Council as set out in
the Corporate Development Plan and evaluating the actions of
Committees in implementing the action plans set out in the Corporate
Development Plan.
Performance Monitoring - To receive reports on the performance of
and trends within all of the Council’s services in terms of service
standards and performance information.
Standards - To ensure that the highest standards of probity and public
accountability are demonstrated.
Page 2

Page 3

Watching the Meeting
You can watch the webcast live by going to: 
http://www.moray.gov.uk/moray_standard/page_43661.html
Webcasts are available to view for 1 year following the meeting.
You can also attend the meeting in person.  If you wish to attend
in person, please come to the High Street entrance door and a
member of staff will let you into the Chamber.
Page 3

Page 4

GUIDANCE NOTES
* Declaration of Group Decisions and Members Interests - The Chair of the
meeting shall seek declarations from any individual or political group at the
beginning of a meeting whether any prior decision has been reached on how
the individual or members of the group will vote on any item(s) of business on
the Agenda, and if so on which item(s).  A prior decision shall be one that the
individual or the group deems to be mandatory on the individual or the group
members such that the individual or the group members will be subject to
sanctions should they not vote in accordance with the prior decision.  Any such
prior decisions will be recorded in the Minute of the meeting.
** Written Questions - Any Member can put one written question about any
relevant and competent business within the specified remits not already on the
agenda, to the Chair provided it is received by the Proper Officer or Committee
Services by 12 noon two working days prior to the day of the meeting.  A copy
of any written answer provided by the Chair will be published on the Council’s
committee management system by 4pm the day before the meeting.  The
Member who has put the question may, after the answer has been published,
ask one supplementary question directly related to the subject matter at the
meeting, but no discussion will be allowed.
No supplementary question can be put or answered more than 10 minutes after
the Council has started on the relevant item of business, except with the
consent of the Chair. If a Member does not have the opportunity to put a
supplementary question because no time remains, then he or she can submit it
in writing to the Proper Officer who will arrange for a written answer to be
provided within 7 working days.
Page 4

Page 5

MORAY COUNCIL
Audit and Scrutiny Committee
SEDERUNT
Councillor Scott Lawrence  (Chair)
Councillor Theresa Coull  (Depute Chair)
Councillor Peter Bloomfield  (Member)
Councillor Tracy Colyer  (Member)
Councillor John Divers  (Member)
Councillor Jérémie Fernandes  (Member)
Councillor Donald Gatt  (Member)
Councillor David Gordon  (Member)
Councillor Sandy Keith  (Member)
Councillor Marc Macrae  (Member)
Councillor Paul McBain  (Member)
Councillor Neil McLennan  (Member)
Councillor John Stuart  (Member)
Councillor Sonya Warren  (Member)
Mr Ivan Augustus  (Non-Voting Member)
Ms Margaret Wilson  (Non-Voting Member)
Clerk Name: Caroline O'Connor
Clerk Telephone: 07779 999296
Clerk Email: committee.services@moray.gov.uk
Page 5

Page 6

Page 6

Page 7

MORAY COUNCIL
Minute of Meeting of the Audit and Scrutiny Committee
Wednesday, 07 May 2025
Council Chambers, Council Office, High Street, Elgin, IV30 1BX
PRESENT
Mr Ivan Augustus, Councillor Peter Bloomfield, Councillor Tracy Colyer, Councillor
Theresa Coull, Councillor John Divers, Councillor Jérémie Fernandes, Councillor
Donald Gatt, Councillor David Gordon, Councillor Sandy Keith, Councillor Scott
Lawrence, Councillor Marc Macrae, Councillor Neil McLennan, Councillor John
Stuart, Councillor Sonya Warren, Ms Margaret Wilson
APOLOGIES
Councillor Paul McBain
IN ATTENDANCE
Chief Executive; Depute Chief Executive (Education, Communities and
Organisational Development); Depute Chief Executive (Economy, Environment
and Finance); Interim Chief Social Work Officer / Head of Service; Audit and Risk
Manager; Head of Governance, Strategy and Performance; Head of Financial
Services; Head of Housing and Property Services; DLO Services Manager;
Service Manager - Provider Services, Strategy and Performance Manager and
Caroline O'Connor, Committee Services Officer, all Moray Council and Joanne
Brown, Grant Thornton - External Auditors.
1.         Chair
The meeting was chaired by Councillor Scott Lawrence.
2.         Declaration of Group Decisions and Members Interests *
In terms of Standing Orders 21 and 23 and the Councillors' Code of Conduct, there
were no declarations from Group Leaders or Spokespersons in regard to any prior
decisions taken on how Members will vote on any item on the agenda or any
declarations of Member's interests in respect of any item on the agenda.
With regard to Item 8 "Annual Audit Plan for the Year Ending 31 March 2025",
Councillor Gatt stated, for transparency, that he is Convener of the Grampian
Valuation Joint Board and would be taking part in the debate.
Mr Augustus stated, for transparency, that he was carer representative on the
Moray Integration Joint Board and also in relation to Item 5 "Internal Audit Section
Update Report" he managed Self-Directed Support Option 1 from its inception and
would be taking part in the debate.
With regard to Item 8 "Annual Audit Plan for the Year Ending 31 March 2025",
Councillor Warren and Councillor Macrae stated, for transparency, that they were
Item 4.
Page 7

Page 8

members of the Grampian Valuation Joint Board and would be taking part in the
debate.
With regard to Item 9 "Local Government Benchmarking Framework 2023-24
Results", Councillor Stuart stated, for transparency, that he is Care Inspector but
does not inspect in Moray and would be taking part in the debate.
3.         Minute of meeting of 12 February 2025
The minute of the meeting of 12 February 2025 was submitted and approved.
4.         Written Questions **
The Committee noted that no written questions had been submitted.
5.         Internal Audit Section Update Report
The meeting had before it a report by the Audit and Risk Manager providing an
update on the work of the Internal Audit Section.
Councillor Keith, in relation to the third follow-up review referenced in Audit
Recommendation 5.02 of Appendix 3 and noting the monies involved, questioned
how assured members of the Committee could be given there was to be a further
postponement for the implementation of the Audit Recommendation.  In response
the Audit and Risk Manager stated his concern however highlighted significant
progress had been made and it was expected the financial reviews would be
completed in full this year.   He stated that the need for another follow-up review
impacts the completion of projects within the annual audit plan. The delay in
implementing these recommendations will also need to be considered within the
context of the internal audit annual report, as previous years have detailed a
limited opinion on the Moray Integration Joint Board's systems of governance and
internal controls.  The Audit and Risk Manager confirmed that he plans to include
another full review of this area within next year's audit plan, with any findings and
recommendations reported to this Committee.
Councillor Gatt stated he shared the concern noted by Councillor Keith in relation
to Audit Recommendation 5.02 of Appendix 3.  He further noted Audit
Recommendation 5.06 of Appendix 3 had been outstanding since 2022 and asked
whether the large surplus referred to was a genuine surplus or due to people not
receiving the care they required due to carer recruitment issues.   In response the
Service Manager - Provider Services advised individuals are assessed in terms of
need and a financial equivalent is provided to the person for their care however
there can then either be an improvement in the amount of care or reduction in the
amount of care required which results in a surplus.   
Councillor Gatt expressed his thanks for the response however stated it was even
more important for the financial reviews detailed in Audit Recommendation 5.02 to
proceed and asked whether the delay in implementation was having a detrimental
effect on the care service if monies were in the wrong place rather than being used
where needed.  In response the Service Manager - Provider Services explained
unmanaged accounts are more difficult to audit and require more resources.  He
stated the number of direct payments had doubled since the audit however agreed
the importance of regular annual assessments.   He further advised that the
previous significant recruitment issues had improved and the service has set up
different ways of monitoring the implementation of audit recommendations  to
Page 8

Page 9

ensure lessons are learned from the work done by Internal Audit through Health
and Social Care Moray's Practice Governance Board and Self-Directed Support
Steering Group.  It was also noted there was a permanent employee now in post
allowing a significant increase in the amount of financial audits and reviews the
service had the capacity to undertake.     
Councillor Gatt, in relation to the decision of Communities Committee on 27
October 2013 for a review of revised working time arrangements to be undertaken
detailed in Audit Recommendation 5.01 of Appendix 4, asked whether his
understanding was correct that the decision had not been enacted.  In response
the Audit and Risk Manager advised it was included as an Audit Recommendation
due to a need for it to be reported back to Committee with the current
arrangements and while there was an agreement, the decision of Committee in
2013 had not been followed through. The DLO Manager provided assurance that
the revised hours pilot scheme was approved in 2013 following consultation with
the Trade Unions and staff and had been operational since that time however had
not been reported back to Committee for approval as a permanent change.  He
apologised and advised it was planned to issue a further survey, engage with the
Trade Unions then report back to Committee for approval.
In response to a follow-up question from Councillor Gatt relating to governance
and how to ensure this would not happen again, the Head of Governance, Strategy
and Performance advised that was demonstrated through reporting to this
Committee allowing scrutiny by Members.   The Audit and Risk Manager provided
assurance that a review of governance arrangements is included in this year’s
audit plan. This will include an assessment of controls, with any findings and
recommendations also reported to this Committee.
Councillor Warren, in relation to Audit Recommendation 5.08 of Appendix 4 and
noting there was no mention of stock control measures being put in place for the
contract, asked for assurance of what would be put in place and fed back to
Committee.   In response, the Audit and Risk Manager advised that the value of
the stock was limited and there were controls in place. However, he provided
assurance that the stock control arrangements will be checked again during the
follow-up review. 
Following lengthy consideration the Committee unanimously agreed to note the
report.
6.         Internal Audit Review - Special Investigation - Building Services -
Windows Replacement Programme
The meeting had before it a report by the Audit and Risk Manager advising
Committee on an internal audit review completed for the period from 12 February
2025 to 7 May 2025.
In order to have a fuller understanding of the scale of the financial and reputational
costs including impacts on tenants who had experienced delays and whether they
had received an apology from the Council, Councillor Warren asked for more
detail.  In response the Head of Housing and Property Services advised a new
contract had been issued to also include other updates to the properties such as
insulation which was expected to be delivered within 10-12 weeks.  With reference
to details of the financial costs,  the Head of Housing and Property Services
advised that the value of the windows included in the report was £40,000 and the
service would look to repurpose or dispose of the windows attaining best value and
Page 9

Page 10

in accordance with the Financial Regulations of the Council.  As a conclusion to
the process, he undertook to provide apologies to affected tenants.   
Councillor Warren asked what procedural changes had been put in place to ensure
more rigorous contract checks, how building services will ensure compliance with
the requirements of the contract  and if the procurement process had been
amended to ensure more oversight of split contracts.  in response the Audit and
Risk Manager advised as part of the audit, Internal Audit would be evidencing
implementation of the recommendations which would be reported back to
Committee.  The Head of Housing and Property Services noted one of the factor
was the separation of the supply and installation elements of the contracts.  He
provided assurance that future contracts would be for supply and fit to provide
further control.
In response to a request from Councillor Lawrence that the final costs to the
Council after disposal and repurposing be included in the Internal Audit follow-up
report, the Audit and Risk Manager agreed he would detail the decision made
whether to reuse or dispose within the follow-up report. 
During the course of discussion concern was expressed by members of the
Committee regarding the period of time that had elapsed since the service became
aware of the issue in 2022 to it being escalated following concerns raised by an
Elected Member 2024.  In terms of governance, the Head of Housing and Property
Services referred to a number of contributing factors including the post Covid
recovery process ongoing and significant staffing changes however was fully
accepting that the issue should have been escalated to a higher level at an earlier
stage.  He explained he was confident there would not be a reoccurrence within
the service as all were now very clear about how matters should be escalated and
resolved. 
Councillor Fernandes in noting that this was not the first occasion when a matter
had not been escalated through the correct channels, asked if there was a cultural
issue within the service preventing staff from raising issues.  In response the Head
of Housing and Property Services confirmed he wished to encourage staff within
the service to raise issues so as to engender a culture where transparency was
key.  The Chief Executive provided assurance that the management controls and
processes would change as detailed in the Audit Recommendations however she
would also be overseeing a change in culture to ensure empowerment of teams
along with a clear understanding of when to escalate issues and when to find
solutions together.   
Following lengthy consideration the Committee unanimously agreed to endorse the
recommendations contained within the report.
7.         The National Fraud Initiative in Scotland
The meeting had before it a report by the Audit and Risk Manager providing
Committee with information on the Council's approach to participation in the
National Fraud Initiative (NFI).
In response to a question from Councillor Bloomfield asking whether the Council
has a whistleblowing policy, the Audit and Risk Manager confirmed there was a
whistleblowing policy which he understood was being reviewed however agreed to
ask the officer concerned for detail and provide an update to Committee.
Page 10

Page 11

Following consideration the Committee unanimously agreed to endorse the Audit
Scotland self-appraisal checklists that participating bodies are invited to complete
and present to their local audit committees.
8.         Annual Audit Plan for the Year Ending 31 March 2025
The meeting had before it a report by the Depute Chief Executive (Economy,
Environment and Finance) informing the Committee of the External Auditor's
Annual Audit Plan for 2024/25.
Councillor Gordon, in relation to the wider scope and best value arrangements (4)
section of Appendix 1 and specifically the sentence in bold print about there being
potentially a risk that budget control and financial management information for
members is not consistent for effective decision making, asked the  Auditor to
expand on the point.  In response the Auditor advised through best value work
previously a potential risk has been identified regarding to the setting of the budget
and detailed financial reports which could create a risk for members in terms of
their understanding.   The Auditor noted that the issue has been captured as a
recommendation in the Council's improvement plan, and it is being progressed, but
needs to be identified as a risk at this stage.   
Councillor Keith asked, with reference to the first sentence of the Financial
management paragraph in the Introduction and headlines (4) section of Appendix
1; whether the sentence was relevant for every Council in Scotland and therefore
included in all audit plans or if it was specific to Moray and queried whether it may
be removed in future reports.  In response the Auditor explained the landscape
round local government and future financial sustainability was a key aspect seen
consistently across external auditor reports. The financial management paragraph
was an element identified in the first year of the auditors appointment and
improvements have been made and evidenced.  She advised it was likely this will
be removed at some point in the future with the focus then being on longer term
financial sustainability. 
Councillor Lawrence noted fraud being one of the identified risks in the report
however the National Fraud Initiative discussed earlier had not identified any major
risks and asked how the work in the Audit Plan differentiated from the work done
by Internal Audit relating to fraud.  In response the Auditor advised external audit's
focus on fraud specifically related to the potential risk regarding financial
statements of a material element of fraud, misreporting or otherwise which would
impact on external audit's ability to give an unmodified opinion on those financial
statements. 
Following consideration the Committee unanimously agreed to note the contents of
the External Auditor's Annual Plan for 2025/25.
9.         Local Government Benchmarking Framework 2023-24 Results
The meeting had before it a report by the Depute Chief Executive (Education,
Communities and Organisational Development) presenting a corporate overview of
benchmarking performance data for the period 2023-24.
Councillor Gordon asked, in relation to budget forecasting referenced in number 23
of Appendix 1, whether budgets should be rebaselined on a more regular basis to
ensure more effective decision making when the Council sets its budget.  In
response the Chief Financial Officer advised there was a particular issue with the
Page 11

Page 12

indicator relating to the timing of a budget decision taken on the day the Council's
budget was set for the next year.  The Council approved exercising its option to
have financial flexibility which which not a normal part of the Council's budget
setting process but as result of the pandemic and the current funding crisis in local
government.  The budget for 2023/24 was amended in February 2024 however it
was too late to reflect it in the budget figures used for this indicator.  She advised
going forward normal regular updates would not be impacted by unusual decisions
such as this.
Councillor Keith asked for an explanation of the Indicator Description "0%
participation for 16-19 year olds", referenced in Note 10 of Appendix 3.  In
response the Strategy and Performance Manager agreed to double check the
metadata relating to the indicator and provide an update to Committee.
Following consideration the Committee unanimously agreed to note the Council's
performance in terms of a corporate overview of benchmarking results.
Page 12

Page 13

Report to: Audit and Scrutiny
Committee 
Meeting Date: 24 June 2025     
Report by: Audit and Risk Manager Report No: GSP029/25/DL  
Author: Dafydd Lewis Contact
Email:
dafydd.lewis@moray.gov.uk 
Subject: Internal Audit Annual Report – 2024/25   
1. PURPOSE 
☒ For Decision      ☐  For Information 
1.1 This report is submitted to Committee in terms of Section III (2) and (10) of the
Council’s Scheme of Administration relating to the consideration of reports from the
Council’s Internal Auditor and the provision of the annual assurance statement provided
by Internal Audit on the Council’s control environment. 
2. SUMMARY  
2.1 To provide Committee with a copy of the Internal Audit Annual Report for the year
ended 31 March 2025, together with the Audit and Risk Manager’s opinion on the
adequacy and effectiveness of the Council’s system of internal control. 
3. RECOMMENDATIONS  
3.1 It is recommended that Committee:   
i) That Committee considers the contents of the annual report given as
Appendix 1 to this report and seeks clarification on any matters relating
thereto.   
Dafydd Lewis
Audit and Risk Manager 
4. BACKGROUND AND CONTEXT  
4.1 The purpose of this report is to present to the Audit and Scrutiny Committee the Internal
Audit Annual Report for the year to 31 March 2025, which includes the Audit and Risk
Manager's independent assurance opinion on the adequacy of the Council's overall
control environment.  
4.2 The Public Sector Internal Audit Standards (PSIAS) requires the Chief Audit Executive
(CAE), the Council’s Audit and Risk Manager, to provide an annual internal audit
opinion and report on the adequacy and effectiveness of the Council’s governance, risk
Item 6.
Page 13

Page 14

management and internal controls to support the preparation of the Annual Governance
Statement.  
4.3  To meet the requirements of the PSIAS, the Internal Audit Annual Report 2024/25
(Appendix 1) includes the annual opinion of the Audit and Risk Manager and provides
details of internal audit activity and performance during the year. 
5. PROPOSALS  
5.1 The Internal Audit annual report provides a summary overview of the nature and extent
of audit work carried out during the year to inform the audit opinion on the internal
control environment operating within the Council. 
6. SUMMARY OF IMPLICATIONS  
6.1 The table below shows whether risks and implications apply if the recommendations
are agreed: 
SUBJECT YES NO
Corporate Plan and 10 Year Plan (Local Outcome Improvement
Plan) 
×
Policy and Legal  ×
Financial  ×
Risk × 
Staffing  ×
Best Value and Transformation × 
Property  ×
Information Communications Technology/Digital             ×
Equalities. Social Inclusion and Economic Impact   ×
Climate Change, Biodiversity and Sustainability  × 
6.2 Corporate Plan and 10 Year Plan (Local Outcomes Improvement Plan (LOIP))
Improved Collaborative Leadership, as part of continuous improvement through Best
Value, will better enable the Council to fulfil the ambitions set out in its strategic plans. 
a) Links to Council Corporate Plan – The proposals in this report support and
contribute to improved outcomes for communities as outlined in the following
Council Plan strategic priorities:
☐ Tackle Poverty and Inequality.
☐ Build Stronger Greener Vibrant Economy.
☐ Build Thriving, resilient, empowered Communities.   
b) Links to Local Outcomes Improvement Plan – The proposals in this report support
and contribute to improved outcomes for communities as outlined in the following
local Outcomes Improvement Plan priorities:
☐ Developing a diverse, inclusive, and sustainable economy
☐ Building a better future for our children and young people in   Moray.
☐ Empowering and connecting communities.
☐ Improving wellbeing of our population   
6.3 Policy and Legal  
No implications directly arising from this report.  
Page 14

Page 15

6.4 Financial  
No implications directly arising from this report. 
One off Costs:
Service
Area
Budget Budget
Years
Proposed
Spend
this Year
Virement
From
Other
Comments       
Annually Recurring Costs:
Service
Area
Budget With
Effect
From
Annual
Net
Impact
Virement
From (if
applicable)
Other
Comments       
6.5 Risk 
The independent review of selected systems and procedures mitigates the risks
associated with inadequate or ineffective control procedures.  
6.6 Staffing 
No implications directly arising from this report.  
6.7 Best Value and Transformation 
Internal audit work supports good governance and the delivery of efficient services.  
6.8 Property 
No implications directly arising from this report.  
6.9 Information Communications/Technology/Digital 
No implications directly arising from this report.  
6.10 Equalities, Social Inclusion and Economic Impact 
No implications directly arising from this report.  
6.11 Climate Change and Biodiversity Impacts 
No implications directly arising from this report. 
7. CONSULTATION  
7.1 There have been no direct consultations during the preparation of this  report. 
8. BACKGROUND PAPERS  
8.1 None   
Page 15

Page 16

APPENDIX 1
1
MORAY COUNCIL
INTERNAL AUDIT ANNUAL REPORT
1 APRIL 2024 to 31 MARCH 2025
Page 16

Page 17

2
CONTENTS  
Page
SECTION 1 –  INTRODUCTION  3
SECTION 2 –  BASIS OF OPINION  3-4
SECTION 3 –  SUMMARY AND LIMITATIONS OF WORK THAT SUPPORTS OPINION  4-13
SECTION 4 –  OPINION     13
Contact Details 
Audit and Risk Manager: Dafydd Lewis
E-mail: dafydd.lewis@moray.gov.uk
www.moray.gov.uk
Page 17

Page 18

3
SECTION 1 – INTRODUCTION
1.1 This report is issued in compliance with the Public Sector Internal Audit Standards (PSIAS), which requires the Audit and Risk
Manager to deliver ‘an annual internal audit opinion and report that can be used by the organisation to inform its governance
statement’, and which ‘must conclude on the overall adequacy and effectiveness of the organisation’s framework of governance,
risk management and control.’ This report constitutes the required statement.
1.2 It is management’s responsibility to maintain risk management systems, internal control and governance. Internal audit is an element
of the internal control framework established by management to examine, evaluate and report on accounting and other controls over
operations. Internal audit assists management in effectively discharging its responsibilities and functions by examining and
evaluating controls. Internal audit cannot be held responsible for internal control failures.
1.3 Internal audit’s role includes assessing the adequacy of the risk management, internal controls and governance arrangements put
in place by management and performing testing on a sample of transactions to ensure those controls were operating for the period
under review.
1.4 Public Sector Internal Audit Standards (PSIAS) require officers of the Internal Audit Section to communicate on a timely basis all
facts and matters that may have a bearing on their independence. I can confirm that all staff members involved in the 2024/25
internal audit reviews were independent of operational processes and their objectivity was not compromised in any way.
SECTION 2- BASIS OF OPINION
2.1 This opinion is based on my knowledge of the Council’s governance, risk and control processes and from the audit work completed
during the period 1 April 2024 to 31 March 2025.  There are limitations to the level of assurance that can be provided, dependent on
the scope and coverage of the audit work completed. My evaluation is based on the following:
Page 18

Page 19

4
.
SECTION 3- SUMMARY AND LIMITATIONS OF WORK THAT SUPPORTS THE OPINION
3.1 Internal audit operates independently within the Council. It helps the Council accomplish its objectives by bringing a systematic,
disciplined approach to evaluate and improve the effectiveness of risk management, control and governance processes. There have
been no limitations imposed by management on the scope of audit work performed. The internal audit opinion has been informed
by the audit work completed during the year.
3.2 The annual audit plan presented to the Audit and Scrutiny Committee describes in some detail the framework around which audit
work is to be developed. In addition, the selection of audit topics was chosen with regard to corporate planning documents, budget
data, information drawn from the corporate risk register and consultation with senior management regarding possible areas for
review. The percentage of internal audit plans completed for 2024/2025, together with a comparison to the previous year, is
summarised below, with a more detailed analysis also provided of the status of each audit project. 
Overall
Opinion
Assurance
statements signed
by Heads of
Services
Risks identified in
the Council's Risk
Register
Reports issued by
the External
Auditor and other 
external review
agencies
Audit work
undertaken by
Internal Audit
during the year to
31st March 2025
Follow Up Reviews
to evidence
implementation of
audit
recommendations
Governance, risk
management and
performance
monitoring
arrangements
Review of
corporate
governance
arrangements
Page 19

Page 20

5
Percentage of Internal Audit Plan Completed (%) - 2023/ 24 and 2024/ 25
Status of each project included within the Internal Audit Plan 2024/ 25
89% 87%
11% 13%
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
2023/ 24 2024/ 25
Completed Carried Forward
Audit Projects      Status
Payroll  Audit Review to be carried forward to Audit Plan 2025/26
Procurement and Creditor
Payments 
Completed
ICT Hardware Assets  Completed
Housing and Property-
Reactive Maintenance Works
Completed
Housing Rent Collection &
Arrears Management
Completed
Education – Secondary
School 
Completed
Page 20

Page 21

6
3.3 The internal audit work has been conducted in accordance with an established methodology that promotes quality and conformance
with the Public Sector Internal Audit Standards and the approved Internal Audit Annual Audit Plan.
Progress on the 2024/2025 Internal Audit Plan
3.4 Progress against planned audit work for the year to 31 March 2025 can be summarised as follows:-
• Each year, an element of the plan covers work on core financial systems, which are of key significance to the good governance
of the Council. These systems receive the most significant focus in terms of management control and are also reviewed on a
cyclical basis by the External Auditor to obtain assurances needed for the audit of the annual accounts. Internal audit testing
has noted examples of non-compliance with the Council’s Financial Regulations, but generally, effective controls are operating
in the management of financial systems.
• Summaries of the issues arising in relation to each system or activity covered by internal audit work in 2024/2025 have been
reported separately to the Audit and Scrutiny Committee. Appropriate responses to the recommendations are also included.
When actioned, the recommendations made in the internal audit reports should provide management with additional comfort
Moray Growth Deal Completed
Treasury Management Completed
Commercial Refuse Collection Completed
Governance arrangements to
prevent Fraud and Corruption
Completed
Education- Secondary School
Premises Security
Completed
Absence Management Audit Review to be carried forward to Audit Plan 2025/26
Following the Public Pound Completed
Residential Care  Completed
Out of area placement Completed
Fostering and Kinship
payments
Completed
Grampian Valuation Joint
Board
Completed
Page 21

Page 22

7
that the system of control operates as intended. It is therefore imperative that the agreed actions are implemented by
management. 
• I am pleased to report that the majority of the 2024/25 Audit Plan has been completed. However, the reviews of absence
management and the testing of payroll payments will need to be carried forward to next year’s Audit Plan. The Internal Audit
Section also undertook additional reviews relating to recovery arrangements for Non-Domestic Rates at the St Giles Shopping
Centre and a contract for the replacement of windows in a housing scheme. Internal audit resources have also been required
to support the Council’s counter-fraud and corruption arrangements due to a decision by senior management to reduce staff
resources. These issues have impacted the completion of this year’s Audit Plan.
• The Internal Audit Section reports follow-up reviews to evidence the implementation of recommendations to the Audit and
Scrutiny Committee. It is appreciated the demands on services, however the follow-up audits undertaken found
recommendations that had yet to be implemented within the agreed timescales. The need to revisit audit reviews to evidence
the implementation of recommendations has again resulted in an additional workload commitment for the Internal Audit Section.
Implementation of recommendations is a key determinant in assessing the adequacy and effectiveness of the Council’s internal
control system. If recommendations are not implemented in a timely manner, then weaknesses in control and governance
frameworks will remain in place.
• On agreement of the Annual Audit Plan by the Audit and Scrutiny Committee, all Heads of Services are informed of the projects
for review for the next financial year. Heads of Services are asked to remind staff that during an audit review, they should
respond to information requests and reply to audit recommendations within an appropriate timeframe, i.e., within 20 days for
audit recommendations and 5 days for information requests. As the Audit and Risk Manager, I have an ongoing requirement to
update the Committee regularly on the work undertaken and the performance of the Internal Audit Service in accordance with
the Public Sector Internal Audit Standards. I have noted delays in responding to audit enquiries and recommendations that have
impacted the timely completion of reviews. I am closely monitoring this issue and have recently requested an additional
paragraph to be included within the Council’s Financial Regulations  formalising this requirement for officers to respond promptly
to audit enquiries and recommendations.
• The audit role for the Moray Integration Joint Board (MIJB) involves providing assurances that governance and financial
arrangements have been developed and are operating in accordance with policies and that selected systems and processes
are suitably controlled. The audits undertaken have noted significant findings, especially in the administration and management
of adult social care. The follow-up reviews completed to evidence implementation of the recommendations have again been a
particularly time-consuming commitment on the Internal Audit Section. It is anticipated this requirement will continue in 2025/26.
Page 22

Page 23

8
• It is acknowledged that the MIJB is a separate statutory body; however, the Council makes a significant ongoing funding
contribution to the delivery of its services. The MIJB Audit Plan for 2024/25 included an audit review of Residential Care and
Out-of-Area placements, both of which identified a number of findings. Additionally, follow-up reviews of audit reports from
previous years found that further progress was still required in implementing recommendations. It is encouraging to note that
the Service is seeking a replacement for the current social work and social care case management system, but there is a need
for this to be progressed to ensure full implementation of a new system at the earliest opportunity, as it involves the management
and recording of highly sensitive information. As the Audit and Risk Manager of the Council, I am increasingly concerned about
the governance and operational arrangements within the MIJB and the potential risks to which the Council may be exposed. I
also note the Chief Financial Officer’s report to the Special Meeting of the Council on 26 February 2025, "2025/26 Budget and
2025 to 2028 Financial Plan," which outlines expectations for financial savings within the MIJB. While the challenges faced by
the MIJB in meeting the needs of social care users within the current financial climate are recognised, these issues continue to
need careful management and oversight.
3.5 The total number of recommendations made is set out in the following table:
Report Risk Ratings for
Recommendations
System/ Testing
Assessment
2024/25 Audit Plan High Medium Low
Payroll  Audit Review Carried forward to 2025/26 Audit Plan
Procurement and Creditor Payments 0 2 0 Substantial
ICT Hardware Assets 1 3 1 Substantial
Building Services- Reactive Works 1 5 0 Substantial
Housing Rent Collection & Arrears Management 0 2 1 Substantial
Moray Growth Deal 2 3 2 Substantial
Education – Secondary School 0 4 2 Substantial
Treasury Management 0 2 3 Substantial
Commercial Refuse Collection 0 6 4 Substantial
Governance arrangements to prevent Fraud and
Corruption
0 3 2 Substantial
Page 23

Page 24

9
Education- Secondary School Premises Security 1 6 0 Substantial
Absence Management Audit Review Carried forward to 2025/26 Audit Plan
Following the Public Pound 3 2 0 Substantial
Residential Care 0 4 3 Substantial
Out of area Placements 3 3 0 Limited
Fostering and Kinship payments 0 1 2 Substantial
Special Investigation: Non Domestic Rates- St Giles
Shopping Centre
2 1 0 Substantial
Special Investigation: Building Services- Windows
Replacement Contract
1 2 0 Limited
Grampian Valuation Joint Board 0 0 0 Full
3.6 The following performance measures were in place for 2024/2025:
Measure Description Target Actual
2023/24
Actual
2024/25
Final Report Percentage of Auditee(s) responding within
20 days of receiving the draft report.
100% 65% 100%
Final Report Percentage of final audit reports issued
within 10 days of agreeing the draft report
100% 100% 100%
Audit Plan Delivery Percentage of audits completed v planned. 85% 89% 87%
Audit Budget Percentage of audits completed within
budgeted days.
80% 76% 77%
Audit Recommendations Percentage of audit recommendations
agreed.
90% 100% 100%
Customer Feedback Percentage of respondents who rated that
the audit added value and provided
meaningful results.
100% 100% 95%
Follow Up Reviews Percentage of Follow Up Reviews
completed v planned
100% 92% 94%
Page 24

Page 25

10
The analysis of the Internal Audit Section's performance for 2024/25 details that the majority of planned projects within the audit
plan for the previous year were completed. A comparison with the previous year’s percentage of audits completed against the
audit plan indicates a similar level of performance, notwithstanding staffing challenges remain. The duties of the vacant Corporate
Investigations Officer have been undertaken by other officers within the Section, along with the additional requirement to conduct
significant reviews requested by senior management. Furthermore, as the Audit and Risk Manager, I prepare the Annual Audit
Plan as a challenging programme, considering staff resources and the additional duties and responsibilities of the Internal Audit
Section. All reports were issued as “final” within 10 days of agreeing on the draft report, with officers accepting all
recommendations. It is pleasing to report that services are responding more promptly to audit recommendations within 20 days
of receiving the draft reports, however delays were observed in obtaining the requested information or explanations to audit
queries. Heads of Services have been reminded of the importance of responding promptly to audit questions or requested
information. Analysis also found that more days were required to complete certain projects from the Audit Plan. This included the
Out of Area review, which required more extensive testing than initially envisaged, but significant findings were noted from the
audit. Additional days were also required within the audit of Reactive Repairs within Building Services as senior management
requested a review of a contract for replacement windows. Feedback has also been positive from officers on the value of
participating in the audit review process, however one auditee questioned the need for additional testing they believed to be out
with the scope of the audit review. 
3.7 Governance – regarding the preparation of the Council’s Annual Governance Statement, it is considered that sufficient
information has been obtained to conclude that the Council generally complies with the latest good governance practice issued
by CIPFA /SOLACE and that the Corporate Management Team and senior managers have a strong awareness of the challenges
facing the Council in the incoming period. Written assurances from senior managers also considered governance practice within
individual service areas.
3.8 Key governance and internal control arrangements have been maintained, albeit capacity issues called for resources to be
prioritised for essential services and to take forward the Council's strategic priorities. It was noted that the Accounts Commission's
Best Value Report on Moray Council, issued in March 2024, detailed a number of governance and service improvement
recommendations. Progress in implementing these recommendations is regularly reported to the full Council. I have also noted
the recent “Change Plan- Corporate Leadership Team - Restructure Proposal” from the Chief Executive to “provide the Council
with a more clearly defined and sustainable leadership structure for the foreseeable future” in meeting operational and strategic
challenges. 
3.9 The Audit and Risk Manager has facilitated a workshop with Members of the Audit and Scrutiny Committee to carry out self-
assessments of compliance with the Good Practice Principles Checklist and Evaluation of Effectiveness Toolkit from the CIPFA
Publication – Audit Committees - Practical Guidance for Local Authorities and Police 2022 Edition. This CIPFA Publication sets
Page 25

Page 26

11
out its guidance on the function and operation of audit committees in local authorities and police bodies and represents CIPFA’s
view of best practices for audit committees in local authorities throughout the UK. This exercise was undertaken in 2024, and it is
pleasing to report that the outcome of the self-assessment and evaluation found significant compliance with good practice
principles and a high degree of effectiveness. 
3.10 Counter Fraud - While the prevention of fraud and error rests with management through the design and operation of suitable
systems of control, the audit plan continues to provide time for Internal Audit to coordinate the Council’s participation in the
National Fraud Initiative (NFI), a data matching exercise involving a range of public sector bodies. This activity is viewed as
complementary to other audit activities, and participation assists Internal Audit in assessing the potential for the occurrence of
fraud and related fraud risk. 
3.11 The 2024/25 NFI exercise has progressed and the agreed approach is for services to review and document the reasons for data
matches while the Internal Audit Section investigates potential fraud, monitors progress, and reports on the outcome. Audit
Scotland recommends that councils complete an "NFI self-appraisal checklist as part of planning for the 2024/25 exercise." This
self-appraisal checklist has been reviewed and completed by the Audit and Risk Manager and was provided to the Audit and
Scrutiny Committee on 7 May 2025.  It is pleasing to report that, based on the overview undertaken, the Council is essentially
meeting Audit Scotland’s requirements, with no immediate actions required.
3.12 An element of the Audit Plan is devoted to reviewing core financial systems. Testing was undertaken using a data analysis
software application to extract a random sample of creditor payment transactions for review. The audit programme of testing
undertaken was developed from the Chartered Institute of Public Finance and Accountancy Systems Based Auditing Control
Matrices. Findings found a need for some administrative improvements, but generally, appropriate controls are operating
effectively, and the integrity of systems has been maintained. Further use is planned of the data analysis software application to
ensure more focused audit testing can be undertaken to provide additional assurance in the prevention of fraud and error.
3.13 A review was undertaken of the Council and the MIJB’s governance arrangements to prevent fraud and corruption. The primary
responsibility for preventing and detecting fraud and corruption rests with management to ensure adequate systems of internal
control, segregation of duties and proper authorisation procedures. However, the Internal Audit Section does have a role in
supporting these arrangements by assessing the adequacy of these controls. Findings included a need for further development
in the effective reporting of irregularities. Implementation of the recommendations within this audit review will support the Council’s
anti-fraud and corruption arrangements.
Page 26

Page 27

12
3.14 Risk Management –  procedures have been developed with a risk management policy in place and risk registers maintained at
corporate and service levels. The Risk Management and Business Continuity Officer has assisted in facilitating further
implementation and development of risk management arrangements. This has included updating policies covering
risk management and business continuity. It was noted that the full Corporate Risk Register was reported to the Corporate
Committee for review and consideration at its meeting on 23 April 2024. At this Committee, it was agreed there should be quarterly
reporting to the Committee on risks that had a high-risk score to enable regular review of the risks and mitigating actions.
3.15 It was noted that financial, staffing, information, communication and technology risks remain on-going challenges to the Council.
These are prominent risks for the Council covering how it discharges its functions in terms of good governance, how it manages
its financial affairs, the arrangements for managing and supporting its workforce, and the use of technology, which is key to
delivering most, if not all services. It is appreciated these high-risk categories come not only from circumstances internal to the
Council but also from challenges from the broader economic and social environment faced by all local authorities. 
Statement on Conformance with the Public Sector Internal Audit Standards
3.16 The Local Authority Accounts (Scotland) Regulations 2014 require that ‘a local authority must operate a professional and objective
internal auditing service in accordance with recognised standards and practices in relation to internal auditing’. The recognised
standards adopted by all Scottish councils are the Public Sector Internal Audit Standards (PSIAS) developed by the Chartered
Institute of Public Finance and Accountancy and the Chartered Institute of Internal Auditors. 
3.17 Internal performance monitoring against PSIAS has been ongoing over the last few years. All Scottish local authorities are required
to have an External Quality Assessment (EQA) every 5 years. As part of the Council’s membership of the Scottish Local Authorities
Chief Internal Auditors’ Group, it was agreed that this EQA requirement would be met by each local authority internal audit service
undertaking a review of another council and will thereafter receive a review in return. An EQA of the Council’s Internal Audit
Section was completed by the Chief Internal Auditor of Perth and Kinross Council, and the findings were reported to the Audit and
Scrutiny Committee on 11 September 2024.  The overall conclusion of the external assessment is that the Council’s Internal Audit
Section fully conforms with the PSIAS. This is the highest level of performance standards in the delivery of an internal audit service
within a Scottish local authority and should provide assurance to members and senior management of the effectiveness of internal
audit arrangements within the Council.
3.18 The Public Sector Internal Audit Standards require the Audit and Risk Manager to assess whether audit staffing resources are
sufficient to meet the organisation’s audit needs. Where it is believed that resource levels may adversely impact the delivery of
the annual internal audit opinion, this must be brought to the attention of the Committee. As reported to this Committee on 12
February 2025 (paragraph 6 of the minutes refers), and in accordance with the Public Sector Internal Audit Standards, I am
Page 27

Page 28

13
required to highlight my concerns regarding whether the current staffing levels within the Internal Audit Section are adequate to
meet the future auditing needs of the Council and its partner organisations. An attempt has been made to appoint a full-time
Assistant Auditor; however, this was unsuccessful. A subsequent effort to recruit a part-time Auditor also proved unsuccessful,
and the post is currently being re-advertised. Members of the Audit and Scrutiny Committee will be kept informed of any
developments in the staffing situation and the potential impact on the delivery of the internal audit service. 
3.19 In considering the sufficiency of the audit coverage, the Committee is reminded that the responsibility for developing and
maintaining a sound control environment rests with management and not with internal audit.
SECTION 4- OPINION
4.1 Any system of control can only ever provide reasonable and not absolute assurances that control weaknesses or irregularities do
not exist or that there is no risk of error, fraud, or breaches of laws or regulations. Furthermore, it is the responsibility of
management to establish an appropriate sound system of internal control and monitor its effectiveness. It is the responsibility of
the Audit and Risk Manager to provide an annual assessment of the robustness of the internal control system.
4.2  It is my opinion, with due consideration to the issues detailed within this report, based on the audit work completed and other
sources of assurance, it is considered that reasonable assurance can be placed on the adequacy and effectiveness of the
Council’s internal control system for the year ending 31 March 2025.
Dafydd Lewis
Audit and Risk Manager
13 April 2025
Page 28

Page 29

Report to: Audit and Scrutiny
Committee 
Meeting Date: 24 June 2025     
Report by: Audit and Risk Manager Report No: GSP024/25/DL  
Author: Dafydd Lewis Contact
Email:
dafydd.lewis@moray.gov.uk 
Subject: Internal Audit Section Update Report 
1. PURPOSE 
☒ For Decision      ☐  For Information 
1.1 The purpose of this report is to consider an update on the work of the Internal Audit
Section. 
1.2 This report is submitted to Committee in terms of Section III (I) (2) and (8) of the
Council’s Scheme of Administration relating to consideration of reports from the Council’s
Internal Auditor and monitoring delivery of the audit service through receipt of quarterly
reports on work carried out by Internal Audit. 
2. SUMMARY  
2.1 Public Sector Internal Audit Standards requires the Audit and Risk Manager to prepare
and present reports to committee on internal audit’s activity, performance relative to its
Audit Plan, and any other relevant matters.  
2.2 This report provides an update on audit activity and projects progressed since the last
meeting. 
3. RECOMMENDATIONS  
3.1 It is recommended that Committee:   
i) Considers and notes the contents of this report and seek clarification on
any points.   
Dafydd Lewis
Audit and Risk Manager 
4. BACKGROUND AND CONTEXT 
Moray Integration Joint Board – Internal Audit Service
4.1 The Audit and Risk Manager of the Council is also the Chief Internal Auditor of the Moray
Integration Joint Board (MIJB). This role includes providing assurance on the internal
Item 7.
Page 29

Page 30

controls of systems and practices required by the MIJB to deliver services, regardless of
whether they operate through Council or NHS systems.  An agreement has been
reached with NHS Grampian management and their Internal Audit Provider to share
audit reports on NHS systems and practices relevant to the MIJB with the Chief Internal
Auditor (MIJB). This arrangement also allows the Chief Internal Auditor (MIJB) to report
these reviews to the Audit, Performance and Risk Committee of the MIJB, enabling
members to fulfil the functions outlined in the Scheme of Administration. In addition, a
“Ways of Working Protocol” has been agreed between the internal audit services of NHS
Grampian and the Moray, Aberdeenshire, and Aberdeen City Integration Joint Boards
(see Appendix 1). This collaborative approach aims to strengthen governance and the
control environment across all organisations by supporting more comprehensive and
overarching reviews.   
Follow Up Reviews
4.2 Internal Audit reports are regularly presented to Members detailing not only findings but
also the responses by management to the recommendations with agreed dates of
implementation. Internal Audit will also undertake follow up reviews to evidence the
effective implementation of these recommendations. Please see detailed the following
completed follow up reviews:  
4.3 Roads Maintenance - Planned 
The previous follow up review undertaken of Roads Maintenance - Planned was
reported to the Audit and Scrutiny Committee on 8 May 2024 (para 5 of minute refers).
The review found recommendations that had not been implemented and needed revised
implementation dates. It is appreciated that the implementation of these
recommendations required significant staff resources, including the support of the
Accountancy Section. This Follow-Up Report, detailed on Appendix 2, provides an
update on the current position regarding these outstanding recommendations.
Unfortunately, it was found that the recommendations to review the in-house contractor
schedule of rates, bills of quantities, and on-cost overhead recovery percentages remain
outstanding, although some progress had been made.  
4.4 During this follow-up review, it was noted that the implementation of the
recommendations had been impacted by a lack of staffing resources, which was outside
the control of the Service. The possibility of securing additional resources is now being
investigated to facilitate a more detailed costing analysis aimed at providing greater
accuracy and transparency in the rates and overhead recovery percentages used for
accounting and cost recovery purposes. It is intended that the Internal Audit Section
undertakes another follow-up review in six months to assess progress in implementing
the outstanding recommendations, with a report to be provided to the Audit and Scrutiny
Committee.     
Moray Integrated Community Equipment Store
4.5  An audit was previously undertaken of the Occupational Therapy Store, now known as
the Moray Integrated Community Equipment Store. Occupational therapy stock
comprises aids and equipment issued to help individuals with various daily tasks,
including cooking, dressing, and bathing. Stock items can vary in value, ranging from a
few pounds to upwards of £1,000 for certain types of hoists and specialised seating. A
particular feature of this Store is that it also handles the return of equipment that is no
longer required. Where possible, this equipment is decontaminated and made available
for reuse.  The audit identified significant areas where improvements are needed in the
current operating arrangements. A recent follow-up review found progress in
implementing the recommendations; however, several remain outstanding and require
the agreement of revised implementation dates. The Follow-Up Report, which evaluates
the implementation of the agreed recommendations, is provided in Appendix 3.
Page 30

Page 31

Self Directed Support (SDS) – Option 2/3 
4.6 A follow-up review was undertaken to assess the implementation of recommendations
from a previous audit of Self-Directed Support (SDS). The Social Care (Self-Directed
Support) (Scotland) Act 2013 came into effect in April 2014, introducing the term "Self-
Directed Support" (SDS) to describe how individuals can exercise choice and control
over the support or services that enable them to live independently and achieve agreed
outcomes. The audit reviewed the systems and procedures for administering SDS
Option 2 – Managed Budget, where individuals, following assessment, choose their own
support while Health and Social Care Moray (HSCM) arranges the provision and
payment of that support, and Option 3 – Managed Support, where HSCM selects,
commissions, and pays for the appropriate support on behalf of the individual.  The audit
examined processes related to supporting individuals in determining their preferred care
delivery options, contractual relationships with care providers, financial management,
and the monitoring of individual care packages.  The Follow-Up Report, provided in
Appendix 4, highlights several recommendations that have not been implemented. The
Service has provided revised implementation dates for the outstanding
recommendations. In addition, the Service intends to review progress in implementing
these recommendations at the monthly SDS Steering Group meetings, with updates also
reported for monitoring at the monthly Practice Governance Board meetings.   
Pool Cars Scheme
4.7 This follow-up review assessed the implementation of recommendations made in a
previous audit of the Pool Car Scheme. A pool car is a vehicle owned by the Council and
made available to employees on a shared basis. At the time of the audit, the Council’s
fleet of pool cars consisted of 118 vehicles; 84 classified as general and 34 designated
as service-dedicated vehicles. Approximately 10% of the pool car fleet comprises
electric vehicles. The pool car system is managed through a software application called
Tranman, which is overseen by Fleet Services. The scope of this audit was to review the
systems and procedures governing the management and use of pool cars. Policies and
procedures were examined to ensure they provide appropriate guidance to officers for
booking and using pool cars. The follow-up review noted progress in the implementation
of recommendations. However, some remain outstanding, and there has been a need to
agree on revised dates to implement these recommendations.  The Follow-Up Report is
provided in Appendix 5.   
Early Learning and Childcare Premises Security
4.8 This follow-up review concerns a previous audit undertaken of the controls to mitigate
the risk of unauthorised access to Early Learning and Childcare Nurseries. The audit
also examined the controls to prevent children from leaving nursery buildings and play
areas unnoticed. As part of the review, policies and procedures were assessed, and
visits were made to a sample of nurseries to observe and test the security measures in
practice. The audit acknowledged that the varying age and type of premises present
challenges in ensuring the consistent implementation of physical security arrangements.
It is pleasing to report that the follow-up review found that all recommendations had
been implemented. The Follow-Up Report is provided in Appendix 6. 
5. PROPOSALS  
5.1 It is recommended that Committee agree to note the progress made by Internal Audit in
the period from 7 May 2025 to 24 June 2025. 
6. SUMMARY OF IMPLICATIONS  
6.1 The table below shows whether risks and implications apply if the recommendations are
Page 31

Page 32

agreed: 
SUBJECT YES NO
Corporate Plan and 10 Year Plan (Local Outcome Improvement
Plan) 
×
Policy and Legal  ×
Financial  ×
Risk × 
Staffing  ×
Best Value and Transformation × 
Property  ×
Information Communications Technology/Digital             ×
Equalities. Social Inclusion and Economic Impact   ×
Climate Change, Biodiversity and Sustainability  × 
6.2 Corporate Plan and 10 Year Plan (Local Outcomes Improvement Plan (LOIP))
Improved Collaborative Leadership, as part of continuous improvement through Best
Value, will better enable the Council to fulfil the ambitions set out in its strategic plans. 
a) Links to Council Corporate Plan – The proposals in this report support and
contribute to improved outcomes for communities as outlined in the following Council
Plan strategic priorities:
☐ Tackle Poverty and Inequality.
☐ Build Stronger Greener Vibrant Economy.
☐ Build Thriving, resilient, empowered Communities.   
b) Links to Local Outcomes Improvement Plan – The proposals in this report support
and contribute to improved outcomes for communities as outlined in the following
local Outcomes Improvement Plan priorities:
☐ Developing a diverse, inclusive, and sustainable economy
☐ Building a better future for our children and young people in   Moray.
☐ Empowering and connecting communities.
☐ Improving wellbeing of our population   
6.3 Policy and Legal 
No implications directly arising from this report.  
6.4 Financial 
No implications directly arising from this report. 
One off Costs:
Service
Area
Budget Budget
Years
Proposed
Spend
this Year
Virement
From
Other
Comments       
Annually Recurring Costs:
Service
Area
Budget With
Effect
From
Annual
Net
Impact
Virement
From (if
applicable)
Other
Comments      
Page 32

Page 33

6.5 Risk 
The independent review of selected systems and procedures mitigates the risk
associated with inadequate or ineffective control procedures.  
6.6 Staffing 
No implications directly arising from this report.  
6.7 Best Value and Transformation 
Internal audit work supports good governance and the delivery of efficient services.  
6.8 Property 
No implications directly arising from this report.  
6.9 Information Communications/Technology/Digital 
No implications directly arising from this report.  
6.10 Equalities, Social Inclusion and Economic Impact 
No implications directly arising from this report.  
6.11 Climate Change and Biodiversity Impacts 
No implications directly arising from this report. 
7. CONSULTATION  
7.1 There have been no direct consultations during the preparation of this report. 
8. BACKGROUND PAPERS  
8.1 None   
Page 33

Page 34

Aberdeenshire
Health & Socia! Care
Partnership
Aberdeen City Health & Social Care Partnership
A., • ''" ' • • ..,,
Ways of Working Protocol
NHS Grampian and Integration Joint Boards Internal Audit
NHS
�
Grampian
The following sets out the protocol to be followed with regards to assurance activities
across NHS Grampian and the Moray, Aberdeenshire and Aberdeen City fntegration
Joint Boards. This work will be led by the respective Chief Internal Auditors (CIAs) and
focus on the following:
• The Internal Audit function of the Partner bodies will be included as formal
consultees in the annual audit plans. It is acknowledged that each Partner body
may have different consultation, committee reporting, and timescale
requirements. However, where practical, ttie CIAs should share their draft audit
plans to allow for consultation before the plans are finalised.
• Where possible, and with the approval of the respective Audit Committees, an
area for joint working/assurance should be considered annually. This will be
subject to the availability of resources from each Partner body. ·A joint thematic
report, bringing together the findings from each of the Partner bodies' reviews,
should be considered. However, reporting arrangements will depend on the
needs and requirements of each Partner body's Audit Committee.
• There will be regular collaboration between the CIAs of the respective bodies.
This will include a formal quarterly check in, in addition to ad hoc catch ups as
required.
• The CIAs will draw to the attention of their counterparts any significant findings
from audit work they d�em as relevant throughout the year.
• In line with their respective timelines, annual audit opinions will be shared by the
CIAs with the Internal Audit function of the respective bodies for information.
• NHS Grampian Internal Audit Reports shall be shared with the CIA of the IJBs in
line with the agreement, as set out in the hold harmless letters. Hold harmless
letters will be reviewed annually and updated as required.
APPENDIX 1
Page 34

Page 35

APPENDIX 2
Moray Council
Internal Audit Section
DEPARTMENT: Economy, Environment & Finance
SUBJECT: Roads Maintenance - Planned
REPORT REF: 22'014 
Follow Up Audit Review 
Risk Ratings for Recommendations
High Key controls absent, not being
operated as designed or could be
improved. Urgent attention required.
Medium Less critically important controls
absent, not being operated as
designed or could be improved.
Low Lower level controls absent, not
being operated as designed or
could be improved.
No. Audit Recommendation Priority Accepted
(Yes/ No)
Date of
Completion
Status / Explanation
Key Control: Works met by the capital budget provision follow proper procurement procedures, are monitored effectively and accurately costed. 
5.1 A review of the in-house
contractor Schedule of Rates
should be undertaken to ensure
individual costings provide value
for money. As works are also
awarded directly to the in house
contractor based on a Bill of
Quantities, the same requirement
Medium Yes 31/03/2023
(Revised
Implementation
Date  31/03/2025)
(2nd Revision to
Implementation
Date: 31/10/2025) 
Part Implemented-  Evidence was noted that
the Service has been reviewing individual
costings within the Schedule of Rates and the
Bill of Quantities, with support from the
Accountancy Section. However, due to a
specific staffing issue, this exercise has not
been completed as planned. The Roads
Maintenance Manager acknowledges the
need to progress the review of in-house
contractor rates in order to evidence the basis
Page 35

Page 36

Moray Council
Internal Audit Section 
2
Risk Ratings for Recommendations
High Key controls absent, not being
operated as designed or could be
improved. Urgent attention required.
Medium Less critically important controls
absent, not being operated as
designed or could be improved.
Low Lower level controls absent, not
being operated as designed or
could be improved.
No. Audit Recommendation Priority Accepted
(Yes/ No)
Date of
Completion
Status / Explanation
should be undertaken. Yearly
changes to individual rates
should also be reviewed to
ensure best value is achieved for
the costs charged. 
of calculation and provide greater
transparency. A similar audit recommendation
was recently made to Building Services,
highlighting the need to review in-house
contractor rates. Further investigation is
underway to secure additional resources for
both Services to facilitate a detailed costing
exercise, adopting a “zero-based” approach
to reviewing in-house contractor rates. It is
proposed that a follow-up review be
undertaken in six months to assess progress
and report to the Audit and Scrutiny
Committee on the implementation of this
recommendation. 
5.2 Oncost percentages charged on
works completed by the in house
contractor should be reviewed to
ensure the rates used reflect the
expenditure incurred. 
Medium Yes 31/03/2023
(Revised
Implementation
Date  31/03/2025)
(2nd Revision to
Implementation
Part Implemented-  This recommendation to
review on-cost percentages charged is
directly linked to the need to review in-house
contractor rates, as detailed in section 5.1. As
previously detailed, it is proposed that a
follow-up review be undertaken again after six
Page 36

Page 37

Moray Council
Internal Audit Section 
3
Risk Ratings for Recommendations
High Key controls absent, not being
operated as designed or could be
improved. Urgent attention required.
Medium Less critically important controls
absent, not being operated as
designed or could be improved.
Low Lower level controls absent, not
being operated as designed or
could be improved.
No. Audit Recommendation Priority Accepted
(Yes/ No)
Date of
Completion
Status / Explanation 
Date: 31/10/2025)  months to assess progress and report back to
the Audit and Scrutiny Committee on the
implementation of this recommendation. 
5.3 Consideration should be
undertaken to develop a range of
performance indicators to monitor
the works undertaken by private
and in-house contractors. 
Medium Yes 31/03/2023
(Revised
Implementation
Date  31/12/2024)
Implemented-  The Association for Public
Service Excellence (APSE) Roads,
Highways, and Winter Maintenance
performance comparison indicators with other
local authorities are used in the management
of the Service. Benchmarking exercises have
also been undertaken to compare in-house
contractor costs with charges made by
external contractors for comparable works. It
is pleasing to note, from discussions with the
Roads Maintenance Manager, that these
benchmarking exercises are to continue and
be further developed. 
5.4 Operating procedures should be
documented to assist officers in
managing projects and ensuring
Medium Yes 31/07/2022
(Revised
Implementation
Date  31/12/2024) 
Part Implemented-   An individual scheme
file pack for all internal works over £10,000
has been developed. At the time of the follow-
Page 37

Page 38

Moray Council
Internal Audit Section 
4
Risk Ratings for Recommendations
High Key controls absent, not being
operated as designed or could be
improved. Urgent attention required.
Medium Less critically important controls
absent, not being operated as
designed or could be improved.
Low Lower level controls absent, not
being operated as designed or
could be improved.
No. Audit Recommendation Priority Accepted
(Yes/ No)
Date of
Completion
Status / Explanation
working practices follow
recommended civil engineering
conditions. 
(2nd Revision to
Implementation
Date: 30/09/2025
up audit, it was found that officers were not
consistently completing all the required fields
in the individual scheme file pack. The Roads
Maintenance Manager has reminded officers
to follow the agreed procedures for the
administration of contracts. A further follow-up
review will be undertaken to verify the correct
completion of individual scheme file packs for
all internal works over £10,000. 
Page 38

Page 39

APPENDIX 3
Moray Council
Internal Audit Section
DEPARTMENT: Health & Social Care Moray
SUBJECT:  Moray Integrated Community Equipment Stores 
REPORT REF: 24'013 
Follow Up Audit Review 
Risk Ratings for Recommendations
High Key controls absent, not being
operated as designed or could be
improved. Urgent attention required.
Medium Less critically important controls
absent, not being operated as
designed or could be improved.
Low Lower level controls absent, not
being operated as designed or
could be improved.
No. Audit Recommendation Priority Accepted
(Yes/ No)
Date of
Completion
Status / Explanation
Key Control: Effective systems and procedures operating to ensure accurate records are maintained to account for all occupational therapy
equipment held within Stores and issued to people who access the service.
5.1 A full stock check should be
undertaken to ensure records
correspond to the actual number of
items held within Stores. 
High  Yes  31/03/2024  Implemented– The review confirmed that
Stores officers completed a full stock check
after implementing new stock management
arrangements. The stock take was verified by
an officer from the Internal Audit Section with
only minor variances noted between system
recorded figures and the actual stock held.
Variances were investigated and explanations
obtained. 
Page 39

Page 40

Moray Council
Internal Audit Section 
2
Risk Ratings for Recommendations
High Key controls absent, not being
operated as designed or could be
improved. Urgent attention required.
Medium Less critically important controls
absent, not being operated as
designed or could be improved.
Low Lower level controls absent, not
being operated as designed or
could be improved.
No. Audit Recommendation Priority Accepted
(Yes/ No)
Date of
Completion
Status / Explanation 
Items of equipment should be kept
wherever possible in Asset Number
order within the Stores Building.
Asset Numbers should be clearly
recorded where possible on
shelving. 
Medium  Yes  31/03/2024 
Implemented- Asset numbers are now
clearly recorded on shelving used for storing
equipment.  Shelf locations across the Store
have also been added to the Stores Software
Application (ELMS).   
5.2 The software application used for
purchasing equipment should be
regularly updated with the stock
issued to ensure an accurate unit
price is maintained. 
Further exploration should be
undertaken of ELMS with the
purpose of enabling the direct
purchase of equipment. 
Medium 
Medium
Yes 
Yes
31/03/2024
(Revised
Implementation
Date
30/06/2025) 
31/10/2024
(Revised
Implementation
Date
30/06/2025)
Outstanding– The review found that the
software application used for purchasing
occupational therapy equipment, which is
separate from  ELMS, was not regularly
updated with the stock issued. This impacts
the accuracy of individual stock valuations. 
Outstanding- The Service is making
enquiries with the software provider for ELMS
to check whether it could provide stock
valuations in accordance with accounting
requirements. However, alternative solutions
may be required. The outcome of these
investigations will be reported to the
Page 40

Page 41

Moray Council
Internal Audit Section 
3
Risk Ratings for Recommendations
High Key controls absent, not being
operated as designed or could be
improved. Urgent attention required.
Medium Less critically important controls
absent, not being operated as
designed or could be improved.
Low Lower level controls absent, not
being operated as designed or
could be improved.
No. Audit Recommendation Priority Accepted
(Yes/ No)
Date of
Completion
Status / Explanation
Operational Management Team so that a
preferred solution can be decided. A revised
implementation date of 30/06/2025 has been
agreed with the Service.    
5.3 A review should be undertaken of
the current policy of revaluing re-
used items of equipment at 50% of
the original unit price. 
Medium Yes  31/01/2024
(Revised
Implementation
Date
30/06/2025)
Outstanding-  The decision to revalue re-
used equipment at 50% of the original
purchase price is still under review. The
Service has indicated they intend to provide a
report to members of the MIJB at the
conclusion of this exercise. A revised
implementation date of 30/06/2025 has been
agreed with the Service.  
5.4 People who access the service
should be advised that any
equipment received should be
included within their personal
property content insurance.
Medium Yes 31/01/2024
(Revised
Implementation
Date
30/06/2025) 
Outstanding–  This recommendation is still
under review by the Service. A report on this
issue is intended to be provided to MIJB
members. A revised implementation date of
30/06/2025 has been agreed with the
Service.
5.5 Maximum and minimum stock levels Medium Yes 31/03/2024 Implemented- The review has confirmed that
Page 41

Page 42

Moray Council
Internal Audit Section 
4
Risk Ratings for Recommendations
High Key controls absent, not being
operated as designed or could be
improved. Urgent attention required.
Medium Less critically important controls
absent, not being operated as
designed or could be improved.
Low Lower level controls absent, not
being operated as designed or
could be improved.
No. Audit Recommendation Priority Accepted
(Yes/ No)
Date of
Completion
Status / Explanation
should be implemented in ELMS to
assist officers in ensuring the
effective management of stock
levels.
maximum and minimum stock level functions
are now used within ELMS. The Service also
intends to review these stock level
parameters regularly. 
5.6 A record should be maintained of the
stock checks undertaken, and any
adjustments to stock figures for
equipment recorded within ELMS
should require the authorisation of
the supervisor. 
Medium Yes 31/01/2024 Implemented– Records of weekly stock
checks are now maintained. It was also
confirmed that adjustments to stock levels
within ELMS can now only be authorised by
supervisory officers.
5.7 In regard to the stock of returned
specialised chairs noted during the
audit review, a decision should be
undertaken regarding their future
use. 
Medium Yes 31/03/2024 Implemented- The Service has decided to
retain the chairs. A meeting between officers
from the Equipment Stores of Aberdeen City,
Aberdeenshire and Moray agreed to explore
options regarding the use of these chairs and
other equipment within the Grampian area. In
addition, the Service has advised that the
chairs could be adapted to meet the specific
needs of individuals, potentially providing an
Page 42

Page 43

Moray Council
Internal Audit Section 
5
Risk Ratings for Recommendations
High Key controls absent, not being
operated as designed or could be
improved. Urgent attention required.
Medium Less critically important controls
absent, not being operated as
designed or could be improved.
Low Lower level controls absent, not
being operated as designed or
could be improved.
No. Audit Recommendation Priority Accepted
(Yes/ No)
Date of
Completion
Status / Explanation
alternative to procuring new items. 
5.8 Further development should be
undertaken of ELMS to enable
greater use of the software
application in the management of
stock items. 
Medium Yes 31/03/2024 Implemented– It was found that the Service
is making greater use of the reporting
functions within ELMS. In addition, data from
ELMS is exported to another software
application to allow for greater analysis of
information. 
5.9 Officers should be instructed to
utilise the facility within ELMS to
mark stock as out for delivery. 
Low Yes 30/06/2024 Implemented- Procedures are now in place
requiring drivers delivering equipment from
Stores to mark equipment as out for delivery
within ELMS. 
5.10 A review of off contract expenditure
should be carried out and where
necessary contracts developed.
Low Yes 31/03/2024
(Revised
Implementation
Date
30/06/2025)
Part Implemented- A contract review for
procurement of occupational therapy
equipment is being undertaken. This includes
developing contacts that include a specialised
type of chairs currently procured off contract.
A revised implementation date of 30/06/2025
has been agreed with the Service.
5.11 A formal procedure should be
established for maintaining a list of
Medium Yes 29/02/2024 Implemented- A record of all NHS officers
with authorised access is maintained,
Page 43

Page 44

Moray Council
Internal Audit Section 
6
Risk Ratings for Recommendations
High Key controls absent, not being
operated as designed or could be
improved. Urgent attention required.
Medium Less critically important controls
absent, not being operated as
designed or could be improved.
Low Lower level controls absent, not
being operated as designed or
could be improved.
No. Audit Recommendation Priority Accepted
(Yes/ No)
Date of
Completion
Status / Explanation
NHS officers requiring access to
ELMS.
including confirmation of up-to-date data
protection training. The audit also confirmed
regular reviews are undertaken that check for
officers on-going access requirements to
ELMS. 
5.12 Current operating practices should
be recorded within a Service
Operating Manual.
Medium Yes 31/03/2024 Implemented - Operating Procedures are
now in place to provide officers with a point of
reference guidance in the administration of
the Moray Integrated Community Equipment
Store.
5.13 A review of service procedures
should be undertaken to ensure the
Store is informed of a change in
circumstances in an individual’s
condition where an item of
equipment may no longer be
required. Arrangements should then
be undertaken for collection at the
earliest opportunity. 
Medium  Yes  29/02/2024  Implemented- The Moray Integrated
Community Equipment Service is informed of
equipment issued to an individual but is no
longer required. Testing has confirmed that
when informed, arrangements are made for
the collection of this equipment. 
Page 44

Page 45

Moray Council
Internal Audit Section 
7
Risk Ratings for Recommendations
High Key controls absent, not being
operated as designed or could be
improved. Urgent attention required.
Medium Less critically important controls
absent, not being operated as
designed or could be improved.
Low Lower level controls absent, not
being operated as designed or
could be improved.
No. Audit Recommendation Priority Accepted
(Yes/ No)
Date of
Completion
Status / Explanation
If no agreement can be made for
the equipment to be returned to
the Store, consideration should
be given to invoicing  the
individual for the item.
Medium Yes 31/01/2024
(Revised
Implementation
Date
30/06/2025)
Outstanding – A review of whether there
should be invoicing for equipment not
returned is currently on-going within the
Service. It is intended to report to members of
the MIJB on this issue. A revised
implementation date of 30/06/2025 has been
agreed with the Service.
5.14 Improvements identified to the
Service during the audit review
regarding the physical security of the
Moray Integrated Community
Equipment Store building should be
implemented as a matter of urgency.  
High Yes 31/03/2024 Implemented - A new alarm system has
been fitted at the Moray Integrated
Community Equipment Store and is now in
operation. 
Page 45

Page 46

APPENDIX 4
Moray Council
Internal Audit Section
BODY: Health & Social Care Moray
SUBJECT: Self Directed Support (Options 2 & 3) 
REPORT REF: 23'025 
Follow Up Audit Review 
Risk Ratings for Recommendations
High Key controls absent, not being
operated as designed or could be
improved. Urgent attention required.
Medium Less critically important controls
absent, not being operated as
designed or could be improved.
Low Lower level controls absent, not
being operated as designed or
could be improved.
No. Audit Recommendation Priority Accepted
(Yes/ No)
Date of
Completion
Status / Explanation
Key Control: Effective controls operate in the management and recording arrangements for the delivery of SDS Options 2 and 3 care
packages.   
5.1 In accordance with SDS
Regulations, evidence should be
maintained to document the
discussions held by social
workers regarding the various
care delivery options discussed
with the individual using care
services. 
High Yes 30/09/2023 Part Implemented- The Service has
developed Social Work Assessment
Guidance and documentation that includes a
requirement for supporting and recording the
conversations that need to occur with
individuals and families when determining
care delivery options. The new
documentation aims to ensure the recording
of clear and transparent discussions
regarding the decision-making on SDS
Page 46

Page 47

Moray Council
Internal Audit Section 
2
Risk Ratings for Recommendations
High Key controls absent, not being
operated as designed or could be
improved. Urgent attention required.
Medium Less critically important controls
absent, not being operated as
designed or could be improved.
Low Lower level controls absent, not
being operated as designed or
could be improved.
No. Audit Recommendation Priority Accepted
(Yes/ No)
Date of
Completion
Status / Explanation
options. A quality assurance review was
undertaken by the Service in January 2025 to
evaluate compliance with the Guidance. The
review found the majority of assessments
sampled to have the supported person’s
views on SDS options discussions recorded,
but instances were identified of no or limited
information being recorded on the supported
person’s views. An action plan is to be
developed on improvements required, and
further reviews are to be carried out by the
Service to monitor the recording of
discussions and their quality. Outcome
reporting will be overseen by monthly
meetings of the Practice Governance Board,
with the next meeting on 27/05/25. Internal
Audit Section does not intend to undertake
another formal review to evidence the
implementation of this recommendation, but
an overview of progress undertaken by the
Service will be done when undertaking a
Page 47

Page 48

Moray Council
Internal Audit Section 
3
Risk Ratings for Recommendations
High Key controls absent, not being
operated as designed or could be
improved. Urgent attention required.
Medium Less critically important controls
absent, not being operated as
designed or could be improved.
Low Lower level controls absent, not
being operated as designed or
could be improved.
No. Audit Recommendation Priority Accepted
(Yes/ No)
Date of
Completion
Status / Explanation
follow-up review of other recommendations
within this audit. 
5.2 Documented procedures should
be developed to support social
workers and individuals using
care services in the selecting of
SDS care delivery options. 
High Yes 31/03/2024
(Revised
Implementation
Date
30/09/2025)
Part Implemented- Comprehensive Social
Work Assessment Guidance to support
officers has been developed by the Service
and put into operational use. An objective of
the Guidance is to support a clear and
transparent decision-making process and
promote consistency whilst aligning with
national and local policy requirements and
best practices. However, additional work is
required on updating the information available
to individuals through guides and internet
content to SDS standards and further
developing the Resource Allocation System.
A revised date of 30/09/2025 for full
implementation has been agreed. 
Page 48

Page 49

Moray Council
Internal Audit Section 
4
Risk Ratings for Recommendations
High Key controls absent, not being
operated as designed or could be
improved. Urgent attention required.
Medium Less critically important controls
absent, not being operated as
designed or could be improved.
Low Lower level controls absent, not
being operated as designed or
could be improved.
No. Audit Recommendation Priority Accepted
(Yes/ No)
Date of
Completion
Status / Explanation 
5.3 An annual reference document
detailing a breakdown of the rates
paid to care providers should be
provided to all relevant officers to
assist in budgetary planning and
the accurate preparation of an
individual's support package.   
High Yes 30/06/2023
(Revised
Implementation
Date
01/04/2025)
Outstanding. An annual reference document
is maintained and made available to all
relevant officers to assist in the costing of
support packages. However, the document
has not been revised to include a breakdown
of costs for block funding arrangements.
Work is currently ongoing, together with the
budget savings plan, to identify the
appropriate costing breakdown required for
block funded services.  A revised
implementation date of 01/04/2025 was
agreed during this follow up review.
Verification regarding the implementation of
the recommendation will be done when
undertaking the next follow up review for this
audit.
Page 49

Page 50

Moray Council
Internal Audit Section 
5
Risk Ratings for Recommendations
High Key controls absent, not being
operated as designed or could be
improved. Urgent attention required.
Medium Less critically important controls
absent, not being operated as
designed or could be improved.
Low Lower level controls absent, not
being operated as designed or
could be improved.
No. Audit Recommendation Priority Accepted
(Yes/ No)
Date of
Completion
Status / Explanation
5.4 All officers should be reminded to
update the CareFirst System to
ensure the database is up-to-date
and accurate for each individual
using care services. 
High Yes 30/09/2023 Implemented. The required content of the
CareFirst System is set out in the new Social
Work Assessment Guidance referred to in
5.1.  Training programmes are being
overseen by the SDS Consultant Practitioner,
and quality assurance and review activities
undertaken by the Service to evaluate the
effectiveness of the new guidance in
achieving the required case recording
standards. This will continue to be monitored
by further Service reviews and outcome
reporting will be overseen by monthly
meetings of the Practice Governance Board,
with the next meeting  on 27/05/25.  
5.5 A tripartite agreement between
the individual using the care
service, Council and care
Medium Yes 30/09/2024
(Revised
Implementation
Date
Part Implemented- A random sample of
Option 2 packages commencing in 2024/25
was selected, and they all had a valid
tripartite agreement in place. However, further
Page 50

Page 51

Moray Council
Internal Audit Section 
6
Risk Ratings for Recommendations
High Key controls absent, not being
operated as designed or could be
improved. Urgent attention required.
Medium Less critically important controls
absent, not being operated as
designed or could be improved.
Low Lower level controls absent, not
being operated as designed or
could be improved.
No. Audit Recommendation Priority Accepted
(Yes/ No)
Date of
Completion
Status / Explanation
provider should be agreed for all
SDS Option 2 care packages. 
31/07/2025) to discussions with officers, a review of
service provider payments is to be
undertaken to identify any gaps in historical
packages to ensure all Option 2 individuals
receiving a social care service have a
tripartite in place. A revised date for full
implementation of the recommendation by
31/07/2025 has been agreed with the
Service.   
5.6 A contractual agreement detailing
service delivery and costs should
be agreed with the 3 providers of
day care services noted within
the findings. 
High Yes 31/03/2024
(Revised
Implementation
Date
31/08/2025)
Outstanding. Contractual agreements with
the 3 providers are not yet in place. However,
work has been ongoing in line with the budget
savings plan which will inform the service
requirements and costs. This exercise is
intended to be completed by 31/03/2025 and
will allow contractual arrangements to be
created for these services via a framework
agreement. A revised implementation date of
Page 51

Page 52

Moray Council
Internal Audit Section 
7
Risk Ratings for Recommendations
High Key controls absent, not being
operated as designed or could be
improved. Urgent attention required.
Medium Less critically important controls
absent, not being operated as
designed or could be improved.
Low Lower level controls absent, not
being operated as designed or
could be improved.
No. Audit Recommendation Priority Accepted
(Yes/ No)
Date of
Completion
Status / Explanation
31/08/2025 has been agreed with the Adult
Social Care Commissioning Service.
5.7 Annual support plan reviews of
individuals in receipt of SDS
Option 2 and 3 care packages
should be undertaken in
accordance with agreed
procedures. 
High Yes 30/09/2024
(Revised
Implementation
Date
31/12/2025)
Outstanding. The recommendation of the
requirement to undertake annual reviews of
care and support plans was also detailed
within the audit of SDS Option 1 and the
recent Out of Area Placements review. The
Heads of Service have stated that a review
schedule is to be established, and the need to
undertake annual reviews of care and support
plans for individuals receiving social care
services is to be considered as part of
efficiency strategies. A revised
implementation date of 31/12/2025 has now
been agreed.   
5.8 Consideration should be given for
management to undertake
regular reviews of the accuracy
Medium Yes 30/09/2023 Implemented. A Standard Operating
Procedure (SOP) has been developed to
comprehensively detail all checks required for
Page 52

Page 53

Moray Council
Internal Audit Section 
8
Risk Ratings for Recommendations
High Key controls absent, not being
operated as designed or could be
improved. Urgent attention required.
Medium Less critically important controls
absent, not being operated as
designed or could be improved.
Low Lower level controls absent, not
being operated as designed or
could be improved.
No. Audit Recommendation Priority Accepted
(Yes/ No)
Date of
Completion
Status / Explanation
and recording of the checks
completed to ensure the accuracy
of payments made to care
providers. 
invoice processing. A management review of
a sample of invoices is being carried out on a
monthly basis, to confirm verification checks
have been fully undertaken in line with the
SOP. The performance of the management
review has been evidenced as recorded on
the invoice monitoring spreadsheet
maintained by Community Care Finance. 
5.9 The Council's charging policy
should be reviewed in regard to
day care and a decision made as
to whether a charge should be
levied for the service in the future. 
High Yes 30/09/2023
(Revised
Implementation
Date
30/09/2025)
Outstanding. The Charging and
Contributions Policy has not yet been
reviewed due to staffing resourcing issues.
However, the Charging and Contributions
Policy is planned for review as part of the
ongoing savings work within the Service. A
working group is reviewing the issue,
considering its alignment with the COSLA
Non-Residential Charging Policy. The
Page 53

Page 54

Moray Council
Internal Audit Section 
9
Risk Ratings for Recommendations
High Key controls absent, not being
operated as designed or could be
improved. Urgent attention required.
Medium Less critically important controls
absent, not being operated as
designed or could be improved.
Low Lower level controls absent, not
being operated as designed or
could be improved.
No. Audit Recommendation Priority Accepted
(Yes/ No)
Date of
Completion
Status / Explanation
outcome of the review and potential charging
for day care services is planned to be
presented to the MIJB for decision. A revised
implementation date of 30/09/2025 has been
agreed with the Service. It is appreciated the
decision will thereafter be required to be
considered by Moray Council under their
statutory duties for the setting of charges,
ahead of the 2026/27 budget setting process. 
5.10 A review of arrangements
regarding the authorisation of
individual care packages should
be undertaken. Thereafter,
authorisation requirements
should be documented and
communicated to all appropriate
officers.   
Medium Yes 31/08/2023
(Revised
Implementation
Date
30/06/2025)
Outstanding. Full review and documentation
of care package authorisation requirements
have not been resourced to date. Significant
temporary measures have been implemented
as a result of work on the budget savings
plan, including the creation of a High Cost
Package Panel for appropriate authorisation,
however expansion of the review and
Page 54

Page 55

Moray Council
Internal Audit Section 
10 
Risk Ratings for Recommendations
High Key controls absent, not being
operated as designed or could be
improved. Urgent attention required.
Medium Less critically important controls
absent, not being operated as
designed or could be improved.
Low Lower level controls absent, not
being operated as designed or
could be improved.
No. Audit Recommendation Priority Accepted
(Yes/ No)
Date of
Completion
Status / Explanation
documentation is required. This is to be taken
forward with urgency by the Service, with a
full review of authorisation levels and
documentation aligning to the development of
the Resource Allocation process and with
consideration given to the Financial
Regulations. A revised implementation date
of 30/06/2025 has been agreed with the
Service. 
Page 55

Page 56

APPENDIX 5
Moray Council
Internal Audit Section
DEPARTMENT: Economy, Environment & Finance 
SUBJECT: Pool Cars
REPORT REF: 24'014 
Follow Up Audit Review 
Risk Ratings for Recommendations
High Key controls absent, not being
operated as designed or could be
improved. Urgent attention required.
Medium Less critically important controls
absent, not being operated as
designed or could be improved.
Low Lower level controls absent, not
being operated as designed or
could be improved.
No. Audit Recommendation Priority Accepted
(Yes/ No)
Date of
Completion
Status / Explanation
Key Control: Confirm that policies and procedures for the arrangements and administration of pool cars are in place, up to date and
adequate. 
5.1 All policies and procedures should
be reviewed and updated on a
regular schedule to ensure content
remains current and valid.
Thereafter, they should be promoted
and included within the Council
Intranet to ensure officers are aware
of their requirements and conditions. 
Medium Yes 31/12/2024
(Revised
Implementation
Date
30/09/2025) 
Outstanding-  Fleet Services has advertised
for a Fleet Officer (Pool Cars and Projects);
however, this proved unsuccessful, with the
post currently being re-advertised. This has
delayed the implementation of this
recommendation, but upon recruitment of this
additional officer, a full review of policies and
procedures will occur. A revised
implementation date of 30/09/2025 has been
agreed with the Service.
Page 56

Page 57

Moray Council
Internal Audit Section 
2
Risk Ratings for Recommendations
High Key controls absent, not being
operated as designed or could be
improved. Urgent attention required.
Medium Less critically important controls
absent, not being operated as
designed or could be improved.
Low Lower level controls absent, not
being operated as designed or
could be improved.
No. Audit Recommendation Priority Accepted
(Yes/ No)
Date of
Completion
Status / Explanation
Key Control:  Effective controls in place in the management, booking and use of pool cars.
5.2 Services should be reminded that if
an officer books a vehicle and is
later not required, the booking must
be cancelled immediately. 
Low Yes 30/09/2024 Implemented-  The pool car booking site has
been updated with a notice reminding officers
that if they book a vehicle that is later not
required, the booking must be cancelled
immediately. 
5.3 Senior Management should be
informed to remind all officers that
the use of pool car vehicles must be
in accordance with the Employee
Guide. 
Service Managers should receive
monthly reports from Fleet Services
of any identified instances where the
use of a pool car is not in
accordance with the Employee
Guide. 
High 
High
Yes 
Yes
31/04/2024 
31/12/2024
(Revised
Implementation                 
Date
30/09/2025)
Implemented-  A Three Minute Brief has
been issued requesting all Heads of Services
to remind officers of the need to comply with
the Employee Guide when using a pool car. 
Outstanding- Fleet Services is currently in
the process of recruiting a Fleet Officer (Pool
Cars and Projects). Once this officer is
appointed, the postholder will be responsible
for developing additional monitoring reports
on the use of pool cars. A revised
implementation date of 30/09/2025 has been
agreed with the Service.
Page 57

Page 58

Moray Council
Internal Audit Section 
3
Risk Ratings for Recommendations
High Key controls absent, not being
operated as designed or could be
improved. Urgent attention required.
Medium Less critically important controls
absent, not being operated as
designed or could be improved.
Low Lower level controls absent, not
being operated as designed or
could be improved.
No. Audit Recommendation Priority Accepted
(Yes/ No)
Date of
Completion
Status / Explanation 
5.4 Fleet Service in consultation with the
Accountancy Service should review
the rechargeable hourly rate used for
funding the pool car service.
Consideration should also be given
to recharging these costs to Services
every month. 
Medium Yes 30/06/2024
(Revised
Implementation                 
Date
31/10/2025)
Part Implemented- The Service is currently
reviewing recharge rates for pool cars;
however, this process has not yet been
completed. A revised implementation date of
31/10/2025 has been agreed with the
Service. 
Page 58

Page 59

Moray Council
Internal Audit Section 
4
Risk Ratings for Recommendations
High Key controls absent, not being
operated as designed or could be
improved. Urgent attention required.
Medium Less critically important controls
absent, not being operated as
designed or could be improved.
Low Lower level controls absent, not
being operated as designed or
could be improved.
No. Audit Recommendation Priority Accepted
(Yes/ No)
Date of
Completion
Status / Explanation
5.5 A review of the current pool car
fleet should be undertaken to
determine whether there are any
further value for money
opportunities to increase the
efficiency of the Service. 
Low Yes 31/12/2024  Implemented- A review has been undertaken
by the Service to explore further value for
money and efficiency opportunities regarding
the use of pool cars. Recommendations for
additional improvements have been identified
and will be considered for implementation by
the Environmental Commercial Management
Team. It was noted that some improvements
have already been introduced, particularly in
monitoring the usage of pool cars and the
recharging arrangements for certain
dedicated service vehicles.
5.6 Regular physical inspections of
pool car vehicles should be
introduced to ensure essential
documentation and equipment are
maintained in all pool car vehicles. 
Low Yes Implemented  Implemented-  Regular physical inspections
of pool cars are now undertaken. Checklists
detailing the equipment held in each vehicle
has also been introduced. 
Page 59

Page 60

APPENDIX 6
Moray Council
Internal Audit Section
DEPARTMENT: Education, Communities & Organisational Development 
SUBJECT:  Early Learning and Childcare Premises Security
REPORT REF:  24'017 
Risk Ratings for Recommendations
High Key controls absent, not being
operated as designed or could be
improved. Urgent attention required.
Medium Less critically important controls
absent, not being operated as
designed or could be improved.
Low Lower level controls absent, not
being operated as designed or
could be improved.
No. Audit Recommendation Priority Accepted
(Yes/ No)
Date of
Completion
Status / Explanation
Key Control: The controls for early learning and childcare nurseries and play areas are appropriate to prevent unauthorised access
and children from absconding.
5.1 Council operated nurseries
should be reminded to update the
Early Learning and Childcare
Policies, Procedures and
Guidance Document with their
site-specific security
arrangements.
Medium Yes 31/08/2024 Implemented- A reminder has been issued to
all Council operated early learning and
childcare nurseries to update, if required, their
site-specific security arrangements.
Testing  has also been done that the Early
Learning and Childcare Policies, Procedures
and Guidance for the nurseries visited during
the audit have been updated. 
5.2 All security training provided to
nursery officers should be recorded
within their personal training
records. Regular security
Medium Yes 31/08/2024 Implemented– The follow-up review has
confirmed, through sample testing of officers'
personal training records, that guidance
regarding security procedures is included. In
Page 60

Page 61

Moray Council
Internal Audit Section 
2
Risk Ratings for Recommendations
High Key controls absent, not being
operated as designed or could be
improved. Urgent attention required.
Medium Less critically important controls
absent, not being operated as
designed or could be improved.
Low Lower level controls absent, not
being operated as designed or
could be improved.
No. Audit Recommendation Priority Accepted
(Yes/ No)
Date of
Completion
Status / Explanation
procedures awareness training
should also be provided on an
ongoing basis. 
addition, training related to security
procedures was found to be part of ongoing
training programmes. 
5.3 All nurseries should agree on site
specific operating guidelines to
follow in the event of unauthorised
access to the nursery by an
individual. 
Medium Yes 31/08/2024 Implemented- Operating guidelines should
now be in place for all nurseries in the event
of unauthorised access. Follow up review
testing of a sample of early learning and
childcare nurseries has confirmed these
operating guidelines are in place. 
5.4 Consideration should be given to
including a requirement for
ensuring premises and play area
security arrangements within the
contractual agreements with
private and third sector early
learning and childcare nurseries. 
Medium Yes 31/08/2024 Implemented- The contract with private and
third sector early learning and childcare
nurseries has been updated and includes a
requirement to have an Access Control Policy
in place and to adhere to national standards
regarding safeguarding, which include
maintaining secure premises. It is pleasing to
note the close collaboration between Council
officers and the private/ third sector providers,
Page 61

Page 62

Moray Council
Internal Audit Section 
3
Risk Ratings for Recommendations
High Key controls absent, not being
operated as designed or could be
improved. Urgent attention required.
Medium Less critically important controls
absent, not being operated as
designed or could be improved.
Low Lower level controls absent, not
being operated as designed or
could be improved.
No. Audit Recommendation Priority Accepted
(Yes/ No)
Date of
Completion
Status / Explanation
which was evidenced by sharing the recently
drafted Invacuation, Lockdown, and
Evacuation Policy and Emergency Guidance. 
5.5 Consideration should be given for
all nurseries to install individual
alarms on external doors
accessible to the children. 
High Yes 31/08/2024 Implemented- Risk assessments have been
carried out for all early learning and childcare
nurseries and where required, additional
alarms have been installed, or additional
mitigating controls have been put in place. 
5.6 Consideration should be given for
all nurseries to undertake a
documented assessment of the
premises and play areas to
assess current security risks and
the controls implemented or
required to mitigate these risks.
Medium Yes 31/08/2024 Implemented- Follow up review has
evidenced that a risk assessment exercise
has been undertaken for all early learning and
childcare nurseries premises and play areas
to assess security risks. It was noted that
additional controls have subsequently been
introduced. 
5.7 Consideration should be given to
service delivery inspections at
Medium Yes 31/08/2024 Implemented- The self-evaluation checklist
completed by Continuous Improvement
Page 62

Page 63

Moray Council
Internal Audit Section 
4
Risk Ratings for Recommendations
High Key controls absent, not being
operated as designed or could be
improved. Urgent attention required.
Medium Less critically important controls
absent, not being operated as
designed or could be improved.
Low Lower level controls absent, not
being operated as designed or
could be improved.
No. Audit Recommendation Priority Accepted
(Yes/ No)
Date of
Completion
Status / Explanation
nurseries, including assessing the
physical controls operating within
the nurseries and play areas. 
Officers during service delivery inspections
has now been updated to include a
requirement to assess site security.
5.8 A premises key holder list should
be maintained for all nurseries. 
Medium Yes 31/08/2024  Implemented- All early learning and
childcare nurseries must maintain an up to
date premises key holder. Follow up review of
a sample of nurseries has confirmed that 
updated lists are maintained. 
Page 63

Page 64

Page 64

Page 65

Report to: Audit and Scrutiny
Committee
Meeting Date: 24 June 2025     
Report by: Audit and Risk Manager Report No: GSP08/25/DL  
Author: Dafydd Lewis Contact Email: dafydd.lewis@moray.gov.uk 
Subject:  Internal Audit Review – Building Services - Reactive Repairs 
1. PURPOSE 
☒ For Decision      ☐  For Information 
1.1 The report advises Committee on an internal audit review completed for the               period from
7 May 2025 to 24 June 2025. 
1.2 This report is submitted to Committee in terms of Section III (I) (2) and (8) of the 
Council’s Scheme of Administration relating to consideration of reports from the
Council’s Internal Auditor and monitoring delivery of the audit service through receipt of
quarterly reports on work carried out by Internal Audit. 
2. SUMMARY  
2.1 This report provides details of the internal audit review of Building Services - Reactive
Repairs; this project has been agreed for review within the Internal Audit Plan for 2024/
25. 
3. RECOMMENDATIONS  
3.1 It is recommended that Committee:   
i) Considers the contents of this report, seeks clarification on any points
noted, and endorses the recommendations contained within the report.   
Dafydd Lewis
Audit and Risk Manager 
4. BACKGROUND AND CONTEXT  
4.1 A review has been undertaken of the systems and procedures within Building Services
for managing reactive repair works on Council house properties. The audit scope
covered systems for the administration and management of reactive repairs. This
involved reviewing processes from raising a requirement and carrying out the work to
recharging costs and managing budgets. Building Services is responsible for the repairs
and maintenance of approximately 6,000 Council properties, with an annual expenditure
of approximately £3.6 million.
Item 8.
Page 65

Page 66

4.2 Findings from the audit review highlighted the need for administrative improvements in
costing arrangements and budget management systems. In addition, the provision of
certification for gas and electrical work undertaken at properties requires improvement.
The audit report for this project is provided in the Appendix 1. 
5. PROPOSALS  
5.1 This report provides Committee with a summary of findings arising from an audit project
completed during the review period. 
6. SUMMARY OF IMPLICATIONS  
6.1 The table below shows whether risks and implications apply if the recommendations are
agreed: 
SUBJECT YES NO
Corporate Plan and 10 Year Plan (Local Outcome Improvement
Plan) 
×
Policy and Legal  ×
Financial  ×
Risk × 
Staffing  ×
Best Value and Transformation × 
Property  ×
Information Communications Technology/Digital             ×
Equalities. Social Inclusion and Economic Impact   ×
Climate Change, Biodiversity and Sustainability  × 
6.2 Corporate Plan and 10 Year Plan (Local Outcomes Improvement Plan (LOIP))
Improved Collaborative Leadership, as part of continuous improvement through Best
Value, will better enable the Council to fulfil the ambitions set out in its strategic plans. 
a) Links to Council Corporate Plan – The proposals in this report support and
contribute to improved outcomes for communities as outlined in the following Council
Plan strategic priorities:
☐ Tackle Poverty and Inequality.
☐ Build Stronger Greener Vibrant Economy.
☐ Build Thriving, resilient, empowered Communities.   
b) Links to Local Outcomes Improvement Plan – The proposals in this report support
and contribute to improved outcomes for communities as outlined in the following
local Outcomes Improvement Plan priorities:
☐ Developing a diverse, inclusive, and sustainable economy
☐ Building a better future for our children and young people in   Moray.
☐ Empowering and connecting communities.
☐ Improving wellbeing of our population 
6.3 Policy and Legal  
No implications directly arising from this report.  
6.4 Financial
Page 66

Page 67

No implications directly arising from this report. 
One off Costs:
Service
Area
Budget Budget
Years
Proposed
Spend
this Year
Virement
From
Other
Comments       
Annually Recurring Costs:
Service
Area
Budget With
Effect
From
Annual
Net
Impact
Virement
From (if
applicable)
Other
Comments       
6.5 Risk 
The independent review of selected systems and procedures mitigates  the risks
associated with inadequate or ineffective control procedures.  
6.6 Staffing 
No implications directly arising from this report.  
6.7 Best Value and Transformation 
Internal audit work supports good governance and the delivery of efficient services.  
6.8 Property 
No implications directly arising from this report.  
6.9 Information Communications/Technology/Digital 
No implications directly arising from this report.  
6.10 Equalities, Social Inclusion and Economic Impact 
No implications directly arising from this report.  
6.11 Climate Change and Biodiversity Impacts 
No implications directly arising from this report. 
7. CONSULTATION  
7.1 There have been no direct consultations during the preparation of this  report. 
8. BACKGROUND PAPERS  
8.1 None   
Page 67

Page 68

APPENDIX 1
1
Final Internal Audit Report
Building Services- Reactive Repairs 
May 2025
Distribution: Head of Housing and Property Services
Building Services Manager
The Internal Audit Section provides Management with an opinion on the internal control
environment and categories risk ratings for recommendations as high, medium, or low (detailed
explanation provided in Appendix1). The audit recommendations for this review have been
classified as follows. 
Assurance Level
Risk Ratings for
Recommendations
Priority 1 1
Substantial Priority 2 5
Priority 3 0
Confidentiality and Disclosure Clause
This report (“Report”) was prepared by the Internal Audit Section of Moray Council. The matters raised in this Report are
only those which came to our attention during our internal audit work. Whilst every care has been taken to ensure that the
information provided in this Report is as accurate as possible, the Moray Council Internal Audit Section has only been able
to base findings on the information and documentation provided and consequently, no complete guarantee can be given
that this Report is necessarily a comprehensive statement of all the weaknesses that exist, or of all the improvements that
may be required.
This Report was prepared solely for the use and benefit of the Moray Council, Moray Integration Joint Board or the
Grampian Valuation Joint Board. Moray Council's Internal Audit Section accepts no responsibility and disclaims all liability
to any third party who purports to use or rely for any reason whatsoever on the Report, its contents, conclusions, any
extract, reinterpretation, amendment and/or modification. Accordingly, any reliance placed on the Report, its contents,
conclusions, any extract, reinterpretation, amendment, and/or modification by any third party is entirely at their own risk.
Please refer to the Statement of Responsibility in Appendix 2 of this report for further information about
responsibilities, limitations, and confidentiality.  
Page 68

Page 69

2
Contents
Page
Building Services- Reactive Repairs 
1. Introduction & Scope 3
2. Key Issues 3-4
Detailed Report
3. Findings/Recommendations 5-14
4. Management Response 5-14
Appendices
1. Audit Terms of Reference and Definitions
2. Statement of Responsibility
Page 69

Page 70

3
1. Introduction and Audit Scope
The annual audit plan for 2024/25 included a review of the systems and
procedures within Building Services for managing reactive repair works on
Council house properties. Reactive repairs refer to works carried out on a
responsive basis as needs arise, rather than being deferred for inclusion in
planned maintenance programmes. Examples of reactive works include
emergency repairs to central heating systems, water leaks, or damaged
windows.
Building Services is responsible for the repairs and maintenance of
approximately 6,400 Council properties. Approximately 20,000 reactive
repairs are carried out annually. Analysis of the Financial Management
System noted that for 2023/24, expenditure for reactive repairs amounted to
approximately £3.6 million. The majority of reactive repairs are requested by
tenants through the Council's Contact Centre; however, the need for repairs
can also be raised by Housing/Building Services officers and through the Out
of Hours Service. 
The audit scope reviewed systems for the administration and management
of reactive repairs. This involved checking processes from raising a
requirement and undertaking the works to recharging costs and managing
budgets. In addition, the contractual relationship between Housing, Property,
and Building Services was also reviewed. The Annual Internal Audit Plan
allows for internal audit reviews to include testing that appears to be “outwith
scope.” During a recent special investigation into a window replacement
contract, an issue was noted regarding the administration of planned works
undertaken by Building Services. As a result, additional testing was also
carried out as part of this audit review.
The audit was carried out in accordance with Public Sector Internal Audit
Standards (PSIAS).
2. Key Issues
• This issue concerns the additional testing undertaken as part of this
review and relates to planned works that are recorded as not completed
within Property Services due to the pending receipt of certification
documentation for gas and electrical works undertaken at properties by
Building Services. The audit review confirmed that several contracts
involving properties requiring gas and electrical certification had not
been provided by Building Services. The need for certification
documentation for electrical and gas works is a regulatory requirement.
This is in addition to the gas and electrical safety checks undertaken by
Page 70

Page 71

4
Building Services at properties. Building Services should review all
reactive and planned works involving gas and electrical works, and, if
required, a Gas Safety Certificate and/or an Electrical Installation
Certificate for the property should be provided to Property Services.
However, it is important to note that this is not a concern regarding the
safety of the works undertaken, but rather about ensuring that the
correct certification documentation is maintained. 
• A Schedule of Rates is used to charge for reactive repair works
undertaken by Building Services. The Schedule of Rates is based on a
costing exercise conducted in 2019. The Building Services Manager
stated that an annual percentage uplift is applied to the Schedule of
Rates, determined following discussions with Property and Housing
Services and a review of construction cost changes detailed by the
Building Cost Information Service. Consideration should be given to
reviewing and if necessary, updating the costs and percentage
recovery rates used within the Schedule of Rates for reactive repairs.
While it is acknowledged that this would be a significant exercise, it
would provide greater transparency and support more accurate
performance data on the actual costs of works undertaken.
• Building Services will recharge the Housing Service on a monthly basis
for the reactive repairs undertaken in the prior month. Audit testing
identified several areas where further administrative improvements are
needed. These include delays in recharging costs; prompt recording
and accounting of costs are essential for effective budgetary
management control. Additionally, improvements were identified in
ensuring that once a reactive repair is completed, the cost is promptly
recharged to the Housing Service and the work order is recorded as
closed within the Dynamic Resource Scheduling (DRS) software
system.
Page 71

Page 72

5 
Findings/Recommendations -Building Services- Reactive Repairs
Ref Risk Ratings for
Recommendations
Audit Finding Audit Recommendation
1 Medium It was noted that the Partnership Agreement
between Housing, Property, and Building Services
has not been reviewed since 2013. An updated
Partnership Agreement was drafted in 2019;
however, it was not approved. The purpose of the
Partnership Agreement is to provide a framework
within which services “can continue to provide an
improved service for council tenants.” This
document outlines the relationships between the
parties, the standards and quality of work, and the
costs involved in implementing an ongoing
housing maintenance program.
A review should be undertaken, and if
required, the Partnership Agreement
between Housing, Property, and Building
Services should be updated to ensure it
reflects current operational and service
best value requirements.
Management Response
Responsible Officer Accepted
(Yes/No
Timescale for
Implementation 
Agreed Management Action/Management Comment
Head of Housing & Property
Services
Yes 31/03/2026 A review of the Partnership Agreement between Housing,
Property, and Building Services will be undertaken and if this is
still required it will be updated to ensure it reflects current
operational and service best value requirements. Consideration
will be given to achieving the objectives of the Partnership
Agreement by alternative means, based on benchmarking with
other local authorities.
Page 72

Page 73

6
Ref Risk Ratings for
Recommendations
Audit Finding Audit Recommendation
2 Medium Building Services undertakes approximately
20,000 reactive repairs annually, costing £3.6
million in 2023/24. Discussions with the Building
Services Manager noted that a Schedule of Rates
is used to recharge the various reactive repair
works undertaken on properties for the Housing
Service. The calculation of the individual rates
within the Schedule was determined through a
costing exercise conducted in 2019. The Building
Services Manager also stated that the annual
percentage increase in the Schedule of Rates is
decided after discussions with Property and
Housing Services, with consideration also given to
the Building Cost Information Service (BCIS)
indices. The BCIS Indices provide cost and price
data for the UK construction industry, including
estimated future construction costs. However, the
audit review found it difficult to determine how the
individual rates have been established, which is
crucial for ensuring the accurate recovery of full
costs and enabling effective performance data
analysis of the actual costs of the works
undertaken. 
A ‘zero-based’ approach should be
considered to review, and if necessary,
update the costs and percentage recovery
rates used within the Schedule of Rates for
reactive repairs. It is acknowledged that
this would be a significant exercise in the
delivery of a multi-trade service, due to the
large number of separate costing lines
detailed within the Schedule of Rates. 
Page 73

Page 74

7
Management Response
Responsible Officer Accepted
(Yes/ No)
Timescale for
Implementation
(Date Required) 
Agreed Management Action/Management Comment
Head of Housing & Property
Services
Yes 31/03/2026 In accepting this recommendation, it is timely for the service to
consider the broader approach to job costing and its
implications for efficiency of process, quality of work and
customer services standards in achieving best value for the
Council and its tenants. 
The service will commission a consultant to undertake the zero-
basing exercise, including a comprehensive review of repairs
data and consider alternatives approaches including a fixed
annual cost per property. 
Page 74

Page 75

8
Ref Risk Ratings for
Recommendations
Audit Finding Audit Recommendation
3    High Additional testing has been undertaken as part of
this review, as planned works were noted within
Property Services, which are still awaiting the
receipt of certification documentation for gas and
electrical works undertaken at properties by
Building Services.
Regarding electrical works, an Electrical
Installation Works Certificate from a qualified
Moray Council electrician or electrical contractor is
a regulatory requirement upon the completion of
electrical installation works. The audit review
noted that a number of planned contracts works
involving electrical works remain open within
Property Services, awaiting the Electrical
Installation Works Certificate from Building
Services. Analysis of contracts issued to Building
Services over a number of years revealed that 36
contracts are still recorded as “open,” awaiting an
Electrical Installation Works Certificate for 43
properties.
For works involving gas, a Gas Safety Certificate
from a qualified engineer is a regulatory
requirement for new gas boiler installations,
Building Services should review both
reactive and planned works involving gas
and electrical requirements to determine if
additional certification is needed. If not
already completed, a Gas Safety Certificate
and/or an Electrical Installation Certificate
for the property should be provided to
Property Services. Moving forward, and in
accordance with regulatory requirements,
Building Services should provide Electrical
Installation Certificates and Gas Safety
Certificates to Property Services in a timely
manner for all completed projects. The
audit finding highlights an administrative
requirement, not a concern regarding the
safety of the works undertaken. 
Page 75

Page 76

9
services, and all other gas appliance checks at a
property. The audit review also examined planned
contracts issued to Building Services involving
works at properties requiring a Gas Safety
Certificate. The audit noted 96 contracts still
recorded as “open,” awaiting the Gas Safety
Certificate for 119 properties.
.
Management Response
Responsible Officer Accepted
(Yes/ No)
Timescale for
Implementation
(Date Required) 
Agreed Management Action/Management Comment 
Building Services Manager Yes 30/06/2025 The issue of delays in providing gas and electricity certificates
in relation to works done was identified within the partnership a
number of years ago and as a result the Plentific (Gas and
Elec-Tag) system was implemented January 2020 for gas
certificates and April 2022 for electric certificates, to allow for
the automation of gas and electricity certification records.
Where certificates have not been passed to the design team
these will be identified and forwarded to them. Where these
cannot be identified, the current safety certification will be
provided to give assurance that properties are safe. A review of
processes will be carried out to ensure all certificates are
issued immediately when works are completed to relevant
Contact Administrators. 
Page 76

Page 77

10
Ref Risk Ratings for
Recommendations
Audit Finding Audit Recommendation
4 Medium An analysis of the Financial Management System
noted that the annual reactive repairs expenditure
was approximately £3.6 million in 2023/24.
Building Services recharge the Housing Service
on a monthly basis for reactive repairs undertaken
in the previous month. However, audit testing of a
sample of works orders from one month's reactive
repairs found that in 13% of work orders tested,
with a cumulative value of £1,511, delays of up to
4 months were noted between the recharging of
costs to the Housing Service and the date the
works were actually undertaken. Enquiries with
Building Services revealed that delays can occur
in receiving the required documentation from
officers and subcontractors. The majority of
reactive repair works are managed through a
repairs Dynamic Resource Scheduling (DRS)
software system, but jobs can also be raised
manually through a paper-based system. Analysis
found that approximately 22% of all reactive repair
work orders are issued through the paper-based
system. The audit was advised that delays in
officers providing all supporting documentation
are more prominent in the paper-based system.
All officers involved in undertaking reactive
repair works should be reminded of the
importance of ensuring that the relevant
supporting documentation for the job is
provided promptly to the administration
officers within Building Services to allow
the prompt recharging of costs.
Consideration should be given to making
further use of the DRS software system
and reducing reliance on the paper based
system for the raising of work orders. This
would allow improved transparency and
performance monitoring arrangements in
the management of reactive works. 
Page 77

Page 78

11
Management Response
Responsible Officer Accepted
(Yes/ No)
Timescale for
Implementation
(Date Required) 
Agreed Management Action/Management Comment
Building Services Manager Yes 30/09/2025 Processes are being reviewed as part of current Repairs
Review, with implementation to be in place by 30 September
2025. Issues have been identified with the timing of sub
contactor invoices being received that has delayed some
repairs from being recharged, this process has also been
amended.
Page 78

Page 79

12
Ref Risk Ratings for
Recommendations
Audit Finding Audit Recommendation
5 Medium In 2023/24, Building Services undertook
approximately 20,000 reactive repair work orders
with 80% completed within agreed performance
timescale targets. At the time of the audit, an
analysis of the DRS found 1506 reactive repair
works orders with an approximate value of
£432,000, remained open past their target
completion dates. Enquiries with the Building
Services Manager noted a significant reason for
not completing work orders within agreed
timescales was due to staff shortages and the
difficulty in the recruitment of officers. The audit
acknowledges that several services within the
Moray Council are experiencing similar issues in
recruiting staff. However, further analysis noted
that 27% of the works orders recorded as not
completed had either been carried out or were no
longer required but had not been closed off within
the DRS. 
Regular reviews should be undertaken with
explanations sought if required for reactive
repair work orders recorded as open, but
jobs have not been completed within the
target timescales. Further to the audit
finding, works orders recorded as not
completed but the job has been undertaken
or no longer required should be closed off
promptly within the DRS software. 
Page 79

Page 80

13
Management Response
Responsible Officer Accepted
(Yes/ No)
Timescale for
Implementation
(Date Required) 
Agreed Management Action/Management Comment
Building Services Manager Yes 30/09/2025 Weekly reports are issued highlighting the volume of repairs
not complete. These are circulated to relevant staff to ensure
outstanding repairs completed can be closed off. A number of
issues have been identified that includes delays recharging a
high volume of paper based works orders (over 70 of
outstanding repairs) , that are being reviewed  as part of the
Repairs Review to ensure that the majority of jobs are
scheduled via DRS which allows jobs to be completed and
recorded in real time, rather than on a paper based system.
Page 80

Page 81

14
Ref Risk Ratings for
Recommendations
Audit Finding Audit Recommendation
6 Medium As detailed previously, Building Services will
recharge the Housing Service on a monthly basis
for the reactive repair works undertaken in the
prior month. However, it was noted during the
audit that the monthly recharges for October and
November 2025, with a total value of £445,000,
had not been processed until January 2025.
Prompt recording and accounting for costs is an
important budgetary management control
requirement. Further to audit enquiries, it was
noted that this error was due to a staffing change,
with an officer unaware of the operating
arrangements. Additionally, it was found that
Building Services had no documented procedures
detailing the monthly recharging requirements for
reactive repair works to the Housing Service. 
The cost of reactive repair works
undertaken by Building Services during a
month should be recharged to the Housing
Service in the following month.
Documented procedures should also be
developed to ensure that officers have
clear guidelines on the actions to be
undertaken when recharging reactive repair
works. 
Management Response
Responsible Officer Accepted
(Yes/ No)
Timescale for
Implementation
(Date Required) 
Agreed Management Action/Management Comment
Building Services Manager Yes 30/06/2025 Process for recharging repairs has been reviewed within
Building Services. These have now been amended to ensure
that recharges are processed within accountancy time frames,
with a written procedure now developed. A further review will
be carried out of procedures within the Housing Asset team to
ensure the authorisation/certification process is improved. 
Page 81

Page 82

15
Appendix 1
AUDIT TERMS OF REFERENCE AND DEFINITIONS 
1. Audit Objectives
1.1 The overall audit objective is to provide an objective independent opinion on
the adequacy and effectiveness of controls / processes.
1.2 The audit will for each controls / process being considered:
• Walkthrough the processes to consider the key controls.
• Conduct sample testing of the identified key controls, and
• Report on these accordingly
1.3 All audit reviews are carried out in accordance with Public Sector Internal
Audit Standards (PSIAS).
2. Definitions for Auditing Opinions and Findings
2.1 In order to assist management in using our reports:
The Internal Auditor will categorise audit assurance opinion according to
their overall assessment of the risk management system, effectiveness of the
controls in place and the level of compliance with these controls and the
action being taken to remedy significant findings or weaknesses.
Assurance
Level
System and Testing Conclusion
Full The controls tested are being consistently applied
Substantial There is evidence that the level of noncompliance with some of
the controls may put some of the system objectives at risk.
Limited The level of noncompliance puts the system objectives at risk.
None Significant non-compliance with basic controls leaves the system
open to error or abuse. 
2.2 Risk ratings for each recommendation is based on the following criteria:
High Fundamental control weaknesses that require immediate
attention by management to action and mitigate significant
exposure to risk
Medium Less critically important controls absent, not being operated as
designed or could be improved
Low Lower level controls absent, not being operated as designed or
could be improved.
Page 82

Page 83

16
Appendix 2
STATEMENT OF RESPONSIBILITY
The responsibility for designing and maintaining a sound system of internal control
to prevent and detect fraud and other irregularities rests with management, with
internal audit providing a service to management to support them to achieve this
objective. The Internal Audit Section will assess the adequacy and effectiveness of
the system of internal control arrangements implemented by management and
perform sample testing on those controls in the period under review with a view to
providing an opinion on the extent to which risks in this area are managed.
The Internal Audit Section will undertake testing with the objective of detecting
significant control weaknesses. However, the audit approach alone should not be
relied upon to identify all strengths and weaknesses in internal controls nor to find
any fraud or irregularity. Even sound systems of internal control can only provide
reasonable and not absolute assurance and may not be proof against collusive
fraud.
The matters raised in this report are only those that came to our attention during
the audit review and are not necessarily a comprehensive statement of all the
weaknesses that exist or all improvements that might be made. Recommendations
for improvements should be assessed by management for their full impact before
they are implemented. The performance of the audit review undertaken should not
be taken as a substitute for management’s responsibilities for the application of
sound management practices.
This report is confidential and must not be disclosed to any third party or
reproduced in whole or in part without the written consent of the Moray Council’s
Audit and Risk Manager.
Page 83

Page 84

Page 84

Page 85

Report to: Audit and Scrutiny
Committee
Meeting Date: 24 June 2025     
Report by: Audit and Risk
Manager
Report No: GSP025/25/DL  
Author: Dafydd Lewis Contact
Email:
dafydd.lewis@moray.gov.uk 
Subject:  Internal Audit Review – Keith Grammar School 
1. PURPOSE 
☒ For Decision      ☐  For Information 
1.1 The report advises Committee on an internal audit review completed for the               period
from 7 May 2025 to 24 June 2025. 
1.2 This report is submitted to Committee in terms of Section III (I) (2) and (8) of the 
Council’s Scheme of Administration relating to consideration of reports from the
Council’s Internal Auditor and monitoring delivery of the audit service through receipt of
quarterly reports on work carried out by Internal Audit. 
2. SUMMARY  
2.1 This report provides details of the internal audit review of Keith Grammar School; this
project has been agreed for review within the Internal Audit Plan for 2024/25. 
3. RECOMMENDATIONS  
3.1 It is recommended that Committee:   
i) Considers the contents of this report, seeks clarification on any points
noted, and endorses the recommendations contained within the report.   
Dafydd Lewis
Audit and Risk Manager 
4. BACKGROUND AND CONTEXT  
4.1 An audit of the administrative arrangements at Keith Grammar School has been
completed. The scope of the audit was to review the Devolved School Management
Scheme, focusing on the allocation and management of funding at the School. In
addition to examining how the School develops, monitors, and controls its £3.3 million
budget, the audit also assessed the management of staffing costs associated with
delivering the curriculum. The audit checked whether non-payroll expenditure complied
with Financial Regulations and Procurement Guidelines. A review was also undertaken
to ensure appropriate accounting arrangements are followed in the management of
Item 9.
Page 85

Page 86

School fund monies. Overall, the audit found that Keith Grammar School was generally
well managed within the scope of the review. However, some areas requiring
administrative improvement were identified. The findings and recommendations are
detailed in the audit report in Appendix 1. 
5. PROPOSALS  
5.1 This report provides Committee with a summary of findings arising from an audit project
completed during the review period. 
6. SUMMARY OF IMPLICATIONS  
6.1 The table below shows whether risks and implications apply if the recommendations
are agreed: 
SUBJECT YES NO
Corporate Plan and 10 Year Plan (Local Outcome Improvement
Plan) 
×
Policy and Legal  ×
Financial  ×
Risk × 
Staffing  ×
Best Value and Transformation × 
Property  ×
Information Communications Technology/Digital             ×
Equalities. Social Inclusion and Economic Impact   ×
Climate Change, Biodiversity and Sustainability  × 
6.2 Corporate Plan and 10 Year Plan (Local Outcomes Improvement Plan (LOIP))
Improved Collaborative Leadership, as part of continuous improvement through Best
Value, will better enable the Council to fulfil the ambitions set out in its strategic plans. 
a) Links to Council Corporate Plan – The proposals in this report support and
contribute to improved outcomes for communities as outlined in the following
Council Plan strategic priorities:
☐ Tackle Poverty and Inequality.
☐ Build Stronger Greener Vibrant Economy.
☐ Build Thriving, resilient, empowered Communities.   
b) Links to Local Outcomes Improvement Plan – The proposals in this report support
and contribute to improved outcomes for communities as outlined in the following
local Outcomes Improvement Plan priorities:
☐ Developing a diverse, inclusive, and sustainable economy
☐ Building a better future for our children and young people in   Moray.
☐ Empowering and connecting communities.
☐ Improving wellbeing of our population   
6.3 Policy and Legal  
No implications directly arising from this report.  
6.4 Financial  
No implications directly arising from this report. 
Page 86

Page 87

One off Costs:
Service
Area
Budget Budget
Years
Proposed
Spend
this Year
Virement
From
Other
Comments       
Annually Recurring Costs:
Service
Area
Budget With
Effect
From
Annual
Net
Impact
Virement
From (if
applicable)
Other
Comments       
6.5 Risk 
The independent review of selected systems and procedures mitigates  the risks
associated with inadequate or ineffective control procedures.  
6.6 Staffing 
No implications directly arising from this report.  
6.7 Best Value and Transformation 
Internal audit work supports good governance and the delivery of efficient services.  
6.8 Property 
No implications directly arising from this report.  
6.9 Information Communications/Technology/Digital 
No implications directly arising from this report.  
6.10 Equalities, Social Inclusion and Economic Impact 
No implications directly arising from this report.  
6.11 Climate Change and Biodiversity Impacts 
No implications directly arising from this report. 
7. CONSULTATION  
7.1 There have been no direct consultations during the preparation of this  report. 
8. BACKGROUND PAPERS  
8.1 None   
Page 87

Page 88

APPENDIX 1
1
Final Internal Audit Report
Keith Grammar School 
April 2025 
Distribution: Head of Education
Head Teacher
School Support Co-ordinator
The Internal Audit Section provides Management with an opinion on the internal control environment
and also categories risk ratings for recommendations as high, medium or low (detailed explanation
provided in Appendix1). The audit recommendations for this review have been classified as follows
Assurance Level Risk Ratings for
Recommendations
Substantial
Priority 1 0
Priority 2 4
Priority 3 2
Confidentiality and Disclosure Clause
This report (“Report”) was prepared by the Internal Audit Section of Moray Council. The matters raised in this Report are only
those which came to our attention during our internal audit work. Whilst every care has been taken to ensure that the information
provided in this Report is as accurate as possible, the Moray Council Internal Audit Section has only been able to base findings
on the information and documentation provided and consequently, no complete guarantee can be given that this Report is
necessarily a comprehensive statement of all the weaknesses that exist, or of all the improvements that may be required.
This Report was prepared solely for the use and benefit of the Moray Council, Moray Integration Joint Board or the Grampian
Valuation Joint Board. Moray Council's Internal Audit Section accepts no responsibility and disclaims all liability to any third party
who purports to use or rely for any reason whatsoever on the Report, its contents, conclusions, any extract, reinterpretation,
amendment and/or modification. Accordingly, any reliance placed on the Report, its contents, conclusions, any extract,
reinterpretation, amendment and/or modification by any third party is entirely at their own risk.
Please refer to the Statement of Responsibility in Appendix 2 of this report for further information about responsibilities,
limitations and confidentiality.
Page 88

Page 89

2
Contents
Page
Keith Grammar School 
1. Introduction & Scope 3
2. Key Issues 3-4
Detailed Report
3. Findings/Recommendations 5-10
4. Management Response 5-10
Appendices
1. Audit Terms of Reference and Definitions
2. Statement of Responsibility
Page 89

Page 90

3
1. Introduction and Audit Scope
The annual Internal Audit plan for 2024/25 provides for a review of a secondary
school within Education Services. This audit details the findings from the review
undertaken of Keith Grammar School as part of a rolling programme of audit visits
planned for secondary schools.
The scope of this audit was to review the operation of the Devolved School
Management Scheme in terms of funding allocation and management at the
school level. Consideration was given to how budgets are affected by National,
Council and School priorities.  
In addition to undertaking an overview of how the School develops, monitors and
controls its £3.3 million annual devolved budget, the audit involved a study of the
management of the staffing costs involved in delivering the curriculum. The audit
checked that non payroll expenditure complied with Financial Regulations and
Procurement Guidelines. A review was also undertaken to ensure appropriate
accounting arrangements are followed when managing School Fund monies in
accordance with the School Fund Regulations. This report sets out the work
undertaken in relation to the 24/25 financial year.
The audit was carried out in accordance with Public Sector Internal Audit
Standards (PSIAS).
2. Key Issues
• A review of the School's Inventory Record noted that movable assets
valued at £250 or above have been recorded. This exceeds the
requirements of the Council's Financial Regulations, which specify the
need for a comprehensive record of all movable items with an individual
replacement cost exceeding £500. In addition, despite recording
movable assets valued at more than £250, the majority of items listed
had no recorded value detailed within the Inventory Record. The School
should review and update its Inventory Record, ensuring that the
replacement costs of all items exceeding £500 are accurately
documented.
• Further improvements are recommended to strengthen controls in the
administration and accounting arrangements for the School Fund. The
review noted that one of the signatories had pre-signed blank cheques
for the School Fund bank account. Enquiries found that the School Fund
bank account only had two signatories, and the pre-signing of cheques
was due to a staffing issue and a need to facilitate the ongoing
Page 90

Page 91

4
processing of payments. To enhance financial oversight, additional
cheque signatories should be established for the School Fund bank
account, ensuring that one signatory authorises a payment while
another verifies the transaction. Additionally, the  annual School Fund
Income and Expenditure Statement could be further detailed to provide
readers with a clearer understanding of financial activities. 
• The iPayimpact online payment system is not being utilised collecting
income related to school activities such as trips, clubs and events. As a
result, the School has had to rely on more labour intensive manual
income collection processes. Consideration should be given to
increasing the use of the iPayimpact online payment system.
Page 91

Page 92

5
Findings/Recommendations - Keith Grammar School 2024/25
Ref Risk Ratings for
Recommendations
Audit Finding Audit Recommendation
1 Medium Financial Regulations require an Inventory List to be
maintained of all movable assets valued at £500 or
above to be maintained. However, it was found that
the School maintained an Inventory List of items
valued at more than £250, a figure specified in a
previous version of the Financial Regulations.
Additionally, at the time of the audit, only 35% of the
listed items had a recorded value. It was explained
that this was due to officers updating the list without
readily available invoice price information. 
Procedures should be amended for
maintaining the School's Inventory List to
reflect the requirements of the current iteration
of the Council's Financial Regulations and to
ensure that cost or estimated replacement
value is recorded against each item.
Management Response
Responsible Officer Accepted (Yes/ No) Timescale for
Implementation
(Date Required)
Agreed Management
Action/Management Comment
Head Teacher Yes 01/09/2025 The current inventory is to be updated and
amended as per the Council's Regulations. 
Page 92

Page 93

6
Ref Risk Ratings for
Recommendations
Audit Finding Audit Recommendation
2 Low The audit visit noted that Supermarket vouchers
totalling £1,000 were held in a secure location at the
School. Enquiries revealed that these vouchers had
been purchased by the School from the Pupil Equity
Fund in 2023, with the intention of providing them to
families of pupils in financial need. However, this
had been done during a period of absence by the
Head Teacher, and to date, none of the vouchers
have been issued since the purchase, nor have any
criteria for issuing them been developed. Options for
the future use of the vouchers were discussed with
the Head Teacher, but it was noted that no decision
had been reached at the time of the audit.
Consideration should be given to the best use
of the vouchers held, in accordance with the
Pupil Equity Fund National Operational
Guidance.
Management Response
Responsible Officer Accepted (Yes/ No) Timescale for
Implementation
(Date Required)
Agreed Management
Action/Management Comment
Head Teacher Yes 01/10/2025 The vouchers will be used to support sessions at a
charitable youth project which supports families in
the local area. Cooking sessions are attended by
pupils disengaging from school, offering life skills
and building on engagement. Additionally, a
Summer Supper Club is run which provides a meal
for families who may be struggling during the
holiday period, fitting the aims of Pupil Equity
Funding.   
Page 93

Page 94

7
Ref Risk Ratings for
Recommendations
Audit Finding Audit Recommendation
3 Low It was noted that the current petty cash imprest level
for the School is £300. On analysis of expenditure
and discussion with officers at the School, it was
noted that this limit is no longer required and that a
lower level of petty cash would be appropriate for the
School's day-to-day needs. The ongoing use of
petty cash was queried with the School but is still
required for the purchase of minor reimbursements
and ad hoc purchases.  
Consideration should be given to reducing the
level of petty cash held by the School.
Management Response
Responsible Officer Accepted (Yes/ No) Timescale for
Implementation
(Date Required)
Agreed Management
Action/Management Comment
School Support Co-ordinator Yes 01/04/2025 The Petty Cash Fund has been reduced to
£50. 
Page 94

Page 95

8
Ref Risk Ratings for
Recommendations
Audit Finding Audit Recommendation
4 Medium An Annual Income and Expenditure Statement must
be prepared and audited in accordance with the
School Fund Regulations. Upon reviewing the
School's Income and Expenditure Statement, it was
found to contain only three income and expenditure
categories: School Fund, School Prizes and
Holding. While the School does hold supporting
evidence detailing the breakdown of the activities
and clubs that contribute to these categories, the
lack of detail in the Annual Statement prevents
readers from understanding the activities
undertaken using the School Fund.   
The School Fund Annual Income and
Expenditure statement should be expanded to
give improved transparency of the significant
activities during the previous year.    
Management Response
Responsible Officer Accepted (Yes/ No) Timescale for
Implementation
(Date Required)
Agreed Management
Action/Management Comment
School Support Co-ordinator Yes 01/09/2025 A more comprehensive report will be produced
at the end of the School Fund financial year to
reflect School Fund activities. 
Page 95

Page 96

9
Ref Risk Ratings for
Recommendations
Audit Finding Audit Recommendation
5 Medium iPayimpact is an online payment system used by
schools to accept online payments from parents and
carers for school related expenses such as school
clubs, trips, and the purchase of tickets for school
events. iPayimpact reduces the inherent control
risks associated with cash handling within an
establishment. Although a trial use of  iPayimpact
has been undertaken for one activity at Keith
Grammar School, no further use has been made of
the system. The current cash handling and banking
arrangements at the School are manually intensive.
Further use of the iPayimpact system would allow
for more efficient use of staff time within the School.
Consideration should be given to the further
use of the iPayimpact system at the School for
the collection and banking of income. 
Management Response
Responsible Officer Accepted (Yes/ No) Timescale for
Implementation
(Date Required)
Agreed Management
Action/Management Comment
School Support Co-ordinator Yes 01/12/2025 Ongoing training for office staff to be
scheduled over the next few months to enable
a robust transition from cash to iPayimpact.
Page 96

Page 97

10
Ref Risk Ratings for
Recommendations
Audit Finding Audit Recommendation
6 Medium The School Fund bank account has only two
authorised signatories, both of whom are required to
sign a cheque for payments made from the account.
During the audit visit, it was discovered that one of
the signatories had pre-signed blank School Fund
cheques. Enquiries revealed that a signatory, who
was on extended leave, had pre-signed cheques to
ensure the ongoing administration of the School
Fund. Unfortunately, it was also found that the
School has been unable to add additional
signatories to the account, as this requires both
existing signatories to engage with the bank to
approve the action. The School Fund Regulations
state that blank cheques must not be signed in
advance.  
The individual circumstances surrounding the
need for cheques to be pre-signed for the
School Fund in this instance are appreciated.
However, in accordance with the School Fund
Regulations, cheques must not be pre-signed.
Discussions with the School have noted an
intention to change the current banking facility.
Management Response
Responsible Officer Accepted (Yes/ No) Timescale for
Implementation
(Date Required)
Agreed Management
Action/Management Comment
School Support Co-ordinator Yes 01/09/2025 New accounts with additional signatories will
be opened as soon as possible. 
Page 97

Page 98

11
Appendix 1
AUDIT TERMS OF REFERENCE AND DEFINITIONS
1. Audit Objectives
1.1 The overall audit objective is to provide an objective independent opinion on
the adequacy and effectiveness of controls / processes.
1.2 The audit will for each controls / process being considered:
• Walkthrough the processes to consider the key controls;
• Conduct sample testing of the identified key controls, and
• Report on these accordingly
1.3 All audit reviews are carried out in accordance with Public Sector Internal
Audit Standards (PSIAS).
2. Definitions for Auditing Opinions and Findings
2.1 In order to assist management in using our reports:
The Internal Auditor will categorise audit assurance opinion according to
their overall assessment of the risk management system, effectiveness of the
controls in place and the level of compliance with these controls and the action
being taken to remedy significant findings or weaknesses.
Assurance
Level
System and Testing Conclusion
Full The controls tested are being consistently applied
Substantial There is evidence that the level of non compliance with some of the
controls may put some of the system objectives at risk.
Limited The level of non compliance puts the system objectives at risk.
None Significant non-compliance with basic controls leaves the system
open to error or abuse. 
2.2 Risk ratings for each recommendation is based on the following criteria:
High Fundamental control weaknesses that require immediate attention by
management to action and mitigate significant exposure to risk
Medium Less critically important controls absent, not being operated as
designed or could be improved
Low Lower level controls absent, not being operated as designed or could
be improved.
Page 98

Page 99

12 
Appendix 2 
STATEMENT OF RESPONSIBILITY   
The responsibility for designing and maintaining a sound system of internal control to
prevent and detect fraud and other irregularities rests with management, with internal
audit providing a service to management to support them to achieve this objective.
The Internal Audit Section will assess the adequacy and effectiveness of the system
of internal control arrangements implemented by management and perform sample
testing on those controls in the period under review with a view to providing an opinion
on the extent to which risks in this area are managed. 
The Internal Audit Section will undertake testing with the objective of detecting
significant control weaknesses. However, the audit approach alone should not be
relied upon to identify all strengths and weaknesses in internal controls nor to find any
fraud or irregularity. Even sound systems of internal control can only provide
reasonable and not absolute assurance and may not be proof against collusive fraud. 
The matters raised in this report are only those that came to our attention during the
course of the audit review and are not necessarily a comprehensive statement of all
the weaknesses that exist or all improvements that might be made. Recommendations
for improvements should be assessed by management for their full impact before they
are implemented. The performance of the audit review undertaken should not be taken
as a substitute for management’s responsibilities for the application of sound
management practices. 
This report must not be disclosed to any third party or reproduced in whole or in part
without the written consent of the Moray Council’s Audit and Risk Manager. 
Page 99

Page 100

Page 100

Page 101

Report to: Audit and Scrutiny
Committee
Meeting Date: 24 June 2025     
Report by: Audit and Risk
Manager
Report No: GSP026/25/DL  
Author: Dafydd Lewis Contact
Email:
dafydd.lewis@moray.gov.uk 
Subject:  Internal Audit Review - Information Communications Technology 
Hardware Assets 
1. PURPOSE 
☒ For Decision      ☐  For Information 
1.1 The report advises Committee on an internal audit review completed for the               period
from 7 May 2025 to 24 June 2025. 
1.2 This report is submitted to Committee in terms of Section III (I) (2) and (8) of the 
Council’s Scheme of Administration relating to consideration of reports from the
Council’s Internal Auditor and monitoring delivery of the audit service through receipt of
quarterly reports on work carried out by Internal Audit. 
2. SUMMARY  
2.1 This report provides details of the internal audit review of systems and procedures in
the management of Information Communications Technology (ICT) Hardware Assets;
this project has been agreed for review within the Internal Audit Plan for 2024/25. 
3. RECOMMENDATIONS  
3.1 It is recommended that Committee:   
i) Considers the contents of this report, seeks clarification on any points
noted, and endorses the recommendations contained within the report.   
Dafydd Lewis
Audit and Risk Manager 
4. BACKGROUND AND CONTEXT  
Item 10.
Page 101

Page 102

4.1 An audit review was undertaken of the systems and procedures involved in managing
the ICT hardware assets within the Council. Hardware asset management refers to the
process of inventorying and tracking physical ICT equipment, such as servers, laptops,
drives, routers, and monitors throughout their entire lifecycles. The scope of the audit
was to review the systems and policies used for the management, recording, and
disposal of ICT hardware equipment. Testing included selecting a random sample of
ICT hardware recorded in the Inventory Register and verifying its physical location. The
audit also assessed the physical controls in place to safeguard and restrict access to
ICT hardware.  
4.2  The findings from the audit included the need to review and update the Corporate
Information Security Policy, as well as to consider improvements in the access,
location, and storage of hardware equipment. The audit report in Appendix 1 details
the findings and recommendations from the review. 
5. PROPOSALS  
5.1 This report provides Committee with a summary of findings arising from an audit project
completed during the review period. 
6. SUMMARY OF IMPLICATIONS  
6.1 The table below shows whether risks and implications apply if the recommendations
are agreed: 
SUBJECT YES NO
Corporate Plan and 10 Year Plan (Local Outcome Improvement
Plan) 
×
Policy and Legal  ×
Financial  ×
Risk × 
Staffing  ×
Best Value and Transformation × 
Property  ×
Information Communications Technology/Digital             ×
Equalities. Social Inclusion and Economic Impact   ×
Climate Change, Biodiversity and Sustainability  × 
6.2 Corporate Plan and 10 Year Plan (Local Outcomes Improvement Plan (LOIP))
Improved Collaborative Leadership, as part of continuous improvement through Best
Value, will better enable the Council to fulfil the ambitions set out in its strategic plans. 
a) Links to Council Corporate Plan – The proposals in this report support and
contribute to improved outcomes for communities as outlined in the following
Council Plan strategic priorities:
☐ Tackle Poverty and Inequality.
☐ Build Stronger Greener Vibrant Economy.
☐ Build Thriving, resilient, empowered Communities.   
b) Links to Local Outcomes Improvement Plan – The proposals in this report support
and contribute to improved outcomes for communities as outlined in the following
local Outcomes Improvement Plan priorities:
☐ Developing a diverse, inclusive, and sustainable economy
Page 102

Page 103

☐ Building a better future for our children and young people in   Moray.
☐ Empowering and connecting communities.
☐ Improving wellbeing of our population   
6.3 Policy and Legal  
No implications directly arising from this report.  
6.4 Financial  
No implications directly arising from this report. 
One off Costs:
Service
Area
Budget Budget
Years
Proposed
Spend
this Year
Virement
From
Other
Comments       
Annually Recurring Costs:
Service
Area
Budget With
Effect
From
Annual
Net
Impact
Virement
From (if
applicable)
Other
Comments       
6.5 Risk 
The independent review of selected systems and procedures mitigates  the risks
associated with inadequate or ineffective control procedures.  
6.6 Staffing 
No implications directly arising from this report.  
6.7 Best Value and Transformation 
Internal audit work supports good governance and the delivery of efficient services.  
6.8 Property 
No implications directly arising from this report.  
6.9 Information Communications/Technology/Digital 
No implications directly arising from this report.  
6.10 Equalities, Social Inclusion and Economic Impact 
No implications directly arising from this report.  
6.11 Climate Change and Biodiversity Impacts 
No implications directly arising from this report. 
7. CONSULTATION  
7.1 There have been no direct consultations during the preparation of this  report. 
8. BACKGROUND PAPERS  
8.1 None   
Page 103

Page 104

1
Final Internal Audit Report
Information Communications Technology
(ICT) Hardware Assets 
May 2025
Distribution: Head of Human Resources, ICT & Organisational Development
ICT Manager (Infrastructure)
The Internal Audit Section provides Management with an opinion on the internal control environment
and also categories risk ratings for recommendations as high, medium or low (detailed explanation
provided in Appendix1). The audit recommendations for this review have been classified as follows
Assurance Level Risk Ratings for
Recommendations
Substantial
Priority 1 1
Priority 2 3
Priority 3 1
Confidentiality and Disclosure Clause
This report (“Report”) was prepared by the Internal Audit Section of Moray Council. The matters raised in this Report are only
those which came to our attention during our internal audit work. Whilst every care has been taken to ensure that the information
provided in this Report is as accurate as possible, the Moray Council Internal Audit Section has only been able to base findings
on the information and documentation provided and consequently, no complete guarantee can be given that this Report is
necessarily a comprehensive statement of all the weaknesses that exist, or of all the improvements that may be required.
This Report was prepared solely for the use and benefit of the Moray Council, Moray Integration Joint Board or the Grampian
Valuation Joint Board. Moray Council's Internal Audit Section accepts no responsibility and disclaims all liability to any third party
who purports to use or rely for any reason whatsoever on the Report, its contents, conclusions, any extract, reinterpretation,
amendment and/or modification. Accordingly, any reliance placed on the Report, its contents, conclusions, any extract,
reinterpretation, amendment and/or modification by any third party is entirely at their own risk.
Please refer to the Statement of Responsibility in Appendix 2 of this report for further information about responsibilities,
limitations and confidentiality.
APPENDIX 1
Page 104

Page 105

2 
Contents 
Page 
Information Communications Technology (ICT) Hardware
Assets 
1. Introduction & Scope 3
2. Key Issues  3-4 
Detailed Report 
3. Findings/Recommendations 5-13
4. Management Response 6-14 
Appendices 
1. Audit Terms of Reference and Definitions 
2. Statement of Responsibility 
Page 105

Page 106

3 
1. Introduction and Audit Scope 
The Audit Plan for 2024/25 provides for a review of systems and practices to
record and monitor the location and use of Information Communications
Technology (ICT) hardware assets. Hardware assets are physical and tangible
pieces of computer equipment. The most common type of hardware
equipment are servers, desktop/laptop computers and monitors. Since this
equipment is a key requirement in the delivery of services, managing and
organising it effectively is essential. This audit considered corporate ICT assets. 
School assets will be considered for review at a future date. 
Analysis of the Financial Management System noted that expenditure for ICT
hardware equipment in 2022/23 amounted to approximately £0.5 million and
£236,000 in 2023/24.  At the time of the audit, the Council had approximately
4,500 individual, corporate ICT hardware items, including 300 desktop
computers, 1,500 laptops and 100 servers. A reason for the significant variance
in annual expenditure is due to the laptop replacement programme. Since the
pandemic, significant changes have occurred with the introduction of the Smarter
Working Initiative, resulting in an increase in the number of Council employees
working from home and a greater demand for laptops. It is essential that all ICT
hardware equipment are tracked and managed appropriately to avoid
unnecessary purchases, promote the efficient use of existing resources, and
ensure Council data is protected. 
The scope of the audit was to review the systems and policies used for the
management, recording, and disposal of ICT hardware equipment. Testing
included selecting a random sample of ICT hardware equipment recorded in the
Inventory Register and verifying its physical location. A review was conducted on
the processes involved in recovering hardware equipment from officers leaving
Council employment. The audit also assessed the physical controls to safeguard
and restrict access to Council servers and network equipment located in various
locations within Council buildings.  
The audit was carried out in accordance with Public Sector Internal Audit
Standards (PSIAS). 
2. Key Issues 
• The Corporate Information Security Policy details the Council’s
requirements for appropriate control mechanisms to prevent
unauthorised access, damage and/or interference to the Council's ICT
infrastructure and systems, including all physical ICT assets that support
critical or sensitive activities. However, it was found that the Policy was
last reviewed and updated in January 2009. It is important that the
Corporate Information Security Policy is regularly updated in response
Page 106

Page 107

4 
to business needs and evolving threats. Discussions with the ICT
Service noted that the Policy has been reviewed, and an updated
version is near completion. 
• The audit review noted various security concerns regarding the location
and storage arrangements for ICT hardware equipment. The challenges
faced by the ICT Service regarding the availability of suitable storage
locations are appreciated. However, in accordance with the Corporate
Information Security Policy there is a requirement for ICT equipment to
be stored and protected to reduce the risks associated with
environmental hazards and opportunities for unauthorised access.
Consideration should be given to investigating the availability of any
alternative storage facilities for ICT hardware equipment or whether
additional security controls are required to safeguard against
unauthorised access. 
Page 107

Page 108

5 
Findings/Recommendations - Information Communications Technology (ICT) Hardware Assets 
Ref Risk Ratings for
Recommendations
Audit Finding Audit Recommendation
1 High The Council’s  Corporate Information Security
Policy establishes the appropriate control
mechanisms “to prevent unauthorised access,
damage and/or interference to the Council's ICT
infrastructure and systems, including all
physical ICT assets that support critical or
sensitive departmental activities”. However, as
previously detailed in other audit reviews, it was
found that the Policy was last reviewed in
January 2009.  The Policy should be reviewed
and, if required, updated to ensure control
requirements remain relevant or be further
strengthened in meeting the Council’s ICT
security management requirements. It is
understood from discussions with the Service
that work is currently being undertaken to
review and update the Policy.   
It is acknowledged that a review and, if
required, updating of the Corporate
Information Security Policy is underway.
However, this should now be progressed,
and in the future, the Policy should be
subject to periodic reviews to ensure its
effectiveness, cost, and impact of controls
on business efficiency, as well as the
effects of technology changes. 
Page 108

Page 109

6 
Management Response
Responsible Officer Accepted (Yes/ No) Timescale for
Implementation
(Date Required)
Agreed Management
Action/Management Comment
ICT Team Leader
(Infrastructure & Information
Security) 
Yes 31/03/2026 Progress on finalising the Policy has been
hindered due to a lack of dedicated resources
for cyber security, as well as operational
pressures taking precedence.  The approval of
funding for additional resources will provide
the capacity to complete the work. 
Proposed timescale allows for completion of
the Policy and appropriate governance for
approval / adoption of the new Policy. 
Page 109

Page 110

7 
Ref Risk Ratings for
Recommendations
Audit Finding Audit Recommendation
2 Medium The  Data Centre is a physical room within the
Headquarters complex where
networked computer servers are located for the
remote storage, processing, or distribution of
large amounts of data. These servers contain
the Council’s critical applications and data and
are therefore essential to ensure the ongoing
delivery of services. Access to the Data Centre
is controlled through a door entry system that
records activity over a 24-hour period, with entry
only allowed to the appropriate ICT officers but
also to Facilities and Property Services officers
for defined purposes. However, external
contractors also require access to the Data
Centre for the maintenance of equipment to
ensure appropriate climatic conditions. 
During the audit review, a visit was made to the
Data Centre to check the security
arrangements. It was noted that the servers are
stored in racks, and while this storage facility
has the option to further restrict access to the
servers, it is not being utilised. 
Consideration should be given to utilising
locks on server racks within the Data
Centre to further enhance the security of
the servers. 
Page 110

Page 111

8 
Management Response
Responsible Officer Accepted (Yes/ No) Timescale for
Implementation
(Date Required)
Agreed Management
Action/Management Comment
ICT Infrastructure
Manager
Yes 19/12/2025 It should be noted that external contractors
who undertake work related to the ICT
infrastructure within the Data Centre are
always accompanied by a member of the ICT
Team.   However, it is appreciated that other
contractors also require access to this area. 
It should also be noted that there are some
racks where the physical dimensions of the
equipment therein, prevent the doors on the
rack from being closed. In relation to access,
this means that someone could potentially
cause physical damage to a server, as
opposed to accessing systems / data. 
In line with the audit recommendation, the  ICT
Team will consider options to mitigate the risk
wherever possible. 
Page 111

Page 112

9 
Ref Risk Ratings for
Recommendations
Audit Finding Audit Recommendation
3 Low ICT Services maintain a computer-based ICT
Inventory Register. This Register should include
all major items of ICT hardware, such as
servers, desktop computers, and laptops. The
audit selected a random sample of laptops
recorded in the Inventory Register, and a check
was made to verify their physical locations. It is
pleasing to report that no discrepancies were
noted. However, examples were found where
certain hardware, including servers and network
equipment were not located in the most secure
areas to reduce the risk of potential
unauthorised access. The challenges and
limitations regarding available and suitable
spaces within Council buildings for locating ICT
hardware are acknowledged. However, as an
example, the audit review noted a network
switch located in an unlocked small room within
an unused office. 
A risk assessment review should be
undertaken of all ICT hardware located
within the various locations of Council
buildings and consideration given to
whether additional security controls are
required to safeguard against
unauthorised access. 
Page 112

Page 113

10 
Management Response
Responsible Officer Accepted (Yes/ No) Timescale for
Implementation
(Date Required)
Agreed Management
Action/Management Comment
ICT Infrastructure Manager  Yes 31/03/26 It is acknowledged that the level of security
varies across Council locations.  In newer
locations where security has been considered
as part of the design, access to ICT hub rooms
is strictly controlled via the Door Entry system.
In other locations, due to practicalities arising
over time, there are examples of shared
facilities e.g. ICT network hub shared with a
printing hub. 
Given the need to rationalise the property
estate, there may be limitations on what can be
achieved.  However, it is accepted that a risk
assessment should be carried out in line with
the audit recommendation. 
Page 113

Page 114

11 
Ref Risk Ratings for
Recommendations
Audit Finding Audit Recommendation
4 Medium It was noted that the main ICT office serves as
a storage area for new laptops, as well as those
designated for refresh or disposal. The audit
observed that, when the office is unoccupied,
the entry door should remain closed, with
access restricted through a keypad entry
system.  However, the main ICT office serves
as the primary workplace for the ICT officers,
and access is also required by other Council
officers. The challenges faced by the ICT
Service regarding the availability of secure
storage facilities and the need to meet
operational service requirements are again
appreciated. 
Consideration should  be given to the 
current use of the main ICT office to store
hardware equipment and whether a more
secure location is available. 
Management Response
Responsible Officer Accepted (Yes/ No) Timescale for
Implementation
(Date Required)
Agreed Management
Action/Management Comment
ICT Infrastructure Manager /
ICT Team Leader (Support) 
Yes 31/10/25 The ICT Section has occupied various
temporary storage locations over time,
culminating in the allocation of the main ICT
office space, when no suitable alternative
storage location could be found.  This
arrangement is not ideal.  However, it does
Page 114

Page 115

12 
have benefits from a service efficiency
perspective, as it minimises ICT Officer travel
time in relation to the configuration of the
equipment. 
The office is always manned during normal
working hours which reduces any associated
risks.  Enquiries will be made into the
availability of suitable, alternative storage
solutions. 
Page 115

Page 116

13 
Ref Risk Ratings for
Recommendations
Audit Finding Audit Recommendation
5 Medium Council officers are required to comply and
regularly confirm adherence with the Computer
Use Policy. However, the audit review noted
that within the Moray Integration Joint Board
(MIJB), approximately 13 NHS Grampian
employed officers also use Council hardware
equipment and software in the delivery of
services. However, there is no agreement with
NHS Grampian employed officers to confirm
their requirement to comply with Council
Policies, which may differ from working
procedures within the NHS. This could result in
different compliance requirements between
NHS Grampian and Moray Council employed
officers in the delivery of  MIJB delegated
services. 
Consideration should be given by the
Chief Officer of the MIJB to request all
NHS Grampian employed officers that use
Council owned hardware and software to
comply with the appropriate Computer and
Information Management Policies of the
Council. 
Management Response
Responsible Officer Accepted (Yes/ No) Timescale for
Implementation
(Date Required)
Agreed Management
Action/Management Comment
Chief Officer (MIJB) / ICT
Infrastructure Manager
Yes 31/10/2025 Although there is no agreement in place, the
NHS Grampian employed officers will be
aware of the Computer Use Policy in the sense
that they will also be prompted to confirm
Page 116

Page 117

14 
adherence as part of the login process on their
Council equipment.  The offices also have
access to the Interchange (the Council’s
Intranet), which is the repository for the policy,
albeit they may not necessarily be aware of
this. 
However, agreement will be sought with NHS
employed officers with access to Council
systems to confirm compliance with the
Computer Use Policy.
.
Page 117

Page 118

15 
Appendix 1 
AUDIT TERMS OF REFERENCE AND DEFINITIONS 
1. Audit Objectives 
1.1 The overall audit objective is to provide an objective independent opinion on
the adequacy and effectiveness of controls / processes.  
1.2 The audit will for each controls / process being considered: 
• Walkthrough the processes to consider the key controls; 
• Conduct sample testing of the identified key controls, and 
• Report on these accordingly 
1.3 All audit reviews are carried out in accordance with Public Sector Internal
Audit Standards (PSIAS). 
2. Definitions for Auditing Opinions and Findings 
2.1 In order to assist management in using our reports: 
The Internal Auditor will categorise audit assurance opinion according to
their overall assessment of the risk management system, effectiveness of the
controls in place and the level of compliance with these controls and the action
being taken to remedy significant findings or weaknesses. 
Assurance
Level
System and Testing Conclusion
Full The controls tested are being consistently applied
Substantial There is evidence that the level of non compliance with some of the
controls may put some of the system objectives at risk.
Limited The level of non compliance puts the system objectives at risk.
None Significant non-compliance with basic controls leaves the system
open to error or abuse. 
2.2 Risk ratings for each recommendation is based on the following criteria: 
High Fundamental control weaknesses that require immediate attention by
management to action and mitigate significant exposure to risk
Medium Less critically important controls absent, not being operated as
designed or could be improved
Low Lower level controls absent, not being operated as designed or could
be improved.
Page 118

Page 119

16 
Appendix 2 
STATEMENT OF RESPONSIBILITY   
The responsibility for designing and maintaining a sound system of internal control to
prevent and detect fraud and other irregularities rests with management, with internal
audit providing a service to management to support them to achieve this objective.
The Internal Audit Section will assess the adequacy and effectiveness of the system
of internal control arrangements implemented by management and perform sample
testing on those controls in the period under review with a view to providing an opinion
on the extent to which risks in this area are managed. 
The Internal Audit Section will undertake testing with the objective of detecting
significant control weaknesses. However, the audit approach alone should not be
relied upon to identify all strengths and weaknesses in internal controls nor to find any
fraud or irregularity. Even sound systems of internal control can only provide
reasonable and not absolute assurance and may not be proof against collusive fraud. 
The matters raised in this report are only those that came to our attention during the
course of the audit review and are not necessarily a comprehensive statement of all
the weaknesses that exist or all improvements that might be made. Recommendations
for improvements should be assessed by management for their full impact before they
are implemented. The performance of the audit review undertaken should not be taken
as a substitute for management’s responsibilities for the application of sound
management practices. 
This report must not be disclosed to any third party or reproduced in whole or in part
without the written consent of the Moray Council’s Audit and Risk Manager. 
Page 119

Page 120

Page 120

Page 121

Report to: Meeting Date:Audit and Scrutiny
Committee
24 June 2025   
Report by: Report No:Audit and Risk
Manager
GSP028/25/DL
Author: Dafydd Lewis Contact
Email:
dafydd.lewis@moray.gov.uk
Subject: Audit & Scrutiny Committee Self-Assessment & Evaluation
Exercises
1. PURPOSE
☒ For Decision      ☐  For Information
1.1 The purpose of this report is to advise Committee on the outcome of a self assessment
of Compliance with the Good Practice Principles Checklist and Evaluation of
Effectiveness Toolkit undertaken from the Chartered Institute of Public Finance and
Accountancy (CIPFA) Publication “Audit Committees: Practical Guidance for Local
Authorities and Police 2022 Edition”.
1.2 This report is submitted to Committee in terms of Section III I (2) and (7) of the
Council’s Scheme of Administration relating to consideration of reports from the
Council’s Internal Auditor and monitoring delivery of the audit service carried out by
Internal Audit.
2. SUMMARY
2.1 This report provides the results a Self-Assessment of Good Practice and an Evaluation
of Effectiveness from the CIPFA Publication – Audit Committees: Practical Guidance
for Local Authorities and Police 2022 Edition undertaken with members of the Audit and
Scrutiny Committee.  This CIPFA Publication sets out its guidance on the function and
operation of audit committees in local authorities and police bodies and represents
CIPFA’s view of best practices for audit committees in local authorities throughout the
UK.
3. RECOMMENDATIONS
3.1 It is recommended that Committee:
i) Considers the contents of this report, seeks clarification on any points
noted, and endorses the recommendations contained within the report.
Dafydd Lewis
Audit and Risk Manager
4. BACKGROUND AND CONTEXT
Item 11.
Page 121

Page 122

4.1 The CIPFA Publication “Audit Committees:  Practical Guidance for Local Authorities
and Police 2022 Edition” sets out its guidance on the function and operation of audit
committees in local authorities and police bodies. Audit committees are a key
component of an authority’s governance framework and provide an independent and
high-level resource to support governance and strong public financial management.
The guidance states the purpose of an audit committee is “to provide an independent
and high-level focus on the adequacy of governance, risk and control arrangements.
The committee’s role in ensuring that there is sufficient assurance over governance risk
and control gives greater confidence to all those charged with governance that those
arrangements are effective.”
4.2 CIPFA promotes that a good standard of performance against recommended practices,
together with a knowledgeable and experienced membership, are essential
requirements for delivering effectiveness. To this effect, CIPFA has provided a high-
level review checklist that incorporates the key principles set out in CIPFA’s Position
Statement: Audit Committees in Local Authorities and Police 2022 Edition. In addition,
the Public Sector Internal Audit Standards also call for the committee to assess their
remit and effectiveness in relation to purpose, authority and responsibility to facilitate
the work of this committee.
4.3 Members from the Audit and Scrutiny Committee carried out self-assessments of
Compliance with the Good Practice Principles Checklist and Evaluation of
Effectiveness Toolkit from the CIPFA Audit Committees Guidance during a workshop
session on 25 March 2025 facilitated by the Audit and Risk Manager. The results of
these self-assessment and evaluation exercises are appended to this report as
Appendix 1 (Good Practice Principles) and Appendix 2 (Effectiveness) for
consideration.
4.4 The outcome of the self-assessment and evaluation noted significant compliance with
good practice principles and a high degree of effectiveness. However, areas have been
identified for further improvements. An Action Plan has been produced as Appendix 3
to strengthen and improve the overall effectiveness of the Audit and Scrutiny
Committee.
5. PROPOSALS
5.1 This report provides the Committee with details of the self-assessment of Compliance
with the Good Practice Principles Checklist and Evaluation of Effectiveness Toolkit
undertaken from the CIPFA Publication  “Audit Committees: “Practical Guidance for
Local Authorities and Police 2022 Edition”.
6. SUMMARY OF IMPLICATIONS
6.1 The table below shows whether risks and implications apply if the recommendations
are agreed:
SUBJECT YES NO
Corporate Plan and 10 Year Plan (Local Outcome Improvement
Plan)
×
Policy and Legal ×
Financial ×
Risk ×
Staffing ×
Page 122

Page 123

Best Value and Transformation ×
Property ×
Information Communications Technology/Digital           ×
Equalities. Social Inclusion and Economic Impact ×
Climate Change, Biodiversity and Sustainability ×
6.2 Corporate Plan and 10 Year Plan (Local Outcomes Improvement Plan (LOIP))
Improved Collaborative Leadership, as part of continuous improvement through Best
Value, will better enable the Council to fulfil the ambitions set out in its strategic plans.
a) Links to Council Corporate Plan – The proposals in this report support and
contribute to improved outcomes for communities as outlined in the following
Council Plan strategic priorities:
☐ Tackle Poverty and Inequality.
☐ Build Stronger Greener Vibrant Economy.
☐ Build Thriving, resilient, empowered Communities.
b) Links to Local Outcomes Improvement Plan – The proposals in this report support
and contribute to improved outcomes for communities as outlined in the following
local Outcomes Improvement Plan priorities:
☐ Developing a diverse, inclusive, and sustainable economy
☐ Building a better future for our children and young people in   Moray.
☐ Empowering and connecting communities.
☐ Improving wellbeing of our population
6.3 Policy and Legal
No implications directly arising from this report.
6.4 Financial
No implications directly arising from this report.
One off Costs:
Service
Area
Budget Budget
Years
Proposed
Spend
this Year
Virement
From
Other
Comment
s
Annually Recurring Costs:
Service
Area
Budget With
Effect
From
Annual
Net
Impact
Virement
From (if
applicable
)
Other
Comment
s
6.5 Risk
The independent review of selected systems and procedures mitigates  the risks
associated with inadequate or ineffective control procedures.
6.6 Staffing
No implications directly arising from this report.
6.7 Best Value and Transformation
Internal audit work supports good governance and the delivery of efficient services.
Page 123

Page 124

6.8 Property
No implications directly arising from this report.
6.9 Information Communications/Technology/Digital
No implications directly arising from this report.
6.10 Equalities, Social Inclusion and Economic Impact
No implications directly arising from this report.
6.11 Climate Change and Biodiversity Impacts
No implications directly arising from this report.
7. CONSULTATION
7.1 The Chief Executive and the Head of Governance, Strategy & Performance have
been consulted on the contents of this report.
8. BACKGROUND PAPERS
8.1 None
Page 124

Page 125

APPENDIX 1
CIPFA
Audit
Committees
Practical Guidance for Local Authorities and Police 2022 Edition
Self-Assessment of Effectiveness of the Audit & Scrutiny Committee
Ref. Good practice questions Yes Partly No Audit Review
Audit committee purpose and governance
1 Does the authority have a
dedicated audit committee that
is not combined with other
functions (eg standards, ethics,
scrutiny)?
P The Council has an Audit and Scrutiny Committee. Responsibility
for scrutiny lies with the Service Committees, but the Audit and
Scrutiny Committee has the authority to seek further service reviews
if required. Discussions during the workshop considered a need to
develop further the scrutiny function of the Audit and Scrutiny
Committee.
2 Does the audit committee report
directly to full council?
Y Yes- The Council has delegated functions to the Audit and Scrutiny
Committee.
3 Has the committee maintained
its advisory role by not taking on
any decision-making powers?
Y Audit and Scrutiny Committee has no decision making powers
4 Do the terms of reference
clearly set out the purpose of
the committee in accordance
with CIPFA’s 2022 Position
Statement?
Y Audit and Scrutiny functions are detailed within the Scheme of
Administration. Functions of the Committee updated (Moray Council
Committee – 7/12/2022- Item 15) to reflect the current CIPFA
Position Statement. A planned review and update of the Scheme of
Administration is planned shortly.
Page 125

Page 126

5 Do all those charged with
governance and in leadership
roles have a good
understanding of the role and
purpose of the committee?
Y Yes- Scheme of Administration details the purpose of the Audit and
Scrutiny Committee to ensure that the highest standards of probity
and public accountability.
Summary of Audit and Scrutiny Committee functions: Audit
Functions - Consider reports from the Council's internal auditor &
Audit Scotland concerning Council Functions. Scrutiny Functions -
Scrutinising the policies of the Council and their effectiveness in
meeting the action plans of the Council as set out in the Corporate
Development Plan and evaluating the actions of Committees in
implementing the action plans set out in the Corporate Development
Plan. Performance Monitoring - To receive reports on the
performance of and trends within all of the Council’s services in
terms of service standards and performance information. Standards
- To ensure that the highest standards of probity and public
accountability are demonstrated.
6 Does the audit committee
escalate issues and concerns
promptly to those in governance
and leadership roles?
P The Audit and Scrutiny Committee is a key part of the Council’s
governance framework. This Committee is a critical component in
the overall corporate governance arrangements of the Council,
where good corporate governance requires independent and
effective assurance about the adequacy of financial management
and reporting. These functions are delivered independently from the
scrutiny functions of the Corporate Management Team.
The Committee can scrutinise areas of policy, service delivery or
performance identified for improvement where sufficient evidence of
progress from the appropriate committee is not available. Any
issues of concern can be raised with the Council's senior
management. This has recently been evidenced by members
raising concerns regarding timescales for implementing audit
recommendations where services have been asked to review
implementation dates.
Page 126

Page 127

However, as detailed within point 1 of this self-assessment exercise,
concerns were discussed regarding the lack of the scrutiny function
of this Committee. It is considered that a review of the Scheme of
Administration should be undertaken to allow further scrutiny by
members of any issue of concern where further review is required.
7 Does the governing body hold
the audit committee to account
for its performance at least
annually?
P Moray Council has 26 councillors. Membership of the Audit and
Scrutiny Committee has 15 councillors and 2 independent (non-
voting) members. As the majority of councillors are already
members of the Audit and Scrutiny Committee, performance is
monitored on an ongoing basis.    
8 Does the committee publish an
annual report in accordance
with the 2022 guidance,
including:
N An annual review is not undertaken. It was discussed that a yearly
report is not a priority as most members are already members of the
Audit and Scrutiny Committee. All members have access to audit
reports and can raise any query or seek further clarification directly
with the Audit and Risk Manager.
• compliance with the CIPFA
Position Statement 2022
N
• results of the annual
evaluation, development work
undertaken and planned
improvements
N
• how it has fulfilled its terms of
reference and the key issues
escalated in the year?
N
Functions of the committee
9 Do the committee’s terms of
reference explicitly address all
the core areas identified in
CIPFA’s Position Statement?
Page 127

Page 128

 good governance
Y Standards of the committee are to ensure that the highest standards
of probity and public accountability are demonstrated.
Reference was made to supporting the Council’s governance, risk
and control arrangements by providing a review of the Annual
Governance Statement and the assurances underpinning it. (I5) In
addition, functions also include considering the annual assurance
statement provided by Internal Audit on the Council’s control
environment (I10
 Risk management
arrangements
Y Supporting the Council’s governance, risk and control arrangements
by considering the effectiveness of the Council’s risk management
arrangements. (I5)
 Internal control
arrangements, including:
 financial management
 value for money
 ethics and standards
 counter fraud and
corruption
P Standards of the committee detail a requirement to ensure that the
highest standards of probity and public accountability are
demonstrated. (Audit Standards (1))
Supporting the Council’s governance, risk and control arrangements
by promoting internal controls and assurances, supporting an anti-
fraud culture, review of revisions to financial procedures. (I5) No
clear reference is made to value for money but implied with
functions of the committee.
Annual governance statement Y Functions detail supporting the Council’s governance, risk and
control arrangements by providing a review of the Annual Council
Statement and the assurances underpinning it. (I5)
Financial reporting Y Enhancing corporate governance arrangements by promoting
internal control and risk management, by supporting an anti-fraud
culture, and by the review of revisions to financial procedures (I5),
Reference also noted to reviewing revisions to financial procedures
within functions. (I5)
Assurance framework Y Implicit in all aspects of Audit functions. However, reference is made
to considering the annual assurance statement provided by Internal
Audit on the Council’s control environment. (I10)
 internal audit Y Considering reports from the Council’s Internal Auditor (I2)
Page 128

Page 129

 external audit Y Considering reports from the External Auditor concerning Council
functions. (I9)
10 Over the last year, has
adequate consideration been
given to all core areas?
Y Per CIPFA Audit Committees: Practical Guidance for Local
Authorities and Police 2022:
“The Position Statement sets out the core functions of the audit
committee. Essentially, the responsibilities of the committee fall into
three broad areas:
1 Supporting the establishment and maintenance of good
governance, risk management and control arrangements.
2 Supporting accountability and public reporting, in particular the
financial statements and the annual governance statement, and
other statements that accompany the financial statements.
3 Supporting the establishment and maintenance of good
arrangements for internal audit and external audit.”
The Audit and Scrutiny Committee functions in accordance with the
Scheme of Administration, which should support effective
governance, risk management, and control arrangements. The
Corporate Risk Register is also regularly reviewed. It is planned for
the updated Corporate Risk Register to be reported to the Corporate
Committee on 10 June 2025.
Financial reporting –Draft accounts are reported to Moray Council
Committee rather than the Audit and Scrutiny Committee. It is
intended for the Annual Governance Statement for 2024/25 to be
reported to Audit and Scrutiny Committee on 24 June 2025.
External and Internal Audit Reports reported to Audit and Scrutiny
Committee.
Page 129

Page 130

11 Over the last year, has the
committee only considered
agenda items that align with its
core functions or selected wider
functions, as set out in the 2022
guidance?
Y Yes core areas considered include:
 Governance – Yes. Governance forms part of some audits.
 Risk management – Not to Audit and Audit and Scrutiny
Committee but to the Corporate Committee
 Accountability  and public reporting- Yes, Annual Governance
Statement is reported to the Audit and Scrutiny Committee
 Internal audit – Yes, reports received and representatives
from Internal Audit attend meetings to allow challenge.
 External audit - Yes, reports received and representatives
from External Audit attend meetings to allow challenge.
12 Has the committee met
privately with the external
auditors and head of internal
audit in the last year?
Y Members have met in private with the Audit and Risk Manager. This
is at minimum a yearly requirement but can be held at any time at
the request of members.   
Membership and support
13 Has the committee been
established in accordance with
the 2022 guidance as follows?
• Separation from executive Y
• A size that is not unwieldy and
avoids use of substitutes
P Membership –15 from 26 Full Council Elected Members  In
accordance with the CIPFA Guidance, this is more than is required,
but members were of the opinion that no change is needed as it is
considered that current arrangements are appropriate. Non-
administration members are appointed to the positions of Chair and
Vice Chair.
• Inclusion of lay/co-opted
independent members in
Y 2 X Independent Members to the Audit and Scrutiny Committee
have been appointed.
Page 130

Page 131

accordance with legislation or
CIPFA’s recommendation
14 Have all committee members
been appointed or selected to
ensure a committee
membership that is
knowledgeable and skilled?
Y Standards detail that all members must demonstrate the highest
probity and public accountability standards. Briefings have also
been provided in informal sessions to coincide with the audit cycle to
help committee members extend their knowledge.
15 Has an evaluation of
knowledge, skills and the
training needs of the chair and
committee members been
carried out within the last two
years?
Y There is a comprehensive Induction Programme. Ongoing training
and briefings are also provided to elected members. In addition, a
training questionnaire has been developed from the knowledge and
skills framework outlined in the CIPFA Guidance and distributed to
members to identify any additional training needs.
.
16 Have regular training and
support arrangements been put
in place covering the areas set
out in the 2022 guidance?
Y Organisational Development provides training to support elected
members in discharging their duties effectively. As detailed
previously, a training questionnaire has been developed from the
CIPFA Questionnaire that will also help identify any skills gap where
Organisational Development can provide further training.
17 Across the committee
membership, is there a
satisfactory level of knowledge,
as set out in the 2022
guidance?
Y The appointment of 2 X Independent Members with specialised
financial and governance skills has assisted in meeting this
requirement.
18 Is adequate secretariat and
administrative support provided
to the committee?
Y Support is provided by Democratic Services who send out agendas
and compile minutes.
19 Does the committee have good
working relations with key
people and organisations,
Y Yes. External/ Internal Audit and CFO representatives attend
meetings where elected members can discuss and challenge items
on the agenda.  Full Council meeting on 21 January 2025 agreed on
a revised committee reporting format and a more efficient and
Page 131

Page 132

including external audit, internal
audit and the CFO?
effective process for the timely submission to the pre-agenda
meetings. 
Effectiveness of the committee
20 Has the committee obtained
feedback on its performance
from those interacting with the
committee or relying on its
work?
Y There is no formal mechanism for feedback on the Committee’s
performance; however, there are opportunities for views and
guidance to be provided as both the Chief Executive and the
Monitoring Officer attend the Audit and Scrutiny Committee.
21 Are meetings well chaired,
ensuring key agenda items are
addressed with a focus on
improvement?
Y As reflected in the Minutes of the Committee
22 Are meetings effective with a
good level of discussion and
engagement from all the
members?
Y As reflected in the Minutes of the Committee
23 Has the committee maintained
a non-political approach to
discussions throughout?
Y Members agreed this should be moved to a “yes” as work has been
ongoing to further develop improved collaborative working
relationships. 
24 Does the committee engage
with a wide range of leaders
and managers, including
discussion of audit findings,
risks and action plans with the
responsible officers?
Y Members challenge officers on audit findings and endorse
recommendations. Audit and Scrutiny Committee may request
Senior Management to attend Committee and provide an update on
their actions to address the risks and associated recommendations
identified by Internal Audit.
25 Does the committee make
recommendations for the
P The Audit and Scrutiny Committee does not make
recommendations; however, it does agree to the Annual Internal
Audit Plan, and the implementation of the plan is monitored
Page 132

Page 133

improvement of governance,
risk and control arrangements?
accordingly. The audits reported to Committee include
recommendations concerning governance, risk and control
arrangements. The Audit and Risk Manager meets with the Chair of
the Audit and Scrutiny Committee independently of senior
management.  As detailed previously, it was discussed that further
development of the scrutiny function for the Audit and Scrutiny
Committee should be considered.
26 Do audit committee
recommendations have traction
with those in leadership roles?
P Audit and Scrutiny Committee can recommend services to provide
progress reports on implementing audit recommendations. Internal
audit recommendations with management responses included
within reports and follow up reviews also undertaken to evidence
implementation.
27 Has the committee evaluated
whether and how it is adding
value to the organisation?
Y A previous self-assessment and evaluation was undertaken to
review how effectively it fulfilled its functions (CIPFA guidance 2022
‘audit committees’).
28 Does the committee have an
action plan to improve any
areas of weakness?
Y As part of this self-evaluation review, an action plan has been
prepared. 
29 Has this assessment been
undertaken collaboratively with
the audit committee members?
Y Meeting held with members to discuss and agree CIPFA self
assessment and evaluation of the Audit and Scrutiny Committee.
Page 133

Page 134

APPENDIX 2
CIPFA Audit Committees: Practical Guidance for Local Authorities
and Police 2022 Edition
Evaluating the Impact and Effectiveness of the Audit & Scrutiny
Committee
AREAS WHERE THE
AUDIT
COMMITTEE CAN ADD
VALUE BY SUPPORTING
IMPROVEMENT
EXAMPLES OF HOW THE AUDIT
COMMITTEE CAN ADD VALUE AND
PROVIDE EVIDENCE OF
EFFECTIVENESS
SELF-EVALUATION, EXAMPLES,
AREAS OF STRENGTH AND
WEAKNESS
OVERALL
ASSESSMENT
5-1 SEE KEY
BELOW
1. Promoting the principles
of  good governance
and   their application to
decision making
Supporting the development of a local
code of governance.
Providing robust review of the Annual
Governance Statement (AGS) and the
assurances underpinning it.
Supporting reviews/audits of governance
arrangements
Participating in self assessments and
evaluation of governance arrangements
Working with partner audit committees to
review governance arrangements in
partnerships.
Chair of the Audit and Scrutiny
Committee meets with Chief
Executive / Heads of Services on a
regular basis.
The Committee supports the role of
audit in improving internal control
and governance.
Chair meets Committee Chairs of
MIJB and GVJB.
The committee scrutinises AGS.
Audit and Risk Manager provides
annual opinion on the adequacy and
effectiveness of the Council’s
internal control systems. 
3
Page 134

Page 135

Annual self-assessment of
Compliance and Evaluation of
Effectiveness from the CIPFA
Publication “Audit Committees:
Practical Guidance for Local
Authorities and Police 2022 Edition”,
undertaken by Audit and Scrutiny
Committee members.
2. Contributing to the
development of an
effective control
environment.
Actively monitoring the implementation
of recommendations from auditors.
Encouraging ownership of the internal
control framework by appropriate
managers.
Raising significant concerns over
controls with appropriate senior
managers.
Committee receives regular
progress reports from Auditors
including follow up reviews to
evidence the implementation of
recommendations.
Heads of Services attend committee
meetings to answer questions
concerning audit findings and
timescales/progress in the
implementation of
recommendations.
Audit and Risk Manager provides
annual opinion on Council’s internal
control systems.
Control frameworks are in place and
operating effectively for key control
areas. External and Internal Audit
findings are reported to the Audit and
Scrutiny Committee.
4
3. Supporting the
establishment of
arrangements for the
governance of risk and
Reviewing risk management
arrangements and their
effectiveness, e.g. risk management
benchmarking.
Monitoring improvements.
Corporate Committee receives
quarterly and an annual report on the
corporate risks and mitigations.
The Corporate Committee approved
an updated Risk Management Policy
4
Page 135

Page 136

for effective
arrangements to
manage risks.
Holding risk owners to account for
major/strategic risks.
on 23 April 2024.
Business Continuity and Risk
Management Officer supports
services to deliver effective
arrangements.
4. Advising on the
adequacy of the
assurance framework
and considering whether
assurance is deployed
efficiently and
effectively.
Specifying its assurance needs,
identifying gaps or overlaps in
assurance.
Seeking to streamline
assurance gathering and
reporting.
Reviewing the effectiveness of
assurance providers, e.g. internal audit,
risk management, external audit.
Induction programme outlines
governance/ assurance framework
and audit cycle.
Audit and Scrutiny Committee
considers annual strategies, plans
and reports from auditors.
The authority’s leadership team has
defined an appropriate assurance
framework for core delivery
arrangements, major service areas
and collaborations with external
bodies.
5
5. Supporting the quality of
the internal audit activity,
particularly by
underpinning its
organisational
independence.
Reviewing the audit charter and
functional reporting arrangements.
Assessing the effectiveness of internal
audit arrangements, providing
constructive challenge and supporting
improvements.
Actively supporting the quality
assurance and improvement
programme (QAIP) of internal audit.
Audit and Scrutiny Committee
considers and approves the Internal
Audit Charter. A copy of the Internal
Audit Charter is also provided
annually as part of the Annual
Internal Audit Plan.
The Committee is provided with
regular internal audit reports allowing
for any points of clarification to be
discussed and the endorsing of
recommendations.
Committee receives Internal Audit
and PSIAS conformance reports.
5
Page 136

Page 137

Internal Audit undertakes projects in
accordance with the approved audit
plan, and any amendments are
explained.
6. Aiding the achievement
of the authority’s goals
and objectives through
helping to ensure
appropriate governance,
risk, control and
assurance
arrangements
Reviewing how the governance
arrangements support the achievement
of sustainable outcomes.
Reviewing major projects and
programmes to ensure that governance
and assurance arrangements are in
place.
Reviewing the effectiveness of
performance management
arrangements.
Auditors provide assurance reports
on governance arrangements for
transformation, sustainability, and
performance management.
Annual Governance Statement sets
out the Governance Framework.
Inspection reports detail current
arrangements and any improvement
areas to support achieving service
objectives.
The authority’s arrangements to
review and assess performance are
primarily undertaken by Service
Committees.
It is considered that further
development of the scrutiny function
of the Audit and Scrutiny Committee
would improve current governance
arrangements.  
3
7. Supporting the
development of robust
arrangements for
ensuring value for
money.
Ensuring that assurance on value for
money arrangements is included in the
assurances received by the audit
committee.
Considering how performance in
value for money is evaluated as
part of the AGS.
Following up issues raised by
external audit in their value-for-
Value for money is assessed by both
Internal and External Audit. 
Annual Governance Statement sets
out the Governance Framework
including arrangements for best
value.
External audit’s assessments of
arrangements to support best value
are satisfactory.
4
Page 137

Page 138

money work. This overall assessment score was
reduced to 4 as the Council is going
through a period of significant
change to ensure future financial
sustainability and a revised
corporate management re-structure.
8. Helping the authority to
implement the values of
good governance,
including effective
arrangements for
countering fraud and
corruption risks.
Reviewing arrangements against the
standards set out in the Code of
Practice on Managing the Risk of
Fraud and Corruption (CIPFA, 2014).
Reviewing fraud risks and the
effectiveness of the organisation’s
strategy to address those risks.
Assessing the effectiveness of
ethical governance arrangements
for both staff and governors.
Audit and Scrutiny Committee has
scrutinised the Policy to Combat
Fraud, Theft, Bribery and Corruption
(which are underpinned by relevant
standards, codes of conduct,
policies and procedures)
The Corporate Committee approved
the Policy to Combat Fraud, Theft,
Bribery and Corruption on 30
January 2024.
Auditors have issued assurance
reports on fraud risks and counter
fraud controls.
4
9. Promoting effective
public reporting to the
authority’s stakeholders
and local community
and measures to
improve transparency
and accountability.
Improving how the authority discharges
its responsibilities for public reporting;
for example, better targeting at the
audience, plain English.
Reviewing whether decision
making through partnership
organisations remains transparent
and publicly accessible and
encourages greater transparency.
Publishing an annual report from the
committee.
The Audit and Scrutiny Committee
meets in public with only reports
exempt from the public discussion
that are presented in private. Plain
English is used throughout reports
with jargon kept to a minimum.
Audit and Scrutiny Chair meets with
other Committee Chairs on a regular
basis to understand assurance
arrangements to avoid duplication.
5
Page 138

Page 139

Evidence noted that the Council
meets statutory deadlines for
financial reporting.
The Audit and Scrutiny Committee
reviews the Annual Governance
Statement to ensure it accurately
assesses the adequacy of
governance arrangements.
As the Audit and Scrutiny Committee
membership includes 15 elected
members, 2 independent members,
audit reports are available to all
members and direct access to the
Audit and Risk Manager, an annual
report would only be for
administrative rather than
governance control purposes.
Assessment key
5 Clear evidence is available from a number of sources that the committee is actively supporting improvements
across all aspects of this area. The improvements made are clearly identifiable.
4 Clear evidence from some sources that the committee is actively and effectively supporting improvement
across some aspects of this area.
3 The committee has had mixed experience in supporting improvement in this area. There is some
evidence that demonstrates their impact but there are also significant gaps.
2 There is some evidence that the committee has supported improvements, but the impact of this support is
limited.
1 No evidence can be found that the audit committee has supported improvements in this area.  
Page 139

Page 140

APPENDIX 3
CIPFA
Audit Committees
Practical Guidance for Local Authorities and Police 2022 Edition
Recommendations
Risk Ratings for Recommendations
High Key controls absent, not being
operated as designed or could
be improved. Urgent attention
required.
Medium Less critically important controls
absent, not being operated as
designed or could be improved.
Low Lower level controls
absent, not being
operated as designed or
could be improved.
No. Audit Recommendation Priority Accepted
(Yes/ No)
Comments Responsible
Officer
Timescale for
Implementation
Key Objective: The Council’s audit, scrutiny and governance arrangements should comply with CIPFA’s Audit Committees: Practical
Guidance for Local Authorities and Police, 2022 Edition.
1 The Audit and Scrutiny
Committee should undertake an
annual self-assessment and
evaluation exercise against the
best practice checklists detailed
within the CIPFA Publication –
Audit Committees: Practical
Guidance for Local Authorities
and Police 2022.(E1)
Medium Yes Annual self-
assessment and
evaluation
exercise will be
undertaken with
members of the
Audit and
Scrutiny
Committee.
Audit and Risk
Manager
Annual
Requirement
2 The External Auditor and the
Audit and Risk Manager should
at least annually meet in private
with members of the Audit and
Scrutiny Committee. (SA12)
Medium Yes Members can
contact the Audit
and Risk
Manager directly
at any time.
However, a
meeting will be
Audit and Risk
Manager
31/10/2025
Page 140

Page 141

Moray Council
Internal Audit Section
Risk Ratings for Recommendations
High Key controls absent, not being
operated as designed or could
be improved. Urgent attention
required.
Medium Less critically important controls
absent, not being operated as
designed or could be improved.
Low Lower level controls
absent, not being
operated as designed or
could be improved.
No. Audit Recommendation Priority Accepted
(Yes/ No)
Comments Responsible
Officer
Timescale for
Implementation
arranged.
3 A self-evaluation questionnaire
should be issued to elected
members to identify additional
skills or training needs. (SA16)
Medium Yes A self
assessment
questionnaire
has been issued
to all members
of the Audit and
Scrutiny
Committee. Any
training
requirements
identified will be
referred to the
Organisational
Development
Service.
Audit and Risk
Manager
Implemented
4 A review and if necessary, an
update of the Scheme of
Administration should be
undertaken with a specific focus
on further developing the
scrutiny function of the Audit and
Scrutiny Committee.
(SA1/4/6/25/E6)
Medium Yes A review will be
undertaken to
explore the
further
development of
the Council's
scrutiny
functions. This
process will
involve
researching how
Head of
Governance,
Strategy &
Performance
31/12/2025
Page 141

Page 142

Moray Council
Internal Audit Section
Risk Ratings for Recommendations
High Key controls absent, not being
operated as designed or could
be improved. Urgent attention
required.
Medium Less critically important controls
absent, not being operated as
designed or could be improved.
Low Lower level controls
absent, not being
operated as designed or
could be improved.
No. Audit Recommendation Priority Accepted
(Yes/ No)
Comments Responsible
Officer
Timescale for
Implementation
other local
authorities
operate their
scrutiny
functions to
identify best
practices. The
review is
expected to be
completed by
the end of
September
2025, and the
Committee will
receive a report
detailing any
proposed
changes by 31
December 2025.
Page 142

Page 143

Report to: Audit and Scrutiny
Committee
Meeting
Date:
24 June 2025    
Report
by:
Report No:Chief Executive GSP039/25/AS
Author: Atholl Scott Contact
Email:
atholl.scott@moray.gov.uk
Subject: Annual Governance Statement
1. PURPOSE
☒ For Decision      ☐  For Information
1.1 This report provides Committee with a copy of the Council’s Annual Governance
Statement for 2024/25 for review and approval.
1.2 This report is submitted to Committee in terms of Section III (I) (5) of the Council’s
Scheme of Administration relating to supporting the Council’s governance
arrangements through review of the Annual Governance Statement.
2. SUMMARY
2.1 The Annual Governance Statement is a mandatory requirement for local government
bodies and is published by the Council alongside its annual accounts. This report
includes a copy of the draft Annual Governance Statement and is presented to the
Committee for scrutiny before it is finalised for inclusion in the audited annual accounts.
3. RECOMMENDATIONS
3.1 It is recommended that Committee:
i) Committee is asked to scrutinise the draft Annual Governance Statement
provided as Appendix 1.
Atholl Scott
Business Continuity and Risk Management Officer
4. BACKGROUND AND CONTEXT
4.1 The function of good governance in the public sector ensures that entities act in the
public interest at all times. Governance comprises the arrangements put in place to
ensure intended outcomes are defined and achieved.
Item 12.
Page 143

Page 144

4.2 The Chartered Institute of Public Finance and Accountancy (CIPFA) and the Society of
Local Authority Chief Executives (SOLACE), building on work undertaken by the
International Federation of Accountants, have published a guidance framework on
‘Delivering Good Governance in Local Government’.
4.3 The Local Authority Accounts (Scotland) Regulations 2014 requires the Council to
publish an Annual Governance Statement with its annual accounts. The Statement is
based on the guidance and summarises practice across the seven principles identified
within the framework, considers the roles of those who oversee the development and
operation of such practice, and provides an overall assessment of the effectiveness of
governance arrangements. The statement includes an annual opinion provided by the
Audit and Risk Manager in line with Public Sector Internal Audit Standards.
4.4 Good governance practice involves both elected members and officers and this is
reflected in the requirement for the statement to be certified by both the Leader of the
Council and the Chief Executive as Head of Paid Service
4.5 The statement is subject to review by external audit, where the external auditor is
required to report on anything believed to be inconsistent with any other findings
disclosed from the audit work completed. There has been nothing to report in this
regard in previous annual audits.
5. PROPOSALS
5.1 This report provides Committee with a copy of the draft 2024/25 Annual Governance
Statement, which has been produced following completion of the annual review of the
Council’s governance arrangements and system of internal control.
6. SUMMARY OF IMPLICATIONS
6.1 The table below shows whether risks and implications apply if the recommendations
are agreed:
SUBJECT YES NO
Corporate Plan and 10 Year Plan (Local Outcome Improvement
Plan)
×
Policy and Legal ×
Financial ×
Risk ×
Staffing ×
Best Value and Transformation ×
Property ×
Information Communications Technology/Digital          
×
Equalities. Social Inclusion and Economic Impact ×
Climate Change, Biodiversity and Sustainability ×
6.2 Corporate Plan and 10 Year Plan (Local Outcomes Improvement Plan (LOIP))
Governance refers to how organisations are managed and controlled. Effective
governance is key to the delivery of the strategic priorities promoted in Community and
Council strategic plans.
Page 144

Page 145

a) Links to Council Corporate Plan – The proposals in this report support and
contribute to improved outcomes for communities as outlined in the following
Council Plan strategic priorities:
☒ Tackle Poverty and Inequality.
☒ Build Stronger Greener Vibrant Economy.
☒ Build Thriving, resilient, empowered Communities.
b) Links to Local Outcomes Improvement Plan – The proposals in this report support
and contribute to improved outcomes for communities as outlined in the following
local Outcomes Improvement Plan priorities:
☐ Developing a diverse, inclusive, and sustainable economy
☐ Building a better future for our children and young people in   Moray.
☐ Empowering and connecting communities.
☐ Improving wellbeing of our population
6.3 Policy and Legal
The Annual Governance Statement forms part of the annual accounts the Council is
required to prepare under statute.
6.4 Financial
No implications directly arising from this report.
One off Costs:
Service
Area
Budget Budget
Years
Proposed
Spend this
Year
Virement
From
Other
Comments
Annually Recurring Costs:
Service
Area
Budget With Effect
From
Annual Net
Impact
Virement
From (if
applicable)
Other
Comments
6.5 Risk
Good governance includes the effective management of risk, as evidenced in this ‘risk
implications’ paragraph in all reports that come before the Council and its committees,
and in the Council’s corporate risk register that is kept under review by Senior
Management and reported at agreed intervals to the Corporate Committee
6.6 Staffing
No implications directly arising from this report.
6.7 Best Value and Transformation
The Council’s Annual Governance Statement is prepared in accordance with the
CIPFA/SOLACE ‘Delivering Good Governance in Local Government’ Framework and is
key to ensure the delivery of the council’s strategic priorities.
6.8 Property
No implications directly arising from this report.
6.9 Information Communications/Technology/Digital
No implications directly arising from this report.
Page 145

Page 146

6.10 Equalities, Social Inclusion and Economic Impact
No implications directly arising from this report.
6.11 Climate Change and Biodiversity Impacts
No implications directly arising from this report.
7. CONSULTATION
7.1 The Chief Executive, and Corporate and Senior Management Teams have been
consulted and have contributed to the content of the Annual Governance Statement. In
addition, the Leader of the Council, as a signatory to the Statement, has also been
consulted.
8. BACKGROUND PAPERS
8.1 None
Page 146

Page 147

APPENDIX 1
Moray Council
Annual Governance Statement
2024/25
Page 147

Page 148

Table of Contents
1. Scope of Responsibility
2. Framework for Good Governance
3. Review of the Adequacy and Effectiveness of the
Council’s Governance Arrangements
4. Overall Assessment of the Effectiveness of
Governance Arrangements
5. Significant governance issues
6. Concluding Remarks
Page 148

Page 149

1. Scope of Responsibility
The council is responsible for ensuring its business is conducted in accordance with
the law and proper standards, and that public money is safeguarded, properly
accounted for, and used economically, efficiently and effectively. The council has a
statutory duty to make arrangements to secure Best Value under the Local
Government in Scotland Act 2003.
In discharging these responsibilities, elected members and the corporate leadership
teams are responsible for putting in place proper arrangements for the governance
of the council’s affairs and for facilitating the effective exercise of its functions. In
delivering these functions, there is a requirement to maintain effective partnership
working with others, principally with NHS Grampian and the Moray Integration Joint
Board, Grampian Valuation Joint Board, tsi Moray, and the Moray Leisure Centre, as
well as with other bodies involved in Community Planning and in the delivery of
projects forming part of the Moray Growth Deal.
This annual governance statement, which covers the period from 1 April 2024
through to the date of signing of these annual accounts, explains how the council
has used the CIPFA/SOLACE 2016 Framework ‘Delivering Good Governance in
Local Government’ as a basis for considering the effectiveness of its own
governance arrangements.
2. Framework for Good Governance
The overall aim of the ‘Delivering Good Governance in Local Government’
Framework is to ensure that: resources are directed in accordance with agreed
policy and according to priorities; there is sound and inclusive decision making; and
there is clear accountability for the use of those resources in order to achieve
desired outcomes for service users and communities.
The key elements of the council’s governance arrangements are described in terms
of the seven principles defined in the Framework, summarised as follows:
2.1 Behaving with integrity, demonstrating strong commitment to
ethical values, and respecting the rule of law;
The roles and responsibilities of elected members and senior officers and the
processes to govern the conduct of the council’s business are defined in procedural
Standing Orders, a Scheme of Administration, a Scheme of Delegation, and
Financial Regulations. These are updated annually following consideration and
review of changes necessary for the effective functioning of the council’s affairs.
These changes are prompted by new legislation, audit recommendations, or to
incorporate identified revisions necessary to improve governance practice.
Supplementary (second tier) documents providing additional guidance on specific
constitutional matters have also been updated to support improvements in
collaborative leadership; these covering councillor roles and responsibilities,
councillor/senior officer relations, and the role of councillors serving on outside
Page 149

Page 150

bodies. Early stages of a plan to implement a revised management structure, to
include new ways of working and a refreshed corporate culture have also been
progressed. 
Codes of Conduct for both elected members and officers are in place, and these
define the ethical values and standards of behaviour expected. The Codes draw on
the ‘Standards in Public Life’ covering issues including leadership, fairness and
integrity. Refresher training on the Code of Conduct for elected members was
delivered in conjunction with the Improvement Service. Two referrals in respect of
councillor conduct were made to the Standards Commission during the year; neither
resulted in formal action being taken.
The council’s Head of Governance, Strategy and Performance is the designated
Monitoring Officer responsible for ensuring that agreed procedures are followed and
that all applicable statutes and regulations are complied with. External support was
secured to support the development of collaborative leadership as an aid to good
governance in decision making, with elected members acknowledging the benefits of
collegiate working where practicable to do so.
2.2 Ensuring openness and comprehensive stakeholder
engagement;
In developing improvement and modernisation opportunities, meetings of the council
and its committees are delivered using a hybrid format that enables attendance in
person or via web link. Meetings of the council and main service Committees are live
streamed and available for public viewing, with matters discussed and determined in
confidence relating only to those deemed confidential in terms of Part 1 of Schedule
7A of the Local Government (Scotland) Act 1973.  The rationale for all decisions
proposed and taken is fully set out in committee reports.
Stakeholder engagement is central to the council’s work at a strategic level, notably
in the development of the updated Corporate Plan which sets out strategic priorities
for the period from 2024-29. Both staff and the public were surveyed, and the results
reported to a meeting of the council to aid and inform consideration of the priorities to
be taken forward. Service consultations are also conducted as appropriate, recent
examples including a tenant satisfaction survey in housing, engagement on town
centre redevelopment, and on options for future school provision in communities
across Moray.
Wide consultation with both internal and external stakeholders also informed the
preparation of a comprehensive Evidence Report, one of the first to be approved by
Scottish Government ahead of the council formulating its Moray Local Development
Plan for 2027.
The council seeks and obtains feedback on delivery of its services having adopted a
comprehensive complaints procedure based on a model scheme developed by the
Office of the Scottish Public Services Ombudsman. All complaints are responded to
Page 150

Page 151

as appropriate and inform improvements to service delivery. A comprehensive report
on complaints handling is prepared and presented annually to a council committee.
2.3 Defining outcomes in terms of sustainable economic, social,
and environmental benefits;
The creation and implementation of a vision for the local area, including expected
outcomes for the community, is encompassed in the Local Outcomes Improvement
Plan (LOIP). The overarching aim and purpose of this 10-year Plan is ‘to raise
aspirations by creating an enabling environment where our residents can achieve
expanded choices, improved livelihoods and wellbeing”.
In particular, the LOIP recognises the importance of and benefits from reducing
inequalities and poverty, with outcomes focused on the need for a growing, diverse
and sustainable economy, building a better future for our children and young people
in Moray, empowering and connecting communities, and improving the wellbeing of
our population.
The LOIP is a partnership plan, and its strategic delivery is overseen by a
Community Planning Board, which meets quarterly. The Board comprises
representatives from a broad range of organisations as reflected in agenda items
considered during the year. These included reports on School Age Childcare,
Climate Change, Moray Growth Deal, Community Learning and Development,
Promotion of Physical Activity, and Community Wealth Building.
Development sessions have been held to strengthen good governance
arrangements, recognising the benefits that working in partnership can bring. A self-
assessment facilitated by the Improvement Service has also been completed with a
feedback development session planned to consider outcomes from the self-
assessment and any further actions arising therefrom.
Currently the LOIP sits alongside a refreshed Corporate Plan Moray 2024-2029, the
latter setting out the vision and priorities of the council for the next five years. The
council plan updates council priorities focussing on three key themes: tackling
poverty and inequality, building a stronger greener vibrant economy, and seeking to
build thriving, resilient, empowered communities. The plan sets targets for outcomes
consistent with maintaining a sustainable council that provides valued services to its
communities.
The period also saw the council agree a Sustainable Development Statement
aligned to the Corporate Plan, council priorities and the Climate Change Strategy.
The statement acknowledges sustainable development as a fundamental aspect of
Best Value and provides a framework against which the council can monitor
progress and demonstrate compliance.
2.4 Determining the interventions necessary to optimise the
achievement of the intended outcomes;
Page 151

Page 152

The strategic partnership and corporate plans are translated into service plans
prepared within each council service area. These facilitate delivery of agreed
outcomes and assist in securing continuous improvement. Service plans are
reported to a meeting of the council or appropriate service committee for
consideration and approval, in reports that provide information on planned activity.
More generally, all committee reports contain a ‘Summary of Implications’ section
that links report content to strategic plans, legal and policy issues; financial
implications, risk, staffing and property matters; equalities; social impact; and climate
change and biodiversity considerations. The format of these reports has been
updated during the period based on advice from the Improvement Service with the
principal objective of providing enhancements to current reporting arrangements. A
particular focus continues to be given to financial implications of any proposals given
the current economic climate.
The council is fully aware of the financial challenges it faces, and elected members
are provided with an extensive volume of information on both the availability of
resources and options for future service delivery. This has been made available
during workshops for elected members; in reports to the council on budget setting,
including projections for the medium to longer term; and in regular budget monitoring
reports covering both capital and revenue expenditure submitted to service
committees. A formal budget protocol was developed during the year to aid
governance in this area, which set a framework of engagement and consultation to
support the process.
A balanced budget for 2025/26 was secured without use of reserves for the first time
in several years. This was achieved through a combination of an improved financial
settlement from Scottish Government, an increase in Council Tax, and savings
delivered in line with the council’s short to medium term financial strategy. A number
of unknowns including impacts of inflation and arising from future pay awards were
highlighted during the budget setting process, as were continued pressures in
respect of the council’s funding obligations to the Moray Integration Joint Board.
Longer term financial planning projections note that further council tax rises and
additional savings will be required going forward, and a transformation strategy was
agreed during the year to aid in the delivery of these savings.
The achievement of agreed outcomes is monitored through an established
Performance Management Framework that calls for frequent reporting on key
performance measures developed for each service. In addition, the council
participates in the Local Government Benchmarking Framework which compares a
range of established performance measures with those of other Scottish local
authorities. Service Committees are provided with reports to review, scrutinise and
note actions undertaken by services to meet performance objectives. An illustrated
annual Public Performance Report is prepared and published to demonstrate the
outcomes and achievements of the council during the year, together with an annual
report on progress relative to delivery of the Corporate Plan objectives.
Page 152

Page 153

2.5 Developing the entity’s capacity, including the capability of its
leadership and the individuals within it;
The Chief Executive is responsible and accountable to the council for all aspects of
management including promoting sound governance, providing quality
information/support to inform decision making and scrutiny, supporting other
statutory officers, and building relationships with all elected members. For the
majority of the period covered by this statement, the Chief Executive role was filled
on an interim basis following retirement of the permanent jobholder. A permanent
replacement Chief Executive has been appointed and commenced in post in March
2025.
Leadership capacity of senior officers is supported through the promotion of a
Leadership Forum, which brings together senior managers from all services to
provide a wider perspective to the consideration of issues facing the council. Forum
meetings ensure consistent messaging is available from senior management to
managers. Human Resources has continued to review and refine workforce
development opportunities, including on leadership development, and to provide
training opportunities for all staff online.
An external review of the roles and responsibilities of senior employees has been
progressed during the period to ensure corporate management arrangements
remain appropriate in terms of capacity and capability in the current operating
environment.  A revised senior management structure was agreed by council in April
2025. Actions arising therefrom will be progressed over the summer period with a
target date for full implementation of September 2025. The revisions stress the
importance of prioritising leadership, in consequence the corporate management
arrangements that applied for most of the period covered by this statement have
been revised. A Corporate Leadership Team (CLT) comprising the Chief Executive,
three Executive Directors, the Monitoring Officer, the Chief Financial Officer and the
Chief Officer (Health and Social Care Moray) has been established. This is
supported by an Extended Corporate Leadership Team (ECLT) that additionally
includes Heads of Services.
The council has an agreed elected members’ development strategy that includes an
on-going training programme of learning, development and briefings. Members
appointed to certain committees also receive specific training related to the
responsibilities of these committees. A Strategic Leadership Forum has been
established involving both elected members and senior officers to facilitate
collaborative cross-party discussions on the future direction of council services.
Senior Officers also meet regularly with Chairs of the council and its committees.
In addition, elected members represent the council on a range of outside bodies,
including on boards of other Community Planning partners, across partnership
bodies such as the Moray Economic Partnership, various national bodies such as
COSLA and its themed Boards, and a broad range of charitable and third sector
organisations. This representation provides valuable learning and networking
opportunities for those members.
Page 153

Page 154

2.6 Managing risks and performance through robust internal
control and strong public financial management;
The council has a risk management policy designed to support the identification,
evaluation and mitigation of risks that may impact on its ability to meet its objectives.
The policy was updated during the year. A Corporate Risk Register is also
maintained providing summary information on issues the CLT considers are the
principal risks facing the council. The register describes how these risks are
managed and controlled. Risk implications are also detailed in all committee reports
to inform decision-making processes.
The council’s system of internal control is based on a framework of financial
regulations, regular management information, administrative procedures,
management supervision and a scheme of delegation that defines accountabilities of
senior officers. Establishing and maintaining an effective system of internal control is
a management function. An Audit and Scrutiny Committee, through its consideration
of reports by internal and external auditors, monitors the effectiveness of the system
of internal control.
Strong financial management is secured through the work of the Chief Financial
Officer appointed in terms of s.95 of the Local Government (Scotland) Act 1973. This
officer advises the Council on all financial matters and ensures the timely production
and reporting of budget estimates, budget monitoring reports and annual accounts.
Draft and audited Annual Accounts are published on the council website.
2.7 Implementing good practices in transparency, reporting, and
audit to deliver effective accountability;
Council business is conducted through an established cycle of webcast committee
meetings. Webcasts remain available for viewing for 12 months following a meeting.
Meeting dates are published in advance, and agenda papers are made available at
least one week before meetings take place. Minutes of meetings are prepared, and
important decisions are publicised on the council website and through social media.
The council’s website provides a platform from which to disseminate a wide range of
information including news items on policy decisions, guidance on council services,
and on service disruptions/interruptions arising from weather events or similar. The
website increasingly facilitates efficient access to digital services across a range of
service areas and allows for consultations to be undertaken and for interested
parties to provide feedback electronically.
The council responds to the findings and recommendations of Internal Audit,
External Audit, and other Scrutiny and Inspection bodies by developing improvement
Action Plans. The Audit and Scrutiny Committee is integral to overseeing
independent and objective assurance processes that make recommendations for
improvements to the system of internal control. Training for elected members on the
specifics of effective scrutiny was provided during the period.
Page 154

Page 155

A particular and continuing focus in the period was the council’s response to the
latest Accounts Commission Best Value review report. The report was considered in
detail at a meeting of the Council in June 2024, with an action plan developed in
response to the Commission’s findings. Progress towards meeting the action plan
objectives, which covers issues including the council’s vision, leadership, effective
use of resources and sustainable development, has been considered by the
council’s Corporate Committee at quarterly intervals for the remainder of the period
covered by this statement, with actions taken to address the agreed
recommendations from the report being closely monitored.
The council responds to requests for information under Freedom of Information
legislation having processed some 1,500 such requests during the period covered by
this statement.
3. Review of the Adequacy and Effectiveness of the Council’s
Governance Framework
3.1 In order to assess the effectiveness of the governance framework, including
the system of internal control, it is necessary to consider the role of the
functions and individuals who contribute to it, as follows:
 Elected Members
Governance arrangements at a political level emanate from the council, its
committees and from other roles that elected members fulfil. These include
participation in the Community Planning Board and associated groups for
multi-agency issues. Elected members also have substantive roles on the
Moray Integration Joint Board for Health and Social Care, the Grampian
Valuation Joint Board, and the Moray Leisure Arm’s Length External
Organisation (ALEO), each of which has its own governance arrangements. In
addition, elected members have membership and represent Moray Council
interests in partnerships that contribute to meeting council aims and
objectives, notably in the development and delivery of projects forming part of
the Moray Growth Deal.  Acknowledging political difference, elected members
have been encouraged to strengthen collegiate working where possible. This
has been evident during the period with improved opportunities for informal
discussion and engagement on development of policy proposals. A survey of
elected members and chief officers on collaborative leadership and working
relationships also returned positive results.
 Audit and Scrutiny Committee
The council has an Audit and Scrutiny Committee where elected members
consider reports on audit matters. These reports provide assurances on the
adequacy and effectiveness of the system of internal controls including those
relative to the delivery of plans, compliance with laws and regulations,
accuracy of information and safeguarding of assets. The Committee functions
Page 155

Page 156

in line with best practice guidance published by the Chartered Institute of
Public Finance and Accountancy. Two external members sit on the committee
to provide an independent perspective on issues under consideration.
This committee is a key component of good governance, distinguished from
other committees by the role elected members are required to fulfil, not in
setting policy or considering service matters, but by providing independent
oversight and challenge in support of the council’s duty to secure continuous
improvement. These functions are delivered independently from the
supervisory oversight roles of the Leadership Teams.
   The Corporate Leadership Team
The Corporate Leadership Team (CLT) has overarching operational
responsibility for good governance arrangements. The team for much of the
year comprised the Chief Executive, two Depute Chief Executives with
portfolio responsibilities for Education, Communities and Organisational
Development; and Economy, Environment and Finance respectively, the Chief
Officer (Health and Social Care Moray), the Monitoring Officer and the Chief
Financial Officer. As reported above, the roles and responsibilities of officers
within the Corporate Management Team have been revised and, in some
cases, redesignated to strengthen strategic leadership arrangements.
   The Corporate Leadership Team / Extended Corporate Leadership
Team
This is an extended management team comprising the CLT and Heads of
Services. The role and remit of this group is to support the formulation and
implementation of policies, strategies and plans to achieve local and national
outcomes, to share and promote good practice from an inter-service
perspective, to act with the wider objectives of the council in mind to ensure
the resources are effectively deployed, and to assist CLT in keeping the
governance of the council and its services under review.
Individual Heads of Service, including the Chief Financial Officer and
Monitoring Officer, have considered the effectiveness of governance
arrangements within their respective services by reference to the principal
risks identified in the council’s Corporate Risk Register and provided
assurance statements for use in the preparation of this corporate statement.
This affirms the broad ownership of good governance and recognition of its
importance within the senior leadership of the council.
Overall, the assurance statements provided confirm that governance
arrangements within services are working as intended, and in support
commentary has been given on elevated risks and on mitigating actions taken
in response. The main issues raised in these returns are:
Page 156

Page 157

 Staffing shortages and vacancies, and their impact on capacity to deliver
change at pace in a number of service areas.
 Continuing risk of data breaches, and the response being taken by
services to mitigate these through provision of training on data security
and reminder on data security considerations when using email.
 Ongoing obligations on the Housing Service to monitor homelessness data
and progress electrical safety improvements in council houses in support
of national initiatives directed by the Scottish Housing Regulator.
 A need for continued focus on Health and Safety requirements thereby
protecting the workforce and minimising the number of reportable
incidents.
 Reported progress made to strengthen governance arrangements around
delivery of Additional Support Needs in Education, and to embed climate
change implications into procurement practice.
 A need to ensure due consideration is given to equalities impacts in all
cases where persons or groups potentially affected have protected
characteristics.
 The Head of Governance, Strategy and Performance (Monitoring Officer)
/   Chief Financial Officer
The Head of Governance, Strategy and Performance and the Chief Financial
Officer perform their respective statutory duties as outlined elsewhere in this
statement. In discharging the responsibilities of the role, the Chief Financial
Officer complies with the governance requirements of the CIPFA Statement on
the role of the Chief Financial Officer, and the Head of Governance, Strategy
and Performance provides an annual information report on discharging the
duties of a Monitoring Officer to a meeting of the council.
 The Chief Social Work Officer
The Head of Service, Health and Social Care Moray fulfils the statutory role of
Chief Social Work Officer (CSWO) as part of the duties of the post. The latest
available CSWO annual report for the year to 31 March 2024 notes continuing
challenges, with increased service needs set against financial and recruitment
pressures.
This report covers the first year Children & Young People and Criminal Justice
Social Work services have been fully integrated into the Health and Social
Care Partnership, and, in the period covered by this statement, work has
continued to better align governance structures across Health and Social
Care.
Improvements under way include replacement of the case management
system, development of data used for performance reporting, and progressing
the review of adult commissioning arrangements in response to a recently
completed audit of current practice by an external firm.
Page 157

Page 158

The report also noted an impending change in the holder of the CSWO post
and in a number of other senior manager roles and stressed the importance of
ensuring services remain as stable as possible during a period of further
transition. The post of CSWO has been filled on an interim basis since June
2024, and arrangements are being finalised for the recruitment of a
permanent CSWO.
 Internal Audit
The Internal Audit activity adds value to the Council by considering strategies,
objectives, and risks; offering ways to enhance governance, risk management
and control processes; and objectively providing relevant assurances.
The Audit and Risk Manager is accountable on a day-to-day basis to the Head
of Governance, Strategy and Performance and to the Audit and Scrutiny
Committee. Internal Audit applies mandatory Public Sector Internal Audit
Standards (PSIAS) in delivering the Internal Audit Service. An external quality
assessment of the service during the year confirmed compliance with the
PSIAS.
The Council has a system of internal control designed to manage risk to a
reasonable level. Internal controls cannot eliminate the risk of failure to
achieve policies, aims and objectives and can therefore only provide
reasonable and not absolute assurance of effectiveness.
The internal audit plan for the year includes a range of audit projects covering
main financial systems, other systems operating within services and several
ad-hoc/unplanned projects. The outcomes from these projects, together with
any recommendations to enhance the control environment, are reported to the
Audit and Scrutiny Committee. This Committee is chaired by an elected
member who is not part of the council Administration. Almost all planned
reviews detailed within the Annual Internal Audit Plan for 2024/25 were
completed as scheduled.
PSIAS requires an internal audit opinion to be provided annually. As planned
audit work was substantially completed by the year-end and based on this and
other knowledge of the organisation and its control systems, it is the opinion of
the Audit and Risk Manager that reasonable assurance can be placed upon
the adequacy and effectiveness of the internal control environment which
operated in the council during the year.
 Health & Social Care Partnership
The council, as a key partner of Health and Social Care Moray has an interest
in the governance arrangements of the Moray Integration Joint Board (MIJB).
This given its financial exposure as a principal funder and continuing statutory
responsibilities for Social Work services and the role and function of the Chief
Social Work Officer. Governance was improved during the period with the
Page 158

Page 159

Chief Officer (Health and Social Care Moray) now attending council meetings
and providing reports summarising details of the Board’s activities.
Audit arrangements for the MIJB are provided jointly by the council’s Internal
Audit Service and NHS Grampian’s Internal Auditors. The council’s Audit and
Risk Manager (as Chief Internal Auditor for the MIJB) provides assurance
over social care services, and oversight of the MIJB governance
arrangements. In prior years there was no formal reporting to the MIJB of
internal audit work relative to NHS services delivered under its direction. This
position has been reviewed to strengthen governance practice, with
agreement now reached to enable relevant NHS Internal audit reports to be
considered by the MIJB.
From audit work completed in this role, the Chief Internal Auditor has provided
an opinion of only limited assurance that the Moray Integration Joint Board
has adequate systems of governance and internal control for the year ended
31st March 2025.
A continuing governance consideration for the council on a recurring basis is
the financial sustainability of the MIJB, with any overspend against budget
requiring to be met by NHS Grampian and the council as principal funders,
pro-rata in line with an agreed funding agreement. For the 2024/25 financial
year, an overspend was forecast and work undertaken to identify savings. A
recovery plan was also agreed and is being delivered. Service pressures in
Health and Social Care are likely to continue and will require close monitoring
going forward.   
 External Agencies
In addition to the various internal review processes and the external audit of
the Annual Accounts, aspects of the council’s governance arrangements are
considered in various inspection reports produced by the external auditor and
other inspectorate agencies.
The latest Accounts Commission Best Value Report on the council, while
highlighting areas of good practice, made a number of recommendations to
further strengthen systems and processes in key strategic areas. The report
called on the council to accelerate plans to transform how it works and deliver
services, and to demonstrate its ability to create capacity to sustain the pace
and momentum necessary to effect change. In particular, the report
highlighted a need for the council’s Improvement and Modernisation
Programme to set out clear deliverables, deadlines and lines of accountability,
and for arrangements to be put in place to ensure the accuracy of financial
forecasting and in-year budget monitoring.
The council in response has reviewed its governance arrangements around
priorities and strategic direction and prepared a comprehensive Best Value
Action Plan and Transformation Strategy to aid progress. The Best Value
Page 159

Page 160

Report findings were formally accepted at a special meeting of the council on
12 June 2024.
The External Audit Plan for 2024/25 notes there is potentially a risk that the
council does not meet its key priorities due to delayed progression of
objectives and the pace of change being limited or slow, and the external audit
assessment of progress will be undertaken as part of the annual audit work
due to take place during the summer of 2025. A thematic external review of
transformation is on-going at the time of drafting this statement.
4. Overall Assessment of the Effectiveness of Governance
Arrangements
4.1 Having regard to the information provided in the preceding paragraphs, it is
considered that established systems and processes are consistent with the
seven principles identified in the ‘CIPFA/SOLACE’ Framework ‘Delivering
Good Governance in Local Government.’ Implementation of the Best Value
Action Plan has further strengthened these arrangements, and work will
continue as outlined below to optimise governance arrangements that deliver
Best Value for Moray.
5. Significant Governance Issues
5.1 Issues reported as requiring attention in the Annual Governance Statement
for the prior year (2023/24) were aligned to the Best Value report, and to
reports prepared by external advisers who provided consultancy support to
the Council. These reports informed a Best Value self-assessment exercise
completed by council managers which included the following priority areas for
improvement:
 Continue work to establish a clear shared vision for Moray that supports
delivery of sustainable public services.
 Maintain current activity to ensure leadership is effective and there is good
collaboration between elected members and senior officers.
 Increase the pace of transformation and identify savings with the intention
of securing longer term financial sustainability.
 Revisit governance arrangements covering partnerships; principally for
Health and Social Care Moray in respect of performance and early
identification of any significant financial and service risks.
5.2 While good progress has been made on all of these areas, the plan for
improvement is a three-year plan and will need further refinement as the
council responds to change both internally and in response to emerging
issues impacting on local government.
5.3 Specifically:
Page 160

Page 161

 The potential to further articulate a clear shared vision for Moray remains
under consideration in terms of developing a single high-level plan that
consolidates the Moray Local Outcomes Improvement Plan and the
council’s Corporate Plan. The absence of a single plan of itself has not
prevented effective working in partnership in multiple areas, including
community safety, leisure and health, child protection, and economic
development.
 Measures to strengthen governance arrangements around leadership
have been developed to enhance collegiate working and a review of
senior management roles and responsibilities has been progressed,
primarily to address workload capacity issues. Notwithstanding interim
arrangements in a number of key roles, the council has continued to drive
forward multiple initiatives across all services, including the management
and oversight of substantial external funding streams including those for
the Moray Growth Deal.
 Transformation opportunities are being pursued with specific funding
allocated from earmarked reserves aimed at securing service
improvements and efficiencies. Financial sustainability has been secured
short-term through delivery of a balanced budget for 2025/26, with
medium to longer term financial plans updated to evidence a continuing
commitment to sound financial management.
 While Health and Social Care Moray has taken steps to generate savings
from its operations during the period, a significant operating deficit in
2024/25 is expected, and further significant budget pressures are forecast
in 2025/26. The council is obliged to meet its share of any overspend and
has made provision to mitigate this risk.    
5.4 Looking forward, key governance challenges relate to:
 supporting elected members to sustain the benefits derived from
collaborative working, while recognising and respecting political
difference;  
 rebuilding a strong and effective corporate leadership team under the
recently appointed Chief Executive in line with the agreed revised senior
management structure.
 continuing to explore transformation opportunities where these are likely
to generate improved, modern and sustainable ways of working.
 monitoring closely capital and revenue spend, including allocations to
partner bodies, to ensure the ongoing financial sustainability of the
council.
 reviewing committee meeting timetables to ensure these fully align with
recently revised reporting arrangements.
 giving consideration to the mechanism for discharging the scrutiny role of
elected members and distinguishing that from their decision-making roles
on service committees.
 progressing the review of other staffing structures to create capacity
Page 161

Page 162

necessary to deliver agreed priorities; this will require on-going
engagement with staff, service users and other stakeholders and provide
clarity around changes to service aims, delivery models, standards and
levels of performance. 
6. Concluding Remarks
6.1 Good governance is key to the successful operation of the council and during
the period covered by this statement, governance arrangements have been
strengthened further through the development and application of a best value
action plan. External support has also been secured to improve organisational
culture. A number of changes in senior management roles have taken place
with interim management arrangements applying for much of the period. A
permanent replacement Chief Executive is now in post and a new senior
management structure designed to strengthen leadership capacity approved.
6.2 The council is now better placed to meet the challenges that undoubtedly lie
ahead. Working together we are committed to securing continuous
improvement in governance practice in order to deliver the best possible
outcomes for the citizens and communities of Moray.
Kathleen Robertson                                                                         Karen Greaves
BEM                           Leader of the Council                                                        
Chief Executive
xx September 2025