Audit and Scrutiny Committee 
Wednesday, 11 September 2024 
NOTICE IS HEREBY GIVEN that a Meeting of the Audit and Scrutiny Committee
is to be held at Council Chambers, Council Office, High Street, Elgin, IV30 1BX
on Wednesday, 11 September 2024 at 09:30. 
BUSINESS 
1. Sederunt 
2. Declaration of Group Decisions and Members Interests * 
3. Resolution
Consider, and if so decide, adopt the following resolution:
"That under Section 50A (4) and (5) of the Local Government
(Scotland) Act 1973, as amended, the public and media
representatives be excluded from the meeting for Items 12, 13 and 14
of business on the grounds that they involve the likely disclosure of
exempt information of the class described in the relevant Paragraphs
of Part 1 of Schedule 7A of the Act.”   
4. Minutes of meeting of 25 June 2024 7 - 12
5. Written Questions ** 
6. Internal Audit Section Update Report
Report by Audit and Risk Manager
13 - 34
7. Internal Audit Review - Procurement and Creditor
Payments
Report by Audit and Risk Manager
35 - 44
8. Internal Audit Review - Following the Public Pound
Report by Audit and Risk Manager
45 - 62
9. Internal Audit Review - Commercial Refuse Collection
Report by Audit and Risk Manager
63 - 80
Page 1

Page 2

10. Public Sector Internal Audit Standards - External Quality
Assessment of Internal Audit
Report by Audit and Risk Manager
81 -
102
11. Carefirst Replacement - Progress Update
Report by Interim Head of Service and Chief Social Work Officer
103 -
108 
Item(s) which the Committee may wish to consider with
the Press and Public excluded   
12. Internal Audit Review - Email Security [Para 14]
• 14. Information relating to action taken, or to be taken, in
connection with the prevention, investigation or prosecution of
crime. 
13. Internal Audit Follow Up Review - Cyber Security [Para
14]
• 14. Information relating to action taken, or to be taken, in
connection with the prevention, investigation or prosecution of
crime. 
14. Update on Improvement Plan for Adult Social Care
Commissioning [Para 8]
• 8. Information on the amount of any expenditure proposed to be
incurred by the Authority; 
Summary of Audit and Scrutiny Committee functions:
Standards - To ensure that the highest standards of probity and public
accountability are demonstrated.
Audit Functions - Consider reports from the Council's internal and
external auditors concerning Council Functions.
Scrutiny Functions - To scrutinise areas of policy, service delivery or
performance identified for improvement.
Inquiries - To deal with all matters relating to local inquiries into
matters affecting children.     
Page 2

Page 3

Watching the Meeting
You can watch the webcast live by going to: 
http://www.moray.gov.uk/moray_standard/page_43661.html    
Webcasts are available to view for 1 year following the meeting.  
You can also attend the meeting in person, if you wish to do so,
please come to the High Street entrance door and a member of
staff will be let into the building. 
Page 3

Page 4

GUIDANCE NOTES 
* Declaration of Group Decisions and Members Interests - The Chair of the
meeting shall seek declarations from any individual or political group at the
beginning of a meeting whether any prior decision has been reached on how
the individual or members of the group will vote on any item(s) of business on
the Agenda, and if so on which item(s).  A prior decision shall be one that the
individual or the group deems to be mandatory on the individual or the group
members such that the individual or the group members will be subject to
sanctions should they not vote in accordance with the prior decision.  Any such
prior decisions will be recorded in the Minute of the meeting. 
** Written Questions - Any Member can put one written question about any
relevant and competent business within the specified remits not already on the
agenda, to the Chair provided it is received by the Proper Officer or Committee
Services by 12 noon two working days prior to the day of the meeting.  A copy
of any written answer provided by the Chair will be tabled at the start of the
relevant section of the meeting.  The Member who has put the question may,
after the answer has been given, ask one supplementary question directly
related to the subject matter, but no discussion will be allowed. 
No supplementary question can be put or answered more than 10 minutes after
the Council has started on the relevant item of business, except with the
consent of the Chair. If a Member does not have the opportunity to put a
supplementary question because no time remains, then he or she can submit it
in writing to the Proper Officer who will arrange for a written answer to be
provided within 7 working days. 
Page 4

Page 5

MORAY COUNCIL 
Audit and Scrutiny Committee 
SEDERUNT 
Councillor Shona Morrison  (Depute Chair)  
Councillor Peter Bloomfield  (Member)
Councillor Theresa Coull  (Member)
Councillor John Divers  (Member)
Councillor Amber Dunbar  (Member)
Councillor Jérémie Fernandes  (Member)
Councillor Donald Gatt  (Member)
Councillor David Gordon  (Member)
Councillor Sandy Keith  (Member)
Councillor Scott Lawrence  (Member)
Councillor Marc Macrae  (Member)
Councillor Neil McLennan  (Member)
Councillor John Stuart  (Member)  
Mr Ivan Augustus  (Non-Voting Member)
Ms Margaret Wilson  (Non-Voting Member)
Clerk Name: Caroline O'Connor
Clerk Telephone: 07779 999296
Clerk Email: committee.services@moray.gov.uk 
Page 5

Page 6

Page 6

Page 7

MORAY COUNCIL 
Minute of Meeting of the Audit and Scrutiny Committee 
Tuesday, 25 June 2024 
Council Chambers, Council Office, High Street, Elgin, IV30 1BX 
PRESENT 
Mr Ivan Augustus, Councillor Peter Bloomfield, Councillor Theresa Coull, Councillor
John Cowe, Councillor Amber Dunbar, Councillor Donald Gatt, Councillor David
Gordon, Councillor Sandy Keith, Councillor Scott Lawrence, Councillor Graham
Leadbitter, Councillor Marc Macrae, Councillor Neil McLennan, Councillor Shona
Morrison 
APOLOGIES 
Councillor John Divers, Councillor Jérémie Fernandes, Ms Margaret Wilson 
IN ATTENDANCE 
Interim Chief Executive; Head of Governance, Strategy and Performance; Head of
Financial Services; Head of Environmental and Commercial Services; Audit and
Risk Manager, Caroline O'Connor, Committee Services Officer, all Moray Council
and Angela Pieri and Andrew Wallace, Grant Thornton - External Auditors. 
1.         Chair 
Councillor Leadbitter, as Chair of the Audit and Scrutiny Committee, chaired the
meeting.  
2.         Pre-Election Period 
The Chair reminded the Committee the meeting was taking place during the pre-
election period and that there are restrictions on the Council over publishing
material which could show support for a particular party.  As Council meetings are
webcast they fall within these restrictions.  
The Chair stated the advice from the Monitoring Officer was that, whilst the
Committee can continue to deal with "business as usual" items, should debate
become overtly political then the Chair may require to intervene. 
3.         Declaration of Group Decisions and Members Interests * 
In terms of Standing Orders 21 and 23 and the Councillors' Code of Conduct, there
were no declarations from Group Leaders or Spokespersons in regard to any prior
decisions taken on how Members will vote on any item on the agenda or any
declarations of Member's interests in respect of any item on the agenda.  
4.         Minute of meeting of 8 May 2024 
The minute of the Audit and Scrutiny Committee on 8 May 2024 had been
submitted.
Item 4.
Page 7

Page 8

Councillor McLennan suggested an amendment to the wording of the minute for
Item 8 "National Fraud Initiative 2022-23" in relation to the last paragraph and
recommendation (ii) to accurately record the discussion at the meeting.  He asked
that the wording be amended to read "In response the Chair moved to add an
additional recommendation instructing the Internal Auditor to explore options
around making sure the Council meet the national requirements of the National
Fraud Initiative whilst also ensuring the work is proportionate" and
recommendation (ii) also be changed to reflect the amended wording.  The Chair
confirmed he was in agreement with the suggested change.  
Subject to the amendment above, the Committee agreed the minute of the
meeting.  
5.         Written Questions ** 
The Committee noted that no written questions had been submitted.  
6.         Internal Audit Annual Report - 2023-24 
The meeting had before it a report by the Audit and Risk Manager providing
Committee with a copy of the Internal Audit Annual report for the year ended 31
March 2024, together with the Audit and Risk Manager's opinion on the adequacy
and effectiveness of the Council's system of internal control.  
Councillor Coull asked for an update on the appointment of an Assistant Auditor
and queried if the Audit and Risk Manager will report back to Committee if there is
still insufficient support following the appointment.  In response the Audit and Risk
Manager advised the post had been advertised however it had not been possible
to proceed to interview and he planned to delay re-advertising the post until July or
August after exam results are published in the hope a suitable candidate can be
appointed. 
In response to a question from the Chair relating to the Audit Plan Delivery
performance measure at paragraph 3.6 and whether the target should be reviewed
given that the actual figures for the last two years were higher than the target, the
Audit and Risk Manager agreed to given it consideration when setting future
targets however advised caution had to be exercised given the impact of the
removal of the Corporate Investigation Officer post.    
Councillor Keith referred to the fourth bullet under paragraph 3.4 where it stated
follow-up audits undertaken found that recommendations had yet to be
implemented within the agreed timescales and, taking into account 100% customer
feedback rating the audit as having added value and provided meaningful results,
asked why management was not acting to ensure recommendations were
implemented.  In response the Interim Chief Executive advised he planned to bring
quarterly performance reports within the Corporate Management Team on the
position with outstanding internal and external audit recommendations to increase
performance scrutiny.  The Audit and Risk Manager also stated that delays
sometimes occur in obtaining timely responses to audit queries and
recommendations that can impact the reporting of reviews to this Committee. The
Audit and Risk Manager intends to contact the Chief Financial Officer to include
timescales for officers responding to audit queries and recommendations within the
Financial Regulations.   
Page 8

Page 9

Following consideration the Committee unanimously agreed to note the contents of
the annual report given as Appendix 1.  
7.         Internal Audit Section Update Report 
The meeting had before it a report by the Audit and Risk Manager providing
Committee with an update on the work of the Internal Audit Section.  
The Chair noted it was pleasing to see the vast majority of recommendations had
been implemented however asked there was any indication if the revised
implementation date at 5.05 in Appendix 4 on the Debtors audit would be
achieved.  In response, the Head of Financial Services advised work had been
undertaken to develop the performance management system and she was
confident the August target would be met.  
Councillor McLennan asked whether the audit capacity issues highlighted by the
Audit and Risk Manager at a previous meeting had impacted on the timescales in
the debtors audit or if there were any other areas of work that would be of concern
given the reduced audit capacity.  In response, the Audit and Risk Manager
advised capacity remains a concern to meet the requirements of the audit plan
given the vacancies and work required by the team on the National Fraud
Initiative.  He confirmed a further strain related to having to go back to services to
evidence implementation on recommendations. 
Following consideration the Committee unanimously agreed to note the contents of
the report.  
8.         Internal Audit Section - Completed Projects Report 
The meeting had before it a report by the Audit and Risk Manager advising
Committee on the work of the Internal Audit Section for the period from 8 May
2024 to 25 June 2024.  
Councillor Coull requested more information on what was causing the issues with
direct debits for Fitlife memberships in Appendix 2 relating to the Keith Sports and
Community Centre audit.  In response, the Audit and Risk Manager advised the
direct debit payments are processed through the Council's financial management
system which is separate to the Gladstone system however variances were found
between the two systems.  He confirmed recommendation 5.04 had been
accepted by the service to undertake a full reconciliation.  In the absence of the
Depute Chief Executive (Education, Communities and Organisational
Development), the Head of Governance, Strategy and Performance provided
further information advising that the issue relates to the delay inherent in a manual
system of matching active users to active payers in addition to an approach to give
users time to reinstate their payments rather than remove them which could have
longer term impact in that they are less likely to return to active membership.  The
reconciliation can be improved by purchasing an additional function on the
Gladstone system to automate the process and a request has been submitted to
Finance for funding through the small service investments budget.  
Councillor Gordon asked if there was any way to assess the amount of lost income
given that those turning 18 should be applying for separate memberships and
removed from family membership but noting was no system set up to review
Page 9

Page 10

this.  In response, the Audit and Risk Manager indicated the reconciliation should
provide more accurate information including on loss of income.  
Councillor Macrae expressed concern that the paper was not being heard in the
private session given the paper was highlighting weaknesses in the processes and
details of procurement regulations not being followed.  He further noted only 50%
of the Gladstone system capabilities were being utilised by the Council in that it
was being used only as a booking system.  In response to the public debate
concerns, the Head of Governance, Strategy and Performance advised the role of
the Committee is to focus on improvement and it was important to be open about
the issues so work can be done to improve the system moving forward. 
In response to a question from Councillor Gatt relating to recommendation 5.01 of
Appendix 2 asking for an update on the numbers of those holding petty cash
across all services in the Council, the Head of Financial Services advised there
has been a gradual reduction in the amount of those holding it since the review
started, however was hopeful it was building momentum and services would
realise the benefits of using other methods such as purchasing cards for smaller
purchases.  
The Chair asked whether work requires to be done on the compatibility of Council
systems to reconcile into something more efficient and effective.  In response the
Audit and Risk Manager advised it is a complex area to record data consistently
across so many different services, also noting that resourcing issues have an
impact on time spent developing systems and testing prior to implementation.  The
Head of Governance, Strategy and Performance agreed it would be challenging to
have one system to cover such a wide range of services, whilst acknowledging it
was something to strive towards.   
In response to a question from Councillor Cowe as to whether it was possible to
attribute income received from Fitlife against the running costs of the Keith Sports
and Community Centre to ascertain if the facility was breaking even, the Head of
Governance, Strategy and Performance confirmed the Clerk had confirmed a
question had been raised at Education, Children's and Leisure Services
Committee on 20 June 2024 asking whether it was possible to produce a
breakdown of memberships by facility and an undertaking had been given to look
into that.  
Councillor Morrison left the meeting during discussion of this item.  
Following consideration the Committee unanimously agreed to note the contents of
the report.  
9.         Annual Governance Statement 
The meeting had before it a report by the Interim Chief Executive providing
Committee with a copy of the Council's Annual Governance Statement for 202/24
for review and approval.  
In relation to Section 2 "Ensuring openness and comprehensive stakeholder
engagement" of the Appendix, the Chair noted stakeholder engagement is
generally very good however asked that the statement be amended to include
work done by the Development Plans Team and suggested consistency is required
across all departments.  In response the Interim Chief Executive agreed to amend
the statement accordingly.
Page 10

Page 11

In relation to Section 1 "Behaving with integrity, demonstrating strong commitment
to ethical values, and respecting the rule of law" of the Appendix, Councillor
Macrae noted the last paragraph referenced the Monitoring Officer being
responsible for ensuring compliance with agreed procedures, statutes and
regulation however stated that reference in audits often report on non-
compliance.  In response the Interim Chief Executive confirmed part of the role of
the Committee is to ensure compliance and gave a commitment to ensure
compliance moving forward and would take action if required.  The Head of
Governance, Strategy and Performance advised statute sets out that any breaches
of rules or codes require to be brought to the Council's attention by the Monitoring
Officer however the issues raised had been through due process within the
Council and seeking improvement where necessary which was part of the healthy
governance of the Council.  He further advised if there was not good governance
or scrutiny by the Committee, the Monitoring Officer would bring a report to the
attention of the Council to advise of any particular issue.   
Councillor Gatt noted that whilst scrutiny is important as to identify improvements,
enforcement is also required. In response, the Head of Governance, Strategy and
Performance referred to a previous training session on scrutiny which related to
accountability and stated individuals should be accountable in order to provide
assurance to the Committee.  
In response to a query from Councillor Coull relating to the website not being easy
to navigate and some information being out of date, the Interim Chief Executive
confirmed he would raise the issue at a digital workshop planned for the beginning
of July which was to consider and prioritise IT systems going forward including
investment.    
Following consideration the Committee unanimously agreed to note the draft
Annual Governance Statement provided as Appendix 1.  
10.         Local Government Benchmarking Framework 2022-23 and 2021-22
Results 
The meeting had before it a report by the Depute Chief Executive (Education,
Communities and Organisational Development) presenting to the Committee a
corporate overview of benchmarking performance data for the period 2022-23 and
2021-22.  
The Head of Governance, Strategy and Performance advised the report had
previously been considered by Corporate Committee and the Committee now had
the opportunity to ask any further questions in terms of their overview role.  
Councillor McLennan asked whether future reports could be considered by a joint
Corporate and Audit and Scrutiny Committee or a briefing meeting for both
Committees.  In response the Head of Governance, Strategy and Performance
advised that could be problematic constitutionally however agreed a briefing may
be appropriate for more informal questions or the performance management
framework reporting arrangements could be reviewed.    
Councillor Macrae asked whether it could be considered by Moray Council to give
every Member an opportunity to address the paper.  In response the Head of
Governance, Strategy and Performance advised any paper can be brought before
Moray Council.
Page 11

Page 12

The Head of Governance, Strategy and Performance sought clarification from the
Committee as to whether they were happy to agree the recommendation for this
report and suggested an additional recommended be added to request that future
reporting arrangements are reviewed.    
There being no-one otherwise minded the Committee unanimously agreed to:-  
i) note the Council's performance in terms of a corporate overview of
benchmarking results; and 
ii) make a request for future reporting arrangements to be reviewed.   
Page 12

Page 13

REPORT TO:  AUDIT AND SCRUTINY COMMITTEE ON 11 SEPTEMBER 2024    
SUBJECT:       INTERNAL AUDIT SECTION UPDATE REPORT
BY:                    AUDIT AND RISK MANAGER 
1. REASON FOR REPORT 
1.1 The report provides Committee with an update on the work of the Internal
Audit Section. 
1.2 This report is submitted to Committee in terms of Section III (I) (2) and (8) of the
Council’s Scheme of Administration relating to consideration of reports from the
Council’s Internal Auditor and monitoring delivery of the audit service through
receipt of quarterly reports on work carried out by Internal Audit. 
2. RECOMMENDATION 
2.1 Committee is asked to consider the contents of this report, seek
clarification on any points noted and otherwise note the report. 
3. BACKGROUND 
3.1  Public Sector Internal Audit Standards requires the Audit and Risk Manager to
prepare and present reports to committee on internal audit’s activity,
performance relative to its Audit Plan, and any other relevant matters. 
3.2  This report provides an update on audit activity and projects progressed since
the last meeting.   
4. UPDATE OF PROGRESS AGAINST THE 2024/25 AUDIT PLAN 
Audit Plan Update
4.1 The Internal Audit Plan is a means of determining the priorities of the internal
audit activity and how these fit with the wider goals of the Council. Enclosed
as Appendix 1 is an update on the progress undertaken by the Internal Audit
Section regarding the completion of audit review projects against the Annual
Audit Plan. 
4.2 In addition to the requirement for completing projects detailed within the Annual
Audit Plan, a review has also been undertaken of the Grampian Valuation Joint
Board. Internal Audit is required to provide annual assurances on the main
Item 6.
Page 13

Page 14

financial systems operated for payroll, payments and income from funding
requisitions from the constituent authorities and other sources. The Joint
Board’s systems align with those of the Council but require annual review and
testing in order to provide assurances for the separate annual financial
statements the Board is required to prepare and publish. It is pleasing to report
that based on the audit work completed, reasonable assurance can be placed
on the adequacy and effectiveness of the system of internal financial control
established within the Assessor’s Service 
Audit Plan 2025/26
4.3 It is planned to shortly begin the preparation for the Annual Audit Plan for
2025/26. Internal Audit’s approach to annual audit planning is risk-based, with all
areas subject to audit review contained within an ‘audit universe.’ The audit
universe is reviewed and updated on an ongoing basis to include all significant
activities and systems. 
4.4 In accordance with the Public Sector Internal Audit Standards, it is the
responsibility of the Audit and Risk Manager to prepare the Annual Audit Plan.
However, consultation on projects for review will be undertaken with senior
officers and members of the Audit and Scrutiny Committee. In addition, this will
also provide the opportunity to remind officers of established timescales for
responding to requests for information during an audit review and to the
recommendations within the audit report. However, I do appreciate the
significant workload demands on officers and will always try to accommodate
any requests for timescale changes in reporting arrangements.   
Follow Up Reviews
4.5 Internal Audit reports are regularly presented to Elected Members detailing not
only findings but also the responses by management to the recommendations
with agreed dates of implementation. Internal Audit will also undertake follow up
reviews to evidence the effective implementation of these recommendations.
Please see detailed the following completed follow up reviews: 
Refugee Integration Scheme  
4.7 An audit has previously been undertaken to review the Refugee Integration
Scheme. The scope of the audit was a review of the financial and administrative
processes involved in delivering the Ukrainian Refugee Scheme. The emerging
Asylum Dispersal, Afghan Citizens Resettlement Scheme and Afghan Relocation
& Assistance Policy Scheme did not form part of the audit testing due to limited
activity at the time of the review. The Council has supported approximately 140
Ukrainian displaced persons, with allocated funding from the Central
Government in 2022/23 of over £1.9 million spread across the Warm Scottish
Welcome Fund, Tariff per Displaced Person funding, Host Thank You Payment
Funding and Educational Tariff Funding. All these funds have specific
requirements and the audit has reviewed the accounting arrangements for
administering these schemes and the claiming of expenditure. The Follow Up
Report to review the implementation of the agreed recommendations is given
in Appendix 2. 
Building Services Stores 
4.8 This follow up review checked the implementation of recommendations within
the Building Services Stores audit report. The scope of the audit reviewed the
systems and controls in managing materials and equipment (stock) stored to
Page 14

Page 15

meet the repairs and maintenance requirements of Council housing. It was noted
that individual stock items varied in value from a few pounds to upwards of
£1,000. Materials and equipment with a cumulative value of approximately
£700,000 are issued annually from Stores. A previous follow up review has been
undertaken that required revised dates to be agreed for the implementation of
some of the recommendations. However, it is now pleasing to report that all
recommendations have been implemented.  The Follow Up Report is given
in Appendix 3. 
5 SUMMARY OF IMPLICATIONS 
(a) Corporate Plan and 10 Year Plan (Local Outcomes Improvement
Plan (LOIP))
Internal audit work supports good governance and the delivery of
efficient services. 
(b) Policy and Legal
No implications directly arising from this report. 
(c) Financial Implications
No implications directly arising from this report. 
(d) Risk Implications
The independent review of selected systems and procedures mitigates
the risk associated with inadequate or ineffective control procedures. 
(e) Staffing Implications
No implications directly arising from this report. 
(f) Property
No implications directly arising from this report. 
(g) Equalities/Socio Economic Impact
No implications directly arising from this report. 
(h) Climate Change and Biodiversity Impacts 
No implications. 
(i) Consultations
There have been no direct consultations during the preparation of this
report. 
6. CONCLUSION 
6.1 This report provides committee with an update on internal audit work
progressed in the latest review period. 
Author of Report:
Background Papers: 
Dafydd Lewis
Internal Audit files
Audit and Risk Manager 
Ref:     
Page 15

Page 16

Page 16

Page 17

APPENDIX 1 
MORAY COUNCIL 
INTERNAL AUDIT SERVICE 
ANNUAL AUDIT PLAN 2024/25 
CORE FINANCIAL SYSTEMS  
Area Type of coverage Status/ Comments
Payroll   Continuous auditing to confirm the
adequacy of the systems and
procedures for the payment of salaries.
Audit programmed to start in the next
quarter(s)
Procurement and Creditor Payments  Continuous auditing of samples of non-
pay expenditure to test compliance with
procurement and payment processing
regulations.
Completed
ICT Hardware Asset  Management review of systems and
practices to record / monitor the location
and use of ICT hardware. 
Audit programmed to start in the next
quarter(s)
Stocks and stores - year end valuations    Attendance at stocktaking and
reconciliation of stocks held to ledger
balances.
Year end stock valuations agreed
OTHER SYSTEMS  
Area Type of coverage 
Housing and Property Reactive
Maintenance Works 
Audit of works undertaken within
Building Services for the completion of
reactive maintenance works (Council
Housing). 
Audit programmed to start in the next
quarter(s)
Grant Claims Certification of grant claims as required:
strategic timber; network support grant,
regeneration schemes as appropriate
Network Support Grant audit completed
and claim submitted to Transport
Item 6.
Page 17

Page 18

Scotland for period- 1/4/23 to
30/09/2023
Housing Rent Collection & Arrears
Management
A review of the income collection and
accounting arrangements for housing
rents. 
Fieldwork in progress
Moray Growth Deal  An audit review of the governance and
administrative procedures within the
Council for the management of the
Moray Growth Deal. The scope will
include the concerning partnership
working, financial management and
measuring success. 
Fieldwork in progress
Education – Secondary School Establishment visits as part of cyclical
review.
Audit programmed to start in the next
quarter(s)
Treasury Management  To provide assurance that processes
and controls are continuing to operate
effectively for the Council's treasury
management system.  
Audit programmed to start in the next
quarter(s)
Commercial Refuse Collection  To consider whether adequate control is
in place covering trade waste income
and expenditure, that appropriate
agreements and other paperwork is in
place, and that accounting arrangements
are robust.
Completed
Governance arrangements to prevent
Fraud and Corruption 
Overview of the Councils governance
arrangements to prevent fraud and
corruption. The audit will use the Cipfa
Code of practice on managing the risk of
fraud and corruption as the basis in
developing the audit programme for the
review.
Fieldwork in progress
Page 18

Page 19

Education- Secondary School Premises
Security
Review the controls in place to mitigate
the risk of unauthorised access to
Secondary School Premises.
Audit programmed to start in the next
quarter(s)
Absence Management An audit to consider the effectiveness of
sickness absence monitoring and
reporting. 
Audit programmed to start in the next
quarter(s)
Following the Public Pound To ensure that there is proper
accountability for public funds used in
delivering services, irrespective of the
means of service delivery.
Completed
Moray Integration Joint Board   
Residential Care An audit to review the adequacy of
procedures and administrative
arrangements regarding the third party
suppliers appointed to provide care
home services The audit will also include
testing to verify the accuracy of the
financial assessments and the charging
for residential care of both respite and
permanent care residents.  
Audit programmed to start in the next
quarter(s)
Out of area placement A review of the systems and procedures
regarding adult services users that are
out of area but responsibility remains to
meet their eligible care and support
needs under the Care Act.  
Fieldwork in progress
Fostering and Kinship payments A review to ensure that the internal
controls in place for administering
Fostering and Kinship Care Allowances
are operating effectively. 
Completed 
Page 19

Page 20

Follow Up reviews to be undertaken
from previous  Audit Assignments *
Audit Review: Original Scope Status/ Comments
Business Continuity  The audit reviewed the Council's Business
Continuity arrangements to confirm up to date
policies, procedures and plans are regularly
tested and reviewed, and that an appropriate
level of awareness of Business Continuity is held
throughout the organisation.
Follow Up Review completed.
Governance, Strategy and Performance
Service Plan is now updated with a
requirement for the Business Continuity
and Risk Management Officer to monitor
the progress by services to ensure
business continuity arrangements are
kept up to date. This work is an ongoing
process and has regard to new risks and
issues that have the potential to impact
or disrupt service delivery. 
Self Directed Support (SDS) – Option 1 This audit remit was to review Option 1 Direct
Payments under the SDS scheme, where a
payment is made by the local authority directly to
a supported person for the provision of support.
The scope of the audit was to ensure compliance
with operating guidelines in the financial
management of SDS packages, expenditure
incurred is in accordance with the agreed budget
and support plans, and surplus funds are
recovered from service users where appropriate.
Follow Up Review programmed to start
in the next quarter(s) 
Self Directed Support (SDS) – Option 2/3  The scope of the audit was to review systems
and procedures in the delivery and management
of adult social care provided under Options 2 and
3 of the SDS scheme. This included examination
of the processes to support individuals in
determining their preferred care delivery option,
contractual relationships with care providers,
financial management and monitoring of
individual care packages. 
Follow Up Review programmed to start
in the next quarter(s) 
Building Services - Planned
Maintenance Projects
An overview was undertaken of how the annual
planned maintenance programme is determined
and the contract management arrangements of
Follow Up Review programmed to start
in this quarter
Page 20

Page 21

these projects by Building Services. The audit
also involved a random selection of projects to
verify costs can be evidenced to supporting
documentation. Additional testing was also
undertaken of the systems regarding the
management and control of overtime paid to
officers. 
Emergency Planning The objective of this audit was to provide
assurance over the adequacy and effectiveness
of current controls over emergency planning. The
audit scope included a check to ensure adequate
training, planning and testing has been
developed in the event of an emergency.
Follow Up Review programmed to start
in the next quarter(s) 
Refugee Integration Scheme The scope of this audit involved a review systems
and procedures to account for the relatively new
and increasing source of funding for national
humanitarian protection schemes. This audit has
specifically covered the financial and
administrative processes involved in the
operation of the Ukrainian Refugee Scheme. 
Completed 
Building Services - Stores  This audit scope reviewed the systems and
controls in managing stock held within Building
Services Stores. Testing involved a review of the
stores software application called Servitor used
for the recording and valuation of materials and
equipment. Testing also included a check of the
security arrangements to safeguard against
unauthorised access to the storage areas. 
Completed 
Debtors The audit scope was to review the key
operational controls within the Council's Debtors
System. The audit checked the systems for
raising invoices, collecting income, recording
income and debt recovery arrangements. The
audit review did not include the arrangements for
recovering debts concerning council tax, non
domestic rates, and housing rents.
Follow Up Review programmed to start
in the next quarter
Domestic Refuse Collection  The scope of this audit was to review systems
and procedures to ensure the most effective and
Follow Up Review programmed to start
in the next quarter(s)
Page 21

Page 22

efficient use is made of resources for the
collection of domestic waste. The audit also
checked the arrangements for disposing of
recyclable waste. This included disposal of
plastic, glass and biodegradable waste, in
addition to paper / card, aluminium and steel
cans for which the Council received regular
payments from recycling contractors. 
Pool Cars Scheme The scope of this audit was to review systems
and procedures in the management and use of
pool cars. Policies and procedures were checked
to ensure they provide appropriate operating
guidance to officers in the booking and use of
pool cars. The audit included a review of
arrangements for internal recharging to services
and also exploration if further use of pool cars
could provide additional value for money
opportunities to the Council.
Follow Up Review programmed to start
in the next quarter(s) 
Cyber Security The audit reviewed systems, practices and an
assessment of the controls in place to protect the
Council from a cyber-attack. The audit also
reviewed Information, Communication and
Technology (ICT) security policies and
procedures to ensure they are regularly reviewed
and promote best practices. The audit
programme has been developed from the
Scottish Government Cyber Resilience
Framework and other good practice guidelines.
Follow Up Review programmed to start
in the next quarter(s) 
Moray Integrated Community Stores The audit reviewed the management of the
Moray Integrated Community Stores. This
included reviewing the procedures for ordering
and issuing occupational therapy equipment to
service users. In addition, a check was made to
compare stock records to the actual equipment
held within the Stores.  
Follow Up Review programmed to start
in the next quarter(s) 
Forres Academy The audit reviewed the operation of the Devolved
School Management Scheme regarding the
allocation of funding and the management of
Follow Up Review programmed to start
in the next quarter(s) 
Page 22

Page 23

these funds at the school level. The review
involved a study of the management of the
significant staffing costs involved in delivering the
curriculum, a review of procurement practices, an
examination of the School's administration of
income and also confirming accountability for
School Fund monies.
Email Security  The audit checked the system controls and
supporting policies and procedures used to
administer the Council's email system. The audit
also reviewed the arrangements for risk
identification and actions undertaken to protect
the Council from phishing emails. In addition, in
response to a request from an elected member,
the audit included a review of the password
management controls for members access to the
Council networks and systems.
Follow Up Review programmed to start
in the next quarter(s) 
Keith Sports & Community Centre  The audit scope reviewed the processes and
procedures in place at the Keith Sports and
Community Centre and evaluate the
effectiveness of internal controls relating to
income and expenditure. This involved the
sample testing of individual transactions to
ensure compliance with Regulations and
Guidelines. In addition, an appraisal of working
practices was also undertaken to assess if the
Service was maximising the income due to the
Council
Follow Up Review programmed to start
in the next quarter(s) 
Environmental Services- Stores  This audit reviewed the systems and controls in
managing stock held within Environmental &
Commercial Services Stores. The audit used the
Chartered Institute of Public Finance
Accountants audit programme to review the
systems and controls in managing stock held
within stores. Testing also included a review of
the security arrangements to safeguard against
unauthorised access to the storage areas
Follow Up Review programmed to start
in the next quarter
Page 23

Page 24

Purchasing Cards  The audit scope for this review was to assess the
key controls and processes in place covering the
usage of purchasing cards. The audit included a
review of purchasing card guidelines and testing
the controls operating over the key processes of
purchase card applications, issue of cards,
usage, authorisation and VAT accounting
arrangements. Monitoring undertaken to ensure
compliance with regulations, policies and
procedures has also been undertaken, in
addition to the reconciliation of purchasing card
transactions detailed within the payment card
system to the Council's Financial Management
System
Follow Up Review programmed to start
in the next quarter 
* Additional follow up reviews may be reported depending on the implementation dates detailed by Services for recommendation 
Page 24

Page 25

APPENDIX 2
Moray Council
Internal Audit Section
DEPARTMENT: Economy, Environmental and Finance
SUBJECT:  Refugee Integration Scheme 
REPORT REF: 24'008 
Follow Up Audit Review 
Risk Ratings for Recommendations
High Key controls absent, not being
operated as designed or could be
improved. Urgent attention required.
Medium Less critically important controls
absent, not being operated as
designed or could be improved.
Low Lower level controls absent, not
being operated as designed or
could be improved.
No. Audit Recommendation Priority Accepted
(Yes/ No)
Date of
Completion
Status / Explanation
Key Control: Grant funding is effectively managed, monitored and applied for the intended purpose
5.01 A consolidation exercise should
be undertaken to identify all
expenditure and designate as
costs being met from the available
funding. A standard  financial
monitoring process should
thereafter be put in place to
ensure funding and its usage is
High Yes 01/12/2023 Implemented. Significant analysis has been
undertaken since the initial audit to identify all
relevant costs of supporting refugee
resettlement. A tailored funding monitoring
report is prepared by Accountancy and issued
to the Service on a monthly basis to allow
effective budget management.   
Item 6.
Page 25

Page 26

Moray Council
Internal Audit Section 
2
Risk Ratings for Recommendations
High Key controls absent, not being
operated as designed or could be
improved. Urgent attention required.
Medium Less critically important controls
absent, not being operated as
designed or could be improved.
Low Lower level controls absent, not
being operated as designed or
could be improved.
No. Audit Recommendation Priority Accepted
(Yes/ No)
Date of
Completion
Status / Explanation
reported and effectively monitored
by the service on a monthly basis. 
5.02 Ongoing financial forecasting
should be undertaken to allow
more informed management
decisions to be taken and ensure
the full potential of the available
funding is utilised.   
High Yes 01/12/2023 Implemented. Financial forecasting for
2024/25 and 2025/26 has been undertaken
and is now embedded as part of the monthly
financial monitoring process to quantify future
commitments and inform service planning. 
5.03 Improved consolidation of
documentation regarding funding
awards and related submissions
requires to be undertaken to
ensure the service holds the full
complement of final version
documents for clarity and
completeness.   
Low Yes 01/11/2023 Implemented. All relevant documentation is
now saved within the Section’s electronic
folders and storage points. A greater degree of
communication was also found between the
Service and the Accountancy Section, with
Accountancy now having an oversight role to
validate financial information submitted for
claims and aid reconciliations. 
Page 26

Page 27

Moray Council
Internal Audit Section 
3
Risk Ratings for Recommendations
High Key controls absent, not being
operated as designed or could be
improved. Urgent attention required.
Medium Less critically important controls
absent, not being operated as
designed or could be improved.
Low Lower level controls absent, not
being operated as designed or
could be improved.
No. Audit Recommendation Priority Accepted
(Yes/ No)
Date of
Completion
Status / Explanation
5.04 In establishing the new Asylum,
Refugee and Resettlement
Section, the temporary
employment contracts currently in
place for team members should be
reviewed and aligned consistently
to funding terms. 
Low Yes 31/03/2024 Implemented. Employment contracts of the
team have been reviewed and aligned since
the initial audit. Furthermore, per reporting to
the Moray Council on 22nd May 2024 (Item 11),
a review of the current staffing requirements of
the Refugee Resettlement Team is to be
undertaken to determine necessary resourcing
for anticipated future support, resettlement and
integration activities with the intention of a
further report to the Committee later in 2024. 
5.05 Petty cash reimbursement claims
submitted must be based on
actual expenditure incurred and
always reconcile to the authorised
petty cash imprest for the section. 
Medium Yes 30/09/2023 Implemented. Since the agreement of the
audit in August 2023, petty cash
reimbursement claims submitted have been
made from actual expenditure and supported
by appropriate documentation. It was also
noted that an adjustment to the authorised
petty cash imprest amount was undertaken in
Page 27

Page 28

Moray Council
Internal Audit Section 
4
Risk Ratings for Recommendations
High Key controls absent, not being
operated as designed or could be
improved. Urgent attention required.
Medium Less critically important controls
absent, not being operated as
designed or could be improved.
Low Lower level controls absent, not
being operated as designed or
could be improved.
No. Audit Recommendation Priority Accepted
(Yes/ No)
Date of
Completion
Status / Explanation
November 2023, and petty cash claims now
reconcile to the authorised imprest amount. 
5.06 Expenditure incurred through the
petty cash fund, other than the
cash Welcome Payments, should
comply with Council procedure of
no single item exceeding £10.
Alternative standard procurement
routes should be used for any
higher value purchases. Receipts
for all expenditure incurred should
be submitted with petty cash
reimbursement claims to account
for purchases and ensure input
VAT is recovered where
applicable. 
Medium Yes 01/12/2023 Implemented. Since the audit, petty cash has
only been used for cash Welcome Payments.
Purchasing cards are now used by the
Service.   
5.07 To improve the audit trail, the Low Implemented  Implemented. The master record has been
Page 28

Page 29

Moray Council
Internal Audit Section 
5
Risk Ratings for Recommendations
High Key controls absent, not being
operated as designed or could be
improved. Urgent attention required.
Medium Less critically important controls
absent, not being operated as
designed or could be improved.
Low Lower level controls absent, not
being operated as designed or
could be improved.
No. Audit Recommendation Priority Accepted
(Yes/ No)
Date of
Completion
Status / Explanation
master record of hosts and guests
should be amended to ensure the
date of arrival which is relevant to
the initial host payment calculation
is clearly recorded. 
Additionally, all payment
calculations which relate to less
than a full month of hosting should
be checked to confirm accuracy
prior to payment processing. 
amended as recommended to clarify the date
of a guest's arrival with the host, from which
payment will be made. A new process has also
been implemented and documented for
undertaking partial month calculations to
ensure consistency in application and involves
a check by two officers. 
5.08 Welcome Hub costs sought for
reimbursement by central
government should be calculated
based on actual expenditure
incurred and require to be
appropriately evidenced.   
Low Yes 31/10/2023 Implemented. No Welcome Hub costs have
been incurred by the Authority since the initial
audit. However, were this to be a feature of any
future resettlement scheme, the Service is 
aware of the process to be followed and would
involve the Accountancy Section in preparing
any summary of costs to be invoiced for
Page 29

Page 30

Moray Council
Internal Audit Section 
6
Risk Ratings for Recommendations
High Key controls absent, not being
operated as designed or could be
improved. Urgent attention required.
Medium Less critically important controls
absent, not being operated as
designed or could be improved.
Low Lower level controls absent, not
being operated as designed or
could be improved.
No. Audit Recommendation Priority Accepted
(Yes/ No)
Date of
Completion
Status / Explanation 
reimbursement.   
Page 30

Page 31

APPENDIX 3
Moray Council
Internal Audit Section
DEPARTMENT: Economy, Environment & Finance
SUBJECT: Building Services - Stores
REPORT REF: 22'019 
Follow Up Audit Review 
Risk Ratings for Recommendations
High Key controls absent, not being
operated as designed or could be
improved. Urgent attention required.
Medium Less critically important controls
absent, not being operated as
designed or could be improved.
Low Lower level controls absent, not
being operated as designed or
could be improved.
No. Audit Recommendation Priority Accepted
(Yes/ No)
Date of
Completion
Status / Explanation
Key Control: Review of the Building Services Stores to ensure effective controls are operating in the management and control of materials and equipment.
5.01 Building Services equipment and
materials purchased as a direct order
for specific schemes and stored at
the Depot should be recorded within
Servitor. 
Medium Yes 31/03/2023 Implemented. Testing has confirmed that
items purchased for direct orders but stored
within the Depot are now recorded on Servitor   
Item 6.
Page 31

Page 32

Moray Council
Internal Audit Section 
2
Risk Ratings for Recommendations
High Key controls absent, not being
operated as designed or could be
improved. Urgent attention required.
Medium Less critically important controls
absent, not being operated as
designed or could be improved.
Low Lower level controls absent, not
being operated as designed or
could be improved.
No. Audit Recommendation Priority Accepted
(Yes/ No)
Date of
Completion
Status / Explanation
5.02 Higher value items should be stored
whether possible in alarmed storage
areas. 
Medium Yes 31/05/2022 Implemented. The follow up review visit has
confirmed that high value items are now stored
within alarmed areas.
5.03 Officers should be reminded that
greater care should be taken to
record items received and issued
within Servitor. 
Medium Yes  30/06/2022 Implemented. A barcoding system is now in
place reducing the need to manually enter item
numbers when receiving and issuing stock.
5.04 All materials and equipment recorded
within Servitor should be updated
with minimum and maximum stock
levels. This should assist in the
effective management of stock levels
at the appropriate levels. 
Low Yes 31/03/2022
Revised
Implementation
date 30/06/2024 
Implemented. Individual maximum and
minimum stock levels have been assigned to
all regularly issued stock items within the
Servitor system.   Regarding the slow moving
stock, a standard minimum and maximum
stock level has been established, which will be
reviewed when re-ordering an item. 
5.05 Contracts should be agreed with
companies used regularly for the
supply of goods and materials where
Medium Yes  31/03/2023
Revised
Implemented. Testing undertaken as part of
the follow-up review has confirmed that the
Service uses national frameworks or local
Page 32

Page 33

Moray Council
Internal Audit Section 
3
Risk Ratings for Recommendations
High Key controls absent, not being
operated as designed or could be
improved. Urgent attention required.
Medium Less critically important controls
absent, not being operated as
designed or could be improved.
Low Lower level controls absent, not
being operated as designed or
could be improved.
No. Audit Recommendation Priority Accepted
(Yes/ No)
Date of
Completion
Status / Explanation
annual expenditure exceeds the
Quick Quote threshold of £5000.
Implementation
date 30/06/2024
contacts to purchase goods and services
where cumulative expenditure to a supplier is
in excess of £5,000. The Service is also
reviewing on an ongoing basis all payments
made to off-contract suppliers to determine
whether there is a need for a more formal
contractual relationship. 
Page 33

Page 34

Page 34

Page 35

REPORT TO:    AUDIT AND SCRUTINY COMMITTEE ON 11 SEPTEMBER 2024 
SUBJECT: INTERNAL AUDIT REVIEW – PROCUREMENT AND CREDITOR
PAYMENTS 
BY: AUDIT AND RISK MANAGER 
1. REASON FOR REPORT 
1.1 The report advises Committee on an internal audit review completed for the
period from 25 June 2024 to 11 September 2024. 
1.2 This report is submitted to Committee in terms of Section III (I) (2) and (8) of
the  Council’s Scheme of Administration relating to consideration of reports
from the Council’s Internal Auditor and monitoring delivery of the audit
service through receipt of quarterly reports on work carried out by Internal
Audit. 
2. RECOMMENDATION 
2.1 That Committee consider the contents of this report, seeks clarification
on any points noted and otherwise notes the report. 
3. BACKGROUND 
3.1     This report provides details the internal audit review completed of Procurement
and Creditor Payments during the period 25 June 2024 to 11 September 2024: 
Procurement and Creditor Payments   
3.2     Part of the annual audit plan is devoted to main financial systems, including
creditor payments that cover non-payroll expenditure, i.e. payment for works,
goods and services to suppliers or contractors. The purpose of the audit was
to confirm ongoing compliance with Financial, Authorisation, Procurement and
Creditor Payment Processing Regulations. 
3.3 Testing was undertaken using a data analysis software application to extract a
random sample of transactions for review. A check for duplicate payments was
also carried out by extracting listings where more than one invoice from a
single supplier had been paid for the same amount. Findings from the review
noted issues concerning the need for improved clarification regarding the
Budget Manager’s responsibilities in authorising expenditure and for the further
development of the Authorisation Database.  The audit report for this project is
given in Appendix 1.
Item 7.
Page 35

Page 36

4.        SUMMARY OF IMPLICATIONS 
(a) Corporate Plan and 10 Year Plan (Local Outcome Improvement Plan
(LOIP))
Internal audit work supports good governance and the delivery of
efficient services. 
(b) Policy and Legal
No implications. 
(c) Financial Implications
No implications directly arising from this report. 
(d) Risk Implications
The independent review of selected systems and procedures mitigates
the risks associated with inadequate or ineffective control procedures. 
(e) Staffing Implications
No implications. 
(f) Property
No implications. 
(g) Equalities/ Socio Economic Impacts
No implications. 
(h) Climate Change and Biodiversity Impacts
No implications. 
(i) Consultations
There have been no direct consultations during the preparation of this
report. 
5.        CONCLUSION 
5.1 This report provides Committee with a summary of findings arising from           
an audit project completed during the review period. 
Author of Report:            Dafydd Lewis, Audit and Risk Manager
Background Papers:       Internal audit files 
Ref:                                 
Page 36

Page 37

APPENDIX 1 
Internal Audit Report 
Procurement and Creditor Payments  
June 2024   
Distribution: Chief Financial Officer 
Assistant FMS & Banking Manager 
The Internal Audit Section provides Management with an opinion on the internal control
environment and also categories risk ratings for recommendations as high, medium or low
(detailed explanation provided in Appendix1). The audit recommendations for this review have
been classified as follows 
Assurance Level
Risk Ratings for
Recommendations 
Priority 1   0     
Substantial Priority 2   2     
Priority 3   0     
Confidentiality and Disclosure Clause 
This report (“Report”) was prepared by the Internal Audit Section of Moray Council. The matters raised in this Report are
only those which came to our attention during our internal audit work. Whilst every care has been taken to ensure that the
information provided in this Report is as accurate as possible, the Moray Council Internal Audit Section has only been able
to base findings on the information and documentation provided and consequently, no complete guarantee can be given
that this Report is necessarily a comprehensive statement of all the weaknesses that exist, or of all the improvements that
may be required. 
This Report was prepared solely for the use and benefit of the Moray Council, Moray Integration Joint Board or the
Grampian Valuation Joint Board. Moray Council's Internal Audit Section accepts no responsibility and disclaims all liability
to any third party who purports to use or rely for any reason whatsoever on the Report, its contents, conclusions, any
extract, reinterpretation, amendment and/or modification. Accordingly, any reliance placed on the Report, its contents,
conclusions, any extract, reinterpretation, amendment and/or modification by any third party is entirely at their own risk. 
Please refer to the Statement of Responsibility in Appendix 2 of this report for further information about
responsibilities, limitations and confidentiality.   
Contents 
Page
Procurement and Creditor Payments 
1. Introduction & Scope 3
2. Key Issues  4
Item 7.
Page 37

Page 38

2 
Detailed Report 
3. Findings/Recommendations 5-6
4. Management Response 5-6 
Appendices 
1. Audit Terms of Reference and Definitions 
2. Statement of Responsibility 
1. Introduction and Audit Scope  
Page 38

Page 39

3 
The Annual Audit Plan for the year 2024/25 provides for coverage of the
Council’s core financial systems. A review of payments made to suppliers of
goods and services has been undertaken. The purpose of the audit was to
confirm compliance with Financial, Authorisation, Procurement and Creditor
Payment Processing Regulations from the sample checked. This review is
part of the annual continuous auditing activity of non-salary expenditure and
will be used to support the Audit and Risk Manager’s annual opinion of the
Council’s internal control system. 
Approximately £80 million was paid by the Council in the six months,
October 2023 to March 2024, to suppliers of goods and services. Through
the use of a data analysis software application, a random sample of
individual payments with a collective total of £11.3 million was selected. The
testing included a check to ensure invoices have been correctly authorised,
coded and in compliance with regulations. The audit programme was
developed from the Chartered Institute of Public Finance and Accountancy
Systems Based Auditing Control Matrices and in consultation with the
External Auditor. In addition, the data analysis software application was also
used to select a sample of high-value invoices to test, and a check made of
identical payment amounts made to the same supplier, which may indicate a
potential duplicate payment. 
From the sample checked and within the scope of the review, no issues of
significant concern were noted regarding the suppliers/ contractors used,
sums paid, authorisation and accounting treatment.  It is considered that
appropriate controls are operating effectively, and the integrity of systems
has been maintained. However, the review has found where further
improvements are recommended to operating and administrative
arrangements. 
The audit was carried out in accordance with Public Sector Internal Audit
Standards (PSIAS). 
Page 39

Page 40

4 
2. Key Issues 
• The Council Authorisation Policy details the management and operating
requirements for officers to follow when committing expenditure on
behalf of the Council. This Policy allows officers to be designated as
Budget Managers with the operational responsibility of actively
managing services. However, within the Policy, a provision is also
made for a named officer to act as an ‘In Absence Authoriser’ to allow
services to function effectively in the absence of the Budget Manager.
Audit testing found where an ‘In Absence Authoriser’ had authorised
the majority of invoices processed within a specific budget area, with
examples of authorisation of individual transactions in excess of
£100,000. The Authorisation Policy should be updated to clearly detail
that a Budget Manager should initially authorise expenditure with an “In
Absence Authoriser’ function only used on an exception basis. 
• This audit required reference to the Authorisation Database to evidence
that the appropriate officer had authorised expenditure with budget
management responsibility. The Authorisation Database is a
standalone software application that requires significant manual
updating of records by officers to remain operationally current.  In
addition, the Authorisation Database does not interface with the
Financial Management System. The Authorisation Database is an
important reference record to ensure the Council maintains effective
budget management and monitoring arrangements. The Finance
Development Team has recognised the limitations of the Authorisation
Database, however software development has been restricted due to
available staff resources.   
Page 40

Page 41

5 
Procurement and Creditor Payments- 2024/25 
Ref Risk Ratings for
Recommendations
Audit Finding Audit Recommendation
1. Medium Audit testing was undertaken on a random sample
of payments to suppliers/ contractors to ensure
that expenditure had been authorised in
accordance with the Council’s Authorisation
Policy. The Authorisation Policy provides for
officers to be designated as Budget Managers
with the authority to commit expenditure in the
operational delivery of services. However, the
Policy details a provision for a named officer to act
as an ‘In Absence Authoriser’ to allow a service to
function effectively in the absence of the Budget
Manager. Audit testing noted where an ‘In
Absence Authoriser’ had authorised the majority
of invoices processed within a specific budget
area, with examples of individual authorisation of
individual transactions in excess of £100,000. 
The Authorisation Policy should be updated
to provide greater clarity that the Budget
Manager should initially make the
authorisation of expenditure and an “In
Absence Authoriser’ function only be used
on an exception basis. 
Management Response
Responsible Officer Accepted
(Yes/ No)
Timescale for
Implementation
(Date Required) 
Agreed Management Action/Management Comment
Chief Financial Officer Yes 31/12/2024 This will be updated at the next review date.  Last review
date of the authorisation policy was Sept 23.
Page 41

Page 42

6 
Ref Risk Ratings for
Recommendations
Audit Finding Audit Recommendation
2. Medium An Authorisation Database is maintained by
Finance Services detailing the names and
signatures of officers with budget management
responsibility that can authorise expenditure
within specific service areas. The Authorisation
Database system is over 20 years old and
requires significant manual administration to
ensure it remains operationally up to date. In
addition, the database does not interface with the
Financial Management System. The Finance
Development Team has recognised the limitations
of the Authorisation Database, however
development has been constrained due to
available staff resources. 
Further development of the Authorisation
Database should be undertaken to enable
an interface with the Financial
Management System and allow a more
automated process for updating standing
information.
Management Response
Responsible Officer Accepted
(Yes/ No)
Timescale for
Implementation
(Date Required) 
Agreed Management Action/Management Comment
Chief Financial Officer Yes 31/12/2025 This is part of a wider authorisation review currently with
the Finance Development Group.  Interdependencies will
be duly considered as part of this development. 
Page 42

Page 43

7 
Appendix 1 
AUDIT TERMS OF REFERENCE AND DEFINITIONS 
1. Audit Objectives 
1.1 The overall audit objective is to provide an objective independent opinion on
the adequacy and effectiveness of controls / processes.  
1.2 The audit will for each controls / process being considered: 
• Walkthrough the processes to consider the key controls; 
• Conduct sample testing of the identified key controls, and 
•    Report on these accordingly 
1.3 All audit reviews are carried out in accordance with Public Sector Internal
Audit Standards (PSIAS). 
2. Definitions for Auditing Opinions and Findings 
2.1 In order to assist management in using our reports: 
The Internal Auditor will categorise audit assurance opinion according to
their overall assessment of the risk management system, effectiveness of the
controls in place and the level of compliance with these controls and the
action being taken to remedy significant findings or weaknesses. 
Assurance
Level
System and Testing Conclusion
Full The controls tested are being consistently applied
Substantial There is evidence that the level of non compliance with some of
the controls may put some of the system objectives at risk.
Limited The level of non compliance puts the system objectives at risk.
None Significant non-compliance with basic controls leaves the system
open to error or abuse. 
2.2 Risk ratings for each recommendation is based on the following criteria: 
High Fundamental control weaknesses that require immediate attention
by management to action and mitigate significant exposure to risk
Medium Less critically important controls absent, not being operated as
designed or could be improved
Low Lower level controls absent, not being operated as designed or
could be improved.
Page 43

Page 44

8 
Appendix 2 
STATEMENT OF RESPONSIBILITY   
The responsibility for designing and maintaining a sound system of internal control
to prevent and detect fraud and other irregularities rests with management, with
internal audit providing a service to management to support them to achieve this
objective. The Internal Audit Section will assess the adequacy and effectiveness of
the system of internal control arrangements implemented by management and
perform sample testing on those controls in the period under review with a view to
providing an opinion on the extent to which risks in this area are managed. 
The Internal Audit Section will undertake testing with the objective of detecting
significant control weaknesses. However, the audit approach alone should not be
relied upon to identify all strengths and weaknesses in internal controls nor to find
any fraud or irregularity. Even sound systems of internal control can only provide
reasonable and not absolute assurance and may not be proof against collusive
fraud. 
The matters raised in this report are only those that came to our attention during
the course of the audit review and are not necessarily a comprehensive statement
of all the weaknesses that exist or all improvements that might be made.
Recommendations for improvements should be assessed by management for their
full impact before they are implemented. The performance of the audit review
undertaken should not be taken as a substitute for management’s responsibilities
for the application of sound management practices. 
This report is confidential and must not be disclosed to any third party or
reproduced in whole or in part without the written consent of the Moray Council’s
Audit and Risk Manager. 
Page 44

Page 45

REPORT TO:    AUDIT AND SCRUTINY COMMITTEE ON 11 SEPTEMBER 2024 
SUBJECT: INTERNAL AUDIT REVIEW – FOLLOWING THE PUBLIC POUND 
BY: AUDIT AND RISK MANAGER 
1. REASON FOR REPORT 
1.1 The report advises Committee on an internal audit review completed for the
period from 25 June 2024 to 11 September 2024. 
1.2 This report is submitted to Committee in terms of Section III (I) (2) and (8) of
the  Council’s Scheme of Administration relating to consideration of reports
from the Council’s Internal Auditor and monitoring delivery of the audit
service through receipt of quarterly reports on work carried out by Internal
Audit. 
2. RECOMMENDATION 
2.1 That Committee consider the contents of this report, seeks
clarification on any points noted and otherwise notes the report. 
3. BACKGROUND 
3.1 This report provides details of the internal audit review completed during the
period 25 June 2024 to 11 September 2024 regarding the Council’s
arrangements for Following the Public Pound: 
Following the Public Pound   
3.2      A “Following the Public Pound” review has been undertaken to ensure proper
accounting arrangements are in place by the Council to fund external bodies in
the delivery of services.  The scope of the audit did not include a review of the
funding of small charitable donations or external bodies with whom the Council
has entered into a contractual relationship. This audit has instead undertaken
a review of the Council’s governance and funding arrangements regarding
Moray Leisure Limited for the management of a leisure centre in Elgin and the
Moray Citizens Advice Bureau for providing support and advice on a number of
different topics, including benefits entitlement, housing, consumer issues, debt
and money management. The audit programme has been developed from the
Financial Regulations and recommended guidance on "Arm's Length External
Organisations (ALEOs)”. Whilst Moray Citizens Advice Bureau is not
specifically categorised as an ALEO, the Council has a significant funding
Item 8.
Page 45

Page 46

contribution and has therefore been included in this review. The audit report for
this project is given in Appendix 1. 
4.       SUMMARY OF IMPLICATIONS 
(a) Corporate Plan and 10 Year Plan (Local Outcome Improvement Plan
(LOIP))
Internal audit work supports good governance and the delivery of
efficient services. 
(b) Policy and Legal
No implications. 
(c) Financial Implications
No implications directly arising from this report. 
(d) Risk Implications
The independent review of selected systems and procedures mitigates
the risks associated with inadequate or ineffective control procedures. 
(e) Staffing Implications
No implications. 
(f) Property
No implications. 
(g) Equalities/ Socio Economic Impacts
No implications. 
(h) Climate Change and Biodiversity Impacts
No implications. 
(i) Consultations
There have been no direct consultations during the preparation of this
report. 
5.        CONCLUSION 
5.1 This report provides Committee with a summary of findings arising from           
an audit project completed during the review period. 
Author of Report:            Dafydd Lewis, Audit and Risk Manager
Background Papers:       Internal audit files 
Ref:                                 
Page 46

Page 47

APPENDIX 1 
Internal Audit Report 
Following the Public Pound  
July 2024   
Distribution:  Head of Governance, Strategy & Performance                  
Sport and Culture Service Manager   
Benefits and Money Advice Manager 
The Internal Audit Section provides Management with an opinion on the internal control
environment and also categories risk ratings for recommendations as high, medium or low
(detailed explanation provided in Appendix1). The audit recommendations for this review have
been classified as follows 
Assurance Level
Risk Ratings for
Recommendations 
Priority 1   3     
Substantial Priority 2   2     
Priority 3   0     
Confidentiality and Disclosure Clause 
This report (“Report”) was prepared by the Internal Audit Section of Moray Council. The matters raised in this Report are
only those which came to our attention during our internal audit work. Whilst every care has been taken to ensure that the
information provided in this Report is as accurate as possible, the Moray Council Internal Audit Section has only been able
to base findings on the information and documentation provided and consequently, no complete guarantee can be given
that this Report is necessarily a comprehensive statement of all the weaknesses that exist, or of all the improvements that
may be required. 
This Report was prepared solely for the use and benefit of the Moray Council, Moray Integration Joint Board or the
Grampian Valuation Joint Board. Moray Council's Internal Audit Section accepts no responsibility and disclaims all liability
to any third party who purports to use or rely for any reason whatsoever on the Report, its contents, conclusions, any
extract, reinterpretation, amendment and/or modification. Accordingly, any reliance placed on the Report, its contents,
conclusions, any extract, reinterpretation, amendment and/or modification by any third party is entirely at their own risk. 
Please refer to the Statement of Responsibility in Appendix 2 of this report for further information about
responsibilities, limitations and confidentiality.   
Contents 
Page
Following the Public Pound 
Item 8.
Page 47

Page 48

2 
1. Introduction & Scope 3
2. Key Issues  4 
Detailed Report 
3. Findings/Recommendations 5-13
4. Management Response 5-13 
Appendices 
1. Audit Terms of Reference and Definitions 
2. Statement of Responsibility 
1. Introduction and Audit Scope  
Page 48

Page 49

3 
The Internal Audit Plan for 2024/25 provided for a “Following the Public
Pound” review to ensure proper accountability for public funds used in
delivering services, irrespective of the means of service delivery. Councils
fund Arms Length External Organisations (ALEOs) to provide important
services to the public. These funding arrangements are often more complex
than purchase contracts for goods or services but can bring both financial
and operational benefits to councils. 
Audit Scotland describes an ALEO as an organisation that is ‘formally
separate to the council but is subject to its control or influence.’ Ownership,
provision of funding, and significant shareholdings in a company indicate
significant control or influence, and therefore constitute an arm’s length
relationship with an external organisation. A council is responsible for
ensuring that Audit Scotland’s ‘Following the Public Pound’ principles are
consistently applied by any ALEOs that it provides funding to and must
ensure that ALEOs can demonstrate value for money. 
A ‘Code of Guidance on Funding External Public Bodies and Following the
Public Pound’ was published by the Convention of Scottish Local Authorities
(COSLA) and the Accounts Commission in 1996, detailing principles and
requirements that should be considered when determining funding for
ALEOs. This Code along with more recent publications from Audit Scotland
including "Arm's length external organisations (ALEOs): are you getting it
right?" (2011) and "Following the Public Pound" (2004 and 2005) was also
considered in the development of the audit programme for this review. 
The audit scope did not include checking the procedures for small charitable
donations or external bodies where the Council has entered into a
contractual relationship. The audit has instead reviewed the arrangements in
place with regard to Moray Leisure Limited for the operational management
of a leisure centre in Elgin, and the Moray Citizens Advice Bureau for
providing support and advice on a number of different topics, including
benefits entitlement, housing, consumer issues, debt and money
management. Whilst Moray Citizens Advice Bureau is not specifically
categorised as an ALEO, the Council has a significant funding contribution
and has been included in this review. 
The audit was carried out in accordance with Public Sector Internal Audit
Standards (PSIAS). 
2. Key Issues 
Page 49

Page 50

4 
• Moray Leisure Centre operated by Moray Leisure Limited, was
established as an ALEO in 1993, and in addition to Council operated
sports and community centres contribute to meeting the leisure and
sporting needs of Moray. The audit noted that reviews have been
undertaken over the last 10 years regarding the future delivery direction
for leisure services. A Moray Sport and Leisure Asset Review report by
the Depute Chief Executive (Education, Communities and
Organisational Development) to the Moray Council Committee on 26
June 2024 (item 12) agreed to procure a company called Alliance
Leisure to conduct a comprehensive leisure assets review for Moray.
The purpose of this review is to establish an evidence base to guide
future strategic planning, investment decisions and management
practices concerning leisure assets, including Moray Leisure Centre.
The audit notes and concurs with the recommendations for a report to
“be presented back to Council within 6 months detailing the findings of
the asset review”.     
• In accordance with recommended guidance and the Council’s Financial
Regulations, there should be a written agreement between the Council
and an externally funded body. It was noted that written agreements in
the form of Service Level Agreements (SLAs) had previously existed
between the Moray Council and Moray Leisure Ltd and Moray Citizens
Advice Bureau (CAB) but had expired in 2018 and 2019, respectively. 
An SLA will provide a contractual relationship detailing expectations in
service delivery, funding requirements and performance monitoring
reporting to evidence how these Organisations contribute to meeting
the Council's strategic plans. 
• A requirement of the Moray Leisure Limited’ Articles of Association is to
appoint 3 elected members as directors on the Board.  Moray Citizens
Advice Bureau requests that 2 elected members attend Board meetings
in an advisory capacity. As part of this audit review, discussions were
held with the elected members on both Boards to ensure there was a
clear understanding of the roles and possible limitations of their duties.
Feedback from elected members noted a need for further guidance to
clarify expectations and possible parameters in responsibilities as
elected members representing the Council within the Boards of these
Organisations. 
Page 50

Page 51

5 
Following the Public Pound - 2024/25 
Ref Risk Ratings for
Recommendations
Audit Finding Audit Recommendation
1. High As detailed within the Financial Regulations, the
Council has adopted the principles of the COSLA /
Accounts Commission's ‘Code of Guidance on
Funding External Bodies and Following the Public
Pound’. The Code sets out a framework for the
Council’s relationships with external bodies through
which they seek to carry out some of their functions
other than on a straight-forward contractual basis. In
accordance with the “Code”, and as detailed within
the Financial Regulations, there is a requirement for
a written agreement between the Council and the
external bodies. It was noted that written
agreements in the form of Service Level Agreements
(SLAs) had been established between the Moray
Council and Moray Leisure Ltd and the Moray
Citizens Advice Bureau. However, the SLAs expired
in 2018 and 2019 respectively. An SLA provides a
formal agreement that describes the scope and
quality of services to be delivered by the external
bodies. In addition, the SLAs should also detail the
performance information to be provided by both
Organisations that will allow effective monitoring
arrangements to ensure Council objectives are met
and Best Value achieved. 
Service Level Agreements should be
agreed between the Council and the Moray
Leisure Ltd and Moray Citizens Advice
Bureau detailing the core activities that
each Organisation is expected to deliver
along with key performance indicators
against which they will be measured. 
Management Response
Page 51

Page 52

6 
Responsible Officer(s) Accepted
(Yes/ No)
Timescale for
Implementation
(Date Required) 
Agreed Management Action/Management Comment
Sport and Culture Service
Manager   
Benefits and Money
Advice Manager
Yes 
Yes
31/12/2024 
31/12/2024
A new draft Service Level Agreement was collectively
drafted between Management staff across Moray Council
and Moray Leisure Centre in mid 2021 – this agreement
was not formally signed/sanctioned at the time due to the
future expansion plans, which was highlighted in the
Committee reports on the MLC expansion plans.  This
draft agreement will be reviewed and updated by the
Management teams of both organisations with input from
legal advisers prior to sign-off. 
A review of the Service Level Agreement with Moray
Citizens Advice Bureau is currently underway and a draft
will be reported to the relevant committee prior to
completion.   
Page 52

Page 53

7 
Ref Risk Ratings for
Recommendations
Audit Finding Audit Recommendation
2. High The Moray Council entered into a 25 year lease in
1993 with Moray Leisure Ltd to operate a leisure
centre from a Council owned building. The lease
was extended by two, one-year extensions until July
2020. A report by the Depute Chief Executive
(Education, Communities and Organisational
Development) to a special meeting of Moray Council
on 17 December 2019, approved a 10 year
extension to the existing lease agreement. An
extended lease agreement would provide Moray
Leisure Ltd with additional security and greater
value for money opportunities for leasing equipment
and supporting better negotiation opportunities for
improved energy deals. A new draft agreement has
been prepared in draft format but has yet to be
finalised. Currently, Moray Leisure Ltd operates on a
monthly contractual agreement with the Council. It is
appreciated that necessary delays have been
required due to consideration and amendments
needed regarding the proposed expansion scheme
of the leisure centre. The audit is also aware of
uncertainties regarding this proposed expansion
scheme, in addition to the recent commissioning of
a company called Alliance Leisure to undertake a
comprehensive leisure assets review for Moray.
However, there is a need to formalise current
arrangements with an agreed lease agreement
Current uncertainties regarding expansion
and the delivery of future leisure services
are appreciated, however a lease
agreement between the Council and Moray
Leisure Ltd should be agreed as a matter
of priority. 
Page 53

Page 54

8 
between the Council and Moray Leisure Ltd. 
Management Response
Responsible Officer Accepted
(Yes/ No)
Timescale for
Implementation
(Date Required) 
Agreed Management Action/Management Comment
Head of Governance,
Strategy & Performance
Yes 31/12/2024 The Council’s legal advisers will co-ordinate with the
agents of Moray Leisure Limited to support the completion
of a lease agreement within the specified timescale. 
Page 54

Page 55

9 
Ref Risk Ratings for
Recommendations
Audit Finding Audit Recommendation
3. High During the course of this audit, a Moray Sport and
Leisure Asset Review report by the Depute Chief
Executive (Education, Communities &
Organisational Development) to the Moray Council
Committee on 26 June 2024 (item 12) agreed to
procure a company called Alliance Leisure to
undertake a comprehensive leisure assets review
for Moray. The purpose is to establish an evidence
base to guide future strategic planning, investment
decisions and management practices concerning
leisure assets, including Moray Leisure Centre. It
was noted that over the last 10 years, other
reviews have been undertaken to explore future
delivery options for leisure services. The internal
audit undertaken agrees with the committee report
recommendation to detail the findings of the asset
review to the Council within the next 6 months. 
Internal Audit concurs with the
recommendation detailed within the Moray
Sport & Leisure Asset Review Report to
Moray Council Committee on 26 June 2024
(item 12) that on conclusion of the external
review, findings should be used “to provide
further evidence base that will contribute to
the design of our future leisure estate”. 
Management Response
Responsible Officer Accepted
(Yes/ No)
Timescale for
Implementation
(Date Required) 
Agreed Management Action/Management Comment
Sport and Culture Service
Manager   
Yes 31/12/2024 As stated in the Committee report in June, a report will be
taken back to Committee before end of Dec 24 detailing
the findings of the Alliance Leisure Review alongside
other future service design evidence.
Page 55

Page 56

10 
Ref Risk Ratings for
Recommendations
Audit Finding Audit Recommendation
4. Medium  In accordance with Financial Regulations, the
Council has a requirement for funding external
organisations to establish “reporting and
monitoring arrangements to ensure Council
objectives are met and Best Value achieved”. It is
pleasing to note that performance related
information is shared with the Council by both
Moray Leisure Limited and Moray Citizens Advice
Bureau on a regular basis. However, no
structured monitoring systems have been
established to measure the performance
information provided against agreed objectives.
Governance arrangements also do not include a
requirement of how the performance of each
Organisation contributes to Council objectives,
which a relevant committee could then scrutinise. 
Consideration should be given to
establishing clear objectives supported by
tailored performance indicators that are
agreed with Moray Leisure Limited and
Moray Citizens Advice Bureau each year.
The Council should then monitor
performance information provided by each
Organisation against these agreed
objectives and if necessary, report it to the
appropriate committee for scrutiny. 
Management Response
Responsible Officer Accepted
(Yes/ No)
Timescale for
Implementation
(Date Required) 
Agreed Management Action/Management Comment
Sport and Culture Service
Manager   
Yes  30/04/2025  Footfall statistics for Moray Leisure Centre are reported as
part of the Council’s Service Performance reporting
however appreciate these do not align to clear objectives. 
Intention is to report annually on performance as per
performance targets set in the new Service Level
Page 56

Page 57

11 
Benefits and Money
Advice Manager 
Yes  30/04/2025
Agreement.  A report will be presented to Education,
Children’s and Leisure Services Committee between
April-June annually which will focus on performance
measures/achievement based on the previous financial
year. 
Relevant performance objectives and performance
reviews will be included in the updated SLA for the Moray
Citizens Advice Bureau and will be monitored and
reported as appropriate. 
Page 57

Page 58

12 
Ref Risk Ratings for
Recommendations
Audit Finding Audit Recommendation
5. Medium It was noted that a requirement of Moray Leisure
Limited’ Articles of Association is for the
appointment of 3 elected members as directors on
the Board.  Moray Citizens Advice Bureau
requests that 2 elected members attend Board
meetings in an advisory capacity. Elected
members sitting as board members can provide
important links between the Council and the
funded bodies and help ensure that the
organisations are being properly run and funds
used effectively. However, there are
disadvantages, with Audit Scotland highlighting
the risk of potential conflicts of interest for elected
members. As part of this audit review discussions
were held with elected members representing the
Council on the Boards of Moray Leisure Limited
and the Moray Citizens Advice Bureau. Feedback
from the elected members noted a need for
improved guidance to further clarify their roles,
responsibilities and parameters in their duties as
elected members representing the Council on the
Board of each Organisation. 
Further to discussions with the Head of
Governance Strategy & Performance, the
Council should consider and confirm
whether to accept the reputational risks
associated with perceived conflicts of
interest where elected members sit on the
boards of funded external bodies. If it is
considered to continue with the current
arrangement, additional guidance should
be provided to elected members to further
clarify the roles, duties and parameters of
their responsibilities as elected members
representing the Council on the board of
funded external bodies.     
Management Response
Page 58

Page 59

13 
Responsible Officer Accepted
(Yes/ No)
Timescale for
Implementation
(Date Required) 
Agreed Management Action/Management Comment
Head of Governance,
Strategy & Performance
Yes 31/10/2024 Consideration will be given to the perceived risks
associated with appointments to outside bodies.  Guidance
will be refreshed and agreed by the council as appropriate
following this consideration. 
Page 59

Page 60

14 
Appendix 1 
AUDIT TERMS OF REFERENCE AND DEFINITIONS 
1. Audit Objectives 
1.1 The overall audit objective is to provide an objective independent opinion on
the adequacy and effectiveness of controls / processes.  
1.2 The audit will for each controls / process being considered: 
• Walkthrough the processes to consider the key controls; 
• Conduct sample testing of the identified key controls, and 
•    Report on these accordingly 
1.3 All audit reviews are carried out in accordance with Public Sector Internal
Audit Standards (PSIAS). 
2. Definitions for Auditing Opinions and Findings 
2.1 In order to assist management in using our reports: 
The Internal Auditor will categorise audit assurance opinion according to
their overall assessment of the risk management system, effectiveness of the
controls in place and the level of compliance with these controls and the
action being taken to remedy significant findings or weaknesses. 
Assurance
Level
System and Testing Conclusion
Full The controls tested are being consistently applied
Substantial There is evidence that the level of non compliance with some of
the controls may put some of the system objectives at risk.
Limited The level of non compliance puts the system objectives at risk.
None Significant non-compliance with basic controls leaves the system
open to error or abuse. 
2.2 Risk ratings for each recommendation is based on the following criteria: 
High Fundamental control weaknesses that require immediate attention
by management to action and mitigate significant exposure to risk
Medium Less critically important controls absent, not being operated as
designed or could be improved
Low Lower level controls absent, not being operated as designed or
could be improved. 
Page 60

Page 61

15 
Appendix 2 
STATEMENT OF RESPONSIBILITY   
The responsibility for designing and maintaining a sound system of internal control
to prevent and detect fraud and other irregularities rests with management, with
internal audit providing a service to management to support them to achieve this
objective. The Internal Audit Section will assess the adequacy and effectiveness of
the system of internal control arrangements implemented by management and
perform sample testing on those controls in the period under review with a view to
providing an opinion on the extent to which risks in this area are managed. 
The Internal Audit Section will undertake testing with the objective of detecting
significant control weaknesses. However, the audit approach alone should not be
relied upon to identify all strengths and weaknesses in internal controls nor to find
any fraud or irregularity. Even sound systems of internal control can only provide
reasonable and not absolute assurance and may not be proof against collusive
fraud. 
The matters raised in this report are only those that came to our attention during
the course of the audit review and are not necessarily a comprehensive statement
of all the weaknesses that exist or all improvements that might be made.
Recommendations for improvements should be assessed by management for their
full impact before they are implemented. The performance of the audit review
undertaken should not be taken as a substitute for management’s responsibilities
for the application of sound management practices. 
This report is confidential and must not be disclosed to any third party or
reproduced in whole or in part without the written consent of the Moray Council’s
Audit and Risk Manager. 
Page 61

Page 62

Page 62

Page 63

REPORT TO:    AUDIT AND SCRUTINY COMMITTEE ON 11 SEPTEMBER 2024 
SUBJECT: INTERNAL AUDIT REVIEW – COMMERCIAL REFUSE COLLECTION 
BY: AUDIT AND RISK MANAGER 
1. REASON FOR REPORT 
1.1 The report advises Committee on an internal audit review completed for the
period from 25 June 2024 to 11 September 2024. 
1.2 This report is submitted to Committee in terms of Section III (I) (2) and (8) of
the  Council’s Scheme of Administration relating to consideration of reports
from the Council’s Internal Auditor and monitoring delivery of the audit
service through receipt of quarterly reports on work carried out by Internal
Audit. 
2. RECOMMENDATION 
2.1 That Committee consider the contents of this report, seeks
clarification on any points noted and otherwise notes the report. 
3. BACKGROUND 
3.1 This report provides details the internal audit review completed of Commercial
Refuse Collection during the period 25 June 2024 to 11 September 2024: 
Commercial Refuse Collection  
3.2 An audit has been undertaken to review systems and controls in managing the
Commercial Refuse Collection Service. The audit examined the accounting
arrangements for commercial trade waste income and expenditure. This
included a check that mandatory trade waste agreements are in place for all
commercial waste customers. Findings from the audit noted a need to review
charges for collecting and disposing of commercial waste to reflect current
operational arrangements. In addition, some improvements were also needed
to administrative systems, but it is pleasing to report that no fundamental
control weaknesses were noted. The audit report for this project is given
in Appendix 1. 
4. SUMMARY OF IMPLICATIONS 
(a) Corporate Plan and 10 Year Plan (Local Outcome Improvement Plan
Item 9.
Page 63

Page 64

(LOIP))
Internal audit work supports good governance and the delivery of
efficient services. 
(b) Policy and Legal
No implications. 
(c) Financial Implications
No implications directly arising from this report. 
(d) Risk Implications
The independent review of selected systems and procedures mitigates
the risks associated with inadequate or ineffective control procedures. 
(e) Staffing Implications
No implications. 
(f) Property
No implications. 
(g) Equalities/ Socio Economic Impacts
No implications. 
(h) Climate Change and Biodiversity Impacts
No implications. 
(i) Consultations
There have been no direct consultations during the preparation of this
report. 
5.        CONCLUSION 
5.1 This report provides Committee with a summary of findings arising
from an audit project completed during the review period. 
Author of Report:            Dafydd Lewis, Audit and Risk Manager
Background Papers:       Internal audit files 
Ref:                                 
Page 64

Page 65

APPENDIX 1 
1
Internal Audit Report 
Commercial Refuse Collection  
August 2024   
Distribution:   Head of Environmental & Commercial Services 
Service Manager 
Waste Manager 
Administration Officer                                 
The Internal Audit Section provides Management with an opinion on the internal control
environment and also categories risk ratings for recommendations as high, medium or low
(detailed explanation provided in Appendix1). The audit recommendations for this review have
been classified as follows 
Assurance Level
Risk Ratings for
Recommendations 
Priority 1  0    
Substantial Priority 2  6     
Priority 3  4       
Confidentiality and Disclosure Clause 
This report (“Report”) was prepared by the Internal Audit Section of Moray Council. The matters raised in this Report are
only those which came to our attention during our internal audit work. Whilst every care has been taken to ensure that the
information provided in this Report is as accurate as possible, the Moray Council Internal Audit Section has only been able
to base findings on the information and documentation provided and consequently, no complete guarantee can be given
that this Report is necessarily a comprehensive statement of all the weaknesses that exist, or of all the improvements that
may be required. 
This Report was prepared solely for the use and benefit of the Moray Council, Moray Integration Joint Board or the
Grampian Valuation Joint Board. Moray Council's Internal Audit Section accepts no responsibility and disclaims all liability
to any third party who purports to use or rely for any reason whatsoever on the Report, its contents, conclusions, any
extract, reinterpretation, amendment and/or modification. Accordingly, any reliance placed on the Report, its contents,
conclusions, any extract, reinterpretation, amendment and/or modification by any third party is entirely at their own risk. 
Please refer to the Statement of Responsibility in Appendix 2 of this report for further information about
responsibilities, limitations and confidentiality.  
Item 9.
Page 65

Page 66

APPENDIX 1 
2
Contents 
Page
Commercial Refuse Collection 
1. Introduction & Scope 3
2. Key Issues  3-4 
Detailed Report 
3. Findings/Recommendations 5-14
4. Management Response 5-14 
Appendices 
1. Audit Terms of Reference and Definitions 
2. Statement of Responsibility 
Page 66

Page 67

APPENDIX 1 
3
1.    Introduction and Audit Scope 
The annual Internal Audit Plan for the 2024/25 year provides for a review to
be undertaken of the controls in the management of the Commercial Refuse
Collection Service. The audit checked to ensure robust accounting
arrangements are followed, and appropriate agreements are in place with
customers. The Waste (Scotland) Regulations 2012 require all businesses
producing waste to appoint a registered carrier for disposing of their waste.
The Moray Council, as a Professional Collector & Transporter of Waste,
collects commercial residual and recycling waste for approximately 1,200
businesses. 
Analysis of the Financial Management System for 2023/24 detailed the
operational cost for delivering a commercial refuse collection service
amounted to £725,000, with staffing and vehicle costs as the most significant
expenditure items. The annual income collected from commercial waste
collection was noted as £922,000. The scope of the audit reviewed the
accounting arrangements for commercial (trade) waste income and
expenditure and the associated administrative processes. This involved a
review of the operational planning and budget monitoring practices and
checking the main cost elements of staffing and vehicle expenditure for
delivering the service. The income charging and collection arrangements
were also reviewed as part of the audit. In addition, a check was made that
mandatory trade waste agreements are in place for all commercial waste
customers of the service. 
The audit was carried out in accordance with Public Sector Internal Audit
Standards (PSIAS). 
2. Key Issues 
• The audit found no full service costing analysis has been undertaken in
the last 5 years. A review should be undertaken to ensure the charges
for collecting and disposing of trade waste continue to reflect current
operational arrangements. In addition, the review will also provide
increased effectiveness in budget monitoring and forecasting
processes. 
• A discrepancy was noted in the current trade waste charges whereby
the Council approved a 10% administration fee to be added to charges
for collecting trade waste from businesses under sub-contracting
arrangements to national waste contractors with customers but no
physical presence in Moray. The administration fee was introduced for
2024/25; however, the audit found that the fee has not been applied to
the charges made to businesses.
Page 67

Page 68

APPENDIX 1 
4
• The Waste (Scotland) Regulations 2012 requires a duty of care on all
business waste producers to have a formal Trade Waste Agreement. 
Trade Waste Agreements are sent to customers by post, on initial
customer engagement and thereafter, on an annual basis, for each
business to agree on and confirm the continuation of the service. This is
a time-consuming paper-based system; consideration should therefore
be given to the development of an electronic method to issue Trade
Waste Agreements to businesses and receive return submissions.   
Page 68

Page 69

APPENDIX 1 
5
Commercial Waste Collection- 2024/25 
Ref Risk Ratings for
Recommendations
Audit Finding Audit Recommendation
1. Low Scottish local authorities have a statutory requisite to
provide domestic waste collection services, but there
is no requirement to deliver a waste collection service
to the commercial sector. The Council's duty
concerning trade waste is to provide information and
advice to businesses. It was noted that a Commercial
Waste Information Guide has been prepared and is
available to businesses on the Council website.
However, it was compiled in 2014 and some of the
information recorded is out of date. 
Council website content relating to the
Commercial Waste Service should be reviewed
on a regular basis to confirm continued validity,
with updates undertaken of any relevant areas
of change.   
Management Response
Responsible Officer Accepted
(Yes/ No)
Timescale for
Implementation
(Date Required) 
Agreed Management Action/Management Comment
Waste Manager Yes 31/10/2024 Review of all online content to be undertaken and any required
updates actioned. 
Page 69

Page 70

APPENDIX 1 
6
Ref Risk Ratings for
Recommendations
Audit Finding Audit Recommendation
2. Medium The audit review found a significant variance between
the actual income collected and the budget for several
financial years. This has been due to a number of
reasons, such as declining trade since the Covid
period and a greater awareness of recycling resulting
in a reduction in waste to be collected, in conjunction
with budget provisions not being wholly realigned to
current market factors. However, it was noted that the
information available on trade waste contracts with
customers is not being used to inform the income
budget figure. 
Consideration should be given to the use of the
trade waste sales contract data held to inform
income projections and align future budget
provisions for improved management
information purposes.
Management Response
Responsible Officer Accepted
(Yes/ No)
Timescale for
Implementation
(Date Required) 
Agreed Management Action/Management Comment
Waste Manager Yes 31/03/2025 Implementation of this recommendation is interlinked with the
service costing and charging review referred to at
Recommendation 7 below. Budget provisions will be
reassessed with Accountancy support following the Council
charges review for 2025/26. 
Page 70

Page 71

APPENDIX 1 
7
Ref Risk Ratings for
Recommendations
Audit Finding Audit Recommendation
3.  Low Analysis of the staffing costs charged to the Waste
Management Service was found to be correct.
However, it was noted that some employee costs for
the Commercial Refuse Collection Service should
have been charged to the Domestic Refuse Service. In
order to allow a more precise analysis of actual
expenditure, costs should be accurately recorded
against the different operational waste sectors. 
Employees identified as misallocated to the
Commercial Refuse Collection Service should
be reassigned to the correct cost centre. Going
forward, staffing cost breakdowns and
establishment listings received by the service
should be scrutinised to ensure staffing
allocations within the service remain accurate. 
Management Response
Responsible Officer Accepted
(Yes/ No)
Timescale for
Implementation
(Date Required) 
Agreed Management Action/Management Comment
Waste Manager  Yes 31/10/2024 Whilst the overall numbers of staff being charged were correct
it is agreed there were some budget charging discrepancies
with regard to who was allocated under Trade Waste. Going
forward, staffing adjustments will be correctly coded. 
Page 71

Page 72

APPENDIX 1 
8
Ref Risk Ratings for
Recommendations
Audit Finding Audit Recommendation
4. Low The Commercial Refuse Collection Service is internally
recharged by Fleet Services to hire vehicles used in
service delivery. Audit testing to confirm the accuracy
of the vehicle costs recharged to the Commercial
Refuse Collection Service found that other waste
services are using some vehicles, and correspondingly
costs for some vehicles used by the Commercial
Refuse Collection Service are being charged to the
Recycling and Domestic Waste Collection cost
centres. 
A review should be undertaken of vehicle costs
recharged to the Waste Management Service
to ensure vehicle recharges are allocated to
the correct cost centres. Any budget
realignment required as a result of vehicle
reassignment should also be undertaken. 
Management Response
Responsible Officer Accepted
(Yes/ No)
Timescale for
Implementation
(Date Required) 
Agreed Management Action/Management Comment
Waste Manager Yes 31/10/2024 Similar to Recommendation 3 above, the correct number of
vehicles are being charged under Trade Waste but there are
discrepancies over vehicle usage between Waste sectors
which require adjustment. 
Page 72

Page 73

APPENDIX 1 
9
Ref Risk Ratings for
Recommendations
Audit Finding Audit Recommendation
5. Medium The Waste (Scotland) Regulations 2012 requires a
duty of care on all business waste producers to have a
formal trade waste agreement to transfer their waste in
the required manner. Businesses requesting the
Council to collect their trade waste must sign a Trade
Waste Agreement.  Thereafter, a business is also
required to sign an annual Trade Waste Agreement to
confirm the continuation of the service. All Trade
Waste Agreements are sent to customers by post.
Documents are returned to the Council using email
and post, depending on customer choice. Audit testing
found that a significant proportion of existing
customers do not return their annual Agreements
despite being issued a reminder. 
Consideration should be given to the
development of E-forms for Trade Waste
Agreements to enable a more automated
approach to businesses and also provide value
for money savings to the Council.
Management Response
Responsible Officer Accepted
(Yes/ No)
Timescale for
Implementation
(Date Required) 
Agreed Management Action/Management Comment
Waste Manager Yes 01/04/2025 It is agreed there should be an assessment of options
undertaken to work smarter in this area. Consideration will be
given as to the impacts of mandatory Digital Waste Tracking to
be introduced from April 2025.   
Page 73

Page 74

APPENDIX 1 
10 
Ref Risk Ratings for
Recommendations
Audit Finding Audit Recommendation
6. Medium The Council’s Trade Waste Agreement allows for a 28-
day notification period for a business or the Council to
cancel a commercial waste collection service. As
businesses are billed in advance, refunds are
frequently required on cessation of the service. The
Conditions of Service permit a nominal charge to cover
the administrative costs of cancelling the service when
processing a refund. However, the audit found there
has been no charge to businesses cancelling their
Trade Waste Agreement.   
Consideration should be given to the
application of the Trade Waste Agreement
cancellation charge on processing a refund, as
stated in the Conditions of Service. If the
service decides to retain this charge, the
decided fee should be included within the
annual approval of the Council’s fees and
charges. 
Management Response
Responsible Officer Accepted
(Yes/ No)
Timescale for
Implementation
(Date Required) 
Agreed Management Action/Management Comment
Waste Manager Yes 30/11/2024 The administration charge for contract cancellation should be
applied. A view will need to be taken on an appropriate fee and
included in the review of annual fees for Council approval in
November 2024 ahead of implementation from April 2025. 
Page 74

Page 75

APPENDIX 1 
11 
Ref Risk Ratings for
Recommendations
Audit Finding Audit Recommendation
7. Medium Commercial waste charges were subject to a price
freeze for the financial years 2019/20 to 2022/23, but a
price increase has been applied to 2023/24 and
2024/25. Before the commencement of the price
freeze in 2019/20 a comprehensive costing exercise
was undertaken, however this has not been repeated
to evidence that current charges for commercial waste
services are based on the current operational model. 
A full-service costing analysis should be
undertaken to determine the appropriate
charges required for current operations. 
Management Response
Responsible Officer Accepted
(Yes/ No)
Timescale for
Implementation
(Date Required) 
Agreed Management Action/Management Comment
Waste Manager Yes 30/11/2024 Charges need to be reviewed, particularly to account for the
recent change in disposal to Energy from Waste (EfW) as
opposed to landfill. This action has previously been noted by
the service and discussed with Accountancy. 
Page 75

Page 76

APPENDIX 1 
12 
Ref Risk Ratings for
Recommendations
Audit Finding Audit Recommendation
8. Low The Council provides a free waste collection service to
registered charities with a set size and number of bins
to be collected on a 3-weekly basis.  Where the charity
requests larger/ additional bins or more frequent
collections, an additional charge should be levied.
Audit testing has confirmed that where additional or
larger sized bins have been requested, the charity has
been correctly charged. However, where more
frequent collections of the free issue bins are required,
the charity has not been charged for this additional
service. 
A review of charitable trade waste customers
should be undertaken to ensure all services
provided in excess of the free allowable
provision are appropriately charged in
accordance with service conditions. 
Management Response
Responsible Officer Accepted
(Yes/ No)
Timescale for
Implementation
(Date Required) 
Agreed Management Action/Management Comment
Waste Manager Yes 30/10/2024 A review of charitable trade waste customers had previously
begun but initial issues identified and staffing shortages have
delayed progress. The exercise will be resumed when staffing 
resources return to full complement.   
Page 76

Page 77

APPENDIX 1 
13 
Ref Risk Ratings for
Recommendations
Audit Finding Audit Recommendation
9. Medium It was noted that for 24/25, the Council approved the
addition of a 10% administration fee for sub-
contracting services to collect commercial waste from
businesses that are part of a national waste contract
where the contractor does not have presence in
Moray. The audit review noted that from analysis of the
sales ledger of invoices issued from April 2024, the
10% administration fee was not applied. 
For 2024/25, administration fees should be
charged to businesses where the Council
collects trade waste as a sub-contractor to a
national waste contract. 
Management Response
Responsible Officer Accepted
(Yes/ No)
Timescale for
Implementation
(Date Required) 
Agreed Management Action/Management Comment
Waste Manager Yes Implemented This has been addressed on audit notification. Necessary
changes have been made to incorporate the 10%
administration fee to charges to customers under sub-
contracted agreements. 
Page 77

Page 78

APPENDIX 1 
14 
Ref Risk Ratings for
Recommendations
Audit Finding Audit Recommendation
10. Medium A review of commercial waste invoices issued to
businesses found low levels of unpaid debt. However,
audit testing has identified examples that despite
following agreed Sundry Debt Management
Procedures, debt has accumulated over a prolonged
period of over 6 months, and in some cases over
multiple years, before the action to cease service
provision has been taken. 
Consideration should be given to establishing
set debt management parameters of financial
limits and / or time periods for the cessation of
a commercial waste collection service when
charges remain unpaid by a business. 
Management Response
Responsible Officer Accepted
(Yes/ No)
Timescale for
Implementation
(Date Required) 
Agreed Management Action/Management Comment
Waste Manager Yes 30/10/2024 This process has been discussed following an earlier
review at service level. The approach to debtors to date
has been to manage through payment plans whilst
retaining customers. However, a strengthening of
approach is accepted as required and the process to be
followed, and its accompanying documentation, is being
developed. 
Page 78

Page 79

APPENDIX 1 
15 
Appendix 1 
AUDIT TERMS OF REFERENCE AND DEFINITIONS 
1. Audit Objectives 
1.1 The overall audit objective is to provide an objective independent opinion on
the adequacy and effectiveness of controls / processes.  
1.2 The audit will for each controls / process being considered: 
• Walkthrough the processes to consider the key controls; 
• Conduct sample testing of the identified key controls, and 
•    Report on these accordingly 
1.3 All audit reviews are carried out in accordance with Public Sector Internal
Audit Standards (PSIAS). 
2. Definitions for Auditing Opinions and Findings 
2.1 In order to assist management in using our reports: 
The Internal Auditor will categorise audit assurance opinion according to
their overall assessment of the risk management system, effectiveness of the
controls in place and the level of compliance with these controls and the
action being taken to remedy significant findings or weaknesses. 
Assurance
Level
System and Testing Conclusion
Full The controls tested are being consistently applied
Substantial There is evidence that the level of non compliance with some of
the controls may put some of the system objectives at risk.
Limited The level of non compliance puts the system objectives at risk.
None Significant non-compliance with basic controls leaves the system
open to error or abuse. 
2.2 Risk ratings for each recommendation is based on the following criteria: 
High Fundamental control weaknesses that require immediate attention
by management to action and mitigate significant exposure to risk
Medium Less critically important controls absent, not being operated as
designed or could be improved
Low Lower level controls absent, not being operated as designed or
could be improved.
Page 79

Page 80

APPENDIX 1 
16 
Appendix 2 
STATEMENT OF RESPONSIBILITY   
The responsibility for designing and maintaining a sound system of internal control
to prevent and detect fraud and other irregularities rests with management, with
internal audit providing a service to management to support them to achieve this
objective. The Internal Audit Section will assess the adequacy and effectiveness of
the system of internal control arrangements implemented by management and
perform sample testing on those controls in the period under review with a view to
providing an opinion on the extent to which risks in this area are managed. 
The Internal Audit Section will undertake testing with the objective of detecting
significant control weaknesses. However, the audit approach alone should not be
relied upon to identify all strengths and weaknesses in internal controls nor to find
any fraud or irregularity. Even sound systems of internal control can only provide
reasonable and not absolute assurance and may not be proof against collusive
fraud. 
The matters raised in this report are only those that came to our attention during
the course of the audit review and are not necessarily a comprehensive statement
of all the weaknesses that exist or all improvements that might be made.
Recommendations for improvements should be assessed by management for their
full impact before they are implemented. The performance of the audit review
undertaken should not be taken as a substitute for management’s responsibilities
for the application of sound management practices. 
This report is confidential and must not be disclosed to any third party or
reproduced in whole or in part without the written consent of the Moray Council’s
Audit and Risk Manager. 
Page 80

Page 81

REPORT TO: AUDIT AND SCRUTINY COMMITTEE ON 11 SEPTEMBER 
2024
SUBJECT: PUBLIC SECTOR INTERNAL AUDIT STANDARDS-                                                
EXTERNAL QUALITY ASSESSMENT OF INTERNAL AUDIT
BY: AUDIT AND RISK MANAGER 
1. REASON FOR REPORT 
1.1 To provide the committee with details of a recent external quality
assessment undertaken on the council’s internal audit service. 
1.2 This report is submitted to Committee in terms of Section III (I) (6) of the
Council’s Scheme of Administration relating to the consideration of reports
in overseeing the independence, objectivity, performance and
conformance to professional standards of Internal Audit. 
2. RECOMMENDATION 
2.1 That Committee considers and notes the report and the action plan
prepared to address the issues raised in the external quality
assessment of internal audit.
3. BACKGROUND
3.1 The Local Authority Accounts (Scotland) Regulations 2014 at paragraph 7
require that ‘a local authority must operate a professional and objective
internal auditing service in accordance with recognised standards and
practices in relation to internal auditing’. 
3.2 The recognised standards adopted by all Scottish councils are the Public
Sector Internal Audit Standards, (PSIAS) developed by standard setters
including the Chartered Institute of Public Finance and Accountancy
(CIPFA) and the Chartered Institute of Internal Auditors. The standards
include a requirement for an External Quality Assessment (EQA) of
internal audit once every five years, and for the findings to be considered
at a meeting of a Council committee. 
Item 10.
Page 81

Page 82

3.3 Through the Scottish Local Authorities Chief Internal Auditors’ Group
which the Council participates in, it was agreed that the EQA
requirement could be met through a peer review process. This required
each council’s chief internal auditor to lead a review of another council’s
internal audit service and receive a review in return. Perth and Kinross
Council was selected to undertake the assessment of Moray Council. 
3.4 The assessment took place in March 2024 and involved the Chief Internal
Auditor of Perth and Kinross Council reviewing operating arrangements
within Moray against PSIAS. This involved verification of a portfolio of
evidence, interviews with the Chair of the Audit and Scrutiny Committee,
the Chief Executive, and the Head of Governance, Strategy &
Performance, as well as discussions and file reviews involving officers
within the Internal Audit Section. A copy of the report detailing the audit
findings together with an action plan containing recommendations is
provided as Appendix 1. 
3.5 The overall conclusion of the external assessment is that Moray Council’s
Internal Audit Service fully conforms with the PSIAS, which can be found in
section 2.1 of the attached report.  This should assure members and senior
management of the effectiveness of internal audit arrangements within the
Council. However, the report includes a recommendation to reinforce the
Internal Audit’s function as an “independent appraisal function” for the
Council and partner organisations. As part of the PSIAS requirements, an
annual internal quality assessment is required. The Senior Auditor will
undertake this, and the findings and any improvement recommendations
will be reported to the Audit and Scrutiny Committee to ensure continuing
compliance with PSIAS.   
4. SUMMARY OF IMPLICATIONS 
(a) Corporate Plan and 10 Year Plan (Local Outcomes
Improvement Plan (LOIP))
Internal audit work supports good governance and the delivery of
efficient services. 
(b) Policy and Legal
No implications directly arising from this report. 
(c) Financial Implications
No implications directly arising from this report. 
(d) Risk Implications
The independent review of selected systems and procedures
mitigates the risk associated with inadequate or ineffective control
procedures. 
(e) Staffing Implications
No implications directly arising from this report.
.
(f) Property
Page 82

Page 83

No implications directly arising from this report. 
(g) Equalities/Socio Economic Impact
No implications directly arising from this report. 
(h) Climate Change and Biodiversity Impacts 
No implications. 
(i) Consultations
There have been no direct consultations during the preparation of
this  report. 
5. CONCLUSION 
5.1 This report provides Committee with a summary of findings arising
from an external quality assessment of the Council’s Internal Audit
Service. 
Author of Report:
Background Papers: 
Dafydd Lewis
Internal Audit files
Audit and Risk Manager
Ref:   
Page 83

Page 84

Page 84

Page 85

Item 10.
Page 85

Page 86

Page 86

Page 87

Page 87

Page 88

Page 88

Page 89

Page 89

Page 90

Page 90

Page 91

Page 91

Page 92

Page 92

Page 93

Page 93

Page 94

Page 94

Page 95

Page 95

Page 96

Page 96

Page 97

Page 97

Page 98

Page 98

Page 99

Page 99

Page 100

Page 100

Page 101

Page 101

Page 102

Page 102

Page 103

REPORT TO: AUDIT AND SCRUTINY COMMITTEE ON 11 SEPTEMBER 2024 
SUBJECT: CAREFIRST REPLACEMENT – PROGRESS UPDATE 
BY:  INTERIM HEAD OF SERVICE & CHIEF SOCIAL WORK OFFICER 
1. REASON FOR REPORT 
1.1 To inform the Committee of the progress of the replacement Social Work and
social care management information system and the outline business case. 
1.2 This report is submitted to the Committee in terms of Section III (I)(11) of the
Council’s Scheme of Administration relating to consideration of reports from the
Council’s Internal Auditor and supporting the Council’s governance, risk and
control arrangements by promoting internal controls and assurances. 
2. RECOMMENDATION 
2.1 Committee are asked to consider the contents of this report, seek
clarification on any points and otherwise note the report. 
3. BACKGROUND 
3.1 CareFirst system is the principal management information system for adult,
children and families and justice social work and social care services. 
CareFirst5 was implemented in 1998 and upgraded to CareFirst 6 in 2010.  The
last upgrade took place in 2017.   
3.2 A report was submitted to this committee on 23 November 2022 (para 7 of
minute refers), and Moray Integration Joint Board (MIJB) Audit, Performance
and Risk Committee on 24 November 2022 (para 7 of minute refers), providing
an update on Internal Audit Completed Projects and reference to a review of
the CareFirst System undertaken that recommended replacement of CareFirst .   
3.3 A report was submitted to the MIJB on 25 January 2024 (para 12 of minute
refers) where approval was given to initiate the process to begin scoping a
replacement system and subsequently the current contract was extended for a
further year to 31 March 2025. 
Item 11.
Page 103

Page 104

3.4 A follow up review was undertaken by Internal Audit and reported to this
committee on 14 February 2024 (para 6 of minute refers) where it was
requested a progress report be provided to this committee at 6 months. 
4. KEY MATTERS RELEVANT TO RECOMMENDATION 
4.1 A project manager was allocated in March 2024 to progress the project
mandate and outline business case. 
4.2 A project mandate was prepared incorporating risks outlined in previous reports
to this committee and MIJB.  The project mandate was presented to the ICT
Gateway Review meeting on 28 May 2024.  They were wholly supportive of the
proposal to replace the system because of the risks of operating a legacy
system, however they would need further information regarding funding and
resource requirements and requested to see the Outline Business Case (OBC)
when completed.  ICT resource will be provided to support specification and
option appraisals for inclusion in the OBC. 
4.3 The mandate was then presented to the Asset Management Working Group
(AMWG) on 12 June 2024 where it was noted that there was no current budget
allocation and there will be options for the replacement that affect the funding. 
If a server based solution is chosen, the spend will be capital and through
Moray Council, if a cloud based system, then the spend is revenue and will be
a pressure for MIJB.  It was also noted that Health and Social Care Moray
(HSCM) was aware of the resourcing pressures on the Procurement team so
there was no additional capacity for this project and there would be a need to
reprioritise existing support provision. AMWG also determined that the project
should be classed as strategic and should proceed to the outline business
case. 
4.4 The project mandate was presented to MIJB on 27 June 2024 (para 10 of
minute refers) and it was noted that project resourcing would be from existing
staff complement and the project was to progress to OBC to the MIJB in
September 2024. 
4.5 All of the governance meetings have agreed with the need to change the
system however it is confirmed that there are no additional funding streams
identified for the replacement and that it was estimated likely costs would be in
excess of £800k.  Given the current financial situation of Moray Council and
MIJB this is a significant challenge. 
4.6 The current provider has created a new cloud-based product and experience
dictates that they will, in the next 3-5 years, discontinue support for the existing
system and push customers towards their new product. It is expected that from
the award of a tender, the new system takes 18 months to 2 years to migrate to
the new product because of the size, complexity and involvement of extremely
sensitive and critical data types. 
4.7 The technology of the platform is over 20 years old and the software was
written years ago, there are no upgrades so no potential for development.  This
system no longer supports efficient and effective working hence the urgency to
progress implementation of a replacement.  There was a failure in one of the
servers on 11 July 2024 resulting in downtime for all social work and social care
Page 104

Page 105

teams of 5 hours during which it was not possible to access any information. 
Services have business continuity arrangements in place, however, considering
the increasing likelihood of potential disruption, arrangements are being
reviewed to ensure they are as robust as possible. 
4.8 Work has continued at a slower pace to develop a detailed specification, to
proceed to options appraisal due to competing pressures for HSCM project
resource.  A resource has now been identified and the project will move forward
with a revised timeline to be presented to MIJB in September 2024 to ensure
appropriate governance routes are followed.  This delay means the anticipated
budgetary pressure will occur during 2025/26. 
5. SUMMARY OF IMPLICATIONS 
(a) Corporate Plan and 10 Year Plan (Local Outcomes
Improvement Plan (LOIP)) and Moray Integration Joint
Board Strategic Plan “Partners in Care 2022 – 2032”
Providing staff with effective tools to provide the right support and
the right time in the right place is essential for meeting people’s
outcomes, the fundamental aim of the strategic plan. 
(b) Policy and Legal
There are no legal implications arising from this report. 
(c) Financial implications
The only budget currently allocated is the current revenue costs for
support and as yet no additional provision has been made in MIJB or
Council budgets.  Future recommendations regarding budgetary
provision would require to be backed up initially by an outline business
case and following Council’s protocols.
It is intended to utilise existing staff resource to progress the project to
Outline Business Case. 
(d) Risk Implications and Mitigation
The audit review noted serious concerns regarding the limitations of the
CareFirst system with information regarding social care users needing to
be retained on a Council server or in paper files. In addition, issues were
also noted regarding access and information management controls
within CareFirst. The Council’s Audit and Risk Manager and Chief
Internal Auditor of the Moray Integration Joint Board is very concerned
about the current recording arrangements of very sensitive information,
the risk of maintaining multiple databases, and the CareFirst System not
being supported. There is an urgent need to agree on a future direction
of how social care information should be recorded that will allow officers
to effectively manage the needs of social care users in accordance with
policies/regulations while still ensuring strong information management
controls are maintained. 
To continue with the existing system is a significant risk to service
delivery.  
• Continuing to operate on a legacy system presents likely risks of non-
compliance with changes to legislation and regulation and provides no
Page 105

Page 106

opportunity to develop working practices to reflect improvements and
good practice.  
• There is an increased risk of lack of data security as the system is not
updated with protection against new cyber threats.
• There are risks to efficient and effective working practices e.g. the
system does not support uploading of documents, requiring records to
be held in alternative storage solutions which impacts negatively on
time to search for information.  Without the system, staff would have
to resort to using paper-based records. 
• The reporting solution of the existing system does not support
provision of robust performance information on which to base
decisions. 
There is a risk to the MIJB budget in that no funding is currently
identified so costs will have to be incorporated, therefore requiring
potential additional savings to be identified.
If the project is not resourced sufficiently there is a risk, it will not deliver
the anticipated efficiencies and will not improve staff morale.  The
proposed governance arrangements through identified resource
requirements would enable assurance and oversight of delivery of the
project. 
(e) Staffing Implications
Internal secondment within HSCM will provide project resource.
There will also be significant input required from project team members and
from other staff across services who will be involved in process mapping to
streamline ways of working before introduction of a new system.  It is
anticipated that if the OBC is approved, additional ICT resource will be
required. 
(f) Property
There are no property implications arising from this report. 
(g) Equalities/Socio Economic Impact
There are no equalities implications arising from this report. 
(h) Climate Change and Biodiversity Impacts
There are no climate change implications arising from this report. 
(i) Consultations
Interim Chief Officer; Chief Financial Officer, HSCM; 
Chief Financial Officer (Moray Council), Head of Human Resources, ICT
& Organisational Development; Chief Internal Auditor, MIJB and Caroline
O’Connor, Committee Services Officer, Moray Council. 
6. CONCLUSION 
6.1 This report provides an update on progress with scoping and outline
business case regarding the requirements for a replacement information
and case management system for Social Work and Social Care services
in HSCM. 
Page 106

Page 107

Author of Report:  Jeanette Netherwood
Background Papers:   
CareFirst Replacement, Moray Integration Joint Board 27 June
2024 
CareFirst Replacement - Appendix 1 
CareFirst Replacement - Appendix 2 
CareFirst Replacement - Appendix 3 
Internal Audit Section Update Report, Audit and Scrutiny
Committee 14 February 2024 
Internal Audit Section Update Report - Appendix 1 
Internal Audit Section Update Report - Appendix 2 
Internal Audit Section Update Report - Appendix 3 
Internal Audit Section Update Report - Appendix 4 
Internal Audit Section Update Report - Appendix 5 
Internal Audit Section Update Report - Appendix 6 
CareFirst Replacement, Moray Integration Joint Board 25
January 2024
Internal Audit Section – Completed Projects Report, 24
November 2022
Internal Audit Section Completed Projects Report – Appendix 1
Internal Audit Section Completed Projects Report – Appendix 2 
Ref: SPMAN-305227695-146
Page 107

Page 108

Page 108