Moray Council
Wednesday, 04 October 2023
NOTICE IS HEREBY GIVEN that a Special Meeting of the Moray Council is to be 
held at Council Chambers, Council Office, High Street, Elgin, IV30 1BX on 
Wednesday, 04 October 2023 at 15:00 or immediately following Corporate 
Committee whichever is the latter.
BUSINESS
1. Sederunt
2. Declaration of Member's Interests
3. Cloddach Bridge
Report by the Depute Chief Executive (Economy, Environment and 
Finance)
 
5 ­ 12
Watching the Meeting
You can watch the webcast live by going to: 
 
 
http://www.moray.gov.uk/moray_standard/page_43661.html
 
 
Webcasts are available to view for 1 year following the meeting.
 
You can also attend the meeting in person, if you wish to do so, 
please come to the High Street entrance door and a member of 
staff will be let into the building.
Page 1

Page 2

Any person wishing to attend the meeting should contact customer services 
on 01343 563217 prior to the meeting as the number of attendees is restricted 
due to the recent Covid pandemic
You can however watch the webcast of the meeting by going to :
http://www.moray.gov.uk/moray_standard/page_43661.html
Page 2

Page 3

GUIDANCE NOTES
* Declaration of Group Decisions and Members Interests ­ The Chair of the 
meeting shall seek declarations from any individual or political group at the 
beginning of a meeting whether any prior decision has been reached on how 
the individual or members of the group will vote on any item(s) of business on 
the Agenda, and if so on which item(s).  A prior decision shall be one that the 
individual or the group deems to be mandatory on the individual or the group 
members such that the individual or the group members will be subject to 
sanctions should they not vote in accordance with the prior decision.  Any such 
prior decisions will be recorded in the Minute of the meeting.
Page 3

Page 4

MORAY COUNCIL
Moray Council
SEDERUNT
Councillor Kathleen Robertson  (Chair)
Councillor Donald Gatt  (Depute Chair)
 
Councillor James  Allan  (Member)
Councillor Peter Bloomfield  (Member)
Councillor Neil Cameron  (Member)
Councillor Tracy Colyer  (Member)
Councillor Theresa Coull  (Member)
Councillor John Cowe  (Member)
Councillor John Divers  (Member)
Councillor Amber Dunbar  (Member)
Councillor Jérémie Fernandes  (Member)
Councillor David Gordon  (Member)
Councillor Juli Harris  (Member)
Councillor Sandy Keith  (Member)
Councillor Scott Lawrence  (Member)
Councillor Graham Leadbitter  (Member)
Councillor Marc Macrae  (Member)
Councillor Paul McBain  (Member)
Councillor Neil McLennan  (Member)
Councillor Shona Morrison  (Member)
Councillor Bridget Mustard  (Member)
Councillor Derek Ross  (Member)
Councillor John Stuart  (Member)
Councillor Draeyk Van Der Horn  (Member)
Councillor Sonya Warren  (Member)
Councillor Ben Williams  (Member)
 
Clerk Name: Tracey Sutherland
Clerk Telephone: 07971 879268
Clerk Email: committee.services@moray.gov.uk
Page 4

Page 5

REPORT TO: SPECIAL MEETING OF MORAY COUNCIL ON 4 OCTOBER 2023
SUBJECT: CLODDACH BRIDGE 
BY:  DEPUTE CHIEF EXECUTIVE (ECONOMY, ENVIRONMENT AND 
FINANCE)
1. REASON FOR REPORT
1.1 To inform Council of the findings of the Pre­feasibility Study undertaken on the
potential repair of Cloddach Bridge.
1.2 This report is submitted to Council in terms of Section III (F) (15) of the 
Council's Scheme of Administration relating to management and 
implementation of the requirements of the Roads (Scotland) Act 1984.
2. REASON FOR URGENCY
2.1 This report is submitted to Committee in terms of the Local Government 
(Access to Information) Act 1985, on the Chair certifying that, in his/her 
opinion it requires to be considered on the grounds of urgency in order to give 
early consideration to progressing a Full Business Case, by 1 February 2024, 
required to secure grant funding to repair Cloddach Bridge.
3. RECOMMENDATION
3.1 It is recommended that Council 
(i) notes the findings of the pre­feasibility study; and
(ii) agrees that a full business case for the repair of Cloddach 
Bridge should not be funded, as this work is contrary to the 
decision of Economic Development and Infrastructure Services 
Committee on 7 February 2023 (para 11 of the minute refers) and 
does not comply with the Council policy on Bridge Maintenance 
Prioritisation.  
4. BACKGROUND
4.1 On 2 May 2023, the Economic Development and Infrastructure Services 
Committee approved the Council’s Policy on Bridge Maintenance 
Prioritisation, (paragraph 12 of the minute refers).  The policy sets out the 
procedure for prioritising bridge maintenance works, which is based on the 
Item 3.
Page 5

Page 6

condition of each bridge and its network criticality.  Network criticality is split 
into three categories, Vital, Important and Standard.  As a significant 
percentage of the Council’s bridge stock is classed as Standard, this category 
has been sub­categorised into Standard – high, medium and low. Cloddach 
Bridge is categorised as Standard – low.  The full prioritisation list was 
distributed to members on 5 September 2023 and is provided in Appendix A.
4.2 Cloddach Bridge was built in 1905 with an estimated design­life of between 
100 and 120 years, after which it would require significant refurbishment or 
replacement. This bridge is located on the C2E road and a traffic survey 
undertaken in 2020 showed the average number of vehicles crossing the 
bridge each day was less than 800.
4.3 Based on the findings of a Special Inspection undertaken in February 2022, 
Cloddach Bridge was closed to vehicular traffic in the interest of public safety. 
The condition of the bridge was confirmed in the findings of a Principal 
Inspection and Structural Assessment undertaken by an independent 
structural engineer in March 2022.
4.4 On 7 February the Economic Development and Infrastructure Services 
Committee (paragraph 11 of the minute refers) agreed to; 
(i) keep Cloddach Bridge closed to vehicular traffic but open to 
pedestrians and cyclists with regular inspections to monitor the 
condition of the bridge;  
(ii) when the bridge condition deteriorates further and it is not safe 
for any user, this route is closed permanently and the bridge is 
removed; and
(iii) To note the Chair’s commitment, in conjunction with his Group, 
to pursue alternative funding sources with a view to keeping Cloddach 
Bridge open.
4.5 On 15 March 2023, the UK Government announced £1,500,000 grant funding 
for the repair of Cloddach Bridge, which is available subject to a business 
case and match funding of 50%.
4.6 Officers have been in consultation with officials from the Department for 
Transport, which has been appointed as the lead agency from UK 
Government, regarding the terms and conditions of the grant funding.  These 
conditions are listed below.
1. The grant funding available is to provide vehicular access. No weight 
threshold is specified.
2. This funding is up to a maximum of £1,500,000 and is subject to 50% 
match funding being provided.
3. A Full Business Case (FBC) must be submitted to secure the grant 
funding.
4. No funding is available from the UK treasury to develop the business 
case.
5. The grant will be limited to the amount stated in the business case, i.e. 
the UK Government will not underwrite any risk that costs associated 
with the bridge works exceed £3m. 
Page 6

Page 7

The grant funding is available for drawdown this financial year 
(2023/24).
4.7 At a meeting of Moray Council on 28 June 2023 the Council agreed to 
commission and fund a Pre­feasibility Study to ascertain if investment in a 
FBC, as required to secure the UK government grant funding to repair the 
bridge, would be of value (paragraph 8 of the minute refers).
The Pre­Feasibility Options
4.8 The Pre­feasibility Study considered 4 options to reopen the bridge to 
vehicular traffic.  Details of these options are provided below, full details are 
provided in Appendix B (additional meeting document on CMIS).  The 
consultant has estimated the capital cost of each option using average 
construction costs for the UK and adding Optimism Bias.  The costs provided 
considered the lower range, most likely and upper range costs.  These costs 
have been tested using one of the Council’s framework contractors and the 
upper range cost is considered to be closest to current market prices.  
However, these costs will need to be further defined as part of the FBC, 
including quantified risks and should be treated with caution. 
4.9 Option 1 Do Minimum – this option would maintain the current status of the 
bridge, which is closed to vehicular traffic but open to pedestrians and cyclists 
and provides a baseline case for comparison with other options.  The bridge 
would be monitored to assess its condition and suitability for continued use by
pedestrians and cyclists.  It is likely that after 5 to 10 years the bridge would 
need to be fully closed and thereafter demolished. The cost of demolition, 
ongoing monitoring and minor maintenance works is included in the whole life 
cost for this option.  The whole life costs for options that do not involve 
demolition of the bridge allow for ongoing monitoring and maintenance 
required throughout the servicalble life of the structure.  A long term road 
closure would be required for this option, with ancillary works such as signage
and turning facilities for motor vehicles. 
Capital Cost Whole Life Cost Total Cost
£83,000 £747,078 £830,078
4.10 Option 2 Repairs to existing bridge – this option would fully refurbish the 
existing bridge, including breakout and replacement of existing elements.  
There is significant amount of risk associated with this option.  The condition 
of the existing structural elements is not fully known, so the extent to which 
they can be retained or strengthened is also unknown. 
Capital Cost Whole Life Cost Total Cost
£3,957,378 £309,208 £4,266,586
4.11 Option 3 Overbridge – this option retains the existing structure with a pre­
fabricated structure installed over the existing deck.  The overbridge can 
either span the top of the existing abutments to rest on new supports or be 
installed onto the existing foundations in combination with repair works or 
modifications to the existing abutments. Overall the maintenance 
requirements for this type of bridge are higher than would be required for a 
Page 7

Page 8

new integral structure.  The level of ongoing maintenance will depend on 
which of these options is constructed and this has been allowed for in the 
estimated costs.
Option Capital Cost Whole Life Cost Total Cost
4 a) demolish 
substructure 
£3,677,494 £279,208 £3,956,702
4 b) re­use 
substructure 
£3,337,022 £309,208 £3,646,230
4.12 Option 4 New Integral Structure – this option would involve full demolition of
the existing structure and construction of a new bridge.  This option would 
require significantly less ongoing maintenance than the other options 
considered to open the bridge to vehicular traffic.  The consultant has 
considered two factors when costing this option, a minimised width of bridge 
and an improved width of bridge. The minimised bridge would allow passage 
of one standard sized vehicle up to 40 tonnes at a time, agricultural vehicle in 
excess of 3.5m wide would not be able to use this bridge safely.  The 
improved width of bridge would allow two way traffic for standard size 
vehicles.
Option Capital Cost Whole Life Cost Total Cost
4 a) wider 
bridge
£3,514,804 £84,850 £3,599.654
45 b) minimum 
width bridge
£2,868,375 £84,850 £2,953,225
Socio­Economic Benefits and BCR(Benefit Cost Ratio)
4.13 The socio­economic benefits associated with reopening the bridge to 
vehicular traffic cannot be defined at this time as there is insufficient data to 
inform this assessment.  Should members decide to progress a FBC, the 
traffic surveys and traffic modelling proposed as part of the FBC development 
will be sufficient to clearly define these benefits.  Specific socio­economic 
benefits or a BCR are not used within the bridge prioritisation policy, they are 
however used by government to determine the value of investing in particular 
schemes. 
4.14 While specific socio­economic benefits cannot be calculated at this time, it is 
clear that, assuming a capital cost in the region of  £3million,  the value of 
socio­economic benefits would need to be greater than £50,000 per year to 
result in a BCR of greater than 1. The indicative number of vehicles and 
potential for benefit in journey time is highly likely to result in benefits of 
greater than this number.  Therefore, while there would be a positive business
case at this level of capital spend (noting the caveats on this above), there are
too many unknowns to provide a definitive BCR with confidence at this stage. 
The decision of Economic Development and Infrastructure Services 
Committee on 7 February 2023 was for Cloddach Bridge to remain closed to 
vehicular traffic and if the recommendation in Section 3.1 (ii) of this report is 
accepted this decision will be adhered to. Should members choose to support 
the preparation of a FBC, the option then likely to be preferred would be 
Option 4b, new integral bridge with minimum width.       
Page 8

Page 9

Costs and Timeline to Develop FBC
4.15 The pre­feasibility study provides an estimate of the costs involved in 
developing a FBC to repair the bridge and how long this is likely to take.  The 
estimated cost of developing the FBC is £187,000 and it is estimated it will 
take 26 weeks to complete.     Based on this estimate, if the contract is 
awarded at the start of October 2023, the FBC will be ready for submission to 
Department for Transport (DfT) on 5 April 2024. To achieve this submission 
date the contract will need to be awarded directly through one of the Council’s
frameworks. Although this appears a lengthy process it is necessary to carry 
out traffic modellilng to accurately assess the benefits of reopening the bridge 
to vehicular traffic.  It is also necessary to undertake intrusive surveys and 
outline design to reduce risk and assess costs as accurately as possible at 
this early stage of the project, outline design and intrusive surveys in order to 
conclude design and accurate costing. 
4.16 The DfT will need to review and approve the FBC prior to any draw down of 
funding. If the FBC does not establish a case to the satisfaction of the DfT in 
terms of value for money then the case may be referred to a member of the 
ministerial team to consider whether a Ministerial Directive would be issued on
other strategic grounds. The DfT has indicated that to achieve timely approval 
the FBC would need to be submitted to them by 1 February 2024. This is to 
enable the DfT to review the FBC, prepare their own papers, submit the case 
for review by the DfT’s investment board, ministers and Treasury officials. The
current estimated date for completion of the FBC is 5 April 2024 and while it 
may be possible to reduce this, it is unlikely that it could be reduced by the 5 
weeks required to meet the DfT deadline. Council may wish to be mindful of 
this risk, noting that schemes of this scale ordinarily take 12 months or more 
to develop to the stage of an approved business case, whereas this project 
would have had less than 11 months from the Chancellor’s budget 
announcement on 15 March 2023.  
4.17 At this point the advice received from the DfT is that Treasury remains firm 
that any release of funding must be this financial year. 
4.18 The business case would follow the five case model set out in the Green 
Book, which includes the Financial Case.  The Financial Case must set out 
how the bridge repair will be funded.  As such, the source of the 50% match 
funding currently estimated at £1.45m required to construct the bridge will 
need to be identified before submission of the FBC. It should be noted that 
council officers are already looking to reduce the council’s capital 
commitments going forward as they are unaffordable.
Match Funding
4.19 A meeting was held with Heldon Community Council on 2 August 2023, to 
discuss progress and funding required to repair Cloddach Bridge.  Heldon 
Community Council has advised it intends to submit an application for funding 
to the Fred. Olsen Renewables Rothes 1­ fund. The closing date for 
applications is 3 October and the application will be considered on 17 
October.  The level of funding, if any, that would be made available from this 
source will not be known until after 17 October, although it should be noted 
that the Community Council has already indicated that any funding is likely to 
be partial rather than full match funding..  The Community Council also 
Page 9

Page 10

intends to petition Scottish Government to explore potential funding streams 
from this source.
Summary
4.20 In summary, should there be a decision to proceed further, the process would 
be as follows:
a. preparation of FBC – including identification of match funding
b. submission of FBC to DfT for approval by 1 February 2024, if possible. 
DfT has advised that HMT position is that the funding must be released in 
2023/24.
c. If FBC demonstrates a positive BCR, approval of FBC for funding 
drawdown is within the remit of the DfT
d. If FBC does not demonstrate a positive BCR the case may be referred for 
a ministerial direction to approve funding
e. drawdown of funding on agreed terms with DfT in line with delivery of 
project
4.21 Notwithstanding the information set out above in this report, and the concern 
of local residents, it remains the case that there is already a standing Council 
decision to close Cloddach Bridge to vehicular traffic. The council has also 
approved the prioritisation policy that determines the order in which these 
bridges are brought forward for funding and Cloddach bridge is classified as 
standard – low, meaning that notwithstanding other financial pressures on the 
council there are a significant number of other bridges in Moray that have a 
higher funding priority for the council. These bridges are brought forward in a 
managed way each year for inclusion in the capital budget to enable an 
affordable and deliverable programme of works to maintain network bridges 
across Moray. 
5 SUMMARY OF IMPLICATIONS
(a) Corporate Plan and 10 Year Plan (Local Outcomes Improvement 
Plan (LOIP))
“Building a better future for our children and young people in Moray”
(b) Policy and Legal
In policy terms Cloddach Bridge is classed as Standard: Low in terms of 
its priority level. In terms of the Short to Mdeium term Financial Strategy 
also on the agenda for this meeting (item 8), reducing the Capital Plan is 
a key contributor to achieving a balanced budget by the end of 2025/26.
(c) Financial implications
There is no committed budget to fund a FBC or undertake works on 
Cloddach Bridge. It is noted that Council on 28 June 2023 (para 10 of 
the minute refers) carried forward £1.5m capital from the 22/23 capital 
budget into 23/24 provisionally in relation to Cloddach Bridge, but 
agreeing that any firm commitment would be subject to further decision 
making. As set out in para 4.20 and 4.21 above and in the risk 
implications below, given the other calls on council funding and the 
requirement to make significant financial savings for 2024/25 and 
2025/26 there are clear financial impacts in committing funding to this 
Page 10

Page 11

project.
When the Council approved the budget for 2022/23 on 22 February 
2022 (paragraph 3 of the Minute refers) it balanced only by using 
reserves and one­off financial flexibilities. The indicative 3 year budget 
showed a likely requirement to continue to make savings in the order of 
£20 million in the next two years.   All financial decisions must be made 
in this context and only essential additional expenditure should be 
agreed in the course of the year.  In making this determination the 
committee should consider whether the financial risk to the Council of 
incurring additional expenditure outweighs the risk to the Council of not 
incurring that expenditure, as set out in the risk section. 
(d) Risk Implications
The pre­feasibility study has indicated that there would be a positive 
BCR to fund the repair works required to re­open Cloddach Bridge to 
vehicular traffic. However, this cannot be confirmed until further traffic 
survey and modelling work has been undertaken to define the benfits 
reopening the bridge would provide.  Officials from the Department of 
Transport have indicated that the grant funding could be made available 
through a Ministerial Directive if there is no positive benefit cost ratio 
(based on socio­economic benefits).  However, this is not guaranteed 
and the funding required to deliver the business case could be abortive 
spend.  
There is a risk that should it make funding available to support this 
project notwithstanding the earlier decision in February this year, the 
Council is seen as departing from its established Bridge Maintenance 
Prioritisation Policy. While it could be suggested that the offer of 
government funding makes this project exceptional, any funding 
contributed by the Council would still be applied to a bridge which would 
not otherwise be accorded priority status, and given the current projected
funding gap of £15m for 2024/25, this may ultimately be to the potential 
detriment of other bridges and communities across Moray, particularly in 
the context of a reducing Capital Plan.
As set out in para 3.16, should there be a decision to proceed with 
developing the FBC there are risks in achieving a timely submission of 
the FBC in order to achieve drawdown of funding, which could lead to 
abortive expenditure. 
 
(e) Staffing Implications
There are no staff resources available within the Consultancy Section to 
undertake the work required to deliver the business case.  As such this 
work will need to be outsourced at a cost of approximately £187,000  
Some staff time would be required to manage the contract for the 
business case and this is likely to impact on the Consultancy Team’s 
delivery of its revenue programme for 2023/24. 
Page 11

Page 12

(f) Property
Cloddach Bridge currently vests with Moray Council in its role as Road 
Authority. If the bridge is closed and the road is Stopped Up, the land on 
which is has been constructed must be reinstated and returned to the 
landowner.
(g) Equalities/Socio Economic Impact
If the bridge remains closed to vehicular traffic, a maximum diversion of 
6 miles may affect some car users.
(h) Climate Change and Biodiversity Impacts
Where possible we would seek to recycle and / or reuse the waste 
material generated through demolition of the existing bridge.
(i) Consultations
Depute Chief Executive (Economy Environment and Finance), Head of 
Environmental and Commercial Services, Chief Financial Officer, Legal 
Services Manager, Equal Opportunities Officer and the Democratic 
Services Manager have been consulted and their comments 
incorporated into the report.
6. CONCLUSION
6.1 A decision not to progress works on Cloddach Bridge was made by 
Economic Development and Infrastructure Services Committee on 7 
February 2023.
6.2 To receive grant funding from DfT to repair Cloddach Bridge the Council 
must submit a FBC, which should demonstrate value for money and 
must identify how the match funding of £1,434,187 will be sourced.
6.3 It is likely that a positive BCR can be achieved over the serviceable life 
of the new bridge but this cannot be confirmed until traffic survey and 
modelling work is undertaken during development of the FBC.
6.4 A commitment to progress with development of a FBC given the 
Council’s stated policy positions, uncertain match funding and 
extremely challenging timescales is not recommended given the risks 
which this would present for the Council.
Author of Report:  Debbie Halliday Consultancy Manager
Background Papers:
Ref: SPMAN­524642768­970