Moray Council 
Wednesday, 24 January 2024 
NOTICE IS HEREBY GIVEN that a Special Meeting of the Moray Council is to be
held at Council Chambers, Council Office, High Street, Elgin, IV30 1BX on
Wednesday, 24 January 2024 at 09:30. 
BUSINESS 
1. Sederunt 
2. Declaration of Group Decisions and Members Interests * 
3. Resolution
Consider, and if so decide, adopt the following resolution:
"That under Section 50A (4) and (5) of the Local Government
(Scotland) Act 1973, as amended, the public and media
representatives be excluded from the meeting for Item 12 of business
on the grounds that it involves the likely disclosure of exempt
information of the class described in the relevant Paragraphs of Part 1
of Schedule 7A of the Act.”   
4. Moray Integration Joint Board Scrutiny
Report by Depute Chief Executive (Education, Communities and
Organisational Development)  
7 - 10
5. Petitions Procedure - Under 18 Year olds
Report by Depute Chief Executive (Education, Communities and
Organisational Development)  
11 - 20
6. Charging for Services
Report by Depute Chief Executive (Economy, Environment and
Finance)  
21 - 26
Page 1

Page 2

7. Short to Medium Term Financial Plan
Report by Depute Chief Executive (Economy, Environment and
Finance)  
27 - 38
8. Capital Strategy
Report by Depute Chief Executive (Economy, Environment and
Finance)  
39 - 56
9. Capital Plan 2024-25
Report by Depute Chief Executive (Economy, Environment and
Finance)  
57 - 72
10. Manufacturing Innovation Centre for Moray
Report by Depute Chief Executive (Economy, Environment and
Finance)  
73 -
288
11. Information Reports - if called in 
Item(s) which the Committee may wish to consider with
the Press and Public excluded   
12. Business Enterprise Hub and Housing Mix Delivery
[Para 6 8 and 9]
• 6. Information relating to the financial or business affairs of any
particular person(s);
• 8 & 9. Information on proposed terms and/or expenditure to be
incurred by the Authority; 
Information Reports - Not for Discussion at this Meeting
Any member wishing to call in a noting or information report from one
meeting shall give notice to Committee Services at least 48 hours
before the meeting for which the report is published. The Notice shall
be countersigned by one other elected member and shall explain the
reason for call in including any action sought. 
Information Report - Charging for Services
Report by Depute Chief Executive (Economy, Environment and
Finance)  
289 -
358
Page 2

Page 3

Watching the Meeting
You can watch the webcast live by going to: 
http://www.moray.gov.uk/moray_standard/page_43661.html    
Webcasts are available to view for 1 year following the meeting.  
You can also attend the meeting in person, if you wish to do so,
please come to the High Street entrance door and a member of
staff will be let into the building. 
Page 3

Page 4

GUIDANCE NOTES 
* Declaration of Group Decisions and Members Interests - The Chair of the
meeting shall seek declarations from any individual or political group at the
beginning of a meeting whether any prior decision has been reached on how
the individual or members of the group will vote on any item(s) of business on
the Agenda, and if so on which item(s).  A prior decision shall be one that the
individual or the group deems to be mandatory on the individual or the group
members such that the individual or the group members will be subject to
sanctions should they not vote in accordance with the prior decision.  Any such
prior decisions will be recorded in the Minute of the meeting. 
Page 4

Page 5

MORAY COUNCIL 
Moray Council 
SEDERUNT 
Councillor Kathleen Robertson  (Chair)
Councillor Donald Gatt  (Depute Chair)  
Councillor James  Allan  (Member)
Councillor Peter Bloomfield  (Member)
Councillor Neil Cameron  (Member)
Councillor Tracy Colyer  (Member)
Councillor Theresa Coull  (Member)
Councillor John Cowe  (Member)
Councillor John Divers  (Member)
Councillor Amber Dunbar  (Member)
Councillor Jérémie Fernandes  (Member)
Councillor David Gordon  (Member)
Councillor Juli Harris  (Member)
Councillor Sandy Keith  (Member)
Councillor Scott Lawrence  (Member)
Councillor Graham Leadbitter  (Member)
Councillor Marc Macrae  (Member)
Councillor Paul McBain  (Member)
Councillor Neil McLennan  (Member)
Councillor Shona Morrison  (Member)
Councillor Bridget Mustard  (Member)
Councillor Derek Ross  (Member)
Councillor John Stuart  (Member)
Councillor Draeyk Van Der Horn  (Member)
Councillor Sonya Warren  (Member)
Councillor Ben Williams  (Member)  
Clerk Name: Tracey Sutherland
Clerk Telephone: 07971 879268
Clerk Email: committee.services@moray.gov.uk 
Page 5

Page 6

Page 6

Page 7

REPORT TO: SPECIAL MORAY COUNCIL ON 24 JANUARY 2024 
SUBJECT: ARRANGEMENTS FOR COUNCIL SCRUTINY OF MORAY
INTEGRATION JOINT BOARD 
BY:  DEPUTE CHIEF EXECUTIVE (EDUCATION COMMUNITIES AND
ORGANISATIONAL DEVELOPMENT) 
1. REASON FOR REPORT 
1.1 To clarify Council scrutiny arrangements for Moray Integration Joint Board
(MIJB). 
1.2 This report is submitted to Committee in terms of Section I of the Council's
Scheme of Administration relating to the terms of reference for committees. 
2. RECOMMENDATION 
2.1 It is recommended that the Council approve the reporting arrangements
for Council scrutiny of Moray Integration Joint Board detailed in
paragraphs 4.1 and 4.2. 
3. BACKGROUND 
3.1 Moray Integration Joint Board (also known as Health and Social Care Moray)
brings together Moray Council and NHS Grampian staff to jointly deliver a
wide range of community health and social care services under the direction
of the Moray Integration Joint Board. It was formally established in April 2016.    
3.2 Both the Council and NHS Grampian have delegated statutory functions to
MIJB through an Integration Scheme approved by the Scottish Government.
The functions delegated by the Council include: 
• Social care services including those provided to children and families
• Fostering and adoption services
• Child protection
• Justice services 
3.3 The Board is made up of members from the Council, members from NHS
Grampian and professional staff. The cost of provision of the services
delegated to the Board is shared between the Council and NHS Grampian. 
Item 4.
Page 7

Page 8

3.4 MIJB has a distinct legal personality and the autonomy to manage itself.
Whilst there is no role for the Council (or NHS Grampian) to independently
sanction or veto decisions of the MIJB, it is important that the Council
scrutinise the MIJB at various levels. 
3.5 There has been some uncertainty over:
• which MIJB related issues should be reported to the Council. 
• which Council meetings these reports should be presented to
• the phrasing of recommendations within these reports. 
3.6 Areas which still require a decision of the Council:
• Annual agreement of the Council’s financial contribution to MIJB 
• Approval of the report of the Chief Social Work Officer.
• As a recipient of formal Directions from MIJB.
• As an employer of staff who provide services directed by the Board
• As a commissioner of hosted services (some functions are not
delegated by managed by MIJB on behalf of the Council). 
3.7 Areas delegated to MIJB where the Council has a scrutiny role:
• As a funding partner, monitoring MIJB’s budgetary position.
• As a community partner monitoring shared plans and outcomes 
• As a service partner delivering integrated services. 
3.8 The proposals at 4.1 and 4.2 below clarify which Council meetings these
issues will be presented to. 
4. PROPOSALS 
4.1 Areas requiring recommendation to the Council to agree or approve.   
Issue Suggested meeting 
4.1.1 Annual approval of Council contribution to
MIJB budget. 
Moray Council
4.1.2 Council Budget-monitoring reports to include
a short section on spending on IJB services
(they already do, so modest change/addition
Moray Council 
4.1.3 Consideration of directions from MIJB
Council compliance with Directions
Relevant Committee or
Moray Council if budgetary
implications. 
4.1.4 Staffing establishment issues Corporate Committee or
Moray Council if budgetary
implications
4.1.5 Report of Chief Social Work Officer Moray Council 
4.2 Areas for Council scrutiny. For these areas report recommendations could
include phrases such as: 
• Note or endorse the position.
• Seek further information/require further assurance 
• Make recommendation to MIJB
:  
Page 8

Page 9

Issue Suggested meeting 
4.2.1 MIJB budget monitoring reports  Moray Council [Audit and
Scrutiny?]
4.2.2 MIJB strategic plan  Moray Council 
4.2.3 MIJB's annual performance report
(legislation says the IJB has to send the
Council a copy) 
Moray Council 
MIJB six monthly performance reports  Moray Council [Audit and
Scrutiny or Education,
Communities and Leisure
Services?]
4.2.4 MIJB board minutes for information   Audit and Scrutiny
4.2.5 Policy and practice issues which overlap with
council services (for example Childrens
Services issues being reported to ECLS
committee).
Relevant Committee 
5. SUMMARY OF IMPLICATIONS 
(a) Corporate Plan and 10 Year Plan (Local Outcomes Improvement
Plan (LOIP))
The aims of the Council and the MIJB are aligned in the LOIP. 
(b) Policy and Legal
It is good practice under national “Following the Public Pound” and “Best
Value” guidance for the Council to monitor the outcomes of externally
funded partners. Any additional responsibilities added to the remit of the
Council’s Audit and Scrutiny committee will require an amendment to the
Council’s Scheme of Administration. 
(c) Financial implications
Given the pressure on Council finances and the risk over overspend in
Social Care budgets it is important that the Council closely monitors the
position. 
(d) Risk Implications
The proposals within 4.1 and 4.2 should help manage the financial risk
outlined in the previous paragraph. 
(e) Staffing Implications
No direct implications. 
(f) Property
No direct implications 
(g) Equalities/Socio Economic Impact
No direct impact. 
(h) Climate Change and Biodiversity Impacts
No direct impact. 
Page 9

Page 10

(i) Consultations
The Chief Executive, Chief Officer Moray Integration Joint Board, Chief
Social Work Officer and Head of Education have been consulted on a
draft of this report. 
5. CONCLUSION 
5.1 This report clarifies Council decision making and scrutiny arrangements
for Moray Integration Joint Board. 
Author of Report: Alasdair McEachan 
Background Papers: 
Ref: 
Page 10

Page 11

REPORT TO: SPECIAL MORAY COUNCIL ON 24 JANUARY 2024 
SUBJECT: PETITIONS PROCEDURE – UNDER 18 YEAR OLDS 
BY:  DEPUTE CHIEF EXECUTIVE (EDUCATION, COMMUNITIES AND
ORGANISATIONAL DEVELOPMENT) 
1. REASON FOR REPORT 
1.1 To ask the Council to agree the inclusion of an addendum to the Petitions
Guidance/Procedure to allow young people up to the age of 18 or still at
school to make representations to the Council. 
1.2 This report is submitted to Council in terms of Section II (10) of the Council's
Scheme of Administration relating to changes in Committee structure,
distribution of functions and responsibilities. 
2. RECOMMENDATION 
2.1 It is recommended that the Council agree the inclusion of an addendum
to the current Petitions Guidance/Procedure that will allow young people
up to 18 years of age or still at school to make representation to the
Council. 
3. BACKGROUND 
3.1 At the meeting of Moray Council on 7 December 2022, the Council agreed to
introduce an e-petition process and that a further report be brought forward on
how the petitions process could best facilitate representation from young
people up to the age of 18 years (para 22 of the Minute refers). 
3.2 The draft procedure and template were considered at the meeting of Moray
Council on 6 December 2023 (para 8 of the Minute refers).  Following
concerns raised by Councillors on a number of issues, the Council agreed to
defer consideration of the report until the meeting of Moray Council in January
2024 to allow for further consultation to simplify the draft procedure with those
Councillors raising concerns.  
Item 5.
Page 11

Page 12

4. ENGAGING WITH YOUNG PEOPLE UP TO THE AGE OF 18 OR STILL AT
SCHOOL 
4.1 As previously discussed at the meeting of Council on 7 December 2022 (para
22 of minute refers), it is considered that the criteria set out within the
Council’s petitions process would be problematic in terms of gaining a fixed
number of signatories who were required to be on the electoral register,
therefore, in order to make it as accessible as possible, a much simpler
process was required. 
4.2 A draft proposed procedure is attached at Appendix 1. The procedure
broadly aligns to the Council’s petition process however has been amended to
use plain English language and explains what issues can and cannot be
raised. A pro forma is attached at Appendix 2 to assist young people and
ensure they provide the information required to progress the petition. 
4.3 It is proposed that any petitions from young people up to the age of 18 or still
at school are administered by Committee Services and then passed to the
Head of Service for a decision on how the issue should be addressed, in
conjunction with the Chair of the relevant Service Committee. 
4.4 Should the Council be minded to approve this procedure it will be added as an
addendum to the Council’s Petition process/guidance on the relevant
webpage. 
4.5 A limited number of young people have been consulted on the draft procedure
via the Community Learning and Development (CLD) Worker from which
positive feedback has been provided. 
4.6 Appendices 1 and 2 have been amended to include input from the
Councillors who raised concerns at the meeting of Moray Council on 6
December 2023.   
5. SUMMARY OF IMPLICATIONS 
(a) Corporate Plan and 10 Year Plan (Local Outcomes Improvement
Plan (LOIP))
Members of the public engaging with the Council by means of petitions
links directly with Moray Council’s priority to Empower Communities. 
(b) Policy and Legal
It is important, in the interests of good corporate governance and the
Best Value Statutory Duty, for the Council to provide a means for the
public to engage in the decision making process. 
Article 12 of the United Nations Convention on the Rights of the Child
and its upcoming enshrinement into Scottish Law via the United Nations
Convention on the Rights of the Child (Incorporation) (Scotland) Bill
outlines that children have the right to express a view and have that view
taken into account. 
Page 12

Page 13

(c) Financial Implications
None 
(d) Risk Implications
The Council could be seen to be excluding young people from being able
engage with the Council on matters for which the Council has a
responsibility or a service it provides relative to them. 
(e) Staffing Implications
None. 
(f) Property
None. 
(g) Equalities/Socio Economic Impact
The proposals are consistent with the UNCRC (Incorporation) (Scotland)
Bill. 
(h) Climate Change and Biodiversity Impacts
None. 
(i) Consultations
Depute Chief Executive (Education, Communities and Organisational
Development); Head of Governance, Strategy and Performance; Head of
Education; Democratic Services Manager; Susan Stronach, CLD
Worker; Stewart McLauchlan, Quality Improvement Manager; Dr L
Puhalak, Policy Officer; Ms L Van Zyl, Service Manager, both Health and
Social Care Moray and the Equalities Officer. 
Councillors Mustard, Van Der Horn and Warren were part of the working
group and their comments to date have been included in the appendices,
however they may wish to make further comment at the meeting. 
6. CONCLUSION 
6.1 It is recognised that the current Petitions Procedure does not provide a
means by which young people up to the age of 18 or still at school can
engage with the Council on matters of importance.  The proposed
addendum to the current Petitions Procedure will allow engagement
from young people in a structured, yet simplified manner. 
Author of Report:  Caroline O’Connor, Committee Services Officer 
Background Papers:  
Ref:    SPMAN-2045703626-347    
SPMAN-2045703626-346    
SPMAN-2045703626-345 
Page 13

Page 14

Page 14

Page 15

APPENDIX 1 
How to submit a petition – A guide for young people up to 18 years or those
still at school 
The Council makes decisions which may affect everyone in Moray.  If you feel
strongly about a decision made by the Council, live in Moray and want to make your
views known then:
• If you are an individual you can contact your local Councillor
• If you and a number of your peers want to raise an issue, then you can submit
a petition to the Council. A petition is a collective request which can be
submitted either by email (committee.services@moray.gov.uk) or by post to:-
Committee Services, Moray Council, Council Office, High Street, Elgin IV30
1BX 
This guide tells you how to submit a petition. 
• Tell us about the issue you want to raise giving enough information to allow
the Council to understand the background and what, if anything, you would
like the Council to do about it.  
• Please keep the information to around 250 words. 
• You need 20 or more of your peers who support your petition to sign it (less
signatures may be accepted in smaller communities).
• We will need to make reasonable checks that everyone who signs the petition
lives in Moray.  If you need some help with confirming if everyone who signs
your petition lives locally, you can ask someone at your school or group to
approve it. 
A form is attached for you to complete. 
About the petition topic 
• The Council can only consider local issues that it has responsibility for or
relates to something the Council does or a service it provides.  Find out more
about what the Council is responsible for at www.moray.gov.uk. 
• In the background to your petition, please do not name any individual.  If you
need to refer to someone who works for the Council then please use their title
rather than their name, ie Guidance Teacher not Mrs X. 
• Petitions should be about general issues and not about an individual person’s
issue or where there is some other established process in place.  Personal
issues can be raised as a complaint. 
Submitting your Petition 
• Please include all the information you want the Council to know about your
issue. Keep a copy of the petition and any information for your own records.
.
• Once the Council receives your petition, you will get a letter or email from
Committee Services within 14 days confirming its receipt. .
Item 5.
Page 15

Page 16

• The Council will pass on your petition to the officer responsible for your
issue so it can be looked at.
• You will then be contacted to tell you what will happen next.
• If it is decided the petition is to be considered at a Council meeting, you or
someone you nominate may be invited to make a short statement at the
meeting in support of the petition. 
Page 16

Page 17

APPENDIX 2
PETITION SUBMISSION FORM (YOUNG PEOPLE) 
If you would like any help in submitting your petition please contact Committee Services on 01343
563014 or email committee.services@moray.gov.uk, or alternatively refer to the information on
the Council’s website at www.moray.gov.uk/petitions
Lead Person’s (Petitioner) contact details
Please enter the name of person raising the issue in this petition.
Include contact details in case the Council needs any further information.
Name:
Address: 
Postcode:
Tel No:
E mail:
Title/subject of issue – please keep the information to around 250 words
Office use: Petition number
Item 5.
Page 17

Page 18

Action sought – How would you like the Council to do to resolve the issue? 
Action to date – what action has been taken so far to try and resolve the issue? 
Background Information - please provide any other information that you think the
Council should be made aware of. 
Page 18

Page 19

Signature of Lead Person (Petitioner)
The Lead Person should sign and date the form in the box below.
Any additional sheets of signatures should be attached to the form. 
Signature ………………………………………………………. Date ……………………………….
Name of signatory in block capitals ……………………………………………………………….
Number of people who have
signed the petition 
Page 19

Page 20

PETITION FORM APPENDIX 
NAME ADDRESS SIGNATURE
1.  
2.  
3.  
4.  
5.  
6.  
7.  
8.  
9.  
10.  
11.  
12.  
13.  
14.  
15.  
16.  
17.  
18.  
19.  
20.  
*Add additional sheets if required
The petition must be supported by 20 signatures or more of young people living in the Moray
Council area 
Page 20

Page 21

REPORT TO: SPECIAL MORAY COUNCIL ON 24 JANUARY 2024 
SUBJECT: CHARGING FOR SERVICES 
BY:  DEPUTE CHIEF EXECUTIVE (ECONOMY, ENVIRONMENT AND
FINANCE) 
1. REASON FOR REPORT 
1.1 To ask Council to approve revised charges for Council services for 2024/25. 
1.2 This report is submitted to Council in terms of Section III (B) (1) and (48) of
the Council's Scheme of Administration relating to financial policy and the
setting of charges. 
2. RECOMMENDATION 
2.1 It is recommended that Committee: 
(i) approves the charges for Council services for 2024/25 set out in
paragraphs 3.5 to 3.13; and 
(ii) notes the list of charges including those uplifted by the default of
5.7% and those outwith the control of the Council . 
3. BACKGROUND 
3.1 The current Charging for Services Policy was approved by Council on
12 December 2023 (paragraph 7 of the draft Minute refers). Under the policy,
an annual revision of charges is required.  In order to preserve the Council’s
financial position, charges within the control of this council are generally
inflated annually and Council at the same meeting agreed that the default
increase for 2024/25 would be 5.7%. 
3.2 The Charging for Services Policy assumes a default position of full cost
recovery, recognising that there will be exceptions to that rule.  In cases
where the Council offers a service where there are alternative service
providers then market conditions should be taken into account.  In other
instances benchmarking with other local authorities may be a good test of
reasonableness.  There may be policy reasons for charging at less than full
cost recovery for some services.  However, charging for services is an
important tool when considering the Council’s overall budget and the
Council’s Short to Medium term Financial Strategy, which was approved by
Item 6.
Page 21

Page 22

Council on 27 September 2023, includes maximising income as a priority to
minimise the needs to reduce service levels.   
3.3 Not all charges are within the Council’s control.  Some charges levied by the
Council for services provided are set by statute, some are limited by statute
and some have the method of calculation prescribed by statute – these are
included in the list of charges for Council services for the sake of
completeness. 
3.4 The reason behind any recommended charges for 2024/25 not recommended
to be increased by 5.7% (with rounding up or down if appropriate), where
these are within the Council’s control, are discussed on a section-by-section
basis below. A full list of charges is provided in the separate Information
Report on Charging for Services published with the meeting agenda. 
3.5 A: Corporate / cross departmental 
There are no charges within the control of the Council not proposed to be
increase by 5.7%, apart from charges for photocopying, which were increased
last year and are proposed to be frozen for 2024/25.  Such small charges are
impractical to increase by inflation annually.   
Charges at A6(ii) for licences under the Civic Government (Scotland) Act and
various other miscellaneous prices of legislation have been increased by
5.7% as an interim measure but these are subject to review by the Licencing
Committee and the results of this review will be reported later in the year,
which may result in amendment to these charges.
.
3.6 B: Social Care Services 
Moray Council delivers social care in partnership with NHS Grampian through
Moray Integration Joint Board (MIJB).  The ability to set charges is a function
of the Council and not of MIJB.  However, as in previous years the Council
has requested MIJB to make recommendations regarding the level of
charges, so that a holistic view can be taken of charges for social care and
their relation to service issues, and in the spirit of partnership working.  The
charges included in section B relating to services carried out for MIJB are
inflated by 5.7% as recommended by MIJB officers.  Contributions towards
social care services, which are generally means tested (as opposed to
charges which are flat rate) fall within the remit of MIJB.  The contributions
policy is planned to be reviewed and further review of charges may take place
as a consequence of this. 
3.7 C: Leisure facilities
- C1 – Fit Life.  Discussions are taking place with Moray Leisure Ltd on
increase of charges for Fit Life and these will be reported to Council when
discussions have concluded In addition to this a new charge is proposed –
Visitor membership.  Visitor membership would be for a minimum of 14
days and is aimed at short term workers, holidaymakers, students etc. 
The cost is based on a 14 day programmed membership card.  Visitor
membership excludes attendance at swimming lessons.  Prices of £28 for
an individual and £30 for a family are recommended.
Page 22

Page 23

- C3a – Fitness rooms.  No increase is proposed for the £25 fee for
induction (this is free to Fit Life members).  The discounted rate of £3.75
for exercise referrals is proposed to be removed.  
3.8 D: Libraries and Information Services
- D1d – replacement card.  Recommended increase from £1 to £1.50.
- D1g – microfilm/fiche – recommended increase charge from 90p to £2.50
Rounding has been applied to the default increase. 
3.9 E: Education
- E3 – school meals.  Previous experience is that a 10p increase is too high
as usage drops off (5.7% would be a 14p increase) and so an increase in
the cost of a primary school meal from £2.40 to £2.45 is recommended. 
3.10 F: Economic Growth and Development Services
- F1 – Pest control.  This service will cease from 1 April 2024 following staff
saving proposals approved by Council. 
Two new charges are proposed: F4y compliance / withdrawal of an
enforcement notice £250 and F4z pre application advice for householder
developments £100.  It is also proposed that sponsored street names be
charged a negotiated fee. 
- F5b – an above inflation increase for copy documents is proposed: from
£33 to £75 for a Planning Decisions Notice or Building Warrants and 
Certificate of Completion and from £23 to £50 for a Search Retrieval
where no reference is given.  A new charge is proposed for extra plans
and documents - £10 per item for documents of 10 pages or less, £20 per
item for documents over 10 pages.  These increases reflect officer time
involved and difficulty of retrieving archived documents.  The charge for
microfiche copies is proposed to be withdrawn as no longer required.  
3.11 G: Waste Management, Land and Parks
- G1b – the charge for collection of bulky household refuse is proposed to
be increased from £24+VAT=£28.80 to £26.67+VAT = £32 which is
considered to be a reasonable market rate. 
- G1g – recycling centre pass: the charge (ex VAT) is proposed to be
increased from £246.88 to £300 as it is considered the market can bear
this increase. 
- G1n – a new charge is proposed: 10% of the weekly fee to the main
contractor as a sub-contractor administration fee for Moray servicing bins
as part of a national waste contract, to reflect the administration entailed in
provided services as a sub-contractor to national waste collectors who
don’t operate directly in Moray. 
- G2 – burial grounds charges are being reviewed as part of a budget
savings proposal and will be reported to Council when proposals have
been finalised. 
Page 23

Page 24

- G4 – commercial events.  The Admin fee for large and major events is
proposed to be increased from £10 to £250 as more reflective of officer
time. 
3.12 H: Fleet, roads and transportation
- H2h – a new charge of £175 as approved by Council on 25/10/2023 for
placement of furniture etc on a public footway. 
- H3 – car parking.  As approved by Council. 
- H5a – an above inflation rise is proposed for the hire of vehicles, to reflect
increased costs: daily charge from £50 to £55, mileage from £1.25 to
£1.33 per mile. 
- H5c – cost of a duplicate school bus pass is recommended to be
increased from £10 to £15 as this charge has not been increased since
2018.  
3.13 I: Harbours
- I1b – a new charge is proposed for cruise ships should that market
develop -  50p per 7 days or part thereof per dead weight all told (DWAT), 
or per gross tonnage where gross tonnage exceeds DWAT. 
- I1c(1) – 10% increase proposed to bring in line with neighbouring
harbours. As below 
2023/24 2024/25
All CTV per day (per length,
per metre or part thereof) 
All CTV per month (per length,
per metre or part thereof) non
refundable  
All CTV per annum (per length,
per metre or part thereof) non
refundable 
£3.53 
£69.51 
£774.02
£4.00 
£81.00 
£851.00   
Three new charges are proposed:  trailers and vessel moving equipment £200
+ VAT pa and hire of forklift and operator (subject to availability) £70 per hour,
minimum 2 hours in line with neighbouring ports; Attendance of harbour staff
outside of normal working hours and/or public holidays – full cost recovery..   
The following increases are also proposed in line with neighbouring ports: 
2023/24 2024/25
Heavy lifting for
extraordinary specialised
activities, eg transformers,
wind turbine parts
50-99 tonnes – per tonne
100-149 tonnes – per tonne 
£1.61
£2.01 
£1.77
£2.21
Page 24

Page 25

150-249 tonnes – per tonne
Over 250 tonnes – per
tonne 
£2.42
£2.82
£2.66
£3.10 
Slipway and repair pads  
Any recreational vessel
using a slipway inclusive of
one entry and one exit from
the harbour per occasion 
Any commercial vessel
using a slipway inclusive of
one entry and one exit from
the harbour per occasion 
Season ticket for
recreational unlimited use of
any Council slipway, valid
for 12 months, commencing
1 April per vessel 
Season ticket for
commercial unlimited use of
any Council slipway, valid
for 12 months, commencing
1 April per vessel 
£16.67 + VAT 
£25 + VAT 
£61.20 + VAT 
£425.00 + VAT 
£20.83 + VAT =
£25.00 
£ 26.67+ VAT=
£32.00 
£65.00 +
VAT = £78.00 
£499.17+
VAT= £539.00 
Generally, harbours charges have been rounded up or down as appropriate. 
3.13 K: Housing and Property
K4 – late payment of commercial rents.  Above inflation increases are
proposed to reflect the work involved. As below 
2023/24 2024/25
Initial investigation and contact
with tenant and issue of
correspondence pursuing
payment
£50 £65
Negotiate and issue Payment
Arrangement
£75 £100
Copy documents  £50 £75 
4. SUMMARY OF IMPLICATIONS 
(a) Corporate Plan and 10 Year Plan (Local Outcomes Improvement
Plan (LOIP))
The levying of charges for Council services is an essential component of
delivering Council priorities on a sustainable basis. 
Page 25

Page 26

(b) Policy and Legal
The current policy for charging for Council services was approved by this
Council on 25 October 2023.  There are no legal implications arising
from this report.  Some charges are set or limited by legislation. 
(c) Financial implications
Increased income from charges will contribute to the Council’s financial
sustainability. 
(d) Risk Implications
There are no risk implications arising directly from this report.   
(e) Staffing Implications
There are no staffing implications arising directly from this report.   
(f) Property
There are no property implications arising from this report. 
(g) Equalities/Socio Economic Impact
There are no equalities implications or implications for the socio-
economic duty arising from  this report 
(h) Climate Change and Biodiversity Impacts
There are no implications for climate change or biodiversity arising from
this report. 
(i) Consultations
All services have been consulted as to recommended charges and
reasons for any departures from the default increase. 
5. CONCLUSION 
5.1 Charges within the Council’s control not following the default increase
of 5.7% are itemised above. 
Author of Report: Lorraine Paisey, Chief Financial Officer
Background Papers: 
Ref: SPMAN-1293228629-1028
Page 26

Page 27

REPORT TO: SPECIAL MORAY COUNCIL ON 24 JANUARY 2024 
SUBJECT: SHORT TO MEDIUM TERM FINANCIAL PLANNING 
BY:  DEPUTE CHIEF EXECUTIVE (ECONOMY, ENVIRONMENT AND
FINANCE) 
1. REASON FOR REPORT 
1.1 To consider the revised budget and estimated actual for 2023/24, the impact of
the draft local government settlement and consequent revisions to the
estimated budget position for 2024/25 and 2025/26. 
1.2 This report is submitted to the Council in terms of the Council's Administrative
Scheme section (III) (A) (2) relating to considering Capital and Revenue
budgets and long term financial plans. 
2. RECOMMENDATION 
2.1 It is recommended that the Council considers and notes: 
(i) the revised budget and estimated actual for 2023/24 and current
estimates for 2024/25 and 2025/26; and 
(ii) that the structural deficit in 2024/25 is now estimated to be £13.4
million and the Council still requires to make very significant levels
of savings in a short timeframe. 
3. BACKGROUND 
3.1 The Council’s revenue and capital budgets for 2023/24 were approved at a
meeting of Moray Council on 1 March 2023 (paragraph 5 of the Minute refers). 
A budget shortfall in 2023/24 of £15.2 million was planned to be funded from
reserves and a savings target of £19 million for 2024/25 projected.  At the time
this budget was set, this level of use of reserves – creating a structural deficit -
was recognised as a high risk strategy. 
3.2 Council on 8 March 2023 (paragraph 14 of the Minute refers) approved £49,000
recurring savings for consultation and further adjustments following finalisation
of the unaudited accounts were approved by Council on 28 June.  Council on
27 September 2023 (paragraph 9 of the Minute refers) noted the impact of
£2.007 million funding for the 2022/23 pay award and a further £2.2 million for
the teachers’ 2022/23 pay award. 
Item 7.
Page 27

Page 28

3.3 Council on 25 October 2023 noted adjustments to income (full year effect
£62,000) to reflect charges approved by service committees and approved
savings totalling £946,000 and a further £2,003,000 subject to consultation.   
3.4 Council on 6 December 2023 noted the estimated out-turn for the year of an
anticipated underspend in 2023/24 of £439,000 and a budget gap across
2024/25 and 2025/26 of £16 million, following adjustment for the savings
approved at that meeting and recognition of a budget pressure estimated at £5
million anticipated to arise from the expected overspend on core services of
Moray Integration Joint Board (MIJB).   
3.5 The impact of the teachers’ and SJC pay awards has been calculated and the
impact reflected in the 2023/24 estimated expenditure.  The impact was
expenditure of £7.3 million above that allowed for in the provision of inflation. 
Funding for the pay awards has been agreed at national level but not all of this
funding has been confirmed at local authority allocation level.  The funding
package is complex, and includes elements which local authorities are asked to
fund from reserves in 2023/24 which will be refunded by Scottish Government
in 2024/25.  Including unconfirmed elements of funding it is estimated that the
Council will receive additional funding in 2023/24 of £6.116 million, with a
further £0.612 million across 2024/25 and 2026/27.  Overall this is a shortfall of
£572,000, of which £170,000 has already been recognised as a budget
pressure, following agreement that councils would meet £10 million of the
additional costs of the pay awards.  The additional shortfall arises from the
calculation of funding being done on an average percentage increase, whereas
the actual increase for each local authority will depend on the individual staffing
structures of the authority, with proportionately higher costs for those local
authorities with a higher proportion than average of staff on lower than average
salaries. 
3.6 Funding for the expansion of Early Learning and Childcare was made through
specific grant – this has now been baselined in General Revenue Grant and
that adjustment is reflected in APPENDIX 1 to this report. 
3.7 The Short to Medium Term Financial Strategy approved by Council on
27 September 2023 set out the following strategy to balance the 2024/25
budget: 
Action Status
Energy savings measures None incorporated – in development
and will be added when available
IMP 3 savings Estimate included from last review
Other small scale transformation None identified
Council Tax increase above 3% SG funding for Council Tax freeze
makes this option impracticable
Council Tax increased ratios Bands E
to H
SG decision not to proceed with this
Council Tax on second homes Subject of report to Corporate
Committee 30 January 2024
General increase in charges Default of 5.75% approved and detail
is subject of a separate report to this
Page 28

Page 29

Action Status
meeting of Council – impact to be
estimated and added to savings
Savings Max First tranche taken, balance to be
considered and APPENDIX 2 is
included below as option at this stage
Emergency temporary measures Not recommended 
Review of Capital Plan Subject of a separate report to this
meeting of Council – budget will
thereafter be adjusted. 
4. EMERGING ISSUES 2023/24 TO 2025/26 
Budget Pressures
4.1 Budget pressures arise in two ways: most budget pressures come from sources
external to the Council or from factors which influence the demand for services. 
Examples would be change in legislation and demographic pressures such as
increasing school rolls.  The Council cannot directly control this source of
pressures, which covers the majority of spend. The second source of budget
pressures is Council decisions which increase planned expenditure.  Budget
pressures approved when the budget for 2023/24 was set are kept under
review and the emergence of new budget pressures will also be reflected in the
financial planning process. 
4.2 A new budget pressure has been recognised in 2023/34 - £50,000 for
increased cost of school transportation.  The budget pressure of £1.515 million
previously advised for teachers’ pension contributions has been included in
APPENDIX 1, but offset by additional funding from Scottish Government.  This
funding is not confirmed, but Scottish Government expect Barnett
consequential in respect of the teachers’ pension scheme and COSLA is
pressing for this to be passed to local authorities.  Unbudgeted pay awards per
paragraph 3.5 are also included. 
Savings
4.3 Savings from the North East of Scotland Pension Fund contributions as
previously notified are now included in APPENDIX 1. 
4.4 Closure of Elgin Community Centre was approved by Council on 23 June 2023
from 31 March 2024.  The financial impact of this has now been calculated in
detail, taking into account plans for use of the Centre during redevelopment of
Elgin Town Hall and savings of £163,000 for 2024/25 are included in
APPENDIX 1, with a further £73,000 in 2025/26. 
4.5 New burdens arising from the settlement letter are included for 2023/24:
standard recommended allowances for Kinship and Foster Carers £262,000,
temporary accommodation costs £29,000 and Educational Psychologists
£9,000.  The first of these was reported to Council on 12 December, and the
actual cost of implementation estimated at £134,000.  The difference of
£128,000 is therefore included as a saving.   
Page 29

Page 30

Funding
4.6 The draft settlement for 2024/25 has been received.  A number of elements of
funding remain undistributed at this stage.  The settlement has been analysed
and an estimate of a reduction in core budget of £1.117 million made.  This fits
with COSLA’s estimate of reduction at national level.   
4.7 Deputy First Minister wrote to the COSLA President on 19 December 2023,
setting out the conditions of the settlement.  These include a stipulation that
additional funding for free personal and nursing care and adult social pay in
commissioned services is passed in full to Integration Joint Boards and the
establishment of a new joint Education Assurance Board and the assurance
framework sought by the Cabinet Secretary for Education and Skills being in
place; commitment to exploring a national indicative rate / range of rates for
Early Learning and Childcare partner providers.  In addition, funding of £144
million is set aside, conditional on a council tax freeze.  An allocation of funding
at local authority level has been provided by Scottish Government and Moray’s
share is £2.485 million.  This is indicated as equivalent to a 5% rise, adjusted
for Council Tax Reduction.  Using that basis of calculation the Council would
expect a 5% increase to generate additional income of £2.499 million, a
marginal difference.  This is a significant sum to be foregone if the Council were
to decide to increase council tax, and for this update it has been assumed that
the council will not exercise that option, as an increase of over 10% would be
required to generate the same level of income as the likely level of grant
funding.  This is reflected in the updated Budget on a Page included as
APPENDIX 2 to this report.  The Income Strategy approved by Council on 12
December 2023 (paragraph 10 of the Minute refers) includes a strategic
approach to recovering the baseline income potentially lost by a council tax
freeze and that has been included in the indicative budget for 2025/26.. 
5 FINANCIAL PLANNING 
5.1 The overall movement in the Council’s projected position from pay award,
savings and funding can be summarised as below:   
2023/24
£m
2024/25
£m
Additional unfunded pay award 0.4 0.4
School transport 0.05 0.05
Pension contributions  (1.91)
Elgin community centre  (0.163)
Kinship and foster carer allowances  (0.128)
Reduction in core funding  1.117   
Total 0.45 (0.634) 
5.2 The net result is an improvement in the Council’s anticipated position for
2024/25 and a reduction in the funding gap of £0.634 million. 
5.3 The following issues in terms of financial planning require to be addressed:
identifying further savings; updated provision for inflation, particularly pay
awards, following this year’s increase; the impact of the revised approach
proposed to the capital plan, which is the subject of a further report to this
Page 30

Page 31

meeting; review of previously approved budget pressures and other central
provisions. 
Savings
5.4 Savings proposed in Appendix 2 of the Short to Medium Term Financial
Planning report made to Council on 25 October – the residual officer green and
amber savings – remain options available to the council and full details are
accessible via the links in the background documents to this report. 
5.5 The engagement  on leisure and library services has now been concluded and
the results are under review .  Any proposals to move to Stage 2 consultations
will be brought to a future meeting of the Council but this will be after  28
February. 
5.6 Officers have been scrutinising operational budgets to identify small pockets of
underspend which can be taken as savings without impacting on service
delivery.  These will be included in budget proposals on 28 February and an
indicative level of savings is included in APPENDIX 2. 
5.7 Potentially income generative proposals relating to Non Domestic Rates and
Council Tax on second homes will reported to Corporate Committee on 30
January 2024.  Again, indicative amounts are included in APPENDIX 2. 
Budget pressures and other provisions
5.8 Indicative provision for inflationary increases in 2024/25 was made on the basis
of 2% inflation when the budget for 2023/24 was approved on 1 March 2023. 
At that time that was the forecast level of inflation used by most commentators. 
Not only is that below current levels of inflation, the cost base used for both pay
and contract prices has been increased by inflationary uplifts in 2023/24 which
were considerable higher than allowed for in the budget.  An appropriate level
of provision is being recalculated and this will be included in the draft budget for
2024/25. 
5.9 Other pressures and provisions will be scrutinised in the light of changed
circumstances.  For example, school rolls have fallen against those predicted in
October 2022 and budget pressures will be revised accordingly.   
6 RISKS 
6.1 The Short to Medium Term Financial Strategy specifically identifies risk as an
important component of short to medium term financial planning. The
importance of considering risk is heightened as the Council’s reserves are
depleted, as that reduces the capacity the Council has to absorb unexpected or
unplanned for costs.  No new risks have been identified since the report to
Council on 12 December 2023. 
6.2  The major risks reported to Council on 25 October 2023 were of continued
overspend in MIJB, Additional Support Needs, adequacy of the inflation
provisions for 2024/25 and 2025/26 and the pay award for 2023/24.  Since then
the risk of overspend in MIJB has crystallised.  The pay award has been agreed
subject to consultation but the impact has yet to be assessed in detail. 
Page 31

Page 32

6.3 The following budget risks are currently recognised.  These cannot be
quantified at present but a scale of potential magnitude is indicated in the
budget risk table where this has been estimated. 
Service area Budget risk Scale of magnitude
Cross cutting Inflation linked contracts
/ Real Living Wage 
Pay awards Adequacy of inflation
provision and additional
SG funding still to be
assessed.
Moray Integration Joint
Board
Overspend at Q2
continues / increased
Based on current core
overspend, in the region
of £5m for council share
Additional Support
Needs
One-off funding in
2023/24 may require to
be made recurring 
Growth in need
£ 2.6m one-off funding
in total, including £0.4m
in 2024/25 
Winter weather Anything other than a
mild winter has the
potential to result in
overspend
£700,000 overspend in
2022/23
Legal fees for specialist
work regarding appeals
/ claims against the
Council and fees arising
due to staff shortages
There is no budget for
appeals / claims. 
Savings in staff salaries
partially offset fees for
work which would
normally be carried out
in house, but external
fees are higher than
staff salaries 
Interest rates Cost of borrowing
increases
The Council budgets for
£6m loans interest
repayments.  An
increase of 1% in
interest rates would
result in an increase of
£1.5m 
Debt management Invoices not raised
timeously 
Payment not pursued /
debt not actively
managed 
The Council wrote off
£222,000 in 2022/23. 
6.4 All of these factors mean that while the structural deficit remains and as further
fluctuations in the budget gap are inevitable, progress to remove that deficit
must continue with pace and urgency.  
Page 32

Page 33

7. SUMMARY OF IMPLICATIONS 
(a) Corporate Plan and 10 Year Plan (Local Outcomes Improvement
Plan (LOIP)), 
Financial Planning is integral to the Council’s overall planning processes
and allows the Council to direct resources to its agreed priorities which
include financial sustainability. 
(b) Policy and Legal
The Council is required by statute to set a balanced budget before the
start of the financial year.  The requirement is set out in the Local
Government Finance Act 1992 (section 93). 
(c) Financial implications
The Council has an underlying structural deficit which will be met from
reserves in 2023/24 and a marginally reduced budget gap is forecast for
2024/25 with further savings required in 2025/26 by which time reserves
which can be drawn upon are likely to be largely depleted.   
(d) Risk Implications
The forecast deficits for 2024/25 and 2025/26 represent a significant risk
to the Council.  There is also a risk that the deficits are understated.  The
main areas of risk are: 
Regarding the levels of savings – these represent a high proportion of
the Council’s budget and not all budgeted spend is under the Council’s
control. 
Regarding the projected levels of deficit -
• The impact of the pay awards and funding for that is still uncertain
and may impact on future years
• The impact of continuing inflation on procured goods and services
may be greater than forecast 
• Higher interest rates pose a risk for capital expenditure
• Approved savings might not achieve target
• There may be emerging budget pressures from changing
circumstances not captured in the current projections and the
areas considered to be pertinent are listed in the report. 
(e) Staffing Implications
Staffing implications arising directly from this report are discussed in the
body of the report.  Where posts are proposed to be deleted the
Transform programme provides alternative employment opportunities.   
(f) Property
There are no property implications arising directly from this report.   
(g) Equalities/Socio Economic Impact
Any savings proposal with an equalities or socio economic impact will be
subject to an Integrated Impact Assessment (IIA) when reported and
changes to IAAs for three savings are accessible via Appendix 3.  
Page 33

Page 34

(h) Climate Change and Biodiversity Impacts
There are no implications for biodiversity arising directly from this report.   
(i) Consultations
CMT and Heads of Service have been fully involved in the preparation of
proposed savings and in regular planning meetings to discuss the
budget, including budget review sessions with elected members and a
series of briefings / workshops.   
8. CONCLUSION 
8.1 There are still considerable uncertainties regarding the Council’s
budgetary position in 2023/24 and beyond, however the underlying
position is a substantial deficit, funded by use of ear-marked reserves to
balance and that is not sustainable.   
Author of Report: Lorraine Paisey, Chief Financial Officer
Background Papers: Links to Savings Templates and IIAs Appendix 1 and 2:
Report to Council 25 October 2023 (Item 9 Appendix 2) 
Reference:   SPMAN-1293228629-1025 
Page 34

Page 35

APPENDIX 1   
2023/24  2024/25  2025/26
Revenue Expenditure  £000s  £000s  £000s
Service allocations (assuming prior year savings
are achieved) 
248,752  270,862  268,928
Adjustments to brought forward figure:  (401)  (5,902)  92
Opening budget  248,351  264,960  269,020
Pay and price increases  3,293  4,236  4,330 
(Decrease) / Increase in Loan Charges per
budget 
2,000  1,500  (495)
New Burdens  3,270  79  0
Budget pressures:      
- Approved or noted for future years when
budget set 
9,175  2,454  55
- Approved since budget set  9,433  24  0
Emerging  2,111  1,518  0
MIJB core overspend    5,000  
ELC removal of specific grant    9,167  
Service developments      
-  Approved  704  0  0
- Proposed  0  0  0         
278,337  288,938  272,190       
Revenue Funding      
General Revenue Grant / NDRI  201,930  203,461  204,478
Funding from Council Tax freeze    2,485  
ELC funding tr from Specific Grant    9,167  9.167
Funding from SG for teachers pension    1,500  1,500
New burdens funding not included in grant
above 
3,270  79  0
Council Tax  49,974  50,399  54,276
Release from Repairs and Renewals Reserve  704           
Funding from General Reserves:      
Funded from Ear-marked reserves:      
Transformation  1,093  701  0
Council priorities  0  0  0
Item 7.
Page 35

Page 36

2023/24  2024/25  2025/26
MGD cash flow  0  1,136  0
Covid - planned  15,477  0  0
Covid – impact of estimated actuals  (1,236)      
271,212  268,928  269,422       
SAVINGS REQUIRED  7,475  20,010  3,488       
Savings Summary      
Savings Approved:      
Approved when budget set  3,115  828  47
Temporary savings  1,928  92  0
Further savings approved  1,908  5,223  313
Indicative Savings from I&M Programme  515  430  370
Other savings proposed  0  0  0       
Savings to be identified    13,437  2,758
Total savings  7,475  20,010  3,488       
Estimated Free Balance on General Reserves    5,000  5,000  5,000
Estimated Balance on covid Reserve    8,656  8,656  8,656
Estimated Balance on Transformation Reserve    4,388  3,687  3,687
Estimated balance on Council priorities  5,881  5,881  5,881
Estimated balance on MGD cash flow reserve  4,000  2,864  2,864
Estimated balance from retrospective service
concession saving 
11,200  11,200  11,200 
Page 36

Page 37

APPENDIX 2   
2023/24  2024/25  2025/26   
£000s  £000s  £000s 
Revenue Expenditure  278,337  288,938  272,422 
Revenue Funding  271,212  268,9280  269,422 
Savings required    20,010  3,488 23,498
SAVINGS APPROVED       
Transformation       
Children’s Services    263  245 
Lean review    235  56 
Information hubs    100   
Smarter Working    28  73 
Income Generation  76  887  105 
Asset Management    142  50 
Procurement  27  259   
Service Savings    3,073  201 
Additional one-off funding    1,586   
Total savings approved    6,573  730 
Balance of savings required    13,437  2,758 
Emerging savings 
Empty Property Relief  338   Report to
Corporate
Committee
Council Tax levy on second homes    976  68 Report to
Corporate
Committee
Increased vacancy factor  250          
Remaining budget gap  11,873  2,690 14,563
Options to bridge the gap: 
NESPF pension saving deducted from
MIJB funding 
175   
Balance of Greens and Ambers    1,714  60 
Savings - Reds    1,698  1,024 
Total    3,587  1,084 4,671         
Item 7.
Page 37

Page 38

Page 38

Page 39

REPORT TO: SPECIAL MORAY COUNCIL ON 24 JANUARY 2024 
SUBJECT: CAPITAL STRATEGY 
BY:  DEPUTE CHIEF EXECUTIVE (ECONOMY, ENVIRONMENT AND
FINANCE) 
1. REASON FOR REPORT 
1.1 To ask Council to approve the amended Capital Strategy presented in draft as
APPENDIX 1 to this report. 
1.2 This report is submitted to Committee in terms of Section III (B) (1) of the
Council's Scheme of Administration relating to consideration of the financial
and budgetary policy of the Council. 
2. RECOMMENDATION 
2.1 It is recommended that Council approve the amended Capital Strategy
as set out in APPENDIX 1. 
3. BACKGROUND 
3.1 The Council’s current Capital Strategy was approved by the Council at its
meeting on 2 February 2023 (paragraph 12 of the Minute refers).   
3.2 The Prudential Code governs the Council’s capital expenditure.  The Code
states that the capital strategy should be tailored to local circumstances
ensuring that each local authority will be able to determine its own
prerequisites for their capital strategy, while taking into account any statutory
requirements.  The draft revised Capital Strategy at APPENDIX 1 complies
with the Prudential Code 2021 and continues to follow the 2021 Chartered
Institute of Public Finance and Accountancy (CIPFA) guidance on Capital
Strategy and its emphasis on a whole organisation approach to capital
planning. 
3.3 As a document, the Capital Strategy complements other documents such as
the Council’s Treasury Management Strategy.  The Capital Strategy is not
intended to be a technical document, but instead viewed as an accessible
document, which sets out the context in which decisions about capital
expenditure are to be made.  This revised Capital Strategy sets the context for
approving the Capital Plan for 2024/25, which is the subject of a further report
to this meeting of Council.
Item 8.
Page 39

Page 40

3.4 The draft Capital Strategy at APPENDIX 1 sets out: 
• what constitutes capital expenditure;
• why the Council undertakes capital expenditure; 
• how the capital programmes of the Council relate to Council priorities
and other Council policies; 
• the link between asset management and capital planning; 
• how the Council finances capital expenditure; 
• the main aims of Treasury Management; 
• the Council’s governance arrangement for approving and monitoring
capital expenditure; 
• the risks the Council is exposed to from its capital programmes; 
• how the Council accesses appropriate knowledge and skills;
• shows diagrammatically the links between different bodies, plans and
processes and the Council’s capital plans. 
3.5 The Council’s indicative ten year plan is recognised as being unaffordable in
the long term and the draft revised Capital Strategy addresses this issue, by
proposing that after slippage anticipated in 2024/25 is accounted for, a cap on
prudential borrowing is set, thus limiting proposed capital expenditure.  The
cap is proposed to be calculated with reference to the Council’s approved
Performance Indicator for percentage of revenue budget spent on servicing
debt.  The cap will require significant scaling back on current proposals for
capital investment and the way in which it would be applied across asset
classes over coming years requires careful consideration. Work will now be
undertaken as a matter of urgency to determine that approach and the
impacts which the iterative approach set out in the strategy will inevitably have
on asset standards and/or the asset base. Progress will be reported and the
strategy and 10 year plan reviewed again accordingly.     
3.6 All proposed amendments are made in tracked changes.  There are no other
substantive amendments proposed. 
4. SUMMARY OF IMPLICATIONS 
(a) Corporate Plan and 10 Year Plan (Local Outcomes Improvement
Plan (LOIP))
The Capital Strategy indicates the links between the LOIP and the
Council’s Corporate Plan and the Council’s planned capital expenditure 
(b) Policy and Legal
Part 7 of the Local Government in Scotland Act 2003 requires local
authorities to have regard to the Prudential Code. 
(c) Financial implications
There are no financial implications arising directly from this report but  
restriction by means of a cap on expenditure will have implications for
asset standards and the asset base. The Capital Strategy is one of a
number of documents which assist in the Council’s financial planning
process. 
Page 40

Page 41

(d) Risk Implications
There are no risk implications arising directly from this report.  The
Capital Strategy indicates risks associated with capital expenditure plans
and introduces measures to deal with the risk the Council is exposed to
from inflation and in particular rising construction costs and increased
interest rates.  There may be risks to service delivery which arise from
application of the cap on capital expenditure and these will be reported
as they are identified. 
(e) Staffing Implications
There are no staffing implications arising directly from this report.  Any
staffing implications which arise from application of the cap on capital
expenditure will be reported as they are identified. 
(f) Property
There are no property implications arising directly from this report.  Any
property implications which arise from application of the cap of capital
expenditure will be reported as they are identified. 
(g) Equalities/Socio Economic Impact
There are no implications for equalities or the socio-economic duty
arising directly from this report. 
(h)    Climate Change and Biodiversity Impacts
There are no climate change or biodiversity issues arising directly from  
this report.  The revised Capital Strategy continues to recognise climate
change as a Council priority which will have implications for the Council’s
capital plan. 
(i)     Consultations
Members of the Council’s Asset Management Working Group, CMT/SMT
and Tracey Sutherland, Democratic Services Manager have been
consulted in the preparation of this report. 
5. CONCLUSION 
5.1 The Council’s Capital Strategy has been revised as part of the financial
planning process 
5.2 The Strategy underpins the Council’s 10 year indicative Capital Plan. 
5.3 The Strategy incorporates setting a cap on capital expenditure for
reasons of affordability with further work required to determine the way
in which the cap will impact across asset classes. 
Author of Report: Lorraine Paisey, Chief Financial Officer 
Background Papers: 
Ref: SPMAN-1203228629
Page 41

Page 42

Page 42

Page 43

APPENDIX 1 
THE MORAY COUNCIL CAPITAL STRATEGY 
1. INTRODUCTION 
1.1 The Council owns a range of assets which are used to deliver – directly or indirectly –
services to the people of Moray. The investment needed to ensure that these assets
meet the Council approved standard for the asset type is ascertained through the asset
management planning process.  The Capital Strategy links that process to the Council’s
Capital Plan.  The Council’s Corporate Asset Management Plan recognises that Asset
Management Planning is an iterative process, with constraints imposed by financial
affordability, and that is reflected directly in this Capital Strategy.  Asset Management is
recognised in the Council’s Medium to Long Term Financial Strategy as one of the main
vehicles which the Council will use to make strategic shifts in expenditure to achieve
financial sustainability. 
1.2 The Council also requires to invest to provide the infrastructure needed for economic
growth, in accordance with the Local Development Plan, but also to ensure that the
Council operates efficiently and can meet the needs of transformation to a sustainable
operating model. 
1.3 The CIPFA Guidance to Capital Strategy 2021 recognises that a capital strategy is not
simply a document but a whole organisation approach to effective, long-term planning
and investment, with outputs and outcomes that lead to healthy, vibrant, green and
resilient communities, businesses, organisations and geographic areas. 
1.4 The Council through its medium-term financial planning, Corporate Plan, Climate
Strategy and Asset Management Plans embraces the approach to capital strategy
recommended by CIPFA, albeit tempered by issues of affordability, which are becoming
more pressing in the current environment of higher interest rates and increased
construction costs. 
1.5 All investment in capital is made under the Prudential Code.  A revised version of the
Code was published in 2021.  The new Code contains requirements for a Capital
Strategy and this Strategy complies with those requirements.  The Code states that:  
“A capital strategy should give a high level overview of how capital expenditure, capital
financing and treasury management activity contribute to the delivery of the authority’s
plans and provisions of services along with an overview of how associated risk is
managed and the implications for future financial sustainability.” 
1.6 The Code requires each local authority to tailor their capital strategy to their own
individual circumstances, whilst containing sufficient detail to allow members to
understand how stewardship, prudence, sustainability, proportionality and affordability
will be secured, taking into account any legislative requirements on reporting. 
1.7 The Capital Strategy incorporates an approach to affordability based on an expenditure
cap.   This approach requires an iterative approach to capital planning, identifying the
expenditure required by the various drivers for capital expenditure then modifying
Item 8.
Page 43

Page 44

APPENDIX 1
planned expenditure to keep within the expenditure cap. In this respect the approach is
similar to that adopted for revenue planning: a balanced budget is identified with
estimated income limiting spending which is then planned and monitored to ensure it
stays within that balanced budget. 
2. CAPITAL EXPENDITURE 
2.1 Capital expenditure is expenditure to acquire, improve, upgrade or extend the life of an
asset, such as land and buildings, roads infrastructure, vehicles and equipment.  The
Council sets de minimis levels below which expenditure will not be accounted for as
capital.  The current levels are: 
 Land and buildings, council houses, surplus assets (valued at current value) -
£20,000
 Infrastructure, vehicles, equipment, community assets (valued at historic cost) -
£6,000 
2.2 Much capital expenditure requires a lead-in time to ensure that relevant legal conditions
are met, e.g. planning permission is in place; for project design, and for procurement. 
Capital expenditure therefore requires a longer planning time-frame than revenue
expenditure.  The Council therefore prepares and annually updates an indicative ten
year capital programme to facilitate future planning. 
2.3 Due to the short-term nature of Council funding settlements from Scottish Government,
only the first year of the plan is submitted to the Council for approval.  However, the full
ten year plan is approved as indicative of the Council’s intentions. 
2.4 Currently all of the Council’s planned capital expenditure is operational; none is for
commercial or purely income generating purposes. 
3. CAPITAL INVESTMENT OBJECTIVES 
3.1 The Council’s objectives in investing in capital are to ensure an adequate suite of assets
to deliver the Council’s services, in accordance with the Council’s policies, strategies
and plans, and priorities; legislative duties and other requirements, including
affordability.  The Council’s Short to Medium Term Financial Strategy, approved by
Council on 27 September 2023, recognises the Council’s asset base as a key financial
lever and the pressing need to review the use of the Council’s assets to generate
savings.  The Council’s Medium to Long Term Financial Strategy, approved by Council
on 25 October 2023 highlights the extent to which the Council’s forecast budget shortfall
is created by the cost of maintaining the Council’s current asset base. Projected capital
costs are very strongly influenced by the current condition of corporate assets, with the
condition of the Learning Estate in particular having been consistently benchmarked as
one of the poorest in Scotland for many years. 
3.2 A key consideration in developing the capital plan is the requirement to provide new
infrastructure and facilities to accommodate planned local developments.   
Page 44

Page 45

APPENDIX 1
3.3 The Capital Plan reflects the requirements identified in the Local Development Plan for
Moray for infrastructure projects required to support growth including transport, schools,
health services and where necessary sports and community facilities. These
requirements are established through the strategic planning of relevant departments
such as Transport and Education Resources but also include Community Planning
Partners and the evidence base on housing and employment land demand and
forecasted delivery. This evidence base allows for the long term planning of Capital
expenditure to support economic growth and also for the Developer Obligations
requirements to ensure that the development pays for the infrastructure burden it
creates. 
3.4 The process relies upon robust strategic planning of major infrastructure provision
relating to Learning Estate, Transport, Health and Sports and Community facilities.
Where this evidence base does not exist or is not robust it will be difficult to obtain
developer obligations. The Council also needs to demonstrate its commitment to deliver
the Infrastructure required to support the economic growth within the Local Development
Plan through its Capital Planning process. 
3.5 The Community Planning Partnership has 4 priorities, which are encompassed in the
Moray 2027 Local Outcomes Improvement Plan (LOIP) and the Council has reflected
these in the priorities for its Corporate Plan 2019 – 2024 (which is currently under
review):
 Our People :Ensure caring and healthy communities
 Our Place: Promote economic development and growth and maintain and
promote Moray’s landscape and biodiversity
 Our Future: Provide a sustainable education service aiming for excellence
 Work towards a financially stable council that provides valued services to our
Communities 
3.6 The General Services Capital Plan includes direct and indirect investment to promote
economic development and investment in the learning estate.  There are two strands to
working towards a financially sustainable Council which are encompassed in the capital
plan: investment in transformation (for example in digital services) and provision for
spend to save projects. 
3.7 A key outcome of the Local Housing Strategy is to ensure there is an adequate supply
of affordable housing and the LHS for 2019-24 identified a requirement to build 1,179
units over 5 years at an average of 239 per annum to meet the housing needs of Moray. 
This is reflected in the Housing Revenue Account (HRA) Capital Plan. 
3.8 Council on 10 March 2021 agreed the Climate Change Strategy 2020-2030 (Para 13
Minute refers). The strategy supports the aims of the Council’s Corporate Plan 2019-
2024 to protect and enhance our environment by creating a more resilient and
sustainable future, with the aim of Moray Council becoming carbon neutral by 2030. The
strategy proposes a phased implementation over the next 10 years. As a
complementary document the Council on 6 April 2022 approved a Route Map to Net
Zero, setting out a series of actions within a carbon management hierarchy, which
prioritises the avoidance of carbon emissions. 
Page 45

Page 46

APPENDIX 1
3.9 Although many of the actions will not require capital investment, many do and in
particular the Climate Change Strategy recognised that significant investment will be
required to ensure that all corporate buildings (including the Learning Estate) meet the
net zero carbon target by 2030. Further significant investment will be required to replace
the Council’s fossil fuelled fleet by 2030. Future Capital Plans will reflect the actions
proposed from the Climate Change Strategy and Route Map to Net Zero which will be
reviewed in 2024. 
3.10 The balance of the Council’s Capital Plan arises from the need to invest in the Council’s
current asset base, either to bring it to the approved standard or to maintain it at the
Council’s approved standard for the asset type.  The Council recognises that the asset
management requirements of the current asset base are such that the asset base is
unaffordable and that the Capital Plan must reflect the need to manage down the
required level of capital investment in part by reducing the asset base. 
4. ASSET MANAGEMENT 
4.1 The Council’s Asset Objectives were approved by the Policy and Resources Committee
on 11 October 2011: 
 To ensure that our assets are fit for purpose in terms of condition, sufficiency,
suitability, and accessibility.
 To ensure that our asset use demonstrates Best Value in terms of running costs
and environmental impacts.
 To ensure that our Asset Management processes reflect good practice.
 To ensure that our assets reflect the policies and priorities of the Council. 
4.2 The Council adopted the following standards for the asset classes within the Capital
Plan on 11 February 2014, which were reviewed during 2021 by the Asset Management
Working Group to ensure that they remain relevant: 
Asset Type Recommended Standard 
Learning Estate B condition B suitability 
Offices, Depots etc Of a standard that supports the
efficient delivery of services
Leisure Centres and Community
Centres
B condition B suitability
Children’s Play Areas To meet safety standards 
Day Centres and Resource Centres B condition B suitability 
ICT Schools 5 Year Replacement 
Offices etc 7 Year Replacement
Plant and Vehicles Replacement based on cost
effectiveness – assessment of replace
or repair
Industrial Estates B condition B suitability
Page 46

Page 47

APPENDIX 1
Asset Type Recommended Standard 
Waste Management Of a standard that supports the
efficient delivery of services
Roads 
Aim to be at the midpoint of the table
for road conditions in Scotland.
Bridges 
Street Lighting 
Harbours  B condition B suitability 
4.3 At the same meeting the Council adopted the following policy in relation to the
preparation of the Capital Plan: 
“The Council recognises the importance of the principles underpinning the CIPFA
Prudential Code in relation to capital expenditure, in particular, affordability and
sustainability of its investment plans. The Council’s policy in relation to Capital Planning
is: 
a) To maintain all buildings at a satisfactory level of condition and suitability for the
provision of council services;
b) To maintain the road infrastructure with regard to the safety of all road users and
aim to be at the mid-point of the table for carriageway conditions in Scotland;
c) To maintain all short-life assets (less than 10 years) required for the provision of
council services at the optimum level to minimise the annual cost to the council;
d) To provide investment funding to support economic development plans; and
e) To identify assets for disposal. 
In relation to the council’s housing stock the same principles are applied in the Housing
Business Plan. The Council is also required to meet the Scottish Housing Quality
Standard.”  It is implicit in the requirements for both affordability and sustainability that
the Council’s asset base is of a size that it can afford to maintain to a suitable standard. 
Following the adoption of a cap on capital expenditure the policy in relation to capital
planning will be reviewed in the context of the Corporate Asset Management Plan. 
4.4 A 30 year Business Plan for the HRA is regularly updated to ensure that housing stock
can be brought up to and maintained at the Scottish Housing Quality Standard (SHQS)
and can achieve the second Energy Efficiency Standard for Social Housing (EESSH2)
set in June 2019, for social rented houses to meet by 2032. This has a target that all
social housing meets, or can be treated as meeting, EPC Band B, or is as energy
efficient as practically possible by the end of December 2032 and within the limits of
cost, technology and necessary consent.
. 
4.5 To ensure that the General Services Capital Plan is affordable and sustainable, the draft
Capital Plan is reviewed in the context of the Council’s financial planning processes for
the General Fund. The Council’s policy decision in February 2019 to move away from
Make Do and Mend, which had underpinned the capital plan in recent years, requires
Page 47

Page 48

APPENDIX 1
required appropriate work to be forward planned and commissioned, taking into account
delays caused by the impact of the Covid pandemic and increased construction costs.
This work further highlighted the unaffordability of the Council’s current asset base. 
4.6 A Property Asset Management Appraisal (PAMA) was carried out with a view to
identifying the Council’s optimal corporate property asset base and an action plan
arising from this was reported to Council (12 December 2018). On 28 September 2022
(paragraph 10 of the minute refers), the latest progress update report to Council linked
continued work on rationalising the office estate to development of the flexible working
policy under the aegis of the Smarter Working Project Board, building on changed
working practices during and since the pandemic. 
4.7 Work continues on the Council’s Learning Estate Strategy, with a programme of
conditions surveys instructed and work has commenced on the Council’s Leisure and
Sports facilities strategy – there will be strong links between the two strategies. 
4.8 Good quality asset management information is vital to enable planning for capital
expenditure.  Where the expenditure required to maintain the Council’s asset base at
approved levels is unaffordable, the Council must takes steps to address this.  This
could be by increasing income to cover costs or by decreasing the asset base or
approved asset standard.  In its Financial Strategies (both short term and medium to
long term) the Council recognises its asset base as a key financial lever.  The financial
sustainability of the Council requires that the asset base is reduced. 
5. CAPITAL FINANCING 
5.1 A number of sources of funding are available to the Council to finance its capital
expenditure: 
 General and specific capital grants from Scottish and UK Governments
and other bodies 
 Contributions from the Council’s revenue budgets
 Capital receipts from the disposal of surplus Council assets
 Developer contributions
 Borrowing, predominantly from the Public Works Loan Board (PWLB) 
5.2 The Council is awarded General Capital Grant from the Scottish Government and this is
used to fund capital expenditure before the use of any other capital receipts.  The HRA
makes extensive use of contributions from its revenue budget, but the General Services
Capital Plan does not budget for contributions from revenue.  The amount of capital
expenditure which cannot be met from grant or other receipts will be funded by
borrowing. 
5.3 When setting the amount which it is willing to borrow, the Council must comply with the
Prudential Code.  The two main criteria for compliance with the code are that the
Council can demonstrate that the borrowing decision is affordable, sustainable, and
prudent.  Accordingly the Council approves Prudential Indicators, prescribed by the
Code, when the budget is set.   
Page 48

Page 49

APPENDIX 1
5.4 The capital plan impacts on the revenue budget in two ways: the impact of increased
loan charges required by additional borrowing required to finance capital expenditure
and the revenue (running) costs of new facilities, or revenue savings achieved through
spend-to-save projects. In the case of the Moray Growth Deal, because of the timing
difference between spend and grant profile the Council will be spending in advance of
funding to varying degrees and borrowing to cover that spend. This will incur additional
loan charges for Moray Growth Deal and the Council earmarked £4 million of reserves
to fund this expenditure.  As the grant is received this will reduce the need to borrow in
future, allowing the replenishment of reserves if this is considered prudent. As projects
enter delivery their financial spend profile is finalised and used in agreeing the planned
grant profile with Scottish Government for the year ahead.This will allow creation of a
revised financial profile at programme level in 2024/25. 
5.5 Loan charges represent the cost of interest on loans and also of principal repayments of
loans used to fund capital expenditure.  The Council has developed a local prudential
indicator based on General Services loan charges as a percentage of the total General
Services revenue budget.  This indicator is to be used, not as a definitive cap, but to act
as a guideline to assist with the Council budget setting process and to highlight the
overall impact of capital expenditure to the Council’s annual budgeted revenue costs. 
As part of the financial planning process each year the budgeted cost of borrowing will
be approved based on an approved level of borrowing for the year ahead and
indicatively for the next nine years.   Borrowing will be capped to a level deemed to be
affordable at projected rates of interest.  The budget for loan charges in 2022/23 stands
at 8.16% of the General Services revenue budget, against a Performance Indicator (PI)
target set of between 9% and 10% which was set after a benchmarking exercise with
other Local Authorities. For 2024/25 the PI can be met through anticipated slippage at
levels in line with seen over the past 2 years. For future years a cap will be applied. The
approach towards implementing a cap across asset classes requires careful
consideration and urgent work will be undertaken to agree this. When completed, this
will inevitably have an impact on both asset standards which are achievable and/or the
asset base – the iterative process described earlier. This strategy and the 10 year plan
will be further reviewed when that approach has been determined and progress will be
reported.     
5.6 The period of time over which loans repayments are made into the loans pool is
matched to the expected life of the asset.  These can vary from three to sixty years. 
5.7 Proposals for expenditure from the General Fund on asset maintenance are scrutinised
to ensure that all costs which could potentially be capitalised are funded through the
capital programme as in the short term this is the most economically advantageous way
for the Council to fund replacement of failed elements or life-expired assets. 
5.8 If appropriate specific grant funding is available it may be applied for to reduce the
amount of borrowing required or to increase the level of expenditure possible within the
Council’s agreed borrowing limit. 
5.9 The Council entered into Public Private Partnership (PPP)/ Private Finance Initiatives
(PFI) contracts in when Scottish Government was promoting these vehicles for learning
estate improvement. Under such arrangements, the Council enters into a long-term
contract with a private sector organisation to construct new assets. Annual payments
Page 49

Page 50

APPENDIX 1
are then made over the life of the contract for the assets provided. The Council has
used such arrangements to facilitate the building of new schools in Keith and Elgin. 
Such arrangements can mean capital investment where, due to financial constraints, it
might not have been possible otherwise.  All the Council’s PPP/PFI arrangements have
been supported by funding from Scottish Government. 
5.10 The Scottish Government has moved away from supporting new PPP/PFI contracts to
the LEIP funding model for school construction projects. Under this arrangement the
Council will be fully responsible for the costs of construction of new schools or
refurbishment of current schools from either existing capital budgets, or by borrowing
through the PWLB. The LEIP outcome Based Funding Model has a number of key
outcome requirements and Scottish Government revenue funding will be released on
evidence of the achievement of these agreed outcomes. These key requirements are: 
 Building Condition
 Energy Efficiency
 Digital Enabled Learning
 Carbon 
6. TREASURY MANAGEMENT
6.1 Treasury management is concerned with keeping sufficient but not excessive cash
available to meet the Council’s spending needs, while managing the risks involved.
Surplus cash is invested until required, while a shortage of cash will be met by
borrowing, to avoid excessive credit balances or overdrafts in the bank current account.
The Council is typically cash rich in the short-term as revenue income is received before
it is spent, but cash poor in the long-term as capital expenditure is incurred before being
financed. 
6.2 The Council’s main objectives when borrowing are to achieve a low but certain cost of
finance while retaining flexibility should plans change in future. These objectives are
often conflicting, and the Council therefore seeks to strike a balance between cheaper
short-term loans and long-term fixed rate loans where the future cost is known but
higher. Statutory guidance from the Prudential Code is that debt should remain below
the capital financing requirement, except in the short-term. 
6.3 Under the Prudential Code, the Council is legally obliged to set an affordable borrowing
limit (also termed the authorised limit for external debt) each year, and a lower
“operational boundary” is also set as a warning level should debt approach the limit. 
6.4 Treasury investments arise from receiving cash before it is paid out again. Any
investment made for service reasons or for pure financial gain would not generally be
considered to be part of treasury management. The Council’s policy on treasury
investments is to prioritise security and liquidity over yield, focussing on minimising risk
rather than maximising returns. Cash that is likely to be spent in the near term is
invested securely to minimise the risk of loss. Both near and longer-term investments
may be held in pooled funds, where an external fund manager makes decisions on
which particular investments to buy and the Council may request its money back at
short notice. 
Page 50

Page 51

APPENDIX 1 
7. GOVERNANCE 
7.1 The development, control, management and delivery of capital investment programmes
is of key concern to the Council to ensure that public money is used wisely, best value is
secured and the responsibility for decisions is clearly understood and taken at the right
level. In managing the aspirations for capital expenditure from Council Services, it is
inevitable that demands for capital resources to meet capital investment needs and
ambitions will exceed the resources available to the Council. 
7.2 As a consequence of this the Asset Management Working Group is tasked with
corporate responsibility for asset management.  It has the responsibility of ensuring
systems are in place to develop and update asset management plans (AMPs) to identify
the maintenance and replacement requirements to deliver the Council’s policy for assets
and agreed position in relation to standards of condition and suitability, moderated by an
assessment of affordability through the capital planning process.   
7.3 The Asset Management Working Group aims to ensure that AMPs are robust and that
tools such as options appraisal are used as appropriate.  The assumptions behind
AMPs are challenged periodically by the Group. 
7.4 The group is also responsible for developing the Council’s draft capital plan each year. 
A ten-year plan is prepared in draft and updated annually.  The group uses a process of
peer review to ensure that appropriate rigour can be demonstrated in preparing the draft
ten year Capital Plan and that revenue consequences of capital expenditure are
recognised in the financial planning process, including whole life costing in relation to
maintenance requirements.  All new proposals for capital expenditure are taken through
the Council’s corporate Gateway process, from mandate to post-project review, as
appropriate for the complexity of project and level of spend.  In 2023, the The group has
been trialling trialled a matrix for prioritising and ranking capital projects, taking into
account Council priorities and other salient factors. 
7.5 Spend-to-save is a feature of the Council’s financial strategy.  There is a presumption
that a spend-to-save proposal with a suitable business case will be approved.  However,
such proposals will always be reviewed to ensure that they fit within the Council’s
priorities and as an indicative guide the payback period of a spend-to-save project
should be three years or less.  The factors to be taken into account when assessing a
spend-to-save proposal are: 
 Size of investment required;
 Payback period;
 Risk assessment of achieving payback;
 Impact on service. 
7.6 The Council’s Planning and Development service provide the Group with information on
the infrastructure required to support new housing development – schools, roads,
leisure and health facilities – and expenditure and developer contributions are factored
into the Capital Plan. 
Page 51

Page 52

APPENDIX 1
7.7 To ensure that no capital project is considered on its own merits alone, but that all
proposals for capital expenditure are considered in the context of the Council’s overall
plans for capital expenditure, no individual requests for capital projects is considered
outwith the agreed cycle of approval when the revenue budget is set (February/March);
reviewed when capital carry forwards from the previous year are considered (generally
June); and when estimated actuals for the year are first reported (November). The
exception to this general rule is spend-to-save projects, and only then if a good case
can be made for why these should be considered outwith the normal planning cycle. 
Exception is also made for emergencies, but there is a general presumption that
planned works will be delayed to minimise additional spend.   
7.8 At a meeting on 27 February 2019, the Council (paragraph 4 of the minute refers)
agreed to commence preliminary work to revert to capital expenditure based on asset
management principles, from a Make Do and Mend policy, with a view to full
implementation by 2022/23.  The legacy Make Do and Mend policy for the learning
estate – now referred to as the BB budget – will gradually be redeveloped on asset
management principles as the Learning Estate Strategy is developed. 
7.9 Governance arrangements for the council’s HRA capital plan are separate and
recognise the ring-fenced nature of any HRA spend.  The HRA Business Plan, last
reviewed in January 2022, models scenarios for additional investment in further new
build development which has been set against a range of risk factors, rent affordability
and debt affordability levels to ensure borrowing levels are prudent, affordable and
sustainable. 
8. RISK AND RISK MANAGEMENT 
8.1 The Council is exposed to risk in various ways through its programmes of capital
expenditure.  There are risks associated with various funding streams, different types of
procurement, and predictability and controllability of spend.  These are managed by
individual project managers and corporately by the monitoring regimes for both General
Services and HRA capital, which include Transformation Board for strategic projects. 
The asset management led components of the programmes themselves are risk-
mitigators against the risk of failure of the Council’s assets. 
8.2 There are different types of risk associated with different methods of financing capital
projects.  Public-private partnerships seek to transfer risk to the private sector.  
Investors will typically expect higher returns for higher risk projects, so there is usually a
financial trade-off when risk is transferred.  General Capital Grant funding comes at no
risk to the Council.  The terms and conditions of the grant are well understood and the
risk of having to repay grant because it had been misapplied are minimal.  However,
specific grants vary greatly in their terms and conditions.  There is a much higher risk
that some specific grants – particularly some European grant funding – may have to be
repaid.  The terms and conditions are typically much more stringent and the very tight
requirements for the records to be retained and the retention period of ten years
following closure of the funding programme make European grants quite high risk. 
There will be no new European funding, but there are significant specific grants now
available from both Scottish and UK governments, many with stringent monitoring
regimes. 
Page 52

Page 53

APPENDIX 1 
8.3 The Council generates capital receipts from the sale of surplus assets.  As a general
rule, capital receipts can only be applied to capital expenditure. The Scottish
Government granted an exception to this in December 2018, for the period 2018/19 to
2021/22 (now extended to 2022/23), allowing the use of capital receipts to fund revenue
expenditure on any project designed to transform service delivery to reduce costs. Any
such expenditure must be approved by Full Council.  Whilst no risk attaches to the use
of capital receipts, there would be a risk in budgeting for significant funding from capital
receipts that they would not meet the target either in terms of amount or timing. 
8.4 Properties which no longer contribute to the delivery of the Council’s services or
objectives are deemed surplus. The Council has procedures in place to ensure that
surplus and/or under-used property is identified and reviewed prior to being offered for
disposal, with the approval of the Asset Management Working Group as an early stage
in that process. 
8.5 The Council also receives developer obligations towards the cost of development of
infrastructure or other requirements arising from developments.  They are time-limited
and the main risk from these is that they are used timeously.  The amounts received
might also be insufficient to fund the expenditure required.  Developer obligations from
major developments will typically be received over a long time scale, whereas the
Council may have to invest up front to provide infrastructure.  The Council bears the
cost associated with the time-lag in funding; the risk that future contributions may not
materialise, and the risk that relevant Council policy might change over time. 
8.6 The Council manages the risks of borrowing through its Treasury Management strategy. 
The residual risk to the Council is that borrowing can carry very long term commitments
and so capital expenditure in any one year can have revenue implications thirty or forty
years into the future. 
8.7 The Council can develop its asset base in conjunction with other public sector partners. 
The risks involved in that relate largely to the governance of the project, and to the
possibilities of one partner rescinding on their agreement.  These risks must be
addressed at the inception of the project. 
8.8 There are risks involved in developing assets through innovative funding models; such
risks are likely to be largely outwith the Council’s control. 
8.9 Inflation can pose a risk to the Council.  Construction Industry inflation can be highly
volatile and current issues within the industry and the wider supply chain resulting from
Brexit, the Covid pandemic and also the war in Ukraine mean that construction cost
increase predictions are have been varying widely with the full impact being hard to
predict.  Projects are included in the Capital Plan at current prices.  Depending on how
far in advance these have been scheduled, costs may be significantly above the original
estimate simply because of inflation in the intervening period.  This is a risk to the
affordability of the Capital Plan.
8.10 The cost to the Council of borrowing is calculated based on interest rates at that time.
The interest rates have been rising recently and it is considered likely that higher
Page 53

Page 54

APPENDIX 1
interest rates than seen in the recent past will continue.  That is a risk to the affordability
of the Capital Plan and will be taken into account when looking at future capital
proposals.  The draft capital plan for 2024/25 and indicative 10 year plan have been
adjusted to factor in current levels of inflation.
8.11 A significant risk arises from the Council’s revenue budget for repairs and maintenance. 
If the budget for revenue maintenance is insufficient and results in deterioration of
assets there may be a resulting requirement for capital expenditure to replace or renew
the asset.  If revenue budgets are reduced without a corresponding reduction in the
asset base then the Capital plan will come under pressure.  A related risk is the risk that
a health and safety issue might arise, contravening the Council’s legislative
responsibility to the public and to Council employees. These challenges are clearly
apparent in management of the Learning Estate. 
8.12 The other main risks concerning the Capital Plan relate to project management and the
many factors which impinge upon the delivery of the Capital Plan.  These factors may
be internal – such as staff shortages or competing priorities – but are frequently
external, ranging across supplier delivery time, landowner disputes/compensation
requests, unforeseen site conditions, contractor delays, weather conditions and many
others.  Project specific risks are identified in the capital monitoring reports to committee
and, where appropriate, project boards. 
9. KNOWLEDGE AND SKILLS 
9.1 The Council employs professionally qualified and experienced staff in senior positions
with responsibility for making recommendations on capital expenditure and borrowing
and investment decisions. The Council also makes use of external advisors and
consultants which are specialists in their field.  Specialist advisors are generally specific
to major capital projects, e.g. NESS energy from waste project, and employed as
required.  This approach is more cost effective than employing specialist staff directly,
and ensures that the Council has access to knowledge and skills commensurate with its
risk appetite.  In addition, the Council also employs treasury management advisors,
currently Arlingclose Ltd. 
Page 54

Page 55

APPENDIX 1
10. LINKS WITH OTHER PLANS AND PROCESSES 
Community Planning Partnership  Local Outcome Improvement Plan (LOIP) 
Asset Management Plans
•Housing
•ICT
•Roads
•Harbours
•Fleet
•Open Spaces
•Learning Estate
•Management Plans
•Property Asset Strategy
•Corporate Plan including
Short to Medium and
Medium to Long term
Financial Plans
•Treasury Strategy
•Corporate Asset
Management Plan
•Local Development Plan
•Departmental Service
Plans
Capital
Strategy
Capital
Plan
NHS Grampian Moray Integrated Joint Board MIJB
Page 55

Page 56

Page 56

Page 57

REPORT TO: SPECIAL MORAY COUNCIL ON 24 JANUARY 2024 
SUBJECT: 2024/25 CAPITAL PLAN AND INDICATIVE CAPITAL PLAN 2024 –
2034 
BY:  DEPUTE CHIEF EXECUTIVE (ECONOMY, ENVIRONMENT AND
FINANCE) 
1. REASON FOR REPORT 
1.1 To ask Council to agree the Council’s capital budget for 2024/25 and to
consider the Council’s indicative ten year Capital Plan for 2024 to 2034. 
1.2 This report is submitted to the Council in terms of the Council's Administrative
Scheme section (II) (22) and (23) relating to the approval of the annual
estimates of capital and revenue expenditure for all services. 
2. RECOMMENDATION 
2.1 It is recommended that the Council approves : 
(i) Capital expenditure of £49,662,000 for 2024/2025 as set out in the
indicative ten year Capital Plan in APPENDIX 1; and 
(ii) That this will be increased by expenditure on Moray Growth Deal as
agreed in the funding agreement with Scottish Government for
2024/25. 
2.2 It is recommended that the Council notes 
(i) the indicative ten year capital plan inclusive of cap set out in
APPENDIX 2, and 
(ii) that the plan remains unaffordable without increased external
funding. 
3. BACKGROUND 
3.1 The Council for many years has considered its capital budget alongside its
revenue budget for the coming year.  As decisions on capital expenditure have
an impact on revenue spend it has been considered good practice to view both
capital and revenue together.  However, recent changes to loans pool
Item 9.
Page 57

Page 58

accounting practices mean that there is no impact on the revenue budget for
2024/25 from capital spend in 2024/25.   
3.2 Increasing interest rates are resulting in increased costs of borrowing for the
capital plan and in the context of the requirement for the Council to make
savings, this inevitably brings the capital plan into focus for a reduction in
planned expenditure.  In addition to this, the general capital grant provided by
Scottish Government has been significantly reduced in the draft settlement and
this should be recognised as a further limiting factor for capital expenditure in
2024/25.  As with other revenue savings, the earlier savings can be identified
and approved the better the Council can plan and implement these.    
3.3 Capital planning requires a longer term focus as there is frequently a
considerable lead-in time for projects.  For this reason the Council has prepared
an indicative ten year plan.  In their Report to Those Charged with Governance,
considered by Council on 25 October 2023 (paragraph 5 of the Minute refers)
the Council’s auditors identified a risk to the Council from the level of borrowing
required by the indicative ten year plan and recommended a review of the plan
for affordability.  This had previously been recongnised by the Council as a
requirement and incorporated in  both the Short to Medum Term Financial
Strategy approved by Council on 27 September 2023 and in the Medium to
Long Term Financial Strategy approved on 25 October 2023. 
3.4 Accordingly, the basis for preparing the Council’s capital budget has been
reviewed. The Capital Plan is reviewed annually, and given the current need for
savings the Capital Plan has been subject to in-year reviews with a view to
reducing expenditure in the short term. The latest version of the 10 year Capital
Plan is based on a full review carried out in July – October 2021.  Since then 2
further reviews with a view to reducing cost have been carried out, with
reductions made on both occasions, but the focus on both occasions was
reducing spend in the short term. The current review (carried out August to
November 2023) focussed on the full 10 year span of the plan. 
3.5 The prime cost driver for the Capital Plan is asset management and so the
focus for reviewing the ten year plan was asset management based.  Budget
managers were asked for the potential to: 
• Reduce the asset base
• Reduce the asset standard
• Lengthen the period over which capital is spent (effectively increasing
the asset life) 
3.6 Although there may be scope to reduce the asset base for some asset types,
this is likely to be a long term process and in many cases dependent on the
conclusion of work already commenced.  The following table summarises the
conclusion of the review of the potential to make these amendments.  
Asset class Scope to reduce asset
base
Scope to re-programme
Bridges Close bridges when fail /
restrict weight
New prioritisation methodology
agreed 
Page 58

Page 59

Asset class Scope to reduce asset
base
Scope to re-programme
Car parks Close / repurpose / sell
land if Council owned
(some held on Common
Goods / Trusts) 
Surface car parks are net
income generative 
Capital costs
requirements mainly
relate to multi-storey car
parks 
No routine upgrades currently
included in plan
Cemeteries  New cemeteries – based
on projected demand.   
Old cemeteries – Health
and Safety issues require
a level of spend. 
Impractical to  dispose of
Dependent on statutory duties
to make provision.  Only new
cemetery in plan is for Elgin. 
Generally little scope to
reprogramme work required on
safety grounds for this or any
other asset type. 
Corporate
equipment
and furniture
Replacement cleaning etc
equipment, audio visual
for chambers –
dependent on office
review
Spend has been minimised as
smarter working office review
phases progress; chambers
equipment subject to recently
renewed contract
Corporate
offices
See smarter working 
review
See smarter working  review
Depots See depot review See depot review – OBC being
reported Q4 2023/24
ELC facilities Partly dependent on
demand.  Could reduce
level of council provision
if there is capacity in the
market for private sector
to absorb, however this
may increase revenue
costs and adds risk to
service delivery.  Could
set finite level of provision
the council is willing to
make.
Most current expenditure
arises from Care Inspectorate
requirements therefore limited
scope to extend spend profile
Flood risk
management
& flood
protection
New schemes dependent
on SG funding. 
Old schemes – residual
compensation budget
only
No unfunded programme
assumed, 
There are AMPs for current
FASs but no major element
renewals included in capital
plan, all AMP requirements low
level maintenance
Page 59

Page 60

Asset class Scope to reduce asset
base
Scope to re-programme
Harbours Sell / decommission
harbours (a complex legal
process) 
Closure of harbours
would require capital
spend to prevent usage.
Based on condition surveys so
not much scope to extend
spend profile if harbours
remain operational, as these
generally entail  Health &
Safety considerations for
harbour users.
ICT Dependent on staff
numbers / ways of
working / buildings
This is an area where Council
infrastructure needs to be
current in order to ensure
security.  Device and software
provision also needs to be at
the forefront to leverage the
greatest digital benefit, which
adds risk to any reduction of
the current programme.
Industrial
portfolio
Sell individual units to
tenants / sell whole
estates as a package 
Policy decision has been been
taken to delay new land 
acquisitions / new build at
present 
Opportunity to sell individual
units / packages of units /
entire estates should be
investigated and options
appraised 
Libraries and
leisure
facilities
Sale / CAT 
Strategy to be developed
following budget
consultation, however,
there are maintenance
issues that if not
addressed could impact
on future service delivery
at a number of current
sites. 
Moray Leisure Centre is
one site with condition
concerns that requires to
be considered, 
Limited scope to extend spend
profile as little works done in
recent years.  Scope would be
for reduced number of
sites/facilities to be maintained 
There are ongoing discussions
with Moray Leisure Ltd about
the Centre.
Parks and
open spaces
(paths, walls
etc)
In some instances sale /
CAT.  Some held on  /
common good so trickier
Largely reactive on Health &
Safety grounds so limited
scope to extend spend profile.
Play areas CAT?  Dismantle and not
replace old equipment?
Programme was for 2 play
areas a year, currently being
grant funded by SG 
Page 60

Page 61

Asset class Scope to reduce asset
base
Scope to re-programme
In absence of SG funding could
review to replace only 1 play
area a year.
Roads More likely that the asset
will be extended with the
adoption of new roads
Could allow further
deterioration, scope to do this
within current agreed asset
standard of mid table for Road
Condition Index
Road
safety/traffic
signs etc
Unlikely Programme minimal
Schools Learning Estate review. 
Overall school rolls are
expected to fall but
despite this may need
new schools to
accommodate new build
in Elgin.  Mitigation from
additional capacity in
current schools buildings
Proposed revised plan factors
in a longer period to complete
BB. 
Potential to reduce asset base
through closure – clear
statutory requirements as to
how this is done. 
Street
lighting
Possible to
decommission some
columns rather than
replace?
LED programme complete (and
was a spend to save) 
Column replacement
programme ongoing and
unlikely to be able to extend
timeline as there could be a
risk of challenge if an accident
arising from a life
expired/decommissioned
column
Vehicle and
plant
Dependent on service
delivery. 
Investigate replacing pool
cars with eg block
booking from a car club
(issues of coverage)
Likely to cost more in revenue
(maintenance and down time) 
Potential savings from move to
electric vehicles needs to be
assessed v increased capital
costs.
Waste
management
equipment
and facilities
Review coverage /
accessibility (in depot
review) 
Equipment largely
demand led
See depot review 
3.7 It is clear that reduction of the Council’s asset base must be a medium to long
term aim but that there are interdependencies with various asset class reviews
being carried out.  Realistically, reduction in asset base must focus on
buildings.  
Page 61

Page 62

External factors affecting cost
3.8 Since the last full scale review of the capital plan construction inflation has
seen considerable increases in costs for many projects.  Budget managers
were asked to review their budgets for inflation.  The most significant impact
was on the projected cost of the Learning Estate, where costs were also
projected to increase based on more up to date information from condition
surveys as well as on updated costs of construction.  Over the ten year period
from 2023/24 to 2033/34 total costs were anticipated to rise by 44%, despite
reprofiling the BB programme across 15 years as opposed to ten.  Costs of
construction are also forecast to rise where contractors have workforces
travelling from the central belt, as they are moving to a four day working week
to allow for travel time and this increases time taken and therefore the costs of
project management.  The core element of the current ten year plan  - that is
those elements not funded by specific grant or other restricted funding – was
forecast at £427 million.  Despite an element of delay in programmed spend
as described, the revised programme, if unamended, would rise to £537
million. 
Revised approach to capital planning
3.9 Having spent some years moving to an asset management planning basis for
the development of the capital plan, in the course of which knowledge of the
state of the Council’s assets has greatly increased, increased need for
investment to maintain appropriate asset standards has become apparent. 
During that period construction costs have increased and the cost of
borrowing has increased.  Identification of asset management costs remains
of vital importance for long-term planning but it is evident that the Council
cannot afford a demand led capital plan.  It is therefore recommended that the
Council, in common with many others, significantly restricts the overall budget
to be spent on capital through application of a cap on expenditure.  The need
for such an iterative approach is explicitly recognised in the asset
management planning cycle descrived in the council’s Corporate Asset
Management Plan. 
3.10 The Council has an approved Performance Indicator for the cost of financing
capital expenditure and the revised Capital Strategy, which was the subject of
a previous report to this meeting of Council, proposes that this is used to
develop a cap on capital expenditure.  Detailed development of meaningfully
capped capital expenditure will take some lead-in time and it is proposed that
as an  interim measure for 2024/25, further slippage components are
introduced to the capital plan.  The auditor’s report noted increased slippage in
capital expenditure in the past 2 financial years and the capital monitoring
report to Council on 6 December 2023 (paragraph x of the Minute refers)
noted expenditure of 11.7% of the approved capital plan as at 30 September
2023.  A significant element for slippage therefore appears to be reasonable
reflecting staffing and capacity levels as well as market conditions. 
3.11 Calculation of the slippage factor for 2024/25 and indicative caps for 2025/26
onwards are included in APPENDIX 2.  Work will be undertaken on how the
cap can be allocated across asset classes and progress reported. The capital
plan remains unaffordable in the latter part of the ten year period, even with
very significantly capped expenditure – shown as “Headroom for 10% ceiling”
Page 62

Page 63

in Appendix 2.  Without significant Scottish Government funding the Council’s
aspirations for its Learning Estate will not be achieved.  An update on the
Learning Estate Strategy will be given to the next meeting of the Education,
Children’s and Leisure Services Committee.   
4. CAPITAL BUDGET 
4.1 The Council’s Financial Regulations require approval of detailed capital spend
by Service Committees.  Accordingly the draft plan at APPENDIX 1 and
indicative 10 year plan at APPENDIX 2 are at a summary level for each asset
class.  This section of the report indicates what is envisaged to be
encompassed by the summary budget for 2024/25, any specific considerations
in developing the budget, and for 2024/25 the impact of applying the proposed
level of slippage pro rata to base budget, with adjustments as set out below. 
4.2 Bridges.  The proposed initial allocation of £965,000 is based on the recently
approved prioritisation process for bridge refurbishments, covering work on
three bridges plus an allowance for footbridges, totalling £965,000.  A slippage
factor of £165,000 is proposed.  This could be met in part if contingencies / risk
allowances are not needed in full or could result in the delay of letting one
contract with any disruption that entails.  In addition to this a further £1,500,000
is allowed as potential match funding for Cloddach bridge in the event of this
project being included – no slippage factor is proposed because of the
conditions of external funding.  If the project is not approved the saving of
£1,500,000 would be offset against the slippage factor. In total this amounts to
£2,300,000. 
4.3 Car parks.  This budget is partly for waterproofing work on multi storey car
parks but also includes an allowance of £150,000 for resurfacing and upgrade
of lighting in car parks.  There has been no budget for resurfacing and upgrade
of lighting in recent capital plans and it is recommended that this is reinstated. 
A slippage factor of £79,000 is proposed, resulting in a budget of £421,000. 
4.4 Climate Change.  £750,000 was included as a lump sum allowance which was
included in 2023/24 and not spent. Plans are being developed and will be
reported in due course.  It is therefore envisaged that this budget will be carried
forward into 2024/25.  A slippage factor of £119,000 is proposed, resulting in
£631,000 budget. 
4.5 Corporate buildings.  This budget of £65,000 is for replacement office
furniture and building cleaning equipment.  The allocation is an annual, historic
allocation.  A slippage factor of £10,000 is proposed. 
4.6 Fleet.  The £3,530,000 allocation for fleet replacement is based on an asset
management plan which considers the average optimum replacement timeline
of different vehicle types. Actual conditions of vehicles are then taken into
account when the replacement programme is agreed with service departments. 
The programme is based on a like-for-like replacement.  A strategy for fleet
decarbonisation is being prepared.  A slippage factor of £558,000 is proposed,
reducing the budget for 2024/25 to £2,972,000. 
Page 63

Page 64

4.7 Flood risk management and coastal protection.  The £74,000 allocation for
2024/25 is for coastal protection.  This allows for an annual programme of
works.  A slippage factor of £12,000 is proposed. 
4.8 Harbours.  The capital plan for harbours is based on inspections of the
condition of the Council’s six harbours and the first three years in the plan are
based on planned asset management arising from the most recent inspections. 
However, the nature of the asset is such that the detail of the works required
can frequently not be ascertained until works have commenced.  A slippage
factor of £34,000 is proposed.  This would reduce the initial allocation of
£217,000 to £183,000. 
4.9 ICT.  A slippage factor was incorporated into the allocation for 2023/24, based
on past expenditure against budget.  A further slippage factor of £65,000 is
proposed for 2024/25.  The Council is dependent on ICT however a range of
factors, including staffing resource impact on the ability to spend the capital
budget.  As more applications move to the Cloud, there may be less need for
capital and more for revenue as cloud based systems are viewed as the
provision of services and not assets and so cannot be classified as capital
expenditure.  A budget of £346,000 after slippage is proposed for 2024/25. 
4.10 Industrial Portfolio.  As a result of the last review of the capital plan all
significant expenditure on the industrial portfolio was deferred and the allocation
of £198,000 for 2024/25 is for minor upgrades only.  A slippage factor of
£31,000 is proposed, resulting in a budget of £167,000. 
4.11 Learning Estate. At £40,213,000 the proposed allocation amounts to 69% of
the proposed capital plan for 2024/25.  £32,500,000 is planned spend on Elgin
High School extension and the replacement Forres Academy.  The conditions
of LEIP funding for Forres Academy make timeous spend an imperative and so
the £25,750,000 budgeted for Forres Academy has been largely excluded from
the allocation of the slippage factor, however slippage at the early stages of a
major project is likely.   A slippage factor of £3,412,000 is proposed. 
4.12 Libraries and Leisure.  Development of the leisure and libraries strategy will
impact on the required capital allocation and at this stage no amendment to the
2024/25 allocation within the indicative ten year plan approved in March 2023 is
recommended.  Based on the same percentage slippage generally applied
across the programme a slippage factor of £442,000 is proposed.  Major works
will be dependent on the strategy and so this factor could perhaps be
increased.  However, condition surveys may identify further works required.  No
significant allocation towards Moray Leisure Centre is currently included.  A
provisional budget of £2,418,000 for Libraries and Leisure in total is
recommended. 
4.13 Parks and Open Spaces.  The allocation of £1,062,000 includes £630,000
expenditure on a replacement cemetery in Elgin.  It also includes play park
refurbishment which will be funded from Scottish Government grant.  A slippage
factor of £168,000 is proposed.  The increased grant funding facilitates
achieving the slippage factor.   
Page 64

Page 65

4.14 Road improvements.  Based on previous expenditure against capital budget a
slippage factor was included in 2023/24 and a slightly higher factor - £664,000
– is proposed for 2024/25.  This leaves a budget of £3,536,000 for 2024/25. 
4.15 Street lighting.  The allocation of £800,000 is historic.  There is a considerable
backlog of life-expired street lighting columns but the workload which can be
carried out is limited by the size of the team.  A slippage factor of £120,000 is
proposed. 
4.16 Traffic and road safety.  This allocation covers a range of road safety
measures and new road markings, replacement and new road signs and
replacement traffic equipment.  It has traditionally been underspent, with the
interplay with active travel external funding enabling expenditure to be
reallocated to such funding.  A slippage factor of £58,000 is proposed, which
would leave a budget of £315,000. 
4.17 Waste Management.  The recurring element of this allocation is for
replacement containers at recycling centres and for new and replacement
wheeled bins.  A further £225,000 is included in 2024/25 for upgrade of
recycling facilities.  A slippage factor of £63,000 is proposed.  The overall
budget would then be £338,000. 
4.18 Two areas of spend to save are proposed: the construction of a salt shed at
Keith depot, included in the draft capital plan at its original estimated cost of
£117,000 and an allowance of £15,000 for small scale energy efficiency
projects.  As these are proposed to generate savings no slippage factor has
been allocated.  The requirements for the salt shed are being reviewed as part
of the depot review and revised proposals will be brought forward. 
4.19 A number of specific capital grants are expected in 2024/25.  The only one
currently confirmed is £411,000 for Cycling, Walking, Safer Streets.  No
slippage factor has been allocated as these funds must be spent in year. 
5. RISKS 
5.1  The following areas are considered to represent risks to the Council’s budget in
regard to the capital plan for 2024/25 and future years: 
• Increasing inflation rates and interest rates
• Future settlements and level of effective ring-fencing of funds
• The condition of the Learning Estate
• De-carbonisation requirements 
5.2 Mitigations to these risks are: 
• Monitoring inflation and interest rates with the assistance of our treasury
advisors and amending forecasts accordingly
• Collective lobbying through COSLA
• Continued development and management of the Learning Estate Strategy
Delivery Programme
• Seeking funding opportunities, monitoring developments in technology.
Page 65

Page 66

.5.3 If the capital plan is not contained within affordable limits then there is a severe
risk to the revenue budget, as increased levels of financing costs would create
futher revenue budget pressures and the need for even more savings to be
found. 
6. SUMMARY OF IMPLICATIONS 
(a) Corporate Plan and 10 Year Plan (Local Outcomes Improvement
Plan (LOIP))
Financial Planning is integral to the Council’s overall planning processes
and allows the Council to direct resources to its agreed priorities. 
(b) Policy and Legal
The Local Government (Scotland) Act 2003 (section 35) places a duty on
local authorities to manage their capital expenditure.  It also provides for
Scottish Government to issue regulations for the governance of capital
expenditure.  In practice this means that compliance with the CIPFA
Prudential Code is in effect a statutory duty. 
(c) Financial implications
The Council has a funding gap for 2024/25 and a projected funding gap
for 2025/26.  Capital expenditure in 2024/25 will have revenue
consequences in 2025/26.  It is prudent to consider these in early course
and minimise the impact of capital expenditure on the funding gap, thus
avoiding creating additional revenue pressures and consequent need for
further savings.     
(d) Risk Implications
Unforeseen circumstances can give rise to unplanned capital expenditure. 
These can range from asset element failures through the impact of
extreme weather events to sudden emergence of health and safety issues
or accidental damage to one of the Council’s assets by a third party.   
(e) Staffing Implications
Staffing implications arise indirectly from this report as much of the capital
plan is dependent on Council staff, and competing priorities, revenue and
capital, can impact on the ability to deliver planned capital works. 
(f) Property
There are no property implications arising directly from this report.  Any
property implications arising from the caital plan will be reported to the
appropriate service committee as detailed capital spend plans are
reported for consideration. 
(g) Equalities/Socio Economic Impact 
The equality duty
Under the equality duty (set out in the Equality Act 2010) the Council
must have ‘due regard’ to the need to eliminate unlawful discrimination ,
harassment and victimisation as well as well as to advance equality of
Page 66

Page 67

opportunity and foster good relations between people who are in a
protected group and those who are not.   
Groups protected by the Act are age, disability, gender reassignment,
pregnancy and maternity, race, religion or belief, sex and sexual
orientation. 
There are no proposals in this report which directly impact on the
equality duty, however the bulk of the capital plan involves spend on
schools and this clearly has most impact on younger people. 
Socio-Economic Impact
The proposals do not impact on the socio-economic duty. 
(h) Climate Change and Biodiversity Impacts
There are no implications for climate change and biodiversity arising
directly from this report, although application of the proposed slippage
factor will have implications for the timing of detailed planned spend. 
(i) Consultations
CMT and Heads of Service have been consulted in the preparation of
this report. 
7. CONCLUSION 
7.1 The Council has limited scope to reduce its asset base in the short term
but has an immediate need to reduce its planned capital spend. 
7.2 A cap on capital spend is proposed, with this being actioned in 2024/25 by
incorporating a slippage factor into the capital plan. 
Author of Report: Lorraine Paisey, Chief Financial Officer
Background Papers: 
Ref:   SPMAN-1293228629-1018 
Page 67

Page 68

Page 68

Page 69

APPENDIX 1 
Core Plan   
Area  
£000s
Slippage
£000s
Budget 
2024/25
Bridges 2,465 165 2,300
Car parks 500 79 421
Climate Change 750 119 631
Corporate buildings 65 10 55
Early Learning and Childcare   
Fleet 3,530 558 2,972
Flood Risk Management & Coastal Protection 74 12 62
Harbours 217 34 183
ICT 411 65 346
Industrial Portfolio  198 31 167
Learning Estate 40,213 6,412 33,801
Libraries & Leisure 2,860 442 2,418
Parks & Open Spaces 1,062 168 894
Road Improvements 4,200 664 3,536
Street Lighting 800 120 680
Traffic & Road Safety 373 58 315
Waste Management 401 63 338
Slippage factor (9,000)  
Non core   
Spend to save 132  132
Moray Growth Deal   
Other funded projects 411  411
Total expenditure 49,962  49,962
Funding 
General Capital Grant (7,341)  (7,341)
Specific grants (411)  (411)
Contributions (35)  (35)
Receipts (155)  (155)
Borrowing (41,720)  (41,720)
Total funding (49,962)  (49,962)
Assumptions 
Item 9.
Page 69

Page 70

Page 70

Page 71

APPENDIX 2       
Core Plan          
Area (before slippage) 2024/25 2025/26 2026/27 2027/28 2028/29 2029/30 2030/31 2031/32 2032/33 2033/34 Total
Bridges 2,465 3,050 650 1,000 1,700 50 50 3,050 50 50 12,115
Car parks 500 400 150 150 150 150 150 150 150 150 2,100
Climate Change 750          750
Corporate buildings 65 65 65 65 65 65 65 65 65 65 650
Early Learning and Childcare           
Fleet 3,530 3,530 3,530 3,530 3,530 3,530 3,530 3,530 3,530 3,530 35,300
Flood Risk Management & Coastal
Protection
74  300 1,158 4,400      5,932
Harbours 217 1,160 300 900 300 300 900 300 300 900 5,577
ICT 411 579 542 502 632 502 562 502 502 502 5,236
Industrial Portfolio  198 160 1,100 921 3,191 2,910 945 780  680 10,885
Learning Estate 40,213 62,963 65,955 54,205 37,705 28,615 47,205 20.205 20,955 20,000 398,021
Libraries & Leisure 2,860 510 320 1,660 310 60 60 120 120 120 6,140
Parks & Open Spaces 1,062 619 285 285 285 285 285 285 285 285 3,961
Road Improvements 4,200 4,200 4,600 4,600 4,600 4,600 4,600 4,600 4,600 4,600 45,200
Street Lighting 800 800 800 800 800 800 800 800 800 800 8,000
Traffic & Road Safety 373 335 373 450 1,373 351 351 351 351 351 4,659
Waste Management 401 135 135 135 135 135 135 135 135 135 1,616
Slippage factor/Cap (9,000) (15,000) (35,000) (40,000) (30,000) (15,000) (25,000) (10,000) (10,000) (6,000) (195,000)
Non core           
Spend to save 132 15 15 15 15 15 15 15 15 15 267
Moray Growth Deal           
Other funded projects 411          411
Total expenditure 49,662 63,521 44,120 30,376 29,191 27,368 34,653 24,888 21,858 26,183 351,409
Funding           
General Capital Grant (7,341) (7,500) (7,500) (7,650) (7,803) (7,959) (8,118) (8,281) (8,446) (8,615) (79213)
Specific grants (411)          (411)
Contributions (35) (1,031) (28) (130) (179) (90)  (1,186) (58)  (2,737)
Receipts (155) (155) (155) (155) (155) (155) (155) (155) (155) (155) (1,550)
Borrowing (41,720) (54,835) (36,437) (22,441) (21,054) (19,164) (26,380) (15,266) (13,199) (17,413) (272,196)
Total funding (49,662) (63,521) (44,120) (30,376) (29,191) (27,368) (34,653) (24,888) (21,858) (26,183) (351,409)
Item 9.
Page 71

Page 72

Assumptions 
Loans pool interest rate 5.6% 5% 4% 3.6% 3.6% 3.6% 3.6% 3.6% 3.6% 3.6%
Inflation (CPIH) 3.6% 3.2% 3% 2% 2% 2% 2% 2% 2% 2%
Projected revenue budget (not
funded from reserves)
251,613 254,519 258,498 262,596 266,725 271,002 276,422 281,950 287,589 293,341
Base budget loans pool 16,407 16,407 18,163 19,534 21,956 24,821 26,845 30,475 30,970 31,497
Impact of previous year’s
borrowing 
2,986 3,681 2,187 1,285 1,206 1,098 1,511 874 756
Allowance for PPP/PFI 5,126 5,242 5,354 5,431 5,510 5,590 5,672 5,755 5,841 5,927
Interest funded from ear-marked
reserve  
(3,000) (5,000) (3,200)     
Offset LEIP funding     (2,551) (2,551) (2,551) (2,551) (2,551) (2,551)
Total cost of borrowing for PI 21,533 24,635 25,428 25,691 26,304 30,790 31,970 33,564 34,524 35,367 
Headroom for 10% ceiling  3,628  817  422  568  368  (3,690)  (4,328)  (5,369)  (5,765)  (6,032) 
Page 72

Page 73

REPORT TO: SPECIAL MEETING OF MORAY COUNCIL ON 24 JANUARY 2024 
SUBJECT: MORAY GROWTH DEAL – MANUFACTURING INNOVATION
CENTRE FOR MORAY FULL BUINESS CASE 
BY:  DEPUTE CHIEF EXECUTIVE (ECONOMY, ENVIRONMENT AND
FINANCE) 
1. REASON FOR REPORT 
1.1 To inform Council of progress made by the Moray Growth Deal to prepare a
full business case for the Manufacturing Innovation Centre for Moray (MICM)
project and grant delegated authority to enable final approval of the business
case so enabling the project to move into delivery. 
1.2 This report is submitted to Council in terms of Section (II) (20) of the Council’s
Scheme of Administration relating to a new policy matter which does not fall
within the terms of reference of any Committee. 
2. RECOMMENDATION 
2.1 It is recommended that the Council: 
(i) consider and approve the Full Business Case (FBC) summarised
in this report and contained in Appendix 1; 
(ii) delegate authority to the Depute Chief Executive (Economy,
Environment and Finance) to make any final changes as required
following completion of the Government review process, with a
view to agreeing final versions of each FBC to progress to
implementation; and 
(iii) delegate authority to the Depute Chief Executive (Economy,
Environment and Finance) or other such signatory as may be
required to accept the Government grants for the projects in line
with the terms of the Moray Growth Deal 
3. BACKGROUND 
3.1 In November 2021 (para 9 of the minute) Council approved full deal
documentation for the Moray Growth Deal that included a full business case
Item 10.
Page 73

Page 74

for the Digital Health project and outline business cases for the remaining 7
projects.   
3.2 Since then the project has been working to prepare it’s FBC, with the Council
presented with an overview of the status of activity as part of the MGD
2021/22 annual report that was submitted in March (para 13 of the minute)
and as an information report in May 20232.   
3.3 This report summarises and presents the MICM FBC which is a £6.85m
project led by Highlands and Islands Enterprise. 
3.4 The submission of this document to the Council is part of an extensive
assurance process that is outlined below. 
Project Pre-
submission
workshop
with the
Governments
Project
Board
approval
MGD Programme Board
approval
Other
approvals
Moray
Economic
Partnership First
approval to
trigger
Government
review
Second
review
following
Government
feedback*
MICM 3 Aug 2023 8 Sep
2023
25 Aug 23 12 Dec 23 31 Oct 23:
HIE Board  
14 Dec 23 
*  Alongside providing approval of the full business case document, this meeting also agreed to
delegate authority to the Depute Chief Executive (Economy, Environment and Finance).  This involves
making any final changes as required following the completion of the Government review process,
with a view to agreeing the final version that will enable the project to enter delivery.   
3.5 Government clearance of the FBC is expected early to mid Quarter 4 2023/24
and this, coupled with approval by the Moray Council on 24th January 2024
and the Community Planning Board (following review and approval by MEP,
with similar delegated authority to the Senior Responsible Officer (SRO) on
29 February 2024 will enable the project to enter delivery in late Q4 2023/24.   
4. CURRENT STATUS OF THE MICM PROJECT FBC 
4.1 The Government review process for the business case has commenced and
the draft appended to this paper incorporates feedback provided from Policy
Advisors.  At this stage, it is not expected that further Government review will
result in material changes to the FBC but rather changes which are more
about added detail or presentation, hence the recommendation seeking
delegated authority for final adjustments. Delegated authority is similarly
sought to accept grant for the project in line with terms agreed previously. 
4.2 In advance of the Council meeting, Member briefings have been held on all
projects progressing to FBC shortly which gave an opportunity for the
respective project teams to provide more detail on proposed activity.  
Page 74

Page 75

5. OVERVIEW OF MICM FBC v2 (APPENDIX 1) 
Summary of the project 
5.1 MICM will see the construction of a Manufacturing Innovation Centre at the
Forres Enterprise Park and will be delivered through a combination of
repurposing existing buildings and new-build construction.   
5.2 Manufacturing accounts for 19% of jobs in Moray, but 67% of the businesses
employ 9 people or less.  This, coupled with a low level of R&D spend, has
given rise to a need for this sector to be supported to innovate, helping to
improve resilience, size and turnover.
5.3 In light of this, the facility aims to develop an innovation ecosystem which will
help manufacturing businesses in Moray to become world-class. 
5.4 Capital totalling £5.6 million will be required to deliver the facility, split between
multiple partners: 
Funding partner Capital contribution
Highlands and Islands Enterprise (HIE) £2,557,010
Scottish Government £610,362
UK Government £2,441,448
TOTAL £5,608,820 
5.5 The project will also be supported by revenue funding of £1.25m from the
Scottish Government to support any deficit in the facilities operating costs
during the first 10 years. 
Investment objectives to be achieved
1 To increase BERD (Business Enterprise, Research and Development) in
Moray’s indigenous manufacturing companies
2 To increase growth, productivity, and efficiency in Moray’s indigenous
manufacturing companies
3 To increase the number of manufacturing start-ups in Moray
4 To support the attraction of manufacturing inward investment to Moray
5 To accelerate the transition to net zero in Moray’s indigenous manufacturing
companies 
What will this project mean for Moray?
5.6 Services to be delivered by the facility include: 
- Supporting product and process innovation projects in businesses
- Facilitation of networking, peer-to-peer learning, and collaboration
- Effectively co-ordinating service delivery guiding/steering businesses to
the best solution for them and the most suitable providers.  This will
involve signposting businesses to support from a number of agencies
including (but not limited to): 
o Highlights and Islands Enterprise
o University of Highlands and Islands (MAATIC and BE Hub projects)
o National Manufacturing Institute Scotland (NMIS) 
Page 75

Page 76

o Scottish Manufacturing Advisory Service (SMAS)
o Interface
o Links to other innovation centres
o Business Energy Scotland 
- Playing an active role in cluster management (advanced manufacturing,
multi-sector)
- Developing a detailed assessment and baseline of productivity and net
zero performance, needs and opportunities for each manufacturing
business
Overview of options considered and the preferred approach
5.7 Three options were considered for the project, with the first discounted due to
the need to support growth within the innovation landscape of Moray
manufacturing businesses. 
Option Description
1 Do nothing, business as usual:  No Growth Deal funding to be
used, current way of working continues. 
2 Do the minimum:  Phase 1 MICM hub (in refurbished premises) and
Phase 2 grow on space (mix of refurbished premises and new build),
3 Do the maximum:  Phase 1 MICM Hub (in new premises) and new
Phase 2 grow on space 
5.8    Focusing on options 2 and 3, an appraisal of the expected benefits each would
deliver was carried out: 
Ref Indicator
Option 2
MICM re-using
Unit 9/and Unit
10/new grow-on
space
Option 3
Full new build
of MICM and
grow-on
space
A Present Value(2023/24) of GVA
benefits and carbon disbenefits £m £40,144,579 £39,947,076
B
Present Value (2023/24) Net Additional
Capital and Revenue Costs (£m) (over
and above Option1, and adjusted for
Optimism Bias)
£6,234,244 £12,385,869
C Net Present Social Value (£m) [A-B] £33,910,335 £27,561,207
D Benefit Cost Ratio [(A / B] 6.4  3.2 
E
Switching Value Benefits (% reduction
in PV of benefits for BCR to be less
than 1)
-84% -69%
F
Switching Value Costs (% increase in
PV Costs required for BCR to be less
than 1)
643.9% 322.5% 
Page 76

Page 77

5.9  Option 2 was identified as the preferred option.  It delivers the same level of
benefits more cheaply, faster, repurposes existing buildings and in doing so
consumes less embodied carbon in the construction process. 
5.10  While GVA analysis forms an essential part of the economic appraisal, it is
worth highlighting that in employment terms (excluding construction effects). 
By year 10 Option 2 is expected to generate over 600 net additional job years
of employment at the Moray level (over 700 job years at the Highlands and
Islands level, over 800 job years at the Scottish level and over 600 job years
at the UK level).  By year 15 this is forecast to have grown to almost 700 net
additional job years for Moray (more than 800 job years at the Highlands and
Islands level, almost 1000 job years at the Scottish level and over 700 job
years at the UK level). 
Key headlines from the business case
5.11  The project has modelled the cost benefit cost ratio over 10, 15 and 25 year 
horizon, all of which are expected to generate strong outcomes for Moray 
Time horizon for economic analysis
10 years 15 years 25 years
Benefit cost ratio  4.5 6.4 9
Net additional benefit for Moray
economy
£27.4m £40.1m £57.7m 
5.12 The service offering is expected to be operational in autumn 2024, with work 
on development of the grow on space expected to start in 2026.   
5.13  As the project prepares to enter delivery, the key risk relates to lower than
expected revenue generation.  In the event that the facility expects to exceed
the £1.25m in revenue funding being provided by the Scottish Government,
HIE will seek to ensure the viability of the facility by: 
- Analysing facility performance data and refining the operating model 
- Securing additional revenue to support the facility 
6. SUMMARY OF IMPLICATIONS 
(a) Corporate Plan and 10 Year Plan (Local Outcomes Improvement
Plan (LOIP)
The MGD projects contribute to the Corporate Plan priority of promoting
economic development and growth, whilst meeting the LOIP vision of
raising aspirations, reducing inequalities in educational attainment,
providing access to employment, expanding choices for residents, and
improving livelihood and well-being.   
(b) Policy and Legal
Each MGD project has been developed to meet local, regional and
national policy agendas in line with legal requirements where relevant.  
Page 77

Page 78

(c) Financial implications
This project is funded through the Growth Deal and led by a partner
external to the Council – Highlands and Islands Enterprise.   
(d) Risk Implications
The risks associated with these projects are captured in the FBCs and
there are robust risk management processes embedded within both
project and programme governance arrangements. 
(e) Staffing Implications
No direct staffing implications beyond existing support for MGD. 
(f) Property
Approval of these FBCs will see a range of properties constructed: 
Partner Facility to be constructed
HIE MICM facility at the Forres Enterprise Park. 
(g) Equalities/Socio Economic Impact
Equalities and socio impact assessments have been considered as each
project has worked to develop their FBCs.  Each FBC document
contains an appendix that outlines further information on equalities /
socio economic impact.  Further information can be found in appendix 9
of the MICM FBC. 
(h) Climate Change and Biodiversity Impacts
As part of their review process with the Governments, Growth Deal
projects need to take account of carbon and environmental
considerations, with net zero aspirations being integrated into design
briefs for new properties. 
(i) Consultations
The full business case that this report seeks approval for have been
subjected to significant consultation, as highlighted in section 3.4.   
Consultation has taken place with the Depute Chief Executive
(Economy, Environment and Finance), the Head of Economic Growth
and Development, the Head Governance, Strategy and Performance,
the Equal Opportunities Officer, the Chief Financial Officer and
Democratic Services Manager have been consulted and comments
received have been incorporated into the report. 
7. CONCLUSION 
7.1 This paper introduces a nearly final draft of the MICM FBC.  The Council
is asked to consider and approve this which, in conjunction with
receiving Government clearance, will enable it to enter delivery. 
7.2 Whilst the FBC presented has already been the subject of significant
review, the Council is asked to delegate authority for the Depute Chief
Executive and Moray Growth Deal Senior Responsible Officer to
approval final iterations following comments from the Governments.
Page 78

Page 79

7.3 The Council is also asked to delegate authority to the Depute Chief
Executive (Economy, Environment and Finance) or other such signatory
as may be required to accept the Government grants for the projects in
line with the terms of the Moray Growth Deal. 
Author of Report:  Michael Kelly, Moray Growth Deal Programme Manager
Background Papers: 
Full Deal documentation (December 2021)
Moray Growth Deal 21/22 annual report 8 March 2023 and 24 May 2023 
Page 79

Page 80

Page 80

Page 81

Moray Growth Deal 
Full Business Case 
Version Number: Issue 1 Created: 17/01/2024 13:02 Saved: 17/01/2024 14:53 
The following is to be completed by High Level Governance Board 
Approved By/Date Group or Officer Name Date of meeting/decision
Approval
(choose from drop
down menu) 
Choose an item.
Comments Any relevant comments from the approving authority should be
documented here. 
PROJECT REF/NAME Manufacturing Innovation Centre for Moray (MICM)
PROJECT SPONSOR Highlands and Islands Enterprise (HIE)
COMPLETED BY David Reid, Moray Area Manager, HIE
DATE 5th September 2023
VERSION Issue 2 
Project Category Strategic 
Item 10.
Page 81

Page 82

Page 2 of 208 
Table of Contents
1. Executive Summary ............................................................................................ 4
2. The Strategic Case ........................................................................................... 18
Organisational overview ....................................................................................... 18
The strategic context ............................................................................................ 18
Business Strategy and Aims ................................................................................. 25
Investment objectives ........................................................................................... 25
Existing arrangements .......................................................................................... 25
Conclusions on current supply of innovation services .......................................... 29
Business needs – current and future .................................................................... 29
Potential scope and service requirements ............................................................ 40
Benefits criteria ..................................................................................................... 41
Strategic risks ....................................................................................................... 42
Constraints ........................................................................................................... 43
Dependencies ....................................................................................................... 43
3. The Economic Case .......................................................................................... 44
Project logic model ............................................................................................... 44
Short-listed options ............................................................................................... 44
Economic Appraisal .............................................................................................. 52
The Preferred option ............................................................................................. 57
4. The Commercial Case ...................................................................................... 61
Required Services ................................................................................................ 61
How will MICM co-ordinate its services to SMEs with SMAS? ............................. 63
How will MICM co-ordinate its services to SMEs with MAATIC and BE Hub? ...... 63
The MICM customer journey ................................................................................ 67
Treatment of VAT ................................................................................................. 69
Potential for Risk Transfer .................................................................................... 69
Procurement strategy and implementation timescales ......................................... 70
Proposed Charging Mechanisms .......................................................................... 73
Proposed Contract Lengths .................................................................................. 74
Proposed Key Contractual Clauses ...................................................................... 74
Personnel implications .......................................................................................... 76
5. The Financial Case ........................................................................................... 77
Project expenditure and income ........................................................................... 77
Overall affordability ............................................................................................... 85
Impact of sensitivity testing on revenue model ..................................................... 85
6. The Management Case ..................................................................................... 87
Programme management arrangements .............................................................. 87
Project management arrangements ...................................................................... 87
Use of special advisors ......................................................................................... 89
Arrangements for change and contract management ........................................... 91
Arrangements for benefits realisation ................................................................... 91
Arrangements for the carbon management process ............................................. 93
Arrangements for risk management...................................................................... 93
Arrangements for post project evaluation ............................................................. 93
Gateway review and internal audit arrangements ................................................. 94
Contingency plans ................................................................................................ 94
Page 82

Page 83

Page 3 of 208 
Communications plan ........................................................................................... 95
MICM operating model transition .......................................................................... 95
Appendices .............................................................................................................. 98
Appendix 1: SOC and OBC options development ................................................ 99
Appendix 2: Economic Impact Assessment ........................................................ 104
Appendix 3: MICM Logic Model .......................................................................... 115
Appendix 4: Optimism Bias assessment ............................................................. 117
Appendix 5: Carbon Categorisation Form ........................................................... 122
Appendix 6: Risk Register .................................................................................. 123
Appendix 7: Capital works – cost estimates ....................................................... 124
Appendix 8: Capital works – contract template ................................................... 137
Appendix 9: Equalities Impact and Fairer Scotland Duty Impact Assessment .... 179
Appendix 10: HIE Equality and Diversity Policy .................................................. 187
Appendix 11: Carbon assessments .................................................................... 197
Appendix 12: Cash drawdown by financial year ................................................. 208 
Page 83

Page 84

Page 4 of 208 
1. Executive Summary
What are the issues?
Manufacturing employs over 5,600 people in Moray in 215 businesses1. Some 19%
of total jobs in the area are in manufacturing compared to 8% for Scotland as a
whole. Employment in food and drink products account for 10% of total jobs in the
Moray economy2. Wages in Moray are below the Scottish average. The average
annual gross full time mean wage is £31,987, 8% lower than for Scotland (£34,936).
The gap widens to 13% when all (full time and part time) jobs are included (£24,879
compared with £28,660 for Scotland3).
The locality has a strong base of skills in manufacturing and engineering. Some 50
out of the 135 whisky distilleries in Scotland are in Moray4. The area is also home to
the global headquarters of several household brands. However, over 67% of
businesses employ nine people or less5 and many lack the resources, and
particularly the knowledge, to execute R&D capital projects and secure the benefits
of enhanced productivity. In 2020 Moray ranked fifth lowest of all local authority
areas in Scotland in relation to spending on business enterprise research and
development (BERD) as a proportion of GDP (0.16% of GDP in 2020 versus a
Scotland average of 0.92%)6.
How will we fix the issues?
What is required is a grass roots cultural shift in how businesses gain insight into the
latest process and production efficiencies that are available, and how they can use
them to undertake product and process innovation.  It is considered that there is an
urgent need for investment in a Manufacturing Innovation Centre for Moray
(MICM) that will act as a local focal point for business to access best practice and,
crucially, help them to collaborate with universities and other research institutes, and
support them in accessing relevant support from organisations such as Highlands
and Islands Enterprise (HIE), National Manufacturing Institute Scotland (NMIS),
Scottish Manufacturing Advisory Service (SMAS), Interface (the knowledge
connection for business), the Scottish Innovation Centres, the Advancing
Manufacturing Centre at Fort William7, Make it Smart Hub for Construction at UHI
Inverness8 and others such as UHI Moray’s MAATIC and Business Enterprise Hub
projects.
To be effective MICM must cover multiple sectors, from textiles to distilling, and be
positioned as “by industry, for industry” to have the necessary credibility to persuade 
1 https://www.gov.scot/publications/businesses-in-scotland-2022/documents/
2 Moray’s Economic Strategy (2022). http://www.moray.gov.uk/downloads/file147200.pdf
3 Moray’s Economic Strategy (2022). http://www.moray.gov.uk/downloads/file147200.pdf
4 https://seemoray.co.uk/things-to-do/distilleries/#:~:text=Moray%20is%20home%20to%20the,in%20this%20relatively%20small%20area
5 https://www.gov.scot/publications/businesses-in-scotland-2022/documents/
6  https://www.gov.scot/publications/business-enterprise-research-and-development-2020/ (local authority estimates are not currently
available beyond 2020) 
7 https://www.whc.uhi.ac.uk/business/advancing-manufacturing/
8 https://www.mis-hub.com/
Page 84

Page 85

Page 5 of 208 
businesses to invest in innovation and their transition to net zero. It also must be
local – large facilities located in distant cities need a local presence to customise and
make their services accessible to rural businesses.  MICM will support businesses to
keep abreast of emerging technologies, showing their relevance, and supporting
their deployment, leading to improved production outcomes and profitability as well
as faster decarbonisation. It will also help local businesses to understand more about
their local supply chains and the benefits from involvement in the relevant clusters of
business activity. In doing so it will make a clear, direct contribution to achieving the
objectives set out in Scotland’s National Innovation Strategy9.
Who is involved?
The project is led by Highlands and Islands Enterprise (HIE) and has been guided by
a Project Board comprising HIE, National Manufacturing Institute Scotland (NMIS),
University of the Highlands and Islands (UHI) Moray, Moray Council, Scottish
Manufacturing Advisory Service (SMAS), Scottish Government’s Advanced
Manufacturing Team and private sector manufacturers in Moray.
How did we identify the solution?
An initial assessment of a long list of options was undertaken to support the
preparation of the Strategic Outline Case for the project in 2019.  These options
were refined further as part of the development of the Outline Business Case (OBC)
in 2021 and, following approval to a number of Change Requests, have been subject
to further detailed design as part of this Full Business Case (FBC) process.
The project development process has been informed by a review of the supply side
delivery of innovation support and demand-side surveys of manufacturing
businesses of all sizes as well as consultation workshops with the Moray Growth
Deal Business Assembly and the Moray Chamber of Commerce. This has clearly
evidenced the need for, and benefits from:
• Enhanced co-ordination of innovation support targeted at manufacturing
business;
• The need to encourage much stronger interaction between manufacturers and
the knowledge base and the ways in which access can be enhanced;
• Meeting the property needs of new manufacturing start-ups, in particular the
need for flexible unit sizes on easy in, easy out terms, and accelerator grow-on
space on flexible terms for them once they have “graduated” from incubation
space;
• Enhanced business services to support decarbonisation 
9 https://www.gov.scot/publications/scotlands-national-innovation-strategy/pages/1/
Page 85

Page 86

Page 6 of 208 
What is the solution?
Following the supply-side and demand assessment work conducted at this FBC
stage, the MICM Project Board met to review the project’s investment objectives and
agree how the project should be positioned to maximise its added value within a
complex delivery landscape.
The MICM service solution is set out in Figure 1.1 on the following page.
In the period since the preparation of the original MICM OBC there has been
substantial change to the MAATIC Growth Deal project and its geographical location.
Therefore it has now been decided that MICM should be located at the Enterprise
Park Forres as a stand-alone facility adjacent to other manufacturing businesses,
including those at the heart of the North Coast Space Cluster, as well as taking
advantage of existing conference facilities at Horizon Scotland.
There will continue to be close collaboration between MICM and MAATIC as well as
with the Business Enterprise Hub (BE Hub) project.  In parallel with MICM’s FBC, the
MAATIC and BE Hub projects have also been developing their own FBCs. As
outlined at the OBC stage, MICM intends to work closely with both projects to
optimise the customer journey for both businesses and individual entrepreneurs. In
relation to MICM/MAATIC engagement, this will mean that where MICM engagement
identifies skills needs, it will facilitate rapid access to relevant advanced
manufacturing skills support through MAATIC in the first instance.  The same will
apply where it identifies management training and broader entrepreneurship skills
development needs, where it will signpost to BE Hub.  MAATIC and BE Hub have
also mapped out the customer journey for referrals into MICM, which will provide
innovation services and facilities to support entrepreneurship activity, both with
MAATIC students (including professional doctorate students) and BE Hub
manufacturing service users who need product and process innovation support.
In parallel with the detailed design process, three Change Requests have been
approved for MICM since the OBC stage.  These approved a change in project
location from land adjacent to RAF Lossiemouth to Enterprise Park Forres as well as
approving the principle of using existing premises to facilitate a more rapid start to
the project.  The most recent Change Request was approved by the MGD Board in
May 2023 and validated by the MICM Project Board at an options workshop in June
2023.  This specified the following options for appraisal.
Option 1: Business as Usual – Do Nothing – No Growth Deal Funding
Option 1 is the Business as Usual option that assumes no Growth Deal funding. 
This is the Reference Case against which the performance of other options can be
judged.  Under this scenario and given the tight fiscal environment and other funding
priorities, MICM would not happen.  Project development costs have been incurred
to bring the MICM project to FBC stage (£134,000).  These sunk costs are included
in Option 1. 
Page 86

Page 87

Page 7 of 208 
Figure 1.1: Manufacturing Innovation Centre for Moray (MICM) project – service solution 
Sector leadership: inspiring, assessing needs, co-ordinating, persuading, joining up
Awareness: marketing, promoting, demonstrating, organising events
Technical: demonstrating equipment and new technologies with MICM buildings as net zero
demonstrators
Core service offer:
Investment Objectives: • To increase BERD (Business Enterprise, Research and Development) in Moray’s indigenous
manufacturing companies
• To increase growth, productivity, and efficiency in Moray’s indigenous manufacturing companies
• To increase the number of manufacturing start-ups in Moray
• To support the attraction of manufacturing inward investment to Moray.
• To accelerate the transition to net zero in Moray’s indigenous manufacturing companies
Playing an active role in cluster management (advanced manufacturing, multi-sector)
Developing a detailed assessment and baseline of productivity and net zero performance, needs and
opportunities for each manufacturing business
Effectively co-ordinating service delivery (deploying HIE, UHI (MAATIC), NMIS, SMAS, Interface, Innovation
Centres, Business Energy Scotland etc.), guiding/steering businesses to the best solution for them and the
most suitable providers
Supporting product and process innovation projects in businesses
Facilitation of networking, peer-to-peer learning, and collaboration Key tasks:
MICM HUB
(Unit 9, Enterprise Park Forres)
MICM Grow-on space
(Unit 10 and adjacent new build expansion, at
Enterprise Park Forres)
4 industrial units totalling 793 sq. m
Property:
6 x 40-70
sq. m
incubator
units
Demonstrati
on and
technical
space
Service provider
and private
sector desk
space
Horizon Scotland (existing events space to be used by MICM)
Wider space cluster activity 
Net zero
demonstrator
Page 87

Page 88

Page 8 of 208 
In addition to Option 1, two intervention options have been appraised as part of the
Full Business Case.  The options are identical in relation to service offer (and thus
revenue model) but take a different approach to the delivery of the capital project.
Option 2: Phase 1 MICM Hub (in refurbished premises) and Phase 2 grow-on
space (mix of refurbished premises and new build)
In this option the MICM Hub (Phase 1) would be provided quickly through a
reconfiguration of the HIE-owned Unit 9 at Enterprise Park Forres.  This light
industrial unit was constructed in 2009, is heated using ground source heat pumps,
and is about to be vacated by a growing electronics manufacturer which is in the
process of expanding elsewhere on the Park.  The design of this building with a
ground floor, mezzanine and sloping roof, has made it difficult to let on a sustainable
basis for manufacturing, but its internal layout lends itself well to the MICM
requirement.
With relatively limited reconfiguration required (the work package will be set out in
detail in the Commercial Case), the capital works on the MICM Hub would be
complete during 2024. These works will also allow the MICM Hub to act as a net
zero demonstrator, with sensors and measurement displays helping to explain how
businesses can improve their existing premises in a cost-effective manner as they
embark on their own net zero transition.
The intention is for a MICM Director to be appointed in spring 2024.  They will start
developing MICM’s presence with local business immediately and ensure that the
project can progress quickly as soon as the MICM Hub is available.  The Director’s
work will include active co-ordination with service providers (notably NMIS, SMAS
and Interface) to ensure a regular presence at MICM and their involvement in
organisation of MICM events, as well as liaison with MAATIC, BE Hub, Business
Gateway and the HIE Moray Area team to market the six incubator units (40-70 sq.
m each) and other flexible workspace.
The MICM Hub will also have a technical and demonstration space that features a
range of specialist prototyping and testing equipment (e.g., 3D printing), helping it to
play an active role in supporting product and process innovation for business as well
as demonstrating relevant, accessible technologies and persuading them to invest in
their internal processes to move up the innovation and net zero ladders.  A MICM
Centre Manager will be appointed by the MICM Director by autumn 2024 to take on
the responsibility of managing MICM’s technical and demonstration activity and part-
time administrative/marketing support will also be recruited during Year 1 of
operation.
The provision of MICM grow-on / accelerator space in Phase 2 will support the MICM
customer journey for those businesses in Hub incubators, enabling them to move on
to larger modern industrial premises on Enterprise Park Forres while remaining part
of the “MICM family” with continued access to MICM Hub support as required.  Once
again, the project is following the principle of repurposing existing building rather
than new build.  Here the proposal is for existing commercial premises at HIE-owned
Unit 10 (already fitted with air source heat pumps) to be reconfigured to three units of
approximately 150 sq. m, supplemented by a 250 sq.m new build unit with air source
heat pumps and solar PV panels.  The new unit would be on land immediately
Page 88

Page 89

Page 9 of 208 
adjacent to Unit 10 owned by HIE with outline planning consent for industrial use. 
These units are a very short walk from Unit 9 / the MICM Hub and at the very heart
of Enterprise Park Forres, adjacent to Orbex and the emerging space cluster.  The
intention is to have these units ready for occupation from 2027/28, in Year 4 of the
MICM Hub’s operation, by which time it is anticipated that one or more occupants
from the incubator space will be looking to move on to larger premises.
MICM incubator and grow-on units will all be let at market rents, but will be provided
on “easy in, easy out” terms.  Flexible lease terms, and the inherently higher risk
profile of new start-up or early stage businesses, are not an attractive proposition to
property developers.  In Moray there is little speculative development of even
mainstream premises for established businesses on standard leases.  This is why, in
Option 1, without Growth Deal funding, nothing would be delivered. Crowding out is
not a concern given this specialised floorspace.
It is always difficult to demonstrate demand in markets that do not currently exist, but
there is clear evidence of unmet demand for incubator space in Moray.  Horizon
Scotland is at 110% occupancy with a waiting list with some businesses there now
having to occupy meeting rooms.  The proposed MICM incubator space is also
entirely complementary to the activities of MAATIC and the BE Hub project in Elgin.
The former will provide desk space for researchers and the latter will provide pre-
incubation space for start-ups across all sectors as well as wider management skills
support for established entrepreneurs.
A key feature of MICM’s operation is to facilitate access by as many existing
businesses as possible to practical manufacturing innovation support that will make
a difference to their bottom line.  MICM will actively co-ordinate existing service
delivery to ensure that business access expertise and funding already available from
HIE, the National Manufacturing Institute for Scotland (NMIS), the Scottish
Manufacturing Advisory Service and Innovation Centres as appropriate to each case. 
It is anticipated SMAS, NMIS (operated by the University of Strathclyde) and
Interface will be present at MICM on a regular basis and actively involved in
supporting delivery and that there will be well-established links and cross-referral
mechanisms with MAATIC and BE Hub as described above. This proactive
collaboration will lead to Moray businesses developing more collaborative R&D
projects and Knowledge Transfer Partnerships to translate ideas into workable
prototypes, accessing NMIS, relevant Innovation Centres and Catapult facilities as
needed.
MICM will stimulate demand through targeted engagement and free demonstration
activities and events as well as a free initial diagnostic service in a concerted effort to
maximise interest and take-up.  The business survey detailed in the Strategic Case
shows a clear, unmet demand for practical “how to” support. The MICM business
model assumes that MICM will charge on a consultancy basis for specific project
support to individual businesses.  The revenue model also assumes that as it gains
momentum, MICM will attract private sector funding from OEMs to support its
delivery activity.
By re-using two existing buildings the project can proceed more quickly and at lower
capital cost than new build.  From a net zero perspective, this approach will also
offer a much better demonstration to other businesses of how existing commercial
Page 89

Page 90

Page 10 of 208 
premises can be upgraded.  Importantly it will also consume less embodied carbon
in the construction process.  It will be an immediate statement of MICM’s intent to
show businesses how they can make important incremental changes to
decarbonisation in ways that have a positive impact on the bottom line.  This will
compliment MICM’s wider efforts to support businesses in decarbonising in their
operations. 
Option 3: Phase 1 MICM Hub (in new premises) and new Phase 2 grow-on
space
Option 3 assumes the same concept, service provision, floorspace configuration and
equipment specification as Option 2.  However, in this option, the MICM Hub is a
new build.  This accords with the approval to Change Request 3 (May 2023) that a
new build comparator should be included in the FBC.  Although it would provide new
premises, Option 3 will be significantly more expensive in capital expenditure terms
and will consume much more embodied carbon in the process.
How will the benefits accrue?
The benefits fall into the following main categories:
• One-off benefits from the construction process and procurement of equipment
(Options 2 and 3).  These temporary benefits are excluded from the value for
money calculation (in line with OCEA guidance at OBC stage);
• Operational benefits associated with the ongoing operation of MICM, its
employment of three staff (2.5 FTEs) as well as occupancy of the incubator
units;
• Catalytic, or further generated benefits, associated with:
o The additional penetration of innovation support services amongst indigenous
manufacturing businesses in Moray and enhancements to their
performance (Options 2 and 3)
o Business acceleration benefits arising from the graduation of businesses from
MICM Hub incubators and their further growth, facilitated by the MICM
grow-on units (Options 2 and 3)
o Additional inward investment to Moray resulting from the cluster development
activities attributable to MICM’s innovation activity.
In addition to the employment, income and GVA impacts of MICM, a RICS Whole
Life Carbon Assessment will be commissioned for Option 2 as part of the detailed
design process for the initial phase involving Unit 9.  The embodied carbon and
operational carbon disbenefits of both options will form part of the value for money
assessment in the final version of the FBC when this is submitted.
Is it financially sustainable?
Yes. Business plan forecasts for the preferred option, considering the full range of
revenue costs (e.g., salaries and overheads) and revenue income potential (adopting
cautious assumptions regarding build-up of incubation and grow-on space
occupancy), suggest that it could be self-sustaining within 10 years of opening. 
Page 90

Page 91

Page 11 of 208 
However, this is dependent on the provision, and successful take-up, of incubator
and grow-on floorspace as well as MICM becoming established as a provider of
manufacturing innovation consultancy support for small and medium sized
manufacturers in Moray.
How does the project fit in the strategic landscape?
MICM will make a direct contribution to national, regional, and local manufacturing
innovation objectives.
At the UK level, the vision in the UK’s recently published Innovation Strategy10
(2021) is to turn the United Kingdom into the world’s most innovative country.
In Scotland, building the innovation capabilities of Scottish manufacturing is
highlighted as a priority in the Scottish Government’s manufacturing recovery plan11
(2021) and its 10-year National Strategy for Economic Transformation (NSET)
published in March 202212.  Scotland’s National Innovation Strategy was published in
June 202313 which up-dated the 2016 Manufacturing Action Plan, building on NSET,
highlighting the importance of building on clusters.  These clusters focus on those in
which Scotland is considered to have major advantages, including energy transition,
health and life sciences, data and digital technologies and advanced manufacturing,
with specific roles identified for NMIS and the National Robotarium. The university
sector is also identified as having a major role to play in terms of investing in
commercialisation research, including a new Investment Fund.
MICM is designed to provide a place-based response to both the UK and Scottish
Government’s innovative objectives. It fits directly with several of the key strands in
NSET and the Scottish National Innovation Strategy where it offers a clear and
significant contribution to the ‘productive businesses and region’ strand with its focus
on innovation and connecting businesses to manufacturing innovation infrastructure,
regionally and Scotland-wide. The establishment of MICM will also enhance the
capacity of local businesses to compete in new and emerging markets, generating
good quality employment prospects and career development opportunities for the
existing workforce as well as new entrants.  If the right connections can be
established, a more skilled workforce will be one of the outcomes, particularly arising
through links with MAATIC and UHI Moray as well as and other institutions such as
NMIS and Strathclyde University.
At a regional level, MICM will directly support the “Prosperity,” “Planet” and “Place”
pillars of HIE’s Strategy 2023-28 and help to deliver three out of four of its outcomes.
The Prosperity pillar identifies innovation as key to improving productivity,
competitiveness, profitability and entrepreneurship. It is recognised that businesses
are not sufficiently engaged in R&D to drive performance and growth, and that
developing and accessing skills can be a challenge. The region has considerable
existing, and planned, innovation, infrastructure and links to national enablers such
as NMIS and Innovation Centres, which will be a catalyst for sectoral growth and 
10 https://www.gov.uk/government/publications/uk-innovation-strategy-leading-the-future-by-creating-it
11 https://www.gov.scot/publications/making-scotlands-future-recovery-plan-manufacturing-business-regulatory-impact-
assessment/#:~:text=The%20actions%20set%20out%20in,new%20technologies%20and%20training%20opportunities
12 https://www.gov.scot/publications/scotlands-national-strategy-economic-transformation/
13 https://www.gov.scot/publications/scotlands-national-innovation-strategy/
Page 91

Page 92

Page 12 of 208 
development, advanced manufacturing, the just transition to net zero and business
and academic collaboration. However, HIE’s Strategy recognises that this
infrastructure needs to be harnessed effectively to meet business need in local
areas.  The Place pillar seeks to develop business and innovation infrastructure,
collaborating with stakeholders to identify needs, promote innovation and deliver new
property assets that will contribute to its outcomes and interventions will be focused
on projects which aid the delivery of regional transformational opportunities.  Under
its Planet pillar, the focus is on taking every opportunity to raise awareness of the
need for decarbonisation amongst all key stakeholders and increase the economic
and social benefit from the transition to net zero.  At local level MICM is also aligned
to HIE’s Property Strategy, particularly in relation to the reuse of existing buildings
and the transition to net zero.
What else is happening in the region?
Moray is the manufacturing focus of the North Coast Space Cluster (NCSC). Orbex
operates a launcher production facility at Enterprise Park Forres, designing and
building the rockets that will launch from Sutherland Spaceport.  Orbex is at the
centre of a new cluster of local businesses providing services and products to the
growing space sector and using data for commercial purposes and academic
research14.  Sited adjacent to Orbex, the MICM Hub, its wider programme of events
and support and the MICM grow-on space will provide a strong innovation
dimension to cluster development activity.
At a local level, MICM also fits well with the objectives of the recently published
Moray Economic Strategy (2022) particularly in enhancing the productivity of the
manufacturing sector and growing wages. As the Strategy makes clear ‘innovation
through automation and new work processes (including artificial intelligence) will
also be required. These will, in some sectors, help to offset limited availability of
workers. This will include traditionally important sectors such as food and drink
manufacturing (and its supply chain) and timber processing.’ 
Finally, as with other Moray Growth Deal projects, MICM provides a real opportunity
to show how Growth Deal activity can be integrated with, and contribute to, national,
regional, and local planning policy as it seeks to meet new imperatives and add real
additionality in the outcomes that are secured from new investment in the local
economy.
MICM is well aligned with the current National Planning Framework (NPF4) and
Scottish Planning Policy (SPP).  Building on the Planning Act (S) Act 2019, NPF4
indicates that planning should be underpinned by the six underlying principles of just
transition, conserving and recycling assets, local living, compact urban growth,
rebalanced development, and rural revitalisation. Scottish national spatial planning
policy applies these six principles in supporting the planning and delivery of
sustainable places (seeking to reduce emissions, restore and better connect
biodiversity); liveable places, enabling people to live better, healthier lives; and
productive places, underpinned by a greener, fairer, and more inclusive wellbeing
economy. 
14 https://www.hie.co.uk/latest-news/2022/february/17/space-sector-set-to-create-new-jobs-in-highland-and-moray/
Page 92

Page 93

Page 13 of 208 
In relation to the planning and delivery of productive places, the NPF4 guidance
would appear to support MICM, and the project also directly addresses the objective
of conserving and recycling assets (re-use of Unit 9 in Option 2) as well as
contributing to rebalanced development and rural revitalisation.  MICM’s net zero
demonstrator role also fits well with NPF4 objectives.
Appropriate attention is also being given to supporting the Town Centre First
principle with an example of this being the coordination between the MICM, MAATIC
and the Enterprise Hub projects to ensure appropriate alignment: MICM is
deliberately based at Enterprise Park Forres to be at the heart of the emerging space
cluster, whereas MAATIC and the Business Enterprise Hub are focused on Elgin to
ensure that student activity in the city is maximised.
All the MGD projects are embedded in the indicative regional spatial strategy (iRSS)
as submitted to the Scottish Government in September 2020.  Moray Council’s
Strategic Planning and Development Manager is on the Moray Growth Deal Board
and is actively engaged with HIE staff in “pre” pre-application discussions, which
includes master planning processes, active travel, access to transport and ensuring
that the Place Principle is appropriately embedded in proposals.
The proposal for MICM, including the efforts made by HIE, UHI and other partners to
co-ordinate its design within other Moray Growth Deal projects such as MAATIC and
the BE Hub, fits well with the national, regional, and sub-regional strategic landscape
summarised above.  It seeks to enable Moray companies to undertake more
innovation to increase their existing turnover and increase their productivity by
realising the opportunities available to them from new advances in technology and
automation. As a rural region with a relatively small existing population, Moray has
the infrastructure capacity to accommodate increased population that may arise from
increased employment created by MICM. The complementary Housing Mix Delivery
project is focusing on the delivery of affordable housing.
Economic Case: Value for Money and the Preferred Option
An economic appraisal for the two intervention options is provided in Table 1.1.  This
presents the Present Value of a 15-year stream of the GVA and carbon impacts at
the Moray level, the associated Present Value of Net Costs over the same period
(after adjustment for Optimism Bias), the resulting Net Present Social Value and the
Benefit Cost Ratio.
Option 2 has a higher Benefit Cost Ratio than Option 3 and a higher Net Present
Social Value.  Option 2 is cheaper in capex terms because it repurposes Unit 9
(MICM Hub) and Unit 10 (the majority of the MICM grow-on space).  Although not
reflected in the relative benefits (which have been modelled to be identical), Option 3
will also take 9-12 months longer to achieve an operational start, since it would
require a more complex detailed design process and it is reasonable to expect that
achieving a building warrant would take longer, in addition to a longer build period.
Table 1.1 also presents switching values for both benefits and costs. Based on 15
years of benefits and costs at the Moray level, it would take a reduction of 84% in the
benefits before Option 2 had a BCR of 1:1 and costs would need to increase more
than six-fold. This demonstrates the strong resilience of the value for money of this
option to potential changes in costs or benefits.
Page 93

Page 94

Page 14 of 208 
Table 1.1: Appraisal Summary Table - 15 years at the Moray level
Ref 
Option 2
MICM Hub re-using
Unit 9 / and Unit 10
/ new grow-on
space
Option 3
Full new build of
MICM Hub and
grow-on space
A Present Value(2023/24) of GVA benefits and
carbon disbenefits £m £40,144,579 £39,947,076
B
Present Value (2023/24) Net Additional Capital
and Revenue Costs (£m) (over and above
Option1, and adjusted for Optimism Bias)
£6,234,244 £12,385,869
C Net Present Social Value (£m) [A-B] £33,910,335 £27,561,207 
Benefit Cost Ratio [(A / B] 6.4  3.2 
Switching Value Benefits (% reduction in PV of
benefits for BCR to be less than 1) -84% -69% 
Switching Value Costs (% increase in PV Costs
required for BCR to be less than 1) 643.9% 322.5%
Note 1: benefits are the operational and catalytic GVA benefits of MICM and capital and operational carbon
disbenefits; the temporary GVA benefits arising from the project’s construction are excluded from the NPSV and
BCR analysis
Note 2: costs and benefits are over and above the Option 1 No MGD funding reference case
Note 3: costs and monetised GVA benefits and carbon disbenefits have been discounted at a rate of 3.5% (the
Social Time Preference Rate) to a base year of 2023/24 (year 0), the year of appraisal
Note 4: 15 years means the period starting in year 1 2024/25 and ending in year 15 2038/39
Table 1.2 shows the relative performance of Option 2 over 10, 15 and 25 years.  The
performance of Option 2 becomes even more apparent over a 25-year period once
all the benefits are fully on stream.  Over a 25-year period Option 2 is forecast to
have a Benefit Cost Ratio of 9:1 at the Moray level and 11:1 at the Scottish level.
Table 1.2: Appraisal Summary Table – Preferred Option (Option 2): Present Value of
net additional costs and net additional GVA benefits and carbon disbenefits over 10,
15 and 25 years at the Moray, Scotland, and UK levels 
Over 10
years
Over 15
years
Over 25
years
Present Value (PV) net additional costs of Option 2
(adjusted for OB on capital costs) £6,119,769 £6,234,244 £6,411,783
PV net additional benefits for Moray (incl. carbon,
excl. construction) £27,356,451 £40,144,579 £57,739,169
PV net additional benefits for the Highlands & Islands £30,470,080 £45,063,149 £65,618,333
PV net additional benefits for Scotland £28,145,231 £44,485,982 £70,802,141
PV net additional benefits for UK £17,239,323 £31,092,176 £56,680,003
Benefit Cost Ratio (BCR) – Moray 4.5 6.4 9.0
BCR – H&Is 5.0 7.2 10.2
BCR – Scotland 4.6 7.1 11.0
BCR – UK 2.8 5.0 8.8
Net Present Social Value – Moray £21,236,682 £33,910,335 £51,327,386
Net Present Social Value - H&Is £24,350,312 £38,828,905 £59,206,550
Net Present Social Value – Scotland £22,025,463 £38,251,738 £64,390,359
Net Present Social Value – UK £11,119,554 £24,857,932 £50,268,221 
Page 94

Page 95

Page 15 of 208 
Option 2 is the preferred option in Value for Money terms. It delivers the same
level of benefits more cheaply, faster, repurposes existing buildings and in doing so
consumes less embodied carbon in the construction process.
While GVA analysis forms an essential part of the economic appraisal, it is worth
highlighting that in employment terms (excluding construction effects):
• By year 10 Option 2 is expected to generate over 600 net additional job years of
employment at the Moray level (over 700 job years at the Highlands and Islands
level, over 800 job years at the Scottish level and over 600 job years at the UK
level).
• By year 15 this is forecast to have grown to almost 700 net additional job years
for Moray (more than 800 job years at the Highlands and Islands level, almost
1000 job years at the Scottish level and over 700 job years at the UK level)
• By year 25 it is estimated that MICM could deliver almost 800 net additional job
years in the Moray economy (over 950 at the Highlands and Islands level, over
1,100 job years at the Scottish level and over 900 job years at the UK level).
How much will it cost?
Table 1.3 shows how the capital expenditure requirement (with an allowance for
future inflation) has changed from OBC stage.  The FBC’s preferred option for MICM
(Option 2) will have a capital cost of £5.61 million (including contingency and inflation
allowance).  This is lower than the £6.89 million anticipated at OBC stage due to the
repurposing of existing premises.  Based on the funding shares established at OBC
stage, of the new total capex requirement Moray Growth Deal funding is anticipated
to provide just over £3m (£2.44m from UK Government and £0.61m from the
Scottish Government) with HIE investing £2.56m (net) to cover the balance.
Table 1.3: Option 2 (preferred option) – capital funding requirement and funding
strategy, including inflation 
OBC capital funding
strategy
Anticipated FBC capital
funding strategy
Highlands and Islands Enterprise 3,142,000 2,557,010*
Scottish Government 750,000 610,362
UK Government 3,000,000 2,441,448
Total 6,892,000 5,608,820
* Note: In addition, the capital model assumes that HIE will provide grant-in-aid funding of
£550,000 to a new MICM entity at the end of the Growth Deal period to acquire the MICM Hub
and Grow-on assets from HIE (see How will it be delivered?) 
MICM is forecast to become financially sustainable within ten years of opening.  Until
its revenue-generating capacity comes fully on stream, it is forecast to require
revenue deficit funding totalling £1.25m to December 2031 (from the Scottish
Government’s £1.25m revenue contribution to the project).  In the event that the
deficit position extends beyond the Growth Deal, HIE will be responsible for
managing any additional revenue deficit.  Table 1.4 shows an income and
expenditure profile for the project from January 2024 to December 2031 when the
Page 95

Page 96

Page 16 of 208 
Growth Deal ends, showing how, as income builds up, MICM is expected to become
self-sustaining by the end of the period.
Table 1.4: Option 2 (preferred option) – revenue income and expenditure including
inflation
Growth Deal
Year 3 4 5 6 7 8 9 10 To Dec
31
MICM year 0 1 2 3 4 5 6 7
Financial year 2023/24 2024/25 2025/26 2026/27 2027/28 2028/29 2029/30 2030/31 2031/32
Income 0 21,975 122,526 192,341 262,470 316,548 394,260 441,231 452,262
Expenditure 47,388 328,261 395,946 443,965 410,894 421,167 491,361 442,488 432,655
Expenditure
minus income
(surplus is
negative)
47,388  309,173  276,423  254,703  151,580  107,853  100,416  4,655 -19,607 
Importance sources of income for MICM include the following:
• Rental income from incubator units in the MICM Hub and the MICM Grow-on
units
• Rent of other desk spaces by service providers and the private sector in the
MICM Hub
• Revenue from project consultancy services to manufacturing SMEs.
These will take time to develop.  There are clear interdependencies between the
capital model (which creates assets to generate an income stream) and revenue
funding to help stand the project up in its initial phase, while income streams develop
to their full potential.
How will it be delivered?
HIE will lead the project.  It will design and procure the refurbishment of Unit 9 and of
the subsequent phase of grow-on units (Unit 10 and new build).  
It is anticipated that, subject to FBC approval, tender pricing for the first phase would
be available in early 2024, enabling works to commence prior to the end of the
2023/24 financial year (subject to final approval of tendered prices).  Detailed design
and tendering of the second Phase will be designed and tendered in 2026/27.
Capital risks are low due to HIE’s long experience of property development, its
ownership of Units 9 and 10 and of the land adjacent to Unit 10.  Risks are further
mitigated by the fact that Enterprise Park Forres is already zoned for these types of
developments.
Until the end of the Growth Deal period MICM will be managed as a HIE project,
governed by a Project Board and with the HIE Area Manager as Senior Responsible
Owner.  From a MICM operational delivery perspective, HIE is currently exploring
ways in which the impact of MICM staffing proposals can be mitigated to avoid
adding to HIE’s head count.  Options being explored include setting MICM up as a
project within HIE with its own dedicated, fixed-term project staff, or an outsourced
Contract for Services. Whatever option is pursued, the management of MICM would
Page 96

Page 97

Page 17 of 208 
sit within HIE’s Moray Team, supported by HIE’s Innovation, Growth Deal and
FM/Property Teams.
As MICM builds up its revenue streams and approaches self-sufficiency, HIE will
work with the MICM Project Board on a transition plan that will lead to MICM
becoming a standalone entity by 31st March 2031. Any decisions on the structure
and stakeholders engaged in any such entity and on related asset transfer
arrangements will be made with the explicit agreement of the Moray Growth Deal
and Scottish Government and UK Government stakeholders.
Page 97

Page 98

Page 18 of 208 
2. The Strategic Case
Organisational overview
The vision for the Moray Growth Deal is built on 4 pillars; Connections; Business
Support, Skills, and Employability; Moray the Place/Brand; and Moray’s Priority
Business Sectors.  The MICM project falls under the Priority Business Sectors
category.
MICM is being developed by Highlands and Islands Enterprise (HIE). The Senior
Responsible Owner (SRO) is HIE’s Area Manager for Moray who chairs a Project
Board with representatives from HIE, UHI Moray, Moray Council, NMIS, SMAS,
Scottish Government’s Advanced Manufacturing Team and private sector
manufacturers in Moray.
The strategic context
Fit with the UK Government’s Industrial Strategy
The key UK Government policy of relevance to manufacturing remains ‘Build Back
Better: our Plan for Growth’15 produced in March 2021 which notes that “the UK has
a lower proportion of innovating firms overall than other advanced economies and
weaker business investment”. The analysis identifies perceived market failures in UK
manufacturing including:
• lack of access to capital in comparison to other markets;
• regional inequalities within the UK in terms of labour market skills and access to
capital;
• the slow adoption of digital technologies.
Building innovation capacity is seen as essential to the growth of the UK economy. In
the 2021 ‘UK Innovation Strategy: Leading the future by creating it’16, the UK
Government states that “innovation is crucial to the UK building back better. It is at
the heart of ‘Build Back Better: our plan for growth’ and so much else we want to
achieve, from fighting coronavirus (COVID-19) to achieving net zero and building
Global Britain. Boosting innovation in the private sector is an essential part of the
UK’s future prosperity and key to achieving UK objectives to be a force for good on
global challenges around climate, biodiversity, prosperity, and security. We are
calling on businesses to invest in innovation, getting British firms to the front of the
pack.”
The UK Government identifies four Strategic Pillars and several key actions that are
required if the UK is to be a global hub of innovation by 2025.  MICM is designed to
provide a place-based response to these innovation objectives and Table 2.1 shows
how the project will address the four Strategic Pillars. 
15 https://www.gov.uk/government/publications/build-back-better-our-plan-for-growth
16 https://assets.publishing.service.gov.uk/government/uploads/system/uploads/attachment_data/file/1009577/uk-innovation-
strategy.pdf
Page 98

Page 99

Page 19 of 208 
Table 2.1: MICM’s fit with UK Government’s Industrial Strategy
Strategic Pillar Manufacturing Innovation Centre for Moray (MICM) fit
People – We will make the UK the
most exciting place for innovation
talent.
MICM will drive awareness of the imperative to innovate and
will be at the forefront of providing practical support to
change mindsets and encourage businesses to invest in
innovation structures, processes and talent.
Institutions & Places – We will
ensure our research, development
and innovation institutions serve the
needs of businesses and places
across the UK 
MICM will support a much-needed cultural shift through
innovation and modernisation across technologies and
sectors. MICM will also provide a focal point for the North of
Scotland when it comes to upgrading manufacturing
infrastructure and the building of the space cluster.
Unleashing Business – We will fuel
businesses who want to innovate 
MICM will support manufacturing businesses to start and
grow in key priority sectors and will provide the technology
management skills to support sustainable development.
Moray has world leading brand names, with its supportive
SME environment. To maintain its world leading market
position the centre will build on these areas of competitive
advantage.
Missions and Technologies – We
will stimulate innovation to tackle
major challenges faced by the UK
and the world and drive capability in
key technologies
MICM will increase skills, share knowledge and best practice,
and support local businesses to stimulate innovation and
adopt new ways of working. 
Fit with Scotland’s Economic Strategy
In February 2016, the Scottish Government produced ‘A Manufacturing Future for
Scotland’17. Innovation and productivity were central themes in the action plan which
noted that “boosting productivity will be key to driving long term growth in the
manufacturing sector. To improve performance, industry must be ready to embrace
and implement technological innovations, new methods and processes and resource
efficient business models into the manufacturing base. This investment will also help
to secure a balanced and resilient economy.” Many of the proposed actions were
intended to address collaboration around, and investment in, innovation. Certain key
themes were identifiable, with actions around innovation including:
• the relationship between digital innovation and manufacturing process;
• the move towards a circular economy, minimising waste in manufacturing
process and product lifecycle design;
• the importance of collaboration spanning business, academia, and the public
sector to deliver the action plan.
Further progress was made with the publication of the Scottish Government’s
manufacturing recovery plan ‘Making Scotland's Future - a Recovery Plan for
Manufacturing’18 in June 2021. This included several actions of relevance, including
a commitment to “develop a manufacturing ‘network of networks’ to pool and
coordinate the resources of the variety of public and private networks already in
operation.”  Further actions included accessing of City and Growth Deal investment 
17 https://www.gov.scot/publications/a-manufacturing-future-for-scotland-action-plan/
18 https://www.gov.scot/publications/making-scotlands-future-recovery-plan-manufacturing-final-june-2021/
Page 99

Page 100

Page 20 of 208 
and ensuring alignment of funds, e.g. the Digital Development Loan, to pilot and
implement capital modernisation such as automation and robotics.
The Recovery Plan also refers to the National Manufacturing Institute Scotland
(NMIS), established in 2016, a Renfrewshire based collaboration of industry,
academia, and the public sector. The NMIS has a remit which includes:
• increase productivity by reducing barriers to innovation;
• growing the economy by galvanising investment and increasing manufacturing
competitiveness;
• strengthen supply chain links;
• build collaborations and enhancing capability to influence adaptation and exploit
manufacturing opportunities to boost Scotland’s transition to a net-zero emissions
economy by 2045;
• attract talent and equip current and future workforces with the skills the
manufacturing and engineering community need.
The Scottish Government published its 10-year ‘National Strategy for Economic
Transformation’ (NSET)19 in March 2022.  The overriding vision for the strategy is to
deliver a ‘wellbeing economy’ for Scotland, which the Scottish Government defines
as “an economy where good, secure and well-paid jobs and growing businesses
have delivered a significantly reduction in poverty.” This vision is to be achieved
through five programmes and related actions (Table 2.2).
Table 2.2 Scotland’s National Strategy for Economic Transformation
Entrepreneurial
people & culture
Establish Scotland as a world-class entrepreneurial nation founded on a
culture that encourages, promotes, and celebrates entrepreneurial activity
in every sector of the economy
New market
opportunities
Strengthen Scotland's position in new markets and industries, generating
new, well-paid jobs from a just transition to net zero
Productive
businesses & regions
Make Scotland's businesses, industries, regions, communities, and public
services more productive and innovative
Skilled workforce Ensure that people have the skills they need at every stage of life to have
rewarding careers and meet the demands of an ever-changing economy
and society, and that employers invest in the skilled employees they need
to grow their businesses
Fairer more equal
society
Reorient the economy towards wellbeing and fair work, to deliver higher
rates of employment and wage growth, to significantly reduce structural
poverty, particularly child poverty, and improve health, cultural and social
outcomes for disadvantaged families and communities
‘Scotland’s National Innovation Strategy’ was published in June 202320. It updates
the 2016 manufacturing action plan and builds on NSET. The five-year strategy has
five goals: 
19 https://www.gov.scot/publications/scotlands-national-strategy-economic-transformation/
20 https://www.gov.scot/publications/scotlands-national-innovation-strategy/ 
Page 100

Page 101

Page 21 of 208 
• to establish Scotland as a world-class entrepreneurial nation founded on a culture
that encourages, promotes, and celebrates entrepreneurial activity in every
sector;
• strengthen Scotland's position in new markets and industries, generating new,
well-paid jobs from a just transition to net zero;
• make Scotland's businesses, industries, regions, communities, and public
services more productive and innovative;
• ensure that people have the skills they need at every stage of life to have
rewarding careers and meet the demands of an ever-changing economy and
society;
• reorient the economy towards wellbeing and fair work, deliver higher rates of
employment and wage growth, reduce structural poverty and improve health,
cultural and social outcomes for disadvantaged families/communities.
Key areas for action include the building of clusters, focused on those in which
Scotland is considered to have major advantages, including energy transition, health
and life sciences, data, and digital technologies and ‘advanced manufacturing’
employing collaborative infrastructures such as NMIS, the Medicines Manufacturing
Innovation Centre and the National Robotarium. The university sector is identified as
having a major role in terms of commercialisation, including a new Investment Fund.
MICM offers a direct fit with several of the key strands in the National Strategy for
Economic Transformation and the National Innovation Strategy. The MICM proposal
makes a clear, and significant contribution to the ‘productive businesses and region’
strand with its focus on innovation and connecting businesses to manufacturing
innovation infrastructure, regionally and Scotland-wide.
The establishment of MICM will also enhance the capacity of local businesses to
compete in new and emerging markets, generating good quality employment
prospects and career development opportunities for the existing workforce as well as
new entrants. A more skilled workforce will be one of the outcomes through
connections with UHI Moray (including MAATIC) and others.
Fit with HIE’s Economic Strategy 
HIE is the economic and community development agency for the north and west of
Scotland. Its mission is to build a prosperous, inclusive, and sustainable economy
across the Highlands and Islands, attracting more people to live, work, invest and
visit. 
HIE’s 2023-28 Strategy21 is under development and will have four pillars: People,
Prosperity, Planet and Place.  The Strategy highlights the main drivers of innovation
change across the region:
• Data innovation and artificial intelligence;
• Automation and robotics; 
21 https://www.hie.co.uk/media/5006/strategyplusplanplus2019-2022-1.pdf
Page 101

Page 102

Page 22 of 208 
• Digital transformation;
• Cyber resilience;
• Circular economy.
The strategy is strongly aligned with the cluster groups identified in the Scottish
Government’s innovation strategy with a particular focus on the energy sector,
particularly in renewables, decarbonisation and the net zero agenda. The region
offers advantages in terms of both existing infrastructure and skills and Moray, with
its proximity and transport links, is well placed to benefit.
The strategy also contains a strong commitment to net zero and fair and inclusive
growth but the section on regional transformational opportunities has the most direct
relevance to manufacturing innovation, highlighting the progression of HIE’s cluster
approach and intended actions across nine identified industrial sectors.
Supply chain development is a clear focus too.  In terms of green hydrogen, for
example, HIE makes a commitment to “stimulate innovation and supply chain
development in partnership with SE and SOSE through establishment of an
innovation network and an industry cluster, and work with organisations such as
NMIS to focus on key manufacturing opportunities.”
As noted above, food and drink is also a highly significant feature of the Moray
economy.  There is a clear recognition in HIE’s strategy for the need to invest in
innovation with a commitment to “increase innovation and sustainable growth in
primary production through the local application of the national food and drink
strategy, through targeted interventions and programmes, and by enabling
collaborations across the sectors and with academia” but also related activities
around the transition to net zero in agriculture and whisky and investment in “digital
technologies, automation and skills”.
The North Highlands and Moray are at the centre of the space revolution, as home to
Sutherland Spaceport and Orbex.  HIE and partners have established the North
Coast Space Cluster (NCSC)22 to capitalise on these and other regional
opportunities and generate new jobs and careers based on the skills and resources
that the region is well placed to deliver. Sutherland Spaceport was the first spaceport
in the UK to gain planning consent and is currently under construction. It will have
capacity for up to 12 orbital launches per year. In 2019, Orbex opened their
development and manufacturing facility on the Enterprise Park in Forres, designing
and building the Orbex Prime launch vehicle  that will launch from Sutherland
Spaceport. Orbex will be at the centre of a new cluster of local businesses providing
services and products to the growing space sector and using data for commercial
purposes and academic research. MICM will provide a strong resource with which to
help build this cluster.
Fit with Planning Policy
As with other Moray Growth Deal projects, MICM provides an opportunity to show
how Growth Deal projects can be integrated with, and contribute to, local planning 
22 https://www.hie.co.uk/latest-news/2022/february/17/space-sector-set-to-create-new-jobs-in-highland-and-moray
Page 102

Page 103

Page 23 of 208 
policy as it seeks to meet new imperatives and add additionality in the outcomes that
are secured from investment in the local economy.  Key issues here are alignment
with the current National Planning Framework (NP4)23 and Scottish Planning Policy
(SPP), particularly in the light of the Planning (S) Act 2019.
Building on the Planning Act (S) Act 2019 NPF4 indicates that planning should be
underpinned by the six underlying principles24 of just transition, conserving and
recycling assets, local living, compact urban growth, rebalanced development, and
rural revitalisation.
Scottish national spatial planning policy applies these six principles in supporting the
planning and delivery of sustainable places (seeking to reduce emissions, restore
and better connect biodiversity); liveable places (enabling people to live better,
healthier lives); and productive places (underpinned by a greener, fairer, and more
inclusive wellbeing economy).
In relation to the planning and delivery of productive places the NP4 guidance
supports MICM particularly as it relates to conserving and recycling assets through
the repurposing of Unit 9 as the MICM Hub, as well as rebalanced development and
rural revitalisation. MICM’s net zero demonstrator role also fits well with NPF4
objectives.
All the MGD projects are embedded in the indicative Regional Spatial Strategy25
(iRSS) as submitted to the Scottish Government in September 2020.  Moray
Council’s Head of Economic Growth and Development is on the MICM Project Board
and is actively engaged with HIE staff on proposals at the well-established
Enterprise Park Forres where MICM will be located.
Appropriate attention is also being given to supporting the Town Centre First
principle with an example of this being the coordination between the MICM, MAATIC
and the Enterprise Hub projects to ensure appropriate alignment: MICM is
deliberately based at Enterprise Park Forres to be at the heart of the emerging space
cluster, whereas MAATIC and the Business Enterprise Hub are focused on Elgin to
ensure that student activity in the city is maximised.
Fit with the economic needs of the local area.
The 10 year “Moray Economic Strategy, Towards Future Prosperity and Economic
Growth’26 was produced by the Moray Economic Partnership in 2022. The Strategy
highlights some key facts on the Moray economy. In 2022 19% of jobs in the Moray
economy were in the manufacturing sector compared to 8% for Scotland. The area
has the greatest number of manufacturing jobs per head in Scotland and some 10%
of all the jobs in the area are in the food and drinks sector. The average annual 
23 https://www.gov.scot/publications/national-planning-framework-4/
24 Just Transition (empower people to shape their places and ensure the transition to net zero is fair and inclusive.); Conserving and
recycling assets. (making productive use of existing buildings, places, infrastructure and services, locking in carbon, minimising waste, and
building a circular economy): Local living (supporting local liveability and improve community health and wellbeing by ensuring people can
easily access services, greenspace, learning, work and leisure locally); Compact urban growth (limiting urban expansion so we can
optimise the use of land to provide services and resources, including carbon storage, flood risk management, blue and green infrastructure
and biodiversity; Rebalanced development (targeting development to create opportunities for communities and investment in areas of
past decline, and manage development sustainably in areas of high demand) and Rural revitalisation (encouraging sustainable
development in rural areas, recognising the need to grow and support urban and rural communities together)
25 https://www.legislation.gov.uk/asp/2019/13/section/5/enacted
26 http://www.moray.gov.uk/downloads/file147200.pdf
Page 103

Page 104

Page 24 of 208 
gross full time mean wage is £31,987 compared to £34,936 for Scotland - a
difference of 8%. The gap widens to 13% when all (full time and part time) jobs are
included. The average annual wage in Moray is £24,879 compared to £28,660 for
Scotland27.
The Strategy highlights many challenges for Moray businesses including the
increased costs of doing business. There is also focus on the Net Zero agenda.  The
Strategy recognises net zero innovation in some of the larger food and drink
companies but recognises that for most businesses there is a long way to go.
Moray’s previous Economic Strategy (2019 to 2029) noted that many businesses in
Moray lack the resources, and particularly the knowledge, to execute R&D capital
projects and secure the productivity benefits. In 2018 Moray ranked 2nd lowest of all
local authority areas in Scotland in relation to spending on business enterprise
research and development (BERD) as a proportion of GDP (0.12% of GDP versus a
Scotland average of 0.83%)28. The 2019 Strategy argued that from a business
perspective, key drivers for growth in the area will be a combination of new start-ups
in growth technologies and a greater density of SMEs with the capability to grow
further, but that “the future economic success of Moray will heavily depend upon
more traditional industries investing, innovating, and adapting, because they are the
area’s major employers. In these industries, which are mostly linked to
manufacturing, the ability to adapt operations and the workforce to sustain
competitiveness and improve productivity will be critical to the future economy.
The current Moray Economic Strategy refers to the eight Moray Growth Deal
Projects and outlines what it expects of the Growth Deal investment – that there will
be new high-quality jobs in existing sectors and diversification of Moray’s economy
into new high value areas. It is anticipated that collectively the eight projects will
create around 3,500 direct and indirect jobs in Moray.
The Strategy concludes with seven priorities for action in support of the Growth Deal
projects. These include the alignment of skills systems with emerging needs,
particularly around green jobs. They also include action to increase awareness
amongst the wider business community of Moray and use the Growth Deal
Investments to drive readiness within the existing supply chain, which is where
MICM is expected to play an important role.
The delivery of MICM will help to create higher paid job opportunities in the types of
technology-driven roles that young people are looking for which will help encourage
more of them to stay in the area.  The switch from manual, relatively low skilled
process jobs to more technical control roles, able to be undertaken by skilled people
of both genders, will also increase opportunities for women locally and helping to
close the gender pay gap. Support for the present proposal fits well with the
ambitions expressed in the Moray Economic Strategy, particularly in enhancing the
productivity of the manufacturing sector and growing wages. As the Strategy makes
clear “innovation through automation and new work processes (including artificial
intelligence) will also be required. These will, in some sectors, help to offset limited 
27 Moray’s Economic Strategy (2022). http://www.moray.gov.uk/downloads/file147200.pdf
28 Scottish Government National Statistics: Business Enterprise Research and Development Scotland, 2018
Page 104

Page 105

Page 25 of 208 
availability of workers. This will include traditionally important sectors such as food
and drink manufacturing (and its supply chain) and timber processing.” 
Business Strategy and Aims
A core objective will be to place Moray business at the forefront in the adoption of
new technologies in order to innovate and be productive. At the present time, much
remains to be done to realise this goal.
The Moray Economic Strategy seeks to sustain a growth economy that can drive
higher wages and influence young people to stay and have a life and career in the
area.  Failure to build on Moray’s local strength in manufacturing and attract new
talent will escalate the departure of skilled young people and the potential demise of
a manufacturing sector that will struggle to survive against external competition.
With some of the lowest business R&D figures in Scotland it is essential that the
area’s manufacturing base drives up its research and development to support its
long term sustainable growth.  What is required is a grass roots cultural shift in how
Moray businesses gain insight into the latest process and production efficiencies that
are available, and how they can use them to undertake product and process
innovation.
MICM’s aim is therefore appropriately ambitious as follows:  Working with other
elements of the Growth Deal, to develop an innovation ecosystem which will
help manufacturing businesses in Moray to become world-class.
Investment objectives 
The MICM project has four primary objectives:
• To increase BERD (Business Enterprise, Research and Development) in
Moray’s indigenous manufacturing companies.
• To increase growth, productivity, and efficiency in Moray’s indigenous
manufacturing companies.
• To increase the number of manufacturing start-ups in Moray.
• To support the attraction of manufacturing inward investment to Moray.
In its pursuit of these primary objectives, MICM can also be expected to contribute,
indirectly, to the creation of higher paid jobs, an improvement of the skills offer,
retention and attraction of young people, and reducing occupational segregation and
the gender imbalance.
Existing arrangements
Scotland’s National Innovation Strategy (2023)29 highlights the considerable amount
of innovation support that is provided to businesses across Scotland at the present 
29 https://www.gov.scot/publications/scotlands-national-innovation-strategy/
Page 105

Page 106

Page 26 of 208 
time. As Figure 2.1 illustrates just how crowded and complex the current innovation
ecosystem is, with support from Scottish Government for innovation provided
through a variety of institutions and policy interventions.
Page 106

Page 107

Page 27 of 208 
Figure 2.1 Scotland’s Existing Innovation Ecosystem Landscape   
Table 2.3 sets out the existing innovation delivery landscape, drawing on the supply-
side assessment undertaken as part of the FBC process.  Key elements of
manufacturing innovation support are highlighted in column “c,” while column “d”
suggests the potential importance of a link to MICM as well as the nature of that
potential involvement.  Beyond those providers identified in Table 2.3, business
consultees also highlighted the value of networks such as the Moray Chamber of
Commerce and Federation of Small Businesses as well as the value of trade
associations and trade shows as sources of occasional learning.
Table 2.3: MICM and the existing innovation delivery landscape
a. Provider b. Who are they c. What do they offer businesses in manufacturing
innovation
d. Link to
MICM?
Scotland-wide  
Scottish
Manufacturing
Advisory Service
(SMAS)
Part of Scottish
Enterprise
Scotland wide and all sectors. Team of 20+
practitioners guide businesses immediate tactical
challenges as well as longer term strategic change.
Seek to offer improvements in productivity, culture,
and behaviours from the shopfloor to boardroom.
Offers tailored support programme. Explore cost saving
technology, supply chain processes and digital
technologies.
High priority.
Potential
virtual and
on-site
presence.
Page 107

Page 108

Page 28 of 208 
a. Provider b. Who are they c. What do they offer businesses in manufacturing
innovation
d. Link to
MICM?
UK Knowledge
Transfer
Partnerships
(KTP), Innovate
UK, Knowledge
Transfer
Network (KTN)
and UK
Research &
Innovation
(UKRI)
UKTP and KTN are
national
Programmes, co-
financed by Scottish
Government
Innovate UK and
UKRI are non-
departmental public
bodies of the UK
Government
Knowledge Transfer Partnerships is a UK-wide
programme that helps businesses for to improve their
competitiveness and productivity through the better
use of knowledge, technology and skills that reside
within the UK Knowledge Base30. Innovate UK31
provides funding to businesses to help with projects to
stimulate innovation. The Knowledge Transfer
Network32 has been established by Innovate UK to help
people and businesses with innovation by helping them
to connect with other businesses. UKRI33provides
funding to help businesses innovate.
High priority.
Potential
virtual and
on-site
presence
National
Manufacturing
Institute
Scotland (NMIS) 
University of
Strathclyde,  SE,
HIE, High-Value
Manufacturing
Catapult, others
Industry-led manufacturing research and development
facility focused on skills, productivity, and innovation in
Scottish advanced manufacturing. Support across all
services and sectors. Filling the space between
academic research and industry, access to R&D
facilities engineers, machining facilities, researchers,
and business advisers. 
The NMIS subsidiary the Advanced Manufacturing
Research Centre (AFRC) is part of the UK wide High
Value Manufacturing Catapult.  
High priority.
Potential
virtual and
on-site
presence or
visiting
presence
Interface Funded by the
Scottish Funding
Council, Interface
connects business
to Scotland's
universities,
research institutes
and colleges
Interface - the knowledge connection for business -
works with businesses of all sizes/sectors, to match
them to Scotland’s academic expertise to tackle
industry sector challenges and individual business
challenges to help them grow. Connections into all
Scottish universities, research institutes and colleges.
Will facilitate connections between academia and
business and help identify funding for joint projects. 
Medium
priority.
Virtual and
occasional
on-site
presence.
Skills
Development
Scotland (SDS)
Scotland’s national
skills agency.
Executive body of
Scot Gov (under
review)
Support to partners and employers to develop Modern
Apprenticeships Framework. Various online tools to
assist businesses recognise and develop skills needs
and strategies. All sectors. 
High priority.
Potential
virtual and
occasional
presence.
Specific Scottish
Innovation
Centres (e.g.
CENSIS, BE-ST
and Data Lab)
Scottish Funding
Council committed
£120 million for the
Innovation Centre
programme over
five years (2013-18)
to support the
university
infrastructure. Each
Innovation Centre is
expected to lever
further investment
from industry and
other sources of
public funding. 
The Centres aim to enhance innovation and
entrepreneurship across Scotland’s key economic
sectors, create jobs and grow the economy. Innovation
Centres (ICs) have backing from industry and draw on
all of Scotland’s research expertise in the relevant
sector to work on problems and opportunities
identified by industry. They add value through
secondments, industrial studentships, spaces for
collaborative work and shared access to equipment. 
Not all will be relevant to MICM – those that are likely
to be most closely involved are:
• CENSIS - sensing, imaging and Internet of Things
(IoT) technologies
• BE-ST - built environment transition to zero carbon
emissions
• Data Lab – data science and AI
High priority.
Potential
virtual and
occasional
presence 
30 http://ktp.innovateuk.org
31 https://www.gov.uk/apply-funding-innovation
32 https://www.gov.uk/government/news/connecting-innovators-the-knowledge-transfer-network
33 https://www.ukri.org
Page 108

Page 109

Page 29 of 208 
a. Provider b. Who are they c. What do they offer businesses in manufacturing
innovation
d. Link to
MICM?
Regional Focus
Highlands and
Islands
Enterprise 
Agency for regional
economic and
community
development
Provide targeted support to businesses with growth
potential by strategical development, with partners, of
the business and innovation infrastructure. Offer
specialist digital technology support and advice.
Assistance with skills through graduate placement
support. Strategic partnerships e.g., with MIT and
Glasgow School of Art, offer a model and means of
drawing in larger scale, established businesses. 
High priority.
On site
presence.
University of
the Highlands
and Islands
Providers of Higher
Education and
Research
Offers apprenticeships, graduate-business links, CPD
and customised research for businesses and graduate
recruitment. Innovation supported through the
Knowledge Exchange Team offering consultancy
services, specialist university facilities, equipment, and
testing services to companies, placements, and
research commercialisation advice.
MICM would also seek to build a close working
relationship with AMC at UHI West Highland
High priority.
Regular
virtual or
visiting
presence.
UHI Moray Providers of Further
and Higher
Education
Offers apprenticeships, employability programmes,
CPD, professional development awards and delivery of
innovation voucher projects. Focus on oil and gas,
digital healthcare, and life sciences.  Delivery of MGD
MAATIC and BE Hub projects.
High priority.
Regular
virtual or
visiting
presence.
Conclusions on current supply of innovation services
There are a significant number of innovation support services currently available to
businesses in the Highlands and Islands, but the evidence clearly shows that despite
the support on offer, there are knowledge and engagement gaps which need to be
overcome to improve take-up.  The missing ingredient is intensive, tailored, local
engagement of the right sort to encourage businesses to make the leap and to
maximise engagement from businesses who are busy, risk averse and do not always
see the benefit to their bottom line.
Business needs – current and future 
Innovation needs of manufacturing businesses in Moray.
To be successful, MICM must meet a clear need from Moray business. This need
was assessed as part of work undertaken at both the OBC and FBC stages through
a series of workshops and structured interviews with businesses in Moray.  All the
key business support stakeholders were also involved, including the Business
Gateway, Chamber of Commerce, Moray Growth Deal Business Assembly, HIE, UHI
Moray, Skills Development Scotland and Moray Council.
Online surveys were also conducted with Moray business in both 2020 and 2023.  In
the 2020 survey some thirty Moray businesses responded to the on-line survey and
in addition there was a wide range of one-to-one consultations with businesses and
other intermediaries. Workshops were also undertaken facilitated by Moray Chamber
of Commerce and Moray Growth Deal Business Assembly. In the 2023 survey a
more extended and detailed online questionnaire was sent to Moray businesses.
Some 17 companies responded to this in-depth survey.
Page 109

Page 110

Page 30 of 208 
The interviews and responses to the two waves of the on-line survey revealed that
Moray business considered that the most important drivers to them in undertaking
innovation were to address environmental impact issues; reduce costs and improve
the quality of their products (Figure 2.2).
Figure 2.2. Key drivers for undertaking innovation by Moray businesses (scored 1-5,
where 1 = least important and 5 of greatest importance) 
However, Moray manufacturing businesses consider that several factors are
currently constraining their ability to innovate. As Figure 2.3 on the following page
shows, besides concerns around Government regulation, they believe that the
economic risks associated with undertaking the required investment are too great.
They also found difficulty in obtaining skilled personnel.
There was a considerable degree of consistency in what were felt to be common
barriers to innovation across the SMEs interviewed as part of the demand
assessment work and this understanding was shared by the intermediaries
consulted. Interviews confirmed:
• the absence of internal resource to pursue research and development;
• the inability to attract people with the skills and experience required to enable
innovation;
• the distances to centres of learning and innovation for businesses in Moray with
much provision being in Scotland’s central belt e.g., staff in the drinks industry
might naturally be drawn to provision at Heriot-Watt University, but travel
requires considerable ‘downtime’ for staff;
• lack of business or sectoral ‘scale’ with insufficient levels of competition to
foster innovation and learning.
Page 110

Page 111

Page 31 of 208 
Figure 2.3. Key Factors Constraining Investment in New Products and Processes in
Moray Business (scored 1-5, where 1 = lowest constraint and 5 biggest constraint) 
Gaps in innovation take-up and support that need to be targeted
The business surveys undertaken as part of the demand assessment identified clear
perceptions of the key gaps in both what they themselves were doing to be proactive
enough in undertaking innovation (‘business innovation activity’) and the extent to
which the existing delivery landscape outlined above was meeting business needs
(the ‘supply of innovation support’).
The consultations also established how businesses and business support
intermediaries considered a manufacturing innovation centre might meet unfilled
needs and highlighted the services it might provide.
Moray Business and their position on the Innovation Ladder
The extent to which companies are “innovation active” varies considerably by the
size of business.  Moray is fortunate in having some very large, well established
multinational businesses who have developed their own extensive and relatively
well-resourced approaches to their innovation needs. Alongside these businesses
are a relatively small number of medium sized companies and for these there is
considerable variation in their approach to innovation.  In general, most would wish
to be undertaking more innovation and would value more guidance on how and
where they should be investing. There are then a fairly large number of smaller
manufacturing businesses who are under-investing in innovation and consider that
they could benefit from several different services that would help them do more.
To obtain a better understanding of the current state of Moray business innovation it
is first helpful to gauge where Moray businesses are on the Innovation Ladder that
has been developed by HIE (Figure 2.4). 
Page 111

Page 112

Page 32 of 208 
Figure 2.4. The Innovation Ladder 
Source: Highlands and Islands Enterprise, 2023
The Moray companies that participated in the survey undertaken in May and June
2023 were asked to position themselves on the ladder. Figure 2.5 shows the results.
The evidence pointed to the businesses being nearer the bottom of the ladder than
the top. Most of the businesses responded stated that either (1) they had an
intention to innovate and have a top level desire to innovate, recognising its
importance, but that there was no-one in a senior position responsible for the
innovation process or (2) that they are active innovators, but still developing their
approach.
Figure 2.5. Moray Business and their position on the Innovation Ladder 
The survey of Moray businesses probed how much they had adopted digital
technology across all major areas of business operation. They indicated whether
they had successfully introduced digital technology, were introducing digital
technology, considering adopting business technology, or not using digital
technology at all. Figure 2.6 shows the results from the sample.  These findings are
Page 112

Page 113

Page 33 of 208 
consistent with a recent national survey conducted by MADE UK (Figure 2.7). The
responses point to relatively low levels of digital technology, but at the Moray level
they were, in general, no worse than UK counterparts, reinforcing innovation as a
national imperative.
Figure 2.6 Moray Business adoption of digital technology 
Figure 2.7. Spread of digital technology across different areas of business from the
MADE UK/Infor Innovation Survey (2022) 
Conclusions on the current position
The evidence from the survey of Moray businesses and consultation with the
business community and business survey providers indicates that the key drivers for
innovation are seen by Moray business to be the need to respond to the
environmental impacts of their products and processes, to secure reductions in costs
and, crucially, to be able to improve the quality of their product and to differentiate it
relative to their competitors.
Page 113

Page 114

Page 34 of 208 
Whilst Moray businesses recognise the need to innovate, they find it difficult to do
enough and are highly risk averse. The lack of key personnel and time available to
senior management are both identified as major constraints, as is an acute lack of
knowledge as to what they should be doing and relevant best practice. 
As a result, Moray businesses are mainly on the lower rungs of the innovation
ladder, a matter of concern that is entirely consistent with the low levels of business
R&D expenditure evidenced by national statistics. Moray businesses generally have
the INTENT to do more innovation, and while some are clearly innovation ACTIVE,
there is still insufficient attention to EMBEDDING innovation activity in the culture of
the business.  Insufficient attention to innovation is reflected in inadequate levels of
adoption of digital technology across the key areas of their business.
Perceptions by Moray business on awareness of existing innovation service
provision
The demand assessment surveys of Moray business conducted as part of the OBC
and FBC development also provide valuable evidence on business awareness of the
innovation support available.  This presented a rather mixed picture across sectors
and size of businesses. Support from HIE is widely acknowledged, increasingly by
those businesses who had experience of being “account managed” by HIE.  As a
very approximate estimate around 15-20% of the existing stock of Moray
manufacturing companies might be considered to have received some degree of
support.
Figure 2.8 on the following page shows that around 14% of businesses perceived
that existing innovation support was meeting all or most of their business needs.
However, just over 30% considered that provision was meeting only some of their
business needs and around 38% considered that existing support was meeting few
or none of their business needs.
Qualitative feedback from the FBC survey a number of areas where respondents felt
the existing supply of innovation support could be improved.  These included:
• More clarity, signposting, and transparency on what specific support is
available;
• More support on methods of funding business development;
• More technical and qualified support required;
• Although there is good support on highlighting what business should do, it was
felt there was less practical support on how to do it;
• Programmes often come along with relatively short windows in which to apply
for support/funding, and the pressure of day-to-day work often means there is
not enough time to apply.  Practical support in helping to access short duration
funds would help;
• The time involved in putting applications can be difficult to justify so some help
is also needed with this aspect;
• More support to enable market diversification;
Page 114

Page 115

Page 35 of 208 
• Moray business also need a growth in support services for new technologies
that will be used in 3 to 5 years.
Page 115

Page 116

Page 36 of 208 
Figure 2.8. Perception of Moray business on the extent to which existing innovation
service provision is meeting their needs 
The businesses were also asked what role they felt that an innovation centre could
play in meeting their needs. Several possible aspects were probed and the findings
from the 2020 and 2023 business surveys are summarised in Table 2.4. The roles
that were given the most emphasis in both surveys were enabling business
collaboration to occur, helping to translate new ideas into commercial application,
building business networks and contributing to the manufacturing knowledge base.
Providing businesses with the skills to scale up and promoting the manufacturing
sector were also seen as relatively important.
Table 2.4 Importance of roles that an Innovation Centre could facilitate (scored 1-5,
with 1 being least important and 5 being most important)
Page 116

Page 117

Page 37 of 208 
The companies were asked which services provided by an innovation centre they
would make most use of.  Figure 2.9 shows that service support to secure net zero
targets and reducing costs were highly rated. Support to increase productivity and
securing process improvements, as well as gaining access to 3D printing and digital
services were also highly rated.
Figure 2.9. Services that businesses would be most likely to use at MICM 
Figure 2.10 shows the innovation services that Moray businesses considered that
they would seek to access from MICM.  Businesses responding pointed to peer-to-
peer networking and learning as being of greatest importance, including finding out
how other Moray manufactures were innovating, as well as workshops on business
development, enterprise and leadership.
Figure 2.10. Innovation activities that business would access at MICM 
Figure 2.11 shows the innovation services that Moray business would seek to
access at MICM by key innovation service provider. There was a strong focus on
access Services provided by HIE, followed by SMAS, SDS, NMIS, Innovate UK and
Interface.
Page 117

Page 118

Page 38 of 208 
Figure 2.11. Innovation services that business would access at MICM 
Conclusions on innovation support and the role of MICM
For those companies that are failing to innovate enough it is important that they have
access to advice.  The Tell element in this advice is to make them aware and
promote not only that ‘something better’ is out there through the diagnostic process,
but to lead into the Show element that will effectively demonstrate how ‘something
better’ can be applied in relevant, cost-effective ways to a specific business.  The Do
element will be a supportive use of technical support to enable good practice and
processes to be project managed into businesses.  This is a direct approach to
tackling the key economic barrier of information deficiency.  It is here where it is
considered that a manufacturing innovation centre could build on the successful
academy approach used by SMAS to build networks of individuals employed in
businesses with the technical and practical skills to make the most of industry 4.0 in
their own workplaces.  
The conclusion of the OBC and FBC process is that this is the optimal way to help
SMEs to successfully execute change.  For hundreds of SMEs, plans, roadmaps,
and good intentions will not lead to an actual investment because they lack technical
capacity and middle management to execute plans.  MICM can address these issues
directly.
How a Manufacturing Innovation Centre for Moray could fill the gap
Moray businesses surveyed as part of the MICM Business Plan see substantial
benefits to the local economy from a dedicated manufacturing innovation centre as
shown in Table 2.5.  All the benefit categories shown scored strongly, but
employment growth, productivity growth, increasing the skill base and promoting the
Moray economy internationally and attracting inward investment tended to be
identified as very important benefits. Figure 2.12 shows the results from both
surveys. In the more recent survey increasing the growth of Moray manufacturing
business sales has assumed prominence, as might be expected in the immediate
post-Covid period. 
Page 118

Page 119

Page 39 of 208 
Table 2.5: How important do you consider the following possible benefits of the
proposed manufacturing innovation centre on the Moray/Highlands and Islands
economy? (Average Scores, where 1 is not important and 5 is very important)
Benefit category Weighted
score
(n=26)
Increasing the growth of employment in the Moray/H&Is manufacturing sector 4.5
Increasing the productivity of Moray/H&Is manufacturing 4.5
Attracting new inward investment into the Moray/H&Is economy 4.5
Increasing the skill base of the Moray/ H&Is manufacturing sector 4.4
Promoting the Moray/ H&Is economy internationally 4.4
Enhancing the growth of sales of Moray/H&Is manufacturing businesses 4.3
Increasing the infrastructure base of the Moray/H&Is manufacturing sector 4.3
Increasing the connectivity of the Moray economy to innovation support services 4.3
Increasing the presence of Moray/H&Is manufacturing businesses in key markets 4.3
Increasing the growth of Moray/ H&Is manufacturing exports 4.1
Attracting international corporates for R&D collaborations 4.0
Increasing the global impact and value from Moray/H&Is manufacturing 4.0 
Figure 2.12. Potential benefits from MICM 
The business survey went on to ask companies how a manufacturing innovation
centre could specifically benefit their business and which elements of potential
support they regarded as more or less important.
Respondents to the survey expressed a strong interest in the innovation centre
enabling collaboration and helping connect with support which could help to translate
new ideas into commercial application, the provision of facilities and services to
assist manufacturing companies and connecting them with key innovation support
services such as SMAS, NMIS, Interface and the services provided by Innovation
Centres.
The overall view was that a manufacturing innovation centre should be seen as an
opportunity for Moray to market itself more and ensure better linkage and
signposting with the outside world.  Whatever new initiatives are undertaken it was
Page 119

Page 120

Page 40 of 208 
considered that they needed to be done well and a new manufacturing innovation
centre should become a centre of excellence in the promotion of best practice and
that it should become a permanent feature of the Moray manufacturing landscape
able to “Show us the future!.” It would promote the area as a centre of excellence in
manufacturing and innovation which would help with the retention of local talent, as
well as the attraction of external business investment. 
In the survey Moray businesses were asked to provide some indication of what they
felt could be the benefits to them of MICM on the growth of sales in their businesses
over the next five years based on their 2022 position. Figure 2.13 shows that over
50% of the businesses considered that the overall impact could be between 11-25%
of their 2022 baseline sales, although a small percentage suggested it could be
higher at between 26-50%. Around 30% considered it would be between 1-10%.
Figure 2.13. Impact of MICM on the growth of sales over the next five years 
Potential scope and service requirements
An initial assessment of a long list of options was undertaken to support the
preparation of the Strategic Outline Case (SOC) for the project in 2019 and these
were refined further during the Outline Business Case (OBC) stage in 2020 (details
of this process are provided in Appendix 1).  These options have been refined further
as part of the development of the Full Business Case (FBC), drawing on a review of
the innovation supply-side and demand assessment work as outlined above.  In
particular, the business case process has explored the need for, and benefits of:
• Enhanced co-ordination of innovation support targeted at manufacturing;
• The need to encourage much stronger interaction between manufacturers and
the knowledge base and the ways in which access can be enhanced;
• The property needs of new manufacturing start-ups, in particular the need for
flexible unit sizes on easy in, easy out terms, and space on flexible terms for
them to grow on once they have “graduated” from incubation space.
The findings from the business case research are that MICM could meet a real need
in enabling Moray business to step-up the scale of their innovation activity with all
the associated benefits that this could bring in enhanced completeness and
economic growth. Key ingredients for success that it should provide:
Page 120

Page 121

Page 41 of 208 
• Carefully targeted, bespoke packages of support, facilitated through regular
presence by key service providers;
• Targeted, themed events, including peer learning, equipment demonstrations,
circular economy, net zero – to inspire/help businesses prioritise what they
need, drawing in existing programmes (e.g. from CeeD) wherever possible;
• Attractive facilities with relevant space, equipment and technical support which
is hard to access. These facilities could encompass:
• Prototyping space and equipment (including 3D printing)
• Instrumentation and testing equipment
• Data analytics support
• Robotics
• Business incubator units for new start-ups and associated commercialisation
support (linked to knowledge base and Business Enterprise Hub);
• Grow on space for scaling businesses.
If MICM is to realise its core ambitions, it should be the primary front door to
manufacturing innovation delivery for SMEs in Moray. It should provide high calibre,
inspirational and accessible leadership (with a credible manufacturing background)
that can spell out clearly to business where they are on the Innovation Ladder, the
potential for them to increase their existing levels of innovation to deliver bottom-line
benefits and how they can be assisted to do this.
Visibility, clarity of purpose and effective partnership working will be key to MICM’s
success.
Benefits criteria
Satisfying the potential scope for this investment will deliver the following high-level
strategic and operational benefits. The primary benefits – linked to the primary aims
and objectives of this project - are shown below.
A distinction is made between the strategic catalytic benefits arising from the
services delivered by MICM, and the operational benefits arising from the
construction and ongoing operation of the facility (Table 2.6). Both have been
modelled as part of the Economic Impact Assessment (EIA) work undertaken to
support the FBC (see Economic Case).
Page 121

Page 122

Page 42 of 208 
Table 2.6: Investment objectives and benefits
Class Of
Objective
Main Benefits Benefits Criteria Stakeholders
Affected
Strategic (wider
social and business
related)
Manufacturing
employment 
Manufacturing GVA 
Income from
employment
Increase business growth 
Increase business
productivity 
Increase BERD 
Increase the number of
new manufacturing start
ups
Local businesses 
Entrepreneurs 
Young people 16-29 
Other Moray residents
Operational
(organisational and
management
related)
Construction
employment 
Operational
employment
FT construction job years 
Permanent FTEs in MICM
operation
Moray residents
Strategic risks
The main business and service risks associated with the potential scope for this
project are shown in Table 2.7, along with the steps already taken to mitigate these:
Table 2.7: MICM Strategic Risks at the FBC stage
Risk categories  Description 
Business risks  Under-estimation of costs (mitigated through business planning process, risk
assessment and Optimism Bias assessment)
Failure to generate sufficient income to cover revenue costs (mitigated
through diversity of income streams and business planning process that has
drawn on both a supply-side and demand-side assessment and Optimism
Bias assessment)
Competing demands for resources (mitigated through good co-ordination
between MICM and other projects to ensure no duplication and maximise
synergies)
Lack of productive engagement with the business community (mitigated
through an OBC business survey, consultation events with the Moray Growth
Deal Business Assembly and Chamber of Commerce and an FBC survey).
Service risks  Inadequate management expertise (mitigated by budgeting for the
recruitment of a high calibre Project Director and Centre Manager to
maximise benefits)
Lack of engagement from service providers (mitigated by strengthening the
MICM Project Board at FBC stage to include representation from NMIS and
SMAS as well as UHI Moray).
Page 122

Page 123

Page 43 of 208 
Risk categories  Description 
External
environmental
risks
Impact of inflation on capital and revenue costs (both on MICM itself and its
impact on business)
These risks are, by definition, outside of our control, but we can mitigate to
some extent through careful budgeting and use of up–to-date inflation
forecasts.
Constraints
The project is subject to the following constraints:
• Compliance with procurement strategies;
• Resources are available to enable the project to be delivered on time and to the
right quality;
• The capital works and contract for services can be procured within the
timescale required to allow the benefits to accrue;
• The successful implementation of the revenue operating model, including
letting incubator and (later) grow-on space and delivering paid-for services.
Dependencies
The project is subject to the following dependencies that will be carefully monitored
and managed throughout the project lifecycle:
• The project is dependent on ongoing political support and the relationship
between partner organisations;
• Alignment with national / regional developments;
• There is sufficient private sector involvement/ interest to make the revenue
model viable;
• Availability of suitable land and premises, identified in the FBC as HIE’s Unit 9
for the MICM Hub and Unit 10 and adjacent land for a new build extension for
MICM Grow-on space;
• Good alignment with the current National Planning Framework (NPF4) and
Scottish Planning Policy (SPP), particularly in the light of the Planning (S) Act
2019;
• Securing building warrants for the capital works;
• Financial approval from the UK Government and Scottish Government for
capital and revenue funding for MICM;
• Financial approval from HIE for capital funding for MICM.
Page 123

Page 124

Page 44 of 208 
3. The Economic Case
Project logic model
The MICM project is expected to lead to material change in the start-up, survival,
growth, and competitiveness of manufacturing businesses in Moray.  The ways in
which it is expected to deliver these benefits are set out in a summary logic model
(Table 3.1).  A more detailed logic model is provided at Appendix 3.
This shows the way in which the different strands of the project are expected to
deliver benefits, moving from the resources used to purchase various activities
(advice and support, incubation, and grow-on space), the business performance
outputs and outcomes these are expected to deliver and the various ways these can
be expected to impact on the Moray economy.
Table 3.1: Logic Model for MICM
Inputs Activities Outputs Outcomes Impacts
Resources
needed to
deliver the
project.
Actions
needed to
deliver the
project.
Measurable direct
results of the activities.
Changes that
occur to the
beneficiaries and
the medium-term
benefits on the
economy. 
The long-term
effect upon the
economy or
society
SG £
UKG £
HIE £
More support
coverage for
indigenous
manufacturing
businesses
• Increasing business
R&D expenditure 
• New start-ups
• Growth and
productivity
improvements in the
indigenous
manufacturing base
• Inward investment by
other manufacturers
Impact on
business
performance:
• Employment
• GVA
• GVA/employee
• BERD
• BERD
• GVA
• Employment
• Productivity
Incubator
space – new
start ups
Grow-on space
Inward
investment
activity
Short-listed options
Following the supply-side and demand assessment work conducted at this FBC
stage (see Strategic Case), the MICM Project Board has reviewed the project’s
investment objectives and agreed how MICM should be positioned to maximise its
added value within a complex delivery landscape.
Proposed service solution
The service solution that emerged from Project Board options workshop in June
2023 is set out in Figure 3.1 on the following page.
Page 124

Page 125

Page 45 of 208 
Figure 3.1: Manufacturing Innovation Centre for Moray (MICM) project 
Sector leadership: inspiring, assessing needs, co-ordinating, persuading, joining up
Awareness: marketing, promoting, demonstrating, organising events
Technical: demonstrating equipment and new technologies with MICM buildings as net zero
demonstrators
Core service offer:
Investment Objectives: • To increase BERD (Business Enterprise, Research and Development) in Moray’s indigenous
manufacturing companies
• To increase growth, productivity, and efficiency in Moray’s indigenous manufacturing companies
• To increase the number of manufacturing start-ups in Moray
• To support the attraction of manufacturing inward investment to Moray.
• To accelerate the transition to net zero in Moray’s indigenous manufacturing companies
Playing an active role in cluster management (advanced manufacturing, multi-sector)
Developing a detailed assessment and baseline of productivity and net zero performance, needs and
opportunities for each manufacturing business
Effectively co-ordinating service delivery (deploying HIE, UHI (MAATIC), NMIS, SMAS, Interface, Innovation
Centres, Business Energy Scotland etc.), guiding/steering businesses to the best solution for them and the
most suitable providers
Supporting product and process innovation projects in businesses
Facilitation of networking, peer-to-peer learning, and collaboration Key tasks:
MICM HUB
(Unit 9, Enterprise Park Forres)
MICM Grow-on space
(Unit 10 and adjacent new build expansion, at
Enterprise Park Forres)
4 industrial units totalling 793 sq. m
Property:
6 x 40-70
sq. m
incubator
units
Demonstrati
on and
technical
space
Service provider
and private
sector desk
space
Horizon Scotland (existing events space to be used by MICM)
Wider space cluster activity 
Net zero
demonstrator
Page 125

Page 126

Page 46 of 208 
In the period since the preparation of the original MICM OBC there has been
substantial change to the MAATIC Growth Deal project and its geographical location
in relation to MICM. It has  therefore been decided that MICM should be located at
the Enterprise Park Forres as a stand-alone facility where it can be amongst other
manufacturing businesses, including those at the heart of the North Coast Space
Cluster, as well as taking advantage of existing conference facilities at Horizon
Scotland.
There will continue to be close collaboration between MICM and MAATIC as well as
with the Business Enterprise Hub (BE Hub) project.  In parallel with MICM’s FBC, the
MAATIC and BE Hub projects have also been developing their own FBCs. As
outlined at the OBC stage, MICM intends to work closely with both projects to
optimise the customer journey for both businesses and individual entrepreneurs. In
relation to MICM/MAATIC engagement, this will mean that where MICM engagement
identifies skills needs, it will facilitate rapid access to relevant advanced
manufacturing skills support through MAATIC in the first instance.  The same will
apply where it identifies management training and broader entrepreneurship skills
development needs, where it will signpost to BE Hub.  MAATIC and BE Hub have
also mapped out the customer journey for referrals into MICM, which will provide
innovation services and facilities to support entrepreneurship activity, both with
MAATIC students (including professional doctorate students) and BE Hub
manufacturing service users who need product and process innovation support. 
Further detail is provided in the Commercial Case.
In parallel with the detailed design process, three Change Requests have been
approved for MICM since the OBC stage.  These approved a change in project
location from land adjacent to RAF Lossiemouth to Enterprise Park Forres (CR1) as
well as approving the principle of using existing premises to facilitate a more rapid
start to the project (CR2).  The most recent Change Request (CR3) was approved by
the MGD Board in May 2023 and validated by the MICM Project Board at an options
workshop in June 2023.  This specified the following FBC options for appraisal.
Option 1: Business as Usual – Do Nothing – No Growth Deal Funding
Option 1 is the Business as Usual option that assumes no Growth Deal funding. 
This is the Reference Case against which the performance of other options can be
judged.  Under this scenario and given the tight fiscal environment and other funding
priorities, MICM would not happen.  Project development costs have been incurred
to bring the MICM project to FBC stage (£134,000).  These sunk costs are included
in Option 1.
In addition to Option 1, two intervention options have been appraised as part of the
Full Business Case.  The options are identical in relation to service offer (and thus
revenue model) but take a different approach to the delivery of the capital project.
Option 2: Phase 1 MICM Hub (in refurbished premises) and Phase 2 grow-on
space (mix of refurbished premises and new build)
Page 126

Page 127

Page 47 of 208 
In this option the MICM Hub (Phase 1) would be provided quickly through a
reconfiguration of the HIE-owned Unit 9 at Enterprise Park Forres.  This light
industrial unit was constructed in 2009, is heated using ground source heat pumps,
and is about to be vacated by a growing electronics manufacturer which is in the
process of expanding elsewhere on the Park.  The design of this building with a
ground floor, mezzanine and sloping roof, has made it difficult to let on a sustainable
basis for manufacturing, but its internal layout lends itself well to the MICM
requirement.
With relatively limited reconfiguration required (the work package is set out in detail
in the Commercial Case), the capital works on the MICM Hub would be complete
during 2024. These works will include solar PV, insulation and LED lighting
improvements.  This will also support MICM in its role as a net zero demonstrator,
with additional sensors and measurement displays helping to demonstrate how
businesses can monitor and improve their existing premises in a cost-effective
manner as they embark on their own net zero transition.
The intention is for a MICM Director to be appointed in spring 2024 (see Commercial
Case).  They will start developing MICM’s presence with local business immediately
and ensure that the project can progress quickly as soon as the MICM Hub is
available in autumn 2024.  The Director’s work will include active co-ordination with
service providers (notably NMIS, SMAS, CeeD and Interface) to ensure a regular
presence at MICM and their involvement in organisation of MICM events, as well as
liaison with MAATIC, BE Hub, Business Gateway and HIE’s own business support
programmes to market the six incubator units (40-70 sq. m each) and other flexible
workspace.
The MICM Hub will also have a technical and demonstration space that features a
range of specialist prototyping and testing equipment (e.g., 3D printing), helping it to
play an active role in supporting product and process innovation for business as well
as demonstrating relevant, accessible technologies and persuading them to invest in
their internal processes to move up the innovation and net zero ladders.  A MICM
Centre Manager will be appointed by autumn 2024 to take on the responsibility of
managing MICM’s technical and demonstration activity. Part-time
administrative/marketing support will also be needed and this will come on stream in
2024/25 as well.
The provision of MICM grow-on / accelerator space in a later phase will support the
MICM customer journey for those businesses in Hub incubators, enabling them to
move on to larger modern industrial premises on Enterprise Park Forres while
remaining part of the “MICM family” with continued access to MICM Hub support as
required.  Once again, the project is following the principle of repurposing an existing
building rather than new build.  Here the proposal is for existing commercial
premises at HIE-owned Unit 10 (already fitted with air source heat pumps) to be
reconfigured to three units of approximately 150 sq. m, supplemented by a 250 sq.m
new build unit with air source heat pumps and solar PV panels.  The new unit would
be on land immediately adjacent to Unit 10 owned by HIE with outline planning
consent for industrial use.  These units are a very short walk from Unit 9 / the MICM
Hub and at the very heart of Enterprise Park Forres, adjacent to Orbex and the
emerging space cluster.  The intention is to have these units ready for occupation
Page 127

Page 128

Page 48 of 208 
from 2027/28, in Year 4 of the MICM Hub’s operation, by which time it is anticipated
that one or more occupants from the incubator space will be looking to move on to
larger premises.
MICM incubators will be on flexible “easy in, easy out” terms and the grow-on space
will be on short, 2-3 year leases.  Flexible and short lease terms, and the inherently
higher risk profile of new start-up or early stage businesses, are not an attractive
proposition to property developers.  In Moray there is little speculative development
of even mainstream premises for established businesses on standard leases.  This
is why, in Option 1, without Growth Deal funding, nothing would be delivered.
Crowding out is not a concern given this specialised floorspace.
It is always difficult to demonstrate demand in markets that do not currently exist, but
there is clear evidence of unmet demand for incubator space in Moray.  Horizon
Scotland is at 110% occupancy with a waiting list, with some businesses there now
having to occupy meeting rooms.  The proposed MICM incubator space is also
entirely complementary to the activities of MAATIC and the BE Hub project in Elgin.
The former will provide desk space for researchers and the latter will provide pre-
incubation space for start-ups across all sectors as well as wider management skills
support for established entrepreneurs.  Further discussion on the complementarity of
the three projects and the arrangements in place to ensure co-ordination can be
found in the Commercial Case.
A key feature of MICM’s operation is to facilitate access by as many existing
businesses as possible to practical manufacturing innovation support that will make
a difference to their bottom line.  MICM will actively co-ordinate existing service
delivery to ensure that business access expertise and funding already available from
HIE, the National Manufacturing Institute for Scotland (NMIS), the Scottish
Manufacturing Advisory Service and Innovation Centres as appropriate to each case. 
It is anticipated SMAS, NMIS (operated by the University of Strathclyde) and
Interface will be present at MICM on a regular basis and actively involved in
supporting delivery and that there will be well-established links and cross-referral
mechanisms with MAATIC and BE Hub as described above. This proactive
collaboration will lead to Moray businesses developing more collaborative R&D
projects and Knowledge Transfer Partnerships to translate ideas into workable
prototypes, accessing relevant Innovation Centres and Catapult facilities as needed.
MICM will stimulate demand through targeted engagement and free demonstration
activities and events as well as a free initial diagnostic service in a concerted effort to
maximise interest and take-up.  The business survey detailed in the Strategic Case
shows a clear, unmet demand for practical “how to” support. The MICM business
model assumes that MICM will provide paid-for services for specific project support
to individual businesses.  The revenue model also assumes that as it gains
momentum, MICM will attract private sector funding from OEMs to support its
delivery activity.  The Commercial Case provides further detail on the operating
model.
By re-using two existing buildings the project can proceed more quickly and at lower
capital cost than new build.  From a net zero perspective, this approach will also
offer a much better demonstration to other businesses of how existing commercial
premises can be upgraded.  Importantly it will also consume less embodied carbon
Page 128

Page 129

Page 49 of 208 
in the construction process.  It will be an immediate statement of MICM’s intent to
show businesses how they can make important incremental changes to
decarbonisation in ways that have a positive impact on the bottom line.  This will
compliment MICM’s wider efforts to support businesses in decarbonising their
operations.  Plan 3.1 shows MICM’s location of Enterprise Park Forres in a Scottish
and Moray context, and Plan 3.2 shows the location of the Unit 9 and Unit 10 plots at
Enterprise Park Forres.
Page 129

Page 130

Page 50 of 208 
Plan 3.1:  Location of Enterprise Park Forres
Page 130

Page 131

Page 51 of 208 
Plan 3.2: Enterprise Park Forres layout, showing location of the MICM Hub (at Unit 9) and MICM Grow-on space (at Unit 10 
with adjacent new build) 
Page 131

Page 132

Page 52 of 208 
Option 3: Phase 1 MICM Hub (in new premises) and new Phase 2 grow-on
space
Option 3 assumes the same concept, service provision, floorspace configuration and
equipment specification as Option 2.  However, in this option the MICM Hub is a new
build.  This accords with the approval to Change Request 3 (May 2023) that a new
build comparator should be one of the FBC options.
Economic Appraisal 
Introduction
This section provides a detailed overview of the main costs, benefits and value for
money associated with each of the selected options, and the approach taken to
determining the preferred option.
Estimating Benefits
The benefits associated with the project have been modelled through an Economic
Impact Assessment conducted by Colin Warnock Associates (CWA) to support the
MICM FBC process.  They follow the same broad assumptions set out in the OBC,
albeit modified with more precise estimates of floorspace and timing.  Benefits have
been profiled per annum for a 25-year period from 2024/25 onwards.
Description, sources, and assumptions
The benefits fall into the following main categories:
• One-off benefits from the construction process and procurement of equipment
(Options 2 and 3).  These temporary benefits are excluded from the value for
money calculation;
• Operational benefits associated with the ongoing operation of MICM, its
employment of three staff (2.5 FTEs) as well as occupancy of the incubator
units;
• Catalytic, or further generated benefits, associated with:
o The additional penetration of innovation support services amongst indigenous
manufacturing businesses in Moray and enhancements to their
performance (Options 2 and 3)
o Business acceleration benefits arising from the graduation of businesses from
MICM Hub incubators and their further growth, facilitated by the MICM
grow-on units (Options 2 and 3)
o Additional inward investment to Moray resulting from the cluster development
activities attributable to MICM’s innovation activity (Options 2 and 3).
The benefits above are assumed to be identical between Options 2 and 3.  The only
difference is in the approach to the capital build, but the service solution is assumed
to be the same and to deliver the same economic impact.
Page 132

Page 133

Page 53 of 208 
Carbon assessments have been prepared by Graham and Sibbald to support the
FBC process and they will also prepare RICS Whole Life Carbon Assessments at
RIBA Stage 4 (detailed design).  These cover:
• Capital (embodied) carbon: this is a one-off disbenefit associated with the
construction process and the materials used in each option
• Operational carbon: this is an annual disbenefit associated with the energy
consumption associated with the MICM premises under each option.
All these benefits have been modelled over 10, 15 and 25 years to estimate the net
additional employment, income, GVA and carbon impacts at the Moray, Highlands
and Islands, Scotland, and UK levels, where:
• jobs are expressed as net additional full time job years, after taking account of
leakage, product market displacement, labour market substitution and indirect
and induced multiplier effects.
• income is expressed in net additional terms, after the same additionality
adjustments as for jobs, as a Present Value in constant 2023/24 prices, after
discounting at the Social Time Preference Rate (3.5%) in line with HM Treasury
Green Book guidance (2022)
• Gross Value Added (GVA), is also expressed in net additional terms as a
2023/24 Present Value, after discounting in the same way as the income
streams
• capital carbon and operational carbon are presented separately as monetary
2023/24 Present Values after discounting using the Social Time Preference
Rate.
The methodology, key assumptions and more detailed results tables can be found at
Appendix 2 while the carbon assessments are provided at Appendix 11.
The Economic Impact Assessment has assessed the impacts associated with the
construction phase of the project separately. These impacts are not included in the
value for money assessment but are provided in the detailed tables in Appendix 2.
Estimating Costs
Capital and revenue models have been developed by the project team, supported by
Torrance Partnership (capital), and Graham and Sibbald and CWA (revenue). The
cashflows developed are internally consistent with the assumptions used in the
economic impact assessment, particularly around the development occupancy of
premises over time.
Capital and revenue costs have been profiled per annum from 2023/24 onwards. 
Phase 1 capital costs will be based on tendered prices for works to Unit 9.  Those for
Phase 2 (grow-on units) are based on recent tender evidence for similar building
types procured by HIE in the last year, with appropriate adjustments for scale and
uplifts for inflation to 2023/24 prices.  (Although not relevant for the Economic Case,
the Financial Case allowances for future inflation to 2027/28 have been made based
on BCIS forecasts provided by Torrance Partnership. The inflation allowance for
Page 133

Page 134

Page 54 of 208 
2028/9 is an assumption based on the BCIS forecast trend for the period 2023/24 to
2027/28).
Rental income estimates have been made through discussion with Graham and
Sibbald, HIE’s retained property agent, and have also been informed by HIE’s direct,
recent experience of letting property at Enterprise Park Forres, including incubator
space at Horizon Scotland.
Contingency levels included in the capital and revenue models are discussed later in
this section (see Risk Appraisal).  For value for money analysis purposes only, the
capital costs and works duration have been subject to an Optimism Bias (OB)
Assessment which can be found in Appendix 4.  In relation to capital costs, the
project now involves reconfiguration to primarily existing commercial premises
owned by HIE with the new build element a standard build to an existing HIE design. 
In OB terms the project category is “standard buildings.” Unmitigated OB at FBC
stage has been assessed at 4.8% on capital costs. An OB adjustment of 5% has
therefore been applied to the base capital costs (including contingency) for Options 2
and 3.
The assessed unmitigated OB on works duration for a standard building (1.2%)
would lead to a very modest extension of a 6-9 month construction programme.
Given the inclusion of a reasonable contingency sum already, the impact of OB on
works duration has been treated as de minimis for the purposes of economic
appraisal.
No ready-reckoners are available for Optimism Bias on revenue costs.  However,
given the sensitivity of the revenue model to assumptions around rental streams and
paid-for services (see Commercial Case and Financial Case), unmitigated OB of
15% has been added to revenue costs for the purposes of the value for money
appraisal.
Economic Appraisal
An economic appraisal for the two intervention options is provided in Table 3.2.  This
presents the Present Value of a 15-year stream of the GVA benefits and carbon
disbenefits at the Moray level, the associated Present Value of Net Costs over the
same period (after adjustment for Optimism Bias), the resulting Net Present Social
Value and the Benefit Cost Ratio.
The results are in line with those forecast at OBC stage (Benefit Cost Ratio of 5.7:1
at the Moray level over 15 years at OBC, compared with 6.4:1 at FBC).  Option 2 has
a higher Benefit Cost Ratio than Option 3 and a higher Net Present Social Value. 
Option 2 is cheaper in capex terms because it repurposes Unit 9.  Although not
reflected in the relative benefits (which have been modelled to be identical), Option 3
will also take 9-12 months longer to achieve an operational start, since it would
require a more complex detailed design process and it is reasonable to expect that
achieving a building warrant would take longer, in addition to a longer build period.
Page 134

Page 135

Page 55 of 208 
Table 3.2: Appraisal Summary Table – 15 years at the Moray level 
Description
Option 2
MICM Hub re-using
Unit 9 / New grow-
on space
Option 3
New build MICM
Hub and grow-on
space
A
Present Value (2023/24) of Net Additional GVA benefits
and carbon disbenefits at the Moray level over 15 years
£m
£40,144,579 £39,947,076
B Present Value (2023/24) of Net Additional Costs (£m)
adjusted for Optimism Bias £6,234,244 £12,385,869
C Net Present Social Value (£m) [A-B] £33,910,335 £27,561,207 
Benefit Cost Ratio [(A / B] 6.4  3.2 
Benefits Switching Value (% reduction in PV of benefits
for BCR to be less than 1) -84% -69% 
Costs Switching Value (% increase in PV Net Costs
required for BCR to be less than 1) 643.9% 322.5%
Note 1: benefits are the operational and catalytic GVA benefits of MICM and capital and operational carbon
disbenefits; the temporary GVA benefits arising from the project’s construction are excluded from the NPSV and
BCR analysis
Note 2: costs and benefits are over and above Option 1 Business as Usual / No MGD funding reference case
Note 3: costs and monetised GVA benefits and carbon disbenefits have been discounted at a rate of 3.5% (the
Social Time Preference Rate) to a base year of 2023/24 (year 0), the year of appraisal
Note 4: 15 years means the period starting in year 1 2024/25 and ending in year 15 2038/39
Table 3.2 also presents switching values for both benefits and costs. Based on 15
years of benefits and costs at the Moray level, it would take a reduction of 84% in the
benefits before Option 2 had a BCR of 1:1 and costs would need to increase more
than six-fold. This demonstrates the strong resilience of the value for money of this
option to potential changes in costs or benefits.
Table 3.3 shows the relative performance of Option 2 over 10, 15 and 25 years.  The
performance of Option 2 becomes even more apparent over a 25-year period once
all the benefits are on stream.  Over a 25-year period Option 2 is forecast to have a
Benefit Cost Ratio of 9:1 at the Moray level and 11:1 at the Scottish level.
Table 3.3: Appraisal Summary Table – Preferred Option (Option 2) over 10, 15 and 25
years at the Moray, Scotland, and UK levels 
10 years 15 years 25 years
Present Value (PV) net additional costs of Option 2 (adjusted
for OB on capital costs) £6,119,769 £6,234,244 £6,411,783
PV net additional benefits for Moray (incl. carbon, excl.
construction) £27,356,451 £40,144,579 £57,739,169
PV net additional benefits for the Highlands & Islands £30,470,080 £45,063,149 £65,618,333
PV net additional benefits for Scotland £28,145,231 £44,485,982 £70,802,141
PV net additional benefits for UK £17,239,323 £31,092,176 £56,680,003
Benefit Cost Ratio (BCR) – Moray 4.5 6.4 9.0
BCR – H&Is 5.0 7.2 10.2
BCR – Scotland 4.6 7.1 11.0
BCR – UK 2.8 5.0 8.8
Net Present Social Value – Moray £21,236,682 £33,910,335 £51,327,386
Net Present Social Value – H&Is £24,350,312 £38,828,905 £59,206,550
Net Present Social Value – Scotland £22,025,463 £38,251,738 £64,390,359
Net Present Social Value – UK £11,119,554 £24,857,932 £50,268,221
Page 135

Page 136

Page 56 of 208 
Option 2 is the preferred option on Value for Money. It delivers the same level of
benefits more cheaply, faster, repurposes an existing building and in doing so
consumes less embodied carbon in the construction process. 
While GVA analysis forms an essential part of the economic appraisal, it is worth
highlighting that in employment terms:
• By year 10 Option 2 is expected to generate over 600 net additional job years of
employment at the Moray level (over 700 job years at the Highlands and Islands
level, over 800 job years at the Scottish level and over 600 job years at the UK
level).
• By year 15 this is forecast to have grown to almost 700 net additional job years
for Moray (more than 800 job years at the Highlands and Islands level, almost
1000 job years at the Scottish level and over 700 job years at the UK level)
• By year 25 it is estimated that MICM could deliver almost 800 net additional job
years in the Moray economy (over 950 at the Highlands and Islands level, over
1,100 job years at the Scottish level and over 900 job years at the UK level).
Further detail can be found in Appendix 5.
Carbon impacts
The carbon impacts of Option 2 are included in the cost benefit analysis above. 
Appendix 5 provides a Carbon Categorisation Form for the MICM project and
Appendix 11 details the carbon assessments undertaken to inform the FBC.  In
summary, in carbon control terms the project is Categorised as 3, i.e. it has a
capital carbon increase and then becomes operational net zero.  Table 3.4 below
shows that Option 2 has a very small one-off capital carbon disbenefit of £26,724
through the embodied materials used in construction, reflecting the fact that works
are minor and non-structural.  In operational carbon terms both Unit 9 and Unit 10
will use grid electricity as their primary energy source for light, heat and power, off-
set to some extent by power generated by newly installed solar PV panels on both
buildings.  They will be operationally net zero once the electricity grid is
decarbonised, but in the short-term they will have an operational carbon disbenefit
which is included in Table 3.4.
Table 3.4 Option 2: additional carbon impacts over and above the Option 1 reference
case
Type of carbon impact
Present Value £
2023/24 prices
10 years 15 years 25 years
Capital carbon (embodied carbon from
construction materials) -26,724 -26,724 -26,724
Operational carbon (from building energy
demand) -154,005 -224,391 -346,252
Total carbon disbenefit -180,729 -251,115 -372,976
In terms of the carbon influence of MICM, the project is classified as Category B
for appraisal purposes (see Appendix 5).  MICM will actively engage with businesses
to influence them on their net zero transition in ways which would support its
classification as Category A, but much of this work will be undertaken in partnership
Page 136

Page 137

Page 57 of 208 
with others. The benefits of this work have not been quantified as part of the
Economic Case but will form part of downstream monitoring and evaluation.  For that
reason, no quantitative benefits arising from this carbon influencing role are claimed
as part of the value for money assessment.
The Preferred option
The MICM Project Board met on 4th August 2023 to consider the output of the
economic appraisal above.  Following discussion and a review of the key
assumptions underpinning the Economic Impact Assessment, the Project Team
recommended Option 2 as the preferred option to take forward for detailed planning
in the Commercial, Financial, and Management cases of the Full Business Case.
Key Assumptions
Option 2 is detailed in full in the Commercial Case (Section 4)
The detailed assumptions which underpin the cost assumptions are set out in
Section 5 (Financial Case) and the EIA assumptions are detailed in Appendix 2.
Risk appraisal and sensitivity testing
The level of risk in Option 2 has been accounted for in the capital and revenue
models by the application of a 5% contingency to all capital works, a further 10%
contingency to the Unit 9 capital works to reflect design immaturity and a 10%
contingency to all revenue costs.  As noted above, for value for money assessment
purposes unmitigated Optimum Bias of 5% on capital expenditure and 15% on
revenue expenditure has been applied to the economic costs.
Table 3.5 describes the key risks which will need to be tracked and mitigated, where
possible, as part of the project’s delivery.  The project’s live risk register is provided
at Appendix 6.
Table 3.5: MICM key risks and their potential mitigation
Risk type Risk Potential mitigation
Reputational
risk
HIE and Moray Council’s
reputation amongst community
and partners and with Scottish
Government and UK Government
is damaged by poor project
delivery or failure
Focused governance on project
development. Appraisal and delivery through
the Moray Growth Deal Programme Board
and the MICM Project Board
Procurement
risk
Risk of legal challenge due to
inadequate planning or
procurement procedures
Adherence to HIE’s well established
procurement frameworks to deliver the
project
Planning risk Risk that building warrant is not
granted for the refurbishment of
Unit 9 or grow-on space
Compared with the OBC, planning risks are
significantly reduced.  No issues are
anticipated with obtaining a building warrant
for Unit 9 refurbishment and Enterprise Park
Forres benefits from outline planning consent
for industrial use which will pave the way for
detailed planning and building warrants for
the grow-on space in due course.
Page 137

Page 138

Page 58 of 208 
Risk type Risk Potential mitigation
Build risk Risk that capital costs exceed
those forecast due to
inadequacies in the design,
procurement, and project
management process. 
Ensuring clarity of the client-side design
process (see governance above), robust
procurement and project management
procedures to minimise scope creep and
contractor claims.
Project
intelligence /
environmental
risk
Unanticipated external risks
cause delays or other impacts on
project performance
Mitigated through regular liaison with key
stakeholders, including Scottish and UK
Governments
Operational
risk
Delay to, or lower quality,
recruitment of key project staff
Benefits Realisation Plan has already
anticipated the timing of preparation of job
description and allowing sufficient time for
high quality recruitment.  This will be further
mitigated by recruitment of a MICM Director
via a secondment route well ahead of
building opening.
Revenue risk Risk of revenue shortfall due to
lower than anticipated take-up of
services, incubator units or grow-
on space
Mitigated by void assumptions in business
planning and evidence-based assumptions
from elsewhere, together with ongoing
monitoring and good quality management
and oversight through governance
arrangements
Utilities risk Risk of delays to, or higher cost
provision of key utilities
Mitigated by early site investigations and
appropriate, evidence-based, cost
assumptions
Funding risk Risk that anticipated MGD funding
from UK and Scottish
Governments and/or HIE is not
available or not available at the
anticipated level
Mitigated through the business case process
by early sighting on funding requirements
and building a robust case for approval. 
A cross-option risk scoring process has not been undertaken for this project.  Both of
the short-listed options require substantial capital investment of a similar type and
the only difference between them is the extent of new build vs refurbishment. Their
risk profile is regarded as identical in relation to option choice.
The risk level of this project is judged by HIE to be acceptable at this stage.  Further
work is currently being undertaken to develop the detailed design for Option 2.  In
the Management Case, a Benefits Realisation Plan is provided demonstrating the
actions which need to be taken to move the project the next stage of detailed design
to procurement.
At this stage, the principal concern is whether Option 2 is resilient to changes in key
performance parameters.  The following two sensitivity scenarios have been
modelled to assess their impact on Option 2’s value for money.
• Scenario 1: Impaired financial performance
o Capital expenditure is assumed to increase by 10% more than the current
assumptions (in a base model which already includes the contingencies
and Optimism Bias adjustments described above)
Page 138

Page 139

Page 59 of 208 
o Rental income from incubators and grow-on units and paid-for service income
is assumed to be 10% lower than forecast from day 1 (on a base model
which already includes a void rate assumption for the MICM incubator
units, contingency and an Optimism Bias adjustment)
• Scenario 2: Reasonable worst-case scenario
o Capital expenditure is assumed to increase by 20% more than the current
assumptions
o Total rental and paid-for service income is assumed to be 20% lower than
forecast from day 1.
The base case performance of Option 2 is compared with the results of these two
sensitivity tests in Table 3.6 on the following page over all three time periods and all
four geographies.
In BCR and NPSV terms the value for money for Option 2 remains good even
in the more pessimistic Scenario 2.
After considering the risk profile of the options, undertaking switching value analysis
and testing its sensitivity to changes in key parameters, Option 2 remains the
preferred option on grounds of cost, benefits, risk and overall value for money. 
Page 139

Page 140

Page 60 of 208 
Table3.6. Option 2: value for money resilience to sensitivity test Scenarios 1 and 2 over 10, 15 and 25 years 
Over 10 years Over 15 years Over 25 years
Base case Scenario 1 Scenario 2 Base case Scenario 1 Scenario 2 Base case Scenario 1 Scenario 2
Present Value (PV) net
additional costs (£m) of
Option 2 (adjusted for
Optimism Bias)
£6,119,769 £6,724,361 £7,328,954 £6,234,244 £6,921,619 £7,608,993 £6,411,783 £7,227,543 £8,043,303
PV net additional
benefits for Moray (incl.
carbon, excl.
construction)
£27,356,451 £27,356,453 £27,356,456 £40,144,579 £40,144,582 £40,144,584 £57,739,169 £57,739,172 £57,739,174
PV net additional
benefits for the
Highlands and Islands
£30,470,080 £30,470,083 £30,470,085 £45,063,149 £45,063,151 £45,063,154 £65,618,333 £65,618,335 £65,618,338
PV net additional
benefits for Scotland £28,145,231 £28,145,234 £28,145,236 £44,485,982 £44,485,984 £44,485,987 £70,802,141 £70,802,144 £70,802,146
PV net additional
benefits for UK £17,239,323 £17,239,326 £17,239,328 £31,092,176 £31,092,178 £31,092,181 £56,680,003 £56,680,006 £56,680,008
Benefit Cost Ratio
(BCR) – Moray 4.5 4.1 3.7 6.4 5.8 5.3 9.0 8.0 7.2
BCR – H&Is 5.0 4.5 4.2 7.2 6.5 5.9 10.2 9.1 8.2
BCR – Scotland 4.6 4.2 3.8 7.1 6.4 5.8 11.0 9.8 8.8
BCR – UK 2.8 2.6 2.4 5.0 4.5 4.1 8.8 7.8 7.0
Net Present Social
Value – Moray £21,236,682 £20,632,092 £20,027,501 £33,910,335 £33,222,963 £32,535,591 £51,327,386 £50,511,629 £49,695,871
Net Present Social
Value – H&Is £24,350,312 £23,745,722 £23,141,131 £38,828,905 £38,141,533 £37,454,161 £59,206,550 £58,390,792 £57,575,035
Net Present Social
Value – Scotland £22,025,463 £21,420,873 £20,816,282 £38,251,738 £37,564,366 £36,876,994 £64,390,359 £63,574,601 £62,758,843
Net Present Social
Value – UK £11,119,554 £10,514,964 £9,910,374 £24,857,932 £24,170,560 £23,483,188 £50,268,221 £49,452,463 £48,636,705 
Page 140

Page 141

Page 61 of 208 
4. The Commercial Case 
Required Services
Capital works
The capital works associated with the Preferred Option comprise the following:
• The MICM Hub which will be located at existing Unit 9 at Enterprise Park
Forres
• MICM Grow-on units which will be located at existing Unit 10 at Enterprise Park
Forres as well as a 250 sq.m new build development immediately adjacent to
Unit 10.
The works are summarised in Table 4.1 below.  Appendix 7 provides a more detailed
breakdown of anticipated construction works.  These will be refined as part of the
detailed design process.
Table 4.1: MICM Option 2 (Preferred option) – capital works
Capital works Summary
MICM Hub
(Unit 9)
• Minor strip out works
• Alterations to lift position
• New front door, new doors to reception and a new large external door to the ground floor
technical/demonstration area to enable access for large pieces of equipment
• Strengthening of floors in ground floor technical/demonstration area with concrete plinths to
support heavy equipment
• Alterations to three existing lab units, including benches, to deliver 3 x incubator units
• Sub-division of ground floor storage space for 2 x incubator units
• Removal of internal partition between two smaller floor meeting rooms to create 1 x
incubator unit
• Works to first floor mezzanine area, enclosing this from ground floor technical /
demonstration area and providing new tea/coffee area and touchdown space
• Improvements to stair balustrades
• Alterations to existing underfloor heating as required
• Upgrade incoming electrical supply, with Phase 3 power to each of the incubator units
• Upgrade existing power and data installations
• Futureproofing for future installation of compressed air
• Upgrade light fittings to LED
• Upgrade access control to principal internal doors
• Solar PV to roof
• Improve roof insulation and acoustic performance (internally)
• Refresh of decoration and upgrade to signage
• Review and upgrade fire/security as required
MICM Grow-
on space
(Unit 10 plus
new build)
• Minor alterations to Unit 10 core (shared) area
• Unit 10 new roller shutter door
• Sub-division of Unit 10 (incl. services) to form 3 units 
• Upgrade to LED lighting throughout
• Link facility to new floorspace
• new 250 sq.m (gross) single story unit, linked to Unit 10 to manufacturing specification with
office accommodation, 3-phase power, Air Source Heat Pump and Solar PV
• general site works forming access road, car parking for new unit
• allowance for SUDS, rainwater, foul water sewers etc. and provision for storm cell
attenuation
Page 141

Page 142

Page 62 of 208 
Capital works Summary
• allowance for external services (electricity, broadband, water)
Table 4.2 summarises the floorspace created following the capital works described
above and sets out the rents which the Financial Case assumes will be charged for
each type of space.  These rents are in line with market rents and those that are
currently being achieved for new tenancies at Enterprise Park Forres.
Table 4.2: MICM Option 2 (Preferred option) – floorspace, lease terms and rents
Location on
Enterprise
Park Forres
Type of floorspace Quantity Lease terms and rent assumed
MICM Hub
(Unit 9)
Incubator unit 1 39.1sq.m (429 sq.ft) 12 month license, 1 month
termination either side.
£15 per sq.ft per annum, all-
inclusive, except for sub-metered
electricity, including
rates/water/cleaning/broadband
Incubator unit 2 59.5 sq.m (639 sq.ft) 
Incubator unit 3 40.4 sq.m (435 sq.ft)
Incubator unit 4 68 sq.m (731 sq. ft)
Incubator unit 5 68 sq.m (731 sq. ft)
Incubator unit 6 62.7 sq.m (674 sq.ft)
Rentable desk spaces 6 x c.5 sq.m
£208 per month (£2,500 pa) for
desks 1-4 and £333 for desks 4-5. 
12 month license, 1 month
termination either side, fully
inclusive
Meeting room (7.3x4.7m) 33.9 sq.m (365 sq.ft) Rental per hour £35, half day £90,
full day £170 (£500 pm assumed)
Other office/touchdown
space c. 125 sq.m (1360 sq.ft) N/A – MICM space
Technical/demonstration
space c. 210 sq.m (2260 sq.ft) N/A – MICM space
MICM Grow-
on Space
Grow-on unit 1 (Unit 10) 152 sq.m (1536 sq.ft) £9 per sq.ft per annum, based on a
2-3 year lease, including pro-rata
share of core space Grow-on unit 2 (Unit 10) 154 sq.m (1657 sq.ft)
Grow-on unit 3 (Unit 10) 154 sq.m (1657 sq.ft)
Core space (lobby / WCs)
in Unit 10 (subject to
service charge)
83 sq.m (893 sq.ft)
Grow-on unit 4 (new build) 250 sq.m (2690 sq.ft) 
Revenue services
The revenue services associated with the Preferred Option are set out in Table 4.3
below.  The delivery of these services is discussed later in this section.
Table 4.2: MICM Option 2 (Preferred option) – revenue services
Services to be
delivered
Detail
MICM Project
Delivery
• Provision of MICM Director (full-time, 35 hours per week) to job and person
specification defined by HIE (gross salary £75,000 pa)
• Provision of MICM Manager (full-time, 35 hours per week) to job and person
specification defined by HIE (gross salary £45,000 pa)
• Provision of MICM Administrator (part-time, 20 hours per week) to job and person
specification defined by HIE (gross salary £15,750 pa / Real Living Wage)
• All marketing and promotion of MICM including website development and maintenance
and search engine optimisation (SEO) support
• Event organisation, including venue hire, speakers, marketing/promotion and cost
Page 142

Page 143

Page 63 of 208 
Services to be
delivered
Detail
recovery through sponsorship
• Focused engagement with manufacturers to understand needs, develop baseline and
identify priority process/product and net zero improvement projects which will benefit
their bottom line
• Partnership development and co-ordination of inputs from other projects/service
providers, notably MAATIC, BE Hub, NMIS, SMAS, Innovation Centres and HIE
• Delivery of MICM paid for services and contracting, invoicing and recovery of
associated revenues
• Proactive role in wider cluster development activity
• Performance monitoring and engagement in evaluation activity
MICM Premises
Management
and
Administration
• Management, operation and maintenance of technical / demonstration space
• Tenant lettings and tenant management of the MICM Hub’s incubator, desk space and
meeting room as well as MICM Grow-on space
• Contract supervision (e.g. cleaning, security, building maintenance not covered by HIE
hard FM services)
• Invoicing and collection of rents from tenants and any other revenues due from other
parties plus financial management of all aspects of MICM with a dedicated cost centre
• Health & Safety Management
• Environmental Management
• Risk Management
• Emergency call-out management
How will MICM co-ordinate its services to SMEs with SMAS?
SMAS and MICM will work in close partnership in supporting Moray’s manufacturing
businesses and will offer complementary support. SMAS has a clear focus on
supporting improvements in productivity, culture and behaviours leadership while
MICM will support businesses moving from improvement to innovation. A good
example of this synergy is the clear pathway from SMAS’s promotion of digital
technology through the Industry 4.0 reviews through to MICM’s proposed support for
businesses to implement digital solutions.
MICM will also support SMAS by referrals and signposting and by extending the
reach of the innovation network into the parts of the manufacturing sector in Moray
who do not currently fully engage with the public sector.
How will MICM co-ordinate its services to SMEs with MAATIC and
BE Hub?
Figure 4.1 shows how MICM will be differentiated from MAATIC and BE Hub and
how the three projects will work collaboratively.
Page 143

Page 144

Page 64 of 208 
Figure 4.1:
Contribution of MICM, MAATIC and BE Hub to Moray’s economic development 
Table 4.3 details the services that will be delivered by each of the three Growth Deal
projects.
Table 4.3: MICM, MAATIC and BE Hub service delivery
Service type Service detail Project
MAATIC MICM BE Hub
Training /
teaching
Aircraft maintenance degree Y  
Non-aviation engineering degrees and
apprenticeships
Y  
Master programmes Y  Y
Apprenticeship Y  Y
Commercial CPD and micro-credentialing Y  Y
Executive programmes (MBA/DBA) Y  Y
Accredited and non-accredited CPD courses
(leadership and management, leadership
behaviours, IT, project management, analytics,
cyber security
Y  Y
STEMD STEMD activities Y  
Research Doctor of Business Administration  Y  Y
Business PhDs Y  Y
Other PhDs (including part time and distance) Y  Y
REF-able research Y  Y
Innovation vouchers  Y Y
Management Knowledge Transfer Partnerships Y  Y
Masters by research Y  Y
Collaborative work with NMIS  Y 
Collaborative work with other HEIs Y  Y
Business
mentoring,
SMAS presence  Y 
Interface presence  Y Y
Page 144

Page 145

Page 65 of 208 
Service type Service detail Project
support,
networking, 
and support
HIE presence  Y Y
Chamber of Commerce presence   Y
Business Gateway presence   Y
Exhibition space   Y
Networking events and activities Y Y Y
Strategic liaison support and signposting Y Y Y
Accessible R&D Digital manufacturing space  Y 
Digital design lab / studio Y Likely 
Distributed factory capacity   Likely 
3D printer lab Y Y 
Robotics lab (demo, coding, signposting and
installation advice)
Y Y 
Flexible / reconfigurable manufacturing bays  Y 
Heavy lifting facilities Y  
Clean research space Y  Y
Consumer / product testing space   Y
Incubation
space
Pre-incubation space (hot desks) or small office
space
Y Y Y
Incubation space on flexible terms  Y Y 
Associated enterprise support delivery  Y Y
Accelerator / grow on space  Y 
Other space Flexible event space / common space (multi-
purpose, multi size with high quality AV) 
In Horizon
Centre, no
revenue
Y
Net zero demonstration facilities  Proposed 
Table 4.4 shows the potential areas for overlap between the three projects and
identifies how service co-ordination will be managed.
Table 4.4: MICM, MAATIC and BE Hub – mitigating service overlaps
Overlap Projects involved How duplication of service provision will be managed
Accessible R&D
facilities
- MAATIC
- MICM 
There will be a clear pathway between the 2 facilities to
ensure that as and when students require access to more
advanced equipment (such as for a dissertation) they are
able to use items available in MICM. 
MAATIC and MICM will use the monthly meetings to liaise
on equipment provision to avoid duplication and
redundancy between the two centres. They will also
consider provision elsewhere in Scotland and the UK as
alternatives to in-house provision. 
As a general principle, equipment provision at MAATIC will
be aimed at general skills development for students while
MICM will focus on specific, higher specification provision
for businesses. 
Incubation space - BE Hub 
- MAATIC
- MICM 
The projects will use these spaces to target different
sectors. 
- BE Hub:  Any micro/small business not directly related to
MAATIC/MICM or if there is no available space at one of
these sites.
- MAATIC:  Aviation, digital/tech businesses and spin offs.
- MICM: Local manufacturing and engineering businesses
including start-ups and established businesses. Will likely
Page 145

Page 146

Page 66 of 208 
Overlap Projects involved How duplication of service provision will be managed
be focused on short term, flexible use on a project basis,
predominantly to give existing businesses space to
progress product or process development away from
‘day job’ activity. The facility will also have grow-on
space for expansion of projects/businesses developed
through other incubators. 
Teaching /
training
- BE Hub 
- MAATIC 
The main difference between the 2 projects is the sectors
being targeted.  BE Hub will focus on business skills,
whereas MAATIC’s will be aerospace skills, digital /
immersive technologies and skills for safety critical
environments.   
HIE and UHI Moray and their associated project teams have mutually agreed that,
“irrespective of where a student, individual or business commences their interaction
with the BE Hub, MAATIC and MICM ecosystem, staff supporting them will be
trained to give advice that ensures the optimum route for progression is set out, even
if that is not within the facility the journey started off in.  This is critical to ensure the
best quality pathways are created and that the strongest outcomes are generated for
users.”
To achieve this, the following steps are proposed:
• Monthly meetings involving the management teams of the facilities.  These will
seek to:
o Identify early any strategic changes in the service offers of each facility, with
the facilities being consultees as part of the change control /approval
process for any service variations within UHI and HIE so there is an ability
to quantify the positive or negative impact on specific facilities with an
associated proportionate management plan to be put in place.
o Review operational activity, gaining insight on the pathway journeys of
students, individuals and businesses that will generate learning on how
these can become more efficient and user focused.
o Ensure visibility around planned future temporary activity such as showcases
or exhibitions, with the aim that agreement is reached regarding how the
three facilities will support these to maximise their impact.
o Jointly assess new or replacement equipment requirements for the facilities
with a view to preventing duplication and to ensure value for money.
• Regular (through the annual employee performance review process or
equivalent) development plans to be put in place for key groups of staff to
ensure insight gained on pathway journeys drives improved training for staff
and continual improvement in service provision.
Page 146

Page 147

Page 67 of 208 
The MICM customer journey
Figure 4.2 on the following page shows the MICM customer journey.
MICM’s services were described in Table 4.2 and include a range of tenancy options
(incubator space, desk space, and grow-on space), but at the heart of MICM’s
objectives is engagement with indigenous manufacturing SMEs in Moray on product
and process innovation as well as supporting net zero transition in their operations.
As Figure 4.2 demonstrates, it is anticipated that the engagement process for many
of these services will be by raising MICM’s profile with these potential service users
through events, referrals and direct engagement. MICM will have a well organised
programme of relevant, targeted events which will be free for SMEs to attend. These
will be organised in close coordination with other service providers (e.g. CeeD and
NMIS).  MICM will follow-up with further free diagnostic and advice services, to
understand business operations, establish their current baseline in product and
process innovation and net zero transition terms.  From there, an action plan can be
developed, quantifying key issues and highlighting specific improvement projects
which will demonstrably bring benefits to the bottom line.
In some cases MICM will then actively support engagement with relevant innovation
service providers (e.g. NMIS, CeeD or Innovation Centres) to meet specific needs. 
In other cases, MICM itself will provide more in-depth advisory and support services
to the SME, either on a specific project or to support them in working up applications
for funding from other providers.  Use cases showing how MICM will engage with
micro, small and medium SMEs in these paid for services – in a differentiated way
from the support available from other providers – are provided in Table 4.5.
Table 4.5: Use cases showing differentiated MICM paid-for services
Business profile The need Barriers to innovation Likely paid for services
Micro Getting started –
taking the first
steps on product
and process
innovation
New to innovation
Time
Skills 
Infrastructure 
Small equipment hire 
Project development 
Project management
Project delivery 
Small Making the leap –
moving from
improvement to
automation 
Sceptical on value
Time
Skills
Infrastructure
Project development 
Project management
Project delivery 
Development space
Demonstration space 
Medium/Large Staying on course
– continuing the
innovation journey
Time
Advanced skills
Need for
justification/business
cases 
Feasibility projects
Project support
Longer term
development/pilot space 
Page 147

Page 148

Page 68 of 208 
Figure 4.2: MICM customer journey 
1.Enquiries
1. Referrals
1a. Evaluation
Refer
2. Project
development
3. Project
execution
Decline and close
4. Project
closure
Project plan Progress reports
Project
closedProgress
Enquiries
• Businesses
• Events
• Direct
Referrals
• SMAS
• NMIS
• CeeD
• Interface
• HIE
• BEH
• MAATIC
• Other
Project plan
• Cost and funding
• Schedule
• Risks
• Partners
• Process
• Equipment
• Space
• Outcomes
Project closure
• Project report
• Benefits
capture
• Lessons learned
• Case study
• Follow-on
projects
MICM – project process flow - generic
Process step
Project
deliverables
Key
Project types
1. Events and training
2. Space provision
3. Feasibility/research
4. Process
development
5. Inhouse support
6. Other
Documents
Page 148

Page 149

Page 69 of 208 
Market rates will be adopted and it is intended that MICM will develop a network of
third party providers to work collaboratively with SMEs, thus mitigating concerns
about crowding out.  If MICM is successful in meeting its objectives, the size of the
local market for manufacturing innovation advisory services can be expected to
increase as SMEs become less risk averse over time.
However, in the short term, as the Strategic Case highlighted, levels of risk aversion
are high and it will take time and concerted effort to stimulate demand. 
Nevertheless, the business survey showed quite clearly that there is both an
underlying need and clearly expressed demand for services of the kind that MICM
will offer.
The revenue model which forms part of the Financial Case makes the following
assumptions about the build-up of paid-for services during MICM’s initial operation
(Table 4.6).  Enquiries to HIE’s Moray office demonstrate latent demand for a MICM-
type service where hands-on advisory support forms part of the service which would
support levels of service activity being forecast.
Table 4.6: Build up of MICM paid-for services
Service user
SME type
Full operating
target 2024/25 2025/26 2026/27 2027/28 2028/29 2029/30
Medium 5 projects pa @
£10,000 0 12,500 20,000 30,000 35,000 50,000
Small 10 projects pa @
£5,000 0 12,500 20,000 30,000 35,000 50,000
Micro 15 projects pa @
£2,500 0 9,375 15,000 22,500 26,250 37,500
Total revenue from paid-for services 0 34,375 55,000 82,500 96,250 137,500 
Treatment of VAT
For the purposes of the financial modelling presented in this FBC, Value Added Tax
is not included.  It is expected that VAT will be levied at the prevailing rate on all
paid-for services (including rents and project support) and that all VAT will be fully
reclaimable.
Potential for Risk Transfer
Table 4.7 provides an assessment of how the associated risks are likely to be
apportioned between the public and private sectors.
The nature of the MICM project means that even though capital works will be
procured from the private sector (see Procurement), most risks will remain with the
public sector, at least until the project is self-sustaining.  However, it is anticipated
that some of the construction and development risk will be shared with the private
sector as part of the procurement of the capital works.  As regards revenue service
delivery, even under an outsourced model, it is anticipated that the risk allocation
would remain with the public sector, at least until the project is self-sustaining,
because of the nature of the services being contracted.
Page 149

Page 150

Page 70 of 208 
Table 4.7: MICM Option 2 (Preferred option) – potential risk allocation 
Risk Category
Potential allocation
Public
(HIE)
Private
(contractor)
Shared
1. Design risk ✓  
2. Construction and development risk   ✓
3. Transition and implementation risk ✓  
4. Availability and performance risk ✓  
5. Operating risk ✓  
6. Variability of revenue risks ✓  
7. Termination risks ✓  
8. Technology and obsolescence risks  ✓  
9. Control risks ✓  
10. Residual value risks ✓  
11. Financing risks ✓  
12. Legislative risks ✓  
13. Other project risks ✓  
Capital risks are assessed as low due to HIE’s long experience of property
development, its ownership of Units 9 and 10 and of the land adjacent to Unit 10. 
Risks are further mitigated by the fact that Enterprise Park Forres already has outline
planning consent for these activities.
Risks in revenue service delivery will be mitigated through clear contractual
arrangements, including KPIs linked to the service specification.
Procurement strategy and implementation timescales
Capital works
HIE will lead the project and will design and procure the refurbishment of Unit 9 and
of the subsequent phase of grow-on units (Unit 10 and new build) using its existing
procurement frameworks.  Procurement will be subject to the contract value following
detailed design but is likely to take the form of either a Quick Quote (up to £2.0M), or
through a Sub-FTS procurement process (previously a Competitive Open Tender,
now a Sub-Find a Tender Service). The procurement of the grow-on Units will either
be via a Sub-FTS or FTS procurement depending on the contract value.
It is anticipated that, subject to FBC approval, tenders would be returned for the
MICM Hub phase in early 2024, enabling works to commence prior to the end of the
2023/24 financial year with completion within 6-9 months.  As discussed above,
detailed design and tendering of the MICM Grow-on space will be designed and
tendered in 2026/27.
Revenue services
HIE has undertaken a review of the issues and options associated with the delivery
of MICM services which is summarised in Table 4.8 on the following page.  Delivery
options which have been considered range from HIE taking on direct delivery of the
service through to a standalone entity.
Page 150

Page 151

Page 71 of 208  Page 151

Page 152

Page 72 of 208 
Table 4.8: MICM Service Delivery – key issues and options framework
TIMESCALES: SHORT-TERM (1-5 YEARS) POSSIBLE MEDIUM/LONGER TERM (5+ YEARS)
GOVERNANCE: HIE Growth Deal Programme governance arrangements
Moray Growth Deal Programme governance arrangements
MICM SRO + Project Board (responsibilities increase with more formal project structures)
PROJECT
STRUCTURE:
Direct Projectised Subsidiary Joint Venture
DELIVERY OPTIONS: Direct – staff
added to HIE’s
headcount
Project staff recruited
and managed by HIE +
all HIE costs projectised
Contract for
services + other
HIE costs
projectised
Direct
(subsidiary
employees)
Contract
for
services
Direct (JV
employees)
Contract
for
services
PROPERTY ASSETS: Retained by HIE Retained by HIE Retained by HIE Transferred to subsidiary
or retained by HIE
Transferred to JV or
retained by HIE
CONCLUSION: REJECTED
Headcount and
access to skills
UNDER EVALUATION
Project team currently appraising these
options
FUTURE DECISION
Informed by interim evaluation and governance
reviews once project underway
KEY
CONSIDERATIONS:
• Alignment with HIE’s current operating model
• Access to skills to ensure timely, effective delivery
• Value for money
• VAT and tax issues (implications for VAT charging and recovery (including on construction costs) of different
options)
• Governance burden
• Legal / technical / accounting burden 
Page 152

Page 153

Page 73 of 208 
It will not be possible for HIE to directly deliver the project from existing headcount or
through recruitment of new HIE permanent staff.  The proposal is that the service will
be delivered initially as a HIE project, allowing it to have its own cost centre within
HIE.  In terms of staffing and the delivery of the range of services set out at Table 4.2
above, HIE is currently assessing the most appropriate way forward, taking into
account the range of considerations set out in Table 4.8, including value for money
as well as technical issues around VAT and tax treatment.  Of the two remaining
options the first is the recruitment on fixed term contracts of project staff and the
alternative is to outsource delivery through a Contract for Services.
In the event that a Contract for Services is pursued, then the procurement process
will be determined by contract length (see below) and contract value but would likely
take the form of a Sub-FTS or FTS procurement process as described above.
The stepping up of revenue services will be phased, so that a MICM Director can be
in place to launch MICM in spring 2024, moving to full operation as the capital works
on the MICM Hub reach completion later in 2024.
Under either delivery option, contract management will sit with HIE. The
Management Case discusses project governance arrangements in more detail.
By 2029/30, two years out from the end of the Growth Deal period, HIE expects to
have developed an approach for the creation of MICM as a standalone entity and
HIE’s exit from the project (see Management Case). Any decisions around service
delivery will be determined by the agreed governance pathway at that stage.
Proposed Charging Mechanisms
Capital works
Payment for all design, construction and development contracts will be made by HIE
according to a pre-agreed payment schedule.  This schedule will form part of the
contract (see below) with the Most Economically Advantageous Tenderer (MEAT)
selected through the procurement process described above.
Revenue services
If MICM is delivered by a dedicated, fixed-term project team, then HIE will charge for
all MICM paid services and all HIE costs incurred in the delivery of the MICM project
would be projectised.
Under an outsourced Contract for Services, payment to the Service Contractor would
be made according to a pre-agreed payment schedule as negotiated with the
successful tenderer.
In that scenario, the Service Contractor would be responsible for delivering the
MICM project to an agreed annual budget and would also be responsible for all
income recovery from incubator spaces, desk spaces and meeting room hire at the
MICM Hub as well as rents from the MICM Grow-on space.  The Service Contractor
would also be responsible for the delivery of other MICM paid services to SMEs.
Page 153

Page 154

Page 74 of 208 
Irrespective of the delivery solution, the charges for all MICM services to end users
will be at market rates. No subsidy will be provided to SMEs through any of MICM’s
charging activities.
Proposed Contract Lengths
Capital works
It is anticipated that there will be two contracts for capital works:
• the creation of the MICM Hub through the refit of Unit 9 will take place first. 
Detailed design work has now commenced, commissioned by HIE through its
Lot 3 Building Surveying Framework.  This includes detailed design, planning
services to building warrant stage and provision of a tender pack for the works. 
The procurement process for these works will commence as soon as possible
following approval to the FBC.  On this basis, it is assumed that the
construction contract will span two financial years (2023/24 to 2024/25).  An
action plan with a programme of key dates is provided in the Management
Case (Section 6.1.3).
• the creation of MICM Grow-on space through the reconfiguration of Unit 10 and
the creation of a linked new building on the same plot is programmed to take
place in 2026/27.  The current programme assumes that the works will span
two financial years, 2026/27 and 2027/28.
Revenue services
If fixed-term project staff are recruited to deliver MICM, then these would be for a
minimum of 3 years with the potential to extend by a further year.
If the services are outsourced, then the contract length will also be for an initial term
of 3 years, with potential to extend by a further 1 year.
An interim evaluation will take place during 2026/27, in good time to assess the
performance of the project and its delivery solution during the initial 3 year delivery
period, prior to a decision about extending to a fourth year.  The interim evaluation
will also inform any update to the specification of requirements for revenue services
for a second 3-4 year period.
Proposed Key Contractual Clauses
Capital works
All capital works will be contracted using a NEC4 Engineering and Construction
Contract June 2017 (with amendments January 2019 and October 2020), the
template for which can be found in Appendix 8.  The key clauses include the
following:
• Scope
• Site information
• Contractor’s main responsibilities
• Time (including Start Date and Completion Date)
Page 154

Page 155

Page 75 of 208 
• Quality management
• Payment
• Compensation events
• Liabilities and insurance
• Resolving and avoiding disputes
• Price, payment and tax
• Retention
• Low performance damages
Revenue services
If revenue services are contracted out, then this would be via a Management
Services contract.  These contracts are bespoke to each service and a draft contract
would be prepared alongside the Specification of Requirements.  Based on HIE’s
experience of managing a similar contract at Horizon Scotland (which includes
management of incubator space), the key contractual clauses could be expected to
include:
• Term
• Scope
• HIE’s obligations
• The Services and Performance Management
• Manner of Carrying Out the Services
• Standard of Work
• Key Personnel
• Contractor’s Staff
• Inspection of Premises
• License to Occupy Authority’s Premises
• Authority Property
• Sub-contracting for the delivery of the Services
• Offers of Employment
• Price
• Payment and Tax
• Statutory Obligations and Regulations
• Protection of Information
• Control of the Agreement, including variation and remedies in the event of
inadequate performance
• Liabilities and insurances
Page 155

Page 156

Page 76 of 208 
• Default, disruption and termination
Any Management Services Contract would also include additional schedules
covering Intellectual Property Rights, Staff Information, Details of Processing of
Authority Personal Data and Key Performance Indicators.
Personnel implications
TUPE – Transfer of Undertakings (Protection of Employment) Regulations 1981 –
will not apply to this investment.  No existing staff are involved. The MICM project
team will either be recruited as fixed term project staff, or delivery will be outsourced
to through a Contract for Services where the contract will ensure that there are no
TUPE liabilities for HIE.
Page 156

Page 157

Page 77 of 208 
5. The Financial Case
Project expenditure and income
Capital expenditure and funding sources
The works associated with the preferred option will have a capital cost of £5.61
million (including contingency and inflation allowance).  This is lower than the £6.89
million anticipated at OBC stage due to the repurposing of existing premises.
Based on the funding shares established at OBC stage, of the new total capex
requirement Moray Growth Deal funding is anticipated to provide just over £3m
(£2.44m from UK Government and £0.61m from the Scottish Government) with HIE
investing £2.56m (net) to cover the balance.
Table 5.1: Option 2 (preferred option) – capital funding requirement and funding
strategy, including inflation 
OBC capital funding
strategy
Anticipated FBC capital
funding strategy
Highlands and Islands Enterprise 3,142,000 2,557,010
Scottish Government 750,000 610,362
UK Government 3,000,000 2,441,448
Total 6,892,000 5,608,820 
Table 5.2 on the following page shows the capital expenditure profile for Option 2 in
more detail.  For FBC purposes, cost estimates have been prepared by Torrance
Partnership on behalf of HIE, based on briefings by the project team on the nature of
the work that will be required for both elements of the project.  These were detailed
in the Commercial Case.
Table 5.2 also shows that in addition to HIE’s £2.56m contribution to the cost of the
works, the capital model assumes that HIE will provide grant-in-aid funding (currently
estimated at £550,000) to a new MICM entity at the end of the Growth Deal period to
enable the entity to acquire the MICM Hub and Grow-on assets from HIE. This is
consistent with HIE’s exit strategy for the project which is set out in the Management
Case.  This sum does not form part of the capital funding ask at this stage but is
shown for completeness. Any decisions on future asset transfer to a new entity will
be made with the explicit agreement of the Moray Growth Deal and Scottish
Government and UK Government stakeholders.
Revenue income and expenditure and funding sources
At OBC stage, MICM was forecast to become self-sustaining by 2033/34, around two
years after the end of the Growth Deal programme in December 2031.  The OBC
forecast was that in addition to full draw-down of the Scottish Government’s revenue
Page 157

Page 158

Page 78 of 208 
grant funding of £1.25m, HIE would need to make a further revenue contribution of
£125,000.
Page 158

Page 159

Page 79 of 208 
Table 5.2: Capital cost and funding requirements
Item Assumptions Total 2023/24 2024/25 2025/26 2026/27 2027/28 2028/29 2029/30 2030/31
Project development costs (OBC,
FBC incl. cost estimates)
Costs to tender stage not
included below 134,000 134,000       
Unit 9 refit and net zero
improvements
TP 23.805 V2, incl. prelims,
5% works contingency, fees
and planning costs + further
10% contingency to reflect
design immaturity
1,597,344 239,602 1,357,742      
Equipment (incl. office equipment)  750,000  750,000      
Net zero demonstration Based on CENSIS proposal 50,000  50,000      
Unit 10 refit (3 x grow-on units, 543
sq.m GIA) and additional new build
grow on unit (250 sq.m GIA)
TP 23.805 V2, incl. prelims,
contingency, fees and
planning costs
2,365,611    1,537,647 827,964   
Total public sector capital cost,
excluding inflation  4,896,955 373,602 2,157,742 0 1,537,647 827,964   
Inflation allowance (per annum) Based on Torrance
Partnership advice of 5-7% pa  1.00 1.06 1.06 1.06 1.06   
Inflation allowance (cumulative)   1.00 1.06 1.12 1.19 1.26   
Total public sector capital cost,
including inflation allowance  5,608,820 444,966 2,287,207 0 1,831,362 1,045,285   
Plus HIE investment to enable new
MICM Entity to acquire Units 9 and
expanded Unit 10 from HIE in Year 7
(2030/31)
Subject to discussions on
governance and valuation of
assets at that time
550,000        550,000
Minus Capital receipt to HIE from sale
of Units 9 and 10 to MICM
Subject to discussions on
governance and valuation of
assets at that time
550,000        550,000
Net public sector capital cost
(2023/24 prices, excluding inflation)  4,896,955 373,602 2,157,742 0 1,537,647 827,964 0 0 0
Net public sector capital cost
(including inflation)
Capital funding ask now
(including inflation) 5,608,820 444,966 2,287,207 0 1,831,362 1,045,285 0 0 0 
Page 159

Page 160

Page 80 of 208 
Following further development of the operating and revenue model during the FBC
process, MICM is now forecast to become financially sustainable during 2031/32,
within ten years of opening.  Until its revenue-generating capacity comes fully on
stream, it is forecast to require revenue deficit funding totalling £1.25m to December
2031 (from the Scottish Government’s £1.25m revenue contribution to the project). 
In the event that the deficit position is higher or extends for longer, HIE will fund any
additional revenue deficit.  Table 5.3 shows an income and expenditure profile for
the project from January 2024 to December 2031 when the Growth Deal ends,
showing how, as income builds up, MICM is expected to become self-sustaining by
the end of the period.
Table 5.3: Option 2 (preferred option) – revenue income and expenditure including
inflation
Growth Deal
Year
3 4 5 6 7 8 9 10 To Dec
31
MICM year 0 1 2 3 4 5 6 7
Financial year 2023/24 2024/25 2025/26 2026/27 2027/28 2028/29 2029/30 2030/31 2031/32
Income 0 21,975 122,526 192,341 262,470 316,548 394,260 441,231 452,262
Expenditure 47,388 328,261 395,946 443,965 410,894 421,167 491,361 442,488 432,655
Expenditure
minus income
(surplus is
negative)
47,388  309,173  276,423  254,703  151,580  107,853  100,416  4,655 -19,607 
Table 5.4 shows the cumulative deficit position over the period to December 2031.
Table 5.4: Option 2 (preferred option) – revenue income and expenditure including
inflation
Financial Year Expenditure minus income in
year (negative is surplus) Cumulative deficit
2023/24 47,388 47,388
2024/25 309,173 356,561
2025/26 276,423 632,984
2026/27 254,703 887,687
2027/28 151,580 1,039,267
2028/29 107,853 1,147,119
2029/30 100,416 1,247,535
2030/31 4,655 1,252,190
Q1-Q3 2031/32 (i.e. to December
2031) -14,705 1,237,485
2031/32 (full year) -19,607 1,232,584
2032/33 -20,097 1,212,487
Table 5.5 shows the revenue model to the end of the Growth Deal period in detail.
Page 160

Page 161

Page 81 of 208 
Table 5.5: MICM revenue model, 2023/24 to 2031/32
Category Item Assumptions 2023/24 2024/25 2025/26 2026/27 2027/28 2028/29 2029/30 2030/31 2031/32
EXPENDITURE
EPF Service
Charges
For Unit 9 from Day 1, and
Unit 10 when this becomes
part of MICM operation
Unit 9: 25% in year 1,
then 100% thereafter;
Unit 10: 100% from Year
3 onwards
317 1,269 1,269 2,230 2,230 2,230 2,230 2,230 2,230
Staffing (incl.
on costs)
Project Director (1 FTE) -
Salary
Contract for services 18,750 75,000 75,000 75,000 75,000 75,000 75,000 75,000 75,000
Project Director - On-costs On-costs assumed to be
21%
3,938 15,750 15,750 15,750 15,750 15,750 15,750 15,750 15,750
Centre Manager (1 FTE) -
Salary
Contract for services 0 33,750 45,000 45,000 45,000 45,000 45,000 45,000 45,000
Centre Manager - On-costs On-costs assumed to be
21%
0 7,088 9,450 9,450 9,450 9,450 9,450 9,450 9,450
Administrator (20 hours) -
salary
Contract for services /
assumed Real Living
Wage
0 8,502 11,336 11,336 11,336 11,336 11,336 11,336 11,336
Administrator (part-time) -
on-costs
On-costs assumed to be
21%
0 1,785 2,381 2,381 2,381 2,381 2,381 2,381 2,381
Marketing Branding and ongoing
promotion 
5,000 20,000 20,000 20,000 15,000 15,000 15,000 15,000 15,000
Website (ongoing)   15,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000
Other
overheads
Rates, Water & Waste Based on G&S Unit 9
data
10,000 40,000 40,000 40,000 40,000 40,000 40,000 40,000 40,000
Broadband
/Telephone/Internet
HIE based on Horizon
Scotland
2,250 9,000 9,000 9,000 9,000 9,000 9,000 9,000 9,000
Electricity Latest assumption is
£2,500 pm (1.5x Horizon
Scotland) (checking also
with AMC Fort William)
0 15,000 30,000 30,000 30,000 30,000 30,000 30,000 30,000
Security & Fire HIE based on Horizon
Scotland
0 1,800 1,800 1,800 1,800 1,800 1,800 1,800 1,800
Cleaning HIE based on Horizon
Scotland
0 2,250 9,000 9,000 9,000 9,000 9,000 9,000 9,000
Event costs (incl. catering
and hire)
Assumption 0 10,000 10,000 10,000 10,000 10,000 10,000 10,000 10,000
Internal maintenance - unit 9 HIE assumption 0 625 2,500 2,500 2,500 2,500 2,500 2,500 2,500
External maintenance - unit
9
HIE assumption 625 1,250 2,500 2,500 2,500 2,500 2,500 2,500 2,500
Insurance   250 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000
Page 161

Page 162

Page 82 of 208 
Category Item Assumptions 2023/24 2024/25 2025/26 2026/27 2027/28 2028/29 2029/30 2030/31 2031/32
Legal fees    3,000 3,000 3,000 3,000 3,000 3,000 3,000 3,000
Other professional fees e.g. equipment,
compliance 
3,000 3,000 3,000 3,000 3,000 3,000 3,000 3,000
Office Equipment purchase   500 500 500 500 500 500 500 500
Staff Training  500 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000
Staff travel expenses  1,000 2,000 2,000 2,000 2,000 2,000 2,000 2,000 2,000
IT support  300 1,200 1,200 1,200 1,200 1,200 1,200 1,200 1,200
Printing, postage and
stationery 
150 600 600 600 600 600 600 600 600
Bank charges    840 840 840 840 840 840 840 840
Other service stand-up costs    12,500 30,000 30,000 30,000 30,000 30,000 30,000  
Governance SLA with HIE Assumed £7.5k (in
2023/24 prices) from
Year 11                
7,500
Accounting and auditing Assumption (from Year
11), say £5k                
5,000
Monitoring
and
Evaluation
Ongoing monitoring (annual
business survey) 
0 3,000 3,000 3,000 3,000 3,000 3,000 3,000 3,000
Interim evaluation (formative,
after 2 years) 
0 0 0 30,000 0 0 0 0 0
Final (impact) evaluation
(after 7 years) 
0 0 0 0 0 0 45,000 0 0
Total revenue cost before contingency  43,080 286,709 332,125 363,087 328,087 328,087 373,087 328,087 310,587
Contingency (10%)  4,308 28,671 33,213 36,309 32,809 32,809 37,309 32,809 31,059
Sub-total, public sector revenue cost 
excuding inflation 
47,388 315,380 365,338 399,396 360,896 360,896 410,396 360,896 341,646
Cumulative inflation allowance from
2024/25 onwards
Assumes 5% in 2024/5,
4% for 2025/6 then 2.5%
thereafter
1.00 1.05 1.09 1.12 1.15 1.18 1.21 1.24 1.27
Total public sector revenue cost, including
inflation allowance 
47,388 331,149 398,949 447,044 414,049 424,401 494,676 445,886 432,655
INCOME
MICM Hub
Incubation
space
Unit 1 (39.06 sq. m / 420 sq.
ft) (GF rear existing)
12 mths license, 1 mth
either side
Assume £15 per sq. ft pa
(all-inclusive
(rates/water/cleaning/bro
adband) except for sub-
metered electricity)
0 4,725 6,300 6,300 6,300 6,300 6,300 6,300 6,300
Unit 2 (59.45 sq. m / 639 sq.
ft) (GF rear existing)
" " 0 7,189 9,585 9,585 9,585 9,585 9,585 9,585 9,585
Page 162

Page 163

Page 83 of 208 
Category Item Assumptions 2023/24 2024/25 2025/26 2026/27 2027/28 2028/29 2029/30 2030/31 2031/32
Unit 3 (40.41 sq. m / 435 sq.
ft) (GF rear existing)
" " 0 0 6,525 6,525 6,525 6,525 6,525 6,525 6,525
Unit 4 (68 sq. m / 731 sq. ft)
(GF front new)
" " 0 0 5,483 10,965 10,965 10,965 10,965 10,965 10,965
Unit 5 (68 sq. m / 731 sq. ft)
(GF front new)
" " 0 0 0 10,965 10,965 10,965 10,965 10,965 10,965
Unit 6 (62.68 sq. m / 674 sq.
ft) (FF rear new)
Treat as void - utilisation
proxy
0 VOID VOID VOID VOID VOID VOID VOID VOID
Recovery of sub-metred
electricity
50% of costs subject to
incubator occupancy 
2,015 9,436 15,000 15,000 15,000 15,000 15,000 15,000
MICM Hub
Desks
Desk 1 (innovation provider -
TBC)
£2,500 pa 0 2,500 2,500 2,500 2,500 2,500 2,500 2,500 2,500
Desk 2 (innovation provider -
TBC)
£2,500 pa 0 2,500 2,500 2,500 2,500 2,500 2,500 2,500 2,500
Desk 3 (innovation provider -
TBC)
£2,500 pa 0 0 2,500 2,500 2,500 2,500 2,500 2,500 2,500
Desk 4 (Private Sector
Project / Hot Desk)
£4,000 pa 0 0 4,000 4,000 4,000 4,000 4,000 4,000 4,000
Desk 5 (Private Sector
Project / Hot Desk)
£4,000 pa 0 0 0 4,000 4,000 4,000 4,000 4,000 4,000
Desk 6 (ASSUME VOID) Treat as void - utilisation
proxy
0 VOID VOID VOID VOID VOID VOID VOID VOID
MICM Hub
Meeting
Room
Income from hire of meeting
room
£500/month (TBC) 0 2,000 4,000 6,000 6,000 6,000 6,000 6,000 6,000
MICM Grow-
on space
Unit 1 (152 sq.m / 1635 sq ft) Assume £9psf pa, based
on a 2-3 year lease
0 0 0 0 14,715 14,715 14,715 14,715 14,715
Unit 2 (154 sq.m / 1,657 sq.
ft)
Assume £9psf pa, based
on a 2-3 year lease
0 0 0 0 0 14,913 14,913 14,913 14,913
Unit 3 (154 sq.m / 1,657 sq.
ft)
Assume £9psf pa, based
on a 2-3 year lease
0 0 0 0 0 0 14,913 14,913 14,913
Unit 4 (250 sq. m / 2,690 sq
ft)
Assume £9psf pa, based
on a 2-3 year lease
0 0 0 0 0 0 0 24,210 24,210
Unit 1-3 core area (83 sq. m
/ 893 sq. ft) cost recovery /
service charge
Assume £9psf pa, based
on a 2-3 year lease        
1,720 3,464 5,207 8,037 8,037
MICM Events Events income from co-
production / sponsorships
Assume one a month
with £1k sponsorship per
event once MICM fully
established 
0 0 5,000 6,000 9,000 9,000 9,000 12,000 12,000
Paid-for Project income from 5 projects per annum at 0 0 12,500 20,000 30,000 35,000 50,000 50,000 50,000
Page 163

Page 164

Page 84 of 208 
Category Item Assumptions 2023/24 2024/25 2025/26 2026/27 2027/28 2028/29 2029/30 2030/31 2031/32
services productivity/net zero service
delivery - medium SMEs @
£15,000 pa
full operation
Project income from
productivity/net zero service
delivery - small SMEs @
£7,500 pa
10 projects per annum at
full operation
0 0 12,500 20,000 30,000 35,000 50,000 50,000 50,000
Project income from
productivity/net zero service
delivery - micro SMEs @
£2,500 pa
15 projects per annum at
full operation
0 0 9,375 15,000 22,500 26,250 37,500 37,500 37,500
Misc income Future project-related
income streams as MICM
reaches full potential to
support delivery of
manufacturing innovation
and net zero activity (e.g.
Scope 3 emissions
reduction)
e.g. from OEMs of
manufacturing / process
control / robotics
equipment
0 0 20,000 30,000 40,000 50,000 50,000 50,000 50,000
Total income from delivery, constant
2023/24prices, excluding inflation 
0 20,929 112,203 171,840 228,775 269,182 327,088 357,128 357,128
Cumulative inflation allowance on income
from 2024/25 onwards
Assumes 5% in 2024/5,
3% for 2025/6 then 2.5%
thereafter
1.00 1.05 1.09 1.12 1.15 1.18 1.21 1.24 1.27
Total income from delivery, including
inflation 
0 21,975 122,526 192,341 262,470 316,548 394,260 441,231 452,262
Net surplus/deficit pa 2023/24 prices
(excluding inflation)
Negative is surplus of
income over
expenditure
47,388  294,451  253,135  227,556  132,120  91,714  83,308  3,768  -15,482 
Net surplus/deficit pa including inflation Negative is surplus of
income over
expenditure
47,388  309,173  276,423  254,703  151,580  107,853  100,416  4,655  -19,607 
Page 164

Page 165

Page 85 of 208 
As discussed in the Commercial Case, there are clear interdependencies between
the capital model (which creates lettable assets to generate an income stream) and
revenue funding to help stand the project up in its initial phase, while income streams
develop to their full potential.
Importance sources of income for MICM include the following:
• Rental income from incubator units in the MICM Hub and the MICM Grow-on
units
• Rent of other desk spaces by service providers and the private sector in the
MICM Hub
• Paid-for services to manufacturing SMEs.
As the revenue model shows, these will take time to develop.  An allowance has also
been made for voids in the incubator units and desk spaces.
The detailed expenditure and income lines in the model are in 2023/24 prices.  An
inflation allowance has then been added to assess the overall annual performance in
income and expenditure terms.  These inflation allowances are 5% for 2024/25, 3%
for 2025/26 and 2.5% thereafter.
Overall affordability
The tables above demonstrate the financial sustainability of the proposed project.
The capital funding requirements from Scottish Government and UK Government
through the Moray Growth Deal are lower than forecast at OBC stage.  The current
forecast is that the revenue grant of £1.25m will still need to be drawn down in full.
Approval to HIE’s contribution to MICM will be sought at HIE’s Board meeting on 31st
October.
Impact of sensitivity testing on revenue model
The same revenue sensitivity tests which were used to assess the resilience of the
project in Value for Money terms have been applied to the revenue model in cash
terms (with inflation) in the Financial Case.  The sensitivity tests are:
• Scenario 1: Impaired financial performance: Incubator and grow-on space
rents and paid-for service income are assumed to be 10% lower than forecast
from day 1
• Scenario 2: Reasonable worst-case scenario: Total Incubator and grow-on
space rents and paid-for service income are assumed to be 20% lower than
forecast from day 1.
The base case financial revenue performance of Option 2 is compared with the
results of these two sensitivity tests in Table 5.6 on the following page.  
Page 165

Page 166

Page 86 of 208 
Table 5.6: Sensitivity analysis of Option 2 revenue model: revenue deficit (surplus)
including inflation (2023/24 to 2032/33)
Financial Year
Base case expenditure
minus income in year
(negative is surplus)
Sensitivity Scenario 1 Sensitivity Scenario 2
2023/24 47,388 47,388 47,388
2024/25 309,173 310,424 311,675
2025/26 276,423 283,223 290,022
2026/27 254,703 265,822 276,941
2027/28 151,580 168,017 184,455
2028/29 107,853 128,277 148,701
2029/30 100,416 128,331 156,246
2030/31 4,655 36,608 68,562
2031/32 -19,607 13,146 45,898
2032/33 -20,097 13,474 47,045
The Economic Case demonstrated that the project would remain good value for
money under both scenarios – subject to funding.  Reviewing this again in the
Financial Case through the specific lens of the revenue model demonstrates that the
revenue position of MICM is finely balanced, relying heavily on successful letting and
paid-for services delivery to break-even by year 10.  This is prominent in the key
performance indicators (KPIs) presented in the Management Case.
Page 166

Page 167

Page 87 of 208 
6. The Management Case 
Programme management arrangements
The project is an integral part of the Moray Growth Deal (MGD) programme, which
comprises a portfolio of projects for the delivery of economic growth to the Moray
region.  The current MGD programme governance arrangements is shown below. 
As discussed in the Commercial Case, HIE and UHI Moray have agreed that there
will be monthly management team meetings between MICM, MAATIC and the BE
Hub projects to provide oversight and co-ordination of all three innovation projects. 
This will help to ensure efficiency in their design and delivery and maximise the
synergies from a highly co-ordinated delivery.
Project management arrangements
Project reporting structure
HIE as owner of the project will continue to report to the Moray Growth Deal
Programme Board on project delivery on a regular basis, following agreed
procedures which will also include output monitoring as required alongside capital
and revenue funding claims.
HIE’s MICM project team or service contractor (depending on the final service
delivery solution) will, in turn, be charged with responsibility for reporting to the MICM
Project Board on a regular basis with financial and output reporting on the project
performance.
It is intended that the MICM Project Board will continue in its present form for the
duration of the Growth Deal phase of MICM.  Membership of the Project Board and
its Terms of Reference will be formally reviewed and agreed on an annual basis.
Project roles and responsibilities
Page 167

Page 168

Page 88 of 208 
The Senior Responsible Owner for the project will continue to be the Area Manager
for Moray at Highlands & Islands Enterprise.  The SRO will continue to be supported
by a project team comprising the Head of Regional Development in HIE’s Moray
Team, HIE’s Property, Procurement and Facilities Management Teams.
HIE’s Property Team will procure and have oversight of the MICM Hub design,
tendering and capital works.  HIE’s Procurement Team will support that process as
well as the procurement of the Contract for Services (should that be identified as the
preferred delivery solution).  HIE’s Facilities Management Team will take over
responsibility for hard maintenance of both the MICM Hub and MICM Grow-on space
once they have been handed over by the contractors.
Project plan
A Project Plan for MICM is provided below, covering the initial period up to the MICM
Hub and Service Contract becoming operational as well as showing the anticipated
timing of the MICM Grow-on space.  The plan focuses on the steps needed to reach
practical completion of the build, as well as the specification of the Contract for
Services which will be critical to benefits realisation in the longer term.
Table 6.1: Project Plan, incorporating a Benefits Realisation Plan
Action summary Action detail Owner Deadline
1. STRATEGIC DIRECTION, GOVERNANCE AND MANAGEMENT
1.1 Governance
arrangements
Delivery continues through HIE and its
established governance and management
arrangements, including the MICM Project Board
SRO Ongoing
Subject to performance, and following the interim
evaluation (see below) HIE and the MICM Project
Board review governance arrangements with a
view to MICM becoming a standalone entity by
the end of the Growth Deal period
SRO Ongoing from
2026/27
Expected establishment of standalone entity SRO Prior to end of
Growth Deal period
1.2 Strategic
direction and key
Gateways
MICM Project Board approve submission of FBC
to MGD Programme Board
MICM Project Board By 16th August
2023
MGD Programme Board approve FBC MGD Programme
Board
25th August
HIE approve project (Gateway 3 local approval)
with decision on preferred service delivery
solution at next available Board meeting
SRO 31st October 2023
Approval of FBC by Scottish Government and UK
Governments (Gateway 3 national approval)
SG/UKG November 2023
Finalise detailed KPIs once service delivery
solution has been agreed
MICM Project Board Autumn 2023
MICM service solution - readiness for service
Gateway 4 review
MICM Project Board Spring 2024
2. CAPITAL WORKS DELIVERY
2.1 MICM Hub
Design
Finalise detailed design for capital works, through
HIE-appointed design team
SRO 
(sign off by MICM
Project Board)
November 2023
(MICM Hub)
2026/27
(MICM Grow-on
space)
2.3 MICM Hub
Planning
Secure Building Warrant for MICM Hub/Unit 9 HIE Property Team December 2023
2.4 MICM Hub
Procurement
Tender for capital works via agreed procurement
mechanisms
HIE Property Team
(sign-off by MICM
Project Board, HIE,
and MGD Board)
January 2024
Page 168

Page 169

Page 89 of 208 
Action summary Action detail Owner Deadline
2.5 MICM Hub
Reconfiguration
Complete capital works HIE Property Team By Autumn 2024
2.6 MICM Grow-on Design, planning and procurement of MICM
Grow-on space (subject to interim evaluation)
SRO 2026/27-2027/28
3. REVENUE SERVICE DELIVERY (TWO OPTIONS)
3.1 Preferred
service delivery
solution
Decision on preferred service delivery solution SRO September 2023
Service delivery via fixed term Project Team within HIE
3.A.2 Project
initiation
Follow established HIE procedures to set MICM
up as a project
SRO February 2024
3.A.3 MICM
Director
recruitment
Prepare job and person specification for MICM
Director (in first instance, other staff to follow later
in 2024)
SRO February 2024
3.A.4 MICM
Delivery
Delivery of MICM services in line with FBC
Commercial Case
SRO Initial period to Q3
2027/28 (4 years)
Service delivery via outsourced Contract for Services
3.B.1
Procurement of
Contract for
Services
Build on FBC Commercial Case to prepare scope
and specification for Contract for Services,
including soft market testing
SRO November 2023
Finalise Specification of Requirements for
Contract for Services
MICM Project Board December 2023
Procurement process for Contract for Services SRO January 2024 
Contract award MICM Project Board April 2024
Delivery of MICM services in line with FBC
Commercial Case and final agreed specification
SRO Initial contract
2024/25 to 2028/29
(initial 3+1
contract)
4. MONITORING AND EVALUATION
3.1 Monitoring
arrangements
Finalise KPIs  SRO November 2023
Ongoing performance monitoring to Project
Board, MGD Programme Director and MGD
Board (Gateway 5 reviews) in line with MGD
reporting requirements
MICM Project Board Ongoing, in line
with MGD reporting
requirements
3.2 Interim
evaluation
An interim review and evaluation of the
performance of the MICM Hub and MICM service,
identifying what is working well and less well and
informing a decision around future delivery
(Gateway 0 Strategic Assessment)
MICM Project Board 2026/27
(commission 1st
April 2026 and
report by June
2026)
3.3 Impact
evaluation
A follow-up evaluation focused on impacts and to
review progress since the interim evaluation
(Gateway 0 Strategic Assessment)
MICM Project Board 2029/30
Use of special advisors
Special advisors have been and will continue to be used in a timely and cost-
effective manner in accordance with the Treasury Guidance.
During the FBC process Torrance Partnership have provided cost and procurement
advice.  Colin Warnock Associates (CWA) was commissioned to prepare the OBC
and FBC.  Graham and Sibbald (G&S) have been commissioned by HIE to
undertake detailed design work on Unit 9, progressing planning to building warrant
and tender pack.  Their work also includes carbon assessments. Torrance
Partnership will support the procurement and project management process on behalf
of HIE’s Property Team.
Page 169

Page 170

Page 90 of 208 
Beyond the project development stage, the MICM Project Board will both provide,
and have access to, the special advisors as shown in Table 6.2 on the following
page.
Page 170

Page 171

Page 91 of 208 
Table 6.2: MICM special advisors in the delivery phase
Project Board representatives Type of Advisor
HIE Subject Matter Expert
SMAS Subject Matter Expert
NMIS Subject Matter Expert
UHI Subject Matter Expert
Scottish Government – Advanced Manufacturing Team Subject Matter Expert
Private sector representatives Users
Supported by
MICM Project Team / Outsourced Service Contractor Supplier
HIE Procurement, Property, Facilities, Finance, Subsidy, Legal Teams Subject Matter Experts 
Arrangements for change and contract management
HIE’s Property and Procurement Teams will be directly responsible for procurement
of the capital works. HIE’s Property Team will then manage those contracts
HIE’s Moray Area Team will work with HIE’s Procurement Team to procure the
Contract for Services for MICM.  This work will include the specification of
requirements as well as the arrangements for contract management.
Change control procedures for the MICM Project Board will be developed in close
co-operation with the Moray Growth Deal Partnership to ensure that these fit with
broader programme management and partner change control requirements.
Arrangements for benefits realisation
As project SRO, HIE’s Moray Area Manager will have lead responsibility for Benefits
Realisation.  The initial Action Plan provided at Table 6.1 above identifies the key
steps which are needed in the short term (between FBC and procurement) to further
develop the project to maximise its potential to deliver the benefits identified in this
FBC.  It also identifies key milestones on the project’s critical path for delivery. As
with the risk register, the Action Plan is now regarded as a live document, owned by
the SRO and will be regularly reviewed with the Project Board once it is established.
MICM will adopt the output delivery targets shown in Table 6.3.  In addition, MICM
will monitor outcomes for those busineses engaged receiving MICM advice or
support in terms of their R&D expenditure, turnover, employment and productivity.
The latter will not be expressed as formal targets as performance will vary according
to the specific baseline, needs and opportunities in each business.  However, it is
essential that these data are recorded and regularly updated (in a GDPR-compliant
manner, in line with HIE’s existing output monitoring arrangements) to help MICM
understand its progress and inform future impact evaluation activity.
Page 171

Page 172

Page 92 of 208 
Table 6.3: Output delivery targets for MICM
Output target Data source /
measurement
Cumulative
target by
31st March
2025
Cumulative
target by
31st March
2027
Cumulative
target by
December 2031
Number of MICM supported events
delivered
MICM monitoring 12 40 80
Number of unique business
attendees at MICM events
MICM monitoring 30 50 100
Number of unique businesses
receiving innovation advice (up to 3
days)
MICM monitoring 5 40 75
Number of unique busineses
receiving innovation project support
(more than 3 days or paid-for
service)
MICM monitoring 0 20 50
Number of new business start-ups MICM monitoring 0 3 8
Number of inward investment jobs
(FTEs) attracted
MICM monitoring 0 10 20
Number of businesses supported
with net zero transition
MICM monitoring 5 30 80 
Monitoring arrangements will include annual surveys of SMEs using MICM services
as well as the wider manufacturing base.  They will also include the specific outputs
above as well as additional service delivery KPIs and requirements for monitoring in
line with the Equalities Impact and Fairer Scotland Duty Impact Assessments
provided at Appendix 9.  Proposals for Evaluation are made below.
A draft set of KPIs is provided at Table 6.4.  These will be refined to ensure
alignment with the preferred revenue service delivery option.
Table 6.4: Draft KPIs to be developed in the Contract for Services for MICM
Broad KPI heading Detailed measure to be developed and quantified in the contract
Website and promotion MICM promotional strategy in place by June 2024 and website by September
2024 in time for MICM hard launch
Events
Minimum of 6 relevant, well-targeted and promoted events in 2024/25 and then
minimum of 12 events per annum thereafter.  KPIs will also be developed for
response times, booking management and event feedback processes
Engagement with
manufacturing SMEs
on innovation and net
zero
Advisory services (up to 3 days) provided to 5 unique businesses in 2024/25, 20
businesses in 2025/26, 40 businesses in 2026/27, 50 businesses in 2027/28, 60
businesses in 2028/29 and 75 businesses in 2029/30
Paid-for services with
micro SMEs
Service delivery to commence no later than 2025/26 and build to 15 projects per
annum by 2026/27 generating paid-for service income in line with revenue
model
Paid-for services with
small SMEs
Service delivery to commence no later than 2025/26 and build to 10 projects per
annum by 2026/27 generating paid-for service income in line with revenue
model
Paid-for services with
medium sized SMEs
Service delivery to commence no later than 2025/26 and build to 5 projects per
annum by 2026/27 generating paid-for service income in line with revenue
model
Incubator unit
occupancy
Minimum occupancy level of 80% by 2026/27 at target rents and strive for 100%
occupancy
Page 172

Page 173

Page 93 of 208 
Grow-on unit
occupancy
Occupancy of 1 Grow-on unit at target rent by 2027/28, 2 units by 2028/29, 3
units by 2029/30 and 4 units by 2030/31
Desk unit occupancy Rental of 2 desk spaces at target rents by 2024/25, 4 by 2025/26 and minimum
of 5 by 2026/27, striving for all 6 to be let at all times.
Meeting room hire Promotion and management of meeting room hire to achieve monthly revenue
target
Tenant management Full range of KPIs to be developed, covering response times, inductions, leasing
information, lease reviews
Customer satisfaction
rate
80% of MICM services users satisfied or very satisfied with MICM services (on a
five point scale of very dissatisfied, dissatisfied, neither/nor, satisfied, very
satisfied).  A KPI will also be included for customer complaints handling.
Managed Services Full statutory compliance in respect of all managed services, e.g. Health &
Safety, Fire & Environmental Regulations
Management of Service
Contracts
A range of KPIs will be developed covering compliance with statutory
requirements, reporting of repairs/defects, reviewing service contracts to ensure
best value for money and accurate record keeping
Factoring services
A range of KPIs will be developed covering invoicing for tenants, desk spaces,
meeting room hire and paid for services; for the effective operation of the MICM
Bank Account; and for debt recovery
Reporting
A range of KPIs will be developed covering reporting arrangements (including
for the KPIS above) to the SRO and to the MICM Project Board and the form
and due dates for each
Arrangements for the carbon management process
Graham and Sibbald have prepared the high level capital and operational carbon
assessments included in the FBC and will prepare a formal Whole Life Carbon
Assessment at RIBA Stage 4 as part of the detailed design process. During the
detailed design process, consideration will be given to the mitigation of capital
carbon through the application of RICS and other best practice. A detailed
assessment will also be made of the operational carbon performance of Unit 9,
post-reconfiguration, as well as the grow-on space at Unit 10 and adjacent new build
in due course.
Arrangements for risk management
A risk register for MICM is provided at Appendix 6.  This is a live document owned by
the SRO and will be reviewed at MICM Project Board meetings.  Responsibilities for
management of these risks are set out in the register.
Arrangements for post project evaluation
The revenue budget for the MICM project includes provision for the following:
• Annual performance reporting, which will include survey work amongst
business beneficiaries, starting from 2024/25 (once MICM becomes
operational);
• An interim (formative) evaluation, anticipated early in 2026/27, two years into
the project. This wide-ranging review will look at project performance up to that
point, identify what is working well and less well and make recommendations
for adjustment to the project’s direction. This evaluation will also make
recommendations for future delivery.  The interim evaluation will also inform the
Page 173

Page 174

Page 94 of 208 
design of any grow-on space, in terms of demonstrating a need for their
provision at that time, and advising on matters such as unit size;
• An impact evaluation, anticipated in 2029/30, approximately five years into the
project.  This will include a formative element, looking back at how the project
has responded to recommendations made in the interim evaluation, but will
seek to establish a full quantitative assessment of the benefits of all of the
various dimensions of the project, including its impact on indigenous
manufacturing businesses, its impact on new manufacturing start-ups (via the
incubator) and early evidence on their acceleration (through grow-on space)
and its impact on inward investment.  It is also expected that the 2029/30
evaluation will include a formative element supporting the review of governance
arrangements including the feasibility of a standalone entity;
• Both evaluations will inform Gateway Reviews for the project (see below and
Action Plan above) and it is expected that they will make clear
recommendations for adjustment to the MICM delivery strategy to optimise
benefits.
Gateway review and internal audit arrangements
The following Gateway reviews will be undertaken:
• Gateway 3 “Investment Decision” reviews will form part of the FBC approval
process;
• A Gateway 4 “Readiness for Service” review will be undertaken towards the
end of the construction process and prior to going live;
• A Gateway 5 “Operational Review and Benefits Realisation” review will be
undertaken once the project is live;
• The interim and impact evaluations will be used to support Gateway 0 Strategic
Assessment reviews.
In addition to Gateway Reviews, MICM will also be the subject of regular in-life
reviews by the Moray Growth Deal Board in line with MGD’s assurance procedures. 
Internal HIE audits of project performance (expected to be every two years) will also
be undertaken in line with HIE’s own project governance arrangements.  The specific
approach will depend on whether the MICM is projectised within HIE or delivered
through an outsourced Contract for Services.
Contingency plans
In relation to capital works, cost estimates prepared by Torrance Partnership include
a works contingency budget of 5% for Unit 9 and Unit 10 and the new build grow-on
space.  HIE has allowed a further 10% contingency on the Unit 9 capital costs to
reflect that the detailed design for these works has not yet completed.
In relation to revenue services, the revenue model includes a 10% contingency on all
revenue costs.
Page 174

Page 175

Page 95 of 208 
These contingency estimates will be reviewed as the detailed design work
progresses.
Utilisation of final contingency budgets during project delivery will be subject to
rigorous change control procedures, as outlined above.
The phased development of the project and the commissioning of formal
evaluations, in addition to ongoing performance management by the SRO and
Project Board, will provide HIE with the opportunity to review performance and
assess whether an alternative direction needs to be taken at key points during the
Growth Deal period.
Communications plan
A communications plan will be developed following the outcome of the final approval
processes agreed for MICM.  This will be aligned with broader Moray Growth Deal,
HIE and Moray Council communication planning and any announcements regarding
approval of the MICM FBC will be co-ordinated with the Moray Growth Deal
Programme Director.  The promotional strategy for MICM will also be agreed with the
Moray Growth Deal.
MICM operating model transition
Figure 6.1 on the following page shows how it is anticipated that the MICM operating
model will transition over the lifetime of the Growth Deal Programme and beyond.
Until the end of the Growth Deal period MICM will be managed as a HIE project,
governed by a Project Board and with the HIE Area Manager as SRO.
As MICM builds up its revenue streams and approaches self-sufficiency, HIE will
work with the MICM Project Board and MICM Director on a transition plan that will
lead to MICM becoming a standalone entity by 31st March 2031. As part of that
process, the current working assumption is that HIE will facilitate the transfer of
assets to the standalone entity.
As noted above, it is expected that the impact evaluation of MICM in 2029/30 will
actively explore the feasibility of a standalone entity and support HIE and the MICM
Project Board in assessing options.  Engagement will be sought with the Moray
Growth Deal Partnership Board and Scottish and UK Government stakeholders at
the appropriate time to ensure full compliance with Growth Deal grant terms and
conditions. 
Page 175

Page 176

Page 96 of 208 
Figure 6.1:  MICM operating model transition 
B
Page 176

Page 177

Page 97 of 208  Page 177

Page 178

Page 98 of 208 
Appendices 
1 SOC and OBC options development
2 Economic Impact Assessment method and detailed results
3 Logic Model
4 Optimism Bias Assessment
5 Carbon Categorisation Form
6 Risk register
7 Capital works - cost estimates
8 Capital works – contract template
9 Equalities Impact and Fairer Scotland Duty Impact Assessment
10 HIE Equality and Diversity Policy
11 Carbon assessments 
Page 178

Page 179

Page 99 of 208 
Appendix 1: SOC and OBC options development
STRATEGIC OUTLINE CASE (SOC) OPTIONS DEVELOPMENT
Scope options
The following main intervention options were considered at SOC stage in relation to
project scope:
• Option 2 – the ‘minimum’ scope – Draw in resource from elsewhere but no
physical presence
• Option 3 – the ‘intermediate’ scope – Establish formal links to NMIS and one
project post based in Moray
• Option 4 – the ‘intermediate-plus’ scope – Sharp focus on SMEs, with
purposeful links to national resources such as catapults and NMIS. Facilities
and staff to execute business-led projects
• Option 5 - ‘maximum’ scope – Bespoke large facility, with academic staff and
project staff.
The table below summarises the assessment of each option against the investment
objectives and CSFs. 
Page 179

Page 180

Page 100 of 208 
Service solution options
Against the preferred scope from above; the table and narrative below summarises
the assessment of each option for service solution against the investment objectives
and CSFs. 
Service delivery options
This range of options considered the options for service delivery in relation to the
preferred scope and potential solution. The table below summarises the assessment
of each option against the investment objectives and CSFs.
Page 180

Page 181

Page 101 of 208 
Implementation options
This range of options considers the choices for implementation in relation to the
preferred scope, solution and method of service delivery. The table below
summarises the assessment of each option against the investment objectives and
critical success factors. 
Funding options
This range of options considers the choices for funding and financing in relation to
the preferred scope, solution, method of service delivery and implementation. The
table below summarises the assessment of each option against the investment
objectives and critical success factors.
Page 181

Page 182

Page 102 of 208 
Short-listed options (at SOC stage)
The ‘preferred’ and ‘possible’ options identified were taken as the starting point for
the short list for detailed appraisal within the OBC.  Section 3 (Economic Case)
explains how these were evolved further.
EVOLUTION OF OPTIONS AT OUTLINE BUSINESS CASE (OBC) STAGE 
Five options were short-listed for more detailed appraisal in the OBC.  In addition to
the Business as Usual Reference Case (Option 1), four intervention options were
explored in detail:
• Option 2: A Virtual Manufacturing Innovation Hub, strengthening the co-
ordination of existing service delivery and acting as a hub for signposting of
support and events organisation targeted at manufacturing businesses;
• Option 3: A standalone Manufacturing Innovation Centre in Forres - The
construction of a new Manufacturing Innovation Centre for Moray on the Forres
Enterprise Park, providing a physical base for the co-ordination activities
delivered in Option 1, including desks for HIE, SMAS and Interface, and with
the additional provision of incubator units to encourage the start-up of new
manufacturing businesses;
• Option 4: Co-location of MICM within the Moray Aerospace, Advanced
Technology and Innovation Campus (MAATIC), which is being developed
in conjunction with Boeing adjacent to the £3bn Poseidon investment at
RAF Lossiemouth – offering direct access for MICM beneficiaries to UHI’s
Advanced Technologies Institute and Aviation Academy as well as an essential
shared space for networking and events in MAATIC’s Atrium;
Page 182

Page 183

Page 103 of 208 
• Option 5: Co-location of MICM and grow-on units within the Moray
Aerospace, Advanced Technology and Innovation Campus (MAATIC) at
Lossiemouth – with all of the benefits of Option 4, and in addition providing
grow-on space, on flexible terms, for companies graduating from the incubation
centre as well as potential inward investors.
The OBC options analysis demonstrated that a physical innovation centre offered
clear advantages to a virtual hub approach and it identified Option 5 as the preferred
option. 
Page 183

Page 184

Page 104 of 208 
Appendix 2: Economic Impact Assessment
OVERVIEW 
Table EIA.1 sets out the principal components of the economic impact assessment prepared
by Colin Warnock Associates, including the indicators used, the valuation approaches
adopted and the spatial levels for which results have been produced.  Except for temporary
construction effects, all these benefit types have been included in the Benefit Cost Ratio. 
Table EIA.1: components of the EIA
Phase Type of benefit /
disbenefit
Indicator
specification
Valuation Duration Geography In
BCR?
CONSTRUCTION
Construction jobs Net additional
construction job
years
Income
and GVA
Temporary,
one-off
Moray,
H&Is,
Scotland,
UK
No
Capital carbon
(part of “Whole
Life Carbon” /
“Carbon
Emissions
Impact”)
“Capital carbon” (i.e.,
net additional tonnes
CO2) embodied in
construction
materials 
Value of
tonnes
CO2
Temporary,
one-off
UK Yes
OPERATIONAL
Jobs at MICM MICM service staff
and net additional
direct (operational)
jobs in MICM Hub
incubator tenants
Income
and GVA
10, 15 and
25 year
snapshots
Moray,
H&Is,
Scotland,
UK
Yes
(GVA)
Operational
carbon (part of
“Whole Life
Carbon” / “Carbon
Emissions
Impact”)
Operational
(floorspace): net
additional direct
tonnes CO2 impact of
MICM Hub and
MICM Grow-on
space
Value of
tonnes
CO2
10, 15 and
25 year
snapshots
Moray,
H&Is,
Scotland,
UK
Yes
CATALYTIC
Indigenous
business growth
and productivity
improvements
Catalytic: net
additional jobs,
income and GVA
from growth in
businesses through
MICM support
Income
and GVA
10, 15 and
25 year
snapshots
Moray,
H&Is,
Scotland,
UK
Yes
(GVA)
Businesses
graduating from
the MICM
incubator
Catalytic: net
additional jobs,
income and GVA
from graduation,
survival, and growth
of businesses from
the MICM incubator
Income
and GVA
10, 15 and
25 year
snapshots
Moray,
H&Is,
Scotland,
UK
Yes
(GVA)
Inward investment
jobs attracted to
Moray by MICM
Catalytic: inward
investment jobs
Income
and GVA
10, 15 and
25 year
snapshots
Moray,
H&Is,
Scotland,
UK
Yes
(GVA)
Page 184

Page 185

Page 105 of 208 
CONSTRUCTION IMPACTS 
Construction job years 
The approach used to estimate construction employment is in line with HIE’s standard
economic impact assessment methodology and begins by utilising the Scottish Input-Output
Tables to translate construction expenditure into employment, income and GVA. 
To the extent that all the capital expenditure is considered additional, all these employment
effects are regarded as 100% gross additional. 
Utilisation of Type I and Type II multipliers using the Scottish Input-Output Tables and UK-
level Type I multipliers for the UK has enabled estimates to be made of the associated
income and GVA impacts of these jobs at the Moray, Highlands & Islands, Scotland, and UK
levels. The model assumes that the Moray share of the Scottish Type I (supply chain)
multiplier is 30%, that the Highlands and Islands share is 50% and that UK multiplier is 125%
of the Scottish multiplier.  For the induced (wages and salaries) effect within the Type II
multiplier, the model assumes a Moray share of 25%, a Highlands and Islands share of 40%,
and that the UK multiplier is 120% of the Scottish multiplier. 
While construction impacts are included for completeness, they are excluded from the
Benefit Cost Ratio and Net Present Social Value calculations given their temporary nature, in
line with guidance provided by OCEA at the OBC stage. 
Capital carbon / embodied carbon 
Capital carbon has been estimated by Graham and Sibbald for the MICM Hub element of
Option 2 (re-use of Unit 9) and Option 3 (new build) as part of the FBC process.  Their
approach and results can be found in Appendix 11 and the output of their work was capital
carbon expressed as tonnes or tonnes per sq. m. 
For the grow-on space component in Option 2, capital carbon tonnes per sq. m associated
with the refurbishment of Unit 9 was applied to the reconfiguration works for the grow-on
space at Unit 10.  This was then added to the capital carbon estimated for the 250 sq. m of
new build grow-on space in Option 2.  The latter was derived using the same ready-reckoner
for capital carbon tonnes per sq. m of new build floorspace provided by Graham and Sibbald
in Appendix 11.  In Option 3, where all of the grow-on space is new build, the new build
ready-reckoner was applied to the total new build grow-on floorspace being provided in that
option. 
These calculations provided total tonnes of capital carbon in each option.  The level of
capital carbon is very low in Option 2 and higher in Option 3 because of the different levels
and types of construction activity involved in each option. 
The application of these results in the FBC economic impact model involved profiling the
consumption of capital carbon over time using the capital expenditure cashflow as a proxy
so that the BEIS34 central carbon prices (November 2022 update) could then be applied
each year. 
34 https://www.gov.uk/government/publications/valuation-of-energy-use-and-greenhouse-gas-emissions-for-appraisal
Page 185

Page 186

Page 106 of 208 
The future annual profile of the value of capital carbon from 2024/25 onwards was then
discounted to 2023/24 (year 0, the year of appraisal) at a discount rate of 3.5%, HM
Treasury’s Social Time Preference Rate to yield a Present Value of Capital Carbon per
option, expressed as a one-off disbenefit. 
OPERATIONAL IMPACTS 
Jobs at MICM and associated income and GVA 
Delivery of the MICM service is forecast to require 2.5 net additional FTEs (before multiplier
effects). 
In addition, jobs will be accommodated through the occupancy of incubator floorspace at the
MICM Hub.  The quantum of incubator space is set out in the Commercial Case and the
occupancy build-up and void assumptions are shown in the revenue model in the Financial
Case.  The approach has been to apply a cautious employment density of 25 sq. m per job
to occupied incubator space, based on the Homes and Communities Agency’s 2016
Employment Densities Guidance.  This generates approximately 11 FTEs once five of the
six incubator units are occupied. 
Sectoral data for 2020 from the Scottish Annual Business Survey (SABS) was used to
generate turnover, GVA and income associated with these jobs. 
For the MICM staff, the following sector data was used: 
• SIC Divisions 69-75 Professional, Scientific and Technical Activities, was applied to
the MICM Director and MICM Manager
• SIC Division 77-82 Administrative and support service activities, was applied to the
part-time MICM Administrator position. 
For the incubator jobs, a weighted average was taken of the following manufacturing
sectors: 
• SIC Divisions 10, 11, 12 Manufacture of Food, Beverages, and Tobacco Products
• SIC Divisions 16, 17, 18 Manufacture of Wood, Paper, and Printing Products
• SIC Divisions 24, 25, 28, 29, 30 Manufacture of Basic and Fabricated metals,
Machinery, Motor Vehicles and Other transport equipment. 
Using the GDP deflator (ONS June 2023 release), these 2020 SABS estimates of GVA and
income per job were inflated to 2023/24 prices. 
The same assumptions were made to both intervention options since the operating model for
MICM is assumed to be identical between the two different capital options. 
The following additionality assumptions were then applied: 
• Deadweight – it assumed that none of the benefits of MICM would occur under the
Option 1 do nothing / reference case option.  Deadweight is therefore assumed to be
0% in both Option 2 and Option 3.
• Displacement – product market displacement arising from competition by business
beneficiaries of MICM at the different geographies described above.  This was based
Page 186

Page 187

Page 107 of 208 
on the response to a question in the FBC business survey which asked, “if your
business was to cease trading tomorrow, what proportion of your turnover (by value)
would be taken by competitors located elsewhere in Moray, elsewhere in the
Highlands and Islands, elsewhere in Scotland and elsewhere in the UK.”  The
displacement adjustment, shown in Table EIA.2 below, was applied to both
intervention options.
• Labour market substitution – unlike displacement and leakage, there is no primary
evidence which would support a specific substitution assumption for MICM.  However,
insofar as the proposal does not offer any public sector subsidy to firms, the level of
poaching of staff stimulated by MICM is regarded to be relatively low.  Nevertheless, a
cautious approach has been adopted.  The mean rate of substitution in the BIS
Additionality Guidance35 is 2.8% for individual enterprise support at the sub-regional
level, so we have applied 3% in the EIA model for Moray and 5% for all the other
spatial levels of analysis.  These assumptions were applied to both intervention
options.
• Leakage – the proportion of jobs taken by residents living outside each level of
geography.  The business survey asked where employees live, and these results were
used to calibrate the leakage assumption (see Table EIA.2 below).  Again, the same
assumptions were applied to both intervention options.
• Multipliers –both indirect (through the business supply chain) and induced (spending
of wages and salaries of those employed directly and indirectly) using the sectoral
mixes discussed above and drawing on the Scottish Input-Output Tables for those
sectors.  The same assumptions were applied to both intervention options.  The
shares of the Scottish multipliers used at each level of geography can be found in
Table EIA.2.
Table EIA.2 sets out the full range of additionality assumptions applied to both intervention
Options. 
Table EIA.2: additionality assumptions – operational jobs 
Moray Highlands
and Islands Scotland United Kingdom
Deadweight 0% 0% 0% 0%
Product/Service Displacement 21% 25% 55% 88%
Labour Market Substitution 3% 5% 5% 5%
Leakage 20% 10% 0% 0%
Share of Scottish Type I multiplier 30% 50% 100% 125%
Share of Scottish induced multiplier
effect (Type II minus Type I) 25% 40% 100% 120%
Type I Multiplier applied 1.4 1.7 1.5 1.6
Type II Multiplier applied 1.6 2.0 1.7 2.0 
Applying all these assumptions generates a stream of future annual income and GVA
benefits from 2024/25 (Year 1) to 2048/49 (Year 25), before discounting back to Year 0 
35
https://assets.publishing.service.gov.uk/government/uploads/system/uploads/attachment_data/file/191512/Research_to_improve_the_
assessment_of_additionality.pdf
Page 187

Page 188

Page 108 of 208 
(2023/24) at 3.5%, the Social Time Preference Rate.  Profiles were created to provide
snapshots of total benefits generated by year 10, year 15 and year 25 at each of the four
geographies. 
Page 188

Page 189

Page 109 of 208 
Operational carbon 
Operational carbon has been estimated by Graham and Sibbald as part of the FBC process
for both intervention options.  The approach and results can be found in Appendix 11.  The
outputs of this work were tonnes of operational carbon per annum for the MICM Hub
element.  These were applied, on a per sq. m basis, to the grow-on space in both options to
generate a total operational carbon per annum expressed in tonnes. Operational carbon was
assumed to be the same across the two intervention options. 
The application of these results in the FBC economic impact model has involved profiling the
consumption of operational carbon over a 25 year period from 2023/24 to 2048/49 so that
correct BEIS36 carbon prices could then be applied each year. 
The annual profile of operational carbon values was then discounted to 2023/24 (year 0, the
year of appraisal) at a discount rate of 3.5%, HM Treasury’s Social Time Preference Rate to
yield a Present Value of future Operational Carbon per option.  Profiles were created to
provide snapshots of total benefits generated by year 10, year 15 and year 25. 
CATALYTIC IMPACTS 
Growth and productivity improvements in manufacturing SMEs resulting from MICM
advice and support 
SABS 2022 data shows that there are 215 manufacturing businesses in Moray.  Of these,
180 have 1-49 employees, 25 businesses have 50-249 employees and 15 have 250
employees or more.  Stakeholder discussions have established that only around 20% of the
total number of businesses (i.e., 40-45 businesses) are in receipt of innovation support.  In
line with the assumption made at OBC stage, and with the revenue model assumptions, the
FBC assumes that the additional profile, focus and dedicated support that will be offered
through MICM will enable a further 20% of businesses (43 businesses) to be provided with
innovation support which they would not otherwise have accessed without MICM. 
For the purposes of the EIA, the cautious assumption is made that the rate of engagement
will start at the 20% baseline and improve at a rate of 5% per annum over 10 years, capped
at 40% (i.e., an additional 43 firms) by 2033/34. 
Baseline performance has been assessed using 2022 SABS data for manufacturing firms in
Moray.  A performance impact from engaging with MICM is then applied.  The business
survey presented in the Strategic Case showed that businesses themselves would expect to
see some growth benefits from engaging with MICM.  The Strategic Case notes that: “over
50% of the businesses considered that the overall impact could be between 11-25% of their
2022 baseline sales, although a small percentage suggested it could be higher at between
26-50%. Around 30% considered it would be between 1-10%”. 
The following business growth assumptions are then assumed to be gross additional
because of MICM’s intervention: 
• The level of impact is a 12.5% one-off increase in the scale of the company’s turnover,
employment, GVA and income 
36 https://www.gov.uk/government/publications/valuation-of-energy-use-and-greenhouse-gas-emissions-for-appraisal
Page 189

Page 190

Page 110 of 208 
• The impact occurs 1 year after the intervention
• The one-off impact persists for a total of three years only. 
Applying the same manufacturing sector assumptions as for the incubator jobs and
associated GVA per FTE and income per FTE, and applying the same leakage,
displacement and multiplier assumptions, generates an annual profile of net additional
employment, income and GVA each year.  The income and GVA benefits were then
discounted to 2023/24 at 3.5% to generate Present Value catalytic income and GVA benefits
from the incubator. 
Businesses graduating from the MICM Hub incubator units 
The following assumptions were used: 
• Proportion of businesses graduating from the MICM incubator each year: 5% (source:
Oxford Innovation)
• Baseline employment of businesses at the point of graduation from the incubator: 2
FTEs
• Post-graduation annual growth rate of businesses: 1.1 FTEs per annum (source:
Oxford Innovation)
• Survival rates of graduating businesses starting at 100% in Years 1 and 2 and falling
to 45% by Year 8 (source: Oxford Innovation) and then 30% by Year 17 and beyond
(CWA assumption). 
For appraisal purposes, it is assumed that these businesses would not have started at MICM
nor graduated without MICM support, including the provision of grow-on space.  It is worth
highlighting that in order to avoid double counting, no benefits have been attributed to the
MICM Grow-on space because it is assumed that the same incubator graduates would
potentially expand into those units. 
Applying these assumptions generates a profile of surviving gross additional FTEs resulting
from incubator graduations over a 25 year appraisal period to 2048/49. 
Applying the same GVA per FTE, income per FTE and leakage, displacement and multiplier
assumptions generates an annual profile of net additional employment, income and GVA
each year.  The income and GVA benefits were then discounted to 2023/24 at 3.5% to
generate Present Value catalytic income and GVA benefits from the incubator. 
Inward investment jobs attracted to Moray by the presence of MICM 
The EIA model assumes that in the Option 2 or Option 3 intervention options, the presence
of MICM would attract two 10-job (FTEs) inward investment projects to Moray (one inward
investment project in 2027/28 and a second one in 2031/32).  For modelling purposes all 20
inward investment FTEs are assumed to be in premises other than MICM, but plausibly they
would be located at Enterprise Park Forres.  These are arbitrary, cautious assumptions but
are judged by CWA to be plausible given the wider cluster development ambitions of MICM
as set out in the FBC. 
The same adjustments for deadweight, leakage, displacement, and multipliers are applied
and a future stream of income and GVA benefits is generated. The income and GVA
benefits were then discounted to 2023/24 at 3.5% to generate Present Value catalytic
income and GVA benefits from inward investment.
Page 190

Page 191

Page 111 of 208 
These benefits were then added to those from the indigenous growth and incubator
graduations to allow an estimate to be made of total catalytic jobs, income and GVA benefits
at the Moray, Highlands & Islands, Scotland, and UK levels over 10, 15 and 25 years from
2024/25 (year 1). 
Overall assessment of costs, benefits, Benefit Cost Ratios (BCRs) and Net Present
Social Value
The benefit summaries on the following pages set out all of the net additional construction,
operational and catalytic benefits estimated from MICM in Options 2 and 3, over and above
the Option 1 reference case.  The tables also show the PV of net public sector cost, the Net
Present Social Value and Benefit Cost Ratio of each option at the four spatial levels and are
provided in the same format for snapshots at 10, 15 and 25 years.
Page 191

Page 192

Page 112 of 208 
OPTIONS 2 AND 3: NET ADDITIONAL BENEFITS AND VALUE FOR MONEY AT MORAY, HIGHLANDS AND ISLANDS,
SCOTLAND AND UK LEVELS - OVER 10 YEARS
10 YEARS MORAY H&IS SCOTLAND UK
Option 2 Option 3 Option 2 Option 3 Option 2 Option 3 Option 2 Option 3
One-off construction & equipment benefits - employment (job years) 19 48 22 54 24 61 21 53
One-off construction & equipment benefits - income 506,325 1,269,177 580,752 1,455,741 655,180 1,642,304 574,310 1,439,593
One-off construction & equipment benefits - GVA 1,060,738 2,658,894 1,219,846 3,057,721 1,060,738 3,456,548 1,212,264 3,038,716
Capital carbon disbenefit -26,724 -224,227 -26,724 -224,227 -26,724 -224,227 -26,724 -224,227
Operational carbon benefit/disbenefit -154,005 -154,005 -154,005 -154,005 -154,005 -154,005 -154,005 -154,005
Direct, on-site operational benefits - employment (job years) 107 107 129 129 118 118 35 35
Direct, on-site operational benefits - income 2,321,974 2,321,974 2,691,592 2,691,592 2,293,484 2,293,484 670,895 670,895
Direct, on-site operational benefits - GVA 6,403,913 6,403,913 7,502,962 7,502,962 6,549,283 6,549,283 1,928,285 1,928,285
Catalytic benefits - incubator graduations -  employment (job years) 71 71 85 85 130 130 146 146
Catalytic benefits - incubator graduations - income 567,933 567,933 658,338 658,338 934,941 934,941 1,025,590 1,025,590
Catalytic benefits - incubator graduations - GVA 1,674,657 1,674,657 1,952,512 1,952,512 2,813,218 2,813,218 3,096,876 3,096,876
Catalytic benefits - indigenous business growth and productivity -  employment (job years) 257 257 309 309 283 283 84 84
Catalytic benefits - indigenous business growth and productivity - income 5,653,179 5,653,179 6,553,066 6,553,066 5,583,816 5,583,816 1,633,389 1,633,389
Catalytic benefits - indigenous business growth and productivity  - GVA 14,000,011 14,000,011 14,833,085 14,833,085 10,251,987 10,251,987 2,776,547 2,776,547
Catalytic benefits - inward investment - employment (job years) 181 181 217 217 311 311 349 349
Catalytic benefits - inward investment - income 1,979,216 1,979,216 2,282,376 2,282,376 3,050,659 3,050,659 3,346,443 3,346,443
Catalytic benefits - inward investment - GVA 5,458,599 5,458,599 6,362,251 6,362,251 8,711,473 8,711,473 9,618,344 9,618,344
PV net additional monetised benefits over 10 years - all, incl. carbon & construction 28,417,188 29,817,841 31,689,926 33,330,298 29,205,969 31,404,277 18,451,587 20,080,536
PV net additional monetised benefits over 10 years, incl. carbon, excl. construction 27,356,451 27,158,947 30,470,080 30,272,577 28,145,231 27,947,728 17,239,323 17,041,820
PV net additional costs over 10 years (incl. OB on capex costs) 6,119,769 12,271,394 6,119,769 12,271,394 6,119,769 12,271,394 6,119,769 12,271,394
Benefit Cost Ratio (10 years) (incl. carbon, excl construction) 4.5 2.2 5.0 2 4.6 2 2.8 1
Benefit Cost Ratio (10 years) (excl. carbon, excl construction) 4.5 2.2 5.0 2 4.6 2 2.8 1
Net Present Social Value (10 years) (incl. carbon, excl. construction) 21,236,682 14,887,554 24,350,312 18,001,184 22,025,463 15,676,335 11,119,554 4,770,426
Page 192

Page 193

Page 113 of 208 
OPTIONS 2 AND 3: NET ADDITIONAL BENEFITS AND VALUE FOR MONEY AT MORAY, HIGHLANDS AND ISLANDS,
SCOTLAND AND UK LEVELS - OVER 15 YEARS
15 YEARS MORAY H&IS SCOTLAND UK
Option 2 Option 3 Option 2 Option 3 Option 2 Option 3 Option 2 Option 3
One-off construction & equipment benefits - employment (job years) 19 48 22 54 24 61 21 53
One-off construction & equipment benefits - income 506,325 1,269,177 580,752 1,455,741 655,180 1,642,304 574,310 1,439,593
One-off construction & equipment benefits - GVA 1,060,738 2,658,894 1,219,846 3,057,721 1,060,738 3,456,548 1,212,264 3,038,716
Capital carbon disbenefit -26,724 -224,227 -26,724 -224,227 -26,724 -224,227 -26,724 -224,227
Operational carbon benefit/disbenefit -224,391 -224,391 -224,391 -224,391 -224,391 -224,391 -224,391 -224,391
Direct, on-site operational benefits - employment (job years) 107 107 129 129 118 118 35 35
Direct, on-site operational benefits - income 3,294,537 3,294,537 3,818,970 3,818,970 3,254,114 3,254,114 951,900 951,900
Direct, on-site operational benefits - GVA 9,086,203 9,086,203 10,645,590 10,645,590 9,292,461 9,292,461 2,735,950 2,735,950
Catalytic benefits - incubator graduations -  employment (job years) 110 110 132 132 201 201 225 225
Catalytic benefits - incubator graduations - income 1,393,017 1,393,017 1,614,761 1,614,761 2,293,208 2,293,208 2,515,552 2,515,552
Catalytic benefits - incubator graduations - GVA 4,107,573 4,107,573 4,789,093 4,789,093 6,900,217 6,900,217 7,595,969 7,595,969
Catalytic benefits - indigenous business growth and productivity -  employment (job years) 309 309 371 371 340 340 101 101
Catalytic benefits - indigenous business growth and productivity - income 6,951,456 6,951,456 8,058,006 8,058,006 6,866,163 6,866,163 2,008,504 2,008,504
Catalytic benefits - indigenous business growth and productivity  - GVA 17,215,175 17,215,175 18,239,568 18,239,568 12,606,401 12,606,401 3,414,193 3,414,193
Catalytic benefits - inward investment - employment (job years) 181 181 217 217 311 311 349 349
Catalytic benefits - inward investment - income 3,621,062 3,621,062 4,175,707 4,175,707 5,581,312 5,581,312 6,122,462 6,122,462
Catalytic benefits - inward investment - GVA 9,986,744 9,986,744 11,640,014 11,640,014 15,938,018 15,938,018 17,597,179 17,597,179
PV net additional monetised benefits over 15 years - all, incl. carbon & construction 41,205,317 42,605,970 46,282,994 47,923,367 45,546,719 47,745,027 32,304,440 33,933,389
PV net additional monetised benefits over 15 years, incl. carbon, excl. construction 40,144,579 39,947,076 45,063,149 44,865,645 44,485,982 44,288,479 31,092,176 30,894,673
PV net additional costs over 15 years (incl. OB on capex costs) 6,234,244 12,385,869 6,234,244 12,385,869 6,234,244 12,385,869 6,234,244 12,385,869
Benefit Cost Ratio (15 years) (incl. carbon, excl construction) 6.4 3.2 7.2 3.6 7.1 3.6 5.0 2.5
Benefit Cost Ratio (15 years) (excl. carbon, excl construction) 6.5 3.3 7.3 3.7 7.2 3.6 5.0 2.5
Net Present Social Value (15 years) (incl. carbon, excl. construction) 33,910,335 27,561,207 38,828,905 32,479,777 38,251,738 31,902,610 24,857,932 18,508,804
Page 193

Page 194

Page 114 of 208 
OPTIONS 2 AND 3: NET ADDITIONAL BENEFITS AND VALUE FOR MONEY AT MORAY, HIGHLANDS AND ISLANDS,
SCOTLAND AND UK LEVELS - OVER 10 YEARS
25 YEARS MORAY H&IS SCOTLAND UK
Option 2 Option 3 Option 2 Option 3 Option 2 Option 3 Option 2 Option 3
One-off construction & equipment benefits - employment (job years) 19 48 22 54 24 61 21 53
One-off construction & equipment benefits - income 506,325 1,269,177 580,752 1,455,741 655,180 1,642,304 574,310 1,439,593
One-off construction & equipment benefits - GVA 1,060,738 2,658,894 1,219,846 3,057,721 1,060,738 3,456,548 1,212,264 3,038,716
Capital carbon disbenefit -26,724 -224,227 -26,724 -224,227 -26,724 -224,227 -26,724 -224,227
Operational carbon benefit/disbenefit -346,252 -346,252 -346,252 -346,252 -346,252 -346,252 -346,252 -346,252
Direct, on-site operational benefits - employment (job years) 107 107 129 129 118 118 35 35
Direct, on-site operational benefits - income 4,802,877 4,802,877 5,567,411 5,567,411 4,743,947 4,743,947 1,387,709 1,387,709
Direct, on-site operational benefits - GVA 13,246,145 13,246,145 15,519,467 15,519,467 13,546,834 13,546,834 3,988,552 3,988,552
Catalytic benefits - incubator graduations -  employment (job years) 206 206 247 247 378 378 423 423
Catalytic benefits - incubator graduations - income 3,608,865 3,608,865 4,183,333 4,183,333 5,940,975 5,940,975 6,516,997 6,516,997
Catalytic benefits - incubator graduations - GVA 10,641,418 10,641,418 12,407,020 12,407,020 17,876,274 17,876,274 19,678,745 19,678,745
Catalytic benefits - indigenous business growth and productivity -  employment (job years) 309 309 371 371 340 340 101 101
Catalytic benefits - indigenous business growth and productivity - income 6,951,456 6,951,456 8,058,006 8,058,006 6,866,163 6,866,163 2,008,504 2,008,504
Catalytic benefits - indigenous business growth and productivity  - GVA 17,215,175 17,215,175 18,239,568 18,239,568 12,606,401 12,606,401 3,414,193 3,414,193
Catalytic benefits - inward investment - employment (job years) 181 181 217 217 311 311 349 349
Catalytic benefits - inward investment - income 6,167,387 6,167,387 7,112,057 7,112,057 9,506,083 9,506,083 10,427,769 10,427,769
Catalytic benefits - inward investment - GVA 17,009,408 17,009,408 19,825,254 19,825,254 27,145,608 27,145,608 29,971,489 29,971,489
PV net additional monetised benefits over 25 years - all, incl. carbon & construction 58,799,907 60,200,560 66,838,178 68,478,550 71,862,879 74,061,186 57,892,267 59,521,216
PV net additional monetised benefits over 25 years, incl. carbon, excl. construction 57,739,169 57,541,666 65,618,333 65,420,829 70,802,141 70,604,638 56,680,003 56,482,500
PV net additional costs over 25 years (incl. OB on capex costs) 6,411,783 12,563,408 6,411,783 12,563,408 6,411,783 12,563,408 6,411,783 12,563,408
Benefit Cost Ratio (25 years) (incl. carbon, excl construction) 9.0 4.6 10.2 5.2 11.0 5.6 8.8 4.5
Benefit Cost Ratio (25 years) (excl. carbon, excl construction) 9.1 4.6 10.3 5.3 11.1 5.7 8.9 4.5
Net Present Social Value (25 years) (incl. carbon, excl. construction) 51,327,386 44,978,258 59,206,550 52,857,422 64,390,359 58,041,231 50,268,221 43,919,092 
Page 194

Page 195

Page 115 of 208 
Appendix 3: MICM Logic Model
Logic model for the Manufacturing Innovation Centre for Moray (MICM) project
Inputs Activities Outputs Outcomes Impacts
Resources
needed to
deliver the
project.
Actions needed to deliver
the project.
Measurable direct results of the activities. Changes that occur to the beneficiaries
and the medium-term benefits on the
economy. 
The long-term
effect upon the
economy or
society
GENERAL SUPPORT FOR BUSINESS GROWTH AND COMPETITIVENESS
£public
£private 
Capital vs
revenue
Overall no. of businesses
assisted to improve their
performance, of which:
• SMES
• Other businesses 
No. of jobs created (FTEs)
No. of jobs safeguarded (FTEs)
No. of businesses with improved performance –
GVA
No. of businesses with improved performance - new
products, processes or services
No. of graduates placed in SMEs
Increase in GVA from improved performance
Increase in GVA/employee (productivity) from
improved performance
Increase in Gross Value Added 
Workplace employment (by SIC and size
of firm) 
% of small businesses in an area
showing employment growth 
Productivity (GVA per employee)
GVA 
Employment 
Productivity
START-UP ASSISTANCE AND PROMOTION OF SPIN-OUTS
£public
£private 
Capital vs
revenue
No. of businesses supported
to start-up (e.g. individuals
helped to start a business or
HEIs or SMEs encouraged
to spin-out new companies)
No. of new businesses (private companies or sole
traders)
No. of new businesses still in operation after 12
months
GVA of new businesses still in operation after 12
months
No of jobs created FTE
No of jobs safeguarded FTE
No of new businesses demonstrating growth from
12-24 months
Total business stock; 
Gross Value Added 
Productivity (GVA per employee) 
Workplace employment (by SIC and size
of firm) 
% of small businesses in an area
showing employment growth
Number of
manufacturing
businesses by
size 
GVA 
Employment 
Page 195

Page 196

Page 116 of 208 
Logic model for the Manufacturing Innovation Centre for Moray (MICM) project (continued)
Inputs Activities Outputs Outcomes Impacts
PROMOTION OF BUSINESS ENTERPRISE RESEARCH AND DEVELOPMENT (BERD)
£public
£private 
Capital vs
revenue
No. of businesses engaged
in new collaborations with
the UK knowledge base
Other activities (advice,
signposting, consultancy,
networking) targeted at
increasing business R&D
activity and the intensity of
that support
Value of increased R&D in those businesses
engaged with the knowledge base 
R&D expenditure as % of turnover in beneficiary
firms 
No of patents filed 
Increase in GVA/employee (productivity)
due to R&D investment
Business R&D as a proportion of GVA 
Gross Value Added 
Productivity (GVA/employee) 
GVA 
BERD 
Productivity
INDUSTRIAL AND COMMERCIAL PROPERTY DEVELOPMENT
£public
£private 
Capital vs
revenue
Sq.m. of space constructed
(by type and grade)
Sq metre of buildings
occupied; Tonnes of Spoil
Removed
Hectares of land regraded
Length of new site access
and on-site roads
constructed
Installation of metres of
linking and on-site service
networks (sewers, water
supply, gas, electricity,
telecoms)
Hectares of land serviced for
industrial or commercial
development. 
Hectares of previously developed land that has been
vacant or derelict for more than 5 years 
Occupancy level for different use (by SIC) 
Occupancy level (proportion of floorspace) 
Number of jobs accommodated (FT/PT > FTEs) 
No of businesses accommodated (by SIC) 
% increase in stock of commercial
development land 
% increase in commercial land values 
% increase in commercial property
values 
Workplace employment (by SIC) 
Gross Value Added
Stock of
commercial
development
land and
floorspace 
Employment 
GVA 
Page 196

Page 197

Page 117 of 208 
Appendix 4: Optimism Bias assessment
A formal Optimism Bias (OB) assessment has been conducted for the project, in
accordance with HM Treasury Green Book guidance.
The first step in the OB assessment is to classify the project. For the purposes
of this assessment, all of the capex works have been defined as “standard building”.
On this basis, the unmitigated upper bound OB impacts at this Full Business Case
stage are standard building: 4% for Works Duration and 24% for Capital Expenditure 
Figure OB.1 shows the factors contributing to Optimism Bias in works duration and
capital expenditure for both types of project.  This draws on research evidence by
Mott MacDonald presented in Supplementary Green Book Guidance (2002) on the
extent to which different factors contribute to Optimism Bias in relation to capital
expenditure and works duration.
The second step in the OB assessment is to assess the level of mitigation
which has been achieved so far in relation to each of these factors at this Outline
Business Case stage.  The level of mitigation would be expected to increase further
the more advanced the project is in relation to its planning, design and procurement. 
The mitigation factors and responses were derived through discussion with the HIE
project team and the comments show how these mitigation factors have been
justified.
The third step derives the level of unmitigated OB, as shown in tables OB.2 and
OB.3.  This applies the mitigation factors to the starting upper bound OB in order to
derive the level of unmitigated Optimism Bias which is felt to be associated with the
project at this FBC stage, in relation to both capital expenditure and works duration.
Within the Cost Benefit Analysis model, the unmitigated OB figures have been used
to make upward adjustments to the Present Value of all capital expenditure for the
purposes of the BCR calculation in the Economic Case (Section 3).
Unfortunately, no evidence exists on Optimism Bias as it relates to project benefits or
revenue costs or income.  As Figure OB.1 makes clear, the principal areas that
cannot be mitigated at present relate to general optimism inherent with Business
Cases at this stage.  Cautious benefit assumptions have been used in the EIA and
the revenue costs include a 10% contingency.  The Financial Case also subjects the
revenue model to sensitivity testing.  In addition, a 15% unmitigated Optimism Bias
adjustment has been included in the value for money assessment.
The capital costs are estimates provided by Torrance Partnership based on recent
procurement activity on similar HIE projects and include works contingency at 5%
with a further contingency of 10% applied to Unit 9 to reflect the immaturity of the
detailed design process.  Even with the further addition of 5% Optimism Bias on
capital expenditure, the switching value calculations in Section 3 demonstrate that
benefits in the preferred option would need to fall by over 80% before the BCR would
fall below 1:1 and that costs would need to increase more than six-fold.
Page 197

Page 198

Page 118 of 208 
Figure OB.1: Optimism Bias Contributory Factors & Mitigation Assessment
Project Type (note 1) Standard Buildings BUILDING Justification For Mitigation factor
Upper Bound 
Optimum Bias
(note 1)
Works
Duration
Capital
Expenditure
Proposed
Mitigation
Factor (%) 
4% 24%
Risk Area Contributions to Recorded Optimism Bias
(%)
Procurement
Complexity of
Contract
Structure
1% 0% 90% No novel contract structures will be
used for building contracts.  Existing
HIE Procurement Frameworks and
NEC4 contracts. HIE will oversee the
process and have a dedicated
procurement team.
Late contractor
involvement in
design
3% 2% 85% Standard works with no novel
elements.  Normal procurement
procedures will apply.
Poor Contractor
Capabilities
4% 9% 90% Procured through Quick Quote
(Contractors already on HIE's
Framework) or via Open Tender with
necessary vetting in place.
Government
Guidelines
0% 0% N/A N/A
Dispute and
Claims
Occurred
4% 29% 85% Disputes will be mitigated with
effective communication, good
design input and effective project
management as well as effective
procurement and contract
management procedures. 
Nevertheless, these cannot be
mitigated until contracts are signed.
Ask for risk register at tender stage
and attribute risks to contractor vs
HIE in advance to set appropriate
boundaries and risk ownership
Information
management
0% 0% N/A N/A
Other (specify) 0% 0% N/A N/A
Project Specific
Design
Complexity
3% 1% 90% Design is sustainable, proven
building design with standard
features and components
Degree of
Innovation
1% 4% 95% No innovative design features
Environmental
Impact
0% 0% N/A N/A
Other (specify) 0% 0% 75% N/A
Client Specific
Inadequacy of
the Business
Case
31% 34% 75% Business case has been developed
in close co-operation with cost
advisors and Project Board with
representatives from relevant public
sector agendies and private sector
representatives. An action plan and
risk register has been developed as
part of the FBC.
Large Number
of Stakeholders
6% 0% 75% Business case has been developed
in close co-operation with project
partners.  A full action plan and risk
register has been developed as part
of the FBC.
Funding
Availability
8% 0% 90% This FBC follows previous approval
to OBC. Funding strategy agreed in
principle.
Project
Management
Team
0% 1% 90% Highly experienced team in HIE with
their retained advisors mitigate this
item.
Poor Project 6% 2% 80% HIE owns Units 9 and 10 and has
Page 198

Page 199

Page 119 of 208 
Figure OB.1: Optimism Bias Contributory Factors & Mitigation Assessment
Project Type (note 1) Standard Buildings BUILDING Justification For Mitigation factor
Upper Bound 
Optimum Bias
(note 1)
Works
Duration
Capital
Expenditure
Proposed
Mitigation
Factor (%) 
4% 24%
Risk Area Contributions to Recorded Optimism Bias
(%)
Intelligence plans and O&M Manuals for both. 
Design standards are clear and
based on other HIE projects.
Other (specify) 0% 1% 75%  
Environment
Public
Relations
8% 2% N/A Experience of delivering previous
projects at Enterprise Park Forres
and managing construction activity
on site and in the surrounding area;
this will inform procedures and
communications for MICM.
Site
Characteristics
5% 2% 85% Enterprise Park Forres is owned by
HIE and has been subject of
extensive investigation;
topographical and ground conditions
are known.
Permits /
Consents /
Approvals
9% 0% 90% Enterprise Park Forres already has
outline planning consent for these
uses.  Building Warrants will be
needed, but the work is not
contentious.
Other (specify) 0% 0% 75% N/A
External Influences
Political 0% 0% 95% The Project has already received
considerable positive feedback from
Government. MICM is in the
Regional Spatial Strategy and is
identified in the national Innovation
Strategy and included in the Moray
Growth Deal. The project is firmly
supported by HIE and Moray Council
and is understood to have the
support of all political parties locally.
Economic 0% 11% 70% Inflation on construction costs is the
most significant external economic
risk.  Provision is made for future
inflation at 6% (mid-point in advised
range of 5-7% by Torrance
Partnership).
Legislation /
Regulations
9% 3% 85% No issues foreseen at this time.
Technology 0% 0% 95% No issues foreseen at this time.
Other (specify) 0% 0% 95% No issues foreseen at this time.
Notes:
1.     ‘Supplementary Green Book Guidance - Optimism Bias’ prepared from advice provided by Mott MacDonald (2002). 
Page 199

Page 200

Page 120 of 208 
Figure OB.2: Optimism Bias Summary Table for Capital Expenditure - STANDARD BUILDING
Standard Building
(a) 100%
(b) 24%
Complexity of Contract
Structure 0% 90% 0.00%
Late contractor
involvement in design 2% 85% 1.70%
Poor Contractor
Capabilities 9% 90% 8.10%
Government Guidelines 0% N/A 0.00%
Dispute and Claims
Occurred 29% 85% 24.65%
Information management 0% N/A 0.00%
Other (specify) 0% N/A 0.00%
Design Complexity 1% 90% 0.90%
Degree of Innovation 4% 95% 3.80%
Environmental Impact 0% N/A 0.00%
Other (specify) 0% 75% 0.00%
Inadequacy of the
Business Case 34% 75% 25.50%
Large Number of
Stakeholders 0% 75% 0.00%
Funding Availability 0% 90% 0.00%
Project Management
Team 1% 90% 0.90%
Poor Project Intelligence 2% 80% 1.60%
Other (specify) 1% 75% 0.75%
Public Relations 2% N/A 0.00%
Site Characteristics 2% 85% 1.70%
Permits / Consents /
Approvals 0% 90% 0.00%
Other (specify) 0% 75% 0.00%
Political 0% 95% 0.00%
Economic 11% 70% 7.70%
Legislation /
Regulations 3% 85% 2.55%
Technology 0% 95% 0.00%
Other (specify) 0% 95% 0.00%
(c) 79.9%
(d)=bxc 19.2%
(e)=b-d 4.8%
(f) 0% (base costs include contingency already)
(g)=e+f 4.8%
(h)=a+e+f 104.8%
OB is applied at 5% / 105% of base cost
Less mitigated Optimism Bias contribution (%)
External
Influences
Total % by which upper bound OB can be mitigated
Net Contribution (%)
Procurement
Project
Specific
Client Specific
Environment
Unmitigated Optimism Bias (%)
Cost of risk management (% of base cost)
Total Optimism Bias %
Base Cost adjusted for total mitigated Optimism Bias (%)
Risk Area
Gross
Contribution to
optimism bias
(%)
Mitigation
factor (%)
Project Type
Estimated Cost
Upper bound Optimism Bias
Page 200

Page 201

Page 121 of 208 
Figure OB.3: Optimism Bias Summary Table for Works Duration - STANDARD BUILDING
Standard Building
(a) 100%
(b) 4%
Complexity of Contract
Structure 1% 90% 0.90%
Late contractor
involvement in design 3% 85% 2.55%
Poor Contractor
Capabilities 4% 90% 3.60%
Government Guidelines 0% N/A 0.00%
Dispute and Claims
Occurred 4% 85% 3.40%
Information management 0% N/A 0.00%
Other (specify) 0% N/A 0.00%
Design Complexity 3% 90% 2.70%
Degree of Innovation 1% 95% 0.95%
Environmental Impact 0% N/A 0.00%
Other (specify) 0% 75% 0.00%
Inadequacy of the
Business Case 31% 75% 23.25%
Large Number of
Stakeholders 6% 75% 0.00%
Funding Availability 8% 90% 7.20%
Project Management
Team 0% 90% 0.00%
Poor Project Intelligence 6% 80% 4.80%
Other (specify) 0% 75% 0.00%
Public Relations 8% N/A 0.00%
Site Characteristics 5% 85% 4.25%
Permits / Consents /
Approvals 9% 90% 8.10%
Other (specify) 0% 75% 0.00%
Political 0% 95% 0.00%
Economic 0% 70% 0.00%
Legislation /
Regulations 9% 85% 7.65%
Technology 0% 95% 0.00%
Other (specify) 0% 95% 0.00%
(c) 69.4%
(d)=bxc 2.8%
(e)=b-d 1.2%
(f) 0% (base costs include contingency already)
(g)=e+f 1.2%
(h)=a+e+f 101.2%
Treated as de minimis - not applied to
programme
Project Type
Estimated Works Duration
Upper bound Optimism Bias
Less mitigated Optimism Bias contribution (%)
Unmitigated Optimism Bias (%)
Total % by which upper bound OB can be mitigated
Net Contribution (%)
Cost of risk management (% of base cost)
Total Optimism Bias %
Works Duration adjusted for total mitigated Optimism Bias (%)
Risk Area
Gross
Contribution to
optimism bias
(%)
Mitigation
factor (%)
External
Influences
Procurement
Project
Specific
Client Specific
Environment
Page 201

Page 202

Page 122 of 208 
Appendix 5: Carbon Categorisation Form
Item Project Owner Response
1. Project Name Manufacturing Innovation Centre for Moray (MICM)
2. Deal Region Moray
3. Brief Description of Project
Creation of MICM Hub (incubator, service provider base and
technical/demonstration space) and MICM Grow-on space through the
refurbishment of existing buildings plus 250 sq.m of new build grow-on
space and delivery of manufacturing innovation services (see Commercial
Case)
4. Expected Carbon Emissions
Impact CONTROL Category (1-5) 3
5. Expected Carbon Emissions
Impact INFLUENCE Category (A-
C)
B (for appraisal purposes), but actively engaging with businesses to
influence them in ways which would support level A – see Q10 below.
6. Justification of Expected Carbon
Emissions Impact Category 
e.g. a short narrative outlining the
key carbon emission sources and
their relationship to capital and
operational net zero following the
Deals Carbon Emissions Impact
Categorisation Process.
Capital carbon: the capital works for the MICM project are primarily for
property construction and refurbishment activity. To that extent it will utilise
construction materials with embodied carbon. 
Operational carbon: there is a clear pathway to operational net zero.  The
Whole of Life Carbon Impact will be mitigated through the use of ground
and air source heat pumps, good levels of insulation and solar PV. 
However, there will be operational carbon through building energy demand
until the grid is decarbonised, there will be an element of operational
carbon. 
MICM will be a net zero demonstrator (see Q8. below).  MICM service
delivery will seek to help businsses find the right support to aid them on
their own net zero transition.  This is the justification for the influencing
category.
7. Could the Carbon Emissions
Impact Category be improved? 
e.g. from Category 4B to Category
3A
No.  Due to the refurbishment and new build activity, embodied carbon will
inevitably be a feature of this project.  An alternative new build option was
rejected in determining that re-use of existing buildings should be the
primary strategy.
8. Could the carbon performance
of the project be improved? 
e.g. reducing emissions further,
achieving net zero faster.
Possibly.
During the detailed design process, efforts will be made to mitigate capital
and operational carbon within the budget envelope.
9. How will carbon be managed? 
e.g. through PAS 2080: Carbon
Management in Infrastructure for
infrastructure projects or the RICS
Whole Life-Cycle Carbon
Professional Statement for
buildings projects
A RICS Whole Life Carbon Statement will be prepared as part of the
detailed design process.  CENSIS will also be involved to install IoT-based
sensors and measurement technology and enable the project to be used as
a net zero demonstrator.
10. What other carbon
savings are expected to result
from the project? 
e.g. wider carbon savings across
the economy resulting from project
output
MICM will have a net zero demonstration component, but no attempt has
been made at this stage to quantify the potential impact on manufacturing
SMEs.  To do so would risk double counting the carbon impacts of those
organisations who may be involved (e.g. Business Energy Scotland,
Innovation Centres).  Efforts will be made to quantify this at evaluation
stage. 
Page 202

Page 203

Page 123 of 208 
Appendix 6: Risk Register 
Impact Likelihood Risk score
There is a risk that….
The potential impact is….
The potential likelihood is….
10 Project Lead Financial Cost inflation compromises delivery of MICM 4 4 16 Monitor. Include contingency. Propose cost savings. Explore additional funding Reduce
11 Project Lead Delivery MAATIC rescoping impacts viability of MICM 4 3 12 Monitor. Ensure HIE are kept informed and that MAATIC team are updated in MICM Reduce/share
3 OBC Objectives & benefits Lack of productive engagement with the business community 4 3 12
Consultation events with the Moray Growth Deal, Business Assembly and Chamber of
Commerce, as well as a broader business survey. Ensure involvement with Project
Board
Reduce
14 FBC Financial Revenue assumptions are overoptimistic 3 4 12 Sensitivity analysis in FBC , monitoring and review Monitor
6 OBC Delivery Inadequate management expertise 5 2 10 Mitigated by budgeting for the recruitment of a high calibre Project Director and Centre
Manager to maximise benefits Reduce
2 OBC Delivery Competing demands for resources across Growth Deal projects 3 3 9 Good co-ordination between what are three highly complementary projects in order to
ensure no duplication and maximise synergies Reduce
1 OBC Financial Under-estimation of costs 3 3 9 Business planning process, risk assessment and Optimism Bias assessment Reduce
7 OBC Objectives & benefits Lack of engagement from NMIS, SMAS, Interface, Business Gateway and
others 3 2 6
Initial consultation work directly through MICM business planning or through UHI’s
development of the MAATIC proposal to ensure they are sighted on, and supportive of
the proposals being made
Reduce/share
9 OBC Objectives & benefits Impact of Brexit on supply chains and business operations 2 3 6
These risks are, by definition, outside of our control, but we can mitigate to some
extent through focused business advice and support, as HIE and its partners have
been doing already during 2020.
Accept
Proposed mitigation options and approach to be takenRef ID Raised by
Area of the project affected by the
entry
Description of the risk Assessment of the risk
Mitigation strategy
Page 203

Page 204

Page 124 of 208 
Appendix 7: Capital works – cost estimates
Page 204

Page 205

Page 125 of 208 
Prepared by
Torrance Partnership LLP
23 Southside Road
Inverness
IV2 3BG
REFIT WORKS AT UNIT 9
HIGHLANDS AND ISLANDS ENTERPRISE
TP Ref: 23.805
21 July 2023
ORDER OF COST
FORRES ENTERPRISE PARK, MORAY
Page 205

Page 206

Page 126 of 208  Page 206

Page 207

Page 127 of 208 
ORDER OF COST
HIGHLANDS AND ISLANDS ENTERPRISE
REFIT WORKS AT UNIT 9
FORRES ENTERPRISE PARK, MORAY
GIFA 1,072           m2
Item Unit Gross Area Total £/m2 Sub-Totals
GENERALLY
GF Left Hand Unit
Downtakings
m2 35 35 50£        1,733£    
New Work
15,000£  
no. 1 1 2,500£    2,500£    
m2 140 140 400£      56,000£   75,233£         
GF Right Hand Unit
Downtakings
Strip out office cubicles m2 39 39 50£        1,925£    
sum 10,000£  
New Work
m2 54 54 1,000£    54,250£  
sum 1 1 10,000£  10,000£  
sum 10,000£  
no. 1 1 7,500£    7,500£     93,675£         
GF Rear Unit
Alterations
15,000£  
sum 1 1 2,500£    2,500£     17,500£       
Mezzanine Area
Alterations
m2 136 136 250£      34,000£  
m2 240 240 150£      36,000£  
no. 50 50 150£      7,500£    
sum 1 1 10,000£  10,000£   87,500£         
Carry Forward 273,908£       
Introduce fire and acoustic separation to
Mezzanine above;  include for glazed
openings to create visual link
Introduce separation between GF Unit
and Rear Fire Escape
Remove existing window and forming
loading area to front with large door
25th JULY, 2023
Review of fire / security / acoustics; 
provisional allowance for improvements
Minor strip out works to lobby and later
additions
Alterations to Lift position to improve
function - assume turning 90 deg
Review of fire / security / acoustics; 
provisional allowance for improvements
General upgrade to right hand side
following separation from GF;  allow for
new tea prep / touchdown space
New double door from Reception area into
Suite
Sub-Divide space into two Offices; 
include for new lowered ceiling over both
offices [M&E allowed separately]
Alterations to raised access flooring and
introduction of 3 No. concrete plinths
approx. 2m x 2m
Alterations to benching
Introduce ceiling over mezzanine areas
including meeting rooms
Introduce acoustic rafts in mezzanine
areas;  include for hanging on wires
Reconfiguration of escape stair to improve
space and function at mezzanine and GF
Page 207

Page 208

Page 128 of 208  Page 208

Page 209

Page 129 of 208 
Brought Forward 273,908£       
m2 64 64 250£      16,000£   16,000£         
Main Stair
sum 1 1 7,500£    7,500£     7,500£           
Main Entrance
sum 1 1 7,500£    7,500£     7,500£           
M&E Improvements
sum 1 1 10,000£  10,000£  
sum 1 1 70,000£  70,000£  
sum 1 1 10,000£  10,000£  
sum 1 1 5,000£    5,000£    
m2 1072 1,072 150£      160,800£ 
m2 1072 1,072 80£        85,760£  
no. 15 15 1,500£    22,500£  
m2 140 140 350£      49,000£  
m2 64 64 350£      22,400£  
Introduce PV to the Roof sum 50,000£   485,460£       
General Areas
sum 5,000£    
m2 1072 1,072 40£        42,880£  
sum 1 1 20,000£  20,000£  
sum 1 1 5,000£    5,000£     72,880£         
Roof
m2 740 740 75£        55,500£   55,500£         
EXTERNAL WORKS
m2 250 250 120£      30,000£   30,000£         
sum 1 1 10,000£  10,000£   10,000£         
Carry Forward 958,748£       
Upgrade of signage strategy
Improve roof insulation and acoustic
performance [all internal]
Allow for sub-division of services within
GF left hand unit to form 2 offices
Alterations to external paving
Allowance for improvements to stair
balustrade/detailing
Upgrade main entrance door to automatic
opening
Alterations to underfloor heating where
flooring changes and at area where new
external doors, etc.
Allow for alterations to FF meeting room 2
and 3 to form single incubator space
Upgrade incoming electrical supply to the
building;  including tracking back to
substation, etc.
Provide 3 Phase power supplies to the
Incubator labs;  assume 2 outlets in each
lab and 2 outlets in GF area
Provide containment for future install of
compressed air
Allow for upgrading existing electrical
installation - power and data
Allow for upgrading existing lighting to
LED fittings
General refresh of internal decoration
throughout
Allowance for external decoration
Allow for upgrading access control to
principal internal doors
General improvements to external
landscaping
General Builderswork in connection with
Services improvements, etc.
Allow for alterations to services within FF
meeting room 2 and 3 to form single
incubator space
Page 209

Page 210

Page 130 of 208 
Brought Forward 958,748£       
Sub-Total Construction Costs 958,748£       
Main Contractor Prelims 15% 143,812£       
1,102,560£     
Main Contractor Fee 7% 77,179£         
Employer Risk, Say 5% 58,987£         
ESTIMATED CONSTRUCTION COSTS 1,238,726£     
Design Team Fees 10% 123,873£       
Prime Consultant Fees - All Stages [6.35% + NM] 83,659£         
4,874£           
1,000£           
1,452,131£     
Building Warrant Fees
ESTIMATED UPGRADE COSTS
Planning Fee + Advertising Fee
Page 210

Page 211

Page 131 of 208 
Notes:
1.
2.
3.
4.
5.
Base date of Order of Cost - July, 2023
This Cost includes the following;
ii   Professional Fees
iii  Building Warrant costs.
iv  Planning Fee
This Cost excludes the following;
All costs are based on rates with allowances included for open tendering during 'Fourth
Quarter 2023' from Main Contractors, incorporating a NEC4 ECC Option A contract.
Should the timescale for commencing construction works be more longer term then
allowances in line with BCIS TPI should be made for inflation.
This Cost is based on outline scope and discussions with HIE and following latest floor
plans for the building.
ii  Office cupboards, general shelving, loose fittings / furniture / FF&E
iii  Professional Fees in respect of the works.
iv  Value Added Tax  (see note below)
Note: In relation to buildings VAT is a complex area. Therefore, it is recommended that
specialist advice is sought on VAT matters to ensure that the correct rates are applied
to the various aspects of a building project.
i   General Upgrade Works as identified.
i   Office desks, chairs, storage units and the like. 
Page 211

Page 212

Page 132 of 208 
Prepared by
Torrance Partnership LLP
23 Southside Road
Inverness
IV2 3BG
26th July, 2023
HIGHLANDS AND ISLANDS ENTERPRISE
EXTENSION TO UNIT 10
FORRES ENTERPRISE PARK, MORAY
ORDER OF COST
TP Ref: 23.805
Page 212

Page 213

Page 133 of 208 
ORDER OF COST
HIGHLANDS AND ISLANDS ENTERPRISE
EXTENSION TO UNIT 10
FORRES ENTERPRISE PARK, MORAY
GIFA 250               m2
Item Unit Gross Area Total £/m2 Sub-Totals
GENERALLY
Extension to Unit 10 with link and associated access road and parking
m2 250 250 3,250£     812,500£ 
m2 30 30 2,500£     75,000£   
sum 1 1 25,000£   25,000£   
m2 460 460 1,030£     473,800£ 
1,386,300£  
External Works
m2 1000 1,000 100£       100,000£ 
m2 300 300 75£         22,500£   
sum 1 1 20,000£   20,000£   
SSE sum 1 1 65,000£   65,000£   
BT sum 1 1 5,000£     5,000£     
Water sum 1 1 10,000£   10,000£   
222,500£       
Sub-Total Construction Costs 1,608,800£     
Main Contractor Prelims 15% 241,320£       
1,850,120£     
Main Contractor Fee 7% 129,508£       
Employer Risk, Say 5% 98,981£         
ESTIMATED CONSTRUCTION COSTS 2,078,610£     
Design Team Fees 10.0% 207,861£       
Prime Consultant Fees - All Stages [3.1% + NM] 69,437£         
7,603£           
2,100£           
2,365,611£     
External Services
Building Warrant Fees
Planning Fee
ESTIMATED TOTAL COST
E.O. for stormcell attenuation, etc.
Link facility to Unit 10
Minor alterations within Unit 10
comprising new opening for roller shutter
door;  minor alterations to core area
26th JULY, 2023
250m2 GFA Unit single storey; with link
facility to Unit 10.  Manufacturing
Specification with Office Accommodation;
3-phase power, ASHP, Solar PV
General Siteworks forming access road,
car parking, etc.
Drainage
General Allowance for SUDS, rainwater,
FW sewers, etc.
Sub-division of Unit 10 to form 3 Units; 
assumes sub-division of services, etc.
Improvements to interior lighting
Page 213

Page 214

Page 134 of 208  Page 214

Page 215

Page 135 of 208 
Notes:
1.
2.
3.
4.
5.
i   Office desks, chairs, storage units and the like.
ii  Office cupboards, general shelving, loose fittings / furniture / FF&E
iii  Professional Fees in respect of the works.
iv  Value Added Tax  (see note below)
Note: In relation to buildings VAT is a complex area. Therefore, it is recommended that
specialist advice is sought on VAT matters to ensure that the correct rates are applied to
the various aspects of a building project.
This Cost excludes the following;
Base date of Order of Cost - July, 2023
All costs are based on rates with allowances included for open tendering during 'Fourth
Quarter 2023' from Main Contractors, incorporating a NEC4 ECC Option A contract.
Should the timescale for commencing construction works be more longer term then
allowances in line with BCIS TPI should be made for inflation.
This Cost is based on outline scope and discussions with HIE. The Cost assumes a
serviced site on the Enterprise Park, Forres is available, i.e. no allowance for roads,
services, etc. outwith plot boundary.
This Cost includes the following;
i   Professional Fees
ii  Building Warrant costs.
iii  Planning Fee
Page 215

Page 216

Page 136 of 208 
TENDER PRICE UPLIFT
HIGHLANDS AND ISLANDS ENTERPRISE
FORRES ENTERPRISE PARK, MORAY
Item Unit Gross Area Total £/m2 Sub-Totals
Tender Price Index Adjustment
3rd Qtr. 2023 387
3rd Qtr. 2024 404 + 4.39%
3rd Qtr. 2025 418 + 3.47%
3rd Qtr. 2026 429 + 2.63%
3rd Qtr. 2027 450 + 4.90%
TP Recommendation :-
21st JULY, 2023
While the above is based on BCIS forecast information, we have seen changes
in the local construction market that are not fully reflected in the UK wide
BCIS indices.  For budgeting purposes we would suggest it would be prudent
to allow in the order of 5-7% per annum uplift to reflect likely changes in the
local market conditions.
Page 216

Page 217

Page 137 of 208 
Appendix 8: Capital works – contract template 
Contract Documents 
INDEX 
1 FORM OF TENDER
2 FORM OF AGREEMENT
3 CONTRACT DATA PART ONE
4 CONTRACT DATA PART TWO
5 APPENDIX A –  AMENDMENTS TO NEC4 ENGINEERING
AND CONSTRUCTION CONTRACT JUNE
2017 (WITH AMENMENTS JANUARY 2019
AND OCTOBER 2020)
6 APPENDIX B –  SCOPE
7 APPENDIX C –  SITE INFORMATION
8 APPENDIX D – CLIENT'S EARLY WARNING REGISTER
9 APPENDIX E –  PRE-CONSTRUCTION HEALTH & SAFETY
INFORMATION PACK 
10 APPENDIX F –  ACTIVITY SCHEDULE : TENDER TOTAL
OF THE PRICES (INCLUDING CASH FLOW
PROJECTION)  
11 APPENDIX G –  [BCIS ELEMENTAL COST ANALYSIS,
TENDER RETURN COST SUMMARY AND
ELEMENTAL COST BUILD UP (SHOWING
RATES AND PRICES)]
12 APPENDIX H –  CONTRACTORS EARLY WARNING
REGISTER 
Page 217

Page 218

Page 138 of 208 
13 APPENDIX I –  WORKS PROGRAMME
14 APPENDIX J –  [DESIGN INFORMATION – [  ]] 
15 APPENDIX K –  [DESIGN INFORMATION – DRAWINGS] 
16 APPENDIX L –  [SURVEY REPORTS]
17 APPENDIX M – [PLANNING PERMISSION] 
18 APPENDIX N – [ROAD CONSTRUCTION CONSENT]
19 APPENDIX O – [BIM] 
20 APPENDIX P –  PERFORMANCE BOND
21 APPENDIX Q – COLLATERAL WARRANTY AGREEMENTS
22 APPENDIX R –  PARENT COMPANY GUARANTEE
23 APPENDIX S – GENERAL HIE SCOPE
24 APPENDIX T –  GENERAL HIE SITE INFORMATION
25 APPENDIX U – COLLUSIVE TENDERING
26 APPENDIX V –  CANVASSING 
27 APPENDIX W –  LEGAL AGREEMENTS
28 APPENDIX X –  [PROJECT SPECIFIC INFORMATION]
29 APPENDIX Y –  ITT CLARIFICATIONS
30 APPENDIX Z- [COVID-19 ALLOWABLE COSTS
SCHEDULE] 
Page 218

Page 219

Page 139 of 208 
1 FORM OF TENDER 
The works are [INSERT]
TENDER  
To 
Highlands & Islands Enterprise (the Client) 
Address 
An Lòchran,
10 Inverness Campus, 
Inverness,
IV2 5NA 
We offer to Provide the Works in accordance with the Contract Data part one and
the attached Contract Data part two for a tendered total of the Prices of    
[£                                       ] in accordance with the conditions of contract. 
You may accept this offer on or before [INSERT] (per A30/190). 
Yours faithfully, 
Signed  ........................................................................................................................... 
Name  ............................................................................................................................. 
Position  ......................................................................................................................... 
On behalf of  ......................................................................................... (the Contractor) 
Address .......................................................................................................................... 
....................................................................................................................................... 
.......................................................................................................................................  
Date  ............................................................................................................................... 
Page 219

Page 220

Page 140 of 208 
2 FORM OF AGREEMENT 
This agreement is made on the ……. day of ………………................20[  ] .....  between 
Highlands and Islands Enterprise established under the Enterprise and New Towns
(Scotland) Act 1990 and having its principal office at An Lòchran, 10 Inverness
Campus, Inverness, IV2 5NA 
and 
...................................................................................................................................... 
............................................................................................................. (the Contractor) 
The Client wishes to have the following works provided:
[INSERT]      
1. The Contractor will Provide the Works in accordance with the conditions of
contract identified in the Contract Data and shall fulfil its other obligations arising
out of this contract. 
2. The Client will pay the Contractor the amount due and carry out his duties in
accordance with the conditions of contract identified in the Contract Data. 
3. The documents forming part of this agreement are: 
• the Contractor’s tender 
• the Client's letter of acceptance 
• conditions of contract (NEC4 Engineering and Construction contract, Main
Option A, June 2017 with Amendments January 2019 and October 2020) as
amended by Appendix A – Amendments to the NEC4 Engineering and
Construction Contract 
• the Contract Data part one [including] 
a. Appendix A – Amendments to the NEC4 Engineering and
Construction Contract 
b. Appendix B – Scope
c. Appendix C – Site Information
d. Appendix D –Client's Early Warning  Register
e. Appendix E – Pre Construction Health & Safety Information
Pack
f. Appendix J – [Design Information – [ ]]
g. Appendix K – [Design Information – Drawings]
h. Appendix L – [Survey Reports]
i. Appendix M – [Planning Permission]
j. Appendix N – [Road Construction Consent]
Page 220

Page 221

Page 141 of 208 
k. Appendix O – [BIM]  
l. Appendix P – Performance Bond
m. Appendix Q – Collateral Warranty Agreements
n. Appendix R – Parent Company Guarantee 
o. Appendix S – General HIE Scope
p. Appendix T – General HIE Site Information 
q. Appendix U – Collusive Tendering
r. Appendix V – Canvassing 
s. Appendix W – Legal Agreements
t. Appendix X – [Project Specific Third Party information]
u. Appendix Y – ITT Clarifications
v. Appendix Z – [Covid-19 Allowable Costs Schedule] 
• the Contract Data part two [including] 
a. Appendix F – Activity Schedule: Tender Total of the Prices
(including Cash Flow Projection)
b. Appendix G – BCIS Elemental Cost Analysis, Tender Return
Cost Summary and Elemental Cost Build-up (showing rates
and prices)
c. Appendix H – Contractors Early Warning Register
d. Appendix I –  Works Programme 
• the following documents:
a. [    ] 
and in the event of a conflict between the requirements set out in this Article 3 the
requirements have precedence in numerical order in this Article 3, except where
specifically provided otherwise in this contract. The requirements within the
documents comprised in the Scope as regards the scope or extent of the works
are where possible to be interpreted as complementary but in the event of a
conflict that which describes a greater extent or scope of works takes
precedence. 
Page 221

Page 222

Page 142 of 208 
4. Governing Law 
a. The formation, existence, construction, performance, validity and all
aspects whatsoever of this agreement or any term of it (including
non-contractual disputes or claims) shall be governed by the laws of
Scotland.
b. The courts of Scotland shall have exclusive jurisdiction to settle any
disputes (including non-contractual disputes or claims), which may
arise out of or in connection with this agreement. The parties
irrevocably agree to submit to that jurisdiction. 
Signed by 
Name [printed]  .............................................................................................................. 
Position ......................................................................................................................... 
On behalf of (Client) ...................................................................................................... 
Witness Signature  ........................................................................................................ 
Witness Name ……………………………………………………………………………... 
Address  ........................................................................................................................ 
...................................................................................................................................... 
Date …………………………………… 
and   
Signed by ………………………………………………………………………………………. 
Name [printed]  .............................................................................................................. 
Position ......................................................................................................................... 
On behalf of (Contractor) ............................................................................................... 
Witness Signature  ........................................................................................................ 
Witness Name ……………………………………………………………………………... 
Address   ....................................................................................................................... 
…………………………………………………………………………………………………… 
Page 222

Page 223

Page 143 of 208 
Date ……………………………………   
Page 223

Page 224

Page 144 of 208 
3 CONTRACT DATA – PART ONE 
Part one – Data Provided by the Client 
Statements given in all contracts
1. General
The conditions of contract are the core clauses and the clauses for the following main Option, the option
for resolving and avoiding disputes and secondary options of the NEC4  A Engineering and
Construction Contract June 2017 (with January 2019 and October 2020 amendments)  as amended by
the terms of Part A of the Appendix to this letter
Main Option  A
Option for resolving and avoiding disputes W2
Secondary Options [X1, X2, X3, X4, X5, X6, X7, X8, X9, X10, X11,
X12, X13, X14, X15, X16, X17, X18, X20,
X21,Y(UK)1] [DELETE WHERE APPROPRIATE]
Y(UK)2 and Z 
The works are [INSERT]   
The Client is
Name Highlands & Islands Enterprise
Address for communications
An Lòchran,
10 Inverness Campus, 
Inverness,
IV2 5NA 
Address for electronic communications  [INSERT] 
The Project Manager is 
Name [INSERT]
Address for communications
[INSERT]
Address for electronic communications  [INSERT]
The Supervisor is
Page 224

Page 225

Page 145 of 208 
Name [INSERT]
Address for communications
[INSERT]
Address for electronic communications  [INSERT] 
The Scope is in Appendices [INSERT]
The Site Information is in Appendices [INSERT].
The boundaries of the site are Specified in [INSERT].
The language of this contract is English
The law of the contract is the law of Scotland and subject to the jurisdiction of the Courts of
Scotland.
The period for reply is [INSERT] weeks except that 
The period for reply for   is                               
The period for reply for  is
The period for reply for  is 
The following matters will be included in the Client's Early Warning Register:
[INSERT] 
Early Warning meetings are to be held at intervals of no less than [INSERT] 
2. The Contractor's main responsibilities   
The key dates and conditions to be met are
Condition to be met  Key date
[INSERT] 
3. Time 
The starting date is [INSERT]
The access dates are 
Page 225

Page 226

Page 146 of 208 
Part of the Site date
[INSERT] 
The Contractor submits revised programmes at intervals no longer than [INSERT]. 
If the Client has decided the completion date for the whole of the works 
The completion date for the whole of the works is [INSERT] 
Taking over the works before the Completion Date
The Client is / is not willing to take over the works before the Completion Date (Delete as applicable) 
If no programme is identified in part two of the Contract Data
The period after the Contract Date within which the Contractor is to submit a first programme for acceptance is
[INSERT] 
4. Quality Management 
The period after the Contract Date within which the Contractor is to submit a quality policy statement and quality
plan is [INSERT] 
The period between completion of the whole of the works and the defects date is [INSERT]
The defect correction period is  [INSERT] weeks except that 
The defect correction period for    is                               
The defect correction period for    is
The defect correction period for    is 
5. Payment
The currency of this contract is the Pounds Sterling (£)
The first assessment date is [INSERT]
The assessment interval is [the period between the last assessment date and the last working day
of the preceding month/[INSERT].
The interest rate is [INSERT]% per annum above the base rate of the [Bank of England/INSERT]. 
Page 226

Page 227

Page 147 of 208 
6 Compensation events
The place where weather is to be recorded is: [INSERT]
The weather measurements to be recorded for each calendar month are
o The cumulative rainfall (mm)
o The number of days with rainfall more than 5mm
o The number of days with minimum air temperature less than 0 degrees Celsius
o The number of days with snow lying at [INSERT]hours GMT
And these measurements: [INSERT]
The weather measurements are supplied by: [INSERT]
The weather data are the records of past weather measurements for each calendar month which were
recorded at [INSERT]and which are available from the [INSERT] 
Where no recorded data are available
Assumed values for the ten year weather return weather data for each weather measurement for each
calendar month are [INSERT] 
If Option A or B is used 
The value engineering percentage is 50% unless another percentage is stated here, in which case it is
100% 
If there are additional compensation events
These additional compensation events [INSERT]   
8 Liabilities and insurance
If there are additional Client's liabilities
These are additional Client's liabilities [INSERT] 
The minimum limit amount of cover  for insurance against  loss of or damage to property (except the
works, Plant and Materials and Equipment) and liability for bodily injury to or death of a person (not an
employee of the Contractor) arising from or in connection with the Contractor Providing the Works  for
any one event is [INSERT]. 
The minimum amount of cover for insurance against death of or bodily injury to employees of the
Contractor arising out of and in the course of their employment in connection with the contract for any
one event is [INSERT]. 
Page 227

Page 228

Page 148 of 208 
If the Client is to provide Plant and Materials 
The insurance against loss of or damage to the works Plant and Materials is to include cover for Plant and
Materials provided by the Client for an amount of [INSERT] 
If the Client is to provide any insurances stated in the Insurance Table 
The Client provides these insurances from the Insurance Table:
1 Insurance against  [INSERT]
Minimum amount of cover is 
The deductibles are 
2 Insurance against  
Minimum amount of cover is 
The deductibles are 
If additional insurances are to be provided 
The Client provides these additional insurances 
1 Insurance against  [INSERT]
Minimum amount of cover is 
The deductibles are 
2 Insurance against  
Minimum amount of cover is 
The deductibles are 
The Contractor provides these additional insurances
1 Insurance against  [INSERT]
Minimum amount of cover is 
The deductibles are 
2 Insurance against  
Minimum amount of cover is 
The deductibles are 
Resolving and avoiding disputes 
The tribunal is [INSERT] 
If the tribunal is arbitration 
The arbitration procedure is [INSERT]
The place where the arbitration is to be held is [INSERT]
Page 228

Page 229

Page 149 of 208 
The person or organisation who will choose an arbitrator if the Parties cannot agree a choice or if the
arbitration
procedure does not state who will choose an arbitrator is [INSERT] 
The Senior Representatives of the Client are 
Name (1) [INSERT]
Address for communications
[INSERT]
Address for electronic communications  [INSERT]
Name (2)  [INSERT]
Address for communications
[INSERT]
Address for electronic communications  [INSERT] 
The Adjudicator is 
Name [INSERT]
Address for communications
[INSERT]
Address for electronic communications  [INSERT] 
The Adjudicator nominating body is [INSERT] 
X1: Price adjustment for inflation  (used only with options A, B, C and D)
If Option X1 is used
The proportions used to calculate the Price Adjustment Factor are [INSERT]
0.    linked to the index for [INSERT]
0.
0.
0.
0.
0.
0.    non-adjustable
1.00
The base date for indices is [INSERT]
These indices are [INSERT] 
X3: Multiple Currencies (used only with Options A and B)
Page 229

Page 230

Page 150 of 208 
If Option X3 is used
The Client will pay for the items or activities listed below in the currencies stated
items and activities other currency  total maximum payment in the
currency   
The exchange rates are those published in [INSERT]
on [INSERT] (date) 
X5: Sectional Completion
If Option X5 is used 
The completion date for each section of the works is 
section  description  completion date 
X6: Bonus for Early Completion 
If Option X6 is used without Option X5
The bonus for the whole of the works is [INSERT] per day 
If Option X6 is used with Option X5
The bonus for each section of the works is 
section description amount per day
(1)  
(2)  
(3)  
(4)  
The bonus for the remainder of the works is 
X7: Delay Damages 
If Option X7 is used without Option X5
Delay damages for Completion of the whole of the works are [INSERT] per day 
Page 230

Page 231

Page 151 of 208 
If Option X7 is used with Option X5
section  description  amount per day 
1  
2  
3  
The delay damages for the remainder of the works are [INSERT] per day 
X8: Undertakings to the Client or Others
N/A - See Z clauses 
X10: Information modelling 
If Option X10 is used
If no information execution plan is identified in part two of the Contract Data
The period after the Contract Data within which the Contractor is to submit a first Information Execution Plan
for acceptance is [INSERT].
The minimum amount of insurance cover for claims made against the Contractor arising out of its failure to
use the skill and care normally used by professional's providing information similar to the Project Information
is, in respect of each claim [INSERT].
The period following Completion of the whole of the works or earlier termination for which the Contractor
maintains insurance for claims made against it arising out of its failure to use the skill and care is [INSERT]. 
X12: Multiparty Collaboration
If Option X12 is used
The Promoter is [INSERT]
The Schedule of Partners is in [INSERT]
The Promoter's objective is [INSERT]
The Partnering Information is in [INSERT] 
X13: Performance bond
If Option X13 is used
The amount of the performance bond is an amount equal to [10% of the Tendered Total of the
Prices/INSERT] 
X14: Advance payment to Contractor 
If Option X14 is used
The amount of the advanced payment is [INSERT]
Page 231

Page 232

Page 152 of 208 
The period after the Contract Date from which the Contractor repays the instalments in assessments is
[INSERT]
The instalments are [INSERT] (either an amount or a percentage of the payment otherwise due)
An advanced payment bond [is/is not] required (delete as applicable) 
X15: The Contractor's design
If Option X15 is used
The period for retention following Completion of the whole of the works or earlier termination is [INSERT] 
The period following Completion of the whole of the works or earlier termination for which the Contractor
maintains insurance for claims made against it arising out of its failure to use the skill and care is [12 years /
INSERT]] 
X16: Retention 
If Option X16 is used
The retention free amount is [INSERT]
The retention percentage is [INSERT%].
Retention bond the Contractor may/may not give the Client a retention bond (delete as applicable) 
X17: Low performance damages
If Option X17 is used 
The amounts for low performance damages are 
amount  performance level 
for 
for 
for 
for   
X18: Limitation of liability 
If Option X18 is used 
The Contractor’s total liability to the Client for all matters arising under or in connection with this contract,
other than excluded matters, is limited to: Unlimited
The end of liability date is [12 / INSERT] years after the Completion of the whole of the works. 
X20: Key Performance Indicators 
If Option X20 is used
The incentive schedule for Key Performance Indicators is in [INSERT]
A report of performance against each Key Performance Indicator is provided at intervals of [INSERT]
months. 
YUK(1): Project Bank Account 
Page 232

Page 233

Page 153 of 208 
Charges made and interest paid by the project bank
The Contractor [is/is not] to pay any charges made and to be paid any interest paid by the project bank
(Delete as applicable) 
YUK(2): The Housing Grants, Construction and Regeneration Act 1996
If Option YUK(2) is used and the final date for payment is not 14 days after the date on which payment
becomes due
The period for payment is [INSERT] days after the date on which payment becomes due.   
Z: Additional conditions of contract  - See appendix A
Page 233

Page 234

Page 154 of 208 
4 CONTRACT DATA – PART TWO 
1  General 
The Contractor is
Name [INSERT]
Address for communications
[INSERT] 
Address for electronic communications  [INSERT] 
The fee percentage is [INSERT]%
The working areas [INSERT]
The key persons are
1 Name  [INSERT]
Job 
Responsibilities  
Qualifications  
Experience  
2 Name  [INSERT]
Job 
Responsibilities  
Qualifications  
Experience  
3 Name  [INSERT]
Job 
Responsibilities  
Qualifications  
Experience  
The following matters will be included in the Early Warning Register: [INSERT]
2  The Contractor's main responsibilities 
If the Contractor is to provide scope for its design
Page 234

Page 235

Page 155 of 208 
The Scope provided by the Contractor for its design is in [INSERT] 
3 Time 
If a programme is to be identified in the Contract Data 
The programme identified in the Contract Data is [INSERT]
If the Contractor is to decide the completion date for the whole of the works
The completion date for the whole of the works is [INSERT]
5 Payment 
If Option A or C is used
• The activity schedule is in [INSERT].
If Option A, B, C or D is used
• The tendered total of the Prices is as detailed in [INSERT] 
6 Resolving and avoiding disputes 
The Senior Representatives of the Contractor are 
Name (1) [INSERT]
Address for communications
[INSERT]
Address for electronic communications  [INSERT]
Name (2)  [INSERT]
Address for communications
[INSERT]
Address for electronic communications  [INSERT]
X10: Information modelling
If Option X10 is used
If an information execution plan is to be identified in the Contract Data
The information execution plan identified in the Contract Data is [INSERT]
Y(UK)(1): Project Bank Account
If Option Y(UK)1 is used
The project bank is [INSERT]
named suppliers are [INSERT]
Page 235

Page 236

Page 156 of 208 
Data for the Short Schedule of Cost components
The people rates are 
Category of person  unit rate 
[INSERT]     
The published list of Equipment is the edition current at the Contract Date of the list published by
[INSERT]
The percentage for adjustment for Equipment in the published list is [INSERT] % (state plus or minus).
The rates for other Equipment are
Equipment  Rate 
[INSERT] 
The rates for Defined Cost of manufacture and fabrication outside the Working Areas by the Contractor
are 
Category of person  rate 
[INSERT] 
The rates for Defined Cost of design outside the Working Areas are
Category of employee  rate 
[INSERT] 
The rates for Defined Cost of design outside the Working Areas are
Page 236

Page 237

Page 157 of 208 
Category  rate 
[INSERT] 
Page 237

Page 238

Page 158 of 208 
5 APPENDIX A - AMENDMENTS TO THE NEC4ENGINEERING
AND CONSTRUCTION CONTRACT JUNE 2017 (WITH
AMENDMENTS JANUARY 2019 AND OCTOBER 2020) 
The terms of the NEC4 Engineering and Construction Contract June 2017 (with amendments January
2019 and October 2020) shall be amended as follows: 
Clause 11.2 (5)
Insert at the end of this clause:
"A Corrupt Act is also if the Contractor does any of the following:
• is convicted or has been convicted of a criminal offence relating to the conduct of its business or profession
• commits or is found to have committed an act of grave misconduct in the course of its business or
profession
• fails or has failed to comply with any obligations relating to the payment of any taxes or social security
contributions
• has made any serious misrepresentations in the tendering process for any project or matter in which the
public sector has or had a significant participation
• fails to obtain any necessary licences or to obtain or maintain membership of any relevant body, or
• substantially changes its corporate structure or otherwise changes its legal form or there is a change of
control as defined by section 450 of the Corporation Tax Act 2010 (any such case being a “Change of
Control”) and such a Change of Control gives the Employer reasonable grounds for concern regarding the
new entity's financial standing, ability to Provide the Works and/or security issues
• commits any breach of any Law including, without limitation, (i) any breach of the Employment Relations
Act 1999 (Blacklists) Regulations 2010 or section 137 of the Trade Union and Labour Relations
(Consolidation) Act 1992; and (ii) any breach of the Data Protection Act 1998 by unlawfully processing
personal data in connection with any blacklisting activities 
• offers to give or agrees to give any person any gift or consideration of any kind as an inducement or reward
for doing, forbearing to do, or for having done or forborne to do any act in relation to the obtaining or
execution of this contract or any other contract for the Client or Her Majesty’s Service or for showing favour
or disfavour to any person in relation to this or any other contract for the Client or Her Majesty’s Service
• enters into this contract or any other contract with the Client or with a person or body employed by the
Client or acting on its behalf or with Her Majesty’s Service in connection with which commission has been
paid or agreed to be paid by him or on his behalf, or to his knowledge, unless before this contract is made
particulars of any such commission and of the terms and conditions of any agreement for the payment
thereof have been disclosed in writing to the Employer, or
Page 238

Page 239

Page 159 of 208 
• commits an offence under the Bribery Act 2010 in relation to this contract or any other contract with the
Client or Her Majesty’s Service" 
Clause 11.2(35)
Insert new clause as follows:
“Elemental Build Up is the Elemental Build Up provided in [INSERT].” 
Clause 11.2(36)
Insert new clause as follows:
“Project Documents” mean any agreements that the Client may at any time enter into with a third party in relation
to the works and/or the Site or other agreements that are relevant to the works or the Site including those
referred to at Clause Z18 (the terms of which shall be deemed to be within the Contractor’s knowledge) and any
method statements referred to in the aforementioned agreements; 
Clause 11.2(37)
Insert a new clause as follows:
“Necessary Consents are the planning permissions, road construction consents, building warrants and any other
permissions, warrants, approvals, consents, licences and the like which may be necessary from any statutory
body or authority; any utility company or any other person to enable the works to be carried out.” 
Clause 11.2.(38)
Insert a new clause as follows:
“Applicable Law means (i) any statute, law, order, regulation, by-law, statutory instrument, decision, rule, consent
or delegated or subordinate legislation or any legislative act of the Westminster or Scottish Parliaments, Council
of the European Union or the European Commission which has legal effect with regard to this contract, the
works, the Site or the parties’ rights and obligations, or any modification, supplement, amendment or
replacement of any of the forgoing having the force of law; and (ii) the Necessary Consents obtained and to be
obtained to carry out the works. All references in this contract to “applicable laws” shall be to Applicable Law.”
Clause 11.2(39)
Insert a new clause as follows:
“CDM Regulations means the Construction (Design and Management) Regulations 2015, together with any
guidance or codes of practice issued thereon by the Health and Safety Executive.” 
Clause 11.2(40) 
Insert a new clause as follows:
“Subconsultant means a person or organisation who has a contract with the Contractor to design part of or
provide services in connection with the works.” 
Page 239

Page 240

Page 160 of 208 
Clause 11.2(41)
Insert a new clause as follows:
"COVID-19" means COVID-19 disease/SARS-COVID-2 virus.
Clause 11.2(6)
Amend clause 11.2(6) second bullet by replacing “applicable law” with “Applicable Law”. 
Clause 12.5
Insert a new clause as follows:
“Save to the extent that the context or the express provisions of this Agreement require otherwise, in this
Agreement:
any phrase introduced by the words "including", "include", "in particular" or any similar expression
shall be construed as illustrative only and shall not be construed as limiting the generality of
any preceding words;
the words "other" and "otherwise" shall not be construed ejusdem generis with any foregoing words
where a wider construction is possible;” 
Clause 17.1
Delete Clause 17.1 and replace it with the following:
“The Contractor checks the Scope upon receipt or production by the Contractor.  The Project Manager or the
Contractor notifies the other as soon as either becomes aware of any conflict, ambiguity, discrepancy, error,
omission, inadequacy, divergence or inconsistency in or between or amongst any requirements of this contract
(including the Scope and Site Information) and any Applicable Law or Necessary Consents. The Project Manager
gives an instruction resolving the conflict, ambiguity, discrepancy, error, omission, inadequacy, divergence or
inconsistency. The Contractor shall not be entitled to a compensation event as a result of any such conflict,
ambiguity, discrepancy, error, omission, inadequacy, divergence or inconsistency unless the Project Manager
gives an instruction changing the Scope to correct an error or omission in the Scope supplied by the Client." 
Clause 20
Insert at the end of clause 20.1:
“, this contract, the Necessary Consents and Applicable Law and approvals from Others and in a proper and
workmanlike manner with new materials which are suitable for their purposes and in accordance with Applicable
Law. The Contractor proceeds regularly and diligently with the works. 
Clause 21
Add the following new clauses:
“21.4 The Contractor shall not, unless specifically instructed to do so and the Contractor has advised the
Project Manager  in writing that the material is prohibited under this clause, specify or approve for use,
Page 240

Page 241

Page 161 of 208 
any prohibited material or product for use in relation to the works and does not authorise or approve the
specification or use by others of any products or materials not in conformity with relevant British or
European Standards or Codes of Practice or which at the time of use are widely known to builders or
designers of the relevant discipline within the United Kingdom to be deleterious to health and safety or
to the durability of buildings and/or other structures and/or finishes and/or plant and machinery or any
parts of them in the particular circumstances in which they are used. 
21.5 If, in the performance of its obligations under this contract, the Contractor becomes aware that it or any
other person has specified or used or authorised or approved the specification or use by others of any
such products or materials as are referred to in clause 21.4 the Contractor notifies the Project Manager
in writing forthwith. 
21.6 The Contractor, warrants that the design of the works has been prepared and will be prepared in
accordance with all the reasonable skill, care and diligence to be expected of a competent and
appropriately qualified engineer or architect or, if relevant, other appropriately qualified designer
experienced in exercising such responsibilities in relation to work of the same type, complexity, value
and timescale as the works and for a site of a similar location, nature and size as the Site in exercising
its responsibilities and that the Contractor exercises (and warrants that it has exercised) all the
reasonable skill, care and diligence to be expected of a competent and appropriately qualified engineer
or architect or, if relevant, other appropriately qualified designer experienced in exercising such
responsibilities in relation to work of the same type, complexity, value and timescale as the works and
for a site of a similar location, nature and size as the Site. 
21.7  The Contractor provides continual supervision of the works and performs and provides everything
necessary for the organisation and co-ordination of the works.” 
Clause 26.3
Insert at the end of the clause:
“The Contractor provides the Project Manager with certified true copies of subcontracts entered into between the
Contractor and any Subcontractors (including Subconsultants) in connection with the works as required by the
Project Manager.” 
Clause 27.5
Insert a new Clause 27.5
“The Contractor is responsible for obtaining all Necessary Consents (subject to clause Z18) insofar as the same
have not already been obtained at the Contract Date and for complying with all conditions pertaining to the
Necessary Consents (whether procured before or after the Contract Date).” 
Page 241

Page 242

Page 162 of 208 
Clause 29A
Insert a new Clause 29A as follows:
“Covid-19
29A.1 Notwithstanding any other provision in this contract, the Parties acknowledge the existence of COVID-
19 and the considerable measures that, at the date of this contract, have been brought into effect by
countries across the world to seek to address the risks and challenges posed by COVID-19.
29A.2 The Contractor confirms that:
• prior to entering into this contract it has evaluated fully every aspect of the possible impact of
COVID-19 on its obligations under this contract taking into account the latest understanding
and Scottish Government legislation and/or guidance in respect of COVID-19 and its impact as
at the Contract Date, including but not limited to:
o the supply of labour and materials 
o the impact of the wide-ranging measures taken by governments to address the risks
and challenges posed
o any other issues arising from COVID-19 that may impact on its ability to discharge its
obligations under this contract,
and has taken all appropriate measures to ensure that it can fulfil its obligations under and in
accordance with this contract and
• no failure on the part of the Contractor to take into account that impact at the Contract Date
entitles the Contractor to a change in the Prices, the Completion Date and the Key Dates.” 
Clause 33.1
Replace the word "The" at the start of the clause with "Subject to the other provisions of this clause 33.1 and any
constraints set out in the Scope , the"; and insert a new sentence at the end "Access to and use and of the Site
shall be subject to the constraints and phasing provisions referred to in the Contract including Key Dates,
Contract Data Part 1 and Scope. " 
Clause 50.1
Delete the existing second sentence and insert:
“The first assessment date is the date prescribed within the Contract Data Part 1.” 
Clause 50.2
After the words "Project Manager" in line 1, insert "not less than seven days" 
Page 242

Page 243

Page 163 of 208 
Clause 60.1
Delete “The” at the beginning of the clause and replace with: 
“Save to the extent that (a) such events are not consequent upon or necessitated by any act, negligence,
omission, default, breach of contract or breach of statutory duty of the Contractor, its sub-contractors or suppliers
or those for whom it is responsible whether arising out of or in connection with this contract or otherwise; (b)
subject to any provision to the contrary in this contract; and (c) save to the extent the Contractor is stated to be
responsible for or assumed the risk of or for or to have allowed for such matters), the” 
Clause 60.1(20)
Delete the clause. 
Clause 60.1(22)
Insert a new clause as follows:
“60.1(22) the resurgence of COVID-19 and/or other similar virus and/or notifiable disease resulting in the
implementation of new or further (i) public health measures (whether in the form of guidance or legislation) and/or
(ii) construction industry specific health and safety guidance and/or legislation after the Contract Date which
stops the Contractor completing the whole of works by the date shown on the Accepted Programme “ 
Clause 60.1(23)
Insert a new clause as follows:
“60.1(23) a change in or the imposition of additional taxes, duties, tariffs, levies, fees and/or customs charges on
Plant and Materials or Equipment imported in the United Kingdom from the European Union ("Imported Plant and
Materials") arising as a direct result of the passing of the European Union (Withdrawal Agreement) Act 2020
and/or any delay and/or disruption to the importation of Imported Plant and Materials (or any component part
thereof) into the United Kingdom (including, but not limited to, the passing through HM Customs and Excise),
which is  incurred after the UK Withdrawal Date, but which is not as a result of  any act or omission of the
Contractor, but only to the extent the Contractor takes reasonable steps to mitigate the effects of such
implications on the Works and/or the Completion Date and/or the Prices.  For the purpose of this clause 60.1(23)
"UK Withdrawal Date" means 31st December 2020 or after the UK Withdrawal Date from the European Union.” 
Clause 61.8  
Insert a new clause as follows
“61.8  The Parties agree that for 
• compensation events arising under clause 60.1(4) where the reason for the instruction is
the resurgence of COVID-19 and/or other similar virus and/or notifiable disease resulting
in the implementation of new or further public health measures after the Contract Date in
connection therewith; and/or
Page 243

Page 244

Page 164 of 208 
• compensation events arising under 60.1(22) 
any changes to the Prices are assessed in accordance with clause 63.1A"
Clause 62.2
Insert at the end of the clause:
“As part of the quotation, the Contractor submits a revised Elemental Build Up (with any changes to the previous
version of the Elemental Build Up being highlighted) to show any change to the build up of the Total of the
Prices.” 
Clause 63.1
Delete the clause and insert:
“The changes to the Prices are assessed as the effect of the compensation event on the relevant component
costs within the Elemental Build Up and the resulting Fee.” 
Insert new clause 63.1A
"63.1A Notwithstanding any other provision of this contract, any changes to the Prices for the compensation
events referred to in clause 61.8 are assessed in accordance with clause 63.1 but the Contractor acknowledges
that the changes to the Prices are restricted to the heads of recoverable cost set out in [the Covid-19 Allowable
Costs Schedule]."   
Clause 63.3
Delete the clause. 
Clause 63.9
Delete the words “Defined Cost and" 
Clause 63.10
Insert at the start of the clause "Without prejudice to clause 17.1,". 
Clause 63.14
At the end of the clause insert:
“The change to the Price for each affected activity is calculated as follows:
(1) where the Elemental Build Up contains a relevant rate, that rate is applied to any change in quantities
and the Price of the activity is adjusted accordingly;
(2)  where there is no rate within the Elemental Build Up, the Project Manager either:
(a)  instructs the Contractor to carry out such competitive tender exercise as the Project Manager
deems appropriate (having regard to the relative value and importance of the activity) to
Page 244

Page 245

Page 165 of 208 
establish a price for any work required that is additional to the works within the activity set out
in the Scope and the price for the activity shall be adjusted accordingly;
(b) negotiates and agrees with the Contractor a lump sum in respect of the change to the Price; or
(c) does any combination of the actions referred to in paragraphs (a) or (b) above as the Project
Manager deems appropriate to assess the change to the Price.” 
Clause 90.2
At the Termination Table set out in clause 90.2, insert:
"or R23" 
next to the second instance of "R21" in the first row of the table under 'Reason' column. 
Clause 91.6
Insert the following at the end of the third bullet point under clause 91.6 before "(R20)":
"provided that where the reason for the instruction is the resurgence of COVID-19 disease/ SARS-COVID-2 virus
and/or other similar virus and/or notifiable disease resulting in the implementation of new or further public health
measures in connection therewith after the Contract Date, the Contractor may not terminate" 
Clause 91.7
Insert the following after the fourth bullet point under clause 91.7 but before "(R21)":
"or 
• Is attributable to the resurgence or Covid-19 disease/ SARS-COVID-2 virus and/or other similar virus
and/or notifiable disease resulting in the implementation of new or further public health measures in
connection therewith after the Contract Date" 
Clause 91.9
Insert new clause 91.9 as follows:
“91.9 The Client may terminate where the assessment (or cumulative assessment) of delay in respect of a
compensation event 60.1(22) exceeds [ INSERT  months   ] (R23)” 
Option Clause X2
Where secondary option X2 (Change in Law) is selected to apply:
Insert the following at the end of clause X2.1:
"Notwithstanding any other provision of this contract where the change in the law of the country in which the Site
is located occurs as a direct result of the resurgence of COVID-19 disease/ SARS-COVID-2 virus and/or other
similar virus and/or notifiable disease any change to the Prices is assessed in accordance with clause 63.1A the
Contractor's only entitlement to relief in terms of a change to the Prices and/or a delay to the Completion Date or
any Key Date is in terms of clause 60.1(22)."   
Page 245

Page 246

Page 166 of 208 
“The Contractor notifies the Project Manager of a compensation event for a change in the law in accordance with
Clause 61.3." 
Option Clause X4
Where secondary option X4 is selected to apply:
Insert new clause X4.3 as follows:
“X4.3 If the guarantee was not given to the  Client within 4 weeks of the Contract Date, 20% of the Price for
Work Done to Date is retained in assessments of the amount due until the guarantee is given to the
Client." 
Option Clause X15
Where secondary option X15 is selected to apply:
Delete existing clause X15.1 and insert the following:
“X15.1 The Contractor is not liable for Defects in the works due to his design so far as he proves that he has
used the level of skill and care set out in clause 21 of this contract, in the carrying out of such design.”
Delete clause X15.5 
Option Clause X18
Where secondary option X18 is selected to apply: 
DELETE X18.2, X18.3 and X18.4. 
In X18.5, DELETE “as stated in the contract” in line five, and after the final bullet point, ADD new bullet points as
follows:
• "fraud, gross negligence, wilful misconduct, wilful default, or breach of statutory duty or of Applicable
Law, on the part of the Contractor, 
• loss of or damage to third party property
• bodily injury to or death of a person
• any matter which is or should be covered by the insurances to be taken out and maintained by the
Contractor pursuant to clause 83 (that is, whether or not the insurance policy/policies respond) and save
for the professional indemnity insurance  required by clause Z15; and
• the carrying out and completion of the works, including the cost of remedying any Defects; “ 
The following new clauses shall be inserted: 
Z1. Communications from the Client The Contractor accepts communication from the Client only from
the Project Manager and the Supervisor.  
Z2. Verbal communications The Contractor seeks written confirmation of any verbal
communication that he considers to give rise to a compensation
Page 246

Page 247

Page 167 of 208 
event before acting on such communication, unless to avoid
imminent death, injury or loss or damage to property.
Z3. Method of Working The Contractor accepts the risk of any method of working
proposed by him or contained in the Scope. The impossibility of
any method of working placed at the Contractor’s risk and any
alternative work to avoid the impossibility are not compensation
events.
Z4. Assignation The Contractor does not assign the whole or any part of or any
benefit or interest in the contract including any monies due or
becoming due to the Contractor unless the Client (in its absolute
discretion) consents to such assignation.  The Client may at any
time and from time to time assign in whole or in part its rights and
remedies arising out of or in connection with this contract without
the Contractor's consent. 
Z5. Works done before the starting
date
The Contractor agrees and acknowledges that the provisions of
the contract apply to all design, services, work and other
activities carried out by the Contractor in respect of the works
regardless of whether such design, services, work and other
activities is carried out prior to the starting date.
Z6. Not used  
Z7. Applications for payment The Contractor provides with each application for payment
details of how the sum applied for is made up and such evidence
of entitlement and value as is prescribed in this contract or in an
instruction or, otherwise, as the Project Manager reasonably
requires.  The Project Manager need not certify any sum for
which the required details or evidence are not provided, and,
notwithstanding clauses 51.3 and 51.4, no interest attaches to
the difference between the sum assessed by the Project
Manager and any greater sum found due after submission of the
required details or evidence.
Z8. Status of certification by Project
Manager
The assessment and certification by the Project Manager and
payment of any sum by the Client is not an admission of liability
or value or a waiver of any right and may be re-opened and
corrected by the Project Manager at any time prior to the defects
date.
Z9. Deduction/ Set-Off The Client may deduct or set-off against any monies due to the
Contractor any sums that the Contractor is liable to pay to the
Client arising out of or connected with the contract or any other
Page 247

Page 248

Page 168 of 208 
contract between them or in delict.  If the sum is unascertained or
the matter is disputed the Client or its representative, acting
reasonably having regard to all the circumstances, estimates the
sum.
Z10. Deduction in respect of Tax The Client may withhold from payment sums on account of the
Contractor’s actual or potential liability for taxation as required
under the statutes and regulations in force.  As a condition
precedent to receiving payment without deduction under this sub-
clause, the Contractor provides such tax details and certificates
as the law prescribes or the Client reasonably requires.
Z11. Notification of Compensation
Events
Where the Contractor or the Project Manager intends to notify a
compensation event they notify that compensation event in a
written notice headed “Notification of Compensation Event”. 
Such notice issued is a document separate from other
correspondence or other documentation issued by that party. 
The compensation event being notified is clearly identified and
described within that notice.
Z12. Keeping of records prior to
acceptance of a compensation
event
Until such time as a quotation is accepted in respect of a
compensation event, the Contractor keeps a daily record of
labour, Plant and Materials and Equipment expended by him in
carrying out the instruction and submits them the next Business
Day to the Project Manager for the purpose only of verification.
Z13. Collateral Warranties 
Z13.1 Contractor Collateral Warranties.
The Contractor shall deliver to the Client forthwith upon each
demand and in any event within 21 days of each such request
collateral warranty agreements in the form of the draft collateral
warranty at Appendix [INSERT] duly completed in accordance
with instructions contained therein and executed in “self proving
form” as defined under the Requirements of Writing (Scotland)
act 1995 by the Contractor in favour of a) each first tenant of the
whole or substantial part of Site; b) each first purchaser of the
whole or substantial part of the Site; c) the Funder(s) of the
parties referred to in paragraphs a) and b) above; d) [INSERT] . 
If the Contractor fails to deliver the requested collateral warranty
agreements within 14 days of a written request from the Project
Manager to do so, 20% of the Price for Work Done to Date is
retained in assessments of the amount due until the Contractor
Page 248

Page 249

Page 169 of 208 
has so delivered such collateral warranties. 
Z13.2 Sub-Consultant Collateral Warranties
The Contractor shall deliver to the Client forthwith upon each
demand and in any event within 21 days of each such request:
(a)  collateral warranty agreements in
the form of the draft collateral
warranty at Appendix [INSERT] 
duly completed in accordance with
instructions contained therein and
executed in “self proving form” as
defined under the Requirements of
Writing (Scotland) act 1995 by the
sub-consultants employed by the
Contractor, and if applicable the
Contractor, in favour of the Client;
and
(b) collateral warranty agreements in
the form of the draft collateral
warranty at Appendix [INSERT]
duly completed in accordance with
instructions contained therein and
each executed in “self proving form”
as defined under the Requirements
of Writing (Scotland) act 1995 by
the sub-consultants employed by
the Contractor, and if applicable the
Contractor, in favour of a) each first
tenant of the whole or substantial
part of Site; b) each first purchaser
of the whole or substantial part of
the Site; c) the Funder(s) of the
parties referred to in paragraphs a)
and b) above; d) [INSERT]
If the Contractor fails to deliver the requested collateral warranty
agreements within 14 days of a written request from the Project
Manager to do so, 20% of the Price for Work Done to Date is
retained in assessments of the amount due until the Contractor
has so delivered such collateral warranties.
Page 249

Page 250

Page 170 of 208 
Z13.4 Design Subcontractor Collateral Warranties
The Contractor shall deliver to the Client forthwith upon each
demand and in any event within 21 days of each such request
collateral warranty agreements in the form of the draft collateral
warranty at Appendix [INSERT]  duly completed in accordance
with instructions contained therein and each executed in “self
proving form” as defined under the Requirements of Writing
(Scotland) act 1995 by the Subcontractors with design
responsibility, and if applicable the Contractor, employed by the
Contractor in favour of a) the Client, b) each first tenant of the
whole or substantial part of Site; c) each first purchaser of the
whole or substantial part of the Site; d) the Funder(s) of the
parties referred to in paragraphs b) and c) above; d) [INSERT].
If the Contractor fails to deliver the requested collateral warranty
agreements within 14 days of a written request from the Project
Manager to do so, 20% of the Price for Work Done to Date is
retained in assessments of the amount due until the Contractor
has so delivered such collateral warranties.
Z14 Copyright 
Z14.1 The Contractor grants to the Client an irrevocable, royalty-free,
non-exclusive licence (carrying the right to grant sub-licences) to
copy and use the plans, drawings, specifications, calculations,
documents and other written or recorded material connected with
the works and the Site and produced by the Contractor or on the
Contractor’s behalf (“the Documents”) and to use and reproduce
the Documents in connection with the works, the Site and/or any
construction project in which the Client has an interest provided
that the Contractor shall have no liability for any use of such
Documents for purposes other than for those purposes in respect
of which they were created or provided or such purposes as are
reasonably foreseeable. 
Z14.2 The Contractor hereby undertakes to procure from sub-
contractors, the grant of the necessary licences in favour of the
Client to give effect to clause Z14.1. 
Z14.3 The Contractor provides to the Client upon written request such
copies from or extracts of all or any of the Documents as the
Client reasonably requests at no cost to the Client. 
Z14.4 The Contractor hereby waives any Moral Rights they may have
Page 250

Page 251

Page 171 of 208 
pursuant to the Copyright Designs and Patents Act 1988 in the
Documents and shall procure that all other persons shall waive
any Moral Rights they have in the Documents.
Z15 Professional Indemnity Insurance The Contractor effects and maintains professional indemnity
insurance for any one occurrence or series of occurrences
arising out of any one event arising out of this Agreement in the
amount of not less than [INSERT]  million pounds (£[ INSERT 
],000,000) sterling from the starting date and thereafter for the
period of twelve years from the date of Completion of the works
provided always that such insurance is available to similar
contractors at commercially reasonable rates and terms.
The Contractor provides the Client, upon request satisfactory
evidence of such insurance.
The Contractor complies with all conditions and obligations of
any such insurance policy and advises the Client forthwith if such
insurance ceases to be maintained.   If for any period such
insurance is not available at commercially reasonable rates the
Contractor informs the Client and shall obtain in respect of such
premium such reduced level of insurance as is available to it.
Z16. Performance Bond The Contractor delivers the performance bond required by the
Client in the form set out in [Appendix /INSERT] executed by all
parties other then the Client in “self proving form” as defined
under the Requirements of Writing (Scotland) act 1995 within 21
days of a written request from the Project Manager to do so.  If
the Contractor fails to deliver such performance bond within 21
days of a written request from the Project Manager to do so, 20%
of the Price for Work Done to Date is retained in assessments of
the amount due until the Contractor has so delivered such
performance bond.
Z17. Subcontracting The Contractor does not subcontract the whole of the works. 
All conditions of contract of subcontracts entered into by the
Contractor:
• contain an obligation upon the Contractor to pay the
subcontractor 30 days from receipt by the Contractor of
a valid invoice rendered by the subcontractor under the
terms of the subcontract; and
• procure that the relevant sub-contract shall contain such
Page 251

Page 252

Page 172 of 208 
obligations as necessary to ensure that it is in all
respects compatible with the terms of this contract and,
insofar as they are applicable to this contract and the
works. 
The Contractor provides to the Project Manager promptly when
requested a certified copy of any sub-contract (save for
particulars of the cost of such sub-contract works unless other
provisions of this contract oblige the Contractor to disclose
them). 
Z18 Project Documents The Contractor hereby acknowledges that it shall be deemed to
be familiar with and have taken full account of the Project
Documents to the extent that it has copies of the same or copies
are made available to it (under deletion of any confidential
information) in sufficient time to allow it to comply with its
obligations hereunder and whether or not provided or made
available to it before or after the date of signing of this Contract.
The Contractor warrants that: 
(a)        it has performed and will continue to perform its
obligations under this contract in such manner and at such times
that no act, omission or default on its part in relation thereto will
constitute, cause or contribute to any breach by the Client of any
of its obligations in the Project Documents; 
(b)        it shall comply with the procedures laid down in the
Project Documents for the drawdown of funding; for design
development and for (or approval of) changes in design,
specification or materials and for the inspection of the works prior
to Completion or the issue of the Defects Certificate and for
similar matters; 
(c)        exercising the level of skill, care and diligence required by
clause 21, the design of all elements of the works will comply
with the requirements of  the Project Documents and the
counterparties thereto 
Page 252

Page 253

Page 173 of 208 
(d)        it shall carry out and complete the works to the standards
required by and in accordance with any restrictions imposed
upon the Client in the Project Documents; 
(e)        it shall comply with any obligations imposed upon the
Client under such Project Documents insofar as such obligations
relate to the design and construction of the works, the making of
changes to the works, the development of the detailed design,
the obtaining of required permissions and consents, the selection
and appointment of sub-contractors and consultants, the
provision of information to a third party relating to the works, the
requirement for site and other meetings, the procedure to be
followed for inspecting the works on completion of the works
(including but not limited to any requirement for joint inspections,
the giving on notice of any inspection and the preparation of
schedules of defects), the rectification of defects and the
insurance of the works, 
failing which the Contractor shall indemnify the Client for any
damages, costs, fees, expenses or losses incurred or suffered by
the Client arising as a result of a breach by the Contractor of this
clause Z18.   
Notwithstanding anything elsewhere in this Contract, where any
obligation in a Project Document requires a higher standard to be
achieved or a different procedure to be followed or a different
timescale to be complied with than a standard or procedure or
timescale in this Contract, the Contractor shall carry out his
duties and obligations under this Contract such that he complies
with, and by such compliance ensures that the Client complies
with, the standard or procedure or timescale in the Project
Document. 
Where any Project Document is provided to the Contractor with
insufficient time to allow it to comply with its obligations
hereunder, the Contractor shall in respect of such Project
Document comply with the obligations imposed upon the
Contractor pursuant to this clause Z18, save that the Contractor
Page 253

Page 254

Page 174 of 208 
shall not be required to comply with such obligations where the
Contractor has within 7 days from receipt of such Project
Document notified the Client in writing of the reasons why and
the extent to which it is unable to comply with the provisions of
this clause Z18 in respect of such Project Document. 
The Contractor hereby acknowledges that it has copies of and is
deemed aware of the terms of the following Project Documents: 
[INSERT] 
Z20 Nuisance 
Z20.1 The Contractor shall at all times, prevent any public or private
nuisance (including any such nuisance caused by noxious
fumes, noisy working operations, vibration or the deposit of any
material or debris on the public highway or rail infrastructure,
contamination of river/water courses, etc.), trespass over
adjoining property, or other interference with the rights of any
occupier or owner neighbouring or in the vicinity of the Site or
permitted accesses thereto and in each case any adjoining or
neighbouring landowner, tenant or occupier or any public utility
company arising out of the carrying out of the works or of any
obligation hereunder and shall not breach the condition of any
consent or license or give rise to enforcement action or criminal
proceedings by any relevant authority, and shall assist the Client
in defending any action or proceedings which may be instituted in
relation thereto.  The Contractor shall be responsible for and
shall indemnify the Client from and against any and all expenses,
liabilities, losses, claims and proceedings whatsoever resulting
from any such nuisance or trespass or interference or breach,
save only where such nuisance or trespass or interference is the
direct and unavoidable consequence of an express instruction of
the Client and not as a result of how the instruction was
implemented 
Z20.2 Without prejudice to the Contractor’s obligations under Clause
Z20.1, the Contractor shall ensure that there is no trespass on or
over any adjoining or neighbouring property arising out of or in
Page 254

Page 255

Page 175 of 208 
the course of or caused by the carrying out of the works or of any
obligation pursuant to Section 4 (Quality Management).  If the
carrying out of the works or of any obligation pursuant to Section
4 (Quality Management) is likely to necessitate any interference
with the rights of adjoining or neighbouring owners or occupiers
or any party working on or at, owning, letting, financing,
occupying or otherwise attending any neighbouring or adjacent
sites, then the Contractor shall, at no cost to the Client, notify the
Client of same and await express instructions from the Client as
to how to proceed. In the event that the Client decides that it
shall obtain the prior written agreement of such owners and/or
occupiers or other parties thereto, the Contractor shall provide
the Client with all reasonable assistance in dealing with the
same.  The Contractor shall comply in every respect with any
conditions contained in any such agreement.
Z21 Data Protection 
Z21.1 The Contractor shall comply with the Data Protection Act 1998
("the 1998 Act") and any other applicable data protection
legislation (including from 25 May 2018 onwards Regulation (EU)
2016/679 (the “GDPR”) and/or any data protection and privacy
laws enacted as a replacement of the GDPR as a result of the
GDPR ceasing to have direct effect in the UK). In particular, the
Contractor agrees to comply with the obligations placed on the
Contractor by the seventh data protection principle ("the Seventh
Principle") set out in the 1998 Act, namely: 
Z21.2 to maintain technical and organisation security measures
sufficient to comply with the obligations imposed on the
Contractor by the Seventh Principle; 
Z21.3 only to process Personal Data (as set out in the 1998 Act) for
and on behalf of the Client for the purpose of performing in and
accordance with the Contract and where necessary only on
written instructions from the Client to ensure compliance with the
1998 Act; and 
Z21.4 to allow the Client to audit the Contractor's compliance with the
requirements of this paragraph 2.1.3 (Data Protection) in respect
of or in connection with this Agreement on reasonable notice
and/or to provide the Client with evidence of its compliance with
the obligations set out in this paragraph 2.1.3 (Data Protection).
Page 255

Page 256

Page 176 of 208 
Z21.5 All claims and proceedings and all liability, loss, costs and
expenses incurred in connection therewith incurred by the Client
or any affiliate as a result of any claim made or brought by any
individual in respect of any loss, damage or distress caused to
that individual as a result of the Contractor's unauthorized
processing, unlawful processing, destruction of and/or damage to
any Personal Data processed by the Contractor, its employees or
agents who provide the works are a Contractor risk..
Z22 Freedom of Information 
Z22.1 The Contractor shall co-operate with, facilitate, support and
assist the Client to comply with the Freedom of
Information (Scotland) Act 2002 (“FOISA”) (which shall be
deemed to be in full force and effect for the purposes of this
Agreement) and any codes of practice applicable from time to
time relating to access to public authorities' information, including
without limitation by providing Documents and other information
relating to this Agreement or to the Contractor, or any other
relevant information within the timescales necessary to allow the
Client to comply with its obligations and duties under FOISA and
the relevant codes of practice. 
Z22.2 All information submitted to the Client may need to be disclosed
and/or published by the Client.  Without prejudice to the
foregoing generality, the Client may disclose information in
compliance with FOISA, (the decisions of the Client in the
interpretation thereof shall be final and conclusive in any dispute,
difference or question arising between the Client and the
Contractor in respect of disclosure under its terms), any other
law, or, as a consequence of judicial order, or order by any court
or tribunal with the authority to order disclosure.  Further, the
Client may also disclose all information submitted to them to the
Scottish or the United Kingdom Parliament or any other
department, office or agency of Her Majesty’s Government in
Scotland or the United Kingdom, and their servants or agents. 
When disclosing such information to either the Scottish
Parliament or the United Kingdom Parliament it is recognised
and agreed by both parties that the Client shall if they see fit
disclose such information but are unable to impose any
Page 256

Page 257

Page 177 of 208 
restriction upon the information that they provide to Members of
the Scottish Parliament, or Members of the United Kingdom
Parliament and such disclosure shall not be treated as a breach
of this agreement. 
Z22.3 If the Contractor considers that specific information provided to
the Client is potentially exempt from disclosure under FOISA
(where, for example, it is considered to be commercially
confidential), the Contractor will identify exactly which information
it considers is exempt, state the period of sensitivity and provide
justification to the Client for its assertions (for example, identify
what harm may result from disclosure). The Parties acknowledge
that the Client is not bound by the Contractor’s views in this
regard and may in its absolute discretion disclose and/or publish
any such information in order to comply with FOISA.
Z23 Applicable Law The Contractor complies at all times with Applicable Law.
Z24 Construction (Design and
Management) Regulations 2015 
Z24.1 The Contractor warrants and undertakes to the Client that it has
and shall maintain the skills, knowledge, experience and
organisational capability to be able to meet all CDM Regulations
requirements and fulfil such duties as are relevant to him
thereunder (including to the extent applicable those of Principal
Contractor and Principal Designer (as more fully described in the
CDM Regulations). The Contractor shall, at no cost to the Client,
fulfil all of its obligations and duties arising from the CDM
Regulations.  The Contractor shall ensure that no act, omission,
breach or default by or on behalf of the Contractor or those for
whom it is responsible causes or contributes to any breach of the
CDM Regulations by the Client.  In particular (but without
limitation) the Contractor shall satisfy itself that any person with
whom it sub-lets any portion of the works (including any design)
has (and maintains) the skills, knowledge, resources and
experience and organisational capability to fulfil its obligations
under the CDM Regulations; and has allocated adequate time,
monies and resources for the purposes of meeting the
requirements of the CDM Regulations and Applicable Law prior
to their being appointed. 
Page 257

Page 258

Page 178 of 208  Page 258

Page 259

Page 179 of 208 
Appendix 9: Equalities Impact and Fairer Scotland Duty Impact Assessment
Part 1: Background 
Section A
Project name Manufacturing Innovation Centre for Moray (MICM)
What is the purpose of the
project?
The investment objectives of the project are to: 
• To increase BERD (Business Enterprise, Research and Development) in Moray’s indigenous manufacturing companies
• To increase growth, productivity, and efficiency in Moray’s indigenous manufacturing companies
• To increase the number of manufacturing start-ups in Moray
• To support the attraction of manufacturing inward investment to Moray.
• To accelerate the transition to net zero in Moray’s indigenous manufacturing companies
Project owner Highlands and Islands Enterprise
EQIA lead (person to
complete the EQIA and will
co-ordinate and involve
stakeholders.)
Project SRO: Moray Area Manager, Highlands and Islands Enterprise
EQIA contributors MICM Project Board
Date of EQIA Updated 7/8/23 
Section B
How does the project:
• meet one or more of the general duties under the Equality Act 2010 and
• address socio-economic disadvantage or inequalities of outcome?
General duties Please Explain
Eliminating discrimination,
harassment and victimisation
In delivering the project, HIE’s core priority is to ensure that it has due regard to the Equality Act 2010 and to avoid discrimination
through the physical design of buildings which are subject to refurbishment or being newly constructed within the MICM project. 
HIE will also have due regard to the Equality Act 2010 and avoid discrimination in the ways that HIE, as landlord, operates these
Page 259

Page 260

Page 180 of 208 
buildings, including through its approach to service delivery, whether through fixed-term project staff or a Contract for Services
procured to support the project’s objectives. 
The approach to this duty under MICM’s delivery is the same as the approach taken by HIE at Horizon Scotland.
Advancing equality of
opportunity*
As the project within MICM’s direct control is principally a building project and a service delivery project targeted at SMEs, opportunities
to advance equality of opportunity will be focused on the design of the buildings and the overall SME service offer which are subject to
investment.  HIE will ensure that the brief for detailed design and planning requires the design and planning teams to actively consider
the opportunity to create spaces which could help to advance equality of opportunity for certain protected groups (see Part 2 – Positive
Impacts).  HIE will also ensure that the service delivery arrangements incorporate all of its standard equalities obligations, including
measures to ensure that equality of opportunity is advanced for protected groups. HIE’s approach to MICM’s delivery will also have
regard to the equalities and wellbeing in manufacturing: recommendations report prepared by the independent Equalities and
Wellbeing in Manufacturing Working Group in November 202237
Fostering good relations
**
As above
Socio-economic
disadvantage
The MICM project will not directly contribute to tackling socio-economic disadvantage and this is not a strategic focus of the project.
Inequalities of outcome The MICM project will contribute indirectly to addressing inequalities of outcome through the provision – indirectly through SMEs - of
economic opportunities in the form of well paid jobs that are potentially attractive to young people in a rural area. 
37 https://www.gov.scot/publications/equalities-wellbeing-manufacturing-recommendations-report/
Page 260

Page 261

Page 181 of 208 
Section C
Is it likely that there is no impact on any of the equality groups (having considered the above)? If yes, please explain why (based on evidence) if this is the
case. There is then no need to complete Parts 2 and 3. However, in most cases it is expected that there will be positive impacts. 
No.  There will be positive impacts on some of the general duties of the Equality Act 2010 as discussed above.  Those directly impacted by the project are as
follows: 
1. Staff engaged in delivering the Contract for Services (MICM Director, MICM Manager, Administrator)
2. MICM tenants: businesses engaged in manufacturing activity, including scientific research, consultancy and other sectors associated with
manufacturing sectors and the low carbon agenda
3. Staff employed by MICM tenants and other MICM service users (including visiting SMEs and students) 
The diversity of MICM tenants, as well as their own equality and diversity policies, will directly impact the success and vitality of MICM and its pursuit of
Equalities objectives and in addressing Inequalities of outcome through the provision of above average salary jobs. 
The remainder of this document focuses solely on those impacts which are within MICM’s direct control. 
Page 261

Page 262

Page 182 of 208 
Part 2: Evidence and Impact Assessment 
Section A
Based on available evidence, consider what the positive or negative impacts of a policy change are on the protected characteristics.
Protected characteristic Positive impact Negative
impact
No
impact
Disabled people Building design: This will be addressed in the detailed design stage 
MICM staffing: This will be addressed either in HIE’s recruitment of fixed-term project staff or in the Contract for
Services which will require the service provider to adhere to HIE’s Equality and Diversity Policy (see Appendix 10)  
Sexual orientation MICM staffing: This will be addressed in the Contract for Services which will require the service provider to
adhere to HIE’s Equality and Diversity Policy (see Appendix 10)  
Women MICM staffing: This will be addressed either in HIE’s recruitment of fixed-term project staff or in the Contract for
Services which will require the service provider to adhere to HIE’s Equality and Diversity Policy (see Appendix 10)  
Men   X
Transgendered people Building design: This will be addressed in the detailed design stage 
MICM staffing: This will be addressed either in HIE’s recruitment of fixed-term project staff or in the Contract for
Services which will require the service provider to adhere to HIE’s Equality and Diversity Policy (see Appendix 10)  
Race (includes
Gypsy Travellers)
MICM staffing: This will be addressed either in HIE’s recruitment of fixed-term project staff or in the Contract for
Services which will require the service provider to adhere to HIE’s Equality and Diversity Policy (see Appendix 10)  
Age (incl. older
people aged 60+)
MICM staffing: This will be addressed either in HIE’s recruitment of fixed-term project staff or in the Contract for
Services which will require the service provider to adhere to HIE’s Equality and Diversity Policy (see Appendix 10)  
Children and
young people
MICM operation: This will be addressed either in HIE’s recruitment of fixed-term project staff or in the Contract
for Services which will require the service provider to adhere to HIE’s Equality and Diversity Policy (see Appendix
10)  
Religion or belief MICM staffing: This will be addressed either in HIE’s recruitment of fixed-term project staff or in the Contract for
Services which will require the service provider to adhere to HIE’s Equality and Diversity Policy (see Appendix 10)  
Pregnancy &
maternity
MICM staffing: This will be addressed either in HIE’s recruitment of fixed-term project staff or in the Contract for
Services which will require the service provider to adhere to HIE’s Equality and Diversity Policy (see Appendix 10)  
Marriage & civil
partnership  
X
Page 262

Page 263

Page 183 of 208 
Section B
Please also consider the impact of the project in relation to: 
Positive impact Negative impact No impact
Looked after children and care
leavers  
Not applicable
Privacy (e.g. information
security & data protection)  
HIE’s existing adherence to its
information security and data
protection policy will extend to MICM
and to any contract for Services
Economy The positive economic impacts of the
investment are set out in the Economic
Case of the FBC following a methodology
detailed in Appendix 2.   
Page 263

Page 264

Page 184 of 208 
Section C
Record the evidence used to support the assessment. It can include officer knowledge and experience, research, customer data and surveys, public
engagement and feedback etc. The amount of evidence gathered should be proportionate to how relevant a particular policy or service is to equality. If
there are gaps in evidence, record these.
Evidence used Source of evidence
1. Officer knowledge and experience Direct experience of designing and operating Units 9 and 10 in their current form
as well as owning Enterprise Park Forres, including Horizon Scotland which is
managed under a Contract for Services
Evidence gaps Planned action to address evidence gaps
1. Property and service design features which would advance equality of
opportunity
This will be undertaken during the detailed design stage for MICM Hub and MICM
Grow-on space as well as in the design of the service delivery arrangements
2. Property and service design features which would foster good
relations
This will be undertaken during the detailed design stage for MICM Hub and MICM
Grow-on space as well as in the design of the service delivery arrangements
3. Age and gender profile of MICM staff and events attendees  Collected by HIE if fixed-term project staff. Data on MICM staff to be provided
under the terms of the Contract for Services if that delivery route is chosen.
Requirement to undertake surveys of all events to capture profile of end users 
Page 264

Page 265

Page 185 of 208 
Part 3: Recommendations 
Section A
Recommendations should be based on evidence available at the time and aim to mitigate negative impacts or enhance positive impacts on any or all of
the protected characteristics.
Recommendation Lead person Timescale
1.  Ensure that HIE’s general duties under the Equality Act 2010, and the commitments and aspirations
expressed in this Equality Impact Assessment, feature prominently in the design and planning briefs for the
detailed design process for MICM
SRO Unit 9 Design brief:
August 2023
Service delivery
arrangements –
November 2023 to
January 2024 
Page 265

Page 266

Page 186 of 208 
Part 4:Equality Impact Assessment Summary Report 
What are the main impacts on equality?
The MICM FBC has focused on major concept design options on the scale and manner of physical development and on the design if MICM services to meet
the project’s investment objectives.  The detailed design and planning work which will have a vital bearing on equalities impact is still to come.  The next
stage of project development activity will focus on detailed design both of the property requirements and service delivery arrangements. 
The project will meet the general duty under the Equality Act 2010 of eliminating discrimination, harassment and victimisation.  As noted above, the
potential to deliver positive impacts under the other two general duties within the Equality Act (advancing equality of opportunity and fostering good
relations) will also form part of the brief for the various professional teams supporting design and planning activity.
In relation to a strategic decision, how will inequalities of outcome caused by economic disadvantage be reduced?
Tackling socio-economic disadvantage is not a priority for the MICM project.  Other projects within the Growth Deal have an explicit focus on this goal and
clearly the Fairer Scotland Duty under the Equality Act 2010 is an important consideration for strategic decision-making at overall Moray Growth Deal level. 
Reducing inequalities of outcome is likely to be an indirect outcome of MICM.  It will be dependent on jobs created by existing and new tenants, their
salary levels and their attractiveness to young people living in Moray.
What are the main recommendations to enhance or mitigate the impacts identified?
No negative impacts on equalities have been identified at this stage.  As noted above, opportunities to enhance positive impacts, and to identify and
mitigate any potential negative impacts will be taken as part of the detailed design and planning stage. 
If there are no equality impacts on any of the protected characteristics, please explain. 
Page 266

Page 267

Page 187 of 208 
Appendix 10: HIE Equality and Diversity Policy
Page 267

Page 268

Page 188 of 208 
EQUALITY AND DIVERSITY
POLICY
2015
Policy Owner – HR 
Page 268

Page 269

Page 189 of 208 
Index 
1. Introduction 
2. Recruitment and selection 
3. Training and development 
4. Equal pay 
5. Employee benefits and policy development and review 
6. Harassment 
7. Individual responsibilities 
8. Complaints 
9. Breach of equality and diversity policy 
10. Monitoring 
11. Further information 
Page 269

Page 270

Page 190 of 208 
1. Introduction 
This policy sets out Highlands and Islands Enterprise’s approach as an employer to
equality and diversity. HIE is fully committed to eliminating unlawful and unfair
discrimination and values the differences that a diverse workforce brings to the
organisation. 
Equality - is about treating people fairly regardless of differences between them.
Equality is enshrined in HIE’s obligation to comply with anti-discrimination
legislation which protects us all from being discriminated against on grounds which
are unfair. 
Diversity - is about understanding, respecting and valuing those differences and the
unique contribution which each of us can bring to our employment. An employer
which values diversity makes the best of people’s talents whatever their
backgrounds, experiences, styles, perceptions or values and beliefs. 
Considering equality and diversity together is therefore not about treating everyone
the same. It is about treating people differently, according to their needs and
circumstances, with the aim of ensuring that all employees receive fair treatment. For
example, HIE recognises that job candidates who have a disability are less likely to
find employment than candidates who have the same qualifications and experience
and have no disability. Consequently we guarantee a job interview to disabled
candidates who meet the essential criteria for a job.  The appointment decision, in
the same way as all decisions on recruitment, selection, training, promotion and
career development, is based on objective and job-related criteria. 
Our commitment to equality and diversity in employment includes: 
• the promotion of equality of opportunity in employment
• the promotion of diversity and equality in the development, implementation,
regular monitoring and review of employment policies with the aim of ensuring
that people receive fair and consistent treatment
• a continuing programme of action to make the policy and its implementation
fully effective, including training and guidance 
• the elimination of discrimination of any kind
• the provision of an in-house mediation service and offer of outside
counselling, supported by occupational health privison and an Employee
Assistance Programme
• ensuring an annual review and, where necessary, revision of this policy. 
We are committed to maintaining a culture which recognises and rewards individual
achievement and merit regardless of age, disability, gender reassignment, marriage
and civil partnership, pregnancy and maternity, race, religion or belief, sex and
sexual orientation as well as working pattern (full-time or part-time) and contract
status (permanent or fixed term). 
HIE believes that the promotion of equality and diversity is key to good management,
to developing an inclusive workplace culture and in maximising employee
productivity. HIE therefore expects all employees to be treated with respect at all
times and not just in relation to the characteristics protected by equality legislation.
(Appendix A)
Page 270

Page 271

Page 191 of 208 
HIE is committed to providing a working environment in which all employees can
realise their full potential, free of harassment or discrimination in any form. HIE
supports employees to ensure that they understand their personal responsibility in
this and that they make this happen in practice. 
2. Recruitment and selection 
The Human Resources Team will be responsible for ensuring that all recruitment and
selection activity is conducted in line with HIE’s commitment to equality and diversity.
HIE will ensure that training and support in equality and diversity is available to all
staff involved in recruitment or other decision making where equality of opportunity
issues are likely to arise. 
Employees are encouraged to apply for internal promotion or other vacancies and
where possible posts will be open to all employees.  However on occasion it may be
necessary to restrict recruitment within a team, for example where there is
organisational restructuring.  Please refer to HIE’s Organisational Change Policy.
All applications will be given full consideration, and this will be supported by
recruitment processes which focus on information that is relevant to the
requirements of the post. Appointment decisions will be recorded and feedback
provided to candidates on request.
Equality monitoring data will not be disclosed to the recruiting panel and will be used
for monitoring purposes only.
External HIE vacancies will be advertised widely to ensure that opportunities are
accessible to a diverse recruitment pool. Recruitment monitoring will be carried out
to identify whether HIE’s workforce is representative of the local community and the
wider recruitment pool. 
All recruitment material will positively encourage applications from all suitably
qualified and experienced people and where appropriate, applications from under-
represented groups will be encouraged. 
3. Training and development 
Promotion and career development are based on objective and job-related criteria.
Consequently access to training and development events will be determined by
reference to individual development plans, in line with the Further Education policy.
Any selection process for training and development opportunities will be free from
bias of any kind. 
Training on equality and diversity is open to all employees and is an integral part of
induction. Managers will be appropriately trained to enable them to properly and
fairly implement HIE’s HR policies and procedures and carry out their management
responsibilities effectively.  This includes taking into account the varying needs and
circumstances of team members and how these may develop over time. 
HIE may encourage, where supported by evidence of disadvantage, selected
employee groups to take advantage of training or development opportunities aimed
at minimising that disadvantage. 
Page 271

Page 272

Page 192 of 208 
4. Equal pay 
In support of HIE’s commitment to equality and diversity, HIE operates a job
evaluation scheme to ensure that pay for work done is fair across the agency.
Where employed doing the same or broadly similar work, which has been given
equal value under HIE’s job evaluation scheme, men and women will be treated
equally with regard to terms and conditions of employment and pay grades. 
All staff will be considered for pay progression in line with public sector pay policy. 
5. Employee benefits and policy development and review 
HIE aims to provide a range of employee benefits which are relevant to and valued
by HIE’s employees, whose interests and circumstances will vary across the
workforce and over time. HIE also endeavours to take account of the differing needs
and aspirations of HIE’s employees alongside HIE’s business need in the
development and review of a range of policies and practices, which will be assessed
for their impact in relation to equality characteristics. 
6. Harassment 
All employees have a personal responsibility not to behave in a manner that is, or
could be considered by others to be offensive. HIE finds any form of harassment,
including third party harassment, to be unacceptable and will act to eliminate it from
the workplace. The bullying and harassment policy sets out further information on
this. 
7. Individual responsibilities 
All HIE employees have a responsibility to promote and advance this policy. HIE will
not tolerate discriminatory behaviour, and lack of knowledge or awareness will not be
an acceptable defence. 
HIE will provide training and guidance for all staff, particularly those with
management responsibilities, to encourage commitment to and awareness of
equality and diversity issues and responsibilities. 
Employees must familiarise themselves with their obligations under this policy and,
in the event of any uncertainty, consult with their manager or the HR Team before
taking any action. 
Any comments, actions or materials that may be considered offensive are
unwelcome and should be kept away from the workplace. 
Line managers have a particular responsibility to ensure that their staff are aware of
and act in accordance with this policy at all times. 
Page 272

Page 273

Page 193 of 208 
8. Complaints 
Any breach of this policy should be raised as a grievance under the HIE Grievance
Procedure. If the complaint is about bullying or harassment reference should be
made to the HIE Bullying and Harassment policy for more information. These
policies outline how action can be taken at an informal level where appropriate. 
9. Breach of equality and diversity policy 
Breaches of this policy will result in action under the disciplinary procedure. Serious
breach of HIE’s commitment to equality and diversity will be considered to be gross
misconduct and will result in summary dismissal. 
10. Monitoring 
In order to review the success of this policy HIE will ask all job applicants to
complete an equality monitoring form. All existing staff will from time to time be
asked to complete information to help HIE to understand the staff profile from an
equality perspective and compare it with the labour market. Understanding HIE’s
demographic profile assists us to identify existing or emerging equality issues or
trends. 
Where there is under-representation of particular groups, the underlying reasons will
be investigated and, where appropriate, practical measures will be taken to address
the issue identified. 
11. Further information 
This policy, which will be widely publicised within HIE, has been prepared in
consultation with the Leadership Team and the JNC. If you require any further advice
or assistance, please contact the HR team. 
Policy Owner:  HR  Last reviewed: December 2015
Review in: 2 years 
Page 273

Page 274

Page 194 of 208 
APPENDIX A  DISCRIMINATION LEGISLATION 
Equality Act 2010 
The Equality Act 2010 came into force on 1 October 2010. The purpose of the
Equality Act 2010 is to simplify discrimination legislation and create a more
consistent and effective framework, while at the same time extending discrimination
protection. 
The protected characteristics under the Equality Act 2010 are: 
• age  (any age group); 
• disability   (a physical or mental impairment which has a substantial and
long-term adverse effect on that person's ability to carry out normal day-to-day
activities.  This includes a range of illnesses); 
• gender reassignment   (the process of transitioning from one gender to
another); 
• marriage and civil partnership  (marriage - between a man and a woman;
civil partnership - a legally recognised relationship between same sex
partners); 
• pregnancy and maternity    (pregnancy – condition of being pregnant;
maternity – the period after birth (maternity leave in employment context and
for 26 weeks after birth in other situations).  This includes breastfeeding. 
• race    (defined by race, colour, nationality (including citizenship), ethnic or
national origin; 
• religion or belief    (religious and philosophical beliefs including lack of belief
(e.g. Atheism); 
• sex    (men or women);
• sexual orientation   (sexual attraction towards sex, the opposite sex or to
both sexes) 
The Act defines direct discrimination as less favourable treatment because of a
protected characteristic. Employers will be liable for acts of unlawful discrimination
committed by their employees against other employees or customers in the course
of their employment unless they can show that they took such steps as were
reasonably practicable to prevent those acts. There is no limit on compensation for
unlawful discrimination, which includes compensation for injury to feelings and
personal injury. 
Employers may take positive action in the form of proportionate measures to
encourage or train people from an under-represented group to apply for jobs,
overcome a perceived disadvantage or meet specific needs based on a protected
characteristic. For example, an employer could facilitate women having access to
childcare facilities, or provide certain religious groups with time off for religious
observance. 
The Equality Act 2010 also makes it unlawful to discriminate in the provision goods
and services. There are slight differences in the characteristics currently protected
but broadly speaking the Equality Act prohibits discrimination or harassment of
customers or clients because of the protected characteristics of disability, gender
Page 274

Page 275

Page 195 of 208 
reassignment, pregnancy and maternity, race, religion or belief, sex, and sexual
orientation. 
Forms of Discrimination in Employment 
Direct Discrimination occurs where someone is treated less favourably on the
grounds of sex, race, disability, sexual orientation etc., than another is or would be
treated. 
(E.g. a candidate is not invited for interview because of his/her ethnic background)
Indirect Discrimination occurs where a condition or practice is applied but it adversely
affects a considerably larger proportion of one particular group (men, women, racial group
etc), and it is not justifiable to apply that condition or practice.  Pregnancy and maternity is
not covered by the provisions on indirect discrimination.  (e.g. a job specification includes
holding a driving licence as an essential attribute.  This disadvantages a disabled candidate
who may not drive but who can access other effective means of travelling to visit clients etc.)
Associative discrimination is where an individual is directly discriminated against
or harassed for association with another individual who has a protected
characteristic This provision does not apply to marriage and civil partnership, and
pregnancy and maternity. 
(e.g. an employee is not given a promotion because they have a disabled partner.) 
Perceptive discrimination is where an individual is directly discriminated against or
harassed based on a perception that he/she has a particular protected characteristic
when he/she does not, in fact, have that protected characteristic. This provision does
not apply to marriage and civil partnership, and pregnancy and maternity. 
(e.g. an employee is not given lead role on a major project because their manager
thinks they are gay.) 
Harassment, which can also be a form of discrimination, occurs where unwanted
conduct affects the dignity of men and women in the workplace.  This is defined
further and dealt with in the HIE’s Bullying and Harassment policy. Essentially
defined where unwanted conduct affecting the dignity of men and women in the
workplace. This provision does not apply to marriage and civil partnership, and
pregnancy and maternity. 
(e.g. employees humiliate a colleague by telling jokes about their religion.)
Third-party harassment occurs where an employee is harassed and the
harassment is related to a protected characteristic (other than marriage and civil
partnership, and pregnancy and maternity), by third parties such as clients or
customers. For an employer to be liable:
• the harassment must have occurred on at least two previous occasions
(although not necessarily by the same harasser or suffering the same type of
harassment); 
• it must be aware that the previous harassment has taken place; and 
• it must have failed to take reasonable steps to prevent harassment from
happening again. 
(e.g. a member of the public makes scathing comments about an employee’s ability
to deal with their enquiry because they consider them too young to know what they
are doing.)
Page 275

Page 276

Page 196 of 208 
Victimisation occurs when someone is treated badly because they have made or
supported a complaint or grievance under the Act. 
(e.g. an employee is not shortlisted for promotion because last year they took out a
grievance against their manager for not shortlisting them for a previous role.) 
Failure to make reasonable adjustments occurs where a physical feature or a
provision, criterion or practice puts a disabled person at a substantial disadvantage
compared with someone who does not have that protected characteristic and the
employer has failed to make reasonable adjustments to enable the disabled person
to overcome the disadvantage.
(e.g. not providing specialist software for a member of staff who develops a visual
impairment and whose job involves using a computer.)
Page 276

Page 277

Page 197 of 208 
Appendix 11: Carbon assessments 
Page 277

Page 278

Page 198 of 208  Page 278

Page 279

Page 199 of 208  Page 279

Page 280

Page 200 of 208  Page 280

Page 281

Page 201 of 208  Page 281

Page 282

Page 202 of 208  Page 282

Page 283

Page 203 of 208  Page 283

Page 284

Page 204 of 208  Page 284

Page 285

Page 205 of 208  Page 285

Page 286

Page 206 of 208  Page 286

Page 287

Page 207 of 208  Page 287

Page 288

Page 208 of 208 
Appendix 12: Cash drawdown by financial year
Total 2023/24 2024/25 2025/26 2026/27 2027/28 2028/29 2029/30 2030/31 2031/32 2032/33
Capital Spend 5,608,820   444,966      2,287,207   -               1,831,362   1,045,285   -               -               -               -               -              
HIE 2,557,010   202,856      1,042,717   -               834,901      476,536      -               -               -               -               -              
Scottish Government 610,362      48,422         248,898      -               199,292      113,750      -               -               -               -               -              
UK Government 2,441,448   193,688      995,592      -               797,169      454,999      -               -               -               -               -              
Total 5,608,820  444,966      2,287,207  -               1,831,362  1,045,285  -               -               -               -               -              
Revenue Deficit (to end FY30/31) 1,252,191   47,388      309,173     276,423     254,703     151,580     107,853     100,416     4,655        19,607-      20,097-     
HIE -               -               -               -               -               -               -               -               -               -               -              
Scottish Government 1,250,000   47,388         309,173      276,423      254,703      151,580      107,853      100,416      2,464           -               -              
UK Government -               -               -               -               -               -               -               -               -               -               -              
Total 1,250,000  47,388        309,173      276,423      254,703      151,580      107,853      100,416      2,464          -               -              
Moray Growth Deal Funding
Moray Growth Deal Funding
CAPITAL
REVENUE
Page 288

Page 289

REPORT TO: SPECIAL MORAY COUNCIL ON 24 JANUARY 2024 
SUBJECT: INFORMATION REPORT: CHARGING FOR SERVICES 
BY:  DEPUTE CHIEF EXECUTIVE (ECONOMY, ENVIRONMENT AND
FINANCE) 
1. REASON FOR REPORT 
1.1 To inform Council with a comprehensive list of revised charges for Council
services for 2024/25. 
1.2 This report is submitted to Council in terms of Section III (B) (1) and (48) of
the Council's Scheme of Administration relating to financial policy and the
setting of charges. 
2. BACKGROUND 
2.1 The current Charging for Services Policy was approved by Council on
12 December 2023 (paragraph 7 of the draft Minute refers). Under the policy,
an annual revision of charges is required.  In order to preserve the Council’s
financial position, charges within the control of this council are generally
inflated annually and Council at the same meeting agreed that the default
increase for 2024/25 would be 5.7%. 
2.2 The Charging for Services Policy assumes a default position of full cost
recovery, recognising that there will be exceptions to that rule.  In cases
where the Council offers a service where there are alternative service
providers then market conditions should be taken into account.  In other
instances benchmarking with other local authorities may be a good test of
reasonableness.  There may be policy reasons for charging at less than full
cost recovery for some services. However, charging for services is an
important tool when considering the Council’s overall budget and the
Council’s Short to Medium term Financial Strategy, which was approved by
Council on 27 September 2023, includes maximising income as a priority to
minimise the needs to reduce service levels.   
2.3 Not all charges are within the Council’s  control.  Some charges levied by the
Council for services provided are set by statute, some are limited by statute
and some have the method of calculation prescribed by statute – these are
included in the list of charges for Council services for the sake of
completeness. 
Page 289

Page 290

2.4 A full list of proposed charges is appended to this report as APPENDIX 1,
under exception of burial charges which are currently being prepared and Fit
Life charge, which are the subject of discussion with Moray Leisure Ltd.. 
3. SUMMARY OF IMPLICATIONS 
(a) Corporate Plan and 10 Year Plan (Local Outcomes Improvement
Plan (LOIP))
The levying of charges for Council services is an essential component of
delivering Council priorities on a sustainable basis. 
(b) Policy and Legal
The current policy for charging for Council services was approved by this
Council on 25 October 2023.  There are no legal implications arising
from this report.  Some charges are set or limited by legislation. 
(c) Financial implications
Increased income from charges will contribute to the Council’s financial
sustainability. 
(d) Risk Implications
There are no risk implications arising directly from this report.   
(e) Staffing Implications
There are no staffing implications arising directly from this report.   
(f) Property
There are no property implications arising from this report. 
(g) Equalities/Socio Economic Impact
There are no equalities implications or implications for the socio-
economic duty arising from  this report 
(h) Climate Change and Biodiversity Impacts
There are no implications for climate change or biodiversity arising from
this report. 
(i) Consultations
All services have been consulted as to recommended charges and
reasons for any departures from the default increase. 
4. CONCLUSION 
4.1 A comprehensive list of charges proposed for 2024/25 is appended at
APPENDIX 1, with the exception of burial charges which are still under
preparation and Fit Life charges which are still under discussion with
Moray Leisure Ltd. 
Author of Report: Lorraine Paisey, Chief Financial Officer
Background Papers: 
Ref: SPMAN-1293228629-1030
Page 290

Page 291

SECTION A:  CORPORATE SERVICES / CROSS DEPARTMENTAL 
CODE: S Set by Statute/Scottish Government  
M At legal maximum  
SD Statutory duty of full cost recovery 
REF SERVICE CODE
S/M/SD
BUDGET
2023/24
CHARGE
2023/24
CHARGE
2024/25
DATE OF LAST
CHANGE
A1. Property Enquiry Certificates   £184 + VAT £   194 + VAT April 2023
A3. Loan and title lending/copying
(Estates and Legal Services)   
From £45 increasing
depending on time
taken
From £ 47.50
increasing
depending on time
taken
April 2023
A3a 14 day letter for industrial debts
arrears 
£50 per letter £   53 per letter April 2023
A3b Initial Irritancy letter linked to
industrial debt recovery 
£100 per letter £    105 per letter New Charge April
2023
A3c Follow up Irritancy letter linked to
industrial debt recovery 
£75 per letter £      79 per letter New Charge April
2023
A3d Letter Instructing Sheriff Officers
linked to industrial debt recovery 
£50 per letter £    53  per letter New Charge April
2023
A4. Recharge of Council’s legal costs
in relation to discretionary property
and leasing work 
£61 - £140 per hour £ 64   - £ 148   per
hour
April 2023
A4a Recharge of Council’s legal costs
in relation to pre judicial litigation
work by litigation team 
£61 - £140 per hour £  64   - £  148   per
hour
April 2023
A4b Judicial expenses:  Court
proceedings including recovery of
rent arrears, industrial debts,
miscellaneous and licensing
matters
S  Varies annually on a
national basis and
by work type/stage
Varies annually on a
national basis and
by work type/stage 
Page 291

Page 292

Page 2 of 68
REF SERVICE CODE
S/M/SD
BUDGET
2023/24
CHARGE
2023/24
CHARGE
2024/25
DATE OF LAST
CHANGE
A5. Orders under Town and Country
Planning (Scotland) Act and other
Roads/planning matters 
£61 - £140 per hour £ 64    - £  148   per
hour
April 2023
A6. Licensing
(i) Liquor Licensing: 
M £ 
Per approved table
of charges set by
the Licensing Board 
Per approved table
of charges set by
the Licensing Board 
September 2022 
(ii) Licences under the Civic Government (Scotland) Act and other miscellaneous pieces of legislation - All charges for licences
managed under the authority of the Licensing Committee as Licensing Authority will be reviewed in full in 2024 by the
Committee. A full review has generally been undertaken each 5 years with inflationary increases in between 
Animal Boarding Establishments  £148,000 £131 £138 April 2022 
Animal Breeding   £115 £122 April 2022 
Cinema Licence   £166 £175 April 2022 
Copy Licence   £22 £23 April 2022 
Dangerous Animals   £285 £301 April 2022 
HMO (5 occupants or under)   £1,800 £1,903 April 2022 
HMO (10 occupants or under)   £2,572 £2,719 April 2022 
HMO (over 10 occupants)   £3,345 £3,536 April 2022 
HMO Change of Circumstance   £260 £275 April 2022 
Itinerant Metal Dealer’s Licence   £683 £722 April 2021 
Itinerant Metal Dealer’s Exemption
Warrant  
£683 £722 April 2022 
Knife Dealers Licence   £723 £764 April 2022 
Late Hours Catering Licence   £952 £1,006 April 2022 
Late Hours Catering Renewal   £952 £1,006 April 2022 
Licence Plates   £22 £23 April 2022 
Market Operator Licence   £447 £472 April 2022 
Market Operator Temporary
Licence  
£447 £472 April 2022
Page 292

Page 293

Page 3 of 68
REF SERVICE CODE
S/M/SD
BUDGET
2023/24
CHARGE
2023/24
CHARGE
2024/25
DATE OF LAST
CHANGE 
Metal Dealer Licence   £683 £722 April 2022 
Metal Dealer’s Exemption Warrant   £683 £722 April 2022 
Performing Animals   £110 £116 April 2022 
Pet Shops   £224 £237 April 2022 
Public Charitable Collections   No Fee No Fee April 2019 
Public Entertainment (under 200
attendees)*  
£315 £333 April 2022 
Public Entertainment (between 200
and 299 attendees)*  
£394 £416 April 2022 
Public Entertainment (between 300
and 399 attendees)*  
£513 £542 April 2022 
Public Entertainment (between 400
and 499 attendees)*  
£671 £709 April 2022 
Public Entertainment (over 500
attendees - commercial)*  
£1,388 £1,467 April 2022 
* Discounts apply for charitable events 
Public Processions   No Fee No Fee April 2019 
Riding Establishments:   £413 £437 April 2022 
Second Hand Dealers Licence   £146 £154 April 2022 
Sex Shop Licence   £1,277 £1,350 April 2022 
Sexual Entertainment Venue new
licence  
£1,530  £1,617 SEV fees set Sept
2020 
Sexual Entertainment Venue
licence grant fee  
TBD TBD 
Sexual Entertainment Venue
licence renewal  
£1,530 £1,617 April 2022 
Sexual Entertainment Venue
licence variation  
£510 £539 April 2022 
Sexual Entertainment Venue
licence transfer  
£281 £297 April 2022 
Sexual Entertainment Venue issue
duplicate licence  
£41 £43 April 2022 
Street Traders   £394 £416 April 2022
Page 293

Page 294

Page 4 of 68
REF SERVICE CODE
S/M/SD
BUDGET
2023/24
CHARGE
2023/24
CHARGE
2024/25
DATE OF LAST
CHANGE 
Tattooing and Piercing   £394 £416 April 2022 
Taxi Booking Office   £515 £544 April 2022 
Taxi/Private Hire Driver Grant   £243 £257 April 2022 
Taxi/Private Hire - Driver Renewal   £197 £208 April 2022 
Taxi/Private Hire Vehicle   £422 £446 April 2022 
Variation of any Licence   £28 £30 April 2022 
Vehicle Substitution   £353 £373 April 2022 
Venison Dealer Licence   £53 £56 April 2022 
Window Cleaner Licence   £155 £164 April 2022 
Zoo Licence   £330 £349 April 2022
A8. Searches in Indexes of Statutory
Registers
S  
£
n/a n/a April 2019
A9 Certificates:  Full extract of birth,
death or marriage and abbreviated
certificate
S n/a n/a January 2011
A10. Note of Marriage or civil
partnership
S As set As set April 2010
A11. Marriage or civil partnership
ceremony conducted by Registrar
S As set As set April 2010
A12. Use of marriage room in Registry
Office
Over 10 guests 
5 – 10 guests 
Non-returnable deposit paid when
making a booking for a ceremony. 
This fee is deducted from the final
charge.   
£192 
£82 
£76 
£203 
£87 
£80
April 2023
Page 294

Page 295

Page 5 of 68
REF SERVICE CODE
S/M/SD
BUDGET
2023/24
CHARGE
2023/24
CHARGE
2024/25
DATE OF LAST
CHANGE
A13. Surcharge for Marriages in all
venues outwith the Registry Office
(Mon-Sat) 
Included in
Registrar’s
total above
(A8 – A11) 
£292 £309 April 2023
A13a Saturday surcharge for Marriages
in Marriage Room 
£141 £149 April 2023
A16. Change of Civil Partnerships to
Marriage
S As set As set 16 / 12 / 15
A17. Freedom of Information requests  £nil 10% of the cost to
the Council for costs
over £105
10% of the cost to
the Council for costs
over £105
April 2020
A18. Photocopying
A4 Black & white
A3 Black & white
A4 colour
A3 colour
Plus staff costs 
£nil 
15p
30p
45p
70p
Up to £20 per
person per hour 
15p
30p
45p
70p
Up to £20 per
person per hour 
April 2023
April 2023
April 2023
April 2023
April 2023
A19. Re-use of public sector information S £nil As set As set October 2007
A20. Data Subject Access Request M £nil As set As set October 2007
A21. Pupil Education Records M £nil Sliding scale from
£2 to a maximum of
£50
Sliding scale from
£2 to a maximum of
£50 
April 2010
A22. Committee services documents  £nil Available free on
internet, otherwise
£8 admin fee plus
10p per side of
photocopy
Available free on
internet, otherwise
£8 admin fee plus
10p per side of
photocopy
April 2021
Page 295

Page 296

Page 6 of 68
REF SERVICE CODE
S/M/SD
BUDGET
2023/24
CHARGE
2023/24
CHARGE
2024/25
DATE OF LAST
CHANGE
A23. HR Training – Social Work
Training Team – to deliver training
to external organisations  
£41 per person £41 per person April 2021
Page 296

Page 297

Page 7 of 68
SECTION B: SOCIAL CARE – MIJB and Moray Training 
REF SERVICE CODE
S/M/SD
BUDGET
2023/24
CHARGE
2023/24
CHARGE
2024/25
DATE OF LAST
CHANGE
B1. Moray Lifeline / Telecare   £41.80 per
quarter inc VAT
£44.18 per
quarter inc VAT
April 2023
B4. Blue Badge M  £20 per badge –
badge valid for 3
years
£20 per badge –
badge valid for 3
years
April 2021
B6. Meals at Day Care Centres (Older People) and Shared Lives:
B6a.  Meal   £5.20 per meal £5.50 per meal April 2023
B6b.  Tea & Biscuits   £0.80 per cup £0.85 per cup April 2023
B6c.  Light meal (Shared 
Lives Service only)  
Per Shared Lives
carer
Per Shared Lives
carer
April 2021
B6d.  Packed lunches 
(Murray Street)  
£5.20 £5.50 April 2023
B10. Stair lift maintenance   £17.22 per
quarter inc VAT
No VAT if
registered
disabled
£18.20 per
quarter inc VAT
No VAT if 
registered
disabled
April 2023
B10
a
Wash / dry toilet maintenance   Nil Nil April 2022
B11. Occupational Therapy Aids
and Equipment  
None
(per CoSLA
recommendation)
None (per CoSLA
recommendation)
October 2005
B12. Hire of Day Centre rooms   £5.71 per hour £6.00 per hour April 2023
B14. Speyside Lunch Club £6.50 inc VAT £6.87 inc VAT April 2023
B16 Case review carried out on
behalf of another local
authority 
£104.43 £110.38  April 2023 
Page 297

Page 298

Page 8 of 68
SECTION C: LEISURE FACILITIES 
REF SERVICE CODE
S/M/SD
BUDGET
2023/24
CHARGE
2023/24
CHARGE
2024/25
DATE OF LAST
CHANGE
C1 Fit Life 
C1a. 
C1b. 
Membership cards
Individual – 12 months
Individual – monthly direct
debit 
Family (1 adult) – 12 months
Family (1 adult) – monthly
direct debit 
Family (2 adults) – 12 months
Family (2 adults) – monthly
direct debit 
£ 
£276
£23 
£360
£30 
£384
£32 
£288
£24 
£396
£33 
£420
£35 
April 2020 
April 2023 
April 2023
C1c. 35 Day Membership  £35  £37  April 2019
C1d. Visitor membership for
minimum of 14 days 
Note – this is a new category and is aimed
at the in-coming short term workers,
holidaymakers, students etc. The cost is
based on a of a 14 day programmed
membership card.  A visitor membership
excludes attendance at swimming lessons.
Individual
Family     
£28.00
£30.00
NEW
C2 Swimming Pools 
C2a. Swimming 
Adult Swim / aqua aerobics /
activity class 
£  
£6.00  £6.40 
April 2023
Page 298

Page 299

Page 9 of 68
REF SERVICE CODE
S/M/SD
BUDGET
2023/24
CHARGE
2023/24
CHARGE
2024/25
DATE OF LAST
CHANGE
Junior swim aged 5 – 17 / over
60s 
Baby/toddler swim (0-4 years
old) 
Registered Disabled +one
carer 
£3.00 
Free 
£3.00
£3.20 
Free 
£3.20 
C2b. Swimming Lessons
Adult Lesson
Junior Lesson block (8 weeks)
Holiday Crash Course (5 x
daily lessons)
Parent and Child Class (1
adult & 1 child)
Individual junior lesson (30
minutes for 1 child)
Additional needs child
individual lesson (30 minutes
for 1 child) 
£ 
£8.00
£48.00
£30.00 
£6.00 
£18.00 
£10.00 
£8.50
£51.20
£32.00 
£6.40 
£19.20 
£10.60 
April 2023
C2c. Pool Hire
General (Buckie, Forres, Keith)
General (Lossiemouth)
General (Speyside) 
Pool Hire with inflatable
(Buckie, Forres, Keith)
Pool Hire with inflatable
(Speyside) 
£ Per hour
£120.00
£95.00
£75.00 
£130.00 
£90.00 
Per hour
£128
£100
£80 
£138 
£95 
April 2023
Page 299

Page 300

Page 10 of 68
REF SERVICE CODE
S/M/SD
BUDGET
2023/24
CHARGE
2023/24
CHARGE
2024/25
DATE OF LAST
CHANGE
Club Hire (Buckie, Forres,
Keith)
Club Hire (Lossiemouth)
Club Hire (Speyside) 
Club hires are exempt from
VAT if a series booking 
£50.00 
£42.00
£37.00
£55 
£45
£40
C2d. Health Suite
Sauna & Steam 
£nil Use of health
suite included in
admission cost.
Use of health
suite included in
admission cost 
C3 Indoor Facilities  All charges are inclusive of VAT, if applicable
C3a. Fitness Rooms
User induction course (Free
with Fit Life? Membership) 
Fitness Room (1 hour)
Adult 
Junior, over 60’s, 
Registered Disabled 
Activity Class 
Physical Activity for Health
class (exercise referral) 
£ 
£25.00 
£6.00
£4.00
£4.00 
£6.00 
£3.75 
£25 
£6.40
£4.30
£4.30 
£6.40 
£6.40 
April 2020 
April 2023
Page 300

Page 301

Page 11 of 68
REF SERVICE CODE
S/M/SD
BUDGET
2023/24
CHARGE
2023/24
CHARGE
2024/25
DATE OF LAST
CHANGE
C3b 
C3b
1
C3b
2
C3b
3
Speyside Sports &
Community Centre – indoor
climbing wall 
Climbing
Adult climb
Junior climb (up to 17 years)
Over 60s concession
Registered disabled + one
carer 
Climbing lessons
Adult lesson block (8 weeks)
Junior lesson block (8 weeks) 
Climbing wall hire (per hour)
Within normal opening hours
Outwith normal opening hours 
£8.00
£6.00
£6.00
£6.00 
Costs according
to type and
duration of class 
£40.00
As above plus
£22 per hour 
£8.50
£6.40
£6.40
£6.40 
Costs according
to type and
duration of class 
£42.50
As above plus
£23.50 per hour
April 2023
C4 Outdoor Sports 
C4a. Multi Sports Area
Multi Sports Area for 5-a-side
football (3 courts) per hour 
Now open-plan –
free access 
Now open-plan -
free access
April 2017
C4b.  Pavilions and Pitches
Football and School sports
field with changing rooms
Adult Teams per Game
Juvenile Teams (Under 17)
per Game 
£  
£70.00
£26.00 
£75.00
£27.50 
April 2023 
Page 301

Page 302

Page 12 of 68
REF SERVICE CODE
S/M/SD
BUDGET
2023/24
CHARGE
2023/24
CHARGE
2024/25
DATE OF LAST
CHANGE
C4c.  Pavilion and / or grassed areas
for training (football and rugby)
and School sports fields
without changing rooms
Adult groups – per session
Juvenile Groups – per
session
Session times are for morning
/ afternoon / evening 
£40.00
£14.00 
£42.50
£15 
April 2023 
Astro Sports Pitches  £   April 2020
C4e.  Aberlour, Buckie, Elgin High,
Lossiemouth, Fochabers
Full Size pitch
Adult Teams per hour
Juvenile Teams per hour 
Third size pitch
Adult Teams per hour (1 x
pitch)
Juvenile Teams per hour (1 x
pitch) 
£65.00
£32.00 
£22.00 
£11.00 
£69
£34.50 
£23 
£11.50 
C4f.  Elgin Academy and Keith 
Full Size pitch
Adult Teams per hour
Juvenile Teams per hour
Half Size pitch
Adult Teams per hour
Juvenile Teams per hour 
£65.00
£32.00 
£33.00
£16.00 
£69
£34 
£35
£17 
Page 302

Page 303

Page 13 of 68
REF SERVICE CODE
S/M/SD
BUDGET
2023/24
CHARGE
2023/24
CHARGE
2024/25
DATE OF LAST
CHANGE
C5. School facilities    
C5a. Meeting Room – per hour 
Community (small – capacity
1-10 people)
Community (medium –
capacity 11-50 people)
Community (large – capacity
51+ people) 
Private/commercial (small –
capacity 1-10 people)
Private/commercial (medium –
capacity 11-50 people)
Private/commercial (large –
capacity 51+ people) 
Requests for bookings can be
considered out-with normal
hours at an additional cost of
£22 per booking per hour 
£53,000 
£10.00 
£13.00 
£18.00 
£20.00 
£26.00 
£36.00 
£22.00 
£10.75 
£13.75 
£19.25 
£21.25 
£27.50 
£38 
£23.50 
April 2020
C5b. Sports/Assembly Hall – per
hour 
Small hall
Standard rate
Junior / over 60s 
Large hall
Standard rate
Junior / over 60s 
.
Included
above 
£23.00
£12.00 
£45.00
£23.00 
£24.50
£12.75 
£47.75
£24.50
April 2023
Page 303

Page 304

Page 14 of 68
REF SERVICE CODE
S/M/SD
BUDGET
2023/24
CHARGE
2023/24
CHARGE
2024/25
DATE OF LAST
CHANGE 
Requests for bookings can be
considered out-with normal
hours at an additional cost of
£22.00 per booking per hour 
£22.00  £23.50 
C9 Community Centres 
C9a  Admission Charges per hour
Adult
Junior aged 5-17
Over 60s
Registered Disabled + one
carer 
£ 
£5.50
£3.50
£3.50
£3.50 
£6.00
£3.70
£3.70
£3.70 
April 2023
C9b 
C9c
Shower 
Use of photocopier
(A4 black and white) 
£2.50 
Please
See
Section
A18 
£2.65 
Please
See
Section
A18 
April 2020 
Page 304

Page 305

Page 15 of 68 
SECTION D: LIBRARIES AND INFORMATION SERVICES 
REF SERVICE CODE
S/M/SD
BUDGET
2023/24
CHARGE
2023/24
CHARGE
2024/25
DATE OF LAST
CHANGE
D1 Libraries and Information Services
D1a 
D1c 
D1d
Adult Fines per week
Maximum per item
People over 60 years 
Inter-Library Loan 
Reader’s Tickets –
Replacement Computer Card 
£ No charge
N/A
No charge 
Full cost recovery
(will vary for each
item) 
£1.00 
No charge
N/A
No charge 
Full cost recovery
(will vary for each
item) 
£1.50 
April 2023
April 2023 
April 2023 
April 2023
D1g  Photocopies: 
Per A4 copy b/w 
Per A3 copy b/w 
Per A4 copy colour 
Per A3 copy colour 
Microfilm/fiche per A4 sheet 
Internet: 
Computer printouts 
Computer printouts (colour) 
Digital Scanning/Emailing - 
£ 
Please
See
Section
A18 
£0.90 
£0.15
£0.50 
£2.05 for first
sheet and
thereafter
£0.10 per sheet 
Please
See
Section
A18 
£2.50 
Same as
photocopy
charges see A18 
£2.20 for first
sheet and
thereafter
£0.10 per sheet 
April 2023 
April 2023
April 2023 
April 2021
Page 305

Page 306

Page 16 of 68
REF SERVICE CODE
S/M/SD
BUDGET
2023/24
CHARGE
2023/24
CHARGE
2024/25
DATE OF LAST
CHANGE 
3D Printing    Standard Setup
Fee - £2 plus £1
per 50g used.
(Minimum charge
of £3) 
Standard Setup
Fee -  £2.50 plus
£1.00 per 50g
used. (Minimum
charge of £3.50) 
April 2022 
D1h Heritage searches (per hour)  £ £34.00 £36  April 2023
D1j Learning Centre 1:1 tuition   £27.00 £29 April 2023
D2 Elgin Library
accommodation per hour 
Community (small – capacity
1-10 people)
Community (medium –
capacity 11-50 people)
Community (large – capacity
51+ people) 
Private/commercial (small –
capacity 1-10 people)
Private/commercial (medium –
capacity 11-50 people)
Private/commercial (large –
capacity 51+ people) 
Requests for bookings can be
considered out-with normal
hours at an additional cost per
booking per hour (cost will be
determined on request) 
£15,000 
£10.00 
£13.00 
£18.00 
£20.00 
£26.00 
£36.00 
£10.75 
£13.75 
£19.25 
£21.25 
£27.50 
£38.00 
April 2021
Page 306

Page 307

Page 17 of 68
SECTION E: EDUCATION 
REF SERVICE CODE
S/M/SD
BUDGET
2023/24
CHARGE
2023/24
CHARGE
2024/25
DATE OF LAST
CHANGE
E2. SPORTS COACHING
Sports coaching sessions 
Active Start Session (45 
mins) 
Walking Sports 
Trampolining/specialist
sessions 
£    
(includes £    
FitLife) 
£4.40 
£4.40 
£3.00 
£4.40 
£4.65 
£4.65 
£3.20 
£4.65 
April 2023 
New April 2023 
MORAY MUSIC CENTRE 
Moray Music Centre weekly
fee   
£5.00  £5.50  April 2023 
E3. SCHOOL MEALS 
Primary School Meals 
(Secondary School meals are
priced per item selected) 
£
£2.40 
Cafeteria system
– charge per item 
£2.45 
Cafeteria system
– charge per item
Priced individually
and will be
uplifted an
average by 5.7%.
Head of Service
has delegated
authority on
pricing to balance
income and
uptake item. Free
August 2023 
Page 307

Page 308

Page 18 of 68
REF SERVICE CODE
S/M/SD
BUDGET
2023/24
CHARGE
2023/24
CHARGE
2024/25
DATE OF LAST
CHANGE
school meal
allowance is
£2.65  
E4 ADULT SITTING SQA
Examination in school 
Set by SQA Set by SQA 
Page 308

Page 309

Page 19 of 68
SECTION F: ECONOMIC GROWTH AND DEVELOPMENT SERVICES 
REF SERVICE CODE
S/M/SD
BUDGET
2023/24
CHARGE
2023/24
CHARGE
2024/25
DATE OF LAST
CHANGE
F1 Environmental Health    
F1a. Pest Control Services
Wasps and bees (visit fee)
Fleas (visit fee)
All other services (visit
fee) 
£ 
£90 + VAT
£167   + VAT  
£100  + VAT
PEST CONTROL
WILL CEASE ON
31 MARCH 24
DUE TO CUTS 
April 2023
April 2023
April 2023 
Bait treatment units, if
required, as listed below (to
cover cost) 
Various, at full
cost – will
increase at next
purchase date 
K-Othrine WC250  £6.19 + VAT
(2.5g)   
Maxforce  £8.44 + VAT
(each)   
Pro Control Insect Killer  £7.88 + VAT (per
can)   
Wasp Nest Destroyer  £11.18 + VAT
(per can) 
April 2020 
Neosorexa Rat Gold Packs  £10.77 + VAT
(1kg) 
April 2020 
Control Blox  £9.06 + VAT
(1kg) 
April 2020 
Brombait  £8.58 + VAT
(3kg) 
April 2020 
Brodifacoum  £9.56 + VAT
(1kg)   
Coopex Mini Generators  £5.06 + VAT
(each)   
Ficam  £7.05 + VAT
(0.5kg)
£     + VAT
(0.5kg)
April 2020
Page 309

Page 310

Page 20 of 68
REF SERVICE CODE
S/M/SD
BUDGET
2023/24
CHARGE
2023/24
CHARGE
2024/25
DATE OF LAST
CHANGE
F1b. Release of stray dog M Nil £26.75 + kennel
fees
£ 28.25 + kennel
fees
April 2023
F1c. Water Sampling 
Type B Risk assessment /
review of risk assessment 
Type B sampling including
preparatory work and admin
charge includes cost of
analysis 
Regulation 2 Samples 
Regulation 2 request sample
(in addition to statutory
sample) 
Verification samples (to check
corrective works) 
M
M
£  
£50 –stat max 
£132 + VAT per
sample – stat
max 
£261 (no VAT) 
£237 + VAT 
Analysis costs +
£107 
£50 –stat max 
£132 + VAT per
sample – stat
max 
£ 276 (no VAT) 
£ 250   + VAT 
Analysis costs + £
113   
April 2017 
April 2019 
April 2023 
April 2023 
April 2023
F1d. Swimming pools per sample  £50 + VAT £ 52.85   + VAT April 2023
F1e. Disposal of Unsound Food per
request:
Commercial 
Domestic 
£101 + cost of
disposal
£77 + cost of
disposal 
£106.75    + cost
of disposal
£81.40    + cost of
disposal
April 2023
F1f. Burial of Indigent dead
Investigation etc  
£107 + VAT
per hour
£113 + VAT per
hour
April 2023
Page 310

Page 311

Page 21 of 68
REF SERVICE CODE
S/M/SD
BUDGET
2023/24
CHARGE
2023/24
CHARGE
2024/25
DATE OF LAST
CHANGE
F1g. Non EU Export Certificates
(per certificate) 
£ £73.56 £78 April 2023 
Attestations to Hubs    £110 £116 April 2023 
EU Export Certificates    £45 £47.60 April 2023
F1h Public Health duties (Hourly
rate per officer) (as F1f) 
£107 + VAT per
hour 
£ 113   + VAT per
hour
April 2023
F1i Section 50 (Licensing) Food
Hygiene Certificate 
£ £96.83 £102.35 April 2023 
Cooksafe Books (per book)   £5.78 + p+p £6.10   + p+p April 2023 
Butchersafe Books (per book)  £5.78 + p+p £ 6.10   + p+p April 2023
F1j Residential Caravan Sites: 
Sites with 50 Pitches and
under 
£ 
First application
£905 
Renewal £656 
First application
£957    
Renewal £693 
April 2023 
Sites with over 50 pitches    First application
£1,262
Renewal £725
First application 
£1334    
Renewal £766
April 2023
K2. Landlord Registration fees  S £ As set As set 
F2 Contaminated Land      
F2b  Level 1 Land Use Report    £178.60 + VAT £188.78 + VAT April 2023
F2c  Level 2 Land Use Report    £428.90 + VAT £453.35 + VAT April 2023
Page 311

Page 312

Page 22 of 68
REF SERVICE CODE
S/M/SD
BUDGET
2023/24
CHARGE
2023/24
CHARGE
2024/25
DATE OF LAST
CHANGE
F2d  Contamination Enquiry Report 
Single Residential Property
<1000m² 
Report Single Residential
property >1000 m² and all
commercial requests 
£103.66 
£103.66 per hour 
£109.57 
£109.57  per hour 
April 2023 
April 2023
F3 Building Standards 
F3a.  Building Warrant Fees set by
Scottish Government
S  As set As set May 2005 
F3b
F3c 
F3d 
Letters of Comfort (LTC) 
Confirmation of completion
Property Inspection of
unauthorised works (for up to 2
site visits)
LTC visit 3, and each
subsequent visit) 
£  
£524 
£788 
£123 
£530 
£796 
£129 
April 2023 
April 2023 
April 2023 
Building Standards Pre
application check 
£89 £95 April 2023 
For major construction projects
requiring Building Standards
input to the design process 
£142 per hour £148 per hour April 2023 
F4 Development Management 
F4a Planning Application Fees –
set by Scottish Government
S  As set  As set  2017 
Page 312

Page 313

Page 23 of 68
REF SERVICE CODE
S/M/SD
BUDGET
2023/24
CHARGE
2023/24
CHARGE
2024/25
DATE OF LAST
CHANGE
F4b 
F4c 
F4d 
Recoverable expenditure: 
Neighbour Notification 
Section 34 Advertising and
Other Advertising (e.g to
establish owner of property) 
Property History Check 
£  
£127 
£207 
£66 
£133 
£213 
£72 
April 2023 
April 2023 
April 2023
F4k High Hedges  £474 £480 April 2023
F4l Pre-application advice on
Major Development proposals 
£1,671 £3,500 April 2023
F4m Pre-application advice on all
local development proposals
(except single houses in the
town & countryside) 
£557 £563 April 2023
F4n Pre-application advice on
single houses in the town &
countryside 
£167 £173 April 2023
F4n
1
Pre-application advice on
commercial developments and
changes of use (max floor
space 500 sqm)  
£167 £173 April 2023
F4o Development enquiry fees for
proposed householder only.
All other development types
require a Certificate of
Lawfulness of Proposed Use
or Development  
£66 £72 April 2023 
Page 313

Page 314

Page 24 of 68
REF SERVICE CODE
S/M/SD
BUDGET
2023/24
CHARGE
2023/24
CHARGE
2024/25
DATE OF LAST
CHANGE
F4p Enquiries relating to proposed
works to Listed Buildings (only
one fee payable if it relates to
a householder, local and or
major development enquiry).  
£66 £72 April 2023
F4q Requests for Non-material
Variation of previously
approved scheme: 
£210  £218 April 2023
F4r  Pre-application advice for
Community Developments  
Free Free April 2021
F4s Pre-application advice for
Town Centre Developments 
Free Free 
F4t Pre-application advice for
Proposals supporting the
Council’s food growing
strategy 
Free Free 
F4u Pre-application advice and
Planning Applications for
Works or alterations to
improve access, safety, health
or comfort for a disabled
person at their home. 
Free Free 
Page 314

Page 315

Page 25 of 68
REF SERVICE CODE
S/M/SD
BUDGET
2023/24
CHARGE
2023/24
CHARGE
2024/25
DATE OF LAST
CHANGE
F4v Compliance with conditions
Where an applicant seeks
confirmation that the terms set
out in a condition attached to a
planning permission have
been met.
Note: There is no charge in
respect of conditions attached
to listed building consent or
conservation area consent. 
Where an enquiry relates to a
householder development,
which would benefit from
planning application fee
exemption under Reg 7
(means of access, etc. for
disabled persons). 
Where an enquiry relates to a
development, which would
benefit from planning
application fee reduction under
Schedule 1, Art 7,
(Community Councils). 
£100 for each
request
No limit on
number of
request 
Fee Waived in
Full
Reduced and
waived fees
subject
to agreement by
Council 
Fee reduced by
half.
Reduced and
waived fees
subject
to agreement by
Council 
£106 for the first
3 conditions then
£106 per
condition
thereafter 
Fee Waived in
Full
Reduced and
waived fees
subject
to agreement by
Council
Fee reduced by
half.
Reduced and
waived fees
subject
to agreement by
Council 
April 2022 
April 2022 
April 2022 
Page 315

Page 316

Page 26 of 68
REF SERVICE CODE
S/M/SD
BUDGET
2023/24
CHARGE
2023/24
CHARGE
2024/25
DATE OF LAST
CHANGE
F4w Discharge of conditions
Where an applicant seeks
approval of information
submitted in respect of a
condition attached to a
planning permission, for the
agreement of the planning
authority.
Note: there is no charge in
respect of conditions attached
to listed building consent or
conservation area consent. 
Where an enquiry relates to a
householder development,
which would benefit from
planning application fee
exemption under Reg 7
(means of access, etc. for
disabled persons). 
Where an enquiry relates to a
development, which would
benefit from planning
application fee reduction under
Schedule 1, Art 7, (Community
Councils). 
£100 for each
request
No limit on
number of
request 
Fee Waived in
Full
Reduced and
waived fees
subject to
agreement by
Council 
Fee reduced by
half.
Reduced and
waived fees
subject to
agreement by
Council. 
£106 for the first
3 conditions then
£106 per
condition
thereafter. 
Fee Waived in
Full
Reduced and
waived fees
subject
to agreement by
Council
Fee reduced by
half.
Reduced and
waived fees
subject
to agreement by
Council 
April 2022 
April 2022 
April 2022 
Page 316

Page 317

Page 27 of 68
REF SERVICE CODE
S/M/SD
BUDGET
2023/24
CHARGE
2023/24
CHARGE
2024/25
DATE OF LAST
CHANGE 
F4x
Surcharges (application
from 1 October 2022
Applications made in
retrospect
Where an application for
planning permission is made
after the whole development
being applied for has been
carried out in full. 
Applications made in
retrospect
Where an application for
planning permission is made
when the development being
applied for has been started
but not completed, including
the revised design of a
previously granted planning
permission. 
Fee calculated in
accordance with
tables above,
plus one quarter 
Fee calculated in
accordance with
tables above,
plus one quarter 
Fee calculated in
accordance with
tables above,
plus one quarter 
Fee calculated in
accordance with
tables above,
plus one quarter 
October 2022
F4y NEW CHARGE 
Compliance/Withdrawal of
an Enforcement Notice   
£250 New Charge -
April 2024
F4z NEW CHARGE
Pre-application advice for
householder developments   
£100 New Charge -
April 2024 
NOTE  Brief non-specific or general pre-application advice which can be given over the telephone. 
Planning and Development
Page 317

Page 318

Page 28 of 68
REF SERVICE CODE
S/M/SD
BUDGET
2023/24
CHARGE
2023/24
CHARGE
2024/25
DATE OF LAST
CHANGE
F4e  Moray Local Development
Plan 2015 (hard copy) 
£75 plus P&P
Individual
volumes £25 plus
P&P except
volume 2 £50
plus P&P 
£75 plus P&P
Individual
volumes £25 plus
P&P except
volume 2 £50
plus P&P 
April 2021 
Moray Local Development
Plan 2020 (hard copy)  
£75 plus P&P
Individual
volumes £25 plus
P&P except
volume 2 £50
plus P&P 
£75 plus P&P
Individual
volumes £25 plus
P&P except
volume 2 £50
plus P&P 
April 2023
F4g  Supplementary Guidance
(hard copy) 
£12:50 + p&p  £12:50 + p&p  April 2021 
F4g
1
Viability Assessments    Applicant to pay
District Valuer’s
fee 
Applicant to pay
District Valuer’s
fee 
Approved at
Committee 2019
F4h Charge for naming streets &
housing 
£    
Address 1   £119 £126 April 2023 
Addresses  2 – 9   £119 + £34per
additional
addresses  2 - 9
(min £153 /max
£391)
£126 + £36  per
additional
addresses  2 - 9
(min £162 /max
£414)
April 2023 
Addresses 10 – 19   £391 + £25 per
additional  
£414 + £27 per
additional  
April 2023
Page 318

Page 319

Page 29 of 68
REF SERVICE CODE
S/M/SD
BUDGET
2023/24
CHARGE
2023/24
CHARGE
2024/25
DATE OF LAST
CHANGE
addresses  10 -
19 (min £416 
/max £641)
addresses  10 -
19 (min £441    
/max £684) 
Addresses 20 – 49   £641  + £19    per
additional
addresses 20 - 49
(min £660 /max
£1,211) 
£684 + £21 per
additional
addresses 20 - 49
(min £705 /max
£1314) 
April 2023 
Addresses 50 – 99   £1,211+ £16 per
additional
addresses 50 - 99 
(min £1,227 /max
£2,011)
£1314 + £18 per
additional
addresses 50 - 99 
(min £1332 /max
£2214)
April 2023 
Addresses 100+  £2,066 + £15 per
additional
addresses 100+ 
(min £2,026)
£2214 + £16 per
additional
addresses 100+ 
(min £2230)
April 2023 
NEW CHARGE
Sponsored Street Name 
Negotiated Fee New Charge -
April 2024
F5  Building Standards /
Development Management    
F5a Section 50 (Licensing)
Certificate 
£62 £68 April 2023 
F5b Copy Documents – Planning
Decisions Notice / Building
Warrants & Certificate of
Completion 
Search Retrieval Fee – No
Reference Number given 
£ £33 
£23 
£75 
£50 
April 2023 
April 2023 
Page 319

Page 320

Page 30 of 68
REF SERVICE CODE
S/M/SD
BUDGET
2023/24
CHARGE
2023/24
CHARGE
2024/25
DATE OF LAST
CHANGE       
NEW CHARGE
Extra plans and documents
£10 per item (max pages of
documents 10) 
NEW CHARGE
Extra plans and documents
over 10 pages 
£10 
£20
New Charge –
April 2024 
New Charge –
April 2024       
Cost of documents – A4 plans   £0.28 £0.40 plus p+p  April 2023 
Cost of documents - A3 plans   £0.54 £0.60 plus p+p  April 2023 
Cost of documents - A2 plans   £11.50 £11.50 plus p+p  April 2023 
Cost of documents - A1 plans 
Microfiche and Digital Copies –
any amount total cost
NO LONGER REQUIRED 
£13.50 
£11.50
£13.50  April 2023 
April 2023
F6 Trading Standards 
F6a Measuring Instruments for
Liquid Fuels and Lubricants
Per nozzle 
Testing of Credit Card
acceptor (per unit regardless
of number of nozzles) 
£  
£101 
£133 
£107 
£141 
April 2023 
April 2023
Page 320

Page 321

Page 31 of 68
REF SERVICE CODE
S/M/SD
BUDGET
2023/24
CHARGE
2023/24
CHARGE
2024/25
DATE OF LAST
CHANGE
F6b  Weights Submitted for Test
Weights not exceeding 25kg  £14.40 first
£9.12 others 
£15
£10
April 2023
F6c  Weighing Instruments
Not exceeding 15kg 
Not exceeding 100kg 
Not exceeding 2 tonne 
Exceeding 2 tonnes (where the
submitter provides labour and
testing equipment) 
Exceeding 2 tonnes (where
Trading Standards provides
labour and testing equipment) 
Cost recovery for hire of
Weighbridge Testing Unit 
Included
above  £43 
£66 
£99 
£267 
By quotation – full
cost recovery 
£45 
£70 
£105 
£282 
By quotation – full
cost recovery 
April 2023 
April 2023 
April 2023 
April 2023
F6d  Road Tanker – Liquid Fuel
Measuring Instrument Above
100 Litres
Wet Hose (2 testing liquids) 
Wet Hose (3 testing liquids)   
£134 
£201 
£142 
£213 
April 2023 
April 2023 
Page 321

Page 322

Page 32 of 68
REF SERVICE CODE
S/M/SD
BUDGET
2023/24
CHARGE
2023/24
CHARGE
2024/25
DATE OF LAST
CHANGE
F6e  Other Services 
Certificate of Errors or
Calibration Certificate on test
of weighing/measuring
equipment 
£57  £60  April 2023 
Hire of weights per day:  £   
Quantity not exceeding
205kg  
£16  £17 April 2023 
Quantity exceeding 205kg  £39 £41 April 2023
F6f  Hourly Rate & Minimum Call
Out Charge for Services not
listed above 
Trading Standards Officer 
Support Officer 
£83
£47 
£88
£50 
April 2023
April 2023
F6g  The Explosives Regulations
2014 
S £ As specified in
current Health
and Safety Fees
Regulations 
As specified in
current Health
and Safety Fees
Regulations 
April 2012
F6h  The Petroleum
(Consolidation) Regulations
2014 
S £ As specified in
current Health
and Safety Fees
Regulations 
As specified in
current Health
and Safety Fees
Regulations 
April 2012
F6j Public Weighbridge
Operator Competence Test
and Certificate  
£80 £85  April 2023 
Page 322

Page 323

Page 33 of 68
REF SERVICE CODE
S/M/SD
BUDGET
2023/24
CHARGE
2023/24
CHARGE
2024/25
DATE OF LAST
CHANGE
F7 Economic Development
Markets coming to Moray 
All commercial operators using
the Plainstones in Elgin
1 visit is up to 3 days
maximum.  
£  
£120.81  £127.70  April 2023 
Page 323

Page 324

Page 34 of 68
SECTION G: WASTE MANAGEMENT, LAND AND PARKS 
REF SERVICE CODE
S/M/SD
BUDGET
2023/24
CHARGE
2023/24
CHARGE
2024/25
DATE OF LAST
CHANGE
G1 Waste collection and
disposal  
All charge are net of VAT 
G1b Collection of bulky household
refuse (white and non-white
goods) 
£ £24 £26.67  April 2023 
G1d Disposal of Commercial
Fridges/Freezers 
SD  Individually
assessed 
Individually
assessed
April 2016 
G1e. Residual Waste per bin per
week  
140 ltr bin  
240 ltr bin  
360 ltr bin  
660 ltr bin
1100 ltr bin
1280 ltr bin
Assessed per sack or
equivalent  
£  
£5.29
£9.04
£13.61
£23.84
£39.73
£46.21
£4.52 
£5.60
£9.55
£14.40
£25.25
£41.60
£49
£4.80 
April 2023 
G1f.  Recyclable Trade Waste per
bin per week  
140 ltr bin  
240 ltr bin  
360 ltr bin  
660 ltr bin
1100 ltr bin
Assessed – Cardboard
packaging 
£  
£2.11
£3.59
£5.42
£9.37
£15.59
Based on
equivalent bin
size 
£2.25
£3.80
£5.75
£10.00
£16.50
Based on 
equivalent bin
size 
April 2023 
Page 324

Page 325

Page 35 of 68
REF SERVICE CODE
S/M/SD
BUDGET
2023/24
CHARGE
2023/24
CHARGE
2024/25
DATE OF LAST
CHANGE
G1g.  Recycling Centre Pass  £246.88 £300 April 2023
G1h.  Disposal of commercial and
industrial waste (per tonne) 
For difficult waste 
£ £29.00 
£46.68 
£31.00 
£50.00 
April 2023 
G1i. Skip/Container hire - based on
recovery of costs i.e.
location/frequency of
service/disposal costs 
£ Individually
assessed 
Individually
assessed 
G1j. Disposal of green waste from
landscape gardeners 
£ £35.59 £38.00 April 2023
G1k Charge per suite of bins/boxes
for new properties 
£ £132.00 £140.00 April 2023
G1l Household garden waste
permits 
£ £36 pa per bin £50.00 pa per bin  April 2023
G1m Use of Waste Disposal points
by Caravans/Camper Vans 
£7.00 £7.50 April 2023
G1n Sub-contractor administration
fee for Moray servicing bins as
part of a national waste
contract 
£ NA 10% of applicable
weekly fee
New Charge
G2 Burial Grounds  All charges are net of VAT 
G2a. Sale of Lair
Non-Resident Sale of Lair
Fee for transfer of lair 
£ £906.58
£1,919.74
£50.49
£
£
£
April 2023
April 2023
April 2023
Page 325

Page 326

Page 36 of 68
REF SERVICE CODE
S/M/SD
BUDGET
2023/24
CHARGE
2023/24
CHARGE
2024/25
DATE OF LAST
CHANGE
Non-Resident Fee for transfer
of Lair
£930.14 £  April 2023
G2b. Interment Charges
Under 18 years of age
Over 18 years of age
Fee for Non-Moray
Resident 
£ 
Nil
£1,044.58
£1,917.50 
Nil
£
£
April 2023 
G2c. Additional charge for
interments
Saturday (over 18 years) 
Non-Moray Resident
Sunday (over 18 years) 
Non-Moray Resident 
Included
above 
£522.85
£959.31
£1,044.58
£1,917.50 
£
£
£
£
April 2023 
G2d. Purchase of Cremated
Remains Lair in Garden of
Remembrance
Non-Moray Residents 
Fee for interment of casket
Fee for Non-Moray Resident 
Additional charge for Caskets:
Saturday 
Non-Moray Resident
Sunday 
Non-Moray Resident 
Scattering of Ashes on Grave
Non-Moray Resident 
£Nil 
£520.61
£1,181.47 
£246.84
£561 
£123.42
£280.50
£246.84
£561 
£42.64
£105.47 
£
£
£
£
£
£
£
£
£
£
April 2023 
Page 326

Page 327

Page 37 of 68
REF SERVICE CODE
S/M/SD
BUDGET
2023/24
CHARGE
2023/24
CHARGE
2024/25
DATE OF LAST
CHANGE
G2e. Fee for digging foundations for
headstone 
Non-Resident Fee for digging
foundations for headstone 
£ £120.05 
£346.70 
£
£
April 2023 
G2f. Search Fee  Nil £74.05  £  April 2023
G2g. Disinterments  Nil Individually
assessed
Individually
assessed 
N/A 
G3 Hiring a space for an event
in a park or open space 
All charges are net of VAT 
Fairgrounds  £   
G3a. Stalls & Children’s ride-on
units 
 April-September (per day
for first seven days)
 October-March (per day for
first seven days)
Thereafter per day:
April-September
October-March 
£15.37 
£7.24 
£7.24
£3.93 
£16.25 
£7.65 
£7.65
£4.15 
April 2023 
Page 327

Page 328

Page 38 of 68
REF SERVICE CODE
S/M/SD
BUDGET
2023/24
CHARGE
2023/24
CHARGE
2024/25
DATE OF LAST
CHANGE
G3b. Large ride-on units (dodgems,
waltzer, big wheel etc) 
 April-September (per day
for first seven days)
 October-March (per day for
first seven days)
Thereafter per day:
April-September
October-March 
£53.75 
£21.75 
£21.75
£10.92 
£57.00 
£23.00 
£23.00
£11.55 
April 2023
G3c Circuses 
Small Circus 
Deposit 
Daily Fee
Admin fee 
Large Circus 
Deposit 
Daily Fee
Admin fee 
£500 
£375.87
£55.00 
£500 
£500.41
£110 
£500 
£400
£60 
£500 
£530
£120 
April 2022 
April 2023
April 2023 
April 2022 
April 2023
April 2023 
Page 328

Page 329

Page 39 of 68
REF SERVICE CODE
S/M/SD
BUDGET
2023/24
CHARGE
2023/24
CHARGE
2024/25
DATE OF LAST
CHANGE
G4 Commercial Events 
Small – up to 199 expected
attendees / capacity
Deposit
Admin Fee
Daily Fee 
Medium – between 200 - 499
expected attendees / capacity
Deposit
Admin Fee
Daily Fee 
Large – between 500 – 1000
expected attendees / capacity
Deposit
Admin Fee
Daily Fee 
Major – more than 1000
expected attendees / capacity
Deposit
Admin Fee
Daily Fee 
£0 
£500
£55
£330 
£1,000
£55
£385 
£2,500
£110
£440 
£5,000
£110
£550 
£500
£60
£350 
£1000
£60
£410 
£2500
£250
£470 
£5000
£250
£585
April 2022 
April 2022
April 2023 
April 2022
April 2023 
April 2022
April 2023 
April 2022
April 2023
G5 Community Charity and Not for
Profit Events 
Deposit
Admin Fee
Daily 
£0 
Nil
Nil
Nil 
Nil
Nil
Nil
April 2022
Page 329

Page 330

Page 40 of 68
REF SERVICE CODE
S/M/SD
BUDGET
2023/24
CHARGE
2023/24
CHARGE
2024/25
DATE OF LAST
CHANGE
G6 Photography Shoot
(Commercial) – Full Day
Deposit
Admin Fee
Daily fee 
Filming (Commercial)
Deposit
Admin Fee 
Daily fee 
£0 
TBC – Note (1)
POA
£150 
TBC – Note (1)
POA (Price on
Application)
£125 per hour 
TBC – Note (1)
POA
£160 
TBC – Note (1)
POA (Price on
Application)
£135 per hour 
April 2022
April 2023
April 2022 
April 2022 
April 2023 
G7 Personal Trainer / Bootcamp –
Commercial
Deposit
Admin Fee
Daily fee 
£0 
TBC – Note (1)
£0
£0 
April 2022
G8 Electricity Charge for Events   Full cost
recovery. 
£0.27 p/kWh @ 1
April 2023
Full cost
recovery. 
£0.31 p/kWh @ 1
April 2024
April 2023 
Page 330

Page 331

Page 41 of 68
REF SERVICE CODE
S/M/SD
BUDGET
2023/24
CHARGE
2023/24
CHARGE
2024/25
DATE OF LAST
CHANGE
G9 Memorial Benches (park or
green space); 
OR 
Memorial Benches (park or
green space):
Phoenix
Lowther
Phoenix Jubilee
Clifton Picnic Table
Pembridge Picnic Table (with
wheelchair accessible area) 
Price on
application 
£1,100
£1,500
£1,620
£1,200
£1,460 
(above prices
excl VAT –
website page with
detail is being
provided to
support this. 
Charges cover
the bench and
materials/labour
to install)
Price on
application 
£1,165
£1,590
£1,715
£1,270
£1,545 
(above prices
excl VAT –
website page with
detail is being
provided to
support this. 
Charges cover
the bench and
materials/labour
to install)
New Charge
April 2023       
Lets for advance units and for approved non-operating days due to inclement weather will be charged at a third of the above prices. 
(1) TBC – To be confirmed on application subject to potential risk of ground damage 
Page 331

Page 332

Page 42 of 68
SECTION H: FLEET, ROADS AND TRANSPORTATION 
REF SERVICE CODE
S/M/SD
BUDGET
2023/24
CHARGE
2023/24
CHARGE
2024/25
DATE OF LAST
CHANGE
H1 Fleet Services  All charges are net of VAT 
H1a Taxis
Taxi Test
Taxi Re-Test
Meter Calibration 
Duplicate Certificate 
£ 
£62.20
£62.20
£17.80 
£15.50 
£65.50
£65.50
£18.80 
£16.00 
April 2023 
April 2021 
H1b Prohibition Clearance on Taxis   £15.50 £16.00 April 2021
H1c  M.O.T Certificate Issue with
Taxi Test
M.O.T Class 7 Vehicles 
M.O.T Test Class 4 
M.O.T Partial Re-Test 
M
M
M
£ These are
charges set by
DVSA 
These are
charges set by
DVSA 
April 2023
H1d Duplicate MOT & Taxi
Compliance Certificate 
Note: DVSA now online
service but can still be issued
aligned taxi certificated (very
rarely issued) 
M  These are
charges set by
DVSA 
These are
charges set by
DVSA 
April 2023 
H1e 
H1g
Vehicle Rectification Certificate 
Minibus Drivers Assessment 
£ DVSA charge 
£67.10
DVSA charge 
£70.92
April 2023 
April 2023 
Page 332

Page 333

Page 43 of 68
REF SERVICE CODE
S/M/SD
BUDGET
2023/24
CHARGE
2023/24
CHARGE
2024/25
DATE OF LAST
CHANGE
H2 Roads  All charges are net of VAT 
H2a  Consent for excavating in a
road by a private party: 
Road opening permit – no
apparatus – minor works
Road opening permit –
standard works
Road opening permit + permit
for installation of plant – major
works (per unit of inspection) 
Additional inspection fee for
installation of plant. As defined
in the Scottish Road Works
Register (SRWR) 
Penalty for overrun of road
opening permit – minor works
Standard Fixed Penalty Notice.
As defined in the Road Works
(Fixed Penalty) Regulations 
£170 
£305 
£800 
In line with
SRWR charge 
In line with
SRWR charge 
£180 
£322 
£846 
In line with
SRWR charge 
In line with
SRWR charge 
April 2023
rounded up/down 
H2b. Road occupations 
Scaffolding 
Up to 7 days
Up to 14 days
Up to 21 days
Up to 28 days
Up to 35 days
Up to 42 days 
£  
£90
£165
£245
£320
£410
£485 
£95
£174
£259
£338
£433
£513
April 2023
rounded up/down 
Page 333

Page 334

Page 44 of 68
REF SERVICE CODE
S/M/SD
BUDGET
2023/24
CHARGE
2023/24
CHARGE
2024/25
DATE OF LAST
CHANGE 
Extension to existing permit:
Up to 7 days*
Up to 14 days*
Up to 21 days*
Up to 28 days*
Up to 35 days*
Up to 42 days* 
*Penalty for over-run of permit
Standard Fixed Penalty Notice
(+ cost of permit)  (As defined
in the Road Works (fixed
penalty) Regulations 2008 
£90
£165
£245
£320
£410
£485 
As set by the
Scottish Road
Works
Commissioner 
£95
£174
£259
£338
£433
£513 
As set by the
Scottish Road
Works
Commissioner 
April 2023
rounded up/down 
Mobile Scaffold Tower 
Crane/Cherry Picker permits
up to a week 
Temporary traffic signals up to
7 days 
Builders Skips up to 7 days
Building materials up to 7 days 
£65 
£150 
£130 
£65
£65 
£69 
£159 
£137 
£69
£69 
April 2023
rounded up/down 
Page 334

Page 335

Page 45 of 68
REF SERVICE CODE
S/M/SD
BUDGET
2023/24
CHARGE
2023/24
CHARGE
2024/25
DATE OF LAST
CHANGE 
Additional fee for deposition of
skip/builders material in Car
Park per bay up to 7 days (free
car parks / low turnover) 
Additional fee for deposition of
skip/builders material in Car
Park per bay up to 7 days (in a
medium/high turnover car
park) 
Licensed vehicle parked in
road to service
works/operations with
pedestrian area between 11:00
and 16:00 
£40 
£65 
£65 
£42 
£69 
£69 
April 2023
rounded up/down 
April 2023
rounded up/down 
April 2023
rounded up/down 
Page 335

Page 336

Page 46 of 68
REF SERVICE CODE
S/M/SD
BUDGET
2023/24
CHARGE
2023/24
CHARGE
2024/25
DATE OF LAST
CHANGE 
H2c.
Contractors vehicle parked in
road to service
works/operations within
Commerce Street, Elgin 
Temporary Traffic Orders
Up to and including five days*
Traffic Order*
Any extension to order* 
Community Events
Commercial (Admission
Charges and Stallholder Fees) 
Community Events (Mass
Events / Free Access) 
Seasonal Community Events
(Parades/Street Parties) 
Remembrance Day Services 
* Penalty for over-run of permit 
Standard Fixed Penalty Notice
(+cost of permit) as defined in
the Road Works (fixed penalty)
Regulations 2008   
£
£65 
£340
£1,615
£1,370 
£230 
£110 
£25 
Free 
As set by the
Scottish Road
Works
Commissioner 
£69 
£359
£1,707
£1,448 
£243 
£116 
£26 
Free 
As set by the
Scottish Roads
Works
Commissioner 
April 2023
rounded up/down 
Page 336

Page 337

Page 47 of 68
REF SERVICE CODE
S/M/SD
BUDGET
2023/24
CHARGE
2023/24
CHARGE
2024/25
DATE OF LAST
CHANGE
H2d. Traffic Data & undertaking
Temporary Traffic Surveys 
Full survey data provided by
post or email (Commercial) 
As above (Voluntary) 
Undertaking a temporary
survey for maximum 7 days
and providing full survey data
(Commercial)
As above (Voluntary) 
Collation and provision of
collision data (up to 2 hours
preparation) 
Collation and provision of
collision data (for each
additional hour preparation or
part thereof) 
£  
£185 
£100 
£520 
£260 
£155 
£75 
£196 
£106 
£550 
£275 
£164 
£79 
April 2023
rounded up/down
H2e. Road Status Enquiry
(outwith Formal Property
Enquiry System)
Application for information for
road classification from the
statutory list of public
highways.  Charge per
application 
£  
£50 + VAT =
£60.00 
£53.33  + VAT =
£64.00
April 2023
rounded up/down 
Page 337

Page 338

Page 48 of 68
REF SERVICE CODE
S/M/SD
BUDGET
2023/24
CHARGE
2023/24
CHARGE
2024/25
DATE OF LAST
CHANGE
H2f. Private Parties/
Accident Damage
Fee for engineer/inspector 
15% of value of
construction work 
15% of value of
construction work
April 2017
H2g. Provision of signage on
request 
Tourist Signposting 
Local Destination Signs  
Individually
calculated to
cover the cost of
design,
manufacture and
erection 
Individually
calculated to
cover the cost of
design,
manufacture and
erection 
April 2017
H2h Outdoor Hospitality 
Placement of furniture and
non-furniture on public footway 
NEW    £175.00
As Approved at
Special Moray
Council
25/10/23
H3. CAR PARKING CHARGES  £ Inclusive of VAT 
High Turnover Sites
Moray Street, Ladyhill Road,
St Giles levels 5 & 6, Cooper
Park 8am- 12 noon (first 30
mins free - Cooper Park only)
Period:
Up to 30 mins
Up to 1 hour
Up to 2 hours
Up to 3 hours
Up to 4 hours 
£0.50
£1.50
£2.00
£2.50
£3.00 
removed
£1.00
£2.00
£2.50
£3.00 
January 2024
Page 338

Page 339

Page 49 of 68
REF SERVICE CODE
S/M/SD
BUDGET
2023/24
CHARGE
2023/24
CHARGE
2024/25
DATE OF LAST
CHANGE 
Medium Turnover Sites
Northfield Terrace, South
Street, Hall Place, St Giles
Levels 1-4, North Port, North
College Street West 
Period:
Up to 30 mins
Up to 1 hour
Up to 2 hours
Up to 3 hours
Up to 4 hours
4+ hours   
£0.50
£1.50
£2.00
£2.50
£3.00
£5.00 
removed
£1.00
£2.00
£2.50
£3.00
£5.00
January 2024 
Low Turnover Sites
Lossie Green, Lossie Wynd,
Batchen Lane  - all levels 
All Day
Weekly Ticket 
£1.00
£5.00 
£2.00
£10.00 
January 2024 
Elgin Railway Station (all day)
Elgin Railway Station (weekly) 
Parking Notices
Parking Notices (if paid within
14 days) 
£2.00 
£10.00 
£80.00
£60.00 
£2.00 
£10.00 
£80.00
£60.00 
May 2018 
April 2018 
Staff Car Parks – per day  Included
above
£1.00 £2.00 November 2019 
Season Tickets includes VAT
High Turnover Site 
Medium Turnover Site 
Included
above  n/a no all day
parking
£45.00 
n/a no all day
parking
£50.00  January 2024
Page 339

Page 340

Page 50 of 68
REF SERVICE CODE
S/M/SD
BUDGET
2023/24
CHARGE
2023/24
CHARGE
2024/25
DATE OF LAST
CHANGE 
Elgin Railway Station
Low Turnover Site 
Charge for opening multi
storey car parks outwith
opening hours 
£40.00
£20.00 
£54.00 
£40.00
£40.00 
£70.00 
May 2018
January 2024 
January 2024 
Electric Charge Point (per
Visit) - flat rate to ensure
operation of unit remains cost
neutral 
Rapid chargers  - per kWh.
(Minimum charge £1.00) 
Rapid Charger Overstay fee
(applied after 70 minutes from
start of session) 
Fast chargers - per kWh.
(Minimum charge £1.00 
NEW 
NEW 
NEW 
£0.30 per kw/h Removed see below 
£0.56 
£10.00 
£0.43 
April 2023 
January 2024 
January 2024 
January 2024
H4. Roads Construction Consent
(RCC) 
£   April 2016 
Inspection fee   £64 per £1,000 of
road bond value 
£     per £1,000 of
road bond value 
Second or subsequent RCC
application 
£287 £ 
Page 340

Page 341

Page 51 of 68
REF SERVICE CODE
S/M/SD
BUDGET
2023/24
CHARGE
2023/24
CHARGE
2024/25
DATE OF LAST
CHANGE
H5 Public Transport Unit     
H5a Hire of vehicle (without
driver) Excluding charges
made under fixed contract with
annual RPI increases
Daily charge
Plus mileage charge:
0-130 miles (per mile) 
£50 
£1.25 
£55 
£1.33 
April 2023
Increase due to cost
of running fleet 
10% 
8% 
April 2023
10%
8% 
rounded up
rounded up 
H5b Hire of vehicle (with driver)
Minimum daily charge
0-130 miles (per mile) 
Driver per hour Mon – Fri
Driver per hour weekend &
public holiday 
£50
£1.25 
£20
£25 
£55
£1.33 
£22
£27
H5c Duplicate school bus pass   £10.00 £15.00  Last increase
August 2018
H5d Community bus fares  £21,000 Adult Single £3-
£9
Adult Return £5-
£9
10 Journeys £20-
£36
Annual £800 -
£1,400 
Adult Single £3-
£9
Adult Return £5-
£9
10 Journeys £20-
£36
Annual £800 -
£1,400 
April 2022
Actual
implementation May
2023 
Page 341

Page 342

Page 52 of 68
SECTION I: HARBOURS 
REF SERVICE CODE
S/M/SD
BUDGET
2023/24
CHARGE
2023/24
CHARGE
2024/25
DATE OF LAST
CHANGE 
Commercial harbours
Leisure harbours 
£ All charges are net of VAT unless
indicated  £
I1 Cargo Vessels     
I1a Cargo Vessel – per 7 days or
part thereof (per dead weight
all told ton (where GT exceeds
DWAT, payment will be based
on GT) 
£0.58 £0.61 April 2023 
I1b Cruise ships - per 7 days or
part thereof (per dead weight
all told ton - where GT exceeds
DWAT)
NEW   £0.50 
I1c Self Propelled and towed
barges per 7 days or part
thereof (per m2 or part thereof) 
£1.12 1.18 April 2023
I1c
(i)
All CTV per day (per length,
per metre or part thereof) 
All CTV per month (per length,
per metre or part thereof) non
refundable  
All CTV per annum (per length,
per metre or part thereof) non
refundable 
£3.53 
£69.51 
£774.02
£4.00 
£81.00 
£851.00
April 2023
10% increase in line
with neighbouring
ports -rounded
up/down
I1d Tugs and maintenance/service
vessels – per 7 days or part
thereof per m or part thereof  
£5.36 
Minimum charge
£80.00
£6.00
Minimum charge
£85.00
April 2021
rounded up
Page 342

Page 343

Page 53 of 68
REF SERVICE CODE
S/M/SD
BUDGET
2023/24
CHARGE
2023/24
CHARGE
2024/25
DATE OF LAST
CHANGE
l1f Compulsory garbage
(cargo)(on arrival per visit) 
£80.33 £85.00 April 2021
rounded up
l1g Storage of cargo equipment on
piers and quaysides per 7
days of part thereof (per m² or
part thereof) 
£5.36 £6.00 April 2021
rounded up
l1h Handling mooring ropes (per
hour or part thereof per
person) during normal working
hours (08:00 – 18:00) 
Handling mooring ropes (per
hour or part thereof per person
– outwith normal working hours
18:00 - 08:00) 
£55.70 
£100.23
£59.00 
£106.00
April 2023
rounded up
I1i Passengers embarking and
disembarking per trip including
pleasure vessels, sea angling
and excluding passengers on
pilot boat and vessels being
charged as CTV – per
passenger 
£1.18 £1.25 April 2023
I1j Cleaning of piers following
cargo movement – per hour or
part thereof 
£246.11 £260.14 April 2023
I1k Fast Rescue Craft – per
entry/departure 
£55.16 £58.30 April 2023
Page 343

Page 344

Page 54 of 68
REF SERVICE CODE
S/M/SD
BUDGET
2023/24
CHARGE
2023/24
CHARGE
2024/25
DATE OF LAST
CHANGE
I1l Cleaning of Piers when waste
left by any vessel (excl cargo) 
£50 £53.00 April 2021
rounded up/down
I1m Annual compound charge for
chartered vessels (including
sea angling, wildlife, tourism –
charge inclusive of garbage
and passenger fees)
Up to 10m – per annum
10m to 15m – per annum
Over 15m – per annum   
£1,000
£1,500
£2,000 
£1,057.00
£1,586.00
£2,114.00 
rounded up/down 
April 2022
April 2023
April 2023
I1n Supply of ice:
Per tonne 
Per standard fish box  
£66 
£2.75 
£70.00 
£3.00
rounded up/down
April 2023 
April 2023 
I2 Fishing Vessels    April 2020
I2a Composition Fee (entries to
qualify for quarterly
composition fee = 3 entries in
1st month)     
Vessels:     
Under 10m   £39.11 £41.34 
10-17m   £58.85 £62.20 
17-22m   £87.36 £92.34 
22-26m   £106.94 £113.04 
26-30m   £124.79 £131.90 
Over 30m  £203.18 £214.76 
I2b Single Entry (per 7 days or part
thereof – including vessels laid
up)     
Page 344

Page 345

Page 55 of 68
REF SERVICE CODE
S/M/SD
BUDGET
2023/24
CHARGE
2023/24
CHARGE
2024/25
DATE OF LAST
CHANGE 
Vessels:     
Under 10m   £39.11 £41.34 
10-17m   £58.85 £62.20 
17-22m   £87.36 £92.34 
22-26m   £106.94 £113.04 
26-30m   £124.79 £131.90 
Over 30m   £203.18 £214.76 
I2e Surcharge after a continuous
period of 12 weeks 
50% on top of
charges above 
50% on top of
charges above 
April 2006 
l2f Compulsory garbage charge
(on arrival, per visit)
Up to 10m
Over 10m
This charge will be levied on only one
occasion per vessel per week   
£10.00
£20.00 
£11.00
£22.00
rounded up/down 
April 2021
April 2021
l2g Storage of Fishing equipment
in net storage area (per m² per
month or part thereof)  
£1.63 £2.00  April 2020
rounded up/down 
I2h Vessels less than or equal to
10m in length engaged in
licensed creel fishing 
Where non declaration of fish
landings per quarter, per
vessel 
Recreational
dues plus 2% of
catch value 
£420.00 
Recreational
dues plus 2% of
catch value 
£444.00 
April 2012 
April 2020
rounded up/down
I3 Recreational Vessels     
Page 345

Page 346

Page 56 of 68
REF SERVICE CODE
S/M/SD
BUDGET
2023/24
CHARGE
2023/24
CHARGE
2024/25
DATE OF LAST
CHANGE
I3a Pontoon Berth - Annual
berthing charges (inc VAT)
Over 3 - 4m
Over 4 - 5m
Over 5 – 6m
Over 6 – 7m
Over 7 – 8m
Over 8 – 9m
Over 9 – 10m
Over 10 – 11m
Over 11 – 12m
Over 12 – 13m
Over 13 – 14m
Over 14 – 15m
Over 15 – 16m
Over 16 – 17m
Over 17 – 18m
Over 18 – 19m
Over 19 – 20m
Each metre thereafter   
£366.96
£458.70
£550.44
£642.18
£733.92
£825.66
£917.40
£1,009.14
£1,100.88
£1,192.62
£1,284.36
£1,376.10
£1,467.84
£1,559.58
£1,651.32
£1,743.06
£1,834.80
£91.74 
£388.00
£485.00
£582.00
£679.00
£776.00
£873.00
£970.00
£1,067.00
£1,164.00
£1,261.00
£1,358.00
£1,455.00
£1,552.00
£1,649.00
£1,746.00
£1,843.00
£1,940.00
£97.00
April 2023
rounded up/down
Page 346

Page 347

Page 57 of 68
REF SERVICE CODE
S/M/SD
BUDGET
2023/24
CHARGE
2023/24
CHARGE
2024/25
DATE OF LAST
CHANGE 
Wall/Loose Mooring - Annual
berthing charges (inc VAT)
Over 3 - 4m
Over 4 - 5m
Over 5 – 6m
Over 6 – 7m
Over 7 – 8m
Over 8 – 9m
Over 9 – 10m
Over 10 – 11m
Over 11 – 12m
Over 12 – 13m
Over 13 – 14m
Over 14 – 15m
Over 15 – 16m
Over 16 – 17m
Over 17 – 18m
Over 18 – 19m
Over 19 – 20m
Each metre thereafter 
£306.00
£382.50
£459.00
£535.50
£612.00
£688.50
£765.00
£841.50
£918.00
£994.50
£1,071.00
£1,147.50
£1,224.00
£1,300.50
£1,377.00
£1,453.50
£1,530.00
£76.50 
£324.00
£405.00
£486.00
£567.00
£648.00
£729.00
£810.00
£891.00
£972.00
£1,053.00
£1,134.00
£1,215.00
£1,296.00
£1,377.00
£1,458.00
£1,539.00
£1,620.00
£81.00
April 2023
rounded up/down
Page 347

Page 348

Page 58 of 68
REF SERVICE CODE
S/M/SD
BUDGET
2023/24
CHARGE
2023/24
CHARGE
2024/25
DATE OF LAST
CHANGE 
Hardstanding - Annual
berthing charges (inc VAT)
Over 3 - 4m
Over 4 - 5m
Over 5 – 6m
Over 6 – 7m
Over 7 – 8m
Over 8 – 9m
Over 9 – 10m
Over 10 – 11m
Over 11 – 12m
Over 12 – 13m
Over 13 – 14m
Over 14 – 15m
Over 15 – 16m
Over 16 – 17m
Over 17 – 18m
Over 18 – 19m
Over 19 – 20m
Each metre thereafter 
£244.80
£306.00
£367.20
£428.40
£489.60
£550.80
£612.00
£673.20
£734.40
£795.60
£856.80
£918.00
£979.20
£1,040.40
£1,101.60
£1,162.80
£1,224.00
£61.20 
£260.00
£325.00
£390.00
£455.00
£520.00
£585.00
£650.00
£715.00
£780.00
£845.00
£910.00
£975.00
£1,040.00
£1,105.00
£1,170.00
£1,235.00
£1,300.00
£65.00 
April 2023
rounded up/down
I3c Discounted rate for pensioners
(boats less than 7m in length)
(for current beneficiaries only) 
75% of current
relevant charge
75% of current
relevant charge 
I3d Trailers and vessel moving
equipment –
intended to be left on harbour
property for storage (outwith period of
launch/recovery of vessels) 
per annum
NEW   £200.00 + VAT =
£240.00 
Page 348

Page 349

Page 59 of 68
REF SERVICE CODE
S/M/SD
BUDGET
2023/24
CHARGE
2023/24
CHARGE
2024/25
DATE OF LAST
CHANGE
I3e Rover Ticket - in line with
Aberdeenshire Council 
£66.67 + VAT =
£80
£ 75.00 + VAT =
£90.00
April 2021 
I3f Visiting Vessel Day Ticket per
day or part thereof 
£16.67 + VAT £20.83 + VAT = 
£25.00
April 2019
I4 Harbour Dues     
I4e Use of port/harbour to
demonstrate or test equipment/
vessel or any other similar
event (commercial) - per day
or part thereof   
£257.04  £271.69  April 2023 
I4f Use of port/harbour for
community/ charity events 
£107.10 £113.20  April 2021
I4g Use of harbour for
paddlesports etc 
By individual
agreement
By individual
agreement
April 2019
I4h Hire of Single Gangway   £37.49  £40.00  April 2021
rounded up/down
I4i Hire of Forklift and operator (on
application -subject to availability) 
NEW   £70.00 ph
Minimum 2 hours 
I4j Attendance of harbour staff
outside of normal working
hours and/or public holidays 
NEW   Full cost recovery 
I5 Wharfage    
Page 349

Page 350

Page 60 of 68
REF SERVICE CODE
S/M/SD
BUDGET
2023/24
CHARGE
2023/24
CHARGE
2024/25
DATE OF LAST
CHANGE
I5a Minimum charge – all
categories per tonne (change
in pricing arrangement) 
£224.91 £237.73  April 2023
I5b Basic materials, manufactured
goods, fuels (other than
petroleum spirit) per tonne 
£1.21 £1.28  April 2020 
I5c Wet fish, including fish
consigned to or from any
harbour not owned by Moray
Council 
Wet fish “That part of landings
of white fish and shellfish in
excess of £7,500 in value”  
2.5%
Ad valorem 
1.5%
Ad valorem
2.5%
Ad valorem 
1.5%
Ad valorem 
April 2008 
April 2008
I5d Wood, Lumber, Cork,
Chipboard and Blockboard per
cubic metre  
£1.05  £1.11 April 2020
I5f Foods (other than wet fish) per
tonne 
£1.21  £1.28 April 2020
I5g Fabricated Goods per tonne  £7.99 £8.45 April 2023
I5h “Loyalty” Reduction in Charges
Above 25,000 tonnes    Scale rate less
5% 
Price on
application 
April 2006 
Page 350

Page 351

Page 61 of 68
REF SERVICE CODE
S/M/SD
BUDGET
2023/24
CHARGE
2023/24
CHARGE
2024/25
DATE OF LAST
CHANGE
l5j Dangerous Goods (any
hazardous chemicals –
explosives or inflammables)
per tonne 
£85.21 £90.00 April 2020
rounded up/down
I5k Heavy lifting for extraordinary
specialised activities, eg
transformers, wind turbine
parts
50-99 tonnes – per tonne
100-149 tonnes – per tonne
150-249 tonnes – per tonne
Over 250 tonnes – per tonne 
£1.61
£2.01
£2.42
£2.82 
£1.77
£2.21
£2.66
£3.10 
April 2023
10% increase in line
with neighbouring
ports
I6 Slipway and repair pads     
I6a Any recreational vessel using a
slipway inclusive of one entry
and one exit from the harbour
per occasion 
Any commercial vessel using a
slipway inclusive of one entry
and one exit from the harbour
per occasion 
Season ticket for recreational
unlimited use of any Council
slipway, valid for 12 months,
commencing 1 April per vessel 
Season ticket for commercial
unlimited use of any Council   
£16.67 + VAT 
£25 + VAT 
£61.20 + VAT 
£425.00 + VAT 
£20.83 + VAT =
£25.00 
£ 26.67+ VAT=
£32.00 
£65.00 +
VAT = £78.00 
£499.17+
VAT= £539.00 
April 2019
9% increase in line
with neighbouring
ports 
April 2019
9% increase in line
with neighbouring
ports    
April 2021
9% increase in line
with neighbouring
ports  
April 2021
9% increase in line
with neighbouring
ports
Page 351

Page 352

Page 62 of 68
REF SERVICE CODE
S/M/SD
BUDGET
2023/24
CHARGE
2023/24
CHARGE
2024/25
DATE OF LAST
CHANGE
slipway, valid for 12 months,
commencing 1 April per vessel 
I7 Weighbridges 
Goods shipped or unshipped
on which harbour dues are
payable per tonne (to nearest
tonne) 
Other goods per weighing 
£0.37 
£12.50 + VAT =
£15.00 
£0.39 
£13.33 + VAT =
£16.00   
April 2021 
April 2023
rounded up/down 
I8 Pilotage     April 2021
I8a Per gross registered ton 
Minimum charge 
£0.43 
£254.85
£0.45 
£270.00
April 2021 
April 2023
rounded up/down 
I8b Detention Charge for Late
arrival of vessel - per hour or
part thereof 
£254.85  £270.00  April 2023
rounded up/down 
I8c Hire of Pilot-Boat and crew per
hour or part thereof including
towing support activity and
similar
Per passenger or crew
member 
£254.85  £270.00  April 2023
rounded up/down 
Page 352

Page 353

Page 63 of 68
REF SERVICE CODE
S/M/SD
BUDGET
2023/24
CHARGE
2023/24
CHARGE
2024/25
DATE OF LAST
CHANGE
I8d Pilot Boat Maintenance
Charge “per dead weight all
told ton” (to be applied when
pilotage not requested)
(where GT exceeds DWAT,
payment will be based on GT) 
£0.16 £0.17  April 2021
I9 Supply of Water     
I9a Cargo vessels:
Minimum Charge
Charge per tonne or part
thereof 
£10.00
£5.00 
£11.00
£5.30 
April 2021
April 2021
rounded up/down
I9b Fishing Vessels regardless of
whether a composition fee has
been paid
Up to 10m
10-20m
Over 20m
On each occasion     
£5.51
£11.03
£17.03 
£6.00
£12.00
£18.00 
April 2021
April 2021
April 2021
rounded up/down
I9c Recreation vessels on each
occasion 
£5.51 £6.00  April 2021
rounded up/down
I10 Supply of electricity - cost
per electrical unit
Up to 3 hours
Per Electrical unit    
£10.71 + VAT
£0.33 + VAT 
£12.00    + VAT
£0.35    + VAT 
April 2021
April 2021
rounded up/down
I12 Fuel transfer - cost per tonne  £2.68 £3.00  April 2021
rounded up/down
Page 353

Page 354

Page 64 of 68
REF SERVICE CODE
S/M/SD
BUDGET
2023/24
CHARGE
2023/24
CHARGE
2024/25
DATE OF LAST
CHANGE
I13 Ground rent for container/fuel
tank (per sq m per annum (pro
rata)) 
£16.07 £17.00  April 2021
rounded up/down
I14 Hire of Room at Harbour
Office
Standard per hour or part
thereof
Junior/over 60/charity per hour
or part thereof
Business Rate per hour or part
thereof 
£26.00 
£20.00 
£36.00 
£27.50 
£21.00 
£38.00
April 2023 
Page 354

Page 355

Page 65 of 68
SECTION K: HOUSING AND PROPERTY 
REF SERVICE CODE
S/M/SD
BUDGET
2023/24
CHARGE
2023/24
CHARGE
2024/25
DATE OF LAST
CHANGE
K1. Housing Support:  Warden’s
Service:  The Moray Council
Sheltered Housing 
£ £36.73 £38.82 April 2023
K2. Homeless Temporary
Accommodation Service  
£179.04 £189.25 September 2023 
K3 Recharge of Council’s
Estates’ costs 
£   
K3a Applications to purchase
ground for incorporation into
gardens: 
Initial fee (confirming
ownership, valuation,
preparing plan, title check by
Legal Section) 
Final fee (processing
application) 
Committee report preparation 
£350 
£550 
£450 
£370 
£580 
£475 
April 2023 
April 2023 
April 2023
K3b Applications for Site
Compounds and Mobile
Trading on Council land 
Initial fee (confirming
ownership, consultation with
Council officers and local
members, drafting of licence) 
£175  £185  April 2023 
Page 355

Page 356

Page 66 of 68
REF SERVICE CODE
S/M/SD
BUDGET
2023/24
CHARGE
2023/24
CHARGE
2024/25
DATE OF LAST
CHANGE
Complex transactions  Hourly rate of £49
- £100 per hour
Hourly rate of £52  
- £106 per hour
April 2023
K3c. Consents: 
(a) Assignations of lease 
(b) Sub leases: standard
leases 
(c) Early lease terminations:
standard charge 
Complex transactions 
Discount for not-for-profit
tenants   
£450 minimum 
£250 minimum 
£330 
Hourly rate of £49  
- £100 per hour 
Hourly rate of
£24.50 - £50 per
hour 
£475 minimum 
£300 minimum 
£350 
Hourly rate of £52
- £106 per hour 
Hourly rate of £26
- £53 per hour  
April 2023 
Above inflation
increase to
reflect amount
of work required 
K3d Utility companies: 
Scottish Water/Gas - 
Electricity
Telecoms 
Electricity/Telecoms (complex) 
200% Rydes
Scale 
£350 minimum
£350 minimum 
Hourly rate of £49  
- £100 per hour 
200% Rydes
Scale 
£370 minimum
£370 minimum 
Hourly rate of £52
- £106 per hour 
April 2023 
Page 356

Page 357

Page 67 of 68
REF SERVICE CODE
S/M/SD
BUDGET
2023/24
CHARGE
2023/24
CHARGE
2024/25
DATE OF LAST
CHANGE
K3e Private parties 
Water and Sewerage  200% Rydes
Scale 
200% Rydes
Scale 
April 2011
K3f Public consultations for
common good property
transactions 
Standard transaction –
alienable property 
Complex transactions   
£250 minimum. 
Hourly rate of £49
- £100 per hour 
as well as
expenses
incurred. 
£265 minimum. 
Hourly rate of £52
- £106 per hour 
as well as
expenses
incurred. 
April 2023
K3g Recharge of Council’s Estates’
costs in relation to
discretionary property
transactions/work 
Hourly rate of £49  
- £100 per hour 
Hourly rate of £52
- £106 per hour 
April 2023
K4 Late Payment of Commercial
Rents    
April 2023
K4a Initial investigation and contact
with tenant and issue of
correspondence pursuing
payment 
£50 £65 Above inflation
increase to
reflect amount
of work required
K4b Negotiate and issue Payment
Arrangement 
£75 £100 Above inflation
increase to
reflect amount
of work required
Page 357

Page 358

Page 68 of 68
REF SERVICE CODE
S/M/SD
BUDGET
2023/24
CHARGE
2023/24
CHARGE
2024/25
DATE OF LAST
CHANGE 
K4c Instruct legal action  £100 £106 
K4d Copy documents    £50 £75 Above inflation
increase to
reflect amount
of work required 
K4e Sheriff Officers   Recovery of
actual cost to the
Council 
Recovery of
actual cost to the
Council 