1.0    INTRODUCTION 
1.1 At the Community Services Committee on 9 March 2023 it was agreed:- 
The Committee agreed to request that the Executive Director with responsibility
for Education prepare an initial report outlining the way forward and potential
for a proposal in terms of the Schools (Consultation) (Scotland) Act 2010 which
would allow for an initial business case to be formulated with a view to replacing
the existing outdated Campbeltown primary schools of Dalintober and
Castlehill, and that the completed report be presented to a meeting of the
Community Services Committee. 
1.2 This update report outlines the steps taken to fulfil this request. 
1.3 The Council recently received notification that it was successful in obtaining
Learning Estate Investment Programme (LEIP) funding from the Scottish
Government for a new campus on Mull, which is the Councils number one priority
as determined in the Learning Estate Strategy.  This means that the Council’s
principal focus of the Education capital budget and priority for strategic change will
be required to support the Council contribution to the Mull project over the coming
few years. 
1.4 Therefore, at this time there is no available budget to support the funding of a
significant change project to the learning estate in Campbeltown. Notwithstanding
this, both asset sustainability work and investment will continue to be delivered in
Campbeltown (and elsewhere) and recent works in 2023 have improved some
areas of condition.  Work undertaken in this review will also be able to be
recommenced if or when funding becomes available.   
2.0    RECOMMENDATIONS 
2.1    It is recommended that the Community Services Committee: 
2.1.1  Note the Campbeltown feasibility study that has been undertaken and
acknowledge that this can be retained for review at a later date should
funding become available; and 
2.1.2  Agree that at this time, the Councils Learning Estate Strategy has
determined that Mull is the number one priority and therefore must take
precedence for any funding. 
ARGYLL AND BUTE COUNCIL  COMMUNITY SERVICES COMMITTEE 
COMMERCIAL SERVICES /
EDUCATION 
14 DECEMBER 2023 
FEASIBILITY STUDY – CAMPBELTOWN EDUCATION ESTATE

Page 2

3.0  DETAIL 
3.1 The Council worked with a consultant team to undertake a feasibility study to
look at a number of potential options to fulfil this request from the Committee
and understand potential options and high level costs associated with them. 
Options Appraisal 
3.2 The feasibility study looked at a number of options and high level costings to
deliver these range from £4m to £24m. 
Prioritisation / Learning Estate Investment Programme (LEIP) 
3.3 The Learning Estate Strategy carried out in 2021 determined that Mull and Islay
were the top 1 and 2 priorities for the Council.  A submission for funding from the
Learning Estate Improvement Programme was made in October 2022 to support
a new campus on Mull.  The Council was advised in October 2023 that the bid
had been successful.  The funding however only supports up to 50% of eligible
costs and therefore requires significant investment from the Council.  The
affordability of this project will mean that the Council is not in a position to commit
to any further strategic investment in education estate at this time. 
3.4 The feasibility study carried out on the learning estate in Campbeltown has
identified a number of viable options which could be taken forward should funding
become available in the future.   
Investment in Campbeltown 
3.5 There have been recent capital works undertaken to both Dalintober Primary and
Castlehill Primary to improve the learning environment within both schools in
2023.  Whilst this does not take either school to the standard of a new build, it has
made the learning spaces much more conducive to the type of space that the
Council aspires to create for all learners.  There will continue to be a focus on
improving asset sustainability but strategic investment to the quantum identified
in para 3.2 is not currently affordable.   
3.6 The LEIP funding for a new campus on Mull means that the focus for the
immediate future must be on delivery of the funding requirements for this project. 
A review of the Learning Estate Strategy priorities could mean that should funding
become available in the future, the feasibility study undertaken can be reviewed
with a view to implementing an option identified. 
4.0 IMPLICATIONS 
4.1 Policy – none 
4.2 Financial – none 
4.3  Legal – none 
4.4  HR – none 
4.5  Fairer Scotland Duty: 
4.5.1   Equalities - protected characteristics – none 
4.5.2   Socio-economic Duty – none 
4.5.3  Islands – none

Page 3

4.6 Climate Change – none 
4.7 Risk – none 
4.8  Customer Service – none 
Douglas Hendry – Executive Director with responsibility for Commercial Services
and Education 
Councillor Yvonne McNeilly – Policy Lead for Education 
For further information contact: 
Ross McLaughlin, Head of Commercial Services 
Jennifer Crocket, Chief Education Officer, Head of Education
Wendy Brownlie, Head of Education