Democracy Spraffa

Agenda Document Pack - Audit, Performance and Risk Committee - 30/01/2025

Moray Council · 30 January 2025
Back to Audit, Performance and Risk Committee — 30 January 2025 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

Audit, Performance and Risk Committee 
Thursday, 30 January 2025 
Council Chambers 
NOTICE IS HEREBY GIVEN that a Meeting of the Audit, Performance and Risk
Committee, Council Chambers, Council Office, High Street, Elgin, IV30 1BX on
Thursday, 30 January 2025 at 14:00 to consider the business noted below. 
AGENDA 
1. Welcome and Apologies 
2. Declaration of Member's Interests 
3. Minute of meeting of 26 September 2024 5 - 10
4. Action Log of Meeting of 26 September 2024 11 - 12
5. Quarter 2 (July to September 2024) Performance
Report
13 - 38
6. Quarter 2 (July to Septemember) Performance Report
for Children and Families and Justice Social Work
39 - 68
7. Internal Audit Section - Update Report 69 - 82
8. Internal Audit Section Completed Projects Report 83 - 126
9. Childrens Services Joint Inspection Improvement Plan
2024
127 - 142
10. Payment Verification 143 - 146
Page 1

Page 2

Item(s) which the Committee may wish to consider
with the Press and Public excluded   
11. CONFIDENTIAL Update on Improvement Plan for Adult
Social Care Commissioning
• 8 & 9. Information on proposed terms and/or expenditure to be
incurred by the Authority; 
Watching the Meeting
You can watch the webcast live by going to: 
http://www.moray.gov.uk/moray_standard/page_43661.html    
Webcasts are available to view for 1 year following the meeting.  
You can also attend the meeting in person, if you wish to do so,
please come to the High Street entrance door and a member of
staff will be let into the building. 
Page 2

Page 3

MORAY INTEGRATION JOINT BOARD 
SEDERUNT 
Mr Sandy Riddell  (Chair)  
Councillor Scott Lawrence  (Voting Member)
Mr Derick Murray  (Voting Member)
Councillor Ben Williams  (Voting Member)
Mr Sean Coady  (Member)
Mrs Jeanette Netherwood  (Member)
Ms Deborah O'Shea  (Member)
Ms Judith Proctor  (Member)
Ms Janette Topp  (Member)  
Ms Deirdre McIntyre  (Non-Voting Member) 
Clerk Name: Caroline O'Connor
Clerk Telephone: 07779 999296
Clerk Email: committee.services@moray.gov.uk 
Page 3

Page 4

Page 4

Page 5

MINUTE OF MEETING OF THE AUDIT, PERFORMANCE AND RISK COMMITTEE 
Thursday, 26 September 2024 
Remote Locations via Connect Remote, 
PRESENT 
Mr Sean Coady, Councillor Scott Lawrence, Mr Derick Murray, Mrs Jeanette
Netherwood, Ms Deborah O'Shea, Ms Judith Proctor, Mr Sandy Riddell 
APOLOGIES 
Ms Deirdre McIntyre, Ms Janette Topp, Councillor Ben Williams 
IN ATTENDANCE 
Interim Chief Officer, Angela Pieri, Engagement Lead and Andrew Wallace, Audit
Manager, both of Grant Thornton, Service Manager (Primary Care Contracts), Carl
Campbell, Service Manager (Education and Social Care), Social Work Service
Manager, Chief Internal Auditor, Chief Financial Officer, Corporate Programme
Manager, Ms L Van Zyl, Service Manager and Mrs L Rowan, Committee Services
Officer as Clerk to the Committee.   
1         Chair 
Mr Sandy Riddell chaired the meeting. 
2         Declaration of Member's Interests 
Mr Riddell stated for transparency that he was Chair of the Mental Welfare
Commission Scotland.  
The Committee noted that there were no other declarations of member's interests.  
3         Minute of meeting of 27 June 2024 
The minute of the meeting of 27 June 2024 was submitted and approved. 
Item 3.
Page 5

Page 6

4         Action Log of Meeting of 27 June 2024 
The Action Log of the meeting of 27 June 2024 was discussed and updated
accordingly.  
5         External Auditors Report to Those Charged with Governance 
The meeting had before it a report by the Chief Financial Officer asking the
Committee to consider the reports to those charged with governance from the Board's
External Auditor for the year ended 31 March 2024.  
The Committee joined the Chair in thanking those involved in providing the External
Auditor's Report and thereafter unanimously agreed to note the reports from the
External Auditor as set out in Appendices 1 and 2 of the report and recommended
them for approval by the Moray Integration Joint Board.  
6         2023-24 Audited Annual Accounts 
The meeting had before it a report by the Chief Financial Officer presenting to the
Committee the Audited Annual Accounts for the year ended 31 March 2024.  
Following consideration, the Committee agreed to note the Audited Annual Accounts
for the financial year 2023/24 and the letter of Representation and recommended
them to the Moray Integration Joint Board for approval. 
7         Quarter 1 (April-June 2024) Performance Report 
Mr Coady, Head of Service joined the meeting during discussion of this item.  
The meeting had before it a report by the Corporate Programme Manager updating
the Committee on performance as at Quarter 1 2024 (April-June).  
During discussion, it was noted that there were several areas where it was
acknowledged that performance is poor, and it was queried whether future reports
could include narrative explaining what measures are being taken to improve
performance in these areas.  
In response, the Interim Chief Officer agreed to include narrative explaining what
measures are being taken to improve performance in areas of poor performance in
future reports.  
During further discussion, the Chair noted that the report stated that there was no
need for an Equality Impact Assessment as there would be no impact on people with
protected characteristics as a result of the report and sought assurance that the
Committee was complying with it's legal responsibilities in relation to equalities and
suggested that this section be expanded in future reports.  
In response, the Interim Chief Officer assured the Committee that the Board is
committed to acknowledging any inequality in minority groups and advised that it was
her intention to refresh equalities training in the near future.  
Following consideration, the Committee unanimously agreed to note: 
Page 6

Page 7

(i) the performance of local indicators for Quarter 1 (April to June 2024) as
presented in the Performance Report at Appendix 1; 
(ii) the analysis of the local indicators that have been highlighted and actions being
undertaken to address performance that is outside of acceptable target ranges as
detailed in Appendix 1 of the report; 
(iii) the performance for 2023/24 against the national indicators, where data is
published, as set out in Appendix 2 of the report; 
(iv) that future performance reports would include narrative explaining what measures
are being taken to improve performance in areas of poor performance; and 
(v) that the Interim Chief Officer intended to refresh equalities training in the near
future. 
8         Quarter 1 Performance Report for Childrens Social Work and Justice
Services 
The meeting had before it a report by the Chief Social Work Officer/Head of Service
informing the Committee on Children and Families and Justice Social Work
performance as at Quarter 1.  
During discussion surrounding the activity that had taken place within Children and
Families and Justice Social Work Section it was queried whether future reports could
include narrative in relation to outcomes resulting from the activity.  
In response, the Service Manager agreed to take this point forward and
include narrative in relation to outcomes resulting from the activity in future
performance reports.  
During further discussion, the Chair again noted that the Equalities paragraph in the
Summary of Implication Section stated that there was no equality impact as a result
of the report when he was aware of some good work that had taken place in this area
and suggested that this section be expanded to reflect this.  
In response, the Service Manager agreed to expand the paragraph in relation to
equalities in future reports.  
Following consideration, the Committee unanimously agreed to note the: 
(i) performance of local indicators for Quarter 1 as presented in the Performance
Report at Appendix 1; and 
(ii) analysis of the local indicators as detailed in Appendix 1 of the report; 
(iii) that future reports would: 
• include narrative in relation to outcomes resulting from the activity in future
performance reports;
• expand the equalities paragraph within the Summary of Implications section
of the report.    
Page 7

Page 8

9         Internal Audit Section - Completed Projects 
The meeting had before it a report by the Chief Internal Auditor providing an update
on audit work completed since the last meeting of the Committee.  
Following consideration, the Committee agreed to note the audit update. 
10         Public Sector Internal Audit Standards - External Quality Assessment of
Internal Audit 
The meeting had before it a report by the Chief Internal Auditor providing the
Committee with details of a recent external quality assessment undertaken of the
Council's Internal Audit Service.  
The Committee joined the Chair in commending all involved in the recent external
quality assessment and thereafter unanimously agreed to note the report and the
Action Plan prepared to address the issues raised in the external quality assessment
of internal audit.  
11         Payment Verification 
The meeting had before it a report by the Head of Service/Depute Chief Officer
providing an update on the review of the Payment Verification (PV) Assurance
Service provided by National Services Scotland (NSS) Practitioner Services Division
(PSD), on behalf of NHS Grampian.  
Following consideration, the Committee unanimously agree to note: 
(i) the arrangements in place in Grampian for the management of the payment
verification process; 
(ii) that the payment verification process has now fully restarted after pausing during
COVID-19; and 
(iii) the actions already taken to address the outstanding issues, with plans for future
action to include an update on progress to this committee in January 2025.  
12         Annual Performance Report 2023-24 
The meeting had before it a report by the Interim Chief Officer presenting the draft
Annual Performance Report 2023/24.  
The Chair thanked the Corporate Programme Manager for circulating the revised
Annual Performance Report for 2023/24 after several typos had been noted following
publication of the agenda.  
Following consideration, the Committee unanimously agreed to: 
(i) note the draft Annual Performance Report 2023/24 at Appendix 1 and
subsequent amendments previously circulated; and 
(ii) recommend to the Moray Integration Joint Board for approval and publication of
the Annual Performance Report 2023/24 by 30 September 2024.   
Page 8

Page 9

13         Internal Audit Section - Update Report [Para 6.2.5] 
The meeting had before it a report by the Chief Internal Auditor providing an update
on the work of the Internal Audit Section.  
Following consideration, the Committee unanimously agreed to note the contents of
the report.  
14         Internal Audit Section - Completed Project - Email Security [Para 6.2.5] 
The meeting had before it a report by the Chief Internal Auditor providing an update
on audit work completed since the last meeting of the Committee.  
Following consideration, the Committee unanimously agreed to note the audit update. 
15         Update on Improvement Plan for Adult Social Care Commissioning
[Para 6.2.2] 
The meeting had before it a report by the Head of Service/Chief Social Work Officer
updating the Committee about progress regarding the Improvement Plan for Adult
Social Care Commissioning.  
Following consideration, the Committee unanimously agreed to note: 
(i) the progress of the Improvement Plan as set out in Appendix 1 of the report; 
(ii) the progress within the report as at the end of July 2024 in relation to the
recommendations detailed in the Improvement Plan; and 
(iii) that the updated report includes details of contract values, timelines, and risks.   
Page 9

Page 10

Page 10

Page 11

MEETING OF MORAY INTEGRATION JOINT BOARD 
AUDIT, PERFORMANCE AND RISK COMMITTEE 
THURSDAY 26 SEPTEMBER 2024 
ACTION LOG 
Item
No.
Title of Report Action Required Due Date Action By Update for 
30 January 2025
1.  Quarter 1 (April-
June 2024)
Performance
Report
• future performance reports should
include narrative explaining what
measures are being taken to improve
performance in areas of poor
performance 
Future
Reports
Corporate
Programme
Manager
Quarter 2 report on
today’s agenda and
the improvement
work will continue as
‘business as usual’
2.  Quarter 1
Performance
Report for
Childrens Social
Work and Justice
Services
Future reports should: 
• include narrative in relation to
outcomes resulting from the activity
detailed within performance reports;
• expand the equalities paragraph within
the Summary of Implications section of
the report (action relevant to all
reports). 
Future
Reports
Head of
Service /
CSWO 
Service
Managers
Quarter 2 report on
today’s agenda and
the improvement
work will continue as
‘business as usual’
3.  Payment
Verification
Share this report with Aberdeen City and Shire
Integrated Joint Boards
ASAP Service
Manager
(Education
Action Complete
Item 4.
Page 11

Page 12

Item
No.
Title of Report Action Required Due Date Action By Update for 
30 January 2025
and Social
Care)
4.  Q1 Performance
Report
Information to be provided about the support
that is on offer to staff to help improve their
wellbeing.
27 June 2024 Sean
Coady/
Natalie
Jeffrey
HSCM is finalising a
Health and Safety
Delivery Plan, which
will be shared at the
next APR Committee
meeting along with
the Workforce
delivery plan.
5.  Internal Audit
Section –
Completed
Projects
Update report and progress delivery plan in
relation to the Moray Integrated Community
Equipment Store audit to be provided to next
meeting.
27 June 2024 Service
Manager,
Provider
Services
Report deferred as
per discussion with
APR Chair / Head of
Service and
Corporate Manager.
To be presented to
Committee March
2025 
6.  Joint Inspection of
Services for
Children & Young
People at Risk of
Harm
Improvement Action Plan and governance
structure chart to be provided to next meeting.
27 June 2024 Head of
Service /
CSWO
Report to be
presented to
Committee on 30
January 2025 as
agreed with Chair 
Page 12

Page 13

REPORT TO: MORAY INTEGRATION JOINT BOARD AUDIT, PERFORMANCE
AND RISK COMMITTEE ON 30 JANUARY 2025 
SUBJECT: QUARTER 2 (JULY - SEPTEMBER 2024) PERFORMANCE
REPORT 
BY:  CORPORATE PROGRAMME MANAGER 
1. REASON FOR REPORT 
1.1 To update the Committee on performance as at Quarter 2 2024 (July -
September). 
2. RECOMMENDATION 
2.1 It is recommended that the Committee consider, provide comment on
and note: 
i) the performance of local indicators for Quarter 2 (July to
September 2024) as presented in the Performance Report at
Appendix 1; and 
ii) the analysis of the local indicators highlighted and actions being
undertaken to address performance that is outside of acceptable
target ranges as detailed in Appendix 1. 
3. BACKGROUND 
3.1   The purpose of this report is to ensure the Moray Integration Joint Board
(MIJB) fulfils its ongoing responsibility to ensure effective monitoring and
reporting on the delivery of services and on the programme of work as set out
in its Strategic Plan. 
3.2   Appendix 1 identifies local indicators for the MIJB and the functions
delegated by NHS Grampian and Moray Council, to allow wider scrutiny by
the Board. 
4. KEY MATTERS RELEVANT TO RECOMMENDATION 
4.1 Local Indicators are assessed on their performance via a common
performance monitoring Red, Amber, and Green (RAG) traffic light rating
system. 
RAG scoring based on the following criteria:
GREEN If Moray is performing better than target.
AMBER If Moray is performing worse than target but within agreed
tolerance.
Item 5.
Page 13

Page 14

RED If Moray is performing worse than target by more than agreed
tolerance. 
4.2 The detailed performance report for quarter 2 is attached in Appendix 1.   
Summary
4.3 Performance within Health and Social Care Moray (HSCM) as demonstrated
by the agreed indicators up to the end of quarter 2 of the financial year
2024/25 are shown in figure 1. Three indicators are presenting as green, one
is amber and seven are red. This represents a reduced performance
compared to quarter 1 2024/25. 
4.4 Figure 1 provides a summary and the historical trends. A summary of
performance for each of the 6 reporting categories is provided below. 
EMERGENCY DEPARTMENT - AMBER
4.5 There was a slight increase in the rate per 1,000 this quarter from 21.5 to
22.6. This is below the number presenting at the same period last year and
this measure has been maintained around the target since October 2023. 
DELAYED DISCHARGES – RED   
4.6 The number of delays at the September quarter 2 snapshot was up to 44,
which is just below a high of 46 in February 2024 and significantly above 26 in
September 2023.  The figure at the snapshot was the highest point this year
and has been reduced, currently sitting around 31, but this figure is subject to
fluctuations. 
4.7 Bed days lost due to delayed discharges increased to 1,115 this quarter, up
from 922 in June 2024, well above 845 in the same period last year. This
mirrors the increase in the more volatile snapshot days (DD-01) measure and
demonstrates an increasing trend overall in Delayed Discharges over the
period. 
EMERGENCY ADMISSIONS – GREEN  
4.8 The rate of emergency occupied bed days for over 65s had a small decrease
to 2,603 this quarter and is still down on the high of 2,749 in quarter 4
2022/23. 
4.9 The emergency admission rate per 1000 population for over 65s has
increased through quarter 2 2023/24 to 189.9 and has now decreased four
quarters in a row to 177.7. Similarly, the number of people over 65 admitted to
hospital in an emergency also had hit a high of 133.2 in quarter 2 2023/24 and
has now decreased to 123.8 in quarter 2 2024/25. 
HOSPITAL RE-ADMISSIONS - RED
4.10 The 7-day re-admissions have increased above target of 3.7%  to 4.6%, and
the 28-day re-admissions have increased to above target of 7.9% for 2024/25
to 8.9%. 
MENTAL HEALTH – RED  
4.11 After achieving a low 40% in January 2024 there has been some fluctuation in
performance through 2024 which is now sitting at 60% of patients being
referred within 18 weeks at the end of quarter 2 2024/25. 
Page 14

Page 15

STAFF MANAGEMENT – RED   
4.12 Sickness absence for NHS employed staff has remained high at 6.4% at the
end of quarter 2 2024/25. Council employed staff sickness has decreased to
7.3% which is the lowest figure see in the last year. 
Page 15

Page 16

Figure 1 – Performance Summary 
Note: In order to match other national and local data sources indicators are showing the last month in the reporting quarter. 
*From May 2022, the census figures for April 2021 onwards include delays due to infection control measures in place at hospital (delay reason codes 26X and 46X)  
Q2 2324 Q3 2324 Q4 2324 Q1 2425 Q2 2425 Target
Jul-Sep Oct-Dec Jan-Mar Apr-Jun Jul-Sep
AE Accident and Emergency
AE-01 A&E Attendance rate per 1000 population (All Ages) 23.3 21.8 22.6 21.5 22.6 21.9 A
DD Delayed Discharges
DD-01 Number of delayed discharges (including code 9) at census point 26 37 43 33 40 26 R
DD-02
Number of bed days occupied by delayed discharges (including code 9) at census
point 845 1162 1501 922 1115 850 R
EA Emergency Admissions
EA-01 Rate of emergency occupied bed days for over 65s per 1000 population 2628 2598 2509 2606 2603 2681 G‚
EA-02 Emergency admission rate per 1000 population for over 65s 189.9 188.7 179.9 178.7 177.7 187 G‚
EA-03
Number of people over 65 years admitted as an emergency in the previous 12
months per 1000 population 133.2 132.9 125.8 124.2 123.8 131 G‚
HR Hospital Readmissions
HR-01 % Emergency readmissions to hospital within 7 days of discharge 3.9% 3.3% 4.4% 3.6% 4.6% 3.7% R
HR-02 % Emergency readmissions to hospital within 28 days of discharge 8.6% 7.9% 8.3% 6.9% 8.9% 7.9% R
MH Mental Health
MH-01
% of patients commencing Psychological Therapy Treatment within 18 weeks of
referral 50% 52% 57% 70% 60% 90% R
SM Staff Management
SM-01 NHS Sickness Absence (% of hours lost) 5.7% 6.6% 5.7% 7.0% 6.4% 4% R
SM-02 Council Sickness Absence (% of days lost) 8.4% 9.6% 9.7% 7.5% 7.3% 4% R                                                             
Health and Social Care Moray Performance Report                                          
Code Barometer (Indicator) RAG
Page 16

Page 17

5. AREAS NOT MEETING TARGETS  
Delayed Discharge - Red
5.1 There was an increase in the numbers awaiting discharge at census date to 40
and the number of bed days occupied by delayed discharges was 1115, up from
922 the previous quarter.  These figures are reflective of the whole system
challenges, which are being managed through a number of initiatives and there
are significant efforts being made across many teams to reduce delays. 
5.2 Community hospitals have a robust flow process that is managed daily to try to
support Dr Grays bed base and ensure people are in the most appropriate place
for the care and support they require.  There are several reasons why people are
delayed, with availability of support in the community remaining a key challenge,
especially for people living in rural locations.   Recruitment to internal care at
home teams has now reached the maximum number of hours available for
provision.  In the community, the level of unmet need reduced slightly but at the
end of September there were still 27 people waiting in hospital and 183 in the
community awaiting care packages amounting to 1,473 hours of care. 
Emergency Department - Amber
5.3 The A&E attendance rate has increased slightly to 22.6 which was the same as 
quarter 4 in 2023/24.  This is reflective of a system that is under pressure and
consistent with previous reports regarding the increasing demands and number
of patients presenting at the emergency department.  There continues to be
national and local communications to inform people of options and direct them to
alternative sources of urgent medical advice such as pharmacists, opticians and
dentists. 
.  
Hospital Re-admissions - Red
5.4 The re-admission rate at 7 days had been well below target until this quarter and
there was a similar peak in Quarter 2 last year.  There is also an increase in re-
admission rate at 28 days, which is also following a similar pattern to last year. 
Delayed Discharge and Flow Mitigation
5.5 Health and social care Moray, as part of NHS Grampian, will be joining a new
collaborative initiative Discharge Without Delays (DWD), being facilitated by
Health Intelligence Scotland.  DWD is a whole system programme for frail older
people currently accessing hospital services and will aim to use best practice,
individual services and related pathways into an integrated model that will strive
to deliver Comprehensive Geriatric Assessments, in a timely manner, whilst
ensuring no negative impacts from hospital induced harm or dependency to the
individual.   
5.6 This is an aspirational model, that will deliver an integrated, multi-disciplinary
community model, as early as possible when the frail older person begins to
show signs of deterioration, limiting the need for hospital admissions.  There has
been work being progressed by various parts of our system but this will be the
opportunity to utilise learning from other NHS Boards and partnerships to collate
progress and develop the integrated model.  A robust set of whole system
outcomes have been determined and are targeted to be delivered by December
2026.  This programme is just being established in NHS Grampian and a report
with further details will be submitted to this committee in March. 
Page 17

Page 18

Mental Health - Red
5.7 The percentage of patients commencing Psychological Therapy within 18 weeks
in quarter 2 has reduced from 70% in quarter 1 to 60%. 
5.8 As reported in quarter 1 there are several factors contributing to the fluctuation in
the number of referrals made to the service and the length of time individuals
may remain in treatment which, within the existing available capacity to meet
need, results in the time spent on the waiting list being extended. 
5.9 Adult mental health services continue to meet the HEAT target with 95% of
people being seen within 18 weeks at quarter 2.  Primary Care psychological
therapies service is not currently meeting the HEAT target with only 35% of
people being referred being seen within 18 weeks in quarter 2.  In adult mental
health there has been an increase in the number of people being referred due to
the availability of groups.  However, given the complexity of some of those
referred group, work is not always appropriate for their needs and they would
require to wait for 1:1 treatment.  The primary care psychological therapies
service also offers group sessions in an attempt to reduce waiting times for
people.  However, as with adult mental health, this is not always appropriate for
their needs and people require to wait for  appointments for 1:1 sessions to
become available.  Both adult mental health and primary care psychological
therapies have been working alongside Grampian colleagues to look at capacity
and demand and job planning has taken place for all staff working in these
services to maximise the numbers of appointments that can be
offered.  However, particularly in primary care, the demand for services
significantly outweighs the resource available to deliver this and the position
remains challenging. 
Staff Management - Red
5.10 NHS employed staff sickness absences have decreased from 7% at the end of
quarter 1, to 6.4% at the end of quarter 2, with Council employed staff sickness
decreasing to 7.3%.  These figures remain well above the 4% target for both. 
5.11 The most common causes of sickness absence continue to be predominantly
mental health or muscular-skeletal injuries and there is support available and
provided to staff for health and wellbeing matters and from occupational health
where appropriate. 
Staff Management - mitigation
5.12 A variety of approaches are being taken forward to reduce absences due to
stress at work.  NHSG is working hard to provide personnel with the tools for
resilience, and how to recognise stress.  The Council have mental health first
aiders for peer to peer support, and the NHS have peer supporters also.  NHSG
are currently promoting an “at your best with rest” to encourage staff to take
breaks, and materials have been shared with the Council as well.  To reduce
anxiety and stress regarding becoming ill from close contact with people, a
number of drop-in vaccination clinics were established to allow staff to get flu
and covid vaccinations, in the hope of preventing respiratory illnesses. 
5.13 Sickness and attendance is a standing item on our workforce, health and safety
partnership meeting agenda.  Recent discussions have focussed on how we
support those involved, so the policies are not viewed as punitive and are applied
consistently and regarded as a supportive measure.  There is regular
communication about people’s responsibilities, for individuals and for managers,
Page 18

Page 19

and the next health and safety newsletter will reiterate this.  Holiday periods still
see to be a period of high absence rates, which may mean that annual leave is
not being managed well, so this is an area being reviewed. 
Performance Framework – development
5.14 Once the strategic delivery plan revision is approved there will be a revision of
the performance framework and associated indicators reported to this committee
to ensure reporting on the specified outcomes is incorporated.  The proposals will
be discussed at a future Moray Integration Board development session prior to
presenting to this committee. 
6. SUMMARY OF IMPLICATIONS 
(a) Corporate Plan and 10 Year Plan (Local Outcomes Improvement Plan
(LOIP)) and Moray Integration Joint Board Strategic Plan “Moray
Partners in Care 2022-2032”
Performance management reporting is a legislative requirement under
section 42 of the Public Bodies (Joint Working) (Scotland) Act 2014.   
In addition to publishing an Annual Performance Report, the Moray
Integration Scheme requires that the MIJB will “monitor the performance of
the delivery of integrated services using the Strategic Plan on an ongoing
basis” (para 5.2.2 of the Moray Integration Scheme refers). 
(b) Policy and Legal
None directly associated with this report. 
(c) Financial implications
None directly associated with this report. 
(d) Risk Implications and Mitigation
There are no risk issues arising directly from this report. The long-term
impact of the COVID-19 on the Health and Social Care system are still
unknown and performance measurement will remain flexible to enable the
service to be prepared and react to any future developments. 
(e) Staffing Implications  
None directly associated with this report. 
(f) Property
None directly associated with this report. 
(g) Equalities/Socio Economic Impact
An Equality Impact Assessment is not required for the Performance
Framework because there will be no impact, as a result of the report, on
people with protected characteristics. 
(h) Climate Change and Biodiversity Impacts
No climate change or biodiversity implications have been determined for
this policy/activity. It should be noted that extreme weather events, such as
the recent storms, are expected to occur more frequently and with greater
ferocity in future years. In the longer-term there are likely to be issues with
the reduction in availability and increases in costs of fossil fuels that will
Page 19

Page 20

pose challenges for the delivery of care services to people living in rural
areas. 
(i) Directions
There are no directions arising from this report. 
(j) Consultations
Senior Management Team, Operational Management Team Health and
Social Care, Caroline O’Connor, Committee Services Officer, Moray
Council and their comments are incorporated in the report. 
7. CONCLUSION 
7.1 This report provides the Committee with an overview of the performance of
specified Local indicators and outlines actions to be undertaken to improve
performance in Section 4 and expanded on in Appendix 1.     
Authors of Report: Jeanette Netherwood, Corporate Programme Manager, HSCM   
Background Papers: Available on request 
Ref: 
Page 20

Page 21

Appendix 1   
PERFORMANCE REPORT
SUPPORTING CHARTS 
QUARTER 2
2024/25 
(1 JULY 2024 – 30 SEPTEMBER 2024)  
Item 5.
Page 21

Page 22

Table of Contents  
Health and Social Care Moray - 1 - 2022-23 Quarter 1 Performance Report
1. TABLE OF CONTENTS
1. Table of Contents ............................................................................................................................. 1
1. Performance Summary .................................................................................................................... 2
Barometer Overview ........................................................................................................................... 2
2. Delayed Discharge - RED .................................................................................................................. 3
DD-01: Number of delayed discharges (including code 9, Census snapshot, at end of quarter) ....... 3
DD-02: Number of Bed Days Occupied by Delayed Discharges per quarter (inc code 9) per 1000 18+
population ........................................................................................................................................... 4
3. Emergency Admissions - GREEN ...................................................................................................... 5
EA-01: Rate of emergency occupied bed days for over 65s per 1000 population .............................. 5
EA-02: Emergency Admissions rate per 1000 population for over 65s .............................................. 6
EA-03: Number of people over 65 years admitted as an emergency in the previous 12 months per
1000 population .................................................................................................................................. 7
4. Emergency Department – AMBER .................................................................................................. 8
AE-01: ED Attendance rates per 1,000 population (All Ages) ............................................................. 8
5. Hospital Re-admissions - RED .......................................................................................................... 9
HR-01: Percentage of Emergency Re-admissions to hospital within 7 days - Moray Patients ........... 9
HR-02: Percentage of Emergency Re-admissions to hospital within 28 days - Moray Patients ....... 10
6. Mental Health – RED ..................................................................................................................... 11
MH-01: Percentage of patients commencing Psychological Therapy Treatment within 18 weeks of
referral ............................................................................................................................................... 11
7. Staff Management - RED ............................................................................................................... 12
SM-01: NHS Sickness Absence % of Hours Lost ................................................................................ 12
SM-02: Council Sickness Absence (% of Calendar Days Lost) ............................................................ 12
Appendix 1: Key and Data Definitions .................................................................................................. 14
RAG Scoring Criteria .......................................................................................................................... 14
Peer Group Definition ....................................................................................................................... 14
Appendix 2: Strategic Priorities............................................................................................................. 15
Appendix 3: National Health and Wellbeing Outcomes ....................................................................... 17 
Page 22

Page 23

Performance Summary  
Health and Social Care Moray - 2 - 2022-23 Quarter 1 Performance Report
1. PERFORMANCE SUMMARY
BAROMETER OVERVIEW 
Moray currently has 11 local indicators. Of these 3 are Green, 1 is Amber and 7 are Red. 
Figure 1 - Performance Summary                                                                                                                         
Q2 2324 Q3 2324 Q4 2324 Q1 2425 Q2 2425 Target
Jul-Sep Oct-Dec Jan-Mar Apr-Jun Jul-Sep
AE Accident and Emergency
AE-01 A&E Attendance rate per 1000 population (All Ages) 23.3 21.8 22.6 21.5 22.6 21.9 A
DD Delayed Discharges
DD-01 Number of delayed discharges (including code 9) at census point 26 37 43 33 40 26 R
DD-02
Number of bed days occupied by delayed discharges (including code 9) at census
point 845 1162 1501 922 1115 850 R
EA Emergency Admissions
EA-01 Rate of emergency occupied bed days for over 65s per 1000 population 2628 2598 2509 2606 2603 2681 G‚
EA-02 Emergency admission rate per 1000 population for over 65s 189.9 188.7 179.9 178.7 177.7 187 G‚
EA-03
Number of people over 65 years admitted as an emergency in the previous 12
months per 1000 population 133.2 132.9 125.8 124.2 123.8 131 G‚
HR Hospital Readmissions
HR-01 % Emergency readmissions to hospital within 7 days of discharge 3.9% 3.3% 4.4% 3.6% 4.6% 3.7% R
HR-02 % Emergency readmissions to hospital within 28 days of discharge 8.6% 7.9% 8.3% 6.9% 8.9% 7.9% R
MH Mental Health
MH-01
% of patients commencing Psychological Therapy Treatment within 18 weeks of
referral 50% 52% 57% 70% 60% 90% R
SM Staff Management
SM-01 NHS Sickness Absence (% of hours lost) 5.7% 6.6% 5.7% 7.0% 6.4% 4% R
SM-02 Council Sickness Absence (% of days lost) 8.4% 9.6% 9.7% 7.5% 7.3% 4% R                                                             
Health and Social Care Moray Performance Report                                          
Code Barometer (Indicator) RAG
Page 23

Page 24

Delayed Discharge - RED  
Health and Social Care Moray - 3 - 2022-23 Quarter 1 Performance Report
2. DELAYED DISCHARGE - RED
Trend Analysis 
The number of delays at the September quarter 2 snapshot was up to 44, which is just below a high
of 46 in February 2024 and significantly above 26 this time last year.    
Bed days lost due to delayed discharges increased to 1,115 this quarter up from 922 in June 2024 and
well above 845 in the same period last year. This mirrors the increase in the more volatile snapshot
days (DD-01) measure and demonstrates that the trend is indeed increasing overall in Delayed
Discharges over the period. 
WDD-01: NUMBER OF DELAYED DISCHARGES (INCLUDING CODE 9, CENSUS
SNAPSHOT, AT END OF QUARTER)
Purpose 
Reliably achieving timely discharge from hospital is an important indicator of
quality and is a marker for person centred, effective, integrated, and harm
free care.
Strategic Priority  2: HOME FIRST Linked Indicator(s) DD-02
National Health & Wellbeing Outcomes 2, 3, 5, 7 
Figure 2 – Delayed Discharges 
Indicator Trend – Increasing
The number of delayed discharges at census date increased over the last quarter.
Source Public Health Scotland 
Page 24

Page 25

Delayed Discharge - RED  
Health and Social Care Moray - 4 - 2022-23 Quarter 1 Performance Report 
DD-02: NUMBER OF BED DAYS OCCUPIED BY DELAYED DISCHARGES PER QUARTER (INC
CODE 9) PER 1000 18+ POPULATION 
Purpose  This monitors the number of people delayed in hospital once medically fit
for discharge. Longer stays in hospital are associated with increased risk of
infection, low mood, and reduced motivation.
Strategic Priority  2: HOME FIRST Linked Indicator(s) DD-01
National Health & Wellbeing Outcomes 2, 3, 5, 7 
Figure 3 – Delayed Discharge Bed-days 
Indicator Trend – Increasing
The number of bed-days lost increased over the last quarter.
Source Public Health Scotland
Page 25

Page 26

Emergency Admissions - GREEN  
Health and Social Care Moray - 5 - 2022-23 Quarter 1 Performance Report
3. EMERGENCY ADMISSIONS - GREEN
Trend Analysis
The rate of emergency occupied bed days for over 65s had a small decrease to 2,603 this quarter and
is still down on the high of 2,749 in quarter 4 2022/23. 
The emergency admission rate per 1000 population for over 65s has increased through quarter 2
2023/24 to 189.9 and has now decreased four quarters in a row to 177.7. Similarly, the number of
people over 65 admitted to hospital in an emergency also had hit a high of 133.2 in quarter 2 2023/24
and has now decreased to 123.8 in quarter 2 2024/25. 
EA-01: RATE OF EMERGENCY OCCUPIED BED DAYS FOR OVER 65S PER 1000
POPULATION
Purpose  EA-01, EA-02, and EA-03 are all interconnected and provide a narrative
when viewed together of whether emergency admissions and bed days are
within tolerance and indicate where potential risks could arise.
Strategic Priority  1: BUILDING RESILIENCE  Linked Indicator(s) EA-02, EA-03
National Health & Wellbeing Outcomes 1, 2, 3, 5 
Figure 4 – Emergency Occupied Bed-days (Over 65s) 
Indicator Trend – Steady
Despite a month on month increase since December 2023 there has been a steady but small
increasing trend which is not significant but could indicate a reversal in the overall decreasing
trend since April 2023.
Source Health Intelligence  
Page 26

Page 27

Emergency Admissions - GREEN  
Health and Social Care Moray - 6 - 2022-23 Quarter 1 Performance Report
EA-02: EMERGENCY ADMISSIONS RATE PER 1000 POPULATION FOR OVER 65S
Purpose  EA-01, EA-02, and EA-03 are all interconnected and provide a story when
viewed together of whether emergency admissions and bed days are within
tolerance and indicate where potential risks could arise.
Strategic Priority  1: BUILDING RESILIENCE  Linked Indicator(s) EA-01, EA-03 
National Health & Wellbeing Outcomes  1, 2, 3, 5 
Figure 5 – Emergency Admissions (Over 65s) 
Indicator Trend – Decreasing
After a small decrease in this measure in December 2023 the last three quarters saw a continuing
decrease in this measure.
Source Health Intelligence  
Page 27

Page 28

Emergency Admissions - GREEN  
Health and Social Care Moray - 7 - 2022-23 Quarter 1 Performance Report
EA-03: NUMBER OF PEOPLE OVER 65 YEARS ADMITTED AS AN EMERGENCY IN THE
PREVIOUS 12 MONTHS PER 1000 POPULATION
Purpose  EA-01, EA-02, and EA-03 are all interconnected and provide a story when
viewed together of whether emergency admissions and bed days are
within tolerance and indicate where potential risks could arise.
Strategic Priority  1: BUILDING
RESILIENCE  Linked Indicator(s) EA-01, EA-02
National Health & Wellbeing Outcomes 1, 2, 3, 5 
Figure 6 – Number of Over 65 People Emergency Admissions 
Indicator Trend – Decreasing
After a small decrease in this measure in December 2023 the last three quarters saw a continuing
decrease in this measure.
Source Health Intelligence  
Page 28

Page 29

Emergency Department – AMBER  
Health and Social Care Moray - 8 - 2022-23 Quarter 1 Performance Report
4. EMERGENCY DEPARTMENT – AMBER
Trend Analysis 
There was an increase in the rate per 1,000 this quarter to 22.6. This is still below the number
presenting at the same period last year. This measure has been trending steadily around the target
since October 2023. 
AE-01: ED ATTENDANCE RATES PER 1,000 POPULATION (ALL AGES)
Purpose  A greater system-wide understanding of how people access emergency
care, and why certain choices are made, will allow local health systems to
develop intelligence about avoidable attendances at emergency
departments and target their responses. 
Strategic Priority  3: PARTNERS IN CARE Linked Indicator(s) HR-01, HR-02
National Health & Wellbeing Outcomes  1, 2, 3, 5 
Figure 7 – ED Attendance Rate 
Indicator Trend – Stable
During quarter 2 the attendance rate per 1,000 population has remained stable, sitting just
above the target level.
Source Health Intelligence  
Page 29

Page 30

Hospital Re-admissions - RED  
Health and Social Care Moray - 9 - 2022-23 Quarter 1 Performance Report
5. HOSPITAL RE-ADMISSIONS - RED
Trend Analysis 
The 7-day re-admissions have increased to above target to 4.6%, and the 28-day re-admissions have
decreased further to well above target at 8.9%. 
HR-01: PERCENTAGE OF EMERGENCY RE-ADMISSIONS TO HOSPITAL WITHIN 28 DAYS
- MORAY PATIENTS
Purpose  Re-admissions are often undesirable for patients and have also been shown
to be associated with the quality of care provided to patients at several
stages along the clinical pathway, including during initial hospital stays,
transitional care services and post-discharge support. (This measure lags by
a month due to the time required for a potential 28 day discharge to occur)
Strategic Priority  1: BUILDING
RESILIENCE  Linked Indicator(s) HR-02, AE-01
National Health & Wellbeing Outcome  1, 2, 3, 5 
Figure 8 – 7-dayEmergency Readmissions 
Indicator Trend – Stable
7-day Hospital Re-admissions have generally remained around the target of 3.7% for the last four
quarters, only having the odd month above target.
Source Health Intelligence  
Page 30

Page 31

Hospital Re-admissions - RED  
Health and Social Care Moray - 10 - 2022-23 Quarter 1 Performance Report
HR-02: PERCENTAGE OF EMERGENCY RE-ADMISSIONS TO HOSPITAL WITHIN 7 DAYS -
MORAY PATIENTS
Purpose  Re-admissions are often undesirable for patients and have also been shown
to be associated with the quality of care provided to patients at several
stages along the clinical pathway, including during initial hospital stays,
transitional care services and post-discharge support.
Strategic Priority  1: BUILDING RESILIENCE  Linked Indicator(s) HR-01, AE-01
National Health & Wellbeing Outcome  1, 2, 3, 5 
Figure 9 – 28-day Emergency Readmissions 
Indicator Trend – Increasing
28-day Hospital Re-admissions have increased significantly over the quarter.
Source Health Intelligence
Page 31

Page 32

Mental Health – RED  
Health and Social Care Moray - 11 - 2022-23 Quarter 1 Performance Report
6. MENTAL HEALTH – RED 
Trend Analysis 
After achieving a low 40% in January 2024 there has been little variation in performance through 2024
with now 60% of patients being referred within 18 weeks at the end of quarter 2 2024/25. 
MH-01: PERCENTAGE OF PATIENTS COMMENCING PSYCHOLOGICAL THERAPY
TREATMENT WITHIN 18 WEEKS OF REFERRAL
Purpose  Timely access to healthcare is a key measure of quality and that applies
equally in respect of access to mental health services.
Strategic Priority  3: PARTNERS IN CARE Linked Indicator(s) 
National Health & Wellbeing Outcome  1, 2, 3, 5 
Figure 10 – Psychological Therapy Treatment within 18 Weeks 
Indicator Trend – Steady but low
The short term monthly trend tends towards just under 60% in this measure in the last year.
Source Health Intelligence  
Page 32

Page 33

Staff Management - RED  
Health and Social Care Moray - 12 - 2022-23 Quarter 1 Performance Report
7. STAFF MANAGEMENT - RED
Trend Analysis 
Sickness absence for NHS employed staff has remained high at 6.4% at the end of quarter 2 2024/25.
Council employed staff sickness has decreased to 7.3% which is the lowest figure see in the last year. 
SM-01: NHS SICKNESS ABSENCE % OF HOURS LOST
Purpose  Attendance at work of all employees is essential in the interests of the
effective and efficient operation of services.
Strategic Priority  1: BUILDING
RESILIENCE  Linked Indicator(s) SM-02
National Health & Wellbeing Outcome  8 
Figure 11 – NHS Sickness Absence 
Indicator Trend – Steadily increasing
This indicator has been varying but steadily increasing since early 2022.
Source Health Intelligence 
SM-02: COUNCIL SICKNESS ABSENCE (% OF CALENDAR DAYS LOST)
Purpose  Attendance at work of all employees is essential in the interests of the
effective and efficient operation of services.
Strategic Priority  1: BUILDING
RESILIENCE  Linked Indicator(s) SM-01
National Health & Wellbeing Outcome  1, 2, 3, 5
Page 33

Page 34

Staff Management - RED  
Health and Social Care Moray - 13 - 2022-23 Quarter 1 Performance Report 
Figure 12 – Moray Council Sickness Absence 
Indicator Trend – Decreasing but high
This indicator been on a steady decrease but is still above target.
Source Council HR 
Page 34

Page 35

Staff Management - RED  
Health and Social Care Moray - 14 - 2022-23 Quarter 1 Performance Report
APPENDIX 1: KEY AND DATA DEFINITIONS
RAG SCORING CRITERIA
GREEN If Moray is performing better than target.
AMBER If Moray is performing worse than target but within specified tolerance.
RED If Moray is performing worse than target but outside of specified
tolerance. 
PEER GROUP DEFINITION
Moray is defined as being in Peer Group 2 in the Local Government Benchmarking Framework 
Family Group 1 Family Group 2 Family Group 3 Family Group 4
East Renfrewshire
East Dunbartonshire
Aberdeenshire
Edinburgh, City of
Perth & Kinross
Aberdeen City
Shetland Islands
Orkney Islands
Moray
Stirling
East Lothian
Angus
Scottish Borders
Highland
Argyll & Bute
Midlothian
Falkirk
Dumfries & Galloway
Fife
South Ayrshire
West Lothian
South Lanarkshire
Renfrewshire
Clackmannanshire
Eilean Siar
Dundee City
East Ayrshire
North Ayrshire
North Lanarkshire
Inverclyde
West Dunbartonshire
Glasgow City 
Page 35

Page 36

Staff Management - RED  
Health and Social Care Moray - 15 - 2022-23 Quarter 1 Performance Report
APPENDIX 2: STRATEGIC PRIORITIES 
Page 36

Page 37

Staff Management - RED  
Health and Social Care Moray - 16 - 2022-23 Quarter 1 Performance Report 
•EA-01: RATE OF EMERGENCY OCCUPIED BED DAYS FOR OVER
65S PER 1000 POPULATION
•EA-02: EMERGENCY ADMISSIONS RATE PER 1000 POPULATION
FOR OVER 65S
•EA-03: NUMBER OF PEOPLE OVER 65 YEARS ADMITTED AS AN
EMERGENCY IN THE PREVIOUS 12 MONTHS PER 1000
POPULATION
•HR-01: PERCENTAGE OF EMERGENCY RE-ADMISSIONS TO
HOSPITAL WITHIN 28 DAYS -MORAY PATIENTS
•HR-02: PERCENTAGE OF EMERGENCY RE-ADMISSIONS TO
HOSPITAL WITHIN 7 DAYS -MORAY PATIENTS
•SM-01: NHS SICKNESS ABSENCE % OF HOURS LOST
•SM-02: COUNCIL SICKNESS ABSENCE (% OF CALENDAR DAYS
LOST)
BUILDING
RESILIENCE
•DD-01: NUMBER OF DELAYED DISCHARGES (INCLUDING CODE 9,
CENSUS SNAPSHOT, AT END OF QUARTER)
•DD-02: NUMBER OF BED DAYS OCCUPIED BY DELAYED
DISCHARGES PER QUARTER (INC CODE 9) PER 1000 18+
POPULATION
•UN-01: NUMBER OF LONG-TERM HOME CARE HOURS UNMET
AT WEEKLY SNAPSHOT
•UN-02: NUMBER OF PEOPLE WITH LONG-TERM CARE HOURS
UNMET AT WEEKLY SNAPSHOT
HOME
FIRST
•OA-01: NUMBER OF REVIEWS OUTSTANDING AT END OF
QUARTER SNAPSHOT
•MH-01: PERCENTAGE OF PATIENTS COMMENCING
PSYCHOLOGICAL THERAPY TREATMENT WITHIN 18 WEEKS OF
REFERRAL
•AE-01: A&E ATTENDANCE RATES PER 1000 POPULATION (ALL
AGES)
PARTNERS
IN CARE
Page 37

Page 38

Staff Management - RED  
Health and Social Care Moray - 17 - 2022-23 Quarter 1 Performance Report
APPENDIX 3: NATIONAL HEALTH AND WELLBEING OUTCOMES
1 - PEOPLE ARE ABLE TO LOOK AFTER AND IMPROVE THEIR OWN HEALTH AND WELLBEING AND
LIVE IN GOOD HEALTH FOR LONGER. 
2 - PEOPLE, INCLUDING THOSE WITH DISABILITIES OR LONG-TERM CONDITIONS, OR WHO ARE
FRAIL; ARE ABLE TO LIVE, AS FAR AS REASONABLY PRACTICABLE, INDEPENDENTLY AT HOME,
OR IN A HOMELY SETTING IN THEIR COMMUNITY. 
3 - PEOPLE WHO USE HEALTH AND SOCIAL CARE SERVICES HAVE POSITIVE EXPERIENCES OF
THOSE SERVICES, AND HAVE THEIR DIGNITY RESPECTED. 
4 - HEALTH AND SOCIAL CARE SERVICES ARE CENTRED ON HELPING TO MAINTAIN OR IMPROVE
THE QUALITY OF LIFE OF PEOPLE WHO USE THOSE SERVICES. 
5 - HEALTH AND SOCIAL CARE SERVICES CONTRIBUTE TO REDUCING HEALTH INEQUALITIES. 
6 - PEOPLE WHO PROVIDE UNPAID CARE ARE SUPPORTED TO LOOK AFTER THEIR OWN HEALTH
AND WELLBEING, INCLUDING TO REDUCE ANY NEGATIVE IMPACT OF THEIR CARING ROLE ON
THEIR OWN HEALTH AND WELLBEING. 
7 - PEOPLE USING HEALTH AND SOCIAL CARE SERVICES ARE SAFE FROM HARM. 
8 - PEOPLE WHO WORK IN HEALTH AND SOCIAL CARE SERVICES FEEL ENGAGED WITH THE WORK
THEY DO AND ARE SUPPORTED TO CONTINUOUSLY IMPROVE THE INFORMATION, SUPPORT,
CARE, AND TREATMENT THEY PROVIDE. 
9 - RESOURCES ARE USED EFFECTIVELY AND EFFICIENTLY IN THE PROVISION OF HEALTH AND
SOCIAL CARE SERVICES.
Page 38

Page 39

REPORT TO: MORAY INTEGRATION JOINT BOARD AUDIT, PERFORMANCE
AND RISK COMMITTEE ON 30 JANUARY 2025 
SUBJECT: QUARTER 2 (JULY TO SEPTEMBER) PERFORMANCE REPORT
FOR CHILDREN AND FAMILIES AND JUSTICE SOCIAL WORK 
BY:      INTERIM CHIEF SOCIAL WORK OFFICER/HEAD OF SERVICE 
1. REASON FOR REPORT 
1.1 To inform the Committee on Children and Families and Justice Social Work
performance as at Quarter 2. 
2. RECOMMENDATIONS 
2.1 It is recommended Committee scrutinise, comment, and note: 
i) the performance of local indicators for Quarter 2 as presented in
the Performance Report at Appendix 1; and 
ii) the analysis of the local indicators as detailed in Appendix 1. 
3. BACKGROUND 
3.1 The purpose of this report is to inform the Committee of the quarterly
performance data which provides the analysis of the delivery of Children,
Families and Justice Social Work services. 
3.2 Appendix 1 identifies local indicators for the Moray Integration Joint Board
and the functions delegated by NHS Grampian and Moray Council of
Children, Families and Justice Social Work services to allow wider scrutiny by
the Committee. 
4. SUMMARY 
4.1 Work is underway to develop and agree the refresh of our key performance
indicators to enable us to record local data and measure this against the
national performance indicators. 
4.2 Appendix 1 provides a summary and the historical trends. 
• Child Protection activity
• Looked after Children 
• Justice and Youth Justice 
Item 6.
Page 39

Page 40

4.3 Statistics for Child Protection activity are provided against the academic
calendar which runs from August to July annually. This is because this data is
gathered and analysed by the Children Services Partnership and reported to
the Child Protection Committee (CPC) through the Child Protection Minimum
Data Set. Appendix 1 begins with Child Protection Q4 from page 1 to 10,
Financial Q2 data is from page 11 to 24. Any trends or anomalies in this data
are considered through the CPC Data subgroup and reported accordingly. 
4.4 Statistics for Looked After Children, Justice and Youth Justice are reflected
across the financial calendar which runs from April to March which is the
reporting calendar for this data. A summary of performance for each of the
reporting categories is provided below. 
4.5 Child Protection activity 
a. At the end of this Child Protection (CP) Quarter 4, 66 children were
registered on the Northeast Child Protection Register (NECPR) at a
rate of 3.7 per 1,000 of 0–17-year-olds within the population.  The
national and comparator data will be available at the end of the CP
year (after August 2025) which will enable us to benchmark our data at
that point. 
4.6 Looked After Children 
a. At the end of Financial (Fin) Quarter 2, the number of looked after
children (175) was 9.9 per 1,000 of 0–17-year-olds within the
population (total: 17,668). This is lower than the national average which
is 12.3 based on the most recent comparator statistics which date from
2022-23. This figure includes 9 Unaccompanied Asylum-Seeking
Children (UASC) and 6 children who are cared for on a part time basis
(Short Breaks). 
b. 90% (47/54) of children in foster care are cared for by Moray Council
foster carers. The Carer Recruitment Campaign continues to focus on
recruitment of foster carers and supported lodgings carers. Resultantly,
there has been an improved ability to have children and young people
cared for by Moray Council foster carers. Thus, reducing the need to
purchase external agency care. The Carer Recruitment Campaign is
continuing where it is anticipated that the use of in-house carers will
increase.         
c. The target for children living with kinship carers is adjusted annually to
the median of comparator authorities which was 25.1% for 2021/22
(this is a more than target based on the assumption Kinship care is
preferable, where it is safe and appropriate, to non-family care).
Currently 24% of looked after children in Moray are in approved
Kinship care with family members. Moray is currently 0.1% below this
median. 
d. 16% of our Looked After Children are cared for in residential care. The
target for this indicator (this is a less than target based on the
assumption foster care and kinship care is the preferred option, when it
is safe and appropriate, where possible) is adjusted annually to the
median of comparator authorities (17.5% 2022/23). This figure includes
Page 40

Page 41

6 young people who are cared for on a part time (Short Breaks) basis.
For illustrative purposes on performance, excluding those who have
Short Breaks, (children and young people who are in the care of their
families) the figure is 13% which is 5.5% lower than the National
comparator median. Overall, Moray is 1.5% lower than the National
comparator. 
e. 90% of brothers and sisters remain together in care settings. The
Maintaining Relationships Project is developing an approach and policy
to ensure that brothers and sisters are able to remain together as far as
possible and where this is their assessed needs.   
f. For UASC, Moray has not adopted the model used by other local
authorities of using residential homes. The Moray model comprises of
a combination of local authority housing and supported lodgings care
settings. As such, the uncertainty regarding the future numbers of
UASC should not have an impact on residential care capacity for
Moray. 
g. Statistically it is difficult to ascertain how other authorities record their
numbers as the level of detail is not readily available. While nationally
significant, the numbers of looked after children are comparatively
small which can provide significant percentage variance. An example
of this is that in Moray, all UASC and Short-term breaks are included
within our Looked After numbers. The service is aware not all
comparator authorities do this and is currently undertaking an exercise
to consider what our comparator authorities record. 
4.7 Justice and Youth Justice 
a. At the end of Financial (Fin) Quarter 2, there were 502 people open to
Justice Services of whom 36 are care experienced young people
(CEYP) (Youth Justice 12 and Justice 24). 
b. Overall, the number of CEYP in both Justice Social Work and Youth
Justice has been on a reducing trend from 13% at the end of March
2021 to 7.2% at the end of Fin Quarter 2.  Work continues to identify
and support care experienced young people within these services, to
offer early support where possible and reduce the risk of re-offending. 
c. The majority of individuals supported by Youth Justice and Justice
Social Work are male (87% Justice Social Work, 93% Youth Justice). 
Gender responsive support is offered to females taking account of
research and data indicating women in the justice system are more
likely to have experienced trauma and more likely to be a sole carer for
a child or family member. 
d. The Justice Social Work Service submitted 100% of reports to Court by
their due date.  This includes requests from our local Court and
nationally. 
5. KEY MATTERS RELEVANT TO RECOMMENDATION 
5.1 Detailed charts and indicator data is attached in Appendix 1.
Page 41

Page 42

6. SUMMARY OF IMPLICATIONS 
(a) Corporate Plan and 10 Year Plan (Local Outcomes
Improvement Plan (LOIP) and Moray Integration Joint
Board Strategic Plan “Partners in Care 2022 – 2032”
This report notes that a review of key performance indicators is currently
being developed in respect of the wider service functions that will align
with key priority areas across the Children’s Services partnership. 
(b) Policy and Legal
None arising as a direct result of this report. 
(c) Financial implications
None arising as a direct result of this report. 
(d) Risk Implications and Mitigation
None arising as a direct result of this report. 
(e) Staffing Implications
There are no proposed changes to the staffing or reporting relationships. 
(f) Property
None arising as a direct result of this report. 
(g) Equalities/Socio Economic Impact
None arising as a direct result of this report. 
(h) Climate Change and Biodiversity Impacts
None arising as a direct result of this report. 
(i) Directions
None arising as a direct result of this report. 
(j) Consultations
Children and Families and Justice Social Work Senior Management
Team, HSCM Operational Management Team (OMT). 
7. CONCLUSION 
7.1 This report provides the Committee with an overview of the performance
of specified local and National indicators. 
Author of Report: Jim Lyon, Interim Chief Social Work Officer/Head
of Service   
Background Papers:  Appendix 1
Page 42

Page 43

APPENDIX 1
1 | P a g e
CHILDRENS AND JUSTICE SOCIAL WORK - QUARTER 2 (JULY-SEPT 2024)
PERFORMANCE REPORT  
PLEASE NOTE THIS REPORT IS SPLIT INTO TWO SECTIONS. THE FOLLOWING SECTION USES
THE ACADEMIC CALENDAR (1 AUG – 31 JULY).  THE INFORMATION PRESENTED REPRESENTS
CP QUARTER 4 WHICH IS LATEST AVAILABLE DATA (MAY TO JULY 24).
At the end of the CP Quarter 4, 621 referrals were made into the Access Team for 478
children (as per graph 1).  
Graph 1: CP Quarter 4 - Referrals received by Access Team
The potential referral
routes are Social Work,
SCRA, Police, Courts,
Education, Health, 3rd
Sector, community,
family and young person. 
When a referral has been
received it can be
categorised as:
IRD – immediate child
protection concerns.
Enquiry – information
gathering to determine
next steps (if any).
Assessment – team will
conduct an initial assessment of needs.
Pie chart 1: Sources of referral 
224
182
215
174
149 155
0
50
100
150
200
250
May-24 Jun-24 Jul-24
Referrals
No of referrals in last month No of children
Item 6.
Page 43

Page 44

APPENDIX 1
2 | P a g e
In CP Quarter 4, 47.3% of the referrals were made by the Police (294), followed by Education
11.1% (69), Health and Social Work 16.6% (103), Family and or Anonymous 14.5% (90), and
10.5% coming from other professionals (65) (as per pie chart 1).  Where the number of
referrals are higher than the number of children, this can be attributed to the fact there can
be multiple sources of referrals about a child (e.g. Health, Education and Police).  This
potentially reflects consistent thresholds across the partnership. 
Initial Referral Discussions (IRDs) are a multi-agency decision making forum where
information is shared and considered between partnership representatives regarding
potential or actual risk of harm to children and young people.  We have been working with
our partner agencies to more robustly apply the criteria for IRDs, for example, where
families are supported by a Social Worker, then we hold a relevant meeting which involves
the family and young person, rather than professionals only.  This is a likely explanation for a
reduction in IRD numbers from CP Quarter 1 to CP Quarter 4. 
Graph 2: IRDs and
number of children
subject to an IRD
Graph 2 shows the
quarterly trend in IRDs
(between 1 Aug 2023 and
31 July 2024).  In CP
Quarter 4, 84 children
were involved in 47 IRDs. 
Of the 84 children, 21
had been subject to two
or more IRDs in the past
(25%).   For each quarter,
the number of children is greater than the number of IRDs as each IRD can consider multiple
children within a family.
Most referrals for IRDs in CP Quarter 4 came from the Police (46.4% [39]), closely followed
by Social Work (39.3% [33]). 
The IRD process determines the most suitable pathway for the child to ensure their safety
and any support required.  An IRD can consider initiating a Child Protection Planning
Meeting, which deliberates the child’s name being placed on the North-East Child Protection
Register (NECPR/CPR/Register). 
66 65 63
47
125
105
89 84
0
20
40
60
80
100
120
140
Q1 Q2 Q3 Q4
IRDs
No. of IRDs since 1 Aug No. of children since 1 Aug
Page 44

Page 45

APPENDIX 1
3 | P a g e
Pie chart 2: Main reasons for IRD 
As per chart above, throughout CP Quarter 4, physical assault remains a consistent reason for an
IRD being held (26, 55%), followed by sexual assault (24, 51%) domestic abuse (11, 23%) and
other reason (this includes cumulative neglect) (12, 25%). 
We are interested to consider over a period whether there is any impact for the reasons an IRD is
convened in relation to the delivery of the following training, Safe and Together and Graded Care
Profile, which is still being delivered.                        
Pie chart 3: Child protection concerns 
During CP Quarter 4, Domestic Abuse, Child affected by parent/carer mental ill health and
Parental Drug Use remain the main child protection concerns.  *Note there may be more than
one concern documented for each child*
Joint consideration with adult mental health services is required to see if there can be any
further support and developments in this area for reporting next quarter.
Page 45

Page 46

APPENDIX 1
4 | P a g e
Following the IRDs, 31 Child Protection Investigations were carried out, 7 Initial Child Protection
Planning Meetings were convened, and 26 Joint Investigative Interviews were requested. From
31 Child Protection Investigations (31 children) this resulted in only 7 Initial Child Protection
Planning Meetings and the families that did not progress to this had actions closed following
support from social work, or social work requested a commissioned service.  We have been
working with the child protection lead in education to support more robust child planning
processes and understanding of significant harm, e.g. a Senior Social Worker will attend future
Education Child Protection Coordinator Network meetings. 
Graph 3: Joint Investigative Interviewing 
Graph 3 shows the trend across the year 2023/24 for joint investigative interviews and Scottish
Child Investigative Interviews. 
16
26
9
12 12
9
13
7 7
13
10
413 22 8 11 9 6 13 7 7 13 9 4
3 4
1 1
3
0 0 0 0 0 1 0
0
2
4
6
8
10
12
14
16
18
0
5
10
15
20
25
30
Aug-23 Sep-23 Oct-23 Nov-23 Dec-23 Jan-24 Feb-24 Mar-24 Apr-24 May-24 Jun-24 Jul-24
JII and Scottish Child Interview Model
No. of children subject to a JII as decision of IRD No. of JII - SCIM
No. of JII - 5 - day No. of children who declined/or did not complete JII
No. of SCIM JIIs undertaken
Page 46

Page 47

APPENDIX 1
5 | P a g e
Graph 4 – JII & SCIM 
Graph 4 shows the activity of Joint Investigative Interviewing across CP Quarter 4, during which
27 children were recommended for Joint Investigative Interview (JII); 22 interviews were
completed and five children either declined or a different form of interview was carried out. 
The Social Work Data Group, chaired by a Service Manager, will track physical assaults across CP
Quarter 4, from IRD to JII considering intervention and support, safety planning and outcomes for
the children and young people. 
Graph 5: Initial Child Protection Planning Meetings 
Graph 5 shows the trend across the last three reporting years (2021-2024) for the number of
Initial and Pre-birth Child Protection Planning Meetings, and the number of children.  The
number of children subject to CPPMs is higher than the number of meetings held, due to some
meetings considering sibling groups.
13
10
4
13
9
4
0 1 02 2 1
11
8
3
13
9
4
0
2
4
6
8
10
12
14
May-24 Jun-24 Jul-24
JIIs using SCIM
No. of children subject to a JII as decision of IRD No. of JII - SCIM
No. of JII - 5 - day No. of children who declined/or did not complete JII
No. of SCIM JIIs undertaken How many JIIs used SCIM
Page 47

Page 48

APPENDIX 1
6 | P a g e
Page 48

Page 49

APPENDIX 1
7 | P a g e
The high numbers in CP Quarter 1 and CP Quarter 2 can be attributed to large numbers of
children within a small number of families.
At the end of CP Quarter 4, 7 Initial and Pre-birth Child Protection Planning Meetings were held
for 12 children of these, 9 children’s names were place on the register. 
Graph 6: Conversions from IRD to ICCPM
Graph 6 above shows the trend from 2020 through to 2024 and specifically CP Quarter 4, where
the conversion rate from ICPPM to Child Protection Registration was 75%.
13
20
28 30
8
18 16
25
8 10
22 18
25
39
19 14
75 78
100
76
100
77
94 91
75 73
45
78 78 83
94
75
0
20
40
60
80
100
120
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
Aug-
Oct
Nov-
Jan
Feb-
Apr
May-
Jul
Aug-
Oct
Nov-
Jan
Feb-
Apr
May-
Jul
Aug-
Oct
Nov-
Jan
Feb-
Apr
May-
Jul
Aug-
Oct
Nov-
Jan
Feb-
Apr
May-
Jul
2020/21 2021/22 2022/23 2023/24
Conversion Rates
% IRD to Initial and Pre-Birth CPPMs % Initial and Pre-Birth CPPMs to Registration
The
conversion
rate from
referral to IRD
is 7.6%
The
conversion
rate from IRD
to CPI is 65%
Conversion
rate from
CPI to ICPPM
is 38.7%
Page 49

Page 50

APPENDIX 1
8 | P a g e
During CP Quarter 4, there were 20 Review Child Protection Planning Meetings (RCPPM)
held for 44 children, where their circumstances were reviewed with their families, lead
professionals and advocates, to assess if the identified risks had been sufficiently reduced to
consider removing the child’s name from the register.
Graph 7: Child Protection Registration Trends
The trend is depicted across Graph 7 from 2021-2024 and shows in CP Quarter 4, that 13
children were de-registered and 9 new children were registered.  This meant at the end of
CP Quarter 4, the number of children who were on the Child Protection Register (CPR) had
reduced by 4 (from 70 to 66). 
5
10
15
21
6 8 9
14
25
34
16
9
31 35
44
50
42
37
27
32
50
79
70 66
9 6 6
15 14 13
20
9 9 5
25
13
0
10
20
30
40
50
60
70
80
90
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
Aug-Oct Nov-Jan Feb-Apr May-Jul Aug-Oct Nov-Jan Feb-Apr May-Jul Aug-Oct Nov-Jan Feb-Apr May-Jul
2021/22 2022/23 2023/24
Child Protection Register
Number of Registrations Number on Register Number of De-Registrations
Page 50

Page 51

APPENDIX 1
9 | P a g e
Pie chart 4: CP Quarter 4 registration reasons
Graph 8: Registration Categories 
Graph 8 above indicates the trend in registration categories across the reporting period
(from August 2023 to July 2024). There has been a significant reduction in new registrations
for the category Child affected by parental mental ill-health, with figures showing a
reduction from 8 new registrations in CP Quarter 3 (Feb 2024 – Apr 2024) to 0 in CP Quarter
4 (May 2024 – July 2024). 
New Reg Concern:
Domestic Abuse, 4,
23%
New Reg Parental
Alcohol Use, 3, 18%
New Reg Concern:
Parental Drug Use,
2, 12%
New Reg Concern:
Physical Abuse, 1,
6%
New Reg Concern:
Emotional Abuse, 4,
23%
New Reg Concern:
Other Concern, 3,
18%
CP Q4 REGISTRATION REASONS
3
1
8
6
8
1
7
11
4 43
5
3 33
16
1 23
1 1
5 5 4
1
8 9
2
4
2 3
0
2
4
6
8
10
12
14
16
18
Q1 Q2 Q3 Q4
Registration Categories
Services find it hard to engage Child Affected by Parent/Carer Mental Ill-Health
Child experiencing mental health problems Domestic Abuse
Parental Alcohol Use Parental Drug Use
Physical Abuse Emotional Abuse
Criminal Exploitation Neglect
Other Concern
Page 51

Page 52

APPENDIX 1
10 | P a g e
37% of IRDs was for the category sexual abuse which does not follow through to registration
reasons because the majority were not familial and were more due to experiences of sexual
abuse from a peer, where the family are supportive and assessed as able to protect the
young people.
45% of IRDs was for physical abuse which does not follow through to registration reasons as
most physical assaults were from parents struggling with their parenting role, and with
appropriate support to families, child protection plans were not necessary.
Graph 9: Family Groups
As shown in Graph 9, at the end of CP Quarter 4, there were 13 family groups consisting of
one child, 8 family groups with 2 children and 10 family groups of 3 or more children on the
register. 
Graph 10: Previous Registrations
25
8
0
5
10
15
20
25
30
Jul-24
Previous Registrations
No. of children with 1 previous registration No. of children with more than 2 previous registration
Page 52

Page 53

APPENDIX 1
11 | P a g e
At the end of the CP Quarter 4, there were 25 children on the register who had 1 previous
registration and 8 with 2 or more previous registrations.  No child or young person’s name
was placed back on the register within 24 months of de-registration (as indicated in Graph
10). 
Graph 11: Time on NECPR 
Graph 12: Age of children on the register
Graph 12 shows the trend for 2023/24 against CP Quarter 4 data where all age categories
have remained consistent with only a slight fluctuation throughout the Quarter. The number
of young people aged 16 years old has remained static since December 2023. 
42
15
10
1
0
34
21
5
6
0
22
32
6
5
1
<6 months
6 mths < 1 year
1 year < 18 mths
18 mths < 2 years
> 2 years
Time on the NECPR
Jul-24 Jun-24 May-24
Page 53

Page 54

APPENDIX 1
12 | P a g e
Page 54

Page 55

APPENDIX 1
13 | P a g e
THE FOLLOWING SECTIONS REPORT AGAINST THE FINANCIAL QUARTER (JULY-SEPT 2024) 
Graph 13: Number of children looked after away from home and at home 
Graph 13 identifies that at the end of Financial (Fin) Quarter 2, there were 175 children who
were looked after by Moray. This figure has remained relatively stable throughout the
reporting period. 
Pie chart 5: Care setting categories
At the end of Fin Quarter 2, 47% of children were in family settings at home or in kinship
care with 53% in other settings such as foster care or residential homes. This is a positive
indication that many looked after children can remain within their network of family and
friends. Alongside this, 90% of siblings remain together in a care setting.  Siblings who are
not together are because of family circumstances or assessed needs.  There is planned work
via the Maintaining Relationships Project to sustain and increase the percentage of siblings
remaining together in care settings in line with the Children’s Service Plan.   
Foster care (54) and kinship care (44) are the highest categories followed by children looked
after at home (38).  Our residential houses (10) remain at approximately the same level as
the Out of Area residential category (11).  The carer recruitment campaign has seen new
176 178
185 187
183 180 182
172 172
177 179
175 173 175
160
165
170
175
180
185
190
Aug-23 Sep-23 Oct-23 Nov-23 Dec-23 Jan-24 Feb-24 Mar-24 Apr-24 May-24 Jun-24 Jul-24 Aug-24 Sep-24
No. of Looked After Children
Page 55

Page 56

APPENDIX 1
14 | P a g e
foster carers approved to support young people remaining in Moray in family care settings. 
A significant majority of young people are in family-based care rather than residential care.   
At the end of Fin Quarter 2, 12% of our looked after children were cared for on a full-time
basis in residential accommodation.  If short breaks are included the figure increases to
14.8%. The indicator (to be kept within or lower) is adjusted annually to the median of
comparator authorities (17.5% 2022/23).  As such, Moray is below the median indicator
when considering full-time care on its own and including short breaks.  This highlights in
Moray there is a priority to support young people in family-based care, where possible, to
provide a positive model of family life.
One young person was placed in secure care from November 2023 on remand at the
direction of the Court.  This aligns with the recent changes in Justice legislation for children
under 18 where they are remanded into the care of local authorities rather than Young
Offenders Institutions.
Moray hosts a group of 10 young people who are Unaccompanied Asylum-Seeking children
and young people via the National Transfer Scheme.  These children and young people are
allocated to the Throughcare and Aftercare Team by the Home Office and are counted as
looked after children to ensure they receive full support.  Initially, these young people are in
Supported Lodgings care settings or Supported Accommodation.  The team continues to
successfully support them to move into their own independent housing once they have been
granted asylum.  The approach adopted by Moray is seen by COSLA as a model of good
practice as it offers flexibility and has an ability to respond to the differing needs of young
people. 
Graph 14: Moray foster care households 
At end of Fin Quarter 2 there were 54 children living in foster care, with 48 (89%) children
living with foster carers employed by Moray Council and six (11%) living with independent
28
36 37 37 36 35
27 25 25
28
31
0
5
10
15
20
25
30
35
40
36 Q2 Q3 Q4 Q1 Q2
Q1
2023/24 2023/24 2023/24 2024/25 2024/25
Moray Foster Care
Number of Moray Council Fostering households
Number of Moray Council Foster Carers with “Active” placements at the end of the period
Page 56

Page 57

APPENDIX 1
15 | P a g e
foster carers.  Those young people living with independent foster carers are all in long-term
care with Permanence Orders. 
Not all fostering households have children living in their care.  At the end of Fin Quarter 2
this comprises four in total.  This is a small number due to family circumstances or matching
considerations of their registration approval where foster carers are inactive for a short
period of time. 
Graph 15: Children who live in foster care   
Graph 16 identifies the number of children cared for by Moray foster carers, 48 which is an
increase from Fin Quarter 2 in 2023 which was 43.  However, this includes some quarterly
fluctuations where the pattern is relatively stable.  The number of approved Moray foster
carer households available for children has seen a small decrease.  Although the carer
recruitment campaign is resulting in new fostering households, this is balanced by other
foster households ceasing or changing the type of fostering they provide. The challenge in
recruiting and retaining foster carers is both a local and national issue.  The carer
recruitment campaign is significant in recruiting foster carers where this is also accompanied
by work in relation to retention.  This is focused on the support provided to foster carers
including supervision, training and finances.   
Foster carers are graded by the level of skills learned and developed, ranging from Level 1 to
Level 4 being the highest. 
44 43 45 47 45 48 46 45 47 46 51 51 50 48
11 11 7 7 7 7 7 6 6 6
6 6 6 6
0
10
20
30
40
50
60
Children in Foster Care
Local Authority Foster Care Foster with other orgs paid for by Local Authority
Page 57

Page 58

APPENDIX 1
16 | P a g e
Graph 16: Kinship carers 
Kinship care is split into two groups: pre-approved kinship homes awaiting presentation at
the Kinship Panel for approval and kinship households already approved at Panel.         
Graph 17: Residential care 
Residential care is divided into those in residential care within Moray and those out with
Moray.  Children cared for within Moray live in the authority's own children’s houses, Cala
and Action for Children’s two houses in Buckie and Elgin.  The figure for this category is 10.
30
32
29
31 32
30 29 30 31
29 29 29 29 28
30 29
26 26
32
34
32 31 30
32 33 32 32 31
10
14 14
16
11
7
9 10
12
9
7 8 8 8
0
5
10
15
20
25
30
35
40
Aug-23 Sep-23 Oct-23 Nov-23 Dec-23 Jan-24 Feb-24 Mar-24 Apr-24 May-24 Jun-24 Jul-24 Aug-24 Sep-24
Kinship Care Settings
No. of households providing Kinship Placements No. of Children in Approved Placements
No. of Children in Pre-Approved Placements
13
14 14 14
13
12
13
12 12
13 13
12
11
10
11 11 11 11 11 11 11
10 10
11 11
9 9
11
0
2
4
6
8
10
12
14
16
Aug-23 Sep-23 Oct-23 Nov-23 Dec-23 Jan-24 Feb-24 Mar-24 Apr-24 May-24 Jun-24 Jul-24 Aug-24 Sep-24
Residential Care
Placement: Residential in Moray Placement: Out of Area
Page 58

Page 59

APPENDIX 1
17 | P a g e
Out of area care tends to be specialist residential houses or residential schools.  There has
been a consistent focus on providing this care in Moray where possible, so children remain
close to their families and support network.  The figure for this category is 11. 
There is work in place to reduce the number of young people in Out of Area care. These are
expensive care options but also do not support young people in maintaining their various
links in Moray including health, education, family and friends. 
Graph 18: Through care after care data
As illustrated in Graph 18, from 30 September 2024, there were 75 young people receiving
care from the Through Care After Care (TCAC) Team including nine receiving continuing care
support. 
The team is divided into three sections: 
• Through Care: Young people receiving support to plan and prepare for
independence.
• After Care: Young people who have left care but are receiving continuing support. 
• Continuing Care: Young people who choose to remain where they live beyond their
18th birthday until they are 21 although it can be in place from 16.  These young
people cease to be formally looked after by Moray but are legally entitled to
continue living where they are. This provides stability in a familiar and nurturing
setting. There is a focus on continuing care to ensure young people in different care
settings are all provided the opportunity to remain where they are living potentially
up until the age of 21.  This is a key responsibility for the organisation and partners as
corporate parents.   
The team is responsible for supported unaccompanied asylum-seeking children and young
people via the National Transfer Scheme.  This is an increasing workload for the team, which
is dependent, in part, on the numbers of young people arriving in Kent, making future
forecasting a significant challenge.       
35
33
28
8
9
9
37
40
38
0 5 10 15 20 25 30 35 40 45
Jul-24
Aug-24
Sep-24
Through Care, After Care and Continuing Care
Through Care Continuing Care Aftercare
Page 59

Page 60

APPENDIX 1
18 | P a g e
Justice and Youth Justice. 
Graph 19: Care experienced young people open to Justice Services
Nationally, care experienced young people (CEYP) are overrepresented in the Scottish Justice
Systems.  At the end of Fin Quarter 2, 7.2% (36 of 502) were CEYP (up to age 26) within the
Justice System (Youth Justice 12, Justice Social Work 24) depicted in graph 19, showing an
increase from 4.5% at end of Fin Quarter 1.  An error in reporting resulted in the figures for
the Youth Justice team not being included in this data and the Fin Quarter 1 figure should
have been 6.4%.  This figure has consistently remained below 12% throughout 2023/24. 
Work continues to identify and offer early intervention and support where possible to
identify CEYP and offer early help where possible to reduce the amount of time in which
they are involved with justice services. The aim is to reduce the risk of re-offending to
prevent CEYP requiring these services in the future. 
435 424 421 424 403 415 422 450 440 449 443 466 472
44 46 46 41
38 39 45
38 40 36 37
32 30
9.18 8.93 8.99
9.46 9.52 9.47
8.35
7.58
7.29
6.39
7.23
6.82
7.17
0
1
2
3
4
5
6
7
8
9
10
0
100
200
300
400
500
600
Sep-23 Oct-23 Nov-23 Dec-23 Jan-24 Feb-24 Mar-24 Apr-24 May-24 Jun-24 Jul-24 Aug-24 Sep-24
Care Experienced People in the Justice System
Open to Justice Team No. open to Youth Justice %  CEYP open to both MYJ and JS
Page 60

Page 61

APPENDIX 1
19 | P a g e
Graph 20: Ages of young people in Youth Justice
The average age of a young person receiving Youth Justice services is 15 years old which is
predominately males accounting for 93% of young people supported by the service. 
Pie chart 6: Gender of young people in Youth Justice 
Pie chart 7: Justice Report Types
At the end of Fin Quarter 2, 13% of individuals in Justice Social Work were women, which has
remained relatively static over the past year.  It is recognised women in the justice process
0 0 1 1 1 1 1 1 0 0 0 0 1 1
33 29 31 30
24 22 22
27
21 22 21 21 21 21
14
15
14 15
15
14 15
14
13
16
13 15 10 7
2
0 0 0
1
1 1
3
4
2
2 1
0
1
49
44 46 46
41
38 39
45
38 40
36 37
32 30
0
10
20
30
40
50
60
Aug-23 Sep-23 Oct-23 Nov-23 Dec-23 Jan-24 Feb-24 Mar-24 Apr-24 May-24 Jun-24 Jul-24 Aug-24 Sep-24
Youth Justice Age Bands
Age Band: 5-10 Age Band: 11-15 Age Band: 16-17 Age Band: 18+ No. open to Youth Justice
87%
13%
JSW Gender
Male Female
28
2
Youth Justice Gender
Male Female
Page 61

Page 62

APPENDIX 1
20 | P a g e
are more likely to have experienced trauma and are also more likely to be a sole carer for a
child or family member.  In line with The Promise, Justice Social Work is committed to
keeping women in their local communities where it is safe to do so and provide robust
alternatives to custodial sentences.  Currently the Justice team offers a gender responsive
service which includes a weekly women’s group and a woman only unpaid work
group.  Support is offered in partnership with other services to promote opportunities for
individuals to engage with community resources which will be available beyond their time
within the justice service.   
Graph 21: Justice social work reports (JSWR)  
Justice social work reports (JSWR) remain a priority to reduce any delays in sentencing and
for Fin Quarter 2 the target of 100% on time has been met.  Whilst reports are prepared at
the request of any Court for an individual living in Moray, most reports are submitted to
Elgin Sheriff Court.  There has been small reduction in sentencing reports completed in Fin
Quarter 2 due to a reduction in requests received from Courts.  The trend of small increases
or decreases is expected each month or quarter. 
Pie chart 8: Justice Report Types
Page 62

Page 63

APPENDIX 1
21 | P a g e
In addition to a standard JSWR report the Court may request additional assessments such as
a Drug Treatment and Testing Order (DTTO) assessment and a Restriction of Liberty Order
(ROLO) assessment as shown in pie chart 8.  The imposition of a ROLO or DTTO can be a
direct alternative to custody so effective assessments for these Orders can offer a robust
community-based disposal. 
Graph 22: Structured deferred sentences (SDS)
An
SDS is a flexible intervention providing structured social work support for an individual after
conviction but prior to sentencing.  Successful completion of an SDS reduces the need for a
statutory Court Order, in turn reducing the overall length of time an individual is open to the
service.  There has been a reduction in SDSs in Fin Quarter 2 which will have been impacted
slightly by the reduction in overall reports requested.  There was also a slight increase in
report requests for a ROLO which indicates a more serious offence or pattern of offending
for which a recommendation for an SDS would unlikely be suitable.
Graph 23: Bail supervision
3, 3%
39, 36%
62, 58%
3, 3%
Type of Report
JSWR DTTO Assessment
JSWR ROLO Assessment
JSWR Standard
JSWR  Unpaid
Work/DTTO/ROLO
Assessment
15
5
7
1
MALE Q1 FEMALE Q1 MALE Q2 FEMALE Q2
Structured Deferred Sentences
Number imposed
Page 63

Page 64

APPENDIX 1
22 | P a g e
Bail supervision is an alternative to remand and the priority for this in Moray is women,
young people, those with caring or parental responsibilities and those with issues relating to
mental health or addictions.  There is no significant change in either numbers of assessments
requested, or bail supervision orders imposed in Fin Quarter 2.  Less than 25% of
assessments result in bail supervision being imposed.  National data is not available to
compare, however, working groups have confirmed this variation is not isolated to Moray. 
Currently the prison population is significantly high, and bail supervision is one area of work
which is hoped will assist in reducing these numbers whilst offering more positive outcomes
for individuals within their local communities. 
Graph 24: CPO with supervision requirement 
Fin Quarter 2 has seen an increase in the imposition of Community Payback Orders (CPO),
despite a small reduction in reports being submitted.  Most individuals made subject to a
CPO are seen on the day of sentencing, for those where this has not been possible, an
appointment with their allocated worker is made within seven days of an Order being
imposed.  Missed targets this quarter all relate to individuals not attending appointments.
54
5
58
413 1 11 2
0
10
20
30
40
50
60
70
Male Q1 Female Q1 Male Q2 Female Q2
Bail Supervision
Bail Sup. Assessments Bail Sup imposed
Page 64

Page 65

APPENDIX 1
23 | P a g e
Diversion from Prosecution
Diversion from prosecution allows someone accused of offences to be dealt with outside of
the formal justice system.  The Justice Social Work team undertakes all assessments of
suitability; however, the Youth Justice team will complete any interventions or support for
young people aged 16 and 17.  The referral rate varies which is a result of the process of
cases being marked by the Procurator Fiscal.  There can occasionally be delays in the
commencement of these cases where additional agreement is required from the Procurator
Fiscal, e.g. an extended period for completion.
Successful completion of a diversion from prosecution means an individual will not have a
conviction for the alleged offence which may impact their current or future employment or
education alongside other significant areas of their life. 
Graph 25: Diversion from prosecution: Female
Page 65

Page 66

APPENDIX 1
24 | P a g e
Graph 26: Diversion from prosecution: Male       
Policy Team. 
Support and protection of children and young people procedure rollout
As noted in the previous report, the Policy Team within Children and Families and Justice
Social Work, in collaboration with partner agencies, lead on the revision of the Moray
Multiagency Child Protection Procedure now known as Support and Protection of Children
and Young People.  This procedure has been successfully rolled out via a comprehensive
implementation plan targeting several practitioners across the partnership, as illustrated on
the figure below. 
Page 66

Page 67

APPENDIX 1
25 | P a g e
The briefing paper outlined the
key changes to the procedure,
whilst the interactive briefing
sessions offered a walkthrough
of various processes through
Alfie’s story, a video series
(developed by the charity Not in
Our Community) exploring the
realities of criminal exploitation
from the perspective of a young
person.   
Commissioning. 
Pie chart 9: Contract categories 
Pie chart 9 identifies the
seven main category areas
of the contracts held
within the Children &
Families and Justice
commissioning team.
The family support
category covers a range of
services which deliver
prevention and early
intervention to avoid
family breakdown and
possible out of area care.
This category covers three
family support services
(Families Together, Functional Family Therapy and Youth Point Services) and the Independent
Advocacy contract.
For the services delivered to children with a disability, the short breaks service contract commenced
this quarter with the incumbent provider following a commissioning process including tender
advertisement, ensuring there was continuity and no gap in service provision.  
There is a new service for children with a disability – group activities, which was tendered, evaluated
and awarded to Action for Children, this contract was due to commence 1 November 2024.  
A local framework was developed to formalise the contractual agreements for 3 young people to reside
locally and be supported with their physical disabilities in a residential home.
There are currently 8 young people residing in residential care in Moray provided by Action for
Children.  This contract expires 31 March 2025 and during Fin Quarter 2 the commissioning team
gathered the views of the young people, developed and finalised the specification with the tender
being advertised as part of the commissioning process.
The three family support services report a combined total of 116 children, young people and their
families on their current workload, broken down in the illustration below:
Page 67

Page 68

APPENDIX 1
26 | P a g e
All three family support services have
capacity for referrals, which has been
communicated across social work
teams.
The three family supports services are
reporting and providing evidence on
achieving 21 contractual outcomes with a further 11 in progress:
Families Together have reported 88 children and young
people (from 57 families) being positively impacted
following families being supported with financial gains
and debt management as part of the Children First
service. 
The illustration above details service outcomes.
The independent relational advocacy service has been
contracted for a full year and the referral rate is
beginning to stabilise.  There are two lots for this contract, lot 1 for all the young people and lot 2 for
their parents, carers and siblings. They currently have 143 children, young people, parents or carers
and siblings on their caseload, including 36 looked after children and 39 subject of child protection.  In
Fin Quarter 2, independent advocates supported children and families in 46 meetings.
Graph 27: Meetings attended by independent advocacy service 
Pie chart 10: LAC and CP on current caseload
A direct award contract for self-regulation and behaviour management was finalised (previously this
was for foster care) which commences on 1 November 2024, will include adoptive, kinship and
supported lodgings care. 
For the first year, the Scottish Government expanded the Scottish Living Wage uplift to cover the
providers of children’s services which the commissioning team continues to implement.
The commissioning team attended 4 training sessions – modern slavery, trauma informed, and 2 x child
criminal exploitation.  These courses have helped to contribute to the language of the specifications
and contract monitoring going forward.
On 13 September 2024 there was a commissioning development day held with adult services
commissioning and service managers in relation to the contract monitoring process. 
LAC & CP on Current Caseload
LAC Under CP
Page 68

Page 69

REPORT TO: MORAY INTEGRATION JOINT BOARD AUDIT, PERFORMANCE
AND RISK COMMITTEE ON 30 JANUARY 2025 
SUBJECT: INTERNAL AUDIT SECTION - UPDATE REPORT 
BY:  CHIEF INTERNAL AUDITOR 
1. REASON FOR REPORT 
1.1 This report provides Committee with an update on the work of the Internal
Audit Section. 
2. RECOMMENDATION 
2.1 Committee is asked to consider the contents of this report, seek
clarification on any points noted and otherwise note the report. 
3.  BACKGROUND 
3.1 Public Sector Internal Audit Standards (PSIAS) require the Chief Internal
Auditor to prepare and present reports to committee on internal audit’s activity
relative to the audit plan and on any other relevant matters. 
4.  KEY MATTERS RELEVANT TO RECOMMENDATION 
Audit Plan 2025/26
4.1 The Internal Audit Plan details a list of projects the Internal Audit Service will
review to provide management and members with an independent opinion
that the MIJB’s risk management, governance and internal control processes
are operating effectively. Internal audits' approach to annual audit planning is
risk-based, with all areas that may be subject to audit review contained within
an ‘audit universe.’ The audit universe is reviewed and updated on an ongoing
basis to include all significant activities and systems. In addition, consultation
has also been undertaken with the Chair of the Audit, Performance and Risk
Committee and the with senior officers to highlight any projects for review. In
accordance with agreed reposting arrangements, the Audit Plan 2025/26 will
be submitted to Moray Council’s Audit and Scrutiny Committee on 12
February 2025 and thereafter to the next Audit, Performance and Risk
Committee on 27 March 2025. 
Item 7.
Page 69

Page 70

NHS Grampian Internal Audit Reports
4.2 As the Chief Internal Auditor of the Moray Integration Joint Board (MIJB), my
role includes providing assurances of internal controls of systems and
practices required by the MIJB to deliver services, irrespective of whether they
use Council or NHS systems. I can provide members of the MIJB Audit,
Performance and Risk Committee with audit reports of reviews undertaken
regarding operating practices that use Moray Council owned systems due to
my role as the Council’s Auditor. However, over the last few years, I have
been trying to obtain copies of internal audit reports of NHS Grampian
systems of interest to the MIJB that I can share with members.  My intention is
for members of the Audit, Performance and Risk Committee to receive similar
assurances, irrespective of whether they relate to Council or NHS Grampian
systems.   
4.3 I have been in discussion with the senior management of NHS Grampian and
their Internal Audit Provider to allow me to receive copies of their internal audit
reports for reporting to the Audit, Performance and Risk Committee. This has
required significant discussions and a requirement to sign an agreement to
several reporting and assurance conditions. Despite certain reservations that
have involved obtaining additional clarification from senior management of
NHS Grampian, I have now signed this agreement. I will therefore be
reporting internal audit reports from the NHS Grampian Internal Audit Provider
of interest to the MIJB to future Audit, Performance and Risk Committees.       
Follow Up Reviews 
4.4 Internal audit reports are regularly presented to members, detailing not only
findings but also management's responses to the recommendations with
agreed dates of implementation. Internal Audit will also undertake follow up
reviews to evidence the effective implementation of these recommendations.
Please see detailed the following completed follow up review: 
Purchasing Cards 
4.5 An audit was previously undertaken of the systems and procedures for the
management, use and control of purchasing cards. A purchasing card is
similar to a personal credit card issued by the Council's Bank used by the
Moray Council to enable purchases of supplies and services to be made
quickly and efficiently. Cards are available to officers on approval of their
budget manager. It provides flexibility and a cost effective alternative to the
Council's standard requisition ordering process. Purchasing cards are
managed by a payment card software application administered by the Bank.
The audit scope for this review was to assess the key controls and systems in
place in the management and use of purchasing cards. The Follow Up Report
to review the implementation of the agreed recommendations is given in
Appendix 1. 
5.  SUMMARY OF IMPLICATIONS 
(a) Corporate Plan and 10 Year Plan (Local Outcomes Improvement Plan
(LOIP)) and Moray Integration Joint Board Strategic Plan “Moray
Partners in Care 2022-2032” 
Internal audit work supports good governance and assists in securing
appropriate  systems of internal control. 
Page 70

Page 71

(b)  Policy and Legal
The internal audit service is provided in terms of paragraph 7:1 of the
Local Authority Accounts (Scotland) Regulations 2014, and there is a
requirement to provide a service in accordance with published Public
Sector Internal Audit Standards. 
(c) Financial Implications 
No implications directly arising from this report. 
(d)  Risk Implications
Audit reports highlight risk implications and contain recommendations for
management to address as a means of mitigating.   
(e) Staffing Implications
No implications directly arising from this report 
(f)   Property
No implications. 
(g)  Equalities/ Socio Economic Impacts 
No implications. 
(h) Climate Change and Biodiversity Impacts
None directly arising from this report. 
(i) Directions 
None arising directly from this report. 
(j)   Consultations
There have been no direct consultations during the preparation of this       
report.     
6. CONCLUSION 
6.1 This report provides committee with an update on internal audit work
progressed in the latest review period. 
Author of Report:  Dafydd Lewis, Chief Internal Auditor
Background Papers: Internal Audit Files
Ref:    mijb/ap&rc/
Page 71

Page 72

Page 72

Page 73

APPENDIX 1
Moray Council
Internal Audit Section 
DEPARTMENT: Economy, Environment & Finance
SUBJECT:  Purchasing Cards
REPORT REF:  24'019
Follow Up Audit Review 
Risk Ratings for Recommendations
High Key controls absent, not being
operated as designed or could be
improved. Urgent attention required.
Medium Less critically important controls
absent, not being operated as
designed or could be improved.
Low Lower level controls absent, not
being operated as designed or
could be improved.
No. Audit Recommendation Priority Accepted
(Yes/ No)
Date of
Completion
Status / Explanation
Key Control: Procedures are in place and frequently reviewed to govern use of the corporate purchasing cards system. 
5.01 In accordance with agreed
timescales, Purchasing Card
Procedures should be reviewed
annually and made available on
the Interchange for user
reference.   
Medium Yes 30/04/2024 Implemented. The Purchasing Card
Procedures Manual has been reviewed and
presented on the Interchange for user
reference in June 2024. Going forward, the
procedures will be reviewed on an annual
basis.
Key Control: A robust purchase card application process is in place accompanied by a controlled process for issue of cards on
acceptance of terms of operation. 
Item 7.
Page 73

Page 74

Moray Council
Internal Audit Section 
2
Risk Ratings for Recommendations
High Key controls absent, not being
operated as designed or could be
improved. Urgent attention required.
Medium Less critically important controls
absent, not being operated as
designed or could be improved.
Low Lower level controls absent, not
being operated as designed or
could be improved.
No. Audit Recommendation Priority Accepted
(Yes/ No)
Date of
Completion
Status / Explanation
5.02 All officers must sign and return a
Payment Card Terms of Use Form
to the Payments Service before
being issued a purchasing card
and access granted to the
Payment Card System. 
Medium Yes 30/04/2024 Implemented. Audit testing has confirmed
administrative processes have been
strengthened to ensure purchasing cards are
not despatched to new users until the signed
terms of use acceptance form has been
received by the Payments Service. A tidy up
exercise has also been undertaken to ensure
conditions of use acceptances are on file for all
existing cardholders.     
Key Control: Usage of purchase cards is controlled by imposed limits, is for purchases not suitable for standard procurement routes, is
appropriately detailed for authorisation and scrutiny purposes and supports the continued appropriateness of card retention.   
5.03 Consideration should be given to
aligning all purchasing
Low Yes 31/07/2024 Implemented. An exercise has been
confirmed as undertaken to align cardholder
Page 74

Page 75

Moray Council
Internal Audit Section 
3
Risk Ratings for Recommendations
High Key controls absent, not being
operated as designed or could be
improved. Urgent attention required.
Medium Less critically important controls
absent, not being operated as
designed or could be improved.
Low Lower level controls absent, not
being operated as designed or
could be improved.
No. Audit Recommendation Priority Accepted
(Yes/ No)
Date of
Completion
Status / Explanation
cardholders who hold a standard
single transaction limit to the
current transaction limit of £1,000
to ensure consistency. 
transaction limits. There are now 15 officers
holding single transaction limits over the
standard £1,000 threshold, all due to assessed
operational requirements, compared to the
151 officers with higher than standard limits in
the original audit review. 
5.04 The Bank should be informed to
correct the errors found in
Cardholders spending limits noted
during the audit review.   
Low Yes 31/07/2024 Implemented. As referred to in 5.03 above, an
exercise has been undertaken to review all
cardholder spending limits and errors
previously identified have been advised to the
Bank, resulting in amended limits being
applied. 
Key Control: Purchase Card transactions are appropriately authorised by the relevant budget manager. 
5.05 Full transaction listings of
purchase card transactions should
be issued for information to all
budget managers every quarter, in
Medium Yes 30/04/2024 Implemented. A catch-up exercise has been
undertaken to issue full transaction listings for
2023/24 and the reports have been evidenced
as issued for Quarter 1 of 2024/25. No delay is
expected for issue of reports to budget
Page 75

Page 76

Moray Council
Internal Audit Section 
4
Risk Ratings for Recommendations
High Key controls absent, not being
operated as designed or could be
improved. Urgent attention required.
Medium Less critically important controls
absent, not being operated as
designed or could be improved.
Low Lower level controls absent, not
being operated as designed or
could be improved.
No. Audit Recommendation Priority Accepted
(Yes/ No)
Date of
Completion
Status / Explanation
compliance with purchasing card
procedures. 
managers going forwards due to streamlining
of the recording process with the newly
implemented electronic transaction logging. 
5.06 Agreed timescales should be
established where payment card
transactions not authorised by a
budget manager are referred to
the appropriate Head of Service to
resolve and if required, authorise
the outstanding expenditure. 
Medium Yes 30/04/2024 Implemented. Significant improvement has
been seen in the prompt authorisation of
transactions since the initial audit. Payments
Section has introduced new processes since
the end of June 2024. Transactions must now
be approved before they can be downloaded
for processing, giving greater impetus for
budget managers to act timeously and for
unapproved transactions to be identified and
pursued by Payments. Unapproved
Page 76

Page 77

Moray Council
Internal Audit Section 
5
Risk Ratings for Recommendations
High Key controls absent, not being
operated as designed or could be
improved. Urgent attention required.
Medium Less critically important controls
absent, not being operated as
designed or could be improved.
Low Lower level controls absent, not
being operated as designed or
could be improved.
No. Audit Recommendation Priority Accepted
(Yes/ No)
Date of
Completion
Status / Explanation
transactions at the time of the follow-up audit
relate to only recent transactions with no
recurring control issue identified. 
Key Control: VAT on purchasing card transactions is accurately documented and accounted for with full recovery of applicable input
tax elements. 
5.07 A reminder should be issued to all
services to remind officers of VAT
accounting requirements for
payment card transactions.   
High Yes 30/04/2024 Implemented. A reminder of the VAT
accounting requirements has been added to
the annual terms of use confirmation issued to
all cardholders in March 2024. In addition, the
Purchasing Card guidelines have been
augmented in June 2024 to include more
clarity and detail on VAT requirements. The
new electronic receipt logging process
implemented in June 2024 has also provided a
Page 77

Page 78

Moray Council
Internal Audit Section 
6
Risk Ratings for Recommendations
High Key controls absent, not being
operated as designed or could be
improved. Urgent attention required.
Medium Less critically important controls
absent, not being operated as
designed or could be improved.
Low Lower level controls absent, not
being operated as designed or
could be improved.
No. Audit Recommendation Priority Accepted
(Yes/ No)
Date of
Completion
Status / Explanation
further opportunity to communicate VAT
accounting requirements to all cardholders.
Process enhancements implemented can be
seen to have strengthened the VAT
accounting system. 
5.08 Consideration should be given for
the Payments Service to
undertake further monitoring of
payment card transactions with
the aim of maximising VAT
recovery where documentary
evidence is required of valid VAT
receipts / invoices from services. 
High Yes 31/07/2024 Implemented. Since the audit took place,
mandatory electronic VAT receipt submission
within the Purchasing Card system has been
introduced. This has assisted the monitoring
process with electronic receipt submissions
being validated by the Payments service and
any documentation unsuitable for VAT reclaim
being immediately identified and further
queried as a routine process to ensure
maximisation of VAT recovery is achieved. 
Page 78

Page 79

Moray Council
Internal Audit Section 
7
Risk Ratings for Recommendations
High Key controls absent, not being
operated as designed or could be
improved. Urgent attention required.
Medium Less critically important controls
absent, not being operated as
designed or could be improved.
Low Lower level controls absent, not
being operated as designed or
could be improved.
No. Audit Recommendation Priority Accepted
(Yes/ No)
Date of
Completion
Status / Explanation 
5.09 The agreed procedure for the
Payments Service of issuing
routine escalation reports on
purchase card transactions with
potential VAT implications to
Heads of Service should be
reinstated to promote VAT
recovery arrangements. 
High Yes 30/04/2024 Implemented. A catch-up exercise has been
undertaken to issue VAT information reports to
Heads of Service (HOS) for 2023/24 and for
Quarter 1 of 2024/25. No delay is expected for
issue of reports to HOS going forwards due to
streamlining of the recording process with the
newly implemented electronic transaction
logging. With the requirement for receipt
production on transaction logging, the need to
escalate to HOS is expected to decrease and
will be reviewed in time to assess if still
appropriate and impactful. 
Page 79

Page 80

Moray Council
Internal Audit Section 
8
Risk Ratings for Recommendations
High Key controls absent, not being
operated as designed or could be
improved. Urgent attention required.
Medium Less critically important controls
absent, not being operated as
designed or could be improved.
Low Lower level controls absent, not
being operated as designed or
could be improved.
No. Audit Recommendation Priority Accepted
(Yes/ No)
Date of
Completion
Status / Explanation 
5.10 Investigation of an electronic
document imaging facility to
record VAT receipts / invoices on
transaction logging should
continue with the aim of
implementing more effective VAT
accounting and documentation
retention arrangements. 
Medium Yes 31/07/2024 Implemented. Mandatory electronic receipt
logging has been introduced as part of the
Purchasing Card system in June 2024. This is
already showing benefits in effective VAT
accounting and document retention
arrangements and is deemed to be a welcome
improvement to Purchasing Card
administration. 
Key Control: Processes are in place to ensure purchase card permissions are fully withdrawn from cardholders on termination of
employment. 
5.11 In accordance with operating
arrangements, the payment card
system should be updated
Medium Yes 30/04/2024 Implemented. A tidy up exercise has been
completed regarding budget managers within
the payment card system. Monthly processing
Page 80

Page 81

Moray Council
Internal Audit Section 
9
Risk Ratings for Recommendations
High Key controls absent, not being
operated as designed or could be
improved. Urgent attention required.
Medium Less critically important controls
absent, not being operated as
designed or could be improved.
Low Lower level controls absent, not
being operated as designed or
could be improved.
No. Audit Recommendation Priority Accepted
(Yes/ No)
Date of
Completion
Status / Explanation
promptly to reflect current budget
management responsibilities
when notified of officers leaving
the employment of the Council.   
of leavers is being undertaken. 
5.12 Greater care should be taken on
inputting payroll reference
numbers when setting up
employees on the purchasing card
system. 
Low Yes 30/04/2024 Implemented. A reminder on input accuracy
has been issued to relevant officers and follow-
up testing has confirmed accurate set up of
new users on the purchasing card system. 
Page 81

Page 82

Page 82

Page 83

REPORT TO: MORAY INTEGRATION JOINT BOARD AUDIT, PERFORMANCE
AND RISK COMMITTEE ON 30 JANUARY 2025 
SUBJECT: INTERNAL AUDIT SECTION COMPLETED PROJECTS REPORT 
BY:  CHIEF INTERNAL AUDITOR 
1. REASON FOR REPORT 
1.1 To provide an update on audit work completed since the last meeting of the
Committee. 
2. RECOMMENDATION 
2.1 Committee is asked to consider and note this audit update. 
3.  BACKGROUND   
3.1 Public Sector Internal Audit Standards (PSIAS) require the Chief Internal
Auditor to prepare and present reports to the committee on internal audit’s
activity relative to the audit plan and any other relevant matters. 
4. KEY MATTERS RELEVANT TO RECOMMENDATION 
4.1      In line with the approved internal audit plan, the following reviews were 
completed:   
Governance arrangements to prevent Fraud and Corruption  
4.2 A review was undertaken of the Council and the Moray Integration Joint
Board’s (MIJB) governance arrangements to prevent fraud and corruption.
The Chartered Institute of Public Finance and Accountancy Code of Practice
on Managing the Risk of Fraud and Corruption was used as the template for
developing the audit programme of testing. This review was part of a joint
audit exercise with the internal audit providers of NHS Grampian and
Aberdeenshire / Aberdeen City Councils. As the Integration Joint Boards
deliver services through officers and systems of the Council and NHS
Grampian, this approach has allowed for a more overarching and complete
review to be undertaken. In addition, the opportunity for sharing knowledge
and expertise has benefited all the internal audit providers in the delivery of
this audit review. 
Item 8.
Page 83

Page 84

4.3 The responsibility for preventing and detecting fraud and corruption rests with
management. However, the Internal Audit Service has a role in supporting
these arrangements by assessing the adequacy of these controls and leading
investigations of irregularities concerning finances, property, services, or
policies of the Council. Regarding allegations of fraud or corruption within
NHS Grampian, it is the responsibility of the NHS Counter Fraud Authority to
investigate. Findings noted where further improvements are needed in
developing agreed procedures between the Internal Audit Service and the
NHS Counter Fraud Authority, as officers of both NHS Grampian and the
Council use systems of both organisations to deliver services. Improvements
were also noted where further development is needed within the Council to
enable more effective reporting of irregularities. The audit report for this
project is given in Appendix 1. 
Moray Growth Deal 
4.4 The Moray Growth Deal is a transformational programme of over £100 million,
designed to drive economic growth across Moray over a ten year period. The
Moray Growth Deal brings together the Scottish and UK Governments, Moray
Council, partners from across the public and third sector, and businesses to
work collaboratively to deliver the Deal’s vision for the area. Moray Council is
the accountable body for the Growth Deal and has the responsibility to hold to
account partner organisations in the delivery of the overall programme. 
4.5 This audit reviewed the governance and administrative procedures for
managing the Moray Growth Deal. A check was also made for a sample of
grant claims for projects currently in delivery, including the verification of
expenditure claimed by a partner organisation to supporting evidence. Overall,
from the audit undertaken and within the scope of this review, effective
arrangements are in place for the governance and administration of the Moray
Growth Deal. The audit report for this project is given in Appendix 2. 
Out of Area Placements
4.6 A review of the systems and procedures of people receiving adult care
services who are Out of Area (OOA) was undertaken. The term “Out of Area”
relates to an individual's care and support being delivered in a local authority
area that is different from the local authority with the statutory responsibility for
providing that care and support. In Health & Social Care Moray Adult
Services, OOA placements are managed within Learning Disability, Mental
Health, Physical and Sensory Disabilities and Older Persons Services.
Overall, a “limited opinion” has been detailed as the assurance level for this
review; audit testing noted significant concerns regarding the progress
undertaken in determining ordinary residence status for OOA placements and
the contractual arrangements with care providers. The audit report for this
project is given in Appendix 3. 
5.  SUMMARY OF IMPLICATIONS 
(a) Corporate Plan and 10 Year Plan (Local Outcomes Improvement Plan
(LOIP)) and Moray Integration Joint Board Strategic Plan “Moray
Partners in Care 2022-2032” 
Internal audit work supports good governance and assists in securing
appropriate  systems of internal control. 
Page 84

Page 85

(b)  Policy and Legal
The internal audit service is provided in terms of paragraph 7:1 of the
Local Authority Accounts (Scotland) Regulations 2014, and there is a
requirement to provide a service in accordance with published Public
Sector Internal Audit Standards. 
(c) Financial Implications 
No implications directly arising from this report. 
(d)  Risk Implications and Mitigation
Audit reports highlight risk implications and contain recommendations for
management to address as a means of mitigating. 
(e) Staffing Implications
No implications directly arising from this report 
(f)   Property
No implications. 
(g)  Equalities/ Socio Economic Impacts 
No implications. 
(h) Climate Change and Biodiversity Impacts
None directly arising from this report. 
(i) Directions 
None arising directly from this report. 
(j) Consultations
There have been no direct consultations during the preparation of this
report. 
6. CONCLUSION 
6.1 This report provides Committee with a summary of findings arising from
audit project completed during the review period. 
Author of Report:  Dafydd Lewis, Chief Internal Auditor 
Background Papers: Internal Audit Files
Ref:     
Page 85

Page 86

Page 86

Page 87

Appendix 1 
1
Final Internal Audit Report 
Governance arrangements to
prevent Fraud and Corruption  
October 2024   
Distribution: Interim Chief Officer Health & Social Care Moray (MIJB) 
Head of Governance Strategy & Performance 
Chief Financial Officer 
Head of Human Resources ICT & Organisational Development 
Audit & Risk Manager                             
The Internal Audit Section provides Management with an opinion on the internal control
environment and also categories risk ratings for recommendations as high, medium or low
(detailed explanation provided in Appendix1). The audit recommendations for this review have
been classified as follows 
Assurance Level
Risk Ratings for
Recommendations 
Priority 1  0    
Substantial Priority 2  3     
Priority 3  2     
Confidentiality and Disclosure Clause 
This report (“Report”) was prepared by the Internal Audit Section of Moray Council. The matters raised in this Report are
only those which came to our attention during our internal audit work. Whilst every care has been taken to ensure that the
information provided in this Report is as accurate as possible, the Moray Council Internal Audit Section has only been able
to base findings on the information and documentation provided and consequently, no complete guarantee can be given
that this Report is necessarily a comprehensive statement of all the weaknesses that exist, or of all the improvements that
may be required. 
This Report was prepared solely for the use and benefit of the Moray Council, Moray Integration Joint Board or the
Grampian Valuation Joint Board. Moray Council's Internal Audit Section accepts no responsibility and disclaims all liability
to any third party who purports to use or rely for any reason whatsoever on the Report, its contents, conclusions, any
extract, reinterpretation, amendment and/or modification. Accordingly, any reliance placed on the Report, its contents,
conclusions, any extract, reinterpretation, amendment and/or modification by any third party is entirely at their own risk. 
Please refer to the Statement of Responsibility in Appendix 2 of this report for further information about
responsibilities, limitations and confidentiality.  
Item 8.
Page 87

Page 88

Appendix 1 
2
Contents 
Page 
Governance arrangements to prevent Fraud and
Corruption   
1. Introduction & Scope 3
2. Key Issues  3-4 
Detailed Report 
3. Findings/Recommendations 5-10
4. Management Response 5-10 
Appendices 
1. Audit Terms of Reference and Definitions 
2. Statement of Responsibility 
Page 88

Page 89

Appendix 1 
3
1. Introduction and Audit Scope 
The Annual Audit Plan for 2024/25 provides for a review of the Council and the
Moray Integration Joint Board (MIJB) governance arrangements to prevent
fraud and corruption.  The primary responsibility for preventing and detecting
fraud and corruption rests with management who should ensure adequate
systems of internal control, segregation of duties and proper authorisation
procedures. However, the Internal Audit Section does have a role in supporting
these arrangements by assessing the adequacy of these controls, and in
accordance with the Council’s Financial Regulations for the Audit and Risk
Manager to investigate in consultation with the Depute Chief Executive
Education, Communities & Organisational Development irregularities
concerning finances, property, services or policies of the Council. The audit also
reviewed the arrangements for the investigation, preventing and detecting fraud
and corruption within the MIJB. The Council’s Audit and Risk Manager is also
the Chief Internal Auditor of the MIJB. 
The Cipfa Code of Practice on Managing the Risk of Fraud and Corruption was
used as the template for developing an audit programme for this review. The
audit was also undertaken as part of a joint working arrangement with the
internal audit service providers of NHS Grampian, Aberdeen City and
Aberdeenshire Councils. This has allowed the sharing of knowledge and
agreement in the audit testing to ensure consistency and a more overarching
review of the Integration Joint Boards (IJBs) counter fraud and corruption
arrangements within the Grampian area. The IJBs deliver services through
officers and systems of the Council and NHS Grampian. Officers from the
Council and NHS Grampian will have access to the systems of both
organisations. It is hoped these joint working arrangements with the internal
audit service providers within Grampian will continue as it provides the
opportunity for a more cross-organisational review of the IJB’s risk
management, control and governance processes irrespective of NHS Grampian
or Council systems are used in the delivery of services.   
The audit was carried out in accordance with Public Sector Internal Audit
Standards (PSIAS). 
2. Key Issues 
•   The Public Sector Internal Audit Standards require the Chief Internal
Auditor to provide an opinion on the overall adequacy and
effectiveness of the MIJB risk management, control, and governance
processes. MIJB delegated services are delivered by Council and
NHS Grampian employed officers with access to systems of both
organisations. Responsibility for investigating fraud within the Council
Page 89

Page 90

Appendix 1 
4
lies with the Audit and Risk Manager, but for NHS Grampian, it is the
responsibility of the NHS Counter Fraud Authority. It is appreciated
that the occurrence of fraud is rare, but consideration should be given
to developing a protocol between the Audit and Risk Manager in
consultation with the Chief Internal Auditor of Aberdeenshire/
Aberdeen City Councils and the NHS Counter Fraud Authority. This
should assist in providing greater clarity and co-ordination of
responsibility in the notification, investigation and reporting of alleged
frauds within the MIJB, irrespective of whether the Council or NHS
Grampian employs the officer delivering the delegated service.   
•   The CIPFA Code of Practice on Managing the Risk of Fraud and
Corruption requires that an “organisation should make arrangements
for appropriate resources to support the counter fraud strategy”. This
includes the need to detect fraud through data and intelligence
analysis. The staff resources of the Internal Audit Section are limited,
but consideration should be given to including a project within the
Annual Internal Audit Plan to review Council systems and practices
where fraud or irregularities have occurred in other organisations. The
testing undertaken should make use of data evaluation software in the
analysis of information, and a review of fraud cases and other
irregularities reported within the media, Audit Scotland Technical
Bulletins and participation in the Scottish Local Authority Investigator's
Group. 
Page 90

Page 91

Appendix 1 
5
Governance arrangements to prevent Fraud and Corruption - 2024/25 
Ref Risk Ratings for
Recommendations
Audit Finding Audit Recommendation
1. Medium A review of the Council’s policy framework which
supports a counter fraud strategy, noted a range of
policies to inform officers in their conduct and
responsibilities as employees. These policies also
protect officers from false allegations of fraud or
corruption. However, the audit review noted that the
Code of Conduct for Employees and the Policy on
Outside Employment had not been reviewed for a
number of years. It is appreciated that both the Code
of Conduct for Employees and the Policy on Outside
Employment detail best practices and are still relevant;
however, both documents should be reviewed and if
required updated. 
The Code of Conduct for Employees and the
Policy on Outside Employment should be
reviewed and if required updated. In addition,
future dates of review should thereafter be
agreed. 
.
Management Response
Responsible Officer Accepted
(Yes/ No)
Timescale for
Implementation
(Date Required) 
Agreed Management Action/Management Comment 
Organisational Development
Manager
Yes 31/03/2026 The employment policy framework is reviewed annually,
resulting in agreement on the priorities for policy review
according to a range of factors, such as changed legislation.
The Code of Conduct for Employees and the Policy on Outside
Employment remain appropriate and have not been identified
as a priority for updating; however, they will be included in the
annual plan for policies review for 2025/26. 
Page 91

Page 92

Appendix 1 
6
Ref Risk Ratings for
Recommendations
Audit Finding Audit Recommendation
2.   Low  It was noted that the Council’s website included details
on reporting allegations of potential fraud to the
Internal Audit Section. However, reference is made
specifically to the reporting of Housing and Social
Security Benefits fraud, as this used to be the most
significant area of allegations received for
investigation. A review of the wording used within the
Council’s internet site should be undertaken, as a
need to report a potential fraud may relate to any
service area of the Council. In addition, research noted
online fraud reporting function within other Local
Authorities as an additional method for an individual to
report an allegation of fraud. 
Current wording used within the Council’s
internet site for reporting an allegation of fraud
should be reviewed and updated. In addition,
consideration should be given to the
development of an online reporting function as
an additional method for an individual to raise a
concern of fraud to the Council.   
Management Response
Responsible Officer Accepted
(Yes/ No)
Timescale for
Implementation
(Date Required) 
Agreed Management Action/Management Comment
Audit and Risk Manager Yes 31/03/2025 The information on the Council’s website for reporting fraud will
be reviewed and updated. The timescale for implementation of
this recommendation has been recorded as 31 March 2025 due
to the need for updating web pages and the development of an
online fraud reporting function which requires the support of the
ICT Section.   
Page 92

Page 93

Appendix 1 
7
Ref Risk Ratings for
Recommendations
Audit Finding Audit Recommendation
3.   Low  As part of the audit planning of projects to be included
within the Annual Audit Plan for 2023/24, a joint
working arrangement was agreed with the internal
audit service providers of NHS Grampian, Aberdeen
City and Aberdeenshire Councils to review the
Integration Joint Boards governance arrangements to
prevent fraud and corruption. This has allowed for a
more overarching review to be undertaken. As part of
the joint audit working arrangement, this has also
enabled the sharing of knowledge and information.
The Financial Regulations of the MIJB were updated
last year to include revised wording for reporting and
investigating a suspected irregularity. However, it was
noted that our neighbouring Councils had developed a
“Counter Fraud Process” detailing best practices to
follow in assessing a referral and investigating fraud.
The occurrence of fraud is rare and the nature of each
investigation can vary in nature, but consideration
should be given to reviewing and if required, adapting
this procedural document within Moray. 
Consideration should be given for the Internal
Audit Section to develop a “Counter Fraud
Process” procedure. 
Management Response
Responsible Officer Accepted
(Yes/ No)
Timescale for
Implementation
(Date Required) 
Agreed Management Action/Management Comment
Audit and Risk Manager Yes 30/11/2024 The “Counter Fraud Process” already developed by a
neighbouring Council will be used to prepare a similar
procedural guidance document for the Moray Council. 
Page 93

Page 94

Appendix 1 
8
Ref Risk Ratings for
Recommendations
Audit Finding Audit Recommendation
4.   Medium  The Council’s Audit and Risk Manager is the
appointed Chief Internal Auditor for delivering an
internal audit service to the MIJB. MIJB delegated
services are undertaken by Council and NHS
Grampian officers and systems. Officers of both the
Council and NHS Grampian are required to use the
systems of each organisation to deliver services. The
Audit and Risk Manager is responsible for
investigating suspected irregularities within the
Council, and the NHS Counter Fraud Authority
investigates NHS Grampian's allegations of fraud.
However, an issue may occur if an officer employed by
the Council commits fraud involving an NHS system
and vice-versa as to whether the allegation within the
MIJB should be investigated by the Council’s Audit
and Risk Manager or the NHS Counter Fraud
Authority. The nature of the fraud may have a cross
organisational implication regarding access to
information and the individual officer's terms and
conditions of employment from each organisation. 
Consideration should be given to the Audit and
Risk Manager, in consultation with the Chief
Internal Auditor of Aberdeenshire and
Aberdeen City Councils, to discuss and if
possible, agree on a protocol for the
notification, investigation and reporting of
alleged fraud within the Grampian IJBs with the
NHS Counter Fraud Authority. This may require
a “letter of understanding” detailing agreed
arrangements for the fraud investigation. 
Management Response
Responsible Officer Accepted
(Yes/ No)
Timescale for
Implementation
(Date Required) 
Agreed Management Action/Management Comment
Audit and Risk Manager Yes 30/11/2024 Contact will be made with the Chief Internal Auditor of
Aberdeenshire and Aberdeen City Councils to discuss arranging a
meeting with the NHS Counter Fraud Authority to agree a protocol
for investigating fraud within the Grampian IJBs. 
Page 94

Page 95

Appendix 1 
9
Ref Risk Ratings for
Recommendations
Audit Finding Audit Recommendation
5.   Medium  At a Special Meeting of the Moray Council on 28
February 2024, it was decided to reduce the Internal
Audit Section staffing budget by replacing the
Corporate Investigations Officer’s post with a 0.5 full-
time equivalent. The remaining budget was used to
appoint an Assistant Auditor, but this proved
unsuccessful, with no suitable applicants. The CIPFA
Code of Practice on Managing the Risk of Fraud and
Corruption requires that an “organisation should make
arrangements for appropriate resources to support the
counter fraud strategy” of the Council. This includes
the need to detect fraud through data and intelligence
analysis. The limited staff resources of the Internal
Audit Section are appreciated, but consideration
should be given to including a project within the
Annual Internal Audit Plan to review systems and
practices where fraud or irregularities have been
reported within other organisations. 
During this review, it was noted that a financial fraud
was reported in the media of an officer in another
Local Authority embezzling over £1 million in council
tax refunds. Further to consultation with the Council’s
Taxation Manager, additional controls have been
introduced to current operating arrangements. 
The Audit and Risk Manager should consider
including a project within the Annual Internal
Audit Plan to review Councill systems and
practices where fraud has occurred within other
organisations. Identification of the scope and
testing to be undertaken will be determined
from a review of fraud cases reported in the
media, Audit Scotland Technical Bulletins and
participation in the Scottish Local Authority
Investigator's Group. The use of information
data evaluation software should also be used in
the analysis of information and databases. 
Page 95

Page 96

Appendix 1 
10 
Management Response
Responsible Officer Accepted
(Yes/ No)
Timescale for
Implementation
(Date Required) 
Agreed Management Action/Management Comment
Audit and Risk Manager Yes 28/02/2025 A project will be included to support the Council’s and MIJB
counter fraud and corruption arrangements in the Annual
Internal Audit Plan. The scope of the audit and testing
undertaken will be determined from frauds reported within other
organisations. The use of IDEA® Data Analysis software will be
further developed in the analysis of information used for audit
testing. 
Page 96

Page 97

Appendix 1 
11 
Appendix 1 
AUDIT TERMS OF REFERENCE AND DEFINITIONS 
1. Audit Objectives 
1.1 The overall audit objective is to provide an objective independent opinion on
the adequacy and effectiveness of controls / processes.  
1.2 The audit will for each controls / process being considered: 
• Walkthrough the processes to consider the key controls; 
• Conduct sample testing of the identified key controls, and 
•  Report on these accordingly 
1.3 All audit reviews are carried out in accordance with Public Sector Internal
Audit Standards (PSIAS). 
2. Definitions for Auditing Opinions and Findings 
2.1 In order to assist management in using our reports: 
The Internal Auditor will categorise audit assurance opinion according to
their overall assessment of the risk management system, effectiveness of the
controls in place and the level of compliance with these controls and the
action being taken to remedy significant findings or weaknesses. 
Assurance
Level
System and Testing Conclusion
Full The controls tested are being consistently applied
Substantial There is evidence that the level of noncompliance with some of
the controls may put some of the system objectives at risk.
Limited The level of non compliance puts the system objectives at risk.
None Significant non-compliance with basic controls leaves the system
open to error or abuse. 
2.2 Risk ratings for each recommendation is based on the following criteria: 
High Fundamental control weaknesses that require immediate
attention by management to action and mitigate significant
exposure to risk
Medium Less critically important controls absent, not being operated as
designed or could be improved
Low Lower level controls absent, not being operated as designed or
could be improved.
Page 97

Page 98

Appendix 1 
12 
Appendix 2 
STATEMENT OF RESPONSIBILITY   
The responsibility for designing and maintaining a sound system of internal control
to prevent and detect fraud and other irregularities rests with management, with
internal audit providing a service to management to support them to achieve this
objective. The Internal Audit Section will assess the adequacy and effectiveness of
the system of internal control arrangements implemented by management and
perform sample testing on those controls in the period under review with a view to
providing an opinion on the extent to which risks in this area are managed. 
The Internal Audit Section will undertake testing with the objective of detecting
significant control weaknesses. However, the audit approach alone should not be
relied upon to identify all strengths and weaknesses in internal controls nor to find
any fraud or irregularity. Even sound systems of internal control can only provide
reasonable and not absolute assurance and may not be proof against collusive
fraud. 
The matters raised in this report are only those that came to our attention during
the course of the audit review and are not necessarily a comprehensive statement
of all the weaknesses that exist or all improvements that might be made.
Recommendations for improvements should be assessed by management for their
full impact before they are implemented. The performance of the audit review
undertaken should not be taken as a substitute for management’s responsibilities
for the application of sound management practices. 
This report is confidential and must not be disclosed to any third party or
reproduced in whole or in part without the written consent of the Moray Council’s
Audit and Risk Manager. 
Page 98

Page 99

Appendix 2 
1
Final Internal Audit Report 
Moray Growth Deal 
October 2024   
Distribution: Acting Head of Economic Growth & Development 
Moray Growth Deal Programme Manager 
Chief Financial Officer 
Senior Communications Officer 
The Internal Audit Section provides Management with an opinion on the internal control
environment and also categories risk ratings for recommendations as high, medium or low
(detailed explanation provided in Appendix1). The audit recommendations for this review have
been classified as follows 
Assurance Level
Risk Ratings for
Recommendations 
Priority 1  2    
Substantial Priority 2  3     
Priority 3  2       
Confidentiality and Disclosure Clause 
This report (“Report”) was prepared by the Internal Audit Section of Moray Council. The matters raised in this Report are
only those which came to our attention during our internal audit work. Whilst every care has been taken to ensure that the
information provided in this Report is as accurate as possible, the Moray Council Internal Audit Section has only been able
to base findings on the information and documentation provided and consequently, no complete guarantee can be given
that this Report is necessarily a comprehensive statement of all the weaknesses that exist, or of all the improvements that
may be required. 
This Report was prepared solely for the use and benefit of the Moray Council, Moray Integration Joint Board or the
Grampian Valuation Joint Board. Moray Council's Internal Audit Section accepts no responsibility and disclaims all liability
to any third party who purports to use or rely for any reason whatsoever on the Report, its contents, conclusions, any
extract, reinterpretation, amendment and/or modification. Accordingly, any reliance placed on the Report, its contents,
conclusions, any extract, reinterpretation, amendment and/or modification by any third party is entirely at their own risk. 
Please refer to the Statement of Responsibility in Appendix 2 of this report for further information about
responsibilities, limitations and confidentiality.   
Item 8.
Page 99

Page 100

Appendix 2 
2
Contents 
Page
Moray Growth Deal 
1. Introduction & Scope 3
2. Key Issues  3-4 
Detailed Report 
3. Findings/Recommendations 5-11
4. Management Response 5-12 
Appendices 
1. Audit Terms of Reference and Definitions 
2. Statement of Responsibility 
Page 100

Page 101

Appendix 2 
3
1. Introduction and Audit Scope
2.  
The annual audit plan for 2024/25 provides for a review of the governance and
administrative procedures for the management of the Moray Growth Deal (the
Deal). The Moray Council’s Internal Audit Service will overview the Deal
programme and project activities, but each partner organisation is separately
responsible for allocating internal audit resources for its specific project. 
The Moray Growth Deal is a transformational programme, designed to drive
economic growth across Moray over a ten year period and is supported by
£100 million of investment with £65 million being invested by the UK and
Scottish Governments.  The Deal brings together the UK and Scottish
Governments and Moray Council, together with Partners from across the
public, third sector, and businesses, to work collaboratively in delivering the
Deal's vision for the region.  This year, the Deal entered its fourth year of the
ten year programme with four of the eight approved projects now in the
delivery phase and three of the four having already made grant claim
submissions to draw down funding. At the time of the audit review, the funding
claimed for the Moray Growth Deal amounted to £5.2 million. 
The scope of the audit included a review of the governance and administrative
arrangements surrounding the Moray Growth Deal.  It also considered how
partnership working is operating, the financial management of the Deal and
how success is being measured. 
It is pleasing to report that from the testing undertaken and within the scope
of this review, effective arrangements are in place for the governance and
administration of the Moray Growth Deal. However, the following areas were
identified for management attention:   
The audit was carried out in accordance with Public Sector Internal Audit
Standards (PSIAS). 
2. Key Issues 
• The audit included testing on a sample of grant claims for projects
currently in delivery and the expenditure claimed. The review found that
in relation to one project, not all expenditure claimed had supporting
documentation to evidence the payment. This concerned certain
categories of expenditure relating to salary costs, overheads, travel/
subsistence and software related recharges.
Page 101

Page 102

Appendix 2 
4
• In accordance with the Moray Growth Deal Financial Plan, each Partner
Organisation is separately responsible for allocating internal audit resources
for Moray Growth Deal Activities. It was agreed within a previous audit report
that each Partner Organisation should provide their Annual Audit Plans to the
Moray Council for planned internal audit activity regarding the Moray Growth
Deal. However, this requirement could be further supported with an annual
meeting between the Internal Audit Services of the Council and Partner
Organisation to review previous audits undertaken and to discuss and agree
on the scope of future auditing activities. 
Page 102

Page 103

Appendix 2 
5
Moray Growth Deal- 2024/25 
Ref Risk Ratings for
Recommendations
Audit Finding Audit Recommendation
1. Medium The Communications Protocol was developed by the
Moray Council Communications Team before the
signing of the Deal.  This document sets out an agreed
framework for communication and engagement
protocols for both proactive and reactive activities in
relation to the Moray Growth Deal. The Protocol
details that effective use should be made of My Moray
web and social media sites to ensure members of the
public are kept up to date on Moray Growth Deal news
and developments. The audit appreciates the limited
staff resources, but it was noted that during the audit
period, news releases had not been posted to the My
Moray website and social media postings can be
infrequent. 
Further use should be made to post information
on My Moray website and social media sites to
ensure effective communication of any
developments concerning the Moray Growth
Deal. 
Management Response
Responsible Officer Accepted
(Yes/ No)
Timescale for
Implementation
(Date Required) 
Agreed Management Action/Management Comment
Senior Communications
Officer/ MGD Programme
Manager
Yes 31/12/2024 A lack of dedicated comms and engagement resource was
flagged as a risk before the deal was signed and has continued
to be an issue with ensuring continuous comms activity.
However, information is shared in-line with project comms
plans. Social media posts are shared when there is a relevant
update and appropriate content – best practice is to only share
updates when there is newsworthy content, otherwise
Page 103

Page 104

Appendix 2 
6
engagement rates will be negatively impacted. A publishing
error on the website has now been rectified to ensure all
releases are shared timeously.  
As more projects enter delivery and there is more content
available to share publicly this will be done. Quarterly full deal
public updates will also be introduced. 
Page 104

Page 105

Appendix 2 
7
Ref Risk Ratings for
Recommendations
Audit Finding Audit Recommendation
2.   Medium  A Stakeholder Engagement Plan was developed in
2021 to detail the framework for engagement across
all Moray Growth Deal projects with a key objective of
promoting positive benefits for Moray and creating
opportunities for stakeholders to influence the projects
as they develop.  The Plan details the need for regular
review, however it was found there is no evidence of a
formal review of this document. The audit also noted
that the Stakeholder Engagement Plan requires
engagement with targeted audiences to evidence the
success of implementing Moray Growth Deal Projects. 
As more projects enter the delivery phase, it will
become more important to obtain this data to evidence
a success objective in supporting the realisation of
benefits. 
The Stakeholder Engagement Plan should be
reviewed and, if required, updated. 
Engagement should be undertaken with the
targeted audiences for a project to evidence an
established objective of the Moray Growth
Deal.  
Management Response
Responsible Officer Accepted
(Yes/ No)
Timescale for
Implementation
(Date Required) 
Agreed Management Action/Management Comment
MGD Programme Manager /
Senior Communications
Officer
Yes 31/03/2025 While engagement has been taking place at the appropriate
stages of project development, the plan needs to be updated
and have partner sign-off.
Analytics, insights and evaluation are included in the comms
tracker and will link to the updated engagement plan. 
Page 105

Page 106

Appendix 2 
8
Ref Risk Ratings for
Recommendations
Audit Finding Audit Recommendation
3.   Low  It was noted that a Communications Planner
spreadsheet is used to organise and plan a
communication strategy for all projects.  The audit
noted examples where fields within this spreadsheet
regarding dates and explanatory information had not
been completed. Better use could be made of the
Communications Planner spreadsheet to support the
management of the communication needs of the
Moray Growth Deal more effectively. It was also found
that not all communications related information is
saved on the Moray Growth Deal Sharepoint site.  In
order to ensure consistency, all information concerning
Deal activities should be saved on the Moray Growth
Deal Sharepoint site.  
All fields within the Communications Planner
spreadsheet should be completed to aid the
communication management needs of the
Moray Growth Deal.   
All communications related activities, where
documented, e.g., press releases, should be
saved on the Moray Growth Deal Sharepoint
site. 
Management Response
Responsible Officer Accepted
(Yes/ No)
Timescale for
Implementation
(Date Required) 
Agreed Management Action/Management Comment
Senior Communications
Officer 
Senior Communications
Officer
Yes 
Yes
Implemented 
Implemented 
The tracker has been refined to ensure all fields are relevant
and information has been backdated where necessary to
create a comprehensive record of comms actions undertaken. 
Now that the comms team has full access to the Sharepoint
site, documentation can be kept updated through version
controls. 
Page 106

Page 107

Appendix 2 
9
Ref Risk Ratings for
Recommendations
Audit Finding Audit Recommendation
4.   High  The audit reviewed a sample of grant claims for
projects currently being delivered where expenditure
has been claimed from Moray Growth Deal funding. It
was noted that not all spending included in the claims
from a partner organisation could be verified with
supporting evidence.  Invoices/receipts had been
provided for some creditor payments, however, certain
expenditure categories i.e. salary costs, overheads,
travel/ subsistence and software application costs
were not supported by claim forms or system back-up
documentation. 
The audit also checked the type of payments included
within the funding claimed by a partner organisation,
as eligibility for reimbursement can depend on whether
the expenditure is capital or revenue cost. It was noted
that included within the claims are payments for
subsistence, travelling and overheads, which are
generally not considered as capital expenditure.
However, it is appreciated the accounting rules
detailing if expenditure can be capitalised are complex. 
All partner organisations should be informed
that supporting evidence must be provided for
all expenditure claimed from Moray Growth
Deal funding. 
Further to the findings noted within the audit
and discussions with the Chief Financial
Officer, a review of the types of payments
claimed by the partner organisation should be
undertaken to ensure the correct classification
of expenditure. 
Page 107

Page 108

Appendix 2 
10 
Management Response
Responsible Officer Accepted
(Yes/ No)
Timescale for
Implementation
(Date Required) 
Agreed Management Action/Management Comment
Chief Financial Officer 
Chief Financial Officer
Yes 
Yes
Immediate 
31/12/2024
Partners are reminded of the requirement for audit evidence
when claims are submitted and additional scrutiny given to the
project in question 
A review of payment types will be undertaken to ensure
compliance with the European System of Accounts 10 and in
accordance with grant conditions. 
Page 108

Page 109

Appendix 2 
11 
Ref Risk Ratings for
Recommendations
Audit Finding Audit Recommendation
5.   Medium  Further to an internal audit report issued in 2022, a
recommendation detailed that 'Each Partner
Organisation should provide their Annual Audit Plan to
the Moray Council of planned internal audit activity
regarding Moray Growth Deal activities.  These plans
should then be forwarded to the Audit and Risk
Manager for Review'.  At the time of this review, two
partner organisations internal audit services have
either delivered or are undertaking reviews regarding
the delivery of Moray Growth Deal projects. Copies of
each partner organisations annual audit plans had not
been provided to the Moray Council Internal Audit
Service. However, it is pleasing to note that one of the
partner organisations internal audit services did
forward details of the scope of a review to the
Council’s Audit and Risk Manager, which does provide
some assurance of the audit coverage undertaken of
Moray Growth Deal project delivery. 
Partner organisations' internal audit services
should be reminded to forward copies of their
annual audit plans to the Moray Council
regarding planned internal audit activity of
Moray Growth Deal activities. This will allow the
Moray Council, as the Accountable Body, to be
consulted and contribute to the scope of the
review.
Management Response
Responsible Officer Accepted
(Yes/ No)
Timescale for
Implementation
(Date Required) 
Agreed Management Action/Management Comment
MGD Programme Manager /
Senior Auditor
Yes 31/03/2025 At the time of the audit 2 of the 4 Growth Deal projects led by
partners were in delivery, with one having completed an
internal audit at the end of 2023 (the details of which had been
passed to the audit team) and the other project had only
entered delivery in 2024.  
Page 109

Page 110

Appendix 2 
12 
Given different approaches to audit in the partner
organisations, the PMO will work collaboratively with the
Council’s Internal Audit Team to organise an annual meeting
that seeks to: 
- Identify audit activity planned for the year ahead, securing
audit plans ahead of the meeting when Moray Growth Deal
activity is scheduled.  
- Review audit activity undertaken in the previous 12 months
- Share learning and identify cross cutting issues that all
partners should take account of when planning future
activity 
It is expected that the first of these meetings will take place
during Q4 24/25 FY and partners were briefed at the MGD
Board on 26/09/24 of the need to support this.   
Page 110

Page 111

Appendix 2 
13 
Appendix 1 
AUDIT TERMS OF REFERENCE AND DEFINITIONS 
1. Audit Objectives 
1.1 The overall audit objective is to provide an objective independent opinion on
the adequacy and effectiveness of controls / processes.  
1.2 The audit will for each controls / process being considered: 
• Walkthrough the processes to consider the key controls; 
• Conduct sample testing of the identified key controls, and 
•    Report on these accordingly 
1.3 All audit reviews are carried out in accordance with Public Sector Internal
Audit Standards (PSIAS). 
2. Definitions for Auditing Opinions and Findings 
2.1 In order to assist management in using our reports: 
The Internal Auditor will categorise audit assurance opinion according to
their overall assessment of the risk management system, effectiveness of the
controls in place and the level of compliance with these controls and the
action being taken to remedy significant findings or weaknesses. 
Assurance
Level
System and Testing Conclusion
Full The controls tested are being consistently applied
Substantial There is evidence that the level of noncompliance with some of the
controls may put some of the system objectives at risk.
Limited The level of non compliance puts the system objectives at risk.
None Significant non-compliance with basic controls leaves the system
open to error or abuse. 
2.2 Risk ratings for each recommendation is based on the following criteria: 
High Fundamental control weaknesses that require immediate attention
by management to action and mitigate significant exposure to risk
Medium Less critically important controls absent, not being operated as
designed or could be improved
Low Lower level controls absent, not being operated as designed or
could be improved.
Page 111

Page 112

Appendix 2 
14 
Appendix 2 
STATEMENT OF RESPONSIBILITY   
The responsibility for designing and maintaining a sound system of internal control
to prevent and detect fraud and other irregularities rests with management, with
internal audit providing a service to management to support them to achieve this
objective. The Internal Audit Section will assess the adequacy and effectiveness of
the system of internal control arrangements implemented by management and
perform sample testing on those controls in the period under review with a view to
providing an opinion on the extent to which risks in this area are managed. 
The Internal Audit Section will undertake testing with the objective of detecting
significant control weaknesses. However, the audit approach alone should not be
relied upon to identify all strengths and weaknesses in internal controls nor to find
any fraud or irregularity. Even sound systems of internal control can only provide
reasonable and not absolute assurance and may not be proof against collusive
fraud. 
The matters raised in this report are only those that came to our attention during
the course of the audit review and are not necessarily a comprehensive statement
of all the weaknesses that exist or all improvements that might be made.
Recommendations for improvements should be assessed by management for their
full impact before they are implemented. The performance of the audit review
undertaken should not be taken as a substitute for management’s responsibilities
for the application of sound management practices. 
This report is confidential and must not be disclosed to any third party or
reproduced in whole or in part without the written consent of the Moray Council’s
Audit and Risk Manager. 
Page 112

Page 113

Appendix 3 
1
Final Internal Audit Report 
Out of Area Placements   
December 2024   
Distribution: Head of Adult Services 
Head of Children’s, Families & Justice Services 
Chief Financial Officer                             
The Internal Audit Section provides Management with an opinion on the internal control environment
and also categories risk ratings for recommendations as high, medium or low (detailed explanation
provided in Appendix1). The audit recommendations for this review have been classified as follows 
Assurance Level
Risk Ratings for
Recommendations 
Priority 1  3    
Limited Priority 2  3     
Priority 3  0       
Confidentiality and Disclosure Clause 
This report (“Report”) was prepared by the Internal Audit Section of Moray Council. The matters raised in this Report are only
those which came to our attention during our internal audit work. Whilst every care has been taken to ensure that the
information provided in this Report is as accurate as possible, the Moray Council Internal Audit Section has only been able to
base findings on the information and documentation provided and consequently, no complete guarantee can be given that
this Report is necessarily a comprehensive statement of all the weaknesses that exist, or of all the improvements that may be
required. 
This Report was prepared solely for the use and benefit of the Moray Council, Moray Integration Joint Board or the Grampian
Valuation Joint Board. Moray Council's Internal Audit Section accepts no responsibility and disclaims all liability to any third
party who purports to use or rely for any reason whatsoever on the Report, its contents, conclusions, any extract,
reinterpretation, amendment and/or modification. Accordingly, any reliance placed on the Report, its contents, conclusions,
any extract, reinterpretation, amendment and/or modification by any third party is entirely at their own risk. 
Please refer to the Statement of Responsibility in Appendix 2 of this report for further information about
responsibilities, limitations and confidentiality.   
Item 8.
Page 113

Page 114

Appendix 3 
2
Contents 
Page 
Out of Area Placements   
1. Introduction & Scope 3
2. Key Issues  4 
Detailed Report 
3. Findings/Recommendations 5-11
4. Management Response 5-11 
Appendices 
1. Audit Terms of Reference and Definitions 
2. Statement of Responsibility 
Page 114

Page 115

Appendix 3 
3
1. Introduction and Audit Scope 
The Internal Audit Plan for the 2024/25 year provides for a review of the
systems and procedures of people receiving adult care services who are Out of
Area (OOA).  The term “Out of Area” relates to an individual's care and support
being delivered in a local authority area that is different from the local authority
with the statutory responsibility for providing that care and support. The reasons
for individuals to receive care out with the Moray Council local authority area
may be a need to be closer to family or a requirement for more specialist care
that cannot be provided locally. However, responsibility, including costs to
ensure the care provided to the OOA placement meets outcomes agreed upon
within their Care and Support Plan, remains with Health & Social Care Moray as
ordinary residence remains in Moray. Guidance for determining Ordinary
Residence status is provided by the Scottish Government and supplemented by
best practice procedures developed by Social Work Scotland. 
In Health & Social Care Moray Adult Services, OOA placements are managed
within Learning Disability, Mental Health, Physical and Sensory Disabilities and
Older Persons Services. Analysis of the Financial Management System noted
expenditure of approximately £5.8 million in 2023/24. In addition, it was also
noted the Moray Integration Joint Board (MIJB) Annual Accounts include OOA
placements managed by NHS Grampian costing £1.8 million in 2023/24. 
The audit randomly selected a sample of OOA placements to review the
arrangements for the care delivery, ascertain the ordinary residence status and
contract management agreements with care service providers. The sample for
testing was chosen from Learning Disability, Mental Health Needs and Physical
& Sensory Disability Services. Annual expenditure within these services was
noted at approximately £4.3 million for 45 individual OOA placements. Older
Persons are not part of this selected sample, as an audit of Residential Care for
Older Persons has been included as a separate review topic within the Internal
Audit Plan for 2024/25. In addition, testing of OOA placement costs charged to
MIJB but managed by NHS Grampian is outside the scope of this review.
Overall, a “limited opinion” has been detailed as the assurance level for this
review; audit testing noted significant concerns regarding the progress
undertaken in determining ordinary residence status for OOA placements and
the contractual arrangements with care providers.   
The audit was carried out in accordance with Public Sector Internal Audit
Standards (PSIAS). 
Page 115

Page 116

Appendix 3 
4
2. Key Issues 
•    Determination of “Ordinary Residence” for people receiving services 
is crucial in deciding which local authority is required to meet the
needs of adults with care and support needs. Whether the person is
ordinarily resident in the area of the local authority is a key test in
determining where responsibilities lie between local authorities for the
funding and provision of care and support. It is appreciated that the
determination of ordinary residence is complex and involves questions
of both fact and degree regarding time, intention and continuity, which
have to be taken into account. From the sample checked of OOA
placements, weekly care and support costs were up to £5,786 per
week, and have been residing out of Moray for a number of years.
The audit review found examples of OOA placements where it is
considered that further escalation was required to determine ordinary
residence status, which has not been pursued timeously. Proactive
management to review and highlight changes in circumstances of
ordinary residence status of people receiving services should be
undertaken regularly to ensure the responsibility for care delivery is
allocated to the appropriate Local Authority. 
•    Analysis of the Financial Management System (FMS) found that
separately identifying expenditure on OOA placements is not readily
distinguishable or reported in totality. Moray Integration Joint Board
(MIJB) financial reports (2023/24) only record the cost of OOA
placements of £1.8 million managed by NHS Grampian and charged
to the MIJB. Expenditure on OOA placements managed through the
Council’s FMS of approximately £5.8 million per annum is not
separately detailed but included within other reported budget
headings. Consideration should be given to reporting the overall cost
in the delivery of OOA placements by the MIJB, irrespective of
budgetary responsibility. 
•    From the sample checked, approximately a third of OOA placements
managed by various social work teams had no formal contract with
the service providers to deliver support and care to the person
receiving the service. There is a need to ensure appropriate contract
and performance monitoring arrangements are formalised for all OOA
placements. 
Page 116

Page 117

Appendix 3 
5
Out of Area Placements - 2024/25 
Ref Risk Ratings for
Recommendations
Audit Finding Audit Recommendation
1. High The audit found that payments for OOA Placements
could not be readily identified from an analysis
undertaken of the Financial Management System,
either as a gross expenditure cost or within each social
work team. Significant analysis was required as part of
the audit to identify OOA Placement expenditure.
Health & Social Care Moray OOA placement
expenditure is allocated to each social work team
budget for Learning Disabilities, Mental Health Needs,
Older People, and Physical & Sensory Disabilities.
Expenditure is included within the total spend per
these sectors in the MIJB Joint Finance Report used
for reporting budget monitoring to the Board. It was
noted that the Joint Finance Report does have a
separate line entitled OOA Placements; however,
these only detail expenditures for OOA placements
managed by NHS Grampian. For 2023/24, the Joint
Finance Report details OOA placement expenditure of
£1.8 million, but there is also an additional £5.8 million
of OOA placement expenditure as part of social work
teams budget headings. Health & Social Care Moray
governance arrangements would benefit from greater
transparency in the financial reporting arrangements to
ensure more effective monitoring of OOA placement
expenditure. 
Consideration should be given to further
developing the financial monitoring and
reporting arrangements to allow for improved
monitoring and scrutiny of all OOA
expenditures. 
Page 117

Page 118

Appendix 3 
6
Management Response
Responsible Officer Accepted
(Yes/ No)
Timescale for
Implementation
(Date Required) 
Agreed Management Action/Management Comment 
Chief Financial Officer Yes 30/06/2025 NHS Out of Area placements are all in one budget, council
teams are split amongst many budgets. A dynamic register of
placements being developed will allow for easy identification
and the Care First system will need to be regularly updated by
teams to ensure correct reporting. All Out of Area packages will
be recoded to allow for easy identification on financial systems
and Care First.   
Page 118

Page 119

Appendix 3 
7
Ref Risk Ratings for
Recommendations
Audit Finding Audit Recommendation
2. Medium For an audit review to select a sample for testing,
there is a need to ensure that the total population can
initially be identified. However, for this review, the
Auditor was required to undertake considerable work
within each social work team and analysis of the
Financial Management System to compile a definitive
listing of all OOA placements managed within Health
and Social Care Moray. The separate identification of
OOA Placements within data systems would assist in
the monitoring and management of these commonly
high-cost placements. From the sample checked, the
audit noted that the weekly cost of care provided to
OOA placements was up to £5,786 per week. 
Consideration should be given to developing 
OOA placement registers / listings within each
social work team to ensure OOA placements
are visible for management to review. 
Management Response
Responsible Officer Accepted
(Yes/ No)
Timescale for
Implementation
(Date Required) 
Agreed Management Action/Management Comment
Head of Adult Services and
Head of Children’s, Families
& Justice Services 
Yes 31/01/2025 Dynamic Register of all Out of Area placements, collating all
costings and review dates, has been compiled and is awaiting
ratification. This register will be reviewed at regular fortnightly
High Cost Packages board meetings. The register will allow for
accurate reporting to the IJB Board. 
Page 119

Page 120

Appendix 3 
8
Ref Risk Ratings for
Recommendations
Audit Finding Audit Recommendation
3.    High The audit randomly selected 12 OOA placements for
testing. It was found that in a third of placements
across various social work teams, no formal contracts
were in place with the care and support service
providers.  While monitoring of the placements is
undertaken by social work teams, without a contractual
agreement, there is the risk of differing expectations,
accompanied by a lack of formal monitoring of the
engagement and overall service provider performance. 
The current contractual position of all OOA
Placements should be reviewed. Where
contracts with service providers are not in place
for the delivery of care and support to people
receiving the service, referrals should be made
to the Adult Care Commissioning Section for
appropriate contract and monitoring
arrangements to be established.   
Management Response
Responsible Officer Accepted
(Yes/ No)
Timescale for
Implementation
(Date Required) 
Agreed Management Action/Management Comment
Head of Adult Services and
Head of Children’s, Families
& Justice Services 
Yes 30/06/2026 All Out of Area placements to receive interim Service Level
Agreement or contracts that impose regular review periods. 
Page 120

Page 121

Appendix 3 
9
Ref Risk Ratings for
Recommendations
Audit Finding Audit Recommendation
4. High The audit has checked a sample of OOA placements
and reviewed the process for deciding ordinary
residence status. The determination of ordinary
residence is crucial in determining which local
authority is required to meet the care needs of people
receiving the service. The audit noted examples of
OOA placements where further escalation is
necessary to establish ordinary residence status, but
this has not been pursued. In addition, it was also
found that communication in the determination of
ordinary residence had been entered into with other
local authorities, which has resulted in protracted
delays in progressing transfers of responsibilities. An
example was noted where discussion with another
local authority regarding agreement of Ordinary
Residence Status for an OOA placement has been
ongoing for approximately 5 years. 
An exercise should be undertaken to identify all
OOA placements where ordinary residence
status requires to be further clarified. This may
require more proactive communication with
other local authorities or, if necessary, through
Scottish Ministerial involvement to determine
responsibility. It is important to ensure not only
the most effective supervision of care delivery
is provided to the person receiving the service
but also that the responsibility for the financial
cost of the OOA placement care and support is
regularly reviewed to ensure it is the
responsibility of the appropriate local authority. 
Management Response
Responsible Officer Accepted
(Yes/ No)
Timescale for
Implementation
(Date Required) 
Agreed Management Action/Management Comment
Head of Adult Services and
Head of Children’s, Families
& Justice Services 
Yes 31/03/2025 Regular ordinary residence meetings with legal support are
being scheduled as part of an overall review schedule. All
reviews will now go via the fortnightly High Cost Package
group, with review dates set and monitored. A schedule of all
reviews will be established and monitored with quarterly
reporting to the Chief Financial Officer. 
Page 121

Page 122

Appendix 3 
10 
Ref Risk Ratings for
Recommendations
Audit Finding Audit Recommendation
5. Medium Social work teams have different authorisation
practices regarding the initial OOA placement approval
and subsequent invoicing arrangements. Authorisation
of placements can involve Team Resource Allocation
Meetings, a recently formed High Cost Packages
Meeting forum and a Resource Management Group. It
was also noted that different procedures can be
followed, for example, by Mental Health who are not
subject to the same resource allocation processes due
to generally not requiring places in the same
establishments as the Area Teams dealing with Older
Persons and Physical and Sensory Disabilities. The
need to review and formalise authorisation practices
regarding care packages was also included within a
previous internal audit report of SDS Option 2 & 3
management. 
A review to agree consistent arrangements for
authorising individual OOA placements should
be undertaken. 
Management Response
Responsible Officer Accepted
(Yes/ No)
Timescale for
Implementation
(Date Required) 
Agreed Management Action/Management Comment
Head of Adult Services and
Head of Children’s, Families
& Justice Services 
Yes 02/12/2024 All new placements, including mental health, are to be
scrutinised via High Cost Packages group which sits every two
weeks. Resource Management Group (RMG) then make
decision whether to accept placement. Appeals are in the first
instance to RMG, then to senior management team if
necessary. The review schedule identified will form a regular
agenda item for High Cost Packages meetings. 
Page 122

Page 123

Appendix 3 
11 
Ref Risk Ratings for
Recommendations
Audit Finding Audit Recommendation
6.   Medium  Care and Support Plans are developed for each OOA
placement detailing agreed outcomes. Procedures
detail that Care and Support Plans should be reviewed
annually to ensure the agreed care is being provided
and continues to meet the supported person's
assessed needs. Audit testing of a random sample of
12 OOA placements found that 5 had not received
annual reviews. This is an audit finding that has
already been highlighted in a number of other social
care audits where the requirement to review the Care
and Support Plans of people receiving services was
noted.   
Care and Support Plans for people receiving
services should be reviewed annually in
accordance with agreed procedures. 
Management Response
Responsible Officer Accepted
(Yes/ No)
Timescale for
Implementation
(Date Required) 
Agreed Management Action/Management Comment
Head of Adult Services and
Head of Children’s, Families
& Justice Services 
Yes 31/12/2025 A review schedule to be established with care and support
plans being part of this. 
SDS and care package reviews as part of efficiencies
strategies will be considered alongside the out of area package
reviews. A full register with review dates will be available by
end January 2025.   
Page 123

Page 124

Appendix 3 
12 
Appendix 1 
AUDIT TERMS OF REFERENCE AND DEFINITIONS 
1. Audit Objectives 
1.1 The overall audit objective is to provide an objective independent opinion on
the adequacy and effectiveness of controls / processes.  
1.2 The audit will for each controls / process being considered: 
• Walkthrough the processes to consider the key controls; 
• Conduct sample testing of the identified key controls, and 
• Report on these accordingly 
1.3 All audit reviews are carried out in accordance with Public Sector Internal
Audit Standards (PSIAS). 
2. Definitions for Auditing Opinions and Findings 
2.1 In order to assist management in using our reports: 
The Internal Auditor will categorise audit assurance opinion according to
their overall assessment of the risk management system, effectiveness of the
controls in place and the level of compliance with these controls and the
action being taken to remedy significant findings or weaknesses. 
Assurance
Level
System and Testing Conclusion
Full The controls tested are being consistently applied
Substantial There is evidence that the level of noncompliance with some of
the controls may put some of the system objectives at risk.
Limited The level of non compliance puts the system objectives at risk.
None Significant non-compliance with basic controls leaves the system
open to error or abuse. 
2.2 Risk ratings for each recommendation is based on the following criteria: 
High Fundamental control weaknesses that require immediate
attention by management to action and mitigate significant
exposure to risk
Medium Less critically important controls absent, not being operated as
designed or could be improved
Low Lower level controls absent, not being operated as designed or
could be improved.
Page 124

Page 125

Appendix 3 
13 
Appendix 2 
STATEMENT OF RESPONSIBILITY   
The responsibility for designing and maintaining a sound system of internal control
to prevent and detect fraud and other irregularities rests with management, with
internal audit providing a service to management to support them to achieve this
objective. The Internal Audit Section will assess the adequacy and effectiveness of
the system of internal control arrangements implemented by management and
perform sample testing on those controls in the period under review with a view to
providing an opinion on the extent to which risks in this area are managed. 
The Internal Audit Section will undertake testing with the objective of detecting
significant control weaknesses. However, the audit approach alone should not be
relied upon to identify all strengths and weaknesses in internal controls nor to find
any fraud or irregularity. Even sound systems of internal control can only provide
reasonable and not absolute assurance and may not be proof against collusive
fraud. 
The matters raised in this report are only those that came to our attention during
the course of the audit review and are not necessarily a comprehensive statement
of all the weaknesses that exist or all improvements that might be made.
Recommendations for improvements should be assessed by management for their
full impact before they are implemented. The performance of the audit review
undertaken should not be taken as a substitute for management’s responsibilities
for the application of sound management practices. 
This report is confidential and must not be disclosed to any third party or
reproduced in whole or in part without the written consent of the Moray Council’s
Audit and Risk Manager. 
Page 125

Page 126

Page 126

Page 127

REPORT TO: MORAY INTEGRATION JOINT BOARD AUDIT, PERFORMANCE
AND RISK COMMITTEE ON 30 JANUARY 2025 
SUBJECT: CHILDRENS SERVICES JOINT INSPECTION IMPROVEMENT
PLAN 2024 
BY:  INTERIM CHIEF SOCIAL WORK OFFICER/HEAD OF SERVICE
1. REASON FOR REPORT 
1.1 To provide the Committee with an overview of the governance arrangements
for the joint inspection improvement plan which was submitted to the Care
Inspectorate on 5 March 2024. 
2. RECOMMENDATION 
2.1 It is recommended that Committee: 
i) scrutinise and note the content of the improvement plan produced
in response to the joint inspection, attached as Appendix 1; and 
ii) note the governance arrangements in place for child protection in
Moray, attached as Appendix 2. 
3. BACKGROUND 
3.1 On 10 July 2023 Moray received notification of Joint Inspection of Services for
Children at Risk of Harm in Moray, which was conducted in 3 phases to 29
November 2023. 
3.2 The findings from the joint inspection were previously reported to this
committee on 29 February 2024 (para 13 of minute refers). 
4. INSPECTION IMPROVEMENT PLAN 
4.1 The improvement plan in Appendix 1 covers three main areas of improvement: 
• Children and young people at risk of harm influencing service planning and
improvement
• Children and young people at risk of harm benefit from independent
advocacy
Item 9.
Page 127

Page 128

• Young people at risk of harm from themselves or to others, or from risk in
the community 
4.2 Partnership approval for the improvement plan was secured via Moray Child
Protection Committee and Moray Public Protection Chief Officers Group prior to
final submission to inspectors on the 5 March 2024. 
4.3 The Independent Chair of Moray Child and Adult Protection Committees will
report progress of the improvement plan to Moray Public Protection Chief
Officers Group. 
5. PARTNERSHIP GOVERNANCE ARRANGEMENTS 
5.1 Chief Officers are ultimately responsible and accountable for improving the
experience and outcomes for children who may need protection as noted within
Scottish Government 2019 guidance Protecting children and young people:
Child Protection Committee and Chief Officer responsibilities. 
5.2 Working within the accountability structures of their respective organisations,
Chief Officers work collectively to identify and commission inter-agency activity
for the protection of children and young people. Moray Child Protection
Committee is the inter-agency mechanism to take this work forward. 
5.3 The improvement plan is broader than child protection and activity also sits
within the context of Moray Community Planning Partnership Childrens
Services Plan 2023-26. 
5.4 The Moray Getting it Right for Every Child (GIRFEC) leadership group is the
strategic planning group for children’s services with remit to oversee the
development and implementation of the Childrens Services Plan 2023-26 on
behalf of Moray Community Planning Board. 
5.5 To support alignment between governance for child protection and wider
children’s services strategic planning, Moray Child Protection Committee also
provides quarterly progress reports to the GIRFEC Leadership Group. 
5.6 Appendix 2 further outlines the governance arrangements for Moray’s
Children’s Services Partnership and the role and remit of groups responsible for
child protection. 
6. SUMMARY OF IMPLICATIONS 
(a) Corporate Plan and 10 Year Plan (Local Outcomes
Improvement Plan (LOIP)) and Moray Integration Joint
Board Strategic Plan “Partners in Care 2022 – 2032”
This report notes that the improvement plan is aligned with key priority
areas across the Children’s Services partnership. 
(b) Policy and Legal
None arising as a direct result of this report. 
(c) Financial implications
None arising as a direct result of this report.
Page 128

Page 129

(d) Risk Implications and Mitigation
None arising as a direct result of this report. 
(e) Staffing Implications
There are no proposed changes to the staffing or reporting relationships 
(f) Property
None arising as a direct result of this report. 
(g) Equalities/Socio Economic Impact
None arising as a direct result of this report. 
(h) Climate Change and Biodiversity Impacts
None arising as a direct result of this report. 
(i) Directions
None arising as a direct result of this report. 
(j) Consultations
HSCM Senior Management Team. 
7. CONCLUSION 
7.1 On 5 March 2024 an improvement plan was submitted to the care
Inspectorate in response to the Joint Inspection of Services for Children
at Risk of Harm in Moray. 
7.2 Progress against the improvement plan is monitored by the Moray Child
Protection Committee. 
7.3 The Independent Chair of the Moray Child Protection Committee provides
updates to both the Moray Public Protection Chief Officers Group and the
Moray GIRFEC Leadership Group. 
Author of Report:  Emma Johnston, Public Protection Lead Officer  
Background Papers: Report of a joint inspection of services for children and young people
at risk of harm in Moray 
Page 129

Page 130

Page 130

Page 131

Approved by Moray Public Protection Chief Officers Group on 12/04/24.
Submitted to Care Inspectorate on 05/03/2024.
Improvement plan
Moray joint inspection of services for children and young people at risk of harm
Introduction
This improvement plan identifies and commits to improvements centred on the findings of the 2024 joint inspection of services for children
at risk of harm in Moray. These improvement’s, some of which are already underway, also sit within a context of a partnership Children’s
Services Plan which incorporates Moray’s Promise plan. 
The leads indicated within the plan form part of the Moray structure which sits below the Child Protection Committee and GIRFEC
Leadership Group and it will be the responsibility of these subgroups to create the detail of the activity necessary to achieve these
improvements and RAG rate them accordingly. A more detailed action plan will therefore sit alongside this document. 
The Child Protection Committee will oversee the activity related to this plan and report progress to Moray Public Protection Chief Officers
Group. 
The Improvement Plan covers three main areas of improvement, namely;
• Children and young people at risk of harm influencing service planning and improvement
• Children and young people at risk of harm benefit from independent advocacy
• Young people at risk of harm from themselves or to others, or from risk in the community
There is a need for improvement in how the partnership self-evaluate and understand the impact their services are making and this is key
to the improvement activity noted in this plan. 
APPENDIX 1
Item 9.
Page 131

Page 132

2 | All children and young people in Moray grow up loved, safe, respected and equal, because our services and workforce put people first and support families with the right help at the right time 
Children and young people at risk of harm, influencing service planning and improvement.
Joint Inspection Findings: Information about children and young people’s experience of services was not routinely sought, analysed and
used to inform service planning.
Development area
What do we need to do?
Action
How Will We Do It?
Lead Timescale  Evidence 
Produce a Children and
Young Person’s Rights
and Participation Strategy
ensuring a focus on
children at risk of harm.
Develop a participation strategy
which includes specific objectives
relating to children in need of care
and protection and those at risk of
harm.
Children’s Rights
and Participation
Group 
TBC
Children’s Rights and Participation
strategy is co- produced with children and
young people and approved through
governance structures.
Ensure that children,
young people, and their
families have
involvement in strategic
planning
Provide opportunities for children,
young people and where
appropriate, parents and/or carers
to contribute to strategic planning 
Children’s Rights
and Participation
Group 
March 2025
Self-evaluation activity undertaken with
children and young people at risk of harm
evidences that their voice is influencing
strategic planning. (included in annual
self-evaluation calendar)
Increase awareness of the
role and function of the
Child Protection
Committee 
Develop a communication and
engagement strategy with children,
young people and frontline
practitioners to increase awareness
of the role and contribution of the
Child Protection Committee
Child Protection
Committee and
Child Protection
Improvement
Officer  
September
2024
Workforce report increased awareness
through quality assurance activity
(included in annual self-evaluation
calendar)
Develop and launch Public
Protection website 
Child
Protection
Improvement
Officer 
September
2024
Public Protection website is live. 
Analysis of website hits 
Moray Childrens
Services Plan
2023-26
Priority High Level Outcome
Hearing Children and Young People’s
voices The voice of children and young people is evident in all things that impact on them.
Page 132

Page 133

3 | All children and young people in Moray grow up loved, safe, respected and equal, because our services and workforce put people first and support families with the right help at the right time 
Children and young people at risk of harm benefit from independent advocacy
Joint Inspection Findings: Children and young people and parents and carers were contributing to decisions about their lives, though not all had access yet
to independent advocacy.
Development area
What do we need to do?
Action
How Will We Do It?
Lead Timescale  Evidence 
Improve how we ensure
children’s views are
central to decision
making
Children and young people at risk of
harm are consistently encouraged by
all staff to take up independent
advocacy
Children’s Rights
and Participation
Group 
September 2024
Analysis of record of offer of independent
advocacy support  Develop mechanisms to establish
and record whether young people
have been offered advocacy services
and their reasons, where
appropriate, for not taking this up  Children’s Rights
and Participation
Group 
September 2024
Identify and address the barriers to
children and young people engaging
with independent advocacy services
March 2025 Increase uptake of advocacy service 
Evidence the impact of independent
advocacy 
Social Work
Commissioning
Team 
March 2025
Commissioned service contract monitoring
processes 
Quality Assurance included in file auditing
activity within annual self-evaluation calendar 
Moray Childrens
Services Plan
2023-26
Priority High Level Outcome
Keeping Children and Young People
Safe Children & young people are empowered to participate in child protection processes 
Page 133

Page 134

4 | All children and young people in Moray grow up loved, safe, respected and equal, because our services and workforce put people first and support families with the right help at the right time 
Young people at risk of harm from themselves or to others, or from risk in the community
Joint Inspection Findings: A multi-agency co-ordinated approach to risk was not yet in place for young people at risk of harm from themselves, to others or
from risk in the community. Planning and support for young people at risk of harm from themselves, or to others or at risk in the community, was less
effective than support for children and young people at risk of abuse and neglect.
Development area
What do we need to do?
Action
How Will We Do It?
Lead Timescale Evidence
Introduce a multi-agency
framework for
vulnerable young people,
who are a risk to
themselves, to others or
are at risk in the
community 
Co-produce a Protection from Serious
Harm procedure and guidance with all
partners including young people and
their families. 
Child Protection
Implementation
Group
September
2024
Procedure and guidance produced and
approved. 
Quality assurance of procedure included in
annual self-evaluation calendar
Implementation of vulnerable young
person procedure, including training
for staff
Child Protection
Implementation
Group
March
2025
Audit activity undertaken (included in annual
self-evaluation calendar) 
Moray Childrens
Services Plan
2023-26
Priority High Level Outcome
Keeping Children and Young People
Safe
Children and young people are safer because risks have been identified early and
responded to effectively.
Children and young people at risk of or who come into conflict with the law are
supported with compassion and care. 
Page 134

Page 135

5 | All children and young people in Moray grow up loved, safe, respected and equal, because our services and workforce put people first and support families with the right help at the right time 
Measuring Impact
Joint Inspection Findings: The child protection committee had not yet fully developed the mechanisms necessary to understand and communicate the
difference that services were making to the lives of children and young people at risk of harm. The partnership’s agenda for improvement and change was
not yet underpinned by a cohesive approach to service review and self-evaluation.
Development area
What do we need to do?
Action
How Will We Do It?
Lead Timescale Evidence
Ensure our agenda for
improvement and change
is underpinned by a
cohesive approach to
service review and self-
evaluation 
Develop a robust performance
management and quality
improvement framework
Child Protection
Committee
/GIRFEC
Leadership
Group 
March 2025 Quality Improvement Framework launched
Establish and implement annual
multi-agency self-evaluation
calendar to ensure self-evaluation
activity is undertaken in key areas.
This includes capturing voice /views
of children and young people at risk
of harm.
Child Protection
Committee  September 2024
Calendar developed and operational. 
Annual quality and standards report produced
to inform ongoing improvement activity
Include the voice of children, young
people, and their parents/ carers in
all quality assurance activity
Children’s
Rights and
Participation
Group 
March 2025 
Moray Childrens
Services Plan
2023-26
Priority High Level Outcome
Working In Partnership
We more consistently and effectively measure impact of the actions we are taking to
improve outcomes for children, young people, and families.
Improved co-ordination of continuous improvement activity.
Page 135

Page 136

6 | All children and young people in Moray grow up loved, safe, respected and equal, because our services and workforce put people first and support families with the right help at the right time 
Planning and Support
Joint Inspection Findings: The quality of chronologies, assessments and plans was variable. While some single agency audit activity had taken place, the
partnership had not yet developed a comprehensive multi-agency approach to quality assurance to support improvement.
Development area
What do we need to do?
Action
How Will We Do It?
Lead Timescale  Evidence 
Ensure the multi-agency
GIRFEC integrated
assessment and planning
framework leads to
improved/consistent
high-quality practice. 
Develop a GIRFEC Integrated
Assessment Framework for Moray
(IAF) 
Child Planning
Group
September
2024 IAF developed and operational
Deliver training and
development on the Moray
GIRFEC IAF 
Learning and
Development
Group 
March 2025
Training in place
Evaluation of impact of training undertaken
with participants
Implement self-evaluation activity to
monitor standards of practice and
inform improvement activity. 
Data and
Evaluation
Group
September
2025 
Self-evaluation activity operational
(incorporated within annual self-evaluation
calendar) 
% Increase in quality of files audited, using
inspection information as baseline. 
Produce multi agency chronologies
to a consistently high standard and
are utilised as a tool of analysis to
inform SMART action planning
Child
Planning
Group
March 2025
Quality assurance activity demonstrates
improvement in quality of multi-agency
chronologies (incorporated within annual
self-evaluation calendar)
Finalise revision of multi-agency
child’s planning process and roll out
associated training 
Child’s Planning
Group 
September
2024
Test of change completed, and process
finalised based on learning. 
Audit activity included within annual self-
evaluation calendar. 
Moray Childrens
Services Plan
2023-26
Priority High Level Outcome
Strengthening Family Support Children and family's needs are addressed early through the implementation of
effective child’s planning processes
Supporting Our Workforce Integrated working practice is enhanced through joint development opportunities that
supports our shared vision, core principles and values.
Page 136

Page 137

7 | All children and young people in Moray grow up loved, safe, respected and equal, because our services and workforce put people first and support families with the right help at the right time 
Relationships with Staff
Joint Inspection Findings: Not all children and young people felt that their worker spent time with them or gave them the help they needed. This was linked
to a lack of consistency of staff members and some families experienced frequent changes in staff.
Development area
What do we need to do?
Action
How Will We Do It?
Lead Timescale  Evidence 
Explore ways to improve
workforce planning to
support children and
young people at risk of
harm having consistent
support from key workers 
Scope current position in relation to
workforce pressures and provide
analysis of gaps, recruitment, and
retention challenges 
Child Protection
Committee September 2024 Analysis of current position completed 
Exploration of potential solutions
with key stakeholders drawing on
local and national best practice
Child Protection
Committee with
Child Protection
Improvement
Officer
September 2024 Potential solutions and recommendations
collated, agreed, and actioned 
Implementation of agreed solutions  
Child Protection
Committee with
Child Protection
Improvement
Officer
September 2024 Quality assurance activity
In partnership with third sector
maximise their services to meet the
needs of children, young people, and
families. 
Child Protection
Committee March 2025
Third sector performance reports demonstrate
improved uptake and impact (as evidenced
through outcome measurement tools used by
third sector) 
Moray Childrens
Services Plan
2023-26
Priority High Level Outcome
Supporting Our Workforce Staff facilitate and enable the relationships, networks and connections that support
our children, young people, and families. 
Page 137

Page 138

Page 138

Page 139

APPENDIX 2 
Children’s Services Governance Arrangements in Moray
The Moray GIRFEC Leadership Group (GLG) works on behalf of the Moray
Community Planning Partnership to deliver on the Moray Childrens Services Plan
2023-26. Keeping children & young people safe is one of the five priorities of the
Childrens Services Plan. This priority is overseen by the Moray Child Protection
Committee which sits within a wider infrastructure for public protection within the
partnership. 
Protecting People in Moray
The Public Protection Chief Officers Group provides leadership, direction and
scrutiny of the respective Child Protection and Adult Support & Protection
Committees, and related strategic partnerships which include the Alcohol and Drug
Partnership, Violence Against Women and Girls Partnership and Moray Community
Justice Partnership. 
The Moray Public Protection Chief Officers Group meet quarterly to review the
delivery of services and improvement plans across the public protection partnership. 
The Independent chair of the Moray Child Protection Committee attends the Public
Protection Chief Officers Group as does the Chief Social Work Officer who is also
chair of the GIRFEC Leadership Group. To support alignment between governance
for child protection and wider children’s services strategic planning, the Moray Child
Protection Committee also provide quarterly progress reports to the GIRFEC
Leadership Group.  
Item 9.
Page 139

Page 140

Moray Child Protection Committee
Chair Independent Chair 
Support
Team
Public Protection Lead Officer 
Child Protection Improvement Officer 
Business Support Public Protection 
Contact mcpc@moray.gov.uk
Purpose The Moray Child Protection Committee (CPC) is the inter-agency body that drives forward the work on
behalf of the Moray Public Protection Chief Officers Groups to protect children from neglect, abuse and
harm.  CPC Objectives are to:
• jointly identify and manage risk to children and young people
• improve the experience of and outcomes for children who may need protection
Membership
Voting Members
• Detective Chief Inspector Public Protection Unit, Police Scotland
• SCRA Regional Manager 
• Lead Nurse for Child Protection
• Childrens Hearings Scotland Area Convener 
• Chief Social Work Officer/ Head of Service Health & Social Care Moray
• Independent Chair of Child Protection Committee 
• Third Sector Representative
• Ministry of Defence Representative
• Service Manager, Children & Families and Justice Social Work 
• Chief Education Officer, Moray Council
Attendees
• Housing Services Representative
• Care Inspectorate Strategic Link Inspector
• Public Protection Lead Officer 
• Specialist Nurse Child Protection
• Mental Health Service Manager
• Children & Families Health Services Lead
• Getting it Right for Every Child (GIRFEC) Lead Officer 
• Quality Improvement Officer Education
Remit The CPC must perform a number of crucial functions in order to jointly identify and manage risk to
children and young people and improve the experience of and outcomes for children who may need
protection.  These functions are: continuous improvement; publicity and promotion; strategic planning
and annual reporting.
Moray CPC Substructure 
Moray Public Protection Introduction Pack (Child Protection) 
Page 140

Page 141

National Publications and Website(s)
National guidance for child protection in Scotland 2021
Protecting children and young people: Child Protection Committee and Chief Officer
responsibilities (2019)
Moray Public Protection Chief Officers Group
Vision We are here to serve the communities of the Moray and will do this with fairness, integrity and respect. 
We will challenge each other constructively when necessary to ensure we deliver beyond expectations
for these communities.
Purpose
The Moray Public Protection Chief Officers Group provides strategic leadership and scrutiny to the
public protection work of their respective agencies and to inter-agency work. 
Chief Officers in Moray are individually and collectively responsible for the leadership, direction and
scrutiny of their respective Child Protection and  Adult Support & Protection Committees and are linked
to public protection partnerships and groups, which include the Alcohol and Drug Partnership, Violence
Against Woman and Girls Partnership and Community Justice Partnership. 
Membership
• Moray Council, Chief Executive 
• NHS Grampian, Chief Executive
• Police Scotland, Chief Superintendent
• Health & Social Care Moray, Chief Officers
• Moray Council, Chief Social Work Officer
• Independent Chair, Adult Protection Committee & Child Protection Committee
• Scottish Fire & Rescue Services
Remit
In relation to public protection, Chief Officers will:
• identify and commission inter-agency activity for protection of children and adults
• be responsible and accountable for improving the experience of and outcomes for children and adults
who may need protection
• consider issues that have an impact on wider public protection arrangements and development
• agree Annual/Biennial Reports and Improvement/Business Plans
• consider performance reports and findings from case reviews 
Page 141

Page 142

National guidance for child protection committees undertaking learning reviews (2021)
Child Protection Scotland (Link to publications page here) 
Page 142

Page 143

REPORT TO: MORAY INTEGRATION JOINT BOARD AUDIT, PERFORMANCE
& RISK COMMITTEE ON 30 JANUARY 2025 
SUBJECT: PAYMENT VERIFICATION 
BY:   HEAD OF SERVICE / DEPUTY CHIEF OFFICER 
1. REASON FOR REPORT 
1.1 The purpose of this report is to provide an update on the review of the Payment
Verification (PV) Assurance Service provided by National Services Scotland
(NSS) Practitioner Services Divisions (PSD), on behalf of NHS Grampian. 
2. RECOMMENDATION 
2.1 It is recommended that Committee: 
i) scrutinise and note the arrangements in place in Grampian for the
management of the payment verification process; 
ii) note that the payment verification process has now fully restarted
after pausing during COVID-19; and 
iii) note the actions already taken to address the outstanding issues,
with plans for future action to include an update on progress to this
committee in 2025. 
3. BACKGROUND 
3.1 A report was presented to this Committee on 26 September 2024 (para 11 of
minute refers) providing a general update on the PV process when it was
agreed that the report was to be shared with Aberdeen City and Aberdeenshire
(Integration Joint Boards (IJBs) (complete) and a progress update was to come
back to this committee in January 2025. 
4. KEY MATTERS RELEVANT TO RECOMMENDATION 
4.1 Difficulties were experienced in receiving updates on progress for the
improvement of PSD/PV outcomes prior to the COVID-19 pandemic. 
Item 10.
Page 143

Page 144

4.2 Since COVID-19 the process has caught up, and there are no longer significant
delays in the system. 
4.3 NHS Grampian has now obtained sessional GP clinical input for the virtual
General Medical Services (GMS) visits. Two GPs are now available which
provides resilience. 
4.3 NHS Grampian has identified lack of consultation on the process in general
plus clear governance channels, particularly with respect to NSS PV Reference
Groups. This has been escalated via both the national Family Health Services
(FHS) Finance Execs and Primary Care Management Lead groups. 
4.4 The above is progressing with dialogue ongoing at a national level, and some
progress has been made. The FHS Finance Execs are reviewing and plan to
discuss again early in 2025. 
4.5 Until this is resolved the Partnership Agreement between NSS and NHS
Grampian referred to in DL 2923 (24) remains unsigned. 
5. SUMMARY OF IMPLICATIONS 
(a) Corporate Plan and 10 Year Plan (Local Outcomes
Improvement Plan (LOIP)) and Moray Integration Joint
Board Strategic Plan “Partners in Care 2022 – 2032”
The Moray Integration Joint Board requires effective governance
arrangements for those services and functions delegated to it. Such
governance arrangements include systems for managing risks. 
(b) Policy and Legal
There are no legal implications arising from this report. 
(c) Financial implications
There are no financial implications arising directly from this report. 
(d) Risk Implications and Mitigation
There is a risk that assurance cannot be provided to NHS Grampian that
Payment Verification is being carried out appropriately. 
(e) Staffing Implications
There are no staffing matters arising directly as a result of this report. 
(f) Property
There are no implications in terms of Council or NHS property directly
arising from this report. 
(g) Equalities/Socio Economic Impact
An Equality Impact Assessment is not required because there are no
service, policy or organisational changes proposed in this report. 
(h) Climate Change and Biodiversity Impacts
There are no matters arising directly as a result of this report. 
(i) Directions
Page 144

Page 145

There are no directions directly as a result of this report. 
(j) Consultations
Consultation has taken place with the Head of Service, Service Manager
Primary Care Contracts and Finance Manager regarding this report. 
6. CONCLUSION 
6.1 It is encouraging to note the PV process has now fully resumed. 
6.2 However, there are still further updates required as to governance of
service provided, especially to do with PV specification. 
6.3 Updates will be brought back to future meetings of this Committee. 
Author of Report:  Peter Maclean, Service Manager, Primary Care Contracts 
Background Papers:   DL (2023) 24 - Revised Payment Verification Protocols 
Ref: 
Page 145