Agenda Document Pack - Risk and Audit Scrutiny Committee - 30/09/2025

South Lanarkshire Council · 30 September 2025
Back to Risk and Audit Scrutiny Committee — 30 September 2025 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

Council Offices, Almada Street        
Hamilton, ML3 0AA 
Monday, 22 September 2025 
Dear Councillor 
Risk and Audit Scrutiny Committee 
The Members listed below are requested to attend a meeting of the above Committee to be
held as follows:- 
Date:  Tuesday, 30 September 2025
Time:  10:00
Venue: Hybrid - Committee Room 1, Council Offices, Almada Street, Hamilton,
ML3 0AA 
The business to be considered at the meeting is listed overleaf. 
Yours sincerely 
Paul Manning
Chief Executive 
Members 
Elaine McDougall (Chair), Mary Donnelly (Depute Chair), Mathew Buchanan, Colin Dewar, Alistair
Fulton, Ross Gowland, Celine Handibode, Susan Kerr, Richard Lockhart 
Substitutes
Monique Equi, Gavin Keatt, Julia Marrs, Helen Toner 
1

Page 2

BUSINESS 
1 Declaration of Interests 
2 Minutes of Previous Meeting
Minutes of the meeting of the Risk and Audit Scrutiny Committee held on 25
June 2025 submitted for approval as a correct record.  (Copy attached) 
5 - 10 
Monitoring Item(s) 
3a  External Auditors' Report 2024/2025
Letter and report dated 30 September 2025 by Audit Scotland, External Auditors
to the Council.  (Copy attached) 
11 - 76 
3b  Transformation: How Councils Are Redesigning and Delivering More
Efficient Services to Achieve Planned Outcomes.  Best Value Thematic
Work in South Lanarkshire Council 2024/2025
Report dated September 2025 by Audit Scotland, External Auditors to the
Council.  (Copy attached) 
77 - 100 
3c  External Auditors' Report 2024/2025. South Lanarkshire Council Charitable
Trusts
Letter and report dated 30 September 2025 by Audit Scotland, External Auditors
to the Council.  (Copy attached) 
101 - 120 
Item(s) for Decision 
4 Audited Annual Accounts 2024/2025
Report dated 19 September 2025 by the Executive Director (Finance and
Corporate Resources).  (Copy attached) 
121 - 124 
5 Internal Audit Activity Report
Report dated 5 September 2025 by the Executive Director (Finance and
Corporate Resources).  (Copy attached) 
125 - 142 
Item(s) for Noting 
6 Financial Resilience and Sustainability
Report dated 10 September 2025 by the Executive Director (Finance and
Corporate Resources).  (Copy attached) 
143 - 152 
7 Audit Scotland – Local Government Budgets 2025/2026
Report dated 7 August 2025 by the Executive Director (Finance and Corporate
Resources). (Copy attached) 
153 - 160 
8 Fraud Statistics Annual Report 2024/2025
Report dated 28 August 2025 by the Executive Director (Finance and Corporate
Resources). (Copy attached) 
161 - 172 
9 Year End Insured Claims Report – 2024/2025
Report dated 5 September 2025 by the Executive Director (Finance and
Corporate Resources).  (Copy attached) 
173 - 184
2

Page 3

10  Year-End Risk Management Report - 2024/2025 and Review of Council's
Top Risks - 2025/2026
Report dated 5 September 2025 by the Executive Director (Finance and
Corporate Resources).  (Copy attached) 
185 - 200 
11  Annual Update on the Use of Surveillance Powers - The Regulation of
Investigatory Powers (Scotland) Act 2000
Report dated 6 August 2025 by the Executive Director (Finance and Corporate
Resources). (Copy attached) 
201 - 230 
12  Forward Programme for Future Meetings
Report dated 20 August 2025 by the Executive Director (Finance and Corporate
Resources). (Copy attached) 
231 - 234 
Urgent Business 
13  Urgent Business
Any other items of business which the Chair decides are urgent. 
For further information, please contact:-
Clerk Name: Elizabeth-Anne McGonigle
Clerk Telephone: 07385403101
Clerk Email: elizabeth-anne.mcgonigle@southlanarkshire.gov.uk 
3

Page 4

4

Page 5

RISK AND AUDIT SCRUTINY COMMITTEE 
Minutes of meeting held via Confero and in Committee Room 1, Council Offices, Almada Street,
Hamilton on 25 June 2025 
Chair: 
Councillor Elaine McDougall 
Councillors Present:
Councillor Mathew Buchanan, Councillor Colin Dewar, Councillor Ross Gowland, Councillor Susan
Kerr, Councillor Julia Marrs (substitute for Councillor Alistair Fulton), Councillor Helen Toner
(substitute for Councillor Mary Donnelly) 
Councillors' Apologies:
Councillor Mary Donnelly (Depute), Councillor Alistair Fulton, Councillor Celine Handibode,
Councillor Richard Lockhart 
Councillor Also Present:
Councillor Joe Fagan (for items 3 to 5) 
Attending:
Chief Executive’s Service
P Manning, Chief Executive (for items 3 to 5)
Finance and Corporate Resources
J Taylor, Executive Director; Y Douglas, Audit and Compliance Manager; C Fergusson, Head of
Finance (Transactions); E-A McGonigle, Administration Adviser; A Norris, Administration Assistant;
L O’Hagan, Head of Finance (Strategy); I Opatha, Administration Officer; I Strachan, Head of
Administration and Legal Services 
Also Attending: 
Audit Scotland
A Barclay and M Ferris, External Auditors 
1 Declaration of Interests 
No interests were declared. 
2 Minutes of Previous Meeting 
The minutes of the meeting of the Risk and Audit Scrutiny Committee held on 6 May 2025 were
submitted for approval as a correct record. 
The Committee decided: that the minutes be approved as a correct record. 
3 Internal Audit Annual Assurance Report 2024/2025 
A report dated 2 June 2025 by the Audit and Compliance Manager (Finance and Corporate
Resources) was submitted providing:- 
 a summary of progress and performance of Internal Audit for the financial year 2024/2025
2
5

Page 6

 an opinion on the adequacy and effectiveness of the Council’s framework of governance,
risk management and control systems based on audit work undertaken in 2024/2025 
Internal Audit was noted as forming part of the Council’s wider governance framework, with its
primary objective being to evaluate and improve the effectiveness of governance, risk
management and control processes.  As a function, it did this by delivering a programme of
audit assignments and using the output from those reviews to inform an annual audit opinion on
the effectiveness of the Council’s framework of governance, risk management and control
arrangements.   
Details were provided on:- 
 compliance with relevant internal audit standards and guidance
 purpose and approach of the Service
 link to the Council’s objectives and top risks
 workload and performance 
 areas of assurance 
 overall assurance and annual audit opinion
 future year challenges and tasks 
The overall opinion expressed on the Council’s control environment was that a reasonable level
of assurance could be placed on the adequacy and effectiveness of the Council’s framework of
governance, risk management and control arrangements for the year ended 31 March 2025. 
The Internal Audit findings would inform the Council’s 2024/2025 Annual Governance
Statement. 
The 2024/2025 Internal Audit Plan had sought to return to a more routine programme of work,
however, this had proved challenging in practice with the implementation of Oracle Fusion,
which required significant resource commitment.  The momentum of the evolving process would
continue after the implementation of Oracle Fusion, with Social Work and Housing systems
planning to go-live in 2025/2026.  This, together with the financial challenges across the public
sector, meant that the Council, like all local authorities, was in a period of transformational
change.  Investing time to fully develop analytical tools would be increasingly important and was
being actively considered as part of post-system implementation reviews.  A data strategy had
been drafted to provide a structure and focus for future plans, as detailed in paragraph 9.2 of the
report. 
Information was also provided on the new Global Internal Audit Standards (GIAS), which were
effective from April 2025.  The latest external assessment of the function’s compliance with the
PSIAS provided assurance that professional standards were being adhered to.  This level of
conformance provided a good foundation for the new Standards. 
The Chair, on behalf of the Committee members, thanked the Audit and Compliance Manager
and wider team for the extensive internal audit work undertaken in 2024/2025. 
The Committee decided: 
(1) that the performance of Internal Audit during 2024/2025 be noted; 
(2) that the overall findings from internal audit work be noted, and that it be approved that
those would inform the Council’s 2024/2025 Annual Governance Statement; and 
(3) that the level of assurance on the Council’s control environment be noted. 
6

Page 7

4 Annual Governance Statement for 2024/2025 and Significant Governance Areas
Quarter 4 Progress Report
A report dated 3 June 2025 by the Executive Director (Finance and Corporate Resources) was
submitted on the Annual Governance Statement for 2024/2025 and progress against significant
governance areas identified within the 2023/2024 Annual Governance Statement at Quarter 4. 
Each year, the Council undertook a review of the governance arrangements required to support
its financial and operational controls.  This review provided the basis for the Annual Governance
Statement, which was included in the Council’s Annual Report and Statement of Accounts. 
The Council’s governance assurance framework was detailed in Appendix 1 to the report.  The
resulting Annual Governance Statement for 2024/2025, attached as Appendix 2 to the report,
provided information on the Council’s compliance during 2024/2025. The annual review of
governance arrangements across the Council demonstrated sufficient evidence that the
principles of delivering good governance in local government, contained in the Local Code of
Corporate Governance, operated effectively and that the Council complied with its Code. 
Progress on the significant governance areas highlighted within the Annual Governance
Statement 2023/2024 was attached as Appendix 3 to the report. 
The Head of Finance (Transactions) responded to a member’s question in relation to information
governance, which was a new significant governance area identified in 2024/2025. 
The Committee decided: 
(1) that the Annual Governance Statement, attached as Appendix 2 to the report, which would
be included in the Council’s 2024/2025 Annual Report and Statement of Accounts, be
approved; and 
(2) that the progress against the significant governance areas identified within the Annual
Governance Statement 2023/2024, attached as Appendix 3 to the report, be noted. 
[Reference:  Minutes of 25 June 2024 (Paragraph 4)] 
5 Unaudited Annual Accounts 2024/2025 
A report dated 2 June 2025 by the Executive Director (Finance and Corporate Resources) was
submitted on the requirement for members to consider the Unaudited Annual Accounts of the
Council and related Charitable Trusts, attached as appendices 1 and 3 to the report, by 30 June
2025. 
The Council’s Unaudited Annual Accounts detailed key information on the Council’s expenditure
and income for the financial year ended 31 March 2025. The accounts also covered the
Charitable Trusts managed by the Council. 
The full Unaudited Annual Accounts would be circulated to all elected members following their
submission to the External Auditor by 30 June 2025 and would be advertised as being available
for public inspection on the Council’s website from 1 July 2025 until the date the Audited
Accounts would be published.   
The information contained in the Unaudited Accounts took into account the final outturn position,
as detailed in Appendix 2 to the report, which was submitted for approval to the Executive
Committee meeting on 25 June 2025.  Appendix 2 also provided an Expenditure and Funding
Analysis, as required by the Chartered Institute of Public Finance and Accountancy (CIPFA)
Code of Accounting Practice.
7

Page 8

Following the audit of the Accounts over the summer months, the Audited Annual Accounts will
be brought back to the Committee at its meeting on 30 September 2025 for approval. 
The Committee decided: that the Unaudited Annual Accounts of the Council and
related Charitable Trusts, to be submitted to Audit Scotland
by the deadline of 30 June 2025, be noted. 
[Reference:  Minutes of 25 June 2024 (Paragraph 5)] 
6 Internal Audit Activity as at 30 May 2025 
A report dated 3 June 2025 by the Executive Director (Finance and Corporate Resources) was
submitted on work completed by Internal Audit during the period 12 April to 30 May 2025. 
Findings from internal audit assignments were reported to this Committee throughout the year,
and the last progress report was considered by the Committee on 6 May 2025.  Information was
provided for the Internal Audit work completed during the period from 12 April to 30 May 2025.   
As at 30 April 2025, 52 of the 54 assignments within the 2024/2025 Audit Plan had reached at
least the draft report stage. Two assignments, both relating to investigative work, remained in
progress.  The assignments completed in the period from 12 April to 30 May 2025, together with
a summary of overall assurances, were detailed in Appendix 1 to the report.  Key performance
indicators for the period to 31 March 2025 were provided in Appendix 2 to the report. 
The Internal Audit function within the Council would continue to comply with the Public Sector
Internal Audit Standards (PSIAS) in the delivery of the Internal Audit Plan 2024/2025.  The new
Global Internal Audit Standards (GIAS) would apply from 1 April 2025, and future activity reports
to the Committee would reflect the requirements of those new standards. 
Updates were also provided on:- 
 progress against the Audit Strategy, which continued to be monitored and reported to the
Committee as part of regular monitoring reports 
 a Position Statement on Sustainability, highlighting challenges and actions related to the
Council’s zero emissions targets and the Local Heat and Energy Efficiency Strategy
(LHEES), as detailed in Appendix 3 
The Committee decided: that progress on Internal Audit activity be noted. 
[Reference:  Minutes of 6 May 2025 (Paragraph 3)] 
7 2024 National Fraud Initiative Exercise 
A report dated 2 June 2025 by the Executive Director (Finance and Corporate Resources) was
submitted on the matches resulting from the 2024 National Fraud (NFI) exercise and of the
proposed number of investigations to be undertaken in 2024/2025.
8

Page 9

The NFI matched similar data across public sector systems and identified possible
inconsistencies. Those inconsistencies, known as matches, required to be investigated by
participating public bodies to detect fraud.  The Council had taken part in NFI exercises since
2004/2005.  Those exercises were undertaken every 2 years and included data from benefits,
payroll, creditors and blue badge holders.  This data was matched to other benefits and payroll
data, as well as to the Department for Work and Pensions’ (DWP) deceased persons’ records
and the electoral register, along with a match of the electoral register to council tax records, to
detect where a single person discount (SPD) had been claimed despite there being more than
one person over 18 in the household. There were 9 separate match areas covered in the 2024
NFI exercise, including:- 
 housing benefits  blue badge holders
 Council Tax Reduction Scheme
 payroll
 housing tenants
 waiting lists
 procurement
 creditors
 Council tax SPD 
The 2024 NFI results were detailed at section 4 of the report and highlighted that:- 
 at 2 April 2025, a total of 32,675 matches had been identified, which represented an
increase of 4,674 from the 2022 exercise.  
 of those, 2,887 high-risk matches were identified as an initial target for investigation. 
Heads of Service were invited to identify any further matches for inclusion, based on risk
and local knowledge.  
 for the 9 matched areas, 7 categories had a decrease and 2 an increase in matches:-
 the greatest decrease in the number of matches related to creditors, housing tenants
and waiting lists.  In relation to creditor matches, that decrease was, in part, due to
the reduced dataset uploaded, covering only the post-implementation period of
Oracle Fusion
 the greatest increase in matches was within the SPD as a result of 2 new match
reports, as detailed in paragraph 4.7 of the report
 councils were still awaiting the release of further matches for 2024, including Small
Business Bonus Scheme (SBBS) and HMRC matches.  Upon receipt of those, analysis
would be undertaken and, where required, target numbers would be increased
 the Housing Benefit Fraud team had transferred to the DWP Fraud and Error Service
(FES), although initial NFI investigations were undertaken by the Council.  If this indicated
a potential benefit fraud, the case was passed to FES.  Matches were closed on the NFI
website as “passed to DWP”
 a deadline for investigations of 31 December 2025 had been proposed; however, it was
anticipated that most would be completed ahead of that date 
The following information was provided in appendices 1 to 3 to the report, respectively:- 
 a list of the matched areas in the 2024 exercise
 a comparison of 2022 and 2024 NFI exercises 
 a breakdown of the 2,887 initial target investigations and deadlines 
In February 2025, the NFI published its strategy for 2024 to 2028.  The aim of the strategy,
which was attached at Appendix 4 to the report, was to commit to, and set out, the NFI’s agenda
for the next 4 years.  The 2024 to 2028 NFI Strategy set out a vision to ‘better detect and
prevent fraud by utilising data and technology from the public and private sector’ and included
the following 5 objectives to achieve that vision:- 
 evolving products through innovation 
 increasing data access and insights
 upholding the highest standards of service quality and data security
9

Page 10

 improving training and support
 enhancing engagement to maximise outcomes 
The Audit and Compliance Manager responded to a member’s question in relation to the risk-
based approach used to identify the target number of high-risk matches that would be
investigated. 
The Committee decided: 
(1) that the results of the matching exercise and the initial target number of investigations
resulting from the 2024 National Fraud Initiative (NFI) exercise be noted; and 
(2) that the 2024 to 2028 NFI Strategy, and associated 5 objectives, be noted. 
[Reference:  Minutes of 27 June 2023 (Paragraph 7) and 24 September 2024 (Paragraph 5)] 
8 Forward Programme for Future Meetings 
A report dated 20 May 2025 by the Executive Director (Finance and Corporate Resources) was
submitted on the outline forward programme for the meetings of the Risk and Audit Scrutiny
Committee to 25 August 2026. 
As part of future arrangements, members were invited to suggest topics for inclusion in the
Committee’s forward programme. 
The Committee decided: that the outline forward programme for the meetings of the
Risk and Audit Scrutiny Committee to 25 August 2026 be
noted. 
[Reference:  Minutes 6 May 2025 (Paragraph 6)] 
9 Urgent Business 
There were no items of urgent business. 
10

Page 11

102 West Port
Edinburgh 
EH3 9DN
8 Nelson Mandela Place
Glasgow 
G2 1BT
The Green House
Beechwood Business Park North
Inverness
IV2 3BL
T: 0131 625 1500
E: info@audit-scotland.gov.uk
www.audit-scotland.gov.uk 
Risk and Audit Scrutiny Committee
30 September 2025
South Lanarkshire Council
Audit of 2024/25 annual accounts 
Independent auditor's report
1.  Our audit work on the 2024/25 annual accounts is now substantially complete. Subject to
receipt of a revised set of annual accounts for final review, we anticipate being able to issue
unmodified audit opinions in the independent auditor's report on 30 September 2025 (the
proposed report is attached at Appendix A).
Annual Audit Report
2.  Under International Standards on Auditing in the UK, we report specific matters arising from
the audit of the annual accounts to those charged with governance of a body in sufficient time to
enable appropriate action. For South Lanarkshire Council, those charged with governance is the
Risk and Audit Scrutiny Committee. We present for the committee’s consideration our proposed
Annual Audit Report on the 2024/25 audit. The section headed "Significant findings and key
audit matters" sets out the issues identified in respect of the annual accounts, including those
that we are required to report to you.
3.  The Annual Audit Report also sets out conclusions on the wider scope areas that frame
public audit as set out in the Code of Audit Practice.
4.  The Annual Audit Report will be issued in final form after the audit of the annual accounts has
been completed.
Unadjusted misstatements
5.  We also report to those charged with governance all uncorrected misstatements in the
annual accounts which we have identified during the course of our audit, other than those of a
trivial nature, and request that these misstatements be corrected.
6.  There is one unadjusted misstatement of £3.849 million in relation to peppercorn leases, as
detailed within Appendix 2 within our Annual Audit Report.
Other ISA (UK) matters
7.  In presenting this letter and the Annual Audit Report to the Risk and Audit Scrutiny
Committee, we seek confirmation from those charged with governance on the following matters: 
• if they are aware of any instances of actual, suspected, or alleged fraud, 
3a
11

Page 12

• if they are aware of any subsequent events that have occurred since the date of the
financial statements,
• if they are content that the methods, assumptions, and data used in making accounting
estimates in the annual accounts are appropriate, 
• if all related party relationships and transactions they are aware of are reflected in the
annual accounts, and
• if they are aware of any non-compliance with laws and regulations. 
8.  Any issues that we have identified from our audit in relation to other ISA (UK) matters that we
are required to report to those charged with governance have been reported in the section
headed “Other matters to report” in the Annual Audit Report.
Representations from Section 95 Officer
9.  As part of the completion of our audit, we are seeking written representations from the
Executive Director (Finance and Corporate Resources) as Section 95 Officer on aspects of the
annual accounts, including the judgements and estimates made.
10.  A draft letter of representation is attached at Appendix B. This should be signed and
returned to us by the Section 95 Officer with the signed annual accounts prior to the
independent auditor’s report being signed.
Outstanding matters
11.   At the time of issuing our proposed Annual Audit Report supporting audit evidence
expenditure sampling remained outstanding. 
12

Page 13

Appendix A:  Proposed Independent Auditor’s Report
Independent auditor’s report to the members of South Lanarkshire
Council and the Accounts Commission
Reporting on the audit of the financial statements
Opinion on financial statements
I certify that I have audited the financial statements in the annual accounts of South Lanarkshire
Council and its group for the year ended 31 March 2025 under Part VII of the Local Government
(Scotland) Act 1973. The financial statements comprise the group and Council only
Comprehensive Income and Expenditure Statement, the group and Council only Balance
Sheets, the group and Council only Movement in Reserves Statements, the group and Council
only Cash-Flow Statements, the Housing Revenue Account Income and Expenditure
Statement, the National Non-Domestic Rates Income and Expenditure Statement, the Council
Tax Income and Expenditure Statement and notes to the financial statements, including
Accounting Policies. The financial reporting framework that has been applied in their
preparation is applicable law and UK adopted international accounting standards, as interpreted
and adapted by the Code of Practice on Local Authority Accounting in the United Kingdom
2024/25 (the 2024/25 Code).
In my opinion the accompanying financial statements:
• give a true and fair view of the state of affairs of the council and its
group as at 31 March 2025 and of the income and expenditure of the
council and its group for the year then ended;
• have been properly prepared in accordance with UK adopted
international accounting standards, as interpreted and adapted by the
2024/25 Code; and
• have been prepared in accordance with the requirements of the Local
Government (Scotland) Act 1973, The Local Authority Accounts
(Scotland) Regulations 2014, and the Local Government in Scotland
Act 2003. 
Basis for opinion
I conducted my audit in accordance with applicable law and International Standards on Auditing
(UK) (ISAs (UK)), as required by the Code of Audit Practice approved by the Accounts
Commission for Scotland. My responsibilities under those standards are further described in the
auditor’s responsibilities for the audit of the financial statements section of my report. I was
appointed by the Accounts Commission on 2 December 2022. My period of appointment is five
years, covering 2022/23 to 2026/27. I am independent of the council and its group in
accordance with the ethical requirements that are relevant to my audit of the financial
statements in the UK including the Financial Reporting Council’s Ethical Standard, and I have
fulfilled my other ethical responsibilities in accordance with these requirements. Non-audit
services prohibited by the Ethical Standard were not provided to the council. I believe that the
audit evidence I have obtained is sufficient and appropriate to provide a basis for my opinion.
Conclusions relating to going concern basis of accounting
I have concluded that the use of the going concern basis of accounting in the preparation of the
financial statements is appropriate.
13

Page 14

Based on the work I have performed, I have not identified any material uncertainties relating to
events or conditions that, individually or collectively, may cast significant doubt on the ability of
the council and its group to continue to adopt the going concern basis of accounting for a period
of at least twelve months from when the financial statements are authorised for issue.
These conclusions are not intended to, nor do they, provide assurance on the current or future
financial sustainability of the council and its group. However, I report on the council’s
arrangements for financial sustainability in a separate Annual Audit Report available from the
Audit Scotland website.
Risks of material misstatement
I report in my Annual Audit Report the most significant assessed risks of material misstatement
that I identified and my judgements thereon.
Responsibilities of Executive Director (Finance and Corporate Resources) and Risk and
Audit Scrutiny Committee for the financial statements
As explained more fully in the Statement of Responsibilities, the Executive Director (Finance
and Corporate Resources) is responsible for the preparation of financial statements that give a
true and fair view in accordance with the financial reporting framework, and for such internal
control as the Executive Director (Finance and Corporate Resources) determines is necessary
to enable the preparation of financial statements that are free from material misstatement,
whether due to fraud or error.
In preparing the financial statements, the Executive Director (Finance and Corporate
Resources) is responsible for assessing the ability of the council and its group to continue as a
going concern, disclosing, as applicable, matters related to going concern and using the going
concern basis of accounting unless there is an intention to discontinue the operations of the
council and its group.
The Risk and Audit Scrutiny Committee is responsible for overseeing the financial reporting
process.
Auditor’s responsibilities for the audit of the financial statements
My objectives are to obtain reasonable assurance about whether the financial statements as a
whole are free from material misstatement, whether due to fraud or error, and to issue an
auditor’s report that includes my opinion. Reasonable assurance is a high level of assurance,
but is not a guarantee that an audit conducted in accordance with ISAs (UK) will always detect a
material misstatement when it exists. Misstatements can arise from fraud or error and are
considered material if, individually or in the aggregate, they could reasonably be expected to
influence the decisions of users taken on the basis of these financial statements.
Irregularities, including fraud, are instances of non-compliance with laws and regulations. I
design procedures in line with my responsibilities outlined above to detect material
misstatements in respect of irregularities, including fraud. Procedures include:
• using my understanding of the local government sector to identify that
the Local Government (Scotland) Act 1973, The Local Authority
Accounts (Scotland) Regulations 2014, and the Local Government in
Scotland Act 2003 are significant in the context of the council and its
group;
14

Page 15

• inquiring of the Executive Director (Finance and Corporate Resources)
as to other laws or regulations that may be expected to have a
fundamental effect on the operations of the council and its group;
• inquiring of the Executive Director (Finance and Corporate Resources)
concerning the policies and procedures of the councils and its group
regarding compliance with the applicable legal and regulatory
framework;
• discussions among my audit team on the susceptibility of the financial
statements to material misstatement, including how fraud might occur;
and
• considering whether the audit team collectively has the appropriate
competence and capabilities to identify or recognise non-compliance
with laws and regulations.
The extent to which my procedures are capable of detecting irregularities, including fraud, is
affected by the inherent difficulty in detecting irregularities, the effectiveness of the council’s
controls, and the nature, timing and extent of the audit procedures performed.
Irregularities that result from fraud are inherently more difficult to detect than irregularities that
result from error as fraud may involve collusion, intentional omissions, misrepresentations, or
the override of internal control. The capability of the audit to detect fraud and other irregularities
depends on factors such as the skilfulness of the perpetrator, the frequency and extent of
manipulation, the degree of collusion involved, the relative size of individual amounts
manipulated, and the seniority of those individuals involved.
A further description of the auditor’s responsibilities for the audit of the financial statements is
located on the Financial Reporting Council's website www.frc.org.uk/auditorsresponsibilities.
This description forms part of my auditor’s report.
Reporting on other requirements
Opinion prescribed by the Accounts Commission on the audited parts of the
Remuneration Report
I have audited the parts of the Remuneration Report described as audited. In my opinion, the
audited parts of the Remuneration Report have been properly prepared in accordance with The
Local Authority Accounts (Scotland) Regulations 2014.
Other information 
The Executive Director (Finance and Corporate Resources) is responsible for the other
information in the annual accounts. The other information comprises the Management
Commentary, Annual Governance Statement, Statement of Responsibilities and the unaudited
parts of the Remuneration Report.
My responsibility is to read all the other information and, in doing so, consider whether the other
information is materially inconsistent with the financial statements or my knowledge obtained in
the course of the audit or otherwise appears to be materially misstated. If I identify such material
inconsistencies or apparent material misstatements, I am required to determine whether this
gives rise to a material misstatement in the financial statements themselves. If, based on the
work I have performed, I conclude that there is a material misstatement of this other information,
I am required to report that fact. I have nothing to report in this regard.
15

Page 16

My opinion on the financial statements does not cover the other information and I do not
express any form of assurance conclusion thereon except on the Management Commentary
and Annual Governance Statement to the extent explicitly stated in the following opinions
prescribed by the Accounts Commission.
Opinions prescribed by the Accounts Commission on the Management Commentary and
Annual Governance Statement
In my opinion, based on the work undertaken in the course of the audit:
• the information given in the Management Commentary for the financial
year for which the financial statements are prepared is consistent with
the financial statements and that report has been prepared in
accordance with statutory guidance issued under the Local Government
in Scotland Act 2003; and
• the information given in the Annual Governance Statement for the
financial year for which the financial statements are prepared is
consistent with the financial statements and that report has been
prepared in accordance with the Delivering Good Governance in Local
Government: Framework (2016).
Matters on which I am required to report by exception
I am required by the Accounts Commission to report to you if, in my opinion:
• adequate accounting records have not been kept; or
• the financial statements and the audited parts of the Remuneration
Report are not in agreement with the accounting records; or
• I have not received all the information and explanations I require for my
audit.
I have nothing to report in respect of these matters.
Conclusions on wider scope responsibilities
In addition to my responsibilities for the annual accounts, my conclusions on the wider scope
responsibilities specified in the Code of Audit Practice, including those in respect of Best Value,
are set out in my Annual Audit Report.
Use of my report
This report is made solely to the parties to whom it is addressed in accordance with Part VII of
the Local Government (Scotland) Act 1973 and for no other purpose. In accordance with
paragraph 108 of the Code of Audit Practice, I do not undertake to have responsibilities to
members or officers, in their individual capacities, or to third parties. 
John Boyd FCPFA
Audit Scotland
4th Floor
South Suite
16

Page 17

The Athenaeum Building
8 Nelson Mandela Place
Glasgow
G2 1BT  
17

Page 18

Appendix B:  Letter of Representation (ISA 580)
Mr John Boyd, Audit Director
Audit Scotland
4th Floor
8 Nelson Mandela Place
Glasgow 
G2 1BT
Dear John
South Lanarkshire Council
Annual Accounts 2024/25
1.  This representation letter is provided in connection with your audit of the annual accounts of
South Lanarkshire Council and its group (hereafter referred to as the council ) for the year
ended 31 March 2025 for the purpose of expressing an opinion as to whether the financial
statements give a true and fair view and have been properly prepared, and for expressing other
opinions on the Remuneration Report, Management Commentary, and Annual Governance
Statement.
2.  I confirm to the best of my knowledge and belief and having made appropriate enquiries of
the Chief Executive and Corporate Management Team, the following representations given to
you in connection with your audit of South Lanarkshire Council’s annual accounts for the year
ended 31 March 2025.
General
3.  The council and I have fulfilled our statutory responsibilities for the preparation of the 2024/25
annual accounts. All the accounting records, documentation, and other matters which I am
aware are relevant to the preparation of the annual accounts have been made available to you
for the purposes of your audit. All transactions undertaken by the council have been recorded in
the accounting records and are properly reflected in the financial statements.
4.  I confirm that the effects of uncorrected misstatements are immaterial, individually and in
aggregate, to the financial statements as a whole. I am not aware of any uncorrected
misstatements other than those reported by you.
Financial Reporting Framework
5.  The annual accounts have been prepared in accordance with the Code of Practice on Local
Authority Accounting in the United Kingdom 2024/25 (2024/25 accounting code), and the
requirements of the Local Government (Scotland) Act 1973, the Local Government in Scotland
Act 2003, and the Local Authority Accounts (Scotland) Regulations 2014.
6.  In accordance with the Local Authority Accounts (Scotland) Regulations 2014, I have ensured
that the financial statements give a true and fair view of the financial position of the council and
its Group at 31 March 2025 and the transactions for 2024/25. 
Accounting Policies and Estimates
7.  All material accounting policies applied are as shown in the notes to the financial statements.
The accounting policies are determined by the 2024/25 Code, where applicable. Where the
2024/25 Code does not specifically apply, I have used judgement in developing and applying an
18

Page 19

accounting policy that results in information that is relevant and reliable. All accounting policies
applied are appropriate to the council’s circumstances and have been consistently applied.
8.  The methodology, significant assumptions, and data used in making accounting estimates
are reasonable, and have been properly reflected and disclosed in the financial statements in
accordance with the 2024/25 Code. Judgements made in making estimates have been based
on the latest available and reliable information. Estimates have been revised where there are
changes in the circumstances on which the original estimate was based or as a result of new
information or experience.
Going Concern Basis of Accounting
9.  I have assessed the council’s ability to continue to use the going concern basis of accounting
and have concluded that it is appropriate. I am not aware of any material uncertainties that may
cast significant doubt on the council’s ability to continue to adopt the going concern basis of
accounting. 
Assets
10.  All assets at 31 March 2025 of which I am aware have been reported in the financial
statements. 
11.  Where a rolling programme of asset valuations has been used, I have satisfied myself that
the carrying amount of assets at 31 March 2025 does not differ materially from that which would
be determined if a revaluation had been carried out at that date.
12.  I carried out an assessment at 31 March 2025 as to whether there is any indication that an
asset may be impaired and have recognised any impairment losses identified in the financial
statements.
13.  I have provided you with all information of which I am aware regarding any valuation
exercises carried out after 31 March 2025. 
14.  There are no plans or intentions that are likely to affect the carrying value or classification of
the assets recognised in the financial statements.
15.  Owned assets are free from any lien, encumbrance, or charge, except as disclosed in the
financial statements. 
16.  The pension assumptions made by the actuary in the IAS 19 report for the council have
been reviewed and I confirm that they are consistent with management's own view. The pension
asset has been capped to reflect the asset ceiling as determined through IFRIC 14. I am
satisfied that the assumptions applied in the calculation are consistent with management’s own
view.
Liabilities
17.  All liabilities at 31 March 2025 of which I am aware have been reported in the financial
statements. 
18.  Provisions have been recognised in the financial statements for all liabilities of uncertain
timing or amount at 31 March 2025 of which I am aware where the conditions specified in IAS
37, as adapted by the 2024/25 Code, have been met. The amount recognised as a provision is
the best estimate of the expenditure likely to be required to settle the obligation at 31 March
2025. Where the effect of the time value of money is material, the amount of the provision has
been discounted to the present value of the expected payments. 
19

Page 20

19.  Provisions recognised in previous years have been reviewed and adjusted, where
appropriate, to reflect the best estimate at 31 March 2025, or to reflect material changes in the
assumptions underlying the calculations of the provisions.
20.  The accrual recognised in the financial statements for annual leave untaken by 31 March
2025 has been estimated on a reasonable basis.
21.  There are no plans or intentions that are likely to affect the carrying value or classification of
the liabilities recognised in the financial statements.
Contingent Liabilities
22.  There are no significant contingent liabilities, other than those disclosed in Note 31 to the
financial statements, arising either under formal agreement or through formal undertakings
requiring disclosure in the accounts. All known contingent liabilities have been fully and properly
disclosed in accordance with the 2024/25 accounting code and IAS 37.
Litigation and Claims
23.  All known actual or possible legal claims have been disclosed to you and have been
accounted for and disclosed in the financial statements in accordance with the 2024/25
accounting code. 
Fraud
24.  I understand my responsibilities for the design, implementation, and maintenance of internal
control to prevent fraud and I believe I have appropriately fulfilled those responsibilities. 
25.  I have provided you with all information in relation to:
• my assessment of the risk that the financial statements may be materially misstated
because of fraud 
• any allegations of fraud or suspected fraud affecting the financial statements, and
• fraud or suspected fraud that I am aware of involving management, employees who
have a significant role in internal control, or others that could have a material effect on
the financial statements. 
Laws and Regulations
26.  I have disclosed to you all known instances of non-compliance or suspected non-
compliance with laws and regulations whose effects should be considered when preparing
financial statements.
Related Party Transactions
27.  All material transactions with related parties have been appropriately accounted for and
disclosed in the financial statements in accordance with IAS 24, as adopted by the 2024/25
Code. I have made available to you the identity of all the council’s related parties and all the
related party relationships and transactions of which I am aware.
Remuneration Report
28.  The Remuneration Report has been prepared in accordance with the Local Authority
Accounts (Scotland) Regulations 2014, and all required information of which I am aware has
been provided to you.
20

Page 21

Management Commentary
29.  I confirm that the Management Commentary has been prepared in accordance with the
statutory guidance and the information is consistent with the financial statements. 
Corporate Governance
30.  I confirm that the council has undertaken a review of the system of internal control during
2024/25 to establish the extent to which it complies with proper practices set out in Delivering
Good Governance in Local Government: Framework 2016. I have disclosed to you all
deficiencies in internal control identified from this review or of which I am otherwise aware.
31.  I confirm that the Annual Governance Statement has been prepared in accordance with the
Delivering Good Governance in Local Government: Framework 2016 and the information is
consistent with the financial statements. There have been no changes in the corporate
governance arrangements, or issues identified, since 31 March 2025 which require to be
reflected in the Annual Governance Statement or annual accounts. 
Group Accounts
32.  I have identified all the other entities in which the council has an interest and have classified
and accounted for them in accordance with the 2024/25 Code. Any significant issues, including
those related to fraud and any qualified audit opinions, in relation to the financial statements of
group entities, have been provided to you.
Common Good Fund
33.  I confirm, to the best of my ability, that all material common good assets have been
identified and correctly accounted for within the common good fund financial statements and
where appropriate, common good assets in use by the council have been assessed and
accounted for in line with IAS 17. 
Events Subsequent to the Date of the Balance Sheet
34.  All events subsequent to 31 March 2025 for which IAS 10, as adopted by the 2024/25
Code, requires adjustment or disclosure have been adjusted or disclosed. 
Yours sincerely 
Executive Director (Finance and Corporate Resources)
Section 95 Officer
21

Page 22

South Lanarkshire
Council
2024/25 Annual Audit Report Proposed 
Prepared for South Lanarkshire Council and the Controller of Audit 
September 2025
22

Page 23

South Lanarkshire Council: 2024/25 Annual Audit Report Proposed | 2 
Contents 
Key messages 3
Introduction 5
Audit scope and responsibilities 6
Audit of the annual accounts 8
Wider scope audit 22
Best Value audit 36
Appendix 1 43
Appendix 2 53
Appendix 3 54 
Accessibility
You can find out more and read this report using assistive technology on
our website www.audit.scot/accessibility.
23

Page 24

Key messages | 3 
Key messages 
Audit of the annual accounts
1 All audit opinions state that the annual accounts of South Lanarkshire
Council, its group and the section 106 charities administered by the council
were free from material misstatement for the year ended 31 March 2025.
2 The management commentary, annual governance statement and
remuneration report were all consistent with the financial statements and
properly prepared in accordance with the relevant regulations and guidance.
Wider scope audit
3 The council continues to operate within its annual budget. While facing
financial challenges through inflationary pressures on pay and non-pay costs
as well as demand on services, the council continues to demonstrate sound
financial management maintaining general fund reserves in line with the long-
term Revenue Financial Strategy.
4 The council implemented a new financial system at the start of the 2024/25,
Oracle’s cloud-based Human Resources (HR) and Finance solution. This was
a significant change programme with a focus on delivering significant
improvements to processes, workflow, support agile working, employee self-
service and engagement as well as greater levels of automation and
improved management information.
5 The council’s revenue budget strategy has reported a projected budget
surplus for 2025/26 however there remains a budget gap over the medium
term. The council continues to undertake scenario planning and
transformation reviews to support medium and long term financial plans.
6 The council has effective budget monitoring arrangements. Given the
financial pressures, the council is continuing to assess its reserves strategy
and review how it assesses, monitors and reports on its financial resilience.
7 The council has sound governance arrangements in place for how it conducts
business. To ensure the Risk and Audit Scrutiny Committee is effective in its
24

Page 25

Key messages | 4 
role an annual review and assessment should be undertaken with the results
captured within an annual report.
Best Value audit 
8 The council has a Transformational Change Programme in place that is
clearly linked to its updated Council Plan, financial plans and digital strategy.
9 The council currently focuses on establishing the financial benefits of its
transformational activities but does not routinely separately track or report on
the impact on service quality or outcomes for service users in relation to
these transformational activities.
10 The council has effective and appropriate arrangements in place for securing
Best Value.
11 Audit work assessed the arrangements the council has in place for preparing
and publishing SPI, including how it has responded to assessments, and
concluded the arrangements in place were effective and appropriate.
12 The council has an effective performance management framework in place.
13 The council reviews and reports its performance using a number of measures
that are clearly aligned to the priorities and outcomes set out in the Council
Plan.
14 The council has an improvement action plan for all indicators, including those
reported as being below the Scottish average. 
25

Page 26

Introduction | 5 
Introduction 
Purpose of the Annual Audit Report
1.  The purpose of this Annual Audit Report is to report the significant
matters identified from the 2024/25 audit of South Lanarkshire Council’s
annual accounts and the wider scope areas specified in the Code of Audit
Practice (2021).
2.  The Annual Audit Report is addressed to South Lanarkshire Council,
hereafter referred to as ‘the council’ and the Controller of Audit, and will be
published on Audit Scotland’s website in due course.
Appointed auditor and independence
3.  John Boyd, of Audit Scotland, has been appointed as external auditor of
the council for the period from 2022/23 until 2026/27. As reported in the
Annual Audit Plan, John Boyd and the audit team are independent of the
council and its group in accordance with relevant ethical requirements,
including the Financial Reporting Council’s Ethical Standard. There have
been no developments since the issue of the Annual Audit Plan that
impact on the continued independence of the engagement lead or the rest
of the audit team from the council, including no provision of non-audit
services.
Acknowledgements
4.  We would like to thank the council and its staff, particularly those
involved in preparation of the annual accounts, for their cooperation and
assistance during the audit. We look forward to working together
constructively over the remainder of the five-year audit appointment.
26

Page 27

Audit scope and responsibilities | 6 
Audit scope and responsibilities 
Scope of the audit 
5.  The audit is performed in accordance with the Code of Audit Practice,
including supplementary guidance, International Standards on Auditing
(ISA) (UK), and relevant legislation. These set out the requirements for the
scope of the audit which includes:
• An audit of the financial statements and an opinion on whether they
give a true and fair view and are free from material misstatement.
• An opinion on statutory other information published with the financial
statements in the annual accounts, the Management Commentary,
and the Annual Governance Statement, and an opinion on the
audited part of the Remuneration Report.
• Conclusions on the council’s arrangements in relation to the wider
scope areas: Financial Management; Financial Sustainability; Vision,
Leadership and Governance; and Use of Resources to Improve
Outcomes.
• Reporting on the council’s arrangements for securing Best Value.
• Providing assurance on the Housing Benefit Subsidy Claim, Non-
Domestic Rates Return, Whole of Government Accounts return, and
summary financial statements.
• A review of the council’s arrangements for preparing and publishing
statutory performance information.
• Provision of this Annual Audit Report.
Responsibilities and reporting
6.  The Code of Audit Practice sets out the respective responsibilities of the
council and the auditor. A summary of the key responsibilities is outlined
below.
Auditor’s responsibilities
7.  The responsibilities of auditors in the public sector are established in
the Local Government (Scotland) Act 1973. These include providing an
independent opinion on the financial statements and other information
reported within the annual accounts, and concluding on the South
Lanarkshire Council’s arrangements in place for the wider scope areas
and Best Value.
27

Page 28

Audit scope and responsibilities | 7 
8.  The matters reported in the Annual Audit Report are only those that
have been identified by the audit team during normal audit work and may
not be all that exist. Communicating these does not absolve the council
from its responsibilities outlined below.
9.  The Annual Audit Report includes an agreed action plan at Appendix 1
setting out specific recommendations to address matters identified and
includes details of the responsible officer and dates for implementation.
The council’s responsibilities
10.  The council has primary responsibility for ensuring proper financial
stewardship of public funds, compliance with relevant legislation and
establishing effective arrangements for governance, propriety, and
regularity that enables it to successfully deliver its objectives. The features
of proper financial stewardship include:
• Establishing arrangements to ensure the proper conduct of its affairs.
• Preparation of annual accounts, comprising financial statements for
the council and its group that gives a true and fair view and other
specified information.
• Establishing arrangements for the prevention and detection of fraud,
error and irregularities, and bribery and corruption.
• Implementing arrangements to ensure its financial position is soundly
based.
• Making arrangements to secure Best Value.
• Establishing an internal audit function.
National performance audit reporting
11.  The Auditor General for Scotland and the Accounts Commission
regularly publish performance audit reports. These cover a range of
matters, many of which may be of interest to the council and the Risk,
Audit and Scrutiny Committee. Details of national and performance audit
reports published over the last year can be seen in Appendix 3.
28

Page 29

Audit of the annual accounts | 8 
Audit of the annual accounts 
Main judgements
Our audit opinions on the annual accounts of South Lanarkshire
Council, its group and the section 106 charities administered by the
council are unmodified, i.e. the financial statements and related reports
are free from material misstatement.
The management commentary, annual governance statement and
remuneration report were all consistent with the financial statements and
properly prepared in accordance with the relevant regulations and
guidance.
Close down procedures should be reviewed by finance to ensure
supporting working papers are available in line with the year-end
timetable.
Audit opinions on the annual accounts are free from
material misstatement
12.  The council approved the annual accounts for South Lanarkshire
Council and its group for the year ended 31 March 2025 by the Risk and
Audit Scrutiny Committee on 30 September 2025. In addition to the
council the group accounts consolidate the financial results of the council
and its subsidiaries and its investments in associates and interests in joint
ventures. These include: Strathclyde Partnership for Transport, Strathclyde
Concessionary Travel Scheme Joint Committee, Lanarkshire Valuation
Joint Board, South Lanarkshire Integration Joint Board, South Lanarkshire
Leisure and Culture Limited, Routes to Work South, Clyde Valley Learning
and Development Joint Committee and the Common Good Fund.
13.  The Independent Auditor’s Report is included in the council’s annual
accounts, and this reports that, in the appointed auditor’s opinion, these
were free from material misstatement. 
Close down procedures should be reviewed to by finance
to ensure supporting working papers are available in line
with the year-end timetable
14.  The unaudited annual accounts were received on 26 June 2025 and in
accordance with the agreed audit timetable. We received good support
29

Page 30

Audit of the annual accounts | 9 
during the course of the financial audit from the core finance team. There
were delays in the provision of a number of underlying working papers to
the audit team to support the financial statements, which was outwith the
control of the core finance team.
15.  Finance Strategy issue a year end timetable to relevant officers across
the council containing year end guidance procedures and timetables for
completion of tasks and submission of information for the preparation of
the draft annual report and accounts. Section A6 states "It is essential that
adequate working papers are available as soon as the Accounts are
presented for audit."
Recommendation 1
Staff should be reminded of the year end timetable and the importance that working papers for
external audit are provided to the Finance Strategy Team in line with the year-end timetable
deadlines to ensure these are available with the unaudited accounts.
Audit Fee
16.  The audit fee for the 2024/25 audit was reported in the Annual Audit
Plan and was set at £633,450. There have been no developments that
impact on planned audit work required, therefore the audit fee reported in
the Annual Audit Plan remains unchanged. 
Materiality
17.  The concept of materiality is applied by auditors in planning and
performing an audit, and in evaluating the effect of any uncorrected
misstatements on the financial statements or other information reported in
the annual accounts.
18.  Broadly, the concept of materiality is to determine whether
misstatements identified during the audit could reasonably be expected to
influence the decisions of users of the annual accounts. Auditors set a
monetary threshold when determining materiality, although some issues
may be considered material by their nature. Therefore, materiality is
ultimately a matter of the auditor’s professional judgement.
19.  Materiality levels for the audit of the council and its group were
determined at the risk assessment phase of the audit and were reported in
the Annual Audit Plan, which also reported the judgements made in
determining materiality levels. These were reassessed on receipt of the
unaudited annual accounts and summarised in Exhibit 1.
30

Page 31

Audit of the annual accounts | 10 
Exhibit 1
2024/25 Materiality levels for South Lanarkshire Council and its group
Materiality The council Group
Materiality – set at 2 per cent of gross expenditure £27.145 million £27.500 million
Performance materiality – set at 75 per cent of
materiality. As outlined in the Annual Audit Plan, this
acts as a trigger point. If the aggregate of
misstatements identified during the audit exceeds
performance materiality, this could indicate further audit
procedures are required. 
£20.350 million £20.600 million
Reporting threshold – set at 5 per cent of materiality.  £1.350 million £1.370 million
Source: Audit Scotland
Significant findings and key audit matters 
20.  ISA (UK) 260 requires auditors to communicate significant findings
from the audit to those charged as governance, which for the council is the
Risk, Audit and Scrutiny Committee.
21.  The Code of Audit Practice also requires public sector auditors to
communicate key audit matters. These are the matters that, in the
auditor’s professional judgement, are of most significance to the audit of
the financial statements and require most attention when performing
the audit. 
22.  In determining key audit matters, auditors consider:
• Areas of higher or significant risk of material misstatement.
• Areas where significant judgement is required, including accounting
estimates that are subject to a high degree of estimation uncertainty.
• Significant events or transactions that occurred during the year.
23.  The significant findings and key audit matters to report are outlined in
Exhibit 2. 
31

Page 32

Audit of the annual accounts | 11 
Exhibit 2 
Significant findings and key audit matters
Significant findings and key audit matters Outcome
1. IFRS 16 - Leases
Effective from 1 April 2024, IFRS 16 requires
Local Authorities to recognise a Right of Use
(RoU) asset and corresponding lease liability
for all lease types (property, land, vehicles,
plant, equipment). On transition, leases are
accounted for retrospectively, with the
cumulative impact recognised at 1 April 2024.
Following the implementation of IFRS 16
Leases from 1 April 2024, several required
disclosures were not fully presented in the
unaudited annual accounts including:
• Disclosures required on initial application
of IFRS 16 on 1 April 2024.
• Exemptions applied under IFRS 16 and
the value of these in relation to short-term
and low value leases.
• The value of liabilities resulting from
service concession arrangements at each
Balance Sheet date, and an analysis of
the movement in those values.
• Peppercorn leases were not disclosed in
the unaudited annual accounts. No
monetary values or narrative explanation
were provided, despite their inclusion
under IFRS 16.
The council has now reflected all the required
IFRS 16 disclosures within the revised annual
accounts. 
32

Page 33

Audit of the annual accounts | 12 
Significant findings and key audit matters Outcome
2. Group Accounts: Prior year restatement
The 2023/24 South Lanarkshire Council
group accounts were prepared using the
unaudited South Lanarkshire Leisure and
Culture Limited accounts (SLLC).
The SLLC unaudited accounts disclosed a
net pension asset of £76.959 million (£78.439
million asset for the funded obligations and
£1.480 million liability for unfunded
obligations).
The South Lanarkshire Council annual
accounts were approved on 27 September
2024.
The audited SLLC accounts, were signed on
13 November 2024 and included a late
adjustment, with the application of a pension
asset ceiling of £78.439 million, reducing the
pension asset to nil, resulting in the audited
accounts disclosing a pension liability of
£1.480 million for the unfunded obligation.
The council has updated the annual accounts
to reflect the adjustment as a prior year
restatement.
Source: Audit Scotland
Qualitative aspects of accounting practices 
24.  ISA (UK) 260 also requires auditors to communicate their view about
qualitative aspects of the council’s accounting practices, including
accounting policies, accounting estimates, and disclosures in the financial
statements.
Accounting policies 
25.  The appropriateness of accounting policies adopted by the council
was assessed as part of the audit. These were considered to be
appropriate to the circumstances of the council, and there were no
significant departures from the accounting policies set out in the Code of
Practice on Local Authority Accounting in the United Kingdom (the Code). 
Accounting estimates 
26.  Accounting estimates are used in number of areas in the council’s
financial statements, including the valuation of land and buildings assets
and the valuation of the pension liability. Audit work considered the
process management of the council has in place around making
accounting estimates, including the assumptions and data used in making
the estimates, and the use of any management experts. Audit work
concluded:
33

Page 34

Audit of the annual accounts | 13 
• There were no issues with the selection or application of methods,
assumptions, and data used to make the accounting estimates, and
these were considered to be reasonable. 
• There was no evidence of management bias in making the
accounting estimates.
Disclosures in the financial statements
27.  The adequacy of disclosures in the financial statements was assessed
as part of the audit. The quality of disclosures was adequate, with
additional levels of detail provided for disclosures around areas of greater
sensitivity, such as financial instruments and valuation of the pension
liability.
Group audit
28.  South Lanarkshire Council is part of a group and prepares group
financial statements. The group is made up of nine components, including
South Lanarkshire Council which is the parent of the group.
29.  As outlined in the Annual Audit Plan, audit work was required on a
number of the group’s components for the purposes of the group audit,
and this work was performed by a combination of the audit team and the
components’ audit teams. Group financial audit questionnaires were
issued to component auditors, where required, to outline the expectations
and requirements in performing the audit work for the purposes of the
group audit. The audit work performed on the group’s components is
summarised in Exhibit 3.
Exhibit 3
Summary of audit work on the group’s components
Group component 
Component Auditor and
audit work required
Summary of audit work
performed 
South Lanarkshire
Council
Audit Scotland
Fully scope audit of the
council’s annual accounts. 
Consolidated on a line-by-line
basis. Audit team confirmed
correct accounting treatment. The
outcome of audit work performed
is reported within the Annual Audit
Report, with details of significant
findings and key audit matters
reported in Exhibit 2.
South Lanarkshire
Leisure and Culture
Limited
Azets
Review accounting treatment
Consolidated on a line-by-line
basis. Audit team confirmed
correct accounting treatment.
34

Page 35

Audit of the annual accounts | 14 
Group component 
Component Auditor and
audit work required
Summary of audit work
performed 
Routes to Work South McDaid & Partners
None
Consolidated on a line-by-line
basis. Audit team confirmed
correct accounting treatment.
South Lanarkshire
Integration Joint Board
Audit Scotland
None
Accounted for on equity basis.
Audit team confirmed correct
accounting treatment.
Lanarkshire Valuation
Joint Board
Audit Scotland
None
Accounted for on equity basis.
Audit team confirmed correct
accounting treatment.
Clyde Valley Learning
and Development Joint
Committee
Audit Scotland
None
Accounted for on equity basis.
Audit team confirmed correct
accounting treatment.
Strathclyde
Concessionary Travel
Scheme Joint Committee
Audit Scotland
None
Accounted for on equity basis.
Audit team confirmed correct
accounting treatment.
Strathclyde Partnership
for Transport
Audit Scotland
Issue risk assessment
questionnaire and undertake
analytical procedures.
Accounted for on equity basis.
Audit team confirmed correct
accounting treatment, reviewed
risk assessment questionnaire and
completed analytical procedures.
Common Good Fund Audit Scotland
Review accounting treatment
Consolidated on a line-by-line
basis. Audit team confirmed
correct accounting treatment.
Source: Audit Scotland
Significant matters discussed with management
30.  All significant matters identified during the audit and discussed with the
council’s management have been reported in the Annual Audit Report. 
Audit adjustments
31.  Audit adjustments were required to the financial statements to correct
misstatements that were identified from the audit. Details of all audit
adjustments greater than the reporting threshold of £1.350 million are
outlined in Exhibit 4.
35

Page 36

Audit of the annual accounts | 15 
Exhibit 4
Audit adjustments
Details
Financial
statements
lines impacted
Group
Comprehensive
Income and
Expenditure
Statement (CIES)
Group Balance
Sheet 
Audit adjustments to financial
statements Dr Cr Dr Cr 
£000 £000 £000 £000
1. Component balances omitted in
consolidation    
Cost of services 1,502   
Provision of services 304   
Other comprehensive income  2,766  
Short-Term creditor   346 
2. Component audit adjustments    
Cost of services  700  
Short-term debtors   701 
Short-term creditors   89 
Cash and cash equivalents    90
3. Classification of pension liability    
Other long-term liabilities (PPP/finance
lease)   1,307 
Other long-term liabilities (Pension)    1,307
Total adjustments 1,806 3,466 2,443 1,397
Net impact on financial statements* 1,660   1,046
*The net difference of £614,000 (£1,660 - £1,046) represents the initial difference
between the group primary statements within the unaudited annual accounts which
has been corrected within the audited annual accounts.
36

Page 37

Audit of the annual accounts | 16 
Details
Financial
statements
lines impacted
Group
Comprehensive
Income and
Expenditure
Statement (CIES)
Group Balance
Sheet 
Audit adjustments in disclosures    
1. Adjustments to Note 17 Leases and Note 28 Public Private Partnerships and Similar
Contracts to include IFRS 16 disclosures required by the Code as detailed in Exhibit 2 above.
2. Adjustments to Note 30 Defined Benefit Pension Scheme required to reflect actual fund
investment performance for the year and updated IAS 19 report from the actuary.
Source: Audit Scotland
32.  Management of the council processed audit adjustments for all
misstatements identified greater than the reporting threshold. As a result,
there are no uncorrected misstatement to report. 
33.  In addition to the corrected misstatements outlined in Exhibit 4, there
were other misstatements identified greater than the reporting threshold.
The value, nature, and circumstances of the uncorrected misstatements
were considered, individually and in aggregate, by the audit team, and it
was concluded these were not material to the financial statements. As a
result, these did not have any impact on the audit opinions given in the
Independent Auditor’s Report.
34.  It is the auditor’s responsibility to request that all misstatements
greater than the reporting threshold are corrected, even if they are not
material. Management of the council have not processed any audit
adjustments to correct these misstatements. However, the final decision
on whether an audit adjustment is processed to correct a misstatement
rests with the Risk, Audit and Scrutiny Committee as those charged with
governance. Details of the uncorrected misstatements can be seen in
Appendix 2. 
Significant risks of material misstatement identified in the
Annual Audit Plan
35.  Audit work has been performed in response to the significant risks of
material misstatement identified in the Annual Audit Plan. The outcome of
audit work performed is summarised in Exhibit  5.
37

Page 38

Audit of the annual accounts | 17 
Exhibit 5 
Significant risks of material misstatement to the financial statements
Risk of material
misstatement Planned audit response Outcome of audit work
Fraud caused by
management override of
controls 
Management is in a unique
position to perpetrate fraud
because of management’s
ability to override controls
that otherwise appear to be
operating effectively.
The audit team will:
• Evaluate the design and
implementation of controls
over journal entry processing.
• Make inquiries of individuals
involved in the financial
reporting process about
inappropriate or unusual
activity relating to the
processing of journal entries
and other adjustments.
• Test journals entries,
focusing on those that are
assessed as higher risk. 
• Evaluate significant
transactions outside the
normal course of business.
• Assess the adequacy of
controls in place for
identifying and disclosing
related party relationships
and transactions in the
financial statements. 
• Assess changes to the
methods and underlying
assumptions used to prepare
accounting estimates and
assess these for evidence of
management bias.
Audit work performed found:
• The design and
implementation of
controls over journal
processing were
appropriate. 
• No inappropriate or
unusual activity relating
to the processing of
journal entries was
identified from
discussions with
individuals involved in
financial reporting. 
• No significant issues
were identified from
testing of journal entries. 
• No significant issues
were identified from
transactions outside the
normal course of
business. 
• The controls in place for
identifying and disclosing
related party relationships
and transactions were
adequate. 
• No significant issues
were identified with
changes to methods and
underlying assumptions
used to prepare
accounting estimates and
there was no evidence of
management bias. 
Conclusion: no evidence of
fraud caused by
management override of
controls. 
38

Page 39

Audit of the annual accounts | 18 
Valuation of property,
plant and equipment 
The council held £3,735
million of property, plant,
and equipment (PPE) at
31 March 2024, of which
£3,324 million was land and
building assets. 
South Lanarkshire Council
is required to value land and
building assets at existing
use value where an active
market exists for these
assets. Where there is no
active market, these assets
are valued on a depreciated
cost replacement (DRC)
basis. As a result, there is a
significant degree of
subjectivity in these
valuations which are based
on specialist assumptions,
and changes in the
assumptions can result in
material changes to
valuations.
The audit team will: 
• Evaluate the design and
implementation of controls
over the valuation process. 
• Review the information
provided to the valuer and
assess this for completeness
and accuracy.
• Evaluate the competence,
capabilities, and objectivity of
the valuer.
• Obtain an understanding of
management’s involvement in
the valuation process to
assess if appropriate
oversight has occurred.
• Review the appropriateness
of the key data and
assumptions used in the
2024/25 valuation process,
and challenge these where
required.
• Review management’s
assessment that the value in
the balance sheet of assets
not subject to a valuation
process in 2024/25 is not
materially different to current
value at the year-end, and
challenge this where
required.
• Review LASAAC guidance,
which specified Scottish
authorities should use the
beacon approach
methodology to value council
dwellings, to ensure the
council’s valuation process
complies with applicable
guidance.
Audit work performed found:
• The design and
implementation of
controls over the
valuation process were
appropriate. 
• The information provided
to the valuer was
accurate and complete. 
• The valuer had sufficient
competence, capability,
and objectivity to perform
their work. 
• Management are
involved in the valuation
process and have an
appropriate level of
oversight. 
• The data and
assumptions used in the
2024/25 valuation
process were
appropriate. 
• Management’s
assessment of assets not
subject to a valuation
process in 2024/25 was
reasonable and
concluded there was
unlikely to be a material
difference to the current
value at the year-end.
• The council’s valuation
process complies with
applicable guidance.
Conclusion: The council
adopt a five year rolling
programme for the valuation
of other land and buildings.
The valuation of these
assets for 2024/25 has
taken place as at 1 April
2024. Management should
consider valuing at 31
March to reduce the risk of
adjustments being required
as a result of material
movements in year.
39

Page 40

Audit of the annual accounts | 19 
Risk of material
misstatement Planned audit response Outcome of audit work
Estimation of the pension
liability
South Lanarkshire Council
had a pension liability of
£113.666 million at 31
March 2024.
South Lanarkshire Council
is a member of Strathclyde
LGPS, which is a defined
benefit pension scheme.
Strathclyde LGPS is subject
to formal valuation every
three years, and this sets
out each member’s share of
the scheme’s overall
pension liability and
contributions for the next
three years. The last formal
valuation was carried out at
31 March 2023.
An estimation of South
Lanarkshire Council’s share
of the overall pension
liability is required in each
intervening year between
formal valuations, and these
are carried out by Hymans
Robertson. There is a
significant degree of
subjectivity in the estimation
of the pension liability as the
estimation is based on
specialist assumptions, and
changes in the assumptions
can result in material
changes to the estimation.
The audit team will:
• Evaluate the design and
implementation of controls
over the pension liability
estimation process. 
• Review the information
provided to the actuary and
assess this for completeness
and accuracy.
• Evaluate the competence,
capabilities, and objectivity of
the actuary.
• Obtain an understanding of
the management’s
involvement in the estimation
process to assess if
appropriate oversight has
occurred.
• Review the appropriateness
of the key data and
assumptions used by
management for the
estimation of the pension
liability, and challenge these
where required.
• Audit Scotland uses PwC as
an auditor’s expert to inform
the planned audit procedures
outlined above. Therefore,
the audit team will also
review the information
provided by PwC and reflect
this in the planned audit
procedures where required.
Audit work performed found:
• The design and
implementation of
controls over the pension
liability estimation
process were
appropriate. 
• The information provided
to the actuary was
accurate and complete. 
• The actuary had sufficient
competence, capability,
and objectivity to perform
their work. 
• Management are
involved in the estimation
process and have an
appropriate level of
oversight. 
• The data and
assumptions used in the
estimation process were
appropriate. 
• The information provided
by PwC was reviewed
and this reflected in the
planned audit
procedures, where
required. 
Conclusion: the recognition
of unfunded and funded
elements of the pension
liability, is not materially
misstated. 
Source: Audit Scotland
The council does not undertake valuations as at the year end, but
has provided satisfactory evidence to support its approach
36.  The council’s valuation team (qualified RICs valuers) have confirmed that
they carried out their valuation duties in line with the RICs professional
standards, and they have provided a formal year-end report to management.
This included a covering report, a Service Level Agreement (SLA) outlining their
40

Page 41

Audit of the annual accounts | 20 
conditions of engagement, and an asset review paper (impairment review)
which focussed on identifying any unusual circumstances which would affect
the value of whole categories of assets. They reviewed the NCA that were most
subject to risk in terms of economic influence.
37.  Bodies should carry out valuations as at the year end, i.e. as at 31 March.
However, there is no requirement for this, and bodies may use 1 April (or other
date) subject to the standard condition that the carrying amount at the end of
the year does not differ materially from the current value at that date.
38.  Where a valuation has been carried out at 1 April 2024, a body should
evaluate whether: 
• there have been any movements in value during 2024/25 that should be
reflected in the 31 March 2025 carrying amount
• there is sufficient evidence that supports the body's consideration of the
above is adequate
• it has made necessary adjustments to the 31 March 2025 carrying
amount to reflect any movements that require to be reflected.
39.  The council adopt a five year rolling programme for the valuation of other
land and buildings. The valuation of these assets for 2024/25 has taken place
as at 1 April 2024. There was a 2.3 per cent increase in the BCIS index year on
year to quarter four, that is, 1 March 2024 to 31 March 2025. The valuer did not
consider this an unusual variance and therefore considered that a
reassessment of the DRC figures was not required out with the 5 year rolling
programme. 
40.  Whilst the council has demonstrated that the current approach of
undertaking valuations as at 1 April has resulted in appropriate valuations in
accordance with the Code, management should consider valuing at 31 March to
reduce the risk of adjustments being required as a result of material movements
in year.
Whole of Government Accounts (WGA) return
41.  The council is part of the WGA boundary and therefore prepares a return
that is used by HM Treasury to prepare the WGA. The National Audit Office
(NAO) is the auditor for the WGA and issues instructions outlining audit
procedures auditors must follow when auditing a WGA return. The threshold for
requiring audit procedures to be performed on the WGA return was set at £2
billion. 
42.  The council is below this threshold and therefore only limited audit
procedures are required, and submission of an assurance statement to the
NAO.
43.  The council has had issues setting up users for portal access to allow
completion of the WGA; despite ongoing dialogue the council did not
receive a response. The council has now identified a new contact and
41

Page 42

Audit of the annual accounts | 21 
dialogue is underway to setup users and allow access for the WGA return
to be completed going forward. 
44.  As a result the above, the council has not submitted the WGA return
for 2023/24 or 2024/25 financial years.
Recommendation 2
The council should continue to engage with HM Treasury to ensure that both prior year and the
2024/25 return is submitted in line with WGA guidance.
Prior year recommendations 
45.  The council has made good progress in implementing the agreed prior
year audit recommendations. For actions not yet implemented, revised
responses and timescales have been agreed with the body and are
outlined in Appendix 1.
42

Page 43

Wider scope audit | 22 
Wider scope audit 
Conclusion
The council operated within budget in 2024/25.
The level of General Fund reserves has increased with the majority of
these earmarked for specific council priorities.
The council implemented a new financial system at the start of the
2024/25, Oracle’s cloud-based Human Resources (HR) and Finance
solution. This was a significant change programme with a focus on
delivering significant improvements to processes, workflow, support
agile working, employee self-service and engagement as well as greater
levels of automation and improved management information.
The council’s revenue budget strategy has reported a projected budget
surplus for 2025/26 however there remains a budget gap over the
medium term. The council continues to undertake scenario planning and
transformation reviews to support medium and long term financial plans.
The council has effective budget monitoring arrangements. Given the
financial pressures, the council is continuing to assess its reserves
strategy and review how it assesses, monitors and reports on its
financial resilience.
The council has sound governance arrangements in place for how it
conducts business. To ensure the Risk and Audit Scrutiny Committee is
effective in its role an annual review and assessment should be
undertaken with the results captured within an annual report.
Audit approach to wider scope
Wider scope
46.  As reported in the Annual Audit Plan, the wider scope audit areas are: 
• Financial Management.
• Financial Sustainability.
• Vision, Leadership and Governance.
• Use of Resources to Improve Outcomes.
43

Page 44

Wider scope audit | 23 
47.  Audit work is performed on these four areas and a conclusion on the
effectiveness and appropriateness of arrangements the council has in
place for each of these is reported in this chapter. 
Significant wider scope risks 
48.  Audit work has been performed in response to the significant wider
scope risks identified in the Annual Audit Plan. The outcome of audit work
performed is summarised in Exhibit 6. 
Exhibit 6
Significant wider scope risks
Significant risk Planned audit response Outcome of audit work
Financial sustainability
South Lanarkshire Council
continues to operate in an
increasingly complex and
challenging environment,
aiming to provide the best
possible service within the
resources available. 
Although a surplus position of
£13.727 million is projected
for 2024/25, the council has
identified a savings
requirement of £77.275
million for the next three
years to 2027/28.
Management have
implemented a programme of
reviews to contribute towards
addressing the financial
pressures. However, there is
a risk that the council plans
do not deliver the required
savings to address the
projected shortfall. 
The audit team will:
• Review the council’s
annual budget setting
arrangements.
• Review and assess budget
monitoring arrangements.
• Review of the council’s
medium to longer term
financial planning including
how the council aligns
savings plans and
transformation activity with
strategic priorities.
• Review the council’s
financial position and
delivery of planned
savings.
Audit work performed found:
• the council’s annual
budget setting and
monitoring arrangements
were appropriate.
• The council’s medium and
longer term financial
planning aligns with their
strategic priorities.
Conclusion: The council
recognise the financial
challenges facing the
organisation. 
The council continues to
undertake scenario planning
and transformational reviews
to support medium and long
term financial plans.
Source: Audit Scotland
44

Page 45

Wider scope audit | 24 
Conclusions on wider scope audit
Financial Management 
The council operated within budget in 2024/25
49.  The council approved its 2024/25 revenue budget of £956.252 million in
February 2024. In its 2024/25 annual accounts, the council reported an
underspend on the provision of services of £30.090 million. This was mainly as
a result of underspends in the corporate items budget, an underspend on loan
charges, and an over-recovery of council tax. There were also underspends in
each resource level with the exception of education resource. Following a
number of agreed transfers to contribute to reserves, the final reported position
was break-even. 
50.  The changes in the budget position were reported in revenue budget
monitoring reports presented to the Executive Committee throughout the year.
These reports contained a good level of detail on the forecast outturn position. 
The level of General Fund reserves has increased with the majority of
these earmarked for specific council priorities
51.  One of the key measures of the financial health of a council is the level of
reserves held. The General Fund is the largest usable reserve and is used to
fund the delivery of services. 
52.  The level of usable reserves increased from £133.689 million in 2023/24 to
£147.568 million in 2024/25 exhibit 7. The General Fund balance is £118.997
million, however £105.954 million has been earmarked for a specific priority
which leaves a residual £13.043 million of uncommitted general reserves.
Against a revenue budget of £956.252 million for 2024/2025, this unearmarked
element represents a 1.36 per cent reserve. Management considers that this
level of reserve reflects a suitable contingency to contribute towards any
unanticipated pressures.
Exhibit 7
South Lanarkshire Council usable reserves 
Reserve 31 March
2021
£’million
31 March
2022
£’million
31 March
2023
£’million
31 March
2024
£’million
31 March
2025
£’million
General fund  116.980 122.424 150.283 109.773 118.999
Housing
revenue
account
12.784 16.241 12.861 13.221 10.440
Repair and
renewal fund
7.484 6.496 7.610 5.346 5.122
45

Page 46

Wider scope audit | 25 
Capital fund 6.268 5.730 4.776 3.975 11.195
Insurance fund  2.304 1.295 1.411 0.195 1.812
Total usable
reserves 
145.820 £152.186 176.941 133.689 147.568
Source: South Lanarkshire Council annual accounts 2020/21 to 2024/25
53.  We are satisfied that reserves are being regularly reviewed to confirm that
they remain at an appropriate level. However, there are ongoing sustainability
challenges of using reserves to fund recurring expenditure. Difficult decisions
will need to be taken in the future, with a clear plan and effective management
of the Council’s reserves key to maintaining financial sustainability.
Capital expenditure was less than originally budgeted in 2024/25
54.  The council approved the 2024/25 capital programmes in February 2024.
The general services programme for 2024/2025 originally totalled £49.512
million, with the housing capital programme amounting to £77.303 million. 
55.  At each meeting of the Executive Committee, capital programme monitoring
reports are presented to members. Throughout the year these reports detailed
the various movements in the general services programme budget.
56.  At the June 2024 Executive committee it was noted that since the approval
of this the baseline general services programme, additional funding was
received resulting in an adjustment to the 2024/2025 Capital Programme. The
final general services capital programme budget was £69.832 million.
57.  At the June 2025 Executive Committee, the general services outturn capital
programme spend was reported as £54.652 million for 2024/25 resulting in an
underspend of £15.180 million.
58.  The main projects contributing to the underspend reflects the profile of
spend across a number of projects including within the multi project and multi-
year programmes of Leisure and Culture Transformation Fund and Prioritised
Urgent Investment Fund where spend is now falling into the new financial year.
59.  The housing capital programme outturn was reported as £71.544 million for
2024/25, against the budget of £77.301 million. This represents slippage of 7.4
per cent against the revised budget (slippage of 2.5 per cent against 2023/24).
60.  Officer meetings take place every four weeks to consider each project on its
own merit. Any variations in spend anticipated are reported to members through
an adjustment to the programme to reflect the revised spend for the year and
achievability in terms of the project deliverables if applicable. These
adjustments are reported on a four-weekly basis to the Executive Committee
and then on an eight weekly basis to the relevant Resources (service)
Committee.
46

Page 47

Wider scope audit | 26 
The council successfully implemented a new financial system at the start
of the 2024/25, Oracle’s cloud-based Human Resources (HR) and Finance
solution
61.  The council successfully implemented a new financial system at the start of
the 2024/25, Oracle’s cloud-based Human Resources (HR) and Finance
solution. This was a significant change programme affecting the whole
workforce, with a focus on delivering significant improvements to processes,
workflow, support agile working, employee self-service and engagement as well
as greater levels of automation and improved management information. 
62.  The council will capture the efficiency improvements to support the council’s
financial position. This change project will also provide a platform for continuing
service improvements and efficiencies.
63.  Oracle (as the Cloud provider) are responsible for:
• security on the Oracle side, including in respect of internal Oracle
staff access to SLC data
• service continuity, including disaster recovery on the Oracle side
• change management, covering system and service maintenance
activities, upgrades and updates, and critical security maintenance
• customer support (with the SLC being the customer).
64.  Under the Oracle Cloud Hosting and Delivery Policies, Oracle are also
responsible for the secure backup of SLC Oracle data and being able to recover
and recreate this in the event of a cyber incident.
65.  Our consideration of the cyber security arrangements for the new Oracle
Cloud platform identified that the SLC data will be stored on the UK
Government Cloud. This is a sovereign Cloud created solely for the use of UK
Government and Defence customers and designed to reflect the requirements
of the UK Government. This arrangement strengthens the security of the data
stored for the SLC finance and HR systems. 
66.  As part of our audit we reviewed the arrangements SLC has in place to
obtain assurance on the Oracle Cloud Third-party hosting controls, through the
use of a service auditor. The role of a service auditor is to provide a report
against recognised standards and provide independent assurance that
outsourced service providers are operating effective controls. This gives the
users of the service assurance that the system operates as intended. It also
delivers efficiencies as it avoids the need for multiple audits and enquiries.
67.  The System and Organisation Controls 2 (SOC2) 2024/25 reports covered
the period 1 April 2024 to 31 March 2025 (from Oracle Fusion go-live until the
end of the 2024/25 financial year) and looked at the UK Government Cloud data
centres based in London and Newport. Our review of the service auditor report
identified that:
47

Page 48

Wider scope audit | 27 
• Physical security controls were outlined and tested via access
reports with no deviations from expected controls noted through the
testing completed. We noted that this testing was all completed
remotely with no datacentres physically visited for the review.
• Oracle Cloud infrastructure and security controls were found to be
operating effectively with event management, vulnerability scanning
and penetration testing undertaken with no deviations noted.
• Oracle Cloud infrastructure databases and configuration backups are
carried out and tested according to the schedules specified by the
council. 
• Change management arrangements related to Oracle’s internal
update processes were found to be appropriately designed and
operating as expected. The council’s internal change management
arrangements relating to Oracle configuration changes were found to
be operating as expected.
• Full stack disaster recovery procedures are the responsibility of
Oracle and policy standards covering business continuity and
disaster recovery are outlined within the report. No testing of
effectiveness of controls have been undertaken within the report.
However, a separate assessment of Oracle business continuity and
disaster recovery is carried out annually and no issues were noted.
68.  Our high level overview of the Oracle Fusion (Cloud) implementation in
relation to General IT Controls noted:
• the data migration process for transferring data from the old systems
to Oracle Fusion was well planned and executed and the scope of
the Finance and HR/ Payroll user acceptance testing plans was
sufficient to support the go-live decision dates with no significant
issues identified
• the cutover process was planned, managed and executed
• the helpdesk support tickets for 2024/25 are being managed as part
of business as usual. Open support tickets are generally planned to
be actioned through Oracle upgrades and policy updates during
2025/26. We plan to monitor the number of open tickets as part of
our 2025/26 audit
• patch testing and upgrades are being carried out on a regular basis
• internal business continuity plans were developed and updated,
however, it is unclear whether there any other key finance systems
that are not included in the plans or whether in the event of an
incident that manual control processes are in place for staff to
continue working
48

Page 49

Wider scope audit | 28 
• the project board approved the decision to go-live, however, we are
unable to obtain a minute of the meeting to identify if there was
anything relevant that needs to be reported, for example, outstanding
issues and risks 
• that clear supporting documentation was not always available due to
the council’s retention policy.
69.  Our review also noted that no post implementation or benefits realisation
review has been undertaken to capture and consider: 
• the impact of timescale delays and increased costs compared to
original budgets of the project
•  feedback of council service user experience of the implementation
process 
• the training and post implementation support provided
• range of benefits to be realised as part of the original business case
• that sufficient resources are available for the project going forward to
support the developments required to ensure the anticipated benefits
are fully realised.
Recommendation 3
Clear supporting documentation for future projects should be kept to back-up the decision
making process.
The council should undertake both a post-implementation and benefits realisation review of the
new Oracle platform to reflect on the overall success of the project in meeting its stated
objectives and expected benefits. This should include assessing which aspects of the project
went well and what could have gone better, and to identify lessons and insights that can be
applied more widely to improve the planning, management and delivery of future projects.
National Fraud Initiative
70.  The National Fraud Initiative (NFI) is a counter-fraud exercise across the
UK public sector which aims to prevent and detect fraud. The council
participates in this biennial exercise.
71.  The value of outcomes from the NFI, recorded since the last report, total
£21.5 million (up from the £14.9 million in 2022). The cumulative value of
outcomes from the NFI in Scotland since participation started in 2006/07 now
stands at around £180 million.
72.  The council has taken part in the NFI exercise since 2004/2005. The full
exercise, which takes place every second year, involves council wide
comparisons including benefits, payroll, creditors, council tax, licences and blue
badge holders. This data is matched to other benefits and payroll data as well
as Department of Work and Pensions (DWP) deceased persons’ records and
49

Page 50

Wider scope audit | 29 
the Electoral Register. Data extracts from council systems were submitted by
the due dates in 2024.
73.  Internal Audit presented a paper to the Risk and Audit Scrutiny Committee
in June 2025 which advised of the matches resulting from the 2024 National
Fraud Initiative (NFI) exercise and of the proposed target number of
investigations to be undertaken in 2025/26.
74.  Investigations have a proposed deadline for investigation of 31 December
2025. The council anticipate that most investigations will have been completed
ahead of this date and further updates on progress will be reported during
2025/2026.
75.  The council’s arrangements for investigating and reporting data matches
identified by the NFI are satisfactory.
76.  The audit work performed on the arrangements the council has in
place for securing sound financial management found that these were
effective and appropriate. This judgement is evidenced by the council: 
• having a system of internal control in place that is operating
effectively and has no significant weaknesses or deficiencies. 
• having clear and up-to-date policies and procedures, for example,
financial regulations and scheme of delegation, in place that ensure
effective financial management. 
• having clear and up-to-date policies in place for preventing and
detecting fraud and other irregularities, and participation in fraud
prevention and detection activities such as the National Fraud
Initiative (NFI). 
• having suitably qualified and experienced staff leading the finance
function, which has sufficient skills, capacity, and capability to
effectively fulfil its role. 
• having effective arrangements in place for the scrutiny of
arrangements that support sound financial management.
Financial Sustainability 
The council’s revenue budget strategy has reported a projected
budget surplus for 2025/26 however there remains a budget gap over
the medium term. The council continues to undertake scenario
planning and transformation reviews to support medium and long
term financial plans
77.  In February 2025 the council reported an expected budget gap of £32.320
million for the financial years 2026/27 (£18.515 million) and 2027/28 (£13.805
million) respectively. 
50

Page 51

Wider scope audit | 30 
78.  At the Executive Committee meeting in June 2025 management presented
the 2026/27 to 2027/28 Revenue Budget Strategy. The report advised that the
revenue budget position, before any corporate solutions, for 2026/27 to 2027/28
was a gap of £24.273 million. 
79.  The reduction in the projected budget gap was achieved by applying the
anticipated budget surplus in 2025/26 of £6.780 million and the full year impact
of 2025/2026 approved savings of £1.267 million. This resulted in the
anticipated budget gap in 2026/27 reducing to £10.468 million as detailed in
Exhibit 8.
Exhibit 8
Identified savings requirement 2025/26 to 2027/28 
2026/27
£ millions
2027/28
£ millions
Total
Original budget gap report to
Council in February 2025
18.515 13.805 32.320
Budget surplus from 2025/26 (6.780) - (6.780)
Full Year Impact of 2025/2026
Approved Savings
(1.267) - (1.267)
Total budget gap 10.468 13.805 24.273
Source: 2025/2026 to 2027/2028 Revenue Budget Strategy
80.  The report also highlighted that the there was a risk that the budget gap
could increase to £42 million as a result of pay awards. The pay deal for non-
teaching staff has been agreed for 2025/2026 and 2026/27. For teaching staff,
there is no pay deal beyond August 2025.
81.  Every 1 per cent that the pay offer is higher than the council has budgeted,
would cost almost £6 million per annum on a recurring basis with a multi-year
pay offer resulting in a recurring funding shortfall of up to £18 million.
82.  One way of managing the Budget Gap is the programme of
Transformational Reviews ongoing across the Council. Savings from completed
reviews have already been factored into the reduction in the projected budget
gap for 2026/27, as detailed above. 
83.  The Transformational Reviews are continuing to progress, and proposals
will be presented to elected members for approval as part of the Budget setting
process for 2026/2027 and 2027/2028. While any savings from the majority of
the Reviews have still to be confirmed, the council recognises that they would
not cover the full extent of the Budget Gap over the next two years.
51

Page 52

Wider scope audit | 31 
84.  One of the levers available to councils to assist in reducing their Budget
Gap is an increase in council tax levels. The 2025/2026 Council Tax Budget is
£171.823 million, therefore every 1 per cent increase in the Band D level means
a £1.718 million of additional income. 
85.  The report presented different scenarios to illustrate how different
percentage increases would reduce the budget gap. A five per cent increase
would reduce the budget gap over the period by £17.2 million whereas an eight
per cent increase would reduce the budget gap by £27.5 million.
86.  In addition the report explained that given the financial horizon, there was a
need to look at the picture not just for the medium-term and the report outlined
that work would continue over the summer with a view to presenting a Long-
Term Financial Strategy to Members in the Autumn. This will state the
assumptions made, and the risk areas which could impact on the Budget Gap
across the years.
The council has effective budget monitoring arrangements. Given the
financial pressures, the council is continuing to assess its reserves
strategy and review how it assesses, monitors and reports on its
financial resilience 
87.  The council recognises the financial challenges it faces in the coming years.
As detailed in exhibit 7, as at 31 March 2025, the council had a total General
Fund balance of £118.999 million. Of this £105.956 million has been earmarked
for a specific priority with a residual balance of £13.043 million of uncommitted
general reserves. 
88.  Councils can hold reserves for a number of reasons. Some reserves are
earmarked for identified expenditure which will, or may occur over the short,
medium or longer term. In addition to these reserves, there are uncommitted
reserves which help manage unforeseen circumstances.
89.  The Local Authority Accounting Panel (LAAP) provides guidance on the
establishment and maintenance of local authority reserves and balances. The
LAAP Bulletin does not prescribe a minimum level of reserves which should be
held by a council. It is for the council to consider an appropriate level of
reserves taking account of their strategic, operational and financial risks.
However, it does state that reserves should not be held without a clear purpose. 
90.  A Reserves Strategy was presented to the Finance and Corporate
Resources Committee on 30 October 2024. This detailed the council’s reserves,
their balance at the end of 2023/2024, their purpose, and also a proposed
strategy.
91.  The Reserves Strategy agreed to an annual review to consider the monies
held in the Earmarked/Committed General Fund Reserve, alongside the
Council’s Revenue Budget Strategy. This will be undertaken following the
completion of the Annual Accounts for 2024/2025 with an update provided to the
Finance and Corporate Resources Committee in September 2025.
92.  The Chartered Institute of Finance and Public Accountancy (CIPFA)
introduced a Financial Management Code for implementation by 31 March
52

Page 53

Wider scope audit | 32 
2021. This provides “guidance for good and sustainable financial management
in local authorities. By complying with the principles and standards within the
code, authorities will be able to demonstrate their financial sustainability”. A key
goal of the FM Code is to improve and evidence the financial resilience of
organisations by embedding enhanced standards of financial management.
93.  In our 2022/23 Annual Audit Report we recommended that given the scale
of the financial challenges facing the Council it should ensure that in developing
its financial strategy and annual budget there is a clear consideration around its
financial resilience, including the level of reserves to allow the council to meet
unforeseen costs and pressures. We also recommended that the council should
also enhance the level of monitoring around financial resilience indicators and
risks.
94.  A Financial Resilience and Sustainability report was presented to the Risk
and Audit Scrutiny Committee on 24 September 2024. This provided a summary
of the 2025/26 to 2027/28 Budget Strategy, demonstrating the council’s
understanding of the medium-term financial outlook and providing information
on the council’s financial resilience and sustainability.
95.  This paper demonstrated the council’s financial resilience by explaining its
detailed financial planning, its level of reserves and its key financial strengths in
term of its balance sheet position. The council recognises that this is about
more than the reliance on usable reserves, and that councils need to be more
comprehensive in their assessment of their level of financial resilience.
96.  The report detailed that the financial resilience of the council looks at its
ability to anticipate and respond to changes in the internal and external financial
environment. In order to do that, the council recognises it is important to know
what resources are available in a time of crisis, and not just reserves. It is also
important for the council to understand its exposure to loss of income, level of
commitment to expenditure, and to know the flexibility the council has in terms
of accessing funds when they are required.
97.  It noted that any risks identified through horizon scanning are mitigated
where appropriate through the Budget Strategy, which is a key part of the
council’s financial resilience framework. An annual update on the Council’s
financial sustainability will be presented to the Risk and Audit Scrutiny
Committee in September. Through the 2026/2027 to 2027/2028 Revenue
Budget Strategy the council demonstrates a clear understanding of the budget
pressures it faces. 
98.  Key financial information considered in forming the judgement on the
council’s arrangements for securing financial sustainability is outlined in
Exhibit 9. 
53

Page 54

Wider scope audit | 33 
Exhibit 9
Key financial information 
Budget setting
2022/23
(£m)
2023/24
(£m)
2024/25
(£m)
2025/26
(£m)
Budget gap 7.260 8.818 20.570 5.264
Planned to be met via:     
• Savings and flexibilities 6.185 1.950 13.190 6.485
• Use of reserves 3.235 6.565 2.176 11.970
• Additional council tax  3.482 8.050 7.869 9.480
• Recurring investments - - 0.480 3.921
• One-Off investments 5.642 7.747 2.185 18.750
Actual
Savings delivered 5.935 1.950 12.667 -
Reserves 
Use of / (contribution to) reserves  43.252 (13.879) -
Total usable reserves carried forward  176.941 133.689 147.568 -
General Fund: 150.283 109.773 118.999 -
• Earmarked  137.240 96.730 105.956 -
• Uncommitted  13.043 13.043 13.043 -
Source: The council’s 2024/25 annual accounts and Executive Committee papers
99.  The audit work performed on the arrangements the council has in
place for securing financial sustainability found that these were effective
and appropriate. This judgement is evidenced by the council:
• making appropriate arrangement to develop medium and longer-term
financial plans and linking these to its Corporate Plan and priorities.
• having effective arrangements in place for identifying risks to
financial sustainability over the medium and longer-term, and
understanding medium and longer-term demand pressures that could
impact on available resources. 
54

Page 55

Wider scope audit | 34 
• having savings plans in place to manage forecast budget deficits,
and a reserves strategy in place to manage the use of reserves if the
required level of savings cannot be met.
Vision, Leadership and Governance 
The council has clearly articulated its vision and priorities
100.  The Council’s Connect Plan 2022-27 is the strategic document that sets
out the Council’s vision, values and objectives and what difference this will
make to the residents and communities of South Lanarkshire. 
101.  The Council’s vision is ‘to improve the lives and prospects of everyone
in South Lanarkshire’. It sets out the key actions to be delivered over five
years, around a long-term vision with three key priorities and supported by six
detailed outcomes.
The council has sound governance arrangements in place for how it
conducts business. To ensure the Risk and Audit Scrutiny
Committee is effective in its role an annual review and assessment
should be undertaken with the results captured within an annual
report
102.  The council’s governance arrangements have been set out in the Annual
Governance Statement in the annual accounts. We have reviewed these
arrangements and concluded that they are appropriate. This is informed by our
regular attendance at the Risk, Audit and Scrutiny Committee and review of
Council, Executive Committee and other committee papers as appropriate.
103.  The Risk and Audit Scrutiny Committee’s role is to support the council in
establishing, maintaining, and improving effective governance, risk
management, and internal control arrangements. 
104.  It is important that elected members understand the financial and other
information presented in reports to committees and are equipped with the
knowledge and skills needed to scrutinise and challenge effectively. 
105.  Members need to ensure that all key decisions are subject to an
appropriate level of challenge and scrutiny at public meetings. This includes
sufficient discussion and scrutiny of performance and financial reports.
106.  As detailed in the Chartered Institute of Public Finance (CIPFA)
guidance on the audit committee and organisational effectiveness in local
authorities Local authority audit committees, recommended practice is for
audit committees to review and assess themselves annually or to seek an
external review. The results of the assessment should be available in the
annual report from the committee.
107.  There is also an opportunity for the council to refresh the Terms of
Reference of the Risk and Audit Scrutiny Committee to clearly document
committee members role in terms of review of risk, controls and audit
functions.
55

Page 56

Wider scope audit | 35 
Recommendation 4
Members should, with the assistance of officers, continue to review their personal training and
development needs and agree a plan to ensure that they have the skills required to effectively
fulfil their scrutiny and challenge roles. 
To ensure the Risk and Audit Scrutiny Committee is effective in its role an annual review and
assessment should be undertaken with the results captured within an annual report. 
108.  The audit work performed on the arrangements the council has in
place around its Vision, Leadership and Governance found that these
were effective and appropriate. This judgement is evidenced by the
council: 
• having a Corporate Plan in place, supported by Operational Plans,
that clearly set out its vision, strategy, and priorities and reflect the
pace and depth of improvement required to realise these in a
sustainable manner. 
• involving service users, delivery partners, and other stakeholders in
the development of its vision, strategy, and priorities to ensure these
align to their needs. 
• having clear financial and performance reporting in place, both
internally and externally, that is linked to its Operational Plans.
• having effective governance arrangements in place in general, as
reflected in the Annual Governance Statement included in the annual
accounts. 
Use of Resources to Improve Outcomes 
109.  The audit work performed on the arrangements the council has in
place around its Use of Resources to Improve Outcomes found that these
were effective and appropriate. This judgement is evidenced by the
council: 
• being able to demonstrate a clear link between the use of resources
and delivery of its priorities. 
• having arrangements in place to benchmark its performance to
identify areas of improvement. 
• being able to demonstrate improvements in performance against
benchmarks and relative to other comparable organisations. 
56

Page 57

Best Value audit | 36 
Best Value audit 
Conclusion
The council has effective and appropriate arrangements in place for
securing Best Value. 
The council has a Transformational Change Programme in place that is
clearly linked to its updated Council Plan, financial plans and digital
strategy.
The council currently focuses on establishing the financial benefits of its
transformational activities but does not routinely separately track or
report on the impact on service quality or outcomes for service users in
relation to these transformational activities.
Audit work assessed the arrangements the council has in place for
preparing and publishing SPI, including how it has responded to
assessments, and concluded the arrangements in place were effective
and appropriate. 
The council has an improvement action plan for all indicators, including
those reported as being below the Scottish average. 
The council has an effective performance management framework in
place.
The council reviews and reports its performance using a number of
measures that are clearly aligned to the priorities and outcomes set out
in the Council Plan.
Audit approach to Best Value
110.  Under the Code of Audit Practice, the audit of Best Value in councils
is fully integrated within the annual audit. As part of the annual audit,
auditors are required to take a risk-based approach to assessing and
reporting on whether the council has made proper arrangements for
securing Best Value, including follow up of findings previously reported in
relation to Best Value.
57

Page 58

Best Value audit | 37 
Themes prescribed by the Accounts Commission
111.  The Accounts Commission also reports nationally on thematic
aspects of councils’ approaches to, and performance in, meeting their Best
Value duties. As part of the annual audit, thematic reviews, as directed by
the Accounts Commission, are conducted on the council. The thematic
review for 2024/25 is on the subject of service transformation and involves
considering how the council is redesigning services to maintain outcomes
and deliver services more efficiently. 
112.  Conclusions and judgements on the council’s approach to service
transformation are outlined in a separate Management Report which is
available on the Audit Scotland website. A summary of the conclusions
and judgments made in the report is outlined below.
• The council has a Transformational Change Programme in place that
is clearly linked to its updated Council Plan, financial plans and digital
strategy.
• The council estimates that it has a budget gap of £42 million to
2027/28. To date it has approved savings of £6.485 million for
2025/26, £2.680 million of which is intended to be delivered from
transformational reviews. It is aware that it needs to explore further
transformation opportunities alongside other measures to help bridge
its budget gap and improve outcomes for the people of South
Lanarkshire.
• The council has effective governance arrangements in place to
oversee its transformational reviews through regular progress
updates to the Corporate Management Team. Comprehensive
updates are provided on a regular basis to elected members through
committee updates on transformational reviews and the budget
process.
• Transformational reviews are the responsibility of senior officers
across the council and are mainly taken forward by staff within its
resources (the council refers to its services or departments as
resources). The council has an officer in place who supports project
teams with the administrative tasks of the Transformational Change
Programme. Going forward, there is a risk that the council does not
have the sufficient dedicated resource to drive future transformational
activity required.
• The council has actively engaged in partnership working to support
the delivery of transformational activity.
• The council has provided examples of where it has engaged or
consulted with communities in relation to its transformational reviews
and budget-setting process. It is unclear what specific changes have
been made as a result of its community engagement.
58

Page 59

Best Value audit | 38 
• The council carries out Integrated Impact Assessments for its
transformational reviews to consider the potential changes to
services on vulnerable groups and there are examples of community
engagement taking place in relation to these.
• The council currently focuses on establishing the financial benefits of
its transformational activities but does not routinely separately track
or report on the impact on service quality or outcomes for service
users in relation to these transformational activities.
113.  The audit recommendations from the thematic report, together with
the management responses, are included in Appendix 1 of this report.
Statutory performance information (SPI) and service
performance 
114.  The Accounts Commission issued a Statutory Performance
Information Direction which requires the council to report its:
• performance in improving services and progress against agreed
desired outcomes, and 
• a self-assessment and audit, scrutiny, and inspection body
assessment of how it has responded to these assessments. 
115.  Auditors have a statutory duty to satisfy themselves that the council
has made proper arrangements for preparing and publishing statutory
performance information in accordance with the Direction and report a
conclusion in the Annual Audit Report. 
116.  Audit work assessed the arrangements the council has in place for
preparing and publishing SPI, including how it has responded to
assessments, and concluded the arrangements in place were effective
and appropriate.
The council has an improvement action plan for all indicators,
including those reported as being below the Scottish average
117.  The council participates in the Local Government Benchmarking
Framework (LGBF). The framework brings together a wide range of information
about how all Scottish councils perform in delivering services, including the cost
of services and how satisfied citizens are with them. 
118.  The most recent National Benchmarking Overview Report 2023-24 by the
Improvement Service was submitted to the Council’s Performance and Review
Scrutiny Forum in April 2025 along with a council specific action plan. Details of
the council’s trend over the past three years against these performance
indicators can be seen at exhibit 10. 
119.  Across the 102 indicators in 2023/24, the council’s performance has
improved against 41 (40 per cent) and declined against 34 (33 per cent). In
terms of the council’s figures relative to the Scottish average, performance was
59

Page 60

Best Value audit | 39 
better than the Scottish average for 44 (43 per cent) and worse than the
Scottish average for 34 (33 per cent) of indicators. 
120.  There are 22 (22 per cent) indicators for which the results or trend
information is not yet available for 2023/2024, including tackling climate change,
looked after children, educational attainment and attendance/exclusions. It is
hoped that these results will be available when the 2023/2024 data is refreshed
over the coming months.
Exhibit 10
South Lanarkshire Council analysis of LGBF results 
Number of
indicators (%)
2021/22
Number of
indicators (%)
2022/23
Number of
indicators (%)
2023/24
Performance   
Improving performance 39 (39%) 52 (51%) 41 (40%)
Declining performance 53 (54%) 36 (35%) 34 (33%)
No change in performance 3 (3%) 4 (4%) 5 (5%)
Information not available 4 (4%) 9 (9%) 22 (22%)
Comparison with Scottish
Average   
Better than Scottish average 50 (51%) 51 (50%) 44 (43%)
Worse than Scottish average 43 (43%) 40 (39%) 34 (33%)
Same as Scottish average 2 (2%) 2 (2%) 2 (2%)
Information not available 4 (4%) 9 (9%) 22 (22%)
Source: LGBF 2023/24 (2023/24 Results at January 2025)
121.  The council has an improvement action plan for all the indicators, including
those reported as being below the Scottish average. The council also
undertakes family group analysis, which focuses on those indicators performing
worse than the Scottish average. This aims to group councils into a “family
group” of councils with similar levels of deprivation and urban profiles, providing
better context to the results.
122.  At a service level, under-performing LGBF measures are included in the
horizon-scanning and self-assessment exercise undertaken each year. This
draws attention to poor performance in the LGBF and services are asked to
review the figures and provide narrative about reasons why and any actions
60

Page 61

Best Value audit | 40 
necessary which would feed into Resource Plans and improvement actions
throughout the year.
123.  The council publish a suite of Public Performance Reports (PPR). Each
PPR relates to a service area and are then grouped on the council website by
Connect outcome. The reports include information on targets, where applicable,
with performance from the prior two financial years detailed for both the council
and the Scotland average to allow comparison. Information is given on how the
target is measured and links are provided to further information. 
124.  Alongside overarching and service level performance reporting the council
publishes Annual Performance Spotlights, 'bite-sized' performance information,
per Connect Outcome which includes:
• a case study to illustrate how the council is working towards achieving
outcomes
• infographics giving a visual presentation of performance; identifying
whether or not performance is improving
• links to additional more detailed information.
125.  The council’s website covers all the requirements set out in the SPI
direction issued by the Accounts Commission. The council continues to
improve its public reporting of performance information through clear
alignment of performance information with its key strategic outcomes.
The council has an effective performance management framework in
place
126.  The Best Value: Revised Statutory Guidance 2020 sets out that councils
should be able to demonstrate a trend of improvement over time in delivering its
strategic priorities. 
127.  The Best Value: Revised Statutory Guidance 2020 also sets out that
performance management arrangements should be in place to promote the
effective use of the local authority’s resource, which includes effective
performance reporting.
128.  In 2021/22 the council engaged with the Improvement Service to review
how it used and reported on the Local Government Benchmarking Framework
(LGBF). This resulted in a suite of refined indicators to allow the council to
prioritise and allow for scrutiny on its identified improvement areas. 
129.  In 2024, the Improvement Service (IS) launched an online dashboard as
the main portal to access LGBF data and analysis. As part of this, the IS offered
to work with interested councils to explore how dashboard technology could be
used at a local level to improve engagement with and use of the LGBF.
130.  Building on the review of LGBF reporting undertaken in 2021-22, the
council has worked with the IS to develop a South Lanarkshire version of the
LGBF dashboard. Key features of the dashboard are:
61

Page 62

Best Value audit | 41 
• based on the 36 “priority indicators” aligned to the council plan outcomes
• focuses on SLC vs Scotland vs family group average performance
• allows drill-down to examine family group members and their performance
• provides at-a-glance time-trend information for each indicator
• presents the LGBF data for SLC along with local.
131.  Of the 102 LGBF indicators, 36 have been identified as aligning with the
outcomes of the Council’s Connect Plan. These are now embedded within the
Connect Plan’s reporting to focus attention on how well the council is
performing in achieving its strategic outcomes.
The council reviews and reports its performance using a number of
measures that are clearly aligned to the priorities and outcomes set
out in the Council Plan
132.  The council reviews its performance using a number of measures that are
aligned to the priorities and outcomes set out in the Council Plan. A total of 256
measures were identified within Resource Plans for 2024/2025. Of those 61 are
nominated as key strategic measures for reporting progress against the
Connect Outcomes detailed in the Council Plan. The measures are detailed
within the individual Resource Plans and bi-annual progress reports are publicly
reported on the performance pages of the Council’s website. 
133.  In addition, progress reports on Connect 2022-27 are taken to the
Performance and Review Scrutiny Forum. The latest Quarter 4 Progress Report
2024/2025 was considered in August 2025. The progress reports include a
summary of performance against measures for each of the Council’s Connect
Plan objectives, along with details of the main achievements for that objective.
134.  The Connect quarter four progress report for 2024/25 reports that of the
council’s 61 strategic performance measures, six projects had been completed;
43 projects, the timescale or target had been met; six projects where there was
minor slippage in timescale or target, four projects where there has been major
slippage against timescale or target and two where the information was not yet
available and would be reported at a later date.
135.  Performance management and reporting is well established within the
council. This provides members the opportunity to scrutinise the council’s
performance against its strategic objectives. Despite the ongoing service
pressures the council has achieved or is on track to achieve most of its
performance measures as set out in its Connect Plan. 
136.  From a review of the service performance information reported by the
council, this was found to be sufficiently detailed to provide an assessment
of progress the council is making against its strategic priorities and allow
effective scrutiny of performance. 
62

Page 63

Best Value audit | 42 
Progress against previous Best Value findings and
recommendations 
137.  Best Value findings and recommendations have been made in
previous years’ Annual Audit Reports, Management Reports on themes
prescribed by the Accounts Commission, and Controller of Audit Reports
on the council’s performance in meeting its Best Value duties. 
138.  Details of previous recommendations and progress the council is
making against these can be seen in Appendix 1. The council has
implemented the previous recommendations made. 
Conclusions on Best Value
The council’s arrangements and performance in meeting Best Value
and community planning duties are effective
139.  The audit work performed on the arrangements the council has in
place for securing Best Value and its community planning arrangements
found these were effective and appropriate. This judgement is evidenced
by:
• the council having well established and effective governance
arrangements in place, with the Best Value being a key aspect of the
governance arrangements
• the arrangements the council has in place around the four wider scope
audit areas, which are effective and appropriate, contribute to it being able
to secure Best Value 
• progress the council is making to embed sustainability into corporate and
operational plans and enhance reporting arrangements around
sustainability. 
63

Page 64

Appendix 1 | 43 
Appendix 1
Action plan 2024/25
2024/25 recommendations
Matter giving rise to
recommendation Recommendation 
Agreed action, officer and
timing
1. Close down procedures
There were delays in the
provision of a number of
underlying working papers to
the audit team to support the
financial statements.
Risk: There is a risk that the
delivery of the financial audit
is inefficient and the resultant
delays impact on the agreed
sign off by the statutory
deadline.
Staff should be reminded of
the year end timetable and
the importance that working
papers for external audit are
provided to the Finance
Strategy Team in line with the
year-end timetable deadlines
to ensure all working papers
are available with the
unaudited accounts.
Accepted 
The importance of meeting
timelines set will be reiterated
to all officers involved in the
Accounts process.
Head of Finance (Strategy)
End March 2026
2. Whole of Government
Accounts (WGA)
The council has had issues
setting up users for portal
access to allow completion of
the WGA; despite ongoing
dialogue the council did not
receive a response.
Risk: There is a risk the
council does not comply with
HM Treasury requirements in
respect of the submission of
WGA information.
The council should continue
to engage with HM Treasury
to ensure that both prior year
and the 2024/25 return is
submitted in line with WGA
guidance.
Accepted 
The Council can now access
the HM Treasury portal and
the WGA Accounts will be
submitted post audit.
Head of Finance (Strategy)
End October 2025
64

Page 65

Appendix 1 | 44 
Matter giving rise to
recommendation Recommendation 
Agreed action, officer and
timing
3. Oracle Fusion
The council successfully
implemented a new financial
system at the start of the
2024/25, Oracle’s cloud-
based Human Resources
(HR) and Finance solution.
Our review identified that
clear supporting
documentation was not
always available due to the
council’s retention policy.
We also noted that, as yet, no
post implementation or
benefits realisation review
has been undertaken.
Clear supporting
documentation for future
projects should be kept to
back-up the decision making
process. 
The council should undertake
both a post-implementation
and benefits realisation
review of the new Oracle
platform to reflect on the
overall success of the project
in meeting its stated
objectives and expected
benefits. This should include
assessing which aspects of
the project went well and
what could have gone better,
and to identify lessons and
insights that can be applied
more widely to improve the
planning, management and
delivery of future projects.
Accepted
Some supporting information
requested was outwith SLC
control as we no longer have
access to the systems where
these are held.
Year 1 post go-live focussed
on stabilisation. Post-
implementation and benefits
review are work in progress
as Year 2 activity with critical
friend approach developed.
Head of Information
Technology
Ongoing 
4. Risk and Audit Scrutiny
Committee
The Risk and Audit Scrutiny
Committee’s role is to support
the council in establishing,
maintaining, and improving
effective governance, risk
management, and internal
control arrangements.
Currently no self-assessment
review is undertaken on the
committee’s performance.
Risk: There is a risk
members do not reflect on
the effectiveness of the
committee to identify areas
for improvement.
Members should, with the
assistance of officers,
continue to review their
personal training and
development needs and
agree a plan to ensure that
they have the skills required
to effectively fulfil their
scrutiny and challenge roles.
To ensure the Risk and Audit
Scrutiny Committee is
effective in its role an annual
review and assessment
should be undertaken with
the results captured within an
annual report.
Accepted 
The annual training needs
assessment exercise will
continue to ensure members
are comfortable in their role.
An annual assessment will be
considered for the Members
of the Risk and Audit Scrutiny
Committee.
Head of Personnel and Audit
Manager
End June 2026
65

Page 66

Appendix 1 | 45 
Matter giving rise to
recommendation Recommendation 
Agreed action, officer and
timing
2024/25 recommendations from the BV thematic report
1. Transformation ambition
The council has significant
budget savings to make over
the next three years and
beyond and is aware that it
must explore further options
for transformation to help
bridge its funding gap and
improve outcomes for the
people of South Lanarkshire.
There is a risk that the
council may not be able to
deliver sustainable services if
the required savings are not
achieved.
The council should ensure its
plans for transformation are
sufficiently ambitious to
ensure that it can continue to
deliver sustainable services,
prioritising transformational
activities that will deliver the
most impact and contribute to
reducing the budget gap.
The Council continues to
progress a long term
schedule of transformational
reviews which run in parallel
with the Budget process, in
order to maximise the impact
on the Budget Gap. 
Executive Director of Finance
and Corporate Resources /
Corporate Management
Team.
September 2025
2. Resourcing
transformation
The council has advised that
delivering transformation is
part of the jobs of managers,
heads of service and
directors and the council has
periodically hired external
support to help capacity. It
has an officer in place to
support project teams with
the administrative tasks of the
transformation programme.
There is a risk that the
council’s Transformational
Change Programme will lose
momentum if it does not have
the sufficient dedicated
resource to drive the activity
required.
The council should assess
whether its arrangements for
resourcing transformation
activities are sufficient to
drive the scale and pace of
change required in future. 
The role of senior officers in
the Council includes
managing change and the
work around transformation
forms part of that role. The
arrangements for resourcing
transformation across the
Council will continue to be
monitored, and as is currently
the case, additional
resources will be deployed as
and when required.
Executive Director of Finance
and Corporate Resources /
Corporate Management
Team.
Ongoing as required
66

Page 67

Appendix 1 | 46 
Matter giving rise to
recommendation Recommendation 
Agreed action, officer and
timing
3. Demonstrating the
impact of community
engagement on
transformational activities
The council has shared
examples of how it has
engaged or consulted with
communities in relation to its
transformational reviews and
budget process. It is unclear
what specific changes have
been made as a result of this
engagement as this has not
been clearly demonstrated.
There is a risk that the
council is not viewed to have
considered community views
when prioritising which
transformational projects to
be taken forward.
The council should ensure it
demonstrates how
engagement with
communities, including
vulnerable groups, has
informed planned changes to
services. 
The Council will consider
adding a final stage to the
Budget Consultation process
for the 2026/2027 exercise,
to ensure outcomes are fed
back to communities. This will
include feedback on the
impact of consultation on
Transformational Reviews.
Head of Finance (Strategy)
March 2026
4. Measuring the impact of
transformational activities
The council currently focuses
on establishing the financial
benefits of its
transformational activities but
does not routinely separately
track or report on the impact
on service quality or
outcomes for service users in
relation to these
transformational activities.
There is a risk that, when
prioritising which
transformational activities to
take forward, the council
does not have adequate
information on impact to
make a fully-informed
decision.
The council should prioritise
establishing a framework that
identifies and monitors the
estimated and realised
impact to date of its
transformation work,
including on service delivery
and on outcomes for service
users. It should report to CMT
and elected members on both
the financial and non-financial
impact of the full range of its
transformational activities. 
The Council will develop a
framework to capture
estimated and actual impacts
from transformation activities. 
An annual report will be
produced which will provide a
summary of the outcomes
from the Transformational
Review Programme.
Executive Director of Finance
and Corporate Resources /
Corporate Management
Team
June 2026
67

Page 68

Appendix 1 | 47 
Follow-up of prior year recommendations
Matter giving rise to
recommendation
Recommendation, agreed
action, officer and timing Update 
1. Council house valuations
The approach taken by the
Council draws on elements of
Guidance for Valuers issued
in 2016, however only one
beacon property is used as a
basis for the full council
house stock held by the
Council.
Risk: There is a risk that the
council house stock is not
valued in line with applicable
guidance.
The valuer should detail the
valuation process followed,
assumptions that have been
made and supporting
information so that the entire
process, sources of
information and assumptions
provide suitable assurances
to management.
In addition the valuer should
review the current valuation
process against applicable
guidance to assure
themselves that the valuation
process remains fit for
purpose.
The Head of Property has
detailed the process followed
and has confirmed that the
valuation method used for
council house valuations
follows the Beacon method.
This valuation process
matches the applicable
guidance and therefore the
valuation process is fit for
purpose.
Responsible officer: 
Head of Property
Implemented.
68

Page 69

Appendix 1 | 48 
Matter giving rise to
recommendation
Recommendation, agreed
action, officer and timing Update 
2. IFRS 16 Implementation
From 1 April 2024, a new
International Financial
Reporting Standard, IFRS 16,
will come into effect for Local
Authorities. The Council is not
yet in a position to quantify
the likely impact of IFRS 16.
Risk: there is a risk that the
Council do not progress the
implementation of IFRS 16 in
line with the project plan.
The Council should review
the current timetable to
ensure that key dates are
being achieved to allow
implementation in line with
the project plan.
The Council is aware of the
requirements of IFRS 16 and
is working towards the
implementation date of end
March 2025. 
Responsible officer:
Head of Finance
Agreed date:
End March 2025
Implemented.
3. Statutory override
The statutory override relating
to valuation of infrastructure
assets is due to end for the
2024/25 financial statements.
Risk: A permanent solution
has not yet been agreed and
CIPFA believe that this will
continue be an area of
enhanced scrutiny for local
government auditors.
The Council should
proactively work with CIPFA
and the wider local
government sector to arrive at
appropriate solution for the
implementation of accounting
for infrastructure assets.
The Council is keeping a
watching brief on national
discussion on this topic and
will continue to engage with
CIPFA and other bodies
where possible, to arrive at a
suitable solution.
Responsible officer:
Head of Finance
Agreed date:
End March 2025
Work in progress.
The council will continue to
engage as required once
options are proposed by
CIPFA. 
69

Page 70

Appendix 1 | 49 
Matter giving rise to
recommendation
Recommendation, agreed
action, officer and timing Update 
4. Reserves strategy and
financial resilience
In our 2022/23 Annual Audit
Report we recommended that
the Council should enhance
the level of monitoring around
financial resilience indicators
and risks. 
Risk – This Council is
preparing a detailed report on
resilience to the Risk and
Audit Scrutiny Committee in
September 2024.
The council should ensure
that there is a clear risk
assessment and scrutiny of
the level of reserves held and
how this supports financial
resilience and sustainability
over the medium term.
The council has presented a
report to the Risk and Audit
Scrutiny Committee detailing
the Council’s Resilience
Framework. 
A further report on the
council’s Reserves position
will be presented to the
Finance and Corporate
Resources Committee in the
Autumn. This will detail the
level of reserves held by the
council, their purpose, and
will note their role in financial
resilience.
Responsible officer:
Head of Finance
Agreed date:
End November 2024
Implemented
70

Page 71

Appendix 1 | 50 
Progress against previous Best Value findings and
recommendations
Matter giving rise to
recommendation
Recommendation, agreed
action, officer and timing Update on progress
5. Corporate level
workforce strategy
supported by clear
reporting on actions
The Council does not have a
corporate level workforce
strategy. The Council level
workforce plan does not
include or refer to workforce
data, such as the age profile
of its workforce, the number
of casual staff used or
indicators of staff wellbeing.
Nor does it include any
information on what it is
currently doing to address
any workforce capacity issues
or how it plans to develop its
future workforce.
Risk – There is a risk that the
Council is not using workforce
data to inform workforce
planning that links to its
strategic priorities.
The Council should develop a
corporate level workforce
strategy to demonstrate a
clear link to the Connect
Council Plan 2022-27. The
Council should build on the
workforce planning to date
and implement a more
strategic, data-driven
approach to workforce
planning, with SMART action
plans, setting out how Council
level and service level actions
are being progressed.
Management response 
The Council will complete an
updated Workforce Strategy
for 2025-2027 with
accompanying workforce
plans to align to the Council
Plan Connect Business
Planning Cycle. 
The Council will create a
strategic workforce plan for
2025– 2027 to align with the
Council plan and will also
create workforce plans for this
period and reference the data
analysis and findings more
clearly to show both the high-
level actions and specific
resource actions.
Responsible officer
Head of Personnel Services
Actioned by
31 March 2025
Implemented 
71

Page 72

Appendix 1 | 51 
Matter giving rise to
recommendation
Recommendation, agreed
action, officer and timing Update on progress
6. Digital technology
The Council is at an early
stage in establishing links
between workforce planning
and digital technology
Risk – There is a risk that the
workforce planning is not fully
utilising the benefits of digital
technology.
The Council should develop
measures to capture and
monitor the impact of digital
technology on workforce
productivity and service
outcomes. It should also set
out how it expects digital
technology to shape its future
workforce.
The Council will include links
in the 2025-2027 workforce
strategy and plans to digital
technology. The Council will
include measures to capture
and monitor the impact of
digital technology.
Responsible officer
Head of Personnel Services
Head of IT Services 
Actioned by
31 March 2025
Implemented
7. Digital Exclusion
Digital inclusion is one of 21
principles set out in the Digital
Strategy 2022-27 and is also
one of eight themes. The
Council is progressing a
number of initiatives to
support digital inclusion.
Risk – There is a risk that
without a SMART action plan
to monitor progress the
Council cannot demonstrate it
is achieving the principles set
out in the Digital Strategy.
The Council should develop
an action plan to allow it to
monitor progress in
addressing digital exclusion in
its workforce and for its
citizens.
The Council will develop an
action plan within its
workforce plans that will detail
the next steps in progressing
digital inclusion in its
workforce. For its citizens,
this will be captured within the
digital strategy action plans.
Responsible officer
Head of Personnel Services
Head of IT Services 
Actioned by
31 March 2025 
Implemented
72

Page 73

Appendix 1 | 52 
Matter giving rise to
recommendation
Recommendation, agreed
action, officer and timing Update on progress
2022/23 recommendations
Transformational change
The Council should continue
to identify where it can
progress transformational
change in how its services
are delivered. This should
identify where recurring
savings, rather than
temporary solutions, can be
made together with proposals
to reduce costs.
The Council should continue
to identify where it can
progress transformational
change in how services are
delivered to address the
longer-term financial
pressures it faces.
Management Response:
The Council has a
programme of cross-cutting
reviews as well as individual
Resource Reviews which will
assist in bridging the budget
gap moving forward. 
Responsible officer:
Executive Director, Finance
and Corporate Resources
Agreed date:
Ongoing
Implemented 
73

Page 74

Appendix 2 | 53 
Appendix 2
Summary of uncorrected misstatements
Details
Financial statements
lines impacted
Statement of
Comprehensive Net
Expenditure (SoCNE)
Statement of
Financial Position
(SoFP)
Uncorrected misstatements Dr Cr Dr Cr  
£000 £000 £000 £000
1. Peppercorn leases not included
within the financial statements     
Property, Plant and
Equipment   3,849 
Surplus/Deficit on
provision of services  3,849   
74

Page 75

Appendix 3 | 54 
Appendix 3
Supporting national and performance audit reports 
Report name Date published
Local government budgets 2024/25 15 May 2024
Integration Joint Boards: Finance and performance 2024 25 July 2024
The National Fraud Initiative in Scotland 2024 15 August 2024
Transformation in councils  1 October 2024
Alcohol and drug services 31 October 2024
Fiscal sustainability and reform in Scotland  21 November 2024
Public service reform in Scotland: how do we turn rhetoric
into reality? 26 November 2024
Auditing climate change 7 January 2025
Local government in Scotland: Financial bulletin 2023/24 28 January 2025
Transparency, transformation and the sustainability of council
services 28 January 2025
Sustainable transport  30 January 2025
A review of Housing Benefit overpayments 2018/19 to 2021/22:
A thematic study 20 February 2025
Additional support for learning 27 February 2025
Integration Joint Boards: Finance bulletin 2023/24 6 March 2025
Integration Joint Boards finances continue to be precarious 6 March 2025
Council Tax rises in Scotland 28 March 2025
75

Page 76

South Lanarkshire Council
2024/25 Annual Audit Report Proposed Proposed 
Audit Scotland, 4th Floor, 102 West Port, Edinburgh EH3 9DN
Phone: 0131 625 1500 Email: info@audit.scot
www.audit.scot 
AS.5.0
76

Page 77

South Lanarkshire
Council
Best Value thematic management report 
Transformation: how councils are redesigning and
delivering more efficient services to achieve planned
outcomes 
Prepared by Audit Scotland
September 2025
3b
77

Page 78

Best Value thematic work:  | 2 
Contents 
Key messages 3
Introduction 5
Transformation planning 8
Programme management 11
Partnership working and community engagement 14
Impact of transformation 18
Appendix 22 
Accessibility
You can find out more and read this report using assistive technology on
our website www.audit.scot/accessibility.
78

Page 79

Key messages | 3 
Key messages 
1 The council has a Transformational Change Programme in place that is
clearly linked to its updated Council Plan, financial plans and digital strategy.
2 The council estimates that it has a budget gap of £42 million to 2027/28. To
date it has approved savings of £6.485 million for 2025/26, £2.680 million of
which is intended to be delivered from transformational reviews. It is aware
that it needs to explore further transformation opportunities alongside other
measures to help bridge its budget gap and improve outcomes for the people
of South Lanarkshire.
3 The council has effective governance arrangements in place to oversee its
transformational reviews through regular progress updates to the Corporate
Management Team. Comprehensive updates are provided on a regular basis
to elected members through committee updates on transformational reviews
and the budget process.
4 Transformational reviews are the responsibility of senior officers across the
council and are mainly taken forward by staff within its resources (the council
refers to its services or departments as resources). The council has an officer
in place who supports project teams with the administrative tasks of the
Transformational Change Programme. Going forward, there is a risk that the
council does not have the sufficient dedicated resource to drive future
transformational activity required. 
6 The council has provided examples of where it has engaged or consulted with
communities in relation to its transformational reviews and budget-setting
process. It is unclear what specific changes have been made as a result of its
community engagement.
7 The council carries out Integrated Impact Assessments for its
transformational reviews to consider the potential changes to services on
5 The council has actively engaged in partnership working to support the
delivery of transformational activity.
79

Page 80

Key messages | 4 
vulnerable groups and there are examples of community engagement taking
place in relation to these.
8 The council currently focuses on establishing the financial benefits of its
transformational activities but does not routinely separately track or report on
the impact on service quality or outcomes for service users in relation to
these transformational activities. 
80

Page 81

Introduction | 5 
Introduction 
1. Transformation is about radically changing how councils operate and
deliver services to achieve planned outcomes in a financially sustainable
way (Transformation in councils, Accounts Commission, October 2024).
The Accounts Commission’s Transformation in councils report recognises
that, while work has been ongoing in relation to local government
transformation for decades, a step change is required and the pace and
scale of transformation must increase significantly.
2. Transformation, through greater collaboration with partners, will be key
for councils to deliver more sustainable service models in challenging
financial climates.
3. This report sets out how the council is redesigning and delivering more
efficient services to achieve planned outcomes.
4. The Accounts Commission’s Strategy (2021-26) sets out its priorities to
focus on inequalities, funding, communities and recovery. The Code of
Audit Practice sets out the Best Value work required to report on these
priorities. 
5. This report covers the thematic aspect of the Best Value audit
requirements. The Commission has directed auditors to report on
transformation and how councils are redesigning and delivering more
efficient services to achieve planned outcomes. In carrying out the work,
auditors have considered the following questions: 
• To what extent does the council have clear plans for transformation
that link to its priorities and support long-term financial
sustainability?
• To what extent do the council’s programme management
arrangements facilitate effective oversight of its transformation
plans?
• To what extent are partners and communities involved in the
development and delivery of the council’s plans for transformation?
• To what extent has the council considered the impact of its
transformation activity, including on vulnerable or protected groups?
6. An improvement action plan is included at the Appendix of this report.
This sets out audit recommendations in key areas, and the council’s
planned response including responsible officers and dates for
implementation.
81

Page 82

Introduction | 6 
7. The coverage of the work is in line with the expectations for councils’
arrangements for the seven Best Value themes in the Local Government in
Scotland Act 2003, Best Value Statutory Guidance 2020 and we have
considered the Accounts Commission’s transformation principles set out in
Transformation in councils (Exhibit 1).  
82

Page 83

Introduction | 7 
Exhibit 1
Transformation principles
Transformation is about radically changing how councils operate and deliver services to achieve
planned outcomes in a financially sustainable way.
Principle  
Vision
Have a clear vision that sets out the intended end state of any transformation
activity, focused on: 
• delivering large-scale recurring savings or generating income for the council,
contributing to its longer-term financial sustainability
• improving outcomes for citizens in line with council priorities
• taking a whole-system approach to see and realise opportunities both within
councils and more widely
• meeting the needs of the people who use services and reduce inequalities
• focusing on preventative activity, where applicable, to reduce the demand for
services and to make them sustainable in the longer term.
Planning
• Be clear on the scale of the change required and ensure transformation plans
are sufficiently ambitious to credibly respond to the scale of the challenge.
• Commit staff with appropriate skills, time, and resources to ensure
transformation occurs at the scale and pace required and that there is enough
capacity for the changes to be embedded.
• Be clear about the timescales, costs, outcomes, and anticipated impacts of
transformation projects.
• Show urgency and progress projects at pace without compromising
appropriate governance on projects.
Governance
• Have a clear process for monitoring, evaluating, and reporting progress.
• Put in place effective governance and escalation processes so that the
transformation activities are well managed in their own right, but also able to be
given priority alongside other business-as-usual activities.
Collaboration 
• Develop better working relationships with communities and/or partners to
achieve a sustainable model of service delivery.
• Actively consider the opportunities offered by regional or national sectoral
collaboration, or by integrating services locally with partners, or by supporting
individuals and communities to achieve desired outcomes in place of an existing
service.
• Learn from good practice across Scotland and beyond.
Innovation 
• Implement new ways of thinking, including innovation, creativity and a desire,
willingness, and action to change and do things in new and different ways that
achieve the outcomes needed.
• Embed the right culture and behaviours to manage change and help maximise
the contribution of all the team.  
Source: Accounts Commission, Transformation in councils, October 2024
83

Page 84

Transformation planning | 8 
Transformation planning 
8. Councils need to ensure they can deliver sustainable services now and
in the future, and difficult decisions will need to be made to achieve this.
The Accounts Commission’s Local government budgets 2025/26 briefing
noted that councils’ cumulative funding gap to 2027/28 is £997 million.
Councils will need to identify and deliver recurring measures such as
savings or increased income to be financially sustainable in the short term.
9. In January 2025, the Accounts Commission advised in its Local
government in Scotland Financial bulletin 2023/24 that councils need to
intensify transformation activity, progressing at scale and pace to ensure
their financial sustainability and how councils plan to use their reserves,
make savings and transform their services needs to become more
transparent.
Findings Evidence
The council has a
Transformational Change
Programme in place.
Transformational activity is
being driven by
transformational reviews. 
• The council has a Transformational Change Programme
that aims to help it achieve a balanced budget and support
medium and long-term financial plans. This approach consists
of transformational reviews that focus on how services are
being delivered with a view to identifying efficiency savings
and redesigning services. 
• The council has advised that, for the past three years, its
transformation work has been primarily focused on
addressing budget pressures. At the June 2024 meeting of
the Executive Committee the council set out its approach to
identifying savings options through transformational reviews.
Some transformational reviews are organisation wide while
others are specific to one service (or resource as they are
referred to by the council). Reviews include charging,
procurement, digital transformation, property and fleet
reduction. The council’s Financial Resilience and
Sustainability report from September 2024 advised that the
transformational reviews would build on past service reviews. 
• A standard template has been created for the Terms of
Reference of each review to include details on the
background, identified issues, desired outcomes, scope of the
review and key milestones. This is being applied consistently
across reviews. 
84

Page 85

Transformation planning | 9 
Findings Evidence
The council has significant
budget savings to make in
2026/27, 2027/28 and
beyond and is aware that it
needs to explore further
transformation
opportunities alongside
other measures to help
bridge its budget gap and
improve outcomes for the
people of South
Lanarkshire. 
• The council’s latest projected budget gap is £42 million
across 2026/27 and 2027/28 after accounting for additional
levers such as council tax and reflecting agreed pay awards
to date. 
• In the April 2025 Performance and Scrutiny Forum update
on Transformational Reviews, the council set out that £2.680
million of the approved savings in 2025/26 (£6.485 million)
were related to the ongoing transformational reviews on
procurement, overtime, management structures and council
charges. 
• The council also sets out its intention for the
Transformational Change Programme to reduce its budget
gap during 2026/27 and 2027/28. The council is currently
quantifying the transformational savings it aims to achieve
across these years.
• A report to council in February 2025 outlined the impact
the 2025/2026 approved savings will have beyond that year.
The savings in relation to Waste Permits (£0.875 million) and
Sheltered Housing – Housing Support Funding to Registered
Social Landlords (£0.392 million) were both approved for
2025/2026 and will have an impact on the budget gap in
2026/2027. This reduces the budget gap by £1.267 million
into 2026/2027.
• The council regularly highlights (including in its 19 August
2025 update to the Performance and Review Scrutiny Forum
on transformational reviews) that there is a need for
transformational change to manage the significant budget
gaps facing the council over the next three years. 
85

Page 86

Transformation planning | 10 
Findings Evidence
The council’s
transformational activity is
clearly linked to its
financial and digital
strategies. 
The council strengthened
the links between
transformation and its
Council Plan through its
mid-term review conducted
in April 2025. 
• The council’s 2025/26 to 2027/28 Revenue Budget
Strategy from June 2024 includes a section on
transformational change. It refers to the importance of the
council having a programme of change to deliver a balanced
budget and the intention for the Transformational Change
Programme to drive continuous improvement as well as
efficiencies. 
• As set out above, the council continues to review its
approach to transformation. There was no specific reference
to transformation in the Council Plan created in 2022,
however the priorities set out are: 
- ‘People – we need to put people first and reduce
inequality’ 
- ‘Planet – we need to work towards a sustainable
future in sustainable places’ 
- ‘Progress – we need to recover, progress and
improve’ 
• A mid-term review of the Council Plan presented to the
Executive Committee on 30 April 2025 recognised the likely
demands of the next few years and resulting requirement for
transformation and service design work. The document
prepared for the mid-term review explains that ‘Given the
magnitude of the budget gap, there requires to be a
fundamental re-think of what public services in Scotland can
do moving forward in order to achieve financial sustainability.
That includes what the council can deliver by way of services
to the public’. The council outlines it is continuing with its
transformational reviews to deliver savings proposals to
members. 
• Transformational activity is also referenced in the Finance
and Corporate Resources Plan 2024/25 and Digital Strategy
2022-27. 
Recommendation 1
The council should ensure its plans for transformation are sufficiently
ambitious to ensure that it can continue to deliver sustainable services,
prioritising transformational activities that will deliver the most impact
and contribute towards reducing its budget gap. 
86

Page 87

Programme management | 11 
Programme management 
10.  It is essential that councils have good programme management
arrangements in place to ensure they are making sufficient progress
against their transformation plans. It is important that councils have the
structures and the staffing resource in place to deliver their transformation
ambitions. In addition, councils must ensure that both senior officers and
elected members have appropriate oversight of progress.
Findings and evidence relating to the council’s programme management
arrangements 
Findings Evidence
The council has an officer
in place who supports
project teams with the
administrative tasks of the
Transformational Change
Programme. 
Going forward, there is a
risk that the council does
not have the sufficient
dedicated resource to drive
the future transformational
activity required. 
• Oversight of the Transformational Change Programme is
led by an Executive Director and CMT meet every two weeks
to discuss the programme. 
• An officer is in place who is responsible for the
administration work around the Transformational Change
Programme. The officer creates a level of consistency and
timeliness around collating all information related to reviews,
leaving staff within Resources to focus on the main content of
the reviews.  
• The council has advised that delivering transformation is
part of the jobs of managers, heads of service and directors
and the council has periodically hired external support to help
capacity. The council recognises that it needs to continually
monitor whether it has sufficient dedicated resource to drive
the scale and pace of transformation required going forward.
• The Terms of Reference for reviews set out resourcing and
details of who is leading the review. 
• The council has an IT Development Fund which can be
used to support transformational reviews when required. The
council has advised that there are also other funds that can
be deployed when necessary, for example, there has been
£24 million set aside to support the output from the Estates
Strategy Review. 
The council has effective
governance arrangements
in place to oversee its
transformation work. 
The Corporate Management
Team receives regular
• There is strong ownership of transformational activity from
senior leadership at the council, with the Chief Executive and
all directors being members of the Corporate Management
Team (CMT) who meet every two weeks to discuss the
transformational reviews. 
87

Page 88

Programme management | 12 
Findings Evidence
updates on progress
against the
transformational reviews
and a clear schedule of
reporting is set out. 
• Progress on the transformational reviews is reported to the
Corporate Management Team through the council’s
efficiencies workstream. The efficiencies workstream is
focussed solely on transformational change at the council
with a view to delivering efficiencies and savings. It also
ensures that services are being delivered in line with CMT
expectations. The CMT meets on a weekly basis to direct
council operations and efficiencies workstream meetings are
held on a rolling two-week schedule. 
• CMT regularly receives progress reports on the revenue
budget savings (at least quarterly). These updates detail what
savings have been achieved to date along with an estimate of
savings still to be achieved in the year and notes any reasons
for variances including slippage from the original savings
targets.  
•  The council advised that a number of the reviews are in
their early stages and resultant savings cannot yet be
quantified for all transformational reviews. These need to be
established as the work progresses to prioritise which
projects to expedite.  
• As the transformational reviews progress, some updates to
CMT have begun to quantify savings where these are known.
Examples include additional income from increased charges
for bereavement services in 2025/26, increased school meals
charging over a three-year period to 2027/28 and savings
already realised by changing the scope of cleaning tasks in
local schools. 
• The updates reported to CMT do not clearly show which
outcomes have already been realised against those identified
for the transformational reviews (per the terms of reference).
We cover this in more detail in the Impact of Transformation
section of this report.
• Examples of good practice demonstrated in reporting to
CMT by other local authorities includes reporting on progress
with projects using RAG statuses and reporting on slippage
and key risks within projects. Some councils use exception
reporting, focusing on the most at-risk projects.
• The council’s Year End Risk Management Report
(2023/2024) and Review of Council’s Top Risks (2024/2025)
sets out that monitoring the delivery of transformational
reviews will inform whether an overarching ‘transformational
change’ risk requires to be developed and added to the top
risk register. It also noted that outcomes from the reviews
offer mitigation against the top risk on funding.
• The council provided the audit team with an example of a
risk register for the Customer Engagement Review. This
88

Page 89

Programme management | 13 
Recommendation 2
The council should assess whether its arrangements for resourcing
transformation activities are sufficient to drive the scale and pace of
change required in future. 
Findings Evidence
clearly sets out what the risks relating to the review are along
with an inherent risk rating, control measures in place,
residual risk rating and details of any further mitigations
required to control the risk. Risk registers are completed for
reviews when deemed necessary based on the stage of the
review. 
Comprehensive updates
are provided on a regular
basis to elected members
through committee updates
on transformational
reviews and the budget
process.
• The Performance and Review Scrutiny Forum receives
updates on the ongoing transformational reviews every two
months. The updates are comprehensive and outline current
progress against each review. The updates also provide
information on risks associated with each of the reviews and
key milestones. 
•  Updates to elected members also include detailed
breakdowns of savings identified to date resulting from
transformational reviews where this is known. Information on
non-financial benefits and outcomes are an integral part of
transformational reviews but are often described in qualitative
terms. All Performance and Review Scrutiny Forum meeting
papers and minutes are publicly available on the council’s
website and meetings are live streamed on YouTube and are
also available to be viewed after the meeting on the YouTube
site. 
• Elected members receive updates on projects, where
appropriate, through relevant committees for example, the
Social Work Resources Committee receives updates on
projects relating to Social Work.
• Updates on the Revenue Budget are presented to the
Executive Committee throughout the financial year. 
89

Page 90

Partnership working and community engagement | 14 
Partnership working and
community engagement 
11. The Best Value in Scotland report noted that councils must now
rethink how they work together, and with local partners and communities,
to provide financially sustainable services. Few councils provide services
jointly or share support services across different councils to a great extent.
The scale and nature of the challenge, as set out in the Transformation in
councils report, means that it is only by working more collaboratively that
councils and their local partners, communities and the third sector will be
able to provide sustainable local services.
Findings and evidence relating to the council’s partnership working and
community engagement arrangement 
Findings Evidence
The council has actively
engaged in partnership
working to support the
delivery of transformation
projects, some of which
have been jointly funded. 
• South Lanarkshire Council is undertaking a review of
partnership working with the local third sector. The review
aims to strengthen collaboration, improve operational
relationships, and build on existing initiatives with the third
sector. It has engaged with the third sector through a range of
workshops throughout the spring and summer of 2025 and is
in the process of updating internal processes and guidance
for the provision of grants for third sector organisations. 
• The council is currently undertaking a review of Digital
Transformation to create efficiencies across three key areas-
business systems and processes, workforce productivity and
customer engagement. To date, work has involved
partnership working with commercial businesses.
• The council has provided two examples of successful
transformation projects it has delivered to date. This includes:
Analogue to Digital: Shared Cloud-Based Alarm Receiving
Centre (ARC) Solution (Case study 1) and South Lanarkshire
Futures (Case study 2). Both examples highlight effective
partnership working and community engagement and have
been jointly funded.
• The council has also identified the Marmot Place
Programme for South Lanarkshire as a key example of
transformational partnership working. This evidence-based
initiative brings together partners to tackle inequalities in a
90

Page 91

Partnership working and community engagement | 15 
Findings Evidence
specific place. South Lanarkshire is one of three areas in
Scotland piloting the programme with Public Health Scotland
and the University College London Institute of Health Equity,
led by Professor Sir Michael Marmot.  A local data working
group is analysing cross-sector data to better understand and
address place-based inequalities. Governance is overseen by
a leadership group of community planning and third sector
partners. Insights from integrated local data will inform future
service delivery and prevention strategies, with stakeholder
workshops planned for Autumn 2025 to establish actionable
responses to the findings. 
The council has shared
examples of how it has
engaged or consulted with
communities in relation to
its transformational
reviews and budget-setting
process. It is unclear what
specific changes have been
made as a result of this
engagement. 
• The budget consultation for 2025/26 provided residents
with savings options to consider and potential council tax
percentage increases, totalling over £11 million. Survey
respondents were asked the extent to which they agreed or
disagreed with the options, as well as having the opportunity
to leave specific comments on each area. Each option clearly
set out the financial impact and workforce implications (eg,
savings amount and number of posts affected). The
consultation also incorporated elements of transformational
reviews, such as the council’s proposals to increase charges
for its services (eg, burials and cremations). The results of the
budget consultation were shared with elected members in
January 2025 for consideration when drafting their budget
proposals and the results were also factored into integrated
impact assessments. It is not clear what impact this had on
decisions made by elected members on the 2025/26 budget. 
• The council also engaged with the community in
developing its 10-Year Estate Strategy. A public consultation
held in April and May 2025 invited views on the future of
council-owned properties and how they could better meet
community needs within its financial constraints. An online
survey received 298 responses, with 96 per cent supporting a
review of the council’s estate and 68 per cent agreeing that
the outcome would likely deliver a smaller but higher quality
estate. The next round of public consultation is currently
being held, and feedback will be used to inform the
development of the final strategy. Therefore, it is too early to
conclude what impact this had on the strategy. 
• The council is in the process of carrying out a
transformational review of its customer engagement. To date,
the work has involved engaging with the Scottish Local
Authority Customer Services Managers Group. A survey has
been issued to capture information on systems and
processes. The council also plans to issue two customer
surveys to obtain feedback on the most efficient contact
91

Page 92

Partnership working and community engagement | 16 
Case study 1 
Digital telecare transformation
The Analogue to Digital: Shared Cloud-Based Alarm Receiving Centre (ARC) Solution project
ensures the continued delivery of community alarms services ahead of the UK-wide analogue
switch off in October 2025, replacing outdated systems with a more resilient cloud-based digital
solution. 
South Lanarkshire Council’s social work department led on delivering the community alarms
locally and were supported through partnership working with Scottish Government’s Digital
Office and Scotland Excel who led on procurement and development of the national ARC
solution. The council also worked in collaboration with a range of other stakeholders including
Chubb, Sky response, TEC Scotland and 16 other local authority RSLs. 
The council was actively involved in the project steering group and co-design workshops and
has engaged with the community in a variety of ways, including outreach through social media,
direct messaging and publishing articles to prepare users for the transition. The design process
was shaped by service users, carers and stakeholders and the project prioritised continuity of
service for vulnerable users, ensuring no disruption during the transition. 
The project has achieved significant milestones, including the deployment of digital-ready
devices to over 50 per cent of users and recognition through a Bronze Digital Telecare
Implementation Award. The project focuses on service improvement rather than cost savings.
However, the cloud-based system offers efficiencies through flexible working and better data
access. A key outcome for the project is for the use of digital solutions to assist in preventing
hospital admissions or the need for long-term care for sheltered housing tenants.  
A project closure report has been prepared that sets out nine follow-up actions. These include  
agreeing and realising community benefits following completion of the first year after going live
and developing a suite of management reports. 
The council received a total of £0.116 million from the Scottish Local Government Digital Office
for this project.
Source: South Lanarkshire Council 
Findings Evidence
methods. It is not yet clear how council services will change
as a result of the engagement. 
92

Page 93

Partnership working and community engagement | 17 
Case study 2 
South Lanarkshire Futures
The SLC Futures project is a transformational initiative led by South Lanarkshire Council, in
partnership with Barnardo’s and local services to support young people transitioning from care
to independent living. It provides tailored housing support, life skills development, and a
structured pathway to tenancy, aiming to reduce inequality and prevent homelessness through
early intervention. 
Young people with experience of care have played a key role in shaping the service, which was
co-developed with stakeholders including Barnardo’s Health and Homeless Team, high school
pupils and those living in temporary accommodation. The project draws on insights from The
Promise Design School and the Scottish Service Design Toolkit, to ensure a user-centred
approach.
Funding of £0.166 million was provided by The Big Lottery and £0.126 million by SLC Social
Work, through the provision of four training flats and a dedicated Throughcare Housing Officer.
By January 2025, five young people had been supported to independent living, generating
£0.230 million in savings for 2024/25. The initiative has reduced out-of-area placements and
homelessness presentations, with projected recurring savings of £0.8 million annually from
2025/26 onwards. The model demonstrates innovation, collaboration, and a scalable approach
to youth housing support.
Source: South Lanarkshire Council
Recommendation 3
The council should ensure it demonstrates how engagement with
communities, including vulnerable groups, has informed planned
changes to services. 
93

Page 94

Impact of transformation | 18 
Impact of transformation 
12. It is important that councils have success measures in place to
demonstrate the impact of their transformational activity on service quality;
outcomes for people who use services, inequalities and/or savings. 
Findings and evidence relating to the impact of the council’s transformation
activity 
Findings Evidence
The council currently
focuses on establishing the
financial benefits of its
transformational activities
but does not routinely
separately track or report
on the impact on service
quality or outcomes for
service users in relation to
these transformational
activities. 
• South Lanarkshire Council reports publicly twice a year on
progress against the six key outcome areas identified in
the Council Plan Connect 2022-2027 (communities and
environment, education and learning, health and wellbeing,
children and young people, housing and land, and our
economy). These reports draw on the latest available data
to provide a summary of progress, key achievements and
areas for improvement. The council also produces annual
public performance reports which focus on the
performance of key areas of council business, such as
finance, budgeting and workforce, and comparing
performance against the Scottish average. Reporting does
not separately cover outcomes resulting from the
transformational review programme, but the council’s
transformation work contributes to the delivery of these
broader outcomes. 
• The council has advised that transformation impact is
tracked through budget reporting, focussing on savings
targets. Broader service areas report separately to
committees using tailored metrics. Interviewees noted that
success is often defined by the ability to continue operating
and delivering services within a reduced budget.
• As set out in the Programme Management section of this
report, regular updates on the progress of reviews are
reported to the CMT efficiencies workstream alongside
updates to elected members through the Performance and
Review Scrutiny Forum. Our analysis shows that the
impact of transformational activity on outcomes and non-
financial benefits is not being monitored or reported on,
and that updates to CMT and elected members lack
94

Page 95

Impact of transformation | 19 
Findings Evidence
specific examples of quantified benefits already realised or
metrics in place to measure success. 
• The council acknowledges that as transformation work
matures, there is a need to track and report outcomes. The
Performance and Review Scrutiny Forum will become the
main platform for this. 
• We note the council’s ongoing work to develop a benefits
tracker in relation to its review of Digital Transformation to
ensure both cashable and non-cashable benefits are
identified, tracked and realised through the programme.
We welcome this recent development and recommend the
approach is broadened to include all of South Lanarkshire
Council’s transformational work. 
• As set out in the Partnership Working section of the report
above, the council has provided two examples of
successful transformation projects. The impacts to date
from the two projects are set out below:
- Analogue to Digital ARC solutions project – The
council has reported improvements in service quality
through better data visibility and system performance.
The key outcome is helping people stay in their homes
and avoiding long-term care or hospital admissions,
though this impact is not yet quantified. The aim of the
project was service improvement, therefore there are
no cost savings associated with the project. 
- SLC Futures Project - In January 2025, the council
reported £0.230 million in savings for 2024/25, with
projected savings of £1 million in 2025/26 and £1.6
million annually by the end of the programme. Key
non-financial benefits include improved tenancy
sustainment and enhanced life skills for young people
The council has adopted The Scottish Housing
Regulator Annual Return on Charter Indicator 16
(Percentage of new tenancies sustained for more than
a year) as a key baseline measure of success in
relation to tenancy sustainment for this project. 
The council carries out
Integrated Impact
Assessments for its
transformational reviews to
consider the potential
changes to services on
vulnerable groups and
there are examples of
community engagement
• The council carries out Integrated Impact Assessments for
its transformational reviews and there are examples of
community engagement taking place in relation to these.
These are publicly available on the council’s website.
Some examples are highlighted below:
- The Integrated Impact Assessment for the Council’s
proposed charges policy aims to apply a 14.4 per
cent inflationary increase across all non-statutory
council charges, in addition to a 1.5 per cent year on
year inflationary increase from 2025/26. The aim is to
95

Page 96

Impact of transformation | 20 
Findings Evidence
taking place in relation to
these.   
achieve full cost recovery for the services it provides,
as well as providing financial sustainability and
protecting frontline services going forward. A public
consultation was undertaken between November 2024
and January 2025, widely promoted through various
channels. It received over 3,000 responses, with the
majority of respondents supporting the proposed
increases. A separate consultation was also designed
for children and young people to ensure their views
were considered. The IIA considers groups which may
experience greater impact such as unemployed
people, single parents and those living in areas of
deprivation. To address potential negative impacts the
council has sets out mitigation strategies, such as
concessions, exemptions for disabled blue badge
holders and access to travel schemes for young and
elderly groups. The council commits to ongoing
monitoring and consultation to assess the impact of the
proposed changes going forward. 
- The Integrated Impact Assessment for the council’s
cross-cutting review of Loans Fund and Service
Concessions aims to implement changes in
accounting practice for loan charges (council debt) and
service concessions (PPP payments for secondary
schools) to reduce costs over the next three years. The
council carried out consultation on this proposal as part
of the engagement for its annual budget process and
the results showed 60 per cent of responders agreed
with the proposal. The IIA considers the impact of the
proposed changes on vulnerable groups but concludes
there is no impact on them given the proposal is a
technical accounting change and is not related to
service delivery. It also notes that not implementing the
proposal could lead to greater service reductions,
which might inadvertently affect vulnerable groups. 
- The Integrated Impact Assessment for the 2025/26
Financial Savings Budget Strategy identifies
cumulative impacts of the council’s budget savings on
those with protected characteristics. The IIA identifies
age, disability and sex as the characteristics most
likely to be affected, as well as socio-economic groups
such as low-income households, those experiencing
deprivation and children and young people, particularly
those additional support needs. A range of specific
proposals are identified as having negative impacts,
such as charging for early years services and school
meals. A public consultation was carried out in relation
96

Page 97

Impact of transformation | 21 
Recommendation 4
The council should prioritise establishing a framework that identifies and
monitors the estimated and realised impact to date of its transformation
work, including on service delivery and on outcomes for service users. It
should report to CMT and elected members on both the financial and
non-financial impact of the full range of its transformational activities.
Findings Evidence
to this as part of the council’s annual budget process
and changes made as a result of the impact
assessment will include mitigations in the form of
exemptions for households meeting eligibility criteria
for school meals and early years charges. 
97

Page 98

Appendix | 22 
Appendix
Improvement action plan
Issue/risk Recommendation
Agreed management
action/timing
1. Transformation ambition
The council has significant
budget savings to make over the
next three years and beyond and
is aware that it must explore
further options for transformation
to help bridge its funding gap and
improve outcomes for the people
of South Lanarkshire. 
There is a risk that the council
may not be able to deliver
sustainable services if the
required savings are not
achieved. 
The council should ensure its
plans for transformation are
sufficiently ambitious to
ensure that it can continue to
deliver sustainable services,
prioritising transformational
activities that will deliver the
most impact and contribute to
reducing the budget gap.
The Council continues to
progress a long term
schedule of
transformational reviews
which run in parallel with
the Budget process, in
order to maximise the
impact on the Budget
Gap. 
Executive Director of
Finance and Corporate
Resources / Corporate
Management Team.
September 2025
2. Resourcing transformation
The council has advised that
delivering transformation is part
of the jobs of managers, heads of
service and directors and the
council has periodically hired
external support to help capacity.
It has an officer in place to
support project teams with the
administrative tasks of the
transformation programme. 
There is a risk that the council’s
Transformational Change
Programme will lose momentum
if it does not have the sufficient
dedicated resource to drive the
activity required.
The council should assess
whether its arrangements for
resourcing transformation
activities are sufficient to drive
the scale and pace of change
required in future. 
The role of senior officers
in the Council includes
managing change and
the work around
transformation forms part
of that role. The
arrangements for
resourcing transformation
across the Council will
continue to be monitored,
and as is currently the
case, additional
resources will be
deployed as and when
required.  
Executive Director of
Finance and Corporate
Resources / Corporate
Management Team.
Ongoing as required 
98

Page 99

Appendix | 23 
Issue/risk Recommendation
Agreed management
action/timing
3. Demonstrating the impact of
community engagement on
transformational activities
The council has shared examples
of how it has engaged or
consulted with communities in
relation to its transformational
reviews and budget process. It is
unclear what specific changes
have been made as a result of
this engagement as this has not
been clearly demonstrated. 
There is a risk that the council is
not viewed to have considered
community views when
prioritising which transformational
projects to be taken forward.
The council should ensure it
demonstrates how
engagement with
communities, including
vulnerable groups, has
informed planned changes to
services. 
The Council will consider
adding a final stage to
the Budget Consultation
process for the
2026/2027 exercise, to
ensure outcomes are fed
back to communities. 
This will include feedback
on the impact of
consultation on
Transformational
Reviews.
Head of Finance
(Strategy)
March 2026
4. Measuring the impact of
transformational activities
The council currently focuses on
establishing the financial benefits
of its transformational activities
but does not track or report
separately on the impact on
service quality or outcomes for
service users in relation to these
transformational activities.
There is a risk that, when
prioritising which transformational
activities to take forward, the
council does not have adequate
information on impact to make a
fully-informed decision. 
The council should prioritise
establishing a framework that
identifies and monitors the
estimated and realised impact
to date of its transformation
work, including on service
delivery and on outcomes for
service users. It should report
to CMT and elected members
on both the financial and non-
financial impact of the full
range of its transformational
activities. 
The Council will develop
a framework to capture
estimated and actual
impacts from
transformation activities. 
An annual report will be
produced which will
provide a summary of the
outcomes from the
Transformational Review
Programme.
Executive Director of
Finance and Corporate
Resources / Corporate
Management Team
June 2026
99

Page 100

South Lanarkshire Council 
Best Value thematic management report 
Transformation: how councils are redesigning and
delivering more efficient services to achieve planned
outcomes 
Audit Scotland, 4th Floor, 102 West Port, Edinburgh EH3 9DN
Phone: 0131 625 1500 Email: info@audit.scot
www.audit.scot 
AS.5.0
100

Page 101

8 Nelson Mandela Place
Glasgow 
G2 1BT 
T: 0131 625 1500
E: info@audit-scotland.gov.uk
www.audit-scotland.gov.uk 
Risk and Audit Scrutiny Committee
30 September 2025
South Lanarkshire Council Charitable Trusts (SC025089)
Audit of 2024/25 annual accounts
Independent Auditor’s Report
Our audit work on the 2024/25 annual accounts is now substantially complete. Subject to
receipt of a revised set of annual accounts for final review, we anticipate being able to issue
unmodified audit opinions in the independent auditor's report on 30 September 2025 (the
proposed report is attached at (Appendix A). 
Annual Audit Report
Under International Standards on Auditing in the UK, we report specific matters arising from the
audit of the financial statements to those charged with governance of a body in sufficient time to
enable appropriate action. We present for the trustees’ consideration our proposed annual audit
report for South Lanarkshire Council Charitable Trusts (SC025089) on the 2024/25 audit. There
are no significant findings or key audit matters to report.
The Annual Audit Report also sets out conclusions on the wider scope areas that frame public
audit as set out in the Code of Audit Practice.
The Annual Audit Report will be issued in final form after the audit of the annual accounts has
been completed.
Uncorrected misstatements
We also report to those charged with governance all uncorrected misstatements in the annual
accounts which we have identified during the course of our audit, other than those of a trivial
nature, and request that these misstatements be corrected.
There are no uncorrected misstatements to report. 
Other ISA (UK) matters
In presenting this letter and the Annual Audit Report to the Risk and Audit Scrutiny Committee,
we seek confirmation from those charged with governance on the following matters: 
• if they are aware of any instances of actual, suspected, or alleged fraud, 
• if they are aware of any subsequent events that have occurred since the date of the
financial statements,
• if they are content that the methods, assumptions, and data used in making accounting
estimates in the annual accounts are appropriate, 
• if all related party relationships and transactions they are aware of are reflected in the
annual accounts, and
3c
101

Page 102

• if they are aware of any non-compliance with laws and regulations. 
Any issues that we have identified from our audit in relation to other ISA (UK) matters that we
are required to report to those charged with governance have been reported in the section
headed “Other matters to report” in the Annual Audit Report. 
Representations from the Section 95 Officer
As part of the completion of the audit, we are seeking written representations from the
Executive Director (Finance and Corporate Resources), who is the Section 95 Officer, on
aspects of the annual accounts, including the judgements and estimates made.
A draft letter of representations is attached at Appendix B. This should be signed and returned
to us by the Section 95 Officer with the signed annual accounts prior to the Independent
Auditor’s Report being signed. 
102

Page 103

Appendix A: Proposed Independent Auditor’s Report
Independent auditor’s report to the trustees of South
Lanarkshire Council Charitable Trusts (SC025089) and the
Accounts Commission
Reporting on the audit of the financial statements
Opinion on financial statements
I certify that I have audited the financial statements in the statement of accounts of South
Lanarkshire Council Charitable Trusts (SC025089) for the year ended 31 March 2025 under
Part VII of the Local Government (Scotland) Act 1973 and section 44(1)(c) of the Charities and
Trustee Investment (Scotland) Act 2005. The financial statements comprise the Statement of
Receipts and Payments, the Statement of Balances, and notes to the financial statements. The
financial reporting framework that has been applied in their preparation is applicable law and a
receipts and payments basis.
In my opinion the accompanying financial statements:
•  properly present the receipts and payments of the charity for the year
ended 31 March 2025 and its statement of balances at that date; and
• have been prepared in accordance with the requirements of the
Charities and Trustee Investment (Scotland) Act 2005, and regulations
9(1),(2) and (3) of The Charities Accounts (Scotland) Regulations 2006.
Basis for opinion
I conducted my audit in accordance with applicable law and International Standards on Auditing
(UK) (ISAs (UK)), as required by the Code of Audit Practice approved by the Accounts
Commission for Scotland. My responsibilities under those standards are further described in the
auditor’s responsibilities for the audit of the financial statements section of my report. I am
independent of the charity in accordance with the ethical requirements that are relevant to my
audit of the financial statements in the UK including the Financial Reporting Council’s Ethical
Standard, and I have fulfilled my other ethical responsibilities in accordance with these
requirements. I believe that the audit evidence I have obtained is sufficient and appropriate to
provide a basis for my opinion.
Responsibilities of the trustees for the financial statements
The trustees are responsible for the preparation of financial statements that give a true and fair
view in accordance with the financial reporting framework, and for such internal control as the
trustees determines is necessary to enable the preparation of financial statements that are free
from material misstatement, whether due to fraud or error.
Auditor’s responsibilities for the audit of the financial statements
My objectives are to obtain reasonable assurance about whether the financial statements as a
whole are free from material misstatement, whether due to fraud or error, and to issue an
auditor’s report that includes my opinion. Reasonable assurance is a high level of assurance,
but is not a guarantee that an audit conducted in accordance with ISAs (UK) will always detect a
material misstatement when it exists. Misstatements can arise from fraud or error and are
considered material if, individually or in the aggregate, they could reasonably be expected to
influence the economic decisions of users taken on the basis of these financial statements.
103

Page 104

Irregularities, including fraud, are instances of non-compliance with laws and regulations. I
design procedures in line with my responsibilities outlined above to detect material
misstatements in respect of irregularities, including fraud. Procedures include:
• using my understanding of the local government sector and charity
sector to identify that the Local Government (Scotland) Act 1973,
Charities and Trustee Investment (Scotland) Act 2005 and The
Charities Accounts (Scotland) Regulations 2006 are significant in the
context of the charity;
• inquiring of the Trustees as to other laws or regulations that may be
expected to have a fundamental effect on the operations of the charity;
• inquiring of the Trustees concerning the charity’s policies and
procedures regarding compliance with the applicable legal and
regulatory framework;
• discussions among my audit team on the susceptibility of the financial
statements to material misstatement, including how fraud might occur;
and
• considering whether the audit team collectively has the appropriate
competence and capabilities to identify or recognise non-compliance
with laws and regulations.
The extent to which my procedures are capable of detecting irregularities, including fraud, is
affected by the inherent difficulty in detecting irregularities, the effectiveness of the charity’s
controls, and the nature, timing and extent of the audit procedures performed.
Irregularities that result from fraud are inherently more difficult to detect than irregularities that
result from error as fraud may involve collusion, intentional omissions, misrepresentations, or
the override of internal control. The capability of the audit to detect fraud and other irregularities
depends on factors such as the skilfulness of the perpetrator, the frequency and extent of
manipulation, the degree of collusion involved, the relative size of individual amounts
manipulated, and the seniority of those individuals involved.
A further description of the auditor’s responsibilities for the audit of the financial statements is
located on the Financial Reporting Council's website www.frc.org.uk/auditorsresponsibilities.
This description forms part of my auditor’s report.
Reporting on other requirements
Other information 
The trustees are responsible for the other information in the statement of accounts. The other
information comprises the Trustees’ Annual Report. 
My responsibility is to read all the other information and, in doing so, consider whether the other
information is materially inconsistent with the financial statements or my knowledge obtained in
the course of the audit or otherwise appears to be materially misstated. If I identify such material
inconsistencies or apparent material misstatements, I am required to determine whether this
gives rise to a material misstatement in the financial statements themselves. If, based on the
work I have performed, I conclude that there is a material misstatement of this other information,
I am required to report that fact. I have nothing to report in this regard.
104

Page 105

My opinion on the financial statements does not cover the other information and I do not
express any form of assurance conclusion thereon except on the Trustees’ Annual Report to the
extent explicitly stated in the following opinion prescribed by the Accounts Commission.
Opinions prescribed by the Accounts Commission on the Trustees’ Annual Report
In my opinion, based on the work undertaken in the course of the audit, the information given in
the Trustees' Annual Report for the financial year for which the financial statements are
prepared is consistent with the financial statements and that report has been prepared in
accordance with The Charity Accounts (Scotland) Regulations 2006.
Matters on which I am required to report by exception
I am required by The Charity Accounts (Scotland) Regulations 2006 to report to you if, in my
opinion:
• proper accounting records have not been kept; or
• the financial statements are not in agreement with the accounting
records; or
• I have not received all the information and explanations I require for my
audit.
I have nothing to report in respect of these matters.
Use of my report
This report is made solely to the parties to whom it is addressed in accordance with Part VII of
the Local Government (Scotland) Act 1973 and for no other purpose. In accordance with
paragraph 108 of the Code of Audit Practice, I do not undertake to have responsibilities to
members or officers, in their individual capacities, or to third parties.
Mark Ferris FCCA
Senior Audit Manager 
Audit Scotland 
4th Floor South Suite 
The Athenaeum Building 
8 Nelson Mandela Place 
Glasgow 
G2 1BT
Mark Ferris is eligible to act as an auditor in terms of Part VII of the Local
Government (Scotland) Act 1973. 
105

Page 106

Appendix B: Letter of Representations (ISA (UK) 580) 
Mark Ferris, Senior Audit Manager
Audit Scotland
4th Floor
8 Nelson Mandela Place
Glasgow 
G2 1BT
Dear Mark
South Lanarkshire Council Charitable Trusts (SC025089)
Annual accounts 2024/25
1.  This representation letter is provided in connection with your audit of the annual accounts of
South Lanarkshire Council Charitable Trusts for the year ended 31 March 2025 for the purpose
of expressing an opinion as to whether the financial statements give a true and fair view and for
expressing other opinions on the information within the annual report and financial statements.
2.  I confirm to the best of my knowledge and belief and having made appropriate enquiries of
the trustees of the registered charities where South Lanarkshire Council is the sole trustee, the
following representations given to you in connection with your audit of annual accounts for the
year ended 31 March 2025.
General
3.  I have fulfilled my responsibilities for the preparation of the 2024/25 annual accounts as set
out in your 2024/25 Annual Audit Plan. All the accounting records, documentation, and other
matters which I am aware are relevant to the preparation of the annual accounts have been
made available to you for the purposes of your audit. All transactions undertaken by South
Lanarkshire Council Charitable Trusts have been recorded in the accounting records and are
properly reflected in the financial statements. 
4.  I confirm that the effects of uncorrected misstatements are immaterial, individually and in
aggregate, to the financial statements as a whole. As you have reported, there are no
uncorrected misstatements. 
Financial Reporting Framework
5.  The annual accounts have been prepared under Part VII of the Local Government (Scotland)
Act 1973 and section 44(1)(c) of the Charities and Trustee Investment (Scotland) Act 2005 and
regulations 9(1),(2) and (3) of The Charities Accounts (Scotland) Regulations 2006.
6.  In accordance with the Local Authority Accounts (Scotland) Regulations 2014, I have ensured
that the financial statements give a true and fair view of the financial position of South
Lanarkshire Council Charitable Trusts at 31 March 2025 and the transactions for 2024/25.
Accounting Policies and Estimates
7.  All material accounting policies applied are as shown in the note included in the financial
statements. The accounting policies are determined by the 2024/25 Code, where applicable.
Where the 2024/25 Code does not specifically apply, I have used judgement in developing and
applying an accounting policy that results in information that is relevant and reliable. All
accounting policies applied are appropriate to South Lanarkshire Council Charitable Trusts
circumstances and have been consistently applied.
106

Page 107

8.  The methodology, significant assumptions, and data used in making accounting estimates
are reasonable, and have been properly reflected and disclosed in the financial statements in
accordance with the 2024/25 Code. Judgements made in making estimates have been based
on the latest available and reliable information. Estimates have been revised where there are
changes in the circumstances on which the original estimate was based or as a result of new
information or experience.
Going Concern Basis of Accounting
9.  I have assessed South Lanarkshire Council Charitable Trusts’ ability to continue to use the
going concern basis of accounting and have concluded that it is appropriate. I am not aware of
any material uncertainties that may cast significant doubt on South Lanarkshire Council
Charitable Trusts’ ability to continue to adopt the going concern basis of accounting. 
Fraud
10.  I understand my responsibilities for the design, implementation, and maintenance of internal
control to prevent fraud and I believe I have appropriately fulfilled those responsibilities. 
11.  I have provided you with all information in relation to:
• my assessment of the risk that the financial statements may be materially misstated as
a result of fraud, 
• any allegations of fraud or suspected fraud affecting the financial statements, and 
• fraud or suspected fraud that I am aware of involving management, employees who
have a significant role in internal control, or others that could have a material effect on
the financial statements. 
Laws and Regulations
12.  I have disclosed to you all known instances of non-compliance or suspected non-
compliance with laws and regulations whose effects should be considered when preparing
financial statements.
Related Party Transactions
13.  All material transactions with related parties have been appropriately accounted for and
disclosed in the financial statements in accordance with IAS 24, as adopted by the 2024/25
Code. I have made available to you the identity of all of South Lanarkshire Council Charitable
Trusts’ related parties and all the related party transactions of which I am aware.
Corporate Governance
14.  The business of the charitable trust is recorded in the systems of South Lanarkshire
Council. As section 95 officer for South Lanarkshire Council, I confirm that there are no issues
or deficiencies in internal control that require to be disclosed within the annual accounts of the
charitable trust.
Events Subsequent to the Date of the Balance Sheet
15.  All events subsequent to 31 March 2025 for which IAS 10, as adopted by the 2024/25
Code, requires adjustment or disclosure have been adjusted or disclosed. 
Yours sincerely
Accountable Officer
107

Page 108

South Lanarkshire Council
Charitable Trusts (SC025089)
2024/25 Annual Audit Report - Proposed 
Prepared for South Lanarkshire Council Charitable Trust
September 2025
108

Page 109

South Lanarkshire Council Charitable Trusts (SC025089): 2024/25 Annual Audit Report -
Proposed | 2 
Contents 
Key messages 3
Introduction 4
Audit scope and responsibilities 5
Audit of the annual accounts 7
Financial Sustainability and Best Value audit 11 
Accessibility
You can find out more and read this report using assistive technology on
our website www.audit.scot/accessibility.
109

Page 110

Key messages | 3 
Key messages 
Audit of the annual accounts
1 All audit opinions stated that the annual accounts were free from material
misstatement. 
2 There were no significant findings or key audit matters to report. All audit
adjustments required to correct the financial statements were processed by
South Lanarkshire Council Charitable Trusts.
Wider scope and Best Value audit
3 South Lanarkshire Council Charitable Trusts has effective and appropriate
arrangements in place for Financial Sustainability and for securing Best
Value. 
110

Page 111

Introduction | 4 
Introduction 
Purpose of the Annual Audit Report
1.  The purpose of this Annual Audit Report is to report the significant
matters identified from the 2024/25 audit of South Lanarkshire Council
Charitable Trusts annual accounts and the wider scope areas specified in
the Code of Audit Practice (2021).
2.  The Annual Audit Report is addressed to South Lanarkshire Council
Charitable Trusts and the Controller of Audit, and will be published on
Audit Scotland’s website in due course. 
Appointed auditor and independence
3.  Mark Ferris, of Audit Scotland, has been appointed as external auditor
of South Lanarkshire Council Charitable Trusts for the period from 2022/23
until 2026/27. As reported in the Annual Audit Plan, Mark Ferris as
engagement lead and the audit team are independent of South
Lanarkshire Council Charitable Trusts in accordance with relevant ethical
requirements, including the Financial Reporting Council’s Ethical
Standard. There have been no developments since the issue of the Annual
Audit Plan that impact on the continued independence of the engagement
lead or the rest of the audit team from South Lanarkshire Council
Charitable Trusts, including no provision of non-audit services. 
Acknowledgements
4.  We would like to thank the Charitable Trust and its staff, particularly
those involved in preparation of the annual accounts, for their cooperation
and assistance during the audit. We look forward to working together
constructively over the remainder of the five-year audit appointment.
111

Page 112

Audit scope and responsibilities | 5 
Audit scope and responsibilities 
Scope of the audit 
5.  The audit is performed in accordance with the Code of Audit Practice,
including supplementary guidance, International Standards on Auditing
(ISA) (UK), and relevant legislation. These set out the requirements for the
scope of the audit which includes: 
• An audit of the financial statements and an opinion on whether they
give a true and fair view and are free from material misstatement. 
• An opinion on statutory other information published with the
financial statements in the annual accounts and the Trustees
Report.
• Concluding on the financial sustainability of South Lanarkshire
Council Charitable Trusts.
• Reporting on South Lanarkshire Council Charitable Trusts
arrangements for securing Best Value.
• Provision of this Annual Audit Report.
Responsibilities and reporting
6.  The Code of Audit Practice sets out the respective responsibilities of the
body and the auditor. A summary of the key responsibilities is outlined
below. 
Auditor’s responsibilities
7.  The responsibilities of auditors in the public sector are established in
the Local Government (Scotland) Act 1973. These include providing an
independent opinion on the financial statements and other information
reported within the annual accounts, and concluding on South Lanarkshire
Council Charitable Trusts arrangements in place for the wider scope areas
and Best Value.
8.  The matters reported in the Annual Audit Report are only those that
have been identified by the audit team during normal audit work and may
not be all that exist. Communicating these does not absolve the body from
its responsibilities outlined below. 
9.  The Annual Audit Report includes an agreed action plan at Appendix 1
setting out specific recommendations to address matters identified and
includes details of the responsible officer and dates for implementation.
112

Page 113

Audit scope and responsibilities | 6 
South Lanarkshire Council Charitable Trusts responsibilities
10.  South Lanarkshire Council Charitable Trusts has primary responsibility
for ensuring proper financial stewardship of public funds, compliance with
relevant legislation and establishing effective arrangements for
governance, propriety, and regularity that enables it to successfully deliver
its objectives. The features of proper financial stewardship include: 
• Establishing arrangements to ensure the proper conduct of
its affairs. 
• Preparation of annual accounts, comprising financial statements for
the body that gives a true and fair view and other specified
information. 
• Establishing arrangements for the prevention and detection of
fraud, error and irregularities, and bribery and corruption. 
• Implementing arrangements to ensure its financial position is
soundly based. 
• Making arrangements to secure Best Value. 
• Establishing an internal audit function.
113

Page 114

Audit of the annual accounts | 7 
Audit of the annual accounts 
Main judgements
All audit opinions stated that the annual accounts were free from
material misstatement. 
There were no significant findings or key audit matters to report. All audit
adjustments required to correct the financial statements were processed
by South Lanarkshire Council Charitable Trusts.
Audit opinions on the annual accounts
11.  South Lanarkshire Council Charitable Trusts annual accounts were
approved by the Risk and Audit Scrutiny Committee on 30 September
2025 and certified by the appointed auditor on 30 September 2025. The
Independent Auditor’s Report is included in South Lanarkshire Council
Charitable Trusts annual accounts, and this reports that, in the appointed
auditor’s opinion, these were free from material misstatement. 
Audit timetable 
12.  The unaudited annual accounts and all working papers were received
on 26 June 2025 in accordance with the agreed audit timetable.
Audit Fee
13.  The audit fee for the 2024/25 audit was reported in the Annual Audit
Plan and was set at £2,000. There have been no developments that
impact on planned audit work required, therefore the audit fee reported in
the Annual Audit Plan remains unchanged. 
Materiality
14.  The concept of materiality is applied by auditors in planning and
performing an audit, and in evaluating the effect of any uncorrected
misstatements on the financial statements or other information reported in
the annual accounts.
15.  Broadly, the concept of materiality is to determine whether
misstatements identified during the audit could reasonably be expected to
influence the decisions of users of the annual accounts. Auditors set a
monetary threshold when determining materiality, although some issues
114

Page 115

Audit of the annual accounts | 8 
may be considered material by their nature. Therefore, materiality is
ultimately a matter of the auditor’s professional judgement.
16.  Materiality levels for the audit of South Lanarkshire Council Charitable
Trusts were determined at the risk assessment phase of the audit and
were reported in the Annual Audit Plan, which also reported the
judgements made in determining materiality levels. These were
reassessed on receipt of the unaudited annual accounts. No changes
were required to the materiality levels, which are outlined in Exhibit 1.
Exhibit 1
2024/25 Materiality levels for the body
Materiality Charitable Trust
Materiality – set at 2 per cent of the benchmark. £24,210
Performance materiality – set at 75 per cent of planning
materiality. As outlined in the Annual Audit Plan, this acts as
a trigger point. If the aggregate of misstatements identified
during the audit exceeds performance materiality, this could
indicate further audit procedures are required. 
£18,158
Reporting threshold – all misstatements greater than the
reporting threshold will be reported.
£1,210
Source: Audit Scotland
Significant findings and key audit matters 
17.  ISA (UK) 260 requires auditors to communicate significant findings
from the audit to those charged as governance, which for South
Lanarkshire Council Charitable Trusts is the Risk and Audit Scrutiny
Committee.
18.  The Code of Audit Practice also requires public sector auditors to
communicate key audit matters. These are the matters that, in the
auditor’s professional judgement, are of most significance to the audit of
the financial statements and require most attention when performing
the audit. 
19.  In determining key audit matters, auditors consider:
• Areas of higher or significant risk of material misstatement. 
• Areas where significant judgement is required, including accounting
estimates that are subject to a high degree of estimation
uncertainty. 
• Significant events or transactions that occurred during the year.
115

Page 116

Audit of the annual accounts | 9 
20.  There are no significant findings or key audit matters to report.
Qualitative aspects of accounting practices 
21.  ISA (UK) 260 also requires auditors to communicate their view about
qualitative aspects of the body’s accounting practices, including
accounting policies, accounting estimates, and disclosures in the financial
statements.
Accounting policies 
22.  The appropriateness of accounting policies adopted by South
Lanarkshire Council Charitable Trusts was assessed as part of the audit.
These were considered to be appropriate to the circumstances of South
Lanarkshire Council Charitable Trusts, and there were no significant
departures from the accounting policies set out in the Code of Practice on
Local Authority Accounting in the United Kingdom (the Code). 
Disclosures in the financial statements
23.  The adequacy of disclosures in the financial statements was assessed
as part of the audit. The quality of disclosures was adequate.
Significant matters discussed with management
24.  All significant matters identified during the audit and discussed with the
Charitable Trust’s management have been reported in the Annual Audit
Report. 
Audit adjustments
25.  There was one audit adjustment required to the financial statements to
include £1,297 for cash and short-term maturity bonds in the investments
balance which had been omitted from the unaudited accounts.
Significant risks of material misstatement identified in the
Annual Audit Plan
26.  Audit work has been performed in response to the significant risks of
material misstatement identified in the Annual Audit Plan. The outcome of
audit work performed is summarised in Exhibit , (page 10).
116

Page 117

Audit of the annual accounts | 10 
Exhibit 2
Significant risks of material misstatement to the financial statements
Risk of material
misstatement Planned audit response Outcome of audit work
Fraud caused by
management override
of controls 
Management is in a
unique position to
perpetrate fraud
because of
management’s ability to
override controls that
otherwise appear to be
operating effectively.
The audit team will:
• Evaluate the design and
implementation of controls
over journal entry
processing.
• Make inquiries of individuals
involved in the financial
reporting process about
inappropriate or unusual
activity relating to the
processing of journal entries
and other adjustments.
• Test journals entries,
focusing on those that are
assessed as higher risk.
• Evaluate significant
transactions outside the
normal course of business.
• Assess the adequacy of
controls in place for
identifying and disclosing
related party relationships
and transactions in the
financial statements. 
Audit work performed found:
• The design and
implementation of controls
over journal processing were
appropriate. 
• No inappropriate or unusual
activity relating to the
processing of journal entries
was identified from discussions
with individuals involved in
financial reporting. 
• No significant issues were
identified from testing of
journal entries. 
• No significant issues were
identified from transactions
outside the normal course of
business. 
• The controls in place for
identifying and disclosing
related party relationships and
transactions were adequate. 
Conclusion: no evidence of
fraud caused by management
override of controls. 
Source: Audit Scotland
117

Page 118

Financial Sustainability and Best Value audit | 11 
Financial Sustainability and Best
Value audit 
Conclusion
The Charitable Trust has effective and appropriate arrangements in
place for Financial Sustainability and for securing Best Value. 
Audit approach to wider scope and Best Value
Wider scope
27.  The Annual Audit Plan reported South Lanarkshire Council Charitable
Trusts was considered to be a less complex body for the wider scope
audit. Therefore, the wider scope audit does not cover all four wider scope
areas and is instead limited to concluding on the financial sustainability of
South Lanarkshire Council Charitable Trusts.
Duty of Best Value
28.  The duty on auditors to consider the arrangements in place to secure
Best Value applies to the body as it falls within section 106 of the Local
Government (Scotland) Act 1973.
29.  Consideration of the arrangements South Lanarkshire Council
Charitable Trusts has in place to secure Best Value has been carried out
alongside the wider scope audit. 
Conclusions on Financial Sustainability
30.  The audit work performed on the arrangements South Lanarkshire
Council Charitable Trusts has in place for securing financial sustainability
found that these were effective and appropriate. This judgement is
evidenced by South Lanarkshire Council Charitable Trusts: 
• having effective arrangements in place for identifying risks to
financial sustainability over the medium and longer-term, and
understanding medium and longer-term demand pressures that
could impact on available resources. 
118

Page 119

Financial Sustainability and Best Value audit | 12 
Conclusions on Duty of Best Value
31.  The audit work performed on the arrangements South Lanarkshire
Council Charitable Trusts has in place for securing Best Value found these
were effective and appropriate. This judgement is evidenced by:
• South Lanarkshire Council Charitable Trusts having well
established and effective governance arrangements in place. 
• the arrangements South Lanarkshire Council Charitable Trusts has
in place to secure financial sustainability which help ensure the
effective use of available resources. 
119

Page 120

South Lanarkshire Council
Charitable Trusts (SC025089)
2024/25 Annual Audit Report - Proposed 
Audit Scotland, 4th Floor, 102 West Port, Edinburgh EH3 9DN
Phone: 0131 625 1500 Email: info@audit.scot
www.audit.scot 
AS.5.0
120

Page 121

Report
Agenda Item 
Report to: Risk and Audit Scrutiny Committee
Date of Meeting: 30 September 2025
Report by: Executive Director (Finance and Corporate Resources)  
Subject: Audited Annual Accounts 2024/2025 
1. Purpose of Report
1.1. The purpose of the report is to:-
[purpose]
 advise members of the requirement to approve the Annual Accounts 2024/2025
for signature, both Council and related Charitable Trusts 
[1purpose]
2. Recommendation(s)
2.1. The Committee is asked to approve the following recommendation(s):-
[recs]
(1) that it be noted that the South Lanarkshire Council Accounts 2024/2025 and
the Charitable Accounts have received a clean audit certificate;
(2) that the audited South Lanarkshire Council Accounts 2024/2025 and the
Charitable Trusts’ Accounts be approved for signature; 
(3) that it be noted that the External Auditor’s Report will be referred to South
Lanarkshire Council for information; and
(4) that it be noted that the Audited Accounts 2024/2025 will be available on the
Council’s website (paragraph 3.6). 
[1recs]
3. Background
3.1. Following the publication of The Local Authority Accounts (Scotland) Regulations
2014, the members of the Committee are required to meet to consider approval of the
Audited Accounts for signature. 
3.2. The submission date for local government is generally set to be consistent with the
date specified in accounts regulations by which a body is required to approve its
audited annual accounts. For 2024/2025, the submission date is 30 September
2025.   
3.3. The members are also required to have regard to any report made or advice provided
on the Annual Accounts by the External Auditor. 
3.4. The External Auditor’s Report was included as an earlier report to this meeting and
will be referred to a meeting of South Lanarkshire Council for information. 
3.5. Copies of the (unsigned) Audited Accounts 2024/2025, for both the Council and
Related Charities, have been emailed to members of this Committee under separate
cover.  Copies of the Council’s Audited Accounts, the Charitable Trusts’ Audited
Accounts and the External Auditor’s Report will be issued to all Elected Members for
their information. 
4
121

Page 122

3.6. Once signed, the Audited Accounts will be available to the general public on the
Council’s website and we can arrange to send a copy out to anyone who requests
them. 
4. Audited Accounts – South Lanarkshire Council 
4.1. As noted in paragraph 3.1, members of the Committee are required to approve the
Audited Accounts for signature.  A copy of the Audited Accounts for 2024/2025 are
being emailed to Members of this Committee under separate cover. 
4.2. As detailed in an earlier report to this Committee, at the time of writing, the Council’s
External Auditors, Audit Scotland, are in the process of completing the audit which
extends across the 2024/2025 Accounts and related matters. 
4.3. The report notes that, at the time of writing, the External Auditor has provided a clear
Audit Certificate with no qualifications on the Council’s Accounts. 
4.4. The External Auditor’s Report also includes an agreed action plan at Appendix 1. 
Officers of the Council will work to ensure that these actions are implemented during
2025/2026. 
5. Audited Accounts – Charitable Trusts
5.1. Members of the Committee are required to approve the Charitable Trusts’ Audited
Accounts for signature.  A copy of the Audited Accounts for 2024/2025 have been
emailed to Members of this Committee under separate cover. 
5.2. The External Auditor also reports on the 2 Charitable Trusts managed by the Council:
South Lanarkshire Council Educational Trust and South Lanarkshire Council
Charitable Trust.   
5.3. The External Auditor’s report shows a clear audit certificate for each Trust.   
6. Employee Implications
6.1. There are no direct employee implications from this report. 
7. Financial Implications
7.1. There are no direct financial implications arising from this report.  The Annual Accounts
received a clear audit certificate.  Any changes identified in the External Auditor’s
report have been made and the impact on the Council’s outturn reflected in the Audited
Accounts. 
8. Climate Change, Sustainability and Environmental Implications
8.1. There are no implications for climate change, sustainability or the environment in terms
of the information contained in this report. 
9. Other Implications
9.1. The main risk associated with the Council and Charitable Annual Accounts is a
qualified audit report. The risk has been assessed as low due to the detailed
preparation in relation to the year end process, technical training undertaken by key
finance staff and the roll out of this to Resource finance staff as appropriate. Finance
and Resources work together to achieve key deadlines and actions set from
timetables. 
122

Page 123

10. Integrated Impact Assessment and Consultation Requirements
10.1. This report does not introduce a new policy, function or strategy or recommend a
change to an existing policy, function or strategy and, therefore, no impact assessment
is required.   
10.2. There is also no requirement to undertake any consultation in terms of the information
contained in this report. 
Jackie Taylor
Executive Director (Finance and Corporate Resources) 
19 September 2025 
Link(s) to Council Values/Priorities/Outcomes
 Accountable, effective, efficient and transparent 
Previous References
 None 
List of Background Papers
 South Lanarkshire Council Annual Accounts 2024/2025 and External Auditor’s Report.
 Charitable Trusts’ Annual Accounts 2024/2025 and External Auditor’s Report.
 Financial Ledger 2024/2025 and associated working papers. 
Contact for Further Information
If you would like to inspect the background papers or want further information, please
contact:-
Lorraine O'Hagan, Head of Finance (Strategy)
Ext:  2601  (Tel:  01698 452601)
E-mail:  lorraine.o’hagan@southlanarkshire.gov.uk
123

Page 124

124

Page 125

Report
Agenda Item 
Report to: Risk and Audit Scrutiny Committee
Date of Meeting: 30 September 2025 
Report by: Executive Director (Finance and Corporate Resources)  
Subject: Internal Audit Activity Report       
1. Purpose of Report
1.1. The purpose of the report is to:- 
 update the Risk and Audit Scrutiny Committee (RASC) on the progress,
performance and output from the Internal Audit service in the period 1 June to 31
August 2025. 
2. Recommendation(s)
2.1. The Committee is asked to approve the following recommendation(s):- 
(1) that progress with delivering the 2025/2026 Internal Audit Plan be noted;
(2) that performance in the period to 31 August 2025, as detailed in Appendix 1,
be noted;
(3) that the proposed amendment to the Audit Plan, as set out in paragraph 4.3,
be approved;
(4)  that audit output from assignments completed in the period, as detailed in
appendices 2 and 3, be noted; and
(5)  that the responses to the Accounts Commission Consultation, as detailed in
Appendix 4, be noted. 
3. Executive Summary 
3.1. The Internal Audit Plan for 2025/2026 was approved by the Risk and Audit Scrutiny
Committee (RASC) in February 2025.  A copy of this plan can be found here.  Good
progress has been made with 74% of the Plan in progress at the end of August
2025. A final report has been issued for 14% of assignments in the Plan,
representing reasonable progress at this point in the year.  The following targets
have been set to progress the Plan for the remainder of the year:- 
RASC meeting Assignments to Draft Report Stage
December 2025 29%
March 2026 59%
May 2026 100%1  
3.2. There are no significant concerns at the end of August 2025 around the overall
deliverability of the Plan but, there remains, inherent risks around unforeseen service
demands and, potentially, responding timeously to team up-skilling requirements,
particularly around the development of digital skills.  These risks are mitigated by 
1 This pattern of delivery reflects that the nature of some audit assignments is such that they are delivered
across the financial year and cannot be closed until the end of this period.
5
125

Page 126

inclusion of contingency time within the annual plan, a focus on coaching and
training and setting realistic expectations around the extent to which data analytics
can begin to be incorporated more widely within audit assignments. 
3.3. The risk of significant, subsequent amendments to the Plan, arising from a change in
the Council’s priorities or risks, is managed by a regular re-assessment of capacity
and Audit Plan content to allow incremental adjustments and reporting to the RASC
as the year progresses.   
3.4. Having provided the mandate for an internal audit service to be delivered within
South Lanarkshire Council (which includes the authority, role and responsibilities
under which Internal Audit operates), the Committee should satisfy itself that the
function is fulfilling its mandate.  One element of this is to review how the Service
has performed in the period under review. 
3.5. To assist the Committee in scrutinising performance, a new suite of performance
indicators has been developed.  These are set out in Appendix 1 alongside targets
and an overall assessment as to whether it is anticipated that these will be met by 31
March 2026.  All indicators have been included for completeness, but some are not
reported until the end of the financial year.  The table notes how these are being
progressed in the interim to provide assurance that all aspects of performance are
being managed. 
3.6. There are currently 5 indicators assessed as amber.  A list of these indicators and
planned corrective action is as follows:- 
Indicator Corrective Action
number of processes where we use
continuous control monitoring
to be developed as part of Fusion
programme of testing through to 31 March
2026
number of training days per employee plans to be formalised in Q2
plan completed to draft report stage by 30
April
targets to complete set out at 3.1
Internal Audit recommendations followed up planned work in Q3 and Q4 
3.7. Members are asked to note progress with delivering the approved Plan in the period, 
and that overall performance against delivery targets is positive in the period to 31
August 2025.   
4. Audit Plan Progress
4.1. The last progress report to the Committee was in June 2025 and reported on work
completed in the period 12 April to 30 May 2025. This report covers all work
completed in the period 1 June to 31 August 2025.   
4.2. All assignments from 1 April 2025 will be conducted in conformance with the Global
Internal Audit Standards. Three assignments from 2024/2025 and 7 assignments
from 2025/2026 were completed or closed in the period to 31 August 2025.  These
are as follows:- 
Audit Assignment Scope of Assignment 
Data Breach review of controls 
Capital Monitoring Arrangements review of controls 
Primary School Cash Review review of controls 
External Audit  provision of a full extract of transactions for the year
ended 31 March 2025 
Self-Directed Support see paragraph 4.3
126

Page 127

Audit Assignment Scope of Assignment 
Governance Statement  participation in process to draft 2024/2025 annual
governance statement 
Economic Crime and Corporate
Transparency Act 2023 
review requirements of new legislation, assess
current practice and identify any further actions to
be taken
Housing Allocation review of controls 
2024/2025 Annual Assurance Report preparation of the annual assurance report
Accounts Commission Consultation prepare and submit response to consultation
exercise 
4.3. All of these assignments, except Self Direct Support, were progressed to a final
report.  It is proposed that the planned assignment reviewing Self-Directed Support
arrangements is deferred to 2026/2027 to align with the implementation of Liquid
Logic, a new IT system being implemented by Social Work Resources.  It is intended
that the allocated days for this assignment should be assigned to a substitute audit
to review direct payment arrangements within Social Work Resources.  This audit
has been chosen as some adhoc reviews of the process have been undertaken in
recent years to respond to specific concerns and it is considered that a wider audit of
the process would allow a fuller assessment of all risks and the controls in place to
mitigate. 
4.4. A summary of the audit output for each assignment (listed at 4.2) is detailed in
Appendix 2.  Further information in relation to the one, more significant assignment,
Economic Crime and Corporate Transparency Act 2023, is set out at Appendix 3.
The key points from this include the introduction of a new ‘failure to prevent fraud’
offence from 1 September 2025, which will hold large organisations, including the
Council, to account if they profit from fraud. To ensure compliance with the new
legislation, the Council is taking proactive steps to understand its fraud risk exposure
and review the effectiveness of the measures in place to prevent, detect and
respond to fraud, which should mitigate the risk of corporate criminal liability.
Members should note the detail of this new offence outlined in Appendix 3. 
4.5. Included in Appendix 4 is South Lanarkshire Council’s response to a recent
consultation exercise conducted by the Accounts Commission. 
4.6. In addition to these assignments, 8 assignments were finalised in the same period
for external clients.  Output from these audits will be reported to their respective audit
committees and Boards. 
4.7. Members are asked to note the assignments completed and closed in the period and
approve the proposal to defer one assignment to 2026/2027, replacing with an
assignment to review the process around direct payments. 
5.  Key Findings and Recommendations
5.1. Across all the assignments concluded in the period, Council Resources have
demonstrated a good level of engagement and, where required, an action plan has
been developed and agreed to address areas for improvement.  These actions have
now been logged together with a ‘responsible owner’ and a due date.  Verbal
updates will be obtained when the action falls due.  This is classed as an informal
follow up and included within routine performance indicators reported to RASC. 
Separately, actions will be formally followed up to confirm that there is evidence of
action being taken and the findings of these reviews reported to RASC throughout
the year. 
127

Page 128

5.2. 36 internal audit actions fell due in the period to 31 August 2025.  These are related
to 6 special investigation assignments and a review of capital monitoring
arrangements. 88% have been verbally advised and implemented on time.   
6.  Emerging Risks and Issues
6.1. The annual process to review the Council’s top risks has concluded and is being
reported to this meeting of the RASC. 
6.2. These revised risks have been mapped to the approved 2025/2026 Internal Audit
Plan, with 4 from 5 of the top risks (categorised as very high) within the scope of
planned assignments in 2025/2026. A further 3 from 11 of the top risks (categorised
as high) are within the scope of planned assignments in 2025/2026. 
6.3. New and emerging risks will continue to develop as the year progresses, and there
will be periodic re-assessments of the Plan to ensure that it continues to be risk-
based and aligned to the organisation’s objectives.  Any proposed amendments to
the Plan will be presented to RASC for approval. 
7.  Compliance and Standards Update
7.1. A report that set out the requirements and responsibilities of the new Global Internal
Audit Standards (GIAS), which were effective from 1 April 2025, was presented to
this Committee on 18 February 2025.  A copy of this report can be found here. 
7.2. As an audit committee, the RASC have a key role to play in ensuring that the internal
audit function adheres to the Standards and fulfils its mandate effectively and
efficiently. The RASC demonstrates support for the Service by engaging
constructively with internal audit’s findings, conclusions and advice.   
7.3. The role of audit committees is set out in some detail in Domain 3 “governance of the
Internal Audit function”, the main elements of which are to:- 
 provide the mandate setting out the authority, role and responsibilities under
which Internal Audit operates 
 obtain assurance that Internal Audit is fulfilling its mandate
 review and approve the internal audit charter as reflecting the Committee’s
expectations of the internal audit service that will be delivered within the Council
 meet with the Chief Internal Auditor on a periodic basis
 ‘champion’ and demonstrate support for Internal Audit 
 review the governance, management and reporting arrangements of the
internal audit function 
 assist with setting audit priorities 
 review and approve arrangements for the external assessment 
7.4. The Code of Practice for the Governance of Internal Audit in UK Local Government
Code assists with the interpretation of the new GIAS, but specifically, in relation to
these activity updates, the Committee should be satisfied that the content is such as
to allow them to effectively scrutinise and challenge.     
7.5. A process to map current practice to all elements of the new GIAS is underway, and
in December 2025, a detailed Audit Strategy will be presented to the Committee
ahead of the proposed Audit Plan for 2026/2027 in March 2026.  Progress to align to
the new GIAS can be seen in the revised and extended suite of performance
indicators as set out in Appendix 2 and, together with the presentation of a detailed
Audit Strategy later in the year, will address the 2 main gaps in compliance with
GIAS.
128

Page 129

8. Governance and Committee Engagement
8.1. The Council’s Internal Audit Manager attends all meetings of the RASC.  The
authority of the internal audit function is established through its direct reporting
relationship to the Council’s audit committee, which allows for unrestricted access. 
8.2. Arrangements to allow members of the RASC to meet privately with the Internal
Audit Manager, as required by GIAS, are being finalised and will allow an opportunity
to provide feedback around the revised format of the activity report and to share
suggestions for areas for inclusion in the 2026/2027 Internal Audit Plan. 
8.3. Further one-to-one or group support will continue to be available to Members should
this be required to allow Members to ensure appropriate scrutiny can be undertaken
by them in their role.   
9. Employee Implications 
9.1. There have been no changes to the team in the period to 31 August 2025, and there
are no vacancies within the Service.  Training arrangements are being formalised,
which include regular team briefs, internal training sessions, attendance at
professional body conferences and external seminars and briefings. 
10. Financial Implications
10.1. The Internal Audit plan for the year aligns to the budget that has been set, and
sufficient resources are in place to deliver the approved programme of audit
assignments. 
11. Other Implications
11.1. There are no implications for sustainability in terms of the information contained in
this report. 
12. Integrated Impact Assessment and Consultation Requirements
12.1. There is no requirement to equality assess the contents of this report. Heads of
Service are consulted on each and every audit assignment. 
Jackie Taylor
Executive Director (Finance and Corporate Resources)   
5 September 2025 
Link(s) to Council Values/Priorities/Outcomes
 Accountable, effective, efficient and transparent 
Previous References
 Risk and Audit Scrutiny Committee -  30 January 2025
 Risk and Audit Scrutiny Committee – 6 May 2025 
 Risk and Audit Scrutiny Committee – 25 June 2025 
List of Background Papers
 Figtree extracts of Action Plans 
129

Page 130

Contact for Further Information
If you would like to inspect the background papers or want further information, please
contact:- 
Yvonne Douglas, Internal Audit Manager
Ext:  2618
(Tel:  01698 452618)
E-mail:  yvonne.douglas@southlanarkshire.gov.uk 
130

Page 131

Key audit performance indicators               
Appendix 1  
Measures reported during financial year 
Area Monthly Measure Target  Actual  Status
Operation Number of open vacancies 0 0 
Operation Employees holding a qualification from a recognised CCAB body or Institute of
Internal Auditors  75%  75% 
Operation Number of audits completed that comply with the requirements of Global Internal
Audit Standards 100% 100% 
Operation Number of processes where we use continuous control monitoring 3 1 
Operation Number of training days per employee 5 2 
Operation Plan completed to draft report stage by 30 April   100% 14% 
Performance  Internal Audit recommendations delivered on time 80% 88% 
Performance Utilisation of contingency time by 30 April 100% 29% 
Performance Meetings with Heads of Service during each audit 2 2 
Performance Planned assignments deferred to a future year to accommodate unplanned work 0 0 
Performance Draft reports issued by target date  80% 100% 
Performance Audit assignments completed within budget days 80% 100% 
Performance Internal Audit recommendations followed up 80% 0% 
Performance Top risks covered in the audit plan on an annual basis  33% 44% 
Performance Number of Council Services covered by Audit Plan on an annual basis  33% 62% 
Strategic Number of audits where objectivity or independence is impaired 0 0 
131

Page 132

Area Monthly Measure Target  Actual  Status
Strategic Audits that align to the Council's values 100% 100% 
Strategic Internal Audit Manager attendance at meetings of the RASC 100% 100% 
Strategic Number of formal complaints about the Service 0 0 
Strategic  Audit Plan presented to Risk and Audit Scrutiny Committee March 2025 February 2025 
Strategic Annual Internal Audit Report presented to Risk and Audit Scrutiny Committee June 2025 June 2025 
Measures to be reported at the end of the financial year 
Area Monthly Measure Target  Actual  Status
Operation Number of key performance indicators achieved  100% March 2026 
Performance Planned annual audit days delivered by 30 April 100% March 2026 
Strategic Issue of Service questionnaires to support audit planning process and assess levels
of satisfaction with the Service March 2026 March 2026 
Strategic Audit Strategy presented to Risk and Audit Scrutiny Committee
Ahead of
2026/2027 IA
Plan
Scheduled
December
2025 
Strategic Meetings with 5 Executive Directors and Chief Executive each financial year 1 Scheduled Q3 
Strategic Meeting with members of the Risk and Audit Scrutiny Committee (in private and
without senior management) 1 Scheduled Q3 
132

Page 133

Definition of Measures 
AREA DEFINITION 
Operation measures that assess day to day operational targets for the Service
Performance measures the effectiveness of the Service in its delivery of core objectives
Strategic measures as to how activity aligns to wider organisational objectives 
STATUS DEFINITION 
anticipate that target will not be met by 31 March 2026 
anticipate that target will be met by 31 March 2026 but some slippage that requires corrective action 
anticipate that target will be met by 31 March 2026 
133

Page 134

Assignments completed 1 June to 31 August 2025           Appendix 2 
Number Assignment name Draft Issue Final Issue Audit Conclusion 
I672211 Data Breach 01/06/2025 01/06/2025 Review of arrangements and identification of series of
actions.  An action plan has been agreed.
I674225 Capital Monitoring
Arrangements
09/04/2025 11/07/2025 Review of arrangements and identification of series of
actions.  An action plan has been agreed.
I674233 Primary School Cash
Review
22/04/2025 12/06/2025 Theft of cash.  Review of arrangements and identification of
series of actions.  An action plan has been agreed.
I261122 External Audit Work 05/09/2025 05/09/2025 Provision of financial ledger data to the External Audit for the
year ended 31 March 2025.
I342127 Self-Directed Support 05/09/2025 05/09/2025 Proposed deferment of assignment to 2026/2027.
I350125 Governance Statement 25/06/2025 25/06/2025 Participation in process to draft 2024/2025 Annual
Governance Statement.
I620240 Economic Crime and
Corporate Transparency
Act 2023
05/09/2025 05/09/2025 See Appendix 3.
I672241 Housing Allocation 20/06/2025 20/06/2025 Review of arrangements and identification of series of
actions.  An action plan has been agreed.
I821047 2024/2025 Annual
Assurance Report
25/06/2025 25/06/2025 Preparation and presentation of the 2024/2025 Internal Audit
Annual Assurance report.
I710105 Accounts Commission –
Response to Consultation 
08/08/2025 08/08/2025 See Appendix 4. 
assignments with action plans 
134

Page 135

Appendix 3 
The Economic Crime and Corporate Transparency Act (ECCTA) 2023 
Background 
1.1 The Economic Crime and Corporate Transparency Act (ECCTA) 2023 is a UK law
aimed at combating economic crime, improving corporate transparency, and
reforming Companies House. The Act introduces new measures to prevent fraud,
money laundering, and other financial crimes, as well as reforms as to how
companies are registered and regulated.  Specifically on 1 September 2025, a new
offence failure to prevent fraud is created that is intended to hold large organisations
to account if they profit from fraud. 
1.2. Home Office guidance notes that, under the offence, an organisation may be
criminally liable where an employee, agent, subsidiary, or other ‘associated person2’,
commits a fraud3 intending to benefit the organisation and the organisation does not
have reasonable fraud prevention procedures in place. In certain circumstances, the
offence will also apply where the fraud offence is committed with the intention of
benefitting a client of the organisation. It does not need to be demonstrated that
directors or senior managers ordered or knew about the fraud. 
1.3. The offence sits alongside existing law; for example, the person who committed the
fraud may be prosecuted individually for that fraud, while the organisation may be
prosecuted for failing to prevent it. 
1.4. The offence is intended to hold organisations to account for fraud committed by
employees, or other associated persons, which may benefit the organisation, or, in
certain circumstances, their clients.  It applies to large organisations4, such as South
Lanarkshire Council, where 2 of the following apply: more than a £36 million
turnover; more than £18 million in assets; more than 250 employees. 
1.5. Organisations may face criminal prosecution and unlimited fines if they fail to prevent
fraud, which overlaps with existing obligations under the failure to prevent tax
evasion offences introduced under the Criminal Finances Act 2017. 
1.6. The question of whether an organisation has reasonable procedures in place to
prevent fraud will be decided by the courts and the onus will be on the organisation
to prove that it had reasonable procedures in place to prevent fraud at the time the
fraud was committed or the court is satisfied that it was not reasonable to expect the
organisation to have any prevention procedures in place. 
1.7. To ensure compliance with the legislation, the Council must now take proactive steps
to understand its fraud risk exposure and review the effectiveness of the measures in 
2 An employee, an agent or a subsidiary of the relevant body is automatically an ‘associated person’ for the
purposes of this offence. A person who provides services for or on behalf of the relevant body is also an
associated person while they are providing those services.
3 This includes fraud by false representation, fraud by failing to disclose information, fraud by abuse of
position, false accounting / false statements, fraudulent trading, participation in a fraudulent business,
cheating the public revenue and obtaining services dishonestly
4 All large, incorporated bodies, subsidiaries and partnerships; large not-for-profit organisations (such as
incorporated charities); incorporated public bodies 
135

Page 136

place to prevent, detect, and respond to fraud and, by doing so, mitigate the risk of
corporate criminal liability. 
2 Compliance 
2.1. The Council’s defence, in the event of such a fraud, will be to have fraud prevention
procedures in place that are deemed to be reasonable by a Court.  Home Office
guidance around ECCTA 2023 has been used to review existing fraud arrangements
and to identify further actions that should be taken.  The findings from this exercise
are set out in paragraphs 4.2 to 4.24 below.  
2.2. Recently published government guidance included several key considerations if an
organisation is to be reliant on the reasonable procedures defence.  There will be an
onus on the Council to prove that it had reasonable procedures in place to prevent
fraud at the time the fraud was committed, albeit procedures to prevent fraud should
be proportionate to the risk.  Public sector organisations are already required to
implement the recommendations of the Public Sector Fraud Authority and the
government counter fraud profession, and, as such, are therefore recognised as
likely to have many of the elements of a robust fraud prevention framework in place.
2.3. The guidance issued by the Home Office sets out how compliance can be
demonstrated across 6 broad headings:
2.4. Top level commitment: Home Office guidance notes that the responsibility for the
prevention and detection of fraud sits with senior management and those charged
with governance, and requires a demonstration of their commitment to prevent fraud. 
This is evidenced within South Lanarkshire Council by the RASC approving anti-fraud
policies, ensuring fraud prevention is embedded within Service procedures and
promoting training and encouraging an open culture founded on a zero-tolerance
approach to fraud. 
2.5. In May 2023, a revised Counter Fraud, Bribery and Corruption Policy was approved
by RASC together with new Due Diligence and Anti-Tax Evasion Polices.  These
reflect the key principles and processes around the Council’s response to and
management of fraud risk.  A refreshed Conflict of Interest approach will now form
part of the annual self-assessment governance process. 
2.6. Oversight of fraud risk management is also achieved through RASC receiving reports
on fraud statistics, trends and patterns on a bi-annual basis alongside reports on
participation, progress and outcomes from the NFI Exercise.   
2.7. To further embed a culture of zero-tolerance, it is intended to: 
 make more direct reference within the Code of Conduct to the obligations and
responsibilities of employees regarding fraud
 reflect this in the induction process for all new employees and require this to form
part of the required ‘behaviours’ set out within annual performance appraisal
forms
 roll out the fraud awareness programme (see below) 
 undertake an annual review of the Council’s fraud policy and assess ongoing
levels of compliance
 review the format of 6-monthly and annual fraud reports to provide a more
comprehensive update on anti-fraud activity
 annual publishing of the Council’s conflict of interest policy and a reminder of an
employee’s responsibility to declare 
136

Page 137

Fraud Awareness Programme 
Current practices are assessed as meeting all of the requirements of a best practice
fraud prevention framework but it is recognised that there would be a benefit in a
more structured programme of communication to further embed a zero-tolerance
approach to fraud, raise awareness of existing policies and procedures that manage
the risk and demonstrate reasonable fraud prevention procedures are in place. 
Communications are issued to employees when policies are revised and ahead of
data extraction for the NFI exercise when employees and South Lanarkshire
residents are advised that a new Exercise is about to begin.  It is suggested that this
is supplemented by further communications. 
In summary, the programme includes an annual reminder of the fraud policy and of
employee’s responsibility to declare any conflict of interest, an annual presentation on
fraud risk to the Risk Sponsor’s Group to inform their review of the Council’s top risks
and a yearly update on the NFI Exercise, including the sharing of broad outcomes
from the investigation of matches.  In both years, it is intended that fraud awareness
bulletins will be posted daily (over the course of 1 week on the intranet). 
2.8. Risk assessment:  fraud is recognised as one of the Council’s top risks that is
mitigated via a series of controls that are set out within risk control cards reviewed on
an annual basis.  Separately, more detailed fraud risk registers are maintained by
Resources and, again, reviewed annually.  These processes have now been merged
in 2025/2026 to improve efficiency and ensure alignment between top risk and
Resource-specific fraud risk registers. 
2.9. To provide assurance around the adequacy of fraud risk assessments, these are now
being reviewed to provide assurance that these: 
 identify where the Council could be susceptible to fraud across its key business
operations
 determine the level of exposure in an objective, consistent and proportionate
manner
 enable the Council to effectively prioritise its resources in mitigating fraud risks
 identify what processes are in place within the Council to detect instances of fraud
and how data is used to enable timely detection
 put in place a robust Counter Fraud Forward Plan integrated and aligned with the
wider Internal Audit Plan to provide assurance over the internal controls in respect
of fraud
 set out a fraud awareness and training programme to promote a culture of
integrity where employees feel empowered and responsible for preventing fraud
 make best use of the resources and expertise within Internal Audit to emphasise
the need to counter fraud
 develop a communication plan in respect of Counter Fraud
 signpost staff and services not only to their own operational procedures and
guidance which references fraud prevention but also to the Council’s specific
Counter Fraud Policies
 develop a Counter Fraud Forward Plan (work programme) for 2025/2026 
 map the Counter Fraud Forward Plan to the new Global Internal Audit Standards
 ensure that the RASC receive periodic updates in fraud reports that are presented
137

Page 138

2.10. Proportionate risk-based prevention procedures: the guidance defines these as
being procedures that are proportionate to the fraud risk that the organisation faces
and being reflective of the nature, scale and complexity of operations.  Council
Services have developed detailed procedures that include controls to minimise the
opportunities for fraud and processes to detect fraud, should this occur.  Wider
corporate procedures5 set out the process and consequences if fraud is committed by
an employee. 
2.11. Audit programmes include a standard suite of fraud checks where a process or
procedure is being reviewed.   
2.12. To support the ongoing review of anti-fraud procedures, it is intended to:- 
 review the fraud audit programme on an annual basis and amend as appropriate 
 capture data around how many of these checks have been undertaken over the
course of a year and report within the annual fraud report 
 require all Resources to review Service specific procedures to ensure these
incorporate fraud prevention measures and that there is evidence of a periodic
briefing of employees 
2.13. Due diligence: fraud risks extend beyond internal threats to also include those
persons who perform or will perform services for or on behalf of the Council.  The
Council seeks to mitigate such risks through financial appraisals, declarations and
compliance clauses within contracts. 
2.14.  Actions in response to due diligence requirements are to: 
 review current vetting of employees, agents, contractors, and subsidiaries who act
“for or on behalf of” the organisation. 
2.15. Communication (including training): the prevention of fraud is the responsibility of
every employee of the Council, so it is key that prevention policy and procedures are
communicated, embedded and understood.  Awareness and understanding of
policies and procedures are key to ensuring that these effectively manage the risk of
fraud and, where required, provide a clear route for reporting concerns.  Training is
broadly via Personnel Circulars or, at times, more targeted briefings.  Wider fraud
awareness training is recommended, if required within a specific Service.  Although
fraud control measures are embedded within processes, investigative work
undertaken by Internal Audit has identified that levels of fraud awareness could be
improved so that all employees are mindful of fraud risks, how these are managed
and controlled and how concerns should be reported.  A whistle-blowing process is
included within the Counter Fraud, Bribery and Corruption Policy but is noted, on
review, as not being formally re-publicised on a periodic basis.  To address gaps, a
formal fraud awareness programme has been developed.   
2.16. Although current practices were assessed as meeting all of the requirements of a
best practice fraud prevention framework it was recognised that there would be a
benefit in a more structured programme of communication to further embed a zero-
tolerance approach to fraud, raise awareness of existing policies and procedures that
manage the risk and demonstrate reasonable fraud prevention procedures are in
place. 
5 Counter Fraud, Bribery and Corruption Policy (January 2023)
138

Page 139

2.17. Communications were noted as issued to employees when policies are revised and
ahead of data extraction for the NFI exercise when employees and South Lanarkshire
residents are advised that a new Exercise is about to begin.  This will now be
supplemented by further communications in the agreed programme. 
2.18. In summary, the programme includes an annual reminder re the fraud policy and of
employee’s responsibility to declare any conflict of interest, an annual presentation on
fraud risk to the Risk Sponsor’s Group to inform their review of the Council’s top risks
and a yearly update on the NFI Exercise, including the sharing of broad outcomes
from the investigation of matches.  In both years, a week of fraud awareness bulletins
will be posted daily on the intranet. 
2.19. The content of the programme will be reviewed after 2026/2027, and a further
programme for the next  2 years developed. 
2.20. Only one other action has been identified in this area to:- 
 develop a formal programme of Learn fraud modules on Fusion 
2.21. Monitoring and Review: this is the final principle in the fraud prevention framework
and is around the monitoring and review of fraud detection and prevention
procedures, making improvements where necessary.  As required by this principle,
South Lanarkshire Council can demonstrate that it learns from investigations and
whistleblowing incidents with action plans developed and improvements tracked. 
2.22. Whistleblowing is recognised as one of the most effective ways to uncover corruption,
fraud, mismanagement and other wrongdoing.  An action to review whistle-blowing
arrangements against the requirements of Home Office guidance and wider best
practice has been included in the action plan. 
2.23. Detection of attempted fraud is an area where new digital processes are being
developed to analyse data on a regular, cyclical basis.  This has the benefit of being
able to test significant volumes of data using pre-determined risk criteria.  Time to
extend the use of such tools, along with a review of the reporting functionality within
Oracle Fusion, is included within the 2025/2026 Internal Audit Plan.  Again, an action
has been included in the action plan to track progress with developing this form of
analysis. 
2.24. The guidance notes that the court will consider adherence to the principles set out in
the guidance. More detailed risk assessments, fraud prevention plans which are
adhered to and monitored, and additional resource allocation are a clear expectation. 
Notwithstanding that existing arrangements establish a sound foundation, actions set
out above would further strengthen arrangements.  These have been included in an
action plan.  Each action has a responsible owner and timescale for completion and
progress with delivery will be reported periodically to RASC. 
139

Page 140

Appendix 4 
South Lanarkshire Council response to “Our work, your views – Consultation on the
Accounts Commission’s work and priorities” consultation:   
1. To what extent have our recent reports and recommendations been considered or
used within your organisation or across your sector to support improvement? 
All reports are reviewed, and where there are relevant points for South Lanarkshire
Council, an action plan is developed.  If appropriate, a report is presented to senior
management and to Council Committees. 
2. If applicable, can you provide any examples? (Optional) 
The recent report on the Council Tax fraud at Aberdeen City Council led to a review of
controls around the processing of refunds within South Lanarkshire Council.  Learning
points were taken around how the fraud had been perpetuated, and additional data
payment validation is now undertaken.   
3. Do you have any comments or feedback about the formats of our recent
publications? 
The format is generally helpful, reports are clear and concise with the summary of key
points particularly useful.   
4. In which of our current areas of work do you think the Accounts Commission can
have the most impact? 
All current areas of work are in areas that the Council would consider to be significant
risks.     
5. What else could the Commission do, alongside publication of our reports, to
maximise impact and support improvement in these areas? 
Bench-marking and sharing best practice is helpful as this supports a review of the
Council’s existing policy and processes.  Sharing lessons learned from fraud is also
helpful. Whilst it is important to summarise the nature, challenges, and risks around the
subject area, these are often already known and recognised within South Lanarkshire
Council.  It is helpful when there is a focus on suggested actions and pragmatic next
steps. 
6.   Please provide any comments relating to this section. (Optional) None.
140

Page 141

7. Which of the areas under consideration for our future work do you think most    
urgently require attention from the Accounts Commission to highlight issues and
support improvement? 
We agree that the over-arching themes of financial sustainability and
transformation/reform are very relevant.  Specific areas that link to identified top risks
within the Council relate to local taxation; digital transformation; housing and
homelessness and health and social care. 
8. In what ways could we best support you or your organisation in the areas you  
selected in answer to the question above?   
It is helpful to provide a concise summary of issues; a benchmarking of approaches
across local government (and across sectors); and an identification of good practice
and suggested actions. 
9.     Please provide any comments relating to this section. (Optional) None.
141

Page 142

142

Page 143

Report
Agenda Item 
Report to: Risk and Audit Scrutiny Committee
Date of Meeting: 30 September 2025
Report by: Executive Director (Finance and Corporate Resources)  
Subject: Financial Resilience and Sustainability 
1. Purpose of Report  
1.1. The purpose of the report is to:- 
 provide a position on the Council’s Financial Outlook, financial resilience and
sustainability, and how we can respond to the risks posed by the financial
challenges ahead 
2. Recommendation(s)
2.1. The Committee is asked to approve the following recommendation(s):- 
(1) that the Financial Position and Plan for 2026/2027 and 2027/2028 (section 4),
be noted; and
(2) that the Financial Resilience Framework (section 5 and Appendix 1), be noted. 
3. Background
3.1. A report on the Council’s Financial Resilience and Sustainability was presented to the
Committee on 24 September 2024. This provided a summary of the 2025/2026 to
2026/2027 Budget Strategy, demonstrating the Council’s understanding of the
medium-term financial outlook and providing information on the Council’s Financial
Resilience and Sustainability. 
3.2. A report titled 2026/2027 to 2027/2028 Revenue Budget Strategy was presented to
the Executive Committee on 25 June 2025.   
3.3. Section 9 of the June 2025 Revenue Budget Strategy report to the Executive
Committee (link above) noted that an annual update on the Council’s financial
sustainability would be presented to the Committee later in the year. 
3.4. This report will, therefore, provide a summary of the 2026/2027 to 2027/2028 Budget 
Strategy reported in June, demonstrating the Council’s understanding of the medium-
term financial outlook (section 4) and section 5 will provide information on the Council’s 
Financial Resilience and Sustainability. 
4. Financial Position and Plan for 2026/2027 to 2027/2028
4.1. The report to Council in June covered the current estimates and assumptions resulting
in the budget gap of £24.273 million for the next 2 years. This gap is the result of
estimations around grant levels, cost increases, and the impact of temporary solutions
previously put in place to manage pressures.  This gap did not include any assumption
around an increase in Council Tax. 
6
143

Page 144

4.2. In addition, the report highlighted the significant risk that a pay award is set at a level
that is higher than the Budget Strategy assumptions. A multi-year pay offer could result
in a funding shortfall of up to £18 million (recurring) which would mean that the Budget
Gap potentially increases from £24.273 million to a figure in excess of £42 million. This
demonstrates the Council’s understanding of the medium-term financial outlook. 
4.3. The June 2025 paper highlighted that one way of managing the Budget Gap is the
programme of Transformational Reviews ongoing across the Council. The 2025/2026
approved Budget included savings of £6.485 million arising from completed Reviews. 
In addition, 2 of the savings approved for 2025/2026 have an impact of £1.267 million
on the Budget Gap in 2026/2027. 
4.4. The Transformational Reviews continue to progress, and as they do so, proposals will
be presented to Members for approval as part of the budget-setting process for
2026/2027 and 2027/2028. This demonstrates a structured approach to identifying
savings proposals for members’ consideration and will assist in managing the Budget
Gap.   
4.5. While any savings from the majority of the Reviews have still to be confirmed, it is
acknowledged that it is unlikely that they would cover the full extent of the Budget Gap
over the next 2 years, given that the Gap could potentially be in excess of £42 million
(section 4.2). 
4.6. The June 2025 paper outlined that another levers available to the Council to reduce
the Budget Gap is an increase in Council Tax levels. 
4.7. In South Lanarkshire, our comparatively low level of Council Tax (the lowest in
Scotland) sets us apart from other councils and provides options for consideration
when addressing the significant Budget Gap for future years. 
4.8. A strategy could be developed to consider increasing South Lanarkshire Council’s
Council Tax to a level more in line with the Scottish average. An option could be to
develop plans to help reduce the Budget Gap through a planned movement to the
Scottish Average Council tax level. Such a strategy could look to take the increase in
Council Tax to a higher level, over a period of years, with the aim of moving to the
average Council Tax level. This again demonstrates the structured approach
presented for Members’ consideration, as part of assisting in managing the Budget
Gap. 
4.9. As part of the process of managing the Council’s finances over the coming 2 years,
especially given the financial challenges that lie ahead and the Budget Gaps being
faced by the Council, consideration again must be given to the Council’s position on
resilience. More than ever, the Council needs to be able to demonstrate our strong
financial management and how we will manage financially in these difficult times.
Financial resilience is covered in the next section of this report. 
5. Financial Resilience
5.1. It is acknowledged that financial resilience is a crucial aspect of financial management
and is particularly important in light of the financial pressures facing local government
especially following years of inflationary cost increases. It is recognised that this is
about more than the reliance on usable reserves, and that councils need to be more
comprehensive in their assessment of their level of financial resilience. 
144

Page 145

5.2. This paper will detail how councils can demonstrate financial resilience, by explaining
key aspects of financial strength as well as highlighting the areas that should continue
to be monitored or examined further. 
5.3. The financial resilience of the Council looks at its ability to anticipate and respond to
changes in the internal and external financial environment. In order to do that, it is
important to know what resources are available in a time of crisis and not just reserves.
It is also important to understand the Council’s exposure to loss of income, your level
of commitment to expenditure, and to know what flexibility the Council has in terms of
accessing funds when they are required. Appendix 1 provides a framework which
looks at:- 
 a review of the balance sheet (Appendix 1, sections 4 to 17, including Council
Reserves and Liquidity, Debt and Investment
 exposure to risk (Appendix 1, sections 18 to 23, including Significant Income
Areas, Top Expenditure Commitments and Group Risk) 
5.4. A summary of the Council’s performance in terms of the Financial Sustainability
element of the Local Government Benchmarks is also included in Appendix 1 (sections
24 to 30) for consideration. 
5.5. As with any set of indicators, there is not necessarily a right or a wrong answer. It is
more important that they are used to provide financial context, and it may be that the
trend in these figures over a number of years is more of an indicator for action as on
an annual basis only, an issue might not be visible or may be overlooked. These
indicators will continue to be monitored across time, and we will report these to the
Committee on an annual basis. 
5.6. Summary of Financial Resilience Framework: The financial resilience framework
demonstrates the level of the Council’s financial resilience in a number of ways. The
Council holds an uncommitted General Fund Reserve to protect against unforeseen
events. This sits alongside a level of earmarked reserves which can be used in a
managed way to smooth the impact of pressures across years – for example, the
Loans Fund Review, Service Concessions and the reduced Pension Fund
Contributions. This aligns with the Council’s medium-term financial strategy, which has
been approved by Members and demonstrates good financial management through
planning and managing key budget pressures. 
5.7. The framework shows that the level of debt costs compared to the net income for the
Council has increased from the previous year. An important point to note that these
debt costs are the result of the planned borrowing undertaken by the Council and that
the debt repayments are considered affordable as part of our Revenue Budget. 
5.8. As well as looking at what resources are available in times of crisis, the financial
resilience of the Council also looks at its ability to anticipate and respond to changes
in the internal and external financial environment. In order to do that, it is important to
understand the Council’s exposure to loss of income and key areas of budget
pressure. The financial resilience framework details the significant income areas and
also the areas of high spend / high risk that the Council acknowledges and will continue
to monitor. 
5.9. The Council participates in the Local Government Benchmarking Framework in
relation to assessing sustainability. The Improvement Service note that a direct
comparison cannot be drawn due to the nuances of individual councils and their own
financial plans. However, reviewing the trend in the Council’s position over time will
145

Page 146

give context. From the Council’s own perspective, analysis of the ratios demonstrates
the level of reserves held by the Council was lower than the Scottish average, as is
the unearmarked element. However, at a value of £13.043 million, this is deemed an
appropriate level but will continue to be monitored. The sustainability indicators also
note that the Council finished its year-end in a break-even outturn position (after
approved transfers to Reserves) which is a positive outturn. 
5.10. This paper demonstrates the Council’s financial resilience by explaining its detailed
financial planning, its level of reserves and its key financial strengths in terms of its
balance sheet position. Any risks identified through horizon scanning are mitigated
where appropriate through the Budget Strategy, a key part of the Council’s financial
resilience framework. 
6. Employee Implications
6.1. There are no direct employee implications from this report. 
7. Financial Implications
7.1. The financial implications are summarised within the report. 
8. Climate Change, Sustainability and Environmental Implications
8.1. There are no implications for climate change, sustainability or the environment in terms
of the information contained in this report.   
8.2. Climate Change targets will have an impact on the Council’s future financial strategies. 
This will be included in future Budget Strategy papers as appropriate. 
9. Other Implications
9.1. The review of financial resilience is a way of understanding the key financial risks to
the Council.  The financial strategy is the way in which the Council can manage a
number of these key risks which directly impact the money available to deliver Council
outcomes.   
9.2. The resilience indicators will continue to be monitored and will be reported on as
appropriate. 
10. Integrated Impact Assessment and Consultation Requirements
10.1. This report does not introduce a new policy, function or strategy or recommend a
change to an existing policy, function or strategy and, therefore, no impact assessment
is required. 
10.2. There is no requirement to undertake any consultation in terms of the information
contained in this report. 
10.3. However, as the process to identify savings continues, and with proposals to be
presented to members later in the year, stakeholder consultation and equality impact
assessments will be carried out.  The results will be provided to members to inform
their decision-making process. 
146

Page 147

Jackie Taylor
Executive Director (Finance and Corporate Resources) 
10 September 2025 
Link(s) to Council Values/Priorities/Outcomes
 Accountable, Effective, Efficient and Transparent 
Previous References
 Risk and Audit Scrutiny Committee - 24 September 2024
 Executive Committee - 25 June 2025 
List of Background Papers
 None 
Contact for Further Information
If you would like to inspect the background papers or want further information, please
contact:- 
Jackie Taylor, Executive Director, Finance and Corporate Resources 
Ext:  4637 (Tel:  01698 454637)
E-mail : jakie.taylor@southlanarkshire.gov.uk 
147

Page 148

Appendix 1
Financial Resilience – A Framework 
1. It is acknowledged that financial resilience is a crucial aspect of financial management
and is particularly important in light of the financial pressures facing local government
especially following years of inflationary increases in costs. It is recognised that this is
not about the reliance on usable reserves, and that councils need to be more
comprehensive in their assessment of their level of financial resilience. 
2. This paper will detail how councils can demonstrate financial resilience by explaining key
aspects of financial strength as well as highlighting the areas that should continue to be
monitored or examined further. 
3. The financial resilience of the Council should look at its ability to anticipate and respond
to changes in the internal and external financial environment. In order to do that, it is
important to know what resources are available in a time of crisis and not just reserves.
It is also important to understand the Council’s exposure to loss of income, your level of
commitment to expenditure, and to know what flexibility the Council has in terms of
accessing funds when they are required. 
4. A Review of the Balance Sheet:  Taking information from the Council’s Balance Sheet
at the end of the financial year is a way to assess resilience.  Maintaining a strong balance
sheet provides the assurance that the Council can respond in time of crisis and that it
can meet its obligations. The Balance Sheet Review considers the following:- 
 council reserves and liquidity, and 
 debt and investment. 
5. Council Reserves and Liquidity:  It is the responsibility of the Executive Director
(Finance and Corporate Resources) to advise the Council on the level of reserves it
should hold and to ensure that there are clear protocols for their establishment and use. 
6. The Local Authority Accounting Panel (LAAP) provide guidance to the Council’s Section
95 Officer (the Executive Director of Finance and Corporate Resources), on the
establishment and maintenance of local authority reserves and balances. The LAAP
Bulletin does not prescribe a minimum level of reserves which should be held by a
council. It is for the Council to consider an appropriate level of reserves taking cognisance
of strategic, operational and financial risks facing the authority at a local level. It does,
however, say that Reserves should not be held without a clear purpose.  
7. The Council keeps an Uncommitted General Fund Reserves to protect against the risk
of unforeseen events. This is considered best practice and demonstrates sound financial
planning. As has been advised to members previously, the use of Reserves is not a
permanent budget solution but can be used to smooth the impact of pressures across
years – for example as we have employed with the monies released by the Loans Fund
Review, Service Concessions and the reduced Pension Contributions. If necessary,
Reserves can be used to absorb one-off costs to avoid an impact on Resource budgets
in-year or can facilitate the rollover of unused elements of grant into the next financial
year. 
8. Table 1 provides information on the level of Reserves across the past 3 years and looks
at these Reserve levels in light of total expenditure commitments. It also looks at the ratio
of current assets to current liabilities (Liquidity) in order to determine whether the Council
could use its current assets to cover its current liabilities, if required.
148

Page 149

Table 1:  Reserves and Liquidity 
2024/2025 2023/2024 2022/2023
General Fund
Useable Reserves (exc. HRA) £137.128m £120.467m £164.080m
Movement in Useable Reserves (exc. HRA) 16.661m (43.613m) £28.135m
Useable Reserves / Net Revenue Stream 14.61% 14.13% 19.86%
Level of Uncommitted General Fund Reserve £13.043m £13.043m £13.043m
Level of Committed Reserves (exc. HRA) £124.085m £107.424m £151.037m
Housing Revenue Account Reserve
Useable Reserves £10.440m £13.221m £12.861m
Movement in Useable Reserves (£2.781m) £0.360m (£3.380m)
Useable Reserves / Net Revenue Stream 9.14% 12.52% 12.67%
Liquidity
Current Assets to Current Liabilities
£129.484m/
£435.737m
= 0.30
£119.471m/
£277.436m
= 0.43
£225.337m/
£242.674m
= 0.93 
9. Table 1 shows the movement in the Total Useable Reserves of the Council (exc. HRA)
as well as the HRA Reserve.  The level of committed reserves for the General Fund and
the HRA have both decreased across years.  At the end of 2024/2025, the General Fund
decrease reflects the use of reserves for Budget Strategies mainly relating to those
Generated by the Loans Fund Review and the implementation of Service Concessions. 
10. As a proportion of the Net Revenue Stream, General Fund Reserves at the end of
2024/2025 have decreased since 2022/2023 (albeit slightly higher than 2023/2024). 
While the Council’s Net Revenue Stream (Council Tax and Government Grant) has
increased, there has been a reduction in useable reserves reflecting the use of reserves
for Budget Strategies.  This is similar for the HRA Reserve as a proportion of its Net
Revenue Stream. 
11. In terms of the Council’s liquidity position, the ideal position is that current assets exceed
current liabilities.  However, this is not the case.  In 2024/2025, the ratio has dipped from
2023/2024 due to an increase in short-term borrowing (as opposed to long term
borrowing) while interest rates remain high. In reality, this indicator reflects the Council’s
position at a point in time, and there are no concerns regarding the Council’s liquidity
position. 
12. Debt and Investment:  The Council’s Balance Sheet provides information on Debt
(borrowing) and Investment levels.  It shows whether the Council’s liabilities are short or
long term. 
13. The Council already prepares a suite of ratios to meet the obligations of the Prudential
Framework.  The ratios that relate to Debt and Investment are provided in Table 2. 
Table 2:  Debt and Investment 
2024/2025 2023/2024 2022/2023
Borrowing 1,030.762 1,034.532 1,036.302
PPP Liability 323.255 172.036 179.134
Gross Debt 1,354.017 1,206.568 1,215.436    
General Fund 1,268.007 1,102.027 1,089.036
HRA 323.678 307.217 292.706
Total Capital Financing Requirement 1,591.685 1,409.244 1,381.742    
149

Page 150

2024/2025 2023/2024 2022/2023
Under / (Over) Borrowed 237.668 202.676 166.306    
Investments 23.582 13.475 160.770    
General Fund   
Financing Costs 45.164 31.249 36.921
Net Revenue Stream 938.760 852.568 826.366
Financing Charges to Net Revenue Stream 4.81% 3.67% 4.47%    
HRA   
Financing Costs 10.662 8.155 14.192
Net Revenue Stream 114.273 105.649 101.531
Financing Charges to Net Revenue Stream 9.33% 7.72% 13.98% 
14. Table 2 shows that the Council’s Gross Debt has increased since last year reflecting
anticipated debt repayment profiles. The Capital Financing Requirement (the level of debt
that we need to finance our assets) has increased over the 3 years and this is because
our in-year borrowing has been higher than the level of debt repayments made. 
15. Comparing the Gross Debt to the Capital Financing Requirement gives a position of
under or over borrowing. The Council has under-borrowed. This is a favourable position
and is because we did not need to borrow as much as predicted due to the level of cash
reserves held. In terms of investments (deposits) – there was an increase in 2024/2025,
and this reflects the higher level of cash balances available. 
16. Finally, the ratio of debt costs to net financing stream for the General Fund and the HRA
are sitting at c5% and c9% respectively.  This is an increase on the previous year and
generally reflects the increase in debt payments offset by the increase in revenue income.     
17. An important point to note is that the borrowing undertaken by the Council is planned and
the repayments on these debts are considered affordable as part of our Revenue Budget
planning. 
18. Exposure to Risk:  A review of Revenue expenditure and income over time ensures that
we know the areas that we need to focus our attention on to ensure we can pre-empt any
potential financial pressures.  A review of the exposure to risk looks at: 
 significant income areas, and
 top expenditure commitments. 
19. Significant Income Areas:  Looking at the Council’s Budget, there are a number of
significant high value Income areas outwith the Government Grant / NNDR Income
budgets.  These are noted in Table 3 as appropriate, giving context on each. 
Table 3:  Significant Income Areas 
2024/2025 2023/2024 2022/2023    
Council Tax Income 161.060 159.053 148.958
Council Tax Income as a % of Net Revenue Stream 17.16% 18.70% 18.03%
Parking Income  2.234 2.031 1.867
School Meals Income  3.585 3.213 2.763
Bereavement Income 2.908 2.979 2.658
Planning and Building Standards Income 3.289 2.885 3.362
150

Page 151

Early Years Fee Income 2.387 1.990 1.591
Licensing and Registration Income 1.676 1.503 1.793 
20. Table 3 shows that as a percentage of the Council’s Total Budget, the level of Council
Tax Income has decreased into 2024/2025.  This mainly reflects the Council Tax freeze
in 2024/2025 while the overall Budget has gone up.  In financial terms, the level of Council
Tax income received in 2024/2025 is actually £2 million higher than the previous year –
a positive position reflecting increased property numbers. 
21. The table also shows some significant income budgets and the pattern over recent years.
Some of these areas (School Meals, Parking, Licensing and Registration) were
significantly affected by the pandemic and have struggled to return to pre-pandemic
levels (before 2020/2021). They will continue to be monitored to identify whether the
pressure reduces. 
22. Top Expenditure Commitments:  Similarly, there are a number of significant Council
budget areas that can be highlighted for a trend analysis, on the basis that they are
demand lead, high value budgets and are, therefore, a risk area for the Council. These
are noted in Table 4 which notes the actual spend and the variance across years to show
the pressure in those areas. Top expenditure commitment areas feature as part of the
Council’s considerations when looking at future budget strategies. 
Table 4:  Top Expenditure Commitments 
2024/2025 2023/2024 2022/2023    
Adult and Older People Social Care 
- delegated to the IJB (after
commitments)
181.334
(0.010 under)
182.657
(breakeven)
165.334
(breakeven)
Children and Family Services 50.031
(0.813 over)
47.160
(0.468 over)
43.749
(1.295 over)
Waste Services 
- Facilities, Streets, Waste and
Grounds
80.963
(0.176 under)
82.954
(0.097 under)
75.349
(0.370 over)    
* All figures are after approved Transfers to Reserves 
23. Table 4 shows that the spend on these areas is increasing over time. For Children and
Families and also for Adults and Older People (albeit the services are delegated to the
Integration Joint Board (IJB)), the Services continue to manage budget pressures through
Budget Planning. In the same way as the Council, the IJB identify Budget Gaps, and
solutions as part of their medium-term financial planning process. For Children and
Families, a detailed Budget recovery Plan is reported on regularly to Social Work
Resources Committee.  The cost of the Waste Service (as part of the Facilities, Streets,
Waste and Grounds) continues to experience high demand and income pressures
(school meals for example). These Services will continue to be monitored. 
24. Local Government Benchmark Framework:  From 2019/2020 onwards, the Local
Government Benchmarking Framework introduced new ratios to assess sustainability.
The 2023/2024 data is shown in Table 5 (2024/2025 information is not yet available).  
Table 5:  Sustainability – Local Government Benchmark Framework 
Council Scotland   
What proportion of my income does the Council hold in reserves? 19.6% 23.9%
What proportion of my Council's revenue is not committed to a 1.4% 2.3%
151

Page 152

specific theme/project?
How much of my Council's income is used to service debt? 3.7% 5.8%
How much of my Council's housing income is used to service debt? 7.7% 20.0%
What proportion of my Council's budgeted spend is spent in
practice?
100% 99.6% 
25. Table 5 shows that the Council’s results alongside the national position. It is noted that a
direct comparison cannot be drawn due to the nuances of individual councils and their
own financial plans. However, reviewing the trend in the Council’s position over time will
give context. The data over years since 2013/2014 are included in the Improvement
Service website. 
26. The financial resilience framework and the Local Government Benchmarks detailed
above can be used as a basis for assessing the financial resilience of the Council. The
aim of the first indicator is to show how much money the Council holds in reserves. At
the end of 2024/2025 the Council was lower than the Scottish average. While the
significance of the level of reserves held is acknowledged, it must also be acknowledged
that most of these reserves are committed. 
27. In terms of the uncommitted revenue monies, that refers to the unearmarked general
fund and while it is lower than the Scottish average, at a level of £13.043 million, this is
deemed appropriate but is kept under review. 
28. The third indicator (and the fourth relation to the HRA) refers to the level of loan charges
compared to the overall budget. Again, the General Fund loan charges are lower than
the Scottish average, and similarly for the HRA. The relevance of this indicator is to
consider affordability. The Council and the HRA have planned for the debt, ensuring
repayments are sustainable. 
29. Finally, the last indicator looks at the year-end position and as the Council had a
breakeven position after approved transfers to reserves (the full budget is spent or
committed in year) this is a positive outturn. 
30. As with any set of indicators, there is not necessarily a right or a wrong answer. It is more
important that they are used to provide financial context, and it may be that the trend in
these figures over a number of years is more of an indicator for action as on an annual
basis only, an issue might not be visible or may be overlooked. 
152

Page 153

Report
Agenda Item 
Report to: Risk and Audit Scrutiny Committee
Date of Meeting: 30 September 2025
Report by: Executive Director (Finance and Corporate Resources)  
Subject: Audit Scotland – Local Government Budgets 2025/2026 
1. Purpose of Report
1.1. The purpose of the report is to:- 
 provide the Risk and Audit Scrutiny Committee with a summary of the information
contained within the Audit Scotland Local Government Budgets Briefing
2025/2026, published in May 2025 
2. Recommendation(s)
2.1. The Committee is asked to approve the following recommendation(s):- 
(1) that the key messages and data from the Audit Scotland Local Government
Budgets 2025/2026 briefing (detailed in sections 4 and 5) be noted; and
(2) that the commentary on the Council’s position, as included in the Audit Scotland
report (section 6), be noted. 
3. Background
3.1. In May 2025, Audit Scotland published the Local Government Budgets 2025/2026 on
behalf of the Accounts Commission. 
3.2. The introduction and key messages from the report are outlined in section 4 of this
report, with section 5 looking at funding, budgets and communities. Section 6 notes
commentary on the Council’s data included in the Audit Scotland report.   
4. Introduction and key messages
4.1. Audit Scotland has prepared this budget briefing on behalf of the Accounts
Commission to summarise key issues arising from analysis of the 2025/2026 budgets
recently agreed by Scotland’s 32 councils. 
4.2. This briefing brings together data from all 32 councils to provide an indicative national
picture of budgets set for 2025/2026. It considers how Scottish councils are addressing
the challenges faced in achieving a balanced budget and long-term financial
sustainability. It also considers how councils have consulted with communities on their
budget priorities, including the measures agreed to achieve financial savings. 
4.3. The wide range of approaches councils take to budget-setting, the level of information,
and the way that it is publicly reported, make it challenging to report a definitive
national position. Some of the variation between councils is likely due to differing
budgeting approaches.  
7
153

Page 154

4.4. The report is part of a series of overview outputs produced for the Accounts
Commission. These reports provide an independent overview of the financial and
operational performance of Scotland’s local government sector. In the next 12 months,
Audit Scotland intends to publish a spotlight report, highlighting overall and specific
service performance, and then the annual financial bulletin which assesses the
financial performance and position of Scotland’s councils in the most recently audited
financial year. 
4.5. A number of key messages are presented by Audit Scotland in their report in relation
to the 2025/2026 Local Government Budgets:- 
 Scottish Government funding to local government in 2025/2026 is increasing by 6
per cent in real terms, to £15.2 billion. However, local government continues to
face recurring pressures in excess of funding uplifts, such as inflation, annual pay
deals and growing demand for services, and most of the increase will be used to
deliver previously agreed national commitments. Alongside this, councils are
facing additional costs related to the increase in employers’ National Insurance
contribution rates, and investing in new buildings and assets is increasingly
expensive. 
 at a time of constrained public finances and growing demand, not all cost increases
can be met from central government funding, and councils need to take local action
to achieve budget balance over the short and medium term. At the time of setting
their budgets, councils identified a difference of £647 million between anticipated
expenditure and the funding and income they receive (the ‘budget gap’). Councils
are required to set balanced budgets and have agreed on a range of actions to
achieve this and close this gap. This includes all councils raising council tax rates
by between 6% and 15.6%, identifying savings, drawing on reserves and
increasing or introducing charges for accessing some services. 
 councils continue to make savings across a broad range of services to address
financial challenges and have been successful in identifying recurring measures
that will help to address underlying pressures. Despite this, councils are still
forecasting that more will need to be done in future years to achieve financial
sustainability, given their projected increases in both costs and level of service
demand. 
 councils’ budget-setting processes vary, partly reflecting differences in
organisational structures and local priorities, and this makes it difficult to compare
information across Scotland. There remains an underlying issue with the
transparency of how budget information is being presented. 
 most councils engaged communities in some way to make decisions on their
budgets for 2025/2026, but there were variations in the depth and level of this
engagement. By improving the accessibility and transparency of how they are
reporting budget information, councils can better inform and include their local
communities in making the choices required to address ongoing financial
challenges. 
5. Funding, budgets and communities
5.1. Scottish Government funding to councils 
Initial funding to councils is higher than last year, with revenue and capital funding both
increasing in real terms, but additional costs and inflationary pressures will remain
challenging to manage. 
154

Page 155

Scottish Government core funding to local government is increasing in
2025/2026
 the Scottish Government will provide £15.2 billion to local government in
2025/2026. The level of funding allocated to local government is expected to
change throughout the year as additional funding is made available to councils.
For example, the 2024/2025 local government budget increased in real terms to
£14.7 billion by the spring Budget revision. It is, therefore, likely that the 2025/2026
local government budget will change. 
All councils are receiving an annual increase in their initial revenue funding
allocations
 the Scottish Government allocated £14.4 billion of revenue funding to local
government in 2025/2026, an annual real terms increase of £789 million (6%).  This
settlement differs from the figures presented in the draft Scottish Budget published
in full in December, due to changes made to the budget prior to receiving
parliamentary approval. 
 the increase in total revenue funding to councils is driven by an 8% annual real
terms increase in the General Revenue Grant (GRG) to £11 billion. GRG has
increased due to additional funding, but also because the Scottish Government
moved previously ring-fenced funding into the general grant. Similarly, some
elements of funding that were previously transferred from other portfolios during
the year have now been included within initial allocations. 
 in 2025/2026, the increase in GRG includes baselining of funding for non-teaching
staff pay awards and teacher pension contribution increases, as well as the
following:- 
 £125 million of Living Wage funding
 £43 million of 2024 pay awards to teachers
 £10 million free personal and nursing care funding. 
 The 2025/2026 finance settlement also outlines an additional £152 million of
revenue funding, including £144 million of additional funding to partly compensate
for the increase in employer’s National Insurance contributions. Prior to this funding
being confirmed, Convention of Scottish Local Authorities (COSLA) estimated that
councils would need to identify £240 million to meet additional costs related to
directly employed council staff. 
Capital funding is increasing for 2025/2026, but it is still lower than in 2023/2024
 the Scottish Government is allocating £779.7 million of capital funding to local
government (a 16 per cent increase compared to last year). This includes £12.4
million of funding to Strathclyde Partnership for Transport and £89.5 million of
undistributed funding in 2025/2026.  The final settlement slightly differs from the
figures presented in the draft Scottish Budget, due primarily to around £60 million
of Specific Capital Grant moving into the General Capital Grant. 
5.2. Council budgets 
Councils continue to identify savings, use reserves and review how they deliver
services to manage financial pressures.  
155

Page 156

Councils’ combined revenue budgets for 2025/2026 have increased from
2024/25
 in 2025/2026, councils reported a combined revenue budget of around £18 billion,
increasing from £16.7 billion in 2024/2025 (around 7%). Councils have again
reported budget gaps in 2025/2026.  At the time of setting their 2025/2026 budgets,
councils identified a combined revenue budget gap of around £647 million. This
represents a budget gap in the range of 3.4 per cent of councils’ total combined
revenue budgets for 2025/2026. Compared to 2024/2025, the total budget gap
identified by councils has increased by £52 million. 
Councils are continuing to forecast budget gaps over the short term
 councils are anticipating that funding pressures will continue, citing several key
assumptions that inform budgets in the medium term. Where the information was
available:- 
 most councils report the pressures around annual pay settlements, with many
expecting 3% increases to 2027/2028. This, alongside higher employers’
National Insurance contributions, increases overall workforce costs
 a majority of councils also reference general inflationary pressures, including
increasing costs of goods and services, making councils’ operations more
expensive
 several councils are also projecting flat cash funding settlements from the
Scottish Government
 potential annual increases to council tax rates, with a lack of consistency on the
projected expected increase from individual councils. 
 based on 31 councils, the total projected revenue budget gap for 2026/2027 is
£528 million. The projected revenue gap for 2027/2028 is £496 million, across
these 31 councils.  While elements of these projections are either expected to be
addressed or lessen in impact, councils are currently anticipating a cumulative
revenue budget gap of £997 million over the next 2 years. 
Financial pressures in 2025/2026 include increased costs related to National
Insurance(NI) contributions
 all councils report facing increased costs from the changes in NI contributions for
employers and in response to this, the Scottish Government announced £144
million in additional funding. COSLA, however, estimated the additional cost could
be up to £370 million: £240 million for directly employed staff and £130 million for
indirectly employed staff (£85 million for staff working in Adult Social Care
commissioned services, and up to £46 million for staff across other commissioned
services and ALEOs). 
 returns submitted by councils showed additional costs of around £235 million within
approved 2025/2026 budgets, as councils mainly adjusted budgets to recognise
costs associated with direct employees.   
Councils, however, continue to benefit from reduced pension costs
 councils’ financial plans and budgets for 2025/2026 incorporated the reduction in
pension contributions, allowing the reduced costs against 2023/2024 rates to be
redirected to other areas.  
156

Page 157

 reduced pension contribution rates should only be seen as a temporary source of
funding by the Council, with rates increasing in 2026/2027. The level of reductions
range from 13 per cent (for 2 years) to one per cent. Councils who reported a 13
per cent reduction in contribution rates are the 12 members of Strathclyde Pension
Fund. Contribution rates will rise from 6.5 per cent in 2025/2026 to 17.5 per cent in
2026/2027. 
Councils continue to make savings across a broad range of services to address
financial challenges
 all councils provided information on the service areas where they are planning
financial savings in 2025/2026. Councils are planning to deliver around £210
million of approved savings in 2025/2026. Most of these saving measures are
recurring, with only £12.2 million of non-recurring savings planned. 
 across all councils, most savings are planned within corporate services, followed
by children’s services. Councils plan to achieve £68 million of savings within
corporate services and £58 million of savings in children’s services. Actions to
tackle climate have the lowest level of saving measures planned, with £0.4 million
of savings planned in 2025/2026. 
All councils chose to increase council tax rates significantly in 2025/2026
 councils had full flexibility over council Tax decisions in 2025/2026. All councils
increased their council tax levels, ranging from a 6% increase in South Lanarkshire
Council to a 15.6 per cent rise in Falkirk Council.  In total, councils expect to receive
£284.3 million from the increase to council tax in 2025/2026. £275 million will be
used to bridge the funding gap and the remaining is additional income. 
Councils continue to raise income by charging for certain local services
 24 councils provided information on their 2024/2025 income from fees and
charges. Those councils generated £966 million from fees and charges in
2024/2025, representing around 5% of their 2025/2026 revenue budgets. Fourteen
councils received more income from fees and charges in 2024/2025 compared to
initial projections.  In total, councils anticipate receiving £1.1 billion from fees and
charges in 2025/2026. This represents around 6% of the combined 2025/2026
approved revenue budgets for councils. 
Councils are also continuing to use reserves to balance their budgets
 at the end of 2024/2025, 25 councils are estimating that they will be holding £1.8
billion in their General Fund, a usable reserve, with £1.3 billion of this committed.
An estimated £0.14 billion has been identified by councils as formal contingency
funding, with a further £0.4 billion of uncommitted reserves also available for that
purpose if required. Combined, this represents a potential contingency of 2.9 per
cent of net revenue expenditure. Councils approved the use of £0.19 billion of
reserves in 2025/2026 during budget-setting as a means of balancing budgets. 
Borrowing continues to be the primary funding source for capital projects
 the total capital budget for all councils in 2025/2026 is £4.74 billion. This is an
increase from £4.23 billion in 2024/2025 across Scotland; however, eleven
councils are reducing their capital budgets.  Borrowing is the main source for
funding capital projects, and councils are intending to borrow £3.13 billion in
2025/2026, an increase from 2024/2025 (£2.67 billion).  
157

Page 158

Councils are increasing the amount they intend to spend on building and
maintaining social housing
 26 councils own and maintain council housing, and all these councils provided
information on how much of their capital budget is allocated to their Housing
Revenue Account (HRA). Councils are committing a combined £1.5 billion from
their capital budgets to the HRA in 2025/2026, an increase of £186 million from the
previous year. All councils are planning expenditure on new builds in 2025/2026:- 
 councils expect to spend £656 million from the HRA on new builds in
2025/2026, an increase of £81 million from 2024/2025. This represents the
largest area of expenditure within the HRA.
 refurbishment costs are the second largest area of expenditure within the HRA,
increasing by £142 million from 2024/25 to 2025/2026. Councils expect to
spend £521 million on refurbishing housing stock in 2025/2026 compared to
£379 million in 2024/2025.
 16 councils are planning programmes of maintenance work in 2025/2026. They
are expecting to utilise £289 million of funding for maintenance, an increase of
£78 million from 2024/2025. 
Social care revenue budgets make up a high proportion of total revenue budgets
for 2025/2026
 of the £18 billion revenue budget in 2025/2026, councils reported £4 billion related
specifically to social care services. This equates to almost 23 per cent of councils’
total revenue budget. Across councils, the social care budget ranges between 18
and 30 per cent of councils’ total revenue budget for 2025/2026. 
5.3. Consulting with communities 
As councils continue to make difficult decisions, it is more important than ever that
they involve communities in the decisions that impact their local services. 
Most councils carried out an assessment to understand the impact budget
decisions will have on different groups
 31 councils completed an Equality Impact Assessment (EIA) as part of their
2025/2026 budget process. 
Most councils consulted with residents on their 2025/2026 budgets
 30 councils provided evidence of how they engaged with residents, while
identifying saving measures and wider proposals within their 2025/2026 budgets.
However, the approaches taken varied. 
The Accounts Commission’s forthcoming work will assess how key council
services are performing
 for the next report in this series, the Accounts Commission will publish a service
spotlight. This new report, due to be published in October 2025, will provide an
overview of council performance as set out by the Local Government
Benchmarking Framework (LGBF) and other key metrics. For 2025, the spotlight
will have a particular focus on culture and leisure services that councils provide. 
6. South Lanarkshire Council – Budgets 2025/2026
6.1. The Audit Scotland report contains a number of tables that set out information for all
councils; however, there are 5 tables of data which show the performance of individual
councils. Commentary on South Lanarkshire Council’s position in each of these tables
is provided below. 
158

Page 159

6.2. Scottish councils’ budget gaps for 2025/2026 ranged between £4.4 million and £70
million. The Council’s Budget Gap was £5.3 million, being 2nd lowest. City of Edinburgh
was the highest with just over £70 million, and Eilean Siar was the lowest with £4.4
million.   
There are differences in the way councils’ approach and present their budget and
identify budget gaps. This means that direct comparison should be taken with caution.
An example noted in previous years is Glasgow City, who are a significant outlier due
to their approach. 
6.3. In terms of the budget gaps for 2025/2026 as a percentage of total revenue
budget, the Council is 0.5%, with other councils ranging from around just under 2%
to just under 7%. The Council has the lowest budget gap as a percentage of revenue
budget. 
Shetland and Orkney are excluded from this dataset as they are outliers due to their
planned use of (large) reserves to their balance budgets (20% and 18% respectively). 
6.4. The Council’s projected budget gaps to 2027/2028 shows the Council’s Budget
Gap for 2026/2027 at £11.7 million and 2027/2028 at £13.8 million. At that point, the
cumulative Budget Gap to 2027/2028 was projected at £25.5 million with the
cumulative gap being 3% of the 2025/2026 net revenue budget. The cumulative gap
for other councils as percentage of their 2025/2026 net revenue budget ranges from
1% (Fife and Moray) to 51% (Shetland). 
As noted above, there are differences in the way councils’ approach and present their
budget and identify budget gaps. This means that direct comparison should be taken
with caution. 
6.5. All councils increased their council tax in 2025/2026 with increases ranging in
2025/2026 from 6% to 15.6%. The South Lanarkshire Council had the lowest increase
(6%), and Falkirk had the highest increase (15%). 
6.6. The Selected 2025/2026 budget information shows the Council’s 2025/2026
revenue budget (£1,019 million), budget gap (£5.3 million), approved savings (£4.7
million) and other bridging to close budget gap (£0.5 million). 
South Lanarkshire Council set a balanced budget for 2025/2026 on 26 February 2025.
The budget was balanced using a combination of savings and earmarked reserves, in
line with the Budget Strategy, as well as a 6% increase in Council Tax levels into
2025/2026 – the lowest increase in Scotland. 
6.7. In terms of Consulting with Communities, the Council undertook a comprehensive
budget and savings consultation process with communities and partner organisations. 
The feedback was provided to Elected Members to facilitate informed decision-
making.  Integrated Impact Assessments on the Budget and Savings were made
available to Elected Members.  These were published and included the feedback from
the consultation process. 
7. Employee Implications
7.1. None.  
159

Page 160

8. Financial Implications
8.1. The Audit Scotland Report raises a number of financial areas for consideration by
councils; however, there are no direct financial implications as a result of the content
of this report. 
9. Climate Change, Sustainability and Environmental Implications
9.1. There are no implications for climate change, sustainability, or the environment in
terms of the information contained in this report. 
10. Other Implications
10.1. None. 
11. Integrated Impact Assessment and Consultation Requirements
11.1. This report does not introduce a new policy, function or strategy or recommend a
change to an existing policy, function, or strategy and, therefore, no impact
assessment is required. 
11.2. There is also no requirement to undertake any consultation in terms of the information
contained in the report. 
Jackie Taylor
Executive Director (Finance and Corporate Resources) 
7 August 2025 
Link(s) to Council Values/Priorities/Outcomes
 Accountable, Effective, Efficient and Transparent 
Previous References
 None 
List of Background Papers
 Local government budgets 2025/2026
 Audit Scotland, May 2025 
Contact for Further Information
If you would like to inspect the background papers or want further information, please
contact:
Jackie Taylor, Executive Director of Finance and Corporate Resources
Ext:  5637 (Tel:  01698 455637)
E-mail: jackie.taylor@southlanarkshire.gov.uk
160

Page 161

Report
Agenda Item 
Report to: Risk and Audit Scrutiny Committee  
Date of Meeting: 30 September 2025
Report by: Executive Director (Finance and Corporate Resources) 
Subject: Fraud Statistics Annual Report 2024/2025 
1. Purpose of Report
1.1. The purpose of the report is to:- 
 provide a summary of the fraud statistics and workload for the year to 31 March
2025 and a comparison to the same period in 2024
 provide an update around other anti-fraud activity
 provide a comparison of current fraud arrangements to best practice 
2. Recommendation(s)
2.1. The Committee is asked to approve the following recommendation(s):- 
(1) that the contents of this report be noted. 
3. Background
3.1. Collating and reporting fraud statistics and setting targets for improvement are
considered best practice by the Chartered Institute of Public Finance and
Accountancy and the Association of Local Authority Risk Managers.   
3.2. This report provides information on the overall fraud workload in 2024/2025 together
with a summary of the number, types and outcomes of fraud investigations within
South Lanarkshire Council (SLC) for the year and a comparison to the statistics for
the same period in 2024.   
3.3. Although the responsibility for housing benefit fraud investigations has transferred to
the Department for Work and Pensions (DWP) Fraud and Error Service (FES), SLC
retains responsibility for the recovery of fraud overpayments from its own Housing
Benefit claimants.  Housing Benefit fraud data will therefore continue to be included
within the fraud statistics reported, once information has been provided by FES.
Numbers are now reducing for new benefit overpayments as most claimants are now
in receipt of Universal Credit.   
3.4. Benefits and Revenue continue to deliver an annual programme of rolling reviews on
Housing Benefit claimants based on risk-profiling to establish the most likely areas of
benefit fraud or overpayment.  Information is also obtained from Her Majesty’s
Revenue and Customs (HMRC) through the Verification of Earnings and Pensions
arrangement, from Department for Work and Pensions (DWP) through the Housing
Benefit Matching Service and from data gathered through the National Fraud
Initiative.  Where fraud is suspected, the case will be passed to FES for investigation
and, if proven, returned to SLC to pursue recovery.  Irrespective of whether a fraud is
proven or not, the Council takes steps to recover any overpayment. 
8
161

Page 162

3.5 The collection and reporting of fraud statistics assists in the management of fraud by
identifying patterns and areas of high risk where preventative controls should be
concentrated. However, in order to do this effectively, fraud statistics must be
complete.  Internal Audit will continue to highlight areas where practice could be
improved to ensure that all instances of potential and actual fraud are reported to
Internal Audit.   
4. 2024/2025 Fraud Statistics, Workload and Outcomes 
Fraud Statistics
4.1. All concerns reported to Internal Audit are risk assessed with high risk areas
investigated by Internal Audit, medium risks investigated by Resources and low risks
registered for monitoring of trends.  Internal Audit may also undertake joint
investigations with Resources and the Fact-Finding team within Personnel Services
depending on the nature of the fraud and the operational knowledge required. 
4.2. Areas within the Council that have an inherently higher risk of fraud are considered
for inclusion in the annual Audit Plan.  There were no new trends or patterns
identified in 2024/2025.  Appendix 1 sets out a summary of the overall fraud
workload across the year.   
4.3. An analysis of the fraud caseload1 for the year to 31 March 2025, and the
comparative period in 2024 is detailed in Table 1. Cases reported in the year were
lower reflecting the transition from Housing Benefit to Universal Credit.   Fraud
referrals in this area are now mostly in relation to Council Tax Reduction. 
Status
Year to  
31/03/2025
Year to 
31/03/2024 
Nos. £000 Nos. £000
Cases open as of 1 April  171 44 136 70
Concerns reported during the financial year   30 9 101 32
SLC caseload for the year    201 53 237 102
Cases closed in period (see Table 2) (177)2 (48) (66) (58)
Work in progress at 31 March    24 5 171 44 
Table 1 
4.4. In addition to those cases summarised above, a further 18 SLC investigations are
being progressed by the DWP with a potential cumulative housing benefit
overpayment/fraud value of £7k.  On conclusion of investigations, SLC will seek
repayment in line with standard recovery procedures. 
4.5. An analysis of closed cases in the year is detailed in Table 2:- 
Source of fraud
Year to  
31/03/2025
Year to
31/03/2024 
Nos. £000 Nos. £000
Founded allegation (see Table 3) 14 11 19 56
Insufficient information 1 0 28 2
Unfounded allegations 44 37 19 0 
1 It includes all frauds reported to Internal Audit, benefit frauds during this period passed to the DWP for
investigation and insurance losses resulting from a failure in internal controls or which have been investigated
by Internal Audit. 
2 Cases where there is no housing benefit in the referral to DWP have been removed to reflect that these will
be treated as DWP fraud and any identified fraud or overpayment will impact benefits paid by DWP, such as
universal credit, rather than housing benefit administered by the Council.  
162

Page 163

No Housing Benefit in claim 118 0 0 0
Total 177 48 66 58 
Table 2 
4.6. An analysis of the founded allegations is detailed in Table 3:- 
Source of fraud
Year to  
31/03/2025
Year to
31/03/2024 
Nos. £000 Nos. £000
External  13 8 18 56
Internal  0 0 1 0
Benefits 1 3 0 0
Total 14 11 19 56
Table 3 
Wider Fraud Workload
4.7. Time spent on investigative work was broadly in line with the planned split of days
available across the year (127 days against a planned 100 days).  Six separate,
investigative assignments were completed in the year, including financial frauds,
grants and complaints about a process.  The majority, on investigation, found
substance to concerns or allegations and appropriate actions were agreed to
address the issue and amend processes going forward.  The nature of these
concerns was wide-ranging, and each of these was investigated in line with
established fraud procedures and reflecting the Council’s zero-tolerance approach to
fraud. 
4.8. External auditors are required to report significant fraud or suspected fraud to Audit
Scotland, where they were caused or facilitated by weaknesses in public bodies’
internal controls.  Frauds and irregularities are considered significant where the
value of the loss is over £5,000 or where it is of significance owing to the nature of
the activity. 
4.9. Audit Scotland routinely reports these significant frauds within technical bulletins,
which also includes details around improvements to controls to prevent similar frauds
occurring. Bulletins are reviewed and cases shared with relevant Services to assess
whether controls require amendment. 
4.10. Three of the 4 cases reported related to payroll fraud, and the fourth, the most
significant, was in relation to a Council Tax fraud at Aberdeen City Council, which
was the subject of a separate report by the Accounts Commission.  Given the
significance of the fraud, a series of actions was circulated to Local Authorities for
review and implementation.  Although controls within South Lanarkshire Council
were considered to be robust, further monitoring arrangements have now been put in
place with Internal Audit facilitating a data analytical review of payments ahead of
processing. 
4.11. Internal Audit has also monitored fraud alerts through internal and external sources
and disseminated information as appropriate.  In 2024/2025 these have continued to
relate to adhoc issues and have been shared with Council Resources as
appropriate.   
4.12. Outcomes from audit work completed in the year was reported in the 2024/2025
Internal Audit Annual Assurance Report or has been captured in the report on the
2022 National Fraud Initiative (NFI) exercise.   
163

Page 164

5. National Fraud Initiative 
5.1. Internal Audit coordinates the delivery of the NFI exercise3 within the Council, liaising
with Resources responsible for investigating matches relevant to them.  65 days
were included in the 2024/2025 Audit Plan to undertake this task.  A total of 28,090
matches were received for the 2022 exercise, which concluded on 31 March 2024.
This resulted in 317 recoverable fraud and errors being detected from matches
received and an (actual) amount to be recovered of £107,116. 
5.2. Preparation for the 2024 exercise began with the data extract and uploads being
completed at the end of September 2024. Matches started being released to the
Council at the end of 2024 / early 2025, and, as at April 2025, 32,675 matches have
been received. Target matches have been determined, and work has started within
Resources to investigate. This is anticipated to conclude early 2026 to meet the final
reporting deadline of 31 Match 2026 that has been set by the Cabinet Office.
Progress will be monitored and reported by Internal Audit, and assistance provided
where required, throughout 2025/2026. 
6. Three Lines of Defence – Fraud Risk Analysis 
6.1 Resource Fraud Risk Registers have again been reviewed and updated to
categorise controls that mitigate fraud risks using the Institute of Internal Auditors
‘three lines of defence’ methodology. This framework recognises that different parts
and levels of the organisation play complementary roles in risk management. 
Controls that form the first line of defence sit at a Service level with the second line
of defence being those that ‘oversee’ (senior management teams, Committees etc). 
The final level is that of independent assurance provided by internal and external
audit or external inspectors.  Good risk management will evidence controls across all
‘lines’.  Going forward, the review of these registers will align to the timetable of that
of the Council’s top risks. 
7. Comparison of Fraud Risk Arrangements to Best Practice
7.1. Periodic self-assessment exercises are undertaken to compare existing fraud
management arrangements to best practice to ensure that these are robust and that
the risk of fraud is being mitigated where possible.  Appendix 2 provides the self-
assessment exercise undertaken in 2024/2025 with highlighted areas where action is
ongoing. 
7.2. Although fraud control measures are embedded within processes, investigative work
undertaken by Internal Audit has identified that levels of fraud awareness could be
improved so that all employees are mindful of fraud risks, how these are managed
and controlled and how concerns should be reported.  A whistle-blowing process is
included within the Counter Fraud, Bribery and Corruption Policy but, was identified,
on review, as not being formally re-publicised on a regular basis.  To address this
gap, and to promote fraud awareness, a formal fraud awareness programme has
been developed for 2025/2026. 
7.3 Services work with the Security Coordinator or with Internal Audit to review and
address gaps in controls identified during the investigation of cases.  Where
appropriate, improvement plans are agreed with the relevant Heads of Service and
the actions followed up by Internal Audit to ensure implementation. Outcomes for
concluded investigations are reported to this Committee as part of Internal Audit’s
annual assurance report. 
3 Undertaken every 2 years
164

Page 165

8. Serious and Organised Crime Group
8.1 The multi-agency Lanarkshire Serious and Organised Crime (SOC) group has
recently agreed a new SOC Delivery Plan, which was launched at an awareness
event for partners on 1 May 2025. The Delivery Plan highlights key issues and
outcomes across the associated SOC themes of Divert, Deter, Detect and Disrupt.
The Delivery Plan launch was supported by the Scottish Government, and its
implementation will be reviewed by the multi-agency Lanarkshire SOC Group on a
six-monthly basis. 
8.2. Governance arrangements are currently being agreed between partners and further
high-level updates will be included within six-monthly fraud reports. 
9. Employee Implications
9.1. SLC has a zero tolerance approach to fraud. Manager and employee roles and
responsibilities are set out in SLC’s Counter Fraud, Bribery and Corruption Policy. 
10. Financial Implications
10.1. The investigation of fraud, participation in the National Fraud Initiative (NFI) exercise
and the collection and reporting of fraud statistics is carried out within existing
resources.   
11. Other Implications
11.1. Fraud risk is recognised as one of the top risks facing SLC.  This risk is significant as
it can adversely affect the delivery of Council objectives and erode valuable
resources.  It is therefore important that the risk of fraud is soundly managed.   
11.2. The new Failure to Prevent Fraud offence in the UK, introduced by the Economic
Crime and Corporate Transparency Act 2023, makes large organizations criminally
liable for failing to prevent fraud committed by an "associated person", for example
by an employee, agent or subsidiary if the fraud benefits the organisation. The
offence came into effect on 1 September 2025 and further updates around actions to
address any gaps in current practice will be provided to this Committee in December
2025 within the 2025/2026 Six Monthly Fraud report. 
11.3. There are no sustainability issues in terms of the information contained in this report.   
12 Integrated Impact Assessment and Consultation Requirements
12.1. There is no requirement to undertake an  integrated impact assessment. 
12.2. Consultation was not necessary for this report. 
Jackie Taylor
Executive Director (Finance and Corporate Resources) 
28 August 2025 
Link(s) to Council Values/Priorities/Outcomes
 Accountable, effective, efficient and transparent 
Previous References  
 Risk Audit Scrutiny Committee - 24 September 2024 (Fraud Statistics Annual Report
2023/2024) 
165

Page 166

 Risk Audit Scrutiny Committee - 24 September 2024 (National Fraud Initiative Exercise
Report 2022)
 Risk Audit Scrutiny Committee -18 February 2025 (Fraud Statistics Six Monthly Update
2024/2025) 
List of Background Papers
 None 
Contact for Further Information
If you would like to inspect the background papers or want further information, please
contact:- 
Yvonne Douglas, Audit and Compliance Manager
Ext:  2618  (Tel:  01698 452618)
E-mail:  yvonne.douglas@southlanarkshire.gov.uk 
166

Page 167

APPENDIX 1 
Summary of Enquiries received in relation to Suspected Fraud 2024/2025     
Category Number Comments
Whistleblowing  9 All 9 enquiries related to a suspected fraud and were investigated in line with protocols.
Missing Equipment  16 Log maintained by Internal Audit.  Assignment in progress to review controls.
Resource Fraud and
Conduct
13 9 from the 13 enquiries led to further investigation and were allocated audit job numbers and
added to the audit plan.  The other 4 required no further investigation. 
Other Local Authorities 4 Related to fraud within other Local Authorities and were investigated by Services.
Scottish Local Authority
Investigator’s Group
(SLAIG)
4 Enquiries via SLAIG from other Local Authorities. 
National Anti-Fraud Network
(NAFN) Alerts
32 Internal Audit regularly receive fraud alerts from NAFN which are disseminated to Services
for information and action.  Since October 2024, formal feedback is now requested given the
frequency of recurring issues.  Services are required to check for relevance, to implement
any recommended actions and to provide feedback.
Other External Bodies 2 1 notification related to a cyber-attack which was passed to IT.  The other related to a SLC
supplier and an email address being compromised.  Action was taken to mitigate the risk.
Police Scotland 1 System check.
TOTAL ENQUIRIES 81 
167

Page 168

APPENDIX 2 
Preventing Fraud – Self Assessment Checklist 
“Managing Fraud Risk in a Changing Environment – A Good Practice Guide” 
Consider each statement and determine whether it should be assessed as: 
Red: The area needs significant strengthening and improvement to reduce fraud risk. 
Amber: The area needs some strengthening and improvement to reduce fraud risk. 
Green: The area is strong, and fraud risk has been reduced to an acceptable level 
R A G Organisational Culture SLC Approach   
✓
Our organisation has a zero-tolerance approach to fraud and
corruption that is communicated to all staff in a policy. All staff
are aware of their role in relation to fraud prevention.
SLC has a zero tolerance to fraud, bribery and corruption.  A
counter fraud bribery and corruption policy are in place which
clearly states expected employee roles and behaviour.   
✓
There is clear commitment from senior management and the
Board that fraud will not be tolerated.
Clear commitment from senior management and Members to a
zero-tolerance approach.   
✓
We have communicated our zero tolerance of fraud to all staff,
contractors and other third parties with whom we do business.
They know what to do if they become aware of possible fraud.
The Council’s Counter Fraud, Bribery and Corruption Policy is
available to all employees.  Fraud awareness programme has
been developed for 2025/2026.   
✓
A designated senior manager has responsibility for counter
fraud work, sufficient resources for this work and direct access
to the Audit Committee.
The Audit and Compliance Manager has responsibility for counter
fraud work and has direct access to the Risk and Audit Scrutiny
Committee.   
✓
There is a code of conduct which sets out clearly for
employees’ which behaviour is acceptable or unacceptable. All
staff are required to sign up to this annually. The code
highlights that unethical behaviour will lead to disciplinary
proceedings.
A Code of Conduct is in place for all employees.  The Code
outlines what is acceptable.  Employees do not sign up to the
Code annually, however, they will be reminded on an annual basis
of the need to declare “Conflicts of Interest”.  Any employee who
does not comply with the Code will be taken through a disciplinary
process.     
✓
There are arrangements in place for reporting and addressing
conflicts of interest, including a register of interests. Staff are
made aware of the need to declare potential conflicts of
interest.
The Council has a Conflict of Interest Policy.   Annual reminder of
Conflict of Interest policy has been developed. 
Our organisation maintains a register of gifts and hospitality.
Staff are aware of the need to register any gifts and hospitality
Register maintained and guidance included within Conflict of
Interest policy.
168

Page 169

✓ received.  
✓
All staff attend regular fraud and ethics awareness training. The
effectiveness of the training is confirmed through testing. New
staff receive fraud and ethics awareness training at induction.
Developed as part of the fraud awareness programme which
commenced in June 2025 and then throughout 2025/2026.   
✓
Our organisation undertakes pre-employment screening by risk
assessing posts and undertaking checks to minimise the risk of
employing dishonest and unethical staff.
SLC undertakes the relevant and necessary screening checks. 
✓
Leavers and retirees are subject to an exit interview which is
designed to identify any vulnerability to fraud. The Audit
Committee is notified of any relevant concerns.
All employees who leave or retire should complete an exit
interview as part of the leaving process.  Outcomes reported to
the Finance and Corporate Resources Committee. 
✓
Our organisation has a counter fraud strategy in place, which
applies to all aspects of the business, is communicated across
the organisation and is overseen by those charged with
governance.
Yes, SLC has a counter fraud strategy in place which is for council
wide practice.     
Fraud Risk Assessment 
✓
Our organisation considers fraud risk as part of the overall risk
management process.
Yes, fraud risk is co-ordinated by Internal Audit on behalf of the
Council.  Fraud risks are incorporated into processes, procedures
and controls.   
✓
Our organisation has carried out a rigorous fraud risk
assessment in the last 2 years (more recently if a new or
merged organisation).
Fraud risk registers are in place for all Resources of the Council
along with Council-wide risks and controls.  Each register must be
reviewed by the Resource and updated annually (at a minimum)
for any new emerging fraud risks or controls implemented.  
✓
Our assessment of fraud risk is based on known fraud risks,
benchmarking with similar organisations and internal
brainstorming with frontline staff.
Based on known fraud risks and known emerging risks.  Council-
wide review process involves a bench-marking exercise.  
✓ Our fraud risk assessment has been reviewed and agreed by
the Audit Committee and/ or Board.
Risk Management Strategy is presented to the Risk and Audit
Scrutiny Committee.  
✓
Counter fraud staff and/or internal audit have a role in fraud-
proofing new policies, strategies and initiatives across our
organisation to minimise fraud risks.
As part of a rolling programme of testing.  
✓
Our fraud risk assessment is reviewed at regular intervals, and
particularly when our organisation changes, to ensure that any
new fraud risks are identified and addressed.
Annual exercise.   
Audit Committee 
✓ Our Audit Committee takes a proactive role with respect to
fraud prevention.
Receive six monthly and annual fraud statistic reports along with
reports on the National Fraud Initiative Exercise.  Output from
169

Page 170

investigations reported within routine activity reports and annual
reports.  
✓
Our Audit Committee is totally independent of management and
includes members with financial expertise.
Risk and Audit Scrutiny Committee operate as an independent
scrutiny committee.  Members receive periodic training to assist in
this role.  
✓
Our Audit Committee meets at least quarterly and devotes
sufficient time to providing assurance on our counter fraud
strategy
Audit Committee meets quarterly and devotes sufficient time to
consider anti-fraud arrangements.   
Internal Control Environment 
✓
Our internal controls have been designed to address identified
fraud risks and help prevent fraud occurring. The controls are
proportionate to the identified fraud risks.
Yes, controls address fraud risks.   Controls are designed to be
proportionate to assessed fraud risk.   
✓
Our internal control environment includes a range of
complementary controls (directive, preventive, detective and
corrective).
Yes, evidenced within Fraud Risk Registers.  
✓
All staff, contractors and other stakeholders are made aware
that there are controls in place to prevent and detect fraud, as a
deterrent.
Anti-fraud clauses within contracts.   
✓
Our fraud risk controls have been reviewed by internal audit
and the Audit Committee.
Yes, Internal Audit review fraud risk registers, which contain the
fraud risk controls for each Resource, to ensure they are relevant.   
✓
Internal Audit has a direct role in reviewing any new or
amended policies and programmes to ensure that fraud risk is
minimised at the outset.
As part of a rolling programme of testing.   
✓
Internal Audit tests controls to mitigate fraud risks as part of its
annual programme of work. 
Yes, all audit work is tested against fraud risks.   
Data Mining and Data Matching 
✓
We regularly use data analysis to detect potentially fraudulent
activity
Yes, Internal Audit uses data analysis on a regular basis to detect
fraud and have devised programmes to enable Resources to
monitor fraud.   
✓
Our IT and information systems include controls (such as
reconciliations, physical counts and analyses) designed to
detect potentially fraudulent activity
Yes, regular reviews are carried out and exceptions reports are
built into systems to enable monitoring.   
✓
Our data analysis controls include review of journal entries,
unusual transactions and period-end transactions, where fraud
may be concealed by management override.
Processes in place and audited by External Audit as part of the
financial year-end audit.   
We share data and participate in data matching exercises (e.g. Yes, SLC takes part every 2 years in the NFI exercise.
170

Page 171

✓ the National Fraud Initiative) to help in the prevention and
detection of fraud.  
✓ We act promptly on any issues of concern identified through
data mining and data matching.
Yes, any concerns are investigated immediately.   
Whistleblowing Arrangements 
✓
Our organisation has an internal whistleblowing policy and
procedures in place which are known to all staff. Staff are
regularly reminded of the policy and procedures.
Yes, SLC has a Whistleblowing policy which can be accessed
both internally and externally for members of the public. Included
within the fraud awareness programme which commenced in June
2025 and then throughout 2025/2026.   
✓
Our whistleblowing arrangements are endorsed by senior
management and the Board and include an assurance that all
concerns raised will be welcomed and treated seriously.
Yes, SLC’s Whistleblowing policy has been approved by senior
management and by Committee.  The policy states that all
whistleblowing communications will be investigated.   
✓
The policy and procedures make clear how, and with whom,
staff should raise concerns about possible fraud. A range of
internal and external reporting options is given.
Yes, clearly stated in policy.  
✓ The policy and procedures make clear how we will handle any
concerns raised.
Yes, states the process.  
✓
Our whistleblowing policy provides reassurance that employees
will not be victimised or suffer detriment for raising concerns.
We monitor to ensure this commitment is borne out in practice.
Whistle-blowing policy commits to protection of anonymity.  
✓
Our whistleblowing policy provides assurance about
confidentiality. Confidentiality is respected as far as possible in
practice.
Yes, all whistleblowing communications are treated confidentially.   
✓
Our whistleblowing policy allows for anonymous disclosures,
which will be treated seriously, but points out the disadvantages
of anonymous disclosures.
Yes, the policy states that a communication can be anonymous.   
✓
There is a clear process by which contractors, third parties and
members of the public can raise concerns about possible fraud
in our organisation, for example a fraud hotline. Details are
easily accessible on our website.
SLC has a generic fraud email address which can be accessed by
members of the public as well as employees.  Suspected fraud
can also be reported via the customer relationship management
system (CRM) or by telephone.  
✓ 
We review our whistleblowing arrangements periodically to
ensure their continued effectiveness. We seek views from
employees as to their level of trust and confidence in the
arrangements.
We review the policy periodically.  Feedback will be sought as part
of the fraud awareness programme which commenced in June
2025 and then throughout 2025/2026. 
✓
We maintain confidential case files on all concerns raised and
analyse the caseload for indications of systemic control
weaknesses.
All whistleblowing concerns sent to IA are confidentially retained.  
171

Page 172

✓ We report on whistleblowing caseload to the Audit Committee. Included within fraud statistic reports and routine activity reports to
the Risk and Audit Scrutiny Committee.   
Fraud Response Plan 
✓
Our organisation has a comprehensive fraud response plan in
place. The plan is approved by the Audit Committee and Board.
The fraud response process is incorporated into the Counter
Fraud, Bribery and Corruption Strategy which has been approved
by the Risk and Audit Scrutiny Committee.  
✓ The fraud response plan makes clear that all allegations of
fraud will be investigated and appropriate action taken.
Yes, all allegations of fraud are taken seriously and investigated. 
Action will be taken where fraud is identified.  
✓ All allegations of fraud, including anonymous allegations, are
assessed in line with the fraud response plan.
Yes, all allegations will be investigated in line with the response
plan.   
Fraud Investigations 
✓  The fraud response plan clearly documents the procedures for
fraud investigations.
Wording in the Counter Fraud, Bribery and Corruption Strategy
will be reviewed at next revision to ensure this is clear.  
✓ All fraud investigations are carried out in accordance with the
fraud response plan.
All completed within established protocols and procedures.  
✓
There are arrangements in place for securing fraud
investigation expertise from outside the organisation, if
required.
Not routinely required but would be secured if expertise required.   
Sanctions and Redress 
✓
In responding to proven fraud, we consider the full range of
possible sanctions – disciplinary, regulatory, civil and criminal.
Where appropriate we consider parallel sanctions.
Independent decision by Personnel Services.  Decision to report
to the Police determined following established protocol. 
✓ The fraud response plan makes clear that we will seek to
recover any losses incurred due to fraud.
The Council policy is to seek any losses incurred due to fraud.   
Fraud Reporting and Case Review 
✓ All frauds are brought to the attention of the Board and Audit
Committee.
All are reported within activity, fraud and annual assurance
reports.  
✓ We review and strengthen systems and controls in light of
proven frauds.
Yes, additional controls will be implemented where relevant
following the identification of a fraud.  
✓ We report annually to the Board and Audit Committee on fraud
caseload.
Yes, a report is provided to the senior management and the Risk
and Audit Scrutiny Committee on a six-monthly basis.  
✓ We report all frauds to external third parties as required. Reported to Police as required.  
✓
We publicise proven frauds, and action taken in response to the
frauds, both internally and externally as appropriate, as a
deterrent.
Addressed by the fraud awareness programme. 
172

Page 173

Report
Agenda Item 
Report to: Risk and Audit Scrutiny Committee
Date of Meeting: 30 September 2025
Report by: Executive Director (Finance and Corporate Resources) 
Subject: Year End Insured Claims Report – 2024/2025 
1. Purpose of Report
1.1. The purpose of the report is to:-
[purpose}
 highlight trends on an annual basis, for insurance claims against the Council
[1purpose]
2. Recommendation(s)
2.1. The Committee is asked to approve the following recommendation(s):-
[recs]
(1) that the Insured Claims Report for year ended 31 March 2025 be noted.
[1recs]
3. Background
3.1. The Council has in place insurance policies for employers’ liability, public liability,
motor, property and other miscellaneous risks. 
3.2. The combined liability policy covers both public liability (PL) and employer’s liability
(EL) claims.  The PL section of the policy provides indemnity for the Council’s legal
liability to pay claims for death, injury and disease to third parties, as well as third party
property damage, where the Council is found to be responsible for such losses.  The
EL section of the policy covers employee injury, disease, and death, where the Council
is deemed to be negligent.  The self-insured excess for this policy is £0.500 million. 
3.3. Motor insurance provides comprehensive cover for all Council vehicles and injuries
resulting from motor incidents.  The self-insured excess for this policy is £0.150 million. 
3.4. The property insurance policy covers damage/loss to Council buildings and assets. 
The self-insured excess for this policy is £0.500 million for all claims other than for
storm and flood where a £1.000 million excess applies.  
4. Five Year Overview
4.1. Claims which fall under the main policies are handled by the Council’s Risk
Management section and external claims handlers, Gallagher Bassett for employer’s
liability and public liability claims, and the Davies Group for motor claims.  The number
and cost of these claims form the basis of this report and includes comparisons with
previous years. 
4.2. Claims will continue to be intimated beyond the financial year end, with numbers
increasing by approximately 10 per cent due to those incidents that have taken place,
but claims have not yet been reported to the Council.   
4.3. Up to date annual comparisons for the last five years are included at Appendix 1.  The
comparison shows that claim numbers have fluctuated over the period, with the
9
173

Page 174

highest number of claims being intimated in 2023/2024 (886). The average number of
claims intimated each year is 840, therefore with 846 claims intimated for 2024/2025,
last year’s claim numbers are around the average figure. It should be noted that
2020/2021 experienced an unusually low number of claims, due to reduced operations
at the start of the pandemic, which affects the 5-year average figure.   
4.4. Claims costs have also fluctuated over the last five years.  On average, over that
period, the self-insured cost of claims per annum is £2.882 million, with 2024/2025
costs notably above average at £4.137 million. It should be noted however that last
year’s figures are higher due to a single significant storm event (Storm Eowyn).
Inflation, increased costs of materials, car parts and repair charges has impacted on
claim values also.   
4.5. In addition, to allow comparison of the position as at the year-end for the last two years,
Appendix Two compares the claim numbers and costs for incidents reported in
2023/2024 as at 31 March 2024 against incidents reported in 2024/2025, as at
31 March 2025.  In effect, this compares the equivalent position and removes the
impact of late claims notification for both years.   
5. Total losses reported as at 31 March each year – 2023/2024 v 2024/2025
5.1. Based on the comparisons in Appendix 2, the overall number of claims for all classes
received to date for incidents occurring during 2024/2025 is 846.  This is a reduction
of 40 claims (4.5 per cent) on the numbers reported last year for 2023/2024.   
5.2. The total self-insured estimated cost of claims for 2024/2025 is £4.137m.  At the same
time last year estimated claims costs for 2023/2024 was £3.548m.  This is an increase
of £0.589m (16.6 per cent), which is a result of the estimated cost of property and
motor claims increasing, with the position being offset slightly by reduced estimated
costs for liability claims.  Aside from the fluctuations across the different classes of
cover, the main reasons for the increase in costs last year is due to Storm Eowyn
occurring at the start of the year. 
5.3. Based upon Appendix 2, sections 6 to 8 detail some of the key findings from the
analysis of 2024/2025 claims. 
6. Combined liability claims
6.1. The combined liability policy covers for both public liability (PL) and employer’s liability
(EL) claims.  The PL section of the policy provides indemnity for the Council’s legal
liability to pay claims for death, injury and disease to third parties, as well as third party
property damage, where the Council is found to be responsible for such losses.  The
EL section of the policy covers employee injury, disease, and death, where the Council
is deemed to be negligent.  The following sections detail the current position for
2024/2025 and make comparisons against the position reported for 2023/2024 as at
31 March 2024. 
6.2. 415 liability claims have been received for 2024/2025, with an estimated value of
£1.308 million. 
6.3. The number of claims received for 2023/2024 was 415 and the estimated settlement
value of these claims was £1.361 million.  The 2024/2025 number of claims received
is the same as that for 2023/2024, however there has been a 3.85 per cent decrease
in claims costs. 
174

Page 175

6.4. A further breakdown of public liability claims numbers and costs specifically for Roads
and for other services within Community and Enterprise Resources is contained within
Appendix 3. 
7. Motor claims
7.1. The Council’s motor insurance policy provides comprehensive cover for all Council
vehicles and injuries resulting from motor incidents.  The following sections detail the
current position for 2024/2025 and makes comparisons against the position reported
for 2023/2024 as at 31 March 2024.   
7.2. 370 motor claims have been received for 2024/2025, with an estimated value of £0.880
million. 
7.3. At the same time last year, 394 motor claims had been received for incidents during
2023/2024, with an estimated settlement value of £0.697 million.  This equates a 6 per
cent reduction in claim numbers and a 26 per cent increase in costs. 
7.4. The rising cost of vehicle parts and repairs is impacting upon the cost of claims and
delays obtaining car parts is leading to an increase in third party hire charges.   
7.5. “At fault” incidents continue to be monitored.  Table 1 compares the number and cost
of “at fault” incidents for the last 5 years. 
Table 1 – Comparison of “at fault” incidents    
Number of
vehicles on
fleet
Number
of
incidents
Cost of
incidents
Number of
Accidents
per vehicle
Average
cost per
incident
2020/2021 1,808 127 £328,250 1:14 £2,585
2021/2022 1,834 189 £432,672 1:10 £2,289
2022/2023 1,700 200 £471,263 1:12 £2,356
2023/2024 1,676 183 £315,447 1:11 £1,724
2024/2025 1,643 189 £527,662 1:12 £2,792 
7.6. The number of “at fault” incidents, per vehicle has improved sightly from last year. 
With one “at fault” incident per every 12 vehicles for 2024/2025, this is in line with the
average for the four previous years. 
7.7. Reports on motor insurance claims are provided to Resources on a quarterly basis,
with Resources being prompted to implement support and actions to mitigate against
future losses. This includes completion of challenging driver behaviour training,
assessments and targeted support that can be offered by our driving
instructors/assessors, as well as fact finding investigations where appropriate. 
8. Property claims
8.1. The property insurance policy covers damage/loss to Council buildings and assets. 
This section of the report details the current claim position for 2024/2025 and makes
comparisons against the status reported for 2023/2024 as at 31 March 2024.   
8.2. 61 property insurance claims have been received for 2024/2025, with an estimated
self-insured value of £1.950 million. 
8.3. The overall number of claims intimated for 2024/2025 has decreased by 16 from the
previous year, which equates to a 21 per cent reduction. The value of estimated claims
intimated during 2024/2025 at £1.950m is an increase of £0.459 million from
2023/2024, a 31 per cent increase.  175

Page 176

8.4. The reason for the increase is due to Storm Eowyn that resulted in damage to Council
properties, mainly housing stock, and an increased number of fires within the housing
stock. 
8.5. Significant weather related events have resulted in large claims over each of three
winters. It is expected that this trend will continue and that we should, as a minimum
account for estimated self-insured costs in the region of £1 million each year.
Insurance premiums have also increased significantly as a result of these claims and
insurers weather modelling.   
8.6. The main cause of property claims during 2024/2025 continues to be fires.  The
number of house fires resulting in insurance claims has increased by four, from 27
incidents in 2023/2024 to 31 in 2024/2025.  Costs over this period have increased by
£0.237m, from £0.507m in 2023/2024 to £0.744m in 2024/2025.  The main causes of
fires within Council housing are wilful fire raising, cooking and cigarettes/smoking
materials. The council continues to raise awareness of fire risks and preventative
measures in conjunction with the Scottish Fire and Rescue Service. 
9. Insurance hotspots/Lessons Learned
9.1. Following a health and safety training review by Gallagher Bassett last year an action
plan was prepared to help mitigate against accidents and claims. 
9.2. 81.8 per cent of actions with a target date of up to 31 March 2025, have been
completed.   
9.3. Table 2 below shows the overall status for all actions due as at 31 March 2025. 
Table 2 – Completion of GB H&S Review actions
Action status Number of
actions
Percentage
of actions
On hold 0 0%
Complete 9 81.8%
On target 0 0%
Slippage 2 18.2%
Total 11 100.0% 
9.4. Slippage has occurred in actions relating to manual handling training and health
surveillance.  Progress towards completion has been made in both actions, and it is
anticipated that these actions will be finalised by 31 December 2025. 
9.5. The actions noted above as being “slippage” have been carried forward.  These
actions, along with those with target dates during 2025/2026 will be progressed
accordingly. 
9.6. An analysis of all claims has been undertaken by the Council’s Risk Management
team. This highlights the main cause of claims and areas of concern within each
Resource, which includes house fires for Housing and Technical Resources,
increasing number of motor incidents within Social Work Resources, injuries to
teaching staff in Education Resources, and damage caused by falling trees and
branches during inclement weather is an emerging claim trend in Community and
Enterprise Resources.  This analysis has now been shared with Resources and
feedback requested on controls that are currently in place and further planned actions
to mitigate against the hotspot areas identified. 
176

Page 177

9.7. An update on risk mitigations will be provided to committee in due course. 
10. Employee Implications
10.1. Time and effort will continue to be required by Resource personnel to deal with the
significant number of claims intimated. Resource Personnel will also require to
dedicate time to implementation of initiatives to mitigate insurance hotspots. 
11. Financial Implications
11.1. Claims received to date, for incidents which occurred during 2024/2025 have an
estimated self-insured cost of £4.137 million.  It is reasonable to expect this value to
increase due to incidents that have taken place, but claims have not yet been received.   
11.2. During 2024/2025, a total of £4.195 million was paid out by the Council on all claims,
irrespective of their incident date.  For claims which occurred between 1 April 2024
and 31 March 2025, £0.466 million was paid out by the Council.  These costs include
claims payments and other associated costs. 
11.3. The total cost of loss for 2024/2025 was £6.947 million.  This covers self-insured
claims costs, (£4.137 million) insurance premiums (£2.810 million), and other costs for
contracted insurance services.  For 2023/2024 the total cost of loss was £5.853 million
(£3.361 million for claims and £2.492 million for premiums). 
11.4. The balance in the insurance fund will require to be closely monitored to ensure
adequate funds are available to meet known liabilities. 
12. Climate Change, Sustainability and Environmental Implications 
12.1.  There are no implications for climate change, sustainability or the environment in terms
of the information contained in this report. 
13. Other Implications
13.1. The cost of insurance claims and premiums is linked to the Council top risk on budget
gaps/pressures. 
13.2. Over the last 5 years, the Council’s claims handlers have repudiated a total of 1,538
public liability claims, which reduces the potential level of claim settlements. This
equates to a repudiation rate of 66 per cent. 
13.3. Failure to adequately manage insurance hotspots is likely to lead to increased claims
numbers, self-insurance costs and insurance premiums.  This risk is mitigated through
the insurance hotspots review and associated action plans and other risk management
initiatives implemented by Resources. 
13.4. There are no implications for sustainability in terms of the information contained in this
report. 
14. Integrated Impact Assessment and Consultation Requirements
14.1. There is no requirement to carry out an impact assessment in terms of the proposals
contained within this report. 
14.2. Copies of this report will be passed to the Resource Risk Representatives. 
177

Page 178

Jackie Taylor
Executive Director (Finance and Corporate Resources) 
5 September 2025 
Link(s) to Council Values/Priorities/Outcomes
 Accountable, Effective, Efficient and Transparent 
Previous References
 Risk and Audit Scrutiny Committee – 2023/2024 Year End Insured Risks – 24
September 2024 
List of Background Papers
 Insured Claims Annual Report for year ended 31 March 2025 
Contact for Further Information
If you would like to inspect the background papers or want further information, please
contact:-
Craig Fergusson, Head of Finance (Transactions)
Ext:  4951 (Tel: 01698 454951)
E-mail:  craig.fergusson@southlanarkshire.gov.uk
178

Page 179

Appendix 1 
Full year claims numbers and values by Resource as at 31 March 2025. 
All claim types     
Number of claims 2020/21 2021/22 2022/23 2023/24 2024/25
Community and Enterprise 522 517 537 642 478
Education 22 39 28 41 17
Finance and Corporate 1 0 2 6 2
Housing and Technical 262 306 319 254 245
Social Work 84 103 107 120 104
Total 891 965 993 1,063 846
Reported at individual year end 768 822 879 886        
Cost of claims 2020/21 2021/22 2022/23 2023/24 2024/25
Community and Enterprise £758,450 £1,041,232 £749,519 £1,048,617 £1,447,836
Education £372,667 £336,632 £210,522 £300,535 £70,980
Finance and Corporate £0 £0 £15,000 £109,702 £30,000
Housing and Technical £635,397 £820,899 £1,454,329 £2,122,557 £2,406,922
Social Work £548,789 £309,008 £299,848 £311,229 £181,503
Total £2,315,304 £2,507,770 £2,729,218 £3,892,639 £4,137,241
Reported at individual year end £2,009,739 £2,241,620 £2,474,988 £3,548,238              
Combined Liability          
Number of claims 2020/21 2021/22 2022/23 2023/24 2024/25
Community and Enterprise 310 281 335 410 285
Education 11 35 18 21 10
Finance and Corporate 1 0 2 5 2
Housing and Technical 167 177 184 123 113
Social Work 11 9 9 32 5
Total 500 502 548 591 415            
Cost of claims 2020/21 2021/22 2022/23 2023/24 2024/25
Community and Enterprise £298,270 £387,676 £391,317 £587,687 £848,757
Education £357,691 £334,984 £204,085 £221,282 £60,740
Finance and Corporate £0 £0 £15,000 £109,702 £30,000
Housing and Technical £359,368 £383,021 £437,373 £444,514 £335,466
Social Work £493,093 £236,628 £206,360 £163,298 £32,810
Total £1,508,422 £1,342,309 £1,254,135 £1,526,483 £1,307,773            
Motor          
Number of claims 2020/21 2021/22 2022/23 2023/24 2024/25
Community and Enterprise 189 213 187 211 180
Education 1 2 7 10 4
Finance and Corporate 0 0 0 1 0
Housing and Technical 56 94 114 94 94
Social Work 63 84 91 79 92
Total 309 393 399 395 370            
Cost of claims 2020/21 2021/22 2022/23 2023/24 2024/25
Community and Enterprise £434,102 £453,421 £345,489 £441,177 £468,057
Education £1,163 £1,297 £5,283 £5,533 £3,765
Finance and Corporate £0 £0 £0 £0 £0
Housing and Technical £90,064 £174,809 £231,375 £244,763 £259,737
Social Work £55,152 £65,552 £92,912 £147,470 £148,393
Total £580,481 £695,079 £675,060 £838,943 £879,951         
179

Page 180

Property          
Number of claims 2020/21 2021/22 2022/23 2023/24 2024/25
Community and Enterprise 23 23 15 21 13
Education 10 2 3 10 3
Finance and Corporate 0 0 0 0 0
Housing and Technical 39 35 21 37 38
Social Work 10 10 7 9 7
Total 82 70 46 77 61            
Cost of claims 2020/21 2021/22 2022/23 2023/24 2024/25
Community and Enterprise £26,078 £200,135 £12,714 £19,754 £131,022
Education £13,812 £350 £1,153 £73,720 £6,475
Finance and Corporate £0 £0 £0 £0 £0
Housing and Technical £185,966 £263,069 £785,581 £1,433,280 £1,811,719
Social Work £544 £6,828 £576 £461 £300
Total £226,400 £470,382 £800,025 £1,527,215 £1,949,517 
180

Page 181

Appendix 2
Comparison of claims costs and numbers for claims occurring during the last 2 years as at
their respective year ends 
All claim types    
Number of claims 2023/24 as
at 31 March
2024
2024/25 as
at 31 March
2025
Difference Difference
Percentage
Community and Enterprise 541 478 -63  -11.65%
Education 35 17 -18  -51.43%
Finance and Corporate 2 2 0  0.00%
Housing and Technical 205 245 40  19.51%
Social Work 103 104 1  0.97%
Total 886 846 -40  -4.51%     
Cost of claims 2023/24 as
at 31 March
2024
2024/25 as
at 31 March
2025
Difference Difference
Percentage
Community and Enterprise £1,283,276 £1,447,836 £164,560 12.82%
Education £202,275 £70,980 -£131,295 -64.90%
Finance and Corporate £16,500 £30,000 £13,500 0.00%
Housing and Technical £1,851,783 £2,406,922 £555,139 29.98%
Social Work £194,404 £181,503 -£12,901 -6.64%
Total £3,548,238 £4,137,241 £589,003 16.60%     
Combined liability    
Number of claims 2023/24 as
at 31 March
2024
2024/25 as
at 31 March
2025
Difference Difference
Percentage
Community and Enterprise 309 285 -24 -7.77%
Education 15 10 -5 -33.33%
Finance and Corporate 1 2 1 100.00%
Housing and Technical 75 113 38 50.67%
Social Work 15 5 -10 -66.67%
Total 415 415 0 0.00%     
Cost of claims 2023/24 as
at 31 March
2024
2024/25 as
at 31 March
2025
Difference Difference
Percentage
Community and Enterprise £818,300 £848,757 £30,457 3.72%
Education £98,354 £60,740 -£37,114 -37.74%
Finance and Corporate £16,500 £30,000 £13,500 81.82%
Housing and Technical £344,890 £335,466 -£9,424 -2.73%
Social Work £82,620 £32,810 -£49,809 -60.29%
Total £1,360,664 £1,307,773 -£52,390 -3.85%     
Motor    
Number of claims 2023/24 as
at 31 March
2024
2024/25 as
at 31 March
2025
Difference Difference
Percentage
Community and Enterprise 211 180 -31  -14.69%
Education 10 4 -6  -60.00%
Finance and Corporate 1 0 -1  0.00%
Housing and Technical 93 94 1  1.08%
Social Work 79 92 13  16.46%
Total 394 370 -24  -6.09% 
181

Page 182

Cost of claims 2023/24 as
at 31 March
2024
2024/25 as
at 31 March
2025
Difference Difference
Percentage
Community and Enterprise £421,169 £468,057 £46,888 11.13%
Education £6,926 £3,765 -£3,162 -45.65%
Finance and Corporate £0 £0 £0 0.00%
Housing and Technical £157,583 £259,737 £102,153 64.83%
Social Work £110,935 £148,393 £37,458 33.77%
Total £696,614 £879,951 £183,337 26.32%     
Property    
Number of claims 2023/24 as
at 31 March
2024
2024/25 as
at 31 March
2025
Difference Difference
Percentage
Community and Enterprise 21 13 -8  -38.10%
Education 10 3 -7  -70.00%
Finance and Corporate 0 0 0  0.00%
Housing and Technical 37 38 1  2.70%
Social Work 9 7 -2  -22.22%
Total 77 61 -16  -20.78%     
Cost of claims 2023/24 as
at 31 March
2024
2024/25 as
at 31 March
2025
Difference Difference
Percentage
Community and Enterprise £43,807 £131,022 £87,215 199.09%
Education £96,995 £6,475 -£90,520 -1397.99%
Finance and Corporate £0 £0 £0 0.00%
Housing and Technical £1,349,310 £1,811,719 £462,409 34.27%
Social Work £850 £300 -£550 -64.71%
Total £1,490,962 £1,949,517 £458,555 30.76% 
182

Page 183

Appendix Three
Public Liability – Community and Enterprise Resources Roads and other claims as at 31
March 2025 
Number of claims        
20/21 21/22 22/23 23/24 24/25 Total
Roads claims - injury 71 58 48 50 43 270
Community and Enterprise
Resources other - injury 8 8 10 12 5 43
Roads claims – property damage 179 161 225 242 178 985
Community and Enterprise
Resources other – property damage 40 48 41 45 46 220
Total 298 275 324 349 272 1,518 
Cost of claims        
20/21 21/22 22/23 23/24 24/25 Total
Roads claims - injury £156,244 £233,702 £167,819 £150,796 £458,051 £1,166,612
Community and Enterprise
Resources other - injury £15,759 £875 £81,722 £37,610 £70,050 £206,016
Roads claims – property damage £47,303 £33,576 £17,115 £44,769 £55,879 £198,641
Community and Enterprise
Resources other – property damage £7,167 £5,682 £18,607 £30,951 £43,252 £105,658
Total  £226,473 £273,834 £285,263 £264,126 £627,232 £1,676,927
*Note number and cost of these public liability claims are also contained in Appendix 1. 
183

Page 184

184

Page 185

Report
Agenda Item 
Report to: Risk and Audit Scrutiny Committee
Date of Meeting: 30 September 2025
Report by: Executive Director (Finance and Corporate Resources) 
Subject: Year-End Risk Management Report - 2024/2025 and
Review of Council's Top Risks - 2025/2026   
1. Purpose of Report
1.1. The purpose of the report is to:-
SAD
 provide the Risk and Audit Scrutiny Committee (RASC) with an update on progress
with risk management activity undertaken during 2024/2025 
 provide an update on the Council’s top risk register following the review and
consultation process 
2. Recommendation(s)
2.1. The Committee is asked to approve the following recommendation(s):-
[recs]
(1) that Resource compliance with the requirements of the Risk Management
Strategy be noted;
(2) that the progress being made in delivering actions to mitigate top Council risks
be noted; and
(3) that the updated Council top risks detailed in Appendix 2 be noted. 
3. Background
3.1. Annual reviews of the Council’s top risks are undertaken, with the findings of the last
review reported to the RASC on 24 September 2024. This year’s full review
commenced in April 2025.  The consultation involved views being sought from Heads
of Service, Elected Members and Trade Unions on new areas of risk. 
3.2. The results of the work undertaken were considered and used to inform proposals for
a refined set of top risks.  The feedback was used to review risk descriptions, as
required.   
3.3. The content of this report provides the Committee with the outcome of the review of
these risks. 
3.4. The Council’s updated Risk Management Strategy, which was presented to RASC on
24 September 2024, was rolled out via a Management Bulletin with an effective date
of 1 April 2025.   
4. Resource compliance with the Risk Management Strategy 
4.1. Risk Sponsors are required on an annual basis to assess Resource compliance with
the Risk Management Strategy and provide supporting evidence.  The information for
2024/2025 is summarised in the end-of-year compliance statement, which is attached
as Appendix 1. 
10
185

Page 186

4.2. Appendix 1 shows that Resources continue to demonstrate full compliance with the
Strategy, having scored 45 out of 45. 
4.3. It is important that the current level of compliance is maintained to demonstrate
effective risk management, which contributes to robust service planning and improved
decision-making. 
5. Progress made in delivering actions to control the Council’s top risks
5.1. As at 31 March 2025, the percentage of actions completed on the 2024/2025 risk
control plan was 73.4% against an overall target of 90%. 
5.2. Table 1 below shows the overall status as at 31 March 2025 for all actions relating to
the Council’s top risk register. 
Table 1 – Completion of top risk control actions
Action status Number of
actions
Percentage
of actions
On hold 2 13.3%
Complete 11 73.4%
On target 0 0.0%
Slippage 2 13.3%
Total 15 100.0% 
5.3. The actions that are on hold or where slippage has occurred relate to Community
Planning and IT forecasting.  These actions have been carried forward to next year’s
risk control plan. 
5.4. Actions carried forward along with those identified during this year’s review have been
included within the 2025/2026 top risk control plan.     
6. Results of the review of the Council’s top risks 
6.1. To assist the review process, the following broad criteria were recommended as a
guide to concluding what constitutes a top risk:- 
 it threatens the delivery of corporate objectives
 it impacts other services or partnerships
 there are financial impacts, or impacts on other key priority strategies
 there are impacts of a social or demographic context 
6.2. Risks from last year’s review were mostly deemed to be still valid. The main changes
and developments with the top risks are summarised below:- 
 Risks Removed 
“The Council is materially affected by the implications arising from the National  
Care Service (NCS) Bill” 
On 23 January, the Government published amendments which delete the entirety
of Part 1 of the National Care Service (Scotland) Bill.  This means that all the
structural reforms in the original NCS bill (and the government’s proposed draft
Stage 2 amendments) have been dropped.  This is therefore no longer
considered a Council Top risk. 
186

Page 187

“The Council inherits commercially unviable shopping centres due to the financial
failure of existing owner/management companies, resulting in significant financial
and operational liabilities transferring to the Council.” 
This risk has been removed following the recent sale of the Regent Shopping
Centre in Hamilton and agreement to demolish Centre West in East Kilbride. 
There are no other shopping centres where ownership may transfer back to the
Council due to Council ownership of land. 
 Risks Consolidated
Table 2 details risks that have been consolidated this year, given that they are
closely related.  The new risk wording is intended to cover all types of civil
emergencies rather than a specific pandemic/endemic event. 
Table 2 – Consolidated Risks
2024 Risks 2025 Risk
 Failure to fulfil emergency
response commitments befitting
the Council’s status as a Category
One (emergency) responder 
 The Council does not have the
appropriate emergency/business
continuity plans, contingency
arrangements, or partnerships in
place to respond to/or recover
from a pandemic/endemic event
 The Council does not have the
appropriate resilience
measures, emergency or
business continuity plans in
place to respond efficiently as a
Category 1 Responder to a civil
emergency. 
 Changes to Residual Risk Scores
Table 3 provides a summary of changes to risk scores 
Table 3 – Amendments to Risk Scores
Risk Residual
Risk
Score
2024
Residual
Risk
Score
2025
Change
in
residual
score
Reason/comments
The Council fails to
comply with or meet
the expected
standards of scrutiny
and deliver the
improvement actions
identified by
regulatory bodies
20 16  As a result of the
Council receiving
positive inspection
reports the residual
risk score has been
reduced
187

Page 188

Risk Residual
Risk
Score
2024
Residual
Risk
Score
2025
Change
in
residual
score
Reason/comments
Due to the fragility
and lack of capacity
of the third and
private sector market,
providers are
potentially unable to
sustain their business
models, which could
result in a
deterioration of their
service standards
and/or provider
failure.  This could
result in the Council
seeking alternative
service provision in a
reduced marketplace
to allow us to meet
the demand for
services
12 16  The increase in risk
score reflects areas
of uncertainty such
as changes to
employer NI
contributions which
will affect all
sectors. 
Changes for
International
Workers in Care - In
May 2025, the UK
Government
announced plans to
end overseas
recruitment for
social care workers.
Barriers related to
the recruitment and
employment of
skilled care workers
will put additional
pressure on the
delivery of care
services in
Scotland 
Information
governance not
subject to adequate
control
12 16  Information
governance has
been added as a
new area in the
annual governance
statement for
2024/2025 due to
an awareness of
the impact of
security information
incidents. 
The perception of
this risk is increased
with the introduction
of new IT systems
planned for
2025/2026.
Inability to ensure
public protection and
safety
16 12  The overall risk
score has
reduced given
that the Council
is compliant with
legislation and
188

Page 189

Risk Residual
Risk
Score
2024
Residual
Risk
Score
2025
Change
in
residual
score
Reason/comments
has sound
governance
processes in
place. 
Following the
move from
analogue to
digital telephone
networks, there
has been periods
of disruption
experienced with
the community
alarm system. 
There are well
established
business
continuity plans
in place to
mitigate against
such risks, with a
focus on
communication
with service
users and next of
kin.
The provision of
Council services is
disrupted because of
industrial action
16 12  The residual risk
has been reduced
due to the recent
agreement of a 2-
year pay deal for
staff members, with
the exception to
teaching staff.
Inability to maintain
infrastructure, assets
and properties in a
well-maintained
condition and
difficulties achieving
the objectives of
asset and property
reviews
9 12  The increase in risk
score reflects an
ageing property
asset portfolio
against limited
funding available to
maintain.  
The Council does not
fully deliver the
strategic outcomes
required of the
Integration Joint
Board (IJB) as
outlined in their
20 9  The risk score
has reduced
given that sound
arrangements
are in place for
the IJB to offer
direction to South
189

Page 190

Risk Residual
Risk
Score
2024
Residual
Risk
Score
2025
Change
in
residual
score
Reason/comments
Strategic
Commissioning Plan
Lanarkshire
Council and/or
NHS Lanarkshire
in the delivery of
the new plan for
2025 to 2028.
The reduction
also reflects
robust
governance
arrangements in
place in each
organisation
which mitigate
against
unfavourable
outcomes. 
The Council fails to
comply with its
statutory duties by
not conducting
sufficiently robust
impact assessments
where the same are
required, including in
respect of
budget/service
redesign proposals,
leading to potential
legal and financial
challenges, which
could result in failure
to deliver those
proposals
16 9  The residual score
has decreased as a
result of the new
integrated impact
assessment
process now being
in place, with
training undertaken
across relevant staff
groups. 
 Changes to Risk Wordings
Some key risk wordings have been updated to reflect the current status of risks
and/or to provide more straightforward and understandable risk descriptions. 
Amendments of note are summarised below:- 
 “Housing Emergency” has been added to the risk description “inability of the
Council to effectively provide accommodation and support to households who are
homeless and people who arrive in South Lanarkshire as part of refugee
resettlement and the asylum seeker dispersal programmes (including those for
unaccompanied children)”.  This is to make the risk description more specific. 
 the risk wording for the adverse weather risk has been expanded to “Inability of
the Council to manage the impacts that increasing frequency and intensity of
adverse weather events such as floods, storms, cold and freezing conditions and
extreme heat, water shortages and wildfires has on Council services, budgets
190

Page 191

and our communities,” this amendment is to recognise the effects that the risk
has on the Council and our local communities. 
 “Inability to maintain infrastructure, assets and properties in a well-maintained
condition that will avoid unplanned closure, due to budget constraints and
difficulties achieving the objectives of asset and property reviews” has been
refined to “Inability to maintain infrastructure, assets and properties in a well-
maintained condition and difficulties achieving the objectives of asset and
property reviews” 
6.3. As part of the review of the Risk Management Strategy, risk categories were realigned,
and some scores have been revised.  This has resulted in the following previously high
categorised risks now being categorised as medium level risks, and no longer feature
as part of the Council’s top risks:- 
 the Council does not fully deliver the strategic outcomes required of the IJB as
outlined in their Strategic Commissioning Plan 
 implications of the Scottish Fire and Rescue Service Unwanted Fire Alarm
Signals Policy within the Council's non-domestic estate
 the Council fails to comply with its statutory duties by not conducting sufficiently
robust impact assessments where the same are required, including in respect of
budget/service redesign proposals, leading to potential legal and financial
challenges, which could result in failure to deliver those proposals
 IT development, functionality and implementation of new systems does not
support service delivery to secure efficiencies
 inability of the Council to deliver the objectives of the Community Wealth Building
Strategy 
 inability of the Council to deliver the outcomes of the Economic Strategy
 failure to ensure the health, safety and well-being of employees and the
protection   of service users and members of the public in the delivery of Council
services 
 inability of the Council to achieve the outcomes of the Community Plan 2022-
2032
 inability of the Council to achieve the outcomes of the Council Plan 
6.4. The Council’s top risk register is monitored on an ongoing basis, ensuring that risks
are adequately managed. Updates are reported annually to this Committee.  Risk
scores and rankings may be amended if new information comes to light that allows the
position to be reassessed. 
6.5. Risks scored 20 to 25 are considered to be very high risks and risks scored 10 to 16
are considered to be high risks. The top risks identified for the Council, that is those
that are residually scored as being very high and high, are attached at Appendix 2. 
7. Benchmarking
7.1. An Informal benchmarking exercise has been undertaken to review risks faced by a
sample of other Scottish local authorities. This review established that the current
South Lanarkshire Council top risk register is in the main reflective of the risks faced
by these other authorities. 
8. Horizon Scanning 
8.1. Through wider analysis and discussion with the Council’s Risk Sponsors Group, areas
that could pose potential threats and risks or are emerging issues and opportunities
that could affect the Council were identified.  Areas identified are listed below. 
191

Page 192

 Transformational Change 
The Council has embarked upon a transformational change programme which
includes a series of cross-cutting reviews, with a view to transforming services
and meeting savings targets over the next 3 years. The level of change will
require the Council to take on new levels of risk in managing and delivering
service change. 
Progress with the transformational reviews is being monitored, and as part of
review the top risks for 2026/2027, updates will be sought to assess progress
and consider the need for a standalone risk. 
 The Terrorism (Protection of Premises) Act
The Act, more commonly known as Martyn’s Law, received Royal Assent on 3
April 2025.   
The Security Industry Authority (SIA) has been named as the national regulator,
and it estimates that establishing the new regulatory capability will take at least
24 months during which time they will work with the Home Office to engage and
inform stakeholders as preparation work progresses. 
The Act will require certain public premises and events to be prepared to keep
people safe in the event of an attack. 
Premises within scope of the legislation will include locations used for
entertainment and leisure, retail, food and drink, museums and galleries, sports
grounds (with controlled entry), the public areas of buildings, visitor attractions
and temporary event spaces where entry to a defined space is ticketed (with or
without a fee), as well as places of worship, health, and education settings. 
Existing Council-wide activities related to health and safety, risk management,
property maintenance, resilience and security generally all contribute to creating
safe environments for our staff, service users, visitors, and pupils.  Martyn’s Law
will add a new reference point for these activities.   
The Resilience Adviser, on behalf of the Executive Director Housing and
Technical Resources, will convene a working group comprising representation
from Risk Management, Personnel, Licensing, Property Services, Facilities,
Health and Safety, Education, South Lanarkshire Leisure and Culture (SLLC) ,
the Health and Social Care Partnership (HSCP) and Police Counter Terrorism
Liaison Officers to:- 
 raise awareness of Martyn’s Law within this group.
 identify premises anticipated to fall within the respective tiers.
 identify key issues and make recommendations on changes to policy
and/or procedure for managing the implementation of Martyn’s Law and
ongoing compliance. 
 The Care Reform (Scotland) Bill
The Care Reform (Scotland) Bill was passed on 10 June 2025 and will introduce
changes to social care procurement and a new right to breaks for unpaid carers. 
The legal right to breaks for unpaid carers means that Councils will have a duty
to decide whether a carer is able to take sufficient breaks from their caring role.  If
192

Page 193

they are not, then the local authority will provide support to enable this, such as
providing funding for short respite breaks. 
This policy, given Scotland has around 700,000 unpaid carers, will cost between
£196 million and £315 million by 2035/2036, according to the Bill's financial
memorandum.   
Scotland’s Census 2022 estimated that there are 42,375 carers in South
Lanarkshire, equating to approximately 13% of its population. This is likely to
have significant financial implications for the Council.  A watching brief will be
maintained, as “sufficient” has not yet been defined. 
 Scotland Excel Supply Chain Intelligence Report  
The Scotland Excel Supply Chain Intelligence 2025 report highlights a significant
number of national and global issues that present supply chain challenges.   
The main areas covered in the 2025 Intelligence Report are:- 
 the economic outlook
 inflation and price fluctuations
 interest rates
 global market security
 international trade tariffs
 US-UK Economic Prosperity Deal
 the labour market
 national Insurance Contributions
 changes for international workers in care
 policy and funding
 local government funding landscape
 proposed policy and legislation changes (Housing, Social Care)
 environmental change
 Avian bird flu
 climate change adaptation
 technological Change
 artificial intelligence in supply chains 
This report has been circulated throughout the Council, and Resources are being
encouraged to prepare and, where possible, put plans in place to react to the
challenges that arise. 
8.2. These areas will continue to be monitored to ensure that the Council is adequately
prepared to respond where required. 
9. Three lines model 
9.1.   The ‘three lines’ model was developed by the Institute of Internal Auditors. When using
this model, risk controls are categorised under three lines of defence.  This aims to
provide assurance around the adequacy of control measures that are in place to
mitigate strategic risks, identify control descriptions that need amendment to clearly
link these to the mitigation of the risk and to highlight any residual gaps in controls that
require to be addressed.    
193

Page 194

9.2. Internal Audit work on the three lines model for the top risks has been concluded.
Resources have been provided with individual analysis and guidance to support them
in developing further controls to close any gaps identified from the three lines approach
for the Council top risks that they lead on.  Work is now ongoing to review and refine
risk controls. This is scheduled to be completed by 31 March 2026. 
10. Scope and appetite for risk
10.1. The Council aims to be risk embracing, that is it will accept a tolerable level of risk in
seeking service efficiencies and in agreeing control measures. 
10.2. The level of risk facing the Council is measured both before (inherent risk) and after
(residual risk) consideration of controls.  The Council should never carry a very high
residual risk exposure as this would indicate instability, but a low residual risk exposure
should also be avoided as this indicates lack of innovation. 
10.3. The Council’s universal risk tolerance levels were updated as part of the review of the
risk management strategy last year, with the ideal risk profile now defined as:- 
 no more than 20% of risks at a very high level
 no more than 25% of risks at a high level
 around 40 to 50% of risks at a medium level
 no more than 25% of risks at a low level 
10.4. Table 4 below shows the top risks heat map, i.e. it details the total number of risks for
each individual risk score.  Table 5 below notes the overall risk profile for the top risks. 
Table 4 – Top risks heat map 
Likelihood
5
Almost
certain   
4 
4
Likely   3 4 1
3
Possible   6 4 
2
Unlikely    3 
1
Rare     
1
Negligible
2
Minor
3
Moderate
4
Major
5
Catastrophic  
Impact 
Table 5 – Top risks risk profile
Risk
category
Risk
rating
Number
of risks
Percentage
of risks
1 Very high 5 20%
2 High 11 44%
3 Medium 9 36%
4 Low 0 0%  
25 100% 
194

Page 195

10.5. The main changes to the risk profile, as a result of the realignment of risk categories,
and changes to risk scores noted in Section 6.2, are:- 
 number of very high risks has reduced from 12 to 5
 number of high risks has reduced from 16 to 11
 9 risks are now recorded as being medium-level risks 
10.6. Whilst the profile noted in Table 5 remains out with the ideal universal risk exposure
defined by the Risk Management Strategy, there has been a reduction in the number
of very high and high risks, and as such, it is now closer to the ideal risk exposure
level. This is in part due to the revision to risk bandings and tolerance levels within the
strategy. 
10.7. Whilst this profile is not unusual in the current climate, where possible, further
mitigation is encouraged. These are the highest-level risks currently being faced by
the Council. 
11. Employee Implications
11.1. There are no direct employee implications relative to this report.  There are proposed
risks which are classified under the heading of employee.  Where this is the case, the
appropriate controls and actions have been included in the risk control cards and
progress will be monitored. 
12. Financial Implications
12.1. There are no direct financial implications associated with the Council’s top risks.  There
are a number of proposed risks which are classified under the heading of financial. 
Where this is the case, the appropriate controls and actions have been included in the
risk control cards, and progress will be monitored. 
13. Climate Change, Sustainability and Environmental Implications
13.1. There are no direct implications associated with the Council’s top risks.   
13.2. A specific risk has been included within the Council’s top risk to cover climate change
and environmental implications.  The risk is titled ‘Inability to take the necessary action
due to funding constraints, to combat climate change, and work toward achieving net
zero carbon emissions by 2045, thereby contributing to negative and irreversible
environmental, social and economic impacts on the Council and its residents.’  Control
measures that currently mitigate against this risk have been identified, with a number
of additional actions recorded to further strengthen these controls. 
13.3. There are a number of further risks within the Council’s top risk register which are
categorised under the risk classification ‘Environmental’ and/or are linked to the
Connect Outcome ‘Communities and Environment’.  Appropriate controls and actions
have been identified within the individual risk control cards, and progress will be
monitored. 
14. Other Implications
14.1. Failure to demonstrate that risk is actively considered and managed can not only lead
to avoidable financial loss but could also adversely affect the delivery of services and
could affect the Council’s reputation. The work carried out to identify and review the
Council’s top risks and to determine the risks, controls and actions necessary enables
the Council to manage the impact.   
195

Page 196

15. Integrated Impact Assessment and Consultation Requirements
15.1. This report does not introduce a new policy, function or strategy or recommend a
fundamental change to an existing policy, function or strategy and, therefore, no
impact assessment is required. 
15.2. Consultation has taken place with Heads of Service, Risk Lead Officers, Elected
Members, Trade Unions and Resource Risk Sponsors. 
Jackie Taylor
Executive Director (Finance and Corporate Resources) 
5 September 2025 
Link(s) to Council Values/Priorities/Outcomes
 Accountable, effective, efficient and transparent 
Previous References
 Risk and Audit Scrutiny Committee – 24 September 2024 (Review of Council’s Top
Risks/Year-End Risk Management Report 2023/2024) 
List of Background Papers
 Top Risk Control Cards 
Contact for Further Information
If you would like to inspect the background papers or want further information, please
contact:-
Craig Fergusson, Head of Finance (Transactions)
Ext:  4951 (Tel: 01698 454951)
E-mail:  craig.fergusson@southlanarkshire.gov.uk 
196

Page 197

Appendix 1 – 2024/2025 Compliance with risk management strategic requirements 
Key
Score 3= Up to date and in line with requirement 
Score 2= Work in progress 
Score 1= Needs addressed 
Requirement from Risk Management Strategy
Community
and
Enterprise
Resources
Education
Resources
Finance
and
Corporate
Resources
Housing
and
Technical
Resources
Social
W
ork
Resources
Risk registers are updated on an annual basis, in line with the Council’s Risk
Management Strategy 3 3 3 3 3
Where appropriate, Council top risks are adequately reflected in the Resource
risk register 3 3 3 3 3
Delivery of Resource risk control actions and control actions for top risks lead
by the Resource are progressed. 3 3 3 3 3
The risk register and risk control plan are approved annually by the Resource
Management Team 3 3 3 3 3
The risk register is presented for noting; and assurance of delivery of actions
is given to the Resource Committee on an annual basis. 3 3 3 3 3
Information held on Figtree reflects the latest Resource Risk Register and Risk
Control Plan 3 3 3 3 3
The Council’s agreed risk profile and risk tolerance level is adopted. 3 3 3 3 3
Risk evaluations are undertaken prior to the commencement of major projects,
partnerships and organisational changes 3 3 3 3 3
Formal risk sharing agreements for major partnerships and contracts are in
place 3 3 3 3 3
Major decisions are transparent and clearly show the following key elements:
• Full cost over life of proposal;
• Funding source;
• Savings or efficiencies;
• Other benefits;
• Associated risks and how they will be managed.
3 3 3 3 3
197

Page 198

Elected members are kept informed of risks by using the “Other Implications”
section of the Committee report template.  This section should include:
• The risks involved with the report’s recommendations;
• The potential positive and negative consequences;
• How these risks are currently being managed (existing controls) or how
they will be managed going forward (additional actions);
• Link to risks on the Council’s top risk register.
3 3 3 3 3
Assurance is gained from contractors and sub-contractors, in line with
procurement processes, of their adoption of recommended risk management
practices, particularly that adequate insurance cover, safe health and safety
practices, and equalities, sustainable development, business continuity and
scrutiny procedures are in place.
3 3 3 3 3
Regular Resource Risk Management Group meetings (or alternative where risk
management is a standing agenda item). 3 3 3 3 3
Liaison with Service Planners to ensure that risks associated with Council and
Resource plans are identified and assessed; and that appropriate plans are put
in place to manage these risks. 
3 3 3 3 3
Management of insurance hotspots and required mitigating actions 3 3 3 3 3
Total 45 45 45 45 45
Percentage compliance 100% 100% 100% 100% 100% 
198

Page 199

Appendix 2 - Council top risk register 2025/2026 
Risk
Category 
Key risk  Inherent Risk
Score
Residual
Risk Score
Controls (Good,
adequate, poor)
1 
Very  
High 
(20-25) 
The Budget Gap that the Council faces across the medium
term continues to be the biggest risk faced by the
Council.  The Budget Gap is the result of the cumulative real
terms reductions in Government funding as well as the
ongoing impact of increased demand, increased cost of
services due to inflation, and increased staff costs resulting
from pay awards.  The potential of reduced fees/income being
received by the Council would further add to budget pressures
across Services
25 20 Adequate 
Housing Emergency - inability of the Council to effectively
provide accommodation and support to households who are
homeless and people who arrive in South Lanarkshire as
part of refugee resettlement and the asylum seeker
dispersal programmes (including those for unaccompanied
children)
25 20 Good 
The Council’s operations are affected by fraud, theft,
organised crime and cyber attacks 
25 20 Adequate 
Inability to take the necessary action due to funding
constraints, to combat climate change, and work toward
achieving net zero carbon emissions by 2045, thereby
contributing to negative and irreversible environmental, social
and economic impacts on the Council and its residents
25 20 Good 
The Council, in conjunction with its partners, is unable to
provide the required support to reduce the overall impact of
the cost-of-living crisis on households in South Lanarkshire,
resulting in increasing levels of poverty, debt, and poorer
outcomes for people 
25 20 Adequate
2 
High 
(10-16) 
Due to the fragility and lack of capacity of the third and
private sector market, providers are potentially unable to
sustain their business models, which could result in a
deterioration of their service standards and/or provider
failure.  This could result in the Council seeking alternative
25 16 Good
199

Page 200

Risk
Category 
Key risk  Inherent Risk
Score
Residual
Risk Score
Controls (Good,
adequate, poor)
service provision in a reduced marketplace to allow us to
meet the demand for services.
Information governance not subject to adequate control  20 16 Adequate
The Council fails to comply with or meet the expected
standards of scrutiny and deliver the improvement actions
identified by regulatory bodies
25 16 Adequate
Inability of the Council to manage the impacts that
increasing frequency and intensity of adverse weather
events such as floods, storms, cold and freezing conditions
and extreme heat, water shortages and wildfires has on
Council services, budgets and our communities
20 16 Good
Inability to ensure public protection and safety 25 12 Good
The Council does not have the appropriate resilience
measures, emergency or business continuity plans in place
to respond efficiently as a Category 1 Responder to a civil
emergency
25 12 Adequate
Procurement activity is affected by supply chain issues; a
lack of resources; non-compliance or legal challenge 
25 12 Good
The provision of Council services is disrupted because of
industrial action
20 12 Adequate
Lack of capacity and skills to meet increased service
demands 
20 12 Good
Inability to maintain infrastructure, assets and properties in
a well-maintained condition and difficulties achieving the
objectives of asset and property reviews
20 12 Good 
Historic childhood abuse   16 12 Good 
200

Page 201

Report
Agenda Item 
Report to: Risk and Audit Scrutiny Committee
Date of Meeting: 30 September 2025
Report by: Executive Director (Finance and Corporate Resources)  
Subject: Annual Update on the Use of Surveillance Powers - The
Regulation of Investigatory Powers (Scotland) Act 2000
(RIPSA) 
1. Purpose of Report
1.1. The purpose of the report is to:-
[purpose]
 provide the Committee with an updated version of the Council’s Regulation of
Inventory Powers (Scotland) Act 2000 (RIPSA) Policy and provide an overview
and update on the use of directed surveillance powers by the Council 
2. Recommendation(s)
2.1. The Committee is asked to approve the following recommendation(s):-
[recs]
(1) that the contents of this report be noted;
(2) that the updated Council’s RIPSA Policy, being the Protocol for Direct Covert
Surveillance and the Protocol for using Covert Human Intelligence Source,
included in Appendix 1 and Appendix 2 to this report, be noted; and 
(3) that it be noted that the Council’s use of surveillance powers under RIPSA will
be reported annually to the Committee going forward. 
[1recs
3. Background
3.1. The use of surveillance to provide information is a potentially valuable resource for
the protection of the public and the maintenance of law and order. To ensure that
local authorities and law enforcement agencies are able to discharge their
responsibilities, use is made of unaided surveillance and surveillance devices. 
3.2. Where this surveillance is covert, that is the subject of the surveillance is unaware
that it is taking place, then it must be authorised in accordance with the relevant
regulations to ensure that it is lawful. CCTV systems in the main, will not be subject
to this procedure as they are “overt” forms of surveillance. However, where CCTV is
used as part of a pre-planned operation of covert surveillance, then authorisation
must be obtained. 
3.3. The Regulation of Investigatory Powers (Scotland) Act 2000 (RIPSA) provides a
legal framework for the use, deployment, duration and effectiveness of covert
surveillance and the use of covert human intelligence sources. The Council must
comply with RIPSA and adhere to the authorisation procedures specified in the
Council’s RIPSA Policy and related procedures. The Investigatory Powers
Commissioner's Office (IPCO) provides independent oversight of the use of the
powers contained within RIPSA. This oversight includes inspections by IPCO
inspectors on a regular basis, approximately every 3 years, with the Council’s next
inspection expected in 2026. 
11
201

Page 202

3.4. Under the Council’s authorisation procedures, applications for directed surveillance
are authorised by a restricted number of Authorising Officers, being certain named
senior officers as listed in Section 2.1 of the Protocol for Direct Covert Surveillance.
A central register of authorisations is maintained by the Head of Administration and
Legal Services, who also carries out a gate-keeping role in connection with draft
applications. 
3.5. The Council’s RIPSA Policy is contained in the Protocol for Direct Covert
Surveillance and the Protocol for using Covert Human Intelligence Source, which
must both be read in conjunction (respectively) with the Scottish Government Code
of Practice on Covert surveillance and Property Interference and the Scottish
Government Code of Practice on Covert Human Intelligence Sources. 
4.  Proposals  
Overview of RIPSA
4.1. The Council’s RIPSA Policy and its procedures applies where ‘Directed Surveillance’
is being planned or carried out. Directed Surveillance can only be conducted to
achieve one of more of the permitted RIPSA purposes, namely (i) preventing or
detecting crime or prevention of disorder, (ii) in the interests of public safety or (iii)
protecting public health. Directed surveillance is covert and is undertaken for the
purpose of a specific investigation to obtain private information. 
4.2.  All applications for authorisations or renewals of authorisations must be reviewed by
one of the Council’s Authorising Officers, with an appropriate form having first been
completed by a relevant Council officer. Authorisations should be made in writing but
can be made verbally in cases of emergency. Authorising Officers must be satisfied
that the authorisation is (i) necessary - where there is no reasonable and alternative
way of achieving the objective, and (ii) proportionate - any use of the surveillance
shall not be excessive i.e. it shall be in proportion to the significance of the matter
being investigated. 
4.3.  Key points in relation to the Authorisation Process are outlined below:- 
Time Periods 
Written authorisations expire after 3 months in the case of directed surveillance. Oral
applications expire after 72 hours. 
Review 
Authorisations, if granted for a period of longer than one month, must be reviewed
every month. 
Renewals 
If at any time before an authorisation expires, the Authorising Officer considers it
necessary for the authorisation to continue for the purpose for which it was given,
authorisations can be renewed for a further period, three months in the case of
directed surveillance and 12 months for use of a covert human intelligence source.
Any renewal must take place before the authorisation expires, and the further period
begins on the day on which the previous authorisation ceases to have effect. 
Cancellation 
202

Page 203

The Authorising Officer must cancel an authorisation if satisfied that the directed
surveillance no longer satisfies the criteria for authorisation, the use or conduct of the
source no longer satisfies the criteria for authorisation or procedures for the
management of the source are no longer in place. 
4.4. It is important that elected members receive regular updates on the Council’s use of
its surveillance powers, given their potentially intrusive nature. Such public reporting
is also recommended by IPCO. In the last 5 years, that is from 2020/2021, the
Council has made no use of RIPSA, for either covert directed surveillance or covert
human intelligence sources.  This reflects what is understood to be a general decline
in the use of RIPSA by Scottish local authorities. 
4.5. Going forward, in line with best practice and the expectations of IPCO, the
Committee will receive an annual report on the use of RIPSA, even if there has been
none. An updated version of the Policy will continue to assist with the Council’s
compliance. 
4.6. All operational procedures and forms have been made available to staff on the
Intranet. Refresher training will be provided later in 2025 to Authorising Officers and
relevant staff. 
Council’s RIPSA Policy
4.7. As noted above, the Council’s RIPSA Policy comprises a Protocol for Covert
Directed Surveillance and a Protocol for Using Covert Human Intelligence Source.
These were last reviewed in May 2023 and November 2016. 
4.8. These have been the subject of a fresh review, and some minor updates have been
made to reflect changes in Council structure and align the 2 Protocols, as attached in
Appendix 1 and Appendix 2. Given the minor nature of the changes, these have
been made by officers under delegated authority in terms of the Scheme of
Delegation. 
4.9. Going forward, these Protocols will be the subject of annual review, the outcome of
which will be reported to the Committee, in line with the IPCO’s recommended
practice. 
5. Employee Implications
5.1. None. 
6. Financial Implications
6.1. None. 
7. Climate Change, Sustainability and Environmental Implications
7.1. There are no implications for climate change, sustainability or the environment in
terms of the information contained in this report. 
8. Other Implications
8.1 RIPSA provides a legal framework for authorising covert surveillance by public
authorities and an independent inspection regime to monitor these activities within
the United Kingdom. If RIPSA has been complied with, then any interference with an
individual’s privacy will be in accordance with the law. Failure to act in accordance
with RIPSA could result in a complaint being raised with the Investigatory Powers
Tribunal. There are clear risks to the Council if unlawful surveillance were to be
undertaken, and keeping the RIPSA Policy under regular review, with appropriate
support and training to staff, will mitigate against this.
203

Page 204

9. Integrated Impact Assessment and Consultation Requirements
9.1. Given the minor changes being proposed to the RIPSA Policy, there is no
requirement for an integrated impact assessment or formal consultation in terms of
the information contained in this report. 
Jackie Taylor
Executive Director (Finance and Corporate Resources) 
6 August 2025 
Link(s) to Council Values/Priorities/Outcomes
 Fair, open and sustainable
 Accountable, effective, efficient and transparent 
Previous References
 None 
List of Background Papers
 None 
Contact for Further Information
If you would like to inspect the background papers or want further information, please
contact:-
Iain Strachan, Head of Administration and Legal Services
Ext: 4658 (Tel:  01698 454658)
E-mail: iain.strachan@southlanarkshire.gov.uk 
204

Page 205

PROTOCOL FOR COVERT DIRECTED SURVEILLANCE 
This Protocol sets out the Council’s Protocols in relation to the use of covert
directed surveillance. It is in 3 parts. 
Part 1 – The Protocol’s Purpose and Principles – deals with why a Protocol is required and
what it requires of officers of the council. 
Part 2 – How to obtain an authorisation – details the actual Protocol and forms to be used
by officers when obtaining, renewing and cancelling authorisations. 
Part 3 – How to make a complaint – details how a person may make a complaint either
through the Council’s internal Protocol or externally through the Investigatory
Powers Tribunal. 
11
205

Page 206

Protocol for Covert Directed Surveillance 
Part 1 – The protocol’s purpose and principles 
1.1 Why do we have a Protocol? 
The objective of this Protocol is to ensure that all covert directed surveillance by
Council employees or on behalf of the Council is carried out effectively, while
remaining in accordance with the law. It should be read in conjunction with the Scottish
Government Code of Practice on Covert Surveillance and Property Interference ('the
Code of Practice') and any subsequent Council policy on surveillance. 
In some circumstances, it may be necessary for Council employees, in the course of
their duties, to make or ask others to make observations of a person or person(s) in a
covert manner, i.e. without that person's knowledge. By their nature, actions of this
sort are potentially intrusive (in the ordinary sense of the word) on some one’s privacy
and may give rise to legal challenge as a potential breach of Article 8 of the European
Convention on Human Rights and the Human Rights Act 1998 ('the right to respect for
private and family life'). 
The Regulation of Investigatory Powers (Scotland) Act (2000) [RIP(S)A] and the
Investigatory Powers Act 2016, together with relevant regulations, ('the Acts')
together provide a legal framework for authorising covert surveillance by public
authorities and an independent inspection regime to monitor these activities within the
United Kingdom. Relevant regulations include the Regulation of Investigatory Powers
(Prescription of Offices, etc and Specification of Public Authorities)(Scotland) Order
2010 and the Regulation of Investigatory Powers (Authorisation of Covert Human
Intelligence Sources) (Scotland) Order 2014. 
This Protocol applies in all cases where directed covert surveillance is being planned
or carried out. Overt surveillance such as public CCTV cameras is not intended to be
covered by the legislation as it has little impact on someone’s private life. 
Where the surveillance is being carried out by others separate from but on behalf of
the Council, the officer instructing the surveillance will be responsible for the seeking
of an authorisation from the Council and also for ensuring that so far as possible the
investigators comply with the authorisation. 
1.2 What is “Directed Surveillance, including the use of Online Surveillance?” 
Directed surveillance is defined in the Code of Practice as undertaken "for the
purposes of a specific investigation or operation" and "in such a manner as is likely to
result in the obtaining of private information about a person" (Scottish Government
Code of Practice, Paragraph 2.2). 
Surveillance itself is not defined in detail in the Regulation of Investigatory Powers
Scotland Act (RIPSA), but it includes (so is not restricted to):- 
 the monitoring, observing or listening to people, their movements, their
conversations or their other activities or communications
206

Page 207

 recording of anything monitored, observed or listened to in the course of
surveillance; and
 surveillance by or with the assistance of any apparatus designed or adapted for
use in surveillance 
So, surveillance does not need to involve the use of equipment; however, there should
be a conscious decision to carry out the surveillance, and in which event, the principles
described below should be followed. 
Online Surveillance - The use of the internet and social media sites may be required
to gather information prior to and/or during an operation, which may amount to directed
surveillance. Although it may be argued as to how anything made publicly available
on the internet can be considered private, the view of the Investigatory Powers
Commissioner’s Office (IPCO) is that the repeat viewing of individual “open source”
sites for the purpose of intelligence gathering, and data collation should be given
protection under RIPSA. In particular, this would include social media sites such as
Facebook, Twitter/X and the like. 
Accordingly, whenever the Council intends to use the internet or social media sites as
part of an investigation, the officer concerned must first consider whether the proposed
activity is likely to interfere with a person’s Article 8 rights, including the effect of any
collateral intrusion. Any activity likely to interfere with an individual’s Article 8 rights
should only be used when necessary and proportionate to meet the objectives of a
specific case. Where it is considered that private information is likely to be obtained,
an authorisation (combined or separate) must be sought as set out elsewhere in this
Protocol. Where an investigator may need to communicate covertly online, for
example contacting individuals using social media websites, a Covert Human
Intelligence Source (“CHIS”) authorisation should be considered (see separate
Council Protocol in relation to the use of CHIS. 
1.3 What are the Principles of Surveillance? 
In planning and carrying out covert surveillance, South Lanarkshire Council employees
and investigators on behalf of the council must comply with the following principles. 
a) Lawful purposes - covert surveillance shall only be carried out where necessary
to achieve one or more of the permitted purposes (as defined in the Acts), i.e.
it must be: 
 for the purpose of preventing or detecting crime or the prevention of disorder;
 in the interests of public safety; and
 for the purpose of protecting public health. 
Only if one or more of these purposes are met can there be any consideration of
undertaking the surveillance. It must be stressed that employees carrying out
surveillance shall not cause damage to any property or harass any person. 
b) Necessity – covert surveillance shall only be undertaken where it is necessary
for one of the purposes mentioned in paragraph a) above. The conduct that it
207

Page 208

is aimed to prevent or detect must be identified and clearly described. It must
also be explained why there is no reasonable and effective alternative way of
achieving the desired objective(s). 
c) Effectiveness – planned covert surveillance shall be undertaken only by suitably
trained or experienced employees, or under their direct supervision. 
d) Proportionality – An authorisation should demonstrate how an authorising
officer has reached the conclusion that the activity is proportionate to what it
seeks to achieve including an explanation of the reasons why the method, tactic
or technique proposed is not disproportionate.  An authorisation should make it
clear that the following elements of proportionality have been fully considered:- 
 balancing the size and scope of the operation against the gravity and extent of
the perceived mischief;
 explaining how and why the methods to be adopted will cause the least possible
intrusion on the target and others;
 that the activity is an appropriate use of the legislation and the only reasonable
way, having considered all others, of obtaining the necessary result; and
 providing evidence of other methods considered and why they were not
implemented. 
e) Intrusive surveillance – no activity shall be undertaken that comes within the
definition of 'intrusive surveillance', i.e. if it involves surveillance of anything
taking place on residential premises, either permanent or temporarily used as
such – but not common areas such as closes, or in a private vehicle, whether
from within or outside. 
f) Collateral intrusion – reasonable steps shall be taken to minimise the
acquisition of personal information of others who are not directly involved in
the investigation or operation being carried out. An excessive amount of
collateral intrusion could mean that the surveillance is not proportionate.            
g)        Authorisation – all directed surveillance must be authorised in accordance
with the Protocols described below. 
1.4 What if the Surveillance is of, or could include, employees? 
RIPSA is only to be used by the Council for its “core” functions. Investigations into staff
conduct are unlikely to fall within a core function and accordingly RIPSA should not be
used to carry out surveillance on employees – Investigatory Powers Tribunal (C v The
Police and Secretary of State for the Home Office IPT/03/32/H) 14 November 2006.
However, the Council considers that employees as individuals should have the same
protection as members of the public and any potential surveillance of employees
should receive an equivalent scrutiny and protection to that provided under RIPSA. 
If surveillance of South Lanarkshire Council employees is being planned, the office
intending this should only do so after consulting the Head of Personnel and the Head
208

Page 209

of Administration and Legal Services, in addition to securing the required
authorisations in terms of Council policy, including this protocol. 
Remember that information obtained on Council employees during an investigation of
other people amounts to collateral intrusion and must be taken into account when
considering an application for authorisation. 
Part 2:   How to obtain an authorisation 
2.1 Who can grant an Authorisation? 
RIPSA requires that officers, who have a high degree of responsibility within the
council, may only grant authorisations. Regulations made under RIPSA refer to these
officers as “authorising officers” and set minimum levels of responsibility of these
officers. The levels laid down and their corresponding levels within the council are as
follows   
Regulations  Council
Chief Executive 
(or Executive Director) 
In cases where confidential material may be
disclosed (see later) all applicants for authorisation
must go to the Chief Executive or in his absence, but
only where it would be prejudicial to the investigation
to wait until he/she becomes available, the Executive
Director of the relevant Resource. Only the Chief
Executive or, in his/her absence an Executive
Director, may authorise the use of a Covert
Human Intelligence Source. 
Assistant Head of Service It is the view of the Council that in terms of the
Regulations a “Head of Service” is a level equivalent
to an Executive Director of a Resource.
Consequently an “Assistant Head of Service” is an
officer a level of responsibility directly below that of
an Executive Director (normally referred to within the
Council as a Head of Service). 
Investigation Manager  It is the view that, where possible within the structure
of a Service, the appropriate level for an
Investigation Manager is the officer whose level is
directly above that of the line manager of the
investigators carrying out the surveillance. This is not
always possible in terms of the structure; in that case
the immediate line manager may be the Investigation
Manager. 
209

Page 210

Unlike an Assistant Head of Service, who is an authorising officer by his or her position
within the Council, Investigation Managers will be appointed by the Chief Executive,
acting under powers given to him by the Council. A list of Investigations Managers is
available on written request from the Head of Administration and Legal Services,
Council Offices, Almada Street, Hamilton. 
The current Authorising Officers (as at the date of this Protocol are: 
All Resources – Paul Manning, Chief Executive 
Community and Enterprise Resources
 Fraser Carlin, Head of Planning and Regulatory Services 
Education Resources
 None 
Finance and Corporate Resources
 Jackie Taylor, Executive Director
 Iain Strachan, Head of Administration and Legal Services 
Housing and Technical Resources
 Sharon Egan, Head of Housing Services 
Social Work Resources
 None 
2.2 What if an Authorisation is required urgently? 
On rare occasions, it will be necessary to apply for an authorisation as a matter of
urgency. Urgency would normally arise where the time that would elapse before the
Authorising Officer was available to grant the authorisation would be likely to endanger
life or jeopardise the operation or investigation for which the authorisation was being
given. Urgent cases do not arise when there has been a failure on the part of the officer
seeking the authorisation. Whilst all applications should be made in writing, an
application for an urgent authorisation may be made orally to the designated
Investigations Manager or an Assistant Head of Service. 
Sometimes an authorising officer, who would normally deal with applications, will not
be available. In those circumstances, a written (but not oral) application may be
approved by another officer of a similar grade as the Investigations Manager or above.
Applicants should apply within their own line management structure unless other
arrangements have been laid down by the Council. 
2.3 How About Confidential Information? 
Applications where a significant risk of acquiring confidential material has been
identified shall always require the approval of the Chief Executive or in his/her
absence, the Executive Director of the Resource of which the service forms part.
However, this would only apply where it would prejudice the investigation not to wait
until the Chief Executive becomes available. Confidential information is:-
210

Page 211

 matters subject to legal privilege;
 confidential personal information such as information on mental health and other
counselling if confidential or disclosure is prohibited by law;
 confidential journalistic material i.e. information received by journalists in
confidence;
 communication  between a minister of religion and an individual relating to the
latter’s spiritual welfare; and
 between a Member of Parliament and a constituent relating to constituency matters 
Information obtained as part of the surveillance which discloses someone’s religious
or other beliefs is not in itself confidential information. There should be an element of
recognised confidentiality about the information i.e. information arising from religious
counselling, such as confession etc. 
However, it might not always be clear whether the information which may be obtained
falls within the definition of “Confidential Information”. In any case where there is a
possibility that the information obtained may fall into this category, then the applicant
officer must contact the Head of Legal & Administration Services in order that the
position can be clarified. This must be done before the authorisation being sought. 
All investigations which have been identified as possibly disclosing confidential
information must be specifically highlighted and all information obtained must be
retained until the next inspection by IPCO and brought to the attention of IPCO or
his/her inspector at that inspection, regardless of whether the investigation has been
completed. 
2.4 The role of the RIPSA Monitoring Officer 
All applications must be sent the council’s RIPSA Monitoring Officer in Legal Services
before being passed to the Authorising Officer. The RIPSA Monitoring Officer has
undergone training in relation to disclosure of communication and will check the
application to ensure that there is sufficient information contained in it to enable the
Authorising officer to make an informed decision. The RIPSA Monitoring Officer will
not consider whether the application should be granted, that is the role of the
Authorising Officer. However, if the RIPSA Monitoring Officer considers there to be
insufficient information in the application it will be returned to the application with an
explanation of why it has been rejected. 
Additionally, originals of the application form and any related papers will be retained
by the RIPSA Monitoring Officer in a central register within Legal Services. 
The RIPSA Monitoring Officer is Margaret Mary Wilson, Legal Services Manager (Extn
4501). 
2.5 What are the duties of an Authorising Officer?   
In considering an application for an authorisation, the Authorising Officer must
ensure that the requirements of the law are met. Therefore, he/she must be satisfied
that
211

Page 212

 one of the purposes exists AND
 the surveillance is absolutely necessary AND
 the surveillance is proportionate. 
If the authorising officer is not satisfied that all of these conditions are met, then he/she
is under a duty to refuse the application. Remember that on any challenge, it shall be
the Authorising Officer who will need to justify the granting of the authorisation and not
the applicant officer. 
2.6 What about proportionality? 
Proportionality will be the most likely area for challenge. The Authorising Officer should
not merely consider the investigation but its wider possible effects. So not only must
he/she be satisfied that the need for the surveillance outweighs the individual’s
expectation of privacy, but also should consider whether there is, for instance, any
unnecessary or excessive collateral intrusion and the possibility of disclosure of
confidential information. Please see paragraph 1.3. d for a fuller description of what
are the requirements of proportionality. 
2.7 How long do authorisations last? 
Urgent authorisations have been granted orally or granted by an officer other than the
designated Investigations Manager or an Assistant Head of Service, unless renewed,
will expire after 72 hours. 
Otherwise in terms of the legislation authorisations last for three months from the date
of granting i.e. they expire at 23.59 hrs on the day preceding three months of the date
of granting. This is the case even if a shorter period of surveillance is intended
by the applicant – the expiry date of the authorisation will still be three months
after granting. 
However, authorisations should be reviewed on at least a monthly basis by the
Authorising Officer. 
2.8 What happens at a Review? 
This review must take place monthly or sooner depending on the circumstances of the
investigation. When the authorisation is first granted the Authorising Officer will state
when the review is to take place. At each review the Authorising Officer shall complete
a review form, confirming that the original criteria adopted for granting the
authorisation still meet the approval tests. 
If surveillance has been carried out for a month and has proved unfruitful, then it is
doubtful whether anything will be gained from the surveillance. Under those
circumstances it may be disproportionate to continue the surveillance. Consequently,
such authorisations must be cancelled by the Authorising Officer. 
212

Page 213

The originals of any renewal or cancellation forms should be sent to the central
register within Legal Services to be retained with the original application and
authorisation. 
2.9 Can authorisation be renewed? 
Prior to (but not after) expiry, officers can apply to have the authorisation renewed on
the same terms as before. Once an authorisation has expired it cannot be renewed
and a new application must be made. 
An Authorising Officer can only renew an authorisation if the renewal meets the same
criteria as the original authorisation, i.e. if surveillance has become disproportionate
the renewal must be refused. 
In urgent cases the authorisation can be renewed in a similar way for the granting of
an urgent application, but the renewal will be subject to the same time restrictions.
Urgency would normally arise where the time that would elapse before the authorising
officer was available to grant the renewal would be likely to endanger life or jeopardise
the operation or investigation for which the authorisation was being given. Urgent
cases do not arise when there has been a failure on the part of the officer seeking the
authorisation.  
2.10 Who cancels an authorisation? 
If it becomes obvious that the surveillance has not been fruitful i.e. is disproportionate
or has already met its purpose, then the authorisation must be cancelled by the
Authorising Officer. However, if the original Authorising Officer is no longer available
i.e. left the Council’s employment, the authorisation must be granted by his/ her
replacement or a more senior officer. If the post of the Authorising Officer is not filled,
then the authorisation must be cancelled by an officer of the same rank or above who
has taken over the responsibilities of the original Authorising Officer. If, for some
reason, that person is not available, then the authorisation may be cancelled by any
officer of the Council who could have granted that level of authorisation. 
2.11 What Documents are to be used? 
This Protocol uses the following documents: 
1) Application for authority for Directed Surveillance 
This form should be completed by the applicant in all cases, including those covered
by oral authorisation. It is effective from the time that approval is given and for a period
of three months thereafter unless cancelled earlier. 
This form includes a record of an oral authorisation, which should be completed by the
applicant. It should be used only in cases where the urgency of the situation makes
the submission of a written application impractical. It should be countersigned by the
original authorising officer on the same day if possible. 
213

Page 214

2) Review of a Directed Surveillance Operation 
This must be used by authorising officers when undertaking a review of a current
authorisation. 
3)  Renewal of the Directed Surveillance authority 
This should be completed by the applicant in all cases where surveillance is required
beyond the previously authorised period (including previous renewals). 
4)  Cancellation of a Directed Surveillance Operation 
This should be completed by either the applicant or the authorising officer when the
authorisation ceases to be either necessary or appropriate. 
2.12 Do the documents have to be kept, and if so, how securely? 
Documents created under this Protocol are highly confidential and shall be treated as
such. Services shall make proper arrangements for their copies of each document’s
retention, security and destruction, in accordance with the requirements of the Data
Protection Act 1998 and the relevant Code of Practice. 
Resources should maintain a register of current and past authorisations (including
those which have been refused by an Authorising Officer). Applicant officers shall
ensure that sufficient information is provided to keep this up to date. However, as
mentioned, there is a Central Register for the whole of the Council which is kept by
Legal Services, Finance and Corporate Resources. Original records of authorisation
re-granting, renewing or cancelling authorisations, together with copies of the relevant
forms and any supplementary documentation referred to by the authorising officer
when making his/her decision, should be sent monthly to the Central Register. The
date of any review of any authorisation should also be notified to the Register as part
of that information. 
2.13 What happens if no authorisation is obtained? 
Basically, the Council could be acting illegally as they could be infringing a person’s
rights under the Human Rights Act 1998 and the European Convention on Human
Rights. 
Practical consequences could be:- 
 courts considering whether not obtaining the authorisation means that the evidence
recovered can be used. This is the same for both criminal prosecutions and civil
cases. It could mean that a prosecution could collapse or the Procurator Fiscal
could refuse to take any action on the case. This could cause difficulties and
embarrassment to the Council and personal embarrassment to the officer
concerned. 
214

Page 215

 civil cases such as court actions against anti-social tenants could be equally
compromised and result in the council being unable to meet its aspirations. 
 however, there are other remedies available to aggrieved individuals. There is an
independent scrutiny system, which could lead to the formal investigation of the
Council and possible adverse reports being issued. 
 also there could be a claim for damages against the Council for the breach of the
individual’s human rights. 
It is in order to avoid these possible situations that the officers of the Council are
expected to obtain authorisations for surveillance. 
215

Page 216

Part 3 - What if a person wants to make a complaint? 
Anyone who is unhappy about the way the council has or is carrying out surveillance
may make complaint through either internal or external procedures. The decision as
to which procedure should be used lies with the individual concerned. 
3.1 How to use the internal Procedure 
If the person wishes to complain using the Council’s internal procedures, then the
complaint should be, in the first instance addressed to the Executive Director of the
Resource carrying out or has carried out the surveillance. If this is unknown then the
complaint should be made to the Council’s RIPSA Monitoring Officer (Finance and
Corporate Resources). The complaint should be in writing and give details as to who
is making the complaint. 
All Executive Directors may be contacted at the following address:- 
Council Offices
Almada Street
Hamilton
ML3 OAA 
The Council will then investigate using officers who were not involved in the
surveillance. Where possible the applicant will be advised of the outcome of the
investigation, however this might not be possible i.e. where the Council is unable to
do so without prejudicing their regulatory functions. 
3.2 How to use external Procedure 
If a person wishes to complain directly to an independent body or has used the
Council’s internal procedures and is still dissatisfied, then he/she may complain to the
Investigatory Powers Tribunal. Complaints should be made in writing to; 
The Investigatory Powers Tribunal
PO Box 33220
London
SWIH 9ZQ. 
Notices and explanatory information on how to make a complaint, copies of this
Protocol and any Council Policies, together with copies of the relevant forms, Code of
Practice and the Regulation of Investigatory Powers (Scotland) Act 2000, must be
made available to members of the public upon request. 
Head of Administration and Legal Services
TBC 2025 
If you need this information in another language or format, please contact us to
discuss how we can best meet your needs. Phone 0303 123 1015 or email
equalities@southlanarkshire.gov.uk
216

Page 217

C:\Program Files (x86)\neevia.com\docConverterPro\temp\NVDC\E85CD5C2-FF8C-4F98-A943-E180573C3521\ba3d5c73-d52c-41b0-813e-
4f07983dc5ad.doc 
PROTOCOL FOR USING COVERT HUMAN INTELLIGENCE SOURCE 
This Protocol sets out the Council’s Protocols in relation to the use of covert human
intelligence sources.  It is in 3 parts. 
Part 1 – The Protocol’s Purpose and Principles – deals with why a Protocol is required
and what it requires of officers of the Council. 
Part 2 – How to obtain an authorisation – details the actual Protocol and forms to be used
by officers when obtaining, renewing and cancelling authorisations. 
Part 3 – How to make a complaint – details how a person may make a complaint either
through the Council’s internal Protocol or externally through the Investigatory
Powers Tribunal. 
IF THE USE OF A CHIS IS BEING CONSIDERED IT IS ESSENTIAL THAT YOU
CONSULT THE HEAD OF ADMINISTRATION & LEGAL SERVICES BEFORE
PROCEEDING.
11
217

Page 218

C:\Program Files (x86)\neevia.com\docConverterPro\temp\NVDC\E85CD5C2-FF8C-4F98-A943-E180573C3521\ba3d5c73-d52c-41b0-
813e-4f07983dc5ad.doc
SOUTH LANARKSHIRE COUNCIL 
Protocol for Covert Human Intelligence Sources 
PART 1 – PROTOCOL’S PURPOSE AND PRINCIPLES 
1.1 Why Do We Have Protocol? 
The objective of this Protocol is to ensure that any use of covert human intelligence
sources by Council employees or on behalf of the Council is carried out effectively,
while remaining in accordance with the law.  It should be read in conjunction with the
Scottish Government’s Code of Practice on Covert Human Intelligence Sources ('the
Code of Practice') and any subsequent Council policy on this activity. 
In some circumstances, it may be necessary for Council employees, in the course of
their duties, to “go under cover” (or in extreme cases use informers) in order to
obtain information on a person’s unlawful or inappropriate activities without that
person's knowledge.  By their nature, actions of this sort are potentially intrusive (in
the ordinary sense of the word) on someone’s privacy and may give rise to legal
challenge as a potential breach of Article 8 of the European Convention on Human
Rights and the Human Rights Act 1998 ('the right to respect for private and family
life'). 
The Regulation of Investigatory Powers (Scotland) Act (2000) [RIP(S)A] and the
Investigatory Powers Act 2016, together with relevant regulations ('the Acts'),
provide a legal framework for authorising covert surveillance by public authorities
and an independent inspection regime to monitor these activities within the United
Kingdom. Relevant regulations include the Regulation of Investigatory Powers
(Prescription of Offices, etc and Specification of Public Authorities) (Scotland) Order
2010 and the Regulation of Investigatory Powers (Authorisation of Covert Human
Intelligence Sources) (Scotland) Order 2014. 
This Protocol applies in all cases where the use of a covert human intelligence
source is being planned or carried out. 
Where the surveillance is being carried out by others separate from but on behalf of
the Council, the officer instructing the surveillance will be responsible for the seeking
of an authorisation from the Council and also for ensuring that, so far as possible,
the investigators comply with the authorisation. 
1.2 What is a Covert Human Intelligence Source, including use of the Internet? 
A covert human intelligence source is defined as a person who establishes or
maintains a personal or other relationship with another person for the covert purpose
of facilitating anything that:- 
 covertly uses such a relationship to obtain information or to provide access to
any information to another person; or 
 covertly discloses information obtained by the use of such a relationship or as
a consequence of the existence of such a relationship.
218

Page 219

In terms of the Code of Practice, a relationship is used covertly if, and only if, it is
conducted in a manner calculated to ensure that the person is unaware of its
purpose. Consequently, it is not intended to cover situations where officers of the
Council visit premises and make themselves known as officers of the Council and
why they are there at the start of the contact with the individual concerned. 
Online Surveillance - The use of the internet and social media sites may be
required to gather information prior to and/or during an operation, which may amount
to directed surveillance. Although it may be argued as to how anything made publicly
available on the internet can be considered private, the view of the Investigatory
Powers Commissioner’s Office (IPCO) is that the repeat viewing of individual “open
source” sites for the purpose of intelligence gathering, and data collation should be
given protection under the Regulation of Investigatory Powers Scotland Act (RIPSA).
In particular, this would include social media sites such as Facebook, Twitter/X and
the like. 
Accordingly, whenever the Council intends to use the internet or social media sites
as part of an investigation, the officer concerned must first consider whether the
proposed activity is likely to interfere with a person’s Article 8 rights, including the
effect of any collateral intrusion. Any activity likely to interfere with an individual’s
Article 8 rights should only be used when necessary and proportionate to meet the
objectives of a specific case. Where an investigator may need to communicate
covertly online, particularly where he or she uses a false persona, for example,
contacting individuals using social media websites, a Covert Human Intelligence
Source (“CHIS”) authorisation may be required. 
1.3 What is meant by a “relationship”? 
Similarly, there must be a “relationship” which is established or maintained as part of
an investigation. What constitutes a relationship is not defined, but it is clear that it
should be more than merely making contact with the person, i.e. test purchases.
However, it is unclear as to what would constitute establishing a relationship and
therefore, in cases of uncertainty, an authorisation should be obtained. 
The use of a source in terms of the Code of Practice is any action to induce, ask or
assist a person to engage in the conduct of a source or obtain information by means
of an action of the source. 
1.4 What Are the Principles of Surveillance? 
In planning and using a covert human intelligence source, South Lanarkshire Council
employees and investigators on behalf of the Council shall comply with the following
principles. 
a) Lawful purposes - the use of a covert human intelligence source shall only be
carried out where necessary to achieve one or more of the permitted
purposes (as defined in the Acts), i.e. it must be:- 
 for the purpose of preventing or detecting crime or the prevention of
disorder
 in the interests of public safety
219

Page 220

 for the purpose of protecting public health 
Only if one or more of these purposes are met can there be any consideration of
undertaking the activity. 
b) Necessity – the use of a covert human intelligence source shall only be
undertaken where it is necessary for one of the purposes mentioned in
paragraph a) above. The conduct that it is aimed to prevent or detect must be
identified and clearly described. It must also be explained why there is no
reasonable and effective alternative way of achieving the desired objective(s). 
c) Effectiveness – planned use of a covert human intelligence source shall be
undertaken only by suitably trained or experienced employees, or under their
direct supervision. 
d) Management – there must be suitable management structures in place to
manage the source and to prevent any harm coming to the source (see later) 
e) Proportionality – the use and extent of the use of a covert human intelligence
source shall not be excessive, i.e. it shall be in proportion to the significance
of the matter being investigated, including the possibility of significant
collateral intrusion. An authorisation should demonstrate how an authorising
officer has reached the conclusion that the activity is proportionate to what it
seeks to achieve, including an explanation of the reasons why the method,
tactic or technique proposed is not disproportionate.  An authorisation should
make it clear that the following elements of proportionality have been fully
considered:- 
 balancing the size and scope of the operation against the gravity and
extent of the perceived mischief;
 explaining how and why the methods to be adopted will cause the least
possible intrusion on the target and others;
 that the activity is an appropriate use of the legislation and the only
reasonable way, having considered all others, of obtaining the necessary
result; and
 providing evidence of other methods considered and why they were not
implemented. 
f)  Collateral intrusion – reasonable steps shall be taken to minimise the
acquisition of personal information of others who are not directly involved in
the investigation or operation being carried out. An excessive amount of
collateral intrusion could mean that the use of the source is not proportionate. 
g) Authorisation – all uses of a covert human intelligence source must be
authorised in accordance with the Protocols described below. 
1.5 What if the Surveillance is of, or could include, employees? 
RIPSA is only to be used by the Council for its “core” functions. Investigations into
staff conduct are unlikely to fall within a core function and accordingly RIPSA should
not be used to carry out surveillance on employees – Investigatory Powers Tribunal
(C v The Police and Secretary of State for the Home Office IPT/03/32/H) 14
220

Page 221

November 2006. However, the Council considers that employees as individuals
should have the same protection as members of the public and any potential
surveillance of employees should receive an equivalent scrutiny and protection to
that provided under RIPSA. 
If surveillance of South Lanarkshire Council employees is being planned, the office
intending this should only do so after consulting the Head of Personnel and the Head
of Administration & Legal Services. 
Remember that information obtained on Council employees during an investigation
of other people amounts to a collateral intrusion and must be taken into account
when considering an application for authorisation, in addition to securing the required
authorisations in terms of Council policy, including this protocol. 
221

Page 222

PART 2 - HOW TO OBTAIN AN AUTHORISATION 
2.1 The role of the RIPSA Monitoring Officer 
As at the date of this Protocol (TBC 2025), there have been no applications for the
use of a covert human intelligence source by South Lanarkshire Council. If you are
considering using such a source, it is essential that you first of all contact the Head
of Administration & Legal Services for advice. 
After consulting with and obtaining the approval of the Head of Administration &
Legal Services to the use in principle of a covert human intelligence source, any
application must be sent to the Council’s RIPSA Monitoring Officer in Legal Services
before being passed to the Authorising officer. The Monitoring Officers have
undergone training in relation to disclosure of communication and will check the
application for to ensure that there is sufficient information contained in it to enable
the Authorising officer to make an informed decision. The Monitoring Officer will not
consider whether the application should be granted; that is the role of the Authorising
Officer. However, if the Monitoring Officers consider there to be insufficient
information in the application, it will be returned to the applicant with an explanation
of why it has been rejected. 
Additionally, originals of the application form and any related papers will be retained
by the Monitoring Officers in a central register within Legal Services. 
The RIPSA Monitoring Officer is Margaret Mary Wilson, Legal Services Manager
(Extn 4501). 
2.2 Who can grant an Authorisation? 
RIPSA requires that officers, who have a high degree of responsibility within the
Council, may only grant authorisations.  Regulations and the Code of Practice made
under RIPSA refer to these officers as “authorising officers” and set minimum levels
of responsibility of these officers.  The levels laid down and their corresponding
levels within the Council are as follows 
Regulations  Council 
Chief Executive
(or Executive Director) 
It has been decided that only the Chief Executive or,
in his/her absence, an Executive Director may
authorise the use of a Covert Human Intelligence
Source. 
2.3 What if an Authorisation is required urgently? 
On rare occasions, it will be necessary to apply for an authorisation as a matter of
urgency. Urgency would normally arise where the time that would elapse before the
Authorising officer was available to grant the authorisation would be likely to
endanger life or jeopardise the operation or investigation for which the authorisation
was being given.  Urgent cases do not arise when there has been a failure on the
part of the officer seeking the authorisation.  Whilst all applications should be made
in writing, an application for an urgent authorisation may be made orally to the Chief
Executive or, in his/her absence, an Executive Director.
222

Page 223

2.4 What about obtaining confidential information? 
Applications where a significant risk of acquiring confidential material has been
identified shall always require the approval of the Chief Executive or, in his/her
absence, the Executive Director of the Resource of which the service form’s part.
However, an Executive Director can only consider applications which disclose
confidential information if the Chief Executive is absent and it would prejudice the
investigation to wait until the Chief Executive becomes available. Confidential
information is:- 
 matters subject to legal privilege
 confidential personal information, such as information on mental health and other
counselling, if confidential or disclosure is prohibited by law
 confidential journalistic material, i.e. information received by journalists in
confidence.
 communication between a minister of religion and an individual relating to the
latter’s spiritual welfare; and
 between a Member of Parliament and a constituent relating to constituency
matters. 
Information obtained as part of the surveillance which discloses someone’s religious
or other beliefs is not in itself confidential information.  There should be an element
of recognised confidentiality about the information, i.e. information arising from
religious counselling, such as confession, etc. 
However, it might not always be clear whether the information which may be
obtained falls within the definition of “Confidential Information”.  In any case where
there is a possibility that the information obtained may fall into this category, then the
applicant officer must contact the Head of Administration & Legal Services in order
that the position can be clarified.  This must be done prior to the authorisation being
sought. 
All investigations which have been identified as possibly disclosing confidential
information must be specifically highlighted and all information obtained retained until
the next inspection by and brought to the attention of IPCO or his/her inspector at
that inspection, regardless of whether the official investigation has been completed. 
2.5 What are the duties of an Authorising Officer? 
On receiving an application for an authorisation, the Authorising officer must ensure
that the requirements of the law are met. Therefore, he/she must be satisfied that 
 one of the purposes exists
 the surveillance is absolutely necessary
 the surveillance is proportionate; and
 there are suitable management arrangements in place in relation to the source
(see later). 
If the Authorising officer is not satisfied that all of these conditions are met, then
he/she is under a duty to refuse the application. Remember that on any challenge, it
223

Page 224

shall be the Authorising officer who will need to justify the granting of the
authorisation and not the applicant officer.
2.6 What about Proportionality? 
Proportionality will be the most likely area for challenge. The authorising officer
should not merely consider the investigation but its wider possible effects. So not
only must he/she be satisfied that the need for the use of the source outweighs the
individual’s expectation of privacy, but also should consider whether there is, for
instance, any unnecessary or excessive collateral intrusion, the possibility of
disclosure of confidential information and any possible harm to the source. Please
see paragraph 1.4.e for a fuller description of what are the requirements of
proportionality. 
2.7 Can Young People or Vulnerable individuals be used as Sources? 
Young people (people under the age of 18 years old) or vulnerable individuals can
be used as Covert Human Intelligence Sources. However, this is strongly
discouraged and should only occur where there is no alternative available adult
source, and the seriousness of the investigation warrants the use of a young person
or such a person.  No person under the age of 16 years old is to be used in an
investigation where the subject of surveillance is their parent or has parental
responsibilities (as defined in the Children (Scotland) Act 1995) for the young
person. 
2.8 What management arrangements need to be put in place? 
There needs to be proper oversight and management of the source. Therefore,
every source must have a designated handler and a designated controller. The
Council should take into account of possible risks to the source and carry out a risk
assessment, in case the source’s purpose should become known. 
Where the source is under 18 years of age, the risk assessment must also show:- 
 the nature and magnitude of any risk of physical injury and/or psychological
distress to the source have been identified and evaluated; 
 the authorising officer has considered the risk assessment and is satisfied that
any risks are justified and, if they are, that they have been explained to and
understood by the source; and 
 the authorising officer is aware whether the subject of the surveillance is a
grandparent, parent, brother, sister, uncle or aunt (including by marriage), a
formal guardian or a person who has assumed responsibility for the source’s
welfare and, if it is, has given particular consideration to whether the authorisation
is justified in light of that fact. 
Where the source is under 16 years of age, there must be an officer responsible for
ensuring that there is an appropriate adult present at all meetings with the Council or
any other investigating authority. 
An appropriate adult means:- 
224

Page 225

 the parent or formal guardian of the source 
 any other person who has assumed responsibility for the welfare of the source; or 
 if neither of the above persons is available, any responsible person who is neither
a member of nor employed by the Council or any other authority taking part in the
investigation. 
This requirement ceases when the source becomes 16 years old. 
Proper records must be kept in relation to the use of the source. Descriptions of the
records which should be kept are detailed in RIPSA and in the Code of Practice. 
The records kept must contain particulars on the matters detailed in Appendix 1. 
2.9 How long do authorisations last? 
Urgent authorisations, which have been granted orally unless renewed, will expire
after 72 hours. 
Where the source is under 18 years old, the authorisation will last for 1 month from
the date of granting. 
Otherwise, authorisations last for twelve months from the date of granting, i.e. they
expire at 23.59 hrs on the day preceding twelve months from the date of granting in
terms of the Act. However, all authorisations should be reviewed regularly by the
authorising officer. 
2.10 What happens at a Review? 
This review must take place monthly or sooner, depending on the circumstances of
the investigation. When the authorisation is granted, at that time the authorising
officer will state when the next review is to take place. At each review, the
authorising officer shall complete a review form, confirming that the original criteria
adopted for granting the authorisation still meet the approval tests. 
If surveillance has been carried out and has proved unfruitful, then it is doubtful
whether anything will be gained from the further use of the source. Under those
circumstances, it may be disproportionate to continue to use the source.
Consequently, said authorisation must be cancelled by the authorising officer. 
2.11 Can authorisations be renewed? 
Prior to (but not after) expiry, officers can apply to have the authorisation renewed
on the same terms as before. 
An authorisation can only be renewed if the authorising officer has considered
whether the source has been used during the period of authorisation, and how the
source has been used and the information obtained.  In addition, where the source is
under the age of 18 years old, the authorising officer must obtain an updated risk
assessment in order to be satisfied that risks are still justified.  If he/she is not
satisfied with these matters, then the authorisation should not be renewed. 
225

Page 226

In very urgent cases, the authorisation can be renewed in a similar way for the
granting of an urgent application. For the avoidance of doubt, urgency would
normally arise where the time that would elapse before the authorising officer was
available to grant the authorisation would be likely to endanger life or jeopardise the
operation or investigation for which the authorisation was being given.  Urgent cases
do not arise when there has been a failure on the part of the officer seeking the
authorisation. 
2.12 Who cancels authorisations? 
If it becomes obvious that the use of the source has not been fruitful, i.e. is
disproportionate or has already met its purpose, then the authorisation must be
cancelled by the authorising officer. However, if the original authorising officer is no
longer available, i.e., has left the Council’s employment, the authorisation must be
granted by his/ her replacement or a more senior officer.  If the post of the
authorising officer is not filled, then the authorisation must be cancelled by an officer
of the same rank or above who has taken over the responsibilities of the original
authorising officer. If, for some reason, that person is not available, then the
authorisation may be cancelled by any officer of the Council who could have granted
that level of authorisation. 
2.13 What Documents are to be used? 
This Protocol uses the following documents: 
I. The use of a covert human intelligence source - Written Authorisation 
This form should be completed by the applicant in all cases except those
covered by oral authorisation (below).  It is affective from the time that approval
is given. 
This form includes a record of an oral authorisation, which should be completed
by the applicant.  It should be used only in cases where the urgency of the
situation makes the submission of a written application impractical.  It should be
countersigned by the original authorising officer on the same day if possible. 
II. The use of a covert human intelligence source - Renewal of Authorisation 
This should be completed by the applicant in all cases where surveillance is
required beyond the previously authorised period (including previous renewals). 
III. The use of a covert human intelligence source - Review 
This should be used by the authorising officer when reviewing an authorisation. 
IV. The use of a covert human intelligence source - Cancellation 
This should be completed by either the applicant or the authorising officer when
the authorisation ceases to be either necessary or appropriate. 
Due to the level of scrutiny required for the Council to authorise a covert human
intelligence source, these documents are not available on the intranet, unlike forms
for directed covert surveillance. If any officer is considering the use of a covert
226

Page 227

human intelligence source, they should contact either of the RIPSA Monitoring
Officers in the first instance - Margaret Mary Wilson, Legal Services Manager (Extn
4501). 
2.14 Do the documents have to be kept, and if so, how securely? 
Documents created under this Protocol are highly confidential and shall be treated
as such.  Services shall make proper arrangements for their copies of the
documents’ retention, security and destruction, in accordance with the requirements
of the Data Protection Act 1998 and the relevant Code of Practice, including making
available to IPCO. 
Resources should maintain a register of current and past authorisations (including
those which have been refused by an authorising officer).  Applicant officers shall
ensure that sufficient information is provided to keep this up to date. All original
applications and related papers will be kept in the central register for the whole of the
Council, located within Legal Services, Finance & Corporate Resources.  Records of
authorisations re granting, renewing or cancelling authorisations, together with
copies of the relevant forms and any supplementary documentation referred to by
the authorising officer when making his/her decision, should be sent monthly to the
Central Register.  The date of any review of any authorisation should also be notified
to the Register as part of that information. 
Records must be kept until the next inspection by IPCO to ensure that they are
available for inspection. Material must not be destroyed without the consent of the
authorising officer. 
The following information is required to be kept in the records relating to each
source:- 
 the identity of the source;
 the identity, where known, used by the source;
 any relevant investigating authority other than the authority maintaining the
records;
 the means by which the source is referred to within each relevant investigating
authority;
 any other significant information connected with the security and welfare of the
source;
 any confirmation made by a person granting or renewing an authorisation for the
conduct or use of a source that the information in paragraph (e) has been
considered, and that any identified risks to the security and welfare of the source
have, where appropriate, been properly explained to and understood by the
source;
 the date when, and the circumstances in which, the source was recruited;
 the identities of the persons who, in relation to the source, are discharging or
have discharged the functions mentioned in section 7(6) (a) to (c) of RIPSA or in
any order
made by the Scottish Ministers under section 7(2)(c);
 the periods during which those persons have discharged those responsibilities;
 the tasks given to the source and the demands made of him or her in relation to
their activities as a source;
227

Page 228

 all contacts or communications between the source and a person acting on
behalf of any relevant investigating authority;
 the information obtained by each relevant investigating authority by the conduct
or use of the source; and
 any dissemination by that authority of information obtained in that way; and in the
case of a source who is not an undercover operative, every payment, benefit or
reward and every offer of a payment, benefit or reward that is made or provided
by or on behalf of any relevant investigating authority in respect of the source's
activities for the benefit of that or any other relevant investigating authority.
(The Regulation of Investigatory Powers (Source Records) (Scotland) Regulations
2002) 
2.15 What happens if no authorisation is obtained? 
Basically, the Council could be acting illegally as they could be infringing a person’s
rights under the Human Rights Act 1998 and the European Convention on Human
Rights. 
Practical consequences could be:- 
 courts will need to consider whether not obtaining the authorisation means that
the evidence recovered can be used. This is the same for both criminal
prosecutions and civil cases. It could mean that a prosecution could collapse, or
the Procurator Fiscal could refuse to take any action on the case. This could
cause difficulties and embarrassment to the Council and personal
embarrassment to the officer concerned. 
 civil cases, such as court actions against anti-social tenants, could be equally
compromised and result in the Council being unable to meet its aspirations. 
 However, there are other remedies available to aggrieved individuals. There is an
independent scrutiny system, which could lead to the formal investigation of the
Council and possible adverse reports being issued. 
 Also, there could be a claim for damages against the Council for the breach of
the individual’s human rights. 
It is in order to avoid these possible situations that the officers of the Council are
expected to obtain authorisations for surveillance. 
228

Page 229

PART 3 - WHAT IF A PERSON WANTS TO MAKE A COMPLAINT? 
Anyone who is unhappy about the way the Council has used or is using a covert
human intelligence source may make a complaint through either internal or external
procedures. The decision as to which procedure should be used lies with the
individual concerned. 
3.1 How to use the internal procedure 
If the person wishes to complain using the Council’s internal procedures, then the
complaint should be, in the first instance, addressed to the Executive Director of the
Resource who has used the source. If this is unknown, then the complaint should be
made to the Council’s RIPSA Monitoring Officer (Finance & Corporate Resources).
The complaint should be in writing and give details as to who is making the
complaint. 
All Executive Directors may be contacted at the following address:- 
Council Offices
Almada Street
Hamilton
ML3 OAA 
The Council will then investigate using officers who were not involved in the use of
the source. Where possible, the applicant will be advised of the outcome of the
investigation; however, this might not be possible, i.e. where the Council is unable to
do so without prejudicing the safety of the source. 
3.2 How to use the external procedure 
If a person wishes to complain directly to an independent body or has used the
Council’s internal procedures and is still dissatisfied, then he/she may complain to
the Investigatory Powers Tribunal. Complaints should be made in writing to:- 
The Investigatory Powers Tribunal
PO Box 33220
London
SWIH 9ZQ. 
Notices and explanatory information on how to make a complaint, copies of this
Protocol and any Council Policies, together with copies of the relevant forms, Code
of Practice and the Regulation of Investigatory Powers (Scotland) Act 2000 must be
made available to members of the public upon request. 
Head of Administration & Legal Services
TBC 2025 
229

Page 230

If you need this information in another language or format, please contact us to
discuss how we can best meet your needs. Phone 0303 123 1015 or email
equalities@southlanarkshire.gov.uk   
230

Page 231

Report
Agenda Item 
Report to: Risk and Audit Scrutiny Committee
Date of Meeting: 25 June 2025 
Report by: Executive Director (Finance and Corporate Resources)  
Subject: Forward Programme for Future Meetings 
1. Purpose of Report
1.1. The purpose of the report is to:-
[purpose]
 advise members of the forward programme for the meetings of the Risk and Audit
Scrutiny Committee to 29 September 2026 invite members to suggest topics for
inclusion in the Committee’s forward programme
[1purpose]
2. Recommendation(s)
2.1. The Committee is asked to approve the following recommendation(s):-
[recs]
(1) that the report and the outline forward programme for the meetings of the Risk
and Audit Scrutiny Committee to 29 September 2026, attached as an
Appendix to the report, be noted.
[1recs]
3. Background
3.1. As part of a range of improvement measures introduced as a result of Audit
Scotland’s report on the Audit of Best Value and Community Planning (2009), an
Action Plan was prepared.  One of the actions was to include, as a standard agenda
item, a list of items proposed for consideration at subsequent meetings of this
Committee to provide an opportunity for members to inform future agendas.  The
outline forward programme to 29 September 2026 is attached, for members’
information, as an Appendix to the report.  
4. Employee Implications
4.1. There are no employee implications. 
5. Financial Implications
5.1. There are no financial implications. 
6. Climate Change, Sustainability and Environmental Implications
6.1. There are no Climate Change, Sustainability or Environmental implications in terms
of the information contained within this report. 
7. Other Implications 
7.1. There are no risk implications in terms of the information contained within this report.
12
231

Page 232

8. Integrated Impact Assessment and Consultation Requirements
8.1. The report does not introduce a new policy, function or strategy or recommend a
change to an existing policy, function or strategy and, therefore, no impact
assessment is required. 
8.2. There was no requirement to undertake any consultation in terms of the information
contained in this report. 
Jackie Taylor
Executive Director (Finance and Corporate Resources) 
20 August 2025 
Link(s) to Council Values/Priorities/Outcomes
 Accountable, Effective, Efficient and Transparent 
Previous References
 Executive Committee 8 July 2009 
List of Background Papers
 Audit Scotland Audit of Best Value and Community Planning 
Contact for Further Information
If you would like to inspect the background papers or want further information, please
contact:-
Elizabeth-Anne McGonigle, Administration Adviser
Tel:  0738 5403101
E-mail:-  elizabeth-anne.mcgonigle@southlanarkshire.gov.uk 
232

Page 233

APPENDIX – RASC OUTLINE FORWARD PROGRAMME 
Meeting Date  Item Responsibility
9 December 2025 Internal Audit Activity Report Audit and Compliance
Manager   
Audit Scotland Report: Local
Government in Scotland Overview
2024
Head of Communications
and Strategy   
Performance and Review Scrutiny
Forum Annual Update 
Head of Communications
and Strategy 
Good Governance Update Head of Administration and
Legal Services 
2025/2026 Six Monthly Fraud
Report
Audit and Compliance
Manager   
Global Internal Audit Standards -
Update
Audit and Compliance
Manager   
10 March 2026 Internal Audit Activity Report Audit and Compliance
Manager   
2026/2027 Internal Audit Plan Audit and Compliance
Manager   
Annual Audit Plan External Audit 
26 May 2026 Internal Audit Activity Report Audit and Compliance
Manager 
2025 NFI Exercise Audit and Compliance
Manager 
Audit Scotland – Financial Bulletin
2024/2025
Head of Finance (Strategy) 
Financial Resources Scrutiny
Forum Activity
Head of Finance (Strategy) 
233

Page 234

Meeting Date  Item Responsibility 
23 June 2026
(Special) 
Internal Audit Assurance Report
2025/2026
Audit and Compliance
Manager 
•    
Annual Governance Statement for
2025/2026 and Significant
Governance Areas for Quarter 4
Progress Report
Head of Administration and
Legal Services 
Unaudited Annual Accounts
2025/2026
Head of Finance (Strategy) 
25 August 2026 Internal Audit Activity Report Audit and Compliance
Manager 
Year End Insured Risks Report
2025/2026 
Head of Finance
(Transactions) 
Year End Risk Management Report
2025/2026 and Review of Council’s
Top Risks 2026/2027
Head of Finance
(Transactions) 
Fraud Statistics Annual Report
2025/2026 
Financial Resilience and
Sustainability Report
Audit and Compliance
Manager 
Head of Finance (Strategy) 
29 September 2026
(Special)
External Auditor’s Annual Report to
South Lanarkshire Council
2025/2026
External Audit 
Audited Annual Accounts
2025/2026
Head of Finance (Strategy) 
N.B:- Audit Scotland national studies and reviews will appear as a recurring item but the
frequency and subject matter will vary according to their programme. 
234