Democracy Spraffa

Agenda Document Pack - Planning Committee - 06/10/2026

South Lanarkshire Council · 6 October 2026
Back to Planning Committee — 6 October 2026 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

Council Offices, Almada Street        
Hamilton, ML3 0AA 
Tuesday, 29 September 2026 
Dear Councillor 
Planning Committee 
The Members listed below are requested to attend a meeting of the above Committee to be
held as follows:- 
Date:  Tuesday, 06 October 2026
Time:  10:00
Venue: Hybrid - Council Chamber, Council Offices, Almada Street, Hamilton,
ML3 0AA 
The business to be considered at the meeting is listed overleaf. 
Yours sincerely 
Paul Manning
Chief Executive 
Members
Richard Nelson (Chair), Gerry Convery (Depute Chair), Maureen Devlin (ex officio), Alex Allison,
Ralph Barker, Archie Buchanan, Ross Clark, Margaret Cowie, Colin Dewar, Mary Donnelly, Alistair
Fulton, Celine Handibode, Graeme Horne, Cal Johnston-Dempsey, Ross Lambie, Martin Lennon,
Davie McLachlan, Norman Rae, Mo Razzaq, John Ross, Graham Scott, David Shearer, Helen
Toner, David Watson, Kirsty Williams 
Substitutes
Walter Brogan, Robert Brown, Mathew Buchanan, Poppy Corbett, Allan Falconer, Grant Ferguson,
Gladys Ferguson-Miller, Richard Lockhart, Julia Marrs, Ian McAllan, Kenny McCreary, Bert
Thomson 
1

Page 2

BUSINESS 
1 Declaration of Interests   
2 Minutes of Previous Meeting
Minutes of the meeting of the Planning Committee held on 8 September 2026
submitted for approval as a correct record.  (Copy attached) 
5 - 8 
Item(s) for Decision 
3 Application P/25/1485 for Use of Stables as House (Class 9) and
Associated Works at Land 190 Metres East Southeast of Huntlybank
House, Huntlybank Lane, Ravenstruther, Lanark
Report dated 29 September 2026 by the Executive Director (Community and
Enterprise Resources).  (Copy attached) 
9 - 16 
4 Application P/26/0092 for Erection of 117 Houses, Landscaping, Access,
Drainage and Associated Works at Winston Barracks, Robertson Drive,
Lanark
Report dated 29 September 2026 by the Executive Director (Community and
Enterprise Resources).  (Copy attached) 
17 - 32 
5 Application P/26/0458 for Erection of 207 Houses, Landscaping, Open
Space, Access, Drainage and Associated Works at Winston Barracks,
Robertson Drive, Lanark
Report dated 29 September 2026 by the Executive Director (Community and
Enterprise Resources).  (Copy attached) 
33 - 48 
6 Application P/26/0470 for Erection of 4 Houses, Vehicular Access and
Associated Infrastructure and Landscaping (Planning Permission in
Principle) at Land Northeast of 41 Covanburn Avenue, Hamilton
Report dated 29 September 2026 by the Executive Director (Community and
Enterprise Resources).  (Copy attached) 
49 - 56 
7 Application P/26/0918 for Erection of 2 Houses and Associated Works at
Hawks Close, Cleghorn, Lanark
Report dated 29 September 2026 by the Executive Director (Community and
Enterprise Resources).  (Copy attached) 
57 - 64 
8 Application P/26/0922 for Construction and Operation of Renewable
Energy Development, Comprising up to 21 Wind Turbines with Maximum
Blade Tip Height of 220 Metres with a Combined Generating Capacity
Greater Than 50MW, a Battery Energy Storage System of Approximately
50MW and Associated Infrastructure (Section 36 Consultation) at Ravengill
Energy Park, B797 from Abington A702 to Leadhills
Report dated 29 September 2026 by the Executive Director (Community and
Enterprise Resources).  (Copy attached) 
65 - 74 
Urgent Business 
9 Urgent Business
Any other items of business which the Chair decides are urgent. 
2

Page 3

For further information, please contact:-
Clerk Name: Stuart McLeod
Clerk Telephone: 07385 370 117
Clerk Email: stuart.mcleod@southlanarkshire.gov.uk 
3

Page 4

4

Page 5

PLANNING COMMITTEE 
Minutes of meeting held via Confero and in the Council Chamber, Council Offices, Almada Street,
Hamilton on 8 September 2026 
Chair:
Councillor Richard Nelson 
Councillors Present:
Councillor Alex Allison, Councillor Ralph Barker, Councillor Archie Buchanan, Councillor Ross
Clark, Councillor Gerry Convery (Depute), Councillor Margaret Cowie, Councillor Colin Dewar,
Councillor Gladys Ferguson-Miller (substitute for Councillor Graeme Horne), Councillor Alistair
Fulton, Councillor Celine Handibode, Councillor Cal Johnston-Dempsey, Councillor Davie
McLachlan, Councillor Julia Marrs (substitute for Councillor Mary Donnelly), Councillor Norman Rae,
Councillor Mo Razzaq, Councillor John Ross, Councillor Graham Scott, Councillor David Shearer,
Councillor Helen Toner, Councillor David Watson, Councillor Kirsty Williams 
Councillors' Apologies:
Councillor Maureen Devlin (ex officio), Councillor Mary Donnelly, Councillor Graeme Horne,
Councillor Ross Lambie, Councillor Martin Lennon 
Attending:
Community and Enterprise Resources
F Carlin, Head of Planning and Regulatory Services; B Darroch, Planning Area Manager (East
Team); S Laird, Engineering Manager (Transportation Engineering); D Russell, Planning Area
Manager (West Team)
Finance and Corporate Resources
L Healy and K McLeod, Administration Assistants; S McLeod, Administration Officer 
1 Declaration of Interests 
The following interest was declared:- 
Councillor(s)
Barker 
Item(s)
Application P/26/0396 for Erection of
Single Storey Rear Extension and
Associated Alterations at Carstairs
Junction Hall, 20 St Charles Avenue,
Carstairs Junction
Nature of Interest(s)
Prior involvement in
application 
2 Minutes of Previous Meeting 
The minutes of the meeting of the Planning Committee held on 11 August 2026 were submitted
for approval as a correct record. 
The Committee decided: that the minutes be approved as a correct record.
2
5

Page 6

3 Application P/26/0299 for Erection of 5 Houses, Formation of Access Road and
Associated Landscaping Works and Ancillary Development at Cottage Grove, 83
Meikle Earnock Road, Hamilton 
A report dated 31 August 2026 by the Executive Director (Community and Enterprise
Resources) was submitted on planning application P/26/0299 by C Revie for the erection of 5
houses, formation of access road and associated landscaping works and ancillary development
at Cottage Grove, 83 Meikle Earnock Road, Hamilton. 
At its meeting on 7 July 2015, the Committee had approved a procedure for processing planning
applications which required completion of a Legal Agreement.  If approved, the application
would be subject to a Legal Agreement and/or other appropriate mechanism and the approved
procedure would apply. 
There followed a discussion on the application during which an officer responded to a member’s
questions on an aspect of the report. 
The Committee decided: that planning application P/26/0299 by C Revie for the
erection of 5 houses, formation of access road and
associated landscaping works and ancillary development at
Cottage Grove, 83 Meikle Earnock Road, Hamilton be
granted subject to:- 
 the conditions specified in the Executive Director’s
report
 the conclusion of a Section 75 Agreement and/or
other appropriate agreement between the Council,
site owner(s) and applicant 
[Reference:  Minutes of 13 February 2024 (Paragraph 6) and 7 July 2015 (Paragraph 15)] 
4 Application P/26/0396 for Erection of Single Storey Rear Extension and
Associated Alterations at Carstairs Junction Hall, 20 St Charles Avenue, Carstairs
Junction 
A report dated 31 August 2026 by the Executive Director (Community and Enterprise
Resources) was submitted on planning application P/26/0396 by Soul of the Junction for the
erection of a single storey rear extension and associated alterations at Carstairs Junction Hall,
20 St Charles Avenue, Carstairs Junction. 
There followed a discussion on the application during which an officer undertook to find out if the
development would meet the criteria for developer funding. 
The Committee decided: that planning application P/26/0396 by Soul of the Junction
for the erection of a single storey rear extension and
associated alterations at Carstairs Junction Hall, 20 St
Charles Avenue, Carstairs Junction be granted subject to
the conditions specified in the Executive Director’s report. 
[Reference: Minutes of Housing and Technical Resources Committee of 8 October 2025
(Paragraph 14)] 
Councillor Barker, having declared an interest in this application, withdrew from the meeting during
its consideration
6

Page 7

5 Application P/26/0449 for Residential Development of 36 Flats Across 2 Number 4
Storey Blocks, Access Arrangements, Parking, Landscaping and Associated
Works at South Parish Church, Baird Hill, East Kilbride 
A report dated 31 August 2026 by the Executive Director (Community and Enterprise
Resources) was submitted on planning application P/26/0449 by Wilson Developments (EK)
Limited and East Kilbride Housing Association for a residential development of 36 flats across 2
number 4 storey blocks, access arrangements, parking, landscaping and associated works at
South Parish Church, Baird Hill, East Kilbride. 
The Committee decided: that planning application P/26/0449 by Wilson
Developments (EK) Limited and East Kilbride Housing
Association for a residential development of 36 flats across
2 number 4 storey blocks, access arrangements, parking,
landscaping and associated works at South Parish Church,
Baird Hill, East Kilbride be refused for the reasons detailed
in the Executive Director’s report. 
6 Application P/26/0243 for Installation of 49.9 Megawatt (MW) Battery Storage
Facility and Associated Infrastructure at Land 190 Metres Northwest of 3 Leadhills
Road, Elvanfoot, Biggar 
A report dated 31 August 2026 by the Executive Director (Community and Enterprise
Resources) was submitted on planning application P/26/0243 by Elvanfoot Energy Storage 2
Limited for the installation of a 49.9 MW battery storage facility and associated infrastructure at
land 190 metres northwest of 3 Leadhills Road, Elvanfoot, Biggar. 
Following discussion, during which an officer responded to members’ questions on various
aspects of the report, Councillor Nelson, seconded by Councillor Convery, moved that the
application be granted, subject to the conditions specified in the Executive Director’s report. 
Councillor Barker, seconded by Councillor Clark, moved as an amendment that the application
be deferred to allow:- 
 the applicants to provide the Committee with an explanation as to why they had submitted
3 separate planning applications that referred to the same wider site and were under the
same ownership
 additional opportunity for the applicants to engage with residents within the vicinity of the
application sites 
On a vote being taken using the electronic voting system, 10 members voted for the motion and
12 members voted for the amendment which was declared carried. 
The Committee decided: that planning application P/26/0243 by Elvanfoot Energy
Storage 2 Limited for the installation of a 49.9 MW battery
storage facility and associated infrastructure at land 190
metres northwest of 3 Leadhills Road, Elvanfoot, Biggar be
deferred to a future meeting of the Planning Committee for
the reasons detailed above. 
[Reference:  Minutes of 4 February 2025 (Paragraph 5)]
7

Page 8

7 Application P/26/0324 for Installation of Circa 25 Megawatt (MW) Battery Storage
Facility and Associated Infrastructure at Land 190 Metres Northwest of 3 Leadhills
Road, Elvanfoot, Biggar 
A report dated 31 August 2026 by the Executive Director (Community and Enterprise
Resources) was submitted on planning application P/26/0324 by Elvanfoot Energy Storage 3
Limited for the installation of a circa 25 MW battery storage facility and associated infrastructure
at land 190 metres northwest of 3 Leadhills Road, Elvanfoot, Biggar. 
The Committee decided: that planning application P/26/0324 by Elvanfoot Energy
Storage 3 Limited for the installation of a circa 25 MW
battery storage facility and associated infrastructure at land
190 metres northwest of 3 Leadhills Road, Elvanfoot,
Biggar be deferred to a future meeting of the Planning
Committee to allow:- 
 the applicants to provide the Committee with an
explanation as to why they had submitted 3 separate
planning applications that referred to the same wider
site and were under the same ownership
 additional opportunity for the applicants to engage
with residents within the vicinity of the application
sites 
[Reference:  Minutes of 4 February 2025 (Paragraph 5)] 
8 Urgent Business 
There were no items of urgent business. 
8

Page 9

Report
Agenda Item 
CHECKED
Report to: Planning Committee
Date of Meeting: 6 October 2026
Report by: Executive Director (Community and Enterprise
Resources)  
Reference no:  P/25/1485
Proposal:  Use of stables as dwellinghouse (Class 9) and associated works
Site Address:  Land 190M ESE of Huntlybank House
Huntlybank Lane
Ravenstruther
Lanark
Applicant:  Mrs L Lindsay
Agent:  Calum Smith Architect
Ward:  03 – Clydesdale East
Application Type:  Full Planning Permission
Advert :  Carluke Gazette 21 January 2026
Development Plan
Compliance: 
No 
Departures:  N/A
Recommendation:  Refuse
Legal Agreement:  N/A
Direction to
Scottish Ministers 
N/A 
3
9

Page 10

1. Reason for Report
1.1. The application is required to be determined by the Planning Committee under the
South Lanarkshire Council Scheme of Delegation (2024) as the Head of Planning and
Regulatory Services, in consultation with the Chair of the Planning Committee, has
determined that it raises policy issues meriting consideration by the Planning
Committee. 
2. Site Description
2.1. The application relates to a stable building accessed from Huntlybank Lane, southeast
of Lanark Road, Ravenstruther.  The site is within the rural area. 
2.2. Excluding the access, the irregularly shaped site extends to approximately 0.16
hectares.  It occupies a separate position from the nearby residential properties,
between agricultural fields and alongside a mature tree line.  Despite some
containment provided by the trees, the building is readily visible. 
2.3. The building has a rectangular footprint of approximately 126m2, including a 50m2 rear
lean-to extension.  It comprises timber framing supported by masonry piers and a steel
beam, with exposed oriented strand board wall sheathing and a profiled metal roof. 
Render has been applied to parts of the frontage.  The three principal front openings
are boarded over, with access through an opening at the side.  Internally, the framing
is exposed and the floor comprises compacted hardcore.  Machinery, hay and other
stored items were evident at the site visit. 
3. Description of Proposed Development
3.1. The development comprises the conversion of the stable to a 2-bedroom
dwellinghouse together with associated works.  These works include the infilling and
formation of openings, installation of windows and doors, wet dash render and
replacement profiled metal roofing, and the erection of a 5m2 front porch extension. 
The structural report identifies additional framing, a new concrete floor slab,
replacement wall sheathing and roof covering, and additional structural connections. 
3.2.  Access would be taken from the existing private access, with two parking spaces
formed beside the dwelling.  Private drainage infrastructure, including a septic tank
and soakaway, is shown within the site.  Details of the driveway surfacing, garden
layout, landscaping and boundary treatments have not been provided. 
4. Relevant Planning History
4.1. The stable was erected following the granting of planning consent in July 2017
(CL/17/0226).  The rear lean-to extension does not have planning consent. 
5. Supporting Information 
5.1. A supporting statement, supplementary supporting statement, and structural report
have been submitted which contend that the building could potentially be made
suitable for conversion to a dwelling and meets the development plan policies on rural
housing. 
6. Consultations
6.1. West of Scotland Archaeology Service – requests an archaeological condition is
attached to any grant of planning permission.
Response:  Noted. 
7. Representations
7.1. Following the statutory period of neighbour notification and advertisement, 4
comments in support and no objections have been received. 
10

Page 11

8. Development Plan
8.1. Under Section 25 of the Town and Country Planning (Scotland) Act 1997, all
applications must be determined in accordance with the development plan unless
material considerations indicate otherwise.  The development plan comprises the
South Lanarkshire Local Development Plan 2 and National Planning Framework 4. 
8.2. National Planning Framework 4 
National Planning Framework 4 (NPF4) is Scotland’s national spatial strategy and
supports the planning and delivery of sustainable places, liveable places, and
productive places. 
National Planning Framework 4 Policies
 Policy 1 Tackling the climate and nature crises
 Policy 2 Climate mitigation and adaptation
 Policy 3 Biodiversity
 Policy 9 Brownfield 
 Policy 13 Sustainable transport
 Policy 14 Design, quality and place
 Policy 15 Local living and 20 minute neighbourhoods
 Policy 17 Rural homes
 Policy 22 Flood risk and water management 
8.3. South Lanarkshire Local Development Plan 2 (2021)
For the purposes of determining planning applications the Council will, therefore, also
assess proposals against the policies contained within the adopted South Lanarkshire
Local Development Plan 2 (SLLDP2).  In this regard, the application site and
associated proposals are affected by the following policies contained in the SLLDP2. 
SLLDP2 Volume 1 Policies
 Policy 2 Climate Change
 Policy 4 Green Belt and Rural Area
 Policy 5 Development Management and Placemaking 
SLLDP2 Volume 2 Policies
 Policy SDCC3 Sustainable Drainage Systems
 Policy SDCC7 Low Carbon Emissions from New Buildings
 Policy GBRA1 Rural Design and Development
 Policy GBRA4 Conversion and Re-use of Existing Buildings
 Policy DM15 Water Supply
 Policy DM16 Foul Drainage/Sewerage Provision 
9. Guidance
9.1. None applicable. 
10. Assessment and Discussion
10.1. Principle of Development
Policy 4 of SLLDP2 seeks to protect the amenity of the countryside while supporting
appropriately located, small-scale development of high environmental quality.  Policy
17(a) of NPF4 supports rural housing where it meets one of the specified
circumstances and is suitably scaled, sited and designed.  The proposal involves the
reuse of an existing building and therefore falls principally to be assessed against
Policy 17(a)(iii) of NPF4 and Policy GBRA4 of SLLDP2.  
11

Page 12

10.2. Policy 17(a)(iii) supports the reuse of a redundant or unused building.  The
supplementary statement advises that the stables are no longer required for their
original private equestrian purpose.  However, the current owner having no further
requirement for the building, does not in itself, establish redundancy.  The
consideration is whether there remains a reasonable prospect of continued use for
that purpose, rather than whether the building meets the owner’s present
requirements. 
10.3. No substantive evidence has been provided to demonstrate that continued equestrian
use is impracticable or that there is no demand for the building.  This could include
evidence of unsuccessful marketing for sale or letting as stables.  The Planning
Authority regularly receives applications for stable buildings, indicating continuing
interest in this form of development.  Although this does not establish demand for this
particular building, it reinforces the need for a site-specific justification. 
10.4. During the site visit, machinery, hay and other items were being stored within the
building.  While they do not establish that horses are currently kept on the site, they
demonstrate that the building is not wholly unused.  The applicant’s statement,
considered alongside the available evidence, does not adequately demonstrate that
the building is redundant or unused for the purposes of Policy 17(a)(iii). 
10.5. Suitability for Conversion
Policy GBRA4 requires buildings to have local, visual or historical merit and be suitable
for conversion.  Their structure, form, setting and architectural integrity should be
respected, with alterations and extensions sympathetic to the original proportions and
character.  The stables are a modern utilitarian structure, and no particular local, visual
or historical merit has been demonstrated.  Their rural use does not, in itself, establish
the traditional or local vernacular qualities sought by the policy. 
10.6. The McLeish structural report which has been submitted is based on a visual
inspection without numerical assessment.  It identifies that the building appears
capable of supporting vertical loads but has inadequate lateral stability.  Concrete strip
foundations are assumed rather than verified, the timber wall panels do not appear
sufficiently tied to the foundations, and there is no concrete floor slab. 
10.7. Recommended works include additional steel frames, a reinforced concrete floor slab,
replacement sheathing to all timber wall panels, replacement roof covering with
structural sarking, and additional restraint and holding-down connections.  These
works remain subject to detailed structural analysis and design.  The report concludes
that the building has the potential to meet building standards without replacement or
holistic structural changes, but the adequacy of the assumed foundations and the final
extent of the necessary works remain unresolved. 
10.8. It is accepted that conversion to residential use would normally require insulation,
weatherproofing and other upgrading.  However, the identified works extend to
substantial intervention in the building’s structural stability and fabric.  Whether the
existing building is suitable for conversion is a planning consideration under Policy
GBRA4 and cannot be deferred entirely to the building warrant process.  On the
evidence assessed, this has not been adequately demonstrated.  
12

Page 13

10.9. Layout, Siting and Design 
Policy 14 of NPF4 and Policies 5 and GBRA1 of SLLDP2 require development to
respond positively to its surroundings.  Policy GBRA1 supports traditional or
contemporary design which interprets and adapts traditional principles, while avoiding
suburban-style development in the countryside.  Policy 17(a) also requires rural homes
to be suitably scaled, sited and designed. 
10.10. The supporting statements describe the development as contained within the
established Huntlybank group.  However, the building occupies a separate position
within an open field setting, with a stronger relationship to the surrounding countryside
than to a cohesive residential group.  Its visibility across surrounding land requires a
design appropriate to this rural setting.  Retaining an existing footprint does not, by
itself, establish that a dwelling would be acceptable. 
10.11. The proposed dwelling would retain the deep plan and extended roof profile created
by the rear lean-to.  Together with the inconsistent proportions and arrangement of
domestic openings, this would produce an unbalanced composition which neither
retains a traditional rural character nor provides a coherent contemporary
interpretation of it. 
10.12. The amended drawings introduce a gabled entrance porch.  Its broad frontage and
shallow projection create an awkward relationship with the main elevation, while its
roof occupies a substantial part of the principal roof slope.  The porch does not resolve
the wider shortcomings in the building’s form and proportions.  Although wet dash
render and profiled metal roofing can be appropriate rural materials, their use does not
overcome these concerns.  The resulting dwelling would have a suburban appearance
which would detract from its visually exposed rural setting. 
10.13. Two parking spaces are indicated, but details of surfacing, landscaping and boundary
treatments are limited.  These would require further consideration if the principle and
design were acceptable, although they would not resolve the fundamental concerns
identified.  Given the separation from neighbouring dwellings and the single-storey
form, unacceptable overlooking or overshadowing is not anticipated. 
10.14. Sustainability 
The applicant identifies benefits from reusing an existing building and reducing new
construction.  These are relevant to Policies 1, 2 and 9 of NPF4 and Policy 2 of
SLLDP2.  However, their extent depends on the fabric retained and must be
considered against the substantial works identified.  Policy 9 supports reuse taking
account of suitability for conversion and does not remove the need to satisfy the
specific rural housing and design requirements. 
10.15. Policy 3 of NPF4 requires proportionate biodiversity enhancements.  No clear
enhancement scheme has been identified, although appropriate measures could be
secured if the development were otherwise acceptable. 
10.16. Policies 13 and 15 of NPF4 promote sustainable transport and local living, with Policy
17(b) requiring consideration of transport needs appropriate to the rural location.  The
applicant contends that residential traffic would be comparable to that associated with
the authorised equestrian use.  The existing access and potential equestrian traffic are
relevant, but do not establish the acceptability of residential development in principle.  
13

Page 14

10.17. Technical Matters
Policy 22 of NPF4 and Policies DM15, DM16 and SDCC3 of SLLDP2 relate to water
management and drainage.  The site is not identified as being at flood risk, and private
foul and surface water drainage would include a septic tank and soakaway.  Full details
could be secured if the development were otherwise acceptable including permeable
surfacing to limit run-off. 
10.18. Policy 5 of SLLDP2 requires development to provide suitable access and parking.  The
existing private access would be used and there is space for parking and
manoeuvring.  Full details could be secured if the development were otherwise
acceptable. 
10.19. Conclusion 
The proposal has not been justified as the reuse of a redundant or unused building,
and its suitability for conversion has not been adequately demonstrated.  The building
does not possess the qualities sought by Policy GBRA4, while the proposed dwelling’s
form and design would detract from the character and amenity of its rural setting.  The
additional supporting information and design amendments do not overcome these
concerns.  The proposal is therefore contrary to Policies 4, GBRA 1 and GBRA4 of the
South Lanarkshire Local Development Plan 2 and Policies 14 and 17 of National
Planning Framework 4. 
11. Recommendation and Reasons
11.1. The Committee is asked to agree the following recommendation:- 
Refuse Planning Permission for the following reasons:- 
01. The proposal would be contrary to Policy 4 – Green Belts and Rural Areas of the South
Lanarkshire Local Development Plan 2 as it is not supported by the Development Plan
in land use terms. 
02. The proposal is contrary to Policy GBRA1 – Rural Design and Development of the
South Lanarkshire Local Development Plan 2 as it would introduce suburban-style
development into the rural environment. 
03. The proposal is contrary to Policy GBRA4 – Conversion and Re-use of Existing
Buildings of the South Lanarkshire Local Development Plan 2 as the building has not
been demonstrated to be of local, visual or historical merit or suitable for conversion. 
04. The proposal would be contrary to Policy 17 – Rural homes of National Planning
Framework 4 as it has not been demonstrated that it would reuse a redundant or
unused building or be suitably designed to be in keeping with the character of the area. 
Kevin Karr
Executive Director (Community and Enterprise Resources) 
Date: 29 September 2026 
Background Papers
Further information relating to the application can be found online:- 
P/25/1485 | Use of stables as dwellinghouse (Class 9) and associated works | Land 190M
ESE Of Huntlybank House Huntlybank Lane Ravenstruther Lanark  
14

Page 15

Corporate Considerations
The report raises no impacts or risks in terms of equalities or financial implications.  Any
implications in terms of climate change, sustainability or the environment will have been
considered above in terms of the relevant national and local policies. 
Contact for Further Information
If you would like to inspect the background papers or want further information, please
contact:-
E-mail:  planning@southlanarkshire.gov.uk   
15

Page 16

16

Page 17

Report
Agenda Item 
Report to: Planning Committee
Date of Meeting: 6 October 2026
Report by: Executive Director (Community and Enterprise
Resources)  
Reference no:  P/26/0092
Proposal:  Erection of 117 dwellings, landscaping, access, drainage and
associated works
Site Address:  Winston Barracks, Robertson Drive, Lanark
Applicant:  Abbey Developments (Lanark) Ltd
Agent:  Ogilvie Homes
Ward:  02 Clydesdale North
Application Type:  Detailed Planning Permission
Advert Type:  Lanark Gazette 25 February 2026
Development Plan
Compliance: 
No 
Departures:  Yes
Recommendation:  Grant subject to conditions and legal agreement
Legal Agreement:  Yes – to secure financial contributions towards education and
affordable housing provision
Direction to
Scottish Ministers 
N/A 
4
17

Page 18

1. Reason for Report
1.1. This application is being presented to Committee as it constitutes a major planning
application under The Town and Country Planning (Hierarchy of Developments)
(Scotland) Regulations 2009, and the Scheme of Delegation requires that all major
applications are determined by the Planning Committee. 
2. Site Description
2.1. The application site (5.54 ha) lies to the east of Lanark – it is vacant land within the
confines of the former Winston Barracks.  Previously, it contained an assortment of
buildings, associated with the military function of the Barracks, since their demolition
the area has the now largely reverted to scrub.  There are individual and groups of
matures trees located within the site, intermittently along the eastern boundary and at
the southern end.  Topographically the site is relatively level other than the southern
corner where it drops steeply towards the A70/A73 junction. 
2.2. The site is bounded to the north by the roundabout onto the A73.  To the west is the
Sandhurst Building and Sergeants Mess (B-Listed Buildings), associated amenity
space and vacant land subject of a separate planning application (Ref. P/26/0458) for
207 dwellings, submitted by Miller Homes.  To the south is the existing entrance into
Winston Bararcks, the roundabout access onto the A73 and the A73/A70 junction. 
3. Description of Proposed Development
3.1. The applicant seeks planning permission for a residential development consisting of
117 dwellings.  The house types are a mixture of 2 storey detached, semi-detached
and terraced dwellings (5 five bedroom, 57 four bedroom, 42 three bedroom and 13
two bedroom).  The house designs are contemporary and external finishes include
red/charcoal facing bricks, white render and red/charcoal tiles. 
3.2. Access will be taken from Robertson Drive via a roundabout access onto Hyndford
Road, (A73) and a new priority access onto A70 in the northeast corner of the site.  A
network of interconnected, secondary roads will branch out from Robertson Drive,
serving residential clusters.  Surface water will be treated by soakaways in the rear
gardens of each plot, and this will be supplemented by soakaway basins located in
amenity open space areas.  Extensive landscaping and amenity space will be laid out
throughout the development.  A centrally located village green will create a focal point. 
3.3. As the proposal relates to a residential development which falls within the definition of
‘major’ development, as set out in the Town and Country Planning (Hierarchy of
Developments) (Scotland) Regulations 2009, the applicants undertook a pre-
application consultation prior to the submission of this planning application.   
4. Relevant Planning History
4.1. The following is a list of previous Planning Decisions affecting the application site:- 
 Listed Building Consent (Ref. P/25/0008) for the demolition of the former Officers
Mess (C-Listed), granted August 2025
 A Proposal of Application Notice (Ref. P/24/0019/PAN) for residential
development was issued in December 2024 with further consultations required
 Planning Permission (Ref. CL/10/0362) for 44 dwellings, granted November 2010
 Planning Permission (Ref. CL/08/0057) for alteration to site layout and
substitution of house types (amendment to CL/06/0345) granted May 2008
 Planning Permission (Ref. CL/06/0345) for 347 dwellings and conversion of 4
Listed Buildings to form 45 residential units, was granted September 2007
 Listed Building Consent (Ref. CL/05/0486) for the conversion of 4 Listed
Buildings, granted December 2006 
18

Page 19

 Planning Permission (Ref. CL/00/0320) for residential development (Outline)
granted March 2006  
5. Supporting Information 
5.1. In support of the planning application, the applicant has submitted:- 
⧫ Preliminary Ecological Appraisal
⧫ Report on Public Consultation
⧫ Report on Site Investigations
⧫ Design and Access Statement
⧫ Transport Assessment
⧫ Arboricultural Impact Assessment
⧫ Report on Road Traffic Sound
⧫ Drainage Assessment
⧫ Strategic Biodiversity Management Plan 
6. Consultations
6.1. West of Scotland Archaeological Service – There is no known significant
archaeological potential and no investigations are required.
Response: Noted. 
6.2. Scottish Power Energy Network (SPEN) – No objection, however, there is a substation
with underground cables in the vicinity of the site and SPEN therefore reserve the right
to protect and/or deviate apparatus at the applicant’s expense. 
Response: Noted. 
6.3. Developer Obligations - Contributions are required for Education in relation to primary
and nursery provision.  The preference is for the affordable housing contribution to be
provided in the form of a commuted sum for off-site provision. 
Response: If Committee is minded to grant consent, these contributions will be dealt
with through a legal agreement. 
6.4. Environmental Services – No objection, subject to conditions requiring a piling method
statement, noise mitigation, contaminated land remediation and dust control. 
Response: Noted. Should planning permission be approved appropriate conditions
would be attached to any decision issued. 
6.5. Roads, Transportation and Fleet Services – No objection subject to conditions.
Response: Noted. 
6.6. Roads Flood Risk Management – No response received to date.
Response:  The site is not identified as falling within a flood risk area.  A Drainage
Assessment and plans showing the proposed drainage system, including SUDS
basins have been submitted.  If consent is granted a condition will be attached
requiring the completion of self-certification and independent check certificates
appendices for drainage as listed in the Council's Developer Design Guidance (May
2020). 
6.7. Scottish Gas Networks High Pressure Pipeline – Do not have any high pressure assets
within the vicinity of the above consultation and, as such, would have no
comment/objection.
Response: Noted.  
19

Page 20

6.8. Scottish Water – No objection.  There is sufficient capacity in the Camps Water
Treatment Works for a foul only connection to the Lanark Wastewater Treatment
works.  The development may impact upon infrastructure in the proximity of the
development and Scottish Water should be contacted by the developer directly. 
Response: Noted. Surface water will be directed to soakaway basins and will not
connect into the sewage network. 
6.9. The Royal Burgh of Lanark Community Council – No objection subject to the
development including appropriate drainage measures and not having a detrimental
impact on associated services and facilities in the surrounding area.  The development
should also include appropriate street lighting, play areas and footpath links. 
Response:  Noted.  The development will include appropriate street lighting, play area
and footpath links.  In addition, affordable housing will be addressed through on-site
provision and a financial contribution will be sought to address any educational
impacts of the development. 
7. Representations
7.1. Following the statutory period of neighbour notification and advertisement in the local
press, 1 objection and 1 letter of support have been received.  The issues raised are
summarised as follows:- 
 the development would be wholly inappropriate in an already built-up area
 in a climate emergency there is a need to protect any natural spaces in the area
 land is going to waste so would be good for the area
 a park and football pitch should be provided as there is nothing for children to do
in the area unless travelling by car 
7.2. The above issues are considered in the assessment below.  These letters are
available to view on the planning portal.  
8. Development Plan
8.1. Under Section 25 of the Town and Country Planning (Scotland) Act 1997, all
applications must be determined in accordance with the Development Plan, unless
material considerations indicate otherwise. 
8.2. National Planning Framework 4 
National Planning Framework 4 (NPF4) is Scotland’s national spatial strategy for
Scotland.  It sets out spatial principles, regional priorities, national developments and
national planning policy.  NPF4 supports the planning and delivery of sustainable
places, liveable places and productive places. 
National Planning Framework 4 Policies 
 Policy 1 - Tackling the climate and nature crises 
 Policy 2 - Climate mitigation and adaptation 
 Policy 3 – Biodiversity
 Policy 7 - Historic assets and places
 Policy 9 - Brownfield, vacant and derelict land and empty buildings
 Policy 13 - Sustainable transport
 Policy 14 - Design, quality and place
 Policy 15 - Local living and 20 minute neighbourhoods
 Policy 16 - Quality homes
 Policy 17 - Rural homes
 Policy 21 - Play, recreation and sport  
20

Page 21

8.3. South Lanarkshire Local Development Plan 2 (2021)
For the purposes of determining planning applications the Council will assess
proposals against the policies contained within the adopted South Lanarkshire Local
Development Plan 2 (SLLDP2).  In this regard the application site and associated
proposals are affected by the following policies contained in the SLLDP2:- 
SLLDP2 Volume 1 Policies
 Policy 2 - Climate Change
 Policy 3 - General Urban Areas and Settlements
 Policy 5 - Development Management and Placemaking
 Policy 7 - Community Infrastructure Assessment
 Policy 11 - Housing
 Policy 12 - Affordable Housing
 Policy 14 - Natural and Historic Environment
 Policy 15 - Travel and Transport 
SLLDP2 Volume 2 Policies
 Policy GBRA1 - Rural Design and Development
 Policy GBRA5 - Redevelopment of Previously Developed Land Containing
Buildings
 Policy NHE3 - Listed Buildings 
9. Guidance
9.1. None applicable 
10. Assessment and Discussion
10.1. The determining issues in the consideration of this application are its compliance with
the National Planning Framework 4 (NPF4) and adopted South Lanarkshire Local
Development Plan 2 (SLLDP2). 
10.2. Climate Change 
Policies 1 and 2 of NPF4 and Policy 2 of the SLLDP2 relate to the climate crises and
identify that all development should seek to minimise and mitigate the effects of
climate change. 
10.3. The site is not identified on SEPA flooding maps as being at risk of flooding.  Proposed
SUDS will effectively manage surface water runoff, benefitting neighbouring properties
and the drainage network.  If approved, conditions will be attached requiring the
implementation of a landscaping scheme which includes tree planting and wildflower
meadow creation.  The proposal involves development of vacant brownfield land which
is served by good public transport links.  Overall, the proposal would not compromise
the objectives of NPF4 Policies 1 and 2 and SLLDP2 Policy 2. 
10.4. Principle of Development 
NPF4 Policy 17 Rural homes advises that development proposals for new homes in
rural areas will be supported where the development is suitably scaled, sited and
designed to be in keeping with the character of the area and the development can
meet one of the following criteria: the site is allocated for housing in the Local
Development Plan; reuses a redundant or unused building; supports a viable rural
business; is for a retired farmer; reuses brownfield land where a return to a natural
state has not or will not happen without intervention; or, is for a one to one replacement
of an existing house.  
21

Page 22

10.5. The application site could be defined as brownfield land because of its previous use
as a barracks.  It contained numerous military style buildings including housing for
soldiers.  Although there is evidence of hardstanding throughout the site it has largely
reverted to scrub comprising young trees, wildflowers and gorse.  Therefore,
considering these circumstances the proposal does not meet criteria NPF4 Policy 17
a) ii where a return to a natural state would not be possible without intervention. 
10.6. However, the site is subject of Planning Permission CL/06/0345 for 347 dwellings and
conversion of 4 Listed Buildings.  This consent was implemented with two of the Listed
Buildings (Sandhurst Building and Sergeants Mess) having been converted and 32
townhouses built, thereby ensuring Planning Permission CL/06/0345 remains extant. 
The remaining approved dwellings, within the current application site area and the
adjoining residential site, being progressed by Miller homes, could in effect still be
built.  The change proposed by the current application principally relates to a change
in house types.  It is therefore considered that this application can be supported as a
departure from the development plan in recognition of the development history of the
site. 
10.7. Policy 4 ‘Green Belt and Rural Area’ of the adopted South Lanarkshire Local
Development Plan 2 specifies that within the Rural Area the aim is to protect the
amenity of the countryside while at the same time, supporting small scale development
in the right places that is appropriate in land use terms and is of a high environmental
quality that will support the needs of communities.  Generally, it is expected that
houses will be accommodated within identified settlements other than circumstances
including redevelopment of previously developed land containing buildings. 
10.8. SLLDP2 Policy GBRA5 ‘Redevelopment of Previously Developed Land Containing
Buildings’ outlines several criteria relevant to redevelopment proposals.  Although
consented prior to the adoption of SLLDP2, the appropriateness of a brownfield
development, (which did contain buildings, since demolished) in this rural location has
been established by the previous consent CL/06/0345 which remains extant.  As the
proposal under consideration will not have an adverse impact on the wider area in
terms of landscape character and setting, it is reasonable to conclude that it complies
with SLLDP2 Policies 4 and GBRA5. 
10.9. NPF4 Policy 16 – Quality homes seek to encourage, promote and facilitate the delivery
of high quality homes, in the right locations.  It advises that development proposals for
new homes on land not allocated for housing in the local development plan will only
be supported in limited circumstances, where there is an agreed timescale for build-
out, where they are consistent with the spatial strategy and local living and in rural
locations, must be consistent with the policy on rural homes. 
10.10. In this case, the proposal contravenes policy criteria above for rural homes.  However,
the proposal represents a housing opportunity, served by a public bus route and within
reasonable walking and cycling distance of Lanark.  The layout will be enhanced by
extensive amenity open space, tree planting and structured landscaping.  The
landscaping scheme will contribute to biodiversity.  The applicant, a national house
builder, has carried out extensive market research and on those findings is confident
of significant demand for new housing in the locality.  The site was previously identified
as a housing supply site and the current proposal would include 30 affordable units. 
Redeveloping unattractive vacant land with a sensitively designed residential
development will result in environmental and amenity improvements.  The applicant
has provided a Statement of Community Benefit.  For these reasons and the reasons
elaborated in paragraph 10.5 above, a departure from policy can be justified. 
22

Page 23

10.11. In NPF4 Policy 9 Brownfield, vacant and derelict land and empty buildings the relevant
sections state: ‘Development proposals that will result in the sustainable reuse of
brownfield land including vacant and derelict land and buildings, whether permanent
or temporary, will be supported.  In determining whether the reuse is sustainable, the
biodiversity value of brownfield land which has naturalised should be taken into
account’ and ‘Where land is known or suspected to be unstable or contaminated,
development proposals will demonstrate that the land is, or can be made, safe and
suitable for the proposed new use’. 
10.12. Although the site has started to regenerate, the scrub habitat is considered to have
low biodiversity value.  Proposed biodiversity enhancements will ensure the housing
development can be integrated into its setting without detriment to overall biodiversity
value.  The proposed development will result in the sustainable reuse of brownfield
land which formerly operated as a military barracks.  A comprehensive Ground
Investigation Report has been submitted containing survey results, assessments, and
recommendations for remediation.  As a precaution Environmental Services in their
consultation response recommended conditions requiring the submission and
implementation of a remediation strategy.  In consideration the proposal complies with
NPF4 Policy 9. 
10.13. SLLDP2 Policy 11 - Housing supports development included in the housing land
supply audit and identified in the Local Plan proposal map.  If, during the period of the
plan, a shortfall in the five year supply of effective land is identified, the Council will
support development proposals which are effective and capable of meeting the
identified shortfall.  This includes non-effective sites that can now be demonstrated to
be effective and additional brownfield sites. 
10.14. Although identified as a windfall site in the recent South Lanarkshire Housing Land
Audit (CL5035 Winston Barracks) the application site is not identified in the Local Plan
proposal map.  Under previous Local Plans it had been identified as allocated housing
land.  For many years only a small proportion of the approved dwellings subject of
Planning Permission CL/06/0345 for 347 dwellings had been completed, leaving the
impression that most of the site was non-effective.  The recent submission of planning
applications for the remaining site area by Miller Homes and Ogilvie now demonstrates
an intention to progress a residential development.  In helping to meet latent demand
for housing the terms of SLLDP2 Policy 11 have not been compromised. 
10.15. Layout, Siting and Design 
NPF4 Policy 14 Design Quality and Place, SLLDP2 Policy 5 Development
Management and Placemaking, and Policy GBRA1 Rural Design and Development
aim to ensure well designed development that makes for successful places and
considers the impact on residential amenity and the appropriateness of the
development to a rural setting. 
10.16. Informal open space, a village green and plays areas, structural landscaping, links to
the existing path network and safe vehicle accesses into and out of the site will create
a sense of place with the benefits of a rural lifestyle.  A range of housing styles and
sizes will be provided, adaptable to the needs of families, couples and individuals. 
Landscaping and new woodland planting will contribute to visual screening whilst
enhancing the overall setting of the development.  The proposed layout has been
designed in a manner which ensures that the amenity and privacy of existing and
future residents will not be compromised.  Connections and linkages through to the
adjacent Miller residential development (Planning Application P/26/0458), will allow
these two parcels of development to function as a single unified neighbourhood. 
Roads, Transportation and Fleet Services in their consultation response did not raise
23

Page 24

any public or traffic safety issues.  There are no infrastructure constraints.  The
proposal will not impact upon landscape features, protected habitats, or species.  The
proposal is therefore satisfactory in terms of NFP4 Policy 14 and SLLDP2 Policies 5
and GBRA1. 
10.17. NPF4 Policy 15 relates to local living and 20 minute neighbourhoods.  It seeks to
create connected and compact neighbourhoods where people can meet most of their
daily needs within a reasonable distance of their home, preferably by using sustainable
transport. 
10.18. Both the adjoining Ogilvie and Miller Homes developments combined will ensure
footpath connections into Lanark racecourse, Lanark Moor Country Park and
Springbank Cemetery.  Lanark market and a veterinary clinic are only 250m to the
west.  The site lies close to a bus stop, where a frequent bus service to Lanark can be
accessed – in Lanark there is a wide range of shops, services, business, schools, a
medical centre, train station and leisure facilities.  There are safe pedestrian routes
into Lanark via the Racecourse.  Lanark is only 2km to the west which is a reasonable
walking and cycling distance.  Within the development an extensive area of
landscaped amenity space with play facilities will be laid out to meet the recreational
needs of a range of ages.  In view of the circumstances described, the proposal does
on balance accord with the aims and intent of Policy 15 Local Living and 20 minute
neighbourhoods of National Planning Framework 4. 
10.19. Community Infrastructure Assessment
SLLDP2 Policy 7 Community Infrastructure Assessment states where development
proposals would require capital or other works or facilities to enable to proceed,
financial contributions towards their implementation will be required.   
10.20. SLLDP2 Policy 12 – Affordable housing advice for sites of 20 or more units advises
25% of capacity should be allocated on site.  If on site provision is not viable, then a
contribution towards affordable housing on alternative sites within the housing
catchment area will be sought. 
10.21. There have been no requests from Roads or Community facilities for contributions.  A
contribution for Education in relation to primary and nursery provision is required. 
Whilst a commuted sum is required to contribute to the provision of affordable housing
elsewhere in the local area.  The terms of SLLDP2 Policies 7 and 12 can be complied
with and a decision will not be issued until the conclusion of a section 75 agreement
covering the contributions and on-site provision of affordable housing. 
10.22. Play, Recreation and Sport 
NPF4 Policy 21 – Play recreation and sport advises that residential development
incorporates well designed, good quality provision for play, recreation, and relaxation
that is proportionate to the scale and nature of the development.  New residential areas
should be inclusive and enable children and young people to play and move around
safely and independently, maximising opportunities for informal and incidental play in
the neighbourhood. 
10.23. The proposed layout identifies a central village green with play area and an amenity
space, close to the entrance.  If planning permission is granted, a condition will be
applied requiring approval of the details for play areas.  There will be a network of
paths throughout the site and connections to the footpath network proposed for the
adjacent Miller Homes site.  The neighbouring Lanark Racecourse and Lanark Moor
Country Park have sports and all weather pitches and mountain bike routes providing
24

Page 25

recreational opportunities for residents.  In consideration the terms of NPF4 Policy 21
can be met. 
10.24. Travel and Transport
NPF4 Policy 13 Sustainable Transport states that for significant car generating
developments, a Transport Assessment and Travel Plan would be required.  Over
reliance on private car journeys will be discouraged.  SLLDP2 Policy 15 Travel and
Transport advises that active travel and the availability and/or provision of public
transport facilities and access to, should be fundamental design and locational
elements of new development. 
10.25. A Transport Assessment has been submitted, and Roads agree with the conclusions
of the report that the additional traffic generation will not adversely impact upon the
road network.  New priority junctions have been designed to a satisfactory standard,
adequate parking can be provided, and the road system includes traffic calming
measures and safe crossings.  The layout will have segregated and safe links to local
facilities via walking and cycling networks.  The residential development is accessible
by public transport.  There are regular buses to Lanark where a wide range of shops,
services and employment opportunities can be accessed.  At Lanark Railway Station
a regular train service to Hamilton, Glasgow and the wider conurbation is available.  In
considering these factors the proposal accords with NPF4 Policy 13 and SLLDP2
Policy 15. 
10.26. Natural and Historic Environment
NPF4 Policy 3 Biodiversity relates to biodiversity and details that all local development
shall include appropriate measures to conserve, restore and enhance biodiversity. 
10.27. Existing woodland in the southern edge will be retained and structured tree planting
will be established along the eastern boundary thereby facilitating ecological corridors
for wildlife.  Wherever possible, existing trees will be retained and protected.  Trees
and bulbs will be planted in selected locations throughout the site.  Extensive areas of
flowering meadows will be created to encourage pollinators.  Recommendations in the
Preliminary Ecological Appraisal and the Strategic Biodiversity Management Plan will
be complied with.  Therefore, the proposal accords with NPF4 Policies 3 and 6. 
10.28. NPF4 Policy 7 Historic assets, SLLDP2 Policies 14 and NHE3 – Listed Buildings states
that the layout, design, materials, scale, siting of any development shall be sensitive
to and respect the character and setting of Listed Buildings. 
10.29. The layout and house designs take cognisance of the setting of two neighbouring listed
buildings, the Sandhurst Building and the Sergeants Mess.  Dwellings fronting
Robertson Drive, towards the Sandhurst Building will reinforce the interrelationship
between the new development and the heritage asset.  Dwellings adjoining the
Sergeants Mess will be positioned to present side elevations thereby deferring to the
prominence of the Sergeants Mess.  At key corner plots, close to the listed buildings,
plots will accommodate larger dwellings with dual aspect frontages, designed and
located to respect the setting.  External finishes will feature red multi brick and red tiles
to enable sensitive integration.  In considering the above assessment, the setting and
character of the Listed Buildings would not be adversely affected.  Therefore, the
proposal complies with NPF4 Policy 7 and SLLDP2 Policies 14 and NHE3. 
10.30. Conclusion 
The proposal will result in the development of vacant land adjoining Lanark and will
help meet demand for housing in the Lanark area.  Whilst the proposal does not fully
comply with the current land use policies contained in the development plan, the extant
25

Page 26

planning permission for a residential development on the site is a significant material
consideration.  The proposed layout reflects the extant permission and is considered
to be acceptable.  On balance, it is considered that this proposal can be supported as
a departure.  Overall, it is an appropriate form of development at this location. 
11. Recommendation and Conditions
11.1.  The Committee is asked to agree the following recommendation:- 
Grant Detailed Planning Permission subject to conditions and the conclusion of
a Section 75 agreement (or other appropriate legal agreement) to secure
affordable housing contributions (or suitable alternative arrangement) and for
financial contributions towards educational provision (nursery and primary
school provision):- 
In accordance with agreed procedure, should there be no significant progress, on
behalf of the applicant, towards the conclusion of the Planning Obligation within 6
months of the date of the Committee, the proposed development may be refused on
the basis that, without the planning control/developer contribution which would be
secured by the Planning Obligation, the proposed development would be
unacceptable. 
Conditions 
01. The development to which this permission relates shall be begun no later than
the expiration of three years beginning with the date of grant of this decision
notice.  
Reason: To comply with Section 58(1) of the Town and Country Planning
(Scotland) Act 1997 (as amended). 
02. That before development starts, full details of the design and location of all
fences and walls, including any retaining walls to be erected on the site shall
be submitted to and approved by the Council as Planning Authority.  Thereafter
the development shall be completed in accordance with the approved details.  
Reason: To ensure the development is satisfactory in appearance and to
maintain the visual quality of the area. 
03. That no trees, identified on the approved Landscaping plans for retention, shall
be felled, removed or otherwise affected without the prior written consent of the
Council as Planning Authority.    
Reason: In the interests of amenity and to ensure the protection and
maintenance of the existing trees and other landscape features within the site. 
04. The tree protection measures and arboricultural recommendations listed in the
Arboricultural Impact Assessment (Envirocentre Ltd, September 2025) shall be
fully complied with.    
Reason: To ensure that the trees to be retained will not be damaged during
construction and to protect and enhance the appearance and character of the
site and locality.  
26

Page 27

05. That the landscaping scheme relating to the development hereby approved
shall be carried out and completed simultaneously with the development.   
Reason: In the interests of the visual amenity of the area. 
06.  The recommendations and mitigation measures as listed in the Preliminary
Ecological Appraisal (Acorna Ecology Associates Ltd, May 2025) and the
Strategic Biodiversity Management Plan (Acorna Ecology Associates, July
2025) shall be fully complied with.    
Reason: In the interests of biodiversity and wildlife 
07. Prior to work commencing on the site, a scheme for the provision of play area(s)
within the site shall be submitted to the Council as Planning Authority for written
approval and shall include:- 
(a) details of the type and location of play equipment, seating and litter bins to
be situated within the play area(s); 
(b) details of the surface treatment of the play area, including the location and
type of safety surface to be installed; 
(c) details of the fences to be erected around the play area(s); and 
(d) details of the phasing for the completion of these works unless agreed in
writing by the Council as Planning Authority.      
Reason: To ensure the provision of adequate play facilities within the site and
in order to retain effective planning control. 
08. No development shall commence unless otherwise agreed in writing with the
Planning Authority until drainage details have been provided and approved
which demonstrate compliance with the principles of sustainable urban
drainage systems and with the Council's Developer Design Guidance (May
2020).  These details shall include the submission of the following signed
appendices:- 
 C 'Sustainable Drainage Design Compliance certificate', 
 D 'Sustainable Drainage Design Independent Check Certificate' and 
 E 'Confirmation of Future Maintenance of Sustainable Drainage
Apparatus’. 
Thereafter development shall not be occupied until the surface drainage works
have been completed in accordance with the approved details.         
Reason: To ensure that the disposal of surface water from the site is dealt with
in a safe and sustainable manner, to return it to the natural water cycle with
minimal adverse impact on people and the environment and to alleviate the
potential for on-site and off-site flooding. 
09.  Prior to development commencing on site, a scheme for the control and
mitigation of dust shall be submitted to and approved in writing by the Council
as Planning Authority.  No changes to the approved scheme shall take place
unless agreed in writing by the Planning Authority.  The scheme shall thereafter
be implemented during construction on site. 
Reason: To minimise the risk of nuisance from dust to nearby occupants. 
27

Page 28

10.  No piling works shall be carried out until a method statement has been
submitted to and approved in writing by the Planning Authority.  This statement
shall include an assessment of the impact of the piling on surrounding
properties, taking into account the guidance contained in BS 6472: 1992
'Evaluation of human exposure to vibration in buildings'.  It shall detail any
procedures which are proposed to minimise the impact of noise and vibration
on the occupants of surrounding properties.  This statement shall be prepared
by a suitably qualified person, and the piling works shall thereafter be carried
out in accordance with the approved method statement. 
Reason: To minimise noise, vibration and disturbance to neighbouring
residents/occupants during blasting. 
11.  That prior to the commencement of development details of the construction,
surface density of materials, final position and maintenance scheme of the
acoustic barriers, as recommended by the Report on Road Traffic Sound
(Charlie Fleming, August 2026) shall be submitted and approved by the
Planning Authority.  The approved acoustic barrier shall be installed prior to the
occupation of the dwellings, unless otherwise agreed in writing by the Planning
Authority and thereafter maintained to the satisfaction of the Council. 
Reason: To protect residents from unreasonable levels of road traffic noise. 
12. Prior to the commencement of development full details of the glazing
components and trickle vents proposed to be used at the properties most
exposed to road traffic noise shall be submitted to and approved in writing by
the Planning Authority.  Thereafter the development shall be completed in
accordance with the approved details. 
Reason: To ensure that the internal noise levels shall complies with BS
8233:2014 Guidance on sound insulation and noise reduction for buildings. 
13. A detailed remediation strategy, which takes cognisance of the conclusions and
recommendations of the Site Investigation Report (Mason Evans, January
2025) shall be submitted to and approved in writing by the Council as Planning
Authority.  No works other than investigative works shall be carried out on site
prior to receipt of the Council's written approval of the remediation plan. 
Reason: To avoid unacceptable risks to human health and the environment, to
ensure that the land is remediated and made suitable for its proposed use. 
14.  (a)  Remediation of the site shall be carried out in accordance with the
approved remediation plan prior to the occupation of dwellings.  Any
amendments to the approved remediation plan shall not be implemented unless
approved in writing by the Planning Authority. 
(b)  On completion of the remediation works, the developer shall submit a
completion report to the Planning Authority, confirming that the works have
been carried out in accordance with the approved remediation plan and that the
works have successfully reduced these risks to acceptable levels. 
(c)  Any previously unsuspected contamination which becomes evident
during the development of the site shall be brought to the attention of the
Planning Authority within one week or earlier of it being identified.  A more
detailed site investigation to determine the extent and nature of the
28

Page 29

contaminant(s) and a site-specific risk assessment of any associated pollutant
linkages, shall then require to be submitted to and approved in writing by the
Planning Authority. 
Reason: To avoid unacceptable risks to human health and the environment, to
ensure that the land is remediated and made suitable for its proposed use. 
12. Reason for Decision
12.1. The principle of a residential development on the site is contrary to Policies 17 and 16
of National Planning Framework 4.  However, planning permission was previously
granted for 347 dwellings on the site and that permission remains extant.  The
remaining approved dwellinghouses can therefore still be constructed and the site is
identified in the South Lanarkshire Housing Land Audit as a windfall development site. 
These factors are a significant material consideration.  The proposal will not adversely
impact on residential amenity, biodiversity and road safety, and makes optimum use
of vacant land, helping to meet demand for housing.  The proposal accords with
Policies 1, 2, 3, 6, 9, 13, 14, 15, and 21 of National Planning Framework 4 and policies
2, 3, 5, 7, 11, 12, 15, GBRA1 and GBRA5 of the South Lanarkshire Local Development
Plan 2.  On balance, it is considered that this proposal can be supported as a departure
since it is an appropriate form of development at this location.   
Kevin Carr
Executive Director (Community and Enterprise Resources) 
Date: 29 September 2026 
Background Papers 
P/26/0092 Erection of 117 dwellings, landscaping, access, drainage and associated works 
Corporate Considerations
The report raises no impacts or risks in terms of equalities or financial implications.  Any
implications in terms of climate change, sustainability or the environment will have been
considered above in terms of the relevant national and local policies. 
Contact for Further Information
If you would like to inspect the background papers or want further information, please
contact:-
E-mail:  planning@southlanarkshire.gov.uk 
29

Page 30

30

Page 31

Addendum Specifying Heads of Terms in relation to any relevant legal agreement 
Planning
Application No.
P/26/0092
Development
Description
Erection of 117 dwellings, landscaping, access, drainage and
associated works 
Site Address  Winston Barracks, Robertson Drive, Lanark 
Applicant Abbey Developments (Lanark) Ltd 
Date of
Committee 
6 October 2026
Type of
obligation 
Section 75 or an appropriate alternative legal agreement such as
a Section 69 agreement 
Obligations 
Resource Summary of Required Contributions
Community  N/A 
Education  Contributions are required for primary and nursery provision within
the surrounding area
Housing  On site provision of affordable housing or an appropriate
contribution
Roads  N/A 
31

Page 32

32

Page 33

Report
Agenda Item 
Report to: Planning Committee
Date of Meeting: 6 October 2026
Report by: Executive Director (Community and Enterprise
Resources)  
Reference no:  P/26/0458
Proposal:  Erection of 207 dwellings, landscaping, open space, access, drainage
and associated works
Site Address:  Winston Barracks, Robertson Drive, Lanark
Applicant:  Miller Homes Scotland West / Abbey Developments (Lanark) Ltd
Agent:  Stantec
Ward:  02 Clydesdale North
Application Type:  Detailed Planning Permission
Advert Type:  Lanark Gazette 13 May 2026
Development Plan
Compliance: 
No 
Departures:  Yes
Recommendation:  Grant subject to conditions and legal agreement
Legal Agreement:  Yes – to secure financial contributions towards education and onsite
provision of affordable housing.
Direction to
Scottish Ministers 
N/A 
5
33

Page 34

1. Reason for Report
1.1. This application is being presented to Committee as it constitutes a major planning
application under The Town and Country Planning (Hierarchy of Developments)
(Scotland) Regulations 2009 and the Scheme of Delegation requires that all major
applications are determined by the Planning Committee. 
2. Site Description
2.1. The application site (8.7 ha) lies to the east of Lanark – it is vacant land within the
confines of the former Winston Barracks.  Previously it contained an assortment of
buildings associated with the military function of the Barracks.  Since their demolition,
the area has largely reverted to scrub.  Topographically the site is relatively level. 
2.2.  The site is bounded to the north and west by existing woodland belts and beyond by
Lanark Racecourse, Lanark Moor Country Park and agricultural land.  To the east is
vacant land subject of a separate Planning Application P/26/0092 for 118 dwellings,
submitted by Ogilvie Homes.  To the south are existing dwellings including the
converted B-Listed Sandhurst Building and associated amenity and parking areas. 
3. Description of Proposed Development
3.1. The applicant seeks planning permission for a residential development consisting of
207 dwellings, including 30 affordable units.  Other than 12 single storey semi-
detached dwellings, the house types are a mixture of 2 storey detached, semi-
detached and terraced dwellings (44 five bedroom, 71 four bedroom, 77 three
bedroom and 15 two bedroom).  The house designs are contemporary and external
finishes include red facing brick, render and grey and red tiles. 
3.2. Access will be taken from an extension of Robertson Drive via a roundabout access
onto Hyndford Road, (A73) and a new priority access onto A70 in the northeast corner
of the site.  From Robertson Drive, a primary loop road will extend around the site.  A
network of interconnected, secondary roads will branch out from the primary loop.  The
footpath network will provide links to the existing core paths.  Surface water will be
treated by an extensive soakaway system connected to several soakaway basins
located in designated green space.  Landscaping and amenity space will be laid out
throughout the development, with a centrally located village green containing a toddler
play area to create a focal point. 
3.3. As the proposal relates to a residential development which falls within the definition of
‘major’ development, as set out in the Town and Country Planning (Hierarchy of
Developments) (Scotland) Regulations 2009 the applicants undertook a pre-
application consultation prior to the submission of this planning application.   
4. Relevant Planning History
4.1. The following is a list of previous applications relating to the application site:- 
 Listed Building Consent (Ref. P/25/0008) for the demolition of the former Officers
Mess (C-Listed), granted August 2025
 A Proposal of Application Notice (Ref. P/24/0019/PAN) for residential
development was issued in December 2024 with further consultations required
 Planning Permission (Ref. CL/08/0057) for alteration to site layout and
substitution of house types (amendment to CL/06/0345) granted May 2008
 Planning Permission (Ref. CL/06/0345) for 347 dwellings and conversion of 4
Listed Buildings to form 45 residential units, was granted September 2007
 Listed Building Consent (Ref. CL/05/0486) for the conversion of 4 Listed
Buildings, granted December 2006  
34

Page 35

 Planning Permission (Ref. CL/00/0320) for residential development (Outline)
granted March 2006 
5. Supporting Information 
5.1. In support of the planning application, the applicant has submitted:- 
⧫ Preliminary Ecological Appraisal
⧫ Proposal of Application Consultation (PAC) Report
⧫ Site Investigation
⧫ Planning Statement
⧫ Transport Assessment
⧫ Air Quality Impact Assessment
⧫ Arboriculture Impact Assessment
⧫ Noise Impact Assessment
⧫ Drainage Statement
⧫ Energy Statement
⧫ Protected Species Survey
⧫ Badger Monitoring
⧫ Bat Emergence Survey 
6. Consultations
6.1. West of Scotland Archaeological Service – There is no known significant
archaeological potential and no investigations are required.
Response:  Noted. 
6.2. Scottish Power Energy Network (SPEN) – No objection, however, there is a substation
with underground cables in the vicinity of the site and SPEN therefore reserve the right
to protect and/or deviate apparatus at the applicant’s expense. 
Response:  Noted. 
6.3. Developer Obligations - Contributions are required for Education in relation to primary
and nursery provision.  On site provision of 30 affordable housing units is also required.
Response: If Committee is minded to grant consent, this contribution and on-site
affordable housing provision will be dealt with through a legal agreement. 
6.4. Environmental Services – No objection, subject to conditions requiring a piling method
statement, noise mitigation, contaminated land remediation and dust control. 
Response:  Noted.  Should planning permission be approved appropriate conditions
would be attached to any decision issued. 
6.5. Roads, Transportation and Fleet Services – No objection subject to conditions.
Response:  Noted. 
6.6. Countryside and Greenspace – No objection and they welcome the recommendations
in the Ecological appraisal to enhance biodiversity. 
Response:  Noted.  The retained woodland belts within the application site will be
reinforced with additional planting and habitat creation. 
6.7. Roads Flood Risk Management – No response received to date.
Response:  The site is not identified as falling within a flood risk area.  A Drainage
Assessment and plans showing the proposed drainage system, including SUDS
basins have been submitted.  If consent is granted a condition will be attached
requiring the completion of self-certification and independent check certificates
appendices for drainage as listed in the Council's Developer Design Guidance (May
2020). 
35

Page 36

6.8. Scottish Water – No objection.  There is sufficient capacity in the Camps Water
Treatment Works for a foul only connection to the Lanark Wastewater Treatment
works.  The development may impact upon infrastructure in the proximity of the
development and Scottish Water should be contacted by the developer directly. 
Response:  Noted.  Surface water will be directed to soakaway basins and will not
connect into the sewage network. 
6.9. The Royal Burgh of Lanark Community Council – No objection subject to the
development including appropriate drainage measures and not having a detrimental
impact on associated services and facilities in the surrounding area.  The development
should also include appropriate street lighting, play areas and footpath links. 
Response:  Noted.  The development will include appropriate street lighting, play area
and footpath links.  In addition, affordable housing will be addressed through on-site
provision and a financial contribution will be sought to address any educational
impacts of the development. 
7. Representations
7.1. Following the statutory period of neighbour notification and advertisement in the local
press, no valid representations have been received.   
8. Development Plan
8.1. Under Section 25 of the Town and Country Planning (Scotland) Act 1997, all
applications must be determined in accordance with the Development Plan, unless
material considerations indicate otherwise. 
8.2. National Planning Framework 4 
National Planning Framework 4 (NPF4) is Scotland’s national spatial strategy for
Scotland.  It sets out spatial principles, regional priorities, national developments and
national planning policy.  NPF4 supports the planning and delivery of sustainable
places, liveable places and productive places. 
National Planning Framework 4 Policies 
 Policy 1 - Tackling the climate and nature crises 
 Policy 2 - Climate mitigation and adaptation 
 Policy 3 – Biodiversity
 Policy 6 - Forestry, woodland and trees
 Policy 9 - Brownfield, vacant and derelict land and empty buildings
 Policy 13 Sustainable transport
 Policy 14 - Design, quality and place
 Policy 15 - Local living and 20 minute neighbourhoods
 Policy 16 - Quality homes
 Policy 17 - Rural homes
 Policy 21 - Play, recreation and sport 
8.3. South Lanarkshire Local Development Plan 2 (2021)
For the purposes of determining planning applications the Council will assess
proposals against the policies contained within the adopted South Lanarkshire Local
Development Plan 2 (SLLDP2).  In this regard the application site and associated
proposals are affected by the following policies contained in the SLLDP2:- 
SLLDP2 Volume 1 Policies
 Policy 2 - Climate Change
 Policy 3 - General Urban Areas and Settlements
 Policy 5 - Development Management and Placemaking
36

Page 37

 Policy 7 - Community Infrastructure Assessment
 Policy 11 - Housing
 Policy 12 - Affordable Housing
 Policy 15 - Travel and Transport 
SLLDP2 Volume 2 Policies
 Policy GBRA1 - Rural Design and Development
 Policy GBRA5 - Redevelopment of Previously Developed Land Containing
Buildings 
9. Guidance
9.1. None applicable 
10. Assessment and Discussion
10.1. The determining issues in the consideration of this application are its compliance with
National Planning Framework 4 (NPF4) and the adopted South Lanarkshire Local
Development Plan 2 (SLLDP2). 
10.2. Climate Change 
Policies 1 and 2 of NPF4 and Policy 2 of the SLLDP2 relate to the climate crises and
identify that all development should seek to minimise and mitigate the effects of
climate change. 
10.3. The site is not identified on SEPA flooding maps as being at risk of flooding.  Proposed
sustainable urban drainage systems (SUDS) will effectively manage surface water
runoff, benefitting neighbouring properties and the drainage network.  If approved,
conditions will be attached requiring the implementation of a landscaping scheme
which includes native tree and hedgerow planting.  The proposal involves
development of vacant brownfield land served by good public transport links.  Overall,
the proposal would not compromise the objectives of NPF4 Policies 1 and Policy 2
and SLLDP2 Policy 2. 
10.4. Principle of Development 
NPF4 Policy 17 Rural homes advises that development proposals for new homes in
rural areas will be supported where the development is suitably scaled, sited and
designed to be in keeping with the character of the area and the development can
meet one of the following criteria: the site is allocated for housing in the Local
Development Plan; reuses a redundant or unused building; supports a viable rural
business; is for a retired farmer; reuses brownfield land where a return to a natural
state has not or will not happen without intervention; or, is for a one to one replacement
of an existing house. 
10.5. The application site could be defined as brownfield land because of its previous use
as a barracks.  It contained numerous military style buildings including an indoor
shooting range, Officers Mess, administrative blocks and Naffi.  Although there is
evidence of hardstanding throughout the site it has largely reverted to scrub,
comprising young trees, wildflowers and gorse.  Therefore, considering these
circumstances the proposal does not meet criteria NPF4 Policy 17 a) ii where a return
to a natural state would not be possible without intervention. 
10.6. However, the site is subject of Planning Permission CL/06/0345 for 347 dwellings and
conversion of 4 Listed Buildings.  This consent was implemented with two of the Listed
Buildings (Sandhurst Building and Sergeants Mess) having been converted and 32
townhouses built, thereby ensuring Planning Permission CL/06/0345 remains extant. 
The remaining approved dwellings, within the current application site area and the
37

Page 38

adjoining residential site, being progressed by Ogilvie Homes, could in effect still be
built.  The change proposed by the current application principally relates to a change
in house types.  It is therefore considered that this application can be supported as a
departure from the development plan in recognition of the development history of the
site. 
10.7. Policy 4 ‘Green Belt and Rural Area’ of the adopted South Lanarkshire Local
Development Plan 2 specifies that within the Rural Area the aim is to protect the
amenity of the countryside while at the same time, supporting small scale development
in the right places that is appropriate in land use terms and is of a high environmental
quality that will support the needs of communities.  Generally, it is expected that
houses will be accommodated within identified settlements other than circumstances
including redevelopment of previously developed land containing buildings. 
10.8. SLLDP2 Policy GBRA5 ‘Redevelopment of Previously Developed Land Containing
Buildings’ outlines a number of criteria relevant to redevelopment proposals.  Although
consented prior to the adoption of SLLDP2, the appropriateness of a brownfield
development, (which did contain buildings, since demolished) in this rural location has
been established by the previous consent CL/06/0345 which remains extant.  As the
proposal under consideration will not have an adverse impact on the wider area in
terms of landscape character and setting it is reasonable to conclude that it complies
with SLLDP2 Policies 4 and GBRA5. 
10.9. NPF4 Policy 16 – Quality homes seek to encourage, promote and facilitate the delivery
of high quality homes, in the right locations.  It advises that development proposals for
new homes on land not allocated for housing in the local development plan will only
be supported in limited circumstances, where there is an agreed timescale for build-
out, where they are consistent with the spatial strategy and local living and in rural
locations, must be consistent with the policy on rural homes. 
10.10. In this case, the proposal contravenes policy criteria above for rural homes.  However,
the proposal represents a housing opportunity, served by a public bus route and within
reasonable walking and cycling distance of Lanark.  The layout will be enhanced by
extensive amenity open space, tree planting and structured landscaping.  The
landscaping scheme will contribute to biodiversity.  The applicant, a national house
builder, has carried out extensive market research and on those findings is confident
of significant demand for new housing in the locality.  The site was previously identified
as a housing supply site and the current proposal would include 30 affordable units. 
Redeveloping unattractive vacant land with a sensitively designed residential
development will result in environmental and amenity improvements.  The applicant
has provided a Statement of Community Benefit.  For these reasons and the reasons
elaborated in paragraph 10.5 above, a departure from policy can be justified. 
10.11. NPF4 Policy 9 Brownfield, vacant, derelict land and empty buildings - the relevant
sections states: ‘Development proposals that will result in the sustainable reuse of
brownfield land including vacant and derelict land and buildings, whether permanent
or temporary, will be supported.  In determining whether the reuse is sustainable, the
biodiversity value of brownfield land which has naturalised should be taken into
account’ and ‘Where land is known or suspected to be unstable or contaminated,
development proposals will demonstrate that the land is, or can be made, safe and
suitable for the proposed new use’. 
10.12. Although the site has started to regenerate, the scrub habitat is not considered to have
significant biodiversity value.  Proposed biodiversity enhancement will ensure the
housing development can be integrated into its setting without detriment to overall
38

Page 39

biodiversity value.  The proposed development will result in the sustainable reuse of
brownfield land which formerly operated as a military barracks.  A comprehensive
Ground Investigation Report has been submitted containing survey results,
assessments, and recommendations for remediation.  As a precaution, Environmental
Services in their consultation response recommended conditions requiring the
submission and implementation of a remediation strategy.  In consideration the
proposal complies with NPF4 Policy 9. 
10.13. SLLDP2 Policy 11 - Housing supports development included in the housing land
supply audit and identified in the Local Plan proposals map.  If, during the period of the
plan, a shortfall in the five year supply of effective land is identified, the Council will
support development proposals which are effective and capable of meeting the
identified shortfall.  This includes non-effective sites that can now be demonstrated to
be effective and additional brownfield sites. 
10.14. Although identified as a windfall site in the recent South Lanarkshire Housing Land
Audit (CL5035 Winston Barracks) the application site is not identified in the Local Plan
proposal map.  Under previous Local Plans it had been identified as allocated housing
land.  For many years only a small proportion of the approved dwellings subject of
Planning Permission CL/06/0345 for 347 dwellings had been completed leaving the
impression that most of the site was non-effective.  The recent submission of Planning
Applications for the remaining site area by Miller Homes and Ogilvie now demonstrates
an intention to progress a residential development.  In helping to meet latent demand
for housing, the terms of SLLDP2 Policy 11 have not been compromised. 
10.13. Layout, Siting and Design 
NPF4 Policy 14 Design Quality and Place and SLLDP2 Policy 5 Development
Management and Placemaking and Policy GBRA1 Rural Design and Development,
aim to ensure well designed development that makes for successful places and
considers the impact on residential amenity and the appropriateness of the
development to a rural setting. 
10.14. Informal open space, a village green and plays areas, structural landscaping, links to
the existing path network and safe vehicle access to and from the site will create a
sense of place with the benefits of a rural lifestyle.  A range of housing styles and sizes
will be provided, adaptable to the needs of families, couples and individuals. 
Landscaping and new woodland planting will contribute to visual screening whilst
enhancing the overall setting of the development.  The proposed layout has been
designed in a manner which ensures that the amenity and privacy of existing and future
residents will not be compromised.  Connections and linkages through to the adjacent
Ogilvie residential development (Planning Application P/26/0092), will allow these two
parcels of development to function as a single unified neighbourhood.  Roads,
Transportation and Fleet Services in their consultation response did not raise any
public or traffic safety issues.  There are no infrastructure constraints.  The proposal
will not impact upon landscape features, protected habitats, or species.  The proposal
is therefore satisfactory in terms of NFP4 Policy 14 and SLLDP2 Policies 5 and
GBRA1. 
10.15. NPF4 Policy 15 relates to local living and 20 minute neighbourhoods.  It seeks to create
connected and compact neighbourhoods where people can meet the majority of their
daily needs within a reasonable distance of their home, preferably by using sustainable
transport.  
39

Page 40

10.16. There are footpath connections into Lanark racecourse, Lanark Moor Country Park
and Springbank cemetery.  Lanark market and a veterinary clinic are only 250m to the
west.  The site lies close to a bus stop, where a frequent bus service to Lanark can be
accessed – in Lanark there is a wide range of shops, services, business, schools, a
medical centre, train station and leisure facilities.  There are safe pedestrian routes
into Lanark via the Racecourse.  Lanark is only 2km to the west which is a reasonable
walking and cycling distance.  Within the development an extensive area of
landscaped amenity space with play facilities will be laid out to meet the recreational
needs of a range of ages.  In view of the circumstances described, the proposal does
on balance accord with the aims and intent of Policy 15 Local Living and 20 minute
neighbourhoods of National Planning Framework 4. 
10.17. Community Infrastructure Assessment
SLLDP2 Policy 7 Community Infrastructure Assessment states where development
proposals would require capital or other works or facilities to enable to proceed,
financial contributions towards their implementation will be required.   
10.18. SLLDP2 Policy 12 – Affordable housing advice for sites of 20 or more units advises
25% of capacity should be allocated on site.  If on site provision is not viable, then a
contribution towards affordable housing on alternative sites within the housing
catchment area will be sought. 
10.19. There have been no requests from Roads or Community facilities for contributions.  A
contribution for Education in relation to primary and nursery provision is required. 
Housing advise that there should be onsite provision of 30 affordable units which is
deemed sufficient to accommodate local housing need.  The applicant has agreed to
building these units.  Revisions to layout and house types show affordable housing in
accordance with the appropriate specification.  The terms of SLLDP2 Policies 7 and
12 can be complied with and the decision will not be issued until the conclusion of a
Section 75 agreement covering the contributions and onsite provision of affordable
housing. 
10.20. Play, Recreation and Sport 
NPF4 Policy 21 – Play recreation and sport advises that residential development
incorporates well designed, good quality provision for play, recreation, and relaxation
that is proportionate to the scale and nature of the development.  New residential areas
should be inclusive and enable children and young people to play and move around
safely and independently, maximising opportunities for informal and incidental play in
the neighbourhood. 
10.21. The proposed layout identifies a toddler play area in the central village green and
another play area has been proposed for the public amenity space, close to the
entrance.  If Planning Permission is granted a condition will be applied requiring
approval of the details for the proposed play areas.  There will be a network of paths,
formal and informal, throughout the site and along the woodland perimeter.  The
neighbouring Lanark Racecourse and Lanark Moor Country Park have facilities
including all weather pitches and mountain bike routes providing recreational
opportunities for local residents.  In consideration the terms of NPF4 Policy 21 can be
met.  
40

Page 41

10.22. Travel and Transport
NPF4 Policy 13 Sustainable Transport states that for significant car generating
developments, a Transport Assessment and Travel Plan would be required.  Over
reliance on private car journeys will be discouraged.  SLLDP2 Policy 15 Travel and
Transport advises that active travel and the availability and/or provision of public
transport facilities and access to, should be fundamental design and locational
elements of new development. 
10.23.  A Transport Assessment has been submitted, and Roads agree with the conclusions
of the report that the additional traffic generation will not adversely impact upon the
road network.  New priority junctions have been designed to a satisfactory standard,
adequate parking can be provided, and the road system includes traffic calming
measures and safe crossings.  The layout will have segregated and safe links to local
facilities via walking and cycling networks.  The residential development is accessible
by public transport.  There are regular buses to Lanark where a wide range of shops,
services and employment opportunities can be accessed.  At Lanark Railway Station
a regular train service to Hamilton, Glasgow and the wider conurbation is available.  In
considering these factors the proposal accords with NPF4 Policy 13 and SLLDP2
Policy 15. 
10.24. Natural and Historic Environment
NPF4 Policy 3 Biodiversity relates to biodiversity and details that all local development
shall include appropriate measures to conserve, restore and enhance biodiversity. 
10.25. NPF4 Policy 6 Forestry, woodland and trees seeks to ensure development proposals
enhance, expand and improve woodland and tree cover. 
10.26. Existing woodland belts will be retained and enhanced with additional tree planting
along the edges thereby facilitating ecological corridors for wildlife.  Wherever possible
existing trees will be retained and protected.  Trees and hedgerow will be planted
throughout the site.  Flowering meadows will be established to encourage pollinators. 
No buildings with potential for bat roosts will be removed or altered unless Licence
authorisation from NatureScot has been obtained.  Recommendations in the Badger
Monitoring Report will be complied with.  The Landscaping Strategy includes a
Biodiversity Enhancement Plan.  Therefore, the proposal accords with NPF4 Policies
3 and 6. 
10.27. Conclusion 
The proposal will result in the development of vacant land adjoining Lanark and will
help meet demand for housing in the Lanark area.  Whilst the proposal does not fully
comply with the current land use policies contained in the development plan, the extant
planning permission for a residential development on the site is a significant material
consideration.  The proposed layout reflects the extant permission and is considered
to be acceptable.  On balance, it is considered that this proposal can be supported as
a departure.  Overall, it is an appropriate form of development at this location. 
11. Recommendation and Conditions
11.1.  The Committee is asked to agree the following recommendation:- 
Grant Detailed Planning Permission subject to conditions and the conclusion of
a Section 75 agreement (or other appropriate legal agreement) to secure 30
affordable housing units within the site (or suitable alternative arrangement) and
for financial contributions towards educational provision (nursery and primary
school provision):-  
41

Page 42

In accordance with agreed procedure, should there be no significant progress, on
behalf of the applicant, towards the conclusion of the Planning Obligation within 6
months of the date of the Committee, the proposed development may be refused on
the basis that, without the planning control/developer contribution which would be
secured by the Planning Obligation, the proposed development would be
unacceptable. 
Conditions 
01. The development to which this permission relates shall be begun no later than
the expiration of three years beginning with the date of grant of this decision
notice.  
Reason: To comply with Section 58(1) of the Town and Country Planning
(Scotland) Act 1997 (as amended). 
02. That before development starts, full details of the design and location of all
fences and walls, including any retaining walls to be erected on the site shall
be submitted to and approved by the Council as Planning Authority.  Thereafter
the development shall be completed in accordance with the approved details.  
Reason: To ensure the development is satisfactory in appearance and to
maintain the visual quality of the area. 
03. That no trees, identified on the approved Landscaping plans for retention, shall
be felled, removed or otherwise affected without the prior written consent of the
Council as Planning Authority.    
Reason: In the interests of amenity and to ensure the protection and
maintenance of the existing trees and other landscape features within the site. 
04. The tree protection measures and arboricultural recommendations listed in the
Arboricultural Impact Assessment (Envirocentre Ltd, September 2025) shall be
fully complied with.    
Reason: To ensure that the trees to be retained will not be damaged during
construction and to protect and enhance the appearance and character of the
site and locality. 
05. That the landscaping scheme relating to the development hereby approved
shall be carried out and completed simultaneously with the development.   
Reason: In the interests of the visual amenity of the area. 
06. The recommendations and mitigation measures as listed in the Preliminary
Ecological Appraisal (Wild Surveys Ltd, August 2025), Badger Monitoring (Wild
Surveys, May 2026) and Dusk Emergence Surveys (Wild Surveys Ltd, August
2026) shall be fully complied with.   
Reason: In the interests of biodiversity and wildlife 
07. Prior to work commencing on the site, a scheme for the provision of play area(s)
within the site shall be submitted to the Council as Planning Authority for written
approval and shall include:-  
42

Page 43

(a) details of the type and location of play equipment, seating and litter bins to
be situated within the play area(s); 
(b) details of the surface treatment of the play area, including the location and
type of safety surface to be installed; 
(c) details of the fences to be erected around the play area(s); and 
(d) details of the phasing for the completion of these works unless agreed in
writing by the Council as Planning Authority. 
Reason: To ensure the provision of adequate play facilities within the site and
in order to retain effective planning control. 
08. No development shall commence unless otherwise agreed in writing with the
Planning Authority until drainage details have been provided and approved
which demonstrate compliance with the principles of sustainable urban
drainage systems and with the Council's Developer Design Guidance (May
2020).  These details shall include the submission of the following signed
appendices:- 
 C 'Sustainable Drainage Design Compliance certificate', 
 D 'Sustainable Drainage Design Independent Check Certificate' and 
 E 'Confirmation of Future Maintenance of Sustainable Drainage
Apparatus’. 
Thereafter development shall not be occupied until the surface drainage works
have been completed in accordance with the approved details.         
Reason: To ensure that the disposal of surface water from the site is dealt with
in a safe and sustainable manner, to return it to the natural water cycle with
minimal adverse impact on people and the environment and to alleviate the
potential for on-site and off-site flooding. 
09.  Prior to development commencing on site, a scheme for the control and
mitigation of dust shall be submitted to and approved in writing by the Council
as Planning Authority.  No changes to the approved scheme shall take place
unless agreed in writing by the Planning Authority.  The scheme shall thereafter
be implemented during construction on site.  
Reason: To minimise the risk of nuisance from dust to nearby occupants. 
10.  No piling works shall be carried out until a method statement has been
submitted to and approved in writing by the Planning Authority.  This statement
shall include an assessment of the impact of the piling on surrounding
properties, taking into account the guidance contained in BS 6472: 1992
'Evaluation of human exposure to vibration in buildings'.  It shall detail any
procedures which are proposed to minimise the impact of noise and vibration
on the occupants of surrounding properties.  This statement shall be prepared
by a suitably qualified person, and the piling works shall thereafter be carried
out in accordance with the approved method statement. 
Reason: To minimise noise, vibration and disturbance to neighbouring
residents/occupants during blasting.  
43

Page 44

11.  That prior to the commencement of development, details of the construction,
surface density of materials, final position and maintenance scheme of the
acoustic barriers, as recommended by the Noise Impact Assessment
(Envirocentre, April 2026) shall be submitted and approved by the Planning
Authority.  The approved acoustic barrier shall be installed prior to the
occupation of the dwellings, unless otherwise agreed in writing by the Planning
Authority.  
Reason: To protect residents from unreasonable levels of road traffic noise. 
12. Prior to the commencement of development full details of the glazing
components and trickle vents proposed to be used at the properties most
exposed to road traffic noise shall be submitted to and approved in writing by
the Planning Authority.  Thereafter the development shall be completed in
accordance with the approved details.  
Reason: To ensure that the internal noise levels shall complies with BS
8233:2014 Guidance on sound insulation and noise reduction for buildings. 
13.  A detailed remediation strategy, which takes cognisance of the conclusions and
recommendations of the Site Investigation Report (Mason Evans, January
2025) shall be submitted to and approved in writing by the Council as Planning
Authority.  No works other than investigative works shall be carried out on site
prior to receipt of the Council's written approval of the remediation plan.  
Reason: To avoid unacceptable risks to human health and the environment, to
ensure that the land is remediated and made suitable for its proposed use. 
14.  (a)  Remediation of the site shall be carried out in accordance with the
approved remediation plan prior to the occupation of dwellings.  Any
amendments to the approved remediation plan shall not be implemented unless
approved in writing by the Planning Authority.  
(b)  On completion of the remediation works, the developer shall submit a
completion report to the Planning Authority, confirming that the works have
been carried out in accordance with the approved remediation plan and that the
works have successfully reduced these risks to acceptable levels. 
(c)  Any previously unsuspected contamination which becomes evident
during the development of the site shall be brought to the attention of the
Planning Authority within one week or earlier of it being identified.  A more
detailed site investigation to determine the extent and nature of the
contaminant(s) and a site-specific risk assessment of any associated pollutant
linkages, shall then require to be submitted to and approved in writing by the
Planning Authority.  
Reason: To avoid unacceptable risks to human health and the environment, to
ensure that the land is remediated and made suitable for its proposed use. 
12. Reason for Decision
12.1. The principle of a residential development on the site is contrary to Policies 17 and 16
of National Planning Framework 4.  However, planning permission was previously
granted for 347 dwellings on the site and that permission remains extant.  The
remaining approved dwellinghouses can therefore still be constructed and the site is
44

Page 45

identified in the South Lanarkshire Housing Land Audit as a windfall development site. 
These factors are a significant material consideration.  The proposal will not adversely
impact on residential amenity, biodiversity and road safety, and makes optimum use
of vacant land, helping to meet demand for housing.  The proposal accords with
Policies 1, 2, 3, 6, 9, 13, 14, 15, and 21 of National Planning Framework 4 and policies
2, 3, 5, 7, 11, 12, 15, GBRA1 and GBRA5 of the South Lanarkshire Local Development
Plan 2.  On balance, it is considered that this proposal can be supported as a departure
since it is an appropriate form of development at this location. 
Kevin Carr
Executive Director (Community and Enterprise Resources) 
Date: 29 September 2026 
Background Papers
P/26/0458 Erection of 207 dwellings, landscaping, open space, access, drainage and
associated works 
Corporate Considerations
The report raises no impacts or risks in terms of equalities or financial implications.  Any
implications in terms of climate change, sustainability or the environment will have been
considered above in terms of the relevant national and local policies. 
Contact for Further Information
If you would like to inspect the background papers or want further information, please
contact:-
E-mail:  planning@southlanarkshire.gov.uk 
45

Page 46

46

Page 47

Addendum Specifying Heads of Terms in relation to any relevant legal agreement 
Planning
Application No.
P/26/0458
Development
Description
Erection of 207 dwellings, landscaping, open space, access,
drainage and associated works 
Site Address  Winston Barracks, Robertson Drive, Lanark 
Applicant Miller Homes Scotland West / Abbey Developments (Lanark) Ltd 
Date of
Committee 
6 October 2026
Type of
obligation 
Section 75 or an appropriate alternative legal agreement such as
a Section 69 agreement. 
Obligations 
Resource Summary of Required Contributions
Community  N/A 
Education  Contributions are required for primary and nursery provision within
the surrounding area.
Housing  On site provision of affordable housing.
Roads  N/A 
47

Page 48

48

Page 49

Report
Agenda Item 
Report to: Planning Committee
Date of Meeting: 6 October 2026
Report by: Executive Director (Community and Enterprise
Resources)  
Reference no:  P/26/0470
Proposal:  Erection of four dwellinghouses, vehicular access and associated
infrastructure and landscaping (Planning Permission in Principle) 
Site Address:  Land Northeast of 41 Covanburn Avenue, Hamilton, ML3 7PX
Applicant:  Hamilton and Kinneil Estates Ltd
Agent:  Interurban Developments Ltd
Ward:  19 Hamilton South
Application Type:  Planning Permission in Principle
Advert Type:  Hamilton Advertiser – 9 July 2026
Development Plan
Compliance: 
Yes 
Departures:  N/A
Recommendation:  Grant subject to conditions
Legal Agreement:  N/A
Direction to
Scottish Ministers 
N/A 
6
49

Page 50

1. Reason for Report
1.1. The application is required to be determined by the Planning Committee under the
South Lanarkshire Council Scheme of Delegation as it has received more than 5
objections. 
2. Site Description
2.1. The site is within Silvertonhill, which is an established residential area in Hamilton. 
Covanburn Avenue is a no through road which is characterised by detached houses
finished in a mix of red brick and dry dash render that sit within relatively large plots. 
2.2. The proposed site is an area of grassed open space located off the hammer head at
the end of the street.  The site extends to 3,369 square metres and is essentially
rectangular in shape.  To the southeast the site is bounded by Covanburn Woods, on
all other sides the site is bounded by residential properties.  The site slopes northwest
to southeast from the rear gardens of the houses in Lilac Hill and Oak Lea down to
Covanburn Woods.  Along the boundary at the top of the slope there are 4 large,
mature sycamore trees. 
3. Description of Proposed Development
3.1. Planning permission in principle is sought for the erection of four dwellinghouses,
creation of an access with associated infrastructure and landscaping.   
3.2. The proposed access would extend from the end of Covanburn Avenue and the first
three houses would sit to the northwest of the access.  The first house would keep to
the same front building line as 41 Covanburn Avenue and the remainder would be set
back in line with the shape of the site so that the fourth house would sit at the end of
the access.  The plots and houses would be similar in scale to those in the surrounding
area. 
4. Relevant Planning History
4.1. The are no previous planning applications relative to this site. 
5. Supporting Information 
5.1. In support of the application, the following documents were submitted:- 
 Supporting Statement 
 Tree Survey 
6. Consultations
6.1. Roads, Transportation and Fleet Services – no objections subject to conditions
covering a dropped kerb access, a pedestrian footway, a drainage system and suitable
parking per unit.
Response:  Noted. 
6.2. Environmental Services – no objections.
Response:  Noted. 
6.3. Scottish Water – no objections.
Response:  Noted.  
50

Page 51

7. Representations
7.1. Following the statutory period of neighbour notification and advertisement, 21 letters
of representation were received objecting to the application.  The issues raised are
summarised as follows:- 
 Loss of an area of well used amenity space.
 The land is managed and maintained by the Low Waters Feuars Association
which residents have financed.
 Loss of a nature corridor and disruption to biodiversity of the area, particularly
nesting birds, owls and animals including bats, badgers, foxes and deer, some of
which are protected.
 Increase in traffic as the existing routes in and out of Silvertonhill are already very
busy.
 There are no details about the topography of the land, design of each plot or
impact on trees.
 Road safety issues from loss of the turning head and additional traffic at the end
of the road.
 The proposal risks creating an incongruous and more intrusive form of
development that is inconsistent with the established character of the area and
would be overdevelopment.
 Negative impact on health and wellbeing from the loss of greenspace.
 Loss of access to Covanburn Woods. 
 There is no public benefit and the harm caused would be disproportionate to the
limited housing gain.
 There is no Environmental Impact Assessment.
 Hamilton and Kinneil Estates have only taken over management of the land in
recent years and gave a guarantee it would not be built on.
 There are no elevations so it is impossible to determine if there will be overlooking
or overshadowing issues. 
7.2. The above issues are considered in the assessment below and full copies are
available to view on the planning portal. 
8. Development Plan
8.1. Under Section 25 of the Town and Country Planning (Scotland) Act 1997, all
applications must be determined in accordance with the development plan unless
material considerations indicate otherwise. 
8.2. National Planning Framework 4
National Planning Framework 4 (NPF4) is Scotland’s national spatial strategy and
supports the planning and delivery of sustainable, liveable and productive places. 
National Planning Framework 4 Policies 
 Policy 1 - Tackling the climate and nature crises
 Policy 2 - Climate mitigation and adaptation
 Policy 13 - Sustainable transport
 Policy 14 - Design, quality and place
 Policy 15 - Local living and 20 minute neighbourhoods
 Policy 16 - Quality homes  
51

Page 52

8.3. South Lanarkshire Local Development Plan 2 (2021) 
For the purposes of determining planning applications the Council will, therefore,
assess proposals against the policies contained within the adopted South Lanarkshire
Local Development Plan 2 (SLLDP2).  In this regard, the application site and
associated proposals are affected by the following policies contained in the SLLDP2:- 
SLLDP2 Volume 1 Policies
 Policy 2 - Climate Change
 Policy 3 – General Urban Areas and Settlements
 Policy 5 - Development Management and Placemaking 
SLLDP2 Volume 2 Policies
 Policy DM1 - New Development Design
 Policy NHE4 - Gardens and Designed Landscape 
9. Guidance
9.1.  None applicable. 
10. Assessment and Discussion
10.1. Principle of Development
The site is located within the general urban area where SLLDP2 Policy 3 applies.  This
policy seeks to ensure that development proposals make a positive contribution to the
character and appearance of the environment in which they are located, taking
account of, and being integrated with, the local context and built form.  The site is
identified as grassed open space within the urban area in the local plan.  Residential
development is therefore generally acceptable providing it does not have a detrimental
impact on neighbours or the surrounding area. 
10.2. Climate Change
Policies 1 and 2 of NPF4 and Policy 2 of SLLDP2 seek to promote developments that
address the global climate emergency and nature crisis.  All development should aim
to minimise and mitigate the effects of climate change.  Given the scale and nature of
the proposed development, it is not considered that any action is required within the
context of this application.  Further details of sustainable technologies such as solar
panels could be provided in a future detailed planning application. 
10.3. Layout, Siting and Design
The site is located in an established residential area of Hamilton where SLLDP2 Policy
3 - General Urban Areas and Settlements applies.  Also applicable are, NPF4 Policy
13 – Sustainable transport which aims to encourage, promote, and facilitate
developments that prioritise active travel and public transport and reduce the need to
travel unsustainably.  NPF4 Policy 15 – Local living and 20-minute neighbourhoods
aims to create neighbourhoods which provide for the daily needs of residents without
a need to make long journeys and NPF4 Policy 16 – Quality Homes, seeks to
encourage, promote, and facilitate the delivery of high-quality homes, in the right
locations.  Given that the site would be in an existing residential area where daily
needs could be reached within a reasonable distance of their home, and potentially
using sustainable transport options, it is considered that the proposal for four
dwellinghouses is acceptable at this location and would comply with SLLDP2 Policy 3
and NPF4 Policies 13, 15 and 16.  
52

Page 53

10.4. Policy 14 of NPF4 and Policies 5 and DM1 of the SLLDP2 relate to the quality and
design of a development.  Policy 14 – Design, quality and place seeks to encourage,
promote and facilitate well designed development that makes successful places. 
Proposals will be supported where they are consistent with the 6 qualities of successful
places.  It confirms that proposals which are poorly designed, detrimental to the
amenity of the surrounding area or inconsistent with the 6 qualities of place will not be
supported.  SLLDP2 Policy DM1 aims to promote quality and sustainability in the
design of new houses and states that their design and layout should enhance or make
a positive contribution to the character and appearance of the environment in which
they are located. 
10.5. In this instance, the application is for planning permission in principle and, as such,
there are no details of the proposed houses as part of this application.  It shall therefore
be up to the applicant to ensure that they take these policies into account when they
submit their further application.  However, in general terms it is considered that the
site has sufficient space to accommodate four dwellinghouses with appropriate
access, car parking and amenity space.  In light of this, it is considered that the
proposal is acceptable in terms of Policy 14 of NPF4 and Policies 5 and DM1 of the
SLLDP2. 
10.6. The most southern portion of the site falls within the Chatelherault Garden and
Designed Landscape covered by Policy NHE4 of the SLLDP.  Development affecting
sites listed in the Inventory of Gardens and Designed Landscapes shall protect,
preserve and, where appropriate, enhance such places and shall not significantly
impact adversely upon their character, important views to, from and within them, or
upon the site or setting of component features which contribute to their value.  It is not
considered that a significant portion of the site falls within this designation.  However,
it does cover Covanburn Woods which runs along the southeastern boundary and, as
such, the development will have to consider the siting and design of the houses
carefully in any future application to ensure that they do not detract from the
designated landscape. 
10.7. Conclusion 
The principle of a small scale development of 4 dwellings within the urban area is
considered to be acceptable.  The proposed dwellinghouses and associated works will
not result in an adverse impact on residential or visual amenity and comply with
Policies 1, 2, 14, 15, 16 of National Planning Framework 4 and Policies 2, 3, 5, DM1
and NHE4 of the adopted South Lanarkshire Local Development Plan 2.  Overall, the
proposal is considered to be an acceptable form of development at this location. 
11. Recommendation and Conditions
11.1. The Committee is asked to agree the following recommendation:- 
Grant planning permission in principle subject to the following conditions:- 
01. The development to which this permission in principle relates shall be begun
no later than the expiration of five years beginning with the date of grant of this
decision notice.   
Reason: To comply with Section 59 of the Town and Country Planning
(Scotland) Act 1997 (as amended).  
53

Page 54

02. Prior to the commencement of development on site, a further application(s) for
the approval of any of the matters specified in this condition must be submitted
to and approved by the Council as Planning Authority, in accordance with the
timescales and other limitations in section 59 of the Town and Country Planning
(Scotland) Act 1997 (as amended).   
These matters are as follows:-   
(a) the layout of the site, including all roads, footways, parking areas and open
spaces; 
(b) the siting, design and external appearance of all building(s) and any other
structures, including plans and elevations showing their dimensions and type
and colour of external materials; 
(c) detailed cross-sections of existing and proposed ground levels, details of
underbuilding and finished floor levels in relation to a fixed datum, preferably
ordnance datum; 
(d) the design and location of all boundary treatments including walls and
fences; 
(e) the landscaping proposals for the site, including details of existing trees and
other planting to be retained together with proposals for new planting specifying
number, size and species of all trees and shrubs, including, where appropriate,
the planting of fruit/apple trees; 
(f) the means of drainage and sewage disposal; 
(g) electric vehicle charging; 
(h) surface water drainage; and 
(i) details of the phasing of development.   
Reason: To comply with section 59 of the Town and Country Planning
(Scotland) Act 1997 as amended. 
03. The surface water drainage arrangements to be submitted in relation to
Condition no. 2 will require to comply with the principles of sustainable urban
drainage systems and with the Council's Sustainable Drainage Design Criteria
and shall include signed appendices as required.  The development shall not
be occupied until the surface drainage works have been completed in
accordance with the details submitted to and approved by the Council as
Planning Authority.   
Reason: To ensure that the disposal of surface water from the site is dealt with
in a safe and sustainable manner, to return it to the natural water cycle with
minimal adverse impact on people and the environment and to alleviate the
potential for on-site and off-site flooding. 
04. Notwithstanding Condition 2, the detailed design for the site should ensure
that:- 
1) A 2m wide footway would be required to be provided along the frontage of
the site where it meets the adopted road. 
2) Where the new footway is being provided, the existing lighting column would
have to be relocated. 
3) The entrance to the proposed properties would require a dropped kerb
access. 
4) A drainage system is required to prevent water flowing onto the proposed
adopted footway. 
54

Page 55

5) Parking for each property shall be as per the National Roads Development
Guide (NRDG) (i.e. 2/3-bedroom house requires 2 spaces, 4 or more-bedroom
house requires 3 spaces).  A parking bay shall be 6m x 3m in size. 
6) The proposed access would be private and not adopted by the Council. 
7) The access onto Covanburn Avenue should be 5.0m wide and the first 6m
behind the new footway should be of a bound material to prevent deleterious
material spilling onto the public road. 
8) The width of the shared joint access should be 3.7m wide. 
Reason: To ensure the provision of adequate parking, access arrangements
for both pedestrians and vehicles and drainage for the development is provided. 
Kevin Carr
Executive Director (Community and Enterprise Resources) 
Date: 29 September 2026 
Background Papers
Further information relating to the application can be found online:- 
P/26/0470 | Erection of four dwellinghouses, vehicular access and associated infrastructure
and landscaping | Land 55M Northeast Of 41 Covanburn Avenue Covanburn Avenue
Hamilton South Lanarkshire 
Corporate Considerations
The report raises no impacts or risks in terms of equalities or financial implications.  Any
implications in terms of climate change, sustainability or the environment will have been
considered above in terms of the relevant national and local policies. 
Contact for Further Information
If you would like to inspect the background papers or want further information, please
contact:-
E-mail:  planning@southlanarkshire.gov.uk 
55

Page 56

56

Page 57

Report
Agenda Item 
CHECKED
Report to: Planning Committee
Date of Meeting: 6 October 2026
Report by: Executive Director (Community and Enterprise
Resources)  
Reference no:  P/26/0918
Proposal:  Erection of two dwellings and associated works
Site Address:  Hawks Close
Cleghorn
Lanark
ML11 8NX 
Applicant:  Mr W Cruickshank Jnr
Agent:  Neville Design Ltd
Ward:  02 – Clydesdale North
Application Type:  Full Planning Permission
Advert :  Carluke Gazette - 12 August 2026
Development Plan
Compliance: 
No 
Departures:  N/A
Recommendation:  Refuse
Legal Agreement:  N/A
Direction to
Scottish Ministers 
N/A 
7
57

Page 58

1. Reason for Report
1.1. The application is required to be determined by the Planning Committee under the
South Lanarkshire Council Scheme of Delegation (2024) as the Head of Planning and
Regulatory Services, in consultation with the Chair of the Planning Committee, has
determined that it raises policy issues meriting consideration by the Planning
Committee. 
2. Site Description
2.1. The site relates to land at Hawks Close, Upper Muirhouse Farm, which is located
between the Harelaw Roundabout and Braehead.  The site is within the rural area. 
2.2. Excluding the access, the rectangular site for the house plots extends to approximately
0.13 hectares and lies between the recently constructed dwellings at Falconers Lane
and Hawks Close, and the existing property at Mid Muirhouse Farm. 
2.3. It is set back from the public road and, aside from the immediate cluster of new houses,
the wider surroundings consist of woodland and agricultural fields.  Although adjacent
land has been subject to development in recent years, the application site itself has
not previously been developed and remains an undeveloped area. 
3. Description of Proposed Development
3.1. The development comprises the erection of two single storey dwellinghouses together
with associated works.  These works include the formation of a private access taken
from Hawks Close, boundary enclosures, and connection to the existing private
surface water and foul drainage system which serves the neighbouring dwellings. 
3.2.  The proposed houses would be identical but handed and have a 160m2 rectangular
footprint, including integral garage, a gable roof finished in concrete tile with a ridge
height of 7.7m; external walls finished in white wet dash render and reconstituted
stone, with a height to the eaves of 2.6m; and modern fenestration including front and
rear French doors. 
4. Relevant Planning History
4.1. Seven houses were built at Upper Muirhouse Farm over the footprint of three
agricultural sheds.  Five have been given the address Falconers Lane (P/20/1666)
and two as Hawks Close (P/24/1079).  The site of this application lies between these
houses and Mid Muirhouse Farm, a recent dwelling (CL/07/0730) which was
developed by the applicant to support a deer enterprise. 
4.2. The planning obligation was subsequently removed (CL/12/0036 and CL/12/0226) and
the dwelling now exists independently. 
4.3. This is the second application for the proposed dwellings.  The first (P/25/1095) was
withdrawn on 26 January 2026 prior to its scheduled presentation to the Planning
Committee on 27 January 2026.   
5. Supporting Information 
5.1. A supporting statement has been submitted which contends that the site should be
regarded as previously developed land and therefore suitable for residential
development.  It also asserts that the proposal would complete a gap between existing
dwellings.  
58

Page 59

6. Consultations
6.1. Roads Development Management – no objection to the proposed development.
Response: Noted. 
6.2. Environmental Services – no objections to the proposed development. 
Response: Noted. 
6.3. Scottish Water – The site is within the catchment of the Coulter Water Treatment
Works but there is no public wastewater infrastructure within the vicinity. 
Response: Noted.
7. Representations
7.1. Following the statutory period of neighbour notification and advertisement, no valid
third-party representations have been received. 
8. Development Plan
8.1. Under Section 25 of the Town and Country Planning (Scotland) Act 1997, all
applications must be determined in accordance with the development plan unless
material considerations indicate otherwise.  The development plan comprises the
South Lanarkshire Local Development Plan 2 and National Planning Framework 4. 
8.2. National Planning Framework 4 
National Planning Framework 4 (NPF4) is Scotland’s national spatial strategy and
supports the planning and delivery of sustainable places, liveable places, and
productive places. 
National Planning Framework 4 Policies
 Policy 1 Tackling the climate and nature crises
 Policy 2 Climate mitigation and adaptation
 Policy 3 Biodiversity
 Policy 13 Sustainable transport
 Policy 14 Design, quality and place
 Policy 15 Local living and 20 minute neighbourhoods
 Policy 17 Rural homes
 Policy 22 Flood risk and water management 
8.3. South Lanarkshire Local Development Plan 2 (2021)
For the purposes of determining planning applications the Council will, therefore, also
assess proposals against the policies contained within the adopted South Lanarkshire
Local Development Plan 2 (SLLDP2).  In this regard, the application site and
associated proposals are affected by the following policies contained in the SLLDP2. 
SLLDP2 Volume 1 Policies
 Policy 2 Climate Change
 Policy 4 Green Belt and Rural Area
 Policy 5 Development Management and Placemaking 
SLLDP2 Volume 2 Policies
 Policy SDCC3 Sustainable Drainage Systems
 Policy SDCC7 Low Carbon Emissions from New Buildings
 Policy GBRA1 Rural Design and Development
 Policy GBRA8 Development of Gap Sites
 Policy DM15 Water Supply
 Policy DM16 Foul Drainage/Sewerage Provision  
59

Page 60

9. Guidance
9.1. None applicable. 
Assessment and Discussion
10.1. Principle of Development
Policy 17 of NPF4 and Policy 4 of the South Lanarkshire Local Development Plan 2
direct new housing to settlements unless specific rural exceptions apply.  For new
homes in the rural area without a demonstrated locational need, it must be shown that
the proposal involves the reuse of brownfield land where a return to a natural state
has not occurred and would not occur without intervention. 
10.2. The supporting information identifies the application site as brownfield land associated
with the former deer farming operation.  However, that association does not, in itself,
establish its status as brownfield land.  The structures associated with the former
operation have all been cleared, and their footprints have already been redeveloped
to accommodate seven dwellings.  The application site lies outwith those footprints,
and no evidence has been provided to demonstrate that it was previously occupied by
buildings or other structures.  Its former inclusion within the curtilage or yard of the
demolished buildings does not, in itself, justify further residential development. 
10.3. A septic tank associated with the demolished agricultural buildings is reported to
remain beneath the site.  Its retention following demolition does not provide sufficient
justification for two additional dwellings, particularly when the former building footprints
have already been redeveloped for housing.  The residential character of the group is
now established, with no remaining incompatible structures or land uses that would
justify a departure from the development plan.  Allowing the site to return to a natural
state would not significantly harm the amenity or character of the surrounding dwelling. 
10.4. The applicant has also referred to the site as a gap site; however, Policy GBRA8 of
SLLDP2 can only be applied once the principle of residential development in the rural
area is established. 
10.5. The proposal fails to meet the requirements for rural housing and is contrary to Policy
4 of SLLDP2 and Policy 17 of NPF4. 
10.6. Sustainability
Policies 1 and 2 of NPF4 and Policy 2 of SLLDP2 require development to minimise
climate impacts.  The proposed dwellings include solar panels and air source heat
pumps. 
10.7. Policy 3 of NPF4 requires development proposals to enhance the biodiversity value of
the site and proposals have been made in this regard. 
10.8. Policies 13 and 15 of NPF4 promote sustainable travel and access to daily services
through active travel networks and public transport.  The supporting statement argues
that these policies should be applied proportionately and that two dwellings would
generate only a marginal increase in travel demand. 
10.9. However, the limited scale of the proposal does not overcome the site’s poor
accessibility.  The site is remote from services and lacks safe, direct active travel
routes, making walking and cycling unrealistic options for everyday journeys.  The
development would therefore be heavily dependent on private cars.  While such
dependency may be accepted where there is a locational justification for the
development, no such justification has been demonstrated in this case.  The proposal
is therefore contrary to Policies 13 and 15 of National Planning Framework 4. 
60

Page 61

10.10. Layout, Siting and Design 
Policy 14 of NPF4 and Policies 5 and GBRA1 of SLLDP2 seek high-quality design that
responds to local character and avoids suburban forms of development in the rural
area.  The proposed dwellings replicate the house type, form, and materials used in
the seven recently constructed properties at Falconers Lane and Hawks Close.  Within
this specific cluster, that approach results in a consistent appearance and an
acceptable relationship with the existing built context.  However, the design is not
characteristic of the wider rural area and would not necessarily be appropriate on a
standalone site.  Its acceptability in this instance arises only from the presence of the
established group. 
10.11. The proposed layout and siting would not result in unacceptable levels of
overshadowing or overlooking.  The rear elevations are at least 7.2 metres from the
front garden of 2 Hawks Close and, given the single-storey design and proposed
boundary fencing, intervisibility would be limited.  The proposed use is compatible with
surrounding residential properties and noise is not expected to be significant. 
Construction impacts would be temporary and are not grounds for refusal. 
10.12. Technical Matters
Policy 22 of NPF4 and Policies DM15, DM16 and SDCC3 of SLLDP2 relate to water
management and drainage.  The site is not identified as being at flood risk, and private
foul and surface water drainage would be via the existing system serving Falconers
Lane and Hawks Close.  Permeable surfacing could be secured to limit run-off. 
10.13. Policy 5 of SLLDP2 requires development to provide suitable access and parking.  The
existing private access could serve five dwellings, which is below the requirement for
adoption.  Each plot proposes adequate parking and turning space. 
10.14. Conclusion 
In summary, the site does not constitute previously developed land and no locational
need for new housing in the rural area has been demonstrated as required by Policy
17 of NPF4.  The site also lacks sustainable access to services and facilities, resulting
in reliance on private vehicles.  The proposal is therefore contrary to Policy 4 of the
South Lanarkshire Local Development Plan 2 and Policies 13, 15 and 17 of National
Planning Framework 4. 
11. Recommendation and Reasons
11.1. The Committee is asked to agree the following recommendation:- 
Refuse Planning Permission for the following reasons:- 
01. The proposal would be contrary to Policy 4 – Green Belts and Rural Areas of the South
Lanarkshire Local Development Plan 2 as it is not supported by the Development Plan
in land use terms. 
02. The proposal would be contrary to Policy 17 – Rural homes of National Planning
Framework 4 as it does not meet any of the criteria allowing for housing in the rural
area. 
61

Page 62

03. The proposal would be contrary to Policy 13 – Sustainable transport of National
Planning Framework 4 as it would be dependent on unsustainable means of transport. 
04. The proposal would be contrary to Policy 15 – Local living and 20 minute
neighbourhoods as there is poor connectivity to daily needs by sustainable means. 
Kevin Carr
Executive Director (Community and Enterprise Resources) 
Date: 29 September 2026 
Background Papers
Further information relating to the application can be found online:- 
P/26/0918 | Erection of two dwellinghouses and associated works | Hawks Close Cleghorn
Lanark ML11 8NX 
Corporate Considerations
The report raises no impacts or risks in terms of equalities or financial implications.  Any
implications in terms of climate change, sustainability or the environment will have been
considered above in terms of the relevant national and local policies. 
Contact for Further Information
If you would like to inspect the background papers or want further information, please
contact:-
E-mail:  planning@southlanarkshire.gov.uk     
62

Page 63

63

Page 64

64

Page 65

Report
Agenda Item 
Report to: Planning Committee
Date of Meeting: 6 October 2026
Report by: Executive Director (Community and Enterprise
Resources)   
Reference no:  P/26/0922
Proposal:  Construction and Operation of Renewable Energy Development,
comprising up to 21 Wind Turbines with maximum blade tip height of
220m with a combined generating capacity greater than 50MW, a
Battery Energy Storage System of approximately 50MW and
associated infrastructure (Section 36 Consultation).
Site Address:  Ravengill Energy Park 
B797 from Abington A702 to Leadhills 
South Lanarkshire 
Applicant:  Ravengill Energy Park Limited
Agent:  Rambol UK Ltd
Ward:  03 Clydesdale East
Application Type:  Electricity notification Section 36 application
Advert Type:  None Required
Development Plan
Compliance: 
No
Departures:  N/A
Recommendation:  That the Scottish Government Energy Consents Unit is informed that,
for the reasons stated, South Lanarkshire Council object to the granting
of consent under Section 36 of the Electricity Act 1989 
Legal Agreement:  In the event that the application is granted the Scottish Government is
also advised that any approval issued in respect of this application
should be subject to the conclusion of a legal agreement(s) covering:-  
1. Community Contribution Payments 
Direction to
Scottish Ministers 
N/A  
8
65

Page 66

1. Reason for Report
1.1. This matter is being presented to the Committee as the Chief Planning Officer, in
consultation with the Committee Chair, considered that it raises significant levels of
concern or policy issues. 
2. Site Description
2.1. The site covers an area of approximately 2,555 ha and is located approximately 1 km
north of Leadhills and 1.5 km south of Abington. 
2.2. The site is located within the wider Southern Uplands area and consists of open upland
moorland (much of which is managed for grouse and sheep grazing), improved
grassland and semi-improved grassland, with areas of forestry located within the lower
lying valleys located predominantly to the east of the B797. 
2.3. The topography within the site is undulating with multiple named hills lying within the
boundary of the site, this general landform being typical of the wider Southern
Uplands. 
2.4. There are multiple watercourses and water bodies within the boundary of the site,
tributaries of the River Clyde, including Glengonnar Water in the north, Snar Water in
the west and Elvan Water in the south, with the River Clyde itself lying approximately
1 km to the east of the site at its closest point. 
2.5. The land within the immediate vicinity of the site is sparsely populated, with
settlements confined largely to the valleys.  The main settlements within the vicinity of
the site are the villages of Leadhills, Abington, Elvanfoot, Wanlockhead and
Crawfordjohn.  There are three individual properties within the site boundary. 
3. Description of Proposed Development
3.1. An application is made to the Scottish Government under Section 36 of the Electricity
Act 1989 for the construction and operation of a renewable energy development. 
3.2. The proposed development would comprise of the following:- 
 Up to 21 turbines with a maximum blade tip height of 220m
 Permanent foundations supporting each turbine and associated crane
hardstanding pads
 A temporary construction site access from the A74(M) to allow for the delivery of
abnormal indivisible loads required for turbine component delivery
 Two new junctions onto the B797 and two new junctions onto the C class road
between the B797 and Crawfordjohn
 New on-site access tracks with associated watercourse crossings
 Underground power cables
 On-site substation and control building
 Temporary construction compounds and laydown areas
 A BESS with appropriately 50 MW capacity, co-located with the on-site sub-
station
 Borrow pits
 Temporary on-site concrete batching plant 
3.3. The scale of the proposed development, in terms of its generating capacity, is such
that it needs to be consented through the Electricity Act, with the Scottish Government
acting as the Consenting Authority. 
3.4. The Council acts as a consultee and is not the Consenting Authority. 
66

Page 67

4. Relevant Planning History
4.1. P/25/0683 – There was a Section 36 Scoping Request (Ref. P/25/0683) submitted and
responded to relative to the Ravensgill Energy Park. 
5. Supporting Information 
5.1. The applicants have submitted supporting documents with the application as set out
below:- 
 Environmental Impact Assessment Report
 Community Benefits Statement 
6. Consultations
6.1. The Council is a consultee in the Section 36 application process and therefore
consultation by the Council is limited to Council services.  A summary of the wider
consultation responses received by the Scottish Government is also included below,
as these may be relevant to the view of the Council. 
6.2. Environmental Services (ES) – at the time of writing a response from ES has not been
received.  However, if the Council were minded to offer no objection to the proposed
development, the standard conditions used by ES would be applicable. 
Response:  Not applicable. 
6.3. Roads, Transportation and Fleet Services (Development Management) – at the time
of writing a response from Roads has not been received.  However, if the Council were
minded to offer no objection to the proposed development, the standard conditions
used by Roads would be applicable. 
Response:  Noted. 
6.4. West of Scotland Archaeology Service (WoSAS) – at the time of writing a response
from WoSAS has not been received.  However, if the Council were minded to offer no
objection to the proposed development, the standard conditions used by WoSAS
would be applicable. 
Response:  Noted. 
6.5. The consultations undertaken by the Energy Consents Unit (ECU) are listed and
summarised below:- 
Scottish Water - no objection to the proposed development. 
Edinburgh Airport - no objection to the proposed development. 
Health and Safety Executive (HSE) - no objection to the proposed development. 
Ministry of Defence (MoD) – they object to the proposal based upon impact on the
Eskdalemuir facility and in terms of the impact on low flying routes in the area. 
National Air Traffic Services (NATS) – they have submitted a holding objection based
upon potential impact on radar facilities. 
Glasgow Prestwick Airport - no objection to the proposed development. 
British Telecom - no objection to the proposed development.  
67

Page 68

7. Representations
7.1. The Energy Consents Unit are responsible for carrying out statutory neighbour
notification and publicity on the application.  Any representations are sent directly to
the ECU for consideration in their assessment of the Section 36 application. 
8. Development Plan
8.1. The application has been submitted to the Scottish Government under Section 36 of
the Electricity Act 1989.  A planning application is required to be determined in
accordance with the Development Plan, unless material considerations indicate
otherwise.  However, for Section 36 applications, the Development Plan has the status
of a material consideration which is required to be considered by the Scottish Ministers
in the determination of the application. 
8.2. The Council has been consulted in its role as the Planning Authority for the area in
which the application site is located and therefore the Council’s response to the
consultation request is required to be informed by an assessment against the
provisions of the Development Plan. 
8.3. Other material considerations pertinent to the application may also be considered.  The
Development Plan comprises the South Lanarkshire Local Development Plan 2
adopted in April 2021 and National Planning Framework 4 adopted by the Scottish
Government in February 2023.
8.4. National Planning Framework 4
National Planning Framework 4 (NPF4) is Scotland’s national spatial strategy and
supports the planning and delivery of sustainable places, liveable places and
productive places. 
National Planning Framework 4 Policies 
 Policy 1 - Tackling the climate and nature crises
 Policy 2 - Climate mitigation and adaptation
 Policy 3 - Biodiversity
 Policy 4 - Natural places
 Policy 5 - Soils
 Policy 6 - Forestry, woodland and trees
 Policy 7 - Historic assets and places
 Policy 11 - Energy
 Policy 29 - Rural development 
8.5. South Lanarkshire Local Development Plan 2 (2021)
The application site and associated proposals are affected by the following policies
contained in the South Lanarkshire Local Development Plan 2 (SLLDP2):- 
SLLDP2 Volume 1 Policies
 Policy 1 - Spatial Strategy
 Policy 2 - Climate Change
 Policy 4 - Green Belt and Rural Area
 Policy 5 - Development Management and Placemaking
 Policy 14 - Natural and Historic Environment
 Policy 15 - Travel and Transport
 Policy 16 - Water Environment and Flooding
 Policy 18 - Renewable Energy  
68

Page 69

9. Guidance
9.1. The relevant guidance documents are:- 
 South Lanarkshire Council (SLC) Supporting Planning Guidance Renewable
Energy (January 2021)
 Landscape Capacity Study for Wind Energy (2019 as amended) 
10. Assessment and Discussion
10.1. Principle of Development 
National Planning Policy Framework 4 (NPF4) sets out the long-term vision for the
development of Scotland through the National Spatial Strategy.  Amongst other things,
NPF4 aims to meet Scotland’s climate ambition which will require a rapid
transformation across all sectors of the economy and society.  The Scottish
Government’s Onshore Wind Policy Statement sets a target for installed onshore wind
generation of 20GW by 2030. 
10.2. NPF4 Policy 1 – Tackling the Climate and Nature Crises states that there is a need to
encourage, promote and facilitate development that addresses the global climate
emergency and nature crisis, whilst Policy 2 – Climate Change and Adaptation seeks
to encourage, promote and facilitate development that minimises emissions and
adapts to the current and future impacts of climate change. 
10.3. In this case, the proposed development comprises the construction and operation of
a wind farm, along with an associated battery energy storage system (BESS).  It would
assist in terms of the generation of renewable energy to enable the decarbonisation
of Scotland’s energy supply and meet Net Zero targets. 
10.4. It is considered that the proposed development is directly linked to renewable energy
generation and supports the general principles which are set out in NPF4 Policies 1
and 2, in addition to Policy 1 – Spatial Strategy and Policy 2 – Climate Change of the
SLLDP2. 
10.5. Policy 11 – Energy of NPF4 as a general principle encourages and promotes all forms
of renewable energy development.  This includes energy generation through wind farm
development, solar arrays and energy storage (such as battery storage).  The policy
makes clear that development proposals for all forms of renewable, low carbon and
zero emissions will be supported.   
10.6. The policy also sets out a range of criteria that proposals should be assessed against
to ensure the impact of the proposed development and any required mitigation is
properly addressed.  In terms of the matters that are within the remit of the Council as
a consultee on the application, these include:- 
 impacts on communities and individual dwellings, including, residential amenity,
visual impact, noise and shadow flicker; 
 significant landscape and visual impacts;
 public access, including impact on long distance walking and cycling routes and
scenic routes; 
 impacts on road traffic and on adjacent trunk roads, including during construction;
and 
 cumulative impacts.  
69

Page 70

10.7. In terms of the adopted South Lanarkshire Local Development Plan 2, Policy 18:
Renewable Energy states that applications for renewable energy infrastructure
developments will be supported subject to an assessment against the relevant criteria
and requirements set out in the Assessment Checklist for Renewable Energy
Proposals contained within SLLDP2 Volume 2.  SLLDP2 Volume 2 Policy RE1
Renewable Energy supports Policy 18 and states that as well as the Checklist,
renewable energy proposals should also take into account the considerations, criteria
and guidance contained within the Supporting Planning Guidance (SPG) on
Renewable Energy, Landscape Capacity Study for Wind Energy (2019 as amended)
and other relevant policies in SLLDP2. 
10.8. Together, NPF4 Policy 11, SLLDP2 Policy 18 and the associated SPG set out the
criteria that are required to be addressed when determining applications of this scale
and nature.  The Landscape and Visual Assessment (LVIA) which forms part of the
Environmental Impact Assessment (EIA) is a key document in assessing the
proposals, with it being considered that the landscape impact of the proposed
development is the principle determining issue from the Council’s perspective. 
10.9. Site History and Material Considerations
In considering the landscape impact of the proposed development, cognisance must
be had to the decision which was taken in respect of the proposed development of the
Harryburn Wind Farm. 
10.10. The proposed Harryburn Wind Farm was a Section 36 development which was
determined (in the first instance) by the Electricity Consents Unit (ECU reference
ECU00005277).  The decision taken by the ECU was to refuse the application.  This
decision was subsequently appealed by the applicant (appeal reference WIN-380-1)
and was the subject of a formal Inquiry. 
10.11. Having considered all the evidence presented to them, it was the recommendation of
the Reporter that the proposed application be refused, citing amongst other things,
adverse landscape impacts. 
10.12. This recommendation was accepted by the Scottish Ministers and by letter dated 27
September 2019. 
10.13. The proposed Harryburn Wind Farm comprised a total of 16 wind turbines to a
maximum height of 149.9m with associated supporting infrastructure.  The relevance
of the Harryburn proposals to the current application is that 13 of the 21 turbines
(turbine numbers 9 – 21) are located on the same area of land covered by the
proposed Harryburn development. 
10.14. Whilst the terms of the development plan have changed since the decision was taken
on the Harryburn application, SSP3 having been replaced by NPF4 and the SLLDP2
having replaced the former local plan, the nature of the relevant policy considerations,
as outlined above, has not changed. 
10.15. Landscape and Visual Impact
The changes to the details of the development plan have not changed the approach
which requires to be followed in terms of assessing the potential landscape impact of
the proposed development.  
70

Page 71

10.16. Those considerations concluded that the Harryburn development would give rise to
adverse landscape impacts and are equally relevant to the Ravengill development,
with it being of importance to note that it is considered that these adverse landscape
impacts will be exacerbated by two factors. 
10.17. Firstly, the turbines proposed as part of the Ravengill proposal would stand some 70m
taller in height to blade tip than those proposed as part of the Harryburn development
and secondly, turbine numbers 1 – 8 of the proposed development would extend the
development footprint significantly further to the west (to the west of the B797). 
10.18. These two factors are considered likely to increase the extent of the visibility and
overall impact of the Ravengill proposals, when compared to those associated with
the Harryburn development. 
10.19. Given that the Harryburn development was found to give rise to, amongst other things,
adverse landscape impacts, the only reasonable conclusion that can be drawn is that
the Ravengill development would give rise to adverse landscape impacts which would
be of greater significance than those associated with the Harryburn scheme 
10.20. Natural Environment
NPF4 Policy 3 – Biodiversity, seeks to protect biodiversity, reverse any biodiversity
loss, deliver positive effects for development and strengthen nature networks.  NPF4
Policy 4 – Natural Places seeks to protect, restore and enhance natural assets, making
best use of nature-based solutions.  NPF4 Policy 5 – Soils seeks to protect carbon-
rich soils, restore degraded peatlands and minimise disturbance to soils because of
development.  These various policy considerations are echoed within Policy 14 –
Natural and Historic Environment of the SLLDP2. 
10.21. The application is supported by an Environmental Impact Assessment (EIA), which
includes detailed survey work in relation to landscape, ecology, ornithology, hydrology,
geology and other relevant environmental considerations.  This information has not
been the subject of any objection by those parties consulted by the ECU. 
10.22. Consequently, it is considered that the proposals comply with the relevant criteria of
the above noted policies, subject to the identified mitigation measures being fully
implemented on site as part of the proposed development.  On this basis, the
application is considered to comply with the relevant provisions of Policies 3, 4 and 5
of NPF4 and Policy 14 of the SLLDP2. 
10.23. Policy 6 – Forestry, woodland and trees of NPF4 seeks to identify and protect existing
woodland and the potential for its enhancement or expansion to avoid habitat
fragmentation and improve ecological connectivity, helping to support and expand
nature networks.  Full details of the implementation of the proposals would require to
be agreed between the applicants and the Scottish Government. 
10.24. Subject to these details being agreed it is considered that the proposals do not raise
any significant concerns in respect of the provisions of Policy 6. 
10.25. Historic Environment 
Policy 7 – Historic assets and places of NPF4 seeks to protect and enhance historic
environment assets and places and to enable positive change as a catalyst for
regeneration.  Similar policy regarding the protection of the historic environment is
contained within Policy 14 of SLLDP2.  
71

Page 72

10.26. Flood Risk
NPF4 Policy 22 – Flood Risk Assessment seeks to strengthen resilience to flood risk
by promoting avoidance as a first principle and reducing the vulnerability of existing
and future development to flooding.  Similar policy is provided in SLLDP2 Policy 16 -
Water Environment and Flooding.  It is considered that these matters could be covered
by suitable planning conditions in the event of the application being approved and on
balance, the proposals are considered to be compliant with the provisions of Policy 22
of NPF4 and Policy 16 of SLLDP2. 
10.27. Rural Environment
NPF4 Policy 29 – Rural development seeks to encourage rural economic activity,
innovation and diversification whilst ensuring that the distinctive character of the rural
area and the service function of small towns, natural assets and cultural heritage are
safeguarded and enhanced.  Similar policy is provided in SLLDP2 Policy 4 – Green
Belt and Rural Area.  Given the concerns which have been highlighted above in
relation to the landscape and visual impact of the proposed development, it is
considered that the proposed development does not represent an acceptable form of
development at this locale.  The proposals are therefore considered to be in conflict
with the provisions of Policy 29 of NPF4 and Policy 4 of SLLDP2. 
10.28. Aviation
In terms of aviation and defence interests, the MoD has objected to the application on
the grounds of the impact on air traffic safety, low flying by MoD aircraft and the effect
on the Eskdalemuir seismology recording facility.  There is currently no seismic noise
capacity available which would have an unacceptable impact on the operation and
capability of the facility.  Based on the information available at present, there appears
to be no immediate prospect of the concerns which have been raised by the MoD
being overcome.  As a result, the proposal is contrary to NPF4 Policy 11 and Policy
18 in SLLDP2. 
11. Conclusion
11.1. The proposals have demonstrated that they address most of the impacts listed in
NPF4 and the assessment criteria in SLLDP2.  However, objections have been
received from several statutory consultees.  The applicant has been working to
progress these matters although at present they remain unresolved. 
11.2. In conclusion, it is considered that the proposed development does not fully comply
with the relevant policies of both the adopted National Planning Framework 4 and the
adopted South Lanarkshire Local Development Plan 2 in terms of policy relating to
landscape and visual impact, air traffic safety and the impact on Eskdalemuir.  It is
therefore recommended that the Scottish Government be notified that the Council
objects to the application for the reasons stated below. 
12. Recommendation and Reasons
12.1. The Committee is asked to agree the following recommendation:- 
01. That the Scottish Government Energy Consents Unit is informed that South
Lanarkshire Council objects to the granting of consent under Section 36 of the
Electricity Act 1989 
The Scottish Government is also advised that any approval should be subject to the
conclusion of a legal agreement(s) covering:- 
1. Community Contribution Payments  
72

Page 73

Reasons for objection 
1. The proposals are considered to have an adverse impact in both landscape
and visual terms and, as such, are considered to be contrary to Policy 18 of the
adopted South Lanarkshire Local Development Plan 2. 
2. The proposals are contrary to Policies 3 and 11 of National Planning
Framework 4 in that the applicant has failed to demonstrate that the impacts on
aviation and defence interests have not been addressed. 
3. The proposals are contrary to Policy 18 of the adopted South Lanarkshire Local
Development Plan 2 and the South Lanarkshire Council Supporting Planning
Guidance on Renewable Energy due to the adverse impact on the aviation and
defence interests. 
4. The proposals are contrary to Policy 29 of National Planning Framework 4 as
the proposals represent an unacceptable form of development which would
give rise to adverse impacts on the surrounding rural area. 
13. Next Steps
13.1. If members agree with this recommendation, Scottish Ministers (via the Energy
Consents Unit) will be advised of the Council’s objection to the proposed development.   
13.2. Where a planning authority objects to an application, a reporter will be appointed to
carry out an examination unless that objection is withdrawn or cannot be resolved by
conditions or modifications.  In any case where no objection is made by a planning
authority which may require an inquiry to be held, the Scottish Ministers will give
consideration as to whether it would be appropriate to cause a public inquiry to be
held. 
Kevin Carr
Executive Director (Community and Enterprise Resources) 
Date:  29 September 2026 
Background Papers
Further information relating to the application can be found online: 
P/26/0922 | Section 36 Consultation relating to the erection of up to 21 turbines with a height
up to 220m and construction of BESS facility with capacity of approximatelely 50MW. |
Ravengill Energy Park B797 From Abington A702 To Leadhills Leadhills Biggar 
Corporate Considerations
The report raises no impacts or risks in terms of equalities or financial implications.  Any
implications in terms of climate change, sustainability or the environment will have been
considered above in terms of the relevant national and local policies. 
Contact for Further Information
If you would like to inspect the background papers or want further information, please
contact:-
E-mail:  planning@southlanarkshire.gov.uk 
73

Page 74

74