Agenda Document Pack - Financial Resources Scrutiny Forum - 27/08/2026

South Lanarkshire Council · 27 August 2026
Back to Financial Resources Scrutiny Forum — 27 August 2026 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

Council Offices, Almada Street        
Hamilton, ML3 0AA 
Wednesday, 19 August 2026 
Dear Councillor 
Financial Resources Scrutiny Forum 
The Members listed below are requested to attend a meeting of the above Forum to be held
as follows:- 
Date:  Thursday, 27 August 2026
Time:  14:00
Venue: Hybrid - Committee Room 1, Council Offices, Almada Street, Hamilton,
ML3 0AA 
The business to be considered at the meeting is listed overleaf. 
Yours sincerely 
Paul Manning
Chief Executive 
Members
Grant Ferguson (Chair), Julia Marrs (Depute Chair), Mathew Buchanan, Colin Dewar, Monique
Equi, Allan Falconer, Ross Gowland, Richard Lockhart, Fiona McDermott, Carol Nugent 
Substitutes
Archie Buchanan, Elise Frame 
1

Page 2

BUSINESS 
1 Declaration of Interests   
2 Minutes of Previous Meeting
Minutes of the meeting of the Financial Resources Scrutiny Forum held on 30
April 2026 submitted for approval as a correct record.  (Copy attached) 
3 - 6 
Item(s) for Monitoring 
3 Capital Budget Monitoring 2025/2026 - General Fund Capital Programme
Report dated 10 August 2026 by the Executive Director (Finance and Corporate
Resources).  (Copy attached) 
7 - 28 
4 Capital Budget Monitoring 2025/2026 - Housing Capital  Programme
Report dated 10 August 2026 by the Executive Director (Finance and Corporate
Resources).  (Copy attached) 
29 - 34 
5 Capital Budget Monitoring 2026/2027 - General Fund Capital Programme
Report dated 10 August 2026 by the Executive Director (Finance and Corporate
Resources).  (Copy attached) 
35 - 62 
6 Capital Budget Monitoring 2026/2027 - Housing Capital Programme
Report dated 10 August 2026 by the Executive Director (Finance and Corporate
Resources).  (Copy attached) 
63 - 68 
7 Revenue Budget Year-End 2025/2026
Report dated 10 August 2026 by the Executive Director (Finance and Corporate
Resources).  (Copy attached) 
69 - 84 
8 Revenue Budget 2025/2026 - Detailed Resource Analysis
Report dated 10 August 2026 by the Executive Director (Finance and Corporate
Resources).  (Copy attached) 
85 - 166 
9 Revenue Budget Monitoring 2026/2027
Report dated 10 August 2026 by the Executive Director (Finance and Corporate
Resources).  (Copy attached) 
167 - 172 
10  Revenue Budget 2026/2027 - Detailed Resource Analysis
Report dated 10 August 2026 by the Executive Director (Finance and Corporate
Resources).  (Copy attached) 
173 - 226 
Urgent Business 
11  Urgent Business
Any other items of business which the Chair decides are urgent. 
For further information, please contact:-
Clerk Name: Laura Cunningham
Clerk Telephone: 07385370044
Clerk Email: Laura.Cunningham2@southlanarkshire.gov.uk 
2

Page 3

FINANCIAL RESOURCES SCRUTINY FORUM 
Minutes of meeting held via Confero and in the Council Chamber, Council Offices, Almada Street,
Hamilton on 30 April 2026 
Chair:
Councillor Grant Ferguson 
Councillors Present:
Councillor Colin Dewar, Councillor Julia Marrs (Depute), Councillor Carol Nugent 
Councillors' Apologies:
Councillor Mathew Buchanan, Councillor Monique Equi, Councillor Ross Gowland, Councillor Gavin
Keatt, Councillor Richard Lockhart 
Attending:
Finance and Corporate Resources
G Booth, Finance Manager (Strategy); S Jessup, Administration Assistant; C Lyon, Administration
Officer; L O’Hagan, Head of Finance (Strategy)
Housing and Technical Resources
A Roxburgh, Project Manager 
1 Declaration of Interests 
No interests were declared. 
2 Minutes of Previous Meeting 
The minutes of the meeting of the Financial Resources Scrutiny Forum held on 12 March 2026
were submitted for approval as a correct record. 
The Forum decided: that the minutes be approved as a correct record. 
3 Capital Budget Monitoring 2025/2026 – General Fund Capital Programme 
A report dated 23 March 2026 by the Executive Director (Finance and Corporate Resources)
was submitted on the position of the General Fund Capital Programme 2025/2026 for the period
1 April to 20 February 2026. 
The revised General Services Capital Programme for 2025/2026 totalled £67.712 million, as
detailed in Appendix A to the report.  The revised programme consisted of the base budget plus
carry forward projects and adjustments which had been agreed by the Executive Committee up
to and including its meeting on 3 December 2025.  There were no adjustments to the
programme presented to the Executive Committee on 4 February and 4 March 2026. 
The programme spend and funding for the General Fund was summarised in Appendix C to the
report and also showed a forecast for the financial year of £65.962 million, an underspend of
£1.750 million. 
As noted previously, the forecast for this financial year reflected anticipated spend on 2 projects,
East Kilbride Town Centre (£0.800 million), where demolition costs were lower than anticipated,
and Hamilton Junctions (£0.950 million), as works planned for Wellhall Road had been
reprogrammed to begin in spring 2026.
2
3

Page 4

Actual spend to 20 February 2026 was £42.034 million and actual funding received at 20
February 2026 was £43.620 million. 
The physical progress achieved with the General Fund Capital Programme 2025/2026 at 20
February 2026 was detailed in appendices D to F of the report. 
The Forum decided: that the physical and financial progress of the 2025/2026
General Fund Capital Programme be noted. 
[Reference: Minutes of 12 March 2026 (Paragraph 3a) and Minutes of the Executive Committee
of 1 April 2026 (Paragraph 4)] 
4 Capital Budget Monitoring 2025/2026 – Housing Capital Programme 
A report dated 23 March 2026 by the Executive Director (Finance and Corporate Resources)
was submitted on the position of the Housing Capital Programme 2025/2026 at 20 February
2026. 
The revised Housing Capital Programme for 2025/2026 totalled £87.740 million.  Programmed
funding for the year also totalled £87.740 million.  The budget, along with a detailed breakdown
of the funding sources, was included in Appendix A to the report. 
As previously reported, the predicted spend position for the Housing and Technical Resources’
Capital Programme for 2025/2026 was £85.940 million, an underspend of £1.8 million. 
Spend to 20 February 2026 totalled £63.563 million and actual funding received was £63.563
million. 
The physical progress achieved with the Housing Capital Programme 2025/2026 at 20 February
2026 was detailed in Appendix B to the report. 
The Forum decided: that the physical and financial progress of the Housing
Capital Programme be noted. 
[Reference: Minutes of 12 March 2026 (Paragraph 3b) and Minutes of the Executive Committee
of 1 April 2026 (Paragraph 4)] 
5 Revenue Budget Monitoring 2025/2026 
A report dated 23 March 2026 by the Executive Director (Finance and Corporate Resources)
was submitted on the position of the Council’s General Fund Revenue Account and Housing
Revenue Account for the period 1 April 2025 to 20 February 2026, and a projection for the year
to 31 March 2026. 
The report and associated appendices:- 
 summarised the 2025/2026 Probable Outturn position for the Council’s General Fund
Revenue Account to 31 March 2026, following agreed transfers to reserves, which showed
a breakeven position
 provided details of the position on the General Fund Account and the Housing Revenue
Account respectively for the period 1 April 2025 to 20 February 2026
 advised that the Council was due to receive a share of the reserves that had been
accumulated by Clydeplan, following its termination on 31 March 2025
 provided the Housing Revenue Account position
4

Page 5

As previously noted, the probable outturn position for the General Fund represented an
underspend of £3.579 million.  This underspend was after the previously identified/approved
transfer to reserves totalling £38.108 million and the proposed transfers to reserves totalling
£16.339 million. 
At 20 February 2026, the projected outturn position on the Housing Revenue Account was a
breakeven position, as detailed in Appendix 3 to the report.  This position included transfers
from reserves of £0.287 million which had been greater than budgeted. 
The Forum decided: 
(1) that the Council’s breakeven Probable Outturn position after transfers to reserves, as
detailed in section 4 of the report, be noted; 
(2) that the current forecast on the General Fund Revenue Account for 2025/2026, as detailed
in section 5.1 of the report, and the actual spend as at 20 February 2026, as detailed in
appendices 1 and 2 of the report, be noted; and 
(3) that the projected breakeven position on the Housing Revenue Account for 2025/2026,
and the actual spend as at 20 February 2026, as detailed in section 6 and Appendix 3 of
the report, be noted. 
[Reference: Minutes of 12 March 2026 (Paragraph 4) and Minutes of the Executive Committee
of 1 April 2026 (Paragraph 3)] 
6 Revenue Budget Monitoring 2025/2026 
A report dated 13 April 2026 by the Executive Director (Finance and Corporate Resources) was
submitted comparing actual expenditure against budgeted expenditure for the period 1 April
2025 to 20 February 2026. 
Appendices A to F to the report provided the following information for each Resource and the
Housing Revenue Account:- 
 an Executive Summary showing the top level position for each of the Services within the
Resource and the Housing Revenue Account as at 20 February 2026
 details of the most significant variances within Resources and the Housing Revenue
Account across subjective headings and across Services as at 20 February 2026
 a line by line trend analysis of the total Resources’ expenditure and income across
subjective headings as at 20 February 2026 
The Forum decided: that the position as at 20 February 2026 be noted. 
[Reference: Minutes of 12 March 2026 (Paragraph 5)] 
7 Urgent Business 
There were no items of urgent business. 
5

Page 6

6

Page 7

Report
Agenda Item 
Report to: Financial Resources Scrutiny Forum
Date of Meeting: 27 August 2026
Report by: Executive Director (Finance and Corporate Resources)  
Subject: Capital Budget Monitoring 2025/2026 - General Fund
Capital Programme 
1. Purpose of Report
1.1. The purpose of the report is to:
[purpose]
 update members of the Financial Resources Scrutiny Forum on the final outturn
position of the Council’s General Fund Capital Programme for the period covering
1 April 2025 to 31 March 2026.
[1purpose]
2. Recommendation(s)
2.1. The Forum is asked to approve the following recommendation:
[recs]
(1) that the final outturn position on the 2025/2026 General Fund Capital
Programme be noted. 
[1recs]
3. Background
3.1. The Capital reports attached provide detail on the position as at 31 March 2026 from
a financial perspective. 
3.2. Appendix A shows the financial position of the General Fund Capital Programme. 
Any physical progress update for projects carried forward into financial year
2026/2027 will be picked up as part of the new year monitoring report. 
4. General Fund Capital Programme 2025/2026
4.1. 2025/2026 Budget:  The final agreed programme for the General Fund in 2025/2026
was £67.712 million. 
4.2. 2025/2026 Year End Position:  Appendix A shows the total expenditure of £57.570
million on the General Fund Capital Programme for financial year 2025/2026.  This is
compared to the budget of £67.712 million and results in an underspend of £10.142
million.  This underspend relates to projects within Community and Enterprise
Resources (£8.401m), Education Resources (£0.966m), Housing and Technical
Resources (£1.014m) and Finance and Corporate Resources (£0.048m), which are
partly offset by a funded overspend in Social Work Resources of £0.287m. 
4.3. The final spend position of £57.570 million results in approximately 96% of the original
capital budget approved at the start of this financial year being spent (£60.216m).   
4.4. This underspend reflects the profile of spend across a number of projects at the end
of the financial year.  The reasons for the revised profile of spend can be categorised
3
7

Page 8

as weather related delays / programme changes, re-tendering of projects required,
and delays with external consultants and contractors progressing planned works. 
4.5. Overall, the programme net underspend results in budget required in 2026/2027
rather than 2025/2026.  The main projects responsible for the overall programme
underspend are detailed in Appendix B.  This appendix provides a list of the
continuing projects into 2026/2027, along with their estimated completion dates. 
5.      Year End and Accounting Adjustments
5.1. Accounting Regulations mean that adjustments are required to report spend correctly
as either Capital or Revenue for the purposes of publishing our Annual Accounts.  This
includes where spend from the Capital Programme is on assets that are not owned by
the Council (for example Shawfield Industrial Estate spend) or where spend must be
classed as Revenue due to the nature of the spend.  This adjustment has no physical
impact on projects – it is an accounting entry only.   
5.2. From reviewing the Council’s Revenue and Capital spend, £8.786 million of capital
spend is required to be recorded as Revenue spend.  These transfers mean that for
the purpose of publishing our Annual Accounts only, there is capital spend of
£48.784 million.  The funding sources for this spend are detailed in Appendix A and
have also been transferred to the Revenue account for the purposes of the
Accounts. 
5.3. Carry Forward to 2026/2027:  As noted in 4.2, the year-end underspend is £10.142
million.  This will carry forward into financial year 2026/2027. 
5.4. The overall base programme for 2026/2027 including this carry forward of £10.142
million is included in a separate report to this Committee.  This separate report reviews
the programme for the coming year detailing the overall level of spend achievable. 
5.5. Funding: Funding available to support the programme in 2025/2026 is detailed in
Appendix A (Page 2). 
6. Employee Implications
6.1. There are no employee implications as a result of this report. 
7. Financial Implications
7.1. The financial implications are included in section 4 of this report. 
8. Climate Change, Sustainability and Environmental Implications
8.1. There are no implications for climate change, sustainability or the environment in
terms of the information contained in this report. 
9. Risk and Other Implications
9.1. The main risk associated with the Council’s Capital Programme is an overspend.  The
risk has been assessed as low given the detailed project management plans prepared
and monitored for each project.  The risk of overspend is managed through four weekly
Investment management meetings. 
10 Integrated Impact Assessment and Consultation Requirements
10.1. This report does not introduce a new policy, function or strategy or recommend a
change to existing policy, function or strategy and therefore no impact assessment is
required. 
8

Page 9

10.2. There was also no requirement to undertake any consultation in terms of the
information contained in this report. 
Jackie Taylor
Executive Director of Finance (Strategy) 
10 August 2026 
Link(s) to Council Values/Priorities/Outcomes
 Accountable, effective, efficient and transparent 
Previous References
 Executive Committee, 24 June 2026 
List of Background Papers
 Capital Ledger prints to 31 March 2026 
Contact for Further Information
If you would like to inspect the background papers or want further information, please contact:
Graham Booth, Finance Manager (Strategy)
Ext:  2699 (Tel:  01698 452699)
E-mail:  graham.booth@southlanarkshire.gov.uk 
9

Page 10

APPENDIX A       
(Page 1) 
SOUTH LANARKSHIRE COUNCIL        
CAPITAL EXPENDITURE 2025/2026       
GENERAL FUND PROGRAMME 
FOR PERIOD 1 APRIL 2025 TO 31 MARCH 2026 
Resource Name 
Annual
Budget
£000 
2023/24
C/F
£000
Previous
Slippage
/Adjs
£000
Total
Original
Budget
£000 
Proposed
Adjs
£000 
Proposed
Slippage
£000 
Total
Budget
£000 
Actual
£000 
Variance
£000 
Community & Enterprise 
Facs, Waste &
Grounds
1,893 978 253 3,124 478 (941) 2,661 1,622 1,039 
Enterprise &  
Sustainable Dev
32,674 7,271 (15,883) 24,062 8,630 (3,404) 29,287 24,252 5,035 
Roads, Transport
& Fleet
14,655 2,820 3,014 20,489 2,722 0 23,211 20,885 2,326 
Resource 
Total
49,222 11,069 (12,616) 47,675 11,830 (4,345) 55,159 46,759 8,400 
Education
Growth /
Accommodation
Pressures
1,603 709 1,370 3,682 566 (1,063) 3,185 2,319 866 
ICT
Developments
1,300 46 0 1,346 0 0 1,346 1,327 19 
Free School
Meals
0 473 3 476 0 0 476 395 81 
Resource 
Total
2,903 1,228 1,373 5,504 566 (1,063) 5,007 4,041 966 
Finance & Corporate
IT Services 300 245 0 545 150 (50) 645 597 48 
Resource 
Total  300  245  0  545  150  (50)  645  597  48 
Housing & Technical
Office Accom 6,000 1,930 180 8,110 (4,258) 0 3,852 3,068 784 
Private Housing
Scheme of
Assistance
1,000 0 0 1,000 (1,000) 0 0 0 0 
Other Housing 645 677 (304) 1,018 1,694 0 2,712 2,481 231 
Resource 
Total
7,156 2,607 (124) 10,128 (3,564) 0 6,564 5,549 1,015 
Social Work
Alarms / SWIS
Plus
146 31 160 337 0 0 337 624 (287) 
Resource Total  146    31  160  337  0  0  337  624  (287) 
Overall Total 60.216 15,180 (11,207) 64,189 8,982 (5,459) 67,712 57,570  10,142 
10

Page 11

APPENDIX A                   
(Page 2) 
SOUTH LANARKSHIRE COUNCIL       
CAPITAL EXPENDITURE 2025/2026       
GENERAL FUND PROGRAMME 
FOR PERIOD 1 APRIL 2025 TO 31 MARCH 2026 
Expenditure
2025/2026
Revised
Budget
2025/2026
Actual to
31/03/26  
£m £m   
General Fund Programme (from Appendix A Page 1) 67.712 57.570
Accounting Adjustments (Sections 5.1 and 5.2):     
Less:  Transfers to Revenue  (8.786) (8.786)   
Add:  Year End Transfers to Capital 0 0   
2024/2025 Outturn Position (Accounting Basis only) 58.926 48.784   
Income 
2025/2026
Actual to
31/03/26  
£m
Prudential Borrowing  10.288
Developer Contributions  3.534
Partners (including Levelling Up Fund, Cycling Scotland and
Transport Scotland) 
2.826
Scottish Government:   
- Capital Grant  28.115 
- Road Safety Improvement  0.698 
- Place Based Investment Programme  0.589
Capital Receipts  0.700
Specific Reserves  0.992
Revenue Contribution  1.042   
TOTAL FUNDING  48.784  
11

Page 12

APPENDIX B
SOUTH LANARKSHIRE COUNCIL      
CAPITAL EXPENDITURE 2025/2026       
GENERAL FUND PROGRAMME 
FOR PERIOD 1 APRIL 2025 TO 31 MARCH 2026 
Projects with budget from 2025/2026 
which will carry forward into 2026/2027
Project Name Project Type Completion Date
Community and Enterprise Resources   
East Kilbride Town Centre Regeneration Throughout 2026/27
and beyond
Hamilton Junctions Improvement Infrastructure Throughout 2026/27
and beyond
Calderglen Pump Track Infrastructure July 2026
Clyde Walkway Infrastructure Throughout 2026/27
SLC Industrial Infrastructure – Energy Efficiency
(Cathcart Road) 
Regeneration September 2026
Shawfield Remediation and Development  Regeneration Throughout 2026/27
and beyond
Leisure and Culture Transformation Fund Infrastructure Throughout 2026/27
Roads Investment Programme  Infrastructure Throughout 2026/27
and beyond
Active Travel Infrastructure Infrastructure Throughout 2026/27
and beyond
Safe Routes Infrastructure Throughout 2026/27
and beyond
Larkhall Leisure Centre Infrastructure Throughout 2026/27
and beyond
Play Parks Infrastructure Throughout 2026/27
and beyond   
Education Resources  
Secondary Schools Refurbishment Throughout 2026/27
and beyond   
Housing and Technical Resources   
Prioritised Urgent Investment Refurbishment Throughout 2026/27
Lifecycle Replacement Schools Refurbishment Throughout 2026/27
Fire Alarm System Upgrade Refurbishment Throughout 2026/27 
12

Page 13

Appendix C
(Page 1)
GENERAL FUND CAPITAL PROGRAMME 2025/26 
BUILD EXECUTIVE SUMMARY 
PERIOD ENDED 31 MARCH 2026 (PERIOD 14)
Expenditure Periods 
1 2 3 4 5 6 7 8 9 10 11 12 13 14
Programme Status               
Projects Complete  - 5 8 11 24 35 40 48 56 73 78 100 106 113
Projects on Programme  - 124 172 170 166 159 156 149 145 130 125 107 102 95
Projects Behind
Programme 
- 1 0 1 3 1 1 0 0 0 0 0 0 0
Projects Altered Brief/
Programme 
- 1 3 3 2 5 4 3 4 2 3 1 0 0
Projects Held  - 12 10 10 7 8 8 9 8 8 7 7 7 7 
- 143 193 195 202 208 209 209 213 213 213 215 215 215               
Project Status               
Design Feasibility  - 79 126 126 112 113 111 73 70 60 56 51 47 46
Sketch Design  - 3 2 1 1 1 1 1 1 1 1 1 1 1
Detailed Design  - 1 1 2 2 3 2 1 1 1 1 1 1 1
Production Information  - 4 5 5 8 8 8 10 10 9 7 6 4 2
Tendering  - 36 36 37 35 32 31 25 26 26 24 21 16 17
On Site  - 15 15 13 20 16 16 51 49 43 46 35 40 35
Complete  - 5 8 11 24 35 40 48 56 73 78 100 106 113 
- 143 193 195 202 208 209 209 213 213 213 215 215 215 
13

Page 14

Appendix C
(Page 2)
General Services Capital Programme 2025/26 
Build Variance Explanations 
Project Name Status Variance Explanation
- - - 
14

Page 15

Appendix D
(Page 1) 
GENERAL FUND CAPITAL PROGRAMME 2025/26       
NON-BUILD EXECUTIVE SUMMARY                  
PERIOD ENDED 31 MARCH 2026 (PERIOD 14)   
Expenditure Periods 
1 2 3 4 5 6 7 8 9 10 11 12 13 14               
Number of Projects           
Carried Forward 24/25
Programme - - - 28 31 31 31 31 31 31 31 31 31 31               
Approved from 25/26
Programme - - - 12 15 16 16 17 17 17 17 17 17 17               
Total Projects Currently
Reported - - - 40 46 47 47 48 48 48 48 48 48 48               
Number of Projects                             
Projects Completed - - - 3 3 5 8 11 11 11 13 13 13 15               
Projects Ahead of
Programme - - - 0 0 0 0 0 0 0 0 0 0 0               
Projects on Programme - - - 37 43 42 39 35 35 35 33 33 33 31               
Projects Behind
Programme - - - 0 0 0 0 0 0 0 0 0 0 0                
Projects, Altered
Brief/Programme - - - 0 0 0 0 0 0 0 0 0 0 0               
Projects On Hold  - - - 0 0 0 0 2 2 2 2 2 2 2               
- - - 40 46 47 47 48 48 48 48 48 48 48 
15

Page 16

General Services Capital Programme 2025/2026                             Appendix D
Non-Build Executive Summary – Project Status                                      (Page 2)          
Project Status
SLLC - Booking and Admission System On programme
Ash Die Back On programme
Langlands Boardwalk Complete
Chatelherault Allotments Complete
Alexander Hamilton Memorial Park – Woodland Management On Hold
Nature Restoration Fund On programme
Renewal of Play Parks On programme
Glenaffeoch Road Play Area On programme
Greenhall Replacement Bridge On Hold
White Bridge Replacement, Chatelherault Country Park (cost design) On programme
Coalburn Tennis Court redevelopment On programme
Headstone Remedial Works On programme
Braidwood Play Area Redevelopment On programme
Wooddean Phase 2 Complete
Clyde Walkway repairs On programme
Country parks upgrades On programme
Composting Pilot Complete
Disposable dishware reduction pilot Complete
McKirdy Park Complete
Alexander Hamilton Memorial Fountain - Stonehouse Park Complete
Calderglen Country Park - One Way System & Infrastructure Complete
Springhall Community Centre - Upgrade Complete
Three Rivers / Clydesdale Way On programme
Country Parks Masterplan - Feasibility On programme
Calderglen Country Park - Pump Track On programme
John Cummings – Outdoor Facilities Complete
Energy Efficiency Measures Feasibility TACT Hall On programme
East Kilbride Town Centre Masterplan On programme
SLC Industrial Infrastructure - Energy Efficiency  On programme
Carnwath Community and Business Enterprise HUB On programme
Shawfield Remediation and Development On programme
Coalyard Housing On programme
Outdoor Space – Lanark Complete
Hamilton Town Centre Masterplan On programme
Hamilton Town Square On programme
Vacant & Derelict Land On programme
School uniform recycling pilot On programme
Schools ICT On programme
Education Digital Futures On programme
IT Infrastructure Refresh On programme
Electronic Document Records Management System - Phase 2 On programme
Audio Visual Upgrade - Council Chambers Complete
Public Switch Telephone Network / Alarms (Analogue to Digital) On programme
Lock Up Areas  Complete
Gypsy Travellers Sites Complete
Central Energy Efficiency Fund  Complete
Replacement SWISS Plus IT System On programme
SLC Website Upgrade On programme
16

Page 17

Appendix D
(Page 3) 
General Services Capital Programme 2025/2026 
Non Build Variance Explanations 
Project Name Status Variance Explanation
- - - 
17

Page 18

Appendix E
(Page 1) 
GENERAL SERVICES CAPITAL PROGRAMME 2025/2026 
ROADS EXECUTIVE SUMMARY 
PERIOD ENDED 32 MARCH 2026 (PERIOD 14)                             
1 2 3 4 5 6 7 8 9 10 11 12 13              
Number of Projects             
Total Projects Currently Reported - - - 158 165 184  186 186 186 218 225 233 236              
Programme Status             
Projects Complete - - - 36 69 80 87 87 87 113 130 153 197              
Projects on Programme - - - 122 87 95   90 90 90 95 83 58 11              
Projects Behind Programme - - - 0 0 0     0 0 0 0 0 4 4              
Projects, Altered Brief / Programme - - - 0 0 0 0 0 0 1 3 4 2              
Projects Still to Commence - - - 0 9 9 9 9 9 9 9 14 22               
- - - 158 165 184 186 186 186 218 225 233 236              
Project Status             
Briefing - - - 19 19 16 15 15 15 16 13 15 23              
Production Information - - - 86 59 69 67 67 67 67 60 40 2              
Billing - - - 0 0 0 0 0 0 0 0 0 0              
Tendering - - - 0 1 2 2 2 2 1 0 4 4              
On Site - - - 17 17 17 15 15 15 21 22 21 10              
Complete - - - 36 69 80 87 87 87 113 130 153 197               
- - - 158 165 184  186 186 186 218 225 233 236 
18

Page 19

Appendix E
(Page 2) 
General Services Capital Programme 2025/2026 
Roads Variance Explanations 
Project Name Status Variance Explanation
Scottish Government Tier 1 Funding
Pedestrian and cycle improvements 
Strathaven Road / Calderglen 
Stonelaw Road - Continuous footways 
Investment Fund ~ Safer Routes
Stonelaw Road - Continuous footways (Partly
funded with Tier 1 funding as above) 
Walk Wheel Cycle Trust
NCN75 Clyde Walkway Phase 1 
Behind
Programme 
Behind
Programme 
Behind
Programme 
Behind
Programme 
Due to the tender period taking longer
than anticipated, there has been a delay
in progressing the works and the project
will continue into next financial year. 
Due to the tender period taking longer
than anticipated, there has been a delay
in progressing the works and the project
will continue into next financial year. 
Due to the tender period taking longer
than anticipated, there has been a delay
in progressing the works and the project
will continue into next financial year. 
The tender received no contractor bids
and a retender exercise was required
which has caused a delay to physical
works being undertaken. 
19

Page 20

SOUTH LANARKSHIRE COUNCIL
RESOURCE: ENTERPRISE, ROADS & TRANSPORTATION SERVICES 2025/26
PROJECT / PROGRAMME STATUS ~ PERIOD 13
Briefing
/ Program
m
e
Production
Inform
ation
Billing
Tendering
On
Site
Com
plete
Projects Com
plete
Projects on
Program
m
e
Projects Behind
Program
m
e
Projects altered
Brief /
Program
m
e
Projects Held
ROADS / FOOTWAYS INVESTMENT PROGRAMME
East Kilbride, Rutherglen and Cambuslang Areas
Strategic Schemes 
Craigend Road, Auldhouse 1 1
Peel Road, Thorntonhall 1 1
Stroud Road, East Kilbride - Safety Barrier 1 1
Glen Moriston, East Kilbride 1 1
Spey Terrace/Grove, East Kilbride                        1 1
A727 Busby Road, East Kilbride 1 1
East Mains Road, East Kilbride 1 1
A749 Glasgow Road , East Kilbride (Kingsgate) 1 1
Mallard Terrace, East Kilbride 1 1
A726 Glasgow Road, Chapelton 1 1
Falkland Park, East Kilbride 1 1
Glen Doll, East Kilbride 1 1
Crutherland Highway, East Kilbride 1 1
Dale Avenue, East Kilbride 1 1
Redwood Drive, East Kilbride 1 1
Tantallon Park, East Kilbride 1 1
Eider Place, East Kilbride 1 1
Calderwood Road, Rutherglen 1 1
Cathkin By Pass, Rutherglen 1 1
Hallside Boulevard, Cambuslang 1 1
A724 Cambuslang Road, Rutherglen 1 1
Surface Dressing & Preventative patching Schemes
Millwell Road, Auldhouse 1 1
Markethill Road, East Kilbride 1 1
Muirburn Road, Glassford 1 1
Breckonridge Highway, Strathaven 1 1
Hallside Road/Manse Brae, Cambuslang 1 1
Newton Brae, Cambuslang 1 1
Calder Road/Westburn Road, Cambuslang 1 1
Manse Brae, Cambuslang 1 1
Westburn Road, Cambuslang - Surface Dressing 2025/2026 1 1
Breckonridge Highway, Strathaven - Surface Dressing 2025/2026 1 1
Newton Brae, Cambuslang - Surface Dressing 2025/2026 1 1
Millwell Road, East Kilbride - Surface Dressing 2025/2026 1 1
Markethill Road, East Kilbride - Surface Dressing 2025/2026 1 1
PROJECT STATUS PROGRAMME STATUS
Project Title
20

Page 21

SOUTH LANARKSHIRE COUNCIL
RESOURCE: ENTERPRISE, ROADS & TRANSPORTATION SERVICES 2025/26
PROJECT / PROGRAMME STATUS ~ PERIOD 13
Briefing
/ Program
m
e
Production
Inform
ation
Billing
Tendering
On
Site
Com
plete
Projects Com
plete
Projects on
Program
m
e
Projects Behind
Program
m
e
Projects altered
Brief /
Program
m
e
Projects Held
PROJECT STATUS PROGRAMME STATUS
Project Title
Strategic Patching and Minor asset improvements
Cairns Road 1 1
Bogleshole Road 1 1
Stonelaw Road 1 1
Westburn Road 1 1
Eaglesham Road, East Kilbride, Peel Road 1 1
Eaglesham Road, East Kilbride, Hairmyres Train Station roundabout 1 1
Quarry Road, East Kilbride 1 1
Laburnum Avenue at Chestnut Crescent, East Kilbride 1 1
Lomond, East Kilbride 1 1
Musgrove Place, East Kilbride 1 1
Philipshill Road, East Kilbride 1 1
Stroud Road, EK - Phase 1 1 1
Alwyn Drive 1 1
Stewartfield Way 1 1
Kirktonholme Road 1 1
Montgomery Street, EK 1 1
Buchandyke Road 1 1
Gilmourton 1 1
The Mid Road 1 1
Lime Road 1 1
Green Street 1 1
Newton Highway 1 1
Minor Asset Improvements 1 1
Footways
Hill View, East Kilbride 1 1
Telford Rd (Denholm to Sinclair) 1 1
Maxwellton Rd (Aikman to Blacklands) 1 1
Kirkton Park, East Kilbride 1 1
Green Street, Strathaven 1 1
Ballochmyle and Lochlea, EK 1 1
Mossneuk Ave (Greenhills to Forth), East Kilbride 1 1
Seymour Green, East Kilbride 1 1
Nithsdale, East Kilbride 1 1
Burnside Road, Rutherglen 1 1
Glasgow Rd, Cambuslang 1 1
Mentieth Drive, Rutherglen 1 1
21

Page 22

SOUTH LANARKSHIRE COUNCIL
RESOURCE: ENTERPRISE, ROADS & TRANSPORTATION SERVICES 2025/26
PROJECT / PROGRAMME STATUS ~ PERIOD 13
Briefing
/ Program
m
e
Production
Inform
ation
Billing
Tendering
On
Site
Com
plete
Projects Com
plete
Projects on
Program
m
e
Projects Behind
Program
m
e
Projects altered
Brief /
Program
m
e
Projects Held
PROJECT STATUS PROGRAMME STATUS
Project Title
Hamilton Area
Strategic Schemes 
Strathaven Road, Hamilton *b/f from 2024 1 1
Queens Drive, Hamilton 1 1
Main Street, Uddingston 1 1
Hunter Road / Margaret Road, Hamilton 1 1
Keir Hardie Road, Larkhall 1 1
Shaws Road, Larkhall 1 1
Avon Street, Hamilton 1 1
A724 Glasgow Road, Blantyre 1 1
Livingstone Gardens / Hope Crescent, Larkhall 1 1
Field Road, Larkhall 1 1
Abercorn Drive, Hamilton 1 1
Muir Street/Nursery Place, Blantyre 1 1
Maitland Bank, Larkhall 1 1
Graham Street, Hamilton 1 1
Muir Street, Hamilton 1 1
Alamada Street, Hamilton 1 1
Swisscott Avenue roundabout 1 1
High Blantyre Road, Blantyre 1 1
Broomfield Road, Netherburn 1 1
Annsfield Road 1 1
Hill Street, Hamilton 1 1
Plotcock Road, Quarter - Phase 1 1 1
Strategic Infrastructure  (Drainage Schemes)
Meikle Earnock Road 1 1
A72 Lanark Road 1 1
Millheugh Road, Larkhall, Broomelton Road to Glenavon Mews 1 1
Millheugh Road, Larkhall, Glenavon Mews 1 1
Preventative Maintenance Schemes
Sandford Road (Phase 2)  (*Preparatory patched in 2024) 1 1
Newhousemill Road, Hamilton (Section1) 1 1
Candermill & Marlage Road 1 1
Newhousemill Road, Hamilton (Section2) 1 1
Spittal Road 1 1
Preparatory Patching 1 1
22

Page 23

SOUTH LANARKSHIRE COUNCIL
RESOURCE: ENTERPRISE, ROADS & TRANSPORTATION SERVICES 2025/26
PROJECT / PROGRAMME STATUS ~ PERIOD 13
Briefing
/ Program
m
e
Production
Inform
ation
Billing
Tendering
On
Site
Com
plete
Projects Com
plete
Projects on
Program
m
e
Projects Behind
Program
m
e
Projects altered
Brief /
Program
m
e
Projects Held
PROJECT STATUS PROGRAMME STATUS
Project Title
Strategic Patching and Minor Asset Improvements
Swisscott Avenue, Hamilton  1 1
Blantyre farm Road, Uddingston (*b/f from 2024 -Lining & AntiSkid 1 1
Calder Street, Blantyre 1 1
Violet Crescent, Stonehouse 1 1
Canderside Toll, Larkhall 1 1
Carlisle Road, Birkenshaw, Larkhall 1 1
Union Street, Hamilton 1 1
John Street, Blantyre 1 1
Burnblea Gardens, Hamilton 1 1
Duke Street, Hamilotn 1 1
Carriageway patching and various minor works 1 1
Footways
Marswood Green / Rosslyn Court, Hamilton 1 1
Alder Avenue, Hamilton 1 1
Lochalsh Place, Blantyre 1 1
Machan Road, Larkhall 1 1
Melrose Street, Hamilton 1 1
Strathaven Road, Stonehouse 1 1
Carlisle Road, Birkenshaw, Larkhall 1 1
Hill Street, Hamilton 1 1
Castle Avenue, Bothwell (Phase 1) 1 1
Castle Avenue, Bothwell (Phase 2) 1 1
Haddow Street, Hamilton 1 1
Woodside Walk, Hamilton 1 1
Lowther Crescent, Stonehouse  1 1
Limekilnburn Road, Quarter 1 1
23

Page 24

SOUTH LANARKSHIRE COUNCIL
RESOURCE: ENTERPRISE, ROADS & TRANSPORTATION SERVICES 2025/26
PROJECT / PROGRAMME STATUS ~ PERIOD 13
Briefing
/ Program
m
e
Production
Inform
ation
Billing
Tendering
On
Site
Com
plete
Projects Com
plete
Projects on
Program
m
e
Projects Behind
Program
m
e
Projects altered
Brief /
Program
m
e
Projects Held
PROJECT STATUS PROGRAMME STATUS
Project Title
Clydesdale Area
Strategic Schemes 
A73 St John's Kirk 1 1
A706 Lanark (Patching) 1 1
A702 Elvanfoot 1 1
A721 Carnwath Road, Carluke 1 1
B7011 Brownlee Road 1 1
B7078 Cairn Lodge Services 1 1
New Trows Road, Lesmahagow 1 1
Stobilee Road, Lanark 1 1
Mousebank Road, Lanark 1 1
A73 Hyndford Road 1 1
B7011 Brownlee Road, Law 1 1
Anstruther Street, Law 1 1
New Kayes Road, Auchenheath 1 1
B7078 Carlisle Road, Blackwood 1 1
C1 Maudslie Road, Carluke 1 1
Coalburn Road/Bellfireld Road, Coalburn 1 1
A70 at Pretsmill 1 1
Jerviswood, Lanark 1 1
Hillview, Symington 1 1
Nemphlar Moor 1 1
Laverockhall, Lanark 1 1
Strategic Infrastructure  - Drainage Schemes
Spittal Road, Carnwath 1 1
A73 Roberton @Littlegill 1 1
B7018 Dillarburn 1 1
Vere Road, Kirkmuirhill 1 1
Tower Road, Douglas 1 1
B7018 Dillarburn at Netheraffleck 1 1
Preventative Maintenance Schemes
A70 Lang whang 1 1
A72 Symington 1 1
B740 Crawfordjohn 1 1
B7078 Parkhead to Millrig 1 1
C29 Carstairs Junction 1 1
Strathaven Road, Lesmahagow 1 1
B7015 Climpy Road, Forth 1 1
Roberton Back Road, Dunsyre 1 1
B7055 Sornfallow 1 1
Auchnatroch, Dillarburn 1 1
Preparatory Patching 1 1
Patching, lining, TM ancilliaries 1 124

Page 25

SOUTH LANARKSHIRE COUNCIL
RESOURCE: ENTERPRISE, ROADS & TRANSPORTATION SERVICES 2025/26
PROJECT / PROGRAMME STATUS ~ PERIOD 13
Briefing
/ Program
m
e
Production
Inform
ation
Billing
Tendering
On
Site
Com
plete
Projects Com
plete
Projects on
Program
m
e
Projects Behind
Program
m
e
Projects altered
Brief /
Program
m
e
Projects Held
PROJECT STATUS PROGRAMME STATUS
Project Title
Strategic Patching and Minor Asset Improvements
Hagholm Road, Cleghorn 1 1
Mousemill Road, Lanark 1 1
Yieldshields Road, Carluke 1 1
C29 Pettinain 1 1
C14 Andershaw Road 1 1
Nursery Avenue, Douglas 1 1
Kirkstyle Car Park, Biggar 1 1
Foulford Road, Lesmahagow (Drainage) 1 1
Foulford Road, Lesmahagow (Surfacing) 1 1
B7078 Woodpark 1 1
B7086 Boghead 1 1
Daer Water Road, Elvanfoot 1 1
B7086 Burnfoot, Auchenheath 1 1
Hawksland, Lesmahagow 1 1
Blair Road, Crossford 1 1
Dillarburn Road, Lesmahagow 1 1
C37 Harelaw A706 to A70 Tarbrax 1 1
Hagholm Road, Cleghorn 1 1
Carriageway patching and various minor works 1 1
Footways
Southfield Road, Blackwood 1 1
B7078 Carlisle Road 1 1
School Road/Strathaven Road, Lesmahagow 1 1
Main street, Forth 1 1
Hyndshaw View/Castlehill Crescent, Law 1 1
Carlisle Road, Crawford 1 1
CLIMATE EMERGENCY FUNDING
Warm Mix / Low Carbon Asphalt Trial
Wilton Road, Carluke 1 1
Murrayhill, East Kilbride 1 1
Victoria Street, Blantyre 1 1
Traffic Signal Upgrades
Ayr Road Crossroads, Ashgill  - Junction Design, MOVA upgrade 1 1
25

Page 26

SOUTH LANARKSHIRE COUNCIL
RESOURCE: ENTERPRISE, ROADS & TRANSPORTATION SERVICES 2025/26
PROJECT / PROGRAMME STATUS ~ PERIOD 13
Briefing
/ Program
m
e
Production
Inform
ation
Billing
Tendering
On
Site
Com
plete
Projects Com
plete
Projects on
Program
m
e
Projects Behind
Program
m
e
Projects altered
Brief /
Program
m
e
Projects Held
PROJECT STATUS PROGRAMME STATUS
Project Title
ROADS REFURBISHMENT BUDGET
Structures projects
Bothwell Bridge, Hamilton ~ Scour Protection Works 1 1
Millheugh Bridge, Larkhall ~ Refurbishment works 1 1
Elvanfoot Bridge ~ Refurbishment works 1 1
Cander Bridge ~ Joint refurbishment 1 1
Cornwall Street footbridge 1 1
East Kilbride Structures (Cont/ from 2024/25) 1 1
Duke St MSCP 1 1
Burnside Bridge, Rutherglen (Porject led by Network Rail) 1 1
Traffic and Transportaion
Various minor works, lining & signing works 1 1
Vehicle Actived Signs ~ Upgrades 1 1
Vehicle and Pedestrian counters ~ Upgrades 1 1
Lighting ~ LED & Columns
Renewal of street lighting infrastructure 1 1
BRIDGES
Clyde Bridge ~ Remedial works and retention release payment only 1 1
SCOTTISH GOVERNMENT TIER 1 FUNDING (FORMERLY CWSR)
Pedestrian and cycle improvements
Hairmyres P&R ~ Active Travel Works 1 1
Redwood Drive ~ junction upgrade 1 1
Strathaven Road / Calderglen ~ Active Travel 1 1
Columbie Junction ~ Active travel 1 1
Stonelaw Road ~ Continuous footways 1 1
Toucan Crossing Installations
Stewartfield Way ~ Toucan crossings 1 1
LOCAL AUTHORITY DIRECT AWARD
Walking Routes to Schools and Town Centres 1 1
NCN74 from Chatelherault to Hamilton ~ Vegetation/scrub clearance 1 1
CITY DEAL PROJECTS
Cathkin ~ Complementary works (various minor works) 1 1
Stewartfield Way 1 1
Greenhills ~ Loss of value payments / Monitoring 1 1
26

Page 27

SOUTH LANARKSHIRE COUNCIL
RESOURCE: ENTERPRISE, ROADS & TRANSPORTATION SERVICES 2025/26
PROJECT / PROGRAMME STATUS ~ PERIOD 13
Briefing
/ Program
m
e
Production
Inform
ation
Billing
Tendering
On
Site
Com
plete
Projects Com
plete
Projects on
Program
m
e
Projects Behind
Program
m
e
Projects altered
Brief /
Program
m
e
Projects Held
PROJECT STATUS PROGRAMME STATUS
Project Title
STRATHCLYDE PARTNERSHIP FOR TRANSPORT
Hairmyres P&R 1 1
Lanark Interchange 1 1
Congestion Reduction Measures
High Blantyre Road / Hunthill Road / Douglas Street Blantyre ~ bus priority 1 1
COMMUNITY BUS FUND
Land Purchase at Lanark Interchange (remainder funding to Interchange) 1 1
INVESTMENT FUND
Safe Routes ~  Stonelaw Road ~ Continuous footways 1 1
BUS INFRASTRUCTURE FUND
Bus Priority Fusion Traffic Control System 1 1
Real Time Information Displays (Hamilton / Rutherglen) 1 1
Various bus stop enhancement (Hamilton / Blantyre/Clydesdale) 1 1
ROAD SAFETY IMPROVEMENT FUND
A721 Newbigging to Elsricke 1 1
B743 Strathaven to Council Boundary 1 1
A730 Mill Street at Main Street/ Burnhill Street signalised junction, Rutherglen 1 1
A724 Main Street at/near Bridge Street, Cambuslang 1 1
RoadTrace ~ connected vehicle data 1 year licence and support 1 1
CYCLING SCOTLAND
Cycle shelter installations @ 7 Primary Schools 1 1
Cycle shelter repairs 1 1
Walk Wheel Cycle Trust
NCN74 Abington to Crawford Quietway 1 1
NCN75 Clyde Walkway, Phase 1 1 1
St Stephens Avenue ~ Pedestrian Crossing 1 1
23 2 0 4 10 197 197 11 4 2 22
27

Page 28

28

Page 29

Report
Agenda Item 
Report to: Financial Resources Scrutiny Forum
Date of Meeting: 27 August 2026
Report by: Executive Director (Finance and Corporate Resources)  
Subject: Capital Budget Monitoring 2025/2026 - Housing Capital
Programme 
1. Purpose of Report
1.1. The purpose of the report is to:
[purpose]
 update members of the Financial Resources Scrutiny Forum on the final outturn
position of the Council’s Housing Capital Programme for the period covering 1 April
2025 to 31 March 2026.
[1purpose]
2. Recommendation(s)
2.1. The Forum is asked to approve the following recommendation:
[recs]
(1) that the final outturn position on the 2025/2026 Housing Capital Programme be
noted. 
[1recs]
3. Background
3.1. The Capital reports attached provide detail on the position as at 31 March 2026 from a
financial perspective.   
3.2. Appendix A shows the financial position of the Housing Capital Programme, which was
reported to the Executive Committee on 24 June 2026.  Any physical progress update
for projects carried forward into financial year 2026/2027 will be picked up as part of the
new year monitoring report. 
4.      Housing Programme
4.1. 2025/26 Budget:  Appendix A summarises the position on the Housing programme as at
31 March 2026.  The revised capital programme for the year is £87.740 million, as
approved by the Executive Committee on 24 June 2026. 
4.2. 2025/2026 Year End Position:  The actual expenditure on the Housing programme
was £85.782 million, an underspend of £1.958 million.  The actual spend is broadly in
line with the outturn previously reported although the actual spend on the New Build
programme was better than forecast, while the spend on Housing Investment
Programme (HIP) was slightly less than expected due to an underspend on kitchens
and heating projects partially offset by overspends in external fabrics, windows and
doors and environmental works.  The planned land settlement for the site on Almada
Street (£0.720 million) could not be concluded by 31 March and settled in early April
2026 and as a result the expenditure has slipped into 2026/2027.  Additional spend on
other sites offset this planned spend. 
Carry Forward to 2026/2027:  Taking into account the year end underspend would
mean a carry forward of £1.958 million.  A breakdown of the carry forward is £0.852
4
29

Page 30

million for New Build programme and £1.106 million for Housing Investment
Programme.  This is detailed in a separate report to this meeting.  It is proposed that the
full amount be included in the 2026/2027 Capital Programme. 
5. Employee Implications
5.1. There are no employee implications as a result of this report. 
6. Financial Implications 
6.1. The financial implications are detailed in section 4 of this report. 
7. Climate Change, Sustainability and Environmental Implications
7.1. There are no implications for climate change, sustainability or the environment in terms
of the information contained in this report. 
8. Risk and Other Implications
8.1. The main risk associated with the Council’s Capital Programme is an overspend.  The
risk has been assessed as low given the detailed project management plans prepared
and monitored for each project.  The risk of overspend is managed through four weekly
Investment management meetings. 
9. Integrated Impact Assessment and Consultation Requirements
9.1. This report does not introduce a new policy, function or strategy or recommend a
change to existing policy, function or strategy and therefore no impact assessment is
required. 
9.2. There was also no requirement to undertake any consultation in terms of the information
contained in this report. 
Jackie Taylor
Executive Director (Finance and Corporate Resources) 
10 August 2026 
Link(s) to Council Values/Priorities/Outcomes
 Accountable, effective, efficient and transparent 
Previous References
 Executive Committee, 24 June 2026 
List of Background Papers 
 Capital Ledger prints to 31 March 2026 
Contact for Further Information
If you would like to inspect the background papers or want further information, please contact:
Graham Booth, Finance Manager (Strategy)
Ext:  2699 (Tel:  01698 452699)
E-mail:  graham.booth@southlanarkshire.gov.uk 
30

Page 31

APPENDIX A 
SOUTH LANARKSHIRE COUNCIL           
CAPITAL EXPENDITURE 2025/2026
HOUSING PROGRAMME 
FOR PERIOD 1 APRIL 2025 TO 31 MARCH 2026 
2025/2026
Annual Budget 
2025/2026
Actual to
31/03/26 
£m  £m
EXPENDITURE   
2025/2026 Budget 
Incl. carry forward from 2024/25
87.740  85.782 
2025/2026
Actual to
31/03/26  
£m
INCOME     
Capital Funded from Current Revenue  25.815
Prudential Borrowing  15.762
Scottish Government Specific Grant:
– Capital Grant   11.312
– New Build  24.620
– Open Market Purchase Scheme  7.700
– Mortgage to Rent  0.160
– Climate Emergency Fund  0.219
Miscellaneous Income  0.194
TOTAL FUNDING  85.782   
31

Page 32

Appendix B
(Page 1)
HOUSING CAPITAL PROGRAMME 2025/2026
EXECUTIVE SUMMARY
PERIOD ENDED 31 MARCH 2026
Expenditure Periods 
1 2 3 4 5 6 7 8 9 10 11 12 13 14
Programme Status               
Projects Complete  - 9 13 15 19 24 29 30 36 40 43 45 46 55
Projects on
Programme 
- 100 104 106 110 98 92 98 92 86 90 84 80 74
Projects Behind
Programme 
- 5 2 0 0 1 1 1 3 2 1 2 4 0
Projects Altered Brief/
Programme 
- 1 3 6 0 5 6     1 1 4 1 4 1 2
Projects Held  - 16 17 17 16 20 20 18 12 12 13 13 17 17 
- 131 139 144 145 148 148 148 144 144 148 148 148 148               
Project Status               
Design Feasibility  - 34 40 43 40 37 36 33 25 25 27 26 25 25
Sketch Design  - 6 5 2 1 1 1 1 1 1 1 1 1 1
Detailed Design  - 2 2 1 2 2 2 2 1 1 1 0 0 0
Production Information  - 18 17 21 21 20 19 19 16 12 12 12 11 10
Tendering  - 20 23 23 23 27 27 23 25 23 22 21 18 19
On Site  - 42 39 39 39 37 34 40 40 42 42 43 47 38
Complete  - 9 13 15 19 24 29 30 36 40 43 45 46 55 
- 131 139 144 145 148 148 148 144 144 148 148 148 148 
32

Page 33

Appendix B
(Page 2) 
Housing Capital Programme 2025/2026 
Build Variance Explanations 
Project Name Status Variance Explanation   
- - -   
33

Page 34

1 2 3 4 5 6 7 8 9 10 11 12 13 14
Original Budget 25/26 0 2.462 7.801 14.379 19.032 27.525 33.147 39.407 45.148 52.315 56.18 63.563 65.704 85.948
Revised Budget 25/26 0 2.462 7.801 14.379 19.032 27.525 33.147 39.407 45.148 52.315 56.18 63.563 65.842 87.74
Actual 25/26 0 2.462 7.801 14.379 19.032 27.525 33.147 39.407 45.148 52.315 56.18 63.563 65.842 85.782
0
10
20
30
40
50
60
70
80
90
100
£ Millions
HRA Capital Expenditure Profile Graph 25/26
34

Page 35

Report
Agenda Item 
Report to: Financial Resources Scrutiny Forum
Date of Meeting: 27 August 2026
Report by: Executive Director (Finance and Corporate Resources)  
Subject: Capital Budget Monitoring 2026/2027 - General Fund
Capital Programme 
1. Purpose of Report
1.1. The purpose of the report is to:
[purpose]
 update members of the Financial Resources Scrutiny Forum of progress on the
Council’s General Fund Capital Programme for the period covering 1 April 2026
to 10 July 2026.
[1purpose]
2. Recommendation(s)
2.1. The Forum is asked to approve the following recommendation:
[recs]
(1) that the physical and financial progress of the 2026/2027 General Fund
Capital Programme be noted. 
[1recs]
3. Background
3.1. South Lanarkshire Council (25 February 2026) approved a General Fund Capital
Programme base budget of £105.247 million for financial year 2026/2027.  Since the
approval of this programme, there have been a number of events that will impact this
budget namely the approval of investments as part of the 2026/2027 revenue budget
and the finalisation of the year-end position for 2025/2026.   This will be detailed in
section 4. 
3.2. The Capital reports attached provide detail on the position as at 10 July 2026 from
both a financial and physical perspective. 
3.3. Appendices A to E show the financial position of the General Fund Capital
Programme, with the physical progress detailed in Appendices F to H – as they are
split into Build, Non-Build and Roads. 
4. General Fund Capital Programme 2026/2027
4.1. 2026/27 Budget:  Section 3.1 notes that the base General Fund Capital Programme
is £105.247 million, as approved by Council in February 2026.  A number of
adjustments to the programme have been required to reflect budget carried forward
from financial year 2025/2026, along with additional funding received in 2025/2026. 
The adjustments also reflect the anticipated spend which can realistically be achieved
in 2026/2027.  In total, these adjustments amount to a net increase of £3.705 million
and result in a base budget for 2025/2026 of £108.952 million.  A full list of these
adjustments is included in Appendix A. 
5
35

Page 36

4.2. During financial year 2026/2027, Resources have advised of adjustments required to
the programme.  The revised programme for the year totals £98.167 million and
includes adjustments to the programme totalling a net decrease of £10.785 million. 
These adjustments were approved by the Executive Committee on 24 June 2026
and 19 August 2026 and are detailed in Appendices B and C respectively.  The
decrease mainly reflects the timing of spend. 
4.3. The funding available to support the programme also totals £98.167 million and is
detailed in Appendix E. 
4.4. 2026/2027 Forecast:  The programme spend and funding for the General Fund is
summarised in Appendix D.  As noted in 4.2, the total capital spending programme
for the year is £98.167 million. 
4.5. Appendix D also shows a forecast for the financial year of £98.167 million. 
4.6. 2026/2027 Actual Position:  Actual spend incurred until the 10 July 2026 totals
£6.381 million. 
4.7. Actual funding received to 10 July 2026 is £10.815 million.  Relevant officers will
continue to closely monitor the generation of all income including receipts. 
5. Employee Implications
5.1. There are no employee implications as a result of this report. 
6. Financial Implications
6.1. The financial implications are included in section 4 of this report. 
7. Climate Change, Sustainability and Environmental Implications
7.1. There are no implications for climate change, sustainability or the environment in
terms of the information contained in this report. 
8. Risk and Other Implications
8.1. The main risk associated with the Council’s Capital Programme is an overspend.  The
risk has been assessed as low given the detailed project management plans prepared
and monitored for each project.  The risk of overspend is managed through four weekly
Investment management meetings. 
9. Integrated Impact Assessment and Consultation Requirements
9.1. This report does not introduce a new policy, function or strategy or recommend a
change to existing policy, function or strategy and therefore no impact assessment is
required. 
9.2. There was no requirement to undertake any consultation in terms of the information
contained in this report. 
Jackie Taylor
Executive Director (Finance and Corporate Resources) 
10 August 2026 
Link(s) to Council Values/Priorities/Outcomes
 Accountable, Effective, Efficient and Transparent 
36

Page 37

Previous References
 South Lanarkshire Council, 25 February 2026
 Executive Committee, 24 June 2026
 Executive Committee, 19 August 2026 
List of Background Papers
 Capital Ledger prints to 10 July 2026 
Contact for Further Information
If you would like to inspect the background papers or want further information, please contact:
Lorraine O’Hagan, Head of Finance (Strategy)
Ext:  2601 (Tel:  01698 452601)
E-mail:  lorraine.o’hagan@southlanarkshire.gov.uk
37

Page 38

APPENDIX A 
2026/2027 General Services Base Budget Position – Required Adjustments 
General Fund – 2025/26 Budget:  As noted at Section 3.1 of this report, the base programme
for the General Fund is £105.247 million, as approved by Council in February 2026.  This base
budget is affected by the adjustments detailed in sections 1.1 to 1.12 and summarised in Table
1. 
1.1. 2026/2027 Investments:  As part of the Revenue Budget setting process in February
2026, an amendment was approved which allocated investment monies of £33.300
million.  Officers from across the Council have considered the budget allocations and
£12.130 million of this is anticipated to spend in 2026/2027.  Of that amount, it is
anticipated that £10.610 million will be Capital spend and will be added to the General
Fund Programme to be funded by Revenue Budgets (CFCR). 
Increase to Budget:  £10.610 million 
1.2. 2025/2026 Carry Forward:  As reported in the Final Outturn Report for 2025/2026 (a
separate report to this meeting), a carry forward total of £10.142 million will ensure
sufficient budget is available to conclude ongoing projects within the General Fund
Capital Programme. 
Increase to Budget:  £10.142 million 
1.3. General Capital Grant: The Local Government Finance Circular received by the
Scottish Government in May revised our 2026/2027 General Capital Grant allocation to
£25.982 million.  This is an increase of £5.031 million and reflects the additional
distribution of a number of funds: 
1.4. Nature Restoration Fund: An allocation has been made for Nature Restoration Fund
£0.285 million.  This will be added to the 2026/2027 Capital Programme and used to
fund Urban Woodland Management plans, Local Nature Reserve plans and Peatland
surveys.
Increase to Budget: £0.285 million 
1.5. Active Travel Funding: An additional amount of £2.451 million for Active Travel
Infrastructure will be added to the 2026/2027 Capital Programme to fund a number of
works including Strathaven Road East Kilbride Phase 2 (inc. footway, cycle way
widening, street lighting, drainage), upgrade of East Kilbride underpasses (inc. lighting,
landscaping, drainage, artwork), National Cycle Network 75 Phase 3 (Cambuslang to
Newton widening, surfacing and lighting), Cambuslang connection to Clyde Cycle Park
(inc. footway, segregated cycle route, street lighting, drainage), and Bothwell to
Uddingston (footpath widening, new surfacing, street lighting, drainage). 
Increase to Budget: £2.451 million 
1.6. Climate Emergency Funding Projects:  An allocation of £1.100 million for Climate
Emergency Funding projects will be used for a number of projects including roof
replacement & PV installation at Coulter Primary School, upgrades to Building Energy
Management Systems at various schools, energy efficiency measures at St Andrews &
St Brides and Holy Cross High Schools, installation of EV charging points at Hawbank
and Canderside Roads Depots, Sports Pitch LED Floodlighting (Fernhill, Willie Waddell,
38

Page 39

Whitemoss and Newton Farm), extension of the Beat the Street programme in
Uddingston and Bothwell, reusable drink system to reduce single use drinks containers
in primary schools, and feasibility studies for the next phase of PV installations and LED
replacement of school staging lights. 
Increase to Budget: £1.100 million 
1.7. Flood Prevention Funding Projects:  An allocation of £1.195 million for Flood
Prevention will be added to the 2026/2027 Capital Programme with a programme of
works being collated.  This will include updating existing studies for Eastfield, Muirbank,
Halfway Stormwater Management Plans, Hamilton Surface Water Management Plan
and Rutherglen Road, Shawfield - Flood Risk Assessment. 
Increase to Budget: £1.195 million 
1.8. Profiling of Spend Exercise 2026/2027:  As per the Capital Budget and Monitoring
Process, Resources were asked to confirm their anticipated spend levels for the full
programme for the coming year to ensure that, in totality, the programme can be
delivered in 2026/2027.  This exercise has identified spend that requires to be removed
from the programme this year.  The movements are outlined below and taken in turn.   
 City Deal Stewartfield Way / Hamilton Junctions:  £7.335 million of budget has been
reprofiled into future years to reflect expected contractor timescales for Stewartfield
Way (£5.335 million), and for Hamilton Junction Improvements (£2 million) where
only 6 months of Utility contractor works can be undertaken this year.
 Secondary Schools expansion budget:  Reflecting the programme of works, spend
of £9.000 million is now anticipated for 2026/2027 meaning that £4.743 million of
budget will be required into future years. 
 Estates Strategy:  As the work on the Estate Strategy progresses, current indications
are that expenditure of £7.3 million could be achieved in 2026/2027, meaning £4.7
million is removed for use in future years.   
1.9. The review of spend profiles has meant a reduction to the programme of £16.778
million. 
Decrease to Budget: (£16.778 million) 
1.10. Transfers to Revenue:  In addition to the adjustments noted at Section 4.9 to 4.10, a
£1.000 million transfer to the Revenue Budget for the Private Housing Scheme of
Assistance project and £4.300m for Planned Maintenance is proposed.  To reflect
Accounting Regulations, this spend cannot be classed as Capital.  Therefore, it is
proposed that budget of £5.300 million will be transferred to Housing and Technical
Resource’s Revenue budget.  
39

Page 40

1.11. Capital expenditure can be funded by Revenue monies however Revenue spend
cannot be paid for from Capital funding.  The Council’s Capital programme includes
funding that can be used for Revenue spend.  We are therefore able to move funding
between the Capital and Revenue Programmes and deliver the project as planned. 
This is an accounting transaction only.
Transfer of Budget: (£5.300 million) 
1.12. 2026/2027 General Services Base Budget Position:  Taking into account the
movements noted in sections 4.2 to 4.12, the General Services Programme for
2026/2027 is now £108.952 million.  This is the base budget for the financial year.  This
is summarised in Table 1. 
Table 1 – 2025/2026 General Services Base Budget 
2026 / 2027
£m
Approved Programme – 26 February 2025  105.247
2025/2026 Investments (Section 1.1) 10.610
2025/2026 Carry Forward (Section 1.2) 10.142
General Capital Grant – Nature Restoration Funding (Section 1.4) 0.285
General Capital Grant – Active Travel Funding (Section 1.5) 2.451
General Capital Grant – Climate Emergency Funding (Section 1.6) 1.100
General Capital Grant – Flood Prevention Funding (Section 1.7) 1.195
Profiling of Spend Exercise – Change in Profile of Spend (Section 1.8) (16.778)
Transfers to Revenue (Sections 1.10 and 1.11) (5.300)
2026/2027 General Services Base Budget  108.952 
40

Page 41

Appendix B 
Adjustments Approved by Executive Committee – 24 June 2026 
Community and Enterprise Resources
Tree Planting
Grant awards from Future Woodlands Scotland (£0.030 million) and Trees for
Cities (£0.001 million) have been received which will be used to expand the reach
of both the Clyde Climate Forest and Future Woodlands Scotland’s strategic
goals. 
Approval is sought to increase the 2026/2027 Capital programme by the grant
awards totalling £0.031 million. 
£0.031m
Education Resources 
St Athanasius Primary School
Upgrading and expansion of the external play and teaching area to increase pupil
capacity of PE, including upgrading of School Multi-Purpose Games Area
(MUGA).  This will be funded from Developers Contributions. 
Approval is sought to allocate £0.050 million received from Developers
Contribution. 
£0.050m
(£0.050m) 
Housing and Technical Resources
Central Energy Efficiency Fund (CEEF) 
This is the revolving fund which delivers savings through the installation of energy
efficient technologies within Council properties. 
Approval is sought to increase the Capital Programme by £0.557 million for the
2026/2027 CEEF programme of works installing PV Panels and LED lighting. 
Climate Emergency Fund
Approval is sought to transfer Climate Change Funding of £0.038 million to the
Housing Programme, to allow the project to be managed as part of the overall
programme of works. 
£0.557m 
(£0.038m)  
TOTAL ADJUSTMENTS £0.550m   
41

Page 42

APPENDIX C 
Adjustments Approved by Executive Committee – 19 August 2026 
Community and Enterprise Resource 
People and Place Local Authority Direct Award
Funding has been made available to take forward active travel initiatives by
supporting active and sustainable travel.  This will involve promoting initiatives to
increase the frequency of active travel journeys, through developing walking
routes to schools, parks and in town centres. Projects include a bike hire pilot,
further work to promote the Think, Move Breath campaign, road safety education,
maintenance and enhancement of active travel routes, and support for community
led events at Clyde Cycle Centre.  These have been provided to the Scottish
Government to confirm eligibility to allow programming of works. 
Approval is sought to increase the 2026/2027 capital programme by £0.140 million
which will be funded by Transport Scotland through the People and Place Local
Authority Direct Award 2026/2027. 
Road Safety Improvement Fund
Transport Scotland have awarded South Lanarkshire Council £0.787 million in
connection with the Road Safety Improvement Fund for 2026/2027. Roads have
identified projects, based upon casualty reduction priorities as reported to the
Road Safety Forum. 
Detailed accident investigation reports have been collated for each location by the
Traffic and Transportation team.  These reports will be used to prioritise the
projects listed below. 
A70, Douglas – M74 J12 northbound
off ramp
B743, Strathaven to council
boundary
A70, Glespin to Council boundary A70, B7078 Junction to Rigside
A721, Newbigging to Elsrickle B758, Blantyre Farm Road, Blantyre
to Uddingston
A702, Council boundary to M74 J14 B7078, Canderside to Blackwood
B7086, Strathaven to Kirkmuirhill Newhousemill Road at Bridge, EK
B7078, M74 Junction 10 to M74 J11 Harsh Braking Sites – Various locals 
Approval is sought to increase the capital programme by £0.787 million.   
Cycling Scotland Grant Award 
Additional funding has been awarded by Cycling Scotland for new cycle storage
and shelter repairs.  Using this funding, shelter installations are proposed at the
following schools: 
Stonelaw High School Bankhead Primary School
Stonhehouse Primary School James Aiton Primary School
Kirkton Primary School Abington Primary School
Forth Primary School Neilsland Primary School
Spittal Primary School Carstairs Primary School 
£0.140m 
£0.787m 
42

Page 43

In addition, David Livingstone memorial Primary School will have additional cycle
hoops and a scooter rack installed. 
Approval is sought to increase the capital programme by £0.121 million.   
East Kilbride Town Centre
As a result of savings on demolition costs and updated profiling on the project, the
anticipated spend in 2026/2027 is lower than originally budgeted. The budget
released by the reduced cost of the demolition will be retained within the overall
project budget of £50.3 million with the design planning stage for the Town Hall
ongoing. 
Approval is sought to transfer £7.183 million into the 2027/2028 Capital
programme. 
Hamilton Town Centre
Due to the timescales confirmed for the demolition of the New Cross Centre, and
the former Bairds’ building, the anticipated date for the start of demolition setup
on sites is March 2027 with a combined tender package being progressed.   
As a result, the budget required this year will be reduced to reflect fees and minor
spend. 
Approval is sought to transfer £3.341 million into the 2027/2028 Capital
programme. 
Larkhall Leisure Centre
The forecast spend in 2026/2027 for Larkhall Leisure Centre is anticipated to be
less than budgeted, reflecting the cost profile information from Hub South West
following financial close for the enabling works.   
Approval is sought to transfer £1.836 million into the 2027/2028 Capital
programme.   
Leisure and Culture Transformation Fund 
The specification and content of the Improvements to Accessibility / Wi-Fi
Accessibility project have expanded with a broader scope than was originally
thought possible, following the rollout of a new front of house system in SLLC
properties.  However, due to the complex nature of the systems integration and
the different logistical requirements across the various locations, additional costs
are required to take the project to completion.   
Alongside this, consideration has been given to the Lifeguard Technology
project.  SLLC have confirmed that this project is not viable at this time due to
the availability of expertise and suitable suppliers.  It is proposed that £0.010m
of the budget be retained for feasibility costs to continue to explore options for
this project in the longer term, and that the remaining budget of £0.390 million to
be reallocated to the Improvements to Accessibility / Wi-Fi Accessibility project. 
£0.121m 
(£7.183m) 
(£3.341m) 
(£1.836m) 
(£0.390m)
£0.390m 
Minor Adjustments (£0.023m)  
TOTAL ADJUSTMENTS (£11.335m) 
43

Page 44

APPENDIX D 
SOUTH LANARKSHIRE COUNCIL       
CAPITAL EXPENDITURE 2026/27      
GENERAL FUND PROGRAMME 
FOR PERIOD 1 APRIL 2026 TO 10 JULY 2026 
£m  
Total Base Budget (including carry forward from 2025/2026)  108.952 
Proposed Adjustments – Period 2 0.550  
Proposed Adjustments – Period 4 (11.335)  
Total Revised Budget  98.167   
2026/27 
Budget 
Period 2
Proposed
Adjustments
Period 4
Proposed
Adjustments
Revised 
2026/27 
Budget 
Resource  £m £m £m £m
Community & Enterprise 79.571 0.031 (11.335) 68.267
Education 15.297 - - 15.297
Finance & Corporate 0.498 - - 0.498
Housing & Technical 13.086 0.519 - 13.605
Social Work 0.500 - - 0.500
TOTAL CAPITAL
PROGRAMME
108.952 0.550 (11.335) 98.167 
44

Page 45

APPENDIX D 
SOUTH LANARKSHIRE COUNCIL        
CAPITAL EXPENDITURE 2026/27      
GENERAL FUND PROGRAMME 
FOR PERIOD 1 APRIL 2026 TO 10 JULY 2026 
Resource Name 
Annual
Budget
£000 
2024/25
C/F
£000
Profiling
/Adjs
£000
Total
Original
Budget
£000 
Proposed
Adjs
£000 
Proposed
Slippage
£000 
Total
Budget
£000 
Forecast
Spend
£000 
Forecast
Variance
£000 
Actual
£000
Community & Enterprise 
Facs, Waste &
Grounds
1,400 1,039 914 3,353 31 (23) 3,361 3,361 0 180 
Enterprise &  
Sustainable Dev
45,439 5,036 (3,297) 47,178 0 (12,360) 34,818 34,818 0 2,265
Roads, Transport
& Fleet
23,000 2,326 3,714 29,040 1,048 0 30,088 30,088 0 2,682
Resource 
Total
69,839 8,401 1,331 79,571 1,079 (12,383) 68,267 68,267  0 5,127           
Education
Growth /
Accommodation
Pressures
12,346 890 (2,469) 10,767 0 0 10,767 10,767 0 72
ICT
Developments
2,400 20 2,100 4,520 0 0 4,520 4,520 0 688
Free School
Meals
0 55 (45) 10 0 0 10 10 0 0
Resource 
Total
14,746 965 (414) 15,297 0 0 15,297 15,297 0 760           
Finance & Corporate
IT Services 400 48 50 498 0 0 498 498 0 (3)
Resource 
Total  400  48  50  498  0  0  498  498  0  (3)           
Housing & Technical
Office Accom 19,262 745 (8,522) 11,485 0 0 11,485 11,485 0 276
Private Housing
Scheme of
Assistance
1,000 0 (1,000) 0 0 0 0 0 0 0
Other Housing 0 269 1,332 1,601 519 0 2,120 2,120 0 217
Resource 
Total
20,262 1,014 (8,190) 13,086 519 0 13,605 13,605 0 493  
Social Work
SWIS Plus 0 (286) 786 500 0 0 500 500 0 4
Resource Total  0    (286)  786  500  0  0  500  500  0  4           
Overall Total 105,247 10,142 (6,437) 108,952 1,598 (12,383) 98,167 98,167  0 6,381 
45

Page 46

APPENDIX E 
SOUTH LANARKSHIRE COUNCIL       
CAPITAL EXPENDITURE 2026/27       
GENERAL FUND PROGRAMME 
FOR PERIOD 1 APRIL 2026 TO 10 JULY 2026 
2026/27
Original
Estimate
inc C/F 
2026/27
Revised
Budget 
2026/27
Forecast
Spend 
2026/27
Forecast
Variance 
2026/27
Actual to
10/07/26      
Expenditure £m £m £m £m £m      
General Fund Programme 108.952 98.167 98.167 - 6.381       
Income
2026/27
Budget
2026/27
Revised
Budget  
2026/27
Actual
To
10/07/26         
£m         £m   £m
Prudential Borrowing 54.520 45.501   0.000
Developers Contributions 1.775 1.775   0.000
Partners  3.071 4.150   0.984
Scottish Government:     
- Capital Grant 25.982 25.959   7.366
Levelling Up Fund 4.196 4.196   2.440
Capital Receipts 4.500 4.500   0.025
Specific Reserves 9.438 6.616   0.000
Revenue Contribution 5.470     5.470   0.000      
TOTAL FUNDING 108.952 98.167   10.815 
46

Page 47

Appendix F
(Page 1)
GENERAL FUND CAPITAL PROGRAMME 2026/2027 
BUILD EXECUTIVE SUMMARY 
PERIOD ENDED 10 JULY 2026 (PERIOD 4)
Expenditure Periods 
1 2 3 4 5 6 7 8 9 10 11 12 13 14
Programme Status               
Projects Complete  - 5 6 9 - - - - - - - - - -
Projects on Programme  - 75 79 104 - - - - - - - - - -
Projects Behind
Programme 
- 0 2 0 - - - - - - - - - -
Projects Altered Brief/
Programme 
- 0 2 0 - - - - - - - - - -
Projects Held  - 8 8 10 - - - - - - - - - - 
- 86 97 123 0 0 0 0 0 0 0 0 0 0               
Project Status               
Design Feasibility  - 50 58 81 - - - - - - - - - -
Sketch Design  - 0 0 0 - - - - - - - - - -
Detailed Design  - 1 0 0 - - - - - - - - - -
Production Information  - 3 6 6 - - - - - - - - - -
Tendering  - 13 11 9 - - - - - - - - - -
On Site  - 14 16 18 - - - - - - - - - -
Complete  - 5 6 9 - - - - - - - - - - 
- 86 97 123 0 0 0 0 0 0 0 0 0 0 
47

Page 48

Appendix F
(Page 2)
General Services Capital Programme 2026/2027 
Build Variance Explanations 
Project Name Status Variance Explanation
- - - 
48

Page 49

Appendix G
(Page 1) 
GENERAL FUND CAPITAL PROGRAMME 2026/2027                     
NON-BUILD EXECUTIVE SUMMARY 
PERIOD ENDED 10 JULY (PERIOD 4) 
Expenditure Periods 
1 2 3 4 5 6 7 8 9 10 11 12 13 14               
Number of Projects           
Carried Forward 25/26
Programme - - - 22                         
Approved from 26/27
Programme - - - 24                         
Total Projects Currently
Reported - - - 46                         
Number of Projects                           
Projects Completed - - - 0                         
Projects Ahead of
Programme - - - 0                         
Projects on Programme - - - 46                         
Projects Behind
Programme - - - 0         
Projects, Altered
Brief/Programme - - - 0                         
Projects On Hold  - - - 0                         
- - - 46           
49

Page 50

General Services Capital Programme 2026/2027                             Appendix G
Non-Build Executive Summary – Project Status                                       (Page 2) 
Project Status
SLLC - Booking and Admission System On programme
Philipshill Cemetery - Extension On programme
Ash Die Back On programme
Chatelherault Allotments - Allers Carpark On Programme
Alexander Hamilton Memorial Park – Woodland Management On Programme
Nature Restoration Fund On programme
Renewal of Play Parks On programme
Glenaffeoch Road Play Area On programme
Tree Planting On programme
Headstone Remedial Works On programme
Clyde Walkway repairs On programme
Country parks upgrades On programme
Three Rivers / Clydesdale Way On programme
Country Parks Masterplan On programme
Calderglen Country Park - Pump Track On programme
Hamilton Palace Sports Ground – Outdoor Facilities On programme
Outdoor Investment – Asset Investment On programme
Outdoor Investment – Community Spaces On programme
Energy Efficiency Measures Feasibility TACT Hall On programme
Roads Depot EV Chargers On programme
Beat the Street  On programme
Primary School Re-usable  Drink System On programme
Shawfield Remediation and Development On programme
SLC Industrial Infrastructure - Energy Efficiency (Cathcart Road) On programme
Carnwath Community and Business Enterprise HUB On programme
Clyde Gateway On programme
Delivering and Enabling Commercial Space On programme
Clyde Cycle Park On programme
Business Grant Retrofit On programme
Council Business Centres On programme
Burgh Business Centre On programme
East Kilbride Town Centre Masterplan On programme
Hamilton Town Centre Masterplan On programme
Langlands West On programme
Hamilton Junctions Improvement On programme
M74 Works On programme
Schools ICT On programme
Education Digital Futures On programme
Visual Equipment On programme
IT Infrastructure Refresh On programme
Electronic Document Records Management System - Phase 2 On programme
Audio Visual Upgrade On programme
50

Page 51

Public Switch Telephone Network / Alarms (Analogue to Digital) On programme
SLC Website upgrade  On programme
Care Experienced Young People: Accommodation (The Promise) On programme
Central Energy Efficiency Fund  On programme 
51

Page 52

Appendix H
(Page 1) 
GENERAL SERVICES CAPITAL PROGRAMME 2026/2027 
ROADS EXECUTIVE SUMMARY 
PERIOD ENDED 10 JULY 2026 (PERIOD 4)                             
1 2 3 4 5 6 7 8 9 10 11 12 13              
Number of Projects             
Total Projects Currently Reported - - - 293 - -  - - - - - - -              
Programme Status             
Projects Complete - - - 29 - - - - - - - - -              
Projects on Programme - - - 264 - -   - - - - - - -              
Projects Behind Programme - - - 0 - -     - - - - - - -              
Projects, Altered Brief / Programme - - - 0 - - - - - - - - -              
Projects Still to Commence - - - 0 - - - - - - - - -               
- - - 293 - - - - - - - - -              
Project Status             
Briefing - - - 102 - - - - - - - - -              
Production Information - - - 135 - - - - - - - - -              
Billing - - - 0 - - - - - - - - -              
Tendering - - - 3 - - - - - - - - -              
On Site - - - 24 - - - - - - - - -              
Complete - - - 29 - - - - - - - - -               
- - - 293 - -  - - - - - - - 
52

Page 53

Appendix H
(Page 2) 
General Services Capital Programme 2026/2027 
Roads Variance Explanations 
Project Name Status Variance Explanation
- - - 
53

Page 54

SOUTH LANARKSHIRE COUNCIL
RESOURCE: ENTERPRISE, ROADS & TRANSPORTATION SERVICES 2026/27
PROJECT / PROGRAMME STATUS ~ PERIOD 4
Briefing
/ Program
m
e
Production
Inform
ation
Billing
Tendering
On
Site
Com
plete
Projects Com
plete
Projects on
Program
m
e
Projects Behind
Program
m
e
Projects altered
Brief /
Program
m
e
Projects Held
ROADS / FOOTWAYS INVESTMENT PROGRAMME
East Kilbride, Rutherglen and Cambuslang Areas
Strategic Infrastructure
Ashkirk Road, Strathaven 1 1
Hunterlees Road, Glassford 1 1
Glen Tanner, East Kilbride 1 1
Dunblane Drive, East Kilbride 1 1
Bishops Park, Thorntonhall 1 1
Somervell Street, Cambuslang 1 1
Dale Avenue, Cambuslang 1 1
Greenbank Street, Rutherglen 1 1
Cruachan Road, Cambuslang 1 1
Cedar Drive and Cedar Place, East Kilbride 1 1
Blacklaw Drive (and defective area on High Common Road) 1 1
Mount Cameron Drive South, East Kilbride 1 1
Young Place, East Kilbride 1 1
Langlands Drive, East Kilbride 1 1
Cathcart Road, Rutherglen 1 1
B7086, Lesmahagow Road, Strathaven 1 1
Stewartfield Drive, East Kilbride 1 1
Greenhills Road, East Kilbride 1 1
Hudson Terrace and Hudson Way & Winnipeg Drive, East Kilbride 1 1
Lavender Drive, East Kilbride 1 1
Springburn Place, College Milton Ind Estate, East Kilbride 1 1
Busby Road, Carmunnock 1 1
Lindsayfield Road, East Kilbride 1 1
Kittochside Road, East Kilbride 1 1
Whitefield Avenue, Rutherglen 1 1
Braemar Road, Rutherglen 1 1
Kirkriggs Gardens, Rutherglen 1 1
Johnstone Drive, Rutherglen 1 1
Bradda Avenue, Rutherglen 1 1
Kirktonholme Road, East Kilbride 1 1
Hayhill Road, Thorntonhall 1 1
Hawbank Road 1 1
B743 (Muirkirk Road), Strathaven 1 1
B743 (Muirkirk Road), Strathaven 1 1
Eaglesham Road, Jackton 1 1
Quarry Road, East Kilbride 1 1
Eaglesham Road, East Kilbride 1 1
Lickprivick Road, East Kilbride 1 1
Eden Drive, East Kilbride 1 1
Burnside Highway, Glassford 1 1
Singer Road, East Kilbride 1 1
Sydney Place, East Kilbride 1 1
PROJECT STATUS PROGRAMME STATUS
Project Title
54

Page 55

SOUTH LANARKSHIRE COUNCIL
RESOURCE: ENTERPRISE, ROADS & TRANSPORTATION SERVICES 2026/27
PROJECT / PROGRAMME STATUS ~ PERIOD 4
Briefing
/ Program
m
e
Production
Inform
ation
Billing
Tendering
On
Site
Com
plete
Projects Com
plete
Projects on
Program
m
e
Projects Behind
Program
m
e
Projects altered
Brief /
Program
m
e
Projects Held
PROJECT STATUS PROGRAMME STATUS
Project Title
Alberta Avenue, East Kilbride 1 1
Seymour Green, East Kilbride 1 1
Franklin Place, East Kilbride 1 1
Cullen Lane and Cullen Road, East Kilbride 1 1
Halfmerk South 1 1
Car Parking Area at Highrise Flats - Globe and Pheonix Courts, EK 1 1
Preventative Maintenance
A726 ~ Torrance RAB to Crutherland Highway 1 1
A726 ~ Shawton Highway to (near) 29 Glasgow Road 1 1
A726 ~ Mounthilly Road to Hapton Craggs 1 1
Langlands Road, Auldhouse (Rural Section) 1 1
Hurlawcrook Road, East Kilbride 1 1
SD Preparatory Patching 1 1
Strategic Patching and Minor Asset Improvements
MP Cairns Road, Cambuslang 1 1
MP Bogleshole Road, Cambuslang 1 1
MP Stonelaw Road, Rutherglen 1 1
MP Westburn Road, Cambuslang 1 1
MP Buchandyke Road 1 1
MP Laurel Court, East Kilbride 1 1
MP Pine Court, East Kilbride 1 1
MP Cornwall Street 1 1
MP Halfmerk South and part of Halfmerk North 1 1
MP St Leonards Road 1 1
MP Nithsdale 1 1
MP Maxwellton Avenue 1 1
MP Ness Drive 1 1
Loch Long 1 1
Allendale 1 1
A749 Kingsway 1 1
Teesdale 1 1
Logi Park 1 1
Sycamore Crescent, East Kilbride 1 1
Sycamore Crescent, East Kilbride 1 1
Sycamore Crescent, East Kilbride 1 1
Sycamore Crescent, East Kilbride 1 1
Sycamore Court, East Kilbride 1 1
Pine Court, East Kilbride, East Kilbride 1 1
Barbana Road, East Kilbride 1 1
Maple Grove, East Kilbride 1 1
Freeland Land, East Kilbride 1 1
Denholm Green, East Kilbride 1 1
55

Page 56

SOUTH LANARKSHIRE COUNCIL
RESOURCE: ENTERPRISE, ROADS & TRANSPORTATION SERVICES 2026/27
PROJECT / PROGRAMME STATUS ~ PERIOD 4
Briefing
/ Program
m
e
Production
Inform
ation
Billing
Tendering
On
Site
Com
plete
Projects Com
plete
Projects on
Program
m
e
Projects Behind
Program
m
e
Projects altered
Brief /
Program
m
e
Projects Held
PROJECT STATUS PROGRAMME STATUS
Project Title
Hastings, East Kilbride 1 1
Nerston Road, East Kilbride 1 1
Bell Green West, East Kilbride 1 1
Kent Place, East Kilbride 1 1
East Greenlees Crescent 1 1
Stonelaw Road 1 1
Main Street, Rutherglen 1 1
Springfield Park Road 1 1
Bankhead Road 1 1
Vicarland Road 1 1
East Kilbride Road 1 1
Westburn Road 1 1
Old Mill Road 1 1
Rosaburn Avenue, East Kilbride 1 1
Oaklands, Strathaven 1 1
B745 (i) 1 1
B745 (ii) 1 1
Footway Schemes
Cruachan Road, Rutherglen (incl kerbing) 1 1
Stonelaw Road, Rutherglen 1 1
B7086 Lesmahagow Road, Strathaven 1 1
Hamilton Road, Cambuslang 1 1
Glen Clova, East Kilbride 1 1
Stewartfield Road, East Kilbride 1 1
Nithsdale, East Kilbride 1 1
Saskatoon Place, East Kilbride 1 1
Ayton Park North 1 1
Green Street, Strathaven 1 1
Hamilton Area
Strategic Infrastructure
A72 Lanark Road - Rosebank to Overton Road 1 1
Central Avenue, Blantyre Ind Est. 1 1
Hume Drive / Knockburnie Road / Ailsa Drive, Kirkfield Rd, Bothwell 1 1
Janefield Place, Blantyre 1 1
Laighlands Road, Bothwell 1 1
Woodhead Crescent, Hamilton 1 1
Wellcroft Terrace, Hamilton 1 1
Portland Place, Hamilton 1 1
Annabella Road, Netherburn 1 1
Meikle Earnock Road, Hamilton 1 1
Almada Street (Eastbound and Westbound Carriageway), Hamilton 1 1
Muir Street, Hamilton 1 1
Sydes Brae, High Blantyre 1 156

Page 57

SOUTH LANARKSHIRE COUNCIL
RESOURCE: ENTERPRISE, ROADS & TRANSPORTATION SERVICES 2026/27
PROJECT / PROGRAMME STATUS ~ PERIOD 4
Briefing
/ Program
m
e
Production
Inform
ation
Billing
Tendering
On
Site
Com
plete
Projects Com
plete
Projects on
Program
m
e
Projects Behind
Program
m
e
Projects altered
Brief /
Program
m
e
Projects Held
PROJECT STATUS PROGRAMME STATUS
Project Title
Annsfield Road, Hamilton 1 1
Woodhead Crescent, Hamilton 1 1
Fallside Road, Bothwell 1 1
Chriss Avenue, Hamilton 1 1
Plotcock Road, Quarter - Phase 2 1 1
A71 Ayr Road, Stonehouse 1 1
Keith Street Car Park, Hamilton 1 1
Haddow Street, Hamilton 1 1
Downie Street, Hamilton 1 1
Five Ways Road, Netherburn 1 1
Kirk Street, Stonehouse phase 1 1 1
Bothwell Road Service Roads, Hamilton 1 1
Forrest Street, Blantyre 1 1
Spital Road (phase 2), Stonehouse 1 1
Preventative Maintenance
Newhousemill Road, Hamilton (Phase 2) 1 1
Newhousemill Road, Hamilton (Phase 2) (Prepatory patching (Hand) 1 1
Candermill and Marlage Phase 2 Prepatory Works 1 1
Calderside Road Preparatory Works 1 1
Prep Patching 1 1
Strategic Patching and Minor Asset Improvements
A72 Lanark Road - Advanced Preparatory Works 1 1
Udston Mill Road, Stonehouse 1 1
Riverside Gardens, Larkhall 1 1
Argyle Street, Stonehouse 1 1
Hillhouse Road, Hamilton 1 1
Aitken Road, Hamilton 1 1
Bothwell Road, Hamilton 1 1
Blantyre Farm Road/ Dalcraig Crescent Roundabout, Blantyre 1 1
Farm Court/ Fallside Road Roundabout, Bothwell 1 1
Castle Avenue, Uddingston 1 1
Hillhouse Road, Hamilton 1 1
Quarry Street, Hamilton 1 1
Union Street, Larkhall 1 1
Broomelton Road, Larkhall 1 1
Meikle Earnock Road 1 1
Bellshill Road, Uddingston 1 1
Carscallan Road, Hamilton (Verge Scrape back) 1 1
Ayr Road, Shawsburn (Verge Scrape Back) 1 1
Minor Permanent Repairs 1 1
57

Page 58

SOUTH LANARKSHIRE COUNCIL
RESOURCE: ENTERPRISE, ROADS & TRANSPORTATION SERVICES 2026/27
PROJECT / PROGRAMME STATUS ~ PERIOD 4
Briefing
/ Program
m
e
Production
Inform
ation
Billing
Tendering
On
Site
Com
plete
Projects Com
plete
Projects on
Program
m
e
Projects Behind
Program
m
e
Projects altered
Brief /
Program
m
e
Projects Held
PROJECT STATUS PROGRAMME STATUS
Project Title
Footway Schemes
Janefield Place, Blantyre 1 1
Chantinghall Road, Hamilton 1 1
Berkley Drive, Blantyre 1 1
Sycamore Drive, Hamilton 1 1
Bryan Street, Hamilton 1 1
Maple Drive, Larkhall 1 1
Balmoral Gardens, Blantyre 1 1
Clydesdale Area
Strategic Infrastructure
A70 Pretsmill 1 1
Abbeygreen Road, Lesmahagow 1 1
B7018 Kirkfieldbank 1 1
A702 Elvanfoot 1 1
Teiglum Road, Lesmahagow 1 1
A721 Newbigging 1 1
A73 Duneaton 1 1
A72 Hazelbank 1 1
Stanmore Road, Lanark 1 1
A706 Cleghorn Road, Lanark 1 1
Old Lanark Road, Caluke 1 1
B7016 Libberton 1 1
A70 Carnwath 1 1
A70 Douglas 1 1
Millstone Park, Biggar 1 1
B740 Crawfordjohn 1 1
B7078 Carlisle Road, Blackwood/Kirkmuirhill 1 1
B7078 Carlisle Road, Draffan 1 1
Millrig Road, Wiston 1 1
B7040 Leadhills 1 1
B7078 Cairn Lodge Services 1 1
Smylum Road, Lanark 1 1
A73 Lee Wood 1 1
A73 Tesco Carluke 1 1
Strategic Infrastructure - Drainage Schemes
B7078 Carlisle Road, Lesmahagow 1 1
A70 Parisholm 1 1
B7086 Auchenheath 1 1
A73 Hyndford Road 1 1
A73 Roberton 1 1
New Kayes Road, Auchenheath 1 1
58

Page 59

SOUTH LANARKSHIRE COUNCIL
RESOURCE: ENTERPRISE, ROADS & TRANSPORTATION SERVICES 2026/27
PROJECT / PROGRAMME STATUS ~ PERIOD 4
Briefing
/ Program
m
e
Production
Inform
ation
Billing
Tendering
On
Site
Com
plete
Projects Com
plete
Projects on
Program
m
e
Projects Behind
Program
m
e
Projects altered
Brief /
Program
m
e
Projects Held
PROJECT STATUS PROGRAMME STATUS
Project Title
Preventative Maintenance
A70 Lang Whang, Carnwath 1 1
Roberton Back Road, Biggar 1 1
A706 Harelaw to Forth, Forth 1 1
B7055 Wiston, Biggar 1 1
C1 Mauldslie Road, Carluke 1 1
A721 Carnwath Road, Carluke 1 1
B740, Crawfordjohn 1 1
B7078, Abington 1 1
New Trows Road, Lesmahagow 1 1
A721 Carluke to Carstairs 1 1
Prep patching 1 1
Strategic Patching and Minor Asset Improvements
Craigenhill Road, Kilncadzow 1 1
Meadowflatts Road, thankerton 1 1
A721 Carnwath Road, Carluke 1 1
A73 Hyndrord Road, Lanark 1 1
A70 Hyndford Road, Hyndford 1 1
Woodstock Road, Lanark 1 1
Lesmahagow Road, Boghead 1 1
A73 Cloburn Quarry access, Lanark 1 1
A70 Carnwath Main Street 1 1
B7086 Lanark Road, Auchenheath 1 1
Footway Schemes
A70 Carnwath 1 1
A70 Carstairs 1 1
Southfield Road, Blackwood 1 1
Stanmore Crescent, Lanark 1 1
Hyndshaw Road, Law 1 1
North Avenue, Carluke 1 1
A73 Westport, Lanark 1 1
Carlisle Road, Crawford 1 1
East Kilbride, Rutherglen, Cambuslang, Hamilton and Clydesdale Areas
Strategic Gulley/Drainage Maintenance ~ Various locations 1 1
East Kilbride, Rutherglen, Cambuslang, Hamilton and Clydesdale Areas
Road Signs ~ Clean/Refurbishment/Repair ~ various Locations 1 1
East Kilbride, Rutherglen, Cambuslang, Hamilton and Clydesdale Areas
Strategic Road Restraint Systems ~ Various Locations 1 1
59

Page 60

SOUTH LANARKSHIRE COUNCIL
RESOURCE: ENTERPRISE, ROADS & TRANSPORTATION SERVICES 2026/27
PROJECT / PROGRAMME STATUS ~ PERIOD 4
Briefing
/ Program
m
e
Production
Inform
ation
Billing
Tendering
On
Site
Com
plete
Projects Com
plete
Projects on
Program
m
e
Projects Behind
Program
m
e
Projects altered
Brief /
Program
m
e
Projects Held
PROJECT STATUS PROGRAMME STATUS
Project Title
East Kilbride, Rutherglen, Cambuslang, Hamilton and Clydesdale Areas
Unerpass Refurbashment ~ various Locations 1 1
Traffic & Transportation and Lighting ~ Roads Refurbishment
Structures
Bothwell Bridge, Hamilton ~ Scour Protection Works inc Bagging works 1 1
A71/10 Glassford Bridge, Painting and refurbishment works 1 1
Bridge joint replacement programme 1 1
B7078/06 Milton Bridge, Lesmahagow - Targeted parapet repairs 1 1
Hapturnal Bridge - Abutment and deck repairs with new parapet 1 1
A73/16 Cartland Bridge - Containment upgrade/refurb options appraisal 1 1
Traffic
Vehcle Activated Signs ~ Various locations 1 1
Traffic Signals ~ Main St / Castle Street, Rutherglen 1 1
Minor Works ~ Various locations 1 1
Flood Risk Management
Culvert Inlet Trash Screen Replacement Programme   1 1
Strategic Culvert Survey and Investigation Programme    1 1
Construction of Flood Exceedance Route & associated works - Coulter 1 1
Road Drainage Upgrade Works - Overton Road, Halfway 1 1
Reservoir Asset Upgrade Works - James Hamilton Heritage Loch, EK 1 1
Lighting Unit
Contractor Columnn Replacement 1 1
Column Structural Testing 1 1
Construction Unit Column / cable installs 1 1
Removal of failed columns (red) from structural testing 1 1
Investigation of deteriorated electrical circuits 1 1
Strathclyde Partnership for Transport
Bus Route Congestion
Bent Road / Dixon Street ~ Jct improvements 1 1
Casualty Reduction Measures
Funding combined with the Road safety 1 1
Bus Infrastructure Improvements
Installation of High Access Kerbs, Glasgow Road 1 1
Installation of HAK ~ Union St and Burnbank Rd 1 1
Abington Bus Hub
Feasability report to be prepared 1 1
60

Page 61

SOUTH LANARKSHIRE COUNCIL
RESOURCE: ENTERPRISE, ROADS & TRANSPORTATION SERVICES 2026/27
PROJECT / PROGRAMME STATUS ~ PERIOD 4
Briefing
/ Program
m
e
Production
Inform
ation
Billing
Tendering
On
Site
Com
plete
Projects Com
plete
Projects on
Program
m
e
Projects Behind
Program
m
e
Projects altered
Brief /
Program
m
e
Projects Held
PROJECT STATUS PROGRAMME STATUS
Project Title
Transport Scotland
Tier 1 ~ Active Travel Infrastructre Works (works Cont 2025/26)
Hairmyres P&R ~ Active Travel Works 1 1
NCN75 ~ Phases 2 1 1
Strathaven Road, East Kilbride ~ Phase 1 1 1
Tier 1 ~ Active Travel Infrastructre Works
Strathaven Road, East Kilbride Phase 2 1 1
Works to upgrade East Kilbride underpasses 1 1
NCN75 ~ Phases 3 1 1
Bogleshole Road, Cambuslang connection to Clyde Cycle Park 1 1
Bothwell to Uddingston Footpath widening 1 1
Udston Road ~ Pedestrian crossing 1 1
High Blantyre Road/ Russell Street ~ Pedestrian crossing 1 1
Local Authority Direct Award
Think Move Breathe scheme 1 1
School Travel Plan / road safety resources 1 1
Scraping back of footways and cycle routes 1 1
Clyde Cycle Centre 1 1
Road safety awareness vehicle 1 1
Road Safety Improvement Fund (Draft ~ Projects to be confirmed)
A70, Douglas ~ M74 J12 n/bound off ramp 1 1
A70, Glespin to Council boundary 1 1
A721, Newbigging to Elsrickle 1 1
A702, Council boundary to M74 Jct 14 1 1
B7086, Strathaven to Kirkmuirhill 1 1
B7078, M74 Jct 10 to M74 Jct 11 1 1
B743, Strathaven to council boundary 1 1
A70, B7078 Jct to Rigside 1 1
B758, Blantyre Farm Road, Blantyre to Uddingston 1 1
B7078, Canderside to Blackwood 1 1
Newhousemill Road at Bridge, East Kilbride 1 1
Harsh Braking sites ~ Various locations 1 1
Community Bus Fund
Lanark Interchange 1 1
Flood Management Infrastructure
Eastfield, Muirbank, Halfway SWMPs 1 1
Hamilton Surface Water Management Plan 1 1
Rutherglen Road, Shawfield - Flood Risk Assessment (Consultant) 1 1
Council and Other Funding
Council Investment Funding
Safer Routes ~ Stonelaw Road, Rutherglen 1 1
Lanark Interchange 1 1
Cycling Scotland ~ Cycle Shelters at Schools 1 1
61

Page 62

SOUTH LANARKSHIRE COUNCIL
RESOURCE: ENTERPRISE, ROADS & TRANSPORTATION SERVICES 2026/27
PROJECT / PROGRAMME STATUS ~ PERIOD 4
Briefing
/ Program
m
e
Production
Inform
ation
Billing
Tendering
On
Site
Com
plete
Projects Com
plete
Projects on
Program
m
e
Projects Behind
Program
m
e
Projects altered
Brief /
Program
m
e
Projects Held
PROJECT STATUS PROGRAMME STATUS
Project Title
City Deal
Cathkin Relief Road (Claims/Comp works) 1 1
Stewartfield Way 1 1
Greenhills / Strathaven Road (Claims) 1 1
M74 Jct 7 on-slip 1 1
Hamilton Junctions 1 1
Total 102 135 0 3 24 29 29 264 0 0 0
62

Page 63

Report
Agenda Item 
Report to: Financial Resources Scrutiny Forum
Date of Meeting: 27 August 2026
Report by: Executive Director (Finance and Corporate Resources)  
Subject: Capital Budget Monitoring 2026/2027 - Housing Capital
Programme 
1. Purpose of Report
1.1. The purpose of the report is to:
[purpose]
 update members of the Financial Resources Scrutiny Forum of progress on the
Council’s Housing Capital Programme for the period covering 1 April 2026 to 10 July
2026. 
[1purpose]
2. Recommendation(s)
2.1. The Forum is asked to approve the following recommendation:
[recs]
(1) that the physical and financial progress of the Housing Capital Programme be
noted. 
[1recs]
3. Background
3.1. The Capital reports attached provide detail on the position as at 10 July 2026 from both
a financial and physical perspective.   
3.2. Appendix A shows the financial position of the Housing Capital Programme, with the
physical progress detailed in Appendix B. 
4. 2026/2027 Housing Capital Programme 
4.1. 2026/2027 Budget:  The total Housing Capital Programme for the year is £94.740 million
as approved by the Executive Committee on 24 June 2026.  This includes carry forward
of £1.958 million from the 2025/2026 financial year. 
4.2. The Scottish Government revised our Affordable Housing grant allocation for 2026/2027.
This has been increased by £2.310 million and will increase the number of Open Market
Purchases made in 2026/2027. 
4.3. The budget is also increased by a transfer of funds from the General Fund’s Climate
Emergency Fund (£0.038 million) for projects that will be managed as part of the Housing
Programme. 
4.4. Programmed funding for the year also totals £94.740 million.  The budget, along with a
detailed breakdown of the funding sources is included in Appendix A to this report.   
4.5. 2026/2027 Forecast:  As noted in 4.1, the total capital spending programme for the
year is £94.740 million.  Current estimates from the Resource have identified an outturn
of £94.740 million for the year. 
6
63

Page 64

4.6. 2026/2027 Actual Position:  Spend to 10 July 2026 on the Housing Capital
Programme amounts to £12.603 million.   
4.7. As at 10 July 2026, £12.603 million of funding had been received. 
5. Employee Implications
5.1. There are no employee implications as a result of this report. 
6. Financial Implications 
6.1. The financial implications are detailed in section 4 of this report. 
7. Climate Change, Sustainability and Environmental Implications
7.1. There are no implications for climate change, sustainability or the environment in terms
of the information contained in this report. 
8. Risk and Other Implications
8.1. The main risk associated with the Council’s Capital Programme is an overspend.  The
risk has been assessed as low given the detailed project management plans prepared
and monitored for each project.  The risk of overspend is managed through four weekly
Investment management meetings. 
9. Integrated Impact Assessment and Consultation Requirements
9.1. This report does not introduce a new policy, function or strategy or recommend a
change to existing policy, function or strategy and therefore no impact assessment is
required. 
9.2. There was also no requirement to undertake any consultation in terms of the information
contained in this report. 
Jackie Taylor
Executive Director (Finance and Corporate Resources) 
10 August 2026 
Link(s) to Council Values/Priorities/Outcomes
 Accountable, Effective, Efficient and Transparent 
Previous References
 South Lanarkshire Council. 25 February 2026
 Executive Committee, 24 June 2026 
List of Background Papers 
 Capital Ledger prints to 10 July 2026 
Contact for Further Information
If you would like to inspect the background papers or want further information, please contact:
Lorraine O’Hagan, Head of Finance (Strategy)
Ext:  2601 (Tel:  01698 452601)
E-mail:  lorraine.o’hagan@southlanarkshire.gov.uk 
64

Page 65

APPENDIX A 
SOUTH LANARKSHIRE COUNCIL       
CAPITAL EXPENDITURE 2026/2027       
HOUSING PROGRAMME 
FOR PERIOD 1 APRIL 2026 TO 10 JULY 2026 
2026/27
Annual
Budget 
2026/27
Forecast
Spend
2026/27
Forecast
Variance
2026/27
Actual to
10/07/26 
£m £m £m £m
Expenditure 
2026/27 Budget  94.740  94.740  -  12.603     
2026/27
Annual
Budget  
2026/27
Actual to
10/07/26 
£m   £m     
Income         
Capital Funded from Current Revenue 33.851   3.493
Capital Receipts -   0.093
Prudential Borrowing 33.385   5.962
Scottish Government Specific Grant:    
- New Build 18.474   2.919
- Open Market Purchase Scheme 8.910   -
- Mortgage to Rent 0.120   0.081
Other Income -   0.055 
94.740   12.603 
65

Page 66

Appendix B
(Page 1)
HOUSING CAPITAL PROGRAMME 2026/2027
EXECUTIVE SUMMARY
PERIOD ENDED 10 JULY 2026
Expenditure Periods 
1 2 3 4 5 6 7 8 9 10 11 12 13 14               
Programme Status               
Projects Complete  - 3 3 6 - - - - - - - - - -               
Projects on Programme - 76 79 72 - - - - - - -      - - -               
Projects Behind
Programme 
- 2 3 2 - - - - - - - - - -               
Projects Altered
Brief/Programme
- 3 2 5 - - - - - - - - - -               
Projects Held  - 15 15 18 - - - - - - - - - - 
- 99 102 103 0 0 0 0 0 0 0 0 0 0               
Project Status              
Design Feasibility  - 39 33 32 - - - - - - - - - -               
Sketch Design  - 2 2 2 - - - - - - - - - -               
Detailed Design  - 0 0 0 - - - - - - - - - -               
Production Information - 9 9 7 - - - - - - -     - - -               
Tendering - 18 18 19 - - - - - - - - - -               
On Site  - 28 37 37 - - - - - - - - - -               
Complete - 3 3 6 - - - - - - - - - -               
- 99 102 103 0 0 0 0 0 0 0 0 0 0 
66

Page 67

Appendix B
(Page 2) 
Housing Capital Programme 2026/2027 
Build Variance Explanations 
Project Name Status Variance Explanation
4 & 12 Strathcona House, EK - Replacement of
Doors with Assisted Access 
Behind Programme Awaiting delivery date of
replacement doors being confirmed. 
Bike Storage Facility at Calderwood Multis  Behind Programme One storage unit remains
outstanding with a location issue
being resolved. 
67

Page 68

1 2 3 4 5 6 7 8 9 10 11 12 13 14
Original Budget 26/27 0.000 3.302 9.762 16.221 22.681 29.140 35.600 42.060 48.519 54.979 61.438 67.898 78.663 94.740
Revised Budget 26/27 0.000 3.302 9.762 16.221 22.681 29.140 35.600 42.060 48.519 54.979 61.438 67.898 78.663 94.740
Actual 26/27 0.000 3.617 9.592 12.603 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
0.000
10.000
20.000
30.000
40.000
50.000
60.000
70.000
80.000
90.000
100.000
£ Millions
HRA Capital Expenditure Profile Graph 26/27
68

Page 69

Report
Agenda Item 
To: Financial Resources Scrutiny Forum
Date of Meeting: 27 August 2026
Prepared By: Executive Director (Finance and Corporate Resources)  
Subject: Revenue Budget Year-End 2025/2026 
1. Purpose of Report
1.1. The purpose of the report is to:-
[purpose]
 advise the Forum of the overall financial position of the Council’s General Fund
Revenue Account and Housing Revenue Account for the period 1 April 2025 to
31 March 2026 
2. Recommendation(s)
2.1. The Forum is asked to approve the following recommendation(s):- 
(1) that across Resources, Corporate Items, Loan Charges and Council Tax, the
Council is showing a year-end underspend of £3.131 million after proposed
Transfers to Reserves (Section 4 and Appendix 1), be noted;
(2) that increase in the Probable Outturn Transfers to Reserves to £60.206 million
(previously £58.026 million) (Appendix 3), be noted;
(3) that the additional year-end Transfers to Reserves totalling £1.886 million
(Appendix 4), be noted; 
(4) that the additional non-recurring underspend of £1.356 million in the delegated
budget to the IJB be held in Reserves for their use in future years (sections
4.13), be noted;
(5) that the proposed use of £3.131 million underspend for 2025/2026 as set out in
section 4.22, be noted;
(6) that this results in a breakeven position for the Council for 2025/2026 (section
4.23), be noted; and
(7) that the breakeven position on the Housing Revenue Account (Section 5), be
noted. 
3. Background
3.1. This overview report will summarise the 2025/2026 year-end position for the Council’s
General Fund Revenue Account and Housing Revenue Account.   
3.2. Section 4 details the final position for the financial year, as well as the movement from
the previously reported Probable Outturn position for the Council. The Housing
Revenue position is shown in Section 5. 
3.3. Appendix 1 to the report details the overall spend position for the current year. This
position includes new proposed Transfers to Reserves since the Probable Outturn was
approved.  The Transfers to Reserves approved at Probable Outturn (Executive
Committee, 4 February 2026) are shown in Appendix 3 for reference, along with some
changes to these transfers to reflect final spend achieved during the year.   
7
69

Page 70

3.4. There are also some new Transfers to Reserves proposed at the end of the year, and
these are shown in Appendix 4.  This includes proposals for the overall underspend of
£3.131 million outlined in Appendix 1. 
4. 2025/2026 General Services Year End Position 
4.1. This report and appendices provide a detailed analysis of the Council’s financial
position.  A summary position including the key highlights is detailed in sections 4.3 –
4.21 with the full detail included in Appendix 2. 
4.2. For reference, the Council’s overall Probable Outturn after approved Transfers to
Reserves was a forecast break-even (Executive Committee, 4 February 2026).   
4.3. The year-end outturn position is showing an underspend of £3.131 million. This is after
proposed Transfers to Reserves at year-end.  Table 1 shows the movement from the
Probable Outturn break-even position to the underspend position of £3.131 million at
financial year-end which includes new proposed Transfers to Reserves at the year-
end.     
Table 1 – General Services Year-End 2025/2026 
Probable
Outturn
Including
Approved
Transfers
£m
Year-End
Before
New
Proposed
Transfers
£m
Movement
from
Probable to 
Year-End
£m
Year-End
Proposed
Transfers 
£m
Year-End
After
Transfers 
£m
Community and Enterprise Resources 
(4.6 – 4.7)
0.348 1.438 1.090 (1.091) 0.347
Education Resources (4.8 – 4.9) 0.000 1.189 1.189 (1.189) 0.000
Finance and Corporate Resources (4.10) 0.578 0.674 0.096 (0.096) 0.578
Housing and Technical Resources (4.11) 0.000 0.000 0.000 0.000 0.000
Social Work Resources (4.12 – 4.16) 0.000 1.047 1.047 (1.047) 0.000
Joint Boards (4.17) 0.000 0.000 0.000 0.000 0.000
Resources Underspend 2025/2026 0.926 4.348 3.422 (3.423) 0.925      
Loan Charges (section 4.18) 2.101 4.006 1.905 0.000 4.006
Corporate Items (section 4.19 – 4.20) 0.422 2.308 1.886 (0.635) 1.673
Council Tax (section 4.21) 0.130 0.114 (0.016) (0.008) 0.106
PO Transfer to Reserves (3.579) (3.579) 0.000 0.000 (3.579)
Total Underspend 2025/2026 0.000 7.197 7.197 (4.066) 3.131 
4.4. This report and appendices provide a detailed analysis of the Council’s financial
position at the end of financial year 2025/2026.  Appendix 1 shows the position in full,
including the outturn before and after transfers to reserves.  A summary is included in
sections 4.5 to 4.21 which details the movement from the Probable Outturn, with the
detail across spend areas included in Appendix 2.   
4.5. Resources: As covered in Table 1, Resources are reporting a combined underspend
position of £0.925 million.  This position across Resources is after £3.423 million of
additional proposed Transfers to Reserves.  These are detailed in Appendices 3 and
4.  A summary of each Resource is provided below with the detail included in Appendix
2.  
70

Page 71

4.6. Community and Enterprise Resources are showing a year end underspend of
£1.438 million after their previously approved Transfers to Reserves.  The Resource
are proposing that the Transfers to Reserves approved at Probable Outturn are
increased to reflect the to the anticipated timing of spend and are shown in Appendix
3.  The underspend is made up of a number of variances including increased fee
income for Planning and Building Standards (£0.5 million), increased turnover of staff
within Regeneration, Support and Facility Services (£0.4 million) and reduced
materials costs within Roads Construction (£1.4 million). These are partially offset by
increased vehicle leasing (£0.4 million), and casual hire costs (£0.2 million) within
Waste and Grounds Services, increased plant and equipment costs within Grounds
(£0.7 million) and reduced income for works within Roads Construction (£0.2 million). 
4.7. In addition, new Transfers to Reserves are proposed for the increased lease costs for
Waste Services Vehicles moving forward (£0.605 million) and funds to support
planned IT Developments in Planning and Building Standards (£0.100m).  This would
take the Resource to an underspend of £0.347 million, which is in line with their
Probable Outturn. 
4.8. Education Resources are showing a year-end underspend position of £1.189
million after their previously approved Transfers to Reserves.  This mainly relates to
underspends on specific funding including Pupil Equity Fund, Additional Support for
Learning and schools’ Devolved Management Scheme budgets.   
4.9. The Resource are proposing new Transfers to Reserves which include an increase to
the previously approved Transfers and are shown in Appendix 3.  In addition, further
Transfers to Reserves are requested to support ASN adaptations (£0.125 million), and
which would take place next financial year, and also for funding from schools’
Devolved Management Scheme (£0.325 million) which can be carried forward in line
with the scheme.  Taking account of these year-end transfers would leave the
Resources in a break-even position, which is in line with their Probable Outturn. 
4.10. Finance and Corporate Resources are showing an underspend of £0.674 million
after previously approved Transfers to Reserves.  Additional Transfers to Reserves
are proposed at the year-end for Discretionary Housing Payment (DHP) funding that
was received later in the year, and which can be carried forward to spend next year
(£0.081 million) and for Place Based funding committed for projects in 2026/2027
(£0.015 million).  After these Transfers to Reserves, the Resource position would be
an underspend of £0.578 million.  This is in line with their Probable Outturn position. 
4.11. Housing and Technical Resources are showing a breakeven position after the
previously approved Transfers to Reserves.  The year-end position includes a £0.373
million underspend in relation to an element of the Resource budget delegated to the
Integrated Joint Board (IJB) for the Centralised Adaptations Service for aids and
adaptations, which is based on Social Work assessments. It is proposed that this
underspend of £0.373 million be retained by the IJB within their reserves earmarked
for future costs.  After this commitment, the year-end position is break-even, which is
in line with the Resource’s Probable Outturn position. 
4.12. Social Work Resources is showing a year-end underspend of £1.047 million after
previously approved Transfers to Reserves / commitments. 
4.13. The Adults and Older People position at the year-end also includes a further £0.983
million commitment in relation to the element of the budget delegated to the IJB – this
is effectively a further underspend on the delegated budget, and mainly reflects
71

Page 72

admissions to hospital and long-term care being greater than new services called on
and the financial impact of the finalisation of financial assessments for new and
existing service users. These are partially offset by employee turnover being less than
assumed and increased spend in Telecare due to demand. It is proposed that this
additional non-recurring underspend of £0.983 million also be retained by the IJB
within their reserves earmarked for future costs.  Including the £0.373 million for aids
and adaptations outlined in section 4.11, this takes the total additional amount being
proposed to be retained by the IJB to £1.356 million. 
4.14. The Social Work Resources non-delegated Services position is showing an
underspend of £1.047 million after previously approved Transfers to Reserves.  This
is mainly due to reduced costs for anticipated residential placements, lower than
anticipated costs of respite and increased turnover in staff across the Services.  At
year-end, a Transfer to Reserves is requested for residual pressures within the
Children and Families Service which are anticipated to continue into 2026/2027 while
the budget recovery plan continues to be implemented.  The year-end Transfer to
Reserves would take the non-delegated budget to break even, in line with their
Probable Outturn. 
4.15. The Resources’ Approved Probable Outturn Transfers to Reserves are shown in
Appendix 3 with their additional Proposed Transfers at year-end shown in Appendix
4). 
4.16. Joint Boards: There is a break-even position within Joint Boards in relation to the
requisition budgets. The Probable Outturn position was break-even. 
4.17. Loan Charges: There is an underspend of £4.006 million after the Transfers to
Reserves approved at Probable Outturn (Appendix 3). The underspend is an improved
position of £1.905 million from the £2.101 million reported at Probable Outturn and
reflects the level of deposit interest received in year being greater than anticipated, as
well as the benefit of interest on Revenue Balances. 
4.18. Corporate Items: There is an underspend at year end of £2.308 million, after taking
into account approved Transfers to Reserves.  This is a movement of £1.886 million
which reflects recent confirmation of the date the new pension contributions were to
be applied (£1.200 million), and 2025/2026 investment monies to be carried forward
for commitments in 2026/2027 (£0.566 million).  These are covered further in Appendix
2. 
4.19. Two year-end Transfers to Reserves are proposed from the Corporate Items budget. 
These are for 2025/2026 investment monies noted above, to be carried forward
(£0.566 million) to complete the programmes of work, and Fairer Futures funding
received (£0.069 million) that was unable to spend before the end of the financial year
and is committed for supporting the development of the new children’s service plan
and a performance framework.  This takes the Corporate Items position to an
underspend of £1.672 million.   
4.20. Council Tax: The over recovery for the year, after the transfer to the HRA reserve in
line with the approved Council Tax Second Homes Policy (100% surcharge), is £0.106
million, representing a minor adverse movement of £0.024 million since the Probable
Outturn. 
4.21. Summary and Proposals:  As noted in Table 1, within section 4.3, there is an overall
underspend of £3.131 million. This year-end underspend of £3.131 million is after
72

Page 73

adjustments to the Transfers to Reserves approved at Probable Outturn (Appendix 3),
and the new proposals detailed in Appendix 4. 
4.22. In terms of this £3.131 million, the following is proposed: 
 that £1.000 million of the underspend be transferred to reserves to allow the
Council to provide financial support to contribute towards the response to
questions posed by the Marmot initiative.  The NHS and the IJB have already set
aside funds of £2.000 million each. This additional £1.000 million will allow the
Council to match these monies (as we have a previous amount of £1.000 million
in Reserves agreed at Probable Outturn) and contribute towards the cost of
taking forward activity to progress Marmot findings including any required staffing
and implementation costs
 that an allocation of £0.030 million be Transferred to Reserves for commitments
in Youth, Family and Community Learning Services in 2026/2027
 that an amount of £1.000 million be Transferred to Reserves and set aside to
fund the Local Government Elections into 2027/2028
 that the remaining £1.101 million underspend be Transferred to Reserves to
support future year’s budget strategies 
4.23. This proposal, agreed at the Executive Committee (24 June 2026), resulted in these
monies being transferred to Reserves and resulting in the Council returning a break-
even position for financial year 2025/2026. 
4.24. Year-end Accounting Adjustments:  As part of the year-end process, expenditure
is reviewed to identify whether it is Revenue or Capital spend.  Any spend that should
be classed as Capital has been removed from these monitoring figures.  This has no
impact on the bottom-line position of the Resources. 
5. Housing Revenue Account Year-End 2025/20256
5.1. As at 31 March 2026, the Housing Revenue Account (HRA) is a showing a break-even
position. 
5.2. This break-even position is after a transfer from the HRA Reserve of £3.988 million.
This Transfer from Reserves is £0.375 million less than the Probable Outturn Transfer
from Reserves of £4.363 million.  The main reasons for this reduction are increased
income from house rents, less than anticipated void rent loss and the less than
anticipated Loan Charges reflecting the level of deposit interest received in year being
greater than anticipated, as well as the benefit of interest on Revenue Balances. 
5.3. These are partially offset by the planned drawdown from reserves for the
implementation costs associated with the new Housing Management system which
went live in early 2026, One Housing.  As a result of the underspends mentioned
above, this spend can now be accommodated within the overall outturn, without
increasing the use of reserves. 
5.4. The details of the variances across the HRA are shown in Appendix 5. 
6. Employee Implications
6.1. None. 
7. Financial Implications
7.1. As detailed in sections 4 and 5 of the report.  
73

Page 74

8. Climate Change, Sustainability and Environmental Implications
8.1. There are no implications for climate change, sustainability or the environment in terms
of the information contained in this report. 
9. Risk and Other Implications
9.1. The main risk associated with the Council’s Revenue Budget is that there is an
overspend.  The risk has been assessed as low given the detailed budget
management applied across the Resources.  The risk is managed through four weekly
Budget Monitoring Meetings at which any variance is analysed. In addition, the
Probable Outturn exercise ensures early warning for corrective action to be taken
where appropriate. 
9.2. There are no implications for sustainability in terms of the information contained in this
report. 
10. Integrated Impact Assessment and Consultation Requirements
10.1. This report does not introduce a new policy, function or strategy or recommend a
change to an existing policy, function or strategy and, therefore, no impact assessment
is required.   
10.2. There is also no requirement to undertake any consultation in terms of the information
contained in this report. 
Jackie Taylor
Executive Director (Finance and Corporate Resources) 
10 August 2026 
Link(s) to Council Values/Priorities/Outcomes
 Accountable, Effective, Efficient and Transparent 
Previous References
 Executive Committee, 4 February 2026 
List of Background Papers
 Financial Ledger and budget monitoring results to 31 March 2026 
Contact for Further Information
If you would like to inspect the background papers or want further information, please
contact:- 
Lorraine O'Hagan, Head of Finance (Strategy)
Ext:  5637 (Tel:  01698 455637)
E-mail: lorraine.o'hagan@southlanarkshire.gov.uk 
74

Page 75

Appendix 1 
75

Page 76

Appendix 2 
Detail of Year-End Position Across Resources and Centrally Held Budgets 
1. Community and Enterprise Resources are showing a year end underspend of £1.438
million after their previously approved Transfers to Reserves.  This reflects increased
fee income for Planning and Building Standards (£0.5 million), increased turnover of
staff within Regeneration, Support and Facility Services (£0.4 million) and reduced
materials costs within Roads Construction (£1.4 million). These are partially offset by
increased vehicle leasing (£0.4 million), and casual hire costs (£0.2 million) within Waste
and Grounds Services, increased plant and equipment costs within Grounds (£0.7
million) and reduced income for works within Roads Construction (£0.2 million). 
The Resource are proposing that the Transfers to Reserves approved at Probable
Outturn are increased to reflect the to the anticipated timing of spend: spend on Front
Line First (£0.046 million), contributions to the Strategic Waste Fund for planned works
(£0.275 million) and works to upgrade air conditioning for Refuse Collection Vehicles
(£0.065 million).  In addition, new Transfers to Reserves are proposed for the increased
lease costs for Waste Services Vehicles moving forward (£0.605 million) and funds to
support planned IT Developments in Planning and Building Standards (£0.100m).   
The Resource is showing an underspend of £0.347 million after proposed Transfers to
Reserves, in line with the Probable Outturn position. 
2. Education Resources are showing a year-end underspend position of £1.189 million
after their previously approved Transfers to Reserves. This mainly relates to
underspends on specific funding including Pupil Equity Fund, Additional Support for
Learning and schools’ Devolved Management Scheme budgets.  The Resource are
proposing an increase to the previously approved Transfers to Reserves for these areas
as spend will be incurred by the end of the school year, but which falls into financial year
2026/2027.  Also, a Transfer to Reserves is requested for funding from schools’
Devolved Management Scheme (£0.325 million) which can be carried forward in line
with the scheme.   
The overall Resource position allows a further transfer requested to support ASN
adaptations required following recent inspection outcomes, and which would take place
next financial year.  This totals £0.125 million and is included in Appendix 3. 
3. Finance and Corporate Resources are showing an underspend of £0.674 million
including previously approved Transfers to Reserves. This mainly relates to
underspends on specific funding including Discretionary Housing Payments that was
received later in the year, and which can be carried forward to spend next year (£0.081
million) and Place Based funding (£0.015 million) which is committed for expenditure in
2026/2027 and have been included as proposed transfer to reserves.  Taking these into
account leave the Resource position as an underspend of £0.578 million.  This is in line
with the Probable Outturn position.  
76

Page 77

4. Housing and Technical Resources are showing a breakeven position after the
previously approved Transfers to Reserves for the First Stop Accommodation project
within Homelessness service.  Underspends in Property Services is mainly due to
reduced grants for disabled adaptations, and which is offsetting overspends in Housing
Services mainly due to reduced rental income than forecast within Homelessness and
increased utilities costs.  As noted above, the year-end position includes a £0.373
million underspend in relation to an element of the Resource budget delegated to the
Integrated Joint Board (IJB) for the Centralised Adaptations Service for aids and
adaptations, which is based on Social Work assessments. It is proposed that this non-
recurring underspend of £0.373 million be retained by the IJB within their reserves
earmarked for future costs.  After this commitment, the year-end position is break-even,
which is in line with the Resource’s Probable Outturn position.   
5. Social Work Resources are showing a year-end underspend of £1.047 million
including the previously approved Transfers to Reserves.  This is an improvement of
£1.047 million since the Probable Outturn. 
Within this is the Adults and Older People budget which is delegated to the Integrated
Joint Board (IJB) and includes already approved Transfers to Reserves.  It also includes
a £2.745 million commitment in relation to the element of the budget delegated to the
IJB – this is effectively an underspend on the delegated budget. 
It was approved at Probable Outturn that the IJB retain £1.762 million within their
reserves for use in future years.  The commitment of £2.475 million noted above is an
increase of £0.983 million from the Probable Outturn position.  This is mainly due to
admissions to hospital and long-term care being greater than new services called on
and the financial impact of the finalisation of financial assessments for new and existing
service users. These are partially offset by employee turnover being less than assumed
and increased spend in Telecare due to demand.  It is proposed that the additional non-
recurring underspend of £0.983 million also be retained by the IJB within their reserves
earmarked for future costs. 
The Social Work Resources non-delegated Services is an underspend of £1.047 million
including approved Transfers to Reserves.  This is mainly due to reduced costs for
anticipated residential placements, lower than anticipated costs of respite and increased
turnover in staff across the Services.  It is proposed that the underspend of £1.047
million be Transferred to Reserves for residual pressures within Children and Families
Service which are anticipated to continue into 2026/2027, while the budget recovery
plan continues to be implemented.   
6. Joint Boards: There is a break-even position within Joint Boards in relation to the
requisition budgets. The Probable Outturn position was break-even. 
7. Loan Charges:  There is an underspend of £4.006 million after the Transfers to
Reserves approved at Probable Outturn (Appendix 3), an additional £1.905 million
since Probable Outturn. This reflects the level of deposit interest received in year being
greater than anticipated, as well as the benefit of interest on Revenue Balances. 
8. Corporate Items: There is a net underspend at year end of £2.308 million, after taking
into account previously approved Transfers to Reserves.  This is a movement of £1.886
million (from the underspend of £0.422 million at Probable Outturn) and mainly reflects
notable movements in relation to superannuation commitments (£1.2 million), and
2025/2026 investment monies to be carried forward (£0.566 million). Detail is shown in
Table 1.
77

Page 78

Table 1: Movements in Corporate Items Since Probable Outturn 
£m
Superannuation Accrual
Monies accrued on the balance sheet in 2024/2025 are no longer
required in 2025/2026 as the superannuation increase to 17.5% has been
implemented from the first full pay in 2026/2027. 
1.231
2025/2026 Investments
Funding allocated to 2025/2026 Investments projects will be required in
2026/2027. This relates to committed staffing costs for Fly Tipping
(£0.121m) and Local Action Fund projects (£0.445m) that will be included
in the 2026/2027 Capital Programme mainly in relation to play parks
projects. This is included as a proposed transfer to reserves. 
0.566
Bad Debt Provision
Movements in specific provisions across Resources has had a favourable
impact on the Corporate Bad Debt Provision budget in 2025/2026. 
0.129
Additional Procurement Savings
A further underspend of £0.100 million has materialised in relation to
procurement savings approved for 2026/2027 but that were achieved
earlier than planned (in 2025/2026). 
0.100
Fairer Futures Funding
Funding received that was unable to spend before the end of the financial
year and is committed for supporting the development of the new
children’s service plan and a performance framework. This is included as
a proposed transfer to reserves. 
0.069
Centre West Rates
Centre West rates bills for 2025/2026 from January to March have been
accounted for as the Council are liable for these while the Centre is back
in Council possession and being demolished. 
(0.111)
Other Minor Movements  (0.099)
Further Underspend since Probable Outturn 1.885 
Two year-end Transfers to Reserves are proposed.  These are for 2025/2026
investment monies to be carried forward (£0.566 million) to complete the programmes of
work, and Fairer Futures funding received (£0.069 million) that was unable to spend
before the end of the financial year and is committed for supporting the development of
the new children’s service plan and a performance framework.  This takes the Corporate
Items position to an underspend of £1.672 million.   
9. Council Tax including Council Tax Reduction Scheme (CTRS):  An over recovery of
£0.314 million in 2025/2026 before Transfers to Reserves is a minor adverse movement
of £0.016 million since the Probable Outturn. An increased Transfer to Reserves is
proposed from that approved at Probable Outturn in relation to income from Second
Homes which should be transferred to the HRA in line with the approved Council Tax
Second Homes Policy (100% Surcharge) (£0.008 million).   
78

Page 79

Appendix 3
Transfers to Reserves – Included in the Probable Outturn 
Purpose / Description Resource  Value
£m
Resources  
Strategic Waste Fund
Due to timing of spend on Waste projects, funding is required to be carried forward to in the Strategic Waste
Fund to support future spend on Waste. 
Community
and Enterprise
0.150
Air Condition for Refuse Collection Vehicles
Due to timing of expenditure on the retro fitting of air condition units within older refuse collection vehicles,
funding is required to be carried forward to next financial year.
Community
and Enterprise
0.080
Operational IT handheld devices
Due to the timing of procurement of handheld devices for Grounds and Streets staff in line with IT
development upgrades, funding is required to be carried forward to next financial year.
Community
and Enterprise
0.100
Front Line First
Funding received as part of 2025/2026 Investment funding is required to be carried forward to reflect the
profile of spend this year and within the overall three-year delivery programme.  
Community
and Enterprise
0.438
Local Plan
Annual contribution for future years costs associated with 2026/2027 Local Plan.
Community
and Enterprise
0.100
Local Growth Fund Transition
Through utilising external funding received in-year, an underspend in core Council funding will be carried
forward to maintain service levels into 2026/2027.
Community
and Enterprise
0.200
Fleet Sinking Fund 
Annual contribution to the Fleet sinking fund to maintain the asset replacement programme.
Community
and Enterprise
0.050
Total Community and Enterprise Resources Transfers at Probable Outturn   1.118
Adjust: Increase / (Decrease) in transfers to reflect spend during the year  0.386
Total Community and Enterprise Resources Transfers at Year End  1.504
PEF
The funding received from the Government can be used up to the end of the school term (June 2026). The
underspend reflects the element of the funding that will be utilised in April to June 2026.
Education 0.400
Additional Support for Learning
Sourcing and purchasing Additional Support for Learning equipment for schools that will be utilised in April
to June 2026.
Education 0.078
Total Education Resources Transfers at Probable Outturn   0.478
Adjust: Increase / (Decrease) in transfers to reflect spend during the year  0.739
Total Education Resources Transfers at Year End  1.217
Insurance Fund
A contribution to manage the anticipated increase in insurance premiums paid from the Fund.
Finance and
Corporate
0.300
Total Finance and Corporate Resources Transfers at Probable Outturn   0.300
First Stop Temporary Accommodation
The use of the in-year underspend to be set aside for the First Stop Accommodation project as planned
(Executive Committee, November 2025).
Housing and
Technical
0.123
Total Housing and Technical Resources Transfers at Probable Outturn  0.123
Children and Families Pressures
The transfer of one-off funding from the IJB due to reduced pension contributions has realised an
underspend which will be carried forward to support the pressures in Children and Families until the Budget
Recovery Plan is fully achieved.
Social Work 3.095
Transformational Residential Care
An in-year underspend is proposed as a contribution to transformational residential care in future years.
Social Work 0.500
The Promise
An in-year underspend in the IJB is proposed as a contribution to The Promise, to further augment the
support for young people transitioning from Children and Family Services to Adult Services over the
following two years.
Social Work 0.750
Total Social Work Resources Transfers at Probable Outturn  4.345
Adjust: Increase / (Decrease) in transfers to reflect spend during the year  1.047
Total Social Work Resources Transfers at Year End  5.392   
Total Resource Transfers to Reserves at Probable Outturn  6.364
Adjust: Increase / (Decrease) in transfers to reflect spend during the year  2.172
Total Resources Transfers at Year End  8.536   
Loans Charges  
Loans Charges
Funding to be utilised in future years in line with borrowing for service concession arrangements.  This will
be required to be drawn down from 2027/2028 (as approved at South Lanarkshire Council, January 2023).
Loans Charges 0.358
Total Loans Charges Transfer at Probable Outturn  0.358 
79

Page 80

Appendix 3 (cont) 
Corporate Items  
Service Concessions
Underspend arising due to a change in interest rates and indexation since the initial calculations were
undertaken, has meant that the estimated savings previously anticipated in 2028/2029 are available earlier.
Corporate
Items
4.388
Pay Award
Underspend carried forward from 2025/2026 as a result of Teachers pay award being implemented in line
with the school year.
Corporate
Items
3.987
Packaging Extended Producer Responsibility (PEPR) Staffing
Profiling of spend on waste project staffing costs in future years.
Corporate
Items
0.545
Central Energy Efficiency Fund (CEEF)
Resources are allocated funding from the CEEF Reserve to pay for spend to save projects which they repay
over future years from the revenue savings generated by the project. This transfer represents the payback
of savings from Resources and allows the Reserve to be regenerated for use on future projects.
Corporate
Items
0.297
Renewable Head Incentive (RHI) and Feed In Tariff (FIT)
Income from RHI and FIT is received in-year and will be set aside for funding future capital spend. 
0.200
Total Corporate Items Transfers at Probable Outturn  9.417
Council Tax  
Council Tax Second Homes Policy (100% Surcharge)
Income of £0.200m should be transferred to the Housing Revenue Account in line with the Council’s second
homes policy.
HRA 0.200
Total Council Tax Transfers at Probable Outturn  0.200
Adjust: Increase / (Decrease) in transfers to reflect spend during the year  0.008
Total Council Tax Transfer at Year End  0.208 
Previously Approved Transfers to Reserves  
Loans Fund Review
(An underspend of £13.349 million is anticipated in the Loans Fund Budget in 2025/2026.  This budget
underspend of £13.349 million will be set aside and used against the Budget Gap in 2027/2028 as planned
(detailed in the Executive Committee report, June 2025).
Loans Fund (T/f
to Reserves)
13.349
Investments 
The total budget line 2025/2026 Investments – Transfers to Reserves is £13.859 million (£10.263 million
one-off Revenue investments not required this year and the underspend in Loan Charges of £3.596
million).  It is proposed that these two amounts (£10.263 million and £3.596 million) be transferred to
Reserves at the end of the year (detailed in the Executive Committee report, June 2025).
Investments (T/f
to Reserves)
13.859
Teachers Numbers
As there is no longer a need to restore teacher numbers to the higher level, this budget line can be
transferred to reserves.  Given the budget pressures resulting from the higher than budgeted pay award, it is
recommended that consideration be given to using the £4.2 million to support the Budget Strategy – with a
view to setting this aside for Pay Award (detailed in the Executive Committee report, August 2025
Teachers
Numbers (T/f to
Reserves)
4.200
Waste and Recycling Services
The November Executive Committee agreed that £2.5 million of core monies released by pEPR funding will
be retained within Community and Enterprise Resources and utilised towards one-off investment in waste
and recycling services.  It is anticipated that £0.3 million will be spent by the end of 2025/2026.  As a result,
£2.2 million has been transferred to earmarked reserves for use in future years (detailed in the Executive
Committee report, December 2025).
Waste (T/f to
Reserves)
2.200
Budget Strategy
The November Executive Committee agreed that £4.5 million of core monies released by pEPR funding will
be used to support the Council’s Budget Gap.  This will be transferred to earmarked reserves for use in
future years (detailed in the Executive Committee report, December 2025).
Budget Strategy
(T/f to
Reserves)
4.500
Total Approved Transfers to Reserves  38.108 
Additional Transfers to Reserves – Use of Outturn Underspend  
Marmot Initiative 
Use of £1.000 million underspend to allow the Council to provide financial support to contribute towards the
response to questions posed by the Marmot initiative.
Use of Outturn
Underspend
1.000
Winter Wishes 
Use of £0.040 million underspend to support the continuation of the Winter Wishes programme within
Children and Families in 2026/2027.
Use of Outturn
Underspend
0.040
Commercial Feasibility 
Use of £0.100 million underspend for Commercial Feasibility costs.
Use of Outturn
Underspend
0.100
Third Sector 
Use of £0.400 million underspend to support the findings of the Third Sector to contribute to the external
medium grants allocation available for the next two years beyond 2026/2027.
Use of Outturn
Underspend
0.400
Budget Strategy
Use of £2.039 million underspend for budget considerations in future years.
Use of Outturn
Underspend
2.039
Total Additional Transfers to Reserves – Use of Outturn Underspend  3.579 
Total Transfers to Reserves at Year End: 
Total Transfers to Reserves Approved at Probable Outturn  58.026
Adjust: Increase / (Decrease) in transfers to reflect spend during the year  2.180
Total Transfers to Reserves at Year End  60.206 
80

Page 81

Appendix 3 (cont) 
The increase in transfers to reflect changes in spend since Probable Outturn is shown below: 
Purpose / Description Resource  Value
£m
Resources
Strategic Waste Fund
Due to timing of spend on Waste projects, funding is required to be carried forward to in the Strategic Waste
Fund to support future spend on Waste. 
Community
and Enterprise
0.275
Air Condition for Refuse Collection Vehicles
Due to timing of expenditure on the retro fitting of air condition units within older refuse collection vehicles,
funding is required to be carried forward to next financial year.
Community
and Enterprise
0.065
Front Line First
Funding received as part of 2025/2026 Investment funding is required to be carried forward to reflect the
profile of spend this year and within the overall three-year delivery programme.  
Community
and Enterprise
0.046
Total Community and Enterprise Resources  0.386
PEF
The funding received from the Government can be used up to the end of the school term (June 2026). The
underspend reflects the element of the funding that will be utilised in April to June 2026.
Education 0.253
Additional Support for Learning
Due to the timing of spend that was originally in the probable outturn assumptions, additional funding is
required to be carried forward for sourcing and purchasing Additional Support for Learning equipment for
schools that will be utilised in April to June 2026.
Education 0.486
Total Education Resources 0.739
Children and Families Pressures
It is proposed that the Service underspend be carried forward to support the pressures in Children and
Families until the Budget Recovery Plan is fully achieved.
Social Work 1.047
Total Social Work Resources 1.047
Total Resource Proposed Transfers to Reserves at Year-End  2.172   
Council Tax  
Council Tax Second Homes Policy (100% Surcharge)
Income of should be transferred to the Housing Revenue Account in line with the Council’s second homes
policy.
HRA 0.008
Total Council Tax Transfers at Year End  0.008
Total Increase in Already Approved Transfers to Reserves  2.180 
81

Page 82

Appendix 4
Transfers to Reserves – Additional Proposed Transfers at Year-End 
Purpose / Description Resource  Value
£m
Resources
Wast Services RCVs
Funding required to support additional leasing costs for RCVs within Waste Services into next year.
Community
and Enterprise
0.605
IT Developments
Funding for planned investment for IT development upgrades to planning and building standards
performance systems. 
Community
and Enterprise
0.100
Total Community and Enterprise Resources  0.705
ASN Adaptations
Funding required to support ASN adaptations next financial year to support service delivery demands. 
Education 0.125
Equipment Replacement Fund
Funding from schools’ Devolved Management Scheme being carried forward to allow spend across the
academic year and to allow schools to support capital equipment requirements over a number of years.
Education 0.325
Total Education Resources 0.450
DHP Funding
Transfer for DHP funding received later in the year, that was unable to spend before the end of the financial
year and will be spent in 2026/2027.
Finance and
Corporate 
0.081
Place Based Funding
Transfer for Council Place Based funding committed for projects in 2026/2027 with funding allocated to
specific areas. 
Finance and
Corporate 
0.015
Total Finance and Corporate Resources 0.096
Total Resource Proposed Transfers to Reserves at Year End  1.251   
Corporate Items  
2025/2026 Investments
Funding required to meet the obligations of the 2025/2026 investment commitments in relation to Local
Action Fund (£0.445m) and Fly Tipping (£0.121m).
Investments
(T/f to
Reserves)
0.566
Fairer Futures Funding
Transfer for additional funding received that was unable to spend before the end of the financial year and is
committed for supporting the development of the new children’s service plan and a performance framework. 
Education  0.069
Total Corporate Items Transfers to Reserves at Year End  0.635
Total Proposed Transfers to Reserves at Year End  1.886 
Final Transfers resulting in a Break Even (section 4.20)  
Marmot Initiative 
Use of £1.000 million underspend (in addition to £1.000 million approved at Probable Outturn) to allow the
Council to provide financial support to contribute towards the response to questions posed by the Marmot
initiative.
Use of Outturn
Underspend
1.000
Youth, Family and Community Learning
Allocation of £0.030 million for commitments in Youth, Family and Community Learning Services in
2026/2027.
Use of Outturn
Underspend
0.030
Local Government Elections
Amount of £1.000 million be set aside to fund the Local Government Elections into 2027/2028.
Use of Outturn
Underspend
1.000
Budget Strategy
Use of £1.101 million underspend to support future year’s budget strategies.
Use of Outturn
Underspend
1.101
Total Final Transfers to Reserves – Use of Outturn Underspend  3.131 
82

Page 83

Appendix 5 
Variance Explanations 
1. The underspend in employee costs is due to vacancies within the service that continue to be actively recruited. 
2. The underspend is due to the net effect of underspends in void rent loss, utility costs and ground maintenance charges partially offset
by greater than budgeted expenditure on fixture and fittings and contract cleaning costs. 
3. The planned overspend reflects anticipated spend on the implementation of the new One Housing system. It was initially anticipated
that this would be funded by an additional use of reserves, however this spend can now be accommodated within the overall outturn. 
4. Income is over recovered mainly due to greater than anticipated house rents as a result of the number of buy backs in year. 
5. The transfer to reserves is lower than budgeted reflecting the net effect of the variances noted. 
6. The underspend is due to the level of deposit interest received in year being greater than anticipated, as well as the benefit of interest
on Revenue Balances. 
Revised Projected Projected Actual Variance Under / % Note
Annual Outturn Outturn 31/03/26 31/03/26 (Over) Variance
Budget Variance
Budget Category £m £m £m £m £m
Employee Costs 15.360 15.295 0.065 15.267 0.093 Under 0.61% 1
Property Costs 62.592 62.420 0.172 62.115 0.477 Under 0.76% 2
Supplies and Services 0.405 0.477 (0.072) 0.427 (0.022) Over -5.43%
Transport and Plant 0.195 0.213 (0.018) 0.193 0.002 Under 1.03%
Administration 5.604 5.537 0.067 5.577 0.027 Under 0.48%
Payment to Other Bodies 12.590 12.981 (0.391) 14.098 (1.508) Over -11.98% 3
Payment to Contractors 0.422 0.422 0.000 0.484 (0.062) Over -14.69%
Transfer Payments 0.000 0.000 0.000 0.000 0.000 - 0.00%
Financing Charges 26.133 26.164 (0.031) 25.985 0.148 Under 0.57%
Total Controllable Exp. 123.301 123.509 (0.208) 124.146 (0.845) Under -0.69%
Total Controllable Inc. (133.819) (133.740) (0.079) (134.150) 0.331
Over
Recovered 0.25% 4
Transfer to/(from) Balance Sheet (4.076) (4.363) 0.287 (3.988) (0.088)
Under
Recovered -2.16% 5
Net Controllable Exp. (14.594) (14.594) 0.000 (13.992) (0.602) Over -4.12%
Loan Charges 14.594 14.594 0.000 13.992 0.602 Under 4.12% 6
Net Controllable Exp. 0.000 0.000 0.000 0.000 0.000 - 0.00%
SOUTH LANARKSHIRE COUNCIL
Revenue Budget Monitoring Report
Period Ended 31 March 2026 (No.14)
Housing Revenue Account
83

Page 84

84

Page 85

Report
Agenda Item 
Report to: Financial Resources Scrutiny Forum
Date of Meeting: 27 August 2026
Report by: Executive Director (Finance and Corporate Resources)  
Subject: Revenue Budget 2025/2026 - Detailed Resource
Analysis 
1. Purpose of Report
1.1. The purpose of the report is to:
[purpose]
 update members of the Financial Resources Scrutiny Forum on the Council’s
revenue budget for 2025/2026.
[1purpose]
2. Recommendation(s)
2.1. The Forum is asked to approve the following recommendation(s):
[recs]
(1) that the 2025/2026 detailed financial analysis for each of the individual
Resources and the Housing Revenue Account, be noted. 
[1recs]
3. Background
3.1. The individual reports attached provide detailed information on each of the Resource
Revenue Budgets for the period to 31 March 2026. The detailed papers cover the
General Services and also the Housing Revenue Account. 
3.2. The following information is provided for each Resource and the Housing Revenue
Account: 
 An Executive Summary showing the top-level position.
 Details of the most significant variances across Subjective headings and across
Services.
 A line-by-line trend analysis of the total Resource expenditure and income across
Subjective headings. 
3.3. These are shown in Appendices A to F attached. 
4. Employee Implications
4.1. None 
5. Financial Implications
5.1. As detailed in each of the individual Resource papers. 
6. Climate Change, Sustainability and Environmental Implications
6.1. There are no implications for climate change, sustainability, or the environment in
terms of the information contained in this report.   
8
85

Page 86

7. Risk and Other Implications
7.1. The main risk associated with the Council’s Revenue Budget is that there is an
overspend. The risk has been assessed as low given the detailed budget
management applied across the Resources. The risk is managed through four
weekly Budget Monitoring Meetings at which any variance is analysed. In addition,
the probable outturn exercise ensures early warning for corrective action to be taken
where appropriate. 
8. Integrated Impact Assessment and Consultation Requirements
8.1. This report does not introduce a new policy, function or strategy or recommend a
change to an existing policy, function, or strategy and therefore no impact
assessment is required.   
8.2. There is also no requirement to undertake any consultation in terms of the
information contained in this report. 
Jackie Taylor
Executive Director (Finance and Corporate Resources) 
10 August 2026 
Link(s) to Council Values/Priorities/Outcomes
 Accountable, Effective, Efficient and Transparent 
Previous References
 None 
List of Background Papers
 Revenue Ledger prints to 31 March 2026 
Contact for Further Information
If you would like to inspect the background papers or want further information, please
contact:
Lorraine O'Hagan, Head of Finance (Strategy)
Ext:  5637 (Tel:  01698 455637)
E-mail: lorraine.o'hagan@southlanarkshire.gov.uk 
86

Page 87

Appendix A
South Lanarkshire Council Revenue
Budget Monitoring Statement
Period Ended 31 March 2026 (No 14)
Community and Enterprise Resources
Committee 
Service Departments :-
Revised
Annual
Budget 
£m 
Projected
Outturn 
£m 
Projected
Outturn
Variance 
£m
Actual
to Period 14
31/03/26
Before
Transfers
£m
Variance
to Period 14
31/03/26 
£m
%
Facilities, Waste and Grounds 79.970  79.208  0.762 79.508 0.462 0.58%
Leisure and Culture 20.048  20.020  0.028 20.048 0.000 0.00%
Planning and Regulatory Services 5.195  4.184  1.011 3.638 1.557 29.97%
Enterprise and Sustainable Development 6.579  7.183  (0.604) 6.587 (0.008) (0.12%)
Roads, Transportation and Fleet 19.833  19.564  0.269 19.288 0.545 2.75%
Position Before Transfer to Reserves 131.625  130.159  1.466 129.069 2.556 1.94%
Transfers to Reserves as at 31/03/2026      2.209 (2.209) (1.68%)
Position After Transfers to Reserves at 31/03/2026      131.278 (0.347) (0.26%) 
8
87

Page 88

Community and Enterprise Resources Variance Analysis 2025/26 (Period 14) 
Subjective Head Variance Subjective line Service / amount Explanation
Employee Costs 5,555k
under
APT&C and Manual Workers
Basic/Superannuation/NI - 6,629k
under
Facilities, Waste and
Grounds Services -
4,805k under
The variances are mainly due to
vacant posts, with recruitment
currently being progressed and
posts being held for savings in
future years.   
Planning and
Regulatory Services -
490k under 
Enterprise and
Sustainable
Development - 474k
under 
Roads, Transportation
and Fleet Services -
1,131k under 
Overtime - (1,219k) over Facilities, Waste and
Grounds Services -
(1,294k) over
The overspend is mainly within
Grounds and is due to vehicle
checks, verge maintenance
works and weekend work at
cemeteries and golf courses.
There was also overspends
within Facilities, Streets and
Waste due to staff absences
and delays in recruitment.
These are offset by
underspends in basic pay
(above).
88

Page 89

Subjective Head Variance Subjective line Service / amount Explanation
Employee Costs
(cont.) 
Additional Pension Costs - (43k) over Planning and
Regulatory Services –
(74k) over 
Roads, Transportation
and Fleet Services -
37k under
The overspend relates to the
ongoing cost of early retirals.
Property Costs (658k) over Rates 100k under Facilities, Waste and
Grounds Services –
81k under
The underspend is mainly due
to rates relief for the former
Civic Amenity site at Muttonhole
Road.  
Scottish Water - Metered Charges -
(36k) over
Facilities, Waste and
Grounds Services -
(41k) over
The level of water charges
received to supply the
cemeteries and crematorium
within Streets and Operations is
higher than the budget set.  
Grounds Maintenance and Additional
Works – (54k) over
Facilities, Waste and
Grounds Services -
(44k) over
The overspend is within
Grounds and is in relation to
additional grounds maintenance
works.  
Lifecycle Maintenance – (51k) over Facilities, Waste and
Grounds Services -
(50k) over
The overspend is within Streets
and relates to the purchase of
CCTV equipment.  
Repairs & Maintenance - Internal
Contractors - (99k) over
Facilities, Waste and
Grounds Services -
(77k) over
The overspend is due to routine
maintenance work carried out
on behalf of Facilities, Waste
and Streets.
89

Page 90

Subjective Head Variance Subjective line Service / amount Explanation
Property Costs
(cont.)  
Roads, Transportation
and Fleet Services -
(37k) over
The overspend mainly relates to
the upkeep of the Road’s
construction depots. 
Repairs & Maintenance - External -
(69k) over
Planning & Regulatory
Services – (20k) over
The overspend is due to
external repairs carried out on
the unsafe Quarry Street
building, with all costs being
fully recoverable.  
Enterprise &
Sustainable
Development – (39k)
over
The overspend partly relates to
costs for the upgrade of the 8th
floor Council offices in respect
of Amenity Staff transfer within
Support Services and property
repair works for Employability
Offices. 
Electricity Contract – 241k under Facilities, Waste and
Grounds Services -
250k under
The underspend is due to costs
being less than budgeted within
Amenity Services.  
Enterprise and
Sustainable
Development - 20k
under
The underspend is due to less
costs incurred for rental
properties within the service  
Roads, Transportation
and Fleet Services -
(30k) over
The overspend mainly relates to
higher than budgeted electricity
costs associated with the
charging of electrical vehicles.
90

Page 91

Subjective Head Variance Subjective line Service / amount Explanation
Property Costs
(cont.) 
Cleaning & Janitorial Supplies - (186k)
over
Facilities, Waste and
Grounds Services -
(182k) over
The overspend relates to an
increase in costs for cleaning
materials within Facilities
Management. 
Health and Hygiene Materials - (84k)
over
Facilities, Waste and
Grounds Services -
(84k) over
The overspend relates to an
increase in costs for health and
hygiene materials within
Facilities Management. 
Refuse Uplifts - (128k) over Facilities, Waste and
Grounds Services -
(129k) over
The overspend relates to
greater than budgeted
expenditure on refuse uplifts in
schools within Facilities
Management. 
Other Property Costs – (315k) over Enterprise &
Sustainable
Development – (318k)
over
The overspend relates to costs
for Hamilton Towers
dilapidations.
Supplies and
Services
(1,085k)
over
IT Equipment Maintenance – 110k
under
Facilities, Waste and
Grounds Services –
74k under
The underspend is due to less
than budgeted costs for IT
Equipment Maintenance
Contract throughout the
services, this is offset by
overspend in IT Leasing.   
Enterprise &
Sustainable
Development – 25k
under
The underspend is mainly due
to less than budgeted costs for
IT equipment and is partly offset
91

Page 92

Subjective Head Variance Subjective line Service / amount Explanation
Supplies and
Services (cont.)   
by an overspend in IT leasing
costs for the service. 
Equipment, Apparatus and Tools -
390k under
Facilities, Waste and
Grounds Services –
365k under
The underspend is due to less
than budgeted costs for
Equipment within Facilities and
Waste Services. 
Small Tools - 47k under Facilities, Waste and
Grounds Services - 25k
under
The underspend within Grounds
partially offsets the overspend
in Materials.  
Roads, Transportation
and Fleet Services -
22k under
The underspend is due to
reduced hire costs for small
tools within Roads
Construction. 
Materials and Stock/Store Issues –
(1,132k) over
Facilities, Waste and
Grounds Services -
(594k) over
The overspend in Grounds
relates to costs for items such
as weedkiller, plants etc. This is
partially offset by an
underspend in Streets and an
underspend in equipment.  
Roads, Transportation
and Fleet Services –
(536k) over
The overspend is within Roads
and relates to a greater spend
on materials due to increased
levels of work on roads
maintenance.
92

Page 93

Subjective Head Variance Subjective line Service / amount Explanation
Supplies and
Services (cont.) 
Food & Beverages – (499k) over Facilities, Waste and
Grounds Services –
(203k) over
The overspend is within
Facilities and relates to an
increase in the cost of food and
drink. 
Protective Clothing & Uniforms -
(259k) over
Facilities, Waste and
Grounds Services -
(262k) over
The overspend is mainly within
Grounds and Waste and relates
to an increase in the
requirement of PPE due to new
staff members. 
Other Supplies & Services - 341k
under
Facilities, Waste and
Grounds Services –
278k under
The underspend is mainly
within Facilities, this offsets the
overspend within Food.  
Roads, Transportation
and Fleet Services -
64k under
The underspend is partly within
Fleet and relates to the costs
for pool car permits being less
than budget. Also reduced
processing costs for credit card
payments within Parking. 
Major Supply of Electrical Power –
(327k) over
Roads, Transportation
and Fleet Services –
(327k) over
The overspend is due higher
than budgeted costs for street
lighting electrical power.
Transport and
Plant
(3,696k)
over
Purchase of Plant – (1,609k) over Facilities, Waste and
Grounds Services –
(1,582k) over
The overspend relates to plant
bought outright by Grounds.   
Roads, Transportation
and Fleet - (27k) over
The overspend relates to the
purchase of containers within
Roads.
93

Page 94

Subjective Head Variance Subjective line Service / amount Explanation
Transport and
Plant (cont.) 
Fleet Services - Fuel - (531k) over Facilities, Waste and
Grounds Services -
(46k) over
The overspend is due to electric
vehicle fuel costs being higher
than budget. This is offset by an
underspend in Fleet Service
Charges, Fuel.  
Roads, Transportation
and Fleet - (485k) over
The overspend is due to fuel
costs being higher than budget.
This is offset by an over
recovery in income. 
Fleet Services - Vehicle Hire - (489k)
over
Roads, Transportation
and Fleet - (497k) over
The overspend within Fleet is
due to casual hire now being
charged annually rather than
monthly, this is offset by an
over recovery in income. 
Fleet Services - Repairs - (849k) over Roads, Transportation
and Fleet - (849k) over
The overspend is due to higher
costs in relation to outside
repairs, materials and tyres
within the Fleet Workshop. 
Fleet Service Charges - Vehicle
Maintenance - (551k) over
Facilities, Waste and
Grounds Services -
(436k) over
This overspend is due to higher
than anticipated charges for
routine maintenance within
Waste, Streets, Grounds and
Facilities Management.  
Roads, Transportation
and Fleet - (117k) over
The overspend is due to higher
than anticipated charges for
routine maintenance within
Fleet and Roads.
94

Page 95

Subjective Head Variance Subjective line Service / amount Explanation
Transport and
Plant (cont.) 
Fleet Service Charges - Plant
Maintenance - 51k under
Facilities, Waste and
Grounds Services - 48k
under
The underspend is mainly due
to lower than anticipated costs
associated with plant vehicles
within Grounds and Waste. 
Fleet Service Charges - Leasing –
(462k) over
Facilities, Waste and
Grounds Services –
(283k) over
The leasing overspend is due to
an increase in the annual
charge for many of the vehicles.
This was a result of new leasing
contracts being awarded.   
Roads, Transportation
and Fleet – (192k) over
The leasing overspend is within
Roads and is due to an
increase in the annual charge
for many of the vehicles
compared to estimated rates for
leased vehicles. 
Fleet Service Charges - Hired
Vehicles/ Contract Hires – 40k under
Facilities, Waste and
Grounds Services –
(357k) over
This overspend is due to higher
than budgeted charges for
external hires within Grounds
and Waste.  
Roads, Transportation
and Fleet - 399k under
The underspend mainly relates
to the lower demand for hired
vehicles within the Roads
Construction Unit in carrying out
maintenance works. 
Fleet Service Charges - Fuel - 584k
under
Facilities, Waste and
Grounds Services -
414k under
The underspend is in the main
due to an increase in the
number of electric vehicles
within the service, meaning less
95

Page 96

Subjective Head Variance Subjective line Service / amount Explanation
Transport and
Plant (cont.)   
fuel is required, this is offset by
an overspend in EV fuel costs
above.  
Roads, Transportation
and Fleet – 162k under
The underspend is mainly due
to less utilisation of fleet
vehicles and plant within the
Construction Unit. 
Hire of External Vehicles - 68k under Facilities, Waste and
Grounds Services - 38k
under
The underspend is within
Streets and is due to there
being less requirement for hire
of external brushes this year.  
Roads, Transportation
and Fleet – 30k under
The underspend is within
Roads and is due to there being
less requirement for hire of
external vehicles.
Administration (271k) over Printing & Stationery - (59k) over Facilities, Waste and
Grounds Services -
(78k) over
The overspend is mainly due to
the printing of menus and
promotional material within
Facilities Management.  
Telephones - 63k under Facilities, Waste and
Grounds Services - 28k
under
The underspend is due to there
being less requirements for
telephones throughout all
services and is partially offset
by an overspend in mobile
phones.
96

Page 97

Subjective Head Variance Subjective line Service / amount Explanation
Administration
(cont.)  
Planning and
Regulatory Services -
15k under 
Enterprise and
Sustainable
Development - 15k
under 
Mobile Phones - (24k) over Facilities, Waste and
Grounds Services -
(6k) over
The overspend is due to an
increase in the cost of mobile
phone contracts throughout all
services and is offset by an
underspend in telephones.  
Enterprise and
Sustainable
Development - (10k)
over 
Roads, Transportation
and Fleet – (5k) over 
Postages - (27k) over Planning and
Regulatory Services -
(12k) over
The overspend is mainly due to
an increased level of postages
within Planning & Building
Standards.  
Roads, Transportation
and Fleet - (15k) over
The overspend is mainly due to
an increased level of postages
within Roads.
97

Page 98

Subjective Head Variance Subjective line Service / amount Explanation
Administration
(cont.) 
Membership Fees – (89k) over Facilities, Waste and
Grounds Services -
(14k) over
The overspend is within
Grounds and is for standpipe
licence costs.  
Enterprise and
Sustainable
Development – (69k)
over
The overspend is due to a
greater amount of membership
fees and subscription costs
within Employability. 
Medical Costs - (69k) over Facilities, Waste and
Grounds Services -
(57k) over
The overspend reflects a higher
than anticipated level of medical
referrals throughout the
services due to staff absence
levels.  
Roads, Transportation
and Fleet - (13k) over 
Training - (39k) over Planning and
Regulatory Services -
(13k) over
The overspend reflects
increased costs for specialised
training within Environmental
Health.  
Roads, Transportation
and Fleet - (21k) over
The overspend relates to
greater than budgeted costs for
statutory training within the
Roads service.
Payment to Other 854k under Payment to Other Bodies - 709k Enterprise and The underspend is mainly due
Bodies  under Sustainable to less than anticipated spend   
Development – 791k on Business Support and   
under Employability programmes and    
carry over of Shared Prosperity
98

Page 99

Subjective Head Variance Subjective line Service / amount Explanation
Payments to Other
Bodies (cont.)   
projects to 26/27, partly offset
by increased expenditure for
Community Led Local
Development initiatives. This
underspend is offset by reduced
income.  
Leisure Services - 21k
under
The underspend is due to the
annual Fireworks Display at
Strathclyde Park not being held
this year, due to ongoing
upgrades at Strathclyde Park.  
Roads, Transportation
and Fleet - (116k) over
The overspend within Roads is
mainly due to payments in
respect of WoSLA for winter
weather forecasts being greater
than budgeted. 
Activities Programme – 174k under Enterprise and
Sustainable
Development – 174k
under
The underspend is due to lower
than budgeted costs through
Employability in respect of No
One Left Behind Training, which
is offset by a reduction of
income.
Payment to
Contractors
(4,580k)
over
Payment to Trading Service - (2,139k)
over
Facilities, Waste and
Grounds Services -
(47k) over
The overspend is within
Grounds and is for payments
made to Roads for resurfacing
works and purchase of salt.
99

Page 100

Subjective Head Variance Subjective line Service / amount Explanation
Payment to
Contractors (cont.)  
Roads, Transportation
and Fleet - (2,098k)
over
The overspend is mainly due to
higher than budgeted costs for
winter and additional costs for
reactive maintenance of
carriageways and street
lighting. 
Payment to Private Contractor -
(2,008k) over
Facilities, Waste and
Grounds Services -
(274k) over
The overspend is mainly due to
higher that anticipated costs on
the upkeep of the Crematorium
and cemeteries along with the
use of sub - contractors within
Grounds.  
Planning and
Regulatory Services –
(97k) over
The overspend relates to the
increased contract rates for the
kennelling of stray dogs, house
clearances and pest control
within Environmental Services.
The overspend is partially offset
by increased income for pest
control.  
Roads, Transportation
and Fleet – (1,609k)
over
This overspend is mainly the
effect of an increased spend on
bridge repairs and statutory
inspections within Structures,
along with increased contract
costs within the Traffic Section
on traffic lights.
100

Page 101

Subjective Head Variance Subjective line Service / amount Explanation
Payments to
Contractors (cont.) 
Payment to Internal Consultant – 72k
under
Facilities, Waste and
Grounds Services –
72k under
The underspend is within
Grounds and partially offsets
the overspend in payment to
private contractors.
Financing Charges (262k) over Leasing Charges – (91k) over Facilities, Waste and
Grounds Services –
(91k) over
The overspend is due to higher
than budgeted costs for IT
leasing within Facilities and
Amenity.  
IT Equipment Leasing – (180k) over Facilities, Waste and
Grounds Services –
(109k) over
The underspend is due to
greater than budgeted costs for
IT Equipment Leasing Contract
throughout the services, this is
partially offset by an
underspend in IT Equipment
Maintenance.   
Planning and
Regulatory Services –
(17k) over 
Enterprise and
Sustainable
Development – (15k)
over 
Roads, Transportation
and Fleet – (39k) over 
Income 6,702 over
recovered
Contributions from Other Bodies –
(1,452k) under recovered
Facilities, Waste and
Grounds Services –
126k over recovered
The over recovery is mainly
within Facilities and is due to
rebates received from Brakes.
101

Page 102

Subjective Head Variance Subjective line Service / amount Explanation
Income (cont.)   Enterprise and
Sustainable
Development –
(1,547k) under
recovered
The under recovery of income
is due to less than anticipated
expenditure for Employability
and Business Support
Programmes as well carry over
of Shared Prosperity funded
projects to 26/27.  
Roads, Transportation
and Fleet – (26k) under
recovered
The under recovery is within
Fleet and is due to part of the
bus grant being distributed to
other Resources. 
Sales - General - 488k over recovered Facilities, Waste and
Grounds Services –
29k over recovered
The over recovery is the net
effect of vending sales being
higher than budget within
Facilities and the general sale
of bins being less than budget
within Waste.  
Roads, Transportation
and Fleet - 459k over
recovered
The over recovery mainly
relates to higher than
anticipated income from skip
permits and road closures and
is offset by overspends within
the overall service. 
Sales – Dept of Authority - 60k over
recovered
Facilities, Waste and
Grounds Services –
38k over recovered
The over recovery is within
Waste and is due to the sale of
bins to internal departments.
102

Page 103

Subjective Head Variance Subjective line Service / amount Explanation
Income (cont.)   Roads, Transportation
and Fleet - 22k under
recovered
The under recovery is due to
lower than budgeted income
recovered for lighting works. 
Fees & Charges - General - 444k over
recovered
Facilities, Waste and
Grounds Services -
(20k) under recovered
The under recovery is within
Streets and is due to a
decrease in demand for burials,
this is partially offset by an over
recovery in uplifts within Waste.  
Planning and
Regulatory Services -
872k over recovered
The over recovery is due to
increased income for Planning
applications during the year.  
Roads, Transportation
and Fleet – (428k)
under recovered
The under recovery is due to
less than budgeted
Construction Consent income
and car park income within
Roads, partially offset by
greater than budgeted income
from Parking penalty charge
notices. 
Fees and Charges - Departments of
the Authority – 1,382k over recovered
Facilities, Waste and
Grounds Services –
279k over recovered
The over recovery is due to an
increase in additional service
requests to Waste services
from Housing and Technical
Resources for additional bin
uplifts as well as an increase in
income for Street Cleansing.
103

Page 104

Subjective Head Variance Subjective line Service / amount Explanation
Income (cont.)   Planning and
Regulatory Services -
400k over recovered
The over recovery is due to
increased income for building
warrants during the year.   
Roads, Transportation
and Fleet – 703k over
recovered 
The over recovery within Fleet
is in the main due to income
received for EV electricity
usage. This partially offsets the
overspend in Transport & Plant.
Roads is also showing an over
recovery due to Roads
Construction carrying out
greater amount of works for
other services. 
Fleet Services – 1,393k over
recovered
Roads, Transportation
and Fleet – 1,393k
over recovered
The over recovery is due to
income received for vehicle
maintenance, casual hire and
taxi inspections being higher
than budgeted. This partially
offsets the overspend in
expenditure. 
Other Income - 328k over recovered Facilities, Waste and
Grounds Services - 50k
over recovered
The over recovery within
Grounds relates to additional
service requests and the over
recovery within Facilities is
mainly due to insurance money
received for a fire at Hallside
PS.
104

Page 105

Subjective Head Variance Subjective line Service / amount Explanation
Income (cont).   Enterprise and
Sustainable
Development – 379k
over recovered
The over recovery is mainly due
to the provision for the
dilapidations of Hamilton
Towers within Property
Development.  
Roads, Transportation
and Fleet – 96k under
recovered
The under recovery within Fleet
is due to recharges for Pool
Cars being less than budget.
This is partially offset by under
spends in supplies & services
and transport costs. 
Recovery From Capital – 81k over
recovered
Roads, Transportation
and Fleet – 81k over
recovered
The over recovery is due to
greater than anticipated design
fee income recovered from
capital projects within Roads. 
Recharges – Departments of the
Authority – 4,022 over recovered
Facilities, Waste and
Grounds Services –
(297k) under recovered
The under recovery is within
Grounds and relates to
adoption monies not being
drawn down, there is also an
under recovery within Facilities
due to requests for additional
cleaning being less than
budget.  
Roads, Transportation
and Fleet - (4,319k)
over recovered
The over recovery is due to
employee recharges within
Fleet and income recovered
from Capital works within the
Roads Construction Unit. 
* The underlined variances represent new variances since the last report.
105

Page 106

South Lanarkshire Council
Community & Enterprise Resources Summary
Expenditure / Income Variance Trends 2025/2026
Revised
Annual
Budget
25/26
Period 14
Actual
to Date
Period 14
Amount
Variance    
EMPLOYEE COSTS   
APT & C BASIC 85,565 79,233 6,332
APT & C OVERTIME 1,305 2,481 (1,176)
APT & C SUPERANNUATION 5,644 5,019 625
APT & C NIC 9,881 9,655 226
MANUAL WORKERS BASIC 0 (6) 6
MANUAL SESSIONAL STAFF BASIC 2,054 2,570 (516)
MANUAL SESSIONAL STAFF OVERTIME 4 47 (43)
MANUAL SESSIONAL STAFF SUPERANNUATION 161 106 55
MANUAL SESSIONAL STAFF NIC 181 280 (99)
TRAVEL AND SUBSISTENCE 109 83 26
OTHER EMPLOYEE COSTS 187 24 163
PENSION INCREASES 1,118 1,161 (43)
STRAIN ON THE FUND 0 2 (2)
APPRENTICESHIP LEVY 418 418 0
COST LABOUR ALLOCATION (64) (65) 1    
EMPLOYEE COSTS 106,563 101,008 5,555    
PROPERTY COSTS   
RATES 1,116 1,016 100
SCOTTISH WATER - UNMETERED CHARGES 8 0 8
SCOTTISH WATER - METERED CHARGES 176 212 (36)
RENT 215 195 20
SERVICE CHARGE 42 46 (4)
FACTORING CHARGES 16 27 (11)
PROPERTY INSURANCE 308 292 16
SECURITY COSTS 52 53 (1)
GROUND MAINTENANCE 8 18 (10)
GROUNDS MAINTENANCE ADDITIONAL WORKS 4 48 (44)
REPAIRS & MAINTENANCE - INTERNAL CONTRACTORS 36 135 (99)
LIFE CYCLE MAINTENANCE 0 51 (51)
REPAIRS & MAINTENANCE - EXTERNAL CONTRACTORS 373 442 (69)
ADAPTIONS - INTERNAL CONTRACTOR 0 1 (1)
GAS HEATING LEASE COSTS 0 1 (1)
ELECTRICITY - CONTRACT 3,984 3,743 241
ELECTRICITY - NON CONTRACT 0 3 (3)
GAS 1,935 1,941 (6)
HEATING OIL 14 (1) 15
FIXTURE & FITTINGS 0 7 (7)
CLEANING CONTRACT 20 20 0
CLEANING AND JANITORIAL SUPPLIES AND EQUIPMENT 715 901 (186)
HEALTH & HYGIENE MATERIALS 43 127 (84)
REFUSE UPLIFT 405 533 (128)
REMOVAL & STORAGE COSTS 0 2 (2)
OTHER PROPERTY COSTS 34 349 (315)
OFFICE ACCOMODATION FACILITIES 4 4 0    
PROPERTY COSTS 9,508 10,166 (658)    
106

Page 107

South Lanarkshire Council
Community & Enterprise Resources Summary
Expenditure / Income Variance Trends 2025/2026
Revised
Annual
Budget
25/26
Period 14
Actual
to Date
Period 14
Amount
Variance
SUPPLIES AND SERVICES   
COMPUTER EQUIPMENT PURCHASE 672 677 (5)
COMPUTER EQUIPMENT RENTAL 6 0 6
COMPUTER EQUIPMENT MAINTENANCE 46 41 5
I.T. EQUIPMENT MAINT-CONTRACT 203 93 110
I.T. ELECTRONIC MESSAGING 3 0 3
EQUIPMENT, APPARATUS AND TOOLS 2,014 1,624 390
SMALL TOOLS 107 60 47
ADAPTATIONS FOR CLIENTS 0 21 (21)
FURNITURE - OFFICE 8 36 (28)
FURNITURE - GENERAL 0 14 (14)
FURNISHINGS (INCL. CROCKERY & LINEN) 110 67 43
MATERIALS 7,480 6,764 716
STOCK/STORE ISSUES 0 1,848 (1,848)
MATERIALS, APPARATUS AND EQUIPMENT 12 8 4
AUDIO VISUAL 0 17 (17)
PUBLICATIONS, JOURNALS, NEWSPAPERS ETC. 2 0 2
PROVISIONS 0 8 (8)
FOOD PURCHASES 5,668 6,151 (483)
BEVERAGES 0 16 (16)
SCHOOL MILK 114 166 (52)
RECHARGES OF DIRECT FOOD COSTS 68 (12) 80
OPENING STOCK 0 3,165 (3,165)
CLOSING STOCK 0 (3,425) 3,425
PROTECTIVE CLOTHING & UNIFORMS 260 519 (259)
LAUNDRY COSTS 10 15 (5)
OTHER SUPPLIES AND SERVICES 532 191 341
MAJOR SUPPLY OF ELECTRICAL POWER 2,368 2,695 (327)
OUTSOURCED MAIL 1 11 (10)
DELIVERY CHARGE 1 3 (2)    
SUPPLIES AND SERVICES 19,685 20,773 (1,088)
107

Page 108

South Lanarkshire Council
Community & Enterprise Resources Summary
Expenditure / Income Variance Trends 2025/2026
Revised
Annual
Budget
25/26
Period 14
Actual
to Date
Period 14
Amount
Variance    
TRANSPORT AND PLANT   
PURCHASE OF VEHICLES 0 (9) 9
PURCHASE OF PLANT 6 1,615 (1,609)
FLEET SERVICES - DRIVERS 65 107 (42)
FLEET SERVICES - FUEL 2,999 3,530 (531)
FLEET SERVICES - VEHICLE HIRE 1,228 1,717 (489)
POOL CAR CHARGES - RENTAL 104 109 (5)
POOL CAR CHARGES - FUEL 19 0 19
POOL CAR CHARGES - ADDITIONAL COSTS 6 5 1
OTHER TRANSPORT COSTS 73 85 (12)
TRANSPORT INSURANCE 93 93 0
LICENCES 491 484 7
FLEET SERVICES - REPAIRS 2,616 3,465 (849)
PLANT SERVICES 19 10 9
FLEET SERVICE CHARGES - VEHICLE MAINTENANCE 4,414 4,965 (551)
FLEET SERVICE CHARGES - PLANT MAINTENANCE 361 310 51
FLEET SERVICE CHARGES - ASSET MODIFICATION 68 71 (3)
FLEET SERVICE CHARGES - LEASING 4,806 5,268 (462)
FLEET SERVICE CHARGES - HIRED VEHICLES 1,433 1,356 77
FLEET SERVICE CHARGES - CONTRACT HIRE 199 236 (37)
FLEET SERVICE CHARGES - ROAD FUND LICENCE 242 228 14
FLEET SERVICE CHARGES - FUEL 3,050 2,466 584
FLEET SERVICE CHARGES - DRIVERS 56 71 (15)
HIRE OF EXTERNAL VEHICLES 68 0 68
HIRE OF EXTERNAL PLANT 278 288 (10)
HIRE OF SKIPS 17 25 (8)
PUPIL TRANSPORT - SPECIAL EDUCATION 298 210 88    
TRANSPORT AND PLANT 23,009 26,705 (3,696)    
ADMINISTRATION   
PRINTING AND STATIONERY 220 279 (59)
TELEPHONES 98 35 63
MOBILE PHONES 60 84 (24)
ADVERTISING - OF COUNCIL SERVICE AVAILABILITY 8 8 0
ADVERTISING - OTHER 93 94 (1)
POSTAGES/COURIERS 31 58 (27)
MEMBERSHIP FEES/SUBSCRIPTIONS 83 172 (89)
INSURANCE 260 262 (2)
MEDICAL COSTS 7 76 (69)
LEGAL EXPENSES 12 17 (5)
HOSPITALITY / CIVIC RECOGNITION 3 1 2
INTERNET AGENCY FEES 23 42 (19)
SECURITY UPLIFT FEES 17 18 (1)
OTHER ADMIN COSTS 4 5 (1)
TRAINING 11 50 (39)    
ADMINISTRATION 930 1,201 (271)
108

Page 109

South Lanarkshire Council
Community & Enterprise Resources Summary
Expenditure / Income Variance Trends 2025/2026
Revised
Annual
Budget
25/26
Period 14
Actual
to Date
Period 14
Amount
Variance    
PAYMENT TO OTHER BODIES   
SPTE: ANNUAL BUS SUBSIDY 2,034 2,034 0
SPTE: BUS OTHER 258 258 0
SPTE: FERRIES 29 29 0
SPTE: UNDERGROUND 1,318 1,318 0
SPTE: OTHER 1,727 1,727 0
SPTE: MAINTENANCE OF BUS SHELTERS AND STOPS 131 131 0
OTHER LOCAL AUTHORITIES 73 101 (28)
GRANTS TO VOLUNTARY ORGANISATIONS 22 20 2
PAYMENTS TO VOLUNTARY ORGANISATIONS 39 41 (2)
PAYMENTS TO OTHER BODIES 11,058 10,349 709
EXTERNAL AUDIT FEES 3 4 (1)
ACTIVITIES PROGRAMME 439 265 174    
PAYMENT TO OTHER BODIES 17,131 16,277 854    
PAYMENT TO CONTRACTORS   
PAYMENT TO TRADING SERVICES CONTRACTOR (1,928) 211 (2,139)
PAYMENT TO LOCAL AUTHORITY CONTRACTOR 302 297 5
PAYMENT TO PRIVATE CONTRACTOR 38,763 40,771 (2,008)
PAYMENT TO INTERNAL CONSULTANT 72 0 72
PAYMENT TO EXTERNAL CONSULTANTS / PROFESSIONAL SERVICES 50 54 (4)
OPENING WORK IN PROGRESS 0 (314) 314
CLOSING WORK IN PROGRESS 0 820 (820)    
PAYMENT TO CONTRACTORS 37,259 41,839 (4,580)    
TRANSFER PAYMENTS   
CONCESSIONARY FARES 625 625 0    
TRANSFER PAYMENTS 625 625 0    
FINANCING CHARGES   
LEASING CHARGES - OPERATIONAL 0 91 (91)
I.T. EQUIPMENT LEASING-CONTRACT 191 371 (180)
INTEREST ON REVENUE BALANCES 0 (9) 9    
FINANCING CHARGES 191 453 (262)    
TOTAL EXPENDITURE 214,901 219,047 (4,146)
109

Page 110

South Lanarkshire Council
Community & Enterprise Resources Summary
Expenditure / Income Variance Trends 2025/2026
Revised
Annual
Budget
25/26
Period 14
Actual
to Date
Period 14
Amount
Variance    
INCOME   
MILK SUBSIDIES FROM THE E.U. (37) 0 (37)
CONTRIBUTIONS FROM OTHER BODIES (21,263) (19,811) (1,452)
ESF GRANT 0 1 (1)
SALES - GENERAL (5,478) (5,966) 488
ELECTIONS - ACCOMMODATION USE 0 (3) 3
SALES - DEPARTMENTS OF THE AUTHORITY (136) (196) 60
FEES AND CHARGES - GENERAL (13,177) (13,621) 444
FEES AND CHARGES - DEPARTMENTS OF THE AUTHORITY (6,711) (8,093) 1,382
RENTAL INCOME (90) (81) (9)
FLEET SERVICES (12,639) (14,032) 1,393
OTHER INCOME (1,861) (2,189) 328
RECOVERY FROM CAPITAL (586) (667) 81
RECHARGES - DEPARTMENTS OF THE AUTHORITY (21,298) (25,320) 4,022    
TOTAL INCOME (83,276) (89,978) 6,702    
NET EXPENDITURE 131,625 129,069 2,556 
110

Page 111

Appendix B
South Lanarkshire Council
Revenue Budget Monitoring Statement
Period Ended 31 March 2026 (No 14)
Education Resources
Committee Revised Projected Projected Actual Variance %
Annual Outturn Outturn to Period 14 to Period 14
Budget Variance 31/03/26 31/03/26
Before
Transfers
Service Departments :- £m £m £m £m £m
Education 503.799 503.321 0.478 502.132 1.667 0.33%
Position Before Transfer to Reserves 503.799 503.321 0.478 502.132 1.667 0.33%
Transfers to Reserves as at 31/03/2026 1.667 (1.667) (0.33%)
Position After Transfers to Reserves at 31/03/2026 503.799 0.000 0.00%
8
111

Page 112

Education Resources Variance Analysis 2025/26 (Period 14) 
Subjective Head Variance  Subjective line Service / amount Explanation
Employee Costs 1,711k under Teachers Basic / Superannuation /
National Insurance - (2,250k) over 
APT&C Basic / Superannuation /
National Insurance – 4,067k under 
Premature Retirals - (108k) over 
Schools - (2,250k) over 
Early Years / Support
Services – 4,067k
under 
Schools - (108k) over 
The overspend relates to the
cost of supply teachers for
absence cover. 
The underspend mainly relates
to Early Years and Support
Services posts and is the result
of staff turnover. 
The overspend relates to
increased monthly costs for
historic early retirals due to
inflation levels and the cost of
pensions. 
Supplies &
Services
939k under Aids for Clients - (106k) over 
Pupil Equity Fund - 653k under 
Schools - (106k) over 
Schools - 653k under 
This overspend is due to the
increased demand and cost of
new equipment required for
children in schools with
complex physical needs. 
The underspend reflects the
profile of Pupil Equity Fund
(PEF) spend and commitment
across the academic year in
line with school improvement
plans and will therefore be
carried forward to 2026/2027, to
be used in the April to June
2026 school session. 
112

Page 113

Subjective Head Variance  Subjective line Service / amount Explanation
Supplies &
Services (cont.) 
Materials, Apparatus and Equipment -
488k under 
Catering Contract - (114k) over 
Schools - 488k under 
Schools - (114k) over
The underspend is due funding
that will be transferred to
reserves for ASL (£0.564m) and
Schools Capital Fund
(£0.325m) to support
expenditure commitments to the
end of the school session in
June 2026. This is partially
offset by the additional cost of
per capita expenditure reflecting
the growth in pupil numbers and
price increase. 
The overspend is due to an
increased cost for food for
breakfast clubs.
Transport and
Plant
(3,451k) over Fleet Services Charges - (101k) over 
Pupil Transport - ASN - (2,538k) over 
Pupil Transport - Strathclyde
Passenger Transport - (809k) over 
Schools - (101k) over 
Schools - (2,538k) over 
Schools - (809k) over 
This is a demand led service
and reflects the volume of
children requiring ASN transport
to school and increased costs. 
This is a demand led service
and reflects the volume of
children requiring ASN transport
to school and increased costs. 
This is a demand led service
and reflects the volume of
children requiring mainstream
transport to school and
increased costs. 
113

Page 114

Subjective Head Variance  Subjective line Service / amount Explanation
Administration 3k under Conferences - 52k under Early Years - 52k
under 
The underspend relates to 
expenditure on Early Years’ 
funded provider meetings being
lower than anticipated. 
Payments to Other
Bodies 
(865k) over  Other Local Authorities - (994k) over 
Payments to Other Bodies - 756k
under 
Independent Schools Places - (608k)
over
Schools - (994k) over 
Early Years - 756k
under 
Schools - (608k) over
The overspend is due to an
increase in the cost of external
school placements within other
local authorities and back dated
charges from another local
authority that were not
anticipated.   
The underspend is due to less
than anticipated core Early
Years spend including cross
boundary charges to other
Local Authorities and is also
due to funding that will be
transferred to reserves for ASN
adaptations (£0.125m). 
This overspend reflects the
increased cost of placements
for pupils with additional
support needs in Independent
Schools and is due to both an
increase in the number of
places and the cost of
placements. 
114

Page 115

Subjective Head Variance  Subjective line Service / amount Explanation
Payments to
Contractors
408k under Payments to Private Contractors -
408k under
Non Schools - 408k
under
The underspend relates to the
timing of savings associated
with the renewal of the
insurance arrangements within
the contract this year.
Transfer Payments 125k under Footwear and Clothing Grants - 125k
under 
Schools - 125k under  This underspend reflects lower
than anticipated expenditure on
footwear and clothing grants
during the financial year,
reflecting current demand. 
Income 2,844k over
recovered
Fees and Charges - Other Local
Authorities - 926k over recovered 
Early Years Fees - 1,927k over
recovered 
Schools - 926k over
recovered 
Early Years - 1,927k
over recovered
This over recovery reflects the
increase in income recovered
from other Local Authorities for
children attending schools in
South Lanarkshire. This income
is used to support the cost of
external placements. 
This over recovery in Early
Years’ fees relates to increased
uptake of available nursery
places beyond 1140 hours. 
115

Page 116

South Lanarkshire Council
Revised Period 14 Period 14
Education Resource - Total Annual  Actual Variance
Budget to Date Amount
Expenditure / Income Variance Trends 2025/2026 25/26
EMPLOYEE COSTS
TEACHERS BASIC 194,509 193,391 1,118
TEACHERS SUPERANNUATION 50,621 49,738 883
TEACHERS NI 25,523 26,264 (741)
FIXED TERM CONTRACT - TEACHER  - APT&C BASIC 1,722 3,135 (1,413)
FIXED TERM CONTRACT - TEACHER  SUPERANNUATION 0 403 (403)
SUPPLY TEACHERS - APT&C BASIC 0 216 (216)
SUPPLY TEACHERS - APT&C SUPERANNUATION 0 896 (896)
SUPPLY TEACHERS - APT&C NIC 0 91 (91)
APT&C BASIC 76,144 72,200 3,944
APT&C OVERTIME 65 522 (457)
APT&C SUPERANNUATION 5,347 4,695 652
APT&C NIC 7,888 8,451 (563)
TRAVEL AND SUBSISTANCE 192 162 30
PENSION INCREASES 434 439 (5)
PREMATURE RETIRALS 5,041 5,149 (108)
STRAIN ON THE FUND 0 6 (6)
TEACHERS TRAINING (10) 1 (11)
CONSULTANTS 5 11 (6)
APPRENTICESHIP LEVY 1,343 1,343 0
EMPLOYEE COSTS 368,824 367,113 1,711
PROPERTY COSTS
RATES 19,398 19,374 24
SCOTTISH AKATER - UNMETERED CHARGES 0 1 (1)
SCOTTISH WATER - METERED (DRAINAGE) CHARGES 1,385 1,416 (31)
SCOTTISH WATER - METERED CHARGES 843 851 (8)
RENT 336 269 67
SERVICE CHARGE 45 78 (33)
PROPERTY INSURANCE 484 507 (23)
SECURITY COSTS 70 70 0
REPAIRS & MAINTENANCE - INTERNAL CONTRACTOR 84 84 0
LIFE CYCLE MAINTENANCE 2 2 0
REPAIRS & MAINTENANCE - EXTERNAL CONTRACTOR 47 53 (6)
ADAPTIONS - INTERNAL CONTRACTORS 90 86 4
GAS HEATING LEASE COSTS 0 2 (2)
SOLID FUEL HEATING MAINTENANCE 0 10 (10)
ASBESTOS 11 11 0
ELECTRICITY  - CONTRACT 7,253 7,415 (162)
ELECTRICITY - NON CONTRACT 0 7 (7)
GAS 3,950 3,900 50
HEATING OIL 105 102 3
SOLID FUEL 295 186 109
FIXTURE & FITTINGS 2 2 0
JANITOR SERVICE 136 135 1
CLEANING CONTRACT 504 516 (12)
CLEANING AND JANITORIAL SUPPLIES AND EQUIPMENT 472 472 0
HEALTH & HYGIENE MATERIALS 33 33 0
REFUSE UPLIFT 33 34 (1)
REMOVAL & STORAGE COSTS 1 1 0
OTHER PROPERTY COSTS 5 8 (3)
ACCOMMODATION RECHARGE TO USERS 882 882 0
PROPERTY COSTS 36,467 36,515 (48)
116

Page 117

South Lanarkshire Council
Revised Period 14 Period 14
Education Resource - Total Annual  Actual Variance
Budget to Date Amount
Expenditure / Income Variance Trends 2025/2026 25/26
SUPPLIES AND SERVICES
COMPUTER EQUIPMENT PURCHASE 486 487 (1)
I.T. EQUIPMENT MAINT-CONTRACT 3,649 3,649 0
I.T. ELECTRONIC MESSAGING 27 28 (1)
EQUIPMENT, APPARATUS AND TOOLS 35 35 0
SMALL TOOLS 3 3 0
AIDS FOR CLIENTS 117 223 (106)
ADAPTATIONS FOR CLIENTS 68 73 (5)
SUPPLIES FOR CLIENTS 13 13 0
FURNITURE - OFFICE 16 15 1
FURNITURE - GENERAL 99 99 0
FURNISHINGS (INCL. CROCKERY & LINEN) 13 14 (1)
MATERIALS 39 39 0
MATERIALS, APPARATUS AND EQUIPMENT 3,846 3,358 488
PUPIL EQUITY FUNDING 653 0 653
LIBRARY/RESOURCE CENTREMATERIALS 74 75 (1)
AUDIO VISUAL 8 8 0
PUBLICATIONS, JOURNALS, NEWSPAPERS ETC. 31 31 0
TV LICENCES - EDUCATION 35 28 7
PROVISIONS 367 377 (10)
FOOD PURCHASES 171 171 0
BEVERAGES 11 12 (1)
SCHOOL MILK 55 28 27
NURSERY MILK 71 72 (1)
NURSERY FRUIT/VEG (25) 2 (27)
RECHARGE OF DIRECT FOOD COSTS 12 12 0
PROTECTIVE CLOTHING & UNIFORMS 91 91 0
OTHER SUPPLIES AND SERVICES 51 45 6
HEALTH AND SAFETY 26 0 26
CATERING - CONTRACT 2,607 2,721 (114)
CATERING - OUTWITH CONTRACT 6 6 0
CATERING - EXTERNAL 19 20 (1)
ARTIST FEES / PERFORMING ARTS / ENTERTA 2 2 0
DELIVERY CHARGE 5 5 0
SUPPLIES AND SERVICES 12,681 11,742 939
TRANSPORT AND PLANT
POOL CAR CHARGES-RENTAL 3 3 0
OTHER TRANSPORT COSTS 2 2 0
INSURANCE 3 3 0
FLEET SERVICE CHARGES 2,182 2,283 (101)
HIRE OF EXTERNAL VEHICLES 300 300 0
HIRE OF SKIPS 18 19 (1)
EXTERNAL TRANSPORT CONTRACT 13 15 (2)
PUPIL TRANSPORT-SPECIAL EDUCATIONAL NEEDS 5,864 8,402 (2,538)
PUPIL TRANSPORT-S'CLYDE PASSENGER TRANSPORT 9,425 10,135 (710)
PUPIL TRANSPORT - OTHER 241 340 (99)
TAXI CHARGES - CONTRACTED 3 3 0
TRANSPORT AND PLANT 18,054 21,505 (3,451)
117

Page 118

South Lanarkshire Council
Revised Period 14 Period 14
Education Resource - Total Annual  Actual Variance
Budget to Date Amount
Expenditure / Income Variance Trends 2025/2026 25/26
ADMINISTRATION
PRINTING AND STATIONERY 756 764 (8)
TELEPHONES 185 190 (5)
MOBILE PHONES 27 29 (2)
ADVERTISING - OTHER 8 8 0
POSTAGES/COURIERS 20 19 1
MEMBERSHIP FEES/SUBSCRIPTIONS 426 426 0
INSURANCE 76 76 0
MEDICAL COSTS 35 35 0
LEGAL EXPENSES 3 18 (15)
HOSPITALITY / CIVIC RECOGNITION 5 5 0
SECURITY UPLIFT FEES 7 8 (1)
OTHER ADMIN COSTS 4 3 1
CONFERENCES - OFFICIALS (incl associated costs) 52 0 52
TRAINING 461 481 (20)
ADMINISTRATION 2,065 2,062 3
PAYMENT TO OTHER BODIES
YOUTH EMPLOYMENT TRAINING 2 2 0
OTHER COMMITTEES OF THE AUTHORITY 30 30 0
OTHER LOCAL AUTHORITIES 1,433 2,427 (994)
SCOTTISH QUALIFICATIONS AUTHORITY 1,563 1,582 (19)
PAYMENTS TO VOLUNTARY ORGANISATIONS 10 10 0
PAYMENTS TO OTHER BODIES 21,520 20,764 756
INDEPENDENT SCHOOL PLACES 3,807 4,415 (608)
CONTRACT SPEECH THERAPY 678 678 0
SCHOOL ACTIVITIES 330 330 0
RESEARCH GRANTS - EDUCATION 47 47 0
PARENT COUNCILS (PREV.SCHOOL BOARDS) 28 29 (1)
P.E. FACILITIES 17 17 0
ACTIVITIES PROGRAMME 408 408 0
COUNSELLING 1,328 1,328 0
COPYRIGHT AGREEMENT 228 228 0
VAT FREE EXCURSIONS - EDUCATION 11 10 1
PRIVATE INDIVIDUALS - GENERAL 3 3 0
PAYMENT TO OTHER BODIES 31,443 32,308 (865)
PAYMENT TO CONTRACTORS
PAYMENT TO LOCAL AUTHORITY CONTRACTOR 3 3 0
PAYMENT TO PRIVATE CONTRACTOR 48,111 47,703 408
PAYMENT TO EXTERNAL CONSULTANTS / PROFESSIONAL SERVICES 18 18 0
PAYMENT TO CONTRACTORS 48,132 47,724 408
TRANSFER PAYMENTS
RENT REBATES 838 838 0
FOOTWEAR & CLOTHING GRANTS 2,306 2,181 125
TRANSFER PAYMENTS 3,144 3,019 125
118

Page 119

South Lanarkshire Council
Revised Period 14 Period 14
Education Resource - Total Annual  Actual Variance
Budget to Date Amount
Expenditure / Income Variance Trends 2025/2026 25/26
FINANCING CHARGES
I.T. EQUIPMENT LEASING - CONTRACT 276 275 1
FINANCING CHARGES 276 275 1
TOTAL EXPENDITURE 521,086 522,263 (1,177)
INCOME
GOVERNMENT GRANT - GAELIC EDUCATION (170) (175) 5
GOVERNMENT GRANTS - OTHER EDUCATION GRANTS (13,046) (13,035) (11)
CONTRIBUTIONS FROM OTHER BODIES (1,359) (1,359) 0
FEES AND CHARGES - OTHER LOCAL AUTHORITIES (1,143) (2,069) 926
PLAYGROUP ACCOMMODATION CHARGE (12) (13) 1
EARLY YEARS FEES (652) (2,579) 1,927
RENTAL INCOME (20) (20) 0
OTHER INCOME (3) 1 (4)
ACCOMMODATION INCOME FROM USERS (882) (882) 0
INCOME (17,287) (20,131) 2,844
NET EXPENDITURE 503,799 502,132 1,667
119

Page 120

120

Page 121

Appendix C
South Lanarkshire Council
Revenue Budget Monitoring Statement
Period Ended 31 March 2026 (No 14)
Finance and Corporate Resources
Committee Revised Projected Projected Actual Variance %
Annual Outturn Outturn to Period 14 to Period 14
Budget Variance 31/03/26 31/03/26
Before
Transfers
Service Departments :- £m £m £m £m £m
Finance Services - Strategy 2.503 2.509 (0.006) 2.549 (0.046) (1.84%)
Finance Services - Transactions 19.172 18.198 0.974 18.240 0.932 4.86%
Audit and Compliance Services 0.371 0.353 0.018 0.354 0.017 4.58%
Information Technology Services 7.808 7.946 (0.138) 7.906 (0.098) (1.26%)
Communications and Strategy Services 2.604 2.381 0.223 2.330 0.274 10.52%
Administration and Licensing Services 5.010 5.028 (0.018) 4.962 0.048 0.96%
Transfers to Reserves as at 31/03/2026 6.734 6.909 (0.175) 6.887 (0.153) (2.27%)
Position Before Transfer to Reserves 44.202 43.324 0.878 43.228 0.974 2.20%
Transfers to Reserves as at 31/03/2026 0.396 (0.396) (0.90%)
Position After Transfers to Reserves at 31/03/2026 43.624 (0.578) 1.31%
8
121

Page 122

Finance and Corporate Resources Variance Analysis 2025/26 (Period 14) 
Subjective Head Variance  Subjective line Service / amount Explanation
Employee Costs  54k under  APT&C Basic, Superannuation, NI –
212k under
Finance Services
(Transactions) – 322k
under 
The underspend is due to
vacant posts within the
Service. 
Communications and
Strategy – 116k under 
Finance Services
(Strategy) – (56k) over 
The overspend is due to
lower than budgeted turnover
during the year.   
IT Services – (110k)
over 
Admin, Legal and
Licensing – (68k) over 
APT&C Overtime – (96k) over Finance Services
(Transactions) – (79k)
over 
Overtime costs have arisen
due to staffing vacancies and
absences, combined with
minimum staffing
requirements and unplanned
operational pressures,
requiring additional hours to
maintain service delivery. 
Property Costs 744k under Other Property Costs – 796k under Finance Services
(Transactions) – 803k
under 
The underspend reflects less
than budgeted spend on
Empty Property Relief. 
122

Page 123

Subjective Head Variance  Subjective line Service / amount Explanation
Supplies and Services (132k) over Computer Equipment Purchase –
(353k) over
Finance Services
(Transactions) – (132k)
over 
The overspend is due to
maintenance of Fire and
Intruder Alarms and annual
platform costs. 
IT Services – (221k)
over 
The overspend is due to
greater than budgeted IT
costs. 
Computer Equipment Maintenance –
140k under
IT Services – 135k
under
The underspend reflects less
than anticipated contract
spend. 
Administration (98k) over Postages and Couriers – (193k) over  Finance Services
(Transactions) – (149k)
over 
The overspend reflects
additional postage costs
required for service delivery.  
Members Allowances – 66k under  Administration, Legal
and Licensing – 64k
under
The underspend is due to
reduced superannuation
contributions in the financial
year.
Transfer Payments 367k under Rent Allowance – 349k under 
Rent Rebates – 18k under
Finance Services
(Transactions) – 349k
under 
Finance Services
(Transactions) – 18k
under 
The underspend in these
lines reflects the demand-led
spend on Rent Allowance
and Rent Rebates and is
offset by an under-recovery
of Income (below).
Financing Charges  (189k) over IT Equipment Leasing Contract –
(190k) over
Finance Services
(Transactions) – (84k)
over 
The overspend in Financing
Charges is due to higher than
budgeted IT leasing charges.
123

Page 124

Subjective Head Variance  Subjective line Service / amount Explanation
Financing Charges
(cont.)  
Admin, Legal and
Licensing – (34k) over 
Personnel – (45k) over 
Income  221k over
recovered
Rent Rebates Subsidy – (396k) under
recovered 
Finance Services
(Transactions) – (396k)
under recovered 
The under recovery in these
lines is offset by the demand-
led underspend in Transfer
Payments (above). 
Rent Allowance Subsidy – (254k)
under recovered 
Finance Services
(Transactions) – (254k)
under recovered 
DHP – 656k over recovered Finance Services
(Transactions) – 656k
over recovered
This over recovery reflects an
additional stream from
Scottish Government that is
offsetting expenditure and
income within DHP line that
is included within Rent
Rebates. 
Contributions from Other Bodies –
(92k) under recovered
Finance Services
(Transactions) – (49k)
under recovered
The under-recovery reflects
lower than budgeted income
for Housing Benefit
overpayments. 
Fees and Charges – General – 612k
over recovered
Finance Services
(Transactions) – 310k
over recovered 
The over-recovery of income
reflects additional
commission received from
Scottish Water for the
collection of water and
sewage and blue badge
applications.
124

Page 125

Subjective Head Variance  Subjective line Service / amount Explanation
Income (cont.)   IT Services – 66k over
recovered
The over-recovery is a result
of recharges to resources for
various IT services. 
Admin, Legal and
Licensing – 153k over
recovered
The over-recovery of income
reflects renewal fees for
private hires and operators. 
Fees and Charges – Departments of
the Authority – 76k over recovered 
Communications and
Strategy – 87k over
recovered
The over-recovery reflects
the demand for Royal Mail
postages and outsourced
mail. 
Other Income – (388k) under
recovered
Finance Services
(Transactions) – (309k)
under recovered 
The under recovery reflects
lower than budgeted income
for Housing Benefit
overpayments. 
Personnel – (58k)
under recovered 
The projected under-recovery
is due to lower than expected
level of legal recharges and
medical charges. 
* The underlined variances represent new variances since the last report.
125

Page 126

South Lanarkshire Council
Revised Period 14 Period 14
Finance & Corporate Resources - Total Annual  Actual Variance
Budget to Date Amount
Expenditure / Income Variance Trends 2025/2026 25/26
EMPLOYEE COSTS
APT & C BASIC 29,123 28,881 242
APT & C OVERTIME 98 194 (96)
APT & C SUPERANNUATION 1,917 1,836 81
APT & C NIC 3,566 3,677 (111)
APT & C TRAVEL EXPENSES 2 22 (20)
TRAVEL AND SUBSISTANCE 1 0 1
MISC TRAINEES BASIC 0 5 (5)
PENSION INCREASES 992 1,030 (38)
APPRENTICESHIP LEVY 184 184 0
EMPLOYEE COSTS 35,883 35,829 54
PROPERTY COSTS
RATES 12 12 0
SCOTTISH WATER - METERED CHARGES 0 1 (1)
RENT 4 27 (23)
SECURITY COSTS 121 162 (41)
REPAIRS & MAINTENANCE - INTERNAL CONTRATOR 3 1 2
ELECTRICITY  - CONTRACT 3 9 (6)
FIXTURE & FITTINGS 2,126 2,121 5
HEALTH & HYGIENE MATERIALS 124 110 14
REMOVAL & STORAGE COSTS 0 2 (2)
OTHER PROPERTY COSTS 1,883 1,087 796
PROPERTY COSTS 4,276 3,532 744
SUPPLIES AND SERVICES
COMPUTER EQUIPMENT PURCHASE 5,152 5,505 (353)
COMPUTER EQUIPMENT MAINTENANCE 2,141 2,001 140
I.T. EQUIPMENT MAINT - CONTRACT 659 602 57
I.T. ELECTRONIC MESSAGING 36 0 36
EQUIPMENT, APPARATUS AND TOOLS 151 115 36
SUPPLIES FOR CLIENTS 79 97 (18)
FURNITURE - OFFICE 1 5 (4)
MATERIALS 112 76 36
MATERIALS, APPARATUS AND EQUIPMENT 2 3 (1)
PUBLICATIONS, JOURNALS, NEWSPAPERS ETC. 2 3 (1)
PROVISIONS - GENERAL 20 6 14
FOOD PURCHASES WITHIN CONTRACT 1 0 1
BEVERAGES 2 2 0
PROTECTIVE CLOTHING & UNIFORMS 2 1 1
OTHER SUPPLIES AND SERVICES 518 556 (38)
HEALTH AND SAFETY 43 44 (1)
CATERING - OUTWITH CONTRACT 6 0 6
OUTSOURCED MAIL 174 217 (43)
SUPPLIES AND SERVICES 9,101 9,233 (132)
126

Page 127

South Lanarkshire Council
Revised Period 14 Period 14
Finance & Corporate Resources - Total Annual  Actual Variance
Budget to Date Amount
Expenditure / Income Variance Trends 2025/2026 25/26
TRANSPORT AND PLANT
FLEET SERVICES - FUEL 1 1 0
POOL CAR CHARGES - RENTAL 15 4 11
POOL CAR CHARGES - FUEL 3 0 3
FLEET SERVICE CHARGES 19 15 4
TRANSPORT AND PLANT 38 20 18
ADMINISTRATION
PRINTING AND STATIONERY 551 557 (6)
TELEPHONES 1,331 1,320 11
MOBILE PHONES 114 125 (11)
ADVERTISING - RECRUITMENT 29 44 (15)
ADVERTISING - OTHER 124 102 22
POSTAGES/COURIERS 1,003 1,196 (193)
SMS MESSAGING 5 6 (1)
MEMBERSHIP FEES/SUBSCRIPTIONS 269 263 6
INSURANCE 141 141 0
MEDICAL COSTS 350 351 (1)
LEGAL EXPENSES 174 177 (3)
HOSPITALITY / CIVIC RECOGNITION 31 16 15
PAYPOINT AGENCY FEES 70 68 2
SECURITY UPLIFT FEES 2 2 0
OTHER ADMIN COSTS 732 751 (19)
MEMBERS ALLOWANCES 2,335 2,271 64
CONFERENCES - MEMBERS (incl associated costs) 11 6 5
CONFERENCES - OFFICIALS (incl associated costs) 5 1 4
TRAINING 761 740 21
VOLUNTEERS' EXPENSES 16 15 1
INTERNAL SUPPORT SERVICES ALLOCATION 68 68 0
ADMINISTRATION 8,122 8,220 (98)
PAYMENT TO OTHER BODIES
OTHER LOCAL AUTHORITIES 4 0 4
GRANTS TO VOLUNTARY ORGANISATIONS 542 542 0
PAYMENTS TO OTHER BODIES 2,388 2,406 (18)
EXTERNAL AUDIT FEES 665 661 4
PRIVATE INDIVIDUALS - GENERAL 0 2 (2)
PAYMENT TO OTHER BODIES 3,599 3,611 (12)
PAYMENT TO CONTRACTORS
PAYMENT TO PRIVATE CONTRACTOR 0 1 (1)
PAYMENT TO EXTERNAL CONSULTANTS / PROFESSIONAL SERVICES 291 289 2
PAYMENT TO CONTRACTORS 291 290 1
127

Page 128

South Lanarkshire Council
Revised Period 14 Period 14
Finance & Corporate Resources - Total Annual  Actual Variance
Budget to Date Amount
Expenditure / Income Variance Trends 2025/2026 25/26
TRANSFER PAYMENTS
RENT ALLOWANCE 17,581 17,232 349
RENT REBATES 32,482 32,464 18
TRANSFER PAYMENTS 50,063 49,696 367
FINANCING CHARGES
LEASING CHARGES - FINANCE 0 (1) 1
I.T. EQUIPMENT LEASING-CONTRACT 1,626 1,816 (190)
FINANCING CHARGES 1,626 1,815 (189)
TOTAL EXPENDITURE 112,999 112,246 753
INCOME
STATUTORY ADDITIONS - COST OF COLLECTION (1,003) (1,043) 40
RENT REBATES SUBSIDY (27,191) (26,795) (396)
RENT ALLOWANCE SUBSIDY (17,067) (16,813) (254)
DWP SUBSIDY (1,170) (1,165) (5)
DHP 0 (656) 656
CONTRIBUTIONS FROM DEVELOPMENT AGENCIES (150) (137) (13)
CONTRIBUTIONS FROM OTHER BODIES (334) (242) (92)
SALES - DEPARTMENTS OF THE AUTHORITY (20) 0 (20)
FEES AND CHARGES - GENERAL (4,845) (5,457) 612
CHARGES TO HEALTH BOARDS (45) (45) 0
FEES AND CHARGES - OTHER BODIES (221) (238) 17
FEES AND CHARGES - DEPARTMENTS OF THE AUTHORITY (2,627) (2,703) 76
HOME LOANS REPAYMENTS (5) (4) (1)
BIRTH REGISTRATION (16) (15) (1)
DEATH REGISTRATION (64) (63) (1)
MARRIAGE STATUTORY FEES (108) (121) 13
EXTRACT ISSUE (83) (94) 11
MARRIAGES (52) (48) (4)
CITIZENSHIP CEREMONIES (18) (17) (1)
CIVIL PARTNERSHIPS (1) 0 (1)
OTHER INCOME (6,685) (6,297) (388)
REALLOCATION OF CENTRAL SUPPORT COSTS (7,092) (7,065) (27)
INCOME (68,797) (69,018) 221
NET EXPENDITURE 44,202 43,228 974
128

Page 129

Appendix D
South Lanarkshire Council
Revenue Budget Monitoring Statement
Period Ended 31 March 2026 (No 14)
Housing and Technical Resources
Committee Revised Projected Projected Actual Variance %
Annual Outturn Outturn to Period 14 to Period 14
Budget Variance 31/03/26 31/03/26
Before
Transfers
Service Departments :- £m £m £m £m £m
Housing Services 9.519 9.285 0.234 9.658 (0.139) (1.46%)
Property Services 11.864 11.975 (0.111) 11.602 0.262 2.21%
Position Before Transfer to Reserves 21.383 21.260 0.123 21.260 0.123 0.58%
Transfers to Reserves as at 31/03/2026 0.123 (0.123) (0.58%)
Position After Transfers to Reserves at 31/03/2026 21.383 (0.000) (0.00%)
8
129

Page 130

Housing and Technical Resources (excl HRA) Variance Analysis 2025/26 (Period 14) 
Subjective Head Variance  Subjective line Service / amount Explanation
Employee Costs 1,762k
under
APT&C Basic / Overtime /
Superannuation / National
Insurance – 1,992k under
Property Services –
2,028k under 
The variance relates to vacancies which
are being recruited in line with Service
requirements.  
Manual Workers – (192k) over  Property Services –
(192k) over 
The variance relates to the current level
of trade operatives and overtime required
to meet service demands. 
Property Costs (1,638k)
over
Rates – (114k) over  Property Services –
(112k) over 
The variance relates to greater than
budgeted rates charges for Council
properties mainly within the Estates
Service. 
Scottish Water – Metered
Charges – (79k) over 
Property Services –
(76k) over 
The overspend related to increase water
charges within the Office Accommodation
and Estates services. 
Rent – (120k) over Property Services –
(92k) over
The overspend relates to an increase in
rent charges for corporate buildings and
for the use of industrial units within
Building Services. 
Service Charge – (304k) over Property Services –
(303k) over
The overspend relates to the cost of
shopping centre service charges which
are not recoverable from tenants. 
130

Page 131

Subjective Head Variance  Subjective line Service / amount Explanation
Property Costs
(cont.) 
Bed & Breakfast – (362k) over Housing Services –
(362k) over 
The variance relates to greater than
budgeted demand for bed & breakfast
within the Homelessness service.  
Security Costs – 115k under  Property Services –
115k under 
This variance relates to lower than
anticipated security costs within Building
Services partially offset by greater than
budgeted expenditure on CCTV security
costs, due to CCTV infrastructure project
delay. 
Repairs & Maintenance – Internal
and External Contractors/ Life
Cycle Maintenance – (747k) over 
Housing Services –
(78k) over 
The overspend relates to additional
expenditure on the maintenance of
homelessness property. 
Property Services –
(669k) over 
The overspend mainly relates to
additional expenditure on the
maintenance of the corporate estate. 
Housing Rent Unlet Period/Bad
Periods – (175k) over
Property Services –
41k under
The underspend is due to lower than
expected unlet properties within the
Estates service.   
Housing Services –
(216k) over
The overspend is due to greater than
expected bad debt write off within the
Homelessness service. 
Gas – 65k under  Property Services –
65k under
The underspend relates to lower than
anticipated gas charges for corporate
buildings.
131

Page 132

Subjective Head Variance  Subjective line Service / amount Explanation
Property Costs
(cont.) 
Fixture & Fittings – (347k) over Property Services –
(198k) over 
Housing Services –
(149k) over
The overspend relates to expenditure
that should have been included within the
materials budget. 
This relates to the furniture costs within
homeless temporary accommodation and
is demand led. 
Refuse Uplift – 366k under Property Services –
366k under
The overspend relates to expenditure on
skips and is offset by an underspend on
hire of skips within Transport and Plant
below 
Other Property Costs – 141k
under
Housing Services –
132k under
The underspend relates to funding
received for Ukraine Resettlement and
will be transferred to reserves at the end
of the financial year. 
Supplies &
Services
(629k) over Computer Equipment Purchase –
(66k) over
Property Services –
(62k) over
The overspend is due to greater than
anticipated IT expenditure within
Consultancy Services. 
IT Equipment/Apparatus – 234k
under 
Property Services –
235k under
The underspend is due to lower than
anticipated expenditure on IT system
costs within Building Services. 
Materials/Stock/Store Issues –
(745k) over
Property Services –
(745k) over
Expenditure on materials varies
depending on the current workload
demands and timing of works on a wide
variety of capital and revenue works. 
132

Page 133

Subjective Head Variance  Subjective line Service / amount Explanation
Transport & Plant (653k) over Purchase Of Plant & Equipment
– (62k) over 
Property Services –
(62k) over 
The overspend relates to the
replacement of tools within Building
Services. 
Fleet Service Charges – (599k)
over
Property Services –
(629k) over
The overspend relates to greater than
budgeted fleet service charges on
leasing, fuel and vehicle maintenance
within Building Services.  
Hire of Scaffolding – 294k under Property Services –
249k under
Expenditure on hires varies depending on
the workload demands and timing of
works on a wide variety of capital and
revenue works. 
Hire of Skips – (420k) over Property Services –
(420k) over
The overspend is offset by an
underspend in refuse uplift within
Property Costs above.
Administration (136k) over  Mobile Phones – (74k) over Property Services –
(73k) over
The overspend relates to mobile phone
charges within Building Services being
greater than budgeted. 
Payment to
Other Bodies
(142k) over Other Committees of the
Authority – (148k) over
Property Services –
(148k) over
The overspend relates to greater than
budgeted recovery of internal support
costs within Building Services. 
Payment to Other Bodies –
(250k) over
Property Services –
(179k) over 
The variance relates to payments to other
bodies within the Estates Service which is
offset by an underspend in Estates
employee costs     
133

Page 134

Subjective Head Variance  Subjective line Service / amount Explanation
Payments to
Other Bodies
(cont.) 
Assistance to Home Owners –
276k under 
Property Services –
276k under
This variance reflects the timing of spend
on grants to owners to date.
Payment to
Contractors 
(1,932k)
over
Payment to Private Contractors –
514k under
Property Services –
126k under
The underspend relates to the lower than
anticipated payments to sub contractors
for work within Building Services. 
Housing Services –
388k under 
The underspend relates to commissioned
services in the Homelessness budget
where expenditure varies according to
service requirements. 
Payment to External Consultant
– (2,446k) over 
Property Services –
(2,446k) over 
This overspend is mainly due to the
nature of some major projects requiring
increased use of specialist consultants
and is partially offset by an underspend in
employee costs. 
Income 3,565k over
recovered 
Fees & Charges – 158k over
recovered
Property Services –
(83k) under
recovered 
The under recovery is due to service
charges for rental properties within
Estates being less than anticipated. 
Housing Services –
241k over recovered 
The over recovery in income is mainly
due to increased demand for the use of
bed and breakfast during 25/26. 
Rental Income – (377k) under
recovered 
Property Services –
(377k) under
recovered 
Income is under recovered due to lower
than budgeted rental income within Office
Accommodation and Estates service. 
134

Page 135

Subjective Head Variance  Subjective line Service / amount Explanation
Income (cont.)  House Rents – 39k over
recovered
Housing Services –
39k over recovered
The over recovery relates to more house
rent income than budgeted within the
Homelessness service.     
Recovery from
Capital/Recharges and Manual
Recharges – Departments of
Authority – 3,631k over
recovered 
Property Services –
3,631k over
recovered 
The level of income recovered varies
depending on the current workload, the
timing of a wide variety of projects and is
offset by a reduction in expenditure. 
135

Page 136

South Lanarkshire Council
Revised Period 14 Period 14
Housing & Technical Resources Annual  Actual Variance
Budget to Date Amount
Expenditure / Income Variance Trends 2025/2026 25/26
EMPLOYEE COSTS
APT & C BASIC 18,019 16,445 1,574
APT & C OVERTIME 195 168 27
APT & C SUPERANNUATION 1,197 1,026 171
APT & C NIC 2,327 2,107 220
MANUAL BASIC 21,061 20,467 594
MANUAL OVERTIME 338 1,216 (878)
MANUAL SUPERANNUATION 1,366 1,323 43
MANUAL NIC 2,741 2,692 49
TRAVEL AND SUBSISTANCE 23 6 17
OTHER EMPLOYEE COSTS (22) (4) (18)
PENSION INCREASES 615 652 (37)
APPRENTICESHIP LEVY 190 190 0
EMPLOYEE COSTS 48,050 46,288 1,762
136

Page 137

South Lanarkshire Council
Revised Period 14 Period 14
Housing & Technical Resources Annual  Actual Variance
Budget to Date Amount
Expenditure / Income Variance Trends 2025/2026 25/26
PROPERTY COSTS
RATES 2,253 2,367 (114)
SCOTTISH WATER - UNMETERED CHARGES 8 1 7
SCOTTISH WATER - METERED CHARGES 236 315 (79)
RENT 1,873 1,993 (120)
SERVICE CHARGE 420 724 (304)
FACTORING CHARGES 5 0 5
OTHER ACCOMMODATION COSTS 3,497 3,449 48
BED AND BREAKFAST 27 389 (362)
PROPERTY INSURANCE 390 404 (14)
SECURITY COSTS 260 145 115
GROUND MAINTENANCE 52 53 (1)
GROUNDS MAINTENANCE ADDITIONAL WORKS 10 2 8
REPAIRS & MAINTENANCE - INTERNAL CONTRACTOR 3,312 4,541 (1,229)
LIFE CYCLE MAINTENANCE 5,054 3,768 1,286
REPAIRS & MAINTENANCE - EXTERNAL CONTRACTOR 352 1,156 (804)
HOUSING - RENT W/O UNLET PERIODS 919 991 (72)
HOUSING - RENT W/O BAD PERIODS 768 871 (103)
ASBESTOS 0 32 (32)
WATER QUALITY 0 (1) 1
FIXED ELECTRICAL 0 31 (31)
EPC 0 11 (11)
ELECTRICITY  - CONTRACT 1,522 1,546 (24)
ELECTRICITY  - NON CONTRACT 27 22 5
GAS 514 449 65
HEATING OIL 12 13 (1)
FIXTURE & FITTINGS 847 1,194 (347)
JANITOR SERVICE 152 152 0
CLEANING CONTRACT 401 401 0
CLEANING OUTWITH CONTRACT 0 9 (9)
CLEANING MATERIALS 10 3 7
WINDOW CLEANING 2 1 1
PEST CONTROL 6 0 6
REFUSE UPLIFT 395 29 366
REMOVAL & STORAGE COSTS 62 40 22
OTHER PROPERTY COSTS 745 604 141
OFFICE ACCOM-FACILITIES MANAGEMENT 1,045 1,089 (44)
ACCOMMODATION RECHARGE TO USERS 33 53 (20)
PROPERTY COSTS 25,209 26,847 (1,638)
137

Page 138

South Lanarkshire Council
Revised Period 14 Period 14
Housing & Technical Resources Annual  Actual Variance
Budget to Date Amount
Expenditure / Income Variance Trends 2025/2026 25/26
SUPPLIES AND SERVICES
COMPUTER EQUIPMENT PURCHASE 520 586 (66)
COMPUTER EQUIPMENT MAINTENANCE 6 0 6
I.T. EQUIPMENT MAINT-CONTRACT 207 16 191
EQUIPMENT, APPARATUS AND TOOLS 45 2 43
ADAPTATIONS FOR CLIENTS 500 508 (8)
FURNITURE - OFFICE 0 5 (5)
MATERIALS 10,813 5,254 5,559
STOCK/STORE ISSUES 0 6,304 (6,304)
MATERIALS, APPARATUS AND EQUIPMENT 0 3 (3)
AUDIO VISUAL 10 51 (41)
TV LICENCES - EDUCATION 1 3 (2)
FOOD PURCHASES WITHIN CONTRACT 0 13 (13)
BEVERAGES 0 1 (1)
PROTECTIVE CLOTHING & UNIFORMS 44 38 6
OTHER SUPPLIES AND SERVICES 90 66 24
HEALTH AND SAFETY 1 1 0
OUTSOURCED MAIL 0 22 (22)
DELIVERY CHARGE 0 1 (1)
BULK BUYING DISCOUNT 0 (8) 8
SUPPLIES AND SERVICES 12,237 12,866 (629)
TRANSPORT AND PLANT
PURCHASE OF VEHICLES 0 4 (4)
PURCHASE OF PLANT 125 187 (62)
FLEET SERVICES - FUEL 4 29 (25)
POOL CAR RECHARGE - RENTAL CHARGE 54 41 13
POOL CAR RECHARGE - FUEL 18 0 18
POOL CAR RECHARGE - ADDITIONAL CHARGES 1 0 1
OTHER TRANSPORT COSTS 0 12 (12)
TRANSPORT INSURANCE 44 44 0
LICENCES 0 1 (1)
PLANT SERVICES 7 12 (5)
FLEET SERVICE CHARGES 2,961 3,560 (599)
HIRE OF EXTERNAL PLANT 257 106 151
HIRE OF SCAFOLDING 1,077 783 294
HIRE OF SKIPS 33 453 (420)
EXTERNAL TRANSPORT CONTRACT 8 10 (2)
TAXI CHARGES - CONTRACTED 5 5 0
TRANSPORT AND PLANT 4,594 5,247 (653)
138

Page 139

South Lanarkshire Council
Revised Period 14 Period 14
Housing & Technical Resources Annual  Actual Variance
Budget to Date Amount
Expenditure / Income Variance Trends 2025/2026 25/26
ADMINISTRATION
PRINTING AND STATIONERY 78 83 (5)
TELEPHONES 101 63 38
MOBILE PHONES 40 114 (74)
ADVERTISING - OF COUNCIL SERVICE AVAILABILITY 0 4 (4)
ADVERTISING - OTHER 6 1 5
POSTAGES/COURIERS 12 38 (26)
SMS MESSAGING 0 1 (1)
MEMBERSHIP FEES/SUBSCRIPTIONS 15 23 (8)
INSURANCE 216 210 6
MEDICAL COSTS 16 46 (30)
LEGAL EXPENSES 22 31 (9)
PETTY OUTLAYS 12 13 (1)
HOSPITALITY / CIVIC RECOGNITION 3 1 2
PAYPOINT AGENCY FEES 0 4 (4)
OTHER ADMIN COSTS 8 2 6
TRAINING 0 31 (31)
INTERNAL SUPPORT SERVICES ALLOCATION 457 457 0
CENTRAL ADMINISTRATION 3,157 3,157 0
ADMINISTRATION 4,143 4,279 (136)
PAYMENT TO OTHER BODIES
OTHER COMMITTEES OF THE AUTHORITY 2,461 2,609 (148)
OTHER LOCAL AUTHORITIES 0 15 (15)
PAYMENTS TO OTHER BODIES 2,659 2,909 (250)
SUPPORTING PEOPLE INTERNAL PROVIDER 1,129 1,129 0
SUPPORTING PEOPLE EXTERNAL PROVIDER 419 419 0
HOUSING ADMINISTRATION 885 885 0
ASSISTANCE TO HOME OWNERS 1,394 1,118 276
PRIVATE INDIVIDUALS - GENERAL 151 156 (5)
PAYMENT TO OTHER BODIES 9,098 9,240 (142)
PAYMENT TO CONTRACTORS
PAYMENT TO LOCAL AUTHORITY CONTRACTOR 1,105 1,105 0
PAYMENT TO PRIVATE CONTRACTOR 16,456 15,942 514
PAYMENT TO EXTERNAL CONSULTANTS 306 2,752 (2,446)
PAYMENT TO CONTRACTORS 17,867 19,799 (1,932)
TRUST FUND EXPENDITURE
TRANSFER PAYMENTS
FINANCING CHARGES
I.T. EQUIPMENT LEASING-CONTRACT 154 230 (76)
INTEREST ON REVENUE BALANCES 2 0 2
FINANCING CHARGES 156 230 (74)
139

Page 140

South Lanarkshire Council
Revised Period 14 Period 14
Housing & Technical Resources Annual  Actual Variance
Budget to Date Amount
Expenditure / Income Variance Trends 2025/2026 25/26
TOTAL EXPENDITURE 121,354 124,796 (3,442)
INCOME
CONTRIBUTIONS FROM OTHER BODIES (3,372) (3,438) 66
SALES - DEPARTMENTS OF THE AUTHORITY (460) (463) 3
FEES AND CHARGES - GENERAL (546) (704) 158
FEES AND CHARGES - DEPARTMENTS OF THE A (46) (48) 2
RENTAL INCOME (4,209) (3,832) (377)
HOUSE RENTS (7,375) (7,414) 39
OTHER INCOME (2,747) (2,727) (20)
REALLOCATION OF CENTRAL SUPPORT COSTS (946) (945) (1)
REALLOCATION OF SUPPORT COSTS (1,630) (1,664) 34
RECOVERY FROM CAPITAL (28,350) (24,806) (3,544)
RECHARGES - DEPARTMENTS OF AUTHORITY (50,290) (50,228) (62)
MANUAL RECHARGES - DEPARTMENTS OF AUTHORITY 0 (7,267) 7,267
INCOME (99,971) (103,536) 3,565
NET EXPENDITURE 21,383 21,260 123
140

Page 141

Appendix E
Housing and Technical Resources (HRA) Variance Analysis 2025/26 (Period 14)   
Subjective Head Variance  Subjective line Service / amount Explanation
Employee Costs 93k under  APT&C Basic/Overtime/
Superannuation/National
Insurance/Travel/Pensions –
157k under 
HRA The underspend is mainly due to
vacancies across the service. 
Property Costs 476k under  Grounds Maintenance and
Additional Works – 61k  
under 
HRA  The underspend is due to lower than
anticipated charges for special uplifts. 
Repairs and Maintenance –
Internal and External Contractor/
Life Cycle Maintenance – (221k)
over 
HRA The overspend reflects the current
demand for repairs and continuing high
cost of voids. The position includes a
recharge for recovery of costs from
chargeable services. 
Housing – Rent: Free
Accommodation/Write off Unlet
Periods/Bad Periods – 661k
under 
HRA The net underspend reflects a lower than
anticipated level of void rent loss along
with lower bad debt provision. During the
year, collection rates for rental income
have been better than forecast, which is
due in part to schemes such as the
tenancy sustainment fund mitigating the
overall level of debt. 
Electricity/Gas/Heating Oil/Solid
Fuel – 104k under 
HRA The forecast underspend is due to lower
than budgeted utility expenditure on
communal areas within HRA. 
8
141

Page 142

Subjective Head Variance  Subjective line Service / amount Explanation
Property Costs
(cont.) 
Fixtures and Fittings – (88k) over  HRA This budget is demand led and the
overspend reflects the increased demand
during the year. 
Cleaning Contract – (110k) over  HRA The overspend is due to greater than
budgeted charges for Facilities
Management cleaning charges within the
overall HRA service. 
Pest Control – (54k) over  HRA The overspend is due to increased
demand for pest control services within
the overall HRA service. 
Payment to
Other Bodies 
(1,508k)
over 
Other Committees of the
Authority – (846k) over
HRA The overspend is due to the release of
HRA surplus to the General Fund from
reduced CFCR requirement in the
financial year along with reduced
requirement from reserves for IT
systems. 
Payment to Other Bodies –
(659k) over
HRA This relates to greater than anticipated
costs incurred in relation to the provision
of support to current IT systems 
Financing
Charges
148k under CFCR – 177k under  HRA  The underspend is due to the reduced
CFCR requirement in the financial year
from the use of general capital grant to
fund the 2025/26 Housing Capital
Programme. 
142

Page 143

Subjective Head Variance  Subjective line Service / amount Explanation
Income 243k over 
recovered 
House/Lock Up Rents – 260k
over recovered
HRA The over recovery is due to the timing of
new builds which were completed ahead
of the anticipated profiles. 
Year End Transfer from the
Balance Sheet – (95k) under
recovered 
HRA The budget assumes a level of transfer
from reserves, due to the current net
underspend across the service. This is
mainly as a result of increased income
from house rents, less than anticipated
void rent loss and the less than
anticipated Loan Charges reflecting the
level of deposit interest received in year
being greater than anticipated, as well as
the benefit of interest on Revenue
Balances 
143

Page 144

South Lanarkshire Council
Revised Period 14 Period 14
Housing and Revenue Account Annual  Actual Variance
Budget to Date Amount
Expenditure / Income Variance Trends 2025/2026 25/26
EMPLOYEE COSTS
APT & C BASIC 12,591 12,558 33
APT & C OVERTIME 69 63 6
APT & C SUPERANNUATION 820 813 7
APT & C NIC 1,626 1,535 91
TRAVEL AND SUBSISTANCE 35 3 32
PENSION INCREASES 219 231 (12)
APPRENTICESHIP LEVY 0 64 (64)
EMPLOYEE COSTS 15,360 15,267 93
PROPERTY COSTS
RATES 72 77 (5)
SCOTTISH WATER - UNMETERED CHARGES 4 0 4
SCOTTISH WATER - METERED CHARGES 8 10 (2)
RENT 6 0 6
SERVICE CHARGE 94 90 4
FACTORING CHARGES 0 4 (4)
OTHER ACCOMMODATION COSTS 1 24 (23)
BED AND BREAKFAST 0 1 (1)
PROPERTY INSURANCE 3,497 3,465 32
SECURITY COSTS 55 6 49
GROUND MAINTENANCE 4,263 4,190 73
GROUNDS MAINTENANCE ADDITIONAL WORKS 0 12 (12)
REPAIRS & MAINTENANCE - INTERNAL CONTRACTOR 46,527 46,137 390
LIFE CYCLE MAINTENANCE 0 176 (176)
REPAIRS & MAINTENANCE - EXTERNAL CONTRACTOR 901 1,336 (435)
HOUSING - RENT FREE ACCOMMODATION 266 152 114
HOUSING - RENT W/O UNLET PERIODS 2,937 2,550 387
HOUSING - RENT W/O BAD PERIODS 1,250 1,090 160
ASBESTOS 143 102 41
FIXED ELECTRICAL 0 3 (3)
EPC 0 (1) 1
ELECTRICITY  - CONTRACT 1,350 1,287 63
ELECTRICITY  - NON CONTRACT 0 14 (14)
GAS 438 415 23
HEATING OIL 54 19 35
SOLID FUEL 4 7 (3)
FIXTURE & FITTINGS 53 141 (88)
JANITOR SERVICE 43 30 13
CLEANING CONTRACT 385 495 (110)
CLEANING MATERIALS 57 25 32
HEALTH & HYGIENE MATERIALS 0 1 (1)
WINDOW CLEANING 16 21 (5)
PEST CONTROL 122 176 (54)
REFUSE UPLIFT 0 34 (34)
REMOVAL & STORAGE COSTS 14 25 (11)
OTHER PROPERTY COSTS 32 1 31
PROPERTY COSTS 62,592 62,115 477
144

Page 145

South Lanarkshire Council
Revised Period 14 Period 14
Housing and Revenue Account Annual  Actual Variance
Budget to Date Amount
Expenditure / Income Variance Trends 2025/2026 25/26
SUPPLIES AND SERVICES
COMPUTER EQUIPMENT PURCHASE 295 251 44
COMPUTER EQUIPMENT RENTAL 0 2 (2)
COMPUTER EQUIPMENT MAINTENANCE 0 10 (10)
I.T. EQUIPMENT MAINT-CONTRACT 0 1 (1)
I.T. ELECTRONIC MESSAGING 0 4 (4)
EQUIPMENT, APPARATUS AND TOOLS 13 29 (16)
FURNITURE - OFFICE 10 4 6
MATERIALS 0 31 (31)
MATERIALS, APPARATUS AND EQUIPMENT 0 2 (2)
PROVISIONS 2 5 (3)
BEVERAGES 4 0 4
PROTECTIVE CLOTHING & UNIFORMS 12 10 2
LAUNDRY COSTS 16 43 (27)
OTHER SUPPLIES AND SERVICES 38 11 27
HEALTH AND SAFETY 15 0 15
CATERING - CONTRACT 0 1 (1)
CATERING - OUTWITH CONTRACT 0 1 (1)
OUTSOURCED MAIL 0 22 (22)
SUPPLIES AND SERVICES 405 427 (22)
TRANSPORT AND PLANT
PURCHASE OF VEHICLES 0 4 (4)
FLEET SERVICES - FUEL 0 19 (19)
POOL CAR RECHARGE - RENTAL CHARGE 26 6 20
POOL CAR RECHARGE - FUEL 6 0 6
POOL CAR RECHARGE - ADDITIONAL CHARGES 1 0 1
OTHER TRANSPORT COSTS 0 11 (11)
FLEET SERVICE CHARGES 158 149 9
HIRE OF SKIPS 0 4 (4)
STORAGE 4 0 4
TRANSPORT AND PLANT 195 193 2
145

Page 146

South Lanarkshire Council
Revised Period 14 Period 14
Housing and Revenue Account Annual  Actual Variance
Budget to Date Amount
Expenditure / Income Variance Trends 2025/2026 25/26
ADMINISTRATION
PRINTING AND STATIONERY 79 79 0
BULK PRINTING 68 0 68
TELEPHONES 95 77 18
MOBILE PHONES 34 56 (22)
ADVERTISING - OTHER 12 0 12
POSTAGES/COURIERS 171 150 21
SMS MESSAGING 0 5 (5)
MEMBERSHIP FEES/SUBSCRIPTIONS 38 41 (3)
MEDICAL COSTS 25 22 3
LEGAL EXPENSES 16 68 (52)
PETTY OUTLAYS 4 0 4
HOSPITALITY / CIVIC RECOGNITION 0 2 (2)
GIRO BANK AGENCY FEES 4 0 4
PAYPOINT AGENCY FEES 13 36 (23)
INTERNET AGENCY FEES 3 0 3
OTHER ADMIN COSTS 15 19 (4)
CONFERENCES - OFFICIALS 7 3 4
INTERNAL SUPPORT SERVICES ALLOCATION 5,020 5,019 1
ADMINISTRATION 5,604 5,577 27
PAYMENT TO OTHER BODIES
OTHER COMMITTEES OF THE AUTHORITY 11,839 12,685 (846)
OTHER LOCAL AUTHORITIES 0 3 (3)
GRANTS TO VOLUNTARY ORGANISATIONS 3 (2) 5
PAYMENTS TO VOLUNTARY ORGANISATIONS 31 19 12
PAYMENTS TO OTHER BODIES 567 1,226 (659)
ASSISTANCE TO HOME OWNERS 0 19 (19)
PRIVATE INDIVIDUALS - GENERAL 150 148 2
PAYMENT TO OTHER BODIES 12,590 14,098 (1,508)
PAYMENT TO CONTRACTORS
PAYMENT TO LOCAL AUTHORITY CONTRACTOR 0 63 (63)
PAYMENT TO PRIVATE CONTRACTOR 80 92 (12)
PAYMENT TO EXTERNAL CONSULTANTS 342 329 13
PAYMENT TO CONTRACTORS 422 484 (62)
FINANCING CHARGES
I.T. EQUIPMENT LEASING-CONTRACT 141 170 (29)
CFCR 25,992 25,815 177
FINANCING CHARGES 26,133 25,985 148
TOTAL EXPENDITURE 123,301 124,146 (845)
146

Page 147

South Lanarkshire Council
Revised Period 14 Period 14
Housing and Revenue Account Annual  Actual Variance
Budget to Date Amount
Expenditure / Income Variance Trends 2025/2026 25/26
INCOME
SPECIFIC GRANT 0 (10) 10
CONTRIBUTIONS FROM OTHER BODIES 0 (8) 8
SALES - DEPARTMENTS OF THE AUTHORITY (1,101) (1,135) 34
FEES AND CHARGES - GENERAL (4,561) (4,598) 37
RENTAL INCOME (465) (479) 14
HOUSE RENTS (121,449) (121,754) 305
LOCK UP RENTS (2,911) (2,866) (45)
INSURANCE RECOVERIES (1,350) (1,350) 0
OTHER INCOME (1,265) (1,257) (8)
REALLOCATION OF SUPPORT COSTS (717) (619) (98)
TRADING SERVICES RECHARGES 0 (2) 2
TMC BALANCE TO BAL SHEET 0 (79) 79
YEAR END T/FER TO BALANCE SHEET (4,076) (3,981) (95)
INCOME (137,895) (138,138) 243
NET EXPENDITURE (14,594) (13,992) (602)
147

Page 148

148

Page 149

Appendix E
South Lanarkshire Council
Revenue Budget Monitoring Statement
Period Ended 31 March 2026 (No 14)
Social Work Resources
Committee Revised Projected Projected Actual Variance %
Annual Outturn Outturn to Period 14 to Period 14
Budget Variance 31/03/26 31/03/26
Before
Transfers
Service Departments :- £m £m £m £m £m
Performance and Support Services 6.213 5.905 0.308 5.586 0.627 10.09%
Children and Families 52.819 50.714 2.105 49.966 2.853 5.40%
Adults and Older People 192.502 191.252 1.250 191.252 1.250 0.65%
Justice and Substance Misuse 0.910 0.228 0.682 0.248 0.662 72.75%
Position Before Transfer to Reserves 252.444 248.099 4.345 247.052 5.392 2.14%
Transfers to Reserves as at 31/03/2026 5.392 (5.392) (2.14%)
Position After Transfers to Reserves at 31/03/2026 252.444 (0.000) (0.00%)
8
149

Page 150

Social Work Resources Variance Analysis 2025/26 (Period 14) 
Subjective Head Variance Subjective line Service / amount Explanation
Employee Costs  4,217k under Admin & Clerical Staff – 498k under 
Basic Grade Social Workers – 2,418k
under 
Adult and Older People –
122k under 
Performance and
Support – 250k under 
Justice – 99k under 
Adult and Older People –
1,216k under 
Children and Family -
982k under 
Justice - 213k under 
This relates to the underspends
to Scheduling Assistant
vacancies in Homecare, which
are being recruited. This is offset
by overtime costs for Managerial
Support Specialist Staff (below).   
This is a result of vacancies
which are actively being
recruited. 
This is a result of vacancies
which are actively being
recruited. 
This is a result of vacancies
which are actively being
recruited. 
This is a result of vacancies
which are actively being
recruited. 
This is a result of new posts
approved at committee which are
actively being recruited to. This
results in an in-year underspend. 
150

Page 151

Subjective Head Variance Subjective line Service / amount Explanation
Employee Costs
(cont.) 
Managerial Support Specialist Staff –
368k under 
Care Staff – (117k) over 
Adult and Older People –
(940k) over 
Children and Family -
841k under 
Performance and
Support – 170k under 
Justice - 325k under 
Children & Family –
(398k) over 
Adult & Older People –
289k under 
This overspend is a result of
turnover being less than
anticipated to date, and overtime
spend to cover the Scheduling
Assistant vacancies in Homecare 
This is a result of vacancies
which are actively being
recruited. 
This is a result of vacancies
which are actively being
recruited. 
This is a result of new posts
approved at committee which are
actively being recruited to. This
results in an in-year underspend. 
This overspend is due to a
provision being made for a job
evaluation where the
implementation date will be part
way through the 2025/26 financial
year. 
This is a result of vacancies
which are actively being
recruited. 
151

Page 152

Subjective Head Variance Subjective line Service / amount Explanation
Employee Costs
(cont.) 
Instructors – 85k under 
Manual Workers (Home Carers) – 442k
under 
Other Employee Costs - 396k under
Adult and Older People –
85k under 
Adult and Older People – 
526k under 
Children & Family – 371k
under 
This underspend relates to
vacancies within day care
services 
This is a result of vacancies
which are actively being
recruited. 
This is a funding solution
identified as part of the overall
budget recovery plan. 
Property Costs  (15k) over Rates – (98k) over 
Rent - (52k) over 
Repairs & Maintenance –Internal (96k)
over 
Adult and Older People –
(91k) over 
Adult and Older People –
(45k) over 
Children & Family –
(49k) over 
Adult and Older People –
(37k) over 
Additional rates for closed
centers that previously had 100%
relief. 
This overspend is in respect of
rental charges for residential care
homes.   
This non-recurring overspend is
met by an underspend against
other property costs. 
This non-recurring overspend is
due to several small higher than
anticipated spends in relation to
repairs and maintenance across
A&OP services. 
152

Page 153

Subjective Head Variance Subjective line Service / amount Explanation
Property Costs
(cont.) 
Electricity - 107k under 
Gas – 101k under 
Other Property Costs – 72k under 
Adult and Older People –
99k under 
Adult and Older People –
93k under 
Children & Family – 50k
over 
The underspend reflects a
reduction in price. 
The underspend reflects a
reduction in price. 
This underspend is being used to
fund the overspend against
internal repairs 
Supplies and
Services 
2k under IT Equipment Maintenance - Contract – 
(55k) over 
IT Electronic Messaging – (53k) over 
Aids for Clients – 135k under 
Supplies for Clients – 107k under 
Performance and
Support – (40k) over 
Adult and Older People –
(53k) over 
Adult and Older People –
137k under 
Children & Family – 89k
under 
This is offset by an underspend in
IT equipment Leasing of 28k 
The overspend reflects higher
than anticipated costs within In-
house residential and Homecare
services. 
The underspend reflects the
requirement to purchase and
replace existing assistive
technology equipment which is
used to support service users to
remain at home. 
The spend on supplies can be
ad-hoc in nature. Underspend
can be used to offset overspends
in other areas. 
153

Page 154

Subjective Head Variance Subjective line Service / amount Explanation
Supplies and
Services (cont.)
Food Purchases within Contract - 65k
under 
Protective Clothing & Uniforms – (143k)
over 
Catering – Contract – (55k) over 
Adult and Older People –
63k under 
Adult and Older People –
(169k) over 
Adult and Older People –
(55k) over
The underspend is due to lower
than anticipated spend on food
purchases mainly within
residential care homes. 
This overspend relates to
additional demand for Telecare
technology. 
The overspend is due to higher
than anticipated recharges.
Transport and
Plant 
(114k) over Pool Car Recharge – Rental Charge
(67k) over 
Other Transport Costs – 73k under 
Fleet Service Charges - (134k) over 
Children and Family
(70k) over 
Adult and Older People –
82k under 
Adult and Older People –
(£155k) over 
The overspend reflects the
demand and arrangements for
pool cars. An internal review of
use is being undertaken to
reduce future pressure. 
The underspend reflects the
current demand for external
service. 
The overspend relates to
slippage in the 2024/25 saving for
the decommissioning of Fleet
buses that are no longer
required. An action plan is being
developed to ensure costs are
reduced to achieve the saving in
full. Alongside an overspend in
Homecare due to aging vehicles.
154

Page 155

Subjective Head Variance Subjective line Service / amount Explanation
Administration  (81k) over Printing and Stationery – (50k) over 
Telephones – 65k under 
Legal Expenses – (83k) over 
Adult and Older People –
(54k) over 
Performance and
Support – 64k under 
Adult and Older People –
(82k) over 
This overspend is due to non-
recurring higher than anticipated
spend within home care service. 
The underspend is a result of
decreased recharges due to a
reduction in demand for the
service. 
This overspend is due an
increase in legal costs in relation
to Adults with Incapacity and
guardianship orders and demand
led overspends in other admin
lines. 
Payment to Other
Bodies 
(295k) over  Payment to Other Bodies - 292k under 
Payment to Voluntary Organisations –
23k under 
Adult and Older People -
94k under 
Children and Family –
179k under 
Children and Family -
66k Under 
Justice – (59k) over 
The underspend is as a result of
several small underspends within
Adult and Older service. 
This is a funding solution
identified as part of the overall
budget recovery plan. 
This is a funding solution
identified as part of the overall
budget recovery plan. 
This overspend is related to
payments for intensive support
packages and gender-based
155

Page 156

Subjective Head Variance Subjective line Service / amount Explanation
Payments to
Other Bodies
(cont.)   
Payment to Private Individuals– 207k
under 
Social Work – Foster Parents – (360k)
over 
Social Work – Adoption Allowance-
(370k) over 
Children and Family –
246k under 
Children and Family –
(360k) over 
Children and Family –
(370k) over 
violence which are offset by
additional income received. 
There has been a reduction in the
number of supported carers and
use of the shared care scheme.
However, work has been
undertaken to attract new carers
in these areas. 
This recurring overspend is
attributable to the requirement to
purchase external foster
placements. 
This overspend relates to the
number of adoptive carers being
paid an ongoing adoption
allowance. It also relates to
interagency adoption payments
where carers have been
identified out with South
Lanarkshire. 
Payment to
Contractors 
1,217k under Payment to Local Authority – (66k) over 
Payment to Private Contractors –
Payment to Col Org Care Element–
690k under
Adult and Older People –
(66k) over 
Children and Family – 
690k under 
This overspend relates to non-
recurring costs in relation to
approved spend for the
refurbishment of Parkhall House. 
This underspend represents a
temporary funding solution as
156

Page 157

Subjective Head Variance Subjective line Service / amount Explanation
Payment to
Contractors
(cont.) 
Payment to Private Contractors – Cet
Allocation- Home Care – 295k under 
Payment to Private Contractor –Secure
Accommodation – 588k under 
Payment to Private Contractors – 
Respite  – 207k under 
Payment to Private Contractors –
Daycare – 82k under 
Payment to Private Contractors – 
Home Support – (260k) over 
Payment to Private Contractors – 
PA College – (257k) over 
Adult and Older People –
319k under 
Children and Family –
588k under 
Children and Family –
107k under 
Adult and Older People –
100k under 
Adult and Older People –
82k under 
Adult and Older People –
(260k) over 
Adult and Older People –
(257k) over 
part of the overall budget
recovery plan. 
This underspend reflects the
current demand for the external
home care service. 
This underspend reflects the
current demand for Council
funded secure placements which
have reduced in 2025/26. 
This underspend relates to the
demand for residential respite. 
This underspend relates to the
demand for residential respite. 
This underspend relates to the
demand for day opportunities 
This overspend reflects the
current demand for the external
home support service. 
The overspend reflects the
current demand for PA College. 
157

Page 158

Subjective Head Variance Subjective line Service / amount Explanation
Payment to
Contractors
(cont.) 
Payment to Private Contractors – 
Groupwork/Social Support – (193k)
over 
Payment to Private Contractors – 
Community Outreach – 83k under 
Adult and Older People –
(193k) over 
Children and Family –
83k under 
The overspend reflects additional
demand for service. 
This underspend reflects the
demand for community outreach
for children with a disability.  The
same period saw overspends in
homecare, direct payments and
transport requirements which led
to a breakeven overall in local
office community spend for
children with a disability. 
Transfer
Payments 
(440k) over Direct Assistance to Persons – (410k)
over 
Children and Family –
(385k) over 
This overspend is due to budget
pressure continuing into 2025/26,
an increase in demand for kinship
care allowances and an increase
to the net cost to the Council
arising from the migration to
Universal Credit which has
resulted in the loss of child tax
credits from some kinship carers.
Finance Charges 27k under IT Equipment Leasing – 28k under Performance and
support – 78k under
This underspend relates to lower
than anticipated recharges.
158

Page 159

Subjective Head Variance Subjective line Service / amount Explanation
Income  874k over
recovered
Contributions from Other Bodies – 331k
over recovered 
Fees and Charges – General – 201k
over recovered 
Fees and Charges - Other Local
Authorities – 127k over recovered 
Children and Family –
135k over recovered 
Adult and Older People –
198k over recovered 
Children and Family –
85k over recovered 
Adult and Older People –
116kover recovered 
Children and Family –
78k over recovered 
Justice – 80k over 
This over recovery is due to the
level of Unaccompanied Asylum-
Seeking Children (UASC) income
being received for children
seeking asylum. 
Additional income was received
from NHS Lanarkshire in relation
to our participation in the Care
Surround Project. 
This over recovery relates to non-
recurring income received in
respect of recovery of prior year
care costs from service users. 
This over recovery relates to non-
recurring income received in
respect of recovery of prior year
care costs from service users. 
This over recovery is due to a
recharge to other local authorities
for interagency adoption fees. 
This over recovery is due to
gender-based violence services
which is off-set with additional
159

Page 160

* The underlined variances represent new variances since the last report. 
Subjective Head Variance Subjective line Service / amount Explanation 
Other Income – 106k over recovered  Adult and Older People –
105k over recovered 
payments. It also includes
additional recharges to other
local authorities for bail and court
services. 
This over recovery of income
relates to recovery of salary
overpayments and income
received from Stairlift grants for
owner occupiers. 
160

Page 161

South Lanarkshire Council
Revised Period 14 Period 14
Social Work Resource - Total Annual  Actual Variance
Budget to Date Amount
Expenditure / Income Variance Trends 2025/2026 25/26
EMPLOYEE COSTS
APT&C BASIC 6,795 6,126 669
APT&C OVERTIME 0 180 (180)
APT&C SUPERANNUATION 444 416 28
APT&C NIC 711 730 (19)
SOCIAL WORKERS BASIC GRADE BASIC 15,098 13,044 2,054
SOCIAL WORKERS BASIC GRADE OVERTIME 76 93 (17)
SOCIAL WORKERS BASIC GRADE SUPERANNUATION 1,027 849 178
SOCIAL WORKERS BASIC GRADE NIC 1,984 1,781 203
MAN/SPEC/FWORK BASIC 26,606 26,185 421
MAN/SPEC/FWORK OVERTIME 142 532 (390)
MAN/SPEC/FWORK SUPERANNUATION 1,718 1,629 89
MAN/SPEC/FWORK NIC 3,739 3,491 248
CARE STAFF BASIC 17,538 17,103 435
CARE STAFF OVERTIME 500 965 (465)
CARE STAFF SUPERANNUATION 1,125 1,139 (14)
CARE STAFF NIC 2,215 2,288 (73)
INSTRUCTORS - SOCIAL WORK BASIC 1,635 1,561 74
INSTRUCTORS - SOCIAL WORK OVERTIME 0 0 0
INSTRUCTORS - SOCIAL WORK SUPERANNUATION 106 100 6
INSTRUCTORS - SOCIAL WORK NIC 197 192 5
OCCUP. THERAPISTS BASIC 0 0 0
INSTRUCTORS - SOCIAL WORK OVERTIME 0 0 0
OCCUP. THERAPISTS SUPERANNUATION 0 0 0
OCCUP. THERAPISTS NIC 0 0 0
MANUAL WORKERS BASIC 30,199 29,566 633
MANUAL WORKERS OVERTIME 1,370 1,699 (329)
MANUAL WORKERS SUPERANNUATION 1,984 1,826 158
MANUAL WORKERS NIC 3,923 3,943 (20)
TRAVEL AND SUBSISTANCE 397 289 108
OTHER EMPLOYEE COSTS 845 449 396
PENSION INCREASES 328 297 31
STRAIN ON THE FUND 0 12 (12)
APPRENTICESHIP LEVY 477 477 0
EMPLOYEE COSTS 121,179 116,962 4,217
161

Page 162

South Lanarkshire Council
Revised Period 14 Period 14
Social Work Resource - Total Annual  Actual Variance
Budget to Date Amount
Expenditure / Income Variance Trends 2025/2026 25/26
PROPERTY COSTS
RATES 362 460 (98)
SCOTTISH WATER - UNMETERED CHARGES 1 0 1
SCOTTISH WATER - METERED CHARGES 177 205 (28)
RENT 547 599 (52)
PROPERTY INSURANCE 292 295 (3)
SECURITY COSTS 2 (9) 11
GROUND MAINTENANCE 12 12 0
GROUNDS MAINTENANCE ADDITIONAL AKORKS 0 3 (3)
REPAIRS & MAINTENANCE - INTERNAL CONTRACTOR 36 132 (96)
LIFE CYCLE MAINTENANCE 0 1 (1)
REPAIRS & MAINTENANCE - EXTERNAL CONTRACTOR 28 47 (19)
ELECTRICAL HEATING MAINTENANCE 0 5 (5)
ELECTRICITY  - CONTRACT 662 555 107
ELECTRICITY - NON CONTRACT 0 11 (11)
GAS 486 385 101
FIXTURE & FITTINGS 32 47 (15)
CLEANING CONTRACT 388 372 16
CLEANING AND JANITORIAL SUPPLIES AND EQUIPMENT 118 102 16
HEALTH & HYGIENE MATERIALS 86 84 2
AKINDOAK CLEANING 9 9 0
REFUSE UPLIFT 39 41 (2)
REMOVAL & STORAGE COSTS 2 10 (8)
OTHER PROPERTY COSTS 175 103 72
PROPERTY COSTS 3,454 3,469 (15)
162

Page 163

South Lanarkshire Council
Revised Period 14 Period 14
Social Work Resource - Total Annual  Actual Variance
Budget to Date Amount
Expenditure / Income Variance Trends 2025/2026 25/26
SUPPLIES AND SERVICES
COMPUTER EQUIPMENT PURCHASE 930 963 (33)
COMPUTER EQUIPMENT MAINTENANCE 27 10 17
I.T. EQUIPMENT MAINT-CONTRACT 176 231 (55)
I.T. ELECTRONIC MESSAGING 97 150 (53)
EQUIPMENT, APPARATUS AND TOOLS 110 78 32
SMALL TOOLS 4 7 (3)
AIDS FOR CLIENTS 860 725 135
ADAPTATIONS FOR CLIENTS 873 867 6
SUPPLIES FOR CLIENTS 352 245 107
FURNITURE - OFFICE 1 9 (8)
FURNITURE - GENERAL 34 38 (4)
FURNISHINGS (INCL. CROCKERY & LINEN) 19 44 (25)
MATERIALS 10 (3) 13
MATERIALS, APPARATUS AND EQUIPMENT 2 18 (16)
TV LICENCES - EDUCATION 0 3 (3)
PROVISIONS 227 223 4
FOOD PURCHASES WITHIN CONTRACT 446 381 65
BEVERAGES 50 40 10
SCHOOL MILK 34 31 3
PROTECTIVE CLOTHING & UNIFORMS 1,457 1,600 (143)
LAUNDRY COSTS 3 4 (1)
OTHER SUPPLIES AND SERVICES 38 25 13
HEALTH AND SAFETY 0 0 0
CATERING - CONTRACT 367 422 (55)
CATERING - OUTWITH CONTRACT 21 19 2
ARTIST FEES/ PERFORMING ARTS 0 3 (3)
OUTSOURCED MAIL 0 1 (1)
DELIVERY CHARGE 0 2 (2)
SUPPLIES AND SERVICES 6,138 6,136 2
TRANSPORT AND PLANT
FLEET SERVICES - FUEL 0 1 (1)
POOL CAR CHARGES-RENTAL 169 236 (67)
POOL CAR CHARGES-FUEL 15 0 15
POOL CAR CHARGES-ADDITIONAL COSTS 3 2 1
OTHER TRANSPORT COSTS 801 728 73
INSURANCE 24 21 3
FLEET SERVICE CHARGES 3,283 3,417 (134)
HIRE OF EXTERNAL VEHICLES 7 2 5
HIRE OF SKIPS 0 2 (2)
EXTERNAL TRANSPORT CONTRACT 0 5 (5)
PUPIL TRANSPORT-S'CLYDE PASSENGER TRANSPORT 0 3 (3)
PUPIL TRANSPORT - OTHER 10 9 1
TRANSPORT AND PLANT 4,312 4,426 (114)
163

Page 164

South Lanarkshire Council
Revised Period 14 Period 14
Social Work Resource - Total Annual  Actual Variance
Budget to Date Amount
Expenditure / Income Variance Trends 2025/2026 25/26
ADMINISTRATION
PRINTING AND STATIONERY 82 132 (50)
TELEPHONES 200 135 65
MOBILE PHONES 282 326 (44)
ADVERTISING - RECRUITMENT 4 4 0
ADVERTISING - OTHER 10 2 8
POSTAGES/COURIERS 54 53 1
SMS MESSAGING 2 0 2
MEMBERSHIP FEES/SUBSCRIPTIONS 74 73 1
INSURANCE 27 27 0
MEDICAL COSTS 34 68 (34)
LEGAL EXPENSES 542 625 (83)
PETTY OUTLAYS 0 1 (1)
HOSPITALITY / CIVIC RECOGNITION 2 3 (1)
PAYPOINT AGENCY FEES 0 3 (3)
OTHER ADMIN COSTS 15 6 9
CONFERENCES - OFFICIALS (incl associated costs) 15 5 10
TRAINING 59 21 38
INTERNAL SUPPORT SERVICES ALLOWANCES 410 409 1
ADMINISTRATION 1,812 1,893 (81)
PAYMENT TO OTHER BODIES
OTHER COMMITTEES OF THE AUTHORITY 75 88 (13)
OTHER LOCAL AUTHORITIES 25 25 0
GRANTS TO VOLUNTARY ORGANISATIONS 23 23 0
PAYMENTS TO VOLUNTARY ORGANISATIONS 1,817 1,794 23
PAYMENTS TO OTHER BODIES 1,509 1,217 292
PAYMENTS TO HEALTH BOARD 1,471 1,524 (53)
PRIVATE INDIVIDUALS - GENERAL 775 568 207
SOCIAL WORK - FOSTER PARENTS 6,570 6,930 (360)
SOCIAL WORK - FOSTER PARENTS 94 79 15
SOCIAL WORK - ADOPTION ALLOWANCES 650 1,020 (370)
DIRECT PAYMENTS 11,261 11,297 (36)
PAYMENT TO OTHER BODIES 24,270 24,565 (295)
PAYMENT TO CONTRACTORS
PAYMENT TO TRADING SERVICES 0 1 (1)
PAYMENT TO LOCAL AUTHORITY CON \ 0000-DEFAULT 0 66 (66)
PAYMENT TO PRIVATE CONTRACTOR 156,045 154,764 1,281
PAYMENT TO EXTERNAL CONSULTANTS / PROFESSIONAL SERVICES 139 136 3
PAYMENT TO CONTRACTORS 156,184 154,967 1,217
TRANSFER PAYMENTS
DIRECT ASSISTANCE TO PERSONS 4,345 4,755 (410)
SECTION PAYMENTS 30 60 (30)
TRANSFER PAYMENTS 4,375 4,815 (440)
164

Page 165

South Lanarkshire Council
Revised Period 14 Period 14
Social Work Resource - Total Annual  Actual Variance
Budget to Date Amount
Expenditure / Income Variance Trends 2025/2026 25/26
FINANCING CHARGES
LEASING CHARGES - OPERATIONAL (1) 0 (1)
I.T. EQUIPMENT LEASING - CONTRACT 398 370 28
FINANCING CHARGES 397 370 27
TOTAL EXPENDITURE 322,121 317,603 4,518
INCOME
NON RELEVANT GOVERNMENT GRANT (8,810) (8,842) 32
DWP SUBSIDY 0 (14) 14
RESOURCE TRANSFER INCOME FROM (25,786) (25,785) (1)
CONTRIBUTIONS FROM OTHER BODIES (828) (1,159) 331
SALES - SALE OF MEALS (29) (54) 25
FEES AND CHARGES - GENERAL (6,704) (6,905) 201
FEES AND CHARGES - OTHER LOCAL AUTHORITIES (443) (570) 127
CHARGES TO HEALTH BOARDS (26,279) (26,307) 28
FEES AND CHARGES - DEPARTMENTS (218) (212) (6)
RENTAL INCOME (45) (52) 7
OTHER INCOME (135) (241) 106
ACCOMMODATION INCOME FROM USERS (400) (410) 10
INCOME (69,677) (70,551) 874
NET EXPENDITURE 252,444 247,052 5,392
165

Page 166

166

Page 167

Report
Agenda Item 
Report to: Financial Resources Scrutiny Forum
Date of Meeting: 27 August 2026
Report by: Executive Director (Finance and Corporate Resources)  
Subject: Revenue Budget Monitoring 2026/2027 
1. Purpose of Report
1.1. The purpose of the report is to:
[purpose]
 advise the Forum of the forecast for the year to 31 March 2026 for the Council’s
General Fund Revenue Account and Housing Revenue Account, and the actual
spend position for the period 1 April 2026 to 10 July 2026. 
[1purpose]
2. Recommendation(s)
2.1. The Forum is asked to approve the following recommendation(s):
[recs]
(1) that the projected break-even position on the General Fund Revenue Account
for 2026/2027 (section 4.1) after budgeted Transfers to Reserves and
previously reported underspends, and the actual spend as at 10 July 2026
(Appendix 1), be noted;
(2) that the proposed Transfers to Reserves (sections 4.3 to 4.5), be noted; and
(3) that the projected break-even position on the Housing Revenue Account for
2026/2027, and the actual spend as at 10 July 2026 (section 5 and Appendix
2), be noted. 
3. Background
3.1. This overview report will summarise the projected outturn for 2026/2027 for both the
Council’s General Fund (section 4) and for the Housing Revenue Account (section 5). 
It will also provide the actual spend as at 10 July 2026. 
4. General Services 2026/2027 Projected Outturn as at 10 July 2026
4.1. As at 10 July 2026, the projected outturn position for 2026/2027 on the General
Services budget is break-even after budgeted Transfers to Reserves and previously
reported underspends (Appendix 1).  The actual spend to date is shown in Appendix
1. 
4.2. Committed Funding:  Following the Budget being set on 25 February 2026, it is
appropriate to update Members on the impact on the 2026/2027 Revenue Budget.    
4.3. £31.959 million of the committed investment monies is funded by one-off Revenue
Budget in 2026/2027.  Officers have considered the budget profiling and it is
anticipated that £12.130 million will be spent in 2026/2027, meaning that one-off
funding of £19.829 million has been moved to the budget line 2026/2027 Investments
– Transfers to Reserves to complete the committed works into future years.    
9
167

Page 168

4.4. In addition, as part of the 2026/2027 Budget setting process, the Council agreed to a
further extension to the Loans Fund Review.  An underspend of £6.017 million was
anticipated in the Loans Fund Budget in 2026/2027.  £6.017 million has, therefore,
been moved to the budget line Loan Charges – Transfers to Reserves and will be set
aside and used to reduce the Budget Gap in 2027/2028 as planned.   
4.5. Similarly, in line with borrowing for service concession arrangements, as approved at
Council (January 2023), £0.826 million is required to be transferred to reserves to be
utilised from 2027/2028.  £0.826 million has therefore also been moved to the Loan
Charges – Transfers to Reserves budget line as planned. 
4.6. This funding of £26.672 million (sections 4.2 to 4.5) is committed for approved
investment and future costs, and has been moved to the Transfers to Reserves budget
lines in Appendix 1. 
4.7. Transfers from Capital:  The Budget in Appendix 1 includes a £5.300 million transfer
from the Capital Programme for the Private Housing Scheme of Assistance (£1.000
million) and Planned Maintenance (£4.300 million) programmes.  Following a review
of the spend, it has been identified that it cannot be classed as Capital.  Therefore, it
is proposed that budget of £5.300 million will be transferred to Housing and Technical
Resource’s Revenue budget.  This is an accounting transaction only. The total overall
budget for the projects remains the same. 
4.8. Across the Council’s Budget, there are 3 notable areas where underspends are
anticipated this financial year.  These are taken in turn. 
4.9. Loan Charges Underspend:  An underspend is anticipated in 2026/2027 due to the
capital profile meaning a reduced requirement to borrow for investment monies this
financial year (£3.596 million), and that anticipated deposit interest and interest on
revenue balances is expected to be higher than budgeted (£2.500 million).   
4.10. Non-Domestic Rates Underspend:  Following the national Rates Revaluation
exercise and the rates poundage figure set as part of the 2026/2027 Settlement, an
underspend of £2.700 million is anticipated in 2026/2027.  This will be a one-off benefit
in 2026/2027 and a permanent benefit to the Budget Strategy from 2027/2028
(included in the Budget Strategy paper to Executive Committee).   
4.11. Empty Property Relief Underspend:  A recurring underspend of £1.000 million is
anticipated due to a reduction in the number of empty properties being supported and
will mean a permanent benefit to the Budget Strategy from 2027/2028 (noted in the
Budget Strategy report to Executive Committee).   
4.12. We are still very early in the financial year.  The budget for each of these areas has
been moved to a separate budget line in Appendix 1 and will be considered later in
the financial year as part of the Probable Outturn position. 
5. Updates on Budget Areas
5.1. Packaging Extended Producer Responsibility (pEPR) and Teacher Numbers /
Reduction in Class Contact Time (RCCT) 2026/2027:  The 2026/2027 Revenue
Budget paper to Council in February 2026 identified £7.865 million of core Council
budget released from pEPR monies and £4.200 million of core Council budget for
potential costs of RCCT in future years available as one-off benefits in 2026/2027. 
Both budgets have already been utilised within the Council’s budget for 2026/2027
and are part of the funding for the approved £33.3 million of one-off investments.
168

Page 169

5.2. Social Work Resources – Children and Families:  The forecasts for Children and
Families, Justice and Performance and Support Services continue to show a
breakeven position.  As reported through Social Work Committee, budget pressures
within Children and Families are continuing into 2026/2027 in relation to statutory
duties of continuing care and increased costs and requirements for residential
placements, fostering and kinship care.  The Social Work Resources position assumes
that Children and Families’ reserves funding will be utilised later in the financial year,
to support a break-even position in 2026/2027. 
5.3. Social Work Resources – Adults and Older People:  As we move through the
financial year, the forecast outturn will continue to be refined, taking into account the
ongoing recruitment across the Service and management decisions. Any transfers to
reserves will be confirmed as part of the Probable Outturn exercise. 
5.4. Inflation and Price Assumptions: The Council’s budget for 2026/2027 includes the
provision of budget for assumed inflationary increases for the Council’s main contracts
including schools’ modernisation contract (Public Private Partnership (PPP)), school
transport (Strathclyde Partnership for Transport (SPT) and Additional Support Needs
(ASN) taxis), social care for Children and Families and waste. It also includes provision
for assumed price impacts of utilities and fuel. 
5.5. Inflation reduced to below 3% in May 2026, however it is anticipated to increase again
during 2026/2027 due to increased utilities prices from June 2026 as a result of the
current conflict in Iran.  The schools’ modernisation contract increase is based on
inflation at the start of the calendar year and has been accounted for.  The costs for
the other main contracts will continue to be monitored throughout the financial year as
more information becomes available. 
5.6. In relation to utilities, the Council is a member of the buying consortium who purchase
wholesale energy in advance, on behalf of ourselves and other public sector bodies.
All of the Council’s required units are purchased for 2026/2027 at a lower price than
2025/2026. However, this does not cover non-energy charges including standing
charges etc. with only a minor net saving assumed in 2026/2027. This will continue to
be monitored throughout the financial year as more information becomes available. 
5.7. Fuel prices have seen an increase of approximately 30% from February to May as a
result of the current conflict in Iran. Prices and any budgetary impact will continue to
be monitored throughout the financial year. 
5.8. An increased inflationary budget requirement for these areas has been assumed in
the Council’s Budget Strategy for 2027/2028 to 2028/2029. However, for 2026/2027,
it is proposed that they continue to be monitored. 
6. Housing Revenue Account Position
6.1. As at 10 July 2026, Appendix 2 of the report shows a break-even position on the
Housing Revenue Account. 
7. Employee Implications
7.1. None. 
8. Financial Implications
8.1. As detailed in sections 4 to 5 of the report. 
169

Page 170

9. Climate Change, Sustainability and Environmental Implications
9.1. There are no implications for climate change, sustainability or the environment in terms
of the information contained in this report. 
10. Risk and Other Implications
10.1. The main risk associated with the Council’s Revenue Budget is that there is an
overspend.  The risk has been assessed as low given the detailed budget
management applied across the Resources.  The risk is managed through four weekly
Budget Monitoring Meetings at which any variance is analysed. In addition, the
probable outturn exercise ensures early warning for corrective action to be taken
where appropriate. 
10.2. There are no implications for sustainability in terms of the information contained in this
report. 
11. Integrated Impact Assessment and Consultation Requirements
11.1. This report does not introduce a new policy, function or strategy or recommend a
change to an existing policy, function or strategy and therefore no impact assessment
is required.   
11.2. There is also no requirement to undertake any consultation in terms of the information
contained in this report. 
Jackie Taylor
Executive Director (Finance and Corporate Resources) 
10 August 2026 
Link(s) to Council Values/Ambitions/Objectives
▪ Accountable, Effective, Efficient and Transparent 
Previous References
 None 
List of Background Papers
 Financial Ledger and budget monitoring results to 10 July 2026 
Contact for Further Information
If you would like to inspect the background papers or want further information, please contact:
Lorraine O'Hagan, Head of Finance (Strategy)
Ext:  5637 (Tel:  01698 455637)
E-mail: lorraine.o'hagan@southlanarkshire.gov.uk
170

Page 171

Note:  While the Year to Date Actual at period 4 presents a net surplus position (£69.501m), this is timing only.  The forecast outturn
shows a breakeven position (section 4.1).
Appendix 1
Revised Projected Projected % Note Year to Date
Annual Outturn Outturn Actual
Budget Variance
Resources: £m £m £m £m
Community and Enterprise Resources 138.980 138.980 0.000 0.00% 30.966
Facilities Waste and Grounds 84.744 85.355 (0.611) (0.72%) 18.544
Leisure and Culture 19.658 19.658 0.000 0.00% 4.071
Planning and Regulatory Services 5.925 5.397 0.528 8.91% 0.966
Enterprise and Sustainable Development 6.940 6.775 0.165 2.38% (0.376)
Roads, Transportation and Fleet 21.713 21.795 (0.082) (0.38%) 7.761
Education Resources 525.944 525.944 0.000 0.00% 128.077
Education 525.944 525.944 0.000 0.00% 128.077
Finance and Corporate Resources 49.367 49.367 0.000 0.00% 19.763
Finance Services - Strategy 2.834 2.776 0.058 2.05% 1.089
Finance Services - Transactions 20.285 20.263 0.022 0.11% 6.490
Audit and Compliance Services 0.417 0.433 (0.016) (3.84%) 0.141
Information Technology Services 9.160 9.255 (0.095) (1.04%) 6.683
Communications and Strategy Services 3.673 3.555 0.118 3.21% 1.431
Administration and Licensing Services 5.258 5.258 0.000 0.00% 1.576
Personnel Services 7.740 7.827 (0.087) (1.12%) 2.353
Housing & Technical Resources 19.005 19.005 0.000 0.00% 4.985
Housing Services 8.954 8.936 0.018 0.20% 1.200
Property Services 10.051 10.069 (0.018) (0.18%) 3.785
Social Work Resources 270.829 270.829 0.000 0.00% 69.101
Performance and Support Services 6.756 6.497 0.259 3.83% 1.767
Children and Families 49.929 50.727 (0.798) (1.60%) 11.676
Adults and Older People 212.592 212.592 0.000 0.00% 54.945
Justice and Substance Misuse 1.552 1.013 0.539 34.73% 0.713
Joint Boards 2.072 2.072 0.000 0.00% 0.638
1,006.197 1,006.197 0.000 0.00% 253.530
Revised Projected Projected Year to Date
Annual Outturn Outturn Actual
Budget Variance
Summary: £m £m £m £m
Resources Total 1,006.197 1,006.197 0.000 0.00% 253.530
CFCR 5.401 5.401 0.000 0.00% 0.000
Loan Charges 35.755 35.755 0.000 0.00% 0.000
Corporate Items (5.593) (5.593) 0.000 0.00% 0.138
2026/2027 Investments - T/f to Reserves 19.829 19.829 0.000 0.00% 0.000
Loan Charges - T/f to Reserves 6.843 6.843 0.000 0.00% 0.000
Loan Charges - Underspend 6.096 6.096 0.000 0.00% 0.000
Non-Domestic Rates - Underspend 2.700 2.700 0.000 0.00% 0.000
Empty Property Relief - Underspend 1.000 1.000 0.000 0.00% 0.000
Total Expenditure 1,078.228 1,078.228 0.000 0.00% 253.668
Council Tax 210.719 210.719 0.000 0.00% 64.837
Less: Council Tax Reduction Scheme (26.228) (26.228) 0.000 0.00% (8.070)
184.491 184.491 0.000 0.00% 56.767
General Revenue Grant 438.388 438.388 0.000 0.00% 134.889
Non Domestic Rates 427.417 427.417 0.000 0.00% 131.513
Transfer from Reserves 27.932 27.932 0.000 0.00% 0.000
Total Income 1,078.228 1,078.228 0.000 0.00% 323.169
Net Expenditure 0.000 0.000 0.000 0.00% (69.501)
Period Ended 10 July 2026 (No.4)
Revenue Budget Monitoring Report
SOUTH LANARKSHIRE COUNCIL
171

Page 172

Note:  While the Year to Date Actual at period 4 presents a net deficit position (£13.495m), this is timing only.  The forecast outturn shows
a breakeven position (section 5.1). 
Appendix 2
Revised Projected Projected Year to Date
Annual Outturn Outturn % Note Actual
Budget Variance
Budget Category £m £m £m £m
Employee Costs 17.393 17.377 0.016 0.09% 4.396
Property Costs 62.761 62.761 0.000 0.00% 16.767
Supplies and Services 0.523 0.523 0.000 0.00% 0.098
Transport and Plant 0.195 0.195 0.000 0.00% 0.091
Administration 5.604 5.620 (0.016) (0.29%) 0.483
Payment to Other Bodies 2.682 2.682 0.000 0.00% 0.006
Payment to Contractors 0.806 0.806 0.000 0.00% 0.722
Transfer Payments 0.000 0.000 0.000 0.00% 0.000
Financing Charges 33.918 33.918 0.000 0.00% 3.495
Total Controllable Exp. 123.882 123.882 0.000 0.00% 26.058
Total Controllable Inc. (141.769) (141.769) 0.000 0.00% (39.553)
Transfer to/(from) Balance Sheet (3.498) (3.498) 0.000 0.00% 0.000
Net Controllable Exp. (21.385) (21.385) 0.000 0.00% (13.495)
Loan Charges 21.385 21.385 0.000 0.00% 0.000
Net Controllable Exp. 0.000 0.000 0.000 0.00% (13.495)
SOUTH LANARKSHIRE COUNCIL
Revenue Budget Monitoring Report
Period Ended 10 July 2026 (No.4)
Housing Revenue Account
172

Page 173

Report
Agenda Item 
Report to: Financial Resources Scrutiny Forum
Date of Meeting: 27 August 2026
Report by: Executive Director (Finance and Corporate Resources)  
Subject: Revenue Budget 2026/2027 - Detailed Resource
Analysis 
1. Purpose of Report
1.1. The purpose of the report is to:
[purpose]
 update members of the Financial Resources Scrutiny Forum on the Council’s
revenue budget for 2026/2027.
[1purpose]
2. Recommendation(s)
2.1. The Forum is asked to approve the following recommendation(s):
[recs]
(1) that the 2026/2027 detailed financial analysis for each of the individual
Resources and the Housing Revenue Account, be noted. 
[1recs]
3. Background
3.1. The individual reports attached provide detailed information on each of the Resource
Revenue Budgets for the period to 10 July 2026.  The detailed papers cover the
General Services and also the Housing Revenue Account. 
3.2. The following information is provided for each Resource and the Housing Revenue
Account:- 
 an Executive Summary showing the top-level position.
 details of the most significant variances across Subjective headings and across
services.
 a line-by-line trend analysis of the total Resource expenditure and income
across Subjective headings. 
3.3. These are shown in Appendices A to F attached. 
4. Employee Implications
4.1. None 
5. Financial Implications
5.1. As detailed in each of the individual Resource papers. 
6. Climate Change, Sustainability and Environmental Implications
6.1. There are no implications for climate change, sustainability, or the environment in
terms of the information contained in this report.   
10
173

Page 174

7. Risk and Other Implications
7.1. The main risk associated with the Council’s Revenue Budget is that there is an
overspend.  The risk has been assessed as low given the detailed budget
management applied across the Resources.   The risk is managed through four
weekly Budget Monitoring Meetings at which any variance is analysed.  In addition,
the probable outturn exercise ensures early warning for corrective action to be taken
where appropriate. 
8. Integrated Impact Assessment and Consultation Requirements
8.1. This report does not introduce a new policy, function or strategy or recommend a
change to an existing policy, function, or strategy and therefore no impact
assessment is required.   
8.2. There is also no requirement to undertake any consultation in terms of the
information contained in this report. 
Jackie Taylor
Executive Director (Finance and Corporate Resources) 
10 August 2026 
Link(s) to Council Values/Priorities/Outcomes
 Accountable, Effective, Efficient and Transparent 
Previous References
 None 
List of Background Papers
 Revenue Ledger prints to 10 July 2026 
Contact for Further Information
If you would like to inspect the background papers or want further information, please
contact:
Lorraine O'Hagan, Head of Finance (Strategy)
Ext:  5637 (Tel:  01698 455637)
E-mail: lorraine.o'hagan@southlanarkshire.gov.uk 
174

Page 175

Appendix A
South Lanarkshire Council
Revenue Budget Monitoring Statement
Period Ended 10 July 2026 (No.4)
Community and Enterprise Resources
Committee
Revised
Annual Projected
Projected
Outturn % Note
Year to
Date
Budget Outturn Variance Actual
Service Departments :- £m £m £m £m
Facilities, Waste and Grounds 84.744 85.355 (0.611) (0.72%) 18.544
Leisure and Culture 19.658 19.658 0.000 0.00% 4.071
Planning and Regulatory Services 5.925 5.397 0.528 8.91% 0.966
Environmental and Sustainable Devlopment 6.940 6.775 0.165 2.38% (0.376)
Roads, Transportation and Fleet 21.713 21.795 (0.082) (0.38%) 7.761
Total Community and Enterprise Resources 138.980 138.980 (0.000) (0.00%) 30.966
10
175

Page 176

Community and Enterprise Resources Variance Analysis 2026/27 (Period 4) 
Subjective Head Variance  Subjective line Service / amount Explanation
Employee Costs 3,131k
under
APT&C Basic/ Superannuation/
National Insurance – 3,714k under 
Facilities, Waste and
Grounds Services –
2,529k under
The variances are mainly due to
vacant posts, with recruitment
currently being progressed.    
Planning and
Regulatory Services -
247k under 
Enterprise &
Sustainable
Development – 178k
under 
Roads, Transportation
and Fleet Services -
952k under 
Overtime - (616k) over Facilities, Waste and
Grounds Services -
(750k) over
The projected overtime
overspend within Facilities,
Waste, Streets and Grounds is
mainly down to the covering of
vacant posts within the
services. 
Roads, Transportation
and Fleet Services -
126k under 
The under spend within Roads
is due to less overtime
anticipated to meet the winter
service, this is partially offset by
a predicted overspend within
Fleet, mainly due to mechanics
and driver’s overtime.  
176

Page 177

Subjective Head Variance  Subjective line Service / amount Explanation
Employee Costs
(cont.) 
Pension Increases – (110k) over Planning and
Regulatory Services –
(80k) over 
The overspend relates to the
ongoing cost of early retirals
within PBS. 
Enterprise &
Sustainable
Development – (£16k)
over 
The overspend relates to the
ongoing cost of early retirals
within Support.   
Roads, Transportation
and Fleet Services –
(14k) over 
The overspend relates to the
ongoing cost of early retirals
within Roads.
Property Costs (342k) over Factoring Charges - (31k) over Roads, Transportation
and Fleet Services -
(31k) over 
The overspend within Fleet is
due to an increase in the
quarterly factoring charges for
Hamilton Boulevard. 
Security Costs – (15k) over Roads, Transportation
and Fleet Services –
(19k) over 
The projected overspend
relates to greater security costs
within Fleet.  
Grounds Maintenance/ Repairs and
Maintenance/ Life Cycle Maintenance
– (65k) over
Facilities, Waste and
Grounds Services -
(40k) over 
The projected overspend
relates to general maintenance
costs throughout the services.  
Cleaning & Janitorial Supplies and
Equipment - (89k) over
Facilities, Waste and
Grounds Services -
(79k) over
The projected overspend
relates to an increase in costs
for cleaning materials within
Facilities Management.
177

Page 178

Subjective Head Variance  Subjective line Service / amount Explanation
Property Costs
(cont.) 
Health & Hygiene Materials – (60k)
over
Facilities, Waste and
Grounds Services -
(60k) over 
The projected overspend is
within Facilities relates to the
purchase of healthy & hygiene
materials 
Refuse Uplift – (101k) over Facilities, Waste and
Grounds Services -
(116k) over 
The projected overspend is
within Waste and relates to the
refuse uplift costs being greater.
Supplies and
Services
(720k) over Computer Equipment Purchase -
(65k) over
Enterprise &
Sustainable
Development – 21k
under 
The projected under spend is
within Support and is due to
computer equipment
purchases.   
Roads, Transportation
and Fleet Services -
(86k) over
This projected overspend
mainly relates to increased
costs for annual subscriptions
for Computer Licenses within
Roads. 
IT Equipment Maintenance – (28k)
over
Facilities, Waste and
Grounds Services -
(28k) over
The predicted over spend is
within Facilities and is due to
costs for the cashless being
greater than budget. 
Small Tools – 24k under Roads, Transportation
and Fleet Services -
24k under
The predicted under spend is
within Roads and is due to the
purchase of tools being less
than budgeted 
178

Page 179

Subjective Head Variance  Subjective line Service / amount Explanation
Supplies and
Services (cont). 
Materials/Stock – (330k) over Facilities, Waste and
Grounds Services -
(144k) over
Grounds is predicted to have an
overspend on materials against
budget.   
Roads, Transportation
and Fleet Services -
(186k) over
The overspend within Roads
relates to greater spend on
materials due to increased
levels of work on roads
maintenance. 
Food Purchases - (150k) over  Facilities, Waste and
Grounds Services -
(150k) over 
The projected overspend
relates to an increase in costs
for food within Facilities
Management.  
Protective Clothing – (70k) over Facilities, Waste and
Grounds Services -
(70k) over 
The overspend is within
Grounds and is for PPE
required within the Service.  
Major Supply of Electrical Power –
(90k) over 
Roads, Transportation
and Fleet Services -
(90k) over
The overspend within Roads is
due to increased spend on
electrical costs 
Transport & Plant (1,216k)
over
Fleet Services - Drivers - (42k) over Roads, Transportation
and Fleet - (42k) over
The forecast overspend is due
to an increased charge from
Fleet to cover Road's PSA
service. 
179

Page 180

Subjective Head Variance  Subjective line Service / amount Explanation
Transport & Plant
(cont.) 
Fleet Services - Fuel - (42k) over  Roads, Transportation
and Fleet - (38k) over 
The overspend predicted is
within Fleet and is for the costs
relating to oils and lubs. 
Pool Car Charges – Rental/ Fuel - 24k
under
Planning and
Regulatory Services –
24k under 
The forecast underspend is
mainly due to demand for the
use of pool cars being less than
budget within Planning.   
Fleet Services Repairs - Outside
Repairs - (87k) over 
Roads, Transportation
and Fleet - (87k) over 
The projected overspend is
mainly due to higher than
anticipated expenditure on
outside repairs within Fleet
Services. This is partially offset
by income for rechargeable
works. 
Fleet Services Repairs - Tyres - (40k)
over
Roads, Transportation
and Fleet - (40k) over
The projected overspend is due
to higher than budgeted costs
for tyres. 
Vehicle Maintenance - (473k) over Facilities, Waste and
Grounds Services -
(356k) over 
Roads, Transportation
and Fleet - (118k) over
The projected overspend is due
to higher than budgeted
charges for routine
maintenance within Facilities,
Grounds and Waste. 
The projected overspend is due
to higher than budgeted
charges for routine
maintenance within Roads. 
180

Page 181

Subjective Head Variance  Subjective line Service / amount Explanation
Transport & Plant
(cont.) 
Fleet Service Charges – Plant
Maintenance – (35k) over
Facilities, Waste and
Grounds Services -
(43k) over 
The projected overspend is due
to higher than budgeted costs
for plant maintenance within
Grounds. 
Fleet Service Charges - Leasing –
306k under
Facilities, Waste and
Grounds Services –
266k under
The forecast reflects reduced
spending on vehicle leasing
within Grounds, Waste and
Streets, primarily due to the
majority of leasing charges
incurred in the previous
financial year. 
Roads, Transportation
and Fleet – 34k under
The forecast reflects reduced
spending on vehicle leasing
within Roads, primarily due to
the majority of leasing charges
incurred in the previous
financial year. 
Fleet Service Charges - Hired
Vehicles – (485k) over
Facilities, Waste and
Grounds Services –
(557k) over 
The projected overspend is
mainly due to an increased
demand for hires within Waste
and Streets for carrying out
street works and refuse
collection. 
Roads, Transportation
and Fleet – 46k under 
The projected underspend is
mainly due to the lower level of
demand for hires for carrying
out road and lighting works. 
181

Page 182

Subjective Head Variance  Subjective line Service / amount Explanation
Transport & Plant
(cont.) 
Fleet Service Charges – Road Fund
Licence (RFL) – 55k under
Facilities, Waste and
Grounds Services –
36k under 
The underspend is mainly due
to the cost of RFL’s for heavy
goods vehicles within Waste
and Streets being reduced as
part of a Road Tax funding
programme.  The reduction is
for one year only. 
Roads, Transportation
and Fleet – 19k under
The underspend is mainly due
to the cost of RFL’s for heavy
goods vehicles within Roads
being reduced as part of a
Road Tax funding programme. 
The reduction is for one year
only. 
Fleet Service Charges - Fuel – (371k)
over
Facilities, Waste and
Grounds Services –
(477k) over 
Roads, Transportation
and Fleet – 106k under
The overspend is within
Grounds and Waste and is due
to a price increase on the cost
of fuel. 
The projected underspend is
within Roads and is due to fuel
costs being less than budget. 
Administration  (130k) over Printing & Stationery – (36k) over Facilities, Waste and
Grounds Services -
(51k) over 
The overspend is within
Facilities and Waste and relates
to menu development costs and
label printing for bins. 
182

Page 183

Subjective Head Variance  Subjective line Service / amount Explanation
Administration
(cont.) 
Postages – (14k) over Roads, Transportation
and Fleet - (14k) over 
The forecast anticipates a
greater demand on postal
services for notification of works
to residents. 
Membership Fees/Subscriptions –
(13k) over 
Facilities, Waste and
Grounds Services -
(15k) over 
The overspend is within
Grounds and relates to costs for
standpipe licennces.  
Medical Costs – (36k) over Facilities, Waste and
Grounds Services -
(34k) over 
The overspend anticipates a
higher level of medical referrals
due to staff absence levels
within Facilities and Waste. 
Internet Agency Fees – (20k) over Facilities, Waste and
Grounds Services -
(20k) over 
The overspend within Facilities
is in relation to payments made
for the Parent Pay system. 
Payment to Other
Bodies
(38k) over Payment to Other Local Authorities –
(37k) over
Planning and
Regulatory Services -
(37k) over 
The forecast overspend is
within Environmental and is due
to increased contract costs for
scientific services. 
183

Page 184

Subjective Head Variance  Subjective line Service / amount Explanation
Payment to
Contractors
(523k) over Payment to Contractors - (522k) over Planning and
Regulatory Services -
(87k) over 
The forecast overspend is
within Environmental and is due
to increased demand for pest
control and increased contract
costs for clinical waste/dog
warden services. The increased
costs for pest control are offset
by increased income. 
Roads, Transportation
and Fleet - (435k) over 
The forecast overspend is
mainly due to increased sub-
contractor cost anticipated
within Roads Construction Unit
to manage overall workload. 
Financing Charges (49k) over IT Equipment Leasing – (49k) over Planning and
Regulatory Services -
(8k) over 
Enterprise &
Sustainable
Development – (24k)
over 
Roads, Transportation
and Fleet - (17k) over 
The overspend is mainly due to
greater than anticipated IT
equipment leasing costs within
PBS. 
The overspend is mainly due to
greater than anticipated IT
equipment leasing costs within
Support. 
The overspend is mainly due to
greater than anticipated IT
equipment leasing costs within
Roads. 
184

Page 185

Subjective Head Variance  Subjective line Service / amount Explanation
Income (113k)
under
recovered
Sales – General – (156k) under
recovered
Facilities, Waste and
Grounds Services -
(156k) under recovered 
The projected under recovery is
mainly due to school meal
income being less than budget,
this is a result of the increase in
free school meals. 
Fees and Charges - General - (279k)
under recovered
Facilities, Waste and
Grounds Services -
(511k) under recovered 
Planning and
Regulatory Services -
432k over 
The projected under recovery is
mainly due to a reduction in
demand for burial services
within Bereavement and lower
than anticipated garden waste
permit purchases within Waste
and lower.   
The projected over recovery is
due to increased fees for
planning applications and
building warrants along with
additional income from pest
control. 
Roads, Transportation
and Fleet - (200k)
under recovered
The projected under recovery is
within Roads and is due to
lower than anticipated income
from vehicle Electrical power
recharging. 
185

Page 186

Subjective Head Variance  Subjective line Service / amount Explanation
Income (cont.)  Fleet Services – 60k over recovered Roads, Transportation
and Fleet – 60k over
recovered
The over recovery is within
Fleet and mainly relates to
income received for Fleet
Services, this partially offsets
overspends within Transport &
Plant.   
Other Income – 239k over recovered  Facilities, Waste and
Grounds Services –
220k over recovered 
The predicted over recovery is
within Grounds and relates to
internal service requests being
higher than budget. 
* The underlined variances represent new variances since the last report
186

Page 187

South Lanarkshire Council
Revised Period 4 Period 4 Period 4
Community & Enterprise Resources Summary Annual  Actual Forecast Forecast
Budget to Date (Projected Variance
Expenditure / Income Variance Trends 2026/2027 26/27 Outturn)
EMPLOYEE COSTS
TEACHERS BASIC 0 0 14 (14)
TEACHERS NIC 0 0 2 (2)
APT & C BASIC 92,832 21,523 90,118 2,714
APT & C OVERTIME 1,265 503 1,878 (613)
APT & C SUPERANNUATION 13,724 3,414 13,148 576
APT & C NIC 10,368 2,592 9,944 424
MANUAL WORKERS  BASIC 0 7 1 (1)
MANUAL SESSIONAL STAFF BASIC 1,949 635 1,842 107
MANUAL SESSIONAL STAFF OVERTIME 0 5 3 (3)
MANUAL SESSIONAL STAFF SUPERANNUATION 277 82 259 18
MANUAL SESSIONAL STAFF NIC 164 69 151 13
TRAVEL AND SUBSISTENCE 99 14 80 19
OTHER EMPLOYEE COSTS 47 0 44 3
PENSION INCREASES 1,114 294 1,224 (110)
COST LABOUR ALLOCATION (64) (65) (64) 0
EMPLOYEE COSTS 121,775 29,073 118,644 3,131
PROPERTY COSTS
RATES 1,101 0 1,100 1
SCOTTISH WATER - UNMETERED CHARGES 25 0 25 0
SCOTTISH WATER - METERED CHARGES 157 48 157 0
RENT 196 28 212 (16)
SERVICE CHARGE 42 13 42 0
FACTORING CHARGES 16 19 47 (31)
PROPERTY INSURANCE 288 0 288 0
SECURITY COSTS 44 (10) 59 (15)
GROUND MAINTENANCE 8 5 23 (15)
GROUNDS MAINTENANCE ADDITIONAL WORKS 0 6 6 (6)
REPAIRS & MAINTENANCE - INTERNAL CONTRACTORS 11 16 32 (21)
LIFE CYCLE MAINTENANCE 0 (3) 8 (8)
REPAIRS & MAINTENANCE - EXTERNAL CONTRACTORS 34 12 49 (15)
ASBESTOS 0 1 0 0
ELECTRICITY - CONTRACT 3,798 94 3,798 0
GAS 1,596 295 1,578 18
HEATING OIL 14 0 14 0
FIXTURE & FITTINGS 0 1 1 (1)
CLEANING CONTRACT 20 21 20 0
CLEANING AND JANITORIAL SUPPLIES AND EQUIPMENT 585 143 674 (89)
HEALTH & HYGIENE MATERIALS 43 36 103 (60)
REFUSE UPLIFT 404 85 505 (101)
REMOVAL & STORAGE COSTS 1 1 1 0
OTHER PROPERTY COSTS 26 (2) 9 17
OFFICE ACCOMODATION FACILITIES 4 4 4 0
PROPERTY COSTS 8,413 813 8,755 (342)
187

Page 188

South Lanarkshire Council
Revised Period 4 Period 4 Period 4
Community & Enterprise Resources Summary Annual  Actual Forecast Forecast
Budget to Date (Projected Variance
Expenditure / Income Variance Trends 2026/2027 26/27 Outturn)
SUPPLIES AND SERVICES
COMPUTER EQUIPMENT PURCHASE 731 298 796 (65)
COMPUTER EQUIPMENT MAINTENANCE 45 1 46 (1)
I.T. EQUIPMENT MAINT-CONTRACT 191 72 219 (28)
I.T. ELECTRONIC MESSAGING 3 0 3 0
EQUIPMENT, APPARATUS AND TOOLS 1,252 367 1,252 0
SMALL TOOLS 107 0 83 24
ADAPTATIONS FOR CLIENTS 1 1 2 (1)
FURNITURE - OFFICE 5 0 5 0
FURNISHINGS (INCL. CROCKERY & LINEN) 110 2 110 0
MATERIALS 7,488 1,484 5,970 1,518
STOCK/STORE ISSUES 0 308 1,848 (1,848)
MATERIALS, APPARATUS AND EQUIPMENT 15 2 17 (2)
AUDIO VISUAL 0 1 1 (1)
PUBLICATIONS, JOURNALS, NEWSPAPERS ETC. 2 1 2 0
PROVISIONS 0 1 1 (1)
FOOD PURCHASES 5,585 1,229 5,735 (150)
BEVERAGES 0 4 1 (1)
SCHOOL MILK 50 47 50 0
RECHARGES OF DIRECT FOOD COSTS 68 (1) 68 0
OPENING STOCK 0 (747) 0 0
CLOSING STOCK 0 753 0 0
PROTECTIVE CLOTHING & UNIFORMS 232 82 302 (70)
LAUNDRY COSTS 10 4 10 0
OTHER SUPPLIES AND SERVICES 629 81 633 (4)
MAJOR SUPPLY OF ELECTRICAL POWER 2,250 (25) 2,340 (90)
OUTSOURCED MAIL 17 14 17 0
DELIVERY CHARGE 1 2 1 0
SUPPLIES AND SERVICES 18,792 3,981 19,512 (720)
188

Page 189

South Lanarkshire Council
Revised Period 4 Period 4 Period 4
Community & Enterprise Resources Summary Annual  Actual Forecast Forecast
Budget to Date (Projected Variance
Expenditure / Income Variance Trends 2026/2027 26/27 Outturn)
TRANSPORT AND PLANT
PURCHASE OF VEHICLES 0 1 0 0
PURCHASE OF PLANT 63 4 63 0
FLEET SERVICES - DRIVERS 65 0 107 (42)
FLEET SERVICES - FUEL 2,998 1,225 3,040 (42)
FLEET SERVICES - VEHICLE HIRE 1,229 616 1,229 0
POOL CAR CHARGES - RENTAL 96 15 83 13
POOL CAR CHARGES - FUEL 15 0 4 11
POOL CAR CHARGES - ADDITIONAL COSTS 7 0 7 0
OTHER TRANSPORT COSTS 77 57 87 (10)
TRANSPORT INSURANCE 93 0 81 12
LICENCES 491 172 491 0
FLEET SERVICES - REPAIRS 22 0 1 21
FLEET SERVICES - REPAIRS - OUTSIDE REPAIRS 800 356 887 (87)
FLEET SERVICES - REPAIRS - INSURANCE OUTSIDE REPAIRS 171 68 171 0
FLEET SERVICES - REPAIRS - OUTSIDE REPAIRS PLANT 59 28 59 0
FLEET SERVICES - REPAIRS - MATERIALS/ SPARES 1,030 322 1,030 0
FLEET SERVICES - REPAIRS -  INDIRECT MATERIALS EQUIP CONSUMBALES 60 17 60 0
FLEET SERVICES - REPAIRS - STOCK 93 29 93 0
FLEET SERVICES - REPAIRS - TYRES 382 133 422 (40)
PLANT SERVICES 19 0 6 13
FLEET SERVICE CHARGES - VEHICLE MAINTENANCE 4,623 1,375 5,096 (473)
FLEET SERVICE CHARGES - PLANT MAINTENANCE 269 84 304 (35)
FLEET SERVICE CHARGES - ASSET MODIFICATION 68 81 51 17
FLEET SERVICE CHARGES - LEASING 4,794 3,096 4,488 306
FLEET SERVICE CHARGES - HIRED VEHICLES 783 334 1,268 (485)
FLEET SERVICE CHARGES - CONTRACT HIRE 200 81 263 (63)
FLEET SERVICE CHARGES - ROAD FUND LICENCE 235 63 180 55
FLEET SERVICE CHARGES - FUEL 3,130 873 3,501 (371)
FLEET SERVICE CHARGES - DRIVERS 56 0 65 (9)
HIRE OF EXTERNAL VEHICLES 68 0 68 0
HIRE OF EXTERNAL PLANT 328 84 328 0
HIRE OF SKIPS 17 7 24 (7)
PUPIL TRANSPORT - SPECIAL EDUCATION 247 3 247 0
TRANSPORT AND PLANT 22,588 9,124 23,804 (1,216)
ADMINISTRATION
PRINTING AND STATIONERY 244 36 280 (36)
TELEPHONES 98 5 89 9
MOBILE PHONES 71 0 79 (8)
ADVERTISING - OF COUNCIL SERVICE AVAILABILITY 8 0 8 0
ADVERTISING - OTHER 75 15 75 0
POSTAGES/COURIERS 27 13 41 (14)
MEMBERSHIP FEES/SUBSCRIPTIONS 56 96 69 (13)
INSURANCE 260 0 260 0
MEDICAL COSTS 7 11 43 (36)
LEGAL EXPENSES 4 3 4 0
HOSPITALITY / CIVIC RECOGNITION 3 0 3 0
INTERNET AGENCY FEES 23 8 43 (20)
SECURITY UPLIFT FEES 26 2 26 0
OTHER ADMIN COSTS 6 0 6 0
TRAINING 12 7 24 (12)
ADMINISTRATION 920 196 1,050 (130)
189

Page 190

South Lanarkshire Council
Revised Period 4 Period 4 Period 4
Community & Enterprise Resources Summary Annual  Actual Forecast Forecast
Budget to Date (Projected Variance
Expenditure / Income Variance Trends 2026/2027 26/27 Outturn)
PAYMENT TO OTHER BODIES
SPTE: ANNUAL BUS SUBSIDY 2,166 2,741 2,167 (1)
SPTE: BUS OTHER 258 0 258 0
SPTE: FERRIES 29 0 29 0
SPTE: UNDERGROUND 1,318 0 1,318 0
SPTE: OTHER 1,727 0 1,727 0
SPTE: MAINTENANCE OF BUS SHELTERS AND STOPS 131 33 131 0
OTHER LOCAL AUTHORITIES 73 33 110 (37)
GRANTS TO VOLUNTARY ORGANISATIONS 22 0 22 0
PAYMENTS TO VOLUNTARY ORGANISATIONS 39 (1) 39 0
PAYMENTS TO OTHER BODIES 5,332 642 5,332 0
EXTERNAL AUDIT FEES 3 2 3 0
ACTIVITIES PROGRAMME 173 50 173 0
PAYMENT TO OTHER BODIES 11,271 3,500 11,309 (38)
PAYMENT TO CONTRACTORS
PAYMENT TO TRADING SERVICES CONTRACTOR 2,123 22 2,124 (1)
PAYMENT TO LOCAL AUTHORITY CONTRACTOR 302 97 302 0
PAYMENT TO PRIVATE CONTRACTOR 39,009 9,012 39,531 (522)
PAYMENT TO EXTERNAL CONSULTANTS / PROFESSIONAL SERVICES 0 19 0 0
PAYMENT TO CONTRACTORS 41,434 9,150 41,957 (523)
TRANSFER PAYMENTS
CONCESSIONARY FARES 640 321 640 0
TRANSFER PAYMENTS 640 321 640 0
FINANCING CHARGES
I.T. EQUIPMENT LEASING-CONTRACT 194 10 243 (49)
FINANCING CHARGES 194 10 243 (49)
TOTAL EXPENDITURE 226,027 56,168 225,914 113
INCOME
MILK SUBSIDIES FROM THE E.U. (37) 0 (37) 0
CONTRIBUTIONS FROM OTHER BODIES (17,810) (2,990) (17,810) 0
ERDF GRANT 0 (876) 0 0
SALES - GENERAL (4,728) (1,524) (4,572) (156)
SALES - DEPARTMENTS OF THE AUTHORITY (136) (68) (136) 0
FEES AND CHARGES - GENERAL (13,869) (4,498) (13,590) (279)
FEES AND CHARGES - DEPARTMENTS OF THE AUTHORITY (6,856) (2,237) (6,879) 23
RENTAL INCOME (48) (27) (48) 0
FLEET SERVICES (12,781) (5,048) (12,841) 60
OTHER INCOME (2,472) (120) (2,711) 239
RECOVERY FROM CAPITAL (1,333) (71) (1,333) 0
RECHARGES - DEPARTMENTS OF THE AUTHORITY (26,977) (7,743) (26,977) 0
TOTAL INCOME (87,047) (25,202) (86,934) (113)
NET EXPENDITURE 138,980 30,966 138,980 0
190

Page 191

Appendix B
South Lanarkshire Council
Revenue Budget Monitoring Statement
Period Ended 10 July 2026 (No.4)
Education Resources
Committee
Revised
Annual Projected
Projected
Outturn % Note
Year to
Date
Budget Outturn Variance Actual
Service Departments :- £m £m £m £m
Education 525.944 525.944 0.000 0.00% 128.077
Total Education Resources 525.944 525.944 0.000 0.00% 128.077
10
191

Page 192

Education Resources Variance Analysis 2026/27 (Period 4) 
Subjective Head Variance  Subjective line Service / amount Explanation
Employee Costs 674k under Teachers Basic / Superannuation /
National Insurance - (1,500k) over 
APT&C Basic / Superannuation /
National Insurance – 2,334k under 
Premature Retirals - (160k) over 
Schools - (1,500k) over 
Early Years / Support
Services – 2,334k under 
Schools - (160k) over 
The projected overspend relates
to the increased use of supply
teachers for absence cover. 
The projected underspend
mainly relates to Early Years and
Support Services posts and is
the result of staff turnover. 
The overspend relates to
increased monthly costs for
historic early retirals due to
inflation levels and the cost of
pensions. 
Property Costs  (100k) over Cleaning and Janitorial Supplies and
Equipment – (100k) over
Schools – (100k) over This overspend represents the
cost of janitorial and cleaning
materials being higher than the
budget for schools. 
Supplies &
Services
(435k) over Aids for Clients - (110k) over 
Materials, Apparatus and Equipment
– (200k) over 
Schools - (110k) over 
Schools - (200k) over 
This forecast overspend is due to
the increased demand and cost
of new equipment required for
children in schools with complex
physical needs. 
The forecast overspend is due to
the additional cost of per capita
expenditure reflecting the growth
in pupil numbers and price
increases. 
192

Page 193

Subjective Head Variance  Subjective line Service / amount Explanation
Supplies &
Services (cont.) 
Catering Contract - (125k) over  Schools - (125k) over The overspend is due to an
increased cost for food for
breakfast clubs. 
Transport & Plant (2,691k) over Fleet Services Charges - (101k) over 
Pupil Transport - ASN - (2,225k)
over 
Pupil Transport - Strathclyde
Passenger Transport - (365k) over 
Schools - (101k) over 
Schools - (2,225k) over 
Schools - (365k) over 
This is a demand led service and
reflects the volume of children
requiring ASN transport to school
and increased costs. 
This is a demand led service and
reflects the volume of children
requiring ASN transport to school
and increased costs. 
This is a demand led service and
reflects the volume of children
requiring mainstream transport to
school and increased costs. 
Payments to
Other Bodies 
(274k) over  Other Local Authorities – (51k) over 
Payments to Other Bodies - 700k
under 
Schools – (51k) over 
Early Years - 700k under 
The overspend is due to an
increase in the cost of external
school placements within other
local authorities 
This projected underspend is
due to less than anticipated core
Early Years spend including
cross boundary charges to other
Local Authorities. 
193

Page 194

Subjective Head Variance  Subjective line Service / amount Explanation
Payments to
Other Bodies
(cont.) 
Independent Schools Places - (923k)
over 
Schools - (923k) over  This projected overspend reflects
the increased cost of placements
for pupils with additional support
needs in Independent Schools. 
Payments to
Contractors
151k under Payment to Private Contractors –
151k under 
Schools – 151k under This underspend represents the
timing of payments for insurance
within the PPP contract. 
Income 2,675k over
recovered
Fees and Charges - Other Local
Authorities - 775k over recovered 
Early Years Fees - 1,900k over
recovered 
Schools - 775k over
recovered 
Early Years - 1,900k over
recovered
This projected over recovery
reflects the increase in income
recovered from other Local
Authorities for children attending
schools in South Lanarkshire.
This income is used to support
the cost of external placements. 
This projected over recovery in
Early Years’ fees relates to
increased uptake of available
nursery places beyond 1140
hours. 
* The underlined variances represent new variances since the last report. 
194

Page 195

South Lanarkshire Council
Revised Period 4 Period 4 Period 4
Education Resource - Total Annual  Actual Forecast Forecast
Budget to Date (Projected Variance
Expenditure / Income Variance Trends 2026/2027 26/27 Outturn)
EMPLOYEE COSTS
TEACHERS BASIC 198,297 50,976 198,297 0
TEACHERS SUPERANNUATION 52,568 13,017 52,568 0
TEACHERS NI 24,674 6,900 24,674 0
FIXED TERM CONTRACT - TEACHER  - APT&C BASIC 1,102 739 2,602 (1,500)
FIXED TERM CONTRACT - TEACHER  SUPERANNUATION 0 94 0 0
SUPPLY TEACHERS - APT&C BASIC 0 394 0 0
SUPPLY TEACHERS - APT&C SUPERANNUATION 0 231 0 0
SUPPLY TEACHERS - APT&C NIC 0 52 0 0
APT&C BASIC 77,100 18,824 75,195 1,905
APT&C OVERTIME 3 139 3 0
APT&C SUPERANNUATION 13,722 3,143 13,469 253
APT&C NIC 9,554 2,260 9,378 176
TRAVEL AND SUBSISTANCE 205 42 205 0
PENSION INCREASES 434 113 434 0
PREMATURE RETIRALS 5,041 1,302 5,201 (160)
STRAIN ON THE FUND 0 1 0 0
EMPLOYEE COSTS 382,700 98,227 382,026 674
PROPERTY COSTS
RATES 19,505 0 19,505 0
SCOTTISH AKATER - UNMETERED CHARGES 0 1 0 0
SCOTTISH WATER - METERED (DRAINAGE) CHARGES 1,385 226 1,385 0
SCOTTISH WATER - METERED CHARGES 784 145 784 0
RENT 329 39 329 0
SERVICE CHARGE 56 26 56 0
PROPERTY INSURANCE 484 0 484 0
SECURITY COSTS 68 19 68 0
GROUNDS MAINTENANCE ADDITIONAL AKORKS 0 (2) 0 0
REPAIRS & MAINTENANCE - INTERNAL CONTRACTOR 71 71 71 0
LIFE CYCLE MAINTENANCE 2 2 2 0
REPAIRS & MAINTENANCE - EXTERNAL CONTRACTOR 34 34 34 0
ADAPTIONS - INTERNAL CONTRACTORS 55 37 55 0
ELECTRICITY  - CONTRACT 7,671 611 7,671 0
GAS 4,074 435 4,074 0
HEATING OIL 164 32 164 0
SOLID FUEL 171 39 171 0
FIXTURE & FITTINGS 0 1 0 0
JANITOR SERVICE 80 19 80 0
CLEANING CONTRACT 513 192 513 0
CLEANING OUTWITH CONTRACT 5 0 5 0
CLEANING AND JANITORIAL SUPPLIES AND EQUIPMENT 397 154 497 (100)
HEALTH & HYGIENE MATERIALS 57 2 57 0
AKINDOAK CLEANING 5 0 5 0
REFUSE UPLIFT 20 3 20 0
OTHER PROPERTY COSTS 260 160 260 0
ACCOMMODATION RECHARGE TO USERS 882 0 882 0
PROPERTY COSTS 37,072 2,246 37,172 (100)
195

Page 196

South Lanarkshire Council
Revised Period 4 Period 4 Period 4
Education Resource - Total Annual  Actual Forecast Forecast
Budget to Date (Projected Variance
Expenditure / Income Variance Trends 2026/2027 26/27 Outturn)
SUPPLIES AND SERVICES
COMPUTER EQUIPMENT PURCHASE 117 75 117 0
COMPUTER EQUIPMENT RENTAL 1 0 1 0
I.T. EQUIPMENT MAINT-CONTRACT 3,025 1,092 3,025 0
I.T. ELECTRONIC MESSAGING 2 1 2 0
EQUIPMENT, APPARATUS AND TOOLS 38 7 38 0
SMALL TOOLS 1 1 1 0
AIDS FOR CLIENTS 117 58 227 (110)
ADAPTATIONS FOR CLIENTS 28 22 28 0
SUPPLIES FOR CLIENTS 3 3 3 0
FURNITURE - OFFICE 3 2 3 0
FURNITURE - GENERAL 86 7 86 0
FURNISHINGS (INCL. CROCKERY & LINEN) 3 3 3 0
MATERIALS 3 3 3 0
MATERIALS, APPARATUS AND EQUIPMENT 2,412 877 2,612 (200)
PUPIL EQUITY FUNDING 7,262 0 7,262 0
LIBRARY/RESOURCE CENTREMATERIALS 70 18 70 0
PUBLICATIONS, JOURNALS, NEWSPAPERS ETC. 12 10 12 0
TV LICENCES - EDUCATION 28 4 28 0
PROVISIONS 64 55 64 0
FOOD PURCHASES 59 49 59 0
BEVERAGES 3 2 3 0
SCHOOL MILK 8 8 8 0
NURSERY MILK 18 18 18 0
RECHARGE OF DIRECT FOOD COSTS 1 1 1 0
PROTECTIVE CLOTHING & UNIFORMS 22 13 22 0
LAUNDRY COSTS 1 0 1 0
OTHER SUPPLIES AND SERVICES 23 (5) 23 0
HEALTH AND SAFETY 40 0 40 0
CATERING - CONTRACT 2,607 26 2,732 (125)
CATERING - OUTWITH CONTRACT 34 0 34 0
CATERING - EXTERNAL 7 7 7 0
ARTIST FEES / PERFORMING ARTS / ENTERTA 5 3 5 0
DELIVERY CHARGE 1 1 1 0
SUPPLIES AND SERVICES 16,104 2,361 16,539 (435)
TRANSPORT AND PLANT
POOL CAR CHARGES-RENTAL 1 1 1 0
OTHER TRANSPORT COSTS 2 0 2 0
INSURANCE 3 0 3 0
FLEET SERVICE CHARGES 1,660 257 1,761 (101)
HIRE OF EXTERNAL VEHICLES 129 123 129 0
HIRE OF SKIPS 8 8 8 0
EXTERNAL TRANSPORT CONTRACT 6 6 6 0
PUPIL TRANSPORT-SPECIAL EDUCATIONAL NEEDS 6,532 1,943 8,757 (2,225)
PUPIL TRANSPORT-S'CLYDE PASSENGER TRANSPORT 9,423 3,951 9,788 (365)
PUPIL TRANSPORT - OTHER 162 30 162 0
TRANSPORT AND PLANT 17,926 6,319 20,617 (2,691)
196

Page 197

South Lanarkshire Council
Revised Period 4 Period 4 Period 4
Education Resource - Total Annual  Actual Forecast Forecast
Budget to Date (Projected Variance
Expenditure / Income Variance Trends 2026/2027 26/27 Outturn)
ADMINISTRATION
PRINTING AND STATIONERY 429 117 429 0
TELEPHONES 221 43 221 0
MOBILE PHONES 13 0 13 0
ADVERTISING - OTHER 11 0 11 0
POSTAGES/COURIERS 58 6 58 0
MEMBERSHIP FEES/SUBSCRIPTIONS 89 85 89 0
INSURANCE 76 0 76 0
MEDICAL COSTS 8 8 8 0
HOSPITALITY / CIVIC RECOGNITION 1 1 1 0
SECURITY UPLIFT FEES 6 2 6 0
OTHER ADMIN COSTS 2 0 2 0
CONFERENCES - OFFICIALS (incl associated costs) 52 0 52 0
TRAINING 177 165 177 0
ADMINISTRATION 1,143 427 1,143 0
PAYMENT TO OTHER BODIES
OTHER COMMITTEES OF THE AUTHORITY 25 6 25 0
OTHER LOCAL AUTHORITIES 1,432 279 1,483 (51)
SCOTTISH QUALIFICATIONS AUTHORITY 1,563 1,578 1,563 0
PAYMENTS TO OTHER BODIES 21,759 6,815 21,059 700
INDEPENDENT SCHOOL PLACES 3,507 418 4,430 (923)
CONTRACT SPEECH THERAPY 678 0 678 0
SCHOOL ACTIVITIES 156 108 156 0
RESEARCH GRANTS - EDUCATION 49 49 49 0
PARENT COUNCILS (PREV.SCHOOL BOARDS) 28 0 28 0
P.E. FACILITIES 93 4 93 0
ACTIVITIES PROGRAMME 177 170 177 0
COUNSELLING 1,438 384 1,438 0
COPYRIGHT AGREEMENT 235 234 235 0
VAT FREE EXCURSIONS - EDUCATION 33 33 33 0
PRIVATE INDIVIDUALS - GENERAL 10 1 10 0
PAYMENT TO OTHER BODIES 31,183 10,079 31,457 (274)
PAYMENT TO CONTRACTORS
PAYMENT TO PRIVATE CONTRACTOR 49,583 8,036 49,432 151
PAYMENT TO EXTERNAL CONSULTANTS / PROFESSIONAL SERVICES 8 6 8 0
PAYMENT TO CONTRACTORS 49,591 8,042 49,440 151
TRANSFER PAYMENTS
RENT REBATES 229 229 229 0
FOOTWEAR & CLOTHING GRANTS 2,330 1,804 2,330 0
WORK EXPERIENCE 16 0 16 0
TRANSFER PAYMENTS 2,575 2,033 2,575 0
FINANCING CHARGES
LEASING CHARGES - OPERATIONAL 3 0 3 0
I.T. EQUIPMENT LEASING - CONTRACT 372 67 372 0
FINANCING CHARGES 375 67 375 0
TOTAL EXPENDITURE 538,669 129,801 541,344 (2,675)
197

Page 198

South Lanarkshire Council
Revised Period 4 Period 4 Period 4
Education Resource - Total Annual  Actual Forecast Forecast
Budget to Date (Projected Variance
Expenditure / Income Variance Trends 2026/2027 26/27 Outturn)
INCOME
GOVERNMENT GRANT - GAELIC EDUCATION (175) (44) (175) 0
GOVERNMENT GRANTS - OTHER EDUCATION GRANTS (9,201) (536) (9,201) 0
CONTRIBUTIONS FROM OTHER BODIES (940) (236) (940) 0
FEES AND CHARGES - GENERAL 0 (11) 0 0
FEES AND CHARGES - OTHER LOCAL AUTHORITIES (769) (25) (1,544) 775
PLAYGROUP ACCOMMODATION CHARGE (12) 0 (12) 0
EARLY YEARS FEES (702) (820) (2,602) 1,900
RENTAL INCOME (20) (4) (20) 0
OTHER INCOME (24) (48) (24) 0
ACCOMMODATION INCOME FROM USERS (882) 0 (882) 0
INCOME (12,725) (1,724) (15,400) 2,675
NET EXPENDITURE 525,944 128,077 525,944 0
198

Page 199

Appendix C
South Lanarkshire Council
Revenue Budget Monitoring Statement
Period Ended 10 July 2026 (No.4)
Finance and Corporate Resources
Committee
Revised
Annual Projected
Projected
Outturn % Note
Year to
Date
Budget Outturn Variance Actual
Service Departments :- £m £m £m £m
Finance Services - Strategy 2.834 2.776 0.058 2.05% 1.089
Finance Services - Transactions 20.285 20.263 0.022 0.11% 6.490
Audit and Compliance Services 0.417 0.433 (0.016) (3.84%) 0.141
Information Technology Services 9.160 9.255 (0.095) (1.04%) 6.683
Communications and Strategy Services 3.673 3.555 0.118 3.21% 1.431
Administration and Licensing Services 5.258 5.258 0.000 0.00% 1.576
Personnel Services 7.740 7.827 (0.087) (1.12%) 2.353
Total Finance and Corporate Resources 49.367 49.367 (0.000) 0.00% 19.763
10
199

Page 200

Finance and Corporate Resources Variance Analysis 2026/27 (Period 4) 
Subjective Head Variance  Subjective line Service / amount Explanation
Employee Costs  (26k) over  APT&C Basic, Superannuation, NI –
(46k) over
IT Services – (104k)
over 
The projected overspend is
due to lower than budgeted
turnover during the year. 
Personnel – (87k) over 
Finance Services
(Transactions) – (34k)
over 
Finance Services
(Strategy) – 72k under
The projected underspend is
due to vacant posts and the
anticipated level of turnover
during the year. 
Communications and
Strategy – 124k under 
Supplies and Services (137k) over Computer Equipment Purchase –
(75k) over
Finance Services
(Transactions) – (75k)
over 
The projected overspend is
due to greater than budgeted
IT costs. 
Computer Equipment Maintenance –
(184k) over 
IT Services – (184k)
over
The projected overspend is a
result of increased contract
costs. This is partially offset
by an over recovery in
income. 
Administration (132k) over Postages and Couriers – (149k) over Finance Services
(Transactions) – 149k
over
The projected overspend
reflects additional postage
costs for service delivery.
200

Page 201

Subjective Head Variance  Subjective line Service / amount Explanation
Income  324k over
recovered
Fees and Charges – General – 240k
over recovered
Finance Services
(Transactions) – 240k
over recovered 
The projected over-recovery
of income reflects additional
commission received from
Scottish Water for the
collection of water and
sewage. 
Other Income – 69k over recovered IT Services – 46k over
recovered
The projected over-recovery
of income reflects internal
recharges to resources and
partially offsets the
overspend on Computer
Equipment Maintenance as a
result of increased contract
costs. 
* The underlined variances represent new variances since the last report.
201

Page 202

South Lanarkshire Council
Revised Period 4 Period 4 Period 4
Finance & Corporate Resources - Total Annual  Actual Forecast Forecast
Budget to Date (Projected Variance
Expenditure / Income Variance Trends 2026/2027 26/27 Outturn)
EMPLOYEE COSTS
APT & C BASIC 30,975 7,869 30,659 316
APT & C OVERTIME 42 55 43 (1)
APT & C SUPERANNUATION 4,949 1,267 4,975 (26)
APT & C NIC 3,523 999 3,858 (335)
APT & C TRAVEL EXPENSES 2 0 1 1
TRAVEL AND SUBSISTANCE 1 0 1 0
MSC TRAINEES BASIC 0 1 0 0
PENSION INCREASES 1,011 264 992 19
STRAIN ON THE FUND 0 1 0 0
EMPLOYEE COSTS 40,503 10,456 40,529 (26)
PROPERTY COSTS
RENT 4 1 4 0
SECURITY COSTS 121 0 121 0
ELECTRICITY  - CONTRACT 0 2 0 0
FIXTURE & FITTINGS 2,117 19 2,117 0
HEALTH & HYGIENE MATERIALS 140 22 140 0
OTHER PROPERTY COSTS 883 0 883 0
PROPERTY COSTS 3,265 44 3,265 0
SUPPLIES AND SERVICES
COMPUTER EQUIPMENT PURCHASE 4,923 2,597 4,998 (75)
COMPUTER EQUIPMENT MAINTENANCE 2,217 2,308 2,295 (78)
I.T. EQUIPMENT MAINT - CONTRACT 657 46 641 16
I.T. ELECTRONIC MESSAGING 36 0 36 0
EQUIPMENT, APPARATUS AND TOOLS 151 20 151 0
SUPPLIES FOR CLIENTS 79 18 79 0
FURNITURE - OFFICE 1 3 1 0
MATERIALS 112 22 112 0
MATERIALS, APPARATUS AND EQUIPMENT 2 0 2 0
PUBLICATIONS, JOURNALS, NEWSPAPERS ETC. 2 1 2 0
PROVISIONS - GENERAL 20 2 20 0
FOOD PURCHASES WITHIN CONTRACT 1 (67) 1 0
BEVERAGES 2 0 2 0
PROTECTIVE CLOTHING & UNIFORMS 2 0 2 0
OTHER SUPPLIES AND SERVICES 170 55 170 0
CATERING - OUTWITH CONTRACT 6 0 6 0
OUTSOURCED MAIL 174 66 174 0
BULK BUYING DISCOUNT 0 (2) 0 0
SUPPLIES AND SERVICES 8,555 5,069 8,692 (137)
TRANSPORT AND PLANT
POOL CAR CHARGES - RENTAL 15 1 13 2
POOL CAR CHARGES - FUEL 3 0 3 0
FLEET SERVICE CHARGES 15 4 15 0
TRANSPORT AND PLANT 33 5 31 2
202

Page 203

South Lanarkshire Council
Revised Period 4 Period 4 Period 4
Finance & Corporate Resources - Total Annual  Actual Forecast Forecast
Budget to Date (Projected Variance
Expenditure / Income Variance Trends 2026/2027 26/27 Outturn)
ADMINISTRATION
PRINTING AND STATIONERY 528 40 528 0
TELEPHONES 1,550 409 1,515 35
MOBILE PHONES 174 159 174 0
ADVERTISING - RECRUITMENT 29 2 29 0
ADVERTISING - OF COUNCIL SERVICE AVAILABILITY 0 2 0 0
ADVERTISING - OTHER 125 17 126 (1)
POSTAGES/COURIERS 908 294 1,057 (149)
SMS MESSAGING 5 1 5 0
MEMBERSHIP FEES/SUBSCRIPTIONS 233 11 238 (5)
INSURANCE 141 0 141 0
MEDICAL COSTS 350 77 353 (3)
LEGAL EXPENSES 167 30 167 0
HOSPITALITY / CIVIC RECOGNITION 31 1 31 0
PAYPOINT AGENCY FEES 70 13 70 0
SECURITY UPLIFT FEES 2 0 2 0
OTHER ADMIN COSTS 532 218 532 0
MEMBERS ALLOWANCES 2,592 628 2,592 0
CONFERENCES - MEMBERS (incl associated costs) 11 1 11 0
CONFERENCES - OFFICIALS (incl associated costs) 5 0 5 0
TRAINING 761 200 770 (9)
VOLUNTEERS' EXPENSES 8 5 8 0
INTERNAL SUPPORT SERVICES ALLOCATION 68 0 68 0
ADMINISTRATION 8,290 2,108 8,422 (132)
PAYMENT TO OTHER BODIES
OTHER LOCAL AUTHORITIES 4 0 0 4
GRANTS TO VOLUNTARY ORGANISATIONS 149 44 149 0
PAYMENTS TO OTHER BODIES 3,112 1,336 3,136 (24)
EXTERNAL AUDIT FEES 665 103 665 0
PAYMENT TO OTHER BODIES 3,930 1,483 3,950 (20)
PAYMENT TO CONTRACTORS
PAYMENT TO PRIVATE CONTRACTOR 0 42 0 0
PAYMENT TO EXTERNAL CONSULTANTS / PROFESSIONAL SERVICES 256 26 256 0
PAYMENT TO CONTRACTORS 256 68 256 0
TRANSFER PAYMENTS
RENT ALLOWANCE 23,581 4,564 23,581 0
RENT REBATES 43,581 7,405 43,581 0
TRANSFER PAYMENTS 67,162 11,969 67,162 0
FINANCING CHARGES
I.T. EQUIPMENT LEASING-CONTRACT 1,422 822 1,433 (11)
FINANCING CHARGES 1,422 822 1,433 (11)
TOTAL EXPENDITURE 133,416 32,024 133,740 (324)
203

Page 204

South Lanarkshire Council
Revised Period 4 Period 4 Period 4
Finance & Corporate Resources - Total Annual  Actual Forecast Forecast
Budget to Date (Projected Variance
Expenditure / Income Variance Trends 2026/2027 26/27 Outturn)
INCOME
STATUTORY ADDITIONS - COST OF COLLECTION (865) 0 (865) 0
RENT REBATES SUBSIDY (37,191) (6,160) (37,191) 0
RENT ALLOWANCE SUBSIDY (23,067) (4,082) (23,067) 0
DWP SUBSIDY (1,170) (305) (1,170) 0
DHP 0 656 0 0
CONTRIBUTIONS FROM DEVELOPMENT AGENCIES (150) (79) (150) 0
CONTRIBUTIONS FROM OTHER BODIES (296) (65) (311) 15
SALES - DEPARTMENTS OF THE AUTHORITY (20) 0 (20) 0
FEES AND CHARGES - GENERAL (4,648) (847) (4,888) 240
CHARGES TO HEALTH BOARDS (45) 0 (45) 0
FEES AND CHARGES - OTHER BODIES (221) (26) (221) 0
FEES AND CHARGES - DEPARTMENTS OF THE AUTHORITY (2,488) (486) (2,488) 0
HOME LOANS REPAYMENTS (5) (5) (5) 0
BIRTH REGISTRATION (16) (3) (16) 0
DEATH REGISTRATION (64) (17) (64) 0
MARRIAGE STATUTORY FEES (108) (41) (108) 0
EXTRACT ISSUE (83) (23) (83) 0
MARRIAGES (52) (23) (52) 0
CITIZENSHIP CEREMONIES (18) (8) (18) 0
CIVIL PARTNERSHIPS (1) 0 (1) 0
OTHER INCOME (6,864) (747) (6,933) 69
REALLOCATION OF CENTRAL SUPPORT COSTS (6,668) 0 (6,668) 0
REALLOCATION OF SUPPORT COSTS (9) 0 (9) 0
INCOME (84,049) (12,261) (84,373) 324
NET EXPENDITURE 49,367 19,763 49,367 0
204

Page 205

Appendix D
South Lanarkshire Council
Revenue Budget Monitoring Statement
Period Ended 10 July 2026 (No.4)
Housing and Technical Resources
Committee
Revised
Annual Projected
Projected
Outturn % Note
Year to
Date
Budget Outturn Variance Actual
Service Departments :- £m £m £m £m
Housing Services 8.954 8.936 0.018 0.20% 1.200
Property Services 10.051 10.069 (0.018) (0.18%) 3.785
Total Housing and Technical Resources 19.005 19.005 (0.000) (0.00%) 4.985
10
205

Page 206

Housing and Technical Resources (excl HRA) Variance Analysis 2026/27 (Period 4) 
Subjective Head Variance  Subjective line Service / amount Explanation
Employee Costs 1,339k
under 
APT&C Basic / Overtime /
Superannuation / National
Insurance – 926k under 
Housing Services –
87k under 
Property Services
847k under
The variance relates to vacancies which
are actively being recruited in line with
Service requirements. 
The variance relates to vacancies, mainly
within consultancy services, estates and
offset in part by building services.
Vacancies are being actively recruited in
line with Service requirements. 
The forecast underspend in consultancy
services if offset by an under recovery in
income   
Manual Workers – 428k under  Property Services –
428k under 
The variance relates to vacancies which
are actively being recruited in line with
Service requirements. 
Property Costs (172k) over Security Costs – (71k) over  Property Services –
(71k) over
This variance relates to greater
expenditure on CCTV security costs than
is currently budgeted, due to CCTV
infrastructure project upgrade. 
Income  (1,148k)
under
recovered
Rental Income – (451k) under
recovered 
Property Services –
(451k) under
recovered
Income is under recovered due to lower
than budgeted rental income within the
Estates service.
206

Page 207

Subjective Head Variance  Subjective line Service / amount Explanation
Income (cont.)  Recovery from
Capital/Recharges – (714k)
under recovered 
Property Services –
(714k) under
recovered 
The level of income recovered is mainly
within consultancy services and varies
depending on the current workload, the
timing of a wide variety of projects and is
offset by a reduction in employee costs. 
* The underlined variances represent new variances since the last report. 
207

Page 208

South Lanarkshire Council
Housing & Technical Resources Revised Period 4 Period 4 Period 4
Annual  Actual Forecast Forecast
Expenditure / Income Variance Trends 2025/2026 Budget to Date (Projected Variance
26/27 Outturn)
EMPLOYEE COSTS
APT & C BASIC 18,688 4,588 17,917 771
APT & C OVERTIME 94 45 194 (100)
APT & C SUPERANNUATION 3,126 730 2,971 155
APT & C NIC 2,403 582 2,303 100
MANUAL BASIC 24,005 5,722 22,981 1,024
MANUAL OVERTIME (316) 280 636 (952)
MANUAL SUPERANNUATION 3,888 928 3,761 127
MANUAL NIC 3,148 746 2,919 229
TRAVEL AND SUBSISTANCE 28 1 20 8
OTHER EMPLOYEE COSTS (22) (11) (24) 2
PENSION INCREASES 643 163 666 (23)
STRAIN ON FUND 0 2 2 (2)
EMPLOYEE COSTS 55,685 13,776 54,346 1,339
PROPERTY COSTS
RATES 2,251 8 2,246 5
SCOTTISH WATER - UNMETERED CHARGES 8 0 8 0
SCOTTISH WATER - METERED CHARGES 236 76 235 1
RENT 1,629 748 1,629 0
SERVICE CHARGE 420 209 422 (2)
FACTORING CHARGES 5 0 5 0
OTHER ACCOMMODATION COSTS 3,455 182 3,455 0
BED AND BREAKFAST 27 (3) 27 0
PROPERTY INSURANCE 322 34 318 4
SECURITY COSTS 260 47 331 (71)
GROUND MAINTENANCE 163 88 167 (4)
GROUNDS MAINTENANCE ADDITIONAL WORKS 10 0 10 0
REPAIRS & MAINTENANCE - INTERNAL CONTRACTOR 3,300 479 3,322 (22)
LIFE CYCLE MAINTENANCE 5,054 1,210 5,055 (1)
REPAIRS & MAINTENANCE - EXTERNAL CONTRACTOR 348 113 348 0
HOUSING - RENT W/O UNLET PERIODS 354 (39) 354 0
HOUSING - RENT W/O BAD PERIODS 790 172 790 0
FIXED ELECTRICAL 0 2 0 0
EPC 0 3 0 0
ELECTRICITY  - CONTRACT 1,348 354 1,383 (35)
ELECTRICITY  - NON CONTRACT 27 6 27 0
GAS 447 112 431 16
HEATING OIL 12 1 31 (19)
FIXTURE & FITTINGS 838 379 852 (14)
JANITOR SERVICE 152 157 157 (5)
CLEANING CONTRACT 401 418 406 (5)
CLEANING OUTWITH CONTRACT 0 9 0 0
CLEANING MATERIALS 10 1 10 0
WINDOW CLEANING 2 1 2 0
PEST CONTROL 6 0 6 0
REFUSE UPLIFT 395 24 395 0
REMOVAL & STORAGE COSTS 68 11 68 0
OTHER PROPERTY COSTS 741 183 741 0
OFFICE ACCOM-FACILITIES MANAGEMENT 1,036 562 1,036 0
ACCOMMODATION RECHARGE TO USERS 33 17 53 (20)
PROPERTY COSTS 24,148 5,564 24,320 (172)
208

Page 209

South Lanarkshire Council
Housing & Technical Resources Revised Period 4 Period 4 Period 4
Annual  Actual Forecast Forecast
Expenditure / Income Variance Trends 2025/2026 Budget to Date (Projected Variance
SUPPLIES AND SERVICES
COMPUTER EQUIPMENT PURCHASE 517 200 537 (20)
COMPUTER EQUIPMENT MAINTENANCE 6 0 6 0
I.T. EQUIPMENT MAINT-CONTRACT 207 1 207 0
EQUIPMENT, APPARATUS AND TOOLS 45 1 45 0
ADAPTATIONS FOR CLIENTS 500 121 502 (2)
FURNITURE - OFFICE 0 5 0 0
FURNISHINGS 0 31 0 0
MATERIALS 10,521 1,254 10,521 0
MATERIALS, APPARATUS AND EQUIPMENT 0 4 0 0
AUDIO VISUAL 10 0 10 0
TV LICENCES - EDUCATION 1 0 1 0
FOOD PURCHASES WITHIN CONTRACT 0 1 0 0
PROTECTIVE CLOTHING & UNIFORMS 44 7 44 0
OTHER SUPPLIES AND SERVICES 119 18 133 (14)
HEALTH AND SAFETY 1 0 1 0
MAJOR SUPPLY OF ELECTRICAL POW 0 28 28 (28)
OUTSOURCED MAIL 0 7 2 (2)
BULK BUYING DISCOUNT 0 (1) 0 0
SUPPLIES AND SERVICES 11,971 1,677 12,037 (66)
TRANSPORT AND PLANT
PURCHASE OF VEHICLES 5 5 5 0
PURCHASE OF PLANT 125 136 125 0
FLEET SERVICES - FUEL 4 7 4 0
POOL CAR RECHARGE - RENTAL CHARGE 39 5 41 (2)
POOL CAR RECHARGE - FUEL 12 0 12 0
POOL CAR RECHARGE - ADDITIONAL CHARGES 1 0 1 0
OTHER TRANSPORT COSTS 4 0 4 0
TRANSPORT INSURANCE 44 0 44 0
FLEET SERVICES - REPAIRS 0 4 0 0
PLANT SERVICES 7 0 7 0
FLEET SERVICE CHARGES 2,672 1,560 2,668 4
HIRE OF EXTERNAL VEHICLES 289 85 289 0
HIRE OF EXTERNAL PLANT 257 18 257 0
HIRE OF SCAFOLDING 1,077 235 1,077 0
HIRE OF SKIPS 33 141 33 0
EXTERNAL TRANSPORT CONTRACT 40 3 40 0
TAXI CHARGES - CONTRACTED 5 0 5 0
TRANSPORT AND PLANT 4,614 2,199 4,612 2
209

Page 210

South Lanarkshire Council
Housing & Technical Resources Revised Period 4 Period 4 Period 4
Annual  Actual Forecast Forecast
Expenditure / Income Variance Trends 2025/2026 Budget to Date (Projected Variance
ADMINISTRATION
PRINTING AND STATIONERY 74 17 76 (2)
TELEPHONES 97 6 94 3
MOBILE PHONES 45 0 45 0
ADVERTISING - OF COUNCIL SERVICE AVAILABILITY 0 0 4 (4)
ADVERTISING - OTHER 6 0 6 0
POSTAGES/COURIERS 28 9 24 4
MEMBERSHIP FEES/SUBSCRIPTIONS 15 5 14 1
INSURANCE 212 0 212 0
MEDICAL COSTS 16 3 16 0
LEGAL EXPENSES 7 10 9 (2)
PETTY OUTLAYS 12 8 12 0
HOSPITALITY / CIVIC RECOGNITION 2 0 2 0
OTHER ADMIN COSTS 8 0 8 0
INTERNAL SUPPORT SERVICES ALLOCATION 894 145 894 0
CENTRAL ADMINISTRATION 2,749 0 2,749 0
ADMINISTRATION 4,165 203 4,165 0
PAYMENT TO OTHER BODIES
OTHER COMMITTEES OF THE AUTHORITY 2,287 414 2,287 0
OTHER LOCAL AUTHORITIES 0 4 1 (1)
PAYMENTS TO OTHER BODIES 953 440 910 43
SUPPORTING PEOPLE INTERNAL PROVIDER 1,129 373 1,129 0
SUPPORTING PEOPLE EXTERNAL PROVIDER 13 5 13 0
HOUSING ADMINISTRATION 885 272 885 0
ASSISTANCE TO HOME OWNERS 1,091 252 1,135 (44)
PRIVATE INDIVIDUALS - GENERAL 151 3 151 0
PAYMENT TO OTHER BODIES 6,509 1,763 6,511 (2)
PAYMENT TO CONTRACTORS
PAYMENT TO LOCAL AUTHORITY CONTRACTOR 0 154 0 0
PAYMENT TO PRIVATE CONTRACTOR 12,102 3,401 12,102 0
PAYMENT TO EXTERNAL CONSULTANTS 306 193 257 49
PAYMENT TO CONTRACTORS 12,408 3,748 12,359 49
TRUST FUND EXPENDITURE
TRANSFER PAYMENTS
FINANCING CHARGES
DEPRECIATION 2 0 2 0
I.T. EQUIPMENT LEASING-CONTRACT 156 3 158 (2)
INTEREST ON REVENUE BALANCES 2 0 2 0
FINANCING CHARGES 160 3 162 (2)
TOTAL EXPENDITURE 119,660 28,933 118,512 1,148
210

Page 211

South Lanarkshire Council
Housing & Technical Resources Revised Period 4 Period 4 Period 4
Annual  Actual Forecast Forecast
Expenditure / Income Variance Trends 2025/2026 Budget to Date (Projected Variance
INCOME
CONTRIBUTIONS FROM OTHER BODIES (1,903) (478) (1,903) 0
SALES - DEPARTMENTS OF THE AUTHORITY (460) 0 (460) 0
FEES AND CHARGES - GENERAL (532) (83) (541) 9
FEES AND CHARGES - DEPARTMENTS OF THE A (46) 0 (46) 0
RENTAL INCOME (4,011) (771) (3,560) (451)
HOUSE RENTS (7,011) (1,812) (7,011) 0
OTHER INCOME (3,684) (944) (3,684) 0
REALLOCATION OF CENTRAL SUPPORT COSTS (876) 0 (884) 8
REALLOCATION OF SUPPORT COSTS (1,630) 0 (1,630) 0
RECOVERY FROM CAPITAL (33,613) (7,284) (32,769) (844)
RECHARGES - DEPARTMENTS OF AUTHORITY (46,889) (11,760) (47,019) 130
MANUAL RECHARGES - DEPARTMENTS OF AUTHORITY 0 (816) 0 0
INCOME (100,655) (23,948) (99,507) (1,148)
NET EXPENDITURE 19,005 4,985 19,005 0
211

Page 212

212

Page 213

Appendix E
Housing and Technical Resources - HRA Variance Analysis 2026/27 (Period 4) 
Subjective Head Variance  Subjective line Service / amount Explanation
Employee Costs  16k under  APT&C Basic/Overtime/
Superannuation/National
Insurance – 16k under
HRA - 16k under  The underspend is mainly due to
vacancies across the service. 
Administration 16k over Membership Fees / Subscriptions
– 16k over 
HRA - 16k over Scotlands Housing Network / Chartered
Institute of Housing/ Landlord
Accreditation Scotland costs exceeding
budget. 
* The underlined variances represent new variances since the last report. 
10
213

Page 214

South Lanarkshire Council
Revised Period 4 Period 4 Period 4
Housing and Revenue Account Annual  Actual Forecast Forecast
Budget to Date (Projected Variance
Expenditure / Income Variance Trends 2026/2027 26/27 Outturn)
EMPLOYEE COSTS
APT & C BASIC 13,083 3,367 13,121 (38)
APT & C OVERTIME 69 17 80 (11)
APT & C SUPERANNUATION 2,300 540 2,234 66
APT & C NIC 1,593 412 1,594 (1)
TRAVEL AND SUBSISTANCE 10 1 10 0
OTHER EMPLOYEE COSTS 27 1 27 0
PENSION INCREASES 244 58 244 0
APPRENTICESHIP LEVY 67 0 67 0
EMPLOYEE COSTS 17,393 4,396 17,377 16
PROPERTY COSTS
RATES 72 0 72 0
SCOTTISH WATER - UNMETERED CHARGES 4 0 4 0
SCOTTISH WATER - METERED CHARGES 8 4 8 0
RENT 6 4 6 0
SERVICE CHARGE 94 0 94 0
FACTORING CHARGES 0 3 0 0
OTHER ACCOMMODATION COSTS 1 0 1 0
PROPERTY INSURANCE 3,661 0 3,661 0
SECURITY COSTS 55 2 55 0
GROUND MAINTENANCE 4,412 3,585 4,412 0
REPAIRS & MAINTENANCE - INTERNAL CONTRACTOR 46,544 11,092 46,544 0
LIFE CYCLE MAINTENANCE 0 37 0 0
REPAIRS & MAINTENANCE - EXTERNAL CONTRACTOR 901 245 901 0
HOUSING - RENT FREE ACCOMMODATION 266 44 266 0
GAS MAINTENANCE COSTS 0 2 0 0
ELECTRICAL HEATING MAINTENANCE 0 2 0 0
HOUSING - RENT W/O UNLET PERIODS 3,130 582 3,130 0
HOUSING - RENT W/O BAD PERIODS 1,331 149 1,331 0
ASBESTOS 143 29 143 0
ELECTRICITY  - CONTRACT 1,350 205 1,350 0
ELECTRICITY  - NON CONTRACT 0 1 0 0
GAS 438 104 438 0
HEATING OIL 54 12 54 0
SOLID FUEL 4 3 4 0
FIXTURE & FITTINGS 53 34 53 0
JANITOR SERVICE 43 31 43 0
CLEANING CONTRACT 482 507 482 0
CLEANING MATERIALS 57 5 57 0
WINDOW CLEANING 16 6 16 0
PEST CONTROL 126 58 126 0
REFUSE UPLIFT 34 7 34 0
REMOVAL & STORAGE COSTS 14 12 14 0
OTHER PROPERTY COSTS 32 2 32 0
PROPERTY COSTS 63,331 16,767 63,331 0
214

Page 215

South Lanarkshire Council
Revised Period 4 Period 4 Period 4
Housing and Revenue Account Annual  Actual Forecast Forecast
Budget to Date (Projected Variance
Expenditure / Income Variance Trends 2026/2027 26/27 Outturn)
SUPPLIES AND SERVICES
COMPUTER EQUIPMENT PURCHASE 345 3 345 0
I.T. EQUIPMENT MAINT-CONTRACT 74 0 74 0
EQUIPMENT, APPARATUS AND TOOLS 13 9 13 0
ADAPTATIONS FOR CLIENTS 0 18 0 0
FURNITURE - OFFICE 10 3 10 0
MATERIALS 0 39 0 0
PROVISIONS 2 1 2 0
BEVERAGES 4 0 4 0
PROTECTIVE CLOTHING & UNIFORMS 12 2 12 0
LAUNDRY COSTS 16 8 16 0
OTHER SUPPLIES AND SERVICES 32 14 32 0
HEALTH AND SAFETY 15 0 15 0
CATERING - CONTRACT 0 1 0 0
SUPPLIES AND SERVICES 523 98 523 0
TRANSPORT AND PLANT
PURCHASE OF VEHICLES 0 3 0 0
FLEET SERVICES - FUEL 0 3 0 0
POOL CAR RECHARGE - RENTAL CHARGE 26 0 26 0
POOL CAR RECHARGE - FUEL 6 0 6 0
POOL CAR RECHARGE - ADDITIONAL CHARGES 1 0 1 0
OTHER TRANSPORT COSTS 0 6 0 0
FLEET SERVICE CHARGES 158 76 158 0
HIRE OF SKIPS 0 3 0 0
STORAGE 4 0 4 0
TRANSPORT AND PLANT 195 91 195 0
ADMINISTRATION
PRINTING AND STATIONERY 79 10 79 0
BULK PRINTING 68 0 68 0
TELEPHONES 95 18 95 0
MOBILE PHONES 34 2 34 0
ADVERTISING - OTHER 12 0 12 0
POSTAGES/COURIERS 171 20 171 0
SMS MESSAGING 0 2 0 0
MEMBERSHIP FEES/SUBSCRIPTIONS 38 395 54 (16)
MEDICAL COSTS 25 2 25 0
LEGAL EXPENSES 16 24 16 0
PETTY OUTLAYS 4 0 4 0
GIRO BANK AGENCY FEES 4 0 4 0
PAYPOINT AGENCY FEES 13 6 13 0
INTERNET AGENCY FEES 3 0 3 0
OTHER ADMIN COSTS 15 4 15 0
CONFERENCES - OFFICIALS 7 0 7 0
INTERNAL SUPPORT SERVICES ALLOCATION 5,020 0 5,020 0
ADMINISTRATION 5,604 483 5,620 (16)
PAYMENT TO OTHER BODIES
OTHER COMMITTEES OF THE AUTHORITY 2,316 0 2,316 0
GRANTS TO VOLUNTARY ORGANISATIONS 3 0 3 0
PAYMENTS TO VOLUNTARY ORGANISATIONS 31 3 31 0
PAYMENTS TO OTHER BODIES 32 0 32 0
PRIVATE INDIVIDUALS - GENERAL 300 3 300 0
PAYMENT TO OTHER BODIES 2,682 6 2,682 0
215

Page 216

South Lanarkshire Council
Revised Period 4 Period 4 Period 4
Housing and Revenue Account Annual  Actual Forecast Forecast
Budget to Date (Projected Variance
Expenditure / Income Variance Trends 2026/2027 26/27 Outturn)
PAYMENT TO CONTRACTORS
PAYMENT TO LOCAL AUTHORITY CONTRACTOR 135 214 135 0
PAYMENT TO PRIVATE CONTRACTOR 81 63 81 0
PAYMENT TO EXTERNAL CONSULTANTS 20 445 20 0
PAYMENT TO CONTRACTORS 236 722 236 0
FINANCING CHARGES
PRINCIPAL DEBT CHARGES 9,700 0 9,700 0
INTEREST-DEBT CHARGES 11,685 0 11,685 0
I.T. EQUIPMENT LEASING-CONTRACT 67 2 67 0
CFCR 33,851 3,493 33,851 0
FINANCING CHARGES 55,303 3,495 55,303 0
TOTAL EXPENDITURE 145,267 26,058 145,267 0
INCOME
SALES - DEPARTMENTS OF THE AUTHORITY (885) (272) (885) 0
FEES AND CHARGES - GENERAL (4,654) (235) (4,654) 0
RENTAL INCOME (1,021) 0 (1,021) 0
HOUSE RENTS (129,224) (38,021) (129,224) 0
LOCK UP RENTS (3,100) (607) (3,100) 0
INSURANCE RECOVERIES (899) (49) (899) 0
OTHER INCOME (1,269) (369) (1,269) 0
REALLOCATION OF SUPPORT COSTS (717) 0 (717) 0
YEAR END T/FER TO BALANCE SHEET (3,498) 0 (3,498) 0
INCOME (145,267) (39,553) (145,267) 0
NET EXPENDITURE 0 (13,495) 0 0
216

Page 217

Appendix F
South Lanarkshire Council
Revenue Budget Monitoring Statement
Period Ended 10 July 2026 (No.4)
Social Work Resources
Committee
Revised
Annual Projected
Projected
Outturn % Note
Year to
Date
Budget Outturn Variance Actual
Service Departments :- £m £m £m £m
Performance and Support Services 6.756 6.497 0.259 3.83% 1.767
Children and Families 49.929 50.727 (0.798) (1.60%) 11.676
Adults and Older People 212.592 212.592 0.000 0.00% 54.945
Justice and Substance Misuse 1.552 1.013 0.539 34.73% 0.713
Total Social Work Resources 270.829 270.829 0.000 0.00% 69.101
10
217

Page 218

Social Work Resources Variance Analysis 2026/27 (Period 4) 
Subjective Head Variance Subjective line Service / amount Explanation
Employee Costs  3,041k under Admin & Clerical Staff – 490k under 
Basic Grade Social Workers – 1,833k
under 
Managerial Support Specialist Staff –
(515k) over
Adult and Older people –
150k under 
Performance and
support – 270k under 
Criminal Justice – 58k
under 
Adult and Older People –
731k under 
Children and Family -
840k under 
Criminal Justice – 262k
under 
Adult and Older people –
(727k) over
This relates to the underspends
for Scheduling Assistant
vacancies in Homecare, which
are being recruited. This is offset
by overtime costs for Managerial
Support Specialist Staff (below).   
This is a result of vacancies
which are actively being
recruited. 
This is a result of vacancies
which are actively being
recruited. 
This is a result of vacancies
which are actively being
recruited. 
This is a result of vacancies
which are actively being
recruited. 
This is a result of vacancies
which are actively being
recruited. 
This is a result of turnover being
less than anticipated to date, and
218

Page 219

Subjective Head Variance Subjective line Service / amount Explanation
Employee Costs
(cont.) 
Care staff – 714k under 
Home Carers (Manual Workers) – 519k
under 
Adult and Older People –
713k under 
Adult and Older People –
519k under 
overtime spend to cover the
Scheduling Assistant vacancies
in Homecare 
This is a result of vacancies
which are being actively
recruited. 
This is a result of vacancies
which are being actively
recruited. 
Transport and
Plant 
173k under Fleet Service Charges – 125k under Adult and Older People –
125k under
The is due to funding set aside to
replace Home Care fleet which
are in the process of being
procured. 
Administration (109k) over Legal Expenses – (79k) over Adult and Older People –
(79k) over
This is due an increase in legal  
costs in relation to Adults with 
incapacity and guardianship 
orders. 
Payment to Other
Bodies 
(77k) over Payment to Private Individuals – 347k
under 
Children and Family –
120k under 
Adult and Older People –
227k under 
There has been a reduction in the
number of supported carers and
use of the shared care scheme.
However, work has been
undertaken to attract new carers
in these areas. 
The reflects the current demand
for Direct Payments (DP). 
219

Page 220

Subjective Head Variance Subjective line Service / amount Explanation
Payment to Other
Bodies (cont.)
Social Work – Foster Parents – (150k)
over 
Social Work – Adoption Allowance-
(120k) over 
Children and Family –
(304k) over 
Children and Family –
(120k) over 
This recurring overspend is
attributable to the requirement to
purchase external foster
placements. 
This overspend relates to the
number of adoptive carers being
paid an ongoing adoption
allowance. It also relates to
interagency adoption payments
where carers have been
identified out with South
Lanarkshire. 
Payment to
Contractors
(2,641k) over Payment to Private Contractors –
Payment to Col Org Care Element–
(1,345k) over 
CET Allocation – Home Care – (1,270k)
over 
Daycare – (90k) over 
Home Support – 64k under 
Children and Family – 
(1,345k) over 
Adult and Older People -
(1,270k) over 
Adult and Older People -
(90k) over 
Adult and Older People -
(64k under 
This overspend reflects the
current commitment for children
in external residential care. 
There are ongoing management
actions and service
improvements to decrease spend
in this area. 
This reflects the current demand
for the external homecare
service. 
This reflects the current demand
for day opportunities. 
This reflects the current demand
for the external home support
service.
220

Page 221

* The underlined variances represent new variances since the last report. 
Subjective Head Variance Subjective line Service / amount Explanation
Income  359k under Fees and Charges – General - 369k
under
Adult and Older People –
380k under
The projected under recovery in
income is based on current
occupancy levels and the service
users assessed ability to
contribute towards their care
costs.
221

Page 222

South Lanarkshire Council
Revised Period 4 Period 4 Period 4
Social Work Resource - Total Annual  Actual Forecast Forecast
Budget to Date (Projected Variance
Expenditure / Income Variance Trends 2025/2026 25/26 Outturn)
EMPLOYEE COSTS
APT&C BASIC 7,074 1,580 6,687 387
APT&C OVERTIME 0 42 9 (9)
APT&C SUPERANNUATION 1,203 254 1,136 67
APT&C NIC 739 190 694 45
SOCIAL WORKERS BASIC GRADE BASIC 15,757 3,606 14,352 1,405
SOCIAL WORKERS BASIC GRADE OVERTIME 60 31 60 0
SOCIAL WORKERS BASIC GRADE SUPERANNUATION 2,733 570 2,477 256
SOCIAL WORKERS BASIC GRADE NIC 2,068 480 1,896 172
MAN/SPEC/FWORK BASIC 27,691 7,004 27,996 (305)
MAN/SPEC/FWORK OVERTIME 44 96 157 (113)
MAN/SPEC/FWORK SUPERANNUATION 4,713 1,090 4,768 (55)
MAN/SPEC/FWORK NIC 3,533 931 3,575 (42)
CARE STAFF BASIC 18,145 4,273 17,523 622
CARE STAFF OVERTIME 533 206 624 (91)
CARE STAFF SUPERANNUATION 3,055 668 2,939 116
CARE STAFF NIC 2,287 559 2,220 67
INSTRUCTORS - SOCIAL WORK BASIC 1,692 416 1,692 0
INSTRUCTORS - SOCIAL WORK SUPERANNUATION 288 67 288 0
INSTRUCTORS - SOCIAL WORK NIC 204 52 204 0
MANUAL WORKERS BASIC 31,110 7,709 30,840 270
MANUAL WORKERS OVERTIME 853 304 853 0
MANUAL WORKERS SUPERANNUATION 5,371 1,214 5,142 229
MANUAL WORKERS NIC 3,999 1,015 3,979 20
TRAVEL AND SUBSISTANCE 393 70 393 0
OTHER EMPLOYEE COSTS 1,206 38 1,206 0
PENSION INCREASES 328 74 328 0
STRAIN ON THE FUND 0 2 0 0
EMPLOYEE COSTS 135,079 32,541 132,038 3,041
PROPERTY COSTS
RATES 358 0 358 0
SCOTTISH WATER - UNMETERED CHARGES 1 0 1 0
SCOTTISH WATER - METERED CHARGES 175 37 175 0
RENT 608 119 608 0
PROPERTY INSURANCE 292 0 292 0
SECURITY COSTS 2 3 2 0
REPAIRS & MAINTENANCE - INTERNAL CONTRACTOR 24 9 24 0
REPAIRS & MAINTENANCE - EXTERNAL CONTRACTOR 31 13 31 0
ELECTRICAL HEATING MAINTENANCE 0 4 0 0
ELECTRICITY  - CONTRACT 672 54 672 0
GAS 476 52 476 0
FIXTURE & FITTINGS 32 5 32 0
JANITOR SERVICE 0 2 0 0
CLEANING CONTRACT 388 384 388 0
CLEANING AND JANITORIAL SUPPLIES AND EQUIPMENT 117 24 117 0
HEALTH & HYGIENE MATERIALS 86 28 86 0
AKINDOAK CLEANING 9 1 9 0
REFUSE UPLIFT 39 5 39 0
REMOVAL & STORAGE COSTS 2 1 2 0
OTHER PROPERTY COSTS 178 76 178 0
PROPERTY COSTS 3,490 817 3,490 0
222

Page 223

South Lanarkshire Council
Revised Period 4 Period 4 Period 4
Social Work Resource - Total Annual  Actual Forecast Forecast
Budget to Date (Projected Variance
Expenditure / Income Variance Trends 2025/2026 25/26 Outturn)
SUPPLIES AND SERVICES
COMPUTER EQUIPMENT PURCHASE 830 397 857 (27)
COMPUTER EQUIPMENT MAINTENANCE 27 0 27 0
I.T. EQUIPMENT MAINT-CONTRACT 161 0 161 0
I.T. ELECTRONIC MESSAGING 97 0 97 0
EQUIPMENT, APPARATUS AND TOOLS 142 20 142 0
SMALL TOOLS 9 2 9 0
AIDS FOR CLIENTS 962 90 962 0
ADAPTATIONS FOR CLIENTS 964 78 964 0
SUPPLIES FOR CLIENTS 353 85 353 0
FURNITURE - OFFICE 9 12 10 (1)
FURNITURE - GENERAL 0 2 0 0
FURNISHINGS (INCL. CROCKERY & LINEN) 28 5 28 0
MATERIALS 10 0 10 0
MATERIALS, APPARATUS AND EQUIPMENT 9 8 9 0
PROVISIONS 228 71 228 0
FOOD PURCHASES WITHIN CONTRACT 457 111 457 0
BEVERAGES 51 10 51 0
SCHOOL MILK 36 9 36 0
PROTECTIVE CLOTHING & UNIFORMS 1,014 481 1,015 (1)
LAUNDRY COSTS 3 3 3 0
OTHER SUPPLIES AND SERVICES 40 5 39 1
CATERING - CONTRACT 367 351 367 0
CATERING - OUTWITH CONTRACT 21 3 21 0
ARTIST FEES/ PERFORMING ARTS 0 1 0 0
DELIVERY CHARGE 0 1 0 0
SUPPLIES AND SERVICES 5,818 1,745 5,846 (28)
TRANSPORT AND PLANT
FLEET SERVICES - VEHICLE HIRE (2) 0 0 (2)
POOL CAR CHARGES-RENTAL 164 34 162 2
POOL CAR CHARGES-FUEL 14 0 14 0
POOL CAR CHARGES-ADDITIONAL COSTS 6 8 6 0
OTHER TRANSPORT COSTS 763 106 715 48
INSURANCE 24 0 24 0
FLEET SERVICE CHARGES 3,699 472 3,574 125
HIRE OF EXTERNAL VEHICLES 7 0 7 0
HIRE OF SKIPS 0 1 0 0
EXTERNAL TRANSPORT CONTRACT 0 2 0 0
PUPIL TRANSPORT - OTHER 10 4 10 0
TRANSPORT AND PLANT 4,685 627 4,512 173
ADMINISTRATION
PRINTING AND STATIONERY 90 21 90 0
TELEPHONES 203 29 203 0
MOBILE PHONES 282 1 282 0
ADVERTISING - RECRUITMENT 4 3 4 0
ADVERTISING - OTHER 8 0 8 0
POSTAGES/COURIERS 54 18 54 0
SMS MESSAGING 2 0 2 0
MEMBERSHIP FEES/SUBSCRIPTIONS 76 50 76 0
INSURANCE 27 0 27 0
MEDICAL COSTS 34 25 64 (30)
LEGAL EXPENSES 405 143 484 (79)
HOSPITALITY / CIVIC RECOGNITION 2 2 2 0
PAYPOINT AGENCY FEES 0 1 0 0
OTHER ADMIN COSTS 5 0 5 0
CONFERENCES - OFFICIALS (incl associated costs) 14 0 14 0
TRAINING 50 30 50 0
INTERNAL SUPPORT SERVICES ALLOWANCES 410 0 410 0
ADMINISTRATION 1,666 323 1,775 (109)
223

Page 224

South Lanarkshire Council
Revised Period 4 Period 4 Period 4
Social Work Resource - Total Annual  Actual Forecast Forecast
Budget to Date (Projected Variance
Expenditure / Income Variance Trends 2025/2026 25/26 Outturn)
PAYMENT TO OTHER BODIES
OTHER COMMITTEES OF THE AUTHORITY 91 0 91 0
OTHER LOCAL AUTHORITIES 25 0 25 0
GRANTS TO VOLUNTARY ORGANISATIONS 23 14 23 0
PAYMENTS TO VOLUNTARY ORGANISATIONS 1,833 591 1,833 0
PAYMENTS TO OTHER BODIES 1,193 225 1,193 0
PAYMENTS TO HEALTH BOARD 1,471 0 1,471 0
PRIVATE INDIVIDUALS - GENERAL 975 158 628 347
SOCIAL WORK - FOSTER PARENTS 6,730 1,646 7,034 (304)
SOCIAL WORK - FOSTER PARENTS 94 17 94 0
SOCIAL WORK - ADOPTION ALLOWANCES 650 369 770 (120)
DIRECT PAYMENTS 11,757 2,986 11,757 0
PAYMENT TO OTHER BODIES 24,842 6,006 24,919 (77)
PAYMENT TO CONTRACTORS
PAYMENT TO LOCAL AUTHORITY 1 0 1 0
PAYMENT TO PRIVATE CONTRACTOR 621 0 621 0
PAYMENT TO PRIVATE CONTRACTOR - PAYMENT TO COL ORGS - CARE ELEMENT 86,259 21,017 87,604 (1,345)
PAYMENT TO PRIVATE CONTRACTOR - CET ALLOCATION - HOME CARE 36,284 8,375 37,554 (1,270)
PAYMENT TO PRIVATE CONTRACTOR - SECURE ACCOMODATION 788 117 788 0
PAYMENT TO PRIVATE CONTRACTOR - RESPITE 2,163 165 2,163 0
PAYMENT TO PRIVATE CONTRACTOR - CARE COMMISSION COSTS 0 3 0 0
PAYMENT TO PRIVATE CONTRACTOR - DAY CARE 1,610 370 1,700 (90)
PAYMENT TO PRIVATE CONTRACTOR - HOME SUPPORT 27,812 6,496 27,748 64
PAYMENT TO PRIVATE CONTRACTOR - EMPLOYMENT TRAINING 59 13 59 0
PAYMENT TO PRIVATE CONTRACTOR - HOSPITAL DISCHARGE 1,980 111 1,980 0
PAYMENT TO PRIVATE CONTRACTOR - OUT OF SCHOOL SERVICE 23 1 23 0
PAYMENT TO PRIVATE CONTRACTOR - P.A (COLLEGE) 394 91 394 0
PAYMENT TO PRIVATE CONTRACTOR - GROUPWORK/ SOCIAL SUPPORT 2,083 485 2,083 0
PAYMENT TO PRIVATE CONTRACTOR - CARER RESPITE 793 173 793 0
PAYMENT TO PRIVATE CONTRACTOR - COMMUNITY OUTREACH 429 26 429 0
PAYMENT TO PRIVATE CONTRACTOR - CONTEXTUAL SUPPORT 395 10 395 0
PAYMENT TO EXTERNAL CONSULTANTS / PROFESSIONAL SERVICES 144 10 144 0
PAYMENT TO CONTRACTORS 161,838 37,463 164,479 (2,641)
TRANSFER PAYMENTS
DIRECT ASSISTANCE TO PERSONS 4,799 1,630 4,799 0
SECTION PAYMENTS 34 14 34 0
TRANSFER PAYMENTS 4,833 1,644 4,833 0
FINANCING CHARGES
LEASING CHARGES - OPERATIONAL (1) 0 (1) 0
I.T. EQUIPMENT LEASING - CONTRACT 402 12 402 0
FINANCING CHARGES 401 12 401 0
TOTAL EXPENDITURE 342,652 81,178 342,293 359
224

Page 225

South Lanarkshire Council
Revised Period 4 Period 4 Period 4
Social Work Resource - Total Annual  Actual Forecast Forecast
Budget to Date (Projected Variance
Expenditure / Income Variance Trends 2025/2026 25/26 Outturn)
INCOME
NON RELEVANT GOVERNMENT GRANT (9,484) (1,700) (9,484) 0
RESOURCE TRANSFER INCOME FROM (26,300) (6,575) (26,300) 0
CONTRIBUTIONS FROM OTHER BODIES (966) (470) (966) 0
SALES - SALE OF MEALS (29) (11) (29) 0
FEES AND CHARGES - GENERAL (6,931) (3,208) (6,562) (369)
FEES AND CHARGES - OTHER LOCAL AUTHORITIES (493) (20) (493) 0
CHARGES TO HEALTH BOARDS (26,822) (13) (26,822) 0
FEES AND CHARGES - DEPARTMENTS (218) 0 (218) 0
RENTAL INCOME (45) (12) (45) 0
OTHER INCOME (135) (68) (135) 0
ACCOMMODATION INCOME FROM USERS (400) 0 (410) 10
INCOME (71,823) (12,077) (71,464) (359)
NET EXPENDITURE 270,829 69,101 270,829 0
225

Page 226

226