Council Offices, Almada Street        
Hamilton, ML3 0AA 
Tuesday, 21 February 2023 
Dear Councillor 
Executive Committee 
The Members listed below are requested to attend a meeting of the above Committee to be
held as follows:- 
Date:  Wednesday, 01 March 2023
Time:  10:00
Venue: Hybrid - Council Chamber, Council Offices, Almada Street, Hamilton,
ML3 0AA 
The business to be considered at the meeting is listed overleaf. 
Yours sincerely 
Cleland Sneddon
Chief Executive 
Members 
Joe Fagan (Chair/ex officio), Gerry Convery (Depute Chair), Alex Allison, John Anderson, Robert
Brown, Andy Carmichael, Maureen Chalmers, Ross Clark, Margaret Cooper, Andrea Cowan,
Maureen Devlin, Gladys Ferguson-Miller, Mark Horsham, Gavin Keatt, Eileen Logan, Katy Loudon,
Hugh Macdonald, Ian McAllan, Catherine McClymont, Kenny McCreary, Lesley McDonald, Mark
McGeever, Davie McLachlan, Richard Nelson, Mo Razzaq, Kirsten Robb, John Ross, David
Shearer, Margaret B Walker 
Substitutes
John Bradley, Walter Brogan, Poppy Corbett, Margaret Cowie, Graeme Horne, Martin Hose, Susan
Kerr, Ross Lambie, Elaine McDougall, Norman Rae, Dr Ali Salamati, Graham Scott, David Watson 
1

Page 2

BUSINESS 
1 Declaration of Interests 
2 Minutes of Previous Meeting
Minutes of the meeting of the Executive Committee held on 1 February 2023
submitted for approval as a correct record.  (Copy attached) 
5 - 12 
Monitoring Item(s) 
3 Revenue Budget Monitoring for Period 11 - 1 April 2022 to 27 January 2023
and Probable Outturn
Report dated 15 February 2023 by the Executive Director (Finance and
Corporate Resources).  (Copy attached) 
13 - 18 
4 Capital Programme 2022/2023 Update and Monitoring for Period 11 – 1
April 2022 to 27 January 2023
Report dated 8 February 2023 by the Executive Director (Finance and Corporate
Resources).  (Copy attached) 
19 - 28 
5 Additional Funding from Scottish Government and Other External Sources
Report dated 9 February 2023 by the Executive Director (Finance and Corporate
Resources).  (Copy attached) 
29 - 32 
Item(s) for Decision 
6 Proposals to Extend, Upgrade and Modernise Our Lady of Lourdes
Primary School, East Kilbride
Report dated 16 February 2023 by the Executive Director (Education
Resources).  (Copy attached) 
33 - 38 
7 Family Support Strategy and Whole Family Wellbeing Funding
Joint report dated 28 December 2022 by the Director, Health and Social Care
and Executive Directors (Education Resources) and (Finance and Corporate
Resources).  (Copy attached) 
39 - 46 
8 Records Management Policy
Report dated 13 February 2023 by the Executive Director (Finance and
Corporate Resources).  (Copy attached) 
47 - 62 
9 Retention and Disposal Policy
Report dated 13 February 2023 by the Executive Director (Finance and
Corporate Resources).  (Copy attached) 
63 - 74 
10  King Charles III Coronation
Report dated 3 February 2023 by the Executive Director (Finance and Corporate
Resources).  (Copy attached) 
75 - 76 
11  Coronation of King Charles III
Report dated 16 February 2023 by the Chief Executive.  (Copy attached) 
77 - 80 
12  Recommendation Referred by Finance and Corporate Resources
Committee
Report dated 15 February 2023 by the Chief Executive.  (Copy attached) 
81 - 84 
2

Page 3

Item(s) for Noting 
13  South Lanarkshire Integration Joint Board Annual Performance Report
2021/2022
Report dated 20 January 2023 by the Director, Health and Social Care.  (Copy
attached) 
85 - 108 
14  Representation on Recruitment Committee
Report dated 9 February 2023 by the Executive Director (Finance and Corporate
Resources).  (Copy attached) 
109 - 110 
Urgent Business 
15  Urgent Business
Any other items of business which the Chair decides are urgent. 
For further information, please contact:-
Clerk Name: Pauline MacRae
Clerk Telephone: 07385 370044
Clerk Email: pauline.macrae@southlanarkshire.gov.uk 
3

Page 4

4

Page 5

EXECUTIVE COMMITTEE 
Minutes of meeting held via Confero and in the Council Chamber, Council Offices, Almada Street,
Hamilton on 1 February 2023 
Chair:
Councillor Joe Fagan (ex officio) 
Councillors Present:
Councillor Alex Allison, Councillor John Anderson, Councillor Robert Brown, Councillor Andy
Carmichael, Councillor Maureen Chalmers, Councillor Ross Clark, Councillor Gerry Convery
(Depute), Councillor Margaret Cooper, Councillor Andrea Cowan, Councillor Margaret Cowie
(substitute for Councillor Gavin Keatt), Councillor Maureen Devlin, Councillor Gladys Ferguson-Miller,
Councillor Mark Horsham, Councillor Susan Kerr (substitute for Councillor Catherine McClymont),
Councillor Eileen Logan, Councillor Katy Loudon, Councillor Hugh Macdonald, Councillor Ian
McAllan, Councillor Kenny McCreary, Councillor Lesley McDonald, Councillor Mark McGeever,
Councillor Davie McLachlan, Councillor Richard Nelson, Councillor Mo Razzaq, Councillor Kirsten
Robb, Councillor Dr Ali Salamati (substitute for Councillor John Ross), Councillor David Shearer,
Councillor Margaret B Walker 
Councillors' Apologies:
Councillor Gavin Keatt, Councillor Catherine McClymont, Councillor John Ross 
Attending:
Chief Executive’s Service
C Sneddon, Chief Executive
Community and Enterprise Resources
D Booth, Executive Director
Education Resources
T McDaid, Executive Director
Finance and Corporate Resources
H Goodwin, Finance Manager; P Manning, Executive Director; G McCann, Head of Administration
and Legal Services; P MacRae, Administration Adviser; K McLeod, Administration Assistant; K
McVeigh, Head of Personnel Services; S Terry, Public Relations Officer 
Housing and Technical Resources
S Gibson, Executive Director; C Mitchell, Strategy and Support Manager
Health and Social Care/Social Work Resources
S Sengupta, Director, Health and Social Care 
1 Declaration of Interests 
No interests were declared. 
2 Minutes of Previous Meeting 
The minutes of the meeting of the Executive Committee held on 30 November 2022 were
submitted for approval as a correct record. 
The Committee decided: that the minutes be approved as a correct record.  
2
5

Page 6

3 Revenue Budget Monitoring for Period 10 - 1 April to 29 December 2022 
A report dated 16 January 2023 by the Executive Director (Finance and Corporate Resources)
was submitted on the overall financial position of the Council’s General Fund Revenue Account
and Housing Revenue Account for the period 1 April to 29 December 2022. 
The report and associated appendices:- 
 summarised the 2022/2023 probable outturn position for the Council’s General Fund
Revenue Account to 31 March 2023, including details of proposed transfers to reserves
 provided details of the position on the General Fund Account and the Housing Revenue
Account for the period 1 April to 29 December 2022 respectively
 detailed anticipated spend for the current year
 proposed funds to be transferred to reserves for future commitments required in the next
financial year
 detailed the position after all transfers to reserves for known commitments
 provided the Housing Revenue Account position 
The final outturn position, after transfers to reserves, resulted in an underspend of £4.696 million. 
This included new proposed transfers to reserves totalling £17.195 million as well as previously
approved transfers of £17.420 million arising from the underspend in Loan Charges due to the
timing of borrowing, increased deposit interest and the Loans Fund Review.  It was proposed that
the underspend of £4.696 million be considered to support the 2023/2024 Budget Strategy. 
The overall Resource position, which was a combined overspend of £0.335 million, included
transfers to reserves totalling £8.405 million.  It also included a break even position for Social
Work Resources.  In relation to Adults and Older People, the position included a £1.423 million
commitment in respect of the element of the budget delegated to the Integration Joint Board (IJB). 
It was proposed that the IJB retain this non-recurring underspend in its reserves earmarked for
future care costs. 
There was a further underspend of £5.635 million relating to core Council funding passed to the
IJB.  In terms of the IJB financial regulations which entitled the Council to adjust its contributions
in respect of such unplanned underspends, it was proposed that the underspend be retained by
the Council to help cover the Children and Families’ budget pressures into 2023/2024. 
The budget for Corporate Items assumed a transfer from reserves of £5.700 million.  This reflected
the Council’s contribution to the increased pay award for 2022/2023.  It was proposed that this be
funded by the retrospective benefit released by implementing new guidance on Accounting for
Service Concessions. 
At 29 December 2022, the figures showed the position on the General Fund Revenue Account
after transfers to reserves, as a net underspend of £0.092 million.  At 29 December 2022, the
Housing Revenue Account showed a breakeven position and the forecast to 31 March 2023 on
the Housing Revenue Account was also a breakeven position. 
The Committee decided: 
(1) that, including Resources, Corporate Items and Council Tax, and the proposed transfer to
reserves, the Council’s outturn underspend of £4.696 million, as detailed in section 4.2 of
the report, be noted; 
(2) that the proposed transfers to reserves totalling £17.195 million, as detailed in section 4.2 of
the report, be approved;  
6

Page 7

(3) that the non-recurring underspend of £1.423 million in the delegated budget to the IJB be
held in its reserves for use in future years, as detailed in section 4.6 of the report; 
(4) that the proposal to include, within the transfer to reserves, the overfunding of £5.635 million
in the budget delegated to the IJB which would be retained by the Council to assist in
managing pressures in Children and Families, as detailed in section 4.7 of the report, be
approved; 
(5) that £5.7 million of the retrospective benefit released by the implementation of the guidance
on Accounting for Service Concessions be used to support the increased 2022/2023 Pay
Award, as detailed in section 4.10 of the report; 
(6) that the outturn underspend of £4.696 be transferred to reserves to assist in the 2023/2024
Budget Strategy as detailed in section 4.16 of the report; 
(7) that the underspend of £0.092 million on the General Fund Revenue Account at 29
December 2022, as detailed in section 5.1 of the report, be noted; and 
(8) that the breakeven position on the Housing Revenue Account at 4 November 2022, as
detailed in section 6.1 of the report, and the forecast to 31 March 2023 of breakeven, as
detailed in section 6.2 of the report, be noted. 
[Reference:  Minutes of 30 November 2022 (Paragraph 3)] 
4 Capital Programme 2022/2023 Update and Monitoring for Period 10 – 1 April 2022
to 29 December 2022 
A report dated 11 January 2023 by the Executive Director (Finance and Corporate Resources)
was submitted on progress of the General Fund Capital Programme and the Housing Capital
Programme for the period 1 April to 29 December 2022. 
At its meeting on 30 November 2022, the Committee had approved a General Fund Capital
Programme for 2022/2023 amounting to £78.272 million.  The total programme of £78.272 million
included proposed new adjustments totalling £0.531 million and included additional funding for
new projects.  Due to the timing of project spend, it was anticipated that this funding would move
into the 2023/2024 budget and the net impact on the 2022/2023 Capital Programme was,
therefore, nil.  Details of the proposed adjustments were provided in Appendix 1 of the report. 
In December 2022, the Scottish Government increased the Council’s General Capital Grant
allocation by £0.202 million, resulting in a revised allocation of £32.074 million.  In view of the late
notification of the additional funding, any new projects were unlikely to be designed and completed
prior to the end of the current financial year.  Consequently, the additional allocation would be
used to fund the existing capital programme and reduce the Council’s level of borrowing. 
Current estimates from Resources suggested an outturn of £73 million in 2022/2023.  Against the
revised budget of £78.272 million, this outturn meant a net underspend across Resources of £5.3
million.  This comprised project underspend totalling £9.7 million, offset by projects with greater
than anticipated spend of £4.4 million. 
At 29 December 2022, £37.238 million had been spent on the General Fund Capital Programme,
an overspend of £1.189 million, and actual funding received to 29 December 2022 totalled
£60.718 million.  The programme spend and funding for the General Fund for the period was
detailed in appendices 2 and 3 of the report.  
7

Page 8

A list of the main projects with anticipated underspends, which were responsible for the overall
underspend of £9.7 million and which would complete in 2023/2024, together with anticipated
completion dates, was provided in Appendix 4 of the report. 
The Housing Capital Programme 2022/2023, approved by the Executive Committee at its meeting
on 24 August 2022, totalled £66.361 million.  Details of the position of the programme at 29
December 2022 were provided in Appendix 5 of the report.   
At 29 December 2022, expenditure on the Housing Capital Programme amounted to £40.525
million and actual funding received to 29 December 2022 totalled £40.525 million. 
The Committee decided: 
(1) that the Period 10 position, as at 29 December 2022, of the General Fund Capital
Programme, as detailed in appendices 1 to 4 of the report, and the Housing Capital
Programme, as detailed in Appendix 5 of the report, be noted; 
(2) that the adjustments to the General Fund programme, as detailed in Sections 4.2 and
Appendix 1 of the report, be approved; and 
(3) that the revised programmes be monitored by the Financial Resources Scrutiny Forum. 
[Reference:  Minutes of 24 August 2022 (Paragraph 4) and 30 November 2022 (Paragraph 4)] 
5 Additional Funding from Scottish Government and Other External Sources 
A report dated 9 January 2023 by the Executive Director (Finance and Corporate Resources) was
submitted on additional funding, totalling £4.057 million, which had been made available to the
Council by the Scottish Government and other external sources. 
The funding had been allocated as follows:- 
Revenue Funding 
Resource 2022/2023 
(£m) 
Education 1.875 
Finance and Corporate 1.980 
Total 3.855 
Capital Funding  
2022/2023 
(£m) 
General Capital Grant 0.202 
Total 0.202 
Overall Total 4.057 
Councillor Brown expressed disappointment that the Council had been unsuccessful in obtaining
funding from the UK Government’s Levelling Up Fund in respect of the Phase 2 bids for:- 
 Clydesdale Way
 Electric Vehicle Charging Points
 Decontamination Works at Shawfield, Rutherglen  
8

Page 9

He cited the bid for decontamination works at Shawfield as particularly suitable in terms of the
funding criteria and asked that a report be submitted to a future meeting of the appropriate
committee on the background to the recent fund bids and the implications of the outcome for the
Council. 
Officers responded to a number of questions in relation to the bids and advised that:- 
 the submitted bids met the technical requirements in relation to the funding
 feedback had not yet been received from the UK government as to why the bids had been
unsuccessful
 preparation costs in relation to the bids involved officer time which would require to be
estimated
 information in relation to Phase 3 of the Levelling Up Fund was anticipated in the spring of
the year
 a report on the matter would be submitted to a future meeting of the relevant committee 
The Committee decided: that the report be noted. 
[Reference: Minutes of 30 November 2022 (Paragraph 5)] 
6 Developing an Age Friendly South Lanarkshire 
A report dated 11 January 2023 by the Executive Director (Finance and Corporate Resources)
was submitted on proposals to develop an Age Friendly South Lanarkshire. 
An Age Friendly Community was one in which people of all ages could participate in activities and
where everyone was treated with respect, regardless of their age.  Age Friendly Communities:- 
 made it easier for older people to stay connected to others
 helped people stay healthy and active in later years
 provided appropriate support to those who could no longer look after themselves 
Details were given on:- 
 the stages required to achieve Age Friendly Community status
 the role of the Council in supporting this development and actions required should it wish to
progress the initiative in South Lanarkshire 
 the work already undertaken by Seniors Together in South Lanarkshire on this programme
and connections made with officers in other Age Friendly Communities and supporting UK
organisations 
It was considered that a strategic plan was required where all stakeholders developed a shared
vision to determine priorities for action and to plan and resource the achievement of age friendly
outcomes in South Lanarkshire.  The Community Planning Partnership had been identified as the
appropriate group to drive forward the delivery of an Age Friendly Community.  Work undertaken
by Seniors Together would assist in the development of a strategic plan and it was proposed that
the views of older people be represented on the Community Planning Partnership, through
Seniors Together. 
To progress the initiative, it was proposed that the Council:- 
 send a letter of commitment to the World Health Organisation from the Leader of the Council  
9

Page 10

 form an Action Planning Group, supported by Seniors Together and comprising
representatives of the Community Planning Partnership, to develop tasks and actions in
relation to the 8 domains, as detailed in the report, which made an Age Friendly Community
 report on progress to the Community Planning Partnership 
Officers responded to members’ questions on various aspects of the report and undertook to
circulate further information on Age Friendly Communities to elected members. 
The Committee decided: 
(1) that the Council make a formal written commitment to establishing South Lanarkshire as an
Age Friendly Community – ‘a great place to grow older’; 
(2) that the Council work with interested partners to develop an Age Friendly action plan; and 
(3) that the voice of older people be represented on the Community Planning Partnership,
through Seniors Together. 
7 Fair Work First Statement 
A report dated 23 December 2022 by the Executive Director (Finance and Corporate Resources)
was submitted on the Council’s Fair Work First Statement. 
On 6 December 2022, the Scottish Government announced that organisations applying for public
sector grants would be required to pay at least the real Living Wage and provide appropriate
channels for effective workers’ voices by July 2023. 
The requirement for organisations to have a public statement on supporting the advancement of
Fair Work First criteria now featured in Scottish Government grant application conditions and the
condition also applied to councils applying for grants.  The Council met the Fair Work First criteria
as an organisation and publishing a statement to that effect on the Council’s website would
demonstrate that in grant application processes.  The Fair Work First Statement, attached as
Appendix 1 to the report, also included reference to procurement and grant awards in relation to
the Fair Work First criteria as the Council had a role in both those processes. 
The Committee decided: 
(1) that the report be noted: and 
(2) that the statement, attached at Appendix 1 to the report, be approved for publication on the
Council’s website. 
8 Land and Property Transfers and Disposals 
A report dated 29 December 2022 by the Executive Director (Housing and Technical Resources)
was submitted on proposed actions in respect of land and property transactions. 
The recommendations had been made in terms of agreed procedures for dealing with surplus
land and property. 
The Committee decided: that the land detailed in appendices A and B to the report be
declared surplus to Council requirements.  
10

Page 11

9 External Representation on the Education Resources Committee - Update 
A joint report dated 4 January 2023 by the Executive Directors (Education Resources) and
(Finance and Corporate Resources) was submitted providing an update on the arrangements for
the appointment of representatives other than councillors to serve on the Education Resources
Committee. 
At its meeting on 29 June 2022, the Committee agreed that the election and selection procedures
to obtain specified categories of religious and parent/carer representation on the Education
Resources Committee be approved. 
In respect of teacher representation, all teachers permanently employed in educational
establishments under the management of the Council and registered with the General Teaching
Council were invited to apply to serve as a teacher representative on the Education Resources
Committee, by the closing date of 13 October 2022. 
At the close of nominations, 2 applications had been received for 2 available places.  On that
basis, it was proposed that the following 2 applicants be confirmed as the new teacher
representatives on the Education Resources Committee:- 
 Jennifer Gaffney, St Andrew’s and St Bride’s High School, East Kilbride
 Joan Lennon, Our Lady and St Anne’s Primary School, Hamilton 
Details were also provided on progress in appointing 2 new Parent Council representatives and
the 1 remaining religious representative on the Education Resources Committee.  In both cases,
nominations exceeded the number of available places and arrangements would be made to
interview each nominee. 
The Committee decided: 
(1) that the appointment of Jennifer Gaffney and Joan Lennon as the new teacher
representatives on the Education Resources Committee be confirmed; and 
(2) that the progress on the appointment of the 2 new Parent Council representatives and the 1
remaining religious representative on the Education Resources Committee be noted. 
[Reference:  Minutes of 29 June 2022 (Paragraph 7)] 
10 Recommendations Referred by Housing and Technical Resources Committee 
A report dated 23 January 2023 by the Chief Executive was submitted on recommendations
referred to this Committee by the Housing and Technical Resources Committee at its meeting of
23 January 2023 (Special). 
The recommendations of the Housing and Technical Resources Committee were as follows:- 
(1) that the proposed rent increase of 3.5% to all Council houses, travelling persons’ sites,
lockups and garage sites and the revenue estimate proposals for the Housing Revenue
Account be endorsed; and 
(2) that, based on the rent increase of 3.5%, the 2023/2024 Housing Capital Programme of
£63.916 million be endorsed. 
11

Page 12

The Committee recommended to the Council: 
(1) that the proposed rent increase of 3.5% for all Council houses, Gypsy/Traveller sites,
lockups and garage sites and the revenue estimate proposals for the Housing Revenue
Account Budget 2023/2024 be approved; and 
(2) that, based on the rent increase of 3.5%, the 2023/2024 Housing Capital Programme,
totalling £63.916 million, be approved. 
[Reference: Minutes of the special meeting of the Housing and Technical Resources Committee
of 23 January 2023 (Paragraph 2)] 
11 Representation on Outside Organisations 
A report dated 5 January 2023 by the Chief Executive was submitted providing an update on the
member representation on the West of Scotland Road Safety Forum. 
At its meeting on 18 May 2022, the Council agreed its representation on certain statutory joint
boards and outside bodies.  Since that meeting:- 
 an update had been reported to the Council meeting held on 15 June 2020
 the Executive Committee, at its meeting on 29 June 2022, had authorised the Chief
Executive, in consultation with the Leaders of the relevant political groups, to confirm
nominations in respect of the remaining vacancies 
The Council was entitled to appoint 1 member and a substitute to the West of Scotland Road
Safety Forum on 1 November 2022.  Previous practice was to appoint the Chair of the Roads
Safety Forum as the Council’s representative on the West of Scotland Road Safety Forum. 
At the meeting of the Roads Safety Forum held on 1 November 2022 Councillor McLachlan was
appointed as Chair of the Forum and Councillor Cowie as Depute Chair.  As a result, in line with
normal practice, Councillor McLachlan had been appointed as the Council’s representative on the
West of Scotland Road Safety Forum with Councillor Cowie substituting as necessary. 
The Committee decided: that the report be noted. 
[Reference:  Minutes of 29 June 2022 (Paragraph 8)] 
12 Urgent Business 
There were no items of urgent business. 
12

Page 13

Report
Agenda Item 
Report to: Executive Committee
Date of Meeting: 1 March 2023
Report by: Executive Director (Finance and Corporate Resources)  
Subject: Revenue Budget Monitoring for Period 11 - 1 April 2022
to 27 January 2023 and Probable Outturn 
1. Purpose of Report
1.1. The purpose of the report is to:- 
 advise Members of the overall financial position of the Council’s General Fund
Revenue Account and Housing Revenue Account for the period 1 April 2022 to 27
January 2023, and the projection for the year to 31 March 2023
[1purpose]
2. Recommendation(s)
2.1. The Committee is asked to approve the following recommendation(s):-
[recs]
(1) that it be noted that the Council’s outturn position is break-even after Transfers
to Reserves (section 4.2)
(2) that the underspend position of £0.355 million on the General Fund Revenue
Account as at 27 January 2023, after transfers to reserves (section 5.1), be
noted; and
(3) that the breakeven position on the Housing Revenue Account at 27 January
2023 and the forecast to 31 March 2023 of breakeven (sections 6.1 and 6.2),
be noted. 
3. Background
3.1. This overview report will summarise the previously reported Probable Outturn position
for the Council’s General Fund Revenue Account to 31 March 2023 (section 4). 
Sections 5 and 6 provide the position on the General Fund Account and the Housing
Revenue Account for the current period 1 April 2022 to 27 January 2023 respectively.   
4. 2022/2023 General Services Probable Outturn 
4.1. As reported previously, the 2022/2023 probable outturn position for the General
Services presented an underspend of £4.696 million.  This underspend was after
previously approved transfers of £17.420 million earmarked for the Budget Strategy,
and new proposed transfers to reserves totalling £17.195 million.  It was proposed that
the outturn underspend of £4.696 million be transferred to reserves to assist in the
2023/2024 Budget Strategy.   
4.2. Full details of the transfers to reserves were included in the 1 February 2023 report to
the Executive Committee.  The new proposed transfers to Reserves and the use of
the £4.696 million underspend to assist in the 2023/2024 Budget Strategy, were
approved at the Executive Committee (1 February 2023).  The forecast position before
and after Transfers to Reserves is shown in appendices 1 and 2.  The position
presented in Appendix 2 includes the underspend of £4.696 million as a Transfer to
Reserves.  This results in a break-even position for the 2023/2024 Probable Outturn.
3
13

Page 14

5. 2022/2023 General Services Monitoring Position  
5.1. Financial Position as at 27 January 2023:  As at 27 January 2023, the position on
the General Services budget, after Transfers to Reserves, is an underspend of £0.355
million (Appendix 2).       
5.2. This position is in line with the forecast position for the General Fund (section 4). 
6. Housing Revenue Account Position
6.1. Financial Position as at 27 January 2023:  Appendix 3 of the report shows a break-
even position against the phased budget on the Housing Revenue Account. Levels of
rent collection are regularly monitored by the Housing Services team and appropriate
corrective action will be taken, as required.   
6.2. Probable Outturn Position:  Appendix 3 also shows the forecast position for the
financial year, being a break-even position for the Housing Revenue Account.   
7. Employee Implications
7.1. None. 
8. Financial Implications
8.1. As detailed in sections 4 to 6 of the report. 
9. Climate Change, Sustainability and Environmental Implications
9.1. There are no implications for climate change, sustainability or the environment in terms
of the information contained in this report. 
10. Other Implications
10.1. The main risk associated with the Council’s Revenue Budget is that there is an
overspend. Inflationary and budget pressures experienced this year increase the risk
of overspend, however, this is mitigated going forward through provision of additional
funds in next year’s budget strategy, and through the one-off use of reserves in the
current year.   
10.2. The actual impact will continue to be reviewed through four weekly Budget Monitoring
Meetings at which any variance is analysed. In addition, the probable outturn exercise
position in this report ensures early warning for corrective action to be taken where
appropriate.  
11. Equality Impact Assessment and Consultation Arrangements
11.1. This report does not introduce a new policy, function or strategy or recommend a
change to an existing policy, function or strategy and, therefore, no impact assessment
is required.   
11.2. There is also no requirement to undertake any consultation in terms of the information
contained in this report. 
Paul Manning
Executive Director (Finance and Corporate Resources) 
15 February 2023 
14

Page 15

Link(s) to Council Values/Priorities/Outcomes
 Accountable, effective, efficient and transparent 
Previous References
 Executive Committee, 1 February 2023 
List of Background Papers
 Financial Ledger and budget monitoring results to 27 January 2023 
Contact for Further Information
If you would like to inspect the background papers or want further information, please contact:
Lorraine O'Hagan, Finance Manager (Strategy)
Ext:  2601 (Tel:  01698 452601)
E-mail: lorraine.o'hagan@southlanarkshire.gov.uk 
15

Page 16

Appendix 1
SOUTH LANARKSHIRE COUNCIL
Revenue Budget Monitoring Report (BEFORE Transfers)
Period Ended 27 January 2023 (No.11)
Committee
Annual
Budget
Annual
Forecast
BEFORE
Transfers
Annual
Forecast
Variance
BEFORE
Transfers
(Over) /
Under
Budget
Proportion
to 27/01/23
Actual
to
Period 10
27/01/23
Variance
to
27/01/23
Departments: £m £m £m £m £m £m
Community and Enterprise Resources 129.797 128.520 1.277 97.467 96.407 1.060 under
Facilities, Waste and Grounds 75.626 73.869 1.757 58.380 56.929 1.451 under
Leisure and Culture Services 23.942 23.930 0.012 15.870 15.853 0.017 under
Planning and Regulatory Services 5.138 4.096 1.042 4.160 3.311 0.849 under
Enterprise and Sustainable Development 6.957 6.843 0.114 5.538 5.421 0.117 under
Roads, Transportation and Fleet 18.134 19.782 (1.648) 13.519 14.893 (1.374) over
Education Resources 396.815 395.315 1.500 307.068 305.799 1.269 under
Education 396.815 395.315 1.500 307.068 305.799 1.269 under
Finance and Corporate Resources 48.243 48.243 0.000 46.613 46.589 0.024 -
Finance Services - Strategy 2.129 2.141 (0.012) 2.892 2.848 0.044 under
Finance Services - Transactions 23.820 23.326 0.494 20.286 19.540 0.746 under
Audit and Compliance Services 0.376 0.376 0.000 0.525 0.528 (0.003) over
Information Technology Services 5.304 5.340 (0.036) 7.285 7.291 (0.006) over
Communications and Strategy Services 3.353 3.504 (0.151) 2.699 2.786 (0.087) over
Administration and Licensing Services 4.274 4.747 (0.473) 4.026 4.370 (0.344) over
Personnel Services 8.987 8.809 0.178 8.900 9.226 (0.326) over
Housing and Technical Resources 19.145 19.487 (0.342) 20.051 20.296 (0.245) over
Housing Services 9.830 9.830 0.000 8.098 8.098 0.000 -
Property Services 9.315 9.657 (0.342) 11.953 12.198 (0.245) over
Social Work Resources 217.057 211.422 5.635 167.600 162.752 4.848 under
Performance and Support Services 7.084 6.405 0.679 5.918 5.229 0.689 under
Children and Families 43.767 44.923 (1.156) 34.705 35.749 (1.044) over
Adults and Older People 165.086 159.451 5.635 125.628 120.803 4.825 under
Justice and Substance Misuse 1.120 0.643 0.477 1.349 0.971 0.378 under
Joint Boards 2.152 2.152 0.000 1.577 1.577 0.000 -
813.209 805.139 8.070 640.376 633.420 6.956 under
Committee
Annual
Budget
Annual
Forecast
BEFORE
Transfers
Annual
Forecast
Variance
BEFORE
Transfers
(Over) /
Under
Budget
Proportion
To 27/01/23
Actual
to
Period 10
27/01/23
Variance
to
27/01/23
£m £m £m £m £m £m
Service Departments Total 813.209 805.139 8.070 640.376 633.420 6.956 under
CFCR 0.514 0.514 0.000 0.000 0.000 0.000 -
Loan Charges 35.041 30.306 4.735 0.000 0.000 0.000 -
Corporate Items 26.583 22.011 4.572 15.113 15.081 0.032 under
Corporate Items – Strategy (Tfr to Reserves) 17.420 0.000 17.420 0.000 0.000 0.000 -
Investments – 2022/23 (Tfr to Reserves) 0.000 0.000 0.000 0.000 0.000 0.000 -
Total Expenditure 892.767 857.970 34.797 655.489 648.501 6.988 under
Council Tax 167.437 170.688 3.251 131.558 134.112 2.554 over
Less: Council Tax Reduction Scheme (23.272) (22.009) 1.263 (18.285) (17.293) 0.992 under
Net Council Tax 144.165 148.679 4.514 113.273 116.819 3.546 over
General Revenue Grant 252.792 252.792 0.000 198.622 198.622 0.000 -
Non-Domestic Rates 422.591 422.591 0.000 332.036 332.036 0.000 -
Transfer from Reserves 73.219 73.219 0.000 73.219 73.219 0.000 -
Total Income 892.767 897.281 4.514 717.150 720.696 3.546 over rec
Net Expenditure / (Income) 0.000 (39.311) 39.311 (61.661) (72.195) 10.534 under
16

Page 17

Appendix 2
SOUTH LANARKSHIRE COUNCIL
Revenue Budget Monitoring Report (AFTER Transfers)
Period Ended 27 January 2023 (No.11)
Committee
Annual
Budget
Annual
Forecast
AFTER
Transfers
Annual
Forecast
Variance
AFTER
Transfers
Budget
Proportion
to 27/01/23
Actual
to
Period 10
27/01/23
Variance
to
27/01/23
Departments: £m £m £m £m £m £m
Community and Enterprise Resources 129.797 129.790 0.007 97.467 97.482 (0.015) under
Facilities, Waste and Grounds 75.626 75.099 0.527 58.380 57.970 0.410 under
Leisure and Culture Services 23.942 23.930 0.012 15.870 15.853 0.017 under
Planning and Regulatory Services 5.138 4.096 1.042 4.160 3.311 0.849 under
Enterprise and Sustainable Development 6.957 6.843 0.114 5.538 5.421 0.117 under
Roads, Transportation and Fleet 18.134 19.822 (1.688) 13.519 14.927 (1.408) over
Education Resources 396.815 396.815 0.000 307.068 307.068 0.000 -
Education 396.815 396.815 0.000 307.068 307.068 0.000 -
Finance and Corporate Resources 48.243 48.243 0.000 46.613 46.589 0.024 -
Finance Services - Strategy 2.129 2.141 (0.012) 2.892 2.848 0.044 under
Finance Services - Transactions 23.820 23.326 0.494 20.286 19.540 0.746 under
Audit and Compliance Services 0.376 0.376 0.000 0.525 0.528 (0.003) over
Information Technology Services 5.304 5.340 (0.036) 7.285 7.291 (0.006) over
Communications and Strategy Services 3.353 3.504 (0.151) 2.699 2.786 (0.087) over
Administration and Licensing Services 4.274 4.747 (0.473) 4.026 4.370 (0.344) over
Personnel Services 8.987 8.809 0.178 8.900 9.226 (0.326) over
Housing and Technical Resources 19.145 19.487 (0.342) 20.051 20.296 (0.245) over
Housing Services 9.830 9.830 0.000 8.098 8.098 0.000 -
Property Services 9.315 9.657 (0.342) 11.953 12.198 (0.245) over
Social Work Resources 217.057 217.057 0.000 167.600 167.577 0.023 -
Performance and Support Services 7.084 6.405 0.679 5.918 5.229 0.689 under
Children and Families 43.767 44.923 (1.156) 34.705 35.749 (1.044) over
Adults and Older People 165.086 165.086 0.000 125.628 125.628 0.000 -
Justice and Substance Misuse 1.120 0.643 0.477 1.349 0.971 0.378 under
Joint Boards 2.152 2.152 0.000 1.577 1.577 0.000 -
813.209 813.544 (0.335) 640.376 640.589 (0.213) over
Committee
Annual
Budget
Annual
Forecast
AFTER
Transfers
Annual
Forecast
Variance
AFTER
Transfers
Budget
Proportion
to 27/01/23
Actual
to
Period 10
27/01/23
Variance
to
27/01/23
£m £m £m £m £m £m
Service Departments Total 813.209 813.544 (0.335) 640.376 640.589 (0.213) over
CFCR 0.514 0.514 0.000 0.000 0.000 0.000 -
Loan Charges 35.041 33.861 1.180 0.000 0.000 0.000 -
Corporate Items 26.583 24.236 2.347 15.113 15.081 0.032 -
Corporate Items – Strategy (Tfr to Reserves) 17.420 22.116 (4.696) 0.000 0.000 0.000 -
Investments – 2022/23 (Tfr to Reserves) 0.000 0.000 0.000 0.000 0.000 0.000 -
Total Expenditure 892.767 894.271 (1.504) 655.489 655.670 (0.181) over
Council Tax 167.437 169.078 1.641 131.558 132.502 0.944 over
Less: Council Tax Reduction Scheme (23.272) (23.409) (0.137) (18.285) (18.693) (0.408) over
Net Council Tax 144.165 145.669 1.504 113.273 113.809 0.536 -
General Revenue Grant 252.792 252.792 0.000 198.622 198.622 0.000 -
Non-Domestic Rates 422.591 422.591 0.000 332.036 332.036 0.000 -
Transfer from Reserves 73.219 73.219 0.000 73.219 73.219 0.000 -
Total Income 892.767 894.271 1.504 717.150 717.686 0.536 over
Net Expenditure / (Income) 0.000 0.000 0.000 (61.661) (62.016) 0.355 under
17

Page 18

Appendix 3 
SOUTH LANARKSHIRE COUNCIL 
Revenue Budget Monitoring Report 
Period Ended 27 January 2023 (No.11) 
Housing Revenue Account 
Annual
Budget 
Forecast 
for Year 
Annual
Forecast
Variance 
Budget
Proportion
to 27/01/23
Actual
to Period 10
27/01/23
Variance
to
27/01/23 
% Note 
£m £m £m  £m £m £m   
Employee Costs 14.641 14.140 0.501  11.899 11.654 0.245 under 2.1% 1
Property Costs 46.906 53.424 (6.518)  37.477 40.192 (2.715) over (7.2%) 2
Supplies & Services 0.609 1.021 (0.412)  0.439 0.451 (0.012) over (2.7%) 
Transport & Plant 0.195 0.183 0.012  0.094 0.084 0.010 under 10.6% 
Administration Costs 5.644 5.593 0.051  0.364 0.318 0.046 under 12.6% 3
Payments to Other Bodies 3.030 3.054 (0.024)  1.702 1.719 (0.017) over (1.0%) 
Payments to Contractors 0.100 0.080 0.020  0.077 0.076 1 under 1.3% 
Transfer Payments 0.000 0.000 0.000  0.000 0.000 0.000 - 0.0% 
Financing Charges 26.050 26.050 0.000  26.116 26.116 0.000 - 0.0% 
Total Controllable Expenditure 97.175 103.545 (6.370)  78.168 80.610 (2.442) over (3.1%) 
Total Controllable Income (112.000) (112.475) 0.475  (82.713) (83.052) 0.339 Over
recovered  0.4% 4
Transfer to/(from) Balance Sheet (3.500) (5.840) 2.340  (2.691) (5.064) 2.103 over
recovered 71.0% 5
Net Controllable Expenditure (18.325) (14.770) (3.555)  (7.506) (7.506) 0.000 - 0.0% 
Add: Non Controllable Budgets       
Financing Charges 18.325 14.770 (3.555)  0.000 0.000 0.000 - 0.0% 
Total Budget 0.000 0.000 0.000  (7.506) (7.506) 0.000 - 0.0% 
Variance Explanations 
1. Employee Costs
The underspend is due to higher than anticipated staff turnover. 
2. Property Costs
The net overspend reflects the current cost and volume of repairs and maintenance. 
3. Administration Costs
A large element of this underspend is due to the demand led legal expenses and the underspend reflects the current level of activity. 
4. Total Controllable Income
Rental income from council housing is higher than forecast due to favourable timing of new build and purchased units being available to rent. 
5. Transfer to (from) Balance Sheet
The net combined overspend year to date requires for a higher than budgeted level of transfer to reserves.
18

Page 19

Report
Agenda Item 
Report to: Executive Committee 
Date of Meeting: 1 March 2023
Report by: Executive Director (Finance and Corporate Resources)  
Subject: Capital Programme 2022/2023 Update and Monitoring
for Period 11 – 1 April 2022 to 27 January 2023 
1. Purpose of Report
1.1. The purpose of the report is to:- 
 update the Executive Committee of progress on the General Fund Capital
Programme and the Housing Capital Programme for the period 1 April 2022 to 27
January 2023 
2. Recommendation(s)
2.1. The Executive Committee is asked to approve the following recommendation(s):-  
(1) that the Period 11 position (ended 27 January 2023) of the General Fund
Capital Programme itemised at Appendices 1 to 4 and the Housing Capital
Programme at Appendix 5, be noted;
(2) that the adjustments to the General Fund programme listed at Sections 4.2 and
Appendix 1, be approved; and
(3) that the revised programmes be monitored by the Financial Resources Scrutiny
Forum. 
3. Background
3.1. The attached statements to this report provide a summarised monitoring position as
at 27 January 2023 (Period 11).  Spending has been split into two separate sections:- 
 General Fund Capital Programme including Education, Social Work, Roads
and Transportation and General Services (Section 4)
 Housing Capital Programme (Section 5) 
4. General Fund Capital Programme
4.1. 2022/2023 Budget:  The budget agreed at Executive Committee on 1 February 2023
was £78.272 million.  This revised programme consists of the base budget plus carry
forward projects and adjustments which have been agreed by the Executive
Committee up to and including the meeting on 1 February 2023.     
4.2. The total programme is now £78.396 million and includes new adjustments to the
programme, which are proposed in this report at Appendix 1.  These adjustments total
a net increase of £0.124 million and mainly reflect additional funding for new Roads
projects.   
4
19

Page 20

4.3. The revised Programme, including the movement from the last report, is detailed in
Appendix 2.   
4.4. Programmed funding for the year also totals £78.396 million.  The funding available to
support the programme is detailed in Appendix 3.   
4.5. 2022/2023 Outturn 
As reported last period, estimates from Resources suggest an outturn of around £73
million.  Against the revised budget of £78.396 million, this outturn means a net
underspend across Resources of £5.3 million.  This is made up of project underspends
totalling £9.7 million offset by projects with greater than anticipated spend of £4.4
million.   Work will continue in the coming weeks to monitor achievable levels of spend. 
4.6. The majority of the variance is due to the timing of spend, resulting in budget required
in 2023/2024 rather than 2022/2023.  Funding for projects remaining underspent at
the financial year-end will be carried forward to allow the projects to be completed in
2023/2024.  Again, this is a timing issue only with funding for the overall spend on
these projects already identified into next financial year. 
4.7. A list of the main projects with anticipated underspends which are responsible for the
overall underspend of £9.7 million, as detailed in section 4.5, and which will now
complete in 2023/2024 is included in Appendix 4, along with their anticipated
completion dates.   
4.8.  Period 11 Position:  The programme spend and funding for the General Fund is
included in Appendix 4.  As noted in 4.1, the total capital spending programme for the
year is £78.396 million.   
4.9.  Appendix 3 also shows budget for the period of £38.915 million and spend to the 27
January 2023 of £39.540 million, an overspend of £0.625 million.  This is mainly due
to the timing of spend in relation to the Oracle Fusion project within Finance and
Corporate Resources (£0.786 million).  This is offset by a number of smaller
underspends across the rest of the Programme.       
4.10.  Actual funding received to 27 January 2023 is £68.848 million.   
4.11. Relevant officers will continue to closely monitor the generation of all income. 
5. Housing Capital Programme
5.1. 2022/2023 Budget:  Appendix 5 summarises the position on the Housing programme
as at 27 January 2023.  The revised capital programme for the year is £66.361 million,
as approved by the Executive Committee on 24 August 2022. There are no new
adjustments proposed in this report. 
5.2. Programmed funding for the year also totals £66.361 million.  The funding sources are
also detailed in Appendix 5. 
5.3. 2022/2023 Outturn:  Current estimates from Housing and Technical Resources
suggest there will be an underspend of £4.1 million within the Housing Capital
Programme by the end of the financial year. This is due to a number of factors - as
advised last period, this is mainly due to the extreme weather experienced in
December 2022, which caused flooding damage to a number of Council properties. 
As a result, operatives from Property Services were diverted away from Capital
investment works to tackle urgent repairs.  
20

Page 21

5.4. In addition, environmental surveys on external fabric projects have required work to
be paused due to the suspected presence of bats which, in turn, has delayed owner
consultations.  There has also been reduced owner uptake for external works. The
Service has also experienced higher than normal volumes of no access for legislative
works. 
5.5. Work to monitor achievable spend will continue in the coming weeks. Funding for
projects remaining underspend at the financial year-end will be carried forward to allow
the projects to be completed in 2023/2024. 
5.6. Period 11 Position:  Budget for the period is £45.339 million and spend to 27 January
2023 amounts to £43.015 million, an underspend of £2.324 million and this mainly
reflects the issues detailed in Sections 5.3 to 5.5 above. 
5.7. As at 27 January 2023, £43.015 million of funding had been received. 
5.8. Regular monitoring of both the General Fund Programme and the Housing
Programme will be carried out in detail by the Financial Resources Scrutiny Forum
and reported on a regular basis to the Executive Committee. 
6. Employee Implications
6.1. There are no employee implications as a result of this report. 
7. Financial Implications
7.1. The financial implications are contained in sections 4 and 5 of the report for the
General Services and Housing capital programmes respectively. 
8. Climate Change, Sustainability and Environmental Implications
8.1. There are no implications for climate change, sustainability or the environment in terms
of the information contained in this report. 
9. Other Implications
9.1. The main risk associated with the Council’s Capital Programme is an overspend. 
There are detailed project management plans prepared and the risk of overspend on
each project is monitored through four weekly investment management meetings. 
9.2. The Council continues to experience material shortages, longer lead times and
extraordinary inflationary price increases and it is anticipated that this will continue to
impact the supply chain for the foreseeable future.  The impact of this will continue to
be monitored through the four weekly investment management meetings.  Further
updates will be reported in the coming months with any significant increases in
contract values being brought to members’ attention.   
10. Equality Impact Assessment and Consultation Arrangements
10.1. This report does not introduce a new policy, function or strategy or recommend a
change to existing policy, function or strategy and, therefore, no impact assessment
is required. 
10.2. There was also no requirement to undertake any consultation in terms of the
information contained in this report.  
21

Page 22

Paul Manning
Executive Director (Finance and Corporate Resources) 
8 February 2023 
Link(s) to Council Values/Priorities/Outcomes
 Accountable, effective, efficient and transparent 
Previous References
 Executive Committee, 24 August 2022
 Executive Committee, 1 February 2023 
List of Background Papers
 Capital Ledger prints to 27 January 2023 
Contact for Further Information
If you would like to inspect the background papers or want further information, please contact:
Lorraine O’Hagan, Finance Manager (Strategy)
Ext:  2601 (Tel:  01698 452601)
E-mail:  lorraine.o’hagan@southlanarkshire.gov.uk 
22

Page 23

APPENDIX 1
SOUTH LANARKSHIRE COUNCIL          
CAPITAL EXPENDITURE 2022/23
GENERAL SERVICES PROGRAMME 
FOR PERIOD 1 APRIL 2022 TO 27 JANUARY 2023 
Proposed Adjustments – Period 11 
Community and Enterprise Resources 
Cycle Shelters at Schools
Approval is sought to increase the 2022/23 Capital Programme by £0.040 million to
reflect funding awarded from Cycling Scotland. The funding has been awarded to
supply, deliver and install cycle shelters at a number of schools including: 
Lesmahagow High School, Douglas Primary School, Rigside Primary School &
Craigbank Primary School.  In addition, refurbishment works will also be
undertaken to the existing shelter at Cairns Primary School. 
£0.040m
National Strategy for 20mph
The National Strategy for 20mph aims to expand 20mph speed limits across
Scotland and will ensure all appropriate roads in built-up areas have a safer speed
limit of 20mph by 2025.  Approval is sought to increase the 2022/2023 Capital
Programme by £0.084 million to identify outcomes to assist in the further delivery of
20mph zones and limits within the South Lanarkshire area.  This project will be
funded by a contribution from Transport Scotland. 
£0.084m
Education Resources 
Woodside Primary School - Adaptations
In order to accommodate an increase in pupil numbers at Woodside Primary
School, Hamilton, approval is sought to increase the 2022/2023 Capital Programme
by £0.100 million to allow the adaptation of the general-purpose area to be
converted into two additional classrooms. 
It is proposed that funding for these adaptation works be transferred from
developers’ contributions already received for the Hamilton area.   
£0.100m 
(£0.100m)  
TOTAL ADJUSTMENTS  £0.124m   
23

Page 24

APPENDIX 2
SOUTH LANARKSHIRE COUNCIL       
CAPITAL EXPENDITURE 2022/23       
GENERAL FUND PROGRAMME 
FOR PERIOD 1 APRIL 2022 TO 27 JANUARY 2023 
£m  
Total Budget (Executive Committee – 1 February 2023) 78.272  
Proposed Adjustments – Period 11 (Section 4.2 and Appendix 1) 0.124  
Total Revised Budget (Executive Committee – 1 March 2023) 78.396   
2022/23
Budget 
Period 11
Proposed
Adjustments   
Revised
2022/23
Budget
Resource £m £m £m    
Community & Enterprise 48.320 0.124 48.444
Education 13.918 - 13.918
Finance & Corporate 3.695 - 3.695
Housing & Technical 8.436 - 8.436
Social Work 3.903 - 3.903
Other Match Funding - - -    
TOTAL CAPITAL PROGRAMME 78.272 0.124 78.396      
24

Page 25

APPENDIX 3
SOUTH LANARKSHIRE COUNCIL       
CAPITAL EXPENDITURE 2022/23       
GENERAL FUND PROGRAMME 
FOR PERIOD 1 APRIL 2022 TO 27 JANUARY 2023 
2022/23
Original
Estimate inc
C/F 
2022/23
Revised
Budget 
2022/23
Budget to
27/01/23 
2022/23
Actual to
27/01/23     
Expenditure £m £m £m £m     
General Fund Programme 95.232 78.396 38.915 39.540 
Income
2022/23
Budget
2022/23
Revised
Budget 
2022/23
Actual
To
27/01/23         
£m         £m  £m
Prudential Borrowing 55.416 30.260  30.260
Developers Contributions 6.552 0.058  0.058
Partners (Including High Blantyre Construction, SPT,
Sustrans, and CARES)
1.745 3.989  1.462
Scottish Government:     
- Capital Grant 22.424 32.074  28.287 
- Cycling, Walking and Safer Routes 2.154 2.887  1.488 
- Vacant and Derelict Land 1.820 1.228  0.728 
- Regeneration Capital Grant  1.720 1.370  0.157 
- Town Centre Regeneration Fund 0.101 0.101  0.101 
- Place Based Investment Programme 1.617 3.357  3.357 
- Electric Vehicle Charging Infrastructure 0.118 0.118  0.089 
- NSS Tec 0.000 0.040  0.040
Glasgow City Region City Deal 0.000 0.000  0.006
Capital Receipts 1.000 1.000  0.901
Specific Reserves 0.534 1.400  1.400
Revenue Contribution 0.031 0.514  0.514     
TOTAL FUNDING 95.232 78.396  68.848 
25

Page 26

APPENDIX 4
SOUTH LANARKSHIRE COUNCIL           
CAPITAL EXPENDITURE 2022/23
GENERAL FUND PROGRAMME 
FOR PERIOD 1 APRIL 2020 TO 27 JANUARY 2023 
Projects with Projected Underspends in 2022/23 
which will Carry Forward into 2023/2024
Project Name Project Type Completion Date   
Community and Enterprise Resources  
Library IT Infrastructure Upgrade Phase 2 –
Desktop Refresh 
Infrastructure Summer 2023
Phillipshill Cemetery - Extension Infrastructure March 2024
Springhall Urban Greenspace Development
(Springhall Cage) - Play Equipment
Equipment Summer 2023
Halfway Park Play Area - Redevelopment Infrastructure April 2023
Chatelherault Allotments Infrastructure March 2024
Play Parks - Various Infrastructure Throughout 2023/24
and beyond
Greenhall Replacement Bridge - Design Infrastructure March 2024
Alexander Hamilton Memorial Park Woodland
Management
Infrastructure Throughout
2023/2024
Larkhall Leisure Centre - Design
(Place Based Investment Funding)
New Build Throughout
2023/2024
Lanark Library, Lindsay Institute – Roof and
Windows
Improvements July 2023
Town Centre Regeneration Fund Regeneration Throughout 2023/24
Vacant & Derelict Land - Cuningar Loop Phase 3
Greening
Regeneration February 2024
City Deal - Calderside Academy Adaptations October 2025
City Deal - Holy Cross High Adaptations October 2025
City Deal - Lanark Road Signalisation Infrastructure December 2023
City Deal - Cathkin Bypass – Grant Payments Only Grants Throughout 2023/24
Daer Bridge Infrastructure December 2023   
Education Resources  
Castlefield Primary School Extension Extension July 2023
Crawforddyke adaptation of nursery to classrooms Adaptations June 2023
Uddingston Nursery Expansion  Adaptations August 2024
Clyde Terrace Early Years New Build November 2023
Small Scale Adaptations Adaptations Throughout 2023/24   
Finance and Corporate Resources  
Digital Tools Infrastructure Throughout 2023/24
Digital Connectivity Infrastructure Throughout 2023/24
Digital Transformation  Infrastructure Throughout 2023/24 
26

Page 27

APPENDIX 4 (continued)
SOUTH LANARKSHIRE COUNCIL           
CAPITAL EXPENDITURE 2022/23
GENERAL FUND PROGRAMME 
FOR PERIOD 1 APRIL 2020 TO 27 JANUARY 2023 
Projects with Projected Underspends in 2022/23 
which will Carry Forward into 2023/2024  
Project Name Project Type Completion Date
Housing and Technical Resources   
Prioritised Urgent Investment Refurbishment Throughout 2023/24
Principal Offices - Fabric and Service Investment Refurbishment Throughout 2023/24
Lifecycle Replacement Schools Refurbishment Throughout 2023/24
New Cross Shopping Centre - Roof Refurbishment Throughout 2023/24
Civic Centre Fabric Upgrade Refurbishment Throughout 2023/24
Communities Facilities Fund Refurbishment Throughout 2023/24
CEEF Programme Refurbishment Throughout 2023/24 
27

Page 28

APPENDIX 5
SOUTH LANARKSHIRE COUNCIL           
CAPITAL EXPENDITURE 2022/23
HOUSING PROGRAMME 
FOR PERIOD 1 APRIL 2022 TO 27 JANUARY 2023 
2022/2023
Original
Budget
2022/2023
Revised
Budget
2022/2023
Budget to
27/01/23
2022/2023 
Actual to
27/01/23 
£m £m £m £m
Expenditure 
2022/2023 Budget 
Incl. adjustment from 2021/2022 
52.230  66.361  45.339  43.015 
2022/2023
Original
Budget
2022/2023
Revised
Budget 
2022/2023
Actual to
27/01/23 
£m £m  £m
INCOME    
Capital Receipts 0.000 7.311  6.314
Capital Receipts - Land Sales 0.000 0.000  0.018
Capital Funded from Current Revenue 26.050 26.050  26.050
Prudential Borrowing 22.018 26.462  5.930
Scottish Government Specific Grant:    
- New Build 2.242 4.048  4.648
- Open Market Purchase Scheme 1.800 2.370  0.000
- Mortgage to Rent 0.120 0.120  0.055 
52.230 66.361  43.015 
28

Page 29

Report
Agenda Item 
Report to: Executive Committee
Date of Meeting: 1 March 2023
Report by: Executive Director (Finance and Corporate Resources)  
Subject: Additional Funding from Scottish Government and
Other External Sources 
1. Purpose of Report
1.1. The purpose of the report is to:- 
 advise Members of additional funding that has been made available to the Council
by the Scottish Government and other external sources since the last report to this
Committee (1 February 2023)
[1purpose]
2. Recommendation(s)
2.1. The Committee is asked to approve the following recommendation(s):
[recs]
(1) that the additional funding totalling £1.537 million, detailed in Appendix 1, be
noted. 
3. Background
3.1. The Council is periodically advised of additional funding which is made available from
the Scottish Government and other sources to enable various initiatives to be
undertaken. 
3.2. Additional funding may either be paid through the General Revenue Grant mechanism
or by the completion of appropriate grant claims. 
3.3. Details of the additional funding are attached at Appendix 1 to the report. The report
details additional funding that has been reported by Resources as part of the additional
resources notification process, as well as any additional funding that has increased
the Council’s budget by more than £0.100 million. 
4. Employee Implications
4.1. None. 
5. Financial Implications
5.1. Additional revenue funding of £1.537 million has been identified for 2022/2023.  No
additional Capital funding has been identified since the last report to Committee.  The
£1.537 million of funding is detailed in Appendix 1. 
5.2. Resource budgets will be updated to reflect this additional funding as required, and,
where appropriate, details of spending plans will be presented to Resource
Committees for approval. 
5
29

Page 30

6. Climate Change, Sustainability and Environmental Implications
6.1. There are no implications for climate change, sustainability or the environment in terms
of the information contained in this report. 
7. Other Implications
7.1. There are no other implications in terms of the information contained in this report. 
8. Equality Impact Assessment and Consultation Arrangements
8.1. This report does not introduce a new policy, function or strategy or recommend a
change to existing policy, function or strategy and, therefore, no impact assessment
is required. 
8.2. There was also no requirement to undertake any consultation in terms of the
information contained in this report. 
Paul Manning
Executive Director (Finance and Corporate Resources) 
9 February 2023 
Link(s) to Council Vision/Priorities/Outcomes
 Accountable, Effective, Efficient and Transparent 
Previous References
 Executive Committee, 1 February 2023 
List of Background Papers
 Additional Funding Reports 8 January 2023 to 8 February 2023 
Contact for Further Information
If you would like to inspect the background papers or want further information, please contact:
Lorraine O’Hagan, Finance Manager (Strategy)
Ext:  2601 (Tel:  01698 452601)
E-mail: lorraine.o’hagan@southlanarkshire.gov.uk
30

Page 31

Appendix 1 
Additional Revenue Funding 
Resource  Description  2022/2023
£m 
Total
£m 
Method
Finance and
Corporate
Discretionary Housing Payment 0.130 0.130 Scottish 
Government
Finance and
Corporate
Energy Bills Support Scheme
Alternative Funding Grant
Determination 2023 
1.407 1.407 UK
Government  
TOTAL REVENUE FUNDING 1.537 1.537 
31

Page 32

32

Page 33

Report
Agenda Item 
Report to: Executive Committee
Date of Meeting: 1 March 2023
Report by: Executive Director (Education Resources)  
Subject: Proposals to Extend, Upgrade and Modernise Our Lady
of Lourdes Primary School, East Kilbride 
1. Purpose of Report
1.1. The purpose of the report is to:- 
 update the Executive Committee on proposals to extend, upgrade and modernise
Our Lady of Lourdes Primary School, East Kilbride
[1purpose]
2. Recommendation(s)
2.1. The Committee is asked to approve the following recommendation(s):-
[recs]
(1) that the extension, upgrading and modernisation of Our Lady of Lourdes Primary
School as detailed in this Report be approved; and
(2) that approval is given to submit a Change Control to the Glasgow City Region
Deal Programme to provide part funding for the Our Lady of Lourdes Primary
School Project.
[1recs]
3. Background
3.1. In January 2004, the Council entered a 20-year lease with Investec to provide a
modular construction building to be utilised as a school building for Our Lady of Lourdes
Primary School and Nursery Class. The lease term was to end on 30 January 2024. At
its meeting on 19 January 2021, the Education Committee approved the acquisition of
the Our Lady of Lourdes building. The building has now been acquired and forms part
of the Council’s property portfolio. 
3.2 Following the acquisition, a feasibility study has been undertaken at the school to
provide solutions and costs for the following:- 
 3 additional classrooms to accommodate pupil growth predicted from several
housing developments in the school catchment area 
 a comprehensive internal and external upgrade of the existing building to include;
a new roof, over cladding of the external walls, upgrading of the ventilation and
heating systems, new windows and doors, general works to bring the school up
to the high specification of the recently completed Primary Schools Modernisation
Programme 
 works to secure the playground with a dedicated entrance walkway and security
fencing around the perimeter of the school playground
6
33

Page 34

4. Programme
4.1. The internal and external upgrading of the school building would be extremely difficult
to undertake with the school remaining within the existing building. Works would have
to be undertaken over several 6-week summer holiday periods and would take a
number of years to complete. This staggered and interrupted construction programme
would also lead to significant cost increases and the school would, essentially, be a
construction site over this period. There could also be significant impact on the
educational environment for pupils and staff if major construction works are undertaken
while the school is operational. 
4.2. The upgrading of the utilities will cause significant disruption to the ceiling and wall 
partitions which are required to be undertaken in zones. The over cladding, windows 
and door replacement and new roof all have implications for the safe movement of 
staff and pupils throughout, due to scaffolding and the Access Strategy requirements, 
and would cause significant Health and Safety issues. Timescales would also be 
significantly increased by possibly two to three years as some works could only be 
undertaken when the school is closed. Housing and Technical Resources are
concerned about the Health and Safety issues and the disruption to Education
implications of undertaking the works with the school continuing to operate on the site.   
4.3. It is, therefore, proposed to take the opportunity to decant Our Lady of Lourdes Primary
School to the new Jackton Primary School building currently being constructed close
by as part of the East Kilbride Community Growth Area. The new non-denominational
Primary School at Jackton is currently programmed to open to pupils in August 2023.
However, in the first year of operation, the new building will have sufficient
accommodation to house both schools. Pupils from Our Lady of Lourdes Primary
School would be transported to the new school for the period of the decant. It would
not be possible to decant the Our Lady of Lourdes Nursery Class to the new school
and Early Years have proposed that these children be accommodated at the new
Kilbryde Early Learning and Child Care Centre. The distance between Our Lady of
Lourdes Primary School and the proposed decant is 3 miles and the Jackton site is
within the catchment area of Our Lady of Lourdes Primary School. The distance
between Our Lady of Lourdes Primary School and Kilbryde ELCC Centre is 0.8 miles. 
4.4. Subject to the successful completion of the new Primary School at Jackton in summer 
2023 and approval of City Deal Funding, the proposal is that the decant of Our Lady of
Lourdes Primary School would commence in August 2023, for 12 months, with the
School returning to their extended and upgraded school building in August 2024.
Consultation around this will be required with both schools and their parents. 
5. Employee Implications
5.1. Education employee resources at Our Lady of Lourdes Primary School would continue
to be provided by means of existing staffing protocols and agreed management
structures. Catering and Janitorial personnel at Our Lady of Lourdes Primary School
would be redeployed within the East Kilbride area for the period of the decant but will
be given the opportunity to return to Our Lady of Lourdes Primary School at the end of
the decant period. 
6. Financial Implications
6.1.  The estimated budget requirement of the proposed extension and upgrading of Our
Lady of Lourdes Primary School is £4.754 million. These costs will be subject to
detailed design and tender.   
34

Page 35

6.2. The identified budget requirement includes the costs of transport and decanting the
pupils and staff as this is a necessary requirement to upgrade the building to South
Lanarkshire standards.   
6.3. The proposal to fund the estimated spend of £4.754 million is noted in Table 1 and
includes monies from the Glasgow City Region City Deal, Developer Contributions from
the local area and an element of the Scottish Government’s Free School Meals funding
which will be used to upgrade the kitchen facilities as part of the project. 
Table 1:  Our Lady of Lourdes Primary School – Estimated Budget and Funding 
Estimated
Budget
Required
(£m) 
Funding
Glasgow
City
Region
City Deal
(£m) 
Developer
Cont.’s
(£m)
Scottish
Govt 
Free
School
Meals
(£m)
Total
Funding
(£m)
Cost of Extension,
Upgrade and
Modernisation
4.754 1.000 3.354 0.400 4.754 
6.4. A Change Control request will need to be submitted to the Glasgow City Region City
Deal Cabinet in the first instance, requesting funding of £1 million be reallocated within
the Council’s overall City Deal Programme, which has been specifically earmarked for
this project.  If successful, submission of a Final Business Case will follow on
completion of a tender exercise.   
6.5. There is a risk that the change control request for City Deal funding is unsuccessful.
Should this be the case, the overall project plans will need to be reviewed in the context
of the funding available. 
6.6. The timing of the receipt of developer contributions is dependent on house building
activity.  Based on the most recent predictions of annual expenditure and income, and
the other Education commitments which have already been approved (Jackton Primary
School, St Andrew’s and St Bride’s High School), the developer contributions from the
East Kilbride Community Growth Area will not be available for the Our Lady of Lourdes
Primary School project until later years.  This will create a temporary shortfall in funding
commencing in financial year 2023/2024 to 2027/2028.   
6.7. In order to address this, the Council will have to borrow to manage this on a cash-flow
basis. It is estimated that this will be repaid during 2027/2028 and 2028/2029, when
the developer contributions are profiled for receipt.  The expenditure and income
profile, as well as the cost of temporary borrowing, is shown in Appendix 1.   
6.8. Based on the assumed profile of expenditure and income, Appendix 1 shows a total
cost of borrowing of £0.276 million. This will be funded by developer contributions
earmarked for Our Lady of Lourdes but not included in the capital expenditure funding
package above.   
6.9. As noted in Section 6.6, the position detailed in Appendix 1 is based on the current
assumed receipt date for developer contributions.  There is a risk that these income
streams, which are dependent on the house-building market, will be impacted by the
current economic climate and developments will not progress as planned.  There is,
35

Page 36

therefore, an additional risk in terms of when the developer contributions for the East
Kilbride Community Growth Area will be received, falling beyond current estimates of
financial year 2027/2028.  For each year of a delay, this would result in an £0.073
million additional cost of borrowing which would need to be managed within the
Education Resources Budget.   
6.10. Furthermore, given the current economic climate, there is a risk that the developments
at East Kilbride Community Growth Area do not progress at all beyond a given point.
Should this happen, the overall shortfall in funding for this project could be up to £2.420
million.  This funding gap would need to be considered in the context of future year
Capital Programmes.   
7. Climate Change, Sustainability and Environmental Implications
7.1. The extension and refurbishment design will include a range of sustainable technology
to reduce the carbon footprint of the building. The works will include
sustainable/renewable technologies relating to lighting, power, heating and energy
generation systems which will be utilised to help produce as close to a ‘carbon neutral’
building as possible, within the budget available. 
8. Other Implications
8.1. There are no other implications identified. 
9. Equality Impact Assessment and Consultation Arrangements
9.1. There was no requirement to carry out an Equality Impact Assessment in terms of this
report. 
Tony McDaid
Executive Director (Education Resources) 
16 February 2023 
Link(s) to Council Values/Priorities/Outcomes
 Accountable, effective, efficient and transparent
 Fair, open and sustainable
 Our children and young people thrive 
Previous References
 Acquisition of Our Lady of Lourdes Primary School Building
 Item 6, Education Committee 19 January 2021 
List of Background Papers
 Education Committee 19 January 2021. Acquisition of Our Lady of Lourdes Primary School
Building 
Contact for Further Information
If you would like to inspect the background papers or want further information, please contact:-
Vance Sinclair, Partnership Development Manager
Ext:  01698 452065  (Tel:  2065)
E-mail:  vance.sinclair@southlanarkshire.gov.uk
36

Page 37

Appendix 1 
Our Lady of Lourdes – Profile of Spend / Income and Cost of Borrowing  
21/22
Actual
£m 
22/23
Est.
£m 
23/24
Est.
£m 
24/25
Est.
£m 
25/26
Est.
£m 
26/27
Est.
£m 
27/28
Est
£m 
28/29
Est
£m 
Total
Est.
£m
Expenditure 0.050 0.300 3.000 1.404 - - - - 4.754
Income:         
- City Deal - - 1.000 - - -   1.000
- Developer Contributions 0.050 0.300 0.410 0.165 0.009 - 1.700 0.720 3.354
- Free School Meals   0.400      0.400
Total Income 0.050 0.300 1.810 0.165 0.009 - 1.700 0.720 4.754           
Surplus/(Deficit)  -  -  (1.190)  (1.239)  0.009  -  1.700  0.720  - 
Cumulative Surplus/(Deficit)  -  -  (1.190)  (2.429)  (2.420)  (2.420)  (0.720)  -  - 
Cost of Borrowing  -  -  0.035  0.073  0.073  0.073  0.022  -  0.276 
37

Page 38

38

Page 39

Agenda Item 
Report to: Executive Committee
Date: 1 March 2023
Report by: Director, Health and Social Care,
Executive Director (Education Resources),
Executive Director (Finance and Corporate Resources)  
Subject: Family Support Strategy and Whole Family Wellbeing
Funding 
1. Purpose of Report
1.1. The purpose of the report is to:-
[purpose]
 provide the Committee with an update on the Family Support Strategy to deliver
earlier, more preventative, strengths-based help and support to families,
preventing escalation to care and protection proceedings
 update the Committee on the proposed spend as agreed by the Children’s
Services Strategy Group for the Whole Family Wellbeing Funding £1.827m
 update the Committee in relation to the proposed spend for the £0.8m non-
recurring funding for Children and Family support as identified in budget setting
for 2022/2023
 update the Committee on national and local drivers informing the Strategy
including the #KeepthePromise Plan 21-24 known as ‘The Plan’ and funding
aligned to develop and enhance earlier help and family support services
[1purpose]
2. Recommendation(s)
2.1. The Executive Committee is asked to approve the following recommendation(s):-
[recs]
(1) that the contents of the report be noted; and
(2) that the additional posts highlighted at section 6 of the report be approved.
[1recs]
3. Background
3.1. The Promise identified the need to significantly upscale Family Support Services and
identified whole family support as a priority in The Plan 21-24.  The COVID-19
Children and Families Collective Leadership Group’s (CLG) vision and blueprint set
out a clear ambition that children and families should be able to access preventative,
needs-based support when they need it, for as long as they need it.  This embodies
the ethos of the Promise by supporting families at their time of need rather than at
crisis point, enabling them to flourish and reduce the chances of family breakdown
and of children entering the care system. 
7
39

Page 40

3.2. The overall funding package comprises funding from the Scottish Government
matched by funding from the Corra Foundation, NHS funding routed through the
Health and Social Care Partnership/ IJB and Council funding committed as part of
the 2022 budget investment. These funding streams are interlinked and can be
illustrated in the table below to demonstrate the partnership commitment to this
initiative. 
Table 1 
Funding Streams 
Whole Family Wellbeing £1,827m
Council Change Fund £0.8m
Health and Social Care Partnership (IJB) £0.570m
Corra Foundation £0.487m 
Full details of the financial implications are highlighted at section 7 of the report that
also highlight funding duration for each funding stream. 
In response to this, the Scottish Government has committed to investing £500m
Whole Family Wellbeing Funding (WFWF) over the lifetime of this Parliament to
support the whole system transformational change required to reduce the need for
crisis intervention, and to shift investment towards prevention and early intervention. 
This is a significant investment and key element of how we will collectively
#KeepthePromise by ensuring families can access the support they need, where and
when they need it. 
3.3. The year one funding is, therefore, intended to be flexible to support Children’s
Services Partnerships to assess local gaps and opportunities and to plan activity
accordingly, with a view to laying the groundwork for scaling up transformational
activity in subsequent years of the WFWF.   
The award identifies 6 spending criteria associated with the fund:- 
1. Planning and decision-making are collaborative.
2. Decisions are based on an assessment of local need.
3. In line with Children’s Rights and statutory guidance on Children’s Services
Planning, decisions are taken with appropriate consultation of children, young
people, families, and existing local providers including Third Sector
organisations not currently commissioned by statutory CSP Partners.
4. Funding is not used to replace or substitute funding for existing services but
supports investment in transformational activity and service redesign.
5. Commissioning and procurement of services supports the outcomes sought
from the funding.
6. Arrangements are in place to ensure that monitoring and reporting contributes
to evaluation of the funding and demonstrate progress against the outcomes
sought. 
3.4. The funding must not be used to support business as usual or be used to replace
funding already in the system for providing support to families.  Rather, the funding
must be used as additional resource to support transformation of the system in line
with the National Principles of Holistic Family Support and the ambition to
#KeepThePromise.  The funding awarded to South Lanarkshire is £1.827m for year
one. 
40

Page 41

3.5. In relation to the 6 criteria identified above, South Lanarkshire Children’s Services
Planning Group has undertaken several consultation events and sessions across
stakeholders and partners.  There is a confidence amongst the Partnership that we
have undertaken the use of our data, engaged with service users including children
and carers, have made the connections between other partnerships such as Alcohol
and Drug partnership (ADP) as well as the Gender Based Violence Partnership and
Community Justice Partnership.  Following all the above, a draft proposal for
commitments to the WFWF has been agreed. 
3.6. It should be noted also that as well as the funding stream identified above in relation
to the Whole Family Wellbeing Fund (£1.827m), the Council have also committed
£0.8m to support a change programme for Family Support. There is also a Corra
Foundation grant for peer support for those with Lived and Living Experience. This is
a 5 year grant of £0.487m and the Health and Social Care Partnership have also
committed £0.570m to recruit staff to support parenting initiatives and child
development and growth through play. This will include utilising evidence-based
parenting programmes such as Solihull approach to support children and families.
This will support multi-disciplinary teams in delivering a whole family wellbeing
approach and will run in parallel with the Council Change Fund (£0.8m) for Family
Support workers. 
3.7. It should also be noted that as part of the Children’s Service Plan for 2023-2026
consultation is currently underway through a Joint Strategic Needs Analysis and the
proposals for the early intervention and prevention initiatives highlighted further at
section 4 of the report have all been supported across the partnerhsip and wider
stakeholders. 
4. Proposals
4.1. Early Help Hub.  Social Work undertook a test of change in relation to managing
and responding to Requests for Assistance and referrals at the front door of the
Service.  This saw the creation of an Earlier Help Hub (EHH).  The EHH was
launched in November 2021 with the aim of providing earlier, more preventative,
strengths-based help and support to families.  The intention was that this more
preventative approach to responding to social work referrals would reduce the need
for care and protection proceedings by providing the right help, at the right time and
would also create more capacity in locality statutory teams to respond to children in
need of care and protection. 
4.2. The EHH has already started to improve the system and culture in South
Lanarkshire as it has brought partners and families together to collaboratively design
and implement an earlier, more preventative service that will align us closer to the
values of The Promise. 
4.3. The EHH has been very positively received by families and core partners as they
see it as an opportunity to receive an earlier, more preventative, strengths-based
and collaborative response from social work and wider partners. 
4.4. In a short space of time the team has developed an excellent knowledge base of
available resources and built good relationships with partners to ensure families can
get the right help, at the right time. 
4.5. The data from the first 5 months of operation indicates that only 7% of 1097 welfare
referrals were passed to child and family statutory teams and 15% who did not
require social work support were supported to engage with a third sector agency. 
41

Page 42

4.6. The proposal is to upscale this to deliver services in the localities through the current
two-family Centres based at Cambuslang and Blantyre and two new Centres in East
Kilbride and Lanark.  Premises have already been identified that are child and family
friendly.  The proposal is to use current staff and create additional staff alongside the
current Family Centre staff to deliver an Early Help Hub model in each locality. 
4.7. This will be augmented by £800,000 identified from the Council budget to recruit
Family Support Workers in the short term (two years) 
4.8. Pathfinder Programme.  As a result of discussion and collaboration between
Education, Social Work and through the Children’s Services Planning Group, the
Pathfinder Initiative was established in 3 secondary schools in Cambuslang and
Rutherglen in 2019.  The aim of the initiative was to promote effective early
intervention and to consider how best to promote resilience and support young
people on the ‘edges of care’, who experienced significant barriers to learning and
whose health and wellbeing were at risk.  This supported the agenda of the Scottish
Government’s Independent Care Review. 
4.9. A decision was made to recruit and establish a team of 6 Pathfinder officers with
Community Learning and Development background and skills.  Two of the team
would be based in each of the 3 schools in the locality and would be managed by the
South Lanarkshire Youth, Family and Community Learning Service, linking with the
local Social Work Teams through Family Support Workers to address school based
and community-based issues for young people on the edge of care.  This would
support an intervention approach which considered the whole environment of the
young person for example, home, school, and the community. 
4.10. The initiative was independently evaluated and revealed an extremely positive
evidence base for the contribution of the Pathfinder team in the three schools in
influencing improved life trajectories of vulnerable young people and also in
strengthening effective partnership working. 
4.11. It is proposed and supported by all partners to extend this initiative through the
commitment of 8 FTE Pathfinder officer posts for the duration of the WFWF. 
5. Third Sector Interface
5.1. The grant requires evidence of partnership across governance groups.  The
Children’s Services partnership jointly with the ADP submitted a bid to the Corra
Foundation for Peer Review Workers to work with the EHH and the wider partnership
as an early intervention approach and have been successful in securing £487,430 to
recruit peer support workers to work with families affected by parental substance
misuse over a 5 year period, with £97,468 being made available each year.  These
posts will be based in the EHH. 
5.2. Also, as part of the Partnership approach, Children First were commissioned to
deliver Family Group Decision Making (FGDM).  This is an evidenced based
intervention with families in crisis, with referral direct or through the EHH.   
5.3. These tests of change and pilots have now developed into a multi-agency and multi-
disciplinary partnership approach.  We have identified the need for a Parenting
Coordinator, 8 parenting Family Support Workers an administrative data post and a
Reflective Practice Coordinator to work with children and families experiencing
trauma as well as upskilling and supporting staff. There is a commitment to train
dedicated parenting support workers through the third sector to deliver early help
42

Page 43

and interventions within an emerging early intervention strategy developing for South
Lanarkshire. 
5.4. The aim of the WFWF is to create the capacity to support the development of holistic
whole family support services.  It has also set out the ambition that, by 2030, at least
5% of community-based health and social care spend should be going towards
preventative whole family support measures.   
5.5. Long term outcomes for children, young people and families through the WFWF will
contribute to:- 
 reduction in families requiring crisis intervention through a shift in investment
towards prevention and early intervention
 reduction in the number of children and young people living away from their
families, by strengthening and supporting families to stay together where children
are safe and feel loved
 increase in families taking up wider supports, such as employability support,
contributing to a reduction in children living in poverty or entering poverty across
the six priority family types as identified in the first Tackling Child Poverty Delivery
Plan
 evidence based parenting programmes based on need will improve the outcomes
for children and young people . For example, intervening early with behavioural
problems reduces negative social outcomes , including school disruption, family
stress and disfunction, drug and alcohol problems, and crime and antisocial
behaviour 
5.6. Through the Children’s Services Planning Group, the aim is to develop and establish
a whole family support service that is multi-disciplinary and multi skilled.  The Service
will be delivered within the four localities through the EHH.  Screening and direct
intervention at locality level will ensure that families are not passed between
services. 
6. Employee Implications
6.1 The following posts at 6.3 will be added to Social Work Resources and Education
Resources establishment on a permanent basis with the exception of the Service
Manager post which is 12 months fixed term. 
6.2. It is recognised that if funding does not continue (proposed for the duration of the
current Parliament) at the end of the funding the postholders will be transferred to
vacancies within the establishment.   
6.3. Whole Family Wellbeing Fund
Post
Proposed
Number of
Additional
posts
Grade SCP
Range
Hourly
Rate
Annual
Salary
Gross Cost
inc on costs
30.3%
Total
Costs
Service
Manager 1 Grade 5
Level 8
107 -
108
£36.64
-
£37.17
£66864
-
£67,832
£87,124 -
£88,384
£87,124 -
£88,384
Team
Leader 2 Grade 3
Level 8 79 -80
£24.28
-
£24.64
£44,309
-
£44,966
£57,737 -
£58,590
£115,468-
£117,180
Social
Workers 2 Grade 3
Level 4 72 -74
£22.07
-
£22.53
£40,276
-
£41,115
£52,479 -
£53,573
£104,958 -
£107,146
43

Page 44

Pathfinder
Officers 8 Grade 3
Level 2 63 -65
£19.47
-
£20.00
£35,531
-
£36,498
£46,297 -
£47,557
£370,373 -
£380,455
Parenting
Support
Workers
8
Grade 2
Level 1 -
4
34- 57
£13.25
-
£17.88
£24,180
-
£32,629
£31,506 -
£42,516
£252,052 -
£340,127
Reflective
Practice Co-
ordinator
1 Grade 3
Level 8 79 -80
£24.28
-
£24.64
£44,309
-
£44,966
£57,737 -
£58,590
£57,737 -
£58,590
Promise
Development
Worker 
2 Grade 2
Level 2 - 39 - 40
£14.15
-
£14.33
£25,822
-
£26,151
£33,647-
£34,075
£67,294 -
£68,150
Clerical
Assistant 1 Grade 1
Level 4 30 - 31
£12.59
-
£12.76
£22,975
-
£23,286
£29,937 -
£30,341
£29,937 -
£30,341  
25          
£1,084,702
-
£1,190,373 
Council Change Fund
6.4. The following posts will be added to the Social Work establishment for a fixed term of
23 months. 
Post
Proposed
Number
of
Additional
posts
Grade SCP
Range
Hourly
Rate
Annual
Salary
Gross
Cost inc
on costs
30.3%
Total
Costs
Family Support
Workers 7 Grade 2
Level 1 - 4 34- 57
£13.25
-
£17.88
£24,180
-
£32,629
£31,506
-
£42,516
£220,545 
-
£297,611 
Corra Funding
6.5. The following posts will be added to the Social Work establishment on a permanent
basis and at the end of the funding the permanent posts will be transferred to
vacancies within social care.   
Post
Proposed
Number
of
Additional
posts
Grade SCP
Range
Hourly
Rate
Annual
Salary
Gross
Cost inc
on costs
30.3%
Total
Costs
Peer Support
Workers 3.5 Grade 1
Level 4 30 - 31
£12.59
-
£12.76
£22,975
-
£23,286
£29,937
-
£30,341
£104,780 -
£106,195 
7. Financial Implications 
Whole Family Wellbeing Funding (WFWF)
7.1. The Scottish Government have provided £1.827m in 2022/2023 for the WFWF to
support local authorities to start to shift spending away from crisis intervention and
more towards preventative whole family support. 
7.2. The cost of the 25 FTE posts in table 1 is £1.190m.  Previous reports to Social Work
Committee in January 2021 and June 2021 established a Fieldwork Manger, 2 Team
Leader, 3 Family Support Worker, a Parenting Support Co-Ordinator and Team
Leader for Supported Carers with the posts being funded from the Community
44

Page 45

Mental Health & Wellbeing Fund (CMH&WF).  These posts are now being aligned to
the Whole Family Wellbeing funding at a cost of £0.437m. 
7.3. Infrastructure Costs of £0.287m are required for property costs for the new family
support hubs in East Kilbride and Lanark (£0.070m), IT costs, including phones for
new staff (£0.040m), a programme budget for Groupwork and Family support
programmes for individuals and families (£0.030m) and third sector support to
enable capacity building for early intervention parenting support (£0.147m). 
7.4. The total cost of the proposals is £1.914m, of which £1.826m is recurring.  The cost
of the Service Manager post which is fixed term for 12 months will be funded from
slippage in the funding in 23/24 due to the timescale to recruit and appoint to posts. 
Summary of costs 
New posts £1.190m
Existing posts £0.437m
Infrastructure costs £0.287m
Total costs £1.914m
Fixed term Service Manager post (£0.088m)
Recurring total costs £1.826m 
Change Fund
7.5. £0.8m Change fund has been allocated to Social Work to develop the family support
strategy over a two-year period.  The cost of the posts at Table 2, which will be
aligned to the Family Support Hubs, will require approximately £0.6m from this
funding over the two-year period. 
The Corra Foundation
7.6. £0.487m has been awarded over a five-year period by The Corra Foundation to
recruit peer support workers to work with families affected by parental substance
misuse.  These posts will be aligned to WFWF.  This equates to £97,468 per annum. 
The cost of the posts in table 3 is £0.106m and the shortfall of £0.009m will be
managed within the overall WFWF. 
8. Climate Change, Sustainability and Environmental Implications
8.1. There are no implications for climate change, sustainability, or the environment in
terms of the information contained in this report. 
9. Other Implications
9.1. There are no risk implications associated with this report. 
9.2. There are no other issues associated with this report. 
10. Equality Impact Assessment and Consultation Arrangements
10.1. This report does not introduce a new policy, function, or strategy, or recommend a
change to existing policy, function, or strategy and, therefore, no impact assessment
is required. 
10.2. Consultation has taken place with the Children’s Services Strategy Group,
stakeholder feedback through Inclusion as Prevention who have informed the
Partnership as well as the consultation and engagement events undertaken by the
Community Mental Health and Wellbeing work involving 3500 children.  Parent and
carer feedback has been gained through the parenting support pathway and
Champions Board engagement and consultation about ‘what works’ in early
intervention.  Engagement also took place with the Gender based Violence
45

Page 46

partnership about non stigmatised supports and the Alcohol and Drug Partnership in
relation to people with Lived and Living Experience and My Support Day Family
support to seek family and carers views. 
Soumen Sengupta 
Director, Health and Social Care 
Tony McDaid
Executive Director (Education Resources) 
Paul Manning 
Executive Director (Finance and Corporate Resources) 
28 December 2022 
Link(s) to Council Values/Priorities/Outcomes
 Focused on people and their needs
 We will work to put people first and reduce inequality
 People live the healthiest lives possible 
Previous References
 None 
List of Background Papers
 None 
Contact for Further Information
If you would like to inspect the background papers or want further information, please
contact:-
Liam Purdie, Head of Children and Justice Services
Phone:  01698 454887
Email:  liam.purdie@southlanarkshire.gov.uk 
46

Page 47

Report
Agenda Item 
Report to: Executive Committee
Date of Meeting: 1 March 2023
Report by: Executive Director (Finance and Corporate Resources)  
Subject: Records Management Policy 
1. Purpose of Report
1.1. The purpose of the report is to:- 
 request approval for the revised Records Management Policy
 advise the Committee on the communication plan for the Policy
[1purpose]
2. Recommendation(s)
2.1. The Committee is asked to approve the following recommendation(s):-
[recs]
(1) that the Records Management Policy, attached as Appendix 1 to the report, and
the proposed arrangements for its communication to employees be approved. 
3. Background
3.1. The first South Lanarkshire Council Records Management Policy was approved in
June 2006. This was revised in 2012 and again in 2016. 
3.2. The Policy was reviewed by the Information Governance Board during 2022 and some
amendments were made to bring it up to date. 
3.3. The Records Management Policy is the overarching policy which provides the Council
with a framework upon which to base the management of the records it creates,
receives, holds, uses and manages. It is an important policy especially in light of The
Public Records (Scotland) Act 2011 which was implemented in January 2013. 
3.4. This Act requires public bodies to set out arrangements for the management of their
records and to prepare a Records Management Plan for submission to the Keeper of
the Records. 
3.5. This policy assists South Lanarkshire Council to meet its obligations under the Act and
provides an important framework from which other guidelines and procedures for
managing records are  developed. 
4. What Does the Policy Cover?
4.1. The Records Management Policy, which is attached as Appendix 1 applies to all
records created, received, held, used and managed by South Lanarkshire Council
irrespective of the format of the records and to all permanent and temporary
employees of South Lanarkshire Council.  
8
47

Page 48

4.2. An example of record formats is listed below:- 
 word-processed correspondence, minutes of meetings, policies, strategies,
case files, spreadsheets, and other documents
 stored maps, plans, drawings and photographs, whether analogue or digital;
 email messages
 CCTV footage (including that taken from body worn cameras)
 SMS text messages, tweets, and social media entries
 data/documents generated and stored in electronic systems such as Electronic
Document Records Management Systems, People Connect or SEEMiS 
4.3. Benefits of Good Records Management
Systematic management of records allows the Council to:- 
 know what records it has, and locate them easily
 increase efficiency and effectiveness
 make savings in administration costs, both in staff time and storage
 support decision-making
 be open, transparent, and accountable
 achieve business objectives and targets
 provide continuity in the event of a disaster by identifying vital records
 demonstrate authenticity, reliability, integrity, and accessibility
 meet legislative and regulatory requirements and apply best practice 
5. Content of the Policy
5.1. The Records Management Policy has been revised and updated from the 2016
version. It does not differ greatly from the previous version in terms of scope, purpose
and responsibilities, however, it now reflects, in section 5, that Paul Manning,
Executive Director (Finance and Corporate Resources) is the Council’s Senior
Information Risk Officer and also has responsibility for the Council’s Records
Management Plan.  Section 6 includes changes in legislation since the previous policy
update, for example the UK GDPR is now included.  The standalone section 7 on
electronic document management systems (EDRMS) has been deleted as this content
is now covered in other sections of the policy and reference to EDRMS has been
changed to ECMs (electronic content management system).  Section 11, Training, has
been updated and now includes cyber security  as well as the updated learn on line
courses available. 
6. Communication
6.1. The Records Management Policy will be circulated to employees by means of a
personnel circular and management bulletin. The policy will be made available for
download from the intranet. 
6.2. Resources will be asked to cascade the revised Policy through Resource management
teams and team meetings bringing it to the attention of employees. 
6.3. The Policy will join a suite of information governance related policies being developed
by the Information Governance Board. 
7. Employee Implications
7.1. There are no employee implications. 
8. Financial Implications
8.1. There are no financial implications.
48

Page 49

9. Climate Change, Sustainability and Environmental Implications
9.1. There are no implications for climate change, sustainability, or the environment in
terms of the information contained in this report. 
10. Other Implications
10.1. The Public Records (Scotland) Act 2011 places statutory duties on the Council as a
Scottish public authority to submit a Records Management Plan and to undertake a
programme of improvement to satisfy the provisions of the legislation. The Records
Management Policy meets the requirements of the legislation. 
11. Equality Impact Assessment and Consultation Arrangements
11.1. There are no equal opportunity assessment implications. 
11.2. The Records Management Policy has been developed in consultation with the
Information Governance Board and Council Resources. 
Paul Manning
Executive Director (Finance and Corporate Resources) 
13 February 2023 
Link(s) to Council Values/Priorities/Outcomes
 Accountable, effective, efficient, and transparent
 Fair, open, and sustainable 
Previous References
 Executive Committee, 21 November 2012
 Executive Committee 11 May 2016 
List of Background Papers
 Records Management Policy v1.0
 Records Management Policy v2.0
 Records Management Policy v3.0 
Contact for Further Information
If you would like to inspect the background papers or want further information, please
contact:- 
Geraldine McCann, Head of Administration and Legal Services 
Ext: 4568 (Tel: 01698 454568)
E-mail: geraldine.mccann@southlanarkshire.gov.uk 
49

Page 50

50

Page 51

Records Management Policy v4.0 1
Appendix 1 
Records Management Policy 
If you need this information in another language or format, please contact us to discuss how we can
best meet your needs. 
Phone 0303 123 1015 or email equalities@southlanarkshire.gov.uk 
8
51

Page 52

Records Management Policy v4.0 2
Document Control Log
Version Date Comments
V3.1 20/09/2021 Revised draft prepared by Lucy Cienkus for IGB comments
V3.2  Changes made to draft V3.1 following IGB comments – replaced
Data Protection 2018 with UK GDPR, replaced EDRMS to ECMs,
changes to responsible records manager (element 2), removed
section 7 EDRMS and other systems by incorporating content
into other sections, updated training courses, re-ordered some
sections, minor formatting, minor addition to section 9 Alternative
formats, updated contacts, fixed broken links to documents.
V3.2 19/10/2022 Circulated to IGB for final comments/approval 
Approvals 
Version Date Group
V4.0  01/11/2022 IGB 
V4.0  Executive Committee 
52

Page 53

Records Management Policy v4.0 3 
Contents 
1. Introduction 
2. Definition of a record 
3. Benefits of records management 
4. Purpose and scope   
5. Responsibilities 
6. Relevant legislation and standards 
7. Principles and implementation of good records management   
8. Digital Continuity and Preservation 
9. Alternative record formats 
10. Public records created or held by third parties 
11. Training 
12. Monitoring and review 
13. Links to Council policies and guidance 
14. Contacts 
Appendix 1 – definition of key terms 
Appendix 2 – characteristics of a managed record 
53

Page 54

Records Management Policy v4.0 4 
1. Introduction 
Records are a vital day to day source of information providing evidence on the Council’s actions,
policies, and decisions.  As a corporate asset, the Council recognises that these records must be
systematically managed throughout their life-cycle to ensure their proper use for as long as is needed. 
The Public Records (Scotland) Act 2011 places an obligation on the Council to prepare and implement
a Records Management Plan (RMP), approved by The Keeper, which sets out proper arrangements for
the management of records within the Council. The creation of a records management policy is a
mandatory element (Element 3) of the RMP and this policy together with associated policies and
guidance, provides a framework to enable continuous improvement in the way in which the council
manages and uses its records and information. 
2. Definition of a record 
A record is any information created, received, or used by South Lanarkshire Council, irrespective of
format, in connection with its business activities or the conduct of its affairs which is retained as
evidence of those activities.  Definitions of key terms used in this policy are provided in Appendix 1. 
Records can be: 
• Word-processed correspondence, minutes of meetings, policies, strategies, case files,
spreadsheets, and other documents
• Stored maps, plans, drawings and photographs, analogue or digital
• Email messages 
• CCTV footage (including footage from body worn cameras)
• SMS text messages, tweets, and social media entries
• Data/documents generated and stored in electronic systems such as Electronic Content
Management Systems (ECM), People Connect or SEEMiS 
See appendix 2 for an outline of the characteristics of a managed record. 
3. Benefits of records management 
Records management is the systematic management of the Council’s records from their creation,
receipt, maintenance, use and disposal. Systematic management of records allows the council to: 
• know what records it has, and locate them easily 
• ensure records are up to date, accurate and reliable
• manage records for as long as they are needed
• increase efficiency and effectiveness 
• save physical and electronic storage space
• reduce duplication
• support decision-making 
• be open, transparent, and accountable 
• achieve business objectives and targets 
• provide continuity in the event of a disaster by identifying vital records
• demonstrate authenticity, reliability, integrity, and accessibility
• meet legislative and regulatory requirements and apply best practice.
• identify records with long term value that require preservation 
54

Page 55

Records Management Policy v4.0 5
Poor and unmanaged records make performance of the Council’s duties more difficult, costs time,
money and resources, and puts the Council and services users at risk in terms of security breaches,
prosecution and loss of good reputation. 
4. Purpose and scope 
This Records Management Policy forms part of the Council’s wider information strategy framework and
associated suite of procedures and guidance for the management of records across the council.  As set
out in our Records Management Plan, they are intended to ensure that Council records are managed
efficiently, transparently, and consistently throughout their life cycle from the point they are created or
received, through maintenance and use, to the time they are destroyed or permanently preserved as
historic archival records. 
The purpose of this policy is to: 
• provide a corporate approach to records management.
• identify relevant legislation and regulations associated with records management.
• set out specific records management responsibilities within the Council.
• encourage a records management culture where all employees recognise the value and
benefits of effective records management 
This policy applies to: 
• all Council Resources and Services in South Lanarkshire Council.
• all council staff, volunteers, including staff on secondment or work experience placement 
• all third parties that manage and process information on the organisation’s behalf when
supporting the delivery of Council statutory or business functions.
• all records created, received, maintained and used by the Council in the course of carrying out
its business activities and it applies to all records regardless of their medium or format. 
5. Responsibilities 
The Council
In line with its obligations under Section 53 of the Local Government (Scotland) Act 1994, the Code of
Practice issued in terms of section 60 of the Freedom of Information (Scotland) Act 2002, the UK
General Data Protection Regulations (GDPR), where the information is or contains personal data, and
the Public Records (Scotland) Act 2011, the Council, has responsibility for ensuring the proper
management of its records.  South Lanarkshire Council will create, maintain and manage records which
document its decision-making process and business activities.  By doing so, the Council will be more
able to meet its statutory, regulatory, social and organisational obligations. 
Senior Officer responsible for the Council’s Records Management Plan
The Executive Director, Finance and Corporate Resources has overall responsibility for the
management of records within the Council including management of the Council’s Records
Management Plan as set out in the Public Records (Scotland) Act. The Executive Director is also the
Senior Information Risk Officer (SIRO) for the Council. 
Records Management responsibility
The Legal Services Adviser/Information Compliance Manager has overall responsibility for developing 
and implementing the Records Management Plan (RMP) and is The Keeper’s initial point of contact for
records management issues.  The Legal Services Adviser/Information Compliance Manager is also
responsible for managing the Council’s Archives and Records Centre. 
55

Page 56

Records Management Policy v4.0 6
Information Governance Board
Chaired by Head of Administration and Legal Services, the Information Governance Board, has
representation from all Resources, and responsibility for helping drive improvements within information
governance principles across the Council.  The Information Governance Board recognises that records
management is a key component to achieving good information governance practice. 
The Information Governance Board has responsibility for the monitoring and review of the Council’s
Information Strategy, Records Management Plan, Records Management Policy, and the
implementation of the vital records programme. 
Archives and Information Management Service (AIMS)
The Archives and Information Management Service sits within Administration and Legal Services,
Finance and Corporate Resources.  This service is responsible for: 
• Records management policy and procedures 
• Best practice guidance
• Records retention and disposal schedules and policies
• Selection, transfer and long-term preservation of historical records to the Council’s Archive
• Management of the Council’s Archives and Records Centre 
The Archives and Information Management service will have appropriate levels of professional and
administrative staff to provide an effective service to South Lanarkshire Council. 
IT Services
IT Services has responsibility for managing the Council’s network infrastructure, ensuring systems
continuity and security, and facilitating the business of the Council by advising on the appropriate tools. 
The IT Business teams also have responsibility for ensuring that records management arrangements
are considered and built into the specification for any new business system. 
All Resources
Individual Resources are responsible for the implementation of records management procedures
across their Services.  Resources must ensure that appropriate employees are designated to
implement records management procedures and liaise with the Archives and Information Management
Service as needed. 
All Council employees
It is the responsibility of every employee to manage the Council’s records, a corporate asset,
responsibly and in line with records management procedures, including specific arrangements in their
service or Resource.     
6. Relevant legislation and standards 
Records must be managed in accordance with relevant legislation, regulations and existing
professional standards. These include the following: 
• Local Government (Scotland) Act 1994
• The UK General Data Protection Regulation (UK GDPR)
• Human Rights Act 1998
• Freedom of Information (Scotland) Act 2002
• Environmental Information (Scotland) Regulations 2004
• Public Records (Scotland) Act 2011
• BS ISO 15489 Standard on best practice in records management
• BS 10008:2008 Evidential weight and legal admissibility of electronic information
56

Page 57

Records Management Policy v4.0 7
• Pupils’ Educational Records (Scotland) Regulations 2003
• The Re-use of Public Sector Information Regulations 2015
• Information Commissioner’s Surveillance camera code of practice
• Other relevant statutory and regulatory obligations covering business functions such as Health
and Safety and Finance. 
7. Principles and Implementation of good records management 
South Lanarkshire Council is committed to the development and implementation of procedures and
guidance to facilitate the creation and maintenance of authentic, reliable, and useable records capable
of supporting its business activities for as long as they are required. 
The guiding principle of records management is to ensure that information is secure and accessible
when and where it is needed, in an organised and efficient manner, in accordance with an agreed
business classification scheme and in a well-maintained environment.   
Procedures will be implemented to ensure the appropriate management of records from their creation
or receipt by the Council, through their active use until final disposition – either by transfer to the
Council’s Record Centre or secure and confidential destruction.  A small percentage of our records will
be selected for permanent preservation as part of South Lanarkshire Council’s Archives, ensuring the
maintenance of the corporate history. 
These procedures will be based upon the Council’s statutory and regulatory requirements, professional
standards and best practice. 
The Council recognises the Resource requirements to effectively implement records management
procedures across its Services and it will ensure that appropriate resources are available across the
Council. 
The Council will deliver good records management by implementing processes and procedures
including but not limited to: 
• Development of a corporate file plan for the Council’s Enterprise Content Management system
(ECM) Objective based on business functions
• Development and implementation of retention and disposal schedules covering all business
areas of the Council applicable to all record formats
• Development of vital records plans to assist Resources in recovering records essential to the
running of their business in the event of a disaster
• Operating a managed off-site storage facility for the Council’s non-current records and archives
• Implementing effective back-up procedures for the maintenance and security of electronic
records
• Appropriate management of personal, sensitive or confidential information 
• Clearly documented records management requirements to be included from the outset into any
new business system specified and provision made for how the records created by the system
will be appropriately retained, deleted or preserved for as long as needed in the future
• Clearly documented records management requirements to be included as part of any major
change to IT systems and business processes
• New systems intended for the processing of personal and sensitive personal data must have a
privacy impact assessment carried out at the conception stage of the project. This assessment
will include the consideration and implementation of proper retention and destruction
policies/procedures for the personal data involved.
• Ensuring employees receive appropriate training to carry out their responsibilities
57

Page 58

Records Management Policy v4.0 8
• Publishing information governance policies, procedures, and guidance on the intranet for all
council staff to access. 
8. Digital continuity and preservation 
Digital continuity is the ability to maintain the digital information of a creator in such a way that the
information will continue to be available, as needed, despite changes in digital technology. It focuses on
making sure that information is complete, available, and usable for business needs. 
Information is usable if it can be:
• found when needed
• accessed when needed 
• worked with it in the way required 
• understood in terms of what it is and what it is about
• trusted that it is what it says it is 
Managing digital continuity protects the information needed to do business. This enables the council to
operate accountably, legally, effectively, and efficiently. It helps the council protect its reputation, make
informed decisions, reduce costs, and deliver better public services. If information is lost because digital
continuity has not been managed properly, the consequences can be as serious as those of any other
information loss. 
Resources should be aware of the risks associated with digital records and that, as technology
advances, appropriate action must be taken in liaison with IT Services, to ensure that electronic records
that are required to be retained long term are migrated, updated, protected or preserved as appropriate
so that they remain authentic, trustworthy, accessible, and useable for as long as is needed.   
9. Alternative record formats 
Consideration should be given to records created using electronic mail, SMS text messaging, social
media and CCTV footage (including body worn cameras).  These records are subject to the same
regulations as other formats of records and therefore should be captured, retained, and managed
appropriately in corporate systems. 
This applies not only to records created using council computers and council issued mobile devices but
also to official business conducted from private email accounts and private mobile phones or devices. 
All official Council records must be captured and retained in official systems.  An example of this might
be an instruction sent by text to a member of staff to carry out a specific duty.  To capture this record,
an officer might type up a file note on return to the office and save it to the shared drive or the council’s 
content management system or a case management system.   
Social media, such as Twitter and Facebook, as well as messaging services such as Microsoft Teams
Chat, should also be considered if used for council business and appropriate procedures introduced to
capture official council records into corporate systems. An example of records created through Twitter
might be responses to complaints received or the publishing of road reports.   
The Council recognises that this is a new and evolving area and separate guidance regarding this topic
will be issued to assist Council employees.  A separate social media policy has been approved by the
Council.
58

Page 59

Records Management Policy v4.0 9 
10.  Public Records created or held by third parties 
One of the requirements of the Public Records (Scotland) Act 2011 is that when a public authority is
contracting out a function to a private or voluntary organisation, the contracting authority is responsible
for ensuring that the records created as part of that contract are managed in an appropriate manner. 
This means that the Council must have procedures in place to ensure that the private or voluntary
organisation is looking after our records appropriately. 
This will be achieved by: 
• Adding the requirement (where applicable) to the Pre-Qualifying Questionnaire in the tendering
process and asking organisations to advise how they will manage the records created in the
process of carrying out the function
• Where appropriate, developing procedures to monitor and assess whether organisations are
adhering to this requirement. 
• Particular arrangements put in place where personal data is being “processed” by the contractor
on behalf of the Council even if the “processing” is merely storage of the information without the
contracting out of a function. This refers to when the council uses an external server or the
cloud to hold the information for us.   
• Provision of a Council Procurement and Data Protection toolkit that contains the contractual
provisions and monitoring arrangements by the Council that must be put in place. 
11. Training 
The Council recognises the importance of records management and information management more
widely.  A suite of core Learn On Line courses is available to help employees carry out their information
management duties and encourage a culture where records management is understood and valued. 
Learn On Line Courses
Cyber security – stay safe online
Data Sharing 2018
Document verification
Email and Online Risk
How Data Protection applies to the Council
Identifying a request for information 
Introduction to the Data Protection - 2018
Information management and me
Information Governance – an introduction
Information Security
Processing a request for information
Records Management
Subject Access Requests 2018 
12. Monitoring and review 
This policy will be reviewed by the Information Governance Board when required or, at the minimum, at
least every 5 years. The Information Governance Board will regularly monitor compliance with the
policy’s procedures and guidelines making any amendments and improvements as necessary.  The
Information Governance Board will report on progress to the Corporate Management Team. 
59

Page 60

Records Management Policy v4.0 10
Resources must monitor and review their own arrangements that have been put in place in order to
comply with this policy on a similar regular basis.   
13. Associated Council policies and guidance 
This policy forms part of a suite of Council policies and guidance that relate to records management. 
These are all available on the intranet and Resources should refer and adhere to these alongside this
Records Management Policy. 
• Information Strategy
• Records Management Plan
• Information Security Policy
• IT Acceptable Use Policy
• Information Requests Compliance Policy
• Data Protection policy
• Employee Code of Conduct 
• Corporate Standards Policy 
• Confidential waste guidance
• Retention and Disposal Policy
• Collection, Transfer and Archiving Policy
• Social Media policy 
• Vital records guidance 
14. Contacts 
Further information on records management and the council’s procedures, is available on the records
management pages of the intranet or contact the Archives and Information Management Service: 
Manager: Bill Dunn, Legal Services Adviser
Phone:  01698 45 4564
Email:  bill.dunn@southlanarkshire.gov.uk 
Record Centre: 
Email: recordcentre@southlanarkshire.gov.uk 
You can also contact your Information Governance Board representative for further information. 
60

Page 61

Records Management Policy v4.0 11
Definition of Key Terms Appendix 1 
Archives
Records which have administrative, evidential, or historical and cultural value over a sustained period of
time. 
File Plan
A file plan lists the records in your service and describes how they are organised and maintained. 
Objective ECM (Enterprise Content Management)
Objective ECM (Enterprise Content Management) is an electronic document and records management
system.  It is a software application designed to facilitate the creation, management, use, storage and
disposal of a range of both physical and digital documents and records in an integrated way. Objective
ECM can also automate business processes such as workflows and approvals and be integrated with
other business systems. 
Personal data
This has a particular meaning under the UK GDPR but, in summary, it is information that relates to a
living, identifiable (not necessarily by name) individual. Relating to an individual includes being used by
the Council to make decisions about the individual or recorded by the Council to tell it something about
the individual. 
Record
Recorded information created, received, or used by South Lanarkshire Council in connection with its
business activities or the conduct of its affairs which is retained as evidence of those activities. 
Records can be held in any format. 
Records Management
The field of management responsible for the efficient and systematic control of the creation, receipt,
maintenance, use and disposal of records.   
Record Retention Schedule
This is a document drawn up by a service in consultation with the Archives and Information
Management Service which sets out all the different sets of records created by the service in
conducting its business.  It outlines how long each type of record should be retained in the office, stored
at the Records Centre and its eventual fate or destruction date. 
Vital Records
Vital records are those without which the Council could not continue to operate in the event of a
disruption or disaster.  They are records which are required to carry out core functions in a legally
compliant manner, they contain information needed to re-establish/continue the business of the Council
in the event of a disaster, they protect the Council’s assets and interests, protect employees, customers
and stakeholders, and the Council’s reputation
61

Page 62

Records Management Policy v4.0 12 
Characteristics of a managed record Appendix 2 
South Lanarkshire Council must ensure that its records are: 
Adequate
Records must be full enough to meet the purposes for which they are being held.  The use of
information that is not adequate for its purpose may not be possible or be detrimental to its use in some
other way. 
Authentic
Records are reliable - that they represent the information that was used in the business process.  It
must be possible to prove that the records are what they purport to be and who created them with audit
trails. 
Accurate and reliable
Our reputation is maintained through the full and accurate record of the Council’s activities.  Records
must reflect the business that the Council carries out. Records must be created close to the time of the
transaction /activity and created by individuals with direct knowledge of the instruments involved in the
transaction /activity. 
Accessible and useable
Records can be readily accessed by those with appropriate authority when required. The context can
be established through links to other records in the transaction /activity. 
Complete and integral
Records must be sufficient in content, context, and structure to reconstruct the relevant activities and
transactions. The records must be complete and unaltered and protected against unauthorised
alteration. An audit trail can be followed to identify alterations after creation and persons making the
changes. 
Comprehensive
Records can be interpreted with ease, providing information about the business activity to which they
relate and pointing to other related records. 
Compliant
Records must comply with any record keeping requirements arising from legislation and other statutory
obligations. 
Effective
Records maintain their qualities of accessibility, interpretation and reliability for as long as the record is
maintained and be kept for as long as they are required to support business activities and to act as an
audit trail of the decisions and transactions of the Council. 
Not excessive
There is little point in collecting/creating information that is excessive for the purpose to which it is
intended. Excessive information could confuse or delay the thinking process of the Council and, where
the information is personal data, could be detrimental to any individuals concerned if lost or in
appropriately disclosed to someone else. 
Secure
Records are protected and kept secure in a manner appropriate to their value and content.
62

Page 63

Report
Agenda Item 
Report to: Executive Committee
Date of Meeting: 1 March 2023
Report by: Executive Director (Finance and Corporate Resources)  
Subject: Retention and Disposal Policy 
1. Purpose of Report
1.1. The purpose of the report is to:- 
 seek approval for the updated Retention and Disposal Policy
 advise the Executive Committee on the communication arrangements for the
Policy
[1purpose]
2. Recommendation(s)
2.1. The Committee is asked to approve the following recommendation(s):-
[recs]
(1) that the Retention and Disposal Policy, attached at Appendix 1, be approved;
and
(2) that the plans for communication of the Policy set out in section 4.4 of the report
be noted. 
3. Background
3.1. South Lanarkshire Council is responsible for managing the records it creates,
receives, and uses. Part of the management of these records involves making
decisions regarding the retention and disposal of the records. This Policy sets out the
framework on how this should be approached. 
3.2. The Public Records (Scotland) Act 2011 was implemented in January 2013. This Act
requires public bodies to set out arrangements for the management of their records
and to prepare a Records Management Plan for submission to the Keeper of the
Records. 
3.3. This Policy will assist South Lanarkshire Council in meeting its obligations under the
Act and will enable employees to make appropriate arrangements for the retention
and disposal of the records under their care. 
4. What Does the Policy Cover?
4.1. Record Retention
4.1.1. Records in South Lanarkshire Council should all be covered in a retention schedule
developed for each business function. A record retention schedule sets out the periods
by which the Council’s business records should be retained to meet legislative,
administrative and operational requirements and to maintain a corporate memory. 
4.1.2. The Council already has retention schedules in place which are reviewed regularly.
The policy formalises the process and explains the benefits of this and why it is
necessary.
9
63

Page 64

4.2. Record Retention Periods
In the development of record retention schedules, a detailed audit and survey is
carried out for the area of business being considered. Retention periods will be
determined for each record set, setting out how long the record should be retained.
This will differ depending on the type of record. For example, financial records are
normally retained for six years after record closure. On the other hand, a Social Work
adoption file is kept for 100 years. Education Records are kept for 25 years after a
pupil leaves school and Legal files are retained for 6 years after closure of the file. 
4.3. Record Disposal
The disposal outcome of a record can be one of the following choices:- 
 Review – consider whether a record should be retained for historical archival
purposes or destroyed
 Destroy – the record has reached the end of its life and no longer has any
business value, nor does it have any value as an historical archive and can be
destroyed.
 Transfer to archive – the record has been identified as having long term value as
a historical archive for future generations 
The disposal outcome will be determined in consultation with the Service which owns
the record series in question and will be documented on the agreed retention schedule.
The Policy explains what arrangements Resources require to put into place in order
that records are disposed of in the appropriate manner. 
4.4. Communication
4.4.1. The Retention and Disposal Policy will be circulated to employees by means of a
personnel circular and management bulletin. The Policy will be made available for
download from the intranet. 
4.4.2. Resources will be asked to cascade the revised policy through Resource management
teams and team meetings bringing it to the attention of employees. 
4.4.3. The Policy will join a suite of information governance related policies being developed
by the Information Governance Board. 
5. Employee Implications
5.1. There are no employee implications. 
6. Financial Implications
6.1. There are no financial implications. 
7. Climate Change, Sustainability and Environmental Implications
7.1. There are no implications for climate change, sustainability or the environment in terms
of the information contained in this report. 
8. Other Implications
8.1. The Public Records (Scotland) Act 2011 places statutory duties on the Council as a
Scottish public authority to submit a Records Management Plan and to undertake a
programme of improvement to satisfy the provisions of the legislation. The Retention
and Disposal Policy meets the requirements of the legislation. 
9. Equality Impact Assessment and Consultation Arrangements
9.1. The Policy has been assessed in terms of an Equalities Impact Assessment.
64

Page 65

9.2. The Retention and Disposal Policy has been reviewed in consultation with the
Information Governance Board and Council Resources. 
Paul Manning
Executive Director (Finance and Corporate Resources) 
13 February 2023 
Link(s) to Council Values/Priorities/Outcomes
 Accountable, effective, efficient, and transparent
 Fair, open, and sustainable 
Previous References
 Executive Committee 15 September 2015 
List of Background Papers
 Retention and Disposal Policy v1 
Contact for Further Information
If you would like to inspect the background papers or want further information, please
contact:- 
Geraldine McCann, Head of Administration and Legal Services
Ext: 4568 (Tel: 01698 454568)
E-mail:geraldine.mccann@southlanarkshire.gov.uk 
65

Page 66

66

Page 67

V2.0       
Appendix 1   
Retention and Disposal Policy 
9
67

Page 68

V2.0 
Document control log 
Issue Date Comments   
V1.0 23 September
2015
Approved by Executive Committee   
V2.0 01 November  Approved by IGB 
68

Page 69

V2.0
Contents 
1. Purpose and scope        page 4 
2. Retention schedule        page 4 
3. Benefits of a retention schedule        page 4 
4. Disposal Fate        page 5 
5. Expiry of retention period – paper records held in offices         page 5 
6. Expiry of retention period – paper records held at Records Centre   page 5 
7. Expiry of retention period – electronic records    page 6 
8. Confidential waste disposal      page 6 
9. Further information        page 7 
69

Page 70

V2.0
1 Purpose and scope 
This policy sets out the framework for how South Lanarkshire Council manages
the retention and disposal of its records. 
It applies to all Resources and Services that create, receive, manage, and use
records. 
2 Retention Schedule
All records in South Lanarkshire Council should be covered by a retention
schedule developed for each business function.  A records retention schedule
sets out the retention periods by which the council’s business records should be
retained to meet legislative, administrative, and operational requirements. A
small selection of records identified for transfer to the archive to preserve
historical corporate memory. 
A retention schedule is a records management tool used to:
• identify and capture groups of common records, known as ‘record series’
• assign retention periods with reference to legislation, best practice and
operational need 
• record disposal fate these being destroy, review, permanent or transfer to                                       
archive.
The Archives and Information Service (AIMS) is responsible for developing
retention schedules for all services across the council.  These are developed
with the individual Services, the final agreed version is signed off by the
appropriate Head of Service.  For those records held in paper format stored at
the Records Centre the signed and agreed retention schedule allows the
Archives and Records Assistants to destroy the records at their appointed
expiry date without needing to refer back to the services.
Retention schedules apply to records in all formats so where a record is held in
both paper and electronic format those records should be disposed of at the
same time or as near as operationally possible using appropriate disposal
methods.
3 Benefits of a retention schedule 
There are a number of benefits which arise from the use of a complete retention
schedule: 
• Managing records against the retention schedule is deemed to be “normal
processing” under the UK General Data Protection Regulations/Data
Protection Act 2018 (UK GDPR) and the Freedom of Information (Scotland)
Act 2002.  Provided members of staff are managing record series using the
retention schedule they can not be found guilty of unauthorised tampering
with files once a freedom of information request or a data subject access
request has been made. 
• Members of staff can be confident about destroying information at the
appropriate time.
70

Page 71

V2.0 
• Information which is subject to Freedom of Information and Data Protection
legislation will be available when required. 
• The Council is not maintaining and storing information unnecessarily. 
4 Disposal Fate
The disposal fate is determined in consultation with the department who owns
the record series in question and is documented on the agreed retention
schedule.
The disposal fate of a record can be one of the following: -
Review
Review means that when a record reaches the end of its retention period, its
fate is considered either for inclusion into the Council’s historical archives, or
if not, destruction.  In some cases, further retention may be agreed, for
example, if new retention instructions are given by an external funder. 
Destroy
Destroy as fate means that once the record reaches the end of its retention
period it is considered of no continuing value to the Council and can be
destroyed.  Occasionally the destruction of specific record series is put on
hold, for example, when there is an inquiry such as The Scottish Children’s
Abuse Inquiry. 
Transfer to archive
Paper records which have been identified for accessioning into the Council’s
historical archive collection will have Archive as their fate. Electronic records
with Archive as their fate should be held by the Resource in the native system
for long term preservation.
Permanent
Some record series have permanent as their disposal fate which means they
are retained permanently by the Service either in the office, on an official
council electronic system or in the Record Centre.  In these instances,
permanent records are not identified to be archival records and therefore are
not transferred to the council’s archive. 
5 Expiry of retention period - paper records held in offices
Once the retention period has expired as per the retention schedule, records
held in council offices should be destroyed.  If the records contain
confidential, personal and or sensitive personal data, these should be
destroyed using the confidential waste service via the Print Centre (see
section 8) or by local secure confidential destruction procedures.  
Records identified as having continuing value must be transferred into the
council archive as directed in the Collection, transfer and archiving policy.
71

Page 72

V2.0
6 Expiry of retention period - paper records held at the
Record Centre
Where paper records have been consigned to the Record Centre and the
retention period has expired, the records are either:
• reviewed for further retention by the Archives and Information Management
service where ‘review’ is given as the fate on the retention schedule
• transferred into the archive for permanent preservation as indicated on the
retention schedule by disposal fate ‘archive’ or
• confidentially and securely disposed using the Council’s Confidential Waste
contract where ‘destroy’ is the assigned fate. 
All disposal decisions, dates of disposal and certificates of destruction of
records destroyed at the Records Centre are documented and a record
permanently kept. 
7  Expiry of retention period – electronic records 
Records of business activities and transactions may be maintained in many
different media and formats and are often stored in multiple locations.
Regardless of location and format effective retention and disposal rules must
be applied to all electronic records using approved retention schedules.
Where possible it is recommended that the retention period is identified
before or at the time of file creation and applied as part of the retention and
disposal process. 
• Network files
Electronic records held on a network drive or an electronic system must be
deleted at the same time as their duplicate paper records. An exception to
this would be when paper copies are electronically scanned and then
destroyed, and the electronic copy becomes the master record.  All copies of
network files must be deleted from the system. 
• C:drives
Records must not be held on c: drives. Any records deleted from your
desktop or c: drive can end up in recycle bins so these must be checked to
ensure that all copies of the record have been deleted and cannot be
resurrected. This is particularly important for records that hold personal and
sensitive information. With digital records deletion from a server may not be
sufficient. Duplicate and/or backup copies must also be destroyed at the
same time, to ensure compliance with the UK General Data Protection
Regulations/Data Protection Act 2018 (UK GDPR) and Freedom of
Information legislation. 
• Emails
Emails which are or contain council records should be retained within the
relevant subject matter folder within the network or electronic system with a
retention period applied.  Microsoft Outlook should not be used as a filing
system. 
• Electronic content management systems 
Records held on any official council system must have retention periods
assigned to them based on approved retention schedules.  
72

Page 73

V2.0
• Long term preservation
Electronic records which have been designated as permanent or for transfer
to the Archives should be maintained in the native system (their original
system).  Arrangements should be made for the long-term preservation of
these records ensuring that the integrity of the record is maintained, and
digital continuity is guaranteed.  At present the council archive has no means
of accepting electronic transfer into a digital repository so it is the
responsibility of Resources to ensure the preservation of these records. The
future long-term aim of the Council is to develop a digital preservation
strategy. 
• Portable media
Records and information held on portable media such as tapes, CDs or
DVDs, should be destroyed by destroying the physical media concerned. For
example, CDs/DVDs can be cut in half and items can then be placed directly
into a general waste container.  Larger quantities of portable media can be
disposed of using the Confidential Waste disposal service from the Print
Centre. (See section 8.)   
8  Confidential waste disposal
The Print Centre operates a confidential waste disposal service.  The service
can be accessed from the Print Shop icon located in the middle of the menu
bar on the intranet  or by emailing printing@southlanarkshire.gov.uk or by
phoning 01698 454241.   
9 Further information 
Further information on records retention and disposal is available on the
records management pages of the intranet or contact the Archives and
Information Management Service: 
Phone: 01355 239193
Email: recordcentre@southlanarkshire.gov.uk 
73

Page 74

74

Page 75

Report
Agenda Item 
Report to: Executive Committee
Date of Meeting: 1 March 2023
Report by: Executive Director (Finance and Corporate Resources)  
Subject: King Charles III Coronation 
1. Purpose of Report
1.1. The purpose of the report is to:- 
 advise the Executive Committee of the arrangements made to enable employees
to celebrate the Coronation of King Charles III
[1purpose]
2. Recommendation(s)
2.1. The Committee is asked to approve the following recommendation(s):-
recs]
(1) that the Council provide a reduced service on Monday 8 May 2023, as
detailed in paragraph 4.1; and
(2) that the addition of a fixed annual leave day for employees on Monday 8 May
2023 be noted.
[1recs]
3. Background
3.1. To mark the Coronation of King Charles III on Saturday 6 May 2023, an additional
national bank holiday has been announced for Monday 8 May 2023.   
3.2. To enable employees to celebrate the event, consistent with other royal occasions,
the council will operate a reduced service to the public. 
4. Arrangements 
4.1. To accommodate celebration of the event, non-essential services will have to be
reduced and Council offices closed, where possible. The following services will be
provided:-  
Community and Enterprise Resources
 Waste 
 Roads – Emergency works only
 Grounds – Bereavement (scheduled burials and cremations only) 
 Essential Staff to support the above 
Finance and Corporate Resources
 Emergency Call Handling
 Planned Ceremonies 
Housing and Technical Resources
 Property Services – Emergency Repairs
 Housing Services – Emergency Homelessness
 Limited Sheltered Housing and Caretaking Services
10
75

Page 76

 CCTV 
Social Work Resources
 Home Care/Residential 
 Emergency Social Work Services 
4.2. Employees required to work on the additional fixed annual leave day will receive a
day to take at another time.  This approach is consistent with previous royal events. 
5. Employee Implications
5.1. Not all employees will be able to take time off on the day as some services will
require a continuation of delivery. Employees unable to take the day off will have a
compensatory day to take at another time. 
6. Financial Implications
6.1. Any additional costs associated with the additional leave day will be accommodated
within existing employee budgets.   
7 Climate Change, Sustainability and Environmental Implications
7.1 There are no climate change or sustainability implications linked to this report. 
8. Other Implications
8.1. There are no other implications arising from this report. 
9. Equality Impact Assessment and Consultation Arrangements
9.1. This report does not introduce a new policy, function or strategy or recommend a
change to an existing policy, function or strategy and, therefore, no impact
assessment is required.   
9.2. Consultation regarding the arrangements have taken place with the Trade Unions. 
Paul Manning
Executive Director (Finance and Corporate Resources) 
3 February 2023 
Link(s) to Council Values/Priorities/Outcomes
 Excellent employer 
Previous References
 None 
List of Background Papers
 None 
Contact for Further Information
If you would like to inspect the background papers or want further information, please
contact:-
Kay McVeigh, Head of Personnel Services
Ext:  4330 (Tel: 01698 454330)
E-mail: kay.mcveigh@southlanarkshire.gov.uk
76

Page 77

Report
Agenda Item 
Report to: Executive Committee
Date of Meeting: 1 March 2023
Report by: Chief Executive  
Subject: Coronation of King Charles III 
1. Purpose of Report
1.1. The purpose of the report is to:- 
 provide the Committee with details of potential opportunities for South Lanarkshire
communities to engage in events related to the Coronation of King Charles III, and
how the Council can assist with such opportunities
[1purpose]
2. Recommendations
2.1. The Executive Committee is asked to approve the following recommendations:-
[]
(1) that the arrangements around the coronation and opportunities for local
communities and organisations to participate are noted.
(2) that free lets should be offered to community groups for the specific purpose of
participating in coronation events, with South Lanarkshire Leisure and Culture
reimbursed for lost income, in key venues as outlined at 5.2.3. 
[1recs]
3. Background
3.1. Following the death of HM The Queen, the coronation of His Majesty King Charles III
and Her Majesty The Queen Consort is scheduled to take place on the morning of
Saturday 6 May 2023 at Westminster Abbey in London. An extra bank holiday on
Monday 8 May 2023 has been announced. The ceremony is expected to be shown
live and in full by the BBC and other broadcasters. 
3.2. The Lord Lyon King of Arms, Dr Joseph Morrow KC, wrote to the council on 7 February
2023, along with other local authorities across the UK, to give initial detail of how
communities across the country might get involved in the event. Dr Morrow noted:
“While London will be the focus of the Coronation, just as it was the centre of the
Platinum Jubilee weekend, it is expected that festivities will take place throughout the
land. In Scotland our celebrations of this nature are best when not imposed from above
but community led, infused with local flavour and demonstrating the care and
consideration of all involved.” 
4. Involvement in South Lanarkshire
4.1. The specific request of local authorities is that they promote this approach in their local
areas and help communities consider how they may participate and prepare for the
coronation. The Lord Lyon notes the short period available until the coronation for such
preparations to be made. 
11
77

Page 78

4.2. A number of suggested ways that local organisations can take part have been made
from within the Royal Household, with support from the Department for Digital, Culture,
Media and Sport. These include:- 
 Street Parties: these would be organised by interested communities themselves,
though they may have to apply to the Council for road closures. 
 The Coronation Big Lunch: groups are invited to gather on Sunday 7 May 2023
for a lunch “to celebrate communities, their connections and allow people to
establish new friendships”. This is being organised nationally by the Eden
Project, and more information can be found here: The Big Lunch | Eden Project
Communities 
 The Big Help Out: this is suggested as “an opportunity to reflect on the legacy
of His Majesty’s service and to highlight the impact of volunteering”. This will take
place on Monday 8 May, the day of the extra bank holiday for the coronation.
Individuals who want to donate time and skills to help charities, causes and the
vulnerable can find out more here: The Big Help Out 
 Events Held in Council Owned Civic Amenities: for example exhibitions,
storytelling or concerts. See 5.2.3 below. 
4.3. The Lord Lyon acknowledges the budget restrictions facing local authorities and the
cost-of-living crisis affecting households and adds: “this, quite rightly will be a
consideration for all embarking on plans for celebrating the coronation”. 
5. Next steps
5.1. South Lanarkshire Council will promote the invitation to local communities to
participate in the Coronation via our usual communications channels, as appropriate,
that is through southlanarkshireview.scot and social media. Also, the Community
Engagement Team will use its local networks and connections with community groups
to make them aware of the opportunities and potential routes for funding. 
5.2.1. In his letter, the Lord Lyon included details of a potential National Lottery route for
community groups to apply for small grants to assist with costs for events. These were
also promoted on social media. Details can be found here: Funding programmes | The
National Lottery Community Fund (tnlcommunityfund.org.uk) 
5.2.2. The Council is aware that this information issued by the Lord Lyon may not have
reached community groups in time for their consideration. Through the routes outlined
in 5.1. above we will make sure such groups are made aware of any potential other
funding opportunities, including the council’s community grants. As members are
aware, community grants can be used to help towards a range of costs, including
administration and publicity, materials and temporary public entertainment licences.
Full details can be found here: Community grant information sheet - South Lanarkshire
Council 
5.2.3. Furthermore, it is proposed that the Council should support events in each of the four
localities by offering free lets for the purposes of community groups specifically
marking the Coronation at the key venues of Rutherglen Town Hall, Lanark Memorial
Hall, Hamilton Town House and East Kilbride Civic Centre. 
5.3. The Council will also assist community groups to prepare for events in other specific
ways within our regular duties, for example by considering requests for road closures
to permit street parties and other events to take place.
78

Page 79

5.4. The Lord Lyon has requested that local authorities keep him aware of planned
activities in the area. The Council will do so, and will encourage community groups to
make any planned events known to him. It is anticipated that events in South
Lanarkshire will be added to a national interactive map similar to one that was created
for the 2022 Platinum Jubilee. 
6. Employee Implications
6.1. There are no significant employee implications other than the potential for staff to be
involved in assisting community groups plan for and deliver events. 
7. Financial Implications
7.1. The Council will cover the costs of any free lets provided through the provision at 5.2.3
to ensure no loss to South Lanarkshire Leisure and Culture. 
8. Climate Change, Sustainability and Environmental Implications
8.1. There are no climate change, sustainability or environmental implications arising from
this report. 
9. Other Implications
9.1. There are no other implications as a result of this report. 
10. Equality Impact Assessment and Consultation Arrangements
10.1. No Equality Impact Assessments or consultations are necessary as a result of this
report. 
Cleland Sneddon
Chief Executive 
16 February 2023 
Link(s) to Council Values//Priorities/Outcomes
 Caring, connected, sustainable communities 
Previous References
 None 
List of Background Papers
 None 
Contact for Further Information
If you would like to inspect the background papers or want further information, please
contact:-
Tom Little, Head of Communications and Strategy
Extension: 4904  (Phone: 01698 454904)
E-mail: tom.little@southlanarkshire.gov.uk 
79

Page 80

80

Page 81

Report
Agenda Item 
Report to: Executive Committee
Date of Meeting: 1 March 2023
Report by: Chief Executive 
Subject: Recommendation Referred by Finance and Corporate
Resources Committee – Non-Domestic Rates – Empty
Property Relief Policy 
1. Purpose of Report
1.1. The purpose of the report is to:- 
 request approval of the undernoted recommendation referred to this Committee
by the Finance and Corporate Resources Committee of 15 February 2023
1purpose]
2. Recommendation(s)
2.1. The Committee is asked to approve the following recommendation(s):-
[recs]
(1) that the Empty Property Relief (EPR) Policy be approved and adopted by the
Council from 1 April 2023.
[1recs]
3. Background
3.1. Recommendation Referred by Finance and Corporate Resources Committee of
15 February 2023 – Non-Domestic Rates – Empty Property Relief Policy –
Extract of Minute 
A report dated 25 January 2023 by the Executive Director (Finance and Corporate
Resources) was submitted on the devolution of Non-Domestic Rates Empty Property
Relief (EPR) from the Scottish Government to local authorities. 
The existing EPR scheme operated at a national level, was mandatory and fully
funded by the Scottish Government through the Local Government Finance
Settlement.  EPR provided certain rates relief on unoccupied non-domestic
properties. 
The Programme for Government 2021/2022 confirmed that the devolution of EPR
would be delivered in April 2023 for the purpose of enabling councils to tailor support
to meet local needs.  This meant that EPR reliefs and exemptions would no longer
be covered by legislation.  All Scottish councils required to have an EPR Policy in
place from 1 April 2023 as the current legislation governing this would lapse on 31
March 2023. 
£105 million was to be devolved across councils by the Scottish Government,
reflecting the Scottish Fiscal Commission (SFC) Medium Term Finance Strategy
(MTFS) forecasts published on 31 May 2022.  The annual allocation of £105 million
was fixed until the next revaluation in 2026.  This considered the impact of the rates
12
81

Page 82

revaluation effective from 1 April 2023 and any inflationary pressures.  The Council’s
allocation for 2023/2024 was £2.183 million. 
It would be for local authorities to decide how they used this funding and the reliefs
and exemptions that might apply under a local scheme.  The funding provided was
based on the operation of the current EPR scheme.  Any changes to the reliefs and
exemptions provided which cost more than the funding would have to be met by the
Council. 
The current legislative criteria for awarding EPR and the relief categories awarded in
2021/2022 were detailed in the report. 
Devolution of EPR would come into effect at a time of significant change, with a
major revaluation of non-domestic rateable values effective from 1 April 2023 and at
a time of major volatility in the economy and financial uncertainty facing businesses. 
Maintaining the current provisions would provide some stability and certainty for
businesses as well as the Council during these challenging times.  It also provided a
period to assess the benefits of any future amendments to the policy.  Indications
from other councils were that this was also the approach they were adopting. 
Clarification was also awaited from the Scottish Government on some specific
aspects of the new arrangements.  A revised funding allocation had been confirmed
to the Council on 24 January 2023. 
It was recommended that the EDR Policy, to be adopted from 1 April 2023, reflect
the change in legislation covering EPR and that the current policy be amended to
reflect this.  The proposed policy was attached as Appendix 1 to the report. 
A review of the Council’s EPR Policy would be undertaken and the outcome reported
to this Committee by March 2024. 
The Committee decided: 
(1) that the devolution of EPR to councils and the funding arrangements be
noted; and 
(2) that the EPR Policy be reviewed and presented to this Committee by March
2024 to allow for a period of stability for rate payers and the Council. 
The Committee
recommended to the
Executive Committee:
that the EPR Policy to be adopted by the Council
from 1 April 2023, as detailed in Appendix 1 to the
report, be approved. 
3.2. A link to the report submitted to the Finance and Corporate Resources Committee of
15 February 2023 is provided here for information. 
4. Employee Implications
4.1. All employee implications were highlighted as part of the original report to the
Resource Committee. 
5. Financial Implications
5.1. All financial implications were highlighted as part of the original report to the
Resource Committee. 
82

Page 83

6. Climate Change, Sustainability and Environmental Implications
6.1. There are no implications for climate change, sustainability or the environment in
terms of the information contained in this report. 
7. Other Implications
7.1. Any risks or other implications were highlighted as part of the original report to the
Resource Committee. 
8. Equality Impact Assessment and Consultation Arrangements
8.1. Equality impact assessment arrangements were highlighted as part of the original
report to the Resource Committee. 
Cleland Sneddon
Chief Executive 
15 February 2023 
Link(s) to Council Values/Priorities/Outcomes
 Accountable, effective, efficient and transparent 
Previous References
 Report to Finance and Corporate Resources Committee of 15 February 2023 
List of Background Papers
 None 
Contact for Further Information
If you would like to inspect the background papers or want further information, please
contact:- 
Pauline MacRae, Administration Adviser
Ext: 4108  (Tel: 01698 454108)
E-mail:  pauline.macrae@southlanarkshire.gov.uk
83

Page 84

84

Page 85

Agenda Item 
Report to: Executive Committee
Date of Meeting: 1 March 2023
Report by: Director, Health and Social Care 
Subject: South Lanarkshire Integration Joint Board Annual
Performance Report 2021/2022 
1. Purpose of Report
1.1. The purpose of the report is to:- 
 present the South Lanarkshire Integration Joint Board’s (IJB) Annual Performance
Report 2021/2022 
2. Recommendation(s)
2.1. The Executive Committee is asked to approve the following recommendation(s):- 
(1) note the content of the report. 
3. Background
3.1. Section 42 of the Public Bodies (Joint Working) (Scotland) Act 2014 requires that
Annual Performance Reports (APR) are prepared by an Integration Authority – i.e. the
Integration Joint Board (IJB) in a South Lanarkshire context.  The 2014 Act obliges
that the APR should cover the preceding year’s activity and be published four months
after the end of that reporting year. 
3.2. The purpose of the APR is to ensure that performance is open and accountable, whilst
at the same time providing an overall assessment of performance in relation to
planning and carrying out integration functions.  The APR is also of interest to the
Health Board and South Lanarkshire Council in monitoring the success of the
integration arrangements they have put in place, as per the Integration Scheme. 
3.3. The Scottish Government issued Guidance for APRs in March 2016, with
recommended areas for inclusion, including:- 
 a summary of progress against the nine National Health outcomes using as a
minimum the 23 core national performance indicators
 Financial performance and best value 
4. Annual Performance Report 2021/2022 
4.1. The IJB’s Annual Performance Report 2021/2022 is attached, following agreement at
the IJB on 13 December 2022. 
4.2. As with previous years, this APR 2021/2022 is aligned to reporting progress against
the intentions outlined in the Strategic Commissioning Plan for that given year.  This
APR covers the final year of the 2019 to 2022 Strategic Commissioning Plan. 
13
85

Page 86

4.3. The Scottish Government have advised that, similar to last year, IJBs can delay the
release of their APR if they wish and as laid out in the Coronavirus Scotland Act (2020).   
4.4. Audit Scotland has previously made recommendations to the IJB relating to enhancing
the public accessibility of its formal publications, notably by encouraging greater use
of infographics where appropriate. 
5. Employee Implications
5.1. There are no employee implications associated with this report. 
6. Financial Implications 
6.1. The APR includes information on financial performance and best value.   
6.2. The IJB’s appointed External Auditor, Audit Scotland, is required to supply an audit
certificate outlining the findings of the audit process undertaken in relation to the IJB’s
Annual Accounts 2021/2022. The External Auditor’s Annual Audit Report 2021/2022
was duly completed and then presented to and approved at the IJB Performance and
Audit Sub-Committee meeting of 12 October 2022 in advance of the statutory
publication timescale of 31 October 2022. 
6.3. The External Auditor concluded that the financial statements of the South Lanarkshire
IJB for 2021/2022 give a true and fair view of the state of affairs and of its net
expenditure for the year and have, therefore, issued an unqualified independent
Auditor’s Report. This assurance is consequently reflected within the attached APR
for that same period. 
6.4. The External Auditors key messages include:- 
 Effective governance and decision-making arrangements were in place during
2021/2022. Integration Joint Boards across Scotland were operating in a volatile
and challenging environment in 2021/2022. The South Lanarkshire IJB had to
prioritise its health and social care response to the COVID-19 pandemic against
the backdrop of workforce and financial challenges that impacted on its capacity
to progress its planned service developments
 The IJB has enhanced the openness and transparency of its activities and
decision making through the introduction of live on-line streaming of the IJB and
the PASC meetings
 The IJB’s effective planning and communication helped in managing the system
- wide health and social care system pressures, including acute service
pressures, experienced during December 2021 and January 2022. The IJB Chief
Officer and their team, through both partners, created a prioritisation framework
that was reflective of the challenges it faced, with a focus on its most vulnerable
citizens. The Scottish Government circulated this framework to other Joint
Boards noting it as a template for good practice 
7. Climate Change, Sustainability and Environmental Implications 
7.1. There are no implications for climate change, sustainability or the environment in terms
of the information contained in this report. 
86

Page 87

8. Other Implications 
8.1. The APR presents progress in a range of areas that contribute to the mitigation of a
number of risks within the IJB Risk Register, notably:- 
 Demand pressures (Very High)
 Financial Sustainability (Very High)
 External Provider Resilience (High)
 Public Protection (Medium)
 Public Sector Duties (Medium)
 Transformation (Medium) 
8.2.  The APR 2021/2022 is aligned to reporting progress against the final year of the 2019
to 2022 Strategic Commissioning Plan. 
8.3. There are no other issues associated with this report. 
9. Equality Impact Assessment and Consultation Arrangements 
9.1.  This report does not introduce a new policy, function or strategy or recommend a
change to an existing policy, function or strategy and, therefore, no impact assessment
is required. 
9.2. The APR 2021/2022 is aligned to reporting progress against the final year of the 2019
to 2022 Strategic Commissioning Plan which was fully consulted upon. 
Soumen Sengupta
Director, Health and Social Care 
20 January 2023 
Previous References
 Strategic Commissioning Plan 2019 – 2022
 Annual Performance Report 2019/2020
 Annual Performance Report 2020/2021 
List of Background Papers
 Appendix 1 - Annual Performance Report 2021/2022 
Contact for Further Information
If you would like to inspect the background papers or want further information, please
contact:- 
Name: Martin Kane, Service Manager Performance and Support
Ext:  3743
Email: martin.kane@southlanarkshire.gov.uk 
87

Page 88

88

Page 89

South Lanarkshire 
Integration Joint Board
Annual Performance Report
2021/22
13
89

Page 90

2021/22Annual Performance Report
2
South Lanarkshire Integration Joint Board
Annual Performance Report 2021/22
Our Vision is
Working together to 
improve health and wellbeing 
in the community – 
with the community
90

Page 91

3
Contents
3
1. Foreword  4
2. The role of the integration joint board  6
3. Our progress: moving forward in the most challenging period on record 6
4. Fact file: what we did to meet our strategic priorities  7
5. Strategic overview  12
6. Governance and accountability  13
7. Risk 13
8. Performance against national indicators 14
9. Financial performance 2021 – 2022 17
10. Looking to the future 18
91

Page 92

2021/22Annual Performance Report
4
1. Foreword
We write these opening remarks at
a time when the environment our
teams and partners operate is more
challenging than anything we have
encountered in our entire history.
Influenza. The cost of living crisis.
Increasing morbidity as people live
longer. The continued impact of
Covid-19, and the many implications
the pandemic has had... 
These are just some of the
combining factors, constituting a
maelstrom of unparalleled pressure
that’s enveloped every facet of the
health and social care system.
With that ‘here and now in mind’,
with our unmitigated focus on
safely negotiating matters in hand,
the publication of an Annual
Performance Report (APR), which
reflects on the previous financial
year (1 April 2021 and 31 March
2022) could, understandably,
seem somewhat of an unnecessary
exercise, perhaps surplus to the
pressing demands of the current,
unprecedented situation.
Yet this a hugely important and
valuable document, now more 
than ever.
Why?
As you would expect, and as required of our
organisation, this report covers all the statutory/
governance requirements relating to performance.
It also sets the scene for going forward; we
endeavour to maintain the wellbeing of the
workforce; we continue to invest in key areas to
address the increased demand for services while
looking at how to redesign services to maximise 
the use of available resources. Of course, our 
Strategic Commissioning Plan has now been
refreshed to cover the period 2022/2025 
along with a Strategic Needs Analysis.
Crucially, the rigour and spirit of our Partnership
is a golden thread woven throughout the following
pages. As we touch on in section 3, the robust
and unbreakable fabric of that partnership has
prevailed despite pressures that have been nothing
short of manifold (or to use a now, well-worn
phrase ‘unprecedented’). Over the course of the
year, we’ve encountered well-publicised, national
challenges around workforce supply, the continued
adversity of the COVID-19 pandemic and ever-
increasing demand, to name but a few.
Yet, in this report, examples abound of
improvement and innovation that show that teams
have done so much more than “just cope”. Indeed,
at the time of writing, and as a result of those
efforts, we have a number of areas of work that in
contention for numerous high-profile awards and
are the subject of positive national interest.
There’s so much to be proud of and we thank our
staff and partners for their ongoing commitment.
We also recognise that in the current conditions
any sense of battle weariness would be completely
understandable (to put it mildly) within our staff
groups, partners and communities.
92

Page 93

5
Soumen Sengupta
Chief Officer, 
South Lanarkshire 
Integration Joint Board
Margaret Walker
Vice Chair,
South Lanarkshire 
Integration Joint Board
Lesley McDonald
Chair,
South Lanarkshire 
Integration Joint Board
This report acts as a reminder of the value 
of true partnership – and working together 
in tough times, united by a common purpose.
Right across our services, teams and
professions, quality – and resilience – 
is borne out of mutual respect and support
for each other; an emphasis on evidence-
based and solution-orientated collaboration;
and, fundamentally a unified commitment to
service users/patients, their carers and the
communities we serve.
And, finally, to answer the question above . . .
As much as this document is a look at the
rearview mirror, the concrete evidence of
outstanding achievement and exemplary
professionalism is a source of renewed
confidence - and bodes well - for whatever
twists and turns we have to collectively
negotiate in the road ahead.
93

Page 94

2021/22Annual Performance Report
6
2. The role of the integration joint board
• Takes forward the operational implementation of the
plan on behalf of the parties – SLC and NHSL
• Provides assurance to the IJB and the parties on
progress with the implementation of the plan
• Formal public body
• Develops and leads the strategy for Health and 
Social Care through the Strategic Commissioning Plan
• Issues ‘Directions’ to SLC and NHSL
Health and Social
Care Partnership
(Operational)
Integration 
Joint Board
(Strategic)
The progress made by the SLHSCP on the strategic
commissioning intentions and the key performance
indicators are reported regularly to the IJB which can
be accessed from the HSCP website.
2021/2022 represented a period where we not only
made marked, concrete progress against our strategic
priorities – we also established nationally-recognised
good practice across many disciplines.
In any ‘ordinary’ year, these achievements would be
noteworthy. It should be emphasised, however, that
these milestones were attained despite a maelstrom
of challenge. Variant strains of Covid-19, staffing
challenges, fluctuating availability of resources
combining with wider societal conditions and the
increased acuity of people - both in hospital and in 
the community – all added significant additional
pressure on our health and social care system.
3. Our progress: moving forward in 
the most challenging period on record
These pressures have been formally noted in the 
Audit Scotland Reports on Social Care and the NHS 
in Scotland. See: Social care briefing | Audit Scotland 
(bit.ly/social-care-briefing) and 
NHS in Scotland 2021 | Audit Scotland 
(bit.ly/nhs-in-scotland-2021)
Testament to the resilience, drive and commitment of
our staff and partners, the following quick-guide fact file
provides a ‘snapshot’ of objectives attained, progress
made and the continued evolution of safe, innovative
and highly effective health and care - during the most
challenging period on record.
94

Page 95

7
4. Fact file: what we did to 
meet our strategic priorities
Strategic priority: 
Supporting the delivery of 
core and statutory duties
What we did:
Protected our most vulnerable 
and our staff
• The safety of those in our care - and of our staff - is
our fundamental priority. A prioritisation framework
was established, which took all available information
to inform live decision making on the deployment of
resources to prioritise support to the most vulnerable
in our communities.
• The Scottish Government circulated the approach to
other IJBs noting it as a ‘template for good practice.’
Kept people safe
• At the turn of the year, health and care services
across South Lanarkshire were faced with escalating
pressures, particularly pronounced amongst the care
at home workforce.
• A range of measures were activated to prioritise
community health and care provision for those
people at most risk within local communities with
Care at Home recommencing on a careful footing to
reintroduce full supports.
Invested in an interactive tool to 
assist adult support and protection
decision making for vulnerable adults
• The app was successfully
downloaded by partners 
across South Lanarkshire
including over 
1000 care at home 
staff as part of 
the pilot stage.
Established a Partnership-wide 
daily safety briefing
• A daily safety brief involving district nurses, allied
health professionals, social workers and care at
home staff enabled partners to come together
to discuss patient safety concerns, supporting a
collaborative approach to risk assessment and risk
management in the delivery of person-centred care.
Launched a campaign
against violence 
and aggression
Health and social care continues to be
a positive, vibrant and rewarding sector
to work in, whether that be in primary
care, community, hospital or with one of our partners. 
As much as it’s very challenging it is very rewarding –
most people are patient and very appreciative. Sadly,
however, during the period we continued to hear reports
from our staff that they are on the receiving-end of
unpalatable behaviours from a minority.
• A high-profile campaign featuring staff from 
South Lanarkshire HSCP taking a stand against 
those who direct any form of abuse to health and
social care professionals can be viewed here: 
https://vimeo.com/682751507 Protecting
vulnerable
adults
1000 
care at home staff as 
part of the pilot stage.
95

Page 96

2021/22Annual Performance Report
8
Strategic priority: 
Improve unscheduled care
What we did:
• Progressed the Discharge without Delay (DWD)
programme and Home First 
Home First is a key part to our local response to the
pressures in health and social care. It is based on
three elements. Firstly, people can be cared for at
home (or as close to home as possible). Secondly,
prevention of avoidable admissions to hospital and
thirdly, where hospital admission is necessary, Home
First seeks to support timely discharge.
• We boosted the capacity of 
local integrated supported teams (ICST) 
with an initial investment package of £4 million
which included additional nursing staff. ICSTs
combine the expertise of a variety of health and
social care professionals working together.
• Multi-agency Home First teams have also 
been established in Lanarkshire’s hospitals. 
Their work is part of the discharge without delay
(DwD) programme, which aims to establish a clear
timeframe of when someone will go home - at the
earliest possible stage - with community, hospital
staff and other partners working together closely. 
Between November 2021 and May 2022 90 patients
were discharged from hospital through Home First. 
Of those patients requiring a care at home package 
42% were either stopped or reduced
following assessment. 
For those requiring end of life
care patients were provided
with holistic care with most
patients able to die at home.
• The End-of-Life pathway team, who provide holistic
care to patients approaching end of life within a
homely setting, are also a key part of the approach.
They work on the premise that no end-of-life care
patients should suffer unnecessary delays in their
discharge from hospital and that all health and 
social care needs will be delivered by the 
community nursing team.
Note: In the summer 2022 members of South Lanarkshire
Integration Joint Board (IJB) showed their support for the
ongoing phase, approving £5.428m of additional investment
to consolidate progress made. South Lanarkshire Health
and Social Care Partnership’s (SLHSCP) Home First
triumphed in the Integrated Care category in the 2022
Scottish Health Awards. The evening recognises excellence
across health and social care services.
Case Study
Assessing a person in their own familiar
environment, as opposed to a clinical setting, 
can be less stressful for them. In turn, that
enables staff to gather a much more accurate
picture of a person’s needs. This is crucially
important to ensuring the right package of care
is set out, whilst supporting independence. When
Jessie Turner was admitted to hospital last year
having suffered a stroke, she feared she might
not return to her Cambuslang home. Having only
just recovered from a hip operation, the still active
94-year-old was convinced that her much-prized
independence was at risk. Thanks to the Home
First programme, she has been able to recover
and rehabilitate in the comfort and security of the
house she’s lived in for decades. 
I don’t know where I would be without the
carers who come in every day, said Jessie.” 
“I feel so fortunate. Thanks to Home First, 
my home carers, the hospital physiotherapists,
and occupational therapists all worked together
and planned things so that I could not only get
back to my home but live well there.
“Having this team of people in my life has
made more difference than I could ever
have imagined, medically, practically and
emotionally and I cannot thank them enough.
It’s been life changing. 
Read Jessie’s full story: bit.ly/jessie-praises-care.
96

Page 97

9
Strategic priority: 
To promote self-care/management 
and mental health and wellbeing
What we did:
Launched a 
Suicide Prevention app
• The app has been downloaded 1,498 times 
and has useful information to help keep people safe
and provide guidance on how to look out for others.
Supported adults in their recovery 
with alcohol and drug misuse
• The Community Addiction and Recovery Service
(CAReS) brought together NHS and SLC staff to form
South Lanarkshire’s first integrated addictions service
to support adults with their recovery from problematic
alcohol and drug use. The service will provide
assessments and interventions to assist individuals in
better managing their alcohol and drug-use.
Supported people through 
assistive technology
Strategic priority: 
To promote early intervention, 
prevention and health improvement
What we did:
Supported children and young people
with complex needs in self-care 
through on-line videos
• 2021/22 saw an increase in requests for
occupational therapy for children and young people
by 25%. The use of on-line videos increased our
capacity and reduced waiting times for more
specialist occupational therapy interventions which
has transformed how families receive early support.
Supported safe care for 
people in care homes
In Lanarkshire, the Care Home Assurance Tactical Group
(CHAT), composed of senior health board, 
local authority and care home 
representatives, was
established in the early
stages of the pandemic to
support care homes negotiate
the many challenges Covid
presented and improve the
healthcare for adults and older
people living in care homes
and to support staff. 
Fire safety sensors and falls detectors 
were the most frequently requested 
assistive technology peripherals 
in 2021/22.
Keysafe installations increased by
Care and Repair technicians carried out 
2046 assistive technology visits 
to community alarm service users’ 
homes during 2021/22, and increase by
• Demand for assistive technology increased by
62%
37%
with 2287 assistive technology
items installed during 2021/22.
on the previous year. 
39%
with 900 visits 
completed during 2021/22.
97

Page 98

2021/22Annual Performance Report
10
This included:
• Infection Prevention and 
Control (IPC) resources were
increased with advice, guidance
and support. Where necessary focused work 
could be undertaken on the prevention of infection.
• While some measures changed or stepped down
as the infection rate reduced, vaccination measures
have been successful, CHAT continued to support
care homes jointly with other arranged visits to
ensure monitoring, assurance and support as well as
strengthening the partnership working relationship.
• This group coordinated the COVID-19 and Flu
vaccination programme for care home residents and
staff ensuring they were prioritised. CHAT monitor
individual care home data, support and encourage
uptake to ensure high levels of compliance.
Supported care home staff wellbeing
• Recognising the challenges the care home workforce
was facing in the early stages of the pandemic, a
number of key staff working alongside Lanarkshire’s
care homes responded proactively; by forming a
wellbeing group. The group was set up to tailor
supports that would be effective, targeted and
available to all care home staff, regardless of role or
employer/owner.
• The group is made up of representatives from North
and South Lanarkshire HSCPs, NHS Lanarkshire,
Scottish Care and, most importantly, members of the
frontline care home workforce themselves. Nursing
staff, clinical psychologists and a communication
adviser supported (and are part of this team too).
• The group’s aim has been to ensure care home staff
are supported. This has ranged from the provision 
of simple wellbeing tools, supporting and nurturing 
a culture of natural peer-to-peer support . . . 
to clear access to clinical support for those who
require mental health assessment and intervention.
Note: The Care Home Wellbeing Group were finalists
at the 2022 Scottish Health Awards for the Care
for Mental Health Award. The approach has been
recognised as good practice across the UK.
Progressed the Primary Care
Improvement Plan (PCIP)
PCIP supports the delivery of the national 2018 General
Medical Services (GMS) contract which, in essence,
aims to refocus the role of GPs as expert medical
generalists - working with a wider team to provide more
care in the community.
Key achievements included:
• The community link worker (CLW) programme 
was implemented and rolled out during the pandemic.
A CLW is a non-clinical practitioner aligned to a cluster
of GP practices who works directly with patients to
help them navigate and engage with wider services.
They often serve a socio-economically deprived
community or assist patients who need support
because of the complexity of their conditions. 
CLWs supported almost 
5000 local people 
since the service was set up in March 2021.
• Improved outpatient musculoskeletal physiotherapy
15% of total demand for outpatient
musculoskeletal physiotherapy is from patients
with knee symptoms. The pandemic accelerated
improvement work with this cohort of patients with
the establishment of a new pathway. To date 
306 patients with knee Osteo Arthritis (OA) 
are being managed through this work. This also
builds on the MSK Website where information 
and evidence based advice and exercise for 
18 common conditions, including knee OA, 
is available for patients and clinicians to help 
manage MSK conditions.
• Achieved the vaccination transformation programme 
All vaccinations are now provided by 
NHS Lanarkshire’s vaccination service – 
with the exception of travel vaccinations 
which are delivered by certain
community pharmacies. 
GP practices no longer have
responsibility for providing
vaccinations. This service 
was delivered and transferred
on time, by the deadline of 
1 April 2022.
98

Page 99

11
Strategic priority: 
Supporting carers
What we did:
• Continued to work in partnership with
carers organisations. Recognising the
important contribution of informal/unpaid
carers a Carers Partnership Group meets regularly
consisting of a wide range of third sector organisations
and is progressing the development of a new 
South Lanarkshire Carers Strategy.
• Contributed to the Care Inspectorate Carer Survey
on carers experiences of adult social care services in
supporting carers to maintain their quality of life.
• In January 2022, the Scottish Government announced
additional funding for local Carers Centres to expand
vital support services for unpaid carers during the
winter period. Shared Care Scotland distributed
this funding through Time to Live delivery partners.
Lanarkshire Carers is the Time to Live delivery partner
for Lanarkshire. Key findings from Winter funding
impact report (April 2022) highlighted the following:
• 949 carers benefitted from 
Carers Winter Funding Package in Lanarkshire
• 781 individual grants awarded to carers
• £268,554 worth of individual
grants awarded, paid directly to carers within 
14 days of receipt of payment information
• £344 average 
grant amount awarded
• 123 new carers engaged 
with Lanarkshire Carers 
as a result of the funding
• South Lanarkshire Young Carers (SLYC)
Action for Children have 99 young
carers registered with the service.
Young carers have been supported to
access funding to support them in their caring role.
Awareness raising through partnered schools has
identified new young carers. In February 2022 SLYC
successfully applied for winter wellbeing funding which
was used to provide breaks and enhancing gaming.
Strategic priority: 
The provision of suitable and
sustainable housing and 
delivering intermediate care
What we did:
Allocated 
20 
technology enabled homes
• Within the Blantyre Care development, 
8 one-bedroom bungalows and 12 one- and 
two-bedroom flats were allocated to tenants based
on assessed need and defined eligibility criteria.
The homes were designed to be fully accessible
and embrace modern technology solutions for
independent living. These solutions range from simple
ideas that you would find in any smart home (such
as voice activated lights) to more advanced and
specialised equipment (such as for fall detection).
Note: At the Chartered Institute of Housing Excellence
Awards 2022, the technology-enabled housing within the
Blantyre development won the award for Excellence in
Health and Wellbeing, recognising the work undertaken
during the period of this APR. South Lanarkshire’s
Health and Social Care Partnership have been working
in collaboration with the council’s Housing and Technical
Resources and Cruden Building (Scotland) Limited on
the multi-million-pound development, supported by
funding from the Scottish Government.
99

Page 100

2021/22Annual Performance Report
12
Case Study
Ms M, who moved into a tech enabled home 
said she loves it but couldn’t believe it was
just for her and gave the development a ringing
endorsement. Due to her disability Ms M 
requires a wheelchair and said: 
It is the most beautiful wee house that
I have moved into. The kitchen is massive I
thought they had made a mistake and given
me a home like this, but it was for me. 
“I really love it. I feel a lot of contentment in
here.” “I have had loads of visitors, and I am
really grateful to all the friends who helped
make my move so easy. 
To make things happen 
our key enablers:
Supported our workforce
• Our workforce is our largest resource
therefore maintaining the safety of the workforce,
including provision of wellbeing support, has been
paramount. Access to wellbeing supports have
been made available to all staff such as wellbeing
seminars, self-help guides and educational
programmes alongside regular management contact
to support physical and mental wellbeing.
• We protected our staff by making sure
they had access to PPE and provided
rest areas to support their wellbeing.
Advanced our learning
• We advanced our learning and work
with a number of academic institutions.
Successful student placements with
Glasgow Caledonian University (GCU) in
2021 by the physiotherapy service has led to offering 
38 level 3 students an unpaid placement
within NHS Lanarkshire for eight weeks in 2022.
• Five clinical educators were seconded for one day a
week over five months which led to changes in clinical
practice and the educators redesigned the placement
approach. Meanwhile, in the field of research,
developments with GCU include falls and rehabilitation,
physiotherapy and podiatry. Research with Strathclyde
university include stroke and diabetic foot ulceration.
Ensured organisational resilience
• Partnership debriefing allowed the sharing of information
on the challenges and key lessons for partners involved
in the response to the COVID pandemic within the
Lanarkshire Resilience Partnership.
• Representatives across the HSCP were actively involved
throughout NHS Lanarkshire’s Strategic Command
Structure. This ensured alignment of approach, 
support and communication throughout the period.
Increased public access to the IJB 
by making use of technology
• To enhance openness and transparency the IJB
have improved accessibility of meetings. From March
meetings of the IJB and the Performance and Audit
Sub-Committees were livestreamed with recordings
made available on South Lanarkshire Council’s
YouTube channel.
Reviewed our Integration Scheme
• A review of the South Lanarkshire Integration
Scheme was undertaken in 2021/2022 completed in
accordance with statutory requirements resulting in
no material changes to delegated functions.
Performance improvement objectives are wide
ranging and take account of complex national
legislation and strategic priorities. The Public
Bodies (Joint Working) (Scotland) Act 2014 sets
out the framework for integrating health and social
care. There is a range of other legislation, policies,
guidance and proposals which have a bearing on
the work that the IJB progresses, and these are
listed in detail in the following document available
here: https://bit.ly/3W2lyMi.
5. Strategic Overview
100

Page 101

13
6. Governance and accountability
The governance framework within the IJB is set
out in the South Lanarkshire IJB Code of Corporate
Governance which comprises of the systems,
processes, culture and values by which the IJB is
directed and controlled.
The IJB has well-established
governance and decision-making
arrangements in place. 
The governance structure for South Lanarkshire HSCP
provides a robust and streamlined process for efficient
and effective Partnership decision making. The IJB
holds the ultimate decision-making and commissioning
authority, with its assurance responsibilities strengthened
by the important scrutiny provided by its Performance
and Audit Sub-Committee (PASC).
The Strategic Commissioning Group (SCG) is a multi-
agency forum comprised of professional key leaders
across the HSCP, South Lanarkshire Council, NHS
Lanarkshire and Third, Independent and Carers sectors.
The group provides support and delivery of the thirteen
priorities and national health and wellbeing outcomes of
our SLHSCP Strategic Commissioning Plan.
It also ensures the delivery of NHS Lanarkshire objectives
in relation to service transformation and financial prudence
as well as relevant elements of South Lanarkshire Council’s
Connect Plan 2017/2022. One function of the SCG is to
ensure effective links to each of our four localities.
In 2021/22 the IJB has reviewed and updated its
Integration Scheme, had its Records Management Plan
approved by the Keeper of the Records, and submitted
a climate change and sustainability statement.
7. Risk
The IJB has undertaken significant work to understand
the importance of risk appetite and risk tolerance
relating to the implementation of its strategic priorities. It
is recognised by the IJB that there cannot be a ‘one size
fits all’ approach to this as it will be very much assessed
depending on the strategic priority under consideration.
For example, where statutory imperatives require to
be fully discharged, the IJB may take a more cautious
approach but conversely in terms of pursuing an early
intervention and prevention strategy, the IJB may be
more open and stretch its overall appetite/tolerance.
With this in mind, the IJB will have a flexible approach
to risk appetite and tolerance, which will be considered
on a case-by-case basis and regularly reviewed by the
IJB and the supporting Sub-Committee structure.
The IJB regularly reviews its Risk Register through its
Performance and Audit Sub-Committee. As the IJB and
the HSCP have matured it is currently undertaking an
exercise to review all risks in line with the new Strategic
Commissioning Plan 2022/2025. This aligns to the
review of strategic directions which was undertaken and
reported to the IJB on 29 March 2022. Going forward
into 2022/23 our key risks highlight the challenges
presented in this report.
They are identified as follows:
Very High or High Risks
• Demand pressures
• Workforce availability
• Financial sustainability
• External provider resilience
Medium/Lower Risks
• Public Protection
• Public Sector Duties
• Transformation
• National Care Service
101

Page 102

2021/22Annual Performance Report
14
Ministerial Strategic Group (MSG) Indicators
MSG Indicator 2017/18 2018/19 2019/20 2020/21 2021/22
Number of emergency
admissions
39,661 40,996 40,460 32,537 37,044
Number of unscheduled hospital
bed days (acute specialties)
229,726 233,385 238,503 200,687* 238,260
Number of A&E attendances 105,876 109,627 110,095 83,441 104,080
Acute bed days lost to delayed
discharges
41,187 38,473 46,570 22,585 35,941
% of last six months of life
spent in Community setting*
87.6% 88.5% 88.2% 90.8% Not available
Balance of care: 
Percentage of 75+ population 
at home unsupported*
83.5% 83.0% 83.6% 84.7% Not available
*Please note that figures presented will not take into account the full impact of COVID-19 during 2020/21 and 2021/22.
The IJB seeks to promote a culture of continuous
improvement to deliver better outcomes for individuals and
communities. Our Performance Management Framework
provides the structure by which the IJB can make
informed decisions on future priorities, using performance
information to identify and drive improvement work.
A core suite of indicators has been agreed nationally to
ensure consistency across all IJB areas. Nine of these
indicators are survey based or qualitative measures
which are gathered every two years from the national
Health and Social Care experience survey, with the
remaining indicators being regular health and social
care performance measures.
8. Performance against national indicators
A summary of the MSG (Ministerial Steering Group)
indicators in South Lanarkshire for currently available
data showing the year-on-year comparison between
April 2021 and March 2022 is detailed below.
The performance trends below are 
reflective of the fact that COVID-19
restrictions significantly impacted more on
access to services in the year 2020/2021
when compared with 2021/2022.
102

Page 103

15
National Indicator 2019/20 2021/22
Percentage of adults able to look after their health very well or quite well 92.1% 89.9%
Percentage of adults supported at home who agreed that they are 
supported to live as independently as possible
84.2% 82.2%
Percentage of adults supported at home who agreed that they had a say 
in how their help, care, or support was provided
75.3% 65.6%
Percentage of adults supported at home who agreed that their health 
and social care services seemed to be well co-ordinated
70.5% 64.3%
Total % of adults receiving any care or support who rated it as 
excellent or good
80.5% 70.2%
Percentage of people with positive experience of the care provided by 
their GP practice
73.2% 56.4%
Percentage of adults supported at home who agree that their services and
support had an impact on improving or maintaining their quality of life
78.1% 80%
Total combined % carers who feel supported to continue in their caring role 31.1% 28.7%
Percentage of adults supported at home who agreed they felt safe 82.0% 80.7%
National Indicator 2019/20 2020/21 2021/22 Comments
*Premature 
mortality rate per
100,000 persons
430.5 493.4 472* Premature mortality rates have improved since
last year but remain higher than 2019/20.
Premature mortality rates are above Scotland
levels during 2021 and remain heavily
influenced by Covid.
*Emergency
admission rate (per
100,000 population)
14,222 11,999 12,840 Emergency admission rates have increased
since 2020/21. This can be attributed to
the impact of the pandemic. This is true
across Scotland as a whole. However, it is
anticipated that the development of the Urgent
Care Pathway will have a positive impact on
unscheduled care performance.
*Emergency 
bed day rate (per
100,000 population)
123,085 97,662 115,799 Emergency Bed day rates have increased for
SL residents and above the Scotland level.
This indicator has been affected by the 
Covid emergency.
*Emergency
readmissions to
hospital within 28
days of discharge (rate
per 1,000 discharges)
97 112 103 The rate of emergency readmissions is below
the average level for Scotland, and the rate for
SL residents has decreased since last year.
103

Page 104

2021/22Annual Performance Report
16
National Indicator 2019/20 2020/21 2021/22 Comments
*Proportion of last
6 months of life
spent at home or in a
community setting
88.2% 90.8% *89.5% One of the key strategies for the HSCP is
shifting the balance of care from hospital
to community settings. The Partnership
continues to make steady progress towards
this aim.
*Falls rate per 1,000
population aged 65+
21.5 19.3 *22.4 Falls can have a significant impact on quality
of life. We have developed a falls action
plan and organised services to support the
prevention of falls. Performance has slightly
decreased against this indicator. However, it is
performing well against the Scotland rate.
*Proportion of care
services graded
'good' (4) or better
in Care Inspectorate
inspections
79.9% 80.1% 76.1% Performance has declined in this area but is
above the Scotland level.
*Percentage of 
adults with intensive
care needs receiving
care at home
63.7% 63.4% 64.8%* People want to stay at home for as long as
possible rather than care home or hospital. We
have steadily improved our performance and
intend to improve through actions outlined in
our Strategic Commissioning Plan 2022-2025.
Number of days
people spend in
hospital when they
are ready to be
discharged (per
1,000 population)
1,156 544 910 This has been an indicator which has been
a major focus for the HSCP. Working in
partnership with NHS and Social Care has
shifted reliance on hospital care. 2021/22
rates will be heavily impacted by Covid.
**Percentage of health
and care resource
spent on hospital stays
where the patient
was admitted in an
emergency
23.7% 19.0% 23.0% SL H&SCP strategic commissioning plan
outlines how we intend to develop strong
community services to reduce the number of
unplanned admissions.
*For indicators 11, 12, 13, 14, 15, 16 and 18, 
Calendar year 2021 is used here as a proxy for
2021/22 due to the national data for 2021/22 being
incomplete. We have done this following guidance
issued by Public Health Scotland to all Health and
Social Care Partnerships. Figures presented may not
fully reflect activity during 2021/22 due to the varying
impact of COVID-19 at different points of the pandemic.
**For Indicator 20 NHS Boards were not able to provide
detailed cost information for 2020/21 due to changes
in service delivery during the pandemic. As a result,
Public Health Scotland have not provided information
for indicator 20 beyond 2019/20. PHS previously
published information to calendar year 2020 using costs
from 2019/20 as a proxy but, given the impact of the
COVID-19 pandemic on activity and expenditure, Public
Health Scotland no longer consider this appropriate.
104

Page 105

17
Financial Performance
2021/22
IJBs across Scotland were operating in a volatile and
challenging environment in 2021/2022. The South
Lanarkshire IJB had to prioritise its health and social care
response to the Covid-19 pandemic against the backdrop
of workforce and financial challenges that impacted on its
capacity to progress its planned service developments.
The financial envelope available to the IJB in
2021/2022 totalled £633.837m. 
The South Lanarkshire Council partner contribution was 
£146.735m. The NHS Lanarkshire partner
contribution was £487.102m and included
resource transfer funding and social care funding
which was transferred to the South Lanarkshire Council
partner to support expenditure across Social Care and
Housing Services.
Financial information is part of our performance
management framework with regular reporting of
financial performance to the IJB. National Health and
Wellbeing Outcome 9 also requires resources to be used
effectively and efficiently in the provision of health and
social care services. The resources available to the IJB to
deliver the delegated functions set out in the Integration
Scheme and the Strategic Commissioning Plan (SCP)
are comprised of the financial contributions from South
Lanarkshire Council (SLC) and NHS Lanarkshire (NHSL).
The financial position for public services continues to be
challenging. Notwithstanding these pressures, within the
financial envelope available to each partner and following
a process of consultation, in March 2021 the IJB agreed
a financial plan 2021/2022 to ensure a balanced budget
was achieved by 31 March 2022. The detail of this plan
is available here: https://bit.ly/3QvVAzL.
9. Financial Performance 2021/22
The IJB Financial Position 
at 31 March 2022
The financial monitoring report for the year ended 
31 March 2022 confirmed an underspend of £63.9m
(NHSL - £57.1m; SLC £6.8m). The total SLC underspend
was £8.8m and £2m funding was returned to the 
SLC partner, resulting in and underspend of £6.8m for
the IJB. The main underspends were as follows:
£33.2m of uncommitted
2021/2022 Covid-19 funding
retained to meet Covid-19
costs in 2022/2023
£9.8m in respect 
of the Primary Care
Improvement funding
£3.0m in respect 
of the Alcohol and Drug
Partnership funding
£1.2m in respect of
the additional funding from
Scottish Government for
Multi-Disciplinary teams
£4.9m on services hosted 
by South Lanarkshire IJB
£5.0m budgets within 
Health Care Services
105

Page 106

2021/22Annual Performance Report
18
Alongside the continued demands of the pandemic,
we planned for the future and undertook considerable
engagement with stakeholders to develop a new
Strategic Commissioning Plan 2022/2025 from 
August 2021 through to its approval on 25 March 2022.
This activity has been favourably audited. 
Read full audit report here: 
bit.ly/SLIJB-meeting-papers-20-september.
10. Looking to the future
£3.7m in respect 
of the additional funding 
from Scottish Government 
for expanding Care at 
Home capacity
£1.3m in respect of 
the additional funding from 
Scottish Government for
interim care
£0.9m of
uncommitted funding
for future strategic
commissioning plan priorities
£0.9m in relation to other 
funding received or generated, 
required in 2022/2023.
The Scottish Government allocated funding in March
2022 for Covid-19 costs incurred in 2021/2022 and for
future years. The balance of the funding at 31 March
2022 of £33.2m was transferred to an earmarked
reserve (ring fenced funding). The underspend of
£9.8m on the Primary Care Improvement funding was
also transferred to an earmarked reserve (ring fenced
funding) at the year end.
In October 2021, the Scottish Government announced
funding of £300m in response to winter planning and
system pressure work that had been undertaken. The
underspends in relation to this funding are referenced
above and were transferred to both an earmarked
reserve (voluntary) and the contingency reserve.
Our plan on a page
provides a clear
summary (overleaf).
106

Page 107

19
Section 2: Plan on a page
Context:
•  Changing needs of the population
•  Meeting the needs of all our
communities fairly and equally
•  Applying evidence of what works
•  Best use of the public pound
•  Feedback from our communities –
what is important to people
Values: Empathy ElevateEmpower
Strategic Commissioning Plan
South Lanarkshire Integration Joint Board
2022–25
Vision:
Working together to improve health 
and wellbeing in the community – 
with the community
Plan on 
a page
• Evidence
• Innovation
• Learning
• Partnerships
• Technology
• Leadership
• Our staff
• Our communities
• Our commitment
Key enablers
Our priorities
Priority 1: Sustaining statutory social
care and core health care functions
Priority 2: Greater emphasis on early
intervention, prevention and inequalities
Priority 3: Addressing mental 
health and addictions
Priority 4: Improving unscheduled care 
and optimising intermediate care
Priority 5: Supporting carers
Priority 6: Promoting self-care
and self-management including
technology enabled care
Priority 7: Improving
transitional arrangements
Priority 8: Facilitating single
point of access and increasing
access to seven-day services
Priority 9: Investing in 
enablers to support integration
Priority 10: Promoting suitable
and sustainable housing
Priority 11: Contributing 
to homelessness prevention 
and reduction
Priority 12: 
Responding to 
the impact of 
the COVID-19 
pandemic
https://vimeo.com/739607180
https://vimeo.com/689689109/cb5228bd69
107

Page 108

Produced for South Lanarkshire Integration Joint Board by Communications and Strategy. 063881/Jan23
If you need this information 
in another language or format, 
please contact us to discuss how 
we can best meet your needs.
Phone: 0303 123 1015
Email: equalities@southlanarkshire.gov.uk
108

Page 109

Report
Agenda Item 
Report to: Executive Committee
Date of Meeting: 1 March 2023
Report by: Executive Director (Finance and Corporate Resources)  
Subject: Representation on Recruitment Committee 
1. Purpose of Report
1.1. The purpose of the report is to:- 
 advise on action taken, in terms of Standing Order No 37(c), because of the
timescales involved, by the Executive Director (Finance and Corporate
Resources), in consultation with the Chair and an ex officio member, to approve a
change in membership of the Recruitment Committee
[1purpose]
2. Recommendation(s)
2.1. The Committee is asked to approve the following recommendation(s):-
[recs]
(1) that the following action taken, in terms of Standing Order No 37(c), by the
Executive Director (Finance and Corporate Resources), in consultation with
the Chair and an ex officio member, be noted:- 
 to approve a change in membership of the Recruitment Committee in
that Councillor Cowan to replace Councillor Macdonald as a substitute
member 
3 Background
3. 1 The Council, at its meeting on 18 May 2022, approved its representation on
committees, with authority delegated to the Chief Executive, in consultation with the
Leaders of the political and independent groups, to finalise membership of
committees on the basis of the number of members and associated political
composition approved by the Council. 
4. Amendment to Representation on Recruitment Committee
4.1 On 7 February 2023, a request was received from the Business Manager of the SNP
Group to replace Councillor Macdonald with Councillor Cowan as a substitute
member of the Recruitment Committee. 
5. Employee Implications
5.1. None. 
6. Financial Implications
6.1 None. 
7. Climate Change, Sustainability and Environmental Implications
7.1. There are no climate change or environmental implications as a result of this report. 
14
109

Page 110

8. Other Implications
8.1. There are no issues in terms of risk arising from this report.   
8.2. In line with usual practice, Councillor Cowan will undertake the necessary training
prior to participating in any Recruitment Committee meeting. 
9. Equality Impact Assessment and Consultation Arrangements
9.1. This report does not introduce a new policy, function or strategy or recommend a
change to an existing policy, function or strategy, therefore, no impact assessment is
required.   
9.2. Consultation on representation has taken place as necessary. 
Paul Manning
Executive Director (Finance and Corporate Resources) 
9 February 2023 
Link(s) to Council Values/Priorities/Outcomes
 Accountable, effective, efficient and transparent 
Previous References
 South Lanarkshire Council - 18 May 2022 
List of Background Papers
 None 
Contact for Further Information
If you would like to inspect the background papers or want further information, please
contact:- 
Susan Somerville, Administration Manager
Ext: 4197 (Tel:  01698 454197)
E-mail: susan.somerville@southlanarkshire.gov.uk 
110