Page 1

Council Offices, Almada Street        
Hamilton, ML3 0AA 
Tuesday, 11 August 2026 
Dear Councillor 
Executive Committee 
The Members listed below are requested to attend a meeting of the above Committee to be
held as follows:- 
Date:  Wednesday, 19 August 2026
Time:  10:00
Venue: Hybrid - Committee Room 1, Council Offices, Almada Street, Hamilton,
ML3 0AA 
The business to be considered at the meeting is listed overleaf. 
Yours sincerely 
Paul Manning
Chief Executive 
Members
Maureen Devlin (Chair/ex officio), Gerry Convery (Depute Chair), Alex Allison, John Anderson,
Robert Brown, Andy Carmichael, Maureen Chalmers, Ross Clark, Andrea Cowan, Gladys
Ferguson-Miller, Elise Frame, Lynsey Hamilton, Cal Johnston-Dempsey, Gavin Keatt, Susan Kerr,
Ross Lambie, Eileen Logan, Katy Loudon, Ian McAllan, Catherine McClymont, Davie McLachlan,
Richard Nelson, Norman Rae, Mo Razzaq, Kirsten Robb, John Ross, David Shearer, Margaret B
Walker 
Substitutes
Walter Brogan, Poppy Corbett, Margaret Cowie, Celine Handibode, Graeme Horne, Martin Hose,
Hugh Macdonald, Kenny McCreary, Elaine McDougall, Mark McGeever, Graham Scott 
1

Page 2

BUSINESS 
1 Declaration of Interests   
2 Minutes of Previous Meeting
Minutes of the meeting of the Executive Committee held on 24 June 2026
submitted for approval as a correct record.  (Copy attached) 
5 - 36 
Monitoring Item(s) 
3 Revenue Budget Monitoring for Period 4 - 1 April 2026 to 10 July 2026
Report dated 27 July 2026 by the Executive Director (Finance and Corporate
Resources).  (Copy attached) 
37 - 42 
4 Capital Budget 2026/2027 and Monitoring for Period 4 - 1 April 2026 to 10
July 2026
Report dated 28 July 2026 by the Executive Director (Finance and Corporate
Resources).  (Copy attached) 
43 - 50 
5 Update to Funding
Report dated 22 July 2026 by the Executive Director (Finance and Corporate
Resources).  (Copy attached) 
51 - 54 
Item(s) for Decision 
6 Estate Strategy: 2026 to 2036
Report dated 29 July 2026 by the Executive Director (Housing and Technical
Resources).  (Copy attached) 
55 - 184 
7 Routes to Work South - Appointment of Independent Directors
Report dated 24 July 2026 by the Executive Director (Community and Enterprise
Resources).  (Copy attached) 
185 - 188 
8 Religious Representation on the Education Resources Committee
Joint report dated 15 July 2026 by the Executive Directors (Finance and
Corporate Resources) and (Education Resources).  (Copy attached) 
189 - 190 
9 South Lanarkshire Council Response to Pre-budget Scrutiny 2027/2028
Call for Views
Report dated 27 July 2026 by the Executive Director (Finance and Corporate
Resources).  (Copy attached) 
191 - 214 
10  End of Current Council and Preparations for the New Council
Report dated 16 July 2026 by the Executive Director (Finance and Corporate
Resources).  (Copy attached) 
215 - 222 
11  Land and Property Transfers and Disposals
Report dated 17 July 2026 by the Executive Director (Housing and Technical
Resources).  (Copy attached) 
223 - 228 
2

Page 3

Item(s) for Noting 
12  Annual Review of the South Lanarkshire Anti-social Behaviour Strategy
2024 to 2029
Report dated 14 July 2026 by the Executive Director (Housing and Technical
Resources).  (Copy attached) 
229 - 236 
13  Cost of Living Support
Report dated 23 July 2026 by the Executive Director (Finance and Corporate
Resources).  (Copy attached) 
237 - 244 
14  Council Complaints Report: SPSO Annual Overview 2025/2026
Report dated 27 July 2026 by the Executive Director (Finance and Corporate
Resources).  (Copy attached) 
245 - 254 
15  Resource Plans and Connect Reporting 2026/2027
Report dated 16 July 2026 by the Chief Executive.  (Copy attached) 
255 - 258 
Urgent Business 
16  Urgent Business
Any other items of business which the Chair decides are urgent. 
For further information, please contact:-
Clerk Name: Tracy Slater
Clerk Telephone: 07385 370089
Clerk Email: tracy.slater@southlanarkshire.gov.uk 
3

Page 4

4

Page 5

EXECUTIVE COMMITTEE 
Minutes of meeting held via Confero and in Committee Room 1, Council Offices, Almada Street,
Hamilton on 24 June 2026 
Chair:
Councillor Gerry Convery (Depute) 
Councillors Present:
Councillor Alex Allison, Councillor John Anderson, Councillor Walter Brogan (substitute for Councillor
Eileen Logan), Councillor Robert Brown, Councillor Andy Carmichael, Councillor Maureen Chalmers,
Councillor Ross Clark, Councillor Andrea Cowan, Councillor Margaret Cowie (substitute for Councillor
Maureen Devlin), Councillor Gladys Ferguson-Miller, Councillor Elise Frame, Councillor Lynsey
Hamilton, Councillor Celine Handibode (substitute for Councillor Gavin Keatt), Councillor Susan Kerr,
Councillor Ross Lambie, Councillor Katy Loudon, Councillor Ian McAllan, Councillor Catherine
McClymont, Councillor Mark McGeever (substitute for Councillor Norman Rae), Councillor Richard
Nelson, Councillor Mo Razzaq, Councillor Kirsten Robb, Councillor John Ross, Councillor Graham
Scott (substitute for Councillor Davie McLachlan), Councillor David Shearer, Councillor Margaret B
Walker 
Councillors' Apologies:
Councillor Margaret Cooper, Councillor Maureen Devlin (Chair and ex officio), Councillor Gavin Keatt,
Councillor Eileen Logan, Councillor Davie McLachlan, Councillor Norman Rae 
Attending:
Chief Executive’s Service
P Manning, Chief Executive; T Little, Head of Communications and Strategy
Community and Enterprise Resources
A Brown, Head of Enterprise and Sustainable Development
Education Resources
D Hinshelwood, Support Services Manager
Finance and Corporate Resources
J Taylor, Executive Director; K McLeod, Administration Assistant; M Milne, Head of Personnel
Services; T Slater, Administration Adviser; I Strachan, Head of Administration and Legal Services
Housing and Technical Resources
S Gibson, Executive Director; S Egan, Head of Housing Services;
Health and Social Care/Social Work Resources
S Sengupta, Director, Health and Social Care 
1 Declaration of Interests 
No interests were declared. 
2 Minutes of Previous Meeting 
The minutes of the meeting of the Executive Committee held on 20 May 2026 were submitted for
approval as a correct record. 
The Committee decided: that the minutes be approved as a correct record.  
2
5

Page 6

3 Revenue Budget Year-End 2025/2026 
A report dated 2 June 2026 by the Executive Director (Finance and Corporate Resources) was
submitted on the overall financial position of the Council’s General Fund Revenue Account and
Housing Revenue Account for the period 1 April 2025 to 31 March 2026. 
Information was provided on:- 
 the year-end outturn position across Resources, Joint Boards, Loan Charges, Corporate
Items and Council Tax, which was an underspend of £3.131 million after proposed transfers
to reserves
 the proposed increase to the probable outturn transfers to reserves to £60.206 million, as
detailed in Appendix 3 to the report
 proposed year-end transfers to reserves of £1.886 million, as detailed in Appendix 4 to the
report
 the additional non-recurring underspend of £1.356 million in the delegated budget to the
Integration Joint Board (IJB), proposed to be held in Reserves for use in future years
 the proposed use of the £3.131 million underspend, as outlined in section 4.22 of the report
 the Housing Revenue Account (HRA) breakeven position, after a transfer from reserves, as
outlined in section 5 of the report 
The Committee decided: 
(1) that it be noted that across Resources, Joint Boards, Loan Charges, Corporate Items and
Council Tax, the Council was showing a year-end underspend of £3.131 million after
proposed Transfers to Reserves, as detailed in section 4 and Appendix 1 of the report; 
(2) that the increase in the Probable Outturn Transfers to Reserves to £60.206 million from
£58.026 million, as detailed in Appendix 3 to the report, be approved; 
(3) that the additional year-end Transfers to Reserves totalling £1.886 million, as detailed in
Appendix 4 to the report, be approved; 
(4) that the additional non-recurring underspend of £1.356 million in the delegated budget to the
Integration Joint Board (IJB) be held in Reserves for use in future years, as detailed in
section 4.13 of the report; 
(5) that the proposed use of the £3.131 million underspend for 2025/2026, as outlined in section
4.22 of the report, be approved; 
(6) to note that this resulted in a breakeven position for the Council for 2025/2026; and 
(7) that the breakeven position on the Housing Revenue Account, as detailed in section 5 and
Appendix 5 of the report, be noted. 
[Reference: Minutes of 1 April 2026 (Paragraph 3)] 
4 Revenue Budget Monitoring for Period 2 - 1 April to 15 May 2026 
A report dated 2 June 2026 by the Executive Director (Finance and Corporate Resources) was
submitted on the overall financial position of the General Fund Revenue Account and the Housing
Revenue Account for the period 1 April to 15 May 2026 and a forecast for the year to 31 March
2027.  
6

Page 7

The report and associated appendices provided information on the:- 
 projected outturn for 2026/2027 for the Council’s General Fund Revenue Account
 General Fund Account for the period to 15 May 2026
 following key budget areas:-
 proposed transfers to reserves
 Loans Charges, Non-Domestic Rates and Empty Property Relief underspends
 packaging extended producer responsibility (pEPR)/teacher numbers and reduction in
class contact time (RCCT) funding
 Social Work Resources’ Children and Families Services
 Social Work Resources’ Adult and Older People Services
 inflation and price assumptions
 Housing Revenue Account position 
The Committee decided: 
(1) that the projected breakeven position on the General Fund Revenue Account for 2026/2027,
and the actual spend as at 15 May 2026, as detailed in Appendix 1 to the report, be noted; 
(2) that the proposed Transfers to Reserves, as detailed in sections 4.3 to 4.5 of the report, be
approved; and 
(3) that the projected breakeven position on the Housing Revenue Account for 2026/2027, and
the actual spend as at 15 May 2026, as detailed in Appendix 2 to the report, be noted. 
[Reference: Minutes of South Lanarkshire Council of 25 February 2026 (Paragraph 3)] 
5 Capital Budget Monitoring Final Outturn - 2025/2026 
A report dated 2 June 2026 by the Executive Director (Finance and Corporate Resources) was
submitted on:- 
 the outturn position of the General Services and Housing Capital Programmes for the year
ended 31 March 2026
 the projects, expressed in financial terms, which had been carried forward into 2026/2027 
Total spend on the General Services Capital Programme 2025/2026, as detailed in Appendix 1 to
the report, amounted to £57.570 million.  This compared to the budget of £67.712 million and
resulted in an underspend of £10.142 million.  This would be carried forward to the 2026/2027
financial year.  Details were provided in Appendix 2 on the reasons for the underspend and those
projects that would continue into 2026/2027.  Information was also provided on the year-end
accounting adjustments. 
The Housing Capital Programme 2025/2026, as detailed in Appendix 3 to the report, totalled
£87.740 million, with actual expenditure amounting to £85.782 million, an underspend of £1.958
million.  Details were given on the reasons for the underspend, which would be carried forward to
the Capital Programme 2026/2027. 
The Committee decided: 
(1) that the outturn on the 2025/2026 General Fund Capital Programme of £57.570 million, as
detailed in section 4.2 of the report, be noted; 
(2) that the carry forward of 2025/2026 projects into the 2026/2027 General Fund Capital
Programme totalling £10.142 million, as detailed in section 4.8 of the report, be approved; 
7

Page 8

(3) that the outturn on the 2025/2026 Housing Capital Programme of £85.782 million, as
detailed in section 5.2 of the report, be noted; 
(4) that £1.958 million of Housing Capital Programme be carried forward into 2026/2027, as
detailed in section 5.3 of the report; and 
(5) to note that the level of overall spend anticipated in 2026/2027, for the General Fund and
Housing Capital Programmes, was the subject of a separate report to this Committee, as
detailed in sections 4.9 and 5.3 of the report. 
[Reference: Minutes of 1 April 2026 (Paragraph 4)] 
6 Capital Budget 2026/2027 and Monitoring for Period 2 - 1 April 2026 to 15 May 2026 
A report dated 2 June 2026 by the Executive Director (Finance and Corporate Resources) was
submitted on:- 
 consolidation of capital budget monitoring to give a Council-wide summary of the 2026/2027
Capital Programme, including 2025/2026 carry forward
 progress on the Capital Programme for the period 1 April to 15 May 2026 
At its meeting on 25 February 2026, the Council agreed a General Services base budget for
2026/2027 amounting to £105.247 million.  Since the approval of this programme, there had been
a number of events that would impact the budget, namely, the approval of investments as part of
the 2026/2027 revenue budget and the finalisation of the year-end position for 2025/2026, as
detailed in section 4 of the report. 
Resources had also submitted proposed adjustments totalling £0.550 million.  A detailed
breakdown of those proposals was provided in Appendix 1 to the report and, if approved, the total
capital spending programme for 2026/2027 would be £109.502 million. 
Appendix 3 summarised the programme spend and funding for the General Fund.  Budget for the
period amounted to £1.767 million and, as at 15 May 2026, £1.899 million had been spent. 
The Housing Capital Programme for 2026/2027 amounted to £94.740 million, with an estimated
outturn of £94.740 million.  Budget for the period amounted to £3.617 million and, as at 15 May
2026, £3.617 million had been spent. 
The position on the General Fund Capital Programme and the Housing Capital Programme would
be monitored by the Financial Resources Scrutiny Forum. 
The Committee decided: 
(1) that the position of the General Fund Capital Programme, as detailed in section 4 of the
report, and the Housing Capital Programme, as detailed in section 5 of the report, be
approved; 
(2) that the adjustments to the General Fund programme, as detailed at Appendix 1 to the
report, be approved; and 
(3) that the revised programmes be monitored by the Financial Resources Scrutiny Forum. 
[Reference: Minutes of South Lanarkshire Council of 25 February 2026 (Paragraph 4)]  
8

Page 9

7 Update to Funding 
A report dated 3 June 2026 by the Executive Director (Finance and Corporate Resources) was
submitted on additional funding, totalling £12.054 million, which had been made available to the
Council by the Scottish Government and other external sources. 
The funding had been allocated as follows:- 
Revenue Funding 
Resource 2026/2027 
(£m) 
Community and Enterprise 4.884 
Finance and Corporate 0.945 
Housing and Technical 0.270 
Social Work 0.924 
Total 7.023 
Capital Funding 
Resource 2026/2027 
(£m) 
Community and Enterprise 5.031 
Total 5.031 
Overall Total 12.054 
The Committee decided: that the report be noted. 
[Reference: Minutes of 20 May 2026 (Paragraph 3)] 
8 Employee Workforce Monitoring Information - 1 April 2025 to 31 March 2026
Summary 
A report dated 19 May 2026 by the Executive Director (Finance and Corporate Resources) was
submitted on workforce monitoring information relating to the Council for the period 1 April 2025
to 31 March 2026, as follows:- 
 attendance statistics
 occupational health statistics
 accident/incident statistics
 disciplinary hearings, grievances and Dignity at Work cases
 employee development
 labour turnover/analysis of leavers and exit interviews
 recruitment monitoring
 Staffing Watch as at 14 March 2026 
The Committee decided: that the report be noted. 
[Reference: Minutes of 3 December 2025 (Paragraph 6)]  
9

Page 10

9 2027/2028 to 2028/2029 Revenue Budget Strategy 
A report dated 12 May 2026 by the Executive Director (Finance and Corporate Resources) was
submitted on the Budget Strategy for 2027/2028 to 2028/2029. 
Information was provided on:- 
 the anticipated budget gap for years 2027/2028 to 2028/2029, including information on the
Government Grant and the impact of budget decisions taken during the 2026/2027 budget
setting process
 the programme of Transformational Reviews ongoing across the Council
 how an increase in Council Tax could impact the budget gap
 the proposed timeline for the next steps of the budget
 the annual review of the Reserves Strategy
 financial management and resilience
 communication and engagement with elected members and the public
 the long-term financial strategy
 the risks for the budget 
The Committee decided: 
(1) that the Revenue Budget position for 2027/2028 to 2028/2029, as detailed in section 4 and
Table 2 of the report outlining the Budget Gap of £26.500 million, be noted; 
(2) that the Programme of Transformational Reviews, as outlined in section 5 of the report, be
noted; 
(3) to note that, in arriving at the Budget Gap, no account had been taken of any increase in
Council Tax; 
(4) to note that a strategy around increasing Council Tax could contribute to reducing the Budget
Gap, as detailed in section 6 of the report; 
(5) that the summary and next steps, including a timeline and Net Zero challenges, as outlined
in section 7 of the report, be approved; 
(6) that the longer-term outlook, as detailed in section 11 of the report, be noted; and 
(7) that the risks, as detailed in section 15.3 of the report, be noted. 
[Reference: Minutes of South Lanarkshire Council of 25 February 2026 (Paragraph 3)] 
10 Larkhall Leisure Centre Replacement – Full Business Case Glasgow City Region
City Deal – Larkhall Community Growth Area 
A report dated 10 June 2026 by the Executive Director (Community and Enterprise Resources)
was submitted setting out the Full Business Case (FBC) for the Larkhall Leisure Centre
replacement element of the Larkhall Community Growth Area City Deal project. 
The Council was one of 8 local authorities who, with the UK and Scottish Governments, were
signatories to the £1.13 billion Glasgow City Region City Deal.  The City Deal was made up of 20
key infrastructure projects that were intended to drive economic and inclusive growth across the
Glasgow City Region area.  The Community Growth Areas (CGAs) was one of 4 South
Lanarkshire projects, as outlined in the report.  
10

Page 11

Information was provided on:- 
 the governance arrangements for the City Deal initiative and the approval process for FBCs
 the proposal for the Larkhall Leisure Centre replacement project, as outlined in the FBC
Executive Summary attached as Appendix 1 to the report, which would provide a new-build
facility and be an essential element of the community infrastructure
 the project cost and funding share between the Council, Glasgow City Deal, the Shared
Prosperity Fund, Place Based Investment Fund, Regeneration Capital Grant Fund and
sportscotland 
The Committee decided: 
(1) that the Larkhall Leisure Centre replacement Full Business Case be approved; and 
(2) that grant funding of £3 million be sought in accordance with the City Deal Grant Distribution
Process, outlined in the Assurance Framework, in relation to the delivery of the project. 
[Reference: Minutes of 8 February 2017 (Paragraph 9) and Minutes of South Lanarkshire Council
of 26 February 2025 (Paragraph 2)] 
11 Pride in Place Programme - Hamilton Town Centre 
A report dated 10 June 2026 by the Executive Director (Community and Enterprise Resources)
was submitted providing an update on the Pride in Place Programme in respect of the appointment
of representatives to the Hamilton Town Centre Neighbourhood Board and associated
governance arrangements. 
The Chair of the Board requested that adverts and public notices be published seeking
expressions of interest for membership of the Board, the make-up of which would follow the criteria
set out in the UK Government Guidance. 
Thirty expressions of interest had been received and, following a shortleeting process, 13
candidates were invited for interview and recommended for appointment, as detailed in section
4.4 of the report.  The Board membership would also comprise the Chair, the local MP and MSP. 
Information was provided on:- 
 the proposed arrangements for future changes to membership of the Board, with any
decisions delegated to the Executive Director (Community and Enterprise Resources), in
consultation with the Chair of the Board, local MP and Chair of the Executive Committee
 the provisions for the replacement of elected representatives
 the governance and operational arrangements for the use of Pride in Place funding and
implementation of Board decisions
 the timescales for the next steps, including:-
 the submission of the proposed membership of the Board to the UK Government
 community engagement
 submission and approval of the Pride in Place Plan for Hamilton Town Centre 
The Committee decided: 
(1) that the appointment of representatives to the Hamilton Town Centre Neighbourhood Board,
as set out in sections 4.4. and 4.5 of the report, be approved;  
11

Page 12

(2) that decisions on the replacement of any Neighbourhood Board members, or the
appointment of additional Neighbourhood Board members, be delegated to the Executive
Director (Community and Enterprise Resources), in consultation with the Chair of the
Neighbourhood Board, the MP for Hamilton and the Chair of this Committee, provided that
should any elected representatives on the Neighbourhood Board no longer hold those
positions, they would be automatically replaced by those elected to their positions as MP,
MSP and Ward 17 Councillors, as the case may be, with any such changes being reported
to Committee for noting; 
(3) that the progression of the Hamilton Town Centre Pride in Place project be directed by the
Neighbourhood Board, and all decisions in respect of the use of Pride in Place funding be
taken by the Neighbourhood Board, with such decisions then being delivered operationally
by the Council as the accountable body, as set out in paragraph 5.1 of the report; 
(4) that authority be delegated to the Executive Director (Community and Enterprise
Resources), in consultation with the Executive Director (Finance and Corporate Resources),
to implement decisions of the Neighbourhood Board, as set out in paragraph 5.1 of the
report, save to the extent such authority had already been delegated in terms of the Scheme
of Delegation; and 
(5) that it be noted that update reports on the Pride in Place Programme, including decisions on
expenditure by the Neighbourhood Board and the proposed Pride in Place Plan, would be
reported to Committee for noting. 
[Reference: Minutes of 1 April 2026 (Paragraph 6)] 
12 Local Action Fund Approach for 2026/2027 
A report dated 1 June 2026 by the Executive Director (Finance and Corporate Resources) was
submitted on the proposed Local Action Fund (LAF) approach for 2026/2027. 
The Council, at its meeting on 25 February 2026, agreed that the LAF would be available again
for the 2026/2027 financial year.  This meant an allocation of £50,000 to each of the Council’s 20
geographical wards, with the spend to be approved by this Committee, following input from local
councillors. 
Following consideration of this matter at its previous meeting, the Committee agreed that the
approach on how this Fund would operate would be deferred to this meeting to allow for members’
briefings to take place.  Those had now been held and a summary of points raised was outlined
at paragraph 3.3 of the report.  As previously requested, a note had been provided to elected
members providing details of how the LAF monies had been spent in 2025/2026. 
The proposed approach for 2026/2027, as outlined in Section 4 of the report, built on that adopted
in the previous financial year, with members seeking to use their knowledge of local priorities to
inform decisions.  A timeline for reporting back to Committee was given at paragraph 4.9 of the
report. 
Subsequent to the members’ briefing sessions, a proposal had been submitted on behalf of all
the Ward 18 members to issue a grant of £1,100 from the LAF to Hillhouse Tenants’ and
Residents’ Association as a contribution towards the cost of transport to take local families on an
annual outing.   
Following discussion and agreement, the list of spend on last year’s Local Acton Fund awards
was to be appended as an annex to the minutes of this meeting.  
12

Page 13

The Committee decided: 
(1) that the proposed Local Action Fund (LAF) approach for 2026/2027, as outlined in section 4
of the report, be approved; 
(2) that the proposal from Ward 18 (Hamilton West and Earnock) members to issue a LAF grant
of £1,100 to Hillhouse Tenants’ and Residents’ Association, as outlined in paragraph 4.10
of the report, be approved; and 
(3) that it be noted that future reports would be submitted to the Committee to seek approval for
further spend from the Local Action Fund. 
[Reference: Minutes of South Lanarkshire Council of 25 February 2026 (Paragraph 3) and
Minutes of 20 May 2026 (Paragraph 4)] 
13 Statutory Consultation on Proposed Primary School Catchment Changes 
A report dated 5 June 2026 by the Executive Director (Education Resources) was submitted: 
 providing information on proposed changes to denominational primary school catchment
arrangements in Hamilton, including:-
 alterations to the catchment areas of St Mary’s Primary School and St Paul’s Primary
School to better balance pupil numbers
 the removal of the optional catchment arrangement between St Mary’s Primary School
and St Peter’s Primary School
 the removal of the optional catchment arrangement between St Peter’s Primary School
and Our Lady and St Anne’s Primary School
 requesting approval to undertake a statutory consultation on the proposed changes, in
accordance with the schools (Consultation) (Scotland) Act 2010 
The current catchment areas for St Mary’s Primary School, Hamilton and St Paul’s Primary
School, Hamilton were shown in Appendix 1 to the report.  Redrawing the boundary would support
more effective management of school capacities and a more balanced distribution of pupils across
the 2 schools. 
The current optional catchment area, where families might choose either St Peter’s Primary
School or St Mary’s Primary School as their denominational catchment school, was shown in
Appendix 3. 
The current optional catchment area, where families might choose either St Peter’s Primary
School or Our Lady and St Anne’s Primary School as their denominational catchment school, was
shown in Appendix 5. 
Details were provided on the affected schools within the catchment areas as follows:- 
 current pupil rolls
 projected school populations
 estimated number of pupils expected to arise from known housing developments   
Proposals in relation to the catchment realignment of St Mary’s Primary School, Hamilton and St
Paul’s Primary School, Hamilton were set out in Section 8 of the report.  Section 9 of the report
outlined proposals to remove the option for parents to choose for their children to attend either
school, instead zoning them to a particular school.  
13

Page 14

Section 10 of the report outlined proposals to remove the option for parents to choose for their
children to attend either St Peter’s Primary School and Our Lady and St Anne’s Primary School,
instead zoning them to a particular school. 
If, following a period of statutory consultation, the proposals were approved, the implementation
date of any catchment realignment would be for P1 enrolment in January 2027 for session
2027/2028. 
The Committee decided: that a statutory consultation, under the Schools
(Consultation) (Scotland) Act 2010, be undertaken on
proposed changes to the catchment areas of St Mary’s
Primary School, Hamilton and St Paul’s Primary School,
Hamilton to:- 
 balance pupil numbers more effectively
 remove the optional catchment area between St
Mary’s Primary School and St Peter’s Primary School
and align this area to St Peter’s Primary School
 remove the optional catchment area between St
Peter’s Primary School and Our Lady and St Anne’s
Primary School and align this area to Our Lady and St
Anne’s Primary School 
14 Council of Sanctuary Accreditation 
A report dated 19 May 2026 by the Executive Director (Housing and Technical Resources) was
submitted:- 
 providing an update on the Council of Sanctuary programme and what was required to
achieve accreditation, following the motion raised at full Council by an elected member in
December 2025
 seeking approval to progress the work to pursue Council of Sanctuary accreditation,
including governance arrangements and the next steps 
At its meeting on 10 December 2025, the Council agreed a motion to adopt Council of Sanctuary
principles and requested that officers work towards achieving accreditation.  Initial scoping had
now been completed. 
City of Sanctuary UK was a recognised charity and national umbrella organisation promoting
welcome, safety and inclusion for people seeking refuge from conflict, persecution or risk.  City of
Sanctuary co-ordinated the Local Authority Network and accreditation process and provided
training and guidance to support organisations to meet the “Learn – Embed – Share” criteria. 
If approved, the Council would join the City of Sanctuary UK Local Authority Network to support
the initial scoping work.  Membership of the Network was a prerequisite for Council of Sanctuary
accreditation, however, councils could be members without committing to pursue accreditation. 
The requirements for accreditation were outlined at Section 5 of the report, and the proposed next
steps were outlined at Section 6 of the report. 
The Committee decided: 
(1) that the Council join the City of Sanctuary UK Local Authority Network; 
(2) that the establishment of a senior officer-led cross-Council Working Group, to lead and
coordinate this work, be noted;  
14

Page 15

(3) that the proposed governance and delivery approach, including the development of a
Council of Sanctuary Action Plan and Evidence Portfolio, be noted; and 
(4) that a further report be presented to the Executive Committee seeking approval to apply for
Council of Sanctuary accreditation, once the Action Plan and Evidence Portfolio were
developed. 
[Reference:  Minutes of South Lanarkshire Council of 10 December 2025 (Paragraph 10)] 
15 Recommendation Referred by Licensing Committee 
A report dated 1 June 2026 by the Chief Executive was submitted on a recommendation referred
to this Committee by the Licensing Committee at its meeting on 19 May 2026 in relation to the
revised Statement of Licensing Policy for Short Term Lets. 
The recommendation of the Licensing Committee was that the updated Statement of Licensing
Policy for Short Term Lets be approved. 
The Committee decided: that the updated Statement of Licensing Policy for Short
Term Lets be approved. 
Reference: Minutes of 2 November 2022 (Paragraph 7), Minutes of the Licensing Committee of
24 June 2025 (Paragraph 3) and 19 May 2026 (Paragraph 3) and Minutes of the
Finance and Corporate Resources Committee of 10 September 2025 (Paragraph
14)] 
16 Appointment of Trustees to South Lanarkshire Leisure and Culture Board 
A report dated 4 June 2026 by the Executive Director (Finance and Corporate Resources) was
submitted:- 
 advising of a change to the trustees to the South Lanarkshire Leisure and Culture (SLLC)
Board
 seeking nominations to fill the vacant trustee positions
 noting the requirement for a further report to be brought back to Committee in September
on Board appointments 
Following her appointment as Leader of the Council, Councillor Devlin had resigned from the
SLLC Board.  While the Council was entitled to appoint up to 5 trustees, it currently only had 2
appointed trustees on the Board. 
It was proposed that Councillor Cowie replace Councillor Devlin as a trustee on the Board.   
It remained open for nominations to be received to fill the remaining 2 vacant positions. 
Councillor Devlin also held the position of Vice-Chair of the SLLC Board.  While the election of
the Vice-Chair was a matter for the SLLC Board, it was proposed that this Committee recommend
to SLLC that Councillor Razzaq be appointed to that position. 
SLLC was currently going through a process to appoint a new independent Chair and an additional
independent trustee.  It was anticipated that the SLLC Nominations Committee would be in a
position to make recommendations on this to the Council in early September 2026, after which
the Council would need to confirm its agreement, in line with SLLC’s constitution.  A further report
would be submitted to the September meeting of this Committee on trustee appointments.  
15

Page 16

The Committee decided: 
(1) that Councillor Cowie replace Councillor Devlin as a trustee of the South Lanarkshire Leisure
and Culture Board; 
(2) that the Council confirm to South Lanarkshire Leisure and Culture that it recommended that
Councillor Razzaq be the new Vice-Chair of the South Lanarkshire Leisure and Culture
Board; and 
(3) to note that a further report on appointments to the South Lanarkshire Leisure and Culture
Board would be brought to this Committee in September 2026. 
[Reference: Minutes of 30 April 2025 (Paragraph 11)] 
Councillor Nelson left the meeting during consideration of the above item of business 
17 Investment Challenge Motion 
A joint report dated 12 May 2026 by the Executive Directors (Finance and Corporate Resources)
and (Community and Enterprise Resources) was submitted on the investment principles and
ambitions for South Lanarkshire. 
At the Council meeting on 10 December 2025, it was agreed that officers would bring forward a
paper on infrastructure and investment proposals to drive constructive challenge across local and
central government to help create a pipeline of credible options for investment for the Council and
its partners.  A copy of the motion was attached as Appendix 1 to the report. 
The investment principles and ambitions of the Council were outlined in Section 4 of the report,
which detailed the development of various masterplans for town centres and country parks. 
In recognition of the future role of Glasgow City Region in decision-making and investment, the
Council would ensure that it had a pipeline of activity that aligned with regional strategies in order
to be best placed to secure investment. 
As well as approving a £105 million capital programme for 2026/2027, the Council also had some
significant investment plans for the years to 2030, including as new leisure centre in Larkhall
costing £27 million, secondary schools’ refurbishment totalling £18 million and improvements to
Stewartfield Way costing £30 million. 
Table 1, at paragraph 6.3 of the report, listed a number of investment ambitions and opportunities
which would advance the Council’s key strategic plans, and which were over and above the
strategic capital plans that were already in place.  Further details of each investment opportunity
and, where appropriate, how it aligned to a Council strategy, were provided in Appendix 2 to the
report. 
Officers continued to communicate with partners to identify potential collaborative working
opportunities and continually looked for external funding opportunities, contacting a number of
organisations to better understand their funding priorities. 
The Committee decided: 
(1) that the investment principles, as detailed in section 4, be noted; 
(2) that the opportunities, as detailed in Appendix 2 and summarised in section 6 of the report,
and the potential partners/funding sources, as detailed in section 6 of the report, be noted;
and 
16

Page 17

(3) that the next steps, as detailed in section 7 of the report, be noted. 
[Reference:  Minutes of South Lanarkshire Council of 10 December 2025 (Paragraph 18)] 
18 Transformational Review Programme – Summary of Outcomes Report 2025/2026
and Future Pipeline 
A report dated 29 May 2026 by the Executive Director (Finance and Corporate Resources) was
submitted providing a summary of the outcomes from the Council’s Transformational Review
Programme 2025/2026 and the future pipeline of transformation activity. 
The Council faced a range of challenges, including economic pressures, demographic change,
increasing demand for services, legislative requirements and rapid technological development. 
Collectively, those factors required a continual focus on transformation and improvement. 
The Council was already delivering a number of transformation programmes that had the potential
to significantly change how services were delivered and how the Council operated.  Those
programmes spanned:- 
 organisational redesign
 the Council’s property estate
 digital development
 system modernisation
 partnership working 
Appendix 1 to the report showed the many areas of transformation that had already taken place
in recent years and included detail of the impact on service outcomes.  This programme of service
reviews had delivered approximately £6 million in savings towards the 2025/2026 and 2026/2027
budget, with more anticipated in future years. 
A planned programme of change was detailed in Appendix 2 to the report.  Appendix 3 to the
report provided the planned template for monitoring outcomes from programmes. 
The Performance and Review Scrutiny Forum would continue to receive updates on the overall
programme of transformation. 
In response to a comment from Councillor Robb, the Executive Director (Finance and Corporate
Resources) agreed that, in relation to the Estates Strategy, wording be added to the benefits
realisation column to recognise the saving of £1.03 million through no and low cost measures
implemented by officers to save energy. 
The Committee decided: 
(1) that the summary of outcomes from the Council’s Transformational Review Programme, as
detailed in section 4 and Appendix 1 of the report, be noted; 
(2) that the transformation themes and pipeline of activity moving forward, as detailed in section
5 and Appendix 2 of the report, be noted; 
(3) that it be noted that the transformation programme would continue to be developed and
refined in line with changes in legislation, demand, financial assumptions and operational
challenges, as detailed in section 5.3 of the report; and 
(4) that the approach to benefits realisation, as detailed in section 6 of the report, the planned
template for monitoring and reporting outcomes, as detailed in Appendix 3 of the report, and
the governance arrangements in place, be noted. 
17

Page 18

19 Update on Scotland’s Climate Change Plan 2026 to 2040 
A report dated 1 June 2026 by the Executive Director (Community and Enterprise Resources)
was submitted providing an overview of the recently published Scottish Government’s Climate
Change Plan (CCP) 2026 to 2040. 
On 6 November 2025, the Scottish Government had published a draft CCP 2026 to 2040 for
consultation.  This set out the policies and proposals the Scottish Government would take forward
to enable Scotland to meet the Carbon Budgets for Scotland, as outlined at paragraph 3.2 of the
report.  The full consultation response had been presented to the Climate Change and
Sustainability Committee on 11 February 2026. 
The draft Plan had now been superseded by the finalised CCP 2026 to 2040 which was published
on 24 March 2026.  The CCP set out the policies and proposals the Scottish Government would
take forward in order to meet its emissions reduction targets, as set out in paragraph 3.2 of the
report. 
On 6 March 2026, the Scottish Government published the ‘Climate change duties:  statutory
guidance for public bodies’.  The purpose of this statutory guidance was to support public bodies
in performing their climate change duties under the Climate Change (Scotland) Act 2009. 
The CCP outlined the emissions pathway for 7 key sectors, the key actions required and the
economic opportunities and benefits those actions would support.  The 7 key sectors were:- 
 Buildings (residential and public)
 Transport
 Waste
 Energy Supply
 Business and Industrial Process and Negative Emissions Technologies
 Agriculture
 Land Use, Land Use Change and Forestry (LULUCF) 
Local authorities had responsibilities for implementation across all 7 key sectors and those were
detailed in Appendix 1 to the report.  This included developing programmes and investable
projects, strengthening partnerships, and securing external funding and private investment. 
Delivery must also incorporate effective community engagement and embed just transition
principles, such as tackling fuel poverty and supporting local employment, as detailed in section
7 of the report. 
Delivery of those commitments would require co-ordinated action across all Council Resources,
with a requirement for climate consideration to be embedded in capital investment decisions and
all Resource and Service planning. 
A new Sustainable Development and Climate Change Strategy, covering the period 2028 to 2035,
was under development and would align with the priorities and requirements of the CCP. 
The Committee decided: 
(1) that the overview of the contents of the Climate Change Plan 2026 to 2040 be noted; and 
(2) that the role and responsibilities for local authorities as set out in the Climate Change Plan,
as detailed in Appendix 1 of the report, be noted. 
[Reference: Minutes of the Climate Change and Sustainability Committee of 11 February 2026
(Paragraph 7)]  
18

Page 19

20 Good Food Nation Plan 
A report dated 4 June 2026 by the Chief Executive was submitted providing an update on the
upcoming duties for all local authorities on the development of Good Food Nation (GFN) plans
and the Council’s current progress with its Plan. 
The Good Food Nation (Scotland) Act 2022 imposed a legislative duty on local authorities to
prepare and publish GFN plans. 
The national GFN Plan set out 6 overarching outcomes for a GFN, as outlined at paragraph 4.2
of the report. 
Section 10 of the Act, which was not yet in force but anticipated to be by April 2027, required
relevant authorities to publish a GFN Plan within a period of 12 months.  In preparing a plan,
consideration had to be given to the role of all parts of the food system and supply chain, the
importance of a sustainable food system in tackling climate change and biodiversity loss, and the
role of high-quality, nutritious, culturally appropriate food in improving wellbeing. 
Council officers had been meeting with both NHS Lanarkshire and North Lanarkshire Council to
ensure some regional consistency and support across each organisation’s Plan.  When preparing
a GFN Plan, the relevant authority must publish and consult on a draft of the Plan and have regard
to any responses received. 
Authorities were required to report progress against their Plan’s outcomes every 2 years and
undertake a full review of the Plan every 5 years.  All plans were required to have outcomes,
indicators, measures and list related policies as part of the duties. 
The Committee decided: that the plans to meet the requirements for the Council to
prepare South Lanarkshire’s Good Food Nation Plan be
noted. 
[Reference:  Minutes of 27 August 2025 (Paragraph 13)] 
21 Membership of Committees, Forums and Trusts - Update 
A report dated 4 June 2026 by the Executive Director (Finance and Corporate Resources) was
submitted providing an update on the membership of committees, forums and trusts following on
from the decisions taken at the previous Council meeting. 
At its meeting on 27 May 2026, the Council agreed that authority be delegated to the Chief
Executive to update memberships as a consequence of Councillor Devlin being appointed as
Leader of the Council and Councillor Razzaq being appointed as Chair of the Finance and
Corporate Resources Committee.  A copy of the updated membership of committees and forums
was attached as an appendix to the report. 
At its meeting on 15 August 2018, the Executive Committee agreed that the Chair of the Finance
and Corporate Resources Committee would be a member of both The South Lanarkshire
Educational Trust and The South Lanarkshire Charitable Trust.  As the newly appointed Chair,
Councillor Razzaq would become a member of both Trusts. 
The Committee decided: 
(1) that the updated committee and forum memberships, as detailed in the appendix to the
report, be noted; and  
19

Page 20

(2) that it be noted that Councillor Razzaq, as Chair of the Finance and Corporate Resources
Committee, was appointed as Trustee to both The South Lanarkshire Educational Trust and
The South Lanarkshire Charitable Trust. 
[Reference: Minutes of South Lanarkshire Council of 27 May 2026 (Paragraph 6) and Minutes of
15 August 2018 (Paragraph 8)] 
22 Scottish Fire and Rescue Service – Service Delivery Review Recommendations 
The Executive Director (Housing and Technical Resources) gave a verbal update on the recent
decisions taken by the Board of Scottish Fire and Rescue Service (SFRS). 
SFRS had been conducting a Service Review, assessing how Fire and Rescue Services were
delivered so their resources better matched local risk, demand and budget pressures.  The review
commenced in 2023, with public stakeholder engagement and consultation held in 2024 and 2025.   
The Council responded to the consultation, as approved by this Committee on 27 August 2025. 
In addition to this, a special members’ awareness session was held with senior SFRS personnel
on 18 August 2025, setting out the potential implications for South Lanarkshire from the options
being considered.  The main concern raised was the impact on the review of the Hamilton
provision.  Its second appliance was already temporarily removed in September 2023 and options
within the review either made the reduction permanent or increased it back to 2 appliances with a
different operating model.  Another option saw the provision of Lesmahagow being enhanced for
a new staffing model, improving it to a nearby station’s ability to respond to incidents during peak
hours. 
The SFRS Board met on Monday 22 June 2026 to discuss the conclusion of the review.  The
Council had since received formal notification that the Hamilton provision would be permanently
reduced to one appliance, which continued the existing operating model in use since 2023, and
that there would be no change to the current provision at Lesmahagow. 
In response to this, and through the Chair of the Safer South Lanarkshire Board, the Council would
now formally respond to the outcome of the review citing its disappointment that the second
appliance in Hamilton was being permanently removed.  Whilst there was no specific process for
the service delivery review, it was proposed that the Council write to the Chair of the SFRS Board
and request that this decision be reconsidered and ask whether a further public or stakeholder
consultation on this decision would take place.  Reassurances would be sought that risks to
residents across South Lanarkshire would not be increased as a result of this decision. 
The Committee decided: that the verbal update be noted. 
[Reference:  Minutes of 27 August 2025 (Paragraph 8)] 
23 Urgent Business 
There were no items of urgent business. 
20

Page 21

Annex 
LOCAL ACTION FUND
APPROVED LOCAL ACTION FUND PROPOSALS
CURRENT STATUS - CORRECT AS AT 10 JUNE 2026 
Ward Project  Funding
approved
Lead Service and
Resource
Current Status / Further Information on
expenditure 
Ward 1 – 
Clydesdale
West
Upgrade of the local skate park and BMX
track 
£50k Facilities, Waste &
Ground Services/C&ER
Contract has been awarded, confirmation awaited
of when work to start. 
Ward 2 –
Clydesdale
North 
Play Park improvements £50k Facilities, Waste &
Ground Services/C&ER
Landscape Team currently working on Clydesdale
Play Area assessments to identify targeted
investment sites.  Once draft programme is ready
members will be consulted. 
Ward 3 –
Clydesdale
East 
Sustainable Pettinain SCIO (Petttinain Hall)  £5k Administration & Legal
Services/F&CR
Funds issued for use by grantee. 
Ward 3 –
Clydesdale
East 
Soul of the Junction SCIO (Carstairs Junction
Hall) 
£5k Administration & Legal
Services/F&CR
Funds issued for use by grantee. 
Ward 3 –
Clydesdale
East 
Carstairs Community Centre (Carstairs
Village) 
£5k Administration & Legal
Services/F&CR
Funds issued for use by grantee. 
Ward 3 –
Clydesdale
East 
Ravenstruther &Cleghorn Hall Association  £5k Administration & Legal
Services/F&CR
Funds issued for use by grantee. 
21

Page 22

Ward Project  Funding
approved
Lead Service and
Resource
Current Status / Further Information on
expenditure 
Ward 3 –
Clydesdale
East 
Quothquan Village Hall  £5k Administration & Legal
Services/F&CR
Funds issued for use by grantee. 
Ward 3 –
Clydesdale
East 
Wiston Village Hall  £5k Administration & Legal
Services/F&CR
Funds issued for use by grantee. 
Ward 3 –
Clydesdale
East 
Dolphinton Hall Community Association  £5k Administration & Legal
Services/F&CR
Funds issued for use by grantee. 
Ward 3 –
Clydesdale
East 
Crawfordjohn Public Hall Association  £5k Administration & Legal
Services/F&CR
Funds issued for use by grantee. 
Ward 3 –
Clydesdale
East 
Elsrickle Community Hub  £5k Administration & Legal
Services/F&CR
Funds issued for use by grantee. 
Ward 3 –
Clydesdale
East 
Biggar Youth Project  £5k Administration & Legal
Services/F&CR
Funds issued for use by grantee. 
Ward 4 –
Clydesdale
South 
Blackwood & Kirkmuirhill Resilience Group –
to support local youth development
£50k Administration & Legal
Services/F&CR
Funds issued for use by grantee. 
Ward 5 –
Avondale &
Stonehouse 
Friends of Stonehouse Park – to purchase a
generator to be used for community events
£12k Administration & Legal
Services/F&CR
Funds issued for use by grantee.
22

Page 23

Ward Project  Funding
approved
Lead Service and
Resource
Current Status / Further Information on
expenditure 
Ward 5 –
Avondale &
Stonehouse
Strathaven Rugby Club – contribution to
renewable energy system to form part of the
new multi sports facility proposed by the club.
£20k Administration & Legal
Services/F&CR
Grant agreement in place, final consents to be
secured for the project and funds will then be
released. 
Ward 5 –
Avondale &
Stonehouse
Targeted improvements to public spaces
across the ward, which might include
renovation/purchase of benches and
installation of bird proof litter bins. 
£8k Facilities, Waste &
Ground Services/C&ER
Completed
Ward 5 –
Avondale &
Stonehouse
Play Park Improvements - £10k towards play
park improvements in the ward, including
accessible play park equipment
£10k Facilities, Waste &
Ground Services/C&ER
Auldhouse agreed with members as location of
spend. Start date for work has been re-scheduled
for 13th July and will be completed by end July 
On track to be undertaken by Landcare Solutions. 
LAF monies forming part of a larger
redevelopment incorporating SGPIP 
Ward 6 – 
East Kilbride
South 
East Kilbride and District Dementia Carers
Group
£25k Administration & Legal
Services/F&CR
Funds issued for use by grantee.
Ward 6 – 
East Kilbride
South 
Waist Not Want Not  £15k Administration & Legal
Services/F&CR
Funds issued for use by grantee.
Ward 6 – 
East Kilbride
South 
Loaves and Fishes  £10k Administration & Legal
Services/F&CR
Funds issued for use by grantee.
23

Page 24

Ward Project  Funding
approved
Lead Service and
Resource
Current Status / Further Information on
expenditure 
Ward 7 – 
East Kilbride
Central
South 
Resurface road to Murray Bowling Club £30k Roads, Transportation &
Fleet Services/C&ER
Completed
Ward 7 – 
East Kilbride
Central
South
Darwin Road play area, accessible play
equipment for children with disabilities 
£20k Facilities, Waste &
Ground Services/C&ER
Darwin Road works is part of the EK Area
contract with site works due to commence on 6
July with detailed programme to follow once all
play equipment is delivered.  Will be complete by
13 November. 
Ward 8 –
East Kilbride
Central
North
Play Park Investment Programme  £42k Facilities, Waste &
Ground Services/C&ER
Maxwellton Play Area works is part of the EK
Area contract with site works due to commence
on 6 July with detailed programme to follow.  Will
be complete by 13 November. 
Ward 8 –
East Kilbride
Central
North
8 Primary Schools (£1000 each) for play-
play-based learning
£8k Education Resources Funds have been transferred for use by the
schools.  Used as summarised below . 
• West Mains PS– outdoor play
• Kirktonholme PS –trim trail 
• Blacklaw PS – outdoor play 
• Halfmerke PS – play resources
• Maxwellton PS – Play based learning
• Mount Cameron PS – creative classroom kits
• St Hilarys PS – outdoor resources mud
kitchen
• Greenburn PS – TBC 
24

Page 25

Ward Project  Funding
approved
Lead Service and
Resource
Current Status / Further Information on
expenditure 
Ward 9 – 
East Kilbride
West
Play Park Investment Programme  £50k Facilities, Waste &
Ground Services/C&ER
Hairmyres Park and JHHP Play Areas are both
part of the EK Area contract with site works due to
commence on 6 July with detailed programme to
follow.  Will be complete by 13 November. 
Ward 10 –
East Kilbride
East
New pathway between Benbecula Play Area
and local housing. 
£16k Facilities, Waste &
Ground Services/C&ER
Benbecula path improvements are due to
commence on site on the 8th of June with an end of
June completion. 
Ward 10 –
East Kilbride
East
6 additional freestanding litter bins at
Calderglen Country Park 
£3k Facilities, Waste &
Ground Services/C&ER
Complete
Ward 10 –
East Kilbride
East
5 schools (£1,000 each, 3 primary schools
and 2 high schools) 
£5k Education Funds have been transferred for use by the
schools.  Used as summarised below 
• Hunter PS – outdoor play 
• Long Calderwood PS – phonic workshops
literacy 
• St Leonards PS – Science Centre
• Calderglen High – Support resources for S2
• Sanderson High – sensory equipment 
Ward 10 –
East Kilbride
East
Improve Lammermoor Play Park  £26k Facilities, Waste &
Ground Services/C&ER
Lammermoor is part of the EK Area contract
awarded in April 2026, site works due to
commence on 08th June with detailed programme
to follow.  Will be complete by end October. 
Ward 11 –
Rutherglen
South 
Refurbishment of Craignure steps  £15k Housing & Technical
Resources
Works are commencing on site. 
25

Page 26

Ward Project  Funding
approved
Lead Service and
Resource
Current Status / Further Information on
expenditure 
Ward 11 –
Rutherglen
South
Repairing of the MUGA pitch at Cathkin
Primary School 
£1k Education To be completed by end June.
Ward 11 –
Rutherglen
South
Douglas Avenue Park - Additional play
equipment 
£10k Facilities, Waste &
Ground Services/C&ER
Works package awarded in June, with works
starting July and expected completion by 14
August.
Ward 11 –
Rutherglen
South
Spittal Community Notice Board/ Defibrillator  £1.8k Property  Community notice board at school or shops
together with a defibrillator at chemists. Will be
completed by end June. 
Ward 11 –
Rutherglen
South 
Burnside. Stonelaw Woods and Woodburn
Park railings 
£3k Facilities, Waste &
Ground Services/C&ER
Work is ongoing weather delayed start, being
undertaken by Community Payback. 
Ward 11 –
Rutherglen
South
Fernhill. Community Noticeboard at
Community Centre 
£800 Property  Consultancy Services are working with
Procurement to order the notice board contractor
has been identified for installation. Will be
completed by end June. 
Ward 11 –
Rutherglen
South 
Blairbeth. Playground equipment at
Rowantree Avenue 
£13,400 Facilities, Waste &
Ground Services/C&ER
Works package awarded in June, with works
starting July and expected completion by 14
August.
Ward 11 –
Rutherglen
South 
Springhall. Skip provision, at site beside the
Cage 
£2k Administration & Legal
Services/F&CR
Funds issued for use by grantee.
Ward 11 –
Rutherglen
South
Grant to Springlaw Nursery  £500 Education Resources Funds have been transferred for use by the
school.  Used for music equipment 
26

Page 27

Ward Project  Funding
approved
Lead Service and
Resource
Current Status / Further Information on
expenditure 
Ward 11 –
Rutherglen
South
Friends of Spittal Primary School  £500 Administration & Legal
Services/F&CR
Funds been transferred to school, for Parent
Council to access in normal way.  Used for
community notice board 
Ward 11 –
Rutherglen
South
St Mark’s Primary School Parent Council  £500 Education Resources Funds been transferred to school, for Parent
Council to access in normal way. Used for school
trip 
Ward 11 –
Rutherglen
South
Cathkin Primary School Parent Council  £500 Education Resources Funds been transferred to school, for Parent
Council to access in normal way. Used for
outdoor play resources 
Ward 11 –
Rutherglen
South
Friends of Loch Primary School  £500 Administration & Legal
Services/F&CR
Funds been transferred to school, for Parent
Council to access in normal way. Used for
outdoor play 
Ward 11 –
Rutherglen
South
St Anthony’s Primary School Parent Council  £500 Education Resources Funds been transferred to school, for Parent
Council to access in normal way. Used for
Christmas fayre 
Ward 12 –
Rutherglen
Central and
North 
Universal Connections £12k Universal
Connections/Education
Funds have been transferred for use by Universal
Connections.
Ward 12 –
Rutherglen
Central and
North
£5,000 for each of the three primary schools,
Bankhead, Burgh, and St Columbkille’s
£5k (£15k
total)
Education  Funds have been transferred for use by the
schools.  Used as summarised below :. 
• Bankhead – outdoor learning
• Burgh – school trip
• St Columbkilles – outdoor learning 
27

Page 28

Ward Project  Funding
approved
Lead Service and
Resource
Current Status / Further Information on
expenditure 
Ward 12 –
Rutherglen
Central and
North 
Rutherglen Community Carers   £2k Administration & Legal
Services 
Funds issued for use by grantee.
Ward 12 –
Rutherglen
Central and
North 
Cambuslang & Rutherglen Sports Council –
Funding to purchase a trophy for the Burgh
cup, a local football tournament for schools.
£1k Administration & Legal
Services
Funds issued for use by grantee.
Ward 12 –
Rutherglen
Central and
North 
High Backs - £7k to the men’s group and £4k
to the after school to support the groups
services.
£11k Administration & Legal
Services
Funds issued for use by grantee.
Ward 12 –
Rutherglen
Central and
North 
Overtoun Park Bowling Club – provision of a
comfort scheme for those using the park.
£9k Administration & Legal
Services
Funds issued for use by grantee.
Ward 13 –
Cambuslang
West
Painting of railings at Cambuslang Park  £4k Facilities, Waste &
Ground Services/C&ER
Work is ongoing weather delayed start, being
undertaken by Community Payback. 
Ward 13 –
Cambuslang
West
Refurbishment of the Wheel Toll Pitch
Pavillion 
£20k Facilities, Waste &
Ground Services/C&ER
Complete
Ward 13 –
Cambuslang
West
Funding for Women’s Wellbeing Collective
community group and for Community Wealth
Building
£20k Education  Funds issued for use by grantee, via Cambuslang
Universal Connections. 
28

Page 29

Ward Project  Funding
approved
Lead Service and
Resource
Current Status / Further Information on
expenditure 
Ward 13 –
Cambuslang
West
Community Skips, Community Skips
Whitlawburn – skip service for large items for
residents who struggle getting to recycling
centres. 
£6k Administration & Legal
Services/F&CR
Funds issued for use by grantee.
Ward 14 –
Cambuslang
East 
Hub Transformation Project  £40k Property Services, HTR Ongoing, works specification being progressed. 
Ward 14 –
Cambuslang
East
LEAP for Cambuslang Project in the
refurbished library building 
£2k Administration & Legal
Services/F&CR
Funds issued for use by grantee. Used for
refurbishment of library building 
Ward 14 –
Cambuslang
East
Project 31 – to support delivery of outreach
community project for the benefit of people
within the ward in Halfway area. 
£500 Administration & Legal
Services/F&CR
Funds issued for use by grantee.
Ward 14 –
Cambuslang
East 
To support delivery of Halfway Park Project  £1k Administration & Legal
Services/F&CR
Funds issued for use by grantee.
Ward 14 –
Cambuslang
East
Particip8 – to support delivery of
Cambuslang East Annual events for the
community, such as fireworks, summer gala,
Christmas light switch on, Santa drive by,
Halloween, Easter, and the like. 
£6.5k Administration & Legal
Services/F&CR
Funds issued for use by grantee.
Ward 15 –
Blantyre
Blantyre Futures – to support delivery of
winter/Christmas community events in the
Blantyre ward.
£5k Administration & Legal
Services/F&CR
Funds issued for use by grantee.
29

Page 30

Ward Project  Funding
approved
Lead Service and
Resource
Current Status / Further Information on
expenditure 
Ward 15 –
Blantyre
Blantyre Miners Welfare Charity - to support
carpeting of 3 rooms in the community
centre.
£5k Administration & Legal
Services/F&CR
Funds issued for use by grantee. Used  to allow 3
rooms to be carpeted. Might seek to rent rooms
out to generate additional income for Centre and
support enhanced community use. 
Ward 15 –
Blantyre
Terminal One – to support delivery of
community activities within the ward being
£13,170 to replace 6 auto belays for climbing
wall, £10k as a contribution to a minibus
replacement and £5k for a summer activities
programme for children and young people. 
£28,170 Administration & Legal
Services/F&CR
Funds issued for use by grantee.
Ward 15 –
Blantyre
Third Blantyre Community Group Scouts – to
support replacement of hall floor and kitchen
refurbishment at High Blantyre Public Hall. 
£10k Administration & Legal
Services/F&CR
Funds issued for use by grantee.
Ward 15 –
Blantyre
Soul Skin Social Enterprise – to support
provision of free holistic treatments within the
ward. 
£1,830 Administration & Legal
Services/F&CR
Funds issued for use by grantee.
Ward 16 –
Bothwell &
Uddingston 
Bothwell Futures to support the employment
of a General Manager for a period of 1 year
on a fixed term basis. 
£25k Administration & Legal
Services/F&CR
Funds issued for use by grantee. 
Ward 16 –
Bothwell &
Uddingston 
Grow Uddingston – travel, community
orchard, and community garden. 
£25k Administration & Legal
Services/F&CR
Funds issued for use by grantee. 
30

Page 31

Ward Project  Funding
approved
Lead Service and
Resource
Current Status / Further Information on
expenditure 
Ward 17 – 
Hamilton
North &
East
Restoration of Bothwell Road Park band
stand
£50k Property Services, HTR Works are due to commence on site on 8th June
and completion 9th October 2026, for
reinstatement of Bandstand and associated
groundworks. Will also be hoarding erected that
will provide historical overview. 
Ward 18 –
Hamilton
West &
Earnock 
Hillhouse Resident’s and Tenant’s Group – to
support delivery of services to local residents
and tenants, broken down as follows, £7k to
supply water to recreational area in Dunkeld
Place, £3,500 for a generator to provide
power at events, £2500 for CCTV, £2k for a
Burntisland trip and £3k for Christmas party. 
£18k Administration & Legal
Services/F&CR
Funds issued for use by grantee.
Ward 18 –
Hamilton
West &
Earnock 
Burnbank Bowling Club – Supply and fitting
of defibrillator. 
£2k Administration & Legal
Services/F&CR
Funds issued for use by grantee.
Ward 18 –
Hamilton
West &
Earnock 
Earnock Resident’s Association - Supply and
fitting of defibrillator
£2k Administration & Legal
Services/F&CR
Funds issued for use by grantee.
Ward 18 –
Hamilton
West &
Earnock
Supporting Our Community (SOC) to support
delivery of services to local residents broken
down as follows: £5k for garden project,
£3,600 for health training and £3k for a
children’s party. 
£12k Administration & Legal
Services/F&CR
Funds issued for use by grantee.
31

Page 32

Ward Project  Funding
approved
Lead Service and
Resource
Current Status / Further Information on
expenditure 
Ward 18 –
Hamilton
West &
Earnock 
Meikle Earnock Community Council –
Christmas event
£2k Administration & Legal
Services/F&CR
Funds issued for use by grantee. 
Ward 18 –
Hamilton
West &
Earnock 
First Steps Nursery £4k Education Resources Funds transferred to the school for use. Used for
Outdoor equipment 
Ward 18 –
Hamilton
West &
Earnock 
Terminal One – for youths of Hillhouse – to
support delivery of services to young people
in the Hillhouse community.
£2k Administration & Legal
Services/F&CR
Funds issued for use by grantee.
Ward 18 –
Hamilton
West &
Earnock 
Community Links Hillhouse – to support
delivery of services in the local community of
Hillhouse 
£1k Administration & Legal
Services/F&CR
Funds issued for use by grantee.
Ward 18 –
Hamilton
West &
Earnock 
Community Links Burnbank - to support
delivery of services in the local community of
Burnbank 
£1k Administration & Legal
Services/F&CR
Funds issued for use by grantee.
32

Page 33

Ward Project  Funding
approved
Lead Service and
Resource
Current Status / Further Information on
expenditure 
Ward 18 –
Hamilton
West &
Earnock
£1k to each PS - Neilsland, St Mark's, St
Ninian's, St Peter's, Townhill and Udston)  
£6k Education Funds transferred to schools for use.  Used as
summarised below : . 
• Neilsland – creation of Happy Hut
• St Marks PS – TBC
• St Ninians – TBC
• Townhill PS - Numeracy resources 
• Udston PS – TBC
• St Peters - TBC 
Ward 19 –
Hamilton
South 
Eddlewood Football Club - to be used for the
supply of new goal posts.  For different age
groups – football and kitchen equipment to
support ongoing delivery of services to the
local community, 
£5k Administration & Legal
Services/F&CR
Funds issued for use by grantee.
Ward 19 –
Hamilton
South
Low Waters Lot Community Group  £1k Administration & Legal
Services/F&CR
Cancelled, not able to take advantage of grant at
this time, agreed with ward members and
Chair/Vice Chair of Executive Committee.
Members agreed to instead transfer to Eddlewood
FC. 
Ward 19 –
Hamilton
South
11th Hamilton Guides – to be used for the
supply of sports and litter picking equipment
and additional resources to support ongoing
delivery of services to the local community. 
£2k Administration & Legal
Services/F&CR
Funds issued for use by grantee.
33

Page 34

Ward Project  Funding
approved
Lead Service and
Resource
Current Status / Further Information on
expenditure 
Ward 19 –
Hamilton
South
Low Waters Community Group – to be used
for the renovation of flooring in kitchen and
bathrooms and purchase of storage
container to support ongoing service delivery
to the local community, 
£2k Administration & Legal
Services/F&CR
Funds issued for use by grantee. Used for
Storage container
Ward 19 –
Hamilton
South
Eddlewood FC - to be used for the supply of
new goal posts.  For different age groups –
football and kitchen equipment to support
ongoing delivery of services to the local
community 
£1k Administration & Legal
Services/F&CR
Funds issued for use by grantee. Replaced Low
Waters Lot Community Group, agreed by ward
members and Chair/Vice Chair.   
Ward 19 –
Hamilton
South
Sunday Allsorts Youth Group – to be used
for the supply of garden games and
stationery to support ongoing delivery of
services to the local community. 
£750 Administration & Legal
Services/F&CR
Funds issued for use by grantee. 
Ward 19 –
Hamilton
South 
Centenary Gardens £2k SW/H&T Funds transferred.
Ward 19 –
Hamilton
South 
Deer Park £2k SW/H&T Funds transferred.
Ward 19 –
Hamilton
South 
John Smith Court £2k SW/H&T Funds transferred.
34

Page 35

Ward Project  Funding
approved
Lead Service and
Resource
Current Status / Further Information on
expenditure 
Ward 19 –
Hamilton
South
Abercorn House Care Home – to be used to
enhance recreational activities, garden
spaces and leisure opportunities at the care
home and improve residents’ quality of life. 
£2k Administration & Legal
Services/F&CR
Funds issued for use by grantee.
Ward 19 –
Hamilton
South
Abbeydale Court - to be used to enhance
recreational activities, garden spaces and
leisure opportunities at the care home and
improve residents’ quality of life.
£2k Administration & Legal
Services/F&CR
Funds issued for use by grantee.
Ward 19 –
Hamilton
South 
Salvation Army  £750 Administration & Legal
Services/F&CR
Funds issued for use by grantee. 
Ward 19 –
Hamilton
South
Richmond Fellowship £750 Administration & Legal
Services/F&CR
Cancelled, no longer delivering services in
Hamilton, agreed with ward members and
Chair/Vice Chair to provide funds to Fairhill Café
and HIPY 
Ward 19 –
Hamilton
South 
The Samaritans  £750 Administration & Legal
Services/F&CR
Funds issued for use by grantee. 
Ward 19 –
Hamilton
South
£4.5k to each Primary School (Chatelherault
Primary, Our Lady & St Anne's Primary, St
Elizabeth's Primary, St John's Primary,
Woodhead Primary and Woodside Primary)
£27K Education  Funds transferred to Schools for use. Funds used
as summarised below : . 
• Chatelherault PS – TBC
• Our Lady and St Annes PS – Stage
equipment 
• St Elizabeths PS – stage equipment
• St Johns PS – playground games/sports lines
• Woodside PS – reading and books
• Woodhead PS – TBC 
35

Page 36

Ward Project  Funding
approved
Lead Service and
Resource
Current Status / Further Information on
expenditure 
Ward 19 –
Hamilton
South
HIPY  £375 Administration & Legal
Services/F&CR
Funds issued for use by grantee. Grant
paperwork being progressed. Replaced Richmond
Fellowship, agreed by ward members and
Chair/Vice Chair.
Ward 19 –
Hamilton
South 
Fairhill Community Café £375 Administration & Legal
Services/F&CR
Funds issued for use by grantee. Replaced
Richmond Fellowship, agreed by ward members
and Chair/Vice Chair.
Ward 20 –
Larkhall 
To be shared between the 10 schools within
the Ward, being Craigbank, Glengowan,
Machanhill. Hareleeshill, Quarter, Dalserf,
Netherburn, St Mary’s and Robert Smilie
Memorial primary schools and Larkhall
Academy. 
£50K Education  Funds transferred to the schools for use. Used as
summarised below. 
• Machanhill PS – viewboards
• Quarter PS – outdoor gym
• Robert Smillie PS – chromebooks
• Craigbank PS – C Touches and reading
resources
• Harelesshill PS – nurture room
• Dalserf PS – outdoor resources
• Netherburn PS – sensory library, arts and
crafts
• Glengowan -musical instruments
• St Marys PS – outdoor classroom
• Larkhall Academy – TBC 
36

Page 37

Report
Agenda Item 
Report to: Executive Committee
Date of Meeting: 19 August 2026
Report by: Executive Director (Finance and Corporate Resources)  
Subject: Revenue Budget Monitoring for Period 4 - 1 April 2026
to 10 July 2026 
1. Purpose of Report
1.1. The purpose of the report is to:-
[purpose]
 advise the Committee of the forecast for the year to 31 March 2026 for the
Council’s General Fund Revenue Account and Housing Revenue Account, and
the actual spend position for the period 1 April 2026 to 10 July 2026
[1purpose]
2. Recommendation(s)
2.1. The Executive Committee is asked to approve the following recommendation(s):-
[recs]
(1) that the projected breakeven position on the General Fund Revenue Account
for 2026/2027 (section 4.1) after budgeted Transfers to Reserves and
previously reported underspends, and the actual spend as at 10 July 2026
(Appendix 1), be noted; and
(2) that the projected breakeven position on the Housing Revenue Account for
2026/2027, and the actual spend as at 10 July 2026 (section 5 and Appendix
2), be noted. 
3. Background
3.1. This overview report will summarise the projected outturn for 2026/2027 for both the
Council’s General Fund (section 4) and for the Housing Revenue Account (section 5). 
It will also provide the actual spend as at 10 July 2026. 
4. General Services 2026/2027 Projected Outturn as at 10 July 2026
4.1. As at 10 July 2026, the projected outturn position for 2026/2027 on the General
Services budget is breakeven after budgeted Transfers to Reserves and previously
reported underspends (Appendix 1).  The actual spend to date is shown in Appendix
1. 
4.2. As previously reported to Committee on 24 June, across the Council’s Budget, there
are 3 notable areas where underspends are anticipated this financial year.  These
relate to Loan Charges (£6.096 million), Non-Domestic rates (£2.700 million) and
Empty Property Relief (£1.000 million).  The budget for each of these areas has been
moved to a separate budget line in Appendix 1 and will be considered later in the
financial year as part of the Probable Outturn position.  
3
37

Page 38

4.3. Social Work Resources – Children and Families:  As previously reported, the
forecasts for Children and Families, Justice, and Performance and Support Services
continue to show a breakeven position.  As reported through Social Work Committee,
budget pressures within Children and Families are continuing into 2026/2027 in
relation to statutory duties of continuing care and increased costs and requirements
for residential placements, fostering and kinship care.  The Social Work Resources
position assumes that Children and Families’ reserves funding will be utilised later in
the financial year, to support a break-even position in 2026/2027. 
4.4. Social Work Resources – Adult and Older People:  As we have reported previously
and taking into account the ongoing recruitment challenges across areas of the
Service, we continue to see underspends in some areas.  To allow services to respond
to continuing service pressures, emerging underspends in year can be used for extra
care packages and prospectively earmark any remaining projected underspends for
the continuing costs of those extra care packages through 2027/2028.  Transfers to
reserves will be confirmed as part of the Probable Outturn exercise. 
5. Housing Revenue Account Position
5.1. As at 10 July 2026, Appendix 2 of the report shows a breakeven position on the
Housing Revenue Account. 
6. Employee Implications
6.1. None. 
7. Financial Implications
7.1. As detailed in sections 4 to 5 of the report. 
8. Climate Change, Sustainability and Environmental Implications
8.1. There are no implications for climate change, sustainability or the environment in terms
of the information contained in this report. 
9. Risk and Other Implications
9.1. The main risk associated with the Council’s Revenue Budget is that there is an
overspend.  The risk has been assessed as low given the detailed budget
management applied across the Resources.  The risk is managed through four weekly
Budget Monitoring Meetings at which any variance is analysed. In addition, the
probable outturn exercise ensures early warning for corrective action to be taken
where appropriate. 
10. Integrated Impact Assessment and Consultation Requirements
10.1. This report does not introduce a new policy, function or strategy or recommend a
change to an existing policy, function or strategy and therefore no impact assessment
is required.   
10.2. There is also no requirement to undertake any consultation in terms of the information
contained in this report. 
Jackie Taylor
Executive Director (Finance and Corporate Resources) 
27 July 2026  
38

Page 39

Link(s) to Council Values/Priorities/Outcomes
 Accountable, Effective, Efficient and Transparent 
Previous References
 None 
List of Background Papers
 Financial Ledger and budget monitoring results to 10 July 2026 
Contact for Further Information
If you would like to inspect the background papers or want further information, please
contact:- 
Lorraine O'Hagan, Head of Finance (Strategy)
Ext:  5637 (Tel:  01698 455637)
E-mail: lorraine.o'hagan@southlanarkshire.gov.uk
39

Page 40

Note:  While the Year to Date Actual at period 4 presents a net surplus position (£69.501m), this is timing only.  The forecast outturn
shows a breakeven position (section 4.1).
Appendix 1
Revised Projected Projected % Note Year to Date
Annual Outturn Outturn Actual
Budget Variance
Resources: £m £m £m £m
Community and Enterprise Resources 138.980 138.980 0.000 0.00% 30.966
Facilities Waste and Grounds 84.744 85.355 (0.611) (0.72%) 18.544
Leisure and Culture 19.658 19.658 0.000 0.00% 4.071
Planning and Regulatory Services 5.925 5.397 0.528 8.91% 0.966
Enterprise and Sustainable Development 6.940 6.775 0.165 2.38% (0.376)
Roads, Transportation and Fleet 21.713 21.795 (0.082) (0.38%) 7.761
Education Resources 525.944 525.944 0.000 0.00% 128.077
Education 525.944 525.944 0.000 0.00% 128.077
Finance and Corporate Resources 49.367 49.367 0.000 0.00% 19.763
Finance Services - Strategy 2.834 2.776 0.058 2.05% 1.089
Finance Services - Transactions 20.285 20.263 0.022 0.11% 6.490
Audit and Compliance Services 0.417 0.433 (0.016) (3.84%) 0.141
Information Technology Services 9.160 9.255 (0.095) (1.04%) 6.683
Communications and Strategy Services 3.673 3.555 0.118 3.21% 1.431
Administration and Licensing Services 5.258 5.258 0.000 0.00% 1.576
Personnel Services 7.740 7.827 (0.087) (1.12%) 2.353
Housing & Technical Resources 19.005 19.005 0.000 0.00% 4.985
Housing Services 8.954 8.936 0.018 0.20% 1.200
Property Services 10.051 10.069 (0.018) (0.18%) 3.785
Social Work Resources 270.829 270.829 0.000 0.00% 69.101
Performance and Support Services 6.756 6.497 0.259 3.83% 1.767
Children and Families 49.929 50.727 (0.798) (1.60%) 11.676
Adults and Older People 212.592 212.592 0.000 0.00% 54.945
Justice and Substance Misuse 1.552 1.013 0.539 34.73% 0.713
Joint Boards 2.072 2.072 0.000 0.00% 0.638
1,006.197 1,006.197 0.000 0.00% 253.530
Revised Projected Projected Year to Date
Annual Outturn Outturn Actual
Budget Variance
Summary: £m £m £m £m
Resources Total 1,006.197 1,006.197 0.000 0.00% 253.530
CFCR 5.401 5.401 0.000 0.00% 0.000
Loan Charges 35.755 35.755 0.000 0.00% 0.000
Corporate Items (5.593) (5.593) 0.000 0.00% 0.138
2026/2027 Investments - T/f to Reserves 19.829 19.829 0.000 0.00% 0.000
Loan Charges - T/f to Reserves 6.843 6.843 0.000 0.00% 0.000
Loan Charges - Underspend 6.096 6.096 0.000 0.00% 0.000
Non-Domestic Rates - Underspend 2.700 2.700 0.000 0.00% 0.000
Empty Property Relief - Underspend 1.000 1.000 0.000 0.00% 0.000
Total Expenditure 1,078.228 1,078.228 0.000 0.00% 253.668
Council Tax 210.719 210.719 0.000 0.00% 64.837
Less: Council Tax Reduction Scheme (26.228) (26.228) 0.000 0.00% (8.070)
184.491 184.491 0.000 0.00% 56.767
General Revenue Grant 438.388 438.388 0.000 0.00% 134.889
Non Domestic Rates 427.417 427.417 0.000 0.00% 131.513
Transfer from Reserves 27.932 27.932 0.000 0.00% 0.000
Total Income 1,078.228 1,078.228 0.000 0.00% 323.169
Net Expenditure 0.000 0.000 0.000 0.00% (69.501)
Period Ended 10 July 2026 (No.4)
Revenue Budget Monitoring Report
SOUTH LANARKSHIRE COUNCIL
40

Page 41

Note:  While the Year to Date Actual at period 4 presents a net deficit position (£13.495m), this is timing only.  The forecast outturn shows
a breakeven position (section 5.1). 
Appendix 2
Revised Projected Projected Year to Date
Annual Outturn Outturn % Note Actual
Budget Variance
Budget Category £m £m £m £m
Employee Costs 17.393 17.377 0.016 0.09% 4.396
Property Costs 62.761 62.761 0.000 0.00% 16.767
Supplies and Services 0.523 0.523 0.000 0.00% 0.098
Transport and Plant 0.195 0.195 0.000 0.00% 0.091
Administration 5.604 5.620 (0.016) (0.29%) 0.483
Payment to Other Bodies 2.682 2.682 0.000 0.00% 0.006
Payment to Contractors 0.806 0.806 0.000 0.00% 0.722
Transfer Payments 0.000 0.000 0.000 0.00% 0.000
Financing Charges 33.918 33.918 0.000 0.00% 3.495
Total Controllable Exp. 123.882 123.882 0.000 0.00% 26.058
Total Controllable Inc. (141.769) (141.769) 0.000 0.00% (39.553)
Transfer to/(from) Balance Sheet (3.498) (3.498) 0.000 0.00% 0.000
Net Controllable Exp. (21.385) (21.385) 0.000 0.00% (13.495)
Loan Charges 21.385 21.385 0.000 0.00% 0.000
Net Controllable Exp. 0.000 0.000 0.000 0.00% (13.495)
SOUTH LANARKSHIRE COUNCIL
Revenue Budget Monitoring Report
Period Ended 10 July 2026 (No.4)
Housing Revenue Account
41

Page 42

42

Page 43

Report
Agenda Item 
Report to: Executive Committee
Date of Meeting: 19 August 2026
Report by: Executive Director (Finance and Corporate Resources)  
Subject: Capital Budget 2026/2027 and Monitoring for Period 4 -
1 April 2026 to 10 July 2026 
1. Purpose of Report
1.1. The purpose of the report is to:- 
 update the Executive Committee of progress on the General Fund Capital
Programme and the Housing Capital Programme for the period 1 April 2026 to
10 July 2026  
2. Recommendation(s)
2.1. The Committee is asked to approve the following recommendation(s):- 
(1) that the position of the General Fund Capital Programme, detailed in (section
4) and the Housing Capital Programme (section 5), be approved; 
(2) that the adjustments to the General Fund programme, listed at Appendix 1, be
approved; and
(3) that the revised programmes be monitored by the Financial Resources Scrutiny
Forum. 
3. Background
3.1. This report provides an update on the Capital programmes as well as a summarised
monitoring position as at 10 July 2026 (Period 4).  Spending has been split into two
separate sections below: 
 General Fund Capital Programme (which includes Education, Social Work,
Roads and Other General Services) (Section 4)
 Housing Capital Programme (Section 5) 
4. General Fund Capital Programme
4.1. 2026/2027 Budget: The revised programme for the General Fund is £98.167 million
(summarised in Appendix 2).  This revised programme consists of the base budget
plus carry forward projects and adjustments which have been agreed by the Executive
Committee up to and including its meeting on 24 June 2026. 
4.2. The programme of £98.167 million also includes proposed adjustments totalling an
overall decrease of £11.335 million.  These are detailed in Appendix 1. 
4.3. The overall funding available of £98.167 million to support the programme is detailed
in Appendix 3.  
4
43

Page 44

4.4. 2026/2027 Forecast:  As noted in 4.1, the total capital spending programme for the
year is £98.167 million. 
4.5. Appendix 3 also shows a forecast for the financial year of £98.167 million. 
4.6. 2026/2027 Actual Position:  Actual spend incurred to the 10 July 2026 totals £6.381
million.   
4.7. Actual funding received to 10 July 2026 is £10.815 million.  This is shown in Appendix
3.  Relevant officers will continue to closely monitor the generation of all income
including receipts. 
5. Housing Programme 
5.1. 2026/2027 Budget:  Appendix 4 summarises the position on the Housing programme
as at 10 July 2026. The revised Housing Capital programme for the year is £94.740
million. 
5.2. Programme funding for the year also totals £94.740 million.  Appendix 4 summarises
the position on the Housing programme as at 10 July 2026. 
5.3. 2026/2027 Forecast:   As noted in 5.1, the total capital spending programme for the
year is £94.740 million.  Current estimates from the Resource have identified an
outturn of £94.740 million for the year. 
5.4. 2026/2027 Actual Position:  Spend to 10 July 2026 on the Housing Capital
Programme amounts to £12.603 million.   
5.5. As at 10 July 2026, £12.603 million of funding had been received. 
5.6. Regular monitoring of both the General Fund Programme and the Housing
Programme will be carried out in detail by the Financial Resources Scrutiny Forum
and reported on a regular basis to the Executive Committee. 
6. Employee Implications
6.1. None.  
7. Climate Change, Sustainability and Environmental Implications
7.1. There are no implications for climate change, sustainability or the environment in terms
of the information contained in this report. 
8. Risk and Other Implications
8.1. The main risk associated with the Council’s Capital Programme is an overspend.  The
risk has been assessed as low given the detailed project management plans prepared
and monitored for each project.  The risk of overspend is managed through four weekly
Investment management meetings. 
9. Integrated Impact Assessment and Consultation Requirements
9.1. This report does not introduce a new policy, function or strategy or recommend a
change to existing policy, function, or strategy and, therefore, no impact assessment
is required. 
9.2. There was also no requirement to undertake any consultation in terms of the
information contained in this report.  
44

Page 45

Jackie Taylor
Executive Director (Finance and Corporate Resources) 
28 July 2026 
Link(s) to Council Values/Priorities/Outcomes
 Accountable, Effective, Efficient and Transparent 
Previous References
 South Lanarkshire Council, 25 February 2026
 Executive Committee, 24 June 2026 
List of Background Papers
 Capital Ledger prints to 10 July 2026 
Contact for Further Information
If you would like to inspect the background papers or want further information, please contact: 
Lorraine O’Hagan, Head of Finance (Strategy)
Ext:  2601 (Tel:  01698 452601)
E-mail:  lorraine.o’hagan@southlanarkshire.gov.uk  
45

Page 46

APPENDIX 1 
Proposed Adjustments 
Community and Enterprise Resource 
People and Place Local Authority Direct Award
Funding has been made available to take forward active travel initiatives by
supporting active and sustainable travel.  This will involve promoting initiatives to
increase the frequency of active travel journeys, through developing walking
routes to schools, parks and in town centres. Projects include a bike hire pilot,
further work to promote the Think, Move Breath campaign, road safety education,
maintenance and enhancement of active travel routes, and support for community
led events at Clyde Cycle Centre.  These have been provided to the Scottish
Government to confirm eligibility to allow programming of works. 
Approval is sought to increase the 2026/2027 capital programme by £0.140 million
which will be funded by Transport Scotland through the People and Place Local
Authority Direct Award 2026/2027. 
Road Safety Improvement Fund
Transport Scotland have awarded South Lanarkshire Council £0.787 million in
connection with the Road Safety Improvement Fund for 2026/2027. Roads have
identified projects, based upon casualty reduction priorities as reported to the
Road Safety Forum. 
Detailed accident investigation reports have been collated for each location by the
Traffic and Transportation team.  These reports will be used to prioritise the
projects listed below. 
A70, Douglas – M74 J12 northbound
off ramp
B743, Strathaven to council
boundary
A70, Glespin to Council boundary A70, B7078 Junction to Rigside
A721, Newbigging to Elsrickle B758, Blantyre Farm Road, Blantyre
to Uddingston
A702, Council boundary to M74 J14 B7078, Canderside to Blackwood
B7086, Strathaven to Kirkmuirhill Newhousemill Road at Bridge, EK
B7078, M74 Junction 10 to M74 J11 Harsh Braking Sites – Various locals 
Approval is sought to increase the capital programme by £0.787 million.   
Cycling Scotland Grant Award 
Additional funding has been awarded by Cycling Scotland for new cycle storage
and shelter repairs.  Using this funding, shelter installations are proposed at the
following schools: 
Stonelaw High School Bankhead Primary School
Stonhehouse Primary School James Aiton Primary School
Kirkton Primary School Abington Primary School
Forth Primary School Neilsland Primary School
Spittal Primary School Carstairs Primary School 
£0.140m 
£0.787m 
46

Page 47

In addition, David Livingstone memorial Primary School will have additional cycle
hoops and a scooter rack installed. 
Approval is sought to increase the capital programme by £0.121 million.   
East Kilbride Town Centre
As a result of savings on demolition costs and updated profiling on the project, the
anticipated spend in 2026/2027 is lower than originally budgeted. The budget
released by the reduced cost of the demolition will be retained within the overall
project budget of £50.3 million with the design planning stage for the Town Hall
ongoing. 
Approval is sought to transfer £7.183 million into the 2027/2028 Capital
programme. 
Hamilton Town Centre
Due to the timescales confirmed for the demolition of the New Cross Centre, and
the former Bairds’ building, the anticipated date for the start of demolition setup
on sites is March 2027 with a combined tender package being progressed.   
As a result, the budget required this year will be reduced to reflect fees and minor
spend. 
Approval is sought to transfer £3.341 million into the 2027/2028 Capital
programme. 
Larkhall Leisure Centre
The forecast spend in 2026/2027 for Larkhall Leisure Centre is anticipated to be
less than budgeted, reflecting the cost profile information from Hub South West
following financial close for the enabling works.   
Approval is sought to transfer £1.836 million into the 2027/2028 Capital
programme.   
Leisure and Culture Transformation Fund 
The specification and content of the Improvements to Accessibility / Wi-Fi
Accessibility project have expanded with a broader scope than was originally
thought possible, following the rollout of a new front of house system in SLLC
properties.  However, due to the complex nature of the systems integration and
the different logistical requirements across the various locations, additional costs
are required to take the project to completion.   
Alongside this, consideration has been given to the Lifeguard Technology
project.  SLLC have confirmed that this project is not viable at this time due to
the availability of expertise and suitable suppliers.  It is proposed that £0.010m
of the budget be retained for feasibility costs to continue to explore options for
this project in the longer term, and that the remaining budget of £0.390 million to
be reallocated to the Improvements to Accessibility / Wi-Fi Accessibility project. 
£0.121m 
(£7.183m) 
(£3.341m) 
(£1.836m) 
(£0.390m)
£0.390m 
Minor Adjustments (£0.023m)  
TOTAL ADJUSTMENTS (£11.335m) 
47

Page 48

APPENDIX 2 
SOUTH LANARKSHIRE COUNCIL       
CAPITAL EXPENDITURE 2026/27       
GENERAL FUND PROGRAMME 
FOR PERIOD 1 APRIL 2026 TO 10 JULY 2026 
£m  
Total Revised Budget – Period 2 109.502  
Proposed Adjustments  (11.335)  
Total Revised Budget 98.167   
2026/27
Budget 
Period 4
Proposed
Adjustments 
Revised
2026/27
Budget
Resource £m £m £m    
Community & Enterprise 79.602 (11.335) 68.267
Education 15.297 - 15.297
Finance & Corporate 0.498 - 0.498
Housing & Technical 13.605 - 13.605
Social Work 0.500 - 0.500    
TOTAL CAPITAL PROGRAMME 109.502 (11.335) 98.167      
48

Page 49

APPENDIX 3
SOUTH LANARKSHIRE COUNCIL       
CAPITAL EXPENDITURE 2026/2027      
GENERAL FUND PROGRAMME 
FOR PERIOD 1 APRIL 2026 TO 10 JULY 2026 
2026/27
Base
Budget 
2026/27
Revised
Budget 
2026/27
Forecast 
Spend 
2026/27
Forecast
Variance 
2026/27
Actual to
10/07/26      
Expenditure £m £m £m £m £m      
General Fund Programme 108.952 98.167 98.167 - 6.381 
Income
2026/27
Budget
2026/27
Revised
Budget  
2026/27
Actual
To
10/07/26         
£m         £m   £m
Prudential Borrowing 54.520 45.501   0.000
Developers Contributions 1.775 1.775   0.000
Partners 3.071 4.150   0.984
Scottish Government:     
- Capital Grant 25.982 25.959   7.366
Levelling Up Fund 4.196 4.196   2.440
Capital Receipts 4.500 4.500   0.025
Specific Reserves 9.438 6.616   0.000
Revenue Contribution 5.470 5.470   0.000      
TOTAL FUNDING 108.952 98.167   10.815 
49

Page 50

APPENDIX 4 
SOUTH LANARKSHIRE COUNCIL       
CAPITAL EXPENDITURE 2026/2027       
HOUSING PROGRAMME 
FOR PERIOD 1 APRIL 2026 TO 10 JULY 2026 
2026/27
Annual 
Budget  
2026/27
Forecast
Spend
2026/27
Forecast
Variance
2026/27
Actual to
10/07/26 
£m £m £m £m
Expenditure 
2026/27 Budget  94.740  94.740  -  12.603     
2026/27
Annual 
Budget  
2026/27
Actual to
10/07/26 
£m   £m     
Income         
Capital Funded from Current Revenue 33.851   3.493
Capital Receipts -   0.093
Prudential Borrowing 33.385   5.962
Scottish Government Specific Grant:    
- New Build 18.474   2.919
- Open Market Purchase Scheme 8.910   -
- Mortgage to Rent 0.120   0.081
Other Income -   0.055 
94.740   12.603 
50

Page 51

Report
Agenda Item 
Report to: Executive Committee
Date of Meeting: 19 August 2026
Report by: Executive Director (Finance and Corporate Resources)  
Subject: Update to Funding 
1. Purpose of Report
1.1. The purpose of the report is to:-
[purpose]
 advise Members of additional funding that has been made available to the
Council by the Scottish Government and other external sources since the last
report to this Committee (24 June 2026)
[1purpose]
2. Recommendation(s)
2.1. The Committee is asked to approve the following recommendation(s):-
[recs]
(1) that the additional funding totalling £1.589 million, detailed in appendices 1 and
2, be noted. 
3. Background
3.1. In year funding can change, and this can be in relation to funding for specific purposes
or funding expected and already included in our budget planning. 
3.2. Additional funding may either be paid through the General Revenue/Capital Grant
mechanism or by the completion of appropriate grant claims. 
3.3. Details of the additional funding is attached in appendices 1 and 2 of the report. The
report details additional funding that has been reported by Resources as part of the
additional resources’ notification process, as well as any additional funding that has
increased the Council’s budget by more than £0.100 million. 
4. Employee Implications
4.1. None. 
5. Financial Implications
5.1. Additional Revenue funding of £0.541 million has been identified across 2026/2027.
This is detailed in Appendix 1. 
5.2. Additional Capital funding of £1.048 million has been identified for 2026/2027. This is
detailed in Appendix 2.   
5.3. Resource budgets will be updated to reflect this additional funding.  Where
appropriate, details of spending plans will be presented to Resource Committees for
approval. 
5
51

Page 52

6. Climate Change, Sustainability and Environmental Implications
6.1. There are no implications for climate change, sustainability or the environment in terms
of the information contained in this report. 
7. Risk and Other Implications
7.1. There are no other implications in terms of the information contained in this report. 
8. Integrated Impact Assessment and Consultation Requirements
8.1. This report does not introduce a new policy, function or strategy or recommend a
change to existing policy, function or strategy and, therefore, no impact assessment
is required. 
8.2. There was also no requirement to undertake any consultation in terms of the
information contained in this report. 
Jackie Taylor
Executive Director (Finance and Corporate Resources) 
22 July 2026 
Link(s) to Council Values/Priorities/Outcomes
 Accountable, Effective, Efficient and Transparent 
Previous References
 None 
List of Background Papers
 Additional Funding Grant Awards 
Contact for Further Information
If you would like to inspect the background papers or want further information, please
contact:- 
Lorraine O’Hagan, Head of Finance (Strategy)
Ext:  5637 (Tel:  01698 455637)
E-mail: lorraine.o’hagan@southlanarkshire.gov.uk
52

Page 53

Appendix 1 
Additional Revenue Funding 
Resource  Description  2026/2027
£m 
Total
£m 
Method
Social Work Children (Care and Justice) (Scotland) Act 2024
Funding is to support costs associated with
implementing new and additional duties under the
Act. The Act will raise the maximum age of referral
to the children’s hearings system up to cover 16
and 17-year-olds until they reach the age of 18
which raises the maximum age of initial referral to
the Children’s Reporter. 
0.209 0.209 Scottish
Government
Housing and
Technical
Funding for Resettlement Teams
This funding is intended to support resettlement
staffing costs to support the integration of refugees
including displaced Ukrainians, people seeking
asylum and other forced migrants within Scotland’s
communities.   
0.122 0.122 Scottish
Government
Education Scottish Disability Assistance
Additional funding to support the collection and
submission of supporting information for Child
Disability Payment (CDP), Adult Disability Payment
(ADP), and Pension Age Disability Payment
(PADP) applications. These processes are intended
to reduce barriers for clients and ensure Social
Security Scotland case managers receive the
information required to make accurate decisions. 
0.210 0.210 Scottish
Government 
TOTAL REVENUE FUNDING 0.541 0.541 
53

Page 54

Appendix 2 
Additional Capital Funding 
Resource  Description  2026/2027
£m 
Total
£m 
Method
Community
and
Enterprise
People and Place Local Authority Direct Award
Funding has been made available to take forward
active travel initiatives supporting active and
sustainable travel, promoting initiatives to increase
the frequency of active travel journeys, by
developing walking routes to schools, parks and in
town centres.   
Projects include a bike hire pilot, further work to
promote the Think, Move Breath campaign, road
safety education, maintenance and enhancement of
active travel routes, and support for community led
events at Clyde Cycle Centre. 
0.140 0.140 Strathclyde
Passenger
Transport
Community
and
Enterprise
Road Safety Improvement Fund
Transport Scotland have awarded South
Lanarkshire Council £0.787 million for 2026/2027 in
connection with the Road Safety Improvement
Fund. Roads have identified the projects below to
be prirotised based upon casualty reduction
priorities, as reported to the Road Safety Forum. 
A70, Douglas – M74 J12
northbound off ramp
B743, Strathaven to council
boundary
A70, Glespin to Council
boundary
A70, B7078 Junction to
Rigside
A721, Newbigging to
Elsrickle
B758, Blantyre Farm Road,
Blantyre to Uddingston
A702, Council boundary to
M74 J14
B7078, Canderside to
Blackwood
B7086, Strathaven to
Kirkmuirhill
Newhousemill Road at
Bridge, EK
B7078, M74 Junction 10 to
M74 J11
Harsh Braking Sites –
Various locals 
0.787 0.787 Transport
Scotland
Community
and
Enterprise
Cycling Scotland Grant Award
Additional funding has been awarded to the Council
by Cycling Scotland for new cycle storage and
shelter repairs at the following schools. 
Stonelaw High School Bankhead Primary School
Stonhehouse Primary
School
James Aiton Primary School
Kirkton Primary School Abington Primary School
Forth Primary School Neilsland Primary School
Spittal Primary School Carstairs Primary School 
In addition, David Livingstone memorial Primary
School will have additional cycle hoops and a
scooter rack installed. 
0.121 0.121 Cycling
Scotland 
TOTAL CAPITAL FUNDING 1.048 1.048 
54

Page 55

Report
Agenda Item 
Report to: Executive Committee
Date of Meeting: 19 August 2026
Report by: Executive Director (Housing and Technical Resources)  
Subject: Estate Strategy: 2026 to 2036 
1. Purpose of Report
1.1.  The purpose of this report is to:- 
 present proposals for South Lanarkshire Council’s 10-Year Estate Strategy for
(2026 to 2036), attached as Appendix 1, which is supported by a proposed £24m
capital investment programme, and seek approval of that programme alongside
progression to Stage 2 consultation 
2. Recommendation(s)
2.1. The Committee is asked to approve the following recommendation(s):- 
(1) that the 10-year Estate Strategy (2026 to 2036) be approved; 
(2) that the proposed £24 million capital investment programme, as detailed in
Section 5, be approved;
(3) that it be agreed to progress with Stage 2 consultation (August to September
2026), as set out of Section 7 of this report;
(4) that the proposed development of a front door approach to Council Service
delivery be supported, with further engagement undertaken with members,
communities and service users prior to implementation;
(5) to note that a further report will be presented to Committee in October 2026
providing feedback on the Stage 2 consultation;
(6) to note that an annual update on the new 10-year Estate Strategy will be
presented to the Executive Committee; and
(7) to note that a revised Corporate Asset Management Strategy 2027 to 2032 will
be presented to Executive Committee in early 2027, which will cover all asset
categories. 
3. Executive Summary 
Context and Need for Change
3.1. The Council’s operational estate, comprising 358 assets across multiple services,
represents a significant physical footprint. While it has supported service delivery over
many years, much of the estate is now ageing, configured around traditional single-
service use, and not consistently utilized to its full capacity. Current analysis indicates
average utilization of approximately 65%, with a number of buildings operating
significantly below this level.  
6
55

Page 56

3.2. This pattern of provision can limit opportunities to:- 
 co-locate services and improve integration
 make best use of staff and resources
 respond flexibly to changing patterns of demand 
At the same time, the Council must operate within a constrained financial environment
while responding to increasing expectations in relation to accessibility, service
responsiveness and environmental performance. 
Outcome of the Review (section 4)
3.3. To address these challenges, the Council requires a planned and proportionate
transition towards a more efficient, better-performing estate that is aligned to modern
service delivery and place-based priorities. 
3.4. Rather than a programme of building closures, the proposed Strategy brings together
a range of measures designed to improve the quality, accessibility, utilisation and
sustainability of the estate. These measures are summarised in Section 4.3 and 4.4
of this report. 
Targeted Capital Investment of £24m (section 5)
3.5. Subject to approval, a capital investment programme of £24 million is proposed to
support delivery of the Strategy. The proposed programme includes investment in
retained assets, replacement facilities, service consolidation projects, office
rationalization and a contribution towards depot modernisation, supporting the delivery
of a smaller, higher-quality and more sustainable estate. 
3.6. A summary of the proposed investment programme is provided in Appendix 2.
Detailed information on individual projects and locality-specific proposals is contained
within the LDP Area Profiles set out in Appendix 3. 
3.7. Savings (Section 5) 
The proposed rationalization of the estate will deliver revenue savings over time
through reductions in utility costs and energy consumption reduced rates, rent and
facilities management costs associated with leased or surplus assets.  Savings
identified from the proposals including office accommodation will generate savings of
£3.0m. 
3.8. New Front Door Approach (Section 6 and Appendix 4) 
The Strategy includes the development of a proposed front door approach, intended
to provide a clearer and more consistent way for residents to access Council services
across localities.  The model would operate through a network of accessible locations,
supported by digital channels and informed through engagement with Members,
communities and service users. 
3.9. Subject to Committee approval, work will commence during 2026/2027 to further
develop the front door approach with Members, communities and service users. This
engagement will help shape the model, identify appropriate locations and inform any
future implementation proposals. 
3.10. Consultation (Section 7) 
Stage 1 consultation validated the requirement for a property review, enabling
progression of the data-led analysis of the different assets in the Council estate,
including building types, uses, condition, and the requirement to meet future needs.  
56

Page 57

3.11.  Subject to approval of this report, Stage 2 will take place between August and
September 2026. Stage 2 of the consultation will seek to understand the potential
impact of proposals on service users, communities and partners and assess the level
of support for, or concern about, proposed changes. 
3.12. Climate Change and Affordability Context (Section 8) 
The scale and condition of the Council’s estate presents a significant challenge in
relation to climate targets. The estimated cost of achieving a net zero estate is
currently beyond available and foreseeable resources. 
3.13. The Strategy, therefore, supports the Council's climate objectives through a
combination of estate rationalisation, targeted investment in retained assets and
improvements in energy performance. While full estate decarbonisation remains
unaffordable within current resources, the proposals represent a “fabric first approach”
which allows a deliverable pathway towards a lower-carbon estate. 
3.14. The Council's long-term approach is to establish a smaller, more efficient and
financially sustainable core estate through implementation of this Strategy. This will
provide the platform for future investment in decarbonization measures as assets
reach lifecycle replacement and funding opportunities become available. 
3.15. While the timing and extent of future investment will be influenced by affordability,
technology and national policy, the Strategy ensures that future resources are
concentrated on those buildings that continue to support long-term service delivery
and communities. This provides a realistic framework for progressively reducing
emissions and improving environmental performance over time. 
4. Outcomes of the Review 
Overview
4.1. The proposed 10-Year Estate Strategy provides a framework for the long-term
management, investment and improvement of the Council's operational estate. It
seeks to ensure that the estate remains aligned to future service requirements,
demographic change, customer expectations, affordability pressures and the Council's
wider climate change objectives. 
4.2. The Strategy is supported by a targeted capital investment programme of £24 million,
as agreed as part of the 2025/2026 budget, to improve the quality, accessibility,
sustainment, and operational performance of assets that form part of the Council's
long-term retained estate. The Strategy, therefore, combines investment in key
buildings with a range of measures designed to improve utilisation, reduce duplication,
support integrated service delivery and ensure that resources are focused on facilities
that provide the greatest benefit to communities and service users. 
Strategic Approach
4.3. The proposed Strategy combines investment, service improvement and estate
rationalisation to create a smaller, higher quality and more sustainable estate. The
distribution of assets across each of the principal categories of change is summarised
in Table 1. 
57

Page 58

Change Category Number of
Properties
Investment in Retained Properties - Improvements to
buildings that will form part of the long-term core estate. 
52
Replacement and Re-provision into improved
accommodation - Services relocating into improved facilities
or replacement buildings. 
3
Service Consolidations - Activities being consolidated into
existing buildings with available capacity. 
2
Lease Expiry - Withdrawal from leased accommodation and
consolidation into Council-owned buildings
5
Surplus/Under-utilised Properties - Removal of vacant,
obsolete or low-demand assets that are either already
decommissioned or no longer required for service delivery.
18
Table 1- Summary of Proposed Estate Improvements and Changes 
4.4. The proposed Strategy balances significant investment in retained assets with service
improvement, consolidation and rationalisation, creating a more efficient, accessible
and sustainable estate. The categories of change summarized in Table 1 provide the
framework through which the Council will reshape its operational estate over the next
decade. 
Local Development Plan Area Based Proposals
4.5. Appendix 3 provides a detailed overview of the proposed changes within each of the
Council's 14 Local Development Plan (LDP) areas. This appendix details properties
proposed for investment; services proposed for reprovision or consolidation; proposed
lease exit; operational rationalization proposals; and surplus properties identified for
removal from the estate. 
4.6. This locality-based approach allows Members to consider proposals within the context
of local service provision, community need, property condition and future investment
priorities. 
5. Investment Proposed and Savings
5.1. The Council has committed £24 million of capital investment to support the initial
phase of the 10-Year Estate Strategy. This funding forms part of a wider programme
of estate investment. Certain projects identified within the Strategy, including depot
rationalisation, may require additional investment from alternative funding sources and
future capital spend. 
5.2. This investment will be directed toward projects across multiple locations, improving
the condition, compliance and energy performance of retained assets. It will support
the modernization of buildings that communities and services rely upon, ensuring they
are fit for purpose, more efficient to operate, and capable of supporting future service
delivery models.  
58

Page 59

5.3. It is proposed that the investment is profiled over three years to coincide with the
programme of works as described in Appendix 2. As follows: 
 £7.30m in 2026/2027
 £11.70m in 2027/2028
 £5m in 2028/2029 (linked to depot rationalisation) 
This phased approach will allow the Council to deliver early improvements while
maintaining flexibility to respond to consultation outcomes and evolving service
requirements. 
The 2026/2027 investment of £7.29m includes the following:   
Element Amount
Condition Improvement Works   £       4,223,300.00 
Boiler Upgrade Works  £          400,000.00 
New Community Sports Facilities    £       1,257,120.00 
Depot Rationalisation Design Development   £          250,000.00 
Proposed Consolidations   £          413,437.00 
Office Accommodation Rationalisation (Desk Booking
System)  £          250,000.00 
Demolition of Exited Properties – various locations  £          150,000.00 
Children’s Care Facility Improvement Works  £          150,000.00 
ASN Provision   £          200,000.00 
£       7,293,857.00 
5.4. The £24 million investment programme represents the initial funding allocation
available to support delivery of the Strategy. Whilst Appendix 2 identifies depot
rationalisation as part of the wider Strategy, the estimated total cost of this project is
currently £18 million. Of this amount, £5 million is included within the £24m
programme, with the balance subject to alternative funding sources and future
approvals through the Council's capital programme and governance arrangements. 
5.5. The condition improvement allocation represents a programme of investment in
retained operational assets that are expected to form part of the Council's long-term
estate. The programme is anticipated to include a combination of building fabric
improvements, compliance works, lifecycle replacements, accessibility enhancements
and energy efficiency measures. These interventions will help improve building
performance, support utilisation of retained assets, reduce liabilities and positively
contribute to the Council's longer-term decarbonisation objectives.’ 
5.6. It is proposed that the programme of £24m is approved and work progresses preparing
for the projects.  The proposed early investment focuses on essential works where
there is a clear and evidenced need to address building condition, statutory
compliance and energy performance. 
5.7. The proposed rationalization of the estate will deliver revenue savings over time
through: 
 reductions in utility costs and energy consumption
 reduced rates, rent and facilities management costs associated with leased or
surplus assets  
59

Page 60

Savings identified from the proposals including office accommodation will generate
£3.0m and will be delivered through changes to the estate as described in Appendix
3.  This will be over the period to 2039. 
5.8. It is likely that future capital receipts may also be realised because of the
implementation of this strategy. These are subject to market conditions, asset
conditions, and any required community engagement, and therefore cannot be fully
quantified at this stage. 
5.9. The move toward modern, flexible working spaces, along with the implementation of
hybrid working will reduce the overall footprint of office accommodation. This is
expected to deliver medium-term savings through: 
 withdrawal from older, less efficient leased accommodation
 reduced facilities and estate operating costs
 consolidation of dispersed teams into fewer, higher-quality locations 
5.10. The final financial implications will be presented within the report to the Executive
Committee in October 2026 following stage 2 public consultation. 
6. Proposed Front Door Approach
6.1. The front door approach is a key initiative that will be developed through a phased
approach as part of this Strategy.  Subject to approval, the intention is to work with
Members, communities and service users to shape the model and determine how it
can best support access to Council services across South Lanarkshire. 
6.2. Aligned with our place-based priorities, this model aims to use our existing buildings
and digital platforms to create a simpler way for residents and service users to contact
the council and understand where and how they can engage with the council to access
services within their locality, whilst making effective use of existing staff, buildings and
current/future digital channels. This is about providing a greater range of access points
to customer services offering telephone and computer access supported by customer
services staff at certain locations. 
6.3. As set out above, the front door approach is a practical extension of the Estate
Strategy, linking retained assets directly to how services are accessed and delivered
within communities. 
6.4. A number of existing libraries and customer-facing facilities may have the potential to
support a future front door approach. Any locations taken forward will be informed
through engagement with Members, communities and service users, and no decisions
on individual locations are being sought through this report. 
6.5. It is proposed that development of the front door approach is progressed during
2026/2027, including engagement with Members, communities and service users. Any
future implementation proposals will be informed by that engagement and brought
forward through future reports as required. Accordingly, Committee has been asked to
support progression of the development work described in Recommendation 4. 
6.6 Further information on the front door approach can be found in Appendix 4. 
60

Page 61

7. Approach to Consultation
7.1. As set out in the report to the Executive Committee in March 2025, the Council
committed to informing residents and others about the development of the Estate
Strategy and to engaging all audiences, especially users of our properties and assets,
in the development of that strategy. In doing so, we advised that we aimed to:- 
 inform stakeholders, by providing details about the review
 seek views on future requirements
 be transparent about what we recommend, and why
 be realistic about the challenges
 give confidence about the future 
7.2. Stage 1 consultation was launched on 22 April 2025 and ran until Friday 30 May 2025.
It included a short survey, which asked whether people approved the approach being
taken and whether a smaller, more flexible estate is the best way to use public money,
meet local needs and address climate change. The findings were reported to the
Executive Committee in June 2025. 
7.3. Stage 1 consultation validated the requirement for a property review, enabling
progression of the data-led analysis of the different assets in the Council estate,
including building types, uses, condition, and the requirement to meet future needs. 
7.4.  Subject to approval of this report, Stage 2 will take place between August and
September 2026. Stage 2 of the consultation will seek to understand the potential
impact of proposals on service users, communities and partners and assess the level
of support for, or concern about, proposed changes. 
7.5 Consultation results from Stage 2 will be used to feedback to the Executive Committee
in October 2026.   
8. Climate Change, Sustainability and Environmental Implications
8.1. The Estate Strategy has been developed having regard to the Council's climate
change commitments, Sustainable Development and Climate Change Strategy, and
the wider ambition to support Scotland's transition to net zero by 2045. 
8.2. The Council's operational estate comprises a large and diverse portfolio of buildings
of varying age, condition and energy performance. Previous analysis has identified
that the cost of fully decarbonising the operational estate would significantly exceed
currently available and foreseeable resources. Consequently, the Strategy adopts a
realistic and prioritised approach, focusing available investment on assets that will
continue to form part of the long-term retained estate. 
8.3. The proposed £24 million investment programme includes significant investment in
condition improvements, and energy-related infrastructure. The proposed £24m
investment includes investment in condition improvements and energy-related
infrastructure within retained operational assets. As many projects remain at an early
stage of development, the specific carbon reduction benefits cannot yet be quantified.
However, the proposed works will improve the condition and performance of buildings
that are expected to form part of the Council's long-term estate and will provide a
foundation for future decarbonization investment and energy-efficiency improvements.  
61

Page 62

8.4. Further information on the strategic approach to climate change, sustainability and
estate decarbonization is contained within Appendix 1. Project-specific investment
proposals and associated estate improvements are set out within Appendices 2 and
3. 
9. Employee Implications
9.1. There are no immediate employee implications associated with this report, however,
there will be implications relating to future changes in employees work locations and
employees will be supported through this change through communication, sufficient
notice and excess travel where eligible. 
10. Financial Implications
10.1. The financial implications for this report are detailed in Sections 4 and 5. 
10.2. The Council has committed £24 million of capital investment to support the initial
phase of the 10-Year Estate Strategy. This includes a £5 million contribution towards
depot rationalisation. The total cost of depot rationalization is currently estimated at
£18m, with the balance subject to alternative funding arrangements and future capital
approvals. Savings identified from the proposals including office accommodation will
generate £3.0m and will be delivered through changes to the estate. 
10.3. As projects are developed (such as the new community pavilions, youth facilities and
Depot changes), any requirement for revenue spend will be considered.  It is expected
that the majority of these costs will be funded from within existing resource budgets
held for the existing properties, or from increased income).  We will continue to update
members as project development progresses. 
10.4. The proposals and associated cost figures contained in this report are provided for
strategic and feasibility purposes only. All financial figures referenced represent high-
level feasibility estimates aligned to Royal Institute of British Architects (RIBA) Stages
0-1 and indicate the potential cost of projects. They do not constitute a fully developed
project costing and remain indicative, subject to further site survey, option appraisal,
design development and risk assessment. 
11. Integrated Impact Assessment and Consultation Requirements
11.1.  An overarching Integrated Impact Assessment (IIA) for the proposed Strategy can be
accessed via the link below and the report presented in October 2026 will detail the
individual IIA’s per project. 
Estate Strategy Review Plans and policies - South Lanarkshire Council 
11.2. Trade Unions will be updated on the strategy proposals and ongoing meetings will be
set up with Trade Unions to consult on ongoing activity and progress and any future
employee implications. 
12. Strategic Environmental Assessment
12.1. As we have not received any communication from the Consultation Authorities within
the ten working days consultation period on the pre-screening opinion for the Estate
Strategy, we can now assume that no further SEA work is required for this report.  
62

Page 63

13. Risk and Other Implications
13.1. The Estate Strategy is a long-term, adaptive framework. The proposals presented at
this stage will continue to evolve through ongoing engagement, detailed feasibility
work, and regular review. Future governance arrangements will be designed to ensure
the Estate Strategy remains a live and continuously reviewed programme. This will
include providing updated reports to Executive Committee on an Annual basis,
allowing the Council to adjust priorities as service needs, community expectations, and
financial pressures evolve. 
13.2. It should be noted that a revised Corporate Asset Management Strategy 2027 to 2032
will be prepared early 2027 and presented to Executive Committee covering all asset
categories. The Estate strategy will feed into a revised Property Asset Management
Plan. 
Stephen Gibson
Executive Director (Housing and Technical Resources) 
29 July 2026 
Link(s) to Council Values/Priorities/Outcomes
 Accountable, effective, efficient and transparent
 Good quality, suitable and sustainable places to live 
Previous References
 Estate Strategy Update Report 12 March 2025 and 17 June 2025 (Executive
Committee) 
List of Background Papers
 IIA Strategy 
Appendices
Appendix 1 – Estate Strategy 2026 to 2036
Appendix 2 – Investment Programme Summary
Appendix 3 – LDP Area Profiles and Investment Proposals
Appendix 4 – Front Door Approach 
Contact for Further Information
If you would like to inspect the background papers or want further information, please contact:
-
Craig Jardine Head of Property Services
Ext (Tel 01698 454073)
e-mail: craig.jardine@southlanarkshire.gov.uk 
63

Page 64

64

Page 65

Appendix 1 
SOUTH LANARKSHIRE COUNCIL
ESTATE STRATEGY  
2026 – 2036 
6
65

Page 66

2 
Contents 
1. Introduction and Purpose ......................................................................................... 6
1.1. Background ....................................................................................................... 6
1.2. Purpose............................................................................................................. 7
1.3. Scope ................................................................................................................ 8
1.4. Structure ........................................................................................................... 9
1.4.1.   Strategic Context ............................................................................................. 9
1.4.2.   Place Based Approach .................................................................................... 9
1.4.3.   Theory of Change ............................................................................................ 9
1.4.4.   Case for Change  ............................................................................................. 9
1.5.  Council Resources ........................................................................................... 9
2. Strategic Context ..................................................................................................... 12
2.1. National Policy ................................................................................................ 12
2.2. Regional Strategy ........................................................................................... 16
2.3. Local Strategy ................................................................................................. 17
2.4. Place-Based Approach ................................................................................... 21
2.5. Theory of Change ........................................................................................... 23    
3. Current Position ...................................................................................................... 24
3.1.  Case for Change ............................................................................................ 24
3.2.  Estate Overview ............................................................................................. 25
3.3.      Condition ........................................................................................................ 26
3.4.      Economic Lifespan ......................................................................................... 27
3.5.      Functional Suitability ...................................................................................... 28
3.6.      Backlog Maintenance ..................................................................................... 29
3.7.      Utilisation ....................................................................................................... 30
3.8.      Sustainability .................................................................................................. 30   
3.9.      Conclusion  ..................................................................................................... 32
4. Future Proposals ..................................................................................................... 33
4.1.      Strategic Objectives ....................................................................................... 33
4.2.      Place Making ................................................................................................. 33
4.3.      SWOT Analysis .............................................................................................. 34
4.4.      High Quality Service Delivery......................................................................... 35
66

Page 67

3 
4.5.      Utilisation and Co-location ............................................................................. 35
4.6.      Cost Effectiveness ......................................................................................... 36
4.7.      Sustainability .................................................................................................. 36
4.8.      Assessment Criteria ....................................................................................... 37
4.9.      Core/Flex/Tail ................................................................................................. 38
4.10.    Core/Flex/Tail Analysis .................................................................................. 38
4.11.    Delivering the Estate Strategy........................................................................ 39
5. Strategic Outcomes ................................................................................................ 42
5.1. Strategic Outcome Classifications .................................................................. 42
5.2. Proposed Estate Profile .................................................................................. 43
5.3. Key Patterns ................................................................................................... 45
5.4.     Statutory Resilience in Education ................................................................... 45
5.5.     Tiered Approach to Leisure and Sports .......................................................... 45
5.6.     Rationalisation of Operational Depots ............................................................. 45
5.7.     Consolidation of the Office Estate ................................................................... 46
6.       Estate Investment .............................................................................................. 46
6.1.     Investment Proposal ....................................................................................... 46
6.2.     Project Types .................................................................................................. 48
6.3.     Consultation  ................................................................................................... 48 
6.4.     Office Rationalisation ...................................................................................... 48
6.5.     Depot Rationalisation  ..................................................................................... 48
6.6.     Community Sports Facilities ............................................................................ 48
6.7.     Operational Decarbonisation........................................................................... 48
6.8.     Condition Improvement Works ........................................................................ 49
6.9.     Front Door Approach ...................................................................................... 49
7.      Conclusion  ......................................................................................................... 49 
67

Page 68

4 
Table of Figures
Figure 1: Condition Ratings ........................................................................................... 26
Figure 2: Economic Lifespan ......................................................................................... 27
Figure 3: Functional Suitability ...................................................................................... 29
Figure 4: Baseline Building Emissions .......................................................................... 31  
68

Page 69

5 
Table of Tables
Table 1: Council Resources ............................................................................................  9
Table 2: National Policy ................................................................................................. 12
Table 3: Regional Strategy ............................................................................................ 16
Table 4: Local Strategy .................................................................................................. 18
Table 5: South Lanarkshire Estate SWOT Analysis ....................................................... 34
Table 6: Strategic Objectives Definitions ....................................................................... 38
Table 7: Core, Flex and Tail Definitions ......................................................................... 38
Table 8: Principal Delivery Mechanisms  ....................................................................... 40
Table 9: Strategic Outcome Classifications ................................................................... 42
Table 10: Current Estate and Proposed Estate Profiles ................................................ 44
Table 11: Strategic Objectives Scoring Matrix ............................................................... 46 
69

Page 70

6 
1. Introduction and Purpose
This document sets out South Lanarkshire Council’s 10-year Estate Strategy (2026-
2036). The development of this strategy marks a step change in the Council’s approach
to managing, maintaining, and investing in its buildings. By using collated data
combined with detailed insight from building users, the Council has been able to
implement a more transparent, objective approach which will help it modernise and
improve the buildings which support its communities. 
The Council’s estate has evolved over decades in response to changing service
demands, community needs, and funding environments. This has resulted in a diverse
portfolio of buildings that varies widely in age, condition, performance, and suitability. In
recent years, increasing financial pressures, sustainability requirements, and shifts in
how services are delivered have made it clear that a different approach to estate
planning is required.
This Estate Strategy is the Council’s response to this challenge. It reflects a move away
from incremental, reactive decision-making towards a more deliberate and evidence-led
approach to planning for the future. One that is grounded in a clear understanding of
how buildings are used, what they cost, and the role they play in supporting the
Council’s wider ambitions.
1.1 Background
Work on the Estate Strategy has taken place alongside a broader shift in how South
Lanarkshire understands and plans for its communities. Over recent years, the Council
has strengthened its focus on place-based work through the development of Local
Place Plans, refreshed community profiles and the preparation of Local Development
Plan 3 (LDP3). This work has provided a richer and more detailed understanding of the
character, challenges and opportunities within each of South Lanarkshire’s
communities, from densely populated urban neighbourhoods in Rutherglen and
Cambuslang to the dispersed rural settlements of Clydesdale. As this picture has
become clearer, it has reinforced the importance of reshaping the Council’s Estate in a
way that is responsive to the distinct needs of different places, rather than applying a
one size fits all model of provision.
The decision to develop a new Estate Strategy also builds on earlier corporate
commitments, including the Council’s Climate Change and Sustainability Strategy and
its recognition that the scale and condition of the current estate is a barrier to meeting
statutory Net Zero obligations. Committee reports in 2024 and 2025 highlighted the
need to reduce carbon emissions from buildings, modernise the operational footprint
and direct investment to the assets that have a long-term role. At the same time, the
Council’s engagement with local communities as part of LDP3 and other planning
activity highlighted recurring themes: the need for accessible, welcoming spaces;
concerns about the condition and suitability of older buildings; and the importance of
locating key services within the heart of towns, villages and neighbourhoods. These
70

Page 71

7 
insights have helped shape this Strategy, ensuring it is grounded not only in asset data
but in how people experience and use their local places.
The Strategy has therefore developed in parallel with, and draws insight from, the place
evidence, engagement findings and spatial understanding being established through
LDP3. While the Estate Strategy does not replicate planning policy or determine land
use allocations, it aligns with the same principles: strengthening town and
neighbourhood centres, supporting sustainable local living, improving equity of access,
responding to demographic change and ensuring that public investment supports
resilient, connected and healthy communities. Decisions made about the estate over the
next decade will therefore reinforce, rather than undermine, the long-term spatial
direction for South Lanarkshire.
Together, this background provides the context for the Estate Strategy. It reflects the
recognition that buildings cannot be considered in isolation; they are part of the lived
experience of place. By drawing on the emerging place evidence and community insight
gathered through LDP3, the Strategy sets out a more grounded and locally responsive
approach to shaping the future estate; one that acknowledges the unique identity,
challenges and priorities of different parts of South Lanarkshire while meeting the
Council’s wider financial, environmental and service objectives.
1.2. Purpose
The Estate Strategy has been developed by Housing and Technical Resources, with
support from Service Leaders through the formation of the Estate Strategy Working
Group, and regular updates to the Corporate Management Team. The document is
intended to be reviewed and updated on an annual basis as projects evolve, and
subsequent delivery budgets emerge. 
The purpose of this Estate Strategy is to provide a clear, evidence-driven framework for
how The Council will reshape its operational estate over the next decade. It responds to
the significant financial, environmental and service pressures facing the organisation,
recognising that the current estate is larger, older and more carbon-intensive than is
sustainable, and does not consistently support the modern, flexible and digitally enabled
ways in which services are now delivered. In this context, the estate is not simply a
collection of buildings, but a key enabler of organisational transformation. This strategy
therefore sets out a planned approach to delivering a smaller, higher-quality and more
efficient estate that supports the Council’s long-term ambitions, responds to the needs
of local communities, and improves outcomes for residents.
Central to this Strategy is the application of the Council’s People, Planet and Progress
ambitions, as defined the LDP3. The Strategy therefore aims to prioritise equity of
access, recognising the differing needs of communities across South Lanarkshire,
including areas of deprivation, rural settlements and places experiencing demographic
change. It aims to strengthen local places by consolidating services into more
accessible, integrated and fit-for-purpose buildings that reinforce town centres, support
71

Page 72

8 
local regeneration and contribute to more sustainable patterns of service delivery. At the
same time, it aims to support the transition to Net Zero by focusing investment on the
buildings that will form part estate for the long term, reducing carbon emissions and
ensuring resources are used responsibly.
By bringing together organisational priorities, technical evidence and place-based
analysis, this Estate Strategy aims to provide a coherent direction for the estate. The
framework approach will enable the Council to plan ahead, make best use of public
money, and respond effectively to future service needs, while maintaining the flexibility
required to adapt to changing circumstances.
The Strategy is supported by a £24 million capital investment programme, which will
improve the quality, accessibility, sustainability and operational performance of assets
that form part of the Council’s long-term retained estate. Additional projects identified
within the Strategy may be subject to separate funding arrangements and future
capital approvals. This investment will support improved community facilities,
replacement sports community facilities, enhanced youth provision,
depot modernisation, office accommodation improvements and targeted condition
improvement works across the estate.
A key feature of the Strategy is the introduction of a Front Door Approach to customer
access. Using a network of existing community-based assets, residents will be provided
with clearer and more consistent routes to Council services within their locality. The
approach is intended to complement estate investment and rationalisation by ensuring
that changes to the Council’s estate deliver tangible improvements in how residents
access information, advice and services across South Lanarkshire. 
1.3. Scope
The Estate Strategy covers all operational non-domestic properties owned and/or
managed by South Lanarkshire Council or the Council’s arms-length non-profit
organisation: South Lanarkshire Leisure and Culture (SLLC). The properties are
organised across five key resource areas, which are explored in detail in the Council
Resources section of this document. 
The five Resources are:
• Housing and Technical 
• Community and Enterprise 
• Education 
• Social Work 
• Leisure (Council Owned, SLLC Operated).
Some property types such as offices and Lifestyles buildings are utilised by multiple
resources simultaneously. 
72

Page 73

9 
The Estate Strategy does not cover assets with any proportion of elderly residential
accommodation, or investment assets which are held by the council purely for income
generation (non-operational estate). 
1.4. Structure
This report is structured to provide a clear and comprehensive roadmap for the
development and management of the Council’s estate. The adopted structure is divided
into the following key sections:
1.4.1. Strategic Context
This section outlines the National legislation, Regional initiatives and local strategies
which provide the foundation for the development of the Estate Strategy. It identifies the
key strategic priorities of each which are expected to require estate change to unlock
and deliver. 
1.4.2 Place based Approach
This section assesses the current state of The Council’s estate, including detailed
descriptions of the individual buildings and their current performance including
condition, functional suitability, and utilisation. This section highlights the key challenges
which arise from the current configuration of the estate.
1.4.3. Theory of Change
This section defines the future vision and strategic objectives for the estate. Using data-
led Assessment Criteria, this section demonstrates the alignment of each asset with the
Strategic Objectives through the assignment of a Core / Flex / Tail designation. 
1.4.4. Case for Change
This section details the strategic outcomes of the proposal: Retain, Replace, and Exit. It
identifies key opportunities for investment, assisting alignment of proposed interventions
against strategic intent. Finally, it sets out the current plan for each asset by LDP area,
demonstrating the impact of proposals on the local community.
1.5. Council Resources
This section provides an overview of the Council’s Resources and the functions they
deliver. It sets out the range of services supported by the estate, highlighting their key
responsibilities and strategic roles within the Council. 
Resource Core
Functions
Key Services/Activities Strategic Role
Community
&
Enterprise
Deliver
frontline and
support
services that
• Facilities, Waste &
Grounds (cleaning,
catering, janitorial, parks
and open spaces) 
Maintains safe,
clean, and
well-connected
communities and
73

Page 74

10 
enhance
quality of life
and enable
sustainable
development.
• Roads, Transportation &
Fleet (network
maintenance, fleet
management) 
• Planning & Regulatory
(planning, building
standards, environmental
health) 
• Enterprise & Sustainable
Development (economic
growth, regeneration,
sustainability programmes) 
supports
economic
development and
climate action. 
Housing &
Technical
Manage
housing
provision and
the Council’s
wider property
and
construction
functions.
• Housing Services
(allocations, homelessness
prevention, tenancy
support, rent collection,
community safety)
• Technical Services (design
and delivery of capital
projects, property
maintenance, compliance,
asset management) 
Delivers
affordable
housing, sustains
tenancies, and is
responsible for
asset compliance
and safety. 
Leisure
(SLLC)
Promote
health,
wellbeing and
cultural
engagement
through
leisure, sport
and culture.
• Sports & Recreation
(leisure centres, pools,
fitness, outdoor sports) 
• Culture & Learning
(libraries, museums, arts
centres) 
Community Facilities
(halls, pavilions, event
spaces)
A non-profit third
party entity
(South
Lanarkshire
Leisure and
Culture) operates
the leisure
portfolio on behalf
of the council. It
aims to support
active lifestyles,
lifelong learning,
and social
inclusion,
contributing to
healthier and
more connected
communities. 
Education Deliver
learning and
development
• Early Years & Schools
(primary, secondary, ASN) 
Improves
attainment,
reduces
74

Page 75

11 
across schools
and
communities.
• Community Learning &
Development (youth work,
family support, lifelong
learning) 
• Support Services
(psychology, inclusion,
home-school links) 
inequality, and
delivers
high-quality
learning
environments
aligned to
national priorities.
Social
Work
Provide care,
protection and
support for
vulnerable
individuals and
communities.
• Community Support
(health and wellbeing,
independence) 
• Children & Families
(support, protection,
fostering, adoption) 
• Adult & Older People (care
at home, day care,
residential services) 
• Justice Services
(community payback,
rehabilitation) 
Delivers statutory
services and
works with
partners to
improve
outcomes for
vulnerable groups
and support
independent 
Table 1: Council Resources  
75

Page 76

12 
2. Strategic Context
This section outlines the internal and external factors which shape the Estate Strategy,
including national legislation and priorities, regional initiatives, and the Trust’s goals. 
This document is intended to be read in conjunction with all documents outlined within
this section. It therefore does not attempt to repeat the information provided but
provides insight into their impact on the development of the Estate Strategy and
highlights any initiatives within them which must be enabled through estate change. 
By first setting out a clear context for the development of the strategy, this section
establishes the rationale for change, clarifies the key drivers influencing future estate
requirements, and provides a transparent framework against which the proposed estate
proposals, investment priorities, and sequencing can be understood and assessed.
2.1 National Policy
Strategic
Direction 
Summary  Relevance to the Estate
Strategy 
Scotland's Climate
Change Plan 2026-
2040 
The Climate Change Plan
2026-2040, published in
March 2026, sets out the
Scottish Government's
policies and proposals for
meeting Scotland's statutory
carbon budgets between
2026 and 2040 and
achieving Net Zero
greenhouse gas emissions
by 2045. The Plan replaces
the previous annual
emissions target framework
with legally binding carbon
budgets and establishes a
coordinated programme of
action across the economy,
including buildings, energy,
transport, land use and the
public sector.
The Estate Strategy supports
the objectives of the Climate
Change Plan through
estate rationalisation,
investment in retained assets,
improved energy performance
and the creation of a smaller,
more sustainable operational
estate. The Strategy provides a
framework that will enable
future decarbonisation activity to
be focused on buildings which
have a long-term service
delivery role, while supporting
the Council's wider climate
change and sustainability
objectives.
National
Performance
Framework (NPF) 
The NPF sets outs a
purpose, values and a series
of National Outcomes to be
delivered. Its purpose is to
focus on creating a more
successful country with
opportunities for all of
Scotland to flourish through
The strategy should align to the
NPF until it is superseded,
ensuring the optimised estate
contributes to broader social,
economic and environmental
goals. 
76

Page 77

13 
increased wellbeing, and
sustainable and inclusive
economic growth. 
As of March 2025, the
Scottish Government is
reforming NPF to better drive
public sector reform, improve
collaboration and empower
communities. The current
NPF outcomes are still in
operation as is the duty to
regard them. 
Programme for
Government  
This Programme for
Government outlines the
Scottish Government's
commitments and priorities
for the year 2025/26. It is
designed to grow the
economy, eradicate child
poverty, tackle climate
change and deliver high-
quality and sustainable
public services. 
The strategy contributes to the
delivery of high-quality public
services through a collaborative,
well managed and efficient built
estate. 
Learning Estate
Strategy  
The Scottish Government’s
Learning Estate Strategy
focuses investment on
improving outcomes for
learners, communities and
the economy by enhancing
and extending joined up
learning experiences. This
includes integrating
experiences and locality-
based services. 
The education estate of South
Lanarkshire is analysed as part
of the strategy, which focuses
on opportunities to co-locate
services to realise the full
potential of education assets. It
also considers investment in
these assets to improve service
delivery. 
Single Scottish
Estate  
Aligned with the Programme
for Government, the Single
Scottish Estate (SSE)
programme aims to deliver a
more efficient approach to
public sector property
management across the
Scottish public sector estate.
It works with public sector
Whilst the core SSE programme
does not include local authority
assets, the Estate Strategy
aligns with the programme
goals and presents
opportunities for further
consolidation in the future. 
77

Page 78

14 
bodies to develop and
deliver targets to retain the
right size and condition of
estate in the right place at
the right times. 
Scottish Futures
Trust –
Sustainable
Infrastructure for a
Thriving Scotland
(2025-2030
Corporate Plan)  
This plan outlines how SFT
aim to deliver for Scotland by
driving best practice in
infrastructure strategy,
investment, delivery and
management. In particular,
through enhancing public
sector property asset
management by maximising
sharing and use of existing
buildings, integrating
maintenance and
decarbonisation and
securing best value from
surplus assets. 
The strategy aligns with the plan
as it aims to enhance SLC’s
property asset management
through estate rationalisation,
collaboration and
decarbonisation.  
Climate Change
(Emissions
Reduction
Targets)
(Scotland) Act
2019  
The climate change
(Emissions Reduction
Targets) (Scotland) Act 2019
– sets a statutory target of
net zero emissions by 2045.
This legislation aligns
Scotland’s efforts with the
global objectives of the Paris
Agreement, aiming for a
sustainable and climate-
resilient future. 
The net zero strategy is aligned
to Scotland’s national target and
identifies a recommended
pathway and associated
building decarbonisation
measures to support and meet
net zero by 2045, for the
buildings within the scope of this
estate strategy. South
Lanarkshire Council have also
aligned their target to the
national target of net zero by
2045.  
Scottish National
Adaptation Plan
(SNAP) 2024-2029
The Scottish National
Adaptation Plan 2024-2029
outlines the actions the
Scottish Government and
partners will take to respond
to the impacts of climate
change over the next five
years, from 2024 to 2029. It
builds on the third UK
Climate Change Risk
Assessment (UKCCRA3)
Consideration should be given
in the following areas that will
directly relate to the ongoing
implementation of the Estate
Strategy.
• Increasing frequency of
heatwaves.
• Wetter winters.
• Drier summers.
• Climate adaptation
works.
78

Page 79

15 
and the independent advice
of the Climate Change
Committee, addressing 61
identified risks and
opportunities for Scotland.
The plan emphasizes a just
transition, ensuring
adaptation measures are fair
and inclusive, particularly for
vulnerable communities such
as low-income households,
older people, minority ethnic
groups, and disabled people.
• Links to Climate Change
Strategy and Clyde
Adaptation Strategy.  
Heat in Buildings
Strategy (2021)  
The Heat in Buildings
Strategy (2021) outlines
Scotland’s plan to reduce
greenhouse gas emissions
from buildings and address
fuel poverty. The strategy
aims for all buildings in
Scotland to achieve zero
emissions by 2045. 
The strategy emphasises
eradicating fuel poverty and
aligns to the Fuel Poverty
Act 2019. 
It focuses on improving
energy efficiency of
buildings, including
converting homes using
high-emissions fuels to zero-
emissions heating, plans for
public engagement and
support services to help
households upgrade their
heating systems. 
The net zero strategy focuses
on identifying energy efficiency,
building fabric and identifying 
low carbon heating
opportunities to transition the
estate from fossil fuel to zero
emissions heating. The estate
strategy aligns with the
objectives of Scotland’s Heat in
Building Strategy (2021) to
reduce greenhouse gas
emissions from buildings. 
Proposed Heat in
Buildings Bill
(2024)  
The Proposed Heat in
Building Bill (2024) aims to
further Scotland’s
commitment to achieving net
zero emissions by 2045. The
bill ensures that all new
buildings applying for a
building warrant from April
2024 will need to install
The net zero strategy is aligned
to the objectives of the
Proposed Heat in Buildings Bill.
As energy efficiency measures
and low carbon heating systems
such as heat pumps are being
considered as decarbonisation
opportunities for buildings within
the estate. This includes a key
79

Page 80

16 
clean heating systems with
the aim of not requiring
future retrofit.  
The bill also included
measures to encourage the
development of heat
networks and aimed to
improve the energy
efficiency of home and
buildings, through the
potential reformed EPC
system among other
measures. 
Expected Revisions to the
bill 
The Acting Net Zero and
Energy Minister confirmed
there is intention to review
the Bill later in 2025 to
include: 
A target for decarbonising
heat systems by 2045. 
Provision to boost heat
network development 
Powers to set minimum
energy efficiency standards. 
focus of decarbonising the
heating systems within the
estate.  
Strategy scenarios have also
been modelled that include
mapping opportunities to
connect to proposed heat
network locations aligned to
South Lanarkshire Councils
LHEES report. These scenarios
can be furthered refined in the
future if detailed heat network
studies are commissioned. 
Heat Networks
(Scotland) Act
2021 
Scotland’s Heat Networks
Act (2021) introduces a
regulatory framework for the
supply of thermal energy
through heat networks,
including construction and
operation of these networks.
The Act requires the review
and designation of areas
particularly suitable for heat
network development and
operation across Scotland,
crucial to reduce greenhouse
gas emissions and transition
to an efficient and
sustainable heating system. 
It sets ambitious targets for
the amount of thermal
energy supplied by heat
Strategy scenarios have been
modelled that include mapping
opportunities to connect to
proposed heat network
locations aligned to South
Lanarkshire Councils LHEES
report. These scenarios can be
further refined in the future if
detailed heat network studies
are commissioned. 
80

Page 81

17 
networks, aiming for 2.6
terawatt hours by 2027, 6
terawatt hours by 2030, and
7 terawatt hours by 2035.  
Table 2: National Policy
At a National Level, there is a clear directive to move towards a smaller, greener and
more collaborative estate which maintains support for the delivery of high-quality
services. National Directive clearly demonstrates an expectation to not just encourage
greater internal collaboration through the delivery of modern, digitally integrated spaces
but also to work more closely with public sector partners and key players within the
community to deliver sustainable economic growth and reduced carbon utilisation
through major shared initiatives such as heat networks and town centre masterplanning.
2.2 Regional Strategy 
Strategic
Direction
Summary Relevance to the estate strategy
Glasgow City
Regional
Economic
Strategy 
The Glasgow City Regional
Economic Strategy sets out
commitment to transforming
the economy to become the
most innovative, inclusive and
resilient economy in the UK by
2030. 
In addition to enhancing
innovation through high quality
services, the strategy accelerates
South Lanarkshire’s progress
towards net zero, a key mission
for the Glasgow City Region.
Glasgow City
Region
National
Wealth Fund
Partnership
The Glasgow City Region
National Wealth Fund
partnership establishes a
framework for attracting
long-term public and private
investment to support
regionally significant
development priorities, with a
focus on inclusive economic
growth, net zero, infrastructure
modernisation, and
place-based regeneration.
The partnership creates
opportunities to align estate
investment and asset planning
with regionally backed funding
mechanisms, particularly where
estate change can enable
regeneration, energy transition,
and the co-location of services.
The Estate Strategy should
therefore support schemes that
are investable, flexible, and
capable of leveraging external
funding to maximise social,
economic, and environmental
value.
NHS
Lanarkshire
Our Health
Together
Our Health Together is NHS
Lanarkshire’s healthcare
strategy for 2024–2031, setting
out proposals to transform
models of care, shift delivery
closer to communities, reduce
inequalities and improve
The strategy provides a key
context for future service models
across the Lanarkshire Region.
The Council can support delivery
by helping to accommodate more
community-based and integrated
provision through its wider estate
81

Page 82

18 
long-term sustainability of
services. The strategy is led by
NHS Lanarkshire and focuses
on prevention, integration and
more flexible ways of delivering
care across Lanarkshire.  
where this aligns with local
priorities.
Table 3: Regional Strategy
At a Regional Level, there is a clear emphasis on collaboration, place-based investment
and inclusive economic growth across the Glasgow City Region. Regional initiatives
promote a more coordinated approach to the use of land and property, encouraging
shared use, regeneration and decarbonisation to support net zero ambitions. Together,
these drivers reinforce the need for an estate that is adaptable and outward-facing,
capable of enabling partnership working, community-based service models and
regionally significant initiatives where the Council can add value and contribute to
regional growth through its land, property and place-shaping role.
2.3 Local Strategy 
Strategic Direction Summary Relevance to the estate
strategy
Connect: Council
Plan 2022-2027 
The Connect plan outlines
South Lanarkshire’s vision,
values, priorities and outcomes,
aiming to improve the lives and
prospects of the people of South
Lanarkshire. It focuses on
delivering the best possible
services and value for money.
The plan also includes focus on
Planet – a sustainable future in
sustainable places.
The goals of the plan
include reduced carbon
emissions, a strong sense of
community, increased
ownership of local assets
and investment in services.
Asset rationalisation,
decarbonisation and
improved service delivery
contributes to the
achievement of these goals.
The strategy aims to reduce
estate carbon emissions,
assisting progress towards
2045 net zero targets. 
South Lanarkshire
Economic Strategy
2022-2027 
The South Lanarkshire
Economic Strategy 2022-2027
aims to create a flourishing,
green dynamic and equitable
South Lanarkshire. The strategy
focusses on three key themes of
sustainable, inclusive economic
The estate strategy is
aligned to key objectives of
the South Lanarkshire
Economic Strategy 2022-
2027, aiming to create
attractive places for people
and businesses to work,
82

Page 83

19 
development; People, Place and
Business and emphasises the
use of data to inform action.
The strategy builds on the
extensive work already
undertaken to achieve the
vision: Our Future is now:
building an environmentally
sustainable, climate resilient and
net zero South Lanarkshire
together in a fair and equitable
way. With activities focused on
People, Communities and
Place, the Natural Environment
and a Green Economy. 
visit and invest through a
high quality, efficient,
collaborative and fit-for-
purpose estate. Sustainable
infrastructure will be
progressed through the
development of operational
decarbonisation delivery
plans.
Corporate Asset
Management Plan
2021-2026
The Corporate Asset
Management Plan focuses on
ensuring Council assets
effectively support current and
future service requirements,
providing a framework for
prioritising future investments
and making rationalisation
decisions. 
The estate strategy will
provide the basis from which
renewed asset management
plans can be produced,
drawing on the
accompanying detailed
Delivery Plan.
Community Plan
2022-2032 
The Community Plan is an
ambitious plan for the future of
South Lanarkshire, focusing on
the improvement of community
wellbeing. 
The strategy contributes to
community wellbeing by
ensuring the high-quality
services are provided in the
right areas for community
needs, and by helping
protect the environment
through decarbonisation of
retained assets. 
South Lanarkshire
Leisure and
Culture Strategy
2022-2027
The Leisure and Culture
Strategy sets out the vision,
mission, values and objectives
out to 2027. Objectives include
being connected and engaged
and organisational sustainability,
The estate strategy
assesses current service
delivery and identifies
opportunities to improve
quality, alongside
developing a
83

Page 84

20 
allowing sustainable provision of
quality services in priority areas.
This includes reviewing facilities
for financially sustainability,
enabling quality service
provision, and reducing waste
and energy usage to be more
energy efficient. 
decarbonisation plan to
ensure the consolidated
estate is energy efficient
and progresses
organisational sustainability. 
Education
Resources Plan 
The Education Resources plan
sets out educational outcomes
and priorities for each year,
aiming to achieve excellence
and equity. The plan aims to
continually improve and enable
effective and efficient use of
resources. 
Local education provision is
fundamental to the
communities of south
Lanarkshire and maintaining
and investing in these
assets is therefore
fundamental to the success
of the estate strategy.
Hamilton
Masterplan
The Hamilton Masterplan seeks
to demonstrate a vision for a
better Hamilton that meets the
requirements of all, focusing on
combatting isolation, creating
opportunity and enriching the
lives of the community.
The estate implications of
the masterplan have been
considered through
consistent stakeholder
engagement, aiming to
understand how changes in
housing and active travel
impact service and service
delivery requirements, and
highlighting what is key to
continue to provide a vibrant
town centre hub. 
East Kilbride
Masterplan
The East Kilbride Masterplan
seeks to provide Scotland’s first
and largest new town,
responding to the changing use
of town centres by combining
urban living and civic areas.
The estate implications of
the masterplan have been
considered through
consistent stakeholder
engagement, aiming to
understand how changes
impact service and service
delivery requirements. The
strategy considers and
reflects the future use of
assets within the town
centre. 
Local Heat and
Energy Efficiency
Strategy (LHEES)
The LHEES sets out South
Lanarkshire Council’s long-term
approach to decarbonising heat
The Estate Strategy will
need to align with the
LHEES by supporting a
84

Page 85

21 
and improving energy efficiency
in buildings to meet national net
zero targets by 2045. It identifies
priorities including a fabric-first
approach, transition to zero
direct emissions heating
systems, and increased use of
heat networks.
fabric-first approach to
estate planning, identifying
opportunities to reduce heat
demand and supporting the
transition to zero direct
emissions heating systems
across the Council’s estate. 
Local Heat and
Energy Efficiency
Delivery Plan
(LHEEDP)
The LHEEDP sets out how
South Lanarkshire Council will
support implementation of the
LHEES over the next five years.
It includes the identification of
12 indicative heat network
zones which may be suitable for
future heat network
development.
The Estate Strategy will
need to take account of the
LHEEDP by considering
opportunities for
Council-owned assets to
support future heat
networks, including
safeguarding sites and
avoiding estate decisions
that would preclude
connection or impact any
planned heat networks,
subject to further heat
network analysis and
feasibility work. 
Sustainable
Development and
Climate Change
Strategy
This strategy has been informed
by extensive public engagement
and supports the development
of associated action plans. The
Council has measured and
reported its carbon footprint
annually since 2005–06, in line
with its legislative duty to
contribute to national net zero
targets by 2045. Ongoing asset
management and planned
maintenance keep buildings
operating efficiently, while new
build and refurbishment projects
are designed to meet required
building standards and achieve
a silver sustainability label.
The estate strategy
incorporates a net zero
strategy and delivery plan
that aligns to SLC’s net zero
target of 2045. The estate
strategy will support the
wider Sustainable
Development and Climate
Change Strategy and
identifies further
decarbonisation projects at
sites that are strategically
important and will be
retained long-term. It sets
out recommendations for
projects to deliver the
strategy and maximise
current available
decarbonisation capital
budgets. 
Table 4: Local Strategy
85

Page 86

22 
At a Local Level, council strategies place a strong emphasis on ensuring that land and
property assets actively support service delivery, environmental sustainability and
place-based priorities across South Lanarkshire. They highlight the need to use the
estate more efficiently, reduce carbon emissions, and align assets with changing service
models, town centre regeneration and community needs. The strategies also reinforce
the importance of rationalisation, investment in retained assets, and decarbonisation of
buildings to deliver long-term value for money. Taken together, they set a clear
expectation that the Estate Strategy will provide a coherent framework for managing,
investing in and repurposing council assets to support local priorities, improve
operational efficiency and contribute to wider economic and environmental objectives.
2.4. Place-Based Approach
In consideration of the broader Strategic Context, the Strategy applies a clear and
consistent place-based approach, ensuring that decisions about buildings are shaped
by the needs, characteristics and priorities of South Lanarkshire’s diverse communities.
This approach reflects both the Council’s strategic ambitions and the evidence gathered
through the emerging Local Development Plan 3 (LDP3), which highlights how patterns
of population change, accessibility, inequality and local priorities vary significantly
across towns, neighbourhoods and rural settlements. Taken together, this evidence
provides a strong foundation for aligning estate change with the realities of each place
rather than relying on historical patterns of provision.
At the heart of this approach is a shift away from managing buildings as isolated assets,
and towards understanding how the estate can support the social, economic and
environmental wellbeing of whole places. It recognises that services work better when
they are designed and located around the daily lives of residents, and that public
buildings have an important role as anchors of community resilience, local identity and
opportunity. By focusing on place, the strategy will aim to support regeneration and
improve access to services in ways that reflect real patterns of use and need.
In consideration of the broader Strategic Context, the Strategy applies a clear and
consistent place-based approach, ensuring that decisions about buildings are shaped
by the needs, characteristics and priorities of South Lanarkshire’s diverse communities. 
By integrating these insights with the technical assessment of each asset, the Estate
Strategy grounds future decisions in a deep understanding of what each community
values, what it needs, and how services can be delivered more effectively. The
approach supports tailored solutions by protecting anchor assets in rural areas,
reducing duplication in urban centres, strengthening Priority Places and aligning the
estate with wider regeneration, active travel and housing plans. It also guides the future
use of surplus assets, ensuring disposals, community transfers and redevelopment
contribute positively to local outcomes and reflect the priorities communities have
identified for their places.
86

Page 87

23 
Using this place-based evidence, decisions about retention, consolidation, replacement
and exit will be made with a clear understanding of what each community requires, what
services are currently provided from an asset, and how different services work best
together. This means identifying where anchor buildings must be protected in rural and
semi-rural areas; where urban neighbourhoods would benefit from consolidation into
higher quality multi-service hubs; and where duplication, poor condition or low utilisation
signal an opportunity to reinvest in stronger, more modern facilities nearby. It also
positions the estate to support the Council’s ambitions for 20-minute neighbourhoods by
focusing on accessibility, active travel and proximity to daily services, particularly in
fast-growing areas and town centres undergoing change.
This approach will also guide how buildings that are no longer required for Council
services are repurposed. Surplus assets will be made available for Community Asset
Transfer, local regeneration or redevelopment opportunities where appropriate, with
Local Place Plans, design briefs and LDP3 policies.
By prioritising place, the Estate Strategy enables the delivery of a future estate that is
not only smaller and more sustainable, but also better aligned with the needs of South
Lanarkshire’s towns, villages and neighbourhoods. It provides a framework for more
integrated, equitable and locally responsive services, and enables every property
decision to demonstrate support for key initiatives such as the creation of thriving,
resilient and well-connected places across South Lanarkshire.
2.5 Theory of Change
The Estate Strategy aims to provide a structured approach for reshaping South
Lanarkshire’s estate over the next decade. Its overarching purpose is to guide future
decisions on investment, rationalisation, co-location and disposal in a way that
strengthens service delivery, improves local places and supports long-term financial and
environmental sustainability. The process is deliberately iterative: as local priorities
evolve, service models change and new evidence becomes available, the assessment
of buildings and places will continue to be refined throughout the lifetime of the Strategy.
The Theory of Change describes how the Council will move from understanding the
current estate to delivering a future estate that is more resilient, more sustainable and
better aligned to community needs. It enables transparent decisions, that are evidence
based and grounded in the strategic objectives set out earlier in this document.
Meaningful change begins with a shared understanding of the estate as it is today. The
Asset Assessment Tool brings together data on condition, performance, running costs,
carbon impact, suitability and utilisation for every asset within scope. 
This provides a consistent, objective picture of how well each building supports its
intended purpose and what would be required to make it fit for future service delivery.
This technical evidence is complemented by engagement with service leads, allowing
the Council to validate data, understand operational pressures and consider future
87

Page 88

24 
demand. Together, these insights create a clear foundation for determining the long-
term role of each asset.
Place-based evidence strengthens this analysis. The emerging Local Development Plan
3, including its Community Profile Areas and Priority Places, provides a detailed
understanding of how different parts of South Lanarkshire are changing, in terms of
population, accessibility, inequality, infrastructure and local priorities. Estate decisions
will not be made uniformly across the authority but reflect the different needs and
characteristics of urban centres, expanding communities and rural settlements. Planned
regeneration activity, particularly in town centres, is also considered to align the estate
change with wider investment and enhance local quality of life.
Community engagement provides the final part of the evidence base. As proposals
emerge, they are tested with residents and service users to demonstrate they reflect
local experience, protect access to essential services and respond to community
priorities. This feedback allows the Council to refine proposals where appropriate,
ensuring that the future estate maintains equity of access and supports inclusive, place-
based outcomes.
By bringing these elements together, the Strategy provides a clear and coherent method
for determining which assets should be retained and improved, which require
replacement, and which no longer meet long term needs. Change will be delivered in a
planned and responsible way: investment will be focused on buildings that have a long-
term strategic role; opportunities for co-location will be used to support more modern
and integrated service delivery; and buildings that are no longer viable will be exited at
an appropriate time. This process aligns closely with digital transformation, service
redesign and the Council’s journey to net zero, ensuring that the estate evolves
alongside wider organisational change.
Applying this structured approach will result in a more coherent, efficient and place
focused estate. A smaller but higher quality core estate will allow investment to be
concentrated where it has the greatest impact, while reducing running costs and
backlog maintenance pressures. Surplus assets can be released for community use,
redevelopment or disposal, supporting regeneration, housing delivery and local priorities
identified through LDP3 and Local Place Plans. Across each locality, proposals will form
a clearer, more sustainable pattern of provision that improves accessibility, strengthens
local hubs and supports collaborative working across public services.
Over time, this approach will create an estate that is more adaptable, more resilient and
better able to meet the needs of South Lanarkshire’s communities. It will improve the
quality of the spaces people rely on, help reduce inequalities in Priority Places, and
contribute directly to stronger local places and better outcomes for residents. 
88

Page 89

25 
3. Current Position
3.1 Case for Change
South Lanarkshire Council is facing a combination of financial, environmental and
service pressures. As these pressures intensify, it is clear that the estate is not simply a
backdrop to service delivery; it is a critical enabler of the wider organisational change
needed to respond effectively.
Across the Council, services are evolving. Communities increasingly expect joined-up,
accessible and digitally enabled provision; demand is shifting both geographically and
demographically; and the organisation must operate within increasingly constrained
financial resources. However, the current estate does not provide the flexibility,
efficiency or sustainability required to support these new models of delivery. Many
buildings are ageing, costly to maintain and not well suited to integrated or modern
service models, limiting the Council’s ability to adapt services in line with service
priorities.
These challenges are reinforced by the scale of the financial and environmental
pressures facing the estate. The operational portfolio generates approximately 29,600
tonnes of CO₂e each year, with the majority arising from fossil fuel heating, alongside
significant and increasing energy and maintenance costs. Without intervention, these
pressures will continue to grow, reducing the resources available to protect and
modernise essential services.
At the same time, patterns of utilisation show that the estate is no longer aligned with
how communities use services. While Education buildings are generally well used,
many community, leisure and administrative assets operate below capacity. This means
the Council is maintaining and funding more space than is required, limiting the ability to
improve accessibility, reduce inequalities and support the creation of strong, sustainable
places.
The Council’s overarching ambition is to improve the lives and prospects of everyone in
South Lanarkshire, underpinned by the principles of People, Planet and Progress.
These priorities emphasise the need to tackle inequality, respond to climate challenges
and support sustainable economic growth through place-based approaches. In addition,
the adoption of the Marmot Principles highlights the importance of reducing health
inequalities through coordinated, community-focused interventions.
Taken together, these drivers demonstrate that estate change is not optional it is
fundamental to enabling the wider transformation required across the organisation.
Reshaping the estate provides an opportunity to consolidate services into better, more
accessible locations, reduce cost and carbon emissions, and support modern,
integrated service delivery. This Strategy sets out how that transition will be achieved in
a structured and responsible way, ensuring the estate becomes an active contributor to
the Council’s long-term objectives.
89

Page 90

26 
3.2 Estate Overview 
This section provides a high-level summary of the scale, composition, and overall
performance of the Council’s estate. It brings together the number and type of assets
across each service area, alongside headline indicators of asset quality (number of
assets with condition and suitability ratings of A/B) and average utilisation, to present a
clear picture of how the estate is structured and is performing at a portfolio level.
The overview highlights the relative distribution of assets across services, the proportion
of the estate that is in good condition and suitable for use, and the extent to which
buildings are actively supporting service delivery. Taken together, this provides an
accessible, “front-page” view of the estate, setting the context for the more detailed
analysis that follows.
At an estate-wide level, the Council manages a large and diverse portfolio, with a
significant concentration of assets in education and leisure alongside a broad range of
community, operational and civic properties. The majority of buildings are in good
condition and suitable for use, indicating that the estate broadly provides a sound
physical platform for service delivery.
The overall composition of the estate reflects how it has evolved over time, rather than a
single, strategically configured portfolio. The scale and distribution of assets across
multiple service areas, locations and property types indicate a relatively extensive and
dispersed estate, with varying roles and levels of dependency.
3.3 Condition
Building conditions refer to the overall physical state of a building and its components. It
is assessed through structured surveys and inspections. Key aspects of building
conditions include:
• Structural integrity: The stability and soundness of the building’s frame, foundations,
and load-bearing elements.
• Building fabric: The condition of walls, roofs, windows, doors, and finishes.
• Mechanical and electrical systems: Performance of heating, ventilation, air
conditioning, plumbing, and electrical installations.
• Compliance: Whether the building meets current health, safety, accessibility, and
regulatory standards
The condition ratings used in the Estate Baseline are primarily from survey exercise
undertaken in 2023 in a non-invasive manner, visually inspecting the various elements
of the estate’s properties and categorising their condition accordingly: 
• A: Performing well and operating effectively. The buildings and grounds support the
resource delivery.
90

Page 91

27 
• B: Performing well but with minor problems. The buildings and grounds generally
support the resource delivery.
• C: Showing major problems and/or not operating optimally. The buildings and
grounds impede the resource delivery.
• D: Does not support the delivery of resource service and impedes activities. 
Figure 1: Condition Ratings
The condition profile shows that much of the estate is performing adequately, providing
a generally stable platform for service delivery. However, a reasonable number of C and
D rated assets present a disproportionate risk, as these properties have the potential to
constrain or have the potential to disrupt services if not addressed. These assets will
require targeted attention within the Estate Strategy to determine the most appropriate
response, whether through focused investment, repurposing or longer-term change.
It is recognised that parts of the estate are supported by incomplete or historic condition
data. This reinforces the need for a more proactive and systematic programme of
condition surveys, ensuring that the estate baseline remains robust and up to date.
Improved data capture will be important following major investment or refurbishment,
helping to maintain the Estate Baseline over time and support the feedback loop
between estate investment and evidenced improvement in estate quality.
3.4. Economic Lifespan
Economic lifespan is the estimated period during which a building can continue to
deliver its intended function in a cost-effective manner before it becomes uneconomical
to maintain or operate. It reflects the point at which the cost of keeping the properties in
service through maintenance, compliance upgrades, and operational expenditure
outweighs the benefits of doing so. 
Economic lifespan is expressed as bands (e.g., 0, 10, 20, 40 years remaining) based on
these combined factors. Bands are assigned on an overall basis and a detailed
breakdown of the components of each assessment was unavailable for analysis.
Unknown lifespan indicates insufficient data rather than imminent failure.
0% 20% 40% 60% 80% 100%
Community & Enterprise
Education
Housing
Leisure
Social Work
A
B
C
D
91

Page 92

28 
Figure 2: Economic Lifespan
The modelled economic life profile indicates that a large proportion of the estate is
expected to remain operational over the long term, providing a broadly resilient
foundation for service delivery. However, the presence of assets with shorter remaining
life and variability across service areas highlights the need for forward-looking
investment planning, particularly for operational and leisure assets where pressures are
more evident. It is recognised that elements of the estate are supported by limited or
historic lifespan data. This reinforces the need for a more proactive and systematic
approach to economic life assessment, ensuring that the estate baseline remains
current and accurately reflects asset performance over time. Strengthening this
evidence base will support better-informed decisions on retention, investment and
longer-term change.
3.5. Functional Suitability
Functional suitability refers to the extent to which a building or space effectively
supports the activities, services, and operational requirements for which it is intended. It
considers factors such as layout, size, accessibility, and the ability to accommodate
modern service delivery models. A functionally suitable property enables efficient
workflows, meets user needs, and complies with statutory requirements, while an
unsuitable property can hinder performance, increase operational costs, and limit
flexibility for future adaptation. 
Functional Suitability is typically assessed through a structured evaluation of how well a
building meets the operational needs of its intended use. This involves looking at factors
such as:
• Layout and Space: Does the internal configuration support efficient workflows and
service delivery?
• Accessibility: Are entrances, circulation routes, and facilities compliant with
accessibility standards?
• Condition and Adaptability: Can the building accommodate modern technology
and future changes?
0% 20% 40% 60% 80% 100%
Community & Enterprise
Education
Housing
Leisure
Social Work 10
20
30
40
92

Page 93

29 
• User Experience: Does the environment support comfort, safety, and functionality
for staff and service users?
The following ratings have been adopted in assessing functional suitability across the
estate:
• A – Highly Suitable: The building fully meets functional requirements with minimal
or no limitations. Layout and facilities are optimal for current and future needs.
• B – Suitable: The building generally meets requirements but has some minor
limitations that do not significantly impact service delivery.
• C – Marginally Suitable: The building has notable shortcomings that affect
efficiency or user experience. Adaptation may be possible but could require
significant investment.
• D – Unsuitable: The building fails to meet functional requirements. Layout,
condition, or compliance issues severely hinder operations, and major refurbishment
or disposal may be necessary.
Given the diversity of the Council’s estate it is worth noting that a building that is
considered unsuitable for its current use may still be suitable for a number of alternative
uses. 
Figure 3: Functional Suitability
The functional suitability profile indicates that most of the estate is broadly fit for its
current purpose, particularly within education and social work assets. However, pockets
of C and D rated accommodation, most notably within the leisure and community estate,
highlight areas where buildings constrain service delivery or limit adaptability. These
assets will require targeted review through the Estate Strategy to determine where
intervention, reconfiguration or longer-term change is required to better align buildings
with current and future service needs.
93

Page 94

30 
3.6 Backlog Maintenance
Backlog maintenance represents the cumulative maintenance work required for assets
to remain safe, functional and capable of supporting service delivery. If left
unaddressed, backlog can increase operational risk, result in unplanned outages, and
lead to higher costs over time.
The Estate Strategy is informed by an Estates Maintenance Rating, which provides a
high-level, qualitative assessment of backlog maintenance for each asset. Assets are
categorised as Low, Medium or High, reflecting the relative scale of maintenance
required across building fabric, mechanical and electrical systems, and statutory
compliance obligations. This assessment indicates the overall level of maintenance
pressure affecting each asset and helps to highlight where risk may emerge.
It is important to recognise the limitations of this approach. The Estates Maintenance
Rating does not represent a calculated or modelled cost to restore an asset to “as new”
condition or to a defined standard such as condition B. Instead, it provides an indicative
view of maintenance burden rather than detailed surveys or costed schedules of work. 
This reinforces the need for continued improvement in asset intelligence over time. As
the Estate Strategy progresses, more detailed condition information and targeted
surveys will be required to support accurate cost modelling, prioritisation of investment
and informed decisions on retention, improvement or wider estate change.
3.7 Utilisation
Space utilisation considers how effectively buildings and spaces across the estate are
used to support service delivery. It reflects factors such as levels of occupancy,
frequency and patterns of use, and the extent to which space aligns with operational
requirements. High utilisation suggests space is being used efficiently, while low
utilisation may indicate underused or surplus space, leading to avoidable cost and
inefficiency. Understanding utilisation is therefore an important tool in identifying
opportunities for consolidation, redesign or repurposing of assets to better meet current
and future needs.
Developing a consistent utilisation metric across a diverse estate is inherently complex.
Different asset types operate in fundamentally different ways: offices can be assessed
using capacity and staff numbers, leisure facilities are influenced by visitor attendance,
and education buildings experience significant peaks and troughs linked to timetables,
with additional periods of underuse outside school hours. Variations in building size,
layout and the presence of multi-functional spaces further complicate direct comparison.
As a result, utilisation assessment requires a balance between simplicity and accuracy,
drawing on both quantitative data and qualitative judgement. Data availability across the
estate is currently inconsistent, with information collected using different methodologies
and to varying levels of completeness. 
94

Page 95

31 
The utilisation profile shows a highly variable estate, with education assets operating
close to capacity and offering limited flexibility, while leisure, housing and some
office-based functions exhibit significantly lower utilisation. This indicates an imbalance
between demand and space provision across the estate. This reinforces the need to
protect and optimise highly utilised assets, while actively reviewing under-utilised
buildings to explore opportunities for consolidation, alternative use or repurposing.
Improving utilisation will be key to reducing operating costs, supporting service change
and ensuring the estate is aligned with current and future demand.
3.8. Sustainability
The baseline operational carbon footprint of South Lanarkshire Council’s publicly owned
building estate is estimated at 29,606 tonnes of CO₂ equivalent (tCO₂e) in 2023/24.  Of
this total, approximately 70% of emissions are attributed to fuel consumption, including
gas, biomass, oil, and LPG while the remaining 30% are associated with electricity use.
A breakdown of Baseline building emissions by Resource is shown below: 
Figure 4: Baseline Building Emissions
The sustainability baseline demonstrates that carbon emissions and energy costs are
not evenly distributed across the estate but are instead concentrated within a relatively
small number of large, energy-intensive assets, particularly within the education and
leisure portfolios. This concentration presents both a challenge and an opportunity:
without targeted intervention, the Council will not meet its interim or long-term net zero
targets and will remain exposed to ongoing operational cost pressures and future
carbon offset liabilities.
Baseline Estate Emissions (TCO2e)
Education 16,850
Leisure 8,203
Housing 2,213
Social Work 1,570
Community & Enterprise 770
0
2,000
4,000
6,000
8,000
10,000
12,000
14,000
16,000
18,000
Baseline GHG emissions TCO2e by Estate Service
95

Page 96

32 
The business-as-usual trajectory clearly shows that incremental change and reliance on
grid decarbonisation alone will be insufficient. Continued dependence on fossil fuel
heating, combined with the current disparity between electricity and gas prices, creates
a structural risk that must be addressed through coordinated estate planning, energy
efficiency improvements and carefully sequenced decarbonisation activity.
This analysis demonstrates that achieving net zero will require a strategic, estate-wide
approach that prioritises investment where it will have the greatest carbon and financial
impact. Improving building performance, reducing demand, and targeting the
highest-emitting sites will be essential to accelerating progress while maintaining
affordability. Collectively, this evidence establishes a robust foundation for the Estate
Strategy to define a clear decarbonisation pathway that supports environmental
objectives, improves long-term resilience, and delivers better value from the Council’s
retained estate.
3.9 Conclusion
The Council’s estate is not sustainable in its current configuration. A combination of low
utilisation across significant parts of the portfolio, including some of the costliest assets
to operate and maintain, is creating ongoing pressure on revenue budgets. This is
compounded by a substantial backlog maintenance liability and the scale of investment
required to meet operational decarbonisation expectations. In parallel, much of the
estate has developed incrementally over time and is not well aligned to modern ways of
working, digital service delivery or emerging models of public service provision. Taken
together, these factors point to an estate that is increasingly expensive to operate,
inefficient in its use of space, and insufficiently adaptable to future change.
While these issues are clear when viewed at a macro, estate-wide level, they present
very differently across individual communities and service areas. Levels of utilisation,
dependency on local facilities, demographic pressures and the availability of alternative
provision vary significantly from place to place. As a result, decisions about the future of
the estate cannot be taken solely based on aggregate performance metrics. The Estate
Strategy must therefore be informed by a detailed understanding of local context and
pressures, ensuring that estate decisions support council-wide objectives for
sustainability, affordability and service transformation, while remaining sensitive to local
needs and the role that individual assets play within their communities. This balance is
essential to delivering an estate that is both strategically coherent and locally
responsive.
4. Future Proposals 
South Lanarkshire Council’s Vision for the estate must be an ambitious, forward-looking
statement. It must be a statement that success can be measured against, and one that
clearly indicates the formation of strategic objectives. 
96

Page 97

33 
Delivery will be achieved through a combination of targeted investment, service
improvement, service consolidation, reprovision and rationalisation, ensuring that
resources are focused on the buildings that best support communities,
service users and staff.
Our response to the wider strategic direction of the Council, as outlined in the Strategic
Context. This will drive us to target interventions where they are most needed and is
underpinned by three the interconnected principles outlined in Connect: People, Planet,
and Progress.
4.1. Strategic Objectives
The Strategic Objectives were approved by the Executive Committee in May 2025 and
will guide the direction of the Council’s estate over the next decade. They translate the
overarching vision for the estate into a clear set of practical priorities, providing a
consistent framework for decision-making on investment, rationalisation and the
configuration of service delivery over time.
In the context of this Estate Strategy, the objectives respond directly to the challenges
identified through baseline analysis, including rising revenue pressures, under
utilisation, backlog maintenance, the need for operational decarbonisation and the
evolution of service delivery models. Together, they establish a structured and
transparent basis for assessing the estate.
The objectives are also aligned to the Council’s wider ambitions around People, Planet
and Progress. Collectively, they aim to create an estate that is fit for purpose, resilient
and capable of responding effectively to changing service demand, while remaining
affordable, adaptable and locally responsive.
4.2. Placemaking
The estate is the catalyst for creating vibrant healthy and connected communities. This
objective focuses on designing spaces that reflect local identity, encourage social
interaction and support regeneration. Placemaking means the estate is not just a
collection of buildings, it is part of the fabric of South Lanarkshire, contributing to
economic growth, wellbeing and a strong sense of place for residents and visitors alike. 
How will we measure success?
• Evidence of estate projects supporting regeneration and masterplan priorities.
• Growth in co-location and multi-use of buildings to support community activity.
• Improved accessibility of assets, including proximity to public transport and active
travel.
• Positive feedback from communities and stakeholders on the role of council
buildings in their area.
97

Page 98

34 
4.3. SWOT Analysis
Taking account of both the macro-level challenges identified within the Estate Overview
and the local pressures highlighted in the area profiles, this section sets out the overall
SWOT analysis for the South Lanarkshire estate.
Strengths
• Overall functional suitability of the
estate is good
• Economic lifespan of most
buildings is well beyond 20 years
• Utilisation of the school estate is
strong
• Good utilisation for some key
leisure assets
• Well performing Education Estate 
Weaknesses
• Property distribution is not consistent
across LDP Areas or population
• Some asset types such as Depots and
Pavilions are generally in poor
condition and not fit for purpose
• Some areas of poor carbon
performance is impacting revenue
costs and overall energy efficiency
• Some data gaps remain, which must
be filled through an ongoing
programme of surveys to be
implemented as part of this strategy 
Opportunities
• Underutilisation of leasehold office
estate presents an opportunity to
rationalise to reduce revenue
expenditure
• Selected decarbonisation projects
across the estate are expected to
have a relatively short payback and
potentially significant carbon impact
• Align projects with funding
opportunities, such as Salix
Decarbonisation grants, to access
grants, and advance opportunities
to work more widely with the private
sector to access shared investment
potential. 
Threats
• Lack of recent survey data may lead
to missed opportunities for investment
• PPP agreements for secondary
schools (until 2039) prevent direct
benefit from energy savings, slowing
decarbonisation progress without
contract renegotiation.
• Ongoing energy price volatility
presents a significant risk to an estate
of this scale.
• Electricity costs are 5x gas, making
electrification financially challenging
without tariff reform.
• Increasing frequency and severity of
extreme weather events, including
flooding, overheating and storm
damage, creating risks to service
continuity, asset resilience,
maintenance costs and insurance
liabilities.
98

Page 99

35 
• Changing demographics including
ageing population and overall
population decline
• Utilisation across the estate will
continue to decline unless actively
managed
Table 5: South Lanarkshire Estate SWOT Analysis
The SWOT analysis highlights that while the estate provides a strong foundation, its
current configuration is not aligned with future service delivery, financial sustainability or
net zero requirements. There is a clear need to move toward a smaller, more efficient
portfolio that responds to changing demand and reduces cost and carbon exposure.
Strengths within the core estate should be protected and built upon, while weaknesses
and opportunities point to the need for consolidation, decarbonisation and improved use
of space. Together, these findings reinforce the need for a future estate that is more
focused, flexible and capable of supporting modern, place-based service delivery.
4.4 High Quality Service Delivery 
The estate is a critical enabler of service excellence. This objective focuses on enabling
every building to support the delivery of modern, inclusive and efficient services. It
means creating space that are safe, compliant and adaptable, designed for digital
connectivity and integrated service models. High-quality service delivery is about more
than functionality, it is about providing environments that enhance user experience,
improve accessibility and enable innovation across education, health, leisure and
community services.  
How will we measure success?
• Proportion of assets assessed as safe, compliant and fit for purpose for current
service delivery.
• Reduction in functional suitability issues that constrain or hinder service delivery.
• Increased provision of digitally enabled spaces that support modern and flexible
service models.
• Improved accessibility and inclusivity of buildings, including compliance with equality
and accessibility standards.
• Positive user and service feedback on the quality, accessibility and effectiveness of
service environments.
4.5 Utilisation and Co-location
The estate is designed to be used efficiently and flexibly. This objective focuses on
maximising the use of available space and reducing duplication by bringing services
99

Page 100

36 
together under one roof. Co-location enables integrated services delivery, improves
accessibility for communities and creates opportunities for collaboration. By optimising
utilisation, the estate becomes leaner, more adaptable and better aligned with modern
ways of working.
How will we measure success?
• Increased average utilisation across the estate, particularly within high-cost and
under-used assets.
• Growth in the number of services delivered through co-located or shared buildings.
• Reduction in duplication of space and accommodation serving similar or
complementary functions.
• Improved flexibility of space to support shared, hybrid and evolving service delivery
models.
• Evidence that estate decisions reduce floor space per service while maintaining or
improving service outcomes.
4.6 Cost Effectiveness
The estate is managed to deliver maximum value for money. This objective focuses on
enabling resources to be targeted where they have the greatest impact. By driving value
for money across the portfolio within the clear context of a place-based lens, the impact
on service delivery will be minimised.
How will we measure success?
• Reduction in total estate running costs, including energy, maintenance and facilities
management.
• Decrease in underutilised or high-cost assets that deliver limited value.
• Improved ratio of revenue cost (£/m²) across the retained estate.
• Evidence that capital investment is targeted at assets that are strategic, well-utilised
and capable of long-term retention.
• Reduction in backlog maintenance liability across the estate over time.
4.7. Sustainability
The estate is a driver for climate action and responsibility. This objective focuses every
decision to support the transition to net zero by 2045 through energy efficiency and
renewable technologies. Sustainability means lowering emissions, reducing operating
costs, and creating healthier environments, embedding resilience and long-term value
into the estate for future generations.
100

Page 101

37 
How will we measure success?
• Progressive reduction in estate-wide carbon emissions, through estate rationalisation,
investment in retained assets and future decarbonisation programmes.
• Decrease in fossil fuel reliance across the retained estate, including the transition to
low-carbon heating systems.
• Improvement in the energy performance of buildings, including reductions in energy
use per m².
• Reduction in energy-related operating costs through efficiency measures and on-site
renewable generation.
• Evidence that estate investment decisions embed long-term resilience, climate
adaptation and whole-life value.
Taken together, the five Strategic Objectives provide a clear and coherent response to
the challenges facing the Council’s estate and translate the vision into practical,
decision-making priorities. They recognise that the estate must do more than simply
house services; it must actively support placemaking, enable high-quality and modern
service delivery, use space efficiently through higher utilisation and co-location, remain
affordable in the face of growing financial pressures, and contribute meaningfully to the
Council’s net zero ambitions.
Collectively, these objectives establish a framework for addressing the unsustainability
of the current estate configuration characterised by underutilisation, high revenue costs,
backlog maintenance and the need for decarbonization while ensuring future investment
and change are purposeful, coordinated and aligned with wider Council priorities. They
also provide the basis for making informed, locally sensitive decisions that balance
estate-wide performance with the needs of individual communities, ensuring the estate
remains resilient, adaptable and fit for the future.
4.8 Assessment Criteria
The aim of the Assessment Criteria is to demonstrate the extent to which each asset
aligns with The Council’s long-term goals. The criteria adopted are explicitly linked to
the five Strategic Objectives of the Estate Strategy.
It is important to note that the assessment criteria do not determine final outcomes for
individual assets. Instead, they provide a structured framework for understanding
relative alignment with strategic priorities, highlighting where assets perform strongly
and where they limit the Council’s ability to deliver its future estate vision.
The criteria combine quantitative data with professional judgement, supported by
engagement with services through the Estate Strategy Working Group. This ensures
that alignment is assessed not only on technical performance, but also on service
needs, local context and anticipated future demand. Together, this approach provides a
101

Page 102

38 
robust and consistent evidence base, enabling informed decision-making while
recognising that final outcomes require further consideration of feasibility, service
implications and place-based factors.
Placemaking Service
Delivery
Utilisation and
Colocation
Cost
Effectiveness
Sustainability
Assesses
strategic
importance to
local service
provision,
accessibility
and proximity
to peers.
Assesses
functional
suitability,
condition, and
digital maturity. 
Assesses how
well space is
currently used,
the flexibility of
buildings to
accommodate
alternative
uses.
the relationship
between
operating costs,
maintenance
liabilities and
long-term value. 
Assesses
operational
carbon
performance
and energy
efficiency.
Table 6: Strategic Objectives Definitions
4.9 Core / Flex / Tail
Based on the outcomes of the assessment criteria, three categories were used to
indicate overall performance and alignment with the Strategic Objectives. These are
defined below:
Core Flex Tail
Assets which represent
the best quality estate
and are already
performing in line with
the Future Vision. Assets
which:
Assets which do not currently
meet quality standards but
have strategic significance.
Over time, the goal is to move
flex assets to core or tail.
Assets which:
Assets which are not
considered fit for purpose in
their current configuration
and may not be
economically adapted.
Assets which:
• Meet long term
strategic needs.
• Are accessible and
compliant.
• Are well utilised or
able to support
service consolidation.
• Require investment to
meet standards and
support long term needs
• Are well utilised or able to
support service
consolidation.
• Services will be effectively
provided albeit from other
locations. 
• Require significant
investment to meet
standards and support
long term needs
• Are not well utilised.
• Will only be retained for
strategic / geographic
spread reasons.
Table 7: Core, Flex and Tail Definitions
4.10 Core / Flex / Tail Analysis
The Core / Flex / Tail profile highlights that the estate, in its current configuration, is not
fully aligned with the Council’s future direction. The relatively small Core portfolio
indicates a limited number of assets that are strongly positioned to support long-term
102

Page 103

39 
objectives, while the scale of the Flex and Tail categories shows that much of the estate
will require change to meet future service, financial and environmental demands.
This does not reflect the importance of the services delivered, but rather the suitability of
the buildings in their current form. In many cases, assets can continue to support
essential services, but only through improvement, reconfiguration or relocation into
more appropriate accommodation.
The analysis therefore points to a need for active management of the estate, focused on
strengthening alignment rather than maintaining the status quo. This includes
concentrating activity in better-performing buildings, reducing fragmentation, and
prioritising investment in assets that can support modern, efficient and sustainable
service delivery.
Overall, the profile reinforces that the challenge is structural: the estate must evolve to
become more focused, adaptable and efficient, ensuring that services are delivered
from buildings that are fit for the future rather than sustained in their current form.
4.11 Delivering the Estate Strategy
The assessment process described in Sections 4.1 to 4.9 has provided a robust
evidence base for determining the future role of individual assets across the Council’s
estate. However, the delivery of the Strategy will require more than a single approach to
estate change. 
The review has considered 358 operational properties and recognises that different
assets, services and communities require different solutions. Consequently, the
proposed Strategy should not be viewed as a programme focused solely on asset
closures. Rather, it combines a range of complementary measures designed to improve
the quality, accessibility, utilisation, sustainability and affordability of the Council’s
operational estate.
These measures include targeted investment in retained assets, replacement and
reprovision of services, service consolidation, office rationalisation and the removal of
surplus assets that are no longer required to support service delivery. Together, these
approaches will support the transition towards a smaller, higher-quality and more
sustainable estate, whilst maintaining service provision and improving the overall
customer experience. 
The principal delivery mechanisms are summarised in Table 8 and described in
Sections 4.11.1 to 4.11.5 below; 
103

Page 104

40 
Category of Change  Purpose Typical Example
Investment in
Retained properties
Improvements to buildings that
will form part of the long-term
core estate 
Leisure centres, schools,
social work facilities,
community assets.
Replacement and
reprovision
Services relocating into
improved facilities or
replacement buildings 
Youth facilities, new build
community sports facilties.
Service
Consolidations
Activities being consolidated into
existing buildings with available
capacity 
Community services,
relocating into retained
assets
Lease Expiry and
office
Rationalisation
Withdrawal from leased
accommodation and
consolidation into council-owned
buildings 
David Dale House,
Brandon Gate,
Cambuslang Gate
Regent House
Surplus and under
utilised properties
Removal of Vacant, obsolete or
low-demand properties, many
where services already
withdrawn 
Vacant pavilions, stores
and low demand buildings
Table 8 Principal Delivery Mechanisms
4.11.1 Investment in the Retained Estate
The Strategy is underpinned by a £24 million capital investment programme, focused on
assets that will continue to support service delivery over the long term. The proposed
investment programme includes: 
• £4.19 million to replace and modernise community sports facilities;
• £5 million from the Estate Strategy capital investment programme to support
depot modernisation and consolidation. The total indicative project cost is
currently estimated at approximately £18 million, with the balance subject to
alternative funding sources and future capital approvals.;
• investment in community halls and leisure facilities;
• targeted investment in children's care facilities;
• improvements to retained office accommodation; and 
• a programme of building condition and energy efficiency improvements across
the retained estate. 
104

Page 105

41 
4.11.2 Replacement and Reprovision
In a number of locations, services will continue to be provided but from improved or
alternative accommodation. Examples include the replacement of older sports pavilion
facilities, the relocation of youth services into multi-use community facilities and
proposals associated with the future redevelopment of East Kilbride town centre. 
These changes are intended to improve the quality, sustainability and suitability of
accommodation while maintaining delivery service and improving the overall customer
experience. 
4.11.3 Service Consolidation
The Strategy also proposes a number of service consolidations where activities can be
accommodated within existing retained assets. This approach supports: 
• improved utilisation of Council buildings;
• greater integration between services;
• improved customer access;
• reduced operating costs; and
• more efficient use of available accommodation. 
4.11.4 Lease Expiry and Office Rationalisation 
The review identified opportunities to reduce reliance on leased accommodation and
improve the utilisation of Council-owned office assets. The Strategy therefore proposes
the gradual withdrawal from a number of leased buildings as lease agreements expire,
supported by greater use of hybrid working arrangements and investment in retained
office accommodation. 
This approach will reduce future lease liabilities, improve utilisation and support the
creation of a more efficient and financially sustainable office estate.   
4.11.5 Surplus and Under-Utilised Properties
The review identified a number of assets that are vacant, obsolete, duplicated by nearby
provision or operate at consistently low levels of demand. Where there is no identified
operational requirement to retain such assets, it is proposed that they be removed from
the estate. 
These proposals relate to a number of unused sports pavilions, vacant stores,
operational facilities and buildings for which suitable alternative provision already exists.
The removal of surplus assets allows resources to be focused on buildings that continue
to support service delivery and benefit from investment through the Strategy. 
105

Page 106

42 
5. Strategic Outcomes
5.1. Strategic Outcome classification
Engagement with services through the Estate Strategy Working Group (ESWG),
supported by the estate baseline and assessment criteria as a single source of truth,
has informed a clear and consistent set of strategic outcomes for each asset. This
process combined technical performance data with service insight, ensuring that both
estate condition and operational requirements were reflected in the final position. To
provide a clear roadmap for implementation, the following sections define the strategic
outcomes for the portfolio. 
These classifications move the estate from the technical evaluation phase into a
focused delivery programme, ensuring every building has a designated pathway that
balances operational necessity with financial and environmental sustainability. 
Outcome Definition Requirements
Retain  “Retain” identifies assets required for
ongoing service delivery and
suitable for long term inclusion in the
Council’s estate. These assets
typically perform strongly across the
Assessment Criteria or hold vital
strategic importance due to statutory
functions or specific local needs.
To protect the value and
performance of these assets, the
following actions are prioritised:
• Full integration into the
Council’s planned
preventative maintenance
(PPM) programme to
prevent future backlog
growth.
• Progression of operational
decarbonisation and energy
efficiency works through
structured lifecycle
planning.
• Ongoing consideration for
colocation or internal
reconfiguration where
surplus capacity exists to
absorb services from "Exit"
properties.  
Exit “Exit” refers to properties that are no
longer required for long term service
delivery and present limited
justification for continued
investment. These properties
typically exhibit high carbon
liabilities, significant backlog
To ensure service continuity and
compliance, several milestones
must be met prior to a final exit:
• Confirmation of a
suitable, accessible, and
operationally compliant
alternative service
106

Page 107

43 
maintenance, or low utilisation. The
exit process may involve open
market disposal, lease termination,
or transfer to a third party through
Community Asset Transfer (CAT).
arrangement within the
locality.
• Development of a
comprehensive service
consolidation plan.
• Formal Committee
approval for disposal or
lease relinquishment as
appropriate.  
Replace “Replace” applies where a service
must continue in a specific location,
but the current asset is unsuitable
for continued operation due to
terminal condition, prohibitive costs,
or fundamental design limitations.
Replacement strategies may involve
new-build facilities, modern modular
solutions, or relocation into
alternative modern assets nearby.
Projects in this category must be
"de-risked" before major capital
expenditure:
• Completion of detailed
feasibility work and
identification of the
preferred technical and
financial solution.
• Confirmation of high-level
capital allocation from the
£24m Estate Strategy
budget envelope, if planned
for immediate
implementation.
• Formal approval to progress
to the Design Stage and
Business Case
development.  
Table 9: Strategic Outcome Classifications
5.2. Proposed Estate Profile
The proposed strategy reduces the overall estate from 358 to 317 assets, representing
a net reduction of around 11%. This reflects a clear shift toward a more focused and
manageable portfolio, while maintaining a substantial core of 317 retained assets that
will continue to support service delivery. 
107

Page 108

44 
Resource Property Type Current
Estate
Proposed
Estate
Community & Enterprise Depot 14 7
Community & Enterprise Bothy 1 1
Community & Enterprise Offices 2 1
Community & Enterprise Store  6 4
Community & Enterprise Training Centre 1 1
Community & Enterprise
TOTAL   24 14
Education ASN Primary School 2 2
Education Nursery School 16 16
Education Offices 1 1
Education Primary School 124 124
Education Secondary School 18 18
Education Youth Centre 9 6
Education TOTAL   170 167
Housing Business Unit 4 3
Housing  Depot 1 0
Housing Offices  8 3
Housing & Technical
TOTAL   13 6
Leisure Business Unit 1 1
Leisure Cultural Venue 9 9
Leisure Hall 20 13
Leisure Leisure Centre 18 18
Leisure Library  10 10
Leisure Neighbourhood Centre 7 7
Leisure Outdoor Sports Facility 15 15
Leisure Pavillion 41 28
Leisure Store 2 2
Leisure TOTAL   123 103
Social Work Adult Training Centre 1 1
Social Work Day Care Centre 9 9
Social Work Family Centre 4 4
Social Work Offices 2 1
Social Work
Throughcare &
Aftercare 1 1
Social Work
Childrens Community
House 6 6
Social Work Care Homes 5 5
Social Work TOTAL   28 27    
GRAND TOTAL   358 317
Table 10: Current Estate and Proposed Estate Profiles across South Lanarkshire
108

Page 109

45 
The majority of reductions are concentrated within Leisure, Community & Enterprise,
and Housing and Technical assets, indicating that these parts of the estate are currently
more dispersed and less aligned to future requirements. In contrast, the education
estate remains largely stable, reinforcing its role as the core of the Council’s service
infrastructure and highlighting the need to protect capacity in these locations.
The relatively small number of replacement assets demonstrates that, in most cases,
change can be achieved through reconfiguration, consolidation or improved use of
existing buildings rather than large-scale redevelopment. At the same time, the
identification of exit assets provides a clear opportunity to reduce fragmentation, remove
higher-cost or lower-value properties, and create a more coherent estate structure.
Importantly, this shift is not about reducing services, but about delivering them from a
more efficient and better-aligned set of buildings. Overall, the proposed estate
represents a move away from a broad and distributed asset base toward a leaner, more
strategic portfolio, better positioned to support service delivery, reduce cost and improve
long-term sustainability.
5.3. Key Patterns 
To provide a summary of the strategic trends emerging from the assessment, the
following key patterns have been identified across the primary asset groups. These
trends highlight the shift toward a more integrated, high performing estate that prioritises
modern service delivery over traditional, single use buildings.
5.4. Statutory Resilience in Education
The Education estate remains universally retained to ensure the continuity of statutory
provision across all wards. However, the methodology has identified opportunities for
co-location and the targeted utilisation of surplus classroom capacity. While operational
challenges will need to be worked through to facilitate implementation of this model, this
will allow schools to function as multi-agency hubs, hosting wider community services
without compromising educational outcomes.
5.5. Tiered Approach to Leisure and Sports
This sector shows the greatest strategic variation. High performing "wet sites"
(swimming pools and leisure centres) are prioritised for retention due to their high
community value and complex infrastructure. Certain "dry sites" are earmarked for
consolidation under wider masterplans, while low-value, poor-condition pavilions will be
exited or transitioned to modern, cost-effective modular replacements to maintain local
pitch provision. 
109

Page 110

46 
5.6. Rationalisation of Operational Depots
Due to inconsistent building conditions, overlapping service catchments, and inherent
operational inefficiencies, the depot estate requires significant rationalisation. The
strategy moves toward a smaller number of strategically located hubs, which will
provide better facilities for staff and more efficient logistics for the Council’s fleet and
maintenance services. Implementation will be subject to detailed design development,
funding confirmation and future approval processes. 
5.7. Consolidation of the Office Estate
Low utilisation rates in administrative buildings (driven by the shift to hybrid working)
present a clear opportunity for consolidation. Administrative functions will be centralised
into the Council’s core hubs, including Almada Street (Hamilton), South Vennel
(Lanark), and the new Civic Centre in East Kilbride. This move will reduce the revenue
burden of underutilised space while fostering more collaborative working environments.
6. Estate Investment
6.1 Investment Proposal
The Council has allocated £24 million of capital investment across 2026/27 (£7.3m) and
2027/28 (£11.70m), 2028/29 (£5.0m) to support the initial delivery of the Estate
Strategy. This represents an important first step in transitioning toward a right-sized,
sustainable estate. However, this funding must be considered in the context of a total
programme requirement in excess of £950 million to achieve net zero by 2045. Given
this scale, early investment must be carefully targeted to enable it to deliver maximum
impact. The approach focuses on prioritising the right buildings in the right places, using
early capital investment to unlock wider service, financial and carbon benefits, and to
enable future phases of estate transformation.
To support this, investment decisions are aligned to the Strategy’s five Strategic
Objectives and guided by a structured prioritisation framework. Given the need to move
quickly into delivery, deliverability has been introduced as a sixth factor, focusing early
investment on projects that can be progressed and implemented at pace.
Projects are assessed using a weighted scoring approach, combining alignment to
Strategic Objectives with deliverability considerations. This enables transparent and
consistent decision-making, ensuring that investment is both strategically aligned and
achievable within the two-year funding window. The framework also supports
sequencing of interventions in line with the Horizon decarbonisation approach, allowing
early actions to enable more complex future change. 
110

Page 111

47 
Objective Weight Description
Place-making 20% Considering Priority Places, areas of deprivation, rurality, 
and areas of high deprivation. It helps to focus investment
in priority areas for health equity and supports 20-minute
neighbourhoods. Directly addresses place-based needs
identified via consultation. Targets services in areas of
highest deprivation (SIMD).
A high-scoring project will demonstrably improve outcomes
for a specific place, not just upgrade a building.
Service
Delivery
15% Building becomes "Higher Quality" or enables a more
modern way of delivering services. Promotes/enables
integrated service delivery and improved accessibility for
service users, prevention or early intervention. This  
A high scoring project will demonstrate clear improvements
to service delivery and respond to future service need. 
Utilisation &
co-location
15% Priority to be given to projects that allow consolidation and
changing facilities from single-use to multi-use buildings,
promoting hubs. 
Reduces long-term maintenance costs and facilitates right
sizing. 
A high scoring project will enable co-location or multiple
occupation and reduce the number of single-use assets. 
Cost-
Effectiveness
15% Prioritises projects with a high return on investment,
reduces future running costs via energy savings/reduced
staffing costs, and enabling disposal of Tail assets.
A high scoring project will deliver value over the lifetime of
the Strategy; including revenue savings and capital
receipts. 
Sustainability 15% Significant reduction in carbon emission and aligned with
Horizons 1,2 or 3 measures.
A high scoring project will deliver on the councils Net Zero
obligations through the adoption sustainable construction /
retrofitting.  
111

Page 112

48 
Deliverability 20% Project has a clear procurement route; minimal or no
Building Standards/Planning risk and certainty of delivery
and completion.
A High Scoring Project will be deliverable within required
timescales.
Table 11: Strategic Objectives Scoring Matrix
Early investment will support replacement pavilion accommodation, improved
community facilities, enhanced youth provision, depot modernisation,
office rationalisation, condition improvement works and energy efficiency projects
across the retained estate.
6.2 Project Types
To support delivery of the Estate Strategy, a number of core project types have been
identified. These represent the primary mechanisms through which the Council will
reshape, improve and decarbonise its estate over time.  Each project type plays a
distinct role within the overall programme, contributing in different ways to service
delivery, efficiency, sustainability and place-based outcomes. Together, they provide a
balanced approach to estate transformation, combining structural change with targeted
investment. 
6.3 Consolidation Projects
Consolidation projects are projects which primarily involve moving services from one
asset into another which meets service requirements.These projects are central to the
Strategy, as they enable a reduction in the overall estate footprint, improve utilisation,
and support the creation of modern, multi-service hubs. Consolidation also unlocks
opportunities to dispose of surplus assets, reducing both cost and carbon exposure.
6.4 Office Rationalisation
Office rationalisation project involves exiting several let offices and consolidating staff
into retained freehold sites. This supports improved space efficiency, reduced operating
costs and better alignment with hybrid working models, while maintaining the Council’s
ability to deliver services effectively.
6.5 Depot Rationalisation
Depot Rationalisation involved exiting several ‘end of life’ depots in the Clydesdale area
and consolidating into a new building on a council owned site. This aims to reduce
fragmentation, improve operational efficiency and create opportunities to modernise
working environments, while ensuring that essential frontline services continue to be
supported effectively. 
112

Page 113

49 
6.6 Community Sports Facilities
Community Sports facilities projects involve the replacement or upgrade of park and
sports facilities using modern, prefabricated buildings. These interventions primarily
support placemaking objectives, improving the quality, accessibility and visibility of
community infrastructure. While they have a more localised impact, they play an
important role in enhancing public spaces and supporting health and wellbeing
outcomes.
6.7 Operational Decarbonisation
Operational decarbonisation projects focus on improving the energy performance and
carbon efficiency of retained assets. These projects are essential to achieving net zero
obligations, improving building reliability and reducing long-term energy demand. Boiler
improvement works may be utilised as an intermediate measure where net zero
interventions are unfeasible or will result in unsustainable revenue costs.
Moving forward, operational decarbonisation projects will also consider climate
adaptation measures where appropriate, including overheating mitigation, flood
resilience, improved drainage, building fabric resilience and measures that support
continuity of service during severe weather events. 
6.8 Condition Improvement Works
Condition improvement works focus on retained operational assets that are expected to
continue supporting service delivery over the medium to long term but require targeted
investment to remain fit for purpose. Projects may include building fabric improvements,
compliance works, accessibility enhancements, lifecycle replacements and energy-
efficiency measures. Costs are based on high-level feasibility assessments and
indicative RIBA Stage 0 estimates and will continue to be refined as projects develop.
These investments support building performance, improve utilisation of
retained assets and provide a foundation for future decarbonisation activity. 
Overall, projects that reduce the size and complexity of the estate, such as
consolidation and rationalisation, consistently perform the strongest across multiple
objectives. These interventions deliver combined benefits, improving utilisation,
reducing costs, and supporting decarbonisation, while also creating opportunities to
modernise service delivery. They therefore represent the most effective way of using
limited capital to unlock wider estate transformation.
In contrast, more targeted or asset-specific interventions, such as modular pavilion
improvements or operational decarbonisation works, tend to deliver benefits in specific
areas (e.g. placemaking or carbon reduction) but have a more limited impact on the
overall efficiency and configuration of the estate. While these projects remain important,
they do not in isolation address the underlying structural challenges identified through
the strategy.
113

Page 114

50 
6.9 Front Door Approach
The Estate Strategy supports the development of a phased Front Door model to
improve how residents access Council services across South Lanarkshire. The
approach will utilise a network of accessible community-based locations, supported by
digital channels, to provide clearer access routes to services and
improve customer experience.
Phase One will focus on a number of locations distributed across South Lanarkshire,
with future phases informed by consultation outcomes, customer feedback and wider
service transformation activity. The Front Door approach is intended to make better use
of existing buildings whilst improving accessibility and strengthening the Council’s
place-based approach to service delivery.
The identification of future locations will be informed through engagement with Members,
communities and service users and will be subject to future approval processes.
7. Conclusion
Delivery of the Estate Strategy will now progress into a more detailed phase of planning,
feasibility and prioritisation. While the Strategy sets out the long-term direction and the
proposed future estate, further technical and operational work is required to translate
these proposals into deliverable projects and coordinated programmes of change. Over
the next 12–24 months, the Council will undertake a series of structured next steps to
confirm that decisions are evidence based, financially sustainable and aligned with
service needs and place-based priorities.
This will include developing detailed project plans for assets identified for replacement,
major investment or co location, allowing the Council to test design options, assess
costs and dependencies, and confirm the most effective approach in each location.  The
Council will manage risks and plan responsible decant and transition arrangements for
relevant projects. Engagement with services and communities will continue throughout
this period to continually test whether emerging proposals reflect operational
requirements and local priorities.
The delivery plan will draw on the assessment outputs, feasibility findings and the
availability of funding across the current and future capital planning periods.
Opportunities for community asset transfer, partnership use, and alignment with
regeneration and place plans will be examined in more depth, ensuring that change in
the estate supports wider outcomes.
The Estate Strategy provides a clear and evidence-based framework for managing,
investing in and improving the Council’s estate over the next decade. Through a
combination of targeted investment, service improvement and estate rationalisation, it
will support better quality facilities, improved accessibility, enhanced sustainability and
more efficient use of public resources across South Lanarkshire. The
Strategy establishes a long-term direction of travel while retaining the flexibility to
114

Page 115

51 
respond to future changes in service demand, community priorities and financial
circumstances.
115

Page 116

116

Page 117

Appendix 2 – Summary of Proposed Investment Programme (£24m) 
Relationship with Estate Strategy and Supporting Appendices 
This appendix should be read in conjunction with Appendix 1 (Estate Strategy 2026
to 2036), which sets out the strategic framework and estate-wide proposals;
Appendix 3 (LDP Area Profiles and Investment Proposals), which provides detailed
locality-based proposals. This appendix provides a summary of the proposed £24
million investment programme that will support delivery of the Estate Strategy. 
The investment allocations contained within this appendix are based on high-level
feasibility assessments and indicative RIBA Stage 0 cost estimates. Project
scopes, costs and delivery arrangements will continue to be refined through site
investigation, option appraisal, design development and business case preparation
prior to implementation. 
The programme includes investment in building condition, statutory compliance,
energy efficiency, replacement facilities, service consolidation and depot
rationalisation. Together, these proposals are intended to support delivery of a
smaller, higher-quality, more sustainable and more accessible estate that supports
modern service delivery and improved customer access. 
Detailed information on the individual projects, proposed investments,
estate changes and locality-based outcomes within each of the 14 Local
Development Plan (LDP) areas is provided in Appendix 3 - LDP Area Profiles and
Investment Proposals. 
The proposed investment allocations are summarised below. Support the proposals
identified within the LDP Area Profiles contained in Appendix 3. 
Table A - Summary of Proposed Investment Programme: 
Investment 
Category  Purpose  Proposed
Investment
Condition Improvement
Works 
Building condition, compliance and lifecycle
investment in retained assets.   £10.085m
New Community Sports
Facility
Replacement of poor-quality pavilion facilities with
modern, accessible and energy-efficient
accommodation.  
£4.19m
Depot 
Rationalisation 
Development of a consolidated depot model and
associated infrastructure. The total indicative project
cost is currently estimated at approximately £18
million (RIBA Stage 0), of which £5 million is included
within the Estate Strategy investment programme.
The balance is subject to alternative funding
arrangements and future approvals. 
£5.00m
Depot Design
Development Depot Design Development / Site investigation works  £0.25m
Service Consolidation 
Projects 
Adaptations and improvements to facilitate co-
location and service reprovision.  £1.23m
6
117

Page 118

Boiler 
Replacement 
Programme 
Heating infrastructure replacement and energy
efficiency improvements.   £1.20m
Office Accommodation 
Rationalisation  Hybrid working and office modernisation measures.   £0.55m
Demolition of 
Exited Assets 
Demolition and site preparation are associated with
estate rationalisation.  £0.50m
Children's Care Facility
Improvements 
Targeted improvements to residential care facilities. 
£0.50m
ASN Provision  Improvements supporting Additional Support Needs
accommodation.  £0.50m
Total Proposed 
Investment    £24.00m 
CONDITION IMPROVEMENT WORKS
Condition Improvement Works focus on retained operational assets that are
expected to continue supporting service delivery over the medium to long term but
require targeted investment to remain fit for purpose. Projects may include building
fabric improvements, statutory compliance works, accessibility enhancements,
lifecycle replacements and energy-efficiency measures. Costs are based on
indicative RIBA Stage 0 assessments and will continue to be refined as projects
develop. 
Property Property Type Investment Type  Total 26/27 Spend
Auchentibbber
Adult Training
Centre
Condition Improv
Works £554,917 £232,269
Blantyre Leisure
Centre Leisure Centre
Condition
Improvement Works £1,000,000 £492,090
Burnbank Family
Centre Family Centre
Condition
Improvement Works £378,459 £158,499
Calderglen Country
Park Visitor Centre Cultural Venue
Condition
Improvement Works £68,950 £28,876
Cambuslang
Family Centre Family Centre
Condition
Improvement Works £143,716 £60,188
Chatelherault
Hunting Lodge and
Visitor Centre Cultural Venue
Condition
Improvement Works £150,000 £104,700
Coalburn Leisure
Complex Leisure Centre
Condition
Improvement Works £250,000 £104,700
East Kilbride Arts
Centre Cultural Venue
Condition
Improvement Works £300,000 £125,640
Hamilton Water
Palace  Leisure Centre
Condition
Improvement Works £1,000,000 £492,090
Harry Heaney
Centre Day Care Centre
Condition
Improvement Works £157,500 £65,961
Harry Smith
Complex Day Care Centre
Condition
Improvement Works £150,000 £62,820
Hillhouse &
Earnock
Community Centre Hall
Condition
Improvement Works £465,000 £194,742
118

Page 119

Jimmy Swinburne
Centre
Throughcare &
Aftercare
Condition
Improvement Works £110,600 £46,319
Jock Stein Sports
Barn Leisure Centre
Condition
Improvement Works £471,029 £197,267
Lanark Memorial
Hall Cultural Venue
Condition
Improvement Works £150,000 £62,820
Lesmahagow Day
Centre Day Care Centre
Condition
Improvement Works £171,200 £71,699
Lifestyle Day Care
Centre (Eastfield) Day Care Centre
Condition
Improvement Works £165,900 £69,479
Low Parks Museum Cultural Venue
Condition
Improvement Works £350,000 £146,580
Newberry Rooney
Centre Day Care Centre
Condition
Improvement Works £350,000 £146,580
Parkhall House Family Centre
Condition
Improvement Works £190,950 £79,970
Rutherglen Library Library
Condition
Improvement Works £163,921 £68,650
South Lan
Lifestyles EK-
Murray Owen
Centre
Neighbourhood
Centre
Condition
Improvement Works £450,000 £188,460
South Lan
Lifestyles-Carluke
Neighbourhood
Centre
Condition
Improvement Works £450,000 £188,460
South Lan
Lifestyles-Fairhill -
Daycare Centre Day Care Centre
Condition
Improvement Works £400,600 £167,770
South Lan
Lifestyles-Lanark
Neighbourhood
Centre
Condition
Improvement Works £450,000 £188,460
South Lan
Lifestyles-
Stonehouse
Neighbourhood
Centre
Condition
Improvement Works £450,000 £188,460
Universal
Connections-
Cambuslang Youth Centre
Condition
Improvement Works £139,300 £58,339
Whitehill
Neighbourhood
Centre
Neighbourhood
Centre
Condition
Improvement Works £552,560 £231,412
Carnwath Town
Hall Hall
Condition
Improvement Works    £  20,000 £0
Willie Waddell
Sports Community
Facility & Library Leisure Centre
Condition
Improvement Works    £  40,000 £0
Biggar Municipal
Hall Hall
Condition
Improvement Works    £  25,000 £0
Symington Hall Hall
Condition
Improvement Works    £    5,000
£0
Crawford Primary
School Primary School
Condition
Improvement Works    £  10,000
£0 
BOILER REPLACEMENT WORKS
119

Page 120

The Boiler Replacement Programme provides lifecycle replacement of essential
heating infrastructure where existing systems have reached the end of their
operational life. 
These projects are intended to maintain service continuity, improve reliability and
support energy-efficiency improvements, whilst longer term decarbonisation
opportunities continue to be assessed.
Property Property Type Investment Type  Total
26/27
Spend
Blacklaw Primary
School Primary School
Boiler Replacement
Works £75,000 £25,000
Bothwell Primary
School Primary School
Boiler Replacement
Works £75,000 £25,000
Castlefield
Primary School Primary School
Boiler Replacement
Works £75,000 £25,000
Cathkin Primary
School Primary School
Boiler Replacement
Works £75,000 £25,000
Crosshouse
Primary School Primary School
Boiler Replacement
Works £75,000 £25,000
Glenlee Primary
School Primary School
Boiler Replacement
Works £75,000 £25,000
Greenhills
Primary School Primary School
Boiler Replacement
Works £75,000 £25,000
Hareleeshill
Primary School Primary School
Boiler Replacement
Works £75,000 £25,000
High Blantyre
Primary School Primary School
Boiler Replacement
Works £75,000 £25,000
Law Primary
School Primary School
Boiler Replacement
Works £75,000 £25,000
Mount Cameron
Primary School Primary School
Boiler Replacement
Works £75,000 £25,000
Robert Owen
Memorial Primary
School Primary School
Boiler Replacement
Works £75,000 £25,000
St Columbkille's
Primary School Primary School
Boiler Replacement
Works £75,000 £25,000
St Elizabeth's
Primary School Primary School
Boiler Replacement
Works £75,000 £25,000
St Hilary's
Primary School Primary School
Boiler Replacement
Works £75,000 £25,000
St Vincent's
Primary School Primary School
Boiler Replacement
Works £75,000 £25,000 
CARE FACILITY IMPROVEMENT
Property Property Type Investment Type  Total
26/27
Spend
120

Page 121

Bardykes Children's Resid
Child Care Home
Childrens Com
House
Care Facility
Improvement £83,334 £25,000
Hillhouse Road RCH
Childrens Com
House
Care Facility
Improvement £83,334 £25,000
Hunters Crescent Children's
Home
Childrens Com
House
Care Facility
Improvement £83,333 £25,000
Langlea Avenue RCH
Childrens Com
House
Care Facility
Improvement £83,333 £25,000
Rosslyn Avenue RCH
Childrens Com
House
Care Facility
Improvement £83,333 £25,000
Station Road RCH
Childrens Com
House
Care Facility
Improvement £83,333 £25,000 
DEMOLITION
Property Property Type Investment Type  Total
26/27
Spend
Demolition Various  Various Demolition Various  £500,000 £150,000 
DEPOT RATIONALISATION – Estate Strategy Contribution
Property Property Type Investment Type  Total
26/27
Spend
Depot Rationalisation - Design
Development  Depot
Depot Rationalisation
- Design Development £250,000 £250,000
Depot Rationalisaton  Depot
Depot Rationalisaton
(total funding for
project £18m which
consists of £5m
capital, £10m EPR and
£3m capital receipts) £5,000,000 £0 
Note: The total indicative cost of depot rationalisation is currently estimated at £18m. This
comprises £5m from the Estate Strategy capital programme, £10m from EPR funding and £3m 
from anticipated capital receipts. Funding assumptions remain indicative and subject to future
approval. 
121

Page 122

ASN PROVISION
Property Property Type Investment Type  Total
26/27
Spend
Greenburn ASN & West Mains
ASN Primary School
Education ASN
Provision - Condition
Improvements £333,333 £133,333
Highmill/Victoria Park PS Primary School
Education ASN
Provision - Condition
Improvements £166,667 £66,667
NEW BUILD COMMUNITY SPORTS FACIILITIES 
Property Property Type Investment Type  Total
26/27
Spend
Brancumhall Pavilion Pavilion
New Community
Sports Facility £3,866,400 £1,200,000
Lanark Racecourse Pavilion Pavilion
New Community
Sports Facility £324,000 £57,120 
OFFICE RATIONALISATION
Property Property Type Investment Type  Total
26/27
Spend
South Lanarkshire Council
Headquarters Offices
Office Accommodation
Rationalisation £275,000 £125,000
South Vennel Council Offices Offices
Office Rationalisation
& Desk Booking
System £275,000 £125,000 
122

Page 123

0 
Appendix 3 – LDP Area Profiles and Investment Proposals 
Index 
Contents         Page
LDP Area Profiles and Investment Proposals    1
• Blantyre        5
• Bothwell & Uddingston      9
• Cambuslang       12
• Carluke       16
• Clydesdale East – North     20
• Clydesdale East – Mid     23
• Clydesdale East – South      26
• East Kilbride       29
• Hamilton       34
• Lanark        39
• Larkhall       43
• Lesmahagow       47
• Rutherglen       51
• Strathaven & Stonehouse     55         
6
123

Page 124

1 
Relationship to the Estate Strategy and Supporting Appendices 
This appendix should be read in conjunction with Appendix 1 (Estate Strategy 2026
to 2036), which sets out the strategic framework, estate-wide proposals and
investment priorities; and Appendix 4 (Front Door Approach), which describes the
Council's proposed approach to improving customer access to services. 
This appendix provides locality-based profiles for each of South Lanarkshire's 14
Local Development Plan (LDP) areas and sets out the proposed estate changes,
service impacts and associated investment activity identified through the Estate
Strategy. Detailed information on individual projects, proposed investments and
estate changes is provided within the individual LDP Area Profiles contained in this
appendix. 
The Proposed Investment Projects List sets out a three-year programme of capital
investment, detailing how funding is distributed across key project categories from
2026/27 through to 2028/29.   
The profile of investment is heavily weighted toward condition-led works and
essential infrastructure, with Condition Improvement Works (£10.08m total) and new
build community sports facilities (£4.19m total) comprising a significant proportion of
early spend. This indicates a strong focus on addressing backlog maintenance and
creating additional capacity in the short term, particularly in those areas where asset
condition and service pressures are most acute. This aligns with the earlier
investment scoring, where higher-priority locations are likely driving the need for
immediate intervention to maintain service continuity. 
The proposals within each LDP Area Profile have been structured using the strategic
change categories set out within the Estate Strategy and summarised in Table 1 of
the covering report. These categories are: 
• Investment in Retained Assets 
• Replacement and Re-provision 
• Service Consolidation 
• Lease Expiry and Office Rationalisation 
• Surplus / Under-utilised Property 
The purpose of this approach is to demonstrate how individual property proposals
contribute to the wider objectives of the Estate Strategy through investment, service
improvements, modernisation, consolidation and the more efficient use of the
Council's estate. Accordingly, the LDP Area Profiles should not be interpreted solely
as a list of property closures or disposals, but as a summary of the strategic estate
changes proposed within each locality to support a smaller, higher-quality, more
accessible and sustainable operational estate over the period 2026 to 2036. 
Condition Improvement Works generally comprise building fabric improvements,
statutory compliance works, accessibility enhancements, lifecycle replacement works
and energy-efficiency measures. These projects focus on retaining operational
assets that are expected to continue supporting service delivery over the medium to
long term. 
124

Page 125

2 
Table 1 - £24m Investment 
The inclusion of proposed consolidations (£1.23m) and office rationalisation
(£0.55m) further reinforces this transition toward a more efficient footprint, with
enabling investment supporting co-location and better use of space. These
interventions are comparatively lower in value but play an important role in unlocking
longer-term savings and improving utilisation, particularly in areas where asset
provision is already relatively high.
Smaller but targeted allocations, such as Children’s Care Facility Improvements and
ASN provision, indicate a continued focus on critical services, ensuring that
investment supports both statutory delivery and key service outcomes alongside
broader estate priorities.
Overall, the programme demonstrates a balanced approach: front-loaded investment
to stabilise and support high-need areas, combined with later-phase funding to
deliver structural change and estate rationalisation. Immediate risks are addressed
while creating the conditions for a more efficient and sustainable estate over the
longer term, with investment appropriately reflecting the differing needs and starting
positions of areas across the portfolio.
Across the 14 LDP areas, the results show a distinct variation in how areas are
positioned, with higher scoring typically reflecting greater pressure on services
and/or a need to address the quality or capacity of the existing asset base. These
areas represent the strongest case for intervention, where investment is likely to
support service resilience, respond to demand, and address more immediate risks
within the estate.
By contrast, lower-scoring areas tend to demonstrate a more favourable starting
position. In several cases, such as Clydesdale, this is underpinned by a relatively
higher provision of assets per head of population alongside generally stronger asset
quality. This suggests that these areas are currently better served by the estate, with
less immediate requirement for large-scale capital investment, and instead greater
scope to focus on maintaining performance and optimising existing provision.
Taking together, the pattern across areas highlights an uneven distribution of both
need and opportunity. Higher-scoring locations point to where gaps in provision or
quality are most acute, reinforcing the importance of directing investment to address
these imbalances. At the same time, areas with a stronger asset base offer flexibility
to consider efficiency measures such as rationalisation or co-location, ensuring that
the overall estate is used as effectively as possible.
Proposed Priority Investment Projects List 26/27 27/28 28/29
Condition Improvement Works 10,084,600.00£            4,223,300£             5,861,300.00£         
Boiler Upgrade Works 1,200,000.00£              400,000£                800,000.00£            
New Build Community Sports Facilities 4,190,400.00£              1,257,120£             2,933,280.00£         
Depot Rationalisation Design Development 250,000.00£                 250,000£                -£                          
Proposed Consolidations 1,225,000.00£              413,437£                811,563.00£            
Office Accomodation Rationalisation (Desk Booking System) 550,000.00£                 250,000£                300,000.00£            
Demolition of Exited Assets - various 500,000.00£                 150,000£                350,000.00£            
Depot Rationalisation Development Allocation 5,000,000.00£              -£                           5,000,000.00£    
Childrens Care Facility Improvement Works 500,000.00£                 150,000£                350,000.00£            
ASN Provision 500,000.00£                 200,000£                300,000.00£            
24,000,000.00£            7,293,857£             11,706,143.00£        5,000,000.00£    
125

Page 126

3 
Table 2: Proposed Investment Per LDP AreLDP Area Total
Blantyre  £   1,823,850
Bothwell/Uddingston  £        75,000 
Cambuslang  £      532,249 
Carluke  £      774,999
Clydesdale/East/North  £        60,000
Clydesdale/East/South  £        10,000
Clydesdale/East/Mid  £        30,000
East Kilbride  £   5,901,300 
Hamilton  £   4,625,981
Lanark (includes £5 million for Depot Rationalisation)  £   6,674,000 
Larkhall  £      425,000
Lesmahagow  £      771,200 
Rutherglen  £   1,346,421 
Stonehouse/Strathaven  £      450,000 
Demolition   £      500,000
Grand Total  £ 24,000,000 
Lanark (Additional Depot Rationalisation funded by EPR
(£10 million) and Capital Receipts (£3 million) - £18
million in total included allocation in Lanark above)
£ 13,000,000
Revised Total £37,000,000 
Note: The £24 million investment programme represents the Estate Strategy capital
allocation. The additional £13 million associated with depot rationalisation reflects
indicative funding from alternative sources, including EPR funding and capital receipts. 
The figures noted in table 2 above and all figures throughout the presentation are
indicative and subject to further review, survey and design work RIBA Stage 0-1.
Revenue Impact of Proposed Estate Changes
The proposed changes to the estate result in an estimated £3.0m in revenue savings
from property by 2039. The total savings are accumulated over the next 10 years,
spanning from 2027 until 2032, as depicted in the table below. 
2027/28
£m
2028/29
£m
2029/30
£m
2030/31
£m
2031/32+
£m
Total
£m
Savings 0.1 0.2 0.1 0.4 2.2 3.0
Table 3: Estimated Revenue Savings Per Year
Longer term savings are shown as 2031/32+ in the table, with the majority of the
savings are gained from cessation of leases in the main corporate buildings. In 2039,
the estimated revenue savings gained by exiting the lease of Brandongate is £1.1m
and for Cambuslang Gate is £1m, on the basis that office-based staff for each
location are consolidated into Council owned buildings. Additional savings will be
gained from boiler replacements and photovoltaic (PV) panel installation: every boiler
replacement will save on average £0.004m per annum and every PV panel installed
will save on average £0.007m per annum. 
Benefits realised from the depot rationalisation project, and from the consolidation
into the new East Kilbride Town Hall, will be in addition to the £3.0m worth of
savings. The savings include an amount for the reinstatement of budget for the June
126

Page 127

4 
Stewart Centre, totalling £0.030m. There has been no community capacity or interest
for a CAT.
Half of the savings listed under 2028/29 in the table are related to a saving on
grounds expenditure for Biggar Golf Course, assuming a handover to a CAT
applicant after 2 years. 
127

Page 128

5 
Blantyre 
Estate Profile
The Estate profile highlights a clear imbalance across the estate. Educational assets are highly
utilised and largely fit for purpose, indicating limited spare capacity and a strong reliance on
the existing portfolio to support service delivery. In contrast, leisure, housing, and social work
assets show significantly lower utilisation despite generally acceptable condition and
suitability, pointing to inefficiencies in space provision. Community and enterprise depots
perform well but with limited flexibility.  Overall, the data reinforces the need to protect
high‑demand assets while actively reviewing lower utilisation properties to improve efficiency
to better align the estate with current service need. 
128

Page 129

6 
Demographics
Most notable within local population change is the increase seen in the 60+ age range. This
is common across all areas of South Lanarkshire and is expected to lead to an increase in
service demand for health and social care services. This area has seen a decrease in all
working age groups and a drop in the volume of secondary age children when compared to
other areas. When taken alongside a drop in under 5’s, should the trend continue, it could
reduce the requirements for the education estate. 
Proposed Changes
In Blantyre, the proposed changes to the estate are limited and focused primarily on
rationalising office provision while maintaining frontline services. The overall estate reduces
slightly from 19 to 18 assets, with all education, leisure and social work facilities retained,
ensuring no loss of core community infrastructure. The only planned exit is David Dale House,
which will be vacated at lease expiry and its services relocated into retained accommodation
as part of a wider shift to a hybrid office model. This results in the removal of the sole housing
office in the area, while all other asset categories remain unchanged. Overall, the approach
reflects a policy of retaining key service assets and minimising disruption, with only targeted
consolidation where assets are no longer required. 
-1.6%
0.1%
-1.0%
-1.6%
-0.8%
-1.8%
-0.9%
1.7%
Blantyre
Age 60+
Age 45 - 59
Age 31 - 44
Age 23 - 30
Age 17 - 22
Age 12 - 16
Age 5 - 11
Map References
3 Fleet Services Depot (Vista Point) 239 High Blantyre Hall
4 Waste and Grounds Depot, Blantyre 241 June Stewart Centre
29 Calderside Academy 256 TACT Community Hall
30 Auchinraith Primary School 264 Blantyre Leisure Centre
45 St Josephs Primary School 341 McAnulty Park Pavilion
46 David Livingstone Memorial PS 364 Jimmy Swinburne Centre
47 St Blane's Primary School 365 Auchentibbber
48 High Blantyre Primary School 370 Bardykes Children's Resid Care Home
49 Kear Campus 399 Universal Connections - Blantyre (Terminal One)
193 David Dale House - Housing & Tech    
129

Page 130

7 
Resource Property Type Current
Estate
Proposed
Estate
Community & Enterprise Depot 2 2
C&E TOTAL   2 2
Education Primary School 5 5
Education Secondary School 2 2
Education Youth Centre 1 1
Education TOTAL   8 8
Housing Offices 1 0
Housing TOTAL   1 0
Leisure Hall 2 2
Leisure Leisure Centre 1 1
Leisure Pavilion 1 1
Leisure TOTAL   4 4
Social Work Adult Training Centre 1 1
Social Work Care Home 1 1
Social Work Children’s Com House 1 1
Social Work Throughcare & Aftercare 1 1
Social Work TOTAL   4 4    
GRAND TOTAL   19 18 
Blantyre
Retain
• Blantyre Leisure Centre remains a key wet-side strategic facility which will
receive significant investment through improvement works. 
• All education assets are proposed to be retained with backlog/decarbonisation
works with a number receiving improvement works in the initial funding allocation.
• Jimmy Swinburn centre and Auchentibber will both be retained and will receive
investment in the initial funding allocation. 
Proposed Change
• David Dale House forms part of the Council's lease expiry and office
rationalisation programme. Services will relocate into retained Council
accommodation, making better use of the Council's core office estate and
supporting the long-term shift toward hybrid working.
Property Change
Category 
Proposed Strategy
David Dale House  Offices lease
expiry
Lease Expiry (August 2030) and
Office Rationalisation – Service relocated into
retained Council accommodation 
Table 1: Blantyre: proposed change 
130

Page 131

8 
Investments
Property Property
Type
Investment Type  Total
Auchentibbber Adult Training
Centre
Operational Decarbonisation
Works + Condition
Improvement Works 
£554,917 
Bardykes
Children's Resid
Child Care
Home
Childrens
Com House
Care Facility Improvement  £83,333 
Blantyre Leisure
Centre
Leisure
Centre
Operational Decarbonisation
Works 
£1,000,000 
High Blantyre
Primary School
Primary
School
Boiler Replacement Works  £75,000 
Jimmy
Swinburne
Centre
Throughcare
& Aftercare
Condition Improvement Works  £110,600 
Grand Total    £1,823,850 
Table 2: Blantyre Proposed Properties for Investment  
131

Page 132

9 
Bothwell & Uddingston 
Estate Profile 
The Estate profile is heavily weighted toward education assets, which are operating at or
beyond nominal capacity, particularly primary and secondary schools. High utilisation
combined with good condition and suitability indicates strong reliance on these buildings and
very limited flexibility to absorb future demand or change. 
Overall, the profile reinforces the need to protect highly constrained education assets while
reviewing lower‑utilisation facilities to ensure space provision is aligned with demand and used
efficiently. 
Demographics
In addition to the universal increase in 60+ age bracket across South Lanarkshire, this area
has seen one of the greatest increases within this cohort. Bothwell and Uddingston LDP are
the only areas that have seen an increase in both the working population and the under 5’s,
which, should the trend continue, potentially increase future requirements on the education
and leisure estate. 
Map References
23 Wooddean ELC 27 St Bride's PS, Bothwell
24 St John the Baptist PS 28 Bothwell PS
25 Uddingston Grammar School 29 Uddingston Library
26 Muiredge PS     
132

Page 133

10 
Proposed Changes
In Bothwell and Uddingston, the proposed changes indicate a fully retained estate with no
rationalisation, reflecting the relatively limited provision of assets in the area. The total number
of assets remains unchanged, with all education and leisure facilities maintained and no
planned exits. This includes the full school estate and the continued provision of library
services within existing multi-use facilities. Overall, the approach recognises that the area
already has a comparatively low level of assets per capita and therefore focuses on
maintaining the existing footprint rather than pursuing consolidation or disposal, ensuring
stability of service provision across the locality. 
Resource Property Type Current
Estate
Proposed
Estate
Education Nursery School 1 1  
Primary School 4 4  
Secondary School 1 1
Education TOTAL   6 6    
GRAND TOTAL   6 6 
0.4%
0.5%
-0.5%
-0.8%
1.4%
-1.3%
1.6%
2.6%
Bothwell/Uddingston
Age 60+
Age 45 - 59
Age 31 - 44
Age 23 - 30
Age 17 - 22
Age 12 - 16
Age 5 - 11
133

Page 134

11 
Bothwell & Uddingston
Retain
• All Council Assets in Bothwell and Uddingston will be retained.
• Bothwell Library service provided by SLLC within Bothwell Futures Building. 
Proposed Change
There are no proposed changes in this area.
Investments
Property  Property Type Investment Type  Total
Bothwell Primary School Primary School Boiler
Replacement
Works 
£75,000 
Grand Total    £75,000 
Table 5: Bothwell and Uddingston Proposed Properties for Investment 
134

Page 135

12 
Cambuslang 
Estate Profile
The Estate profile is dominated by education assets, which are generally in good condition
and highly utilised, particularly primary and secondary schools, indicating limited spare
capacity and continued pressure on these buildings to support service delivery. In contrast,
housing and most leisure assets are operating well below capacity despite being largely fit for
purpose, highlighting potential inefficiencies in space use. Social work assets sit mid‑range,
with reasonable utilisation but some variation in suitability. Overall, the data points to a need
to protect and manage high‑demand education assets, while reviewing lower‑utilisation
properties to improve alignment between space provision and demand. 
135

Page 136

13 
Map References 
31 Newton Farm Primary School 43 St Cadoc's Primary School
32 Universal Connections-Cambuslang 44 Cairns Primary School
33 James Aiton Primary School 56 Trinity High School
34 Westburn Nursery School-Caledonian
Centre
194 Cambuslang Gate
35 Park View Primary School 224 Cambuslang Institute
36 Lightburn Early Learning Centre 276 Stonelaw Community Sports Centre
37 Millburn Early Learning & Childcare 297 South Lan Lifestyle-Eastfield
38 Hallside Primary School 348 Peter Brownlee Pavilion
39 St Charles' Primary School 349 Priory Park Pavilion
40 Cathkin High School 367 Langlea Avenue RCH
41 St Brides Primary School-Cambuslang 368 Cambuslang Family Centre
41 West Coats Primary School 372 Lifestyle Day Care Centre (Eastfield) 
Demographics
In consideration of the universal increase in the 60+ age bracket across South Lanarkshire, it
is noted that Cambuslang has the largest rise of all areas. In addition, the area has seen the
largest rise in primary school age children which, as this cohort move through the age
brackets, will increase the requirement on secondary education and potentially leisure
services. 
Proposed Changes
In Cambuslang, the proposed changes involve a modest rationalisation of the estate, reducing
the total number of assets from 25 to 23, primarily through the removal of surplus or
underutilised buildings while retaining core service provision. All education facilities are
retained, along with key leisure and community anchors such as Eastfield Lifestyles and
Stonelaw Sports Centre. The main changes focus on the exit of a leased office (Cambuslang
Gate) at lease expiry and the disposal of an unused pavilion (Peter Brownlee Pavilion),
alongside a small reduction in pavilion provision more generally. Despite these changes, the
overall structure of the estate remains largely intact, with community, leisure and social work
services broadly maintained. The approach reflects an intent to consolidate around strong,
well-used assets while addressing duplication and removing low-value or vacant properties,
resulting in a slightly smaller but more efficient estate footprint. 
136

Page 137

14 
Resource Property Type Current
Estate
Proposed
Estate
Education Nursery School 3 3
Education Primary School 9 9
Education Secondary School 2 2
Education Youth Centre 1 1
Education TOTAL   15 15
Housing Offices 1 0
Housing TOTAL   1 0
Leisure Hall 1 1
Leisure Leisure Centre 1 1
Leisure Neighbourhood Centre 1 1
Leisure Pavilion 2 1
Leisure TOTAL   5 4
Social Work Care Home 1 1
Social Work Children’s Com House 1 1
Social Work Day Care Centre 1 1
Social Work Family Centre 1 1
Social Work TOTAL   4 4    
GRAND TOTAL   25 23 
Cambuslang
Retain
• All education assets are retained with backlog/decarbonisation.
• South Lanarkshire Lifestyles – Eastfield is proposed to be retained as the area’s wet-side
anchor, with improvement works. 
• Lifestyle Day Care Centre (Eastfield) retained; Cambuslang Family Centre is proposed to
be retained with options work on land/lease with NHS Lanarkshire. 
• The Cambuslang Institute is retained but reconfigured to make better use of space,
reflecting the shortage of dedicated community assets in Cambuslang East.
• Stonelaw Community Sports Centre retained with improvements to sustain the sport
network across Cambuslang/Rutherglen. 
Proposed Change
• Lease expiry - Cambuslang Gate forms part of the Council's longer-term office
rationalisation programme and is proposed to be vacated at lease expiry, with
services relocating into retained accommodation. 
• Surplus / Under-utilised Properties - Peter Brownlee Pavilion is currently unused
and is identified as a surplus asset that no longer supports operational or community
requirements. 
137

Page 138

15 
Property Change Category Proposed Strategy
Cambuslang Gate Lease Expiry Lease Expiry (December 2039) and
Office Rationalisation – Service relocated into
retained Council accommodation.
Peter Brownlee
Pavilion
Surplus / Under-
utilised Property 
Strategic Disposal
Table 6: Cambuslang Proposed Change
Investments
Property  Property Type Investment Type  Total
Cambuslang Family
Centre
Family Centre Condition
Improvement Works 
£143,716 
Langlea Avenue RCH Children’s Com
House
Care Facility
Improvement 
£ 83,333 
Lifestyle Day Care
Centre (Eastfield)
Day Care Centre Condition
Improvement Works 
£165,900 
Universal Connections-
Cambuslang
Youth Centre Condition
Improvement Works 
£139,300 
Grand Total    £532,249 
Table 7: Cambuslang Proposed Properties for Investment  
138

Page 139

16 
Carluke 
Estate Profile
The Estate profile shows a generally well‑performing education estate with high utilisation,
particularly within primary and secondary schools, indicating sustained pressure and limited
spare capacity. Community and enterprise assets present a contrasting picture, with the depot
operating significantly above capacity highlighting uneven demand within a small operational
portfolio. Leisure assets show low to moderate utilisation overall, despite being largely suitable
for purpose, suggesting misalignment between space provision and usage, particularly across
pavilions and community facilities. Overall, the profile reinforces the need to protect and
manage high‑pressure education and operational assets, while actively reviewing
lower‑utilisation leisure space to improve efficiency and alignment with demand. 
139

Page 140

17 
Demographics
Most notable in local population data is the increase seen in the 60+ age range. However, this
is common in all areas of South Lanarkshire and is expected to lead to an increase in service
demand for health and social care services. It is noted that this area has seen one of the
largest increases in this cohort. A significant decline in the 17-44 age brackets may impact on
demand for leisure facilities. 
Proposed Changes
In Carluke, the proposed changes involve a more significant rationalisation of the estate, with
the total number of assets reducing from 19 to 15. This is driven primarily by the removal of
operational and low‑use assets, including the closure of the waste depot and cemetery stores
as services are consolidated into the new Caldwellside depot, alongside a substantial
reduction in pavilion provision, with several identified for disposal. Despite this, all education
assets and key leisure facilities are retained, ensuring continuity of services. The overall
approach focuses on eliminating underused or high‑cost assets, particularly across the
pavilion and operational estate, while maintaining the main service anchors, resulting in a
smaller, more efficient and consolidated estate footprint. 
Map References
20 Wilton Cemetery Stores 175 Braidwood Primary School
21 Waste Depot, Carluke 265 Carluke Leisure Centre
166 High Mill Primary School 298 South Lan Lifestyles-Carluke 
167 Carluke Primary School 318 Burn Road Pavilion
168 St Athanasius Primary School 322 Castlehill Bowling Pavilion
169 Carluke High School 324 Crawforddyke Park Pavilion
170 Kirkstyle Early Learning & Childcare 340 Law Football Pavilion
171 Crawforddyke Primary School 346 Moorpark Pavilion Carluke
172 Kirkton Primary School 359 John Cumming Stadium
173 Universal Connections-Carluke 391 Station Road RCH
174 Law Primary School        
140

Page 141

18 
Resource Property Type Current
Estate
Proposed
Estate
Community & Enterprise Depot 1 0
Community & Enterprise Store 1 0
C&E TOTAL   2 0
Education Nursery School 1 1
Education Primary School 7 7
Education Secondary School 1 1
Education Youth Centre 1 1
Education TOTAL   10 10
Leisure Leisure Centre 1 1
Leisure Neighbourhood Centre 1 1
Leisure Outdoor Sports Facility 1 1
Leisure Pavilion 3 1
Leisure TOTAL   6 4
Social Work Children’s Residential Care 1 1
Social Work TOTAL   1 1    
GRAND TOTAL   19 15 
Carluke
Retain
• All Education Assets and Key Leisure assets are retained with targeted investment.
• Library Service provided within Lifestyles Building. 
Proposed Change
• Service Consolidation - Waste Depot services (Carluke) will transfer into the new
consolidated Caldwellside Depot. 
• Surplus / Under-utilised Property – listed in table below. 
Property Change Category Proposed Strategy
Crawforddyke Park
Pavilion
Surplus/Under-utilised
Property
Strategic Disposal, not used in 10 years
plus no pitch in use.
Waste Depot, Carluke Service Consolidation Move service to New Caldwellside Depot
Wilton Cemetery Stores Service Consolidation Strategic Disposal
Moorpark Pavilion
Carluke
Surplus/Under-utilised
Property
Strategic Disposal, vacant building not
used for 10 years no pitch use. 
Table 8: Carluke: Proposed Changes 
141

Page 142

19 
Investments
Property  Property Type Investment Type  Total
Law Primary School Primary School Boiler Replacement
Works 
£75,000 
South Lan Lifestyles-
Carluke
Neighbourhood
Centre
Condition Improvement
Works 
£450,000 
Station Road RCH Childrens Com
House
Care Facility
Improvement 
£83,333 
Highmill/Victoria Park PS Primary School ASN condition
Improvements
£166,666
Grand Total    £774,999 
Table 9: Carluke Proposed Properties for Investment 
142

Page 143

20 
Clydesdale East – North
Estate Profile
The Estate profile shows a strong and well‑performing education estate. Utilisation is mixed
with the ASN school oversubscribed and other schools showing more moderate use. In
contrast, the leisure estate is characterised by lower utilisation and more variable
performance, suggesting some misalignment between provision and need. Overall, while the
estate is broadly of good quality, the profile highlights a clear opportunity to better balance
provision by protecting capacity in education and improving the efficiency and use of leisure
assets. 
Map References
14 Carnwath Roads Depot 226 Carnwath Town Hall
116 Forth Primary School 279 Willie Waddell Sports and Community Centre
117 Braehead Primary School 320 Carnwath Bowling Pavilion - King George's Park 
118 Carnwath Primary School 329 Forth Bowling Pavilion
119 Auchengray Primary School 345 Monteith Football Facility
120 Carstairs Primary School  
121 Carstairs Junction PS  
143

Page 144

21 
Demographics
In addition to the universal increase in 60+ age bracket across South Lanarkshire,  this area
sees one of the largest decreases in the under 5’s age bracket and the 31-44 bracket, which
is similar to Clydesdale East – Mid and South and suggests a reduction in family groups in the
wider Clydesdale area, potentially reducing the future use of the education and leisure
services. 
Proposed Changes
In Clydesdale East – North, the proposed changes involve a significant rationalisation of the
estate, with the total number of assets reducing from 13 to 9. This is primarily driven by the
consolidation of operational facilities and a substantial reduction in pavilion provision, with
several low‑use or ground‑lease pavilions identified for disposal. The local roads depot is also
proposed for closure, with services transferring to the new consolidated Caldwellside facility.
Despite these reductions, all education assets are retained, ensuring continued access to
essential services across rural communities, alongside a small number of key leisure and
community facilities. Overall, the approach focuses on maintaining critical service access in a
rural context while removing underutilised and unsustainable assets, resulting in a leaner and
more efficient estate. 
Resource Property Type Current
Estate
Proposed
Estate
Community & Enterprise Depot 1 0
C&E TOTAL   1 0
Education Primary School 6 6
Education TOTAL   6 6
Leisure Hall 1 1
Leisure Leisure Centre 1 1
Leisure Pavilion 4 1
Leisure TOTAL   7 3    
GRAND TOTAL   13 9  
144

Page 145

22 
Clydesdale East North
Retain
• All education assets, including Auchengray, Carnwath, Carstairs, Carstairs Junction,
Braehead and Forth primaries, are proposed to be retained with targeted improvement
works to support rural access. 
• Well-used pavilions such as Carnwath Football Pavilion and the listed Monteith Bowling
Pavilion are proposed to be retained due to their continued value to local communities. 
• Library Service provided within Willie Waddell Sports Community & Library Centre. 
Proposed Change
• Surplus / Under-utilised Property - Forth Bowling Pavilion and Monteith Football
Facility are identified as surplus assets where current levels of use do not justify
ongoing retention within the operational estate. 
Property Change Category Proposed Strategy
Forth Bowling
Pavilion
Surplus / Under-
utilised property
Strategic Disposal, 1 building on site to
be demolished.
Monteith Football
Facility
Surplus / Under-
utilised property
Strategic Disposal, building to be
demolished. 
Table 10: Clydesdale East North Proposed Change
Investments
Property  Property Type Investment Type  Total
Carnwath Town Hall Hall Condition Improvement
Works 
£20,000 
Willie Waddell Sports
Community Facility &
Library 
Leisure Condition Improvement
Works 
£40,000
Grand Total    £60,000 
Table 11: Clydesdale East North Investment 
145

Page 146

23 
Clydesdale East – Mid 
Estate Profile
The Estate profile shows a generally well‑performing education estate, with all assets in good
condition and suitable for purpose, but with uneven utilisation. The ASN primary school is
operating significantly above capacity, indicating acute pressure, while other primary and
secondary schools retain some flexibility. In contrast, the leisure estate is characterised by low
utilisation despite mostly acceptable condition and suitability, particularly across halls, libraries
and leisure centres. Overall, the profile highlights opportunities to review and better optimise
leisure assets to improve alignment between space provision and demand. 
Map References
130 Biggar High School 218 Biggar Municipal Hall
131 Wiston Primary School 225 Carmichael Hall
133 Tinto Primary School 252 Roberton Hall
134 Libberton Primary School 255 Symington Hall
135 Carmichael Primary School 263 Biggar Sports Centre
136 Coulter Primary School 280 Biggar Library
137 Black Mount Primary School  
141 Biggar Primary School         
146

Page 147

24 
Demographics 
In addition to the universal increase in 60+ age bracket across South Lanarkshire,  this area
sees one of the largest decreases in the under 5’s age bracket and the 31-44 bracket, which
is similar to Clydesdale East – North and South and suggests a reduction in family groups in
the wider Clydesdale area, potentially reducing the future use of the education and leisure
services. 
Proposed Changes
In Clydesdale East – Mid, the proposed changes involve a clear rationalisation of leisure and
community assets, reducing the overall estate from 17 to 15 properties.  This is primarily driven
by the disposal of several underperforming or low‑use facilities, including golf-related assets
at Biggar and a number of small community halls. In contrast, all education assets are
retained, maintaining a stable core service network across the rural area. Key community and
leisure anchors in Biggar are also retained, ensuring continued access to essential services
for the wider catchment. Overall, the approach focuses on removing weaker, underutilised
properties while retaining core provision, resulting in a more concentrated and sustainable
estate that reflects actual usage patterns. 
Resource Property Type Current
Estate
Proposed
Estate
Education ASN Primary School 1 1
Education Primary School 6 6
Education Secondary School 1 1
Education TOTAL   8 8
Leisure Hall 4 2
Leisure Leisure Centre 1 1
Leisure Library 1 1
Leisure Outdoor Sports Facility 3 3
Leisure TOTAL   9 7    
GRAND TOTAL   17 15 
-2.1%
-0.4%
-0.1%
-1.1%
-1.6%
-2.6%
0.8%
2.1%
Clydesdale/East/Mid
Age 60+
Age 45 - 59
Age 31 - 44
Age 23 - 30
Age 17 - 22
Age 12 - 16
Age 5 - 11
147

Page 148

25 
Clydesdale East Mid
Retain
• All education assets in this area are proposed to be retained with targeted works to
maintain quality. 
• Key community assets such Biggar Municipal Hall are proposed to be retained due to
their strong use and strategic importance. 
Proposed Change
• Service Consolidation - Community activity currently delivered from Carmichael
Hall and, in the longer term, Roberton Hall, will be reviewed alongside opportunities
for delivery through alternative community facilities and education assets within the
locality. 
Property Change Category Proposed Strategy
Carmichael
Hall
Service
Consolidation
Strategic Disposal, last used 10 plus years ago.
Roberton
Hall
Service
Consolidation
Exit - move service prior to 2032.
Table 12: Clydesdale East Mid Proposed Change
Investments
Property  Property Type Investment Type  Total
Biggar Municipal Hall Hall Condition Improvement
Works 
£25,000 
Symington Hall Hall Condition Improvement
Works 
£ 5,000
Grand Total    £30,000 
Table 13: Clydesdale East Mid Proposed Investment 
148

Page 149

26 
Clydesdale East – South 
Estate Profile
The Estate profile shows a relatively low‑utilisation estate overall, with moderate use across
all asset types. Education assets are generally fit for purpose and operating at manageable
utilisation levels, suggesting some flexibility within the primary school estate. In contrast,
leisure and community facilities show consistently low utilisation alongside gaps in condition
and suitability data, indicating under‑use and potential inefficiencies. Overall, the profile points
to opportunities to review and rationalise lower‑utilisation leisure and community assets, while
monitoring education provision to ensure space remains aligned with future demand. 
Map References
132 Lamington Primary School 246 Leadhills Hall
138 Abington Primary School 395 Elvanfoot Salt Store
139 Crawford Primary School 395 Abington Hall
140 Leadhills Primary School   
149

Page 150

27 
Demographics
In addition to the universal increase in 60+ age bracket across South Lanarkshire,  this area
sees one of the largest decreases in the under 5’s age bracket and the 31-44 bracket, which
is similar to Clydesdale East – Mid and North and suggests a reduction in family groups in the
wider Clydesdale area, potentially reducing the future use of the education and leisure
services. 
Proposed Changes
In Clydesdale East – South, the proposed changes involve a notable rationalisation of a small
and dispersed estate, reducing the total number of assets from 7 to 5.  This is driven by the
removal of underused community and operational assets, including the closure of a depot
through consolidation into the new Caldwellside facility, and the disposal of low‑use halls and
a pavilion. Despite these reductions, all education assets are retained, ensuring continued
access to essential local services across rural settlements. Overall, the approach reflects a
move to reduce overprovision in community facilities and eliminate low‑value assets, while
maintaining a core network of essential services in a challenging rural context. 
Resource Property Type Current
Estate
Proposed
Estate
Community & Enterprise Depot 1 0
C&E TOTAL   1 0
Education Primary School 4 4
Education TOTAL   4 4
Leisure Hall 2 1
Leisure TOTAL   3 1    
GRAND TOTAL   7 5 
150

Page 151

28 
Clydesdale East South
Retain
• All education properties are proposed to be retained. 
Proposed Change 
• Service Consolidation - Elvanfoot Salt Store operational activities will be
transferred into the consolidated Caldwellside Depot.
• Surplus / Under-utilised Property - Abington Hall is identified as a surplus property
where continued retention cannot be justified based on operational and community
demand. 
Property Change Category Proposed Strategy
Elvanfoot
Salt Store
Service
Consolidation
Move service to New Caldwellside Depot
Abington
Hall
Surplus/under-
utilised property.
Strategic Disposal, last used 2022.
Table 14: Clydesdale East South Proposed Change 
Investments
Property  Property Type Investment Type  Total
Crawford Primary
School
Primary School Condition Improvement
Works 
£10,000 
Grand Total    £10,000 
Table 15: Clydesdale East South Proposed Investment 
151

Page 152

29 
East Kilbride 
Estate Profile
The Estate profile shows a large and predominantly education-led estate, with schools
operating at consistently high utilisation. Despite generally good condition and suitability, this
indicates sustained pressure and limited flexibility within the education portfolio. In contrast,
community and enterprise, leisure and housing assets operate at much lower utilisation levels,
with mixed condition and suitability, suggesting under-use and inefficiencies across a portion
of the estate. Overall, the profile reinforces the need to protect and manage high-pressure
education assets, while actively reviewing a broad range of lower-utilisation community and
leisure facilities to better align space provision with demand and improve overall estate
efficiency. 
152

Page 153

30 
Map References
2 Langlands Depot 92 Auldhouse Primary School
6 Hawbank Roads Depot 93 Kilbryde Early Learning & Childcare
7 Parkhead Farm 94 South Park Primary School
8 Murray Parks Store 95 Greenhills Primary School
9 Phillipshill Cemetery Works Base 195 Civic Centre
65
Universal Connections - East
Kilbride 196 East Kilbride Business Unit
66 Kirktonholme Primary School 209 Calderglen Country Park Visitor Centre
67 St Andrew's and St Bride's High 211 East Kilbride Arts Centre
68
Rooftop Early Learning &
Childcare 212 East Kilbride Village Theatre
69 St Kenneth's Primary School 253
South Lanarkshire Lifestyles EK - Murray Owen
Centre
70 St Hilary's Primary School 262 Alistair McCoist Complex
71 Blacklaw Primary School 267 Dollan Aqua Centre
72 Mount Cameron Primary School 268 East Kilbride Ice Rink
73 Calderglen High School 272 John Wright Sports Centre
74 Greenburn School 286 East Kilbride Central Library
75 Maxwellton Primary School 288 Halfmerke Primary School
76 Long Calderwood Primary School 295 St Leonards Library
77 St Leonard's Primary School 305 James Hamilton Heritage Centre
78 Hunter Primary School 313 Ballerup Pavilion
80 Our Lady Of Lourdes PS 317 Brancumhall Pavilion
81 Murray Primary School 319 Calderglen Conservatory / Zoo Base
82 St Louise's Primary School 338 Langlands Starters Office
83 Heathery Knowe Primary School 354 The Murray Bowls Pavilion
84 Canberra Primary School 355 The Murray Football Pavilions
85 East Milton Primary School 358 Whitemoss Pavilion
86 Jackton Primary School 361 Calderglen Country Park, AAOR Building
87 Mossneuk Primary School 374 Hunters Crescent Children's Home
88 Duncanrig High School 375 Rosslyn Avenue RCH
89 Crosshouse Primary School 376 Parkhall House
90 St Vincent's Primary School 378 Meldrum House
91 Castlefield Primary School 406 Ballerup Hall 
Demographics
In addition to the universal increase in 60+ age bracket across South Lanarkshire, it is noted
that this area has seen one a reduction in secondary age children, which, as the cohort works
its way through the age bands, may result in a reduction in requirements from the leisure
estate. 
153

Page 154

31 
Proposed Changes - In East Kilbride, the proposed changes focus on targeted
rationalisation of offices and some community assets, while maintaining the broader service
estate. The key changes are the planned exit of the Civic Centre and Ballerup Hall, with
services to be relocated into new accommodation as part of the wider East Kilbride
masterplan. These exits from 68 to 66 reflects a shift away from older, less efficient buildings
towards a reconfigured estate aligned to long-term regeneration plans. While specific asset
totals are not set out in the same way as other areas, the overall approach indicates
selective consolidation rather than wholesale reduction, with the core education, leisure and
community infrastructure largely maintained. This results in a more modernised and
strategically aligned estate, supporting future town centre transformation while reducing
reliance on outdated assets. 
Resource Property Type Current Estate Proposed Estate
Community & Enterprise Bothy 1 1
Community & Enterprise Depot 2 2
Community & Enterprise Store 2 2
Community & Enterprise Total   5 5
Education ASN Primary School 1 1
Education Nursery School 2 2
Education Primary School 24 24
Education Secondary School 3 3
Education Youth Centre 1 1
Education TOTAL   31 31
Housing Business Unit 1 1
Housing Offices 1 0
Housing TOTAL   2 1
Leisure Cultural Venue 3 3
Leisure Hall 1 0
Leisure Leisure Centre 5 5
Leisure Library 2 2
Leisure Neighbourhood Centre 1 1
Leisure Outdoor Sports Facility 5 5
Leisure Pavilion 6 6
Leisure Store 1 1
Leisure TOTAL   24 23
Social Work Care Home 2 2
Social Work Children’s Com House 2 2
Social Work Day Care Centre 1 1
Social Work Family Centre 1 1
Social Work TOTAL   6 6    
GRAND TOTAL   68 66
154

Page 155

32 
East Kilbride
Retain
• All Schools, and major leisure facilities are planned to be retained with planned
investment where required. 
Proposed Change
• Brancumhall pavilion is proposed to be replaced through new modular provision to
sustain participation and reduce lifecycle costs.   
Property Change Category  Proposed Strategy
Ballerup Hall Replacement and
Re-provision
The current Civic Centre and Ballerup Hall form
part of a wider programme of replacement and
reprovision associated with the East Kilbride
Masterplan. Services will continue to be
delivered from modern accommodation.
Civic Centre Replacement and
Re-provision
The current Civic Centre and Ballerup Hall form
part of a wider programme of replacement and
reprovision associated with the East Kilbride
Masterplan. Services will continue to be
delivered from modern accommodation.
Table 16: East Kilbride Proposed Change
Investments
Property Property Type Investment Type  Total
Blacklaw
Primary School
Primary School Boiler Replacement
Works 
£75,000 
Brancumhall
Pavilion
Pavilion Modular Pavillion
Replacement 
£3,866,400 
Calderglen
Country Park
Visitor Centre
Cultural Venue Condition Improvement
Works 
£68,950 
Castlefield
Primary School
Primary School Boiler Replacement
Works 
£75,000 
Crosshouse
Primary School
Primary School Boiler Replacement
Works 
£75,000 
East Kilbride
Arts Centre
Cultural Venue Condition Improvement
Works 
£300,000 
Greenhills
Primary School
Primary School Boiler Replacement
Works 
£75,000 
Hunters
Crescent
Children's Home
Childrens Com
House
Care Facility
Improvement
£83,333
Mount Cameron
Primary School
Primary School Boiler Replacement
Works
£75,000
Parkhall House Family Centre Operational
Decarbonisation Works +
Condition Improvement
Works
£190,950
Rosslyn Avenue
RCH
Childrens Com
House
Care Facility
Improvement
£83,333
155

Page 156

33 
South Lan
Lifestyles EK-
Murray Owen
Centre
Neighbourhood
Centre
Operational
Decarbonisation Works
£450,000
St Hilary's
Primary School
Primary School Boiler Replacement
Works
£75,000
St Vincent's
Primary School
Primary School Boiler Replacement
Works
£75,000
Greenburn ASN
& West Mains
ASN
Primary School Education ASN Provision  £333,333
Grand Total   £5,901,300
Table 17: East Kilbride Proposed Properties for Investment 
156

Page 157

34 
Hamilton 
Estate Profile
The estate profile shows primary and secondary schools operating at very high utilisation,
including several assets beyond nominal capacity. In contrast, leisure, social work, housing
and community assets are typically operating at much lower utilisation, with mixed
performance in condition and suitability, pointing to inefficiencies and under‑use across a large
part of the portfolio. Overall, the profile reinforces the need to prioritise capacity and resilience
within education assets, while actively reviewing lower‑utilisation space elsewhere to better
align provision with demand and improve estate efficiency. 
157

Page 158

35 
Map References 
1 Mausoleum 213 Hamilton Town House
17 Industrial Park - Museums Store
(Whistleberry) 214 Low Parks Museum
19 Eddlewood Training Academy 222 Burnbank Hall
142 Holy Cross High School 234 Eddlewood Public Hall
143 Beckford Primary School 240 Hillhouse & Earnock Community
Centre
144 St Cuthbert's Primary School 270 Hamilton Palace Indoor Training
Facility
145 St Paul's Primary School 271 Hamilton Water Palace
146 Glenlee Primary School 278 The Jock Stein Centre
147 St Mary's Primary School - Hamilton 284 Burnbank Library
148 Hamilton Grammar School 289 Hamilton Central Library
149 St John's Primary School - Hamilton 299 South Lanarkshire Lifestyles - Fairhill
150 Our Lady and St Annes Primary School 301 Whitehill Neighbourhood Centre
151 Universal Connections - Hamilton 304 Hamilton Palace Sports Grounds
152 Woodside Primary School 314 Bent Road Pavilion
153 Chatelherault Primary School 327 Fairhill Pavilion
154 St Elizabeth's Primary School 328 Ferniegair Football Pavilion
156 Hollandbush Nursery School 331 Hamilton Palace Bowling Pavilion
157 St Peters Primary School 332 Hamilton Palace Football Pavilion
158 Neilsland Primary School 334 Hunthill Football Pavilion
159 Woodhead Primary School 343 Meikle Earnock Football Pavilion
160 St Mark's Primary School - Hamilton 353 Strathclyde Park Golf Pavilion
161 St John Ogilvie High School 362 Operational Archive Store - 8/7
Whistleberry I.E.
162 First Step Community Nursery 383 Newberry Rooney Centre
163 Udston Primary School 384 Burnbank Family Centre
164 St Ninian's Primary School 385 Autism Resources Coordination Hub
(ARCH)
165 Townhill Primary School 386 Regent House
200 South Lanarkshire Council
Headquarters 387 South Lanarkshire Lifestyles - Fairhill
Daycare Centre
201 Brandon Gate Offices Block A 388 Number 30 Highstonehall Rd
202 Brandon Gate Offices Block B 389 Hillhouse Road RCH
203 Hamilton Business Unit 403 Jock Stein Football Pavilions
206 Outdoor Resource Base 404 Jock Stein Sports Barn
210 Chatelherault Hunting Lodge and
Visitor Centre 407 Beckford Streets Centre 
158

Page 159

36 
Demographics
In addition to the universal increase in 60+ age bracket across South Lanarkshire, School age
population has remained relatively stable with a minor decrease in births and a minor increase
in school leavers (17-22), this is expected to impact education and potentially social care
demand. 
Proposed Changes
In Hamilton, the proposed changes involve a moderate rationalisation of a large and diverse
estate, reducing the total number of assets from 63 to 57.  The approach focuses on removing
underutilised pavilions and consolidating office accommodation, with several pavilion assets
identified for disposal due to lack of use, alongside the planned exit of a number of leased
office buildings as part of the wider office rationalisation programme. At the same time, the
core estate is retained, including the full education network and key leisure, cultural and
community facilities, ensuring continued service provision. Overall, the strategy seeks to
reduce duplication and reliance on inefficient buildings while maintaining the main service
anchors, resulting in a more streamlined and efficient estate aligned to operational needs. 
159

Page 160

37 
Resource Property Type Current
Estate
Proposed
Estate
Community & Enterprise Store 1 1
Community & Enterprise Training Centre 1 1
C&E TOTAL   2 2
Education Nursery School 2 2
Education Primary School 17 17
Education Secondary School 3 3
Education Youth Centre 1 1
Education TOTAL   23 23
Housing Business Unit 2 1
Housing Offices 3 1
Housing TOTAL   5 2
Leisure Business Unit 1 1
Leisure Cultural Venue 4 4
Leisure Hall 3 3
Leisure Leisure Centre 4 4
Leisure Library 2 2
Leisure Neighbourhood Centre 2 2
Leisure Outdoor Sports Facility 2 2
Leisure Pavilion 7 5
Leisure Store 1 1
Leisure TOTAL   26 24
Social Work Children’s Residential Care  1 1
Social Work Day Care Centre 3 3
Social Work Family Centre 1 1
Social Work Offices 2 1
Social Work TOTAL   7 6    
GRAND TOTAL   63 57 
Hamilton
Retain
• Leisure sites, cultural hubs, and schools are proposed to be retained, with targeted
investment to maintain them. 
• A number of Social Work, Community and Education assets will receive improvement
works to improve service provision and carbon performance. 
• Library Service is provided within Fairhills Lifestyles.
Proposed Change
• 2 pavilions will be exited due to underutilisation, and poor quality. These are not currently
used by teams or community groups. Similarly, the former Beckford Street Centre is
proposed for disposal/demolition.
• A number of expensive, let offices will be exited as part of long-term office rationalisation
plans. However, Brandon Gate will continue to support operational requirements in the
short to medium term ahead of future lease expiry and rationalisation decisions ahead of
its lease expiry in 2039. 
160

Page 161

38 
Property Change Category Proposed Strategy
Brandon Gate
Offices Block A
Lease Expiry and
Office Rationalisation
Lease Expiry (2039) and
Office Rationalisation – services
relocated into retained Council
accommodation.
Brandon Gate
Offices Block B
Lease Expiry and
Office Rationalisation
Lease Expiry (2039) and
Office Rationalisation – services
relocated into retained Council
accommodation.
Ferniegair
Football Pavilion
Surplus / Under-
utilised Property
Strategic Disposal, no pitch used building last
used 2021.
Hunthill Football
Pavilion
Surplus / Under-
utilised Property
Strategic Disposal
Regent House Lease Expiry and
Office Rationalisation
Lease Expiry (September 2028) and
Office Rationalisation – services
relocated into retained Council
accommodation.
Beckford Street
Business Centre
Surplus / Under-
utilised Property
Strategic Disposal 
Table 18: Hamilton Proposed Change
Investments
Property Property Type Investment Type  Total
Burnbank Family
Centre
Family Centre Condition
Improvement Works 
£378,459 
Chatelherault
Hunting Lodge and
Visitor Centre
Cultural Venue Condition
Improvement Works 
£150,000 
Glenlee Primary
School
Primary School Boiler Replacement
Works 
£75,000 
Hillhouse & Earnock
Community Centre
Hall Condition
Improvement Works 
£465,000 
Hillhouse Road RCH Childrens Com
House
Care Facility
Improvement 
£83,333 
Jock Stein Sports
Barn
Leisure Centre Condition
Improvement Works 
£471,029
Low Parks Museum Cultural Venue Condition
Improvement Works 
£350,000 
Newberry Rooney
Centre
Day Care Centre Condition
Improvement Works 
£350,000 
South Lan Lifestyles-
Fairhill - Daycare
Centre
Day Care Centre Condition
Improvement Works 
£400,600 
South Lanarkshire
Council
Headquarters
Offices Office
Accommodation
Rationalisation 
£275,000 
St Elizabeth's
Primary School
Primary School Boiler Replacement
Works 
£75,000 
Hamilton Water
Palace 
Leisure Centre Condition
Improvement Works
£1,000,000
Whitehill
Neighbourhood
Centre
Neighbourhood
Centre
Condition
Improvement Works 
£552,560 
Grand Total    £4,625,981 
Table 19: Hamilton Proposed Properties for Investment
161

Page 162

39 
Lanark
Estate Profile
The Estate profile shows a moderately utilised estate with clear variation across asset types.
Education facilities are generally well used and in good condition and suitable for purpose,
indicating steady demand with some flexibility remaining. In contrast, leisure and community
assets operate at consistently lower utilisation and show greater gaps in condition and
suitability, suggesting under‑use and potential inefficiencies. Housing assets sit mid‑range,
with mixed performance across a small portfolio. Overall, the profile points to the need to
monitor education capacity while reviewing underutilised leisure and community facilities to
improve alignment between space provision and demand. 
162

Page 163

40 
Demographics
In addition to the universal increase in the 60+ age demographic across South Lanarkshire,
this area also sees a more moderate increase in the 45-59 age demographic. In addition, the
area shows one of the largest decreases in the under 5’s age bracket, which as the cohort
moves its way through the age brackets and should it be sustained, may reduce the
requirement on the education estate. 
Proposed Changes
In Lanark, the proposed changes represent a significant rationalisation of the estate, reducing
the total number of assets from 22 to 15.  This is primarily driven by the consolidation of depot
operations into the new Caldwellside facility, resulting in the closure of multiple depot sites,
alongside the disposal of underused halls, pavilions and a small park building. In parallel,
some services are proposed to be relocated into existing assets, such as moving provision
from Nemphlar Hall into Kirkfieldbank Primary School, reflecting a broader push toward
co‑location. Despite these reductions, all education assets and key town‑centre and
community anchors are retained, ensuring continuity of services. Overall, the approach
focuses on removing inefficient and underutilised assets while consolidating services into
stronger, better-used facilities, creating a more streamlined and operationally efficient estate. 
-1.9%
0.3%
-0.5%
-0.9%
-1.1%
-1.9%
0.6%
1.6%
Lanark
Age 60+
Age 45 - 59
Age 31 - 44
Age 23 - 30
Age 17 - 22
Age 12 - 16
Map References
13 Caldwellside Depot 247 Nemphlar Hall
112 Robert Owen Memorial Primary School 274 South Lanarkshire Lifestyles - Lanark
113 Lanark Primary School 291 Lanark Library
114 Universal Connections - Lanark 307 Lanark Loch Park
115 St Mary's Primary School - Lanark 308 Lanark Racecourse Pavilion
122 Lanark Grammar School 335 Kildare Football Pavilion
124 New Lanark Primary School 336 Kirkfieldbank (Kilbank) Football Pavilion
125 Kirkfieldbank Primary School 381 Harry Smith Complex
197 South Vennel Council Offices 382 Lanark Family Support Hub
198 New Clydesdale Business Unit 396 Caldwellside Depot (Fleet)
243 Lanark Memorial Hall 397 Lanark Depot (HTR)
163

Page 164

41 
Resource Property Type Current
Estate
Proposed
Estate
Community & Enterprise Depot 2 0
C&E TOTAL   2 0
Education Primary School 5 5
Education Secondary School 1 1
Education Youth Centre 1 1
Education TOTAL   7 7
Housing Business Unit 1 1
Housing Depot 1 0
Housing Offices 1 1
Housing TOTAL   3 2
Leisure Cultural Venue 1 1
Leisure Hall 1 0
Leisure Library 1 1
Leisure Neighbourhood Centre 1 1
Leisure Outdoor Sports Facility 1 0
Leisure Pavilion 3 1
Leisure TOTAL   8 4
Social Work Day Care Centre 1 1
Social Work Family Centre 1 1
Social Work TOTAL   2 2    
GRAND TOTAL   22 15 
Lanark
Retain
• All Education assets are planned to be retained with targeted investment.
• Lanark Memorial Hall retained.
• Lanark Library is retained.
• Lanark Racecourse Pavilion retained with improvement works.
• South Lanarkshire Lifestyles – Lanark retained. 
• Harry Smith Complex retained with upgrades. 
• Lanark Family Support Hub retained although some reconfiguration works are expected.
Proposed Change
• Service Consolidations - The currently occupied Caldwellside Depots and Nemphlar
Hall support consolidation of operational and community services into modern facilities
and better utilised assets. 
• Surplus/Under- utilised property - Kildare Football Pavilion and Kirkfieldbank (Kilbank)
Football Pavilion. 
164

Page 165

42 
Property Change
Category 
Proposed Strategy
Caldwellside
Depot
Service
Consolidation
Move service to New Caldwellside Depot
Caldwellside
Depot
(Fleet)
Service
Consolidations
Move service to New Caldwellside Depot
Kildare
Football
Pavilion
Surplus/Under-
utilised property
Strategic Disposal
Kirkfieldbank
(Kilbank)
Football
Pavilion
Surplus/Under-
utilised property
Strategic Disposal
Lanark
Depot (HTR)
Service
Consolidations
Move service to New Caldwellside Depot
Nemphlar
Hall
Service
Consolidations
Service Consolidation – Community activity
relocated into Kirkfieldbank Primary School,
improving utilisation and long-term sustainability.
Lanark Loch
Park
Outdoor Sports
Facility
Small SLC owned building, building last used 3 years
ago.
Table 20: Lanark Proposed Change 
Investments
Property Property Type Investment Type  Total
Harry Smith
Complex
Day Care Centre Condition Improvement Works  £150,000 
Lanark Memorial
Hall
Cultural Venue Condition Improvement Works  £150,000 
Lanark Racecourse
Pavilion
Pavilion Modular Pavillion Replacement  £324,000 
Nemphlar Hall Hall Consolidation of Service into
Destination Property 
£250,000 
Robert Owen
Memorial Primary
School
Primary School Boiler Replacement Works  £75,000 
South Lan
Lifestyles-Lanark
Neighbourhood
Centre
Condition Improvement Works  £450,000 
South Vennel
Council Offices
Offices Office Rationalisation & Desk
Booking System 
£275,000 
Depot
Rationalisaton 
Estate Strategy capital
allocation
£5,000,000
Grand Total    £ 6,674,000 
Table 21: Lanark Proposed Properties for Investment 
165

Page 166

43 
Larkhall 
Estate Profile
The Estate profile shows high quality primary and secondary schools operating at high
utilisation. In contrast, leisure and community assets operate at much lower utilisation, with
notable gaps in condition and suitability, suggesting under-use and inefficiencies across these
parts of the portfolio. Housing assets are limited in number and also show low utilisation.
Overall, the profile reinforces the need to protect and manage capacity within education
assets, while actively reviewing under-utilised leisure, community and housing properties to
improve alignment between space provision and service demand. 
166

Page 167

44 
Map References
22 Canderside Roads Depot 188 Netherburn Primary School
177 St Mary's Primary School - Larkhall 190 Dalserf Primary School
178 Universal Connections - Larkhall 204 Larkhall Area Office
179 Craigbank Primary School 245 Larkhall Community Centre
180 Skylark ELC 273 Larkhall Leisure Centre
181 Robert Smillie Memorial Primary School 292 Larkhall Library
182 Larkhall Academy 309 Larkhall Golf Course
183 Larkhall Children's Centre 311 Ashgill Pavilion
184 Machanhill Primary School 316 Birkenshaw Pavilion
185 Hareleeshill Primary School 339 Larkhall Starters Office
186 Youth Trust / Learning Offices (Summerlee) 394 Merryton Salt and Storage Facility
187 Glengowan Primary School   
Demographics
It is noted that over 60’s and the primary school age brackets are the only groups that have
seen a growth in the Larkhall area. As the primary school cohort moves into secondary
education it may place a slight increase in requirement on the education and leisure estates,
however, should the under 5 trends continue this will be temporary. 
Proposed Changes
In Larkhall, the proposed changes involve a moderate rationalisation of the estate, reducing
the total number of assets from 24 to 20.  This is driven primarily by the exit of underutilised
community buildings and operational assets, including the disposal of Larkhall Community
Centre and a number of low‑use pavilions, alongside the consolidation of storage facilities into
the wider depot network. In addition, there is service consolidation, with the Universal
Connections youth service proposed to relocate into Larkhall Library, reducing the need for a
standalone facility. Despite these changes, the core estate is maintained, with all schools, the
library and key leisure facilities retained. Overall, the approach focuses on removing surplus
or low‑demand assets while consolidating services into better-used buildings, resulting in a
more efficient and streamlined estate. 
-0.6%
0.4%
-0.4%
-0.6%
-0.8%
-1.3%
-0.2%
1.2%
Larkhall
Age 60+
Age 45 - 59
Age 31 - 44
Age 23 - 30
Age 17 - 22
Age 12 - 16
167

Page 168

45 
Resource Property Type Current
Estate
Proposed
Estate
Community & Enterprise Depot 1 1
Community & Enterprise Store 1 0
C&E TOTAL   2 1
Education Nursery School 2 2
Education Offices 1 1
Education Primary School 8 8
Education Secondary School 1 1
Education Youth Centre 1 0
Education TOTAL   13 12
Housing Offices 1 1
Housing TOTAL   1 1
Leisure Hall 1 0
Leisure Leisure Centre 1 1
Leisure Library 1 1
Leisure Outdoor Sports Facility 2 2
Leisure Pavilion 3 2
Leisure TOTAL   8 6    
GRAND TOTAL   24 20 
Larkhall
Retain
• The full education estate in Larkhall is proposed to be retained with targeted
improvement works. 
• Larkhall Library is proposed to be retained, with its upper floor identified for potential
consolidation of other services, including Universal Connections. 
Proposed Change
• Service Consolidation - Universal Connections relocating to Larkhall Library.
• Surplus / Under-utilised Property - Larkhall Community Centre building has been
closed since 2024.
Property Change Category Proposed Strategy
Birkenshaw Pavilion Surplus / Under-
utilised Property
Strategic Disposal, Building to be demolished
last used 10 years ago, pitch not used.
Larkhall Community
Centre
Surplus / Under-
utilised Property
Strategic Disposal, closed in 2024
Merryton Salt and
Materials Storage
Facility
Service
Consolidation
Move service to New Caldwellside Depot
Universal
Connections-Larkhall
Service
Consolidation
Service Consolidation – Universal
Connections relocating into Larkhall Library to
support improved utilisation, integrated
service delivery and customer access. 
Table 22: Larkhall Proposed Change 
168

Page 169

46 
Investments
Property Property Type Investment Type  Total
Hareleeshill
Primary School
Primary School Boiler Replacement Works  £75,000 
Universal
Connections-
Larkhall
Youth Centre Consolidation of Service into
Destination Property 
£350,000 
Grand Total    £425,000 
Table 23: Larkhall Proposed Properties for Investment  
169

Page 170

47 
Lesmahagow 
Estate Profile
The Estate profile shows a moderately utilised estate with education assets generally
performing well and supporting service delivery within manageable capacity levels. Leisure
and community facilities operate at lower utilisation and display more mixed condition and
suitability, suggesting under‑use and potential inefficiencies across these parts of the portfolio.
Community and enterprise depots also show relatively low utilisation, despite their operational
role. Overall, the profile indicates scope to actively review and rationalise lower‑utilisation
leisure and community assets, while continuing to monitor education provision to ensure
capacity remains aligned with future demand. 
170

Page 171

48 
Map References
12 Lesmahagow Roads Depot 176 Underbank Primary School
105 Woodpark Primary School 21 Auchenheath Hall
106 Milton Primary School 221 Brocketsbrae Hall
107 Lesmahagow High School 251 Rigside Hall
108 Bent Primary School 266 Coalburn Leisure Complex
109 Coalburn Primary School 281 Blackwood & Kirkmuirhill Community Library
110 Universal Connections - Douglas 293 Lesmahagow Library
111 Douglas Primary School 310 Moorpark Stadium (Juniors) Lanark
123 Blackwood Primary School 380 Lesmahagow Day Centre
126 Rigside Nursery School 398 Lesmahagow Grounds Depot
127 Rigside Primary School  
128 Woodhill Early Learning & Childcare  
129 St Johns Primary School   
Demographics
In addition to the universal increase in 60+ age bracket across South Lanarkshire,  it is noted
that Lesmahagow is an area that has seen all working age brackets decrease and, in addition
the area with the greatest decrease in the under 5’s age group, which suggests a decrease in
family groups in the area and should the trend continue may place loess demand on the
education and leisure estate. 
Proposed Changes
In Lesmahagow, the proposed changes involve a moderate rationalisation of the estate,
reducing the total number of assets from 25 to 21.  This is primarily driven by the consolidation
of depot provision into the new Caldwellside facility, alongside the exit of underused or vacant
community assets, including Auchenheath Hall, and the reconfiguration of youth services, with
Universal Connections in Douglas relocating into alternative community accommodation.
There is also a reduction in some leisure and community facilities where utilisation is low.
Despite these changes, all education assets and key leisure facilities are retained, maintaining
core service provision across the area. Overall, the approach focuses on removing surplus
and underperforming assets while consolidating services into more sustainable locations,
resulting in a smaller, more efficient estate while preserving essential access for local
communities. 
171

Page 172

49 
Resource Property Type Current
Estate
Proposed
Estate
Community & Enterprise Depot 2 0
C&E TOTAL   2 0
Education Nursery School 2 2
Education Primary School 9 9
Education Secondary School 1 1
Education Youth Centre 1 0
Education TOTAL   13 12
Leisure Hall 3 2
Leisure Leisure Centre 1 1
Leisure Library 2 2
Leisure Pavilion 3 3
Leisure TOTAL   9 8
Social Work Day Care Centre 1 1
Social Work TOTAL   1 1    
GRAND TOTAL   25 21 
Lesmahagow
Retain
• All education assets are proposed to be retained supported by targeted backlog and
decarbonisation works. 
• Key leisure sites are proposed to be retained because they provide important geographic
coverage for sport and recreation. 
• The Lesmahagow Day Centre is retained, with co-location considerations managed
through service planning. 
Proposed Change
• Service Consolidations - Reprovision of the Universal Connections, Douglas service is
planned into the Fountain Community Hall, this is expected to improve access for most
service users. Lemahagow depot will be reprovided as part of wider plans for a new
larger depot in Lanark to consolidate services and avoid duplication. 
• Surplus / Under-utilised Property - Auchenheath Hall is not used and will be disposed
of. 
172

Page 173

50 
Property Change
Category
Proposed Strategy
Auchenheath Hall Surplus / Under-
utilised Property
Strategic Disposal
Lesmahagow
Roads Depot
Service
Consolidations
Move service to New Caldwellside Depot
Universal
Connections-
Douglas
Service
Consolidations
This proposal forms part of the Strategy's
Service Consolidation programme and will
improve accessibility through delivery from the
Fountain Community Hall / Abbey Green Bank
Table 24: Lesmahagow Proposed Change
Investments
Property  Property
Type
Investment Type  Total
Coalburn Leisure
Complex
Leisure
Centre
Operational Decarbonisation
Works 
£275,002 
Lesmahagow Day
Centre
Day Care
Centre
Condition Improvement
Works 
£171,200 
Universal Connections-
Douglas
Youth
Centre
Consolidation of Service into
Destination Property 
£350,000 
Grand Total    £771,200
Table 25: Lesmahagow Proposed Properties for Investment 
173

Page 174

51 
Rutherglen 
Estate Profile
The Estate profile highlights continued pressure within key education and operational assets.
Primary schools are operating at high utilisation and the secondary school is significantly over
capacity, indicating limited flexibility despite generally good condition and suitability. The
community and enterprise depot is also operating above capacity, pointing to a potential
operational pressure point. In contrast, leisure, office based and social work assets show lower
utilisation. Overall, the profile reinforces the need to protect capacity within high-pressure
education and operational assets, while reviewing lower-utilisation space elsewhere to
improve alignment between provision and demand. 
Map References
5 Quay Road Depot 61 Spittal Primary School
50 Burgh Primary School 62 Springlaw Early Learning & Childcare
51 Universal Connections - Rutherglen 63 St Anthony's Primary School
52 Glenburgh Nursery 64 Loch Primary School
53 Bankhead Primary School 208 Fernhill Community Centre
54 St Columbkille's Primary School 215 Rutherglen Town Hall
55 Stonelaw High School 254 Springhall Community Centre and Library
57 Calderwood Primary School 294 Rutherglen Library
58 Cathkin Primary School 373 Harry Heaney Centre
59 Burnside Primary School 393 169 Main Street
60 St Marks Primary School - Rutherglen    
174

Page 175

52 
Demographics
In addition to the universal increase in 60+ age bracket across South Lanarkshire, it is noted
that Rutherglen sees one of the highest changes in the 45-59 group, which indicates the
service demand for health and social care services will remain in demand as time progresses.
There is a greater drop in secondary school age children in this area, compared to other areas
in South Lanarkshire, which as the group progress through the age brackets may see a
reduction in services delivering to young adults. 
Proposed Changes
In Rutherglen, the proposed changes involve a moderate rationalisation and reconfiguration
of the estate, reducing the total number of assets from 22 to 20.  The changes are driven by
a combination of office rationalisation and service consolidation, including the planned exit of
169 Main Street with services relocated into retained office accommodation. In addition, the
existing Universal Connections asset is to be replaced, with services moving into alternative
provision at the former Cathkin Inn, reflecting a shift toward more suitable and sustainable
facilities. While some community assets are also subject to longer-term exit considerations
linked to lease or funding constraints, the core estate is largely retained, including all schools
and key civic assets such as the town hall and library. Overall, the approach focuses on
targeted exits and relocation of services rather than widespread asset reduction, maintaining
service continuity while improving the efficiency and suitability of the estate. 
-0.4%
-0.4%
-2.0%
-1.0%
0.4%
-1.8%
1.1%
1.1%
Rutherglen
Age 60+
Age 45 - 59
Age 31 - 44
Age 23 - 30
Age 17 - 22
Age 12 - 16
Age 5 - 11
175

Page 176

53 
Resource Property Type Current
Estate
Proposed
Estate
Community & Enterprise Depot 1 1
Community & Enterprise Offices 1 0
Community & Enterprise Total   2 1
Education Nursery School 2 2
Education Primary School 10 10
Education Secondary School 1 1
Education Youth Centre 1 0
Education Total   14 13
Leisure Cultural Venue 1 1
Leisure Hall 1 1
Leisure Leisure Centre 1 1
Leisure Library 1 1
Leisure Total   4 4
Social Work Care Home 1 1
Social Work Day Care Centre 1 1
Social Work TOTAL   2 2    
GRAND TOTAL   22 20 
Rutherglen
Retain
• School network is proposed to be retained with backlog/decarbonisation. Some small
sites note sustainability pressures but are proposed to retain with careful monitoring. 
• Key Town Centre civic assets, including Rutherglen Library, are proposed to be retained. 
Proposed Change
• Replacement and Re-provision - Universal Connections Rutherglen is proposed to
be replaced with alternative accommodation within the former Cathkin Inn, aligning
youth provision with demand and a more sustainable footprint. 
• Lease Expiry and Office Rationalisation - 169 Main Street office is proposed to be
exited with the employability team absorbed into long-term retained offices, improving
utilisation of these core assets. 
Property Change Category Proposed Strategy
169 Main
Street
Lease Expiry and
Office Rationalisation 
Lease Expiry and Office Rationalisation – service
relocated into retained Council accommodation. 
Universal
Connections-
Rutherglen
Replacement and
Re-provision
Universal Connections – Rutherglen forms part of the
Strategy's Replacement and Reprovision programme,
with services relocating into improved accommodation
within the former Cathkin Inn. 
Table 26: Rutherglen Proposed Change 
176

Page 177

54 
Investments
Property Property Type Investment Type  Total
Cathkin Primary
School
Primary School Boiler Replacement Works  £75,000 
Harry Heaney
Centre
Day Care Centre Condition Improvement
Works 
£157,500 
Rutherglen Library Library Operational
Decarbonisation Works 
£163,921 
St Columbkille's
Primary School
Primary School Boiler Replacement Works  £75,000 
Universal
Connections-
Rutherglen
Youth Centre Consolidation of Service
into Destination Property 
£875,000 
Grand Total    £ 1,346,421 
Table 27: Rutherglen Proposed Properties for Investment 
177

Page 178

55 
Strathaven & Stonehouse 
Estate Profile
The Estate profile shows an estate under significant pressure within the education portfolio,
with primary schools operating above capacity and the secondary school at full utilisation. This
indicates very limited flexibility in responding to future demand. Leisure provision shows a
mixed picture, with the leisure centre fully utilised but neighbourhood and pavilion assets
operating well below capacity, suggesting uneven demand across facilities.  Overall, the profile
reinforces the need to safeguard capacity within education assets, while reviewing
lower-utilisation leisure and support facilities to improve alignment between space provision
and service demand. 
178

Page 179

56 
Demographics
In addition to the universal increase in 60+ age bracket across South Lanarkshire, it is noted
that the school age population has seen the largest rise, but the requirements on the education
estate may drop back in time as at present the under 5s population remains stable. 
Proposed Changes
In Strathaven and Stonehouse, the proposed changes involve a very limited rationalisation of
the estate, with the total number of assets reducing slightly from 22 to 21.  The only substantive
change is the exit of a small pavilion asset, reflecting low value or limited use, while all other
parts of the estate are retained. This includes the full education network, key leisure facilities
such as Strathaven Leisure Centre, and core operational assets including the depot. As a
result, the overall estate footprint remains largely unchanged, with the strategy focused on
maintaining a well-balanced and appropriately scaled asset base, with only minimal removal
of surplus provision. 
Map References
10 Crosshill Store 155 Quarter Primary School
11 Strathaven Land & Fleet Depot 189 Stonehouse Primary School
96 Strathaven Academy 191 Newfield Primary School
97 Avondale Early Learning & Childcare 277 Strathaven Leisure Centre
98 Kirklandpark Primary School 300 South Lanarkshire Lifestyles - Stonehouse
99 Wester Overton Primary School 337 Kirklandpark Showfield Pavilion
100 St Patricks Primary School 351
Alexander Hamilton Park - Stonehouse
Running Track Pavilion
101 St Patricks Primary School 352 Strathaven Park Barrie Shelter / Bowls etc.
102 Gilmourton Primary School 392
South Lanarkshire Lifestyles - Stonehouse
Daycare Centre
103 Chapelton Primary School 405 John Hastie Park
104 Glassford Primary School    
179

Page 180

57 
Resource Property Type Current
Estate
Proposed
Estate
Community & Enterprise Depot 1 1
Community & Enterprise Store 1 1
Community & Enterprise Offices 1 1
C&E TOTAL   3 3
Education Nursery School 1 1
Education Primary School 10 10
Education Secondary School 1 1
Education TOTAL   12 12
Leisure Leisure Cenre 1 1
Leisure Neighbourhood Centre 1 1
Leisure Pavilion 4 3
Leisure TOTAL   6 5
Social Work Day Care Centre 1 1
Social Work TOTAL   1 1    
GRAND TOTAL   22 21 
Strathaven & Stonehouse
Retain
• All education assets Strathaven Leisure centre and Strathaven Land & Fleet Depot are
planned to be retained with targeted improvements.
• South Lanarkshire Lifestyles – Stonehouse to be retained, there is identified scope to
increase Social Work/NHS use as SLLC consolidates.  
Proposed Change
• Surplus / Under-utilised Property - Kirklandpark Showfield Pavilion is identified as
surplus to operational requirements, reflecting community use and requirements, and
is proposed for disposal. 
Property Change Category Proposed Strategy
Kirklandpark
Showfield Pavilion
Surplus / Under-
utilised Assets
Strategic Disposal, services will be provided at
John Hastie Pavillion  
Table 28: Strathaven and Stonehouse Proposed Change
Investments
Property Property Type Investment Type  Total
South Lan Lifestyles-
Stonehouse
Neighbourhood
Centre
Condition Improvement
Works   
£450,000 
Grand Total    £450,000 
Table 29: Strathaven and Stonehouse Proposed Properties for Investment 
180

Page 181

Appendix 4 - Proposed introduction of Front Door Model 
1.  Purpose
1.1.  This appendix provides further detail on the proposed front door approach,
which forms a key component of the 10-Year Estate Strategy (2026 to 2036). 
1.2.  The approach sets out how the Council will provide clearer, more consistent
and more accessible routes for residents to engage with services across
localities, making effective use of existing buildings, staff, digital channels
and, where appropriate, partner provision. 
2.  Strategic Context
2.1.  The Estate Strategy establishes a shift toward a smaller, higher-quality and
more sustainable estate. As part of this transition, it is essential that access to
services remains visible, accessible and responsive to local needs. 
2.2.  The front door model is therefore not a standalone initiative, but a practical
extension of the Estate Strategy, providing a clear link between:
• retained buildings;
• service delivery; and
• community access to Council services. 
2.3.  This approach reflects the need for more joined-up, place-based service
delivery, recognising that residents often require access to multiple services
across organisational boundaries. 
2.4. The Front Door approach directly supports the Strategy's objectives relating to
placemaking, high-quality service delivery, utilisation and co-location by
making better use of retained assets and improving how residents access
Council services within their locality. 
3.  Overview of the Front Door Approach
3.1.  The front door approach will establish a network of accessible locations
across South Lanarkshire, supported by digital channels, where residents can
access help, advice and services through a simplified and consistent point of
contact. 
3.2.  The model builds on existing assets and behaviours, using buildings that
residents already visit such as libraries, community facilities and other public-
facing venues to act as clear and supported access points. The approach is
intended to maximise the use of the Council's retained estate rather than
create a requirement for additional facilities. 
3.3. The approach delivers a more coordinated and visible way of providing
access to services. 
6
181

Page 182

4.  Customer and Community Offer
4.1.  The front door will provide a consistent and recognisable offer across all
locations. This will include:
• access to telephone and digital channels to contact Council services;
• access to online services, including assisted digital provision;
• general advice and guidance to help residents navigate services;
• signposting to appropriate services and support; and
• access to in-person services such as Housing and Money Advice at
designated times where possible. 
4.2. This will be developed in a managed and proportionate way, recognising that:
• arrangements will be dependent on service need, capacity and
governance and
• detailed delivery models will be subject to further development and
agreement. 
5.  Delivery Model
5.1.  Delivery of the front door approach will be phased and aligned with the
implementation of the Estate Strategy. 
5.2.  The model will utilise:
• existing customer-facing buildings within each locality;
• existing staff roles, supported by clearer processes and guidance; and
• targeted additional support through generalist or service specific roles
where required;
• continue to develop and refine the Front Door Approach through
engagement with elected members, communities and service users. 
5.3.  The approach will also incorporate:
• planned and pre-arranged service “drop-in” sessions delivered by key
Council services such as Housing, money advice and Employability,
provided at defined locations on pre-arranged and publicly advertised
dates and times;
• integration with digital access routes; and
• opportunities for co-location and coordinated delivery with
partner organisations where this supports improved outcomes. 
5.4.  Detailed operational arrangements, including additional staffing requirements,
partner involvement and service scope, will continue to be developed through
internal collaboration and engagement with relevant partners. 
5.5.  This approach will provide a structured and predictable presence for key
services within local communities, ensuring that residents can access in-
person support where required, while maintaining flexibility in how services
are deployed across locations. 
182

Page 183

6.  Proposed Initial Locations
6.1. The Front Door Approach will initially focus on development of the model
during 2026/27. This will include engagement with elected Members,
communities, service users and relevant partners to inform how the approach
should operate and how it can best support access to Council services across
South Lanarkshire.
6.2. As part of this work, consideration will be given to:
• the range of services that may be accessed through the Front Door
Approach;
• the role of assisted digital support, telephone access and face-to-face
provision;
• the use of existing Council buildings and community facilities;
• accessibility and locality requirements; and
• opportunities for partnership working and co-location.
6.3.   Whilst Existing libraries and other customer-facing facilities may have a role in
supporting delivery of the Front Door Approach, no decisions are being
sought at this stage on individual Front Door locations. Potential locations will
be identified and assessed as part of the development process and will be
informed by engagement with Members, communities and service users.
6.4. Any future proposals relating to implementation, including proposed locations,
service delivery arrangements and resource implications, will be subject to
further consideration and approval through the Council's governance
arrangements. 
7.  Relationship to Estate Strategy 
7.1.  The front door approach will be implemented alongside the wider Estate
Strategy programme, ensuring that:
• access to services is maintained as buildings
are rationalised or consolidated; and
• retained properties provide a clear and active role in supporting
communities. 
7.2.  It represents a visible benefit of the Strategy, linking investment in buildings
directly to improved service access and customer experience. 
7.3.  It also supports the broader ambition of the Strategy to enable co-
location, integration and more effective use of public sector buildings. 
8.  Resourcing, Development and Financial Implications
8.1.  The resourcing for the front door approach will be considered through the
consultation process, considering ability to use existing resources, including
buildings and staff where possible. 
183

Page 184

8.2. It is recognised that:
• additional capacity and/or changes to ways of working are likely to be
required; and
• the future potential for partner involvement will be explored as the
approach evolves and may introduce further requirements in relation to
space, technology and coordination. 
8.3.  The extent of any additional staffing requirement and associated costs will be
established through Phase One implementation and will be informed by
operational demand, usage patterns and service requirements. Any resulting
financial implications will be reported through future updates to Committee. 
9.  Monitoring and Next Steps
9.1.  The delivery model for the programme is being developed. Progress on the
front door approach will be monitored as part of the Estate Strategy
governance arrangements. 
9.2 . This will include:
• performance measures relating to access, demand and customer
experience;
• feedback mechanisms to support continuous improvement; and
• assessment of opportunities for expanded partner collaboration over
time. 
184

Page 185

Report
Agenda Item 
Report to: Executive Committee
Date of Meeting: 19 August 2026
Report by: Executive Director (Community and Enterprise
Resources)  
Subject: Routes to Work South - Appointment of Independent
Directors 
1. Purpose of Report
1.1. The purpose of the report is to:-
[purpose]
 seek approval for the appointment of six Independent Directors to the Routes to
Work South Board of Directors
 seek nominations for the appointment of four elected members to the Routes to
Work South Board of Directors
[1purpose]
2. Recommendation(s)
2.1. The Committee is asked to approve the following recommendation(s):-
[recs]
(1) that the update on the review of Routes to Work South be noted;
(2) that the appointment of the six Independent Directors to the Routes to Work
South Board, as set out in paragraphs 4.2 and 4.3, be approved; and
(3) that nominations be sought for the appointment of four Elected Members to the
Routes to Work South Board of Directors.
[1recs]
3. Background
3.1. Routes to Work South (RTWS) is a South Lanarkshire based company limited by
guarantee and a registered charity that delivers a range of employability programmes
on behalf of South Lanarkshire Council. RTWS was established in 2005 and operates
as an Arms-Length External Organisation (ALEO) of the Council. 
3.2. The outcome of a transformational review of RTWS was approved by Executive
Committee at its meeting on 3 December 2025, being for the Council to maintain the
Council membership of RTWS and the current Teckal arrangements and reduce
overlap between RTWS and the Council. The approved outcome of the review resulted
in a number of actions, including changes to RTWS’s Articles of Association to ensure
an appropriate balance of control and independence between the Council and RTWS.
This included changes to the structure of the RTWS Board of Directors to include four
elected members and six independent directors who are appointed by the Council. 
4. Independent Director Recruitment 
4.1. Prior to the review, the current Chair and more recently one other Director, for personal
reasons, have confirmed that they intend to step down from their positions this year,
leaving 5 Independent Director vacancies.  To fill these roles, a recruitment exercise
was carried out through the Council’s social media channels seeking individuals with
experience in: 
7
185

Page 186

 Finance, audit, or risk management
 Human Resources / People & Culture
 Legal and regulatory compliance
 Strategic leadership and organisational development
 Digital, data, or information governance
 Employability, skills, health, or economic development
 Community development / third sector leadership 
4.2. Six applications were received and interviews were held in June 2026. Following the
interview process, five candidates have been identified to be recommended for
appointment as Independent Directors as outlined below: 
Candidate  Background and experience 
Louisa Clow  Risk and compliance management at a senior level within
the finance sector. 
Jenni Hall  Strategic leadership and governance in international
development sector. 
Louise McKay  Strategic governance, risk and quality assurance
leadership within the public sector. 
Sean Seery  Health and Safety management and community
volunteering. 
Richard Tawse  Finance leadership within the private sector with voluntary
experience across education and national sports body. 
4.3. In addition to the five new Directors, Niki Spence has indicated that she wishes to
continue in her role as an Independent Director. Ms Spence has significant experience
within the employability and skills sector, including in her current role at Clyde
Gateway. 
4.4. It is recommended that the appointment of the five candidates as set out in paragraph
4.2 and that of Niki Spence be approved. As before, these posts are not remunerated. 
4.5. As noted above, in implementation of the approved outcome of the RTWS review,
nominations are also sought for the appointment of four elected members to the
Routes to Work South Board of Directors. Given the geographical reach of RTWS,
representation from both the urban and rural area is desirable. In terms of the political
balance of the Council, and in line with existing practice, it would be for the Council’s
Labour and SNP Groups to decide if they wished to each appoint two elected members
for these vacancies. Thereafter, other nominees could be sought. 
5. Employee Implications
5.1. There are no employee implications in terms of this report. 
6. Financial Implications
6.1. There are no financial implications in terms of this report.  
186

Page 187

7. Climate Change, Sustainability and Environmental Implications
7.1. There are no implications for climate change, sustainability or the environment in terms
of the information contained in this report. 
8. Risk and Other Implications
8.1. There are no other implications in terms of this report. As noted above, the
implementation of the approved outcome in respect of the RTWS review will help
ensure an appropriate balance of control and independence between the Council and
RTWS. 
8.2. An elected member is not obliged to accept an appointment to an external
organisation. However, if they do then they may find themselves taking on additional
legal duties, e.g. as a trustee of a charity or a director of a company, where they will,
in essence be obliged to act in the best interests of that organisation. The exact nature
of these legal duties will depend upon the nature of the organisation in question and
the role they are appointed to. There is also potential for future conflicts of interests
between such a role and their role as an Elected Member. The Standards Commission
has issued an Advice Note  on such matters. 
9. Integrated Impact Assessment and Consultation Requirements
9.1. This report does not introduce a new policy, function or strategy or recommend a
change to an existing policy, function or strategy and, therefore, no impact assessment
is required. As previously reported to the Committee, the review included consultation
with a range of stakeholders including participants, Routes to Work South Board and
management team and employability partners. 
Kevin Carr
Executive Director (Community and Enterprise Resources) 
24 July 2026 
Link(s) to Council Values/Priorities/Outcomes
 We will work to put people first and reduce inequality
 Thriving business, fair jobs and vibrant town centres
 Focused on people and their needs 
Previous References
 Transformational Review of Routes to Work South - Performance and Review Scrutiny
Forum - 24th February 2026
 Transformational Review of Routes to Work South - Executive Committee - 3rd
December 2025 
List of Background Papers
 None 
Contact for Further Information
If you would like to inspect the background papers or want further information, please
contact:- 
Alison Brown, Head of Enterprise and Sustainable Development 
E-mail:  alison.brown@southlanarkshire.gov.uk 
187

Page 188

188

Page 189

Report
Agenda Item 
Report to: Executive Committee
Date of Meeting: 19 August 2026
Report by: Executive Director (Finance and Corporate Resources)
Executive Director (Education Resources)  
Subject: Religious Representation on the Education Resources
Committee 
1. Purpose of Report
1.1. The purpose of the report is to:-
[purpose]
 provide an update on religious representation on the Education Resources
Committee
[1purpose]
2. Recommendation(s)
2.1. The Committee is asked to approve the following recommendation(s):-
[recs]
(1) that Reverend Fiona Anderson be confirmed as the nominated religious
representative from the Church of Scotland on the Education Resources
Committee.
1recs]
3. Background
3.1. A local authority, when establishing an Education Resources Committee, is required
to invite representatives from Church organisations to act as religious
representatives on the Education Resources Committee. 
4 Religious Representatives
4.1. In terms of the Local Government (Scotland) Act 1973, an education authority is
required to appoint:- 
 a representative from the Church of Scotland
 a representative of the Roman Catholic Church
 a third religious representative having regard to:-
 representation from the churches referred to above
 the comparative strength within their area of all the churches and
denominational bodies having duly constituted charges or other regularly
appointed places of worship there 
4.2. At its meeting on 7 August 2024, the Committee confirmed the appointment of
Reverend Jillian Storrie as the religious representative from the Church of Scotland
on the Education Resources Committee. 
4.3. Reverend Storrie has since stepped down from this position and replacement
nominations were sought.  The Church of Scotland has nominated Reverend Fiona
Anderson.
8
189

Page 190

5. Employee Implications
5.1. There are no employee implications as a result of the information contained in this
report. 
6. Financial Implications
6.1. There are no financial implications as a result of the information contained in this
report. 
7. Climate Change, Sustainability and Environmental Implications
7.1. There are no climate change, sustainability or environmental implications associated
with this report. 
8. Risk and Other Implications
8.1. There are no risk or other implications associated with this report. 
9. Integrated Impact Assessment and Consultation Requirements
9.1. This report does not introduce a new policy, function or strategy or recommend a
change to an existing policy, function or strategy and, therefore, no impact
assessment is required. 
Jackie Taylor
Executive Director (Finance and Corporate Resources) 
Lyndsay McRoberts
Executive Director (Education Resources) 
15 July 2026 
Link(s) to Council Values/Priorities/Outcomes
 Accountable, effective, efficient, and transparent 
Previous References
 Executive Committee – 7 August 2024 
List of Background Papers
 None 
Contact for Further Information
If you would like to inspect the background papers or want further information, please
contact:- 
Tracy Slater, Administration Adviser
Tel: 07385 370089
E-mail:  tracy.slater@southlanarkshire.gov.uk 
190

Page 191

Report
Agenda Item 
Report to: Executive Committee
Date of Meeting: 19 August 2026
Report by: Executive Director (Finance and Corporate Resources)  
Subject: South Lanarkshire Council Response to Pre-budget
Scrutiny 2027/2028 Call for Views 
1. Purpose of Report
1.1. The purpose of the report is to:-
[purpose]
 present the Council’s response to two ‘call for views’ requests issued by the
Finance and Public Administration Committee and the Public Service Reform
Committee of the Scottish Parliament, as part of the pre-budget scrutiny
process
[1purpose]
2. Recommendation(s)
2.1. The Executive Committee is asked to approve the following recommendation(s):-
[]
(1) that the South Lanarkshire response to the call for views, attached at
appendices 1 and 2, be approved; and
(2) that the responses be submitted to the Scottish Parliament. 
3. Background
3.1. In recent years, in line with the recommendations of the Budget Process Review
Group report, Scottish Parliament subject committees have undertaken pre-budget
scrutiny, in advance of the publication of the Scottish Budget. 
3.2. The intention is that committees will use pre-budget reports to influence the
formulation of spending proposals while they are still in development. In order to
facilitate this, committees are required to publish pre-budget reports at least six
weeks prior to the Scottish budget. 
3.3. As part of its pre-budget scrutiny, the Finance and Public Administration Committee
of the Scottish Parliament issued a call for views on 29 June 2026 to inform its
enquiry, which this year is on the affordability and sustainability of Scotland’s tax and
spending plans. 
3.4. In addition, the Public Service Reform Committee of the Scottish Parliament issued a
separate call for views on 1 July 2026 to inform its enquiry to consider how the
2027/2028 Scottish Budget can promote public service reform. 
3.5. The submission date for both was 14 August 2026, however, agreement was
reached with the Scottish Parliament that our submissions be returned after this
Committee, to allow for member discussion if required.  
9
191

Page 192

3.6. Section 4 provides detail and a proposed response in relation to the Finance and
Public Administration Committee call for views, while section 5 provides the same for
the Public Service Reform Committee’s request. 
4. The Pre-budget Scrutiny Call for Views – Finance and Public Administration 
4.1. The focus of the Finance and Public Administration Committee’s pre-budget scrutiny
is the following areas: 
 assess the viability of the Scottish Government’s plans to plug the anticipated
£4.77 billion fiscal gap by 2029/2030
 establish what steps the Scottish Government should take to respond to the
structural pressures on the Scottish Budget
 better understand the extent to which the Scottish Government considers
affordability and sustainability when prioritising and deprioritising spending
 consider how the Scottish Government’s approach to taxation fits within its
wider plans to ensure sustainability of the public finances
 bring greater transparency to how new policies announced by the Scottish
Government in recent months will be funded and their potential impact on other
areas of the Scottish Budget
 consider actions the Scottish Government should respond to inflationary
pressures on the Scottish Budget, including in relation to the cost of living
 assess how the Scottish Government should use its financial flexibilities—such
as borrowing, bonds, the mutual finance model and the Scotland Reserve—to
manage budget pressures
 establish what steps the Scottish Government takes to ensure public money
delivers good value and effective outcomes 
4.2. To help inform its enquiry, the Committee has asked for views on the following
questions, and have provided some context in italics to aid understanding: 
1. Are the spending allocations outlined in the 2026 Scottish Spending Review the
most effective approach to strengthen public finances?
2. What are the biggest risks to the spending plans outlined in the 2026 Scottish
Spending Review? 
The Medium-Term Financial Strategy (June 2025) is a five-year financial plan setting
out the Scottish Government’s forecast for revenues and demand, spending priorities
and borrowing plans. 
3. Does the 2025 Medium-Term Financial Strategy (MTFS) recognise and clearly
set out the scale of the fiscal challenges facing the Scottish budget, and are the
actions identified in the Fiscal Sustainability Delivery Plan (FSDP) likely to
address the forecast shortfall?
4. What do the next MTFS and update to the FSDP need to include to show that
the Scottish Government is on track?
5. What actions should the Scottish Government take to grow the tax base and
increase labour market participation, productivity, and Scotland’s economic
growth? 
The 2026 Scottish Spending Review sets out further details on the £1.5 billion in
public sector efficiencies that are to be achieved over three years. On average, these
efficiency savings range from 0.7% to 0.9% per year.  
192

Page 193

6. Are the planned efficiencies realistic and deliverable at a scale sufficient to
make public services sustainable? 
7. What are the main risks to revenues from devolved taxes? 
Preventative spend – investment aimed at avoiding future demand on services - has
long been a priority of the Scottish Government, but the intended outcomes have yet
to be fully achieved. This may reflect the complexity of changing entrenched
budgeting practices that tend to prioritise short-term, reactive spending, as well as
the challenge of coordinating action across multiple services where costs and
benefits fall in different areas. 
The Scottish Government recently published a Preventative Budgeting Tool and
Guidance, with a view to embedding this system of tracking prevention into ongoing
annual budgeting by December 2026. 
8. Preventative spend has been a goal for several years, but the intended
outcomes have not been fully achieved.  Why do you think this is the case and
how might a Preventative Budgeting Tool help track progress with achieving
outcomes? 
9. In which areas should the Scottish Government prioritise its capital spend to
best support economic growth?
10. How effective are the Scottish Government’s existing financial flexibilities -
including borrowing and the Scotland Reserve - in managing fiscal pressures,
and what limitations, if any, should be addressed? 
Alternative financing approaches are increasingly considered as ways to support
public investment and strengthen financial resilience. Bonds allow governments to
raise upfront capital from investors, repaid over time. The Scottish Government has
indicated it intends to launch its first bonds this year and, as set out in the Scottish
Spending Review, expects them to fund the majority of capital borrowing in this
parliamentary term.  Mutual Investment Model (MIM) is a revenue-financed model
that brings in private investment with payments spread over the life of an asset.   
While these approaches can unlock additional funding beyond traditional budgets,
their role remains evolving, reflecting the need to balance affordability, risk, and long-
term value for money. 
11. What role should alternative financing approaches – such as bonds, the mutual
investment model, or other mechanisms – play in supporting public investment
and strengthening Scotland’s financial resilience? 
4.3. Within the Council’s response, attached at Appendix 1, the Executive Committee is
asked to note the following key points: 
 We welcome the acknowledgement in the Spending Review 2026 that Local
Government is an essential partner in the Public Service Reform strategy and
the commitment to work together through the Verity House Agreement to
reform, working together on the basis of mutual trust and respect, and focusing
on outcomes.  We also welcome the acknowledgement that Local Government
continues to deliver reform and efficiencies.  However, we would emphasise
that Local Government has been delivering efficiencies for more than a decade
and cannot be expected to continue to absorb the pressures the sector faces.  
193

Page 194

Moving forward, Local Government will be required to achieve efficiency
savings in order to bridge their own budget gaps, and it cannot be assumed
that these efficiencies would be able to support national budget gaps. 
 The biggest risks to the spending plans are the achievement of efficiency
savings, public sector pay pressures, rising social security costs, a tight fiscal
settlement, capital spending constraints, and demographic pressures. The
Scottish Government assumes £1.5 billion recurring efficiency savings across
the public sector.  Failure to achieve this may impact service delivery /
performance. 
 The Scottish Government’s planned efficiencies are highly ambitious, and this
raises questions about whether they are credible, especially in the shorter
term. The efficiency agenda focuses on shared services, automation, digital
transformation, workforce reduction through natural attrition, procurement
savings, estate rationalisation, NHS productivity improvements, and reducing
duplication across public bodies, while seeking to maintain frontline services
and outcomes. They may contribute to closing medium-term funding gaps, but
there is considerable uncertainty over whether they can be delivered quickly
enough and on a sufficient scale to make public services sustainably affordable
on their own.  The degree of uncertainty and scale of ambition represent a
huge risk, and the question is what happens when the savings are not
achieved, and where will the impact be felt if these savings are not achieved. 
Local Government cannot function if it does not get fair sustainable funding to
help achieve shared outcomes. 
 The plans are linked to public service reform, digital transformation, workforce
reform, prevention and productivity improvements rather than simple budget
reductions.  The Spending Review relies heavily on recurring efficiency savings
and productivity gains that exceed historical performance in some sectors,
particularly health and social care. From the Council’s perspective, we have
been required to make efficiency savings for years and we need to continue to
cover our own savings requirements and budget shortfalls on an annual basis. 
Planned recurring savings across portfolios are on top of this requirement
meaning further financial pressures on Local Government. Initiatives such as
Extended Producer Responsibility on Packaging (pEPR) as a means to drive
waste reduction, increase recycling and move towards net zero are welcomed
and we remain firm in our position that all revenue received for pEPR should
not be offset by a reduction in the Local Government Settlement. 
 Improving population health, supporting inclusive economic growth and
restoring sustainable public finances will require a decisive shift from crisis
response to long-term prevention.  Local Government is central to this
ambition.  Councils and their Leisure Trusts deliver the majority of Scotland’s
leisure services and manage key community assets, including sports facilities,
parks and active travel spaces, providing vital opportunities for people of all
ages and abilities to stay active and connected. However, the challenge
remains that funding would require to be moved from one portfolio to another
which results in disinvestment in particular areas.  
194

Page 195

 The Scottish Government should focus capital investment in areas that deliver
long-term productivity gains, strengthen economic resilience, and leverage
private sector investment.  Priorities include Transport and Connectivity, Digital
Infrastructure, Industrial Development, Research, Innovation and Advanced
Manufacturing, Net Zero / Green Infrastructure and Housing. Overall,
alternative financing should be used as a supplementary tool alongside
traditional funding. Approaches such as bonds, Mutual Investment Model and
pension fund investment can support infrastructure, housing and net-zero
projects, provided they offer value for money and remain affordable over the
long term. 
5. The Pre-budget Scrutiny Call for Views – Public Service Reform
5.1. The Public Service Reform Committee’s pre-budget scrutiny will consider how the
2027/2028 Scottish Budget can promote public service reform, including by: 
 removing barriers to progress
 promoting preventative approaches
 simplifying the delivery of public services 
5.2. To help inform its enquiry, the Committee has asked for views on the following
questions:   
1. The Scottish Government aims to deliver on average £0.5 billion in savings
through efficiencies per year for the next three years (2026/2027 to 2028/2029): 
a) To what extent are these savings achievable, and how will they shape
public service delivery?
b) What progress is being made towards achieving these efficiencies?
c) What are the barriers to achieving greater efficiency and how can these be
addressed? 
2. How should the Scottish Government best present the extent of any realised
efficiencies in the annual budget publication, including providing clarity on
whether these are expected to be recurring savings? 
3. The Fiscal Sustainability Delivery Plan aims to achieve an average reduction of
the public sector workforce of 0.5% per year over five years. 
a) To what extent is this target achievable and how will it shape public
service delivery? 
b) What progress is being made towards achieving this target? 
4. What actions can the Scottish Government take to ensure these workforce
reductions are delivered in a managed way which best supports effective
government and public service delivery 
5. The Public Sector Reform (PSR) strategy states that it will protect frontline
services. To what extent is there sufficient clarity about how frontline roles are
defined and how efficiencies in back-office functions can be delivered in a way
that minimises impact on the delivery of public services? 
6. Beyond the financial benefits that the PSR Strategy aims to achieve, what are
the key outcomes that reform should be aiming for?  
195

Page 196

7. The PSR Strategy includes 18 different workstreams which aim to remove
barriers to reform. One workstream focuses on “simplification”, recognising that
“complexity of processes, structures and reporting requirements is a key barrier
to effective and efficient service delivery”. “Prevention” is one of three pillars
providing structure to the Strategy. 
a) What should the Scottish Government’s priorities be under its
simplification workstream and what level of savings can be achieved
through this approach?
b) What progress has been made to date with preventative budgeting?
c) How should the forthcoming Budget support greater progress towards
preventative budgeting across the devolved public sector? Please set out
any barriers and how these can be addressed.
d) What changes to the Scottish Government's approach to budget-setting
are needed to effectively deliver public service reform? 
8. The Scottish Government included an upfront Invest to Save Fund of around
£30 million in the 2025/2026 and 2026/2027 Scottish Budgets for reform
projects that will deliver ongoing savings and support the delivery of the PSR
strategy. 
a) To what extent is the Invest to Save Fund delivering projects that achieve
ongoing savings? 
b) How are successful outcomes from this Fund being shared more widely
across the public sector? 
5.3. Within the Council’s response, attached at Appendix 2, the Executive Committee is
asked to note the following key points: 
 The Scottish Government’s public sector savings of £0.5 billion per annum is
very ambitious, especially in the short term. As per the Scottish Governments
Fiscal Sustainability Delivery Plan, savings from workforce changes, digital
transformation, shared services, procurement reform, estate rationalisation,
and service redesign have been highlighted as being required.  This level of
savings is achievable only if reform, digital transformation, procurement reform
and service redesign are delivered at pace.  The Scottish Government’s
planned efficiencies are highly ambitious, and this raises questions about
whether they are credible, especially in the shorter term.  Many previous
efficiencies have already been captured, meaning future savings increasingly
require structural service reform rather than straightforward cost reductions. 
Inflation, pay settlements and rising service demand may offset headline
savings.  Key barriers to achieving greater efficiency include organisational
fragmentation where there is a lack of joined up working across services,
legacy systems, workforce capacity, risk aversion and short-term budgeting. 
Stronger collaboration across public sector bodies and improved data sharing
and investment in change capability are needed to overcome political and
public resistance.  
196

Page 197

 Progress towards achieving savings targets remains aspirational at this stage
with policy direction only being made clear through reforms designed to
support workforce reductions, including expansion of digital service delivery,
automation of administrative processes, planned greater use of shared
corporate services and investments. As a result, no financial benefit has been
achieved to date and the level that can be achieved in the short term is
questionable.   
 To ensure workforce reductions are delivered in a managed way, the Scottish
Government should prioritise workforce planning, retraining, redeployment,
digital investment, succession planning and the protection of critical operational
roles. 
 The key outcomes that reform should be aiming for are improved outcomes,
earlier prevention, increased productivity, better user experience, reduced
inequalities, stronger collaboration, faster decision making and more
sustainable public services.  These principles align to the aims of the Marmot
programme of work being undertaken by the Council and its partners in Health
and in communities. 
 There is scope for the Scottish Government to strengthen how successful
outcomes from the Invest to Save Fund are shared.  Potential improvements
include creating a publicly accessible repository of case studies and business
cases, reporting expected and realised savings on a recurring basis, identifying
projects suitable for replication by other public bodies and tracking adoption
rates across sectors. 
6. Next steps
6.1. The Executive Committee is asked to approve the submission at appendices 1 and 2
to the Scottish Parliament. 
7. Employee Implications
7.1. None. 
8. Financial Implications
8.1. There are potentially significant financial implications for the Council arising from
decisions taken in relation to the Scottish Budget 2027/2028. The responses
prepared by the Council underlines the scale and significance of the financial
challenges facing local government. 
9. Climate Change, Sustainability and Environmental Implications
9.1. There are no direct climate change, sustainability and natural environment
implications arising from this report. 
10. Risk and Other Implications
10.1. Considering the detail of the report and identifying actions as appropriate contribute
towards effective risk management. There are very significant risks to local
government arising from the decisions taken in the Scottish Budget 2027/2028.  
197

Page 198

11. Integrated Impact Assessment and Consultation Requirements
11.1. This report does not introduce a new policy, function or strategy or recommend a
change to an existing policy, function or strategy and, therefore, no impact
assessment is required. 
11.2. Consultation was undertaken internally on the contents of this report. 
Jackie Taylor
Executive Director (Finance and Corporate Resources) 
27 July 2026 
Link(s) to Council Values/Priorities/Outcomes
 Accountable, effective, efficient and transparent 
Previous References
 None 
List of Background Papers
 None 
Contact for Further Information
If you would like to inspect the background papers or want further information, please
contact:- 
Lorraine O’Hagan, Head of Finance (Strategy)
Ext:  5637  (Tel:  01698 455637)
E-mail:  Lorraine.O'Hagan@southlanarkshire.gov.uk
198

Page 199

Appendix 1 
Finance and Public Administration Committee 
Pre-Budget Scrutiny 2027-28 Call for Views 
1. Are the spending
allocations outlined in the
2026 Scottish Spending
Review the most effective
approach to strengthen
public finances? 
We would reiterate our view (made in previous year pre-
budget submissions) that Local Government is a key partner
in progressing the 4 Spending Review priorities of eradicating
child poverty, growing the economy, tackling the climate
emergency, and ensuring high quality, sustainable public
services. 
We welcome the acknowledgement in the Spending Review
2026 that Local Government is an essential partner in the
Public Service Reform strategy and the commitment to work
together through the Verity House Agreement to reform,
working together on the basis of mutual trust and respect, and
focusing on outcomes. 
However, it is essential that there is meaningful long term,
sustainable investment in Local Government to achieve better
outcomes across our shared priorities. Without meaningful
investment, achieving these four priorities will be impossible. 
Local Government in Scotland is under increasing, and
unsustainable, pressure.  Figures from Audit Scotland show
that councils collectively are facing a £0.5 billion funding gap
in 2026/2027. 
In addition to the budget gap councils face, the £497.5m gap
in 2025/2026 in Health and Social Care Partnerships will
continue to rise as demand and complexity increases. 
We welcome the acknowledgement that Local Government
continues to deliver reform and efficiencies.  However, we
would emphasise that Local Government has been delivering
efficiencies for more than a decade and cannot be expected
to continue to absorb the pressures the sector faces. 
As articulated in the COSLA position stated in ‘What does the
2026-27 Budget mean for Councils?’ spending allocations do
not: 
- Provide the funding needed to address the demand-led
pressures in social care and start to build capacity within
our communities to achieve our shared national priorities. 
- Provide assurance for the future of our services. Flat cash
projections over the spending review place our core, most
in demand services at risk. 
- Resolve the workforce capacity and recruitment
challenges, nor provide comfort or security to our current
council staff.
199

Page 200

- Enable a shift towards a more sustainable future through
investment in preventative services. The benefit of Local
Government to the whole system cannot be fully realised
until it is sufficiently resourced. 
- End the continuing cuts to our non-statutory services,
particularly in culture and leisure, which represent a high
impact investment in our health and wellbeing. 
- Reverse the difficult decisions needing to be made as a
result of housing emergencies across Scotland, and end
the increasing bills for temporary accommodation. 
- Address the pressures in capital budgets (and increasingly
in revenue budgets through borrowing) used to maintain,
invest and decarbonise our vital infrastructure, assets and
estate as we struggle to meet Net Zero targets. 
The Medium-Term Financial Strategy notes that Scotland’s
population is ageing, demand for health and social care
services is rising and health inequalities are widening, with a
projected 3.3% real-terms growth (5.4% nominal) from 2030
onwards. 
This underscores the need to drive a focus on greater
investment upstream to reduce demand on health and social
care services, not just funding the NHS and continue to be
reactive with prevention being key. 
2. What are the biggest
risks to the spending
plans outlined in the 2026
Scottish Spending
Review? 
The biggest risks to the spending plans are the achievement
of efficiency savings, public sector pay pressures, rising
social security costs, a tight fiscal settlement, capital spending
constraints, and demographic pressures. 
- The Scottish Government assumes £1.5 billion recurring
efficiency savings across the public sector.  Failure to
achieve this may impact service delivery / performance. 
- Increasing health and social care demands driven by
demographics remains the dominant pressure on Scottish
budget.  The risk is that other areas will see budget
reductions in order alleviate this pressure. 
- Tighter funding settlements for non-health services e.g.
local authorities. The Institute for Fiscal Studies estimate
outwith health & social care, some budgets could see real
term reductions of 1.7% on average in the later years of
the review period. 
- As acknowledged by the Scottish Government, Capital
spending is projected to fall slightly in real terms by
2029/2030, mainly due to decisions affecting the UK
Government funding, which create risk in terms of
infrastructure investment.
200

Page 201

- Supporting sustainable economic growth is a central
objective of the Spending Review.  Therefore, if growth is
less than expected, tax revenues may be depressed,
demand on social security may increase etc all of which
has an impact on the funding and allocation of resources
within the public sector. 
- Scottish Government plans to make greater use of
borrowing including issuing bonds for capital investment. 
Therefore, the inherent market risks will come into play:
higher than expected borrowing costs / interest, weak
investor demand, future repayment pressures. 
3. Does the 2025
Medium-Term Financial
Strategy (MTFS)
recognise and clearly set
out the scale of the fiscal
challenges facing the
Scottish budget, and are
the actions identified in
the Fiscal Sustainability
Delivery Plan (FSDP)
likely to address the
forecast shortfall?
The 2025 MTFS recognises and clearly sets out the scale of
the fiscal challenges facing the Scottish Budget.  It identifies a
fiscal gap approaching £5 billion by 2029/2030 and explains
the pressures arising from health, social care, social
security, demographics and constrained funding
growth. However, it does not reflect the fact that the Council
has its own fiscal challenge on top of this. 
The strategy provides greater transparency
than previous versions, explains the assumptions behind
spending projections and links fiscal challenges to a
structured programme of reform through the Fiscal
Sustainability Delivery Plan (FSDP). 
The FSDP focuses on three pillars: 
• spending reform and prioritisation, 
• sustainable economic growth and 
• a strategic approach to taxation. 
Actions include efficiency savings, workforce reform,
productivity improvements and measures intended to broaden
the tax base. 
Many planned savings rely on ambitious assumptions about
public-service reform, workforce reductions and productivity
gains. Demand-led spending, particularly health and social
security, may continue to grow faster than expected. 
The FSDP provides a credible framework and could reduce a
substantial part of the projected shortfall.  However,
there remains significant delivery risk and additional
measures may be required if planned reforms do not achieve
the anticipated savings. 
The MTFS assumes that Local Government will experience
the same funding pressures as the rest of the public sector
(para 3.2.5), however this fails to take account of the
changing legislative and policy landscape which has seen
demands on councils increase with, in many cases, no
additional funding.  The Council have been required to make
efficiency savings for years and we need to continue to cover
201

Page 202

our own savings requirements and budget shortfalls before
further implications from the MTFS.   
Moving forward, Local Government will be required to
achieve efficiency savings in order to bridge their own
budget gaps, and it cannot be assumed that these
efficiencies would be able to support national budget gaps. 
In light of the considerable changes which may need to be
implemented, e.g., in the health and social care field, it would
be appropriate for some recognition of the potential for
additional costs to fall to Local Government. 
Councils are having to rationalise demands when money is
tight.  Fully funded joined-up policies which prioritise
prevention are required, and not just simply continuing to
shore up systems which need to change. 
4. What do the next
MTFS and update to the
FSDP need to include to
show that the Scottish
Government is on track? 
The next iteration of the MTFS and FSDP could demonstrate
the following: 
• Clear Progress Against Savings Targets
Provide year-by-year reporting against planned
efficiency, reform and workforce savings, including what
has been delivered, what remains outstanding and any
slippage.
• Updated Fiscal Gap Projections
Show whether the projected resource and capital funding
gaps have narrowed since the 2025 MTFS, with
transparent explanations of changes.
• Evidence of Public Service Reform
Include measurable outcomes from
reform programmes such as productivity improvements,
digital transformation and service redesign.
• Workforce Reform Delivery 
Report on progress against workforce reduction targets,
vacancy management measures and impacts on service
delivery.
• Demand Management
Provide evidence that growth in health, social care and
social security spending is being managed sustainably.
• Economic Growth Outcomes
Demonstrate whether economic and tax-base growth
assumptions are being achieved through investment and
policy interventions.
• Capital Investment Prioritisation
Show how capital budgets are being prioritised and
whether infrastructure and net-zero
commitments remain affordable.
• Risk and Contingency Planning
Set out alternative scenarios, delivery risks and
contingency actions if savings or revenues fall below
expectations. 
202

Page 203

Overall, the strongest evidence that the Scottish Government
is on track would be a demonstrable reduction in the forecast
fiscal gap, verified delivery of recurring savings, and clear
evidence that public service reform is generating sustainable
productivity improvements without reducing outcomes. 
At the moment, the Scottish Government’s planned
efficiencies appear are highly ambitious, and this raises
questions about whether they are credible, especially in the
shorter term. 
5. What actions should
the Scottish Government
take to grow the tax base
and increase labour
market participation,
productivity, and
Scotland’s economic
growth?
The Scottish Government could undertake the following
actions:
• Investment in skills and workforce development,
particularly in sectors facing labour shortages and those
with significant growth potential, including advanced
manufacturing, digital technologies, construction, health
and social care, and the net zero economy.
• Measures to increase labour market participation,
including affordable childcare, support for people with
disabilities and long-term health conditions, employability
programmes, and initiatives to retain older workers in the
labour market.
• Accelerated investment in infrastructure, including
transport, digital connectivity, energy networks and
housing, to unlock economic growth and attract private
sector investment.
• Support for business growth and innovation, including
increased support for research and development,
entrepreneurship, and the scaling-up of Scottish
businesses.
• Expansion of employment land addressing market
failures in the supply of industrial space. Recent research
commissioned by South Lanarkshire Council and wider
Glasgow City Region partners highlights significant
shortages of modern industrial accommodation which are
constraining business expansion and inward investment
opportunities.
• A place-based approach to economic development,
recognising the differing opportunities and challenges
across Scotland’s urban, rural and town centre
economies.
• Support for inward investment and exports, building on
Scotland's strengths in advanced manufacturing,
renewable energy, life sciences, space technologies and
digital sectors.
6. Are the planned
efficiencies realistic and
deliverable at a scale
The Scottish Government’s planned efficiencies are highly
ambitious, and this raises questions about whether they are
credible, especially in the shorter term. 
203

Page 204

sufficient to make public
services sustainable?
They may contribute significantly to closing medium-term
funding gaps, but there is considerable uncertainty over
whether they can be delivered quickly enough and on a
sufficient scale to make public services sustainably affordable
on their own. 
The degree of uncertainty and scale of ambition represent a
huge risk, and the question is what happens when the
savings are not achieved and where will the impact be felt if
these savings are not achieved.  Local Government cannot
function if it does not get fair sustainable funding to help
achieve shared outcomes. 
The plans are linked to public service reform, digital
transformation, workforce reform, prevention and productivity
improvements rather than simple budget reductions. 
The Spending Review relies heavily on recurring efficiency
savings and productivity gains that exceed historical
performance in some sectors, particularly health and social
care. 
The key issue is scale, the Spending Review assumes
approximately £1.5 billion of recurring savings across
portfolios over the review period. 
The Institute for Fiscal Studies (IFS) has warned that these
assumptions are ambitious by historical standards. It noted
that the planned shift of spending towards community and
preventative services depends heavily on health boards
consistently delivering productivity improvements well above
recent experience. Without those gains, pressures would
either reappear within NHS services or require reductions
elsewhere in government spending. 
Similarly, the Scottish Fiscal Commission has emphasised
that future budgets remain exposed to pay pressures, social
security growth and demographic change even if efficiency
plans are delivered. 
Even if savings are achieved, wider pressures from
demographics, pay costs, social security demand and capital
investment needs are likely to persist. 
As noted above, the Scottish Government’s planned
efficiencies are highly ambitious, and this raises questions
about whether they are credible, especially in the shorter term
and are unlikely, by themselves, to make public services fully
sustainable without additional reform, prioritisation and
potentially further revenue measures. 
From the Council’s perspective, we have been required to
make efficiency savings for years and we need to continue
to cover our own savings requirements and budget
shortfalls on an annual basis.  Planned recurring savings
204

Page 205

across portfolios are on top of this requirement meaning
further financial pressures on Local Government.  Moving
forward, Local Government will be required to achieve
efficiency savings in order to bridge their own budget gaps,
and it cannot be assumed that these efficiencies would be
able to support national budget gaps. Initiatives such as
Extended Producer Responsibility on Packaging (pEPR) as
a means to drive waste reduction, increase recycling and
move towards net zero are welcomed and we remain firm
in our position that all revenue received for pEPR should
not be offset by a reduction in the Local Government
Settlement. 
7. What are the main
risks to revenues from
devolved taxes?
The largest risk to devolved tax revenues is weaker Scottish
Income Tax performance relative to the rest of the UK. 
Other significant risks include behavioural responses to tax
policy, property market volatility affecting Land and Buildings
Transaction Tax (LBTT), demographic pressures, Fiscal
Framework reconciliation risks and wider economic
uncertainty. 
Scottish Income Tax is the largest devolved tax. Revenue
growth could be weakened by slower earnings growth,
weaker employment growth or lower productivity relative to
the rest of the UK. 
Differences between Scottish and UK tax policies may
influence taxpayer behaviour, including income planning,
migration decisions and other responses that affect revenues. 
LBTT revenues depend heavily on property market activity.
Housing market downturns, reduced transactions and weaker
commercial property activity can significantly affect receipts. 
An ageing population and slower growth in the working-age
population could weaken the future tax base and revenue
growth. 
The Scottish Budget depends on how Scottish tax revenues
perform relative to equivalent revenues elsewhere in the UK.
Faster growth elsewhere can reduce Scotland’s net budget
benefit. 
Inflation shocks, recessions, labour market changes and
wider global economic developments can create forecasting
errors and revenue volatility. 
Overall, Income Tax underperformance relative to the rest of
the UK remains the most significant risk to devolved tax
revenues, while property market volatility, demographic
pressures and Fiscal Framework effects create additional
uncertainty. 
205

Page 206

8. Preventative spend
has been a goal for
several years, but the
intended outcomes have
not been fully achieved.   
Why do you think this is
the case and how might a
Preventative Budgeting
Tool help track progress
with achieving outcomes? 
Nearly 15 years on from the Christie Commission, prevention
is not yet fully embedded in Scotland’s public services. 
The health and social care system in particular has been
subject to successive and complex layers of national policy
and structural reform, however a sustained focus on
empowering and resourcing Local Government to support
people to live well and independently in their own
communities is required. 
Prevention works best when delivered close to home.
Empowered Local Government can provide community-based
support, innovative housing solutions, and ethical, inclusive
digital care tailored to local needs.
A skilled and supported workforce is critical to this vision. This
means that staff need to have the time, capacity, and support
to intervene early and build trusted relationships with those
they serve. 
Investment in community-based services can reduce
avoidable crises by strengthening connections between
health, housing, families, and local support networks. 
A whole-system approach to reform is required that integrates
health and social care, embeds human rights, values the
workforce, and enables the flexibility councils need to
respond to local circumstances. 
However, current funding approaches are undermining
progress. Short-term, ring-fenced funding limits the ability to
plan and invest in long-term preventative solutions.  A further
challenge is that without additional funding, spend would
require to be dis-invested from one area. 
Improving population health, supporting inclusive economic
growth and restoring sustainable public finances will require a
decisive shift from crisis response to long-term prevention. 
Local Government is central to this ambition. Councils and
their Leisure Trusts deliver the majority of Scotland’s leisure
services and manage key community assets, including sports
facilities, parks and active travel spaces, providing vital
opportunities for people of all ages and abilities to stay active
and connected. 
However, the sector faces increasing pressure from
legislation, rising operational costs and short-term funding. 
What is needed instead is flexible investment, modernisation
of existing legislation, national support for infrastructure
renewal, stronger leadership and data, and a renewed focus
on inclusion and workforce development. 
In terms of tracking preventative spend and the delivery of
outcomes, an analysis by the Fraser of Allander Institute
206

Page 207

suggests that budgetary information published by the Scottish
Government is at too high a level to allow insight.  They
concluded that “this makes it extremely difficult to identify
what is actually being spent on prevention, let alone to assess
effectiveness.”  They also argue that the organisation of the
budget by portfolio does not lend itself to understanding what
is spent on prevention.  “Portfolio-based budgeting obscures
these connections, and…accountability for delivering
preventive outcomes often sits apart from those with
accountability for the budget levers that can deliver
prevention.” 
We agree with the FAI conclusion that “getting this right
matters. Prevention is not just a technical budgeting exercise.
It is about reshaping how government understands problems,
prioritises action, and invests public resources to improve
long-term outcomes for people and communities across
Scotland, as well as playing a key role in ensuring fiscal
sustainability”.  However, there is a risk around how
information collated on prevention is utilised, and how that
may impact on future financial settlements. 
Investing public resources to improve long-term outcomes is
fundamental, and Local Government services are key levers
in this redesign of public service delivery. 
9. In which areas should
the Scottish Government
prioritise its capital spend
to best support economic
growth?
The Scottish Government should focus capital investment in
areas that deliver long-term productivity gains, strengthen
economic resilience, and leverage private sector investment.
Priorities include:
• Transport and Connectivity
- Investment in strategic transport infrastructure,
including rail services, bus networks and the Glasgow
Metro programme.
- Improved connectivity between cities, towns and
importantly rural communities to enhance access to
employment opportunities and markets.
• Digital Infrastructure
- Expansion of high-quality digital connectivity and
future-proofed telecommunications infrastructure to
support business competitiveness, innovation and
flexible working.
• Industrial Development
- Investment to address the shortage of modern
industrial premises across Scotland.
- Support for enabling infrastructure, servicing of
employment land and development of business and
innovation space to facilitate business growth and
inward investment. South Lanarkshire Council's
industrial property study and similar Glasgow City
Region research have identified significant supply
constraints and increasing obsolescence within
industrial property stock.
• Research, Innovation and Advanced Manufacturing
207

Page 208

- Continued investment in research and development
facilities, innovation districts, and technology to
improve productivity and competitiveness.
• Net Zero and Green Infrastructure
- Investment in renewable energy, hydrogen
technologies, energy networks, electric vehicle
infrastructure, decarbonisation projects and energy
efficiency programmes.
- These investments support job creation, business
innovation and Scotland’s transition to a low-carbon
economy.
• Housing
- Increased investment in affordable and sustainable
housing development and retrofit programmes to
address housing shortages, support labour mobility
and stimulate economic activity within the construction
sector. 
10. How effective are the
Scottish Government’s
existing financial
flexibilities - including
borrowing and the
Scotland Reserve - in
managing fiscal
pressures, and what
limitations, if any, should
be addressed?
Acknowledging that the Scotland Reserve is a financial
mechanism that allows the Scottish Government to manage
its budget by moving funds between financial years, and that
it was established to help smooth spending, manage tax
volatility, and carry forward underspends from existing
budgets, the Scottish Government’s existing flexibilities
(including this and borrowing) are used to support
infrastructure investment during periods of fiscal pressure.   
These flexibilities are constrained by strict Fiscal Framework
with regards to borrowing and reserve caps.  Engagement
with UK Treasury to negotiate on the Framework should
continue. 
Leveraging new funding streams to maximise alternative
funding should also continue to progress.  However,
regardless of the approach, we still need to pay for this over
the longer term. 
11. What role should
alternative financing
approaches – such as
bonds, the mutual
investment model, or
other mechanisms – play
in supporting public
investment and
strengthening Scotland’s
financial resilience? 
Alternative financing should complement, not replace,
traditional public funding. Used carefully, it can help local
authorities accelerate investment, diversify funding and
improve financial resilience.  However, regardless of the
approach, we still need to pay for this over the longer term. 
• Local Authority Bonds – Provide long-term funding for
housing, regeneration, net zero and infrastructure projects
while diversifying borrowing sources.
• Mutual Investment Model (MIM) – Supports investment
when capital budgets are constrained, with the public
sector retaining a stake in projects and sharing returns.
• Institutional and Pension Fund Investment – Can provide
stable, long-term funding aligned with infrastructure and
local economic development.
• Public-Private Partnerships – Can accelerate project
delivery and transfer some risks, provided there is strong
governance and value-for-money assessment.
208

Page 209

• Community and Place-Based Finance – Supports
regeneration, renewable energy and local economic
development through community-led investment
mechanisms. 
Overall, alternative financing should form part of a wider
capital funding strategy, alongside grants and conventional
borrowing, to support infrastructure investment during periods
of fiscal pressure.
Audit Scotland recognises that alternative financing can help
deliver infrastructure when public capital budgets are
constrained, but stresses that it is not a substitute for
sustainable public funding. 
Key points include: 
• Alternative finance can support earlier delivery of
infrastructure such as schools, hospitals and regeneration
projects.
• Private finance is usually more expensive than direct
public borrowing and can create significant long-term
repayment commitments.
• Strong value-for-money assessments, transparency and
clear business cases are essential.
• Councils need to consider long-term affordability and the
impact of repayments on future budgets and services.
• The Mutual Investment Model (MIM) may offer
improvements over previous models, but its performance
should be monitored and evaluated. 
Overall, alternative financing should be used as a
supplementary tool alongside traditional funding. Approaches
such as bonds, MIM and pension fund investment can
support infrastructure, housing and net-zero projects,
provided they offer value for money and remain affordable
over the long term. 
209

Page 210

Appendix 2 
Public Service Reform Committee 
Pre-Budget Scrutiny 2027-28 Call for Views 
1. The Scottish
Government aims to
deliver on average £0.5
billion in savings through
efficiencies per year for
the next three years
(2026-27 to 2028-29):  
a) To what extent are
these savings achievable,
and how will they shape
public service delivery? 
b) What progress is being
made towards achieving
these efficiencies? 
c) What are the barriers
to achieving greater
efficiency and how can
these be addressed? 
a) The Scottish Government’s public sector savings of £0.5
billion per annum is very ambitious especially in the short
term. This level of savings is achievable only if reform, digital
transformation, procurement reform and service redesign are
delivered at pace. As the Scottish Government’s planned
efficiencies are highly ambitious, this raises questions about
whether they are credible, especially in the shorter term.   
Many previous efficiencies in local authorities have already
been captured, meaning future savings increasingly require
structural service reform rather than straightforward cost
reductions. 
Inflation, pay settlements and rising service demand may
offset headline savings. 
Service delivery is likely to become more standardised and
digitally enabled. Service delivery may see a reduction on
local service capacity and longer waiting times. In addition,
there may be increased workforce pressures and reduced
organisational resilience. 
b) Early progress on achieving savings is evident through the
Spending Review efficiency plans, workforce controls and
reform programmes, but most savings remain to be delivered. 
c) Key barriers to achieving greater efficiency include
organisational fragmentation where there is a lack of joined
up working across services, legacy systems, workforce
capacity, risk aversion and short-term budgeting. Stronger
collaboration across public sector bodies and improved data
sharing and investment in change capability are needed to
overcome political and public resistance. 
2. How should the
Scottish Government
best present the extent of
any realised efficiencies
in the annual budget
publication, including
providing clarity on
whether these are
expected to be recurring
savings? 
The Scottish Government should move beyond simply
reporting a headline efficiency figure and instead adopt a
transparent efficiency reporting framework within the annual
budget and supporting documents. This would enable
Parliament, stakeholders and the public to assess whether
reported efficiencies represent genuine productivity
improvements, one-off reductions, or recurring savings. 
Local Government have been required to make efficiency
savings for years. 
210

Page 211

3. The Fiscal
Sustainability Delivery
Plan aims to achieve an
average reduction of the
public sector workforce of
0.5% per year over five
years. 
a) To what extent is this
target achievable and
how will it shape public
service delivery? 
b) What progress is being
made towards achieving
this target? 
a) An annual workforce reduction of 0.5% may be achievable
if it is delivered through natural staff turnover, retirements and
service reform. However, this will be at a cost to services
delivered. 
The target is supported by:
• A large public sector workforce, allowing gradual
reductions through natural attrition.
• Investment in digital services, automation and shared
services.
• A focus on reducing back-office roles rather than frontline
posts, acknowledging that there is an impact of this. 
However, challenges include:
• Growing demand for health and social care and other
services.
• Existing recruitment and staffing pressures.
• The need for productivity improvements to offset
workforce reductions. 
If successful, the approach could:
• Improve efficiency through technology and automation.
• Reduce duplication across organisations which takes time. 
Key risks are:
• Increased workloads for remaining staff.
• Loss of skills and experience.
• Reduced support services affecting frontline delivery.
• Digital exclusion for some service users. 
Overall, the target may be achievable, but only if workforce
reductions are accompanied by genuine service reform and
productivity gains, rather than simply reducing staff numbers. 
As outlined elsewhere, Local Government have already been
reducing their workforce for years. 
b) Progress is most evident in the establishment of a policy
framework linking workforce reform to wider fiscal
sustainability and public service reform objectives. 
Progress is also being made through reforms designed to
support workforce reductions, including:
• Expansion of digital service delivery. 
• Planned greater use of shared corporate services.
• Investments through the £30 million Invest-to-Save Fund
aimed at improving productivity and reducing future
workforce requirements, for example, Scottish
Government initiative to share digital evidence across the
country’s justice system.
211

Page 212

While the policy direction is clear, publicly available evidence
on actual workforce reductions achieved to date remains
limited, acknowledging that it is still early in the process.
To date, there is little published information on:
• Actual headcount reductions achieved.
• Workforce reductions by sector.
• Productivity gains realised.
• The impact on service performance.
Progress towards achieving savings targets remains
aspirational at this stage with policy direction only being
made clear through reforms designed to support workforce
reductions, including expansion of digital service delivery,
automation of administrative processes, planned greater
use of shared corporate services and investments. As a
result, no financial benefit has been achieved to date and
the level that can be achieved in the short term is
questionable.   
4. What actions can the
Scottish Government
take to ensure these
workforce reductions are
delivered in a managed
way which best supports
effective government and
public service delivery 
To ensure workforce reductions are delivered in a managed
way, the Scottish Government should prioritise workforce
planning, retraining, redeployment, digital investment,
succession planning and the protection of critical operational
roles. 
5. The PSR strategy
states that it will protect
frontline services. To
what extent is there
sufficient clarity about
how frontline roles are
defined and how
efficiencies in back-office
functions can be
delivered in a way that
minimises impact on the
delivery of public
services? 
Greater clarity is needed on what constitutes a frontline role.
Savings in corporate functions should focus on shared
services, automation and simplification rather than
transferring administrative burdens to operational frontline
staff. 
Local Government have been required to make efficiency
savings in back-office functions for years. 
6. Beyond the financial
benefits that the Public
Sector Reform (PSR)
Strategy aims to achieve,
what are the key
outcomes that reform
should be aiming for? 
The key outcomes that reform should be aiming for are
improved outcomes, earlier prevention, increased
productivity, better user experience, reduced inequalities,
stronger collaboration, faster decision making and more
sustainable public services.  These principles align to the
aims of the Marmot programme of work being undertaken by
South Lanarkshire Council and its partners in Health and in
communities. 
212

Page 213

7. The PSR Strategy
includes 18 different
workstreams which aim
to remove barriers to
reform. One workstream
focuses on
“simplification”,
recognising that
“complexity of processes,
structures and reporting
requirements is a key
barrier to effective and
efficient service delivery”.
“Prevention” is one of
three pillars providing
structure to the Strategy. 
a) What should the
Scottish Government’s
priorities be under its
simplification workstream
and what level of savings
can be achieved through
this approach? 
b) What progress has
been made to date with
preventative budgeting?
c) How should the
forthcoming Budget
support greater progress
towards preventative
budgeting across the
devolved public sector?
Please set out any
barriers and how these
can be addressed. 
d) What changes to the
Scottish Government's
approach to budget-
setting are needed to
effectively deliver public
service reform? 
a) Priorities under the simplification workstream should
include reducing reporting burdens, simplifying grants,
consolidating organisations where appropriate, standardising
processes and expanding shared services. Savings towards
the overall requirement may be achievable through this
approach. 
b) Progress on preventative budgeting remains limited. The
collation of information on prevention is ongoing however,
there is a risk around how this is utilised, and how that may
impact on future financial settlements. 
c) Future budgets should provide flexible investment, national
support for infrastructure renewal and a renewed focus on
inclusion and workforce development. Barriers include that
without additional funding, spend would require to be dis-
invested from one area. 
d) To effectively deliver public service reform in Scotland, the
Scottish Government could implement the following changes
in its budget-setting approach:
• Integrate public sector pay and workforce planning
• Adopt preventative budgeting
• Collaborate further with public bodies
• Focus on coordinated, holistic services
• Address fiscal pressure 
8. The Scottish
Government included an
upfront Invest to Save
Fund of around £30
million in the 2025-26 and
2026-27 Scottish Budgets
for reform projects that
will deliver ongoing
savings and support the
a) The Fund was established specifically to support projects
that produce long-term efficiencies rather than short-term
reductions in expenditure. Government statements indicate
that funded projects are expected to deliver recurring savings
through service redesign, digital transformation and improved
productivity. 
b) Whilst there are good examples of projects being
delivered, these need to be transferrable and shared across
213

Page 214

delivery of the PSR
strategy. 
a) To what extent is the
Invest to Save Fund
delivering projects that
achieve ongoing
savings? 
b) How are successful
outcomes from this Fund
being shared more widely
across the public sector? 
all Council so that they can be replicated across Local
Government. 
214

Page 215

Report
Agenda Item 
Report to: Executive Committee
Date of Meeting: 19 August 2026
Report by: Executive Director (Finance and Corporate Resources)  
Subject: End of Current Council and Preparations for the New
Council 
1. Purpose of Report
1.1. The purpose of the report is to:-
[purpose]
 advise members of a number of key operational preparations required for the
end of this Council and the establishment of the new Council following the Local
Government Election on 6 May 2027
 request approval for decision-making arrangements in the period leading up to
and immediately following the Local Government Election on 6 May 2027
[1purpose]
2. Recommendations
2.1. The Committee is asked to approve the following recommendation(s):-
[recs]
(1) that the final cycle of meetings in the current Council term, as detailed in the
attached appendix to the report, covering the period up to the final meeting of
the Council on 10 March 2027, be approved;
(2) that, in line with normal practice, with the exception of quasi-judicial matters,
the Chief Executive be authorised to deal with any issues during the period
from 10 March 2027 until the establishment of the new Council, with a report
on the issues dealt with being submitted to the first meeting of the new
Council for noting; and
(3) that preparations for the new Council, as detailed in sections 5 to 8 of this
report, be noted.
[1recs]
3. Background
3.1. The Local Government Elections will be held on 6 May 2027.  The first meeting of
the new Council requires to be held within 21 days of the date of the election. 
4. Arrangements to Deal with Council Business in the Period Leading up to the
Election
4.1. In previous years in which local government elections have been held, the Council’s
committees and forums have ceased to operate for a period of time ahead of the
elections.  One of the main reasons for raising this issue with Committee at this early
stage is to allow Executive Directors to plan the business they need to have
considered by members prior to and including the last meeting of the Council.
10
215

Page 216

4.2. It is proposed that the final cycle of meetings concludes week beginning 8 March
2027 prior to the anticipated publication of the Notice of Election the following week,
when the pre-election period would commence.  This would mean some changes to
the normal cycle of meetings.  It is proposed that the Executive Committee meets on
Wednesday 10 March 2027 at 10.00am followed by a meeting of the full Council at
11.30am (or immediately following Executive Committee, whichever is the later).  It is
further proposed that the Risk and Audit Scrutiny Committee meets on Tuesday 2
March 2027 at 2.00pm.  The proposed final cycle of meetings is attached as an
appendix to the report. 
4.3. There may be a requirement to hold meetings to deal with specific matters such as
planning or licensing issues, hearings or appeals.  Appropriate arrangements will be
made for any meetings considered necessary. 
4.4. In line with the practice previously adopted by the Council, it is proposed that, with
the exception of quasi-judicial matters, authority be delegated to the Chief Executive
to deal with issues that would normally be subject to committee approval from the
last meeting of the Council on 10 March 2027 until the Statutory Meeting of the new
Council.  A report on the matters dealt with by the Chief Executive will be submitted
to the first meeting of the new Council for noting. 
5. Preparations for the New Council
5.1. There are a number of other operational issues which require to be progressed in the
lead up to the end of this term of the Council including:- 
 a review of procedural documentation and the decision-making process
 arrangements for members’ induction and training
 members’ ICT provision (the return of kit for those members not intending to
stand for re-election and the ordering of any necessary new kit)
 the first statutory meeting of the new Council 
5.2. A summary of the key tasks is given in sections 6 to 8 below. 
6. Review of Supporting Procedural Documentation/Decision-Making Process
6.1. A review of the Council’s procedural documentation will be carried out in advance of
the new Council term, which will include a review of the following political
management documentation: - 
 Standing Orders on Procedures
 Scheme of Delegation
 Terms of Reference for Committees, etc
 Standing Orders on Contracts
 Financial Regulations 
6.2. While a comprehensive review of the above documentation was undertaken as part
of the mid-term review that concluded with reports to the Council in September and
November 2024, it is proposed to, once again, consult with officers, the Corporate
Management Team, as well as members via the Standards and Procedures Advisory
Forum (SPAF).  In addition to the procedural management documentation,
consultation will be undertaken on whether changes are required to the Role Profiles
for Elected Members and Multi Member Ward Protocol.  Consultation with officers
will be undertaken in August/September 2026 and a meeting arranged of the SPAF
in September to consult with members.  The outcomes following the consultation will
be presented to members at a meeting of the SPAF to be arranged in November
2026.  Further meetings of the SPAF will be arranged as required.
216

Page 217

6.3. The revised documents will be presented for approval to the new Council at its
Statutory meeting in May 2027 (this meeting has to be held within 21 days following
the date of the Local Government Elections). 
6.4. It is further proposed that the views of elected members are invited via a survey as
part of the end of Council consultation process.  The previous end of term survey
focused on the following main areas:- 
 Policy, Priorities and Direction
 Engagement with the Community and the Council’s Partners
 Decision-making and Delegation
 Respective Roles of Officers and Elected Members 
 Delivering Services
 Support for Members
 ICT Equipment
 Moving Forward – comments sought on what the Council does particularly well
and where it could do better 
6.5. It is proposed that the survey is submitted to the SPAF in September 2026 for
endorsement and then issued to members, with a deadline date for return in October
2026.  The outcomes could be reported to the next meeting of the SPAF which will
be scheduled for late November 2026. 
7. Member Induction and Training Programme
7.1. A member induction and training programme will be put in place for the new Council. 
In the initial period, training will be prioritised to cover mandatory/regulatory
requirements.  Although both the format and method of delivery have still to be
agreed as part of the programme, Resources will have the opportunity to provide
briefings to elected members which are summarised below. 
7.2. In the week following the Local Government Elections (week commencing 10 May
2027), it is proposed that drop-in sessions will be arranged for all members.  In the
past, those sessions covered: - 
 ‘Welcome and General Overview’ by the Chief Executive
 Role and Responsibilities as a councillor
 The Council (how it works – overview of the decision-making process; Council
Plan; Performance and Challenges)
 ‘The First Few Weeks in Office’
 ‘Strathclyde Pension Fund’ - information on the scheme given by a
representative of SPF 
7.3. A number of sessions will be held on The Councillors’ Code of Conduct.  It will be
mandatory for all members to attend one of those sessions which will be delivered by
the Chief Executive, Executive Director (Finance and Corporate Resources) and the
Head of Administration and Legal Services.  IT training sessions will be planned in
the same week as the Code of Conduct sessions.  This will cover the use of the
smartphone, laptop devices and downloading committee papers.  The use of the
Council’s AV system, Confero will also be covered prior to the statutory meeting.
217

Page 218

7.4. Further induction training will be programmed to be held prior to the summer recess
in 2027 and will include:- 
 Resource briefings
 The Council Plan 2027 to 2032
 Training for Chairs/Deputes
 Data Protection and Freedom of Information
 Licensing Board training (by law, this is mandatory for all Board members)
 Planning and Planning Local Review Body overview (this is expected to be
made mandatory for all relevant members)
 Licensing Committee training
 Appeals Panel Training
 Education Appeals Panel Training
 Recruitment Panel Training
 Local Government Finance, including Risk and Audit 
7.5. It should be highlighted that members will also be given access to the e-learning
through the Council’s Fusion learning platform and Improvement Service materials
and webinars. 
7.6. A further programme of training will be scheduled following the 2027 summer recess
and, in liaison with Personnel Services, an individual Training Needs Analysis will be
developed for each elected member, at an appropriate time, to inform further training
requirements. 
8. Members’ ICT Provision
8.1. In accordance with previous years, members will have the option to retain their
equipment until the election date. However, arrangements will be put in place to
allow any non-returning members who might wish to return their equipment early, in
the period from the last scheduled meeting to the date of the election on 6 May 2027,
to do so. 
8.2. Arrangements will be made to ensure that ICT equipment is rolled out to newly
elected councillors in week commencing 10 May 2027. 
9. First Statutory Council Meeting
9.1. As previously stated, the first Statutory meeting of the Council must be held within 21
days after the election and at that meeting, the new Council will consider its decision-
making structure, committee/decision making timetable and issues relating to
committee cycles and recess periods. 
10. Employee Implications
10.1. There are additional tasks/duties that required to be managed within the associated
timeframe. These will be managed within existing employee resources. 
11. Financial Implications
11.1. All costs will be met within existing budgets. 
12. Climate Change, Sustainability and Environmental Implications
12.1. There are no climate change, sustainability, or environmental implications in terms of
this report. 
218

Page 219

13. Risk and Other Implications
13.1. There is a risk that appropriate decision-making arrangements are not in place to
deal with Council business both in the lead up to an election and immediately
following it and this might reflect on the reputation of the Council.  Planning in
advance for such a major event helps to mitigate any risk. 
14. Integrated Impact Assessment and Consultation Requirements
14.1. There was no requirement to undertake an integrated impact assessment or
consultation in relation to the proposals contained within this report.  Consultation will
be undertaken as part of the processes involved in preparing for the new Council. 
Jackie Taylor
Executive Director (Finance and Corporate Resources) 
16 July 2026 
Link(s) to Council Values/Priorities/Outcomes
 Accountable, effective, efficient, and transparent 
Previous References
 None 
List of Background Papers
 None 
Contact for Further Information
If you would like to inspect the background papers or want further information, please
contact: - 
Susan Somerville, Administration Manager
Ext:  4197 (Tel:  01698 454197)
E-mail:  susan.somerville@southlanarkshire.gov.uk 
219

Page 220

220

Page 221

Appendix 1 
Last Cycle of Meetings in Current Council Term 
Cycle Day of Week Time Committee 
Week 1 Monday 1/2/27  
Tuesday 2/2/27 10.00am
2.00pm
Licensing Committee
Community and Enterprise Resources
Committee
Wednesday 3/2/27 10.00am
2.00pm 
Housing and Technical Resources Committee
Cambuslang and Rutherglen Area Committee 
Week 2 Monday 8/2/27 10.30am PLRB
Tuesday 9/2/27 9.30am
10.00am
Conference Allocation Committee
Planning Committee
Wednesday 10/2/27 10.00am
2.00pm
Rural Task Force
Clydesdale Area Committee
Week 3 Monday 15/2/27 1.00pm Joint Consultative Forum
Tuesday 16/2/27 10.00am
2.00pm
Roads Safety Forum
East Kilbride Area Committee
Wednesday 17/2/27 10.00am
2.00pm
EXECUTIVE COMMITTEE
Employee, Equality, Diversity and Inclusion
Forum (EEDIF)
Week 4 Monday 22/2/27  
Tuesday 23/2/27 10.00am
2.00pm
Licensing Committee
Performance and Review Scrutiny Forum
Wednesday 24/2/27 10.00am
2.00pm
Climate Change and Sustainability Committee
Hamilton Area Committee
Thursday 25/2/27 2.00pm Financial Resources Scrutiny Forum
Week 5 Monday 1/3/27  
Tuesday 2/3/27 10.00am
2.00pm
Education Resources Committee
Risk and Audit Scrutiny Committee
Wednesday 3/3/27 10.00am
2.00pm
Social Work Resources Committee
Finance and Corporate Resources Committee
Week 6 Monday  8/3/27 10.30am PLRB
Tuesday 9/3/27 9.30am
10.00am
Conference Allocation Committee
Planning Committee
Wednesday 10/3/27 10.00am
11.30am
Executive Committee
SOUTH LANARKSHIRE COUNCIL 
Note:   
• a meeting of the Licensing Committee scheduled for Tuesday 16 March 2027 at
10.00am will remain
• scheduled partnerships and joint boards are not included in the table above
• in accordance with usual arrangements, a special meeting of South Lanarkshire Council
will be arranged in February 2027 to agree the budget for 2027/2028 
10
221

Page 222

222

Page 223

Report
Agenda Item 
Report to: Executive Committee
Date of Meeting: 19 August 2026
Report by: Executive Director (Housing and Technical Resources)  
Subject:   Land and Property Transfers and Disposals 
1. Purpose of Report
1.1. The purpose of the report is to:-
[purpose]
 advise the Executive Committee of the actions required in respect of land and
property transactions
1purpose]
2. Recommendation(s)
2.1. The Committee is asked to approve the following recommendation(s):-
[recs]
(1) that the land detailed in Appendix A, which will be the subject of negotiated
transactions, be declared surplus to Council requirements.
[1recs]
3. Background
3.1. Details of land and property, which is potentially suitable for redevelopment or
disposal, are circulated to all Resources and Community Planning Partners to
establish if they are suitable for alternative operational use. 
3.2. Recommendations are made following the consideration of planning, title and other
legal constraints.  Any assets with competing interests are judged against Council
priorities, including the need for capital receipts. 
3.3. Transactions outwith the Property Bulletin process, where there is a requirement to
reallocate or declare property surplus as part of minor/adjoining sales, or to facilitate
a Council project, are not circulated through the Property Bulletin, however the
details are included in this report. 
3.4. Transactions are only included in the report after successful consultation with the
holding Resource(s) and Planning. 
4. Non Bulletin Disposals
4.1. Appendix A details negotiated transactions where the land requires to be declared
surplus in order that Property Services can conclude negotiations for its disposal to
adjoining owners. 
4.2. The proposed disposal for the land at Loch Striven, East Kilbride is for inclusion into
the existing garden area to regularise the shape and allow for a potential future,
small extension, subject to planning. 
11
223

Page 224

4.3. The land at Abernethy Park, East Kilbride will be incorporated into the neighbouring
property which has been extended (within the curtilage of the existing ownership).
This sale will correct an existing encroachment of land and provide privacy for the
garden from the elevated, adjacent road. 
4.4. The sale of the land to the rear of the property at Strathlachlan Avenue is for an
extension to the rear garden and includes a garage/lock up which the owner of the
property currently leases from the Council. 
5.  Employee Implications
5.1. There are no employee implications. 
6. Financial Implications
6.1. Capital receipts for both General Services and Housing Revenue Accounts will be
secured through the disposals identified in this report. 
7. Risk and Other Implications
7.1. There is a low risk that the capital receipts anticipated, as a result of declaring these
properties surplus, may not be realised if, for reasons out with the Council’s control,
the purchasers choose not to proceed with the transactions.  However, the
procedures and consultations described in Sections 3 and 8 of this report have been
implemented to minimise this risk. 
7.2. There are no significant issues in terms of sustainability arising from this report. 
8. Integrated Impact Assessment and Consultation Requirements
8.1. This report does not introduce a new policy, function or strategy or recommend a
change to an existing policy, function or strategy and, therefore, no impact
assessment is required. 
8.2. Consultation was undertaken with Planning, Roads, Legal, and the respective
holding resource prior to the inclusion in this report. 
Stephen Gibson
Executive Director (Housing and Technical Resources) 
17 July 2026 
Link(s) to Council Values/Priorities/Outcomes
 Accountable, effective, efficient and transparent 
List of Background Papers
 Plans of the land and property referred to in this report 
Contact for Further Information
If you would like to inspect the background papers or want further information, please
contact:- Gerry McParland, Property Services Manager (Assets and Estates)
Ext: 5177  (Tel: 01698 455177)
E-mail:  gerry.mcparland@southlanarkshire.gov.uk
224

Page 225

APPENDIX A - Land 
NON BULLETIN DISPOSALS 
Area  Description Holding
Account
Proposal Value
Band
29 sq m 2 Loch Striven, East Kilbride Community
& Enterprise
Garden Ground 4
183 sq
m
1 Abernethy Park, East
Kilbride
Community
& Enterprise
Garden
Ground/Encroachment
4
70 sq m 18 Strathlachlan Avenue,
Carluke
Housing
(HRA)
Garden
Ground/Parking
4
Value Bands
1 – over £1 million
2 – £500,000 to £999,999 
3 – £100,000 to £499,999 
4 – less than £100,000 
225

Page 226

226

Page 227

227

Page 228

228

Page 229

Report
Agenda Item 
Report to: Executive Committee
Date of Meeting: 19 August 2026
Report by: Executive Director (Housing and Technical
Resources)  
Subject: Annual Review of the South Lanarkshire Anti-
social Behaviour Strategy 2024 to 2029 
1. Purpose of Report
1.1. The purpose of the report is to:- 
 provide Executive Committee with an update on the progress made during
2025/2026 against delivering the agreed outcomes in the Anti-social Behaviour
Strategy 2024 to 2029
[purpose]
2. Recommendation(s)
2.1. The Committee is asked to approve the following recommendation(s):- 
(1) that the progress in delivering the agreed Anti-social Behaviour Strategy 2024 to
2029 actions and measures be noted; and
(2) to note that the outcomes of the review would be reported to the Safer South
Lanarkshire Board on 7 September 2026 for noting. 
3. Background
3.1. The Anti-social Behaviour etc. (Scotland) Act 2004 requires local authorities to prepare,
publish, and review a strategy for dealing with anti-social behaviour within the local
authority area, in conjunction with Police Scotland. 
3.2. The South Lanarkshire Anti-social Behaviour Strategy 2024 to 2029 was approved by
Executive Committee on 20 March 2024 and implemented from 1 April 2024.   
3.3. The Strategy covers a five-year period with the second annual review outlining
progress achieved during 2025/2026.  The first annual review was presented to
Executive Committee on 24 September 2025. 
3.4. The Strategy is constructed around six strategic objectives with a series of indicators
(actions or measures) contained within each to be delivered by the Council and its
partners. These are:- 
 People behave responsibly in their attitude to alcohol and are educated in relation
to the impact of drugs
 People behave responsibly in relation to fire safety
 The impact of domestic noise is reduced
 Illegally discarded litter and household waste is reduced, improving the safety
and attractiveness of communities  
12
229

Page 230

 Levels of disorder are reduced, including graffiti and vandalism, improving safety
within communities
 Partners engage with residents to promote and improve the availability of and
access to services for those affected by anti-social behaviour 
3.5. The Anti-social Behaviour Strategy Implementation Group (ASBIG) is responsible for
overseeing the ongoing implementation and monitoring of the Strategy. This
partnership group considers progress against outcomes achieved and the effective
reporting of progress through the Safer South Lanarkshire Board and wider
community planning structures. 
3.6. In addition, the ASBIG is responsible for identifying issues to be reflected in the annual
review of the Strategy, including any additions to or removals or from the action plan. 
4. Context and Wider Policy Changes
4.1. A small number of changes in the policy context relating to anti-social behaviour have
taken place nationally since the Strategy was approved in March 2024, including: 
 The Scottish Government commissioned Safer Communities Scotland to
conduct a nationwide review of anti-social behaviour strategies across 32 local
authorities.  The review was published in November 2025 and highlighted a
range of positive approaches to partnership working, integration, and innovation,
with strategic and partnership working in South Lanarkshire included as an
example of good practice.  The review also noted a range of persistent and
shared challenges including outdated legislation, resource constraints,
information sharing, and responding to complex cases.  Plans for implementation
of recommendations continue to be developed in line with the existing Verity
House Funding Agreement  
 The Scottish Government has commenced a review of anti-social behaviour
legislation to identify where updates may be required to assist local authorities
and Police Scotland in tackling new or emerging issues.  Community Safety
partners in South Lanarkshire will participate in the review as required, including
the stakeholder consultation expected during 2026/2027. 
5. Anti-social Behaviour Strategy Annual Review
5.1. The Anti-social Behaviour Strategy 2024 to 2029 is structured around six strategic
outcomes.  There are 36 indicators against which the Council monitors progress,
made up of 22 actions and 14 measures.  In line with wider reporting arrangements
across the Council, these indicators can be categorised into ‘green’, ‘amber’, or ‘red’
depending on the progress made against them.  Actions can also be recorded as
‘completed’ where appropriate, or ‘to be reported later’ if they are planned for delivery
in a future year of the strategy. 
5.2. At the end of 2025/2026, 94% of indicators were in line with projected targets, up from
91% in 2024/2025.  Table 1 outlines the 2025/2026 categorisation of the 36 indicators.  
230

Page 231

Table 1: Overview of actions and measures 
Blue Green Amber Red To be reported
later Total
0 34 2 0 0 36
Table 1: Categorisation of ASB Strategy actions and measures 2025/26 
5.3. Key highlights across the six strategic outcomes achieved during 2025/2026, including
those in relation to actions or measures categorised as ‘green’ in the review are
provided below:-   
Strategic Outcome 1 – People behave responsibly in their attitude to alcohol and
the impact of drug misuse is reduced 
 The ‘It’ll Cost You!’ campaign was run by Police Scotland and partners, including
Housing Services, between June and August 2025 to raise awareness of the
damaging effects and criminal nature of buying alcohol for under 18s. The
campaign was supported by 43 licensed premises in South Lanarkshire, and no
one was charged with illegally buying alcohol for underage youths.  This
maintains the good progress made in 2024/2025 when 46 premises promoted
the campaign with one person being charged 
 The Council’s Joint Problem Solving Unit continues to build on its positive
approach to partnership working to help minimise the impact of drug and alcohol
misuse.  During the year this has included an Anti-social Investigation Officer
becoming a member of the Alcohol and Drug Partnership Working Group, as well
as increasing promotion of support available by including details in letters issued
to perpetrators of anti-social behaviour and circulating the Positive Pathways
booklet to staff and customers 
 During 2025/2026, the Lanarkshire Police Licensing Department (LPLD)
delivered guidance and support to licensed premises through the Pubwatch
scheme, with a particular focus on women’s safety, domestic abuse, and drink
spiking.  Additionally, they delivered 10 bystander training events to licensed
premises to help reduce anti-social behaviour and create a safer environment for
staff and customers 
 The Cambuslang and Rutherglen Community Policing Team established a
Community Alcohol Partnership (CAP) with the aim of working with partners to
reduce the threat of alcohol misuse and drug use among young people and
promote healthier lifestyles and safer communities.  The CAP works with youth
groups in safe community spaces, encouraging constructive peer engagement
while providing informal alcohol education 
 School Liaison and Prevention Officers from Police Scotland delivered
workshops and presentations to 1,715 young people in schools across South
Lanarkshire on the dangers, risks, and possible consequences around drug
consumption.  
231

Page 232

Strategic Outcome 2 – People behave responsibly in relation to fire safety 
 The Scottish Fire and Rescue Service (SFRS) responded to 440 deliberate
secondary refuse fires during 2025/2026, which represents a decrease of 13%
from the baseline (2022/2023) for the Strategy 
 80 fire related education programmes reaching approximately 2,500 children
were delivered by Scottish Fire and Rescue Service in schools across South
Lanarkshire, including primary and secondary schools in Larkhall, East Kilbride,
Blantyre, and Biggar.  These are complemented throughout the year by thematic
and seasonal, including in the run up to Bonfire Night, contributing to no notable
incidents or acts of violence being recorded during the bonfire period in 2025 
 There were five tailored Fire Reach Courses delivered to 36 young people by the
SFRS, including people who are known to have been involved in unsafe
behaviour around fire. These courses outline the impact of anti-social behaviour
on others, potential consequences of hoax calls, costs to the service and impact
on future life and career choices for young people 
 An information leaflet on the safe storage of flammable items such as electric
bikes was developed by SFRS and widely circulated by the Council’s Housing
Services and Police Scotland in locations where they are known to be stored in
common escape routes from domestic buildings. An article was also published
in the council’s summer edition of Housing News, shared with over 26,000
tenants, providing advice on the storage of equipment such as mobility scooters,
vapes and laptops which have Lithium-ion batteries with additional safety tips
from the Scottish Fire and Rescue Service 
Strategic Outcome 3 – The impact of domestic noise is reduced 
 During 2025/2026 the Council received 2,476 noise complaints, with 948
incidents requiring a visit by officers to assess noise levels.  While there has been
a slight increase in the number of reports compared to 2024/2025, the number
of complaints remains 10% lower than the strategic baseline (2022/2023), with
the number of incidents requiring attendance by an officer remaining 16% lower 
 The Council’s Housing Services promoted mediation where there are issues of
domestic noise, which can be useful in uncovering unintentional noise in
situations where people have not realised the impact on neighbours.  During
2025/2026 the Environmental Health Noise Team made 74 referrals for
mediation, leading to  the agreement of mutually agreeable improvements for
residents, particularly in relation to domestic living noise in four in a block and
flatted properties 
 The Council’s Environmental Health Noise Team continues to work with partners
within the locality-based Community Safety Hubs to ensure early intervention
where partners highlight any domestic noise issues  
232

Page 233

Strategic Outcome 4: Illegally discarded litter and household waste is reduced,
improving the safety and attractiveness of communities 
 Environmental Health Services made use of additional short-term resources in
2025/2026 to recruit staff to support a stronger, enforcement-based approach to
fly-tipping across the council area.  This has contributed to a 3% reduction in the
number of recorded fly-tipping incidents compared to the baseline for the strategy
(reducing from 2,994 to 2,903) and an increase in referrals for potential criminal
charges to the Crown Office and Procurator Fiscal Service from 1 in 2024/2025
to 17 in 2025/2026 
 Grounds Services continued to work alongside Housing Services across each
division to identify issues within bin stores at flatted properties. This includes
trialing possible solutions such as introducing additional bin areas and improving
access to communal bin storage areas to encourage people to return bins when
emptied and reduce the number left out on the street. Transparent sided bins
have also been trialled in a number of different areas for flatted properties. These
have been found to decrease contamination and encourage residents to be more
responsible with their waste.  
 Targeted patrols continue to take place throughout South Lanarkshire in areas
where there are high numbers of complaints about litter and/or dog fouling, such
as public parks and town centers/retail parks.  This has contributed to five Fixed
Penalty Notices for dog fouling being issued during 2025/2026 compared to zero
in 2024/2025 
Strategic Outcome 5: Levels of disorder are reduced, improving safety within
communities 
 Police Scotland recorded 3,347 anti-social behaviour offences during 2025/2026. 
Whilst this remains 11% below the baseline for the strategy of 3,462, it is an
increase of 17% from 2024/2025.  Police Scotland state the main factors
contributing to the rise include an increase in threatening and abusive behaviour,
racially aggravated crimes, licensing offences, and drinking in public.  To tackle
the increase, Police Scotland have put in place high visibility patrols in hotspot
areas, delivered licensed premise visits, and ensure daily scrutiny of all hate
crimes, most of which are against Police Officers, to ensure all necessary
resources are allocated to investigations.  Data will continue to be monitored to
identify whether this is a short-term increase or the beginning of a longer-term
trend 
 During 2025/2026, the number of vandalism incidents reported to Police
Scotland remained static at 1,228 but were 27% lower than the baseline figure
of 1,681.  To maintain this reduction, Police Scotland and the Council’s Joint
Problem Solving Unit continue to work in partnership to identify emerging trends
and hotspot areas where vandalism takes place.  Analytical work can help narrow
down dates, times and common locations of offences, allowing Police Scotland
to deliver targeted, visible patrols, supported by the council’s Community
Wardens who play an important role in supporting the community while
promoting public safety.  The council’s graffiti removal team respond quickly
where it has been identified, removing offensive graffiti within 24 hours  
233

Page 234

 A range of diversionary activities were delivered during the year to tackle disorder
including:- 
➢ Supporting young people to achieve a Duke of Edinburgh award which
contributes to the development of self-esteem and confidence, leading
people onto other positive activities.  As an early intervention route, the
Duke of Edinburgh Award offers structured goals and positive role models
that support young people towards constructive personal growth and
opportunities to build connections within their community.   
➢ Delivering drug and alcohol workshops through Universal Connections to
support young people live healthy Iifestyles.  The trusted relationships
between Youth, Family and Community Service staff and young people play
an important role in facilitating honest engagement and finding the right
engagement opportunities. 
➢ Rolling out Pathfinder programmes to all South Lanarkshire secondary
schools, with a Youth Family and Community Service Pathfinder member
of staff in all 17 mainstream secondary schools by the start of the academic
term in 2026.  The approach acts as a bridge between home and school
through building relationships built on trust, openness and partnership. This
contributes to improving confidence and self-esteem, which supports young
people to recognise factors impacting on their lives and improve self-
management of negative peer influences. 
Strategic Outcome 6: Partners engage with residents to promote and improve
the availability of and access to services for those affected by anti-social
behaviour 
 Victim Support Scotland (VSS) has continued to work closely with partners to
increase awareness of the support available to victims of anti-social behaviour
across South Lanarkshire. During 2025/2026 they received 144 referrals from
South Lanarkshire Council in relation to  court and community support, up from
the baseline figure (2022/2023) of 81 referrals and 138 referrals in 2024/2025. 
 Housing Services continue to work with the Council’s Corporate Communications
to co-ordinate an annual programme of information on the impact that anti-social
behaviour has on local communities and the range of services available from
across the Council and its partners to offer support.  Monthly articles are posted
on the council’s social media or published in the South Lanarkshire View
reflecting priorities for that time of the year. 
5.4. Two ‘amber’ measures were partially achieved with minor slippage:- 
 While the number of reported crimes of wilful fire raising dropped from 165 in
2024/2025 to 154 in 2025/2026, they remain marginally higher than the baseline
(2022/2023) of 153.  Scottish Fire and Rescue Service continue to focus on
reducing instances of deliberate fire setting through partnership working and
delivering anti-social behaviour presentations to young people across South
Lanarkshire 
234

Page 235

 The number of referrals made to the Housing Services’ Mediation Service for
community mediation decreased from the baseline figure of 418 to 362 in
2025/2026, with 55 of these referrals coming for young people at risk of
homelessness.  Despite the slight reduction in referrals, the mediation service
continues to deliver high success rates, with 96% of cases requiring no further
contact with Council services 
5.5. No indicators were assessed as having major slippage (‘red’) through the review during
2025/26. 
6. Proposed Revisions to the Strategy
6.1. As well as providing an opportunity to assess and report on progress, the annual
review process allows for a general re-examination of the Anti-social Behaviour
Strategy 2024 to 2029 by partners to ensure that the strategic objectives, actions and
measures remain appropriate, relevant and measurable. 
6.2. Following the completion of the review, there are no proposed revisions to the
performance framework were identified at this stage, with all objectives and indicators
remaining relevant. 
7. Next Steps
7.1. Subject to approval from Executive Committee, the annual review  will also be
presented to the Safer South Lanarkshire Board on 7 September 2026 for noting.   
7.2. The Council will continue to work strategically with Police Scotland and a range of
community safety partners to tackle anti-social behaviour through ASBIG and other
forums across South Lanarkshire throughout 2026/2027. 
7.3. The third annual review, covering progress and activity within 2026/2027 will be
presented to Executive Committee in autumn 2027. 
8. Employee Implications
8.1 There are no employee implications as a result of this report. 
9. Financial Implications
9.1 There are no financial implications as a result of this report. 
10. Climate Change, Sustainability and Environmental Implications
10.1. There are no climate change, sustainability, or environmental implications as a result
of this report. 
10.2. The Strategic Environmental Assessment (SEA) pre-screening determination reached
during the development of the strategy concluded that a full SEA was not required. 
11. Risk and Other Implications
11.1. There are no other implications as a result of this report. 
11.2. Undertaking an annual review of the Anti-social Behaviour Strategy is a statutory
requirement. 
12. Integrated Impact Assessment and Consultation Requirements
12.1. Whilst the Anti-social Behaviour Strategy 2024 to 2029 was introduced prior to the
implementation of Integrated Impact Assessments, both an Equality Impact
235

Page 236

Assessment and a Fairer Scotland Duty assessment were conducted. These
documents are available on request from Housing Services. 
12.2. There was no requirement to undertake any consultation in terms of the information
contained in this report. 
Stephen Gibson
Executive Director (Housing and Technical Resources) 
14 July 2026 
Links to Council Values/Priorities/Outcomes
 Focused on people and their needs
 Working with and respecting others
 Accountable, effective, efficient and transparent
 Ambitious, self-aware and improving
 Fair, open and sustainable 
Previous References
 Executive Committee Report ‘Anti-social Behaviour Strategy 2024 to 2029’, 20 March
2024.
 Executive Committee Report ‘Anti-social Behaviour Strategy Annual Review
2024/2025’, 24 September 2025 
List of Background Papers
 South Lanarkshire Anti-social Behaviour Strategy 2024 to 2029 
Contact for Further Information
If you would like further information, please contact: - 
Claire Frew, Strategy and Policy Co-ordinator, Housing and Technical Resources E-mail:
claire.frew@southlanarkshire.gov.uk 
236

Page 237

Report
Agenda Item 
Report to: Executive Committee
Date of Meeting: 19 August 2026
Report by: Executive Director (Finance and Corporate Resources)  
Subject: Cost of Living Support 
1. Purpose of Report
1.1. The purpose of the report is to:-
[purpose]
 provide the Executive Committee with an update on the welfare support that has
been provided to households in South Lanarkshire by a range of Council services
and organisations to 31 March 2026 
2. Recommendation(s)
2.1. The Executive Committee are asked to note the following recommendation(s):-
]
(1) that the support provided by a range of services and organisations in helping
households manage the effects of the cost-of-living crisis be noted.
1ecs]
3. Background
3.1. The cost of living continues to present significant financial pressures for many
households.  The conflict in the Middle East has put sustained pressure on oil prices,
that in turn has impacted the price of many commodities notably fuel, energy and
heating oil. Inflation was 2.6% for the 12 months to June 2026.  The Bank of England
base rate is currently 3.75%, with the Bank noting they need to make sure higher
energy costs do not lead to sustained higher inflation. 
3.2. The report focuses on how a range of Council services (Money Matters Advice
Services, Benefits and Revenues, Housing, Social Work and Education), Foodbanks,
Citizens Advice Bureaus, Social Security Scotland and NHS Lanarkshire provided vital
welfare support to many households in South Lanarkshire during 2025/2026. 
4. Cost of Living Support
4.1 Money Matters Advice Service
4.1.1. During 2025/2026, the Money Matters Advice Service (MMAS) continued to support
residents across South Lanarkshire to maximise income, provide emergency
assistance and address issues relating to over-indebtedness. 
4.1.2. By 31 March 2026, the Service had supported 12,723 unique clients in relation to
31,803 issues.  This included 11,769 residents who contacted the Service during
2025/2026, together with clients whose cases had been carried forward from
2024/2025.  The final financial gains achieved during the reporting period are set out
overleaf:- 
13
237

Page 238

Type of Gain 2025/2026
Total welfare/benefit financial gain £24.89m
Total debt write-off £2.58m
Total Financial Gain  £27.47m 
4.1.3. The Community Wellbeing Team made the following referrals for energy top-up
vouchers and food bank vouchers during the reporting period:- 
Type of Referral 2025/2026
Energy Top Up Voucher Referrals 2,682
Foodbank Referrals 1,855 
4.1.4. Importantly, 97% of all clients receiving food bank and fuel bank referrals received
support on the same day that they contacted the Service. 
4.1.5. MMAS continues to work with a range of fuel bank voucher providers, including the
Fuel Bank Foundation and Scottish Power. During 2025/2026, the Service also had
access to a modest allocation of vouchers funded through SGN, which could be issued
directly by MMAS. 
4.1.6. Additional support provided by the Community Wellbeing Team to residents
experiencing food and fuel crisis was available through the Cash First Scheme,
delivered in partnership with local Citizens Advice Bureaux.  The scheme provided £50
vouchers and was launched in October 2023 using Scottish Government Local
Authority Covid Economic Recovery funding. The project concluded in September
2025. 
4.1.7. A total of 99% of eligible applicants received their cash voucher on the same day that
they applied.  Overall, 8,763 vouchers were issued and redeemed over the duration
of the Scheme, representing a combined financial value of £438,150.  This substantial
level of support demonstrates the scale and impact of the project in helping to address
immediate food and fuel insecurity across South Lanarkshire. 
4.1.8. In addition, referrals were made to specialist Welfare Rights, Money Advice, or Energy
Advice services, ensuring clients received comprehensive support beyond their
immediate crisis needs. 
4.1.9. MMAS continues to work with SGN, a British gas distribution company and was
awarded £0.070 for 24 months, to employ an additional temporary Energy Adviser until
March 2028. This is to provide a variety of support including provision of energy advice. 
4.1.10 MMAS continues to work collaboratively with a range of other internal and external
partners to enhance support for South Lanarkshire residents.  This includes joint
initiatives with Employability Services to improve financial stability and sustain
employment; partnership working with Macmillan Cancer Support to provide specialist
welfare rights advice to individuals affected by cancer; and close collaboration with
NHS Lanarkshire to support NHS teams and patients experiencing financial hardship
because of ill health and the cost-of-living crisis.  These partnerships ensure a
coordinated approach to advice provision, improve access to specialist support, and
maximise the overall impact of the service. 
238

Page 239

4.2. Benefits and Revenues Service
4.2.1. Support for households who have fallen into arrears or are experiencing difficulty with
payment of Council Tax, continues to centre on the award of Council Tax Reduction
(CTR).  There are currently 30,189 active claims for CTR in South Lanarkshire.  The
actual value of awards for 2025/2026 was £24.976m and the projected value of awards
for 2026/2027 is £26.719m; 7% higher than last year. 
4.2.2. There continues to be significant demand for grants from the Scottish Welfare Fund
(SWF).  Applications received up to 31 March 2026 were 0.8% more than the same
time last year.  The award rate up to 31 March 2026 was 60%, up 4% on the same
time the previous year. Grants to a value of £2.726m were awarded up to 31 March
2026. 
4.2.3. To 31 March 2026, the service made payments to low-income households of £3.702m
covering School Clothing Grants (£2.181m) and Free School Meal (FSM) payments
for holidays (£1.521m). 
4.3. Housing Support for Tenants
4.3.1. Housing Services continues to support all Council tenants with rent arrears, this can
include providing financial assistance through the successful Tenancy Sustainment
Fund, which aims to sustain tenancies and prevent homelessness.  During the last
financial year, this fund has helped 489 individual households, including 207 children,
with awards totalling £0.3m.  The Service also continues to promote supports available
to tenants through the council’s social media platforms and in the Housing news. 
4.3.2. The Council declared a housing emergency in 2024 due to sustained pressure on
housing and homeless services, driven by increasing demand for homelessness
assistance, including temporary accommodation, alongside a reduction in available
housing options.  These pressures have been compounded by cost-of-living increases
and a contraction in the private rented sector.  While the position has since stabilised
to some extent, with a slight reduction in homelessness presentations, levels remain
above pre-pandemic trends.  The cumulative pressure on the system continues to
have a lasting impact, particularly on the time taken to resolve homelessness and
pressure on temporary and permanent housing. 
4.3.3. The Department for Work and Pensions (DWP) Managed Migration Programme (Move
to Universal Credit (UC)) is nearing completion with the majority of housing benefit
and Employment and Support Allowance (ESA) claimants now migrated.  Housing
Services will continue to work with and support tenants to help them make a successful
claim for UC and manage their rent payments to reduce this impact. 
4.3.4. Households at risk of or experiencing homelessness remain vulnerable to financial
insecurity and hardship, particularly in the current economic climate.  To address these
challenges, housing options advice is provided at an early stage to support
homelessness prevention, with targeted support offered to those with an assessed
need.  This support is tailored to individual circumstances, helping households secure
and sustain permanent accommodation and reduce the risk of repeat homelessness. 
4.4. Care Experienced Young People
4.4.1. In 2025, funding of £0.040m was used to reach and support more than 200 young
people.  The funding allowed continuation of the targeted winter support provided in
previous years. 
239

Page 240

4.4.2. As before, the criteria and distribution approach were reviewed to ensure support
reached the following groups. Winter Support Delivered Funding enabled a range of
practical and meaningful supports throughout the winter period, including:- 
 enhancement of the food larder in the Continuing Care Hub from November to
March
 crisis support for young people returning from custody or external placements
 provision of warm clothing through vouchers and supported shopping
 increased sessions for The Champions and other care-experienced young
people throughout winter 
4.5. School Meal Debt
4.5.1. Grant funding to support councils in the write off of school meal debt was received in
2024/2025 and to date has been used to write off over £0.200m of school meal debt
in line with the guidance.  This relates to school meal debt for 4,147 children.  Work
continues to support families in hardship and the introduction of school meals for
eligible children who are in receipt of Scottish Child Payment provides further support
to families. 
4.5.2. Education Resources and Facilities Services review school meal debt on a quarterly
basis and provision is made for further write off for families in financial hardship should
this be required.  The Council continues to provide a school meal for all children who
require one, even if they are unable to pay on the day. 
4.6. Schools Support
4.6.1. Education Resources remain dedicated to the principles of the South Lanarkshire
Council Cost of the School Day (CoSD) guidance.  As part of ongoing work to support
CoSD and deliver on our Strategic Equity Fund stretch aim for all schools to have a
CoSD policy in place, 20 schools were identified as having the strongest written
policies for implementation in their context during session 2025/2026. 
4.6.2. This included 18 primary schools and 2 secondary schools.  Several of the primary
schools also incorporated nursery classes.  Analysis work was carried out with 20
schools participating in individual follow up meetings. 
4.6.3. The purpose of the follow up meetings was to gather evidence of progress made in
implementation the school’s plan. 
4.6.4. Upon conclusion of the meetings the overarching aim is to collate
approaches/challenges and successes in reducing stigma and poverty-related barriers
to learning and produce a guidance document exemplifying effective approaches to
reducing the CoSD early in the 2026/2027 term. 
4.6.5. Schools involved have been extremely positive so far about this collective approach.
Consideration will be given as to how to continue to support our work on CoSD in a
more sustainable way with potentially some of the lead school reps taking on a
leadership role in ensuring further discussions take place in clusters/locality meetings
during the remainder of this term and throughout 2026/2027. 
4.8. Food Aid
4.8.1. There were seven food banks that made a return as part of the annual reporting for
year 2025/2026, down from the eight that reported in 2024/2025.  The 2025/2026
figures exclude Share Alike food bank which closed during the year. 
240

Page 241

4.8.2. Across the seven food banks 29,822 households were either referred to or attended
for assistance during 1 April 2025 and 31 March 2026.  The table below breaks down
this information to the locality level where possible:- 
Households referred on to or accessing Foodbanks 2024/2025 and 2025/2026 
Area/Locality  1st April 2024 and
31st March 2025
1st April 2025
and 31st March
2026
Change 
Clydesdale 2,589 2,592 +0.1%
Rutherglen/
Cambuslang
7,477 7,427 -0.7%
Hamilton, Larkhall 4,791 3,817 -20.3%
East Kilbride 15,511 15,986 +3.1%
Total 30,368 29,822 -1.8% 
4.8.3. While the household figures have reported a decrease, the foodbanks also provide
information on the number of people fed through emergency food parcels which is
reporting an increase, indicating more households with children in them have been
accessing food bank support. 
4.8.4. In total 57,305 people in South Lanarkshire were fed though emergency food parcels
during 1 April 2025 to 31 March 2026, an 11% increase compared to the 51,655
people receiving parcels in 2024/2025. 
4.8.5. Overall, 37,340 adults were fed through emergency food parcels between 1 April
2025 and 31 March 2026, an 8.9% increase compared to the 34,276 reported in
2024/2025.  It is worth noting that at the end of March 2025, this figure had reduced
in comparison with the previous year by 4% and is now on the rise again. 
4.8.6. The number of children being fed though emergency food parcels between 1 April
2025 and 31st March 2026 was 19,965, a 14.9% increase compared to 17,379
children receiving parcels in 2024/2025. 
4.8.7. Across all households accessing food banks in South Lanarkshire during the period
1 April 2025 and 31 March 2026, 54% of them attended the food banks in East
Kilbride.  This represented an increase in the locality share compared to the same
time period last year.  One of the reasons for the higher percentage of people and
households accessing the food banks in East Kilbride is that the access policy of the
East Kilbride foodbanks does not operate a referral system that restricts the number
of times a user can access. 
4.8.8. There were 71 organisations and public service providers across South Lanarkshire
that referred people onto the four local foodbanks that use a referral system during
2025/2026. 
4.8.9. Financial support was provided by the Council to the foodbanks following agreement
by the Council’s Executive Committee in February 2026. Payments totalling £0.040m
were made in 2025/2026 utilising an underspend in the Areas Grants budget from
2024/2025. 
241

Page 242

4.8.10. South Lanarkshire’s foodbanks continue to look at alternatives to emergency food
parcels through utilising cash first approaches to meet demand, with 586 retail
vouchers issued to clients to buy fresh food and vegetables between 1 April 2025 and
31 March 2026, a drop of 48% on the 1,116 vouchers distributed by the food banks
in 2024/2025.   
4.8.11. Help to clients with issues such as fuel/energy poverty also continued to be provided
by the local food banks with 931 fuel/energy vouchers dispensed between 1 April
2025 and 31 March 2026, a drop of 17% compared to the 1,116 vouchers issued
during 2024/2025. 
4.9. Citizens Advice Bureaux
4.9.1. Benefits remain the top area of advice, with debt, energy and finance support the
second and third biggest areas of advice respectively, with clients struggling to afford
energy debt and ongoing their liability making up the majority of enquiries. 
4.9.2. The value of benefits awarded for the 12 months to 31 March 2026 totalled £7.235m
with £1.370m of debt written off for clients.  Across South Lanarkshire Citizens Advice
Bureaux there has been another significant increase in demand for both benefit and
debt advice. 
4.9.3. The Citizens Advice Bureaux have sustained the increase to the outreach advice and
have continued to provide accessible advice services, which is available in local,
community venues.  This ensures the Citizens Advice Bureaux reach the most
vulnerable who would historically not access our main offices. 
4.9.4. Citizens Advice Bureaux and MMAS continue to work in close partnership,
complementing each other's strengths to ensure that residents receive timely access
to advice and support.  Both services work collaboratively to support Community
Hubs, make cross-referrals where appropriate, and ensure clients are directed to the
organisation best placed to meet their needs. 
4.9.5. This flexible partnership ensures that the strengths and capacity of both organisations
are utilised effectively, improving resilience across the advice sector and helping
residents access the right support at the right time. 
4.10. Social Security Scotland
4.10.1. Social Security Scotland is now delivering 15 different benefits.  The range of benefits
provide support for families, unpaid carers, disabled people, young people and
support for warmer homes. 
4.10.2. Anyone applying for Scottish benefits can access direct support from the Local
Delivery team.  The service is now fully operational in all 32 Scottish local authorities,
and support is being delivered to clients in various ways; home visits, outreach
venues within the local area and by phone or video. 
4.10.3. The Local Delivery team provides person-to-person support from trained staff.  The
team has a base in Brandon Gate, Hamilton. Client Support Advisers work from
outreach venues, client’s homes and a blend of office/home working.  Current
outreach venues are in Hamilton, Larkhall, East Kilbride, Cambuslang and Lanark. 
242

Page 243

4.10.4. Social Security Scotland provides a range of data in relation to the benefits paid to
South Lanarkshire on its website.  Since being introduced, 12,260 applications for
Adult Disability Payment have been approved. In total £420.0m has been paid (up to
31 January 2026).  At 31 December 2025, 19,395 children in South Lanarkshire are
benefitting from Scottish Child Payment.  A total of £90.1m has been paid.  To 31
March 2026 there has been 4,730 authorised new applications for Child Disability
Payment.  A total of £122.0m has been paid.  At 31 January 2026 there has been
1,560 authorised new applications for Pension Age Disability Payment.  A total of
£24.9m has been paid.  Further statistics can be found on the Social Security
Scotland website. 
4.11. NHS
4.11.1 Midwives, Health Visitors and Family Nurses work with families to help identify any
money worries and make referrals to Money Matters Advice Services.  In the period
April 2025 to March 2026, there were 188 referrals from these key staff groups,
leading to a client financial gain of £0.023m.  When including all NHS-linked referrals,
including those from Primary and Secondary care, the total number rises to 1,013
referrals and a total financial gain of £0.403m.  
4.11.2. From April 2025 to March 2026, 32 South Lanarkshire families received support from
the Family Support and Financial Inclusion - Royal Hospital for Children initiative with
a total financial gain of £0.105m.  In addition, families were supported with housing
and non-housing debt management to the amount of £0.078m. 
5. Outlook
5.1. Council services and organisations have provided an extensive range of support to
households during 2025/2026.  However, the cost of living remains high with prices
continuing to increase and energy costs forming a significant proportion of
household’s costs.  The impact of the war in the Middle East on the prices of everyday
essentials will negatively affect household finances well into 2026/2027. 
5.2. The Council and organisations will continue to provide support to households from
the wide range of services and budgets available. 
5.3. In 2026, a neurodiversity project has been launched with support from the Scottish
Government Child Poverty Accelerator Fund.  The project aims to increase early and
successful take-up of Child Disability Payment (CDP) and related benefits for families
whose children have Autism, Aspergers or other neurodivergent conditions.  It aims
to generate new evidence, improve access, and establish a model of specialist
support designed around the needs of neurodivergent children and their carers.  The
fund has provided £0.046m for the MMAS to meet the costs of an advisor for one
year. 
6. Employee Implications
6.1. There are no employee implications from the report with employees from many
different services engaged in providing cost of living support to residents.   
7. Financial Implications
7.1. There are no financial implications from the report, with the cost of support met from
existing budgets. 
8. Climate Change, Sustainability and Environmental Implications
8.1. There are no implications for climate change, sustainability or the environment in
terms of the information contained in this report.
243

Page 244

9. Risk and Other Implications
9.1. While a broad range of support was provided throughout 2025/2026 with a significant
level of financial resources, the actions outlined in the report are not expected to be
sufficient to fully mitigate the worst effects of the cost-of-living crisis experienced by
many households in South Lanarkshire.  This reflects the scale and depth of the crisis
and the need for significant input from other sectors such as governments and the
energy sector. 
10. Integrated Impact Assessment and Consultation Requirements
10.1. This report does not introduce a new policy, function or strategy or recommend a
change to an existing policy, function or strategy and, therefore, no impact assessment
is required. 
10.2. There is also no requirement to undertake any consultation in terms of the information
contained in this report. 
Jackie Taylor
Executive Director (Finance and Corporate Resources) 
23 July 2026 
Link(s) to Councils Values/Priorities/Outcomes
 Accountable, effective, efficient and transparent 
Previous References
 Executive Committee – 3 December 2025 
List of Background Papers
 None 
Contact for Further Information
If you would like further information, please contact:- 
Craig Fergusson, Head of Finance (Transactions), Finance and Corporate Resources
Tel: 01698 454951
Email:  craig.fergusson@southlanarkshire.gov.uk
244

Page 245

Report
Agenda Item 
Report to: Executive Committee
Date of Meeting: 19 August 2026
Report by: Executive Director (Finance and Corporate Resources)  
Subject:    Council Complaints Report: SPSO Annual Overview
2025/2026 
1. Purpose of Report
1.1. The purpose of the report is to:- 
 provide a report on the performance of the Council’s handling of complaints
received during the period 1 April 2025 to 31 March 2026
 provide customer feedback on complaint handling (Appendix 2) 
2. Recommendation(s)
2.1. The Executive Committee is asked to approve the following recommendation(s):- 
(1) that complaints performance and areas highlighted for improvement be noted.
[1recs]
3. Background
3.1. The Council is required to monitor and assess complaints handling performance to
provide assurance in relation to how it has performed, to facilitate continuous
improvement, and to assist in benchmarking performance between local authorities.
The performance indicators for the Scottish Public Sector Ombudsman (SPSO) model
complaints handling procedure (MCHP) are the minimum requirements for a local
authority to self-assess and report on performance, and to undertake benchmarking
activities.  
3.2. Compliance with the MCHP is monitored by the SPSO on an annual and quarterly
basis. 
4. Overview
4.1. Quarterly Council complaints reports are produced, and an annual report is shared
with the elected members. The Council continues to work to improve its performance
and learn from complaints to improve its services. 
4.2. The SPSO performance indicators which the Council is required to report against are: 
Indicator 1 -  complaints received per 1,000 of population 
Indicator 2 -  % of closed complaints at each stage
Indicator 3 -  average time in working days to respond to complaints at each stage 
Indicator 4 -  % of complaints upheld, not upheld, and resolved  
14
245

Page 246

5. Indicator Performance
5.1. The latest 2022 Census information released in September 2023 estimates the
population of South Lanarkshire to be 327,200. Between 1 April 2025 and 31 March
2026, the Council received 1,719 complaints. This is equal to 5 complaints per 1,000
people. In 2024/25, the Scottish local authority average was 12 complaints per 1,000
people. 
5.2. Table 1 shows complaints received between 1 April 2025 and 31 March 2026. This
data relates to complaints received, not complaint outcomes. Over the last three
years, the data shows: 
 2023/24 and 2024/25: a 17% rise in complaints received
 2024/25 and 2025/26: a 32% rise in complaints received 
Table 1: total *number of complaints received – 1 April 2025 to 31 March 2026
Resource Year
2023/24
Year
2024/25
Year
2025/26
% Change
in last year
Community and
Enterprise
320 442 626 42% (184)
Education 269 253 397 57% (144)
Finance and Corporate 110 122 132 8% (10)
Housing and Technical 174 198 303 53% (105)
Social Work 239 283 261 -8% (-22)
Total 1112 1298 1719 32% (421) 
*Figures for the total number of complaints received do not include complaints that
were categorised as withdrawn or created in error, which totalled 24 for 2025/26. 
5.3. Published annual SPSO statistical data, showed complaints received by SPSO
covering the breadth of the public sector in Scotland, saw a rise from 5,021
complaints received in 2024/25 to 6,588 in 2025/56, a 31% increase.  This trend is
also reflected in the Council complaints received which has increased in 2025/26 as
detailed in Table 1.  Discussions at Society Personnel and Development Scotland
indicate that complaints numbers are rising across all local authorities.  
5.4. The increases in complaints were across four resources, as detailed in the table
above, with Social Work having a decrease in complaints. Data showed distinct
drivers within each Resource, rather than one overall pattern organisation wide. 
5.5. Data from Resources shows that improved reporting routes, more consistent
recording and stronger quality assurance have increased the visibility of complaints
that may previously have been managed informally.  Wider access to the complaints
process, a stronger focus on transparency and service user voice, and changes to
data capture, including child involvement, have also contributed to higher reported
numbers. 
246

Page 247

There is also evidence of increased repeat and escalated complaints, alongside a
notable impact from AI-enabled submissions which can amplify both volume and
complexity. More detailed AI-enabled complaints require additional investigation,
greater coordination across service areas and  are likely to take longer to resolve,
increasing the likelihood that customers remain dissatisfied and request escalation to
Stage 2. This is reflected in the rise in complaints escalated from Stage 1 to Stage 2,
which increased from 174 in 2024/25 to 262 in 2025/26. 
5.6. The SPSO Complaints Handling Procedure states that Stage 1 complaints are
responded to within 5 working days, and Stage 2 within 20 working days. 
The average time in working days to respond to complaints (SPSO indicator 3), are
detailed by Resource at Appendix 1, table 5. For the period 2025/2026, the average
number of days to respond at Stage 1 is 4 working days and Stage 2 is 13 working
days. 
5.7. Appendix 1, Table 4 shows that Social Work dealt with Stage 1 complaints within an
average of 4 working days and dealt with Stage 2 complaints within an average of 19
working days. 
5.8. The data provided at Appendix 1, Table 5 is a comparison of response rates over the
last three years and shows:- 
 the average time in working days to respond to complaints at Stage 1 is being
met consistently and the average response rate is 5 days, which meets the SPSO
performance indicator
 the timescale for Stage 2 responses continues to meet the SPSO performance
indicator, and the Council’s performance over the last 3-years remains consistent
with the average time rate being 13 working days
 the timescale to respond to complaints after escalation is also being achieved
consistently with the average response rate being 13 days over the last 3-years,
which meets the SPSO performance indicator 
5.9. This year, 262 complaints were escalated from Stage 1 to Stage 2 compared to 174
in 2024/25. This represents an increase of 50.6%. 
It should be noted that Resources have the opportunity to place complaints directly at
Stage 2 if it is appropriate rather than escalating from Stage 1 to Stage 2, as the
purpose of the two-stage procedure is to handle complaints effectively at the first time
of asking and not to have multiple attempts at resolving complaints. Where a complaint
is further escalated to the SPSO they are interested in whether the Council has
followed the procedure correctly and appropriately. 
5.10. The data in Appendix 1, Tables 6, 7 and 8 is referred to for this section of the report
and shows the number of complaints which were upheld, not upheld or resolved as a
percentage of closed complaints at Stage 1, Stage 2 and Stage 2 escalated. In
response to SPSO Indicator 4:- 
2025/26 complaints upheld: 
 485 complaints were upheld (28%)
 868 complaints were not upheld (51%)
 360 complaints were resolved (21%)  
247

Page 248

The number of complaints upheld varies across Resources. A review of the upheld
complaints indicated that these were due to the knowledge and experience of
employees, gaps in communication and alignment to processes.  Further support and
training is being provided to employees in these services.  As part of the ongoing
complaints process review referenced in section 4.3, further analysis of the increase
in complaints and the rise in upheld complaints is taking place. 
5.11. Stage 1 data in Appendix 1 shows that 45% of all stage 1 complaints were not upheld,
with 26% being resolved prior to categorisation, and 29% being upheld. 
5.12. The data shows that when stage 1 complaints were escalated to stage 2, due to the
complainant being dissatisfied with the stage 1 response, 72% of the complaints
remained unchanged as not upheld.  On average, stage 1 decisions were changed to
upheld in 24% of cases and 4% were resolved. 
5.13. Stage 2 data in Appendix 1 shows that 65% of complaints received directly at stage
2 were not upheld, 33% were upheld and the remaining 2% were resolved. 
5.14. The data in Appendix 1 shows the number of complaints which were upheld, not
upheld or resolved as a percentage of closed complaints at Stage 1, Stage 2 and
Stage 2 escalated in 2025/26 by Resource. 
6. Customer Satisfaction
6.1. The Council asks customers who have used the complaints procedure for feedback.
This helps the council understand customer experience and identify service
improvements. 
6.2. As in previous years, the survey was carried out by email. Customers who agreed to
take part were sent a link to the survey. This is in line with the complaints handling
procedure. 
6.3. This year, 57 respondents completed the customer feedback survey compared to 66
in 2024/25. Appendix 2 shows the results of the customer feedback survey for the
period from 1 April 2025 to 31 March 2026. Not all 57 respondents answered all the
questions within the survey. 
6.4. The learning from the Customer Survey has been incorporated into the Complaints
Handling Procedure (CHP) Review and any improvement actions will be included in
the outputs of this process. 
7. National Issues and SPSO Updates
7.1. The SPSO publish their annual statistics on their website. These detail the enquiries
and complaints they have received and determined in the past year. The full statistics
are available on the SPSO website at Statistics 2025-26 | SPSO 
8. Learning from Complaints
8.1. The SPSO requires local authorities to learn from complaints by identifying the root
cause of the complaint, taking action to reduce the risk of recurrence, and
systematically reviewing complaints to improve service delivery.  Resources are
responsible for analysing complaints data and reviewing individual complaint
performance.  
248

Page 249

9. Employee Implications
9.1. Employees are key to effective service delivery and in trying to resolve complaints. 
Training is available to all employees through a range of methods including eLearning,
good practice and a range of information for local authorities on the SPSO website. 
10. Financial Implications
10.1. There are no additional financial implications of this report, and the cost of the MCHP
is incorporated into current budgets. 
11. Climate Change, Sustainability and Environmental Implications
11.1. There are no climate change, sustainability or environmental associated with this
report. 
12. Risk and Other Implications
12.1. There is a risk of damage to the Council’s reputation. If complaints are not handled
effectively, there can be an adverse effect on the public perception of the Council
which can lead to a lack of trust in the services provided. 
13. Integrated Impact Assessment and Consultation Requirements
13.1. Council Resources have been consulted on the data required for this report. 
13.2. There is no requirement to carry out an impact assessment in relation to the proposals
within this report. However, the learning from complaints is used to ensure Council
services are accessible to all members of the community and, wherever possible, to
prevent discrimination, harassment, or victimisation from occurring. 
Jackie Taylor
Executive Director (Finance and Corporate Resources) 
27 July 2026 
Link(s) to Council Values/Priorities/Outcomes
 Accountable, effective, efficient, and transparent
 Fair, open, and sustainable
 Ambitious, self-aware, and improving 
Previous References
 None 
List of Background Papers
 Monitoring information provided by each Resource.
 Complaints handling customer feedback report. 
List of Appendices 
 Appendix 1 – Scottish Public Services Ombudsman’s Performance indicators from 1 April
2025 to 31 March 2026.
 Appendix 2 - Overview of responses for the complaints handling customer feedback survey
from 1 April 2025 to 31 March 2026.
249

Page 250

Contact for Further Information
If you wish to inspect the background papers or want further information, please contact:- 
Michelle Milne, Head of Personnel Services
Ext:  4330 (Tel:  01698 454330)
Email: michelle.milne@southlanarkshire.gov.uk 
250

Page 251

Appendix 1 
SPSO performance indicators (KPI’s) from 1 April 2025 to 31 March 2026 
Complaints closed at stage 1 and stage 2 as a percentage of all complaints closed
(SPSO indicator 2). Actual numerical figure shown in brackets. 
The term “closed” refers to a complaint that has had a response sent to the  
customer and at the time no further action is required (regardless at which stage it 
is processed and whether any further escalation takes place). 
Table 2: total number of complaints closed – 1 April 2025 to 31 March 2026
Resource (total no. closed) % closed at
Stage 1
% closed at
Stage 2
% closed at
Stage 2 -
escalated from
Stage 1 
Community and Enterprise
(625)
83% (518) 5% (33) 12% (74)
Education (397) 64% (253) 14% (58) 22% (86)
Finance and Corporate (146) 82% (120) 2% (3) 16% (23)
Housing and Technical (293) 79% (232) 2% (6) 19% (55)
Social Work (252) 84% (213) 6% (15) 10% (24)
Total (1713) 78% (1336) 7% (115) 15% (262) 
Table 3: three-year comparison.  Number of complaints closed at each stage. 
% closed at
Stage 1
%closed at
Stage 2
%closed at
Stage 2 –
escalated from
Stage 1
Total - 2025/26 (1713) 78% (1336) 7% (115) 15% (262)
Total - 2024/25 (1286) 81% (1038) 6% (74) 13% (174)
Total - 2023/24 (1096) 79% (865) 7% (82) 14% (149) 
251

Page 252

Average time in working days for a full response to complaints at each stage
(working days) (SPSO indicator 3) 
Table 4: average response times in working days 
Resource  Average time in
working days
to respond to
complaints at
stage one (5-
day resolution
target) 
Average time in
working days
to respond to
complaints at
stage two (20-
day resolution
target)
Average time in
working days
to respond to
complaints
after escalation
(20-day
resolution
target)
Community and Enterprise  4 15 14
Education  5 17 15
Finance and Corporate  2 4 5
Housing and Technical  4 11 13
Social Work  4 19 19
Total Average Times 4 13 13 
Table 5: three-year comparison 
Average time in working days for a full response to complaints at each stage. 
Average times Stage 1 Stage 2 Escalated
Total - 2025/26 4 13 13
Total - 2024/25 5 14 13
Total - 2023/24 5 13 14 
Complaints upheld/not upheld/resolved at each stage as a percentage of complaints
closed in full at each stage, (SPSO indicator 4). Actual numerical figure shown in
brackets. (See table 2 for complaints closed figures). 
Upheld – failings found
Not upheld – no failings found
Resolved – remedial action taken prior to establishing if upheld or not upheld.  
252

Page 253

Complaints upheld/not upheld/resolved at each stage as a percentage of complaints closed
in full at each stage in this period are shown in Tables 6, 7 and 8. 
Table 6: complaints upheld/not upheld/resolved at Stage 1 
Resource (total no.
closed at Stage 1)
% upheld at Stage
1
% not upheld at
Stage 1
% resolved at
Stage 1
Community and
Enterprise (518)
31% (158) 34% (177) 35% (183)
Education (253) 23% (58) 62% (156) 15% (39)
Finance and
Corporate (120) 
23% (28) 57% (68) 20% (24)
Housing and
Technical (232)
40% (92) 52% (122) 8% (18)
Social Work (213) 23% (49) 38% (81) 39% (83)
Total (1336) 29% (385) 45% (604) 26% (347) 
Table 7: complaints upheld/not upheld/resolved at Stage 2 
Resource (total no.
closed as Stage 2)
% upheld at Stage
2
% not upheld at
Stage 2
% resolved at
Stage 2
Community and
Enterprise (33)
30% (10) 67% (22) 3% (1)
Education (58) 41% (24) 59% (34) Nil
Finance and
Corporate (3) 
33% (1) 67% (2) Nil
Housing and
Technical (6)
17% (1) 67% (4) 16% (1)
Social Work (15) 13% (2) 87% (13) Nil
Total (115) 33% (38) 65% (75) 2% (2) 
Table 8: escalated complaints upheld/not upheld/resolved 
Resource  % of escalated
complaints upheld
% of escalated
complaints not
upheld
% of escalated
complaints
resolved
Community and
Enterprise (74)
16% (12) 78% (58) 6% (4)
Education (86) 33% (28) 67% (58) Nil
Finance and
Corporate (23)
22% (5) 78% (18) Nil
Housing and
Technical (55)
14% (8) 73% (40) 13% (7)
Social Work (24) 37% (9) 63% (15) Nil
Total (262) 24% (62) 72% (189) 4% (11)  
253

Page 254

Appendix 2 
Complaints handling customer feedback survey
Overview of responses from 1 April 2025 to 31 March 2026 
Note: data based on 57 respondents 
Customers were asked to answer based on the complaints process rather than the outcome of
the complaint.
Question Answer 
Strongly
disagree
Disagree Neutral Agree Strongly
Agree
Information about the
complaints’ procedure
was easily accessible.
19% 24% 23% 25% 9%
I found it easy to make
my complaint.
17% 21% 21% 32% 9%
I was happy that the
Investigating Officer
fully understood my
complaint.
27% 23% 14% 16% 20%
I was given the
opportunity to fully
explain my complaint.
32% 10% 16% 25% 17%
The points of my
complaint were
identified and
responded to.
41% 11% 12% 20% 16%
The response to my
complaint was easy to
understand.
25% 13% 22% 22% 18%
Overall, I was satisfied
with the handling of my
complaint.
42% 23% 11% 13% 11%
I was clearly told what
the next stage of the
complaints process
was to me.
37% 13% 16% 16% 18%
I was told if the
response was going to
take longer than the
timescales (five
working days at stage
1 and 20 working days
at stage 2). 
(38% was not
applicable)
23% 14% 11% 9% 5%
254

Page 255

Report
Agenda Item 
Report to: Executive Committee
Date of Meeting: 19 August 2026
Report by: Chief Executive  
Subject: Resource Plans and Connect Reporting 2026/2027 
1. Purpose of Report
1.1. The purpose of the report is to:-
[purpose]
 provide the Committee with the Resource Plans for 2026/2027, for noting,
together with an indication of how the Council Plan, Connect, will be reported in
the 2026/2027 financial year
[1purpose]
2. Recommendation(s)
2.1. The Committee is asked to approve the following recommendation(s):-
[]
(1) that the Resource Plans 2026/2027, prepared in line with the corporate
Guidance, be noted; and
(2) that the reporting intention in relation to Connect, summarised at Section 5 of
this report, be noted. 
3. Background
3.1. This report presents the suite of Resource Plans 2026/2027. These plans  have been
submitted to the relevant Resource Committee for approval and can be accessed at
the following link: Plans and progress - South Lanarkshire Council. This report also
provides an indication of how the Council Plan, Connect, will be reported in the
2026/2027 financial year. 
4. Resource Planning Process 2026/2027
4.1. The Resource Plans for 2026/2027 were prepared in line with corporate Resource
Planning guidance and template. 
4.2. As part of the Resource Planning process, Resources undertake a horizon-scanning
and situational-awareness exercise covering Social Change, Legislation and Policies;
Areas for Improvement, including Local Government Benchmarking Framework
(LGBF), customer views and external inspection results; and other triggers for action
such as top risks. 
4.3. From this exercise, a maximum of ten topics are selected as key areas of focus for
inclusion and development in the Resource Plans. The key areas are shown in table
1 below and are provided to give Committee an overview of the most significant
Resource Plan issues identified for 2026/2027. 
15
255

Page 256

Table 1: Key areas of focus in Resource Plans 2026/2027
CER 1. Local Development Plan (LDP)
2. Tackling inequality and poverty
3. Economic Development and Renewal
4. External funding
5. Glasgow City Region City Deal
6. Deliver effective Employability Services to support Individuals and
Business
7. Sustainable Development and Climate Change (SDCC)
8. Circular Economy
9. Local Transport Strategy (LTS)
10. Health and Wellbeing
11. Free school meals roll out
12. Legislative and Policy Changes
EDR 1. Learning, teaching and assessment
2. Developing our curriculum
3. Wellbeing, inclusion and equity
4.   Leadership, self-evaluation and a connected 3-18 support system
FCR 1. Tackling inequality and poverty
2. Financial Strategy
3. Involving our Communities
4. Strategic Workforce planning
5. Strategic digital developments
6. Sustainable development and climate change
7. Continued development of the Council Transformation Programme
8. Customer engagement
9. Digital transformation
10. Strategic planning and Best Value
11. Money matters advice services
HTR 1. Tackling inequality and poverty
2. Housing to 2040
3. Financial considerations
4. Severe pressure on Homelessness services
5. Continuing to improve the supply and availability of housing
6. Provision of services to Gypsy/Travellers
7. Health and social care
8. Development of integrated housing and property management
system
9. Health and safety
10. Sustainable development and climate change
11. Refugee re-settlement programme and asylum dispersal
SWR 1. Delivering safe, high quality and sustainable statutory services 
2. Child poverty and reducing inequalities 
3. Children and Family Services – Care Close to Home
4. Adult Social Work and Integrated Community Health and Social
Care
5. Care at home and supporting independence
6. Hospital discharge, flow and system performance
7. Justice Social Work and public protection
8. Commissioning, Assurance and Best Value
9. Workforce sustainability, capability and leadership
256

Page 257

10. Digital transformation and enabling infrastructure
11. Responding to National Reform and future change
12. Sustainable Development and Climate Change 
4.4. Tackling inequality and poverty features as one of the main challenges in the year
ahead in most Resource Plans. Sustainability and climate change features strongly,
as does financial, budget and efficiency considerations. Other topics listed across a
number of Plans include, health and wellbeing, workforce planning and engagement
with communities 
5. Resource Plans – Outcomes, Measures and the Link to Connect
5.1. Resources have used the six Connect outcomes to generate their own Resource
outcomes, supported by a range of actions and measures.  Recognising that the
Council continually aims to improve and ensure effective and efficient use of
resources, additional actions and measures have been developed under the heading
Delivering the Plan and achieving Best Value. 
5.2. Table 2 below shows the number of measures from each Resource Plan selected to
be reported against Connect. The figures for 2026/2027 are based on the Resource
Plans 2026/2027. 
Table 2: Number of measures from Resource Plans selected to be reported
against Connect 
Number of measures 
2024-25 2025-26 2026-27
Community and Enterprise 53 60 63
Education 44 52 40
Finance and Corporate 37 41 40
Housing and Technical 70 88 60
Social Work  27 24 21 
TOTAL (Resource Plans) 231 265 224    
Council Plan, Connect 61 66 60 
(Note – 2026/2027 figures correct per Resource Plans as at May 2026; the final
number of measures may vary following internal verifications and cross-checks.) 
5.3. As part of the performance reporting arrangements Connect progress reports will be
presented to the Performance and Review Scrutiny Forum for monitoring at the mid-
year point (Quarter 2) and at the end of the financial year (Quarter 4). 
6. Next Steps
6.1. Committee is asked to note the suite of Resource Plans 2026/2027, and that progress
reports will be taken to the appropriate Resource Committees for monitoring at Quarter
2 and Quarter 4. Following Committee approval, summaries of these reports are now
uploaded as web content onto the Council’s website, also at Plans and progress -
South Lanarkshire Council. 
7. Employee Implications
7.1. There are no direct employee implications. 
8. Financial Implications
8.1. There are no direct financial implications. 
257

Page 258

9. Climate Change, Sustainability and Environmental Implications
9.1. There are no direct climate change, sustainability and natural environment implications
arising from this report. 
9.2. The Council acknowledges the serious and immediate threat of climate change and is
committed to accelerating the pace of action in response to the climate emergency
and in Scotland’s transition to a net-zero and climate resilient society and economy.
All Resource Plans have recognised sustainable development and climate change as
a key area of focus for 2026/2027. 
10. Other Implications
10.1. Considering the detail of the report and identifying actions as appropriate contribute
towards effective risk management. 
11. Integrated Impact Assessment and Consultation Requirements
11.1. This report does not introduce a new policy, function or strategy or recommend a
change to an existing policy, function or strategy and, therefore, no impact assessment
is required. 
11.2. There is also no requirement to undertake any consultation in terms of the information
contained in this report. 
Paul Manning
Chief Executive 
16 July 2026 
Link(s) to Council Values/Priorities/Outcomes
 Accountable, effective, efficient and transparent
 Ambitious, self-aware and improving 
Previous References
 Community and Enterprise Resource Committee – 2 June 2026
 Housing and Technical Resources Committee – 3 June 2026
 Education Resources Committee – 30 June 2026
 Social Work Resources – 1 July 2026
 Finance and Corporate Resources Committee – 1 July 2026 
List of Background Papers
 None 
Contact for Further Information
If you would like to inspect the background papers or want further information, please
contact:- 
Tom Little, Head of Communications and Strategy
Ext:  4904  (Tel:  01698.454904)
E-mail:  Tom.Little@southlanarkshire.gov.uk 