Democracy Spraffa

Agenda Document Pack - Community and Enterprise Resources Committee - 14/03/2023

South Lanarkshire Council · 14 March 2023
Back to Community and Enterprise Resources Committee — 14 March 2023 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

Council Offices, Almada Street        
Hamilton, ML3 0AA 
Monday, 06 March 2023 
Dear Councillor 
Community and Enterprise Resources Committee 
The Members listed below are requested to attend a meeting of the above Committee to be
held as follows:- 
Date:  Tuesday, 14 March 2023
Time:  14:00
Venue: Hybrid - Council Chamber, Council Offices, Almada Street, Hamilton,
ML3 0AA 
The business to be considered at the meeting is listed overleaf. 
Yours sincerely 
Cleland Sneddon
Chief Executive 
Members 
Robert Brown (Chair), Maureen Devlin (Depute Chair), Joe Fagan (ex officio), John
Anderson, Ralph Barker, Walter Brogan, Andy Carmichael, Maureen Chalmers, Gerry
Convery, Poppy Corbett, Andrea Cowan, Margaret Cowie, Colin Dewar, Gladys Ferguson-
Miller, Ross Gowland, Graeme Horne, Cal Johnston-Dempsey, Martin Lennon, Richard
Lockhart, Hugh Macdonald, Ian McAllan, Kenny McCreary, Davie McLachlan, Carol
Nugent, Helen Toner, David Watson 
Substitutes
Alex Allison, Ross Clark, Margaret Cooper, Allan Falconer, Alistair Fulton, Lynsey Hamilton,
Ross Lambie, Lesley McDonald, Elaine McDougall, Mark McGeever, Richard Nelson,
Graham Scott, David Shearer 
1

Page 2

BUSINESS 
1 Declaration of Interests 
2 Minutes of Previous Meeting
Minutes of the meeting of the Community and Enterprise Resources
Committee held on 13 December 2022 submitted for approval as a
correct record.  (Copy attached) 
5 - 12 
Monitoring Item(s) 
3 Community and Enterprise Resources - Revenue Budget Monitoring
2022/2023
Joint report dated 8 February 2023 by the Executive Directors (Finance
and Corporate Resources) and (Community and Enterprise Resources). 
(Copy attached) 
13 - 22 
4 Community and Enterprise Resources - Capital Budget Monitoring
2022/2023
Joint report dated 22 February 2023 by the Executive Directors (Finance
and Corporate Resources) and (Community and Enterprise Resources). 
(Copy attached) 
23 - 26 
5 Community and Enterprise Resources – Workforce Monitoring – October
to December 2022
Joint report dated 2 February 2023 by the Executive Directors (Finance
and Corporate Resources) and (Community and Enterprise Resources). 
(Copy attached) 
27 - 34 
Item(s) for Decision 
6 Revocation of Lanark Air Quality Management Area – South Lanarkshire
Report dated 22 February 2023 by the Executive Director (Community
and Enterprise Resources).  (Copy attached) 
35 - 40 
7 Zero Carbon Indoor Multi Sports Facility Proposal at Strathaven Rugby
Club
Report dated 22 February 2023 by the Executive Director (Community
and Enterprise Resources).  (Copy attached) 
41 - 46 
8 Ash Dieback Disease Programme – Arboriculture Operatives (Trainee)
Joint report dated 24 February 2023 by the Executive Directors
(Community and Enterprise Resources) and (Finance and Corporate
Resources).  (Copy attached) 
47 - 50 
Item(s) for Noting 
9 Community and Enterprise Resource Plan - Quarter 2 Progress Report
2022/2023
Report dated 21 February 2023 by the Executive Director (Community
and Enterprise Resources).  (Copy attached) 
51 - 76 
2

Page 3

Urgent Business 
10  Urgent Business
Any other items of business which the Chair decides are urgent. 
For further information, please contact:-
Clerk Name: Elizabeth-Anne McGonigle
Clerk Telephone: 07385 403101
Clerk Email: elizabeth-anne.mcgonigle@southlanarkshire.gov.uk 
3

Page 4

4

Page 5

COMMUNITY AND ENTERPRISE RESOURCES COMMITTEE 
Minutes of meeting held via Confero and in the Council Chamber, Council Offices, Almada Street,
Hamilton on 13 December 2022 
Chair:
Councillor Robert Brown 
Councillors Present:
Councillor John Anderson, Councillor Ralph Barker, Councillor Walter Brogan, Councillor Maureen
Chalmers, Councillor Ross Clark (substitute for Councillor Graeme Horne), Councillor Gerry
Convery, Councillor Poppy Corbett, Councillor Andrea Cowan, Councillor Margaret Cowie,
Councillor Maureen Devlin (Depute), Councillor Colin Dewar, Councillor Gladys Ferguson-Miller,
Councillor Ross Gowland, Councillor Cal Johnston-Dempsey, Councillor Martin Lennon, Councillor
Richard Lockhart, Councillor Ian McAllan, Councillor Kenny McCreary, Councillor Lesley McDonald
(substitute for Councillor Andy Carmichael), Councillor Davie McLachlan, Councillor Carol Nugent,
Councillor David Shearer (substitute for Councillor Hugh Macdonald), Councillor Helen Toner,
Councillor David Watson 
Councillors' Apologies:
Councillor Andy Carmichael, Councillor Joe Fagan, Councillor Graeme Horne, Councillor Hugh
Macdonald 
Attending:
Community and Enterprise Resources
D Booth, Executive Director; K Carr, Head of Facilities, Waste and Grounds Services; A Goldie,
Facility Services Manager; C Park, Head of Roads, Transportation and Fleet Services; L Sprowl,
Development Officer
Finance and Corporate Resources
N Docherty, Administration Assistant; L Harvey, Finance Manager; E Maxwell, Human Resources
Business Partner; P MacRae, Administration Adviser; L O’Hagan, Finance Manager (Strategy); M M
Wilson, Legal Services Manager 
1 Declaration of Interests 
No interests were declared. 
2 Minutes of Previous Meeting 
The minutes of the meeting of the Community and Enterprise Resources Committee held on 4
October 2022 were submitted for approval as a correct record. 
In response to a member’s question, the Executive Director provided an update on the status of
and recruitment to the posts referred to in items 7 and 8 of the minutes. 
The Committee decided: that the minutes be approved as a correct record. 
3 Community and Enterprise Resources - Revenue Budget Monitoring 2022/2023 
A joint report dated 16 November 2022 by the Executive Directors (Finance and Corporate
Resources) and (Community and Enterprise Resources) was submitted comparing actual
expenditure at 4 November 2022 against budgeted expenditure for 2022/2023 for Community
and Enterprise Resources.
2
5

Page 6

At 4 November 2022, there was an overspend of £0.056 million against the phased budget. 
Details were also provided on proposed budget virements in respect of Community and
Enterprise Resources to realign budgets. 
The Committee decided: 
(1) that the overspend on the Community and Enterprise Resources’ revenue budget of
£0.056 million as at 4 November 2022, as detailed in Appendix A of the report, be noted;
and 
(2) that the budget virements, as detailed in appendices B to F of the report, be approved. 
[Reference: Minutes of 4 October 2022 (Paragraph 3)] 
4 Community and Enterprise Resources - Capital Budget Monitoring 2022/2023 
A joint report dated 23 November 2022 by the Executive Directors (Finance and Corporate
Resources) and (Community and Enterprise Resources) was submitted advising of progress on
the Community and Enterprise Resources’ Capital Programme 2022/2023 and summarising the
expenditure position at 4 November 2022. 
The revised capital programme for 2022/2023, as agreed at the meetings of the Executive
Committee held on 2 and 30 November 2022, amounted to £48.270 million, a net decrease of
£16.270 million and, at 4 November 2022, expenditure was £16.292 million. 
The Committee decided: that the Community and Enterprise Resources’ Capital
Programme of £48.270 million, and expenditure to date of
£16.292 million, be noted. 
[Reference: Minutes of 4 October 2022 (Paragraph 4)] 
5 Community and Enterprise Resources - Workforce Monitoring – August and
September 2022 
A joint report dated 10 November 2022 by the Executive Directors (Finance and Corporate
Resources) and (Community and Enterprise Resources) was submitted on the following
employee information for Community and Enterprise Resources for the period August and
September 2022:- 
 attendance statistics
 occupational health statistics
 accident/incident statistics
 disciplinary hearings, grievances and Dignity at Work cases
 analysis of leavers and exit interviews
 staffing watch as at 10 September 2022 
The Committee decided: that the report be noted. 
[Reference: Minutes of 4 October 2022 (Paragraph 5)] 
6

Page 7

6 Update of the Community and Enterprise Resources’ Risk Register and Risk
Control Plan
A report dated 21 November 2022 by the Executive Director (Community and Enterprise
Resources) was submitted providing an update on Community and Enterprise Resources’ Risk
Register and Risk Control Actions. 
The risks were scored in accordance with the Council’s scoring mechanism which scored risks
based on likelihood and impact of risk.  This resulted in risks being scored between 1 to 25 (low
to very high).  Risks were scored on their inherent risk (risk if nothing was done) and their
residual risk (risk after applying controls).  The risk scoring matrix was attached at Appendix 1 to
the report. 
The Risk Register had been developed and was monitored on an ongoing basis to add any new
risks and to review the scores of existing risks.  The main changes to the Community and
Enterprise Resources’ register were as follows:- 
 the addition of the following 3 new top risks -
 inability of the Council to support households significantly impacted by the cost of
living crisis, resulting in increasing levels of poverty, debt and damage to health
 failure to deliver the outcomes of the Community Wealth Building Strategy
 failure to achieve the Council Plan
 rescoring of damage caused by Ash Dieback disease as a high risk and re-categorisation
as an ‘all service’ risk due to the potential impact on other Services
 removal of the ‘EU Exit’ risk as this was no longer considered a significant issue for the
Resource 
Risks scored 15 to 25 were considered very high and risks scored 8 to 12 were considered high
risks.  The top risks identified for the Resource were detailed in Appendix 2 to the report. 
Comparisons of risk scores for 2021 and 2022 were detailed in Appendix 3 to the report. 
The Committee decided: 
(1) that the current position with regard to the Community and Enterprise Resources’ Risk
Register be noted; and 
(2) that it be noted that any outstanding Risk Control Actions identified during the year would
be progressed by relevant officers. 
[Reference:  Minutes of the Executive Committee of 28 September 2021 (Paragraph 11)] 
7 South Lanarkshire Draft Tourism Strategy
A report dated 24 November 2022 by the Executive Director (Community and Enterprise
Resources) was submitted on the South Lanarkshire Draft Tourism Strategy. 
As part of the 2021/2022 Revenue Budget, members had approved a sum of £3 million towards
economic recovery under the heading “Get South Lanarkshire Working”.  Members’ ambitions
for the £3 million fell under the following 3 headings:- 
 Social Enterprise and Business Support
 Locate in South Lanarkshire
 Tourism Co-operative and Strategy
7

Page 8

£0.5 million of the funding had been allocated to a South Lanarkshire Tourism Strategy and the
potential creation of a Tourism Co-operative body. 
A Tourism Strategy and associated Action Plan, attached as Appendix 1, to the report had been
drafted to take account of a rapidly changing sector at international, national and local levels. 
The draft Tourism Strategy had been shared with partners, stakeholders and members of the
public as part of a consultation process and comments received had helped define the current
document. 
It was intended that the Strategy would:- 
 evolve to ensure that all sectors of the South Lanarkshire tourism industry had their say in
shaping the Strategy and associated Action Plan
 help the tourism sector recover, increase the value of the tourism sector and enhance the
benefits of tourism across South Lanarkshire 
Details were given on the various sections contained in the Strategy. 
If approved, the Strategy would be published on the Council’s website.  Officers would continue
to engage with partners and businesses to provide support and advocate the creation of a
sustainable, collaborative industry body to co-ordinate actions and deliver the Strategy.  It was
proposed that, during the implementation stage, annual updates measuring the success of the
Strategy and Action Plan would be submitted to the relevant Committee.  In response to a
member’s question, officers advised that, where appropriate, brief updates could be submitted to
Committee on a more regular basis. 
Officers responded to members’ questions on various aspects of the report. 
The Committee decided: that the draft Tourism Strategy and Action Plan be
approved. 
8 Scottish Government 5 Year Play Investment Programme
A report dated 21 November 2022 by the Executive Director (Community and Enterprise
Resources) was submitted on work undertaken to date on the Scottish Government’s 5 Year
Play Area Investment Programme and proposing a strategic, place based approach to allocating
funding from the programme. 
The Scottish Government had launched a £60 million fund for the renewal of play parks in
Scotland to allow children access to high quality outdoor play in their own communities.  In
2021/2022 and 2022/2023, £10 million of funding was distributed across councils, with the
Council’s share totalling £594,000.  The Scottish Government had now confirmed the full
allocation of which South Lanarkshire would receive a total of £3.58 million up to 2025/2026. 
The Scottish Government had originally intended that all play areas in Scotland would be
renewed and transformed, however, this would not be achievable in terms of the proposed
funding package.  Due to the shortfall in funding, the Scottish Government had agreed that
councils could identify their own investment priorities.
8

Page 9

An exercise to identify potential costs of bringing all of the Council’s play areas up to an
appropriate standard, rather than full renewal, had identified a funding shortfall of approximately
£0.620 million.  It was considered that allocation of the available funding across all play areas
would see minimal impact in many play areas and it was proposed that consideration be given
to a more strategic place based approach to allocating specific investment that could see
targeted investment in priority play areas.  The initial assessment of all play areas against the
appropriate standards could be used as the basis of funding in each identified locality.  If
adopted, this approach would be developed in collaboration with the local community and local
ward members, building on consultation already undertaken and delivering local investment
based on local priorities. 
Given the multi year profile of the funding, a programme was proposed with focus on specific
localities each year, as detailed in the report.  Within the programme, there would be flexibility to
bring forward or push back projects as funding and staffing resources allowed. 
The Committee decided: 
(1) that the Scottish Government 5 Year Play Investment Programme be noted; and 
(2) that the proposed place-based, local approach be approved. 
9 South Lanarkshire Gift Card - Update
A report dated 21 November 2022 by the Executive Director (Community and Enterprise
Resources) was submitted on the outcome of the 1 year trial of the South Lanarkshire Gift Card
Scheme. 
All local authorities in Scotland, including South Lanarkshire Council, had been asked by the
Scottish Government, through Scotland’s Town Partnership, to back a Scotland Loves Local Gift
Card Scheme.  The scheme had been designed to encourage local shopping, drive footfall to
local businesses and keep spend in the local area. 
At its meeting held on 7 December 2021, this Committee approved a 1 year trial of the scheme
and a South Lanarkshire Gift Card was promoted through Council networks as well as through
partner organisations such as the Hamilton BID.  The gift cards used the existing MasterCard
network and could be accepted by small independent businesses and national retailers who
used that network.  There was no cost to individual businesses and Scotland’s Town
Partnership (STP), on behalf of the Scottish Government, had a contract in place to cover the
full costs of the first year.   
As of 30 September 2022, 207 businesses had signed up to the South Lanarkshire scheme and
the card had generated sales of £1,235.  Continuation of the scheme would attract an annual
cost of £11,700 and it was considered that the level of uptake did not represent value for money
or an effective use of resources.  Given the limited economic benefit to the area, it was
proposed not to continue with the scheme.   
The Committee decided: 
(1) that the evaluation of the South Lanarkshire Gift Card Scheme be noted; and 
(2) that the gift card programme be not progressed by the Council. 
[Reference: Minutes of 7 December 2021 (Paragraph 8)]
9

Page 10

10 Roads Asset Management Plan – 2022 Update
A report dated 21 November 2022 by the Executive Director (Community and Enterprise
Resources) was submitted on the Roads Asset Management Plan (RAMP) 2022. 
The principles of asset management had been developed, at both a national and local level, to
provide a basis for associated investment decisions and to ensure that a sound understanding
of investment needs was available. 
The main purpose of developing the RAMP was to ensure:- 
 a knowledge of the extent and condition of main asset groups
 an understanding of where gaps existed to allow consideration of how those might be
addressed
 an understanding of the level of current investment on each asset group and the
associated condition trend 
Details were given on:- 
 the Council’s main roads asset groups 
 the overall condition of the infrastructure
 issues for consideration in relation to roads and related infrastructure 
Officers responded to members’ questions on various aspects of the report. 
The Committee decided: that the report be noted. 
[Reference: Minutes of 7 December 2021 (Paragraph 12)] 
11 Comfort Scheme Pilot, Lanark
A report dated 21 November 2022 by the Executive Director (Community and Enterprise
Resources) was submitted providing an update on the comfort scheme pilot, Lanark. 
In 2013, the Council made the decision to close all public conveniences as part of the budget
process.  The Council had continued to make an annual contribution of £2,000 to the New
Lanark Heritage site for public use of their facilities. 
At its meeting on 22 January 2019, this Committee took a decision to pilot a comfort scheme
initiative in Lanark from April 2019 to April 2020.  As a result of the COVID pandemic, the pilot
was interrupted and was extended to September 2022.  The comfort scheme enabled local
authorities to work in partnership with local businesses to provide access for the public to clean,
safe, accessible toilets in local business premises.  A small annual fee was paid to local
businesses for providing this access and details of the 3 local businesses participating in the
pilot were given in the report together with arrangements to publicise the scheme. 
Prior to the evaluation process, Council officers visited the 3 business premises on a number of
occasions when it was noted that footfall to all 3 premises was low, ranging from 0 to 4 visitors. 
The total cost for the pilot was £9,675 and anticipated costs for the retention of the scheme
would be approximately £6,800.
10

Page 11

Given the evaluation of the pilot scheme and the overall cost to the Council to administer and
run the scheme, it was proposed that the Council did not continue the scheme.  It was, however,
proposed that, following positive initial discussions with Discover Lanark, those discussions be
progressed to continue the scheme under their management with appropriate support from the
Council.  Following discussion, and having heard the Chair, it was also proposed that the
Council continue to engage with local communities in support of their aspirations, which could
include community led comfort schemes. 
Officers responded to members’ questions on various aspects of the report 
The Committee decided: 
(1) that the evaluation of the comfort scheme pilot be noted; 
(2) that it be noted that, following the evaluation of the pilot, the Council would not continue
the scheme; 
(3) that it be noted that the Council would progress discussions with Lanark Business
Improvement District (BID) on the potential continuation of the scheme under their
management and operation; and 
(4) that it be noted that the Council would continue to engage with local communities in
support of their aspirations, which could include community led comfort schemes. 
[Reference: Minutes of 22 January 2019 (Paragraph 11)] 
12 Notification of Contracts Awarded: 1 April to 30 September 2022
A report dated 21 November 2022 by the Executive Director (Community and Enterprise
Resources) was submitted on contracts awarded by Community and Enterprise Resources in
the period 1 April to 30 September 2022. 
In terms of Standing Order Nos 21.8 and 22.5 of the Standing Orders on Contracts, Resources
were required to notify the relevant Committee of contracts awarded.  Details of the contracts
awarded by Community and Enterprise Resources were provided in the appendix to the report. 
The Committee decided: that the report be noted. 
[Reference: Minutes of 7 December 2021 (Paragraph 16)] 
13 Urgent Business 
There were no items of urgent business. 
11

Page 12

12

Page 13

Report
Agenda Item 
Report to: Community and Enterprise Resources Committee 
Date of Meeting: 14 March 2023
Report by: Executive Director (Finance and Corporate Resources)
Executive Director (Community and Enterprise
Resources)  
Subject: Community and Enterprise Resources - Revenue
Budget Monitoring 2022/2023 
1. Purpose of Report
1.1. The purpose of the report is to:-
[purpose]
 provide information on the actual expenditure measured against the revenue
budget for the period 1 April 2022 to 27 January 2023 for Community and
Enterprise Resources
 provide a forecast for the year to 31 March 2023
[1purpose]
2. Recommendation(s)
2.1. The Committee is asked to approve the following recommendation(s):- 
(1) that the forecast to 31 March 2023 of an underspend of £0.007 million after
approved transfers to reserves as detailed in Appendix A of the report, be
noted;
(2) that an overspend of £0.015 million as at 27 January 2023 after approved
transfers to reserves, as detailed in Appendix A of the report, be noted; and
(3) that the proposed budget virements as detailed in appendices B to F be
approved.
[1recs]
3. Background
3.1. This is the fourth revenue budget monitoring report presented to the Community and
Enterprise Resources Committee for the financial year 2022/2023. 
3.2. The Resource has completed its formal probable outturn exercise for the year
identifying expected spend to the 31 March 2023.  Details are outlined in section 5
below. 
3.3. The report details the financial position for Community and Enterprise Resources in
appendix A and the individual services’ reports in appendices B to F, including
variance explanation. 
4. Employee Implications
4.1. None 
3
13

Page 14

5. Financial Implications
5.1. Probable Outturn: Following the Council’s probable outturn exercise, the Resource
is reporting an underspend of £0.007 million after approved transfers to reserves of
£1.270 million.  The Resource position is detailed in Appendix A and the transfers to
reserves by service area are noted in appendices B to F. 
5.2. The Resource is showing an underspend of £0.007 million and this is due to
underspends in employee costs across all services, income from waste streams and
an over recovery of Planning and Building Standards income offset by costs within
Roads, Transportation and Fleet services in relation to transport costs and charging
of Electric Vehicles, prior to tariffs being introduced, loss of income for school meals
and costs of PPE, bin replacement and increased ICT costs within supplies and
services.    
5.3. Position as 27 January 2023:  The Resource position as at 27 January 2023 is an
overspend of £0.015 million after approved transfers to reserves.  Appendix A outlines
this position and the overspend in the main reflects further under recovery on school
meal income.  Detailed variance explanations by service area are included in
appendices B to F.     
5.4. Virements are proposed to realign budgets across budget categories and with other
Resources.  These movements are detailed in the appendices B to F of this report.  
6. Climate Change, Sustainability and Environmental Implications
6.1 There are no implications for climate change, sustainability or the environment in terms
of the information contained in this report. 
7. Other Implications
7.1. The main risk associated with the Council’s revenue budget is that there is an
overspend.  There are inflationary and budget pressures including utilities and fuel (as
well as general inflation pressures) this year which increase the risk of overspend ,
however, we have mitigated this going forward by providing additional funds in future
years’ budget strategy, and in this year, through some reserve funds available  There
are also emerging underspends in employee costs which will help offset increasing
inflationary pressures. 
7.2. We will also continue to monitor the actual impact through four weekly budget
monitoring meetings at which any variance is analysed. In addition, the probable
outturn exercise ensures early warning for corrective action to be taken where
appropriate. 
8 Equality Impact Assessment and Consultation Arrangements
8.1. This report does not introduce a new policy, function or strategy or recommend a
change to an existing policy, function or strategy and, therefore, no impact assessment
is required. 
8.2. There is also no requirement to undertake any consultation in terms of the information
contained in this report. 
Paul Manning
Executive Director (Finance and Corporate Resources) 
14

Page 15

David Booth
Executive Director (Community and Enterprise Resources) 
8 February 2023 
Link(s) to Council Values/Priorities/Outcomes
 Accountable, effective, efficient and transparent 
Previous References
 None 
List of Background Papers
 Financial ledger and budget monitoring results to 27 January 2023. 
Contact for Further Information
If you would like to inspect the background papers or want further information, please
contact:-
Louise Harvey, Finance Manager
Ext:  2658 (Tel: 01698 452658)
E-mail: louise.harvey@southlanarkshire.gov.uk 
15

Page 16

Appendix A 
SOUTH LANARKSHIRE COUNCIL 
Revenue Budget Monitoring Report 
Community and Enterprise Resources: Period 11 Ended 27 January 2023 (No. 11) 
Community and Enterprise Resources Summary 
Annual
Budget 
Forecast
for Year
BEFORE
Transfers
Annual
Forecast
Variance
BEFORE
Transfers
Annual
Forecast
Variance
AFTER
Transfers
Budget
Proportion
27/01/23
Actual 
BEFORE
Transfers
27/01/23
Variance 
27/01/23 
%
Variance
27/01/23 
Note 
£000 £000 £000 £000 £000 £000 £000   
Budget Category           
Employee Costs 94,463 92,087 2,376 2,376 75,836 73,640 2,196 under 2.9% 
Property Costs 4,012 4,726 (714) (814) 3,313 4,042 (729) over (22.0%) 
Supplies & Services 17,920 18,277 (357) (397) 13,516 13,768 (252) over (1.9%) 
Transport & Plant 23,531 23,972 (441) (441) 18,282 18,878 (596) over (3.3%) 
Administration Costs 816 988 (172) (172) 593 667 (74) over (12.5%) 
Payments to Other Bodies 10,989 11,064 (75) (75) 7,713 7,692 21 under 0.3% 
Payments to Contractors 46,304 45,966 338 (792) 31,522 30,931 591 under 1.9% 
Transfer Payments 603 603 0 0 530 530 0 - 0.0% 
Financing Charges 185 237 (52) (52) 171 207 (36) over (21.1%) 
Total Controllable Exp. 198,823 197,920 903 (367) 151,476 150,355 1,121 under 0.7% 
Total Controllable Inc. (69,026) (69,400) 374 374 (54,009) (53,948) (61) under
recovered (0.1%) 
Net Controllable Exp. 129,797 128,520 1,277 7 97,467 96,407 1,060 under 1.1% 
Transfer to Reserves 
(as at 27/01/23) - 1,270 (1,270) - - 1,075 (1,075) over  
Position After Transfers to
Reserves 
(as at 27/01/23)
129,797 129,790 7 7 97,467 97,482 (15)      over (0.0%) 
Variance Explanations 
Detailed in Appendix B to F. 
Budget Virements 
Budget virements are shown in Appendices B to F. 
Approved Transfers to Reserves 
Detailed in Appendix B to F 
16

Page 17

Appendix B 
SOUTH LANARKSHIRE COUNCIL 
Revenue Budget Monitoring Report 
Community and Enterprise Resources: Period 11 Ended 27 January 2023 (No. 11) 
Facilities, Waste and Grounds Services 
Annual
Budget 
Forecast
for Year
BEFORE
Transfers
Annual
Forecast
Variance
BEFORE
Transfers
Annual
Forecast
Variance
AFTER
Transfers
Budget
Proportion
27/01/23
Actual 
BEFORE
Transfers
27/01/23
Variance 
27/01/23 
%
Variance
27/01/23
Note 
£000 £000 £000 £000 £000 £000 £000   
Budget Category           
Employee Costs 59,860 59,009 851 851 48,120 47,279 841 under 1.7% 1,a,b,f
Property Costs 1,855 2,047 (192) (292) 1,490 1,703 (213) over (14.3%) 2,c,d,f
Supplies & Services 8,763 8,780 (17) (17) 6,509 6,604 (95) over (1.5%) 3,f
Transport & Plant 8,506 8,523 (17) (17) 6,630 6,652 (22) over (0.3%) f
Administration Costs 165 211 (46) (46) 103 159 (56) over (54.4%) 4
Payments to Other Bodies 51 53 (2) (2) 44 44 0 - 0.0% 
Payments to Contractors 15,997 14,768 1,229 99 11,684 10,636 1,048 under 9.0% 5,a
Transfer Payments 0 0 0 0 0 0 0 - n/a 
Financing Charges 45 63 (18) (18) 44 52 (8) over (18.2%) 6           
Total Controllable Exp. 95,242 93,454 1,788 558 74,624 73,129 1,495 under 2.0% 
Total Controllable Inc. (19,616) (19,585) (31) (31) (16,244) (16,200) (44) under
recovered (0.3%) 7,b,e
Net Controllable Exp. 75,626 73,869 1,757 527 58,380 56,929 1,451 under 2.5% 
Transfer to Reserves 
(as at 27/01/23) - 1,230 (1,230) - - 1,041 (1,041) over  
Position After Transfers to
Reserves 
(as at 27/01/23)
75,626 75,099 527 527 58,380 57,970             410     under 0.7% 
Variance Explanations 
1.        The variance is mainly due to vacancies that are being actively recruited within School Crossing Patrollers, Catering and Janitors Services within
Facilities, and turnover and staff working on reduced hourly contracts as a result of flexible retirement throughout the service.
2.  The overspend is due to greater than budgeted expenditure on refuse uplifts and Health and Hygiene charges within Janitorial Service and rates
charges associated with historic public conveniences, and higher than anticipated expenditure on the security and upkeep of the Castlehill Transfer
station. In addition, the overspend is also due to the retention of the additional death facility at Peel Park, however, partial income is anticipated this
financial year to support costs.  
3.  The overspend is mainly due to higher than anticipated expenditure on bin purchases and PPE along with upgrading of IT systems within Waste,
partially offset by an underspend within Facilities on school meals food purchases partially offset by an overspend on equipment. 
4.  The overspend is mainly due to an overspend on medical costs within the service along with printing costs within Facilities Management. 
5. The variance is mainly due to income received from the disposal of both fibres and containers within the Waste Service. 
6. The overspend is due to increased IT leasing costs.
7. The under recovery of income mainly relates to the decrease in uptake of the Care of Gardens Service, no income recovered from Adoption Monies
within Grounds, an under recovery in school meals income which has increased due to loss of income from school closures and teachers strike days
and less demand for bereavement services within Streets and Bereavement. These are partially offset by an over recovery within Waste and Streets
as a result of additional service requests from Housing and Tech and additional service requests within Facilities. 
Budget Virements 
a. Transfer of budget to corporate items in respect of National Insurance budget 22-23 clawback and domestic waste tonnage support for COVID. Net
effect (£1.011m): Employees (£0.111m), Payment to Contractor (£0.900m).
b. Transfer of budget in relation to pay award. Net effect £4.286m: Employees £4.411m, Income (£0.125m).
c. Transfer of budget in respect of additional rates poundage. Net effect £0.007m: Property £0.007m.
d. Transfer of budget in respect of utilities. Net effect £0.084m: Property £0.084m.
e. Realignment of budget to reflect service provision within Grounds and Facilities. Net effect £0.000m: Employees (£0.385m), Property £0.007m, Supplies
and Services £0.223m, Transport and Plant (£0.082m), Income £0.237m. 
Approved Transfers to Reserves (£1.230m): 
i. Allotment (£0.100m)
ii. Crematorium Sinking fund (£0.050m)
iii. Unbudgeted Waste Income - (£1.080m) 
17

Page 18

Appendix C 
SOUTH LANARKSHIRE COUNCIL 
Revenue Budget Monitoring Report 
Community and Enterprise Resources: Period 11 Ended 27 January 2023 (No. 11) 
Planning and Regulatory Services 
Annual
Budget 
Forecast
for Year
BEFORE
Transfers
Annual
Forecast
Variance
BEFORE
Transfers
Annual
Forecast
Variance
AFTER
Transfers
Budget
Proportion
27/01/23
Actual 
BEFORE
Transfers
27/01/23
Variance 
27/01/23 
%
Variance
27/01/23
Note 
£000 £000 £000 £000 £000 £000 £000   
Budget Category           
Employee Costs 7,409 7,012 397 397 5,952 5,585 367 under 6.2% 1,a,b
Property Costs 193 195 (2) (2) 143 143 0 - 0.0% c
Supplies & Services 270 284 (14) (14) 150 169 (19) over (12.7%) 2,c
Transport & Plant 553 516 35 35 522 503 19 under 3.6% 3
Administration Costs 146 150 (4) (4) 89 94 (5) over (5.6%) 
Payments to Other Bodies 277 200 77 77 142 94 48 under 33.8% 4,c
Payments to Contractors 1,640 1,665 (25) (25) 1,219 1,239 (20) over (1.6%) c
Transfer Payments 0 0 0 0 0 0 0 - n/a 
Financing Charges 46 63 (17) (17) 44 48 (4) over (9.1%) 
Total Controllable Exp. 10,534 10,087 447 447 8,261 7,875 386 under 4.7% 
Total Controllable Inc. (5,396) (5,991) 595 595 (4,101) (4,564) 463 over
recovered 11.3% 5,c
Net Controllable Exp. 5,138 4,096 1,042 1,042 4,160 3,311 849 under 20.4% 
Transfer to Reserves 
(as at 27/01/23) - - - - - - - -  
Position After Transfers to
Reserves 
(as at 27/01/23)
5,138 4,096 1,042 1,042 4,160 3,311 849 under 20.4% 
Variance Explanations 
1. The variance is mainly due to vacant posts within the services which are being recruited.
2. The over spend is due to greater than anticipated IT charges for the Flare Environmental IT system.
3. The variance is mainly due to lower than anticipated pool car charges within Environmental Services.
4. The variance is due to lower than anticipated expenditure on scientific services within Environmental Services.
5. The over recovery of income is mainly due to a greater demand for Planning and Building Standard applications. 
Budget Virements 
a. Transfer of budget to corporate items in respect of National Insurance budget 22-23 clawback. Net (£0.022m): Employees (£0.022m). 
b. Transfer of budget in relation to pay award. Net effect £0.222m: Employees £0.222m.
c. Realignment of budget to reflect service delivery within Projects, Environmental and Planning. Net effect £0.000m: Property £0.045m, Supplies and
Services (£0.007m), Payment to Other Bodies £0.022m, Payment to contractor £0.016m, Income (£0.076m). 
18

Page 19

Appendix D 
SOUTH LANARKSHIRE COUNCIL 
Revenue Budget Monitoring Report 
Community and Enterprise Resources: Period 11 Ended 27 January 2023 (No. 11) 
South Lanarkshire Leisure and Culture 
Annual
Budget 
Forecast
for Year
BEFORE
Transfers
Annual
Forecast
Variance
BEFORE
Transfers
Annual
Forecast
Variance
AFTER
Transfers
Budget
Proportion
27/01/23
Actual 
BEFORE
Transfers
27/01/23
Variance 
27/01/23 
%
Variance
27/01/23
Note 
£000 £000 £000 £000 £000 £000 £000   
Budget Category           
Employee Costs 4 6 (2) (2) 3 43 (1) over (33.3%) 
Property Costs 98 76 22 22 81 64 17 under 21.0% 1
Supplies & Services 0 0 0 0 0 0 0 - n/a 
Transport & Plant 0 0 0 0 0 0 0 - n/a 
Administration Costs 8 9 (1) (1) 8 9 (1) over (12.5%) 
Payments to Other Bodies 80 91 (11) (11) 0 0 0 - n/a 
Payments to Contractors 23,752 23,752 0 0 15,778 15,778 0 - 0.0% a,b
Transfer Payments 0 0 0 0 0 0 0 - n/a 
Financing Charges 0 0 0 0 0 0 0 - n/a 
Total Controllable Exp. 23,942 23,934 8 8 15,870 15,856 14 under 0.1% 
Total Controllable Inc. 0 (4) 4 4 0 (3) 3 over
recovered n/a 
Net Controllable Exp. 23,942 23,930 12 12 15,870 15,853 17 under 0.1% 
Transfer to Reserves 
(as at 27/01/23) - - - - - - - -  
Position After Transfers to
Reserves 
(as at 27/01/23)
23,942 23,930 12 12 15,870 15,853 17      under  0.1% 
Variance Explanations 
1. The variance relates to reduced service charges for East Kilbride ice rink. 
Budget Virements 
a. Transfer of budget in relation to pay award. Net £0.878: Payment to Contractors £0.878m. 
b. Transfer of funding to corporate items for Warm Welcome Initiative. Net (£0.600m): Payment to Contractors (£0.600m). 
19

Page 20

Appendix E 
SOUTH LANARKSHIRE COUNCIL 
Revenue Budget Monitoring Report 
Community and Enterprise Resources: Period 11 Ended 27 January 2023 (No. 11) 
Enterprise and Sustainable Development 
Annual
Budget 
Forecast
for Year
BEFORE
Transfers
Annual
Forecast
Variance
BEFORE
Transfers
Annual
Forecast
Variance
AFTER
Transfers
Budget
Proportion
27/01/23
Actual 
BEFORE
Transfers
27/01/23
Variance 
27/01/23 
%
Variance
27/01/23
Note 
£000 £000 £000 £000 £000 £000 £000   
Budget Category           
Employee Costs 5,276 5,168 108 108 4,254 4,130 124 under 2.9% 1,a,b,d,f
Property Costs 798 808 (10) (10) 670 676 (6) over (0.9%) c
Supplies & Services 300 311 (11) (11) 143 155 (12) over (8.4%) 2,e
Transport & Plant 47 42 5 5 45 43 2 under 4.4% 
Administration Costs 99 77 22 22 68 52 16 under 23.5% 3
Payments to Other Bodies 4,948 4,987 (39) (39) 2,091 2,118 (27) over (1.3%) 4,f
Payments to Contractors 52 52 0 0 52 52 0 - 0.0% 
Transfer Payments 0 0 0 0 0 0 0 - n/a 
Financing Charges 44 36 8 8 42 48 (6) over (14.3%) 
Total Controllable Exp. 11,564 11,481 83 83 7,365 7,274 91 under 1.2% 
Total Controllable Inc. (4,607) (4,638) 31 31 (1,827) (1,853) 26 over
recovered 1.4% 5,f
Net Controllable Exp. 6,957 6,843 114 114 5,538 5,421 117 under 2.1% 
Transfer to Reserves 
(as at 27/01/23) - - - - - - - -  
Position After Transfers to
Reserves 
(as at 27/01/23)
6,957 6,843 114 114 5,538 5,421 117       under 2.1% 
Variance Explanations 
1. This variance is mainly due to vacant posts within the services which are being recruited. 
2. The overspend mainly relates to greater than budgeted IT costs within Business Support.
3. The variance is due to lower than anticipated printing & stationery, telephone costs and membership fees within Business Support.
4. The overspend is due to higher than anticipated costs for Christmas events.
5. The income is over recovered due to greater than budgeted rental income within Support Services. 
Budget Virements 
a. Transfer of budget to corporate items in respect of National Insurance budget 22-23 clawback. Net effect (£0.011m): Employees (£0.011m).
b. Transfer of budget in relation to pay award. Net effect £0.221m: Employees £0.221m.
c. Transfer of budget in respect of utilities. Net effect £0.002m: Property £0.002m.
d. Transfer to reserves funding for the Food Development officer post within Support Services. Net effect (£0.056m): Employees (£0.056m).
e. Transfer from reserves in respect of expenditure commitments for Montrose House move to Headquarters. Net effect £0.004m: Supplies and Services
£0.004m.
f. Establish budgets in respect of external income from Hamilton Palace Grounds, Strathaven Cars, Business Support Fund, Business Loans Scotland
Funding and Business Ventilation Fund along with realignment of budget within Get South Lanarkshire Working to reflect service. Net effect £0.000m:
Employees £0.008m, Payment to Other Bodies £0.762m, Income (£0.770m). 
20

Page 21

Appendix F 
SOUTH LANARKSHIRE COUNCIL 
Revenue Budget Monitoring Report 
Community and Enterprise Resources: Period 11 Ended 27 January 2023 (No. 11) 
Roads, Transportation and Fleet Services 
Annual
Budget 
Forecast
for Year
BEFORE
Transfers
Annual
Forecast
Variance
BEFORE
Transfers
Annual
Forecast
Variance
AFTER
Transfers
Budget
Proportion
27/01/23
Actual 
BEFORE
Transfers
27/01/23
Variance 
27/01/23 
%
Variance
27/01/23
Note 
£000 £000 £000 £000 £000 £000 £000   
Budget Category           
Employee Costs 21,914 20,892 1,022 1,022 17,507 16,642 865 under 4.9% 1,a,b,e
Property Costs 1,068 1,600 (532) (532) 929 1,456 (527) over (56.7%) 2,c,d,e
Supplies & Services 8,587 8,902 (315) (355) 6,714 6,839 (125) over (1.9%) 3,d,e
Transport & Plant 14,425 14,889 (464) (464) 11,085 11,680 (595) over (5.4%) 4,e
Administration Costs 398 541 (143) (143) 325 353 (28) over (8.6%) 5
Payments to Other Bodies 5,633 5,733 (100) (100) 5,436 5,436 0 - 0.0% e
Payments to Contractors 4,863 5,729 (866) (866) 2,789 3,226 (437) over (15.7%) 6,f
Transfer Payments 603 603 0 0 530 530 0 - 0.0% 
Financing Charges 50 75 (25) (25) 41 59 (18) over (43.9%) 7           
Total Controllable Exp. 57,541 58,964 (1,423) (1,463) 45,356 46,221 (865) over (1.9%) 
Total Controllable Inc. (39,407) (39,182) (225) (225) (31,837) (31,328) (509) under
recovered (1.6%) 8,b,e
Net Controllable Exp. 18,134 19,782 (1648) (1,688) 13,519 14,893 (1,374) over (10.2%) 
Transfer to Reserves 
(as at 27/01/23) - 40 (40) - - 34 (34)   
Position After Transfers to
Reserves 
(as at 27/01/23)
18,134 19,782 (1,688) (1,688) 13,519 14,927 (1,408) over (10.4%) 
Variance Explanations 
1.  The variance relates to staff turnover and vacancies within Roads and Fleet which are being recruited.  
2. The overspend is in the main due to higher than anticipated electricity costs for Electrical Vehicle charging points and the upkeep of Roads depots.
3. The overspend mainly relates to increased costs for annual subscriptions for Computer Licences and PPE within roads.
4. The overspend is mainly due to the timing of efficiencies and greater than anticipated expenditure in the workshop within Fleet services, partially offset
by under spend in casual hire charges.
5. The overspend is mainly due to a greater than budgeted spend on printing & stationery, telephones, membership fees and medical costs within Fleet
services and advertising of road closures within Roads.
6. The overspend is mainly due to higher than anticipated routine maintenance costs within Clydesdale and Lighting services in Roads.
7. The overspend is due increased IT leasing costs.
8. The under recovery in income is mainly due to less than anticipated income from taxi inspections income, pool car charges, casual hire charges
partially offset by income from the sale of vehicles and the recovery of vehicle maintenance within Fleet. The under recovery is also due to less than
anticipated income from maintenance works within Roads at this time, which is partially offset by the recovery of income from previous years within
Parking and an over recovery within HQ Operations for inspection fees. 
Budget Virements 
a. Transfer of budget to corporate items in respect of National Insurance budget 22-23 clawback. Net effect (£0.058m): Employees (£0.058m).
b. Transfer of budget in relation to pay award. Net effect £1.046m: Employees £1.083m, Income (£0.037m).
c. Transfer of budget in respect of additional rates poundage. Net effect £0.009m: Property £0.009m.
d. Transfer of budget in respect of utilities Net effect £0.098m: Property £0.049m, Supplies and Services £0.049m.
e. Realignment of budget to reflect service provision within Roads and Fleet. Net effect £0.000m: Employees (£0.028m), Property £0.007m, Supplies and
Services £0.002m, Transport and Plant £0.014m, Payment to Other Bodies £0.380m, Income (£0.368m).
f. Transfer from reserves in respect of Roads Winter Maintenance. Net effect £0.404m: Payment to Contractors £0.404m. 
Approved Transfers to Reserves (£0.040m): 
i. Fleet Sinking Fund (£0.025m)
ii. Year 3 of Electric Vehicle Payback (£0.015m)
21

Page 22

22

Page 23

Report
Agenda Item 
Report to: Community and Enterprise Resources Committee
Date of Meeting: 14 March 2023
Report by: Executive Director (Finance and Corporate Resources)
Executive Director (Community and Enterprise
Resources)  
Subject: Community and Enterprise Resources - Capital Budget
Monitoring 2022/2023 
1. Purpose of Report
1.1. The purpose of the report is to:-
[purpose]
 provide information on the progress of the capital programme for Community and
Enterprise Resources for the period 1 April 2022 to 27 January 2023
[1purpose]
2. Recommendation(s)
2.1. The Committee is asked to approve the following recommendation(s):-
[recs]
(1) that the Community and Enterprise Resources’ capital programme of £48.444
million, and expenditure to date of £22.898 million, be noted; and 
(2) that the projected outturn of £43.7 million be noted. 
[recs]
3. Background
3.1. This is the fourth capital monitoring report presented to the Community and
Enterprise Resources Committee for the financial year 2022/2023. A further report
will follow after the financial year end. 
3.2. As noted in the last report to this Committee (13 December 2022), the budget for
Community and Enterprise Resources for financial year 2022/2023 was £48.270
million. 
3.3. Since that meeting, the Executive Committee has agreed changes to the Community
and Enterprise Resources Capital Programme totalling a net increase of £0.174
million.  The details are shown in Appendix A.  This takes the Community and
Enterprise Resources’ programme for 2022/2023 to £48.444 million.   
3.4. The report details the financial position for Community and Enterprise Resources in
Appendix A. 
4. Employee Implications
4.1. There are no employee implications as a result of this report. 
5. Financial Implications
5.1. As detailed in Section 3.3, the revised capital programme for Community and
Enterprise Resources for 2022/2023 is £48.444 million. 
4
23

Page 24

5.2. 2022/2023 Outturn
Work has been ongoing to monitor the predicted spend position for this financial year
and current estimates from Community and Enterprise Resources suggest an
outturn of £43.7 million, an underspend of £4.744 million.  The majority of the
variance is due to the timing of spend on a number of projects resulting in budget
required in 2023/2024 rather than 2022/2023.   
5.3. This includes a number of Glasgow City Region City Deal projects (including the
grant payment element of Cathkin Bypass as well as Lanark Road Signalisation),
Renewal of Play Parks, the Town Centre Regeneration Fund and Vacant and
Derelict Land project at Cuningar Loop.  Funding for these projects will carry forward
into next financial year. 
5.4. Period 11 Position   
Anticipated spend to date was £23.073 million and spend to 27 January 2023
amounts to £22.898 million, an underspend of £0.175 million.  This mainly reflects
the timing of spend on the Greenhills Road and Jackton Primary School projects
within the Glasgow City Region City Deal Programme.  This has been offset by
spend in relation to Clyde Gateway being incurred earlier than anticipated. 
6. Climate Change, Sustainability and Environmental Implications
6.1. There are no implications for climate change, sustainability or the environment in
terms of the information contained in this report. 
7. Other Implications
7.1. The main risk associated with the Council’s Capital Programme is that there is an
overspend.  The Council continues to experience material shortages, longer lead
times and extraordinary inflationary price increases and it is anticipated that this will
continue to impact the supply chain for the foreseeable future.  The impact of this will
continue to be monitored through the four weekly investment management
meetings.  Further updates will be reported in the coming months with any significant
increases in contract values being brought to members’ attention. 
8. Equality Impact Assessment and Consultation Arrangements
8.1. This report does not introduce a new policy, function or strategy or recommend a
change to an existing policy, function or strategy and therefore no impact
assessment is required. 
8.2. There was also no requirement to undertake any consultation in terms of the
information contained in this report. 
Paul Manning
Executive Director (Finance and Corporate Resources) 
David Booth
Executive Director (Community and Enterprise Resources) 
22 February 2023 
Link(s) to Council Values/Priorities/Outcomes
 Accountable, effective, efficient and transparent
24

Page 25

Previous References
 Community and Enterprise Resources Committee, 13 December 2022
 Executive Committee, 1 February 2023
 Executive Committee, 1 March 2023 
List of Background Papers
 Financial ledger to 27 January 2023 
Contact for Further Information
If you would like to inspect the background papers or want further information, please
contact:-
Lorraine O’Hagan, Finance Manager (Strategy)
Ext:  2601 (Tel:  01698 452601)
E-mail: lorraine.o’hagan@southlanarkshire.gov.uk
25

Page 26

Appendix A
South Lanarkshire Council
Capital Expenditure 2022/2023
Community and Enterprise Resources 
For Period 1 April 2022 – 27 January 2023 
Community and
Enterprise Resources
Base
Budget 
£000
Budget
Adjustments
£000 
Slippage
£000
Total
Budget
£000
Budget 
to Date
£000
Actual
Expenditure
£000 
Facilities, Waste and
Grounds
1,949 1,108 (503) 2,554 261 254 
Enterprise and Sustainable
Development
27,435 2,368 (10,670) 19,133 9,752 10,004 
Roads, Transport and
Fleet
29,997 2,652 (5,892) 26,757 13,060 12,640 
TOTAL 59,381 6,128 (17,065) 48,444 23,073 22,898 
For Information Only   
Budget Adjustments approved by Executive Committee, 
1 February 2023: 
Budget Adjustments approved by Executive Committee, 
1 March 2023: 
Budget Adjustments 
Priory Changing Pavilion - Blantyre 
Total Budget Adjustments           
£0.050m   
£0.050m
Budget Adjustments 
Cycle Shelters at Schools
National Strategy for 20mph 
Total Budget Adjustments           
£0.040m
£0.084m 
£0.124m 
26

Page 27

Report
Agenda Item 
Report to: Community and Enterprise Resources Committee
Date of Meeting: 13 February 2023
Report by: Executive Director (Finance and Corporate Resources)
and Executive Director (Community and Enterprise
Resources)  
Subject: Community and Enterprise Resources – Workforce
Monitoring – October to December 2022 
1. Purpose of Report
1.1. The purpose of the report is to:-
[purpose]
 provide employment information for October to December 2022 relating to
Community and Enterprise Resources
[1purpose]
2. Recommendation(s)
2.1. The Committee is asked to approve the following recommendation(s):-
[recs]
(1) that the following employment information for October to December 2022
relating to Community and Enterprise Resources be noted:- 
 attendance statistics;
 occupational health;
 accident/incident statistics;
 discipline, grievance and Dignity at Work cases;
 analysis of leavers and exit interviews;
 staffing watch as at 10 December 2022 
[1recs]
3. Background
3.1. As part of the Council’s performance management arrangements, regular workforce
monitoring reports are submitted to Committee.  This report for Community and
Enterprise Resources provides information on the position for October to December
2022. 
4. Monitoring Statistics
4.1. Attendance Statistics (Appendix 1) 
Information on absence statistics is analysed for the month of December 2022 for
Community and Enterprise Resources. 
The Resource absence figure for December 2022 was 8.0%, this figure has
increased by 0.3% when compared to the previous month and is 1.0% higher than
the Council-wide figure.  Compared to December 2021, the Resource absence figure
has increased by 0.6%. 
Based on the absence figures at December 2022 and annual trends, the projected
annual average absence for the Resource for 2022/2023 is 7.4%, compared to a
Council-wide average figure of 6.0%.
5
27

Page 28

Managers follow the procedures outlined in the Maximising Attendance Policy to
support employees to remain at work, or to return to work after a sickness absence. 
There are comprehensive employee supports in place and additionally, Personnel
Services work in close partnership with line managers and Resource Management
Teams on a case management basis to ensure that appropriate actions are taken. 
The attendance information contained in this report includes absences as a result of
COVID-19, and employees are being supported through this difficult time to maintain
attendance levels where they can.  At the time of this report, the Council overall
absence level was 5.81% with 0.30% of this relating to COVID-19 for sickness and
special leave. 
4.2. Occupational Health (Appendix 2) 
In terms of referrals to occupational health, which include medical examinations and
physiotherapy, overall, 337 referrals were made this period.  This represents an
increase of 8 when compared with the same period last year.   
4.3. Accident/Incident Statistics 
There were 49 accidents/incidents recorded within the Resource this period, an
increase of 17 when compared to the same period last year. 
4.4. Discipline, Grievance and Dignity at Work (Appendix 2) 
During the period, 32 disciplinary hearings were held within the Resource, an
increase of 24 when compared to the same period last year.  One appeal was heard
by the Appeals Panel.  Three grievance hearings were raised within the Resource,
this figure has increased by 1 when compared to the same period last year.  No
Dignity at Work complaints were raised within the Resource, this figure has
decreased by 1 when compared to the same period last year. 
4.5. Analysis of Leavers (Appendix 2) 
There were a total of 46 leavers in the Resource this period eligible for an exit
interview. This figure has increased by 7 when compared with the same period last
year.  Nine exit interviews were conducted in this period, a decrease of 4 when
compared to the same period last year. 
4.6. When processing an employee termination, managers were asked to identify
whether they intended to replace the employee who had left the Council.  If they
indicated that they did not intend to replace the employee, they were asked to select
from the following options:- 
 plan to hold for savings
 fill on a fixed term basis pending savings
 transfer budget to another post
 end of fixed term post 
4.7. Appendix 2a provides a breakdown of vacant posts and whether these are being
replaced or held for savings.  In the period October to December 2022, 145 (95.48
FTE) employees in total left employment, managers indicated that 120 posts (71.07
FTE) were being replaced and 25 posts (24.41 FTE) were due to the end of a fixed
term contract. 
5. Staffing Watch 
5.1. There has been a decrease of 74 in the number of employees in post from 10
September 2022 to 10 December 2022.
28

Page 29

6. Employee Implications
6.1. There are no implications for employees arising from the information presented in
this report. 
7. Financial Implications
7.1. All financial implications are accommodated within existing budgets. 
8. Climate Change, Sustainability and Environmental Implications
8.1. There are no Climate Change, Sustainability and Environmental Implications in
terms of the information contained within this report. 
9. Other Implications
9.1. There are no implications for sustainability or risk in terms of the information
contained within this report. 
10. Equality Impact Assessment and Consultation Arrangements
10.1. This report does not introduce a new policy, function or strategy or recommend a
change to an existing policy, function or strategy and, therefore, no impact
assessment is required. 
10.2. There was no requirement to undertake any consultation in terms of the information
contained in this report. 
Paul Manning
Executive Director (Finance and Corporate Resources) 
David Booth
Executive Director (Community and Enterprise Resources) 
2 February 2023 
Link(s) to Council Values/Priorities/Outcomes
 Accountable, effective, efficient and transparent
 Fair, open and sustainable
 Ambitious, self aware and improving
 Excellent employer
 Focused on people and their needs
 Working with and respecting others 
Previous References
 Community and Enterprise Resources – 13 December 2022 
List of Background Papers
 Monitoring information provided by Finance and Corporate Resources 
Contact for Further Information
If you would like to inspect the background papers or want further information, please
contact:-
Elaine Maxwell, HR Business Manager
Ext:   (Tel: 01698 454647)
E-mail:  Elaine.Maxwell@southlanarkshire.gov.uk 
29

Page 30

2020 /
2021
2021 /
2022
2022 /
2023
2020 /
2021
2021 /
2022
2022 /
2023
2020 /
2021
2021 /
2022
2022 /
2023
2020 /
2021
2021 /
2022
2022 /
2023
% % % % % % % % % % % %
April 3.1 2.3 4.4 April 5.3 5.7 7.3 April 5.0 5.2 6.9 April 4.4 4.3 5.6
May 2.4 2.7 3.9 May 4.3 6.4 6.8 May 4.0 5.9 6.3 May 3.1 4.9 5.4
June 1.6 2.8 3.5 June 4.0 6.6 7.2 June 3.6 6.0 6.7 June 2.7 4.7 5.3
July 1.8 2.9 3.9 July 3.6 5.3 5.9 July 3.4 4.9 5.6 July 2.3 4.0 4.6
August 1.7 2.9 3.4 August 4.9 6.4 6.6 August 4.4 5.9 6.1 August 3.1 4.7 4.4
September 1.6 3.4 3.1 September 5.8 8.2 7.9 September 5.1 7.5 7.1 September 4.2 6.4 5.4
October 3.1 3.8 5.1 October 6.3 7.9 7.5 October 5.8 7.3 7.1 October 4.8 6.3 5.8
November 3.6 3.5 4.2 November 7.1 8.0 8.3 November 6.6 7.3 7.7 November 5.8 6.9 6.5
December 3.1 4.2 3.7 December 6.4 8.0 8.8 December 5.9 7.4 8.0 December 5.6 6.9 7.0
January 3.4 3.6 January 6.0 9.6 January 5.6 8.6 January 4.8 7.0
February 2.8 4.4 February 6.5 9.5 February 5.9 8.7 February 4.8 6.6
March 2.6 6.0 March 6.8 11.0 March 6.2 10.2 March 4.9 7.9
Annual Average 2.6 3.5 4.1 Annual Average 5.6 7.7 8.0 Annual Average 5.1 7.1 7.4 Annual Average 4.2 5.9 6.0
Average Apr-Dec 2.4 3.2 3.9 Average Apr-Dec 5.3 6.9 7.4 Average Apr-Dec 4.9 6.4 6.8 Average Apr-Dec 4.0 5.5 5.6
524 2884 3408 16104
Appendix 1
Absence Trends - 2020/2021, 2021/2022 & 2022/2023
Community and Enterprise Resources
APT&C Council WideManual Workers Resource Total
No of Employees at 31 Dec 2022 No of Employees at 31 Dec 2022 No of Employees at 31 Dec 2022 No of Employees at 31 Dec 2022
30

Page 31

COMMUNITY AND ENTERPRISE RESOURCES
Oct-Dec Oct-Dec
2021 2022
MEDICAL EXAMINATIONS
Number of Employees Attending
EMPLOYEE COUNSELLING SERVICE
Total Number of Referrals
PHYSIOTHERAPY SERVICE
Total Number of Referrals
REFERRALS TO EMPLOYEE SUPPORT OFFICER 110 108
REFERRALS TO COGNITIVE BEHAVIOUR THERAPY 0 0
TOTAL 329 337
Oct-Dec Oct-Dec
2021 2022
Over 7 day absences 4 10
Over 3 day absences** 0 2
Minor 14 21
Near Miss 4 4
Violent Incident:  Physical**** 3 5
Violent Incident:  Verbal***** 7 7
Total Accidents/Incidents 32 49
Oct-Dec Oct-Dec
2021 2022
Total Number of Hearings 8 32
Total Number of Appeals 4 1
Time Taken to Convene Hearing Oct - Dec 2022
0-3 Weeks 4-6 Weeks Over 6 Weeks
16 8 8
Oct-Dec Oct-Dec
2021 2022
Number of Grievances 2 3
Number Resolved at Stage 2 2 3
Oct-Dec Oct-Dec
2021 2022
Number of Incidents 1 0
Number Resolved at Formal Stage 1 0
Oct-Dec Oct-Dec
2021 2022
Career Advancement 1 3
Poor Relationship with Manager/Colleagues 1 1
Personal Reasons 5 1
Travelling Difficulties 1 1
Further Education 0 1
Childcare/caring responsibilities 2 1
Dissatisfaction With Terms and Conditions 1 1
Other 2 0
Number of Exit Interviews conducted 13 9
Total Number of Leavers Eligible for Exit Interview 39 46
Percentage of interviews conducted 33% 20%
****Physical violent incidents and ***** Verbal Violent Incidents are included in the "Over 3-day or
Over 7-day" figures, where applicable, to provide the "Total Over 3-day or Over 7-day" figures.
****Physical Violent Incidents and ***** Verbal Violent Incidents are included in the "Minor" figures,
where applicable, to provide the "Total Minor" figures.
ANALYSIS OF REASONS FOR LEAVING
RECORD OF DISCIPLINARY HEARINGS
RECORD OF GRIEVANCE HEARINGS
RECORD OF DIGNITY AT WORK
CAUSE OF ACCIDENTS/INCIDENTS
115
*A Specified Injury is any fracture (other than to the fingers, thumbs or toes), amputation, loss of
sight, serious burns, crushing injury, scalping, loss of consciousness caused by asphyxiation/ head
injury, a chemical or hot metal burn to the eye or penetrating injury as defined by the HSE.
**Over 3 day / over 7day absence is an injury sustained outwith specified injury category that results
in a period of absence of absence as defined by the HSE. 
***Near Miss - Any unexpected, unplanned occurrence (except Dangerous Occurrences) that does
not lead to injury of persons, damage to property, plant or equipment but may have done so in
different circumstance.
****Physical violent incidents are included in the "Specified" figures, where applicable, to provide the
"Total Specified" figures.
104
APPENDIX 2
91 106
13 19
31

Page 32

FTE* H/C** FTE H/C
Number of Leavers 95.48 145 264.14 467
Replace Employee 71.07 120 231.67 430
Filling on a Temp Basis 0.00 0 0.00 0
Plan to transfer budget to another post 0.00 0 0.00 0
End of fixed term post 24.41 25 32.46 37
Leave vacant pending savings or service review 0.00 0 0.00 0
Plan to remove for savings 0.00 0 0.00 0
* Full time equivalent
** Head count/number of employees
Appendix 2a
Oct - Dec 2022 Cumulative total
(Apr 22 - Mar 23)
32

Page 33

As at 10 December 2022
Total Number of Employees
F/T P/T F/T P/T
1235 233 203 1392
Director Grade 1 Grade 2 Grade 3 Grade 4 Grade 5 Grade 6 Fixed SCP Teacher TOTAL
1.00 1471.04 386.49 233.64 44.23 17.00 2.00 5.00 0.00 2160.4
As at 10 September 2022
Total Number of Employees
F/T P/T F/T P/T
1287 236 206 1408
Director Grade 1 Grade 2 Grade 3 Grade 4 Grade 5 Grade 6 Fixed SCP Teacher TOTAL
1.00 1525.42 397.39 233.22 45.23 17.00 2.00 9.60 0.00 2230.86
Appendix 3
JOINT STAFFING WATCH RETURN
COMMUNITY AND ENTERPRISE RESOURCES
*Full - Time Equivalent No of Employees
Salary Bands
3063
MALE FEMALE TOTAL
*Full - Time Equivalent No of Employees
Salary Bands
MALE FEMALE TOTAL
3137
33

Page 34

34

Page 35

Report
Agenda Item 
Report to: Community and Enterprise Resources Committee
Date of Meeting: 14 March 2023
Report by: Executive Director (Community and Enterprise
Resources)  
Subject: Revocation of Lanark Air Quality Management Area –
South Lanarkshire 
1. Purpose of Report
1.1. The purpose of the report is to:-
[purpose]
 update the Committee on improvements to air quality within the Lanark area and
the subsequent proposal to revoke the Lanark Air Quality Management Area
(AQMA) 
2. Recommendation(s)
2.1. The Committee is asked to approve the following recommendation(s):-
[recs]
(1) that it be approved that Environmental Services proceed to revoke the Lanark
AQMA.
[1recs]
3. Background
3.1. South Lanarkshire Council has a statutory duty to monitor the quality of air within its
area. This is defined in the Environment Act 1995 and details provided within the Air
Quality (Scotland) Regulations 2000 and 2002 as amended. The results of the
monitoring must be considered against the air quality objectives/targets. Should an air
quality objectives/target be exceeded the local authority must take action to improve
air quality. Exceedances were previously found in East Kilbride, Rutherglen and
Lanark which resulted in the declaration of 3 AQMAs for these areas. 
3.2. An AQMA encompassing the whole town of Lanark was declared in June 2016 due to
likely breaches of the Nitrogen Dioxide (NO2) hourly mean and annual mean air quality
objectives/targets. 
3.3. The formal declaration process for the AQMAs and the resultant Air Quality Action
Plan development have been detailed in previous Committee reports dated 3 June
2008, 11 November 2008, 8 December 2015 and 19 March 2019. 
3.4. Environmental Services has supported traffic management and air quality
improvement actions since 2016.  Lanark specific initiatives included:- 
 Beat the Street’ and ‘Lanark on the Move’ which support the uptake of active and
sustainable travel choices for short local journeys. 
 Improvements to traffic flow to ease congestion in sensitive locations has been
facilitated by improvements to traffic signalling, in conjunction with colleagues in
Roads and Transportation.
6
35

Page 36

 Electric vehicle charging was introduced in Lanark to support the transition to
lower emission vehicles.
 A number of engine idling campaigns and vehicle emission testing events have
taken place locally to increase awareness of the impact vehicle emissions can
have on health.
 The local projects are supported by South Lanarkshire wide initiatives including
fleet and emission tailored support to fleet and taxi operators through the Eco
Stars project.
 Support to encourage the uptake of cycling via the ‘Love to Ride South
Lanarkshire’ project as well as South Lanarkshire’s walking and cycling
campaign.   
3.5. Collectively, the above interventions have resulted in improved traffic flow and
pollutant reduction. 
4. Current Position
4.1. Measured NO2 concentrations have declined over recent years, supporting a Detailed
Assessment of Air Quality at Lanark for NO2 and Particulate Matter (PM2.5). The
Detailed Assessment demonstrated air quality has improved and air quality
objectives/targets currently, and in future, will not be exceeded. A copy of the
executive summary from the Detailed Assessment report is included at Appendix 1. 
4.2. The Detailed Assessment reviewed pollutant measurements over the previous 10
years concluding:- 
 The annual mean for NO2 of 40µgm-3 was exceeded in 2013 and since then
measured concentrations have declined in general at all measurement sites. In
2019 all measured concentrations were significantly less than the Scottish
objective for NO2. 
 To avoid the possibility of re-declaring for PM2.5 at a future date, a review of
measured PM2.5 data was undertaken. This indicated annual mean
concentrations have been consistently below the Scottish objective of 10µgm-3
for PM2.5 since monitoring for this pollutant began in 2015. 
4.3. Dispersion modelling study of current and future road traffic NO2 and PM2.5 emissions
indicated:-  
 In 2019, the NO2 and PM2.5 annual mean objectives were not exceeded at any
locations where relevant human exposure is present within the study area.
 The sensitivity analysis conducted using meteorological dataset from 2009
through to 2019 indicates that is unlikely that exceedances of the NO2 or PM2.5
annual mean objective will occur at these receptor locations due to inter-annual
variability in weather conditions.
 In 2025, when likely traffic growth and inter-annual variability in weather
conditions are considered, the NO2 and PM2.5 annual mean are not predicted to
exceed the Scottish objectives at any locations where relevant human exposure
is present within the study area.
 In 2025 with future developments, the NO2 and PM2.5 annual means are not
predicted to exceed the Scottish objectives at any locations where relevant
human exposure is present within the study area. 
4.4. The Council’s Annual Progress Report on air quality together with the Detailed
Assessment have been submitted to the Scottish Government and Scottish
Environment Protection Agency (SEPA) for appraisal as part of statutory reporting
36

Page 37

requirements. Both reports conclude the Lanark AQMA should now be revoked under
Section 83(2) of the Environment Act 1995. The findings of both reports have been
accepted by the Scottish Government and SEPA. 
4.5. In view of the conclusions of the Detailed Assessment of Air Quality in Lanark and
acceptance of the findings by Scottish Government and SEPA, Environmental
Services recommends South Lanarkshire Council revokes the Lanark AQMA. 
4.6. Following acceptance of the recommendation, the Revocation Order will be drawn up
in conjunction with Legal Services and the Order advertised among statutory
consultees before coming into effect spring/summer 2023. 
5. General/Other Implications for the Council
5.1.  Where a local authority considers it necessary to revoke an AQMA the Scottish
Government expects the authority to consult SEPA. For the Lanark proposed
revocation this consultation has already taken place. In addition, it is also expected
that the local authority consults statutory consultees, businesses, members of the
public and other interested parties. 
5.2. Once the consultation process has been completed, Environmental Services would
submit the Revocation Order to the Scottish Government for information. 
5.3. Where a Revocation Order is accepted, local authorities are expected to consider
drawing up a Local Air Quality Strategy to ensure air quality maintains a high profile
locally and to respond to public expectations. Such a strategy should incorporate
measures designed to tackle climate change. It should also cover the linkages
between air quality and wider environmental sustainability issues. Environmental
Services will seek to develop such a Strategy during 2023/2024. 
5.4. Environmental Services plans to continue air monitoring at the existing automatic air
station for a year following revocation of the AQMA to demonstrate the decision to
revoke was justified. Environmental Services will report this monitoring through the
Annual Progress Report to the Scottish Government and SEPA on compliance with
the national air quality statutory objectives. 
6. Employee Implications
6.1. There are no employee implications. 
7. Financial Implications
7.1. Advertising costs for the consultation and publicising of the Revocation Order, will be
met from the existing Environmental Services’ budget. 
8. Climate Change, Sustainability and Environmental Implications
8.1. In accordance with the requirements of the Environmental Assessment (Scotland) Act
2005, a Strategic Environmental Assessment is not required as the revocation of the
Air Quality Management Area is not a policy, plan, programme or strategy as defined
by the Act. However, a Strategic Environmental Assessment will be carried out
alongside the development of an Air Quality Strategy. 
9. Other Implications
9.1. There are no other significant implications as result of the contents of this report.    
37

Page 38

10. Equality Impact Assessment and Consultation Arrangements
10.1. This report does not introduce a new policy, function or strategy or recommend a
change to an existing policy, function or strategy and, therefore, no equality impact
assessment or consultation is required 
David Booth
Executive Director (Community and Enterprise Resources) 
22 February 2023 
Link(s) to Council Values/Priorities/Outcomes
 Focused on people and their needs
 We will work towards a sustainable future in sustainable places
 We will work to recover, progress and improve
 Caring, connected, sustainable communities
 People live the healthiest lives possible
 Good quality, suitable and sustainable places to live 
Previous References
 Community Resources Committee 3 June 2008 - Air Quality Management Area
 Community Resources Committee 11 November 2008 - Air Quality Management Area –
Whirlies Roundabout East Kilbride
 Community Resources Committee 8 December 2015 - Air Quality Management Area –
Rutherglen
 Community Resources Committee 8 December 2015 - Air Quality Management Area –
Lanark
 Community and Enterprise Resources Committee 4 February 2020 - Air Quality Action
Plan – Beat the Street – Lanark and Rutherglen 
List of Background Papers
 Environment Act 1995
 Air Quality (Scotland) Regulations 2000
 Air Quality (Scotland) Amendment Regulations 2002 and subsequent amendments 
Contact for Further Information
If you would like to inspect the background papers or want further information, please
contact:-
Craig Brown, Environmental Services Manager
Tel: 07795453408
E-mail: Craig.M.Brown@southlanarkshire.gov.uk  / Craig.Brown2@southlanarkshire.gov.uk  
38

Page 39

Appendix 1 
Detailed Assessment to the revocation of Lanark AQMA, South Lanarkshire
Executive Summary. 
Ricardo Energy and Environment have been commissioned by South Lanarkshire Council to
undertake a Detailed Assessment of Air Quality at Lanark, South Lanarkshire. 
An Air Quality Management Area (AQMA) encompassing the whole town of Lanark was
declared in June 2016 due to likely breaches of the Nitrogen Dioxide (NO2) hourly mean and
annual mean air quality objectives. 
Measured NO2 concentrations have declined over recent years; on this basis, South
Lanarkshire Council are currently considering revocation of the Lanark AQMA. This Detailed
Assessment aims to provide evidence that will aid the Council in deciding if revocation is
appropriate, or if an AQMA is still required in Lanark or may be required in the future. 
The assessment includes the following main elements:- 
 A review of measured NO2 concentrations within the AQMA over recent years.
 Detailed dispersion modelling of NO2 concentrations for the most recent year of 2019 
 A sensitivity analysis of potential fluctuations in annual mean pollutant concentrations
attributable to meteorological conditions. 
 Detailed dispersion modelling of NO2 concentrations in a future year (with estimates
of road traffic emissions attributable to future housing allocations in/around the AQMA
included). 
 A review and detailed dispersion model of PM2.5 in 2019 and future years. Although
Lanark does not have an AQMA declaration for exceedance of PM2.5, the pollutant
was included in this assessment to avoid the possibility of re-declaring an AQMA for
PM2.5  at a future date. 
The review of pollutant measurements over the last ten years has concluded:- 
 An annual mean in excess of the NO2 40 µg.m-3 objective was measured once at the
Bloomgate diffusion tube in 2013. Since then, measured concentrations have in
general declined at all measurement sites. In 2019, all measured concentrations were
significantly less than the 40µg.m-3 objective. 
 For PM2.5, annual mean concentrations have been consistently below the Scottish
objective of 10 μg.m-3 since monitoring began in 2015. 
The dispersion modelling study of current and future road traffic NO2 and PM2.5  emissions
indicated that:- 
 In 2019, the NO2 and PM2.5  annual mean objectives were not exceeded at any
locations where relevant human exposure is present within the study area. 
 The sensitivity analysis conducted using meteorological dataset from 2009 through to
2019 indicates that is unlikely that exceedances of the NO2 or PM2.5  annual mean
objective will occur at these receptor locations due to inter-annual variability in weather
conditions. 
 In 2025, when likely traffic growth and inter-annual variability in weather conditions are
considered, the NO2 and PM2.5  annual mean are not predicted to exceed the Scottish
objectives at any locations where relevant human exposure is present within the study
area.
39

Page 40

 In 2025 with future developments, the NO2 and PM2.5  annual means are not predicted
to exceed the Scottish objectives at any locations where relevant human exposure is
present within the study area 
In light of the conclusions of this Detailed Assessment of Air Quality, South Lanarkshire
Council may wish to consider revocation of the Lanark Air Quality Management Area at this
time.
40

Page 41

Report
Agenda Item 
Report to: Community and Enterprise Resources Committee
Date of Meeting: 14 March 2023
Report by: Executive Director (Community and Enterprise
Resources)  
Subject: Zero Carbon Indoor Multi Sports Facility Proposal at
Strathaven Rugby Club 
1. Purpose of Report
1.1. The purpose of the report is to:- 
 provide information on a planning application submitted by Strathaven Rugby
Club (SRC) to add an indoor training facility (“the Facility”) to their current
establishment
 seek approval to support the Facility with funds from the Strathaven Community
Sports and Sports Facilities Fund (“the Funds”) created in accordance with an
agreement under Section 75 of the Town and Country Planning (Scotland) Act
subject to an appropriate legal agreement being entered into between the Council
and SRC
[1purpose]
2. Recommendations
2.1. The Committee is asked to approve the following recommendation(s):-
[ 
(1) that subject to the grant of the Planning Application on acceptable terms to the
Council, the release of the Funds totalling £387,473 to support the Facility be
approved;
(2) that the Funds shall not be released until an appropriate legal agreement has
been concluded between the Council and SRC be noted. This legal agreement
shall cover, amongst other things, the:-
 level and phasing of payments of the Funds
 the requirement that the Facility shall serve the local community at large
 the ability for the Council to clawback the Funds for use on alternative
community projects if the Funds are not used within a certain timescale;
and
(3) that authority be delegated to the Executive Director (Community and
Enterprise Resources) in consultation with the Head of Administration and
Legal Services to conclude the legal agreement be approved. 
3. Background
3.1. In September 2022 SRC submitted a planning application to the Council for the
Facility as part of their continued development of the Club. 
3.2. SRC has requested funding from the Council to help support the Facility. 
3.3. The Strathaven Community and Sports Facility Fund was established as part of an
agreement made under section 75 of the Planning Act between the Council and
Henry Jardine Patterson and Mrs Jean Watson Patterson, registered in the Land
7
41

Page 42

Register of Scotland (“the Section 75 Agreement”) on 23 December 2014.  This
agreement was pursuant to Planning Application EK/12/0003. Section 5.4 of this
report outlines the policy tests which are required to be met with regards to
developer contributions and section 75 agreement. 
4. Zero Carbon Indoor Multi Sports Facility
4.1. SRC’s planning application for the Facility states that the purpose of their
organisation is to ‘provide sporting facilities for a large rural area’ and their aim is to
‘provide an indoor training facility which can accommodate training and general
exercise in all weathers’ and will be built ‘in line with carbon neutral standards
complying with the governments carbon net zero by 2035’. 
4.2. SRC have advised that initial quotes received for the build range from £920,000 to
£1.1 million, and that from commencement of the construction the programme will be
28 weeks.  In addition to the request for funds from the Council, SRC are seeking
funding from the Scottish Rugby Union, and will also look to match fund through
other identified opportunities including Virador, Sports Scotland, Banks Renewables
and the National Lottery. 
4.3. The Facility will allow for the provision of two rugby ready 3G pitches and one hard
sports surface.  In addition to the playing surfaces, there will be an area for gym
equipment, fitness classes and space for local boxing club to include a boxing ring
for training purposes. 
4.4. The Facility will include solar panels on the roof which will power the building and
provide energy to tesla storage batteries to deliver clean electricity to external
floodlights.  Externally the plan includes planting trees in line with carbon neutral
principles to help provide clean air within the town of Strathaven whilst shielding the
Facility from the road and local homeowners. 
4.5. SRC believes that through the addition of the Facility, along with continued
engagement with other clubs and groups within the area, they can achieve their goal
of becoming a community hub allowing them to develop other aspects of sport to use
the facilities, develop further partnerships with other community groups and to further
develop their existing partnership with all local schools. 
4.6. Current membership for SRC is 546 and it is anticipated membership could increase
by 10% based on numbers of players and parents who have intimated that they
would return if an indoor facility was introduced. In addition, the facility will be used
by Strathaven Dynamo who have more than 500 members, Strathaven Striders who
have 80 members and the netball club who have 30 members. 
4.7. SRC also state that their ‘main aim as a club is to reduce social isolation among all
age groups promoting fitness and mental health wellbeing for all regardless of age,
gender or ability’.  The entire facility will be disabled friendly allowing for provision of
wheelchair rugby and development of a growing walking rugby club, attracts older
members. 
4.8. Facilities at the Club are currently well used by the local community for other types of
sport including football, hockey, cricket, yoga and jogging and have letters of support
from several local organisations.   
5. Developers Contributions
5.1.  The total and final balance of Council funds held in the Strathaven Community and
Sports Facility Fund is £387,473.
42

Page 43

5.2. SRC have requested that the Council considers releasing the Funds to contribute
towards the Facility. 
5.3. The section 75 agreements provide that the Strathaven Community and Sports
Facility Fund will be administered and used by the Council in consultation with the
initial owner of the East Overton land (Initial Owner). The Initial Owner has been
consulted in relation to the proposal and supports the application for the Facility. 
5.4. In addition, planning obligations require to meet the policy tests under Scottish
Government Circular 3/2012 in that they need to be:- 
 necessary to make the proposed development acceptable in planning terms
(paragraph 15)
 serve a planning purpose (paragraph 16)
 where it is possible to identify infrastructure provision requirements in advance
should relate to development plans, relate to the proposed development either
as a direct consequence of the development or arising from the cumulative
impact of development in the area (paragraphs 17 to 19)
 fairly and reasonably relate in scale and kind to the proposed development
(paragraphs 20 to 23) and be reasonable in all other respects (paragraphs 24 to
25) 
5.5. The Council, therefore, must ensure that we are using the Strathaven Community
and Sports Facility Fund appropriately, considering the Section 75 Agreement, and
the legal restrictions and guidance relating to the proper use of developer
contributions, whilst assessing the project meets the threshold of suitability. 
5.6. The Council considers that the addition of the Facility, will deliver leisure and
recreational benefits to the increased population in Strathaven, which has arisen as a
result of the new housing development.  Not only this, but the new provision and will
address a gap in the leisure offer within the area. It is recognised that the club is one
of the main pillars of sport and recreational activity for the local community, and the
proposed project extends this position, as well as helping in the overall journey to net
zero.  Other benefits of the Facility to the area are highlighted at items 4.1 to 4.4
above. 
6. Legal Agreement
6.1. It is proposed that releasing monies from the Fund for this project will require to be
underpinned by an appropriate legal agreement. The agreement will include the
conditions that SRC would need to adhere to in order to access the funds, including
demonstrating that the project will benefit the wider community, and officers will
engage with the club in this respect. 
6.2. As part of entering into a legal agreement the Council will ensure that we work
through legal governance. 
6.3. The Council through the legal agreement would also ensure that monies would be
released in phases and through approval of work stages.  There would also be a cap
on the amount which would be released and the ability to clawback monies if the
project did not adhere to set conditions. 
7. Employee Implications
7.1. There are no employee implications as a result of this report.  All staffing for the
Facility is provided by Strathaven Rugby Club.
43

Page 44

8. Financial Implications
8.1. The proposed funding for the facility will be drawn from the Strathaven Community
Sports and Sports Facilities Fund and concerns the allocation of £387,473 subject to
the conditions outlined in the report. 
9. Climate Change, Sustainability and Environmental Implications
9.1. The Strathaven Rugby Club state that this new Zero Carbon Indoor Multi Sports
Facility will be built ‘in line with carbon neutral standards complying with the
government’s carbon net zero by 2035’. 
9.2. Having low carbon facilities within South Lanarkshire communities ties in with the
objectives of the Council’s Sustainable Development and Climate Change Strategy
(SDCCS). Providing communities with a safe and accessible sports hub promotes
good health and wellbeing, one of the global sustainable development goals which is
also supported by the Council’s SDCCS. 
10. Other Implications
10.1. The main aim of SRC (as detailed in section 4.3) aligns with SLLC’s vision for
‘healthier, happier, more connected lives’, and the Council’s vision to ‘improve the
lives and prospects of everyone in South Lanarkshire. 
11. Equality Impact Assessment and Consultation Arrangement
11.1. This report does not introduce a new policy, function or strategy or recommend a
change to an existing policy, function or strategy and, therefore, no impact
assessment is required. 
David Booth
Executive Director (Community and Enterprise Resources) 
22 February 2023 
Link(s) to Council Values/Priorities/Outcomes
Values
 Focused on people and their needs
 Working with and respecting others
 Accountable, effective, efficient and transparent
 Fair, open and sustainable 
Priorities
 We will work to put people first and reduce inequality
 We will work towards a sustainable future in sustainable places
 We will work to recover, progress and improve 
Outcomes
 Our children and young people thrive
 Caring, connected, sustainable communities
 People live the healthiest lives possible
 Inspiring learners, transforming learning, strengthening partnerships 
44

Page 45

Previous References
 None 
List of Background Papers
 None 
Contact for Further Information
If you would like to inspect the background papers or want further information, please
contact:- 
Elaine Melrose (Development Officer) 
E-mail:  elaine.melrose@southlanarkshire.gov.uk
45

Page 46

46

Page 47

Report
Agenda Item 
Report to: Community and Enterprise Resources Committee
Date of Meeting: 14 March 2023
Report by: Executive Director (Community and Enterprise
Resources)
Executive Director (Finance and Corporate Resources) 
Subject: Ash Dieback Disease Programme – Arboriculture
Operatives (Trainee) 
1. Purpose of Report
1.1. The purpose of the report is to:-
[purpose]
 update the Committee on a programme of work required on Ash Dieback Disease
(ADD) following allocation of capital funding
 seek approval for 3.0 FTE Arboriculture Operatives (Trainees) to be added to the
Resource’s establishment for a fixed-term of 12 months
[1purpose]
2. Recommendation(s)
2.1. The Committee is asked to approve the following recommendation(s):- 
(1) that the contents of the report be noted; and
(2) that it be approved that 3.0 FTE Arboriculture Operatives (Trainees) be added
to the Grounds Services establishment for a fixed-term of 12 months, as
detailed in section 5. 
3. Background
3.1. ADD is the most significant tree disease to affect broadleaved trees in the UK since
Dutch elm disease gained prominence in the 1960s. It has spread rapidly, with only a
small fraction of trees proving resistant due to genetic factors which give them
tolerance to the disease. This incurable disease is caused by the fungal pathogen
Hymen scyphus fraxineus and affects just ash species. Data from Europe suggests it
will lead to the decline and death of 50% to 75% of ash trees in Scotland over the next
two decades and has the potential to infect more than 75 million ash trees across the
country. ADD was first recorded in the UK and South Lanarkshire in 2012. 
3.2. The national cost of managing trees with ash dieback (which could include monitoring,
pruning and, where necessary, felling) is difficult to calculate but it has been estimated
that is likely to exceed £2.5 billion across the UK in the next 10 years. As part of that,
Scotland’s costs could potentially be in the region of £200 million. This disease will
cost more than just lost habitats for wildlife and treasured woods for recreation. A new
estimate of the economic cost by APSE, puts the price tag at £14.8 billion, which is
around 3 times as much as estimates for the Dutch Elm disease crisis in the 1960s
and 1970s, largely because there are far more ash trees. 
8
47

Page 48

3.3. Ash trees infected with ADD display crown decline resulting in deadwood/dead stems
at height that may be within striking distance of a target/road. This can often be
accompanied by vigorous sprouting on the trunk or branches forming in bundles
creating almost ‘pom-pom’ like clumps of crowded foliage. The infected trees can
become unpredictably brittle in structure, and at a later stage more problematic and
hazardous, and as a result more expensive to remove. Risks are site specific, and
target based, but viability is questioned at +/- 50% remaining canopy which is also the
same point that climbing by arborists becomes unviable/unsafe. Tree death in less
than 4 growing seasons is not unknown. 
3.4. Current guidance is that given the scale of health and safety risks caused by ADD
alone will mean that it will ‘not be business as usual’ for any organisation who manage
ash trees. The management of Ash Dieback is proving a real challenge for tree
managers as to whether trees should be felled, or allowed to stand, in order to develop
resistance to the disease and protect species which are reliant upon the Ash for their
home. 
4. Investment Proposals
4.1. South Lanarkshire Council through the Arboriculture team has participated in a
number of national initiatives with key stakeholders such as The Forestry Commission,
the Tree Council and the Scottish Government to develop policy and processes in the
country’s response to the ADD problem. The Council has also now included ADD in
the corporate risk register as well as the Sustainable Development and Climate
Change Strategy. 
4.2. A pilot investigation has now been undertaken following allocation of funding over the
last year and this has identified an initial programme of work to further quantify the
scale of the issue and respond to immediate concerns. The Council has allocated a
£0.500 million in the 2023/2024 Capital Programme and this will be utilised to deliver
that programme of work. 
4.3. This will require additional resources and given the challenges in the arboriculture
sector it is intended to establish 3 temporary trainee positions that will allow the team
to reprofile current workload and address succession planning concerns by “growing
our own”. 
5. Employee Implications
5.1. If approved, the following posts will be added to the Grounds Services establishment
as detailed below for a 12-month period:  
Post FTE   Grade/SCP Hourly
Rate
Annual
Salary
Gross
Cost (inc
on costs)  
Total (12
months)
Arboriculture
Operative
(Trainee) –
Temporary
3.0 Grade 1,
Level 2,
SCP 22 - 23
£11.41 -
£11.55
£22,011 -
£22,282
£28,681 -
£29,033 
£86,043 - 
£87,099  
6. Financial Implications
6.1. Funding of £0.500 million has been allocated from the 2023/2024 Capital Programme
to deliver this programme of work. Around £0.087 million will be utilised on staffing
costs and the remaining £0.413 million on vehicles, equipment, materials and other
contractor costs.
48

Page 49

7. Climate Change, Sustainability and Environmental Implications
7.1. If not effectively managed, Ash Dieback has the clear potential to lead to long lasting
changes in our landscape, tree populations and canopy cover, loss of ecosystem
services and may potentially increase effects such as flooding and reduce carbon
lockup. 
8. Other Implications
8.1. There are no other significant implications as result of the contents of this report 
9. Equality Impact Assessment and Consultation Arrangements
9.1. There are no equality impact assessment implications arising for this report. 
David Booth
Executive Director (Community and Enterprise Resources) 
Paul Manning
Executive Director (Finance and Corporate Resources) 
24 February 2022 
Link(s) to Council Values/Priorities/Outcomes
 We will work towards a sustainable future in sustainable places
 We will work to recover, progress and improve
 Caring, connected, sustainable communities
 Good quality, suitable and sustainable places to live 
Previous References
 None 
List of Background Papers
 None 
Contact for Further Information
If you would like to inspect the background papers or want further information, please
contact:-
Kevin Carr
Head of Facilities, Waste and Grounds Services
Tel:  01698 454708
E-mail:-  kevin.carr@southlanarkshire.gov.uk 
49

Page 50

50

Page 51

Report
Agenda Item 
Report to: Community and Enterprise Resources Committee
Date of Meeting: 14 March 2023
Report by: Executive Director (Community and Enterprise
Resources)  
Subject: Community and Enterprise Resource Plan - Quarter 2
Progress Report 2022/2023 
1. Purpose of Report
1.1. The purpose of the report is to:-
[purpose]
 provide the Community and Enterprise Resource Plan Quarter 2 Progress
Report 2022/2023, for the period 1 April to 30 September 2022
[1purpose]
2. Recommendations
2.1. The Committee is asked to approve the following recommendation(s):-
[
(1) that the Community and Enterprise Resource Plan Quarter 2 Progress Report
2022/2023, as summarised in paragraph 5.2. and attached as Appendix 2 of
this report, be noted; 
(2) that the key achievements made by the Resource up to Quarter 2, as detailed
in paragraph 5.3. of this report, be noted; and
(3) that the areas for improvement and associated management actions, as
detailed in paragraph 5.4. of this report, be noted. 
3. Background
3.1. The Community and Enterprise Resource Plan 2022/2023 was approved by the
Executive Committee on 24 August 2022, and subsequently noted by the
Community and Enterprise Resources Committee on 4 October 2022.  The Plan sets
out the strategic outcomes and actions to be managed and delivered by the
Resource for the financial year 2022/2023.   
3.2. The Resource Plan follows the agreed corporate structure and style. The Plan is a
key element of the Council’s performance management arrangements and provides
details of the context within which the Resource operates and establishes actions
and measures for the year ahead based on the outcomes set out in the Council Plan
Connect 2022 to 2027. 
3.3.  From March 2020 onwards, at times, the Council was forced to suspend or reduce a
number of services that could not be continued in full due to the COVID-19
pandemic. The Council was also obliged to redirect resources so that it could deliver
vital new services and supports for individuals, communities, and businesses.
Despite the return of services through the Council’s Recovery Plan there is a
COVID-19 legacy in terms of a residual impact on some services and a significant
build-up of demand, as a result of which there remains an inevitable impact on
performance in some areas.
9
51

Page 52

4. Resource Outcomes 2022/2023
4.1. The Resource has established a number of outcomes to support the delivery of the
Connect Outcomes in 2022/2023. These are detailed at Appendix 1. 
5. Quarter 2 Progress Report 2022/2023
5.1. Progress against all Resource Plan measures is contained in the Quarter 2 Progress
Report 2022/2023, attached as Appendix 2.  This report has been produced from the
Council’s performance management reporting system IMPROVe, and uses a traffic
light format with the following definitions to give a status report on each measure:  
Status Definition
Blue Project complete
Green The timescale or target has been met as per expectations
Amber There has been minor slippage against timescale or minor shortfall
against target
Red There has been major slippage against timescale or major shortfall
against target
Report
later
The information is not yet available to allow us to say whether the
target has been reached or not.  This will be reported when available
Contextual Included for ‘information only’, to set performance information in context 
5.2. The overall summary of progress as at 30 September 2022 was as follows: 
Status Measures
Statistical Project Number %
Blue 0 3 3 11.6%
Green  6 7 13 50.0%
Amber  1 5 6 23.0%
Red  1 0 1 3.8%
Report later/Contextual 3 0 3 11.6%
Totals  11 15 26 100.0% 
(Data correct as at end September 2022, however, some of the narratives within
Appendix 2 (dated 26 January 2023) have been amended to provide an updated
position for Committee).  
5.3. Key achievements for the first 6 months of 2022/2023, are noted below: 
Connect Outcome Communities and Environment
Resource Outcome Achievement
All roads, footways, cycle
routes, bridges and
associated infrastructure are
safe and fit for purpose
The Roads, Transportation and Fleet Service
were successful in winning the award for ‘Most
Effective in Road Safety, Traffic Management and
Enforcement’ at the Scottish Transport Awards
which were held at the Radisson Blu Hotel in
Glasgow on 29 September 2022.
Road and transportation
infrastructure support new
development enables use of
public transport and
encourages active travel
The major infrastructure phase of the Greenhills
Road/Strathaven Road City Deal Project was
completed in June 2022. The new dual
carriageway enables improved and joined up
regional connections and is hoped to attract
business growth and private investment. 
High-quality streets, parks
and other public areas
ensures South Lanarkshire is
A comprehensive five-year Litter Strategy for
South Lanarkshire was approved by the Climate
Change and Sustainability Committee in August
52

Page 53

a place where people want to
live, work, visit and invest
2022. The Strategy outlines how the Council, its
partners, and the wider community can tackle the
issues. 
Three parks in South Lanarkshire have
successfully retained the Green Flag status
(Strathaven Park, Cambuslang Park and
Castlebank Park). The international Green Flag
Award is administered in Scotland by Keep
Scotland Beautiful and acts as a benchmark for
recreational outdoor space. The award celebrates
well maintained parks and greenspaces and
supports the opportunities that they provide to
enable exercise, improve mental wellbeing and
provide safe areas for play.
The Council addresses
climate change by reducing
carbon emissions, protecting
our natural environment,
adapting to the impacts of
climate change, and acting
sustainably
The new Sustainable Development and Climate
Change Strategy was approved by the Climate
Change and Sustainability Committee in June
2022. The strategy was prepared following
extensive public engagement and builds on the
successes of the previous strategy. The mission
statement of the new strategy is: Our Future is
Now: building a sustainable, climate resilient and
net-zero South Lanarkshire together, in a fair and
inclusive way
It was reported in August 2022 that the Council's
carbon emissions for the year 2021/2022 reduced
by 17% compared with the baseline year
2019/2020. This is partly due to the continued
service disruption throughout the year due to
COVID-19, reductions in national carbon
conversion factors and reduced amounts of
household waste going to landfill. 
Connect Outcome Our Economy 
Resource Outcome Achievement
South Lanarkshire is an
attractive place to start, grow
and locate a business. 
New Economic Development Officers are now in
post to provide targeted support for: 
- social enterprises
- the tourism sector, and 
- locate in South Lanarkshire (investment,
marketing, and funding) 
Our economy is fair,
inclusive, sustainable and low
carbon, with thriving town and
neighbourhood centres which
provide a focal point for local
communities
The first face-to-face ‘Lanarkshire Women in
Business’ event was held in June 2022, with more
than 70 local businesses attending the event at
the Strathaven Hotel. A follow up event was also
held at the Excelsior Stadium in August 2022.
Lanarkshire Women In Business events are
targeted to aspiring and existing business women
as well as those working in business seeking
personal and professional development. 
Connect Outcome Delivering the plan and chieving Best Value  
Resource Outcome Achievement
The Council demonstrates New governance arrangements between South
53

Page 54

high standards of governance
and sound financial
stewardship 
Lanarkshire Council and South Lanarkshire
Leisure and Culture Ltd were approved at the Full
Council meeting on 15 June 2022. 
5.4. Areas for improvement
One measure has been classified as “red” (major slippage against timescale or
shortfall against target). This is detailed below, together with the reason why, and the
management action being taken. 
Communities and Environment 
Resource Outcome:   Communities are encouraged and supported to reduce,
re-use and recycle their waste
Measure Comments/Progress Action by Manager 
Percentage of total
household waste
that is recycled 
This measure is reported per
calendar year. The figure for
quarter two (April to June
2022) was 45.07%, which is
an improvement on the
previous quarter. The year to
date figure of 40.28%,
however, is below the 2021
figure (41.50%) and remains
below the target of 50.00%. 
Higher residual waste
tonnages collected at the
kerbside due to
homeworking, high residual
waste content in bulk uplifts
(black bag waste accepted),
and more non-recyclable
waste being disposed of in
Household Waste Recycling
Centres, are all factors that
need to be taken into account
when understanding the
household waste recycling
performance
A new contract is now in
place for bulky waste (from
1 April 2022). This has
increased the amount of
bulky waste being recycled.
The service is also currently
recruiting Waste Education
Officers to roll out a new
service change for flatted
properties to try and
improve the recycling rate.
Currently the majority of the
material is too badly
contaminated to recycle and
ends up being disposed of
as residual waste. 
All Resource Plan red and amber measures as at Quarter 2 were reported to the
Performance Review Scrutiny Forum on 29 November 2022. 
5.5.  Report Later / Contextual 
Measures in the quarterly progress report which are not red, amber, green or blue
can be assigned a status of ‘report later’ or ‘contextual’. At quarter two, there were
three measures with ‘report later’ status, and these will be reported once the
information becomes available.  An update on the status of the 6 measures identified
as ‘report later’ as at Quarter 4 of 2021/2022, is included in Appendix 3. 
6. Employee Implications
6.1. The outcomes noted within the Resource Plan will inform the Service Action Plans,
where applicable, and in turn the Performance Appraisal process for individual
employees. 
54

Page 55

6.2. Absence statistics are monitored and reported through the Council-wide workforce
monitoring report which is presented to each Resource Committee and the
Employees Issues Forum. The absence rate for Community and Enterprise
Resources from April 2022 to September 2022 was 6.5%, which is higher than the
Council-wide figure of 5.1%. 
7. Financial Implications
7.1. The outcomes within the Resource Plan are reflected in the respective annual
Resource Revenue and Capital budgets and, longer term, within the framework of
the Council’s approved Financial Strategy. 
8. Climate Change, Sustainability and Environmental Implications
8.1. There are no climate change or environmental implications as a result of this report,
however, a number of actions within the Resource and Service Plans contribute
positively to the Council’s Sustainable Development and Climate Change Strategy. 
8.2. The Resource Plan takes into account the Resource’s responsibilities in relation to
sustainable development and climate change. 
9.  Other Implications
9.1. The Community Plan 2022 to 2032 was agreed at the Community Planning
Partnership Board on 22 June 2022.  A significant element of the delivery of the
outcomes in the Community Plan will come through the achievement of the
outcomes and actions contained within Connect. 
9.2. Resource Plan actions are assessed as part of the Resource’s risk management
arrangements and relevant issues have been added to the Resource Risk Register. 
10. Equality Impact Assessment and Consultation Arrangements
10.1. Many of the actions detailed within the Resource Plan reflect ongoing strategies and
policies which will be or have been the subject of consultation and equality impact
assessment. 
David Booth
Executive Director (Community and Enterprise Resources) 
21 February 2023 
Link(s) to Council Values/Priorities/Outcomes
Values
 Focused on people and their needs
 Working with and respecting others
 Accountable, effective, efficient and transparent
 Ambitious, self-aware and improving
 Fair, open and sustainable
 Excellent employer 
Priorities
 We will work to put people first and reduce inequality
 We will work towards a sustainable future in sustainable places
 We will work to recover, progress and improve 
55

Page 56

Outcomes
 Our children and young people thrive
 Good quality, suitable and sustainable places to live
 Thriving business, fair jobs and vibrant town centres
 Caring, connected, sustainable communities
 People live the healthiest lives possible
 Inspiring learners, transforming learning, strengthening partnerships 
Previous References
 Community and Enterprise Resources Quarter 4 Progress Report 2021/2022 - 4
October 2022 
List of Background Papers
 Council Plan Connect 2022 to 2027 – approved by the full Council on 15 June 2022
 Community and Enterprise Resources Plan 2022/2023 – approved by Executive
Committee on 24 August 2022, and noted by Community and Enterprise Resources
Committee on 4 October 2022 
Contact for Further Information
If you would like to inspect the background papers or want further information, please
contact:-
Gillian Simpson (Development Adviser)
E-mail:  gillian.simpson@southlanarkshire.gov.uk
56

Page 57

Appendix 1
Community and Enterprise Resource Outcomes 2022/2023   
Connect Outcomes Resource Outcomes  
Communities and
Environment 
• High-quality streets, parks and other public areas
ensures South Lanarkshire is a place where people want
to live, work, visit and invest
• Communities are encouraged and supported to reduce,
re-use and recycle their waste
• The Council addresses climate change by reducing
carbon emissions, protecting our natural environment,
adapting to the impacts of climate change, and acting
sustainably
• The Council supports and promotes a fairer, healthier,
and more sustainable food system 
• All roads, footways, cycle routes, bridges and associated
infrastructure are safe and fit for purpose
• Road and transportation infrastructure support new
development, enables use of public transport and
encourages active travel
Education and Learning  • No resource outcomes for this priority 
Health and Wellbeing  • Public health is safeguarded through an effective
environmental regulation and enforcement service
• All school and nursery children have access to nutritious
school meals 
• All residents have the opportunity to access cultural,
leisure and outdoor recreational activities to help improve
their wellbeing and quality of life
Children and Young
People 
• No resource outcomes for this priority 
Housing and Land  • Vacant, derelict and contaminated land is brought back
into productive use
Our Economy  • Our economy is fair, inclusive, sustainable and low
carbon, with thriving town and neighbourhood centres
which provide a focal point for local communities 
• South Lanarkshire is an attractive place to start, grow
and locate a business
• Physical development and land use in the area is
enabled, guided and controlled to help facilitate
economic growth  
• Consumers and communities are protected through an
effective trading standards service 
Delivering the Plan and
achieving Best Value
• Customers experience high quality and improving
Council services
• The Council demonstrates high standards of governance
and sound financial stewardship
• The workforce has the skills, flexibility and capacity to
deliver the Council’s priorities
• Digital and ICT services meet the needs of the Council
and its customers 
57

Page 58

58

Page 59

IMPROVe - SLC Performance Management System                                                                                                                  Report printed on 26 Jan 15:27
Quarter 2 : April 2022 - September 2022
Community and Enterprise Resources
Resource Plan
(This represents the cumulative position to September 2022)
Performance Report 2022-23
9
59

Page 60

IMPROVe - SLC Performance Management System                                                                                                                  Report printed on 26 Jan 15:27
Summary - number of measures green, amber and red under each Council Plan Outcome /
Theme
Council Outcome/ Theme Green Amber Red Report later /
Contextual
Total
Communities and Environment 2 1 1 3 7
Education and Learning 0 0 0 0 0
Health and Wellbeing 1 0 0 0 1
Children and Young People 0 0 0 0 0
Housing and Land 0 0 0 0 0
Our Economy 3 0 0 0 3
Delivering the plan and achieving best value 0 0 0 0 0
Total 6 1 1 3 11
Page 1
60

Page 61

IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Thursday 26 January 2023
Resource Plan Performance Indicators Community and Enterprise Resources -
Communities and Environment
High-quality streets, parks and other public areas ensures South Lanarkshire is a place where people want to live, work, visit and invest
Performance Indicators Comments/ Progress Status Target To Date
-------- Last 3 Years ------------------- This Year -----------
Percentage of streets found to be
acceptable during LEAMS survey
The LEAMS survey has now been replaced by the Litter Monitoring
System (LMS). This is a statutory requirement and involves external
validation by Keep Scotland Beautiful.
In 2021-22, South Lanarkshire Council continued to score higher for its
street cleansing service than the Scottish average, with 92.10% of
streets surveyed found to be of an acceptable standard. This is down
slightly from 94.05% in 2020-21.
The LMS results for 2022-23 will be reported as part of the LGBF
framework in early 2024.
Report Later 94.10% ------ 94.80% 94.10% 92.10%
Land Audit Management System grounds
maintenance score
LAMS measures the quality of grounds maintenance based on surveys
which are completed throughout the year. Taking the scores to date (68,
73, 72 and 71), the current overall score is 71. This is slightly below
target, however the final score for 2022-23 will be reported in quarter
four.
Amber 72.0 71.0 72.0 72.0 71.3
Page 2
61

Page 62

IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Thursday 26 January 2023
Resource Plan Performance Indicators Community and Enterprise Resources -
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Thursday 26 January 2023
Resource Plan Performance Indicators Community and Enterprise Resources -
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Thursday 26 January 2023
Resource Plan Performance Indicators Community and Enterprise Resources -
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Thursday 26 January 2023
Resource Plan Performance Indicators Community and Enterprise Resources -
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Thursday 26 January 2023
Resource Plan Performance Indicators Community and Enterprise Resources -
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Thursday 26 January 2023
Resource Plan Performance Indicators Community and Enterprise Resources -
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Thursday 26 January 2023
Resource Plan Performance Indicators Community and Enterprise Resources -
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Thursday 26 January 2023
Resource Plan Performance Indicators Community and Enterprise Resources -
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Thursday 26 January 2023
Resource Plan Performance Indicators Community and Enterprise Resources -
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Thursday 26 January 2023
Resource Plan Performance Indicators Community and Enterprise Resources -
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Thursday 26 January 2023
Resource Plan Performance Indicators Community and Enterprise Resources -
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Thursday 26 January 2023
Resource Plan Performance Indicators Community and Enterprise Resources -
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Thursday 26 January 2023
Resource Plan Performance Indicators Community and Enterprise Resources -
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Thursday 26 January 2023
Resource Plan Performance Indicators Community and Enterprise Resources -
Communities and Environment
Communities are encouraged and supported to reduce, re-use and recycle their waste
Performance Indicators Comments/ Progress Status Target To Date
-------- Last 3 Years ------------------- This Year -----------
Percentage of total household waste that is
recycled in 2022
Measure is reported per calendar year. The figure for quarter two (April
to June 2022) was 45.07%. This equates to 40.28% for the year to date
(2022). This is below the 2021 figure of 41.50%, and remains below the
target figure of 50.00%.
Higher residual waste tonnages collected at the kerbside due to
Covid-19 and home-working, high residual waste content in bulk uplifts
(black bag waste accepted), and more non-recyclable waste being
disposed of in Household Waste Recycling Centres, are all factors that
need to be taken into account when understanding the household waste
recycling performance.
A new contract is now in place for bulky waste (from 1 April 2022), and
this has increased the amount of bulky waste being recycled. the
previous contract only managed approximately 15% however the new
contract is now recycling over 50% of this waste.
The service is also currently recruiting Waste Education Officers to roll
out a new service change for flatted properties to try and improve the
recycling rate. Currently the majority of the material is too badly
contaminated to recycle and ends up being disposed of as residual
waste.
Red 50.00% 40.28% 46.40% 40.50% 41.50%
Page 3
62

Page 63

IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Thursday 26 January 2023
Resource Plan Performance Indicators Community and Enterprise Resources -
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Thursday 26 January 2023
Resource Plan Performance Indicators Community and Enterprise Resources -
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Thursday 26 January 2023
Resource Plan Performance Indicators Community and Enterprise Resources -
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Thursday 26 January 2023
Resource Plan Performance Indicators Community and Enterprise Resources -
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Thursday 26 January 2023
Resource Plan Performance Indicators Community and Enterprise Resources -
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Thursday 26 January 2023
Resource Plan Performance Indicators Community and Enterprise Resources -
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Thursday 26 January 2023
Resource Plan Performance Indicators Community and Enterprise Resources -
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Thursday 26 January 2023
Resource Plan Performance Indicators Community and Enterprise Resources -
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Thursday 26 January 2023
Resource Plan Performance Indicators Community and Enterprise Resources -
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Thursday 26 January 2023
Resource Plan Performance Indicators Community and Enterprise Resources -
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Thursday 26 January 2023
Resource Plan Performance Indicators Community and Enterprise Resources -
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Thursday 26 January 2023
Resource Plan Performance Indicators Community and Enterprise Resources -
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Thursday 26 January 2023
Resource Plan Performance Indicators Community and Enterprise Resources -
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Thursday 26 January 2023
Resource Plan Performance Indicators Community and Enterprise Resources -
Communities and Environment
Communities are encouraged and supported to reduce, re-use and recycle their waste
Performance Indicators Comments/ Progress Status Target To Date
-------- Last 3 Years ------------------- This Year -----------
Percentage of household waste sent to
landfill in 2022
Measure is reported per calendar year. The percentage of household
waste sent to landfill in quarter two (April to June 2022) was 1.5%, and
the year to date figure for 2022 is 1.9%. This is significantly better than
the 10% target.
Viridor prioritise South Lanarkshire Council waste over waste from other
sources at the Dunbar Energy Recovery Facility, and so the council's
residual waste is sent to other Energy from Waste facilities (rather than
landfills) during planned and un-planned outages.
The council also awarded a new contract for bulky waste which contains
provisions to divert more of the waste stream from landfill than under
previous contracts.
Green 10.00% 1.90% ------ 9.71% 8.66%
The council addresses climate change by reducing carbon emissions, protecting our natural environment, adapting to the impacts of climate change, and actingsustainably
Performance Indicators Comments/ Progress Status Target To Date
-------- Last 3 Years ------------------- This Year -----------
Reduction in the council’s carbon
emissions achieved by March 2023
(buildings, waste, street lighting, transport)
The results for financial year 2022-23 will be reported in July 2023.
The results for financial year 2021-22 were calculated and reported to
CMT in August 2022. It was reported that the council's carbon emissions
reduced by 17% compared with baseline year 2019-20. This is partly
due to the continued service disruption throughout the year due to
Covid, reductions in national carbon conversion factors and reduced
amounts of household waste going to landfill.
Report Later 5.0% ------ 44.0% 19.0% 17.0%
Page 4
63

Page 64

IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Thursday 26 January 2023
Resource Plan Performance Indicators Community and Enterprise Resources -
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Thursday 26 January 2023
Resource Plan Performance Indicators Community and Enterprise Resources -
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Thursday 26 January 2023
Resource Plan Performance Indicators Community and Enterprise Resources -
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Thursday 26 January 2023
Resource Plan Performance Indicators Community and Enterprise Resources -
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Thursday 26 January 2023
Resource Plan Performance Indicators Community and Enterprise Resources -
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Thursday 26 January 2023
Resource Plan Performance Indicators Community and Enterprise Resources -
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Thursday 26 January 2023
Resource Plan Performance Indicators Community and Enterprise Resources -
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Thursday 26 January 2023
Resource Plan Performance Indicators Community and Enterprise Resources -
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Thursday 26 January 2023
Resource Plan Performance Indicators Community and Enterprise Resources -
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Thursday 26 January 2023
Resource Plan Performance Indicators Community and Enterprise Resources -
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Thursday 26 January 2023
Resource Plan Performance Indicators Community and Enterprise Resources -
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Thursday 26 January 2023
Resource Plan Performance Indicators Community and Enterprise Resources -
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Thursday 26 January 2023
Resource Plan Performance Indicators Community and Enterprise Resources -
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Thursday 26 January 2023
Resource Plan Performance Indicators Community and Enterprise Resources -
Communities and Environment
All roads, footways and bridges and associated infrastructure are safe and fit for purpose
Performance Indicators Comments/ Progress Status Target To Date
-------- Last 3 Years ------------------- This Year -----------
Percentage of our road network that should
be considered for maintenance treatment
This figure is derived from the Society of Chief Officers of Transportation
in Scotland (SCOTS) Road Condition Index (RCI) survey which is
undertaken each year.
The target figure of 29.7% is based on the results for the period
2020-22.
The RCI for 2021-23 will be published in January 2023 and reported in
quarter four.
Report Later 29.7% ------ 30.3% 30.6% 29.7%
Number of road casualties in South
Lanarkshire during 2022
Provisional casualty figures are available for the eight months of 2022,
when there were 127 casualties. Of these, there were 5 fatal casualties,
38 serious casualties and 84 slight casualties. There were 0 child fatal
casualties, 1 child seriously injured and 7 children slightly injured.
Compared with the same period in 2021, there were 158 casualties. Of
these, there were 6 fatalities, 51 serious casualties and 101 slight
casualties. For children in 2021, there were 0 child fatal casualties,  8
children seriously injured and  11 children slightly injured.
These are provisional 2022 figures and additional records may be added
in addition to the reported figures above.
Green 432 127 431 317 252
Page 5
64

Page 65

IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Thursday 26 January 2023
Resource Plan Performance Indicators Community and Enterprise Resources -
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Thursday 26 January 2023
Resource Plan Performance Indicators Community and Enterprise Resources -
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Thursday 26 January 2023
Resource Plan Performance Indicators Community and Enterprise Resources -
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Thursday 26 January 2023
Resource Plan Performance Indicators Community and Enterprise Resources -
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Thursday 26 January 2023
Resource Plan Performance Indicators Community and Enterprise Resources -
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Thursday 26 January 2023
Resource Plan Performance Indicators Community and Enterprise Resources -
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Thursday 26 January 2023
Resource Plan Performance Indicators Community and Enterprise Resources -
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Thursday 26 January 2023
Resource Plan Performance Indicators Community and Enterprise Resources -
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Thursday 26 January 2023
Resource Plan Performance Indicators Community and Enterprise Resources -
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Thursday 26 January 2023
Resource Plan Performance Indicators Community and Enterprise Resources -
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Thursday 26 January 2023
Resource Plan Performance Indicators Community and Enterprise Resources -
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Thursday 26 January 2023
Resource Plan Performance Indicators Community and Enterprise Resources -
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Thursday 26 January 2023
Resource Plan Performance Indicators Community and Enterprise Resources -
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Thursday 26 January 2023
Resource Plan Performance Indicators Community and Enterprise Resources -
Health and Wellbeing
Public health is safeguarded through an effective environmental regulation and enforcement service
Performance Indicators Comments/ Progress Status Target To Date
-------- Last 3 Years ------------------- This Year -----------
Broad compliance with food law statutory
requirements secured in premises
The rating scheme used to determine broad compliance with food safety
requirements in food businesses operating within South Lanarkshire and
inspected by Environmental Services changed on 1 July 2019. The
previous food law rating scheme focused on broad compliance with food
hygiene requirements only, whereas the new scheme assesses overall
compliance with both food hygiene and food standards legislation.
Under the combined old and new food law rating schemes, 96% were
found to be broadly compliant in the second quarter of 2022-2023 (July -
September 2022).  This equates to 2,641 food businesses.  Year to date,
96% were found to be broadly compliant with both food hygiene and
food standards legislation.
This compliance figure continues to exceed the annual target set for this
measure, and has increased gradually since the new food law rating
scheme has come into affect. This is due to the fact that the new food
law rating scheme allows local authorities to focus resources on high
risk and non-compliant businesses by conducting more frequent
inspections in these establishments.
Green 85.0% 96.0% 87.9% 90.0% 93.0%
Our Economy
South Lanarkshire is an attractive place to start, grow and locate a business
Performance Indicators Comments/ Progress Status Target To Date
-------- Last 3 Years ------------------- This Year -----------
Number of jobs created or sustained per
annum as a direct result of Economic
Development intervention
325 jobs created. This includes jobs created and safeguarded on
projects that have been awarded a Business Recovery and Growth
Grant. On track to achieve target by year end.
Green 500 325 943 ------ 1,095
Number of new South Lanarkshire
business starts supported by Business
Gateway
This is a new measure for 2022-23. The figure shown is up to and
including August 2022. September data is not yet available.  On track to
achieve year-end target. The target is 50% of the Business Gateway
pan-Lanarkshire contract target.
Green 500 215 ------ ------ ------
Page 6
65

Page 66

IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Thursday 26 January 2023
Resource Plan Performance Indicators Community and Enterprise Resources -
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Thursday 26 January 2023
Resource Plan Performance Indicators Community and Enterprise Resources -
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Thursday 26 January 2023
Resource Plan Performance Indicators Community and Enterprise Resources -
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Thursday 26 January 2023
Resource Plan Performance Indicators Community and Enterprise Resources -
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Thursday 26 January 2023
Resource Plan Performance Indicators Community and Enterprise Resources -
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Thursday 26 January 2023
Resource Plan Performance Indicators Community and Enterprise Resources -
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Thursday 26 January 2023
Resource Plan Performance Indicators Community and Enterprise Resources -
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Thursday 26 January 2023
Resource Plan Performance Indicators Community and Enterprise Resources -
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Thursday 26 January 2023
Resource Plan Performance Indicators Community and Enterprise Resources -
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Thursday 26 January 2023
Resource Plan Performance Indicators Community and Enterprise Resources -
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Thursday 26 January 2023
Resource Plan Performance Indicators Community and Enterprise Resources -
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Thursday 26 January 2023
Resource Plan Performance Indicators Community and Enterprise Resources -
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Thursday 26 January 2023
Resource Plan Performance Indicators Community and Enterprise Resources -
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Thursday 26 January 2023
Resource Plan Performance Indicators Community and Enterprise Resources -
Our Economy
Physical development and land use in the area is enabled, guided and controlled to help facilitate economic growth
Performance Indicators Comments/ Progress Status Target To Date
-------- Last 3 Years ------------------- This Year -----------
Percentage of all planning applications
approved
The approval rate in quarter two was 99.2%, and the year to date figure
is 98.5% which continues to exceed the target figure of 95%.
Green 95.0% 98.5% 96.9% 96.2% 97.1%
Page 7
66

Page 67

Summary - number of measures complete, green, amber and red under each Council Plan
Outcome / Theme
Council Outcome/ Theme Complete Green Amber Red Report later Total
Communities and Environment 1 6 2 0 0 9
Education and Learning 0 0 0 0 0 0
Health and Wellbeing 0 0 0 0 0 0
Children and Young People 0 0 0 0 0 0
Housing and Land 0 0 0 0 0 0
Our Economy 1 1 2 0 0 4
Delivering the plan and achieving best value 1 0 1 0 0 2
Total 3 7 5 0 0 15
Page 8
67

Page 68

IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Thursday 26 January 2023
Resource Plan actions and measures Community and Enterprise Resources -
Communities and Environment
High-quality streets, parks and other public areas ensures South Lanarkshire is a place where people want to live, work, visit and invest
Action Measures Comments/ Progress Status
Develop new Litter
Strategy (2022-27) to
promote the new Code
of Practice on Litter and
Refuse (COPLAR), with
particular emphasis on
prevention
Develop final Litter Strategy for approval by Climate Change
and Sustainability Committee in September 2022
The Litter Strategy was approved by the Climate Change and
Sustainability Committee on 31 August 2022.
The Litter Strategy will be launched early in 2023 and will be
accessible on the SLC website and promoted on social media and via
the press.
Green
Prepare an Open Space
Strategy in partnership
with Glasgow and Clyde
Valley Green Network
Partnership and other
council services.
Strategy will contain
standards on access to
and quality of open
spaces
Report on draft Open Space Strategy to Planning Committee
in March 2023
There has been a further delay with Scottish Government's
programme for issuing the Open Space Strategy (OSS) Regulations
and Guidance. It will not be possible to make progress on the SLC
OSS until these are available. It is unlikely that a report to March 2023
committee is feasible in these circumstances.
Amber
The council addresses climate change by reducing carbon emissions, protecting our natural environment, adapting to the impacts of climate change,
and acting sustainbly
Action Measures Comments/ Progress Status
Lead by example and
influence area-wide
climate change and
sustainability action
Finalise the new Sustainable Development and Climate
Change Strategy (2022-27) for approval alongside the new
Council Plan in June 2022
The new Sustainable Development and Climate Change Strategy
(2022-27) has been finalised and was approved at Full Council in June
2022. It was also noted at the Climate Change and Sustainability
Committee in August 2022.
Complete
Implement year one of the Sustainable Development and
Climate Change Strategy (2022-27) Action Plan, and report
progress at quarter two and quarter four to Climate Change
and Sustainability Committee
The Sustainable Development and Climate Change Strategy
(2022-27) Action Plan is being implemented and progress is due to be
reported at the Climate Change and Sustainability Committee in
February 2023 (Quarter 2) and September 2023 (Quarter 4).
Green
Page 9
68

Page 69

IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Thursday 26 January 2023
Resource Plan actions and measures Community and Enterprise Resources -
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Thursday 26 January 2023
Resource Plan actions and measures Community and Enterprise Resources -
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Thursday 26 January 2023
Resource Plan actions and measures Community and Enterprise Resources -
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Thursday 26 January 2023
Resource Plan actions and measures Community and Enterprise Resources -
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Thursday 26 January 2023
Resource Plan actions and measures Community and Enterprise Resources -
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Thursday 26 January 2023
Resource Plan actions and measures Community and Enterprise Resources -
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Thursday 26 January 2023
Resource Plan actions and measures Community and Enterprise Resources -
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Thursday 26 January 2023
Resource Plan actions and measures Community and Enterprise Resources -
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Thursday 26 January 2023
Resource Plan actions and measures Community and Enterprise Resources -
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Thursday 26 January 2023
Resource Plan actions and measures Community and Enterprise Resources -
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Thursday 26 January 2023
Resource Plan actions and measures Community and Enterprise Resources -
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Thursday 26 January 2023
Resource Plan actions and measures Community and Enterprise Resources -
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Thursday 26 January 2023
Resource Plan actions and measures Community and Enterprise Resources -
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Thursday 26 January 2023
Resource Plan actions and measures Community and Enterprise Resources -
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Thursday 26 January 2023
Resource Plan actions and measures Community and Enterprise Resources -
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Thursday 26 January 2023
Resource Plan actions and measures Community and Enterprise Resources -
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Thursday 26 January 2023
Resource Plan actions and measures Community and Enterprise Resources -
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Thursday 26 January 2023
Resource Plan actions and measures Community and Enterprise Resources -
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Thursday 26 January 2023
Resource Plan actions and measures Community and Enterprise Resources -
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Thursday 26 January 2023
Resource Plan actions and measures Community and Enterprise Resources -
Communities and Environment
The council addresses climate change by reducing carbon emissions, protecting our natural environment, adapting to the impacts of climate change,
and acting sustainbly
Action Measures Comments/ Progress Status
Deliver the £2m Climate
Emergency Fund by
March 2024
Report on progress and impact of the funding to date to the
Climate Change and Sustainability Committee in March 2023
A mid-term report on the progress and impact of the Climate
Emergency Fund was presented to the Climate Change and
Sustainability Committee in November 2022. Further updates will be
provided at subsequent committees.
Green
Protect, enhance and
respect South
Lanarkshire's natural
environment
Develop a new Biodiversity Implementation Plan for
(2023-27) for approval by Climate Change and Sustainability
Committee by March 2023
Currently progressing the recruitment of a new Biodiversity Officer, and
this will remain a priority for this financial year.
Update: A new Biodiversity Officer has now been appointed .
Amber
The council supports and promotes a fairer, healthier, and more sustainable food system
Action Measures Comments/ Progress Status
Develop a sustainable
food system to
overcome social, health,
economic and
environmental issues
related to food
Implement year three of the Good Food Strategy (2020-25)
Action Plan and report progress at quarter two and quarter
four to the Climate Change and Sustainability Committee
The action plan of the Good Food Strategy for 2022-2023 was
approved by the Climate Change and Sustainability Committee in
August 2022. The quarter two progress report was presented to the
same Committee in November 2022.
Green
Deliver the £0.3m Food
Strategy Support Fund
by March 2024
Report on progress and impact of the Food Strategy funding
to date to the Climate Change and Sustainability Committee
in March 2023
The fund continues to be monitored, with £0.27m fully committed to
date.
A report on the progress and impact of the fund will be presented at a
future Committee to allow the projects to be implemented.
Green
Page 10
69

Page 70

IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Thursday 26 January 2023
Resource Plan actions and measures Community and Enterprise Resources -
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Thursday 26 January 2023
Resource Plan actions and measures Community and Enterprise Resources -
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Thursday 26 January 2023
Resource Plan actions and measures Community and Enterprise Resources -
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Thursday 26 January 2023
Resource Plan actions and measures Community and Enterprise Resources -
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Thursday 26 January 2023
Resource Plan actions and measures Community and Enterprise Resources -
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Thursday 26 January 2023
Resource Plan actions and measures Community and Enterprise Resources -
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Thursday 26 January 2023
Resource Plan actions and measures Community and Enterprise Resources -
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Thursday 26 January 2023
Resource Plan actions and measures Community and Enterprise Resources -
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Thursday 26 January 2023
Resource Plan actions and measures Community and Enterprise Resources -
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Thursday 26 January 2023
Resource Plan actions and measures Community and Enterprise Resources -
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Thursday 26 January 2023
Resource Plan actions and measures Community and Enterprise Resources -
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Thursday 26 January 2023
Resource Plan actions and measures Community and Enterprise Resources -
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Thursday 26 January 2023
Resource Plan actions and measures Community and Enterprise Resources -
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Thursday 26 January 2023
Resource Plan actions and measures Community and Enterprise Resources -
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Thursday 26 January 2023
Resource Plan actions and measures Community and Enterprise Resources -
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Thursday 26 January 2023
Resource Plan actions and measures Community and Enterprise Resources -
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Thursday 26 January 2023
Resource Plan actions and measures Community and Enterprise Resources -
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Thursday 26 January 2023
Resource Plan actions and measures Community and Enterprise Resources -
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Thursday 26 January 2023
Resource Plan actions and measures Community and Enterprise Resources -
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Thursday 26 January 2023
Resource Plan actions and measures Community and Enterprise Resources -
Communities and Environment
Road and transportation infrastructure supports new development, enables use of public transport and encourages active travel
Action Measures Comments/ Progress Status
Provide road and
infrastructure
improvements to
support new
developments including
those undertaken as
part of the City Deal
Develop the outline business case for the Stewartfield Way
Sustainable Transport Capacity Enhancement Project and
associated supporting technical assessments / designs by
Spring 2023
The strategic business case has been finalised and was considered /
approved by Executive Committee on 10 March 2021.  It was also
considered and approved by Programme Management Office, Chief
Executive Group and Cabinet in May / June 2021.  The financial profile
was reviewed and adjusted to reflect the revised programme.  Work on
the outline business case has been refocused and the next steps are
ongoing, including a potential Member's awareness session in autumn
2022.
Update: An awareness session was held for local members, committee
members and local roads staff on the 12 December 2022.
Green
Our Economy
Our economy is fair, inclusive, sustainable and low carbon, with thriving town and neighbourhood centres which provide a focal point for local
communities
Action Measures Comments/ Progress Status
Deliver an economic
development strategy to
capitalise on our
economic strengths,
tackle weaknesses and
create a flourishing,
green, dynamic and
equitable place for all
Consult on the draft Economic Strategy (2022-27) during
Summer 2022, and present the final Strategy for Committee
approval by October 2022
The final community consultation exercise was completed on 26
September 2022.
Update: Results were collated and the final strategy was presented to
Community and Enterprise Resources Committee slightly behind
schedule, in December 2022. Action now complete.
Amber
Undertake a rolling
programme of review of
the existing Town Centre
Strategies and Action
Plan on a 5 yearly cycle
Finalise Blantyre Town Centre Strategy and action plan
following public consultation and seek formal adoption of the
plan in October 2022
The finalised strategy was presented to the Community and Enterprise
Resources Committee on 4 October 2022.
Complete
Page 11
70

Page 71

IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Thursday 26 January 2023
Resource Plan actions and measures Community and Enterprise Resources -
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Thursday 26 January 2023
Resource Plan actions and measures Community and Enterprise Resources -
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Thursday 26 January 2023
Resource Plan actions and measures Community and Enterprise Resources -
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Thursday 26 January 2023
Resource Plan actions and measures Community and Enterprise Resources -
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Thursday 26 January 2023
Resource Plan actions and measures Community and Enterprise Resources -
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Thursday 26 January 2023
Resource Plan actions and measures Community and Enterprise Resources -
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Thursday 26 January 2023
Resource Plan actions and measures Community and Enterprise Resources -
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Thursday 26 January 2023
Resource Plan actions and measures Community and Enterprise Resources -
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Thursday 26 January 2023
Resource Plan actions and measures Community and Enterprise Resources -
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Thursday 26 January 2023
Resource Plan actions and measures Community and Enterprise Resources -
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Thursday 26 January 2023
Resource Plan actions and measures Community and Enterprise Resources -
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Thursday 26 January 2023
Resource Plan actions and measures Community and Enterprise Resources -
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Thursday 26 January 2023
Resource Plan actions and measures Community and Enterprise Resources -
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Thursday 26 January 2023
Resource Plan actions and measures Community and Enterprise Resources -
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Thursday 26 January 2023
Resource Plan actions and measures Community and Enterprise Resources -
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Thursday 26 January 2023
Resource Plan actions and measures Community and Enterprise Resources -
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Thursday 26 January 2023
Resource Plan actions and measures Community and Enterprise Resources -
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Thursday 26 January 2023
Resource Plan actions and measures Community and Enterprise Resources -
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Thursday 26 January 2023
Resource Plan actions and measures Community and Enterprise Resources -
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Thursday 26 January 2023
Resource Plan actions and measures Community and Enterprise Resources -
Our Economy
Our economy is fair, inclusive, sustainable and low carbon, with thriving town and neighbourhood centres which provide a focal point for local
communities
Action Measures Comments/ Progress Status
recognising the evolving
trends in our town
centres and market
conditions
Report on the Hamilton Town Centre Strategy by December
2022, which will update on delivery of the approved action
plan and develop future actions and strategies
Work continuing on town centre visioning study which will feed into the
updated Hamilton Strategy.
Green
Support and nurture
growth in the Tourism
sector, taking advantage
of South Lanarkshire's
natural environment,
heritage, and culture
Launch new South Lanarkshire Tourism Strategy by October
2022, and work with partners and stakeholders to implement
the subsequent South Lanarkshire Tourism Action Plan
Finalised strategy to be presented to Community and Enterprise
Resources Committee in December 2022, and arrangements are in
place for action plan to be implemented.
Update: The Tourism Strategy was approved at Community and
Enterprise Resources Committee in December 2022.
Amber
Delivering the plan and achieving best value
The council demonstrates high standards of governance and sound financial stewardship
Action Measures Comments/ Progress Status
Modernise Governance
arrangements between
SLC & SLLC
Develop new governance arrangements for approval by the
Council in June 2022
Council approval completed in June 2022, with approval also received
from SLLC Board. Legal measures to complete the conversion are
underway.
Complete
Develop a new five-year
strategy for South
Lanarkshire Leisure and
Culture Ltd
Develop new strategy for noting by the Council in August
2022
The strategy has been submitted to the Council for noting at a future
Committee meeting and will be launched by SLLC in Autumn 2022.
Amber
Page 12
71

Page 72

72

Page 73

Appendix 3
‘Report later’ measures from 2021/2022 
Update of Community and Enterprise Resource Plan 2021/2022 Quarter 4 Progress Report 
Measure Comments at 
Quarter 4
2021/2022
Updated
status 
Updated comments
Percentage of
streets found to
be acceptable
during LEAMS
Survey
This is a Local Government
Benchmarking Framework (LGBF)
indicator. 2021/2022 data will not be
available until January 2023. 
2020/2021 results show that South
Lanarkshire Council continues to
score higher for its street cleansing
service than the Scottish average,
with 94.1% of streets surveyed found
to be of an acceptable standard in
2020-21. This is down slightly from
94.8% in 2019/2020, however we are
still above the Scottish average. It
should be considered that since
March 2020 we have had to introduce
a more fluid service to protect our staff
who have been working at the front
line during the COVID-19 pandemic to
continue to ensure that our streets
remain clean and tidy, bins are
emptied, and fly tipping is removed. It
should also be noted that the Street
Cleansing service were finalists in the
2021 APSE Service Awards for the
whole of the UK in the category of
“Best performer in Street Cleansing” 
Target -
> 94.1% (2020/2021 level) 
Actual -
92.1% 
Local Government Benchmarking
Framework (LGBF) 2021/2022
results show that South
Lanarkshire Council continues to
score higher for its street
cleansing service than the
Scottish average, with 92.1% of
streets surveyed found to be of an
acceptable standard, although
this is down slightly from 94.1%
in 2020/2021. 
It should also be noted that the
Street Cleansing service were
once again finalists in the 2022
APSE Service Awards for the
whole of the UK in the category of
“Best performer in Street
Cleansing”
Town vacancy
rates (vacant
retail units as a
percentage of
the total units) 
This is a Local Government
Benchmarking Framework (LGBF)
indicator. 2021/2022 data will not be
available until January 2023. 
In 2020/2021, the vacancy rate
decreased. Positively, this put South
Lanarkshire below the Scottish
Average (12.4%). Vacancy rates
across South Lanarkshire held up
reasonably well through the first year
of the COVID-19 pandemic, however,
there is bit of fluctuation across the
various towns, and we continue to
work with the relevant stakeholders.
South Lanarkshire is fortunate in so
far as many of the smaller towns and
settlements have no or very few
vacancies. Economic Development
are working with private sector,
business groups and partners to
deliver on town centre strategies,
accessing Scottish Government
regeneration funding and seeking to
diversify uses in town centres to 
Target -
<12.4% (2020/2021 Scottish Av) 
Actual -
9.85% 
As anticipated, Town centre
vacancy rates have continued to
increase in line with the rest of the
country, from 8.80 in 2020/2021
to 9.85 in 2021/2022. This is
obviously a disappointing trend
however we are seeing many
positive examples of new
occupiers across our town
centres, and we remain slightly
ahead of the Scottish average.
The challenge across all town is
significant, however, we are
seeing the anticipated early signs
of new footfall patterns as a result
of people working from home, and
although it is still not a positive
measure, the vacancy rate is
increasing at a slower rate than
many other areas. 
9
73

Page 74

Measure Comments at 
Quarter 4
2021/2022
Updated
status 
Updated comments
maintain viability and vibrancy.  There are some key centres
where the rates are especially
high, e.g. East Kilbride, which
pulls the average up. There are a
number of factors affecting this
including the loss of key anchor
retailers in a short period of time
and areas which have been
allowed to become vacant by the
private sector owners in order to
facilitate wider redevelopment. 
When these aspects are factored
in, overall South Lanarkshire is
in a better position than we have
been for a few years although
much still needs to be achieved. 
Reduction in the
council’s carbon
emissions
achieved by
March 2022
(buildings,
waste, transport
etc. 
Data for 2021/2022 will not be
available until July 2022, however,
interim data for this year is showing
reductions, which have largely been
affected by COVID-19 safety
measures. 
Target -
5% reduction (compared to
2019/2020)
Actual -
17% reduction (compared to
2019/2020) 
The results for financial year
2021/2022 were calculated and
reported to CMT in August 2022.
It was reported that the council's
carbon emissions reduced by
17% compared with baseline year
2019/2020. This is partly due to
the continued service disruption
throughout the year due to Covid,
reductions in national carbon
conversion factors and reduced
amounts of household waste
going to landfill. 
Immediately
available
employment
land as a
percentage of
total land
allocated for
employment
purposes in the
local
development
plan
This is a Local Government
Benchmarking Framework (LGBF)
indicator. 2021/2022 data will not be
available until January 2023. 
In 2020/2021, there was a slight
decrease in the supply of marketable
land as a proportion of total allocated
employment land at 37.5%, which is
down from 38.5% in 2019/2020. This
brings South Lanarkshire just below
the Scottish average. A reduction in
immediately available employment
land is, however, a positive sign that
South Lanarkshire remains an
attractive investment location. The
market for industrial space has been
very active over the last 2 years with
private developers taking advantage
of strong demand and healthy rental
levels at key locations to construct 
Target -
37.5% (2020/2021 level) 
Actual -
12.73% 
In 2021/2022, there was a notable
decrease in the supply of
marketable land as a proportion
of total allocated employment
land at 12.73%, which is down
from 37.5% in 2020/2021. As
such, South Lanarkshire remains
below the Scottish average of
27.19%. It should be noted that
the methodology for categorising
business and industrial land
supply has changed. 
Following the approval of the
National Planning Framework
(NPF4) by the Scottish Parliament
74

Page 75

Measure Comments at 
Quarter 4
2021/2022
Updated
status 
Updated comments
new industrial units for lease.
Economic Development will seek to
increase marketing of key investment
sites as the new Economic Strategy is
implemented and will also compliment
this with support for new industrial
development by the private sector,
identification and appraisal of potential
new investment sites, and
opportunities to maintain an adequate
supply of employment-land through
collaboration with private and public
sector partners.
on 13 February 2023. Formal
authority to commence work on
the next iteration of the South
Lanarkshire Local Development
Plan will be sought from the
Planning Committee in May 2023.
This will provide an opportunity to
identify new land and sites for
economic and employment
purposes.
Maintain 3-year
business
survival rate 
The 3-year business survival rate
figure comes from ONS sources and
is not yet available for reporting this
year. 
The most recently reported data is for
2017 to 2020, when the 3-year
business survival rate had fallen
slightly to 53.2%. In 2016 to 2019 the
figure was 54.4% (1.2% decrease). It
is difficult to understand the reasons
for this decline, as we are not closely
involved in measuring this data. There
is a ‘churn’ in business start-up and
failure, as this often encompasses
self-employment as a consequence of
redundancy, often followed by shut
down to take up new, secure
employment. The new Business
Gateway contractor, Elevator, who
have just completed their first year of
delivery in Lanarkshire, are
specifically tasked with increasing
business start-ups and also to
increase the business survival rate. In
addition, we have refocused SLC
business support grant funding
towards improving these areas of
performance. Additional Economic
Development resources have been
secured, with new officers focusing on
key sectors, improved marketing and
promotion, developing business
networks and encouraging inward
investment, which, it is hoped, will see
these stats improve over the next 3
years. 
Data still not available. 
The 3-year business survival rate
figure comes from ONS sources,
and not yet available for reporting
Number of
business
gateway start-
ups per 10,000
population
This is a Local Government
Benchmarking Framework (LGBF)
indicator. 2021/2022 data will not be
published until January 2023, 
however, provisional figures suggest
there were approximately 15.3
Business Gateway start-ups per 
Target -
>15.6 (2017/2018 level)
Actual -
15.71 
The number of business gateway
start-ups per 10,000 population
75

Page 76

Measure Comments at 
Quarter 4
2021/2022
Updated
status 
Updated comments
10,000 population during 2021/2022.
This is an improvement on the
previous year, which saw a reduction
in recorded Business Gateway start-
ups owing to the impact of the
COVID-19 pandemic. A new Business
Gateway contractor, Elevator, took
over the Lanarkshire Business
Gateway contract on 1 March 2021,
which is contributing to this
improvement.
has increased from 8.95 in
2020/2021 to 15.71 in 2021/2022.
This is higher (better than) the
Scottish Average of 14.41, and
places South Lanarkshire in 17th
place in the rankings (an
improvement from 23rd in
2020/2021). 
Economic Development continue
to work with the Lanarkshire
Business Gateway contractor,
Elevator, to increase business
start-up and sustainability. 
76