Democracy Spraffa

Agenda Document Pack - Community and Enterprise Resources Committee - 13/12/2022

South Lanarkshire Council · 13 December 2022
Back to Community and Enterprise Resources Committee — 13 December 2022 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

Council Offices, Almada Street        
Hamilton, ML3 0AA 
Monday, 05 December 2022 
Dear Councillor 
Community and Enterprise Resources Committee 
The Members listed below are requested to attend a meeting of the above Committee to be
held as follows:- 
Date:  Tuesday, 13 December 2022
Time:  14:00
Venue: Hybrid - Council Chamber, Council Offices, Almada Street, Hamilton,
ML3 0AA 
The business to be considered at the meeting is listed overleaf. 
Yours sincerely 
Cleland Sneddon
Chief Executive 
Members 
Robert Brown (Chair), Maureen Devlin (Depute Chair), Joe Fagan (ex officio), John Anderson,
Ralph Barker, Walter Brogan, Andy Carmichael, Maureen Chalmers, Gerry Convery, Poppy
Corbett, Andrea Cowan, Margaret Cowie, Colin Dewar, Gladys Ferguson-Miller, Ross Gowland,
Graeme Horne, Cal Johnston-Dempsey, Martin Lennon, Richard Lockhart, Hugh Macdonald, Ian
McAllan, Kenny McCreary, Davie McLachlan, Carol Nugent, Helen Toner, David Watson 
Substitutes
Alex Allison, Ross Clark, Margaret Cooper, Allan Falconer, Alistair Fulton, Lynsey Hamilton, Ross
Lambie, Lesley McDonald, Elaine McDougall, Mark McGeever, Richard Nelson, Graham Scott,
David Shearer 
1

Page 2

BUSINESS 
1 Declaration of Interests 
2 Minutes of Previous Meeting
Minutes of the meeting of the Community and Enterprise Resources
Committee held on 4 October 2022 submitted for approval as a correct
record.  (Copy attached) 
5 - 14 
Monitoring Item(s) 
3 Community and Enterprise Resources - Revenue Budget Monitoring
2022/2023
Joint report dated 16 November 2022 by the Executive Directors (Finance
and Corporate Resources) and (Community and Enterprise Resources). 
(Copy attached) 
15 - 24 
4 Community and Enterprise Resources - Capital Budget Monitoring
2022/2023
Joint report dated 23 November 2022 by the Executive Directors (Finance
and Corporate Resources) and (Community and Enterprise Resources). 
(Copy attached) 
25 - 28 
5 Community and Enterprise Resources - Workforce Monitoring - August
and September 2022
Joint report dated 10 November 2022 by the Executive Directors (Finance
and Corporate Resources) and (Community and Enterprise Resources). 
(Copy attached) 
29 - 36 
6 Update of the Community and Enterprise Resources' Risk Register and
Risk Control Plan
Report dated 21 November 2022 by the Executive Director (Community
and Enterprise Resources).  (Copy attached) 
37 - 58 
Item(s) for Decision 
7 South Lanarkshire Draft Tourism Strategy
Report dated 24 November 2022 by the Executive Director (Community and
Enterprise Resources).  (Copy attached) 
59 - 110 
8 Scottish Government 5 Year Play Investment Programme
Report dated 21 November 2022 by the Executive Director (Community
and Enterprise Resources).  (Copy attached) 
111 - 114 
9 South Lanarkshire Gift Card - Update
Report dated 21 November 2022 by the Executive Director (Community
and Enterprise Resources).  (Copy attached) 
115 - 118 
Item(s) for Noting 
2

Page 3

10  Roads Asset Management Plan 2022 - Update
Report dated 21 November 2022 by the Executive Director (Community
and Enterprise Resources).  (Copy attached) 
119 - 132 
11  Comfort Scheme Pilot Lanark
Report dated 21 November 2022 by the Executive Director (Community
and Enterprise Resources).  (Copy attached) 
133 - 136 
12  Community and Enterprise Resources - Notification of Contracts Awarded
- 1 April to 30 September 2022
Report dated 21 November 2022 by the Executive Director (Community
and Enterprise Resources).  (Copy attached) 
137 - 144 
Urgent Business 
13  Urgent Business
Any other items of business which the Chair decides are urgent. 
For further information, please contact:-
Clerk Name: Elizabeth-Anne McGonigle
Clerk Telephone: 07385 403101
Clerk Email: elizabeth-anne.mcgonigle@southlanarkshire.gov.uk 
3

Page 4

4

Page 5

COMMUNITY AND ENTERPRISE RESOURCES COMMITTEE 
Minutes of meeting held via Confero and in the Council Chamber, Council Offices, Almada Street,
Hamilton on 4 October 2022 
Chair:
Councillor Robert Brown 
Councillors Present:
Councillor John Anderson, Councillor Ralph Barker, Councillor Walter Brogan, Councillor Andy
Carmichael, Councillor Maureen Chalmers, Councillor Poppy Corbett, Councillor Andrea Cowan,
Councillor Margaret Cowie, Councillor Maureen Devlin (Depute), Councillor Colin Dewar, Councillor
Allan Falconer (substitute for Councillor Gerry Convery), Councillor Gladys Ferguson-Miller,
Councillor Ross Gowland, Councillor Graeme Horne, Councillor Cal Johnston-Dempsey, Councillor
Martin Lennon, Councillor Richard Lockhart, Councillor Hugh Macdonald, Councillor Ian McAllan,
Councillor Kenny McCreary, Councillor Davie McLachlan, Councillor Carol Nugent, Councillor Helen
Toner, Councillor David Watson 
Councillors' Apologies:
Councillor Gerry Convery, Councillor Joe Fagan (ex officio) 
Attending:
Community and Enterprise Resources
D Booth, Executive Director; K Carr, Head of Facilities, Waste and Grounds Services; C Park, Head
of Roads, Transportation and Fleet Services; I Ross, Project Manager; I Russell, Construction Unit
Manager; G Simpson, Development Adviser
Finance and Corporate Resources
N Docherty, Administration Assistant; L Harvey, Finance Manager; E Maxwell, Human Resources
Business Partner; E-A McGonigle, Administration Officer; L O’Hagan, Finance Manager (Strategy);
M M Wilson, Legal Services Manager; L Wyllie, Administration Assistant 
1 Declaration of Interests 
No interests were declared. 
2 Minutes of Previous Meeting 
The minutes of the meeting of the Community and Enterprise Resources Committee held on 9
August 2022 were submitted for approval as a correct record. 
The Committee decided: that the minutes be approved as a correct record. 
3 Community and Enterprise Resources - Revenue Budget Monitoring 2022/2023 
A joint report dated 7 September 2022 by the Executive Directors (Finance and Corporate
Resources) and (Community and Enterprise Resources) was submitted comparing actual
expenditure at 12 August 2022 against budgeted expenditure for 2022/2023 for Community and
Enterprise Resources. 
At 12 August 2022, there was an overspend of £0.050 million against the phased budget. 
Details were also provided on proposed budget virements in respect of Community and
Enterprise Resources to realign budgets.
2
5

Page 6

The Finance Manager responded to a member’s question in relation to budget virements. 
The Committee decided: 
(1) that the overspend on the Community and Enterprise Resources’ revenue budget of
£0.050 million as at 12 August 2022, as detailed in Appendix A of the report, be noted; and 
(2) that the budget virements, as detailed in appendices B to F of the report, be approved. 
[Reference: Minutes of 9 August 2022 (Paragraph 3)] 
4 Community and Enterprise Resources - Capital Budget Monitoring 2022/2023 
A joint report dated 14 September 2022 by the Executive Directors (Finance and Corporate
Resources) and (Community and Enterprise Resources) was submitted advising of progress on
the Community and Enterprise Resources’ Capital Programme 2022/2023 and summarising the
expenditure position at 12 August 2022. 
The revised capital programme for 2022/2023, as agreed at the 24 August and 21 September
2022 meetings of the Executive Committee, amounted to £64.540 million, a net increase of
£0.117 million and, at 12 August 2022, expenditure was £6.505 million. 
The Committee decided: that the Community and Enterprise Resources’ Capital
Programme of £64.540 million, and expenditure to date of
£6.505 million, be noted. 
[Reference: Minutes of the Executive Committee of 24 August 2022 (Paragraph 4) and 21
September 2022 (Paragraph 4)] 
5 Community and Enterprise Resources - Workforce Monitoring – June and July
2022 
A joint report dated 6 September 2022 by the Executive Directors (Finance and Corporate
Resources) and (Community and Enterprise Resources) was submitted on the following
employee information for Community and Enterprise Resources for the period June and July
2022:- 
 attendance statistics
 occupational health statistics
 accident/incident statistics
 disciplinary hearings, grievances and Dignity at Work cases
 analysis of leavers and exit interviews
 staffing watch as at 11 June 2022 
Officers responded to members’ questions on various aspects of the report. 
The Committee decided: that the report be noted. 
[Reference: Minutes of 9 August 2022 (Paragraph 6)] 
6

Page 7

6 Community and Enterprise Resources’ Workforce Plan 2022 to 2025 
A report dated 14 September 2022 by the Executive Director (Community and Enterprise
Resources) was submitted on Community and Enterprise Resources’ Workforce Plan 2022 to
2025. 
The Executive Committee had agreed the Council Workforce Plan 2017 to 2020, with
Resources being required to provide updates on their Workforce Plan to their respective
committees.  The review of Workforce Plans had been delayed due to the COVID-19 pandemic
and Resources had produced Plans covering the period 2022 to 2025. 
The Community and Enterprise Resources’ Workforce Plan 2022 to 2025, together with the
Action Plan, was attached as Appendix 1 to the report. The Plan provided an overview of the
services delivered by the Resource, the service demands and a workforce profile.  This,
together with the strategic plans and drivers, was used to identify the objectives and actions
required. 
The key themes for workforce planning that had been identified were:- 
 demographic of the workforce and the impact on succession planning
 recruitment and retention of employees in key front line and professional areas
 development of the current workforce to ensure skills were readily available to deliver in
key strategic areas
 maintaining employee wellbeing and resilience 
The key activities identified were:- 
 revised recruitment practices to attract and retain employees
 a graduate apprenticeship approach to recruitment
 to establish links with schools and colleges to encourage pupils and students to consider a
role with the Council
 to establish methods to grow our own talent and future proof the workforce
 review of working practices and business delivery models
 optimise the efficiency of the existing workforce, including staff absence cover 
This aligned with the general common themes from all Resource Action Plans which were:-: 
 increased demand and a reduced workforce pool which was a national issue
 demographic challenges, increased turnover, employees retiring earlier than expected and
succession planning
 employee wellbeing 
The Executive Director (Community and Enterprise Resources) responded to a member’s
question around optimising efficiencies and processes. 
The Committee decided: 
(1) that the content of the report be noted; and 
(2) that the Community and Enterprise Resources’ Workforce Plan 2022 to 2025, attached as
Appendix 1 to the report, be approved. 
[Reference:  Minutes of the Executive Committee of 8 November 2017 (Paragraph 15)] 
7

Page 8

7 Economic Development – Additional Officers
A joint report dated 7 September 2022 by the Executive Directors (Community and Enterprise
Resources) and (Finance and Corporate Resources) was submitted:- 
 seeking approval to make 4 full time equivalent (FTE) existing temporary Economic
Development officer posts permanent, increasing the Economic Development
establishment accordingly
 seeking approval to make 1 FTE existing temporary post of Marketing and Events
Assistant, seconded to the Supplier Development Programme (SDP), permanent 
The importance of the Council’s Economic Development Service had been highlighted during
recent economic events, which included the delivery of the emergency response to the COVID-
19 pandemic.  Furthermore, the introduction of the Community Wealth Building agenda and the
National Strategy for Economic Transformation had highlighted that the Economic Development
Service was fundamental to achieving the ambition of both the Council and the Scottish
Government’s objective of creating a more successful country with opportunities for all to
flourish through increased wellbeing and sustainable and economic growth. 
A new Economic Strategy and associated Action Plan had been drafted which took account of a
rapidly changing economy at international, national and local levels which were increasingly
influenced by a number of key economic policies and emerging funding streams at UK
Government, Scottish Government and City Region level. 
Several temporary posts had been created to focus on economic development and recovery
and, specifically, on business engagement, key sector development and inward investment.  A
shortage of skills and experience had led to recruitment issues and there was competition from
other councils with regards to recruitment when permanent posts were being offered elsewhere.   
Funding was available to retain the Economic Development Officer posts and this was
anticipated to continue to be the position with the emergence of Levelling Up and UK Prosperity
funding through to April 2025 and beyond.  Making these posts permanent would provide
employment security for those on temporary contracts and assist with workforce planning for
anticipated turnover, including retirements. 
The Supplier Development Programme (SDP) was a business support initiative, funded by
public bodies, which aimed to help Small and Medium Enterprises (SMEs) improve their
performance in winning contracts with public sector organisations.  The Council had hosted the
SDP since 2014 and it had grown in membership to include all 32 local authorities, the Scottish
Government, over 14 government agencies, and private sector associate membership which
had been introduced.  Income was generated through events and Scottish Government
contributions. 
The Marketing and Events Assistant post was responsible for assisting with the delivery of
training, workshops/webinars, Meet the Buyer events and exhibitions, and also provided support
to the SDP team in delivering increased social media outputs.  The Scottish Government
provided annual funding of £24,000 to fund the post and support delivery of the associated
activities. 
To deliver on the objectives of the Economic Development Service, it was proposed that the
following temporary posts be added to the establishment on a permanent basis, as detailed in
section 5 of the report:- 
 4 FTE posts of Economic Development Officer on Grade 3, Level 2-8, SCP 63-80 (£33,651
to £42,830) 
 1 FTE post of Marketing and Events Assistant, seconded to the SDP, on Grade 2, Level 1-
4, SCP 34-57 (£22,300 to £30,749) 
8

Page 9

The costs associated with the establishment of the above Economic Development Officer posts
would be funded from existing strategic investment funding and Business Loans Scotland
funding which was already approved through to 2024/2025, with future years expected to be
funded from sources such as Levelling Up and UK Prosperity programmes. If those funds did
not continue, then consideration would be made to reducing the establishment accordingly. 
The costs associated with the SDP staffing requirements would be met, in part, from the annual
Scottish Government funding received for the Programme and the remaining costs would be
managed through existing SDP funding streams in line with current practice. 
The Executive Director (Community and Enterprise Resources) responded to members’
questions on various aspects of the report. 
The Committee decided: 
(1) the content of the report be noted; 
(2) that the 4 FTE temporary Economic Development Officer posts on Grade 3, Level 2-8
(£33,651 to £42,830) in the Economic Development establishment, as detailed in section 5
of the report, be made permanent; and 
(3) that that the 1 FTE temporary post of Marketing and Events Assistant on Grade 2, Level 1-
4 (£22,300 to £30,749), seconded to the Supplier Development Programme, as detailed in
section 5 of the report, be made permanent. 
8 Investment Fund Projects – Temporary Employees
A joint report dated 15 September 2022 by the Executive Directors (Community and Enterprise
Resources) and (Finance and Corporate Resources) was submitted:- 
 providing an update on the staffing changes and proposals within the Waste Service to
deliver the approved strategic investments in Waste Services
 seeking approval to temporarily increase the Waste Services’ establishment by 2.5 FTE for
23 months 
Most domestic properties in South Lanarkshire had been provided with means of presenting
food waste separately, however, there were approximately 5,000 properties in rural areas that
had not been provided with a food waste collection service due to environmental and economic
reasons. 
Waste Services had been allocated funding for strategic investments as part of the 2022/2023
revenue budget strategy to purchase hot composters which would be provided, free of charge,
to residents in rural areas who did not receive a food waste collection service.  The project
included the recruitment of a Waste Services Operative to deliver the composters to the rural
properties. 
It was estimated that over 30% of properties in South Lanarkshire were flats and the majority of
those had been provided with a single recycling bin for co-mingled recycling because of space
restrictions. Residents with co-mingled bins could present paper, card, cardboard, plastic, cans
and tins in the blue bins. The quality of material collected from co-mingled bins was generally
insufficient to be recycled and, consequently, the waste had to be treated as residual waste.  
9

Page 10

The proposed project would re-designate the bins to ‘paper and card’ only bins and Waste
Services had been awarded £15,470 from the Climate Change Fund to develop communications
to support the project. Consistency with regards to the blue bin collections across South
Lanarkshire would also be achieved and, therefore, waste awareness messaging would be less
confusing for residents. The second phase of the project would involve assessing those
properties without recycling bins in order that a recycling service could be provided where space
and accessibility allowed. 
The investment proposals for both projects were fully detailed at section 4 of the report. To
deliver on the objectives of Waste Services, it was proposed that the following posts be added to
the establishment, as detailed in section 5 of the report:- 
 0.5 FTE post of Waste Operative on Grade 1, Level 3, SCP 25-27 (£10,398 to £10,687) for
a period of 23 months
 2.0 FTE posts of Waste Service Assistant (Waste Awareness) on Grade 2, Level 1, SCP
34-35 (£22,300 to £22,665) for a period of 23 months 
The costs associated with the establishment of the above posts would be met from strategic
investment funding of £0.682 million, approved as part of the 2022/2023 revenue budget. 
Funding would be allocated over this financial year and also 2023/2024 based on programme
implementation.  The balance of the strategic investment fund would be allocated, on a phased
basis, as the projects developed and associated costs were identified. 
There followed a full discussion during which members asked for details on:- 
 timescales involved for delivery of the hot composters
 ease of use of the hot composters 
 the recycling rejection rate from flatted properties 
 current contamination rates and variances at flatted properties
 why recycling of paper and card was being prioritised at flatted properties
 the Council’s opt in policy for those flatted properties which would no longer be able to
recycle glass, cans, tins and plastic containers 
In response to a member’s suggestion for a members’ awareness session on issues around
Waste Services and recycling, the Executive Director (Community and Enterprise Resources)
advised that this would be developed for elected members in due course. 
The Committee decided: 
(1) that the content of the report be noted; and 
(2) that the additional temporary increase in the Waste Services’ establishment, as detailed in
section 5 of the report, to facilitate 2 projects aimed at reducing residual waste and
increasing recycling, be approved. 
9 Community Benefit Funds – Renewable Energy Fund – Grant Applications 
A report dated 15 September 2022 by the Executive Director (Community and Enterprise
Resources) was submitted on 2 applications to the various Community Benefit Funds.  The
Community Benefit Funds had been established to provide funding to suitable projects providing
community benefit in eligible areas.
10

Page 11

It was proposed that, subject to the applicant providing written confirmation that all other
additional funding for the projects had been secured, a grant of up to:- 
 £61,066 be awarded to Sandford and Upper Avondale Community Council towards eligible
costs associated with facilitating the refurbishment of Gilmourton Park from the Calder
Water Windfarm Renewable Energy Fund (REF)
 £49,167.20 be awarded to Sandford Village Hall Trust towards eligible costs associated
with facilitating the refurbishment of the village hall from the Kype Muir Windfarm REF 
The Committee decided: that, subject to the applicant providing written confirmation
that all other additional funding for the projects had been
secured, a grant be awarded of up to a maximum of:- 
 £61,066 to Sandford and Upper Avondale Community
Council towards eligible costs associated with
facilitating the refurbishment of Gilmourton Park from
the Calder Water Windfarm REF
 £49,167.20 to Sandford Village Hall Trust towards
eligible costs associated with facilitating the
refurbishment of the village hall from the Kype Muir
Windfarm REF 
[Reference: Minutes of 9 August 2022 (Paragraph 9)] 
10 Blantyre Town Centre Strategy Action Plan
A report dated 14 September 2022 by the Executive Director (Community and Enterprise
Resources) was submitted on the Blantyre Town Centre Strategy and Action Plan. 
Supporting town centres was a Council priority and the Council worked closely with appropriate
groups and organisations through a partnership approach to achieve common goals.  In
developing the Blantyre Town Centre Strategy, key partners were the Blantyre Business
Community and Blantyre Community Council, with a focus on town centre regeneration. 
Following completion of the Blantyre Town Centre Strategy consultation, officers had requested
that elected members and Blantyre Community Council consider the resulting feedback.  The
outcomes from the consultation had broadly supported the priorities and actions that had been
set out in the Strategy, but additional information was provided that had impacted the wider
Community Plan.  The resulting changes to the Strategy, outlined below, were set out at section
4.3 of the report:- 
 inserting the consultation findings
 comments about related sites outwith the town centre sphere of influence, but that could
have potential impact 
Following the consultation exercise, the Blantyre Town Centre Strategy and Action Plan,
attached as Appendix 1 to the report, had been amended and it was proposed that the Strategy
and Action Plan be approved. 
In addition, it was also proposed that officers from Economic Development would liaise with
other Services in the Council and partner organisations to oversee the implementation of the
Strategy and delivery of the Action Plan.
11

Page 12

Officers responded to members’ questions on various aspects of the report.  In response to a
member’s question on the role of Area Committees in monitoring progress against the action
plans of the Town Centre Strategies, the Executive Director (Community and Enterprise
Resources) advised that progress reports could be taken to Area Committees on a regular
basis. 
The Committee decided: 
(1) that the outcome of the Blantyre Town Centre consultation be noted; 
(2) that Blantyre Town Centre Strategy be approved, taking account of the amendments as
detailed in section 4.3 of the report; and 
(3) that the Executive Director (Community and Enterprise Resources) be authorised to
proceed with implementation of the Strategy. 
[Reference: Minutes of 7 December 2021 (Paragraph 6)] 
11 Community and Enterprise Resource Plan – Quarter 4 Progress Report 2021/2022 
A report dated 24 August 2022 by the Executive Director (Community and Enterprise
Resources) was submitted on the Community and Enterprise Resource Plan Quarter 4 Progress
Report 2021/2022 for the period 1 April 2021 to 31 March 2022. 
The Resource Plan measures were rated using a traffic light system of red, amber or green as
well as blue (BRAG) which indicated that an action had been completed. 
Details were provided on:- 
 progress against all Resource Plan measures, as detailed in the Quarter 4 Progress
Report 2021/2022, attached as Appendix 2 of the report
 key achievements made by the Resource to date
 measures which had changed in status from Quarter 2 to Quarter 4, as contained in
Appendix 3 of the report. 
Officers responded to members’ questions on various aspects of the report. 
The Committee decided: 
(1) that the Community and Enterprise Resource Plan Quarter 4 Progress Report 2021/2022,
as summarised in paragraph 5.2 and attached as Appendix 2 to the report, be noted; 
(2) that the key achievements made by the Resource to date, as detailed in paragraph 5.3 of
the report, be noted; 
(3) that the areas for improvement and associated management actions, as detailed in
paragraph 5.4 of the report, be noted; and 
(4) that the additional scrutiny of changes in BRAG status between Quarter 2 and Quarter 4,
as summarised at paragraph 5.5 and detailed at Appendix 3 of the report, be noted. 
[Reference: Minutes of 28 September 2021 (Paragraph 6)]
12

Page 13

12 Community and Enterprise Resource Plan 2022/2023
A report dated 25 August 2022 by the Executive Director (Community and Enterprise
Resources) was submitted on the Community and Enterprise Resource Plan 2022/2023. 
Details were provided on the Resource Plan for 2022/2023, attached as Appendix 1 to the
report, which outlined the:- 
 key areas of focus for the year ahead
 objectives and outcomes
 measures and actions
 resourcing of the Plan 
The Resource had established a number of outcomes to support the delivery of the Connect
priorities in 2022/2023.  In line with the Council’s performance management arrangements, a
mid-year progress report on actions identified in the 2022/2023 Resource Plan would be
submitted to a future meeting of the Committee.   
The Committee decided: that the Community and Enterprise Resource Plan for
2022/2023 be noted and uploaded to the Council’s website. 
[Reference: Minutes of the Executive Committee of 24 August 2022 (Paragraph 8)] 
13 Community and Enterprise Resources – Notification of Contracts Awarded – 1
October 2021 to 31 March 2022
A report dated 16 September 2022 by the Executive Director (Community and Enterprise
Resources) was submitted on contracts awarded by Community and Enterprise Resources in
the period 1 October 2021 to 31 March 2022. 
In terms of Standing Order Nos 21.8 and 22.5 of the Standing Orders on Contracts, Resources
were required to notify the relevant Committee of contracts awarded.  Details of the contracts
awarded by Community and Enterprise Resources were provided in the appendix to the report. 
Officers responded to members’ questions on various aspects of the report. 
The Committee decided: that the report be noted. 
[Reference: Minutes of 7 December 2022 (Paragraph 16)] 
14 Urgent Business 
There were no items of urgent business. 
13

Page 14

14

Page 15

Report
Agenda Item 
Report to: Community and Enterprise Resources Committee 
Date of Meeting: 13 December 2022
Report by: Executive Director (Finance and Corporate Resources)
Executive Director (Community and Enterprise
Resources)  
Subject: Community and Enterprise Resources - Revenue
Budget Monitoring 2022/2023 
1. Purpose of Report
1.1. The purpose of the report is to:-
[purpose]
 provide information on the actual expenditure measured against the revenue
budget for the period 1 April to 4 November 2022 for Community and Enterprise
Resources.  
[1purpose]
2. Recommendation(s)
2.1. The Committee is asked to approve the following recommendation(s):- 
(1) that an overspend of £0.056m as at 4 November 2022 on Community and
Enterprise Resources’ revenue budget, as detailed in appendix A of the report
be noted.
(2) that the proposed budget virements be approved.
[1recs]
3. Background
3.1. This is the third revenue budget monitoring report presented to the Community and
Enterprise Resources Committee for the financial year 2022/2023. 
3.2 The report details the financial position for Community and Enterprise Resources in
appendix A and the individual services’ reports in appendices B to F. 
4. Employee Implications
4.1. None 
5. Financial Implications
5.1. As at 4 November 2022, there is a minor overspend of £0.056m against the phased
budget. 
5.2. The report details the financial position for Community and Enterprise Resources in
appendix A and variance explanations for each service area are detailed in
appendices B to F where appropriate. 
3
15

Page 16

The minor overspend of £0.056m reflects underspends within employee costs and
over recovery of Planning and Building Standards income from fees and income from
waste streams and these are supporting costs within Roads, Transportation and Fleet
services in relation to transport costs and charging of Electric Vehicles, prior to tariffs
being introduced.   
5.3. Virements are proposed to realign budgets across budget categories and with other
Resources.  These movements are detailed in appendices B to F of this report.  
6. Climate Change, Sustainability and Environmental Implications 
6.1.  There are no implications for climate change, sustainability or environment in terms of
the information contained in the report 
7 Other Implications
7.1. The main risk associated with the Council’s revenue budget is that there is an
overspend.  There are inflationary and budget pressures including utilities and fuel (as
well as general inflation pressures) this year which increase the risk of overspend,
however, we have mitigated this going forward by providing additional funds in future
years’ budget strategy, and in this year, through some reserve funds available  There
are also emerging underspends in employee costs which will help offset increasing
inflationary pressures. 
7.2. We will also continue to monitor the actual impact through four weekly budget
monitoring meetings at which any variance is analysed. In addition, the probable
outturn exercise ensures early warning for corrective action to be taken where
appropriate. 
8. Equality Impact Assessment and Consultation Arrangements
8.1. This report does not introduce a new policy, function or strategy or recommend a
change to an existing policy, function or strategy and, therefore, no impact assessment
is required. 
8.2. There is also no requirement to undertake any consultation in terms of the information
contained in this report. 
Paul Manning
Executive Director (Finance and Corporate Resources) 
David Booth
Executive Director (Community and Enterprise Resources) 
16 November 2022 
Link(s) to Council Values/Priorities/Outcomes
 Accountable, effective, efficient and transparent 
Previous References
 None 
16

Page 17

List of Background Papers
 Financial ledger and budget monitoring results to 04 November 2022. 
Contact for Further Information
If you would like to inspect the background papers or want further information, please
contact:-
Louise Harvey, Finance Manager
Ext:  2658 (Tel: 01698 452658)
E-mail: louise.harvey@southlanarkshire.gov.uk
17

Page 18

Appendix A 
SOUTH LANARKSHIRE COUNCIL 
Revenue Budget Monitoring Report 
Community and Enterprise Resources: Period 7 Ended 04 November 2022 (No.8) 
Community and Enterprise Resources Summary 
Annual
Budget 
Forecast
for Year 
Annual
Forecast
Variance
Budget
Proportion
04/11/22
Actual 
04/11/22
Variance 
04/11/22 
%
Variance
04/11/22
Note 
£000 £000 £000 £000 £000 £000   
Budget Category         
Employee Costs 89,189 89,189 0 49,748 48,631 1,117 under 2.2% 
Property Costs 3,809 3,809 0 2,485 2,998 (513) over (20.6%) 
Supplies & Services 17,648 17,648 0 9,206 9,203 3 under 0.0% 
Transport & Plant 23,601 23,601 0 12,742 13,608 (866) over (6.8%) 
Administration Costs 816 816 0 501 552 (51) over (10.2%) 
Payments to Other Bodies 9,825 9,825 0 5,491 5,491 0 - 0.0% 
Payments to Contractors 46,506 46,506 0 21,464 21,165 299 under 1.4% 
Transfer Payments 603 603 0 330 330 0 - 0.0% 
Financing Charges 185 185 0 96 109 (13) over (13.5%) 
Total Controllable Exp. 192,182 192,182 0 102,063 102,087 (24) over 0.0% 
Total Controllable Inc. (67,888) (67,888) 0 (35,839) (35,807) (32) under
recovered (0.1%) 
Net Controllable Exp. 124,294 124,294 0 66,224 66,280 (56) over (0.1%) 
Variance Explanations 
Detailed within Appendices B to F. 
Budget Virements 
Budget virements are shown in Appendices B to F.
18

Page 19

Appendix B 
SOUTH LANARKSHIRE COUNCIL 
Revenue Budget Monitoring Report 
Community and Enterprise Resources: Period Ended 04 November 2022 (No.8) 
Facilities, Waste and Grounds Services 
Annual
Budget 
Forecast
for Year 
Annual
Forecast
Variance
Budget
Proportion
04/11/22
Actual 
04/11/22
Variance 
04/11/22 
%
Variance
04/11/22
Note 
£000 £000 £000 £000 £000 £000   
Budget Category         
Employee Costs 55,948 55,948 0 31,350 31,053 297 under 0.9% 1,b,d,e,
f
Property Costs 1,756 1,756 0 988 1,044 (56) over (5.7%) 2,a,c,f,
g
Supplies & Services 8,539 8,539 0 4,347 4,263 84 under 1.9% 3,b,f,g
Transport & Plant 8,588 8,588 0 4,865 4,911 (46) over (0.9%) b,f
Administration Costs 165 165 0 76 108 (32) over (42.1%) 4,f
Payments to Other Bodies 50 50 0 39 39 0 - 0.0% F
Payments to Contractors 16,897 16,897 0 7,961 7,662 299 under 3.8% 5,a.b,f
Transfer Payments 0 0 0 0 0 0 - n/a 
Financing Charges 45 45 0 28 32 (4) over (14.3%) 
Total Controllable Exp. 91,988 91,988 0 49,654 49,112 542 under 1.1% 
Total Controllable Inc. (19,728) (19,728) 0 (11,683) (11,634) (49) under
recovered (0.4%) 6,f,g
Net Controllable Exp. 72,260 72,260 0 37,971 37,478 493 under 1.3% 
Variance Explanations 
1. The variance is mainly due to vacancies that are being actively recruited within School Crossing Patrollers, Catering, Cleaning and Janitors services
within Facilities, and turnover and staff working on reduced hourly contracts as a result of flexible retirement throughout the service.
2. The variance is due to greater than budgeted expenditure on Health & Hygiene charges within the Janitorial service and rates charges associated with
historic public conveniences, and higher than anticipated expenditure on the security and upkeep of the Castlehill Transfer station. In addition, the
overspend is also due retention of the additional death facility at Peel Park.  
3. The variance is due to an under spend on school meals food purchases and is offset by an under recovery in school meal income.
4. The overspend is due to a greater spend on medical costs within the service.
5. The variance is mainly due to the income received from the disposal of both fibres and containers with the Waste service.  
6. The variance is due to an under recovery in school meals income, income from Horizons restaurant, hospitality and cleaning service movements, a
decrease in uptake in the Care of Gardens service within Grounds partially offset by income from the provision of additional conference & banqueting
services for Vaccination centre.   
Budget Virements 
a. Transfer from reserves in respect of expenditure commitments for Lammermoor retention money, repairs and renewals for Forrest Street containers,
work carried out at the crematorium and laptops for Cooks in Charge.  Net effect £0.162m: Property Costs £0.019m, Supplies & Services £0.062m
Payment to Contractors £0.081m.
b. Transfer previous investment monies to Cost of Living initiatives in respect of funding for Waste Education and organic waste collection, fly tipping and
CCTV.  Net effect (£0.262m): Employees (£0.067m), Supplies & Services (£0.185m), Transport & plant (£0.021m), Payment to Contractor £0.011m.
c. Funding received for utilities support.  Net effect £0.098m: Property Costs £0.098m.
d. Transfer of budgets to support New Deal, maximising attendance resourcing and procurement savings.  Net effect (£0.226m).  Employee Costs
(£0.224m), Property Costs (£0.002m)..
e. Transfer from Education Resources for provision of additional services.  Net effect £0.022m.  Employee costs £0.022m
f. Realign budget to reflect service delivery within Facilities, Waste and Streets & Bereavement. Net effect £0.000m: Employees £0.819m, Property
(£0.108m), Supplies and Services £0.396m, Transport £0.298m, Administration (£0.008m), Payment to Other Bodies £0.010m, Payment to
Contractors (£0.367m), Income (£1.040).
g. Income received from Scottish Power for work carried out at Coalburn play park.  Net effect £0.000m.  Supplies & Services £0.183m, Income
(0.183m). 
19

Page 20

Appendix C 
SOUTH LANARKSHIRE COUNCIL 
Revenue Budget Monitoring Report 
Community and Enterprise Resources: Period Ended 04 November 2022 (No.8) 
Planning and Regulatory Services 
Annual
Budget 
Forecast
for Year 
Annual
Forecast
Variance
Budget 
Proportion
04/11/22
Actual 
04/11/22
Variance 
04/11/22 
%
Variance
04/11/22
Note 
£000 £000 £000 £000 £000 £000   
Budget Category         
Employee Costs 7,207 7,207 0 4,077 3,808 269 under  6.6% 1,b
Property Costs 148 148 0 131 130 1 under 0.8% a,d
Supplies & Services 277 277 0 120 120 0 - 0.0% c,d
Transport & Plant 554 554 0 477 476 1 under 0.2%    d
Administration Costs 146 146 0 61 62 (1) over (1.6%) d
Payments to Other Bodies 255 255 0 73 73 0 - 0.0% d
Payments to Contractors 1,624 1,624 0 751 751 0 - 0.0% 
Transfer Payments 0 0 0 0 0 0 - n/a 
Financing Charges 46 46 0 25 25 0 - 0.0% 
Total Controllable Exp. 10,257 10,257 0 5,715 5,445 270 under 4.7% 
Total Controllable Inc. (5,320) (5,320) 0 (3,173) (3,393) 220 over
recovered 6.9% 2,d
Net Controllable Exp. 4,937 4,937 0 2,542 2,052 490 under 19.3% 
Variance Explanations 
1. The variance is mainly due to vacant posts within the services which are being recruited.  
2. The over recovery in income is due to a greater demand for planning and building standards applications. 
Budget Virements 
a. Funding received for utilities support.  Net effect £0.005m: Property Costs £0.005m.
b. Transfer of budgets to support New Deal.  Net effect (£0.110m).  Employee costs (£0.110m)
c. Transfer from reserves in respect of expenditure commitments for Environmental Flare system.  Net effect £0.030m.  Supplies & Services £0.030m.
d. Realign budget to reflect service delivery within Environmental Services and Planning and Building Standards.  Net effect £0.000m: Property £0.107m,
Supplies and Services (£0.018m), Transport £0.428m, Administration £0.020m, Payment to Other Bodies £0.010m, Income (£0.547). 
20

Page 21

Appendix D 
SOUTH LANARKSHIRE COUNCIL 
Revenue Budget Monitoring Report 
Community and Enterprise Resources: Period Ended 04 November 2022 (No.8) 
South Lanarkshire Leisure and Culture 
Annual
Budget 
Forecast
for Year 
Annual
Forecast
Variance
Budget
Proportion
04/11/22
Actual 
04/11/22
Variance 
04/11/22 
%
Variance
04/11/22
Note 
£000 £000 £000 £000 £000 £000   
Budget Category         
Employee Costs 4 4 0 2 2 0 - 0.0% 
Property Costs 98 98 0 62 63 (1) over (1.6%) 
Supplies & Services 0 0 0 0 1 (1) over n/a 
Transport & Plant 0 0 0 0 0 0 - n/a 
Administration Costs 8 8 0 8 9 (1) over (12.5%) 
Payments to Other Bodies 80 80 0 0 0 0 - n/a 
Payments to Contractors 23,474 23,474 0 10,655 10,655 0 - 0.0% a,b
Transfer Payments 0 0 0 0 0 0 - n/a 
Financing Charges 0 0 0 0 0 0 - n/a 
Total Controllable Exp. 23,664 23,664 0 10,727 10,730 (3) over 0.0% 
Total Controllable Inc. 0 0 0 0 (3) 3 over
recovered n/a 
Net Controllable Exp. 23,664 23,664 0 10,727 10,727 0 - 0.0% 
Variance Explanations 
No variances to report. 
Budget Virements 
a. Transfer from Corporate items in respect of funding for warm welcome initiative.  Net effect £3.000m: PTC £3.000m.
b. Transfer previous investment monies to Cost of Living initiatives in respect of funding for Community Led Activities and Cardio equipment
investments.  Net effect (£0.424m): PTC (£0.424m). 
21

Page 22

Appendix E 
SOUTH LANARKSHIRE COUNCIL 
Revenue Budget Monitoring Report 
Community and Enterprise Resources: Period Ended 04 November 2022 (No.8) 
Enterprise and Sustainable Development 
Annual
Budget 
Forecast
for Year 
Annual
Forecast
Variance
Budget
Proportion
04/11/22
Actual 
04/11/22
Variance 
04/11/22 
%
Variance
04/11/22
Note 
£000 £000 £000 £000 £000 £000   
Budget Category         
Employee Costs 5,115 5,115 0 2,888 2,882 6 under 0.2% 1,b,
d,e
Property Costs 796 796 0 534 536 (2) over (0.4%) c
Supplies & Services 296 296 0 139 140 (1) over (0.7%)    a
Transport & Plant 47 47 0 45 44 1 under 2.2% 
Administration Costs 99 99 0 40 45 (5) over (12.5%) a
Payments to Other Bodies 4,187 4,187 0 1,340 1,340 0 - 0.0% a,b,
d
Payments to Contractors 52 52 0 52 52 0 - 0.0% d
Transfer Payments 0 0 0 0 0 0 - n/a 
Financing Charges 44 44 0 20 20 0 - 0.0% 
Total Controllable Exp. 10,636 10,636 0 5,058 5,059 (1) over 0.0% 
Total Controllable Inc. (3,838) (3,838) 0 (1,979) (1,989) 10 over
recovered 0.5% d,e
Net Controllable Exp. 6,798 6,798 0 3,079 3,070 9 under 0.3% 
Variance Explanations 
1.   The variance is mainly due to vacant posts within the services which are being recruited.   
Budget Virements 
a. Transfer from reserves in respect of expenditure commitments for Montrose House move to Headquarters, food strategy and climate change
investments.  Net effect £0.051m: Supplies and Services £0.038m, Administration £0.001m, Payment to Other Bodies £0.012m.
b. Transfer previous investment monies to Cost of Living initiatives in respect of investment funding for Get South Lanarkshire Working.  Net effect
(£0.428m): Employees (£0.004m), Payment to Other Bodies (£0.424m).
c. Funding received for utilities support.  Net effect £0.002m: Property Costs £0.002m.
d. Establish budget in respect of income received for East Overton Community and Sports Facilities, Strathaven CARS project, Smarter Choices
Smarter Places, UK Shared Prosperity Fund, Community Led Local Development funding.  Net Effect £0.000m: Employee Costs £0.102m, Payment
to Other Bodies £0.486m, Payment to Contractors £0.009m, Income (£0.597m).
e. Realign budget to reflect service delivery within Economic Development. Net effect £0.000m: Employees (£0.181m), Income £0.181m. 
22

Page 23

Appendix F 
SOUTH LANARKSHIRE COUNCIL 
Revenue Budget Monitoring Report 
Community and Enterprise Resources: Period Ended 04 November 2022 (No.8) 
Roads, Transportation and Fleet Services 
Annual
Budget 
Forecast for
Year 
Annual
Forecast
Variance
Budget
Proportion
04/11/22
Actual 
04/11/22
Variance 
04/11/22 
%
Variance
04/11/22
Note 
£000 £000 £000 £000 £000 £000   
Budget Category         
Employee Costs 20,915 20,915 0 11,431 10,886 545 under 4.8% 1,b
Property Costs 1,011 1,011 0 770 1,225 (455) over (59.1%) 2,a
Supplies & Services 8,536 8,536 0 4,600 4,679 (79) over (1.7%) 3,a
Transport & Plant 14,412 14,412 0 7,355 8,177 (822) over (11.2%) 4,d
Administration Costs 398 398 0 316 328 (12) over (3.8%) 
Payments to Other Bodies 5,253 5,253 0 4,039 4,039 0 - 0.0% 
Payments to Contractors 4,459 4,459 0 2,045 2,045 0 - 0.0% c 
Transfer Payments 603                603 0 330 330 0 - 0.0% 
Financing Charges 50 50 0 23 32 (9) over (39.1%) 
Total Controllable Exp. 55,637 55,637 0 30,909 31,741 (832) over (2.7%) 
Total Controllable Inc. (39,002) (39,002) 0 (19,004) (18,788) (216) under
recovered (1.1%) 5,d
Net Controllable Exp. 16,635 16,635 0 11,905 12,953 (1,048) over (8.8%) 
Variance Explanations 
1. The variance is due to staff turnover and vacancies within Roads and Fleet which are being recruited. 
2. The overspend is in the main due to higher than anticipated electricity costs for Electrical Vehicle charging points and the upkeep of Roads depots.
3. The overspend mainly relates to increased costs for annual subscriptions for Computer Licences and PPE within Roads.
4. The overspend is mainly due to the timing of efficiencies and greater than anticipated expenditure in the workshop within Fleet services.
5. The under recovery is mainly due to the net effect of less than anticipated income from maintenance works within Roads and an under recovery in
taxi inspection income partially offset by income recovered from the sale of vehicles within Fleet. 
Budget Virements 
a. Funding received for utilities support.  Net effect £0.115m.  Property Costs £0.045m, Supplies & Services £0.070m.
b. Transfer of budgets to support maximising attendance resourcing and transfer of emergency planning to Finance & Corporate Resources.  Net effect
(£0.150m).  Employee Costs (£0.150m).
c. Transfer previous investment monies to Cost of Living initiatives in respect of community resilience funding.  Net effect (£0.220m).  Payment to
Contractor (£0.220m)
d. Realign budget to reflect service delivery within Fleet services.  Net effect £0.000m: Transport £0.230m, Income (£0.230). 
23

Page 24

24

Page 25

Report
Agenda Item 
Report to: Community and Enterprise Resources Committee
Date of Meeting: 13 December 2022
Report by: Executive Director (Finance and Corporate Resources)
Executive Director (Community and Enterprise
Resources)  
Subject: Community and Enterprise Resources - Capital Budget
Monitoring 2022/2023 
1. Purpose of Report
1.1. The purpose of the report is to:
[purpose]
 provide information on the progress of the capital programme for Community and
Enterprise Resources for the period 1 April to 4 November 2022.
[1purpose]
2. Recommendation(s)
2.1. The Committee is asked to approve the following recommendation:
[recs]
(1) that the Community and Enterprise Resources capital programme of £48.270
million, and expenditure to date of £16.292 million, be noted. 
3. Background
3.1. This is the third capital monitoring report presented to the Community and Enterprise
Resources Committee for the financial year 2022/2023.  Further reports will follow
throughout the year. 
3.2. As noted in the last report to this Committee (4 October 2022), the budget for
Community and Enterprise Resources for financial year 2022/2023 was £64.540
million. 
3.3. Since that meeting, the Executive Committee has agreed changes to the Community
and Enterprise Resources Capital Programme totalling a net decrease of £16.270
million.  The details are shown in Appendix A.  This takes the Community and
Enterprise Resources programme for 2022/2023 to £48.270 million.   
3.4. The report details the financial position for Community and Enterprise Resources in
Appendix A. 
4. Employee Implications
4.1. There are no employee implications as a result of this report. 
5. Financial Implications
5.1. As detailed in Section 3.3, the revised capital programme for Community and
Enterprise Resources for 2022/2023 is £48.270 million. 
4
25

Page 26

5.2. Period 8 Position   
Anticipated spend to date was £15.906 million and spend to 4 November 2022
amounts to £16.292 million, an overspend of £0.386 million.  This mainly reflects the
timing of spend on the new Jackton Primary School project within the Glasgow City
Region City Deal Programme and a number of projects within the Place Based
Investment Programme. 
6. Climate Change, Sustainability and Environmental Implications
6.1. There are no implications for climate change, sustainability or the environment in
terms of the information contained in this report. 
7. Other Implications
7.1. The main risk associated with the Council’s Capital Programme is that there is an
overspend.  The Council continues to experience material shortages, longer lead
times and extraordinary inflationary price increases and it is anticipated that this will
continue to impact the supply chain for the foreseeable future.  The impact of this will
continue to be monitored through the four weekly investment management
meetings.  Further updates will be reported in the coming months with any significant
increases in contract values being brought to members’ attention. 
8. Equality Impact Assessment and Consultation Arrangements
8.1. This report does not introduce a new policy, function or strategy or recommend a
change to an existing policy, function or strategy and, therefore, no impact
assessment is required. 
8.2. There was also no requirement to undertake any consultation in terms of the
information contained in this report. 
Paul Manning
Executive Director (Finance and Corporate Resources) 
David Booth
Executive Director (Community and Enterprise Resources) 
23 November 2022 
Link(s) to Council Values/Priorities/Outcomes
 Accountable, effective, efficient and transparent 
Previous References
 Community and Enterprise Resources Committee, 4 October 2022
 Executive Committee, 2 November 2022
 Executive Committee, 30 November 2022 
List of Background Papers
 Financial ledger to 4 November 2022 
Contact for Further Information
If you would like to inspect the background papers or want further information, please
contact:
Lorraine O’Hagan, Finance Manager (Strategy)
Ext:  2601 (Tel:  01698 452601)
E-mail: lorraine.o’hagan@southlanarkshire.gov.uk
26

Page 27

Appendix A
South Lanarkshire Council
Capital Expenditure 2022-2023
Community and Enterprise Resources 
For Period 1 April 2022 – 4 November 2022 
Community and
Enterprise Resources
Base
Budget 
£000
Budget
Adjustments
£000 
Slippage
£000
Total
Budget
£000
Budget 
to Date
£000
Actual
Expenditure
£000 
Facilities, Waste and
Grounds
1,949 834 (226) 2,557 222 219 
Enterprise and Sustainable
Development
27,435 2,061 (10,416) 19,080 6,592 6,874 
Roads, Transport and
Fleet
29,997 2,528 (5,892) 26,633 9,092 9,199 
TOTAL 59,381 5,423 (16,534) 48,270 15,906 16,292 
For Information Only   
Budget Adjustments approved by Executive Committee, 
2 November 2022: 
Budget Adjustments approved by Executive Committee, 
30 November 2022: 
Budget Adjustments 
Douglas Park – Floodlights 
Halfway Park Play Area – Redevelopment
Place Based Investment Programme
Vacant and Derelict Land – Cuningar Allotments
Rural Business Centre, Lanark 
Total Budget Adjustments           
£0.016m 
£0.174m
(£0.100m)
(£0.592m)
(£0.650m) 
(£1.152m)
Budget Adjustments 
White Bridge Replacement, Chatelherault Country Park
Glasgow City Region City Deal – Stewartfield Way
Clyde Bridge
Larkhall Leisure Centre 
Total Budget Adjustments           
(£0.226m)
(£0.492m)
(£5.400m)
(£9.000m) 
(£15.118m) 
27

Page 28

28

Page 29

Report
Agenda Item 
Report to: Community and Enterprise Resources Committee
Date of Meeting: 13 December 2022
Report by: Executive Director (Finance and Corporate Resources)
Executive Director (Community and Enterprise
Resources)  
Subject: Community and Enterprise Resources – Workforce
Monitoring – August and September 2022 
1. Purpose of Report
1.1. The purpose of the report is to:-
[purpose]
 provide employment information for August and September 2022 relating to
Community and Enterprise Resources
[1purpose]
2. Recommendation(s)
2.1. The Committee is asked to approve the following recommendation(s):-
[recs]
(1) that the following employment information for August and September 2022
relating to Community and Enterprise Resources be noted:- 
 attendance statistics;
 occupational health;
 accident/incident statistics;
 discipline, grievance and Dignity at Work cases;
 analysis of leavers and exit interviews;
 staffing watch as at 10 September 2022 
[1recs]
3. Background
3.1. As part of the Council’s performance management arrangements, regular workforce
monitoring reports are submitted to Committee.  This report for Community and
Enterprise Resources provides information on the position for August to September
2022. 
4. Monitoring Statistics
4.1. Attendance Statistics (Appendix 1) 
Information on absence statistics is analysed for the month of September 2022 for
Community and Enterprise Resources. 
The Resource absence figure for September 2022 was 7.1%, this figure has
increased by 1.0% when compared to the previous month and is 1.7% higher than
the Council-wide figure.  Compared to September 2021, the Resource absence
figure has decreased by 0.4%. 
Based on the absence figures at September 2022 and annual trends, the projected
annual average absence for the Resource for 2022/2023 is 7.4%, compared to a
Council-wide average figure of 6.0%.
5
29

Page 30

Managers follow the procedures outlined in the Maximising Attendance Policy to
support employees to remain at work, or to return to work after a sickness absence. 
There are comprehensive employee supports in place and, additionally, Personnel
Services work in close partnership with line managers and Resource Management
Teams on a case management basis to ensure that appropriate actions are taken. 
The attendance information contained in this report includes absences as a result of
Covid-19, and employees are being supported through this difficult time to maintain
attendance levels where they can.  At the time of this report, the Council overall
absence level was 6.12% with 0.54% of this relating to Covid-19 for sickness and
special leave. 
4.2. Occupational Health (Appendix 2) 
In terms of referrals to occupational health, which include medical examinations and
physiotherapy, overall, 257 referrals were made this period.  This represents a
decrease of 2 when compared with the same period last year.   
4.3. Accident/Incident Statistics 
There were 32 accidents/incidents recorded within the Resource this period, an
increase of 20 when compared to the same period last year. 
4.4. Discipline, Grievance and Dignity at Work (Appendix 2) 
During the period, 15 disciplinary hearings were held within the Resource, an
increase of 7 when compared to the same period last year.  Four appeals were
heard by the Appeals Panel, and at the end of September 2022, 4 Appeals Panels
were pending.  One grievance hearing was raised within the Resource, this figure
has increased by 1 when compared to the same period last year.  No Dignity at Work
complaints were raised within the Resource, this figure has decreased by 1 when
compared to the same period last year. 
4.5. Analysis of Leavers (Appendix 2) 
There were a total of 47 leavers in the Resource this period eligible for an exit
interview. This figure has increased by 1 when compared with the same period last
year.  Seven exit interviews were conducted in this period, a decrease of 3 when
compared to the same period last year. 
4.6. When processing an employee termination, managers were asked to identify
whether they intended to replace the employee who had left the Council.  If they
indicated that they did not intend to replace the employee, they were asked to select
from the following options:- 
 plan to hold for savings
 fill on a fixed term basis pending savings
 transfer budget to another post
 end of fixed term post 
4.7. Appendix 2a provides a breakdown of vacant posts and whether these are being
replaced or held for savings.  In the period August to September 2022, 93 (45.34
FTE) employees in total left employment, managers indicated that 90 (43.21 FTE)
posts were being replaced and 3 posts (2.12 FTE) were due to the end of a fixed
term contract.
30

Page 31

5. Staffing Watch 
5.1. There has been a decrease of 48 in the number of employees in post from 11 June
to 10 September 2022. 
6. Employee Implications
6.1. There are no implications for employees arising from the information presented in
this report. 
7. Financial Implications
7.1. All financial implications are accommodated within existing budgets. 
8. Climate Change, Sustainability and Environmental Implications
8.1. There are no Climate Change, Sustainability and Environmental Implications in
terms of the information contained within this report. 
9. Other Implications
9.1. There are no risk in terms of the information contained within this report. 
10. Equality Impact Assessment and Consultation Arrangements
10.1. This report does not introduce a new policy, function or strategy or recommend a
change to an existing policy, function or strategy and, therefore, no impact
assessment is required. 
10.2. There was no requirement to undertake any consultation in terms of the information
contained in this report. 
Paul Manning
Executive Director (Finance and Corporate Resources) 
David Booth
Executive Director (Community and Enterprise Resources) 
10 November 2022 
Link(s) to Council Values/Priorities/Outcomes
 Accountable, effective, efficient and transparent
 Fair, open and sustainable
 Ambitious, self aware and improving
 Excellent employer
 Focused on people and their needs
 Working with and respecting others 
Previous References
 Community and Enterprise Resources – 4 October 2022 
List of Background Papers
 Monitoring information provided by Finance and Corporate Resources 
31

Page 32

Contact for Further Information
If you would like to inspect the background papers or want further information, please
contact:-
Elaine Maxwell, HR Business Manager
Ext:   (Tel: 01698 454647)
E-mail:  Elaine.Maxwell@southlanarkshire.gov.uk 
32

Page 33

2020 /
2021
2021 /
2022
2022 /
2023
2020 /
2021
2021 /
2022
2022 /
2023
2020 /
2021
2021 /
2022
2022 /
2023
2020 /
2021
2021 /
2022
2022 /
2023
% % % % % % % % % % % %
April 3.1 2.3 4.4 April 5.3 5.7 7.3 April 5.0 5.2 6.9 April 4.4 4.3 5.6
May 2.4 2.7 3.9 May 4.3 6.4 6.8 May 4.0 5.9 6.3 May 3.1 4.9 5.4
June 1.6 2.8 3.5 June 4.0 6.6 7.2 June 3.6 6.0 6.7 June 2.7 4.7 5.3
July 1.8 2.9 3.9 July 3.6 5.3 5.9 July 3.4 4.9 5.6 July 2.3 4.0 4.6
August 1.7 2.9 3.4 August 4.9 6.4 6.6 August 4.4 5.9 6.1 August 3.1 4.7 4.4
September 1.6 3.4 3.1 September 5.8 8.2 7.9 September 5.1 7.5 7.1 September 4.2 6.4 5.4
October 3.1 3.8 October 6.3 7.9 October 5.8 7.3 October 4.8 6.3
November 3.6 3.5 November 7.1 8.0 November 6.6 7.3 November 5.8 6.9
December 3.1 4.2 December 6.4 8.0 December 5.9 7.4 December 5.6 6.9
January 3.4 3.6 January 6.0 9.6 January 5.6 8.6 January 4.8 7.0
February 2.8 4.4 February 6.5 9.5 February 5.9 8.7 February 4.8 6.6
March 2.6 6.0 March 6.8 11.0 March 6.2 10.2 March 4.9 7.9
Annual Average 2.6 3.5 4.0 Annual Average 5.6 7.7 8.0 Annual Average 5.1 7.1 7.4 Annual Average 4.2 5.9 6.0
Average Apr-Sep 2.0 2.8 3.7 Average Apr-Sep 4.7 6.4 7.0 Average Apr-Sep 4.3 5.9 6.5 Average Apr-Sep 3.3 4.8 5.1
546 2940 3486 16136
Resource Total
No of Employees at 30 Sept 2022 No of Employees at 30 Sept 2022 No of Employees at 30 Sept 2022 No of Employees at 30 Sept 2022
Appendix 1
Absence Trends - 2020/2021, 2021/2022 & 2022/2023
Community and Enterprise Resources
APT&C Council WideManual Workers
33

Page 34

COMMUNITY AND ENTERPRISE RESOURCES
Aug-Sep Aug-Sep
2021 2022
MEDICAL EXAMINATIONS
Number of Employees Attending
EMPLOYEE COUNSELLING SERVICE
Total Number of Referrals
PHYSIOTHERAPY SERVICE
Total Number of Referrals
REFERRALS TO EMPLOYEE SUPPORT OFFICER 81 75
REFERRALS TO COGNITIVE BEHAVIOUR THERAPY 0 0
TOTAL 259 257
Aug-Sep Aug-Sep
2021 2022
Specified Injuries* 0 0
Over 7 day absences 2 5
Over 3 day absences** 1 1
Minor 6 16
Near Miss 1 3
Violent Incident:  Physical**** 1 6
Violent Incident:  Verbal***** 1 1
Total Accidents/Incidents 12 32
Aug-Sep Aug-Sep
2021 2022
Total Number of Hearings 8 15
Total Number of Appeals 0 4
Appeals Pending 0 4
Time Taken to Convene Hearing Aug - Sep 2022
0-3 Weeks 4-6 Weeks Over 6 Weeks
9 2 4
Aug-Sep Aug-Sep
2021 2022
Number of Grievances 0 1
Still in Progress 0 1
Aug-Sep Aug-Sep
2021 2022
Number of Incidents 1 0
Number Resolved at Formal Stage 1 0
Aug-Sep Aug-Sep
2021 2022
Career Advancement 2 2
Poor Relationship with Manager/Colleagues 2 0
Moving Outwith Area 0 1
Personal Reasons 0 3
Further Education 2 1
Childcare/caring responsibilities 1 0
Other 3 0
Number of Exit Interviews conducted 10 7
Total Number of Leavers Eligible for Exit Interview 46 47
Percentage of interviews conducted 22% 15%
APPENDIX 2
86 95
14 6
CAUSE OF ACCIDENTS/INCIDENTS
78
*A Specified Injury is any fracture (other than to the fingers, thumbs or toes), amputation, loss of
sight, serious burns, crushing injury, scalping, loss of consciousness caused by asphyxiation/ head
injury, a chemical or hot metal burn to the eye or penetrating injury as defined by the HSE.
**Over 3 day / over 7day absence is an injury sustained outwith specified injury category that results
in a period of absence of absence as defined by the HSE. 
***Near Miss - Any unexpected, unplanned occurrence (except Dangerous Occurrences) that does
not lead to injury of persons, damage to property, plant or equipment but may have done so in
different circumstance.
****Physical violent incidents are included in the "Specified" figures, where applicable, to provide the
"Total Specified" figures.
81
****Physical violent incidents and ***** Verbal Violent Incidents are included in the "Over 3-day or
Over 7-day" figures, where applicable, to provide the "Total Over 3-day or Over 7-day" figures.
****Physical Violent Incidents and ***** Verbal Violent Incidents are included in the "Minor" figures,
where applicable, to provide the "Total Minor" figures.
ANALYSIS OF REASONS FOR LEAVING
RECORD OF DISCIPLINARY HEARINGS
RECORD OF GRIEVANCE HEARINGS
RECORD OF DIGNITY AT WORK
34

Page 35

Appendix 2a     
Aug - Sep 2022
Cumulative total
(Apr 22 - Mar
23)  
FTE* H/C** FTE H/C
Number of Leavers 45.34 93 150.48 290
Replace Employee 43.21 90 142.42 278
Filling on a Temp Basis 0.00 0 0.00 0
Plan to transfer budget to another post 0.00 0 0.00 0
End of fixed term post 2.12 3 8.06 12
Leave vacant pending savings or service review 0.00 0 0.00 0
Plan to remove for savings 0.00 0 0.00 0     
* Full time equivalent     
** Head count/number of employees     
35

Page 36

As at 10 September 2022
Total Number of Employees
F/T P/T F/T P/T
1287 236 206 1408
Director Grade 1 Grade 2 Grade 3 Grade 4 Grade 5 Grade 6 Fixed SCP Teacher TOTAL
1.00 1525.42 397.39 233.22 45.23 17.00 2.00 9.60 0.00 2230.86
As at 11 June 2022
Total Number of Employees
F/T P/T F/T P/T
1300 231 196 1458
Director Grade 1 Grade 2 Grade 3 Grade 4 Grade 5 Grade 6 Fixed SCP Teacher TOTAL
1.00 1543.77 402.16 227.38 45.73 17.00 2.00 5.00 0.00 2244.04
Appendix 3
JOINT STAFFING WATCH RETURN
COMMUNITY AND ENTERPRISE RESOURCES
*Full - Time Equivalent No of Employees
Salary Bands
3137
MALE FEMALE TOTAL
*Full - Time Equivalent No of Employees
Salary Bands
MALE FEMALE TOTAL
3185
36

Page 37

Report
Agenda Item 
Report to: Community and Enterprise Resources Committee
Date of Meeting: 13 December 2022 
Report by: Executive Director (Community and Enterprise
Resources)  
Subject: Update of the Community and Enterprise Resources
Risk Register and Risk Control Plan 
1. Purpose of Report
1.1. The purpose of the report is to: -
]
 present an update on the Risk Register and Risk Control actions for Community
and Enterprise Resources
[1purpose]
2. Recommendation(s)
2.1. The Committee is asked to approve the following recommendation(s):-
[
(1) that the current position with regards to the Resource Risk Register is noted;
and
(2) that it be noted that the outstanding Risk Control Actions will be progressed by
relevant officers
[1recs]
3. Background
3.1. The Council’s Risk Management Strategy promotes consideration of risk in service
delivery, planning and decision-making processes.  The Strategy requires Resources
to record and review risks and control actions regularly.  Community and Enterprise
Resources follow the guidance in developing, monitoring and updating the risk register
on an ongoing basis. 
3.2. The purpose of the register is to ensure that the Resource is fully aware of its top risks,
that these risks are prioritised and that controls are in place to eliminate or minimise
the impact of the risks. 
3.3. The Resource scores the risks in accordance with the Council scoring mechanism,
based on likelihood and impact.  This results in risks being scored between one and
twenty-five (low – very high). 
3.4. Risks are scored on their inherent score (risk if we do nothing) and their residual risk
(risk after applying controls). The Council’s scoring matrix is attached at Appendix
One. 
3.5. The last update of the Community and Enterprise Resources Risk Register was
reported to Committee on 28 September 2021. 
3.6. The Resource’s top risk register, and risk control plan has been reviewed.  This work
was completed in August 2022.    
6
37

Page 38

3.7. The Central Risk Management team annually reviews Resource compliance with the
Risk Management Strategy.  The outcome of the 2021/22 review identified that
Community and Enterprise Resources achieved 100 per cent compliance, scoring 45
out of a possible 45. 
4. Resource Risk Management
4.1. Each Resource has a Resource Risk Management Group which has responsibility for
the promotion and management of risk.   
4.2. The Community and Enterprise Resources Risk Management Group continues to
meet as required.   
4.3. The work of the group over the last year has focused on the review and update of the
Resource Risk Register and ensuring that the register reflected the Council Plan and
individual Service Plans.   
5. Risk Register
5.1. Work has been completed by the Resource Risk Group to finalise the review of the
Resource Risk Register.  The review gave consideration to risks at a Service level, as
well as strategic Council risks. 
5.2. The Resource Risk Register will be monitored on an ongoing basis to allow new risks
to be added and for the control measures and scores of the existing risks to be
reviewed in light of new information.   
5.3. Risks can result from internal or external influences, with examples being the impact
of projected funding cuts or legislative changes or the impact of internal service
changes. 
5.4. The development process for the Resource Plan requires a risk assessment process
to be undertaken as appropriate, resulting in some actions within the Resource Plan
having a corresponding risk identified within the risk register.   
5.5. The main changes to the register are summarised below:-
 Three new top risks have been added 
 The Council is unable to support households most impacted by the cost-of-
living crisis, resulting in increasing levels of poverty, debt and damage to
health (SLC Top Risk)
 The Council fails to deliver the outcomes of the Community Wealth Building
Strategy (SLC Top Risk)
 Failure to achieve the outcomes of the Council Plan (SLC Top Risk)
 The previous Grounds Service risk which covered the damage caused by Ash
Dieback disease has been re-scored as a high risk and re-categorised as an ‘all
service’ risk due to the potential impact on other services
 The ‘EU Exit’ risk has been removed as a Council top risk as this is no longer
considered a corporate issue for the Council. This remains as a CER top risk,
scoring high, to allow any residual risk issues to be addressed. 
 The Emergency Response Council top risk has been transferred to Finance and
Corporate Resources 
5.6. Risks scored 15 to 25 are considered to be very high risks and risks scored eight to
12 are considered to be high risks.  Very high and high risks are monitored closely.
The top risks identified for the Resource, that is those that are residually scored as
being very high and high, are attached at Appendix Two. 
38

Page 39

5.7. Appendix Three provides a comparison of risk scores for 2021 and 2022. This
appendix also details any significant changes made to the risks.     
5.8. Risks evaluated residually as being medium or low risk will be monitored to ensure
that they continue to be adequately managed. 
5.9. The Committee is asked to note the contents of the Resource Risk Register. 
6. Insurance Hotspots
6.1. Following the completion of claims analysis reports by insurers, various areas of work
have been identified to mitigate insured losses. Those which affect Community and
Enterprise Resources include a property insurer survey programme; ongoing
development of driving at work training; and a Health and Safety/training review to be
undertaken by the Council’s claims handlers:
 Property
 A property insurer survey programme is underway
 Work to address functionality and reliability of CCTV systems across South
Lanarkshire  
 Motor
 Following the development and launch of a ‘Challenging Driver Behaviour’
learn online course for managers this year, a review to be undertaken on
the uptake and steps taken to ensure that all managers with responsibilities
for driving at work complete the course.
 Development and roll out of the same ‘Challenging Driver Behaviour’ learn
online course for all drivers 
 Following the update and roll out of motor insurance procedures this year,
managers have been asked, through a more detailed post incident interview
process, to establish the root cause of motor accidents and identification of
support/corrective action, where required. Continued support and
monitoring of this process via the Drivers Safety Group
 Continued factfinding investigations into accidents, as per guidance which
forms part of the Council’s driving at work procedures   
 Combined Liability 
 Health and Safety/training review to be undertaken by the Council’s claims
handlers, Gallagher Bassett
 Roads and Transportation Services to trial technology associated with road
safety inspections and network condition surveys 
7. Scope and Appetite for Risk
7.1. The Council aims to be risk embracing, that is it will accept a tolerable level of risk in
seeking service efficiencies and in agreeing control measures. 
7.2. The level of risk facing the Council is measured both before (inherent risk) and after
(residual risk) consideration of controls.  The Council should never carry a very high
residual risk exposure as this would indicate instability, but a low residual risk exposure
should also be avoided as this indicates lack of innovation. 
7.3. The Council’s ideal risk profile is defined within the Risk Management Methodology
as:-
 No more than 10 per cent of residual risks at a very high level
 No more than 15 per cent of risks at a high level
 Around 50 to 60 per cent of residual risks at a medium level
 No more than 30 per cent of residual risks at a low level  
39

Page 40

7.4. Table One below shows the top risks heat map, i.e. it details the total number of risks
for each individual residual risk score.  Table Two below notes the overall risk profile
for the top risks. 
Table One – Community and Enterprise Resources Top Risks Heat Map 
Likelihood
5
Almost Certain 0 0 1 2 0
4
Likely 0 2 3 1 0
3
Possible 0 3 7 4 0
2
Unlikely 0 4 10 2 0
1
Rare 0 3 4 4 0  
1
Negligible
2
Minor
3
Moderate
4
Major
5
Catastrophic  
Impact 
Table Two – Community and Enterprise Resources Top Risks Risk Profile 
Risk
Category
Risk
Rating
Number
of risks
Percentage
of risks
1 Very high 4 8%
2 High 18 36%
3 Medium 21 42%
4 Low 7 14% 
7.5. Despite the fact that the profile noted in Table Two is outwith the ideal universal risk
exposure defined by the Risk Management Strategy, this risk exposure is reasonable
given the number of high-level risks currently being faced by the Resource.   
7.6. Community and Enterprise Resources have ensured that all inherent risks scored at
a very high and high level have cost effective control measures in place.  Where further
control measures are required, these are included within the Resource risk control
plan. 
8. Risk Control Actions
8.1. Two risk control actions due for completion during 2021/22 have been completed. One
hundred per cent (2/2) of these risk control actions were completed on time against an
overall Resource target of 90 per cent.  A further 4 have completion dates for March
2023 
8.2. Details of the completion of risk control actions during 2021/22 and those due in
2022/23 to date are contained in Table Three below. 
Table Three – Completion of top risk control actions 
2021/22  2022/23
(as at 16
September 2022)
Total number of actions due 2 4
Completed on time 2 0
Completed late 0 0
Due to be completed at a later date 0 4 
40

Page 41

8.3. Progress with completion of Resource Risk Control Actions is monitored on a monthly
basis by the Central Risk Management team.  This is also reviewed by the Resource
Risk Group.   
8.4. There are four risk control actions due for completion during 2022/23.  The Committee
is asked to note that the outstanding actions to mitigate risks within the Risk Control
Plan will be progressed by the relevant officers. 
9. Major Projects, Partnerships or Change
9.1. Within Community and Enterprise Resources, 26 partnerships have been identified. 
Four of these are considered to be high risk, these are the Clyde Gateway Partnership,
SPT, City Deal and Climate Ready Clyde Partnership.  The remaining 22 partnerships
have been assessed as being low risk. 
9.2. Appropriate risk management arrangements are in place for the high-level
partnerships. 
10. Next Steps
10.1. The Resource Risk Management Group will continue to meet as required.  The risk
register will be reviewed on an ongoing basis by the group to ensure that risks remain
valid for the appropriate Service areas and to identify new areas of risk that affect the
Resource.  An update report will be provided to Committee on an annual basis.   
11. Employee Implications
11.1. Time will be required by the Resource Risk Management Group in the management
of the Resource Risk Register and Risk Control Plan. 
12. Financial Implications
12.1. There are no direct financial implications associated with the Council’s top risks.  There
are a number of proposed risks which are classified under the heading of financial.
Where this is the case, the appropriate controls and actions have been included in the
risk control cards and progress will be monitored. 
13  Climate Change, Sustainability and Environmental Implications 
13.1 Sustainable development issues are included within the Council’s top risk register
through being linked directly to the Council plan objective ‘make communities safer,
stronger and sustainable’ 
14. Other Implications
14.1. Failure to demonstrate that risk is actively considered and managed cannot only lead
to avoidable financial loss but could also affect delivery of services and could affect
the Resources’ reputation. 
15 Equality Impact Assessment and Consultation Arrangements
15.1. This report does not introduce a new policy, function or strategy or recommend a
change to existing policy, function or strategy and, therefore, no impact assessment
is required. 
15.2. Consultation on the content of this report has been undertaken with members of the
Community and Enterprise Resources Risk Management Group. 
41

Page 42

David Booth
Executive Director (Community and Enterprise Resources) 
21 November 2022 
Link(s) to Council Values/Priorities/Outcomes
 Accountable, effective, efficient and transparent 
Previous References
 Community and Enterprise Resources Committee – 28 September 2021 - Annual
update on Resource Risk Register and Risk Control Action Plan 
List of Background Papers
 Figtree extracts (risk register and risk control action plan) 
Contact for Further Information
If you would like to inspect the background papers or want further information, please
contact: -
Linda Burnett, Support Manager Tel:  07795 455507
E-mail:  linda.burnett@southlanarkshire.gov.uk 
42

Page 43

Appendix One – Risk scoring matrix and likelihood and impact definitions 
Likelihood 
Score 1 2 3 4 5
Description Rare   Unlikely  Possible  Likely Almost
certain 
Likelihood of
occurrence
1 in 10 years 1 in 3 years 1 in 2 years Annually Monthly
Probability of
occurrence
The event may
occur in certain
circumstances
The event
could occur
The event may
occur
The event will
probably occur
The event is
expected to
occur or
occurs
regularly 
Impact 
Reputation Financial Service delivery/
Time to recover
Compliance Safety
1
Negligible
Public concern
restricted to
local
complaints
<£50,000 per
annum
No impact to
service quality;
limited disruption
to operations.
No external
interest
Minor injury
– no lost
time
2
Minor
Minor adverse
local/public/me
dia attention
and complaints
£50,000-
£250,000 per
annum
Minor impact to
service quality;
minor service
standards are not
met; short term 
Very minor
attention
from
legislative
/regulatory
body
Minor injury
– resulting
in lost time
3
Moderate
Adverse
national media
Public attention
£250,000 to
£500,000 per
annum
Significant fall in
service quality;
major partnership
relationships
strained; serious
disruption in
service standards
Short-term
attention
from
legislative/
regulatory
body 
Major injury
or ill health
resulting in
lost time
4
Major
Serious
negative
national or
regional
criticism
£500,000 to
£1million per
annum
Major impact to
service delivery;
multiple service
standards are not
met; long term
disruption to
operations;
multiple
partnerships
affected
Medium-term
attention
from
legislative/
regulatory
body 
Fatality;
Or injuries
to several
people
5
Catastrophic
Prolonged
international,
regional and
national
condemnation
>£1million per
annum
Catastrophic fail
in service quality
and key service
standards are not
met; long term
catastrophic
interruption to
operations;
several major
partnerships are
affected
National
impact with
rapid
intervention
of legislative/
regulatory
body 
Multiple
fatalities; Or
injuries to
large
number of
people 
The assessments for impact and likelihood combine to provide an overall inherent risk score on the
scale of between 1 and 25, using the Council’s recognised risk matrix. 
43

Page 44

Risk matrix
Likelihood
5
Almost
Certain
5 10 15 20 25
4
Likely 4 8 12 16 20
3
Possible 3 6 9 12 15
2
Unlikely 2 4 6 8 10
1
Rare 1 2 3 4 5  
1
Negligible
2
Minor
3
Moderate
4
Major
5
Catastrophic  
Impact 
The risk score is calculated as follows: 
Likelihood score x Impact score = Risk Score 
44

Page 45

Appendix Two 
Community and Enterprise Resources Risk Register (as at October 2022) 
Extract of risks with residual score category of Very High and High 
Risk
Category
Key risk Inherent
Risk Score
Sample of Controls Residual
Risk Score
1
Very High
(15-25)
Reduction in external funding and
fees/income received by the Council, as
well as the increased demand for services
including the residual impact of the
pandemic, and the increased cost of
services due to rising inflation and the cost
of living crisis, results in increasing budget
gaps. 
The Council is seeing considerable
increases in prices in terms of energy, fuel
and food costs reflecting the global
economic environment.  These will have
an impact on the current and future years’
Budget Strategy.  This may also affect the
level of service that the council can
provide.
Council Top Risk 
25
Very high 
• Reports prepared to Council timetable and
reported to Finance, CER Committee to
provide assurances that income and
expenditure is within budget and regular
updates provided to Director of Finance
• Robust arrangements in place to monitor
service delivery outturns against budgets
• Implications of changes to service provision
managed through consultation, impact
assessments and Trade Union negotiation. 
• Promotion of new/updated policies via
Website, Press, Social media etc.
• Management of outsourced work including
regular contractor meetings as appropriate. 
20
Very high 
The council is unable to support 
households most impacted by the cost-of
living crisis, resulting in increasing levels of
poverty, debt and damage to health
Council Top Risk 
25
Very high
• Provision of support to local business by
Economic Development
• Increased School Meal provision / breakfast
clubs 
• Resourcing and support to the provision of 
‘Warm Spaces’ hubs in Lifestyle Centres/
Libraries and other council properties. 
20 
Very High
45

Page 46

Risk
Category
Key risk Inherent
Risk Score
Sample of Controls Residual
Risk Score 
The council fails to maximise the benefits
of the Community Wealth Building Strategy
Council Top Risk 
25
Very High
• Supplier Development Programme provides
training to businesses on how to bid for
contracts/meet the buyer events
• Work with Scottish Enterprise, Scottish
Development International and Glasgow
City Region partners to raise the profile of
investment opportunities
• Support is provided to all businesses
through the council’s Business Support
Team and Business Gateway Lanarkshire
service
• Reporting schedule in place to monitor
progress through Sustainable Development
and Climate change Strategy
16
Very High 
Failure to meet sustainable development
and climate change objectives
Council Top Risk 
20
Very High 
• Sustainable development and climate
change is mainstreamed across the Council
and associated Plans, Policies and
Strategies
• Implementation of the Council's Sustainable
Development and Climate Change Strategy
and Carbon Management Plan 
• A long-term capital programme that tackles
climate change mitigation and adaptation 
• The preparation of a pipeline of climate
change mitigation and adaptation projects
to attract investment/funding
• Active membership in Climate Ready Clyde
regional adaptation partnership 
15
Very high 
2
High
(8-12) 
The council does not have the appropriate
emergency / business continuity plans;
contingency arrangements or partnerships
25 
Very high 
• The ability to adapt funding to support
community and third sector groups, e.g.
government support provided via additional
12
High
46

Page 47

Risk
Category
Key risk Inherent
Risk Score
Sample of Controls Residual
Risk Score
in place to respond to/or recover from a
pandemic/endemic event.
Council Top Risk 
funding to support vulnerable groups,
hardship funds etc. 
• Business Continuity Plan developed to
facilitate the continued delivery of safety
critical Priority 1 Services, the plan also
facilitates the delivery of priority 2 services
as far as practicable and priority 3 services
as far as resources allow     
• Budget monitoring and re-alignment
arrangements in place for lines that could
potentially be affected by loss of income 
The Council is significantly affected by the
impact of the UK leaving the European
Union (Brexit) 
• Limited procurement options and
contract restrictions 
• Loss of EU funding
• Implications of changes to free
movement of trade and people
• Demand on business support services
could be affected 
25
Very high
• All grants covering ESF, ERDF activity up to
April 2023 approved and grant accepted
prior to deadlines
• Economic Development provides ongoing
support to businesses within the South
Lanarkshire area and gathers information
and intelligence through partners and
business networks
• Implementation of the UK shared prosperity
fund which replaced the previous
ESF/ERDF funding streams
• Contractor and supplier management
arrangements in place including regular
contract management for Contractors with
meetings as appropriate 
12 
High 
Fraud, theft, organised crime and cyber
attacks
Council top risk 
20
Very high 
• CER Fraud risk register in place and
updated annually.
• Fraud, Cyber / Information security Training
Learn on Line Modules; mandatory for all
employees 
12
High 
47

Page 48

Risk
Category
Key risk Inherent
Risk Score
Sample of Controls Residual
Risk Score 
Information governance not subject to
adequate control
Council top risk 
20
Very high
• Compliance with Information Governance
Strategy
• Retention schedules
• Electronic Content Management System
(ECM)
• Completion of annual information
Governance checklist 
12 
High 
The council fails meet statutory and
legislative duties in respect of public
protection 
Council Top Risk 
16 
Very high 
• Responsive public health service and
inspection programme in place including
food hygiene, health and safety
enforcement and advisory service,
contaminated land and air quality, private
sector housing stock,
• Ongoing review of contaminated land
strategy and maintenance of register of
contaminated land
• Agreed programme of business compliance
visits and Health and Safety Welfare
inspections and follow up visits carried out
throughout the year, targets for inspections
set and closely monitored
• Partnership working with police Scotland
and NHS
• Raising awareness of current scams and
frauds being perpetrated in the local
community 
12
High 
Failure to work effectively with the private
sector to support local businesses, town
centres and the rural economy  
16 
Very high
• Support to Business Improvement Districts,
town centres and other partnerships via
numerous channels include the ‘Invest in
South Lanarkshire’ website and
management of the Supplier Development
12
High
48

Page 49

Risk
Category
Key risk Inherent
Risk Score
Sample of Controls Residual
Risk Score
Programme including strategic development
and delivery of events, training and e-
commerce
• Regular operational and steering group
meetings and ongoing liaison with
partnership authorities.  (e.g. EK task force
and Clyde Gateway, Lanarkshire Area
Tourism Partnership)
• Implementation of the Community Led Local
Community Fund (CLLD), Community
Benefit funding in rural area with
appropriate funding in line with relevant
(e.g. rural) strategies, and the Business
Loan Scotland 
Lack of capacity and skills to meet
increased service demands
Council top risk 
20
Very high 
• Performance Appraisal (PDR) process
including service learning and development
priorities and employee training plans 
• The Workforce strategy provides greater
level of organisational control rather than
service/resource specific and has a focus
on agile working. 
• Management Development and Leadership
Challenge Programme 
• Stress audit tool 
• Effective partnership working with Trade
Unions  
9 
High 
IT development and functionality does not
keep pace with changing service
requirements 
Council Top Risk 
20
Very high 
• Service IT requirements restricted to reflect
available resources  
• IT service plan closely monitored and
progress reports issued to the IT Strategy
Group/ICT Board on a regular basis
9
High 
49

Page 50

Risk
Category
Key risk Inherent
Risk Score
Sample of Controls Residual
Risk Score 
Ash Dieback Disease  20 
Very high
• Raising awareness of ash dieback and the
issues it may cause
• Preparing and implementing an Ash
Dieback Action Plan
• Assisting with recovery of landscape and
infrastructure affected by ash dieback 
9
High 
Failure of unrestricted substandard bridges 
• Injury to people, damage to assets and
network interruption/disruption  
16 
Very high
• Implement and maintain enhanced
structural monitoring
• Maintain list of qualifying structures
• Implement appropriate reactive mitigation
measures when need for repair identified. 
• Option to close if absolutely necessary
9
High 
Failure to secure external funding and
effectively manage funds / maximise
investment 
16 
Very high
• CMT approval process for external funding
• Manage expectations of Councils income at
outset
• Funding and compliance section investigate
all methods of external funding
9
High 
Failure to improve SLC infrastructure  16 
Very high
• Roads investment programme. 
• Major programme of carriageway upgrading
to improve the road condition being
undertaken - progress monitored closely
through iMPROVE. 
• Regular monitoring by managers of
progress and budgets.  
• Improvements to road related infrastructure
using Roads Investment Programme and
external funding. 
9
High 
Increasing levels of adverse weather
Council Top Risk 
16 
Very high 
• Council wide emergency planning
arrangements, Duty Manager, standby rota
and weather forecasting systems in place
• Effective management of existing budget
resources through regular reporting and
dialogue with Exec Dir Finance and
9
High 
50

Page 51

Risk
Category
Key risk Inherent
Risk Score
Sample of Controls Residual
Risk Score
Corporate and investment in flooding
infrastructure 
• Remote monitoring of high risk flood sites
using flood camera/telemetry solutions
• Winter weather procedures, Winter Service
Policy and Ops manual and dedicated flood
risk management team 
• Pothole inspection and pro-active
rectification programme using sub-
contractors during extended severe weather 
Impact of Waste Management market
changes
• Changes to global economic policy
changes resulting in market collapse
and inability to dispose of recycled
products
12 
High
• Market changes monitored through waste
industry network groups and via meetings
with contractors
• Contracts include contingency
arrangements including back up provision
for alternative suppliers
• Operational monitoring process in place  
• Waste Awareness Team – ongoing
initiatives to promote and improve levels of
domestic recycling
9
High 
Failure to ensure the health, safety and
wellbeing of employees and the protection
of service users and members of the public
in the delivery of council services 
Council Top Risk 
20 
Very high 
• Occupational Health and Safety
Management System embedded throughout
Resource
• Risk Assessments and Safe Systems of
Work and associated local management
procedures developed and implemented
• Resource, Service and Trade Union
communication and consultation
arrangements in place
• H&S Training matrices (Specific training
requirements for employees at Service level
within the Council)
8
High 
51

Page 52

Risk
Category
Key risk Inherent
Risk Score
Sample of Controls Residual
Risk Score
• Programme of H&S Audits and Inspections
undertaken 
Failure to achieve the outcomes of the
Community Plan 
Council Top Risk 
20
Very high 
• Partners signed up to Community Plan
2022-2032 and have agreed to mainstream
the Sustainable Development Goals to work
on the Partnership
• Governance arrangements via the
Community Planning Partnership Board
• Regular progress reporting to
RMT/CMT/Committee 
• Community Planning Risk Register
maintained and monitored
8
High 
Failure to achieve the outcomes of the
Council Plan
Council Top Risk 
20
Very High
• Annual performance reporting 
• Governance arrangements via the
Executive Committee, Performance and
Review Scrutiny Forum and CER Resource
Committee
8
High 
Increased costs providing winter
maintenance 
• Failure to provide essential services
during periods of extreme winter
weather 
12 
High
• Effective management of existing budget
resources through regular reporting and
dialogue with Exec Dir Finance and
Corporate.  
• Salt stocks and storage capacity
• Winter weather procedures, winter service
policy and ops manual 
• Daily winter task force meetings held during
periods of extreme weather to ensure
service delivered in most efficient and
effective way.
• Implementation of the actions arising from
the review of winter maintenance
8
High 
52

Page 53

Appendix 3 – Comparison of the 2022 and 2021 Resource risk register 
Risk
Category
2022 Risk description 2021
Residual
risk score
2022
Residual
risk
score
Change in
residual risk
scores
Key changes 
Very High The council is unable to 
support households most 
impacted by the cost-of-living 
crisis, resulting in increasing 
levels of poverty, debt and 
damage to health 
N/A 20 New risk The focus of this new risk is on the support 
that the council can provide to households.  
The council’s support role is only a small
part of the mitigation, with the Government
and Energy Companies playing a lead role. 
Very High  Reduction in external funding
and fees/income received by
the Council, as well as the
increased demand for services
including the residual impact of
the pandemic, and the
increased cost of services due
to rising inflation and the cost-
of-living crisis, results in
increasing budget gaps. 
The Council is seeing
considerable increases in
prices in terms of energy, fuel
and food costs reflecting the
global economic environment. 
These will have an impact on
the current and future years’
Budget Strategy.  This may
also affect the level of service
that the council can provide.
20 20 = The risk description has been updated, to
reflect the level of Government grant
received, inflationary increases, rising
energy costs, reduced income (cost-of-
living crisis) and greater pressure on
council budgets
53

Page 54

Risk
Category
2022 Risk description 2021
Residual
risk score
2022
Residual
risk
score
Change in
residual risk
scores
Key changes 
(App 5) The council fails to maximise
the benefits of the Community
Wealth Building Strategy 
N/A 16 New Risk This new council risk recognises the
importance of councils Community Wealth
Building (CWB) strategy.  CWB is an
alternative approach to traditional
economic development and a fundamental
shift in the councils approach across a
number of services. 
Failure to meet sustainable
development and climate
change objectives 
15 15 = The risk has been updated to reflect the
recently approved strategy and pending
development of an action plan. 
High  The council does not have the
appropriate emergency /
business continuity plans;
contingency arrangements or
partnerships in place to
respond to/or recover from a
pandemic/endemic event.
16 12  The risk description has been refocused to
consider potential future events and
residual effects of the current pandemic
being managed at Resource level.   
Fraud, theft, organised crime
and cyber attacks
12 12 = The risk has been updated to reflect the
global increase in cyber attacks 
Information governance not
subject to adequate control
12 12 = 
The council fails meet
statutory and legislative duties
in respect of public protection
12 12 = 
The Council is significantly
affected by the impact of the
UK leaving the European
Union (Brexit) 
12 12 = No longer considered a top risk for the
council, remains on CER register until
residual risk issues are addressed 
54

Page 55

Risk
Category
2022 Risk description 2021
Residual
risk score
2022
Residual
risk
score
Change in
residual risk
scores
Key changes 
• Limited procurement
options and contract
restrictions 
• Loss of EU funding
• Implications of changes to
free movement of trade and
people
• Demand on business
support services could be
affected 
Failure to work effectively with
the private sector to support
local businesses, town centres
and the rural economy
12 12 = Introduction of the new Community Wealth
Building top risk provided opportunity to
combine three business support risks   
Lack of capacity and skills to
meet increased service
demands
9 9 = The risk has been updated noting
difficulties with the recruitment and
retention of staff 
IT development and
functionality does not keep
pace with changing service
requirements
9 9 = 
Increasing levels of adverse
weather
9 9 = The risk has been updated to cover
droughts/water supply issues and wildfires 
Ash Dieback Disease N/A 9 New CER risk The focus of this risk is to ensure the
development of an Ash Dieback Action
Plan in line with the Ash Dieback Toolkit
(Scotland), the four key parts of the
approach are Awareness, Planning, Action
and Recovery.  Ash Dieback has the
potential to lead to long lasting changes in
our landscape, tree populations and
canopy cover and loss of ecosystem
55

Page 56

Risk
Category
2022 Risk description 2021
Residual
risk score
2022
Residual
risk
score
Change in
residual risk
scores
Key changes 
services potentially leading to reduce
carbon lockup. Tree failures could result in
an increase in road network disruptions,
flooding, and a potential significant
increase in vehicle and property claims. 
Failure of unrestricted
substandard bridges 
• Injury to people, damage to
assets and network
interruption/disruption
9 9 = 
Failure to secure external
funding and effectively
manage funds / maximise
investment
9 9 = 
Failure to improve SLC
infrastructure
9 9 = 
Impact of Waste Management
market changes
• Changes to global
economic policy changes
resulting in market collapse
and inability to dispose of
recycled products
9 9 = 
Failure to ensure the health,
safety and wellbeing of
employees and the protection
of service users and members
of the public in the delivery of
council services
8 8 = 
Failure to achieve the
outcomes of the Community
Plan 
8 8 = 
56

Page 57

Risk
Category
2022 Risk description 2021
Residual
risk score
2022
Residual
risk
score
Change in
residual risk
scores
Key changes 
Failure to achieve the
outcomes of the Council Plan
N/A 8 New risk This new risk recognises the importance of
achieving the values, visions, priorities and
outcomes set out in the Council plan 
Increased costs providing
winter maintenance 
• Failure to provide essential
services during periods of
extreme winter weather 
8 8 = 
57

Page 58

58

Page 59

Report
Agenda Item 
To: Community and Enterprise Resources
Date of meeting: 13 December 2022
Prepared by: Executive Director (Community and Enterprise
Resources)  
Subject: South Lanarkshire Draft Tourism Strategy 
1. Purpose of Report
1.1. The purpose of the paper is to: - 
 provide an overview of the work undertaken to create a new draft South
Lanarkshire Tourism Strategy
 seek approval of the South Lanarkshire Tourism Strategy 
2. Recommendation(s)
2.1. The Committee is asked to approve the following recommendation(s):- 
(1) that the draft South Lanarkshire Tourism Strategy and Action Plan be approved. 
3. Background
3.1. As part of the 2021/2022 Revenue Budget, members approved a sum of £3 million
towards economic recovery under the heading “Get South Lanarkshire Working”.
Members’ high-level ambitions for the £3 million were broken down into three headings
– “Social Enterprise and Business Support”,” Locate in South Lanarkshire” and
“Tourism Cooperative and Strategy”. 
3.2. As a key business sector in South Lanarkshire, it is important to support and nurture
growth in the Tourism sector, taking advantage of South Lanarkshire’s natural
environment, heritage, and culture, not only to attract tourists from Scotland/UK and
abroad but also to encourage local people to spend their recreational time and money
closer to home. £0.5m of the funding was allocated to a South Lanarkshire Tourism
Strategy and potential creation of a Tourism Cooperative body. 
3.3. The new Tourism Strategy and associated Action Plan has been drafted to take
account of a rapidly changing sector at international, national, and local levels. 
3.4. The draft Tourism Strategy has been shared with partners, stakeholders and members
of the public within and outwith the Council as part of a consultation process and the
comments received have helped define the current document. 
3.5. In addition, a symposium event entitled “Shaping the future for South Lanarkshire
tourism” was held as an online webinar event on 1 February 2022 with 45 attendees
from both the public and private sector, with presentations from VisitScotland, Scottish
Tourism Alliance, Business Gateway, Elevator, Rural Dimensions and South
Lanarkshire Council Officers. 
7
59

Page 60

3.6. Tourism has been identified as a key sector in South Lanarkshire and has been
supported on a pan-Lanarkshire basis in partnership with VisitScotland and North
Lanarkshire Council. One of the principal themes of the first-ever Lanarkshire Tourism
Action Plan, launched in 2005, was to develop a tourism network structure in
Lanarkshire. The Lanarkshire Area Tourism Partnership was created to oversee the
action plan and agree strategic ambitions. 
3.7. Two independent associations were also created – the Lanarkshire Visitor Attractions
Association and the Lanarkshire Accommodation Association. To obtain better
synergies and organisation efficiencies, these groups were later merged to create the
Lanarkshire Tourism Association (LTA). Interest and membership in the LTA tailed off
in its latter years and, when the longstanding chair stepped down in 2020, the LTA
struggled to find volunteers willing to become office bearers and the decision was
made by its members to wind down the group. This coincided with the Covid-19
pandemic and the resultant shut down of the economy as a preventative measure has
had a particularly adverse effect on the tourism sector. Consequently, there is currently
no active tourism membership group that represents the South Lanarkshire tourism
sector as a whole. 
3.8. The allocated funding has been used to recruit an Economic Development Officer with
responsibility for the Tourism sector. An initial appointee left the Council’s employment
in February 2022 and, following a further recruitment process, a new officer was been
appointed in May. The £0.5m funding is intended to cover staff costs and technical
support and advice needed to set up a new Destination Marketing Organisation (DMO)
as well as promoting and marketing it to the industry to maximise numbers of local
tourism businesses signing up. A further member of staff may be recruited, when
appropriate, to undertake administration functions as a new tourism body for
Lanarkshire comes to fruition.   
3.9. Tourism is a key employer in South Lanarkshire and pre-COVID (2019-20) was
responsible for employing 3,013 full-time equivalent (FTE) jobs (Scottish Tourism
Economic Activity Monitor STEAM). The re-purposing of land and property to create
new tourism assets not only offers the potential to create new attractions to entice
visitors to visit the region and spend money, but it can also create facilities that local
communities can use and benefit from and can make facilities more viable than if they
were just relying on local custom, protecting, and enhancing jobs and communities.
Tourism, therefore, makes a significant contribution towards the Community Wealth
Building agenda as well as to the economy of South Lanarkshire. 
4. Draft Tourism Strategy 2022-2025
4.1. The proposed draft Tourism Strategy is attached at Appendix 1. 
4.2. In the new strategy ‘Our Vision’ for South Lanarkshire is:- 
 to cultivate a vibrant, successful visitor economy in South Lanarkshire which
promotes responsible growth and creates jobs and opportunities for communities
throughout the region 
4.3. The desire is for this to be a shared strategy which evolves to ensure that all sectors
of the South Lanarkshire tourism sector have their say in shaping the Strategy and the
associated action plan. In keeping with this collaborative approach, other public
agencies have been invited to feed in actions that will have a positive effect on South
Lanarkshire’s visitor economy. Actions that have been fed in are included in the
associated action plan (included in Appendix 1).
60

Page 61

4.4. The Strategy is intended to help the sector recover, increase the value of the tourism
sector, and positively enhance the benefits of tourism across South Lanarkshire by
delivering the very best for our visitors, our businesses, our people, our communities,
and our environment. 
4.5. It is important to note that this Strategy and action plan is not set in stone. The
economy is currently operating in a very fast moving, uncertain environment and it is
important to adopt a flexible approach to respond effectively to change. Should a new
tourism membership group be created in South Lanarkshire, it is recognised that
tourism businesses and wider stakeholders who form the membership of any new
group may wish to make changes to this Strategy and action plan. 
4.6. In summary, the strategy includes the following sections:- 
 Foreword – This briefly sets out the background and the focus of our proposed
activity around the six priority areas identified – People, Place, Business,
Marketing, Responsible Tourism and Partnership Working. 
 The Strategy in Context – South Lanarkshire is refreshing and launching a suite
of key strategies and plans including our Council Plan ‘Connect’, our Community
Plan, our Community Wealth Building Strategy, our Economic Strategy,
Sustainable Development and Climate Change Strategy and our Tourism
Strategy, all of which are inherently linked and informed by our communities. 
Council Plan priorities are:- 
 People – we need to put people first and reduce inequality
 Progress – we need to recover, progress and improve
 Planet – we need to work towards a sustainable future in sustainable places 
The Tourism Strategy dovetails with these priorities and seeks to promote
inclusive growth and maximise opportunities across all our communities as we
intensify our activity on the journey to net zero. 
 Consumer Trends – This sets out the consumer trends that have been identified
since the pandemic. At the time of writing this Strategy, various consumer trends
were being forecast and have been taken into account to maximise the Tourism
Strategy’s impact. 
 Strategic Priorities – We set out the key priorities of People, Place, Business,
Marketing, Responsible Tourism, Partnership Working (and the creation of
a new collaboration model). Further details on the priority areas, commitments,
actions and leading organisations can be found in the action plan contained in
Appendix 1. 
 Measuring Success - progress in delivering the action plan is measured through
the data sources currently available – the Council subscribes to two sources of
data on the sector - the regional Scottish Tourism Economic Activity Monitor
(STEAM) data and Visitor Attraction data from the Moffat centre. VisitScotland
are also leading on the Scottish Tourism Observatory project which aims to
create a resource for Scotland’s tourism industry which would make necessary,
relevant, and valuable data, analysis, and insight easily accessible. The Strategy
refers to other associated strategies and action plans. Existing monitoring and
reporting arrangements to monitor those action plans will remain in place to avoid
duplication and ensure consistency.
61

Page 62

 Delivering on our Ambitions - The key actions and areas of activity are set out in
the Strategy’s Action Plan (attached in Appendix 2) which defines our priorities,
outcomes, actions and how we will measure success. The Council cannot, by
itself, direct all of the activities set out in the Strategy and will rely on partners and
stakeholders to lead on some aspects of its delivery.  Nonetheless, the objective
is to show that the Council, as the democratic institution covering the area, has a
pivotal role – not only as a direct provider and deliverer of economic development
activity but also as a co-ordinator, influencer and facilitator of activity led by
others. The action plan is a dynamic document, designed to be agile and updated
using an evidence and data driven approach to recognise and meet changing
economic circumstances. 
5. Next Steps and Timescales
5.1. On the basis this Strategy is approved, it is intended to communicate it via publication
on the Council’s website. Officers will continue to engage with partners and
businesses providing support and advocating the creation of a sustainable,
collaborative industry body to coordinate actions and deliver the Strategy. 
5.2. During the implementation phase, annual updates on measuring the success of the
Strategy and Action Plan will be provided to relevant Committee. Officers recognise
that we will require to respond to ever changing economic challenges that are
influenced by national and international factors and consider how we can enhance the
level of activity in any of the key thematic areas to mitigate negative economic impacts
to our local economy. 
6. Employee Implications
6.1. The Council has recruited a full time Tourism Officer to finalise and assist with
delivering this Strategy’s action plan and measure its success going forward. Existing
resources within Enterprise and Sustainable Development that have already been
approved via the 2022/23 budget will also contribute to deliver actions where
necessary. 
7. Financial Implications
7.1. Community and Enterprise Resources have a budget of £0.094m for year 2022/2023
and £0.131m for year 2023/2024 to support the Tourism Strategy.  External funding
will also be sought from UK Government and Scottish Government funding streams to
maximise the impacts of activity across the sector. 
8. Climate Change, Sustainability and Environmental Implications 
8.1.  Following a Strategic Environmental Assessment (SEA) Screening and with the
agreement of the statutory Consultation Authorities, the Council made a formal
determination in May 2022 that a full SEA is not required for the Tourism Strategy.
This is because it is considered unlikely that new significant environmental effects
would be identified from implementing the Strategy which have not been identified,
assessed and reported within the South Lanarkshire Local Development Plan, the
Council Plan and the Community Plan. 
9. Other Implications
9.1. The key risk associated with the finalisation, delivery and monitoring of the Strategy is
the potential for further national and/or international economic shocks.  This could
constrain recovery and economic growth in the tourism sector both locally and
nationally.  
62

Page 63

10. Equality Impact Assessment and Consultation Arrangements
10.1. The requirement for an Equality Impact Assessment (EqIA) is currently being
reviewed. 
10.2. Council Resources and external partners have been consulted as part of the
consultation process. An online public consultation exercise has also taken place.
Responses have been considered and, where appropriate, incorporated into the
strategy and action plan.   
David Booth
Executive Director (Community and Enterprise Resources) 
24 November 2022 
Link(s) to Council Values/Priorities/Outcomes 
Values
 Focused on people and their needs 
Priorities
 We will work towards a sustainable future in sustainable places
 We will work to recover, progress and improve 
Outcomes
 Good quality, suitable and sustainable places to live
 Thriving business, fair jobs and vibrant town centres 
Previous References
 None 
List of Background Papers
 Draft South Lanarkshire Tourism Strategy 2022-2025 
Contact for Further Information
If you would like to inspect the background papers or want further information, please
contact: - 
Stephen Keating, Economic Development Manager, Enterprise and Sustainable
Development Services
Email: Stephen.Keating@southlanarkshire.gov.uk 
Laura Sprowl, Enterprise and Sustainable Development Services
Email: Laura.Sprowl@southlanarkshire.gov.uk 
63

Page 64

64

Page 65

7
65

Page 66

South Lanarkshire Tourism Strategy 2022-
2025 (Draft for consultation)
The vision – To cultivate a vibrant, successful visitor economy in
South Lanarkshire which promotes responsible growth and creates
jobs and opportunities for communities throughout the region. 
Foreword/summary
Tourism is a key sector in the South Lanarkshire economy. In the year prior to the COVID
pandemic, 2019, Lanarkshire attracted 614,820 visitors. These visitors generated an
economic impact of £204.5M for South Lanarkshire and the sector supported 3,013 full-time
equivalent (FTE) jobs (SOURCE: Scottish Tourism Economic Activity Monitor 2020). 
It is widely recognised that the Scottish tourism sector has been one of the sectors hit
hardest by the COVID-19 pandemic. South Lanarkshire tourism businesses have been hit
extremely hard. Loss of revenue, rising costs and staff recruitment difficulties have combined
to put a tremendous strain on business owners and their staff.
South Lanarkshire Council is determined to help the local economy recover and grow and
through this document encourages collaboration within the sector to raise the profile of
South Lanarkshire’s world class heritage, cultural and natural assets and attract more
visitors to the area. 
Our mission
 To cultivate a vibrant, successful visitor economy in South Lanarkshire
which creates benefits and opportunities for all. 
Tourism can be a force for positive change, it can sustain communities and the economy by
creating jobs, tackling de-population, and offers the possibility of improving the well-being of
local residents as well as visitors. With our new strategic approach, and a renewed spirit of
collaboration to facilitate a greater alignment between public, private and third sector tourism
stakeholders, we are confident that South Lanarkshire will not just recover lost ground, but
we can grow a stronger, more resilient visitor economy which will benefit communities
throughout the region. 
We are currently operating in a very fast moving, uncertain environment and it is important
that we adopt a flexible approach to respond effectively to change. 
It is important to note that this strategy and action plan are not set in stone and the desire is
for it to represent a set of shared goals which will evolve over time as new opportunities
arise. 
Partnership working will remain an important aspect of future delivery. South Lanarkshire
Council will continue to work in partnership with key long-standing partners including North
Lanarkshire Council, VisitScotland and Business Gateway to maximise opportunities for the
businesses and the wider area. We will also raise awareness of funding opportunities for the
tourism sector to ensure that South Lanarkshire achieves its fair share of support.
In keeping with this collaborative approach, a range of public agencies have identified
actions that will have a positive effect on South Lanarkshire’s visitor economy. A current list
of all actions to date are included in the Action plan at Appendix A. 
Date – November 2022
66

Page 67

Contents 
1. Strategic context 
2. Consumer trends 
3. Key priorities
• People
• Place
• Business 
• Marketing
• Responsible tourism 
• Partnership working 
4. Measuring success 
Appendix A Action plan 
Appendix B Strategic context- policies and plans 
67

Page 68

1. Strategic context 
In 2005, the first-ever Lanarkshire Tourism Strategy was launched. Subsequent strategies
were launched in 2009 and 2016. Previous strategies have all been pan-Lanarkshire
strategies covering both North and South Lanarkshire. This is the first South Lanarkshire
area specific tourism strategy which allows us to have a clearer focus on the challenges
and opportunities for the South Lanarkshire area.
Creating a strategy in an unpredictable and fast changing environment presents some
challenges. Rather than create a long-term strategy such as the national tourism strategy –
‘Scotland Outlook 2030,’ which covers a ten-year period, this strategy will cover a relatively
short timescale to the end of 2025, when a full review, evaluation and update can then take
place. Even though the accompanying action plan covers the same short timescale, it needs
to be flexible enough to allow the partners the ability to respond to changes in the operating
environment, market conditions and evolving consumer trends and behaviour. We would
therefore consider the action plan to be a live document which will be updated and modified
as required.
This Tourism Strategy has been developed as part of the wider work South Lanarkshire
Council are leading, together with partners, to refresh and launch a range of new key
strategies and plans including our Council Plan ‘Connect’, our Community Plan, our
Community Wealth Building Strategy, our Sustainable Development and Climate Change
Strategy, our Economic Strategy and this Tourism Strategy. All of these documents are
inherently linked and have been informed by what our communities have told us should be
our priorities:
• People – we need to put people first and reduce inequality  
• Progress – we need to recover, progress and improve  
• Planet – we need to work towards a sustainable future in sustainable places 
Tourism’s role in community wealth building (CWB)
Tourism plays a key role in community wealth building (CWB) and South Lanarkshire’s CWB
strategy includes five pillars which are:
• Spend: The council will support and encourage the local economy to grow
sustainably through the effective use of procurement to benefit local economies.
• Workforce: The council recognises the importance of employment for individuals and
families in terms of achieving potential, improving feelings of self-worth, achieving
financial independence, and reducing poverty.
• Land and Property: The council will use or repurpose council property and assets,
and that of other anchor organisations, in a socially productive way to generate
wealth for local citizens.
• Finance: The council will encourage and support communities’ financial growth,
including building and attracting development and investment opportunities and
encouraging local spend.
• Building the Generative Economy: The council will work to support local businesses,
not-for-profit organisations, and communities to safeguard and create local jobs and
address post-Covid recovery. 
Tourism offers tremendous opportunities to deliver CWB outcomes. The sector is a key
employer in the region and makes a positive contribution to the workforce pillar. The re-
purposing of land and property to create new tourism assets not only offers the potential to
create new attractions to entice visitors to visit the region to spend money, but it can also
68

Page 69

create facilities that locals can use and benefit from and can make facilities more viable than
if they were just relying on local custom, protecting, and enhancing jobs and communities. 
This strategy is influenced by the following strategic plans:
• Tourism Lanarkshire 2020
• Scotland Outlook 2030 and The Scottish Tourism Emergency Response Group
(STERG) Recovery Plans
• Scotland’s National Strategy for Economic Transformation (NSET)
• Scottish Agritourism A Strategy for Sustainable Growth
• Promote Economic Strategy for South Lanarkshire (2013-23)
• South Lanarkshire Community Wealth Building Strategy (CWB)
• South Lanarkshire Community Plan (2017-27)
• Connect 2017-2022
• Sustainable Development and Climate Change
• South Lanarkshire Good Food Strategy 2020-2025
• Spatial Planning
Further details on these documents can be found in Appendix B.  
69

Page 70

2. Consumer trends
At the time of writing this strategy various consumer trends were being forecast and
these have been taken-into-account when preparing this strategy and the
accompanying action plan. These trends include:
Localism and slow tourism will see people travelling less but travelling ‘better’ 
Consumers have long been encouraged to 'discover what’s on your doorstep' and 'think
global, act local', however, during and after the COVID-19 pandemic, this became a much
more tangible concept for all. This trend is predicted to remain with visitors seeking authentic
experiences, close to home. South Lanarkshire’s proximity to the ‘Central Belt’ of Scotland
and to the North of England, allied with good transport links will mean that we are ideally
positioned to benefit from consumers wishing to limit their travel time. 
Adaptable adventure
There is much evidence that the fundamental need for outdoor activities – which has been a
growing tourism driver for years – has been further strengthened by the pandemic-related
restrictions, with an increasing number of people becoming more active in their own local
areas or looking for alternative ways of staying healthy and physically fit.
Private, personalisation and premium experiences
There will be an increased demand for small group travel and private tours. Consumers will
seek personalisation and bespoke products and will plan and curate holidays which offer
cultural experiences, unique activities, and services that provide travel advice and route
planning services.
Travelling with purpose
It is predicted that wellness, fitness, and health enhancement will become increasingly
important considerations when visitors are choosing holiday destinations. 
Artisanal retail and food and drink
Consumers are looking to reconnect with the processes and products they use and the
people producing them, both at home and as part of planned trips. 
Workcations
Individuals are being enabled to make decisions about working environments based on their
own personal circumstances and, as such, can choose to work from less traditional settings
or combine work with opportunities to undertaken leisure activities.
Affordability 
In the current economic environment, with the cost-of-living crisis added to the economic
shocks of the past few years such as Covid and Brexit, at the forefront of people’s minds,
consumers are seeking affordable experiences that demonstrate value for money. 
All these trends and drivers represent future opportunities for the tourism sector.
Public agencies are here to support businesses as they respond to these
opportunities and changing environments and can provide help, advice, tailored
training programmes, financial assistance, and signposting to other sources of
support. 
70

Page 71

3. Key priorities
Our vision
 To cultivate a vibrant, successful visitor economy in South Lanarkshire
which creates benefits and opportunities for all. 
Key priorities
Our six key priority areas will centre on:
3.1 People 
3.2 Place 
3.3 Business
3.4 Marketing
3.5 Responsible tourism
3.6 Partnership Working
Each of the key priority areas includes a summary of proposed actions. Appendix A provides
the full detail for each action including suggesting which organisation will take the lead in
delivery. 
71

Page 72

3.1 People 
The South Lanarkshire tourism sector will become a career of choice. Our sector will
attract, develop, and retain a skilled, committed, diverse and valued workforce. 
Analysis undertaken on behalf of the Lanarkshire Economic Forum has identified the
following as key factors in the economic recovery in Lanarkshire.
• Employability - maximising outcomes for young people and
unemployed/underemployed adults across Lanarkshire’s communities; and 
• Skills - addressing current and future economic opportunities with specific emphasis
on the up-skilling and re-skilling of the workforce and safeguarding apprenticeships. 
Tourism is an important employer in Lanarkshire and pre-COVID (2019-20) was responsible
for employing 3,013 full-time equivalent (FTE) jobs (Scottish Tourism Economic Activity
Monitor STEAM). 
Tourism is a valuable provider of jobs as it offers job creation opportunities throughout our
urban and rural communities. By creating quality jobs offering the right pay and conditions,
there are huge opportunities to grow employment within the tourism sector, with our tourism
businesses becoming more aware of fair work practices and more responsible employers.
Tourism offers vast, meaningful, and exciting opportunities for our future and existing
workforce.  If we want our tourism sector to grow, it is vital that the South Lanarkshire
tourism sector attracts, trains, and retains the size and quality of workforce needed to meet
the sector’s needs and growth ambitions. 
The COVID pandemic and the EU Exit has created significant challenges for the South
Lanarkshire tourism sector, and we will work together to increase the number and quality of
tourism employment opportunities, develop sustainable career pathways and tourism
becoming a career of choice rather than a default sector. 
Collaborations are taking place to address skills shortages in the tourism and hospitality
sectors such as the CareerScope job portal, founded by Springboard, Hospitality Action, the
Institute of Hospitality, The Scottish Tourism Alliance, Savoy Educational Trust and UK
Hospitality. 
Proposed actions
To help deliver an effective people strategy we will: 
• Encourage work placements in the tourism and hospitality sectors.
• Provide support to individuals to enable them to develop their skills. 
• Provide recruitment support to employers via the Flexible Workforce Development
Fund. 
• Raise the profile of the tourism sector as a career of choice, promote the courses we
offer and attract applicants.
• Actively engage with Tourism employers in South Lanarkshire to ensure our further
and higher education institutions’ curriculum offer meets their needs of staff new to
the Tourism industry and for staff progression and upskilling.
• Seek opportunities to network across the Tourism industry within South Lanarkshire
through our engagement with the Federation of Small Businesses, Lanarkshire
Chamber of Commerce and Trade and other industry bodies.
• Support Scotland Food & Drink’s Regional Food Tourism Ambassador Programme.
72

Page 73

3.2 Place
We will create and develop an attractive, competitive visitor destination. 
A rich history
South Lanarkshire has a lot to offer potential visitors with an exciting mix of urban and rural
experiences. An undoubted strength is our wealth of historic assets which has been recently
enhanced by the addition of The David Livingstone Birthplace following a £9 million
investment.
The new David Livingstone Birthplace Museum complements an already strong heritage
offering which includes the William Adam designed Chatelherault Hunting Lodge located
within the vast Chatelherault Country Park. Other historic Duke of Hamilton heritage assets
include the magnificent Hamilton Mausoleum, and Low Parks Museum with its Cameronians
(Scottish Rifles) Gallery reflecting over 300 years of this unique regiment's story. In addition
to castles – Bothwell and Craignethan – other South Lanarkshire heritage attractions include
the 5-star Biggar and Upper Clydesdale Museum and National Museum of Rural Life. 
The most iconic historic asset in the region however is undoubtably New Lanark World
Heritage Site. The new UNESCO National Trail in Scotland which will digitally connect the
13 UNESCO World Heritage Sites, Biosphere Reserves, Global Geoparks and Creative
Cities, is sure to offer opportunities to encourage visitors to stay longer and spend more
locally.
At one with nature
South Lanarkshire offers a mix of natural assets ranging from the popular Calderglen
Country Park in East Kilbride, one of the region’s most visited attractions, through to a large
beautiful rural landscape. Visitors wanting to explore the region either by foot or by bike will
not be disappointed as South Lanarkshire has an extensive core path network (2217 km)
including the Clyde Walkway, and two National Cycle Routes connecting to Glasgow,
Edinburgh, and Carlisle.
Venues, events, and festivals
The area offers high-quality venues including the Category A listed Edwardian Baroque Style
Hamilton Town House, the Scottish Baronial Style Rutherglen Town Hall, and the impressive
Lanark Memorial Hall. South Lanarkshire has some popular and well-established events and
festivals including Lanimers Day, and the Strathaven Balloon Festival. Expanding the
region’s calendar of events will be largely dependent on being able to make South
Lanarkshire a more attractive destination for event organisers. 
For example, the first edition of the combined UCI Cycling World Championships will be held
between August 3-13, 2023, Described as an '11-day mega event' by the UCI,
the Glasgow 2023 World Championships will bring together 13 different cycling World
Championships, across at least six different locations around Glasgow and southern
Scotland. This presents a great opportunity for South Lanarkshire Tourism businesses.
Tourism infrastructure and transport
South Lanarkshire has some excellent transport links and has the M74 running right through
the area. South Lanarkshire has benefitted from transport improvements in the past few
years particularly with regards to the M8/M73/M74 upgrade, including works at the Raith
Interchange. The area is also home to the picturesque Clyde Valley Tourist Route. 
In addition to the road network, many South Lanarkshire attractions are served by train and
bus stations. It is important from an environmental as well social inclusion point of view that
public transportation is well promoted through all activity.
73

Page 74

Visitor accommodation 
Visitors to South Lanarkshire can choose from a diverse range of accommodation options
ranging from urban hotels through to farm stay self-catering and bed and breakfasts. In the
last few years, the region’s hotel stock has been boosted by the addition of the Hampton by
Hilton, Hamilton Park, The Premier Inn Hotel in Hamilton and the Ramada by Wyndham,
East Kilbride. Several other developments are currently in the pipeline with an expansion to
Crossbasket Castle and the proposed Lannraig Scotland Resort planned near Carnwath. 
One area which requires further investigation is the growth in caravan and campervan
usage. The increase in campervan ownership has been keenly noticed since the COVID
pandemic Whilst perhaps not as badly affected as some hotspot areas such as Loch
Lomond National Park, Skye and the Pentland Hills, South Lanarkshire has not been
immune to issues with Tinto Hill being particularly affected. With the growth in caravan and
campervan ownership showing no signs of abating, the council and private and public sector
partners will need to consider how best to respond to this development in a way that
mitigates any negative impacts whilst taking advantage of the opportunities that this market
growth offers.
Another trend is the establishment of short term let accommodation. This can result in the
provision of reasonably priced accommodation where it is appropriately managed. The law
around short-term lets recently changed and from 1 October 2022 those who provide short-
term let accommodation need to apply for a licence from South Lanarkshire Council in order
to operate. 
South Lanarkshire food and drink
Food and drink are an important part of the tourism mix and experience and help to shape
visitor’s perceptions of a destination. While food and drink are not typically drivers of
destination choice, food and drink are key elements that can significantly enhance our
visitors’ experience – and therefore enjoyment – of a particular destination. Local food and
drink products and activities can help foster a sense of connection to South Lanarkshire’s
natural environment, local people, local customs and help create a sense of place as visitors
increasingly seek local produce
With visitors increasingly seeking new experiences, local produce, and ways to partake in
sustainable tourism, agritourism has become a growing consumer trend. Agritourism is
something that we are seeing throughout South Lanarkshire in the form of farm stays, farm
shops which sell locally grown and sourced produce, and farm visits. 
Locally, ‘Lanarkshire Larder,’ a local network of food and drink businesses, is working hard
to raise the profile of the region’s food and drink offering. With our rich and seasonally
variable larder, and wide range of excellent independent producers, South Lanarkshire is
well placed to excel in the provision of locally sourced, high-quality food and drink products
for visitors.
Availability and the promotion of local food and drink in the hospitality sector is important.
VisitScotland’s Taste our Best Quality Assurance scheme has a role to play here as it
recognises high quality and locally sourced produce. South Lanarkshire Council’s Food &
Drink Officer works closely with the food and drink sector in the area and with the national
agency Scotland Food & Drink to champion local produce and assist with supporting the
industry.   
74

Page 75

Retail and town centres
South Lanarkshire’s town centres are diverse and perform many functions including
education, health, shopping, public services, leisure, culture and history. Our towns are
multipurpose destinations which support the visitor experience by providing amenities,
quality places to eat and drink, transport links and retail. This in turn provides income, jobs
and services for our local communities.
Each town centre has its own unique identity and history – from picturesque market towns
such as Lanark, Strathaven and Biggar to those with an abundance of leisure activities such
as East Kilbride. The range of different town centre offers throughout the authority mean that
there is an experience to attract every type of visitor. 
Our town centres have to adapt to survive and generating visitors through tourism will be
vital to achieving this goal.
Creating high quality, authentic and memorable experiences
To remain competitive, the South Lanarkshire tourism industry will need to provide a wide
range of high quality, and memorable visitor experiences that fully utilise our strengths, our
assets and responds to visitor trends.
Creating a memorable experience is critical and our attractions must continue to evolve to
generate repeat visits.
High quality visitor experiences will require us all to monitor visitor feedback and take-action
where necessary. Communication takes place with agencies such as VisitScotland,
Association of Scottish Visitor Attractions and Green Tourism, who all operate quality
assurance schemes and training programmes, to explore if partnership activity could help
provide Lanarkshire businesses with the quality assurance support that they require.
Through partner collaboration we will undertake some exploratory work to find out what
support, if any, is required and desired.
Proposed Actions
To help deliver the place priority, we will:
• Ensure national planning policy on tourism and the visitor economy is considered in
decision making on planning applications.
• Work to secure funding to develop and enhance the tourism and visitor infrastructure.
• Work with communities to support community-led tourism opportunities.
• Work with town centre partners and stakeholders to ensure that our towns are a
welcoming, functional, and vibrant place to live, work, visit and do business.
• Extend the Clyde Walkway south from its current termination point at New Lanark to
connect with adjacent sections of the ‘Scotland’s Great Trail’ network.
• Provide a tourism offer that will directly contribute to the quality of life for South
Lanarkshire’s residents via improved places to visit, looking after our environment
and greenspace, including thriving country parks for all to enjoy.
• Provide a programme of high-quality productions throughout our 5 Cultural Venues to
encourage theatre goers to remain within the (South) Lanarkshire area rather than
travel to neighbouring authorities and additionally will enhance Lanarkshire as an
area to visit from out with the locality. 
• Encourage the media/film industry to use our locations and our rural landscape and
heritage settings as film locations, raising the profile of our venues.
• Further develop new and diverse accommodation options. 
75

Page 76

3.3 Business 
We will build business resilience, sustainability, improve viability and profitability. 
Research undertaken on behalf of the Lanarkshire Economic Forum has identified new
business starts, sustaining and growing existing businesses, and building the capacity and
capability of companies, as critical elements in Lanarkshire’s economic recovery.
The national tourism strategy – Scotland Outlook 2030 paints a picture of success involving:
• Our businesses will thrive in a supportive environment, adopting responsible and fair 
business practices whilst being open to change and committed to investing in their
future.
• Businesses will have a stronger capability to secure appropriate investment which
will be reflected in the productivity of the sector, showing positive improvement,
growth and improved financial returns. 
• We will see all businesses able to embrace innovation and technology to create and
deliver new and better visitor experiences in line with the changing landscape and
consumer behaviour.
Several public agencies already provide financial support to the tourism sector. South
Lanarkshire Council’s Business Support team provide help and support to businesses
through advice and offer financial grant support in the form of small grants up to £3000, and
larger recovery and growth grants up to £20,000, (There is a proposal to increase the
maximum grant to £50k being presented to Council on 7 December.) The team provide a
business one-stop-shop by making introductions and signposting businesses to partners and
other relevant council departments. 
Business Gateway Lanarkshire, through their team of specialist advisors, provide a range of
advice, expert knowledge, market intelligence, workshops, advise on funding opportunities
and events to help businesses achieve their goals. 
Other national public agencies are on hand to help Lanarkshire tourism businesses and
include VisitScotland Skills Development Scotland and Scottish Enterprise. 
Industry bodies also offer advice, support and training opportunities to the tourism sector and
include the Lanarkshire Chamber of Commerce and Trade, Scottish Tourism Alliance (STA),
Federation of Small Business (FSB) and the Association of Scottish Visitor Attractions
(ASVA). 
76

Page 77

Proposed actions
To help support our businesses we will: 
• Provide financial support to tourism and hospitality businesses through the council’s
business support grants.
• Provide advice and support to tourism and hospitality businesses via the Business
Gateway Lanarkshire service.
• Work together with other partners to support tourism and hospitality businesses.
• Drive product development with existing and new pipeline businesses.
• Support businesses to deliver high quality memorable experiences which benefit
visitors and the places they visit.
• Support business through successful delivery of digital skills and development
advice.
• Support and advise businesses in the adoption of responsible tourism practices and
development of sustainable experiences.
• Support tourism businesses to build business resilience, sustainability, improve
business viability and profitability.
• Further develop networking connections between tourism businesses to coordinate
and extend the tourism offer, events and attractions. 
77

Page 78

3.4 Marketing
We will raise the profile of South Lanarkshire as an attractive visitor destination.  
Consumer segments
VisitScotland’s national segmentation model helps optimise marketing spend. It helps us to
understand visitor behaviours and target communications to the right consumers with shared
needs using the most cost effective and targeted marketing channels. 
VisitScotland have identified 5 target segments:
• Natural Advocates
• Curious Travellers
• Engaged Sightseers
• Adventure Seekers 
• Food-Loving Culturalists
Natural Advocates, Curious Travellers and Engaged Sightseers appear be the most
appropriate prospects for the South Lanarkshire tourism offering. With Engaged Sightseers
preference to use ‘trusted’ or well-known websites, and National Advocates being the
heaviest users of official country tourism websites, it is important that South Lanarkshire
content is maximised and communicated on VisitScotland channels to ensure we also
benefit from United Kingdom marketing spend.
Natural Advocates
Natural Advocates tend not follow the crowds and desire holidays that help them to
unwind, recharge and enjoy quiet time. With their desire to get away from it all, rural
South Lanarkshire will appeal to this segment. 
Curious Travellers 
A holiday or break for the Curious Traveller will pack a lot in, exploring the history
and culture of destinations, enjoying scenery and landscapes, getting ‘off the beaten
track’ and trying new things will all appeal to their natural curiosity. Enjoying the
outdoors via hiking, rambling or short walks and taking in natural sites are also
activities that this segment will relish. 
Engaged Sightseers 
Engaged Sightseers are above average holiday takers, taking the highest number of
nights away on holiday per year of all the segments.  Engaged Sightseers particularly
enjoy spending their UK holiday time touring and general sightseeing. Historical
places are of great interest as well as scenery, nature, and wildlife. They enjoy
visiting castles, monuments, parks and gardens, museums, and galleries. Short
walks will appeal but typically they will not participate in more active sports.
Digital marketing – capacity building
Having a welcoming, visible, and bookable website is key to attracting new
customers to a tourism business. Today’s holidaymakers use a wide variety of
channels to find and book trips and it’s no surprise that the greeting they receive
online should be as welcoming as it is in person. From search engine listings to
social media platforms and online travel agent websites, the secret to being found is
to maintain a strong presence in the places your customers look for inspiration. 
78

Page 79

Many tourism businesses have invested a great deal in their digital offering but with
advances occurring at a rapid rate, there is a need to stay up to date and ensure that
individual business websites are discoverable and bookable. 
Business Gateway Lanarkshire and other agencies offer regular free training which allow
businesses to develop their digital knowledge so they can continue to invest in their digital
offering. 
VisitLanarkshire
Given that the VisitLanarkshire brand and associated website is now well established, the
intention will be to continue to use this VisitLanarkshire brand in the immediate future for
consumer marketing. It is imperative that all tourism businesses are listed on this website to
benefit from these marketing campaigns.
Regional tourism websites have changed over the past few years, so the website is currently
being refreshed and it will act as an effective portal for planning a trip to South Lanarkshire
and then direct visitors out to the individual business external websites to make their
booking.
Proposed actions
To help the marketing priority we will: 
• Raise the profile and digital booking ability of South Lanarkshire tourism offering.
• Ensure that South Lanarkshire is represented in Glasgow City Region (GCR) tourism
marketing activity.
• Gather tourism data to inform collaborative and individual decision making and share
with tourism operators.
• Promote use of local food and drink produce (promotion and events) across business
sectors including tourism.
• Promote our town centres.
• Work with VisitScotland to profile our visitors and understand their needs.
• Work with VisitScotland to enhance visitlanarkshire.com.
• Work with VisitScotland to enhance South Lanarkshire content in relevant marketing
activity.
• Raise the profile of South Lanarkshire Leisure and Culture assets.
• Promote the development of tourism sector and connections between businesses,
events and attractions and offers to extend visitor stays and spend in South
Lanarkshire. 
79

Page 80

3.5 Responsible tourism
We will develop a sustainable visitor economy, maximising the positive impacts, and
minimising any potential negative impacts.
What is responsible tourism? 
Responsible tourism requires the South Lanarkshire tourism industry, public sector
agencies, communities, and visitors to work collectively to maximise the positive economic,
social, and environmental impacts of their activity, and minimise the negative ones. 
Responsible tourism considers not only the needs of the visitor and the tourism industry, but
also host communities and the environment. 
There are three strands to a responsible tourism approach: 
1. Sustainability - environmental, cultural, and economic
• Environmental - looking after our key South Lanarkshire assets by seeking to
address the impacts of climate change and reducing harm to the natural and
built environment.
• Cultural - protecting our cultural heritage; our attractions, events, and
activities. 
• Economic – enabling economic growth whilst ensuring progress is beneficial
to everyone. 
2. Inclusion - ensuring South Lanarkshire is a place for everyone by prioritising
accessibility and inclusivity, so no one faces barriers to visiting the area.
3. Communities - connecting visitors and host communities meaningfully while working
with local people to make sure they experience the benefits of tourism – economic,
social and well-being. 
Why is responsible tourism important? 
We have a duty of care to protect our assets for the future. A responsible approach to
tourism will help South Lanarkshire’s attractiveness, help communities thrive, and enable
growth and at the same time minimising any negative impacts. 
Working towards a low carbon economy 
Sustainable Development and Climate Change is a key focus of the national tourism efforts
and is also shared by South Lanarkshire Council. 
The Sustainable Development and Climate Change Strategy 2022-2027 has been agreed.
The council has also signed up to the Glasgow Food and Climate Declaration and Edinburgh
Biodiversity Declaration. In addition, emerging planning policy at a national level is heavily
focussed on addressing climate change which in turn will be addressed in Local
Development Plan 3. 
VisitScotland have already committed to:
• Take action to reduce carbon emissions as an organisation and encourage Scotland
tourism industry to consider and address their carbon footprint. 
• Work collaboratively with the Scottish tourism and events industry to educate and
share best practice around effectively reducing carbon emissions. 
• Play a leading role in the development of Scotland as a globally recognised
responsible destination. 
80

Page 81

• Engage our communities to make sure they are at the heart of our responsible
tourism future. 
As a tourism sector we should ensure that we engage and support the efforts of
VisitScotland and other agencies such as Scottish Enterprise who are progressing projects
to work towards a low carbon economy and do likewise with efforts being made at a council
level. 
Proposed Actions
To help support responsible tourism we will: 
• Explore low carbon opportunities.
• Develop more sustainable town centres.
• Reduce our carbon footprint by utilising digital communication channels when
appropriate to do so  
• Encourage visitors to act responsibly when visiting South Lanarkshire.
• Develop tourism programmes to include input on the sustainable visitor economy and
how to maximise positive and minimise negative impacts
• Develop planning policies to ensure the delivery of the Tourism Strategy is
sustainable. 
81

Page 82

3.6 Partnership working 
Collaborative working will allow the South Lanarkshire tourism sector to realise its
full potential.
While there is a strong history of successful partnership working in Lanarkshire, there is
currently no formal grouping or structure in place for the industry. 
South Lanarkshire Council already has well established links and levels of engagement with
other bodies involved in tourism initiatives including VisitScotland, Scottish Enterprise and
has a long-established working relationship with North Lanarkshire Council delivering, who
share the management of the VisitLanarkshire brand and associated marketing activity.  
The Scottish Governments NSET strategy highlights the importance of Scotland’s Regional
Economic Partnerships as they bring together key economic drivers to enhance regional
interests, focus and align resources and provide the opportunity to share knowledge and
expertise.
The council is a member of the Glasgow City Region Tourism Portfolio group, as well as the
Scottish Local Authority Economic Development (SLAED) tourism group and the Scottish
Tourism Alliance. The council’s arms-length organisation – South Lanarkshire Leisure and
Culture, is a member of the Association of Scottish Visitor Attractions (ASVA). 
Successful delivery however will require the input from the sector itself, and a wide number
of stakeholders including the Lanarkshire Chamber of Commerce and Trade and the
Federation of Small Business. The importance of our further education establishments –
University of the West of Scotland, South Lanarkshire College and New College Lanarkshire,
and our schools will also be critical as we aim to progress our tourism people strategy. 
Proposed Actions
To help promote partnership working we will: 
• Continue to listen to the views of the Lanarkshire tourism sector on their desire for a
new collaborative tourism membership organisation and what form it should take.  
• Utilise Regional Economic Partnerships to raise the profile of our tourism offering.
• Work in partnership with North Lanarkshire Council on appropriate pan-Lanarkshire
activity.
• Encourage joint working with tourism colleagues across the 32 local authorities in
Scotland.
• Support food and drink networks and linkages to tourism businesses in South
Lanarkshire.
• Work in partnership with employers in the Tourism sector in South Lanarkshire to
support their training and development needs to help realise the potential of their
business and of their employees 
82

Page 83

4 Measuring success
Tourism Action Plan
The current action plan at appendix A, in November 2022, includes actions from the council
and some public sector partners. Each action has a nominated lead officer and progress will
be monitored and shared. 
This is intended to be a shared document and additional activities will be identified and
tracked as the strategy progresses.  
Data sources
The council already subscribes to twos sources of data on the sector – the regional Scottish
Tourism Economic Activity Monitor (STEAM) data and Visitor Attraction data from the Moffat
centre. STEAM data provides us with data relating to visitor numbers, volume and value data
and employment statistics. 
This information will allow us to compare data and trends with the majority of local authorities
in Scotland and will also allow us to compare current performance against historical data as
we have subscribed to this model for several years. The Moffat Centre’s Visitor Attraction
Monitor provides good quality trend data for the visitor attraction sector.
This is a partnership document and, pending the potential forming of a collaborative tourism
group, it is anticipated that such a group will take action to monitor and measure the success
of the action plan. Each lead organisation will require to take responsibility for their
respective actions in the action plan and measure their actions regularly and report back as
evidence of progress in delivering the strategy in addition to economic outcomes like
numbers of new businesses, employment and turnover. 
83

Page 84

Appendix A – Tourism Action Plan 
These actions are intended as an initial list of actions that will be delivered by South Lanarkshire Council and other partners. The intention is
that this will be a live document which will get updated and changed over time. It is recognised that a new tourism membership group (if
created), may wish to re-prioritise, progress, and deliver activity to address the specific challenges and opportunities that they believe need to
be addressed.     
People
We will: High Level
Actions
Steps we will take to deliver this
action
How will we know
this step is
complete and
measure
outcomes?
Timescales  Lead 
Support
apprenticeships in the
tourism and hospitality
sectors
Fund and
promote
hospitality and
travel Foundation
Apprenticeships,
Modern
Apprenticeships
and Graduate
Apprenticeships  
Work with industry to identify
demand for apprenticeships
Number of
hospitality and
travel Foundation
Apprenticeships,
Modern
Apprenticeships
and Graduate
Apprenticeships
2022 - 2025 Skills
Development
Scotland
(SDS) Contract with Training providers to
deliver apprenticeships
Promote apprenticeships through
our digital portals 
https://www.apprenticeships.scot/  
https://www.ourskillsforce.co.uk/
84

Page 85

People
We will: High Level
Actions
Steps we will take to deliver this
action
How will we know
this step is
complete and
measure
outcomes?
Timescales  Lead 
Provide financial
support to individuals
to enable them to
develop their skills 
Provide financial
support via
Individual
Training Accounts
(ITAs) which is
administered by
SDS
Promote ITAs to individuals across
Scotland
Number of
individuals who
secure ITAs,
number of training
courses completed
Ongoing SDS
Provide support to
employers via the
Flexible Workforce
Development Fund 
• Provide
support &
promote the
Flexible
Workforce
Development
Fund
Promote the fund to employers
through the SDS website and via
other channels
Applications are via SDS who will
review and evaluate applications
Number of
employers and
employees
supported/assisted
Ongoing SDS
Through our
marketing strategy
work to raise the
profile of the tourism
We review our
curriculum offer in
Travel and
Tourism annually
Keep up to date with industry
trends and leading industry bodies
to ensure curriculum is kept up to
date
Publication of all
courses including
those relating to
Tourism courses
Ongoing South
Lanarkshire
College
85

Page 86

People
We will: High Level
Actions
Steps we will take to deliver this
action
How will we know
this step is
complete and
measure
outcomes?
Timescales  Lead 
sector as a career of
choice, promote the
courses we offer and
attract applicants.
on the College
website
To review our
Marketing
Strategy 
Evaluate the success of previous
campaigns and adapt to suit
changes in curriculum and the
sector as a whole
That we attract
students to relevant
courses either
those new to the
Tourism industry or
by delivering
upskilling to those
already in the
Tourism industry 
Ongoing South
Lanarkshire
College
Actively engage with
Tourism employers in
South Lanarkshire to
ensure our curriculum
offer meets their
needs of staff new to
the Tourism industry
and for staff
progression and
upskilling. 
Through
consultation we
will align our
curriculum offer to
meet the needs of
the South
Lanarkshire
Tourism sector  
Contact South Lanarkshire Tourism
sector employers to consult on the
relevance of the curriculum offer in
Tourism and to adapt the
curriculum to meet the needs of the
Tourism sector
When contact has
been made and
arrangements to
meet and/or
network with
Tourism sector
employers. 
That the curriculum
has been reviewed
to meet the needs
of the Tourism
sector
Academic
Year (AY)
(Aug - Jun)
22/23 and
beyond
South
Lanarkshire
College 
Through
networking with
relevant South
Contact relevant South Lanarkshire
Tourism networking groups
When contact has
been made and
arrangements to 
South
Lanarkshire
College
86

Page 87

People
We will: High Level
Actions
Steps we will take to deliver this
action
How will we know
this step is
complete and
measure
outcomes?
Timescales  Lead 
Lanarkshire and
national groups
relating to
Tourism we will
promote South
Lanarkshire
college courses
meet and/or
network with
Tourism
businesses.
Successful
engagements with
the tourism sector
employers and the
sharing of relevant
course information 
Place 
We will: High Level Actions Steps we will take to deliver
this action
How will we know this
step is complete and
measure outcomes?
Timescales  Lead 
Develop planning
policies to support
the delivery of the
Tourism Strategy
Existing policy on the
visitor economy and
tourism will be
reviewed and
refreshed
Prepare South Lanarkshire
Local Development Plan 3
Adoption of SLLDP3 The finalised
SLLDP3 will
be produced
in 2027/28
but
preparatory
work will
begin long
before this.  
SLC Planning
87

Page 88

Place 
We will: High Level Actions Steps we will take to deliver
this action
How will we know this
step is complete and
measure outcomes?
Timescales  Lead 
Prepare Rural Design Guide
to include visitor facilities and
accommodation
Committee approval of
Supporting Planning
Guidance
Dec 2022 SLC Planning
Ensure national
planning policy on
tourism and the
visitor economy is
considered in
decision making
on planning
applications
Establish National
Planning Framework
4 as key issue once it
is approved and
becomes part of the
Development Plan
Prepare interim Supporting
Planning Guidance based on
NPF4 as appropriate 
Committee approval of
Supporting Planning
Guidance
Mar 2023 SLC Planning
Engage with the tourism
industry and partner
organisations when preparing
policy and SPG
Hold engagement event  Dec 2022 SLC Planning
Work to secure
funding to
develop and
enhance the
tourism and visitor
infrastructure 
Prepare and submit
funding bids
Develop designs and costings
for missing long distance
walkway sections in S
Lanarkshire. Submit
applications for funding 
Securing funding and
construction of long-
distance paths 
Mar 2024 SLC Rural and
Funding Team  
Develop Clyde100 concept
and designs for associated
infrastructure improvements
creating proposals for
enhanced SLC infrastructure
at key locations 
Secure funding for
design and scoping of
projects 
Dec 2022 SLC Rural and
Funding Team  
Work with third sector,
landowners, and community
organisations and trusts to
develop the quality and variety
of the visitor experience 
Value of funding
secured for enhanced
visitor facilities and
attractions   
Mar 2024 SLC Rural and
Funding Team  
88

Page 89

Place 
We will: High Level Actions Steps we will take to deliver
this action
How will we know this
step is complete and
measure outcomes?
Timescales  Lead 
Work with
communities to
support
community led
tourism
opportunities 
Undertake a rural community
tourism engagement
consultation. Assessing,
demands, pressures, and
opportunities identified by
rural communities.
Report completed   2022 SLC Rural and
Funding Team  
Work with town
centre partners
and stakeholders
to ensure that our
towns are a
welcoming,
functional, and
vibrant place to
live, work, visit
and do business. 
Work with town
centre organisations
such as Development
Trusts and Business
Improvement Districts
to enhance the town
centre offer. 
Regular meetings and
coordination with
organisations to support their
ambitions 
Minutes of meetings
etc. 
Ongoing  SLC Town
Centre
Management
Team
Extend the Clyde
Walkway south
from its current
termination point
at New Lanark to
connect with
adjacent sections
of the ‘Scotland’s
Great Trail’
network.
Create connection
south to the Southern
Upland Way at
Leadhills/
Wanlockhead
• Review Clyde
Walkway extension
feasibility study
• Undertake landowner
and community
consultation
• Secure funding from
appropriate sources
including Renewable
Energy Fund 
• Completion of
landowner and
community
consultation
• Funding secured
• Detailed design
specifications
and costings
prepared
• Completion of
contract
documentation 
2025 SLC Countryside
and Greenspace
Service in
partnership with
Planning and
Regeneration
Services
89

Page 90

Place 
We will: High Level Actions Steps we will take to deliver
this action
How will we know this
step is complete and
measure outcomes?
Timescales  Lead 
• Prepare detail design
specifications and
costings
• Prepare contract
documentation
• Undertake site
implementation
Create connection
east via Biggar to join
with the John Buchan
Way in the Scottish
Borders
• Review Clyde
Walkway extension
feasibility study
• Undertake landowner
and community
consultation
• Secure funding from
appropriate sources
including Renewable
Energy Fund 
• Prepare detail design
specifications and
costings
• Prepare contract
documentation
• Undertake site
implementation
• Completion of
landowner and
community
consultation
• Funding secured
• Detailed design
specifications
and costings
prepared
• Completion of
contract
documentation
2025 SLC Countryside
and Greenspace
Service in
partnership with
Planning and
Regeneration
Services
Connection west via
Douglas and Glespin
to the River Ayr Way
in East Ayrshire
• Review Clyde
Walkway extension
feasibility study
• Undertake landowner
and community
consultation
• Completion of
landowner and
community
consultation
• Funding secured
2025 SLC Countryside
and Greenspace
Service in
partnership with
Planning and
90

Page 91

Place 
We will: High Level Actions Steps we will take to deliver
this action
How will we know this
step is complete and
measure outcomes?
Timescales  Lead 
• Secure funding from
appropriate sources
including Renewable
Energy Fund 
• Prepare detail design
specifications and
costings
• Prepare contract
documentation
• Undertake site
implementation 
• Detailed design
specifications
and costings
prepared
• Completion of
contract
documentation
Regeneration
Services
Provide a tourism
offer that will
directly contribute
to the quality of
life for South
Lanarkshire’s
residents via
improved places
to visit, looking
after our
environment and
greenspace
including thriving
country parks for
all to enjoy
Turn our assets into
experiences attracting
new and repeat
visitors   
Review and develop our
cultural programme to best fit
our target markets, providing
imaginative and creative
programming and curation of
collections, exhibitions,
events, and festivals. Deliver a
visitor attraction activities and
events programme
Annual visitor numbers Dec 2022
then annual
reviews
South
Lanarkshire
Leisure and
Culture (SLLC) 
Invest in our local
heritage to ensure we
sustain our tourism
offer  
Seek external funding
opportunities to invest in our
open spaces. 
We will study visitor numbers
at Key assets eg Tinto Hill in
order to improve facilities to
meet demand. 
External funding
secured and delivery of
investment projects
Dec 2022
then annual
reviews
SLLC
91

Page 92

Place 
We will: High Level Actions Steps we will take to deliver
this action
How will we know this
step is complete and
measure outcomes?
Timescales  Lead 
We will Promote the 6 SLL&C
golf courses. 
Provide a
programme of
high-quality
productions
throughout our 5
Cultural Venues
to encourage
theatre goers to
remain within the
(South)
Lanarkshire area
rather than travel
to neighbouring
authorities and
additionally will
enhance
Lanarkshire as an
area to visit from
out with the area
Work in partnership
with similar services
in North Lanarkshire
to provide a
comprehensive
offering from
Lanarkshire as a
whole.
Programme high quality
performances and companies.   
Ticket sales Dec 2022
then annual
reviews 
SLLC
Invest in the
infrastructure of our
venues to ensure
they are ‘fit for
purpose’ in terms of
delivering large scale
productions
Investigate funding and capital
expenditure opportunities to
invest and enhance the quality
of performances and invest in
our venues, including
equipment
Total funding secured Dec 2022
then annual
reviews
SLLC
Research caravan
and camping
provision and the
demand and
appropriateness
for Aires provision
in the area 
Research demand
and explore
appropriate delivery
options to meet this
demand.
Gather views from interested
stakeholders, liaise with other
local authorities who have
operated pilot schemes and
explore the viability of
potential pilot schemes/sites.
Initial research
completed. Pilot
scheme(s) identified.
2023/2024 SLC Tourism
Officer,
Economic
Development
working in
partnership with
planning, roads,
92

Page 93

Place 
We will: High Level Actions Steps we will take to deliver
this action
How will we know this
step is complete and
measure outcomes?
Timescales  Lead 
and licensing
colleagues
Encourage the
media/film
industry to use
our locations and
our rural
landscape and
heritage settings
as film locations 
Work in collaboration
with the film industry
to identify suitable
locations
Establish links with potential
partners
Number of film
bookings secured
Dec 2022
then annual
reviews
SLLC
93

Page 94

Business
We will: High Level Actions Steps we will take to
deliver this action
How will we know this
step is complete and
measure outcomes?
Timescales  Lead 
Provide support
to tourism and
hospitality
businesses
through the
council’s grants
scheme 
Offer targeted support
to South Lanarkshire
tourism and hospitality
businesses, enabling
them to create and
safeguard jobs,
increase turnover and
profit
Administer the Business
Support Grants scheme to
support businesses to invest,
subject to eligibility etc
criteria. 
Annual evaluation of
programmes / interventions:
• Number of grant
applications.
• Number of
businesses
supported.
• Number of jobs
safeguarded/created
2022 then
annual
evaluations
SLC Economic
Development team 
Support Scotland
Food & Drink’s
Regional Food
Tourism
Ambassador
Programme
Ensure that good links
are in place between
Scotland Food &
Drink, the current
South Lanarkshire
Food Tourism
Ambassador, and with
South Lanarkshire
Council 
Ensure regular
communication takes place. If
the scheme is expanded and
additional ambassadors are
required, help Scotland Food
& Drink to identify other new
potential ambassadors
Evaluation of Food Tourism
Ambassador Scheme by
Scotland Food & Drink  
Ongoing South Lanarkshire
Council (SLC)
Food and Drink
Sector Lead,
Economic
Development
Provide support
to tourism and
hospitality
businesses via
the Business
Gateway
Lanarkshire
service
Work with the current
contractor – Elevator,
to deliver support to
tourism and hospitality
businesses
Regular meetings are held
with SLC, North Lanarkshire
Council and the Business
Gateway Lanarkshire
contractor – Elevator
Annual evaluation of
activity:
• Number of
businesses to
receive business
advice.
• Number of training
events.
• Number of tourism-
specific initiatives
2022 then
annual
evaluations
Business Gateway
Lanarkshire / SLC
Economic
Development team 
94

Page 95

Business
We will: High Level Actions Steps we will take to
deliver this action
How will we know this
step is complete and
measure outcomes?
Timescales  Lead 
e.g., Lanarkshire
Tourism Month.
• Number of
tourism/hospitality
businesses
attending training
events.
Work with other
partners to
support tourism
and hospitality
businesses
Signpost to
businesses to other
sources of help and
advice.
Through our engagement
with organisations such as
the Scottish Tourism Alliance,
VisitScotland, Glasgow City
Region and the Scottish
Local Authorities Economic
Development (SLAED)
tourism sub-groups, we will
endeavour to be aware of
available support and
opportunities to the sector
and share this information
with the sector
Number of referrals made
to partner organisations
2022 then
annual
evaluations
SLC Economic
Development team 
95

Page 96

Business
We will: High Level Actions Steps we will take to
deliver this action
How will we know this
step is complete and
measure outcomes?
Timescales  Lead 
Drive product
development with
existing and new
pipeline
businesses
Help industry to
develop and diversify
their product to target,
in the short term,
those key markets first
to return post Covid-
19, and longer term,
targeted higher value
market segments  
Develop product readiness
by ensuring businesses are
travel trade ready,
understanding travel
distribution by key market,
available routes to market,
and then identifying and
engaging with intermediaries.
Delivered through a range of
business surgeries and
events as well as providing
platforms for business to
participate e.g., missions,
workshops, pre-event
training, VisitScotland Expo
TBC Ongoing VisitScotland 
Support business
through
successful
delivery of digital
skills and
development
advice 
Delivering digital
advice and support
specifically tailored for
the tourism industry.
Driven by keen
understanding the
visitor journey.
Helping businesses
upskill their digital
capabilities, taking
advantage of the
digital routes to
market
Achieved through a series of
1-2-1 digital reviews,
webinars and workshops
covering: digital
fundamentals, online
booking, digital technologies,
online travel agent
distribution, reputation
management, social media
and google analytics
Number of businesses
participating in reviews,
webinars, and workshops
Ongoing VisitScotland 
96

Page 97

Business
We will: High Level Actions Steps we will take to
deliver this action
How will we know this
step is complete and
measure outcomes?
Timescales  Lead 
Support tourism
businesses to
build business
resilience,
sustainability,
improve business
viability and
profitability.
Communicate South
Lanarkshire College’s
curriculum offer that
can support upskilling
and the development
of employees in the
Tourism sector
Work with our Marketing
Team to actively promote our
courses to the Tourism sector
in South Lanarkshire
On production of targeted
information on the College
website and
communications sent to
Tourism groups we have
networked with as above. 
AY 22/23 South Lanarkshire
College 
97

Page 98

Marketing
We will: High Level Actions Steps we will take to
deliver this action
How will we know this
step is complete and
measure outcomes?
Timescales  Lead 
Raise the profile
of the South
Lanarkshire
tourism offering 
Raise awareness via the
Visitlanarkshire.com
website and associated
social media channels 
Work with North Lanarkshire
Council (NLC) colleagues to
review the current website
content
Completion of website
review report.
Ongoing  SLC Tourism
Officer,
Economic
Development
team 
Redevelop website and liaise
with VisitScotland when
doing so to ensure alignment
with national VisitScotland
site
Launch of new refreshed
website
December
2022
SLC Tourism
Officer,
Economic
Development
team 
Ensure the site remains
relevant by maintaining and
adding relevant content onto
the site and associated
social media channels 
Visitor traffic stats will be
monitored
2022 then
annual
evaluations
SLC Tourism
Officer,
Economic
Development
team 
Promote the area’s
tourism offering via
VisitLanarkshire
campaigns and
marketing activity
Work with NLC colleagues to
develop and execute
marketing activity
All activity (where
measurable), will be
reviewed and evaluated
when completed
2022 then
annual
evaluations
SLC Tourism
Officer,
Economic
Development
team 
Ensure visitors
have information
on the
accessibility of
venues and
attractions 
Raise awareness of
accessible tourism
through linking listings
on VisitLanarkshire.com
with AccessAble
Keep the VisitLanarkshire
website up to date and
maintain ongoing
subscription with AccessAble
Continue to work with
AccessAble and ensure
website is kept up to date
Ongoing SLC Tourism
Officer 
98

Page 99

Marketing
Promote our town
centres 
Promote all town centre
offers through use and
promotion of the inside
out app. 
Delivery of the insideOut app
to provide a communication
tool for town centre
businesses, communities,
and visitors. The app
contains information on town
centre business, attractions,
events, and trails.
We will continue to work
with town centre
stakeholders to populate
and promote the app.
Complete App
development
in 2022.
Ongoing
marketing and
promotion.
SLC Town
Centre
Management
Team 
Ensure that South
Lanarkshire is
represented in
Glasgow City
Region (GCR)
tourism marketing
activity
Be an active member in
the GCR Tourism and
Destination Marketing
Portfolio, and GCR
Tourism Delivery Group. 
Collaborate with group
members and participate in
appropriate marketing
activity
Production of final action
plan progress report  Ongoing 
SLC Tourism
Officer,
Economic
Development
team 
Gather tourism
data to inform
decision making
and share with
tourism operators 
Work with key national
organisations such as
VisitScotland and the
Scottish Tourism
Alliance (STA) to access
market data and visitor
intelligence  
Hold regular meetings with
VisitScotland and monitor
Scottish Tourism
Observatory developments. 
Retain membership with the
STA and encourage South
Lanarkshire organisations to
participate in data gathering
activity
Number of South
Lanarkshire organisations
participating in data
gathering exercises
Ongoing SLC Tourism
Officer,
Economic
Development
team 
Commission research to
inform decision making
Commission data from
existing models such as
Scottish Tourism Economic
Activity Monitor (STEAM)
reports, and the Moffat
Centre Visitor Barometer
reports. 
We will keep a record of
the number of data
sources being used and
ensure that South
Lanarkshire trends are
monitored, and
appropriate action taken
where required  
Annual
reviews
SLC Tourism
Officer,
Economic
Development
team 
99

Page 100

Marketing
Consider commissioning
data where gaps exist
Promote use of
local food and
drink produce
(promotion and
events) across
business sectors
including tourism
Support promotion and
events which celebrate
the use of local food and
drink in tourism
Work with national
organisations such as
Scotland Food & Drink, and
local groups like Lanarkshire
Larder to promote local food
and drink produce 
Number of events
organised/supported,
number of initiatives
supported, number of
participating businesses,
number of visitors
attending
Ongoing SLC Food and
Drink Sector
Lead,
Economic
Development
team 
Work with
VisitScotland to
profile our visitors
and understand
their needs. 
Create market
prioritisation framework 
Use VS research and
insights to identify key target
markets and segments, their
location, and interests
Completed framework will
align with VS insights
Ongoing SLC Tourism
Officer in
partnership
with
VisitScotland 
Align South Lanarkshire
product offering with the key
markets and segments
identified
Visitor needs and products
will be matched
Ongoing SLC Tourism
Officer in
partnership
with
VisitScotland 
Work with
VisitScotland to
enhance South
Lanarkshire
content in relevant
marketing activity 
South Lanarkshire
products are included in
relevant VS marketing
material 
Explore creation of a
High level – digital visitor
Regular updates with VS
ensuring they are kept up to
date with regional product
development 
Examples of South
Lanarkshire products
included in relevant VS
marketing activity and
reflected on
visitscotland.com 
Procure a digital
Ongoing-
fortnightly
series of
meetings with
VisitScotland
SLC Tourism
Officer,
Economic
Development
team 
100

Page 101

Marketing
guide  that highlights
offering 
development consultant 
to deliver this 
Partner with VS to deliver
paid marketing activity where
relevant using their channels
to extend reach
Paid marketing activity
completed
Ongoing SLC Tourism
Officer in
partnership
with
VisitScotland 
Prepare new Marketing Plan
2022/23
New Marketing Plan
launched
2022 SLLC 
Raise the tourism
profile of SLLC
assets 
Existing South
Lanarkshire Leisure and
Culture Marketing Plan
reviewed and refreshed.
Raise the profile of our
venues and move away
from the perception of
provincial venues,
instead focussing on the
high-profile artists and
companies that perform
Marketing Plan 2022/23
reviewed
Marketing Plan 2022/23
progress report
completed, and progress
reviewed
Nov 2022 SLLC 
Prepare new Marketing Plan
2023/2024
New Marketing Plan
launched
Apr 2023 SLLC 
Instigate a marketing
campaign aimed at the
profile of the venues as
opposed to specific shows,
focussing on our online Box
Office
www.sllcboxoffice.co.uk
Number of marketing
campaign delivered
Dec 2022 then
annual
reviews
SLLC 
101

Page 102

Responsible tourism
We will: High Level Actions Steps we will take to deliver
this action
How will we know this
step is complete and
measure outcomes?
Timescales  Lead 
Develop planning
policies to ensure
the delivery of the
Tourism Strategy
is sustainable 
Develop planning
policy requiring the
provision of
appropriate
infrastructure and
visitor management
in new
developments and
the protection of the
natural and built
environment
Prepare South Lanarkshire Local
Development Plan 3
Adoption of SLLDP3 The
finalised
SLLDP3 will
be produced
in 2027/28
but
preparatory
work will
begin long
before this.  
SLC Planning 
Reduce our
carbon footprint
by utilising digital
communication
channels when
appropriate to do
so  
We will use digital
marketing methods
when appropriate. A
blend of online and
offline meetings will
be used to reduce
the need for
participants to travel
to meetings
The carbon impact of activity will
be considered when we are
planning marketing and other
communication activity. When we
are planning in-person events we
will promote public/active
transport options where these are
available
We will monitor the
amount of print we are
generating and use
surveys when we are
holding in-person
events. 
Ongoing SLC Tourism
Officer, Economic
Development team
Encourage
visitors to act
responsibly when
visiting South
Lanarkshire 
Embed responsible
tourism messaging
in the new
VisitLanarkshire.com
website 
Ensure the new website contains
information on:
• Responsible tourism
• Accessibility
• Links to Public transport
options
• Active Travel
Launch of refreshed
website 
22/23
SLC Tourism
Officer, Economic
Development team
102

Page 103

Responsible tourism
• ‘Green tourism’
Develop Tourism
courses to include
input on the
sustainable visitor
economy and how
to maximise
positive and
minimise negative
impacts
As above where we
consult with tourism
sector partners to
inform the
curriculum to meet
needs 
Contact Tourism sector
employers in South Lanarkshire
and with relevant South
Lanarkshire Tourism networking
groups to encourage discussion
about embedding sustainable
tourism into the curriculum to
meet sector and employee need
Attendance and
feedback from
successful networking
events.
AY 22/23
and 23/24
South Lanarkshire
College
103

Page 104

Partnership working
We will: High level actions Steps we will take to deliver
this action
How will we know this
step is complete and
measure outcomes?
Timescales Lead
Consult with the
Lanarkshire
tourism sector and
find out their
views on whether
a tourism
membership
organisation is
desired for the
region.  
Ongoing
discussions with
the industry in both
group settings and
with individual
businesses to
establish the desire
for the formation of
a collaborative
group. 
Virtual symposium held and
survey issued in Feb 2022. 
Further consultation is taking
place in order to reach a
consensus on the establishment
of a sector collaborative body. 
Sector engagement will
be completed with a
majority view
established on the
desire for a
collaborative tourism
group. 
March 2023 SLC Tourism
Officer,
Economic
Development
team         
Engage in joint
working with
tourism
colleagues across
the 32 local
authorities in
Scotland
Share intelligence
and explore joint
opportunities with
tourism officers in
other local authority
areas
Be an active members of the
Scottish Local Authority Economic
Development (SLAED) Tourism
Sub-group
Meeting minutes,
participation in joint
working activity
Meetings
take place
quarterly 
104

Page 105

Partnership working
Support food and
drink networks in
South Lanarkshire
Work with
organisations such
as Scotland Food &
Drink to provide
help and advice to
groups like
Lanarkshire Larder
Raise awareness of promotional
and funding opportunities from
the council and other
organisations
Number of food and
drink groups supported;
number of
members/activities
undertaken; number of
attendees at events 
Quarterly
reports
SLC – Food and
Drink Sector
Lead, Economic
Development
team 
105

Page 106

Appendix B strategic context –relevant
policies and plans
This strategy is influenced by the following strategic plans:
Tourism Lanarkshire 2020
This strategy picks up some themes from the Tourism Lanarkshire 2020, a Lanarkshire wide
strategy which covered the period 2016-20.
Scotland Outlook 2030 and The Scottish Tourism Emergency Response Group
(STERG) Recovery Plans
Scotland Outlook 2030 represents the longer-term tourism strategy for Scotland up to 2030.
The STERG Recovery Plans were created in 2020-21 to deal with short to medium-term
actions required to assist the tourism sector to recover from the effects of the COVID
pandemic. 
Scotland’s National Strategy for Economic Transformation (NSET)
The vision of the national strategy is to create a wellbeing economy: a society that is thriving
across economic, social and environmental dimensions, and that delivers prosperity for all
Scotland's people and places. It mentions that it is vital that every region in Scotland benefits
from, and contributes to, a more productive and innovative economy, therefore highlighting
the importance of Regional Economic Partnerships.
Scottish Agritourism A Strategy for Sustainable Growth
This strategy highlights the growing trend that is agritourism. With South Lanarkshire having
a vast rural landscape, there are already businesses in the area diversifying to offer
agritourism experiences and this strategy notes globally agritourism has a sector worth over
£1 billion per annum. It is therefore essential that agritourism is clearly defined as a unique,
authentic experience for visitors. We particularly look to encourage tourism in the rural areas
of South Lanarkshire and therefore the Scottish Agritourism Strategy was a positive
influence when developing the tourism strategy. 
Promote Economic Strategy for South Lanarkshire (2013-23) and South Lanarkshire
COVID-19 Recovery Plan
This strategy picks up key development themes from the Promote Economic Strategy which
are business development and growth, physical infrastructure and place, and Skills - learning
and employability. This tourism strategy aims to contribute towards progressing the following
indicators and targets from that plan: 
• Increase the number of businesses per 10,000. 
• Increase Gross Value Added (GVA).
• Maintain 3-year business survival rate.
• Increase the number of business start-ups.
• Increase the number of school leavers into positive and sustained destinations. 
• Reduce the proportion of South Lanarkshire residents below the Living Wage.
• Increase the employment rate.
• Reduce the number of working age residents who are employment deprived.
• Reduce the levels of income deprivation.
The new tourism strategy and associated action plan also aims to make a positive
contribution to ongoing COVID-19 recovery efforts.
106

Page 107

South Lanarkshire Community Wealth Building Strategy (CWB)
CWB is an alternative approach to traditional economic development, and seeks to develop
resilient, inclusive local economies, with more local employment and a larger, more diverse
business base. Our diverse tourism sector is ideally placed to make a positive contribution to
South Lanarkshire’s CWB aspirations and enhance our urban and rural communities.
South Lanarkshire Community Plan (2017-27)
The vision for South Lanarkshire Community Plan is: "to improve the quality of life for all in
South Lanarkshire by ensuring equal access to opportunities and to services that meet
people's needs". The overarching objective is to tackle deprivation, poverty, and inequality. 
Successful implementation of this tourism strategy and action plan will make a positive
contribution to several Community Planning Partnership (CPP) goals including encouraging
growth of new businesses; improving the growth and survival of existing businesses in ways
that generate better pay, job security and opportunities to progress; and help new
businesses to develop through creating the right environment and signposting help and
financial support.
Tourism is also ideally placed to make a positive contribution towards a family focused
financial inclusive strategy with many jobs within tourism and hospitality industry sectors not
being typical ‘9-5 jobs’ with a wide range of full-time, part-time and seasonal jobs being
provided. The wide variety of shift patterns can suit a variety of people and their own unique
circumstances for example some part-time roles may be more suitable for single parents.
Tourism can also help tackle health inequalities. Natural tourism assets – walking and
cycling trails for example, can be freely accessed by locals as well as visitors, and their use
can provide a wide range of physical and mental health benefits. Cultural assets such as
museums can promote a sense of belonging and can help combat social isolation.
Sensitive investment in tourism assets can help improve the natural environment as can
responsible tourism campaigns to encourage visitors to look after the environment when
they are visiting.
Connect (2017-22)
Connect is the council Plan for South Lanarkshire. It sets out the council’s vision, values,
and ambitions and what we hope to achieve to improve outcomes for local people over the
next five years.
At the very heart of this is our vision, which is to improve everyone's quality of life through
the services delivered by our five Resources (Education, Social Work, Community and
Enterprise, Housing and Technical, and Finance and Corporate) and in the work we do with
communities and partners, including the South Lanarkshire Community Planning Partnership
and the Health and Social Care Partnership.
107

Page 108

Sustainable Development and Climate Change
The development of A South Lanarkshire Sustainable Development and Climate Change
Strategy 2022-2027 is ongoing. The council has also signed up to the Glasgow Food and
Climate Declaration and Edinburgh Biodiversity Declaration. A key theme of this strategy is
to identify sustainable development opportunities which will help progress moving towards a
net zero economy. 
South Lanarkshire Good Food Strategy 2020-2025
One of the actions of the South Lanarkshire Good Food Strategy is to “showcase and
promote the local food sector to South Lanarkshire residents and visitors” with food and
drink being an “integral part of the visitor experience”. Key themes include quality and
provenance.
Spatial Planning 
The South Lanarkshire Local Development Plan 2 was adopted by the council April 2021.
Policy in relation to the visitor economy and tourism supports the provision of new high
quality visitor attractions and facilities together with infrastructure and accommodation as
well as the safeguarding of existing features. Proposals are expected to be sustainable,
located in appropriate locations while ensuring developments include low and zero carbon
energy generating technologies. 
At a national planning policy level, the focus is on enabling sustainable development that
helps strengthen the tourism sector. There is a recognition that tourism will need to adapt to
climate change and its impact on travel as well as economic challenges. Impact on the
environment and communities will require visitor management and the protection of key
assets while investment in appropriate infrastructure is critical. The policy direction will be set
out in National Planning Framework 4 which is expected to be approved by the Scottish
Parliament in mid-2022; this in turn will inform the preparation of Local Development Plan 3. 
If you need this information in another language or format, please contact us to discuss how
we can best meet your needs.  
Phone: 0303 123 1015  
Email: equalities@southlanarkshire.gov.uk 
www.southlanarkshire.gov.uk 
108

Page 109

Appendix 2 List of bodies consulted/responded to online consultation process. 
The following business engagement and other work has been undertaken to inform the
tourism cooperative and strategy work. 
 The additional funding was announced in February 2021. South Lanarkshire tourism
businesses were issued with a survey in May 2021 to gather information and their
views on current challenges, opportunities and their priorities for the sector moving
forward. 
 Informal discussions with individual businesses have informed our strategic
approach. Economic Development officers are in frequent dialogue with businesses
regarding a wide variety of topics – planning applications, grant applications, COVID
support etc., and this has provided officers with an opportunity to gather from
businesses their views on opportunities and challenges for promoting tourism in
South Lanarkshire and their views regarding whether they would like to see a new
tourism membership body set up in South Lanarkshire.   
 An example of this approach includes engagement with the Clydesdale Tourism
Group. Officers have attended meetings to advise on support for the sector and
where local businesses and stakeholders have expressed their views and have
provided feedback. Officers have strived to reflect the needs and aspirations of the
group within the draft tourism strategy. 
 The council’s Economic Development team often receive feedback and comments
from residents and visitors about a wide variety of tourism issues. This feedback has
informed and been reflected in the draft tourism strategy.   
 Discussions with the former Chair of the Lanarkshire Area Tourism Partnership and
Lanarkshire Tourism Association (LTA) and former members of both organisations
have taken place to learn lessons from the past.   
 The Scottish Tourism Emergency Response Group (STERG) was created in March
2020 to respond to the COVID-19 crisis and their work has included wide ranging
industry surveys and engagement across the Scottish tourism sector. STERG data
and intelligence has been considered to inform a strategic approach. 
 Officers have had discussions with a wide variety of external organisations to inform
work regarding the potential development of a tourism membership organisation in
South Lanarkshire. Individual discussions have taken place with South of Scotland
Destination Alliance, Ayrshire and Arran Destination Alliance, Argyll and the Isles
Tourism Cooperative, Visit Inverness, Loch Ness Improvement District, Breadablane
Tourism Cooperative, Cooperative Scotland, the Scottish Tourism Alliance, and
Scottish Enterprise. 
• An online consultation was held in February 2022 with 32 responses from a variety
of organisations including VisitScotland, Quothquan and Thankerton Community
Council, Royal Burgh of Lanark Community Council, Lanarkshire Larder, Campaign
for Real Aires, Carluke Community Council, Lanarkshire Police Historical Society,
Lanarkshire Heritage Forum, Leadhills Heritage Trust, Hollandbush Golf Club. 
7
109

Page 110

110

Page 111

Report
Agenda Item 
Report to: Community and Enterprise Resources Committee
Date of Meeting: 13 December 2022
Report by: Executive Director (Community and Enterprise
Resources)   
Subject:
Scottish Government 5 Year Play Investment
Programme 
1. Purpose of Report
1.1. The purpose of the report is to: - 
 provide an update on the work undertaken to date on the Scottish Government’s
proposed Play Area Investment Programme
 propose a strategic, place-based approach to allocating funding from the
programme 
2. Recommendation(s)
2.1. The Committee is asked to approve the following recommendation(s): - 
(1) that the content of the report be noted; and 
(2) that the proposed place-based, local approach is approved rather than a blanket
spend approach. 
3. Background
3.1. The Scottish Government has launched a £60 million fund to renew play parks in
Scotland, in order that children have access to high-quality outdoor play in their own
communities. £10 million of funding was distributed across councils in 2021/2022 and
2022/2023, with the Council’s share totalling £594,000. The Scottish Government has
now confirmed the full allocation which would see South Lanarkshire receiving a total
of £3.58 million up to 2025/2026.  
3.2. The original intention of the Government was to renew and transform all play areas in
Scotland. However, it was clear from the proposed funding package that this would
not be achievable. Due to the potential shortfall in funding, the Scottish Government
agreed that councils could identify their own investment priorities. Previously,
Committee approved the appointment of two temporary Landscape Architects for 2
years utilising the Scottish Government funding received to date. However, only one
post was able to be appointed, and the post holder has been able to independently
assess what was required in each play area to bring it up to a basic standard. This
employee will also be responsible for any consultation going forward as well as
associated designs, procurement and contract management relating specifically to
Scottish Government spend. 
8
111

Page 112

3.3. The Council has now completed an initial exercise to identify potential costs to bring
all 233 play areas up to an appropriate standard rather than full renewal. This has
identified a funding shortfall of approximately £620,000 to bring all play areas up to an
appropriate standard. 
3.4. Prior to the assessment process starting, the Council also carried out a high-level
survey on play in general with 6,395 responses received. The consultation response
will be utilised as the Council begins implementation of the programme, with the
comments received for each site considered in more detail and further consultation
undertaken with local children, families, and ward members as proposals are
developed. 
3.5. Separate to this, there is a forthcoming review of planning regulations and the Planning
Service is leading on the development of an Open Space Strategy which incorporates
new play sufficiency requirements, albeit the exact criteria for assessing play provision
and surrounding open space has not yet been confirmed.  It is hoped that by ensuring
that all play areas meet a basic standard, this would help contribute to meeting future
play sufficiency requirements. To support the implementation of the Programme, the
service is also investigating an IT solution to capture and maintain up to date play
inspection and investment information. 
4.  Investment programme
4.1.  The Scottish Government has now confirmed the profile of spend that South
Lanarkshire Council will receive for the investment programme, including funding
already received. The Council will also continue to explore opportunities for external
funding or developers’ contributions that could be utilised to supplement the
investment programme and maximise the benefit of individual projects. 
Year Allocation (£m)
2022/23 0.594
2023/24 0.597
2024/25 0.896
2025/26 1.493
Total 3.580 
4.2. As highlighted in section 3.3, initial inspection of all play areas has shown a funding
shortfall of £620,000 to bring all sites up to an appropriate standard. A simple allocation
of the funding available across all current play areas, regardless of any other
considerations, would see minimal impact in many play areas. For some, funding
would only go some way to addressing accessibility issues, environmental conditions
or applying modern safety standards to historic locations i.e. new fencing for play
areas near roads. 
4.3. The shortfall in funding provides the opportunity to consider a more strategic place-
based approach to allocating specific investment that could see targeted investment
in priority play areas. The initial assessment of all play areas against appropriate
standards will be used as the basis of funding in each identified locality. This approach
would be developed in collaboration with the local community and local ward
members, building on the consultation already undertaken and delivering local
investment based on local priorities.  
112

Page 113

4.4. Given the multi-year profile of the funding, the following programme is proposed with
focus on specific localities each year. Within the programme there will be flexibility to
bring forward or push back projects as funding and staffing resource allows. 
Year Areas
Number
of sites
2023/24 Larkhall, Rutherglen, Cambuslang 31
2024/25
Hamilton, Bothwell, Uddingston,
Blantyre, Strathaven and surrounds 36
2025/26 East Kilbride 65
2026/27 Clydesdale 101
Total 233 
4.5. Taking the programme forward will require a mix of resource usage. The Resource
has recruited one temporary Landscape Architect dedicated to the programme and
the service has 3 further permanent Landscape Architects who work on a variety of
different projects at any given time. As the programme develops, work will be
prioritised accordingly internally and there will also be a requirement to commission
specific work packages or projects as determined by resource capacity. Further
consideration will also be given to additional managerial support as the programme
develops into a more complex programme of individual projects. 
4.6. Current market conditions will also have an impact on programme implementation.
With all 32 councils accessing a small number of specialist approved contractors
across Scotland, lead in times to commence projects have already increased
significantly and some contractors are not bidding for tenders in outlying areas due to
the amount of local work available.    
5. Employee Implications
5.1. The temporary Landscape Architect post has been recruited on a 2-year basis and is
due to terminate in February 2024. It is expected the programme will continue for two
years beyond this date and so will be reviewed as future resources are considered. 
6. Financial Implications
6.1. South Lanarkshire Council has been allocated £3.58m for the investment programme
with £0.594m received to date and the remainder due to be received over the next 3
years as shown in section 4.1. Applying an appropriate standard investment to the
Council’s 233 play areas has identified a funding shortfall for this purpose of £0.6m.
The proposed place-based approach of identifying priority work within a locality will
allow the funding to be applied to local priorities. 
6.2. The current market for contractors and equipment is exceptionally volatile and the
initial assessment was based on best estimates at that time. The actual cost of projects
will not be known until the tender process is underway. Additionally, RPI over the 5-
year period will have an impact on costs over this time and, therefore, reduce the
amount of work that will be able to be undertaken. This will be continually reviewed as
the investment programme is developed. 
6.3. It should also be noted that the investment programme is one off funding and does not
account for any increased maintenance costs over the long term of new and additional
play equipment. In addition, the Council may not be able to meet ongoing public
expectations to maintain these standards and this is something that COSLA has raised
with the Scottish Government on behalf of all councils.
113

Page 114

7. Climate Change, Sustainability and Environmental Implications
7.1.  All potential play area improvements will create a more inviting and pleasant
environment for children and families to gather and, where possible, we will utilise
natural site characteristics more effectively to enhance the play experience and will
increase tree canopy cover and add other vegetation to improve climate change
resilience. 
8. Other Implications 
8.1. There are no implications for risk currently identified in terms of the information
contained within this report. 
9. Equality Impact Assessment
9.1. The report does not introduce a new policy, function or strategy or recommend a change to 
an existing policy, function or strategy and, therefore, no impact assessment is required. 
David Booth
Executive Director (Community and Enterprise Resources) 
21 November 2022 
Links to Council Values/Priorities/Outcomes 
Values
 Focused on people and their needs
 Working with and respecting others 
Priorities
 We will work to put people first and reduce inequality 
Outomes
 Good quality, suitable and sustainable places to live
 People live the healthiest lives possible 
Previous References
 None 
List of Background Papers
 None 
Contact for Further Information
If you would like to inspect the background papers or want further information, please contact:
Lynn Carr, Amenity Services Manager Ext: 815 7755 (Tel: 01698 717755) 
E-mail: lynn.carr@southlanarkshire.gov.uk
114

Page 115

Report
Agenda Item 
Report to: Community and Enterprise Resources Committee
Date of Meeting: 13 December 2022
Report by: Executive Director (Community and Enterprise
Resources)  
Subject: South Lanarkshire Gift Card – Update 
1. Purpose of Report
1.1. The purpose of the report is to:- 
 update members on the performance of the South Lanarkshire Gift card over year
one 
2. Recommendation
2.1. The Committee is asked to approve the following recommendation(s):
[
(1) the evaluation of the South Lanarkshire Gift Card Scheme, be noted; and 
(2) that the Council does not progress with the gift card programme. 
3. Background 
3.1.  Along with all other local authorities in Scotland, South Lanarkshire Council was asked
by the Scottish Government, through Scotland’s Town Partnership, to back a Scotland
Loves Local Gift Card scheme. The scheme was designed to encourage local
shopping, drive footfall to local businesses and keep spend in the local area for longer. 
3.2. The initiative was fully funded and supported by the Scottish Government for the first
year, September 2021 to August 2022. Each local authority signed up to the scheme
via a concordat and was provided with 5000 gift cards for its local area for the first
year. The scheme was fully paid and managed for the first year. Thereafter, the local
authority has the option to agree to continue the scheme for a further year, subject to
covering all running costs. 
3.3.  Approval to proceed with a 1-year trial of the proposal was given by this Committee at
its meeting of 7 December 2021. South Lanarkshire Council signed up to the
concordat, through which the council gave its support to the scheme for an initial one-
year period. Through this, the Council agreed to:- 
 promote the Scotland Loves Local Gift Card scheme amongst outlets, merchants
and attractions in the local authority area
 a local launch and promotion of the Gift Card to businesses in South Lanarkshire
 provide content for a landing page specific to South Lanarkshire 
3.4. The gift cards utilise the existing MasterCard network and can be accepted by small
independent businesses and national retailers who use this network. There was no
cost to individual businesses and full operational support and merchant care was
delivered by Miconex, who provide all purchase and fulfilment functions. Scotland’s
9
115

Page 116

Town Partnership (STP), on behalf of Scottish Government, had a contract in place
with Miconex and covered the full costs of the first year including licence fee,
administration, support and management costs. Data was also collected and used to
track spend on the cards and provide information to determine what the benefit is to
businesses from such a scheme. 
3.5. The only cost to the Council for the initial year pilot period was officer time. 
4. Card Performance in South Lanarkshire
4.1. The South Lanarkshire Gift Card was promoted through the Council’s networks as well
as through partner organisations such as Hamilton BID. Support was also given by
Miconex by approaching individual businesses to encourage sign up. 
4.2.  As of 30 September 2022, 207 businesses had signed up to the South Lanarkshire
programme (this includes nationals who have signed up across Scotland). The card
had generated sales in South Lanarkshire of £1,235. 
4.3. This is a disappointing level of uptake and does not represent value for money or an
effective use of the resources.   
4.4. Continuation of the gift card scheme comes with an annual cost of £11,700. This
breaks down into a £600 per month administration fee as well as printing costs of
£4,500 for 5,000 cards. Should a local authority want more cards, there will be an
additional fee. 
4.5. Given the low sales in South Lanarkshire and, therefore, limited economic benefit to
the area, it is not deemed best value to, continue with the card, particularly as no
budget currently exists to meet the schemes costs. 
5. Employee Implications
5.1. There are no employee implications arising from the content of this report 
6. Financial Implications 
6.1. Continuation of the card would require an annual budget of £11,700. This funding is
not available from existing budgets. The uptake and levels of spend associated with
the trial clearly shows that the economic benefits do not provide a suitable return on
investment. 
7.  Climate Change, Sustainability and Environmental Implications 
7.1.  There are no climate change or environmental implications as a result of this report. 
8. Other Implications
8.1. The card is being widely promoted by Scotland’s Towns Partnership discontinuation
may result in complaint from some businesses. 
9. Equality impact assessment and Consultation Arrangements
9.1. This report does not introduce a new policy, function or strategy or recommend a
change to an existing policy, function or strategy and, therefore, no Impact
Assessment is required. 
9.2 There is no requirement to undertake consultation in terms of the information
contained in this report. 
116

Page 117

David Booth
Executive Director (Community and Enterprise Resources) 
21 November 2022 
Link(s) to Council Values/Priorities/Outcomes
 Accountable, Effective, Efficient and Transparent 
Previous References 
 Community and Enterprise Committee 7 December 2021 - South Lanarkshire Gift
Card 
List of Papers Attached
 None 
Contact for Further Information
Name  Victoria Eccles
Designation Project Development Officer
E-mail  victoria.eccles@southlanarkshire.gov.uk 
117

Page 118

118

Page 119

Report
Agenda Item 
Report to: Community and Enterprise Resources Committee
Date of Meeting: 13 December 2022
Report by: Executive Director (Community and Enterprise
Resources)  
Subject: Roads Asset Management Plan 2022 - Update 
1. Purpose of Report
1.1. The purpose of the report is to: -
[purpose]
 provide an update on the Roads Asset Management Plan (RAMP) and outline the
condition of roads and related infrastructure assets.
[1purpose]
2. Recommendation(s)
2.1. The Committee is asked to approve the following recommendation(s):-
[recs]
(1) that the contents of this report be noted.
[1r
3. Background
3.1. The Executive Committee, at its meeting held on 22 September 2010, approved the
implementation of an extended model for Corporate Asset Management from 2011.
This included developing Asset Plans across several service areas, in line with CiPFA
guidance, and summarised, under an overarching Corporate Asset Management Plan,
which demonstrates how each area supports corporate objectives. The Service Areas
are Property, Housing, ICT, Roads Infrastructure and Fleet. 
3.2. The Corporate Asset Management Plan (AMP) is reviewed annually and, being the
Council’s single largest asset group, the Roads Asset Management Plan (RAMP) is a
key element of the corporate document. 
3.3. The development of RAMPs across Scotland provides an excellent example of 
collaborative working across all 32 councils.  A 4-year project, in which all councils
participated, was completed in 2016. The good progress achieved is now being
developed further via a successor project in which all Scottish councils are again
participating. 
3.4. The main purpose of developing the RAMP is to: - 
 Ensure we have a sound knowledge of the extent and condition of our main asset
groups
 Understand where any knowledge gaps exist and consider how these might be
addressed
 Understand the level of current investment on each asset group and the
associated condition trend  
10
119

Page 120

3.5. The roads asset consists of the following main groups.  
Asset Type Asset Description and Components 
Carriageway The part of the road used by vehicles. This asset group includes
drainage systems, lay-bys, bus lanes, traffic calming and verges. 
Footways,
Footpaths
and
Cycleways
Footways – used by pedestrians adjacent to the carriageway.
Footpaths – used by pedestrians remote from the carriageway.
Cycleways – used by cyclists and in some cases pedestrians.
Pedestrianised Areas – generally located in town centres. 
Structures Primarily bridges and culverts with a span greater than 0.9 metres
and retaining walls with minimum retained height of 1.35 metres. 
Street
Lighting
Includes lamps, columns, ducts, cabling, control pillars, illuminated
road signs and bollards and festive lighting 
Traffic
Management
Systems
Signalised junctions and pedestrian crossings, detection
equipment, ducts, and cabling 
Street
Furniture
Vehicle restraint systems (safety fence) 
4. Carriageway Asset 
4.1.  The Council is responsible for a total of 2,295 kilometres (1,426 miles) of carriageway.
The Council’s carriageway network is divided into four classifications A, B, C and
Unclassified. 
4.2. Inventory records are accurate for the lengths of road, however, the widths of the road
are estimated based on classification of the road. Over time, these widths will be
collected and added into our network management system and will aid with
quantification and refinement of the valuation of the carriageway asset. 
4.3. The carriageway asset Gross Replacement Cost of the recorded asset, as derived
utilising the Asset Valuation tool developed by Society of Chief Officers of
Transportation in Scotland (SCOTS), is £2.226 billion. 
4.4. Safety inspections are carried out in accordance with the Guidance Document for
Road Safety Inspections and Defect Categorisations. This manual takes cognisance
of the guidance contained within Well Managed Highway Infrastructure Code of
Practice. These safety inspections are carried out on a monthly, three monthly or
annual basis depending on the hierarchy of the carriageway. 
4.5. In addition to these inspections, regulatory inspections to deliver our obligations under
the New Roads and Street Works Act 1991 (NRSWA) and the Transport Scotland Act
2005 (2019 legislation currently being implemented) are also carried out. 
4.6. Annually, the Scottish Roads Maintenance Condition Survey (SRMCS) is undertaken
on our road network by SCOTS nominated contractor WDM Ltd. This survey tackles
100% of our A class carriageways in one direction, with the other direction being
surveyed the following year. 50% of our B and C class roads are surveyed with the
whole of the B and C class network being surveyed over a four-year period. Only 10%
of our unclassified road network is completed each year. This survey produces our
120

Page 121

Road Condition Index (RCI) based on the percentages above and applied to the whole
of the network. The survey identifies for each 10-metre section of road whether it falls
into the red category (requires maintenance) amber (should be considered for
maintenance) or green (serviceable). The RCI is published each year as a national
performance indicator. 
4.7. In 2017, SCOTS requested that the backlog for carriageway maintenance across
Scotland was recalculated by WDM Ltd, based on the latest SRMCS survey data at
the time. The backlog calculation for our road network was £90.420m in 2018. This is
the sum of money required to be invested in a single year to bring our road network
back to a serviceable standard.  This backlog figure has reduced from £137m in 2013,
and this is to be welcomed.  The backlog figure is due to be updated in 2023. 
4.8. The condition of our carriageways has improved as outlined below and, although there
was a slight regression over the 2019-2021 period, a further improvement was
recorded for the latest survey going below 30% for the first time. The RCI is the
combined value of the red and amber categories referenced at 4.6 and, overall, a lower
figure is better.   
4.9. Full tables of the Road Condition Index for A, B, C and Unclassified roads is shown in
Appendix A 
4.10. Our position in Scotland in terms of RCI ranking has improved as shown below from
19th reported over the period 2012-14 to 10th over the period 2020-22, noting a year
on year drop from 8th over the 2019-21 period.  Once again, the lower figure indicates
the better performance. 
121

Page 122

4.11. An independent assessment was undertaken by WDM Ltd to calculate the Steady 
State cost for South Lanarkshire’s network in 2018. The steady state is the amount of
investment required to maintain the road network in its current condition. Based on the
network condition in 2018, the steady state figure, which is based upon the
needs/condition of the carriageway network, is £12.500m. 
4.12. It should be recognised that 4 years on, and given significant and observed increases
in construction costs, that the equivalent steady state figure is likely to have increased,
although any increase may be offset slightly by an improving network across some
category of roads. This figure, both in terms of needs and expected cost, was
scheduled to be updated this financial year, but this is now expected during 2023-
2024. 
4.13. It should be borne in mind that the steady state figure is an estimate, rather than an
actual figure and it is important to note that the need to improve the condition of the
road network is assessed on an individual basis to support and justify expenditure. It
must also be noted that the current steady state figure does not take account of the
significant construction inflation that the industry is presently encountering.  In simple
terms, projects are costing much more than before, and the equivalent scale of works
are not presently possible with the same level of investment. 
4.14. During this financial year 2022-2023, approximately £9.765m is being directed towards
carriageway improvements.  
5. Footway Asset
5.1.  The Council is responsible for a total of 2,425 kilometres (1,506 miles) of footway. It
should be noted that this figure represents adopted footways/footpaths only and there
are other footpaths that are maintained by other parts of the Council or third parties.
Most of the adopted footway network is contained within the urban area. 
5.2. The length of footway network is an estimated length based on there being two
footways on each length of carriageway within the urban area. All the footways have
been estimated as having a 2-metre width. The footway asset Gross Replacement
Cost of the recorded asset is estimated at £612.7m.  
19
16 17 18 19 19
13 14
13
10
9
7 8
10
0
4
8
12
16
20
24
28
32
South Lanarkshire Network (out of 32 RA's)
Network
122

Page 123

5.3. Inspection arrangements and maintenance categories are similar to those for
carriageways in terms of the nature of inspections, but the frequencies can vary
depending on the hierarchy. 
5.4. There is no national condition survey for footways similar to that which is undertaken
for carriageways.  Instead, priorities for resurfacing are established via the local
knowledge of our officers considering the condition of a footway and its level of use. 
5.5. A sample survey of 59.2% of our estimated footway length was undertaken in calendar
years 2014, 2015, 2016 and 2017 which indicated that 16.2% of our footways should
be considered for maintenance purposes.  This figure is likely to have increased since
the sample survey. 
5.6. The estimated steady state figure for footway maintenance is £0.800m and we are
currently investing above this level.   
5.7. Following the participatory budgeting investment in roads and footpaths completed in
2021/2022, a second phase of investment was agreed that will focus on the
improvement of pavements, making our towns and villages safer for pedestrians,
supporting healthy lifestyles through physical activity and improving the look and feel
of our environment 
5.8. In addition to £1.000m funding which has been allocated from our roads investment
programme for prioritised footway improvements through the participatory budgeting
process, a further £2.500m has been identified to support footway and footpath
improvements which are part of the adopted footway network.  This investment of
£3.500m for 2022/2023 will continue the Council’s commitment to prioritising
investment in roads infrastructure by directing additional funds to help improve the
condition of our footways and footpaths.  Some of £3.500m will carry forward in
2023/2024. 
6. Lighting Asset
6.1. The Council has 60,923 lighting columns, 66,017 luminaires, 2,260 Control Pillars and
an estimated 1,976 kilometres (1228 miles) of cabling. Inventory records for lighting
columns, luminaires and control pillars are accurate, however, inventory of the cabling
network and knowledge of its condition is limited as most of it is underground. 
6.2. The percentage of lighting columns exceeding their design life is 35.7%, giving the
Council the sixth oldest lighting column stock in Scotland.  The cost to replace all these
columns at current rates would be £37.26 million.  The cost to maintain the lighting
asset in its current condition (steady state) is £1.00million.  This should be considered
relative to existing capital and revenue funding totalling £0.640m. 
6.3. The trend in columns beyond their design life continues to improve from 48% in 2015
to 35.7% at present. This progress is primarily a consequence of the column renewal
programme which was undertaken in parallel with the LED installation programme,
commencing in 2015 and being completed over 3 years.  This programme saw some
60,000 lighting units converted to energy saving LEDs and some 7,250 of our oldest
lighting columns replaced. 
7. Structures Asset
7.1. The Council is responsible for a total of 778 structures which includes road bridges,
footbridges, culverts, and subways together with a currently unquantified number of
road related retaining walls.
123

Page 124

7.2. Good records are held for most of these assets, however, there are currently limited
records held by the Council in respect of road related retaining walls. 
7.3. The current Gross Replacement Cost of the Structures asset is estimated at £507.9m. 
This figure does not include the replacement cost of any road related retaining walls. 
7.4. Bridge inspections are carried out in accordance with the guidance and
recommendations of the “Well Managed Highway Infrastructure: A Code of Practice”
published by the UK Roads Liaison Group.  This recently published Code encourages
the use of a risk-based approach toward identifying bridge inspection intervals.  At
present, General Inspections are carried out every two years and Principal Inspections
every six years on all structures with a span more than 0.9m.  More frequent Special
Inspections are carried out on structures where more specific monitoring of condition
is appropriate (e.g. where assessments have indicated potential capacity issues). 
7.5. Routine repairs that are identified during the bridge inspection process are prioritised
considering the severity and extent of the defect which has been observed. 
7.6. There are 102 steel bridges across the structures asset.  Properly specified and
applied protective paint systems are expensive but serve to prolong the life span of
steel structures and can substantially extend intervals between maintenance and
repair operations.  The introduction of a formalised maintenance painting regime for
our steel bridges would be of significant benefit.  Currently, this work is tackled on a
needs basis as funding permits. 
7.7. Investment during 2021/2022 on bridge maintenance and renewal was £860,000. This
figure represents a 52% increase upon the 2019/2020 budget allocation but it should
be noted that this includes targeted investment at two discrete major bridge
replacement projects which extended into 2021/2022. The cost to maintain the
structures asset in its current condition (steady state) is £5.230m. 
7.8. In addition to the inspection process discussed above, a national assessment
programme, carried out to determine the suitability (i.e. strength) of the bridge stock
for the introduction of 40/44 tonne vehicles onto the road network, revealed 123
bridges to have a load bearing capacity below current standards.  A comprehensive
bridge strengthening programme has, in recent years, seen excellent progress in
addressing the Council’s weak bridges. Of the 123 bridges which failed the
assessment, only 16 remain to be addressed.  These are subject to an enhanced
monitoring and inspection regime. 
7.9. The bridge assessment process included a risk analysis of vehicle containment
characteristics at each bridge location.  The results of the analysis revealed that, in
terms of risk and containment, parapets on 8% of the Council’s bridge stock require to
be upgraded.  A programme to improve vehicle containment capability at these
structures has been initiated.  Due to competing priorities, there were no containment
upgrades undertaken in 2020/2021 and 52 structures remain outstanding as a priority
for the implementation of improvement measures. 
7.10. If current funding levels continue to be provided and depending on the nature and
priority afforded to other commitments arising, the completion of several containment
improvement schemes per year is anticipated.  Again, in terms of risk and
containment, the need for upgrading works at the remaining 92% of bridges is currently
considered low.  It should be recognised that some of these parapets do have
containment issues, but the level of risk is low given the site characteristics.  
124

Page 125

7.11. The condition of all highway structures is determined following a General or Principal
Inspection and rated in accordance with the ADEPT Bridge Condition Index (BCI)
Guidance.  BCI values are generated from ratings apportioned to the severity and
extent of defects recorded during a bridge inspection and can be interpreted broadly
as the percentage condition score of a bridge or a group of bridges.  Separate BCI
figures are derived to account for the condition of all structural elements of a bridge
(BCIav) and for the condition of those elements defined as being of very high
importance (BCIcrit).  The condition indicators for the entire bridge stock as a single
group over the past six years are as follows, noting the higher figure indicates better
condition. 
7.12. It may be observed from the second and third columns in the above table that BCIav
and BCIcrit values for the entire asset fluctuate slightly over time but have remained
within the range of “good condition” (BCI value 80-90) and “fair condition” (BCI value
65-80) respectively throughout the last six years.  It should be noted, however, that
there has been a regression in the value of both indicators over the past 6 years which
represents an overall and ongoing deterioration in asset condition within that time. 
7.13. The assembly of a register of road related retaining walls within South Lanarkshire
was commenced in 2014/15.  The retaining wall asset will be of significant magnitude
and the formation of the database which will contain several thousand items is a long-
term commitment for the Council.  The code of practice suggests that all road related
retaining walls should be subject to the same type of inspection regime as is currently
carried out on bridges and culverts (see section 7.4). 
8. Traffic Signals
8.1. The Council is responsible for 231 sets of traffic signals and controlled pedestrian
crossings.  The numbers and different types of installations are listed below: -  
 110 Traffic Signals
 73 Puffins
 15 Pelicans
 33 Toucans 
8.2. South Lanarkshire has an ageing traffic signal and pedestrian crossing asset base,
with many utilising older and energy inefficient technology. In recent years, the Council
has initiated a programme to replace older traffic signals and pedestrian crossings with
modern ones.  The replacement of an average traffic signal junction costs in the region
of £275k and a pedestrian crossing around £77k.  The existing level of funding
generally allows for the renewal of one traffic signal junction per year or 4 pedestrian
crossings. 
Year BCIav BCIcrit
2013-14 85.68 74.60
2014-15 84.91 75.72
2015-16 84.49 75.14
2016-17 84.09 73.02
2017-18 83.83 72.20
2018-19 83.68 72.11
2019-20 82.51 70.39
2020-21 81.87 68.76
2021-22 81.21 68.48
125

Page 126

8.3. External funding does allow other infrastructure to be renewed but this is a changing
situation as it is dependent on the availability of funding and our ability for a project to
meet grant conditions.  These new installations both maximise the safety benefits to
all road users and improve the flow of traffic using modern computer control systems
such as Microprocessor Optimised Vehicle Actuation (MOVA) and Split Cycle Offset
Optimisation Technique (SCOOT). 
8.4. Typically, Roads and Transportation Services receive and respond to approximately
1,500 traffic signal faults annually. In 2020/2021, officers dealt with 1,289 faults and,
in 2021/2022, this decreased to 1,140. 
8.5. The gross replacement value of all traffic signal apparatus is currently estimated at a
value of £33.6m.  The cost to maintain the traffic signal asset in its current condition
(steady state) is £1.500m. 
8.6. In 2022/2023, funding of around £0.975m will be directed towards investment in traffic
signal infrastructure.  This comprises some £0.8m of external funding and £175k of
capital funding. 
8.7. At present, the Council is developing a 15-year lifecycle plan, although the
replacement of each asset is still assessed on an individual needs basis. Any plan
longer than this would result in reliability issues arising and, over recent years, some
installations have failed, resulting in emergency replacement works being necessary.
The Council currently has 34 sets of traffic signals and 56 pedestrian crossings
(representing 35% of our assets) that are 15 years old or older. This is an increase of
5 sets of traffic signals and the status quo for pedestrian crossings compared to the
previous year. 
8.8. It should also be noted that there is no guarantee that, after September 2023, there
will be a supply of incandescent lamps due to an EU directive prohibiting their use and
with the reducing demand, lighting manufactures ceasing their manufacture. The
Council currently has supply for 22 sets of traffic signals and 45 pedestrian crossings
that use these incandescent lamps. 
8.9. The age of the equipment is increasing quicker than replacement equipment is being
installed, therefore, the trend for the overall condition of the asset continues to regress
each year. While these older installations continue to operate, the risk of them failing
is higher than at other locations with potentially greater impact if they fail during a busy
period of the year. 
9. Street Furniture - Vehicle Restraint Systems
9.1. There are currently 515 vehicle restraint systems, totalling 43.3 Km. Approximately
20% of the systems have reached the end of their serviceable life (life expired) due to
having timber posts suffering from rot as opposed to steel posts. Some systems have
also suffered from extensive corrosion. 
9.2. Approximately 10% of existing systems are damaged, and an estimated 95% of the
systems surveyed would not comply with current design standards, although there is
no need to retrospectively replace older installations unless they have suffered
significant damage and need replacement. Repairs are prioritised in line with available
funding.  
126

Page 127

9.3. The estimated gross replacement cost of the vehicle restraint systems which would
bring the systems up to current standards is £12.97million. The estimated cost to
replace older systems is £8.6million. The estimated annual cost to maintain the asset
in its current condition (steady state) is £0.4million. 
10. Conclusions and Summary
10.1. Roads and related infrastructure keep our communities and businesses connected.
Businesses use it to deliver goods and services, buses travel along it, people use it to
travel to work and communities to access shopping, learning, healthcare, and active
travel priorities. This paper sets out the overall condition of this infrastructure and
important matters to note are as follows: 
 Carriageways: This has generally been improving in condition because of
previous investment decisions, with a slight regression in RCI figure in 2020,
recovering slightly again in 2021. 
 Footways / Footpaths: At least 16.2% of our network requires to be considered
for maintenance but it should be noted that investment has been increased
significantly in recent years. 
 Structures: Bridge condition is generally good to fair although the overall outlook
is one of slow deterioration.  Good progress has been made in dealing with
bridges assessed as being inadequate for current loading standard, however,
greater investment is required in the maintenance of the bridge stock to arrest
the general deterioration in condition and continuing attention is additionally
required to the many bridges with sub-standard parapets.  The specific
investment commitment to replace two bridges in Clydesdale is welcomed noting
the need to significantly increase funding for the Clyde Bridge project. 
 Street Lighting: Recent investment has reduced energy use by approximately half
and replaced 7,253 of the oldest lighting columns representing significant
progress. Current investment is focusing on targeting columns over their critical
age, to maintain a ‘steady state’ position.  The percentage of lighting columns
exceeding their design life is 35.7%. 
 Traffic Management Systems: The overall condition of traffic signal equipment is
deteriorating as the current replacement programme is not sufficient to upgrade
the number of installations that are greater than 15 years in age.   
 Street Furniture: The condition of vehicle restraint systems is such that a
significant number are beyond their design life and require to be improved.  A
prioritised programme of sustained investment will be required. 
11. Employee Implications
11.1.  There are no employee implications associated with this report. 
12.  Financial Implications
12.1.  Investment in roads and related infrastructure will be necessary to lock in and retain
the benefits of the already significant investment levels to date.  Capital programmes
for future years will, therefore, consider necessary investment opportunities for the
asset groups discussed above. 
127

Page 128

12.2.  However, as noted earlier, projects are costing much more than before, and the
equivalent scale of works are not presently possible with the same level of investment. 
This point must be considered should the overall condition of the asset groups be
expected, at least, to be maintained to the same level. Moving forward, pressures
across Council budgets are likely to impact on the level of funding that can, in the short
term, continue to be directed at these road infrastructure asset groups. 
12.3.  Similarly, opportunities will be taken to secure and lever in new sources of funding
including external partner funding where possible. Significant success has already
been achieved in securing external funding for traffic signal and active travel
investment 
13. Climate Change, Sustainability and Environmental Implications
13.1.  Policy and asset management directed at maintaining, improving, or making road and
transport infrastructure safe and resilient is essential to support economic and
sustainability priorities. 
14.  Other Implications
14.1.  There are no other implications or risk in relation to the information contained within
this report. 
15.  Equality Impact Arrangements and Consultation Arrangements
15.1.  This report does not introduce a new policy, function or strategy or recommend a 
change to an existing policy, function, or strategy and, therefore, no impact 
assessment is required. 
David Booth
Executive Director (Community and Enterprise Resources) 
21 November 2022 
Link(s) to Council Values/Priorities/Outcomes 
Values 
 Focused on people and their needs 
 Working with and respecting others 
 Accountable, effective, efficient and transparent
 Ambitious, self-aware and improving 
 Fair, open and sustainable 
Priorities 
 We will work to put people first and reduce inequality
 We will work towards a sustainable future in sustainable places 
 We will work to recover, progress and improve 
Outcomes 
 Good quality, suitable and sustainable places to live
 Thriving business, fair jobs and vibrant town centres
 Caring, connected, sustainable communities 
 People live the healthiest lives possible 
128

Page 129

Previous References
 Community and Enterprise Resources Committee -  7 December 2021 
List of Background Papers
 Roads Asset Management Plan – 2022 Update 
Contact for Further Information
If you would like to inspect the background papers or want further information, please contact: 
Colin Park, Head of Roads, Transportation and Fleet Services
Tel: 07795 090 494
E-mail:  colin.park@southlanarkshire.gov.uk  
129

Page 130

Appendix A
RCI tables for A, B, C and Unclassifed Roads
30.2
28.9
28
27.2
25.9
22.7
21
22.2
23 22.9 23.3 23.2 23.9 24
20
22
24
26
28
30
32
34
RCI Value
South Lanarkshire A Class
A Class
32.3
29.7 30.1
31.8
30.4
25.0
22.7
23.7 24.1 24.5
25.0 25.3
26.2
25.6
20.0
22.0
24.0
26.0
28.0
30.0
32.0
34.0
RCI Value
South Lanarkshire B Class
B Class
130

Page 131

32.3
29.7 30.1
31.8
30.4
25.0
22.7
23.7 24.1 24.5 25.0 25.3
26.2
25.6
20.0
22.0
24.0
26.0
28.0
30.0
32.0
34.0
RCI Value
South Lanarkshire B Class
B Class
37.8
39.5
40.5
38.7 39.0 39.5
37.0 36.8
35.5
33.4
32.3
30.3 30.5
29.9
28.0
30.0
32.0
34.0
36.0
38.0
40.0
42.0
RCI Value
South Lanarkshire Unclassified
U Class
131

Page 132

132

Page 133

Report
Agenda Item 
Report to: Community and Enterprise Resources Committee
Date of Meeting: 13 December 2022
Report by: Executive Director (Community and Enterprise
Resources)  
Subject: Comfort Scheme Pilot (Lanark) 
1. Purpose of Report
1.1. The purpose of the report is to: - 
 provide Community and Enterprise Resources Committee with an update on the
comfort scheme pilot (Lanark) 
2. Recommendation(s)
2.1. The Committee is asked to approve the following recommendation(s):- 
(1) that the evaluation of the comfort scheme pilot be noted;
(2) that it be noted that, following the evaluation of the pilot, the Council would not
continue the scheme; and
(3) that it be noted that the Council would progress discussions with Lanark
Business Improvement District (BID) on the potential continuation of the
scheme under their management and operation. 
3. Background
3.1. In 2013, the Council made the decision to close all public conveniences, as part of
that year’s budget process. Over the subsequent 3 years, all the Council’s 21 public
conveniences were closed to the public. Since then, the Council has continued to
make an annual £2k contribution to the New Lanark heritage site for public use of
their facilities. There are also 2 local community groups which operate and manage
public convenience provision in Larkhall and Biggar. 
3.2. At the time, the Council explored extending the comfort scheme arrangement at
New Lanark to local businesses in areas where the public convenience was
closing. The conclusion was that there were sufficient alternative locations including
shops, that provided public access to toilet provision. The final determining factor
was the low usage of the existing public conveniences. 
3.3. In line with the Business Improvement District (BID) for Lanark, a decision was
taken to pilot a comfort scheme (Community Toilet Scheme) initiative from April
2019 to April 2020.  The comfort scheme enables local authorities to work in
partnership with local businesses to provide access for the public to clean, safe,
and accessible toilets in local business premises.  Local businesses are paid a
small annual fee for providing this access.  
11
133

Page 134

4. Comfort Scheme Pilot 
4.1. Local businesses were written to in March 2019 to request expressions of interest
to participate in the comfort scheme. From the expressions of interest received, 3
local businesses were registered for the pilot: Clydesdale Inn, Castlebank
Horticultural Centre and Horse and Jockey Bar. In addition, it was agreed that
Council and SLLC premises would participate i.e. South Vennel, Lanark Memorial
Hall, Lanark library and Lanark Lifestyles. 
4.2. The three local businesses were assessed in line with agreed comfort scheme
assessment criteria.  The annual fees range from £500 to £1,500 per annum, as
determined by the standard of the facilities provided. South Lanarkshire Legal
Services prepared Minutes of Agreement in relation to access and fee payments as
agreed with the local businesses for the pilot period.   
4.3. The scheme was launched in July 2019 for an initial period of 1 year. However, as
a result the onset of the Covid pandemic in March 2020, the pilot has been
interrupted on several occasions and the decision was taken to extend the scheme
until the end of the September 2022 to allow at least one full year of operation. It
should be noted that the Council facilities were also closed to the public during this
time. 
4.4. The scheme was publicised using social media and the Council website as well as
publicity at the local train station. Local businesses also display the scheme logo on
windows and entrances to buildings. In 2021, the publicity was extended to include
lamppost advertising which displayed a QR code and this allowed the posters to be
dynamic and updated via the Council website. The website provided up to date
details of the premises offering the comfort scheme and a map to locate them.   
5. Evaluation of Pilot 
5.1. Prior to the evaluation commencing, the 3 business were visited to agree the final
extension to September 2022 and to discuss the evaluation process. Council
officers visited the three local premises on a number of different occasions to
observe the activity of visitors to these premises. During these visits, footfall to all 3
premises was low ranging from 0 visitors to 4 visitors. It cannot be determined if
visitors were attending the premise for the sole purpose of the comfort scheme. The
visits took place in July and August 2022 at various points in the day, with a
particular focus on lunchtime periods. The total cost for the pilot was £9,675 (see
breakdown at 6.1). 
5.2. The anticipated ongoing costs for the retention of the existing scheme would be
around £6,800. Ongoing support would be required for the scheme to respond to
business and member enquires and undertake assessments.  Annual fees,
advertising costs and legal costs would continue to be incurred. 
5.3. During this time, following local member request, Discover Lanark (BID) were
contacted to discuss the comfort scheme with the Discover Lanark Board keen to
see the outcome of the pilot evaluation. It is clear from discussions that the Board
sees a value to having toilets available to visitors to the area and is willing to
discuss and work with the Council to ensure provision of a comfort scheme can
continue. 
134

Page 135

5.4. Given the evaluation of the pilot and the overall cost to the Council to administer
and run the scheme, it is proposed that the Council does not continue the scheme
on a permanent basis. However, following positive initial discussions with Discover
Lanark it is proposed to continue these discussions with the aim of continuing the
comfort scheme under their management and operation with appropriate support
from the Council. 
6. Employee Implications
6.1. The Council has committed staff time and resource from Facilities Management and
Legal Services in the set up and operation of the pilot scheme. Any continuation of
the scheme will require further commitment in staff time. 
7. Financial Implications 
7.1. The financial costs incurred for operating and administering the comfort scheme
pilot are shown below:- 
Fees for 3 current members  £5,555 
Advertising  £200
Staffing costs (inc. set up, administering, and assessing)  £3,920
Total  £9,675 
7.2. There is no identified ongoing revenue budget for the set up and operation of a
comfort scheme. 
8. Climate Change, Sustainability and Environmental Implications
8.1. There are no significant implications in terms of climate change, sustainability and 
environmental implications associated with this report 
9. Other Implications
9.1. There are no other significant implications as result of the contents of this report.   
10. Equality Impact Assessment and Consultation Arrangements:  
10.1. The report does not introduce a new policy, function or strategy or recommend a
change to an existing policy, function or strategy and, therefore, no impact
assessment is required 
10.2. There is no requirement to undertake consultation in terms of the information
contained in this report. 
David Booth 
Executive Director (Community and Enterprise Resources) 
21 November 2022   
Link(s) to Council Values/Priorities/Outcomes
 Focused on people and their needs 
 Working with and respecting others 
 Accountable, effective, efficient and transparent 
135

Page 136

List of Background Papers
 None 
Contact for Further Information
If you would like further information, please contact:
Anne Goldie, Facilities Services Manager
Mobile (07795 090278)
E-mail:  anne.goldie@southlanarkshire.gov.uk 
136

Page 137

Report
Agenda Item 
Report to: Community and Enterprise Resources Committee
Date of Meeting: 13 December 2022
Report by: Executive Director (Community and Enterprise
Resources)  
Subject: Community and Enterprise Resources - Notification of
Contracts Awarded - 1 April to 30 September 2022 
1. Purpose of Report
1.1. The purpose of the report is to:-
[purpose]
 provide notification in line with Standing Orders on Contracts to Committee of
all contracts awarded by Community and Enterprise Resources during the
period 1 April to 30 September 2022.
1purpose] 
2. Recommendation(s)
2.1. The Committee is asked to approve the following recommendation(s):-
[recs]
(1) that details of the contracts awarded be noted.
[1recs]
3. Background
3.1. It is a requirement of Clauses 21.8 and 22.5 of the Standing Orders on Contracts that
details of the acceptance of all tenders above £50,000 be reported retrospectively to
the relevant Committee for noting, other than those under Clause 21.3 where the
award is not the lowest in a price only tender, or costs exceed the approved financial
provision. In these instances, a report is submitted to the appropriate Committee and
subsequent authority to award is granted by that Committee. 
4. Contract Awards
4.1. A full list of contracts awarded during the period 1 April to 30 September 2022 on the
basis of lowest offer and/or most economically advantageous offer submitted, is
provided at Appendix 1. 
5. Employee Implications
5.1. Contracts management including performance appraisal will be undertaken by both
the main user Services and Procurement. 
6. Financial Implications
6.1. There are no financial implications associated with this report which is for information
purposes only. Appropriate budgetary provision is available for each of the contracts
awarded. 
7. Climate Change, Sustainability and Environmental Implications
7.1. There are no climate change or environmental implications as a result of this report 
12
137

Page 138

8. Other Implications
8.1. There is a risk that failure to report awards may lead to contracts being awarded that
do not represent best value, breach statutory procurement obligations and Standing
Orders or do not follow internal processes which mitigate the risk. 
9. Equality Impact Assessment and Consultation Arrangements
9.1. This report does not introduce a new policy, function or strategy nor recommend a
change to an existing policy, function, or strategy and therefore, no impact assessment
is required. 
9.2. There is also no requirement to undertake any consultation in terms of the
information contained in this report. 
David Booth
Executive Director (Community and Enterprise Resources) 
21 November 2022 
Link(s) to Council Values/Ambitions/Objectives
 Accountable, Effective, Efficient and Transparent 
Previous References
 Community and Enterprise Resources Committee 
List of Background Papers
 Standing Orders on Contracts 
Contact for Further Information
If you would like to inspect the background papers or want further information, please
contact:-
Emma Smith, Corporate Procurement and Transactions Manager
Ext:  5329 (Tel:  01698 455329)
E-mail: emma.smith@southlanarkshire.gov.uk 
138

Page 139

Appendix 1 
Community and Enterprise Resources 
Contracts Awarded over £50,000 in value 
Contractor CRN
Value of
Contract
Awarded
Date of Award Brief Description Contract
Period
Calor Gas Ltd SLC/PS/COMENT/21/149 £80,000.00 19 April 2022
The Supply and Delivery of Industrial
Gases
19/04/2022 
-
31/03/2023
Extension
31/03/2024
Stanger Testing Services
Ltd  SLC/PS/COMENT/21/135 £429,337.50 13 May 2022 Road Materials Testing Contract
13/05/2022 
-
12/05/2025
Extension to 
12/05/2027
Glasdon UK Ltd SLC/PS/COMENT/21/032 £279,980.00 19 May 2022
Supply and Delivery of Bollards and
Verge Markers
30/05/2022 
-
29/05/2024
Extension to
29/05/2026
Ricardo-Aea Ltd SLC/PS/COMENT/21/116 £50,000.00 20 May 2022
Air Quality Monitoring Support
Services 
01/07/2022 
-
31/03/2023
Elveden farms Ltd SLC/PS/COMENT/22/041 £65,207.00 30 May 2022
Supply and Delivery of Christmas
Trees 2022
30/05/2022 
- 
31/01/2023
Facultatieve Technologies
Ltd SLC/PS/COMENT/21/161 £180,000.00 1 June 2022
Maintenance of Crematorium
Equipment 
01/06/2022 
- 
31/05/2026
Extension to 
31/05/2028
139

Page 140

Lloyd Ltd  SLC/PS/COMENT/22/034  £261,128.00  31 May 2022
The Supply of Bobcat E19
Excavators with Double Dozer Blade
and C/W Trailer 
31/05/2022 
- 
30/04/2023
Patersons of Greenoakhill
Ltd SLC/PS/COMENT/21/219 £477,400.00 1 June 2022
Landfilling of Residual Waste
(unsuitable for processing via
Thermal Treatment Facilities) 
01/06/2022 
- 
31/12/2025
Charles Tennant & co Ltd SLC/PS/COMENT/21/157 £160,005.00 8 June 2022 Supply of Ad-Blue Fuel Additive
08/06/2022
- 
07/06/2025
Tarmac Ltd SLC/PS/COMENT/21/199 £68,266.50 17 June 2022
Supply and Delivery of Cold
Permanent Pothole Repair - Viafix
13/06/2022 
- 
29/02/2024 
Extension to 
28/02/2025
P F Cusack (tools supplies)
Ltd SLC/PS/COMENT/21/037 £120,000.00 22 June 2022
Supply and Delivery of
Miscellaneous Roads Products
27/06/2022 
- 
26/06/2024
Extension to 
26/06/2026
Mallatite Minor Struct &
Prod Ltd SLC/PS/COMENT/22/046 £230,000.00 9 June 2022
Supply and Delivery of Ultracrete
M90 (Eprobed)
27/06/2022 
- 
26/06/2024
Extension to 
26/06/2026
SSI Schaefer Limited SLC/PS/COMENT/22/051 £850,000.00 1 July 2022
The Supply and Delivery of Refuse
Containers
01/07/2022 
- 
30/06/2023
Intelligent Health SLC/PS/COMENT/22/053 £114,997.00 13 July 2022 Beat the Street East Kilbride
01/07/2022 
- 
31/07/2023
Compass Minerals UK Ltd SLC/PS/COMENT/22/064 £1,333,042.00 11 July 2022
Bulk Rock Salt for Winter
Maintenance
11/07/2022
- 
31/10/2022
Salt Sales Company SLC/PS/COMENT/22/064 £1,333,042.00 11 July 2022
Bulk Rock Salt for Winter
Maintenance
11/07/2022 
-
31/10/2022
140

Page 141

TRL Ltd SLC/PS/COMENT/22/002 £140,000.00 1 August 2022
ECO Stars Commercial Fleet
Scheme 
01/08/2022 
- 
31/07/2025
Boyd Brothers (Fauldhouse)
Ltd SLC/PS/COMENT/21/212 £124,853.79 20 July 2022
Electric Vehicle Public Charing
Infrastructure 
01/08/2022
- 
01/12/2022
A G Barr plc SLC/PS/COMENT/21/162 £845,480.00
17 August
2022
Supply and Delivery of Soft Drinks
and Bottled Water for Resale
17/08/2022 
- 
17/08/2025
Extension to
17/08/2027
Fast Fixx Catering
Engineers Ltd SLC/PS/COMENT/22/031 £450,000.00 1 May 2022
Repair, Inspection and Maintenance
of Commercial Catering Equipment
01/05/2022 
- 
30/04/2023
Extension to
30/04/2024
Chargemaster Ltd SLC/PS/COMENT/22/085 £254,287.00 
6 September
2022
Installation of Electric Vehicle
Charging Points 
03/01/2022 
- 
30/06/2022
Parks Motor Group SLC/PS/COMENT/22/090 £58,000.00
20 September
2022 Supply and delivery of Light Vehicles 
20/09/2022 
- 
31/03/2023
Motus Commercials SLC/PS/COMENT/22/091 £1,728,218.00
20 September
2022
Supply and delivery of Heavy
Vehicles 
20/09/2022 
- 
31/03/2023
Brakes SLC/PS/COMENT/22/027 £4,859,077.98 31 May 2022
Supply and distribution of Frozen
Foods 
30/05/2022
- 
29/05/2024
Extension to
29/05/2026
Dennis Eagle Ltd SLC/PS/COMENT/22/036 £2,551,720.00  4 May 2022
Supply and delivery of Heavy
Vehicles 
04/05/2022
- 
31/12/2022
Fuchs Lubricants (UK) plc SLC/PS/COMENT/21/216 £156,000.00  5 May 2022
Supply and Delivery of Lubricant
Oils, Greases and Anti-Freeze
09/05/2022 
- 
08/05/2025
Extension to
08/05/2026
141

Page 142

Brakes SLC/PS/COMENT/22/005 £127,891.70
12 September
2022
The Supply and Distribution of Fresh
Meats, Cooked Meats & Fresh Fish
01/10/2022 
- 
31/03/2023
Campbells Prime Meat Ltd SLC/PS/COMENT/22/005 £127,891.70
12 September
2022
The Supply and Distribution of Fresh
Meats, Cooked Meats & Fresh Fish
01/10/2022 
- 
31/03/2023
Covanburn Contracts Ltd SLC/PS/COMENT/18/062 £59,772.37
23 September
2022 Scrogton Bridge Refurbishment
27/09/2022 
- 
08/11/2022      
Electrical Testing Ltd SLC/PS/COMENT/21/234 £600,000.00 22 June 2022
Highway Electrical Connections and
Minor Installation Works
23/06/2022
–
22/12/2023
Extension to 
22/06/2025
Tructyre Fleet Management
McConechy’s Tyre Service SLC/PS/COMENT/21/147 £2,200,000.00 23 June 2022
Supply and Fitting of Tyres for
Vehicles and Plant
15/06/2022
-
31/01/2026
Grafton Merchanting GB Ltd SLC/PS/COMENT/21/036 £560,000.00 27 July 2022
Supply and Delivery of Drainage
Products
01/08/2022 
-
31/07/2024
Extension to
31/07/2026  31-Jul-24 
142

Page 143

Contract extensions awarded over £50,000 in value 
Contractor Contract Reference Value of Contract
Awarded
Date of
Extension Brief Description
Contract
Extension
period 
Excel
Environmental
Services SLC/PS/COMENT/17/247 £2,460,000.00 1 September 2022
Pest Control, Industrial Cleaning
and Other Environmental Services
30/09/2022 
-
30/09/2023
John McGeady Ltd SLC/PS/COMENT/19/133 £3,780,000.00 6 April 2022 Planer and Paver Hire and Works
30/04/2022 
-
30/04/2024
Scottish SPCA SLC/PS/COMENT/19/004 £100,000.00 1 July 2022 Kennelling of Stray Dogs
30/09/2022 
-
30/09/2024
Various
contractors SLC/PS/COMENT/17/138 £10,800,000.00 1 April 2022
Framework for the Supply and
Delivery of Coated and 
Uncoated Roadstone & Readymix
Concrete
01/04/2022 
-
31/03/2023
Extension to
30/09/2023 
143

Page 144

144