Democracy Spraffa

Agenda Document Pack - Community and Enterprise Resources Committee - 18/06/2024

South Lanarkshire Council · 18 June 2024
Back to Community and Enterprise Resources Committee — 18 June 2024 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

Council Offices, Almada Street        
Hamilton, ML3 0AA 
Monday, 10 June 2024 
Dear Councillor 
Community and Enterprise Resources Committee 
The Members listed below are requested to attend a meeting of the above Committee to be
held as follows:- 
Date:  Tuesday, 18 June 2024
Time:  14:00
Venue: Hybrid - Council Chamber, Council Offices, Almada Street, Hamilton,
ML3 0AA 
The business to be considered at the meeting is listed overleaf. 
Yours sincerely 
Paul Manning
Chief Executive 
Members 
Robert Brown (Chair), Maureen Devlin (Depute Chair), Joe Fagan (ex officio), John
Anderson, Ralph Barker, Walter Brogan, Andy Carmichael, Gerry Convery, Poppy Corbett,
Andrea Cowan, Margaret Cowie, Colin Dewar, Gladys Ferguson-Miller, Ross Gowland,
Graeme Horne, Cal Johnston-Dempsey, Susan Kerr, Martin Lennon, Richard Lockhart,
Hugh Macdonald, Ian McAllan, Kenny McCreary, Davie McLachlan, Carol Nugent, Helen
Toner, David Watson 
Substitutes
Alex Allison, Ross Clark, Margaret Cooper, Allan Falconer, Alistair Fulton, Lynsey Hamilton,
Ross Lambie, Lesley McDonald, Elaine McDougall, Mark McGeever, Richard Nelson,
Graham Scott, David Shearer 
1

Page 2

BUSINESS 
1 Declaration of Interests 
2 Minutes of Previous Meeting
Minutes of the meeting of the Community and Enterprise Resources
Committee held on 23 April 2024 submitted for approval as a correct
record.  (Copy attached) 
5 - 18 
Monitoring Item(s) 
3 Community and Enterprise Resources – Workforce Monitoring – March to
April 2024
Joint report dated 10 May 2024 by the Executive Directors (Finance and
Corporate Resources) and (Community and Enterprise Resources). 
(Copy attached) 
19 - 26 
4 Community and Enterprise Resource Plan - Quarter 4 Progress Report
2023/2024
Report dated 28 May 2024 by the Executive Director (Community and
Enterprise Resources).  (Copy attached) 
27 - 66 
Item(s) for Decision 
5 Community and Enterprise Resource Plan 2024/2025
Report dated 23 May 2024 by the Executive Director (Community and
Enterprise Resources).  (Copy attached) 
67 - 94 
6 Community Benefit Funds – Renewable Energy Fund Grant Applications
Report dated 23 May 2024 by the Executive Director (Community and
Enterprise Resources).  (Copy attached) 
95 - 108 
7 Community Benefit Funds Kype Muir Windfarm Connect2Renewables
Extension
Report dated 28 May 2024 by the Executive Director (Community and
Enterprise Resources).  (Copy attached) 
109 - 114 
8 South Lanarkshire Council Bereavement Services Strategy 2024 to 2033
Report dated 29 May 2024 by the Executive Director (Community and
Enterprise Resources).  (Copy attached) 
115 - 142 
9 Introduction of Charge for Uplift of Household Garden Waste (Burgundy)
Bin
Joint report dated 28 May 2024 by the Executive Directors (Community
and Enterprise Resources) and (Finance and Corporate Resources). 
(Copy attached) 
143 - 154 
10  Extension of the Household Waste and Recycling Centres (HWRCs)
Booking System
Report dated 28 May 2024 by the Executive Director (Community and
Enterprise Resources).  (Copy attached) 
155 - 160
2

Page 3

11  Operational and Financial Implications of Managing Waste Upholstered
Domestic Seating (WUDs) containing Persistent Organic Pollutants (POPs)
Joint report dated 28 May 2024 by the Executive Directors (Community and
Enterprise Resources) and (Finance and Corporate Resources).  (Copy
attached) 
161 - 166 
12  UK Levelling Up Fund Update and Next Steps
Report dated 7 June 2024 by the Executive Director (Community and Enterprise
Resources).  (Copy attached) 
167 - 170 
Item(s) for Noting 
13  Scottish Government Play Investment Programme
Report dated 30 May 2024 by the Executive Director (Community and
Enterprise Resources).  (Copy attached) 
171 - 188 
14  Biggar Public Park - Update
Report dated 30 May 2024 by the Executive Director (Community and
Enterprise Resources).  (Copy attached) 
189 - 194 
15  Community and Enterprise Resources - Notification of Contracts Awarded
- 1 October 2023 to 31 March 2024
Report dated 20 May 2024 by the Executive Director (Community and
Enterprise Resources).  (Copy attached) 
195 - 200 
Urgent Business 
16  Urgent Business
Any other items of business which the Chair decides are urgent. 
For further information, please contact:-
Clerk Name: Elizabeth-Anne McGonigle
Clerk Telephone: 07385 403101
Clerk Email: elizabeth-anne.mcgonigle@southlanarkshire.gov.uk 
3

Page 4

4

Page 5

COMMUNITY AND ENTERPRISE RESOURCES COMMITTEE 
Minutes of meeting held via Confero and in Committee Room 1, Council Offices, Almada Street,
Hamilton on 23 April 2024 
Chair:
Councillor Robert Brown 
Councillors Present:
Councillor John Anderson, Councillor Gerry Convery, Councillor Poppy Corbett, Councillor Andrea
Cowan, Councillor Margaret Cowie, Councillor Maureen Devlin (Depute), Councillor Colin Dewar,
Councillor Lynsey Hamilton (substitute for Councillor Davie McLachlan), Councillor Graeme Horne,
Councillor Cal Johnston-Dempsey, Councillor Hugh Macdonald, Councillor Ian McAllan, Councillor
Kenny McCreary, Councillor Carol Nugent, Councillor Graham Scott (substitute for Councillor Ralph
Barker), Councillor Helen Toner, Councillor David Watson 
Councillors' Apologies:
Councillor Ralph Barker, Councillor Walter Brogan, Councillor Andy Carmichael, Councillor Joe
Fagan, Councillor Gladys Ferguson-Miller, Councillor Ross Gowland, Councillor Susan Kerr,
Councillor Martin Lennon, Councillor Richard Lockhart, Councillor Davie McLachlan 
Attending:
Community and Enterprise Resources
D Booth, Executive Director; A Brown, Head of Enterprise and Sustainable Development Services;
K Carr, Head of Facilities, Waste and Grounds Services; K Lean, Economic Development Manager
(Funding and Rural); C Park, Head of Roads, Transportation and Fleet Services; I Ross, Project
Manager; I Russell, Construction Manager
Finance and Corporate Resources
J Davitt, Public Relations Team Leader; N Docherty, Administration Assistant; L Harvey, Finance
Manager; E-A McGonigle, Administration Officer; E McPake, Human Resources Business Manager;
L O’Hagan, Finance Manager (Strategy); M M Wilson, Legal Services Manager 
1 Declaration of Interests 
No interests were declared. 
2 Minutes of Previous Meeting 
The minutes of the meeting of the Community and Enterprise Resources Committee held on 6
February 2024 were submitted for approval as a correct record. 
The Head of Enterprise and Sustainable Development Services provided updates in response to
members’ questions on Item 11, the Inward Investment Strategy. 
The Committee decided: 
(1) that minutes be approved as a correct record; and 
(2) that the update from the Head of Enterprise and Sustainable Development Services in
relation to the Inward Investment Strategy be noted. 
Councillors Cowan and Dewar entered the meeting during consideration of the above item of
business 
2
5

Page 6

3 Community and Enterprise Resources - Revenue Budget Monitoring 2023/2024 
A joint report dated 6 March 2024 by the Executive Directors (Community and Enterprise
Resources) and (Finance and Corporate Resources) was submitted comparing actual
expenditure at 26 January 2024 against budgeted expenditure for 2023/2024 for Community
and Enterprise Resources and providing a forecast for the year to 31 March 2024.   
Following the probable outturn exercise, the Resource was reporting a breakeven position after
approved transfers to reserves of £0.240 million as at 31 March 2024.  The breakeven position
was due to underspends, as detailed at paragraph 5.2 of the report, which had been offset by a
marginal over recovery of income from Planning and Building applications. 
The Resource position as at 26 January 2024 was a breakeven position after approved transfer
to reserves, as outlined in Appendix A.  The breakeven position reflected underspends in
employee costs and costs within Roads, Transportation and Fleet Services in relation to
transport costs and an under recovery in parking income.   
Details were also provided in appendices B to F on proposed budget virements in respect of
Community and Enterprise Resources to realign budgets. 
The Committee decided: 
(3) that the forecast to 31 March 2024 of a breakeven position after approved transfers to
reserves, as detailed in Appendix A of the report, be noted; 
(4) that the breakeven position as at 26 January 2024 on Community and Enterprise
Resources’ revenue budget, as detailed in Appendix A of the report, be noted; and 
(5) that the proposed budget virements, as detailed in appendices B to F, be approved. 
[Reference: Minutes of 6 February 2024 (Paragraph 4)] 
4 Community and Enterprise Resources - Capital Budget Monitoring 2023/2024 
A joint report dated 6 March 2024 by the Executive Directors (Community and Enterprise
Resources) and (Finance and Corporate Resources) was submitted advising of progress on the
Community and Enterprise Resources’ capital programme 2023/2024 and summarising the
expenditure position at 26 January 2024. 
The revised Capital Programme for 2023/2024 amounted to £45.177 million. This reflected the
budget of £38.577 million reported to the last meeting of the Committee which had been
adjusted to reflect an increase of £6.600 million in relation to the Glasgow City Region City Deal,
Greenhills Road project which had been approved by the Executive Committee on 24 January
2024.  This adjustment was incorporated into the 2023/2024 capital programme following
approval by the Glasgow City Region City Deal Cabinet on 13 February 2024. 
As at 26 January 2024, expenditure was £18.907 million, which was £0.239 million behind
programme.  The underspend reflected timing of project expenditure on the Roads Carriageway
programme, with recharges still to be processed for works completed to date.  The projected
outturn for the financial year was £40.700 million.  This represented an underspend of £4.477
million and the majority of the variance was due to timing of spend on a number of projects
which resulted in budget required in 2024/2025 rather than 2023/2024. 
Details of those projects which would underspend in 2023/2024 were provided at paragraph 5.3
of the report.
6

Page 7

The Committee decided: 
(1) that the Community and Enterprise Resources’ capital programme of £45.177 million, and
expenditure to date of £18.907 million, be noted; and 
(2) that the projected outturn of £40.700 million be noted. 
[Reference: Minutes of the Executive Committee of 24 January 2024 (Paragraph 4) and 21
February 2024 (Paragraph 4) and Minutes of 6 February 2024 (Paragraph 5)] 
Councillor Horne entered the meeting during consideration of the above item of business 
5 Community and Enterprise Resources - Workforce Monitoring – December 2023
to February 2024 
A joint report dated 13 March 2024 by the Executive Directors (Community and Enterprise
Resources) and (Finance and Corporate Resources) was submitted on the following employee
information for Community and Enterprise Resources for the period December 2023 to February
2024:- 
 attendance statistics
 occupational health statistics
 accident/incident statistics
 disciplinary hearings, grievances and Dignity at Work cases
 analysis of leavers and exit interviews
 staffing watch as at 9 December 2023 
The Human Resources Business Manager responded to a member’s questions on various
aspects of the report. 
The Committee decided: that the report be noted. 
[Reference:  Minutes of 6 February 2024 (Paragraph 6)] 
6 Hagshaw Energy Cluster – Retention of Economic Development Officer 
A joint report dated 28 March 2024 by the Executive Directors (Community and Enterprise
Resources) and (Finance and Corporate Resources) was submitted on the extension of 1 Full
Time Equivalent (FTE) Economic Development Officer within the Enterprise and Sustainability
Services for a further 24 months. 
In March 2022, the Executive Committee approved that the annual income from the Douglas
West Windfarm community benefit payments, estimated at £117,000 per annum, be used to
fund an Economic Development post for up to 23 months with the remaining contribution going
to the Renewable Energy Fund (REF) for use in the local area. 
The Hagshaw Energy Cluster Development Framework was approved by the Planning
Committee in October 2023 and reported to the Community and Enterprise Resources
Committee in August 2023.  In December 2023, the Framework won the Scottish Green Energy
Award in sustainable development and was shortlisted in the Landscape Institute Awards in the
Excellence in Climate, Environment and Social Outcomes category in November 2022.
7

Page 8

The Economic Development Officer post, which was filled in June 2022, had been successful in
commencing scoping on larger, more successful projects such as adventure tourism, rural
housing, circular economy, and active travel connections in the area.  The post was supporting
local communities within the Douglas Valley area to develop larger strategic projects and it was
recognised that this would take time.  The windfarm developers of the Hagshaw Energy Cluster
Developers’ Group, as detailed in section 4.1 of the report, had requested that the post be
continued beyond the initial 23 month contract. 
The income to the Douglas West Windfarm Community Benefit Fund in 2023/2024 was
£141,000, with a further uncommitted balance of £331,000.  It was proposed that the 1 FTE post
of Economic Development Officer on Grade 3, Level 2–4, (£37,867 to £43,615) be extended for
a further 24 months, using funds from the Douglas West Windfarm, as detailed in paragraphs
4.2 and 4.3 of the report. 
The Committee decided: that the 1 FTE Economic Development Officer post on
Grade 3, Level 2– 4 (£37,867 to £43,615) within the
Enterprise and Sustainability Services establishment be
extended to June 2026 using funds from the Douglas West
Windfarm community benefit contributions, as detailed in
paragraphs 4.2 and 4.3 of the report. 
[Reference: Minutes of the Executive Committee 2 March 2022 (Paragraph 7) and Minutes of
29 August 2023 (Paragraph 13)] 
7 Community Benefit Funds – Renewable Energy Fund – Grant Application 
A report dated 28 March 2024 by the Executive Director (Community and Enterprise Resources)
was submitted on 2 applications to the various Community Benefit Funds.  The Community
Benefit Funds had been established to provide funding to suitable projects providing community
benefits in eligible areas. 
It was proposed that, subject to the applicants providing written confirmation that all other
additional funding for the projects had been secured, a grant be awarded up to a maximum of:- 
 £57,858 towards eligible costs associated to create an activities shelter and the installation
of photovoltaic panels to Auchengray Church Centre Trust from the Black Law Windfarm
Renewable Energy Fund
 £100,689.48 towards eligible costs associated with the upgrade of McKirdy Park
community space to Lesmahagow Community Council from the Kype Muir Windfarm
Renewable Energy Fund 
The Committee decided: that, subject to the applicants providing written confirmation
that all other funding for the projects had been secured, a
grant be awarded of up to a maximum of:- 
 £57,858 towards eligible costs associated to create
an activities shelter and the installation of
photovoltaic panels to Auchengray Church Centre
Trust from the Black Law Windfarm Renewable
Energy Fund
 £100,689.48 towards eligible costs associated with
the upgrade of McKirdy Park community space to
Lesmahagow Community Council from the Kype Muir
Windfarm Renewable Energy Fund 
[Reference: Minutes of 7 November 2023 (Paragraph 9)]
8

Page 9

8 Scottish Mines Restoration Trust - Mainshill 
A report dated 28 March 2024 by the Executive Director (Community and Enterprise Resources)
was submitted seeking approval for funds received from the Scottish Mines Restoration Trust
(SMRT) Limited to be managed by Community and Enterprise Resources in accordance with
the conditions of the grant. 
The SMRT was established as a charity in 2013 and had the charitable aims of advanced
environmental, conservation and/or improvements at, or within, a 10 mile boundary of any
opencast coal mining site at any time owned by the SMRT. 
Following the demise of Scottish Coal, SMRT undertook site restoration works at Mainshill
opencast mine near Douglas, creating Mainshill Wood, and had passed the ownership to
Forestry and Land Scotland. 
In late 2022, SMRT notified the Council that it would be ceasing operations and remaining funds
would be disbursed to suitable organisations for use of those funds in line with the Trust’s
charitable aims.   
The Council entered discussions with SMRT in 2023 and, under delegated authority, accepted a
payment of £105,000 in August 2023.  The Environmental Improvement Agreement between
SMRT and the Council was detailed at paragraph 4.2 of the report.  The “Grant Project” would
involve the construction and improvement of paths, and associated environmental improvement
works at, or within, the 10 mile boundary of the former Mainshill opencast coal mining site. 
External funding was currently being sought from Paths for All for delivery of the following 2
active travel path projects in the Douglas Valley area:- 
 Douglas to Coalburn – estimated at £600,000
 Coalburn to NCN74 – estimated at £176,000 
Renewable Energy Funding (REF) would also be sought as a contribution to the projects, with
delivery planned later in 2024.  It was proposed that the SMRT grant of £105,000 should be
used as a contribution to one, or both projects, depending on the progress with securing grant
funding. 
The Committee decided: that the £105,000 grant from the Scottish Mines
Restoration Trust (SMRT) be used to deliver active travel
paths, as detailed at paragraph 4.3 of the report. 
9 Centre West Shopping Centre, East Kilbride – Transfer of Ownership to South
Lanarkshire Council 
A report dated 27 March 2024 by the Executive Director (Community and Enterprise Resources)
was submitted:- 
 providing an update on the current position of Centre West Shopping Centre, East Kilbride
 seeking endorsement for the proposed approach to ensure the smooth handover of Centre
West Shopping Centre, East Kilbride to the Council   
East Kilbride, like most town centres across the UK, had faced many challenges over recent
years resulting in significant voids throughout the shopping centre.  Approximately a third of
vacant units in the shopping centre had been empty for more than 3 years.  Those challenges
had resulted in the shopping centre being put into administration on 16 November 2022.  
9

Page 10

The administrator, Interpath, had appointed a team of specialists to consider the future of the
town centre.  This was led by Scoop Asset Management, and included 360 Architecture and
Savills property agent, who worked closely with Council officers to undertake a masterplanning
exercise for the town centre.  The resultant East Kilbride Town Centre Masterplan was approved
by the Executive Committee on 13 September 2023. 
Despite being the most recently developed part of the town centre, Centre West had several
challenges which made it commercially unviable and those were fully detailed at paragraph 3.3
of the report.  The East Kilbride Masterplan had identified Centre West as a new residential
neighbourhood following demolition of the site. 
The current position of East Kilbride Shopping Centre was detailed in section 4 of the report
whereby it was held in split ownership, with Centre West being owned by Sapphire 15 and the
remainder of the asset (Olympia, Plaza and Princes Malls) by Sapphire 16.  The remainder of
the shopping centre would be marketed for sale over the coming months and it was expected
that Sapphire 16 would be put on the market in April/May 2024.   
Given the stark financial position, Sapphire 15 had confirmed its intention to hand back Centre
West to the Council which retained the ground lease.  The existing owners were expecting a
legal agreement to facilitate this as early as summer 2024, with transfer of ownership expected
to take place in December 2025/January 2026.  A proactive approach was, therefore, required
for the transfer of ownership alongside the progression of the Masterplan.  The Council’s
external advisers, Knight Frank, had undertaken an options appraisal and made a clear
recommendation that the Council would continue to engage with the owners to prepare for
ownership and to progress the Masterplan proposals within the indicated timescales. 
Demolition of Centre West would allow for early elements of the Masterplan to be delivered and
would bring new residents to the town centre.  The development of a ‘Civic Hub’ Council facility
would also be progressed and details of that project would be presented at a future meeting of
the Committee. 
To take control of Centre West in a controlled and managed way, a variety of arrangements had
to be implemented and it was proposed that a professional team was put in place as follows:- 
 interim/ongoing property management advice by an independent adviser, appointed to act
on behalf of the Council, to oversee property management decisions by Scoop/new owner
 appointment of independent technical consultants to advise on:-
 the current condition of Centre West
 the preferred approach to splitting services, including mechanical, electrical, access
routes and formation of a new ‘end piece’ to the Plaza Mall
 potential other costs of separating assets
 the demolition 
 Burness Paull LLP was currently being procured as legal advisers to provide external
advice on:-
 the rights/obligations/liabilities the Council would inherit upon taking control
 the termination/relocation of the remaining occupier leases to ensure vacant
possession
 a project management team to lead the technical delivery of the project for elements such
as the demolition of Centre West 
The proposed approach, if endorsed, would be referred to the next meeting of the Executive
Committee for approval.  Thereafter, officers would commence the procurement of the external
professional team to advise on the transfer process over the course of the next 18 months.  It
was expected that the ownership of Centre West would be transferred by December
2025/January 2026.  The appointment of technical consultants would allow background work for
the demolition of the site to be prepared in tandem with the transfer process.  Demolition work
would then commence when ownership was transferred.
10

Page 11

It was proposed that the costs of the project would be met through Glasgow City Region City
Deal funding for East Kilbride, details of which were presented in a separate report to the
Committee.   
There would be significant risks if the Council did not agree to enter into a Heads of Terms with
Interpath and appoint a professional team of experts, and those were detailed in paragraph 10.2
of the report.   
Officers responded to members’ questions on various aspects of the report. 
The Committee decided: 
(1) that the position in relation to the administration of Centre West Shopping Centre, East
Kilbride and the associated risks to the Council be noted; 
(2) that entering into a Heads of Terms with Interpath for the transfer of Centre West Shopping
Centre, East Kilbride to South Lanarkshire Council be endorsed; 
(3) that the appointment of a professional team to manage the transfer of ownership of Centre
West Shopping Centre, East Kilbride to the Council, and the subsequent demolition of the
site, be endorsed; and 
(4) that the recommendations be referred to the Executive Committee for approval. 
The Committee recommended
to the Executive Committee:
that the proposed approach to ensure the smooth
handover of Centre West Shopping Centre, East Kilbride
to the Council be approved. 
[Reference: Minutes of the Executive Committee 13 September 2023 (Paragraph 6)] 
10 Glasgow City Region City Deal – Stewartfield Way – East Kilbride Town Centre 
A report dated 27 March 2024 by the Executive Director (Community and Enterprise Resources)
was submitted on the proposed next steps in developing and delivering the Stewartfield
Way/East Kilbride Town Centre Infrastructure project. 
The Stewartfield Way project was approved at the Executive Committee on 26 August 2015 as
one of the original 20 Glasgow City Region (GCR) City Deal projects.  Several iterations had
been considered since this approval and the Strategic Business Case had been updated
periodically in line with the governance arrangements of the City Deal.   
The challenges in delivering the original scheme, in terms of engineering challenges and
difficulties around land ownership, put the deliverability of that option in question.  Subsequent
updates had refined the project scope based on a public consultation in late 2019, and an
augmented Strategic Business Case had been approved by the Executive Committee on 10
March 2021 and, thereafter, by the GCR City Deal Cabinet in June 2021. 
To date, the project had focused on the transportation challenges across the town and how
improvements to the road and wider sustainable transport network could accelerate and unlock
development potential, improve access to existing facilities and improve journey times.  While
those issues remained at the heart of proposals, a refined approach was being considered
which brought together a combination of transportation improvements and direct town centre
interventions. 
The East Kilbride Town Centre Masterplan, which set out the strategic direction of the town
centre for the next 20 years, was approved by the Executive Committee on 13 September 2023.
11

Page 12

Delivery of the Masterplan was underway with officers working closely with representatives of
the town centre’s administrators and the Council’s professional advisers.  The Council would
require to directly deliver significant elements of the Masterplan, particularly in relation to Centre 
West and the development of a new ‘Civic Hub’ facility.  Endorsement for interventions in Centre
West was included in a separate report to the Committee. 
The current position was fully detailed at section 4 of the report and highlighted the economic
climate and the challenges facing the town since the City Deal projects had been established
and approved in 2015.  The key elements of the project, which reflected the approval of the
Executive Committee on 10 March 2021, were detailed at paragraph 4.4 of the report. 
It was proposed that the project be rescoped to be split into 2 component parts:- 
 delivering transportation improvements
 accelerating the town centre redevelopment infrastructure works 
As the rescoped project moved to the Outline Business Case (OBC) stage, a further report
would be brought to the Committee prior to submission to the GCR Programme Management
Office (PMO) in November 2024. 
The proposal was set out fully at section 5 of the report, whereby a report would be considered
by the City Deal Cabinet on 11 June 2024, following endorsement by this Committee and
subsequent approval by the Executive Committee, asking for permission to rescope the project
and to realign the approved project budget of £62.2 million.  The intention would be to direct £30
million to the Stewartfield Way Transport Infrastructure project and to direct £32.2 million to town
centre activity. 
The transportation infrastructure elements were at various stages of development and a delivery
timeline, including necessary planning approvals, was being developed, taking cognisance of
available resources and other infrastructure priorities.  The town centre work would be a major
project, requiring a level of resource that the Council did not have internally.  It was, therefore,
proposed that a project management led team be procured, as detailed in paragraph 5.3 of the
report. 
Detailed information of project development/delivery timelines and the proposed next steps was
provided in section 6 of the report.  A revised timeline was provided to progress through each
stage in both the approval process and on-site delivery.  Those timescales would be refined as
the project progressed through the business case process and the elements became more
defined.   
Officers responded to members’ questions on various aspects of the report. 
The Committee decided: 
(1) that the proposed next steps in developing the Outline Business Case (OBC) and
delivering the Stewartfield Way/East Kilbride Town Centre Infrastructure project be
endorsed and referred to the Executive Committee for approval; and 
(2) that a report be submitted to the GCR Programme Management Office, following
endorsement by this Committee and approval by the Executive Committee, to seek
permission to rescope the project and develop the OBC for a Stewartfield Way and East
Kilbride Town Centre project. 
The Committee recommended
to the Executive Committee:
that the proposed next steps in developing and
delivering the Stewartfield Way/East Kilbride Town
Centre Infrastructure project be approved. 
12

Page 13

[Reference: Minutes of the Executive Committee of 26 August 2015 (Paragraph 23), 10 March
2021 (Paragraph 10) and 13 September 2023 (Paragraph 6)] 
11 Glasgow City Region – Electric Vehicle Charging Infrastructure (EVCI)
Collaboration 
A report dated 26 March 2024 by the Executive Director (Community and Enterprise Resources)
was submitted:- 
 providing an update on the work being undertaken to develop a collaborative approach to
expanding the public electric vehicle charging infrastructure (EVCI) network across the 8
local authorities of the Glasgow City Region (GCR)
 seeking approval for the next steps required to progress towards a commercial delivery
arrangement 
In January 2022, the Scottish Government launched the Electric Vehicle Infrastructure Fund
(EVIF) which had the objective of unlocking private sector investment to expand the publicly
accessible charging network on local authority land and assets.  Transport Scotland had
engaged with the Scottish Futures Trust to support local authorities in the development of their
EVCI strategies and actively encouraged local authorities to collaborate with their strategies and
delivery activity to expand the charging network. 
In December 2021, the GCR Cabinet agreed to progress an initial report into current electric
vehicle charging provision, tariffs, and future forecast needs of the 8 GCR local authorities,
jointly funded using the EVIF allocations from Transport Scotland.  The report was concluded in
June 2022.  It was further agreed by the GCR Cabinet in August 2022 that the GCR Programme
Management Office (PMO) would engage consultants on behalf of the local authorities to
develop more detailed Strategy and Expansion Plans (SEP). 
Building upon the SEP, which was presented to the GCR Cabinet in May 2023, the GCR Electric
Vehicle Senior Officers’ Group was established, chaired by the Council’s Head of Roads,
Transportation and Fleet Services. The Senior Officers’ Group had senior officer representation
from each of the 8 GCR member authorities.  The Senior Officers’ Group had overseen a Prior
Information Notice (PIN), published in June 2023, to engage with Charge Point Operators
(CPOs) in order to:- 
 explore the market appetite
 provide information on GCR’s approach to the expansion of EVCI 
There was significant interest from the private sector and the clear preference expressed by
most CPOs was to engage collaboratively with all 8 GCR local authorities as part of a planned
and strategic approach.  In August 2023, the GCR Cabinet agreed that a collaboration between
the 8 local authorities to expand the EVCI network should be based on a clear set of agreed
principles, and those were detailed in paragraph 3.8 of the report. 
At the request of the GCR Chief Executives’ Group (CEG), further commercial and financial
analysis was undertaken during summer 2023 to gain a better understanding of the risks and
opportunities of the different commercial arrangements that local authorities could use to expand
the EVCI.  On 7 November 2023, the GCR Cabinet was advised of the conclusion of that stage
of work, and that the CEG’s preferred approach to progress was through a continued
collaboration among the 8 local authorities based on a concessionary-type commercial model. 
Collaborating to expand the EVCI infrastructure offered a range of benefits for the local
authorities’ wider policy objectives which were described in detail in section 4 of the report.
13

Page 14

Section 5 of the report provided detailed information on the potential shape of a GCR EVCI
collaboration.  Joint working and procurement options were detailed in section 6 of the report
and it was recognised that there was a need to have an Inter Authority Agreement (IAA) in place
to facilitate the collaboration.  There had been consensus that one local authority should
contract with a commercial partner on behalf of all 8 local authorities, with a preference for a
single procurement, rather than establishing a framework for local authorities to draw down
from. 
If the approach to progress the collaboration was approved, then the GCR PMO would work with
the EV Senior Officers’ Group to monitor the operational timeline for delivery of the project.  A
draft timeline for milestones was set out in paragraph 7.1 of the report.   
A pressing issue was Transport Scotland’s decision not to renew the Charge Place Scotland
(CPS) contract.  This would require all local authorities (and other chargepoint owners currently
using the CPS system) to put alternative arrangements in place for back-office and maintenance
of their chargepoints before December 2025.  The ambition of GCR to include the approximately
600 existing chargepoints included within the scope of the first lot brought with it a significant
risk that the timing of the new arrangement would fail to align with Transport Scotland’s ending
of the CPS service.  The GCR PMO was consulting closely with Transport Scotland to identify
potential mitigations for this risk.  The concession approach was a key opportunity for GCR to
deal with the requirement for a new back-office system for CPS. 
To allow the project to meet the proposed timeline, it was proposed that the Executive Director
(Community and Enterprise Resources), in consultation with the Head of Administration and
Legal Services, be authorised to progress the following:- 
 approval of the IAA
 issue of the tender documents
 approval of the preferred bidder and agreement to enter a contract 
All 8 local authorities would have to approve the proposed approach through their own local
governance structures prior to any contract being entered into.  A longer-term agreement
between the 8 GCR local authorities would be finalised at the point of entering a contract with a
commercial partner and would include the ongoing contract management arrangements.   
To support the development of the tender documents, site selection process and development
of the GCR EVCI proposal, GCR PMO would continue to provide support to the EV Senion
Officers’ Group.  Expert technical consultancy support would be engaged by the GCR PMO and
funded by contributions from each local authority through their allocations from Transport
Scotland EVIF.  Officer support groups would be established to provide expert advice and to
update their own organisations as required to ensure that each local authority was engaged in
the development process.  In addition to the existing EV Senior Officers’ Group, it would require
groups with a focus on legal, procurement and technical issues. 
The next steps that would be progressed, if the recommendations in the report were approved,
were detailed in section 9 of the report. 
The intention was to use Transport Scotland’s EVIF to meet the costs of the development of the
GCR proposal, development of the procurement documents, specialist legal advice, and other
costs associated with the development of the collaboration.  Each local authority would
contribute a portion of their grant award which would be pooled by the GCR PMO who would
engage the required consultancy and advice services on behalf of the 8 local authorities as
required.
14

Page 15

The main legal requirement would be the establishment of an IAA that allowed one local
authority to function as lead in the process to procure and contract with a commercial partner on
behalf of the other authorities.  There would be a requirement for expert external legal and
procurement advice to support the development of the GCR proposal and this would be
engaged by the GCR PMO.  A legal support group, consisting of solicitors from each of the 8
local authorities, would be established to support development of the project. 
Update reports would be presented to relevant committees as the project progressed and as
required throughout the development of the project. 
The Head of Roads, Transportation and Fleet Services responded to a member’s question in
relation to CPS and the likelihood of alternative arrangements being in place for back-office and
maintenance of chargepoints before December 2025. 
The Committee decided: 
(1) that the content of the report, and the collaborative work undertaken to date, be noted; 
(2) that the participation of South Lanarkshire Council in a collaborative procurement to
engage a commercial partner via a concession type contract through a partnership with all
8 local authorities in the GCR, to deliver the benefits set out in the report, be approved; 
(3) that it be agreed in principle, to enter an Inter Authority Agreement (IAA) among the 8 local
authorities, and that authorisation be given for the subsequent nomination of lead
authority, as well as procurement and commercial decisions relating to the commencement
and conclusion of the procurement process, to the Executive Director (Community and
Enterprise Resources), in consultation with the Head of Administration and Legal Services,
in line with the approach set out in the report; 
(4) that it be agreed that the GCR Programme Management Office (PMO), through Glasgow
City Council, would utilise available local authorities’ Electric Vehicle Infrastructure Fund
(EVIF) allocations to engage programme management and expert technical consultancy
support, that would assist in taking a GCR proposition to market and subsequent
appointment of a commercial partner; and 
(5) that it be noted that officers would provide update reports on the progress of the work to
relevant committees as required throughout the development of the project. 
[Reference: Minutes of the Climate Change and Sustainability Committee of 29 November 2023
(Paragraph 6)] 
12 South Lanarkshire Economic Strategy Update 
A report dated 28 March 2024 by the Executive Director (Community and Enterprise Resources)
was submitted providing an update on the delivery of the South Lanarkshire Economic Strategy
2022 to 2027. 
The South Lanarkshire Economic Strategy 2022 to 2027 was approved by the Executive
Committee on 30 November 2022.  The Economic Strategy, and associated Action Plan,
continued to respond to a rapidly changing economy at international, national and local levels. 
The Strategy was also increasingly influenced by a number of key economic policies and
emerging funding streams at UK Government, Scottish Government and City Region levels. 
A summary of the Economic Strategy 2022 to 2027 was provided at section 4 of the report and
this included the vision, key messages and the monitoring framework.
15

Page 16

This was the first report to the Committee providing an update on progress.  The key actions
and areas of activity were set out in the Strategy’s Action Plan, which was attached in Appendix
1 to the report.  The Action Plan detailed the priorities, outcomes, actions and how success was
being measured.  Although at the early stages of implementation, good progress was being
demonstrated across each of the themes and priorities. 
The Head of Enterprise and Sustainable Development Services responded to a member’s
question in relation to industrial property in East Kilbride, owned by private landlords, which
required substantial investment to meet market requirements.   
The Committee decided: that the progress in the delivery of the South Lanarkshire
Economic Strategy 2022 to 2027, and associated Action
Plan, be noted.  
[Reference: Minutes of the Executive Committee of 30 November 2022 (Paragraph 8) and
Minutes of 6 February 2024 (Paragraph 11)] 
13 South Lanarkshire Tourism Strategy - Update 
A report dated 28 March 2024 by the Executive Director (Community and Enterprise Resources)
was submitted providing an update on activity in the tourism sector during 2022/2023 and
2023/2024 following the launch of the South Lanarkshire Tourism Strategy 2022 to 2025. 
Tourism was a key sector in South Lanarkshire and it was, therefore, important to support and
nurture its growth.  The South Lanarkshire Tourism Strategy 2022 to 2025 was approved by the
Committee on 13 December 2022.  The Strategy, and associated Action Plan, took account of a
rapidly changing sector at international, national and local levels, and sat alongside the South
Lanarkshire Economic Strategy 2022 to 2027. 
Tourism was a key employer in South Lanarkshire, and in 2022 was responsible for:- 
 employing 3,483 full-time equivalent (FTE) jobs
 welcoming 1.46 million tourist visits
 generating £266 million within the local economy 
The tourism sector was still struggling to fully recover to pre-pandemic levels, with many
businesses not trading viably.  It had been intended that the Lanarkshire Economic Forum would
have been the Forum for partners to coordinate the delivery of the Action Plan.  Unfortunately,
that Forum was no longer operational.  The Tourism Officer in the Enterprise and Sustainable
Development Service had been actively pursuing many of the outlined actions, engaging in
consultations with specific businesses and groups on an individual basis to drive initiatives
forward. 
Updates on activity were provided in sections 4 and 5 of the report for activity in the tourism
sector during 2022/2023 and 2023/2024, respectively.  The next steps for 2024/2025 were
detailed in section 6 of the report.  A programme of financial support for 2024/2025 was
proposed from the UK Shared Prosperity Fund which would target digital projects such as web
booking and product development. 
The Committee decided: that the updates provided in sections 3 to 6 of the report be
noted. 
[Reference: Minutes of 13 December 2022 (Paragraph 7)] 
16

Page 17

14 Local Transport Strategy 2024 to 2034 - Update 
A report dated 28 March 2024 by the Executive Director (Community and Enterprise Resources)
was submitted providing an interim update on the progress towards the Local Transport Strategy
2024 to 2034. 
The current Local Transport Strategy had been published in 2013, presenting a 10-year vision
for transport in the local authority area.  A new Strategy, which would cover the period 2024 to
2034, was in the process of being developed.   
The new Strategy would set the future direction for the approach to the development and
upkeep of the transport infrastructure and policy within South Lanarkshire.  Transport policies
and actions were being developed alongside indicators to monitor progress on those actions. 
The Strategy would also set out how the Council would contribute to the delivery of the
obligations set out in the National and Regional Transport Strategies. 
The Strategy would be ambitious and forward thinking, developed in line with the national and
regional policy landscape, to develop sustainable, healthy and innovative transport opportunities
in South Lanarkshire over the next 10 years.  The Strategy would also take cognisance of
increasing global awareness of climate change, changes in travel patterns/activities and a
rapidly developing market in transport and travel technology.  Furthermore, the Strategy would
be used to influence the actions of a range of partner organisations who delivered aspects of
transport within South Lanarkshire.   
The key stages of development of the Strategy were detailed at paragraph 4.5 of the report, with
the final Strategy programmed to be completed and launched in late summer 2024.  Progress to
date in the development of the Strategy was detailed in section 5 of the report.  An internal peer
review was underway and was scheduled to be concluded at the end of May 2024.  The
finalised draft Strategy would then be shared with elected members and then to wider
stakeholder consultation for feedback.  The finalised draft Strategy would be presented to the
Committee for approval after the summer recess. 
The Committee decided: that the contents of the report be noted. 
[Reference: Minutes of the Enterprise Services Committee of 19 March 2013 (Paragraph 12)] 
15 Scottish Aggregate Tax - Consultation 
A report dated 28 March 2024 by the Executive Director (Community and Enterprise Resources)
was submitted on the Council’s response to the Scottish Government’s consultation on the
Aggregates Tax and Devolved Taxes Administration (Scotland) Bill. 
The Council, along with all other local authorities in Scotland, had been contacted by the
Scottish Parliament seeking a response to a consultation on a proposed Scottish Aggregates
Tax (SAT) Bill.  The proposed tax would replace the existing UK Aggregates Levy which was
applied to the use of primary aggregates used in road construction.  The tax would be applied at
the point of production, however, it was inevitable that consumers would be affected if the level
of taxation differed from the UK Aggregates Levy.  Any difference between Scottish and UK
taxation levels would create competitive advantages/disadvantages to aggregate producers,
particularly those closest to the Scotland/England border.   
If the SAT was implemented, then the block grant from the UK Government would be reduced in
line with the reduced aggregate taxation revenues.  The SAT would replace the UK Aggregates
Levy, with a devolved tax which was similar to the current UK tax in terms of its function and
operation.  There were, however, substantial costs to set up and administer the SAT, estimated
at between £3.385 million and £4.320 million until the end of the 2026/2027 financial year.  
17

Page 18

Whilst the financial memorandum had set out the scale of the costs, no detail was provided on
how those costs would be funded, or what level of additional cost each authority might be
expected to bear.  There was no information in the consultation papers on what the anticipated
benefits would be in Scotland or what the levels of taxation would be set at in comparison with
the rest of the UK. 
The consultation was issued on 11 December 2023 and a reply was requested by 9 February
2024.  The consultation questions, and the Council’s responses to those, were fully detailed at
section 4 of the report.  The Council’s response had been discussed with the Chair of the
Community and Enterprise Resources Committee prior to submission on 8 February 2024. 
Costs for the implementation of the SAT would be a clear consideration for the Council as the
proposed Bill progressed.  As detailed in the response, the Council was not confident that it
would meet any additional costs that would arise from the proposed arrangement.   
The Committee decided: 
(1) that the Council’s response to the SAT consultation be noted; and 
(2) that the implications of the introduction of the proposed SAT be noted. 
16 Urgent Business 
There were no items of urgent business. 
18

Page 19

Report
Agenda Item 
Report to: Community and Enterprise Resources Committee
Date of Meeting: 18 June 2024
Report by: Executive Director (Finance and Corporate Resources)
and Executive Director (Community and Enterprise
Resources)  
Subject: Community and Enterprise Resources – Workforce
Monitoring – March to April 2024 
1. Purpose of Report
1.1. The purpose of the report is to:-
[purpose]
 provide employment information for March to April 2024 relating to Community
and Enterprise Resources
[1purpose]
2. Recommendation(s)
2.1. The Committee is asked to approve the following recommendation(s):-
[recs]
(1) that the following employment information for March to April 2024 relating to
Community and Enterprise Resources be noted:- 
 attendance statistics;
 occupational health;
 accident/incident statistics;
 discipline, grievance and Dignity at Work cases;
 analysis of leavers and exit interviews;
 staffing watch as at 9 March 2024 
[1recs]
3. Background
3.1. As part of the Council’s performance management arrangements, regular workforce
monitoring reports are submitted to Committee.  This report for Community and
Enterprise Resources provides information on the position for March to April 2024. 
4. Monitoring Statistics
4.1. Attendance Statistics (Appendix 1) 
Information on absence statistics is analysed for the month of April 2024 for
Community and Enterprise Resources. 
The Resource absence figure for April 2024 was 6.3%, this figure has decreased by
0.9% when compared to last month and is 1.1% higher than the Council-wide figure. 
Compared to April 2023, the Resource absence figure has increased by 0.3%. 
Based on the absence figures at April 2024 and annual trends, the projected annual
average absence for the Resource for 2024/2025 is 6.3%, compared to a Council-
wide average figure of 5.2%.   
3
19

Page 20

Managers follow the procedures outlined in the Maximising Attendance Policy to
support employees to remain at work, or to return to work after a sickness absence. 
There are comprehensive employee supports in place and additionally, Personnel
Services work in close partnership with line managers and Resource Management
Teams on a case management basis to ensure that appropriate actions are taken. 
4.2. Occupational Health (Appendix 2) 
In terms of referrals to occupational health, which include medical examinations and
physiotherapy, overall, 207 referrals were made this period.  This represents a
decrease of 3 when compared with the same period last year.   
4.3. Accident/Incident Statistics (Appendix 2) 
There were 35 accidents/incidents recorded within the Resource this period, an
increase of 5 when compared to the same period last year. 
4.4. Discipline, Grievance and Dignity at Work (Appendix 2) 
During the period, 24 disciplinary hearings were held within the Resource, a
decrease of 7 when compared to the same period last year.  During the period 2
appeals were heard by the Appeals Panel, this figure has increased by 2 when
compared to the same period last year.  Two Appeals Panels were pending, this
figure has increased by 2 when compared to the same period last year.  One
grievance hearing was raised within the Resource, this figure has increased by 1
when compared to the same period last year.  No Dignity at Work complaints were
raised within the Resource, this figure remains unchanged when compared to the
same period last year. 
4.5. Analysis of Leavers (Appendix 2) 
There were a total of 26 leavers in the Resource this period eligible for an exit
interview. This figure has decreased by 3 when compared with the same period last
year.  Seven exit interviews were conducted in this period, this figure remains
unchanged when compared to the same period last year. 
4.6. When processing an employee termination, managers were asked to identify
whether they intended to replace the employee who had left the Council.  If they
indicated that they did not intend to replace the employee, they were asked to select
from the following options:- 
 plan to hold for savings
 fill on a fixed term basis pending savings
 transfer budget to another post
 end of fixed term post 
4.7. Appendix 2a provides a breakdown of vacant posts and whether these are being
replaced or held for savings. In the period March to April 2024, 70 employees (37.14
FTE) in total left employment, managers indicated that 66 posts (33.98 FTE) were
being replaced and 4 posts (3.16 FTE) were due to the end of fixed term contracts. 
5. Staffing Watch 
5.1. There has been a decrease of 121 in the number of employees in post from 9
December 2023 to 9 March 2024. 
6. Employee Implications
6.1. There are no implications for employees arising from the information presented in
this report.
20

Page 21

7. Financial Implications
7.1. All financial implications are accommodated within existing budgets. 
8. Climate Change, Sustainability and Environmental Implications
8.1. There are no Climate Change, Sustainability and Environmental Implications in terms 
of the information contained within this report. 
9. Other Implications
9.1. There are no implications for sustainability or risk in terms of the information
contained within this report. 
10. Equality Impact Assessment and Consultation Arrangements
10.1. This report does not introduce a new policy, function or strategy or recommend a
change to an existing policy, function or strategy and, therefore, no impact
assessment is required. 
10.2. There was no requirement to undertake any consultation in terms of the information
contained in this report. 
Jackie Taylor
Executive Director (Finance and Corporate Resources) 
David Booth
Executive Director (Community and Enterprise Resources) 
10 May 2024 
Link(s) to Council Values/Priorities/Outcomes
 Accountable, effective, efficient and transparent
 Fair, open and sustainable
 Ambitious, self aware and improving
 Excellent employer
 Focused on people and their needs
 Working with and respecting others 
Previous References
 Community and Enterprise Resources – 6 February 2024 
List of Background Papers
 Monitoring information provided by Finance and Corporate Resources 
Contact for Further Information
If you would like to inspect the background papers or want further information, please
contact:-
Elaine Maxwell, HR Business Manager
Ext:   (Tel: 01698 454647)
E-mail:  Elaine.Maxwell@southlanarkshire.gov.uk 
21

Page 22

2022 /
2023
2023 /
2024
2024 /
2025
2022 /
2023
2023 /
2024
2024 /
2025
2022 /
2023
2023 /
2024
2024 /
2025
2022 /
2023
2023 /
2024
2024 /
2025
% % % % % % % % % % % %
April 4.4 3.6 3.2 April 7.3 6.3 6.8 April 6.9 6.0 6.3 April 5.6 5.1 5.2
May 3.9 3.7 May 6.8 6.3 May 6.3 5.9 May 5.4 5.1
June 3.5 4.3 June 7.2 5.9 June 6.7 5.7 June 5.3 4.7
July 3.9 2.3 July 5.9 4.6 July 5.6 4.3 July 4.6 3.8
August 3.4 3.0 August 6.6 5.2 August 6.1 4.9 August 4.4 4.1
September 3.1 2.5 September 7.9 7.1 September 7.1 6.4 September 5.4 5.3
October 5.1 2.0 October 7.5 7.0 October 7.1 6.3 October 5.8 5.1
November 4.2 2.6 November 8.3 8.1 November 7.7 7.3 November 6.5 6.2
December 3.7 3.0 December 8.8 7.5 December 8.0 6.8 December 7.0 6.6
January 2.6 3.6 January 7.4 7.4 January 6.7 6.9 January 5.8 6.1
February 3.6 4.0 February 7.4 7.8 February 6.9 7.2 February 5.9 6.4
March 3.9 3.2 March 7.9 7.9 March 7.3 7.2 March 6.4 6.3
Annual Average 3.8 3.2 3.2 Annual Average 7.4 6.8 6.8 Annual Average 6.9 6.2 6.3 Annual Average 5.7 5.4 5.2
Average Apr-Mar 3.8 3.2 3.2 Average Apr-Mar 7.4 6.8 6.8 Average Apr-Mar 6.9 6.2 6.3 Average Apr-Mar 5.7 5.4 5.2
524 2926 3450 16192
Appendix 1
Absence Trends - 2022/2023, 2023/2024 & 2024/2025
Community and Enterprise Resources
APT&C Council WideManual Workers Resource Total
No of Employees at 30 April 2024 No of Employees at 30 April 2024 No of Employees at 30 April 2024 No of Employees at 30 April 2024
22

Page 23

COMMUNITY AND ENTERPRISE RESOURCES
Mar - Apr Mar - Apr
2023 2024
MEDICAL EXAMINATIONS
Number of Employees Attending
EMPLOYEE COUNSELLING SERVICE
Total Number of Referrals
PHYSIOTHERAPY SERVICE
Total Number of Referrals
REFERRALS TO EMPLOYEE SUPPORT OFFICER 46 63
REFERRALS TO COGNITIVE BEHAVIOUR THERAPY 0 0
TOTAL 210 207
Mar - Apr Mar - Apr
2023 2024
Specified Injuries* 1 0
Over 7 day absences 5 4
Minor 12 14
Near Miss 8 7
Violent Incident:  Physical**** 4 8
Violent Incident:  Verbal***** 0 2
Total Accidents/Incidents 30 35
Mar - Apr Mar - Apr
2023 2024
Total Number of Hearings 31 24
Total Number of Appeals 0 2
Appeals Pending 0 2
Time Taken to Convene Hearing March to April 2024
0-3 Weeks 4-6 Weeks Over 6 Weeks
20 2 2
Mar - Apr Mar - Apr
2023 2024
Number of Grievances 0 1
Still in Progress 0 1
Mar - Apr Mar - Apr
2023 2024
Number of Incidents 0 0
Mar - Apr Mar - Apr
2023 2024
Career Advancement 4 3
Poor Relationship with Manager/Colleagues 1 0
Personal Reasons 1 1
Childcare/caring responsibilities 0 1
Dissatisfaction With Terms and Conditions 0 1
Other 1 1
Number of Exit Interviews conducted 7 7
Total Number of Leavers Eligible for Exit Interview 29 26
Percentage of interviews conducted 24% 27%
****Physical violent incidents and ***** Verbal Violent Incidents are included in the "Over 3-day or
Over 7-day" figures, where applicable, to provide the "Total Over 3-day or Over 7-day" figures.
****Physical Violent Incidents and ***** Verbal Violent Incidents are included in the "Minor" figures,
where applicable, to provide the "Total Minor" figures.
ANALYSIS OF REASONS FOR LEAVING
RECORD OF DISCIPLINARY HEARINGS
RECORD OF GRIEVANCE HEARINGS
RECORD OF DIGNITY AT WORK
CAUSE OF ACCIDENTS/INCIDENTS
70
*A Specified Injury is any fracture (other than to the fingers, thumbs or toes), amputation, loss of
sight, serious burns, crushing injury, scalping, loss of consciousness caused by asphyxiation/ head
injury, a chemical or hot metal burn to the eye or penetrating injury as defined by the HSE.
**Over 3 day / over 7day absence is an injury sustained outwith specified injury category that results
in a period of absence of absence as defined by the HSE. 
***Near Miss - Any unexpected, unplanned occurrence (except Dangerous Occurrences) that does
not lead to injury of persons, damage to property, plant or equipment but may have done so in
different circumstance.
****Physical violent incidents are included in the "Specified" figures, where applicable, to provide the
"Total Specified" figures.
58
APPENDIX 2
83 86
11 0
23

Page 24

FTE* H/C** FTE H/C FTE H/C
Terminations/Leavers 14.90 32 322.89 509 337.79 541
Being replaced 11.74 28 260.22 441 271.96 469
Filled on fixed term basis 0.00 0 3.63 5 3.63 5
Plan to transfer this budget to another post 0.00 0 0.00 0 0.00 0
End of fixed term contract 3.16 4 54.58 57 57.74 61
Held pending service Review 0.00 0 4.46 6 4.46 6
Plan to remove for savings 0.00 0 0.00 0 0.00 0
* Full time equivalent
** Head count/number of employees
FTE* H/C** FTE H/C
Terminations/Leavers 22.24 38 22.24 38
Being replaced 22.24 38 22.24 38
Filled on fixed term basis 0.00 0 0.00 0
Plan to transfer this budget to another post 0.00 0 0.00 0
End of fixed term contract 0.00 0 0.00 0
Held pending service Review 0.00 0 0.00 0
Plan to remove for savings 0.00 0 0.00 0
* Full time equivalent
** Head count/number of employees
Apr 2023 - Feb 2024
Apr-24 Cumulative total
Appendix 2a
Mar-24 Reconciliation figure Cumulative total
24

Page 25

As at 9 March 2024
Total Number of Employees
F/T P/T F/T P/T
1112 273 198 1410
Chief Officer Grade 1 Grade 2 Grade 3 Grade 4 Grade 5 Grade 6 Fixed SCP Teacher TOTAL
5.00 1412.35 348.58 244.59 43.55 15.30 0.00 5.00 0.00 2074.37
As at 9 December 2023
Total Number of Employees
F/T P/T F/T P/T
1222 269 202 1421
Chief Officer Grade 1 Grade 2 Grade 3 Grade 4 Grade 5 Grade 6 Fixed SCP Teacher TOTAL
5.00 1514.30 359.98 244.18 44.05 15.70 0.00 5.00 0.00 2188.21
Appendix 3
JOINT STAFFING WATCH RETURN
COMMUNITY AND ENTERPRISE RESOURCES
*Full - Time Equivalent No of Employees
Salary Bands
2993
MALE FEMALE TOTAL
*Full - Time Equivalent No of Employees
Salary Bands
MALE FEMALE TOTAL
3114
25

Page 26

26

Page 27

Report
Agenda Item 
Report to: Community and Enterprise Resources Committee
Date of Meeting: 18 June 2024
Report by: Executive Director (Community and Enterprise
Resources)  
Subject: Community and Enterprise Resource Plan - Quarter 4
Progress Report 2023/2024 
1. Purpose of Report
1.1. The purpose of the report is to:-
[purpose]
 provide the Community and Enterprise Resource Plan Quarter 4 Progress
Report 2023/2024, for the period 1 April 2023 to 31 March 2024.
[1purpose]
2. Recommendations
2.1. The Committee is asked to approve the following recommendations:- 
(1) that the Community and Enterprise Resource Plan Quarter 4 Progress Report
2023/2024, as summarised in paragraph 5.2 and attached as Appendix 2 of
this report, be noted;
(2) that the key achievements made by the Resource, as detailed in paragraph
5.3. of the report, be noted
(3) that the areas for improvement and associated management actions, as
detailed in paragraph 5.4 of the report, be noted; and
(4) that the additional scrutiny of changes in BRAG status between Quarter 2 and
Quarter 4, as summarised at paragraph 5.5 and detailed at Appendix 3 of the
report, be noted. 
3. Background
3.1. The Community and Enterprise Resource Plan 2023/2024 was approved by the
Community and Enterprise Resources Committee on 30 May 2023, and
subsequently noted by the Executive Committee on 21 June 2023. The Plan sets out
the strategic outcomes and actions to be managed and delivered by the Resource
for the financial year 2023/2024.   
3.2. The Resource Plan follows the agreed corporate structure and style. The Plan is a
key element of the Council’s performance management arrangements and provides
details of the context within which the Resource operates and establishes actions
and measures for the year ahead based on the outcomes set out in the Council Plan
Connect 2022 to 2027. 
4. Resource Outcomes 2023/2024
4.1. The Resource has established a number of outcomes to support the delivery of the
Connect Outcomes in 2023/2024. These are detailed at Appendix 1.
4
27

Page 28

5. Quarter 4 Progress Report 2023/2024
5.1. Progress against all Resource Plan measures is contained in the Quarter 4 Progress
Report 2023/2024, attached as Appendix 2.  This report has been produced from the
Council’s performance management reporting system IMPROVe, and uses a traffic
light format with the following definitions to give a status report on each measure:-  
Status Definition
Blue Project complete
Green The timescale or target has been met as per expectations
Amber There has been minor slippage against timescale or minor shortfall
against target
Red There has been major slippage against timescale or major shortfall
against target
Report
later
The information is not yet available to allow us to say whether the
target has been reached or not.  This will be reported when available
Contextual Included for ‘information only’, to set performance information in context 
5.2. The overall summary of progress to date is as follows:- 
Status Measures
Statistical Project Number %
Blue 0 13 13 23.2%
Green  12 17 29 51.8%
Amber  3 7 10 17.8%
Red  3 0 3 5.4%
Report later/Contextual 1 0 1 1.8%
Totals  19 37 56 100.0% 
(Data correct as at 8 May 2024) 
5.3. Key achievements for 2023/2024, are noted below:-  
5.3.1.
Connect Outcome Our Economy
Resource Outcome Achievement
Economic development and
growth in South Lanarkshire
is fair, inclusive, sustainable
and low carbon  
A new South Lanarkshire Social Enterprise
Strategy was approved by Executive Committee
on 21 June 2023. The Strategy sets out the
Council’s commitment to increase the number of
social enterprises and improve the sustainability
of the sector in South Lanarkshire.
A seminar proposing new priorities and changes
to the Renewable Energy Fund (REF) was given
to the Rural Task Force on 2 October 2023 and a
final paper taken to the Rural Task Force on 15
November 2023. The proposals were taken to
Community and Enterprise Resources Committee
in February 2024 and the strategic aims for the
REF to address over 5 years were approved.
28

Page 29

Connect Outcome Our Economy
Resource Outcome Achievement
South Lanarkshire is an
attractive place to start, grow
and locate a business
The number of jobs created or sustained per
annum, and the increased value of sales
generated by businesses, as a direct result of
Economic Development intervention exceeded
the targets set. 646 jobs were created or
sustained, and increased sales derived
exclusively from additional sales through
Business Support Grants amounted to £14.496
million.  
Programmes aimed at developing the skills of
business owners, and the growth of businesses in
the following sectors have been delivered during
2023/2024: Construction, Social Economy,
Tourism, and Food and Drink. 
Connect Outcome Communities and Environment
Resource Outcome Achievement
All roads, footways, cycle
routes, bridges and
associated infrastructure are
safe and fit for purpose
Casualty reduction measures have been
introduced at the following locations:
A749, East Kilbride Road – new warning signage
and road markings
A73 Braidwood – new signs and road markings
A73 Bogside to Carluke – alterations to junctions
at Wildman Road and Law Hospital
A73 – application of high friction surfacing north
of Hyndford Bridge
In addition to the above, general signing, lining
and catseye improvements were completed on
the A721, A70 and A706.
Communities are encouraged
and supported to reduce, re-
use and recycle their waste
During 2023, 1.5% of household waste was sent
to landfill, which is significantly below (better than)
the target of 10%.
The Council addresses
climate change by reducing
carbon emissions, protecting
our natural environment,
adapting to the impacts of
climate change, and acting
sustainably
The Climate Emergency Community Grants fund
was re-launched in April 2023 and has once
again proven to be a big success, with the
£75,000 fully committed by the end of June 2023.
A further £150,000 from Shared Prosperity Fund
has been allocated for climate emergency
community grants in 2024/2025.  A full report on
the overall impact of the Climate Community
Grants will be presented to the Climate Change
and Sustainability Committee at the beginning of
2025.
The Office for Zero Emission Vehicles (OZEV)
Project has resulted in the installation of 13 dual
on-street electric vehicle chargers in various
residential streets in South Lanarkshire.
Protect, enhance and respect
South Lanarkshire’s natural
environment
A new Biodiversity Strategy (2024 to 2030) was
developed along with a Biodiversity
Implementation Plan (2024 to 2030) during
2023/2024 and both approved by the Climate
29

Page 30

Connect Outcome Communities and Environment
Resource Outcome Achievement
Change and Sustainability Committee on 28
February 2024. 
Connect Outcome Communities and Environment
Resource Outcome Achievement
The Council supports and
promotes a fairer, healthier,
and more sustainable food
system. 
As part of our efforts to identify opportunities to
increase food growing provision throughout South
Lanarkshire, planning permission was applied for
a new allotment site at Chatelherault and
planning consent was granted.  Works started in
April 2023 and were completed in August 2023. 
All the plots have now been let with the site fully
operational.
High quality streets, parks
and other public areas
ensures South Lanarkshire is
a place where people want to
live, work, visit and invest
Strathaven, Castlebank and Cambuslang Parks
have successfully retained Green Flag status in
2023.  Strathaven Park has won the prestigious
award from Keep Scotland Beautiful for the 11th
year in a row, while Cambuslang Park and
Castlebank Park have won for nine and eight
consecutive years respectively. Recognising the
very best of our country’s outdoor areas, the
International Green Flag Award acts as a
benchmark for clean, safe and well-maintained
parks and green spaces. 
Road and transportation
infrastructure supports new
development, enables use of
public transport and
encourages active travel
A number of cycling and walking projects
progressed during 2023/2024 including:
Active Travel Studies completed for towns such
as Blackwood, Kirkmuirhill, Abington, Crawford,
Carnwath, Forth and Biggar.
Development of a segregated cycle network with
enhanced pedestrian facilities in East Kilbride is
now complete on Churchill Avenue, linking West
Mains Road to Cornwall Street and towards the
trunk road network on the A726.
Locations for cycle shelters and parking stands in
schools have been identified and funding
awarded by Cycling Scotland, works will be
undertaken in early summer 2024. 
Connect Outcome Health and Wellbeing   
Resource Outcome Achievement
Health inequalities are
addressed through
collaboration with local
communities and partners
The Shaping Places for Wellbeing project has
enabled a range of services and partners to come
together to understand the factors that are
affecting health inequality in Rutherglen.
Extensive health data has been analysed and
developed into data profiles for the main
settlements in South Lanarkshire. This will form a
significant element of the Local Development
Plan 3 (LDP3) evidence report as well as other
council strategies and action plans.
30

Page 31

Connect Outcome Health and Wellbeing   
Resource Outcome Achievement
All residents have the
opportunity to access cultural,
leisure and outdoor
recreational activities to help
improve their wellbeing and
quality of life
Implementation of the multi-year Play Area
Investment Programme is well underway with
consultation undertaken for Larkhall, Rutherglen
and Cambuslang with local members and young
people. The contract for the play areas in Larkhall
identified for refurbishment has been awarded
and works have started on site. 
5.3.2. In addition to working towards these Outcomes, it is recognised that the Council will
continually aim to improve and ensure effective and efficient use of resources, and
that business will be conducted with integrity and transparency and will operate to
the highest standards.  In order to monitor and report progress against these values,
Resource outcomes have also been identified under the heading Delivering the Plan
and achieving Best Value. 
Delivering the Plan and achieving Best Value
Resource
Objective
Achievement 
Customers
experience high
quality and
improving council
services 
A new Cemetery Strategy was approved at Community and
Enterprise Resources Committee in May 2023 to allow the
service to take forward and develop new working
arrangements within Bereavement Services. 
5.4. Areas for improvement
Three measures were classified as “red” (major slippage against timescale or
shortfall against target). These are detailed below, together with the reason why, and
the management action being taken. 
Communities and Environment 
Resource Outcome:   Communities are encouraged and supported to reduce,
re-use and recycle their waste
Measure  Comments/Progress Action by Manager 
Percentage of total
household waste
that is recycled
The Household Recycling
Rate for January to
December 2023 was 43.75%.
This remains below the target
of 50%. 
The new bulky waste
contract commenced on 1
April 2022, and continues to
increase the quantities of
bulky waste being recycled,
as evidenced by the
increase from 2022 (41.2%)
to 2023 (43.75%).
Performance will continue to
be closely monitored. 
31

Page 32

Communities and Environment 
Resource Outcome:   All roads, footways and bridges and associated
infrastructure are safe and fit for purpose
Measure  Comments/Progress Action by Manager 
Percentage of our
road network that
should be
considered for
maintenance
treatment
This figure is derived from the
Society of Chief Officers of
Transportation in Scotland
(SCOTS) Road Condition
Index (RCI) survey. The
survey has now been
completed and the overall
RCI is 31.9% for 2022 to
2024. This falls short of the
target of 30.8% and indicates
a regression of 1.1% of the
amount of our road network
in an amber or red status.
Deterioration is also showing
across individual road
categories to a similar extent.
The Service is currently
preparing the annual Roads
Asset Management Plan
(RAMP) update for 2024 to
reflect the most recent data
and this will be reported to
committee later this year. 
Budgetary as well as
inflationary pressures
impacts on the ability to
improve the condition of our
assets; and whilst there has
been an increase in capital
funding for this financial
year, this is being used to
help balance the reduction
in the revenue budget which
provides the Service with its
day-to-day funding to help
maintain the network in a
safe and serviceable
condition. The Service will
continue to inspect routes
on a regular basis and
identify priorities within
available budgets. 
Our Economy 
Resource Outcome:  South Lanarkshire is an attractive place to start, grown and
locate a business
Measure  Comments/Progress Action by Manager 
Number of
business support
interventions per
annum by
Economic
Development
(grants, loans or
advice)
The Business Support
service supported 829
businesses during
2023/2024, significantly lower
than the target of 1,200.
There are a number of
contributing factors that have
led to the reduction in the
number, including that the
Business Growth Grant did
not open until August 2023
and there were fewer face to
face events this year e.g. no
business exhibitions or ‘meet
the real buyer’ events.  
The Business Support team
has been impacted by
reduced resources, in
particular a reduction in the
number of staff within the
team. For 2024/2025, the
targets will need to be
reviewed in line with the
reduced resources available
within the team. The
Business Gateway Service
has been taken into North
Lanarkshire Council. This
provides opportunities to
review how the Council
supports businesses and
32

Page 33

Our Economy 
Resource Outcome:  South Lanarkshire is an attractive place to start, grown and
locate a business
will also be a factor in a
review of targets. 
5.5. Scrutiny of changes in BRAG status 
A further analysis introduced to aid scrutiny of performance, is to highlight and
explain all measures that have changed status from Quarter 2 to Quarter 4. On
analysis of these, seven measures show a decline in performance and details of
these seven measures are included at Appendix 3. The remaining measures under
scrutiny changed to Green or to Blue (complete) and need no further action. It should
be noted that the measures with a ‘report later’ status at Quarter 4 will be followed up
and reported on in the 2024/2025 Quarter 2 Community and Enterprise Resource
Plan progress report. 
5.6. Report Later/Contextual 
Measures in the quarterly progress report which are not red, amber, green or blue
can be assigned a status of ‘report later’ or ‘contextual’. At quarter four, there was
one measures with a ‘report later’ status; the percentage of procurement spend on
local enterprises isn’t available to report on until the figures are released by the
Improvement Services, and this is not expected until July/August 2024. This will be
reported in future progress update reports, as noted at 5.5. 
6. Employee Implications
6.1. The outcomes noted within the Resource Plan will inform the Service Action Plans,
where applicable, and in turn the Performance Appraisal process for individual
employees. 
6.2. Absence statistics are monitored and reported through the Council-wide workforce
monitoring report which is presented to each Resource Committee and the
Employees Issues Forum. The absence rate for Community and Enterprise
Resources from April 2023 to March 2024 was 6.2%, which is higher than the
Council-wide figure of 5.4%, however, it is less than the figure for 2022/23 (6.9%). 
7. Financial Implications
7.1. The outcomes within the Resource Plan are reflected in the respective annual
Resource Revenue and Capital budgets and, longer term, within the framework of
the Council’s approved Financial Strategy. 
8. Climate Change, Sustainability and Environmental Implications
8.1. There are no climate change or environmental implications as a result of this report,
however, a number of actions within the Resource and Service Plans contribute
positively to the Council’s Sustainable Development and Climate Change Strategy. 
8.2. The Resource Plan takes into account the Resource’s responsibilities in relation to
sustainable development and climate change. 
9. Other Implications
9.1. The Community Plan 2022 to 2032 was agreed at the Community Planning
Partnership Board on 22 June 2022.  A significant element of the delivery of the
outcomes in the Community Plan will come through the achievement of the
outcomes and actions contained within Connect.
33

Page 34

9.2. Resource Plan actions are assessed as part of the Resource’s risk management
arrangements and relevant issues have been added to the Resource Risk Register. 
10. Equality Impact Assessment and Consultation Arrangements
10.1. Many of the actions detailed within the Resource Plan reflect ongoing strategies and
policies which will be or have been the subject of consultation and equality impact
assessment. 
David Booth
Executive Director (Community and Enterprise Resources) 
28 May 2024 
Link(s) to Council Values/Priorities/Outcomes
Values
 Focused on people and their needs
 Working with and respecting others
 Accountable, effective, efficient and transparent
 Ambitious, self-aware and improving
 Fair, open and sustainable
 Excellent employer
Priorities
 We will work to put people first and reduce inequality
 We will work towards a sustainable future in sustainable places
 We will work to recover, progress and improve
Outcomes
 Our children and young people thrive
 Good quality, suitable and sustainable places to live
 Thriving business, fair jobs and vibrant town centres
 Caring, connected, sustainable communities
 People live the healthiest lives possible
 Inspiring learners, transforming learning, strengthening partnerships 
Previous References
 Community and Enterprise Resources Quarter 2 Progress Report 2023-24: Community
and Enterprise Resources Committee 6 February 2024 
List of Background Papers
 Council Plan Connect 2022 to 2027 - approved by the full Council on 15 June 2022
 Community and Enterprise Resources Plan 2023/2024 – approved by the Community
and Enterprise Resources Committee on 30 May 2023, and noted by the Executive
Committee on 21 June 2023 
Contact for Further Information
If you would like to inspect the background papers or want further information, please
contact:-
Anne Lewis (Performance and Development Officer)
E-mail:  anne.lewis@southlanarkshire.gov.uk
34

Page 35

Appendix 1
Community and Enterprise Resource Outcomes 2023/2024   
Connect Outcomes Resource Outcomes  
Communities and
Environment 
• High-quality streets, parks and other public areas
ensures South Lanarkshire is a place where people want
to live, work, visit and invest
• Communities are encouraged and supported to reduce,
re-use and recycle their waste
• The Council addresses climate change by reducing
carbon emissions, protecting our natural environment,
adapting to the impacts of climate change, and acting
sustainably
• The Council supports and promotes a fairer, healthier,
and more sustainable food system 
• All roads, footways, cycle routes, bridges and associated
infrastructure are safe and fit for purpose
• Road and transportation infrastructure supports new
development, enables use of public transport and
encourages active travel
Education and Learning  • No resource outcomes for this priority 
Health and Wellbeing  • Public health is safeguarded through an effective
environmental regulation and enforcement service
• All school and nursery children have access to nutritious
school meals 
• All residents have the opportunity to access cultural,
leisure and outdoor recreational activities to help improve
their wellbeing and quality of life
Children and Young
People 
• No resource outcomes for this priority 
Housing and Land  • Vacant, derelict and contaminated land is brought back
into productive use
Our Economy  • Our economy is fair, inclusive, sustainable and low
carbon, with thriving town and neighbourhood centres
which provide a focal point for local communities 
• South Lanarkshire is an attractive place to start, grow
and locate a business
• Physical development and land use in the area is
enabled, guided and controlled to help facilitate
economic growth  
• Consumers and communities are protected through an
effective trading standards service 
Delivering the Plan and
achieving Best Value
• Customers experience high quality and improving
Council services
• The Council demonstrates high standards of governance
and sound financial stewardship
• The workforce has the skills, flexibility and capacity to
deliver the Council’s priorities
• Digital and ICT services meet the needs of the Council
and its customers 
35

Page 36

36

Page 37

IMPROVe - SLC Performance Management System Report printed on 14 May 16:02
Quarter 4 : April 2023 - March 2024
South Lanarkshire Council
Community and Enterprise
Resource Plan
(This represents the cumulative position to March 2024)
Performance Report 2023-24
Appendix 2
4
37

Page 38

IMPROVe - SLC Performance Management System                                                                                                                  Report printed on 14 May 16:02
Summary - number of measures green, amber and red under each Council Plan Outcome /
Theme
Council Outcome/ Theme Green Amber Red Report later /
Contextual
Total
Communities and Environment 5 2 2 0 9
Education and Learning 0 0 0 0 0
Health and Wellbeing 3 0 0 0 3
Children and Young People 0 0 0 0 0
Housing and Land 0 0 0 0 0
Our Economy 4 1 1 1 7
Delivering the plan and achieving best value 0 0 0 0 0
Total 12 3 3 1 19
Page 1
38

Page 39

IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
Communities and Environment
High-quality streets, parks and other public areas ensures South Lanarkshire is a place where people want to live, work, visit and invest
Performance Indicators Comments/ Progress Status 2021/22 2022/232020/21Target To Date
-------- Last 3 Years ------------------- This Year -----------
Percentage of streets found to be
acceptable during Litter Monitoring
Systems Surveys
Percentage of streets found to be acceptable via Litter Monitoring
Systems Surveys is 92% meeting the target for the year.
Green 92.00% 92.00% 94.10% 92.10% 92.30%
Land Audit Management System grounds
maintenance score
The Land Audit Management System (LAMS) maintenance score at year
end has met the annual target.
Green 72.0 72.0 72.0 71.3 72.0
Communities are encouraged and supported to reduce, re-use and recycle their waste
Performance Indicators Comments/ Progress Status 2021/22 2022/232020/21Target To Date
-------- Last 3 Years ------------------- This Year -----------
Percentage of total household waste that is
recycled in 2023
This measure is reported per calendar year. The year to date figure to
the right reflects performance from January to December 2023
(43.75%).  This remains below the target of 50%.
Performance in October to December 2023 (38.71%) was an
improvement on the same quarter in 2022 (37.75%).
The new bulky waste contract continues to increase the quantities of
bulky waste being recycled. Performance will continue to be closely
monitored.
Red 50.00% 43.75% 40.50% 41.50% 41.20%
Percentage of household waste sent to
landfill in 2023
This measure is reported per calendar year and the latest figures relate
to the period from January to December 2023  (1.50%).  This remains
well below the target to stay under 10%.
Performance in October to December 2023 (1.61%) is lower  (better)
than the same quarter in 2022 (2.07%).
Green 10.00% 1.50% 9.71% 8.66% 1.84%
Page 2
39

Page 40

IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
Communities and Environment
The council addresses climate change by reducing carbon emissions, protecting our natural environment, adapting to the impacts of climate change, and actingsustainably
Performance Indicators Comments/ Progress Status 2021/22 2022/232020/21Target To Date
-------- Last 3 Years ------------------- This Year -----------
Reduction in the council’s carbon
emissions achieved by March 2024
(buildings, waste, street lighting, transport)
The council's carbon emissions reduced by 20% in 2022-23 compared
to 2019-20. The reduction is partly due to the national carbon
conversions factors for electricity, gas and waste which are significantly
lower than the 2019-20 factors. It is also due to the significant reduction
in the emissions associated with the household waste collection, as
there has been a reduction in the amount of waste going to landfill. The
figures for financial year 2023-24 will be available later in 2024.
Green ------ ------ ------ ------ 20.0%
Communities are well connected
Performance Indicators Comments/ Progress Status 2021/22 2022/232020/21Target To Date
-------- Last 3 Years ------------------- This Year -----------
Percentage of properties with Superfast
Broadband >30Mbps
Progress towards target is slow with 0.09% increase in quarter four,
however the year to date figure remains high at 97.9% just over one
percent less than the 99% target. Progress is dependent on BT
Openreach investment. Alternative solutions such as Starlink satellite
availability may affect this target.
It should be noted that coverage increases in Full Fibre continue at a
more rapid level than expected and investment is dependent on market
conditions.
Amber 99.0% 97.9% 96.6% 97.0% 97.3%
Percentage of properties with Full Fibre
Connection
Investment in Full Fibre connection to households continues within
urban and rural towns with a 2.27%  increase in coverage in quarter
four. This takes the percentage of residential properties that can access
Full Fibre in South Lanarkshire to 45.43%, well above the target (33%).
Green 33.0% 45.4% 13.8% 21.9% 32.6%
Page 3
40

Page 41

IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
Communities and Environment
All roads, footways and bridges and associated infrastructure are safe and fit for purpose
Performance Indicators Comments/ Progress Status 2021/22 2022/232020/21Target To Date
-------- Last 3 Years ------------------- This Year -----------
Percentage of our road network that should
be considered for maintenance treatment
This figure is derived from the Society of Chief Officers of Transportation
in Scotland (SCOTS) Road Condition Index (RCI) survey which is
undertaken each year.
The target figure of 30.8% is based on the results for the period
2021-23.
The revised figure for 2022-24 at 31.9% indicates a regression of 1.1%
of the amount of our road network in an amber or red status.
Deterioration is also showing across individual road categories to a
similar extent.
The Service is currently preparing the annual Roads Asset Management
Plan (RAMP) update for 2024 to reflect the most recent data and this will
be reported to committee later this year.
Red 30.8% 31.9% 30.6% 29.7% 30.8%
Number of road casualties in South
Lanarkshire during 2023
Provisional casualty figures are available for the full year 2023, when
there were 370 casualties. Of these, there were 7 fatal casualties, 125
serious casualties and 238 slight casualties. There were 0 child fatal
casualties, 23 children seriously injured and 24 children slightly injured.
Compared with the same period in 2022, there were 284 casualties. Of
these, there were 10 fatalities, 84 serious casualties and 190 slight
casualties. For children in 2022, there were 0 child fatal casualties, 4
children seriously injured and 16 children slightly injured.
In 2021 and 2022, casualty numbers were notably low, due to Covid-19's
impact on travel patterns; but in 2023, they increased, approaching pre
2020 levels. Despite the increase, overall casualty figures in 2023
decreased by 36% compared to the 2014-18 baseline and the overall
annual trend is downwards.
Amber 284 370 317 254 284
Page 4
41

Page 42

IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
Health and Wellbeing
Public health is safeguarded through an effective environmental regulation and enforcement service
Performance Indicators Comments/ Progress Status 2021/22 2022/232020/21Target To Date
-------- Last 3 Years ------------------- This Year -----------
Broad compliance with food law statutory
requirements secured in premises
95% of food businesses that have been inspected were found to be
broadly compliant in the fourth quarter of 2023-24 (January  to March
2024). This equates to 2,638 food businesses.  Year to date, 95% of
food businesses that have been inspected were found to be broadly
compliant with both food hygiene and food standards legislation.
This compliance figure continues to exceed the annual target set for this
measure.
Green 85.0% 95.0% 90.0% 93.0% 96.0%
All schools and nursery children have access to nutritious school meals
Performance Indicators Comments/ Progress Status 2021/22 2022/232020/21Target To Date
-------- Last 3 Years ------------------- This Year -----------
Level of primary school meal uptake (as a
proportion of total primary school meals
which could be taken up over the period)
Annual figure (until 31 March 2024) was not available when preparing
the report. The figure reported here shows the position until 22 February
2024 and that the target is achieved.
Green 60.0% 69.2% 41.3% 58.2% 66.0%
Level of secondary school meal uptake (as
a proportion of total primary school meals
which could be taken up over the period)
Annual figure (until 31 March 2024) was not available when preparing
the report. The figure reported here shows the position until 22 February
2024 and that the target is achieved.
Green 38.0% 39.9% 24.4% 36.3% 38.0%
Page 5
42

Page 43

IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
Our Economy
South Lanarkshire is an attractive place to start, grow and locate a business
Performance Indicators Comments/ Progress Status 2021/22 2022/232020/21Target To Date
-------- Last 3 Years ------------------- This Year -----------
Number of new South Lanarkshire
business starts supported by Business
Gateway
Figures provided are up to 29 February 2024, March figures not
available as yet.
This target has been achieved at a time when the Business Gateway
was undergoing significant staffing changes and moving from an
external contractor to local authority delivery.
Green 500 499 ------ ------ 520
Number of business support interventions
per annum by Economic Development
(grants, loans or advice)
The Business Support service supported 829 businesses during
2023-24, significantly lower than the target of 1,200. There are a number
of contributing factors that have led to the reduction in the number,
including that the Business Growth Grant did not open until August 2023
and there were less face to face events this year e.g. no business
exhibitions or ‘meet the real buyer’ events.
The Business Support section have been impacted by reduced
resources, in particular a reduction in the number of staff within the
team. For 2024-25, the targets will need to be reviewed in line with the
reduced resources available within the team. The Business Gateway
Service has been taken into North Lanarkshire Council. This provides
opportunities to review how the Council supports businesses and will
also be a factor in a review of targets.
Red 1,200 829 3,075 2,679 1,615
Number of jobs created or sustained per
annum as a direct result of Economic
Development intervention
646 jobs were created or sustained during 2023-24 as a direct result of
Economic Development intervention, exceeding the target of 500.
Eligibility criteria for SLC Business Growth Grant amended in August
2023, from then on applications were only accepted for projects that led
to direct job creation or net zero projects.
Green 500 646 ------ 1,095 1,256
Increased value of sales generated by
businesses as a direct result of Economic
Development intervention
Increased sales figure derived exclusively from additional sales from
Business Support Grants.
Green £5.000m £14.496m ------ £22.107m £13.113m
Perecentage of procurement spend on
local enterprises
Measure isn’t reported until the Improvement Service calculate this in
July/August 2024.
Report Later ------ ------ 0 18 18
Page 6
43

Page 44

IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                   Report printed on Tuesday 14 May 2024
Resource Plan Performance Indicators South Lanarkshire Council - Community and Enterprise
Our Economy
Economic development and growth in South Lanarkshire is fair, inclusive, sustainable and low carbon
Performance Indicators Comments/ Progress Status 2021/22 2022/232020/21Target To Date
-------- Last 3 Years ------------------- This Year -----------
Delivery of UK Shared Prosperity Program Progress over 23 projects has meant that we have met the anticipated
financial target. Projects delivered across employability, business
support, communities and Multiply maths support.
The financial figure is an initial assessment, a full report will be delivered
to Glasgow City region and progress with the programme reported to
Community and Enterprise Resource committee.
Green £3.000m £3.489m £0.000m £0.000m £0.000m
Physical development and land use in the area is enabled, guided and controlled to help facilitate economic growth
Performance Indicators Comments/ Progress Status 2021/22 2022/232020/21Target To Date
-------- Last 3 Years ------------------- This Year -----------
Percentage of all planning applications
approved
The figure for 2023-24 is below the target of 95% and is also lower than
the outcome for 2022-23. The reduced figure reflects the determination
of a higher number of legacy cases during the year which resulted in a
greater proportion of applications being refused due to lack of adequate
supporting information being submitted by applicants and/or
unwillingness to amend proposals to comply with the development plan.
Amber 95.0% 89.1% 96.2% 97.1% 97.6%
Page 7
44

Page 45

Summary - number of measures complete, green, amber and red under each Council Plan
Outcome / Theme
Council Outcome/ Theme Complete Green Amber Red Report later Total
Communities and Environment 4 10 2 0 0 16
Education and Learning 0 0 0 0 0 0
Health and Wellbeing 1 4 2 0 0 7
Children and Young People 0 0 0 0 0 0
Housing and Land 0 0 1 0 0 1
Our Economy 8 3 2 0 0 13
Delivering the plan and achieving best value 0 0 0 0 0 0
Total 13 17 7 0 0 37
Page 8
45

Page 46

IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
Communities and Environment
High-quality streets, parks and other public areas ensures South Lanarkshire is a place where people want to live, work, visit and invest
Action Measures Comments/ Progress Status
Prepare an Open Space
Strategy in partnership
with Glasgow and Clyde
Valley Green Network
Partnership and other
council services.
Strategy will contain
standards on access to
and quality of open
spaces
Draft Open Space strategy to be presented to the Planning
Committee by March 2024
Timescales for the presentation of a draft Open Space Strategy to the
Planning Committee have been revised to correlate with work on the
LDP3 evidence report.
Analysis of data from the open space audit has been completed.
Engagement on these finding will be carried out during quarter two
2024/25 which in turn will be used to inform the evidence report. It is
anticipated that a draft Open Space Strategy will be available in early
2025 once the Gatecheck of the Evidence Report has been
completed.
Amber
To make South
Lanarkshire a cleaner
place to live, work and
visit free of litter, fly
tipping and dog waste
Prepare an annual progress report for Climate Change and
Sustainability Committee in September 2023, demonstrating
the impact of the Litter Strategy (2022-2027)
The annual progress report for the Litter Strategy was presented to
committee on 20 September 2023.
Complete
Page 9
46

Page 47

IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
Communities and Environment
Communities are encouraged and supported to reduce, re-use and recycle their waste
Action Measures Comments/ Progress Status
Support a circular
economy by re-using,
recycling and generating
energy from the waste
we manage
Commence a review of the waste service during 2023-24
that will incorporate the impact of the Deposit Return
Scheme
Scotland's Deposit Return Scheme has been postponed until at least
2025; however, forthcoming legislative changes such as the proposed
Circular Economy Bill, Circular Economy and Waste Route Map,
Packaging Reforms and the implementation of Persistent Organic
Pollutants (POPs) legislation will have a significant impact on the
service, meaning the review of the waste service continues to
progress.
An update on the Waste Review will be presented to Community and
Enterprise Resources Committee on 13 June 2024.
Green
The council addresses climate change by reducing carbon emissions, protecting our natural environment, adapting to the impacts of climate change,
and acting sustainably
Action Measures Comments/ Progress Status
Lead by example and
influence area-wide
climate change and
sustainability action
Implement the Sustainable Development and Climate
change Strategy (2022-2027) Action Plan, and report
progress at quarter two and quarter four to Climate Change
and Sustainability Committee
The Sustainable Development and Climate Change Action Plan has
been implemented and progress for quarter two and quarter four has
been reported to the Climate Change and Sustainability Committee at
September 2023 (2022-23 Action Plan quarter four) and February
2024 (2023-24 Action Plan quarter two).
Complete
Protect, enhance and
respect South
Lanarkshire's natural
environment
Develop a new Biodiversity Strategy (2024-2030) and
Biodiversity Implementation Plan for (2024-2026) for
approval by Climate Change and Sustainability Committee
by February 2024
The Biodiversity Strategy and the Biodiversity Duty Implementation
Plan were approved by the Climate Change and Sustainability
Committee in February 2024.
Complete
Page 10
47

Page 48

IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
Communities and Environment
The council addresses climate change by reducing carbon emissions, protecting our natural environment, adapting to the impacts of climate change,
and acting sustainably
Action Measures Comments/ Progress Status
Ensure national
planning policy set out in
National Planning
Framework 4 in relation
to climate change,
biodiversity and
sustainable travel is
embedded in decision
Prepare Supporting Planning Guidance on climate change &
sustainability and green issues as an interim measure
pending preparation of LDP3
Draft supporting planning guidance has been prepared and has been
the subject of informal engagement with other council services and
partners. It is expected a finalised version will be presented to the
Sustainable Development and Climate Change Committee in quarter
two 2024-25.
An awareness session is to be delivered jointly by Countryside and
Greenspace and Nature Scot in the same period.
Green
making process for
planning applications
and the preparation of
the South Lanarkshire
Local Development Plan
3
Awareness sessions to be developed for elected members,
planning officers and developers/agents by September 2023.
A programme of awareness sessions for officers in the planning
service and other areas of the Council has been developed in order to
broaden understanding of the Local Development Plan process and
encourage participation in its preparation.
The agents event in May 2023 covered this topic. An event for major
developers is timetabled to take place in quarter two 2024-25.
An awareness session for elected members is expected to take place
in May 2024.
Green
Page 11
48

Page 49

IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
Communities and Environment
The council addresses climate change by reducing carbon emissions, protecting our natural environment, adapting to the impacts of climate change,
and acting sustainably
Action Measures Comments/ Progress Status
Create the conditions for
the decarbonisation of
the council's fleet
Implement and review the Fleet Strategy (2020-2025) Action
Plan including a reduction in transport related emissions,
conversion of fossil fuelled small fleet to full electric and the
trailling of a new fuel option for the medium to heavy fleet
A revised / rescoped Fleet Asset Management Plan will be completed
during 2024-25 and will provide an update in relation to progress
against the actions contained in the Fleet Strategy (2020-25). It is
recognised that the two years lost to the Covid-19 pandemic impacted
the extent of progress that might have otherwise been made. Recent
recruitment exercise has now provided some stability to focus on this
key piece of work.
Green
Deliver new and
improved low carbon
vehicle charging
infrastructure
Maintain, manage and expand public infrastructure points /
hubs in line with available internal and external funding
sources
Office for Zero Emissions Vehicles (OZEV) Project.
This project consists of the installation of 13 dual on-street electric
vehicle chargers in various residential streets in South Lanarkshire.
Works are now complete.
Electric Vehicle Charging Infrastructure
Glasgow City Council, in conjunction with other City Region Local
Authorities, including South Lanarkshire, commissioned a consultant
to complete an Electric Vehicle Strategy and Plan. This body of work is
now complete and work is continuing to develop a concession model
and evaluate the best route to market.
Green
The council supports and promotes a fairer, healthier, and more sustainable food system
Action Measures Comments/ Progress Status
Develop a sustainable
food system to
overcome social, health,
economic and
environmental issues
related to food
Implement the Good Food Strategy (2020-2025) Action Plan
and report progres at quarter two and quarter four to the
Climate Change and Sustainability Committee
The year four action plan was approved in September 2023 by the
Climate Change and Sustainability Committee. The quarter two
progress report was presented at the same Committee in February
2024 and the quarter four report will be presented in May 2024.
Green
Page 12
49

Page 50

IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
Communities and Environment
The council supports and promotes a fairer, healthier, and more sustainable food system
Action Measures Comments/ Progress Status
Continue to identify
opportunities to increase
food growing provision
throughout South
Lanarkshire
Progress planning application and process for new site at
Chatelherault, and if successful, begin development of the
site and allocating plots from the waiting list by March 2024
Planning consent for the new site at Chatelherault was granted and
works started April 2023 with completion August 2023.  All plots are
now let with the site fully operational with 100% occupancy.
Complete
All roads, footways, cycle routes, bridges and associated infrastructure are safe and fit for purpose
Action Measures Comments/ Progress Status
Deliver prioritised road
safey infrastructure
improvements and
promote road safety
Deliver road safety projects and schemes in line with agreed
2023-24 programme
Casualty reduction measures have been introduced at the following
locations:
A749, East Kilbride Road - new warning signage and road markings.
Bloomgate/Westport Lanark - pedestrian refuge island and new town
gateway pinch point.
A73 Braidwood - new signs/road markings.
A73 - Bogside to Carluke - alterations to junctions at Wildman Road
and Law Hospital.
A73 - application of high friction surfacing north of Hyndford Bridge.
General signing, lining and catseye improvements on A721, A70 and
A706.
Green
Improve resilience of
strategic routes during
adverse weather
Implement prioritised / enhanced drainage / gulley cleaning
action plan across the network by June 2023
As part of the Frontline First fund, we allocated additional resources to
a gully cleaning and drainage repairs programme. During financial year
2023-24 the investment enabled the team to temporarily double their
existing fleet of three gully cleaning vehicles to six, using hired vehicles
to supplement their own fleet.  These changes have given them the
ability to temporarily increase the frequency of the gully route cleans in
order to keep gullies functioning more effectively and making the
network more resilient.
Green
Page 13
50

Page 51

IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
Communities and Environment
Road and transportation infrastructure supports new development, enables use of public transport and encourages active travel
Action Measures Comments/ Progress Status
Produce a new Local
Transport Strategy for
South Lanarkshire to
support the National and
Regional Transport
Strategy as well as the
provisions, where
appropriate, of the
Transport Scotland Act
Draft Local Transport Strategy to be presented to Committee
by Spring 2024
A consultant to undertake the development of the next Local Transport
Strategy (LTS) has been appointed. An extensive consultation exercise
was undertaken in July/August 2023 with numerous groups,
organisations, elected members and the public invited to contribute
views. We have reviewed the feedback and a draft document is now
being reviewed. A second public consultation will commence mid-2024
and it is anticipated that a draft document will be presented to
Community and Enterprise Resource Committee in summer 2024.
An update report outlining the shape of the new LTS will be considered
by Community and Enterprise Committee on 23 April 2024.
Green
Page 14
51

Page 52

IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
Communities and Environment
Road and transportation infrastructure supports new development, enables use of public transport and encourages active travel
Action Measures Comments/ Progress Status
Provide road and
infrastructure
improvements to
support new
developments including
those undertaken as
part of the City Deal
An Outline Business Case will be prepared for the
Stewartfield Way Sustainable Transport Capacity
Enhancement Project in Autumn 2023
Work is now underway to rescope the project to have greater focus on
Town Centre redevelopment as well as the core transportation
infrastructure improvement. A consultant has been appointed to
progress an outline business case for submission later this year.  A
report will be considered by Community and Enterprise Resources
Committee in April 2024.
Amber
Page 15
52

Page 53

IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
Communities and Environment
Road and transportation infrastructure supports new development, enables use of public transport and encourages active travel
Action Measures Comments/ Progress Status
Encourage active travel
by extending our
network of walking and
cycling routes
Deliver walking and cycling projects/schemes in line with
agreed 2023-24 capital programme
A number of cycling and walking projects are progressing: -
1) Active Travel Studies – A number of further studies have been
completed for towns such as Blackwood, Kirkmuirhill, Abington,
Crawford, Carnwath, Forth and Biggar.  These complete studies for all
areas of South Lanarkshire and are now available on the Council’s
website.  The priorities identified in these studies will be reviewed as
part of the development of the new Local Transport Strategy.
2) The development of a segregated cycle network with enhanced
pedestrian facilities in East Kilbride is now complete on Churchill
Avenue. This links West Mains Road to Cornwall Street and towards
the trunk road network on the A726.
3) Carstairs to Carluke – Works which include surfacing upgrades,
shared cycle /pedestrian crossing points of the A706 and A70, signing,
road markings and other associated works are complete and and
transfer of land ownership to allow for the final section to be
constructed is ongoing.
4) Cycle Parking Provision in Town Centres – Locations for new
provision in Strathaven have been identified and works will be
undertaken in early summer.
5) Cycle Shelters and parking stands in schools – Locations for new
shelters have been identified and funding has been awarded by
Cycling Scotland and works will be undertaken in early summer.
6) Cycle Route designs continue being taken forward in various
locations such as Carstairs, Hamilton, Uddingston and Bothwell.
Green
Page 16
53

Page 54

IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
Health and Wellbeing
All school and nursery children have access to nutritious school meals
Action Measures Comments/ Progress Status
Complete the roll out of
free school meals to all
primary children
All P6s and P7s to receive free school meals in line with
Scottish Government timescales
The implementation date has still to be confirmed from Scottish
Government. Work is ongoing to prepare for the roll out.  Anticipated
date for roll out 2026.
Pupils entitled to the New Scottish Children payment will receive free
school meals from February 2025 - roll out programme unknown at
this time.
Green
Health inequalities are addressed through collaboration with local communities and partners
Action Measures Comments/ Progress Status
Complete the Shaping
Places for Wellbeing
project in Rutherglen
Use the data analysis conducted during 2022-23 to develop
actions to address health inequalities, taking account of the
existing infrastructure available in the form of codesigned
solutions, by October 2023
The Shaping Places for Wellbeing project has enabled a range of
services and partners to come together to understand the factors that
are affecting health inequality in Rutherglen. Extensive health data has
been analysed and developed into data profiles for the main
settlements in South Lanarkshire. This will form a significant element
of the LDP3 evidence report as well as other council strategies and
action plans.
Green
Present regular update reports to the Corporate
Management Team, with a final outcome report being
delivered by March 2024
The Shaping Places for Wellbeing programme will conclude in
2024/25 and a range of actions will be developed to address the
issues affecting the health and wellbeing of the area that have been
identified. As a result a final outcome report will be presented to CMT
once this process has been completed.
Amber
Page 17
54

Page 55

IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
Health and Wellbeing
All residents have the opportunity to access cultural, leisure and outdoor recreational activities to help improve their wellbeing and quality of life
Action Measures Comments/ Progress Status
Develop a
Commissioning Plan to
define the council’s ask
of South Lanarkshire
Leisure and Culture
(SLLC)
Develop a Commissioning Plan for approval by Executive
Committee
An initial session was held with Elected Members on 19 June 2023 to
provide contextual information to support the development of a new
Commissioning Plan for SLLC. The Commissioning Plan is intended to
set out a clear strategic framework for the provision of leisure and
culture activities in South Lanarkshire.
A survey was developed for completion by Members over the summer
period, with a follow up session in September 2023.
Activity in this area had been paused pending the outcome of the
SLLC asset review. The development of the Commissioning Plan will
now recommence in 2024-25.
Amber
Improve health and
wellbeing by offering
attractive and affordable
leisure and cultural
activities delivered with
warmth, friendliness and
individual pride (SLLC
Mission)
Implement the South Lanarkshire Leisure and Culture
Strategy (2022-2027), monitor impact on a quarterly basis via
the four SLLC Strategy Implementation Groups, and report
on progress twice per year to the Community and Enterprise
Resources Committee
South Lanarkshire Leisure and Culture (SLLC) continuing to
implement the SLLC Strategy 2022-2027 and monitoring its impact
through quarterly reporting to the SLLC Board.  Quarter three progress
was presented to the SLLC Board on 28 February 2024.
Following the outcome of the SLLC asset review, work will commence
on developing SLLC reports for Community and Enterprise Committee.
Green
Begin implementation of
the multi-year Play Area
Undertake consultation with local members and communities
in Larkhall, Cambuslang and Rutherglen
Consultation for Larkhall, Rutherglen and Cambuslang has been
undertaken with local members and young people.
Complete
Investment Programme Finalise design options and implement agreed proposals by
March 2024
The contract for the play areas in Larkhall identified for refurbishment
has been awarded and works have started on site.
The tender for the play areas identified in Rutherglen and Cambuslang
has been prepared for publishing by procurement.
Green
Page 18
55

Page 56

IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
Housing and Land
Vacant, derelict and contaminated land is brough back into productive use
Action Measures Comments/ Progress Status
Agree and implement
vacant and derelict /
contaminated land
programme
Implement projects approved within the Vacant and Derelict
Land Fund framework agreed for 2023-24
Cuningar Allotments project returned from tender and work will start on
site in May 2024.
Grant offers issued and accepted by Clyde Cycle Park and Carnwath
Hub. Both projects have committed to expend funds.
Clyde Gateway grant fully expended.
Langlands project subject to delays. Recovery programme prepared
for implementation in 2024.
Amber
Page 19
56

Page 57

IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
Our Economy
South Lanarkshire is an attractive place to start, grow and locate a business
Action Measures Comments/ Progress Status
Prioritise business
development advice,
support and financial
assistance to ensure
businesses are able to
continue to operate,
whilst creating the right
conditions for low
carbon economic growth
Deliver programmes, services, and events to businesses
around sectors, location, and themes (e.g., food and drink,
tourism, construction, low carbon, innovation,
internationalisation, collaboration, and young enterprise)
The following programmes aimed at developing the skills of business
owners, and the growth of businesses in the following sectors, have
been delivered in the last year:
Construction: Build Lanarkshire programme.
Social Economy: Accelerator Programme and Leadership
Development Programme.
Tourism: Green tourism webinar and resources made available to all
tourism businesses to assist with their sustainability journey.
VisitScotland Connect – supported one business in April 2023 and
supporting six in April 2025 to attend VisitScotland Connect.
Food and Drink: EAT South Lanarkshire Programme delivered.
Participation in, and marketing of, the Larder of the Lowlands event.
SLC also supports the Food and Drink Sector by having a seat on the
committee of the Lanarkshire Larder (industry led regional food group).
SLC also has a seat on the board of the Young Enterprise Company
Programme in Lanarkshire.
Green
Manage the Supplier Development Programme to deliver
events, training and e-commerce support to SME’s or third
sector organisations who are interested in working with the
public sector
Delivery of programme ongoing in line with agreed targets. Green
Page 20
57

Page 58

IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
Our Economy
Economic development and growth in South Lanarkshire is fair, inclusive, sustainable and low carbon
Action Measures Comments/ Progress Status
Review the remit,
membership and
effectiveness of the
existing Lanarkshire
Economic Forum, and if
required,
refocus/restructure in
Review the original scope and membership of the
Lanarkshire Economic Forum, together with the outputs of
the Forum since establishment in 2020
Review of the Lanarkshire Economic Forum has been completed.  The
Forum was established at the start of the Covid-19 pandemic to
ensure dissemination of information.  As such the purpose of the
Forum is no longer required since members engage in a variety of
other ways.
Complete
order for it to act as the
Economic
Transformation Board to
drive forward the South
Lanarkshire Economic
Strategy
Dependent on the outcomes of the review,
refocus/restructure the forum in consultation with the partner
organisations
The Review concluded that the Forum was no longer required as
partner organisations now communicate in a variety of other ways.
Complete
Promote sustainable
economic development
across South
Lanarkshire
Prepare an annual progress report for Community and
Enterprise Resources Committee, demonstrating the impact
of the South Lanarkshire Economic Strategy (2022-2027)
Annual report was submitted to Community and Enterprise Committee
on 23 April 2024.
Complete
Positively enhance the
benefits of tourism
across South
Lanarkshire by
delivering the very best
for our visitors, our
businesses, our people,
our communities, and
our environment
Prepare an annual progress report for Community and
Enterprise Resources Committee, demonstrating the impact
of South Lanarkshire Tourism Strategy (2022-2025)
Annual report was submitted to Community and Enterprise Committee
on 23 April 2024.
Complete
Page 21
58

Page 59

IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
Our Economy
Economic development and growth in South Lanarkshire is fair, inclusive, sustainable and low carbon
Action Measures Comments/ Progress Status
Champion the social
enterprise sector and
invest in start-up and
growth of our local
social enterprise
Develop a new Social Enterprise Strategy for approval by
Community and Enterprise Resources Committee in May
2023
The South Lanarkshire Social Enterprise Strategy 2022-27 was
approved at the Council's Executive Committee in August 2023. The
strategy can be accessed on the Council's website.
Complete
Income generating
projects will be scoped
across all council
resources to identify
viable projects with a
focus on green
initiatives including
exploring options for
delivery and funding
Liaise with all Council resources, third parties and funders to
identify new opportunities for generating income and
consider a risk analysis of each opportunity
A report setting out potential commercial opportunities for the Council
was presented to Executive Committee on 24 January 2024.
Whilst this initial piece of work is complete, the activity is ongoing as a
range of commercial opportunities continue to be explored.
Complete
Consult with community
organisations and
develop a Rural Action
Plan maximising existing
and future funding
through Community Led
Local Development and
Renewable Energy
Fund
Finalise the Rural Action Plan and report to Rural Task Force
in November 2023
A seminar proposing new priorities and changes to the Renewable
Energy Fund (REF) was given to the Rural Task Force on 2 October
2023 and a final paper taken to the Rural Task Force on 15 November
2023, completing this action.
The proposals were taken to Community and Enterprise Resource
Committee in February 2024 approving the strategic aims for the REF
to address over five years.
Complete
Page 22
59

Page 60

IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
Our Economy
Thriving town and neighbourhood centres provide a focal point for local communities
Action Measures Comments/ Progress Status
Complete the south
Lanarkshire wide town
centre visioning strategy
which will give a
strategic overview on
the engagement and
interventions with town
centres over the next 10
years, and a series of
town specific strategies
and action plans will sit
below this, giving a
template for
placemaking within our
communities.
Complete draft town centre visioning study by end June 2023
for consultation, and present final visioning strategy to
Community and Enterprise Resources Committee in
November 2023
Work complete, report presented to Community and Enterprise
Resources Committee in November 2023.  This action can be closed
for 2023-24.
Complete
Physical development and land use in the area is enabled, guided and controlled to help facilitate economic growth
Action Measures Comments/ Progress Status
Preparation of revised
Residential Design
Guide
Develop interim framework for consultation with
stakeholders, with final framework prepared by end of June
2023
A review of the purpose of this document during 2023-24 led to a shift
in focus from a purely residential design guide to one that addresses
wider placemaking principles and explores themes that will apply
across Council services and our partners in the delivery of projects.
This has led to a delay in the preparation of the draft guide.
Internal discussion on the initial version started in quarter four. It is
intended to present a draft Placemaking Guide to the Planning
Committee in June 2024 with consultation being carried out thereafter.
Amber
Page 23
60

Page 61

IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
IMPROVe - SLC Performance Management System                                                                                                                                                                                                  Report printed on Tuesday 14 May 2024
Resource Plan actions and measures South Lanarkshire Council - Community and Enterprise
Our Economy
Physical development and land use in the area is enabled, guided and controlled to help facilitate economic growth
Action Measures Comments/ Progress Status
Present finalised document to Planning Committee for
approval by December 2023
A draft document will be presented to the Planning Committee in June
2024 which will be followed by consultation. It is currently anticipated a
finalised version will be presented to committee in quarter four
2024-25.
Amber
Customers experience high quality and improving council services
Action Measures Comments/ Progress Status
Implement the Frontline
First Fund
Identify and implement a programme of projects to deliver
the Frontline First Fund
First year of Frontline First Fund went well, majority of equipment for
the Grounds Service was purchased in first year and a number of
locations benefited from environmental improvements, work will
commence again winter 2024.
Green
Page 24
61

Page 62

62

Page 63

Appendix 3 
CER Quarter 2 to Quarter 4 2023-24 scrutiny of change in measure status   
Quantitative measures    
Communities and Environment 
Communities are encouraged and supported to reduce, re-use and recycle their waste
Actions/
Measures  Qtr 2 Comments Q2 Status Qtr 4 Comments Q4 Status
Percentage of
total household
waste that is
recycled in 2023
This measure is reported
per calendar year and the
latest figures relate to the
period from April to June
2023 (48%). The year-to-
date figure reflects
performance from January
to June 2023 (44.24%).
This remains below the
target of 50%. Performance
in April to June 2023 (48%)
is an improvement on the
same quarter in 2022
(45.08%). The new bulky
waste contract continues to
increase the quantities of
bulky waste being recycled.
Performance will continue
to be closely monitored.
Amber This measure is reported
per calendar year. The
year-to-date figure to the
right reflects performance
from January to December
2023 (43.75%). This
remains below the target
of 50%. Performance in
October to December
2023 (38.71%) was an
improvement on the same
quarter in 2022 (37.75%).
The new bulky waste
contract continues to
increase the quantities of
bulky waste being
recycled. Performance will
continue to be closely
monitored.
Red 
All roads, footways and bridges and associated infrastructure are safe and fit for purpose
Actions/ Measures     Qtr 2 Comments Q2 Status Qtr 4 Comments Q4 Status
Percentage of our
road network that
should be
considered for
maintenance
treatment
This figure is derived from
the Society of Chief
Officers of Transportation
in Scotland (SCOTS)
Road Condition Index
(RCI) survey which is
undertaken each year.
The target figure of 29.7%
is based on the results for
the period 2020-22. The
RCI for 2021-23 will be
published in January 2023
and reported in quarter
four. 
Report Later This figure is derived
from the Society of Chief
Officers of
Transportation in
Scotland (SCOTS) Road
Condition Index (RCI)
survey. The survey has
now been completed and
our overall RCI is 30.8%
for 2021-2023. This falls
short of our target of
29.7% and is a
depreciation of 1.1% in
the overall condition of
the road network.
Individual road
categories are generally
also showing a
concerning regression in
condition demonstrating
need for sustained
investment in the
network.
Red 
4
63

Page 64

Our Economy 
South Lanarkshire is an attractive place to start, grow and locate a business
Actions/ Measures     Qtr 2 Comments Q2 Status Qtr 4 Comments Q4 Status
Number of
business support
interventions per
annum by
Economic
Development
(grants, loans or
advice)
Slightly behind the
halfway point of 600 on
the annual target as the
UKSPF programmes have
not been opened for the
full 6 months period.
However, there is a strong
pipeline and we should be
able to achieve the full
annual target.
Green The Business Support
service supported 829
businesses during
2023/24, significantly
lower than the target of
1,200.  There are a
number of contributing
factors that have led to
the reduction in the
number, including that
the Business Growth
Grant did not open until
August 2023, and there
were fewer face to face
events this year eg no
business exhibitions or
‘meet the real buyer’
events. 
Red 
Project measures
Communities and Environment 
High-quality streets, parks and other public areas ensures South Lanarkshire is a place
where people want to live, work, visit and invest
Action     Measure     Qtr 2 Comments Q2 Status Qtr 4 Comments Q4 Status
Prepare an Open
Space Strategy in
partnership with
Glasgow and
Clyde Valley
Green Network
Partnership and
other council
services. Strategy
will contain
standards on
access to and
quality of open
spaces
Draft Open
Space strategy
to be presented
to the Planning
Committee by
March 2024
Consultants
appointed and initial
data gathering
commenced.
Green Timescales for the
presentation of a
draft Open Space
Strategy to the
Planning Committee
have been revised
to correlate with
work on the LDP3
evidence report. 
Analysis of data
from the open
space audit has
been completed.
Engagement on
these findings will
be carried out
during quarter two
2024-25 which in
turn will be used to
inform the evidence
report. It is
anticipated that a
draft Open Space
Strategy will be
available in early
2025 once the
Gatecheck of the
Evidence Report
has been
completed.
Amber 
Health and Wellbeing 
64

Page 65

Health inequalities are addressed through collaboration with local communities and
partners
Action     Measure     Qtr 2 Comments Q2 Status Qtr 4 Comments Q4 Status
Complete the
Shaping Places
for Wellbeing
project in
Rutherglen
Present regular
update reports
to the Corporate
Management
Team, with a
final outcome
report being
delivered by
March 2024
Updates reported to
CMT as appropriate.
Green The Shaping Places
for Wellbeing
programme will
conclude in 2024/25
and a range of
actions will be
developed to
address the issues
affecting the health
and wellbeing of the
area that have been
identified.  As a
result, a final
outcome report will
be presented to
CMT once this
process has been
completed.
Amber 
All residents have the opportunity to access cultural, leisure and outdoor recreational
activities to help improve their wellbeing and quality of life
Action     Measure     Qtr 2 Comments Q2 Status Qtr 4 Comments Q4 Status
Develop a
Commissioning
Plan to define the
council’s ask of
South Lanarkshire
Leisure and
Culture (SLLC)
Develop A
Commissioning
Plan for
approval by
Executive
Committee
An initial session
was held with
Elected Members
on 19 June 2023 to
provide contextual
information to
support the
development of a
new
Commissioning
Plan for SLLC. The
Commissioning
Plan is intended set
out a clear strategic
framework for the
provision of leisure
and culture
activities in South
Lanarkshire. A
survey was
developed for
completion by
Members over the
summer period,
with a follow up
session in
September 2023.
Green An initial session was
held with Elected
Members on 19 June
2023 to provide
contextual
information to
support the
development of a
new Commissioning
Plan for SLLC. The
Commissioning Plan
is intended to set out
a clear strategic
framework for the
provision of leisure
and culture activities
in South Lanarkshire.
A survey was
developed for
completion by
Members over the
summer period, with
a follow up session in
September 2023.
Activity in this area
had been paused
pending the outcome
of the SLLC asset
review. The
development of the
Commissioning Plan
will now recommence
in 2024-25
Amber 
Housing and Land 
Vacant, derelict and contaminated land is brought back into productive use
65

Page 66

Action     Measure     Qtr 2 Comments Q2 Status Qtr 4 Comments Q4 Status
Agree and
implement vacant
and derelict /
contaminated
land programme
Implement
projects
approved within
the Vacant and
Derelict Land
Fund framework
agreed for
2023/24
Clyde Gateway
project to upgrade
access road and
extend car park at
Cuningar Phases 2
and 3 completed.
Cuningar
allotments project
out to tender.
Vacant Derelict
Land Fund
programme for
2023-24 approved
at Community and
Enterprise
Committee.
Green Cuningar Allotments
project returned from
tender and work will
start on site in May
2024. Grant offers
issued and accepted
by Clyde Cycle Park
and Carnwath Hub.
Both projects have
committed to expend
funds. Clyde
Gateway grant fully
expended. Langlands
project subject to
delays. Recovery
programme prepared
for implementation in
2024
Amber 
(Data/Information correct as at: 14 May 2024) 
66

Page 67

Report
Agenda Item 
Report to: Community and Enterprise Resources Committee
Date of Meeting: 18 June 2024
Report by: Executive Director (Community and Enterprise
Resource)  
Subject: Community and Enterprise Resource Plan 2024/2025 
1. Purpose of Report
1.1. The purpose of the report is to:- 
 present the Community and Enterprise Resource Plan 2024/2025 for approval
and note the monitoring arrangements
[1purpose]
2. Recommendations
2.1. The Committee is asked to approve the following recommendation(s):-
[
(1) the Resource Plan 2024/2025, attached as Appendix 1, be approved
(2) the Resource Plan 2024/2025 be uploaded onto the Council’s website
following consideration by this Committee; 
(3) that following Committee approval, all Resource Plans will be presented to the
Executive Committee on 26 June 2024, for noting; and
(4) that Progress Reports on the Resource Plan 2024/2025 be provided at
Quarter 2 and Quarter 4 to future meetings of this Committee. 
3. Background
3.1. The Community and Enterprise Resource Plan for 2024/2025 was prepared in line
with the corporate Resource Planning guidance. 
3.2. The Resource Plan is a key element of the Council’s performance management
arrangements.  It provides details of the context within which Community and
Enterprise Resource operates and establishes actions and measures for the year
ahead based on the priorities and outcomes set out in the Council Plan Connect
2022 to 2027. 
3.3. Performance management is a keystone of Best Value and ensures that the Council
can demonstrate sound governance arrangements.  The Resource Plan is one part
of the Council’s framework for planning and budgeting and demonstrates how this
leads to effective front line service delivery. 
3.4. As part of this framework, the Community and Enterprise Resource Plan reflects the
aspirations of the Council Plan and the Community Plan as well as being
complemented by the details of individual Service, Business and other Plans. 
Ultimately, these details are included in the key work objectives of individual officers. 
This demonstrates the ‘Golden Thread’ of performance management which ensures
a clear understanding of the Council’s vision, values, priorities and outcomes at all
levels. 
5
67

Page 68

3.5. The current format for performance reporting has been established since 2007 and is
used for Executive Directors’ reports to the Chief Executive, Resource Management
Teams, Resource Committees and the Performance and Review Scrutiny Forum. 
The focus has been on reporting progress on Council outcomes, statutory
performance indicators, other key performance measures and high-level Resource
outcomes. Progress reports are provided at Quarter 2 and Quarter 4 to this
Committee. 
3.6. In preparing the Community and Enterprise Resource Plan, account has also been
taken of the need to ensure a robust response to Risk Management and Control. 
Risks associated with delivery of the actions in this Resource Plan have been
identified and evaluated and are listed in the Resource Risk Register.  Where
necessary, controls or further actions to mitigate these risks have been agreed. 
Such actions are tracked through the Resource Risk Control Plan which is kept
under review by the Risk Sponsor for the Resource. 
3.7. Following approval at individual Resource Committees, all Resource Plans will be
presented, as a pack, to Executive Committee on 26 June 2024, for noting. 
4. Resource Plan 2024/2025
4.1. The Community and Enterprise Resource Plan 2024/2025 is attached as Appendix 1
and is structured around the following headings:- 
1. Introduction 
2. Key areas for the year ahead 
3. Resource outcomes 
4. Measures and actions 
5. Resourcing the Plan 
4.2. Resource Outcomes 2024/2025
The Resource has established a number of outcomes to support the delivery of the
Connect Outcomes in 2024/2025.  To support these outcomes, the Resource has
developed performance measures in an action plan which is set out in section 4 of
the Resource Plan.  Key or strategic measures will be included in the Council Plan
Connect Progress Reports 2024/2025, with the rest being monitored and reported at
Resource level. 
4.3. Monitoring and reporting 
As part of the performance management arrangements, the Committee will receive a
mid-year update of progress on the measures in the Community and Enterprise
Resource Plan covering the period April 2024 to September 2024 (Quarter 2) as well
as an end of year progress report covering the full year April 2024 to March 2025
(Quarter 4). 
5. Employee Implications
5.1. The outcomes noted within the Resource Plan will inform the Service Action Plans,
where applicable and, in turn, the Performance Appraisal process for individual
employees. 
6. Financial Implications
6.1. The outcomes within the Resource Plan are reflected in the respective Resource
Revenue and Capital budgets and, longer term, within the framework of the Council’s
approved Financial Strategy.
68

Page 69

7. Climate Change, Sustainability and Environmental Implications
7.1. There are no climate change or environmental implications as a result of this report. 
7.2. The Council acknowledges the serious and immediate threat of climate change and
is committed to accelerating the pace of action in response to the climate emergency
and in Scotland’s transition to a net-zero and climate resilient society and economy.
All Resource Plans have recognised sustainable development and climate change
as a key area of focus for 2024/2025. 
8. Other Implications
8.1. Resource Plan actions are assessed as part of the Resource’s risk management
arrangements and relevant issues have been added to the Resource Risk Register. 
9. Equality Impact Assessment and Consultation Arrangements
9.1. Many of the actions detailed within the Resource Plan reflect ongoing strategies and
policies which will be or have been the subject of consultation and equality impact
assessment. 
David Booth
Executive Director (Community and Enterprise Resources) 
23 May 2024 
Link(s) to Council Values/Priorities/Outcomes
Values
 Focused on people and their needs
 Working with and respecting others
 Accountable, effective, efficient and transparent
 Ambitious, self-aware and improving
 Fair, open and sustainable
 Excellent employer
Priorities
 We will work to put people first and reduce inequality
 We will work towards a sustainable future in sustainable places
 We will work to recover, progress and improve
Outcomes
 Our children and young people thrive
 Good quality, suitable and sustainable places to live
 Thriving business, fair jobs and vibrant town centres
 Caring, connected, sustainable communities
 People live the healthiest lives possible
 Inspiring learners, transforming learning, strengthening partnerships 
Previous References
 None 
List of Background Papers
 Council Plan 2022-2027
69

Page 70

Contact for Further Information
If you would like to inspect the background papers or want further information, please
contact:-
Anne Lewis (Performance and Development Officer)
E-mail:  anne.lewis@southlanarkshire.gov.uk
70

Page 71

1 
Community and Enterprise Resources 
Community and Enterprise Resource Plan 2024 – 2025 
5
71

Page 72

2 
Section      Contents 
1.0   Introduction 
2.0   Key areas of focus for the year ahead 
3.0   Resource outcomes 
4.0   Measures and actions 
5.0   Resourcing the Plan
72

Page 73

3 
Section One – Introduction 
I am pleased to introduce our Resource Plan for 2024-25 which sets out our intended outcomes
and priorities for the coming year. This is the main annual business planning document for the
resource. It reflects the council’s key priorities as set out in the Council Plan ‘Connect’ and
provides an overview of the resource’s main areas of activity. 
Our resource comprises the following four service areas – facilities, waste and grounds
services; roads, transportation and fleet services; planning and regulatory services; and
enterprise and sustainable development.  The resource employs 3,428 people who together
provide a wide range of services for local communities, including: 
• delivering key services within schools and council premises, including cleaning, catering,
receptionist, janitorial, concierge, and crossing patrol services
• keeping our streets clean and maintaining and developing public parks, open spaces, tree
stock, fixed play areas, sports fields, golf courses, allotments, and food growing
opportunities
• collecting and disposing of waste and encouraging recycling
• managing and maintaining the councils’ cemeteries and crematorium, providing
bereavement services, and ensuring the provision of burial ground 
• maintaining our roads and transportation network to support safe and effective transport,
and promoting active travel
• procuring and managing the council’s vehicle fleet, including refuse collection, roads
maintenance, street sweeping and passenger transport
• providing planning and building standard services which guide and control physical
development and land use in the area, ensure the health and safety of persons in or about
buildings, ensure the conservation of energy and the achievement of sustainable
development
• protecting public health through the delivery of environmental health services
• providing trading standards to protect consumers and communities 
• promoting economic development and delivering support for local businesses
• delivering effective employability services to support individuals and business
• supporting town centres and physical regeneration, and
• leading the council in developing and promoting sustainability, supporting the transition to a
net zero carbon economy, and addressing climate change 
The resource also has a significant role to play in managing the relationship between the
council and South Lanarkshire Leisure and Culture (SLLC).  SLLC deliver leisure and cultural
services on behalf of the council and promote the health and wellbeing of South Lanarkshire
residents through libraries, cultural venues, museum, arts centres, indoor and outdoor sports
and leisure centres, community halls and country parks. 
The Resource Plan is an important element of the council’s performance management
arrangements and is complemented by individual service plans and other key business plans
and strategies.  During 2024-25, service teams will continue to be involved in a series of
reviews which will inform how our services are shaped and delivered in the future. 
David Booth
Executive Director
Community and Enterprise Resources 
73

Page 74

4 
Section Two – Key areas of focus for the year ahead 
2.0. Overview 
The resource has identified the main challenges, risks and new developments which will
have significant impact on the delivery of services in the coming year. These are outlined
briefly below. 
2.1. Cost of Living Crisis The UK is experiencing the worst cost-of-living crisis in 40
years.  While all sectors of society are seeing prices rise, the impacts are greatest for
those on the lowest incomes.  The council recognises the immense pressures being faced
by households across South Lanarkshire and acknowledges the potential for additional
demands on council services as a result.  The council has in place a range of support
which can help households manage scarce resources, and services will continue to
explore all avenues to support the most vulnerable in the year ahead. 
While doing all we can to support our communities in these difficult times, the council
recognises that inflationary pressures will also present significant challenges for council
services as budgets are increasingly squeezed by rising costs. This will undoubtedly be
the case within Community and Enterprise Resources. 
2.2.  Economic Development and Renewal The UK, Scottish, Glasgow City
Region and South Lanarkshire economies are all facing real challenges following the
global pandemic, our country’s new international trading position, the war in Ukraine and
the climate emergency; all of which impact our lives now and in the foreseeable future. 
Economic recovery in South Lanarkshire will incorporate the principles of community
wealth building and be framed around three key themes of sustainable development:
People, Place and Business (or social, physical, and economic regeneration). These
themes align council and pan-Lanarkshire activity with local, national and regional
strategies, delivering the collaborative approach required to achieve sustainable and
inclusive economic growth. The Economic Strategy (2022-27) sets out the key priorities
and actions for the council and aims “to make South Lanarkshire a flourishing, green,
dynamic and equitable place for all”.   
Working in partnership with North Lanarkshire Council, the delivery of the Business
Gateway Service has been changed to an ‘in-house’ model following the contract with the
previous provider coming to an end. The new delivery model combined with alignment to
the new Business Gateway National Service Specification, which was approved by
COSLA in November 2023 and takes effect from 1 April 2024, will deliver a more
customer focussed service which lead to better outcomes for businesses and the
economy. 
Town Centre Regeneration Town centres retain a key role at the heart of our
communities as a focal point for retail, business, culture, leisure and social interaction.
Our town centres remain a council priority and we are working across all our towns to
manage change to allow our towns centres to serve the evolving needs of communities in
the future. The way in which we support each town varies depending on the specific
challenges, ranging from large transformational masterplans in East Kilbride and Hamilton
to smaller local interventions linking to local priorities and Community Wealth Building
priorities. 
2.3. External Funding 
UK Government Shared Prosperity Funding (UKSPF) Following the UK
withdrawal from the European Union, the UK Government outlined proposals to replace
74

Page 75

5 
EU funding with national funds to address structural and economic imbalances and to aid
the public and private sector in delivering transformational change in communities. The
delivery of the 3-year £12m UK Shared Prosperity Funding (UKSPF) programme
commenced in 2022. Economic Development Officers are working with council services
and external partners on delivery of the UKSPF to maximise economic and community
outcomes.  Delivery over 23 projects across council resources ranging from employability
support to business grants and grants to communities is progressing and is reported
quarterly to the UK Government through Glasgow City Region. Work will commence in
2024 on the potential programme post March 2025.   
Levelling Up Fund Two projects have been awarded funding by the UK
Government Levelling Up Fund.  These are the Clydesdale Way (awarded £6.8 million of
grant as part of the cross-council border Three Rivers Active Tourism project) and
Shawfield Remediation (awarded £14.6m) for Clyde Gateway URC to progress
decontamination and redevelopment of the Shawfield area. These projects will be
progressed in 2024 with completion in 2026.   
2.4.  Glasgow City Region City Deal As part of the City Deal, the resource is leading
the delivery of three major transportation projects being undertaken to boost South
Lanarkshire’s access to the rest of Scotland.  The Cathkin Relief Road in Rutherglen /
Cambuslang is complete and the Greenhills Road project in East Kilbride substantially
complete and open. Proposals in relation to Stewartfield Way are being developed
through the preparation of the outline business case. 
The City Deal is also helping to deliver private housing led development in some of its
Community Growth Areas, including new schools and community facilities. 
2.5. Deliver effective Employability Services to support Individuals
and Business Following a strategic review of the council’s employability service, as
of 1st April 2024, the service will now sit within Community and Enterprise Resources
which will foster improved links with the business sector whilst continuing to achieve the
aims set out in the No-one Left Behind national strategy for employability. 
This approach involves ensuring that programmes are tailored and responsive and meet
the needs of people of all ages including those who require significant and long-term
support to progress to sustained employment. From April 2024, the council will have
responsibility for meeting the needs of people with long term health conditions and
disabilities who were previously supported by the Scottish Government’s Fairstart
programme. This activity will be planned with our partners on the South Lanarkshire Local
Employability Partnership and set out through a No-one Left Behind Investment Plan,
reflecting the range of support and training available to local people including keywork
support, employability skills development and work-based training. 
Local employers will continue to be at the heart of our employability programmes with
opportunities for employability participants to take part in work placements and sector-
based training to address gaps in the local labour market. We will also continue to provide
support to parents to progress to employment or improve their labour market position
though a range of employability and in-work support programmes as part of the council’s
Tackling Child Poverty strategy. 
2.6.  Sustainable Development and Climate Change (SDCC) The council
acknowledges the serious and immediate threat of climate change and is committed to
accelerating the pace of action in response to the climate emergency and in Scotland’s
transition to a net-zero and climate resilient society and economy. It is expected that, as a
75

Page 76

6 
public body, the council leads by example and uses its role to influence area-wide climate
change action and sustainability.  The Sustainable Development and Climate Change
Strategy 2022 – 2027 and action plan sets out how the council aims to develop
sustainably and tackle climate change. 
Local Development Plan (LDP) The council has started preparation of its next
Local Development Plan which will set out the spatial strategy for the area while at the
same time helping deliver the key priorities in the Council Plan and SDCC Strategy. The
LDP will reflect the outcomes for the planning system set out in National Planning
Framework 4, and in particular seek to encourage, promote and facilitate development
that addresses the global climate emergency and nature crisis. The overarching theme of
the Plan will be to reduce, minimise, or avoid greenhouse gas emissions, guide
development to, and create sustainable locations. Other actions will include supporting the
implementation of Local Living principles (so that the main needs of, and service provision
for, communities are met locally) and encouraging measures to facilitate sustainable
transport and active travel; while at the same time ensuring there is a Just Transition
approach to meeting net zero targets.   
At the same time, the Planning Service will continue to support inward investment across
all commercial sectors including new housebuilding and employment opportunities. New
development will be directed to the right locations and will be expected to meet the
principles of placemaking. A Placemaking guide will be produced this year which will
highlight the key design principles proposals that developers should follow. 
The Planning Service will work closely with colleagues in Housing Services to help deliver
the council’s own housebuilding programme. 
The implementation of changes to the Building Regulations in 2024 in relation to the
energy performance of buildings will also be a focus for 2024/25. 
2.7. Circular Economy The Scottish Government has consulted on proposals for a
Route Map to deliver a circular economy in Scotland (Delivering Scotland’s circular
economy: A Route Map to 2025 and beyond), and on proposals for legislation in a Circular
Economy Bill.  The proposed Route Map will set out how we will reach 2025 waste and
recycling targets and achieve a long-term goal of net zero by 2045.  The outcome of this
consultation will influence the decisions the council makes over the next 5 – 10 years. 
2.8. Health and Wellbeing This is a cross-cutting theme within Community and
Enterprise Resources and covers a wide range of activities, from promoting healthy eating
(via the provision of school meals), to the positive contribution that our partners SLLC
make in ensuring inclusive access to sport, leisure and culture across our communities.  
Community and Enterprise Resources will assist SLLC in the provision of these services
by continuing to oversee capital investment in the council’s leisure and culture facilities:
the new build of Larkhall Leisure Centre over the next three to four years will be a major
project for the Resource, as will be the implementation of the council’s £13m Leisure and
Culture Transformation Fund which will help modernise the leisure and culture estate,
optimise use of the leisure and culture assets and assist in the transition towards net zero. 
The environmental health service promotes health protection practices and regulates
public health across South Lanarkshire.  Access to good quality greenspace and safe and
accessible active travel routes are also a key priority for the resource, encouraging
physical exercise and improving the wellbeing of our communities. 
The continuing preparation of the council’s Open Space Strategy will contribute to
achieving these aims.  It should be noted that each of these themes are identified as
76

Page 77

7 
matters in National Planning Framework 4.  In turn the preparation of the council’s Local
Development Plan 3 will seek to address these issues in a local context 
2.9.  Legislative and Policy Changes New and revised legislation will also impact on
the work of the resource during 2024-25, including: 
Climate Change Act (2019) – Whilst not new legislation, the Climate Change Act (2019)
continues to impact on the council’s activities and commits Scotland to net-zero
greenhouse gas emissions by 2045.  
The Climate Change (Scotland) Act states that a public body must:
➢ contribute to the delivery of Scotland’s national emissions reduction targets
➢ help deliver Scotland’s statutory climate change adaptation programme, and
➢ act in a way that it considers is most sustainable
It is anticipated that the Scottish Government will publish an updated draft Climate
Change Plan in 2024 that will set out how Scotland will achieve emission reductions
between 2024-2040 and which will influence the council’s resource and service planning. 
Transport (Scotland) Act 2019 This act is designed to help make Scotland’s transport
network cleaner, smarter and more accessible. The Act deals with a number of issues
including National Transport Strategy (NTS), Prohibition of Pavement Parking, Bus
Services, Roadworks, Workplace Parking and Low Emission Zones.  
➢ Transport Strategy The published NTS sets out the vision of Scotland’s Transport
System with a vision underpinned by priorities to reduce inequalities, take climate action,
help deliver inclusive economic growth and improve our health and wellbeing. The
council’s next Local Transport Strategy (LTS) is currently being developed with
publication expected early in 2024.  Policies and actions are drafted taking cognisance
of the Regional and National Transport Strategies.
➢ Strathclyde Partnership for Transport (SPT) have also recently published their Regional
Transport Strategy.  Several themes are highlighted relating to public transport,
managing travel needs, active travel, integration of travel, road safety, sustainable travel,
climate resilience, environment and connecting places.
➢ Pavement Parking A key provision of the Act is to prohibit the parking of vehicles on
pavements, prohibit double parking and prohibit parking adjacent to dropped
footways. The final legislative process has concluded, and guidance has been issued to
local authorities and we are now working towards completing back-office function
upgrades to allow enforcement to take place as well as concluding a review of streets
where there could be exemptions. Significant resources will be required for the
promotion of any associated traffic regulation orders and signage / road markings. 
Notwithstanding this we are anticipating beginning enforcement actions later in 2024. 
This will include an initial “soft” approach where drivers will be advised they are
committing an offence and a short period thereafter, Penalty Charge Notices will be
issued.
➢ 20mph speed limits Scotland’s Road Safety Framework to 2030 is committed to
creating a safer, healthier and greener Scotland. It is our aspiration to introduce
mandatory 20mph speed limits within residential areas in line with the new Scottish
Government policy. An assessment study of approximately 6000 streets is ongoing and
the outcome will shape the delivery of 20mph speed limits across South Lanarkshire. 
Significant resources will be required for the promotion of associated traffic regulation
orders and signage.
➢ Bus Services The Act provides local transport authorities with powers to make bus
travel more attractive, allowing local transport authorities to run their own bus services;
franchise bus services in their areas; or enter into Bus Services Improvement
Partnerships (BSIPs) with bus operators within their areas. The Act also introduces new
regulations covering the way in which bus operators must provide information to local
authorities when they plan to reduce or withdraw the services they provide.  Strathclyde
77

Page 78

8 
Partnership for Transport are currently taking forward a Regional Bus Strategy and on
completion this will allow consideration of what opportunities there are for these types of
measures as well as the Act’s other section which relates to smart ticketing options.
These provisions will have significant employee and financial resourcing issues.
➢ Roadworks The Act seeks to continually encourage a raise in standards to improve the
quality of road works.  The key provisions include additional powers given to the Scottish
Road Works Commissioner to strengthen enforcement on non-compliance of legislation
in relation to road works with the use of fines and monitoring, a requirement for all
undertakers to have a Reinstatement Quality Plan (RQP) in place, a revised timescale
for notifying within 2 hours of the commencement and completion of works and a revised
Specification for the Reinstatement of Opening in Roads (SROR) is now in force
increasing the guarantee period for the majority of asphalt reinstatements to 6 years.
➢ Others The Act also enables local authorities to manage vehicle emissions via the
establishment of Low Emission Zones (LEZ) however, there are no plans at this time to
introduce these in South Lanarkshire. 
Free School Meals Roll Out – the Scottish Government is committed to extending free school
meal provision to pupils in P6 and P7, with stage 1 extending free school meals to those pupils
in P6 and P7 in receipt of the Scottish Children payment.  There will be a phased roll out of free
school meals to children and young people in primary 6 and 7 who are in receipt of the Scottish
Child Payment beginning in February 2025 to be completed by August 2026. 
EU Food Imports - phased implementation of checks on EU food imports were due to
commence in 2021 and implementation has been delayed by UK Government.  Food Standards
Scotland (FSS) has indicated new Border Control Points in Scotland will not be ready and
operational, which could require inland (point of destination) import controls. The central
location and good transport links of South Lanarkshire is likely to mean the council will be asked
to carry out import controls. It is not possible to quantify the potential increase in workload at
this time and could lead to a reprioritisation of work during 2024-25. 
78

Page 79

9 
Section Three – Resource Outcomes 
3.1. Resource Outcomes
Community and Enterprise Resources has established the following Resource outcomes
to support the delivery of Connect Outcomes in 2024-25. 
Connect
Outcomes Resource Outcomes  
Communities and
Environment 
• High-quality streets, parks and other public areas ensures South
Lanarkshire is a place where people want to live, work, visit and invest
• Communities are encouraged and supported to reduce, re-use and recycle
their waste
• The council addresses climate change by reducing carbon emissions,
protecting our natural environment, adapting to the impacts of climate
change, and acting sustainably
• Communities are well connected 
• All roads, footways, cycle routes, bridges and associated infrastructure are
safe and fit for purpose
• Road and transportation infrastructure supports new development, enables
use of public transport and encourages active travel
• The 20-minute neighbourhood principle is established in our communities to
make our places more sustainable and liveable.
Education and
Learning 
• No resource outcomes for this Connect outcome 
Health and
Wellbeing 
• Public health is safeguarded through an effective environmental regulation
and enforcement service
• All school and nursery children have access to nutritious school meals 
• Health inequalities are addressed through collaboration with local
communities and partners
• All residents have the opportunity to access cultural, leisure and outdoor
recreational activities to help improve their wellbeing and quality of life
Children and
Young People 
• No resource outcomes for this Connect outcome 
Housing and
Land 
• Vacant, derelict and contaminated land is brought back into productive use
• Appropriate supply of housing land (including affordable housing) is
maintained
Our Economy  • South Lanarkshire is an attractive place to start, grow and locate a business
• Economic development and growth in South Lanarkshire is fair, inclusive,
sustainable and low carbon
• Thriving town and neighbourhood centres provide a focal point for local
communities 
• Physical development and land use in the area is enabled, guided and
controlled to help facilitate economic growth  
• Consumers and communities are protected through an effective trading
standards service 
• A people-centred approach to recovery is implemented to help individuals,
communities, businesses and the social and third party sector thrive 
79

Page 80

10 
3.2. Delivering the Plan and achieving Best Value
In working towards the six Outcomes, the council will continually improve and ensure
effective and efficient use of resources, and our business will be conducted with integrity,
transparency and will operate to the highest standards. 
Community and Enterprise Resources has established the following Resource Outcomes
to support Delivering the Plan and achieving Best Value. 
Delivering the
Plan and
achieving Best
Value
• The council demonstrates high standards of governance and sound
financial stewardship
• Customers experience high quality and improving council services
• The workforce has the skills, flexibility and capacity to deliver the council’s
outcomes
• Digital and ICT services meet the needs of the council and its customers 
80

Page 81

11 
Section Four – Measures and actions 
4.0. Performance measures and action plan 
This section of the Resource Plan is divided into two parts: part (a) sets out our main
performance measures against our outcomes; and part (b) describes the key actions we
will take in the coming year to respond to the challenges ahead and improve services and
outcomes. 
4.a  How we will measure our performance
The impact of COVID-19 continues to have an effect on performance of some services.
The table below shows our performance measures, and includes the actual data last
reported to Committee and the targets for both the last financial year and 2024-25. 
Additional context for the results/targets is provided within the notes column, where
applicable. 
Resource Outcome: High-quality streets, parks and other public areas ensures South Lanarkshire
is a place where people want to live, work, visit and invest
Measure 2022-23
Actual
2023-24 
Target
2024-25
Target
Links Service Notes
1. Percentage of
streets found to be
acceptable during
Litter Monitoring
System surveys.      
(Locally set target)
92% More than
92%
More than
92%
01.09 Facilities,
Waste and
Grounds 
2. Land Audit
Management
System grounds
maintenance score.      
(Locally set target) 
72.0 72.0 72.0 C01.09 Facilities,
Waste and
Grounds
72 is still a
challenging
target score
that the
Service strives
to meet       
Resource Outcome:  Communities are encouraged and supported to reduce, re-use and recycle
their waste
Measure 2022-23
Actual
2023-24
Target
2024-25
Target
Links Service Notes
3. Percentage of total
household waste
that is recycled in
the calendar year
2023.      
(Locally set target)
41.2%
(2022)
50% 50% C01.14 Facilities,
Waste and
Grounds 
4. Percentage of
household waste
sent to landfill in the
calendar year 2023.      
(Locally set target)
1.84%
(2022)
Less than
10%
Less than
5%
C01.06 Facilities,
Waste and
Grounds 
81

Page 82

12 
Resource Outcome:  The council addresses climate change by reducing carbon emissions,
protecting our natural environment, adapting to the impacts of climate change, and acting sustainably
Measure 2022-23
Actual
2023-24
Target
2024-25
Target
Links Service Notes
5. Reduction in the
council’s carbon
emissions in 2024-
25 (buildings, waste,
transport etc.)
compared to 2019-
20.      
(Locally set target)
TBC Less than
20%
Less than
20%
C01.13 Enterprise and
Sustainable
Development 
Resource Outcome:  Communities are well connected
Measure 2022-23
Actual
2023-24
Target
2024-25
Target
Links Service Notes
6. Percentage of
properties with
Superfast
Broadband
>30Mbps.      
(Locally set target)
97.3% 99% 99% C01.07 Enterprise and
Sustainable
Development 
7. Percentage of
properties with Full
Fibre connection. 
(Locally set target)
32.6% 33% 52% 01.07 Enterprise and
Sustainable
Development 
Resource Outcome: All roads, footways and bridges and associated infrastructure are safe and fit for
purpose
Measure 2022-23
Actual
2023-24
Target
2024-25
Target
Links Service Notes
8. Percentage of our
road network that
should be
considered for
maintenance
treatment (Roads
Condition Index).      
(Locally set target)
30.8%
(2021-
2023)
Less than
30.8%
Less than
31.9%
C01.10 Roads,
Transportation
and Fleet
Target:
improvement
on the
previous year
9. Number of road
casualties in South
Lanarkshire during
2024.      
(Locally set target)
284
(2022)
Less than
284
Less than
370
C01.01 Roads,
Transportation
and Fleet
Target:
improvement
on the
previous year 
Resource Outcome:  Public health is safeguarded through an effective environmental regulation and
enforcement service
Measure 2022-23
Actual
2023-24
Target
2024-25
Target
Links Service Notes
10. Broad compliance
with food law
statutory
requirements
secured in
premises. (Locally set
96.0% 85.0% 85.0% C01.11 Planning and
Regulatory
Services
Target to
remain at
85% since
the council is
not in direct
control of the
82

Page 83

13 
Resource Outcome:  Public health is safeguarded through an effective environmental regulation and
enforcement service
Measure 2022-23
Actual
2023-24
Target
2024-25
Target
Links Service Notes
target) measure.
Compliance
is the
responsibility
of the
business.       
Resource Outcome: All school and nursery children have access to nutritious school meals 
Measure 2022-23
Actual
2023-24
Target
2024-25
Target
Links Service Notes
11. Level of primary
school meal uptake
(as proportion of to-
tal primary school
meals which could
be taken up over the
period).      
(Locally set target)
66% 60% 66% 03.03 Facilities,
Waste and
Grounds
Target of
66% remains
challenging
12. Level of secondary
school meal uptake
(as proportion of
total secondary
school meals which
could be taken up
over the period).      
(Locally set target)
38% 38% 38% 03.03 Facilities,
Waste and
Grounds
Target of
38% still
remains
challenging       
Resource Outcome: South Lanarkshire is an attractive place to start, grow and locate a business 
Measure 2022-23
Actual
2023-24
Target
2024-25
Target
Links Service Notes
13. Number of new
South Lanarkshire
business starts
supported by
Business Gateway.      
(Locally set target)
520 500 500 C06.08 Enterprise and
Sustainable
Development 
14. Number of business
support
interventions per
annum by Economic
Development
(grants, loans or
advice).      
(Locally set target)
1,615 1,200 800 C06.08 Enterprise and
Sustainable
Development
2024-25
targets
reviewed in
line with
reduced
resources
available and
changes to
the Business
Gateway
Service now
being hosted
by North
Lanarkshire
Council.
83

Page 84

14 
15. Number of jobs
created or sustained
as a direct result of
Economic
Development
intervention.       
(Locally set target)
1,256 500 500 C06.08 Enterprise and
Sustainable
Development 
16. Increased value of
sales generated by
businesses as a
direct result of
Economic
Development
intervention.      
(Locally set target)
£13.11m £5m £5m C06.08 Enterprise and
Sustainable
Development
ERDF
funding has
been coming
to an end,
and whilst we
are still
seeing some
benefits
being
accrued in
recent years
from the
fund, going
forward,
there is less
certainty on
what can be
achieved
within
remaining
funds. It is
therefore
advisable to
keep the
target to £5m
for 2024/25. 
Resource Outcome: South Lanarkshire is an attractive place to start, grow and locate a business 
Measure 2022-23
Actual
2023-24
Target
2024-25
Target
Links Service Notes
17. Percentage of
procurement spend
on local enterprises     
(Locally set target)
18.1% 18% More than
2023-24
figure 
C06.11 Enterprise and
Sustainable
Development
2023-24 data
will not be
available
until the
Improvement
Service
calculate this
in July/
August 2024. 
Resource Outcome: Economic development and growth in South Lanarkshire is fair, inclusive,
sustainable and low carbon
Measure 2022-23
Actual
2023-24
Target
2024-25
Target
Links Service Notes
18. Delivery of UK
Shared Prosperity
Program      
(National target)
N/A £3m £6m 07.02 Enterprise and
Sustainable
Development
New
measure for
2023-24 
84

Page 85

15 
Resource Outcome: A people-centred approach to recovery is implemented to help individuals,
communities, businesses and the social and third sector thrives.
Measure 2022-23
Actual
2023-24 
Target
2024-25 
Target
Links Service Notes
19. Number of
participants
supported via
council-operated
employability
programmes (local
target)
1,687
People
1,350
people
1,500
people
C06.01 Enterprise and
Sustainable
Development
Target
increased to
1,500 to reflect
anticipated
additional
Scottish
Government
Funding to
support people
with long-term
health
conditions and
additional
support needs
to enter
employment
20. Number of
participants gaining
sustainable
employment (local
target)
584
People
675
people
700 
people 
C06.13 Enterprise and
Sustainable
Development
Target
increased to
700 to reflect
anticipated
additional
Scottish
Government
Funding to
support people
with long-term
health
conditions and
additional
support needs
to enter
employment 
21. Number of
participants
accessing further
education or training
(local target)
536
people
225
people
400
people
C06.02 Enterprise and
Sustainable
Development
Target
adjusted to
include youth
employability
participants
supported to
access further
education 
85

Page 86

16 
4.b What actions we will take in 2024-25
Resource Outcome: High-quality streets, parks and other public areas ensures South Lanarkshire is
a place where people want to live, work, visit and invest
Action  Milestones/steps we will take to deliver
our actions Links Service
1. Prepare an Open Space
Strategy in partnership with
Glasgow and Clyde Valley
Green Network Partnership
and other council services. 
Engagement on the findings following
analysis of the Open Space audit will be
carried out during Q2 and will in turn be
used to inform the evidence report for the
Local Development Plan 3. It is anticipated
that a draft Open Space Strategy will be
available early 2025 once the Gatecheck
of the Evidence Report has been
completed.
C01.09 Planning and
Regulatory
Services
2. To make South Lanarkshire
a cleaner place to live, work
and visit free of letter, fly-
tipping and dog waste
Prepare an annual progress report for
Climate Change and Sustainability
Committee in September 2024,
demonstrating the impact of the Litter
Strategy (2022-2027)
01.09 Facilities,
Waste and
Grounds 
Resource Outcome: Communities are encouraged and supported to reduce, re-use and recycle their
waste
Action  Milestones/steps we will take to deliver
our actions Links Service
3. Support a circular economy
by re-using, recycling and
generating energy from the
waste we manage
Complete the review of waste services
taking into consideration that the Deposit
Return Scheme (DRS) has been
postponed until October 2027 and the
outcome of the Circular Economy Bill
consultation
01.06 Facilities,
Waste and
Grounds 
Resource Outcome: The council addresses climate change by reducing carbon emissions, protecting
our natural environment, adapting to the impacts of climate change, and acting sustainably
Action  Milestones/steps we will take to deliver
our actions Links Service
4. Lead by example and
influence area-wide
climate change and
sustainability action 
Implement the Sustainable Development
and Climate Change Strategy (2022-2027)
Action Plan, and report progress at quarter
two and quarter four to Climate Change
and Sustainability Committee
C01.08 Enterprise and
Sustainable
Development
5. Ensure national planning
policy set out in National
Planning Framework 4 in
relation to climate change,
biodiversity and
sustainable travel is
embedded in decision
making process for
planning applications and
the preparation of the
South Lanarkshire Local
Development Plan 3 
Awareness sessions to be developed for
elected members, planning officers and
developers/agents by September 2024 
01.08 Planning and
Regulatory
Services 
86

Page 87

17 
Resource Outcome: The council addresses climate change by reducing carbon emissions, protecting
our natural environment, adapting to the impacts of climate change, and acting sustainably
Action  Milestones/steps we will take to deliver
our actions Links Service
6. Create the conditions for
the decarbonisation of the
council’s fleet 
Implement and review the Fleet Strategy
(2020-2025) Action Plan including reducing
in transport related emissions, through
converting the fossil fuelled small fleet to
full electric and trialling new fuel options for
the medium to heavy fleet as such
opportunities become commercially viable
01.13 Roads,
Transportation
and Fleet 
7. Deliver new and improved
low carbon vehicle
charging infrastructure
Maintain, manage and expand public
infrastructure points / hubs in line with
available internal and external funding
sources
01.13 Roads,
Transportation
and Fleet 
Resource Outcome: All roads, footways, cycle routes, bridges and associated infrastructure are safe
and fit for purpose
Action  Milestones/steps we will take to deliver
our actions Links Service
8. Prepare prioritised
programme of carriageway
and footway maintenance
works 
Deliver road safety projects and schemes in
line with agreed 2024-25 programme 
01.01 Roads,
Transportation
and Fleet 
9. Prepare prioritised
programme of bridge and
structure maintenance
works
Deliver a programme of bridge and other
structures projects in line with agreed 2024-
25 funding
01.01 Roads,
Transportation
and Fleet
10. Prepare prioritised
programme of traffic
signal and pedestrian/
cycle crossing
maintenance works
Deliver a programme of traffic signal and
pedestrian / cycle crossing upgrade projects
in line with agreed 2024-25 funding
01.01 Roads,
Transportation
and Fleet
11. Deliver winter
maintenance carriageway
and footway gritting
actions during inclement
weather
During adverse weather, undertake
appropriate precautionary actions and
during severe weather ensure main,
secondary and extreme routes are treated
as necessary
01.01 Roads,
Transportation
and Fleet
12. Deliver prioritised road
safety infrastructure
improvements and
promote road safety
Deliver road safety projects and schemes in
line with agreed 2024-25 programme
01.01 Roads,
Transportation
and Fleet 
Resource Outcome: Road and transportation infrastructure supports new development, enables use
of public transport and encourages active travel
Action  Milestones/steps we will take to deliver
our actions Links Service
87

Page 88

18 
Resource Outcome: Road and transportation infrastructure supports new development, enables use
of public transport and encourages active travel
Action  Milestones/steps we will take to deliver
our actions Links Service
13. Produce a new Local
Transport Strategy for
South Lanarkshire to
support the National and
Regional Transport
Strategy as well as the
provisions, where
appropriate, of the
Transport Scotland Act 
Draft Local Transport Strategy to be
presented to Committee in Autumn 2024
C01.10 Roads,
Transportation
and Fleet 
14. Deliver road and
transportation
infrastructure
improvements to support
new developments,
including those
undertaken as part of the
City Deal
Stewartfield Way and East Kilbride Town
Centre Project business case will be
prepared in 2024 
C01.10 Roads,
Transportation
and Fleet   
15. Encourage active travel by
extending our network of
walking and cycling routes 
Deliver walking and cycling projects/
schemes in line with agreed 2024-25 capital
programme 
01.10 Roads,
Transportation
and Fleet   
Resource Outcome: All school and nursery children have access to nutritious school meals 
Action  Milestones/steps we will take to deliver
our actions Links Service
16. Complete the roll out of free
school meals to all primary
children
All P6s and P7s to receive free school
meals in line with Scottish Government
timescales 
C03.03 Facilities,
Waste and
Grounds 
Resource Outcome: All residents have the opportunity to access cultural, leisure and outdoor
recreational activities to help improve their wellbeing and quality of life
Action  Milestones/steps we will take to deliver
our actions Links Service
17. Work in partnership with
South Lanarkshire Leisure
and Culture (SLLC) to
maintain and deliver
community facilities
Continue to review leisure and culture
community facilities, maintaining and
improving them through the Capital
Programme and Transformational Fund
03.03 Enterprise and
Sustainable
Development
18. Begin implementation of the
multi-year Play Area
Investment Programme
Undertake consultation with local
members and communities in Hamilton
area by March 2025 
03.03 Facilities,
Waste and
Grounds
Consultation exercise to be completed
with schoolchildren for Rutherglen and
Cambuslang before proceeding to design
stage and then putting these works out to
tender. Works to be completed in 2024 
88

Page 89

19 
Resource Outcome: Vacant, derelict and contaminated land is brought back into productive use 
Action  Milestones/steps we will take to deliver
our actions Links Service
19. Agree and implement
vacant and derelict /
contaminated land
programme
Implement projects approved within the
Vacant and Derelict Land Fund framework
agreed for 2024-25
05.04 Enterprise and
Sustainable
Development 
Resource Outcome: South Lanarkshire is an attractive place to start, grow and locate a business 
Action  Milestones/steps we will take to deliver
our actions Links Service
20. Prioritise business
development advice,
support and financial
assistance to ensure
businesses are able to
continue to operate, whilst
creating the right conditions
for low carbon economic
growth
Deliver programmes, services, and events
to businesses around sectors, location,
and themes (e.g., food and drink, tourism,
construction, low carbon, innovation,
internationalisation, collaboration, and
young enterprise)
06.03 Enterprise and
Sustainable
Development
Support and host the Supplier
Development Programme to deliver
events, training and e-commerce support
to SME’s or third sector organisations who
are interested in working with the public
sector 
06.09 Enterprise and
Sustainable
Development 
Resource Outcome: Economic development and growth in South Lanarkshire is fair, inclusive,
sustainable and low carbon
Action  Milestones/steps we will take to deliver
our actions Links Service
21. Promote sustainable
economic development
across South Lanarkshire 
Prepare an annual progress report for
Community and Enterprise Resources
Committee, demonstrating the impact of
the South Lanarkshire Economic Strategy
(2022-2027)
C06.05 Enterprise and
Sustainable
Development
22. Deliver the Levelling Up
Funded projects 
Delivery of the Levelling Up Fund grant
funded projects through the Clydesdale
Way and Shawfield Remediation with a
value of £6.7m in 2024-25
C06.05 Enterprise and
Sustainable
Development
23. Positively enhance the
benefits of tourism across
South Lanarkshire by
delivering the very best for
our visitors, our
businesses, our people, our
communities, and our
environment
Prepare an annual progress report for
Community and Enterprise Resources
Committee, demonstrating the impact of
South Lanarkshire Tourism Strategy
(2022-2025)
06.06 Enterprise and
Sustainable
Development
Begin the refresh of the South Lanarkshire
Tourism Strategy for 2025-2028
24. Champion the social
enterprise sector and invest
in start-up and growth of
our local social enterprise
Prepare an annual progress report on the
Social Enterprise Strategy approved in
May 2023 for Community and Enterprise
Resources Committee
06.03 Enterprise and
Sustainable
Development
89

Page 90

20 
Resource Outcome: Economic development and growth in South Lanarkshire is fair, inclusive,
sustainable and low carbon
Action  Milestones/steps we will take to deliver
our actions Links Service
25. Income generating projects
will be scoped across all
council resources to identify
viable projects with a focus
on green initiatives
including exploring options
for delivery and funding
Liaise with all council resources, third
parties and funders to identify new
opportunities for generating income and
consider a risk analysis of each
opportunity  
06.05 Enterprise and
Sustainable
Development
26. Develop single door ap-
proach to economic devel-
opment and inward invest-
ment activity which links
employment, skills, busi-
ness support and planning
Undertake activity (i.e. Lanarkshire
Business Events website / supports to
national themed weeks aimed at
increasing the number of companies
engaged with partners which lead to
improved performance and turnover,
increased employment, innovation,
investment and internationalisation
06.05 Enterprise and
Sustainable
Development
27. Consult with community
organisations and develop
a Rural Action Plan max-
imising existing and future
funding through Community
Led Local Development
and Renewable Energy
Fund 
Deliver the Rural Action Plan and report to
Rural Task Force in November 2024 
C05.13 Enterprise and
Sustainable
Development 
Resource Outcome: Thriving town and neighbourhood centres provide a focal point for local
communities 
Action  Milestones/steps we will take to deliver
our actions Links Service
28. Complete East Kilbride
Town Centre masterplan
and deliver initial actions to
enable the delivery of
realignment   
Negotiate and agree terms of masterplan
delivery programme.  Deliver early
projects to support programme of securing
change
C06.04 Enterprise and
Sustainable
Development
29. Complete Hamilton Town
Centre masterplan and
deliver initial actions to
enable the delivery of
realignment
Negotiate and agree terms of masterplan
delivery programme.  Deliver early
projects to support programme of securing
change
C06.04 Enterprise and
Sustainable
Development 
Resource Outcome: Customers experience high quality and improving council services
Action  Milestones/steps we will take to deliver
our actions Links Service
30. Implement the Frontline
First Fund
Identify and implement a programme of
projects to deliver the Frontline First Fund
07.01 Facilities,
Waste and
Grounds 
Resource Outcome: A people-centred approach to recovery is implemented to help individuals,
communities, businesses and the social and third sector thrives
90

Page 91

21 
Resource Outcome: A people-centred approach to recovery is implemented to help individuals,
communities, businesses and the social and third sector thrives
Action Milestones/Steps we will take to deliver
our actions
Links Service 
31. Deliver effective
Employability Services to
support individuals and
business
Monitor and adjust the delivery plan
agreed via the South Lanarkshire Local
Employability Partnership (SLLEP) and
Community Planning Partners
C06.10 Enterprise and
Sustainable
Development 
91

Page 92

22 
Section Five – Resourcing the Plan 
5.0. Introduction 
In this section we consider the resources needed to implement our plan, including funding
and staffing. 
5.1. Revenue Budget 2024-25
The resource has a Net Revenue Budget of £130.547 million for 2024-25. The table
below allocates this budget across the services:
. 
NET Budget by Service 2024-25
Detail £ million %
Facilities, Waste, and Grounds 79.833 61.2
Roads, Transportation and Fleet 18.775 14.3
Planning and Regulatory Services  5.249 4.0
Enterprise and Sustainable Development 4.952 3.8
South Lanarkshire Leisure and Culture Ltd 21.738 16.7
Detail 130.547 100 
5.2.     Capital Budget 2024-25 
The following capital budget of £31.638 million is allocated to the resource for 2024-25: 
Capital Programme 2024-25  
Approved
Council
Budget
Amendment
- Roads
Investment
Revised
Budget
after
Investment
Service £ million £ million £ million
Facilities, Waste, and Grounds 1.380   1.380
Roads, Transportation and Fleet 11.798 7.200 18.998
Planning and Regulatory Services   0   0.000
Enterprise and Sustainable Development  18.460   18.460
Total 31.638 7.200 38.838 
The council also approved an amendment to the Revenue Budget for 2024/2025, which
includes investment funding for Roads equating to a further £7.2million of capital funding.
92

Page 93

23 
5.3. Resource Employees
Community and Enterprise Resources has 3,428 employees, as at 12 February 2024. We
support these employees to deliver their duties through a range of policies, including
personal appraisal and a robust training framework. 
The number of employees by service is as follows: 
Service Number of
employees
Facilities, Waste, and Grounds 2,676
Roads, Transportation and Fleet 505
Planning and Regulatory Services  138
Enterprise and Sustainable Development 109
Total 3,428 
If you need this information in another language or format, please contact us to discuss how we
can best meet your needs. Phone 0303 123 1015 or email equalities@southlanarkshire.gov.uk 
93

Page 94

94

Page 95

Report
Agenda Item 
Report to: Community and Enterprise Resources Committee
Date of Meeting: 18 June 2024
Report by: Executive Director (Community and Enterprise
Resources)  
Subject: Community Benefit Funds – Renewable Energy Fund
Grant Applications 
1. Purpose of Report
1.1. The purpose of the report is to:- 
 consider a grant application to Nutberry Windfarm Renewable Energy Fund (REF)
from Coal-Play Trust
 consider a grant application to Auchrobert Windfarm REF from Larkhall
Community Growers
 consider a grant application to Middle Muir Windfarm REF from Leadhills Golf Club
 consider a grant application to Kype Muir Windfarm REF from Outreach
Community Church
 consider 2 grant applications to Middle Muir Windfarm REF from the Rural
Development Trust
[purpose]
2. Recommendation(s)
2.1. The Committee is asked to approve the following recommendation(s):- 
(1) that a grant be awarded to Coal-Play Trust of up to £223,462.32 from the
Nutberry Windfarm Renewable Energy Fund (REF) to create a MUGA and a
skatepark with community seating and planting area;
(2) that a grant be awarded to Larkhall Community Growers of up to £30,000 from
the Auchrobert Windfarm REF to employ a development officer;
(3) that a grant be awarded to Leadhills Golf Club of up to £290,000 from the Middle
Muir Windfarm REF to construct a new clubhouse and storage facilities;
(4) that a grant be awarded to Outreach Community Church of up to £59,280 from
the Kype Muir Windfarm REF to employ facilitators and youth workers
specialising in youth mental health provision;
(5) that a grant be awarded to the Rural Development Trust of up to £181,679.15
from the Middle Muir Windfarm REF to upgrade and renew core paths around
Bellfield Road, Wallace Cave and Ponneil; and
(6) that a grant be awarded to the Rural Development Trust of up to £158,719.18
from the Middle Muir Windfarm REF to upgrade and create a new core footpath
from Coalburn to NCN74.
[recs]
3. Background
3.1. Since 2004, the Council has collected and administered Community Benefit funding
through the Enterprise and Sustainable Development Service. The Service is
responsible for securing the contributions from windfarm developers, advising
potential applicants, assessing applications and monitoring projects to ensure that the
community benefits associated with each project are delivered. Processes are
6
95

Page 96

continuously reviewed to ensure best practice in grant provision and monitoring is
undertaken to ensure the necessary support is delivered to eligible communities. 
3.2. Grant awards above £20,000 require approval from Committee.  Awards below this
level are approved by the Head of Enterprise and Sustainable Development under
delegated authority. All grants awarded are reported annually to the Community and
Enterprise Resources Committee.   
3.3. Several changes were made to the REF criteria at the Community and Enterprise
Resources Committee of 6 February 2024 including supporting revenue funding,
increases to intervention levels and aiming to deliver larger more strategically
impactful projects. 
4. Grant Recommendation
4.1. Application Number 1077 
Coal-Play Trust– project value £298,462.32 
Proposed Grant award £223,462.32 intervention rate of 75% 
The proposed grant of £223,462.32 will be funded from Nutberry Windfarm which
contributes into the REF 
4.2. Coal-Play Trust (CP) is a community group with its purpose being:- 
To enhance cohesion through leisure and sporting opportunities within the community.
To provide a safe environment for all the family to enjoy and interact with others
through outdoor activities, sport and recreation. 
4.3. CP has a 7-member management committee with 60 regular volunteers.   Outdoor
activities have been a reoccurring theme within the community action plan for the area
of Coalburn.  Consultation has been undertaken with the community and the project
has been developed to reflect their views. 
4.4. The grant will allow CP to redevelop and enhance the Council owned disused tennis
court area within Coalburn, which will promote healthy leisure and recreation time
activities. 
4.5. The project requires capital funding to meet the cost to create a MUGA and skatepark
area with community seating for all to enjoy.  The Council’s grounds maintenance team
will maintain the area and footpaths. The project will be managed by the Council’s
landscape design team. A partnership agreement between the Council and CP will be
entered on successful funding award. 
4.6. The project has been established in response to community demand which will create
a new community space and encourage leisure activities and promote inclusion. 
4.7. The application has been assessed and scored an average of 36.5 out of 53
supporting a grant award of up to £233,462.32 totalling 75% of eligible costs. 
4.8. All Renewable Energy Fund awards are subject to suitable match funding being
secured. The REF grant sought is 75% of the project value with the match funding as
set out below. 
96

Page 97

Funder Stage Value
Dalquandy Wind Farm To be confirmed £25,000
Cumberhead Wind Farm To be confirmed £25,000
Galawhistle Wind Farm To be confirmed £25,000
SLC Renewable Energy Fund Grant
(75%) Nutberry. 
For approval £223,462.32
Total project value   £298,462.32 
4.9. The project is scheduled to commence in July 2024 and be complete by March 2025.
Officers will work with the applicant to monitor progress and any impact on the
timescales. 
4.10. The lead in time to the project start date of July 2024 will allow officers to confirm
match funding has been secured. 
5. Grant Recommendation
5.1. Application Number 1092 
Larkhall Community Growers – project value £65,000 
Proposed grant award £30,000 intervention rate of 46% 
The proposed REF grant of £30,000 will be funded from Auchrobert Windfarm which
contributes into the REF 
5.2. Larkhall Community Growers (LCG) is an established community group with its
purpose being: - 
To promote and advance education, health, community development, environment
and provide recreational facilities while organising leisure activities which are inclusive
of all members of the community through access to community garden, tools,
materials, workshops and resources to cultivate fresh produce and associated
activities. Using the gardens as a place where the community can come together to
work and socialise. 
5.3. LCG management committee has 3 members, 20 volunteers and one full-time and
three part-time staff. LCG’s seek support to deliver a strategic approach to
regeneration in Larkhall.   
5.4. The grant will allow LCG to recruit and employ a development officer to progress on
what has already been achieved relying mainly on voluntary capacity, which is
testimony to the drive and commitment that exists within the local community.
However, funding is required to build on this momentum, as well as increasing
resilience, sustainability and to move to the next stage in their development. 
5.5. The project requires revenue funding to meet the cost to employ a development officer
whose key priorities will be defined from the community survey to engage with the
specific public authorities and ensure opportunities for development and improvement
are created and developed. 
5.6. The project has been established in response to community demand and discussion
with SLC’s Communications and Strategy Service, to ensure community development
continues for the Larkhall and surrounding areas citizen. 
5.7. The application has been assessed and scored an average of 33.5 out of 53
supporting a grant award of up to £30,000 totalling 46% of eligible costs. 
97

Page 98

5.8. All Renewable Energy Fund awards are subject to suitable match funding being
secured. The REF grant sought is 46% of the project value with the match funding as
set out below.  
Funder Stage Value
Shared Prosperity Fund  To be confirmed £35,000
SLC Renewable Energy Fund Grant
(46%) Auchrobert
For approval £30,000
Total project value   £65,000 
5.9. The lead in time to the project start date October 2024 will allow officers to confirm
match funding has been secured. 
6. Grant Recommendation
6.1. Application Number 1095 
Leadhills Golf Club – project value £440,357.78   
Proposed Grant award £290,000 intervention rate of 66% 
The proposed grant of £290,000 will be funded from Middle Muir Windfarm which
contributed to the REF. 
6.2. Leadhills Golf Club (LGC) is a community group with its purpose being: - 
To promote and encourage the sport of golf without any distinction of sex, colour,
nationality or of political, religious or other opinions.
The club is a non-profit making organisation with all profits and surpluses being used
to maintain and improve the club facilities. 
6.3. LGC has a 12-member management committee with 52 members.  The project is a
proven community asset. LGC has held two open evenings, gaining ideas and
aspirations from the community in support of the project. The project has been
developed to reflect the views of the community it represents. 
6.4. The grant will allow LGC to rebuild the club house and install a storage unit to house
golf course machinery and equipment.   
6.5. The project will be managed by an architect and quantity surveyor overseen by LGC
committee chair. Investment in the club house will help build on tourism for Leadhills
and surrounding areas, supporting other local businesses. 
6.6. The project has been established in response to community demand which will create
a new community space and encourage leisure activities and promote inclusion. On
completion, the facility will be available to the wider community which will be able to
accommodate up to 25 people.  Currently the golf club is used by dog walking and
dark sky groups and on completion will be able to host footgolf and golf parties.      
6.7. The application has been assessed and scored an average of 36.5 out of 53
supporting a grant award of up to £290,000 totalling 66% of eligible costs. 
6.8. All Renewable Energy Fund awards are subject to suitable match funding being
secured. The REF grant sought is 66% of the project value with the match funding as
set out below. 
98

Page 99

Funder Stage Value
SSE Development Fund Confirmed £40,000
SLC SSE Clyde Windfarm Fund To be confirmed £110,357.78
SLC Renewable Energy Fund Grant
(66%) Middle Muir
For approval £290,000
Total project value   £440,357.78  
6.9. The project is scheduled to commence in August 2024 and be complete by March
2025. Officers will work with the applicant to monitor progress and any impact on the
timescales. 
6.10. The lead in time to the project start date August 2024 will allow officers to confirm
match funding has been secured. 
7. Grant Recommendation
7.1. Application Number 1068 
Outreach Community Church – project value £59,280 
Proposed grant award £59,280 intervention rate of 100% 
The proposed REF grant of £59,280 will be funded from Kype Muir Windfarm which
contributes into the REF 
7.2. Outreach Community Church (OCC) based in Strathaven is an established charity with
its purpose being: - 
To connect with the community and provide help and support to those who need it, in
a wide variety of formats and activities. The charity run youth events, autism &
additional educational needs support groups, peer support groups, and have an on-
site contemporary community coffee house. They also work in partnership with local
community groups such as the Community Council and the Round Table to support
and dovetail into existing community events and activities. 
7.3. OCC management committee has 5 members, 50 volunteers, three full-time and four
part-time staff.  Previous success of similar projects bolstered by many personal
testimonies of the help and unique support the peer groups offer. Discussions with
local bodies (Community Council, MSP's) and the local academy Head Teacher all
support the need and success of youth peer support. 
7.4. The grant will allow LCG to recruit and employ two professional facilitators and 2 youth
workers for the delivery of a weekly youth peer support programme over a 3-year
period and include one to one counselling. 
7.5. The project requires revenue funding to meet the cost to employ the facilitators, youth
workers, suitable hall hire and refreshments to host a three-year programme. Over the
3-year period this equates to 150 weeks X 50 young people supporting 7,500 people
weeks. It should be noted that some of the same young people will be receiving
support for the whole 3-year period.   
7.6. The project has been established in response to community demand, to continue
providing peer support groups, to address mental health issues for youths in the town
of Strathaven and surrounding area supporting P7 to S6 aged youths. They currently
have around 50 in attendance weekly. Peer support provides an opportunity to equip
and educate people with life skills to enable them to face life's challenges more
confidently. 
99

Page 100

7.7. The application has been assessed and scored an average of 29.5 out of 53
supporting a grant award of up to £59,280 totalling 100% of eligible costs. Strathaven
is one of the villages where through changes made at the February 2024 Community
and Enterprise Resources Committee 100% grants can be approved where good
projects have difficulty on securing match funding. 
7.8. The REF grant sought is 100% of the project value as set out below.  
Funder Stage Value
SLC Renewable Energy Fund Grant
(100%) Kype Muir
For approval £59,280
Total project value   £59,280 
7.9. The project is scheduled to commence in June 2024 and be complete by April 2027.
Officers will work with the applicant to monitor progress and any impact on the
timescales. 
8. Grant Recommendation
8.1. Application Number 1089 
Rural Development Trust – project value £386,679.15 
Proposed Grant award £181,679.15 intervention rate of 47% 
The proposed grant of £181,679.15 will be funded from Middle Muir Windfarm which
contributes into the REF 
8.2. Rural Development Trust (RDT) is a Charity with its purpose being: - 
To develop and deliver projects which tackle rural issues and improve life for residents
of rural communities. They have been involved in a variety of projects in recent years
and undertake a range of work including community capacity building, local energy
provision and community transport. 
8.3. RDT has a 7-member management committee, 20 regular volunteers, one full-time
and three part-time staff.  Connectivity and travel is at the forefront of the community
action plan for the Coalburn area.  Consultation with the community has been
undertaken and the project has been developed to reflect the views of the community
it represents. 
8.4. The grant will allow RDT to progress a partnership project involving Coalburn Miners
Welfare, Coalburn Community Action Group, South Lanarkshire Council, landowners
and other stakeholders, to create an active travel route from Coalburn to Poneil,
helping rural communities to safely connect.   
8.5. The project requires capital funding to upgrade the core path section from Bellfield
Road to Wallace Cave and from Poneil back towards the Wallace Cave area. The
central section of this core path is largely impassable to only the fittest of walkers and
cyclists.   A new section will be created to bypass this route with the new section
providing a high quality direct and off-road route. The end point of this path at Poneil
is on road access which leads to the NCN74. The path also connects and supports
the Clydesdale Way project.  Please refer to Appendix 1 which identifies the route
map. 
8.6. RDT's Project Officer will project manage all aspects of the project. This includes
procurement and management of the contractor, ongoing landowner and liaison with
the Council.   
100

Page 101

8.7. The project has been established in response to community consultation which will
create a new pathway section and upgrade existing pathways, encourage leisure
activities and connectivity within the communities. 
8.8. The application has been assessed and scored an average of 39 out of 53 supporting
a grant award of up to £181,679.15 totalling 47% of eligible costs. 
8.9. All REF awards are subject to suitable match funding being secured. The REF grant
sought is 47% of the project value with the match funding as set out below. 
Funder Stage Value
Ian Findlay Path Fund  Confirmed £100,000
Mainshill Trust (SLC)  Confirmed £105,000
SLC Renewable Energy Fund Grant
(47%) Middle Muir
For approval £181,679.15
Total project value   £386,679.15  
8.10. The project is scheduled to commence in September 2024 and be complete by April
2025. Officers will work with the applicant to monitor progress and any impact on the
timescales. 
8.11. The lead in time to the project start date September 2024 will allow officers to confirm
match funding has been secured. 
9. Grant Recommendation
9.1. Application Number 1090 
Rural Development Trust – project value £258,719.18 
Proposed Grant award £158,719.18 intervention rate of 61% 
The proposed grant of £158,719.18 will be funded from Middle Muir windfarm which
contributes into the REF 
9.2. Rural Development Trust (RDT) is a Charity with its purpose being: - 
To develop and deliver projects which tackle rural issues and improve life for residents
of rural communities. They have been involved in a variety of projects in recent years
and undertake a range of work including community capacity building, local energy
provision and community transport. 
9.3. RDT has a 7-member management committee, 20 regular volunteers, one full-time
and three part-time staff.  Connectivity and travel are at the forefront of the community
action plan for the Coalburn area.  Consultation with the community has been
undertaken and the project has been developed to reflect the views of the community
it represents. 
9.4. The grant will allow RDT to progress a partnership project involving Coalburn Miners
Welfare, Coalburn Community Action Group, South Lanarkshire Council, landowners
and other stakeholders, to create an active travel route from Coalburn to NCN74,
helping rural communities to safely connect. 
9.5. The project requires capital funding to create a new section and upgrade the core path
section. Currently there is a missing link between Coalburn and the NCN74 which will
require a completely new path. This will create the most direct and safe route between
Coalburn and Lesmahagow. It will include core path and various other sections
including the former railway Line to Lesmahagow. All sections will require upgrading
101

Page 102

to the surface needed to form a two-metre-wide active travel route from the end point
near Auldton. Please refer to Appendix 2 which identified the route map. 
9.6. RDT's Project Officer will project manage all aspects of the project. This includes the
procurement and management of contractor, ongoing landowner and Council liaison. 
9.7. The project has been established in response to community consultation which will
create a new pathway section and upgrade existing pathways, encourage leisure
activities and connectivity within the rural communities. 
9.8. The application has been assessed and scored an average of 40 out of 53 supporting
a grant award of up to £158,719.18 totalling 61% of eligible costs. 
9.9. All Renewable Energy Fund awards are subject to suitable match funding being
secured. The REF grant sought is 61% of the project value with the match funding as
set out below. 
Funder Stage Value
Ian Findlay Path Fund  Confirmed £100,000
SLC Renewable Energy Fund Grant
(61%) Middle Muir 
For approval £158,719.18
Total project value   £258,719.18  
9.10. The project is scheduled to commence in September 2024 and be complete by April
2025. Officers will work with the applicant to monitor progress and any impact on the
timescales. 
10. Employee Implications
10.1. There are no employee implications arising from this report. 
11. Financial Implications
11.1. The awards will come from Nutberry, Auchrobert, Middle Muir and Kype Muir
Windfarms which contribute to the REF. The Fund has sufficient resources to meet
the proposed grant award commitments detailed in this report. 
11.2. REF funding awards are subject to all other funding being secured.   
12. Climate Change, Sustainability and Environmental Implications
12.1. The projects will allow groups to continue to support the rural area by providing
leisure/sport activities and support outreach and development work.   
13. Other Implications
13.1. The risks associated with the project are focused on the potential for cost overruns,
delays to the projects or match funding not being secured. Work will continue with the
applicant to help ensure match funding is secured and that projects are delivered
broadly on time and within budget. 
14. Equality Impact Assessment and Consultation Arrangements
14.1 This report does not introduce a new policy, function or strategy and, therefore, no
impact assessment is required. 
14.2 Community consultation is a requirement for all REF grants awards.  Consultation can
be referenced through community action plans, independent consultation and social
media platforms.   
102

Page 103

David Booth 
Executive Director (Community and Enterprise Resources) 
23 May 2024 
Link(s) to Council Values/Priorities/Outcomes
Values
 Focused on people and their needs
 Working with and respecting others
Priorities
 We will work to put people first and reduce inequality
 We will work towards a sustainable future in sustainable places
 We will work to recover, progress, and improve
Outcomes
 Good quality, suitable and sustainable places to live
 Thriving business, fair jobs and vibrant town centres
 Caring, connected, sustainable communities
 People live the healthiest lives possible
 Inspiring learners, transforming learning, strengthening partnerships 
Previous References
 Community and Enterprise Resources Committee 6 Feb 2024 Renewable Energy Fund -
Strengthening Links to Rural Priorities. 
List of Background Papers
 Completed REF Grant Application Form for application number 1077
 Completed REF Appraisal Scoring Sheet for application number 1077
 Completed REF Grant Application Form for application number 1092
 Completed REF Appraisal Scoring Sheet for application number 1092
 Completed REF Grant Application Form for application number 1095
 Completed REF Appraisal Scoring Sheet for application number 1095
 Completed REF Grant Application Form for application number 1068
 Completed REF Appraisal Scoring Sheet for application number 1068
 Completed REF Grant Application Form for application number 1089
 Completed REF Appraisal Scoring Sheet for application number 1089
 Completed REF Grant Application Form for application number 1090
 Completed REF Appraisal Scoring Sheet for application number 1090 
Contact for Further Information
If you would like to inspect the background papers or want further information, please
contact: -
Colin McFarlane
Project Development Officer
Enterprise and Sustainable Development Services
E-mail:-  colin.mcfarlane@southlanarkshire.gov.uk 
103

Page 104

104

Page 105

Appendix 1
Coalburn – Douglas Path Upgrade 
6
105

Page 106

106

Page 107

Appendix 2
Coalburn – NCN74 Path Upgrade 
6
107

Page 108

108

Page 109

Report
Agenda Item 
Report to: Community and Enterprise Resources Committee
Date of Meeting: 18 June 2024
Report by: Executive Director (Community and Enterprise
Resources)  
Subject: Community Benefit Funds Kype Muir Windfarm:
Connect2Renewables Extension 
1. Purpose of Report
1.1. The purpose of the report is to:-
[p
 seek approval for the continuation of community benefits from Kype Muir Windfarm
to support the Connect2Renewables employability project
[1purpose]
2. Recommendation(s)
2.1. The Committee is asked to approve the following recommendation(s):-
[recs]
(1) that the funding support of the Connect2Renewables (C2R) programme, as
set out at paragraphs 4.4 and 4.5, be approved.
[1recs]
3. Background
3.1. The Kype Muir Windfarm was operated by Banks Renewables Ltd who are now
OnPath Energy and is located south of Strathaven, with an eligible funding area shown
in Appendix 1.   
3.2. The developer committed to provide a community benefit package equating to an
annual payment of £5,000 per MW of installed capacity. The windfarm comprises of
26 turbines of 3.4KW which in 2019 this generated a community benefit of £442,000
per annum. 
3.3. The developer agreed to apportion £1,875 per MW to South Lanarkshire Council (SLC)
and £3,125 per MW to Kype Muir Community Partnership (KMCP) an independent
community panel consisting of Sandford and Upper Avondale, Strathaven and
Glassford, Stonehouse, Lesmahagow and Blackwood and Kirkmuirhill (including
Boghead) Community Council areas. 
3.4. The Community and Enterprise Resources Committee of 3 September 2019 approved
the allocation of £82,875 or 50% of the Council’s community benefit income per annum
to the deliver C2R employability programme for an initial 5 years with the remaining
50% administered through the Council’s Renewable Energy Fund (REF) grants
programme. 
3.5. Banks Renewables along with KMCP agreed to contribute £138,125 per annum to
C2R resulting in an annual total budget of £221,000 per annum for a 5 year period
until 2024, thereafter subject to review.     
7
109

Page 110

3.6. The C2R employability programme provides skills development support to
unemployed people and/or individuals within the eligible area of the windfarm to gain
employment or study. The fund has been used for five categories of support:- 
 Employment incentive programme - where an employer receives a wage
subsidy for up to a year to employ someone from the local area.
 Pre employment support grant - a grant of up to £200 to help move people into
work and overcome barriers.
 Grant towards college living costs - a grant of £500 to anyone starting
college/university for the first time who needs additional support.
 Tailored funding - funding to remove barriers to college or employment and can
include contribution to such things as computer training, tools, PPE, driving
lessons or lifeguard training for the local leisure centre.
 Non-financial support from staff - this can include guidance and links to
partners and CV advice. 
3.7. The C2R employability programme is funded by 2 windfarms: Middle Muir and Kype
Muir covering different geographic areas. The Middle Muir funding commitment was
extended for 5 years at the Community and Enterprise Resources Committee of 6
February 2024. 
4. Connect2Renewables Continuation.
4.1. In early 2023, Banks Renewables commissioned a study on the outcomes of the
community benefit funds and specifically C2R which are summarised below. 
The number of people supported by the C2R employability fund
since 2019 
Kype Muir
Supported into a job through the employment incentive programme 45
Pre-employment support grant  44
Grant towards college living 140
Tailored financial support 24
Non-financial employment support  181
Totals people supported  433 
4.2. The study concluded that the initiative has been a success and has had significant
benefit to the target groups within the area. 
4.3. OnPath Energy (formerly Banks Renewables) and the Council’s Employability Service
believe the C2R programme has delivered good results and should continue. KMCP
has, however, indicated they wish to withdraw their contribution to the programme from
2024 onwards as they would prefer to have full control of their share of the budget (as
set out at paragraph 3.3) to award community grants and focus on projects raised
within local Community Action Plans. 
4.4. Following the agreement with OnPath Energy and the Council’s Employability Service,
it is proposed that the Kype Muir C2R programme is extended for a further 5 years to
the end of 2029 using only REF funding. 
4.5. The annual income to the SLC Community Benefit Fund from Kype Muir has risen to
£291,000 per annum and an allocation of 50% of this to C2R would be £145,500 per
annum.  This is a reduction in total funding to C2R in the Kype Muir area from £221,000
110

Page 111

per year to £145,500 per year, which the Employability Services has agreed is
manageable.   
4.6. The programme will continue to support unemployed people and/or individuals who
require support for skills development within the eligible area of the windfarm. The
programme will target early-stage employability activity with a particular focus on
disengaged and economically inactive residents with a focus on people experiencing
health related barriers and parents including those in low waged/part time jobs,
supporting families. The C2R programme will continue to develop and adapt and
compliment other Council and national support programmes and adaptations or
additional support will be undertaken in partnership with Banks Renewables and the
local communities. 
5. Employee Implications
5.1. There are no employee implications arising from this report.   
6. Financial Implications
6.1. There are no additional financial implications for the Council in managing the C2R
programme. 
7. Climate Change, Sustainability and Environmental Implications
7.1. The C2R programme complements sustainability aims, supporting local people into
local employment and supports local SME employers reducing transport to work
demands by delivering local services. Practical examples of this include, local people
being helped into local jobs on a dairy farm and the local Coalburn Leisure Centre.   
8. Other Implications
8.1. There are no other implications or risks arising from this report. 
9. Equality Impact Assessment and Consultation Arrangements
9.1. There was no requirement for consultation in terms of the information contained in this
report. 
9.2. The Council has consulted with OnPath Energy with regards to the future use of the
funds. OnPath Energy has undertaken a detailed consultation with local communities
regarding the success and outcomes of the C2R programme. Through this
consultation KMPC indicated their withdrawal of funding to C2R, however, OnPath
Energy is fully supportive of the C2R programme continuing. 
David Booth
Executive Director (Community and Enterprise Resources) 
28 May 2024 
Link(s) to Council Values/Priorities/Outcomes
Values
 Focused on people and their needs
 Working with and respecting others
 Accountable, effective, efficient and transparent
 Ambitious, self-aware and improving
 Fair, open and sustainable  
111

Page 112

Priorities
 We will work to put people first and reduce inequality
 We will work towards a sustainable future in sustainable places
 We will work to recover, progress and improve
Outcomes
 Our children and young people thrive
 Good quality, suitable and sustainable places to live
 Thriving business, fair jobs and vibrant town centres
 Inspiring learners, transforming learning, strengthening partnerships 
Previous References
 Community and Enterprise Resources Committee 3 September 2019, Community Benefit
Funds – New Contribution – Kype Muir Wind Farm
 Community and Enterprise Resources Committee 6 February 2024 – Community Benefit
Fund Middlemuir : Connect 2 Renewables extension 
List of Background Papers
 Executive Committee 3 March 2004, Community Benefit: Establishment of a Renewable
Energy Fund 
Contact for Further Information
If you would like to inspect the background papers or want further information, please
contact:- 
Kenny Lean Economic Development Manager (funding and rural) 
Ext:    (Tel: 07469027925 )
E-mail:  kenny.lean@southlanarkshire.gov.uk  
112

Page 113

113

Page 114

114

Page 115

Report
Agenda Item 
Report to: Community and Enterprise Resources Committee
Date of meeting: 18 June 2024
Report by: Executive Director (Community and Enterprise
Resources)  
Subject: South Lanarkshire Council Bereavement Services
Strategy 2024 to 2033 
1. Purpose of Report
1.1. The purpose of this report is to:- 
 seek endorsement for the Bereavement Services Strategy for South Lanarkshire
which will cover the period 2024 to 2033 
2. Recommendation
2.1. The Committee is asked to approve the following recommendation(s):- 
(1) that the Bereavement Services Strategy for South Lanarkshire 2024 to 2033
(Appendix 1) be endorsed;
(2) that the new crematorium service time pilot, as detailed in section 4.4, be
endorsed;
(3) that the new and harmonised charges, as detailed in sections 4.9 and 4.10, be
endorsed; and
(4) that the recommendations be referred to the Executive Committee on 26 June
2024 for approval. 
3. Background
3.1. South Lanarkshire Council operates a Bereavement Service that provides a dignified
and sensitive burial and cremation service. The key piece of legislation governing the
service is the Burial and Cremation (Scotland) Act 2016 which was passed by the
Scottish Parliament on 22 March 2016 and received royal assent on 28 April 2016.
The 2016 Act fulfils the commitment of the Scottish Government to implement the
recommendations made by: 
 The Burial and Cremation Review Group (2007)
 The Infant Cremation Commission (2014)
 The National Cremation Investigation (2016) 
3.2. In July 2016 a working group headed by the Scottish Government was formed to work
on the regulations of the Act and after prioritising Part 2 (Cremation) of the Act the
Cremation (Scotland) Regulations 2019 were introduced from 4 April 2019. 
3.3. Having been hampered by the COVID-19 pandemic a working group is still actively
working on the regulations for Part 1 (Burial) of the Act. The most recent activity has
been a consultation on the regulations which was completed in November 2023.  
8
115

Page 116

3.4. The Council’s first Cemetery Strategy was presented to the Community and Enterprise
Resources Committee on 30 May 2023 and has allowed the Council to implement a
strategic approach to the provision of burial ground within the authority area by:- 
 implementing a Cemetery Catchment area which provides area-based
measurements of lair availability and usage within each catchment
 expanding cemeteries
 increasing capacity within existing cemeteries by:-
o recovering underutilised space
o reclaiming burial rights in unused lairs 
3.5. The Cemetery Strategy set out a new strategic approach to recovering the rights of
burial for lairs that have not been used in the last 60 years. This approach prioritises
those cemeteries with no or limited capacity and work has commenced, with
information gathered on all lairs which fall into this category for Strathaven Cemetery
with on-site and lair holder verification now being finalised.  Legal advice has been
sought regarding how the Council should proceed when a lair owner is deceased with
initial letters issued to the last known address of the registered owner. 
3.6. Work is continuing with the Council’s Communications department to make best use
of the Council’s website and social media platforms to highlight the project and ensure
communications have maximum reach. It is expected this process will take a minimum
of one year, after which there may be available lairs within the cemetery once again. 
3.7. The Bereavement Strategy incorporates the previous work undertaken in the
Cemetery Strategy to include the Crematorium to deliver a long-term vision for the
Councils Bereavement Service. 
4. Bereavement Services Strategy – Key Points 
Crematorium Services
4.1. The Council provides its cremation services from South Lanarkshire Crematorium,
Blantyre. The facility opened in September 2006 and has seen an increase in annual
services from 1,164 in 2007 to 1,725 in 2022. Following the national trend the demand
for cremation services in South Lanarkshire has increased in comparison to burial
services:-    
2007  2022
Cremations 1,164 (49%)  1,725 (63%)
Burials 1,225 (51%)  1,011 (37%)  
4.2. This trend is set to continue along with the need to provide burial ground for the burial
of ashes rather than full coffin burials as the chart below demonstrates. 
116

Page 117

4.3. The crematorium operates with 3 different options of service times and an analysis of
the usage of the uptake of services has shown:-   
Service Type     % of uptake (2022)
 Full services (1 hour slot)  80%
 Half Services (30 minute slot) 22%
 Direct Cremation (no attendance) 5%  
4.4. Analysis of service usage has shown that the crematorium has unused capacity first
thing in the morning. It is not clear if there is a demand for services at this time,
however, it is proposed to offer a new type of morning service to establish if there is
an unmet need. The service would be offered at 8am and 8:15am and allow for music
for entry and exit, a short poem or eulogy and a maximum of 10 mourners. This would
add to the options available for a bereaved family and at a lower cost which recognises
the continued financial difficulties faced by many at the present time. It is hoped this
addition would increase the uptake of early services at the crematorium and would be
monitored for a trial period of 6 months. 
Crematorium Infrastructure
4.5. In terms of crematorium infrastructure, the cremators are now over 17 years old and
require regular repair as well as annual servicing. Recurring costs over the last 3 years
of over £300,000 are shown in the table below. In addition, major repairs and
replacements have been required over the last 3 years at a cost of over £180,000. The
service operates a financial sink fund, where any additional income generated is set
aside to re-invest in the ongoing maintenance requirements of the crematorium. The
cremators become less efficient over time and given their age it is likely they will
require to be fully replaced at some point over the next 5 years. Costs will be
significant, and the Service will work closely with Finance colleagues to plan well in
advance.  
Year Maintenance,
Servicing and
Repair Costs
Gas Electricity Water SEPA
Licence
Specialist
Waste
Removal
Total
2020 £34,830 £22,438 £16,128 £6,402 £3,502 £8,159 £93,479
2021 £35,714 £24,942 £16,875 £6,446 £3,542 £5,710 £95,250
2022 £29,525 £64,953 £17,866 £5,813 £3,648 £6,043 £129,871
Total £100,069 £112,333 £50,869 £18,661 £10,693 £19,912 £312,537  
117

Page 118

Item Cost
Replacement hearth £18,062
Replacement analyser £43,000
Rebrick £105,318
Replacement bag filter  £15,305
Total £181,685 
4.6. Future replacement of the cremators will provide the opportunity to consider larger
capacity to meet the increasing requirement for outsized coffins. Accommodating this
requirement at the present time reduces the number of services the crematorium can
deliver due to the operational impact on the individual cremators. In addition, modern
cremators operate using alternative fuel sources, including options for electric and
hybrid configurations that will contribute to the Council’s net zero commitments and
potentially reduce running costs. 
IT Modernisation
4.7. The current IT system used by the service has been in place since 2005 and provides
a database to store all information and scheduling around cremations, disposal
systems and memorials.  The system also provides similar functionality for cemeteries
and burials. Given the age of the system, it is limited in scope for development and
there is an inherent risk with the local storage of essential data. The service is aiming
to invest in a new cloud-based system to drive modernisation with the aim of:- 
 providing integrated mapping
 allowing remote access at site
 digitising existing paper-based processes and work instructions
 removing onsite data risk 
4.8. Soft market testing has suggested one off costs of such a system in the region of
£140,000, with an annual support fee of around £20,000. The Service is working with
colleagues in Finance, IT and Procurement to progress the project. 
Charging Framework
4.9. As the strategy highlights, operating costs for the Bereavement Service and the
Crematorium in particular continue to increase. The service has undertaken a review
of existing charges and benchmarked against comparators to ensure these are in line
with the current market. The review has identified 4 activities where the Council do not
currently charge where it is proposed to introduce a charge, these are shown in the
table below. The number of these requests received are not currently recorded,
therefore, it is not possible to estimate potential additional income. However, as a
minimum the introduction of a charge will likely lead to a reduction in requests that will
allow the service to focus on value adding activities. 
New Income Lines Current charge Proposed charge
Family Search/Genealogy £0.00 £25.00
Test Dig £0.00 £100.00
Memorial Work Permit £0.00 £45.00
Headstone Fixing £0.00 £150.00
118

Page 119

4.10. The review has also allowed the opportunity to harmonise charging across the
crematorium and cemeteries and these proposals are show in the table below with the
potential financial impact based on 2023/2024 demand and 2024/2025 charging. Any
additional income generated by the charging changes will be allocated to the
crematorium sink fund to offset future investment and expenditure. 
Stakeholder Engagement
4.11. The Council recognises the importance of the burial and cremation services provided
to the local community and is committed to the on-going and changing needs of the
bereaved and the wider community within South Lanarkshire. To ensure that the
Council to continues to meet that need, it is proposed to undertake the first broad
consultation on the service to include members of the public, funeral directors, clergy,
humanists and other celebrants and any other interested parties to identify areas for
development or improvement as part of the delivery of the strategy over the next
decade. 
5. Employee Implications
5.1. No employee implications as result of the contents of this report. 
6. Financial Implications
6.1. There are no immediate financial implications of the Bereavement Strategy, however,
as highlighted in section 4.5, the cremators will require to be replaced at some point
over the next 5 years. It is likely costs will be significant. In addition, it is estimated the
cost of upgrading existing and out of date IT systems will be in the region of £130,000. 
It is anticipated that the Crematorium Sink fund is used to cover costs where possible,
with a longer-term plan being considered to ensure funding is available for these
projects. 
6.2. New and harmonised charges are detailed in sections 4.9. and 4.10. The number of
these requests received are not currently recorded, therefore, it is not possible to
estimate potential additional income. The Service will monitor uptake of services
against the current budget. However, as a minimum the introduction of a charge will
likely lead to a reduction in requests that will allow the Service to focus on value adding
activities. 
7. Climate Change, Sustainability, and Environmental Implications
7.1. The Bereavement Services Strategy will support delivery of the Council’s Climate
change and Sustainable Development Strategy and progress more sustainable
options for delivery of services such as alternatives to coffin and burial provision and
woodland burials. 
7.2. The crematorium is fully abated (abatement is where the toxic gases are removed and
are not released into the atmosphere) and, therefore, has a low environmental impact
which is in line with the Council and the Resource’s commitment to sustainable
environment. 
Existing Service Lines Current
charge
Number
2023/2024 Total Proposed
charge
Estimate
2024/2025
Right of Burial
Crematorium £832.22 36 £29,959 £532.65 £19,175
Lair Memorial and 30
letters Incl in above -  £400.00 £14,400
Interment Fee
Crematorium £89.19 -  £284.91 £10,256
Total   £29,959  £43,831
119

Page 120

7.3. A screening determination was completed in relation to the Strategic Environmental
Assessment (SEA) which confirmed there is no need for a separate SEA for these
proposals. 
8. Other Implications
8.1. The Council’s obligations under the Fairer Scotland Duty and the Consumer Duty have
also been assessed in respect of these proposals. In terms of the Fairer Scotland Duty,
whilst this proposal is not a new strategy it is the introduction of four new charges for
services that are currently provided for free. The assessment does not anticipate a
negative impact on residents as two of the charges will primarily impact on businesses
and the other two are optional services. In terms of the Consumer Duty the
assessment is similar and for the same reasons. If requested by an elected member,
copies of the impact assessments are available from the report author. 
9. Equality Impact Assessment and Consultation Arrangements
9.1. An equality impact assessment (EQIA) has been undertaken during the development
of the proposals to identify and mitigate any negative impacts and seek opportunities
to promote equality. 
9.2. The assessment is that the proposals do not have any adverse impact on any of the
protected characteristics groups. 
9.3. A full consultation will be undertaken with members of the public, funeral directors,
clergy and other stakeholders to shape the strategic direction of the Service over the
coming years. 
David Booth
Executive Director (Community and Enterprise Resources) 
29 May 2024 
Link(s) to Council Values/Priorities/Outcomes
Values
 Focused on people and their needs
 Working with and respecting others
 Accountable, effective, efficient and transparent
 Ambitious, self-aware and improving
 Fair, open and sustainable
Priorities
 We will work towards a sustainable future in sustainable places
 We will work to recover, progress and improve
Outcomes
 Good quality, suitable and sustainable places to live
 Caring, connected, sustainable communities 
Previous References
 Community and Enterprise Resources Committee – 30 May 2023 
List of Background Papers
 None 
120

Page 121

Contact for Further Information
If you would like to inspect the background papers or want further information, please
contact: -
Kevin Carr, Head of Facilities, Waste and Grounds
Tel: 07788 351841
E-mail: kevin.carr@southlanarkshire.gov.uk
121

Page 122

122

Page 123

Facilities, Waste & Grounds Services 
Bereavement Services Strategy
2024 – 2033
8
123

Page 124

Contents 
Section  Title 
1.0    Introduction
2.0   Purpose and Vision
3.0   Legal Context
4.0   Demographic Context, Demand and Capacity
5.0   Crematorium Rules and Areas for Development 
6.0   Cemeteries Rules and Areas for Development
7.0   Infrastructure and Maintenance
8.0   Pricing Structure
9.0   Bereavement Services Strategy Short, Medium and Long Term
124

Page 125

1. Introduction
1.1 This ‘Bereavement Services Strategy’ is a strategic document which will assist the Council in
providing, maintaining, and managing its crematorium and cemeteries over the long term. This
strategy includes all aspects of the management and operation of the Council’s Bereavement
Services. 
1.2 Within Community and Enterprise Resources, Bereavement Services manage their cremation
service from South Lanarkshire Crematorium and all cemeteries within the South Lanarkshire
Council area. 
1.3 The maintenance of the grounds at South Lanarkshire Crematorium are managed by
Bereavement Services staff based at the crematorium. The maintenance of the grounds within
the Cemeteries are managed by Grounds Services. 
2. Purpose and Vision
2.1 The strategy will set out the current provision, legislation and the short, medium and long-term
needs for bereavement services provision in the Council area. 
2.2 Bereavement Services are an integral part of our community infrastructure, and the Council is
committed to providing our services with dignity, respect, competency, and efficiency. Our
service is at the heart of the community, and as such, we offer a high standard of care and
options to ensure that each member of the community can have a funeral which is meaningful
to them and their family. 
2.3 With the legal responsibility to provide burial ground, the Council is committed to ensuring
there is adequate provision within each geographical area of the authority. 
2.4 Our vision is to meet the on-going and changing needs of the bereaved and the wider
community within South Lanarkshire. 
3. Legal Context
3.1 Following the Burial and Cremation Review Group 2007, the Infant Cremation Commission
(2014), and the National Cremation Investigation (2016), the Burial and Cremation (Scotland)
Act 2016 was passed by the Scottish Parliament on 22 March 2016 and received Royal Assent
on 28 April 2016. The Act fulfils the commitment of the Scottish Government to implement the
recommendations made by these groups. 
3.2 In July 2016 a working group, headed by the Scottish Government, was formed to commence
work on the regulations of the Act. Priority was given to implementing Part 2 (Cremation)
resulting in the Cremation (Scotland) Regulations 2019. The working group was made up of
different areas of the industry including local authorities, Funeral Directors and Crematorium
Authorities, the work from which led to the new regulations being introduced from 4 April 2019. 
3.3 Whilst there is no legal requirement for a local authority to provide a crematorium as a
crematorium authority, we are obliged to comply with all aspects of the regulations set out in
the Cremation (Scotland) Regulations 2019. As a Crematorium Authority, we require to comply
with annual inspections which are carried out by the Inspector of Burial, Cremation and
Funeral Directors. 
3.4 Whilst the Council have the legal and statutory requirement to provide burial ground within the
authority, there is no legal nor statutory requirement for the Council to provide burial ground
within each town or within any specific area. The Burial and Cremation (Scotland) Act 2016
states that for the provision of burial ground, each local authority:  
125

Page 126

• Must provide one burial ground within the area of the local authority, and;
• May provide other burial grounds within that area. 
3.5 The Burial and Cremation (Scotland) Act 2016 also provides for two or more local authorities
to provide burial ground jointly. 
3.6 All burials must be authorised by the appropriate local authority and under the Act this will
cover private burials (those burials which occur in any land other than a cemetery). The
Council will be required to keep a register for private burials. 
3.7 The right of burial can only be sold by the local authority, and at present, rights are sold in
perpetuity/. However, on implementation of the full Burial and Cremation (Scotland) Act 2016,
rights will be sold on a lease basis of 25 years (excluding those lairs owned by the
Commonwealth Graves Commission, these rights will remain in perpetuity). After the initial 25
years, with the burial authority’s agreement, the lease period can be extended every 10 years
thereafter. 
3.8 The Burial and Cremation (Scotland) Act 2016 makes provision for inspection of crematorium
and burial authorities which the Council are required to comply with. The inspections for the
crematorium are carried out annually and are conducted by the Inspector of Burial, Cremation
and Funeral Directors. 
3.9 When the burial regulations are implemented, we will be inspected annually as a burial
authority also by the Inspector of Burial, Cremation and Funeral Directors. 
3.10 Under the new Burial and Cremation (Scotland) Act 2016, and previously the National
Assistance Act 1984, the Council has a legal obligation to provide either a burial or cremation
service for anyone who dies within the local authority area who has left no funds for their
funeral, nor anyone willing or able to pay for a service. Working with other partners (for
example: Police, Hospitals, Care Homes, and Social Work Departments along with family and
friends), we arrange a dignified service for the deceased, ensuring that any religious and
cultural beliefs or preferences are recognised and respected. 
3.11 A Burial Regulations Working Group is still actively working on the regulations for Part 1
(Burial). Although it has been hampered by Covid-19 pandemic, the current iteration of the
group, set up in December 2021, seeks to continue the work of the previous working groups.
The remit of the group is to inform the regulations of burial grounds and authorities in Scotland,
the development of statutory guidance and the creation of a Code of Practice for burial
authorities. South Lanarkshire Council are actively participating in the working group for the
regulations and, in November 2023, completed the consultation paper for the Management of
burial grounds, application for burial, exhumation, private burial, and restoration of lairs:
regulation of Scotland. 
3.12 The Burial & Cremation (Scotland) 2016 Act covers alternative methods of disposal of human
remains: 
• Section 99 of the Burial & Cremation (Scotland) Act 2016 enables Scottish Ministers to
make regulations to extend the application of the 2016 Act to encompass new methods of
disposal of human remains. The proposals to regulate alkaline hydrolysis (water
cremation) aim to provide the public a possible alternative choice to burial and cremation.
These regulations are part of a public consultation (November 2023) 
126

Page 127

Whilst this is only in the consultation stage at present, it is important that as part of our strategy,
the Council keep in mind that alternative methods may become more desired by the
Community, and we should therefore keep in line with the legislation and how the consultation
progresses as a way forward. 
4. Demographic Profile, Demand & Capacity
4.1 South Lanarkshire is an area of 684 square miles with a population of 322,630 (as at 2021). 
4.2 There is one crematorium within South Lanarkshire area (South Lanarkshire Crematorium in
Blantyre). The crematorium opened in September 2006 and this opening allowed for the
formation of Bereavement Services. 
4.3 There are 55 cemeteries within the South Lanarkshire area, for which we provide operational
works. These include churchyards, small rural cemeteries, and large urban cemeteries. Within
the 55 cemeteries, there are 2 cemeteries which are privately owned and for which the Council
carries out excavation works required for burials. Locations are outlined in the image below:
127

Page 128

4.4 The crematorium is a modern facility and sits in tranquil landscaped gardens, which have
proven to be popular with the bereaved, funeral directors and clergy. The crematorium
grounds provide various memorial options for bereaved families from the traditional book of
remembrance to memorial trees, wall plaques and family lairs. 
4.5 The crematorium conducted 1164 cremation services in the first full year of opening. This has
risen to 1725 in 2022. (Note: 2022 figures have been used throughout this document as this
is the most up to date figure available for deaths in the local authority area). 
4.6 The demand for cremation services has increased since the crematorium opened. This trend
follows the national trend for increasing cremation demand and is demonstrated by the figures
produced by the Cremation Society. The latest statistics for Scotland in 2022 show that from
annual deaths of 62,941, 45,102 (71%) were cremations. This compares to 2007 where annual
deaths for Scotland were 56,313, 34,557 (61%) were cremations. 
• For comparison, in South Lanarkshire in 2007, there was a total of 2390 cremations and
burials (1164 (49%) were cremations and 1226 (51%) were burials).
• In South Lanarkshire in 2022, there was a total of 2736 cremations and burials. (1725
(63%) were cremations and 1011 (37%) were burials). 
4.7 The graph below demonstrates this clear trend of increasing cremations and decreasing full
burials. It should be noted that 2020 should be considered as an exceptional year due to the
Covid-19 pandemic. 
*For clarification, a full burial is the burial of a coffin, and an ashes burial is the burial of a set of cremated
remains. 
128

Page 129

4.8 With an increase in the number of cremations comes the demand for more burials of ashes.
The chart below shows the trend for cremations, full burials, and ashes burials. Please note,
these figures do not include the family lairs at the crematorium (424 at present, averaging 56
per year). 
4.9 Looking at the next 10 years, this trend is set to continue as the chart below demonstrates.
The interment of ashes at the crematorium is not included in the below data. 
4.10 At present, the family lairs are the most popular memorial choice, and is the only memorial
where a burial of ashes can be carried out within the crematorium grounds. There are currently
424 family lairs within the grounds. On average, we release 28 lairs biannually in Spring and
Autumn. 
As with the right of burial in cemeteries, the family lairs are presently sold in perpetuity.
However, when the burial regulations are implemented, the family lairs at the crematorium will
be sold on a 25-year lease basis, as per the burial regulations. This may lessen the appeal of
this memorial as an option.
1164 1215 1282 1279 1369 1491 1423 1355 1526 1606 1612 1673 1682
1945
1749 1725
1226 1213 1137 1169 1143 1068 1055 1049 1111 1029 1019 1033 981 1071 1022 1010
270 289 293 242 240 261 241 218 257 279 228 222 262 176 290 272
2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
Cremations, Full Burials, Ashes Burials
2007 to 2022
Cremations Full Burials Ashes Burials
129

Page 130

4.11 Currently there are over 105,000 existing lairs across all South Lanarkshire Cemeteries, with
a further 4,024 new lairs available. On average, there are 1,154 interments every year, of
which 342 are new lairs. 
4.12 As detailed in the Bereavement Services Cemetery Strategy, passed by Community &
Enterprise Resource Committee on 30 May 2023, on-going land provision is becoming more
difficult to source as available land use changes for community requirements as well as the
suitability of land to be used for burials. Therefore, the Council is required to achieve maximum
land use throughout the Council area and within our existing cemeteries, whilst maintaining
our legal obligation to provide burial ground. 
4.13 A key aim of our strategic approach to cemetery provision was to establish catchment
groupings in geographical location within the authority area. This approach has allowed us to
measure lair availability and usage within each catchment area and provide the most
appropriate burial provision within communities. The work is continuing, and we aim to
increase capacity in the following cemeteries: 
• Philipshill Cemetery – The extension is expected to be completed by March 2024,
providing an additional 1,117 new lairs. 
• Douglas Cemetery - Planning permission has been received to create an extension which
will provide an additional 391 new lairs. As there is currently sufficient capacity in the
catchment, it is proposed to begin work on the extension in 2-3 years. 
• Springbank Cemetery – This has the potential maximum capacity of 8,000 lairs within the
Council’s existing land ownership. This will require enabling infrastructure at the
appropriate time to increase capacity. 
4.14 The Council has commenced the work to increase new lair provision within our existing
cemeteries. The first will see a pro-active approach to recovering underutilised space within
individual cemeteries. Recent work in this area has identified the potential creation of 27 new
lairs within Strathaven Cemetery. Similar investigatory work in Rutherglen Cemetery has
identified potentially 65-70 new lairs, and a further 100 at Philipshill. A programme of work will
be developed to identify further opportunities to increase new lair capacity from existing
cemetery provision. 
4.15 Furthermore, within the legislative framework, councils have the powers to reclaim burial
ground for which the right of burial has been purchased in advance, and where no interments
have taken place over a period of time. Within the Council’s current policy this period is 40
years. However, this is believed to be too short a timeframe. It is proposed to increase the
period of inactivity to 60 years, and the Council will now begin the legal process to reclaim
lairs unused after this timeframe or longer. 
4.16 The following graph highlights the difference between the deaths which have occurred in
South Lanarkshire and the cremation and burial services which took place in the authority
area:
130

Page 131

The above data demonstrates that a significant number of deaths have occurred in South
Lanarkshire where the service has taken place elsewhere. Although there will have been
deaths which have occurred in South Lanarkshire where the person was resident out with the
authority area, and it is assumed their services were therefore held elsewhere to assist in the
understanding and development of our services, there is a need to investigate the reason/s
for the gap between the numbers. 
4.17 It would be proposed to conduct a public consultation on cremation and burial facilities within
the local authority area. This would gather information on the aspects and demands of the
service, and feed information into the rules and areas for development within each part of the
service. It is expected that this consultation will allow a full analysis of both the crematorium
and cemeteries service including: 
• Service users - Geographically
• Reasons for choosing South Lanarkshire for burial or cremation
• Reasons for not choosing South Lanarkshire for burial or cremation
• Service times
• Memorialisation
• Comparisons with neighbouring crematoria
• Burial types (i.e. the desire for green/natural burials) 
5. Crematorium Rules and Areas for Development
5.1 A crematorium management plan is required under the Burial & Cremation (Scotland) 2016
Act. The South Lanarkshire Crematorium Plan was created in 2019 following the
implementation of the Cremation (Scotland) Regulations 2019. This plan covers: 
• Administration function of the service
• Maintenance procedures and servicing of equipment
• SEPA permit, inspection reports and contact details
• Disposal of cremation residues procedures
• Disposal of ashes procedure
• Increase in unexpected numbers procedure
• Contingency arrangements
• Plan review
3,440 3,382 3,212 3,207 3,214 3,439 3,329 3,323 3,497 3,529 3,523 3,603 3,522
4,221 3,942 3,818
2,390 2,428 2,419 2,448 2,512 2,559 2,478 2,404 2,637 2,635 2,631 2,706 2,663
3,016 2,771 2,736
2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
Total Registered Deaths to South Lanarkshire
Services in South Lanarkshire
Registered Deaths Total Services in SLC
131

Page 132

5.2 As a Crematorium Authority, we are inspected annually by the Burial, Cremation & Funeral
Director Inspector. These inspections include: 
• Cremation Fees
• Staffing Levels
• Office Management
• Annual Cremation Number
• Cremation/Identity Card Process
• Recovery of Ashes
• Ashes Policy
• Cremators
• Sample of Cremation Register
• Use of baby tray
• Pregnancy Loss Policy/Procedure
• Metal Extraction
• Crematorium Management Plan
• General Observations/Recent Changes
• Overall Assessment 
5.3 A Crematorium Authority requires to hold a licence to cremate. This involves an annual
inspection by the Scottish Environmental Protection Agency (SEPA) who issue the licence to
cremate and without which the crematorium cannot operate. 
5.4 The crematorium is fully abated (abatement is where the toxic gases are removed and are not
released into the atmosphere), and therefore has a low environmental impact. This is in line
with the Council and the Resources commitment to sustainable environment. The technology
and equipment required for the abatement system was invested in the facility from the
beginning, with a commitment to sustainable environment in mind. 
5.5 A heat exchange system is currently in place where the heat generated from the cremators
heats the crematorium buildings, which aids the running of the crematorium and assists both
financially, and in line with the commitment to sustainable environment. 
5.6 The crematorium requires specialist staff to carry out a cremation. Each qualified staff member
must be certified as a Crematorium Technician. Our staff are trained and certificated by the
Federation of Burial and Cremation (FBCA). Following the Infant Cremation Commission
(2014) and the National Cremation Investigation (2016), South Lanarkshire Crematorium
became a training centre for the infant module cremation. Working with the FBCA we continue
to provide this training service monthly. 
5.7 There are currently three permanent fully trained Crematorium Technicians and two
permanent Grounds Maintenance Operatives. The Grounds Maintenance Operatives cover
Crematorium Technician duties as and when required (1 Grounds Maintenance Operative is
a certified Crematorium Technician and 1 is currently undergoing the relevant training). 
5.8 Service Times and Availability
The crematorium has 11 service slots available per weekday and 5 service slots on a
Saturday. This gives a potential availability of 60 service slots per week. The following tables
highlight the availability and the percentage of the slots taken, and how much the facility is
being utilised, divided by different service types during 2022. 
132

Page 133

2022 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Total
Full Services 138 143 152 138 142 134 118 147 111 119 137 128 1607
Availability 149 156 177 167 170 170 167 177 170 167 170 160 2000
Percentage 93% 92% 86% 83% 84% 79% 71% 83% 65% 71% 81% 80% 80% 
2022 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Total
Half Services 17 15 9 11 14 14 5 8 7 7 3 14 124
Availability 42 44 50 47 48 48 47 50 48 47 48 45 564
Percentage 40% 34% 18% 23% 29% 29% 11% 16% 15% 15% 6% 31% 22% 
The most popular time slots are those for a full service. These slots are at 1-hour intervals and
operate from 9am to 3pm on a weekday and 9am to 12pm on a Saturday. The half service
slots run for up to 30 minutes, and there are 2 half service slots available each weekday
(8:30am and 4pm) and 1 available on a Saturday (8:30am). 
There are 2 service slots per weekday, at 8am and 8:15am, for direct services. These services
are dedicated to those who do not wish for anyone to attend the service nor any music/tributes
etc. The following table highlights the number of direct services available, and the percentage
of the slots taken during 2022. 
2022 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Total
Direct
Services 3 2 0 1 1 1 1 3 3 3 2 6 26
Availability 38 40 46 42 44 44 42 46 44 42 44 40 512
Percentage 8% 5% 0% 2% 2% 2% 2% 7% 7% 7% 5 15% 5% 
5.9 After analysing the usage of the service slots, it is proposed to change the format of the
services offered at 8am and 8:15am to allow for an additional option: 
• Retain the direct cremation (no mourners, or tributes)
• Create the additional option of a simple service to include entry and exit music, a poem or
short eulogy, and a maximum of 10 mourners. 
These options would be offered at the same time on the usual first come first served basis.
This would start with a trial period of 6 months to determine level of interest and take up of the
additional options. 
5.10 The crematorium also offers the full service and the half service time slots for memorial
services where only the use of the service room is required. There were 32 memorial services
booked in 2022 and these are included in the full-service numbers shown above. The service
room allows for seating of 160 mourners and is larger than the service room offered at funeral
133

Page 134

directors. Once the memorial service has been conducted, the deceased is usually taken for
burial in a cemetery, although families can book the service room for a memorial service. 
5.11 It should be noted that there are inhouse reasons that services may not have been taken: 
• Servicing/Maintenance of cremators which require service times to be closed.
• “Outsized” cremations which require services to be closed off to allow cooler cremators
and reduce pressure on the cremators. 
5.12 The table below shows the time slots for full services and the uptake by quantity and
percentage of each time. There is quite an even split between the time slots however 11am is
the most popular which is due in the most part to church service times and the 11am is
generally the first time to be booked on any given day.
2022 9am 10am 11am 12pm 1pm 2pm 3pm
Number 113 265 277 250 235 243 224
% of Services 7% 17% 17% 16% 15% 15% 14% 
5.13 There are external reasons that a service time is not taken, and this may include: 
• Funeral Director availability
• Church availability
• Crematorium location 
The influence of funeral directors, clergy, humanists, and celebrants on the choice a family
makes for cremation cannot be underestimated. It is accepted that the majority of services
booked at the crematorium are within an 8-mile radius of the facility. A consultation with the
above groups and individuals will assist in developing our future services and how we can
promote the facility to other geographical areas. 
5.14 Cremator Service Agreement & Financial Information 
The crematorium currently operates with 2 gas cremators supplied from Facultative
Technologies, who are also responsible for the servicing of the equipment. The current service
agreement commenced 1 June 2022 and runs until 30 May 2026 (with the option to extend for
a further 24 months thereafter). 
The cremators are expensive to maintain. The table below outlines the total yearly cost of
routine maintenance/servicing/running costs between 2020 and 2022: 
Year Routine Maintenance, Servicing
& Running Costs
2020 £93,479
2021 £95,250
2022 £129,871   
134

Page 135

Over the past 3 years, major works have been required, totalling £181,685. The breakdown of
works is as follows: 
− Replacement hearth   £18,062
− Replacement analyser   £43,000
− Rebrick     £105,318*
− Replacement bag filter   £15,305
Total (£181,685) 
*For comparison of increasing costs, the previous rebrick was carried out in 2017 and cost
£77,712. The 2023 rebrick cost shows an increase in cost of 35.52%. 
The crematorium and the cremators are now over 17 years old and although they have been
well maintained over the years with major works and replacements, it will be difficult to
maintain replacing parts. Therefore, we expect that completely new cremators will be required
to be fitted at some point. This will incur significant costs to ensure the equipment is fit for
purpose. The Council will continue to set money aside to fund on-going works. 
The cremators are no longer as efficient as they once were and are being overtaken in the
industry by newer crematoriums/cremators with the ability to handle more outsized coffins.
Currently when we receive an outsized coffin it requires to be a morning service to allow for a
cooler temperature. As the cremation process takes longer, we require to close off other
service time which is a potential loss of business to the Council. The cremators work from the
same filtration system which means when an outsized cremation is taking place both
cremators cannot be operated. An additional larger cremator would allow all oversized
cremations to be operated from a standalone machine without the need to close off services
to the other cremators. 
Development
5.15 As part of the strategy management rules for the crematorium, grounds and memorialisation 
require to be created and implemented. 
5.16 The proposal for a consultation will assist in information gathering as to how we can increase 
uptake on service times and help to mould our cremation services to maximise its potential. It 
is hoped that the consultation will give insight on our service times and would assist in 
developing and expanding the future of our cremation provisions. 
5.17 South Lanarkshire Crematorium are currently part of the ICCM (Institute of Cemetery and
Crematorium Management) recycling of metal scheme. The scheme operates with an
independent company based in the Netherlands called Orthometals, who make an annual
collection from the crematorium. Via the ICCM, all monies received, less administrative and
operating costs, are donated to UK charities. As a member of the scheme, South Lanarkshire
Council can nominate 2 charities to benefit from the funds. The current nominated charity for
South Lanarkshire is Kilbryde Hospice. The most recent donation made in January 2024
totalled £14,000. 
5.18 It is proposed as part of the Bereavement Services Strategy that the possibility of an
alternative disposal for the recycled metals with a company based in the UK is considered. It
is believed that a higher value from the alternative company would be received (RS Bruce
current estimation is to receive 33% more funds than the current agreement with
ICCM/Orthometals). The distribution of the payment details could be to that of the Council to
allow the distribution of the funds as the Council sees fit. This payment could in part be donated
to charity and part to improvement works at the Crematorium. 
135

Page 136

5.19 Due to the Covid-19 pandemic, the Council engaged with a company to allow a webcast
system. The company, Obitus, was put in place to allow services to be webcast live and to
provide an extra facility to allow family and friends to view services whilst attendance numbers
were restricted. In November 2020 the Obitus system was implemented in full which allowed
the music to be streamed through the system and visual tributes to be arranged thereby
negating the need for CD’s, DVD’s, USB’s etc. This made our music and tribute service more
efficient. The system generates additional revenue for the crematorium and is currently being
reviewed for an upgrade to allow a more efficient and streamlined service. 
5.20 The memorialisation available at the crematorium is an on-going element of service delivery
and is a significant income generator. There are various options with the memorials and the
consultation will include questions on the memorialisation, alongside an evaluation and review
of the current memorials. As we are always looking to improve and provide additional choices,
there is currently a new woodland scattering area under development at the crematorium
which will provide an alternative location for scatterings within the grounds. 
5.21 When a coffin is being placed in the cremator it is known as ‘charging the coffin’ and is currently
carried out manually by trained crematorium staff. The dignity of the deceased during the
cremation process is of the utmost importance for any cremation but in particular when
handling an outsized coffin as it places larger pressure on staff to ensure that the coffin is
positioned in the best possible advantage for the cremation process. It is proposed that an
investment through the Crematorium Sink Fund is made for an automatic charger to reduce
stress and strain on staff, prevent injury and to promote best practice when charging a coffin. 
5.22 Furthermore, new cremators offer ability to utilise various fuel sources, including options for
electric and hybrid configurations. It is recommended that these options are given
consideration for any renewal of the cremators and would support the Council’s sustainability
development strategy. 
6. Cemetery Rules and Areas for Development 
6.1 The Cemetery Rules and Regulations are the basis for the management of cemeteries. They
enable the public, funeral directors, and memorial masons to understand the rules that the
Council applies within all Council Cemeteries. 
6.2 In addition, Council Officers follow these rules and regulations to ensure the cemeteries are
managed and operated in a common sense, practical and sympathetic manner. The following
areas are covered within our Rules and Regulations. 
• Layouts of cemeteries and designation of plots 
• Rights of Burial 
• Burials 
• Memorialisation 
• Preparation of lairs 
• Register of burials
• Charges and Fees 
6.3 The regulations, which will follow the Burial and Cremation (Scotland) Act 2016 legislation, are
still being established and will form part of a consultation undertaken by the Scottish
Government working group. Once the results of the consultation have been processed, the
working group will start finalising the regulations. It is anticipated there will be further contact
requested of us by the working group via SBBG (Scottish Bereavement Benchmarking Group)
of which we actively participate in. 
136

Page 137

6.4 A Cemetery Management Plan will require to be completed in line with the Burial and
Cremation (Scotland) Act. The full extent of this requirement will be laid out in the regulations
produced following the implementation of the burial regulations. 
Cemetery Headstones/Memorials 
6.5 Bereavement Services are responsible for the management of headstone placement within
our cemeteries.  As a burial authority there is a duty of care for the safety of both visitors and
staff.   
To meet this duty of care, a Memorial Mason Registration Scheme was set up in 2015,
whereby memorial masons would be required to register with South Lanarkshire Council prior
to them undertaking works within our cemeteries.  This allows the service to check that
memorial masons are carrying out works within our guidance; that their work conforms to the
appropriate standard, and that they have appropriate public liability insurance.  
6.6 Furthermore, the Council conducts a headstone safety check as part of a rolling five-year
programme in all our cemeteries.  In doing so, advance notice is given to the public and
Councillors of the programme, whilst reporting the actions that we take and those a family may
require to take, following a headstone being deemed unsafe.  
Previously the headstone inspection programme implemented by the Council was produced
with guidelines issued by the Scottish Government. However, the inspection of headstones
will be included in the regulations set out by the Burial and Cremation (Scotland) Act 2016 and
will require to be reviewed and updated in line with proposed regulations. 
It is recommended that a review is carried out as part of the programme to allow dedicated
staff, who are fully trained, to be able to re-erect headstones. This would increase our
service/revenue potential. 
Rights of Burial
6.7 The Council understands families may not want a traditional type of coffin or burial and 
therefore we explore alternative options, such as sustainable and woodland burials, and 
environmentally friendly coffins made of materials such as wicker or cardboard. Current burial 
practice allows for the burial of full (coffin) and ashes. 
The Council is committed to working with religious, ethnic, and culturally diverse groups to
provide a range of burial options that meet the needs of our community. Currently. we provide
dedicated burial areas as detailed below: 
• Chinese community in Priestfield Cemetery 
• Coptic Orthodox Church in Bent Cemetery 
• Muslim community in Bent Cemetery (the Muslim faith also requires, where possible,
for a burial to take place within 24 hours of death) 
6.8  Current procedures allow for the termination of the right of burial in lairs which have not been 
used for 40 years. However, it is proposed to extend this to a period of 60 years to ensure a 
more appropriate time has elapsed. 
The process of terminating the rights of burial requires a letter to be issued to the registered
lair owner to advise on the intention. There is also a further requirement to place adverts in
two national newspapers and two local newspapers asking for any lair holder to come forward.
It is anticipated this process will take 18 – 24 months to complete and will target the following
cemeteries in the first phase: 
137

Page 138

• Strathaven 
• Rutherglen 
• East Kilbride 
• Lesmahagow 
Following the approval of the Bereavement Services Cemetery Strategy 2023, work has
commenced on the termination of rights on those cemeteries with no or limited burial capacity. 
7. Infrastructure and Maintenance
7.1 The Council acknowledges that the appearance of the crematorium and cemeteries can be
enhanced by good maintenance, in keeping with a peaceful and respectful environment. 
7.2 Maintenance of the crematorium is incorporated within the scope of duties of crematorium
operational staff. Staff are trained on grounds maintenance as well as crematorium technician
roles to enhance the working of the crematorium. Duties include: 
• Front of house duties
• Back of house duties
• Maintenance of cremators
• Grass cutting
• Excavations for interments in family lairs
• Carrying out ashes burials/scatterings
• Witnessed burials/scatterings service
• Care and placing of memorials
• Plants/Shrubs
• Weeding/borders/beds
• Tree maintenance
• Litter picking
• Customer Contact 
7.3 Maintenance of cemeteries is provided by Grounds Services. Cemetery staff are specially
trained due to the nature of the work with duties including grave digging and liaising with
bereaved families. Duties undertaken in this role are: 
• Digging graves 
• Assisting burials 
• Cutting graves 
• Weeding and borders 
• Topping up of graves 
• Cleaning and tidying up 
• Inspection of approved Memorial works 
• Testing of Memorials and Headstones 
7.4 The Council is responsible for the ongoing and long-term maintenance of associated
infrastructures within cemeteries such as the roads, footpaths and walls. Given the age of
many of our cemeteries, the maintenance requirements are increasing every year. Many of
the boundary walls around our churchyards, both in urban and rural areas, are deteriorating,
with sections of some cemeteries being closed off for safety. 
7.5 The Council has allocated funding in the Capital Programme for new cemeteries, extensions,
and infrastructure. This funding will be aligned with existing commitments and proposals
outlined in the strategy: 
• Completion of Philipshill cemetery extension 
• Douglas cemetery extension 
138

Page 139

• Enabling infrastructure for the recovery of space within existing cemeteries 
• Ongoing infrastructure maintenance of roads, footpaths and walls 
7.6 It is anticipated that further funding may be required following the 5-year capacity review
process – should further capacity be required in current cemeteries. The headstone inspection
and stabilisation programme has been supported by annual allocations from the Councils
capital programme. The service will continue to bid for funding through this annual process to
support this ongoing programme of work. 
8. Pricing Structure
8.1 Fees and charges are reviewed and set annually and are linked to the need for investment in
our crematorium and cemeteries and to meet the needs of our bereaved and wider community. 
8.2 All fees and charges are determined by balancing what is a reasonable charge and the cost
of managing and operating the crematorium and cemeteries. It is important to note that the
operating and managing costs of both the crematorium and cemeteries are increasing and
with known difficult financial situation for the Council it is noted that we require to look to other
areas within the service to promote additional income. 
8.3 An analysis of the current products shows a difference between the cost of an ashes only lair
at the crematorium as opposed to the cemeteries: 
• Current cost of family lair at crematorium - £832.22 (this is inclusive of a memorial block
and 30 letters of inscription
• Current cost of an ashes only lair in the cemetery - £532.65 (this is only the cost for the
right of burial 
8.4 It is therefore proposed that a right of burial cost should be the same charge whether at the
crematorium or the cemetery (currently £532.65), and the memorial fee would then be charged
on top of this for family lairs at the crematorium. This would give an approximate lowest cost
of £932.65 (currently £832.22). It is also noted that the family lairs at the crematorium are
inclusive of the first interment free, and it is therefore proposed that this is removed to bring in
to line with the burial fees. 
8.5 It is further proposed that the interment of ashes fee should be the same whether it is carried
out at the crematorium or in the cemetery. Currently additional interments at the crematorium
are charged at £89.19 however the same service in a cemetery would cost £284.91. 
8.6 When comparing South Lanarkshire Council’s current service fees with neighbouring local
authorities, it is clear there are areas within the service where a different pricing structure could
be suggested for services such as: 
• Family Search/Genealogy
• Memorial Fees
• Test Digs 
Family Search/Genealogy
8.7 At present, neighbouring local authorities charge for undertaking this search, with Glasgow
City Council charging £79.50, and North Lanarkshire Council charging £20. 
The current price list includes a for family search/genealogy cost for South Lanarkshire Council
of £17.92 - although this fee has never actually been charged as the search is completed
within 30 minutes. However, it should be noted the time it takes to respond to customers who
139

Page 140

often respond to the initial email with follow-up enquiries. It is therefore proposed that flat a
cost of £25 per search is implemented which would be required to be paid before a search is
carried out. Note, this would not be applied to any searches required for an imminent burial. 
Memorial Fees
8.8 At present, neighbouring local authorities charge for the issuing of a memorial fee permit, with
Glasgow City Council charging £75, and North Lanarkshire Council charging £43. 
Currently there is no charge for the issuing of a permit for the cleaning of headstones, added
inscriptions, or restoration of lettering. Therefore, it is proposed to set a charge for a memorial
permit for work on a headstone at £45.00 (excluding foundation fee). 
Test Digs
8.9 There are a number of local authorities within Scotland that charge for test digs. These are
sometimes requested, and it is proposed to implement a charge for this service. The table
below shows the current Scottish Councils who charge for this service and their current
charge. 
Test Digs Cost
Scottish Borders £812.00
City of Edinburgh £424.00
Aberdeenshire £239.00
Falkirk £170.00
Highland £153.10
Aberdeen City £123.00
Moray £120.05 
From the data above, it is evident that there is a variance in the prices charged. We would
propose to implement a charge of £100.00 per test dig. However, this charge would not apply
to an imminent burial, as this tends to be part of the excavation for the burial itself. 
Moving/Re-erecting Headstones
8.10 Currently, when an existing headstone requires to be moved and then re-erected to allow an
excavation/burial in a lair in a cemetery, the cost to the Council can be up to £500 per
headstone. 
Therefore, it is recommended to explore options of carrying out the work of re-erecting
headstones internally, thereby eliminating the need for an outside company to complete works.
This would allow an additional service to be offered to families to re-erect any unsafe
headstones. It should be noted that careful consideration is required in offering this service as
the Council may be accused of deliberately making a headstone unsafe to gain income. 
9. Bereavement Services Strategy - Short, Medium and Long Term
9.1 Short Term Strategy 
• Catchment capacity to be reviewed every 5 years. 
• Complete the extension at Philipshill Cemetery, providing over 1000 new lairs. 
• Re-evaluate our existing cemeteries to recover underutilised space for new lairs and
smaller ashes-only lairs. 
• Begin the first phase of the process of terminating the rights on lairs which have not been
used in excess of 60 years.
140

Page 141

• Reduce paper-based systems and replace these with electronic systems, including
handheld devices for front line staff. 
• Complete a public consultation on service provision of cremation and burial and analyse
information received.
• Adapt all systems and plans to incorporate legislation following implementation of the
burial regulations following Burial and Cremation (Scotland) Act 2016.
• Create crematorium management rules.
• Adapt cemetery management rules.
• Review and adapt Memorial Mason Registration Scheme to ensure this is fit for purpose.
• Create forums for funeral directors to improve working relationships.  
9.2 Medium Term Strategy 
• Complete the extension at Douglas Cemetery.
• Explore options for the provision of alternative burial provision, including woodland burial
sites.
• Modernise and improve IT systems to provide better data for the service and enabling
more effective performance reporting. 
• Update lair maps in all cemeteries.
• Review charges in line with benchmarking of other local authorities.
• Progress a workforce plan to ensure continuity of services.
• Update and adapt the headstone inspection programme to ensure it is fit for purpose.
• Ensure that all reasonable measures are put in place to guarantee accessibility of
cemeteries (under the Equality Act, 2010).  
9.3 Long Term Strategy 
• Complete a Bereavement Strategy, incorporating all elements of the service, including
Crematorium provision. 
• Undertake the first 5-year review of cemetery catchment capacity. 
• Develop proposals for infrastructure investment (roads, footpaths, walls).
• Work with religious, ethnic, and culturally diverse groups to provide a range of burial and
cremation options that meet the needs of our community. 
• Continue working with Memorial Mason Registration Scheme.
• Investigate the benefit of electrical cremators for any potential expansion of cremation
services. In particular, the cost effectiveness and the environmental impact. 
141

Page 142

142

Page 143

Report
Agenda Item 
Report to: Community and Enterprise Resources Committee
Date of Meeting: 18 June 2024
Report by: Executive Director (Community and Enterprise
Resources)
Executive Director (Finance and Corporate Resources)  
Subject: Introduction of Charge for Uplift of Household Garden
Waste (Burgundy) Bin 
1. Purpose of this Report
1.1. The purpose of the report is to:- 
 seek endorsement from the Committee on a proposal to introduce a charge for the
uplift of burgundy bins containing garden waste
2.        Recommendation(s)
2.1. The Committee is asked to approve the following recommendation(s):- 
(1) that the proposal, detailed at section 4 of the report, to introduce a charge for the
uplift of burgundy bins containing garden waste be endorsed;
(2) that the increase of the Waste Services’ establishment by 4 FTE on a temporary
basis and 9 FTE on a permanent basis, as detailed in sections 5.2 to 5.4 of the
report, be endorsed;
(3) that the increase of the vehicle establishment for Waste Services, as detailed in
section 4.8 of the report, be endorsed; and
(4) that the recommendations be referred to the Executive Committee on 26 June
2024 for approval. 
3. Background
3.1. In 2015, the Council introduced a burgundy bin to collect food waste to comply with
the Waste (Scotland) Regulations 2012. These regulations placed a statutory
obligation on local authorities within Scotland to provide householders with a separate
food waste collection service. The legal obligation only applied to urban areas;
however, the Council made the decision to provide the service in rural areas in
circumstances where it was deemed technically, environmentally, and economically
practical to do so. 
3.2. Although there is no statutory requirement to provide residents with a garden waste
collection service, the Council allowed residents who had been provided with a
burgundy bin to deposit unbagged, compostable garden waste free of charge. 
3.3. Approximately 110,000 households have been provided with a burgundy bin to present
commingled food and garden waste. Residents in flatted properties (with no gardens)
have communal ‘food only’ burgundy bins. Around 5,000 rural properties, mainly in the
Clydesdale, were not provided with a burgundy bin and so are currently unable to
present food or garden waste separately at the kerbside.  All South Lanarkshire
9
143

Page 144

Council residents, including those in rural areas, can request a garden waste uplift for
unbagged compostable waste. The cost of this service is currently £40 for up to 10
items.   
3.4. As councils across the country look for ways to reduce budgetary pressures, charges
for garden waste collections have become increasingly common.  There are currently
6 councils in Scotland who do not provide a kerbside garden waste collection service
for residents.  Of the remaining councils, 21 operate a chargeable garden waste permit
scheme, which means only 5 councils in Scotland currently provide a free of charge
garden waste collection service. 
3.5. The councils who operate a permit system charge residents between £30 and £60 (an
average of £42.16) each year.  More information on the cost of garden waste permits
in Scotland can be found in Appendix 1 to this report. 
4. Introduction of Garden Waste Permits
4.1. It is proposed that a similar garden waste permit scheme is introduced in South
Lanarkshire to recover some of the costs associated with providing the service.
Residents who wish to participate in the scheme would be required to purchase a
permit for each bin containing garden waste. It should be noted that residents who use
the bin solely for depositing food waste would not require a permit as food waste would
still be collected free of charge. 
4.2. The cost of the permit would be £45 per annum and would allow a resident to present
one burgundy bin containing garden waste on each scheduled collection day until the
end of that financial year. It is proposed that garden waste uplifts are suspended during
the Christmas and New Year period to allow Waste Services to prioritise the collection
of residual and recyclable waste as tonnages of these waste streams increase over
this period, while garden waste tonnages are at their lowest. Therefore, except for a
2-week period over Christmas and New Year, the burgundy bin would be uplifted every
2 weeks between 1 April and 31 March each year. Absence rates tend to be higher
over the winter period because of the higher prevalence of seasonal colds and flus in
the workforce; reducing the employee requirement would limit the need for overtime
payments.  The temporary suspension of the burgundy bin service during this period
would also allow more front-line staff to take annual leave, giving them the opportunity
to spend more time with their families.   
4.3. The permit scheme, unlike the current food and garden waste collection service, would
be made available to residents in rural Clydesdale, meaning that all South Lanarkshire
residents would benefit from a kerbside collection service for garden waste. The cost
of the permit would include the cost of providing the resident with a new burgundy bin
as well as a food waste caddy, should they wish to use the bin to recycle food waste.
In addition, the establishment of this service would allow those residents in rural
Clydesdale not currently on the service to opt in to receive a burgundy bin and caddy
for food waste only. 
4.4. It is proposed that the new service will commence from 1 April 2025; however, given
the scale of the project and the lead-in times required to recruit the project team and
to procure the required IT systems to manage the permit process, it is anticipated that
the project would commence on 1 July 2024 (9 months prior to the implementation
date). Discussions with local authorities who have brought in a similar system have
indicated that 9 months is the minimum implementation period required for a
successful project. 
144

Page 145

4.5. During this time, the Waste Service will undertake significant community engagement
to ensure residents are aware of the new charge as well as the alternatives if they do
not wish to participate in the service. These include continued use of the Council’s 6
Household Waste Recycling Centres (HWRC) to dispose of garden waste for free as
well as the promotion of home composting. Information on home composting is
available on the Council’s website which also signposts to guidance and toolkits from
Zero Waste Scotland.  More information can be found at Appendix 2, Frequently Asked
Questions. 
4.6. The costs associated with the proposal include the establishment of a Project Team
to manage the design, implementation and roll out of the service.  The Project Team
will also be responsible for liaising with public, issuing communications and dealing
with any queries. This will limit the impact the project may have on the Council’s
Customer Contact Centre staff. It is also worth noting Waste Services will be
developing and managing the changes associated with the larger Waste Review at
the same time so additional resources will be required to ensure the project is delivered
on time. The project costs also include the purchase of a specialist IT system to
manage the permit process. 
4.7. The Project Team, consisting of an Officer and 3 Waste Education Assistants
(temporary for 21 months and 12 months, respectively), would be recruited following
committee approval. The Project Team costs are estimated to be in the region £0.068
million 2024/2025 and £0.134 million in 2025/2026. 
4.8. There is a requirement to increase the vehicle fleet establishment by 3 refuse
collection vehicles in 2025/2026. The increased number of vehicles is necessary to be
able to provide the Service in the rural areas of South Lanarkshire as crews are
required to travel lengthy distances to households and to tipping locations. Leasing
and maintenance costs for the 3 new vehicles are estimated at £0.120 million in
2025/2026 and £0.210 million per annum from 2026/2027 onwards. 
4.9. Employee costs associated with the additional Waste Operatives required to crew
these vehicles will be in the region of £0.184 million in 2025/2026 and £0.330 million
from 2026/2027 onwards. 
4.10. To ensure the Service can continue to operate across South Lanarkshire, there is a
requirement to replace four 14-tonne refuse collection vehicles that were purchased
using funding received from Zero Waste Scotland in 2015. These owned assets are
not on the vehicle replacement list and are now nearing end of life. These smaller
vehicles are required to collect food waste from flatted properties as well as food and
garden waste from properties located on restricted access roads. The cost of replacing
these owned assets with leased vehicles is estimated to be (£0.096 million) per annum
from 2026/2027 onwards. 
4.11. The financial modelling for the subscription charge has considered one-off capital
costs (IT system, bin purchase and replacement) as well as the ongoing revenue,
including resource requirements, associated with expanding the service to rural
Clydesdale. It has included an assumption that a proportion of garden waste will be
diverted to the non-recyclable waste stream, leading to higher disposal costs. It is also
anticipated that more garden waste will be diverted through the Council’s 6 HWRCs
and these costs have also been incorporated in the financial modelling. If the proposal
is approved, Waste Services will closely monitor household waste flows to determine
the impact on the waste disposal budget. 
145

Page 146

4.12. Information gathered from other local authorities suggest that uptake of the Service is
likely to be around 30% in the first year of implementation, rising to 50% uptake from
year 2 onwards. Using these assumptions, full year net income is estimated to be
£0.500 million in 2025/2026. Further additional income of £0.875 million is expected
in 2026/2027. This means that recurring annual income from year 2 onwards is
estimated to be in the region of £1.375 million. 
4.13. Costs in 2024/2025, associated with establishing a Project Team, the purchase of an
IT system and burgundy bins for delivery in advance of the 1 April 2025 ‘go-live date’
are estimated at £0.170 million. 
4.14. It should be noted that the Scottish Government are currently considering proposals
to make garden waste collections mandatory. If this proposal is approved the Council
would no longer be able to charge for the collection service; however, under these
circumstances it would be expected that appropriate compensatory funding would be
made available to local authorities in respect of the new statutory obligation. 
4.15. A Frequently Asked Questions (FAQs) information sheet has been developed for
residents and is included at Appendix 2. 
5. Employee Implications
5.1. The following posts should be added to the establishment as detailed below. The
salaries shown reflect the current pay rates. 
5.2. Temporary Posts 
Post  FTE Grade/SCP Hourly
Rate 
Annual
Salary
Gross
Costs
inc. on
costs
30.3%)
Total
Annual
Costs
Project
Officer 
(temp 21
months)
1 Grade 3
Level 2 to 4
SCP 63-74 
£20.75
-
£23.90 
£37,866
-
£43,615 
£49,340
-
£56,830 
£49,340
-
£56,830 
Waste
Education
Assistant
(temp 12
months)
3 Grade 2
Level 1
SCP 34-35
£14.26
-
£14.47
£26,023
-
£26,406
£33,908
-
£34,407
£101,724
-
£103,221 
5.3. Permanent Posts for additional service in rural areas 
Post FTE   Grade/SCP Hourly
Rate
Annual
Salary
Gross
Cost
(inc. on
costs
30.3%)  
Total
Annual
Costs
Waste
Operative
(Loaders)
4 Grade 1
Level 3
SCP 25-27
£12.81
- 
£13.11
£25,140
£25,729
£32,757 
- 
£33,525 
£131,030
-
£134,100
146

Page 147

Post FTE   Grade/SCP Hourly
Rate
Annual
Salary
Gross
Cost
(inc. on
costs
30.3%)  
Total
Annual
Costs
Waste
Operative
(Drivers)
5 Grade 1
Level 4 
SCP 30-31
£13.59
-
£13.76
£29,682
-
£30,054
£38,676 
- 
£39,160
£193,380
–
£195,800 
5.4. The proposal overall would result in 13.0 FTE posts being added to the establishment,
4.0 FTE on a temporary basis, and 9.0 FTE on a permanent basis This will be
implemented on a phased basis to reflect the estimated uptake of the service over 2
years as follows:-  
2025/2026 Waste Operative (Loaders) – 2 FTE; Waste Operative (Drivers) –
3 FTE
2026/2027 Waste Operative (Loaders) – 2 FTE; Waste Operative (Drivers) –
2 FTE 
6. Financial Implications
6.1. The total costs associated with the proposal across the financial years 2024/2025 to
2026/2027 are £0.170 million, £1.010 million and £1.140 million respectively. This
covers all costs including employee costs, vehicle and replacement bin costs, excess
waste costs and administrative costs including IT system.   
6.2. Net income after deducting costs of the Service, is estimated at £0.500 million in
2025/2026 with an additional income in 2026/2027 of £0.875 million. There is a cost
associated with start-up £0.170 million in 2024/2025.   
2024/2025 2025/2026 2026/2027
Est income (cost) (£0.170m) £0.500m £0.875m 
6.3. Recurring annual income from year 2 onwards is estimated to be in the region of
£1.375 million. 
7. Climate Change, Sustainability and Environmental Implications
7.1. The proposal allows residents in rural areas access to a kerbside recycling service for
garden waste but also gives them the ability to recycle food waste for the first time.
Residents who do not wish to pay for the service can use HWRCs to dispose of garden
waste for free but there is a risk that some garden waste could end up in the non-
recyclable waste bin, which could have an impact on household recycling rates. 
8. Other Implications
8.1. There are no other risks or implications associated with this report. 
8.2. The Council’s obligations under the Fairer Scotland Duty and the Consumer Duty have
also been assessed in respect of these proposals.  In terms of the Fairer Scotland
Duty, whilst this proposal is not a new strategy it is the introduction of a new charge
for a service that is currently provided for free and it is recognised that it has the
potential to have a negative impact on residents, including on those who are socio-
economically disadvantaged, such as those with a low income. To mitigate any such
negative impacts the Council will also promote home composting opportunities,
through advice and guidance from Zero Waste Scotland, and residents can also
choose to use the Council’s 6 Household Waste Recycling Centres for free. In terms
147

Page 148

of the Consumer Duty the proposal likewise has the potential to impact consumers,
however the same mitigations will be available, and it is to be noted that this proposal
gives residents in rural areas access to this service and food waste recycling that they
currently do not have.  If requested by an elected member, copies of the impact
assessments are available from the report’s author. 
9. Equality Impact Assessment and Consultation Arrangements
9.1. The EQIA determined that no equality group will be impacted more than any other
service user by the introduction of this proposal; however, the service will monitor
comments, complaint and feedback to ensure any unexpected consequences are
mitigated. Financial reports will also be monitored to ensure income is in line with
estimates.  If requested by an elected member, a copy of the EQIA is available from
the report’s author. 
9.2. If approved, the Waste Service will undertake significant community engagement to
ensure local residents are aware of the new charge as well as the alternatives if they
do not wish to participate in the service. These include continued use of the Council’s
6 HWRCs to dispose of garden waste for free as well as the promotion of home
composting. Information on home composting is available on the Council’s website
which also signposts to guidance and toolkits from Zero Waste Scotland. More
information can be found at Appendix 2, Frequently Asked Questions. 
David Booth
Executive Director (Community and Enterprise Resources) 
Jackie Taylor
Executive Director (Finance and Corporate Resources) 
28 May 2024 
Link(s) to Council Values/Priorities/Outcomes
Values
 Focused on people and their needs
 Working with and respecting others
 Accountable, effective, efficient and transparent
 Ambitious, self-aware and improving
 Fair, open and sustainable
 Excellent employer
Priorities
 We will work to put people first and reduce inequality
 We will work towards a sustainable future in sustainable places
 We will work to recover, progress and improve
Outcomes
 Our children and young people thrive
 Good quality, suitable and sustainable places to live
 Thriving business, fair jobs and vibrant town centres
 Caring, connected, sustainable communities
 People live the healthiest lives possible
 Inspiring learners, transforming learning, strengthening partnerships 
148

Page 149

Previous References
 None 
List of Background Papers
 None 
Contact for Further Information
If you would like to inspect the background papers or want further information, please
contact:-
Kevin Carr, Head of Facilities, Waste and Grounds Services
Tel:  01698 454708 
E-mail: kevin.carr@southlanarkshire.gov.uk  
149

Page 150

Appendix 1
Garden Waste Charges (Scotland) 
Local Authority Service Charge Cost (£)
Aberdeenshire No No n/a
Aberdeen City Yes yes 30
Angus Yes yes 50
Argyll and Bute no no n/a
City of Edinburgh Yes yes 35
Clackmannanshire Yes yes 48
Dumfries & Galloway No No n/a
Dundee City Yes yes 45
East Ayrshire Yes yes 30
East Dunbartonshire Yes yes 50
East Renfrewshire Yes yes 52.5
East Lothian Yes yes 35
Falkirk Yes yes 45
Fife Yes No 0
Glasgow City Yes yes 50
Highland Yes yes 35
Inverclyde Yes yes 42
Midlothian Yes yes 40
Moray Yes yes 50
Western Isles Yes no 0
North Ayrshire Yes no 0
North Lanarkshire Yes No 0
Orkney Islands No No n/a
Perth & Kinross Yes yes 40
Renfrewshire Yes yes 40
Scottish Borders No No n/a
Shetland Isles No No n/a
South Ayrshire Yes yes 50
South Lanarkshire Yes No 0
Stirling Yes yes 50
West Dunbartonshire Yes yes 60
West Lothian Yes yes 50 
150

Page 151

Appendix 2   
Frequently Asked Questions 
Residents of South Lanarkshire who use a burgundy bin to dispose of garden waste will be required
to buy an annual permit if they wish to use the service from 1 April 2025. The charge for an annual
permit is £45.00. A separate permit is required for each bin used. 
How will the new service work?
• If you would like to dispose of garden waste in your kerbside burgundy bin, you need to
apply and pay for an annual permit. Payment can be taken online
www.southlanarkhsire.gov.uk  or over the telephone. 
• Once paid for, you will receive your permit by post. Peel the customised permit from the
backing paper and stick it carefully to the back of your burgundy bin (below the handles). Full
instructions can be found on the reverse of the permit.  
• Each permit entitles you to present one burgundy bin containing garden waste every 2
weeks (except for a two-week period over Christmas and New Year). 
• Your permit is subscribed on an annual basis, so you will need to reapply each year. 
How much does a permit cost?
• An annual permit costs £45.00. A separate permit will be required for each burgundy bin
used to collect garden waste. 
How do I apply and pay for a permit? 
• You can apply and pay for a permit via the online form on the council website or by
telephoning Waste Service’s. 
Does everyone need to purchase a permit to dispose of garden waste in a burgundy
bin?
• Yes, anyone who wishes to dispose of garden waste in the burgundy bin will need to
purchase a permit. There are no exceptions or concessions. 
How can I dispose of garden waste if I don’t want to pay for a permit? 
• You can still take your garden waste, free of charge, to one of our six Household Waste and
Recycling Centres.  Information about our recycling centres can be found on the council
website Waste and recycling centres - South Lanarkshire Council.
• You can also compost garden waste at home. More information about composting can be
found on the  Zero Waste Scotland website:
https://wasteless.zerowastescotland.org.uk/articles/easy-guide-to-composting-home 
Can I still use my burgundy bin to dispose of food waste?
• Yes, you can still use your burgundy bin to dispose of food waste free of charge; permits are
only required if you wish to dispose of garden waste in the burgundy bin. 
Who can participate in this service?
• All households in South Lanarkshire can apply for the garden waste service.  If you would
like to receive a garden waste collection, please apply online at:
www.southlanarkshire.gov.uk 
Why is there a charge for my garden waste collection?
• The Council is not legally required to collect garden waste. This is an optional subscription
service, and you will only pay if you subscribe to the service.
Is the charge included in my council tax?
• No, the Council is not legally required to collect garden waste. This is an optional
subscription service, and you will only pay if you subscribe to the service. 
151

Page 152

Are there any concessions or discounts?
• No concessions or discounts are available for the garden waste permit.   
Do other councils charge for this service?
• Yes, many other councils in Scotland charge for this service. 
Can I buy a garden waste permit at any point throughout the year?
• You can apply for a permit at any point during the year, but the cost will remain at £45.00 per
permit. 
• We would encourage you to apply as early in the year as possible, so you benefit from a full
year’s service. 
How many permits and burgundy bins can I have?
• A separate permit will be required for each burgundy bin. One annual permit costs £45.00.
There is a maximum of three permits/ burgundy bins per household. 
How often will my burgundy bin be emptied?
• You will receive a fortnightly garden waste collection, between 1 April and 31 March each
year except for a two-week period over Christmas and New Year. 
How will my collection crew know I have paid for garden waste to be collected?
• Each permit will detail the property address for which the permit was purchased for that year. 
• Collection crews will only empty garden waste from burgundy bins which display a valid
garden waste permit. 
• Permits are issued to the property and are not transferable. Copies of permits will not be
accepted. 
What happens if I move house?
• If you move home the permit should remain at the property. You cannot take it with you and
will not receive a refund.
• If you move to a house that has an existing permit, you can continue to use it until it expires.
You will then have to re-apply to use the service.
• You can apply at any point during the year, but the cost will remain at £45.00 per permit. 
What happens to my burgundy bin if I decide not to participate in the garden waste collection
service?
• You can continue to use your burgundy bin for food waste only; no permit is required. 
• Your burgundy bin remains the property of South Lanarkshire Council, therefore, it should
not be removed unless requested by contacting us online at Bins and recycling - South
Lanarkshire Council . 
I paid for my permit and have not received it.
• Once your payment has been processed, it can take up to 21 days to print the personalised
permit for your bin and post it to your home.  If it has been more than 21 days since you
ordered your permit, please report online at: www.southlanarkshire.gov.uk 
What happens if I have paid for a permit and my garden waste bin collection is
missed?
• Severe weather, access difficulties or breakdowns, may result in service disruption or
missed collections. In this event, leave your bin out and we will collect it at the earliest
opportunity.
• If the contents are compressed too tightly in the bin, then the material will not dislodge during
the emptying process. In these circumstances, customers will be asked to dislodge the
material manually and re-present the bin at the next scheduled collection day. To avoid this
happening, please do not tightly pack garden waste into the bin. 
• Your bin may not have been collected because it contained contaminants (i.e.  contents
other than food or garden waste). In these circumstances, your bin will be tagged and you
will be asked to remove the contamination and re-present the bin at the next scheduled
152

Page 153

collection dated.  Details of what can be put in your bin can be found online at: Recycle
Burgundy Bins 
Can I cancel a permit?
• Permits can be cancelled within 14 days of purchase to receive a full refund, thereafter no
refunds will be given. 
I do not always have garden waste - do I still need to pay?
• Yes, if you plan to use your burgundy bin for recycling any garden waste during the year,
you will need to purchase a permit. 
Can I share a garden waste bin collection service with my neighbour?
• If you want to share a garden waste bin with your neighbour, you will have to come to a
private agreement who will be responsible for the bin and pay for the permit. The permit can
only be registered to one address. 
What will happen to bins that contain garden waste presented without a permit?
• From 1 April 2025. we will not empty burgundy bins that contain garden waste unless a valid
garden waste permit is affixed to the bin. 
How will I stop residents who have not paid for the service placing garden waste in
my bin? 
• You are responsible for the waste and recycling that is contained within your bins, and it is
your responsibility to remove contamination.  Please store your bin securely between
collections. 
What happens if I present my burgundy bin containing the wrong material? 
• The Council will not empty bins that contain the wrong waste type (contaminants), are of
excessive weight, or present a health and safety risk to staff. 
• If the bin is contaminated with contents other than food or garden waste, the bin will be
tagged, and you will be asked to remove the contaminants and present the bin at the next
scheduled collection date. Details of what can be put in your bin can be found online at:
Recycle Burgundy Bin 
What can I recycle in my burgundy bin? 
• Details of what can be put in your bin can be found online at: Recycle Burgundy Bins 
What can I do if my burgundy bin is damaged or lost during uplift? 
• Please report this online at Damaged recycling bins (blue/burgundy/grey) - South
Lanarkshire Council.  Damaged bins will be removed and replaced.  If your permit is
attached to the bin, a replacement bin and permit will be delivered free of charge.   
Will the council provide free compost bins to people so they can compost their
garden waste themselves? 
• No, however, we can provide advice and guidance on how to compost at home:
https://wasteless.zerowastescotland.org.uk/articles/easy-guide-to-composting-home. 
Is there any other way to apply and pay for the permit, other than online?
• We recommend you apply and pay online.  Should you have difficulty accessing the internet,
or require assistance, please call Waste Services on 0303 123 1020 
153

Page 154

154

Page 155

Report
Agenda Item 
Report to: Community and Enterprise Resources Committee
Date of Meeting: 18 June 2024
Report by: Executive Director (Community and Enterprise
Resources)  
Subject: Extension of the Household Waste and Recycling
Centres (HWRCs) Booking System 
1. Purpose of Report
1.1. The purpose of the report is to:-
[purpose]
 update the Committee on a proposal to extend the booking system to all Household
Waste and Recycling Centres (HWRCs) in South Lanarkshire
[1purpose]
2. Recommendation(s)
2.1. The Committee is asked to approve the following recommendation(s):-
[recs]
(1) the contents of the report be noted; and
(2) that the proposal to implement a booking system for visitors to the 6 Household
Waste and Recycling Centres (HWRCs) in South Lanarkshire be agreed with
implementation in line with the timetable at section 5.1.
[1s]
3. Background 
3.1. In November 2021, the Clydesdale Area Committee noted the introduction of a
booking system for residents visiting the Household Waste and Recycling Centre
(HWRC) in Carluke on a trial basis. The aims of the pilot were to: reduce waiting times
for residents; prevent queuing traffic on the access road to the site (long queues were
impacting on businesses located within Castlehill Industrial Estate); reduce incidences
of verbal and physical abuse being experienced by site staff; prevent residents from
other local authorities using the site; and reduce ‘trader abuse’. 
3.2. The booking system trial went live on Monday 21 February 2022. Over 27,000 booking
requests were made by residents in the first 6 months, almost 96% of which were
made using the simple on-line booking form embedded within the Council’s website.
The remainder of the bookings were made on behalf of the resident by the Council’s
Customer Contact Centre staff. Although residents were initially sceptical about the
requirement to book before visiting the site, the feedback was overwhelmingly positive,
and, on the 12 October 2022, the Clydesdale Area Committee noted the use of the
booking system on a permanent basis. During 2023/2024, over 59,000 bookings were
made with 98.6% of these bookings made online. 
3.3. The booking system for Carluke HWRC continues to receive positive feedback from
site users. A review of the responses received during 2023/2024 (1,280 responses,
16% return rate) shows that over 95% were satisfied with their experience of using the
site, 97% were satisfied with availability of slots; and more than 98% of respondents
10
155

Page 156

rated the booking system easy to use. The table below provides a breakdown of the
feedback received:- 
Ease of Use >98% satisfactory
or above
77% excellent <2% unsatisfactory
Availability of Slots >97% satisfactory
or above 
76% excellent < 2% unsatisfactory
Experience of
Using the Site
>95% satisfactory
or above
75% excellent <5% unsatisfactory 
3.4. Some comments from the most recent survey of site users at Carluke have been
provided below:- 
 “I would just like to say how much I appreciate the Carluke recycling centre. The
ease of booking a slot and the choice of visiting times available. Further, I have
to compliment the site personnel who are so helpful and friendly”.
 “Very easy to book, good slot availability and easy to access the site”.
 “Staff very helpful – the teams at Carluke are excellent, always willing to help,
give clear direction and keep the site very clean and tidy for users.”
 “Overall, a good system and very good user experience”. 
3.5. In addition to the positive feedback from site users, several operational and
environment benefits were identified, including:- 
 ability to manage service demand for the site throughout the day
 reduction in the number of unplanned site closures due to skip changeovers
(these can now be scheduled due to coincide with quieter periods)
 significant reduction in visitor turnaround/queuing times 
 significant reductions in queue lengths
 improved relations with local businesses in the area 
 reduction in Trader Abuse (i.e. commercial businesses illegally disposing of
waste at Carluke HWRC) 
 reduction in engine idling/ air pollution 
3.6. Since the introduction of the booking system at Carluke, Waste Services no longer
receive complaints about queue lengths from residents or local businesses in the
vicinity of the site. This is because the number of visitors (and vehicles) is spread
throughout the working day, which minimises the risk of residents arriving at the site
at the same time. The Service does, however, continue to receive complaints about
queuing traffic at the other HWRCs. The highest number of complaints relate to
queues at East Kilbride, Blantyre and Rutherglen sites. Residents regularly complain
about the queue lengths at peak times, businesses complain that the queues prevent
customers visiting their premises, and officers with Roads and Fleet Service have
raised concerns on several occasions about the impact that queuing traffic has on road
safety at these locations.   
3.7. The Council’s new contractual arrangements for the management and operation of 5
HWRCs (Strathaven, Larkhall, Blantyre, East Kilbride and Rutherglen) commenced on
1 April 2024. The contract, awarded to the incumbent service provider Biffa Ltd,
contained provisions that allowed the Council to require the contractor to implement a
booking system for visitors to the site. Waste Services have informally notified Biffa
Ltd that following approval by this Committee, the Council intends to invoke this
provision during financial year 2024/2025. Biffa Ltd have confirmed their support for
the booking system, noting that the system will enhance their ability to manage
demand, plan downtime and allow them to provide a better service to site users. 
156

Page 157

3.8. Of the 32 local authorities in Scotland, 9 now have a full booking system in place, one
has a partial system in place (South Lanarkshire) and the remaining 22 do not have a
booking system in place. The full list of local authorities is shown at Appendix 1. 
4. Proposal and Next Steps
4.1. It is proposed that the Committee approves current booking system at Carluke and the
expansion of the current booking system to Strathaven, Larkhall, East Kilbride,
Blantyre and Rutherglen HWRCs. Opening hours are shown in Appendix 2. This will
assist in the management of visitor numbers, minimise queuing times, reduce the
impact of queuing traffic on local businesses and improve road safety in areas where
the sites are located. The booking system will also reduce opportunities for ‘trader
abuse’ and prevent residents from other local authorities accessing South Lanarkshire
sites.  Finally, introducing a booking system at all HWRCs provides the Council with
the opportunity to standardise visitor arrangements throughout South Lanarkshire 
4.2. If approved, it is proposed that the booking system would ‘go-live’ on 12 August 2024.
Should approval be granted, Waste Services will work with Biffa Ltd, to ensure that
booking slots are maximised to mitigate the impact on residents. Waste Services will
also work with the Council’s corporate communication team to ensure residents are
made aware of the changes well in advance of the ‘go-live’ date. The campaign used
to promote the booking system for Carluke HWRC will be reviewed and updated for
this purpose. Communications will be issued 4 weeks before the ‘go-live date’ of the
12 August 2024. 
5.  Timeline
5.1. 
Action Date
Issue Communications to Residents 12 July 2024
Booking System ‘Go Live’ 12 August 2024 
6. Employee Implications
6.1. There are no employee implications associated with this proposal. 
7. Financial Implications
7.1. The cost of maintaining the on-line booking system is £5,000 per annum and will be
met from existing Waste Services revenue budget.  
8. Climate Change, Sustainability and Environmental Implications 
8.1. The booking system will reduce queue times and improve turnaround times at the
sites. Anecdotal evidence from Carluke HWRC suggest that there will be reduction in
the amount of engine idling on access roads to the sites, which will improve air quality
in the locality. 
8.2. The booking system confirmation e-mail advises site users to separate recyclable/
non-recyclable waste streams before visiting the site. This helps to improve recycling
and re-use rates and reduces the amount of non-recyclable waste requiring disposal. 
9. Other Implications
9.1. Shorter queues at the site will benefit visitors and local businesses. It will also improve
perceptions about road safety in the areas where the sites are located. 
157

Page 158

9.2. The booking system supports the Council’s channel shift agenda since currently
almost 99% of bookings are made on-line.   
10. Equality Impact Assessment and Consultation Arrangements
10.1. An equality impact assessment highlighted that the HWRC booking system may have
an impact on protected characteristics of age and disability. The impact of the system
will be mitigated by allowing residents to continue to make bookings via the customer
contact centre as well as via the online booking form. 
10.2. Evidence from introducing the booking system at Carluke HWRC demonstrates that
the booking system has been well received with high customer satisfaction rates being
reported by site users. 
10.3.  Benefits of the system include quick turnaround times and shorter queues for site
visitors. There have also been benefits to local businesses who were previously
impacted by traffic queuing on access roads to the site at peak times. 
10.4. Waste Services will monitor feedback from site users across all sites to identify any
previously unidentified impacts and address them accordingly. 
David Booth
Executive Director (Community and Enterprise Resources) 
28 May 2024 
Link(s) to Council Values/Priorities/Outcomes
Values
 Focused on people and their needs
 Accountable, effective, efficient and transparent
Priorities
 We will work towards a sustainable future in sustainable places
 We will work to recover, progress and improve
Outcomes
 Good quality, suitable and sustainable places to live
 Thriving business, fair jobs and vibrant town centres
 Caring, connected, sustainable communities 
Previous References
 Update on Household Waste and Recycling Centre (HWRC) Booking System - Carluke
Pilot, Clydesdale Area Committee - 12 October 2022 
List of Background Papers
 None 
Contact for Further Information
If you would like to inspect the background papers or want further information, please
contact:-
Kirsty McGuire, Waste Services Manager
Tel:  01698 717748)
E-mail:  Kirsty.McGuire@southlanarkshire.gov.uk
158

Page 159

Appendix 1 
Local Authority Booking system
Aberdeen City Council No
Aberdeenshire Council Yes
Angus Council No
Argyll and Bute Council No
City of Edinburgh Council Yes
Clackmannanshire Council No
Comhairle nan Eilean Siar No
Dumfries and Galloway Council Yes
Dundee City Council No
East Ayrshire Council Yes
East Dunbartonshire Council Yes
East Lothian Council No
East Renfrewshire Council Yes
Falkirk Council Yes
Fife Council Yes
Glasgow City Council No
Inverclyde Council No
Midlothian Council No
North Ayrshire Council No
North Lanarkshire Council No
Orkney Islands Council No
Perth and Kinross Council No
Renfrewshire Council No
Scottish Borders Council No
Shetland Islands Council No
South Ayrshire Council Yes
South Lanarkshire Council 1 out of 6 HWRCs
Stirling Council No
The Highland Council No
The Moray Council No
West Dunbartonshire Council No
West Lothian Council No 
159

Page 160

Appendix 2 
HWRC Centre Opening hours
Strathaven From 1 April to 30 September 
Monday – Friday 9am – 8pm 
Saturday 9am – 7pm 
Sunday 9am – 6pm
From 30 September – 31 March 
Monday – Sunday 8am – 5pm 
Closed Christmas and New Years Day
Larkhall From 1 April to 30 September 
Monday – Friday 9am – 8pm 
Saturday 9am – 7pm 
Sunday 9am – 6pm
From 30 September – 31 March 
Monday – Sunday 8am – 5pm 
Closed Christmas and New Years Day
East Kilbride From 1 April to 30 September 
Monday – Friday 9am – 8pm 
Saturday 9am – 7pm 
Sunday 9am – 6pm
From 30 September – 31 March 
Monday – Sunday 8am – 5pm 
Closed Christmas and New Years Day
Blantyre From 1 April to 30 September 
Monday – Friday 9am – 8pm 
Saturday 9am – 7pm 
Sunday 9am – 6pm
From 30 September – 31 March 
Monday – Sunday 8am – 5pm 
Closed Christmas and New Years Day
Rutherglen From 1 April to 30 September 
Monday – Friday 9am – 8pm 
Saturday 9am – 7pm 
Sunday 9am – 6pm
From 30 September – 31 March 
Monday – Sunday 8am – 5pm 
Closed Christmas and New Years Day 
160

Page 161

Report
Agenda Item 
Report To: Community and Enterprise Resources Committee
Date: 18 June 2024
Report by  Executive Director (Community and Enterprise
Resources)
Executive Director (Finance and Corporate Resources)  
Subject: Operational and Financial Implications of Managing
Waste Upholstered Domestic Seating (WUDs)
Containing Persistent Organic Pollutants (POPs) 
1. Purpose of Report
1.1. The purpose of the report is to:- 
 provide an update on the operational changes required to comply with the
Persistent Organic Pollutants (POPs) Regulations 2007 in respect to Waste
Upholstered Domestic Seating (WUDS)
 provide an estimate of the additional costs likely to be incurred by Waste Services
and Street Cleansing due to WUDS containing POPs being collected, transported
and treated in line with current legislative requirements
 seek approval to increase the Waste Services establishment for 3 FTE Waste
Operatives (Loaders) and 3 FTE Waste Operative (Drivers) on a permanent basis 
2. Recommendation(s)
2.1. The Committee is asked to approve the following recommendation(s):-
[recs]
(1) that the operational changes required to comply with the legislation be noted;
(2) that the additional financial implications associated with compliance be noted;
(3) that the increase to the Waste Services establishment by 6 FTE on a permanent
basis, as set out in sections 5.4 and 7.1, be approved; and
(4) that the increase in vehicle establishment for Grounds and Waste Services, as
detailed at sections 5.3 and 5.5, be approved. 
3. Background 
3.1. The Environment Agency in England recently published a study highlighting that the
presence of persistent organic pollutants (POPs) in waste upholstered domestic
seating (WUDS) was higher than the threshold limit set out in Persistent Organic
Pollutants Regulations 2007. These regulations, which are in force throughout the UK
(United Kingdom), implement the levels agreed in the Stockholm Convention. The
Scottish Environment Protection Agency (SEPA) enforce these regulations in
Scotland. Guidance on the management of WUDS containing POPs was published by
SEPA in October 2023. 
3.2. POPs are organic chemical substances which pose a risk to human health and the
environment due to their persistence in the environment, bioaccumulation through the
food chain and their transboundary nature. Wastes containing POPs above the
threshold levels must be managed in a way that destroys them (incineration). These
wastes cannot be landfilled. 
11
161

Page 162

3.3. There are specific requirements relating to the management of POPs waste which 
include:- 
 ban on the landfilling of POPs waste
 requirement to incinerate POPs waste
 preventing the mixing of POPs and non-POPs waste
 strict controls on the compaction of POPs waste
 ban on recycling/recovery of POPs waste 
3.4. At the time of writing, specific requirements for managing POPs waste apply to waste 
upholstered domestic seating (WUDS), namely:- 
 sofas, sofa beds, armchairs
 kitchen and dining chairs
 stools and footstools
 home office chairs, futons, beanbags
 floor and sofa cushions
 electrical recliner chairs
 any part made of or containing, leather, synthetic leather, other fabric, or foam. 
4. Current arrangements for collecting, transporting, and treating waste containing
WUDS
4.1. Waste and Grounds Services currently collect WUDS from 3 sources: bulky uplift
collections, fly-tipping, and at Household Waste and Recycling Centres (HWRCs). 
4.2. It is estimated that in 2023/2024, Facilities, Waste and Grounds Services collected
12,293 tonnes of bulky waste. Of this, 5,420 tonnes were collected via the Council’s
network of HWRCs. The remainder, approximately 6,873 tonnes, was collected from
bulk uplifts and fly-tipping. Evidence suggests that up to 20% of this waste could be
comprised of WUDS containing POPs.   
4.3. WUDS presented as part of bulk uplifts are collected by Waste Services, in refuse
collection vehicles (RCVs). WUDS in fly-tipped waste, is collected by Street Cleansing
in caged tippers. There is currently no separation of POPs and non-POPs waste and
WUDS collected in RCVs are subject to compaction, which contradicts the specific
requirements set out in Section 3.3. of this report.   
4.4. In terms of HWRC sites, separate skips for WUDS have been placed at 4 of the
Council’s 6 sites. Unfortunately, there is insufficient space at either Strathaven or
Larkhall to accommodate an additional skip meaning that WUDS cannot be accepted
at either site. 
5. Future Arrangements for collecting, transporting and treating WUDS
5.1. In order to comply with POPs legislation, a separate WUDS collection service is
required to ensure these items are collected, transported, bulked, hauled and treated
in accordance with the requirements of POPs legislation. 
5.2. Additional resources are required to facilitate the separate collection of WUDS in
Waste Services (bulky waste) and Street Cleansing (fly-tipped waste). 
5.3. Waste Services require three 7.5 tonne caged tippers to enable the separate collection
of WUDS from other bulky waste. The cost of these vehicles would be offset by
reduction in the refuse collection fleet, realising a saving of £0.005 million per annum. 
162

Page 163

5.4. Waste Services require to increase the employee establishment by an additional 6
FTE Waste Operatives to deliver the WUDS collection service. This is estimated to
cost £0.218 million per annum (Section 7.1). 
5.5. To facilitate the separate collection of WUDS by fly-tipping crews, Grounds would be
required to lease four 7.5 tonne caged tippers. The cost of increasing the vehicle
establishment in Grounds is £0.100 million per annum. 
5.6. Higher disposal costs for WUDS (estimated to be £0.231 million) will impact on the
Waste Disposal Budget. 
6. Future Mitigation
6.1. The Council’s current arrangements for the treatment of bulky waste end on 30
September 2025, although there is an option to extend the contract for a further 2-
year period. Waste Services will undertake a soft market testing exercise to identify
alternative suppliers who may be able to offer a cheaper gate fee for the processing
of WUDS waste. 
6.2. Waste Services will liaise with the Council’s corporate communications team to
promote re-use initiatives aimed at diverting upholstered domestic seating from the
waste stream. This will not only drive-up reuse rates but reduce the costs associated
with disposal of these items when they become waste. 
6.3. Waste Services will also look to establish the total costs for the collection, and
transportation of WUDs. This will allow us to consider amending bulk uplift charges for
these items to achieve full net cost recovery for the collection of WUDS. 
6.4. COSLA, who have recognised the additional burden this legislation places on councils,
is currently lobbying the Scottish Government for funding to cover the additional costs
of complying with this legislation. 
7. Employee Implications
7.1. Should the proposal to separately collect WUDS be approved, there will be a
requirement to increase the Waste Employee Establishment by 6 FTE on a permanent
basis. This is estimated to cost £0.218 million per annum. The breakdown of employee
costs is included below: 
Post FTE   Grade/SCP Hourly
Rate
Annual
Salary
Gross Cost
(inc. on costs
30.3%)  
Total
Annual
Costs
Waste
Operative
(Loaders)
3 Grade 1 Level 3
SCP 25-27
£12.81 
- 
£13.11
£25,140 
- 
£25,729
£32,757
-
£33,525 
£98,271 
-
£100,575
Waste
Operative
(Drivers)
3 Grade 1 Level 4 
SCP 30-31
£13.59 
-
£13.76
£29,682 
- 
£30,054
£38,676 
-
£39,160 
£116,028 
–
£117,480 
163

Page 164

8. Financial Implications
8.1. The total costs associated with complying with POPs legislation is estimated to be
£0.544 million per annum. This figure includes additional employee and vehicle costs
as well as the budget requirements associated with the higher gate-fee for treating
WUDS (£0.231 million per annum). 
8.2. It is proposed that funding currently held in reserves for Waste Services is utilised to
provide the additional costs in 2024/2025.  
9. Climate Change, Sustainability and Environmental Implications
9.1. The Persistent Organic Pollutants Regulations 2007 implement the agreements set
out in the Stockholm Convention, which is aimed at reducing the impact of POPs on
human health and the environment. This proposal will ensure the Council complies
with this legislation and takes the appropriate steps to mitigate the impact of WUDS
waste on the environment. 
10. Other Implications
10.1. The proposal would see the net vehicle establishment for Waste increase by two
vehicles (3 x 7.5 tonne caged tippers, replacing 1 x 26 tonne refuse collection vehicle)
and the vehicle establishment for Grounds increase by four 7.5 tonne caged tippers.
In total, there is a requirement for an additional seven, 7.5 tonne caged tippers across
the Facilities, Waste and Grounds Service. The costs would be offset by a reduction
of one 26 tonne open-backed refuse collection vehicle (currently used to collect bulky
waste). 
10.2. There is a legal requirement to separate POPs waste from other waste streams and
minimise the release of dust during collection, transport, and processing. The proposal
to separately collect WUDS in non-compaction vehicles, would allow the Council to
comply with its relevant legal obligations. 
10.3. The implementation of POPs Regulations 2007 in Scotland will see a reduction in the
amount of household waste that can be recycled, since WUDS must be incinerated
and cannot be recycled or re-used. However, the proposal limits this impact since the
bulky waste that is delivered separately from WUDS will still be able to be sorted and
recycled where possible.   
11. Equality Impact Assessment and Consultation Arrangements 
11.1. There are no equality impacts associated with the content of this report. 
11.2. The proposal relates to the implementation of statutory legislation and, therefore, no
consultation is required. 
David Booth
Executive Director (Community and Enterprise Resources) 
Jackie Taylor (Finance and Corporate Resources) 
28 May 2024 
164

Page 165

Link(s) to Council Values/Priorities/Outcomes
Values
 Focused on people and their needs
 Working with and respecting others
 Accountable, effective, efficient and transparent
 Ambitious, self-aware and improving
 Fair, open and sustainable
 Excellent employer
Priorities
 We will work to put people first and reduce inequality
 We will work towards a sustainable future in sustainable places
 We will work to recover, progress and improve
Outcomes
 Our children and young people thrive
 Good quality, suitable and sustainable places to live
 Thriving business, fair jobs and vibrant town centres
 Caring, connected, sustainable communities
 People live the healthiest lives possible
 Inspiring learners, transforming learning, strengthening partnerships 
Previous References
 None 
List of Background Papers
 None 
Contact for Further Information
If you would like to inspect the background papers or want further information, please
contact:-
Kevin Carr, Head of Facilities, Waste and Grounds Services
Tel:  01698 454708 
E-mail: kevin.carr@southlanarkshire.gov.uk 
165

Page 166

166

Page 167

Report
Agenda Item 
To: Community and Enterprise Resources Committee 
Date: 18 June 2024
Prepared by: Executive Director (Community and Enterprise
Resources)  
Subject: UK Levelling Up Fund Update and Next Steps 
1. Purpose of Report
1.1. The purpose of the report is to:- 
 provide an update on South Lanarkshire’s UK Levelling Up Fund (UKLUF)
awards
 seek approval for next steps 
2. Recommendation(s)
2.1. The Committee is asked to approve the following recommendation(s):- 
(1) that South Lanarkshire Council enter into legal agreements with UK Levelling Up
Fund (UKLUF) partners, that is Clyde Gateway Urban Regeneration Company
(URC) and Dumfries and Galloway Council, as required, as set out in section 5;
and
(2) that any implications of the upcoming General Election be noted. 
3. Background
3.1. As reported to the Community and Enterprise Resources Committee on 6 February
2024, 2 South Lanarkshire bids have been shortlisted for an allocation from UKLUF
Round 3:-
 National Business District (NBD): Shawfield Remediation and Development
 Three Rivers Active Tourism: Clydesdale Way (joint bid developed in partnership
with Dumfries and Galloway and Scottish Borders Councils) 
3.2. Full details of project values, UKLUF grant requested, and match funding requirements
are detailed in the table below:-
Project Name Partners Total Project
Value
LUF Grant
Requested
Match Funding
and Source
NBD: Shawfield
Remediation
and
Development
Clyde
Gateway
URC
£16,264,000 £14,637,600 £1,626,400
Clyde Gateway
Developments
Limited
Three Rivers
Active Tourism 
Partnership
Project:
-Clydesdale
Way 
-Annan Harbour
-Chambers
Institute 
Dumfries
and
Galloway
Council
(Lead
applicant) 
£25,343,796
of which:
£7,550,000 (SLC)
£13,131,796
(DGC)
£4,662,000 (SBC) 
£22,809,416 
of which:
£6,795,000 (SLC)
£11,818,616
(DGC)
£4,195,800 (SBC)
£2,534,380
of which:
£755,000 (SLC)
£1,313,180 (DGC)
£466,200 (SBC)   
12
167

Page 168

3.3. UK Government officials have confirmed that the provisional award of funding is
subject to UK Government departmental ‘sign-off’. 
3.4. In January 2024, Enterprise and Sustainable Development Service (ESDS) completed
validation checks for both awards, which have a total value of £21,432,600. 
3.5. ESDS is working closely with UK Government officials to fully understand the
implications of the upcoming General Election and any implications on timescales. 
4. UKLUF Project Summary 
4.1. National Business District: Shawfield Remediation and Development          
Developed in partnership with Clyde Gateway URC, this project will support
remediation and development at the National Business District – Shawfield Phase 2. 
The project will help address the historical legacy of chromium contamination at
Shawfield via ground remediation, improvements to the ground water and the
development of business space to stimulate local economic activity through
enhancement of the built environment, attracting and supporting business activity in
the Clyde Gateway area, and providing training and employment opportunities.       
4.2. Three Rivers Active Tourism: Clydesdale Way  
Developed in partnership with Dumfries and Galloway Council (Lead Applicant) and
Scottish Borders Council, the project is focussed on the Dumfriesshire, Clydesdale,
and Tweeddale constituency. The bid was developed to promote tourism, culture and
rural economies and is made up of three projects, one from each of the three local
authorities. South Lanarkshire’s project focuses on the rural path and cycling network
through the development of the Clydesdale Way. The Clydesdale Way will transform
access and connectivity within and between rural communities by enhancing the path
network and visitor infrastructure which will in turn support place, tourism, and local
community needs.     
5. UK LUF Next Steps
5.1. National Business District: Shawfield Remediation and Development
The project will be delivered by Clyde Gateway on behalf of South Lanarkshire Council
using the well-established governance structures Clyde Gateway and South
Lanarkshire Council have in place. Reporting and monitoring requirements are being
updated to reflect UK Government guidance. The Council will enter into a legal
agreement with Clyde Gateway to enable the release of funds. 
5.2. Three Rivers Active Tourism: Clydesdale Way 
A governance structure will be implemented which reflects the scale of the project
together with the reporting requirements of both the UK Government and Dumfries and
Galloway Council as lead applicant . The Council will enter into a legal agreement with
Dumfries and Galloway Council to enable the release of funds. 
6. Employee Implications
6.1. ESDS is working with colleagues across the Council to develop a Resource Schedule
which will identify staffing and support requirements within all services involved and
inform planning and work programmes. 
7. Financial Implications
7.1. Match funding values and sources are set out in this report. South Lanarkshire
Council’s match funding for the Clydesdale Way project is identified within existing
budgets.     
168

Page 169

8. Climate Change, Sustainability and Environmental Implications
8.1. The projects will make  significant contribution to the local environment through the
remediation of significant land contamination and the creation of new active travel and
leisure path networks. 
9. Other Implications 
9.1. The UKLUF awards provide significant capital investment in South Lanarkshire and
will contribute to priorities set out in Connect, the Council Plan 2022-27. 
10. Equality Impact Assessment and Consultation Arrangements
10.1. There is no requirement to carry out an impact assessment in terms of the updates
contained within this report. Consultation and project development activity is ongoing
with a number of Resources.   
David Booth  
Executive Director (Community and Enterprise Resources) 
7 June 2024 
Link(s) to Council Values/Priorities/Outcomes
Values
 Focused on people and their needs.
Priorities
 We will work towards a sustainable future in sustainable places.
 We will work to recover, progress and improve.
Outcomes
 Good quality, suitable and sustainable places to live.
 Thriving business, fair jobs and vibrant town centres.
 Caring, connected, sustainable communities.
 People live the healthiest lives possible. 
Previous References
 UK Levelling Up Fund: Round 3, Community and Enterprise Resource Committee, 6
February 2024
 UK Levelling Up Fund Update,  Community and Enterprise Resources Committee, 30
May 2023
 Members Briefing UK Funds Briefing 10 September 2021 
List of Background Papers
 None 
Contact for Further Information
If you would like to inspect the background papers or want further information, please
contact:- 
Pauline Crisp, Team Leader  
Enterprise and Sustainable Development Services 
Email: pauline.crisp@southlanarkshire.gov.uk 
169

Page 170

170

Page 171

Report
Agenda Item 
Report to: Community and Enterprise Resources Committee
Date of Meeting: 18 June 2024
Report by: Executive Director (Community and Enterprise
Resources)  
Subject: Scottish Government Play Investment Programme 
1. Purpose of Report
1.1. The purpose of the report is to:-
[purpose]
 provide an update on the progress to date on the Scottish Government’s Play
Area Investment Programme
[1purpose]
2. Recommendation(s)
2.1. The Committee is asked to approve the following recommendation(s):- 
(1) that the progress made to date on the 5-year Play Investment Programme be
noted.
[1recs]
3. Background
3.1. The Scottish Government launched a £60 million fund to renew play parks in Scotland,
in order that children have access to high-quality outdoor play in their own
communities. £10 million of funding was distributed across councils in 2021/2022 and
2022/2023, with the Council’s share totalling £0.594 million. The Scottish Government
has confirmed the full allocation which would see South Lanarkshire receiving a total
of £3.58 million up to 2025/2026. 
3.2. The original intention of the Government was to renew and transform all play areas in
Scotland. However, it was clear from the proposed funding package that this would
not be achievable. Due to the potential shortfall in funding, the Scottish Government
agreed that councils could identify their own investment priorities. Previously, the
Committee approved the appointment of 2 temporary Landscape Architects for 2 years
utilising the Scottish Government funding received to date. However, only one post
was able to be appointed, and the post holder independently assessed what was
required in each play area to bring it up to a basic standard. Unfortunately, the
employee left the Council to take up a job in the private sector and the Service has
been unable to externally recruit to backfill the post. This has meant that the Service
has had to re-profile internal resources within the landscape design team to prioritise
the investment programme. 
3.3. The Council completed an initial exercise to identify potential costs to bring all 233
play areas up to an appropriate standard rather than full renewal. This identified a
funding shortfall of approximately £620,000 to bring all play areas up to an appropriate
standard. 
13
171

Page 172

3.4. Prior to the assessment process starting, the Council also carried out a high-level
survey on play in general with 6,395 responses received. The consultation response
has been utilised as the Council begins implementation of the programme, with the
comments received for each site considered in more detail and further consultation
undertaken with local children, families, and ward members as proposals are
developed. 
3.5. Separate to this, there is a review of planning regulations, with the Planning Service
leading on the development of an Open Space Strategy which incorporates new play
sufficiency requirements, albeit the exact criteria for assessing play provision and
surrounding open space has not yet been confirmed. It is hoped that by ensuring that
all play areas meet a basic standard, this would help contribute to meeting future play
sufficiency requirements. To support the implementation of the programme, the
Service is also investigating an IT solution to capture and maintain up to date play
inspection and investment information. 
4. Investment Programme Current Position
4.1. The Scottish Government has confirmed the profile of funding that South Lanarkshire
Council will receive for the investment programme, including funding already received.
The Council will also continue to explore opportunities for external funding that could
be utilised to supplement the investment programme and maximise the benefit of
individual projects. 
Year Allocation (£m)
2022/2023 0.594
2023/2024 0.597
2024/2025 0.896
2025/2026 1.493
Total 3.580 
4.2. As highlighted in section 3.3, initial inspection of all play areas has shown a funding
shortfall of £620,000 to bring all sites up to an appropriate standard. A simple allocation
of the funding available across all current play areas, regardless of any other
considerations, would see minimal impact in many play areas. For some, funding
would only go some way to addressing accessibility issues, environmental conditions
or applying modern safety standards to historic locations i.e. new fencing for play
areas near roads. 
4.3. In December 2022, the Committee approved a more strategic place-based approach
to allocating specific investment that would see targeted investment in priority play
areas. The initial assessment of all play areas against appropriate standards has been
used as the basis of funding in each identified locality. This approach has also been
developed in collaboration with the local community and local ward members, building
on the consultation already undertaken and delivering local investment based on local
priorities. 
4.4. Given the multi-year profile of the funding, the following programme was agreed with
focus on specific localities each year. Within the programme there will be flexibility to
bring forward or push back projects as funding and staffing resource allows.  
172

Page 173

Year  Areas
Number
of sites
2023/2024 Larkhall, Rutherglen, Cambuslang 31 
2024/2025
Hamilton, Bothwell, Uddingston,
Blantyre, Strathaven and
surrounds 
36
2025/2026 East Kilbride 65
2026/2027 Clydesdale 101
Total 233 
4.5. Larkhall is the first area to receive investment with consultation undertaken with
elected members and local primary school, complementing the findings of a previous
local authority wide public survey which has led to the targeting of 6 sites for
investment. The investment will replace and/or add to existing play equipment to
improve play experiences for children of all abilities with an emphasis on improved
accessibility to play for all users. This will include surfacing where required to ensure
children of all abilities can enjoy the play experiences offered. This framework for
improvement meets the criteria for spend as indicated by the Scottish Government. 
4.6. Following a procurement exercise using the Council’s NEC3 Road and Infrastructure
framework, the contract for Larkhall was awarded in March 2024 with the works
commencing on site on the 27 May 2024, starting with Brown Street play area. It is
anticipated that the contract duration will be approximately 8 weeks for all 6 sites,
shown below. Designs are shown in Appendix A. 
 Glenview Memorial Park: will receive a range of additional play equipment to
complement the existing play experiences including a wheelchair accessible
climber and slide multi-play item, additional swings, seesaw, interactive music
panel and wheelchair accessible roundabout located within wet pour surfacing.
This will increase the level of play available for children of all abilities within a
popular play area accessed by residents throughout Larkhall. 
 Millheugh and Muirshot Street: additional inclusive play equipment will be
installed within with wet pour surfacing complementing existing provision. 
 Brown Street: the existing play area has been removed and a new fenced play
facility will be created within the open space. The play area will include a
toddler/junior inclusive multi-play item accessible for all, a basket swing, play
panel and inclusive spring mobile in addition to seating and a litter bin within wet
pour surfacing. The one set of swings shall also be replaced. The original play
area footprint towards Percy Street will be relandscaped addressing the obsolete
timber retaining structures creating a picnic and informal play space which can
be enjoyed by all ages. 
 Stewartgill Place (Ashgill): at the play area at the area of accessible open space
between the existing play equipment and the informal parking area will be utilised
for the installation of a wheelchair accessible roundabout, musical spring mobile,
multi-user spring mobile, seating and wheelchair accessible picnic table. The
proposed wet pour surfacing shall extend to the existing facility and incorporate
the existing slide providing an improved accessible route to the existing play
equipment will enhance the accessibility of the overall play area whilst providing
play experiences not catered for in the existing provision. 
173

Page 174

 Netherburn: flooding issues deterring access to the play provision has been
highlighted by the local community and, therefore, improved drainage will be
undertaken at this location to improve access to the existing play area for all. 
4.7. The confirmed value of the proposed investment for the Larkhall area is £0.340 million. 
4.8. The same process has been followed for the Cambuslang and Rutherglen area, with
consultation undertaken with elected members and local primary schools
complementing the findings of the previously mentioned local authority wide public
survey, which has identified the following 6 sites for investment. Designs are shown in
Appendix A. 
 Barnflat Street: play area will receive a complete upgrade with the iconic train
climbing frame and slide being the only items being retained. A new inclusive
play area will be constructed within the original play area footprint and will include
a range of inclusive equipment for the toddler and junior age range installed within
wet pour safer surfacing. The facility will feature traditional swings, basket swing,
inclusive spring mobile, interactive music ball, wheelchair accessible roundabout
and spinning net climber to complement the existing train climber and slide unit.
The existing multicourt area will be removed and relandscaped to improve
visibility creating a safe environment to play and a new multicourt will be
constructed with associated surfacing for ball games. 
 Cambuslang Park: play area is a large existing facility with a wide range of play
equipment and this will be enhanced by the provision of activity play panels and
the damaged interactive drums will be replaced. 
 Hamilton Crescent: additional inclusive play equipment will be installed in wet
pour safer surfacing, linking to existing tarmacadam access pathways to increase
accessibility for all. New equipment will consist of a basket swing, two interactive
musical items and an interactive panel all designed to complement the existing
play experiences. 
 Quarryfield Park: existing play equipment will be cleaned, repainted, and
repaired where required as there is no room for further development. The existing
damaged/obsolete wet pour surfacing shall be replaced throughout the play area
locations creating a safe play space for all children play within. 
 Fernhill Community Centre: the play area accessed from Sheildaig Drive, will
be further complemented with the addition of a climbing block feature providing
an additional challenge for older children. A trampoline jumping square will also
be installed within wet pour which promotes active play for all children including
wheelchair users. 
 Westburn Community Hall: the existing play area, associated multi-games and
skate equipment located within the open space will be enhanced by the provision
of wet pour surfacing within the area designed for young children incorporating
existing spring mobile play increasing accessibility for all. The wet pour surfacing
will be large enough to accommodate additional interactive music play items and
a spinning bowl roundabout. The existing gravel surfacing linking the play to the
existing skate equipment and access pathways will be replaced with tarmacadam
addressing potential hazards within the environment adjacent to the play area.  
174

Page 175

4.9. Following a procurement exercise using the council’s NEC3 Roads and Infrastructure
framework, evaluation of the Rutherglen/Cambuslang tender has been completed and
the contract has been awarded. The Council is awaiting the formal programme of
works from the appointed contactor. 
4.10. The confirmed value of the proposed investment for the Rutherglen and Cambuslang
area is £0.377 million. 
4.11. The Service has begun preparatory work on the Hamilton, Blantyre, Uddingston and
Bothwell areas which are next to receive detailed assessment, thereafter consultation
will commence with elected member and local primary schools to identify the play
areas to be targeted for investment. 
5. Employee Implications
5.1. Grounds Services has been unable to recruit additional temporary staff to support
delivery of the investment programme. The service has re-profiled the work
programme of the Landscape Design team to ensure the investment programme is
prioritised over the coming years. 
6. Financial Implications
6.1. South Lanarkshire Council has received £1.91 million of funding to date and has spent
£0.082 million, therefore, £1.109 million has carried forward into 2024/2025. The
remaining £2.389 million will be received during financial years 2024/2025 and
2025/2026 (as shown in section 4.1) and added to the Capital Programme as required.   
6.2. In addition to the £0.082 million already spent, £0.717 million of the grant funding has
been committed to projects in Larkhall, Cambuslang and Rutherglen. The remainder
of the funding (£2.781 million) will be committed over the rest of 2024/2025 and up to
2026/2027 as outlined in section 4.4. The bulk of the remaining funding will not be
received from the Scottish Government until 2025/2026. 
6.3. As the programme is implemented across South Lanarkshire, the Service will work
with colleagues and community groups to identify external funding opportunities that
could be used to further enhance the investment programme. 
6.4. It should also be noted that the investment programme is one off funding and does not
account for any increased maintenance costs over the long term of new and additional
play equipment. In addition, the Council may not be able to meet ongoing public
expectations to maintain these standards and this is something that COSLA has raised
with the Scottish Government on behalf of all councils. 
7. Climate Change, Sustainability and Environmental Implications
7.1. All play area improvements will create a more inviting and pleasant environment for
children and families to gather and, where possible, we will utilise natural site
characteristics more effectively to enhance the play experience and will increase tree
canopy cover and add other vegetation to improve climate change resilience. 
8. Other Implications
8.1. There are no implications for risk or other implications currently identified in terms of
the information contained within this report. 
175

Page 176

9. Equality Impact Assessment and Consultation Arrangements
9.1. The report does not introduce a new policy, function, or strategy or recommend a
change to an existing policy, function or strategy and, therefore, no impact
assessment or consultation is required. 
David Booth
Executive Director (Community and Enterprise Resources) 
30 May 2024 
Link(s) to Council Values/Priorities/Outcomes
Values
 Focused on people and their needs
 Working with and respecting others
Priorities
 We will work to put people first and reduce inequality
Outcomes
 Our children and young people thrive
 Good quality, suitable and sustainable places to live
 People live the healthiest lives possible 
Previous References
 Community and Enterprise Resources Committee – 28 September 2021
 Community and Enterprise Resources Committee – 13 December 2022 
List of Background Papers
 Community and Enterprise Resources Committee - Scottish Government 5 Year Play
Investment Programme Report - 13 December 2022 
Contact for Further Information
If you would like to inspect the background papers or want further information, please
contact:-
Jo Gillies, Senior Landscape Officer
Tel: 0198 717806
E-mail: jo.gillies@southlanarkshire.gov.uk 
176

Page 177

0,65
0,45
3,65
47.77
47.77
823
472
AREA 117.5m²
HIC 2.3m
1.2
1.2
1.2
1.2
1.2
1.2
0.3
HIC 1.2m
Area 59m²
Perimeter 30m
Multi spring seesaw Kompan Home Seesaw
Kompan Ref: M186
Wheelchair accessible Carousel Roundabout
Kompan Ref: PCM157
Inclusive Junior Multi-play unit , Sutcliffe Scramble and Slide Ref: PZW686
1.8m two seat swing  to be supplied with cradle seats
Sutcliffe Play: SWB062Z
Playdale City Bench Ref: BEN
Existing play equipment located on
grass matting to be retained on site
Existing significantly decayed tree has
been removed. Stump grinding will be
required
Proposed wet pour surface creating accessibility
for all to utilise inclusive play equipment experiances
Inclusive Helicopter Spring
Mobile Proludic J836
Install Kompan Music Play Panel
Proludic HelicopterRef: J836
a
e d c b
95
B 7019
99
43
B 7078
B 7078
GLENVIEW
Memorial
War
102.9m
CR
5961
35
10
18
40
31
21
11
6
9
B 7078
4
2
15
1
272
93
2
4
8
54
51
11
1
1
2
3
4
1
5
53
57
Sub StaElB 7078
CADZOW STREET
102.4m
GLENVIEW
DOUGLAS STREET
103.3m
B 7019
B 7019
60
GXY932*278cm
74m²
GXY932_150.tgaGXY92644.8m²*180
C
:
\
D
o
c
u
m
e
n
t
s
a
n
d
S
e
t
t
i
n
g
s
\
M
i
c
h
a
e
l
H
e
a
l
d
\
M
y
D
o
c
u
m
e
n
t
s
\
M
y
P
i
c
t
u
r
e
s
\
k
o
m
p
a
n
\
G
X
Y
9
2
6
_
E
N
_
S
C
A
.
j
p
g
GXY801410m²*100
GXY8014_25.tga
GXY801510m²*100
C:\Documents and Settings\Michael Heald\My Documents\My Pictures\kompan\GXY8015_EN_SCA.jpg
3,45
0,65
0,45
3,65
3,40
3,600,60
0,40 0.9
HIC 0.9m29m²
9
6
11
21
31
40
18
10
35
61
59
CR
.
WarMemorial
Glen View
Memorial
Park
B7078
43
B 7019
bcde
B 7019
103.3m
DOUGLASSTREET
CADZOWSTREET
57
53
5
1
4
3
2
1
1
51
54
8
4
2
2
4
0B 7019
Changes in level should be site.
Only access point onto the
AREA 64m²
HIC 1.3m
COMMUNITY & ENTERPRISE RESOURCES
S O  U  T  H
LANARKSHIRE
C O  U  N  C I L
Project Title:
Drawing Title:
Scale @ A1:
Drawing No:
Drawn by: Date: Checked by:
Drawing: I:\GIS\Specialist\Data\Open\M
ichael Heald\C
drive december 2022\play design sufficiency information\Larkhall area\Councillor Submission\Glenview
M
emorial Park Proposed Investment.dwg By: healdm
DO NOT SCALE DIMENSIONS FROM THIS DRAWING
ALL DIMENSIONS TO BE VERIFIED ON SITE.
Reproduced from the Ordinance Survey mapping with the permission of the Controller of Her
Majesty's Stationery Office © Crown copyright. Unauthorised reproduction infringes Crown
copyright and may lead to prosecution or civil proceedings. South Lanarkshire Council:
LA090472.
Facilities, Waste And Grounds Services -
Landscape Development Section
Notes:
© South Lanarkshire Council Community Resources
Tel: 01698717806                      Fax 01698717750
PSIP_GMP_MRH_01
12/10/23MRHAs Shown
Contract Drawing
Glenview Memorial Park, Larkhall
Additional Investment Proposals
Ward 20
Play Sufficency  Investment Programme
Proposed Play Area Investment Glenview Memorial Park, Larkhall Scale 1:100
Location of existing play facility
Existing play area to be retained
Location of proposed wet pour surfacing
Glenview Memorial Park  Location Plan
Scale 1:1250
and additional play equipment
13
177

Page 178

Mill Leat
Weir
Fish Ladder
41
(PH)
Applebank Inn
37
33
MILLHEUGH
29
FB
FB
Avon House
FB
Lower exposed pc concrete pin kerbs
to create a 1800mm entrance to proposed
wet pour area
Wheelchair accessible Carousel Roundabout
Kompan Ref: PCM157
Proposed Sutcliffe Inclusive
Springie SSB300
Proposed Kompan Crazy Daisy
Ref: M128Existing Jupiter multi-play item
to be retained
Existing retained swingsExisting Jupiter rotary item
Existing Jupiter roll up item
to be retained
COMMUNITY & ENTERPRISE RESOURCES
Project:
Drawing:
Scale @ A1:
Drawing No:
Drawn by: Date: Checked by:
Drawing: I:\GIS\Specialist\Data\Open\Michael Heald\C
drive december 2022\play design sufficiency information\Larkhall area\Councillor Submission\Millheugh Play Area Proposed Investment.dwg By: healdm
DO NOT SCALE DIMENSIONS FROM THIS DRAWING
ALL DIMENSIONS TO BE VERIFIED ON SITE.
Reproduced from the Ordinance Survey mapping with the permission of the Controller of
Her Majesty's Stationery Office © Crown copyright. Unauthorised reproduction infringes
Crown copyright and may lead to prosecution or civil proceedings. South Lanarkshire
Council: LA090472.
Facilities, Waste & Grounds Services,
Landscape Development Section
Notes:
© South Lanarkshire Council Community Resources
Tel: 01698 717740
S O  U  T  H
LANARKSHIRE
C O  U  N  C I L
Drawing Status:
Location:
PSIP_M_MRH_01
12/10/23MRHAs Shown
Contract Drawing
Additional Investment Proposals Millheugh, Larkhall
Ward 20
Play Sufficency  Investment Programme
Proposed Play Area Investment Millheugh, Larkhall Scale 1:100
Millheugh  Location Plan
Scale 1:1250
178

Page 179

MEADOWHILL STREET
Existing swings to be
retained
Existing tarmacadam surfacing
to be retained
Existing tarmacadam surfacing
to be retained
Existing spring elephant to be
retained
Existing steel climbing frame to be
removed and replaced with an inclusive
wheelchair accessible roundabout
Proposed steel bench and litter bin
PC 600mm x 600mm concrete slabs
Existing woodchip area to be removed
and replaced with accessible wet pour
Proposed additional Jupiter Inclusive
Minisphere play panel supplied by SLC
2
Wynd
25
2
2
MEADOWHILL STREET
1
Braeside Lane1
37
29
19
18
8
Bank Way
119
Parknook
Sub
Way
El
18
Sighthill
2
13
107
Glenburn
Loan
7
47
MATTHEW
MCWHIRTER PLACE
Portland Wynd
Sta
19
29
2
2
8
Portland Wynd
George
Way
Albany Wynd
16
11
7
8
MUIRSHOT ROAD
11
2
COMMUNITY & ENTERPRISE RESOURCES
S O  U  T  H
LANARKSHIRE
C O  U  N  C I L
Project Title:
Drawing Title:
Scale @ A1:
Drawing No:
Drawn by: Date: Checked by:
Drawing: I:\GIS\Specialist\Data\Open\Michael Heald\C
drive december 2022\play design sufficiency information\Larkhall area\Councillor Submission\Muirshot Road Play Area Proposed Investment.dwg By: healdm
DO NOT SCALE DIMENSIONS FROM THIS DRAWING
ALL DIMENSIONS TO BE VERIFIED ON SITE.
Reproduced from the Ordinance Survey mapping with the permission of the Controller of
Her Majesty's Stationery Office © Crown copyright. Unauthorised reproduction infringes
Crown copyright and may lead to prosecution or civil proceedings. South Lanarkshire
Council: LA090472.
Facilities, Waste And Grounds Services -
Landscape Development Section
Notes:
© South Lanarkshire Council Community Resources
Tel: 01698717806                      Fax 01698717750
PSIP_MR_MRH_01
12/10/23MRHAs Shown
Contract Drawing
Additional Investment Proposals Muirshot Road Play Area
Ward 20
Play Sufficency  Investment Programme
Proposed Play Area Investment Muirshot Road , Larkhall Scale 1:100
Location of existing play facility
Muirshot Road Location Plan Scale 1:1250
179

Page 180

17
16
0.9
38m²0.9m
0.9
0.3
Inclusive Helicopter Spring
Mobile Proludic J836
Steel Swing with basket seat Ht. 2.5m
Kompan Ref: KSW92008
RoSPA accredited Bow top fencing
height 900mm with self closing gates
Existing swings retained
surfacing replaced with wet pour
Inclusive Toddler / Junior Multi-play unit , Sutcliffe Pull Up unit Ref: DZW353
Inclusive Kompan Creative
play panel supplied by SLC
Self closing access gate
RoSPA accredited 1.0m wide
Tarmacadam access path 1200mm wide
with pc concrete pin kerb edging
Tarmacadam access path 1200mm wide
with pc concrete pin kerb edging
Self closing access gate
RoSPA accredited 1.0m wide
17
16
14
BROWN STREET
9
4
30
COURT
33
35
BAREFIELD STREET
1b
28
1
2
5
80
2021
7
VICTORIA
43
1a
Link path
Link path
Log seating forming edge to informal
natural play area
Proposed picnic bench
Proposed picnic bench Proposed play boulders
Proposed play boulders
Existing woodchip area removed, top soiled and returned to grass
COMMUNITY & ENTERPRISE RESOURCES
Project:
Drawing:
Scale @ A1:
Drawing No:
Drawn by: Date: Checked by:
Drawing: I:\GIS\Specialist\Data\Open\Michael Heald\C
drive december 2022\play design sufficiency information\Larkhall area\Councillor Submission\Brown Street Proposed Investment.dwg By: healdm
DO NOT SCALE DIMENSIONS FROM THIS DRAWING
ALL DIMENSIONS TO BE VERIFIED ON SITE.
Reproduced from the Ordinance Survey mapping with the permission of the Controller of
Her Majesty's Stationery Office © Crown copyright. Unauthorised reproduction infringes
Crown copyright and may lead to prosecution or civil proceedings. South Lanarkshire
Council: LA090472.
Facilities, Waste & Grounds Services,
Landscape Development Section
Notes:
© South Lanarkshire Council Community Resources
Tel: 01698 717740
S O  U  T  H
LANARKSHIRE
C O  U  N  C I L
Drawing Status:
Location:
PSIP_BS_MRH_01
12/10/23MRHAs Shown
Contract Drawing
Additional Investment Proposals Brown Street Play Area
Ward 20
Play Sufficency  Investment Programme
Proposed Play Area Investment Brown Street , Larkhall
Original play area removed and returned to grass
creating a natural play open space linking to existing
soft landscape . Timber log retainers removed off site
Proposed new play area created where existing
swings are located. Site to be accessible for all
Brown Street Location PlanScale 1:500
Proposed New Inclusive Play Area Scale 1:100
Proposed re-landscaped existing play area introducing natural play and seating
Scale 1:100
180

Page 181

32
40
1 1
36
10CRESCENT
15
13
1738
CENTRAL
30
5
34
1
4
8
Shelter
1
2
10
12
16
8
PLACE
5
GRAHAM
4
14
PLACE
STEWARTGILL
105.4m
10
1
6
10
3
11
ESS
Hall
Ashlea
Dalserf Primary School
20
8
6
1
14
1
24
922
4
2
20
3
1
Existing wet pour area with
multiplay climbing unit to be
retained
Existing items of equipment within
grass matting surfacing
Proposed spring seesaw
Kompan Crazy Daisy M128
Proposed Playdale steel bench
Ref:BEN
Existing slide to receive wet pour
safer surfacing
Existing swings to receive wet pour
safer surfacing
Proposed wet pour safer surfacing linking existing
surfacing provision creating accessibility for all
Existing car park
Wheelchair accessible Carousel Roundabout
Kompan Ref: PCM157
Proposed Jupiter musical Orb
Ref:IP05
Proposed Broxap picnic table
extended with wheelchair access
Proposed Playdale steel litter bin
length 2100mm with root fixings  colour brown
COMMUNITY & ENTERPRISE RESOURCES
Project:
Drawing:
Scale @ A1:
Drawing No:
Drawn by: Date: Checked by:
Drawing: I:\GIS\Specialist\Data\Open\Michael Heald\C
drive december 2022\play design sufficiency information\Larkhall area\Councillor Submission\Stewartgill Place Ashgill Public Park Proposed Investment.dwg By: healdm
DO NOT SCALE DIMENSIONS FROM THIS DRAWING
ALL DIMENSIONS TO BE VERIFIED ON SITE.
Reproduced from the Ordinance Survey mapping with the permission of the Controller of
Her Majesty's Stationery Office © Crown copyright. Unauthorised reproduction infringes
Crown copyright and may lead to prosecution or civil proceedings. South Lanarkshire
Council: LA090472.
Facilities, Waste & Grounds Services,
Landscape Development Section
Notes:
© South Lanarkshire Council Community Resources
Tel: 01698 717740
S O  U  T  H
LANARKSHIRE
C O  U  N  C I L
Drawing Status:
Location:
PSIP_APP_MRH_01
12/10/23MRHAs Shown
Contract Drawing
Additional Investment Proposals, Ashgill Public Park
Ward 20
Play Sufficency  Investment Programme
Proposed Play Area Investment Ashgill Public Park, Larkhall Scale 1:100
Ashgill Public Park  Location Plan Scale 1:1250
181

Page 182

OVERTON ROAD
52
66
OVERTON ROAD 145.2m
ANNABELLA
ROAD
HONEYCOMB PLACE
1
1
11
13
H
I
C
1
m
2
1
m
²
0.9
0.9
0.9
H
I
C
0
.
9
m
3
3
m
²
H
I
C
0
.
6
m
1
0
m
²
H
I
C
0
.
6
m
1
0
m
²
1.2
1.5
H
I
C
1
.
5
m
1
2
m
²
H
I
C
2
.
4
m
4
4
m
²
Hall
Roddingeye
Existing 100mm diameter perforated plastic branches
Existing 150mm diameter perforated plastic main drain
David Ogilvie
"Balmoral"
90ltr. litter bin
20mm size rounded washed gravel
100mm diam U.P.V.C. rigid slotted drain
New Connection
Drain Detail
Geotextile Liner
Approximate indication of finishedground levels
0.30
0.30
0.10
Scale 1:10
1.5
Existing 100mm diameter perforated plastic branches
Existing 150mm diameter perforated plastic main drain
David Ogilvie
"Balmoral"
90ltr. litter bin
Existing tarmacadam
pathway
Existing tarmacadam
pathway
Existing tarmacadam
pathway
Existing tarmac surface to be
removed and area regulated to
form falls towards new gully
and resurfaced with
tarmacadam 11 m2
Proposed new pin kerb to edge additional
tarmacadam area 2.5 lm
Proposed new
tarmacadam edge to
gully 1m2
Proposed new 100mm diameter drainage pipe
connecting new gully to existing 150mm
drainage pipe 3 lm
20mm size rounded washed gravel
100mm diam U.P.V.C. rigid slotted drain
New Connection
Drain Detail
Geotextile Liner
Approximate indication of finished
ground levels
0.30
0.30
0.10
Scale 1:10
COMMUNITY & ENTERPRISE RESOURCES
S O  U  T  H
LANARKSHIRE
C O  U  N  C I L
Project Title:
Drawing Title:
Scale @ A1:
Drawing No:
Drawn by: Date: Checked by:
Drawing: I:\GIS\Specialist\Data\Open\M
ichael Heald\C
drive december 2022\play design sufficiency information\Larkhall area\Councillor Submission\Netherburn Play Area Proposed Investment.dwg By: healdm
DO NOT SCALE DIMENSIONS FROM THIS DRAWING
ALL DIMENSIONS TO BE VERIFIED ON SITE.
Reproduced from the Ordinance Survey mapping with the permission of the Controller of Her
Majesty's Stationery Office © Crown copyright. Unauthorised reproduction infringes Crown
copyright and may lead to prosecution or civil proceedings. South Lanarkshire Council:
LA090472.
Facilities, Waste And Grounds Services -
Landscape Development Section
Notes:
© South Lanarkshire Council Community Resources
Tel: 01698717806                      Fax 01698717750
PSIP_N_MRH_01
12/10/23MRHAs Shown
Contract Drawing
Additional Investment Proposals Netherburn Play Area
Ward 20
Play Sufficency  Investment Programme
Proposed Play Area Investment Netherburn Scale 1:100
Netherburn  Location Plan
Scale 1:1250
182

Page 183

Hall
3.46
3.57
Proposed Jupiter Music Ball
Ref:IP500M
Existing tarmacadam excavated and removed
off site. The remaining construction stone to
be reused for regulating within the proposed
wet pour surfacing and new path access, 226 m2
Existing tarmacadam excavated and removed
off site. The remaining construction stone to
be reused for regulating within the proposed
wet pour surfacing and new path access. Hand dig
where existing tree roots are encountered, 24 m2
Existing tarmacadam excavated and removed
off site. The remaining construction stone to
be reused for regulating within the proposed
wet pour surfacing and new path access, 56 m2
Timber retaining sleepers to be broken out
and removed off site. Existing retained soil
to be re-graded reducing area available for
multi-court, 48 lm.
Proposed Multi Court to be Inclusive J22200A
Installed on new porous tarmacadam surface
Proposed Kompan Inclusive
Twister Ref: COR20330
Proposed Sutcliffe Inclusive
springie Ref: SSB300
Proposed Jupiter Wheelspin
inclusive roundabout  Ref: IP12
Proposed Playdale City Bench
Ref: BEN
Proposed Kompan steel swing 2.5m,
100cm  Rope Seat, Anti-wrap  Ref: KSW92012
Existing Wicksteed Steam Engine Climbing Frame and Slide
To Be Retained, Repainted And Located Within New Wet Pour Surfacing
Entrance reopened with relocation of
steel pedestrain road barrier fencing
Existing tarmacadam excavated and removed
off site. The remaining construction stone to
be reused for regulating within the proposed
wet pour surfacing and new path access, 34 m2
27
28
19
40
36
23
31
2
4
25
21
29
17
34
3826
3
2 to 12
to 20 14
22 to 32
9
1
MONTRAIVE STREET
5
7 to 11
2
15
12
1
STREET
Kingdom
BARNFLAT
AVENUE STREET
Warehouse
7 to 11
Hall
Hall
BARNFLAT COURT
6
COMMUNITY & ENTERPRISE RESOURCES
S O  U  T  H
LANARKSHIRE
C O  U  N  C I L
Project Title:
Drawing Title:
Scale @ A1:
Drawing No:
Drawn by: Date: Checked by:
Drawing: I:\GIS\Specialist\Data\Open\Michael Heald\C
drive december 2022\play design sufficiency information\Rutherglen and Cambuslang\Councillor Submission\Barnflats Street Councillor.dwg By: healdm
DO NOT SCALE DIMENSIONS FROM THIS DRAWING
ALL DIMENSIONS TO BE VERIFIED ON SITE.
Reproduced from the Ordinance Survey mapping with the permission of the Controller of
Her Majesty's Stationery Office © Crown copyright. Unauthorised reproduction infringes
Crown copyright and may lead to prosecution or civil proceedings. South Lanarkshire
Council: LA090472.
Facilities, Waste And Grounds Services -
Landscape Development Section
Notes:
© South Lanarkshire Council Community Resources
Tel: 01698717806                      Fax 01698717750
PSIP_BF_MRH_02_2
30/01/24MRHAs Shown
Tender
Proposed  New Play Facility and MUGA Provision
Barnflat Street Play Area Investment
Ward 12
Play Sufficency  Investment Programme
Proposed Play Area Investment Barnflat Street, Rutherglen. Proposed Design Scale 1:100
Location of play area investment
Location Plan
Scale 1:1250
183

Page 184

Play Area
Supply and install Tuned Drums
Available from Inclusive Play Ref: IPTD
Install Kompan Emotion Classic Play Panel
Supplied By South Lanarkshire Council
Remove damaged musical drums and replace with new drums .
Works shall include for all tarmcadam reinstatement
Existing trampoline
Existing wheelchair
accessible roundabout
Existing pedestrian
pathway
Existing spring
mobiles
Existing small
climbing frame unit
EAST GREENLEES GARDENS
75.3m
8
2
ESS
1
9
34 to 49
18 to 33
EAST
3GREENLEES
CRESCENT
18
63.1m
LB
65.2m
10
11
3
Sports Court
4
HOLLYBANK PLACE
61.0m
96
106
62.5m
86
96
2
63.5m
11
5
15
EAST
112
102
COMMUNITY & ENTERPRISE RESOURCES
Project:
Drawing:
Scale @ A1:
Drawing No:
Drawn by: Date: Checked by:
Drawing: I:\GIS\Specialist\Data\Open\Michael Heald\C
drive december 2022\play design sufficiency information\Rutherglen and Cambuslang\Councillor Submission\cambuslang park Councillor.dwg By: healdm
DO NOT SCALE DIMENSIONS FROM THIS DRAWING
ALL DIMENSIONS TO BE VERIFIED ON SITE.
Reproduced from the Ordinance Survey mapping with the permission of the Controller of
Her Majesty's Stationery Office © Crown copyright. Unauthorised reproduction infringes
Crown copyright and may lead to prosecution or civil proceedings. South Lanarkshire
Council: LA090472.
Facilities, Waste & Grounds Services,
Landscape Development Section
Notes:
© South Lanarkshire Council Community Resources
Tel: 01698 717740
S O  U  T  H
LANARKSHIRE
C O  U  N  C I L
Drawing Status:
Location:
PSIP_CP_MRH_02
15/01/24MRHAs Shown
Tender
Cambuslang Park Play Area Investment
Ward 13
Play Sufficency  Investment Programme
Proposed Play Area Investment Cambuslang Park,  Cambuslang
Scale 1:100
Location of play area investment
Location Plan
Scale 1:1250
184

Page 185

AREA
38.5M²
PERIMETER
24.8M
HIC
1.6M
Proposed Wet pour area for proposed additional inclusive play
equipment (DDA compliant) and possible additional
equipment 63m2
Steel Swing with basket seat Ht. 2.5m
Kompan Ref: KSW92008
Proposed Jupiter musical Orb
Ref:IP05
Proposed Jupiter Music Ball
Ref:IP500M Proposed Jupiter Colourfly
Ref:IP304 supplied by SLC
Existing Kaiser Kuhne spring mobile  to be retained
Existing Sutcliffe spinning bowl to be retained with the
grass matting
Existing Sutcliffe multi-play item to be retained
Existing tarmacadam pathway incorporating seating to be retained
Existing Sutcliffe inclusive spring mobiles  to be retained
Existing Sutcliffe toddler swings and seesaw to be retained with the
grass matting
Existing play equipment retained within grass matting
Existing play equipment retained within grass matting
safer surfacing
Existing Bowtop 1.00m high steel boundary fence
1.00m wide access gate
1.00m wide access gate
Existing tarmacadam pathway incorporating seating to be retained
Proposed precast concrete pin kerb edging
Existing bow top boundary fence to be retained
148
36
31
26
146
41
11
1
151
145
52
50
58
49.1m
15
206
1
12
AVENUE
25
22
WOODLAND CRESCENT
23
2
El
11
JANEBANK
1
65
81
2
10
4
44
54
60
2a
15
LANGCROFT AVENUE
LANGCROFT PARK
14234.7m
HAMILTON CRESCENT
12
62
2b
72
3
111
3
LB
70
2c
53
1
71
91
11
78
101
10
11
1
145
17
14
123
133
9
CAIRNSW
ELL
PLACE
Sub Sta
LB
19
ROSEBANK DRIVE
1
2
132
Gas Gov
139
109
119
129
El Sub Sta
214
12
153
143
HAMILTON
204
102
112
101
113
CRESCENT
DRIVE
LANGCROFT
1
192
109
92
90
Shelter
95
MAC CALLUM DRIVE
3615
99
10
23
Terram 1000
200 x 50 mm flat top pin kerb300mm x100 mm ST1 concrete foundation,
haunching and 10 mm mortar bed
0
.
1
5
wet pour depth to vary dependant on
critical fall height
Minimum depth of 150mmcompacted type 1 sub-base
0
.
1
5
Wet pour depth 60mm for BasketSwing CFH 1.45m
Wet pour depth 40mm for interactive
musical items and play panel CFH1.00m and less.
0
.
1
7
Terram 1000
200 x 50 mm flat top pin kerb
300mm x100 mm ST1 concrete foundation,
haunching and 10 mm mortar bed
0.15
wet pour depth to vary dependant on
critical fall height
Minimum depth of 150mm
compacted type 1 sub-base
0.15
Wet pour depth 60mm for Basket
Swing CFH 1.45m
Wet pour depth 40mm for interactive
musical items and play panel CFH
1.00m and less.
0.17
COMMUNITY & ENTERPRISE RESOURCES
Project:
Drawing:
Scale @ A1:
Drawing No:
Drawn by: Date: Checked by:
Drawing: I:\GIS\Specialist\Data\Open\Michael Heald\C
drive december 2022\play design sufficiency information\Rutherglen and Cambuslang\Councillor Submission\Hamilton Crescent Councillor.dwg By: healdm
DO NOT SCALE DIMENSIONS FROM THIS DRAWING
ALL DIMENSIONS TO BE VERIFIED ON SITE.
Reproduced from the Ordinance Survey mapping with the permission of the Controller of
Her Majesty's Stationery Office © Crown copyright. Unauthorised reproduction infringes
Crown copyright and may lead to prosecution or civil proceedings. South Lanarkshire
Council: LA090472.
Facilities, Waste & Grounds Services,
Landscape Development Section
Notes:
© South Lanarkshire Council Community Resources
Tel: 01698 717740
S O  U  T  H
LANARKSHIRE
C O  U  N  C I L
Drawing Status:
Location:
PSIP_HC_MRH_02
18/12/23MRHAs Shown
Tender
Hamilton Crescent Play Area Investment
Ward 14
Play Sufficency  Investment Programme
Proposed Play Area Investment Hamilton Crescent Cambuslang Scale 1:100
Location of play area investment
Hamilton Crescent Play Area Location Plan
Scale 1:2500
Wet Pour Construction Detail Scale 1:10
185

Page 186

Existing wet pour surfacing pin kerb
edging
All existing wet pour surfacing to be lifted and removed off site
to an approved disposal site. All edging, play equipment and stone
base to be retained 264 m2
Existing seating to be retained
Existing seating to be retained
Existing Sutcliffe junior swings to be retained
Existing spring mobiles to be retained
Existing seating to be retained
Existing Sutcliffe toddler swings to be retained
Existing Sutcliffe basket swing to be retained
Existing Sutcliffe spinning bowl to be retained
All existing wet pour surfacing to be lifted and removed off site
to an approved disposal site. All edging, play equipment and stone
base to be retained 195 m2
Existing Sutcliffe 2 up 1 down multi-play unit
with a critical fall height of 0.9m
Existing Inclusive Sutcliffe Scramble and Slide multi-play unit
with a critical fall height of 1.2m
with a critical fall height of 1.0m
with a critical fall height of 1.5m
with a critical fall height of 0.9m
with a critical fall height of 1.2m
with a critical fall height of 1.5m
0.3
1.2
1.2
1.2
1.8
1.21.2 1.8
1.2
HIC 1.2m
41.5m ²
HIC 2.4m
46m²
Existing Inclusive Sutcliffe Scramble and Slide multi-play unit
with a critical fall height of 2.4m
El Sub Sta
96
102
100
86
78
88
26
84
76
33
21.6m
31
SALVIA STREET
10
0.3
1.2
1.2
1.2
1.8
1.21.2
1.8
1.2
HIC 1.2m
41.5m ²
HIC 2.4m
46m²
COMMUNITY & ENTERPRISE RESOURCES
Project:
Drawing:
Scale @ A1:
Drawing No:
Drawn by: Date: Checked by:
Drawing: I:\GIS\Specialist\Data\Open\Michael Heald\C
drive december 2022\play design sufficiency information\Rutherglen and Cambuslang\Councillor Submission\Quarryfield Park Councillor.dwg By: healdm
DO NOT SCALE DIMENSIONS FROM THIS DRAWING
ALL DIMENSIONS TO BE VERIFIED ON SITE.
Reproduced from the Ordinance Survey mapping with the permission of the Controller of
Her Majesty's Stationery Office © Crown copyright. Unauthorised reproduction infringes
Crown copyright and may lead to prosecution or civil proceedings. South Lanarkshire
Council: LA090472.
Facilities, Waste & Grounds Services,
Landscape Development Section
Notes:
© South Lanarkshire Council Community Resources
Tel: 01698 717740
S O  U  T  H
LANARKSHIRE
C O  U  N  C I L
Drawing Status:
Location:
PSIP_QP_MRH_02
18/12/23MRHAs Shown
Tender
Quarryfield Park Play Area Investment
Ward 13
Play Sufficency  Investment Programme
Proposed Play Area Investment Quarryfield Park, Rutherglen Scale 1:100
Location of play area investment
Quarryfield Park Location Plan
Scale 1:500
186

Page 187

SHIELDAIG
DRIVE
Existing tarmac path
HIC 1.7m58m²
0.9
0.9
0.9
AREA 25.3m²HIC 1m
MH
EXISTING GRASS AREA
EXISTING GRASS AREA
Existing tarmac path
Proposed Jumper Square
Kompan Ref: JUM101
Proposed Focal Feature Climbing Bloqx
Kompan Ref: BLX4103
Proposed wet pour surfacing
providing accessability for all
Proposed Additional Play Equipment
Existing Play Area
Existing Play Area
Existing Play Area
Proposed Pin Kerb Edging
5m high Heras Pallas
Sports  Fence around the
pitch
57
55a
55
1
31
3
1
49
49a
51
51a
53
53a
59a
59
57a
ARNISDALE WAY
SHIELDAIG DRIVE
BM 89.71m
SHIELDAIG DRIVE18
12
14
57
55a
55
61 to 91
2 to 28 1 to 31
FERNHILL ROAD
1
31
3
1
49
49a
51
51a
53
53a
59a
59
57a
ARNISDALE WAY
TCB
BM 89.71m
10
SHIELDAIG DRIVE18
12
14
Proposed Site Boundary
Gate
Light dot - dash line indicates
existing steel fence position
COMMUNITY & ENTERPRISE RESOURCES
S O  U  T  H
LANARKSHIRE
C O  U  N  C I L
Project Title:
Drawing Title:
Scale @ A1:
Drawing No:
Drawn by: Date: Checked by:
Drawing: I:\GIS\Specialist\Data\Open\Michael Heald\C
drive december 2022\play design sufficiency information\Rutherglen and Cambuslang\Councillor Submission\fernhill PA
Councillor.dwg By: healdm
DO NOT SCALE DIMENSIONS FROM THIS DRAWING
ALL DIMENSIONS TO BE VERIFIED ON SITE.
Reproduced from the Ordinance Survey mapping with the permission of the Controller of
Her Majesty's Stationery Office © Crown copyright. Unauthorised reproduction infringes
Crown copyright and may lead to prosecution or civil proceedings. South Lanarkshire
Council: LA090472.
Facilities, Waste And Grounds Services -
Landscape Development Section
Notes:
© South Lanarkshire Council Community Resources
Tel: 01698717806                      Fax 01698717750
PSIP_SD_MRH_02
18/12/23MRHAs Shown
Tender
Sheildaig Drive Play Area Investment
Ward 11
Play Sufficency  Investment Programme
Location of play area investment
Location Plan
Scale 1:1250
Proposed Play Area Investment Shieldaig Drive  (Fernhill), Rutherglen Scale 1:100
187

Page 188

Hall
Existing Play Area Benches to remain
Existing swings to be retained located within
grass matting
Existing Kompan Crazy Daisy to be retained and surfacing removed
and replaced with wet pour surfacing
Existing Sutcliffe inclusive spring mobile to be retained and surfacing removed
and replaced with wet pour surfacing 87.5 m2
Proposed Jupiter musical Orb
Ref:IP05
Install Kompan Music Play
Panel Supplied by SLC
Proposed Russells Inclusive Calypso Dish
Roundabout Ref:CA_06_0010
Proposed pc concrete pin kerb edging to
wet pour area to be created, 38 lm
Proposed wet pour surfacing
Existing damaged blaes surfacing to be removed and replaced with
tarmacadam surfacing creating an access route for all (139 m2)
(87 m2)
Timber edging to the proposed
tarmacadam surfacing (103 lm)
Existing skatepark to be retained
Existing junior play area
equipment located within areas
of grass matting
Ref: PCM000721
Existing Community Garden
23
Signal Box
25.0m
Newton Junction
S Br
31
S Br
S Br
9993
70
S Br
S Br
S Br
S Br
S Br
83
58
15
22
32
Path
S Br
S Br
McIVER STREET
14
12
10
21
24
36
140
136
16
27
7
211
28
30
215
24
219
26
Sports Facility
McKENZIE GATE
5
29
2725
23
7
30.5m
209
225
154
205
26
207
166
WESTBURN ROAD
213
223
PH
Light Burn
217 221
Hall
DUNLOP STREET
12
20
6
20
227
Install Kompan Music Play
Panel Supplied by SLC
Ref: PCM000721
Terram 1000
200 x 50 mm flat top pin kerb
300mm x100 mm ST1 concrete foundation,
haunching and 10 mm mortar bed
wet pour depth to be 40mm out with safety
zones
Wet pour depth 40mm for interactive
musical items, dish roundabout and
play panel CFH 1.00m and less.
0.20
Lotrack 10/7 Geotextile DOT type 1 stone
Liner compacted in two layers to
a depth of 150mm
6mm nominal size DBM,
25mm deep
New Tarmacadam Re-surfacing Of Existing Blaes
Scale 1:20
Cross-fall of 1:100
20mm nominal size DBM,
50mm deep
150mm x 50mm flat top concrete kerb
Path Width 1800mm
(hot dipped galvanised)
90mm annular ring nails
pointed pegs and afixed with
600mm x 50mm x 50mm
timber edge rail mounted on
Pressure treated 250mm x 38mm
Topsoil finish to be 25mm higher than path
COMMUNITY & ENTERPRISE RESOURCES
Project:
Drawing:
Scale @ A1:
Drawing No:
Drawn by: Date: Checked by:
Drawing: I:\GIS\Specialist\Data\Open\Michael Heald\C
drive december 2022\play design sufficiency information\Rutherglen and Cambuslang\Councillor Submission\westburn community hall Councillor.dwg By: healdm
DO NOT SCALE DIMENSIONS FROM THIS DRAWING
ALL DIMENSIONS TO BE VERIFIED ON SITE.
Reproduced from the Ordinance Survey mapping with the permission of the Controller of
Her Majesty's Stationery Office © Crown copyright. Unauthorised reproduction infringes
Crown copyright and may lead to prosecution or civil proceedings. South Lanarkshire
Council: LA090472.
Facilities, Waste & Grounds Services,
Landscape Development Section
Notes:
© South Lanarkshire Council Community Resources
Tel: 01698 717740
S O  U  T  H
LANARKSHIRE
C O  U  N  C I L
Drawing Status:
Location:
PSIP_HC_MRH_02
18/12/23MRHAs Shown
Tender
Hamilton Crescent Play Area Investment
Ward 14
Play Sufficency  Investment Programme
Proposed Play Area Investment Westburn Community Hall Cambuslang Scale 1:100
Location of play area investment
Westburn Community Hall  Play Area
Scale 1:2500
Wet Pour Construction Detail Scale 1:10
Scale 1:20
Location Plan
188

Page 189

Report
Agenda Item 
To: Community and Enterprise Resources Committee
Date: 18 June 2024
Prepared by: Executive Director (Community and Enterprise
Resources)  
Subject: Biggar Public Park - Update 
1. Purpose of Report 
1.1. The purpose of this report is to:- 
 provide an update on the work undertaken to secure arrangements for the long
term financial sustainability for Biggar Public Park 
2. Recommendation(s)
2.1. The Committee is asked to approve the following recommendation(s):- 
(1) that the contents of the report be noted. 
3. Background
3.1. Biggar Park is located south of Biggar town and was originally set out as a traditional
park providing open space for recreation in 1906. Over the years the park has
developed to facilitate a wide variety of formal and informal recreation activity. 
3.2. The park is owned by South Lanarkshire Council (Council) and operationally is
managed by South Lanarkshire Leisure and Culture (SLLC). Until March 2024 the
Council had a service contract whereby the provider was responsible for the day-to-
day management and operational programming of activities on the site. The service
provider, BCP Management Services (BCP), had provided the services at the park
since at least 1996. The most recent contract commenced in 2009 for a 10-year
period (1 April 2009 – 31 March 2019), with the Council having options for 5 one-
year extension periods. Due to the condition of the infrastructure (as set out in
paragraphs 3.5 and 3.6) a notice to terminate the contract was given to the service
provider on 5 September 2023 and the contract ended on the 31 March 2024.   
3.3. The contract included the provision of an on-site dwelling house and entailed the
provision of the:- 
 83 caravan pitches
 6 camping pitches
 18-hole golf course
 2 tennis courts
 bowling and putting
 boating pond
 catering outlet
 retail outlet 
14
189

Page 190

3.4. The park has proven to be attractive to caravan holiday makers with a good level of
demand. The other activities at the park, including golfing and general play, have
also proven demand. 
3.5. However, the facilities on the site are in a poor condition. The infrastructure is at the
end of its useful life. In particular, the utilities and the shower blocks require
significant and urgent investment. 
3.6. The following capital investment is required in the park to retain the services:- 
 Electrical Supply - Housing and Technical Resources have advised that should
the existing services be considered as still being required after the end of 2024,
the entire underground electrical cabling infrastructure system needs to be
replaced and upgraded to current standards. This would cost in the region of
£180,000.
 Shower block - There is a modular unit which has 2 ladies’ showers, 2 gents’
showers and a disabled/family shower. This unit is now beyond economical
repair and SLLC and the service provider have been receiving complaints.
There is only one ladies’ shower and one gents’ shower operational on a site
that has the capacity to accommodate 83 caravans at any one time. Replacing
the shower block is likely to cost £250,000. The provider has also highlighted
that the portacabin laundry block is beginning to develop the same structural
and internal problems as the shower blocks.
 Other areas requiring investment include the tennis court, the bowling and
putting areas, and the dwelling house. At a minimum, this investment would
amount to £85,000 in the short term. 
3.7. The Council maintains the caravan park grounds and golf course whilst SLLC
receive the income for the golf course (neither SLLC nor the Council received any
income from the caravan park). 
3.8. The Council currently lease the clubhouse to the Trustees Biggar Golf Club (the Golf
Club) who have exclusive use of the golf course on 8 occasions per year. This lease
of the clubhouse runs to 30 March 2032 and the Golf Club currently pays £1,240 in
annual rent to the Council. 
3.9. Cala Management Ltd have title to the access road to Biggar Public Park from
Broughton Road. Given that access to the Biggar Public Park has taken place for
over 20 years, it is the Council’s opinion that access rights are established, and this
is no impediment to the delivery of operations at Biggar Public Park. 
3.10. A review of titles to Biggar Public Park and Golf Course is currently being undertaken
in respect of Common Good land which may determine the way forward/future
management arrangements. 
3.11.  In order to consider the future of Biggar Park, the Council sought specialist advice
and commissioned Savills to undertake market appraisals.  The Council also
engaged Ironside Farrar to prepare outline design options for the Park. 
4. Review of options 
4.1. The options appraisal undertaken by Savills analysed the existing site, the market
potential and provided a series of options. 
4.2. The consultant undertook a high-level appraisal of national and local market
conditions which concluded that national group caravan operators are taking a
190

Page 191

cautious approach to expansion, with a notable cooling of the market. However,
regional operators are still cautiously looking for the right opportunities, with
increased scale allowing them to operate more efficiently. Savills analysis has
identified several small regional operators that could potentially be interested in
exploring opportunities at Biggar Public Park.  Expressions of interest have also
been received from local providers. 
4.3. Using information developed by Savills and options prepared by landscape
consultants Ironside Farrar, community consultation was undertaken in January and
February 2024 at staffed drop-in sessions in Biggar.  An online survey was also
available. 
4.4. The online consultation received 497 responses and the drop-in sessions had over
150 attendees.  The Biggar Public Park Visitor and Stakeholder Engagement
summary report provides a wealth of information and is available to members upon
request. 
4.5. The consultation provided 3 broad design options for the future of the park
summarised as:- 
Option 1 Retain and develop the caravan and leisure capacity within the existing
space.
Option 2 Site wide enhancement increasing park space and developing some of
the golf course as caravan and holiday park space.
Option 3 Creation of a community parkland in place of any caravan and leisure
park provision.   
4.6. The communities’ preference was Option One, the retention of the caravan park
facilities as there was recognition of the economic benefit to the town of a camping
and caravan facility at the site and of the need for investment.   
4.7. The communities’ response concurred with the recommendations from Savills for the
continuation of a caravan park as the optimum solution.  Savills have also advised
that the Council should seek third-party interest or lease either for the caravan park
or the full Park, incorporating the golf course, on a long-term arrangement
(approximately 25 year+).   
4.8. If the full site was let to a single operator, once the enhanced Park has become
established, the Council could expect an annual rent. Income projections are based
on an established park operation with 100 pitches.  There will likely be a requirement
to provide a rent-free period in initial years to allow any operator to invest in the park
and establish the site. 
4.9. In order to attract third-party interest, Savills have advised the following to be
desirable:- 
 vacant possession of caravan park and potentially golf course
 subject to gaining necessary planning consents and licensing requirements
 that SLC invest in access improvements (passing bays etc)
 that SLC contribute towards electrical upgrades
 approximately 25-year + lease terms
 mid-term break clause
 potential rent-free period of approximately 2/3 years
 potential reduced rent in years 3 and 4
191

Page 192

 from year 5 onwards, higher of either guaranteed minimum rent or 10% of
income
 tenant to have option to invest in and provide ancillary facilities (that is. tennis.
pitch and put, catering etc.).  All additional facilities income to be linked to
turnover rent 
4.10. On the basis that planning consent and site improvement works will be required for
any new development, it is unlikely a new caravan park will be operational prior to
Easter 2025, which would be the start of the 2025 season.  As such, the Council and
SLLC have implemented contingency plans for the provision of pay to play golf and
general park management for 2024. 
4.11.  As the former service provider is no longer on site, the Council has also implemented
increased security measures on the site including new CCTV.  Site wide clearance is
also being undertaken and reinstatement of grass areas following the removal of all
caravans in March 2024.   
5. Employee Implications
5.1. There are no Council employee implications arising from this report. 
6. Financial Implications
6.1. The aim of securing a new operator is to ensure the long term financially sustainable
for Biggar Public Park. This may generate an income to the Council and/or could
reduce operating costs of the site for the Council. It will importantly also bring wider
economic benefits to the town.   
6.2. Capital investment is, however, required to bring the basic infrastructure up to
standard, as set out in paragraph 3.6.  We will look to the prioritised urgent
investment funding alongside other external funding to meet the costs of the
essential works.   
7. Climate Change, sustainability and environmental implications
7.1. The park and golf course are a natural asset and the proposals may have
opportunities to fully incorporate sustainable and energy efficient design within the
final option.  Consultation with SEPA will be required as part of any updated layout
and design considerations. 
8. Other Implications
8.1. Marketing the site offers the opportunity to secure a long-term future for the site and
the facilities. However, the risk of not receiving suitable offers or agreeing contractual
terms with a service provider will correspondingly risk the provision of facilities. 
8.2. The timescales for identifying and agreeing terms on a new service contract are
compressed and any delays in the process risks a new service provision being in
place for April 2025. 
9. Equality Impact Arrangements and Consultation Arrangements
9.1. Community consultation on the options were carried out in January and February
2024 and the report is available to members upon request.   
9.2. There was no equality impact assessment required for this report.
192

Page 193

David Booth
Executive Director (Community and Enterprise Resources) 
30 May 2024 
Link(s) to Council Values/Priorities/Outcomes
Values
 Focused on people and their needs
 Working with and respecting others
 Accountable, effective, efficient and transparent
 Fair, open and sustainable
Priorities
 We will work towards a sustainable future in sustainable places
Outcomes
 Good quality, suitable and sustainable places to live
 Thriving business, fair jobs and vibrant town centres
 Caring, connected, sustainable communities 
Previous References
 None 
List of Background Papers
 None 
Contact for Further Information
If you would like to inspect the background papers or want further information, please
contact:-
Kenneth R Lean
Economic Development Manager (Rural and Funding) 
E-mail: Kenny.lean@southlanarkshire.gov.uk 
193

Page 194

194

Page 195

Report
Agenda Item 
Report to: Community and Enterprise Resources Committee
Date of Meeting: 18 June 2024
Report by: Executive Director (Community and Enterprise
Resources)  
Subject: Community and Enterprise Resources - Notification of
Contracts Awarded - 1 October 2023 to 31 March 2024 
1. Purpose of Report
1.1. The purpose of the report is to:-
[purpose]
 provide notification to Committee, in accordance with Standing Orders on
Contracts, of contracts awarded by Community and Enterprise Resources during
the period 1 October 2023 to 31 March 2024 
2. Recommendation(s)
2.1. The Committee is asked to approve the following recommendation(s):- 
(1) the details of the contracts awarded during the period 1 October 2023 to 31
March 2024 be noted.
[1recs]
3. Background
3.1. It is a requirement of Clauses 21.8 and 22.5 of the Standing Orders on Contracts that
details of the acceptance of all tenders above £50,000 be reported retrospectively to
the relevant Committee for noting, other than those under Clause 21.3 where the
award is not the lowest in a price only tender, or costs exceed the approved financial
provision.  In these instances, a report is submitted to the appropriate Committee and
subsequent authority to award is granted by that Committee. 
4. Contract Awards
4.1. The details of contracts awarded for the period 1 October 2023 to 31 March 2024, on
the basis of lowest offer and/or most economically advantageous offer submitted, is
provided at Appendix 1. 
5. Employee Implications
5.1. There are no employee implications arising from this report. 
6. Financial Implications
6.1. The costs of the programmes detailed above for 2023/2024 are met entirely by the
Council’s externally funded employability grants. 
7. Climate Change, Sustainability and Environmental Implications
7.1. There are no Climate Change, Sustainability and Environmental Implications arising
from the information presented in this report.  
15
195

Page 196

8. Other Implications
8.1. There are no direct risks or implications for sustainability in terms of the information
contained in this report. 
9. Equality Impact Assessment and Consultation Arrangements
9.1. This report does not introduce a new policy, function or strategy nor recommend a
change to an existing policy, function or strategy and therefore, no impact assessment
is required. 
9.2. There is also no requirement to undertake any consultation in terms of the information
contained in this report. 
David Booth
Executive Director (Community and Enterprise Resources) 
20 May 2024 
Link(s) to Council Values/Priorities/Outcomes
 Accountable, effective, efficient and transparent 
Previous References
 Community and Enterprise Resources Committee – 7 November 2024 
List of Background Papers
 Standing Orders on Contracts 
Contact for Further Information
If you would like to inspect the background papers or want further information, please
contact:- 
Emma Smith, Corporate Procurement and Transactions Manager
Ext:  5329 (Tel:  01698 455329)
E-mail: emma.smith@southlanarkshire.gov.uk 
196

Page 197

Appendix 1
Contracts Awarded by Community and Enterprise Resources over £50,000 in value 
Contracted supplier
Contract reference
number
Estimated
contract
value - GBP
Contract
award date Contract description
Contract
start date
Contract
end date
Contract end
date
(including
extension)
Parks of Hamilton SLC/CE/23/109 £1,810,552 1/10/2023
Supply and Delivery of Light
Vehicles  1/10/2023 01/10/2023 -
RSK Environmental Ltd
SLC/PS/COMENT/
22/136 £58,720 10/10/2023
Initial Appraisal and condition survey
Duke Street Multi storey Car park
Hamilton 10/10/2023 19/12/2023 -
John McGeady Ltd SLC/CE/23/100 £78,143 29/10/2023
Repairs to Roads within Larkhall,
Priestfield and Philipshill Cemeteries 30/10/2023 20/11/2023 -
Fuellink Systems Limited SLC/CE/23/067 £77,840 20/11/2023
Repair and Maintenance of In-House
Fuel Management System 01/12/2023 30/11/2028 30/11/2030
Karring International Ltd
SLC/CE/23/102 
£264,926 16/11/2023
Supply & Delivery of Hot and Cold
Beverage Supplies, Equipment, and
Machinery which includes the
Purchase of New Equipment and
Maintenance of Existing Equipment 01/12/2023 30/11/2028 30/11/2030
Parks of Hamilton
SLC/CE/23/143 
£203,347 28/11/2023
Direct Award for the Supply and
Delivery of Light Vehicles  05/12/2023 05/06/2024 -
Q-Free (Bristol) UK Ltd
SLC/PS/COMENT/
22/138 £141,272 7/12/2023
Supply, Installation and Maintenance
of Cycle and Pedestrian Counting
Equipment 22/12/2023 21/12/2028 10/12/2031
Biffa Waste Services
SLC/PS/COMENT/
21/233 £39,096,332 11/01/2024
Management and Operation of
Household Waste and Recycling
Centres (HWRC) 01/04/2024 31/03/2031 31/03/2034 
Liebherr Great Britain Ltd SLC/CE/23/171 £75,060 01/01/2024 Hire of a Material Handler 01/01/2024 30/06/2024 31/12/2024
Lightways (Contractors)
Limited 
SLC/CE/23/009 
£1,281,333 06/01/2024
Maintenance, Storage, Erection 
and Dismantling of Festive Lighting 07/01/2024 06/01/2028 06/01/2029
Joseph Leckie & Sons Ltd  SLC/CE/23/128 £65,457 10/01/2024
Shawlands Crescent Play
Area 15/01/2024 08/04/2024 N/A
197

Page 198

Contracted supplier
Contract reference
number
Estimated
contract
value - GBP
Contract
award date Contract description
Contract
start date
Contract
end date
Contract end
date
(including
extension)
Excel Vending Limited
SLC/CE/23/112
SLC/CE/23/127 
£65,440 23/01/2024  Vending Machine services 23/01/2024 23/01/2024
One Off
Purchase 
Landcare Solutions Ltd 
SLC/CE/23/117 £320,640 25/01/2024 Play investment programme Larkhall 19/02/2024 05/04/2024 -
Joseph Leckie & Sons  SLC/CE/23/157 £498,492 08/02/2024 Philipshill Cemetery Extension 12/02/2024 06/05/2024 - 
Alliance Disposables Ltd 
SLC/CE/23/178 
£5,320,000 19/02/2024 Janitorial Products 19/02/2024 18/02/2028 -
Ayrshire Tree Surgeons
Ltd
TD Tree and Land
services Ltd
Ayrshire Tree Surgeons
Ltd 
SLC/CE/23/126
£62,081 16/02/2024 
Tree Surgeon works various
locations 01/03/2024 30/04/2021 -
Turner & Townsend
Management Ltd
SLC/CE/23/082 
£249,150 19/02/2024 Country Park Masterplan 07/03/2023 06/09/2024 -
Stepford Contracts
SLC/PS/COMENT/
23/019/1/009 £50,484 22/02/2024 Footway Resurfacing East Kilbride 04/03/2024 29/03/2024 -
Greenleaf Estate
Maintenance Ltd
Excel Environmental
Services Ltd
SLC/PS/COMENT/
22/154 
£4,000,000 08/03/2024
Pest Control and Other
Environmental Services 01/04/2024 31/03/2026 31/03/2028
Storm Environmental Ltd SLC/CE/23/184 £167,250 14/03/2024
Supply and Delivery of communal
bins 14/03/2024 30/09/2024 31/03/2025
M Squared Ltd
SLC/PS/COMENT/
23/019/6/003 £96,387 19/03/2024
Woods Stock Fencing Mauldslie
Woods, Rosebank 05/04/2024 26/04/2024 -
Hillhouse Quarry T/A
MacAsphalt
SLC/PS/COMENT/
23/019/2/003 £62,682 21/02/2024
Carriageway Resurfacing/anti-
skid/Lining - A73 near Hyndford
Bridge, Lanark 22/03/2024 22/03/2024 - 
JC Peacock SLC/CE/23/152 £160,800 31/03/2024 Bagged Salt 01/04/2024 31/03/2028 - 
198

Page 199

Contract Extensions for contracts over £50,000 in value 
Contractor CRN
Original Value
of Contract
Awarded
(including
extension
value)
Value of
Extension
Award
Date of
Extension Brief Description
Contract
Extension
start
Contract
extension
end
Electrical Testing Ltd
SLC/PS/COMENT/
21/234 £600,000 £151,351.40 21/09/2023
Highway 
Electrical Connections 23/12/2023 22/06/2025
George Carruthers
and Sons Ltd
SLC/PS/COMENT/
19/139 £3,000,000 £1,000,000 14/03/2024
Supply and Delivery of
Fresh Fruit and Vegetables 01/04/2024 31/04/2025
Brake Brothers
SLC/PS/COMENT/
22/027 £4,589,078 £2,112,542 13/03/2024
Supply and Distribution of
Frozen foods 30/05/2024 29/05/2026
199

Page 200