Page 1

Council Offices, Almada Street        
Hamilton, ML3 0AA 
Tuesday, 06 August 2024 
Dear Councillor 
Climate Change and Sustainability Committee 
The Members listed below are requested to attend a meeting of the above Committee to be
held as follows:- 
Date:  Wednesday, 14 August 2024
Time:  10:00
Venue: Hybrid - Committee Room 1, Council Offices, Almada Street, Hamilton,
ML3 0AA 
The business to be considered at the meeting is listed overleaf. 
Yours sincerely 
Paul Manning
Chief Executive 
Members 
Kirsten Robb (Depute Chair), Joe Fagan (ex officio), Alex Allison, John Anderson, Ralph
Barker, Maureen Chalmers, Ross Clark, Margaret Cooper, Colin Dewar, Ross Gowland,
Lynsey Hamilton, Gavin Keatt, Ross Lambie, Richard Lockhart, Katy Loudon, Julia Marrs,
Monique McAdams, Lesley McDonald, Elaine McDougall, Mark McGeever, Carol Nugent,
Mo Razzaq, John Ross, Graham Scott, Bert Thomson, Helen Toner, Margaret B Walker,
Kirsty Williams 
Substitutes
Walter Brogan, Robert Brown, Andy Carmichael, Gerry Convery, Poppy Corbett, Andrea
Cowan, Allan Falconer, Gladys Ferguson-Miller, Elise Frame, Geri Gray, Martin Hose,
Richard Nelson, David Watson 
1

Page 2

BUSINESS 
1 Declaration of Interests 
2 Minutes of Previous Meeting
Minutes of the meeting of the Climate Change and Sustainability
Committee held on 15 May 2024 submitted for approval as a correct
record.  (Copy attached) 
3 - 8 
Item(s) for Noting 
3 Social Vulnerability amid Just Transition in South Lanarkshire
Presentation by Sage Kuhens, PHD Student 
Monitoring Item(s) 
4 Sustainable Development and Climate Change Action Plan 2023/2024
Q4 Progress Report
Report dated 25 July 2024 by the Executive Director (Community and
Enterprise Resources).  (Copy attached) 
9 - 68 
Item(s) for Decision 
5 2024/2025 Action Plan for Sustainable Development and Climate
Change Strategy
Report dated 25 July 2024 by the Executive Director (Community and
Enterprise Resources).  (Copy attached) 
69 - 92 
Item(s) for Noting 
6 Glasgow City Council - Model for Climate Investment
Report dated 25 July 2024 by the Executive Director (Community and
Enterprise Resources).  (Copy attached) 
93 - 96 
Urgent Business 
7 Urgent Business
Any other items of business which the Chair decides are urgent. 
For further information, please contact:- 
Clerk Name: Susan Somerville
Clerk Telephone: 07557 323097
Clerk Email: susan.somerville@southlanarkshire.gov.uk 
2

Page 3

CLIMATE CHANGE AND SUSTAINABILITY COMMITTEE 
Minutes of meeting held via Confero and in Committee Room 1, Council Offices, Almada Street,
Hamilton on 15 May 2024 
Chair:
Councillor Mark McGeever 
Councillors Present:
Councillor Alex Allison, Councillor John Anderson, Councillor Ralph Barker, Councillor Maureen
Chalmers, Councillor Ross Clark, Councillor Margaret Cooper, Councillor Colin Dewar, Councillor
Ross Gowland, Councillor Gavin Keatt, Councillor Ross Lambie, Councillor Richard Lockhart,
Councillor Katy Loudon, Councillor Julia Marrs, Councillor Lesley McDonald, Councillor Elaine
McDougall, Councillor Carol Nugent, Councillor Mo Razzaq, Councillor Kirsten Robb (Depute),
Councillor John Ross, Councillor Graham Scott, Councillor Bert Thomson, Councillor Helen Toner,
Councillor Margaret B Walker, Councillor Kirsty Williams 
Councillors' Apologies:
Councillor Joe Fagan (ex officio), Councillor Lynsey Hamilton, Councillor Monique McAdams 
Attending:
Community and Enterprise Resources
D Booth, Executive Director; A Brown, Head of Enterprise and Sustainable Development; C Park,
Head of Roads, Transportation and Fleet Services; K McCafferty, Sustainable Development Officer
(Funding); A Wallace, Sustainability Adviser; M Wilkie, Performance and Policy Development
Manager
Finance and Corporate Resources
K McLeod, Administration Assistant; S Somerville, Administration Manager
Housing and Technical Resources
G McParland, Property Manager (Assets and Estates); J Read, Strategy and Policy Advisor; J
Smith, Strategy Team Leader (Built Environment); S Turner, Section Leader (Legislative) 
1 Declaration of Interests 
No interests were declared. 
2 Minutes of Previous Meeting 
The minutes of the meeting of the Climate Change and Sustainability Committee held on 28
February 2024 were submitted for approval as a correct record. 
The Committee decided: that the minutes be approved as a correct record. 
3 Good Food Strategy Update – Q4 2023/2024 
A report dated 24 April 2024 by the Executive Director (Community and Enterprise Resources)
was submitted on the Good Food Strategy actions and measures at Quarter 4 of 2023/2024.
2
3

Page 4

The Good Food Strategy had been approved by the Executive Committee on 4 December 2019
and covered a 5 year period from 2020 to 2025.  It set out outcomes and actions organised
around 6 key themes as follows:- 
 good food at home and in the community  good food growing
 good food in the public sector  good food for the environment
 good food economy  good food governance 
The Good Food Strategy contained an action plan which set out specific actions to progress the
objectives in the Strategy.  It contained 22 performance measures towards the Strategy’s
outcomes, together with 17 improvement actions.  The measures were rated using a traffic light
system of green, amber or red, while the improvement actions were rated using green, amber or
red as well as blue, which indicated that an action had been completed.  Of the 22 measures
within the Strategy:- 
 12 had been achieved or were on course to be achieved (green)
 10 would be reported later when data was available 
Of the 17 improvement actions within the Strategy:- 
 4 actions were complete (blue)
 12 had been achieved or were on course to be achieved (green)
 1 had minor slippage against timescale or minor shortfall against target (amber) 
No measures or improvement actions had seen major slippage against timescale or major
shortfall against target. 
Progress on all objectives, actions and measures was detailed in Appendix 1 of the report. 
Officers responded to members’ questions on various aspects of the report.   
The Executive Director (Community and Enterprise Resources) gave an undertaking to respond
to members’ questions in relation to:- 
 what the Council’s percentage spend was on Fairtrade products
 what checks were undertaken to ensure allotments were utilised and details of contractual
arrangements put in place
 the frequency of checks to ensure food businesses were compliant with food safety
statutory requirements 
The Committee decided: that the report be noted. 
[Reference:  Minutes of 28 February 2024 (Paragraph 4)] 
Councillors Cooper and Dewar joined the meeting during consideration of the above item of
business 
4 Carbon Management Interim Update 2023/2024 
A report dated 24 April 2024 by the Executive Director (Community and Enterprise Resources)
was submitted providing an update on the mid-year position with respect to South Lanarkshire
Council’s carbon emissions for 2023/2024. 
The Scottish Government had set climate targets within legislation to reduce all greenhouse gas
emissions Scotland-wide by 75% by 2030, 90% by 2040 and a total reduction from the 1990
baseline by 2045.
4

Page 5

Following the Scotland’s Climate Change Committee’s annual report indicating that the Scottish
Government would not meet its statutory 2030 goal to reduce emissions by 75%, the Scottish
Government had announced that the 2030 target and annual carbon targets would be replaced
with a system measuring emissions every 5 years. 
To align the Council’s carbon management reporting with the Public Sector Climate Change
Duties Compliance report, going forward all Council carbon management related reports would
categorise the Council’s corporate emissions as Scope 1 (direct emissions), Scope 2 (energy
indirect) or Scope 3 (other direct emissions). 
Figure 1, at paragraph 4.2 of the report, provided an overview of the scope of the Council’s
carbon footprint and which category those aligned with. 
The Council’s interim 2023/2024 carbon emissions from April to September 2023 were detailed
and compared with the same corresponding period for 2022/2023.  Those figures demonstrated
that an overall reduction of 4.49% had been achieved so far for 2023/2024 Scope 1 to 3
emissions, and 8.08% had been achieved for Scope 1 emissions.  The reasons for those
reductions were detailed. 
Discussions had taken place across Resources to establish achievable carbon reduction targets
for 2024/2025.  Based on the information, it was proposed that a percentage reduction target
was not set for 2024/2025 and, instead, the Council should continue to aim to reduce as much
as possible compared with the previous year. 
While the Council had a zero direct emissions target by 2038, it did not have a route map in
place to achieve this target.  This route map was now being developed and a series of reports
would be produced which would form the basis for it. 
In addition, it was expected that the new Climate Intelligence Service (CIS) would provide a joint
approach to councils meeting Scotland’s national commitment to net zero by 2045. 
Furthermore, the Enterprise and Sustainable Development Service was looking to undertake a
feasibility study on energy and income generating opportunities for the Council through
renewable technologies. 
Officers responded to members’ questions on various aspects of the report.   
The Committee decided: that the mid-year position in relation to the Council’s carbon
emissions for the year 2023/2024, as detailed in paragraph
5.2 of the report, be noted. 
Councillor Toner joined the meeting during consideration of the above item of business 
5 Non-Domestic Buildings - Net Zero Feasibilities 
A report dated 24 April 2024 by the Executive Director (Housing and Technical Resources) was
submitted providing an update on:- 
 the outcome of 7 feasibility studies, conducted to assess the investment required to
achieve national net zero standards for the Council’s primary school and wet leisure estate
 the estimate of total capital investment required to meet national net zero standards for the
council’s non-domestic property estate based on the outcome of the feasibility studies
5

Page 6

Through the proposed Heat in Building’s Bill, currently under development, the Scottish
Government intended to legislate for non-domestic buildings in the public sector to be using
clean heating systems by the end of 2038.  This meant that no Council building would be
permitted to burn fossil fuels to generate energy for heating or hot water systems.  Currently,
just under 300 of the Council’s non-domestic properties were heated using fossil fuels. 
To better understand the practical challenges and financial implications from this proposed
legislation, Housing and Technical Resources undertook a range of feasibility studies across the
Council’s non-domestic estate, aiming to quantify what would be required to achieve net zero
within those building types. 
Four primary schools and 3 wet leisure properties were selected, with the intention to cover a
range of build contractor, geographical location and year of construction.  In total, those property
types accounted for approximately 48% of carbon emissions from all the Council’s non housing
buildings. 
Table 2 in the report provided a summary of the outcomes, combining the results for all 4
schools.  Table 3 combined the results for the 3 wet leisure facilities.  This suggested that
significant energy and carbon reductions could be achieved by investing in the measures
identified in Table 1 in sequence.  However, operational cost reductions, which would typically
be used to financially appraise investment decisions, were far less significant. 
The findings from those 7 feasibility studies were extrapolated across the Council’s non housing
estate to estimate the level of investment required to transition those properties towards net
zero.  The result of this exercise suggested around £927 million of capital investment would be
required at 2023 prices for the existing non-housing portfolio. 
The Council had a fabric first approach to improving the energy efficiency of its non-domestic
buildings which aimed to reduce energy consumption, leading to reduced operating costs and
lower carbon emissions.  Due to the capital costs and running cost increases from currently
available clean heating systems, the Council did not have a programme for the replacement of
its fossil fuel system across its non-domestic estate at present. 
The outcomes of the feasibility studies and modelling for the council’s other non-domestic
properties would be incorporated into the South Lanarkshire Local Heat and Energy Efficiency
Strategy, subject to approval at Executive Committee on 26 June 2024. 
Officers responded to members’ questions on various aspects of the report.   
The Committee decided: 
(1) that the outcome from the feasibility studies completed be noted; 
(2) that it be noted that, based on the outcome of the feasibility studies, the updated estimate
of total capital investment that would be required to achieve national net zero standards
was £927million; 
(3) that it be noted that the Scottish Government intended to legislate that all non-domestic
buildings in the public sector should be using clean heating systems by 2038 which would
require the Council to replace fossil fuel heating systems at around 300 properties; and 
(4) that the Council’s existing fabric first approach around retrofit investment decisions be
noted.
6

Page 7

6 Energy Demand Reduction Plan Update 
A report dated 24 April 2024 by the Executive Director (Housing and Technical Resources) was
submitted providing an update on the work undertaken to date on the development of an Energy
Demand Reduction Plan, contained within the motion approved by the Council on 7 December
2022 entitled ‘Cut Fuel Bills, Cut Carbon Emissions, Kick Start the Green Economy’. 
An analysis of the total energy use in the non-domestic estate was undertaken which identified
the properties with the highest energy consumption.  Leisure facilities, secondary schools,
homes for the elderly and nursery schools were omitted from the exercise for various reasons,
as outlined in the report.  Following the analysis, where it was safe to do so, a temperature
reduction of 1C was implemented in buildings. 
In order to test the concept, a pilot had commenced in 30 buildings across the Council’s non-
domestic buildings estate to monitor the energy consumption over a 6-month period prior to
rolling out to other facilities. 
An update was provided on action taken on the following areas: 
 energy champions
 energy audits
 vacant properties
 Central Energy Efficiency Fund 
It was also intended:- 
 that the heating season be reduced to commence from 1 October and run until 31 March
each year, however, this would be weather dependent
 that the current pilot be extended to identify an Energy Champion on each site with
responsibility for ensuring that energy use was limited, where possible, and promoting
changes in behaviour
 to work with teachers and pupils on school sites regarding education on energy use
 to develop a staff behavioural change programme in relation to energy awareness
 to engage with IT Services to ensure that PC shutdown software was in place across the
Council’s estate
 to ensure continuous monitoring and management of energy use 
Officers responded to members’ questions on various aspects of the report, including
communications and promotion of practical tips to save energy.   
The Committee decided: 
(1) that the update on progress made to date on the Energy Demand Reduction Plan and the
proposed action going forward be noted; and 
(2) that the actions detailed in Appendix 1 of the report be noted. 
[Reference: Minutes of 14 June 2023 (Paragraph 3) and Minutes of South Lanarkshire Council
of 7 December 2022 (Paragraph 16)] 
Councillor Toner left the meeting during consideration of the above item of business
7

Page 8

7 Scottish Government Consultations on the Social Housing Net Zero Standard in
Scotland and Heat in Buildings Bill 
A report dated 25 April 2024 by the Executive Director (Housing and Technical Resources) was
submitted providing:- 
 an overview of 2 recent Scottish Government consultations on a proposed new net zero
standard for social housing and the new Heat in Buildings Bill
 a summary of the Council’s response to the consultations, submitted to the Scottish
Government on 8 March 2024 
In 2021, the Scottish Government published a Heat in Buildings Strategy which committed to:- 
 review the existing standards for improving energy efficiency within social housing across
Scotland
 introduce new legislation to phase out the need to install new or replacement fossil fuel
boilers across all domestic and non-domestic buildings in Scotland, while also requiring
building owners to improve the energy efficiency of buildings to help achieve net zero
targets 
Consultations on each of those commitments were launched by the Scottish Government in
early 2024 and an overview and summary of the Council’s responses to both was provided. 
An officer responded to members’ questions on various aspects of the report.   
The Committee decided: 
(1) that the overview of the consultations on the proposed new net zero standard for social
housing and Heat in Buildings Bill be noted; and 
(2) that the summary of the Council’s response to each consultation be noted. 
8 Urgent Business 
There were no items of urgent business. 
8

Page 9

Report
Agenda Item 
Report to: Climate Change and Sustainability Committee
Date of Meeting: 14 August 2024
Report by: Executive Director (Community and Enterprise
Resources)  
Subject: Sustainable Development and Climate Change Strategy
Action Plan: Quarter 4 Progress Report 
1. Purpose of Report
1.1. The purpose of the report is to: -
[
 present the Sustainable Development and Climate Change Strategy Quarter 4
Progress Report 2023/2024, for the period 1 April 2023 to 31 March 2024. 
2. Recommendations
2.1. The Committee is asked to approve the following recommendation(s):- 
(1) that the Sustainable Development and Climate Change Strategy Action Plan
Quarter 4 Progress Report 2023/2024 be noted. 
3. Background
3.1. The Sustainable Development and Climate Change Strategy 2022-27 was approved
by the Council on 15 June 2022. The Strategy sets out how the Council aims to
develop sustainably and tackle the climate change emergency over a five-year
period, whilst also providing a broad strategic direction for longer term planning to
help deliver on the agreed outcomes and contribute to achieving a longer-term
vision. 
3.2. The Action Plan for 2022-2027 was approved at the Climate Change and
Sustainability Committee in February 2023. 
3.3. Progress against these actions is monitored using IMPROVe and reported to the
Climate Change and Sustainability Committee at Quarter 2 and Quarter 4 each year. 
3.4. Delivery of actions within the strategy and associated action plan provides the main
focus for the sustainable development activity and also enables the Council to fulfil
its duties under the Local Government (Scotland) Act 2003, the Climate Change
(Scotland) Act 2009 and the Council’s contribution to the UN’s Sustainable
Development Goals. 
3.5.  Progress on all objectives, actions and measures as at Quarter 4 1 April 2023 – 31
March 2024 is set out in Appendix 1. All data and comments included in the
appendix are correct as of 10 July 2024. 
4
9

Page 10

4. Sustainable Development Strategy 2022-2027 Quarter 4 Update
4.1. The Action Plan progress report comes in two parts; the first part contains
performance/contextual measures towards the Strategy’s outcomes, and the second
part contains improvement actions for each of the themes within the Strategy. 
4.2. Part One - Performance Measures 
The overall summary of performance measures at the end of Quarter 4 is as follows: 
Total number of performance/ contextual measures 21
Status – Green
The timescale or target has been met as per
expectations.  4
Status – Amber
There has been minor slippage against timescale
or minor shortfall against target.  0
Status - Red
There has been major slippage against timescale
or major shortfall against target.  1
Reportable at a
later stage
For some measures, the statistics are not yet
available to allow us to report whether the target
has been reached or not. These will be reported
when available
3
Contextual
The contextual measures provide a health check
for South Lanarkshire. The Council’s activities
contribute to these measures, however there are
many factors that could influence these measures
which are not fully within the Council’s scope. 
13 
4.3. Areas for Improvement
There was one measure marked as ‘red’ (major slippage) for 2023/24, relating to
percentage of household waste recycled, which remains below target of 50%.
Performance against this measure will continue to be monitored. No ‘amber’ (minor
slippage) actions were reported in 2023/24. Three measures are reportable at a later
stage. Two of these are because of delays in the receipt of survey data from
participants and external organisations, updates are expected later this year; and the
third is due to changes in data reporting from the Scottish Government. Further
justification for delays, and associated management actions, is included within
Appendix 1. 
4.4.  Part Two – Improvement Actions 
Total number of improvement actions 111
Status - Blue Action Complete 27
Status – Green The timescale or target has been met as per
expectations 70
Status – Amber There has been minor slippage against timescale
or minor shortfall against target 11
Status - Red There has been major slippage against timescale
or major shortfall against target 2
Reportable at a
later stage
For some measures, the statistics are not yet
available to allow us to report whether the target
has been reached or not. These will be reported
when available
1
10

Page 11

4.5. Areas for Improvement
There were two measures marked as ‘red’ at Quarter 4. These relate to the
development of the business case for demonstrator Internet of Things projects (still
to be considered); and the provision of up-skilling and reskilling opportunities to meet
the needs of the transition to a green economy (there was a refocus on both
increasing earnings from employment for parents and on the care sector). There are
eleven ‘amber’ actions with minor slippage in 2023/2024. In the case of nine of these
actions, there has been a revision of timescales for the delivery of associated
workplans, strategies, and legislation. For the remaining two actions, which relate to
the use of ultra-low carbon vehicles for Education related travel, there has been
limited availability of the required electric vehicle technology for school bus provision.
One action was marked as ‘Reportable at a later stage’ this relates to the
introduction of the Deposit return Scheme in schools (delayed pending Scottish
Government legislation). Further explanation for these delays, and associated
management actions, is included within Appendix 1. 
4.6. Key Highlights 
Progress on all objectives, actions and measures is set out in Appendix 1. Some of
the key achievements for Q4, are noted below: 
 1.5% of household waste was sent to landfill in 2023/24 – well below the target
of <10%
 The Lanark air quality management area was revoked in February 2024 as a
result of air quality objectives having been successfully met; similarly, Whirlies
and Rutherglen air quality management areas are showing signs of improved
air quality
 The next phase of the East Kilbride Active Travel network on Churchill Avenue
and part of Cornwall Street was completed, with Active Travel Plans for part of
the Clydesdale area concluded (and priority routes for future active travel
infrastructure identified)
 An EV infrastructure Expansion Plan and Strategy has been developed
identifying the future requirement for charging infrastructure within SLC.
 A number of bus and rail infrastructure improvements have been undertaken
(as listed in Appendix 1)
 A number of flood protection projects / studies have been undertaken in
2023/24 (as listed in Appendix 1)
 A detailed analysis of the open space audit has been completed by consultants
and draft technical report submitted
 The Council’s Biodiversity Strategy and the Biodiversity Duty Implementation
Plan was approved by the Climate Change and Sustainability Committee in
February 2024
 An update on the delivery of the Litter Strategy Action plan was presented to
the Climate Change and Sustainability Committee in September 2023 along
with a review of the Action Plan for the coming year; and an annual rural roads
clear-up programme was undertaken resulting in nine tonnes of discarded
waste collected over 30 days, clearing more than 77 miles of roads and verges
 There was a slight reduction in the amount of glysophate used to control weeds
in 2023; and we piloted the use of Aquateck cleaning solution in schools leading
to the roll out across all 17 high schools
 Shared Prosperity Fund was used to help ensure a just transition to net zero in
2023/24 funding: £75,000 of Climate Emergency and Resilience Grants to
community groups, the development of Extend PLUS which will facilitate carbon
reporting for SMEs across the Glasgow City Region; and Employment Land and
11

Page 12

Market Analysis in East Kilbride to assess the need for, and feasibility of,
energy investments
 45 schools currently hold Green Flag awards, an increase of 10 schools from
the previous year; Green Flag accreditation was also successfully retained for
Strathaven park, Cambuslang Park and Castlebank Park
 Chatelherault allotment site opened in summer 2023, with an increase of 64 plot
holders.
 Jump app has been introduced in four secondary schools - this includes
sustainable targets for pupils and staff with monthly prizes; following the
success of the COS2 (Conference of Schools) event, planning is underway for
a COS3 event
 A new SLC Climate Change and Sustainability Officers Group has been set up
to support the work of the Climate Change and Sustainability Steering Group.
 Climate Change Learn online modules have been completed by 1,416
employees since being introduced in 2023
 Regular articles and good news stories have been prepared and shared across
Council social media, including coverage of the Climate and Nature event
hosted in October 2023 by the Community planning Partnership, the Council’s
roll out of the electric vehicle charging infrastructure, and the impact of projects
funded through the council-managed Renewable Energy Fund
 A Sustainability Impact Assessment process has been developed and
implemented for the Council’s Capital and Revenue Programmes 
5.  Employee Implications 
5.1. All Resources are required to contribute to the implementation of the Sustainable
Development and Climate Change Strategy to ensure that actions and targets are
met. Officers within the Sustainable Development and Climate Change team monitor
and report the Council’s progress, however there are officers from all Resources who
have responsibility for updating and owning the actions noted within the IMPROVe
action plan. 
6.  Financial Implications 
6.1.  The actions detailed in the Sustainable Development and Climate Change Strategy
and associated action plan are funded from existing Resource budgets, however the
scale and pace of action needed to meet climate change targets and address the
current climate crisis will require significant capital investment and is likely to require
external funding and investment. The delivery of the Strategy may help leverage for
additional funding and investment; however alternative financing models are also
being explored. 
7.  Climate Change, Sustainability and Environmental Implications
7.1.  The Sustainable Development and Climate Change Strategy contributes towards the
Public Sector Climate Change Duties, the Biodiversity Duty, and the UN Sustainable
Development Goals. 
8.  Other Implications 
8.1.  The Sustainable Development and Climate Change Strategy has been assessed as
part of the Council’s risk management arrangements and relevant issues have been
added to the Resource Risk Registers. 
9.  Equality Impact Assessment and Consultation Arrangements
9.1.  An Equality Impact Assessment and Fairer Scotland Duty impact assessment have
been carried out on the Sustainable Development and Climate Change Strategy. 
12

Page 13

9.2.  Public and stakeholder consultation was undertaken during the development of the
Sustainable Development and Climate Change Strategy. 
David Booth
Executive Director (Community and Enterprise Resources) 
25 July 2024 
Link(s) to Council Values/Priorities/Outcomes
Values
 Focused on people and their needs
 Working with and respecting others
 Accountable, effective, efficient and transparent
 Ambitious, self-aware and improving
 Fair, open and sustainable 
Priorities
 We will work to put people first and reduce inequality
 We will work towards a sustainable future in sustainable places
 We will work to recover, progress and improve 
Outcomes
 Our children and young people thrive
 Good quality, suitable and sustainable places to live
 Thriving business, fair jobs and vibrant town centres
 Caring, connected, sustainable communities
 People live the healthiest lives possible
 Inspiring learners, transforming learning, strengthening partnerships 
Previous References
 South Lanarkshire Council report on 15 June 2022 entitled ‘Sustainable Development
and Climate Change Strategy 2022-2027’
 Climate Change and Sustainability Committee report on 31 August 2022 entitled
‘Sustainable Development and Climate Change Strategy 2022-2027’
 Climate Change and Sustainability Committee report on 28 February 2024 entitled
‘Sustainable Development and Climate Change Strategy Action Plan: Quarter 2
Progress Report’  
List of Background Papers
 The Climate Change (Scotland) Act 2009
 Sustainable Development and Climate Change Strategy 2017-2022
 Sustainable Development and Climate Change Strategy 2022-2027
 UN’s Sustainable Development Goals 
Contact for Further Information
If you would like to inspect the background papers or want further information, please
contact: - 
Adam Wallace, Sustainability Adviser
Email: adam.wallace@southlanarkshire.gov.uk
13

Page 14

14

Page 15

IMPROVe - SLC Performance Management System                                                                                   Report printed on 6 Aug 12:32
Quarter 4 : 2023/24 - April to March
Appendix 1
Performance Report
4
15

Page 16

IMPROVe - SLC Performance Management System                                                                                   Report printed on 6 Aug 12:32
Page 2 of 3
16

Page 17

IMPROVe - SLC Performance Management System                                                                                   Report printed on 6 Aug 12:3217

Page 18

IMPROVe - SLC Performance Management System                                                                                   Report printed on 6 Aug 12:32
Summary (Section 1) - number of Quantitative Measures green, amber and red under each
Sustainable Development Theme
Sustainable Development Theme Green Amber Red Report later /
Contextual
Total
People 1 0 0 3 4
Place and Communities 0 0 0 13 13
Natural Environment (Planet) 2 0 0 0 2
A Green Economy (Planet) 1 0 1 0 2
Total 4 0 1 16 21
Summary (Section 2) - number of Improvement Actions complete, green, amber and red
under each Sustainable Development Theme
Sustainable Development Theme Complete Green Amber Red Report
later
Total
People 14 9 3 0 0 26
Place and Communities 10 36 4 1 0 51
Natural Environment (Planet) 2 6 3 0 0 11
A Green Economy (Planet) 1 19 1 1 1 23
Total 27 70 11 2 1 111
Page 1 of 51
18

Page 19

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Performance Measures
Sustainable Development and Climate Change
Strategy - Section 1: Performance Measures
The following section provides performance and contextual measures for each of the themes in the strategy. 
The performance measures highlights progress towards each of the outcomes.  The contextual measures
provide a health check; however, these are not fully in the scope of influence for the Council.
Page 2 of 51
19

Page 20

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Performance Measures
People
Contribute to improving health and wellbeing through environmental protection and access to environmental benefits for all
Performance Indicators Comments/ Progress Status 2021/22 2022/232020/21Target To Date
-------- Last 3 Years --------------------- This Year -------------
Number of Environmental Volunteering
days
There are still some data returns outstanding which could increase this
figure. Any increase in the full year figure will be reported by end of
September 2024.
Report Later 2,000 1,890 2,380 4,168 5,212
Progress climate justice and ensure the transition to net-zero by 2045 does not exacerbate poverty or inequalities
Performance Indicators Comments/ Progress Status 2021/22 2022/232020/21Target To Date
-------- Last 3 Years --------------------- This Year -------------
Fuel poverty percentage in South
Lanarkshire
Source data for this measure is no longer available as the data is no
longer broken down to local authority level following removal of this
indicator from the Scottish Household Condition Survey in 2020. The
last reported figure of 22% derives from the 2020 Scottish Household
Condition Survey. Measure has been removed from 2024/25 action plan.
Contextual 20.0% ------ 22.0% 22.0% ------
Influence change through improving the understanding of Sustainable Development and the Climate emergency across South Lanarkshire
Performance Indicators Comments/ Progress Status 2021/22 2022/232020/21Target To Date
-------- Last 3 Years --------------------- This Year -------------
Number of council employees who have
completed the Learn on Line Climate
Change modules
Since introduction the Climate Change Learn on Line modules have
been completed by 1,416 employees.
Contextual ------ 1,416 ------ ------ 1,354
Encourage schools to achieve eco school
status
Schools continue to be encouraged to achieve Eco Schools status
through attainment of Green Flag awards. Participating schools are
informed about overviews and opportunities via X (Twitter) and through
monthly newsletters available to staff via SLC’s 'The Feed'. Since
September 2023, 16 establishments have received a Green Flag award
through the Eco Schools programme – for 2 of these establishments this
was their first Green Flag and for 14 establishments they achieved an
additional Green Flag award. Updates from Keep Scotland Beautiful
show that South Lanarkshire has 45 establishments who hold current
Green Flags.
Green ------ 45 ------ ------ 35
Place and Communities
Page 3 of 51
20

Page 21

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Performance Measures
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Performance Measures
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Performance Measures
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Performance Measures
Place and Communities
Improve affordable, sustainable, and accessible transport options
Performance Indicators Comments/ Progress Status 2021/22 2022/232020/21Target To Date
-------- Last 3 Years --------------------- This Year -------------
Proportion of journeys made by foot in
South Lanarkshire
13% of journeys were made by foot in South Lanarkshire in 2022,
compared to 22.6% nationally.
Where a journey involves more than one mode of transport (e.g. a bus,
then a train), the main mode is defined as the one used for the longest
stage (in distance).
Figures reported here are taken from Transport Scotland’s 'Transport
and Travel in Scotland' document published in February 2024 using data
from the Scottish Household Survey 2022.
Contextual ------ 13.0% ------ ------ ------
Percentage of trips being made by bike In South Lanarkshire 0% of journeys were made by cycle in 2022.
Nationally this figure was 1.7%.
Note: where a journey involves more than one mode of transport (e.g. a
bus, then a train) the main mode is defined as the one used for the
longest stage (in distance).
(Figures taken from Transport Scotland’s Transport and Travel in
Scotland document published in February 2022 using data from the
Scottish Household Survey 2022. Data is influenced by small sample
size used due to Covid 19 pandemic impacts).
Contextual ------ 0.0% ------ ------ ------
Proportion of journeys that are made by
bus and rail
In South Lanarkshire 6% of journeys were made by bus and rail in 2022.
Nationally this figure was 8.1%.
Note: where a journey involves more than one mode of transport (e.g. a
bus, then a train), the main mode is defined as the one used for the
longest stage (in distance).
(Figures taken from Transport Scotland’s Transport and Travel in
Scotland document published in February 2024 using data from the
Scottish Household Survey 2022 – Local Authority Table 16 - Main Mode
of Travel).
Contextual ------ 6.0% ------ ------ ------
Page 4 of 51
21

Page 22

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Performance Measures
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Performance Measures
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Performance Measures
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Performance Measures
Place and Communities
Improve affordable, sustainable, and accessible transport options
Performance Indicators Comments/ Progress Status 2021/22 2022/232020/21Target To Date
-------- Last 3 Years --------------------- This Year -------------
Mode share of school children traveling by
active or public transport (Annual national
'Hands Up' Survey)
In South Lanarkshire, 60.1% of children travelled to school by active or
public transport during 2023 (excluding nursery). 37.7% walked, 3.5%
cycled, 2.7% travelled by scooter/skate and 16.2% travelled by bus.
Nationally, in 2023 65.7% of school children travelled by active or public
transport.
Figures reported here are taken from Sustrans Annual National Hands
Up Survey published in May 2024 using data from 2023.
Contextual ------ 60.1% 59.8% 59.0% 59.9%
Mode share of adults traveling to work or
education by active or public transport
(Scottish Household Survey)
In South Lanarkshire, 28% of adults travelled to work by active or public
transport in 2022 (10% walked, 1% cycled, 6% travelled by bus and 11%
travelled by rail). Nationally this figure was 29.4%.
(Figures taken from Transport Scotland’s Transport and Travel in
Scotland document published in February 2024 using data from the
Scottish Household Survey 2022  - Local Authority Table 1 - Employed
adults (aged 16+) not working from home - usual method of travel to
work)
Contextual ------ 28.0% 21.0% 24.0% 24.0%
Progress a transition to net-zero, energy efficient and climate resilience homes, buildings and infrastructure, and minimise the unsustainable use of natural
resources and regenerate where appropriate
Performance Indicators Comments/ Progress Status 2021/22 2022/232020/21Target To Date
-------- Last 3 Years --------------------- This Year -------------
Carbon emissions in tonnage for South
Lanarkshire: emissions within scope of
Local Authority. (figures from BEIS with a
2-year lag)
Annual data is published by the Department for Energy Security and Net
Zero (previously BEIS). It has a two-year lag. Data for 2022 will be
included in the quarter two update for 2024-25.
Contextual ------ ------ 1,263.2 1,203.9 ------
Percentage reduction on area-wide
emissions compared to previous year:
emissions within scope of Local Authority
(figures from BEIS with a 2-year lag)
Annual data is published by the Department for Energy Security and Net
Zero (previously BEIS). These figures have a two year lag. Area-wide
emissions increased by 10% in calendar year 2021 compared to 2020.
Figures for that period had been impacted by the Covid-19 pandemic.
Data for 2022 will be included in the quarter two update for 2024-25.
Contextual ------ ------ -9.2% 10.0% ------
Per capita: emission within scope of Local
Authority (figures from BEIS with a 2-year
lag)
Annual data is published by the Department for Energy Security and Net
Zero (previously BEIS). These figures have a two year lag. Data for
2022 will be included in the quarter two update for 2024-25.
Contextual ------ ------ 3.40 3.70 ------
Page 5 of 51
22

Page 23

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Performance Measures
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Performance Measures
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Performance Measures
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Performance Measures
Place and Communities
Progress a transition to net-zero, energy efficient and climate resilience homes, buildings and infrastructure, and minimise the unsustainable use of natural
resources and regenerate where appropriate
Performance Indicators Comments/ Progress Status 2021/22 2022/232020/21Target To Date
-------- Last 3 Years --------------------- This Year -------------
Achieve zero direct emissions from Council
operations (buildings and fleet fossil fuels)
by 2038
The council’s direct carbon emissions (32,869 carbon tonnes) for
financial year 2022-23 reduced by 2.3% compared with baseline year
2019-20. Data for 2023-24 will be included in the quarter two update for
2024-25.
Contextual ------ ------ ------ ------ 32,869.0
Reduce indirect emissions from Council
carbon footprint (electricity, household
waste and staff travel)
The council’s indirect carbon emissions for financial year 2022-23
(20,685 carbon tonnes) reduced by 38% compared with baseline year
2019-20. Data for 2023-24 will be included in the quarter two update for
2024-25.
Contextual ------ ------ ------ ------ 20,685.0
Occurrence/reduction of flood events In 2023, across three gauged locations, there was an average of
905mm of rainfall, including 3 days with rainfall in excess of 20mm.
During this year there were 737 recorded flooding incidents across
South Lanarkshire, a reduction from 1054 in 2022.
Contextual ------ 737 1,214 705 1,054
Percentage of Council dwellings that are
meeting the Energy Efficiency Standard for
Social Housing (EESSH 2032)
The 2025 and 2032 EESSH Milestones have been suspended as the
Scottish Government are reviewing the EESSH2 standards to
strengthen and realign the standard with the target for net zero heat in
houses from 2045.
Report Later ------ ------ 93.88% 98.64% ------
Empower communities to take climate action and be more environmentally sustainable
Performance Indicators Comments/ Progress Status 2021/22 2022/232020/21Target To Date
-------- Last 3 Years --------------------- This Year -------------
Increase in the overall number of food
growing participants on Council land
including schools, care homes, housing
area and areas managed by community
groups or third-party organisations
We have experienced difficulty in securing responses to the food
growing survey this year from external organisations, however we expect
further returns in the coming months which will evidence increase in
number of food growing participants. Cuningar Allotment site is currently
under construction and will be handed over to Amenity Services in early
Autumn 2024, increasing the overall number of allotment plots and food
growing participants. The total number of recorded food growing
participants on Council land is currently 1,065.
Report Later 5% 0% ------ ------ ------
Natural Environment (Planet)
Page 6 of 51
23

Page 24

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Performance Measures
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Performance Measures
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Performance Measures
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Performance Measures
Natural Environment (Planet)
Improve the availability and access to quality outdoor spaces and services
Performance Indicators Comments/ Progress Status 2021/22 2022/232020/21Target To Date
-------- Last 3 Years --------------------- This Year -------------
Percentage of streets found to be
acceptable during Litter Monitoring System
Survey
Percentage of streets found to be acceptable via Litter Monitoring
Systems Surveys is 92% meeting the target for the year.
Green 92.0% 92.0% 94.1% 92.1% 92.3%
Retain Green Flag accreditation at
Strathaven Park, Cambuslang Park and
Castlebank Park
Green Flag accreditation was successfully retained for all three parks in
2023. Action plans are being developed for all three parks in 2024 this
year.
Green 3 3 3 3 3
A Green Economy (Planet)
Lead the transition to a circular economy and improve resource efficiency through responsible consumption and production, and buying and selling of local
goods and services
Performance Indicators Comments/ Progress Status 2021/22 2022/232020/21Target To Date
-------- Last 3 Years --------------------- This Year -------------
Percentage of total household waste that is
recycled
This measure is reported per calendar year. The year to date figure to
the right reflects performance from January to December 2023
(43.75%).  This remains below the target of 50%.
Performance in October to December 2023 (38.71%) was an
improvement on the same quarter in 2022 (37.75%).
The new bulky waste contract continues to increase the quantities of
bulky waste being recycled. Performance will continue to be closely
monitored.
Red 50.00% 43.75% 40.50% 41.50% 41.20%
Percentage of household waste sent to
landfill
This measure is reported per calendar year and the latest figures relate
to the period from January to December 2023  (1.50%).  This remains
well below the target to stay under 10%.
Performance in October to December 2023 (1.61%) is lower  (better)
than the same quarter in 2022 (2.07%).
Green 10.0% 1.5% 9.7% 8.7% 1.8%
Page 7 of 51
24

Page 25

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
Sustainable Development and Climate Change
Strategy - Section 2: Improvement Actions
The following section provides improvement actions that contribute towards meeting the outcomes in each
theme for this financial year.
Page 8 of 51
25

Page 26

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
People
Contribute to improving health and wellbeing through environmental protection and access to environmental benefits for all
Action Measures Comments/ Progress Status
Safeguard health by
improving air quality
Implement grant funded air quality measures during 2023-24
to support the Air Quality Action Plan and continue to
maintain and publicise both real time and historical air quality
monitoring results.
The Lanark air quality management area was revoked in February
2024 as air quality objectives had been successfully met. Further work
has commenced on reviewing the remaining two air quality
management areas at the Whirlies and Rutherglen. Study findings of
measured particulate matter levels show they have been successfully
brought to below air quality objectives indicating improved air quality.
A review of South Lanarkshire Council's Air Quality Action Plan has
been undertaken and formal consultation is about to commence.
Engine idling campaign work continues with a focus on idling outside
schools. This work is funded through Scottish Government grant
funding.
Action planning work is also ongoing with EcoStars, BetterPoints -
Think, Move, Breathe, WALKCYCLE4AIR, Beat the Street
(Clydesdale), Waymarking signage project in east Kilbride and Walk to
School projects. All being supported through grant funding.
Green
Identify and manage
contaminated land
within the statutory
regulatory framework
Implement the Contaminated Land Strategy and support the
Planning Authority in relation to development applications
Work continues in relation to sites with historical contamination issues
linked to previous land use.  Contamination legacy issues have been
found in various sites.
The review of site investigations, remediation proposals, as well as
final verification of remediation works, form part of the work to ensure
that sites with contamination issues are identified and any
contamination issues addressed. The overarching ambition to bring
such sites into sustainable and beneficial use.
Green
Incorporate the risk of
heat and overheating in
the corporate risk
Include the risk of heat and overheating in the corporate
severe weather scorecard with relevant mitigation measures
Top risk for adverse weather has been updated to include heat and
overheating within the corporate severe weather scorecard. Updated
as at 2023/2024 review.
Complete
Page 9 of 51
26

Page 27

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
People
Contribute to improving health and wellbeing through environmental protection and access to environmental benefits for all
Action Measures Comments/ Progress Status
register Ensure that heat and overheating is incorporated in each
Resource's risk scorecard
All relevant Resources have been instructed to include heat and
overheating within risk scorecard.
Complete
Promote healthy and
local sustainable food
including Fairtrade
products to Council
employees and South
Lanarkshire residents
Support campaigns promoting healthy and local sustainable
food and share good practices.
National campaigns from the national Love Food Hate Waste initiative
and promoting food waste reduction were shared on Council social
media.
Green
Continue to administer
and monitor the Food
Strategy Support Fund
Ensure project delivery and outcomes achieved by March
2024.
£0.277m of the £0.300m has been committed, with the breakdown of
projects as follows:
• £205,000 to provide a new allotment site in the Hamilton area. The
Chatelherault site is complete and fully occupied.
• £15,000 to develop additional growing space at Richmond Allotment.
• £5,000 for Unpaid Work Service Garden Project (Social Work).
• £20,000 for the Food Strategy Community Grants were allocated to
groups in 2022-23.
• £32,500 to five other projects which were approved for funding in
financial year 2021-22.
The remaining £23,000 was returned to Corporate Finance as a result
of a savings exercise.
Complete
Page 10 of 51
27

Page 28

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
People
Progress climate justice and ensure the transition to net-zero by 2045 does not exacerbate poverty or inequalities
Action Measures Comments/ Progress Status
PHD student from
Glasgow Caledonian
University will undertake
a study to assess impact
of climate change on
South Lanarkshire
communities.
The PHD student will submit a proposal and methodology
which will be internally assessed by the supervisory panel by
March 2024.
The PhD Student submitted the final version of their RDC2
(Application for Confirmation of Progression) in October 2023 and this
was approved by the supervisory panel. The report provides details on
research aim and research objectives, and proposed methodology and
methods including ethical considerations. Approval of this has allowed
the student to progress onto the data collection phase of the project.
Complete
Support the households
within the South
Lanarkshire Council
area that are in, or are
susceptible to being in,
fuel poverty
Use the datasets available via the Scottish Government and
the Energy Savings Trust's Home Analytics tool to identify
properties where residents are in or are susceptible to
poverty. The findings will be used to prioritise investment and
support energy efficiency measures.
The findings from analysis of the datasets is being incorporated in the
decision-making process for investment via the council’s LHEES.
Complete
Investigate options to
replace fossil fuel
heating systems within
our domestic properties
Carry out a review of the Air Source Heat Pumps (ASHP)
installation programme in our domestic properties by March
2024
No pre ASHP installation heating data was available for our domestic
properties to complete an appraisal. Instead, there is sufficient
third-party studies available demonstrating that air source heat pumps
use less electricity to produce the same heating output as electric
storage heating. To date ASHPs have only been used to replace
non-gas heating systems so as not to burden our tenants with
additional costs due to the high electricity to gas cost ratio.
Complete
Page 11 of 51
28

Page 29

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
People
Progress climate justice and ensure the transition to net-zero by 2045 does not exacerbate poverty or inequalities
Action Measures Comments/ Progress Status
Carry out feasibility work to assess the financial implications
to a household as a result of decarbonisation of heat to their
home by March 2024
An exercise was carried out which found that the costs associated with
heating a property using gas was more than £100 cheaper per annum
than heating a property using an ASHP at that time.
Complete
Page 12 of 51
29

Page 30

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
People
Progress climate justice and ensure the transition to net-zero by 2045 does not exacerbate poverty or inequalities
Action Measures Comments/ Progress Status
Identify and support the
development of
initiatives to tackle food
poverty and food
security
Work in partnership with the Community Planning
Partnership organisations and community food organisations
to reduce the reliance on food banks by prioritising access to
emergency financial assistance, money advice and access
to holistic support services
Following the publication of the national plan “Cash-First: towards
ending the need for food banks in Scotland” in June 2023, Money
Matters Advice Service launched a Cash-First Scheme using the
Council Financial Wellbeing Support Fund to support households with
£50 vouchers.
From the beginning of this project on 2nd October 2023 to 1st March
2024, the service has issued 1,845 vouchers of £50 to households for
a total value of £93,250. There have been 1,743 families accessing
the voucher with 122 accessing the fund for a second voucher. Money
Matters Advice Service has a partnership agreement in place with
Clydesdale, Hamilton, and East Kilbride Citizen Advice Bureau
therefore clients can be referred to the fund via those agencies.
The council financially supported seven local food banks in
2023-2024, they received £4,000 each.
Along with St Anthony's and St Mark's foodbank, all seven council
supported foodbanks are listed within the new version of 'Money is Not
the Only Problem' booklet. The online directory will also be updated.
During Christmas, over 1,000 gifts were donated across the 8 food
banks, all taking a share of either gifts, or food items (in some cases
some foodbanks opted for both) (1,056 Gifts were donated by council
and SLLC staff, and 790 food items).
A community networking event including community food organisations
was organised by the Community Engagement Team during the
Challenge Poverty Week in October 2023.
Eleven "Spectacular Summer Session Hubs" were successfully
delivered across the four localities of South Lanarkshire in key
Green
Page 13 of 51
30

Page 31

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
People
Progress climate justice and ensure the transition to net-zero by 2045 does not exacerbate poverty or inequalities
Action Measures Comments/ Progress Status
locations between 03/07/2023 and 11/08/2023. Each hub delivered a
targeted intensive two-week programme which ran Monday-Friday with
breakfast and lunch included. Across the 6 weeks, over 4,500 meals
were provided.
Promote the
weather-related
warnings and advice
provided by the Met
Office and SEPA to
support individual and
community
preparedness
Cascade Met Office and SEPA warnings and advice via
council social media in real time through the council's Public
Communications Team
Alerts issued where appropriate Complete
Localise the UN's global
Sustainable
Development Goals
(SDGs) and integrate
with South Lanarkshire's
Community Plan
The Community Planning Partnership will map the SDGs to
the community plan related Statutory Partnership Plans and
agree local targets and indicators by March 2024
Thematic Group Leads completed a workshop on the SDG toolkit and
how to map their plans to the SDG goals in January 2024.  All plans
have now been mapped, however the development of local targets
and indicators has been put on hold due to a request from the
Community Planning Partnership Board for a session on Performance
which will take place in May 2024.  The outcomes of this session will
inform how this work moves forward.
Amber
Influence change through improving the understanding of Sustainable Development and the Climate Emergency across South Lanarkshire
Action Measures Comments/ Progress Status
Mainstream
sustainability and
climate literacy learning
and development across
the Council
Review the learning and development options we currently
deliver to identify where sustainability and climate literacy
could feature by September 2023.
Review was completed by September 2023. The Sustainability team
continue to review opportunities for embedding climate change and
sustainability into existing training with learning and development
teams. Further training on implementation of Sustainability Impact
Assessments (SIAs) and sustainable procurement are planned for the
forthcoming year.
Complete
Page 14 of 51
31

Page 32

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
People
Influence change through improving the understanding of Sustainable Development and the Climate Emergency across South Lanarkshire
Action Measures Comments/ Progress Status
Develop a climate emergency training package for all
employees including a learn online module by September
2023
Keep Scotland Beautiful Climate Emergency E-learning module is now
available to staff on Learn on Line.
Complete
Deliver climate literacy training to elected members by
September 2023.
KSB climate literacy training was available to all Elected Members and
was delivered in summer 2023. 14 Elected Members attended the
climate literacy training, with 6 going on to complete the assessment
and receive Climate Literacy accreditation.
Complete
Develop and implement
a robust
communications plan for
promoting and raising
awareness of the vision,
themes and priorities of
the sustainable
Work with the council’s corporate communications team to
develop a 2023-24 communications plan, by April 2023. This
will include the promotion of key campaigns throughout the
year, for example, Climate Week
At the Corporate Management Team meeting on 26 January 2023, it
was agreed that climate change would be added to the list of
permanent communications campaigns for the Council. The Climate
Change and Sustainability (CCS) Team worked with the Campaign
Lead to develop a Communications Plan which was implemented over
the course of the year. A communications plan for the 2024-25 year
has also been prepared for the forthcoming year.
Complete
development and
climate change strategy
Implement the agreed communications plan and prepare
articles, including case studies, to communicate success
stories and achievements and inspire further positive action
Regular articles and good news stories have been prepared and
shared across council social media in line with the 2023-24
communications plan in order to raise awareness, inspire and
influence positive behaviour change. Stories have included coverage
of the Climate and Nature event hosted in October 2023 by the
Community Planning Partnership, the council’s roll out of electric
vehicle charging infrastructure, and the impact of projects funded
through the council-managed Renewable Energy Fund.
Complete
Page 15 of 51
32

Page 33

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
People
Influence change through improving the understanding of Sustainable Development and the Climate Emergency across South Lanarkshire
Action Measures Comments/ Progress Status
Redesign the new Council website and intranet to ensure
sustainability and climate change information is easily
accessed
The Council will launch the new Invest South Lanarkshire website in
2024. The website provides access to sustainability information for
businesses, as well as relevant case studies.
Redesign of the main SLC website and Intranet is included in the
2024/25 IT service plan and ease of access to sustainability and
climate change information will be considered as part of this project.
Amber
Further embed
sustainable
development and
climate change into the
council’s
decision-making
process
Develop and pilot a sustainable development
decision-making tool to be applied to proposed projects and
initiatives presented to the Corporate Management Team
and Committee for approval by the March 2024
Sustainability Impact Assessments (SIAs) were developed
collaboratively by Sustainability and Finance teams and were trialled in
early 2024 on both revenue and capital budget proposals. It is
anticipated that the SIA process will remain iterative and will develop
as officers become more familiar with the process. Work is ongoing
with the roll out of SIAs and training will be delivered in the forthcoming
year to upskill officers on the implementation of the tool.
Green
Deliver town centre
visioning at a local level
Complete town centre visioning study by end June 2023 and
present final visioning strategy to Community and Enterprise
Resources Committee in November 2023
This work is now complete has been reported in conjunction with
masterplan work being carried out for Hamilton and East Kilbride.
Complete
Page 16 of 51
33

Page 34

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
People
Influence change through improving the understanding of Sustainable Development and the Climate Emergency across South Lanarkshire
Action Measures Comments/ Progress Status
Empower learners to
shape and influence
action on climate
change and
sustainability through
the youth forum
Continue to support the Youth Forum on Climate Change
and Sustainability to ensure Young People’s voices are
represented on appropriate council matters relating to this
subject area
We continue to support the Youth Forum and after the success of
COS2 (Conference of Schools) planning is underway for a COS3
event. We have also engaged the Forum in the design and
implementation of the Jump app and they are actively engaged in the
'Teach the Teacher' programme across all schools.
Green
Improve carbon footprint
of all school
communities
Introduce an app to all secondary schools to monitor and
improve behaviours linked to climate change and
sustainability.
We have introduced the Jump app in four of our secondary schools as
part of the pilot which has sustainable targets for pupils and staff at
each school with monthly prizes. The Jump app has multiple features
to record and encourage staff and pupils to lead a more sustainable
life, this includes information on active travel, recycling, energy
consumption and eating habits. The app enables users to accumulate
points depending on their behaviours and prizes are awarded monthly
for staff and pupils who have accumulated the most points. We also
have a monthly newsletter that celebrates success and promotes
national and global events and can be accessed through the app. It is
intended that the app will be rolled out to all schools.
Amber
Page 17 of 51
34

Page 35

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
People
Influence change through improving the understanding of Sustainable Development and the Climate Emergency across South Lanarkshire
Action Measures Comments/ Progress Status
Embed sustainability in
the curriculum across all
Education
establishments
Develop resources and peer learning programmes for all
schools. Utilise national resources, such as HGIOS module
on sustainability, within all schools by January 2024
Peer review materials for primary schools have been created and
trialled.  All primary schools are now in a peer review group and will
commence in session 2024/25.  Secondary schools have also
completed their trial phase of Collaborative review with all schools
ready to participate with partners during session 2024/25.
All schools have been advised to include sustainability on their school
improvement plans for next session and have been kept up to date on
all aspects and developments in this area by the Science and
Sustainability Development Officer.
Green
Page 18 of 51
35

Page 36

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
People
Influence change through improving the understanding of Sustainable Development and the Climate Emergency across South Lanarkshire
Action Measures Comments/ Progress Status
Work with our
communities to provide
programmes and
opportunities to increase
sustainability awareness
and action
Provide access to adult learning opportunities which raise
awareness on climate change
A range of projects continue to be delivered to support adult learners
engage with climate change and sustainable practices. These include:
East Kilbride Universal Connections Nowhere To Grow project; a
learner-led project for adults who wish to build skills and knowledge in
gardening and horticulture and assist in increasing local biodiversity.
Lanark Universal Connections staff worked with parents and their
children in Carstairs Junction Primary, enabling parents to support their
children complete the John Muir Award.
ESOL (English for Speakers of Other Languages) food sustainability
workshop at Glasgow Science Centre where learners attended a
workshop on food sustainability.
Such projects support adult learners to improve their understanding of
climate impact and simple changes that can provide a net benefit to
the environment and South Lanarkshire. These programmes also help
provide educational opportunities that develop learners' core and
social skills.
Green
Page 19 of 51
36

Page 37

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
People
Influence change through improving the understanding of Sustainable Development and the Climate Emergency across South Lanarkshire
Action Measures Comments/ Progress Status
Promote the Environmental and Sustainability Learning
Programmes and Awards delivered across the authority
Learners continue to be supported to access awards such as the John
Muir Award as well as increase understanding of environmental
issues, through participating in outdoor learning opportunities delivered
through the Youth, Family and Community Learning (YFCL) Awards
Team and the network of Universal Connections facilities and YFCL
projects. This work is underpinned by the South Lanarkshire Youth
Strategy as well as the Learning for Sustainability Action Plan.
It should be noted that the John Muir Award will not be available for the
next year as the John Muir Trust are reviewing and updating the
award. However, the aims and objectives will continue to be
progressed and recognition awarded through local systems, and
alignment with other awards where applicable.
Following a development session with the Community Planning
Partnership board, a model of engagement has been proposed to
strengthen dialogue between young people and the Board regarding
environmental issues and ideas to tackle climate change in South
Lanarkshire.
The revised Community Learning and Development 3-year strategic
action plan will underpin such developments and opportunities to
promote environmental and sustainability learning programmes and
awards, both existing and new, will be considered.
Green
Page 20 of 51
37

Page 38

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
Place and Communities
Improve affordable, sustainable, and accessible transport options
Action Measures Comments/ Progress Status
Encourage active travel
by extending our
network of walking and
cycle routes
Continue the design and implementation of various cycle
routes in towns and villages throughout South Lanarkshire
and consult key stakeholders throughout the project stages.
The next phase of the East Kilbride Active Travel Network on Churchill
Avenue and part of Cornwall Street was completed.
Three further Active Travel Plans for part of the Clydesdale area were
concluded and these identified priority routes for the introduction of
future active travel infrastructure.
Green
Page 21 of 51
38

Page 39

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
Place and Communities
Improve affordable, sustainable, and accessible transport options
Action Measures Comments/ Progress Status
Deliver walking and cycling projects / schemes in line with
agreed 2023-24 capital programme
A number of cycling and walking projects are progressing:
1) Active Travel Studies – A number of further studies have been
completed for towns including Blackwood, Kirkmuirhill, Abington,
Crawford, Carnwath, Forth and Biggar. These complete studies for all
areas of South Lanarkshire and have been uploaded onto the
Council’s website. The priorities identified in these studies will be
reviewed as part of the development of the new Local Transport
Strategy.
2) East Kilbride Cycle Network – The next phase of the development
of a segregated cycle network with enhanced pedestrian facilities in
East Kilbride has commenced on Churchill Avenue. This will link West
Mains Road to Cornwall Street and towards the trunk road network on
the A726. This construction work is complete and landscaping works
will be undertaken during appropriate growing seasons in 2024.
3) Carstairs to Carluke – Works which include surfacing upgrades,
shared cycle /pedestrian crossing points of the A706 and A70, signing,
road markings and other associated works, and transfer of land
ownership to allow for the final section to be constructed, is
programmed for 2024.
4) Cycle Parking Provision in Town Centres – Locations for new
shelters have been identified with associated consultation and works
programmed for 2024.
5) Cycle Shelters and parking stands in schools – New shelters will be
installed in several schools in 2024.
6) Cycle Route designs continue being taken forward in various
locations such as Carstairs, Hamilton, Uddingston and Bothwell.
Green
Page 22 of 51
39

Page 40

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
Place and Communities
Improve affordable, sustainable, and accessible transport options
Action Measures Comments/ Progress Status
Deliver new and
improved low carbon
vehicle charging
Install and renew charging infrastructure points which are
available for use by the public within South Lanarkshire
The installation of 13 dual outlet 7kW charge points within on-street
residential areas is now complete and all charge points are now
available for public use.
Green
infrastructure Continue project design development and implementation
and attract private investment within South Lanarkshire
We have developed an EV infrastructure Expansion Plan and Strategy
which has identified the future requirement for charging infrastructure
within SLC. This project was done in partnership with Glasgow City
Region and we are now investigating the most appropriate financial
model to allow for the rapid expansion of the network.
Green
Page 23 of 51
40

Page 41

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
Place and Communities
Improve affordable, sustainable, and accessible transport options
Action Measures Comments/ Progress Status
Progress towards
decarbonising the fleet
of South Lanarkshire
Council vehicles
Implement the Fleet Strategy (2020-2025) Action Plan
including a reduction in transport related emissions,
conversion of fossil fuelled small fleet to full electric and the
trialling of new fuel option for the medium to heavy fleet.
The Fleet Asset Management Plan 2024 is being finalised, when
complete it will be forwarded to Head of Service for review, after which
it will be copied to Housing and Technical Resources for inclusion in
the Corporate Asset Management Plan. The Fleet Asset Management
Plan provides an update in relation to progress against the actions
contained in the Fleet Strategy (2020-25). It is recognised that the two
years lost to the Covid-19 pandemic have impacted the extent of
progress that might have otherwise been made.
Green
Page 24 of 51
41

Page 42

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
Place and Communities
Improve affordable, sustainable, and accessible transport options
Action Measures Comments/ Progress Status
Encourage greater use
of public transport by
working with partners to
improve public transport
infrastructure
Deliver prioritised improvements to bus and rail infrastructure
(e.g., park and ride) in line with available external funding for
2023-24
A number of projects are being taken forward as outlined below:
Bus Infrastructure Improvements:
This project consists of enhancing bus stop provision on the Stonelaw
Road corridor and will see the provision of high access kerbs/
enhanced road markings. Works are complete.
Lanark Interchange Improvements:
This project consists of two sections.
Section 1 – Park and Ride. Works associated with the main
construction elements of the second phase of the car park are
complete. A total of 64 spaces are now available including two electric
bays and eight disabled bays located adjacent to the rail and bus
interchange.
Section 2 – Bus Station. The design of new bus station layout is
complete.  Discussions are ongoing with Network Rail to progress the
land acquisition/transfer.  Planning Permission has been granted and a
contract award has been delayed due to SPT's Capital Funding
position for 2024/25.
Hairmyres Station Park and Ride:
This project consists of the design and submission of a planning
application for proposed Park and Ride facilities associated with the
East Kilbride Rail Enhancement project. The package of works
associated with the Park and Ride includes new active travel
connections, bus stop and bus layover provision and electric vehicle
charging infrastructure. Pre-planning application public engagement
exercises were completed and a planning application has been
submitted. Programming discussions with Network Rail and Transport
Scotland are ongoing.
Bus Priority System - Approximately 60 traffic signal controlled
Green
Page 25 of 51
42

Page 43

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
Place and Communities
Improve affordable, sustainable, and accessible transport options
Action Measures Comments/ Progress Status
junctions have been upgraded to facilitate a new priority system. This
operates by identifying in real time whether buses are behind their
timetable, with traffic signals altered to allow  late buses to make up
lost time. This system has been installed and initial monitoring is
ongoing.
Work with partners to encourage and highlight the benefits of
public transport usage and transport integration
We continue to work with SPT and public transport operators to
encourage the use of public transport. Lanark Park & Ride facility
opened this year and was funded by SPT and we are progressing with
the planning application for Hairmyres Park and Ride Site. Real time
information has also been installed at a number of bus stop locations
in Rutherglen. Real time information displays the bus services/route
numbers due and provides live updates on expected arrival times,
comparing these to the scheduled timetable.
Green
Ensure climate change,
access to services and
active travel forms part
of the design of new
residential
developments through
the revised Residential
Design Guide
Develop interim framework for consultation with
stakeholders, with final framework prepared by end of June
2023
Planning and Building Standards have developed a Place-Making
Guide rather than a Residential Design Guide, reflecting national
policy on the importance of place-making. The Placemaking Guide will
ensure that the places we shape will be sustainable at their core and
are nature positive, bolstering climate resilience and nature recovery.
The draft Place-Making Guide will be presented to the relevant
committee. There will be a six week period of public consultation
following committee approval.
Amber
Present finalised document to Planning Committee for
approval by December 2023
Once the above comments have been received and considered, the
finalised Place-Making Guide will be presented to the relevant
committee later in 2024.
Amber
Page 26 of 51
43

Page 44

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
Place and Communities
Improve affordable, sustainable, and accessible transport options
Action Measures Comments/ Progress Status
Utilise ultra-low carbon
vehicles or public
transport for Education
related travel
Consider a staged approach to changing the school
transport specification to prioritise low carbon vehicles over
price.
There are still not enough transport providers with low carbon vehicles
to meet the requirements of school transport. After consideration, there
is not enough market availability for school transport specification to be
changed. Once the market changes and required vehicle types are
more readily available we will look at altering our tender specifications.
Amber
Liaise with SPT and improve our internal procurement
framework to procure and provide ultra-low carbon vehicles.
There are still not enough transport providers with low carbon vehicles
to meet the requirements of school transport. However we continue to
engage with SPT on this issue and encourage contractors to access
funding that may be available to change some of their fleet to low
carbon vehicles.
Amber
Consider sustainable
travel within the
council’s employee
travel plan
Review the current employee travel plan during FY 2023-24
to encourage employees to adopt sustainable travel choices
An initial review has been undertaken. So far, opportunities to reduce
employee travel have been related to the greater use of online
meetings.
A more comprehensive review will take place in 2024/25 and is an
action within the HR team 2024 - 25 workplan.
Green
Continue to achieve
Cycle Friendly Employer
status
Ensure that current cycle friendly status facilities are retained Current cycle friendly status facilities have been maintained with any
additional requests considered in line with available funding.
Green
Page 27 of 51
44

Page 45

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
Place and Communities
Progress a transition to net-zero, energy efficient and climate resilience homes, buildings and infrastructure, and minimise the unsustainable use ofnatural resources and regenerate where appropriate
Action Measures Comments/ Progress Status
Reduce South
Lanarkshire Council's
carbon footprint
Prepare a route map for reducing the council's direct and
indirect carbon emissions.  Agree milestones and targets for
both direct and indirect emissions reductions
The Council has committed to a zero Scope 1 (direct emissions) target
by 2038 but it does not have a route-map in place to achieve this
target. This route map is being developed as part of the Council’s
longer-term Net Zero strategy and will require collaboration with all
Resources. Over the next 18 months a number of reports will be
produced which will inform a future SLC net zero route map. These will
be presented to Climate Change and Sustainability Committee and
include:
•Carbon Management Year End Report 2023-24
•Public Sector Climate Change Public Duties Report 2023 -24
•Fleet Modernisation Plan
•South Lanarkshire Local Heat and Energy Efficiency Strategy
•Carbon Future Targets Report
Green
Reduce South
Lanarkshire Council's
carbon footprint for
indirect emissions not
currently measured
Agree the scope of indirect emissions not currently
measured and prepare a route map for reducing.
A Climate Intelligence Service (CIS) is being jointly funded by Scottish
Government and local government to help councils to deliver their own
net zero targets and for the development of Scope 3 (indirect
emissions) and area-wide programmes of emissions reduction. The
CIS is in the initial stages with user groups being set up with local
authorities to establish the key requirements of the service. The
Council’s Sustainable Development Officers are attending these
preliminary sessions and will continue to engage with the CIS on
behalf of South Lanarkshire Council.
Green
Support towns to
transition to net zero
Complete Town Centre net zero study by end June 2023 and
present finding to Community and Enterprise Resources
Committee in November 2023.
This work is now complete has been reported in conjunction with
masterplan work being carried out for Hamilton and East Kilbride.
Complete
Page 28 of 51
45

Page 46

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
Place and Communities
Progress a transition to net-zero, energy efficient and climate resilience homes, buildings and infrastructure, and minimise the unsustainable use ofnatural resources and regenerate where appropriate
Action Measures Comments/ Progress Status
Explore funding and
finance models for
net-zero and climate
adaptation projects
Establish an internal process that will support Services to
maximise funding options and secure match funding for
projects
A report on Scottish Government funding opportunities has been
circulated round the Climate Change and Sustainability Steering
Group. Managers have been advised that the External Funding Team
provide support on funding applications for all Resources.
Green
Continue to administer
and monitor the Climate
Emergency Fund
Ensure project delivery and outcomes achieved by March
2024. Report on progress and impact of the funding  to the
Climate Change and Sustainability Committee
The fund has been fully committed to posts, internal projects and
community grants and all projects are progressing.
A mid-term report on the progress and impact of the Climate
Emergency Fund was presented at the Climate Change and
Sustainability Committee in November 2022. This report highlighted
the progress made and impact of the fund so far, how the fund has
been allocated and the projects that are underway. A full-term report on
the Climate Emergency Fund will be presented to the Climate Change
and Sustainability Committee when all project outcomes have been
received and collated.
Green
Ensure environmental
sustainability
considerations are
Review proposed capital programme and assess
sustainability impacts
Detailed Sustainability Impact Assessments completed for the
2024/2025 Council Capital Programme and issued to Elected
Members for consideration.
Complete
considered within capital
plan
Establish a climate impact assessment process for the
capital programme and projects by end June 2023
Process agreed by Climate Change and Sustainability Committee and
used for 2024/2025 Budget. Sustainability Impact Assessments (SIAs)
will continue to be refined and embedded, to be utilised in all future
Capital Budget setting exercises.
Complete
Page 29 of 51
46

Page 47

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
Place and Communities
Progress a transition to net-zero, energy efficient and climate resilience homes, buildings and infrastructure, and minimise the unsustainable use ofnatural resources and regenerate where appropriate
Action Measures Comments/ Progress Status
Ensure environmental
sustainability
considerations are
considered within
budget strategies
Carry out an environmental impact assessment on the
annual revenue budget
Sustainability Impact Assessments were completed for 2024/2025
Revenue Budget and Savings and issued to Elected Members for
consideration.
Complete
Provide a summary on a
place-based approach
to climate action across
South Lanarkshire
Prepare a report for the Community Planning Partnership
summarising the various local placed based climate actions
and ensure local placed based action is being incorporated
into other actions
A report on community place-based climate action was presented to
the Sustainable Development and Climate Change Committee in
February 2024.
The Sustainable Communities Engagement Officer was in post until
March 2024 and was successful in building relationships and working
alongside communities, colleagues and external partners to help
support and encourage climate action at community level. The work
undertaken by this fixed-term post has been successful in further
embedding a place-based approach to climate action across South
Lanarkshire.
Green
Page 30 of 51
47

Page 48

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
Place and Communities
Progress a transition to net-zero, energy efficient and climate resilience homes, buildings and infrastructure, and minimise the unsustainable use ofnatural resources and regenerate where appropriate
Action Measures Comments/ Progress Status
Promote and encourage community engagement for
community led neighbourhood planning
The Sustainable Communities Engagement Officer continued to work
in conjunction with the Community Engagement Team within
neighbourhood planning up to the end of the fixed term post in March
2024. This work was particularly successful in embedding
sustainability considerations in community led neighbourhood
planning, for example through the Sustainable Communities
Engagement Officer's attendance at neighbourhood planning meetings
and events with community members and other stakeholders.
Green
Page 31 of 51
48

Page 49

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
Place and Communities
Progress a transition to net-zero, energy efficient and climate resilience homes, buildings and infrastructure, and minimise the unsustainable use ofnatural resources and regenerate where appropriate
Action Measures Comments/ Progress Status
Manage flooding
priorities and deliver
prioritised flood
protection schemes.
Deliver prioritised flood protection projects / studies in line
with available capital and revenue funding for 2023-24
Programme of Culvert Maintenance:
This is an ongoing programme of works on our network of culvert inlets
and their surrounding areas, with a view to improving the performance
of assets and the safety of operatives. Works have been identified and
these include the repair/replacement of culvert inlet trash screens and
the construction of suitable access paths, steps, fencing and handrails.
These works are being progressed on a continuous basis throughout
the year.
Backmuir Road, Hamilton:
Proposed works include the repair of damaged security fencing,
improved access for mechanical cleaning operations and repair of
damaged gabion baskets at this culvert inlet. The extent of the
required works are currently being scoped, and are programmed to go
out to tender in June 2024 with works being undertaken in late
summer/autumn 2024 depending upon contractor availability.
Park Avenue, Coulter:
Proposed installation of Property Level Protection measures and
community resilience measures in the vicinity of Park Avenue, Coulter.
The specification of materials is still under review at this time, however
works are programmed to be awarded to our contractor in June 2024
with works complete by September 2024.
Jonquil Way, Carluke:
Proposed works to create a flood bund adjacent to Jonquil Way, to
intercept and attenuate flood water during heavy rainfall events to
protect adjacent residential properties. The extent of the required
works are currently being scoped, and are programmed to go out to
tender in July 2024 with works being undertaken in autumn 2024
depending upon contractor availability.
Green
Page 32 of 51
49

Page 50

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
Place and Communities
Progress a transition to net-zero, energy efficient and climate resilience homes, buildings and infrastructure, and minimise the unsustainable use ofnatural resources and regenerate where appropriate
Action Measures Comments/ Progress Status
James Hamilton Heritage Loch, East Kilbride:
In response to the recommendation contained within the Reservoir
Engineer’s report, we are progressing with the internal lining of the
outflow pipe that drains the James Hamilton Heritage Loch in East
Kilbride. The scope of works has been agreed, and the contractor has
been awarded these works in May 2024. Works are programmed to be
complete in June 2024.
Improve resilience of the
road network through
routine maintenance
Review current road maintenance practices to improve
climate change resilience through the use of alternative
methods, materials and design standards
The service regularly considers alternative maintenance techniques in
conjunction with industry best practice to help improve our carbon
footprint and climate change resilience.
The use of alternative techniques is subject to the scrutiny of our
engineering teams where consideration is given to engineering merit,
operational delivery, future maintenance, and whole life cost.
The service regularly collaborates with Scottish Collaboration of
Transportation Specialists (SCOTS) and the Scottish Roads Research
Board to drive innovation within this area.
Green
Develop online services
for citizens reducing
need for travel
Continue to develop online services as part of the council’s
Digital Strategy
The SLC website now hosts 195 online forms that allows citizens to
request council services.  This is an increase of 20 forms since the
previous update from September 2023.
Green
Maximise the number of council services which can be
provided online via the council website
Progress against this action outlined above. We will continue to
identify options for increasing the number of council services provided
online.
Green
Page 33 of 51
50

Page 51

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
Place and Communities
Progress a transition to net-zero, energy efficient and climate resilience homes, buildings and infrastructure, and minimise the unsustainable use ofnatural resources and regenerate where appropriate
Action Measures Comments/ Progress Status
Utilise innovative and
new information
technologies for
environmental benefits
Develop business cases for demonstrator Internet of Things
(IoT) projects
IOT describes a network of devices with sensors, processing ability,
software and other technologies that connect and exchange data with
other devices and systems over the Internet or other communications
networks.
IT Services have included IoT within the Digital Transformation
workstream. The project has been placed on hold to better align with
Digital Transformation timeline. IT Services will provide updates as this
progresses.
Red
Continue the migration to Oracle Cloud Fusion system to
support agile working, employee self-service and
engagement
Fusion is live for Finance and Procurement functions. HR and Payroll
functionality is due to go live in August 2024.
Green
Explore sustainable web design to reduce the council
website's carbon footprint
Redesign of SLC website and Intranet is included in the 2024/25 IT
service plan and sustainable web design will be considered as part of
the project. Our ongoing focus seeks to ensure that we minimise our
carbon footprint through the reuse of code and compressed images to
reduce server load.
Green
Implementation of
revised Building
Regulations in relation
to energy performance
in new buildings and the
adaptation of existing
buildings.  
Undertake awareness sessions for surveyors and
internal/external stakeholders on the application of revisions
to building regulations related to energy standards, including
guidance for surveyors where required
Ongoing training and awareness sessions have been provided for
surveyors and other colleagues involved in new building development
within the Council.
Green
Page 34 of 51
51

Page 52

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
Place and Communities
Progress a transition to net-zero, energy efficient and climate resilience homes, buildings and infrastructure, and minimise the unsustainable use ofnatural resources and regenerate where appropriate
Action Measures Comments/ Progress Status
Assess council housing
stock in order to meet
the Energy Efficiency
Standard for Social
Housing (EESSH2) by
2032
Analyse housing stock by property type and current EPC
/RdSAP rating to identify properties that will be unable to
attain EPC Band B by 2032
Analysis completed and a report has been prepared for Housing and
Technical Resource Management Team detailing the findings.
Complete
Promote and provide
assistance to owner
occupiers and private
landlords to improve
energy efficiency,
reduce fuel poverty and
assist in the
decarbonisation of
homes
Work with local energy advice and support organisations to
understand the prevalence of fuel poverty in owner occupied
and private rented properties. Support targeted interventions
for owner occupiers /private landlords which could help to
reduce fuel poverty in these areas.
Work in this area continues, with our approach to tacking fuel poverty
incorporated into the Council’s Local Heat and Energy Efficiency
Strategy (LHEES) which was approved by the Executive Committee on
26 June 2024.  With a priority of alleviating fuel poverty, South
Lanarkshire Council has used the LHEES process to investigate areas
of high probability of multiple deprivation in conjunction with specific
property types (using data from the Scottish House Condition Survey
and the Scottish Index for Multiple Deprivation).
The Financial Inclusion Networks’ Fuel Poverty Sub-Group continues
to raise awareness of issues between services and identify solutions to
help households who may be impacted by fuel poverty. Short term
actions such as identifying grants for eligible households are taken
forward alongside longer, strategic discussions on how best to support
households across all tenures.
Green
Develop a Local Heat
and Energy Efficiency
Strategy (LHEES) and
delivery plan for South
Lanarkshire
Prepare LHEES and delivery plan for South Lanarkshire by
end of 2023 by working with colleagues across council
Resources and registered social landlord partners
The Council’s Local Heat and Energy Efficiency Strategy (LHEES) and
Delivery Plan were approved by the Executive Committee on 26 June
2024.
Complete
Page 35 of 51
52

Page 53

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
Place and Communities
Progress a transition to net-zero, energy efficient and climate resilience homes, buildings and infrastructure, and minimise the unsustainable use ofnatural resources and regenerate where appropriate
Action Measures Comments/ Progress Status
Support Registered
Social Landlord partners
to improve the energy
efficiency of their
housing stock and meet
EESSH2
Use the RSL forum to engage with Registered Social
Landlord partners with council wide Energy Efficient
Scotland: Area Based Schemes
The Council regularly consults with the RSLs on applications for the
Area Based Schemes.
Green
Review new build home
specifications to meet
the national low or zero
emissions heat
requirements
The implications for future design enhancements will be
assessed and specifications updated as required
Consultancy Services design review group continually update and
review current specifications and standards to ensure maximum
energy efficiency and consideration of embodied carbon.
Green
Review specification
and standards for new
build non-domestic
buildings for maximum
energy efficiency
Set up a joint working group to review and update current
specifications and standards to ensure maximum energy
efficiency and consideration to embodied carbon. Briefing
sessions will be arranged with Council Resource
representatives who are looking to construct new
non-domestic properties or extensions to existing buildings
A Performance and Standards Team has been created within the new
Property Services Structure which will have a focused approach on
standardisation of specifications and the approach to retrofit. The team
will work closely with the Investment team.
Currently our New Build properties are being designed in close
collaboration with Building Standards and managed by our New Build
Design Co-ordinator and Design Advisor.
Complete
Assess the council's
non-domestic buildings
and develop a detailed
action plan on how it will
Commission feasibility studies to assess what types of
intervention will be required and  what types of replacement
heating systems may be viable
Feasibility studies were completed for a sample of wet leisure facilities
and primary schools by December 2023. The findings of these studies
were reported to Climate Change and Sustainability Committee in May
2024.
Complete
Page 36 of 51
53

Page 54

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
Place and Communities
Progress a transition to net-zero, energy efficient and climate resilience homes, buildings and infrastructure, and minimise the unsustainable use ofnatural resources and regenerate where appropriate
Action Measures Comments/ Progress Status
meet the national target
of being heated by zero
carbon heat sources by
2038.
Assess the financial implications to both upfront Capital and
ongoing Revenue costs of the interventions
Report has been presented to Climate Change and Sustainability
Committee on 15th May 2024 entitled "Non-Domestic Buildings – Net
Zero Feasibilities". The report detailed the scale of investment required
to undertake interventions, in terms of both capital and revenue costs.
Complete
Support the delivery of
Climate Ready Clyde's
(CRC) Adaptation
Strategy
Continue as an active member of the CRC Local Authority
Forum participating in city-region wide workshops and
events, creating connections and opportunities for
development/co-sharing of knowledge and training by 2024
South Lanarkshire Council continues to be an active member of CRC
which meets quarterly. This is the Local Authority Forum for
Collaborative Climate Adaptation Action across Glasgow City Region.
The Forum allows Local Authorities to work together to build capacity
to support adaptation action and look for opportunities to deliver
integrated and collaborative adaptation.
Green
Contribute to the development and implementation of local
actions that contribute to the wider Glasgow City Region's
(GCR) Adaptation Strategy, where appropriate, working
across Council Resources
SLC continues to be an active member of Climate Ready Clyde and
contributes to raising awareness internally of the GCR Adaptation
Strategy.
Green
Benchmark the Council
against Adaptation
Scotland’s Adaptation
Capability Framework
Set up an adaptation working group by summer 2023 A new Climate Change and Sustainable Development Officers' Group
has been set up which will assume the responsibilities and key tasks
of the proposed adaptation working group. The group has already
undertaken a Climate Change Assessment Tool review which includes
consideration of Adaptation and has contributed to the council's
response to the Scottish Government's Scottish National Adaptation
Plan 2024 - 2029 (SNAP3) consultation.
Green
Page 37 of 51
54

Page 55

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
Place and Communities
Progress a transition to net-zero, energy efficient and climate resilience homes, buildings and infrastructure, and minimise the unsustainable use ofnatural resources and regenerate where appropriate
Action Measures Comments/ Progress Status
Undertake a capability assessment to understand the
Council’s current status and to identify gaps and areas for
improvement by March 2024 
The new Climate Change and Sustainability Officer Group undertook a
Climate Change Assessment Tool (CCAT) assessment in May 2024.
The CCAT is designed to help public bodies to assess their current
performance and make a plan for future action through identifying
gaps and areas for improvement. The CCAT will be revisited annually
to give a comprehensive overview of progress made, where the
council is improving in addressing climate chance and its impacts, and
anywhere weaknesses may continue to exist.
Green
Work collaboratively with
Clyde Gateway Urban
Regeneration Company
(URC) on district heating
Complete technical studies, obtain statutory consents and
implement enabling infrastructure on site to influence and
enable the delivery of a district heating and cooling system at
Shawfield Phase 1
Clyde Gateway URC is continuing to deliver the D2 Grids Renewable
Energy project which will create a 5th generation heating and cooling
network utilising treated effluent wastewater from Scottish Water’s
Waste Water Treatment Works.   The system connects to an energy
network in Magenta Business Park, Shawfield and will provide energy
to Red Tree Magenta and future developments.  The system also
includes ground based solar array to support the operational
requirements of the sub-station.  The project has experienced some
delays due to SPEN approvals however works are on site.
Green
Empower communities to take climate action and be more environmentally sustainable
Action Measures Comments/ Progress Status
Continue to administer
and monitor the Climate
Emergency Community
grant fund
Allocate £75,000 to projects over financial year 2023/24.
Provide support to groups to apply and implement their
sustainability projects. Monitor grants to ensure projects are
progressing.
The £75,000 for the Climate Emergency Community Grants 2023-24
has been fully allocated to groups and projects are being progressed.
Green
Page 38 of 51
55

Page 56

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
Place and Communities
Empower communities to take climate action and be more environmentally sustainable
Action Measures Comments/ Progress Status
Develop and deliver a
Public Engagement plan
Develop a public engagement plan for climate change and
sustainability which supplements the council’s existing
community engagement activity, and supports the
communities own priorities and aspirations, for approval by
the Climate Change and Sustainability Committee in May
2024
An outline structure for the proposed Plan was drafted and an initial
meeting was held with the Council's Community Engagement
Manager. As this piece of work developed over the course of the year it
was determined that the proposed communications plan for 2024-25
would supersede the public engagement plan. The 2024-25
communications plan will be finalised by summer 2024.
Green
Celebrate success by developing an annual report to the
Climate Change and Sustainability Committee to highlight
sustainable development and climate change activity in
action within our communities, by February 2024
A report ‘Community Climate Action in South Lanarkshire’ was
presented to Climate Change and Sustainability Committee in
February 2024 providing an update to the Committee on community
climate action initiatives occurring within South Lanarkshire, which
have been supported by the Council. This report focused
predominantly on the work undertaken by the fixed-term Sustainable
Communities Engagement Officer, in post for 18 months up to March
2024. The report provided detail on a number of community climate
action projects across six themes: Young People; Biodiversity &
Conservation; Sustainable Travel; Community Energy &
Decarbonisation; Recycle & Reuse;  and Regional Climate Action Hub.
Complete
Page 39 of 51
56

Page 57

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
Place and Communities
Empower communities to take climate action and be more environmentally sustainable
Action Measures Comments/ Progress Status
Increase food growing
provision throughout
South Lanarkshire
Provide an opportunity for more people to grow food through
the provision of land for food growing, the promotion of
sustainable practices and supporting third sector
organisations involved in food growing
Chatelherault allotment site opened in Summer 2023 with an increase
of 64 plot holders.
Richmond plot 1 (Rutherglen) was reconfigured to provide 15 raised
beds to complement the existing site.
Further updates will be provided following the food growing survey
which is scheduled for later in 2024. Updates will relate to number of
growing participants, growing area available, type of growing area and
examples of activity undertaken.
Green
Support the remediation
of vacant and derelict
land that promotes
social and
environmental benefits
Support Clyde Gateway Urban Regeneration Company in a
further phase of greening and environmental improvement
works at Cuningar Loop and in further remediation works in
the next phase at Shawfield Phase 3.
Creation of 50 food growing allotments at Cuningar Loop about to
commence on site for completion in September 2024.
Remediation of Shawfield Phase 2 site being developed and
implemented following the successful Levelling Up Fund award from
UK Government.
Green
Include environmental
considerations within the
delivery of the council's
Community Wealth
Building Strategy
Improve the environmental outcomes from procurement
including support for the transition to net zero
Progress has been made with the Flexible Framework Sustainability
action plan to further embed good procurement practice. The flexible
framework is updated 6 monthly and the Council has achieved level 2
(from 5) and is working towards level 3 in People, Process, Reporting
and Stakeholders and level 4 in Strategy. Achievements this year
include implementation of a mandatory 30% sustainability score in the
technical envelope for Fair Work, Community Benefits and Climate
impacts. All high value contracts within the priority sustainability
categories receive a full sustainability test to inform the specification
and technical requirements of the tender.
Green
Work with our own services, public and private sector
partners to identify the skills they need to grow and create
wealth in the local economy, including skills needed for the
transition to a net-zero economy
A new employer engagement team has been established within the
employability team and works closely with Routes to Work South,
Business Gateway and Skills Development Scotland to co-ordinate
support to employers and identify opportunities.
Green
Page 40 of 51
57

Page 58

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
Natural Environment (Planet)
Improve the availability and access to quality local outdoor spaces and services
Action Measures Comments/ Progress Status
Ensure national
planning policy set out in
National Planning
Framework 4 in relation
to climate change,
biodiversity and
sustainable travel is
embedded in decision
making process for
planning applications
and the preparation of
the South Lanarkshire
Local Development Plan
3.
Collation of appropriate information and data to inform the
Evidence Report required as new first stage of LDP
preparation by March 2024.
Work has started on the first stage of the LDP3 process which involves
the preparation of an Evidence Report through the gathering of
qualitative and quantitative data.
It is anticipated the Evidence Report will be presented to the Full
Council for approval in early 2025. Thereafter it will be submitted to
Scottish Ministers for a Gatecheck. Once approval has been given
work will start on preparation of the Proposed Plan. It is currently
anticipated the plan will be adopted by the end of 2027.
Green
Prepare an Open Space
Strategy in partnership
with Glasgow and Clyde
Valley Green Network
Appoint a consultant to analyse the council’s open space
audit results, develop standards on open space provision
and engage with local communities and other stakeholders
Detailed analysis of the open space audit has been completed by
consultants and a draft technical report submitted. It is intended that
engagement will be carried out between now and the end of the
calendar year.
Amber
Partnership and other
council services
Draft Open Space strategy to be presented to the Planning
Committee by March 2024.
It is anticipated that a report providing an update on progress and
detailing plans for engagement on the analysis of the open space audit
will be presented to Planning Committee in Q2 2024 - 25. Thereafter, it
is anticipated that the Draft Open Space Strategy will be presented to
Planning Committee in Q4 2024 - 25.
Amber
Page 41 of 51
58

Page 59

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
Natural Environment (Planet)
Enhance, protect, and respect the outdoors and the natural and historic environment.
Action Measures Comments/ Progress Status
Make South Lanarkshire
a cleaner place to live,
work and visit free of
litter, fly-tipping and dog
waste
Encourage awareness, behaviour change and personal
responsibility, through communication with internal and
external stakeholders. Work with individual client groups to
tackle local issues such as fly tipping.
Activities and discussions are continuing to take place with all the
Resources in the Litter Strategy Steering Group as we implement the
the Litter Strategy Action Plan. An update on the delivery of the Litter
Strategy Action Plan was presented to Climate Change and
Sustainability Committee in September 2023 along with a review of the
Action Plan for the coming year.
Two pilot initiatives are underway focusing on town centres and
housing that aim to address issues of fly tipping, waste in the wrong
place, and correct presentation of domestic bins.
We undertook the annual rural roads clear-up programme with more
than nine tonnes of discarded waste collected. Clean-up teams were
sent out for 30 days, clearing more than 77 miles of roads and verges
in and around the Clydesdale, East Kilbride, Hamilton, Larkhall,
Stonehouse and Strathaven areas. The clean-up was included in
Council social media.
Green
Prepare an annual progress report for the Climate Change
and Sustainability Committee in September 2023
demonstrating the impact of the Litter Strategy (2022-2027)
The annual progress report for the Litter Strategy was presented to
Climate Change and Sustainability Committee on 20 September 2023.
Complete
Page 42 of 51
59

Page 60

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
Natural Environment (Planet)
Conserve, restore and improve biodiversity, and use nature-based solutions in tackling the climate crisis
Action Measures Comments/ Progress Status
Review council use of
herbicide with a view to
reduce the amount used
Continue to look at alternative methods to control weeds.
Carry out further trials during 2023-24 and report on progress
to Climate Change and Sustainability Committee in February
2024
Works ongoing in this area, slight reduction again in 2023 on
glyphosate used, new equipment purchased to tackle weed problems
on slabbed paths 2024-25. This is a work in progress and findings are
presented to the Amenity Forum.
Work will continue to review herbicide applications. Alternatives being
used are the recently purchased full path width metal brushes and we
are looking to develop greater use of the makur lances in all areas.
The council will continue to review dilution rates and any other new
alternatives that come onto the market to decrease the volume of
herbicide being used.
Green
Measure tree canopy
and increase tree
planting across South
Lanarkshire
Continue to measure and plot all trees to build an accurate
picture of the council’s position on canopy cover
Across South Lanarkshire, the council continue to measure / assess
existing tree canopy cover and tree equity. On Council owned or
controlled land, it also continues to develop records of the nature,
condition and resilience of tree assets and their canopy cover.
Green
Identify suitable council owned land that can be utilised for
additional tree planting. Work with all external and internal
stakeholders including community groups to seek additional
funding for tree planting.
On Council owned or controlled land, we continue to identify sites
suitable for planting trees to increase canopy cover and species
diversity. We are developing a masterplan with a prioritised delivery
plan. We are seeking additional funding for tree and woodland planting
through internal and external sources, including community groups.
Green
Increase Biodiversity
and invest in peatlands
across South
Develop a new Biodiversity Implementation Plan for
(2024-2027) approval by Climate Change and Sustainability
Committee by March 2024.
The Biodiversity Strategy and the Biodiversity Duty Implementation
Plan were approved by the Climate Change and Sustainability
Committee in February 2024.
Complete
Page 43 of 51
60

Page 61

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
Natural Environment (Planet)
Conserve, restore and improve biodiversity, and use nature-based solutions in tackling the climate crisis
Action Measures Comments/ Progress Status
Lanarkshire Participate in Clyde Peatlands to bring about a step change
in the scale and rate of peatland restoration across the City
Region
The Project Officer for Clyde Peatlands has been investigating
restoration opportunities with landowners of several raised bogs in the
East Kilbride/Chapelton area. This is with the purpose of making bids
for NatureScot Peatland Action Fund. This is currently at the early
stages and so far no proposals have been agreed.
Amber
Implement new
technologies and more
sustainable cleaning
materials within council
facilities
Pilot the use of 'Aquateck' cleaning solution in key facilities
and evaluate during 2023/24
Evaluation of Aquateck cleaning solution pilot was undertaken which
led to the roll out across all 17 of the high schools (due to complete by
August 2024).
Green
A Green Economy (Planet)
Take action to allow South Lanarkshire to become a zero-waste society
Action Measures Comments/ Progress Status
Support a circular
economy by re-using,
recycling and generating
energy from the waste
we manage
Undertake a review of the waste service during 2023-24 that
will determine most efficient refuse collection patterns and
incorporate the impact of the Deposit Return Scheme
The waste review continues to progress. A report on the scope and
progress of the review was presented to CMT in May 2024. To date,
the infrastructure review and the Household Waste Recycling Centre
(HWRC) review (including the award of the contract for the
management and operation of the council's HWRCs) has been
completed. The review of kerbside services has commenced but has
been heavily influenced by the the complex and dynamic nature of
legislative and policy landscape within the waste management sector.
Green
Page 44 of 51
61

Page 62

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
A Green Economy (Planet)
Take action to allow South Lanarkshire to become a zero-waste society
Action Measures Comments/ Progress Status
Review of recycling bins
at flatted properties in
South Lanarkshire
Review existing arrangements at flats during 2023/24 and
work with Corporate Communications to produce
communications campaign.
This work continues to progress. The service was awarded a £150k
grant from Scottish Government to pilot a new style of communal bins
for flatted properties. These new bins (along with household
communications produced in conjunction with Zero Waste Scotland)
were rolled out during April and May 2024.
Green
Reduce the instances of
avoidable food waste
Identify the share of householders using the council’s food
waste collection service during 2023 and consider extending
the food waste collection service
This piece of work was completed in early 2024. The results showed
that approximately 30% of residents who have been provided with
burgundy bins to collect food and garden waste use the bins to
dispose of food waste.
Complete
Manage and monitor
food waste in schools
Implement a pilot project in schools to reduce level of food
waste from the dining rooms during 2023/24.
Waste Warrior programme has rolled out to 31 schools by end of June
2024. Working with Education to create a resource pack for all schools
by August 2024.
Green
Deliver training online
where possible and
develop the digital skills
of South Lanarkshire
Council employees
Review existing training delivery models identifying options
for further transition to online delivery
Review of existing training delivery models within the Council is
ongoing as we continue to identify areas for improvement.  We have
successfully embedded sustainability considerations into the
commissioning of training. Where possible the Council continues to
transition training to online delivery.
Green
Ensure environmentally
sustainable training
options are delivered by
external training
providers
Work with external training providers to identify
environmentally sustainable delivery options
The Council continues to work with training providers, to identify more
sustainable delivery options. SLC commissions and delivers a large
volume of courses and sustainability is built  into considerations when
planning/commissioning the training. Sustainability is now part of our
'business as usual' plan of working, with external training providers
asked to identify more sustainable delivery options.
Green
Page 45 of 51
62

Page 63

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
A Green Economy (Planet)
Enable a fair transition to a green economy leaving no one behind
Action Measures Comments/ Progress Status
Deliver the UK Shared
Prosperity Fund to help
ensure a just transition
to net zero
Progress delivery of the new UK Shared Prosperity Fund,
initiatives that support the council, communities, and
businesses transition to net zero.
1. In 2023/24 Shared Prosperity Fund (SPF) awarded £75,000 in
Climate Emergency and Resilience Grants to community groups and
partner organisations to pursue environmental, sustainability, or
climate change projects.
2. In 2023/24 SLC worked with Glasgow City Region (GCR) and the
University of Strathclyde to develop ExtendPLUS (launched March
2024) which will facilitate carbon reporting for SMEs across the GCR.
3. In 2023/24 SPF funded an Employment Land and Market Analysis
in East Kilbride to assess the need for and feasibility of energy
efficiency investments.
Green
Increase the number of
young people obtaining
the skills to access
green and circular
economy employment
Provide senior phase vocational learning opportunities that
prepare young people for the green economy
The GradU8 programme provides opportunities for young people in
S5-S6 to engage in work based learning within a college setting.
Opportunities within the 12 subject choices with potential routes to
green jobs include engineering, construction, horticulture, and travel
and tourism.
Green
Use outdoor learning and environmental volunteering
opportunities to develop young people's employability skills
A range of outdoor learning opportunities have been developed and
funded through small grants and supported volunteering placements
including Clydesdale Community Initiatives, Lets Grow (Skills
Exchange) and Wiston Lodge and Duke of Edinburgh.
Green
Page 46 of 51
63

Page 64

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
A Green Economy (Planet)
Enable a fair transition to a green economy leaving no one behind
Action Measures Comments/ Progress Status
Engage with employers
and key stakeholders to
provide workforce
up-skilling and re-skilling
for a green and circular
economy
Procure a demand led Green Jobs programme to deliver on
fair work for local people
Following the transformational review of employability and associated
funding change it has not been possible to develop a specific green
jobs programme for unemployed people. The employability team will
continue to engage with employers, Business Gateway and Routes to
Work South to respond to vacancies within the green jobs sector. A
proposal has been developed seeking Banks Renewables funding to
deliver a pilot green job focused senior phase programme for SLC
school pupils but is yet to be agreed.
Amber
Provide local businesses with up-skilling and reskilling
opportunities to meet the needs of the transition to a green
and circular economy
Due to Scottish Government funding changes, the Council’s
Employability Team’s upskilling programme has been reviewed to
focus on parents requiring in-work support and training to increase
their earnings from employment, and there has been a reduction in
budget to support re-skilling activity. Re-skilling activity delivered in
2023/24 has been employer needs-led and has focused primarily on
the care sector.
However, ongoing discussions with South Lanarkshire College by our
Business Support team have recognised an emerging skills shortage
in the green economy and a need to adapt and increase training to
meet this demand. Much of the required training is complementary to
the existing courses offered by the College e.g. a heating engineer’s
training can easily be enhanced / extended to include heat pumps, and
the College are looking at including this and other aspects into future
years’ curriculum.
Red
Page 47 of 51
64

Page 65

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
A Green Economy (Planet)
Enable a fair transition to a green economy leaving no one behind
Action Measures Comments/ Progress Status
Consider climate
change impacts within
the council’s workforce
planning
Consider as part of Resource workforce  planning process
the impact of climate change and the need for new or
additional skills or knowledge
An initial review has been undertaken and there has been discussion
on impact of climate change as part of a wider discussion on
workforce planning.
The workforce planning cycle runs 2022 – 2025 so from September
2024 we will begin the review of workforce plans to review and refresh
for the next cycle.
Green
Lead the transition to a circular economy and improve resource efficiency through responsible consumption and production, and buying and sellingof local goods and services
Action Measures Comments/ Progress Status
Review the scope and
scoring of sustainability
requirements in
procurement contracts
Rollout of new tender scoring approach for Sustainable
Procurement Duty and awareness for Resources through the
Procurement Network to improve environmental outcomes
and transition to net-zero emissions for appropriate
procurements by June 2023
A revised minimum sustainability score of 30% of the technical
envelope was agreed by CMT and implemented in 2023/2024. The
score is allocated between Fair Work, Community Benefits and
Climate impact on a variable basis depending on the tendered
commodity.
Green
Progress the
Procurement Flexible
Framework
Sustainability action plan
Use the Scottish Procurement's Sustainable Procurement
Framework to self-assess progress in embedding
sustainability outcomes to improve the consideration of
climate change in procurement activity and outcomes in
appropriate procurement
The Scottish Government's Sustainable Procurement Toolkit is
evaluated every six months to track progress in sustainable outcomes.
During 2023/2024, the Council achieved level 2 (from 5 levels) in
People, Process, Stakeholders and Reporting and level 4 in Strategy.
Progression to level 3 is targeted for 2024/2025
Green
Page 48 of 51
65

Page 66

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
A Green Economy (Planet)
Lead the transition to a circular economy and improve resource efficiency through responsible consumption and production, and buying and sellingof local goods and services
Action Measures Comments/ Progress Status
Provide procurement
support to council
services within contract
specification
development
Identify regulated contracts with sustainability impacts
through the 2023/24 service planning exercise with a view to
improve climate change outcomes, with appropriate input
from Sustainability Team and Resources
The following tenders received a full sustainability assessment in
2023/2024 with sustainable outcomes embedded within the
specification as mandatory requirements or assessed through
technical questions: Household Waste Recycling Centres, Education
Digital Futures, Care at Home and Intensive Family Support services.
Green
Assess the capacity of
the local food and drink
sector to supply food
and drink to the council
Examine the results and recommendations of the Market
Capacity Assessment in 2023 with a view to increase
procurement of local food and drink
Following the presentation of the results of the market capacity
assessment at the Climate Change and Sustainability Committee on
20 September 2023, the following actions were undertaken:
-The Council engaged directly with the 22 businesses
interested in supplying food to the Council
-Chatelherault is getting ready to proceed with Quick Quote
processes to identify local suppliers for meat, fruit and vegetable,
coffee and artisan bread in 2024-2025
-Engagement with the catering team of Glasgow City Council
and North Lanarkshire Council was conducted and key lesson shared
with relevant services
-Through the EAT South Lanarkshire Programme, eight
companies were supported to achieve their growth ambitions
-The Council continues to financially support Lanarkshire
Larder and provide expertise
-"Showcasing the Larder of the Lowlands” event was organised
with support from Scotland Food and Drink in April 2023 with 50 food
and drink businesses attending the event. The event took place again
in April 2024.
Green
Page 49 of 51
66

Page 67

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
A Green Economy (Planet)
Lead the transition to a circular economy and improve resource efficiency through responsible consumption and production, and buying and sellingof local goods and services
Action Measures Comments/ Progress Status
Promote the use of local
and seasonal food and
drink produce to
residents and visitors
Promote local products through campaigns and events and
across business sectors
The Supplier Development Programme hosted a Meet the Buyer event
on 5th June 2024 which attracted 1,598 individuals nationally
representing a 14% increase in attendance from the year before. This
event offered South Lanarkshire businesses opportunity to promote
local products and network with the wider business community.
Green
Introduce the Deposit
Return Scheme in line
with national guidance
Undertake a pilot of Reverse Vending Machine in one high
school to investigate the integration with cashless school
catering system
The ongoing pilot in St Andrews and St Brides is progressing and
outputs have been positive. The reverse vending machine is still in
operation, and it continues to collect cans and bottles. The cans and
bottles are then placed in the mixed recycling waste stream.
Legislation on Deposit Return Scheme does not come into force until
2027.
Green
Consider options for schools in line with the Scottish
Government programme
Legislation on Deposit Return Scheme has been delayed and does not
come into force until 2027. Options for schools will be considered in
line with Scottish Government programme timescales.
Report Later
Reduction on single use
plastic items
Continue to review use of all single use items and consider
and evaluate sustainable alternatives
Single use plastic items have been removed from the Alliance
eCatalogue and are no longer available to order. Work will continue in
raising awareness of need to reduce the use of all single use items.
Green
Page 50 of 51
67

Page 68

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Tuesday 6 August 2024 12:32:10pm
Sustainable Development Strategy Improvement Actions
A Green Economy (Planet)
Support South Lanarkshire’s businesses in the transition to a net-zero economy and helping to ensure they are climate resilient
Action Measures Comments/ Progress Status
Promote the support
that is available to
businesses for good
sustainability outcomes
Publicise internal and external funding opportunities for
businesses for carbon reduction and improved energy
performance
Marketing for funding opportunities has continued throughout the year,
including the council's own business support grants and ExtendPLUS
which enables businesses to obtain a free Carbon Footprint Baseline
report. Publicity has focused on communicating the various
opportunities via the Council's social media channels including
Facebook, X, and LinkedIn. Business Support continue to liaise with
the council's Communications team to ensure effective promotion of
available funding opportunities.
Green
Update website, share information with partners and prepare
and implement marketing plan
The council's business support pages have been updated to share
relevant information. This includes information on funding and support
available. Our business grants specifically support businesses on their
journey to net zero. In the last three months we have also launched the
ExtendPLUS programme in South Lanarkshire. This lets SME’s obtain
a free carbon baseline assessment report, this has been launched via
Social Media posts, website updates and cascading of information to
partner organisations e.g. Business Gateway. This programme will
also be embedded into our business grants application process and all
applicants to our grants will be referred to ExtendPLUS.
Green
Encourage and
influence sustainable
property improvements
in business premises
Commission a consultant to update the review of East
Kilbride industrial properties to understand which properties
meet environmental standards and to improve energy
performance
Consultants Ryden have completed an Employment Land and
Property Analysis for the East Kilbride, Hamilton, Blantyre, Larkhall,
and Clydesdale areas, and are nearing completion of a review for
Cambuslang/Rutherglen and an Executive Summary of all these
reports. The reviews summarise the condition of existing industrial
stock and make a series of recommendations for refurbishment works
including the need for improvements to environmental standards and
energy performance.
Green
Page 51 of 51
68

Page 69

Report
Agenda Item 
Report to: Climate Change and Sustainability Committee
Date of Meeting: 14 August 2024
Report by: Executive Director (Community and Enterprise
Resources)  
Subject: 2024/2025 Action Plan for Sustainable Development
and Climate Change Strategy 
1. Purpose of Report
1.1. The purpose of the report is to:-
[purpose]
 agree the Action Plan for the 2024/2025 year of the Council’s Sustainable
Development and Climate Change Strategy
[1purpose]
2. Recommendation(s)
2.1. The Committee is asked to approve the following recommendation(s):-
[
(1) that the Council Action Plan for 2024/2025 for the implementation of the
Sustainable Development and Climate Change Strategy, as attached at
Appendix 1, be agreed.
s]
3. Background
3.1. The Council’s Sustainable Development and Climate Change Strategy 2022-2027
was approved by the Council on 15 June 2022. The five-year Action Plan for the
implementation of the Strategy was then approved by the Climate Change and
Sustainability Committee on 8 February 2023. The 2024/2025 Action Plan is the
second annual Action Plan under this overarching Plan. 
3.2. The Strategy sets out how the Council aims to develop sustainably and tackle the
climate change emergency over a five-year period, whilst also providing a broad
strategic direction for longer term planning to help deliver on the agreed outcomes and
contribute to achieving a longer-term vision. 
3.3. Delivery of actions within the Strategy provides the main focus for our sustainable
development activity and also enables the Council to fulfil its duties under the Local
Government (Scotland) Act 2003, the Climate Change (Scotland) Act 2009, the
Climate Change (Emissions Reduction Targets) (Scotland) Act 2019 and the Council’s
contribution to the UN’s Sustainable Development Goals. 
3.4. The Action Plan sets out specific actions to be undertaken to deliver objectives under
each theme. 
4. Sustainable Development & Climate Change Strategy Action Plan 2024-25
4.1. The Action Plan for the second year of implementation of the Sustainable
Development and Climate Change Strategy (SDCCS) is available in Appendix 1. The
Action Plan was produced following extensive consultation with all Council Resources
and key services throughout the Council. 
5
69

Page 70

4.2. The Action Plan is split across 13 main priorities that were agreed as part of the
development of the SDCCS. These align with the four key themes of the Council Plan
and each action is mapped to one of the four main themes: 
 People 
 Place and Communities 
 The Natural Environment (Planet) 
 A Green Economy (Planet) 
4.3.  The Action Plan includes two sections: Performance/contextual measures towards the
Strategy’s outcomes, and improvement actions for each of the themes within the
Strategy. 
 performance measures - providing information on how well the Council is
performing against the strategic outcomes in the Strategy
 contextual measures - providing a health check against outcomes
 improvement actions - that will be taken during the term of the action plan to
respond to the challenges ahead and contribute to meeting the outcomes in the
Strategy 
4.4. The Action Plan also includes details of the steps to be taken, lead Council Service,
and expected outcomes. 
5.  Monitoring Framework 
5.1.  Progress of the Action Plan will be reported to the Climate Change and Sustainability
Committee at Quarter 2 and Quarter 4. The IMPROVe system will continue to be used
to gather the progress from services and to produce monitoring reports. 
6. Employee Implications
6.1. All Resources are required to contribute to the implementation of the Sustainable
Development and Climate Change Strategy to ensure that actions and targets are met.
Officers within the Sustainable Development and Climate Change team monitor and
report the Council’s progress, however there are officers from all Resources who have
responsibility for updating and owning the actions noted within the IMPROVe action
plan. 
7. Financial Implications
7.1. The actions detailed in the Sustainable Development and Climate Change Strategy
and associated Action Plan are funded from existing Resource budgets, however the
scale and pace of action needed to meet climate change targets and address the
current climate crisis will require significant capital investment and is likely to require
external funding and investment. The delivery of the Strategy may help leverage for
additional funding and investment; however alternative financing models are also
being explored. 
8. Climate Change, Sustainability and Environmental Implications 
8.1. The Sustainable Development and Climate Change Strategy contributes towards the
Public Sector Climate Change Duties, the Biodiversity Duty and the UN Sustainable
Development Goals. 
8.2. A full Strategic Environmental Assessment was carried out alongside preparation of
the SDCCS.  This has ensured a consistency in approach to addressing the climate
crisis alongside the ecological emergency.  It ensures that the importance of
sustainable development is mainstreamed across the Council and promoted to
70

Page 71

communities and partners incorporating this sustainable approach across all Council
led policies, plans, programmes and strategies should result in continued
environmental benefits for South Lanarkshire and the people who live, work and visit
here. 
9. Other Implications 
9.1. There are no other implications for risk in terms of the information contained within this
report. 
10. Equality Impact Assessment and Consultation Arrangements 
10.1. An Equality Impact Assessment (EIA) was carried out on the Sustainable
Development and Climate Change Strategy and no adverse impacts were identified. 
10.2. The Sustainable Development and Climate Change Strategy and associated Strategic
Environmental Assessment underwent full public consultation for six weeks during
February and March 2022. The results from the consultation and the preceding
community workshops shaped the vision, themes and priorities of the strategy. 
David Booth 
Executive Director (Community and Enterprise Resources) 
25 July 2024 
Link(s) to Council Values/Priorities/Outcomes
Values
 Focused on people and their needs
 Working with and respecting others
 Accountable, effective, efficient and transparent
 Ambitious, self-aware and improving
 Fair, open and sustainable
 Excellent employer 
Priorities
 We will work to put people first and reduce inequality
 We will work towards a sustainable future in sustainable places
 We will work to recover, progress and improve 
Outcomes
 Our children and young people thrive
 Good quality, suitable and sustainable places to live
 Thriving business, fair jobs and vibrant town centres
 Caring, connected, sustainable communities
 People live the healthiest lives possible
 Inspiring learners, transforming learning, strengthening partnerships 
Previous References
 Climate Change and Sustainability Committee report on 31 August 2022 entitled
‘Sustainable Development and Climate Change Strategy 2022-2027’
 Climate Change and Sustainability Committee report on 8 February 2023 entitled
Sustainable Development and Climate Change Strategy 2022 to 2027 Action Plan 
71

Page 72

List of Background Papers
 The Climate Change (Scotland) Act 2009
 Sustainable Development and Climate Change Strategy 2017-2022
 Sustainable Development and Climate Change Strategy 2022-2027
 UN’s Sustainable Development Goals 
Contact for Further Information
If you would like to inspect the background papers or want further information, please contact:
Adam Wallace, Sustainability Adviser
Email: adam.wallace@southlanarkshie.gov.uk 
72

Page 73

Appendix 1 
Performance measures and action plan
This Action Plan is divided into two parts: part (a) sets out our main performance measures against our outcomes; and part (b)
describes the key actions we will take in the coming year to respond to the challenges ahead and improve services and outcomes. 
A. How we will measure our performance 
Priority 1: Contribute to improving health and wellbeing through environmental protection and access to environmental
benefits for all
Measure Baseline year Target Responsibility
Number of Environmental Volunteering days 2022 2,000 days CER Facilities, Waste & Grounds 
Priority 3:  Influence change through improving the understanding of Sustainable Development and the Climate Emergency
across South Lanarkshire
Measure Baseline year Target Responsibility
Number of council employees who have
completed the Learn of Line Climate Change
modules
n/a Increase by 5% from
previous year.
CER Enterprise and Sustainable
Development Service
Encourage schools to achieve eco school
status n/a Increase by 10% from
previous year.  Education Support Services 
73

Page 74

Priority 4:  Improve affordable, sustainable, and accessible transport options
Measure Baseline year Target Responsibility
Number of trips being made by bike 2019 Increase by 1% from
previous year.
CER Roads, Transportation and Fleet
Services
Mode share of school children traveling by
active or public transport (Annual national
‘Hands Up’ Survey)
2022 Increase by 1% from
previous year.
CER Roads, Transportation and Fleet
Services 
Priority 5: Progress a transition to net-zero, energy efficient and climate resilience homes, buildings and infrastructure, and
minimise the unsustainable use of natural resources and regenerate where appropriate
Measure Baseline year Target Responsibility
Carbon emissions in tonnage for South
Lanarkshire: emissions within scope of Local
Authority. (figures from DESNZ with a 2-year
lag)
Annual Reduction on previous year.
(Contextual)
CER Enterprise and Sustainable
Development Service 
Percentage reduction on area-wide emissions
compared to previous year: emissions within
scope of Local Authority (figures from DESNZ
with a 2-year lag)
Annual Reduction on previous year.
(Contextual)
CER Enterprise and Sustainable
Development Service 
Per capita: emission within scope of Local
Authority (figures from DESNZ with a 2-year
lag)
Annual Reduction on previous year.
(Contextual)
CER Enterprise and Sustainable
Development Service
Reduce Scope 1 emissions from Council
carbon footprint (Council operations i.e.
buildings and fossil fuelled fleet)
2024-25
Zero direct emissions by
2038
(National Target adopted by
the Council)
CER Enterprise and Sustainable
Development Service
Reduce Scope 2 and 3 emissions from
Council carbon footprint (electricity, waste
and staff travel)
2024-25
Indirect emissions as close
to zero by as soon as
possible
CER Enterprise and Sustainable
Development Service
74

Page 75

Priority 5: Progress a transition to net-zero, energy efficient and climate resilience homes, buildings and infrastructure, and
minimise the unsustainable use of natural resources and regenerate where appropriate
Measure Baseline year Target Responsibility
Occurrence/reduction of flood events 2022 Reduction on previous year.
(Contextual)
CER Roads, Transportation and Fleet
Services
Secure external funding to help deliver the
Council’s Sustainable Development and
Climate Change priorities
n/a £1m CER Enterprise and Sustainable
Development Service 
Priority 6: Improve the availability and access to quality local outdoor spaces and services
Measure Baseline year Target Responsibility
Percentage of streets found to be acceptable
during Litter Monitoring System Surveys 2021-22 >92.1% CER Grounds Services
Retain Green Flag accreditation at Strathaven
Park, Cambuslang Park and Castlebank Park 2022 3 CER Grounds Services 
Priority 7: Empower communities to take climate action and be more environmentally sustainable
Measure Baseline year Target Responsibility
Increase in the overall number of food
growing participants on council land including
schools, care homes, housing areas and
areas managed by community groups or
third-party organisations
2021
Increase in number of food
growing participants by 5%
compared to previous year.  CER Amenity Services 
75

Page 76

Priority 12: Lead the transition to a circular economy and improve resource efficiency through responsible consumption and
production, and buying and selling of local goods and services
Measure Baseline year Target Responsibility
Percentage of total household waste that is
recycled 2022 50% Waste Services
Percentage of household waste sent to
landfill 2022 <10% Waste Services 
B. What actions we will take in 2024-25
Priority 1: Contribute to improving health and wellbeing through environmental protection and access to environmental
benefits for all
Improvement Actions for 2024-
25
Steps we will take to deliver the actions Responsibility 
Safeguard health by improving and
protecting air quality 
Implement grant funded air quality measures during
2024-2025 to support the Air Quality Action Plan and
continue to maintain and publicise both real time and
historical air quality monitoring results
CER Environmental Health 
Identify and manage contaminated
land within the statutory regulatory
framework
Implement the Contaminated Land Strategy and support
the Planning Authority in relation to development
applications   
CER Environmental Health
Identify relevant climate hazards,
as well as risks and opportunities
which are/will affect South
Lanarkshire
Develop a climate risk register through CCS Steering
Group upon which action planning, decision-making and
monitoring will be built upon with regards to climate
change adaptation and resilience 
CER Enterprise and Sustainable
Development Service 
76

Page 77

Priority 2: Progress climate justice and ensure the transition to net-zero by 2045 does not exacerbate poverty or
inequalities
Improvement Actions for 2024-
25
Steps we will take to deliver the actions Responsibility 
Commission a PHD student from
Glasgow Caledonian University
undertake a study to assess
impact of climate change on South
Lanarkshire communities
Following approval and assessment of project, the PHD
student will progress data-collection stage of project
through undertaking community engagement
CER Enterprise and
Sustainable Development
Service 
Continue to raise awareness internally of the project,
through participating in events, attending meetings and
delivering presentations to both external and internal
stakeholders
Work with partners to promote
available energy advice and
funding support schemes to
minimise fuel costs for households
Partners deliver range of actions to tackle fuel poverty,
including: 
• Advice and support
• Signposting to financial support 
Fuel Poverty Subgroup
Promote weather-related warnings
and advice from national agencies
(e.g. Met Office and SEPA) to
inform individuals and communities
Continue to work with the Council’s Corporate
Communications Team to deliver and/or share regional
and/or national weather warnings where relevant or
appropriate
FCR Council Resilience Team         
Work to enhance individual and community level
preparedness via sharing and utilising resources
available (e.g. Ready Scotland and Adaptation Scotland)
and work to raise awareness of the need for community
and business resilience to climate change risks 
CER Enterprise and Sustainable
Development Service
Continue to raise awareness and
embed sustainability within social
work resources and South
Lanarkshire HSCP
Continue to deliver upskilling and awareness sessions
within social work resources, utilising frameworks such
as the UN Sustainable Development Goals
Social Work Resources 
77

Page 78

Priority 3:  Influence change through improving the understanding of Sustainable Development and the Climate
Emergency across South Lanarkshire
Improvement Actions for 2024-
25
Steps we will take to deliver the actions Responsibility 
Mainstream sustainability and
climate literacy learning and
development across the Council
Re-promote Learn on Line training on sustainability to
elected members and officers by March 2025 
FCR Learning and Development
Team and CER Enterprise and
Sustainable
Develop and implement a robust
communications plan for promoting
and raising awareness of the
sustainability, climate change and
adaptation agenda within the SLC,
national and global context
Implement the agreed 2024/25 communications plan
and prepare articles, including case studies, to
communicate success stories and achievements and
inspire further positive action
CER Enterprise and Sustainable
Development Service
Work with the council’s corporate communications team
to develop a refreshed 2025/26 communications plan,
by April 2025. This will include the promotion of key
campaigns throughout the year, for example, Climate
Week
Further embed sustainable
development and climate change
into the council’s decision-making
process 
Identify potential for development and piloting of an
integrated sustainable development decision-making
tool to be applied to proposed projects and initiatives
presented to the Corporate Management Team and
Committee for approval by the March 2025
CER Enterprise and Sustainable
Development Service
Deliver town centre masterplans,
strategies, and visioning at a local
level
Ensure that all town centre development activity has
sustainability at its core with reference to the
recommendations contained in the Town Centre Net
Zero Strategy, NPF4 and other strategic
recommendations
CER Economic Development
Services
Empower learners to shape and
influence action on climate change
and sustainability through the
youth forum
Continue to support the Youth Forum on Climate
Change and Sustainability to ensure young people’s
voices are represented on appropriate council matters
relating to this subject area
Education Support Services 
78

Page 79

Priority 3:  Influence change through improving the understanding of Sustainable Development and the Climate
Emergency across South Lanarkshire
Improvement Actions for 2024-
25
Steps we will take to deliver the actions Responsibility 
Continue to support the Youth Forum in empowering,
shaping and influencing behaviour change in relation to
climate change and sustainability in schools 
Education Support Services 
Embed sustainability in the
curriculum across all Education
establishments
Considering recent national guidance, enhance our
focus on learning for sustainability across all levels and
curricular subjects
Education CQIS Service
Work to continue to raise awareness and monitor
achievement of learning for sustainability in Early Years
establishments
Education Early Years 
All educational establishments will participate in a
Learning for Sustainability Conference and consider how
to incorporate aspects within educational settings.
e.g. primary schools will aim to deliver one project each
year which has an overt focus on sustainability
Education Early Years
Explore and review options for
carbon reduction from school
estates through understanding
carbon footprint of activities/
estates
Work with Resources from across the Council to
understand and reduce carbon footprint through a set of
co-developed carbon reduction initiatives 
Education Support Services,
Roads CER, HTR, Steering
Group
Work with our communities to
provide programmes and
opportunities to increase
sustainability awareness and
action
Provide access to adult learning opportunities which
raise awareness on climate change
Education Youth, Family and
Community Learning Service
(YFCL) Promote the Environmental and Sustainability Learning
Programmes and Awards delivered across the authority 
79

Page 80

Priority 4:  Improve affordable, sustainable, and accessible transport options
Improvement Actions for 2024-
25
Steps we will take to deliver the actions Responsibility
Encourage active travel by
extending our network of walking
and cycle routes 
Continue the design and implementation of various cycle
routes in towns and villages throughout South
Lanarkshire and consult key stakeholders throughout
the project stages
CER Roads, Transportation and
Fleet Services
Deliver walking and cycling projects / schemes in line
with agreed 2024-25 capital programme       
Deliver new and improved low
carbon vehicle charging
infrastructure
Install and renew charging infrastructure points which
are available for use by the public within South
Lanarkshire
CER Roads, Transportation and
Fleet Services
Continue project design development and
implementation and attract private investment within
South Lanarkshire
Progress towards decarbonising
the fleet of South Lanarkshire
Council vehicles
Implement the Fleet Strategy (2020-2025) Action Plan
including a reduction in transport related emissions,
conversion of fossil fuelled small fleet to full electric and
the trialling of new fuel option for the medium to heavy
fleet
CER Roads, Transportation and
Fleet Services
Encourage greater use of public
transport by working with partners
to improve public transport
infrastructure
Deliver prioritised improvements to bus and rail
infrastructure (e.g. park and ride) in line with available
external funding for 2024-25 
CER Roads, Transportation and
Fleet Services
Ensure climate change mitigation
and adaptation, particularly net
zero area-wide emissions form a
Develop interim framework for consultation with
stakeholders, with final Placemaking Guide prepared by
end of June 2024
CER Planning Services
80

Page 81

Priority 4:  Improve affordable, sustainable, and accessible transport options
Improvement Actions for 2024-
25
Steps we will take to deliver the actions Responsibility
strategic part of the new
Placemaking Guide as per NPF4
Present finalised document to Planning Committee for
approval by December 2024
Consider sustainable travel within
the council’s employee travel plan
Reviewing the current employee travel plan during 2024-
25 to encourage employees to adopt sustainable travel
choices
FCR Personnel Services
Continue to achieve Cycle Friendly
Employer status
Ensure that current cycle friendly status facilities at
principal building (e.g. HQ, South Vennel) are
maintained and promoted through providing facilities
such as storage and showers to encourage and enable
staff to active travel to work.  Promotion of Cycle to
Work Scheme 
FCR Personnel Services 
Priority 5:  Progress a transition to net-zero, energy efficient and climate resilience homes, buildings and infrastructure,
and minimise the unsustainable use of natural resources and regenerate where appropriate
Improvement Actions for 2024-
25
Steps we will take to deliver them  Responsibility 
Reduce South Lanarkshire
Council's carbon footprint
Present 2023/24 interim carbon management report to
CCS Committee in May 2024
CER Enterprise and Sustainable
Development  
Prepare Carbon Future Targets Report reviewing
current strategic Net Zero work being undertaken by the
Council and examples of other local authorities Net Zero
plans/route maps for CCS Committee by March 2025,
and consider the development of a carbon emission
reduction plan
81

Page 82

Priority 5:  Progress a transition to net-zero, energy efficient and climate resilience homes, buildings and infrastructure,
and minimise the unsustainable use of natural resources and regenerate where appropriate
Improvement Actions for 2024-
25
Steps we will take to deliver them  Responsibility 
Present 2023-24 year-end carbon management report to
CCS Committee by December 2024
Develop the Public Bodies Climate
Change Report 
Work with Services to complete the Public Bodies
Climate Change Report 2023-24 for submission to the
Scottish Government by 30 November 2024
CER Enterprise and Sustainable
Development  
Support towns to transition to net
zero
Undertake feasibility planning for the implementation of
the findings of the Town Centre net zero study by March
2025
CER Economic Development
Services
Explore funding and finance
models for net-zero and climate
adaptation projects  
Present findings of research into potential funding and
finance models and examples of good practice
elsewhere to CCS Steering Group by March 2025
CER Enterprise and Sustainable
Development and FCR Finance
(Strategy)
Continue to administer and monitor
the Climate Emergency Fund
Ensure project delivery and outcomes achieved by end
of March 2025. Report on progress and impact of the
funding to the Climate Change and Sustainability
Committee
CER Enterprise and Sustainable
Development Service
Ensure sustainability
considerations are considered
within capital and revenue budget
plans
Continue to embed Sustainability Impact Assessment
Process as part of decision-making for both capital and
revenue proposals
FCR Finance (Strategy) 
Enterprise and Sustainable
Development
Deliver training, awareness and upskilling on
Sustainability Impact Assessment for the revenue and
capital budget process
Integrate climate change and
sustainable development into
finance strategy and reporting
Explore options for better evidencing carbon emissions
associated with future Budget spend in line with Public
Bodies Climate Change Duties
FCR Finance (Strategy)
Enterprise and Sustainable
Development
82

Page 83

Priority 5:  Progress a transition to net-zero, energy efficient and climate resilience homes, buildings and infrastructure,
and minimise the unsustainable use of natural resources and regenerate where appropriate
Improvement Actions for 2024-
25
Steps we will take to deliver them  Responsibility 
Manage flooding priorities and
deliver prioritised actions under the
Local Flood Risk Management
Plan(s)
Deliver prioritised flood protection projects / studies in
line with available capital and revenue funding for 2024 -
2025
CER Roads, Transportation and
Fleet Services
Improve resilience of the road
network through routine
maintenance
Review current road maintenance practices to improve
climate change resilience through use of alternative
methods, materials, and design standards 
CER Roads, Transportation and
Fleet Services
Utilise innovative and new
information technologies for
environmental benefits
Develop business cases for demonstrator Internet of
Things (IoT) projects
FCR IT Services
Continue the migration to Oracle Cloud Fusion system
to support agile working, employee self-service and
engagement
Explore sustainable web design to reduce the council
website's carbon footprint
Implementation of revised Building
Regulations in relation to energy
performance in new buildings and
the adaptation of existing
buildings 
Continue to raise awareness and upskill surveyors on
the Proposed Domestic Building Environmental
Standards (Scotland) Bill, considering changes to
legislation and building regulations, through facilitating
training and awareness sessions
CER Building Standard Services
Increase the overall energy
efficiency of homes and increase
the rates of decarbonisation within
domestic properties across South
Lanarkshire 
Support homeowners and private landlords to improve
the energy efficiency of their properties through
administering and promoting the Energy Company
Obligation Scheme (ECO) and Energy Efficient
Scotland: Area Based Schemes   
HTR Housing Strategy
Support Registered Social Landlord partners to improve
the energy efficiency of their housing stock and take
HTR Housing Strategy
83

Page 84

Priority 5:  Progress a transition to net-zero, energy efficient and climate resilience homes, buildings and infrastructure,
and minimise the unsustainable use of natural resources and regenerate where appropriate
Improvement Actions for 2024-
25
Steps we will take to deliver them  Responsibility 
forward opportunities to work jointly to decarbonise
heating systems
Deliver Housing Investment Programmes to improve the
energy efficiency of the council’s existing homes  
HTR Property
Deliver the council’s affordable housing supply
programme to increase the proportion of new, energy
efficient homes with clean heating systems
HTR Strategy
Prepare for the introduction of the
new Social Housing Net Zero
Standard (SHNZS) 
Develop South Lanarkshire Council’s strategic approach
to meeting the new standard
HTR Property
Develop South Lanarkshire’s Local
Heat and Energy Efficiency
Strategy (LHEES) and Delivery
Plan
Seek committee approval for the LHEES and delivery
plan and work with the relevant lead partners to
implement the agreed delivery plan for 2024/25
HTR Property
Assess the council’s non-domestic
buildings and develop a detailed
action plan on how it will meet the
proposed legislative requirement of
being heated by zero carbon heat
sources by 2038
Based on the findings from the net zero feasibilities
progress the development of an action plan to meet the
national targets for publicly owned buildings by 2038
HTR Property
Utilise the Central Energy
Efficiency Fund (CEEF)
Programme to deliver energy
efficiency improvement projects in
council non-domestic buildings
Implement the agreed CEEF delivery plan for 2024/25 HTR Property
84

Page 85

Priority 5:  Progress a transition to net-zero, energy efficient and climate resilience homes, buildings and infrastructure,
and minimise the unsustainable use of natural resources and regenerate where appropriate
Improvement Actions for 2024-
25
Steps we will take to deliver them  Responsibility 
Support the delivery of Climate
Ready Clyde's (CRC) Adaptation
Strategy
Continue as an active member of the CRC Local
Authority Forum participating in city-region wide
workshops and events, creating connections and
opportunities for development/co-sharing of knowledge
and training by 2025 
CER Enterprise and Sustainable
Development Service   
Contribute to the development and implementation of
local actions that contribute to the wider Glasgow City
Region's (GCR) Adaptation Strategy, where appropriate,
working across Council Resources 
Benchmark the Council against
climate change risk assessments 
Undertake a capability assessment to understand the
Council’s current status and to identify gaps and areas
for improvement by March 2025  
CER Enterprise and Sustainable
Development Service   
Priority 6:  Improve the availability and access to quality local outdoor spaces and services
Improvement Actions for 2024-
25
Steps we will take to deliver them  Responsibility 
Ensure national planning policy set
out in National Planning
Framework 4 in relation to climate
change mitigation and adaptation,
biodiversity and sustainable travel
is embedded in decision making
process for planning applications
and the preparation of the South
Collation of appropriate information and data to inform
the Evidence Report required as new first stage of LDP
preparation by December 2024
CER Planning Service 
85

Page 86

Priority 6:  Improve the availability and access to quality local outdoor spaces and services
Improvement Actions for 2024-
25
Steps we will take to deliver them  Responsibility 
Lanarkshire Local Development
Plan 3
Explore options for data-gathering and analysis to
ensure climate, biodiversity, and sustainability related
topics (such as surface water flooding, flood risk, nature
networks and green infrastructure) to enable data-driven
decision making through tools such as GIS
CER Planning Service
Provide guidance for Development Management
colleagues on how to consider climate change and
sustainability topics when assessing planning
applications, utilising the State of the Environment
Report as evidence base
CER Planning Service
Continue to deliver upskilling, awareness, and training
sessions to Planning Officers and key stakeholders such
as Building Standards on climate change adaptation, net
zero and biodiversity
CER Planning Service
Prepare an Open Space Strategy
in partnership with Glasgow and
Clyde Valley Green Network
Partnership and other council
services
Utilise the technical report provided by the consultant to
inform engagement on open space and establish an
internal working group to develop a strategy
CER Planning Service
Open Space strategy to be presented to the Planning
Committee in 2026, following alignment with the
timescales for the LDP Evidence Report   
Priority 7:  Empower communities to take climate action and be more environmentally sustainable
Improvement Actions for 2024-25 Steps we will take to deliver them Responsibility 
Continue to administer and monitor
the Climate Emergency Community
grant fund 
Allocate £110,000 to projects over financial year
2024/25 
CER Enterprise and Sustainable
Development Service
86

Page 87

Priority 7:  Empower communities to take climate action and be more environmentally sustainable
Improvement Actions for 2024-25 Steps we will take to deliver them Responsibility 
Increase food growing provision
throughout South Lanarkshire 
Provide an opportunity for more people to grow food
through the provision of land for food growing, the
promotion of sustainable practices and supporting third
sector organisations involved in food growing
CER Amenity Services
Support the remediation of vacant
and derelict land that promotes
social and environmental benefits
Support Clyde Gateway Urban Regeneration Company
in a further phase of greening and environmental
improvement works at Cuningar Loop and in further
remediation works in the next phase at Shawfield
Phase 3
CER Economic Development
Services 
Priority 8:  Take action to allow South Lanarkshire to become a zero-waste society
Improvement Actions for 2024-25 Steps we will take to deliver them Responsibility 
Work to support SME’s in accessing
wider business support in relation to
climate change and net-zero,
including the Circular Economy
Establish connections with organisations such as
Business Gateway Lanarkshire, Scottish Enterprise,
Lanarkshire Climate Action Hub to build capacity and
share knowledge in relation to climate change, net zero
and circular economy
CER Economic Development 
Undertake a review of the Climate
Confident South Lanarkshire Pilot,
supporting SMEs in accessing
expertise and advice to reduce their
carbon footprint
Follow up on recommendations as appropriate
following review of Climate Confident South
Lanarkshire pilot
CER Economic Development
Service
Review waste services
(infrastructure and collection
services) in line with delivering
current and future waste legislation
(including the Circular Economy)
Continue to undertake a review of the waste service
through 2024/25 that will determine most efficient
refuse/ recycling collection services and related waste
services infrastructure
CER Waste Services
87

Page 88

Priority 8:  Take action to allow South Lanarkshire to become a zero-waste society
Improvement Actions for 2024-25 Steps we will take to deliver them Responsibility 
Review of recycling bins at flatted
properties in South Lanarkshire
Continue to review existing arrangements at flats
during 2024/25 and work with Corporate
Communications to produce communications
campaign
CER Waste Services
Manage and monitor food waste in
schools
Undertake a review and conduct data analysis of the
pilot “Waste Warrior” initiative prior to exploring further
roll-out options
CER Facilities Services Manager
and Education Support Services 
Priority 9:  Enhance, protect, and respect the outdoors and the natural and historic environment.
Improvement Actions for 2024-25 Steps we will take to deliver them Responsibility 
Make South Lanarkshire a cleaner
place to live, work and visit free of
litter, fly-tipping and dog waste
through progression of actions in the
Litter Strategy (2022-2027)
Continue to progress actions on reducing litter, fly-
tipping and dog waste in South Lanarkshire through
working with stakeholders, partners and community
groups as per the Litter Strategy Action Plan (2022-
2027)
CER Initiatives Officer and
Ground Services Manager 
Priority 10:  Conserve, restore and improve biodiversity, and use nature-based solutions in tackling the climate crisis
Improvement Actions for 2024-25 Steps we will take to deliver them Responsibility
Review council use of herbicide with
a view to reduce the amount used 
Continue to look at alternative methods to control
weeds. Carry out further trials during 2024-25
CER Ground Services 
Measure and increase tree canopy
cover across South Lanarkshire 
Across South Lanarkshire, continue to measure /
assess existing tree canopy cover and tree equity
CER Ground Services 
On Council owned or controlled land, continue to
develop records of the nature, condition and resilience
of tree assets and their canopy cover
88

Page 89

Priority 10:  Conserve, restore and improve biodiversity, and use nature-based solutions in tackling the climate crisis
Improvement Actions for 2024-25 Steps we will take to deliver them Responsibility
On Council owned or controlled land, continue to
identify sites suitable for planting trees to increase
canopy cover and species diversity. Develop a
masterplan with a prioritised delivery plan.  Seek
additional funding for tree and woodland planting
through internal and external sources, including
community groups
Contribute to the delivery of the Clyde Climate Forest,
working with partners to achieve targets outlined in the
Concordat
Increase Biodiversity and invest in
peatlands across South Lanarkshire
Participate in the Clyde Peatlands Project to bring
about a step change in the scale and rate of peatland
restoration across the City Region
CER Ground Services 
Work with key partners including the Clyde grasslands
and Clyde wetlands projects to identify and establish
regional nature networks
CER Ground Services 
Continue to improve key ecosystems within our Local
Nature Reserves and Country Parks utilising the
Nature Restoration Fund
CER Ground Services 
Implement new technologies and
more sustainable cleaning materials
within council facilities
Deliver Aquateck in Corporate Units and further roll out
in the second quarter of 2024 to all High Schools in
South Lanarkshire Council, following successful pilot
exercise in 2023/24
CER Facilities Services
89

Page 90

Priority 11: Enable a fair transition to a green economy leaving no one behind
Improvement Actions for 2024-25 Steps we will take to deliver them Responsibility
Deliver the UK Shared Prosperity
Fund to help ensure a just transition
to net zero
Progress delivery of the new UK Shared Prosperity
Fund. Fund initiatives that support the council,
communities, and businesses transition to net zero
CER Economic Development
Services
Consider climate change impacts on
the council’s workforce in the
workforce plan including need for
green skills
Consider the impact of climate change and the need
for new or additional skills or knowledge as part of the
Resource workforce planning process in 2024/25 
FCR Personnel Services/ CER
Enterprise and Sustainable
Development
Consider and explore options for embedding
sustainability and climate- related behaviours in the
Council’s Behaviours Framework, particularly key roles
FCR Personnel Services/ CER
Enterprise and Sustainable
Development 
Priority 12:  Lead the transition to a circular economy and improve resource efficiency through responsible consumption
and production, and buying and selling of local goods and services
Improvement Actions for 2024-25 Steps we will take to deliver them Responsibility
Review the scope and scoring of
sustainability requirements in
procurement contracts and build
knowledge and awareness of
evaluating sustainability issues
Continue to embed new tender scoring approach, new
sample questions, through training and development of
Resource clients, working to improve knowledge of
sustainability issues in specification and tenders,
including scoring and evaluating tender responses
FCR Central Procurement Team 
Utilise Scottish Government’s
Flexible Framework Assessment
Tool to assess current level of
performance to realise intended
sustainable outcomes
Work to progress towards Level 4 of the Flexible
Framework to show continuous progression in
embedding consideration of climate change and
sustainability in procurement activity and outcomes
FCR Central Procurement Team
Provide procurement support to
council services within contract
specification development
Raising awareness of new sustainable procurement
process which provides support to council services for
non-priority contracts through training and
FCR Central Procurement Team
90

Page 91

Priority 12:  Lead the transition to a circular economy and improve resource efficiency through responsible consumption
and production, and buying and selling of local goods and services
Improvement Actions for 2024-25 Steps we will take to deliver them Responsibility
development, with all priority contracts going through
Scottish Government Sustainability Test
Improve contract management of
sustainability factors through the
Council’s new electronic appraisal
process
Monitor sustainability measures and KPIs in contracts
to ensure sustainability performance and achievement
of intended sustainability outcomes 
FCR Central Procurement Team 
Priority 13:  Support South Lanarkshire’s businesses in the transition to a net-zero economy and helping to ensure they
are climate resilient
Improvement Actions for 2024-25 Steps we will take to deliver them Responsibility
Promote the support that is
available to businesses for good
sustainability outcomes
Publicise funding opportunities and share information
with businesses for carbon reduction and improved
energy performance 
CER Economic Development
Services 
Promote and encourage the use of
bespoke Lanarkshire sustainable
tourism resources, commissioned
via Green Tourism
Engage tourism businesses to uptake more
sustainable practices utilising the resources situated on
the VisitLanarkshire website by March 2025
CER Economic Development
Services
Encourage and influence
sustainable property improvements
in business premises 
Engage consultants to undertake SLC-wide review of
industrial properties and to identify opportunities for
incorporating Net Zero and sustainable technologies
into the delivery of SLC projects by March 2025
CER Economic Development
Services 
91

Page 92

92

Page 93

Report
Agenda Item 
Report to: Climate Change and Sustainability Committee
Date of Meeting: 14 August 2024
Report by: Executive Director (Community and Enterprise
Resources)  
Subject:  Glasgow City Council - Model for Climate Investment 
1. Purpose of Report
1.1. The purpose of the report is to:-
[purpose]
 Provide background information on Glasgow City Council’s recently announced
model for climate investment, and potential implications and opportunities for the
Glasgow City Region including South Lanarkshire
[1purpose]
2. Recommendation(s)
2.1. The Committee is asked to approve the following recommendation(s):-
[recs]
(1) that the content of the report and indicative timescales for engagement with the
Glasgow City Region on the proposal be noted.
[1recs]
3. Background
3.1. On 22 March 2024, Glasgow City Council (GCC) published details of their proposed
model for taking forward the investment required to realise the Council ambitions
around heat decarbonisation and Net Zero. This was developed in response to
recognition of the shortfall in finance for projects to achieve Net Zero and need to
deliver through innovative business models unlocking private sector investment. 
3.2. The model comprises two distinct elements outlined below:
 Delivery Vehicle – to create the conditions that enable the private sector to work
with the Council in bringing forward infrastructure projects that are within the
Council’s control, business case ready and investable.
 Climate Investment Vehicle - for the city/city region that would be controlled
externally. Similar vehicles have been created in other regions of the UK and
consist of private finance consortiums. These often include pension funds, that
commit to funding investable infrastructure projects which demonstrate a return on
investment, often over a longer timeframe. 
3.3. GCC’s proposed model notably will see the creation of a specialist green investment
team, at a cost of £4m over two years, tasked with unlocking a £40billion fund needed
for the city’s ambition to be Net Zero by 2030. 
4. Resourcing and Governance
4.1. Project development in Glasgow has been led by the Council’s Finance, Legal, and
Procurement teams recognising the instrumental roles they will play in establishing the
new model, with strategic direction from the Leader of the Council. Input from other
Council teams has been sought including Sustainability, Built Environment,
6
93

Page 94

Regeneration, and Neighbourhoods. Recognising the scale and scope of the
investment and work required in achieving the Council’s ambitious net zero by 2030
commitment, and understanding the available internal resource, external expertise
has been brought in to augment the available resources. 
4.2. Acknowledging the complexity of the proposal and the need to accelerate net-zero
projects, the proposed model requires the set-up of a specialist team to drive the
project forward. The specialist team will seek to bring together expertise in finance,
sustainability, procurement, and law. The cost of the team is projected as circa £4m
over the 2-year period, split across internal and external resource. It is anticipated that
£1.8m will be required for internal resources and a further £2.2m required for external
expertise in areas such as legal and procurement support. 
4.3. GCC has proposed the establishment of a Political Oversight Group to ensure
appropriate governance, long-term political stability, and to provide advisory capacity.
This will supplement existing sustainability governance, and progress will be reported
to appropriate committees across the Council. 
5. Glasgow City Council Climate Investment Model
5.1. Councils are facing financial pressures and public sector funding alone cannot provide
the investment required to achieve net-zero ambitions. GCC has proposed an
innovative model aimed at attracting investment in the city to fulfil its ambitions. 
5.2. The Delivery Vehicle will allow GCC to take a strategic approach to control and
manage investment in the city. This will involve investigating and implementing viable
and appropriate business models and tools for the city and articulates what the city
wants to achieve, what city assets are in scope for development, and what the
minimum requirements any model must achieve are. 
5.3. GCC is exploring a public private partnership or concession agreement for the Delivery
Vehicle which will build on LHEES strategic direction for decarbonising heat and
improving building efficiency. This could see investment in areas such as low/zero-
carbon heat networks, renewable energy from wind and solar, energy efficiency, and
smart energy systems but can be extended to other energy related projects. 
5.4. The Climate Investment Vehicle would unlock access to capital from the private sector,
as well as long-term patient capital from other sectors, such as Pension Funds. The
fund would help to address the funding gap as well as providing city partners with the
opportunity to progress projects that otherwise may not be delivered. In addition,
further mechanisms for appointing institutional investors will be assessed to allow for
a more streamlined approach to mobilising investment opportunities. 
5.5. Any vehicle created would have a separate governance and decision-making process
from the internal Delivery Model similar to a fund management company. This means
that projects led by city stakeholders outwith the Council could be taken forward and
funded once assessed on their commercial viability. 
5.6. At the end of the two-year funded period it is hoped that the Council will be in a position
to begin investing in identified projects. This will require the establishment of an
appropriate legal structure, identification of a suitable procurement route, and
development of a series of ‘shovel ready’ projects. No capital works are expected to
be undertaken within the two-year funded period. 
94

Page 95

6. Other Notable Models
6.1. GCC undertook a review of climate investment models happening elsewhere and
concluded that the only examples available were in England and internationally. The
two foundational models in England were: 
6.2. Bristol Leap Model 
The Bristol Leap model is a public/private partnership between Bristol City Council and
Ameresco Ltd, a private sector renewable energy and energy efficiency company. The
Leap, with its own governance structure, is Bristol’s approach to decarbonising the city
with a stated ambition of investing £500m over 5 years, whilst mobilising private sector
funding and ensuring that social value is achieved. 
6.3. Greater London Authority (GLA) Model 
The Greater London Authority (GLA) model, the London Efficient and Decentralised
Generation of Energy Fund (The Edge) is an example of a city level funding approach,
creating a fund for organisations to bid in to. A partnership between GLA and
Sustainable Development Capital LLP (SDCL) was developed with a £100m fund
created that can be accessed through the submission of a full business case and
allows organisations across the city region to be supported to become energy efficient. 
7. Glasgow City Region
7.1. The GCC proposal makes reference to the potential for the proposed model to be
extended across the whole Glasgow City Region, potentially including South
Lanarkshire. 
7.2. The Council’s report to Members notes that “the opportunity of extending to
neighbouring Local Authorities should be left open for any decisions that Glasgow
makes to ensure that the benefits are extended beyond the city where appropriate.
Once the approach has been agreed Glasgow will commence discussions with
regional partners to make them aware of our intended next steps.” 
7.3. It is understood that the GCC report will be tabled at a future GCR Cabinet meeting. It
is anticipated that South Lanarkshire Council (SLC) will be approached in due course
to discuss any implications.  SLC should continue to monitor the development of
GCC’s Model for Climate Investment and engage with colleagues across the City
Region on potential for the model to be rolled out to other local authorities. This
process could inform SLC’s own approach to securing investment to realise the
Council’s ambitions around heat decarbonisation and Net Zero. 
8. Employee Implications
8.1. Employee implications arising from this are limited. SLC staff will maintain a working
knowledge and understanding of the project as it develops and will report internally
where appropriate. Should the model be rolled out to the Glasgow City Region, SLC’s
involvement would be more significant and requirement for staff resource would likely
increase. 
8.2. In June 2024, SLC officers met with the project lead at GCC, to discuss the new model
for climate investment. Officers agreed to continue engagement as the project
developed to identify the most appropriate routes for collaboration. A further meeting
is expected to take place in September 2024. 
9. Financial Implications
9.1. There are no immediate financial implications for the Council arising from development
of this model by GCC. If the model is rolled out to the wider Glasgow City Region in
95

Page 96

future, there is potential for the Council to be asked to contribute financially to the
ongoing costs of the team. 
10. Climate Change, Sustainability and Environmental Implications
10.1. This has the potential to address significant barriers to achieving Net Zero that the
Council currently faces. If successfully rolled out across the Glasgow City Region the
model could deliver benefits to the Council in terms of supporting delivery against
Climate Change, Sustainability and Environmental ambitions. 
11. Other Implications
11.1. Failure to meet sustainable development and climate change objectives’ is one of the
top risks for the Council. By exploring all options available to the Council in achieving
Net Zero ambitions this risk may be mitigated. 
12. Equality Impact Assessment and Consultation Arrangements
12.1. No equality impact assessment or consultation required at this time. 
David Booth
Executive Director (Community and Enterprise Resources) 
25 July 2024 
Link(s) to Council Values/Priorities/Outcomes 
Values
 Focused on people and their needs
 Accountable, effective, efficient and transparent
 Ambitious, self-aware and improving
 Fair, open and sustainable 
Priorities
 We will work to put people first and reduce inequality
 We will work towards a sustainable future in sustainable places
 We will work to recover, progress and improve 
Outcomes
 Good quality, suitable and sustainable places to live
 Thriving business, fair jobs and vibrant town centres
 Caring, connected, sustainable communities
 People live the healthiest lives possible 
Previous References
 None 
List of Background Papers
 None 
Contact for Further Information
If you would like to inspect the background papers or want further information, please