Democracy Spraffa

Agenda Document Pack - Climate Change and Sustainability Committee - 11/02/2026

South Lanarkshire Council · 11 February 2026
Back to Climate Change and Sustainability Committee — 11 February 2026 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

Council Offices, Almada Street        
Hamilton, ML3 0AA 
Tuesday, 03 February 2026 
Dear Councillor 
Climate Change and Sustainability Committee 
The Members listed below are requested to attend a meeting of the above Committee to be
held as follows:- 
Date:  Wednesday, 11 February 2026
Time:  10:00
Venue: Hybrid - Committee Room 1, Council Offices, Almada Street, Hamilton,
ML3 0AA 
The business to be considered at the meeting is listed overleaf. 
Yours sincerely 
Paul Manning
Chief Executive 
Members 
Norman Rae (Chair), Kirsten Robb (Depute Chair), Joe Fagan (ex officio), Alex Allison, John
Anderson, Ralph Barker, Maureen Chalmers, Ross Clark, Margaret Cooper, Colin Dewar,
Monique Equi, Ross Gowland, Lynsey Hamilton, Gavin Keatt, Ross Lambie, Richard
Lockhart, Katy Loudon, Julia Marrs, Lesley McDonald, Elaine McDougall, Carol Nugent, Mo
Razzaq, John Ross, Graham Scott, Bert Thomson, Helen Toner, Margaret B Walker, Kirsty
Williams 
Substitutes
Walter Brogan, Robert Brown, Andy Carmichael, Gerry Convery, Poppy Corbett, Andrea
Cowan, Allan Falconer, Gladys Ferguson-Miller, Elise Frame, Geri Gray, Martin Hose,
Richard Nelson, David Watson 
1

Page 2

BUSINESS 
1 Declaration of Interests 
2 Minutes of Previous Meeting
Minutes of the meeting of the Climate Change and Sustainability
Committee held on 12 November 2025 submitted for approval as a correct
record.  (Copy attached) 
5 - 12 
Item(s) for Noting 
3 Just Transition in South Lanarkshire: Preliminary Evidence Report
Presentation by Sage Kuhens, PHD Student 
Monitoring Item(s) 
4 Sustainable Development and Climate Change Strategy Action Plan
2025/2026 Quarter 2 Progress Report
Report dated 21 January 2026 by the Executive Director (Community and
Enterprise Resources).  (Copy attached) 
13 - 94 
Item(s) for Decision 
5 Sustainable Development and Climate Change Strategy 5-Year Action
Plan – Mid Point Review
Report dated 21 January 2026 by the Executive Director (Community and
Enterprise Resources).  (Copy attached) 
95 - 102 
6 Response to the Council’s Climate Emergency Declaration
Report dated 21 January 2026 by the Executive Director (Community and
Enterprise Resources).  (Copy attached) 
103 - 108 
Item(s) for Noting 
7 Scottish Government Consultation on the Climate Change Plan 2026
to 2040
Report dated 21 January 2026 by the Executive Director (Community and
Enterprise Resources).  (Copy attached) 
109 - 132 
Urgent Business 
8 Urgent Business
Any other items of business which the Chair decides are urgent.       
2

Page 3

For further information, please contact:- 
Clerk Name: Susan Somerville
Clerk Telephone: 07557 323097
Clerk Email: susan.somerville@southlanarkshire.gov.uk 
3

Page 4

4

Page 5

CLIMATE CHANGE AND SUSTAINABILITY COMMITTEE 
Minutes of meeting held via Confero and in Committee Room 1, Council Offices, Almada Street,
Hamilton on 12 November 2025 
Chair:
Councillor Norman Rae 
Councillors Present:
Councillor John Anderson, Councillor Ralph Barker, Councillor Maureen Chalmers, Councillor Ross
Clark, Councillor Andrea Cowan (substitute for Councillor Elaine McDougall); Councillor Colin
Dewar, Councillor Monique Equi, Councillor Ross Gowland, Councillor Richard Lockhart, Councillor
Katy Loudon, Councillor Julia Marrs, Councillor Lesley McDonald, Councillor Carol Nugent,
Councillor Mo Razzaq, Councillor Kirsten Robb (Depute), Councillor John Ross, Councillor Graham
Scott, Councillor Kirsty Williams 
Councillors' Apologies:
Councillor Alex Allison, Councillor Margaret Cooper, Councillor Joe Fagan (ex officio), Councillor
Gavin Keatt, Councillor Ross Lambie, Councillor Elaine McDougall, Councillor Bert Thomson,
Councillor Helen Toner, Councillor Margaret B Walker 
Attending:
Community and Enterprise Resources
D Booth, Executive Director; E Berry, Environmental Initiatives Officer; A Brown, Head of Enterprise
and Sustainable Development; K Carr, Head of Facilities, Waste and Grounds Services; G Dodds,
Sustainable Development Officer; S Laird, Engineering Manager; K McCafferty, Carbon
Management Officer; A Wallace, Sustainability Adviser
Education Resources
D Hinshelwood, Interim Head of Education (Support Services and School Estate); G Reilly,
Development Officer
Finance and Corporate Resources
E-A McGonigle, Administration Adviser; N Tollan, Administration Assistant 
Chair’s Opening Remarks
The Chair advised that, in terms of Standing Order No 4(c), he had agreed to accept an item of
urgent business, due to the timescales involved, in relation to a Scottish Government consultation
on the Draft Climate Change Plan and it would be dealt with at the appropriate point in the agenda. 
In response to a question from Councillor Clark, the Head of Enterprise and Sustainable
Development confirmed the intention of how the response to the consultation would be dealt with. 
1 Declaration of Interests 
No interests were declared. 
2 Minutes of Previous Meeting 
The minutes of the meeting of the Climate Change and Sustainability Committee held on 3
September 2025 were submitted for approval as a correct record. 
The Committee decided: that the minutes be approved as a correct record.
2
5

Page 6

3 Just Transition in South Lanarkshire Preliminary Evidence Report 
The Chair advised that as S Kuhens, PHD Student, Glasgow Caledonian University, was not yet
present, this item would be deferred until later on in the agenda.  If, however, she was unable to
make the meeting, then the item would be continued to a future meeting. 
The Committee decided: that the position be noted. 
4 Public Bodies Climate Change Duties – Annual Report 2024/2025 
A report dated 22 October 2025 by the Executive Director (Community and Enterprise
Resources) was submitted on the Council’s annual Public Bodies Climate Change Duties
Compliance report for 2024/2025, as required under the Climate Change (Scotland) Act 2009. 
The report contained the following 6 sections:- 
 organisational profile
 governance, management and strategy
 emissions, targets and projects
 adaptation
 procurement
 validation 
The purpose of each of those areas was summarised in the report. 
Highlights from the 2024/2025 annual report were provided in the Executive Director’s report
and the annual report itself was attached as Appendix 1 to the report.   
In response to a member’s question, the Executive Director (Community and Enterprise
Resources) gave an undertaking to circulate information on how many electric miles were
covered in a year.  He also confirmed that the Local Transport Strategy would be submitted to
Community and Enterprise Resources Committee for approval and to this Committee for noting
in early 2026. 
The Committee decided: that the Council’s annual Public Bodies Climate Change
Duties report for 2024/2025 be approved and submitted to
the Scottish Government. 
5 Strategic Climate Change Risk and Opportunities Assessment 
A report dated 23 October 2025 by the Executive Director (Community and Enterprise
Resources) was submitted:- 
 providing an update on the development of a climate change risk and opportunity
assessment for the Council
 outlining the strategic importance and significance of identifying organisational risk and
opportunities posed by climate change
 outlining the proposed approach to preparation of a report on the impact of climate
induced severe weather as per the Climate Emergency Declaration motion approved at
Council on 1 October 2025 
The Council was legally required to contribute to the objectives of the Scottish National
Adaptation Plan and had to submit annual reports to the Scottish Government detailing how its
activities supported those objectives, as part of the Public Bodies Climate Change Duties
reporting process.
6

Page 7

The Scottish National Adaptation Plan 3 (SNAP3), which had been developed in September
2024, set out the actions that the Scottish Government and partners would take to respond to
the impacts of climate change from 2024 to 2029.  Over the 5 years, SNAP3 committed the
Scottish Government and its partners, including local authorities, to deliver 23 objectives and
over 200 policies and actions across 5 outcomes, as outlined in paragraph 3.4 of the report. 
In early 2025, a benchmarking exercise was undertaken by the Council’s Climate Change and
Sustainability Steering Group and Officers’ Group using Adaptation Scotland’s Capability
Framework.  The Framework was developed to help public bodies to meet their statutory climate
change duties.  One of the tasks identified in enabling the Council to progress action on
adaptation, was the development of a climate change risk and opportunity assessment. 
The climate trends, as outlined in section 4 of the report, were projected to continue and
intensify over the coming decades.  However, the scale of future temperature increases and
climatic changes would depend on how quickly global emissions were reduced and how soon
net zero was reached. 
Those climate trends had clear implications for the Council’s operations, assets and
communities.  At the same time, they might also present opportunities to build resilience,
improve sustainability and enhance service design and delivery.  Understanding how those
trends interacted with the Council’s specific functions, priorities and vulnerabilities was essential
to identifying both risks and opportunities, and to ensuring that climate adaptation was
integrated into strategic planning and long-term decision-making. 
To progress the Council’s strategic climate change risk and opportunity assessment, the
Adaptation Scotland guidance, ‘Connecting Climate Risk and Strategic Priorities’, was being
adopted as the primary framework.  The guidance set out a clear, structured 6-stage process for
assessing climate risks at a strategic level, as outlined at paragraph 8.2 of the report.  An
overview of the stages involved in the assessment process was outlined in Appendix 2 to the
report. 
Stage 1 of the assessment process had now been completed.  During this stage, appropriate
governance arrangements were established, and key stakeholders were identified to support the
development and delivery of the assessment. 
Actions outlined within Stage 2 of the process were being progressed, focusing on scoping the
assessment prior to evidence gathering.  It was proposed that the completed risk and
opportunity assessment would inform a future report on the increasing impact of climate induced
severe weather on the Council’s services and budgets, including what plans there were to
mitigate those impacts and costs. 
Officers responded to members’ question on various aspects of the report. 
It was noted that there was a typographical error in paragraph 9.4 of the report in that the South
Lanarkshire Climate Emergency Declaration motion had been approved at a meeting of South
Lanarkshire Council rather than at this Committee. 
The Committee decided: 
(1) that the importance and significance of identifying organisational climate risks and
opportunities be noted; 
(2) that the Council’s progress towards identifying organisational climate risks and
opportunities in the form of a strategic climate change risk and opportunity assessment be
noted; and
7

Page 8

(3) that the proposed approach to preparation of a report on the impact of climate induced
severe weather be approved. 
[Reference:  Minutes of South Lanarkshire Council of 1 October 2025 (Paragraph 8)] 
Councillor Williams left the meeting during this item of business 
6 Carbon Management Year End Report 2024/2025 
A report dated 22 October 2025 by the Executive Director (Community and Enterprise
Resources) was submitted providing details of carbon emissions from the Council’s operations
in 2024/2025. 
In November 2024, the Scottish Parliament passed the Climate Change (Emissions Reduction
Targets) (Scotland) Act 2024 which modified the greenhouse gas emissions reduction targets
within previous climate change legislation. 
The Council’s carbon emissions for 2024/2025, not including the new emissions sources
detailed at paragraph 3.8 of the report, showed a 70.65% reduction since the baseline year of
2005/2006.  Compared to 2023/2024, the Council’s carbon emissions had reduced by 7% in
2024/2025. 
The Council’s carbon emissions for 2024/2025, including the new emissions sources, showed a
70% reduction from the baseline year of 20005/2006 and a reduction of 5% compared to the
previous year. 
Table 4, at paragraph 4.5.1, detailed the Scope 1 emissions for 2024/2025.  Scope 1 emissions
accounted for 65% of the Council’s operational carbon emissions.  A comparison from
2023/2024 to 2024/2025 showed that:- 
 gas consumption had decreased by 3.6%, resulting in an emissions reduction of 3.5%
 emissions from oil for heating had increased by 7.48%, however, there had been an
overall decrease of 85.28% when compared to the baseline year of 2005
 an emissions reduction of 0.65% had been achieved from fleet vehicles 
Table 5, at paragraph 4.6.1, detailed the Scope 2 emissions for 2024/2025.  Scope 2 emissions
accounted for 25% of the Council’s operational emissions.  This category of emissions had
reduced by 77% since the baseline year of 2005/2006.  Compared to 2023/2024, Scope 2
emissions had reduced by 2.61%.  A comparison from 2023/2024 to 2024/2025 showed that:- 
 electricity consumption in Council buildings had decreased by 3.65%, resulting in a
decrease in emissions of 3.53%
 there had been an emissions reduction of 12% from electric vehicle usage
 electricity consumption from street lighting had increased slightly by 3.4%, resulting in an
emission increase of 3.39% 
Table 6, at paragraph 4.7.1, detailed the Scope 3 emissions for 2024/2025.  Scope 3 emissions
accounted for 10% of the Council’s operational emissions at present, however, this figure was
expected to rise as additional emissions categories were added, in line with forthcoming Scottish
Government guidance.  Scope 3 emissions had reduced by 92.44% since the baseline year
2005/2006.  Compared to 2023/2024, Scope 3 emissions had reduced by 23.35%.  A
comparison from 2023/2024 to 2024/2025 showed that:- 
 carbon emissions associated with household waste had reduced significantly by 39.39%
 there had been an emissions decrease of 4.97% from staff business travel
8

Page 9

At its meeting on 19 March 2025, this Committee had agreed to the development of a net zero
route map for Scope 1 emissions.  The route map would take cognisance of other statutory
strategies and highlight the significant financial investment required to achieve net zero,
detailing costs and potential sources of finance.  The results of the work to develop the 10-year
Estate Strategy and Delivery Plan, as well as a review of the Fleet Strategy, would inform the
development of the net zero route map. 
Officers responded to members’ questions on various aspects of the report. 
The Committee decided: 
(1) that the Council’s operational carbon emissions for the year 2024/2025 be noted; and 
(2) that the approach in 2025/2026 for operational carbon emissions be noted. 
[Reference:  Minutes of 19 March 2025 (Paragraph 4) and 9 October 2024 (Paragraph 5)] 
Councillor Nugent joined the meeting during this item of business 
7 South Lanarkshire Council – Climate Week 2025 
A report dated 17 October 2025 by the Executive Director (Community and Enterprise
Resources) was submitted providing an update on the work undertaken by the Council in
support of Scotland’s Climate Week 2025. 
Scotland’s Climate Week was an annual event that raised awareness about the global climate
emergency and promoted individual and collective action.  This year it took place between 29
September and 5 October 2025. 
Climate Week 2025 coincided with several other campaigns, such as Second-hand September,
Recycle Week, Lanarkshire Climate Festival and World Car Free Day.  The Council delivered a
month-long programme of climate communications and events throughout September, as
outlined in Section 5 of the report. 
The Sustainable Development Officer responded to a member’s question in terms of
engagement and accessing analytics on feedback from social media posts and View articles. 
The Committee decided: that the update on climate action initiatives during
Scotland’s Climate Week 2025 be noted. 
Councillor Williams re-joined the meeting during this item of business 
8 Education Resources’ Sustainability Report 
A report dated 23 October 2025 by the Executive Director (Education Resources) was submitted
providing an update on activities ongoing within Education Resources since last reported in
February 2024. 
Education Resources had expanded school-based eco-initiatives, increased access to
professional learning on sustainability for educators and the continued development of learner-
led sustainability projects. 
Details of key activities and achievements by the Youth Forum in 2024/2025 were outlined in
paragraph 4.7 of the report.
9

Page 10

The Conference of Schools (COS) had become an established annual event, forming a key part
of the Council’s approach to climate education and pupil engagement.  Planning was underway
for COS4, which was scheduled to take place in March 2026. 
A monthly Learning for Sustainability and STEM newsletter continued to play an important role
in supporting staff and schools across South Lanarkshire and was a key tool in ensuring
consistent messaging, celebrating achievements, and supporting the continued integration of
sustainability and STEM education across the curriculum. 
A range of projects recently undertaken was provided at paragraph 5.3 of the report, with
Section 6 of the report outlining progress and further plans for 2025/2026. 
In response to members’ questions, the Executive Director (Community and Enterprise
Resources) advised that he would:- 
 liaise with colleagues in Education Resources in terms of the Youth Forum attending a
future meeting
 investigate what level of data might be extracted on the Beat the Street initiative 
In response to a member’s question in respect of promoting the forestry and outdoor learning
award, the Interim Head of Education (Support Services and School Estate) advised that he
would contact the Quality Improvement Team to establish the progress made and how this
would continue in the future. 
The Committee decided: that the range of activities across Education Resources in
relation to sustainability and the continued steps for further
activity be noted. 
[Reference:  Minutes of 28 February 2024 (Paragraph 7)] 
9 Litter Strategy - Update 
A report dated 23 October 2025 by the Executive Director (Community and Enterprise
Resources) was submitted providing an update on the work undertaken to date on the Litter
Strategy 2022 to 2027 and the associated action plan. 
Over the past year, there had been positive engagement with diverse community groups and
individuals.  Through the Community Clean Up webform, groups and residents had been
supported in conducting litter picks and clean-ups.  Grounds Services had also actively engaged
with the Climate Change and Sustainability Youth Forum by attending meetings, providing
information and assisting with initiatives run in schools. 
The litter bin mapping and inventory undertaken for the Litter Strategy had been invaluable for
understanding the current locations and capacities of existing bin infrastructure.  This had
enabled informed decisions about new bin requests.  Going forward, litter bins with hoods were
being prioritised to prevent litter escape. 
The Council had successfully obtained Chewing Gum Task Force grant funding for the last 4
years.  This year, for Year 4 of the grant funding, £27,058 had been received and work
associated with this would continue. 
A copy of the Litter Strategy Action Plan was attached as Appendix 1 to the report.  Some
highlights of achievements over the year were detailed at paragraph 4.5 of the report.
10

Page 11

To support delivery of the Litter Strategy and help measure success, the Steering Group had
previously set out a suite of baseline data that would be updated and monitored, and this was
included in Appendix 2 to the report. 
In 2024/2025, the LEAMS (Local Environmental Audit and Management System) data showed
that the figures for South Lanarkshire had increased and the Council’s performance now
exceeded both the Benchmarking Club 3 and national average. 
Information was provided on:- 
 pilot initiatives in Cambuslang to address some issues caused by commercial and
household waste as well as infrastructure, and within Housing Services to address fly
tipping and improper waste disposal around housing properties
 the fly tipping reporting process
 fly tipping investment
 the communications plan 
Officers responded to members’ questions on various aspects of the report. 
The Committee decided: 
(1) that progress and updates on the Litter Strategy Action Plan be noted; and 
(2) that the pilot project updates be noted. 
[Reference:  Minutes of 18 December 2024 (Paragraph 5)] 
10 Item of Urgent Business – Scottish Government Consultation on the Draft Climate
Change Plan 
A Wallace, Sustainability Adviser advised that the Scottish Government had launched a public
consultation on the Draft Climate Change Plan.  This Plan outlined the policies and proposals
required for Scotland to achieve its goal of ending its contribution to global greenhouse gas
emissions.  The consultation was open for responses until 29 January 2026. 
It was proposed that officers circulate details of the consultation, together with the associated
document, to members of the Committee to enable them to provide comments by 8 January
2026.  The draft submission, on behalf of the Council, would then be circulated to provide
members of the Committee with a further opportunity to comment.  The final copy of the
submission would be submitted to the next meeting of this Committee for noting. 
In response to a member’s comments that, to allow for proper scrutiny of the consultation, it
might be best to submit the proposed response to either the Executive Committee or Community
and Enterprise Resources Committee in December 2025 for approval, the Executive Director
(Community and Enterprise Resources) advised that, owing to the volume of work involved, the
timelines for that would prove difficult.  He gave an undertaking to explore the option of taking
the consultation response to an earlier committee, however, would also contact the Scottish
Government to establish whether a late submission would be acceptable to allow for committee
approval. 
The Committee decided: to note the position.
11

Page 12

Chair’s Closing Remarks
The Chair advised that:- 
 the presentation by S Kuhen on Just Transition would be continued to a future meeting of the
Committee
 this would be the last Committee meeting that D Booth, Executive Director (Community and
Enterprise Resources), would be attending prior to his retirement from the Council in February
2026.  The Chair, on behalf of the Committee, thanked David for his many years of public
service and wished him well for the future.  Councillor Ross, on behalf of the SNP Group,
echoed the Chair’s sentiments.  Mr Booth responded in suitable terms. 
12

Page 13

Report
Agenda Item 
Report to: Climate Change and Sustainability Committee
Date of Meeting: 11 February 2026
Report by: Executive Director (Community and Enterprise
Resources)  
Subject: Sustainable Development and Climate Change Strategy
Action Plan 2025/2026: Quarter 2 Progress Report 
1. Purpose of Report
1.1. The purpose of the report is to: -
[
 present the Sustainable Development and Climate Change Strategy Quarter 2
Progress Report 2025/2026, for the period 1 April 2025 to 30 September 2025. 
2. Recommendations
2.1. The Committee is asked to approve the following recommendations: - 
(1) the Sustainable Development and Climate Change Strategy Action Plan Quarter
2 Progress Report 2025/2026 be noted. 
3. Background
3.1. The Sustainable Development and Climate Change Strategy 2022 to 2027 was
approved by the Council on 15 June 2022. The Strategy sets out how the Council
aims to develop sustainably and tackle the climate change emergency over a five-
year period, whilst also providing a broad strategic direction for longer term planning
to help deliver on the agreed outcomes and contribute to achieving a longer-term
vision. 
3.2. The Action Plan for 2025/2026 was approved at the Climate Change and
Sustainability Committee in March 2025. 
3.3. Progress against these actions is monitored using IMPROVe and reported to the
Climate Change and Sustainability Committee at Quarter 2 and Quarter 4. 
3.4. Delivery of actions within these strategies provides the main focus for the sustainable
development activity and also enables the Council to fulfil its duties under the Local
Government (Scotland) Act 2003, the Climate Change (Scotland) Act 2009 and the
Council’s contribution to the UN’s Sustainable Development Goals. 
3.5.  Progress on all objectives, actions and measures as at Quarter 2, 1 April 2025 to 30
September 2025, is set out in Appendix 1. All data and comments included in the
appendix are correct as of 30 September 2025. 
4. Sustainable Development Strategy 2022-2027 Quarter 2 Update
4.1. The Action Plan progress report comes in two parts; the first part contains
performance/contextual measures towards the Strategy’s outcomes, and the second
part contains improvement actions for each of the themes within the Strategy.
4
13

Page 14

4.2. Part One - Performance Measures 
The overall summary of performance measures at the end of Quarter 2 is as follows: 
Total number of performance/ contextual measures 18
Status – Green
The timescale or target has been met as per
expectations.  8 (44.5%)
Status – Amber
There has been minor slippage against timescale
or minor shortfall against target.  1 (5.6%)
Status - Red
There has been major slippage against timescale
or major shortfall against target.  0
Reportable at a
later stage
For some measures, the statistics are not yet
available to allow us to report whether the target
has been reached or not. These will be reported
when available
5 (27.8%)
Contextual
The contextual measures provide a health check
for South Lanarkshire. The council’s activities
contribute to these measures, however there are
many factors that could influence these measures
which are not fully within the council’s scope. 
4 (22.2%) 
Areas for Improvement
4.3.  There are no measures marked as ‘red’ (major slippage). There is one ‘amber’ action
where minor slippage was reported at Quarter 2. The amber categorisation relates to
the percentage of total household waste that is recycled which has, to date, fallen
short of the target but is continuing to be monitored. Further detail on this measure is
included within Appendix 1. 
Part Two – Improvement Actions
4.4. The overall summary of improvement actions at the end of Quarter 2 is as follows: 
Total number of improvement actions 96
Status - Blue Action Complete 6 (6.3%)
Status – Green The timescale or target has been met as per
expectations 80 (83.3%)
Status – Amber There has been minor slippage against timescale
or minor shortfall against target 8 (8.3%)
Status - Red There has been major slippage against timescale
or major shortfall against target 0 (0%)
Reportable at a
later stage
For some measures, the statistics are not yet
available to allow us to report whether the target
has been reached or not. These will be reported
when available
2 (2.1%) 
Areas for Improvement
4.5. There are no measures marked as ‘red’ (major slippage). There are eight ‘amber’
actions where minor slippage was reported at Quarter 2. Seven of these action
categorisations relates to revision of timescales for the delivery of associated plans,
guides, and strategies. One of the amber measures relates to the withdrawal of the
Nature Restoration Fund by the Scottish Government, which will in turn impact the
14

Page 15

scale and pace of biodiversity related work within South Lanarkshire. Further detail
on these delays, and associated management actions, are included within Appendix
1. 
Key Highlights
4.6. Progress on all objectives, actions and measures is set out in Appendix 1. Some of
the key achievements for Q2, are noted below: 
 During the month of September 2025, a host of communications were delivered
in recognition of some key national and local campaigns such as Recycle Week,
Secondhand September, Lanarkshire Climate Festival, Beat the Street and Car
Free Day.
 Officers from across Council services have attended ‘Youth Forum on Climate
Change and Sustainability’ meetings to discuss their work and its impacts on
sustainability. Facilities Services met with students to explore sustainable school
meal options and held a tasting session to help shape new menus. 
 Rutherglen Universal Connections “Square Roots” gardening project is
supporting adult learners to learn about sustainability activity whilst improving
confidence in their numeracy.
 The redesigned John Muir Award has now been released which in addition to
fresh content and new resources, has a new level “Wild Places Guardian” which
will encourage people to connect with, enjoy and care for wild places. Education
establishments have been alerted to the new award and are exploring use within
their curriculum programmes.
 Waste Services worked with Digital and PR to launch a successful composter
pilot scheme early in August 2025. The service procured, promoted and
delivered 360 composters in the first phase. The second phase was launched to
coincide with Recycle Week and Climate Week 2025.
 The Council’s carbon emissions totalled 46,730 tCO2e in 2024-25. This shows a
70% reduction from the baseline year of 2005-06 and a reduction of 5%
compared to 2023-24.
 A Sustainability Impact Assessment (SIA) has been completed to assess the
likely environmental impacts of the design proposals contained within the
Country Parks Masterplan. 
 Over £6.5m in external funding secured, including £5.49m shared ground source
heat pump system in six multi-storey blocks in East Kilbride, £0.05m for detailed
feasibility studies for district heating at Almada Street, and £0.015m for the ‘Walk
n’ Roll’ programme encouraging young people to walk, wheel and cycle.
 Only 0.8% of household waste has been sent to landfill, significantly below the
upper limit target of 5%.
 Installation of loft and wall cavity insulation undertaken to 106 Council and owner
occupier properties.
 Three projects have delivered external wall insulation to properties in Forth,
Larkhall, Hamilton, with cavity wall insulation also delivered in 55 properties in
Forth and work ongoing at 60 properties in Hamilton. 
5.  Employee Implications 
5.1. All Resources are required to contribute to the implementation of the Sustainable
Development and Climate Change Strategy to ensure that actions and targets are
met. Consequently, officers from these Resources have responsibility for updating
and owning the actions noted within the IMPROVe action plan. Officers within the
Sustainable Development and Climate Change team monitor and report the
Council’s progress in implementing the overall action plan.
15

Page 16

6.  Financial Implications 
6.1.  The actions detailed in the Sustainable Development and Climate Change Strategy
and associated action plan are funded from existing Resource budgets, however the
scale and pace of action needed to meet climate change targets and address the
current climate crisis will require significant capital investment and is likely to require
external funding and investment. The delivery of the Strategy may help leverage
additional funding and investment; however alternative financing models are also
being explored. 
7.  Climate Change, Sustainability and Environmental Implications
7.1.  The Sustainable Development and Climate Change (SDCC) Strategy contributes
towards the Public Sector Climate Change Duties, the Biodiversity Duty, and the UN
Sustainable Development Goals. 
7.2. The Public Sector Climate Change Duties require that a public body must, in
exercising its functions, act in the way best calculated to contribute to the delivery of
emissions reduction targets; help deliver any statutory climate change adaptation
programme; and in a way that it considers is most sustainable. The 2025/26 Action
Plan includes initiatives such as reducing carbon emissions from Council operations,
encouraging active travel through Beat the Street and the employee Cycle to Work
Scheme, as well as encouraging completion of Climate Emergency training modules.
These are all efforts that align with the Council’s obligation to act sustainably and
mitigate climate implications of operations. 
7.3. Under the Nature Conservation (Scotland) Act 2004, all public bodies in Scotland
have a duty to further the conservation of biodiversity when carrying out their
responsibilities. The 2025/26 Action Plan emphasises the Council’s commitment to
protecting and improving biodiversity. This is evidenced through the work being
progressed in conjunction with partners (Clyde Grasslands, Clyde Wetlands and
Clyde Climate Forest) to establish Nature Networks which are now evidenced in
Nature Network maps. These are providing important evidence in the progress of the
Local Development Plan 3.     
7.4. The 2025/26 Sustainable Development and Climate Change Action Plan support
multiple UN Sustainable Development Goals. Some examples of these are: 
 Goal 7 Affordable and clean energy – The Housing Investment Programme
allocated £9.779 million towards energy efficiency improvements in 2025/26,
furthering efforts to reduce carbon emissions from Council owned housing stock.
 Goal 13 Climate Action – September 2025 marked a month of climate
communications in recognition of many climate related national and local
campaigns such as the Lanarkshire Climate Hub Climate Festival, Climate
Week, Recycle Week, Secondhand September and Car Free Day. Social media
posts, VIEW articles, events and intranet posts were delivered among many
other initiatives.
 Goal 15 Life on Land – In partnership with the Clyde Climate Forest (CCF) and
with tools such as Tree Equity Score UK, the council continues to measure and
assess tree canopy cover and tree equity. The current overall tree canopy cover
(TCC) is approximately 17% with a strategic target of 21% by 2032. 
8.  Other Implications 
8.1.  The Sustainable Development and Climate Change Strategy has been assessed as
part of the Council’s risk management arrangements and relevant issues have been
added to the Resource Risk Registers.
16

Page 17

9.  Integrated Impact Assessment and Consultation Requirements
9.1.  An Equality Impact Assessment and Fairer Scotland Duty impact assessment have
been carried out on the Sustainable Development and Climate Change Strategy. 
9.2.  Public and stakeholder consultation was undertaken during the development of the
Sustainable Development and Climate Change Strategy. 
Kevin Carr
Executive Director (Community and Enterprise Resources) 
21 January 2026 
Link(s) to Council Values/Priorities/Outcomes
 Focused on people and their needs.
 Working with and respecting others
 Accountable, effective, efficient and transparent
 Ambitious, self-aware and improving
 Fair, open and sustainable
 We will work to put people first and reduce inequality.
 We will work towards a sustainable future in sustainable places.
 We will work to recover, progress and improve.
 Our children and young people thrive.
 Good quality, suitable and sustainable places to live.
 Thriving business, fair jobs and vibrant town centres
 Caring, connected, sustainable communities.
 People live the healthiest lives possible.
 Inspiring learners, transforming learning, strengthening partnerships 
Previous References
 South Lanarkshire Council report on 15 June 2022 entitled ‘Sustainable Development
and Climate Change Strategy 2022-2027’
 Climate Change and Sustainability Committee report on 31 August 2022 entitled
‘Sustainable Development and Climate Change Strategy 2022-2027’
 South Lanarkshire Council report on 14 August 2024 entitled ‘2024/25 Action Plan for
Sustainable Development and Climate Change Strategy’ 
List of Background Papers
 The Climate Change (Scotland) Act 2009
 Sustainable Development and Climate Change Strategy 2022-2027
 UN’s Sustainable Development Goals 
Contact for Further Information
If you would like to inspect the background papers or want further information, please
contact: - 
Gemma Dodds, Sustainable Development Officer
Email: Gemma.dodds@southlanarkshire.gov.uk
17

Page 18

18

Page 19

IMPROVe - SLC Performance Management System                                                                                   Report printed on 2 Feb 11:30
Quarter 2 : 2025/26 - April to September
Appendix 1
Performance Report
4
19

Page 20

IMPROVe - SLC Performance Management System                                                                                   Report printed on 2 Feb 11:30
Page 2 of 4
20

Page 21

Intervention Type
Definition:
Mitigation - Reducing greenhouse gas emissions that contribute to climate change
Adaptation - Reducing or managing impacts of climate change
Sustainable Development - Development that meets the needs of the present
without compromising the ability of future generations to meet their own needs
Page 3 of 4
21

Page 22

IMPROVe - SLC Performance Management System                                                                                   Report printed on 2 Feb 11:3022

Page 23

IMPROVe - SLC Performance Management System                                                                                   Report printed on 2 Feb 11:30
Summary (Section 1) - number of Quantitative Measures green, amber and red under each
Sustainable Development Theme
Sustainable Development Theme Green Amber Red Report later /
Contextual
Total
People 3 0 0 0 3
Place and Communities 4 0 0 8 12
Natural Environment (Planet) 0 0 0 1 1
A Green Economy (Planet) 1 1 0 0 2
Total 8 1 0 9 18
Summary (Section 2) - number of Improvement Actions complete, green, amber and red
under each Sustainable Development Theme
Sustainable Development Theme Complete Green Amber Red Report
later
Total
People 0 27 1 0 1 29
Place and Communities 3 27 1 0 1 32
Natural Environment (Planet) 0 14 6 0 0 20
A Green Economy (Planet) 3 12 0 0 0 15
Total 6 80 8 0 2 96
Page 1 of 71
23

Page 24

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Performance Measures
Sustainable Development and Climate Change
Strategy - Section 1: Performance Measures
The following section provides performance and contextual measures for each of the themes in the strategy. 
The performance measures highlights progress towards each of the outcomes.  The contextual measures
provide a health check; however, these are not fully in the scope of influence for the Council.
Page 2 of 71
24

Page 25

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Performance Measures
People
Contribute to improving health and wellbeing through environmental protection and access to environmental benefits for all
Performance Indicators Comments/ Progress Status 2023/24 2024/252022/23Target To Date
-------- Last 3 Years --------------------- This Year -------------
Intervention type
Number of Environmental Volunteering days Sustainable
Development
During the period from April to September 2025, there
were 851 volunteers days carried out across South
Lanarkshire.
Green 2,000 851 5,212 1,890 1,662
Page 3 of 71
25

Page 26

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Performance Measures
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Performance Measures
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Performance Measures
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Performance Measures
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Performance Measures
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Performance Measures
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Performance Measures
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Performance Measures
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Performance Measures
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Performance Measures
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Performance Measures
People
Influence change through improving the understanding of Sustainable Development and the Climate Emergency across South Lanarkshire
Performance Indicators Comments/ Progress Status 2023/24 2024/252022/23Target To Date
-------- Last 3 Years --------------------- This Year -------------
Intervention type
Number of Council employees who have
completed the Oracle Fusion Climate
Change modules
Sustainable
Development
The number of employees who have completed
Oracle Fusion Climate Change modules during
2025-26 so far has increased by 67 to 1,736. This is
good progress towards achieving the target increase
of 5% over the year.
Climate Change training modules are promoted
throughout the year by officers via intranet posts and
employee circulars as well as during appropriate
campaigns.
Green 1,752 1,736 1,354 1,416 1,669
Encourage schools to achieve Eco-Schools
status
Sustainable
Development
South Lanarkshire Council continues to make strong
progress in promoting Eco-Schools. Currently, 64
schools (35%) are active in the programme, achieving
the target for 2025-26 and exceeding the Scottish
average of 29%.
Burnside Primary School earned a national
commendation for its Eco-Schools work, and
celebration visits were held at several schools to
showcase achievements.
Pupil and teacher engagement remains high through
Climate Ready Classrooms, Live Lessons, and
Eco-Schools training, while participation in related
programmes such as LEAF, Pocket Garden, and
Young Reporters for the Environment demonstrates
broad environmental involvement.
Overall, South Lanarkshire is performing well, with
increasing participation, national recognition, and
strong collaboration across schools to achieve and
maintain Eco-Schools status.
Green 64 64 35 45 58
Page 4 of 71
26

Page 27

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Performance Measures
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Performance Measures
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Performance Measures
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Performance Measures
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Performance Measures
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Performance Measures
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Performance Measures
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Performance Measures
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Performance Measures
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Performance Measures
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Performance Measures
Place and Communities
Improve affordable, sustainable, and accessible transport options
Performance Indicators Comments/ Progress Status 2023/24 2024/252022/23Target To Date
-------- Last 3 Years --------------------- This Year -------------
Intervention type
Number of trips being made by bike Mitigation At quarter two, monitoring showed a total of 123,605
cycling trips across all 47 monitoring sites.
Contextual ------ 123,605 ------ ------ 55,290
Mode share of school children travelling by
active or public transport (Annual national
'Hands Up' Survey)
Mitigation Official figures issued by Transport Scotland for 2024
were issued in June 2025. There were 58.6% of
children travelling to school by active or public
transport during 2024 (excluding nursery). 37.2%
walked, 2.7% cycled, 2.0% by scooter / skate and
16.7% by bus.
This is a slight decrease of 1.5% when compared to
2023 data which was 60.1% (37.7% walked, 3.5%
cycled, 2.7% scooter / skate and 16.2% by bus).
Nationally in 2023 and 2024 these figures were
63.7% and 65.7% showing a 2% increase.
Figures reported here are taken from Sustrans annual
‘Hands Up’ Scotland Survey published in May 2025
using data from 2024.
Report Later 59.6% ------ 59.9% 60.1% 58.6%
Page 5 of 71
27

Page 28

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Performance Measures
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Performance Measures
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Performance Measures
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Performance Measures
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Performance Measures
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Performance Measures
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Performance Measures
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Performance Measures
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Performance Measures
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Performance Measures
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Performance Measures
Place and Communities
Progress a transition to net-zero, energy efficient and climate resilient homes, buildings and infrastructure, and minimise the unsustainable use of natural
resources and regenerate where appropriate
Performance Indicators Comments/ Progress Status 2023/24 2024/252022/23Target To Date
-------- Last 3 Years --------------------- This Year -------------
Intervention type
Carbon emissions in tonnage for South
Lanarkshire: emissions within scope of Local
Authority (figures from DESNZ with a 2-year
lag)
Mitigation Annual data is published by the Department for
Energy Security and Net Zero. It has a two-year lag;
therefore this figure (1,005.6 kilotonne CO2e) relates
to the area wide carbon emissions for 2023, which is
the most recent data available.
Contextual ------ ------ 1,066.9 1,005.6 ------
Percentage reduction on area-wide
emissions compared to previous year:
emissions within scope of Local Authority
(figures from DESNZ with a 2-year lag)
Mitigation Annual data is published by the Department for
Energy Security and Net Zero. Area-wide emissions
decreased by 5.74% in calendar year 2023 compared
to 2022. 2023 is the most recent data available.
Contextual ------ ------ 11.4% 5.7% ------
Per capita: emission within scope of Local
Authority (figures from DESNZ with a 2-year
lag)
Mitigation Annual data is published by the Department for
Energy Security and Net Zero Data. This figure (3
tCO2e) is for calendar year 2023, which is the most
recent data available.
Contextual ------ ------ 3.30 3.00 ------
Reduction in the council’s greenhouse gas
emissions in 2024-25 compared to the
previous year (percentage reduction)
Mitigation The Council’s carbon emissions totalled 46,730
tCO2e (tonnes of carbon dioxide equivalent) in
2024-25. This shows a 70% reduction from the
baseline year of 2005-06 and a reduction of 5%
compared to 2023-24.
The 2024-25 decrease in emissions is due to a
reduction in gas and electricity consumption for the
Council Estate and significant reduction in the
emissions associated with the household waste
collection. The Carbon Management report for
2024-25 was presented to the Climate Change and
Sustainability Committee on 12 November 2025.
Report Later ------ ------ ------ 9.5% 5.0%
Reduce Scope 1 emissions from Council
carbon footprint (Council operations i.e.
buildings and fossil fuelled fleet)
Mitigation Scope 1 emissions account for 65% of the Council’s
operational emissions. This category of emissions
has reduced by 28% since the baseline year 2005-06.
Compared to 2023-24, Scope 1 emissions have
reduced by 2.34% in 2024-25.
This decrease in emissions is mainly due to a
reduction in gas consumption from the Council estate.
Green ------ ------ 32,869.0 31,019.0 30,291.0
Page 6 of 71
28

Page 29

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Performance Measures
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Performance Measures
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Performance Measures
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Performance Measures
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Performance Measures
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Performance Measures
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Performance Measures
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Performance Measures
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Performance Measures
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Performance Measures
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Performance Measures
Place and Communities
Progress a transition to net-zero, energy efficient and climate resilient homes, buildings and infrastructure, and minimise the unsustainable use of natural
resources and regenerate where appropriate
Performance Indicators Comments/ Progress Status 2023/24 2024/252022/23Target To Date
-------- Last 3 Years --------------------- This Year -------------
Intervention type
Reduce Scope 2 emissions from Council
carbon footprint (electricity)
Mitigation Scope 2 emissions account for 25% of the Council’s
operational emissions. This category of emissions
has reduced by 77% since the baseline year 2005-06.
Compared to 2023-24, Scope 2 emissions have
reduced by 2.61% in 2024-25.
This decrease in emissions is due to a reduction in
electricity consumption from the Council estate.
Green ------ ------ 11,781.0 11,982.0 11,651.0
Reduce Scope 3 emissions from Council
carbon footprint (waste and staff travel
currently reported)
Mitigation Scope 3 emissions account for 10% of the Council’s
operational emissions at present, however, this figure
is expected to rise as additional emissions categories
are added, in line with forthcoming Scottish
Government guidance. Scope 3 emissions have
reduced by 92.44% since the baseline year 2005-06.
Compared to 2023-24, Scope 3 emissions have
reduced by 23.35% in 2024-25.
A reduction has been achieved despite the addition of
the three new emissions categories this year (waste
and water from council buildings and homeworking
emissions).
Green ------ ------ 8,904.0 6,332.0 4,770.0
Occurrence/reduction of flood events Adaptation 2025 data will be provided in the quarter four update. Report Later ------ ------ 1,054 737 572
Page 7 of 71
29

Page 30

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Performance Measures
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Performance Measures
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Performance Measures
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Performance Measures
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Performance Measures
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Performance Measures
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Performance Measures
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Performance Measures
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Performance Measures
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Performance Measures
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Performance Measures
Place and Communities
Progress a transition to net-zero, energy efficient and climate resilient homes, buildings and infrastructure, and minimise the unsustainable use of natural
resources and regenerate where appropriate
Performance Indicators Comments/ Progress Status 2023/24 2024/252022/23Target To Date
-------- Last 3 Years --------------------- This Year -------------
Intervention type
Secure external funding to help deliver the
Council’s Sustainable Development and
Climate Change priorities
Sustainable
Development
Significant progress has been made in securing
external funding to support the Council’s sustainable
development and climate change priorities. A total of
£6.558 million in external funding has been secured
up to 30 September 2025.
Key highlights include:
• £5.49 million from Scotland’s Heat Network Fund for
a shared ground source heat pump system to serve
522 properties across six multi-storey tower blocks in
Calderwood, East Kilbride.
• Up to £50,000 from the Heat Network Support Unit
to complete a detailed feasibility study for a potential
district heat network in Almada Street, Hamilton.
• £15,000 from the SPT People and Place
Programme to fund the 'Walk 'n' Roll' programme in
East Kilbride and Cambuslang to support young
people and adults to walk and cycle.
• £11,000 from the SPT People and Place
Programme to support the 'Bikes Without Borders'
project in Cambuslang and Rutherglen which will
increase bike ownership and proficiency.
Over and above external funding sources,
non-competitive funding has been allocated including
£2.2m to fund sustainability projects as part of the
Scottish Government Climate Emergency Fund.
Green £1.00m £6.56m £0.00m £0.00m £1.67m
Page 8 of 71
30

Page 31

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Performance Measures
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Performance Measures
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Performance Measures
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Performance Measures
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Performance Measures
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Performance Measures
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Performance Measures
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Performance Measures
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Performance Measures
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Performance Measures
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Performance Measures
Place and Communities
Empower communities to take climate action and be more environmentally sustainable
Performance Indicators Comments/ Progress Status 2023/24 2024/252022/23Target To Date
-------- Last 3 Years --------------------- This Year -------------
Intervention type
Increase in the overall number of food
growing participants on Council land
including schools, care homes, housing area
and areas managed by community groups or
third-party organisations
Adaptation Figures will be collated for reporting at the end of the
financial year.
Report Later 1,118 ------ ------ 1,065 1,065
Natural Environment (Planet)
Improve the availability and access to quality outdoor spaces and services
Performance Indicators Comments/ Progress Status 2023/24 2024/252022/23Target To Date
-------- Last 3 Years --------------------- This Year -------------
Intervention type
Percentage of streets found to be acceptable
during Litter Monitoring System Survey
Sustainable
Development
One survey was completed for April to July 2025.
There are an additional two surveys to be carried out
by the financial year end, with the second survey
covering the period August-end of November 2025. A
final cumulative percentage will be reported at the
year end.
Report Later 92.0% ------ 92.3% 92.0% 92.9%
Page 9 of 71
31

Page 32

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Performance Measures
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Performance Measures
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Performance Measures
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Performance Measures
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Performance Measures
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Performance Measures
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Performance Measures
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Performance Measures
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Performance Measures
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Performance Measures
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Performance Measures
A Green Economy (Planet)
Lead the transition to a circular economy and improve resource efficiency through responsible consumption and production, and buying and selling of local
goods and services
Performance Indicators Comments/ Progress Status 2023/24 2024/252022/23Target To Date
-------- Last 3 Years --------------------- This Year -------------
Intervention type
Percentage of total household waste that is
recycled
Mitigation This measure is reported per calendar year, so the
figure shown (41.3%) relates to the period January to
June 2025. During this period the garden waste
permit scheme commenced and the potential for the
scheme to have an impact on the recycling rate was a
known risk associated with the project. However, the
garden waste permit scheme is just one factor
affecting the recycling rate, the other issue relates to
bulky waste treatment. Until June 2025 bulky waste
was sent to the Levenseat facility for recycling, since
the facility closed the bulky waste has had to be
diverted to landfill. The Service will continue to
monitor waste data flow and identify impacts on waste
statistics.
Amber 50.00% 41.30% 41.20% 43.75% 41.80%
Percentage of household waste sent to
landfill
Mitigation This measure is reported per calendar year and the
latest figures (0.83%) relate to the period from
January to June 2025. Performance for the first half of
the year is well within target.
Green 5.0% 0.8% 1.8% 1.5% 1.3%
Page 10 of 71
32

Page 33

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
Sustainable Development and Climate Change
Strategy - Section 2: Improvement Actions
The following section provides improvement actions that contribute towards meeting the outcomes in each
theme for this financial year.
Page 11 of 71
33

Page 34

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
People
Contribute to improving health and wellbeing through environmental protection and access to environmental benefits for all
Action Measures Comments/ Progress StatusIntervention type
Safeguard health by
improving and protecting
air quality
Implement grant funded air quality measures during
2025-26 to support the Air Quality Action Plan and
continue to maintain and publicise both real time and
historical air quality monitoring results
Mitigation The Council's two Strathclyde Partnership for Transport
People and Place funded projects continue to be delivered to
support active and sustainable travel behaviour change. Beat
the Street Cambuslang and Rutherglen commenced the game
phase on 15 September 2025 and will run for six weeks with
post-game legacy works being developed to support and
encourage our local communities to continue their active and
sustainable travel habits developed during the game phase of
the project. The first week of the project has seen over 8,000
local people participate with over 30,000 miles already
travelled actively. The BetterPoints - Think, Move, Breathe app
continues to engage with almost 1,400 members of our wider
South Lanarkshire community and rewards walking, cycling,
wheeling and public transport forms of travel.
Work also continues to support ongoing local air quality
monitoring activities as well as action planning measures to
improve air quality. The anti-engine idling campaign focused
on sports venues over the summer months, however this has
now transitioned back to focusing on idling outside schools.
Eco Stars continues to support fleet and taxi operators
travelling within South Lanarkshire with fuel and emissions
efficiency guidance.
Public consultation on revoking the remaining two air quality
management areas at the Whirlies, East Kilbride and
Rutherglen has commenced with the aim of revoking both air
quality management areas within Q3 2025-26.
The annual Air Quality Annual Progress Report has been
submitted and accepted by Scottish Government.
Green
Page 12 of 71
34

Page 35

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
People
Contribute to improving health and wellbeing through environmental protection and access to environmental benefits for all
Action Measures Comments/ Progress StatusIntervention type
Work to remove vacant,
derelict and
contaminated sites from
the Vacant and Derelict
Land Register
Implement projects approved within the Vacant and
Derelict Land Fund framework for 2025-26
Adaptation Following allocation by the Scottish Government of the
2025-26 Vacant and Derelict Land (VDL) Programme, the
Delivery Plan was presented to Community and Enterprise
Resources (CER) Committee on 12 August 2025. Approval of
the final allocation of funding (£103k) will be sought at CER
Committee in December 2025.  Projects are now being
progressed.
Green
Identify relevant climate
hazards, as well as risks
and opportunities which
are/will affect South
Lanarkshire
Develop a climate risk register upon which action
planning, decision-making and monitoring will be
built upon with regards to climate change adaptation
and resilience
Adaptation A climate change risk assessment process was started in
quarter two 2025-26. To progress this, the Adaptation Scotland
guidance 'Connecting Climate Risk and Strategic Priorities' is
being adopted as the primary framework, a six-stage nationally
recognised approach. Stage 1 of the process was completed
in September 2025. During this stage, appropriate governance
arrangements were established, and key stakeholders were
identified to support the development and delivery of the
assessment. Stage 2 - scoping and gathering evidence - will
continue throughout the remainder of 2025-26. A key output
from Stage 4 of the assessment will be the creation of a
climate risk register. It is anticipated this will be available by
quarter two 2026-27.
Green
Progress climate justice and ensure the transition to net-zero by 2045 does not exacerbate poverty or inequalities
Action Measures Comments/ Progress StatusIntervention type
Commission a PHD
student from Glasgow
Caledonian University to
undertake a study to
understand the impact
Analyse quantitative data from survey responses by
October 2025
Sustainable
Development
The survey period was extended to the end of December 2025
in order to collect more responses from South Lanarkshire
residents, to allow for more statistically significant analysis.
Analysis of the results will be undertaken in quarter four
2025-26.
Amber
Page 13 of 71
35

Page 36

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
People
Progress climate justice and ensure the transition to net-zero by 2045 does not exacerbate poverty or inequalities
Action Measures Comments/ Progress StatusIntervention type
of climate change on
South Lanarkshire
communities to inform
Analyse qualitative data and use this to produce and
deliver an interim report to the Climate Change and
Sustainability Committee by March 2026
Sustainable
Development
A presentation will be given to CCS Committee in February
2026 which will provide detail on the analysis of qualitative
data undertaken to date.
Green
for facilitating a just
transition
Continue to raise awareness internally of the project,
through participating in events, attending meetings
and delivering presentations to both external and
internal stakeholders
Sustainable
Development
The Sustainability team continue to raise awareness of the
project both internally and externally. The PhD student has
presented to the Council's CCS Committee, Officers Group,
and Steering Group, as well as engaging directly with Services
in the development of a number of strategic areas of work
including development of the LDP3 and Local Transport
Strategy to ensure just transition is appropriately considered.
The project was also raised at the Lanarkshire Climate
Conference in September 2025, organised by the Lanarkshire
Climate Hub and attended by third sector organisations from
across Lanarkshire.
Green
Page 14 of 71
36

Page 37

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
People
Progress climate justice and ensure the transition to net-zero by 2045 does not exacerbate poverty or inequalities
Action Measures Comments/ Progress StatusIntervention type
Work with partners to
promote available
energy advice and
funding support
schemes to minimise
fuel costs for
households
The Fuel Poverty Sub-Group will implement an
Action Plan to deliver a range of actions that help
tackle fuel poverty, including advice and support
Sustainable
Development
The Fuel Poverty Sub Group meets quarterly and held a
meeting on 1 September 2025. A presentation was given by
ChangeWorks, an organisation providing advice and support
to help households reduce costs, improve energy efficiency
and help people keep warm.
Throughout the period all group members were involved in
sharing information on a wide variety of topics including
funding, surveys, events, vacancies and training. To do this,
the group utilised the Financial Inclusion Network (FIN) weekly
bulletin and delivered a range of events held during Challenge
Poverty Week in October 2025, including a major event in
Council HQ on 10 October 2025 where group members
facilitated a number of stalls and workshops.
Green
Page 15 of 71
37

Page 38

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
People
Progress climate justice and ensure the transition to net-zero by 2045 does not exacerbate poverty or inequalities
Action Measures Comments/ Progress StatusIntervention type
Promote
weather-related
warnings and advice
from national agencies
(e.g. Met Office and
SEPA) to inform
individuals and
communities
Continue to work with the Council’s Communications
Team to deliver and/or share regional and/or national
weather warnings where relevant or appropriate
Adaptation The Communications Team actively monitor trusted partner
organisation sites to stay informed about weather events.
Where appropriate, the team share regional and national
weather warnings in advance to help communities prepare.
Ahead of severe weather, South Lanarkshire residents are
signposted to the Council website for information on how to
stay safe and prepare for severe weather events. During these
events, the team provides regular updates on impacts and
shares practical advice from partner organisations via the
Council’s social media channels.
Green
Page 16 of 71
38

Page 39

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
People
Progress climate justice and ensure the transition to net-zero by 2045 does not exacerbate poverty or inequalities
Action Measures Comments/ Progress StatusIntervention type
Work with Lanarkshire Climate Hub to enhance
individual and community resilience to the impacts of
climate change
Adaptation The Sustainability Team meet on a quarterly basis with the
Lanarkshire Climate Hub. These meetings allow both officers
and the Hub lead to discuss upcoming work, events and
priorities in order to understand how we can work together to
support common goals.
The Hub launched a Climate Ready Places Grant at the
beginning of the 2025 financial year. This supports Lanarkshire
based groups to engage with local communities to help start a
project within the local area that will give communities the
capacity to prepare, respond and bounce back from the
impacts of climate change and extreme weather events. Two
South Lanarkshire based projects are currently benefitting
from this funding and the Sustainability Team will continue to
monitor the progress and outcomes of these projects through
regular meetings with the Hub representatives.
Green
Page 17 of 71
39

Page 40

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
People
Progress climate justice and ensure the transition to net-zero by 2045 does not exacerbate poverty or inequalities
Action Measures Comments/ Progress StatusIntervention type
Raise awareness of
online services for
citizens where
appropriate, reducing
need for travel and to
improve service delivery
Promote self-care and self-management through
increasing the awareness and uptake of telehealth
and telecare as part of broadening the options
around how health and social care can be delivered
Mitigation and
Sustainable
Development
Self-care and self-management continues to be promoted in
South Lanarkshire. Across Lanarkshire 1,956 patients were
onboarded to remotely monitor their health between April and
September 2025 with Primary Care blood pressure monitoring
being the most utilised pathway. 12,930 consultations were
undertaken using Near Me.
In South Lanarkshire for quarter one and quarter two, 2,551
telecare installation visits were carried out. There were 1,251
telecare referrals approved. A key milestone was reached with
6,500 service users now transitioned from analogue to digital
alert alarm systems.
The Technology Enabled Care (TEC) team continue to
progress the Amazon Healthcare Project, aimed at enhancing
digital support for service users. Ongoing support is provided
to Intermediate Care (IC) service users and updated care
surround guides have been placed in each IC bedroom in
response to service user feedback.
South Lanarkshire University HSCP extended the use of Smart
TVs across residential and intermediate care services in
August and September 2025, following a positive evaluation of
the project within David Walker Gardens care home. The
technology has enabled residents to communicate directly via
text message or video call with care home staff, their families,
and friends via their TV, having a positive impact on improved
wellbeing of residents and increased connectivity with families.
Green
Page 18 of 71
40

Page 41

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
People
Influence change through improving the understanding of Sustainable Development and the Climate Emergency across South Lanarkshire
Action Measures Comments/ Progress StatusIntervention type
Mainstream
sustainability and
climate literacy learning
and development across
the Council
Promote training and upskilling opportunities relating
to climate change adaptation and mitigation
Sustainable
Development
The Sustainability Team continue to promote sustainability and
climate change adaptation and mitigation training opportunities
to colleagues across the council. This includes both internal
and external training.
Both climate change and biodiversity training modules
available on Oracle Fusion were promoted to council
colleagues during the month of climate communications in
September 2025. These continue to be publicised throughout
2025/26 using various methods available and linking them with
related campaigns.
Various external upskilling events and sessions have been
promoted to relevant colleagues which have covered the
following topics: just transition, nature networks, energy,
adaptation and flooding to name a few.
Green
Page 19 of 71
41

Page 42

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
People
Influence change through improving the understanding of Sustainable Development and the Climate Emergency across South Lanarkshire
Action Measures Comments/ Progress StatusIntervention type
Develop and implement
a robust
communications plan for
promoting and raising
awareness of the
sustainability, climate
change and adaptation
agenda within the South
Lanarkshire Council,
national and global
context
Work with the council's corporate communications
team to develop and implement the 2025-26
communications plan. This will include the promotion
of the key campaigns throughout the year, for
example, Climate Week
Sustainable
Development
A consistent suite of climate change and sustainability
communications have been delivered during 2025. The
initiatives and campaigns have covered a diverse range of
topics which represent and align with work being carried out
across the Council. Some campaigns and themes have
included Earth Hour, Earth Day, local community action
festivals, litter reduction, walking campaigns, emissions
reductions, green health, tree planting, road safety and air
quality.
During the month of September 2025 a host of
communications have been delivered in recognition of some
key national and local campaigns such as Recycle Week,
Secondhand September, Lanarkshire Climate Festival, Beat
the Street and Car Free Day. A range of delivery methods have
been employed including in person events, conservation days,
social media posts, VIEW articles, plus council emails and
intranet posts.
Green
Work with the council's corporate communications
team to develop a refreshed 2026-27
communications plan, by April 2026
Sustainable
Development
Work will progress to create the 2026-27 climate change and
sustainability communications plan early in 2026. This will
allow for lessons learned during the implementation of the
2025-26 communications plan to help inform the approach and
initiatives for 2026-27.
Report Later
Page 20 of 71
42

Page 43

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
People
Influence change through improving the understanding of Sustainable Development and the Climate Emergency across South Lanarkshire
Action Measures Comments/ Progress StatusIntervention type
Further embed
sustainable
development and
climate change into the
Council’s
decision-making
process
Support the Climate Change and Sustainability
Officers Group and Steering Group to embed climate
change and sustainability scrutiny into reporting
Sustainable
Development
The Sustainability team continue to work with the Officers and
Steering Groups to ensure that climate change and
sustainability considerations are considered in committee
reports and IIAs. This has primarily been through the sharing
of relevant updates from organisations such as the
Sustainable Scotland Network, through promotion of internal
training, and offering one-to-one support when required.
Green
Broaden engagement through existing governance
structures such as the Steering Group and Officers
Group to invite attendance by external partners when
appropriate
Sustainable
Development
Sustainability team members have broadened engagement
over quarter one and quarter two 2025-26 by working more
closely with Lanarkshire Climate Hub, including presenting at
their Climate Conference in September 2025; by engaging with
the pan-Lanarkshire public sector sustainability working group,
which has representation from local authorities, NHS
Lanarkshire, Police Scotland, Scottish Fire and Rescue
Service, and colleges; and through regular meetings with
sustainability counterparts in North Lanarkshire Council
alongside engagement with national networks to share good
practice.
Green
Page 21 of 71
43

Page 44

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
People
Influence change through improving the understanding of Sustainable Development and the Climate Emergency across South Lanarkshire
Action Measures Comments/ Progress StatusIntervention type
Ensure sustainability is
considered within capital
and revenue budget
plans
Use the Officers Group and Steering Group to
provide Officers with support and encouragement to
embed greater scrutiny within the sustanability and
climate change section of committee reports and
within Integrated Impact Assessments
Sustainable
Development
Training on completing the SIA section of the IIA tool is in
development and anticipated to be made available by quarter
four 2025-26. A workshop is planned with the CCS Officers
Group in quarter four 2025-26 providing advice and support in
completing the Climate Change, Sustainability, and
Environmental Implications section of committee reports.
Green
Page 22 of 71
44

Page 45

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
People
Influence change through improving the understanding of Sustainable Development and the Climate Emergency across South Lanarkshire
Action Measures Comments/ Progress StatusIntervention type
Empower learners to
shape and influence
action on climate
change and
sustainability through
the Youth Forum
Continue to support the Youth Forum on Climate
Change and Sustainability to ensure young people’s
voices are represented on appropriate Council
matters relating to this subject area
Sustainable
Development
The Youth Forum on Climate Change and Sustainability
continues to be supported to ensure young people’s voices are
represented on relevant Council matters. Schools have raised
key issues affecting them, including school uniforms, travel,
local litter picking, and opportunities to engage in Council-led
events.
Officers from across Council services have attended Forum
meetings to discuss their work and its impact on sustainability.
For example, Food Services met with students to explore
sustainable school meal options and held a tasting session to
help shape new menus.
On 22 October 2025, Forum members presented their
2025–26 targets to the Community Planning Partnership,
seeking support for two priorities: community litter picking and
raising awareness of the Youth Forum at Council-wide events.
Green
Page 23 of 71
45

Page 46

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
People
Influence change through improving the understanding of Sustainable Development and the Climate Emergency across South Lanarkshire
Action Measures Comments/ Progress StatusIntervention type
Continue to support the Youth Forum in empowering,
shaping and influencing behaviour change in relation
to climate change and sustainability in schools
Sustainable
Development
Support for the Youth Forum continues to empower young
people to shape and influence behaviour change around
climate change and sustainability in schools. There has been
an increase in the number of students attending Youth Forum
meetings, demonstrating the growing importance of this work
to young people across the authority.
In June 2025, Forum members brainstormed a wide range of
ideas for the 2025–26 school year, and in August, they
explored and voted on their top targets for the year ahead. A
variety of opportunities have been offered to members,
including participation in Teach the Teacher training, where
students will deliver sessions to their own teachers on
embedding climate education across all subjects and
discussing climate anxiety from a student perspective.
Forum members have also taken part in a national competition
led by Keep Scotland Beautiful and are now preparing for the
next annual Conference of Schools event, where they will
deliver presentations to primary pupils, empowering them to
drive change and share learning across age groups.
Green
Page 24 of 71
46

Page 47

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
People
Influence change through improving the understanding of Sustainable Development and the Climate Emergency across South Lanarkshire
Action Measures Comments/ Progress StatusIntervention type
Embed sustainability in
the curriculum across all
Education
establishments
Aligned with Scotland's Learning for Sustainability
Action Plan 2023-2030, "Target 2030", aim to
enhance our commitment to Learning for
Sustainability at all educational levels and in line with
General Teaching Council Professional Standards,
all practitioners, schools, and education leaders
should incorporate learning for sustainability into
their practice
Sustainable
Development
Implementation of this measure is progressing steadily. In line
with Scotland’s Learning for Sustainability Action Plan
2023–2030 (Target 2030), steps are being taken to strengthen
commitment to Learning for Sustainability across all
educational levels.
Green
Offer professional learning sessions that focus on
how to incorporate Learning for Sustainability into
teaching, how to plan sustainability projects, and
how to involve the community and students in these
initiatives
Sustainable
Development
This work is progressing steadily. Professional learning
opportunities on Learning for Sustainability have been
developed and shared with staff, focusing on integrating
sustainability into teaching and project planning. While
participation has so far been limited, feedback has been
constructive, and further sessions are planned to broaden
engagement and strengthen community and learner
involvement over time.
Green
Page 25 of 71
47

Page 48

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
People
Influence change through improving the understanding of Sustainable Development and the Climate Emergency across South Lanarkshire
Action Measures Comments/ Progress StatusIntervention type
Work to continue to raise awareness and monitor
achievement of learning for sustainability in Early
Years establishments
Sustainable
Development
The majority of Early Years learning settings, both SLC and
funded providers, are completing a sustainability project. A
sustainability event is arranged for quarter three 2025-26. At
the event, Education Scotland will provide an overview of the
national picture and deliver a workshop for attendees. Several
external agencies, e.g. Keep Scotland Beautiful will host stalls,
showcases will be delivered by some participants, and SLC's
Youth Climate Ambassadors are delivering a presentation.
Following this event, project updates will be sought from
settings.
Green
All Early Years establishments will participate in a
Learning for Sustainability knowledge sharing event
to encourage incorporating sustainaiblity in Early
Years settings
Sustainable
Development
The event is scheduled for quarter three 2025-26. A range of
external agencies will host stalls and three early years settings
are showcasing. The SLC Education Sustainability
Development Officer and Sustainable Development Team
representative will be attending and will host a stall. The officer
will also link in with the Youth Forum regarding their input to
the event.
Green
Each Early Years establishments will plan and begin
delivering a sustainability project by March 2026
Sustainable
Development
The majority of establishments are currently carrying out a
variety of projects. Updates will be requested following the
face to face event scheduled for quarter three 2025-26 and an
update will be provided in the quarter four update report to
CCS Committee.
Green
Page 26 of 71
48

Page 49

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
People
Influence change through improving the understanding of Sustainable Development and the Climate Emergency across South Lanarkshire
Action Measures Comments/ Progress StatusIntervention type
Deliver a Learning for Sustainability showcase event
where Early Years, Primary and Secondary schools
present projects and initiatives that integrate
sustainable development education, global
citizenship, and outdoor learning into the curriculum
Sustainable
Development
Planning for this event is underway. A confirmed date of 10
February 2026 has been secured, and work is in progress to
identify and engage schools to participate and contribute to the
programme. The current focus is on coordinating participants,
developing content, and ensuring alignment with Learning for
Sustainability priorities.
Green
Page 27 of 71
49

Page 50

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
People
Influence change through improving the understanding of Sustainable Development and the Climate Emergency across South Lanarkshire
Action Measures Comments/ Progress StatusIntervention type
Explore and review
options for carbon
reduction from school
estates through
understanding carbon
footprint of activities/
estates
Work with Resources from across the Council to
understand and reduce carbon footprint through a
set of co-developed carbon reduction initiatives
Mitigation Quarterly meetings are held where a representative from
Education Resources collaborates with other Council services
to share progress and explore ways to collectively reduce the
Council's carbon footprint. These sessions provide valuable
opportunities to exchange information, align activities, and
identify how services can support one another in achieving
sustainability goals. This collaborative approach continues to
be particularly beneficial for Education Services, helping to
coordinate specific events and establish key contacts to further
support the work of the Youth Forum on Climate Change and
Sustainability.
Green
Page 28 of 71
50

Page 51

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
People
Influence change through improving the understanding of Sustainable Development and the Climate Emergency across South Lanarkshire
Action Measures Comments/ Progress StatusIntervention type
Work with our
communities to provide
programmes and
opportunities to increase
sustainability awareness
and action
Provide access to adult learning opportunities which
raise awareness on climate change
Sustainable
Development
A range of projects continue to be delivered to support adult
learners engage with climate change and sustainable
practices. These include:
Rutherglen Universal Connections “Square Roots” gardening
project is supporting adult learners to learn about sustainability
activity whilst improving confidence in their numeracy.
Douglas Universal Connections “Hameldaeme” project has
introduced opportunities for adult learners to understand and
engage with sustainable practices and to help reduce climate
impact locally. Both the 'Square Roots' and 'Hameldame'
programmes are part of the legacy of the Youth, Family and
Community Learning Service’s multiply project “Make Numbers
Count” which continues to help embed adult numeracy
learning within wider programmes across the service.
East Kilbride Universal Connection’s “Nowhere To Grow”
project continues to expand space to cover 400 square
metres. The programme is seeking to increase opportunities to
learn whilst also expanding the crops being grown. This will
present increased capacity for crops and develop learners'
capacity to engage in growing food.
Lanark Universal Connections have progressed plans to utilise
the area beside the building to create raised beds with the
support of the Community Payback Team. This has now been
completed.
Green
Page 29 of 71
51

Page 52

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
People
Influence change through improving the understanding of Sustainable Development and the Climate Emergency across South Lanarkshire
Action Measures Comments/ Progress StatusIntervention type
Promote access to Environmental and Sustainability
Learning Programmes and Awards delivered across
the authority
Sustainable
Development
Learners continue to be supported to access a number of
awards. The Duke of Edinburgh’s Award Scheme continues to
facilitate volunteering with community groups looking at
conservation and environmental awareness.
The redesigned John Muir Award has now been released
which in addition to fresh content and new resources, has a
new level “Wild Places Guardian” which will encourage people
to connect with, enjoy and care for wild places. Education
establishments have been alerted to the new award and are
exploring use within their curriculum programmes in addition to
Youth, Family and Community Learning (YFCL) provision.
Learners are also encouraged to increase understanding of
environmental issues by participating in outdoor learning
opportunities delivered through the YFCL Awards Team and
projects as well as through the network of Universal
Connections facilities. This work is underpinned by the South
Lanarkshire Youth Strategy, the Community Learning and
Development Strategic 3-Year Action Plan, and the Learning
for Sustainability Action Plan.
Following on from the success of the Conference of Schools 3
(COS3) event, supported by the Community Planning
Partnership, a Conference of Schools 4 is currently being
planned for early 2026. COS3 helped to develop ideas for
content and delivery, to over 300 Primary 5 to Primary 7 pupils
across South Lanarkshire. A further event will continue to
equip young people with the knowledge and confidence to
progress ideas at school, and at home, to change behaviours
in support of tackling environmental issues.
Green
Page 30 of 71
52

Page 53

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
People
Influence change through improving the understanding of Sustainable Development and the Climate Emergency across South Lanarkshire
Action Measures Comments/ Progress StatusIntervention type
Provide food growing learning programmes across
South Lanarkshire
Sustainable
Development
Food growing activities are developing within Youth, Family
and Community Learning (YFCL) Service. Drawing on
experience from existing provision within YFCL, we are
seeking to extend programmes to facilities that do not currently
have the capacity to provide raised beds, working between
centres to provide access to skills development and capacity
to replicate practices within home and community settings.
Growing activities have been embedded into school
programmes too, recognising both the wider application of
resources and opportunities to diversify learning. Such activity
supports progression of the Learning for Sustainability Action
Plan.
Green
Raise awareness about
the impact of avoidable
food waste and the
benefit of composting
food waste
Collaborate with Corporate Communications to raise
awareness of the climate impact of food waste and
promote composting and food waste recycling, in
alignment with the rollout of the chargeable garden
waste project
Mitigation Waste Services worked with Digital and PR to launch a
successful composter pilot scheme early in August 2025. The
service procured, promoted and delivered 360 composters in
the first phase. The second phase was launched to coincide
with Recycle Week and Climate Week 2025. The Service also
worked on a communications campaign to promote food waste
recycling.
Green
Page 31 of 71
53

Page 54

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
Place and Communities
Improve affordable, sustainable, and accessible transport options
Action Measures Comments/ Progress StatusIntervention type
Encourage active travel
by extending our
network of walking and
cycle routes
Continue to design and deliver walking and cycling
projects in line with agreed 2025-26 capital
programme
Mitigation Schemes are being developed in line with available funding.
These include schemes at the following locations: Strathaven
Road, Calderglen; Columbie Junction and Stonelaw Road.
Green
Deliver new and
improved low carbon
vehicle charging
infrastructure
Work with Glasgow City Region partners to expand
publicly available charging infrastructure across
South Lanarkshire
Mitigation Work is continuing on the regional collaboration initiative to
expand and enhance vehicle charging infrastructure across
the west. A consultant has been appointed to project manage
the next phase and to prepare tender documentation. This will
seek to appoint a commercial operator for publicly available
electric vehicle charging infrastructure.
Tender preparation has commenced with a view to a contract
being awarded in late 2026.
Green
Progress towards
decarbonising the fleet
of South Lanarkshire
Council vehicles
Review the Fleet Strategy by 31 December 2025,
outlining targets and ambitions to reduce
fleet-related emissions
Mitigation Progress on the Fleet Strategy review has been impacted on
by competing priorities.
A recent recruitment exercise has now provided some stability
to focus on this key piece of work. A paper will be presented to
a future committee in 2026-27.
Amber
Encourage greater use
of public transport by
working with partners to
improve public transport
infrastructure
Deliver prioritised improvements to bus and rail
infrastructure (e.g. park and ride) in line with
available external funding for 2025-26
Mitigation Lanark Interchange - A tender for the construction of a new
bus station area was issued in September 2025 and it is
anticipated that works will begin early in 2026 and span the
financial year 2026-27.
Green
Page 32 of 71
54

Page 55

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
Place and Communities
Improve affordable, sustainable, and accessible transport options
Action Measures Comments/ Progress StatusIntervention type
Consider sustainable
travel within the
Council’s employee
travel plan
Update the existing employee travel plan during
2025-26 with consideration made to sustainable
travel choices
Mitigation The employee travel plan is under review and will reflect the
full range of travel choices available to employees as well as
reflecting the changes in travel requirements as a result of
improvements in technology and remote working.
Green
Continue to achieve
Cycle Friendly Employer
status
Ensure that current cycle friendly status facilities at
principal building (e.g. HQ, South Vennel) are
maintained and promoted, encouraging and enabling
staff to actively travel to work, alongside promotion of
the Cycle to Work Scheme
Mitigation The Cycle to Work scheme continues to be promoted via the
intranet and cycle friendly status has been maintained. Both of
these initiatives will continue to be promoted as part of the
revisions to the employee travel plan.
Green
Page 33 of 71
55

Page 56

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
Place and Communities
Progress a transition to net-zero, energy efficient and climate resilient homes, buildings and infrastructure, and minimise the unsustainable use ofnatural resources and regenerate where appropriate
Action Measures Comments/ Progress StatusIntervention type
Reduce South
Lanarkshire Council's
carbon footprint
Explore options for an initial Net Zero Route Map for
Scope 1 emissions
Mitigation It was agreed at the CCS Committee on 19 March 2025 as
part of the Council’s longer term strategic planning that a net
zero route map for Scope 1 emissions be developed. The
route map will be developed in cognisance of other statutory
service strategies and highlight the significant financial
investment required to achieve net zero, detailing costs and
potential sources of finance.
The Net Zero Route Map for Scope 1 emissions will be
informed by the new Fleet Strategy and the ten Year Estates
Strategy. New statutory climate change guidance for public
bodies is anticipated to be published imminently, which will
also inform the next steps in the Council’s Net Zero Route
Map.
Green
Page 34 of 71
56

Page 57

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
Place and Communities
Progress a transition to net-zero, energy efficient and climate resilient homes, buildings and infrastructure, and minimise the unsustainable use ofnatural resources and regenerate where appropriate
Action Measures Comments/ Progress StatusIntervention type
Present 2024-25 carbon management report to CCS
Committee by December 2025
Mitigation The Council’s carbon emissions totalled 46,730 tCO2e in
2024-25. This shows a 70% reduction from the baseline year
of 2005-06 and a reduction of 5% compared to 2023-24.
The Carbon Management report for 2024-25 was presented at
the Climate Change and Sustainability Committee on 12
November 2025.
Complete
Page 35 of 71
57

Page 58

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
Place and Communities
Progress a transition to net-zero, energy efficient and climate resilient homes, buildings and infrastructure, and minimise the unsustainable use ofnatural resources and regenerate where appropriate
Action Measures Comments/ Progress StatusIntervention type
Work to progress the
Council's maturity and
capability in tackling the
climate and nature
emegencies using the
Scottish Government
Leaders' Climate
Emergency Checklist
Implement improvement actions outlined in the
Leaders' Climate Emergency Checklist to advance
sustainability efforts and achieve greater maturity
across all identified themes
Sustainable
Development
Specific actions have been incorporated into the Sustainable
Development and Climate Change Action Plan that address
the improvement actions identified in the Leadership Climate
Emergency Checklist. Progress on these actions will help the
Council to achieve greater maturity across all identified
improvement themes. The actions are noted below:
• Use the Officers Group and Steering Group to provide
Officers with support and encouragement to embed greater
scrutiny within both the sustainability and climate change
section of committee reports and within Integrated Impact
Assessments.
• Explore options for an initial Net Zero Route Map for Scope 1
emissions.
• Broaden engagement through existing governance structures
such as the Steering Group and Officers Group to invite
attendance by external partners when appropriate.
• Develop and deliver the agreed 2025-26 communications
plan using diverse delivery methods to effectively engage all
identified audiences and stakeholders both internal to the
Council and externally.
• Update the Climate Change and Sustainability Steering
Group on funding and finance models and examples of good
practice by March 2026.
• Engage Services to understand how to better align spending
plans and use of resources to contribute to reducing
emissions.
• Work to enhance individual and community resilience to the
risks of climate change by promoting preparedness resources
(e.g. Adaptation Scotland) and raise awareness of the
importance of community and business adaptation to
weather-related challenges.
• Work with the council’s corporate communications team to
Green
Page 36 of 71
58

Page 59

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
Place and Communities
Progress a transition to net-zero, energy efficient and climate resilient homes, buildings and infrastructure, and minimise the unsustainable use ofnatural resources and regenerate where appropriate
Action Measures Comments/ Progress StatusIntervention type
develop a refreshed 2026-27 communications plan, by April
2026. This will include the promotion of key campaigns
throughout the year, for example, Climate Week.
• Number of council employees who have completed the Learn
of Line Climate Change modules.
• Promote training and upskilling opportunities relating to
climate change adaptation and mitigation.
• Consider the impact of climate change and the need for new
or additional skills or knowledge as part of the Resource
workforce planning process in 2025-26.
• Identify senior phase vocational learning opportunities that
prepare young people for the green economy.
• Connect with businesses to help them grow and upskill their
current workforce to adapt to industry requirements.
• Continue to embed the Sustainability Impact Assessment
Process into decision-making for both capital and revenue
proposals by delivering training, raising awareness, and
upskilling staff involved in the budget process.
Page 37 of 71
59

Page 60

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
Place and Communities
Progress a transition to net-zero, energy efficient and climate resilient homes, buildings and infrastructure, and minimise the unsustainable use ofnatural resources and regenerate where appropriate
Action Measures Comments/ Progress StatusIntervention type
Embed sustainability in
the decision-making
process in capital
projects
Consider sustainability as part of the ongoing country
parks masterplan during 2025
Sustainable
Development
A Sustainability Impact Assessment (SIA) has been completed
to assess the likely environmental impacts of the design
proposals contained within the Country Park Masterplans. The
SIA considers the Whole Life Carbon impacts, Climate
Resilience, Circular Economy, Environmental Stewardship,
Nature Enhancement, Active Travel provision, Community
Resilience and Health and Wellbeing outcomes. The SIA will
be used by project lead officers in the further development and
delivery of the proposals, to avoid unsustainable and
environmentally unfavourable outcomes.
Green
Page 38 of 71
60

Page 61

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
Place and Communities
Progress a transition to net-zero, energy efficient and climate resilient homes, buildings and infrastructure, and minimise the unsustainable use ofnatural resources and regenerate where appropriate
Action Measures Comments/ Progress StatusIntervention type
Ensure sustainability is a priority in the
redevelopment of Larkhall Leisure Centre
Sustainable
Development
The new leisure centre will be developed in line with the
principles of Passivhaus which focuses on high levels of
insulation and airtightness, mechanical ventilation with heat
recovery and triple glazed windows.
The building footprint generates estimates for the use of
energy and the intention with the design is to reduce the
estimated usage and provide a more efficient operational
energy demand for the building.
Thermal comfort of the regularly occupied spaces will also be
measured in the building design.
Carbon reduction will be achieved through the careful
selection and use of modern building materials such as Cross
Laminated Timber, with emphasis on satisfying energy
demands through the use of utilities and products that will
reduce or eliminate the use of fossil fuels.
Green
Page 39 of 71
61

Page 62

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
Place and Communities
Progress a transition to net-zero, energy efficient and climate resilient homes, buildings and infrastructure, and minimise the unsustainable use ofnatural resources and regenerate where appropriate
Action Measures Comments/ Progress StatusIntervention type
Develop the Public
Bodies Climate Change
Duties Report
Work with Services to complete the Public Bodies
Climate Change Duties Report 2024-25 for
submission to the Scottish Government by 30
November 2025
Sustainable
Development
The annual Public Bodies Climate Change Duties compliance
report for 2024-25 has been completed. The report was
presented at the Climate Change and Sustainability
Committee on 12 November 2025 for approval, before being
submitted to the Scottish Government by the 30 November
deadline.
Complete
Explore funding and
finance models for
net-zero and climate
adaptation projects,
while engaging services
to better integrate
climate change and
sustainable
development into
finance strategies and
reporting, ensuring
alignment with long-term
Update the Climate Change and Sustainability
Steering Group on funding and finance models and
examples of good practice by March 2026
Sustainable
Development
Funding is a standing item on the agenda for the CCS
Steering Group.
The Sustainability Team continue to engage with Glasgow City
Council (GCC) on their proposed model for climate investment
which has potential for roll out across the Glasgow City Region
(GCR). Officers are also engaging with Salix Finance, who
administer funds on behalf of the Department for Energy
Security and Net Zero and the Scottish Government, on their
Recycling Fund which provides long term investment in energy
efficiency across the public sector, to better understand the
suitability of this option for SLC.
Green
Page 40 of 71
62

Page 63

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
Place and Communities
Progress a transition to net-zero, energy efficient and climate resilient homes, buildings and infrastructure, and minimise the unsustainable use ofnatural resources and regenerate where appropriate
Action Measures Comments/ Progress StatusIntervention type
sustainability goals Engage Services to understand how to better align
spending plans and use of resources to contribute to
reducing emissions
Sustainable
Development
This work is primarily being furthered through ongoing
engagement with services in development of the Council's Net
Zero Scope 1 Route Map. The Sustainability team is engaging
with Fleet and Property Services to ensure that forthcoming
plans make clear how emissions reduction forms a key part of
services' future activity.
Green
Page 41 of 71
63

Page 64

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
Place and Communities
Progress a transition to net-zero, energy efficient and climate resilient homes, buildings and infrastructure, and minimise the unsustainable use ofnatural resources and regenerate where appropriate
Action Measures Comments/ Progress StatusIntervention type
Work with the Scottish
Climate Intelligence
Service to support
planning and delivery of
programmes of
area-wide emissions
reduction across South
Lanarkshire
Develop the Climate View area wide emissions
dashboard for the South Lanarkshire area by March
2026
Mitigation Officers continue to work collaboratively with the Scottish
Climate Intelligence Service (SCIS) to build capacity and
capability around the ClimateView platform. Priority
interventions from the Sustainability and Climate Change
Strategy and Local Heat and Energy Efficiency Strategy
(LHEES) have been identified using the SCIS Intervention
Capture Process. Awareness raising sessions have been held
with the CCS Steering Group and Officers Group.
Next steps include inputting key interventions into the Council's
official ClimateView dashboard and engaging with key service
areas to begin collating wider Council interventions from plans
and policies.
Green
Page 42 of 71
64

Page 65

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
Place and Communities
Progress a transition to net-zero, energy efficient and climate resilient homes, buildings and infrastructure, and minimise the unsustainable use ofnatural resources and regenerate where appropriate
Action Measures Comments/ Progress StatusIntervention type
Manage flooding
priorities and deliver
prioritised actions under
the Local Flood Risk
Management Plan(s)
Deliver prioritised flood protection projects/studies in
line with available capital and revenue funding for
2025-26
Adaptation A number of culvert and access improvement works are
programmed to be carried out this financial year at various
watercourses across the council area, including culvert inlet
trash screen replacements and construction of maintenance
access at both Benbecula in East Kilbride and Bankhead Pond
in Rutherglen.
Property-level flood protection measures have been identified
for installing to three at-risk properties in Park Avenue, Coulter.
The specification of these measures has been agreed with
Housing and Technical Resources, and in advance of the
contract being awarded the contractor is undertaking the
Council’s vetting requirements. Updates will be provided on
the installation of the measures at the 2025/26 Q4 update.
In response to ongoing flooding issues being experienced in
Carstairs Junction, a flood study is scheduled to be
undertaken to assess the flooding mechanisms in the area
and identify suitable improvement opportunities. The scope of
this study has been finalised, and the contract is currently out
to tender using the Council’s Quick Quote procedure. This
project is scheduled for completion by end of 2025-26 financial
year.
Internal culvert-lining works were required to the outfall pipe
which drains James Hamilton Heritage Loch in East Kilbride.
These works have been delayed several times due to
contractor availability, however, further to a change to the
repair method being used, these works were completed in
Summer 2025.
A surface water management plan (SWMP) is proposed to be
Green
Page 43 of 71
65

Page 66

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
Place and Communities
Progress a transition to net-zero, energy efficient and climate resilient homes, buildings and infrastructure, and minimise the unsustainable use ofnatural resources and regenerate where appropriate
Action Measures Comments/ Progress StatusIntervention type
carried out in Hamilton. Utilising existing sewer models, known
flood history and new hydraulic modelling this project will
provide a greater understanding of flood risk across the area,
and inform optioneering projects that will be progressed in
subsequent financial years. Due to other flooding issues
requiring the progression of immediate remedial works at
Carluke High School, Lanark Loch and Hyndford Road, the
delivery of this SWMP in Hamilton has been delayed. It is now
envisaged that the Hamilton SWMP will be procured using the
Council’s Quick Quote procedure late 2025-26 for completion
within the 2026-27 financial year.
In addition to above, annual reservoir inspections, drainage
investigation works, watercourse surveys, and subsequent
clearance works are undertaken regularly by the Flood Risk
Management team.  As situations arise during a financial year,
minor work packages are regularly included in our Works
Programme for investigation and delivery of solutions.
Page 44 of 71
66

Page 67

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
Place and Communities
Progress a transition to net-zero, energy efficient and climate resilient homes, buildings and infrastructure, and minimise the unsustainable use ofnatural resources and regenerate where appropriate
Action Measures Comments/ Progress StatusIntervention type
Improve resilience of the
road network through
routine maintenance
Review current road maintenance practices to
improve climate change resilience through the use of
alternative methods, materials and design standards
Adaptation The service actively explores alternative maintenance
techniques aligned with industry best practices to reduce its
carbon footprint and enhance resilience to climate change.
All proposed techniques undergo rigorous evaluation by the
Engineering Teams, who assess their engineering merit,
feasibility of operational delivery, long-term maintenance
implications, and whole-life cost.
To foster innovation in this field, the service maintains close
collaboration with the Scottish Collaboration of Transportation
Specialists (SCOTS) and the Scottish Roads Research Board.
In 2025-26, the service received funding through the Climate
Emergency Fund to support trials of low-carbon road surfacing
materials. Work was undertaken at the three trial sites over
October and November 2025.
Green
Utilise innovative and
new information
technologies for
environmental benefits
Explore sustainable web design to reduce the
Council website's carbon footprint
Mitigation Approval has now been given for the re-design and
development of a new Council website and intranet.
The development of an implementation plan has commenced
which will consider key sustainability principles relative to the
design of the website.
Green
Page 45 of 71
67

Page 68

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
Place and Communities
Progress a transition to net-zero, energy efficient and climate resilient homes, buildings and infrastructure, and minimise the unsustainable use ofnatural resources and regenerate where appropriate
Action Measures Comments/ Progress StatusIntervention type
Implementation of
revised Building
Regulations in relation
to energy performance
in new buildings and the
adaptation of existing
buildings  
Continue to raise awareness and upskill surveyors
on the Proposed Domestic Building Environmental
Standards (Scotland) Bill, considering changes to
legislation and building regulations, through
facilitating training and awareness sessions
Adaptation The Building Standards Team continue to upskill surveyors on
revisions to building standards with respect to the energy
performance of buildings. Surveyors undertake Continuous
Professional Development (CPD) through learning and
development delivered by the Scottish Building Standards Hub
(SBSH). In addition, a training team has been established to
promote learning through peer review.
Green
Increase the overall
energy efficiency of
homes and increase the
rates of decarbonisation
within domestic
properties across South
Lanarkshire
Support homeowners and private landlords to
improve the energy efficiency of their properties
through administering and promoting the Energy
Company Obligation Scheme (ECO) and Energy
Efficient Scotland: Area Based Schemes
Mitigation The project details for ECO4 are published on our website.
238 declarations have been processed.
124 owner occupiers' homes have had 129 measures
installed.
We also continue to implement the Area Based Scheme (ABS)
programme as part of our Housing Investment Programme.
Property owners and private tenants are formally notified of
upcoming works via letter, invited to attend public consultation
meetings, and provided with a detailed brochure outlining the
scope of works and associated costs. 106 properties have had
additional energy measures installed: 61 Council and 33
owners had cavity wall insulation installed and 10 Council and
2 owners have had loft insulation installed.
Green
Page 46 of 71
68

Page 69

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
Place and Communities
Progress a transition to net-zero, energy efficient and climate resilient homes, buildings and infrastructure, and minimise the unsustainable use ofnatural resources and regenerate where appropriate
Action Measures Comments/ Progress StatusIntervention type
Support Registered Social Landlord partners to
improve the energy efficiency of their housing stock
and take forward opportunities to work jointly to
decarbonise heating systems
Mitigation Through the new Registered Social Landlord group, alignment
of investment plans to maximise opportunities to improve
energy efficiency and decarbonise domestic buildings is
considered, with a key aim to reduce delays in upgrades for
mixed tenure blocks.
The Council are planning to undertake a heat pump
accelerator research project in 2025-26 to demonstrate
effectiveness of heat pumps. When complete, this research
will be shared with our Registered Social Landlord partners.
Green
Page 47 of 71
69

Page 70

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
Place and Communities
Progress a transition to net-zero, energy efficient and climate resilient homes, buildings and infrastructure, and minimise the unsustainable use ofnatural resources and regenerate where appropriate
Action Measures Comments/ Progress StatusIntervention type
Deliver Housing Investment Programmes to improve
the energy efficiency of the Council’s existing homes
Mitigation £32.338m of refurbishment works were approved for 2025-26
of which £9.779m is targeted towards energy efficiency works.
An external wall insulation project has delivered upgrades in
Forth, Larkhall and Hamilton. A cavity wall insulation project is
also being delivered SLC wide with 55 properties completed in
Forth and work ongoing at 60 properties in Hamilton.
Green
Page 48 of 71
70

Page 71

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
Place and Communities
Progress a transition to net-zero, energy efficient and climate resilient homes, buildings and infrastructure, and minimise the unsustainable use ofnatural resources and regenerate where appropriate
Action Measures Comments/ Progress StatusIntervention type
Deliver the Council’s affordable housing supply
programme to increase the proportion of new, energy
efficient homes with clean heating systems
Mitigation The delivery of the Council's new build programme is driven by
national and local sustainable development strategies. All new
homes are built to Silver Greener Standard as set out in
Section 7, Silver Level, of the 2011 Building Regulations in
respect of both carbon dioxide emissions and energy for space
heating. All Strategic Housing Investment Plan (SHIP) sites
that have been granted planning approval from February 2023
are being built to zero greenhouse gas emissions, using
additional grant subsidy support from the Scottish Government
to help meet the cost of achieving the standards. Work is due
to commence in quarter three 2025/26 at two Council sites
where air source heat pumps will be used to heat the homes,
with further projects in design development stages.
In addition to providing clean heating systems, modern
construction methods are utilised as far as possible to help
minimise adverse environmental impacts.
Green
Page 49 of 71
71

Page 72

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
Place and Communities
Progress a transition to net-zero, energy efficient and climate resilient homes, buildings and infrastructure, and minimise the unsustainable use ofnatural resources and regenerate where appropriate
Action Measures Comments/ Progress StatusIntervention type
Prepare for the
introduction of the new
Social Housing Net Zero
Standard (SHNZS)
Develop South Lanarkshire Council’s strategic
approach to meeting the new standard
Mitigation The Scottish Government have delayed the introduction of the
new SHNZS until 2026. Officers continue to keep up with
guidance and emerging developments on the SHNZS. The
Council’s strategy will be developed once the details of the
standard are known.
In the meantime, consultants have been procured to complete
a detailed analysis of the Council’s domestic estate to outline
key actions that can be taken to align with SHNZS, based on
the proposals in the consultation document.
Green
Develop South
Lanarkshire’s Local
Heat and Energy
Efficiency Strategy
(LHEES) and Delivery
Plan
Work with the relevant lead partners to implement
the agreed Delivery Plan for 2025-26
Mitigation,
Adaptation and
Sustainable
Development
The LHEES Cross-Resource Delivery Group has been
established with representation from across the Council. As
part of the group’s remit, lead officers will refine actions or
initiatives, including the addition of timescales or milestones.
The group meets every eight weeks and will continue to review
the proposed priority actions for 2025-26.
Green
Prepare for the
introduction of the new
Heat in Buildings Bill in
2025
Develop South Lanarkshire Coucil's strategic
approach to meeting the new standard following
publication of the new Scottish Government
legislation in 2025
Mitigation,
Adaptation and
Sustainable
Development
On 18 November 2025 the Scottish Government confirmed
that they would not introduce a Heat in Buildings Bill during
this parliamentary session. The Scottish Government intend to
introduce a bill in the next parliament.
SLC will feed into any future consultation on the contents of a
bill.
Report Later
Page 50 of 71
72

Page 73

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
Place and Communities
Progress a transition to net-zero, energy efficient and climate resilient homes, buildings and infrastructure, and minimise the unsustainable use ofnatural resources and regenerate where appropriate
Action Measures Comments/ Progress StatusIntervention type
Utilise the Central
Energy Efficiency Fund
(CEEF) Programme to
deliver energy efficiency
improvement projects in
Council non-domestic
buildings
Implement the agreed CEEF delivery plan for
2025-26
Mitigation This action is on target. A report on the 2024-25 - 2025-26
programme was approved by CMT on 29 May 25. All projects
in the 2024-25 programme are now complete and all projects
in the 2025-26 programme are on target to complete within the
current financial year.
Green
Page 51 of 71
73

Page 74

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
Place and Communities
Progress a transition to net-zero, energy efficient and climate resilient homes, buildings and infrastructure, and minimise the unsustainable use ofnatural resources and regenerate where appropriate
Action Measures Comments/ Progress StatusIntervention type
Support the delivery of
Climate Ready Clyde's
(CRC) Adaptation
Strategy
Continue as an active member of the CRC Local
Authority Forum participating in city-region wide
workshops and events, creating connections and
opportunities for development/co-sharing of
knowledge and training by 2026
Adaptation South Lanarkshire Council remains an active member of the
Climate Ready Clyde (CRC) local authority forum, which meets
quarterly to support collaborative climate adaptation across the
Glasgow City Region. Through this forum, officers contribute to
shared planning, knowledge exchange, and the delivery of
integrated climate adaptation actions.
Throughout the year, officers have actively participated in CRC
workshops and progress meetings, helping shape the forum’s
work programme. These sessions have supported connections
with other local authorities and created opportunities for
shared learning and future collaboration.
As part of Climate Ready Clyde and the associated Public
Sector Climate Adaptation Network, officers have attended
several upskilling sessions including a session most recently
on adaptation reporting requirements under the Public Bodies
Climate Change Duties. In May 2025 CRC also facilitated a
collaboration event for all CRC local authority members and
Climate Action Hubs within the region to work towards better
collaborative working.
Green
Page 52 of 71
74

Page 75

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
Place and Communities
Progress a transition to net-zero, energy efficient and climate resilient homes, buildings and infrastructure, and minimise the unsustainable use ofnatural resources and regenerate where appropriate
Action Measures Comments/ Progress StatusIntervention type
Begin development of an adaptation plan in line with
emerging Scottish Government guidance
Adaptation The Scottish Government's update to the Climate Change
Duties - Statutory Guidance is anticipated to provide guidance
and best practice with respect to creating an adaptation plan.
While waiting for this, the Sustainability team have started
work to assess risk to the Council as a result of hazards
associated with climate change. This will help to identify
actions for inclusion in South Lanarkshire Council's adaptation
action plan.
Green
Benchmark the
Council's performance
against Adaptation
Scotland's climate
change adaptation
maturity levels
Reassess the Council against Adaptation Scotland's
Capability Framework and use the results to
benchmark current performance and identify key
actions for improvement and progression
Adaptation A capability assessment was undertaken using Adaptation
Scotland's benchmarking tool in early 2025. The exercise
identified a number of improvement actions for the Council for
the coming year which would enable the Council to build its
adaptation capacity. These actions have been built into the
Sustainable Development and Climate Change Strategy
(SDCCS) Action Plan for 2025-26. The benchmarking
assessment will be carried out again later this year to assess
progress against the previous year's scoring.
Complete
Improve efficiencies in
recycling collection
routes
Design a re-routing project for kerbside recycling
services by March 2026
Mitigation Work on the routing project continues. Collection calendars
are already available online for residents who have registered
for the portal. The Service is working with IT and the
Improvement Service to integrate the portal with My Account to
improve the user experience.
Green
Page 53 of 71
75

Page 76

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
Place and Communities
Empower communities to take climate action and be more environmentally sustainable
Action Measures Comments/ Progress StatusIntervention type
Support the remediation
of vacant and derelict
land that promotes
social and
environmental benefits
Support Clyde Gateway Urban Regeneration
Company in further remediation works in the next
phase at Shawfield Phase 2
Adaptation Work led by Clyde Gateway is ongoing and being delivered on
budget and programme. Clyde Gateway are currently in the
process of tendering for work on sites which have been
subject to Chromium 6 contamination. Remediation works are
anticipated to commence spring 2026.
Green
Natural Environment (Planet)
Improve the availability and access to quality local outdoor spaces and services
Action Measures Comments/ Progress StatusIntervention type
Ensure national
planning policy set out in
National Planning
Framework 4 in relation
to climate change,
biodiversity and
sustainable travel is
Gather and assess data on these topics for inclusion
in the Evidence Report for LDP3 and to aid decision
making. Evidence report to be presented to Full
Council by September 2025
Sustainable
Development
Data gathering, assessment and consultation has been
ongoing, and was reflected in the Evidence Report presented
to the Executive Committee on 5 November 2025 in line with
timescales for reporting to Full Council on 10 December 2025.
Amber
embedded in decision
making process for
planning applications
and the preparation of
the South Lanarkshire
Local Development Plan
3.
Provide guidance and deliver awareness and training
for Development Management colleagues and key
stakeholders on how to consider climate change and
sustainability topics when assessing planning
applications, utilising the State of the Environment
Report as an evidence base and the approved
Placemaking Guide. This will be augmented by
planning guidance proposed by the Scottish
Government in 2025-26
Sustainable
Development
The Scottish Government published planning guidance on
climate mitigation and adaptation in support of NPF4 policy on
this topic in June 2025 and this is now a material consideration
when assessing planning applications. A first stage
Placemaking in South Lanarkshire document has been
approved and published. This will be augmented by more
detailed guidance which it is intended will be presented to the
Planning Committee in 2026-27.
Amber
Page 54 of 71
76

Page 77

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
Natural Environment (Planet)
Improve the availability and access to quality local outdoor spaces and services
Action Measures Comments/ Progress StatusIntervention type
Update the current State
of the Environment
Report
Collaborate with Council Resources to prepare the
2025 edition of the biennial State of the Environment
Report for South Lanarkshire by 31 March 2026
Sustainable
Development
Good progress is being made in preparing the draft 2025 State
of the Environment Report. There are no issues anticipated in
the development of the report by the end of 2025-26.
Green
Prepare an Open Space
Strategy
Present a draft Open Space Strategy to Planning
Committee by end of September 2025
Sustainable
Development
The recent focus has been on the preparation of a Play
Sufficiency Assessment which is required to be included with
the Local Development Plan (LDP) Evidence Report.
The Open Space Strategy (OSS) will flow from, and be
informed by this, therefore programming has been put back to
2026. This will also allow it to be informed by the LDP3 Call for
Ideas taking place in the first half of 2026.
In the meantime, a detailed assessment of the open space
audit has been carried out together with extensive
engagement.
Amber
Carry out statutory consultation on the draft Open
Space Strategy in November 2025
Sustainable
Development
Due to the reprogramming of the Open Space Strategy (OSS),
consultation on the draft strategy will be delayed.
However, extensive engagement to gather views on the quality
and quantity of open space has been carried out and this will
inform the draft OSS.
Amber
Final approval of the Open Space Strategy by June
2026
Sustainable
Development
Changes to the timescale for preparing the Open Space
Strategy (OSS) means that the June 2026 target will not be
met. However, information received through the Local
Development Plan (LDP) Evidence Report process and the
Play Sufficiency Assessment production will minimise slippage.
Amber
Page 55 of 71
77

Page 78

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
Natural Environment (Planet)
Improve the availability and access to quality local outdoor spaces and services
Action Measures Comments/ Progress StatusIntervention type
Provide an effective and
efficient grounds
maintenance service
Retain Green Flag accreditation at previously
nominated parks, expand on this through work with
other friends of groups and develop into other
categories
Sustainable
Development
Green flag status retained and routine winter operations within
designated parks scheduled in line with Park
management/Green Flag plans.
Green
Enhance, protect, and respect the outdoors and the natural and historic environment.
Action Measures Comments/ Progress StatusIntervention type
Make South Lanarkshire
a cleaner place to live,
work and visit, free of
litter, fly-tipping and dog
waste through
progression of actions in
the Litter Strategy
(2022-2027)
Continue to progress actions on reducing litter,
fly-tipping and dog waste in South Lanarkshire
through working with stakeholders, partners and
community groups as per the Litter Strategy Action
Plan (2022-2027)
Sustainable
Development
The annual progress report for the Litter Strategy was
presented to the Climate Change and Sustainability
Committee on the 12 November 2025.
Updates have been provided to the Litter Strategy Steering
Group and included within the body of the report and action
plan update to CCS Committee.
Green
Page 56 of 71
78

Page 79

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
Natural Environment (Planet)
Conserve, restore and improve biodiversity, and use nature-based solutions in tackling the climate crisis
Action Measures Comments/ Progress StatusIntervention type
Review Council use of
herbicide with a view to
reduce the amount used
Continue to look at alternative methods to control
weeds and identify further potential trials during
2025-26
Sustainable
Development
Work on alternative methods of weed control continues and
Grounds Services are constantly reviewing options. Grounds
Services have more recently been reviewing application rates
and use of wetting agents to reduce the dosage required of the
herbicide.
Green
Measure and increase
tree canopy cover
across South
Lanarkshire
Across South Lanarkshire, continue to measure /
assess existing tree canopy cover and tree equity
Adaptation In partnership with the Clyde Climate Forest (CCF) and with
tools such as Tree Equity Score UK, the council continues to
measure and assess tree canopy cover and tree equity. Tree
Canopy Cover (TCC) shown by ward is set out in table 2.6 of
South Lanarkshire State of the Environment Report 2023
Chapter 2 Biodiversity, Fauna and Flora and illustrated in the
CCF interactive map for Urban Tree Canopy (UTC). The
current overall TCC is approximately 17% with a strategic
target of 21% by 2032. Similarly the UTC as assessed by CCF
is 17.2% with a target of 20% by 2032.
Green
Page 57 of 71
79

Page 80

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
Natural Environment (Planet)
Conserve, restore and improve biodiversity, and use nature-based solutions in tackling the climate crisis
Action Measures Comments/ Progress StatusIntervention type
On Council owned or controlled land, continue to
develop records of the nature, condition, resilience
and management of tree assets
Adaptation On Council owned or controlled land, the council continues to
enhance its records of the nature, condition and resilience of
tree assets through assessment and ongoing development of
its Tree Asset Management System. This approach to data
collection, improved reporting and landscape level analysis is
beginning to inform a deeper insight into the composition and
structure, resilience, benefits and management strategies.
Furthermore, this approach is also aiding an insight into assets
that form part of the developing Broad Leaved Nature Network
(Glasgow City Region initiative), and species for future planting
schemes.
In addition, the Council is actively developing Urban Woodland
Management Plans (UWMP)  for both country parks. Longer
term, a further 12 other UWMPs aimed at improving long-term
resilience, biodiversity, community engagement and access
are planned.
Green
Page 58 of 71
80

Page 81

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
Natural Environment (Planet)
Conserve, restore and improve biodiversity, and use nature-based solutions in tackling the climate crisis
Action Measures Comments/ Progress StatusIntervention type
On Council owned or controlled land, continue to
identify sites suitable for planting tree assets to
improve canopy cover, species diversity and tree
equity and continue to develop a masterplan with a
prioritised delivery plan
Adaptation Work regarding the Clyde Climate Forest (CCF)  'opportunities
for tree establishment on Council-owned or controlled land'
study is ongoing, with further refinement, site-specific
assessments and continued collaboration with CCF. The
identified opportunities span various scales of planting, each
with potential to positively contribute to increased canopy
cover. The study has been submitted for inclusion in the LDP3
Evidence Report. Using the Tree Asset Management System,
a dynamic five-year planting masterplan is currently under
development. Although full integration of the study is pending,
787 sites and 2,856 standard trees are already undergoing
assessment. Site prioritisation is informed by the Tree Equity
Score, the CCF, the Broadleaved Nature Network
development, and available resources.
Green
Page 59 of 71
81

Page 82

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
Natural Environment (Planet)
Conserve, restore and improve biodiversity, and use nature-based solutions in tackling the climate crisis
Action Measures Comments/ Progress StatusIntervention type
Seek additional funding for tree and woodland
assets through internal and external sources,
including community groups
Adaptation The Scottish Government have provided £20k for developing
tree planting projects on private vacant and derelict land, and
additional funding through the Nature Restoration Fund, and
from Future Woodlands Scotland targeting low Tree Equity
areas and Clyde Climate Forest target areas. The Tree
Warden Scheme through the CCF continues along with a new
Tree Council 'Growing Together Pilot' initiative linking schools
with Community Tree Nurseries to grow and care for trees
locally. Other identified funding options for tree planting include
Woodland Trust, Trees for Cities, The Tree Council, and The
Conservation Volunteers.
Green
Page 60 of 71
82

Page 83

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
Natural Environment (Planet)
Conserve, restore and improve biodiversity, and use nature-based solutions in tackling the climate crisis
Action Measures Comments/ Progress StatusIntervention type
Work with regional partners to deliver the Clyde
Climate Forest Concordat
Adaptation The Council continues to work closely with regional partners to
deliver the Clyde Climate Forest Concordat. Schools are now
active in the national Tree Champions programme,
establishing orchards, edible hedges and pollinator habitats
while developing pupils’ understanding of trees and climate
resilience.
Growing Together Pilot – This new South Lanarkshire/The
Tree Council pilot initiative links schools with Community Tree
Nurseries (CTN) to grow and care for trees locally. Three
School Community Tree Nurseries will be established in Clyde
Climate Forest (CCF) target neighbourhoods with support to a
further 10 with Orchard packs this financial year.
Green
Page 61 of 71
83

Page 84

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
Natural Environment (Planet)
Conserve, restore and improve biodiversity, and use nature-based solutions in tackling the climate crisis
Action Measures Comments/ Progress StatusIntervention type
Increase biodiversity
and invest in peatlands
across South
Lanarkshire
Participate in the Clyde Peatlands Project to bring
about a step change in the scale and rate of
peatland restoration across the City Region
Adaptation Due to the Nature Restoration Fund (NRF) not being awarded
in 2024-25, there has been a delay to this work. However the
NRF award for 2025-26 has enabled a number of projects to
progress. The contracts for the peatland feasibility surveys
were awarded and works commenced in December 2025 and
are due to complete by April 2026. This will allow the Council
to approach NatureScot to access the Peatland Action Fund in
future and with an aim to work with the Clyde Peatlands Officer
in restoring the peatlands at Mossneuk and Langlands Moss
Local Nature Reserves to protect the carbon reserves stored
in these sites.
Amber
Page 62 of 71
84

Page 85

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
Natural Environment (Planet)
Conserve, restore and improve biodiversity, and use nature-based solutions in tackling the climate crisis
Action Measures Comments/ Progress StatusIntervention type
Work with key partners including the Clyde
grasslands and Clyde wetlands projects to identify
and establish regional nature networks
Adaptation Nature Network projects include:
- Wetland restoration work in partnership with Froglife - a three
year Heritage Lottery Fund project (2025- 2028) creating and
restoring over 30 wetland sites in five Local Nature Reserves
and one Country Park.
- The Countryside and Greenspace Team (CAG) continue to
expand the areas of wildflower grassland throughout South
Lanarkshire, identifying and creating new wildflower sites for
pollinators, linking to and expanding our grassland nature
networks.
- In 2025 CAG purchased a layer in the Council's Treeplotter
software to map grassland pollinator sites throughout the
region. This will allow SLC to manage assets more effectively,
providing information on wildlife surveys, habitat diversity,
photos, management regimes and areas.
Green
Page 63 of 71
85

Page 86

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
Natural Environment (Planet)
Conserve, restore and improve biodiversity, and use nature-based solutions in tackling the climate crisis
Action Measures Comments/ Progress StatusIntervention type
Continue to improve key ecosystems within our Local
Nature Reserves, Country Parks and green spaces,
utilising the Nature Restoration Fund
Adaptation The Nature Restoration Fund awarded in 2025-26 will be used
to improve grasslands, plant trees, remove invasive non native
species and restore habitats within our Local Nature Reserves
and greenspaces.
The Council is progressing plans for Local Nature Reserve
management plans and Urban Woodland Management Plans
to identify conservation tasks to enhance the reserves for
biodiversity, access and people.
Green
Page 64 of 71
86

Page 87

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
Natural Environment (Planet)
Conserve, restore and improve biodiversity, and use nature-based solutions in tackling the climate crisis
Action Measures Comments/ Progress StatusIntervention type
Participate in the delivery of national biodiversity
targets highlighted within the Scottish Biodiversity
Delivery Plan 2024-2030, where local authorities play
a key role in conserving, restoring and reducing
threats to biodiversity
Adaptation South Lanarkshire's Biodiversity Partnership group meet once
a year with representatives from NatureScot, SEPA, Scottish
Wildlife Trust, RSPB, Glasgow City Region (GCR) Green
Network and many more to discuss the progress of
conservation projects and national biodiversity targets. There
is also a nature networks development subgroup. The
Biodiversity Officer attends NatureScots Local Nature
Conservation Sites advisory group, GCR nature network
group, the National Nature Reserve partnership group and
meetings throughout the year hosted by NatureScot to discuss
the development of projects that meet the national biodiversity
objectives.
Green
Encourage uptake of the
Oracle Fusion online
training course 'Your
Biodiversity Duty' by
Council employees and
Elected members
Promote course uptake through communications via
Officers Groups and Communications and Strategy
Resource
Adaptation The online learning course titled 'Biodiversity - It's Your Duty'
has been updated to include the targets within the National
Biodiversity Strategy 2045 and highlights the biodiversity
projects in South Lanarkshire. The course is available to all
employees and elected members within the Council.
The Biodiversity Officer and CAG have highlighted this course
within presentations including the Strategic Environmental
Assessment officers group and within Climate Change and
Sustainability Committee meetings. The course was also
promoted via internal email to all Council employees as part of
Climate Week 2025.
Green
Implement new
technologies and more
sustainable cleaning
materials within Council
facilities
Continue to research and assess new sustainable
cleaning technologies and consider piloting them if
appropriate
Sustainable
Development
The Aquateck system is still in use across Council premises,
and is working well. New cleaning chemicals have been
deployed in all primary schools which have reusable bottles
and quarterly deliveries are now in place to reduce delivery
related emissions.
Green
Page 65 of 71
87

Page 88

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
A Green Economy (Planet)
Take action to allow South Lanarkshire to become a zero-waste society
Action Measures Comments/ Progress StatusIntervention type
Work to support SME’s
in accessing wider
business support in
relation to climate
change and net zero,
Establish connections with organisations such as
Business Gateway Lanarkshire and Scottish
Enterprise to build capacity and share knowledge in
relation to climate change, net zero and circular
economy
Sustainable
Development
South Lanarkshire Council co-manage Business Gateway with
North Lanarkshire Council, this allows us to ensure that our
business base can access financial and practical advice to
support their green journey. We have regular contact with
Scottish Enterprise at senior and operational levels.
Green
including the circular
economy
Promote the Expert Help programme to SMEs Sustainable
Development
The Council and colleagues in the Business Gateway, who
provide face to face business support, regularly promote the
Expert Help programme via social media.
A case study has also been prepared and Business Gateway
provide an introduction to the project to all eligible clients.
Green
Review waste services
(infrastructure and
collection services) in
line with delivering
current and future waste
legislation (including the
circular economy)
Continue to undertake a review of the waste service
through 2025-26 that will determine most efficient
refuse and recycling collection services and related
waste services infrastructure
Mitigation The review of Waste Services is complete and the Circular
Economy Act Scotland 2024 has now been published. The
Service continues to consider the potential implications that
the statutory code of practice (due to be published by end of
financial year 2025-26) will have on household waste
collection services in South Lanarkshire.
Complete
Review of recycling bins
at flatted properties in
South Lanarkshire
Continue to review and implement improvements to
existing collection arrangements at flats during
2025-26 and monitor progress and address any
issues identified
Mitigation The flat project was completed in March 2025. Over 18,000
properties now have access to dual stream recycling.
Monitoring of the quality of the material being collected
continues and the Waste Education Team visit areas identified
as being problematic to engage in education / intervention
activities.
Green
Page 66 of 71
88

Page 89

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
A Green Economy (Planet)
Take action to allow South Lanarkshire to become a zero-waste society
Action Measures Comments/ Progress StatusIntervention type
Manage and monitor
food waste in schools
Explore opportunities for pilot projects aimed at
reducing food waste in schools
Mitigation Aligning with the global Stop Food Waste Day in April 2025, a
theme day was carried out in primary schools to raise
awareness on tackling the issue of food waste. 75 schools
took part, the menu included the top five menu choices to
encourage children to eat everything on their plate and
information sheets prepared illustrating how leftover foods
such as pepper seeds and potatoes can be harvested and
cultivated to be used in future meals.
Green
Support the transition to
a circular economy by
increasing the use of
recycled equipment
Audit and work to increase the use of recycled stock
as a percentage of all Equipu activity
Mitigation and
Sustainable
Development
To date there have been a total of 2,239 items issued, of which
(16%) 363 were recycled. The service is currently on track to
meet and exceed the performance target this financial year.
The service's ability to achieve the target as they progress
through the year will be determined by the availability of
recycled equipment within the Equipu store. In quarter two,
there was a total of 1,049 items, of which 18% (190) were
recycled.
Green
Page 67 of 71
89

Page 90

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
A Green Economy (Planet)
Enable a fair transition to a green economy leaving no one behind
Action Measures Comments/ Progress StatusIntervention type
Deliver the UK Shared
Prosperity Fund to help
ensure a just transition
to net zero
Progress delivery of the UK Shared Prosperity Fund
to fund initiatives that support the Council,
communities, and businesses transition to net zero
Sustainable
Development
The UK Shared Prosperity Fund (UKSPF) was extended to 31
March 2026 and is supporting a range of projects including:-
1.The provision of a ‘One Stop Shop’ for domestic retrofit
and energy advice as a means of supporting residents and
homeowners in the South Lanarkshire area to upgrade their
homes.
The project provides advice across four defined geographical
areas (1. Clydesdale Area, 2. Cambuslang & Rutherglen Area,
3. East Kilbride Area, 4. Hamilton Area) which allows it to meet
the specific priorities in each area.
2.Construction of net zero industrial units (making them
as sustainable as possible) at Cathcart Road, Rutherglen.
Green
Consider climate
change impacts on the
Council’s workforce in
the workforce plan
including need for green
skills
Consider the impact of climate change and the need
for new or additional skills or knowledge as part of
the Resource workforce planning process in 2025-26
Adaptation The Council Workforce Plan was approved at Executive
Committee on 28 May 2025 which includes actions to expand
skills and knowledge to enable the delivery of climate actions.
In addition, individual Resource workforce plans were
approved at the Resource Committee in September / October
2025. The Resource Workforce Plans include actions to
address skills and knowledge gaps to support the delivery of
the Sustainable Development and Climate Change Strategy.
Complete
Page 68 of 71
90

Page 91

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
A Green Economy (Planet)
Enable a fair transition to a green economy leaving no one behind
Action Measures Comments/ Progress StatusIntervention type
Engage with employers
to provide workforce
up-skilling and re-skilling
support to meet the
needs of the transition to
a green and circular
economy
Connect with businesses to help them grow and
upskill their current workforce to adapt to industry
requirements
Adaptation Through the Council's management of the Business Gateway,
who now deliver face to face business support, the Business
Grant and Expert Help programme are both promoted and
made available. These opportunities can both be utilised for
net zero support and projects.
All applicants to the Business Grant are asked to provide a
copy of the Scottish Enterprise Net Zero accelerator tool with
their application.
Green
Develop a strategic
approach to increase
the number of young
people obtaining the
skills to access Green
Economy jobs
Identify senior phase vocational learning
opportunities that prepare young people for the
green economy
Adaptation Through our GradU8 programme, we collaborate with South
Lanarkshire College and New College Lanarkshire to offer
senior phase vocational courses in areas such as engineering
and construction. These vocational areas specifically
incorporate key elements of sustainability, and emerging
opportunities related to green jobs in their industries,
equipping young people with foundational knowledge and
preparing them for future opportunities within the green
economy. Many students are able to progress onto further
learning at college to study courses designed for green
economy related jobs.
Green
Page 69 of 71
91

Page 92

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
A Green Economy (Planet)
Lead the transition to a circular economy and improve resource efficiency through responsible consumption and production, and buying and sellingof local goods and services
Action Measures Comments/ Progress StatusIntervention type
Utilise Scottish
Government’s Flexible
Framework Assessment
Tool to assess current
level of performance to
realise intended
sustainable outcomes
Work to progress towards Level 4 of the Flexible
Framework to show continuous progression in
embedding consideration of climate change and
sustainability in procurement activity and outcomes
Sustainable
Development
Level 4 of the Flexible Framework has been achieved for
People and Objectives and we are working towards level 4 for
Processes, Stakeholders and Reporting by March 2026.
Green
Improve contract
management of
sustainability factors
through the Council’s
new electronic appraisal
process
Monitor sustainability measures and KPIs in
contracts to ensure sustainability performance and
achievement of intended sustainability outcomes
Sustainable
Development
KPI monitoring arrangements are in place for contracts,
including sustainability measures where stipulated in the
contract. There are plans to move high risk, high value
contracts to Fusion electronic contract performance
management by March 2026.
Green
Implement an updated
approach to whole life
costing based on the
Sustainable
Procurement Toolkit
Develop a new approach in consultation with
Resources to support specification and evaluation of
tenders
Sustainable
Development
The Council continues to consider environmental and social
issues when purchasing goods and services. The Council
adheres to the Sustainable Procurement Duty to ensure that
regulated procurements:
- Improve the economic, social and environmental wellbeing of
the authority area, with a particular focus on reducing
inequality.
- Facilitate the involvement of small and medium enterprises,
third sector bodies and supported businesses.
- Promote innovation.
The new sustainable procurement process has been rolled out
to all Resources and now fully embedded. Guidance has been
created for sustainability questions in relation to tender
specification and evaluation.
Complete
Page 70 of 71
92

Page 93

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 2 February 2026 11:30:06am
Sustainable Development Strategy Improvement Actions
A Green Economy (Planet)
Support South Lanarkshire’s businesses in the transition to a net-zero economy and helping to ensure they are climate resilient
Action Measures Comments/ Progress StatusIntervention type
Promote the support
that is available to
businesses for good
sustainability outcomes
Publicise funding opportunities and share
information with businesses for carbon emission
reduction and improved energy performance
Sustainable
Development
The Council, and partners in the Business Gateway, regularly
publicise the Council's business grant, which can be used for
projects exclusively aimed at supporting a businesses' journey
to net zero.
The Expert Help programme also has net zero as one of the
lots available for support. This means that SLC businesses
can have up to five days fully funded support with a net zero
consultant to support them on their journey.
Green
Promote and encourage
the use of bespoke
Lanarkshire sustainable
tourism resources,
commissioned via
Green Tourism
Engage tourism businesses to uptake more
sustainable practices utilising the resources situated
on the VisitLanarkshire website
Sustainable
Development
The Council aims to continue to actively promote and
encourage the use of the bespoke Lanarkshire sustainable
tourism resources commissioned via Green Tourism.
The Economic Development Team will continue to push for
greater uptake of these resources through a variety of
platforms and engagements, ensuring that sustainability
remains a key focus for businesses in Lanarkshire’s tourism
sector.
Green
Page 71 of 71
93

Page 94

94

Page 95

Report
Agenda Item 
Report to: Climate Change and Sustainability Committee
Date of Meeting: 11 February 2026
Report by: Executive Director (Community and Enterprise
Resources)  
Subject: Sustainable Development and Climate Change Strategy
5-Year Action Plan – Mid Point Review 
1. Purpose of Report
1.1. The purpose of the report is to:-
[purpose]
 update Committee on progress made against the Sustainable Development and
Climate Change Strategy (SDCCS) 5 Year Action Plan (April 2022 to March
2027)
[1purpose]
2. Recommendation(s)
2.1. The Committee is asked to approve the following recommendation(s):-
[recs]
(1) Note the progress made against the SDCCS 5 Year Action Plan. 
(2) Approve the ongoing actions and next steps as outlined in this report. 
[1recs]
3. Background
3.1. The Sustainable Development and Climate Change Strategy (SDCCS) 2022 to 2027
was approved by South Lanarkshire Council on 15 June 2022. This Strategy sets out
the Council’s approach to developing sustainably and tackling the climate
emergency over a five-year period, while also providing a broad strategic direction
for longer-term planning. The aim is to deliver on agreed outcomes and contribute to
a long-term vision for a more sustainable, resilient, and equitable South Lanarkshire. 
3.2. The focus of South Lanarkshire Council’s 5 Year SDCCS is to deliver a coordinated,
ambitious response to the climate emergency by embedding sustainability across all
Council activities, reducing carbon emissions, enhancing resilience, and supporting a
fair transition to net zero. To support delivery of the SDCCS an associated
overarching 5-year action plan was developed, alongside more detailed annual
action plans which are approved by, and reported biannually to, the Climate Change
and Sustainability Committee. A copy of the 5-year action plan can be found here or
on request. The plans set out clear priorities and actions to improve health and
wellbeing, promote climate justice, empower communities, protect and restore the
natural environment, and drive economic transformation, highlighting achievements,
challenges, and next steps across the Council’s 13 strategic priorities. 
3.3. Delivery of the actions within the Strategy and associated Action Plan forms the main
focus for sustainable development activity across the Council. This work enables the
Council to fulfil its statutory duties under the Local Government (Scotland) Act 2003,
the Climate Change (Scotland) Act 2009, and to contribute to the United Nations
5
95

Page 96

Sustainable Development Goals (SDGs). The Council’s activities are designed to
support public sector climate change duties, biodiversity obligations, and the wider
sustainability agenda. 
3.4. The most recent annual action plan for 2025-2026 was approved by the Climate
Change and Sustainability Committee in March 2025, which was the third such
annual action plan under the 5-year plan. Progress against the actions in the annual
plans are monitored using the Council’s IMPROVe system and reported to the
Committee at Quarter 2 and Quarter 4 each year. This robust monitoring framework
ensures transparency and accountability, enabling the Council to track
achievements, identify challenges, and adjust actions as needed. 
3.5. This report is not intended as a forensic analysis of the progress of the 5-year action
plan - the biannual updates to Committee on the annual action plans provide that
level of granular detail and should be referred to for further information. This report
has been prepared to provide a high-level overview of progress made against the
priority actions of the 5-year Action Plan, and to identify areas of further attention in
forthcoming annual action plans in 2026/2027 and 2027/2028. 
4. Progress to Date
4.1. This section provides an overview of the progress made against each of the 13
strategic priorities, including information on delivery of associated actions and steps
for each priority. The progress updates also include an indication of the status of
each action, with green indicating ‘on track’, amber indicating ‘minor slippage’, and
red indicating ‘not on course’. 
Action Progress Status
Priority 1: Contribute to improving health and wellbeing through environmental protection and access
to environmental benefits for all
Air Quality
Projects
Annual applications to the Scottish Government’s Air Quality Grant
Fund continue to enable air quality projects, with measurable
improvements reported and case studies developed. Progress includes
revocation of two air quality management areas.
Green
Contaminated
Land
Ongoing statutory work, including maintenance of public register.
Projects to remove sites from the Vacant and Derelict Land Register
continue to be implemented and Planning advice provided in support of
this.
Green
Healthy &
Sustainable
Food
Campaigns and food programmes implemented in line with previous
Council Good Food Strategy; partnership working ongoing. 
Green
Heat Risk Adverse weather including heat risk has been incorporated into
corporate risk register and mitigation/control measures in place. The
ongoing Strategic Climate Change Risk and Opportunity Assessment
will provide further detail on risks associated with heat to the Council.
Green
Priority 2: Progress climate justice and ensure the transition to net-zero by 2045 does not exacerbate
poverty or inequalities
Climate
Vulnerability
Impact Study
PhD student-led research underway, providing baseline for targeted
interventions. Study will investigate South Lanarkshire communities’
climate vulnerability and make policy recommendations to address.
Green
Fuel Poverty
Review
Work superseded by Fuel Poverty Sub-group/LHEES; ongoing
investment in energy efficiency both within Council properties and
owner occupiers. Key LHEES priority is to remove poor energy
performance as a driver of fuel poverty.
Green
Heat
Decarbonisation
A number of feasibility studies and pilot projects have been delivered
with more in progress. These include social housing net zero report
completed, heat network feasibility studies in progress, and structural
Green
96

Page 97

Action Progress Status
surveys to a number of properties.
Food Security Community engagement ongoing, work to be progressed in line with
Good Food Nation planning. 
Amber
Emergency
Preparedness
Routine response to weather alerts established with summer
preparedness information in development to support work addressing
risk from heat and overheating.
Green
Sustainable
Development
Goals
Localisation
The SDG’s have been mapped against South Lanarkshire’s
Community Plan and ongoing work in the delivery of the Plan aligns
with the Goals.
Green
Priority 3: Influence change through improving the understanding of Sustainable Development and
the Climate
Training Climate emergency and sustainability training has been rolled out to
staff and elected members. This has included accredited Climate
Emergency training from Keep Scotland Beautiful and development of
bespoke internal modules. More widely, digital delivery of training
prioritised across the Council with majority of training available through
Fusion. Opportunities for development of training options continue to
be monitored.
Green
Communications Annual climate change and sustainability communications plans in
place, with regular updates to Committee provided and key case
studies and stories promoted to South Lanarkshire VIEW. The
anticipated redesign of the Council’s website will consider how best to
incorporate sustainability information.
Green
Decision-
Making Tools
A Sustainability Impact Assessment (SIA) has been developed and
included within the Council’s wider Integrated Impact Assessment
process (IIA). The SIA includes consideration of carbon impacts and
impacts of future climate scenarios. Training has been developed to
support the roll out and use of the SIA tool with promotion and training
delivery ongoing.
Green
Town Centre
Visioning & Net
Zero
The ongoing town centres redevelopment continues to be guided by
the completed town centre net zero study. Masterplans for Hamilton
and East Kilbride have been prepared and approved by Executive
Committee.   
Green
Youth
Engagement
Pupil and youth forums active, influencing council policy. Work is
ongoing to understand and influence carbon footprints within school
communities. Schools continue to develop sustainability resources
across all education settings. Key successes in the development of the
Youth Forum for sustainability and in the delivery of multiple
Conference of Schools events.
Green
Community
Engagement
Community grants programmes have enabled significant community
involvement in sustainability projects, with targeted communications
campaigns designed to support community action. Adult learning
opportunities continue to be delivered. Work ongoing to build
collaborative relationship with Lanarkshire Climate Action Hub.
Amber
Priority 4: Improve affordable, sustainable, and accessible transport options
Active Travel Cycle network and EV charging infrastructure expanded; public
transport enhancements ongoing. Update on Active Travel
infrastructure to be presented to Committee in 2026.
Green
Fleet
Decarbonisation
Continued progress made in decarbonising the Council’s fleet vehicles
in line with 2030 targets. Funding challenges noted with respect to the
cost of EVs and the financial resources available to the Council,
alongside challenges in the availability and procurement of heavy fleet
vehicles (e.g. buses, refuse collection vehicles etc.).
Amber
Residential
Design
Climate and active travel considerations integrated into new
developments considering guidance within the new Place-Making
Guide. 
Green
Employee Travel The staff travel plan is currently under review and will be presented to
Committee in due course. 
Green
97

Page 98

Action Progress Status
Cycle Friendly
Employer
Status maintained and options for expansion are reviewed
continuously.
Green
Priority 5: Progress a transition to net-zero, energy efficient and climate resilient homes, buildings,
and infrastructure, and minimise the unsustainable use of natural resources and regenerate where
appropriate
Emissions
Reduction
A Route map for reducing the Council’s Scope 1 emissions in line with
national targets is in development for presentation to Committee.  The
route map will consider timescales, milestones, and costs. Regular
reporting to Committee on emissions reductions are provided, including
baseline information. Where data is available, new emissions sources
will be included in the baseline, specifically with regards to Scope 3
emissions.
Green
Flood Risk Projects to reduce flood risk continue to be implemented across South
Lanarkshire in line with available resources; ongoing monitoring.
Green
Digital Services Online service provision has been expanded where possible to reduce
need for travel. Options for further digitisation of services continue to
be explored and will form part of Council website redesign.
Green
Building
Standards
Compliance with new energy standards continued to be monitored and
implemented in line with national developments; ongoing training
delivered to Council staff to ensure compliance.
Green
Housing Stock The Council awaits the publication of new energy efficiency standard
for housing by the Scottish Government. This has been delayed and is
expected to be made available in 2026, alongside further information
relating to the revised Heat in Buildings Bill.
Amber
Adaptation Participation in Climate Ready Clyde partnership ongoing, the Council
also utilises Adaptation Scotland capabilities framework benchmarking.
Ambition to develop an adaptation plan in line with national guidance
when it is available and upon completion of climate change risk
assessment.
Green
Priority 6: Improve the availability and access to quality local outdoor spaces and services
Local
Development
Plan 3
Statutory process for the development of LDP3 is underway, aligned
with NPF4. Progress will be reported to relevant Committee at key
stages throughout.
Green
Open Space
Strategy
Strategy development in progress Amber
Local Food
Promotion
Work to develop this area will progress in line with Good Food Nation
Plan led by the Scottish Government. The final Plan was presented
December 2025 and work in line with this will be progressed over the
coming years. Campaigns and events to promote local food and drink
ongoing.
Green
Priority 7: Empower communities to take climate action and be more environmentally sustainable
Community
Grants
Climate Emergency Fund community grants have been fully allocated
and reports presented to Committee alongside case studies. Options
for the delivery of new grants programmes continue to be explored in
line with available finances.
Green
Public
Engagement
Annual communications plans continue to be implemented with regular
sustainability communications distributed via approved channels. The
Council continues to participate in high profile national campaigns,
including Climate Week and Recycle Week. The Council continues to
build its relationship with the recently established Lanarkshire Climate
Action Hub.
Green
Food Growing Opportunities for food growing continue to be explored and where
possible expanded; statutory obligations met.
Green
Vacant and
Derelict Land
Remediation
Projects at Cuningar Loop and Shawfield to remediate land are
progressing. Opportunities for further remediation works continue to be
explored in line with available funding.
Green
98

Page 99

Action Progress Status
Community
Wealth Building
Environmental considerations embedded within CWB Strategy delivery.
Sustainability considerations now embedded within SLC procurement
processes and skills development.
Green
Priority 8: Take action to allow South Lanarkshire to become a zero waste society
Waste Collection The review of recycling bins at flatted properties has been concluded
and recommendations implemented. The re-routing project considering
alternative refuse collection patterns continues and updates will be
presented to relevant Committee in due course.
Green
Training &
Printing
Options for sustainable training are reviewed and considered and
continued digitisation of Council Services is designed to reduce
unsustainable practices including digital certification. Reduced printing
implemented.
Green
Food Waste Awareness campaigns in schools are ongoing including Waste
Warriors, and options for other pilot projects are considered in line with
available funding on an ongoing basis. Home composters have been
made available to residents to address residential food waste.
Green
Priority 9: Enhance, protect, and respect the outdoors and the natural and historic environment
Litter Strategy Implementation of the Council’s Litter Strategy is ongoing with regular
updates to Committee provided. Compliance and awareness activities
in place.
Green
Historic
Environment
Work to understand the Council’s built and natural historic assets will
be developed in forthcoming annual action plans.
Amber
Priority 10: Conserve, restore and improve biodiversity, and use nature-based solutions in tackling
the climate crisis
Herbicide Use Trials and reviews of current herbicide use and alternative weed control
measures are ongoing.
Green
Tree Canopy &
Planting
Measurement of tree canopy cover has been undertaken and work to
increase this is ongoing. Planting programs are in place in line with
Clyde Climate Forest objectives and studies to assess suitability of
Council land for planting are ongoing and will be reported in due
course.
Green
Biodiversity Communications on biodiversity within South Lanarkshire continue to
be developed, training on Biodiversity is in place for Council
employees. Pollinator projects have been delivered on Council owned
land supported by the Nature Restoration Fund. Work is ongoing to
identify areas for further biodiversity gain projects in line with available
funding.
Green
Peatlands Restoration projects are ongoing in partnership with Clyde Peatlands
Project. Work has been delivered in line with available funding through
Nature Restoration Fund.
Green
Sustainable
Cleaning
New cleaning technologies and processes have been piloted and rolled
out in Council buildings including schools and HQ. Other options for
sustainable cleaning continue to be explored.
Green
Priority 11: Enable a fair transition to a green economy leaving no one behind
UK Shared
Prosperity Fund
Projects supporting net zero and skills development continue to be
delivered. Future projects dependent on the availability of alternative
funding.
Green
Workforce Skills Challenges in delivering green and circular economy upskilling, as
focus of employability services is demand based and focused more on
entry level skills. Work to expand upskilling opportunities via South
Lanarkshire College is ongoing.
Amber
Youth Skills Green economy skills embedded in senior phase learning. All
educational settings deliver learning for sustainability.
Green
Workforce
Planning
The Council Workforce Plan makes considerations for the need for new
skills to address climate change and its impacts. Workforce Plans
across the Council will continue to be updated in line with changing
Green
99

Page 100

Action Progress Status
skills needs.
Priority 12: Lead the transition to a circular economy and improve resource efficiency through
responsible consumption and production, and buying and selling of local goods and services
Procurement Sustainability procurement in place with weighted scoring for
sustainability. Work ongoing to progress against Flexible Framework.
All Council procurement now subject to sustainability scoring and
support provided to all Council Services where required, including roll
out of bespoke training.
Green
Local Food
Supply
Market capacity assessment completed. This was undertaken to
assess the capacity of the local food and drink sector to supply the
Council.
Green
Deposit Return
Scheme
Pilot in progress in select high schools; national rollout pending. The
Council will respond to national guidance relating to the roll out of the
delayed Deposit Return Scheme.
Amber
Single Use
Plastics
Removal of single use plastics from catering outlets implemented;
ongoing review for further changes, including reduction in single use
cups.
Green
Priority 13: Support South Lanarkshire’s businesses in the transition to a net zero economy and
building climate resilience
Business Grants
& Support
Funding and advisory services promoted, including through partnership
working with Business Gateway; networking events held.
Green
Property
Improvements
Consultant-led reviews have been undertaken. Pilot improvement
projects are being implemented, delivering sustainability upgrades to
suitable premises to improve energy performance.
Green 
4.2. The table above highlights that the vast majority of the actions within the 5 year
action plan are on track. Eight actions are amber, indicating minor slippage in these
areas. A number of these actions have been impacted by slipping national timelines,
for example for the implementation of the Deposit Return Scheme and Heat in
Buildings Bill, while others have been delayed in anticipation of forthcoming national
guidance, for example with regards to the national Good Food Nation Plan. The
remaining amber actions will be prioritised over the remainder of the 5-year plan. 
5. Next Steps
5.1. The forthcoming annual action plans for 2026/2027 and 2027/2028 will prioritise
ongoing actions and actions rated amber above, ensuring concentrated effort on
areas requiring further progress and development. By directing attention to these key
activities, the Council aims to accelerate delivery, address outstanding challenges,
and drive meaningful advancements in line with the strategic priorities of the
SDCCS.
5.2. The key work areas which have been identified for inclusion in future annual plans
are as follows:- 
 Continue to develop action to reduce the Council’s carbon emissions, including
development of a route map for net zero Scope 1 emissions
 Continued implementation of the Council’s LHEES and associated Delivery
Plan, including efforts to address fuel poverty
 Progress implementation of Sustainability Impact Assessment and Sustainable
Procurement Process, including roll out of relevant training
 Develop the Council’s approach to local implementation of the Good Food
Nation Plan
 Contribute to the redesign of the Council’s website to support sustainability
objectives
100

Page 101

 Preparation for the forthcoming energy efficiency standards for housing and the
anticipated Heat in Buildings Bill
 Development of the Open Space Strategy and Local Development Plan 3
(LDP3)
 Continue the Council’s efforts to adapt to the impacts of climate change,
including completion of the strategic climate change risk and opportunity
assessment and development of an adaptation plan
 Strengthening collaboration with the Lanarkshire Climate Action Hub to
enhance local climate action initiatives and community engagement
 Continuing waste reduction efforts including further exploration of food waste
reduction pilots, promotion of reuse activity and the circular economy,
preparation of the anticipated Deposit Return Scheme, and continued
implementation of the Litter Strategy
 Assessing and developing understanding of the Council’s built and natural
historic assets for informed decision making
 Progressing projects for tree planting on Council-owned land to support climate
targets
 Further work to increase biodiversity and peatlands restoration to improve
carbon sequestration and ecosystem health
 Expanding workforce upskilling opportunities in the green and circular economy
 Evaluating the local food and drink sector’s capacity to supply the Council,
supporting local economic resilience 
6. Employee Implications
6.1. All Resources are required to contribute to the implementation of the Sustainable
Development and Climate Change Strategy and action plan to ensure that actions
and targets are met. This work is predominantly delivered through existing
resources. 
7. Financial Implications
7.1. Actions within the plan are being delivered within existing resources, supplemented
by external funding (e.g., Climate Emergency Fund, Scottish Government grants, UK
Shared Prosperity Fund or its equivalent). 
8. Climate Change, Sustainability and Environmental Implications
8.1. The actions outlined directly support the Council’s climate change and sustainability
objectives, contributing to area-wide emissions reductions, improved resilience, and
enhanced community wellbeing. 
9. Other Implications
9.1. The Sustainable Development and Climate Change Strategy has been assessed as
part of the Council’s risk management arrangements and relevant issues have been
added to the Resource Risk Registers. 
10. Integrated Impact Assessment and Consultation Requirements
10.1. An Equality Impact Assessment and Fairer Scotland Duty impact assessment have
been carried out on the Sustainable Development and Climate Change Strategy. 
10.2.  Public and stakeholder consultation was undertaken during the development of the
Sustainable Development and Climate Change Strategy. 
Kevin Carr
Executive Director (Community and Enterprise Resources)
101

Page 102

21 January 2026 
Link(s) to Council Values/Priorities/Outcomes
 Focused on people and their needs
 Working with and respecting others
 Accountable, effective, efficient and transparent
 Ambitious, self-aware and improving
 Fair, open and sustainable
 Excellent employer
 We will work to put people first and reduce inequality
 We will work towards a sustainable future in sustainable places
 We will work to recover, progress and improve
 Our children and young people thrive
 Good quality, suitable and sustainable places to live
 Thriving business, fair jobs and vibrant town centres
 Caring, connected, sustainable communities
 People live the healthiest lives possible
 Inspiring learners, transforming learning, strengthening partnerships 
Previous References
 South Lanarkshire Council report on 15 June 2022 entitled ‘Sustainable Development
and Climate Change Strategy 2022-2027’
 Climate Change and Sustainability Committee report on 31 August 2022 entitled
‘Sustainable Development and Climate Change Strategy 2022-2027’
 Climate Change and Sustainability Committee report on 8 February 2023 entitled
‘Sustainable Development and Climate Change Strategy 2022 to 2027 Action Plan’
 Climate Change and Sustainability Committee report on 20 September 2023 entitled
‘Sustainable Development and Climate Change Strategy Action Plan 2022/23 – Q4
Progress report’
 Climate Change and Sustainability Committee report on 14 August 2024 entitled
‘Sustainable Development and Climate Change Strategy Action Plan 2023/24 – Q4
Progress report’
 Climate Change and Sustainability Committee report on 4 June 2025 entitled
‘Sustainable Development and Climate Change Strategy Action Plan 2024/25 – Q4
Progress report’ 
List of Background Papers
 The Climate Change (Scotland) Act 2009
 Sustainable Development and Climate Change Strategy 2022-2027
 UN’s Sustainable Development Goals 
Contact for Further Information
If you would like to inspect the background papers or want further information, please
contact:- 
Adam Wallace – Sustainability Adviser
E-mail:  adam.wallace@southlanarkshire.gov.uk
102

Page 103

Report
Agenda Item 
Report to: Climate Change and Sustainability Committee
Date of Meeting: 11 February 2026
Report by: Executive Director (Community and Enterprise
Resources)  
Subject: Response to the Council’s Climate Emergency
Declaration 
1. Purpose of Report
1.1. The purpose of the report is to:-
[purpose]
♦ detail the steps to be undertaken by officers in response to the Climate
Emergency Declaration motion of 1 October 2025
[1purpose]
2. Recommendation(s)
2.1. The Committee is asked to approve the following recommendation(s):-
[recs]
(1) that the steps proposed in Appendix 1 to respond to the Council’s Climate
Emergency Declaration be approved.
[1recs]
3. Background
3.1. On 1 October 2025, South Lanarkshire Council passed a motion declaring a climate
emergency. The motion made reference to the serious and immediate threat of
climate change and the need to accelerate the pace of delivering action. The motion
also noted that the impacts of climate induced severe weather are being increasingly
felt locally on citizens, services, infrastructure and budgets. 
4. Proposed Next Steps
4.1. To respond to the motion and the agreed actions within it, the Council will need to
progress a number of key work areas over the remainder of this term (up to May
2027). The table at Appendix 1 details the actions as per the motion and the
proposed next steps to be undertaken by the Council in order to deliver them. 
5. Employee Implications
5.1. All of the actions detailed under the next steps align well with existing work
programmes for the Council (e.g. development of net zero route map, committee
reports on new climate risk assessment and new sustainable development and
climate change strategy), or do not require significant employee resources (email to
elected members of climate hub, letter to Scottish Government on active travel
investment, committee reports on active travel investment). It should be noted that
one of the actions within the motion - report on action that will be taken to reduce the
impact of Council events and catering - may require input from several Service
areas. 
6
103

Page 104

6. Financial Implications
6.1. Responding to this motion, as set out in Appendix 1, does not have any financial
implications. 
7. Climate Change, Sustainability and Environmental Implications
7.1. Delivery of the work associated with the Climate Emergency Declaration would
support the Council in delivering its duties as per the Climate Change (Scotland) Act
2009. 
8. Other Implications
8.1. None 
9. Integrated Impact Assessment and Consultation Requirements
9.1. No integrated impact assessment is required for this paper. The motion response will
be undertaken in conjunction with a number of Resources. 
Kevin Carr
Executive Director (Community and Enterprise Resources) 
21 January 2026 
Link(s) to Council Values/Priorities/Outcomes
♦ Accountable, effective, efficient and transparent
♦ Ambitious, self-aware and improving
♦ Fair, open and sustainable
♦ We will work to put people first and reduce inequality
♦ We will work towards a sustainable future in sustainable places
♦ We will work to recover, progress and improve
♦ Good quality, suitable and sustainable places to live
♦ Caring, connected, sustainable communities
♦ People live the healthiest lives possible 
Previous References
♦ South Lanarkshire Council Net Zero Route Map - Scope 1 Organisational Emissions,
Climate Change and Sustainability Committee, 19 March 2025
♦ Notice of Motion - South Lanarkshire's Climate Emergency Declaration, South
Lanarkshire Council, 1 October 2025 
List of Background Papers
♦ None 
Contact for Further Information
If you would like to inspect the background papers or want further information, please
contact:- 
Adam Wallace – Sustainability Adviser
E-mail:  adam.wallace@southlanarkshire.gov.uk 
104

Page 105

Appendix 1 
Proposed next steps in response to the Climate Emergency Declaration motion 
Action Current activity Next steps Lead
Reaffirming the need to set
targets and detail how we
will align spend before the
end of this term to
contribute to national
emission reduction targets. 
The Year End Carbon Management
Report was presented to CMT on 30
October and to CCS Committee on
12 November 2025. The above
reports have already reaffirmed the
need to set targets and align spend
to reduce the Council’s carbon
emissions. 
The Council will develop a Net Zero
Route Map by March 20271 which will
include detail on: clear and
achievable Council emission
reduction targets, coordinated action,
and spend aligned to achieving these
targets. 
Since the Route Map relates only to
Scope 1 carbon emissions which are
100% comprised of emissions from
council buildings (not including
Council housing stock) and fleet, the
above Route Map will be informed by
the actions, emissions reductions,
indicative costs, and potential funding
options within the following strategies:
• Estates Strategy (a report on the
development of this strategy will
be presented to the Executive
Committee in 2026, with the final
strategy developed thereafter)
• The Fleet Strategy (development
of this strategy anticipated
December 2026)
CER –
Enterprise and
Sustainable
Development 
HTR – Property 
CER – Roads,
Transportation
and Fleet 
1 as agreed at CCS Committee on 19 March 2025
105

Page 106

Action Current activity Next steps Lead
Service
Reports to be submitted to the Climate Change and Sustainability Committee on:
• the increasing impact of
climate induced severe
weather such as extreme
heat, storms and flooding
on the Council’s services
and budgets, including
what plans there are to
mitigate these impacts and
costs. 
The Council is undertaking a
strategic climate change risk and
opportunity assessment. Stage 2 of
the process will explore the impact of
recent weather events and Stage 6
will develop actions that reduce risks
and optimise opportunities (thus
addressing request for information in
the motion). 
A series of reports will be presented
to CCS Committee in relation to
progress and outcomes of the
strategic climate change risk and
opportunity assessment: 
• Update on Risk Assessment (by
June 2026)
• Report on outcome of Risk
Assessment (Feb 2027)
CER –
Enterprise and
Sustainable
Development 
With input from
other Service
areas, including
Risk Team,
Finance Team,
Roads,
Transportation
and Fleet
Service,
Facilities, Waste
and Grounds
Service, and
Property Service 
• action that will be taken to
reduce the impact of
Council events and
catering by, but not limited
to, use of reusable cups,
hybrid events as default
where appropriate,
promotion of sustainable
travel, use of local and low
carbon food and drink, 
CCS Committee report provisionally
proposed to be scheduled for June
2026. 
Given the breadth of the request
within the motion, work to develop
this report will require input from
Services across the Council, notably
Facilities, Procurement, Fleet,
Communications, IT, and Personnel.
CER –
Enterprise and
Sustainable
Development 
With input from
Facilities, Waste
and Grounds
Service; Roads,
Transportation
106

Page 107

Action Current activity Next steps Lead
including opportunities for
third sector and local
caterers, subject to
compliance with Council
procedures. 
Officers from each Service to be
nominated as points of contact with
regards to facilitating sharing of
information. 
and Fleet
Service,
Communications
team;
Procurement;
and Personnel
• how the next 2027 to 2032
Climate Change and
Sustainability Strategy can
have input from local
communities to help
support the individual
behaviour change required
to achieve a just transition
and thriving, liveable
communities.
Preparatory work for the new
strategy will begin in 2026. 
A report will be prepared outlining
the approach to the development of
the strategy, including local
community engagement e.g. the
Lanarkshire Climate Hub will be the
key community engagement forum
for Lanarkshire on climate change.
The approach will also be informed
by the findings from PHD research
which is looking specifically at just
transition in South Lanarkshire. 
CCS Committee Report outlining
approach to development of new
Climate Change and Sustainable
Development Strategy (including
aspects mentioned within the motion)
scheduled for September 2026. 
CER –
Enterprise and
Sustainable
Development 
Encourage elected members
to connect with the
Lanarkshire Climate Action
Hub and visit local groups
taking climate action in their
localities. 
Email elected members with links to
the Lanarkshire Climate Hub website
by end of February 2026.
CER –
Enterprise and
Sustainable
Development 
Endorse continued calls for
fair funding for local
government and greater
action to expand local
government’s capacity to
Endorsement was approved by
South Lanarkshire Council on
October 1st, 2025.
Action complete. N/A
107

Page 108

Action Current activity Next steps Lead
invest in communities,
including in the transition to
a transformed economy and
a net zero future.
Write to the Scottish
Government to request the
full devolution of all active
travel investment
channelled through local
government to local
government, to help direct
investment to walking and
wheeling, as well as cycling
whilst maintaining and
valuing our partnership
working with other delivery
agencies.
Formal engagement in writing will
take place noting the current
methods of allocating active travel
funding and presenting an
alternative model which enables
local authorities to have the ability to
move quicker to construction, rather
than the often more bureaucratic and
time-consuming processes in place
at present. This would also allow
local authorities more flexibility and
reduce barriers by targeting local
needs in a more streamlined
process. 
A letter was sent by CER Executive
Director to Transport Scotland /
Scottish Government. 
Action complete.
CER – Roads,
Transportation
and Fleet
Service 
Request a report to the
Executive Committee or
Community and Enterprise
Resources (CER)
Committee, providing an
update on active travel
investment and its
effectiveness, to allow for
further scrutiny.
A report will be developed which will
include an update on active travel
investment over recent years and
will include information about cycle
usage related to a selection of recent
projects.
Report to be presented to CER
Committee in March 2026.
CER – Roads,
Transportation
and Fleet
Service 
108

Page 109

Report
Agenda Item 
Report to: Climate Change and Sustainability Committee
Date of Meeting: 11 February 2025
Report by: Executive Director (Community and Enterprise
Resources)  
Subject: Scottish Government Consultation on the Climate
Change Plan 2026 to 2040 
1. Purpose of Report
1.1. The purpose of the report is to:-
[purpose]
 provide the Committee with an overview of the Scottish Government’s draft
Climate Change Plan
 update the Committee on South Lanarkshire Council’s response to the Climate
Change Plan consultation
[1purpose]
2. Recommendation(s)
2.1. The Committee is asked to approve the following recommendation(s):-
[recs]
(1) that the overview of the contents of the draft Climate Change Plan be noted
(2) that the Council’s response to the Climate Change Plan consultation, as
attached as Appendix 1, be noted. 
3. Background
3.1.  In November 2024, the Scottish Parliament passed the Climate Change (Emissions
Reduction Targets) (Scotland) Act 2024  which modified the greenhouse gas
emissions reduction targets within previous climate change legislation. The new Act
was introduced following advice from the Climate Change Committee (CCC) that the
previous 2030 interim target was unachievable. The new legislation therefore
replaces Scotland's previous system of annual and interim greenhouse gas
emissions targets with a framework of five-year carbon budgets which set limits on
emissions over these periods. 
3.2. The proposed Carbon Budgets for Scotland (as recommended by the Climate
Change Committee) are:- 
 57% lower than 1990 levels for the First Carbon Budget (2026 to 2030)
 69% lower than 1990 levels for the Second Carbon Budget (2031 to 2035)
 80% lower than 1990 levels for the Third Carbon Budget (2036 to 2040)
 94% lower than 1990 levels for the Fourth Carbon Budget (2041 to 2045) 
3.3.  The Scottish Government has now published a draft  Climate Change Plan – 2026-
2040  (CCP) for consultation on 6 November 2025. The CCP sets out the policies
and proposals the Scottish Government will take forward to enable Scotland to meet
7
109

Page 110

the carbon budgets set out at paragraph 3.2. The consultation closed on 29 January
2026.   
4. Draft Climate Change Plan 2026 to 2040
4.1. The CPP contains over 150 policies and proposals to decarbonise Scotland’s
economy to align with net-zero by 2045. The Plan outlines the emissions pathway for
seven key sectors, some of the key actions required and the economic opportunities
and benefits these actions will support. 
4.2. A summary of the key policy drivers relevant to South Lanarkshire are outlined
below. 
4.2.1. Buildings (residential and public)
 A target for decarbonising heating systems by 2045. A Heat in Buildings
Strategy and Delivery Plan will be published
 Heat in Buildings Programme. A programme of support schemes and advice
services which are designed to support a wide range of groups to decarbonise
heat in our buildings
 Financial support for energy efficiency. Enable progress towards the
decarbonisation goal while reducing fuel poverty, by providing advice and
financial support for energy efficiency
 Heat networks. Develop plans to boost heat networks by requiring certain
properties to change from fossil fuel heating systems when a heat network is
available 
4.2.2. Transport: 
 Vehicle Emissions Trading Scheme and zero emissions vehicle (ZEV) Mandate.
Legislation and sales targets to encourage sales of lower emission and zero-
emission cars and vans
 Policies to reduce car use, such as free bus travel, investment in public and
active transport, and local schemes
 Consumer incentives to encourage electric vehicle (EV) uptake by households,
sole traders and micro businesses to make the transition to EVs
 Early investment in HGV infrastructure and vehicle replacement, to support the
private sector to transition to Zero-Emission HGVs 
4.2.3. Waste
 Measures to reduce landfill emissions further, including the forthcoming ban on
biodegradable municipal waste going to landfill, maximising landfill gas capture
opportunities and reviewing and targeting materials currently landfilled to
identify and drive alternative management routes
 Measures to reduce waste and ensure producers take greater responsibility for
the environmental impact of their products, including action on textiles,
delivering the Deposit Return Scheme for single-use drinks containers and
reforms to extended producer responsibility schemes (e.g. packaging and
batteries)
 Actions to reduce waste, including supporting households and businesses to
cut food waste, and helping make reuse and repair the norm
 Actions to modernise recycling, including a new co-designed statutory Code of
Practice for household waste and recycling services, and statutory local
recycling and reuse performance targets
110

Page 111

4.2.4. Energy Supply
 Support the inclusion of energy from waste in the UK Emissions Trading
Scheme (ETS). 
4.2.5. Business and Industrial Process
 Electrification of Industrial Processes: Reduces emissions by leveraging
Scotland’s growing renewable electricity generation, especially in energy-
intensive sectors
 Carbon Capture, Utilisation and Storage (CCUS) Deployment 
 Hydrogen Action Plan and Sector Development
 Scottish Industrial Energy Transformation Fund (SIETF): Directly reduces
emissions at industrial sites by improving energy performance and enabling
cleaner energy use 
4.2.6. Agriculture
 Delivery of the Agricultural Reform Route Map, ensuring that future support will
deliver high-quality food production, climate mitigation and adaptation, and
nature restoration
 Reduce emissions from agriculture non-road mobile machinery by investigating
and promoting efficiencies, alternative fuels and technological developments
and providing knowledge exchange, guidance and advice
 Investigate technologies for alternative, improved or more efficient fertilisers,
including organic and organo-mineral fertilisers and fertilising products 
4.2.7. Land Use, Land Use Change and Forestry (LULUCF)
 Increase in the annual woodland creation target every year until the end of the
decade, hitting 18,000 hectares per year in 2029/2030, and with an aim of
achieving 21% woodland cover in Scotland by 2032
 Targeted forestry grants to support landowners and by additional private
finance through the Woodland Carbon Code
 Increase peatland restoration by 10% each year to 2030 and maintain levels
after that, leading to the restoration of more than 400,000 hectares by 2040 
5. Consultation Response
5.1. The CPP consultation opened on 6 November 2025. The consultation on the draft
plan is split into six sections, seeking feedback and suggestions on:- 
 Delivering a Just Transition
 Sectoral Contributions, Policies and Proposals
 Impact Assessments
 Strategic Environmental Impact Assessment
 Monitoring Emissions Reductions
 Monitoring Just Transition 
5.2 The Council submitted a response to the consultation in advance of the 29 January
2026 deadline. The response was compiled with contributions from key services
across the Council. The full response can be found in appendix 1. 
5.3. Due to the tight consultation timescale set by the Scottish Government, it was not
possible to present the consultation response for approval at this Climate Change
and Sustainability Committee meeting. As agreed at CCS Committee of 12
November 2025, contact was made with the Scottish Government to establish
whether a late submission would be acceptable to allow for committee approval. The
111

Page 112

Scottish Government advised that an extension of two weeks would not be possible,
and that any late submission would be less able to influence the final Plan. 
5.4 As such, the draft CCP and consultation questions were circulated to members of
the Climate Change and Sustainability Committee for comment on 17 November
2025, as discussed at Committee in November 2025. The final response was also
circulated on 19 December 2025 for comment prior to submission. Feedback on the
consultation response was received from two elected members. 
6. Employee Implications
6.1. All Resources will be required to contribute to the implementation of the Scottish
Government’s finalised Climate Change Plan to ensure that actions and targets are
met. The Council’s Policy and Performance Team will monitor and report on the
Council’s progress through Public Sector Climate Change Duties Reporting. 
7. Financial Implications
7.1. As previously reported, emissions reduction projects to date have been achieved
within current budgets and from ad hoc funding, however, further financial
investment out with the Council’s current and projected resources will be required for
the Council to contribute to the challenging national net zero targets. 
8. Climate Change, Sustainability and Environmental Implications
8.1. The climate change, sustainability and environmental implications of the Scottish
Government’s Climate Change Plan will be significant. The policies in the draft plan
provide a framework for Scotland and South Lanarkshire Council to reduce
greenhouse gas emissions and adapt to climate change. 
9. Other Implications
9.1. One of the top risks for the Council is: ‘Inability to take the necessary action due to
funding constraints, to combat climate change, and work toward achieving net zero
carbon emissions by 2045, thereby contributing to negative and irreversible
environmental, social and economic impacts on the council and its residents’.
Without a fully funded plan in place to support the required action within the Scottish
Government’s Climate Change Plan, this will continue to be one of the Council's top
risks. 
10. Integrated Impact Assessment and Consultation Requirements
10.1. At this stage, this report does not introduce a new policy, function or strategy or
recommend a change to an existing policy; therefore, no impact assessment is
required. 
10.2. In the preparation of the consultation response at appendix 1, the sustainability team
has consulted with all relevant Council Resources and members of the Climate
Change and Sustainability Committee. 
Kevin Carr
Executive Director 
21 January 2026 
112

Page 113

Link(s) to Council Values/Priorities/Outcomes
 Focused on people and their needs
 Accountable, effective, efficient and transparent
 Fair, open and sustainable
 We will work to put people first and reduce inequality
 We will work towards a sustainable future in sustainable places
 We will work to recover, progress and improve
 Our children and young people thrive
 Good quality, suitable and sustainable places to live
 Thriving business, fair jobs and vibrant town centres
 Caring, connected, sustainable communities
 People live the healthiest lives possible
 Inspiring learners, transforming learning, strengthening partnerships 
Previous References
 None 
List of Background Papers
 Climate Change (Scotland) Act 2009
 Sustainable Development and Climate Change Strategy 2022 -2027 
Contact for Further Information
If you would like to inspect the background papers or want further information, please
contact:- 
Adam Wallace – Sustainability Adviser
E-mail: adam.wallace@southlanarkshire.gov.uk 
113

Page 114

Appendix 1: Climate Change Plan – Consultation Response
Section 1: Delivering a Just Transition
The following questions concern the Delivering a Just Transition section of the Plan, more
specifically: communities, skills, workforce, employers and adapting to climate change.
Question 1
What are your views on our approach to delivering a just transition for people and
communities?
The plan sets out the fundamentals of what a just transition is and acknowledges that progress in
this area must go beyond emissions assessments alone. The plan sets out a number of diverse
indicators and considerations recognising public participation, spatial equity, affordability, worker
transition, and environmental impacts as also critical in delivery of a just transition. Delivery
mechanisms, responsibilities, and resourcing have not been detailed. The information provided
constitutes more of a monitoring framework, rather than a delivery plan. 
The CCP also provides clear information on progress made so far around just transition, focusing
on areas of success. However less detail on areas which have been challenging or which have not
gone so well and what the plan for improvement here is. The draft CCP is over-focused on what is
being done well and offers limited scrutiny on the challenges around delivery e.g. the plan offers the
example of electric vehicles being ‘cheaper to run’ but there is no reference to often more expensive
initial outlays associated with these vehicles.
The primary weakness of the approach proposed is in its limited delivery strategy. The CCP offers
no explanation on how indicator results will trigger interventions, or on who is responsible for
delivering outcomes across sectors. The plan sets out how it will measure a just transition, but does
not detail how it will deliver it.
The proposed monitoring arrangements for the CCP also rely in part on subjective assessments e.g.
Satisfaction with opportunities to influence decisions (Indicator 1.1); Managing well financially
(Indicator 2.4); Transport affordability (Indicator 2.2), and Place quality perceptions (Indicator 1.4).
Objective measures such as income change, welfare level, fuel costs, quality of engagement
processes, or the actual socioeconomic impact of the transition may provide additional insight into
just transition.
There is limited discussion of wider economic impacts in the draft CCP including changing job
quality (pay, security etc.); security of work outcomes for transitioning oil & gas workers specifically
is not covered (Indicator 3.1 only measures number accessing a training fund, not job destinations).
The indicators also do not capture the effects on supply chains for heavy industry, manufacturing, or
ports.
Finally, the CCP offers no mechanism to identify and respond proactively to emerging harms e.g.
job losses and increases in fuel poverty. Anticipating and responding effectively to potential harms
from the transition should be a critical element of the CCP. Improved ability to deliver intersectional
analysis of the CCP impacts would be beneficial, focusing for example on: women in male-
dominated sectors (e.g., oil and gas), low-income households (beyond fuel poverty), and young
workers entering affected labour markets. The CCP effectively outlines how progress will be
monitored, but does not fully articulate how a just transition will be delivered.
South Lanarkshire Council endorses continued calls for fair funding for local government including
specific funding for climate action, and greater action to expand local government’s capacity to
invest in communities, including in the transition to a transformed economy and a net zero future.
Question 2
We recognise that workers face particular impacts from the Plan and we have outlined our
approach to supporting the transition of the workforce, including skills for jobs. What skills,
114

Page 115

training and qualification provisions will be most important in a net zero future and what
more could be done to support them?
The CCP details a number of specific training and skills policies for specific sectors, however it
doesn’t provide a detailed plan for skills development across the whole transition. 
Specific sectors focused on within the CCP are oil and gas workforce and transport and this is
welcomed. However it is focused on training. The CCP should go further and detail how it will track
how training will translate to secure employment.
The skills development approach should be more holistic than expert/technical skills – and should
also focus on general understanding among wider public. The CCP should provide greater detail on
plans around addressing the basic skills gap in understanding of climate change and its impacts
among the population. This is key to delivering wider behaviour changes within society that the plan
centres as important, and would also help prevent spread of climate change misinformation.
A comprehensive workforce plan for the transition to net zero would be useful in moving this
ambition towards a delivery phase, as again the information laid out represents more of a
monitoring framework. The CCP should include detail on anticipated number of workers in low-
carbon sectors; provide more clarity on which existing workers will need retraining, at what scale,
and by when; which qualifications/training should be expanded; and align these projections with
anticipated declines in specified sectors. The CCP should offer more detail on the proposed support
for sectors beyond oil and gas and transport, for example expand on heat pump installation and
building retrofit, hydrogen production and distribution, offshore wind, and grid and flexibility
technologies. 
Critically the draft CCP does not make any provision for assessment of current versus future skills
demand. It is challenging to make an assessment on the efficacy of the CCP in terms of skills,
training and qualification provisions when there is limited detail provided on the anticipated scale
and pace of change. Modelling of future skills shortages would provide useful information for skills
providers and employers in planning future workforce development needs.
Detailed funding commitments aligning with clear delivery mechanisms and timelines are essential.
This would support public bodies’ own employability work and their workforce planning to be
developed.
Question 3
The Plan will bring opportunities and challenges for businesses and employers. How can we
best support employers across the private, public and third sectors to make the changes
needed and seize the benefits of net zero?
Public sector bodies can be supported with funding to decarbonise public buildings and transition
fleets under Transport Outcome 4. Clear multi-year funding commitments from the Scottish
Government would enable public bodies to deliver a phased decarbonisation of fleet and buildings
over the life of the CCP. Greater support to develop attractive opportunities for private sector would
be welcomed. The CCP makes vague reference to the need for better private/public sector
collaboration but does not provide any detail on how this could be delivered. Significant expertise
and investment is required to facilitate this and the CCP could be improved by articulating how this
can be achieved more clearly including funding options and the powers of local government that
may be required to facilitate this. 
The CCP mentions subsidised accreditation for tradespeople switching to clean heat/net zero,
however there is no clear pathway into jobs identified where is there is no accredited route. The
CCP could make clear how transition will be facilitated via non accredited routes i.e. wider skills
development opportunities. 
A major barrier for employers is uncertainty. The Plan repeatedly stresses supportive policy levers,
however uncertainty over elements such as the previously proposed Heat in Buildings Bill will foster
hesitancy to invest in skills transition in some sectors where future changes have not been well
defined through timescales and deadlines. All employers could be better supported by providing
clarity on future regulations which will help employers to plan for long-term investment.
115

Page 116

Further, Employers cannot transition alone; many changes depend on public infrastructure e.g. grid
capacity, EV infrastructure. Clearer planning on how this will be delivered nationwide would provide
certainty for employers and could reduce the transition costs for employers themselves. The CCP
could be clearer on the delivery plan for these wider infrastructural elements which will be
foundational for the wider transition. 
Question 4
Our approach recognises that some of the Plan’s impacts will have greater implications for
particular regions of Scotland. What are your views on our approach to supporting places
where the transition presents particular regional impacts?
The plan explicitly states that the impacts of industrial decarbonisation will be “geographically
concentrated” and that the effects on jobs, communities and supply chains will vary by region
however, this recognition does not translate into a detailed regional plan.
The CCP details a number of geographies expected to be affected most acutely by the transition
away from sectors with high emissions, however the CCP does not outline:
• region-specific support packages
• detailed skills transition pathways
• local economic diversification strategies
• targeted investment plans
These are essential for areas facing accelerated job disruption. More detailed planning on how
certain geographies will be supported would be welcomed. 
The impact of the transition on rural communities could be more thoroughly explored as these areas
are affected by different decarbonisation costs, fewer alternatives to car travel, and emissions
profiles associated with agriculture. The transport proposals note that policies must work for rural
and island communities and acknowledge that impacts differ outside urban areas however again,
this is mostly only a recognition without a full regional plan. The CCP describes the issues for rural
communities, however it does not deliver operational plans for dealing with these issues. For
example, detail on rural-specific decarbonisation timelines, differentiated transport policy based on
rurality, and tailored heating transition pathways for off-gas-grid homes would all help make
progress in terms on supporting rural communities to manage the transition.
Further, with regards to rural communities, as mentioned in Q13, climate, nature and economic
objectives should be aligned to ensure communities have a meaningful share in the benefits of land-
use change. The Plan could explore how climate action can enhance rural regeneration – e.g.
through staycations; land use / peat / forestry restoration for adaptation and sequestration, improved
local living outcomes (e.g. community transport, community-based based services, rural business
support); and community ownership of renewables. 
It should also be noted that previous mining communities in South Lanarkshire have been
historically harmed by transition. The net-zero transition should not be viewed as a standalone shift,
but as a phase in a much longer transition in energy production and use. The CCP could be
improved by making reference to previous mining communities and the lasting damage that shifts in
industry have caused. Further, the recognition around not repeating previous transition mistakes
would add important context to the CCP.
Restorative justice measures would add value to the plan by providing a vehicle for course
correction for previous mining communities. Areas which have historically been affected by energy
transition should feature more prominently in the plan; the new CCP offers opportunity to still deliver
a just transition in those communities affected previously (possibly decades ago) by transition from
coal. The CCP could detail how these geographies can specifically be targeted to address historical
injustice, offering detail on what supports and investment should be targeted here. This approach
would help to not only prevent future unjust transition elements, but also correct historic ones.  
Section 2: Sectoral contributions, Policies and Proposals
116

Page 117

The following questions concern the Sectoral contributions, policies and proposal sections
of the Plan.
Buildings (Residential and Public)
Question 5
How can we decarbonise homes and buildings in a way that is fair and leaves no one
behind?
Support a ‘fabric first’ approach to reducing energy demand; provide funding support schemes to
assist those who most need help to improve the energy efficiency of their homes and to
decarbonise. 
The government should embrace the principles of PAS2035 and fully engage with the process of
improving it and the associated standards.
Retrofit agencies should be supported and encouraged to drive retrofit better and increase
confidence and familiarity with heat pumps and retrofit. This means integrating the various agendas
such as carbon reduction, fuel poverty, housing standards, quality of life, public health, climate
change resilience, and repairs & maintenance.
While a reserved issue, the Plan could make the case for decoupling the price of electricity from gas
as this would likely stimulate investment in renewables at a household and industry level by
positively impacting affordability.
Practical guidance should be accompanied by targeted financial support including funding for local
authorities to assist their decarbonisation efforts.
Question 6
How can clean heating systems (such as heat pumps) be made more affordable for
everyone? 
The government needs to stimulate demand to encourage the market to increase supply and
thereby reduce costs. This can be done by having greater clarity in policy and providing funding
support to encourage greater uptake and installation of heat pumps. 
There needs to be more flexibility around the heat pump grant, e.g. the relaxation of the requirement
for 100% of a house to be covered by a heat pump. This can be an unnecessary blocker. Air to air
heat pumps should also be included in the scheme, as in the England and Wales Boiler Upgrade
Scheme.
Transport
Question 7
Which of the following would be most effective in enabling you to transition your vehicle(s)
to zero emissions alternatives? Please rank your choices from highest to lowest priority,
where 1 is the highest priority. Please only give one ranking to each option:
If you’re responding for an organisation: you may want to consider car fleets as well as HGV
fleets.
1. Cost of new zero emissions vehicles needs to come down 2
2. Cost of used zero emissions vehicles needs to come down 7
3. Reliable infrastructure for vehicles (such as fuel or charging networks) 1
4. Noticeably cheaper running costs (including electricity, maintenance and insurance) 5
5. Convenient access to public charging infrastructure 4
6. Ensuring an adequate number of trained mechanics available to perform essential 
maintenance and repairs 6
7. Access to funding support /low cost finance 3
8. All of the above
117

Page 118

9. Other (use box below)
Question 8
How can the Scottish Government support communities to participate in planning of local
sustainable infrastructure (such as, walking, wheeling and cycling routes)?
Supporting communities to participate in the planning of local sustainable infrastructure such as
walking, wheeling and cycling routes is a key part of delivering the objectives of South Lanarkshire
Council’s Draft Local Transport Strategy (2025-2035). The draft LTS is currently being finalised
following consultation which took place in November and December 2025.  
In particular, a key objective of the Draft LTS is to improve the health and wellbeing of South
Lanarkshire residents through the facilitation and encouragement of walking, wheeling and cycling.
The draft LTS notes that the successful delivery of the LTS objectives will require close engagement
with communities across South Lanarkshire to understand their needs and to develop measures
that are tailored to them. 
Local authorities are best placed to deliver sustainable transport infrastructure at a local level, with
priorities aligned to the needs of the communities which they serve.  Following engagement and
participation in the planning of sustainable infrastructure, communities rightly wish to see this
participation translated into delivery within a realistic timescale. Ongoing, consistent and increased
long-term funding for sustainable transport infrastructure and associated behaviour change
initiatives should be provided to local authorities, ensuring resources are available for both
infrastructure projects and public engagement programmes.  Evidence of delivery further
encourages local communities to participate in ongoing meaningful engagement. In addition,
assistance to community groups in terms of best practice guidance including how local authorities
need to balance the needs of all road users would be useful.
SLC’s view is that all active travel investment channelled through local government should be
decided by local government. While the importance of partnership is recognised, councils are best
placed to decide the most effective and acceptable use of active travel funding. This approach could
help counteract the criticisms of cycling infrastructure.
Longer term funding settlements (more than the current one year) would facilitate better planning for
maximum impact.
Question 9
What action by the Scottish Government would be most helpful in supporting you to live a
more climate-friendly lifestyle?
Volunteers play a vital role in delivering nature-based solutions at the local level, supporting national
objectives outlined in the Scottish Biodiversity Strategy (SBS) and the Climate Change Plan (CCP)
to halt biodiversity loss, restore ecosystems, and achieve Net Zero.
Both strategies prioritize nature-based solutions, and community-based volunteer-led initiatives—
such as tree planting, peatland restoration, and invasive species control help deliver tangible
outcomes by improving ecosystem health and enhancing carbon sequestration. With additional
support to the voluntary sector, these projects could become more cost-effective and scalable
locally and nationally.
Community based volunteer programmes create pathways into green careers, strengthen
community resilience, and improve health and wellbeing, supporting a fair transition to a low-carbon
economy. Local, Volunteer led nature-based conservation projects are the practical link between
policy and action, ensuring that biodiversity restoration and climate adaptation happen together at
local and national scales.
Scotland’s National Volunteering Action Plan plays an enabling role in the country’s Climate Change
Plan by engaging with local people and communities to deliver practical nature-based solutions and
climate resilience projects.
118

Page 119

Additionally, further funding for Council services to support community engagement to promote and
facilitate more climate-friendly behaviour would be beneficial. For example, investment in low or free
public transport, good quality walking and cycling infrastructure, investment in energy efficiency
support for households and public agencies will also help to enable behaviour changes.
Waste
Question 10
Are there any additional proposals to support waste sector emission reduction that should
be considered across the following 5 areas:
• Strengthen the circular economy
• Reduce and reuse
• Modernise recycling
• Decarbonise disposal
• Other emission sources (including waste water and anaerobic digestion)
Not at this point in time. It is important that we take time to assess the impacts of forthcoming
changes to the waste sector (ETS, DRS, pEPR etc) before considering introducing further
regulation or policies on the waste sector.
Energy Supply
Question 11
What are your views on Scotland generating more electricity from renewable sources?
Scotland has enough natural resources for 100% of our electricity to be generated from renewable
sources. We should increase this renewable generation as we shift towards the electrification of
heat in order to reduce the reliance on fossil fuels for electricity generation.
Business and Industrial Processes
Question 12
What support do industries need to reduce their carbon emissions while remaining
competitive?
Business Energy Scotland offer practical and financial support to businesses but it appears to be
under resourced, and businesses have to wait a significant period of time to engage with an adviser.
More resources for BES to allow more speedy intervention would be welcomed.
Also, a more simplified process of financial support would be welcomed. i.e. separate the cashback
grant from the SME loan.
Agriculture and Land Use, Land Use Change and Forestry (LULUCF)
Question 13
How can the Scottish Government encourage sustainable land use, that is also productive
for local communities?
The Scottish Government should align climate, nature and economic objectives and ensure
communities have a meaningful share in the benefits of land-use change. Realising benefits such
as food production, nature restoration, carbon storage and local employment and demonstrating
real local benefits are key.
Funding and incentives should be targeted towards land-use approaches that demonstrate clear
local value, including jobs, skills, community ownership or access, alongside environmental benefits.
119

Page 120

Stronger requirements for community engagement and benefit-sharing in forestry, peatland
restoration and renewable developments can help ensure changes are shaped with local needs in
mind. Supporting local decision-making, skills development and diversified rural economies allows
sustainable land use to strengthen communities, not displace them, while contributing to net zero
and nature recovery goals.
Requiring biodiversity net gain and monitoring / reporting in renewable energy developments for the
Energy Consents Units and Council determined applications will help ensure that renewable energy
investment also benefits biodiversity.
Question 14
What do you think about our proposals for planting trees and restoring natural habitats like
peatlands?
We strongly support the proposals for tree planting as essential nature-based solutions for climate
mitigation and adaptation. However, we recommend far greater ambition and meaningful resourcing
to maximise benefits for communities and biodiversity:
• Increase Canopy Targets: The proposed 21% woodland cover target is modest compared to
European benchmarks. We suggest aiming for 30% nationally, with urban canopy targets of
at least 20% (aligned with Clyde and Forth Climate Forest initiatives) and then an
aspirational urban long-term goal of 30%.
• Embed Tree Equity: Prioritise planting in areas with low canopy cover and high social
vulnerability using metrics such as the Tree Equity Score. This ensures cooling, air quality,
and flood mitigation benefits reach those most at risk.
• Urban Forestry Partnership: Establish and fund a Scottish Urban Forestry Partnership, as
promoted and being set up by the Scottish Tree Officers Group. This would coordinate
delivery across local authority tree and woodland officers, partners such as NGO's and
share best practice and funding.
• Far greater emphasis should be placed on resourcing Local Authority Arboriculture and
urban forestry services. Currently there is a significant skill shortage. Funding should reflect
the value placed on canopy cover
• Maintenance and Survival: Provide multi-year funding for establishment and maintenance,
not just planting, to secure survival rates and carbon benefits in urban areas. 
• Strongly agree that the Scottish Government needs to protect and restore our peatland soils
and habitats. These unique and irreplaceable soils contain vast amounts of carbon that has
taken 1000’s of years to form. However, many are degraded, in poor condition and are not
active peatland forming sites. Prospective developers still use these arguments to justify
development on peat, so would welcome more incentives to encourage landowners to
consider restoring and protecting these carbon rich soils where they store and hold more
carbon and water in the future.     
• Planting trees – more of the applications for new woodland creation and forestry do take into
consideration diverse and species rich habitats, peatland soils and avoid planting conifer
trees on these important habitats.  Welcome more broadleaved woodland incorporated into
the design / forestry plan, especially along the banks of watercourses. Salmon and trout data
show a direct decline in breeding / spawning grounds in correlation with increasing water
temperature. Providing shelter along the watercourses would hopefully provide a cooling
mechanism against increasing temperatures predicted with climate change. Broadleaved
woodlands also add to the biodiversity of the forestry sites, allowing ground flora to continue
to grow under the broadleaved trees, something that is limited under the stands of conifer
plantation. These broadleaved woodlands should also connect to similar woodland in the
wider landscape, linking to proposed nature networks and provide connectivity / climate
resilience
• Forestry sites should also consider the location of proposed site to prevent fragmentation of
existing habitats and the spread of Sitka Spruce on peatlands and Important habitats for
example wet grasslands for BAP wading and ground nesting birds.
Question 15
120

Page 121

How can the Scottish Government support farming to become more climate-friendly while
continuing to support food production and improve biodiversity?
By providing Agri-environmental funding and support to the agricultural sector to encourage
peatland restoration, tree / hedgerow planting and to use more efficient fertilisers.
Section 3: Impact Assessments
The following questions concern the Business and Regulatory Impact Assessment (BRIA),
Child rights and wellbeing impact assessment (CRWIA), Island Communities Impact
Assessment (ICIA), Equality Impact Assessment (EQIA), Fairer Scotland Duty Assessment
(FSD). The purpose of these impact assessments is to understand the effects of government
policy on specific groups, including children and young people, island communities,
business and equalities groups.
Question 16
Which groups or communities do you think will be most affected by the transition to net
zero, and in what ways?
The transition to net zero will impact groups and communities in Scotland in different ways. Without
targeted and equitable support, existing inequalities risk being widened. Some of the groups most
likely to be affected include:
Low-income households
• Face substantial barriers to affording the upfront costs of low carbon technology such as
EVs, heat pumps and home retrofits, despite long-term savings.
• More likely to live in poor-quality or energy-inefficient homes and possibly relying on
cheaper, less sustainable goods with carbon intensive supply chains.
• Stand to benefit significantly from co-benefits such as warmer homes, improved air quality
and lower bills, but only if support is accessible, fair and tailored to need.
Squeezed middle income households
• Often ineligible for grants or support schemes but unable to afford low-carbon technologies
without incurring significant debt.
• Risk being left behind unless support mechanisms are broadened and better aligned with
real household affordability.
Workers in high-emitting sectors
• Those employed in oil and gas, agriculture, manufacturing, ICE vehicle services and gas
engineering are likely to face job disruption.
• A just transition requires clear, inclusive reskilling and upskilling pathways and strong
support for affected workers and communities.
Rural and island communities
• Experience higher costs and have fewer viable transport and heating options, with limited
alternatives to private vehicles. 
• Are more exposed to climate risks and infrastructure disruption, and may face additional
barriers such as distance from services and limited digital connectivity.
Residents of old, listed, or hard-to-treat homes
• Face complex and costly retrofit challenges, risking exclusion from the benefits of the
transition.
• May also encounter difficulties balancing decarbonisation requirements with the preservation
of historic and heritage properties.
Communities dependent on high-emission industries
121

Page 122

• Regions such as the North East, Grangemouth and former industrial or coalfield areas may
face significant economic restructuring.
• Require well-resourced, place-based and participatory transition planning to avoid long-term
disadvantage.
People with protected characteristics
• Women: More likely to experience lower incomes and wealth, and often carry substantial
caring responsibilities, making reskilling more difficult.
• Older people: Can face financial constraints, digital exclusion and difficulties navigating
complex processes.
• Children and young people: Vulnerable to both climate impacts and rising household costs.
• Disabled people: Often have higher energy needs and face greater challenges accessing
support schemes.
• Minority ethnic communities: May experience linguistic, cultural and digital barriers,
alongside higher rates of poverty and poor housing quality.
Across all these groups, personal safety concerns exist, for instance around active and sustainable
travel in winter when commuting hours are darker which can be pose a barrier to low-carbon
behaviours. If these groups are not fully considered in the planning of active travel routes, lighting,
and public transport infrastructure, the transition risks reinforcing existing inequalities and personal
safety concerns.
SMEs, microbusinesses and sole traders
• Face compliance costs and the need for upskilling but often lack the capacity to navigate
complex funding and regulatory requirements.
• Lack of skilled contractors to deliver low carbon technologies meanwhile training and
accreditation costs are prohibitive
• If not supported effectively, there is a risk that small businesses become increasingly
incompatible with the changing climate and economy, limiting their resilience and
competitiveness as they can’t afford the large costs of decarbonising or dealing with climate
impacts.
Communities with low social cohesion or near new green infrastructure
• May find behaviour change more challenging and may experience disruption or perceived
inequity during the roll-out of large-scale energy or infrastructure projects.
Intersectionality is an essential consideration: many individuals belong to more than one of these
groups, compounding vulnerability. Furthermore, the same groups who are most exposed to the
costs and challenges of the transition are often those most vulnerable to the impacts of climate
change itself. For this reason, plans for mitigation must be developed alongside robust, equitable
adaptation approaches.
Question 17
How do you think the Climate Change Plan aligns with existing local, regional, or national
priorities that you are aware of or involved in?
Areas of strong alignment between the draft CCP and South Lanarkshire Council’s own Council
Plan priority areas are detailed here:
‘People – we need to put people first and reduce inequality’
The CCP’s focus on fairness, tackling poverty, and ensuring no one is left behind closely reflects
our local priority to take a people-first approach. The inclusion of just transition principles, impact
assessments and recognition of regional differences supports efforts to reduce inequality.
Its co-benefits framing — warmer homes, reduced energy bills, improved air quality and healthier
places — aligns strongly with our own aims to improve wellbeing and target support to those who
need it most.
122

Page 123

‘Progress – we need to progress and improve’
The CCP’s commitments on green skills, supporting SMEs, promoting green jobs, and transforming
transport and buildings align with our objectives to continuously improve, modernise infrastructure
and strengthen the local economy.
The emphasis on innovation, making better use of resources, and improving how services are
delivered supports our ambition to find new ways of working and deliver positive change for South
Lanarkshire communities.
‘Planet – we need to work towards a sustainable future in sustainable places’
The CCP’s priority areas around biodiversity, nature restoration, adaptation and climate-resilient
places are closely aligned with our commitment to protect natural assets, support sustainable
development and raise awareness of environmental responsibilities.
Areas where alignment is weaker or delivery is challenging
• Funding and affordability: Many households and businesses cannot meet the upfront costs
of retrofit, low-carbon heating or transport changes. National funding remains insufficient for
mixed-tenure buildings, hard-to-treat homes, rural areas and low-income groups, creating
risks of widening inequalities.
• Local understanding, capacity and adoption: The pace of national ambition exceeds current
local skills capacity and community readiness. Upskilling costs for trades and SMEs are
high, and demand is not yet strong enough to justify investment for many small businesses.
Lack of accessible, reliable information on low-carbon technologies and their practical
implications for public adopters.
• SME engagement: Despite national tools and support schemes, uptake locally is low.
Complexity and limited awareness mean businesses often do not fully understand their role
or the requirements of the transition.
• Joined-up investment: The need to integrate mitigation, adaptation and nature recovery is
known, however, funding streams remain siloed. This makes it difficult to develop coherent,
place-based approaches that fully reflect local needs and vulnerabilities.
• Oversimplification of advantages: Some examples in the CCP do not reflect real-world
practicalities. For instance, the cost savings associated with electric vehicles may not be
realised for households unable to access cheaper private charging, demonstrating the need
to recognise nuances and inequalities in how benefits are distributed.
Further, the current South Lanarkshire Local Transport Strategy (LTS) covers the ten-year period
from 2025 to 2035. It is an ambitious and forward-thinking strategy that sets out a strategic vision
and objectives. It has been developed in line with the national and regional policy landscape, to
develop sustainable, healthy and innovative transport opportunities in South Lanarkshire over the
next ten years. It has been developed against a backdrop of increasing global awareness of climate
change, changes in travel patterns and activities, and a rapidly developing market in transport and
travel technology. It sets out the actions and priorities for South Lanarkshire over the lifetime of the
LTS and adopts Just Transition principles.
South Lanarkshire Council’s Vision Statement for the draft Local Transport Strategy 2025-2035 is
as follows:
“Our transportation network will support net-zero carbon emission targets and make it easier to
move around by sustainable modes, helping to support improved health and wellbeing. It will be
accessible, affordable and integrated and provide strengthened connectivity for urban and rural
areas and increase the attractiveness of South Lanarkshire as a place to live, visit, work, study and
invest. All transport infrastructure operated and maintained by South Lanarkshire Council will be
well maintained, safe to use and support sustainable economic growth.”  
Objectives have been developed to support this vision including: 
• Support decarbonisation of the transport network, including through mode shift, reducing the
need to travel and support for shared mobility practices.
123

Page 124

• The draft LTS is currently being finalised following consultation on the draft document, which
took place in November and December 2025.  
Question 18
If you identified there could be negative impacts of the Climate Change Plan, are there any
ways you think we could reduce that negative impact and if so, what would you recommend?
• Use ethical investment criteria to avoid supporting high-carbon or unethical industries
(Scottish Government Action).
• Expand accessible, low-interest finance and grant support, especially for low/middle-income
households and mixed-tenure blocks.
• Provide tailored finance for private owners in mixed-tenure buildings to avoid unaffordable
debt and stalled works.
• Provide targeted grants/loans to small businesses to take carbon reduction measures
• Incentivise upskilling/reskilling/accreditations through supported apprenticeships and
reduced cost of training schemes
• Expand sector-specific guidance and training
• Enhance and expand public transport and deliver an affordable public transport service
• Ensure public transport and active travel routes are safe for everyone 
• Ensure climate education is accessible by addressing digital exclusion.
• Develop inclusive and flexible reskilling programmes for identified protected characteristic
groups.
• Ensure all engagement routes are accessible (multilingual, non-digital options, screen-
reader compatible).
• Co-design communication with minority ethnic communities.
• Consult specific groups to understand what they need to reduce barriers and avoid
exacerbating existing inequalities
• Screen policies for maladaptation risks.
• Improve alignment of central funding streams to support genuinely place-based, integrated
solutions.
Question 19
Please share any other quantitative data, or sources of this, to assist in developing the
impact assessments:
We would highlight the South Lanarkshire Council State of the Environment Report as an important
quantitative source for understanding local vulnerability, inequalities and baseline conditions which
have relevance to the Climate Change Plan. Key data includes:
Demographics and health:
• South Lanarkshire’s population is ageing, with faster growth in those aged over 70 and 80
and a decline in those under 25.
• Life expectancy at birth (2020–2022 interim): 76.0 years for men and 80.0 years for women,
slightly below Scottish averages.
• Major causes of death include cancer, coronary heart disease, stroke and Covid-19. Alcohol-
specific and drug-related deaths have increased in recent years.
• Long-term conditions are rising:
• 25,470 people aged 65–74 had one or more long-term health condition in 2016/17,
increasing to 26,336 in 2018/19 (+3.4%).
• 22,638 people aged 75+ had one or more long-term condition in 2016/17, rising to 23,153 in
2018/19 (+2.3%).
• High prevalence conditions include anxiety and depression (264.5 per 1,000), COPD/asthma
(150.8/1,000), hypertension (148.5/1,000), chronic pain (82.8/1,000), and gastro-
oesophageal reflux (58.9/1,000).
124

Page 125

Population density and geography:
• Overall population density is 182 persons per km², but this ranges from 2,443 persons per
km² in Rutherglen to 47 persons per km² in Clydesdale.
• This demonstrates the mix of urban, semi-urban and rural contexts relevant to place-based
transition design.
Local economy and land use:
• In 2021, 88.5% of land was designated as severely disadvantaged agriculturally, 9.4%
disadvantaged and only 1.9% non-disadvantaged.
• Around 45.5% of land is cultivated grassland and 40% rough grazing, with falling areas for
grains/stock feed and recent increases in land used for vegetables and potatoes.
• Woodland area has fallen to its lowest since 2017 locally, while increasing nationally.
• The agricultural workforce in 2021 (2,189) was the lowest since at least 1995, with a shift
towards more full-time family involvement and fewer seasonal/casual workers.
Growth sector enterprises (2022):
• 3,260 growth sector enterprises in South Lanarkshire:
• 1,155 (35.4%) in Financial and Business Services
• 715 (21.9%) in Sustainable Tourism
• 620 (19.0%) in Creative Industries
• 615 (18.9%) in Food and Drink
• 135 (4.1%) in Energy (including Renewables)
• 20 (0.6%) in Life Sciences
Income and gender pay gap:
• Average resident earnings (2022): £15.38 per hour, with men earning £15.74 and women
£15.19, a gender pay gap of 3.3% (2021).
• Around 14,000 residents (12.5% of employees) earned less than the UK Living Wage
(£9.90).
Social security and targeted payments:
• Scottish Child Payment (Nov 2020–March 2023): 19,325 applications from South
Lanarkshire (6.1% of the Scottish total), with 15,945 authorised and 153,770 payments
totalling £15,092,010 (also 6.1% of Scottish total value).
• Child Disability Payment (July 2021–March 2023): 1,940 applications; 1,295 processed,
1,085 authorised; South Lanarkshire accounts for around 6.3% of applications and
authorisations, with processing and authorisation rates slightly above Scottish averages.
• Young Carers Grant (Oct 2019–March 2023): 770 applications; 480 authorised, 475
payments totalling £147,913.
• Scottish Winter Heating Payment (Winter 2022–23): 24,860 payments worth £1,243,000,
representing 6.31% of Scottish totals.
Deprivation and health inequalities:
• 88 SIMD datazones (20.4% of South Lanarkshire) are among the 20% most deprived in
Scotland, accounting for 6.31% of Scotland’s most deprived data zones.
• 20 SIMD datazones (4.6%) are in Scotland’s 5% most deprived areas.
• Life expectancy in the 20% most deprived areas (2017–2021) is 71.1 years for men, 6.6
years lower than in the rest of South Lanarkshire (77.7 years).
• There is strong evidence of an interaction between environmental deprivation (e.g. pollution,
noise, poor public transport, lack of greenspace) and socio-economic deprivation, leading to
worse health outcomes and reinforcing health inequalities.
Homelessness:
125

Page 126

• South Lanarkshire Council received 2,515 homelessness applications in the year to March
2023, an 18% increase on the previous year.
• Through the Rapid Rehousing Transition Plan, key gains have included:
• 67% reduction in long-term homelessness (temporary accommodation >12 months).
• 3.7% reduction in average days spent in temporary accommodation (now 174 days).
• Homelessness avoided in 65% of cases via prevention work.
Question 20
Are there any previous examples or case studies we should consider when assessing
potential impacts?
We do not have any specific case studies to highlight beyond the evidence outlined in question 19.
Question 21
Can you think of any further positive or negative impacts, that are not covered in the impact
assessments, that may result from the Climate Change Plan?
We consider that the main positive and negative impacts are captured within our responses to
questions 16-18 and data provided within our response to question 19.
Section 4: Strategic Environmental Assessment (SEA)
The following questions concern the SEA. There is a legal requirement to consult on the SEA
Environmental Report (Environmental Assessment (Scotland) Act 2005). The purpose of the
SEA is to assess the likely environmental effects of government policy, considers how
negative impacts can be avoided or minimised and ways that positive effects can be
enhanced.
Question 22
What are your views on the accuracy and scope of the environmental baseline set out in the
environmental report? Are you aware of further information that could be used to inform the
assessment findings?
SLC has reviewed the CPP’s SEA and consider it to be a thorough assessment and report on the
environmental implications of the Plan. From our assessment of the content, it is robust,
comprehensive and does not have any gaps in content.
Question 23
What in your view are the most significant environmental effects which should be taken into
account as the Draft Climate Change Plan is finalised?
The SEA is comprehensive in its analysis of the environmental effects of the Plan. 
Question 24
What are your views on the predicted environmental effects as set out in the environmental
report? Please share any other useful sources.
The SEA is comprehensive in its analysis of the environmental effects of the Plan. 
Question 25
What are your views on the proposals for mitigation, enhancement and monitoring of the
environmental effects set out in the environmental report?
SLC has reviewed the CPP’s SEA and consider it to be a thorough assessment and report on the
environmental implications of the Plan. From our assessment of the content, it is robust,
comprehensive and does not have any gaps in content.
126

Page 127

Section 5: Monitoring emissions reductions
The following questions concern the reporting of annual emissions reductions.
Question 26
What are your views on the proposed approach to reporting annual emissions output and
how this could support public understanding of Scotland’s progress towards achieving our
Carbon Budgets?
The proposed approach to reporting annual emissions is useful and could strengthen public
understanding of Scotland’s progress towards meeting its carbon budgets.
The reporting of emissions at a more detailed, sub-sectoral level will make it clearer where
reductions are being achieved and where challenges remain. 
The reporting framework improves transparency and enables earlier identification of risks through
the sub sectoral reporting.  This could help people see the link between specific actions and overall
emissions reductions, supporting clearer accountability for each sector. 
Reporting methods should be accessible and visual to allow for public engagement and
understanding of the emissions pathway. 
As highlighted in the plan: There are significant uncertainties with planning actions to deliver carbon
budgets over a fifteen-year time span – technological change, action from UK government in
reserved areas, wider European and global developments and other factors will impact the policies
and proposals set out in this document and result in other options becoming available.
Flexibility must therefore be embedded in the reporting framework to accommodate changes as
new options emerge.
Question 27
How useful do you think reporting emissions statistics at a more detailed level (including at
the sub-sectoral level), would be in helping people understand key sources of emissions,
and our progress in reducing them?
Reporting emissions statistics at a more detailed level, including at the sub-sectoral level, will be
useful in helping people understand the key sources of Scotland’s emissions and the progress
being made to reduce them. 
This approach is useful as it shows the source of emissions and not just the totals. If reported in a
transparent manner this will allow the public to connect their own actions and lifestyles with climate
change and emissions. Reporting methods should be accessible and visual to allow for
understanding of the emissions pathway. 
This clarity supports a more informed understanding of where progress is strong, where challenges
persist and which sectors need further action. It also makes the link between policy measures and
emissions outcomes more transparent, improving accountability and helping people engage more
meaningfully with Scotland’s pathway towards meeting its carbon budgets. 
This approach will allow the public to see where progress is being made, where delays are
occurring and the impact of specific policies. 
A regional breakdown of emissions showing key emissions sources and indicators would help
communities see where they fit in the national picture.
Question 28
How might the use of timely indicators, as proposed, help people to understand what needs
to be delivered to achieve our Carbon budgets, and to understand whether progress is on
track?
127

Page 128

The inclusion of timely indicators is helpful as these indicators are more relatable to the public than
reporting on tonnes of carbon. 
These indicators should also help develop an understanding of what must be delivered to achieve
Scotland’s carbon budgets and whether progress is on track. As the emissions inventories are
published with a 3-year time lag, these indicators will provide more up to date progress on the key
actions that are driving emissions reductions and where the gaps are. 
Timely indicators will also allow greater scrutiny of which policies are being implemented, where
delays or risks are emerging and which sectors are contributing as planned. This in turn should
improve transparency and help people understand the practical steps required to stay within
Scotland’s carbon budgets. 
Again, as in Question 27 a regional approach would be beneficial to help engage communities and
local areas in climate action.
Section 6: Monitoring Just Transition
The following questions concern the following 14 proposed indicators for monitoring and
evaluation of the Climate Change Plan.
1. Participation in decision making
2. Community energy
3. Community benefits
4. Changes to places
5. Fuel Poverty
6. Transport affordability
7. Socio-economic impact on oil and gas communities
8. Impact on household finances in oil and gas communities
9. Access to training for offshore oil and gas workers
10. Green jobs
11. Impact of energy prices on small businesses
12. Air pollution
13. Woodland creation
14. Peatland restoration
Question 29
Please detail any specific changes that would improve any of the 14 proposed indicators,
including any data sources not currently included within this framework that could provide a
useful indicator of progress towards a just transition in Scotland on an annual basis.
The proposed set of 14 indicators is a strong starting point and signals a clear intention to embed
just transition principles into climate governance. However, many of the indicators would benefit
from refinement to ensure they move beyond high-level perception or activity measures and instead
capture whether people, workers and places are genuinely experiencing fair outcomes from the
transition.
Across the framework as a whole, three overarching improvements would strengthen all indicators.
First, every indicator should be capable of regional and local disaggregation, particularly for areas
facing concentrated transition impacts such as the North East, industrial clusters, rural and island
128

Page 129

communities. Second, wherever possible, subjective perception-based measures should be
complemented by objective measures of participation, investment or outcomes. Third, the
framework should draw more consistently on existing administrative and labour market datasets,
reducing reliance on new survey questions whose continuation is uncertain.
The indicator on participation in decision-making relies solely on self-reported satisfaction drawn
from new Scottish Climate Survey questions. While perceptions matter, this indicator would be
strengthened by pairing it with objective measures such as the number and type of participatory
processes linked to net zero decisions, the demographic profile of participants, and whether
engagement influenced final outcomes. Data could be drawn from local authority planning records,
statutory consultation returns, and reports from bodies delivering community engagement. Without
this, the indicator risks capturing attitudes rather than agency.
The community energy indicator focuses on installed capacity, which measures scale but not
benefit. This could be improved by also tracking financial returns retained locally, community
ownership shares, or number of households benefiting from reduced energy costs. Annual data
already collected by the Energy Saving Trust could be supplemented with information from Local
Energy Scotland and community benefit registers to better reflect distributive justice.
Indicators relating to affordability and access, such as fuel poverty, are essential but would benefit
from clearer alignment with transition policies. Fuel poverty rates should be consistently
disaggregated by housing type, rurality and heating system, enabling clearer links between clean
heat rollout and lived outcomes. The Scottish House Condition Survey already provides much of
this data annually and could be more explicitly integrated.
More broadly, there is a gap in relation to cost burdens created by the transition, such as upfront
costs for heat, transport or compliance with standards. An additional indicator could track household
expenditure on energy and transport as a proportion of income, using the Living Costs and Food
Survey or Scottish Household Survey, to ensure decarbonisation does not exacerbate inequality.
The employment and skills indicators are among the weakest in their current form. They focus
largely on high-level labour market outcomes without clearly tracking whether workers are
successfully transitioning from high-carbon to low-carbon roles. These indicators should be
strengthened by including worker transition pathways, such as the proportion of workers leaving
declining sectors who enter training, redeployment or comparable employment within a defined
period.
Skills indicators would be far more meaningful if they drew on Skills Development Scotland
administrative data, including enrolments and completions in net-zero-relevant courses,
apprenticeships, and reskilling programmes, disaggregated by region, age and previous sector. This
would allow annual monitoring of whether training provision aligns with the scale and location of
workforce need, rather than simply tracking job numbers after the fact.
A further gap is the absence of any indicator relating to job quality. Including measures of pay,
contract security and fair work compliance in net zero sectors—using Annual Population Survey or
Fair Work Employer data—would ensure the transition delivers good work, not just green work.
The environmental indicators are generally robust but tend to track physical outputs rather than
social outcomes. For example, indicators on land use change and restoration could be strengthened
by including community involvement or benefit, such as local employment in restoration projects or
community stewardship agreements. NatureScot and Forestry and Land Scotland already collect
data that could be adapted for this purpose.
There is also a gap in relation to cumulative local impacts of infrastructure development. An
additional indicator could track the concentration of major net zero infrastructure by region, helping
identify areas experiencing disproportionate land use or visual impacts without commensurate
benefits.
The framework currently relies heavily on the future continuation of the Scottish Climate Survey.
While valuable, this creates risk. The framework would be more resilient if it drew more
systematically on existing annual datasets, including:
129

Page 130

• Skills Development Scotland training and apprenticeship statistics
• Annual Population Survey and NOMIS labour market data
• Scottish House Condition Survey
• Local authority planning and infrastructure data
• Energy Saving Trust and Local Energy Scotland administrative data
Finally, the indicators would be significantly strengthened if the Plan committed to a clear feedback
mechanism, explaining how indicator results will inform policy adjustment or targeted intervention.
Without this, even improved indicators risk becoming descriptive rather than transformative.
Question 30
What are the most appropriate indicators for judging whether we are achieving meaningful
public participation in decisions related to the climate? This includes both the quality of the
participatory process itself, and the impact of that participation on the decision-making
process.
The most appropriate indicators should assess who participates in decisions, their experience of
that participation, and how much participation influences decisions and outcomes. This would
enhance indicators around satisfaction and attendance. 
The depth of participation is a key indicator, as participation can range from information-sharing
through consultation to co-design and shared decision-making. Tracking the share of climate
decisions that use co-design approaches would provide a quality indicator in terms of how engaged
people are in the process.
Meaningful participation requires that those most affected by climate decisions are able to take part
and influence outcomes, therefore indicators around who is participating are key. Participation in
climate-related decision processes should reflect the demographic and socioeconomic profile of the
affected population, including income, age, gender, disability, ethnicity, rurality and island status. 
Another essential indicator is inclusion of affected groups. This focuses specifically on whether
communities and workers facing disproportionate transition impacts—such as those linked to
carbon-intensive industries or major infrastructure developments—are directly engaged. 
Indicators around barriers to participation would also be useful to include. Factors such as timing,
location, digital access, language, childcare etc all affect ability to participate and should therefore
be considered. Tracking whether these barriers are systematically addressed would show if
participation is genuinely open or structurally exclusionary.
Indicators on whether participation actually influences outcomes would be useful. Participation
should include explanation of how public input shaped the final decision, including which
recommendations were adopted, modified or rejected and why. Identifying linkages between
participation and policy changes would be key indicator in tracking the tangible impacts of
participation. 
Another important indicator is participant confidence in influence. Rather than general satisfaction,
this measures whether participants believe their involvement had a real effect. When tracked over
time and across demographic groups, this provides insight into trust and perceived legitimacy in
climate governance.
Meaningful public participation in climate decision-making should assess not just whether people
were asked for their views, but whether they were included early, supported to participate well, and
able to see their contributions reflected in real decisions.
Question 31
What indicator would provide the best measure of the impact of net zero development in
local communities across Scotland? For example, the impact of the installation of renewable
energy infrastructure or other land use changes (e.g. through peatland restoration or tree
planting).
130

Page 131

A useful indicator would be whether communities receive direct and tangible benefits from projects
in their area. This would provide information on the proportion of net zero developments that provide
formal, locally controlled community benefits, such as community benefit payments, shared
ownership arrangements, or locally agreed investment funds.
This indicator would likely be easier to track as it would draw on existing planning and community
benefit data, and applies across a wide range of developments, including renewable energy projects
and land use change. While it does not capture every aspect of community impact, it provides a
clear and accessible measure of whether net zero development is delivering something of value to
the communities hosting it.
Consideration should also be given to including indicators such as Tree Equity, Access to
Greenspace, Numbers of Green Jobs etc. Would also suggest considering looking at monitoring
biodiversity using street-tree diversity (ensuring that urban tree populations don’t include more than
10% of 1 species, 20% of one genus or 30% of one family of tree).
Question 32
Ensuring positive outcomes for workers who have transitioned from jobs within high-carbon
industries is central to delivering a just transition. What specific data or indicators could we
use to monitor the extent to which workers in high-carbon industries are securing alternative
employment?
A good indicator would be one looking at workers from high-carbon industries transitioning to other
secure positive outcomes. Indicators could track what happens to them after they leave those
sectors by following them over time and measuring whether they move into sustained employment,
particularly in sectors aligned with net zero.
A useful indicator would focus on the proportion of workers leaving high-carbon industries who are
in secure employment 6–12 months later, with data drawn from administrative sources such as
PAYE records, labour market surveys, and Skills Development Scotland training data. This could be
complemented by information on whether new roles are full-time, permanent, and comparable in
pay and skill level to previous employment.
This would show whether the transition is leading to stable, decent alternative employment for
affected workers, rather than only recording participation in training or job search activity.
Question 33
What specific data or indicators could we use to meaningfully monitor the impact of the
transition to net zero on the environment and biodiversity across Scotland on an annual
basis?
To meaningfully monitor the impact of the transition to net zero on the environment and biodiversity,
indicators should focus on real changes in ecological condition, not just activity or investment. By
tracking outcome-focused measures which are updated regularly we will be able to compare over
time and between places. Additionally, there is a broader need for more species data to be
generated and made available. This requires additional resources to be made available to bodies,
including local authorities, to undertake work to develop species data. The availability of this data is
foundational if we are to be able to meaningfully monitor the impact of the transition to net zero and
the CCP should make provision for this need.
At the ecosystem level, a key indicator would be change in the condition and extent of priority
habitats, such as peatlands, native woodland, wetlands and species-rich grasslands. This goes
beyond counting hectares restored and instead measures whether habitats are improving in
ecological quality. 
To capture biodiversity outcomes, an important indicator would be population trends of key species,
particularly those sensitive to land-use change or climate impacts. Using established biodiversity
indices allows annual reporting on whether species abundance and diversity are recovering or
declining as net zero measures are implemented.
131

Page 132

A further useful indicator would track land use change linked to net zero activity, such as
afforestation, peatland restoration or renewable infrastructure, alongside associated environmental
outcomes. This helps assess whether climate actions are delivering wider nature benefits or
creating unintended pressures.
Tracking the proportion of net zero projects that deliver demonstrable biodiversity enhancement,
such as habitat creation, restoration or long-term management commitments would also be useful
as it directly links climate action to nature recovery. 
It is important that any biodiversity indicators used are able to provide information on whether the
transition to net zero is supporting a healthier natural environment across Scotland, rather than
simply shifting emissions at the expense of biodiversity. 
132