Council Offices, Almada Street        
Hamilton, ML3 0AA 
Tuesday, 10 December 2024 
Dear Councillor 
Climate Change and Sustainability Committee 
The Members listed below are requested to attend a meeting of the above Committee to be
held as follows:- 
Date:  Wednesday, 18 December 2024
Time:  10:00
Venue: Hybrid - Committee Room 1, Council Offices, Almada Street, Hamilton,
ML3 0AA 
The business to be considered at the meeting is listed overleaf. 
Yours sincerely 
Paul Manning
Chief Executive 
Members 
Norman Rae (Chair), Kirsten Robb (Depute Chair), Joe Fagan (ex officio), Alex Allison, John
Anderson, Ralph Barker, Maureen Chalmers, Ross Clark, Margaret Cooper, Colin Dewar,
Monique Equi, Ross Gowland, Lynsey Hamilton, Gavin Keatt, Ross Lambie, Richard
Lockhart, Katy Loudon, Julia Marrs, Lesley McDonald, Elaine McDougall, Carol Nugent, Mo
Razzaq, John Ross, Graham Scott, Bert Thomson, Helen Toner, Margaret B Walker, Kirsty
Williams 
Substitutes
Walter Brogan, Robert Brown, Andy Carmichael, Gerry Convery, Poppy Corbett, Andrea
Cowan, Allan Falconer, Gladys Ferguson-Miller, Elise Frame, Geri Gray, Martin Hose,
Richard Nelson, David Watson 
1

Page 2

BUSINESS 
1 Declaration of Interests 
2 Minutes of Previous Meeting
Minutes of the meeting of the Climate Change and Sustainability
Committee held on 9 October 2024 submitted for approval as a correct
record.  (Copy attached) 
3 - 8 
Monitoring Item(s) 
3 Sustainable Development and Climate Change Strategy Action Plan:
Quarter 2 Progress Report
Report dated 27 November 2024 by the Executive Director (Community
and Enterprise Resources).  (Copy attached) 
9 - 68 
Item(s) for Noting 
4 Public Bodies Climate Change Duties - Annual Report 2023/2024
Report dated 27 November 2024 by the Executive Director (Community
and Enterprise Resources).  (Copy attached) 
69 - 100 
5 Litter Strategy - Update
Report dated 27 November 2024 by the Executive Director (Community
and Enterprise Resources).  (Copy attached) 
101 - 116 
6 Artificial Intelligence (AI) Litter Survey
Report dated 27 November 2024 by the Executive Director (Community
and Enterprise Resources).  (Copy attached) 
117 - 122 
7 Ash Dieback Disease (ADD)
Report dated 27 November 2024 by the Executive Director (Community
and Enterprise Resources).  (Copy attached) 
123 - 146 
Urgent Business 
8 Urgent Business
Any other items of business which the Chair decides are urgent. 
For further information, please contact:-
Clerk Name: Susan Somerville
Clerk Telephone: 07557 323097
Clerk Email: susan.somerville@southlanarkshire.gov.uk 
2

Page 3

CLIMATE CHANGE AND SUSTAINABILITY COMMITTEE 
Minutes of meeting held via MS Teams and in Committee Room 1, Council Offices, Almada Street,
Hamilton on 9 October 2024 
Chair:
Councillor Norman Rae 
Councillors Present:
Councillor Alex Allison, Councillor John Anderson, Councillor Ralph Barker, Councillor Maureen
Chalmers, Councillor Ross Clark, Councillor Colin Dewar, Councillor Monique Equi, Councillor Allan
Falconer (substitute for Councillor Lesley McDonald), Councillor Ross Gowland, Councillor Lynsey
Hamilton, Councillor Gavin Keatt, Councillor Richard Lockhart, Councillor Katy Loudon, Councillor
Julia Marrs, Councillor Elaine McDougall, Councillor Carol Nugent, Councillor Mo Razzaq,
Councillor Kirsten Robb (Depute), Councillor John Ross, Councillor Bert Thomson, Councillor Helen
Toner 
Councillors' Apologies:
Councillor Margaret Cooper, Councillor Joe Fagan (ex officio), Councillor Ross Lambie, Councillor
Lesley McDonald, Councillor Graham Scott, Councillor Margaret B Walker, Councillor Kirsty
Williams 
Attending:
Chief Executive’s Service
S Terry, Web Journalist
Community and Enterprise Resources
D Booth, Executive Director; A Brown, Head of Enterprise and Sustainable Development; K Carr,
Head of Facilities, Waste and Grounds Services; G Dodds, Sustainable Development Officer; A
Goldie, Operations Manager; K McCafferty, Sustainable Development Officer (Funding); C Park,
Head of Roads, Transportation and Fleet Services; A Wallace, Sustainability Adviser
Education Resources
L Sherry, Head of Education (Support Service and School Estate)
Finance and Corporate Resources
K McLeod, Administration Assistant; S Somerville, Administration Manager
Housing and Technical Resources
S Turner, Section Leader (Legislative) 
Also Attending:
Mr McKenna, Principal Teacher and P6 pupils, St Vincent’s Primary School, East Kilbride 
Chair’s Remarks
The Chair:- 
 paid tribute to Councillor McGeever, former chair, for all his good work during his tenure
 welcomed Mr McKenna, Principal Teacher and the following P6 pupils from St Vincent’s
Primary School, East Kilbride:-
 Ibraheem Mahmood
 Ellie Parker
 Sanidh Jailkhani
 Ellie Scott
2
3

Page 4

1 Declaration of Interests 
No interests were declared. 
2 Minutes of Previous Meeting 
The minutes of the meeting of the Climate Change and Sustainability Committee held on 14
August 2024 were submitted for approval as a correct record. 
In terms of matters arising, Councillor Marrs requested an update in relation to the:- 
 full environmental tonnage of private vehicles travelling to and from schools, following on
from the school transportation changes
 ‘Hands Up’ survey, which gave a breakdown of how children travelled to school 
L Sherry, Head of Education (Support Service and School Estate) confirmed that meetings had
taken place with colleagues from Community and Enterprise Resources in terms of seeking
advice on how to approach the matter. 
In summary, if it was possible to take forward work looking at this area, then this could involve
some form of transport analysis, also considering the mitigating strategies that Education
Resources were looking to implement.  She advised that this would take some time and, while
the exact timescales were unknown, a further report considering potential approaches could be
brought to a future meeting of this committee.  She confirmed it would not be ready for the
meeting in December 2024 but, if possible, would aim to have it ready for spring 2025. 
The Committee decided: 
(1) that the minutes be approved as a correct record; and 
(2) that it be noted that it was intended to bring a report on the issues raised previously, as
detailed above, to a future meeting of this Committee in spring 2025. 
3 Food Waste Projects 
A report dated 13 September 2024 by the Executive Director (Community and Enterprise
Resources) was submitted providing an update on the work undertaken to reduce food waste
within Facilities Services. 
Following Climate Emergency training in July 2022, a cross Resource working group was
formed to look at food waste within primary schools.   
The project team sourced materials from Zero Waste Scotland and worked with Waste Services
on a programme of school visits and presentations to promote the Food Waste journey in South
Lanarkshire. 
Facilities Services had identified avoidable food waste in primary school dining rooms and
sought innovative solutions to aid Scotland’s net zero transition.  Partnering with Education
Resources, the Service launched a whole-school initiative to address the issue, and piloted a 6-
week programme in 5 primary schools, including St Vincent’s Primary School, East Kilbride. 
This was followed by a further 21 schools over 3 rollout periods.  Pupils, designated as ‘Waste
Warriors’, were provided with scales, high-visibility vests, and resources to monitor the clearing
station area by ensuring correct waste segregation, communication with their peers in
encouraging them to eat their full lunch and reduce food waste in the dining hall.  The catering
team measured the kitchen preparation and counter waste.  All data from the dining hall and
kitchen areas was brought together, recorded and discussed on a daily and weekly basis.
4

Page 5

The initiative sparked creativity across schools, with pupils forming a gardening club at
Carnwath Primary and a composting group at Kirktonholme Primary.  The initiative has now
expanded to over 20% of the Council’s primary schools, with 26 school groups taking part and
other schools awaiting rollout. 
The outcomes of the project were as follows:- 
 an enjoyable and fun learning experience, with pupils taking a proactive approach to being
involved
 changes and/or a focus on menu items and products that resulted in higher food waste
 cooks in charge considering the quantity of certain foods they were cooking to reduce
waste
 greater awareness and confidence on the benefits of reducing food waste
 food waste data showed the importance of a focus on waste and continuous engagement
to maintain improvements
 development of an education learning pack 
Having identified vegetables from the pupils’ ‘autopsy’ as a food group with higher food waste,
this became an area for development as it formed a crucial part of children and young people’s
diet.  It was also a requirement of the Food and Drink in Schools (Scotland) Regulations 2020,
where 2 portions of vegetables and fruit must be available daily as part of the lunchtime offering. 
Positive actions taken were detailed in paragraphs 4.5.1 and 4.5.2 of the report. 
The study demonstrated that waste reduction was achievable with targeted efforts, details of
which were provided at paragraph 4.6 of the report. 
Other projects/initiatives aimed at reducing food waste included:- 
 a pre-order lunch service across all schools and nurseries’
 a ‘Still Fresh’ station fridge located within a designated area of high schools to enable cold,
pre-packaged food which had been left unsold to be taken by pupils or employees at no
cost
 monitoring of waste at the HQ coffee shop and the introduction of a ‘Still Fresh’ station
 all meals and snacks were pre-ordered in the Early Years nursery establishments, with
Early Years staff managing and distributing any unused food
 a pictorial menu pack for all primary schools and, as part of the move to a digital process,
a pilot had been developed where a presentation of the menu pack and a split screen
function allowed the pictorial menu pack to be shown alongside the Parent Pay menu
selector on the whiteboard 
The Principal Teacher and the pupils from St Vincent’s Primary School, East Kilbride gave a
presentation, in the form of a Q&A session, speaking on the challenges and benefits of the
project. 
Officers and the pupils responded to members’ questions on various aspects of the report and
project. 
Mr McKenna and the P6 children were thanked for their very informative presentation. 
The Committee decided: that the progress and updates on Food Waste initiatives be
noted.
5

Page 6

4 Approval of Forthcoming Public Bodies Climate Change Duties 2023/2024 Report 
A report dated 13 September 2024 by the Executive Director (Community and Enterprise
Resources) was submitted on the reporting timetable for the Council’s annual Public Bodies
Climate Change Duties Compliance report for 2023/2024, as required under the Climate
Change (Scotland) Act 2009. 
Due to the Climate Change and Sustainability Committee timetable this year, it was not possible
to present the full report to this Committee prior to its submission to the Scottish Government by
the due date of 30 November 2024.  Instead, it was proposed that the report be submitted to the
Council’s Executive Committee on 13 November 2024 and presented to the next meeting of this
Committee for noting on 18 December 2024. 
In response to a member’s question, the Sustainability Adviser confirmed that data had not been
available to allow reporting to this Committee within the timescales. 
The Committee decided: 
(1) that the Council’s Public Bodies Climate Change Duties Compliance report for 2023/2024
be presented for approval to the Executive Committee on 13 November 2024; and 
(2) that the Council’s Public Bodies Climate Change Duties Compliance report be presented
for noting to the Climate Change and Sustainability Committee on 18 December 2024. 
5 Carbon Management Year End Report 2023/2024 
A report dated 13 September 2024 by the Executive Director (Community and Enterprise
Resources) was submitted providing an update on the year end position with respect to the
Council’s carbon emissions for 2023/2024. 
The Scottish Government had set climate targets within legislation to reduce all greenhouse gas
emissions Scotland-wide by 75% by 2030, 90% by 2040 and a total reduction from the 1990
baseline by 2045. 
On 5 September 2024, the Climate Change (Emissions Reduction Target) (Scotland) Bill was
published.  The Bill sought to amend the Climate Change (Scotland) Act 2009, in response to
the Climate Change Committee’s (CCC’s) advice that Scotland’s interim emissions reduction
target for 2030 was beyond what could be achieved.  While the target of net zero emissions by
2045 would not be changed, the Scottish Government was seeking to establish 5-yearly carbon
budgets, which were based on the CCC’s recommendations and were more reflective of the
realities of long-term decarbonisation policy planning. 
To align the Council’s carbon management reporting with the Public Sector Climate Change
Duties Compliance report, going forward all Council carbon management related reports would
categorise the Council’s corporate emissions as Scope 1 (direct emissions), Scope 2 (energy
indirect) or Scope 3 (other indirect emissions). 
The Council’s carbon footprint for 2023/2024 was detailed at Section 4 of the report and gave a
comparison with the same corresponding period for 2022/2023.  This showed that a reduction of
9.46% had been achieved.  The reasons for the reduction were detailed at paragraph 4.2. of the
report.
6

Page 7

While the Council had a zero direct emissions (Scope 1) target by 2038, it did not have a route
map in place to achieve this target.  A report would be submitted to a future committee, taking a
longer-term view on the likelihood of Council Services meeting national carbon reduction
targets.  This would outline key national carbon reduction targets and legislation for those
individual Services which contributed most to Council carbon emissions, as well as the next
steps in reducing carbon emissions in the medium to long-term. 
Officers responded to members’ questions on various aspects of the report. 
The Committee decided: that the final year end position in relation to South
Lanarkshire Council’s carbon emissions for the year
2023/2024 be noted. 
6 South Lanarkshire Council - Climate Week 2024 
A report dated 13 September 2024 by the Executive Director (Community and Enterprise
Resources) was submitted providing an update on the work undertaken by South Lanarkshire
Council in support of Climate Week 2024 which was held from 23 to 29 September 2024. 
The Council’s Sustainability Team, in collaboration with the Communications team and other
Services, had planned a programme of engagement initiatives that were delivered during
Climate Week 2024.  The Council’s approach aimed to set a positive tone whilst underlining the
urgency of action.  Further details were provided in Section 5 of the report. 
The Sustainability Team would incorporate lessons learned from Climate Week into its
Sustainability Communications Plan. 
Councillor Robb highlighted that sustainability and climate change was a top risk for the Council
and outlined the many co-benefits of action on tackling climate change, including saving money,
improving health/fitness and green jobs.  She encouraged all councillors to complete the climate
emergency and sustainability training to see the connections between the global issues and
what could be done locally. 
The Committee decided: that the climate action initiatives during Climate Week 2024
be noted. 
7 Item of Urgent Business – Nature Restoration Fund 
The Chair advised that he had ruled to accept a request, submitted in terms of Standing Order
No 4(c), for an item of urgent business from Councillor Robb. 
Councillor Robb advised that, since the last meeting, there had been notification of a cut to the
nature restoration funding which meant a reduction of £265,000 for nature restoration.  She
highlighed that this would affect seasonal workers at Langlands Moss, tree planting and signage
at the new nature reserves.  She advised that the Council had declared a nature emergency this
year and asked officers what the intention was to maximise internal and external resources to
make sure the Council continued to contribute towards its biodiversity strategy.  
7

Page 8

In response, the Head of Facilities, Waste and Grounds Services advised that, over the last 3
years, a lot of good work had been undertaken using the funding, which amounted to £545,000
last year.  This had helped the Council expand its local nature reserves and the green network. 
There had been a lot of work planned, including the use of the funding to retain seasonal
workers over the winter period.  This was all additional work and would not be possible under
current budgets.  As it stood at the moment, the Council would not be able to undertake the
additional work planned for this winter period, however, the team was looking at whether there
were other funding sources available that might supplement some of the winter work.  He
advised that the Scottish Government was suggesting that the funding might be reinstated next
year but the details were unclear at this stage.   
The Committee decided: to note the update in terms of the Nature Restoration Fund. 
8

Page 9

Report
Agenda Item 
Report to: Climate Change and Sustainability Committee
Date of Meeting: 18 December 2024
Report by: Executive Director (Community and Enterprise
Resources)  
Subject: Sustainable Development and Climate Change Strategy
Action Plan: Quarter 2 Progress Report 
1. Purpose of Report
1.1. The purpose of the report is to: -
[
 present the Sustainable Development and Climate Change Strategy Quarter 2
Progress Report 2024-25, for the period 1 April 2024 to 30 September 2024 
2. Recommendations
2.1. The Committee is asked to approve the following recommendation(s): - 
(1) that the Sustainable Development and Climate Change Strategy Action Plan
Quarter 2 Progress Report 2024-25 be noted. 
3. Background
3.1. The Sustainable Development and Climate Change Strategy 2022-27 was approved
by the Council on 15 June 2022. The Strategy sets out how the Council aims to
develop sustainably and tackle the climate change emergency over a five-year
period, whilst also providing a broad strategic direction for longer term planning to
help deliver on the agreed outcomes and contribute to achieving a longer-term
vision. 
3.2. The Action Plan for 2024-2025 was approved at the Climate Change and
Sustainability Committee in August 2024. 
3.3. Progress against these actions will be monitored using IMPROVe and reported to the
Climate Change and Sustainability Committee at Quarter 2 and Quarter 4. 
3.4. Delivery of actions within these strategies provides the main focus for the sustainable
development activity and also enables the Council to fulfil its duties under the Local
Government (Scotland) Act 2003, the Climate Change (Scotland) Act 2009 and the
Council’s contribution to the UN’s Sustainable Development Goals. 
3.5.  Progress on all objectives, actions and measures as at Quarter 2, 1 April 2024 – 30
September 2024, is set out in Appendix 1. All data and comments included in the
Appendix are correct as of 30 September 2024. 
4. Sustainable Development Strategy 2022-2027 Quarter 2 Update
4.1. The Action Plan progress report comes in two parts; the first part contains
performance/contextual measures towards the Strategy’s outcomes, and the second
part contains improvement actions for each of the themes within the Strategy.
3
9

Page 10

4.2. Part One - Performance Measures 
The overall summary of performance measures at the end of Quarter 2 is as follows: 
Total number of performance/ contextual measures 17
Status – Green
The timescale or target has been met as per
expectations.  8 (47%)
Status – Amber
There has been minor slippage against timescale
or minor shortfall against target.  1 (6%)
Status - Red
There has been major slippage against timescale
or major shortfall against target.  0
Reportable at a
later stage
For some measures, the statistics are not yet
available to allow us to report whether the target
has been reached or not. These will be reported
when available
4 (23.5%)
Contextual
The contextual measures provide a health check
for South Lanarkshire. The council’s activities
contribute to these measures, however there are
many factors that could influence these measures
which are not fully within the council’s scope. 
4 (23.5%) 
4.3. Areas for Improvement
There are 0 measures marked as ‘red’ (major slippage). There is one ‘amber’ action
where minor slippage was reported at Quarter 2. The amber categorisation relates to
the percentage of total household waste that is recycled which has, to date, fallen
short of the target but is continuing to be monitored. Further detail on this measure is
included within Appendix 1. 
4.4.  Part Two – Improvement Actions
The overall summary of improvement actions at the end of Quarter 2 is as follows: 
Total number of improvement actions 93
Status - Blue Action Complete 7 (8%)
Status – Green The timescale or target has been met as per
expectations 67 (72%)
Status – Amber There has been minor slippage against timescale
or minor shortfall against target 6 (6%)
Status - Red There has been major slippage against timescale
or major shortfall against target 1 (1%)
Reportable at a
later stage
For some measures, the statistics are not yet
available to allow us to report whether the target
has been reached or not. These will be reported
when available
12 (13%) 
4.5. Areas for Improvement
There is one measure marked as ‘red’, relating to the Internet of Things project
which is on hold to better align with the Digital Transformation timeline. There are six
‘amber’ actions where minor slippage was reported at Quarter 2. Four of these
actions’ categorisation relates to revision of timescales for the delivery of associated
plans, guides, and strategies. One of the amber measures relates to work to embed
10

Page 11

consideration of climate change and sustainability in procurement activity and
outcomes: the Scottish Government’s procurement assessment tool has identified
that the Council still requires to make further progress in relation to two of the five
categories. The final amber categorisation relates to the withdrawal of the Nature
Restoration Fund by the Scottish Government, which will in turn impact the scale and
pace of biodiversity related work within South Lanarkshire. Further detail on these
delays, and associated management actions, are included within Appendix 1. 
4.6. Key Highlights 
Progress on all objectives, actions and measures is set out in Appendix 1. Some of
the key achievements for Q2, are noted below: 
 The Council’s direct carbon emissions for the financial year 2023-24 reduced by
7.87% compared with the previous year. Meanwhile, the Council’s indirect
carbon emissions reduced by 12% during financial year 2023-24 compared with
the previous year. 
 Up to £1.2 million has been secured from Scotland’s Public Sector Heat
Decarbonisation Fund to support decarbonisation measures at Our Lady of
Lourdes Primary School.
 A new Integrated Impact Assessment process has been introduced that
includes a Sustainability Impact Assessment. Completion of this will now have
to be considered for all proposed projects and initiatives which are being
presented to the Corporate Management Team and Committee for approval. 
 27 schools are involved in the Waste Warriors initiative which aims to reduce
food waste within schools. Work continues to extend the programme to more
schools across the Council. 
 50 schools currently hold Green Flag awards, an increase of 5 schools on the
previous year. On top of this, 5 further schools are currently progressing
through the assessment framework.
 A robust and varied schedule of engagement was carried out during Climate
Week (23-29 September). This included 5 South Lanarkshire VIEW articles
featuring community climate initiatives, 3 videos promoting local food growing, 2
intranet posts, 1 employee circular, 1 national news release and over 50 social
media posts throughout September 2024. 
 The number of Council employees who have completed Oracle Fusion Climate
Change training modules has exceeded the target of a 5% increase in course
completion, with a 15% increase since April 2024. 
5.  Employee Implications 
5.1. All Resources are required to contribute to the implementation of the Sustainable
Development and Climate Change Strategy to ensure that actions and targets are
met. Officers within the Sustainable Development and Climate Change team monitor
and report the Council’s progress, however, there are officers from all Resources
who have responsibility for updating and owning the actions noted within the
IMPROVe action plan. 
6.  Financial Implications 
6.1.  The actions detailed in the Sustainable Development and Climate Change Strategy
and associated action plan are funded from existing Resource budgets, however, the
scale and pace of action needed to meet climate change targets and address the
current climate crisis will require significant capital investment and is likely to require
external funding and investment. The delivery of the Strategy may help leverage
additional funding and investment; however, alternative financing models are also
being explored. 
11

Page 12

7.  Climate Change, Sustainability and Environmental Implications
7.1.  The Sustainable Development and Climate Change (SDCC) Strategy contributes
towards the Public Sector Climate Change Duties, the Biodiversity Duty, and the UN
Sustainable Development Goals. 
The Public Sector Climate Change Duties require that a public body must, in
exercising its functions, act in the way best calculated to contribute to the delivery of
emissions reduction targets, in the way best calculated to help deliver any statutory
climate change adaptation programme, and in a way that it considers is most
sustainable. The 2024/25 Action Plan includes initiatives such as reducing carbon
emissions from Council operations, encouraging active travel through Beat the Street
and the employee Cycle to Work Scheme, as well as encouraging completion of
Climate Emergency training modules. These are all efforts that align with the
Council’s obligation to act sustainably and mitigate climate implications of operations. 
Under the Nature Conservation (Scotland) Act 2004, all public bodies in Scotland
have a duty to further the conservation of biodiversity when carrying out their
responsibilities. The 2024/25 Action Plan emphasises the Council’s commitment to
protecting and improving biodiversity. This is evidenced through the work being
progressed in conjunction with partners (Clyde Grasslands, Clyde Wetlands and
Clyde Climate Forest) to establish Nature Networks which are now evidenced in
Nature Network maps. These are providing important evidence in the progress of the
Local Development Plan 3.     
The 2024/25 Sustainable Development and Climate Change Action Plan supports
multiple UN Sustainable Development Goals. Some examples of these are: 
 Goal 7 Affordable and clean energy – The Housing Investment Programme
allocated £6.5 million towards energy efficiency improvements in 2024/25,
furthering efforts to reduce carbon emissions from Council owned housing
stock.
 Goal 11 Sustainable Cities and Communities – Through projects such as the
Hairmyres Station improvement work and the addition of two pedestrian
crossings at Burnbank Road, the Council is extending its network of walking
and cycling routes and encouraging sustainable travel. 
 Goal 13 Climate Action – The Youth Forum empowers young people to
influence and engage with climate action efforts. The ‘Teach the Teacher’
initiative has enabled students to educate secondary teachers on climate
concerns and the type of environmental education they wish to receive. 
 Goal 15 Life on Land – Since June 2021, the Clyde Climate Forest initiative
has planted 3.5 million trees across the Glasgow City Region with a further
13,227 trees planned to be planted this Winter in South Lanarkshire. 
8.  Other Implications 
8.1.  The Sustainable Development and Climate Change Strategy has been assessed as
part of the Council’s risk management arrangements and relevant issues have been
added to the Resource Risk Registers. 
9.  Integrated Impact Assessment and Consultation Arrangements
9.1.  An Equality Impact Assessment and Fairer Scotland Duty impact assessment have
been carried out on the Sustainable Development and Climate Change Strategy. 
9.2.  Public and stakeholder consultation was undertaken during the development of the
Sustainable Development and Climate Change Strategy. 
12

Page 13

David Booth
Executive Director (Community and Enterprise Resources) 
27 November 2024 
Link(s) to Council Values/Priorities/Outcomes 
Values
 Focused on people and their needs.
 Working with and respecting others
 Accountable, effective, efficient and transparent
 Ambitious, self-aware and improving
 Fair, open and sustainable
Priorities
 We will work to put people first and reduce inequality.
 We will work towards a sustainable future in sustainable places.
 We will work to recover, progress and improve.
Outcomes
 Our children and young people thrive.
 Good quality, suitable and sustainable places to live.
 Thriving business, fair jobs and vibrant town centres
 Caring, connected, sustainable communities.
 People live the healthiest lives possible.
 Inspiring learners, transforming learning, strengthening partnerships 
Previous References
 South Lanarkshire Council report on 15 June 2022 entitled ‘Sustainable Development
and Climate Change Strategy 2022-2027’
 Climate Change and Sustainability Committee report on 31 August 2022 entitled
‘Sustainable Development and Climate Change Strategy 2022-2027’
 Climate Change and Sustainability Committee report on 14 August 2024 entitled
‘2024/25 Action Plan for Sustainable Development and Climate Change Strategy’
 Climate Change and Sustainability Committee on 14 August 2024 entitled ‘Sustainable
Development and Climate Change Strategy Action Plan: Quarter 4 Progress Report’ 
List of Background Papers
 The Climate Change (Scotland) Act 2009
 Sustainable Development and Climate Change Strategy 2022-2027
 UN’s Sustainable Development Goals 
Contact for Further Information
If you would like to inspect the background papers or want further information, please
contact: -
Gemma Dodds, Sustainable Development Officer
Email: Gemma.dodds@southlanarkshire.gov.uk 
13

Page 14

14

Page 15

IMPROVe - SLC Performance Management System                                                                                   Report printed on 18 Nov 16:30
Quarter 2 : 2024/25 - April to September
Appendix 1
Performance Report
3
15

Page 16

IMPROVe - SLC Performance Management System                                                                                   Report printed on 18 Nov 16:30
Page 2 of 3
16

Page 17

IMPROVe - SLC Performance Management System                                                                                   Report printed on 18 Nov 16:3017

Page 18

IMPROVe - SLC Performance Management System                                                                                   Report printed on 18 Nov 16:30
Summary (Section 1) - number of Quantitative Measures green, amber and red under each
Sustainable Development Theme
Sustainable Development Theme Green Amber Red Report later /
Contextual
Total
People 2 0 0 1 3
Place and Communities 3 0 0 7 10
Natural Environment (Planet) 2 0 0 0 2
A Green Economy (Planet) 1 1 0 0 2
Total 8 1 0 8 17
Summary (Section 2) - number of Improvement Actions complete, green, amber and red
under each Sustainable Development Theme
Sustainable Development Theme Complete Green Amber Red Report
later
Total
People 1 19 0 0 2 22
Place and Communities 2 29 2 1 6 40
Natural Environment (Planet) 1 9 3 0 3 16
A Green Economy (Planet) 3 10 1 0 1 15
Total 7 67 6 1 12 93
Page 1 of 52
18

Page 19

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Performance Measures
Sustainable Development and Climate Change
Strategy - Section 1: Performance Measures
The following section provides performance and contextual measures for each of the themes in the strategy. 
The performance measures highlights progress towards each of the outcomes.  The contextual measures
provide a health check; however, these are not fully in the scope of influence for the Council.
Page 2 of 52
19

Page 20

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Performance Measures
People
Contribute to improving health and wellbeing through environmental protection and access to environmental benefits for all
Performance Indicators Comments/ Progress Status 2022/23 2023/242021/22Target To Date
-------- Last 3 Years --------------------- This Year -------------
Number of Environmental Volunteering
days
The number of Environmental Volunteering days will be provided in the
Q4 update.  The figure reported for 2023/24 will also be updated in Q4
as there has been a delay in receiving figures from external groups
leading community volunteering efforts.
Report Later 2,000 ------ 4,168 5,212 1,890
Influence change through improving the understanding of Sustainable Development and the Climate Emergency across South Lanarkshire
Performance Indicators Comments/ Progress Status 2022/23 2023/242021/22Target To Date
-------- Last 3 Years --------------------- This Year -------------
Number of Council employees who have
completed the Oracle Fusion Climate
Change modules
The number of employees who have completed Oracle Fusion Climate
Change modules to date has increased by 218 to 1,634. This exceeds
the target of a 5% increase on the previous year.
Climate change training modules were promoted during Climate Week
2024. During Q2 there was a system migration from Learn on Line to
Oracle Fusion during which training modules were not available.
Green 1,487 1,634 ------ 1,354 1,416
Encourage schools to achieve
Eco-Schools status
The Council now have 50 establishments with an Eco-Schools Green
Flag Award and another five currently working towards the award.
Through our Youth Forum on Climate Change and Sustainability,
Officers are promoting the Green Flag Award by encouraging staff and
students from secondary schools that have achieved the award to share
their experiences through presentations at Youth Forum meetings. This
offers other participating schools’ valuable insights into the steps and
efforts involved in earning a Green Flag Award. Additionally, the Primary
STEM and Sustainability Development Officer provides tailored support
and training on Learning for Sustainability to schools and nurseries. This
includes using Education Scotland’s self-evaluation tool to foster
dialogue and action towards a whole-school and community approach to
sustainability, as well as helping settings understand the benefits of
becoming an Eco-School and achieving a Green Flag Award.
Green 50 50 ------ 35 45
Place and Communities
Page 3 of 52
20

Page 21

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Performance Measures
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Performance Measures
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Performance Measures
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Performance Measures
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Performance Measures
Place and Communities
Improve affordable, sustainable, and accessible transport options
Performance Indicators Comments/ Progress Status 2022/23 2023/242021/22Target To Date
-------- Last 3 Years --------------------- This Year -------------
Number of trips being made by bike An initial baseline number of trips being made by bike will be reported in
Q4.
Contextual ------ ------ ------ ------ 0
Mode share of school children travelling by
active or public transport (Annual national
'Hands Up' Survey)
This data is reported per calendar and the figure for 2024 will be
provided in the Q4 update.
Report Later 61.1% ------ 59.0% 59.9% 60.1%
Progress a transition to net-zero, energy efficient and climate resilience homes, buildings and infrastructure, and minimise the unsustainable use of natural
resources and regenerate where appropriate
Performance Indicators Comments/ Progress Status 2022/23 2023/242021/22Target To Date
-------- Last 3 Years --------------------- This Year -------------
Carbon emissions in tonnage for South
Lanarkshire: emissions within scope of
Local Authority (figures from DESNZ with a
2-year lag)
Annual data is published by the Department for Energy Security and Net
Zero. It has a two-year lag; therefore this figure (1,066.9 kilotonne
CO2e) relates to the area wide carbon emissions for 2022.
Contextual ------ ------ 1,203.9 1,066.9 ------
Percentage reduction on area-wide
emissions compared to previous year:
emissions within scope of Local Authority
(figures from DESNZ with a 2-year lag)
Annual data is published by the Department for Energy Security and Net
Zero. Area-wide emissions decreased by 11.4% in calendar year 2022
compared to 2021.
Contextual ------ ------ 10.0% -11.4% ------
Per capita: emission within scope of Local
Authority (figures from DESNZ with a
2-year lag)
Annual data is published by the Department for Energy Security and Net
Zero Data. This figure (3.3 tCO2e) is for calendar year 2022.
Contextual ------ ------ 3.70 3.30 ------
Reduce Scope 1 emissions from Council
carbon footprint (Council operations i.e.
buildings and fossil fuelled fleet)
The council’s Scope 1 carbon emissions (30,281 carbon tonnes) for
financial year 2023/24 reduced by 7.87% compared with the previous
year.
This decrease in emissions is due to a reduction in gas consumption for
the council estate, a reduction in the Fleet size in 2023/24 compared
with 2022/23 and the procurement of 50 modern commercial vehicles
that offer improved fuel efficiency.
Green ------ ------ 32,001.0 32,869.0 30,281.0
Page 4 of 52
21

Page 22

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Performance Measures
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Performance Measures
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Performance Measures
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Performance Measures
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Performance Measures
Place and Communities
Progress a transition to net-zero, energy efficient and climate resilience homes, buildings and infrastructure, and minimise the unsustainable use of natural
resources and regenerate where appropriate
Performance Indicators Comments/ Progress Status 2022/23 2023/242021/22Target To Date
-------- Last 3 Years --------------------- This Year -------------
Reduce Scope 2 and 3 emissions from
Council carbon footprint (electricity, waste
and staff travel)
The council’s Scope 2 and 3 carbon emissions for financial year
2023/24 (18,205 carbon tonnes) reduced by 12% compared with the
previous year.
The amount of waste being processed at the Energy from Waste (EfW)
facility, as an alternative to landfill, continues to increase, contributing to
this reduction in emissions. The carbon associated with waste
processed at EfW facilities is much less than if the waste had been
landfilled.
Green ------ ------ 23,797.0 20,685.0 18,205.0
Occurrence/reduction of flood events 2024 data will be provided in the Q4 update. Report Later ------ ------ 705 1,054 737
Secure external funding to help deliver the
Council’s Sustainable Development and
Climate Change priorities
A total of up to £1.49m of external funding has been secured up to the
end of Q2 to support delivery of the priorities within the SDCCS. Projects
include up to £1.2M from Scotland's Public Sector Heat Decarbonisation
Fund to support decarbonisation measures at Our Lady of Lourdes
Primary School; £24,000 from Paths for All Community Transition Fund
in partnership with Healthy and Active for promotion of accessible and
inclusive active travel; £43,000 from Scottish Power Energy
Transmission Net Zero Fund in partnership with Clydesdale Community
Initiatives for installation of solar panels at their Lanarkshire Craft
Studios; £150,000 from NHS Charities Together in partnership with NHS
Lanarkshire for hospital gardening projects; and £75,000 from Scottish
Government Heat Network Fund for feasibility work on Hamilton District
Heating Network.
Green £1.00m £1.49m £0.00m £0.00m £0.00m
Empower communities to take climate action and be more environmentally sustainable
Performance Indicators Comments/ Progress Status 2022/23 2023/242021/22Target To Date
-------- Last 3 Years --------------------- This Year -------------
Increase in the overall number of food
growing participants on Council land
including schools, care homes, housing
area and areas managed by community
groups or third-party organisations
An update on the number of food growing participants will be provided at
Q4.
The upcoming opening of Cuningar Loop Allotment site is anticipated to
increase the total number of plots and participants. Cuningar Loop
Allotment site is due to be completed in November 2024.
Report Later 1,118 ------ ------ ------ 1,065
Page 5 of 52
22

Page 23

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Performance Measures
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Performance Measures
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Performance Measures
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Performance Measures
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Performance Measures
Natural Environment (Planet)
Improve the availability and access to quality outdoor spaces and services
Performance Indicators Comments/ Progress Status 2022/23 2023/242021/22Target To Date
-------- Last 3 Years --------------------- This Year -------------
Percentage of streets found to be
acceptable during Litter Monitoring System
Survey
Surveys are undertaken three times per year. The figure to date reflects
the results from the first survey only.
With two more surveys to be undertaken over the year, there is still
potential that the target at year end will be met.
Green 92.0% 89.4% 92.1% 92.3% 92.0%
Retain Green Flag accreditation at
Strathaven Park, Cambuslang Park and
Castlebank Park
Confirmation has been received that Castlebank Park and Cambuslang
Park will retain Green Flag accreditation. Official confirmation of
Strathaven Park's Green Flag accreditation is pending. This will be
reported at Q4.
Green 3 2 3 3 3
A Green Economy (Planet)
Lead the transition to a circular economy and improve resource efficiency through responsible consumption and production, and buying and selling of local
goods and services
Performance Indicators Comments/ Progress Status 2022/23 2023/242021/22Target To Date
-------- Last 3 Years --------------------- This Year -------------
Percentage of total household waste that is
recycled
This measure is reported per calendar year. The calendar year to date
figure for January to June 2024 is 42.94% and is lower than the annual
target of 50%.
However, it is noted that the figure rose to 46.97% during the period
from April to June 2024.
The inability to now recycle Waste Upholstered Domestic Seating
(WUDS) means that this type of waste goes to landfill, and is affecting
the percentage of total household waste that is recycled. However, it is
not possible to measure exactly what the impact is as the specific
amount of WUDS going to landfill is not recorded. The percentage of
total household waste that is recycled will continue to be monitored.
Amber 50.00% 42.94% 41.50% 41.20% 43.75%
Page 6 of 52
23

Page 24

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Performance Measures
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Performance Measures
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Performance Measures
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Performance Measures
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Performance Measures
A Green Economy (Planet)
Lead the transition to a circular economy and improve resource efficiency through responsible consumption and production, and buying and selling of local
goods and services
Performance Indicators Comments/ Progress Status 2022/23 2023/242021/22Target To Date
-------- Last 3 Years --------------------- This Year -------------
Percentage of household waste sent to
landfill
This measure is reported per calendar year and the year-to-date figure is
1%, remaining significantly lower than the annual target of 5%. While
this figure remains well below the target to stay under 5%, a planned
waste outage tonnage was evident in May/June 2024, meaning that the
energy from waste facility in Dunbar was closed for planned
maintenance and a relatively small amount of waste was therefore
diverted to landfill.
Green 5.0% 1.0% 8.7% 1.8% 1.5%
Page 7 of 52
24

Page 25

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
Sustainable Development and Climate Change
Strategy - Section 2: Improvement Actions
The following section provides improvement actions that contribute towards meeting the outcomes in each
theme for this financial year.
Page 8 of 52
25

Page 26

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
People
Contribute to improving health and wellbeing through environmental protection and access to environmental benefits for all
Action Measures Comments/ Progress Status
Safeguard health by
improving and protecting
air quality
Implement grant funded air quality measures during
2024-2025 to support the Air Quality Action Plan and
continue to maintain and publicise both real time and
historical air quality monitoring results
Encouraging uptake of active and sustainable travel forms part of
action planning to improve air quality. Formal grant funding from SPT
to support active travel behaviour change initiatives has now been
confirmed and a grant of £173,500 has been awarded to fund a further
Beat the Street project as well as continuing with the BetterPoints
Think, Move, Breathe project until March 2025.
Scottish Government funding is being used to support air quality
monitoring activities as well as for active travel promotional campaigns,
anti-idling campaigns, and Eco Stars support for businesses that
operate fleet which travel through the South Lanarkshire area.
The total awarded in 2024/25 from Scottish Government Air Quality
Resource grant and SPT is £369,914.05.
Green
Page 9 of 51
26

Page 27

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
People
Contribute to improving health and wellbeing through environmental protection and access to environmental benefits for all
Action Measures Comments/ Progress Status
Identify and manage
contaminated land
within the statutory
regulatory framework
Implement the Contaminated Land Strategy and support the
Planning Authority in relation to development applications
Land which has been impacted by historic industrial use continues to
be considered in terms of contamination. Contamination legacy issues
have been found in locations across South Lanarkshire.
Site investigations, remediation proposals as well as verification of
remediation works form part of the work to ensure that sites with
contamination issues are identified and any contamination issues
addressed taking into consideration the final use of that land. The
overarching ambition is to bring such sites into sustainable and
beneficial use. Work to achieve this is ongoing with the Planning
Service.
Green
Identify relevant climate
hazards, as well as risks
and opportunities which
are/will affect South
Lanarkshire
Develop a climate risk register through CCS Steering Group
upon which action planning, decision-making and monitoring
will be built upon with regards to climate change adaptation
and resilience
The following continues to be a top risk for the Council: 'Inability to
take the necessary action due to funding constraints, to combat
climate change, and work toward achieving net zero carbon emissions
by 2045, thereby contributing to negative and irreversible
environmental, social and economic impacts on the Council and its
residents’. The scoring for this risk has been reassessed this year to
reflect funding constraints and the difficulties faced by the council in
meeting climate change targets. Work to develop a climate risk
register will begin in early 2025.
Report Later
Page 10 of 51
27

Page 28

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
People
Progress climate justice and ensure the transition to net-zero by 2045 does not exacerbate poverty or inequalities
Action Measures Comments/ Progress Status
Commission a PHD
student from Glasgow
Caledonian University to
undertake a study to
assess the impact of
climate change on
South Lanarkshire
communities
Following approval and assessment of the project, the PHD
student will progress the data-collection stage of the project
through undertaking community engagement
During the period of March 2024 to September 2024, the student has
conducted five focus groups with community members across South
Lanarkshire, as well as seven interviews with various specialists,
community leaders, and South Lanarkshire Councillors. The next
stage of the data collection process will be to use these findings to
inform the questions included in a discrete choice survey. All focus
group data will be analysed and synthesised into an intermediate
report for South Lanarkshire Council that will be presented to the
Climate Change and Sustainability Committee in 2025.
Green
Continue to raise awareness internally of the project, through
participating in events, attending meetings and delivering
presentations to both external and internal stakeholders
The student presented to Climate Change and Sustainability
Committee in August 2024. The presentation focused on the
background for the project, information on early data collection, and
gave an update on the proposed next steps for the project. The
student has also been engaging with the Planning team to ensure that
data collected is available to inform ongoing development of the LDP3.
Green
Work with partners to
promote available
energy advice and
funding support
schemes to minimise
fuel costs for
households
Partners deliver a range of actions to tackle fuel poverty,
including advice and support, and signposting to financial
support
The Fuel Poverty Sub Group meets quarterly. The Chair of the group
provided a presentation at the Financial Inclusion Network (FIN)
networking event in May 2024. Many Fuel Poverty Sub Group
members were involved with, or present at, this event. The Chair also
gave a presentation at the Community Planning Progress Group. All
group members continue to share information and signpost clients on
an ongoing basis and can also access the FIN weekly bulletin which is
hosted on the Community Planning Partnership website. Additionally,
they are encouraged to utilise this resource for sharing news, funding
opportunities, consultations, events and training. All Fuel Poverty Sub
Group members' Services are also detailed on the 'Money is not the
only problem' online resource which is shared widely.
Green
Page 11 of 51
28

Page 29

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
People
Progress climate justice and ensure the transition to net-zero by 2045 does not exacerbate poverty or inequalities
Action Measures Comments/ Progress Status
Promote
weather-related
warnings and advice
from national agencies
Continue to work with the Council’s Corporate
Communications Team to deliver and/or share regional
and/or national weather warnings where relevant or
appropriate
Alerts issued where appropriate. Complete
(e.g. Met Office and
SEPA) to inform
individuals and
communities
Work to enhance individual and community level
preparedness via sharing and utilising resources available
(e.g. Ready Scotland and Adaptation Scotland) and work to
raise awareness of the need for community and business
resilience to climate change risks
The Council regularly monitors the social media channels of partner
organisations to identify posts and events that support and promote
weather preparedness and climate resilience. Posts offering guidance
on home adaptations to help residents stay warm and safe this winter
have been shared on the Council's social media platforms.
Additionally, Facebook has been used to promote Home Energy
Scotland's webinar series, organised by NHS Lanarkshire, which
covered important topics like energy-saving.
Green
Continue to raise
awareness and embed
sustainability within
social work resources
and South Lanarkshire
HSCP
Continue to deliver upskilling and awareness sessions within
Social Work resources, utilising frameworks such as the UN
Sustainable Development Goals
Awareness session has been held with the Planning and Performance
Team within Social Work in order to upskill staff in relation to UN
Sustainable Development Goals across statutory planning functions.
These goals will be embedded across operational service areas
throughout the work of the Social Work Planning and Performance
Team.
Green
Page 12 of 51
29

Page 30

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
People
Influence change through improving the understanding of Sustainable Development and the Climate Emergency across South Lanarkshire
Action Measures Comments/ Progress Status
Mainstream
sustainability and
climate literacy learning
and development across
the Council
Re-promote Oracle Fusion training on sustainability to
elected members and officers by March 2025
The Climate Change and Sustainability (CCS) Team encouraged
Officers to complete Climate Emergency Training on Oracle Fusion
during Climate Week (23-29 September). The training modules were
promoted via an all staff email and in a Climate Week intranet post
inviting employees to take part in the training modules available.
Green
Develop and implement
a robust
communications plan for
promoting and raising
awareness of the
sustainability, climate
Work with the council’s corporate communications team to
develop a refreshed 2025/26 communications plan, by April
2025. This will include the promotion of key campaigns
throughout the year, for example, Climate Week
The Climate Change and Sustainability (CCS) Team worked with the
Communications Team to develop a refreshed Communications Plan
for 2024/25 which is currently being followed and the initiatives within
the plan are being implemented. Lessons learned from 2024/25
communications plan implementation will be used to inform the
2025/26 communications plan which will be devised in early 2025.
Report Later
Page 13 of 51
30

Page 31

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
People
Influence change through improving the understanding of Sustainable Development and the Climate Emergency across South Lanarkshire
Action Measures Comments/ Progress Status
change and adaptation
agenda within the SLC,
national and global
context
Implement the agreed 2024/25 communications plan and
prepare articles, including case studies, to communicate
success stories and achievements and inspire further
positive action
Regular articles and good news stories have been prepared and
shared across Council social media channels and South Lanarkshire
VIEW as well as local and national newspapers. Stories have included
national coverage of the Scottish Tea House in The Herald Scotland,
showcasing South Lanarkshire as a location for sustainable tourism
pursuits as well as local promotion of the Clyde Cycle Park in the
Rutherglen Reformer. More stories have been shared on the South
Lanarkshire VIEW, telling the story of positive climate action being
carried out by the Cambuslang Apiary, Douglasdale REAL Group,
Clyde Climate Forest and the Nowhere to Grow project. The success
of the Climate Emergency and Resilience Fund (CEF) grants have
been displayed with the use of a three part video series released on
social media, featuring Biggar Food Growing Group. All
communication initiatives are designed to raise awareness of climate
change in terms of the impacts but also the co-benefits. The aim has
been to inspire and influence positive behaviour change. We continue
to actively share useful information and good news stories on social
media from the South Lanarkshire community and national partners.
Green
Page 14 of 51
31

Page 32

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
People
Influence change through improving the understanding of Sustainable Development and the Climate Emergency across South Lanarkshire
Action Measures Comments/ Progress Status
Further embed
sustainable
development and
climate change into the
Council’s
decision-making
process
Identify potential for development and piloting of an
integrated sustainable development decision-making tool to
be applied to proposed projects and initiatives presented to
the Corporate Management Team and Committee for
approval by the March 2025
The Council is implementing a new Integrated Impact Assessment
process in 2024 which will include a Sustainability Impact Assessment
section.
Green
Deliver town centre
masterplans, strategies,
and visioning at a local
level
Ensure that all town centre development activity has
sustainability at its core with reference to the
recommendations contained in the Town Centre Net Zero
Strategy, NPF4 and other strategic recommendations
Town Centre masterplans for East Kilbride and Hamilton have been
developed with sustainability at the core. Both masterplans contain
sections on sustainability and work to implement masterplans has
been procured with this in mind.
Both action plans are aligned with the Town Centre Net Zero Strategy,
NPF4 and other strategic recommendations to ensure that all
masterplan redevelopment is compliant. For example building
redevelopment will be considered before demolition and any
demolition strategies will recycle materials where possible. Initiatives
such as district heating and active travel form part of the plan as
lasting sustainable impacts.
Green
Page 15 of 51
32

Page 33

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
People
Influence change through improving the understanding of Sustainable Development and the Climate Emergency across South Lanarkshire
Action Measures Comments/ Progress Status
Empower learners to
shape and influence
action on climate
change and
sustainability through
the youth forum
Continue to support the Youth Forum on Climate Change
and Sustainability to ensure young people’s voices are
represented on appropriate Council matters relating to this
subject area
Officers are supporting an increased number of Youth Forum meetings
during the 2024/25 school session. Additionally, they have supported
the candidate selection process for the Forum to vote for their new
Chair and Vice Chair, who took up post in August 2024. Officers have
also worked on tracking and reviewing the activities the Youth Forum
have been involved in, and gauged pupils' views on the areas they
would like to see developed in the 2024/25 school session.
Green
Continue to support the Youth Forum in empowering,
shaping and influencing behaviour change in relation to
climate change and sustainability in schools
In September 2024, Youth Forum members participated in the ‘Teach
the Teacher’ programme in order to present to secondary teachers on
issues, concerns and areas they wish to be learning about. Officers
are also working on identifying funding to support the Youth Forum’s
desire to hold a third Conference of Schools event targeted at pupils in
early 2025. Planning is underway for the Learning for Sustainability
conference for teachers from early years, primary and secondary
sectors.
Green
Page 16 of 51
33

Page 34

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
People
Influence change through improving the understanding of Sustainable Development and the Climate Emergency across South Lanarkshire
Action Measures Comments/ Progress Status
Embed sustainability in
the curriculum across all
Education
establishments
All educational establishments will participate in a Learning
for Sustainability Conference and consider how to
incorporate aspects within educational settings. e.g. primary
schools will aim to deliver one project each year which has
an overt focus on sustainability
All primary schools have a goal to deliver at least one project per year
with a clear focus on sustainability. To assist schools in achieving this
goal, officers have developed a curricular framework specifically
designed to support the planning and delivery of sustainability-focused
projects. This framework provides guidance and inspiration for
incorporating Learning for Sustainability into everyday teaching and
learning practices.
A Learning for Sustainability Conference is also being organised for
November of this year. This event will offer practitioners an exciting
opportunity to collaborate with Learning for Sustainability partners and
explore a wide range of resources designed to support the integration
of sustainability into educational settings.
At the conference, educators will have access to a variety of tools,
workshops, and networking opportunities aimed at embedding
sustainability into the curriculum.
Green
Page 17 of 51
34

Page 35

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
People
Influence change through improving the understanding of Sustainable Development and the Climate Emergency across South Lanarkshire
Action Measures Comments/ Progress Status
Considering recent national guidance, enhance our focus on
learning for sustainability across all levels and curricular
subjects
We are in the early stages of enhancing our focus on Learning for
Sustainability (LfS) across all levels and curricular subjects, following
recent national guidance. The Curriculum and Quality Improvement
Service Team continues to support schools to embed and strengthen
LfS through the provision of resources, staff training, and whole-school
sessions.
A key development has been the collaboration with the Youth Forum
through the Teach the Teacher programme. Drawing on student ideas,
a new resource for secondary schools has been created, offering
practical suggestions for integrating climate change education across
various subjects, with four ideas provided per subject. The resource
will be reviewed by secondary school staff before being shared more
widely across the authority.
Green
Work to continue to raise awareness and monitor
achievement of learning for sustainability in Early Years
establishments
Work to plan the Conference of Schools event is underway with the
assistance of the Sustainability lead within Education. Following this,
new training will be developed and delivered in the new year. The
training will help increase work across the Sustainable Development
Goals. This will be delivered to Council Early Years establishments and
to funded providers, including childminders.
Green
Page 18 of 51
35

Page 36

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
People
Influence change through improving the understanding of Sustainable Development and the Climate Emergency across South Lanarkshire
Action Measures Comments/ Progress Status
Explore and review
options for carbon
reduction from school
estates through
understanding carbon
footprint of activities/
estates
Work with Resources from across the Council to understand
and reduce carbon footprint through a set of co-developed
carbon reduction initiatives
Recycling projects within two secondary schools are ongoing.
Meanwhile, Officers are working on a funding bid to support the
purchase of more recycling bins as part of a rollout to more schools.
Additionally, Education Resources are assisting Community and
Enterprise Resources with the Food Waste Warriors project across
primary schools. A number of schools have been involved and work is
ongoing to roll the initiative out further.
The opportunity for schools to access trees and hedgerows for
planting continues to be promoted.
Green
Page 19 of 51
36

Page 37

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
People
Influence change through improving the understanding of Sustainable Development and the Climate Emergency across South Lanarkshire
Action Measures Comments/ Progress Status
Work with our
communities to provide
programmes and
opportunities to increase
sustainability awareness
and action
Provide access to adult learning opportunities which raise
awareness on climate change
A range of projects continue to be delivered to support adult learners
to engage with climate change and sustainable practices. These
include:
ESOL (English for Speakers of Other Languages) food sustainability
workshop and ecological workshop. These provide attendees with the
opportunity to learn how to create safe cleaning products and make
small steps towards environmental conservation.
The Adult Literacy and Numeracy team have been working in the heart
of rural Lanarkshire to deliver teaching sessions on how to make
eco-friendly products in the Glespin and Douglas areas.
The East Kilbride Universal Connections Nowhere To Grow project
continues to provide learner-led projects for adults who wish to build
skills and knowledge in gardening and horticulture and assist in
increasing local biodiversity. Food grown in the garden is shared with
other centre users or utilised by the adult cooking group, Eco Eaters.
Attendees are also sharing their experiences with others, helping to
increase knowledge and understanding.
Additionally, staff have undertaken Ride Cycle Leader training, allowing
them to lead group cycle rides with learners. The sessions
demonstrate how changes in transport habits can help reduce carbon
emissions.
All of these projects support adult learners to improve their
understanding of climate impacts and the simple changes that can
provide a net benefit to the environment and South Lanarkshire. These
programmes also help provide educational opportunities that develop
the core and social skills of learners.
Green
Page 20 of 51
37

Page 38

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
People
Influence change through improving the understanding of Sustainable Development and the Climate Emergency across South Lanarkshire
Action Measures Comments/ Progress Status
Promote the Environmental and Sustainability Learning
Programmes and Awards delivered across the authority
Learners continue to be supported to access awards such as the Duke
of Edinburgh’s Award and are encouraged to increase understanding
of environmental issues by participating in outdoor learning
opportunities delivered through the Youth, Family and Community
Learning (YFCL) Awards Team and the network of Universal
Connections facilities and YFCL projects. This work is underpinned by
the South Lanarkshire Youth Strategy as well as the Learning for
Sustainability Action Plan.
The Duke of Edinburgh’s Award (for learners up to the age of 26)
facilitates volunteering with community groups such as Friends of the
Caulder, looking at conservation and environmental awareness.
The John Muir Award has been suspended for a year due to the
organisation reviewing the award. The aims and objectives continue to
be progressed however, and recognition awarded through local
systems, and alignment with other awards where applicable.
Dialogue between young people and the Community Planning
Partnership board continues to progress with an additional
development session planned yearly to discuss and tackle issues as
well as progress ideas in South Lanarkshire.
The draft Community Learning and Development 3-year Strategic
Action Plan 2024 - 2027 is currently being presented at relevant
committees which supports opportunities to promote environmental
and sustainability learning programmes and awards, both existing and
new.
Green
Page 21 of 51
38

Page 39

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
Place and Communities
Improve affordable, sustainable, and accessible transport options
Action Measures Comments/ Progress Status
Encourage active travel
by extending our
network of walking and
Continue the design and implementation of various cycle
routes in towns and villages throughout South Lanarkshire
and consult key stakeholders throughout the project stages.
Active Travel Tier 1 funding has been awarded by Transport Scotland,
enabling active travel project works to progress (see below).
Green
cycle routes Deliver walking and cycling projects / schemes in line with
agreed 2024-25 capital programme
Active travel project works are progressing as follows: new facilities for
pedestrians and cyclists as part of the Hairmyres Station project; two
pedestrian crossings at Burnbank Road; and cyclops
junction/crossings at Eaglesham Road/Redwood Drive/Greenhills
Road.
Green
Deliver new and
improved low carbon
vehicle charging
infrastructure
Install and renew charging infrastructure points which are
available for use by the public within South Lanarkshire
Work is continuing on the regional collaboration initiative to expand
and enhance vehicle charging infrastructure across the West in line
with the Inter Authority Agreement. Tenders are currently being
reviewed for the appointment of a consultant to prepare tender
documentation and project manage the next phase. This will seek to
appoint a commercial operator for publicly available electric vehicle
charging infrastructure across the Glasgow City Region.
Green
Continue project design development and implementation
and attract private investment within South Lanarkshire
As outlined above, tenders are currently being reviewed for the
appointment of a consultant to prepare tender documentation and
project manage the expansion of electric charging infrastructure
across SLC. An Electric Vehicle Infrastructure Expansion Plan and
Strategy has been created which identifies the future requirement for
charging infrastructure within SLC. This was carried out in partnership
with Glasgow City Region partners and the most appropriate financial
model is being investigated to allow for the rapid expansion of the
network.
Green
Page 22 of 51
39

Page 40

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
Place and Communities
Improve affordable, sustainable, and accessible transport options
Action Measures Comments/ Progress Status
Progress towards
decarbonising the fleet
of South Lanarkshire
Council vehicles
Implement the Fleet Strategy (2020-2025) Action Plan
including a reduction in transport related emissions,
conversion of fossil fuelled small fleet to full electric and the
trialling of new fuel option for the medium to heavy fleet.
A revised/rescoped Fleet Asset Management Plan will be completed
during 2024/25 and will provide an update in relation to progress
against the actions contained in the Fleet Strategy (2020-25). It is
recognised that the two years lost to the Covid-19 pandemic impacted
the extent of progress that might have otherwise been made. A recent
recruitment exercise has now provided some stability to focus on this
key piece of work.
Green
Encourage greater use
of public transport by
working with partners to
improve public transport
infrastructure
Deliver prioritised improvements to bus and rail infrastructure
(e.g. park and ride) in line with available external funding for
2024-25
Land purchase for the Lanark Interchange station area is in progress.
This is expected to conclude during the current financial year.
The contract for Hairmyres Park and Ride was awarded in September
2024 and works are expected to commence on site in Autumn 2024
with expected completion in Summer 2025.
Green
Ensure climate change
mitigation and
adaptation, particularly
net zero area-wide
emissions form a
strategic part of the new
Placemaking Guide as
per NPF4
Develop interim framework for consultation with
stakeholders, with final Placemaking Guide prepared by end
of June 2024
Significant progress has been made on the preparation of the
Placemaking Guide during 2024. This has included ongoing
engagement and consultation at various stages of document evolution,
with other Council services as well as organisations such as Seniors
Together and Alzheimer's Scotland. Further drafting is being carried
out during the remainder of 2024 with a view to the document being
completed in February 2025. The document completion date has
changed as the result of a strategic decision to make the document a
Corporate document, rather than a Planning document.
Amber
Present finalised document to Planning Committee for
approval by December 2024
It is intended a report on the finalised Placemaking Guide will be
presented for approval at the Planning Committee in early 2025. The
document completion date has changed as the result of a strategic
decision to make the document a Corporate document, rather than a
Planning document.
Amber
Page 23 of 51
40

Page 41

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
Place and Communities
Improve affordable, sustainable, and accessible transport options
Action Measures Comments/ Progress Status
Consider sustainable
travel within the
Council’s employee
travel plan
Reviewing the current employee travel plan during 2024-25
to encourage employees to adopt sustainable travel choices
A more comprehensive review of the travel plan will take place in
2024/25 and is an action within the HR team 2024/25 workplan.
Report Later
Continue to achieve
Cycle Friendly Employer
status
Ensure that current cycle friendly status facilities at principal
building (e.g. HQ, South Vennel) are maintained and
promoted through providing facilities such as storage and
showers to encourage and enable staff to active travel to
work and promotion of the Cycle to Work Scheme’ I’ve
highlighted where the only change is for your ease.
Current cycle friendly status facilities continue to be maintained.
Information about the Cycle to Work Scheme is always readily
available on the Council intranet. The scheme is now open all year
round and is periodically promoted through employee circulars and
featured intranet news articles.
Green
Progress a transition to net-zero, energy efficient and climate resilience homes, buildings and infrastructure, and minimise the unsustainable use ofnatural resources and regenerate where appropriate
Action Measures Comments/ Progress Status
Reduce South
Lanarkshire Council's
Present 2023/24 interim carbon management report to CCS
Committee in May 2024
The Carbon Management Interim Update for 2023/24 was reported to
the CCS Committee on 15 May 2024.
Complete
carbon footprint for
indirect emissions not
currently measured
Prepare Future Carbon Management Report reviewing
current strategic net zero work being undertaken by the
Council and examples of other local authorities net zero
plans/route maps for CCS Committee by March 2025, and
consider the development of a carbon emission reduction
plan
Whilst the Council has a zero direct emissions (scope 1) target by
2038, it does not have a route-map in place to achieve this target. The
Sustainability Team is currently working with Resources to develop a
forthcoming committee report which will outline key national carbon
reduction targets and legislation for those individual Services (namely
Property and Fleet) who contribute most to Council carbon emissions,
and their next steps in reducing carbon emissions in the medium to
long term.
Green
Present 2023-24 year-end carbon management report to
CCS Committee by December 2024
An update will be provided in Q4. Report Later
Page 24 of 51
41

Page 42

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
Place and Communities
Progress a transition to net-zero, energy efficient and climate resilience homes, buildings and infrastructure, and minimise the unsustainable use ofnatural resources and regenerate where appropriate
Action Measures Comments/ Progress Status
Develop the Public
Bodies Climate Change
Duties Report
Work with Services to complete the Public Bodies Climate
Change Report 2023-24 for submission to the Scottish
Government by 30 November 2024
The annual Public Bodies Climate Change Duties Compliance report
for 2023/24 has been completed and submitted to the Scottish
Government. The report was approved by the Corporate Management
Team and Executive Committee (13 November 2024) prior to
submission.
Complete
Support towns to
transition to net zero
Undertake feasibility planning for the implementation of the
findings of the Town Centre net zero study by March 2025
The Town Centre Net Zero study is in the process of being
incorporated into all town centre masterplans.
This study considers each town on an individual basis and looks at
interventions which could be incorporated to make each town more
sustainable. These include measures such as the introduction of
district heating on new developments, sustainable business practices
and the introduction of more greening in town centres.
By taking a holistic approach to new development in towns, alongside
the practice and approach of those who use the town centre it is the
hope that carbon consumption can be reduced.
Report Later
Page 25 of 51
42

Page 43

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
Place and Communities
Progress a transition to net-zero, energy efficient and climate resilience homes, buildings and infrastructure, and minimise the unsustainable use ofnatural resources and regenerate where appropriate
Action Measures Comments/ Progress Status
Explore funding and
finance models for
net-zero and climate
adaptation projects
Present findings of research into potential funding and
finance models and examples of good practice elsewhere to
CCS Steering Group by March 2025
A report was presented to CCS Committee in August 2024 on a
proposed model for climate investment within Glasgow City Council
(GCC) with potential for roll out across Glasgow City Region. SLC
Officers have met with the project lead at GCC, to discuss the new
model for climate investment. Officers will continue engagement as the
project develops to identify the most appropriate routes for
collaboration.
Green
Continue to administer
and monitor the Climate
Emergency Fund
Ensure project delivery and outcomes are achieved by the
end of March 2025. Report on progress and impact of the
funding to the Climate Change and Sustainability Committee
The fund has been committed to posts, internal projects and
community grants and projects are progressing.
A mid-term report on the progress and impact of the Climate
Emergency Fund was presented at the Climate Change and
Sustainability Committee in November 2022. This report highlighted
the progress made and impact of the fund so far and how the fund has
been allocated. A full-term report on the Climate Emergency Fund will
be presented to the Climate Change and Sustainability Committee
following completion of all projects (scheduled for June 2025).
Green
Ensure sustainability is
considered within capital
and revenue budget
plans
Continue to embed the Sustainability Impact Assessment
Process as part of decision-making for both capital and
revenue proposals
Sustainability Impact Assessments have been embedded as part of
the new Integrated Impact Assessments being implemented by the
Council. These will be completed for both the Revenue and Capital
Budgets for 2025/2026, as appropriate.
Green
Page 26 of 51
43

Page 44

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
Place and Communities
Progress a transition to net-zero, energy efficient and climate resilience homes, buildings and infrastructure, and minimise the unsustainable use ofnatural resources and regenerate where appropriate
Action Measures Comments/ Progress Status
Deliver training, awareness and upskilling on Sustainability
Impact Assessment for the revenue and capital budget
process
Training on the new Integrated Impact Assessments, as well as on-call
support and advice, has been made available in advance of
completing the Integrated Impact Assessments for the 2025/2026
Revenue Budget. This includes provision of support to officers on the
element that covers Sustainability Impact Assessments.
Green
Page 27 of 51
44

Page 45

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
Place and Communities
Progress a transition to net-zero, energy efficient and climate resilience homes, buildings and infrastructure, and minimise the unsustainable use ofnatural resources and regenerate where appropriate
Action Measures Comments/ Progress Status
Integrate climate change
and sustainable
development into
finance strategy and
reporting
Explore options for better evidencing carbon emissions
associated with future Budget spend in line with Public
Bodies Climate Change Duties
With the roll out of the Integrated Impact Assessment process,
emissions are anticipated to be a key consideration. The Scottish
Government has stated that in line with future requirements for local
authorities to report on their Scope 3 emissions, a suite of guidance
materials will be produced and made available to public bodies over
the coming years to provide support in measuring emissions
associated with key Council functions including procurement.
Green
Page 28 of 51
45

Page 46

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
Place and Communities
Progress a transition to net-zero, energy efficient and climate resilience homes, buildings and infrastructure, and minimise the unsustainable use ofnatural resources and regenerate where appropriate
Action Measures Comments/ Progress Status
Manage flooding
priorities and deliver
prioritised actions under
the Local Flood Risk
Management Plan(s)
Deliver prioritised flood protection projects / studies in line
with available capital and revenue funding for 2024 - 2025
Programme of Culvert Maintenance:
This is an ongoing programme of works on the network of culvert inlets
and their surrounding areas, with a view to improving the performance
of assets and the safety of operatives. Works have been identified and
these include the repair/replacement of culvert inlet trash screens and
the construction of suitable access paths, steps, fencing and handrails.
These works are being progressed on a continuous basis throughout
the year.
Backmuir Road, Hamilton:
Proposed works include the repair of damaged security fencing,
improved access for mechanical cleaning operations and repair of
damaged gabion baskets at this culvert inlet. Due to a reduction in
staff members within the Flood Risk Management (FRM) team, the
extent of the required works at this location have still to be clarified.
These works are now programmed to be instructed to a contractor in
Oct/Nov 2024 with works being undertaken in January 2025
depending upon contractor availability.
Park Avenue, Coulter:
There is proposed installation of Property Level Protection (PLP)
measures and community resilience measures in the vicinity of Park
Avenue, Coulter. The specification and delivery mechanism of PLP
measures is still under review at this time, however, these PLP
measures are still expected to be implemented this financial year.
Community Resilience measures, consisting of a large storage
container, have been ordered and due for delivery in Oct/Nov 2024.
Jonquil Way, Carluke:
Proposed works include creating a flood bund adjacent to Jonquil Way,
to intercept and attenuate flood water during heavy rainfall events to
protect adjacent residential properties. However, due to recent
Green
Page 29 of 51
46

Page 47

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
Place and Communities
Progress a transition to net-zero, energy efficient and climate resilience homes, buildings and infrastructure, and minimise the unsustainable use ofnatural resources and regenerate where appropriate
Action Measures Comments/ Progress Status
discussions with Scottish Water relating to the potential for them to
deliver large-scale flood intervention measures in this area, work has
not yet progressed at this location while waiting for clarification of
Scottish Water’s proposals. Further details relating to this work will be
provided in the Q4 update.
James Hamilton Heritage Loch, East Kilbride:
In response to the recommendation contained within the Reservoir
Engineer’s report, work is progressing on the internal lining of the
outflow pipe that drains the James Hamilton Heritage Loch in East
Kilbride. These works were originally programmed for June 2024;
however, contractor availability issues have led to a delay in
commencing works. Further to the latest Reservoir Inspection being
carried out during September 2024, these lining works are estimated
to be completed this calendar year.
Page 30 of 51
47

Page 48

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
Place and Communities
Progress a transition to net-zero, energy efficient and climate resilience homes, buildings and infrastructure, and minimise the unsustainable use ofnatural resources and regenerate where appropriate
Action Measures Comments/ Progress Status
Improve resilience of the
road network through
routine maintenance
Review current road maintenance practices to improve
climate change resilience through the use of alternative
methods, materials and design standards
The service regularly considers alternative maintenance techniques in
conjunction with industry best practice to help improve carbon footprint
and climate change resilience.
The use of alternative techniques is subject to the scrutiny of the
Engineering teams where consideration is given to engineering merit,
operational delivery, future maintenance, and whole life cost.
The service regularly collaborates with Scottish Collaboration of
Transportation Specialists (SCOTS) and the Scottish Roads Research
Board to drive innovation within this area.
Green
Utilise innovative and
new information
technologies for
environmental benefits
Develop business cases for demonstrator Internet of Things
(IoT) projects
IOT describes a network of devices with sensors, processing ability,
software and other technologies that connect and exchange data with
other devices and systems over the Internet or other communications
networks.
IT Services have included IoT within the Digital Transformation
workstream. The project has been placed on hold to better align with
Digital Transformation timeline. IT Services will provide updates as this
progresses through 2024/25.
Red
Continue the migration to Oracle Cloud Fusion system to
support agile working, employee self-service and
engagement
The Oracle Cloud Fusion system is live for Finance and Procurement,
HR and Payroll functionalities. Finance and Procurement are now in
normal operation, HR & Payroll remain in post-go-live hypercare.
Further information will be available in the Q4 update.
Green
Page 31 of 51
48

Page 49

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
Place and Communities
Progress a transition to net-zero, energy efficient and climate resilience homes, buildings and infrastructure, and minimise the unsustainable use ofnatural resources and regenerate where appropriate
Action Measures Comments/ Progress Status
Explore sustainable web design to reduce the Council
website's carbon footprint
Redesign of the Council website and intranet is included in the
2024/25 IT service plan and sustainable web design will be considered
as part of the project. The ongoing focus seeks to ensure that carbon
footprint is minimised through the reuse of code and compressed
images to reduce server load.
Green
Implementation of
revised Building
Regulations in relation
to energy performance
in new buildings and the
adaptation of existing
buildings  
Continue to raise awareness and upskill surveyors on the
Proposed Domestic Building Environmental Standards
(Scotland) Bill, considering changes to legislation and
building regulations, through facilitating training and
awareness sessions
Ongoing training and awareness sessions have been provided for
surveyors and other colleagues involved in new building development
within the Council.
Green
Page 32 of 51
49

Page 50

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
Place and Communities
Progress a transition to net-zero, energy efficient and climate resilience homes, buildings and infrastructure, and minimise the unsustainable use ofnatural resources and regenerate where appropriate
Action Measures Comments/ Progress Status
Increase the overall
energy efficiency of
homes and increase the
rates of decarbonisation
within domestic
properties across South
Lanarkshire
Support homeowners and private landlords to improve the
energy efficiency of their properties through administering
and promoting the Energy Company Obligation Scheme
(ECO) and Energy Efficient Scotland: Area Based Schemes
The council’s ECO4 scheme opened for applications in July 2023 and
runs until 31 March 2026.
By 30 September 2024, 463 households have been assessed as
eligible for energy efficiency measures to be installed in their homes,
representing 97% of all applications received.  The majority of eligible
households contain at least one member that has a health condition
that makes them vulnerable to the effects of living in a cold home.
At 30 September 2024, 584 energy efficiency measures have been
installed in 214 homes across South Lanarkshire.
Ofgem is currently testing a new online Portal for Council submissions
and is working towards the development of ECO5.
Green
Support Registered Social Landlord partners to improve the
energy efficiency of their housing stock and take forward
opportunities to work jointly to decarbonise heating systems
Support continues to be provided to Registered Social Landlord (RSL)
partners to help improve the energy efficiency of their own housing
stock. This includes sharing grant funding opportunities as well as
information that can be distributed to tenants to provide support for
those impacted by or susceptible to fuel poverty. Some of the support
consists of short-term financial relief provided through third sector
partners.
Consideration will be given later in 2024/25 to jointly progressing
energy efficiency improvements with RSLs on housing stock utilising
national grant funding to do so.
Green
Page 33 of 51
50

Page 51

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
Place and Communities
Progress a transition to net-zero, energy efficient and climate resilience homes, buildings and infrastructure, and minimise the unsustainable use ofnatural resources and regenerate where appropriate
Action Measures Comments/ Progress Status
Deliver Housing Investment Programmes to improve the
energy efficiency of the Council’s existing homes
£33.506m of refurbishment works have been approved for 2024/25, of
which £6.5m is targeted towards energy efficiency works.
Green
Deliver the Council’s affordable housing supply programme
to increase the proportion of new, energy efficient homes
with clean heating systems
The delivery of the new build programme is driven by national and
local sustainable development strategies. All new homes are built to
Silver Greener Standard as set out in Section 7, Silver Level, of the
2011 Building Regulations in respect of both Carbon Dioxide
emissions and Energy for Space Heating. In addition, all Strategic
Housing Investment Plan sites that have been granted planning
approval from February 2023 are being built to zero greenhouse gas
emissions. A higher grant subsidy is available from the Scottish
Government to help meet the cost of achieving such standards. In
addition, modern construction methods are utilised as far as possible
to help minimise adverse environmental impacts.
Green
Prepare for the
introduction of the new
Social Housing Net Zero
Standard (SHNZS)
Develop South Lanarkshire Council’s strategic approach to
meeting the new standard
The final meeting of the Scottish Government Review group to agree
the new SHNZS is scheduled to be held in October 2024. A strategy
will be developed once the details of the standard are known.
More information will be provided in the Q4 update.
Report Later
Page 34 of 51
51

Page 52

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
Place and Communities
Progress a transition to net-zero, energy efficient and climate resilience homes, buildings and infrastructure, and minimise the unsustainable use ofnatural resources and regenerate where appropriate
Action Measures Comments/ Progress Status
Develop South
Lanarkshire’s Local
Heat and Energy
Efficiency Strategy
(LHEES) and Delivery
Plan
Seek committee approval for the LHEES and delivery plan
and work with the relevant lead partners to implement the
agreed delivery plan for 2024/25
The LHEES Strategy and Delivery Plan was approved by the Council’s
Executive Committee on 26 June 2024.
A Co-ordinator has been recruited who is due to take up post at the
end of October 2024. Their remit will involve taking forward actions
outlined in the LHEES Delivery Plan. An action plan will also be
developed to plan and co-ordinate performance as well as monitoring
and reporting on LHEES progress and outcomes.
Green
Assess the Council’s
non-domestic buildings
and develop a detailed
action plan on how it will
meet the proposed
legislative requirement
of being heated by zero
carbon heat sources by
2038
Based on the findings from the net zero feasibility studies
progress the development of an action plan to meet the
national targets for publicly owned buildings by 2038
The Non-Domestic Buildings Net-Zero Feasibilities paper was
submitted to the Climate Change and Sustainability Committee on 15
May 2024.
The Scottish Government have committed to bring forward a Heat in
Buildings Bill in 2025 and this legislation will inform future programmes
of work.
An action plan will be developed for the LHEES delivery plan actions in
early 2025 and performance monitoring and reporting on LHEES
progress/outcomes will be introduced.
Report Later
Page 35 of 51
52

Page 53

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
Place and Communities
Progress a transition to net-zero, energy efficient and climate resilience homes, buildings and infrastructure, and minimise the unsustainable use ofnatural resources and regenerate where appropriate
Action Measures Comments/ Progress Status
Utilise the Central
Energy Efficiency Fund
(CEEF) Programme to
deliver energy efficiency
improvement projects in
Council non-domestic
buildings
Implement the agreed CEEF delivery plan for 2024/25 Of the eight projects approved at Executive Committee, three are
complete, one is currently on site and three have still to be
programmed. One project has been cancelled as the necessary
external funding was not achieved.
Green
Support the delivery of
Climate Ready Clyde's
(CRC) Adaptation
Strategy
Continue as an active member of the CRC Local Authority
Forum participating in city region wide workshops and
events, creating connections and opportunities for
development/co-sharing of knowledge and training by March
2025
South Lanarkshire Council continues to be an active member of CRC
which meets quarterly. This is the Local Authority Forum for
Collaborative Climate Adaptation Action across the Glasgow City
Region. The Forum allows local authorities to work together to build
capacity to support adaptation action and look for opportunities to
deliver integrated and collaborative adaptation. Officers continue to
attend workshops and progress meetings as required and contribute to
and inform the work programme of CRC.
Green
Contribute to the development and implementation of local
actions that contribute to the wider Glasgow City Region's
(GCR) Adaptation Strategy, where appropriate, working
across Council Resources
SLC continues to be an active member of Climate Ready Clyde and
contributes to raising awareness internally of the GCR Adaptation
Strategy. Actions within the GCR Adaptation Strategy are incorporated
within the Council's Sustainable Development and Climate Change
Strategy. Climate Ready Clyde has indicated that a new monitoring
framework will be developed by the end of 2024/25 which will better
enable local authorities to report on progress against the GCR
Adaptation Strategy. Further progress on this will be reported at Q4.
Green
Benchmark the Council
against climate change
risk assessments
Undertake a capability assessment to understand the
Council’s current status and to identify gaps and areas for
improvement by March 2025 
Climate Ready Clyde is undertaking a review of the Capabilities
Framework to be completed later in 2024. Once the refreshed
Capabilities Framework is made available a capability assessment will
be undertaken with the Climate Change and Sustainability Officers
Group.
Report Later
Page 36 of 51
53

Page 54

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
Improve the availability and access to quality local outdoor spaces and services
Action Measures Comments/ Progress Status
Ensure national
planning policy set out in
National Planning
Framework 4 in relation
to climate change,
biodiversity and
sustainable travel is
embedded in decision
making process for
Collation of appropriate information and data to inform the
Evidence Report required as new first stage of LDP
preparation by December 2024
Close collaboration has been established with key Council services to
gather and assess relevant data and information as part of the
preparation of the Evidence Report. In terms of timescales, it is
intended that the Natural Environment Topic Paper will be published in
the latter part of 2024. After which interested parties will have the
opportunity to comment on the findings to date and identify any gaps in
evidence or disagreements with the outcomes. Thereafter, the
Evidence Report will be presented to full Council in mid-2025 before
being submitted to Scottish Ministers for approval.
Amber
planning applications
and the preparation of
the South Lanarkshire
Local Development Plan
3.
Explore options for data-gathering and analysis to ensure
climate, biodiversity, and sustainability related topics (such
as surface water flooding, flood risk, nature networks and
green infrastructure) to enable data-driven decision making
through tools such as GIS
As noted above, extensive collaboration has taken place with key
Council services as well as external organisations such as Nature
Scot, the Glasgow City Region Environment Team and RSPB to
ensure appropriate data is gathered and assessed. The Planning
Service employed two data analysts in 2024 to inform this process.
Green
Page 37 of 51
54

Page 55

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
Improve the availability and access to quality local outdoor spaces and services
Action Measures Comments/ Progress Status
Provide guidance for Development Management colleagues
on how to consider climate change and sustainability topics
when assessing planning applications, utilising the State of
the Environment Report as evidence base
The State of the Environment report will form a significant part of the
Council’s Local Development Plan 3 Evidence Report, currently under
preparation.
It is also referenced in guidance on the wider topic of nature (including
biodiversity, trees, soils and natural places) that has been developed
and will be used in the assessment of planning applications. This will
be presented to the Planning Committee in Q3.
It is intended that awareness raising and Officer training will be
provided by the end of 2024/25.
Green
Continue to deliver upskilling, awareness, and training
sessions to Planning Officers and key stakeholders such as
Building Standards on climate change adaptation, net zero
and biodiversity
The Scottish Government has committed to publishing guidance on
biodiversity net gain, including the development of a metric. In addition,
new Planning and Climate Change guidance is being produced by the
Scottish Government to support the implementation of the National
Planning Framework 4 policy on mitigation and adaptation. This is
intended to integrate climate considerations into development
proposals and support emissions reduction and increased resilience to
climate risks.
Once it is published, awareness raising and training will be developed.
Amber
Prepare an Open Space
Strategy in partnership
with Glasgow and Clyde
Valley Green Network
Partnership and other
council services
Utilise the technical report provided by the consultant to
inform engagement on open space and establish an internal
working group to develop a strategy
The first round of engagement on open space will be carried out in late
2024. This will provide an opportunity for residents and communities to
have their say on the quality and quantity of open spaces in their area.
Thereafter, a draft document will be presented to the Planning
Committee in Spring 2025. Following this, a formal consultation will be
carried out.
Report Later
Page 38 of 51
55

Page 56

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
Improve the availability and access to quality local outdoor spaces and services
Action Measures Comments/ Progress Status
Open Space strategy to be presented to the Planning
Committee in 2026, following alignment with the timescales
for the LDP3 Evidence Report
A finalised version of the Open Space Strategy will be reported to the
Planning Committee in 2026.
Report Later
Empower communities to take climate action and be more environmentally sustainable
Action Measures Comments/ Progress Status
Continue to administer
and monitor the Climate
Emergency Community
grant fund
Allocate £110,000 to projects over financial year 2024/25 The majority of the Climate Emergency Community Grants Fund
2024/25 has been allocated to groups and full spend will be achieved
by March 2025. Projects are progressing and update reports will be
requested from grant recipients later in the financial year.
Green
Increase food growing
provision throughout
South Lanarkshire
Provide an opportunity for more people to grow food through
the provision of land for food growing, the promotion of
sustainable practices and supporting third sector
organisations involved in food growing
Cuningar Loop Allotment is due to be completed in November 2024.
Once completed, the new allotment site will provide more land for food
growing. Meanwhile, Officers continue to support food growing
opportunities by distributing newsletters with cultivation tips, promoting
composting, and working closely with allotment associations.
Green
Support the remediation
of vacant and derelict
land that promotes
social and
environmental benefits
Support Clyde Gateway Urban Regeneration Company in a
further phase of greening and environmental improvement
works at Cuningar Loop and in further remediation works in
the next phase at Shawfield Phase 2.
The creation of 50 food growing allotments at Cuningar Loop is due to
be completed in November 2024.
Remediation of the Shawfield Phase 2 site is being developed and
implemented following the successful Levelling Up Fund award from
UK Government.
Green
Page 39 of 51
56

Page 57

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
Take action to allow South Lanarkshire to become a zero-waste society
Action Measures Comments/ Progress Status
Work to support SME’s
in accessing wider
business support in
relation to climate
change and net zero,
including the circular
economy
Establish connections with organisations such as Business
Gateway Lanarkshire, Scottish Enterprise, Lanarkshire
Climate Action Hub to build capacity and share knowledge in
relation to climate change, net zero and circular economy
South Lanarkshire Council delivers a range of business and other
programmes aimed at supporting enterprises to align with circular
economy principles, adapt to climate change and reduce carbon
emissions. Examples of this include: the Council’s grant programmes
and Council referral to the Extend Plus programme (which allows
businesses to obtain a carbon baseline report).
Business Gateway Lanarkshire delivers a range of national and local
business support services, including workshops, training and 1-1
Advisor support to businesses including social enterprises, and is
represented on the South Lanarkshire Social Economy Steering group.
Social Enterprises are signposted to Business Gateway and the
Supplier Development Programme to access a range of business and
procurement support as a matter of course.
South Lanarkshire Council Business Support team, along with
Business Gateway Lanarkshire supported South Lanarkshire College
with the launch of their College Local Innovation Centre in Sustainable
Development on 25 September 2024.
Lanarkshire Climate Action Hub was invited in early 2024 to participate
in the Social Economy Steering group and has engaged with the
sector via local network events. The Hub also has a dedicated web
portal and local support programmes which are promoted to the sector.
Green
Page 40 of 51
57

Page 58

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
Take action to allow South Lanarkshire to become a zero-waste society
Action Measures Comments/ Progress Status
Undertake a review of
the Climate Confident
South Lanarkshire Pilot,
supporting SMEs in
accessing expertise and
advice to reduce their
carbon footprint
Follow up on recommendations as appropriate following
review of Climate Confident South Lanarkshire pilot
The Climate Confident South Lanarkshire pilot has now been
completed. This pilot has enabled the refinement of the Scottish
Council for Voluntary Organisations’ Climate Confident National Portal,
ensuring it provides suitable support for social enterprises to
implement carbon reduction measures following the completion of their
carbon baseline study. When social enterprises reach out to South
Lanarkshire Council for sustainability and climate change assistance
they are directed to the portal for information, guidance, and funding
options.
Additionally following the pilot, with the support of the Scottish
Government, the Lanarkshire Climate Action Hub has been
established. A representative from the hub has been invited to join the
South Lanarkshire Social Economy Steering Group which oversees
actions aligned with the local Social Economy Strategy.
Green
Review waste services
(infrastructure and
collection services) in
line with delivering
current and future waste
legislation (including the
circular economy)
Continue to undertake a review of the waste service through
2024/25 that will determine most efficient refuse/ recycling
collection services and related waste services infrastructure
The review, which considers how the service will comply with new
legislation, such as the Circular Economy (Scotland) Act 2024, the
Producer Responsibility Obligations (Packaging and Packaging
Waste) Regs 2024, and forthcoming strategies such as the Circular
Economy and Waste Route Map, is progressing in line with relevant
timescales.
Green
Page 41 of 51
58

Page 59

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
Take action to allow South Lanarkshire to become a zero-waste society
Action Measures Comments/ Progress Status
Review of recycling bins
at flatted properties in
South Lanarkshire
Continue to review existing arrangements at flats during
2024/25 and work with Corporate Communications to
produce communications campaign
The project is progressing well. A successful pilot in Springhall area,
which attracted funding from Scottish Government Recycling
Improvement Fund,  has led to a full re-designation of recycling bins in
the Cambuslang and Rutherglen Area. The project is scheduled to be
extended to East Kilbride and Hamilton areas over the next six
months.
Green
Manage and monitor
food waste in schools
Undertake a review and conduct data analysis of the pilot
“Waste Warrior” initiative prior to exploring further roll-out
options
This programme has been implemented in 27 schools, providing a fun
and engaging learning experience. As a result, changes have been
made to specific menu items and the quantities of food produced. Data
on food waste highlights the importance of focusing on waste
reduction and maintaining ongoing engagement to sustain
improvements. Looking ahead, Education Resources has developed a
learning resource pack using materials from Zero Waste Scotland,
which will be made available to all schools.
Green
Enhance, protect, and respect the outdoors and the natural and historic environment.
Action Measures Comments/ Progress Status
Make South Lanarkshire
a cleaner place to live,
work and visit, free of
litter, fly-tipping and dog
waste through
progression of actions in
the Litter Strategy
(2022-2027)
Continue to progress actions on reducing litter, fly-tipping
and dog waste in South Lanarkshire through working with
stakeholders, partners and community groups as per the
Litter Strategy Action Plan (2022-2027)
The actions and projects are being progressed and we will be
discussing what amendments and changes we want to make to the
Action Plan next year.
The annual Litter Strategy Action Plan progress update will be
presented to the Climate Change and Sustainability Committee on the
18th December 2024.
Green
Page 42 of 51
59

Page 60

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
Conserve, restore and improve biodiversity, and use nature-based solutions in tackling the climate crisis
Action Measures Comments/ Progress Status
Review Council use of
herbicide with a view to
reduce the amount used
Continue to look at alternative methods to control weeds.
Carry out further trials during 2024-25
The service continues to look at alternative methods of weed control
available on the market. New tractors and brushes were procured this
year and are being utilised in the East Kilbride and Hamilton areas.
This is providing the opportunity to trial mechanical weed control
methods.
Details on the outcome of the trial will be provided in Q4.
Green
Page 43 of 51
60

Page 61

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
Conserve, restore and improve biodiversity, and use nature-based solutions in tackling the climate crisis
Action Measures Comments/ Progress Status
Measure and increase
tree canopy cover
across South
Lanarkshire
Across South Lanarkshire, continue to measure / assess
existing tree canopy cover and tree equity
Across South Lanarkshire, with the Clyde Climate Forest (CCF) and
tools such as Tree Equity Score UK, the Council continues to measure
and assess tree canopy cover and tree equity. The overall tree canopy
cover is currently 17% (2032 target 21%) with the urban tree canopy
assessed by CCF as 17.2% (2032 target 20%).
Trees are essential to public health and wellbeing, yet not everyone
has good access to trees and their benefits. Unequal distribution of
canopy cover means some communities – and most likely those that
would benefit most – are potentially losing out. Therefore tools such as
the Tree Equity Score UK are being used to better understand
disparities in urban tree canopy and identify areas in greatest need of
people-focused investment in trees.
Green
Page 44 of 51
61

Page 62

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
Conserve, restore and improve biodiversity, and use nature-based solutions in tackling the climate crisis
Action Measures Comments/ Progress Status
On Council owned or controlled land, continue to develop
records of the nature, condition and resilience of tree assets
and their canopy cover
On Council owned or controlled land, the Council continues to develop
records of the nature, condition and resilience of tree assets through
onsite assessments and updating web-based tree asset management
software.
This approach to collecting records and the ability to report and
analyse tree assets at a landscape level is starting to provide an
insight into composition and structure, as well as resilience, benefits
and the management strategies required as part of developing the
Tree Canopy Cover Strategy. The approach is also aiding an insight
into tree diversity which helps inform tree planting requirements and
offers insight into progress towards developing a broad-leaved nature
network.
Green
Page 45 of 51
62

Page 63

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
Conserve, restore and improve biodiversity, and use nature-based solutions in tackling the climate crisis
Action Measures Comments/ Progress Status
On Council owned or controlled land, continue to identify
sites suitable for planting trees to increase canopy cover and
species diversity. Develop a masterplan with a prioritised
delivery plan. Seek additional funding for tree and woodland
planting through internal and external sources, including
community groups
A high-level study has been completed by the CCF that initially
identified opportunities for tree planting on Council owned or controlled
land. The opportunities identified involve various scales of planting, all
of which could positively contribute to an increase in canopy cover.
Although the study has yet to be fully integrated, 588 sites are already
in the assessment process. Prioritisation is based on canopy, equity,
Nature Networks and resource. The study information has been put
forward for inclusion in the Local Development Plan Evidence Report.
Using tree asset management software, a dynamic 5-year planting
masterplan is being created.
This winter, 13,227 trees are scheduled for planting with the viability of
a further 6,900 potential trees in Larkhall being assessed. 5,135
scheduled trees are being provided at no cost by our CCF partners i.e.
‘Woodland Trust, Trees for Cities, The Tree Council and The
Conservation Volunteers. So far, £13.5k of external funds have been
secured from Arbor Day Foundation and Trees for Cities. Scottish
Government are also providing £10,000 for developing tree planting
projects on vacant and derelict land. We continually work to identify
additional funding available.
Forming part of the Tree Councils Volunteer Tree Warden program
CCF has now created a Community Volunteer Coordinator to
co-ordinate and manage a team of volunteer Tree Wardens, who will
help in the creation and monitoring of tree planting projects. The Tree
Councils Young Tree Champions program also continues to be
promoted within our schools. A number of community CCF planting
events are planned this planting season.
Green
Page 46 of 51
63

Page 64

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
Conserve, restore and improve biodiversity, and use nature-based solutions in tackling the climate crisis
Action Measures Comments/ Progress Status
Contribute to the delivery of the Clyde Climate Forest,
working with partners to achieve targets outlined in the
Concordat
The council continues to contribute to the delivery of the Clyde Climate
Forest, working with partners to achieve targets outlined in the CCF
Concordat.
The CCF Canopy Working Group and Steering Group have been
combined to create a more efficient Delivery Working Group that the
Council chairs.
Since launching in June 2021, the CCF initiative has planted a
staggering 3.5 million trees across Glasgow City Region. The
initiative’s 3-Year Review highlighted that more than 10,000 urban
trees were planted by local community groups, volunteers and school
children across 27 community planting events. The initiative continues
to forge very strong partnerships and joined up delivery.
Green
Increase biodiversity
and invest in peatlands
across South
Participate in the Clyde Peatlands Project to bring about a
step change in the scale and rate of peatland restoration
across the City Region
Clyde Peatlands are currently awaiting news on funding for this year.
The aim is to have feasibility surveys completed for the Council's two
peatland sites early next year.
Report Later
Page 47 of 51
64

Page 65

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
Conserve, restore and improve biodiversity, and use nature-based solutions in tackling the climate crisis
Action Measures Comments/ Progress Status
Lanarkshire Work with key partners including the Clyde grasslands and
Clyde wetlands projects to identify and establish regional
nature networks
For the past two years the Council has been working in partnership
with Clyde Grasslands, Clyde Wetlands and Clyde Climate Forest
(CCF) to establish Nature Networks. As a result, a series of proposed
Nature Network maps have been produced, and Officers are now
working with the Council Planning Team for the maps to be included in
the Local Development Plan 3.
An Evidence Report has been produced on Nature Networks as part of
the Local Development Plan process.
Green
Continue to improve key ecosystems within our Local Nature
Reserves and Country Parks utilising the Nature Restoration
Fund
The Scottish Government Nature Restoration Fund (NRF) has been
deferred for 2024-25, with the hope of being reinstated next year.
For the past three years the NRF has allowed the Council to employ
seasonal staff for six months to improve and create habitats within
South Lanarkshire Local Nature Reserves, Country Parks and other
greenspaces. Work has included: planting trees, creating wildflower
meadows for pollinators and removing invasive non-native species.
With the withdrawal of the NRF this year, Officers are investigating
alternate funding schemes and partnership working opportunities
available, to continue this work.
Amber
Implement new
technologies and more
sustainable cleaning
materials within Council
facilities
Deliver Aquateck in Corporate Units and further roll out in the
second quarter of 2024 to all High Schools in South
Lanarkshire Council, following a successful pilot exercise in
2023/24
The Aquateck system has been rolled out in all Corporate Units with
the exception of East Kilbride Civic Centre and has now been
implemented and working successfully in all 17 High Schools.
Complete
Page 48 of 51
65

Page 66

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
Enable a fair transition to a green economy leaving no one behind
Action Measures Comments/ Progress Status
Deliver the UK Shared
Prosperity Fund to help
ensure a just transition
to net zero
Progress delivery of the UK Shared Prosperity Fund. Fund
initiatives that support the council, communities, and
businesses transition to net zero
The UK Shared Prosperity Fund supports two initiatives:
1. The Climate Emergency and Resilience Grant programme which
awarded grants through 2023 and early 2024.
2. The Extend Plus programme delivered by the Glasgow City Region
on behalf of the Council which supports businesses to undertake a
carbon baseline analysis which allows them to identify carbon
reduction opportunities and measures.
Green
Consider climate
change impacts on the
Council’s workforce in
Consider the impact of climate change and the need for new
or additional skills or knowledge as part of the Resource
workforce planning process in 2024/25
The workforce planning timeline has been approved at CMT. The
strategy and toolkit have been revised and both include references to
the Sustainable Development and Climate Strategy.
Green
the workforce plan
including need for green
skills
Consider and explore options for embedding sustainability
and climate related behaviours in the Council’s Behaviours
Framework, particularly key roles
This will be picked up as part of a review of the competence initiative
which is scheduled to commence in 2025.
Report Later
Page 49 of 51
66

Page 67

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
Lead the transition to a circular economy and improve resource efficiency through responsible consumption and production, and buying and sellingof local goods and services
Action Measures Comments/ Progress Status
Review the scope and
scoring of sustainability
requirements in
procurement contracts
and build knowledge
and awareness of
evaluating sustainability
issues
Continue to embed new tender scoring approach, new
sample questions, through training and development of
Resource clients, working to improve knowledge of
sustainability issues in specification and tenders, including
scoring and evaluating tender responses
A new procurement process, including sustainability guidance and
sample questions was published and shared with Officers. In addition
to this, a series of training sessions were provided to Resource clients
throughout Q2.
Complete
Utilise Scottish
Government’s Flexible
Framework Assessment
Tool to assess current
level of performance to
realise intended
sustainable outcomes
Work to progress towards Level 4 of the Flexible Framework
to show continuous progression in embedding consideration
of climate change and sustainability in procurement activity
and outcomes
The Flexible Framework is reviewed every six months. There are five
categories for self assessment: People, Strategy, Process,
Stakeholders, and Reporting. At the end of Q2, People, Strategy, and
Process had achieved Level 3, reflecting improvements in
sustainability processes and training arrangements. There is an action
plan in place to work towards Level 4 in these categories. The
remaining two categories, Stakeholders and Reporting, remain at
Level 2 and work is ongoing to achieve Level 3.
Amber
Provide procurement
support to Council
services within contract
specification
development
Raising awareness of the new sustainable procurement
process which provides support to Council services for
non-priority contracts through training and development, with
all priority contracts going through Scottish Government
Sustainability Test
The Sustainability in Procurement training programme was
successfully rolled out to 45 contract managers based in Resources
during Q2.
Complete
Improve contract
management of
sustainability factors
through the Council’s
new electronic appraisal
process
Monitor sustainability measures and KPIs in contracts to
ensure sustainability performance and achievement of
intended sustainability outcomes
Where sustainable outcomes are identified as a performance indicator,
these are being monitored through the performance appraisal process.
Performance appraisals for high risk/high value contracts will be
migrated to electronic appraisals via Oracle Fusion by Q4.
Green
Page 50 of 51
67

Page 68

IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
IMPROVe - SLC Performance Management System                                                                                                                                                                       Report printed on Monday 18 November 2024
04:30:42pm
Sustainable Development Strategy Improvement Actions
Support South Lanarkshire’s businesses in the transition to a net-zero economy and helping to ensure they are climate resilient
Action Measures Comments/ Progress Status
Promote the support
that is available to
businesses for good
sustainability outcomes
Publicise funding opportunities and share information with
businesses for carbon emission reduction and improved
energy performance
The Council business support grant provides assistance to businesses
running projects that are exclusively related to carbon reduction.
Officers have also supported the launch and ongoing development of
the College Local Innovation Centres (CLIC) for Sustainable
Development at South Lanarkshire College. The Council attended the
recent Sustainability Innovation event at South Lanarkshire College
where information was provided publicising funding opportunities and
sharing information on support to reduce carbon emissions. The event
was promoted on all of the Council's social media channels, including
LinkedIn, in order to reach businesses.
Green
Promote and encourage
the use of bespoke
Lanarkshire sustainable
tourism resources,
commissioned via
Green Tourism
Engage tourism businesses to uptake more sustainable
practices utilising the resources situated on the
VisitLanarkshire website by March 2025
By March 2025, the Council aims to engage more tourism businesses
in adopting sustainable practices, leveraging the sustainable tourism
resources available on the VisitLanarkshire website that have been
created in partnership with Green Tourism. Some businesses have
already utilised the green tourism resources, with The Scottish Tea
House having developed a Sustainability Policy and two businesses
having written their "green stories" to enhance their PR efforts and to
allow further promotion of their sustainable tourism initiatives. There is
also now a section on VisitLanarkshire.com to display these green
stories and to encourage tourists to visit Lanarkshire for an
eco-tourism break.
Green
Encourage and
influence sustainable
property improvements
in business premises
Engage consultants to undertake SLC-wide review of
industrial properties and to identify opportunities for
incorporating net zero and sustainable technologies into the
delivery of SLC projects by March 2025
Consultants Ryden LLP have completed four industrial land and
property reviews throughout South Lanarkshire that will inform
planning policy and future capital investment. Net Zero and
sustainable technologies will be incorporated into projects where
applicable. The latest example is the design of the Net Zero Industrial
Units for development at Cathcart Road, Rutherglen.
Complete
Page 51 of 51
68

Page 69

Report
Agenda Item 
Report to: Climate Change and Sustainability Committee 
Date of Meeting: 18 December 2024
Report by: Executive Director (Community and Enterprise
Resources)  
Subject: Public Bodies Climate Change Duties - Annual Report
2023-24 
1. Purpose of Report
1.1. The purpose of the report is to: -
[purpose]
 present the Council’s annual Public Bodies Climate Change Duties Compliance
report for 2023-2024, as legally required under the Climate Change (Scotland)
Act 2009
[1purpose]
2. Recommendation(s)
2.1. The Committee is asked to approve the following recommendation(s):-
[recs]
(1) that the Council’s Public Bodies Climate Change Duties Compliance report for
2023-24, which was approved by the Executive Committee on 13 November
2024 and has since been submitted to the Scottish Government, be noted. 
3. Background
3.1. The statutory framework for climate action and reporting is outlined by the Climate
Change (Scotland) Act 2009 and the Climate Change (Public Duties) (Scotland) Act. 
3.2. Section 44 of Part 4 of the Climate Change (Scotland) Act 2009 states that a public
body must, in exercising its functions, act:
 in the way best calculated to contribute to the delivery of Scotland’s national
emissions reduction targets,
 in the way best calculated to help deliver Scotland’s statutory climate change
adaptation programme, and
 in a way that it considers is most sustainable. 
3.3.  Public bodies are required to prepare annual reports on their compliance with these
duties and publish and submit these reports to the Scottish Government by 30th
November each year. 
3.4. The Council has complied with the statutory reporting requirement every year since its
introduction in 2015. The Council has also been reporting climate change action on a
voluntary basis since 2007 as a signatory of Scotland’s Climate Change Declaration. 
3.5. Due to the Committee timetable this year, it was not possible to present the full report
to the Climate Change and Sustainability (CCS) Committee prior to submission.
Instead, it was agreed at the CCS Committee on 9 October 2024 that the report be
4
69

Page 70

submitted for approval at the Executive Committee meeting on 13 November 2024
and presented to the CCS Committee for noting on 18 December 2024. 
4. Climate Change Duties Report 2023-24
4.1. The report is in a similar format to previous years and is based on a template issued
by Scottish Government. It contains six sections: 
1 Profile of Reporting
Body
Provides a better understanding of the scale of activity
of the body in addressing climate change in relation to
its size.
2 Governance,
Management and
Strategy
Organisations should be able to demonstrate a robust
system of governance, management and strategy in
respect of duties, decision making and leadership on
climate action.
3 Emissions, Targets
and Projects
Provides data on corporate greenhouse gas (GHG)
emissions arising from organisational activities
including service delivery and the exercise of other
functions.
4 Adaptation Seeks to establish if the body has assessed the current
and future risks climate change presents to its assets,
infrastructure, service provision and business
continuity. Reporting on action and capacity building,
and monitoring and evaluating adaptation progress. 
5 Procurement  Clarify how sustainable procurement policy has had an
impact on climate change reduction, reporting and
compliance issues. 
6 Validation  Demonstrating internal and/or external validation of
data. 
4.2. A copy of the Public Bodies Climate Change Duties report for 2023-24 can be found
at Appendix 1. Some of the key achievements from the 2023-24 report are noted
below:   
 There is a robust climate change and sustainability governance structure led by
the Climate Change and Sustainability Committee and supported by the Climate
Change and Sustainability Steering Group. 
 A new Council Climate Change and Sustainability Officers Group has been set
up to support the work of the Climate Change and Sustainability Steering Group.
 A Sustainability Impact Assessment process has been developed and
implemented for the Council’s Capital and Revenue Programmes.
 A Strategic Environmental Assessment process is in place that ensures that all
plans, polices and strategies undergo an environment assessment which
includes considering climatic factors.
 Carbon emission reductions of 68.9% have been reported in 2023-24 compared
to the baseline year of 2005-06. This includes a 9.46% reduction in 2023-24
compared to the previous year.
 The Council’s Biodiversity Strategy and the Biodiversity Duty Implementation
Plan was approved by the Climate Change and Sustainability Committee in
February 2024.
 South Lanarkshire Council continues to participate in the Climate Ready Clyde
partnership which is a collaborative initiative with an adaptation strategy and
70

Page 71

action plan for the Glasgow City Region (which includes all South Lanarkshire’s
rural and urban areas). 
4.3. The information contained in Section 3 of the report provides data on corporate
greenhouse gas (GHG) emissions arising from organisational activities. It details the
Council’s carbon footprint which is currently measured from five sources: 
 Buildings energy
 Fleet
 Employee travel
 Household waste
 Street lighting  
4.4. Other sources that are reported as part of the Public Bodies Climate Change Duties
report but are currently not included within the Council’s carbon footprint include waste
and water from Council building and homeworking emissions. It was agreed at the
Corporate Management Team meeting on 21 March 2024 that these emissions would
be added to the Council’s carbon management reporting from 2024-25. 
4.5. The information contained in Section 4 of the report details how the Council is
assessing and adapting to the impacts of climate change. The strategies and plans
relevant to this include the Sustainable Development and Climate Change Strategy,
Risk Management Strategy, Local Development Plans, Local Transport Strategy and
Biodiversity Strategy. 
5. Employee Implications
5.1. The Council’s Policy and Performance Team produce the annual Public Bodies
Climate Change Duties report in conjunction with relevant Council Resources. The
statutory reporting regime has elevated the importance and accountability of climate
change reporting within the Council.   
6. Financial Implications
6.1. Collection of climate change information is a core management task and therefore is
absorbed into the daily business operations. 
7. Climate Change, Sustainability and Environmental Implications 
7.1. The Council’s Sustainable Development and Climate Change Strategy outlines the
action to meet our climate change duties and has undergone a full Strategic
Environmental Assessment (SEA).  This can be found on the Scottish Government’s
SEA Gateway database. 
8. Other Implications
8.1. The annual statutory reporting requirements have implications for all Resources;
however, the following services will have more involvement: 
 Community and Enterprise Resources - Sustainable Development and Carbon
Management, Fleet Services, Environmental Services, Roads and
Transportation, Flood Risk Management, Street Lighting, Waste Services,
Resilience Support, Countryside and Greenspace, Planning and Building
Standards.
 Finance and Corporate Resources – Procurement, Finance (Capital Investment),
Risk Management.
 Housing and Technical Resources - Energy Management, Asset Management
and Property Services.
71

Page 72

8.2. Failure to meet sustainable development and climate change objectives’ is one of the
top risks for the Council. Without a plan in place and a financial plan to support it then
this risk will continue to be one of the Council's top risks. 
9. Integrated Impact Assessment and Consultation Requirements
9.1. This report does not introduce a new policy, function or strategy or recommend a
change to an existing policy; therefore, no impact assessment is required. The
Sustainable Development and Climate Change Strategy 2022-2027 has undergone
full Strategic Environmental Assessment and Equality Impact Assessments. 
9.2. Consultation has been undertaken with all relevant Council Resources in the
preparation of this report. 
David Booth
Executive Director 
27 November 2024 
Link(s) to Council Values/Priorities/Outcomes
Values
 Focused on people and their needs
 Fair, open and sustainable
Priorities
 We will work to put people first and reduce inequality
 We will work towards a sustainable future in sustainable places
 We will work to recover, progress and improve
Outcomes
 Good quality, suitable and sustainable places to live
 Thriving business, fair jobs and vibrant town centres
 Caring, connected, sustainable communities
 People live the healthiest lives possible 
Previous References
 Public Bodies Climate Change Duties annual report 2022-23, Climate Change and
Sustainability Committee on 29 November 2023 
List of Background Papers
 The Climate Change (Scotland) Act 2009
 Sustainable Development and Climate Change Strategy 2022-2027 
Contact for Further Information
If you would like to inspect the background papers or want further information, please
contact:-
Name: Kathryn McCafferty
Designation: Carbon Management Officer
E-mail: kathryn.mccafferty@southlanarkshire.gov.uk  
72

Page 73

Appendix 1 
Public Bodies Climate Change Duties Compliance Report 2023 - 24: South Lanarkshire Council 
If you need this information in another language or format, please contact us to discuss how we can
best meet your needs. 
Phone 0303 123 1015 
Email equalities@southlanarkshire.gov.uk 
73

Page 74

Part 1: Profile of reporting body 
1(a) Name of reporting body: South Lanarkshire Council 
1(b) Type of body: Local Government 
1(c) Highest number of full-time equivalent staff in the body during the report year: 12,299 
1(d) Metrics used by the body Specify the metrics that the body uses to assess its performance
in relation to climate change and sustainability: 
Metric Unit Value Comments
Population size served population 327,430 Figure taken from mid-year estimate 
1(e) Overall budget of the body   Specify approximate £/annum for the report year: 
£918,074,000 The budget represents the year end budget from our 2023-24 outturn report 
1(f) Report year: Financial (April 2023 to March 2024) 
1(g) Context Provide a summary of the body’s nature and functions that are relevant to
climate change reporting. 
South Lanarkshire is Scotland's fifth largest local authority in terms of population with 327,430 (2022
mid-year estimate) residents living within 154,355 households (National Records of Scotland 2023
household estimate figure). The Council covers 180,000 hectares of land stretching from almost the
centre of Glasgow to the Scottish Borders. The area has a mix of urban, rural, and former mining
environments - almost 80% is classed as agriculture but 70% of the population live in the major
settlements in the north.   
There are four towns in South Lanarkshire with a population of more than 20,000 (East Kilbride,
Hamilton, Rutherglen and Cambuslang) and a further 23 towns and settlements with a population of
over 1,000. 
South Lanarkshire is divided into 20 electoral wards which are represented by 64 Councillors who are
responsible for agreeing the Council's plans and policies and deciding how the Council's budget
should be spent. 
The Council provides services for everyone in this large and diverse geographical area from five
Resources: 
Community and Enterprise Resources comprises various services operating from a wide variety of
locations throughout South Lanarkshire.  The diverse range of services contributes significantly to the
quality of life experienced by both residents and visitors to South Lanarkshire.  Activities include:
maintaining the road and active travel networks; waste disposal and recycling services; street cleaning
and maintaining open spaces; promoting economic development; planning and building standards;
environmental health; trading standards; facilities services within schools and council offices;
bereavement services; fleet; and leading the development and promotion of sustainable development
and climate change action. 
Education Resources is South Lanarkshire Council’s biggest service. There are 54,085 young
people attending nursery, primary, secondary and additional support needs schools in South
Lanarkshire. Education is both a national and local priority. The service aims to raise achievement
and attainment and improve young people’s health and wellbeing. The main focus is on raising
standards, particularly in numeracy and literacy and in closing the gap between the most and least
disadvantaged children so that every child has the same opportunity to succeed. Also, to provide
young people with the necessary skills for life and work.
74

Page 75

Finance and Corporate Resources provides the framework of support which allows the Council to
deliver its wide range of services on behalf of local people.  Services throughout the Resource include:
overseeing the Council’s budget; revenue; Customer Services Centre; digital transformation; human
resources; registrars and licencing; audit; communications; and legal services. 
Housing and Technical Resources is the third largest social landlord in Scotland and delivers a
range of key housing management, homelessness, and property and repairs services. Activities
include: managing just over 25,000 homes for tenants; support to prevent and alleviate
homelessness; adapting homes for independent living; maintenance, repair and improvements to the
Council’s properties; and asset management. 
Social Work Resources supports social welfare and provide effective care and support to meet the
needs of vulnerable people in South Lanarkshire. Activities include: assessment and support; targeted
services for vulnerable children, young people and adults; providing care at home; community support
services; respite and residential services; and supporting carers. 
South Lanarkshire Leisure and Culture is a Scottish Charitable Incorporated Organisation
delivering services on behalf of South Lanarkshire Council including the operation, management and
development of indoor and outdoor sport and leisure facilities, community halls, arts venues, country
parks, libraries and museum services. 
The scope of South Lanarkshire Council's carbon footprint includes the energy used in our buildings,
household waste sent to landfill and for processing/recycling, the fuel used in our fleet of vehicles,
energy used for our street lighting and miles travelled as business travel. These are considered the
most appropriate sources to measure with robust data collected and converted into carbon using the
carbon conversion factors published each year by the Department for Energy Security and Net Zero.   
The data includes emissions reporting from South Lanarkshire Leisure and Culture SCIO.   
75

Page 76

Part 2: Governance, management and strategy 
2(a) How is climate change governed in the body? Provide a summary of the roles performed
by the body’s governance bodies and members in relation to climate change. If any of the
body’s activities in relation to climate change sit outside its own governance arrangements
(in relation to, for example, land use, adaptation, transport, business travel, waste, information
and communication technology, procurement or behaviour change), identify these activities
and the governance arrangements. 
Sustainable Development, including climate change duties compliance is a priority objective for the
Council. This is reflected in the Council Plan and the Council's Sustainable Development and Climate
Change Strategy (SDCCS).   
The climate change agenda is governed through the Council's Climate Change and Sustainability
Committee which has decision making powers to help to accelerate the pace and scale of action
needed in response to the climate emergency and meet challenging climate change national targets.  
The Committee is supported by the Climate Change and Sustainability Steering Group which is made
up of senior managers from all Council Resources and has responsibility for overseeing the
implementation of the SDCCS; compliance with the climate change duties; embedding sustainable
development within Council policy; and the scrutiny of performance monitoring reports.  Progress on
the Council's SDCCS and complying with our climate change duties are reported to the Climate
Change and Sustainability Committee biannually using IMPROVe (the Council's performance
management system). 
A Climate Change and Sustainable Development Officers Group has been established to support
strategic direction, oversight, and guidance on climate change mitigation, adaptation, and
sustainability initiatives within South Lanarkshire Council. The group will work to ensure that South
Lanarkshire Council aligns its operations, policies, and practices with sustainable and environmentally
responsible principles, aiming to mitigate climate change impacts and promote sustainability. 
The Strategic Environmental Assessment (SEA) Corporate Working Group is a cross-resource group
that works together to ensure that all plans, polices and strategies undergo the SEA process which
includes assessment of climatic factors. The SEA group feeds into the Steering Group and reports
progress of the Council’s SEA process to the Climate Change and Sustainability Committee. 
76

Page 77

The following diagram outlines governance, management and strategy for the Council: 
2(b) How is climate change action managed and embedded by the body? Provide a summary
of how decision-making in relation to climate change action by the body is managed and how
responsibility is allocated to the body’s senior staff, departmental heads etc. If any such
decision-making sits outside the body’s own governance arrangements (in relation to, for
example, land use, adaptation, transport, business travel, waste, information and
communication technology, procurement or behaviour change), identify how this is managed
and how responsibility is allocated outside the body 
Sustainable Development and Carbon Management sits within the Performance and Development
Team of Community and Enterprise Resources. The Performance and Development Team have a
strategic overview of the Council's progress to reduce carbon emissions, climate change adaptation
and environmental sustainability and work with all Council Resources to build capacity on climate
change awareness.   
The Performance and Development Team are responsible for developing the Sustainable
Development and Climate Change Strategy (SDCCS) and yearly action plan in conjunction with all
Resources. The SDCCS action plan is monitored and reported using the Council's IMPROVe system.
The SDCCS action plan is reported bi-annually to the Climate Change and Sustainability Committee
using the progress update in IMPROVe. Many of the SDCCS actions are embedded in Resource and
Service plans which results in many employees having climate change actions included in their key
work objectives as part of their annual performance development review.   
The Council also has a ‘Behaviours Framework’ which sets out 5 key principles of how employees
are expected to approach their work.  The first principle is ‘Efficient’ which includes taking action to
ensure sustainability and minimising environmental impact. Employees must evidence how they
contribute to this principle as part of their annual review.  The Behaviours Framework helps to embed
sustainability and climate change considerations in the culture of the Council.  
77

Page 78

The Council has corporate key performance measures that all Resources must comply with that
contribute to meeting the climate change duties. Each Resource reports progress on these measures,
on a quarterly basis using IMPROVe, to each Resource’s committee. 
The Council has taken steps to further embed climate change action across the organisation. Staff
engagement and awareness activities are ongoing including Keep Scotland Beautiful bespoke carbon
literacy training for elected members and officers, an e-learning module on climate change and
sustainability, climate change and sustainability sessions in the management development
programme and regular articles on the staff intranet.  The Council has a Sustainable Development
and Climate Change Communications Plan. The purpose of the Communications Plan is to identify
suitable communication methods and approaches for: 
• promoting and raising awareness of the vision, themes and priorities of the sustainable
development and climate change strategy.
• promoting the climate positive work which is already happening in our communities and
encourage others in the community to undertake climate positive action. 
• informing council employees about upcoming events or useful information.
• sharing information about funding opportunities. 
The SEA Corporate Working Group provides a mechanism to liaise with council services to ensure
that relevant plans, polices and strategies include the climate change duties considerations and any
actions accordingly. 
The Sustainable Development Adviser is also part of the Council's procurement network. The
Council’s sustainable procurement objectives, in accordance with the Sustainable Procurement Duty,
are set out in the Procurement Strategy.   
The following diagram outlines how climate change is managed and embedded in the Council: 
78

Page 79

2(c) Does the body have specific climate change mitigation and adaptation objectives in its
corporate plan or similar document?  Provide a brief summary of objectives if they exist. 
Objective Doc Name Doc Link
The Council Plan has 3 priorities – 
People, Progress and Planet. 
Planet – we need to work towards a
sustainable future in sustainable
places. 
We will act in ways that protect our
natural world for a healthier future.
We will work together to develop
local solutions to protect nature and
to take action on climate change and
support our young people to lead the
way.
The Council’s Corporate
Plan: Connect 2022–
2027-page 10
Plans and policies - South
Lanarkshire Council 
2(d) Does the body have a climate change plan or strategy?  If yes, provide the name of any
such document and details of where a copy of the document may be obtained or accessed. 
The Council's Sustainable Development and Climate Change Strategy (SDCCS) 2022-2027,
published on the Council website, has been prepared following extensive public consultation which
helped to shape the strategic vision and themes of the strategy. It outlines the changes in sustainable
development and climate change policy since the publication of the last strategy, and the Council's
strategic priorities for sustainable development and climate change over the five-year period.  This is
the Council's fourth strategy, the first was published in 2007, and covers the actions taken throughout
the reporting period FY 2023-24. 
The main principles of the SDCCS are: 
• Promote opportunities to support climate change mitigation and adaptation.
• Promote improvements in human health and wellbeing and reduce inequality across South
Lanarkshire.
• Promote the protection of a functioning environment.
• Promote sustainable economic growth and sustainable communities.
• Promote the benefits of greenspace and biodiversity across urban and rural areas of South
Lanarkshire.
• Promote the benefits of sustainable development and infrastructure and encourage sustainable
living. 
• Promote the importance of effective corporate and partnership working to achieve better
outcomes for South Lanarkshire. 
Carbon management and emissions reduction actions are incorporated into the Sustainable
Development and Climate Change Strategy 2022-2027. 
2(e) Does the body have any plans or strategies covering the following areas that include
climate change?  Provide the name of any such document and the timeframe covered.  
Topic Document Link Time period Comments
Adaptation Local
Development
Plan
Local
development
plan 
2020 - 2025 Climate adaptation is
embedded throughout
the plan – in particular
Policy 1: Spatial
79

Page 80

Topic Document Link Time period Comments
Planning, Policy 2:
Climate Change, Policy
13: Green Network and
Greenspace, and Policy
16: Water Environment
and Flooding.
Adaptation Biodiversity
Strategy
Biodiversity
Strategy 2024 -
2030 
2024 - 2030 Climate change
adaptation is
incorporated into
Chapter 3: Our eco-
systems and challenges.
Adaptation Local
Transport
Strategy
Local transport
strategy 
2013 – 2023
(A new
strategy that
cover the
period 2024 -
2034 is in
development)
LTS includes adaptation
through Flood Risk
Management. 
Adaptation Sustainable
Development
and Climate
Change
Strategy
Sustainable
Development
and Climate
Change
Strategy 
2022-2027 Climate adaptation is
embedded throughout
the strategy.
Adaptation Local Flood
Risk
Management
Plans
(LFRMP) - 
Clyde and
Loch Lomond,
and Tweed
Local flood risk
management
plan 
2022- 2028 The Flood Risk
Management team also
have 'Response to
Flooding' procedures.
Business travel Air quality
Action plan
Air quality
action plan 
2024 -2029 The air quality action
plan includes a number
of measures to
encourage a shift to
walking, cycling and
public transport instead
of the reliance of private
car.
Business travel Sustainable
Development
and Climate
Change
Strategy
Sustainable
Development
and Climate
Change
Strategy 
2022-2027 Priority 4: Improve
affordable, sustainable
and accessible transport
options. 
Energy efficiency Sustainable
Development
and Climate
Change
Strategy
Sustainable
Development
and Climate
Change
Strategy 
2022-2027 Priority 5: Progress a
transition to net-zero,
energy efficient and
climate resilience
homes, buildings and
infrastructure.
Energy efficiency Local Housing
Strategy 
Local Housing
Strategy 
2022-2027 Chapter 2: Housing
Quality, Energy
Efficiency and
Decarbonisation.
Fleet transport Air quality
Action plan
Air quality
action plan 
2024-2029 South Lanarkshire
provide fleet operators,
including the Council's
own fleet, free access to
80

Page 81

Topic Document Link Time period Comments
assessment and tailored
guidance to assist fleet
operators in becoming
more economic in terms
of fuel, emissions and
costs.
Fleet transport Sustainable
Development
and Climate
Change
Strategy
Sustainable
Development
and Climate
Change
Strategy 
2022-2027 Priority 4: Improve
affordable, sustainable
and accessible transport
options.
Land Use Core Paths
Plan 
Core paths
plan South
Lanarkshire
Council 
The CPP provides
easier access to the
outdoors and the
countryside and helps to
promote active travel.
Land Use Contaminated
Land Strategy
Contaminated
Land Strategy 
The CLS provides
opportunities for future
land use changes to
mitigate the effects of
climate change. 
Land Use Local
Development
Plan
Local
development
plan 
2020 - 2025 Land use is featured
throughout the LDP
however the most
relevant policies are
Policy 1: Spatial
Strategy, Policy 2:
Climate Change, Policy
13: Green network and
greenspace.
Land Use Sustainable
Development
and Climate
Change
Strategy
Sustainable
Development
and Climate
Change
Strategy 
2022-2027 Priority 9: Enhance,
protect, and respect the
outdoors and the natural
and historic
environment.
Renewable
energy
Local
Development
Plan
Local
development
plan 
2020 - 2025 Policy 1: Spatial
Planning, Policy 2:
Climate Change, and
Policy 18: Renewable
Energy.
Renewable
energy
Local Heat
and Energy
Efficiency
Strategy
Local Heat and
Energy
Efficiency
Strategy
(LHEES) 
2024 - 2028 Priority 2: Transition to
zero direct emissions
heating systems in
buildings across South
Lanarkshire to tackle
climate change.
Renewable
energy
Sustainable
Development
and Climate
Change
Strategy
Sustainable
Development
and Climate
Change
Strategy 
2022-2027 Priority 5: Progress a
transition to net-zero,
energy efficient and
climate resilience
homes, buildings and
infrastructure.
Staff Travel Employee
Travel Plan
Employee
travel plan 
The staff travel plan was
refreshed in March 2020
however was not
published due to impact
of Covid19 pandemic.
81

Page 82

Topic Document Link Time period Comments
Changes in working
arrangements for
employees will require
the employee travel plan
to be reviewed again.
Sustainable/
renewable heat
Local
Development
Plan
Local
development
plan 
2020 - 2025 Sustainable/renewable
heat is included in Policy
2: Climate Change.
Sustainable/
renewable heat
Local Housing
Strategy
Local Housing
Strategy 
2022-2027 Chapter 2: Housing
Quality, Energy
Efficiency and
Decarbonisation.
Sustainable/
renewable heat
Local Heat
and Energy
Efficiency
Strategy
Local Heat and
Energy
Efficiency
Strategy
(LHEES) 
2024 - 2028 Priority 2: Transition to
zero direct emissions
heating systems in
buildings across South
Lanarkshire to tackle
climate change.
Waste
management
Local
Development
Plan
Local
development
plan 
2020 - 2025 Policy 2: Climate
Change, and Policy: 18
Waste
Waste
management
Sustainable
Development
and Climate
Change
Strategy
Sustainable
Development
and Climate
Change
Strategy 
2022-2027 Priority 8: Take action to
allow South Lanarkshire
to become a zero-waste
society
Other (please
specify in
comments)
Air quality
Action plan
Air quality
action plan 
2024 - 2029 The air quality action
plan includes a measure
to incorporate green
infrastructure integration
to reduce emissions
within air quality
management areas
Other (please
specify in
comments)
Procurement
Strategy
Procurement
strategy 
2023 - 2028 Sustainable
Procurement - includes
contribution to
sustainable procurement
duty and the climate
emergency 
2(f) What are the body’s top 5 priorities for climate change governance, management and
strategy for the year ahead?  Provide a brief summary of the body’s areas and activities of
focus for the year ahead. 
1. Implement the 2024-25 action plan for the Sustainable Development and Climate Change
Strategy.
2. Further embed sustainable development and climate change into the Council’s decision-making
processes. Identify potential for development and piloting of an integrated sustainable
development decision making tool to be applied to projects and initiatives. 
3. Review current strategic net zero work being undertaken by the Council and consider the
development of a standalone carbon emission reduction plan. 
4. Development of a climate risk register upon which action planning, decision-making and
monitoring will be built upon with regards to climate change adaptation and resilience. 
5. Implement a robust communications plan for promoting and raising awareness of the
sustainability, climate change and adaptation agenda within the SLC, national and global context.
This sets out the Council’s overarching framework for engaging the people of South Lanarkshire
in relation to sustainable development and climate change. 
82

Page 83

2(g) Has the body used the Climate Change Assessment Tool (CCAT) (a) or equivalent tool to
self-assess its capability - performance?  If yes, please provide details of the key findings and
resultant action taken. 
A Climate Change Assessment Tool (CCAT) was last carried out in early 20024 as part of the
development of the 2024-25 action plan development. The Leadership Climate Emergency Checklist
was also used to review the Council’s compliance with reporting duties and to identify areas for
improvement. Workshops were held with the both the Climate Change and Sustainability Steering
Group and Officers Group to assess performance and identify the key priority areas and actions for
improvement. The key findings are as follows: 
83

Page 84

Leadership Checklist Workshop Outcomes
Theme SLC Current
Rating 
Improvement Actions Identified
Strategy Advanced  Climate Change, Sustainability and
Environmental Implications section in reports –
corporately encourage officers to embed
scrutiny into reports, key issues to be listed  at
this section. 
Targets Foundation  National targets are reported on, however, step
targets are now required
Tangible actions and projects required for each
service to ensure progress is being made. 
Governance Advanced  Influencing role needs to be expanded to move
to exemplary
Broaden our governance structure to include
partners (e.g. SPT, NHS, SPEN and other
energy providers). 
Delivery Foundation  Co-ordination with all Resources to ensure
targets are met
Increase reporting to Climate Change and
Sustainability Committee
Increase visibility of what is happening council
wide, share good practice. 
Finance Foundation Spend needs to be aligned with climate change
targets (Steps being taken to address this for
example Sustainable Impact assessments for
the capital budget process).
Performance Advanced  Share and review reporting with Stakeholders
Increase and encourage peer review (for
example the Public Sector Duties reporting)
Communicate more effectively externally 
Skills Foundation Review training requirements for all staff 
Make Climate Change LOL modules
mandatory
Encourage as part of the staff appraisal
process 
The outputs from these workshops and the identified improvement actions will inform the
development of a net zero route map. 
2(h) Supporting information and best practice. Provide any other relevant supporting
information and any examples of best practice by the body in relation to governance,
management, and strategy. 
84

Page 85

A Climate Change and Sustainability Committee was established in 2019.  This was in response to
both the UK and Scottish Governments declaring a climate emergency in May 2019 and new national
climate change targets introduced (net-zero greenhouse gas emissions by 2050 in UK and by 2045
in Scotland). To support the work of the Committee a cross-resource Steering Group was established
to provide senior level management and guidance on the actions required in the Council’s transition
to a net zero economy and society, help to build resilience to climate risks, and address the climate
emergency. A Climate Change and Sustainable Development Officers Group has also been
established to support the work of the Committee and Steering Group. 
South Lanarkshire Council also participate in the Sustainable Scotland Network Local Authority
Forum and have been an active member of the network with participation in both Finance and
Reporting Action Groups and presenting at member events.   
Part 3: Emissions, targets and projects 
3(a) Emissions from start of the year which the body uses as a baseline (for its carbon
footprint) to the end of the report year 
Reference
Year
Year Scope 1 Scope 2 Scope 3 Total
tCO2e
Comments
Baseline
carbon
footprint
2005-
06
42,014 50,836 63,115 155,965 Water is not included. Emission
factors were set at baseline year and
have not been updated for any
subsequent year. Scope 1= buildings
gas and oil and fleet; Scope 2=
buildings and street lighting electricity;
Scope 3=waste, staff travel.
Year 1  2006-
07
40,119 49,806 61,956 151,881 Comment as above
(in baseline year)
Year 2 2007-
08
39,655 52,085 59,597 151,337 Comment as above
(in baseline year)
Year 3  2008-
09
38,168 52,797 56,658 147,623 Comment as above
(in baseline year)
Year 4  2009-
10
41,637 50,846 52,349 144,832 Comment as above
(in baseline year)
Year 5  2010-
11
40,263 50,645 50,356 141,264 Comment as above
(in baseline year)
Year 6  2011-
12
36,510 51,081 47,665 135,256 Water is not included. Emission
factors were set at baseline year and
have not been updated for any
subsequent year. Scope 1= buildings
gas and oil and fleet; Scope 2=
buildings and street lighting electricity;
Scope 3=waste, staff travel and pool
cars.
Year 7  2012-
13
39,999 53,216 46,226 139,441 Comment as above
(in year 2011-12)
Year 8  2013-
14
37,119 51,383 47,513 136,015 Comment as above
(in year 2011-12)
Year 9  2014-
15
35,269 47,850 42,084 125,203 Comment as above
(in year 2011-12)
Year 10  2015-
16
35,498 45,071 39,707 120,276 Comment as above
(in year 2011-12)
85

Page 86

Reference
Year
Year Scope 1 Scope 2 Scope 3 Total
tCO2e
Comments
Year 11  2016-
17
34,017 38,950 37,927 110,894 Comment as above 
(in year 2011-12)
Year 12 2017-
18
34,599 36,860 42,656 114,115 Comment as above 
(in year 2011-12) 
Year 13 2018-
19
32,863 35,378 31,942 110,183 Comment as above 
(in year 2011-12)
Year 14 2019-
20
33,583 14,966 18,783 67,282 Water is not included. Emission
factors are updated annually. Scope
1= buildings gas and oil and fleet;
Scope 2= buildings and street lighting
electricity; Scope 3=waste, staff travel
and pool cars
Year 15 2020-
21
32,530 12,256 9,805 54,591 Comment as above 
(in year 2019-20)
Year 16 2021-
22
31,989 11,807 12,002 55,798 Comment as above 
(in year 2019-20)
Year 17 2022-
23
32,869 11,781 8,904 53,554 Water is not included. Emission
factors are updated annually. Scope
1= buildings gas and oil and fleet;
Scope 2= buildings and street lighting
electricity and EV pool cars; Scope
3=waste, staff travel (own cars).  
Year 18  2023-
24
30,281 11,982 6,223 48,486 Comment as above 
(in year 2022-23) 
3(b) Breakdown of emission sources 
Emission
source Scope
Consumption
data Units
Emissions
(tCO2e) Units Source
Biomass 1 2,953,456 kWh 31.72 kgCO2e/kWh Buildings
Gas Oil 1 3,744,192 kWh 960.37 kg CO2e/kWh Buildings
Natural Gas 1 122,197,176 kWh 22,353.4 kg CO2e/kWh Buildings
Diesel (average
biofuel blend) 1 2,651,353.57 litres 6,660.37 kg CO2e/litre Fleet
Gas Oil 1 51,045 litres 140.65 kg CO2e/litre Fleet
Petrol (average
biofuel blend) 1 79,257 litres 166.24 kg CO2e/litre Fleet
Grid Electricity
(generation) 2 49,387,797 kWh 10,226.94 kg CO2e/kWh Buildings
Average
business travel
car - Battery
Electric Vehicle 2 917,093 kWh 77.56 kg CO2e/mile
Electric
vehicles
(Fleet)
Grid Electricity
(generation) 2 8,063,979 kWh 1,669.84 kg CO2e/kWh
Street
Lighting
86

Page 87

Emission
source Scope
Consumption
data Units
Emissions
(tCO2e) Units Source
Average Car -
Unknown Fuel 3 1,185,436 miles 329 kg CO2e/mile
Staff travel
(own
vehicles)
Grid Electricity
(transmission
and distribution
losses) 3 49,387,797 kWh 884.79 kg CO2e/kWh Buildings 
Water supply 3 411,485
Cubic
metres 41.15
kgCO2e/cubic
metres Buildings
Grid Electricity
(transmission
and distribution
losses) 3 8,063,979 kWh 144.47 kg CO2e/kWh
Street
Lighting
Refuse Municipal
to combustion 3 79,133 tonnes 1,684
kg
CO2e/tonne Waste
Refuse Municipal
to composting 3 18,695 tonnes 166.62
kg
CO2e/tonne Waste
Refuse Municipal
to Landfill 3 6,259 tonnes 3,111
kg
CO2e/tonne Waste
Refuse Municipal
to mixed
recycling 3 46,238 tonnes 983.98
kg
CO2e/tonne Waste
Homeworking 3
15%
workforce kWh 804.61 
kg
CO2e/FTE/
annum
Estimated
figure using
PBDR
Guidance 
Total 50,436.71 (Home working, biomass emissions and grid electricity (transmission and distribution
losses) are included in 3b but not in 3a) 
3(c) Generation, consumption and export of renewable energy. Provide a summary of the
body's annual renewable generation (if any), and whether it is used or exported by the body. 
Renewable
Electricity
Renewable Heat 
Technology Consumed by
organisation (kWh)
Consumed by
organisation (kWh)
Comments
Solar PV 1,412,496  67 sites with PV systems 
Biomass  2,953,456 49 sites with Biomass heating 
All renewable electricity and heat generated is consumed by the organisation. 
3(d) Organisational Targets. List all of the body’s targets of relevance to its climate change
duties. 
87

Page 88

Name of
target
Target Scope of
target
Baseline
Year 
Baseline
figures
(tCO2e)
Target
completion
year
Progress
against
target 
(tCO2E)
(2023/24
figure)
Zero direct
emissions
Reduce to zero
emissions 
Energy use in
buildings
(gas and oil) 
2005 31,595  2038 23,314
Zero direct
emissions
• New cars and light
commercial vehicles -
zero emissions from
2025 
• All larger new
vehicles - zero
emissions by 2030 
• Petrol/diesel HGVs
phased out from 2030
Fleet  2005 10,417  2025 and
2030
6,967
Reducing
indirect
emissions
Reduce to as close to
zero as soon as
possible 
Energy use in
buildings
(electricity) 
2005 37,831 2045 10,227
Reducing
indirect
emissions
Reduce to as close to
zero as soon as
possible 
Waste
collected
from
households 
2005  61,320 2045 5,945
Reducing
indirect
emissions
Reduce emissions as
quickly as possible and
In line with relevant
transport policies.
Staff travel
(travel in
personal
vehicles) 
2005 1,795 2045 278
Reducing
indirect
emissions
Reduce to as close to
zero as soon as
possible 
Street lighting  2005  13,005 2045 1,681
Reduce
overall
carbon
footprint
Reduce to as close to
zero as soon as
possible
Council
carbon
footprint
2005 155,965 2045 48,486 
3(d)a How will the body align its spending plans and use of resources to contribute to reducing
emissions and delivering its emission reduction targets?     
All Council committee reports include a section on 'Climate Change, Sustainability and Environmental
Implications' to ensure that these implications are fully assessed and taken into consideration when
making decisions. The capital programme bid, and approval process includes an environmental
assessment which ensures all environmental impacts, both positive and negative are considered
when making decisions.  The Annual Revenue Budget process includes information on the
environmental impact of budget additions and the savings package, to ensure that the impact, positive
or negative, is considered when making decisions.                         
In September 2023, a Sustainability Impact Assessment process was introduced as part of the capital
and revenue budget which ensures that factors related to carbon reduction, climate change adaptation
and the wider principles of sustainable development are included in the decision-making process. As
part of the annual budget process, assessments of the impact of projects, and changes to the revenue
88

Page 89

budget, are prepared and shared with Members, prior to them making decisions around these
budgets. 
3(d)b How will the body publish, or otherwise make available, it's progress towards achieving
its emissions reduction targets?   
Performance on all actions relating to the Council's Sustainable Development and Climate Change
strategy are made available via the Council’s Climate Change and Sustainability Committee update
reports which are uploaded to the Council website. This includes reporting on progress towards
emissions reduction targets. The Public Bodies Climate Change Duties Report is also published on
the Council website.   
3(e) Estimated total annual carbon savings from all projects implemented by the body in the
report year 
Emissions Source Total estimated annual
carbon savings (tCO2e)
Comments
Electricity 35 LED lighting and PV installations projects 
3(f) Detail the top 10 carbon reduction projects to be carried out by the body in the report year
Provide details of the 10 projects which are estimated to achieve the highest carbon savings
during report year.   
Project  Funding
source
Capital cost
(£)
Project
lifetime
(years)
Fuel/
emission
source
saved
Estimated
carbon savings
per year (tCO2e/
annum)
PV Panels – Calderwood
Primary School
CEEF  75,000   25 Electricity  7
PV Panels – High
Blantyre Primary School
CEEF  75,000 25 Electricity  7
PV Panels – St Peters
Primary School
CEEF  60,000  25 Electricity  5.5
LED lighting* – 10 sites CEEF 150,000 10 Electricity  10
PV Panels – Deer Park
Sheltered Housing
Complex
Housing
Capital
Programme
75,000 25 Electricity 5.5
*LED projects reported as one project 
3(g) Estimated decrease or increase in the body's emissions attributed to factors (not reported
elsewhere in this form) in the report year.  If the emissions increased or decreased due to any
such factor in the report year, provide an estimate of the amount and direction. 
n/a 
3(h) Anticipated annual carbon savings from all projects implemented by the body in the year
ahead 
Source Total estimated annual
carbon savings (tCO2e)
Comments
89

Page 90

Electricity 40 4 PV projects 
Natural Gas 55 Our Lady of Lourdes Primary –
replacement of gas heating with air
source heat pump and other energy
efficiency measures. 
3(i) Estimated decrease or increase in the body's emissions attributed to factors (not reported
elsewhere in this form) in the year ahead  If the emissions are likely to increase or decrease
due to any such factor in the year ahead, provide an estimate of the amount and direction. 
Emissions Source Total estimated annual
emissions  savings (tCO2e) 
Comments
Estate changes 150 Removal of properties from Council
Estate via Community Asset Transfers
and other closures 
3(j) Total carbon reduction project savings since the start of the year which the body uses as
a baseline for its carbon footprint. If the body has data available, estimate the total emissions
savings made from projects since the start of that year ("the baseline year"). 
Unknown 
3(k) Supporting information and best practice. Provide any other relevant supporting
information and any examples of best practice by the body in relation to its emissions, targets
and projects. 
Carbon management actions, targets and projects are incorporated into the Sustainable Development
and Climate Change Strategy and Action Plan. Updates are reported on the Council website. Carbon
Management Reports outlining the yearly and mid-yearly carbon emissions reductions are presented
to the Climate Change and Sustainability Committee. This demonstrates our commitment to reducing
our carbon footprint and reporting in a transparent manner. 
Part 4: Adaptation  
4(a) Has the body assessed current and future climate-related risks?  If yes, provide a
reference or link to any such risk assessment(s). 
The Council’s Risk Management Team assists in the identification and evaluation of risks associated
with the delivery of the Council's objectives and provide support to help manage these risks. The risk
management team manage the Council's risk register and one of the top risks identified is ‘Failure to
meet sustainable development and climate change objectives’. The risk scorecard identifies the
business impacts of climate change now and in the future and contains control measures such as
ensuring that the climate change duties are embedded in policies, plans and strategies and working
with services to raise the awareness of the business risks of a changing climate.  
Severe weather is also one of the risks in the Council's risk register.  Across the Council the impacts
of severe weather on the functionality and responsiveness of individual services are recognised.
These council functions range from flood defence management to local planning. The Council’s
Corporate Contingency Plan sets out how it will work with partners to deal with emergencies, including
the impacts of severe weather events. The Council’s Emergency Management Team (EMT) leads on
responding to emergencies. The EMT is made up of senior managers from Services who may be
involved in dealing with emergencies and led by the Council's Resilience Adviser.   
90

Page 91

The South Lanarkshire area is covered by the West of Scotland Resilience Partnership which has
representatives from the emergency services, councils, NHS boards and utilities companies. The
West of Scotland Community Risk Register includes severe weather incidents, the possible
consequences and what the Regional Resilience Partnership are doing to mitigate the risks.
Assessing Future Climate Risks
The Council has a dedicated Flood Risk Management Team who manage flooding priorities and
deliver prioritised flood protection schemes. In accordance with the requirements of the Flood Risk
Management (Scotland) Act 2009, the Flood Risk Management Team has been involved in the
publication of the Clyde and Loch Lomond Local Plan District and the Tweed Local Plan District Flood
Risk Management Plans. The production of these plans has involved a national flood risk assessment
and identification of potentially vulnerable areas. Flood risk assessments and the implementation of
sustainable drainage systems are required as part of the planning process for any new builds
developments.  These future flood risks are also incorporated into the Local Development Plan 2.
The impacts from increased rainfall are the area’s biggest climate change risks, however the
challenges from rising temperatures and sea levels will also bring risks as well as opportunities for
the area.  To understand these risks further, and what action is required to mitigate them, the Council
is an active member of the Climate Ready Clyde partnership, a collaborative initiative that has
developed an Adaptation Strategy and Action Plan for the Glasgow City Region (which includes all of
South Lanarkshire, both rural and urban areas).     
4(b) What arrangements does the body have in place to manage climate-related risks?  
Provide details of any climate change adaptation strategies, action plans and risk management
procedures, and any climate change adaptation policies which apply across the body 
The Sustainable Development and Climate Change Strategy 2022-2027 includes the Council's
approach to managing climate change adaptation.  Within the ‘Sustainable Places’ theme the intention
is to work in partnership to ensure local infrastructure, buildings and communities are resilient to the
impacts of climate change. This theme builds on work already happening across South Lanarkshire
to improve communities and place, although it will do this through a sustainable development and
climate lens which will take the diversity of rural and urban South Lanarkshire into account. 
The Council’s Risk Management Strategy aims to provide a sensible and proportionate approach to
risk management that promotes awareness rather than avoidance. Resources are required to ensure
that risk management is embedded in service planning and delivery; in the way they make decisions;
in major projects; and in their dealings with partners and contractors. The Council also has a corporate
Business Continuity Plan which is managed by the Resilience Adviser. South Lanarkshire Council is
a category 1 responder and leads the Local Resilience Partnership on work required to meet the Civil
Contingencies Act 2004 and its associated Scottish Regulations and Guidance as part of Scotland
Regional Resilience Partnership. 
In addition, the Council has the following strategies and plans which include policies and actions to
address climate related risks: 
Local Development Plan 2 (2020-2025) 
A key theme running through the Local Development Plan 2 is the need to address the land use
issues arising from the impact of climate change.
• Policy 2: Climate Change – proposals for new development must, where possible, seek to
minimise and mitigate against the effects of climate change.
• Policy 13: Green network and Greenspace - Development proposals should safeguard the
green network, as identified on the proposals map, and identify opportunities for enhancement
and/or extension which can contribute towards mitigating greenhouse gases and adapting to
the impacts of climate change.
• Policy 16: Water environment and flooding - the avoidance principle of flood risk management
as set out in Scottish Planning Policy must be met. 
Managing Flood Risk 
91

Page 92

The Flood Risk Management team have procedures aimed at reducing flood risk and managing the
impacts of flood events, called the “Managing Flood Risk2 procedure, which is reviewed annually and
takes cognisance of the effects of climate change upon predicted flood risk. Flood risk assessments
and the implementation of sustainable drainage systems are required as part of the planning process
for any new builds or developments. 
Local Transport Strategy 2013-2023 
The Local Transport Strategy includes the following key objectives relating to climate change
adaptation: 
• Improve health and wellbeing by facilitating and encouraging active travel, through the
development of attractive, safe and convenient walking and cycling networks
• Mitigate, adapt and manage the effects of climate change, including flooding, on transport
infrastructure and communities. 
A new Local Transport Strategy is under development and due to be published later in 2024. 
Biodiversity Strategy 2024- 2030
Climate change is identified as a key cross-cutting theme in the Biodiversity Strategy 2024-2030 that
affects all ecosystems. Issues related to this are identified and addressed where possible. Peatland
management which benefits carbon sequestration remains a key theme. The Biodiversity Duty
Implementation Plan 2024-2026 (BDIP) encourages appropriate management of the council estate. 
The BDIP, through the planning function, encourages other landowners and developers to adopt the
principles of the Biodiversity Strategy in their land use. This is especially important in woodland cover
and peatland conservation for carbon management and intrinsic biodiversity. 
4(c) What action has the body taken to adapt to climate change?  Include details of work to
increase awareness of the need to adapt to climate change and build the capacity of staff and
stakeholders to assess risk and implement action.   
Delivering adaptation actions:
• The Flood Risk Management team continue to be consulted regularly during the Planning and
Development Management process to ensure all new developments are being designed in
accordance with the latest guidance on flood risk, climate change and the sustainable
management of surface water.
• The Council continues to encourage active travel by extending the network of walking and
cycle routes.
• A number of Active Travel Studies have been completed for all areas of South Lanarkshire
The priorities identified in these studies will be reviewed as part of the development of the new
Local Transport Strategy. 
• The Council has signed the Clyde Climate Forest Concordat committing to actively participate
in, and promote, the realisation of Clyde Climate Forest (CCF) targets; increase the average
tree canopy cover to 20%, increase the average broadleaf network by 20% and increase forest
and woodland cover in Glasgow city region to 20% by 2032 (totalling 18 million trees planted
across the region over the next decade as a response to the Climate and Ecological
Emergencies).
• A high-level study has been completed to identify opportunities for tree planting on all South
Lanarkshire Council’s owned or controlled land as part of the councils plans to achieve net
zero. A more detailed investigation and pipeline of tree planting and afforestation projects for
funding is being developed. 
• A Tree Canopy Cover Strategy is being developed to protect, enhance and manage a thriving
canopy cover that broadens community engagement in local urban forest planning and
improves community and canopy cover resilience to climate change, pests and storm events
through best management and maintenance practices.
• An Ash Dieback Disease Action and Recovery plan is being developed.
• A biosecurity statement is being developed to promote implementation and understanding of
good practices to help safeguard the future of our trees from the introduction and spread of
other harmful organisms. 
92

Page 93

• Continue to contribute to the flagship actions in Climate Ready Clyde’s climate adaptation
strategy and action plan.  
• Ongoing peatland conservation at Langlands Moss to help ensure the long-term viability of
the site as a peat bog that can contribute to biodiversity, flood management and carbon
storage. 
• The Making Space for Pollinators  report (2024) highlights the work and commitment we have
made in improving grasslands for pollinators and wildlife throughout South Lanarkshire.
Greater plant species-richness is a key driver to increased diversity, abundance and activity
of soil microbes, fungi and ecosystem engineers such as worms and ants, which facilitate
greater sequestration of soil organic carbon. Species rich grassland habitats also improve soil
structure and nutrient cycling; provide pollination services to nearby crops, wildflowers and
trees, purify water, mitigate against drought and flood events, increasing resilience to the
impact of climate change.   
Building adaptive capacity:
• As a member of Climate Ready Clyde, the Council has been involved in training on adaptation
skills and competencies, training on Climate justice and the new projections of future flood
disadvantage; and have access to an advisory board which is a virtual group of practitioners,
cities and adaptation experts to inform and challenge the City Region’s approach to
adaptation. 
• Flagship action 1 in the Climate Ready Clyde adaptation strategy is ‘Local authorities in the
region working together to build capabilities and deliver collaborative adaptation’. 
• The Council continues to raise awareness of Climate Ready Clyde’s Risk and Opportunity
Assessment and Climate Adaptation Strategy.
• The Council has started using Adaptation Scotland’s Benchmarking Tool.  The tool provides
a baseline assessment of current adaptation capabilities and how development progresses
over time.
• A PhD project is being jointly funded by the Council and Glasgow Caledonian University’s
Centre for Climate Justice. The study will focus on the climate vulnerability of South
Lanarkshire communities, capacity to transition to net-zero and building resilience in this area. 
4(d) Where applicable, what contribution has the body made to helping deliver the
Programme? 
Local Development Plan 
The Local Development Plan 2 contains policies on protecting and enhancing priority greenspace and
green networks and ensuring the effect of development proposals on the natural environment and
flood risk is considered during the application process. The plan also contains policy to ensure
development proposals mitigate and adapt against climate change. The Planning Service works
closely with colleagues in Greenspace and Countryside to ensure habitats are not adversely affected
by new development. Masterplanning of the Council’s Community Growth Areas has incorporated
measures to enhance existing habitats. 
Managing Flood Risk
Local flood risk management plans (LFRMPS) were published in December 2022. South Lanarkshire
Council (SLC) was involved in the production of the Clyde and Loch Lomond and Tweed LFRMPs.
Through the process of developing these plans, a National Flood Risk Assessment identified the
areas at risk of coastal, pluvial and fluvial flooding, and objectives and actions were included in the
Plans for Responsible Authorities to undertake to improve the current situation. 
The Council has been involved in the production and the ongoing updating of the Scottish Detailed
River Network (SDRN), and in complying with the duty under the Flood Risk Management (FRM) Act.
This dataset is used within the asset management database to assess and maintain waterbodies.
The Council also has access to the LiDAR (Light Detection and Ranging) dataset which is regularly
utilised during the catchment analysis stage in the production of Flood Studies. 
Local Transport Strategy
The Council continue to encourage active travel by extending the network of walking and cycle routes.
The next phase of the development of a segregated cycle network with enhanced pedestrian facilities
93

Page 94

in East Kilbride has commenced. Cycle Route designs are being taken forward in various locations
such as Carstairs, Hamilton, Uddingston and Bothwell. 
The Council work with SPT and public transport operators to encourage the use of public transport.
Lanark Park & Ride facility opened this year and Hairmyres Park and Ride Site is being progressed. 
Biodiversity
South Lanarkshire Council have designated 17 Local Nature Reserves (LNRs) with a broad spectrum
of habitats including ancient woodland, open water, wetlands, peatland and grassland.  The Council
continue to maintain and enhance the diversity of habitats creating wildflower meadows, planting
trees, enhancing existing wetlands and preserving our peatlands. Invasive non-native species (INNS)
including rhododendron, snowberry and Himalayan balsam continue to be removed from the LNR
areas. 
In partnership with Glasgow and Clyde Valley Green Network, the Council have been collating and
mapping data on priority species rich grasslands, wetlands and woodland in establishing our regional
Nature Networks, a key priority in the draft Scottish Biodiversity Strategy 2045: Tackling Nature
Emergency. As part of this over 100 Local Nature Conservation Sites (LNCS) have been identified for
the next Local Development Plan. 
The amount of intensively managed grassland throughout the area has been reduced with the aim to
improve habitats for pollinators. A pilot project in East Kilbride is underway in partnership with local
volunteers and Glasgow & Clyde Valley Green Network as part of their Clyde Grasslands  project. At
selected sites mowing and management regimes have been altered, and species composition is
monitored through survey work. 
The Council’s Biodiversity Officer works in partnership with the Peatland Officer at Glasgow and Clyde
Valley Green Network to determine the need for future management to restore and preserve local
peatland sites. 
In partnership with the Clyde Climate Forest, the Council have identified and continue to plant trees
in three ‘Target Neighbourhoods’ across the urban parts of South Lanarkshire which have low levels
of existing tree canopy cover and are particularly vulnerable to the impacts of climate change.
Approximately 23,700 trees have been planted in 2022-23 on council land, many with community
engagement. Working in partnership with the Clyde Climate Forest Community Volunteer
Coordinator, the Council is creating wider stakeholder groups for  tree and woodlands through
development of a Tree Warden scheme, promotion of the existing Young Tree Champions and Clyde
Climate Forest. 
Other Measures
Heat Energy Efficient Scotland: Area Based Scheme (HEES:ABS) programmes were developed to
install external wall insulation in privately owned and Council properties and are prioritised to target
fuel poor areas and households in most need of assistance. There are significant changes to the way
in which these programmes can now be delivered, with the introduction of PAS2035, market supply
of materials and the significant increase in costs. 
In the financial year 2023-24, 77 private properties, two private rented properties and 37 council
properties had external wall insulation applied. Eight private properties had new windows and doors
installed as a secondary measure, 37 council properties had new windows and doors installed. Four
amenity units at one of the Travelling Persons Sites had new PV’s and battery storage installed. This
information was reported to the Scottish Government as part of the HEES:ABS Returns. 
Measures Owner
Occupied
Private
rented
Social
Landlord Total
External Wall Insulation (solid wall) 77 2 37 116
Window Glazing 8 0 37 45
94

Page 95

High Performance External Doors with less
than or equal to 60% glazing area 8 0 37 45
Photovoltaics & Battery Storage 0 0 4 4
Total (ECO funded measures) 93 2 115 210 
The Council also facilitates the Local Authority Flexible Eligibility (LA Flex) Scheme. The Energy
Company Obligation (ECO) programme is funded from the large energy suppliers who provide funding
for the installation of energy efficiency measures to owner occupied homes across the UK in order to
reduce the country’s carbon emissions. Each local authority is required to complete and submit their
annual return to the Department for Business Energy & Industrial Strategy (BEIS). Last financial year,
under ECO 4, 163 homeowners have had 428 energy efficiency measures installed, including for the
first time, central heating, replacement of gas boilers and new heating controls, loft and cavity wall
insulation, underfloor insulation and internal wall insulation. 
Measures for ECO4 Flex period July 23 to 5 April 2024 Measures completed
Boiler - Upgrade to a non-renewable heating system  41
Boiler - Upgrade to a renewable heating system  89
Cavity wall insulation 22
ESH - Repair or replacement of a broken efficient ESH 1
ESH - Upgrade of an inefficient electric storage heater 11
External / Hybrid / Internal insulation of a solid wall 18
External / Hybrid / Internal wall insulation of a cavity wall 1
First time central heating  21
Flat roof insulation  4
Loft insulation where there is greater than 100mm pre-existing
insulation 2
Loft insulation where there is less than or equal to 100mm pre-existing
insulation 43
Pitched roof insulation 1
Programmer & room thermostat  32
Room-in-roof insulation insulated 6
Room-in-roof insulation uninsulated 3
Smart Thermostat 2
Solar PV  91
Time and temperature zone control 9
TRV's 20
Underfloor insulation  11
Total  428 
4(e) What arrangements does the body have in place to review current and future climate
risks? Provide details of arrangements to review current and future climate risks, for example,
what timescales are in place to review the climate change risk assessments referred to in
Question 4(a) and adaptation strategies, action plans, procedures and policies in Question
4(b). 
The Sustainable Development and Climate Change Strategy (SDCCS) 2022-2027 includes the
Council's approach to managing climate change adaptation. The strategy includes current and future
climate risks and a 5 year action plan has been developed.  The SDCCS annual action plan is reported
bi-annually to the Climate Change and Sustainability Committee. 
The Council's top risks, which include risks on both climate change and adverse weather, are
reviewed annually. 
95

Page 96

The Local Development Plan (LDP) was renewed in 2020.  Climate change mitigation and adaptation
are key themes throughout the LDP2. 
The Biodiversity Strategy 2024-2030 and Biodiversity Duty Implementation Plan (BDIP) were
launched in 2024. The Biodiversity Partnership group meet annually to monitor the progress of the
Biodiversity Strategy. The Biodiversity Duty Report 2024-2026 is requested by Scottish Government
every three years, this summarises the work achieved by the Council on biodiversity. The BDIP is
reviewed every three years. Action planning takes places on a rolling programme and kept under
continuous review.   
The Strategic Environmental Assessment (SEA) process is well embedded within the Council and
provides an opportunity to assess the risks and opportunities of climate change in new or revised
plans, policies and strategies. A full SEA was carried out alongside preparation of the Sustainable
Development and Climate Change Strategy. This has ensured a consistency in approach to
addressing the climate crisis alongside the ecological emergency. It ensures that the importance of
sustainable development is mainstreamed across the Council and promoted to communities and
partners. The climate adaptation strategy for the city region is also undergoing a full SEA. 
Local Flood Risk Management Plans (LFRMP) continue to be delivered. The monitoring of weather
patterns, including rainfall statistics, continues to be carried out to help inform how the Council
allocates resources and tracks the observed effects of climate change. Actions for the Council in the
LFRMPs include the production of four Flood Protection Studies and five Surface Water Management
Plans. The Council are currently working through a programme of delivering these projects, and the
effects of climate change upon future flood level, and the resultant impacts upon building and
infrastructure networks, will be considered in each of these projects. 
Climate Ready Clyde launched the first comprehensive risk and opportunity assessment for the
Glasgow City Region in October 2018. The findings and recommendations in the assessment
were used in the development of the first Adaptation Strategy and Action Plan for the Glasgow
City Region. The risk and opportunity assessment provides context for the Council’s risk
management approaches to climate change adaptation. 
4(f) What arrangements does the body have in place to monitor and evaluate the impact of the
adaptation actions?  Please provide details of monitoring and evaluation criteria and
adaptation indicators used to assess the effectiveness of actions detailed under Question 4c
and Question 4d. 
South Lanarkshire's State of the Environment Report provides data that facilitates the monitoring and
evaluation of a range of environmental issues - such as Biodiversity, Soil, and Water - where climate
change adaptation action has been undertaken. This also includes a specific chapter related to
climate change. 
The Council's performance management system IMPROVe is used to monitor and report actions and
measures within Resource Plans and the Sustainable Development and Climate Change Strategy
(SDCCS). The SDCCS includes adaptation actions such as biodiversity, greenspace and flood risk
management which are monitored and evaluated through IMPROVe and reported to the Climate
Change and Sustainability Committee biannually. 
SEPA prepared indicators that have been used in the first cycle of the LFRMPs, however these will
be reviewed and adapted to ensure they are reflective of the on-going changes within the cycles and
as our understanding improves through the process. Several Surface Water Management Plans
(SWMP) and Flood Studies have been developed for the locations assessed with the highest Annual
Average Damages from surface water and river flooding. Any actions or recommendations identified
within the plans and studies will be evaluated regarding the reduction or mitigation of damages due
to flooding within these areas. 
The regional adaptation strategy and action plan, through Climate Ready Clyde, will be monitored
and evaluated. 
96

Page 97

4(g) What are the body’s top 5 priorities for the year ahead in relation to climate change
adaptation?  Provide a summary of the areas and activities of focus for the year ahead. 
1. Develop a climate risk register upon which action planning, decision-making and monitoring
with regards to climate change adaptation and resilience will be built.
2. Continue as an active member of the Climate Ready Clyde Local Authority Forum participating
in city-region wide workshops and events, creating connections and opportunities for
development/co-sharing of knowledge and training by 2025.
3. Contribute to the development and implementation of local actions that contribute to the wider
Glasgow City Region's (GCR) Adaptation Strategy, where appropriate, working across Council
Resources.
4. Benchmark the Council against Adaptation Scotland’s Adaptation Capability Framework to
identify current position and areas for improvement.
5. Mainstream adaptation into governance practices and other key council plans and strategies. 
4(h) Supporting information and best practice, Provide any other relevant supporting
information and any examples of best practice by the body in relation to adaptation. 
South Lanarkshire Council is  a partner in Climate Ready Clyde which is a cross sector initiative
bringing partners together to work strategically to minimise risks and seize opportunities climate
change presents for the economy, society and environment across the Glasgow City Region. Its aims
are: 
• People and communities benefit from actions to adapt to climate change.
• Climate adaptation helps to secure existing investment and generates new opportunities.
• To protect the area’s natural environment and uses it to help adapt to climate change. 
Climate Ready Clyde has developed Glasgow City Region’s first Adaptation Strategy and Action Plan.
The Strategy aims to ensure Glasgow City Region’s economy, society and environment is not only
prepared for but continues to flourish in the face of current and future climate impacts. The  Council
develops and implements local actions that contribute to the wider Adaptation Strategy and Action
Plan. 
Part 5: Procurement 
5(a) How have procurement policies contributed to compliance with climate change duties?  
Provide information relating to how the procurement policies of the body have contributed to
its compliance with climate changes duties. 
The Council continues to consider environmental and social issues when purchasing goods and
services. The Council adheres to the Sustainable Procurement Duty to ensure that regulated
procurements: 
• Improve the economic, social and environmental wellbeing of the authority area, with a
particular focus on reducing inequality.
• Facilitate the involvement of small and medium enterprises, third sector bodies and supported
businesses.
• Promote innovation. 
The Council also use the Scottish Government’s Sustainable Procurement Toolkit and performance
against the Flexible Framework is published in the Annual Procurement Report 2023-2024. Where
appropriate, tenders include full sustainability tests to ensure sustainable outcomes have been
embedded in the Invitation to Tender. A new sustainability process has been in place since
2022/2023, which mandates a new scoring approach in the technical envelope, with 30% of the total
technical score allocated to sustainability, including Fair Work First, Community Benefits and, for the
first time, a specific score for climate considerations. 
The Council has approved a new a five-year Procurement Strategy for 2023-2028 and one of the
seven key objectives is sustainable procurement, incorporating the climate change duties. 
97

Page 98

In 2023/2024, the Council’s spend with local enterprises increased from 18% to 19.5%, representing
£67m spent in the South Lanarkshire area, with a further £41m spent with North Lanarkshire
enterprises. 
5(b) How has procurement activity contributed to compliance with climate change duties?  
Provide information relating to how procurement activity by the body has contributed to its
compliance with climate changes duties. 
The Council has confirmed it will contribute to the Scottish Government led research on driving
emission reduction through the public supply chain and will consider any new recommendations from
this research.   
In respect of procurement activity which has contributed to compliance with climate change duties,
the procurement team has supported the Council approaches to: 
• Expanding the use of electric fleet and the EV charging infrastructure
• Upgrade projects for social housing to achieve Energy Efficiency standards (EESSH)
• New construction arrangements for construction projects, including Larkhall Leisure Centre,
with embedded sustainability standards. 
5(c) Supporting information and best practice 
The output from the Sustainable Procurement tools can be accessed through the Council’s Annual
Procurement Report 2023-2024 
Part 6: Validation and declaration
6(a) Internal validation process   Briefly describe the body’s internal validation process, if any,
of the data or information contained within this report. 
The report was prepared by the Performance and Development Team with relevant Council
Resources. It has been reviewed by the Performance and Policy Development Manager, the Head of
Enterprise and Sustainability Development and approved by the Executive Director of Community
and Enterprise Resources. It has also been reviewed by the Executive Committee prior to submission.   
Finance and Corporate Resources have previously carried out an internal audit of the climate change
duties report. The audit interrogated the data compilation and evidence pack and reported that the
methodologies and processes were robust and sound. The 2023-24 report has not been audited;
however, the same methodologies and processes have been applied as in previous years. 
6(b) Peer validation process. Briefly describe the body’s peer validation process, if any, of the
data or information contained within this report. 
When the internal audit was carried out, a benchmarking exercise took place comparing the level of
reporting detail within the South Lanarkshire report against six other local authorities in the Local
Government Benchmarking Framework ‘family group’. Overall South Lanarkshire’s report compared
favourably with the other councils reviewed. 
6(c) External validation process. Briefly describe the body’s external validation process, if any,
of the data or information contained within this report. 
No external validation carried out at this time. 
6(d) No Validation process. If any information provided in the report has not been validated,
identify the information in question and explain why it has not been validated. 
Internal validation process as outlined in 6a. 
98

Page 99

6 (e) - Declaration
I confirm that the information in this report is accurate and provides a fair representation of the body’s
performance in relation to climate change. 
Name Role in the body Date
David Booth Executive Director of Community
and Enterprise Resources 
04/10/2024 
99

Page 100

100

Page 101

Report
Agenda Item 
Report to: Climate Change and Sustainability Committee 
Date of Meeting: 18 December 2024
Report by: Executive Director (Community and Enterprise
Resources)  
Subject: Litter Strategy - Update 
1. Purpose of Report
1.1. The purpose of the report is to:
[purpose]
 provide an update on the work undertaken to date on the Litter Strategy 2022 to
2027 and the associated action plan
[1purpose]
2. Recommendation
2.1. The Committee is asked to approve the following recommendations:
[
(1) that the progress and updates on the Litter Strategy Action Plan be noted.
(2) the pilot project updates be noted.
(3) that the update on the review of fly tipping reporting process be noted. 
3. Background
3.1.  The Litter Strategy covers the period 2022 – 2027 and was approved by the Climate
Change and Sustainability Committee on 31 August 2022. The strategy outlines a
clear vision for how the Council will develop various plans and initiatives to prevent
and address litter, dog fouling, and fly tipping. It builds on existing initiatives and
complements national campaigns promoted by organisations like Keep Scotland
Beautiful and Zero Waste Scotland. 
3.2. Over the past year, there has been positive engagement with diverse community
groups and individuals. Through the Community Clean Up webform, groups and
residents have been supported in conducting litter picks and cleanups. Ground
Services have also actively engaged with the Climate Change and Sustainability Youth
Forum by attending meetings, providing information, and assisting with initiatives run
in schools. This is an encouraging start for collaborating with Education and individual
schools. 
3.3. The litter bin mapping and inventory undertaken for the Litter Strategy have been
invaluable for understanding the current locations and capacities of infrastructure. This
has informed decisions about new bin requests. The Litter Bin Map is now publicly
available for residents and community members to access. Our Litter Bin Replacement
Programme is continuing to ensure locations and capacities suit the area's needs.
Going forward, litter bins with hoods are being prioritized to prevent litter escape from
animals and wind. 
3.4. The Council has successfully obtained Chewing Gum Task Force grant funding for the
last 3 years. This has allowed effective cleaning of gum staining in town centres across
5
101

Page 102

all localities. This year for Year 3 of the grant funding £27,045.40 was received which
has enabled us to continue tackling gum issues in other communities. 
Circular Economy Bill
3.5. The Scottish Government passed the Circular Economy Bill on 26 June 2024. The Bill
establishes the legislative framework to support Scotland’s transition to a zero waste
and circular economy, significantly increase reuse and recycling rates, and modernise
and improve waste and recycling services. 
3.6. The Bill includes specific provisions regarding litter and fly tipping. It establishes a new
penalty system for littering from vehicles, powers to seize vehicles involved in specified
waste crimes, and strengthened household duty of care responsibilities around
household waste to help prevent fly tipping. 
The National Litter and Fly Tipping Strategy
3.7. The Scottish Government published the National Litter and Fly Tipping Strategy on 28
June 2023. It outlines a refreshed approach to tackling litter and fly tipping to protect
and enhance Scotland's environment, ensure safer and cleaner communities, and
contribute to a thriving circular economy. 
3.8. The Strategy sets out how national and local governments, businesses, third sector,
communities and individuals can collaborate to support behaviour change, improve
infrastructure, and strengthen enforcement. This aims to protect the environment,
better value societal resources, and prevent materials escaping the economy. 
3.9. Scottish Government and the delivery partners have been working on the Year 1 action
plan before launching Year 2. This has included several data and research projects,
the launch of The Community Litter Hub as well as the reopening of the Private
Landowners Grant Fund. 
4. Litter Strategy Steering Group
4.1.  The purpose of the Litter Strategy Steering Group is to provide leadership, governance
and oversight that will drive collaborative action across the Council to achieve the
vision and objectives outlined in the Litter Strategy. 
4.2. The Steering Group is made up of colleagues from Grounds Services, Waste Services,
Roads and Transportation Services, Housing and Technical, Environmental Services,
Education, Economic Development, Estates, Sustainable Development and Comms.
The meetings take place every two months and cover topics within the action plan,
updates on the pilot projects and presentations on related topics. 
4.3.  The group has been invaluable for discussing current practices and encouraging
innovative corporate collaboration across all Council resources. It has highlighted
areas for future development, progressed with pilot projects, and fed into the Litter
Strategy Action Plan. 
Litter Strategy Action Plan
4.4.  The Action Plan was approved by the Steering Group early 2023 and covers the main
themes of Education, Engagement and Enforcement with 19 actions - 6 for Education,
8 for Engagement and 5 for Enforcement. Actions are assigned to Resources to
progress over the period of the strategy with a copy of the updated Litter Strategy
Action Plan included in Appendix 1 with updates against each action.  
102

Page 103

4.5. Some highlights over the year so far include: 
 Ongoing recycling pilots have been taking place in two secondary schools to
educate pupils and staff to reduce general waste and increase recycling. Larkhall
Academy and Trinity High School have trialled different recycling infrastructure,
designed posters and provided information and education to the schools.
Recycling levels and contamination are being monitored for continuous data and
as evidence for a Zero Waste Scotland Recycling Improvement Fund (RIF)
application, which has just been submitted
 It's Your Place campaign was launched in December 2023 and the branding used
for a number of different campaigns throughout the year
 Litter survey utilising AI technology was undertaken to map litter around Hamilton
town centre, including 3 secondary schools. The report provided interesting and
beneficial results, and an action plan developed
 Upgrade and improvements currently being progressed for fly tipping reporting. 
 Three pilot initiatives took place focussing on Town Centres; Housing; Industrial
Estates 
5. Data
5.1. To support delivery of the Strategy and help measure success, the Steering Group
has previously set out a suite of baseline data that will be updated and monitored over
the life of the strategy. This is presented in Appendix 2, with indicators listed below. 
 Local Environmental Audit and Management System (LEAMS)
 Fixed Penalty Notices (FPNs)
 Procurator Fiscal (PF) Reports
 Fly tipping
 Housing (waste in the wrong place) Requests
 Community Groups
 Community Clean Up – bag uplifts
 Community Clean Up – support  
5.2. The LEAMS data shows annual figures from 2015/16 for the Council, the national
average, and Benchmarking Club 3. Until 2023/24, the Council's performance has
been better than both comparators and has followed a similar trend over the period.
The 2023/24 figures for South Lanarkshire and Benchmarking Club 3 have decreased
slightly, with the national average increasing and overtaking them marginally.   
5.3. The Fixed Penalty Notice (FPN) data that has been provided by Environmental Health
shows a decline in FPNs issued in the last 4 years. Covid-19 restrictions resulted in a
reduction in enforcement activity over the first part of that period. 
5.4.  The number of cases/reports passed to the Procurator Fiscal (PF) peaked at 21 in
2019/20. Due to COVID-19 restrictions they dropped to 1 per year but have since
increased back up to 8 in 2022/23 and 2023/24. 
5.5. From 2013-2019, reported fly tipping instances were around 2,500 annually. Although
high, it was believed that additional unreported cases existed. In early 2020, a new
process was implemented to ensure all instances were recorded onto Confirm to track
numbers and hotspot locations.  
5.6. This was implemented during the Covid-19 pandemic and whilst expecting an increase
in reporting due to the new process, the data suggests there may also have been an
actual increase of fly tipping during this time. Since peaking in 2020, this has been
103

Page 104

decreasing over recent years with around 2,800 instances over 2023 which is
encouraging. 
5.7.  The baseline dataset that the Steering Group is working with also includes Housing
requests for abandoned waste and 'waste in the wrong place' within housing areas.
During 2023/2024, there were 4,814 requests for the removal of waste, which is a 15%
increase from 2022/2023. 
5.8. The Community Clean Up webform has been an invaluable resource for both South
Lanarkshire Council and local community groups. The form was launched in May 2021
as services started to open up after lockdown and saw an initial peak of 105 enquiries
for support. Since then, main peaks have been around February, March and April each
year when the Spring Clean takes places. The other option on the webform is to inform
South Lanarkshire Council of bags for uplift which allows the Council to uplift bags
promptly after a litter pick. These requests also peak during the Spring Clean period
and this year there was the highest level of bags recorded in a month. April 2024 saw
582 bags uplifted by community groups and volunteers and recorded through the
webform.   
6. Pilot initiatives        
6.1. As part of the implementation of the Strategy, the Steering Group established three
pilot initiatives that would require collaborative working to target areas of concern. The
pilots are Town Centres (Cambuslang); Housing; Industrial Estates. The Industrial
Estates pilot project was concluded after approximately 6 months as there were
improvements and no ongoing issues.     
Town Centres – Cambuslang
6.2. The Council is working in partnership with Cambuslang Community Council to address
some of the issues on the Main Street caused by commercial and household waste
and bin infrastructure. The majority of the continued issues are with commercial bins
and waste, which the Council unfortunately are unable to change or enforce. The
Council is looking at ways to engage with the business community on this subject. 
6.3. While the predominantly wide pavements mean bins do not block access, they create
street clutter and are unsightly. Bins are often abandoned or not returned to more
appropriate locations against buildings or barriers. Overflowing or unsecured bins and
side waste are common nearing collection day. Continued communication with
Cambuslang Community Council, the local businesses and Economic Development is
ongoing and aims to encouraging collaborative working. 
6.4. The Council is in the process of purchasing communal bin enclosures for domestic
bins that will allow the removal of numerous individual household bins at appropriate
locations and reducing street clutter on collection days. This will improve the aesthetics
of the area, and it is hoped will encourage the local business community to consider
their waste management arrangements. 
Housing
6.5. Housing Services are working in partnership with Grounds Services, Environmental
Services and Waste Services to address fly tipping and improper waste disposal
around housing properties. 
6.6. Letters are still being issued to households in problem areas, reminding them of their
responsibilities, what to do with their waste and how to report occurrences. Housing,
Waste Education, and Environmental Health have also been active, talking to
104

Page 105

residents and distributing leaflets. Housing's "Common Sense" Campaign highlights
waste in closes, fire risks, and proper wheelie bin return after collection. 
6.7. Housing Services are investigating all deposits of waste or waste in the wrong place
within Housing land. Working cooperatively with other Resources is allowing the
occurrences to be checked if it has been booked as a bulk uplift by the resident before
proceeding with action.       
6.8. Housing Services are also working with Grounds Services to focus on a number of ‘hot
spot’ areas that require improvements and investment. This includes clearing and
physical preventative measures to fly tipping hotspots, removing historic shrubbery
that is not maintained and general improvement to areas. Waste and recycling
solutions for flats or areas with inadequate accessibility are also being explored.
Communal bins and custom communal bin enclosures are also being considered for
different areas. 
Industrial Estates 
6.9. Allanshaw Industrial Estate in Hamilton was highlighted by Hamilton and Blantyre Litter
Pickers through their local MP due to concerns about dumped litter and waste around
the estate and unsecured business bins. Grounds Services and Estates team have
engaged with the local community including issuing a letter to estate tenants reminding
them of their responsibilities around waste and litter and potential enforcement activity.
Litter and fly tipping has improved subsequently, and the pilot project concluded. The
Industrial Estate is being monitored to determine if further intervention is required.   
7. Litter AI Survey - Hamilton
7.1.  One of the priorities of the strategy was to ‘Explore technology opportunities to map
littering’ and it was decided to engage in discussions with two organisations that
undertake litter AI surveys. Hamilton town centre was selected as a good location with
a varied make up of commercial areas, residential areas, parks, industrial zones and
schools.   
7.2.  Ellipsis Earth was the successful bidder, and a survey of Hamilton undertaken. Images
were collected by smartphones and vehicle cameras. The images were then detected,
labelled and mapped by Ellipsis AI software. Representative data was captured across
all seven days of the week at various times of the day with a total of 166,980 sqm
surveyed. 
7.3. The surveys also incorporated 157 existing bins and 207 potential litter sources such
as cafes, transport stops and shops, for performance evaluation. A total of 113,655
items of litter were detected across a typical week, with an average of 17 items a
minute: or an item being littered across the city every 3.5 seconds and every 1.48
metres. 
7.4.  The analysis of the data of the most commonly littered items shows a proportional
breakdown of littering that is very heavily dominated by small items and fragments.
These account for 51% of the 84% identified in the top 10 (plastic fragment, cigarette
butt, foreign object, bottle cap/lid, sachet packet). This data shows the majority of the
litter recorded is not in general a highly visible issue since the littered items can be
very small in size and fragmented. The data allows examination of cleansing
schedules, and techniques and allows investigation into the reasons for this litter being
present in Hamilton when it is not normally typical to town centres. 
105

Page 106

7.5. Since receiving the Ellipsis Earth report, an action plan has been developed to focus
on changes and initiatives that can be made going forward. A more detailed report
on the work undertaken forms another item on this agenda. 
8. Fly tipping reporting
8.1 A sub group of the Litter Strategy Steering Group has recently been established to
review and improve the way that fly tipping is reported by the public and the way that
this is managed internally across the different services involved in the process. So far,
a new streamline reporting process for customer enquiries has been mapped that
allows access to the right information at the right time and reducing hand offs. The aim
is to have a fully interactive online form linking to GIS mapping to encourage channel
shift. 
8.2 New simple forms are also being developed for internal use that will help reduce
timescales in processing requests and ultimately lead to quicker response times in
dealing with fly tipping. The councils bulk uplift arrangements are also being
considered as part of the review process as uplift request can often be mistaken for
fly tipping. It is hoped to conclude work by early 2025 and new processes launched
quickly thereafter. 
8.3 Over 2024, Environmental Health has reviewed the approach to investigating fly
tipping incidents with the aim of obtaining more information which would enable
enforcement action to be taken. Reporting arrangements with other council services
have been redesigned as outlined in section 8.1, which has resulted in an increase in
notifications from services who have obtained evidence (usually CCTV footage) of fly
tipping incidents. During the summer period the out of hours noise team undertook site
visits to known hot spot areas in an attempt to catch people fly tipping and also to act
as a deterrent. 
8.4 Recording arrangements at the call centre for fly tipping have been clarified and
updated which will enable the reports to be directed to the appropriate service quickly
and obtain the best information from members of the public reporting incidents. During
2024 Environmental Services also liaised with the Procurator Fiscal (PF) on the
evidence required to enable cases to be taken by the PF. This will allow officers to
gather the specific evidence the PF requires ensuring cases are more likely to be
pursued by the Fiscal. 
9. Communications Plan        
9.1. Effective communications are an important part of the Litter Strategy, to encourage
public understanding and support and to bring key messages to specific audiences.
Overarching and long-term branding was the key component for this campaign to
encourage buy in and engagement. It's Your Place campaign was launched in
December 2023 and the branding has been used for a number of different campaigns
within Community and Enterprise Resources. 
9.2.  Communications and Strategy are working with Community and Enterprise Resources
to promote all significant developments and actions currently being undertaken as part
of the Strategy. 
10. Employee Implications
10.1. Implementing the Strategy has been a key task for the Policy Officer. All Resources
contribute to the actions within the Strategy to ensure a coordinated, comprehensive
and collaborative approach. Resource and service implications will vary based on the
relevance of their activities to litter and the action plan. 
106

Page 107

10.2.  Beyond implementing the Strategy, the Policy Officer will champion and report on
broader litter, dog fouling, and fly tipping prevention issues. 
11. Financial Implications
11.1. The cost of the Ellipsis Earth AI Litter Survey was £17,500, which was met within
existing Grounds Services revenue budget. 
12. Climate Change, Sustainability, and Environmental Implications
12.1. Littering and fly tipping detrimentally impact health, wellbeing, the economy, and the
natural environment. Litter and waste can lead to soil, water, and air pollution. It's
estimated 80% of marine litter originates on land. Ecosystem services and biodiversity
are also harmed. Preventing litter and fly tipping plays a key role in sustainable
development and the circular economy. The Litter Strategy will support the Council's
Sustainable Development and Climate Change Strategy outcomes. 
12.2. Proper disposal preventing littering and fly tipping will also positively impact the
Council's recycling figures. Currently, litter and fly tipped materials are not separated
before disposal, mainly being incinerated. 
13. Other Implications
13.1. There are no other risks or implications associated with this report. 
14. Equality Impact Assessment and Consultation Arrangements
14.1. This report does not introduce a new policy, function or strategy nor recommend a
change to an existing policy, function or strategy and therefore, no impact assessment
is required. 
14.2. There was no consultation arrangements required in relation to this report. 
David Booth
Executive Director (Community and Enterprise Resources) 
27 November 2024 
Link(s) to Council Values/Priorities/Outcomes
Values
 Focused on people and their needs.
 Working with and respecting others
 Ambitious, self-aware and improving
 Fair, open and sustainable
Priorities
 We will work towards a sustainable future in sustainable places.
 We will work to recover, progress and improve.
Outcomes
 Good quality, suitable and sustainable places to live.
 Thriving business, fair jobs and vibrant town centres
 Caring, connected, sustainable communities. 
Previous References
 Community and Enterprise Resources Committee report on Code of Practice on Litter
and Refuse (Scotland) 2018 on 24 August 2017
 Community and Enterprise Resources Committee report on Litter Development Policy
Officer on 26 March 2018
107

Page 108

 Climate Change and Sustainability Committee – 10 February 2021
 Climate Change and Sustainability Committee report on Litter Strategy on 31 August
2022 
List of Background Papers
 None 
Contact for Further Information
If you would like to inspect the background papers or want further information, please
contact: - 
Emma Berry (Environmental Initiatives Officer)
Ext: 7775 (Tel: 07385032023)
E-mail: emma.berry@southlanarkshire.gov.uk 
108

Page 109

Appendix 1  Litter Strategy Action Plan 
Litter Strategy Steering Group 
Action Plan 
THEME ACTION RESPONSIBILITY STATUS TIMESCALE UPDATE 
Education
Establish a baseline for
tracking performance
against the strategy.
Grounds Services
(Emma Berry)  Complete  First quarter of 2023
Baseline data has been discussed and
provided. Will be updated
quarterly/annually as appropriate. 
Education
Update annual data
for tracking
performance against
the strategy. 
Grounds Services
(Emma Berry)  In Progress  Ongoing  Data for 23/24 has been updated. 
Education 
Develop a series of
short and long term
projects for schools. 
Education (David
Hinshelwood)
Grounds Services
(Emma Berry)
Waste Services (Kirsty
McGuire/Tom
McGowan)
Facilities ? 
In Progress  Ongoing
Trinity High School and Larkhall Academy -
recycling pilot in street area and
classrooms. Currently trialling different
recycling bins and Education has applied
for the ZWS Recycling Improvement Fund
to roll improved recycling out across all
High Schools. 
Multiple Primary and Secondary schools
are taking part in litter picks and
community clean ups. The Youth Forum
have also highlighted this as an area they
want to get involved in supporting. 
Education
Review the Scottish
Secure Tenancy
Agreement to ensure
tenants’ responsibilities
in relation to disposal
of waste and use of
common parts is
clearly detailed. 
Housing (Tracey
O'Donnell/Anne
Desport) 
Complete  First quarter of 2023 
Review of current SST Agreement
undertaken to ensure responsibilities
clearly defined. Robust in relation to
tenant's responsibilities 2.13 and 3.3 of
agreement. 
Education
Review information
available to private
landlords on proper
waste disposal by
themselves and
tenants and promote
via PL Forum.
Housing (Tracey
O'Donnell/Anne
Desport)
Grounds Services
(Emma Berry)
Environmental Services
(Craig Brown) 
Complete  First quarter of 2024 
Grounds and Environmental Services
presented to the PL Forum on 21st March
2024. Although it was the engaged
landlords in attendance, the presentation
was well received.
In Progress
Complete
Not Started
Overdue
On Hold 
109

Page 110

Education 
Explore technology
opportunities to map
littering and review bin
infrastructure. 
Grounds Services
(Emma Berry)  In Progress  Ongoing
Litter bin mapping - available internally for
staff and available on the website for
residents. This data is assisting with the
Litter Bin Replacement Programme. 
Ellipsis Earth - survey undertaken in
November 2023 which provided
interesting and beneficial results. an
action plan has been developed to focus
on changes and initiatives that can be
made going forward. 
Education
All resources to provide
best practice
opportunities and
ideas from other local
authorities. 
All Services   
Engagement
Further engagement
with key partners and
community groups to
encourage the
creation of litter
prevention action
plans. 
All Services  In Progress  2025 
LPAP Template has been created and we
will be investigating the best way to
engage will community groups and other
key partners. 
Engagement
Review lease
agreements across all
commercial properties
to ensure appropriate
waste disposal is
included. 
Economic
Development (Iain
Ross/Victoria Eccles)
Estates (Robert
Harkness) 
Complete  2023
Lease arrangements reviewed and both
cleaning and refuse disposal are included
within. When tenants move in they are
advised that they need to contact one of
the various commercial waste contractors
to set up a waste and recycling contract. 
Engagement 
Work with community
groups and businesses
to increase
engagement,
volunteer clean ups
and build a proactive
communications
campaign. 
Grounds Services
(Emma Berry)
PR (Stephen Terry)
Community
Engagement (Gillian
Alexander) 
In Progress  Ongoing 
We continue to work with community
groups, businesses and volunteers to support
them with their clean ups and other
initiatives. Spring Clean Scotland always has
high levels of volunteers that take part and
we promote the work and outcomes. 
Increase engagement with Education to
promote all schools undertaking clean ups,
similar to Uddingston Grammar View article. 
Engagement 
Identify the most
common types of fly
tipping and create a
communication
campaign. 
Grounds Services
(Emma Berry)
PR (Stephen Terry) 
In Progress  Ongoing
It's Your Place campaign has been used
for litter and fly tipping communications,
however we haven't put of content for
specific fly tipping materials. 
Rural road clean up at Spring Clean time
is always a successful campaign. We
want to target other problem areas like
this that could be highlighted on a
seasonal/annual campaign basis .
110

Page 111

Engagement
Create a formal
communication plan
to promote the work of
the Litter Strategy
steering group that will
include a number of
different campaigns
that will cover the
themes of the strategy. 
Litter Strategy Steering
Group
Grounds Services
(Emma Berry)
PR (Stephen Terry) 
Complete  Ongoing 
It's Your Place campaign was launched in
December 2023 and the branding has
been used for a number of different
campaigns within Community and
Enterprise. 
Engagement 
Develop options to
tackle commercial
and household waste
issues in town centres
and high streets.
Housing (Tracey
O'Donnell/Anne
Desport)
Waste Services (Kirsty
McGuire/Tom
McGowan)
Estates (Robert
Harkness)
Economic
Development (Iain
Ross/Victoria Eccles)
Grounds Services
(Emma Berry) 
In Progress  Ongoing
Pilot projects in Cambuslang and
Rutherglen Main Street.
Environmental Services have had
discussions with commercial premises
regarding presentation and storage of
waste.
Waste Education Team has been visiting
households in the main streets to give
advice and encourage responsible waste
management.
Communal bin hubs to be installed in
pilots areas in town centres and main
streets.
Ongoing work with CCTV for evidence of
occurrences 
Engagement 
Increase monitoring
and mapping of fly
tipping occurrences to
identify hotspots using
the Litter Monitoring
System. 
Grounds Services
(Emma Berry)  Complete  First half of 2023
Previous fly tipping data has been
uploaded to the Litter Monitoring System
through ZWS, however we have since
found the data inaccurate for postcode
location (postcode of the enquirer and
not the fly tipping location). Other options
will be investigated in line with improving
the fly tipping web form. 
Engagement 
Upgrade the fly tipping
reporting process and
streamlined route for
customer enquiries.
Grounds Services
(Emma Berry)
Environmental Services
(Craig Brown)
Enterprise and
Sustainable
Development Service
(Linda Burnett) 
In Progress  
Reviewed all other Scottish Local authority
websites to identify good practice.
Reviewed current reporting process and
agreed streamlined route for customer
enquiries. All relevant departments were
involved in these discussions and changes
required for the proposed process. 
Engagement 
Further engagement
with businesses around
their responsibilities to
keep the area around
their premises clear of
litter and to take steps
to prevent future
littering. 
Grounds Services
(Emma Berry)
Environmental Services
(Craig Brown)
Economic
Development (Iain
Ross/Victoria Eccles)
BIDs (Victoria Eccles) 
In Progress  Ongoing
Environmental Services have had
discussions with commercial premises in
town centres regarding presentation and
storage of waste. 
Discussion undertaken with Hamilton BID
and confirmation of their commitment to
use BID communication channels to
further send out the message. Discussion
underway with Lanark BID. Litter strategy
outputs incorporated into the Rutherglen
Town Centre Strategy.
111

Page 112

Enforcement 
Scoping a way
forward for improved
CCTV provisions for fly
tipping, litter and
environmental ASB. 
Environmental Services
(Craig Brown)
Housing (Tracey
O'Donnell/Anne
Desport)
CCTV (William
McKelvie)
Grounds Services
(Emma Berry) 
In Progress  Ongoing
A improved working relationship has been
developed with the CCTV Control Centre
to make more use of public space
coverage for fly tipping, littering and
environmental ASB. 
Grounds procured 1 additional public
space CCTV camera for fly tipping
occurrences. 
Environmental Services are happy to
receive images and footage from other
council services or the public and will
investigate any incidents providing
evidence of non-compliance with fly
tipping legislation. During 2023/24 images
relating to flytipping were passed to
Environmental Health on a few occasions. 
Enforcement 
Investigate options
and sources for
funding streams for
additional CCTV
provisions.
Environmental Services
(Craig Brown)
Housing (Tracey
O'Donnell/Anne
Desport)
CCTV (William
McKelvie)
Grounds Services
(Emma Berry)
Economic
Development (Iain
Ross/Victoria Eccles) 
In Progress  Ongoing 
No funding sources available for
additional CCTV provisions. 
Grounds procured 1 additional public
space CCTV camera for fly tipping
occurrences. 
Enforcement
Investigate recharging
costs for waste in the
wrong place within
Housing factored
properties (for tenants,
private leases, and
owner occupiers). 
Housing (Tracey
O'Donnell/Anne
Desport)
Legal Service 
In Progress  Ongoing
Housing Services are continuing to
investigate the ability to rechange costs
for tenants and factored properties. This
goes along with the investigation work
they are currently undertaking to establish
who the waste belongs to. 
Enforcement
Develop a new
proactive approach to
maximise enforcement
opportunities. 
Environmental Services
(Craig Brown)  In Progress  Ongoing
Environmental Services has initiated a
project to divert resources from public
health and housing functions to a more
proactive waste enforcement and
deterrent role. The project will be
reviewed in autumn/winter 2024. 
Enforcement
Identify the most
common
geographical
locations of fly tipping
for enforcement
action. 
Environmental Services
(Craig Brown)
Grounds Services
(Emma Berry) 
Complete  2023
This is the way Environmental Services has
always operated in relation to the
deployment of surveillance cameras.
Appropriate sites are reviewed on an
ongoing basis. 
112

Page 113

Appendix 2  Baseline data 
84
86
88
90
92
94
96
98
100
2015/16 2016/17 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24
LEAMS street cleanliness score
South Lanarkshire Benchmarking club 3 National
0
20
40
60
80
100
120
140
2018/19 2019/20 2020/21 2021/22 2022/23 2023/24
Number of fixed penalty notices (FPN) issued
Fly tipping Littering Dog fouling
113

Page 114

0
2
4
6
8
10
12
14
16
18
20
2018/19 2019/20 2020/21 2021/22 2022/23 2023/24
Number of cases/reports passed on to the Procurator Fiscal (PF)
Fly tipping Littering Dog Fouling
0
500
1000
1500
2000
2500
3000
3500
4000
4500
2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023
Number of fly tipping instances
114

Page 115

0
1000
2000
3000
4000
5000
6000
2013-14 2014-15 2015-16 2016-17 2017-18 2018-19 2019-20 2020-21 2021-22 2022-23 2023-24
Dumped waste and 'waste in the wrong location' - Housing
requests
0
20
40
60
80
100
120
Number of enquiries for Community Clean Up Support
0
50
100
150
200
250
300
350
400
450
Number of bags for uplift from Community Clean Up web form
115

Page 116

116

Page 117

Report
Agenda Item 
Report to: Climate Change and Sustainability Committee 
Date of Meeting: 18 December 2024
Report by: Executive Director (Community and Enterprise
Resources)  
Subject: Artificial Intelligence (AI) Litter Survey 
1. Purpose of Report
1.1. The purpose of the report is to:
[purpose]
 provide an update on the work undertaken on the AI litter survey of Hamilton
town centre by Ellipsis Earth
[1purpose]
2. Recommendation
2.1. The Committee is asked to approve the following recommendation(s):-
[
(1) that the information, actions and next steps of the Hamilton AI litter survey be
noted. 
3. Background
3.1.  The Litter Strategy covers the period 2022 to 2027 and was approved by the Climate
Change and Sustainability Committee on 31 August 2022. The strategy outlines a
clear vision for how the Council will develop various plans and initiatives to prevent
and address litter, dog fouling, and fly tipping. It builds on existing initiatives and
complements national campaigns promoted by organisations like Keep Scotland
Beautiful and Zero Waste Scotland. 
3.2. One of the priorities from the Litter Strategy was to ‘Explore technology opportunities
to map littering and review bin infrastructure’. To achieve this priority, Grounds
Services has begun mapping all existing bin infrastructure on GIS mapping. The
service undertook soft market testing with organisations who used Artificial Intelligence
(AI) to undertake litter surveys. Hamilton town centre was selected as a good location
for a survey with a varied make up of commercial areas, residential areas, parks,
industrial zones and schools.   
3.3. The project went out to tender, with Ellipsis Earth the successful bidder. After
discussing and clarifying the survey parameters, criteria and route with Ellipsis Earth,
work began late 2023.   
4. AI litter survey
4.1.  The survey was undertaken over a week for the image collection phase. Images were
collected by smartphones and vehicle cameras. The images were then detected,
labelled and mapped by the AI software utilising machine learning. Representative
data was captured across all seven days of the week at various times of the day with
a total of 166,980 sqm surveyed. 
6
117

Page 118

4.2. The survey also incorporated 157 existing bins and 207 potential litter sources such
as cafes, transport stops and shops, for performance evaluation. A total of 113,655
items of litter were detected across a typical week, with an average of 17 items a
minute; or an item being littered across the town every 3.5 seconds and every 1.48
metres. 
5. Litter analysis 
5.1. Analysis of the most commonly littered items over the survey location shows a
proportional breakdown of littering that is very heavily dominated by a few key items,
notably plastic fragments which comprise over a quarter of all litter across the town.
These items are defined as small irregular pieces of plastic less than 2cm in size of
varied origins. These fragments are mostly from broken down food and drinks
packaging or industrial sources, and indicate a long residence time to allow
weathering, erosion or physical deterioration by wildlife. 
5.2. From the analysis, small items and fragments account for 51% of the 84% identified
in the top 10 (plastic fragment, cigarette butt, foreign object, bottle cap/lid, sachet
packet). This data shows the majority of the litter recorded is not in general a highly
visible issue since the littered items can be very small in size and fragmented. The
data allows examination of cleansing schedules and techniques and allows
investigation into the reasons for this litter being present in Hamilton when it is not
normally typical to town centres. 
5.3. Ellipsis Earth technology includes automated identification of 23 global brands across
a wide range of items - for example, specific branded items will be recognised across
hot and cold drinks cups and lids, food packaging, sauce sachets, and paper bags.
Brand analysis across Hamilton highlights minimal branded items being littered with
just 1.2% of all litter on the ground being branded and only 3.65% of all food and drinks
litter being branded. This is a low number, however, it is a higher proportion than
national averages of less than 1% all litter and 2-3% of food and drinks. 
5.4.  The most common branded items to be littered were from fast food outlets, which is
usually less common but in Hamilton was found across the entire survey; this could
be indicative of the majority active footfall demographic of the town being students,
commercial staff and commuters patronising fast food restaurants relatively frequently.
Soft drink brands were also found to be frequently littered. 
5.5. Review of the litter data shows a mixed spread of littering across the 7 days of the
week. The highest littering rates occurring midweek with lower levels across the
weekends. Littering is highest on Wednesday mornings and Thursday afternoons, with
litter levels being higher on weekday mornings except for Thursdays. Contrastingly,
litter levels at the weekends are lower overall but higher in the afternoons. This is
supported by hourly data which shows litter levels being highest during the weekdays
between 8am and 11am, with peaks on Wednesdays at 9am and Mondays at 11am,
while later weekend afternoon peaks on Friday, Saturday and Sunday being at 1pm,
and lower litter levels in the evenings throughout the week. This is opposite of typical
UK town centre littering, which usually sees low and consistent local residential worker
litter throughout the week and high levels of social littering at the weekends. It is similar
to a commuter/student town, however local knowledge would tell us weekends are still
very busy but lower littering could be explained by a different kind of visitor. 
5.6. Schools were the third most littered site after the two commercial zones. This was
particularly food and drinks litter and especially cans. School sites all saw otherwise
low-level site averages boosted by highly localised littering, with particular patterns of
118

Page 119

distribution at each school. St John Ogilvie High School saw distinct hotspots at the
school entrance with 50% of all littering occurring at Udston Road, Farm Road and
Glenlee Street from 12-1pm, and 40% occurring further away enroute away from the
school on Donaldson Street and George Street from 3-4pm, specifically outside the
sandwich shop and convenience store at High Blantyre Road, the open square
opposite food outlets which saw the second highest littering by weight, and the bus
stop on the A724 on Glasgow Road. 
5.7. Holy Cross High School saw hotspots at congregation points enroute to the Hamilton
Retail Park, which came in third for environmental impact due to the numbers of small
confectionery wrappers, and at the Auchinraith Ave sloped pedestrian exit point,
particularly between 1 and 2pm. 
5.8. Hamilton Grammar School saw hotspots on Union Street by the bus stop and along
the roadside, particularly for drinks litter between 12 and 1pm, with high numbers of
glass bottles ranking this site high by weight. All three school areas saw distinct
pedestrian routes of litter.   
6. Litter Bins        
6.1. A key element of an Ellipsis Earth Environmental Audit is the application of Bindex
software which identifies and evaluates bin provision and performance across the
survey site. In Hamilton, 157 bins were assessed. Some findings from bin evaluation
are listed below. 
 Undamaged bins captured an average of 12% more litter than damaged bins
 The colour of the bins had an impact on their performance
 Larger bins are performing better than small and medium bins
 18% of all litter present within 20m of a bin
 Over 1,000 items of litter within 20m of a bin outside schools (this is over triple
the UK average) 
7. Summary        
7.1. Hamilton received an Ellipsis Earth Environmental Audit score of 64 which is a high C
grade (UK average is a mid C). There were low levels of medium-frequency dispersed
littering across Hamilton with some very high-density litter hotspots in a number of
localised situations, notably schools, commercial centres and the train station. These
hotspots are masking an otherwise relatively clean and well-managed town. 
7.2.  Ellipsis Earth also highlighted there was a lack of bin provision in some areas of
Hamilton. This statement was questioned, however, there was agreement that there
is the wrong type of bin infrastructure in some areas and these will now be considered
as part of the review of bin provision. The results also showed that current cleaning or
collection schedules appear to be missing some hotspots, causing accumulation
patterns of litter. This has been investigated and may be explained by access
challenges caused by parked vehicles at some locations.  This is especially apparent
when concerning small and fragmented litter.   
8. Actions and next steps
8.1.  Since receiving the Ellipsis Earth report, the approach to street cleansing has been
reviewed, especially surrounding the small and fragmented litter. Litter picking is
undertaken twice daily in some locations of Hamilton town centre and along the school
routes. This should mean that new pieces of larger litter do not remain on the ground
for any length of time, however, the ‘It’s your place’ education and a behaviour change
campaign remains essential for encouraging positive behaviour going forward. 
119

Page 120

8.2.  The survey area covered three secondary schools in Hamilton, and it provided
powerful data that shows the litter issues surrounding schools and on lunch routes is
very apparent and consistent. The Grounds team has engaged with the Youth Forum
on littering and environmental issues and will continue to do so to highlight the issues
around schools as identified by the survey. 
8.3. Areas of particular concern that were highlighted from the survey were the retail parks
which are private land that the council does not service or maintain. Hamilton Retail
Park and Palace Grounds Retail Park have considerably high levels of litter recorded.
Engagement has begun with the fast-food outlets identified in the data on how this
relates to their brand and the surroundings of their premises as well specific
operational issues such as the timings and span of litter picking. Initial discussions
have been positive to date. 
9. Employee Implications
9.1. This project was an action within the Litter Strategy and a key task for the Policy
Officer. Although all Resources are contributing to the action plan, there are no other
employee implications over the standard duties. 
10. Financial Implications
10.1. The cost of the Ellipsis Earth AI Litter Survey was £17,500. 
11. Climate Change, Sustainability, and Environmental Implications
11.1. Littering and fly tipping detrimentally impact health, wellbeing, the economy, and the
natural environment. Litter and waste can lead to soil, water, and air pollution. It is
estimated 80% of marine litter originates on land. Ecosystem services and biodiversity
are also harmed. Preventing litter and fly tipping plays a key role in sustainable
development and the circular economy. The Litter Strategy will support the Council's
Sustainable Development and Climate Change Strategy outcomes. 
12. Other Implications
12.1. There are no other risks or implications associated with this report. 
13. Integrated Impact Assessments and Consultation Arrangements
13.1. This report does not introduce a new policy, function or strategy and, therefore, no
impact assessment is required. 
13.2. There was no consultation arrangements required in relation to this report. 
David Booth
Executive Director (Community and Enterprise Resources) 
27 November 2024 
Link(s) to Council Values/Priorities/Outcomes
Values
 Focused on people and their needs
 Working with and respecting others
 Ambitious, self-aware and improving
 Fair, open and sustainable
Priorities
 We will work towards a sustainable future in sustainable places
 We will work to recover, progress and improve 
Outcomes
120

Page 121

 Good quality, suitable and sustainable places to live
 Thriving business, fair jobs and vibrant town centres
 Caring, connected, sustainable communities 
Previous References
 Community and Enterprise Resources Committee report on Code of Practice on Litter
and Refuse (Scotland) 2018 on 24 August 2017
 Community and Enterprise Resources Committee report on Litter Development Policy
Officer on 26 March 2018
 Climate Change and Sustainability Committee – 10 February 2021
 Climate Change and Sustainability Committee report on Litter Strategy on 31 August
2022
 Climate Change and Sustainability Committee report on Litter Strategy Update on 20
September 2023 
List of Background Papers
 None 
Contact for Further Information
If you would like to inspect the background papers or want further information, please
contact: 
Emma Berry (Environmental Initiatives Officer)
Ext: 7775 (Tel: 07385032023)
E-mail: emma.berry@southlanarkshire.gov.uk 
121

Page 122

122

Page 123

Report
Agenda Item 
Report to: Climate Change and Sustainability Committee
Date of Meeting: 18 December 2024
Report by: Executive Director (Community and Enterprise
Resources)  
Subject: Ash Dieback Disease (ADD) 
1. Purpose of Report
1.1. The purpose of the report is to:- 
 provide an update on the work undertaken regarding Ash Dieback Disease (ADD) 
2. Recommendation(s)
2.1. The Committee is asked to approve the following recommendation(s):- 
(1) that the work undertaken to date regarding Ash Dieback Disease (ADD) be noted;
(2) that the ongoing risk, management and financial implications associated with
ADD be noted; and
(3) that the Ash Dieback Action Plan (ADDAP), as shown in Appendix 1, be noted. 
3. Background
3.1. ADD remains the most significant tree disease to affect broadleaved trees in the UK
since Dutch elm disease gained prominence in the 1960s. It has spread rapidly in
South Lanarkshire, with only a small fraction of trees proving resistant due to genetic
factors which give them disease tolerance. This incurable disease affecting only ash
species is caused by the fungal pathogen Hymenscyphus fraxineus. European data
continues to suggest it will lead to decline and death of 50%-75% of ash trees in
Scotland over two decades and has the potential to infect more than 75 million ash
trees across the country. ADD was first recorded in the UK/South Lanarkshire in 2012. 
3.2. Risks are site specific, but tree viability is questioned at +/- 50% remaining canopy
(Ash Health Class 3-4) which is also the same point that climbing by arborists becomes
unsafe. Tree death in under 4 growing seasons is not unknown. 
3.3. This report provides an update on the work undertaken in relation to ADD over the last
18 months and the Ash Dieback Action Plan (ADDAP) that was approved by
Community and Enterprise Resources Committee on 17 September 2024. 
4. Progress over the last two years 
4.1. To help inform the Ash Dieback Action Plan (ADAP), a 2022/2023 pilot project was
completed with £100,000 additional budget. The scale and impact of the disease on
high use parts of the road network from the earlier virtual survey and high use routes
in high population settlements were also investigated. 
7
123

Page 124

4.2. Additional funding of £500k was included in the capital programme for 2023/2024 to
continue the assessment and operational work on ash trees posing the highest level
of risk (not acceptable) for example Ash Health Class 3-4 (or other dangerous trees)
in high target areas. Operational work focused on reducing the ‘not acceptable’ risks
posed by Council ash trees to an ‘acceptable’ level. 
4.3. The additional funding provided the opportunity to review current operational practices
and incorporate ADD into the existing workload and move towards managing trees
pro-actively. It has enabled the purchase of specialised plant, access machinery and
procurement of contractors. It has also allowed the appointment of temporary tree
assessing Officers and temporary ‘grow your own’ operational staff, targeting the
recruitment of young people through employability and apprenticeships. This has
allowed the service to address pre-existing recruitment challenges and will provide a
level of succession planning in an ageing workforce. This also goes someway to
addressing market concerns as the general commercial arboricultural industry will not
be able to meet the expected demand over the coming years. A further £0.200m was
allocated in 2024/2025 and this has allowed this work to progress further. 
4.4. In addition, there has been a broader restructure within the arboricultural service with
the creation of a strategic function to focus on ADD, pro-active management and the
Clyde Climate Forest; and an operational function focused on the day-to-day arbor
service and tackling the current lengthy back log of reactive tree work. This has been
delivered within the existing budget of the service. As the service modernises, further
opportunities to commercialise and generate income are also being actively pursued.
The service is trialling a timber station to store and investigate potential revenue
streams associated with timber and biomass products. 
4.5. A Tree Risk-Benefit Management and Assessment approach is also being developed
to manage the risk from trees and branches falling, to meet the Council’s duty of care.
This approach uses traffic light risk ratings and development of a proportionate and
balanced ‘Tree Risk-benefit Management position statement’. An asset management
approach is being applied to trees using costs, benefits, and alignment with the
Council’s overall objectives. 
4.6. Central to maintaining easy-to-use tree records and meeting the Council’s duty of care,
is the Tree Asset Management software - Treeplotter. This is an evidence-based tool
that helps accurately target and manage resources to an acceptable level of risk. It
also enables a better understanding of our tree resource, impact of current/future
threats, and associated ecosystem services for proportionate replacement planting.
Strategic planning, working smarter and directing resources based on actual needs
are progressing well along with the provision of meaningful benchmark for monitoring. 
4.7. To help channel shift, customers are now directed to website guidance, illustrative
guide on Obvious Tree Risk Features, general public online form, Housing online form,
Frequently asked questions guide and ‘general management advice’ on Ash Dieback.
Overall, the enquiry backlog is decreasing and compliments increasing. 
4.8. In line with the Ash Dieback Toolkit (Scotland), an Ash Dieback Action Plan (ADAP)
has been developed and is presented in Appendix 1.This plan addresses the risks
presented by the impact of Ash Dieback on people and property, as well as the
ecosystems ash trees are found across South Lanarkshire. It prepares for a positive
recovery phase to achieve a net biodiversity gain by 2034 and landscape recovery by
2054. This planned approach will also help us retain more ash trees for longer so that
we can reduce the impact of ADD and manage time and costs more effectively. 
124

Page 125

4.9. With 2022/2023 Climate Emergency Funds of £100,000, an initial ADD – Recovery
and adaptation project was progressed. Alongside other drivers such as Clyde Climate
Forest, approximately 23,700 trees have been planted between 2022 and 2024, many
with community participation. Kickstarting the ‘ADD Landscape level recovery’ gained
notable community support. 
4.10. The Council is an active member of the Ash Dieback Risk Group (Scotland) that
advises the Scottish Government on associated policy and plans. As Chair of the
Scottish Tree Officers Group (STOG), the Council hosted an ADD webinar and
associated working group. This working group services practitioners from 15 Scottish
Local Authorities and has developed a technical Knowledge Hub and STOG
rebranding. The ‘KHub’ now connects Tree Officers digitally across Scotland, shares
knowledge, and collective ways of working. 
5. Current Position – South Lanarkshire
5.1. The Council’s assessments have identified approximately 124,530 (85%) Ash trees
from a best estimate population of approximately 145,977 that may impact on the
Council’s duties. These are trees either managed or owned by the Council, or in private
ownership within falling distance of the road/public area. Below is the summary of the
findings. 
Ash
Health
Class 1 
Ash
Health
Class 2 
Ash
Health
Class 3 
Ash
Health
Class 4  Est. total
regardless of
risk category 
Estimated statistics of assessment areas 
8,374 5,902 2,836 3,969 21,081  Estimated number of ash trees in private ownership and
within falling distance of the Road 
9,213 7,063  3,622  4,375  24,273
Estimated number of ash trees managed or owned by the
Council that are within falling distance of either a road or
public area target 
40,905  28,116  13,217  18,385 100,623 Estimated number of Council owned or managed
woodland/group ash trees 
58,492  41,081 19,675 26,729 145,977 Figures illustrate both assessed trees, and estimated trees
that have not yet been assessed 
5.2. Last year’s spend focused on reducing the risk to an ‘acceptable’ level for those
Council trees categorised as posing the highest level of risk (‘not acceptable’) for Ash
Health Class 3-4 in high target areas such as the core road network, emergency
access routes, high use parks and footpaths etc. This work continues with resources
being progressed by risk rating. Roadside private ‘not acceptable’ trees will be
progressed similarly, working in partnership with Roads colleagues, alongside new
processes, and practices. 
40.1%
28.1%
13.4%
18.4%
Ash Health Class Ash Health Class 1 –
100%–76% remaining
canopy (-7% from 2022)
Ash Health Class 2 –
75%–51% remaining
canopy (+1% from 2022)
Ash Health Class 3 –
50%–26% remaining
canopy (+4% from 2022)
Ash Health Class 4 –
25%–0% remaining
canopy (+2% from 2022)
0%
20%
40%
60%
80%
100%
0-5m 5-10m 10-15m 15-20m 20m+
Trees by Height Band (metres)
Class 1 Class 2 Class 3 Class 4
125

Page 126

5.3. The extent of the disease continues to steadily progress by tree size/age (see above).
60% of the identified ash trees have been assessed as Ash Health Class 2, 3 or 4,
32% as Ash Health Class 3 or 4, and 290 trees unaffected (100% alive). Of those
individual trees and groups in Ash Health Class 3 and 4, 37% are on private land. The
precise speed of decline of any individual ash tree is currently impossible to predict
and will be influenced by several factors. The targeting of long-term resource at
monitoring the health of ash trees and focusing on those trees with severe symptoms,
including root and stem decay, in higher risk locations will require continued funding. 
5.4. Financial estimates are based on the average price to remove a diseased tree with
high value targets such as roads, buildings, and utility lines or a ‘woodland’ type
settings with lower value targets. Following the increased survey work, estimates for
worse case tree works suggest that the Council’s potential financial costs associated
with dealing with 50-75% ADD mortality on land it manages or owns has now
decreased from the previous estimate of £11.000m, to between £5.100m - £9.600m
respectively. This estimate excludes traffic management costs and replacement
planting. 
5.5. Additionally, there are significant numbers of ash trees not owned by the Council within
falling distance of the road that could incur additional costs for the Council to remove
if deemed dangerous and not removed by the owner. Unfortunately, there is no simple
answer in terms of what is/is not a public road verge. Each case must therefore be
decided on its own merits by Roads and Transportation/Legal Services and the
economic impact must be mindful of these unquantified financial implications.
5.6. The delivery plan of the attached ADAP identifies the key actions required to try and
address and mitigate the consequences of this issue. Given the ongoing risk,
additional funding will be considered through future capital programmes to allow
ongoing assessment of the spread of the disease and the removal of those trees most
at risk. So far, the Scottish Government has not provided any additional funding for
this work. However, the scale of the problem is such that councils will not be able to
manage ADD safely and effectively without additional financial support. Going forward,
it will be important for the Council’s political leadership, through CoSLA and other
forums, to apply pressure for a financial commitment from Government in support of
the issue.
6. Employee Implications
6.1. Additional funding of £0.500m was allocated for 2023/2024 and this has been used to
target the recruitment of young people through employability and apprenticeships
(Grow our Own) and for the recruitment of two temporary assistant Arboricultural
Officers. Further detail has been provided in section 4. As a direct result of the ‘grow
our own’ initiative, one trainee has been permanently employed as a Council Arborist.
This has also allowed the service to address succession planning concerns. 
7.  Financial Implications
7.1. The financial implications are set out in detail in section 5, with current estimates
suggesting a potential cost of £5.100m to £9.600m over the long term to deal with
ADD on Council land safely and effectively. However, as the Council’s ADAP and
developing ‘Tree Risk-benefit Management position statement’ embed, it is hoped that
current estimates can reduce further over time. Additionally, there are significant
numbers of ash trees not owned by the Council within falling distance of the road that
could incur further costs for the Council, as set out in section 5.5. 
126

Page 127

7.2. There is no additional external funding from the Scottish Government to assist local
authorities manage or mitigate ADD, despite this now being registered as a high risk
for all Local Authorities. Scottish Forestry continue to advise that there is no statutory
plant health duty to manage ash dieback and that the safe management of trees
remains an existing statutory duty under Section 3 of the Health and Safety at Work
Act, and Roads (Scotland) Act. etc. 
7.3. Additional funding of £0.500m was allocated in the capital programme for 2023/2024
and £0.200m for 2024/2025. As the planned approach through the action plan will help
the Council retain more ash trees for longer, it is hoped the impact of ADD can be
mitigated further. Consideration to additional funding will be made through future
capital programmes to allow implementation of the action plan, retention of employees
for ongoing assessment of the spread of the disease and the removal of those trees
at most risk. 
8. Climate Change, Sustainability and Environmental Implications
8.1. If not effectively managed, ADD has the clear potential to lead to long lasting changes
in our landscape, tree populations and canopy cover, loss of ecosystem services and
may potentially increase effects such as flooding and reduce carbon lockup. 
9. Other Implications
9.1. ADD tree failures could translate into an increase in road network disruptions, the
number of people harmed/killed by trees and a potential significant increase in
vehicle/property claims. Failure to act could see the Council face an increase in liability
claims as well as reputational damage. 
10. Equality Impact Assessment and Consultation Arrangements
10.1. This report does not introduce a new policy, function or strategy or recommend a
change to an existing policy, function or strategy and therefore, no impact assessment
is required. 
10.2. There is no requirement to undertake any consultation at this time in terms of the
information contained in this report. However, as detailed proposals are developed,
these will be subject to appropriate consultation arrangements. 
David Booth
Executive Director (Community and Enterprise Resources) 
27 November 2024 
Link(s) to Council Values/Priorities/Outcomes
Values
 Focused on people and their needs
 Accountable, effective, efficient and transparent
 Ambitious, self-aware and improving
 Fair, open and sustainable
Priorities
 We will work towards a sustainable future in sustainable places
 We will work to recover, progress and improve
Outcomes
 Good quality, suitable and sustainable places to live
 Thriving business, fair jobs and vibrant town centres
 Caring, connected, sustainable communities
 People live the healthiest lives possible
127

Page 128

Previous References
 None 
List of Background Papers
 None 
Contact for Further Information
If you would like to inspect the background papers or want further information, please contact: 
Kevin Carr (Head of Facilities, Waste and Grounds)
Contact Number: 01698 845708
Email: kevin.carr@southlanarkshire.gov.uk 
128

Page 129

1
South Lanarkshire Council
Ash Dieback Action Plan (ADAP) 
7
129

Page 130

2
Contents          page
1  Summary         3
2 Introduction          4
3 Aims and objectives        4
4  Ashes and Ash Dieback       5
4.1 What is Ash Dieback?
4.2 Where is Ash Dieback?
4.3 How many ash trees are affected? 
5 Potential impact of Ash Dieback on the Council     7
5.1 Summary of legal requirements 
5.2 Financial impact  
5.3 Incorporating Ash Dieback Disease into existing workloads. 
6  Wider Impacts of Ash Dieback Disease      10
6.1 Local landowners, land managers and homeowners
6.2 Utilities and infrastructure organisations
6.3 Landscape and biodiversity. 
7 The Delivery Plan         12
7.1  Resources – existing
7.2  Continues service improvement and monitoring.  
7.3  Communication plan   
7.4  Landscape recovery plan   
Appendix 1 – Action!        14 
1. Summary 
This document lays out the Ash Dieback Action Plan (ADAP) for South Lanarkshire Council.
Ash Dieback Disease (ADD) is the most significant tree disease to affect broadleaved trees
in the UK since Dutch elm disease gained prominence in the 1960s. It has spread rapidly in
South Lanarkshire, with only a small fraction of trees proving resistant due to genetic factors
which give them disease tolerance. We plan for a scenario that it will lead to the decline and
death of 50%-75% of ash trees in Scotland over two decades.
130

Page 131

3  
Our trees and woodlands represent an essential element of the character of South
Lanarkshire and are a fundamental part of the solution to some of the key challenges of our
age, from peoples declining health and wellbeing to the climate and biodiversity emergency.
To lose these wider services will mean a noticeable impact on the environment, far beyond
the immediate visual change that will be observed. The landscape restoration programme
(recovery) will be just as important as the felling works to reduce the risk from ash trees to
acceptable levels. 
Compared with other parts of the country, our assessments do not indicate an overall high
coverage of ash trees but a steady population with pockets of high ash coverage. The
disease is now present in all areas where ash was recorded. The extent of infection, rapid
decline and early mortality of some trees suggest the disease is well established and
endemic in the wider treescape. Current estimates for the ‘best’ and ‘worst’ case scenario
suggest that the Council’s potential financial costs over the long term associated with dealing
with 50-75% ADD mortality only on land it manages or owns is estimated between £5.100m -
£9.600m respectively. However, due to the unpredictability of the disease, and the very
challenging and difficult questions associated with ownership, responsibility, and legal and
financial liability of trees along our road network there are other unquantified financial
implications. 
If not effectively managed, ADD has the potential to lead to an increase in road network
disruptions, the number of people harmed/killed by trees and a potential significant increase
in vehicle/property claims as well as reputational damage. Additionally, long lasting changes
to our landscape, tree populations, with loss of ecosystem services may have effects on
flooding and reduced carbon lockup. 
This document addresses the risks presented by the impact of ash dieback on people and
property, and the ecosystems ash trees are found across South Lanarkshire. It prepares for
a positive recovery phase to achieve a net biodiversity gain by 2034 and landscape recovery
by 2054. It also recognises the need to work together with local landowners, land managers,
homeowners, Local utilities, and infrastructure organisations. This planned approach will
also help us all retain more ash trees for longer so that we can Identify individuals with
genetic resistance, slow down the pace of landscape change and allow replacement trees
time to grow before Ash becomes scarce. 
Key Recommendations and Actions:
• Continued  ash tree assessments and action, and the respective resources.
• Knowledge exchange, comunity engagment and communication Plan.
• Tree Risk-benefit position statement,  bio‐security, and a recovery plan.
• Evidence based systems of monitoring and recording ADD spread.
• Dynamic approach to ash tree management and monitoring of the ADAP delivery
and incorporating ADD into our existing workload.
• Requirement for a Tree Canopy Cover Strategy to create greater resilience and
ensure preparedness for future tree diseases and threats.
131

Page 132

4
2. Introduction 
Ash Dieback Disease has the clear potential to lead to long lasting changes in our
landscape, tree populations and canopy cover, loss of ecosystem services and may
potentially increase effects such as flooding and reduce carbon lockup. Not effectively
managing could also translate into an increase in road network disruptions, the number of
people harmed/killed by trees and a potential significant increase in vehicle/property claims.
Failure to act could result in an increase in liability claims as well as reputational damage.
This document addresses the risks presented by the impact of ash dieback on people and
property, and the ecosystems ash trees are found across South Lanarkshire. It prepares for
a positive recovery phase to achieve a net biodiversity gain by 2034 and landscape recovery
by 2054. 
A planned approach helps us all retain more ash trees for longer so that we can: 
• identify individuals with genetic resistance to the disease
• slow down the pace of landscape change, allowing replacement trees time to grow
before Ash becomes scarce.
• reduce the impact on biodiversity and associated species.
• budget time and costs more effectively. 
3. Ash Dieback Action Plan Aims and Objective 
Aim 1 - Identify the risks from ash dieback disease to people, property and
biodiversity across South Lanarkshire.
1. Produce an overarching Action Plan to identify, communicate and manage the risks
of Ash Dieback disease. Compatible with The Tree Council's Ash Dieback: Action
Plan Toolkit for Scotland, and the collective working  of the Scottish Tree Officers
Group. 
Aim 2 - Identify management actions for South Lanarkshire Council.
2. plan for a scenario where over 50-75% of ashes die or are clearly dying within a ten-
year period.
3. Identify and manage the overall risks from the disease. 
4. Prioritise actions to address risks related to the Council's land holdings and statutory
duties.
Aim 3 - Develop a recovery plan to achieve net biodiversity gain by 2034 and
landscape recovery by 2054.
5. Plan for recovery to mitigate biodiversity and landscape losses, that is both Nature
Positive and aligns with the Clyde Climate Forest. 
6. Promote biosecurity vigilance for potential risks to South Lanarkshire’s tree and
woodland from new emerging pests and diseases. 
132

Page 133

5
4. Ashes and Ash Dieback 
4.1   What is Ash Dieback disease (ADD)?
Ash dieback disease is incurable disease affecting only ash species that is caused by the
fungal pathogen Hymenscyphus fraxineus. The fungus overwinters in leaf litter on the
ground and produces small white fruiting bodes during summer months which release
spores into the atmosphere. Spores are carried by the wind allowing the disease to spread
quickly across large distances. Spores land on and attach to the leaves of ash trees from
where the fungus can spread through the tree. The fungus blocks the water transport
systems of the tree causing leaf loss, lesions in the wood and on the bark. The crown of the
tree suffers from gradual dieback and Infected ash trees display crown decline resulting in
deadwood/dead stems at height that may be within striking distance of a target/road. This
can often be accompanied by vigorous sprouting on the trunk or branches forming in
bundles creating almost ‘pom-pom’ like clumps of crowded foliage. Infected trees can
become unpredictably brittle in structure, and at a later stage more problematic and
hazardous, and as a result more expensive to remove. Risks are site specific, and target
based, but the trees viability is questioned at +/- 50% remaining canopy which is also the
same point that climbing by arborists becomes unviable/unsafe. Tree death in less than four
growing seasons is not unknown. Risk based, alternative management options may include
pollarding, retrenchment and natural fracture pruning rather than felling.  
Ash dieback disease is the most significant tree disease to affect broadleaved trees in the
UK since Dutch elm disease gained prominence in the 1960s and 1970s. Since ADD was
first recorded in the UK / South Lanarkshire in 2012, the disease has spread rapidly across
South Lanarkshire. So far only a small fraction of trees appear resistant, possibly due to
genetic factors giving them some disease tolerance. 
Data from earlier infections across Europe suggests that it will lead to decline and death of
50%-75% (5% tolerance/immunity) of ash trees in Scotland over two decades and has the
potential to infect more than 75 million ash trees across the UK. Please see our frequently
asked questions guide for further information and guidance on ADD. 
4.2   Where is Ash Dieback?
Scotland - An assessment of the potential impact of
Ash Dieback Disease in Scotland  (Dr Rick Worrell on
behalf of Forestry Commission Scotland 2013)
showed that there are approximately 13,500 ha (total)
of predominantly ash woodland in Scotland, although
ash is a component of some 150,000 ha of native
woodland. The Native Woodland Survey of Scotland
(2014) showed: ash makes up 4.2% of upper canopy
cover in all native woodlands; ash comprises 25% of
canopy in upland mixed ashwood priority habitat
which covers 12,353 ha; and 16% of canopy in
lowland mixed deciduous woodland priority habitat
which covers 23,189 ha. Upland mixed ashwood is
commonly found across South Lanarkshire,
especially in the river and burn valleys. 15 of 32 local
authorities have officers attending the Scottish Tree
Officer ADD working group. 
South Lanarkshire - In 2020, the council’s
arboriculture team undertook a ‘Google Street View virtual survey’ of South Lanarkshire’s A
133

Page 134

6
and B roads, and sampling of U and C roads, to understand the abundance of ash trees,
and their state of health. Compared with other parts of the country, the study area did not
indicate an overall high coverage of ash trees but did indicate a wide distribution with
pockets of high density i.e. East Kilbride. The disease was present in all sections of the
survey area where ash was recorded. The extent of infection, rapid decline, and early
mortality of some trees across the network suggested it had been well established for
several years across the road network and in the wider treescape. 
In 2022/23, the scale and impact of the disease on high use parts of the road network from
the 2020 virtual survey, and other high use routes in high population settlements, were
visually assessed. The abundance of ash trees, and their state of health on the councils
remaining landholdings and woodland assets were then progressed and are still currently
ongoing. Ash Health Assessment System illustrating the state of health are as follows: 
Ash Health Class 1: 100%–
76% remaining canopy 
Ash Health Class 2: 75%–
51% remaining canopy 
Ash Health Class 3: 50%–
26% remaining canopy  Ash Health Class 4: 25%–
0% remaining canopy  
4.3   How many ash trees are affected?
The Council’s assessments have identified approximately 124,530 (85%) Ash trees from a
best estimate population of approximately 145,977 that may impact on the Council’s duties.
These are trees either managed or owned by the Council, or in private ownership within
falling distance of the road/public area. Below is the summary of the findings. 
Ash
Health
Class 1 
Ash
Health
Class 2 
Ash
Health
Class 3 
Ash
Health
Class 4 
Est. total
regardless
of risk
category 
Estimated statistics of assessment areas 
8,374 5,902 2,836 3,969 21,081 
Estimated number of ash trees in private
ownership and within falling distance of the
Road 
9,213 7,063  3,622  4,375  24,273
Estimated number of ash trees managed or
owned by the Council that are within falling
distance of either a road or public area target 
40,905  28,116  13,217  18,385 100,623 Estimated number of Council owned or managed
woodland/group ash trees 
40.1%
28.1%
13.4%
18.…
Ash Health Class Ash Health Class 1
– 100%–76%
remaining canopy (-
7% from 2022)
Ash Health Class 2
– 75%–51%
remaining canopy
(+1% from 2022)
Ash Health Class 3
– 50%–26%
remaining canopy
(+4% from 2022)
0%
20%
40%
60%
80%
100%
0-5m 5-10m 10-15m 15-20m 20m+
Trees by Height Band (meters)
Class 1 Class 2 Class 3 Class 4
134

Page 135

7
58,492  41,081 19,675 26,729 145,977 Figures illustrate both assessed trees, and estimated
trees that have not yet been assessed 
The extent of the disease continues to steadily progress by tree size/age (see above). 60%
of the identified ash trees have been assessed as Ash Health Class 2, 3 or 4, 32% as Ash
Health Class 3 or 4 and 290 trees unaffected (100% alive). The precise speed of decline of
any individual ash tree is currently impossible to predict and will be influenced by several
factors. 
5. Potential impact of Ash Dieback on the Council  
The impacts of dying and dangerous trees resulting from ADD are a significant risk and
recognised as such on our corporate risk register. This plan to manage these risks and the
impact on our statutory and non-statutory duties outlines a clear approach to manage the
problems posed by ADD. A summary of some of the risks we considered include:
• Health and Safety Impacts/ Environmental Impacts/Reputational Damage
• Financial Impacts 
• Incorporating Ash Dieback Disease management into existing workloads 
5.1 Summary of legal requirements - 
Duty of care - Under the Occupier’s Liability (Scotland) Act 1960, the Health and Safety at
Work Act (1974) and common law. We have a duty of care to manage the risk from our
trees. The duty also says we should be reasonable, proportionate, and reasonably
practicable when managing the risk. That means there's a balance we need to strike
between the many benefits trees provide, the risk, and the costs of managing the risk. By
taking a balanced approach, we don't waste resources by reducing risk - and losing benefits
- when the risk is already Acceptable or Tolerable. The council will develop a ‘Tree Risk-
benefit position statement’ and systematic assessment regime. 
Roads (Scotland) Act* – The owner of the land on which a tree is growing is responsible for
the tree. Landowners have a legal duty of care to ensure that, as far as is reasonably
practical, public safety is not compromised by the failure of tree branches or the whole tree. 
The council has duties to have a sufficient assessment scheme for trees within falling
distance of the road (and also under SLC ownership), has duties to address dangerous trees
in a timely manner within falling distance of the road/land and that there may be liability if it
fails to do so. The council has powers to serve a notice to landowners to remove or
otherwise make safe, within 28 days, trees growing outside public roads boundaries that the
council considers to be in such a condition that they are likely to cause danger by the tree, or
parts of it, falling on a public road. If the danger posed by a tree is imminent, the council may
dispense with the requirement to serve a notice and carry out the work. Financial liability lies
with the owner of the land. 
*Roads and Transportation Services and Legal Services have reviewed the very challenging
and difficult questions associated with ownership, responsibility, legal and financial liability,
and duties associated with ADD. Unfortunately, there is no simple or straightforward answer
in terms of what is/is not a public road verge. Each case must therefore be decided on its
own merits by the Roads and Transportation /Legal Services and the economic impact
below must be mindful of these unquantified financial implications. 
TPOs and Conservation Areas - ADD tree work is not exempt from the need for Tree
Preservation Order (TPO) consent and Conservation Area notification. Applications/notices
will therefore be submitted through the ePlanning portal in accordance with the standard
135

Page 136

8
procedure. Trees protected by TPO or in a Conservation Area which become infected by the
disease will lead to an increase in applications and requests for advice.   
Felling permission - Many council sites/trees are exempt from the need for felling
permission and the council will record this information on its asset management system.
Where works are not exempt, we will consult Scottish Forestry and seek felling permission. 
Biodiversity - The UK Forestry Standard requires the Council to manage its woodlands and
wider landscape in a way that conserves or enhances biodiversity. Under the Nature
Conservation (Scotland) Act 2004 the Council also has a duty to consider biodiversity in all
its work. This is affirmed as a priority in South Lanarkshire’s Biodiversity Action Plan, which
promotes the preservation and enhancement of the natural environment. Bats, birds, and
badgers are protected under the Wildlife and Countryside Act 1981. Any tree works
undertaken by the Council will proceed in accordance with this legislation to minimise
disturbance of these protected species.
5.2  Financial impact 
Following the increased assessment work, estimates for the ‘best’ and ‘worst’ case scenario
suggest that the Council’s potential financial costs associated with dealing with 50-75% ADD
mortality on land it manages or owns has now decreased, to between £5.100m - £9.600m
respectively. There is no simple or straightforward answer in terms of what is/is not a public
road verge. Additionally, there are significant numbers of ash trees  not owned by the council
within falling distance of the Road that could incur additional costs for the Council to remove
if deemed dangerous and not removed by the owner. Due to the unpredictability of the
disease and the varying impacts on our trees, the council will adopt a more dynamic
approach to ADD management and budgeting, that will be informed by on-going research,
data collection and the development of the councils Tree Risk-benefit position statement. 
The Council has invested in recent years to allow the incorporation of ADD into the existing
workload and making a step change from a reactive to pro-active service delivery. There is
still no additional external funding from Scottish Government to assist local authorities
manage or mitigate ADD, despite this being registered as a high risk for the local authorities.
Scottish Forestry also continue to advise that there is no statutory plant health duty to
manage ADD and that the safe management of trees remains an existing statutory duty
under Section 3 of the Health and Safety at Work Act, and Roads (Scotland) Act. etc. 
The action plan in appendix 1 identifies the key actions required to address and mitigate the
impact of ADD.
5.3  Incorporating Ash Dieback Disease into existing workloads. 
To help inform this Ash Dieback Action Plan, a 2022/23 pilot project was completed with
£0.100m additional budget. The scale and impact of ADD on high use parts of the road
network from the earlier virtual survey and high use routes in high population settlements
were also investigated. 
Additional funding of £0.100m in 2023/24 and £0.200m in 2024/25 was included in the
capital program to continue the assessment and operational work on ash trees posing the
highest level of risk (‘not acceptable’) in high target areas. Operational work focuses on
reducing the ‘not acceptable’ risks posed by Council ash trees to an ‘acceptable’ level with
>700 removed/pruned.  Other species trees posing an ‘not acceptable’ risk have also been
identified as part of the process and incorporated into existing workloads. 
The additional funding above has provided the opportunity to review current operational
practices and incorporate ADD into the existing workload and move towards managing trees
pro-actively. It is enabling the purchase of specialised plant, access machinery and specialist
136

Page 137

9
contractors. It has also allowed the appointment of temporary Assistant Arboricultural
Officers, temporary ‘grow our own’ operational staff targeting the recruitment of young
people through employability and apprenticeships. This has allowed the service to address
pre-existing recruitment challenges and will provide a level of succession planning in an
aging workforce. This also goes someway to addressing market concerns as the general
commercial arboricultural industry will not be able to meet the expected demand over the
coming years. 
In addition, there has been a broader restructure within the arboricultural service with the
creation of a ‘strategic’ function to focus on ADD, proactive management, Woodland
Management Plans, and the Clyde Climate Forest; and an ‘operational’ function focused on
the day-to-day arboricultural service and tackling the current lengthy back log of reactive tree
work. This has been delivered within the existing budget of the service. As the service
modernises further opportunities to commercialise and generate income are also being
actively pursued. The service is trialling a timber station to store and investigate potential
revenue streams associated with timber and biomass products. 
Tree Risk-Benefit Management & Assessment - approach is being developed to manage
the risk from trees and branches falling, and to meet the Council’s overall duty of care. This
approach uses traffic light risk ratings and development of a proportionate and balanced
‘Tree Risk-benefit position statement’. This asset management approach now being applied
to trees uses costs, benefits, and alignment with council’s overall objectives. 
Knowing our tree and woodland resource - The appointment of temporary Assistant
Arboricultural Officers have significantly helped to understand the abundance and health of
ash trees, and begin creating a record of the current condition of the council’s wider tree and
woodland resource, and identification of other pest and disease threats. 
The Tree Asset Management software is key to managing and implementing this plan. This
is an evidence-based tool that helps us accurately target and manage resources efficiently
and risk to an acceptable level. It also enables us a better understanding of the resource,
impact of current/future threats, directing of resources based on actual needs along with
effective contract management and monitoring. 
Communication and multi‐agency structure - The Council is an active member of the Ash
Dieback Risk Group (Scotland) that advises Scottish Government on associated policy and
plans. As current Chair of the Scottish Tree Officers Group (STOG) the council hosted an
ADD webinar and associated working group. This working group services practitioners from
15 Scottish local authorities and has developed a technical Knowledge Hub and STOG
rebranding. The KHub now connects Tree Officers digitally across Scotland, shares
knowledge, and collective ways of working. 
Our customer enquires are now directed to our website guidance. This provides illustrative
guide on Obvious Tree Risk Features, general public online form, Housing online form, and 
Red
‘Not Acceptable’ risks will be reduced to an ‘Acceptable’ level 
‘Not Tolerable’ risks will be reduced to an ‘Acceptable’ level, but with a lower priority than
‘Not Acceptable’ risks 
Amber  ‘Tolerable’ risks will not be reduced, but may require an increased frequency of assessment
than green ‘Acceptable’ risks   
Green  ‘Acceptable’ risks will not be reduced 
137

Page 138

10
Frequently asked questions guide and ‘general management advice’ on ADD. This approach
is more efficient in managing general enquiries and separating out specific trees needing
management. 
Biosecurity - A short biosecurity statement is also being drafted to promote implementation
and understanding of good practices to help safeguard the future of our trees from the
introduction and spread of other harmful organisms and build resilience.  
Landscape level recovery – With 2022/23 Climate Emergency Funds of £0.100m an initial
ADD – Recovery and adaptation project was progressed. Alongside other drivers such as
Clyde Climate Forest (CCF), a total of approx.  23,700 trees have been planted 2022-24 on
council land, many with community engagement.  The kickstarting of the ‘ADD Landscape
level recovery’ has gained notable and growing community support. A 3/2/1 mitigation
formula is being used: outside woodlands at least 3 new trees for loss of a large tree, 2 for a
medium tree and 1 tree for a small tree. 
In partnership with the council, in 2023 CCF undertook a high-level study that aimed initially
to identify outline opportunities for tree planting on the Councils owned or controlled land.
The opportunities identified involve various scales of planting, all of which could positively
contribute to an increase in canopy cover. The tree planting opportunities identified will be
subject to a more detailed investigation and review at a future date. This will not only help to
develop a structured approach towards CCF tree and woodland planting, but also inform off
site planting as part of our ADD landscape recovery plan. 
Across South Lanarkshire schools are beginning to use the Tree Council’s Young Tree
Champions scheme. There is support from the Tree Council to develop the  Tree Warden
scheme across the CCF. 
Developing a Tree Canopy Cover Strategy – The council is developing a Tree Canopy
Cover Strategy to ‘protect, enhance and manage’ a benefit-generating  canopy cover. At the
centre is a shared vision to build greater ecological value and resilience into its canopy cover
for future generations that is in tune with their needs and aspirations and responds to the
challenges of our times. Furthermore, the strategic approach will help better understand and
address significant threats to our tree cover, such as ash dieback, while maximising the
diverse benefits tree cover brings to our community. Whilst the developing strategy will aim
to reduce the risks of new pests and diseases affecting our tree population, it equally
recognises we can never eliminate them. The strategic approach will therefore provide a
framework to work with a wide range of partners to ensure that South Lanarkshire’s canopy
cover and economy are more resilient to the new pests that will inevitably arrive from time to
time. 
6. Wider Impacts of Ash Dieback Disease 
ADD has the clear potential to lead to long lasting changes in our landscape, tree
populations and canopy cover, loss of ecosystem services and may potentially increase
effects such as flooding and reduce carbon lockup. Not effectively managing could also
translate into an increase in road network disruptions, the number of people harmed/killed by
trees and a potential significant increase in vehicle/property claims. Failure to act could
result in an increase in liability claims as well as reputational damage.
138

Page 139

11
6.1  Local landowners, land managers and homeowners
We recognise that the people living and working alongside our own sites and road network
will be managing the impacts of ash dieback too. Where possible we will aim to: 
✓ Maximise the opportunity for appropriate tree works during road closures.
✓ Provide information to enable our neighbours to take action.
✓ Develop joint mitigation and tree planting plans where feasible. 
✓ Ensure neighbours are kept informed when our project will impact on them. 
✓ Respond to enquiries effectively to ensure trees that present a risk are addressed. 
6.2 Utilities and infrastructure organisations
We are working closely with our colleagues in other organisations and local authorities
through the Ash Dieback Risk Group (Scotland) and Scottish Tree Officers Group. There are
many crossovers with roads, rail, rivers, canals, wildlife sites, parks, and other properties. To
manage these effectively we will:  
✓ Ensure we use a consistent approach to managing our own activities.
✓ Develop our relationships to ensure we have the correct contacts in organisations.
✓ Where possible we will aim to work together to develop joint mitigation plans.
✓ Inform them when trees are identified as being under their responsibility.
✓ Respond promptly when we receive notifications from others.
✓ Monitor progress on referrals to us, and referrals from us.
✓ Use these developments to continuously improve our methods. 
6.3   Landscape and biodiversity
Trees are a fundamental part of the solution to some of the key challenges of our age, from
declining health and wellbeing to the climate and biodiversity emergency. Ash trees form a
significant proportion of old, large trees that are important for hole nesting birds and provide
roosting and hibernating places for bats. Ash is important for lichens, mosses and liverworts
and is also one of the most significant trees for invertebrates, supporting a rich diversity of
beetles, hoverflies, and moths, including uncommon or declining species.  In woodland
affected by ADD, where trees don’t pose an unacceptable level of risk, a significant
proportion of dead and dying trees should be left to provide alternative habitat for the
specialist species. 
Ash trees and ash-dominated woodlands are biodiverse supporting a large number of other
species. At least 955 species using ash trees has been collated, of which 45 are only known
to occur on ash trees and a further 62 are highly associated with ash (being rarely found on
trees other than ash). 
Pests and diseases like ADD pose a significant threat to Scotland’s biodiversity. Plant health
issues can have a direct impact on biodiversity and nature’s ability to mitigate climate
change. The loss of ash would significantly impact woodland diversity and would leave
significantly impoverished native woodlands and the urban forest.
Ash loses its leaves when they are green, meaning the leaf litter contains high levels of
nutrients and the leaf litter breaks down quickly. The ground flora within an ash woodland is
also unique as ash casts a very light shade meaning many species can grow underneath it.
If ash is replaced by tree species with a darker shade / closed canopy, some ground flora
species may decline, and this would have a negative effect on plant communities.
Replacement species should be with less shading trees such as willows, hazel, oak, silver,
and downy birch. Upland mixed ashwoods are included on the Scottish Biodiversity List.
139

Page 140

12
They are also protected under the European Habitats Directive. Woodlands are one of the
six priority ecosystems within South Lanarkshire’s Biodiversity Strategy 2024-2030. The
Clyde Valley Woodlands National Nature Reserve is an important example of ash
woodlands.  
Scottish Biodiversity Strategy 'Tackling the Nature Emergency' proposed vision by 2045 is
that we will have restored and regenerated biodiversity across our land, freshwater and
seas. Where forest/woodland management will have led to sustainable natural regeneration;
greater diversity of woodland species; increased woodland cover with healthy understorey,
enhanced woodland connectivity; and improved integration of trees into other land uses.
7. The Delivery Plan 
The plan in appendix 1 identifies the key actions
required to address each of seven major issue or risk
areas (see right). Risks to public safety and
communication networks are considered short term risks
(i.e. likely to be faced within a decade), those to the
environment longer-term risks. 
For each action, an assessment is made of its priority
relative to others. 
7.1  Resources – existing
Additional funding of £0.500m was allocated for 2023/24 and this has been used to target
the recruitment of young people through employability and apprenticeships (Grow our Own)
and for the recruitment of two temporary assistant Arboricultural Officers. As a direct result of
the initiative, one outstanding trainee has been permanently employed as a Council Arborist.
This has also allowed the service to address succession planning concerns. The additional
funding is also enabling the purchase of specialised plant and access machinery and
specialist Arboricultural contractors. 
As a result of funding and broader restructure within the arboricultural service, it is now
modernising from a reactive ‘firefighting’ service managing circa 2.4 - 2.8m trees, to a pro-
active asset managing service with a clear vision and ‘Strategic’ and ‘operational’ function. 
Long-term resources for monitoring the health of ash trees and will require continued funding
focusing on those trees with severe symptoms, including root and stem decay, in higher risk
locations. 
7.2  Continues monitoring and service improvement.  
The Action Plan will be reviewed in 2026/27 and it is expected the plan will extend to at least
2034/35. The council will monitor implementation through regular service improvement
meetings, quarterly Key Performance Indicators and reporting back to the Climate Change
and Sustainability Officers Group.  A vital part of the management of the disease will be tree
assessments, monitoring, and preparedness for the decline of the ash trees ensuring that
works and recovery are undertaken within the appropriate timeframe. The monitoring
process will ensure we have successfully included all the trees we are responsible for, where
they currently present an acceptable or tolerable level of harm but have the potential to 
Section 1: Plan delivery, communication, and
strategic planning
Section 2: Short term risks, to public safety and
communication networks
Section 3: Longer term risks, to the environment
Section 4: Assessments and monitoring, and
biosecurity
Section 5: Training
Section 6: Regulation
Section 7: Wood-based businesses 
Strategic 
Arboricultural Officer (principle). Assistant
Arboricultural Officer (2x temporary post))
Operational
Arboricultural Officer, Assistant Arboricultural Officer,
Arborists (10x)
Trainee Arborists (2x temporary post)
140

Page 141

13
become an unacceptable risk of harm within the next 3 years. ‘Strategic’ monitoring of the
disease will enable us to prioritise where, when, and how we need to carry out tree works. 
7.3  Communication plan   
The removal of trees is an emotive subject for many. Public awareness of ash dieback and
the actions necessary to manage its impacts are therefore important considerations. The
following communication approaches will therefore be initiated: 
✓ A public information campaign – social media, local press, Council website, public
signage etc - will inform the public about the Council’s ash dieback action plan and
will also provide advice to owners of ash trees. 
✓ ADD guidance - to be circulated on social media and sent to any resident who is
found to have a diseased tree. 
✓ Political communications - keeping Councillors, MPs and MSPs informed of issues
and progress. 
7.4  Landscape recovery plan   
We fully recognise that the loss of so many trees of a single species will have a detrimental
effect on the wildlife species which depend on ash and the benefits we receive from trees.
We have already started developing and implementing a proportionate and long-term ash
tree recovery plan. This plan aims to mitigate biodiversity, landscape and environmental
losses, and aligns with the council’s commitment to the Clyde Climate Forest (CCF), and
aims to achieve both a net biodiversity (ecosystem services) gain and landscape recovery. 
Progressing community involvement through the Tree councils  Young Tree Champion and
Tree Warden scheme can make a significant contribution to  the recovery plan. The Tree
Canopy Cover Strategy will help provide a framework to continue to work with a wide range
of partners to ensure that South Lanarkshire’s canopy cover and economy are more resilient
to the new pests that will inevitably arrive from time to time. 
141

Page 142

14
Appendix 1 - Action
Section 1: Plan delivery, communication, and strategic planning  AA - Arboricultural Association  AO/-AO(S)- Arboricultural Officer (Operational /Strategic)
Section 2: Short term risks, to public safety and communication networks  ADRG - Ash Dieback Risk Group (Scotland) HoS - Head of Service 
Section 3: Longer term risks, to the environment  STOG - Scottish Tree Officers Group CCSOG Climate Change and Sustainability Officers Group
Section 4: Assessments and monitoring, and biosecurity ATO - Association of Tree Officers  SEA - Strategic Environmental Assessment Corporate Working
Group Section 5: Training  CAG – Countryside and Greenspace
Section 6: Regulation  CT- Communications Team 
Section 7: Wood-based businesses WT – Woodland Trust 
# Topic Key people/
bodies affected Section 1 Actions: Plan delivery, communication, and strategic planning  Priority Lead Timescale 
1 Plan delivery CCSOG, AO,  Incorporate the ADAP into existing workloads High HoS, Ongoing 
2 Communicati
on 
CT, CAG,
stakeholders 
Develop and deliver an ADD communications plan High AO(S),
CT
Ongoing 
3 Knowledge
exchange &
multi-agency 
AO, STOG, ATO,
ADRG, AA, CAG
Continue to contribute to the STOG, ADRG and ATO. Develop methods that
provide a long-term system improvement leaving us equipped to other large-scale
environmental impacts.
High AO(S),
BO
Ongoing 
4
Working
together
CAG, Grounds,
landowners/
managers
homeowners 
Provide information for the Local landowners, land managers and homeowners
to enable them to act. 
Where appropriate, work closely utilities and infrastructure organisations on
ADD 
High Roads,
CT
2025 
5
Tree/woodla
nd Strategy 
SEA, stakeholders  Develop a Tree Canopy Cover Strategy that helps reduce the risks of new pests
and diseases affecting our tree population.  Med 
AO(S)
Planning,
SEA, CT 
2025
6 Strategic
planning
Roads, CAG Ensure that emerging policies, strategies, and management plans consider the
implications of ADD and other serious pests and diseases. Carry out an audit of
existing policies and processes that may need to be reviewed.  Promote the
recognition of trees as benefit generating assets. 
Med  AO(S)
SEA
2024/25
7 Financial
planning
Finance, AO,
AO(S)
Secure additional funding for dealing with ADD  High  HoS Ongoing
Key
142

Page 143

15
8 Potential -
rogue
traders
taking
advantage of
situation
Comms Team,
STOG, AA, AO,  Promote guidance on how tree owners can appoint professional tree
contractors and expected standards. Alert Trading Standards to any reports of
rogue tree contractors linked to ADD and work to resolve/ minimise issues as
appropriate
Med  AO(S),
Trading
Standards
2024
9 Woodland
management  All stakeholders  Incorporate ADD, progress good woodland management practices and the
development of woodland management plans for council landholdings. 
Med AO(S),
CAG
Ongoing
# Topic Key people/
bodies affected
Section 2 Actions: Short term risks, to public safety and communication
networks Priority Lead Timescale 
10 Risk-benefit
based
approach 
AO, Housing, CAG,
Grounds Education,
Planning, Property
Establish and implement a ‘Tree risk-benefit position statement’ to manage the
risk from trees (including Ash) and branches falling, and to meet the Council’s
overall duty of care. 
High  AO(S),
Roads,  
Ongoing
11 Prioritisation
of tree works 
AO, CAG Develop, maintain, and monitor, processes to ensure that any resulting action
as a result of tree assessments are untaken within an appropriate timescale.
Tree removals will be undertaken using a risk-based approach to prioritisation. There
may be circumstances that merit the pre-emptive felling of healthy ash trees,
although this will be minimised.
High AO(S),
AO,
Roads 
Ongoing
12  Tree Work
framework
AO(S), Contractors  Develop a Tree Work contractor framework along with Contractor access to
SLC tree management software 
Med Procurem
ent 
2025
13 Ash on
private land
adj. Roads
Roads, Legal, AO,
contractors
Where appropriate the council will use its powers under the Roads (Scotland)
Act. Council has powers to deal with private trees and enforce their removal where
they pose an unacceptable level of risk to the Road network. The council will also
recover reasonable costs. 
High  Roads,
AO(S),  
Ongoing
# Topic Key people/
bodies affected Section 3 Actions: Longer term risks, to the environment Priority Lead Timescale 
14 Community
involvement 
The Tree Council,
AO (S),
stakeholders, 
Community team,
CT, Education
Create a wider stakeholder group for  tree and woodlands through development
of a Tree Warden scheme - The Tree Council, promotion of the existing Young Tree
Champions - The Tree Council and Clyde Climate Forest. 
High Communit
y team,
Education 
Ongoing -
2024
15 Promote
best practice
All stakeholders,
SEA, Planning
Liaise with owners and managers of designated wildlife sites to assess impact
of ADD and assist in developing strategies to minimise. Promote the healthy,
Med  AO(S),
CAG
2024/25
143

Page 144

16
to enhance
biodiversity
sustainable, management of hedges, woods, etc to increase their resilience to ash
dieback and other diseases. 
16 Ancient, Vet
trees
All stakeholders,
CT, STOG, WT
In addition to designated sites Identify veteran and ancient trees, ancient
woods with ash on council land.  Ancient Tree Inventory - Woodland Trust
Med AO(S),
CAG  
Ongoing 
17 Tree
diversity and
size 
CAG Monitor SLC individual tree diversity using the 10-20-30 rule (suggests 10% of
any one species, 20% of any one genus, or 30% of any family) and SLC individual
tree size distribution using industry standard. 
Med AO(S), Ongoing
18 Landscape
restoration
programme 
AO, Housing, CAG,
Grounds Education,
Roads, Planning,
Property, CCF,
STOG, Scottish
Forestry
Favour direct replacement planting wherever felling occurs dependant on site
suitability. Mitigate tree loss by the 3/2/1/ formula (minimum of at least 3 new
trees for loss of a large tree, 2 for a medium tree and 1 tree for a small tree
(excluding woodlands)). 
Develop and implement a longer-term ash tree recovery plan to mitigate
biodiversity, landscape and environmental losses that aligns with the council’s
commitment to the Clyde Climate Forest and aspires to a net biodiversity gain
(by 2034) and landscape recovery (by 2054). 
Med AO(S),
Roads
Comms
Team
Ongoing –
2026
# Topic Key people/
bodies affected Section 4 Actions: Assessments, monitoring, and biosecurity Priority Lead  Timescale 
19 Establish
pro-active
assessments 
AO, Housing,
Grounds,
Education,
Planning, Property,
CAG
Based on the Tree Risk-benefit position statement, establish a proportionate
and balanced assessment regime to understand the abundance and health of
ash and other trees the council has duty towards. 
High  AO(S),
Roads,
2024
20 Action plan
delivery
CCSOG, AO,  Monitor ADAP’s delivery. Embed the delivery plan into monthly Arbor service
improvement meetings, quarterly Roads Team meeting, report KPI’s quarterly to HoS
and yearly to the CCSOG.   
High AO(S),
HoS,
2024
21 Biosecurity SEA, Landscape
team, CAG, 
Develop a biosecurity statement - promote implementation and understanding of
good practices to help safeguard the future of our trees from the introduction and
spread of other harmful organisms 
High  AO(S),
CT
Ongoing 
# Topic Key people/
bodies affected Section 5 Actions: Training Priority Lead  Timescale 
144

Page 145

17
22 Tree Risk-
benefit
statement
AO, CAG, Grounds,
Roads, 
Undertake Tree Risk-benefit position statement and Tree plotter training for
core staff. Provide training for all relevant staff to identify ash dieback, when a tree
has become a significant risk and how to report. 
High  AO(S),
Roads
June/July
2024
23 Tree Asset
Management 
Contractors, AO,
Arb chargehands 
Undertake training on the use of Tree plotters for ‘Contractor’ access.  High AO(S),
Roads
2024
# Topic Key people/
bodies affected Section 6 Actions: Regulation Priority Lead  Timescale
24 Protected
trees
Planning  Ensure adequate staffing for the administration of ash dieback related
applications for Tree Preservation Orders, Conservation Area, and Planning
Conditions etc. 
High  Planning Ongoing
25 Felling
permissions
AO, Contractors  We will establish a process for obtaining permission for each relevant site. We
will note exceptions for a felling notice on Tree Plotter, where they apply. 
High  AO(S),
AO 
2024
26 Duties to
tree safety 
AO(S), AO, CAG,
Roads, Education,
Planning, Housing,
Grounds, Legal 
We will comply with our duty of care to manage the risk from our trees. We will
be reasonable, proportionate, and reasonably practicable when managing the risk.
We will strike a balance between the many benefits trees provide, the risk, and the
costs of managing the risk. 
High  Hos Ongoing -
2025
27 Ash on
private land
adjacent to
Roads
Roads, Legal, AO,
contractors
Establish a communication/serving of notice protocol, reporting, and
monitoring system along with cost recovery process.  Develop a process for
identifying and responding to ADD on land where ownership is private or unclear.
Develop a site notice specific for ash dieback with advisory information which can be
attached to trees on private land adjacent to the network. Each case will be decided
on its own merits by the Roads and Transportation Services. 
High 
Roads,
AO(S),    2025
# Topic Key people/
bodies affected Section 7 Actions: Wood-based businesses Priority Lead  Timescale 
28 Explore use
of products
of ash felling
Grounds, CAG, Investigate further opportunities to commercialise & generate income from tree
arisings. Investigate the development of a timber station and revenue streams
associated with timber and biomass products. Also explore outlets for wood & arising
other than fuel (Biomass and firewood) which reduce the rate of loss of stored
carbon. Including strategies for deadwood 
Med  AO(S),
AO 
2025 
145