Caledonian Economics 
Argyll & Bute Council
Mainland Ferries Study

Page 2

Caledonian Economics 
Argyll & Bute Council
Mainland Ferries Study
Comparative Analysis of Options for Council-run ferries
April 2024

Page 3

Caledonian Economics 
Introduction
Argyll & Bute Council is responsible for four ferry services to Jura, Luing, Easdale and Lismore.
Three of the four routes are operated using ageing vessels and none have any vessel redundancy.
The services currently operate at a significant deficit with a Scottish Government settlement
required to help bridge the funding gap.
The forthcoming Islands Connectivity Plan (ICP) being produced by Transport Scotland seeks to
address the future of ferry and alternative transport for Scottish Islands but excludes those ferry
services operated by Local Authorities. This report seeks to address the mainland ferry services
operated by Argyll and Bute Council.
The Jura –Islay route is not considered in this report. This is due to separate legislation that
covers this specific route which is set in a unique location and is subject to wider workstreams
already in motion.
The current Lismore service was initially considered within this report. The route is currently
serviced by the newest vessel in the fleet, with a life expectancy of at least 15 years.
There are issues with timetable provision which encroach on the operational performance,
these will be dealt with through a proposed ferry user forum to be established.
This report concentrates on the lifeline services provided between Luing– Seil and Easdale -
Seil. Both services are supported by aging vessels and insufficient infrastructure which does
not comply with current Equalities Act Legislation.
This report seeks to provide further information on current services and offers potential future
solutions in both locations along with information gathered via public consultation with local
users.

Page 4

Caledonian Economics 
Isle of Luingand Easdale Island Ferry Crossings
Past, Present and Future
1. Background: Population trends and subsidies
2. Isle of Luing/Cuan Crossing:
• Past and present
• Options, analysis and conclusions
3. Isle of Easdale:
• Past and present
• Options, analysis and conclusions
4. Other Impacts on Public Services
5. Final Comments
6. Appendices
4

Page 5

Caledonian Economics 
Population Trends
Argyll and Bute Population Forecasts
(Source: National Records of Scotland)
5
79,500
80,000
80,500
81,000
81,500
82,000
82,500
83,000
83,500
84,000
2023 2024 2025 2026 2027 2028
Argyll and Bute Population Forecast (2018 based,
Source NRS)
Population
0
5,000
10,000
15,000
20,000
25,000
30,000
0 to 15 16 to 24 25 to 44 45 to 64 65 to 74 75 and
over
Age cohort forecasts (2018-2028 Source: NRS)
2018 2028
The population of Argyll and Bute is forecast to fall and age

Page 6

Caledonian Economics  6
• School roll forecasts for Easdale
and Luing were presented during
the statutory consultation on the
future of Luing Primary School.
These indicate a similar picture of
population decline
• The population of Oban Lorne
and the Isles is forecast to fall
and age, following a similar
pattern to Argyll and Bute
presented on the previous page
Population Trends
Oban, Lorne and the Isles
(Source: NHS Scotland)

Page 7

Caledonian Economics 
Scottish Transport Appraisal Guidance (STAG)
Study, Cuan 2007
STAG Options Appraisal for Cuan Sound Crossing – key points
• Appraisal Conducted: Evaluation by STAG of the transport possibilities for the Cuan Sound
crossing.
• Options Considered: A range of solutions including high/low level bridges, a causeway, a
tunnel, and enhancements to the ferry service schedule.
• Identified Issues with current provision: Disruptions in the ferry service, insufficient capacity
during peak times, limitations for large vehicle transport, constrained Sunday/evening
services, financial challenges, high perceived costs, and limited access to Seil and the
mainland.
• Community Perspective: Debate on whether to retain and improve the current ferry service
or construct a fixed link.
• Excluded Options: low-level bridge, causeway, and tunnel options were rejected from initial
list due to navigation, environmental, geological, and financial concerns.
• Appraisal Conclusion: A detailed appraisal indicated that a bridge provides the most
significant improvement in accessibility, benefiting social inclusion, economic gains, and local
business growth.
• Overall Recommendation: Advised building a high-level bridge for optimal economic and
social advantages.
Framework for Luing’s Future 2022
Isle of Luing Community Housing and Business Needs Survey Report
2023
Consultation overview:
• Studies were carried out on behalf of the community
• Involved residents (past and present), stakeholders and authorities
Key Findings
• Strong community interest in enhancing connectivity
• Poor transport links are cited as a reason for people leaving the island
• Request for more reliable and frequent transport links to support local economy and
accessibility.
• Plans to develop housing and expand the economy
• Concerns about the current infrastructure’s capacity to meet future demands.
7
Isle of Luing
Cuan Sound Crossing
Past Studies

Page 8

Caledonian Economics 
• MV Belnahua provides all sailings. The Grey Dog and/or alternative vessel is hired in
when MV Belnahuais away for her refits.
• The service runs at an annual loss of around £366,000 (based on the 2023 Service
Review), expected to rise to £470,000 as the vessel ages.
• MV Belnahua was built in 1972 and is at the end of her reasonable and already extended
life. Parts can no longer be sourced for her engines and work is required to bring her up to
standard with current marine requirements. She is also operating around 25% above
capacity to support demand, especially in summer. She is scheduled to have a life
extending refit early in 2024 that will fit new engines and other compliant equipment such
as fixed firefighting equipment and bilge alarms. This should extend her life for around 5
years but she needs to be retired.
• Current plan is that a new vessel will be built for the Jura-Islay route which would free up
MV Eilean Dhiurato replace the MV Belnahua.
• This is currently unfunded so there is not a timescale for this. The condition of the MV
Belnahuawould dictate a maximum of 5 years to prepare the Cuan crossing in readiness
for the MV Eilean Dhiurato use it, if it is freed up by then.
• The gradient on the pier on Luing does not meet Equalities Act guidelines and there
needs to be facilities for an overnight berth for the vessel.
• Previous proposals suggested a new slip would be constructed to suit MV Eilean Dhiura.
This would need be complicated by the need to operate the current slip until a new slip
was completed.
8
Isle of Luing
Cuan Sound Crossing
Current Situation

Page 9

Caledonian Economics 
Passenger/Vehicle Numbers (on basis of
tickets sold)
2022/23 Actual HITRANS 2003
SPT Concessionary Travel 1044
Foot Passengers and drivers (single and
return)
9,805
Foot Passengers and driver on 5-Return
Journey tickets
5 x 2 x 2,453 = 24,530
Total Passengers 35,379 20,170
Private motor cars 3,276
Private motor cars on 5-Return tickets 5 x 2 x 1,406 = 14,060
Car Blue Badge 633
Motorcycles 52
Total cars and MCs 18,021 14,337
Commercial vehicles/coaches – 5-8m 484
Not availableCommercial vehicles/coaches – 8-12m 138
Commercial vehicles/coaches – 12-18m 5
9
• Passenger numbers increased by around 75% and private vehicles up 25% from
2003 to 2023
Isle of Luing
Cuan Sound Crossing
Ferry Services Data

Page 10

Caledonian Economics 
Adult return Car return Commercial return
Per STAG (Published March
2007 so data assumed to
be from 2006)
£1.45 £5.90 £13.20
(>3.5t)
Current 2023 £2.50 £9.70 £17.10
(5-8m)
% increase 72% 64% 30%
10
• A range of other tickets are offered in addition to those shown, including multi-journey
booklets, concessions and children.
• Price inflation for the period 2006 to 2023 was around 65% so the price of the basic
passenger and car tickets appear to have kept pace with inflation.
• The price of tickets for commercial vehicles seems to have lagged inflation although the
basis of classifying commercials has changed from weight to length.
• SPT concessionary travel is too small value to be claimed back
Isle of Luing
Cuan Sound Crossing
Ticket Prices

Page 11

Caledonian Economics  11
• Option 1 – Operate MV Belnahuafor five years, then open low bridge
• Option 2 - Operate MV Belnahuafor five years, then use MV Eilean Dhiura* for five years
to the same timetable, then open low bridge
• Option 3 - Operate MV Belnahuafor five years, then use MV Eilean Dhiura* for five years
with an enhanced timetable, then open low bridge
• Option 4 – Operate MV Belnahuafor five years, then open high bridge
• Option 5 - Operate MV Belnahuafor five years, then use a new vessel (hybrid-powered)
for the remainder of the period of the analysis (with mid-term replacement)
1. Assumed no scrap/resale value for ferries
2. ‘Low bridge’ would be an opening bridge to allow vessels to pass through
3. ‘High bridge’ would have clearance for vessels to pass under
* MV Eilean Dhiura currently operating on the Jura to Islay route and this option is subject
to Argyll and Bute Council gaining funding  for a replacement vessel for this route.
Isle of Luing
Cuan Sound Crossing
Future Options Assumptions

Page 12

Caledonian Economics  12
• Net present value (NPV) using the Treasury Green Book discount rates is the correct metric
to use for investment appraisal of this type.
• Total cash is also shown for comparison.
• Capital cost cashflows are assumed to happen in the first year of operations for the asset
concerned.
30.0
34.3 35.4
49.5
84.8
22.9 22.7 23.5
38.8
50.6 
-
10.0
20.0
30.0
40.0
50.0
60.0
70.0
80.0
90.0
Belnahua then low bridge Belnahua then E.D. same TT
then low bridge
Belnahua then E.D +TT then
low bridge
Belnahua then high bridge Belnahua then Hybrid
Cuan 60 year cash and NPV, £M
60yy Cash 60yy NPV
Isle of Luing
Cuan Sound Crossing Options
Net present value

Page 13

Caledonian Economics  13
0.0
10.0
20.0
30.0
40.0
50.0
60.0
1 2 3 4 5 6 7 8 9 101112131415161718192021222324252627282930313233343536373839404142434445464748495051525354555657585960
Cuan DCF £M
Belnahua then low bridge Cumulative
DCF/NPV
Belnahua then E.D. same TT then low bridge Cumulative
DCF/NPV
Belnahua then E.D +TT then low bridge Cumulative
DCF/NPV
Belnahua then Hybrid Cumulative
DCF/NPV
Belnahua then high bridge Cumulative
DCF/NPV
Isle of Luing
Cuan Sound Crossing Options
Discounted cash flow
• See Appendix 2.1 to 2.5 for details of how costing estimates were prepared

Page 14

Caledonian Economics 
Support for a Fixed Link (Bridge or Tunnel):
• Over a quarter of respondents expressed explicit support for a fixed link, either a bridge or
tunnel
• those expressing support saw benefits in terms of connectivity and ease of access for work,
leisure and essential services.
• There were few specific objections to a fixed link - more people would simply prefer an
improved ferry service
Support for Ferry Service:
• Over half respondents expressed a preference for retention of the ferry service,
• However, many are dissatisfied with the vessel, the reliability, and the level of service.
• Commonly expressed views include a better vessel, an extension of the timetable, better
links with other public transport, and reduced fares.
Common Concerns and Suggestions:
• Cost: A common theme is the concern over the cost of the ferry service and its impact on the
island's residents, with suggestions for reduced fares.
• Accessibility: Several comments mention the need for better accessibility, especially for
wheelchairs and prams.
• Timetable: Many residents express a desire for a ferry timetable that accommodates
residents’ needs, including later services and better synchronization with buses.
• Sustainability: Some responses highlight the need for sustainability, mentioning electric
ferries and a service that doesn't rely on the ferry.
• Employment: The ferry service is noted as providing local employment, which is valued.
14
Isle of Luing
Cuan Sound Crossing Options
Residents Survey Findings (2024)

Page 15

Caledonian Economics 
Financial Analysis1:
• a fixed link (low level) as soon as possible is the lowest cost in cash terms.
• Using the MV Eilean Dhuirabefore building a fixed link (low level) adds around £4M to the total in cash terms, no material difference in NPV
• Extending the timetable adds slightly over £1M in cash and NPV terms
• Compared to a low level bridge, a high level bridge adds around £20M (cash) or £8M (NPV). A high level bridge would be preferable from a navigability and resilience perspective.
• A permanent ferry solution is almost three times to cost of a low level bridge in cash terms, or around 1.7 times the cost of a high level bridge in NPV terms
Community views:
• There is notable dissatisfaction with the current arrangement
• This is a general preference for improving the ferry service, although a significant number of respondents see real benefits in a fixed link
• Few specific objections to a fixed link were raised.
Next steps/way forward:
• This is a preliminary analysis that could be expanded on in future studies. It is not intended to be a full options appraisal in line with the STAG and HMT Green Book methodologies, but it follows their principles and can be considered a starting point for full studies in the future.
• There is no plan for the route beyond the life of the existing aged vessels (MV Belnahuaand MV Eilean Dhiura).
• Thus, a solution needs to be in place in five years (without Eilean Dhiura) or in ten years (if Eilean Dhiurabecomes available)
• The long-term options are either a new vessel or a fixed link.
• The long-term costs of a fixed link are significantly less than a replacement ferry.
• The community has expressed dissatisfaction with the existing arrangement.  Some in the community would prefer to see this addressed by an improved ferry service, others would prefer a fixed link.
• The community has plans to attract new families to the island and to develop the local economy, including reopening a quarry.  Good transport connectivity will help these important initiatives succeed.
• Either solution will require significant capital investment.  A fixed link would provide a permanent solution at a lower cost, address many aspects of the community’s dissatisfaction with the current arrangements, and facilitate improvements in public service delivery.
• Considering long-term sustainability and cost-effectiveness, this study concludes that the preferred option from a technical and financial would be a fixed link.
• It is recommended that these options be explored more fully including detailed technical appraisals, updated STAG study and relevant community engagement in line with legislation.
15
1 60-year comparisons
Isle of Luing
Cuan Sound Crossing Options
Conclusions

Page 16

Caledonian Economics 
Intentionally blank
16

Page 17

Caledonian Economics 
Scottish Transport Appraisal Guidance (STAG) study, Easdale 2009
Transport Options Appraisal for Easdale Island – key points (2009)
• Appraisal Conducted: Evaluation by STAG to determine suitable transport options for Easdale
Island.
• Options Explored: Considered either an upgrade to the existing ferry service or the
construction of a causeway with a fixed bridge.
• Ferry Service Option: Found to be more cost-effective, aligned with transport objectives but
would require additional infrastructure and presented financial risks for the Council.
• Responsibility Transfer:Suggested that giving Islanders control could lead to better financial
management and tailored services (although it was unclear if there was appetite or capacity
for this in the community)
• Causeway Construction Option: Better reliability and safety at higher cost.  Would require an
Environmental Impact Assessment. Community acceptance uncertain (presumably meaning
that the community could block the development at the planning stage )
• Community Consideration: The causeway's benefits would depend on how much it is utilised
by the island's residents (although presumably this would be at least the same as the ferry
use)
• Overall Recommendation: the study was inconclusive.
17
Easdale Island
Easdale Sound Crossing
Past Studies

Page 18

Caledonian Economics 
• Per the Easdale STAG, the route is covered by MV Fladdaand ML Easdale (relief vessel).
• The service runs at an annual loss of around £290,000 (based on the 2023 Service Review),
expected to rise to over £600,000.
• No plans for changes/improvements until the results of this appraisal are available.
• The harbour is owned by ‘Eilean Eisdeal’, the Easdale Island Community Development Group
• Slipway is owned by Argyll and Bute Council
• Easdale Island is privately owned. Owner was contacted for comment as part of this study but
has not responded.
• Ongoing dredging of the harbour at Easdale is undertaken by the Council if deemed necessary
along with any routine repairs to both slips as required.
18
Easdale Island
Easdale Sound Crossing
Current Situation

Page 19

Caledonian Economics 
Passenger Numbers Easdale 2022/23 Actual1 HITRANS 20032
SPT Concessionary Travel 346
n/a
Out of Hours (before and after midnight).
Foot Passengers (individual single journeys). 10,690
Foot Passengers – travelling on 5-return
journey books sold)
12,422
Freight Customers n/a
Other (please specify) n/a
Total Usage (individual journeys) 23,458 18,1723
19
1 ABC - Marine Operations Data Requirements v3 (17 July 23)
2 Strategic Sea Crossings in the Highlands and Islands: Development
Opportunities 2005-2025, Nov 2005, Fisher Associates on behalf of HITRANS
3 a figure of 13,000 was given in the text of the STAG report
• Use has increased by around 29% 2003-2023
Easdale Island
Easdale Sound Crossing
Ferry Services Data

Page 20

Caledonian Economics 
Adult return Car return Commercial
return
Per STAG (Published March
2009 so data assumed to be
from 2008)
£1.55
Passenger-only serviceCurrent 2023 £2.50
% increase 61%
20
• A range of other tickets are offered in addition to those shown, including multi-
journey booklets, concessions and children.
• Price inflation for the period 2008 to 2023 was around 65% so the price of the basic
passenger ticket appears to have kept pace with inflation
Easdale Island
Easdale Sound Crossing
Ticket Prices

Page 21

Caledonian Economics  21
• Option 1 - Do minimum, continue to provide current service and replace vessels like
for like - minor improvements to waiting room/staff accommodation
• Option 2 - Replace the vessel with a Landing Craft-type vessel & minor waiting room
improvements (with mid-life replacement)
• Option 3 - Replace the vessel as above and build four breakwaters, relocate slipways,
and provide new waiting facilities
• Option 4 - Install fixed link (footway to take vehicles no larger than  quad bike size)
• Option 5 - Install fixed link as above with additional services
Easdale Island
Easdale Sound Crossing
Future Options Assumptions

Page 22

Caledonian Economics  22
39.4
44.2
83.7
7.3
11.6
25.3 28.5
67.6
6.9 9.6 
-
10.0
20.0
30.0
40.0
50.0
60.0
70.0
80.0
90.0
Option 1 Do minimum Option 2 - Landing Craft Option 3-  vessel +
breakwaters
Option 4 - Fixed link Option 5 - fixed link +
Easdale Crossing -60 year cash and NPV cumulative(£M)
Total Cash NPV @ 60 years
Easdale Island
Easdale Sound Crossing
Net Present Value
• See Appendix 1.1 to 1.5 for details of how costing estimates were prepared

Page 23

Caledonian Economics  23
-
10.0
20.0
30.0
40.0
50.0
60.0
70.0
80.0
1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 33 35 37 39 41 43 45 47 49 51 53 55 57 59
Easdale -Cumulative Discounted Cashflow (£M)
Option 1 - Do Nothing
Option 2 - Replace with Landing Craft-type vessel and minor waiting room improvements.
Option 3 - Replace vessel as above and build 4No Breakwaters, relocate slipways, provide new waiting facilities
Option 4 - Fixed link
Option 5 - Fixed Link Plus Extra Support
Easdale Island
Easdale Sound Crossing
Discounted Cash Flow
• See Appendix 1.1 to 1.5 for details of how costing estimates were prepared

Page 24

Caledonian Economics 
Support for Improving the Ferry Service:
• Residents prioritise compliance with legislation and addressing access issues due to climate
change.  Many called for a solution to the infilling of the harbour.
• There is a desire for a ferry better equipped to handle a range of items, reduce manual handling
issues, and improve accessibility
• Several residents emphasised the need to retain the ferry service to preserve the island's
character and prevent negative ecological impacts. Suggestions include better parking,
improved ferry facilities, and enhanced welfare facilities for staff
• There are calls for multiple breakwaters to be constructed to reduce weather interruptions,
ensure safety and stop the problem of slate filling the harbour.
Support for a Fixed Link:
• A very small number express a preference for a fixed link to modernise access to the island,
with one respondent specifically suggesting a bridge for its modern convenience and potential
to enhance trade.
Concerns and Additional Suggestions:
• The concerns about infrastructure extend to the preservation of the island's ecology and the
well-being of its wildlife, with some respondents worried about the introduction of invasive
species if a fixed link were built (Responses #5, #57).
• Residents express a deep appreciation for the ferry staff and the community spirit they
embody, highlighting the social aspect of the ferry service.
• There is an acknowledgment of the island's unique character and its appeal to tourists, which
many feel would be compromised by infrastructure changes.
• Financial sustainability of the ferry service was also mentioned, with suggestions for integrating
ferry ticket costs into council tax for residents and increasing prices for visitors.
24
Easdale Island
Easdale Sound Crossing
Residents Survey Findings (2024)

Page 25

Caledonian Economics 
Financial Analysis:
• In cash terms, a fixed link is a fifth of the cost of maintaining the current arrangement, around one quarter in NPV terms.
• Continuation of the existing arrangement is around £5M cash (£3M NPV) less than replacement with a Landing Craft-type vessel with replacement at year 30.
• In NPV terms the cost of creating breakwaters (with replacement vessels and slip upgrades to meet regulations) is ten times the cost of creating a fixed link
Community views:
• There is resistance to a fixed link
• Concerns about a fixed link include ecological issues and fear of problems brought by visitors.
• Residents express a deep appreciation for the ferry staff and the community spirit they embody, highlighting the social aspect of the ferry service.
• The community values the island's unique character and its appeal to tourists. Many feel this would be compromised by a fixed link.
Next steps/way forward:
• This is a preliminary analysis that could be expanded on in future studies. It is not intended to be a full options appraisal in line with the STAG and HMT Green Book methodologies, but it follows their principles and can be considered a starting point for full studies.
• The cost of maintaining the existing arrangement is unviable.
• The costs of breakwaters are prohibitive.
• The long-term costs of a fixed link are far less than maintaining the existing arrangement.
• Considering long-term sustainability and cost-effectiveness, this study concludes that the preferred option from a technical and financial perspective would be a fixed link.
• It is recommended that these options be explored more fully including detailed technical appraisals, updated STAG study and relevant community engagement in line with legislation.
• The communities on Jura and Ulva operate ferry services themselves, funded directly by central government.  This is an additional option to consider for Easdale if the community were to present a sustainable and deliverable long-term business model.
25
Easdale Island
Easdale Sound Crossing
Conclusions

Page 26

Caledonian Economics  26
Intentionally blank

Page 27

Caledonian Economics 
Waste Collection - Luing:
• Currently a ‘narrow width’ refuse vehicle is used to provide waste pick up from Luing.
The weight of the the vehicle and refuse is restricted by the ferry weight limit.  The
Council has a limited number of such vehicles which increases the risk of service
interruption due to breakdowns.
• A fixed link would permit the use of a standard-width refuse vehicle on this route.  This
would improve the volume capacity and would reduce the risk of service interruption
due to breakdowns.
Waste Collection - Easdale:
• A fixed link would allow for easier transportation of the bins to Ellenabeich. This would
support a more regular pickup, reducing the demand for storage space and reducing
the pressure on public bins in Ellenabeich.
• A fixed link along with some improvements to the footpath network may also support
transport and recycling of heavier items such as white goods and building materials.
School transport:
• Luing – under the present arrangement, some pupils have to wait for the next
scheduled sailing. A fixed link would remove this constraint.
• Easdale – pupils sometimes must wait for space on the ferry, particularly during busier
summer months when school is still in session. A fixed link would remove this
constraint
• In both locations – inclement weather can prevent the ferries from sailing, resulting in
pupils being removed from school early to ensure they return home safely.  A fixed link
would reduce the frequency of these occurrences.
• In both locations - families incur additional ferry fares to attend parents’ evenings after
after-school events, and in some cases timetable restrictions may preclude attendance.
A fixed link would remove these costs/constraints.
27
Impacts/Implications
Council Services

Page 28

Caledonian Economics 
Social and health:
• Under the current arrangements, social and healthcare professionals are limited in their
ability to provide care on both islands outside the ferry operating hours. 
• A fixed link would provide unhindered access to and from both islands allowing the same
standard of at-home care as in Seil and the mainland.
Blue light services:
• At Easdale, an air ambulance is used for every medical emergency. The provision of a fixed
link would enable the Scottish Ambulance Service to triage and send local ambulances to
attend when it is more appropriate to do so.
• At Luing, ferry staff are kept on standby to operate the ferry should emergency access be
required. A fixed link would allow emergency vehicles to attend emergencies more quickly,
especially during bad weather.
28
Impacts/Implications
Social, Health and Emergency Services

Page 29

Caledonian Economics 
Other potential impacts:
• EV charging and utilities management – A fixed link would enable easier access for upgrading
and maintaining essential utilities.  This could include an upgrade to the electricity network
which may be required to expand EV charging provision.
• Plans for Quarry on Luing – LuingCommunity Trust plans to develop the quarry at Cullipool,
reviving small-scale slate production, protecting the island heritage and ensuring traditional
methods are passed on. A fixed link would support this by making it easier and less costly to
transport explosives, plant and equipment, and slate exports to and from the island.
• Housing – with a fixed link in place, the costs of transporting materials to Luing will be less and
should result in lower construction costs. Similarly, a fixed link may also attract new people to
the island, currently put off by the restrictions of a ferry connection.
• In Easdale, the transport of goods would be unrestricted, making it easier to receive deliveries
of cooking gas and fuel for power tools and similar needs.  It may also reduce the costs of trade
services such as electricians, plumbers, and other aspects of small-scale building projects.
• Tourism – A fixed link to both islands may enhance tourism opportunities by improving
connectivity, extending the tourist season, and providing opportunities for more unique
attractions, which would further enhance the visitor experience.
29
Impacts/Implications
Other Services

Page 30

Caledonian Economics 
Luing Conclusions:
• A fixed link (low-level bridge) is identified as the most cost-effective solution in the long term. 
A high-level bridge would provide navigability and resilience advantages.
• The community shows dissatisfaction with the current ferry service arrangement, although
there's a preference for improving the ferry service.
• A significant proportion of respondents see benefits in a fixed link. Few specific objections to
a fixed link were raised.
• Considering long-term sustainability and cost-effectiveness, the study concludes that a fixed
link is the preferred option from both technical and financial perspectives.
• It is recommended that these options be explored further, including detailed technical
appraisals, an updated STAG study, and relevant community engagement.
EasdaleConclusions:
• The financial analysis reveals that a fixed link is substantially less costly over the long term
than maintaining or upgrading the current ferry arrangement.
• There is resistance within the community to a fixed link due to ecological concerns and the
potential impact on the island's character.
• A fixed link would resolve many issues related to service accessibility and reliability.
• The community values the ferry service for its employment opportunities and the community
spirit it fosters.
• Despite the financial advantages, the community's preference is for improving the ferry
service rather than establishing a fixed link.
Impacts on Public Services in the Islands:
• a fixed link could improve waste collection, school transport, and emergency services by
providing unrestricted access and addressing the limitations of ferry services.
• a fixed link could extend the tourist season and offer opportunities for unique attractions and
new jobs.
In summary, from a financial and technical standpoint, a fixed link presents a more sustainable
and cost-effective long-term solution for both Luingand Easdale. However, community
sentiment, particularly in Easdale, leans towards improving the existing ferry services due to
concerns over the cultural and ecological impact of a fixed link
30
Final Comments

Page 31

Caledonian Economics 
Appendices
estimates/assumptions used in financial calculations
(provided by Argyll & Bute Council)
31

Page 32

32
Do minimum, continue to provide current service and maintain existing vessels– minor
improvements to waiting room/staff accommodation
Annual costs Capital costs Annual Income Life span
Staff costs £400,000.00 0
Annual vessel and
infrastructure maintenance £240,553.00 0 Annual - cost
varies
Reset gabion baskets with
imported fill * £100,000.00 0 10 years
Dredging of Easdale
Harbour £40,000.00 0 2 years
Additional refuse
collection costs £30,000.00 Annual
Income from ticket sales £45,870.00 Annual
Waiting room
improvements ** £50,000.00 0 25 years
Totals £690,553.00 £150,000.00 £45,870.00
Appendix 1.1
Easdale Options 1
Do Minimum – Cost Estimates
• Staff costs include, 4 x skipper and crew, Technical Officer Ferries 25%, Admin Officer 15%,
Marine Ops Manager 5% (includes pay, holiday pay, pension, training and Contracted staff
costs)
• Vessel and infrastructure costs based on average of costs incurred between FY's 2013 - 2023
includes for vessel maintenance, infrastructure maintenance, ticketing software, VHF
licensing, crew PPE, safety checks, audits and inspections, CCTV, fuel etc
• Income based on financial year 22/23 ticket sales
• Annual dredging based on actual costs for work carried out in 2022 and 2024 averaged
• * Gabions - based on estimate of 4,000 tonnes of granite material at £20
per tonne delivered and baskets refilled and rebuilt. Estimate 3-4 weeks   
work, 2 persons and excavator
• ** Small sum for waiting/staff room improvements - details not determined

Page 33

33
Replace current vessels with Carvoriatype vessel, minor waiting room improvements
Annual costs Capital costs Annual Income Life span
New vessel costs *** £270,000.00 0 30 years
Replacement vessel in year 30 £2,000,000.00 0
Amendments to existing pier to
suit new vessel and Equality Act
requirements ****
£1,500,000.00 0 40 years
Staff costs £400,000.00 0
Annual vessel and infrastructure
maintenance £240,553.00 0
Reset gabion baskets with
imported fill * £100,000.00 0 10 years
Dredging of Easdale Harbour £40,000.00 0 2 years
Income from ticket sales -£45,870.00
Waiting room improvements ** £50,000.00 0
Totals £680,553.00 £3,920,000.00 -£45,870.00
Appendix 1.2
Easdale Options 2
Landing Craft – Cost Estimates
• Staff costs, annual vessel and maintenance costs, dredging costs, gabions, waiting room
improvements and income as previous pages - does not allow for increased number of
crew to provide more sailings than current timetable allows.
• refuse collection costs removed - anticipated to be included in staff costs/time if this
option implemented.
• ***New vessel costs - assumption based on CMAL Carvoriavessel. Cost £200k in 2017
increased by inflation at 5% per year. New vessel anticipated life is 30 years. Alternative
vessels may cost more
• ****Existing slip improvement costs based on Iona slipway repairs at £650,000 for one
slipway - doubled for two plus round up to include for additional costs to get
plant/materials to Easdale

Page 34

34
Replace vessel as above and build 4No Breakwaters, relocate slipways, provide new waiting
facilities
Annual costs Capital costs Annual
Income Life span
New vessel costs £270,000.00 30 years
Replacement vessel in year
30 £2,000,000.00
Construction of new
breakwaters £30,777,000.00 100 years
Construct new slipways and
additional infrastructure
(waiting room/fuel
store/path network on
Easdale) £15,000,000.00 100 years
Staff costs £400,000.00
Annual vessel and
infrastructure maintenance £240,553.00
Income from ticket sales -£45,870.00
Totals £640,553.00 £48,047,000.00 -£45,870.00
Appendix 1.3
Easdale Options 3
Breakwater – Cost Estimates
• Staff costs, vessel and replacement vessel costs and annual income as described in previous
pages.
• Breakwater volumes based on cross section area of 35m wide by 11m high with 5m wide flat
top = 181m2. Length of breakwaters estimates as follows West (Seil) - 190m, West (Easdale) -
225m, East (Seil) - 160m, East (Easdale) - 105m - total volume 123,080m3
• Breakwater cost based on average of latest Iona Breakwater estimate at £225/m3 plus
Dunoon breakwater in 2020 at  £209/m3 - average cost used of £217/m3
• Anticipate constructing new slips to reduce commitment to dredge harbour (not A&BC
owned) Seil slipway approx80m long by 6m wide (480m2) Easdale slip 95m long x 6m wide
(570m2)
• New waiting room costs - £300,000 (based on Iona toilet block costs at £215,000) includes for
additional pipe network or septic tank, upgrade of path network and new exclusive use fuel
store at Ellenabeich.

Page 35

35
Install fixed link
Annual costs Capital costs Annual
Income Life span
Design and construction
costs £4,760,000.00 0
Land purchase £2,240,000.00 0
Annual inspection and
maintenance £5,000.00 0 125 years
Totals £5,000.00 £7,000,000.00 £0.00
Appendix 1.4
Easdale Options 4
Fixed Link – Cost Estimates
• Suggested design of short length of causeway to reduce span. Max span estimated at 70m
to maintain access via sea for smaller vessels - suggest steel truss or composite beams.
Bridge to be designed to suit crowd loading by pedestrians, cyclist and quad access. Max
4m wide with a parapet height of 1.5m, min design life of 125 years. Not suitable for
vehicular access larger than a quad bike or similar.
• Consider additional gate (perhaps coded?) on Easdale side for residents to manage night-
time access.
• On completion, structure will be added to existing bridge inspection and maintenance
regime. (Assumption max £5k per annum, likely less in first 10 years of operation)
• A&BC in-house design team may have availability to carry out design which may offer a
reduced cost.

Page 36

36
Possible additional costs that could supplement a fixed link provision
Annual
costs
Capital costs Annual
income
Life span
Local Ranger Service (continues
employment in area)
£70,000 0 0 As required
Provision of coin operated trolleys
and trolley store for transporting
heavy goods/luggage
£6,000 0 15 year
Provision of quad bike and training
for operatives to move refuse bins
£500/
year
£8,000 0 20 years
Improvements to bin storage area £10,000 0 20 years
Appendix 1.5
Easdale Options 5
Fixed Link – Additional support - Cost Estimates
• Local ranger service, providing local employment. Based on 2 x full time employees, with
duties to include managing visitor behaviour, littering, car parking etc where feasible Could
extended to wider community duties on Easdale, Seil and Luing.
• Trolleys based on SBS Trailers marina troller. 10 @ £400 plus sum to create two trolley
stores, one located near car park and one centrally on Easdale (Hall?)
• Quad bike costs based on a £5,000 for Honda quad bike and trailer plus £1,000 for storage
shed and £2,000 for sundry items such as training, PPE, etc. Annual £500 towards
servicing, fuel etc
• Sum for improvements, e.g. hardstanding, fencing, for bin storage area on Easdale

Page 37

37
Current service
Annual costs Capital costs Annual
Income Life span
Staff costs £450,000.00
Annual vessel and
infrastructure maintenance £205,000.00
5 years
remaining
Annual costs towards
bathymetric surveys and
dredging £10,000.00
Income from ticket sales -£190,336.00
Totals £665,000.00 £0.00 -£190,336.00
• Staff costs include, 4 x skipper and crew, Technical Officer Ferries 25%, Admin Officer
15%, Marine Ops Manager 5% (includes pay, holiday pay, pension, training and
Contracted staff costs)
• Vessel and infrastructure costs based on average of costs incurred between FY's 2013 -
2023 includes for vessel maintenance, infrastructure maintenance, ticketing software,
VHF licensing, crew PPE, safety checks, audits and inspections, CCTV, fuel etc.
• Income based on financial year 22/23 ticket sales.
• Annual dredging and survey costs based on percentage share of wider council
framework contract.
Appendix 2.1
Cuan Options
Current service assumptions

Page 38

38
Replace vessel with Eilean Dhuira, same timetable
Annual costs Capital costs Annual Income Life span
Staff costs £450,000.00 5 - 10 years
Annual vessel and
infrastructure
maintenance
£280,000.00
Annual costs towards
bathymetric surveys
and dredging
£10,000.00
Income from ticket
sales -£190,336.00
Minor amendments to
existing pier to suit new
vessel and Equality Act
requirements ****
£1,500,000.00 25 years
Totals £740,000.00 £1,500,000.00 £190,336.00
Appendix 2.2
Cuan Options Assumptions
Eilean Dhuira on current timetable
• Staff costs, dredging costs and income as previous page.
• Annual vessel and maintenance costs based on Eilean Dhuiracosts in current
location.
• Slip improvements required for Eilean Dhiurabased on Iona slipway repairs at
£650,000 for one slipway - doubled for two plus round up to include for additional
costs to get plant/materials to Luing.
• Eilean Dhuirahas 40 tonne capacity compared to Belnahuaat 15 tonnes. Will allow
larger vehicles access to the island to support community projects.
• Eilean Dhuirareplacement not anticipated in next 5 years, Eilean Dhuirawill have
limited life span at point of relocation.

Page 39

39
Eilean Dhuira with extended timetable – 2 additional crew members
Annual costs Capital costs Annual
Income Life span
Current staff costs £450,000.00 5 - 10 years
Staff costs * 2 £175,000.00
Annual vessel and infrastructure
maintenance £280,000.00
Annual costs towards bathymetric
surveys and dredging £10,000.00
Income from ticket sales -£190,336.00
Minor amendments to existing pier
to suit new vessel and Equality Act
requirements **** £1,500,000.00
Totals £915,000.00 £1,500,000.00 £190,336.00
• Staff, maintenance, vessel and infrastructure costs as Appendix 2.1.
• Assumed a minimum of 2 additional staff required to provide an extended timetable
beyond current provision
• Slip improvements required for Eilean Dhiurabased on Iona slipway repairs at £650,000 for
one slipway - doubled for two plus round up to include for additional costs to get
plant/materials to Luing.
• Income based on financial year 22/23 ticket sales. Potential additional income not
predicted.
Appendix 2.3
Cuan Options Assumptions
Eilean Dhuira with extended timetable

Page 40

40
Replace with hybrid vessel, new slipways, extended timetable (more staff)
Annual costs Capital costs Annual Income
Current staff costs £450,000.00
Staff costs * 2 £175,000.00
New vessel £17,220,000.00
New slipways and waiting room/crew
room facilities at both sides £23,000,000.00
Annual vessel and infrastructure
maintenance £10,000.00
Annual costs towards bathymetric
surveys and dredging £10,000.00
Income from ticket sales £190,336.00
Totals £645,000.00 £40,220,000.00 £190,336.00
• Vessel costs based on MV Catriona, constructed in 2015. Unlikely this specific class is
suitable for the route but provides a reasonable cost comparison for the construction of
a hybrid vessel.
• At least a minimum of 2 additional crew members required to operate a new vessel.
• This option would require construction of new slipways, overnight berth and new waiting
facilities. This is likely to require additional land purchase to complete.
• This would present an opportunity to review fares and increase to reflect expenditure
and increase capacity on the route. Income left at current rates for this report.
Appendix 2.4
Cuan Options Assumptions
New Hybrid Vessel

Page 41

41
Design and Build Fixed Link (High/Low level costs)
Annual costs Capital costs Annual
Income Life span
Design and construction costs
- low level £23,500,000.00 125 years
Design and construction costs
- high level £43,000,000.00 125 years
Annual inspection and
maintenance £5,000.00
2 x staff costs - options are
possible ranger service for
area if high level options
selected or operators for low
level swing bridge
£70,000 as required
Low Level Total £75,000 £23,500,000 125 years
High Level Total £5,000 £43,000,000 125 years
Appendix 2.5
Cuan Options Assumptions
Fixed Link
• High level bridge is anticipated to require meterage of new road on both approaches.
New road would be twin track to provide optimum forward sight distance on
approaches.
• Low level bridge is anticipated to require a section of the bridge that will open to sea
traffic. This will require a minimum of 2No staff members plus relief.
• Any bridge would be designed to current DMRB standard for all classification of
vehicles and be added to the Council’s bridge inspection list.
• It should be noted that the existing roads in this area are reasonably weak and any
solution that would likely increase the volume or load capacity of vehicles on the
Islands of Luingand Seil may result in a need to invest further fund into the local road
network to support usage.
• This includes for both a fixed link or any replacement vessel with a great tonnage or
capacity to carry more vehicles than at present.

Page 42

42
Option
1 2 3 4 5
Belnahua
then low
bridge
Belnahua
then E.D.
same TT
then low
bridge
Belnahua
then E.D
+TT then
low bridge
Belnahua
then high
bridge
Belnahua
then Hybrid
Belnahua final service year 5 5 5 5 5
Eilean Dhuira first service year 0 6 6 0 0
Eilean Dhuira final service year 0 11 11 0 0
Hybrid Vessel Life Expectancy 0 0 0 0 30
Hybrid first service year 0 0 0 0 6
Hybrid  final service year 0 0 0 0 36
Replacement Hybrid first service
year 0 0 0 0 37
Replacement Hybrid final service
year 0 0 0 0 67
Fixed link open (year 0 = never) 6 12 12 6 0
Select High Level (1) or Low Level
(0) 0 0 0 1 1
Select Eilean Dhuira Timetable
Current (1) or Extended (0) 1 1 0 1 1
Appendix 2.6
Cuan Options Assumptions
Possible timings of option
* Indicates year i.e. Year1, Year 6 etc. Year 0 = never