A85 A828 (OLI)
3 Month "Lookahead"
Programme
North West Bridges/Structures - Please note that none of these are confirmed and most are likely to change, potential dates only
Scheme Name/location Brief Description/TTM Proposed Start Proposed End
A85 670 W87 Esplanade Sea Wall Scour Repair Temporary traffic lights 01-Mar-25 31-Mar-25
A85 480 Orchy Drainage Improvement Temporary traffic lights 01-Apr-25 30-Apr-25
A828 50 Barcaldine Gardens Parapet Replacement Temporary traffic lights 01-Apr-25 30-Apr-25
Scheme Name Brief Description/TTM Proposed Start Proposed End
A85 Stronmilchan Junction Resurfacing (non-structural inlay/overlay) 05-Feb-25 06-Feb-25
A828 Ledaig (CS228_2022) Resurfacing (non-structural inlay/overlay) TBC TBC
A85 Loch Awe East Resurfacing (non-structural inlay/overlay) 09-Feb-25 15-Feb-25
A828 Beinn Sgluish Resurfacing (non-structural inlay/overlay) 19-Jan-25 05-Feb-25
A85 Dunollie Road (Oban) Resurfacing (non-structural inlay/overlay) 16-Mar-25 21-Mar-25
A85 West of Lix Toll Resurfacing (non-structural inlay/overlay) 31-Mar-25 06-Apr-25
A85 Cruachan Power Station Resurfacing (non-structural inlay/overlay) 03-Feb-25 05-Feb-25
A85 Loch Lubhair Resurfacing (non-structural inlay/overlay) 31-Mar-25 08-Apr-25
A828 South of Connel Bridge Resurfacing (non-structural inlay/overlay) 30-Mar-25 03-Apr-25
North West - Minor Improvement schemes, potential dates
Scheme Name Brief Description/TTM Proposed Start Proposed End
A83 OMR Medium Term Solution
Completion of Old Military road
Improvements, Glen Croe - No TM as off
A83 24-Feb-25 28-Feb-25
A83 RaBT Ph 3 A B Slip
Installation of debris flow barrier - TM
covered by Operational managemnt
above 10-Feb-25 10-Apr-25
North West Planned Maintenance - surfacing.  Again proposed dates
Version: 1.0 05/02/2025