Democracy Spraffa

21-1520-PP Supplementary Report- Lyon Road DL130123 - AM reviewed 17 Jan

Renfrewshire Council · 24 January 2023
Back to Planning and Climate Change Policy Board — 24 January 2023 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

Renfrewshire Council Planning and Climate Change Policy Board Page 1
Planning Application: Supplementary Report
Reference No.    21/1520/PP       
Agenda Item
KEY INFORMATION 
Ward: (10) Houston,
Crosslee and Linwood 
Applicant:
SSH Recycling Ltd 
Registered: 
10.09.2021 
RECOMMENDATION 
Refuse 
Report by Head of Economy & Development 
PROSPECTIVE PROPOSAL: 
LOCATION: 
APPLICATION FOR: Full Planning Permission 
This supplementary report should be read together with
the original report of handling considered by the
Planning and Climate Change Policy Board on 1st
November 2022. 
BACKGROUND 
The Planning and Climate Change Policy Board at its
meeting on 1st November 2022 considered the attached
report of handling and decided to continue the consideration
of the report to allow a site visit to take place and to review
correspondence related to the flood risk matters associated
with the site.  The detailed assessment of the proposed
development is included in the attached report of handling.   
SITE VISIT 
A site visit took place on the 11th January 2023 and those
members attending viewed the application site and its
surroundings. 
The site visit was conducted in accordance with the Protocol
for Site Visits (May 2018) and members attending did not
discuss the merits of the proposal. 
FLOODING CORRESPONDENCE 
All correspondence from SEPA, the applicant, and Dougal
Bailie Associates relating specifically to the flood risk matters
associated with the site has been made available for
members to view. 
Alasdair Morrison
Head of Economy &
Development

Page 2

Renfrewshire Council Planning and Climate Change Policy Board Page 2
Reason for Decision 
1. The proposed development is at a location susceptible to flooding and will increase
the risk of flooding elsewhere. It does not therefore align with the precautionary and
avoidance principles advocated by the sustainable flood risk management framework
set out in Scottish Planning Policy and is contrary to Policy I3 of the Adopted Local
Development Plan and the associated New Development Supplementary Guidance
on flooding and drainage.     
Local Government (Access to Information) Act 1985 - Background Papers
For further information or to inspect any letters of objection and other background papers,
please contact James Weir on 07483370666

Page 3

Alasdair Morrison
Head of Economy &
Development  
IDENTIFIED KEY ISSUES 
 The application site is identified by Policy E1
‘Renfrewshire’s Economic Investment Locations’ of the
Adopted Renfrewshire Local Development Plan (2021). 
 No representations have been received 
 There has been an objection from SEPA. 
 The proposal does not fully accord with Policy I3 of the
Adopted Renfrewshire Local Development Plan (2021)
on Flooding and Drainage.
Planning Application: Report of Handling
Reference No. 21/1520/PP 
Report by Head of Economy & Development 
PROSPECTIVE PROPOSAL: Erection of Waste Tyre and
Rubber Recycling and Processing Plant (Use Class 5,
General Industry) with ancillary office and staff welfare
facilities and associated access, parking, landscape, 
and infrastructure proposals. 
LOCATION: 2 Lyon Road, Linwood, Paisley, PA3 3BQ 
APPLICATION FOR: Full Planning Permission 
© Crown Copyright and database right 2021. All rights reserved. Ordnance Survey Licence number 100023417. 
Renfrewshire Council Planning and Climate Change Policy Board Page 1 
Ward: (10) Houston,
Crosslee and Linwood 
Applicant:
SSH Recycling Ltd 
Registered:
10.09.2021
KEY INFORMATION 
RECOMMENDATION 
Refuse

Page 4

Renfrewshire Council Planning and Climate Change Policy Board
Page 2 
REPORT OF HANDLING FOR APPLICATION 21/1520/PP 
SITE ADDRESS 2 Lyon Road, Linwood, Paisley, PA3 3BQ
PROPOSAL Erection of Waste Tyre and Rubber Recycling and Processing Plant
(Use Class 5, General Industry) with ancillary office and staff welfare
facilities and associated access, parking, landscape, and
infrastructure proposals.
RECOMMENDATION Refuse 
PROPOSALS This application seeks planning permission for the erection of a waste
tyre and rubber recycling and processing plant with ancillary facilities,
parking and infrastructure on a part vacant site at Lyon Road,
Linwood. 
The application site extends to 4.469 hectares in area. It is bound by
the White Cart Water and the A737 to the north and west, and a mix
of industrial and warehouse uses to the south and east. There is an
existing manufacturing building in the northeast corner of the site. The
remainder of the site is vacant having previously been used as a
sewage treatment works. In terms of topography, the existing
manufacturing building sits on higher ground. Most of the site to the
west of this is on lower ground adjacent to the White Cart. 
For the purposes of the development the existing manufacturing
building will be retained and incorporated as part of the proposed
recycling plant. Three additional large warehouse style buildings,
comprising a total of 8,577 square metres, are proposed on the
western section of the site. These will be complemented by two
smaller buildings housing staff welfare and office facilities with
associated car parking, road infrastructure and hard standing. Access
to the site is via Lyon Road and Burnbrae Drive. 
The proposed use will involve the processing of approx. 100,000
tonnes of loose tyres into a mix of tyre shred, wires, and fabric. The
tyre shred will be further processed into crumbs and rubber products
for onward distribution.
SITE HISTORY Application No: 21/1148/PP
Description: engineering works to stabilise river- bank & realignment
of pedestrian path. including re-positioning 3m high palisade fencing
to site boundary.
Decision: Grant subject to conditions 
Application No: 21/0114/EO
Description: Request for screening opinion.

Page 5

Renfrewshire Council Planning and Climate Change Policy Board
Page 3 
Decision: Environmental Assessment not Required. 
Application No: 21/0051/NO
Description: Erection of waste tyre processing and recycling plant with
associated access, parking, and infrastructure proposals.
Decision: Accepted 
Application No: 21/0044/PP
Description: Erection of 3m high palisade security fencing around the
site boundary.
Decision: Not yet determined. 
Application No: 19/0674/PP
Description: Erection of two storey temporary office, canopy to rear of
existing warehouse, single storey microturbine, installation of five
roller shutters and external alterations
Decision: Grant subject to conditions. 
Application No: 17/0844/PP
Description: Erection of single storey industrial building for use as an
organic waste transfer station.
Decision: Grant subject to conditions. 
Application No: 12/0391/PP
Description: Formation of temporary concrete composting pad with
associated access road.
Decision: Grant subject to conditions. 
Application No: 08/0658/PP
Description: Creation of anaerobic digestion facility to treat local
authority waste streams and food waste from commercial and
industrial facilities.
Decision: Grant subject to conditions. 
Application No: 07/0037/PP
Description: Creation of a composting facility using local authority
green waste and formation of hardstanding and weighbridge.
Decision: Grant subject to conditions. 
Application No: 05/0268/PP
Description: Erection of a 2.4m high galvanised palisade fence.
Decision: Grant subject to conditions. 
Application No: 03/0041/PP
Description: Erection of control building and formation of access road
at wastewater pumping station.
Decision: Grant subject to conditions.
CONSULTATIONS SEPA – Object in principle to the development on the grounds that it

Page 6

Renfrewshire Council Planning and Climate Change Policy Board
Page 4 
is contrary to the principles of sustainable flood management and the
requirements of SPP. 
Chief Executive’s Service (Roads Development) – No objection
subject to conditions regarding active travel links to the site. 
Communities & Housing Services (Environmental Protection Team) –
No objections subject to conditions relating to contaminated land and
noise. Air Quality Assessment has been approved. 
Transport Scotland – No objections. 
Scottish Water – There is capacity to serve the development with
respect to water supply and foul water disposal. 
NATS – No objections. 
Coal Authority – No objections. 
Glasgow Airport Safeguarding – No objection subject to conditions
regarding submission of a Bird Hazard Management Plan and further
details of all soft and water landscaping.
REPRESENTATIONS None received.
DEVELOPMENT PLAN
POLICIES
Clydeplan Strategic Development Plan (2017)
Policy 11 – Planning for Zero Waste
Renfrewshire Local Development Plan (2021)
Policy E1 – Economic Investment Locations
Policy I1 – Connecting Places
Policy I3 – Flooding and Drainage
Policy I5 – Waste Management
Policy ENV2 – Natural Heritage
Policy ENV4 – The Water Environment
Policy ENV5 – Air Quality 
New Development Supplementary Guidance (2021) 
Delivering the Economic Strategy
Delivering the Infrastructure Strategy
Delivering the Environment Strategy 
Material considerations 
Scottish Planning Policy
Scotland’s Zero Waste Plan

Page 7

Renfrewshire Council Planning and Climate Change Policy Board
Page 5 
Planning legislation requires that planning decisions are made in
accordance with the Development Plan unless material considerations
indicate otherwise. In this case the proposal shall require to be
assessed against the policies and guidance set out above, the history
of the site, the comments of the consultees and any objections
received.
PLANNING
ASSESSMENT
The proposal is classed as a strategic development by virtue of the
floor space proposed and the site area. It must therefore be assessed
against Clydeplan. 
Policy 11 states that development proposals for waste management
facilities will generally be acceptable (subject to local considerations)
in the locations listed in the policy. 
The application site comprises of derelict land that has been
designated for industrial uses. It is therefore in an appropriate location
with regard to the requirements of policy 11 and is compliant with
Clydeplan. 
Within the Local Development Plan the site is designated as a
development opportunity site within an economic investment location
as specified within Policy E1. 
Policy E1 states that class 5 uses will be promoted within economic
investment locations. The proposed development in this regard is
therefore considered to comply with Policy E1 in principle as it
comprises of a class 5 use. 
Regarding the economic development criteria, the development will
facilitate the regeneration of vacant previously used land. It will result
in employment creation and bring economic benefit. It is also noted
that other waste management uses are located within the vicinity of
the site, and the development will complement this cluster of
economic uses. 
The Roads Development team have offered no objection to the
development and have advised that trip generation can be
accommodated within the local road network. However, concerns are
raised over the suitability of active travel routes to the site. 
The application site is not within a designated area with respect to
natural heritage, and it is not anticipated that there will be a significant
adverse impact on the natural environment. 
The development is of a scale, design and finish that is compatible
with the character of the area. 
The application site is within the Burnbrae Local Industrial Area. The
role of this area is as a locally important industrial area which includes
a strategic freight transport hub.

Page 8

Renfrewshire Council Planning and Climate Change Policy Board
Page 6 
The proposed class 5 use will support the role and function of this
economic investment location and is compatible with the character of
the surrounding area. The development will not have a significant
impact upon existing uses in the area. 
In view of the above, I am satisfied that the development complies
with Policy E1 
In addition to the employment and brownfield regeneration benefits
noted above, the proposed development will also contribute to
delivery of Scotland’s Zero Waste Plan. The planning statement which
accompanies the application states that the site would have capacity
to process 100,000 tonnes of waste tyres. 
Policy I5 states that development proposals for waste management
will be supported if they meet the listed criteria. Each of the criteria will
be considered in turn. 
The site has a good level of accessibility, and the development does
not have an adverse impact on the existing road network. 
The development will be able to co-exist with surrounding existing and
allocated land uses. 
The benefits of the proposal with respect to processing of waste
materials are noted. The development will also facilitate the re-use of
a sustainably located vacant brownfield site and will create additional
jobs within an area allocated for industrial uses. There are positive
environmental, social, and economic benefits associated with the
development. 
The development is located on land adjacent to other waste
management operations and is compatible with the Burnbrae
economic investment location. Site operations will not have a
detrimental impact on other users at this location. 
There are no significant impacts with respect to built heritage or the
natural environment. 
There is no requirement for restoration or after-use proposals. 
In view of the above, the development is considered to comply with
Policy I5. 
With respect to Policy I3, it is noted that SEPA have objected to the
development in principle on the grounds that it is contrary to
sustainable flood risk management practices and the requirements of
Scottish Planning Policy (SPP). 
Policy I3 states that a precautionary approach will be adopted to the
reduction of flood risk in line with the framework set out in SPP. New

Page 9

Renfrewshire Council Planning and Climate Change Policy Board
Page 7 
developments require to avoid areas susceptible to flooding. 
It is accepted that the precautionary approach would advocate
avoidance of development at this location given the flood risk. While
the site has been developed before, the previous use as a sewage
treatment works would be compatible with the site location in terms of
land use vulnerability. The proposed development has a different
character in terms of land use vulnerability. 
The developer has submitted a flood risk assessment which identifies
measures that would mitigate flood risk at the site. These measures
include all staff welfare and office facilities being elevated above the
predicted peak flood risk level. Within the processing buildings all
equipment will be on raised decks to protect it from flooding. The
buildings will also be designed with large openings on all sides. These
openings will allow flood water to pass through the building during
storm events. Further measures include a bespoke suds drainage
system, and installation of a flood monitoring alarm system. 
The Council has sought an independent review of the flood risk
analysis undertaken by the applicant. While the mitigation measures
proposed by the applicant are acknowledged, it is noted that the
development will nevertheless result in an increased flood risk
upstream including to an allocated housing land supply site. There is
also a marginal increased flood risk downstream. 
Additionally, the applicant sought to demonstrate that the
development would result in betterment to existing flood risk within the
surrounding economic investment location. However, the analysis
shows that tolerances within the modelling mean that this betterment
may not be realised. 
In view of the above, it is concluded that development of the site
would be contrary to the precautionary approach advocated by policy
I3. Despite the mitigations proposed the development will increase
flood risk upstream and downstream. Betterment within the immediate
locality may also not be realised. The development is therefore
considered to be contrary to Policy I3. 
Policy I1 states that all development proposals require to ensure
appropriate provision and accessibility including connection to active
travel and public transport networks. 
The site is accessibly by all transport modes. It is also near the
Burnbrae strategic freight hub which provides opportunities for inter
modal freight transfer. 
The roads development officer has offered no objection to the
development subject to conditions regarding active travel links to the
site. Should planning consent be granted, it is recommended that a
condition be applied to ensure that active travel links to the site are
upgraded.

Page 10

Renfrewshire Council Planning and Climate Change Policy Board
Page 8 
The development is considered to comply with Policy I1. 
Regarding policies ENV 2, 4 and 5, the Ecological Appraisal submitted
with the application states that the site is of low ecological value and
there are no ecological constraints. The site predominantly comprises
of hard standing. Woodland habitat on the northern side of the Black
Cary Water will not be impacted by the works. The development will
not have a significant detrimental impact on natural heritage assets in
this regard. 
The Ecological Appraisal goes onto outline ecological enhancement
opportunities at the site. These range from clearance of invasive
species to improvement of habitat along the banks of the Black Cart
Water. Should planning consent be granted, it is recommended that a
condition be applied to ensure the development is undertaken in
accordance with the recommendations within the ecological appraisal. 
To protect the water environment during the construction phase, the
developer will be required to submit a construction management and
pollution prevention plan for approval. 
Finally, regarding policy ENV5 the air quality assessment submitted in
support of the application has been approved. 
In view of the above I would consider the development to comply with
policies ENV2, 4 and 5. 
In conclusion it is noted that the proposed development would be
compatible with the economic investment designation at this location.
The development would regenerate a brownfield site, result in
employment creation, and contribute to zero waste goals. 
However, the site is at risk of flooding, and despite mitigation it is
noted that the development would increase the risk of flooding
elsewhere. The development is therefore contrary to the precautionary
and avoidance principles set out within SPP and Policy I3 and has
attracted an objection from SEPA on this basis. Flood risk is
considered to take precedence in terms of the overall assessment of
the development, and it is not considered that the development can be
supported on this basis.
RECOMMENDATION Refuse 
Reason for Decision 
1. The proposed development is at a location susceptible to flooding and will
increase the risk of flooding elsewhere. It does not therefore align with the
precautionary and avoidance principles advocated by the sustainable flood risk
management framework set out in Scottish Planning Policy, and is contrary to

Page 11

Renfrewshire Council Planning and Climate Change Policy Board
Page 9 
Policy I3 of the Adopted Local Development Plan, the associated New
Development Supplementary Guidance on flooding and drainage. 
Local Government (Access to Information) Act 1985 - Background Papers
For further information or to inspect any letters of objection and other background
papers, please contact Gwen McCracken on 07483419705.